SUBMISSION

(Pre-KM)

TNB SKMM
(Pre-consult) (Pre-consult)

Documents for TNB:-


1) Standard cover letter Network facilities Microwave clearance
2) 2 sets of Map A, B & C Tapping-point
provider (NFP) (if building > 5 storey)
3) 2 sets of key plan, location plan &
site plan drawing showing:
a) Location of TNB sub-station Documents for SKMM:- Documents for all 9 NFP:-
b) GPS coordinate of project site 1) Standard cover letter 1) Standard cover letter
2) 3 sets of key plan, location plan & 2) 1 set of key plan, location plan &
site plan drawing showing site plan drawing showing
Submit to Bahagian Pembahagian TNB GPS coordinate of project site GPS coordinate of 4 corners of
the building
3) 1 set of elevation drawing
Input from TNB:- Submit to SKMM
No obstruction/supporting letter Documents for selected NFP:-
1) Standard cover letter Submit to NFP
Input from SKMM:- 2) 3 sets of key plan, location plan &
1) Available NFP site plan drawing showing:
2) GPS coordinate for tapping-point a) Telecommunication infrastructure
b) GPS coordinate of project site Input from NFP:- No input from NFP
3) 1 CD copy of the above drawings Microwave clearance letter (within 14 days)

Submit to selected NFP Documents for SKMM:- Documents for SKMM:-


Microwave clearance letter Acknowledgement letter
issued by NFP submitted to 9 NFP
Input from selected NFP:-
1) No obstruction/supporting letter
2) Surat Perakuan Persetujuan Submit to SKMM

Input from SKMM:-


Microwave clearance letter

Documents for OSC/Planner:- Documents for OSC/Planner:- Documents for OSC/Planner:- Documents for OSC/Planner:-
Letter issued by TNB 1) Letter issued by SKMM Letter issued by selected NFP Microwave clearance letter issued by SKMM
2) Surat Perakuan PSP

Submit to OSC/Planner