You are on page 1of 219

Daily Accomplishment

Pulsar Event Hall, Tuguegarao City


March 29-April-5, 2016
Date Activities Manpower
March 29,2016 1.Dismantling of Formworks for Mezzanine slab 1-Engr
2.Installation of stirrups for Column 3rd lif 1-IT
3.Installation of Formworks for column 3rd lif
4.Rebars works
5.Installation of Waterline Layout
March 30,2016 1.Installation of Formworks for column 3rd lif 1-Engr
2.Installation of stirrups for Column 3rd lif 1-IT
3.Rebars works
4.Installation of Scaffolding
5.Installation of Barracks for Pulsar Staff
March 31,2016 1.Installation of stirrups for Column 3rd lif 1-Engr
2.Installation of Barracks for Pulsar Staff 1-IT
3.Rebars works 4-Drivers(TM20,17, 14,)SV 27)
4.Dismantling of Formworks for Mezzanine slab 1-Operator (PC2)
5.Installation of Formworks for column 3rd lif
6.Bracing of column 3rd lif
7.Concrete Pouring for column 3rd lif(34 m) 1-Engr
April 1, 2016 1.Instalation of Formworks for Slab 1-IT
2.Dismantling of H-frame(mezzanine slab) 1-Driver(SV22)
3.Rebars Works
4.Installation of Stirrups for Column 4th lif 1-Engr
April 2, 2016 1.Instalation of Formworks for Slab 1-IT
2.Installation of Formworks for column 3rd lif 1-Driver(SV27)
3.Rebars Works
4.Installation of Fence 1-Engr
April 3, 2016 1.Installation of fence and gate 1-IT
(SUNDAY) 2.Installation of Formworks for slab 1-Driver(DT13)
3.Dismantling of Formworks for mezzanine slab
April 4,2016 1.Installation of fence and gate 1-Engr
2.Installation of Formworks for slab 1-IT
3.Dismantling of Formworks for mezzanine slab 2-Drivers(SV18,SL-3)
4.Rebars Works
5.Installation of Scaffolding
April 5,2016 1.Installation of formworks for Slab 1-Engr
2.Rebars works 1-IT
3.Installation of Beam for Slab
4.Dismantling of formworks for mezzanine slab
Daily Accomplishment
Pulsar Event Hall, Tuguegarao City
April-6-12,2016
Date Activities Manpower
1.Installation of Formworks for slab 1-Engr
2.Installation of stirrups for Gym Area 1-IT
April 6, 2016 3.Installation of H-frame for Cantilever Slab 1-Operator (BH16)
4.Rebars works 3-Driver(SV27,TH3,DT13)
5. Trimming
1.Installation of Formworks for slab 1-Engr
2.Installation of bars for roof beam 1-IT
April 7, 2016
3.Rebars works Driver-(SV18)
4.Installation of formworks for Cantilever Slab
1.Installation of Formworks for slab 1-Engr
2.Installation of scaffolding 1-IT
April 8, 2016 3.Rebars works Driver-(SV22)
4.Installation of formworks for Cantilever Slab
5.Installation of bars for beam
1.Instalation of Formworks for Slab 1-IT
2.Installation of scaffolding 2-Driver(SV22,DT13)
3.Rebars Works
April 9, 2016
4.Installation of bars for beam
5.Installation of H-frame for Cantilever Slab
6.Dismantling of Formworks for Column 3rd lif
April 10, 2016 1.Instalation of Formworks for Slab 1-Engr
2.Installation of Scaffolding 1-IT
(SUNDAY)
1-Operator(LD13)
1.Isstallation of Formworks for slab 1-Engr
2.Installation of formworks for Cantilever Slab 1-IT
3.Installation of bars for beam 2-Drivers(SV2,Sv)
April 11,2016
4.Rebars Works
5.Excavation with gravel bedding
6.Dismantling of formworks for column 2nd lif
1.Installation of formworks for Slab 1-Engr
2.Rebars works 1-IT
April 12,2016 3.Installation of Bars for beam
4.Trimming and gravel bedding
5.Rebars Works
Daily Activities
Pulsar Event Hall, Tuguegarao City
April-13-19,2016
Date Activities Manpower
1.Installation of Formworks for slab 1-Engr
2.Installation of bars for roof beam 2-IT
3.Rebars works
April 13, 2016
4.Trimming with gravel bedding
5.Installation of scaffolding
6.Installation of bars for beam
1.Installation of Formworks for slab 1-Engr
2.Installation of bars for roof beam 2-IT
3.Rebars works 2-Driver-(SV28)(forward)
April 14, 2016
4.Installation of formworks for Cantilever Slab
5.CHB Laying for RC Wall
6.Trimming with gravel bedding
1.Installation of Formworks for slab 1-Engr
2.Installation of scaffolding 2-IT
3.Rebars works
April 15, 2016
4.Installation of formworks for Cantilever Slab
5.Installation of bars for beam
6.Chb Laying for RC Wall
1.Instalation of Formworks for Slab 1-Engr
2.Installation of scaffolding 2-IT
April 16, 2016 3.Rebars Works 2-Driver(SV22,DT13)
4.Installation of bars for beam
5.Chb Laying for RC Wall
April 17, 2016 1.Instalation of Formworks for Slab 1-Engr
2.Installation of Scaffolding 2-IT
(SUNDAY)
3.Cutting of Dowels
1.Installation of Formworks for slab 1-Engr
2.Chb laying for Rc wall 2-IT
April 18,2016 3.Installation of bars for beam 2-Drivers(SV7,Sv28)
4.Rebars Works
5.Installation of Scaffolding
1.Installation of Formworks for slab 1-Engr
2.Rebars Works 2-IT
April 19,2016
3.Installation of Scaffolding
4.Installation of Bars for Slab
5.Installation of Fence
Daily Activities
Pulsar Event Hall, Tuguegarao City
April-19-25,2016
Date Activities
1.Installation of Formworks for slab
2.Rebars Works
3.Installation of Scaffolding
April 19, 2016 4.installation of Bars for Slab
5.Installation of Bars for Cantilever Slab
6.Installation of fence and gate
7.Installation of Anchor Bolt
1.Installation of Formworks for slab
2.Rebars Works
3.Installation of Dowwnspout
April 20, 2016
4.Installation of Bars for Beam
5.Installation of Bars for Cantilever Slab
6.Installation of Anchor Bolt
1.Installation of Formworks for slab
April 21, 2016 2.Installation of formworks for Cantilever Slab
3.Rebars works
1.Installation of Sorng jack for the Support of Slab
2.Installation of Gate
3.Rebars Works
4.Concrete Pouring for Slab
April 22, 2016
5.Installation of Dowel
i
7.Installtion of Scaffolding
8.Installation of Forworks for column 3rd lif
1.Installation of Formworks for slab
2.Installation of Bars for slab
April 23,2016 3.Installation of Dowel
4.Rebars Works
5.Dismantling of Formworks for Slab
6.Installation ofplanted column
7.Installation of Strirruos for Planted Column
1.Installation of Bars for Beam
2. Dismanting of Formworks for column 3rd lif/ beam
April 25,2016 3. Plastering/Watering for Slab
4. Hauling
April 25,2016

5. Rebars Works
Manpower
1-Engr
2-IT

1-Engr
2-IT
2-Driver-(SV18)(DT19)

1-Engr
1-IT
1-driver(SV28)
1-Engr
2-IT
3-Driver(SV28,TM14,TM21)
1-Operator(PC2)

1-Engr
1-IT
2-Drivers(SV7,Sv28)

1-Engr
1-IT
2Driver(Sv18,Sv24)
2-Operator(LD3,LD4)
Date

June 8,2016

June 9, 2016

June 10, 2016

June 11, 2016

June 12, 2016

June 13, 2015

June 14, 2015


Daily Activities
Pulsar Event Hall, Tuguegarao City
June 8-14,2016
Activities
1.Installation of formworks for Remaining Span @ mezzanine $ dance G/L E-D,planted column @ dance studio
2. Rebars works remaining span @ mezzanine and dance studio G/L ED,
planted column @ dance studio $ new footing / column based on plan
3. Excavation , Levelng and hauling @ hotel
4. Fabricaton of Steel bars
1.Installation of formworks for Remaining Span @ mezzanine $ dance G/L E-D,planted column @ dance studio
2. Rebars works remaining span @ mezzanine and dance studio G/L ED,
planted column @ dance studio $ new footing / column based on plan
3. Excavation , Levelng and hauling @ hotel
4. Fabricaton of Steel bars
1.Installation of formworks for Remaining Span @ mezzanine $ dance G/L E-D,planted column @ dance studio
2. Rebars works remaining span @ mezzanine and dance studio G/L ED,
planted column @ dance studio $ new footing / column based on plan
3. Manual trimming of new footing/ column based on plan
4. Fabricaton of Steel bars
1. Installation of Anchor Bolt
2.Installation of formworks for Remaining Span @ mezzanine $ dance G/L E-D,planted column @ dance studio
3. Rebars works remaining span @ mezzanine and dance studio G/L ED,
planted column @ dance studio $ new footing / column based on plan
4. Fabricaton of Steel bars
5. Manual Trimming
1. Concrete pouring @ dance studio & mezzanine area (remaining span ) & new footing (F-3)
2. Installation of anchor bolt

1. Installation of formworks at planted column @ dance studio & URG @ roof deck
2. Rebars works for planted column @ dance studio & URG @ roof deck, new footing/ column base on plan
3. Fabrication of Steel bars

1. Installation of formworks at planted column @ dance studio & URG @ roof deck
2. Rebars works for planted column @ dance studio & URG @ roof deck, new footing/ column base on plan
3. Fabrication of Steel bars
Manpower
1-Engr
2-IT
1-operator (BH 9)
1- Driver (SV 5)

1-Engr
2-IT
2-Driver-(SV5)(DT9)
1- operator (BH9)

1-Engr
2-IT
2-Driver-(SV5)(SV22)
1- operator (BH9)

1-Engr
2-IT
2-Driver-(SV5)(SV22)
1- operator (BH9)

1-Engr
2-IT
3-Driver-(TM14 ) (TM 21) (TM23)
1- operator (PC 2)
1-Engr
2-IT
1- operator (BH9)

1-Engr
1-IT
1- operator (BH9)
3-Driver (SV5)(DT 25) (DT 24)
Date

June 22, 2016

June 23, 2016

June 24, 2016

June 25, 2016

June 27, 2016

June 28, 2016


June 28, 2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
June 22-28,2016
Activities
1.Installation of formworks @ planted column @ dance studio & Construction New septic tank for Hotel I
2. Rebars works for planted column @ dance studio & New Septic tank For Hotel I
3. Excavation , Levelng and hauling @ hotel
4. Fabricaton of Steel bars (Hotel & Ballroom)
5. Fabrication of steel truss( Ballroom)
6. Hauling of debris
7. Concrete Breaking
8. Delivery of steel truss on site
1. Installation of formworks at planted column @ dance studio
2. Rebars works for construction of new septic tank for pulsar hotel 1
3. Excavation , Levelng and hauling @ hotel
4. Fabricaton of Steel bars (Hotel & Ballroom)
5. Fabrication of steel truss( Ballroom)
6. Excavation of Hotel II
7. Hauling of Debris
8. Lifing of CHB
1. Hauling of Debris
2. Fabrication of Steel Truss For Water tank
3. Installation of Temporary waterline for construction
4. Rebars works
5. Dismantling of Scaffolding
6. Lifing of CHB
7. Concrete Pouring of Septic tank (Hotel I)
1. Hauling of Debris
2. Fabrication of Steel Truss For Water tank
3. Installation of Temporary waterline for construction
4. Rebars works
5. Dismantling of Scaffolding
6. Lifing of CHB
1. Trimming of Hotel
2. Hauling of Debris
3. Excavation
4. Rebars works @ new column /footing Based on plan & new planted column
5. Stripping of Scaffolding & formworks
1. Installation of formwoks @ planted column @ dance studio, column C-3 C-4 (2nd lif) URG @ Roof Deck
and constructionof new septic tank
2.Rebars works for Planted column @ dance studio C-3 C-4 (2nd lif) , URG @ roof deck and construction of new septi
3. Excavation
4. Manual Trimming
5. Excavation, Leveling and hauling @ Hotel
6. Fabrication of steel bars (Hotel & ballroom)
7. Preparing of steel Truss
8. Tapping of Temporary water tank/line for construction
Manpower
1-Engr
2-IT
2-operator (BH 9) (STC250)
3- Driver (SV 5) (DT1) (SL3)

1-Engr
2-IT
2-operator (BH 9) (STC250)
3- Driver (SV 5) (DT1) (SL3)

1-Engr
2-IT
2-operator (BH 9) (STC250)
3- Driver (SV 5) (DT1) (TM 23)

1-Engr
2-IT
2-operator (BH 9) (STC250)
2- Driver (SV 5) (DT1)

1-Engr
2-IT
2-operator (BH 9) (STC250)
2- Driver (SV 5) (DT1)

1-Engr
2-IT
2-operator (BH 9) (STC250)
2- Driver (SV 5) (DT1)
Date

June 29,2016

June 30, 2016

July 1, 2016

July 2, 2016

July 3,2016

July 4, 2016
July 4, 2016

July 5,2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
June 29- July 5,2016
Activities
1.Installatonof formworks for planted column @ dance studio column C-3, C-4 (2nd lif),
URG @ roof deck construction of new septic tank (RC wall 2nd lif), Pulsar hotel II level 1 (RC wall)
2. Rebars works for planted column @ dance studio, URG @ Roof deck & Pulsar hotel II level I (RC wall)
3. Fabrication of steel bars (Baallroom & hotel)
4.Installation / fabricatn of steel truss
5. Installation of septic tank sewer line
6. Tapping of temorary water tank/ line for construction
7. Lifing of steel truss
8. Hauling of debris
1.Installatonof formworks for planted column @ dance studio column C-3, C-4 (2nd lif),
URG @ roof deck construction of new septic tank (RC wall 2nd lif), Pulsar hotel II level 1 (RC wall)
2. Rebars works for RC wall (Hotel II level I)
3. Fabrication of steel bars (Baallroom & hotel)
4. Excavation/ Hauling of peabbles
1. Hauling of Debris
2. excavation, Leveling @ hotel
3. Fabrication of steel bars (Baallroom & hotel)
4. Installation of formworks @ pulsar Hotel II (Level I) (RC wall)
5. Rebars works @ Pulsar Hotel II Level I (RC wall)
6. Manual Trimming @ Pulsar Hotel II Level I (RC wall )
7. Gravel Bedding @ Pulsar Hotel II level I
8. Lifing of Steel Truss
9.Installation of water filters steel frame
1.Manual trimming @ pulsar hotel II Level I (RC wall)
2. Installation of formworks Hotel II Level 1 (RC wall)
3. rebars works @ Pulsar Hotel II level 1 (Rc wall)
4. Excavation
5. Hauling of debris & Peabbles
6. Installation/ Fabrication of steel truss
7. Concrete pouring of new septic tank (RC wall 2nd lif ) Hotel 1
1.Lifing of steel truss
2. Installation of formworks @ roof deck & septic tank
3. Installation / Fabrication of steel truss / Erection
4. Installation of Ripe sewer line (septic tank)
1.Lifing of steel truss
2. Fabrication/ Erection of roof steel truss
3. excavation (Hotel II)
4. Fabrication of steel bars (Hotel & Ballroom)
5. Dismantling of Formworks
6. Installation of formworks @ suspended slab on upper roof deck & dance studio,suspended slab @ septic tank
7. Rebars works @ suspended slab on upper roof deck@ dance studio, footing RC wall of Domestic Tank on 1st level (Hotel II)
8. Concrete breaking for sewer line
1. Installation of roof steel truss
2.Fabrication of steel bars (Hotel & ballroom)
3. Excavation and concrete breaking (Hotel II)
4. Hauling of Debris
5. Rebars works @ footing /RC wall of domestic tank on 1st level of (hotel II)
6. Dismantling of steel stairs of water tank house
7. Demolition of Existing water tank house
Manpower
1-Engr
2-IT
2-operator (BH 9) (STC250)
2- Driver (SV 5) (DT2)

1-Engr
2-IT
3-operator (BH 9) (STC250)(BH15)
3- Driver (SV 5) (DT1) (DT5)

1-Engr
2-IT
2-operator (BH 9) (STC250)
3- Driver (SV 5) (DT1) (DT13)

1-Engr
2-IT
2-operator (BH 9)
3- Driver (SV 5) (DT1) (TM23)

1-Engr
1-IT
1-operator (STC250)

1-Engr
2-IT
2-operator (BH 9) (STC250)
2- Driver (SV 5) (DT1)

1-Engr
2-IT
2-operator (BH 9)
2- Driver (SV 5) (DT1)
Date

July 6,2016

July 7, 2016

July 8, 2016

July 9,2016

July 10, 2016

July 11,2016
July 11,2016

July 12, 2016


Daily Activities
Pulsar Event Hall, Tuguegarao City
July 6-12,2016
Activities
1.Installation/ Erection of Roof steel truss
2. Rebars works@ footing (RC wall of domestic tank on first level of Hotel II )
3. Concrete breaking of sewerline (Hotel I)
4. Installation of formworks @ pulsar Hotel II (Level I) (RC wall) and pulsar Hootel II Domestic tank
5. Lifing of roof steel truss
6. Leveling, excavating & hauling of debris (Hotel I)
1.Installation of formworks @ column C-3, C-4 (2nd lif) Pulsar hotel II level I (RC wall ) & (Pulsar Hotel II Domestic tank)
2. Rebars works @ column C-3, C-4 (2nd lif), Pulsar Hotel II level I (Rc wall), Pulsar Hotel II Domestic tank
3. Clearing of manhole @ construction of new septic tsnk (Rc wall- 2nd lif)
4. Excavation, Leveling & hauling @ hotel
5.Fabrication of steel bars (Hotel & ballroom)
6. Installation/ Fabrication of steel truss
7. Fabrication of Steel platform of water filter
8. Installation of anchor bolt for 2nd floor @ dance studio Tapping of temporary water tank/ line for septic tank sewer line (hot
9. Mobilization (Ballroom) Installation of Drain line @ ground floor
10.Demolition of existing water tank
1.Dismantling of formworks
2. Fabrication of steel bars (Hotel & ballroom)
3. Rebars works @ column C-3, C-4 (2nd lif), Pulsar Hotel II level I (RC wall)
4. Fabrication of steel platform of water filter
5. Installation of anchor bolts for 2nd floor @ Dance studio
6. Concrete pouring of Roof beams , Concrete ledge & column
7. Excavation Level 2&3, Leveling & hauling of Debris @ hotel
1.Dismantling of formworks
2. Fabrication of steel bars (Hotel & ballroom)
3. Installation/ Faabrication of steel truss (ballroom)
4. Fabrication of steel platform of water filter
5. Installation of PVC pipe for temporary water line
6. Excavation Level 2&3, Leveling & hauling of Debris @ hotel
7. Backfilling of Groud floor
8. Concrete pouring @ domestic tank, fire tank, column footing (F-2, F-5,C-1 & C-2) Matt foundation Rc wall )Level I (Hotel II)
1. Installation of fomworks for slab
2. Dismantling of formworks
3. Fabrication & Installation of steel platform for filter
1.Fabrication & Installation of steel platform for filter
2. Installation of formworks @ suspended slab @ second floor
3. Slab on Grade @ service Area, Backfilling , Leveling & compaction
4.URG @ roof deck removal of formworks
5. Fabrication of steel bars (Hotel & ballroom)
6.Installation of formworks @ pulsar Hotel II Level I (RC wall 2nd lif )
7. Construction of new septic tank (slab) for removal of formworks (hotel)
8. Rebars works of pulsar hotel II level I ( RC wall 2nd lif ) and pulsar hotel II domestic tank
9. Excavation, Leveling , Hauling @ hotel
1.Rebars works @ suspended slab @ 2nd lif
2. Backfilling , leveling & compaction @ slab grade @ Service area
3. Removal of formworks @ new septic tank (slab)
4. Fabrication of steel bars
5. Installation /Fabrication of steel truss
6. Fabrication of steel platform of water
7. Filter/Installation of anchor bolt for 2nd floor @ dance studio
8. CHB Laying @ mezzanine level
9. Lifing of water filter
10.Excavation, Leveling &Hauling @Hotel
11.Hauling debris
Manpower
1-Engr
2-IT
3-operator (BH 9) (STC250)(bobcat)
1- Driver (DT1)

1-Engr
2-IT
3-operator (BH 9) (STC250)(bobcat)
2- Driver (DT1) (SL 1)

1-Engr
2-IT
4-operator (BH 9) (STC250)(bobcat)
(PC2)
4- Driver (DT1) (DT25) (DT23) (TM25)

1-Engr
2-IT
2-operator (BH 9) (Bobcat)
4- Driver (DT1) (TM24)(TM25)(TM11)

1-Engr
1-operator (CP1)

1-Engr
2-IT
2-operator (BH 9) (BObcat)
1- Driver (DT 1)

