You are on page 1of 30

SUMMER INTERNSHIP REPORT

7th June 2016 to 7th July 2016


(4 weeks)

Department of Civil Engineering,

SHANTI NIKETAN GROUP OF INSTITUTIONS,


MEERUT

Submitted To: Submitted by:


Mr. Nitin Vivek kumar
(H.O.D) Civil Engineering Roll no.:- 1451400938 (4 year B.Tech)
th

Shivani
Roll no.:- 1451400933 (4 year B.Tech)
th

Preeti
Roll no.:- 1451400921 (4 year B.Tech)
th
ACKNOWLEDGEMENT

With the deepest gratitude, I would like to thank AMRAPALI GROUP for
having given me this opportunity to undertake this summer training at their
prestigious project.
I would like to thank Mr. Rakesh Kumar Singh, Project Manager for bestowing
upon me this great learning experience.
I would like to convey my gratitude to Mr. Vivek Kumar, Assistant Engineer
and Mr. Shyam Srivastava, Assistant Engineer who guided and encouraged me
throughout the duration of my summer training and imparted in depth knowledge
regarding the project.
I extend my heartfelt and sincere gratitude to Assistant Manager Mr. Ram
Kishore for his continuous and strict monitoring that kept us motivated and
focused on our work. It is under his teaching; we could perceive the core topics
and basic techniques used at the site in great details. I truly admire him for his
efforts and the wealth of knowledge that he posses.
INDEX

1. Acknowledgement. 02

2. Definitions and Abbreviations... 04

3. Project Details............ 05

4. Project Description..... 06

5. Site Layout.................................... 07

6. Structural element details.. 09

7. Sequence of work.. 14

8. General Terms............... 18

9. Joints..................................... 20

10. Site Pictures......... 22

11. Conclusion........... 30
DEFINITIONS AND ABBREVIATIONS

P&M : Plant and Machinery

I&M : Instrumentation and Monitoring

OCS : Outline Construction Specification

ODS : Outline Design Specification

QA : Quality Assurance

QC : Quality Control

CRD : Construction Reference Drawing

OPC : Ordinary Portland Cement

PCC : Plain Cement Concrete

RCC : Reinforced Cement Concrete

RL : Reduced Level

BUA : Built-Up Area

TM : Transit Mixer
PROJECT DETAILS

1. About the developer


i) Name of the developer: Amrapali Dream Valley Pvt. Ltd.
ii) Address : Sec Tech zone IV, Gr NOIDA
iii) Past experience of executing similar projects at this location: 9
iv) Geographical presence of developer(locations):NCR, U.P., Rajast
han, MP, Bihar, Jharkhand, Orissa, Maharashtra, Kerala

2. About the project


i) Name of the project: Amrapali Dream Valley
Address of the project: GH09,Tech Zone 4, Greater Noida
ii) Total area of the project(acres): 5000(approx.)
iii) No. of units offered to NEHWO:1000 units
iv) Current land use: Residential
v) Land acquired from: Greater Noida Authority
vi) Name of local development authority(LDA): GNIDA
vii) Distance from main road: On the main Road
viii) Distance from nearest railway/metro station: Noida city centre
metro station 8 km approx. Ghaziabad Railway Station 5km
ix) Distance from airport: 35 km
x) Distance from bus stand: 8km
xi) Current status of project: On going
xii) Date of commencement : Feb, 2013
xiii) Date of completion : Apr, 2018 (expected)
PROJECT DESCRIPTION

G+25 Storey fully Precast Residential Building.

Precast elements are manufactured at Amprapali Precast manufacturing


unit located in Kasna, Greater Noida.

Total BUA = 5000 Acres.

Divided in to 2 phases viz.,


Phase 1 Tower A, B, C (Completed)
Phase 2 Tower D, E, F (Ongoing).

PROJECT BRIEF:

Total BUA 5000 Acres

Unit Configuration 14-16 Units/ Floor

Sub Structure Pile foundation Ground

Ground & Terrace Floor Conventional Construction

1st to 23rd Floor Precast Large Wall Panel System


SITE LAYOUT
STRUCTURAL ELEMENTS DETAILS

Foundation:
Casted in situ using M40 grade concrete mix.
Raft type foundation is provided.
Depth of foundation is 1.5 metres.
Area of foundation of apartment is 2,66,000 sq.ft.
Reinforcement dia. used is min. 20 mm and max. 32 mm. @ 100-150 mm c/c spacing.
Column:

Casted in situ using M40 grade concrete mix poured using tower crane.
Height of column:
Width of column:
Reinforcements: min. dia. used is 10 mm and max. 32 mm @ 100-150 mm c/c spacing.
Stirrups: dia. used is 8 mm @ 100-300 mm c/c spacing.
Time required to set is 24 hrs.
Beam:

Precast prestressed beam of M40 grade is used.


