You are on page 1of 4

Project Name

CONTRACTOR CLIENT

DAILY REPORT
Weather: Wind: Temperature:
Clear Still 00 - 300C
Cloudy Moderate 300 - 400C
Fog High 400 - 500C
Dusty 500C +

Description of Work:
1

Manpower
Sl No. Description No. Sl No. Description
1 Project Manager 1 13 Surveyor
2 Project Coordinator 1 14 Chainman
3 Site Manager 1 15 Lab Technician
4 QA / QC Engineer 1 16 Lab Assistant
5 Planning Engineer 1 17 Safety Engineer
6 Site Engineer 1 18 Safety Officer
7 Secretary 1 19 Store Keeper
8 Quantity Surveyor 1 20 Time Keeper
9 Assistant QS 1 21 Office Boy
10 Draughtsman 3 22 Watchman
11 Chief Surveyor 1 23 General Foreman
12 Rackman 4 24 Gaugeman
Plant / Machinery (WG - Working; IL - Idle; BD - Break Down)
Sl No. Description No. WG IL BD
1 DC Pick-up 4 4 0 0
2 Long Chase Pick up 0 0 0 0
3 Bus 1 1 0 0
4 Dozer 2 2 0 0
5 Excavator 1 1 0 0
6 Shovel 3 3 0 0
7 JCB 2 2 0 0
8 Grader 2 2 0 0
9 Steel Roller 3 2 0 1
10 PTR 7 6 0 1
Three Days Look Ahead
Sl No. Description Day 1

3
4
5

For Contractor:

Planning Engineer
Project Name

CLIENT CONSULTANT

DAILY REPORT
Temperature: Humidity
Dry Date : 20/11/13
Moderate
Humid Day: WED
Site Timing : 6:30AM to 5:30PM

No. Sl No. Description No. Total


4 25 Foreman 3 Manpower
8 26 Charge hand 2
0 27 LV / HV Driver 23
170
2 28 Operators 28
1 29 Mason 8
0 30 Carpenter 7 Plant / Machinery
1 31 Electrician 2 Total - 52
1 32 Grade Checker 2
2 33 Pipe Fitter 1 WG - 50
4 34 Steel Fixer 2 IL - 0
1 35 Labour 47 BD - 2
4 36

Sl No. Description No. WG IL BD


11 Bob Cat 1 1 0 0
12 Six Wheel / Trailor 7 7 0 0
13 Dumpers 0 0 0 0
14 Water Tankers 5 5 0 0
15 Plate Compactor 2 2 0 0
16 Hand Roller 2 2 0 0
17 Generators 5 5 0 0
18 Paver 2 2 0 0
19 Baby Roller 1 1 0 0
20 DDR 2 2 0 0

Day 2 Day 3

Consultant

ARE Road Works