1-Engr
2-IT
3-operator (BH 9) (Bobcat)(PC2)
1- Driver (DT1)
Date

July 13,2016

July 14,2016

July 15,2016

July 16, 2016


July 18,2016

July 19,2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
July 13-19,2016
Activities
1.Rebars works @ Pulsar Hotel II level I (RC wall -2nd lif) & pulsar hotel II domestic tank
2. Installation of formworks @ pulsar hotel II level I (RC wall- 2nd lif) & Domestic tank
3. Excavation, leveling, & hauling
4. Fabrication of steel bars (hotel & ballroom)
5.Rebars works @ suspended slab @ 2nd lif
6. Installation of formworks @ suspended slab @ 2nd flr.
7. CHB laying @ mezzanine level
8. Installation /Fabrication of steel truss
9. Fabrication/Installation of steel platform & water filter
10. Backfilling of ground floor
1.Installation of formworks @ pulsar hotel II domestic tank
2. Excavation, leveling & hauling @ hotel
3. Fabrication of steel bars (Ballroom & hotel)
4.Rebars Works @ Suspended Slab @ 2nd floor
5. Removal of formworks @ URG roof deck
6. Backfilling @ ground floor
7. Installation/ Fabrication of roof steel truss
8. Installation of drain line @ ground floor
1.Installation of formworks @ pulsar hotel II domestic tank
2. Excavation, leveling & hauling @ hotel
3. Fabrication of steel bars (Ballroom & hotel)
4.Concrete Breaking
5. Removal of formworks @ URG roof deck
6. Installation/ Fabrication of roof steel truss
7. CHB laying @ mezzanine level
8. Installation of formworks @ column C-3, C-4 (2nd lif)
9. Installation of drain line @ Ground floor
1.Installation of formworks @ pulsar hotel II domestic tank
2. Excavation, leveling & hauling @ hotel
3. Fabrication of steel bars (Ballroom & hotel)
4. Installation of formworks @ column C-3, C-4 (2nd lif)
5.Installation/ Fabrication of roof steel truss
6. Installation of drain line @ ground line
7. Concrete pouring @ slab ,beam, corbel, concrete gutter, ledge and column
1.Rebars works @ level I (RC wall)
2. Installation of formworks @ level I (RC wall) & domestic tank
3. Excavation, leveling, & hauling
4. Fabrication of steel bars (hotel & ballroom)
5.Concrete tapping for preparation of water proofing
6. Remooroval of formworks (remaining ) URG @ second floor
7. Installation of scaffolding @ URG 2nd flr. & planted column 2nd flr.
8. Hauling Of CHB & laying of CHB @ mezzanine level
9. Installation/Fabrication of roof steel truss
10. Installation of drain line @ ground line
11. Compaction
1.Rebars works @ level I (RC wall) & domestic tank
2. Installation of formworks @ level I (RC wall) & domestic tank
3. Excavation, leveling, & hauling
4. Fabrication of steel bars (hotel & ballroom)
5. Concrete tapping for preparation of water proofing
6. Removal of formworks (remaining) @ URG second floor
7. Installation of scaffolding @ URG 2nd flr. & planted column 2nd flr.
8. Hauling Of CHB & laying of CHB @ mezzanine level
9. Hauling of pure sand for CHB laying
10. Hauling of debris/ waste @ canopy foundation
11. Installation/ Fabrication of roof steel truss
Manpower
1-Engr
2-IT
2-operator (BH 9) (bobcat)
4- Driver (DT1) (DT23)(DT25)(DT16)

1-Engr
2-IT
2-operator (BH 9) (bobcat)
1- Driver (DT1)

1-Engr
2-IT
2-operator (BH 9) (bobcat)
1- Driver (DT1)

1-Engr
2-IT
3-operator (BH 9) (Bobcat)(PC2)
4- Driver (DT1) (TM24)(TM25)(TM11)

1-Engr
2-IT
2-operator (BH 9) (Bobcat)
1-Driver (DT1)

1-Engr
2-IT
2-operator (BH 9) (BObcat)
2- Driver (DT 1) (DT25)
Daily Activities
Pulsar Event Hall, Tuguegarao City
July 20-26,2016
Date Activities Manpower
1.Concrete Tapping for Preparation of water proofing 1-Engr
2. Installation of scaffolding @ URG 2nd flr. & planted column @ 2nd Flr. 2-IT
3.Rebars works @ URG 2nd flr. & planted column 2nd flr. 1- Checker
4. Installation of formworks @ new planted column 2-operator (BH 9) (bobcat)
5. CHB laying @ mezzanine level 4-Driver (DT1) (DT23)(DT25)
6. Installation of base plate for corbel / for steel truss (SV 31)
July 20,2016 7. Fabrication of steel bars (HOTEL & Ballroom)
8. Hauling pure sand for CHB laying
9. Pouring @ ground floor Grid line J-1
10. Rebars works @ level 1 (RC wall -2nd lif) & domestic tank
11. Installation of formworks @ Level 1 (RC wall- 2nd lif) & domestic tank
12.Tapping of Inlet & outlet septic tank 1
13. Excavation, leveling & hauling
1.Rebars Works @ URG (2nd flr.)& planted column (2nd flr.) 1-Engr
2.Instrallation of formworks @ URG (2nd flr.) & planted column (2nd flr.) 2-IT
3. Fabrication of steel bars (Ballroom & hotel) 1- Checker
4.Lifing of pure sand @ mezzanine level 2-operator (BH 9) (bobcat)
July 21,2016 5. Installation of base plate for roof steel truss 1- Driver (DT1)
6. CHB laying @ mezzanine level
7. Rebars works @ level 1 (RC wall -2nd lif) & domestic tank
8. Installation of formworks @ Level 1 (RC wall- 2nd lif) & domestic tank
9. Excavation, leveling & hauling
1. Installation of formworks @ URG (2nd flr.) & planted column ( 2nd flr.) 1-Engr

July 22,2016
2. Fabrication of steel bars (Hotel & ballroom) 2-IT
3. Installation/ Fabrication of steel truss 1- Checker
July 22,2016 4. CHB laying @ mezzanine level 1-operator (BH 9)
5. Rebars works @ level 1 ( RC wall- 2nd lif) 1- Driver (DT1)
6. Installation of formworks @ domestic Tank
7. Excavation, Leveling & hauling
1. Removal of formworks @ mezzanine level/dance studio 1-Engr
2. CHB laying @ gutter wall 2-IT
3. Fabrication of steel bars (Ballroom & hotel) 1- Checker
July 23,2016
4. Installation steel truss 1-operator (BH 9)
5.Installation of formwoks @ level 1 (RC wall-2nd lif) 1- Driver (DT1)
6. Excavation, leveling & hauling
1. Dewateringg of flooded Excavations 1-Engr
2. Trimming works for footing/ footing tie bean @ canopy column 2-IT
3. Installation of roof steel truss 1- Checker
July 25,2016 4. CHB laying @ dance studio/ Gym on 2nd flr. 1-operator (BH 9)
5. Gravel bedding @ domestic tank 1- Driver (DT1)
6. Excation, leveling & hauling of 2nd floor of hotel
7. Fabrication of steel bars (HOTEL & Ballroom)
1.Installation of formworks @ canopy (Foundation & FTB ) & 2nd floor (Remaining span ) 1-Engr
2. Rebars works @ canopy (Foundation & FTB ) & 2nd floor (Remaning span) 2-IT
3. Lifing of CHB & Cement 1- Checker
4. CHB laying 1-operator (BH 9)
July 26, 2016
5. Fabrication of steel bars (HOTEL & Ballroom) 1- Driver (DT1)
6. Installation of formworks @ level 1 (RC wall - 1st lif) & domestic tank
7. Rebars works @ level 1 (RC wall- 1st lif) & domestic tank
8. Excavation, Leveling & hauling
Daily Activities
Pulsar Event Hall, Tuguegarao City
July 27- August 2,2016
Date Activities Manpower
1. Haulingb of CHB @ Second floor 1-Engr
2. CHb laying @ Second Floor 2-IT
3. Fabrication of steel bars (Ballroom & hotel) 1- Checker
4. Installation/ Fabricatio0n of Roof Framing @ 2nd floor 1-operator (BH 9)
July 27,2016
5. Installation of Formworks @ level 1 (RC wall- 1st lif) & domestic tank
6. Rebars works @ level 1 (RC wall - 1st lif) & domestic tank
7. Excavation, Leveling & hauling
8. Installation of vent Pipe
1. Gravel Bedding @ canopy (Foundation & FTB) 1-Engr
2. Hauling of CHB & Cement for masonry works @ second floor 2-IT
3. CHB laying @ second floor 1- Checker
4. Fabrication of Steel bars (Hotel & Ballroom) 2-operator (BH 9) (PC 2)
July 28,2016 5. Installation / Fabrication of roof framing @ 2nd floor 3- Driver (DT1) (TM 25)(TM 24)
6. Concrete pouring @ canopy (Foundation & FTB)
7.Installation of formworks @ level 1 (RC wall - 1st lif ) & domestic tank
8. Rebars works @ level 1 (RC wall- 1st lif)
9. Concrete pouring domestic tank & fire tank
1.Removal of formworks 1-Engr
2. Hauling of CHB @ second floor 2-IT
July 29, 2016 3. CHB laying @ second floor 1- Checker
4. Fabrication of Steel bars (Hotel & Ballroom) 1-operator (BH 9)
5.Excavation, Leveling & Hauling 1- Driver (DT1)
1. Haulingb of CHB 1-Engr
2. Removal of formworks 2-IT
July 30, 2016
July 30, 2016 3. CHB laying @ second floor 1- Checker
4. Fabrication of Steel bars (Hotel & Ballroom) 1-operator (BH 9)
5.Excavation, Leveling & Hauling 1- Driver (DT1)
1. Installation of Anchor- Bolts for 2nd floor roof framing 1-Engr
2. Hauling of sand and cement to second floor 1-IT
August 1,2016 3. Scratch Coating (Rebokada ) @ 2nd floor 1- Checker
4. Repairing of fallen fence\ 2-operator (BH 9)(CP 2)
5. Removing and cleaning of storm debris
1.Compaction 1-Engr
2. Scratch Coating(Rebokada) 1-IT
3.Fabrication of steel bars (Hotel & Ballroom) 1- Checker
4.Installation of scaffoldings @ URG 2nd floor 3-operator (BH 9)(CP 2) (PC 2)
August 2,2016 5.Dewatering of flooded excavations 2-driver (TM 14) (TM 7)
6. Sifing grains of sand
7. Rebars works @ level 1 (RC wall -1st lif)
8. Cleaning of Storm debris
9.Concrete pouring of leedge, roof beams, planted column and canopy (foundation and FTB)
Daily Activities
Pulsar Event Hall, Tuguegarao City
August 3-9,2016
Date Activities Manpower
1.Plastering @ second floor (masonry works) 1-Engr
2. Fabrication of steel bars (Hotel & ballroom) 1-IT
3. Hauling cement & pure sand 1- Checker
4. Installation of formworks @ second floor 1-operator (BH 9)
5. CHB laying @ second floor 1-driver (DT 3)
August 3,2016 6. Rebars works @ second floor
7. Installation of filter's catwalk
8. Installation of formworks @ level 1 (RC wall- 1st lif ) & domestic tank
9. Rebars works @ level 1 (RC wall- 1st lif ) & domestic tank
10. Excavation, leveling & hauling
11. Installation of vent pipe
1. Stripping of forms @ canopy (foundation & FTB) & second floor (Remaining span) 1-Engr
2. Installation of formworks @ canopy (Foundation & FTB) 1-IT
3. Rebars works @ canopy (Foundation & FTB) 1- Checker
4. Plastering @ second floor (Masonry works) 1-operator (BH 9)
5. Fabrication of Steel bars (Hotel & ballroom) 1-driver (DT 3)
August 4,2016 6. Installation of filter's catwalk
7. Hauling of CHB
8. Installation of formworks @ level 1 (RC wall- 1st lif ) & domestic tank
9. Rebars works @ level 1 (RC wall- 1st lif ) & domestic tank
10. Excavation, leveling & hauling
11. Installation of vent pipe
1. Rebars works @ canopy (Foundation & FTB) 1-Engr

August 5,2016
2. Dewatering of flooded excavations 1-IT
3. CHB laying 1- Checker
4. Backfilling 1-operator (BH 9)
5. Fabrication of Steel bars (Hotel & ballroom) 1-driver (DT 3)
August 5,2016
6.Installation of plain bar
7. Installation of formworks @ level 1 (RC wall- 1st lif ) & domestic tank
8. Rebars works @ level 1 (RC wall- 1st lif ) & domestic tank
9. Excavation, leveling & hauling
10. Installation of vent pipe
1.Rebars works @ canopy (Foundation & FTB) 1-Engr
2. Installation of scaffoldings @ canopy (Foundation & FTB) 1-IT
3. Fabrication of steel bars (Hotel & Ballroom) 1- Checker
4.Rebars works @ level 1 (RC wall-1st lif) & domestic tank 1-operator (BH 9)
August 6,2016
5. Excavation, Leveling & hauling 1-driver (DT 3)
6. Gravel Bedding
7. Installation of vent pipe
8. Installation of vulcanic clay for RC wall of Domestic tank & Fire water tank
1. Insatllatiohn of Rebars for column of canopy 1-Engr
2. Plastering @ dance studio/ Gym on second floor 1-IT
3. Applying liquid water plug, liquid asphalt primer and installationj of water proof membrane @ concrete gutter 1- Checker
4. Fabrication of steel bars (Hotel & ballroom) 2-operator (BH 9)
August 8,2016 5. Hauling of cement, sand and water proof membrane (Bobcat)
6. Installation of cross bracing @ the roof 1-driver (DT 3)
7. Installation of formworks & rebars for RC Wall of domestic & fire water tank
8. Installation of bentonite (Vulcanic) clay for RC wall of domestic tank & Fire watewr tank
9. Hauling, Leveling of level 3 of hotel
1. Hauling of sand and cement 1-Engr
2. Plastering @ dance studio/ Gym on second floor 1-IT
3. Installation of rebars for columns for canopy 1- Checker
4. Fabrication of steel bars (Hotel & ballroom) 1-operator (BH 9)
August 9,2016 5. Installation of formworks & rebars for RC Wall of domestic & fire water tank 1-driver (DT 3)
6. Installation of bentonite (Vulcanic) clay for RC wall of domestic tank & Fire watewr tank
7. Hauling, Leveling of level 3 of hotel
August 9,2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
August 10-16,2016
Date Activities Manpower
1.Erection of Scaffoldings @ canopy (Columns, beams, Girders) 1-Engr
2.Rebars works @ canopy (Columns, Beams, Girders) 1-IT
3. Installation of formworks @ cvanopy (Columns, Beams, Girder) 1- Checker
4. Stripping of forms (Suspended slab) @ Ground floor 1-operator (BH 9)
5. Plastering @ second floor (Masonry Works) 1-driver (DT 2
6. Fabrication of steel bars (Hotel & Ballroom)
August 10,2016 7. Installation of sog rod
8. Painting
9. Installation of water proof membrane
10. Rebars works @ Level 1 (RC wall-1st lif) & domestic tank
11. Installation of formworks @ level 1 (Rc wall - 1st lif) & domestic tank
12. Installation of vulcanic clay (water stop) @ level 1 (RC wall-1st lif) & domestic tank
12. Excavation, Leveling & Hauling @ level 2 footings
1.Rebars works @ canopy (Columns, Beams, Girders) 1-Engr
2. Installation of formworks @ cvanopy (Columns, Beams, Girder) 1-IT
3. Stripping of forms (Suspended slab) @ Ground floor 1- Checker
4. Plastering @ second floor (Masonry Works) 2-operator (BH 9)
5. Fabrication of steel bars (Hotel & Ballroom) (Bobcat)
August 11,2016 6. Installation of sog rod 1-driver (DT 3)
7. Painting
8. Installation of water proof membrane
9. Installation of formworks @ level 1 (Rc wall - 1st lif) & domestic tank
10. Installation of vulcanic clay (water stop) @ level 1 (RC wall-1st lif) & domestic tank
11. Concrete breaking
1.Rebars works @ canopy (Columns, Beams, Girders) 1-Engr
2. Installation of formworks @ cvanopy (Columns, Beams, Girder) 1-IT
3. Stripping of forms (Suspended slab) @ Ground floor 1- Checker
4. Plastering @ second floor (Masonry Works) 2-operator (BH 9)
5. Fabrication of steel bars (Hotel & Ballroom) (Bobcat)
August 12,2016
6. Installation of sog rod 1-driver (DT 3)
7. Painting
8. Installation of water proof membrane
9. Installation of formworks @ level 1 (Rc wall - 1st lif) & domestic tank
10.Excavation, Leveling & Hauling @ level 2 footings
1. Installation of formworks @ canopy (Columns, beams & girdes) 1-Engr
2.Plastering @ second floor (Masonry works) 1-IT
3. Fabrication of steel bars (Hotel & Ballroom) 1- Checker
August 13,2016 4. Installation of Sog rod 3-operator (BH 9)
5.Painting (Bobcat) (PC 2)
6.Excavation, Leveling & Hauling @ level 2 footings 5-driver (DT 3) (TM 25)
7. Concrete pouring @ columns & Rc wall of domestic tank & fire tank (TM24) (TM16) (TM 7)
1.Installation of formworks @ canopy (Columns, beams & Girders) 1-Engr
2. Dismantling of scaffoldings 1-IT
3.Dismantling of Scaffoldings @ domestic tank 1- Checker
August 15,2016
4. Concrete breaking 2-operator (BH 9)
(Bobcat)
1- Driver (DT3)
1. Installation of formworks @ canopy (Columns, beams & girdes) 1-Engr
2. Fabrication of steel bars (Hotel & Ballroom) 1-IT
3. Dismantling of scaffoldings 1- Checker
4. CHB laying @ 2nd floor 3-operator (BH 9)
August 16,2016 5. Concrete pouring @ canopy (columns, beams & girders) (Bobcat) (PC 2)
5. Hauling of sand & cement 4-driver (DT 3) (TM16)
6. Rebars works @ level 1 (RC wall- 2nd lif) & domestic tank (TM24) (TM7)
7. Fabrication of steel bars
8. Excavation, Leveling @ level 2 Footings
Date

August 17,2016

August 18,2016

August 19,2016

August 20,2016
August 20,2016

August 22,2016

August 23,2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
August 17-23,2016
Activities
1.Hauling of Cement, Sand @ CHB @ second floor
2. Fabrication of Steel bars
3. CHB layin @ 2nd Floor
4. Fabrication of Steel bars (Hotel & Ballroom)
5. Gravel Bedding @ Service Area
6. Erection of scaffoldings for beams
7. Rebars works @ Level 1 (RC Wall- 2nd Lif) & Domestic tank
8. Installation of formworks @ Level 1 (RC wall 2nd-Lif) & Domestic tank
9. Breaking
1. CHB Laying @ Second Floor
2. Hauling of Cement & Sand
3. Installation of Formworks @ beam
4. Rebars works @ Footing- Tie- Beam & Service Area
5. Fabrication of Steel Bars (Hotel & Ballroom)
6. Clearing
7. Fabrication of Steel Truss
8. Rebars works @ Level 1 (RC Wall- 2nd Lif) & Domestic tank
9. Installation of formworks @ Level 1 (RC wall 2nd-Lif) & Domestic tank
10. Compaction
11.Excavation, Leveling & Breaking
1. CHB Laying @ Second Floor
2. Hauling of Cement & Sand
3. Dismantling of formworks @ Canopy foundation
4. Rebars works @ Service Area
6. Fabrication of Steel bars (Hotel & Ballroom)
7. Rebars works @ Level 1 (RC Wall- 2nd Lif) & Domestic tank
8. Installation of formworks @ Level 1 (RC wall 2nd-Lif) & Domestic tank
9.Excavation, Leveling & Hauling
1. CHB Laying @ Second Floor
2. Hauling of Cement & Sand
3. Fabrication Steel bars (Hotel & Ballroom)
4. Rebars works @ Service Area
5. Pouring @ second Floor
6. Rebars works @ Level 1 (RC Wall- 2nd Lif) & Domestic tank
7. Installation of formworks @ Level 1 (RC wall 2nd-Lif) & Domestic tank
8. Breaking
1. Installation of formworks for 2nd floor beam
2.Rebars works @ beam
3. Dewatering of flooded excavations
4. Plastering @ Mezzanine Level
5. Fabrication of Steel Bars (Hotel & Ballroom)
6. Hauling of sand & Cement
7. CHB Laying @ Mezzanine level
8. Insttalation of membrane type water proofing
9.Mock-up of base plate
10. Rebars works @ Level 1 (RC Wall- 2nd Lif) & Domestic tank
11. Installation of formworks @ Level 1 (RC wall 2nd-Lif) & Domestic tank
12. Breaking
13. Installation of Volclay @ LEVEL 1 (RC wall-2nd lif) & Domestic tank
1. Rebars works @ 2nd floor beams(GL-K & L)
2. Installation of formworks @ Upper Roof beam (GL-K& L)
3. Installation of Membrane Type Water Proofing
4. Hauling of CHB
5. Fabrication of Steel Bars (Hotel & Ballroom)
6. Mock-up of base plate
7.Concrete pouring @ Service Area, Column & Footing
8.Installation of formworks @ level 1 (RC wall- 2nd lif) & domestic tank
9. Excavation & leveling @ level 3 Footings
10. CHB Laying for Air & Water of Total Gas Station
11. Gravel Bedding
Manpower
1-Engr
1-IT
1- Checker
2-operator(BH 9)(Bobcat)
1-driver (DT 3)

