Professional Documents
Culture Documents
Shivani
Roll no.:- 1451400933 (4 year B.Tech)
th
Preeti
Roll no.:- 1451400921 (4 year B.Tech)
th
ACKNOWLEDGEMENT
With the deepest gratitude, I would like to thank AMRAPALI GROUP for
having given me this opportunity to undertake this summer training at their
prestigious project.
I would like to thank Mr. Rakesh Kumar Singh, Project Manager for bestowing
upon me this great learning experience.
I would like to convey my gratitude to Mr. Vivek Kumar, Assistant Engineer
and Mr. Shyam Srivastava, Assistant Engineer who guided and encouraged me
throughout the duration of my summer training and imparted in depth knowledge
regarding the project.
I extend my heartfelt and sincere gratitude to Assistant Manager Mr. Ram
Kishore for his continuous and strict monitoring that kept us motivated and
focused on our work. It is under his teaching; we could perceive the core topics
and basic techniques used at the site in great details. I truly admire him for his
efforts and the wealth of knowledge that he posses.
INDEX
1. Acknowledgement. 02
3. Project Details............ 05
4. Project Description..... 06
5. Site Layout.................................... 07
7. Sequence of work.. 14
8. General Terms............... 18
9. Joints..................................... 20
11. Conclusion........... 30
DEFINITIONS AND ABBREVIATIONS
QA : Quality Assurance
QC : Quality Control
RL : Reduced Level
TM : Transit Mixer
PROJECT DETAILS
PROJECT BRIEF:
Foundation:
Casted in situ using M40 grade concrete mix.
Raft type foundation is provided.
Depth of foundation is 1.5 metres.
Area of foundation of apartment is 2,66,000 sq.ft.
Reinforcement dia. used is min. 20 mm and max. 32 mm. @ 100-150 mm c/c spacing.
Column:
Casted in situ using M40 grade concrete mix poured using tower crane.
Height of column:
Width of column:
Reinforcements: min. dia. used is 10 mm and max. 32 mm @ 100-150 mm c/c spacing.
Stirrups: dia. used is 8 mm @ 100-300 mm c/c spacing.
Time required to set is 24 hrs.
Beam:
Slab:
Ensure the anchorage for the propping does not damage cast-in building services.
Ensure the desired Reduced Level (R.L.) of panel-base by adjusting the shim plate. Shim
plate to be at an interval of 500mm c/c.
Construction Requirements
Elements of control
Alignment, Verticality and Levels
Tolerance level
1. For Wall
Horizontal deviation 0 mm
Procedure
In-Situ Column construction
1. Any cut-outs in the column required for service, water outlets, bolts, etc are determined.
2. Reinforcing steel of dia. 20mm (min.) 32mm (max.) @ 100mm (min) 150mm (max.)
is properly positioned.
3. Stirrups of 8 mm @ 100-300 mm is provided.
4. Steel formworks connected through wingnut used for shuttering.
5. M40 concrete mixture poured in between formworks using tower crane.
6. Concrete is allowed to set forthe next 24 hrs.
Setting Out
Wall Positioning
Staircase
METHOD STATEMENT
It is the reference manual issued to the contractor by which the construction is to be carried out.
In this reference code there is a mention of methodology and specification of work in which it is
to be executed. Separate method statement for each different work is issued. This reference code
is to be followed strictly while working, not doing so may result in non-approval of executed 19
work which may further result in loss of money, time, resources and demolition and
reconstruction of same work (now according to the referral code).
SURVEYING
Surveying or land surveying is the technique, profession, and science of determining the
terrestrial or three-dimensional position of points and the distances and angles between them. A
land surveying professional is called a land surveyor. These points are usually on the surface of
the Earth, and they are often used to establish land maps and boundaries for ownership, locations
like building corners or the surface location of subsurface features, or other purposes required by
government or civil law, such as property sales. Instruments used for surveying are:
Total Stations
Auto Level
Level Staff
COUPLER
A coupler is a mechanical splicing system or a bar break mechanical splicing system designed to
be used in the construction industry for splicing high tensile deformed (HTD) bars. Increasingly,
the use of mechanical couplers has been recognized by engineers and contractors to bring about
benefits that can accelerate construction speed, increase productivity and simplify design details.
It carries further advantages like:
Couplers save on lap lengths and could result in lower construction cost
Enhances construction speed.
Reduces congestion in lap zones, thus enhancing concrete flow.
TRANSIT MIXER
A T.M.(concrete mixer) is a device that homogeneously combines cement, aggregate such as sand
or gravel, and water to form concrete. A typical concrete mixer uses a revolving drum to mix the
components. For smaller volume works portable concrete mixers are often used so that the
concrete can be made at the construction site, giving the workers ample time to use the concrete
before it hardens. It has a capacity of 7.5 m 3.
GROUTING
Grout is a flowable plastic material, which should have negligible shrinkage to fill the gaps or
voids completely and should remain stable without cracking, delaminating or crumbling.
Grouting is a process of placing concrete as a material into cavities to increase load bearing
capacity of the structure, reinstate the monolithic nature of a structural member, fill gaps and
voids around precast connections steel base plates and provide fire stops, leakage and soil
stabilization. Injection grouting is process of filling cracks, voids or honeycombs under pressure
in concrete or masonry structural member. The most popular polymer used for this particular
purpose is epoxy. It possesses low pot life, effective in sealing cracks, excellent bond with almost
all materials and good chemical resistance.
JOINTS
Beam to column connection
Beams are set on bearing pads on the column corbels.
Steel angles are welded to metal plates cast into the beams and columns and the joint
is grouted solid.
Slab-to-Beam Connection
Hollow core slabs are set on bearing pads on precast beams.
Steel reinforcing bars are in inserted into the slab keyways to span the joint.
Joint is grouted solid.
Slab may remain untopped as shown, or topped with several inches of cast in place
concrete.
Column-to- column
connection
The vertical bars are
coonected
longitudinally
either using lap splicing
technique or the
couplers.
SITE PICTURES
A Batching Plant at the site for making concrete used for column and
foundation works
Precast elements brought from manufacturing unit located in Kasna and kept on
site for use
The excavation works followed by PCC application
Hooks provided in precast stairs to lift and position them using tower cranes and
also to tie them with the beam of adjoining floor followed by grouting
Hollow core slab placed on the corbels of the column
Lap splicing provided in the columns
Props used to support the column before monolithic casting and welding used to
join few bars of beam and column
Inner walls of the buildings are constructed using conventional brick masonary
works which are covered from outside using Precast PANELS which is smooth
and aesthetically beautiful
Proper coordination between Amrapali employees helps to maintain quality of work and
efficiency. Regular audits and inspection reports keeps the track of the project. Safety and
environmental factors are given utmost importance. Thus, the labours here are skilled and guided
from time to time regarding safe construction techniques. Moreover the quality of project is given
due consideration by conducting regular tests and maintaining the records.
As a final year engineering student, it was a wonderful experience, having gotten the opportunity
to work with such experienced staff members. I got to learn several new techniques that can be
adopted while construction, which otherwise we dont generally get to see in day-to-day life. Not
only was the experience valuable, but the kind of friendly and cooperative work environment was
absolutely commendable.
THANK YOU