Plan for Wiper Trip.

Before reach WL depth raise FR to 3.7 M3/min in case of overflowing.


Once reach KD of 800m, sweep 17-1/2 hole with 5m3 HVP, circ. Hole till
shakers clean.
Record P/U,S/O WT and rotation W/O pumping.
Drop single- shot survey tool.
Wiper trip from bottom to 20"casing shoe smoothly (work on O/P more than
10T till normal WT). reaming parameters: WOB:2-3 & RPM:60-80 & FR: 2.7-3
Circulate to clean bit and Stab.
Check for any over flow to flow line and shakers, be ready.
RIH to bottom with wash down last joint.
Perform bit service.
Resume drilling 17-1/2 hole to 1050m.
Keep back ream and ream down twice after eack KD.