1-Engr
1-IT
1- Checker
3-operator (BH 9)
(Bobcat) (CP2)

1-Engr
1-IT
1- Checker
3-operator (BH 9)
(Bobcat) (CP2)

1-Engr
1-IT
1- Checker
2-operator(BH 9)(Bobcat)
1-driver (DT 3)
1-Engr
1-IT
1- Checker
2-operator(BH 9)(Bobcat)

1-Engr
1-IT
1- Checker
3-operator(BH 9)(Bobcat)
(PC2)
2- Driver (TM7) (TM25)
Daily Activities
Pulsar Event Hall, Tuguegarao City
August 24-30,2016
Date Activities Manpower
1.Rebars works @ Second Floor beams (GL-K & L) 1-Engr
2. Installation of formworks @ Upper Roof Beam (GL- K &L) 1-IT
3. Installation of Membrane Type Water Proofing 1- Checker
4. Hauling of Cement & CHB (Ballroom & Hotel) 1-operator(BH 9)
5. Installation of Catwalk
6. Pouring @ column
August 24,2016
7. Plastering @ service Area
8.Installation of formworks @ Level 1 (Rc wall-2nd lif) & Domestic tank
9. Rebars works @ Level 1 Footings
10. CHB laying for Air & Water of Total Gas Station
11. Fabrication of steel bars (Hotel & Ballroom)
12. Excavation, Leveling & Breaking
1. Sifing grains and sand 1-Engr
2. Plastering @ service area 1-IT
3.Dismantling of formworks @ Canopy Foundation 1- Checker
4. Fabrication of steel bars (Hotel & Ballroom) 2-operator(BH 9) (Bobcat)
5. Installation of formworks @ 2nd floor beams (GL- K& L) 1- Driver (DT-3)
6. CHB laying @ Mezzanine level
August 25,2016
7. Installation of Catwalk
8.Installation of formworks @ Level 1 (Rc wall-2nd lif) & Domestic tank
9. Rebars works @ Level 1 Footings
10. Gravel Bedding
11. CHB laying for Air & water of total gas station
12. Excavation, Leveling & Hauling
1. Hauling of CHB and Cement 1-Engr
2. Dismantling of formworks @ canopy foundation 1-IT
3. Installation of formworks @ 2nd floor beams (GL- K & L) 1- Checker
4. CHB laying @ second floor 2-operator(BH 9) (Bobcat)
5. Rebars works @ 2nd floor column
6. Fabrication of steel bars (Hotel & Ballroom)
7. Mock- Up of Base Plate
August 26,2016
8. Insatallation of Catwalk
9.Installation of volclay @ level 1 (RC wall-2nd lif) & Domestic tank
10. Installation of formworks @ level 1 (RC wall 2nd- lif) & Domestic tank
11. Rebars works @ level 1 Footings
12. Concrete pouring for air and water of total gas station
13. Excavation and Leveling
14. Hauling of sand and cement
1. Dismantling of formworks @ canopy foundation 1-Engr
2. Rebars works @ 2nd floor column 1-IT
3. Installation of formworks @ 2nd floor beams (GL- K & L) 1- Checker
4. Plastering @ service area and second floor masonry works 2-operator(BH 9) (Bobcat)
August 27,2016
5. Fabricatio n of steel bars (Hotel & Ballroom)
6.Installation of ofrmworks @ level 1 (RC wall- 2nd lif) & Domestic tank
7. Rebars works @ level 1 Footings
8. Excavation and Leveling
1.Installation of formworks for beam 1-Engr
2. Plastering @ Second floor & service Area 1- Checker
3. Fabrication of steel bars (Hotel & Ballroom) 2-operator(BH 9) (Bobcat)
4.Rebars works for beam
5. Stripping
August 29,2016
6.Installation of formworks for Retaininmg wall @ level 3
7. Rebars works for retaining wall @ level 3
8. Insatallation of formworks for tie beam @ level 1
9. Rebars works for tie beam @ level 1
10. Welding of dowel for retaining wall @ level 1
1. Plastering @ service area & second floor 1-Engr
2. Installation of formworks for beam 1- Checker
3. Rebars works for beam 2-operator(BH 9) (Bobcat)
4. Fabrication of steel bars (Hotel & Ballroom)
5. Leveling the elevetion of ballroom
August 30,2016 6. Trimming
7. Fabrication of I-Beam
8. Dismantling of formworks @ 2nd floor
9.Installation of formworks @ retaining wall 3rd lif & tie beam
10. Rebars works @ retaining wall 3rd lif & tie beam
11. Welding bar for retaining wall 3rd lif
Daily Activities
Pulsar Event Hall, Tuguegarao City
August 31-September 5,2016
Date Activities Manpower
1.Plastering @ Mezzanine Level & second floor 1-Engr
2. CHB layin @ Roof Deck 1-IT
3. Stripping 2-operator(BH 9) (EX50)(Bobcat)
4. Dismantling of Scaffoldings 5-Driver (DT2) (DT3) (TM16)
5. Sifing grains sand (TM 24) (TM 7)
6. Hauling of cement, wall right and sand
7. Leveling @ ground floor
August 31,2016 8. Painting
9. Erection of roof Framing
10. Concrete pouring @ ledge, beam & column
11. Rebars works @ level 3 (RC wall, footings & columns)
12. Installation of formworks @ level 3 (RC wall, footngs & columns)
13. Fabrication of Steel bars (Hotel & Ballroom)
14. hauling & leveling @ level 3
15. Concrete pouring @ level 1(RC wall-2nd lif ) & domestic tank
1. CHB laying @ Mezzanine level 1-Engr
2. Plastering @ mezzanine level & second floor 1-IT
3. Pouring @ lintel beam 4-operator(BH9)(EX50)(CP2)
4. Hauling & Compaction (Bobcat)
5. Fabrication of steel bars (Hotel & Ballroom) 1-Driver (DT2)
September 1,2016
6. Mock-up of base plate
7. Dismantling of scaffoldings
September 1,2016

8.Rebars works @ level 1 (RC wall-3rd lif ) & domestic tank , Level 3 (RC wall, footings,columns)
9. Installation of formworks @ level 3 (RC wall, footings, columns)
10. Leveling & hauling
1. Installation of scaffoldings 1-Engr
2. Sifing grains sand 1-IT
3. Plastering @ mezzanine level 1- Checker
4. Dismantling of Scaffoldings 4- Operator (BH9) (EX50) (CP2)
5. Hauling & Compaction (Bobcat)
6. Topping of concrete gutter 1-Driver (DT2)
September 2,2016
7. Scratch coating (rebokada) @ second floor
8. Fabrication of steel bars (Hotel & ballroom)
9.Installation of Perforated Pipe
10.Rebars works @ level 1 (RC wall-3rd lif ) & domestic tank , Level 3 (RC wall, footings & Columns)
11. Installation of formworks @ level 3 (RC wall, footings & columns)
12. Leveling & hauling
1. Sifing Grains sand 1-Engr
2. Installation of Formworks 1-IT
3. CHB laying @ service area 1- Checker
4. Concrete topping 3-operator(BH 9) (Bobcat) (EX50)
5. Plastering @ concrete Gutter & service area
6. Fabrication of steel bars (Hotel & Ballroom)
7. Gravel Bedding
September 3,2016 8. Installation of perforated pipe
9. Hauling of aggrigates
10. Cutting of I-beam
11. Hauling of cement & wall right
12. Rebars works @ level 1 (RC wall- 3rd lf), Doestic tank & Level 3 (RC wall, footings& columns)
13. Installation of formworks @ level 3 (RC wall, footings & columns)
14. Dismantling of formworks @ level 1
15. Excavation & leveling
1. Installation of anchor bolt & base plate 1-Engr
2. Excavation & hauling of waste 1- Checker
September 4, 2016
September 4, 2016
1-operator(BH 9)
1- Driver (DT2)
1. Installation of formworks 1-Engr
2. Plastering @Service area, mezzanine level & Concrete gutter 1-IT
3. Dismantling of scaffolfdings 1- Checker
4. Rebars works @ ground floor 2-operator (Bobcat) (EX50)
5. Hauling of Cement & CHB
6. CHB laying @ second Floor
September 5, 2016
7. Fabrication of Steel bars (Hotel & Ballroom)
8. Erection of roof framing
9. Concrete Topping @ gutter
10. Installation of formworks @ level 3 (RC wall, footings,& columns)
11. Rebars works @ level 3 (RC wall , footings & columns)
12. Dismantling of formworks @ level 1 (RC wall)
Date

September 6, 2016

September 7, 2016

September 8, 2016
September 8, 2016

September 9, 2016

September 10,2016
September 12,2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
September 6-12,2016
Activities
1. Plastering @ Service Area and second Floor
2. CHB laying @ Second Floor
3. Dismantling of Scaffoldings
4. Fabrication of steel bars (Hotel & Ballroom)
5. Hauling of sand
6. Installation of formworks @ lintel beam
7. Backfilling @ ground floor
8. Fabrication of C-purlins
9. Installation of formworks @ level 1 (RC wall-3rd if), Domestic tank Level 1 Footings & level 3 (GL-1 t 4 RC wall, Footings, Shear wall & Columns)
10. Rebars works @ level 1 (RC wall-#rd lif), Domestic tank & Level 3 (GL-1 to4 RC wall, footings, shear wall & columns
11. Gravel Bedding
1. Installation of formworks @ Upper Roof beam & planted columns (GL-K & L)
2. Plastering @ service area & second floor (GL-K to L @ dance studio)
3. CHB laying @ second floor (GL-k to L @ Dance studio)
4. Hauling of cement & sand
5. Fabrication of steel bars (Hotel & Ballroom)
6. Backfilling
7. Concrete pouring @ ground floor
8. Installation of formworks @ level 1 (RC wall-3rd if), Domestic tank Level 1 Footings & level 3 (GL-1 t 4 RC wall, Footings, Shear wall & Columns)
9. Rebars works @ level 1 (RC wall-#rd lif), Domestic tank & Level 3 (GL-1 to4 RC wall, footings, shear wall & columns
1. Hauling of Cement
2. Sifing grains sand
3. Plastering @ mezzanine level & second floor
4.Installation of formworks @ roof deck
5. Dismantling of scaffoldings @ canopy foundation
6. Fabrication of steel bars (Hotel & Ballroom)
7. Installation of roof framing
8. Installation of formworks @ level 1 (RC wall-3rd if), Domestic tank Level 1 Footings & level 3 (GL-1 t 4 RC wall, Footings, Shear wall & Columns)
9. Rebars works @ level 1 (RC wall-#rd lif), Domestic tank & Level 3 (GL-1 to4 RC wall, footings, shear wall & columns
10. Hauling
1. Sifing grains sand
2. Installation of of fomworks @ roof deck
3. Rebars works @ roof deck
4. Plastering @ service area (Interior & exterior)
5. CHB laying @ service area
6. Fabrication of steel bars (Hotel & Ballroom)
7. Hauling & Backfilling @ ground floor
8. Installatio of roof framing
9. Installation of formworks @ level 1 (RC wall-3rd lif) & Domestic tank
10. Rebars works @ level 1 (RC wall-#rd lif) & Domestic tank
11. Compaction
12. Installation of Volcanic Clay
1. Installation of fomworks @ roof beam @ gridline K & L - 1 TO 5
2. Plastering of Exterior walls of Mezzanine floor & service area
3. Sifing of grains sand for plastering
4. CHB laying @ Service area on ground floor
5. Fabrication of steel bars (Hotel & Ballroom)
6. Installation of water proof membrane for concrete gutter
7. Leveling/ Backfilling of ground floor level
8. Installation of roof framing @ gymon second floor
9. Installation of forms (3rd lif) of domestic tank & fire water tank
10. Concrete pouring @ level 3 RC wall, footings, Shear wall & columns
1. Installation of forms of Roof Beam @ gridline K & L
2. Plastering @ Exterior walls @ Mezzanine Floor
3. Sifing of grains sand for plastering
4. CHB laying @ Service area on ground floor
5. Fabrication of steel bars (Hotel & Ballroom)
6. Dismantlling of Scaffoldings
7. Leveling of Ground floor Level
8. Cutting of sog rod
9.Installation of forms (3rd lif) of domestic tank & fire water tank
10. Stripping of forms of retaining wall column footing & column @ 3rd lif
11. Installation of (1st lif forms of column below swimming pool @ level 1)
12. Excavation of foundation of Level 3
Manpower
1-Engr
1-IT
1-Checker
2-operator (EX50)(Bobcat)

1-Engr
1-IT
1-Checker
3-operator) (EX50)(CP2) (PC 2)
3-Driver (TM24) (TM16) (TM11)

1-Engr
1-IT
1- Checker
1-Operator (BH 20)

1-Engr
1-IT
1- Checker
2-operator(EX 50) ( CP2)

1-Engr
1-IT
1- Checker
4-operator(EX 50) ( CP2) (Bobcat)
(PC 2)
3- Driver (TM11) (TM16) (TM24)

1-Engr
1-IT
1- Checker
3-operator (Bobcat) (EX50) (BH9)
Daily Activities
Pulsar Event Hall, Tuguegarao City
September 13-18,2016
Date Activities Manpower
1. Installation of forms of Roof Beam @ gridline K & L 1-Engr
2. Plastering @ Exterior walls @ Mezzanine Floor & Service area 1-IT
3. Sifing of grains sand for plastering 1-Checker
4. Fabrication of steel Bars (Hotel & ballroom) 3-operator (EX50)(Bobcat) (BH 9)
5. Leveling of Ground Floor
September 13,2016 6. Cutting of Sog rod
7. Installation of water proof membrane for concrete gutter
8. Installation of (3rd lif) forms of water tank
9. Rebars works @ level 1 & level 3
10. Dismantling of formworks @ Level 3
11. Excavation and Leveling
1. Installation of forms of Roof Beam @ gridline K & L and slab on grade 1-Engr
2. Sifing grains of sand 1-IT
3. CHB laying @ service area 1-Checker
4. Installation of Perforated pipe 2-operator (EX50)(Bobcat)
5. Compaction @ Ground floor
6. Backfilling
September 14,2016
7. Fabrication of steel bars (Hotel & Ballroom)
8. Fabrication of sog rod
9. Rebars works @ slab on grade
10. Installation of sog rod
11. Installation of (3rd lif) forms of water tank
12. Rebars works @ level 1 and level 3
1. Sifing grains of sand 1-Engr
2. Dismantling of formworks 1-IT
3. Plastering @ service area 1- Checker
4. Chipping 2-Operator (EX 50) (CP 2)
5. Rebars works @ slab on grade 2-Driver (TM 11) (TM 24)
6. CHB laying @ service area
7. Installation of batter board
September 15,2016 8. Fabrication of sog rod
9. Installation of sog rod
10. Compaction
11. Lifing of C-purlins
12. Concrete pouring @ slab on grade
13. Installation of (3rd lif) forms of water tank
14. Rebars works @ level 1 and level 3
15. Fabrication of steel bars (Hotel & Ballroom)
1. Dismantling of scaffoldings 1-Engr
2. CHB laing @ service area 1-IT
3. Plastering @ service area 1- Checker
September 16,2016 4. Fabrication of steel Bars (Hotel & ballroom) 2-operator(EX 50) ( Bobcat)
5. Sifing grains of sand
6. Installation of (3rd lif) forms of water tank and level 3
7. Rebars works @ level 3
1. Sifing grains of sand 1-Engr
2. Erection of scaffoldings for roof beam 1-IT
3. Dismantling of scaffoldings of Canopy's support 1- Checker
4. Plastering @ walls @ fuinction room on ground floor 1-operator ( Bobcat)
September 17,2016 5. Installation of forms for slab on grade 2-Driver (TM 11) (TM 24)
6. Installation of (1st lif) forms and rebars @ level 3
7. Installation of (3rd lif) forms of water tank @ level 1
8. Fabrication of steel bars (Hotel)
9. Concrete Pouring @ RC wall, column, & Footing @ leve 3
1. Sifing grains of sand 1-IT
2. Concrete pouring @ Lintel Beam 1- Checker
3. CHB laying @ Ground floor 1-operator (Bobcat)
4. Plastering @ Service Area
September 19,2016 5. Rebars works @ Mezzanine Level
6. Installation of Formworks @ Roof deck
7. Fabrication of steel bars (Hotel & Ballroom)
8. Installation of (1st lif) forms and rebars @ level 3
9. Installation of (3rd lif) forms of water tank @ level 1
Daily Activities
Pulsar Event Hall, Tuguegarao City
September 20-26, 2016
Date Activities Manpower
1.Formworks @ Ground floor & Second floor 1-Engr
2. Leveling & compaction @ Ground floor 1-IT
3. Plastering @ mezzanine loor 1-Checker
September 20,2016 4. Erection of I-Beam for mezzanine framing 2-operator (Bobcat) (STC250)
5. Formworks @ level 1 & level 3
6. Installation of volcanic clay of water tank
7. Fabrication of steel bars (Hotel )
1. Sifing grains of sand 1-Engr
2. Plastering @ service area & second floor 1-IT
3. Gravel bedding 1-Checker
4. Hauling of sand & cement 2-operator (Bobcat) (LD7)
5. Erection of I-beam for mezzanine framing 2-Driver (TM 11) (TM 24)
September 21,2016
6. Rebars works @ roof beam
7. Compaction
8. Formworks @ level 3
9. Rebars works @ level 3
10. Fabrication of steel bars (Hotel)
1. Sifing grains of sand 1-Engr
2. Rebars works @ roof beam & slab on grade 1-IT
3. Formworks @ roof beam 1- Checker
4. Plastering @ roof deck & mezzanine floor 2-Operator (Bobcat) (GR11)
5. Backfilling @ slab on grade
September 22, 2016 6. Compaction
September 22, 2016
7. Hauling of sand & wall right
8. Pouring @ lintel beam
9. Formworks @ level 3
10. Fabrication of steel bars (Hotel)
11. Splice rebars @ column
1. Hauling of sand & wall right 1-Engr
2. Rebars works @ roof beam & slab on grade 1-IT
3. Plastering of parapet walls @ roof deck 1- Checker
4. Formworks @ second floor for new planted column, roof beam & slab on grade 2-operator(EX 50) ( Bobcat)
5. Concrete pouring @ slab on grade 2-Driver (TM 11) (TM 24)
September 23, 2016 6. Sifing grains of sand
7. Concreting of new planted column (1st lif) @ storage area on second floor
8. Gravel bedding @ Ground floor for slab on grade
9. Formworks @ level 3
10. Installation of tie rod for retaining wall @ level 3
11.Fabrication of steel bars (Hotel)
1. Installation of rebars forms for new planted @storage area 1-Engr
2. Plastering of parapet walls @ roof deck 1-IT
3. Watering of concreted slab @ ground floor 1- Checker
4. Stripping of forms of concreted slab on grade 2-operator ( Bobcat) (EX50)
5. Fabrication of steel bars (Hotel & Ballroom)
September 24, 2016 6. Erection of scaffolding as support of additional roof beam @ storage area
7. Gravel Bedding
8. Full welding of beam support for mezzanine
9. Installation of forms for Lintel beam of parapet wall
10. Application of plaster band & scratch coating on columns & beams @ gym
11. Installation of supports for forms of retaining wall @ level 3
1. Installation of rebars forms for new planted @storage area 1-Engr
2. Plasteing of beams & columns @ gym on second floor 1-IT
3. Chipping on existing planted columns for the connection to the additional planted column 1- Checker
4. Fabrication of steel bars (Hotel & Ballroom) 1-operator (Bobcat) (EX50) (BH9)
September 26, 2016
5. Hauling of sand
6. Erection of I-Beam for mezzanine floor framing of function room
September 26, 2016