Dimension:

Reinforcement of 15 dia. is used in precast beams.

Slab:

Precast prestressed hollow core slab is used.


Grade of concrete mix used is M60.
Reinforcement of 15 dia. is used in precast beams.
Dimesnsion:
Advantages of hollow core slab are:
heavy weight capacity
exceptional fire resistance
lower self-weight
superior acoustic, insulation and thermal properties
highly effective for circulating fresh and warm air
requires less concrete
extended length without central supports
efficient span/depth ratio resulting in decreased structure heights
can be easily changed to include electrical wiring, plumbing and sprinkler facilities
within the building.

SEQUENCE OF WORK
A Quick Check
Ensure the correct panel before hoisting.

Ensure the crane lifting capacity before hoisting the panel.

Ensure the desired cranes working radius.

Ensure the anchorage for the propping does not damage cast-in building services.

Ensure the desired Reduced Level (R.L.) of panel-base by adjusting the shim plate. Shim
plate to be at an interval of 500mm c/c.

Ensure the desired verticality/position is achieved.

Estimated time to install a typical precast element is 1/2 to 3/4 hour.

Construction Requirements

Elements of control
Alignment, Verticality and Levels

Tolerance level
1. For Wall

Vertical deviation +2 mm, -2 mm

Horizontal deviation 0 mm

2. For Beam & Slab

Departure from intended horizontal position, +2 mm or 2 mm

Departure from intended vertical position, +2 mm or 2 mm


The diagrams below illustrates the sequence of installation for the precast beam-slab system:

Procedure
In-Situ Column construction

1. Any cut-outs in the column required for service, water outlets, bolts, etc are determined.
2. Reinforcing steel of dia. 20mm (min.) 32mm (max.) @ 100mm (min) 150mm (max.)
is properly positioned.
3. Stirrups of 8 mm @ 100-300 mm is provided.
4. Steel formworks connected through wingnut used for shuttering.
5. M40 concrete mixture poured in between formworks using tower crane.
6. Concrete is allowed to set forthe next 24 hrs.

Setting Out

1. Surveyor to set cross reference.

2. Transfer grid and mark wall position on slab.


3. Mark 100mm offset line from rear
building edge.
4. Offset wall position by 200 mm.
5. Secure 2x2 timber to the floor at wall edge to
guide wall.

Wall Positioning

1. The first wall in place has to be the partition


wall at the rear.

2. Mark a line parallel to and 100mm from the


external edge of the wall.

3. Place shim plate @ 500 c/c on the floor and


level to wall soffit. Shim plate may also be
placed on Non-shrink mortar bed and allow to
set.
4. Adjust position of the dowel bar.
Wall Adjustment
1. Position adjacent walls and plumb wall corners
at 200 mm offset
2. Adjust verticality until within +2 or 2 mm
3. Ensure the four faces of every walls are adjusted
4. Position string 250 mm from face of walls
5. Walls within the same line are to be adjusted
within same tolerance
6. Ensure air-pocket is fully grouted.

Beam Setting Out

1. Cast wall joint.


2. Mark 1 m reference line.
3. Confirm pocket level. Position shim plate to
correct beam soffit level if required.
4. Mark position of beam on floor.
5. Hoist beam in place and check top level.
6. Plumb beam to verify position on floor below.
7. Ensure beam verticality with a spirit level.
8. Wedge beam against pocket and grout the gap
between the beam and the wall.

Slab Setting Out I

1. Position the slab temporary supports and


adjust the slab soffit level approximately.

2. Raise the height of the supports about 5 mm


above slab soffit level.
Slab Setting Out II

1. Hoist slab in place on top of beam and support.


2. Verify level of every plank soffit at four corners
and center.
3. Adjust level of temporary support accordingly.

Staircase

1. Position landing or slab and verify soffit


level at four corners.
2. Adjust level to within tolerance.
3. Position shim plates at staircase support
location to correct level.
4. Verify level difference between pegs on top
and below.
5. Hoist staircase in place.
6. 10mm gap between precast plank and
staircase.
GENERAL TERMS

METHOD STATEMENT
It is the reference manual issued to the contractor by which the construction is to be carried out.
In this reference code there is a mention of methodology and specification of work in which it is
to be executed. Separate method statement for each different work is issued. This reference code
is to be followed strictly while working, not doing so may result in non-approval of executed 19
work which may further result in loss of money, time, resources and demolition and
reconstruction of same work (now according to the referral code).

