NARMADA OFFSHORE CON

narmada
PROJECT SCHEDULE
PROJECT: REPLACEMENT OF PIPE IN MPPL
Mechanical Scope of
S.No. Activity Description Gang No. Work Start Date

1 Marking of Defective Pipe Locations 1&2 NOCPL 06.05.2017

2 Excavation 1&2 NOCPL 06.05.2017

3 Identification of Defective Pipe 1&2 HPCL 07.05.2017

4 Shifting of Air Compressor to Khopoli Bosster Station 3 NOCPL 09.05.2017

Dewatering of Pipeline by Air Pigging, from Khopoli to Vashi


5 4 NOCPL 10.05.2017
Terminal

6 Removal of defective pipe from existing pipeline 1&2 NOCPL 11.05.2017

7 Lowering of Pipe 1&2 NOCPL 11.05.2017

8 Welding of Pipe with existing Pipeline 1&2 NOCPL 11.05.2017

9 Radiography Testing of Joints 1&2 NOCPL 11.05.2017

10 Weld repair (If Required) 1&2 NOCPL 12.05.2017

11 Radiography Testing of Repaired Joints 1&2 NOCPL 12.05.2017


12 Joint Coating 5 NOCPL 12.05.2017

13 Post Padding 6 NOCPL 13.05.2017

14 Backfilling 7 NOCPL 13.05.2017

Note:
Simulataneously all activities will be carried out at both locations. (Except Joint Coating).
RMADA OFFSHORE CONSTRUCTIONS PRIVATE LIMITED

ROJECT SCHEDULE
PLACEMENT OF PIPE IN MPPL
Remarks
End Date

06.05.2017 Assuming Shutdown starting date as 10.05.2017

07.05.2017

07.05.2017

09.05.2017

By 10th May 2017 morning Pipeline Shall be handed over to


11.05.2017
NOCPL to start De-watering activities.

11.05.2017

11.05.2017

11.05.2017

11.05.2017

12.05.2017

12.05.2017
12.05.2017

13.05.2017

13.05.2017

s. (Except Joint Coating).