SBP COMMERCIAL PVT. LTD.

Concrete Order Qty

Date Of Order 5/10/2017 Grade M-25 Location B2

STITCH SLAB AT B2 Level


S. No. PARTICULARS NOS. Length Breath Height Qty. REMARKS
1 STITCH SLAB AT B2 Level 1.0 27.3 17.0 0.1 45.5 TOTAL AREA
2 STITCH SLAB AT B2 Level -1.0 40.0 0.5 0.1 -2.2 Deduct for Drains
3 STITCH SLAB AT B2 Level -1.0 1.5 1.5 0.1 -0.2 Deduct for Sump
4 STITCH SLAB AT B2 Level -1.0 2.0 2.0 0.1 -0.4 Deduct for Sump

GRAND TOTAL 43
ORDERED QTY 43
SBP COMMERCIAL PVT. LTD.
Concrete Order Qty

Date Of Order 5/15/2017 Grade M-25 Location

Raft of STP
S. No. PARTICULARS NOS. Length Breath Height
1 Raft of STP 1 10 5.4 0.4

GRAND TOTAL
ORDERED QTY
D.
Qty

STP TANK (0.00-4.65 m)

Qty. REMARKS
21.6 Stage one of raft
4.82
22 4.65
22
SBP COMMERCIAL PVT. LTD.
Concrete Order Qty

Date Of Order 5/18/2017 Grade M-25 Location

Raft of STP
S. No. PARTICULARS NOS. Length Breath Height
1 Raft of STP 1 7 5.4 0.4
2 Outer Wall Of Stp 1 20 0.33 4.1

GRAND TOTAL
ORDERED QTY
D.
Qty

STP TANK ( 0.00-4.65 m)

Qty. REMARKS
15.12 Stage 2 of raft
27.06 Stage1 of Walls 4.82
4.65
42
42
SBP COMMERCIAL PVT. LTD.
Concrete Order Qty

Date Of Order 5/22/2017 Grade M-25 Location

Raft of STP
S. No. PARTICULARS NOS. Length Breath Height
1 Outer Wall Of Stp 1 20 0.33 4.1
1 inner Wall Of Stp 1 4.27 0.33 3.5

GRAND TOTAL
ORDERED QTY
D.
Qty

STP TANK ( 0.00-4.65 m)

Qty. REMARKS
27 Stage 2 of Walls 4.82
4.9 Stage 1 of Walls
4.65
32 39.9
32
SBP COMMERCIAL PVT. LTD.
Concrete Order Qty

Date Of Order 5/28/2017 Grade M-25 Location

Raft of STP
S. No. PARTICULARS NOS. Length Breath Height
1 inner Wall Of Stp 7 4.27 0.23 2.55

GRAND TOTAL
ORDERED QTY
D.
Qty

STP TANK ( 0.00-4.65 m)

Qty. REMARKS
17.5 Stage 1 of Walls
#REF!
18 39.9
18
SBP COMMERCIAL PVT. LTD.
Concrete Order Qty

Date Of Order 5/28/2017 Grade M-25 Location

Raft of STP
S. No. PARTICULARS NOS. Length Breath Height
1 STP Tank Roof 1 15.02 4.93 0.2

GRAND TOTAL
ORDERED QTY
D.
Qty

STP TANK ( 0.00-4.65 m)

Qty. REMARKS
14.8
#REF!
15 39.9
15