SURVEYING
Surveying or land surveying is the technique, profession, and science of determining the
terrestrial or three-dimensional position of points and the distances and angles between them. A
land surveying professional is called a land surveyor. These points are usually on the surface of
the Earth, and they are often used to establish land maps and boundaries for ownership, locations
like building corners or the surface location of subsurface features, or other purposes required by
government or civil law, such as property sales. Instruments used for surveying are:
Total Stations
Auto Level
Level Staff

COUPLER
A coupler is a mechanical splicing system or a bar break mechanical splicing system designed to
be used in the construction industry for splicing high tensile deformed (HTD) bars. Increasingly,
the use of mechanical couplers has been recognized by engineers and contractors to bring about
benefits that can accelerate construction speed, increase productivity and simplify design details.
It carries further advantages like:
Couplers save on lap lengths and could result in lower construction cost
Enhances construction speed.
Reduces congestion in lap zones, thus enhancing concrete flow.
TRANSIT MIXER
A T.M.(concrete mixer) is a device that homogeneously combines cement, aggregate such as sand
or gravel, and water to form concrete. A typical concrete mixer uses a revolving drum to mix the
components. For smaller volume works portable concrete mixers are often used so that the
concrete can be made at the construction site, giving the workers ample time to use the concrete
before it hardens. It has a capacity of 7.5 m 3.

GROUTING
Grout is a flowable plastic material, which should have negligible shrinkage to fill the gaps or
voids completely and should remain stable without cracking, delaminating or crumbling.
Grouting is a process of placing concrete as a material into cavities to increase load bearing
capacity of the structure, reinstate the monolithic nature of a structural member, fill gaps and
voids around precast connections steel base plates and provide fire stops, leakage and soil
stabilization. Injection grouting is process of filling cracks, voids or honeycombs under pressure
in concrete or masonry structural member. The most popular polymer used for this particular
purpose is epoxy. It possesses low pot life, effective in sealing cracks, excellent bond with almost
all materials and good chemical resistance.
JOINTS
Beam to column connection
Beams are set on bearing pads on the column corbels.
Steel angles are welded to metal plates cast into the beams and columns and the joint
is grouted solid.

Slab-to-Beam Connection
Hollow core slabs are set on bearing pads on precast beams.
Steel reinforcing bars are in inserted into the slab keyways to span the joint.
Joint is grouted solid.
Slab may remain untopped as shown, or topped with several inches of cast in place
concrete.
Column-to- column
connection
The vertical bars are
coonected
longitudinally
either using lap splicing
technique or the
couplers.

SITE PICTURES
A Batching Plant at the site for making concrete used for column and
foundation works

Precast elements brought from manufacturing unit located in Kasna and kept on
site for use
The excavation works followed by PCC application

TM of 7.5 cubic metre capacity was used


Workers carrying out centering operation to mark the location of foundation

Hooks provided in precast stairs to lift and position them using tower cranes and
also to tie them with the beam of adjoining floor followed by grouting
Hollow core slab placed on the corbels of the column
Lap splicing provided in the columns

Balcony of the building


Worker correcting the position of reinforcements of foundation before
concreting

Props used to support the column before monolithic casting and welding used to
join few bars of beam and column
Inner walls of the buildings are constructed using conventional brick masonary
works which are covered from outside using Precast PANELS which is smooth
and aesthetically beautiful

Completed multi-storey precast building


CONCLUSION
The main aim of studies within this project was to investigate how a structure is constructed
within its desired properties. We get knowledge about the basic & advanced techniques
of building construction as well as saw the challenges which a civil engineer have to face
during construction i.e. labour problems, cost management, environmental challenges etc. We
cleared our many doubts regarding building construction.

Proper coordination between Amrapali employees helps to maintain quality of work and
efficiency. Regular audits and inspection reports keeps the track of the project. Safety and
environmental factors are given utmost importance. Thus, the labours here are skilled and guided
from time to time regarding safe construction techniques. Moreover the quality of project is given
due consideration by conducting regular tests and maintaining the records.

As a final year engineering student, it was a wonderful experience, having gotten the opportunity
to work with such experienced staff members. I got to learn several new techniques that can be
adopted while construction, which otherwise we dont generally get to see in day-to-day life. Not
only was the experience valuable, but the kind of friendly and cooperative work environment was
absolutely commendable.

THANK YOU

You might also like