7. Installation of forms for retaining walls @ level 3


8. Excavation & leveling @ Level 2
Daily Activities
Pulsar Event Hall, Tuguegarao City
September 27-October 3, 2016
Date Activities
1. Plastering of planted column and roof beam @ Caf Gym area & parapet walls, @ new dance studio area
2. Installation of forms & rebars of additional planted column & roof beam @ storage area on 2nd floor
3. Installation of forms of lintel beam @ serviice area
September 27,2016 4. Full weld of mezzanine floor frames @ function rooms
5. Installation of forms of extended slab @ mezzanine fllor
6. Manual concreting of extended slab @ mezzanine floor
7.Installation of 1st lif forms of retaining wall,shearwall and columns.
1.Installation of forms and rebars of planted column and roof beams @ storage area on 2nd floor.
2.CHB laying for parapet wall @ 2nd floor.
3.Fabrication of steel bars
4.Application of epoxy primer to c-purlins
September 28,2016
5.Plastering of walls @ service area
6.Erection of scaffoldings @function area
7.Installation of 1st lif forms of retaining wall,shearwall and columns.
8.Excavation and hauling of excess soil
1.Installation of forms and rebars of planted column and roof beams @ storage area on 2nd floor.
2.Installation of forms and rebars of extended slab @mezzanine floor
3.Manual concreting of extended slab @ mezzanine floor
4.CHB laying @service area
5.Erection of scaffoldings and installation steel decking for function rooms @ mezzanine floor.
September 29, 2016 6.Fabrication of steel bars
7.Full welding of I-beam frames for mezzanine floor function area
8.Plastering of walls @service area
September 29, 2016

9.Adjusting of roof truss elevation @ 2nd floor


10.Installation and welding of tie rods of retaining walls
11.Excavation and stock filing of excess soil
1.Installation of forms and rebars of planted column and roof beams @ storage area on 2nd floor.
2.Manual concreting of extended slab @ mezzanine floor
3.Installation of steel decking for function rooms @ mezzanine floor
4.Concrete topping of gutter @2nd floor
September 30,2016 5.Full welding of I-beams frames for mezzanine floor function area
6.Adjusting of trusses new elavation @ second floor
7. Re-Installation of installed roof frames
8. Plastering of walls @ service area & parapet wall @ second floor
9. Installation & welding of tie rod
1. Installation of forms of roof beam, planted column & ledge @ storage area on second floor
2. Installation of rebars @ function area on mezzanine floor
3. Plasteing of walls @ service area & parapet walls @ new dance studio on second floor
4. manual Excavation for grade beams along grid line L
October 1, 2016
5. Installation of roof frames @ caf and gym area on second floor
6. Installation of forms (Batter board) for slab ongrade @ gridline 1 to 5- K to L
7. Concrete pouring of additional planted column & roof beam @ storage area on second floor
8. Concrete pouring of 1st lif retaining wall and column @ level 3
1.Installation of forms and rebars of planted column and roof beams @ storage area on 2nd floor.
2. Installation of forms (Batter board) for slab on grade @G/L 1 To 5 - K to L
3. Installation of form for extended slab (remaining) @ mezzanine floor
4. Installation of rebars @ function area on mezzanine floor
5. Stripping of forms of concreted columns and roof beams @ second floor
October 3, 2016
6. CHB laying @ roof deck for parapet wall
7. Plastering @ lintel beams @ service area
8. Stripping of form of concreted retaining walls and columns
9. Installation of rebars for (2nd lif) Retaning wall
10. Concrete pouring @ columns,Shear wall & footing tie beam
Manpower
1-Engr
1-IT
1-Checker
2-operator (Bobcat) (EX50)

1-Engr
1-IT
1-Checker
2-operator (Bobcat) (STC250)

1-Engr
1-IT
1- Checker
1-Operator (Bobcat)
1-Engr
1-IT
1- Checker
2-operator (BH9) (Bobcat)

1-Engr
1-IT
1- Checker
2-operator ( Bobcat) (PC2)
3-driver (TM11) (TM13) (TM24)

1-Engr
1-IT
1- Checker
2-operator (Bobcat) (PC2)
3-driver (TM11) (TM13) (TM2)
Daily Activities
Pulsar Event Hall, Tuguegarao City
October 4-10,2016
Date Activities Manpower
1. Hauling of cement and wall right 1-Engr
2. CHB laying @ roof deck 1-IT
3. Plastering 1-Checker
4. Concrete pouring @ slab on grade 2-operator (Bobcat) (BH9)
5. Removal offormworks @ second floor 3-driver (TM11) (TM13) (TM24)
October 4, 2016
6. Fabrication of steel bars (Hotel & ballroom)
7. Installation of roof framing @ second floor
8. Removal of formworks @ level 3 (shear wall, columns & FTB)
9. Installation of formworks & rebars @ level 3 (2nd lif Retaining wall, shear wall & columns)
10. Hauling @ level 2
1. Formworks @ upper roof deck (lintel beam of parapet wall) 1-Engr
2. Removal of formworks @ second floor 1-IT
3. Hauling of cement & wall right 1-Checker
4. Plastering @ second floor (roof beam & concrete gutter) 3-operator (Bobcat)(EX50)(BH9)
5. CHB laying @ ground floor (mock-up partition) 1-driver (DT3)
6. Fabrication of steel bars (Hotel & ballroom)
October 5,2016
7. Installation of roof framing @ second floor
8. Formworks @ storage area (additional planted columns & roof beam)
9. Compaction
10. manual concreting @ lintel beam (parapet wall)
11. Installation of formworks & rebars @ level 3 (2nd lif Retaining wall, shear wall & columns)
12. Hauling @ level 2
1.Plasteing @ upper roof deck (parapet wall and roof beam @ gym) 1-Engr

October 6,2016
2. Removal of formworks @ second floor 1-IT
3. Hauling of cement & wall right 1- Checker
4. CHB laying @ Ground floor (mock-up partition) 3-Operator (Bobcat)(EX50)(CP7)
October 6,2016
5. Fabrication of steel bars (Hotel & Ballroom)
6. Installation of roof frames @ second floor
7. Manual concreting of wall footing
8. Installation of formworks & rebars @ level 3 (2nd lif Retaining wall, shear wall & columns)
1. CHB laying 1-Engr
2. Gravel bedding 1-IT
3. Plastering @ upper roof deck (parapet wall & roof beam) 1- Checker
October 7,2016 4. Hauling of cement & wall right 2-operator (EX50) (Bobcat)
5. Fabrication of steel bars (Hotel & Ballroom)
6. Installation of roof frames @ second floor
7. Installation of formworks & rebars @ level 3 (2nd lif Retaining wall, shear wall & columns)
1. CHB laying @ gound floor (mock-up partition) 1-Engr
2. Plastering @ upper roof deck 1-IT
3. Hauling of cement & wall right 1- Checker
October 8,2016 4.Installation of roof frames 3-operator( Bobcat) (EX50)(BH9)
5. Fabrication of steel bars (Hotel & Ballroom) 2-driver (DT16) (DT2)
6. Installation of formworks & rebars @ level 3 (2nd lif Retaining wall, shear wall & columns)
7. Hauling @ level 2
1. Hauling of CHB and wall right 1-Engr
2. CHB laying @ ground floor (mock-up partition) 1-IT
3. Plastering @ upper roof deck (parapet wall & roof beam) 1- Checker
October 10,2016
4. Pouring @ lintel beam 1-operator( Bobcat)
5. Rebars @ ground floor
6. Installation of formworks & rebars @ level 3 (2nd lif Retaining wall, shear wall & columns)
Daily Activities
Pulsar Event Hall, Tuguegarao City
October 11-17,2016
Date Activities Manpower
1.CHB laying @ ground floor 1-Engr
2. Removal of formworks & scaffoldings @ 2nd floor 1-IT
3. Fabrication of steel bars (Hotel & Ballroom) 1-Checker
October 11,2016
4. Installation of sog rod 2-operator (Bobcat) (BH22)
5. Installation of roofs 2-driver (DT1)(DT16)
6.Formworks & rebars works @ level 4 (Beams,Girders & suspended slab)
1.CHB laying @ mezzanine level 1-Engr
2. Concreting @ lintel beam 1-IT
3. Fabrication of steel bars (Hotel & Ballroom) 1-Checker
October 12,2016
4. Fabrication of roof truss & strut 2-operator (Bobcat)(BH22)
5.Formworks & rebars works @ level 4 (Beams,Girders & suspended slab) 1-driver (DT1)(DT2)(DT3)(DT16)
6. Hauling @level 2 (excess soil)
1. CHB laying @ mezzanine level 1-Engr
2. Plastering @ second floor (wall gutter @ storage area) 1-IT
3. Sifing grains of sand 1-Checker
4. Fabrication of steel bars (Hotel & Ballroom) 3-operator(Bobcat)(BH22)(BH9)(CP7)
5. fabrication of roof frames 3-driver (DT1)(DT6) (DT10)
October 13, 2016 6. Insatallation of roofs
7. Gravel bedding
8. Installlation of moisture barrier (Polythelene sheet)
9.Formworks & rebars work @ level 4 (Beam,girders and suspended slab)
10. Stock filing and hauling @ level 4 (Excess soil)
11. Application of water proofing @ level 3 (Retaining wall)
1. CHB laying @ mezzanine level 1-Engr
2. Plastering @ second floor (gutter) 1-IT
3. Formworks & rebars works @ ground floor (slab on grade) 1- Checker
4. Hauling of sand to second floor 1-operator (Bobcat)
October 14, 2016 5. Fabrication of steel bars (Hotel & Ballroom)
6. Fabrication of roof frames
7. Hauling of roofs to second floor
8. Formworks & rebars work @ level 4 (Bottom beam & suspended slab)
9. Application of water proofing @ level 3 (retaining wall)
1. Plastering @ mezzanine level 1-Engr
2. Fabrication of steel bars 1-IT
October 15,2016
1- Checker
2-operator( Bobcat) (BH9)
1. CHB laying @ mezzanine level 1-Engr
2. Plastering @ ground floor & mezzanine level 1-IT
3. Manual concreting @ second floor (roof beams and planted column) 1- Checker
4. Fabrication of steel bars (Hotel & Ballroom) 2-operator( Bobcat) (BH9)
5. Erection of roof truss 3- driver (TM11)(TM13)(TM2)
6. Rebars works @ level 4 (Columns)
October 17,2016
7. Concrete pouring @ ground floor (slab on grade)
8. Formwork @ level 3 (retaining wall)
9. Installation of sakoline & sand bagging for flood protection & erosion control
10. Dewatering @ level 2
11. Application of water proofing @ level 3 (Retaining wall)
12. Stockfilling of excess soil
s
Daily Activities
Pulsar Event Hall, Tuguegarao City
October 18-24,2016
Date Activities
1. Plastering @ ground floor & mezzanine level (wall @ pre function area)
2. Manual concreting @ second floor (roof beams & planted columns)
3. Sifing of sand grains
4. Fabrication of steel bars (Hotel & Ballroom)
5. Erection of roof strut (@ G/L J to K)
October 18,2016 6. Rebars work @ level 4 (Column)
7. Formworks @ level 3 (Retaining wall )
8. Application of water proofing
9. Stockfilling of excess soil
10. Sheet filing for erosion control
11. Installation of sakoline and ribtype roof as flood protection
1. Plastering @ ground floor & mezzanine level (wall @ pre function area)
2. Sifing of sand grains
3. Fabrication of steel bars (Hotel & Ballroom)
October 19,2016
4. Installation of sakoline and roofs as flood protection & erosion control
5. Concrete pouring @ level 3 (retainintg wall)
6. Installation of sheet pile for erosion control
1. Cleaning & clearing of storm debris
2. Repairing of fallen fence
October 21,2016 3. Repairing of destroyed temfacil

1. Cleaning & clearing of storm debris


2. Repairing of fallen fence
October 22,2016 3. Reparing of destroyed temfacil
4. Dismantling of disaligned rebars

1. Cleaning & clearing of storm debris


2. Repairing of fallen fence
October 24,2016 3. Reparing of destroyed temfacil
4. Dismantling of disaligned rebars
5. Hauling @ Level 2 (Excess Soil)
1. Cleaning & clearing of storm debris
2. Repairing of fallen fence
October 25,2016 3. Reparing of destroyed temfacil
October 25,2016
4. Dismantling of disaligned rebars
5. Hauling @ Level 2 (Excess Soil)
ao City

Manpower
1-Engr
1-IT
1-Checker
3-operator (Bobcat) (BH9) (STC250)
1-Driver (SV5)

1-Engr
1-IT
1-Checker
3-operator (Bobcat)(BH9) (PC2)
3-driver (TM24) (TM2) (SV5)

1-Engr
1-IT
1-Checker
1- operator (BH9)
1- driver (SV5)
1-Engr
1-IT
1- Checker
1-operator (BH 9)
1-Driver (SV5)
1-Engr
1-IT
1- Checker
1-operator (BH 9)
1-Driver (SV5)
1-Engr
1-IT
1- Checker
1-operator (BH 9)
1-Driver (SV5)
Daily Activities
Pulsar Event Hall, Tuguegarao City
October 26-November 1,2016
Date Activities
1. Concreting of roof beams and ledge @ second floor (Comfort room area ) (Manual job mix)
2. Re-installation of dismantled rebars @ level 1 (columns)
October 26,2016 3. Hauling @ level 2 (Excess soil)
4. Formworks @ level 3 (Retaining wall)

1. Concreting of roof beams and ledge @ second floor (Comfort room area ) (Manual job mix)
2.Staging of RSB 's to ballroom
October 27,2016

1. Concreting of roof beams and ledge @ second floor (Comfort room area ) (Manual job mix)
2. Concrete pouring of roof beam , ledge and planted column @ second floor , suspended slab @ mezzanine floor
October 28,2016 3. Staging of warehouse stock to new warehouse
4. Installation of sakoline and support (G.I pipe ) to the wall for erosion control

1. Staging of warehouse stock to new warehouse


2. Cleaning and clearing of formworks strips
October 29,2016

October 31,2016 No Activity


November 1,2016 HOLIDAY
Manpower
1-Engr
1-IT
1-Checker
1-operator (BH9)
1-Driver (SV5)
1-Engr
1-IT
1-Checker
1-Driver (SV5)
1-Engr
1-IT
1-Checker
1- operator (PC2)
3- driver (SV5) (TM 2) (TM13)
1-Engr
1-IT
1- Checker
1-Driver (SV5)
1-Engr
1-IT
1- Checker
1-Driver (SV5)
Daily Activities
Pulsar Event Hall, Tuguegarao City
November 2-8,2016
Date Activities Manpower
November 2,2016 HOLIDAY

1.Removal of formworks @ second floor (Column,Roof beam & ledge) 1-Engr


2. Formworks @ level 4 (Suspended slab) 1-IT
November 3,2016
3. Rebars works @ level 4 (Column) 1-Checker
1-operator (Bobcat)
1. removall of formworks @ seond floor (columns,roof beam & ledge) 1-Engr
2. Formworks @ level 4 (Suspended slab) 1-IT
November 4,2016 3. Rebars works @ level 4 (Column) 1-Checker
4. Fabrication of steel bars 1- operator (Bobcat)
5. Dewatering @ level 2
1. Removal of formworks @ second floor (Columns, roof beam & ledge 1-Engr
2. Hauling of scrap metal 1-IT
3. Hauling of demoslished wall 1- Checker
4. Dismantling of damaged roof frames (C-purlins) 1-operator (Bobcat)
November 5,2016
5. Formworks @ level 4 (Suspended slab)
6. Rebars works @ level 4 (column)
7. Fabrication of steel bars
8. Dewatering
1. Installation of port-a-lif (New location) 1-Engr
2. Applying of metal primer to roof frames (C-purlins) 1-IT
3. Hauling of aggregates to seond floor 1- Checker
November 7,2016
November 7,2016 4. Formworks @ level 3 (Elavator's shear wall) 1-operator (EX50)
5. Formworks @ level 4 (Suspended slab)
6. Rebars works @ level 4 (Suspended slab)
7. Excavation @ level 4 (foundation)
1. Hauling of sand and CHB 1-Engr
2. Installation of ceiling @ management temfacil 1-IT
3. Formworks @ level 4 (Suspended slab) 1- Checker
November 8,2016
4. Rebars works @ level 4 (Suspended slab) 1-operator (EX50)
5. Fabrication of steel bars
6. Excavation @ level 4 (Column footing & FTB)
Date

November 9,2016

November 10,2016

November 11,2016

November 12,2016

November 14,2016

November 15,2016
November 15,2016
Daily Activities
Pulsar Event Hall, Tuguegarao City
November 9-15,2016
Activities
1.Fabrication of roof frames
2. Erection of roof frames
3. Rebars & formworks @ level 4 (Suspended slab)
4. Trimming @ level 4 (Footing tie Beam & Column footing)
5. Gravel Bedding @ Level 4 (Footing tie Beam & column footing)
6. Fabrication of steel bars
1. Fabrication of roof frames
2. Erection of roof frames
3. Installation of sog rod
4. Rebars & formworks @ level 4 (suspended slab)
5. Excavation @ level 2
6. Hauling @ level 2 (Excess soil)
7. Formworks @ Level 4 (Column footing)
8. Rebars @ level 4 (Column footing & column)
9. Fabrication of steel bars
1. Full welding of roof frames
2. Excavation @ level 4 (Stockfile)
3. Formworks & rebars work @ level 4 (Suspended slab)
4. Rebars work @ level 4 (Column & footing tie beam)
5. Fabrication of steel bars
6. Manual Excavation & trimming @ level 3 (eroded soil) for retaining wall
1. Erection of roof truss @ second floor (gym area)
2. Rebars work @ level 4 (Column & footing tie beam)
3. Fabrication of steel bars
4. Manual excavation & trimming @ level 3 (Eroded soil) for retaining wall
1.CHB laying @ 2nd floor (external wall & parapet wall @ storage area)
2. Erection of roof truss @ second floor (gym area)
3.Formworks & rebars work @ level 4 (Suspended slab & beam)
4. Rebars work @ level 4 ( footing tie beam)
5. Clearing of way for pumpcrete location for tommorow's concrete pouring
6. Installation of pipe sleeves for fire protection system
1. Concreting of lintel beam @ 2nd floor (parapet wall @ storage area)
2. Erection of roof truss @ second floor (gym area)
3.Formworks & rebars work @ level 4 (Suspended slab & beam)
4. Cleaning of form strips & dust prior to scheduled concrete pouring
5. Formworks & rebars work @ level 4 (Grade beam)
6. Excavation @ level 2 (Cutting of elevation)
7. Hauling of excess soil @ level 2
8. Concrete pouring of (1) Column footing, footing tie beam , beams & suspended slab @ level 4
(2) Retaining wall ,shear wall & column @ level 3 (2nd lif)
Manpower
1-Engr
1-IT
1-Checker

1-Engr
1-IT
1-Checker
1-Operator (BH 9)
1-Driver (DT 16)

1-Engr
1-IT
1-Checker
1-Operator (BH 4)

1-Engr
1-IT
1-Checker
1-Operator (BH 4)
1-Engr
1-IT
1-Checker
3-Operator (BH 4) (BH9) (EX 50)

1-Engr
1-IT
1-Checker
2-Operator (BH9) (PC2)
6-Driver (DT1)(DT16)(TM11)
(TM2)(TM8) (TM13)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
November 16-22-,2016
Date Activities
1.Fabrication of Steel bars
2. Excavation @ level 2 (cutting of level 2)
November 16,2016 3. Hauling of excess soil @ level 2

1. Fabrication of Steel bars


2. Haulung of excess soil @ level 2
November 17,2016

1.Excavation of temporary
2. Fabrication of additional roof truss
3.Formworks @ level 4 (column)
November 18,2016
4. Fabrication of steel bars
5. Excavation @ level 2 (cutting of level)
6. Hauling of excess soli @ level 2
1.Fabrication of Additional roof truss
2. Formworks @ level 4 (column)
November 19,2016
3. Fabrication of steel bars
4. Excavation @ level 2 (Wall footing & column footing)
1. Fabrication of additional roof truss
November 20,2016 2. Formworks @ level 2 (Wall footing & column footing)
3. Adobe Hard soil Breaking @ level 2
1.Fabrication of Additional roof truss
2. Erection of additional roof truss
3.Formworks @ level 2 (wall footing & column footing)
4. Rebars work @ level 2 (wall footing & columjn footing)]
5. Hauling @ level 2 (excess soil)
November 21,2016
6. Excavation @ level 2 (cutting of level)
7. Removal of formworks @ level 3 & level 4
8. manual excavation @ level 3 (eroded soil)
9. Gravel bedding @ level 2 (wall footing & column footing)
10. Fabrication of steel bars
1.Farbrication of additional roof truss
2. Erection of additional roof truss

November 22,2016
3. Rebars work @ level 2 (column)
4. Removal of fomworks @ level 3 & level 4
November 22,2016
5. Manual excavation @ level 3 (Eroded soil)
6. Fabrication of steel bars
7. Hauling @ level 2(excess soil)
8. (Adobe) Hard soil breaking @ level 2
Manpower
1-Engr
1-IT
1-Checker
1-Operator (BH9)
1-Driver (DT 2)
1-Engr
1-IT
1-Checker
1-Operator (BH9)
1-Driver (DT 1)
1-Engr
1-IT
1-Checker
1-Operator (BH9)
3-Driver (DT 1) (DT2) (DT14)

1-Engr
1-IT
1-Checker
1-Operator (BH9)
1-Operator (BH9)

