INSPECTION AND TEST PLAN FOR WELDED PIPE JOINT OF HVAC PIPING CONSTRUCTION
DEVELOPMENT COMPANY
L.L.C

Contract No.: Contract Title: ITP Sequence No. Rev. No.: 00

2777 QF OFFSITE WAREHOUSE AND DISTRIBUTION CENTRE 2777-ITP-05-00006

Discipline: References
page 1
HVAC ASME SECTION IX

Act. Verifying Inspection


Activity Controlling Document Acceptance Criteria Frequency
No. Documents CDC APM/LB

A Submittals

A2 Inspection and Test Plan. 2777-ITP-08-00006-0 M/s ASTAD / L/B (STATUS 1 & 2) to proceed the work pre commencement of site work 2777-ITP-08-00006 H R

A3 Method Statement. 2777-MS-08-00006-0 M/s ASTAD / L/B (STATUS 1 & 2) to proceed the work pre commencement of site work 2777-MS-08-00006 H R

after each welding works is inspected


Engineer's acceptance of the Contractor's finished butt weld & fillet
Weld Examination and and tested by non-destructive Request for Inspection / Testing
A4 2777-MS-08-00006-0 joints in accordance to approved WPS (Mock-up welded joint H R
Inspection Reports examination methods (Liquid Penetrant Form (RFIT)
approval)
Test) - as deemed necessary

Welding Procedure Specifications


Fabrication and Examination M/s ASTAD / L/B (STATUS 1 & 2) to proceed the work ; Compliance
A5 2777-MS-08-00006-0 before welding work commence (WPS) & Procedure Qualification H R
Procedures to ASME Section IX for welding procedures
Record (PQR)

A6 Qualification Certificates 2777-MS-08-00006-0 In accordance to ASME Section IX. pre commencement of site work Welders Certificates H R

Striked Not Included


B QUALITY ASSURANCE

Welding Electrodes and Filler Material Delivery To Site Form


B1 2777-MS-08-00006-0 Compliance to AWS A / SFA 5.1 before procurement of material H R
Metals (MDS)

Legend :
a. Witness Point (W) - The Contractor shall advise the Site Engineer, a reasonable time - minimum of 24 hours, in advance of the operation to ensure the Site Engineer may be able to attend the required witness point. The Contractor may proceed
with work beyond such witness points in case the Site Engineer / Resident Engineer (RE) can not turn up for the inspection at the specified time.
b. Hold Point (H) - The Contractor is shall advise the Site Engineer/Resident Engineer, a reasonable time minimum of 24 hours, in advance of the operation that an item must be visually examined, tested, or measured by the Site Engineer to verify
conformance to quality requirements. The Contractor shall not proceed with the work beyond such hold points, except by written agreement from the responsible Resident Engineer.
c. Surveillance (S) - In process monitoring of Contractors activities to the degree necessary that confidence is gained that the work processes /methods are in compliance with established criteria.
d. Review (R) - Reviews of the Inspection and Testing records recorded by the Contractor and by the Engineer for correctness and completeness.