1-Engr
1-IT
1-Checker
1-Operator (BH9)
2-Driver (DT 1) (DT2)

1-Engr
1-IT
1-Checker
1-Operator (BH9)
2-Driver (DT 1)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
November 23-29,2016
Date Activities Manpower
1.Fabrication and Erection of additional roof truss 1-Engr
2. Repairing of management office 1-IT
3. Re-Staging of RSB to Ballroom 1-Checker
4. Removal of Eroded soil @ level 2 1-Operator (BH9)
November 23,2016 5. Hauling @ level 2 (Eroded soil) 1-Driver (DT 1)
6.Manual Excavation @ level 3 (Eroded soil)
7. Rebars work @ level 2 (Column)
8. Fabrication of steel bars
9. Removal of formworks @ level 3 & level 4
1.Fabrication and Erection of additional roof truss 1-Engr
2. Re-Staging of RSB to Ballroom 1-IT
3.Removal of formworks @ level 3 & level 4 1-Checker
4. Manual excavation @ level 3 (Eroded soil) 1-Operator (BH9)
November 24,2016 5. Rebars work @ level 2 (column) 2-Driver (DT1)(DT3)
6. Fabrication of steel bars
7. Dismantling of Scaffoldings @ level 3
8. Excavation @ level 2(cutting @ level 1)
9. hauling @ level 2 (Excess Soil)
1. Fabriaction and Erection of additional truss 1-Engr
2. Re-Staging of RSB 1-IT
3. Plastering @ second floor (Concrete Gutter @ storage area) 1-Checker
4. Removal of formworks @ level 3 & level 4 2-Operator (BH9) (PC2)
5. Cleaning & clearing @ level 3 (Eroded soil) 3-Driver (DT 1)(TM2)(TM13)
November 25,2016
November 25,2016 6. Re-installation of formworks @ level 2 (wall & column footing)
7. Fabrication of steel bars
8. Excavation @ level 2(cutting @ level 1)
9. hauling @ level 2 (Excess Soil)
10. Dismantling of scaffoldings @ level 3
11. Concrete pouring of column (1st lif) @ level 4, wall footing Retaining wall & column footing @ level 2 , column (2nd lif) @ level 3)
1.Fabrication and Erection of additional roof truss 1-Engr
2. Removal of formworks @ level 2 (wall & column footing), @ level 3 (column-2nd lif) @ level 4 (Column 1st lif) 1-IT
November 26,2016 3. Re-Installation of rebars and formworks @ level 2 (wall footing, column footing Retaining wall & column) 1-Checker
4. Fabrication of steel bars 1-Operator (BH9)
5. Hauling @ level 2 (Eroded soil) 1-Driver (DT 1)
1. Erection of additional truss 1-Engr
2. Application of epoxy primer to roof frames (C-purlins) 1-IT
November 28,2016 3. Hauling/segregation of damage roof 1-Checker
3.Formworks @ level3 (Retaining wall) 1-Operator (BH9)
4. Fabrication of steel bars
1. Erection of additional truss & roof truss @ second floor (Gym area) 1-Engr
2. Application of epoxy primer to roof frames (C-purlins) 1-IT
3.Removal of formworks@ 2nd floor (Concrete ledge) & Stiffener column for parapet wall 1-Checker
November 29,2016 4. Formorks @ level 3 (retaining wall) 1-Operator (BH9)
5. Formworks @ level 4 (Tie beam)
6. Rebars work @ leve 2 (column)
7. Fabrication of steel bars
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
November 30 - December 6,2016
Date Activities Manpower
1. Application of Epoxy Primer to Roof Roof Frames (C-Purlins) 1-Engr
2. Plastering @ Second Floor (Gutter) 1-IT
3. Erection of Scaffolding @ Level 4 1-Checker
November 30, 2016
4. Concrete Pouring of Wall and Column Footing @ Level 2, Retaining wall @ Level 3 and Tie Beam @ level 4 2-Operator (BH9) (PC2)
5. Rebars Work @ level 2 (Retaining Wall) and @ Level 4(Column) 6-Driver (DT 1)(TM13)
6. Fabrication of Steel Bars (TM2)(TM11)(TM7)(SV4)
1. Application of Epoxy Primer to Roof Roof Frames (C-Purlins) 1-Engr
2. Plastering @ Second Floor (Gutter) 1-IT
3. Erection of Additional Truss (Ballroom) and Truss @ Second Floor (Dance Studio Area) 1-Checker
4. Fabrication of Additional Truss and Roof Frames 1-Operator (BH9)
5. Installation of Sag Rod (Ballroom) 1-Driver (DT 1)
December 1, 2016
6. Erection of Scaffolding @ Level 4
7. Formworks @ Mezzanine Level (Beams & Girders)
8. Rebars work @ Lvel 2 (Retaining Wall, Column and Footing Tie Beam)
9. Fabrication of Steel Bars
10. Removal of Formworks of Wall and Column Footing @ Level 2, Retaining wall @ Level 3 and Tie Beam @ level 4
1. Application of Epoxy Primer to Roof Roof Frames (C-Purlins) 1-Engr
2. Erection of Additional Truss (Ballroom) and Truss @ Second Floor (Dance Studio Area) 1-IT
3. Fabrication of Additional Truss and Roof Frames 1-Checker
4. Installation of Sag Rod (Ballroom) 1-Operator (BH9)
5. Erection of Scaffolding @ Level 4
December 2, 2016
6. Formworks @ Mezzanine Level (Beams & Girders)
7. Rebars work @ Lvel 2 (Footing Tie Beam)
8. Formworks @ Level 2 (Retaining Wall)
9. Fabrication of Steel Bars
10. Installation of Sheet Piles @ Level 2
1. Application of Epoxy Primer to Roof Roof Frames (C-Purlins) 1-Engr
2. Formworks @ Mezzanine Level (Beams & Girders) 1-IT
December 3, 2016 3. Formworks @ Level 2 (Retaining Wall) 1-Checker
4. Fabrication of Steel Bars 1-Operator (BH9)
5. Formworks @ Level 4(Suspended Slab)
1. Application of Epoxy Primer to Roof Roof Frames (C-Purlins) 1-Engr
2. Erection of Truss @ Second Floor (Dance Studio Area) , Roof Frames and Additional Truss @ Second Floor ( Gym and Restaurant Area) 1-IT
3. Installation of Sag Rod (Ballroom) 1-Checker
4. Rebars Work @ Mezzanine Level (Columns, Beams & Girders) 3-Operator (BH9) (Bobcat)(BH16)
5. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders)
6. Formworks @ Level 2 (Retaining Wall)
December 5, 2016 7. Rebars work @ Level 4 (Suspended Slab)
8. Installation of Sheet Piles @ Level 2
9. Fabrication of Steel Bars
10. Backfilling @ Level 4 (Foundation)
11. Hauling of Form Strips
12. Dewatering @ Cistern (Water Tank)
11. Formworks @ Cistern (Suspended Slab)
1. Application of Epoxy Primer to Roof Roof Frames (C-Purlins) 1-Engr
2. Erection of Truss @ Second Floor (Dance Studio Area) , Roof Frames and Additional Truss @ Second Floor ( Gym and Restaurant Area) 1-IT
3. Installation of Sag Rod @ Second Floor (Dance Studio Area) 1-Checker
4. Rebars Work @ Mezzanine Level (Columns, Beams & Girders) 3-Operator (BH9) (Bobcat) (PC2)
5. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders)
December 6, 2016
6. Formworks @ Level 2 (Retaining Wall)
7. Fabrication of Steel Bars
8. Backfilling @ Level 4 (Foundation)
9. Dewatering @ Cistern (Water Tank)
10. Formworks & Rebars Work @ Cistern (Suspended Slab)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
December 7 - December 13, 2016

Date Activities Manpower


1. Fabrication of Roof Frames (Additional Rafer & Purlins) @ Gym & Restaurant Area on Second Floor
2. Erection of Roof Frames @ Gym & Restaurant Area on Second Floor
3. Installation of Sag Rods @ Dance Studio on Second Floor 1-Engr
4. Application of Epoxy Primer to Roof Frames 1-IT
5. Rebars Work @ Mezzanine Level (Beams & Girders) 1-Checker
December 7, 2016
6. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders) 3-Operator (BH9) (PC2) (Bobcat)
7. Formworks @ Level 2 (Wall & Column Footing) 3-Driver (TM11)(TM13)(TM02)
8. Excavation @ Level 2 (Foundation)
9. Fabrication of Steel Bars
10. Concrete Pouring @ Level 2 (Retaining Walll and Footing Tie Beam), @ Level 3 (Retaining Wall) & @Level 4 (Suspended Slab)
1. Fabrication of Roof Frames (Additional Rafer & Purlins) @ Gym & Restaurant Area on Second Floor
2. Erection of Roof Frames @ Gym & Restaurant Area on Second Floor 1-Engr
3. Application of Epoxy Primer to Roof Frames 1-IT
December 8, 2016 4. Rebars Work @ Mezzanine Level (Beams & Girders) 1-Checker
5. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders) 1-Operator (Bobcat)
6. Removal of Formworks @ Level 2 (Footing Tie Beam)
7. Fabrication of Steel Bars
1. Fabrication of Roof Frames (Additional Rafer & Purlins) @ Gym & Restaurant Area on Second Floor
2. Erection of Roof Frames @ Gym & Restaurant Area on Second Floor 1-Engr
3. Application of Epoxy Primer to Roof Frames 1-IT
December 9, 2016 4. Rebars Work @ Mezzanine Level (Beams & Girders) 1-Checker
5. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders) 1-Operator (Bobcat)
6. Removal of Formworks @ Level 2 (Reataining Wall)
December 9, 2016

7. Fabrication of Steel Bars


1. Fabrication of Roof Frames (Additional Rafer & Purlins) @ Comfort Rooms on Second Floor
2. Erection of Roof Frames @ Gym & Restaurant Area on Second Floor
3. Application of Epoxy Primer to Roof Frames
4. CHB Laying @ Comfort Room on Second Floor 1-Engr
5. Sifing of Sand Grains 1-IT
December 10, 2016
6. Hauling of Aggregates to Second Floor 1-Checker
7. Rebars Work @ Mezzanine Level (Beams & Girders) 1-Operator (Bobcat)
8. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders)
9. Formworks @ Level 2 (Column)
10 . Rebars Work @ Level 2 (Wall & Column Footing)
1. Full Welding of Roof Frames @ Second Floor (Gym & Restaurant Area)
2. Plastering @ Second Floor ( Roof Beams @ Gym Area & Wall @ Comfort Room
3. Plastering @ Ground Floor (Door Opening) 1-Engr
4. CHB Laying @ Ground Floor 1-IT
December 12, 2016 5. Hauling of New Roofs to Second Floor 1-Checker
6. Rebars and Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders) 2-Operator (Bobcat)(PC2)
7. Rebars Work @ Level 2 ( Reatining Wall & Column) 3-Driver (TM11)(TM13)(TM02)
8. Concrete Pouring of Wall & Column Footing @ Level 2
9. Fabrication of Steel Bars
1. Full Welding of Roof Frames @ Second Floor (Gym & Restaurant Area)
2. Plastering @ Second Floor ( Roof Beams @ Gym Area & Wall @ Comfort Room 1-Engr
3. Plastering @ Ground Floor (Door Opening) 1-IT
December 13, 2016 4. CHB Laying @ Ground Floor 1-Checker
5. Formworks @ Mezzanine Level (Suspended Slab, Beams & Girders) 1-Operator (Bobcat)
6. Formworks @ Level 2 (Retaining Wall)
7. Fabrication of Steel Bars
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
December 14 - December 19, 2016

Date Activities Manpower


1. Full Welding of Roof Frames @ Second Floor (Gym & Restaurant Area)
2. Application of Epoxy Primer on Roof Frames @ Second Floor
3. Plastering @ Second Floor ( Wall @ Comfort Room Area and Roof Beams @ Gym & Restaurant Area)
4. Chb Laying @ Ground Floor 1-Engr
5. Concrete Chipping @ Ground floor (Service Area) 1-IT
December 14, 2016 6. Formworks & Rebars Work @ Mezzanine Level (Suspended, Beams & Girders) 1-Checker
7. Formworks @ Level 2 (Retaining Wall) 3-Operator (BH9) (PC2) (Bobcat)
8. Rebars Works @ Level 2 (Columns) 3-Driver (DT-3)(DT-16)
9. Fabrication of Steel Bars
10. Hauling of Excess Soil @ Level 2

1. Full Welding of Roof Frames @ Second Floor (Gym & Restaurant Area)
2. Application of Epoxy Primer on Roof Frames @ Second Floor
3. Plastering @ Second Floor ( Wall @ Comfort Room Area and Roof Beams @ Gym & Restaurant Area)
4. Chb Laying @ Ground Floor 1-Engr
5. Plastering @ Ground floor (Service Area) 1-IT
6. Concrete Pouring of Columns @ Level 4 and Suspended Slam, Beams & Girders @ Mezzanine Level 1-Checker
December 15, 2016
7. Rebars Work @ Level 2 (Footing Tie Beam) 4-Operator (Bobcat) (BH-09) (PC-02) (BH-19)
8. Formworks @ Level 2 (Retaining Wall) 5-Driver (DT-04)(TM2)(TM11)(TM12)(TM13)
9. Dewatering @ Level 2
10. Fabrication of Steel Bars
11. Hauling of Excess Soil @ Level 2
1. Erection of Purlins @ Second Floor (Comfort Room Area)
2. Fullwelding of Roof Frames @ Second Floor (Comfort Room Area)
3. Demolition of Dis-aligned CHB Wall @ Ground Floor 1-Engr
4.CHB Laying @ Ground Floor 1-IT
5. Plastering @ Second Floor ( Wall @ Comfort Room Area and Roof Beams @ Gym & Restaurant Area) 1-Checker
December 16, 2016
6. Rebars Work& Formworks @ Mezzanine Level (Column 1-Operator (Bobcat) (BH-19)
7. Erection of Scaffolding @ Mezzanine Level 2-Driver (DT-01) (DT-03)
8. Rebars Work @ Level 2 (Sher wall Columns , Footing Tie Beam & Column Footing)
9. Fabrication of Steel Bars
10. Hauling of Excess Soil @ Level 2
1. Fullwelding of Roof Frames @ Second Floor (Comfort Room Area)
2. Installation of Additional Purlin Connector
3. Plastering @ Second Floor ( Wall @ Comfort Room Area and Roof Beams @ Gym & Restaurant Area) 1-Engr
4. Plastering @ Ground Floor (Service Area) 1-IT
5. Erection of Scaffolding @ Ground Floor (Additional Bridge)
December 17, 2016 6. Formworks @ Mezzanine Level (Column) 1-Checker
7. Erection of Scaffolding @ Mezzanine Level 2-Operator (Bobcat) (BH-19)
8. Formworks & Rebars Work @ Level 2 (Sher wall Columns , Footing Tie Beam & Column Footing) 2-Driver (DT-01) (DT-03)
9. Hauling of Excess Soil @ Level 2
10. Formworks & Rebars Work @ Water Tank ( Suspended Slab)
11. Fabrication of Steel Bars
1. Full Welding of Roof Frames @ Second Floor (Comfort Room Area)
2. Plastering @ Second Floor ( Roof Beams @ Gym Area & Restaurant Area and Wall @ Comfort Room)
3. Plastering @ Ground Floor (Service Area) 1-Engr
4. Installation of Roofs 1-IT
December 19, 2016 5. Formworks @ Level 5 ( Beams & Girders) 1-Checker
6. Erection of Scaffolding @ Mezzanine Level 2-Operator (Bobcat) (BH-09)
7. Formworks & Rebars Work @ Level 2 (Sher wall Columns , Footing Tie Beam & Column Footing) 1-Driver (SV-04)
8. Formworks & Rebars Work @ Water Tank ( Suspended Slab)
9. Fabrication of Steel Bars
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
December 20 - December 22, 2016

Date Activities
1. Full Welding of Roof Frames @ Second Floor (Comfort Room Area)
2. Plastering @ Second Floor ( Roof Beams @ Gym Area & Restaurant Area and Wall @ Comfort Room)
3. Plastering @ Ground Floor (Service Area)
4. Installation of Roofs
December 20, 2016 5. Formworks @ Level 5 ( Beams & Girders)
6. Erection of Scaffolding @ Mezzanine Level
7. Formworks & Rebars Work @ Level 2 (Sher wall Columns , Footing Tie Beam & Column Footing)
8. Formworks & Rebars Work @ Water Tank ( Suspended Slab)
9. Fabrication of Steel Bars
1. CHB Laying @ Ground Floor & Mezzanine Floor
2. Plastering @ Ground Floor (Service Area)
3. Formworks @ Level 5 ( Beams & Girders)
December 21, 2016 4. Erection of Scaffolding @ Mezzanine Level
5. Formworks & Rebars Work @ Water Tank ( Suspended Slab)
6. Concrete Pouring of Columns @ Level 1 and Retaining Wall, Shear Wall, Columns, Column Footing & Footing Tie Beam
7. Fabrication of Steel Bars
1. CHB Laying @ Ground Floor & Mezzanine Floor
2. Plastering @ Ground Floor (Service Area)
3. Formworks @ Level 5 ( Beams & Girders)
4. Erection of Scaffolding @ Mezzanine Level
December 22, 2016
5. Formworks & Rebars Work @ Water Tank ( Suspended Slab)
6. Removal of Formworks of Columns @ Level 1 and Retaining Wall, Shear Wall, Columns, Column Footing & Footing Tie Beam
December 22, 2016

7. Fabrication of Steel Bars


Manpower
1-Engr
1-IT
1-Checker
1-Operator(Bobcat)

1-Engr
1-IT
1-Checker
2-Operator (Bobcat) (PC-02)
6-Driver (TM2)(TM11)(TM12)(TM13)(TM22)(TM7)

1-Engr
1-IT
1-Checker
1-Operator (Bobcat)(BH-1)
1-Driver (DT-16)
eam
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
Januyary 4 - January 10, 2017

Date Activities
1. Plastering @ Ground Floor (Service Area)
2.CHB Laying @ Second Floor
3. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
4. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab
5. Stripping of Formworks @ Mezzanine Level (Suspended Slab)
January 4, 2017
6. Dismantling of Suspended Slab Support (Scaffoldings) @ Mezzanine Level
7. Fabrication of Steel Bars
8 Excavation @ Level 2
9. Fabrication of Steel Bars

1. Plastering @ Ground Floor (Service Area)


2.CHB Laying @ Second Floor
3. Installation of Gutter's Downspout
4. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 5, 2017 5. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab
6. Stripping of Formworks @ Mezzanine Level (Suspended Slab)
7. Dismantling of Suspended Slab Support (Scaffoldings) @ Mezzanine Level
8. Fabrication of Steel Bars

1. Plastering @ Ground Floor (Service Area)


2.CHB Laying @ Second Floor
3. Installation of Gutter's Downspout

January 6, 2017
4. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 6, 2017 5. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab
6. Stripping of Formworks @ Mezzanine Level (Suspended Slab)
7. Dismantling of Suspended Slab Support (Scaffoldings) @ Mezzanine Level
8. Fabrication of Steel Bars
9. Excavation @ Level 2
1. CHB Laying @ Ground Floor & Mezzanine Floor
2. Plastering @ Ground Floor (Service Area)
3. Formworks @ Level 5 ( Beams & Girders)
4. Erection of Scaffolding @ Mezzanine Level
January 7, 2017
5. Formworks & Rebars Work @ Water Tank ( Suspended Slab)
6. Removal of Formworks of Columns @ Level 1 and Retaining Wall, Shear Wall, Columns, Column Footing & Footing Tie Beam
7. Fabrication of Steel Bars

1. Plastering @ Second Floor


2. Installation of Gutter's Downspout
3. Erection of Scaffolding for Erection of High Ceiling @ Ballroom's Lobby
4. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 9, 2017 5. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab
6. Stripping of Formworks @ Mezzanine Level (Suspended Slab)
7. Dismantling of Suspended Slab Support (Scaffoldings) @ Mezzanine Level
8. Fabrication of Steel Bars
9. Compaction prior to Schecduled Concrete Pouring
1. Plastering @ Second Floor
2. Installation of Gutter's Downspout
3. Erection of Scaffolding for Erection of High Ceiling @ Ballroom's Lobby
4. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
5. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab
January 10, 2017 6. Stripping of Formworks @ Mezzanine Level (Suspended Slab)
7. Dismantling of Suspended Slab Support (Scaffoldings) @ Mezzanine Level
8. Fabrication of Steel Bars
9. Excavation @ Level 2
10. Compaction prior to Schecduled Concrete Pouring
11. Concrete Pouring of Columns, Footing Tie Beam and Shear Wall @ Level 2
Manpower
1-Engr
1-IT
1-Checker
1-Operator(BH-13)

1-Engr
1-IT
1-Checker

1-Engr
1-IT
1-Checker
1-Operator (BH-13)

1-Engr
1-IT
1-Checker
1-Operator (BH-13)

eam

1-Engr
1-IT
1-Checker
1-Operator (CP-10)

1-Engr
1-IT
1-Checker
1-Operator (CP-10)(BH-13)(PC-02)
4-Driver (TM-11)(TM-22)(TM-12)(TM-02)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
January 11-17,2017

Date Activities
1. Plastering @ Second Floor (Roof Beams & Planted Column)
2. CHB Laying & Plastering @ Mezzanine Floor (Window Opening)
3. Installation of Gutter's Downspout
4. Fabrication of Roof Framing for Ballroom's Lobby (Roof Truss)
5. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
6. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab)
January 11, 2017
7. Stripping of Formworks @ Mezzanine Level (Suspended Slab)
8. Dismantling of Suspended Slab Support (Scaffoldings) @ Mezzanine Level
9. Stripping of Forms @ Level 2 (Column Footing, Footing Tie Beam & Shear Wall)
10. Fabrication of Steel Bars
11. Excavation @ Level 1 (Foundation) and Cutting of Level 2
12. Hauling of Excess Soil @ Level 2
1. Plastering @ Second Floor (Roof Beams & Planted Column)
2. CHB Laying & Plastering @ Mezzanine Floor (Window Opening)
3. Installation of Gutter's Downspout
4. Fabrication of Roof Framing for Ballroom's Lobby (Roof Truss)
5. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 12, 2017 6. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab)
7. Formworks @ Level 1 (Column Footing & Retaining Wall Footing)
8. Gravel Bedding @ Level 1 (Column Footing & Retaining Wall Footing)
9. Stripping of Forms @ Level 2 (Column Footing, Footing Tie Beam & Shear Wall)
10. Fabrication of Steel Bars
11. Excavation & Backfilling @ Level 2
1. Plastering @ Second Floor (Roof Beams & Planted Column)
2. CHB Laying & Plastering @ Mezzanine Floor (Window Opening)
3. Installation of Gutter's Downspout
4. Fabrication of Roof Framing for Ballroom's Lobby (Roof Truss)
5. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 13, 2017 6. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab)
7. Formworks @ Level 1 (Column Footing & Retaining Wall Footing)
8. Rebars Work @ Level 1 (Columns, Retaining Wall and Column Footing & Retaining Wall Footing)
9. Stripping of Forms @ Level 2 (Column Footing, Footing Tie Beam & Shear Wall)
10. Fabrication of Steel Bars
11. Excavation & Backfilling @ Level 2
1. Plastering @ Second Floor (Roof Beams & Planted Column)
2. CHB Laying & Plastering @ Mezzanine Floor (Window Opening)
3. Installation of Gutter's Downspout
4. Fabrication of Roof Framing for Ballroom's Lobby (Roof Truss)
5. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 14, 2017
6. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab)
7. Formworks @ Level 1 (Column Footing & Retaining Wall Footing)
8. Rebars Work @ Level 1 (Columns, Retaining Wall and Column Footing & Retaining Wall Footing)
9. Erection of Scaffolding for Support of Formworks @ Level 3
11. Excavation & Backfilling @ Level 2
1. Plastering @ Second Floor (Roof Beams & Planted Column)
2. CHB Laying & Plastering @ Mezzanine Floor (Window Opening)
3. Installation of Gutter's Downspout
4. Fabrication and Erection of Roof Framing for Ballroom's Lobby (Roof Truss)
5. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 16, 2017 6. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab)
7. Formworks @ Level 1 (Column Footing & Retaining Wall Footing)
8. Concrete Pouring @ Leve1 (Wall & Column Footing and @ Level 2 (Shear Wall Footing)
9. Formworks of Beams and Girders for Level 3
10. Fabrication of Steel Bars
11. Excavation & Backfilling @ Level 2
1. Plastering @ Second Floor (Roof Beams & Planted Column)
2. CHB Laying & Plastering @ Mezzanine Floor (Window Opening)
3. Installation of Gutter's Downspout
4. Fabrication and Erection of Roof Framing for Ballroom's Lobby (Roof Truss)
5. Formworks @ Level 5 ( Beams & Girders & Suspended Slab)
January 17, 2017 6. Rebars Work @ Level 5 (Beams & Girders, Columns & Suspended Slab)
7. Formworks @ Level 1 (Column Footing & Retaining Wall Footing)
8. Gravel Bedding @ Level 1 (Column Footing & Retaining Wall Footing)
9. Formworks of Beams and Girders for Level 3
10. Fabrication of Steel Bars
11. Excavation & Backfilling @ Level 2
Manpower
2-Engr
1-IT
1-Checker
1-Operator(BH-13)

2-Engr
1-IT
1-Checker
2-Engr
1-IT
1-Checker

2-Engr
1-IT
1-Checker
1-Operator (BH-13)

2-Engr
1-IT
3-Operator (BH-13) (ST-250) (PC-02)
6-Driver (TM-11) (TM-02) (TM-13) (TM-12)

2-Engr
1-IT
2-Operator (BH-13) (ST-250)
1-Driver (DT-03)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
January 18 - 24, 2017

Date Activities
1. Erection of Roof Trusses of Ballroom's Lobby
2. Plastering of Walls of Pre-Function Area
3. Manual Excavation of Dranaige Lines
4. Rebars Work and Formworks @ Level (Concrete Ledge)
5. Fabrication of Temporary Gutter for Concrete Pouring
January 18, 2017
6. Rebars Work @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
7. Formworks @ Level 3 (Suspended Slab)
8. Rebars Work @ Level 1 (Columns and Retaining Wall)
9. Fabrication of Steel Bars
10. Hauling of Excess Soil @ Level 2
1. Installation of Roof Purlins of Ballroom's Lobby
2. Plastering of Walls of Pre-Function Area
3. Manual Excavation of Dranaige Lines
4. CHB Laying @ Parapet Wall on Upper Roof Deck (Additional Height)
5. Rebars Work and Formworks @ Level (Concrete Ledge)
January 19, 2017 6. Fabrication of Temporary Gutter for Concrete Pouring
7. Formworks @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
8. Formworks @ Level 3 (Suspended Slab)
9. Formworks @ Level 1 (Columns, Retaining Wall and Footing Tie Beam)
10. Fabrication of Steel Bars
11. Excavation and Hauling of Excess Soil @ Level 2
1. Installation of Roof Purlins of Ballroom's Lobby
2. Plastering of Walls of Pre-Function Area
3. Manual Excavation of Dranaige Lines
4. CHB Laying @ Parapet Wall on Upper Roof Deck (Additional Height)
5. Concrete Pouring on Suspended Slab, Beams & Girder @ Level 5 and Columns @ Mezzanine (Level 4)
January 20, 2017
6. Formworks @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
7. Rebars Work @ Level 3 (Beams & Girders)
8. Formworks @ Level 1 (Columns, Retaining Wall and Footing Tie Beam)
9. Fabrication of Steel Bars
10. Excavation and Hauling of Excess Soil @ Level 2
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. Manual Excavation of Dranaige Lines
4. CHB Laying @ Parapet Wall on Upper Roof Deck (Additional Height)
5. Concrete Breaking of Walls @ Mezzanine Floor for Window Opening (Due to Revision of Plan)
6. Formworks for Stiffener Column @ Parapet Wall on Upper Roof deck
January 21, 2017 7. Formworks @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
8. Rebars Work @ Level 3 (Beams & Girders)
9. Formworks @ Level 1 (Columns, Retaining Wall and Footing Tie Beam)
10. Fabrication of Steel Bars
11. Excavation of Retaining Wall's Foundation of Level 2
12. Hauling of Excess Soil @ Level 2
13. Backfilling of Excess Soil @ Level 1
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. Manual Excavation of Dranaige Lines
4. Concreting of Stiffener Column of Parapet Wall on Upper Roof Deck
5. Concrete Breaking of Walls @ Mezzanine Floor for Window Opening (Due to Revision of Plan)
6. Formworks @ Level 2 (Shear Wall and Retaining Wall)
January 23, 2017 7. Rebars Work @ Level 3 (Beams & Girders)
8. Formworks @ Level 1 (Columns, Retaining Wall and Footing Tie Beam)
9. Fabrication of Steel Bars
10. Dismantling of Supports(Scaffolding) of Mezzanine Forms (Suspended Slab, Beams and Girders)
11. Removal of Forms @ Level 5 (Beams and Girders)
12. Excavation of Retaining Wall's Foundation of Level 2
13. Hauling of Excess Soil @ Level 2
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. Manual Excavation of Dranaige Lines
4. Concreting of Stiffener Column of Parapet Wall on Upper Roof Deck
5. Constructing of New Temfacil for Pulsar Site Engineer
6. Formworks @ Level 2 (Shear Wall and Retaining Wall)
January 24, 2017
7. Rebars Work @ Level 3 (Beams & Girders)
8. Formworks @ Level 1 (Columns, Retaining Wall and Footing Tie Beam)
9. Fabrication of Steel Bars
10. Excavation of Retaining Wall's Foundation of Level 2
11. Backfilling @ Level 1
12. Compaction @ Level 1 (Slab on Grade)
Manpower
2-Engr
1-IT
2-Operator(BH-13)(STC-250 Crane)
1-Driver (DT-03)

2-Engr
1-IT
1-Operator(BH-13)
1-Driver (DT-03)

2-Engr
1-IT
2-Operator(BH-13) (PC-02)
7-Driver (DT-03)(TM-02)(TM-10)(TM-11)(TM-12)(TM-13)(TM-22)

2-Engr
1-IT
2-Operator(BH-13)(BH-16)
1-Driver (DT-03)

2-Engr
1-IT
2-Operator(BH-13)(BH-16)
1-Driver (DT-01)

2-Engr
1-IT
3-Operator(BH-13)(BH-16)(Bobcat)
1-Driver (DT-01)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
January 25 - 31, 2017

Date Activities
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
4. Plastering of Walls and Window Opening @ Mezzanine Floor
5. Constructing of New Temfacil for Pulsar Site Engineer
January 25, 2017
6. Rebars Work @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
7. Rebars Work @ Level 3 (Suspended Slab)
8. Rebars Work @ Level 1 (Columns and Retaining Wall)
9. Fabrication of Steel Bars
10. Hauling of Excess Soil @ Level 2
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
4. Plastering of Walls and Window Opening @ Mezzanine Floor
5. Constructing of New Temfacil for Pulsar Site Engineer
6. Concrete Pouring @ Level 1 (Footing Tie Beam, Columns and Retaining Wall) and @ Level 2
January 26, 2017 (Footing Tie Beam, Shear Wall and Retaining Wall)
7. Formworks @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
8. Rebars Work @ Level 3 (Suspended Slab)
9. Formworks @ Level 1 (Columns) and @ Level 2 (Beams and Girders)
10. Fabrication of Steel Bars
11. Excavation and Hauling of Excess Soil @ Level 2
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
4. Plastering of Walls and Window Opening @ Mezzanine Floor
5. Constructing of New Temfacil for Pulsar Site Engineer
6. Formworks @ Level 2 (Column Footing and Wall Footing)
January 27, 2017
7. Gravel Bedding @ Level 2
8. Rebars Work @ Level 3 (Beams & Girders)
9. Formworks @ Level 2 (Suspended Slab)
10. Fabrication of Steel Bars
11. Backfilling @ Level 4 Foundation
12. Excavation and Hauling of Excess Soil @ Level 2
1. Fullwelding and Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
4. Plastering of Walls @ Mezzanine Floor
5. Constructing of New Temfacil for Pulsar Site Engineer
January 28, 2017 6. Formworks @ Level 2 (Suspended Slab)
7. Formworks @ Level 3 (Suspended Slab)
8. Rebars Work @ Level 3 (Suspended Slab, Beams & Girders)
9. Formworks @ Level 1 (Columns, Retaining Wall and Footing Tie Beam)
10. Rebars Work and Manual Concreting @ Level 4 (Suspended Slab)
11. Fabrication of Steel Bars
1. Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
January 30, 2017 4. Plastering of Walls @ Mezzanine Floor
5. Constructing of New Temfacil for Pulsar Site Engineer
6. Rebars Work @ Level 3 (Beams & Girders)
7. Fabrication of Steel Bars
1. Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
4. Plastering of Walls @ Mezzanine Floor
5. Constructing of New Temfacil for Pulsar Site Engineer
January 31, 2017
January 31, 2017 6. Formworks @ Level 2 (Column Footing and Wall Footing)
7. Rebars Work @ Level 2 (Wall Footing, Column Footing and Retaining Wall)
8. Rebars Work @ Level 3 (Beams & Girders)
9. Formworks @ Level 2 (Suspended Slab)
10. Fabrication of Steel Bars
11. Gravel Bedding @ Level 2 Foundation
City

Manpower
2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
2-Driver (DT-01) (SV-16)

2-Engr
1-IT
3-Operator (BH-13)(Bobcat)(PC-02)
7-Driver (SV-16)(DT-01)(TM-02)(TM-10)(TM-11)(TM-13)(TM-22)
2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
2-Driver (DT-01)(SV-16)

2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
1-Driver (SV-16)

2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
1-Driver (SV-16)

2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
1-Driver (SV-16)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
February 1 - 7, 2017

Date Activities
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Mezzanine Floor
February 1, 2017
3. Plastering of Walls, Columns and Beams @ Mezzanine Floor
4. Fabrication of Steel Bars
1. Painting of Roof Frames @ Second Floor
2. Plastering of Walls of Pre-Function Area
3. CHB Laying @ Mezzanine Floor
4. Plastering of Walls, Columns and Beams @ Mezzanine Floor
February 2, 2017
5. Constructing of New Temfacil for Pulsar Site Engineer
6. Formworks @ Level 2 (Shear Wall, Retaining Wall, Column & Footing Tie Beam)
8. Rebars Work @ Level 3 (Suspended Slab, Beams and Girders)
10. Fabrication of Steel Bars
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Mezzanine Floor
3. Plastering of Walls, Columns and Beams @ Mezzanine Floor
4. Rebars Work @ Level 2 (Column Footing, Wall Footing and Retaining Wall)
5. Formworks @ Level 2 (Shear Wall, Retaing Wall, Column Footing and Wall Footing)
February 3, 2017
6. Rebars Work @ Level 3 (Beams and Girders)
7. Dewatering @ Level 2 Foundation
8. Formworks @ Level 2 (Suspended Slab)
9. Fabrication of Steel Bars
10. Excavation and Hauling of Excess Soil @ Level 2
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Mezzanine Floor
2/4/2017 3. Plastering of Walls, Columns and Beams @ Mezzanine Floor
4. Rebars Work @ Level 2 (Column Footing, Wall Footing and Retaining Wall)
5. Formworks @ Level 3 (Suspended Slab)
6. Rebars Work @ Level 3 (Columns)
7. Dewatering @ Level 2 Foundation
. 8. Manual Hauiling of Eroded Soil @ Level 2
9. Concrete Pouring of Wall Footing and Column Footing @ Level 2 Foundation
10. Fabrication of Steel Bars
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Mezzanine Floor
3. Plastering of Walls, Columns and Beams @ Mezzanine Floor
4. Formworks @ Level 2 (Retaining Wall)
5. Rebars Work @ Level 2 (Column Footing, Wall Footing and Retaining Wall)
February 6, 2017
6. Formworks @ Level 3 (Suspended Slab)
7. Rebars Work @ Level 3 (Columns)
8. Dewatering @ Level 2 Foundation
9. Manual Hauiling of Eroded Soil @ Level 2
10. Fabrication of Steel Bars
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Mezzanine Floor
3. Plastering of Walls, Columns and Beams @ Mezzanine Floor
4. formworks and Rebars work @ Level 2 (Retaining wall)
5. Formworks @ Level 3 (Suspended Slab)
February 7, 2017
6. Rebars Work @ Level 3 (Columns)
7. Rebars Work @ Level 4 (Beams and Girders)
7. Concrete Pouring @ Level 2 (Columns, Retaining Wall, Elevetor's Shear)
and @ Level 3 (Suspended Slab, Beams and Girders)
8. Fabrication of Steel Bars
City

Manpower
2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
1-Driver (SV-16)
2-Engr
1-IT
3-Operator (BH-13)(Bobcat)(PC-02)
1-Driver (SV-16)

2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
2-Driver (DT-10)(SV-16)
2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
1-Driver (SV-16)

2-Engr
1-IT
3-Operator (BH-13)(Bobcat)(PC-02)
5-Driver (SV-16)(TM-13)(TM-14)(TM-11)(TM-10)

2-Engr
1-IT
3-Operator (BH-13)(Bobcat)(PC-02)
7-Driver (SV-04)(TM-22)(TM-14)(TM-11)(TM-02)(TM-10)(TM-13)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
February 8 - 14, 2017

Date Activities
1. Plastering of Walls of Pre-Function Area
2. Plastering of Walls @ Mezzanine Floor
3. Installation of Roof of Ballroom (Remaining)
February 8, 2017 4. Installation of Forms of Retaining Wall @ Level 2
5. Erection of Scaffoldings for support for Level 4 (Slab & Beams)
6. Installation of Forms @ Level 3 (Columns)
7. Fabrication of Steel Bars
1. Plastering of Walls of Pre-Function Area
2. Plastering of Walls @ Mezzanine Floor
3. Hualing of Roof to Second Floor
4. Installation of Forms of Retaining Wall @ Level 2
February 9, 2017 5. Installation of Rebars of Columns @ Level 2
6. Erection of Scaffoldings for support for Level 4 (Slab & Beams)
7. Installation of Forms @ Level 3 (Columns)
8. Fabrication of Steel Bars
9. Manual Excavation/Trimming @ Level 2(Tie Beams)
1. Plastering of Walls of Pre-Function Area
2. Plastering of Walls @ Mezzanine Floor
3. Installation of Forms of Retaining Wall @ Level 2
4. Installation of Rebars of Columns and Tie Beams @ Level 2
5. Erection of Scaffoldings for support for Level 4 (Slab & Beams)
February 10, 2017 6. Installation of Forms @ Level 4 (Beams & Girders)
February 10, 2017
7. Installation of Forms @ Level 3 (Columns)
8. Fabrication of Steel Bars
9. Backfilling of Soli @ Level 4 Foundation
10. Excavation of Foundation @ Level 2 (Footings)
11. Hauling of Excess Soil @ Level 2
1. Plastering of Walls of Pre-Function Area
2. Plastering of Walls @ Mezzanine Floor
3. Installation of Forms of Retaining Wall @ Level 2
4. Installation of Rebars of Columns and Tie Beams @ Level 2
5. Erection of Scaffoldings for support for Level 4 (Slab & Beams)
6. Installation of Forms @ Level 4 (Beams & Girders)
February 11, 2017 7. Installation of Forms @ Level 4 (Beams and Suspended Slab)
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4 Foundation
10. Gravel Bedding @ Level 2 (Column Footings and Footing Tie Beam)
11. Hauling of Excess Soil @ Level 2
12. Dismantling of Scaffoldings @ Mezzanine Level 4
13. Concrete Pouring @ Level 2 (Retaining Wall)
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Service Area on Ground Floor (Window Opening)
3. Plastering @ Mezzanine Floor (Columns and Window Opening)
4. Installation of Rebars of Columns and Tie Beams @ Level 2
5. Installation of Formworks @ Level 2 (Column Footings and Footing Tie Beam)
6. Installation of Forms @ Level 4 (Beams & Girders)
February 13, 2017
7. Installation of Rebars @ Level 4 (Beams and Girders)
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4 Foundation
10. Fabrication of Steel Bars
11. Removal of Forms @ Level 2 (Retaining Wall)
12. Gravel Bedding @ Level 2 (Column Footings and Footing Tie Beam)
1. Plastering of Walls of Pre-Function Area
2. CHB Laying @ Service Area on Ground Floor (Window Opening)
3. Plastering @ Mezzanine Floor (Columns and Window Opening)
4. Installation of Rebars of Columns and Tie Beams @ Level 2
5. Installation of Formworks @ Level 2 (Column Footings and Footing Tie Beam)
February 14, 2017
February 14, 2017 6. Installation of Forms @ Level 4 (Beams & Girders)
7. Installation of Rebars @ Level 4 (Beams and Girders)
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4 Foundation
10. Removal of Forms @ Level 2 (Retaining Wall)
11. Gravel Bedding @ Level 2 (Column Footings and Footing Tie Beam)
City

Manpower
2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
2-Operator (Bobcat)(STC-250)
1-Driver (SV-04)

2-Engr
1-IT
2-Operator (BH-13)(Bobcat)
2-Driver (DT-01)(SV-04)
2-Engr
1-IT
3-Operator (BH-13)(Bobcat)(PC-02)
5-Driver (SV-04)(TM-13)(TM-22)(TM-11)(TM-10)

2-Engr
1-IT
2-Operator (Bobcat)(BH-13)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
February 15 - 21, 2017

Date Activities
1. Plastering @ Holding Area on Mezzanine Floor (Exterior Walls & Window Opening)
2. Concrete Chipping for Plastering Preparation @ Mezzanine Floor (Columns & Beams)
3. Sifing of Grains of Sand for Plastering
4. Installation of Formworks @ Level 2 (Retaining Wall, Column Footings and Footing Tie Beam)
5. Installation of Rebars @ Level 2 (Columns)
February 15, 2017
6. Installation of Formworks @ Level 4 (Suspended Slab, Beams & Girders)
7. Fabrication of Steel Bars
8. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
9. Backfilling of Soil @ Level 4 Foundation
10. Concrete Pouring on Column Footing and Footing Tie Beam @ Level 2 Foundation
1. Plastering @ Holding Area on Mezzanine Floor (Columns, Walls & Window Opening)
2. Concrete Chipping for Plastering Preparation @ Mezzanine Floor (Columns & Beams)
3. Sifing of Grains of Sand for Plastering
4. Installation of Formworks @ Level 2 (Retaining Wall)
5. Installation of Rebars @ Level 2 (Columns)
February 16, 2017
6. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
7. Fabrication of Steel Bars
8. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
9. Backfilling of Soil @ Level 4 Foundation
10. Removal of Formworks @ Level 2 (Column Footing and Footing Tie Beam)
1. Plastering @ Holding Area on Mezzanine Floor (Columns, Walls & Window Opening)
2. Concrete Chipping for Plastering Preparation @ Mezzanine Floor (Columns & Beams)
3. Sifing of Grains of Sand for Plastering
4. Erection of I-beam for Additional Support of Stair Opening @ Mezzanine Floor
5. Installation of Formworks @ Level 2 (Columns and Retaining Wall)
February 17, 2017 6. Installation of Rebars @ Level 2 (Columns)
7. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
8. Fabrication of Steel Bars
9. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
10. Backfilling of Soil @ Level 4 Foundation
11. Dismantling of Remaining Scaffolding @ Mezzanine Level
1. Concrete Chipping for Plastering Preparation @ Pre-Function Area (Columns)
2. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
3. Sifing of Grains of Sand for Plastering
4. Erection of I-beam for Additional Support of Stair Opening @ Mezzanine Floor
5. Installation of Formworks @ Level 2 (Columns and Retaining Wall)
February 18, 2017
6. Installation of Rebars @ Level 4 (Suspended Slab)
7. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
8. Fabrication of Steel Bars
9. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
10. Backfilling of Soil @ Level 2 and Level 4 Foundation
1. Concrete Chipping for Plastering Preparation @ Pre-Function Area (Columns)
2. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
3. Sifing of Grains of Sand for Plastering
4. Plastering @ Pre-Function Area (Columns)
5. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
6. Installation of Formworks @ Level 2 (Columns and Retaining Wall)
February 20, 2017 7. Installation of Rebars @ Level 4 (Suspended Slab)
8. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
9. Fabrication of Steel Bars
10. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
11. Backfilling of Soil @ Level 4 Foundation
12. Removal of Eroded Soil @ Retaining Wall Forms
13. Concrete Pouring on Columns and Retaing Wall @ Level 2
1. Concrete Chipping for Plastering Preparation @ Pre-Function Area (Columns)
2. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
3. Sifing of Grains of Sand for Plastering
4. Plastering @ Pre-Function Area (Columns)
5. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
February 21, 2017 6. Installation of Rebars @ Level 4 (Suspended Slab)
7. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
8. Fabrication of Steel Bars
9. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
10. Backfilling of Soil @ Level 4 Foundation
11. Removal of Forms @ Level 2 (Columns and Retaining Wall)
ity

Manpower
2-Engr
1-IT
2-Operator (Bobcat)(PC-2)
5-Driver (SV-04)(TM-14)(TM-11)(TM-2)(TM-13)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
2-Operator (BH-9)(Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
2-Operator (Bobcat)(PC-2)
5-Driver (SV-04)(TM-14)(TM-13)(TM-11)(TM-2)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
February 22 - 28, 2017

Date Activities
1. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
2. Sifing of Grains of Sand for Plastering
3. Plastering @ Pre-Function Area (Walls & Columns)
4. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
February 22, 2017 5. Installation of Rebars @ Level 4 (Columns)
6. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
7. Fabrication of Steel Bars
8. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
9. Backfilling of Soil @ Level 4 Foundation
1. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
2. Sifing of Grains of Sand for Plastering
3. Plastering @ Pre-Function Area (Walls & Columns)
4. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Removal of Installed Rebars on Slab on Grade @ Main Stair Foundation
6. Installation of Rebars @ Level 4 (Columns)
February 23, 2017
7. Installation of Formworks @ Level 4 (Suspended Slab, Concrete Ledge, Beams & Girders)
8. Fabrication of Steel Bars
9. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
10. Backfilling of Soil @ Level 4 Foundation
11. Conrete Pouring of Columns, Shearwal and Elevator Pit @ Level 3 and Suspended Slab,
Concrete Ledge, Beams and Girders @ Level 4
1. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
2. Sifing of Grains of Sand for Plastering
3. Plastering @ Pre-Function Area (Walls & Columns)
4. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
6. Removal of Installed Rebars on Slab on Grade @ Main Stair Foundation
7. Erection of Scaffolding for Support of Level 3 Structure (Suspended Slab, Beams & Girders)
February 24, 2017
8. Installation of Formworks @ Level 3 (Beams & Girders)
9. Installation of Rebars @ Level 4 (Columns)
10. Installation of Rebars @ Level 5 (Columns)
11. Fabrication of Steel Bars
12. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
13. Backfilling of Soil @ Level 4 Foundation
14. Watering of New Concreted Structure
1. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
2. Sifing of Grains of Sand for Plastering
3. Plastering @ Pre-Function Area (Walls & Columns)
4. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
6. Erection of Scaffolding for Support of Level 3 Structure (Suspended Slab, Beams & Girders)
February 25, 2017 7. Installation of Formworks @ Level 3 (Beams & Girders)
8. Installation of Rebars @ Level 4 (Columns)
9. Installation of Rebars @ Level 5 (Columns)
10. Fabrication of Steel Bars
11. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
12. Backfilling of Soil @ Level 4 Foundation
13. Watering of New Concreted Structure
1. Sifing of Grains of Sand for Plastering
2. Plastering @ Pre-Function Area (Walls & Columns)
3. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
February 27, 2017 6. Installation of Formworks @ Level 3 (Suspended Slab, Beams & Girders)
7. Installation of Rebars @ Level 3 (Retaining Wall)
8. Installation of Rebars @ Level 5 (Columns)
9. Fabrication of Steel Bars
February 27, 2017

10. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
11. Backfilling of Soil @ Level 4 Foundation
1. Sifing of Grains of Sand for Plastering
2. Plastering @ Pre-Function Area (Walls & Columns)
3. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
6. Backfilling of Excavated Slab for Pipe Line
February 28, 2017
7. Installation of Formworks @ Level 3 (Suspended Slab, Beams & Girders)
8. Installation of Rebars @ Level 3 (Beams & Girders)
9. Fabrication of Steel Bars
10. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
11. Backfilling of Soil @ Level 4 Foundation
12. Unloading of Delivered Materials (RSB)
ity

Manpower
2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)(PC-2)
1-Driver (SV-04)(TM-11)(TM-13)(TM-14)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
2-Engr
1-IT
2-Operator (Bobcat)(STC-250)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
March 1 - 7, 2017

Date Activities
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Layouting & Constructing of Mock-up for Hanging Stair
5. Removal/Cutting of Installed Rebars on Slab on Grade @ Main Stair Foundation
6. Manual Backfilling & Compaction of Soil on Excavation for Sewerage Pipe Line
March 1, 2017 7. Installation of Forms @ Level 2 (Retaining Wall)
8. Installation of Forms @ Level 3 (Suspended Slab)
9. Installation of Rebars @ Level 3 (Suspended Slab)
11. Removal of Forms @ Level 2 (Columns, Shear Wall & Retaining Wall)
12. Removal of Forms @ Level 3 (Suspended Slab, Beams & Girders)
13. Fabrication of Steel Bars
14. Cutting of Excess Rebars @ Domestic & Fire Tank
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Removal of Forms @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Gravel Bedding @ Ground Floor (Slab on Grade)
6. Installation of Polyethelene Sheet
7. Installation of Rebars (Slab on Grade)
March 2, 2017
8. Excavation of Main Stair Foundation
9. Installation of Rebars @ Level 3 (Suspended Slab, Coumns and Retaiing Wall)
March 2, 2017

10. Removal of Forms @ Level 2 (Columns, Shear Wall & Retaining Wall)
11. Removal of Forms @ Level 3 (Suspended Slab, Beams & Girders)
12. Fabrication of Steel Bars
13. Re-staging of Aggregates (G1)
14. Unloading of Delivered Materials (G.I. Pipes)
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Removal of Forms @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Gravel Bedding @ Ground Floor (Column Footing for Main Stair Foundation)
6. Installation of Forms @ Ground Floor (Slab on Grade & Main Stair Footing)
7. Installation of Rebars @ Ground Floor (Slab on Grade & Main Stair Footing)
8. Demolition of Wall for Beams of Hanging Stair
March 3, 2017
9. Concrete Pouring @ Ground Floor (Slab on Grade & Main Stair Footing)
10. Installation of Rebars @ Level 3 (Suspended Slab, Coumns and Retaiing Wall)
11. Removal of Forms @ Level 2 (Columns, Shear Wall & Retaining Wall)
12. Removal of Forms @ Level 3 (Suspended Slab, Beams & Girders)
13. Fabrication of Steel Bars
14. Backfilling of Soil @ Level 4 Foundation
15. Concrete Pouring @ level 2 (Columns and Retaining Wall)
16. Concrete Pouring @ Level 3 (Suspended Slab, Beams & Girders)
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. CHB Laying @ Upper Roof Level (Additional Parapet Wall)
5. Installation of Forms @ Ground Floor (Main Stair)
6. Installation of Rebars @ Ground Floor (Main Stair)
7. Demolition of Wall for Beams of Hanging Stair
8. Erection of Scaffolding for Level 4 Support & Mezzanine Level Support
March 4, 2017 9. Installation of Rebars @ Level 3 (Coumns and Retaiing Wall)
10. Installation of Rebars @ Level 3 (Columns)
11. Removal of Forms @ Level 3 (Columns, Shear Wall & Retaining Wall)
12. Removal of Forms @ Level 4 (Suspended Slab, Beams & Girders)
13. Installation of Rebars @ Level 4 (Shear Wall)
14. Installation of Forms @ Mezzanine Level (Suspended Slab, Beams & Girders)
15. Fabrication of Steel Bars
16. Backfilling of Soil @ Level 4 Foundation
17. Cutting of Excess Rebars @ Domestic & Fire Tank
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Removal of Forms @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Installation of Forms @ Ground Floor (Main Stair)
6. Installation of Rebars @ Ground Floor (Main Stair)
March 6, 2017
7. Demolition of Wall for Beams of Hanging Stair
8. Installation of Forms @ Level 4 (Shear Wall, Beams & Girders)
9. Installation of Forms @ Mezzanine Level (Suspended Slab, Brams & Girders)
10. Fabrication of Steel Bars
11. Cutting of Excess Rebars @ Domestic & Fire Tank (Due to Revision of Plan)
12. Backfilling of Soil @ Level 4 Foundation
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Removal of Forms @ Upper Roof Level (Additional Parapet Wall & Ledge)
5. Installation of Forms @ Ground Floor (Main Stair)
6. Installation of Rebars @ Ground Floor (Main Stair)
7. Demolition of Wall for Beams of Hanging Stair
March 7, 2017
8. Installation of Forms @ Level 4 (Suspended Slab, Beams & Girders)
9. Installation of Rebars @ Level 4 (Beams & Girders)
10. Installation of Forms @ Mezzanine Level (Suspended Slab, Beams & Girders)
11. Fabrication of Steel Bars
12. Cutting of Excess Rebars @ Domestic & Fire Tank
13. Re-staging of Aggregates (G1)
14. Unloading of Delivered Materials (RSB)
ity

Manpower
2-Engr
1-IT
1-Operator (Bobcat)

2-Engr
1-IT
3-Operator (Bobcat)(STC-250)(BH-16)
1-Driver (SV-22)
2-Engr
1-IT
2-Operator (Bobcat)(PC-02)
4-Driver (TM-13)(TM-22)(TM-11)(TM-5)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
2-Operator (Bobcat)(STC-250)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
March 8 - 14, 2017

Date Activities
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Plastering @ Upper Roof Level (Additional Parapet Wall - Inside)
4. Installation of Forms @ Ground Floor to Second Floor (Main Stair)
5. Installation of Rebars @ Ground Floor (Hanging Stair - Beam Support)
March 8, 2017
6. Installation of Forms @ Level 4 (Suspended Slab)
7. Installation of Rebars @ Level 4 (Columns)
8. Fabrication of Steel Bars
9. Unloading of Delivered Materials (RSB)
10. Backfilling @ Level 2
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
4. Plastering @ Upper Roof Level (Additional Parapet Wall - Inside)
5. CHB Laying @ Upper Roof Level (Additional Parapet Wall - Inside)
6. Installation of Forms @ Ground Floor to Second Floor (Main Stair)
7. Installation of Rebars @ Ground Floor (Hanging Stair - Beam Support)
March 9, 2017
8. Installation of Forms @ Level 3 (Retaining Wall)
9. Installation of Forms @ Level 4 (Suspended Slab & Concrete Ledge)
10. Installation of Rebars @ Level 4 (Suspended Slab, Columns, Elevator's Pit & Shear Wall)
11. Installation of Rebars @ Mezzanine Level (Beams)
12. Fabrication of Steel Bars
13. Unloading of Delivered Materials (RSB)
14. Re-Staging of Materials (RSB & G.I. Pipes)
1. Installation of Formworks @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Installation of Rebars @ Upper Roof Level (Additional Parapet Wall & Ledge)
3. Plastering @ Upper Roof Level (Additional Parapet Wall - Inside)
4. Installation of Forms @ Level 3 (Retaining Wall)
March 10, 2017
5. Installation of Forms @ Level 4 (Suspended Slab & Concrete Ledge)
6. Installation of Rebars @ Level 4 (Suspended Slab, Concrete Ledge & Columns)
7. Installation of Rebars @ Mezzanine Level (Beams)
8. Fabrication of Steel Bars
1. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Plastering @ Upper Roof Level (Additional Parapet Wall - Inside)
3. Installation of Rebars @ Ground Floor (Hanging Stair)
4. Installation of Forms @ Level 3 (Retaining Wall)
March 11, 2017
5. Installation of Forms @ Level 4 (Suspended Slab, Beams & Girders)
6. Installation of Rebars @ Level 4 (Suspended Slab & Columns)
7. Installation of Rebars @ Mezzanine Level (Suspended Slab & Beams)
8. Fabrication of Steel Bars
1. Manual Concreting @ Upper Roof Level (Additional Parapet Wall & Ledge)
2. Plastering @ Upper Roof Level (Additional Parapet Wall - Inside)
3. Installation of Forms @ Ground Floor (Hanging Stair - Beam Support)
4. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
5. Constructing of Relocated Temfacil of Multi-r
6. Excavation for Septic Vault of Multi-R New Temfacil
7. Installation of Rebars @ Level 4 ( Columns)
March 13, 2017 8. Installation of Rebars @ Mezzanine Level (Suspended Slab)
9. Fabrication of Steel Bars
10. Demolition of Excess Wall of Water Tank
11. Installation of Rebars @ Water Tank on Level 2 (Beams)
12. Erection of Scaffoldings for Support of Suspended Slab @ Water Tank on Level 2
13. Concrete Pouring @ Level 3 (Columns & Retaining Wall)
14. Concrete Pouring @ Level 4 (Suspended Slab, Beams & Girders)
15. Application of Waterproofing System @ Domestic Tank
1. Plastering @ Upper Roof Level (Additional Parapet Wall - Inside)
2. Installation of Forms @ Ground Floor (Hanging Stair - Beam Support)
3. Demolition of Wall @ Pre-Function Area (Due to Revision of Plan)
4. Installation of Forms & Rebars @ Wall of Pre-Function Hall (Stiffiner Column & Lintel Beam)
5. Constructing of Relocated Temfacil of Multi-r
6. Installation of Forms @ Water Tank on Level 2 (Suspended Slab & Beams)
March 14, 2017 7. Installation of Rebars @ Water Tank on Level 2 (Beams)
8. Installation of Forms @ Level 4 (Columns, Elevator's Pit & Shear Wall)
9. Installation of Rebars @ Level 5 (Columns)
10. Concrete Watering of Concreted Structure @ Level 3 & Level 4
11. Removal of Forms @ Level 3 (Retaining Wall)
12. Fabrication of Steel Bars
13. Application of Waterproofing System @ Domestic Tank
ity

Manpower
2-Engr
1-IT
3-Operator (Bobcat)(Crane-2)(BH-24)
1-Driver (SV-04)

2-Engr
1-IT
3-Operator (Bobcat)(Crane-2)(BH-16)
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
3-Operator (Bobcat)(PC-2)(BH-8)
4-Driver (SV-04)(TM-11)(TM-13)(TM-22)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
March 15 - 21, 2017

Date Activities
1. Plastering of Parapet Wall (Inside) @ Upper Roof Level
2. Constructing of Relocated Temfacil of Multi-r
3. Installation of Forms for Suspended Slab & Beams @ Level 2
4. Installation of Rebars for Beams @ Level 2
5. Installation of Forms(First lif) for Columns, Elevator's Pit & Shear Wall @ Level 4
March 15, 2017
6. Installation of Rebars for Columns @ Level 5
7. Removal of Forms of Columns & Retaining Wall @ Level 3
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4
10. Application of Waterproofing System @ Domestic Tank
1. Plastering of Parapet Wall (Inside) @ Upper Roof Level
2. Constructing of Relocated Temfacil of Multi-r
3. Installation of Forms for Suspended Slab & Beams @ Level 2
4. Installation of Rebars for Beams @ Level 2
5. Installation of Forms(First lif) for Columns, Elevator's Pit & Shear Wall @ Level 4
March 16, 2017
6. Installation of Rebars for Columns @ Level 5
7. Removal of Forms of Columns & Retaining Wall @ Level 3
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4
10. Application of Waterproofing System @ Domestic Tank
1. Plastering of Parapet Wall (Inside) @ Upper Roof Level
2. Constructing of Relocated Temfacil of Multi-r
3. Installation of Forms for Suspended Slab & Beams @ Level 2
4. Installation of Rebars for Beams @ Level 2
5. Installation of Forms(First lif) for Columns, Elevator's Pit & Shear Wall @ Level 4
March 17, 2017
6. Erection of Scaffoldings as a Support for Mezzanine Level
7. Installation of Forms for Suspended Slab & Beams @ Mezzanine Level
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4
10. Application of Waterproofing System @ Domestic Tank
1. Plastering of Parapet Wall (Inside) @ Upper Roof Level
2. Constructing of Relocated Temfacil of Multi-r
3. Excavation of Septic Tank for Trade Contractors Temfacil
4. Installation of Forms for Suspended Slab & Beams @ Level 2
5. Installation of Rebars for Beams @ Level 2
March 18, 2017
6. Concrete Pouring on Columns, Elevator's Pit & Shear Wall @ Level 4(First lif)
7. Installation of Forms for Suspended Slab & Beams @ Mezzanine Level
8. Fabrication of Steel Bars
9. Backfilling of Soil @ Level 4
10. Application of Waterproofing System @ Domestic Tank
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Cutting of Level @ Relocated Temfacil of Trade Contractors
3. Installation of Forms for Suspended Slab & Beams @ Level 2
4. Installation of Forms for Suspended Slab & Beams @ Level 2
5. Installation of Rebars for Beams @ Level 2
6. Installation of Forms for Suspended Slab & Beams @ Mezzanine Level
March 20, 2017
7. Installation of Rebars for Suspended Slab & Beams @ Mezzanine Level
8. Erection of Scaffoldings as Support of Level 5
9. Fabrication of Steel Bars
10. Backfilling of Soil @ Level 4
11. Application of Waterproofing System @ Domestic Tank
12. Removal of Forms of Columns, Elevator's Pit & Shear Wall @ Level 4(First lif)
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Cutting of Level @ Relocated Temfacil of Trade Contractors
3. Constructing of Septic Tank for Trade Contractors
4. Installation of Forms for Suspended Slab & Beams @ Level 2
5. Installation of Rebars for Beams @ Level 2
March 21, 2017
6. Installation of Forms for Suspended Slab & Beams @ Mezzanine Level
March 21, 2017
7. Installation of Rebars for Suspended Slab & Beams @ Mezzanine Level
8. Erection of Scaffoldings as Support of Level 5
9. Fabrication of Steel Bars
10. Backfilling of Soil @ Level 4
11. Application of Waterproofing System @ Domestic Tank
12. Removal of Forms of Columns, Elevator's Pit & Shear Wall @ Level 4(First lif)
ity

Manpower
2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Bobcat)
1-Driver (SV-04)

2-Engr
1-IT
3-Operators (Bobcat)(PC-2)(BH-16)
3-Drivers (SV-04)(TM-11)(TM-13)

2-Engr
1-IT
2-Operators (Bobcat)(BH-9)

2-Engr
1-IT
1-Operator (Bobcat)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
March 29 - April 4, 2017

Date Activities
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Application of Epoxy Primer to Fascia Frame
3. Erection of Scaffoldings @ Level 2 as Support of Level 3
4. Installation of Rebars for Columns @ Level 3
March 29, 2017
5. Erection of Scaffoldings as Support of Level 5
6. Installation of Forms for Beams and Girders @ Level 5
7. Dismanlting of Scaffoldings @ Level 3
8. Removal of Forms @ Level 3
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Application of Epoxy Primer to Fascia Frame
3. Erection of Scaffoldings @ Level 2 as Support of Level 3
4. Installation of Rebars for Columns @ Level 3
5. Erection of Scaffoldings as Support of Level 5
March 30, 2017
6. Installation of Forms for Beams and Girders @ Level 5
7. Installation of Rebars for Beams and Girders @ Level 5
8. Dismanlting of Scaffoldings @ Level 3
9. Removal of Forms @ Level 3
10. Stock Filling of Soil for Backfilling of Level 3
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
3. Erection of Scaffoldings @ Level 2 as Support of Level 3
4. Installation of Rebars for Columns @ Level 3
5. Erection of Scaffoldings as Support of Level 5
March 31, 2017
March 31, 2017 6. Installation of Forms for Beams and Girders @ Level 5
7. Installation of Rebars for Beams and Girders @ Level 5
8. Dismanlting of Scaffoldings @ Level 3
9. Removal of Forms @ Level 3
10. Stock Filling of Soil for Backfilling of Level 3
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Erection of Scaffoldings as Support of Level 5
3. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
4. Installation of Rebars for Beams and Girders @ Level 5
April 1, 2017 5. Fabrication of Steel Bars
6. Dismanlting of Scaffoldings @ Level 3
7. Removal of Forms @ Level 3
8. Removal of Forms @ Level 4 (Shear Wall)
9. Stock Filling of Soil for Backfilling of Level 3
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Demolition of Old Temfacil due to Site Development
3. Plastering of Parapet Wall(Outside) @ Upper Roof Level
4. Erection of Scaffoldings as Support of Level 5
5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
April 3, 2017
6. Installation of Rebars for Beams and Girders @ Level 5
7. Fabrication of Steel Bars
8. Dismanlting of Scaffoldings @ Level 3
9. Removal of Forms @ Level 3
10. Stock Filling of Soil for Backfilling of Level 3
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Demolition of Old Temfacil due to Site Development
3. Plastering of Parapet Wall(Outside) @ Upper Roof Level
April 4, 2017 4. Erection of Scaffoldings as Support of Level 5
5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
6. Installation of Rebars for Beams and Girders @ Level 5
7. Fabrication of Steel Bars
ity

Manpower
2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
2-Engr
3-Operator (LD-4)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-4)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
April 5 - April 8, 2017

Date Activities
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Demolition of Old Temfacil due to Site Development
3. Plastering of Parapet Wall(Outside) @ Upper Roof Level
April 5, 2017 4. Erection of Scaffoldings as Support of Level 5
5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
6. Installation of Rebars for Beams and Girders @ Level 5
7. Fabrication of Steel Bars
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Demolition of Old Temfacil due to Site Development
3. Plastering of Parapet Wall(Outside) @ Upper Roof Level
April 6, 2017 4. Erection of Scaffoldings as Support of Level 5
5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
6. Installation of Rebars for Beams and Girders @ Level 5
7. Fabrication of Steel Bars
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)
2. Demolition of Old Temfacil due to Site Development
3. Plastering of Parapet Wall(Outside) @ Upper Roof Level
April 7, 2017 4. Erection of Scaffoldings as Support of Level 5
5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
6. Installation of Rebars for Beams and Girders @ Level 5
7. Fabrication of Steel Bars
1. Constructing of Relocated Temfacil of Trade Contractor (Multi-r)

April 8, 2017
2. Demolition of Old Temfacil due to Site Development
3. Plastering of Parapet Wall(Outside) @ Upper Roof Level
April 8, 2017 4. Erection of Scaffoldings as Support of Level 5
5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
6. Installation of Rebars for Suspended Slab, Beams and Girders @ Level 5
7. Fabrication of Steel Bars
ity

Manpower
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
April 10 - April 18, 2017

Date Activities
1. Concreting of Hanging Stair Step @ Mezzanine Level
2. Plastering of Parapet wall (Outside) @ Upper Roof Level
3. Demolition of Old Temfacil due to Site Development
4. Erection of Scaffoldings as Support of Level 5
April 10, 2017 5. Installation of Forms for Suspended Slab, Beams and Girders @ Level 5
6. Installation of Rebars for Beams and Girders @ Level 5
7. Concrete Pouring on Columns, Shear Wall & Elevators Pit @ Level 4 (2nd Lif)
8. Concrete Pouring of Suspended Slab, Concrete Ledge, Beams & Girders @ Level 5
9. Fabrication of Steel Bars
1. Watering of New Concreted Structure @ Level 5
2. Site Cleaning & Clearing
April 11, 2017

1. Watering of New Concreted Structure @ Level 5


April 12, 2017

1. Watering of New Concreted Structure @ Level 5


April 17, 2017

1. Watering of New Concreted Structure @ Level 5


April 18, 2017
2. Hauling of Scaffoldings to Level 5
April 18, 2017
3. Erection of Scaffoldings @ Level 5 as support for Level 6 Structure
ity

Manpower
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
April 19 - April 25, 2017

Date Activities
1. Installation of Forms of Main Stair
2. Installation of Rebars of Column @ Level 3
3. Erection of Scaffoldings @ Level 2 as support of Level 3 Structure
4. Erection of Scaffoldings @ Level 4 as support of Level 5 Structure
April 19, 2017
5. Erection of Scaffoldings @ Level 5 as support of Level 6 Structure
6. Fabrication of Steel Bars
7. Hauling of Materials(Forms, Rebars & Scaffoldings) to Level 5
8. Hauling of Form Strips & Scrap Bars
1. Installation of Forms of Main Stair
2. Installation of Rebars of Column @ Level 3
3. Erection of Scaffoldings @ Level 2 as support of Level 3 Structure
4. Installation of Forms of Beams & Girders @ Level 3
5. Erection of Scaffoldings @ Level 4 as support of Level 5 Structure
April 20, 2017
6. Installation of Forms of Beams & Girders @ Level 5
7. Erection of Scaffoldings @ Level 5 as support of Level 6 Structure
8. Fabrication of Steel Bars
9. Hauling of Materials(Forms, Rebars & Scaffoldings) to Level 5
10. Hauling of Form Strips & Scrap Bars
1. Installation of Forms & Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Beams & Girders @ Level 3
4. Erection of Scaffoldings @ Level 2 as support of Level 3 Structure
April 21, 2017
5. Installation of Forms of Suspended Slab, Beams & Girders @ Level 5
April 21, 2017
6. Installation of Rebars of Beams & Girders @ Level 5
7. Erection of Scaffoldings @ Level 4 as support of Level 5 Structure
8. Fabrication of Steel Bars
9. Hauling of Materials(Forms, Rebars & Scaffoldings) to Level 5
10. Hauling of Form Strips & Scrap Bars
1. Installation of Forms & Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Beams & Girders @ Level 3
4. Installation of Forms of Suspended Slab, Beams & Girders @ Level 5
April 22, 2017
5. Installation of Rebars of Beams & Girders @ Level 5
6. Fabrication of Steel Bars
7. Hauling of Materials(Forms, Rebars & Scaffoldings) to Level 5
8. Hauling of Form Strips & Scrap Bars
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Beams & Girders @ Level 3
April 24, 2017 4. Installation of Forms of Suspended Slab & Ledge @ Level 5
5. Installation of Rebars of Beams & Girders @ Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Beams & Girders @ Level 3
April 25, 2017 4. Installation of Forms of Suspended Slab & Ledge @ Level 5
5. Installation of Rebars of Beams & Girders @ Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
ity

Manpower
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
April 26 - May 2, 2017

Date Activities
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Beams & Girders @ Level 3
4. Installation of Forms of Suspended Slab & Ledge @ Level 5
April 26, 2017
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
8. Hauling of Form Strips & Scrap Bars
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
April 27, 2017 4. Installation of Forms of Suspended Slab & Ledge @ Level 5
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms of Suspended Slab & Ledge @ Level 5
April 28, 2017 5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
April 28, 2017

8. Concrete Pouring on Columns(2nd Lif) @ Level 4


9. Concrete Pouring on Suspended Slab, Beams & Girders @ Level 5
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
April 29, 2017 4. Watering on New Concreted Structure @ Level 5
5. Hauling/Lifing of Materials to Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
May 1, 2017 4. Watering on New Concreted Structure @ Level 5
5. Hauling/Lifing of Materials to Level 5
6. Fabrication of Steel Bars
7. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
1. Installation of Rebars of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
May 2, 2017 4. Watering on New Concreted Structure @ Level 5
5. Hauling/Lifing of Materials to Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
ity

Manpower
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5) (PC-2)
4-Drivers (SV-04) (TM-13) (TM-11) (TM-14)
2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
April May 3 - May 9, 2017

Date Activities
1. Concrete Pouring of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
May 3, 2017 4. Watering on New Concreted Structure @ Level 5
5. Hauling/Lifing of Materials to Level 5
6. Fabrication of Steel Bars
7. Backfilling @ Level 2 (Slab on Fill)
1. Concrete Pouring of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Hauling/Lifing of Materials to Level 5
May 4, 2017
5. Fabrication of Steel Bars
6. Backfilling @ Level 2 (Slab on Fill)
7. Concrete Pouring on Columns & Shear Wall @ Level 2
8. Concrete Pouring on Suspended Slab, Beams & Girders @ Level 3
1. Watering of Concreted Structure of Main Stair
2. Watering on New Concreted Structure @ Level 3
3. Hauling/Lifing of Materials to Level 6
May 5, 2017
4. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
5. Fabrication of Steel Bars
6. Backfilling @ Level 2 (Slab on Fill)
1. Removal of Forms of of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
May 6, 2017 5. Watering on New Concreted Structure @ Level 3
6. Hauling/Lifing of Materials to Level 6
7. Fabrication of Steel Bars
8. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
9. Backfilling @ Level 2 (Slab on Fill)
1. Removal of Forms of of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
May 8, 2017
5. Watering on New Concreted Structure @ Level 3
6. Hauling/Lifing of Materials to Level 6
7. Fabrication of Steel Bars
8. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
1. Removal of Forms of of Main Stair
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
May 9, 2017
5. Watering on New Concreted Structure @ Level 3
6. Hauling/Lifing of Materials to Level 6
7. Fabrication of Steel Bars
8. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
ity

Manpower
2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
2-Operator (LD-5) (PC-2)
4-Drivers (SV-04) (TM-13) (TM-11) (TM-27)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (LD-5)
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
May 10 - May 16, 2017

Date Activities
1. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 2
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
May 10, 2017 4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
5. Hauling/Lifing of Materials to Level 6
6. Fabrication of Steel Bars
7. Watering of New Concreted Structure @ Level 3
1. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 2
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
May 11, 2017 4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
5. Hauling/Lifing of Materials to Level 6
6. Fabrication of Steel Bars
7. Watering of New Concreted Structure @ Level 3
1. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 2
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
May 12, 2017
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
5. Hauling/Lifing of Materials to Level 6
6. Fabrication of Steel Bars
1. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 2

May 13, 2017


3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
May 13, 2017
5. Hauling/Lifing of Materials to Level 6
6. Fabrication of Steel Bars
7. Concrete Pouring on Columns @ Level 1 and Suspended Slab, Beams and Girders @ Level 2
8. Concrete Pouring on Columns @ Level 5 and Suspended Slab, Beams & Girders @ Level 6
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
May 15, 2017 5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
6. Hauling/Lifing of Materials to Level 6
7. Fabrication of Steel Bars
8. Watering on New Concreted Structure @ Level 2 & Level 6
9. Removal of Forms inside of the Domestic Tank
1. Installation of Fascia Frame @ Second Floor
2. Installation of Forms & Rebars of Columns @ Level 2
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
5. Installation of Forms & Rebars of Columns @ Level 5
May 16, 2017
6. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Watering on New Concreted Structure @ Level 2 & Level 6
9. Removal of Forms inside of the Domestic Tank
ity

Manpower
2-Engr
1-IT

2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (PC-2)
6-Drivers (SV-04)(TM-2)(TM-8)(TM-27)(TM-13)(TM-14)

2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
May 17 - May 23, 2017

Date Activities
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
May 17, 2017 5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
6. Installation of Forms & Rebars of Beams & Girders @ Level 6
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Application of Water Proofing System on Retaining Wall @ Level 2
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
May 18, 2017 5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
6. Installation of Forms & Rebars of Beams & Girders @ Level 6
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Application of Water Proofing System on Retaining Wall @ Level 2
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
May 19, 2017
May 19, 2017 5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
6. Installation of Forms & Rebars of Suspended Slab @ Level 6
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Application of Water Proofing System on Retaining Wall @ Level 2
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
May 20, 2017 6. Installation of Forms & Rebars of Suspended Slab @ Level 6
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Application of Water Proofing System on Retaining Wall @ Level 2
10. Backfilling @ Driveway
11. Unloading of Delivered RSB
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
May 22, 2017 5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
6. Installation of Forms & Rebars of Suspended Slab @ Level 6
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Application of Water Proofing System on Retaining Wall @ Level 2
1. Installation of Forms & Rebars of Columns @ Level 2
2. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
3. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Forms & Rebars of Columns @ Level 5
May 23, 2017 5. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
6. Installation of Forms & Rebars of Suspended Slab @ Level 6
7. Hauling/Lifing of Materials to Level 6
8. Fabrication of Steel Bars
9. Application of Water Proofing System on Retaining Wall @ Level 2
ity

Manpower
2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (Crane-02)
1-Driver (SV-04)
2-Engr
1-IT
2-Operator (BH-)(Crane-02)
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
May 24 - May 30, 2017

Date Activities
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Forms & Rebars of Columns @ Level 2
4. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
May 24, 2017
7. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
8. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
9. Installation of Forms & Rebars of Suspended Slab @ Level 6
10. Hauling/Lifing of Materials to Level 6
11. Fabrication of Steel Bars
12. Application of Water Proofing System on Retaining Wall @ Level 2
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Forms & Rebars of Columns @ Level 2
4. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
May 25, 2017
7. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
8. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
9. Installation of Forms & Rebars of Suspended Slab @ Level 6
10. Hauling/Lifing of Materials to Level 6
11. Fabrication of Steel Bars
12. Application of Water Proofing System on Retaining Wall @ Level 2
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Forms & Rebars of Columns @ Level 2
4. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 6
7. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 6
May 26, 2017
8. Erection of Scaffoldings @ Level 5 as Support of Level 6 Structure
9. Installation of Forms & Rebars of Suspended Slab @ Level 6
10. Installation of Rebars of Beams & Girders @ Level 7
11. Fabrication of Steel Bars
12. Application of Water Proofing System on Retaining Wall @ Level 2
13. Concrete Pouring of Columns, Elevator Pit & Shear Wall @ Level 5
14. Concrete Pouring of Suspended Slab, Beams & Girders @ Level 6
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
5. Installtion of Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
6. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
May 27, 2017
7. Installation of Rebars of Beams & Girders @ Level 7
8. Fabrication of Steel Bars
9. Hauling/Lifing of Materials to Level 7
10. Fabrication of Steel Bars
11. Application of Water Proofing System on Retaining Wall @ Level 2
12. Backfilling on Excavation @ Driveway
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Forms of Suspended Slab, Beams & Girders @ Level 3
4. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 3
5. Installtion of Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
6. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
May 29, 2017 7. Installation of Rebars of Beams & Girders @ Level 7
May 29, 2017
8. Fabrication of Steel Bars
9. Hauling/Lifing of Materials to Level 7
10. Fabrication of Steel Bars
11. Application of Water Proofing System on Retaining Wall @ Level 2
12. Concrete Pouring of Columns @ Level 2
13. Concrete Pouring of Suspended Slab, Beams & Girders @ Level 3
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Rebars of Columns @ Level 3
5/30/2017
4. Installtion of Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
5. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
6. Installation of Rebars of Beams & Girders @ Level 7
. 7. Fabrication of Steel Bars
8. Hauling/Lifing of Materials to Level 7
9. Fabrication of Steel Bars
10. Application of Water Proofing System on Retaining Wall @ Level 2
ity

Manpower
2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)
2-Engr
1-IT
1-Operator (PC--2)
7-Driver (SV-04)(TM-11)(TM-13)(TM-6)(TM-8)(TM-10)(TM-27)

2-Engr
1-IT
1-Operator (BH-23)
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (PC-2)
4-Driver (SV-04)(TM-11)(TM-13)(TM-27)
2-Engr
1-IT
1-Driver (SV-04)
Daily Activities
Pulsar Events Hall & Hotel II, Tuguegarao City
May 31 - June 6, 2017

Date Activities
1. Fabrication of Gutter for Second Floor Roof
2. Installation of Gutter for Second Floor Roof
3. Installation of Forms & Rebars of Columns & Shear Wall @ Level 3
4. Installation of Suspended Slab, Beams & Girders of Columns @ Level 4
5. Installtion of Forms & Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
6. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
May 31, 2017 7. Installation of Rebars of Beams & Girders @ Level 7
8. Installation of Forms of Beams & Girders @ Level 7
9. Fabrication of Steel Bars
10. Hauling/Lifing of Materials to Level 7
11. Fabrication of Steel Bars
12. Application of Water Proofing System on Retaining Wall @ Level 3
13 . Unloading of Delivered Materials(RSB)
1. Installation of Forms & Rebars of Columns & Shear Wall @ Level 3
2. Installation of Suspended Slab, Beams & Girders of Columns @ Level 4
3. Installtion of Forms & Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
4. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
5. Installation of Rebars of Beams & Girders @ Level 7
June 1, 2017
6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 7
7. Fabrication of Steel Bars
8. Hauling/Lifing of Materials to Level 7
9. Fabrication of Steel Bars
10. Application of Water Proofing System on Retaining Wall @ Level 3
1. Installation of Forms & Rebars of Columns & Shear Wall @ Level 3
2. Installation of Suspended Slab, Beams & Girders of Columns @ Level 4
3. Installtion of Forms & Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
June 2, 2017 4. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
5. Installation of Rebars of Beams & Girders @ Level 7
asdsadasdasdas 6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 7
Super man 7. Fabrication of Steel Bars
8. Hauling/Lifing of Materials to Level 7
9. Fabrication of Steel Bars
10. Application of Water Proofing System on Retaining Wall @ Level 3
1. Installation of Forms & Rebars of Columns & Shear Wall @ Level 3
2. Installation of Suspended Slab, Beams & Girders of Columns @ Level 4
3. Installtion of Forms & Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
4. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
5. Installation of Rebars of Beams & Girders @ Level 7
June 3, 2017 6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 7
7. Fabrication of Steel Bars
8. Hauling/Lifing of Materials to Level 7
9. Fabrication of Steel Bars
10. Application of Water Proofing System on Retaining Wall @ Level 3
11. Backfilling on Excavation @ Driveway
1. Installation of Forms & Rebars of Columns & Shear Wall @ Level 3
2. Installation of Suspended Slab, Beams & Girders of Columns @ Level 4
3. Installtion of Forms & Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
4. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 7
June 5, 2017
6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 7
7. Fabrication of Steel Bars
8. Hauling/Lifing of Materials to Level 7
9. Fabrication of Steel Bars
10. Application of Water Proofing System on Retaining Wall @ Level 3
1. Installation of Forms & Rebars of Columns & Shear Wall @ Level 3
2. Installation of Suspended Slab, Beams & Girders of Columns @ Level 4
3. Installtion of Forms & Rebars of Columns, Elevator's Pit & Shear Wall @ Level 6
4. Erection of Scaffoldings @ Level 6 as Support of Level 7 Structure
5. Installation of Rebars of Suspended Slab, Beams & Girders @ Level 7
June 6, 2017 6. Installation of Forms of Suspended Slab, Beams & Girders @ Level 7
7. Fabrication of Steel Bars
8. Hauling/Lifing of Materials to Level 7
9. Fabrication of Steel Bars
10. Application of Water Proofing System on Retaining Wall @ Level 3
11. Backfilling on Excavation @ Driveway
ity

Manpower
2-Engr
1-IT
1-Operator (Crane-2)
1-Driver (SV-04)

2-Engr
1-IT
1-Driver (SV-04)
2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (BH-7)
2-Driver (SV-04)(DT-14)

2-Engr
1-IT
1-Driver (SV-04)

2-Engr
1-IT
1-Operator (BH-25)
1-Driver (SV-04)