You are on page 1of 12

Rate Analysis of Plai

Data Re

Unit Quantity = 100 cf

Rate of Cement = Rs. 450 per bag


Rate of Sand = Rs. 20 per cf
Rate of Stone Ballast = Rs. 35 per cf
Rate of Mason = Rs. 700 per day
Rate of Labour = Rs. 400 per day

Quntity of Material

Quantity of Cement = 17.6 bags


Quantity of Sand = 44 cf
Quantity of Stone Ballast = 88 cf

Cost of Labour (B)

Cost of Mason = Rs. 700


Cost of Labour = Rs. 3400
Total Cost = Rs. 4100

Cost of Scaffolding and Formwork (D)

Cost of Scaffolding & Formwork = Rs. 489

Total C

Total Cost = Rs. 18467

* In this problem the complete working day comprises of 8 working hours


ate Analysis of Plain Cement Concrete
Data Required

Concrete Mix = 1 : 2 : 4

per bag Mason Effort = 8 hrs


per cf Labour Effort = 68 hrs
per cf Cost of Water and Sundries = 2 % of (A+B)
per day Cost of Formwork and Scaffolding = 3 % of (A+B+C)
per day Contractor Profit = 10 % of (A+B+C+D)

Cost of Material (A)

Cost of Cement = Rs. 7920


Cost of Sand = Rs. 880
Cost of Stone Ballast = Rs. 3080
Total Cost = Rs. 11880

Cost of Water and Sundries (C)

Cost of Water And Sundries = Rs. 320

work (D) Contractor Profit (E)

Contractor Profit = Rs. 1678.859

Total Cost

Cost per cf = Rs. 185

orking hours
Rate Analysis o
Data Re

Unit Quantity = 100 cf

Rate of Cement = Rs. 450 per bag


Rate of Sand = Rs. 20 per cf
Rate of Brick = Rs. 7 per brick
Rate of Mason = Rs. 700 per day
Rate of Labour = Rs. 400 per day

Quntity of Material

Quantity of Cement = 6 bags


Quantity of Sand = 22.5 cf
Quantity of Brick = 1350 Nos

Cost of Labour (B)

Cost of Mason = Rs. 1400


Cost of Labour = Rs. 1400
Total Cost = Rs. 2800

Cost of Scaffolding and Formwork (D)

Cost of Scaffolding & Formwork = Rs. 471.24

Total C

Total Cost = Rs. 17797

* In this problem the complete working day comprises of 8 working hours


Rate Analysis of Brick Work
Data Required

Mortar Mix = 1 : 3

per bag Mason Effort = 16 hrs


per cf Labour Effort = 28 hrs
per brick Cost of Water and Sundries = 2 % of (A+B)
per day Cost of Formwork and Scaffolding = 3 % of (A+B+C)
per day Contractor Profit = 10 % of (A+B+C+D)

Cost of Material (A)

Cost of Cement = Rs. 2700


Cost of Sand = Rs. 450
Cost of Brick = Rs. 9450
Total Cost = Rs. 12600

Cost of Water and Sundries (C)

Cost of Water And Sundries = Rs. 308

work (D) Contractor Profit (E)

Contractor Profit = Rs. 1617.924

Total Cost

Cost per cf = Rs. 178

orking hours
Rate Analysis of int
Data Re

Unit Quantity = 100 sf

Rate of Cement = Rs. 450 per bag


Rate of Sand = Rs. 20 per cf
Thickness of plaster = 0.5 inch
Rate of Mason = Rs. 700 per day
Rate of Labour = Rs. 400 per day

Quntity of Material

Quantity of Cement = 0.5714 bags


Quantity of Sand = 4.2857 cf

Cost of Labour (B)

Cost of Mason = Rs. 700


Cost of Labour = Rs. 950
Total Cost = Rs. 1650

Cost of Scaffolding and Formwork (D)

Cost of Scaffolding & Formwork = Rs. 60.981

Total C

Total Cost = Rs. 2303

* In this problem the complete working day comprises of 8 working hours


Rate Analysis of internal wall plaster
Data Required

Mortar Mix = 1 : 6

per bag Mason Effort = 8 hrs


per cf Labour Effort = 19 hrs
Cost of Water and Sundries = 2 % of (A+B)
per day Cost of Formwork and Scaffolding = 3 % of (A+B+C)
per day Contractor Profit = 10 % of (A+B+C+D)

Cost of Material (A)

Cost of Cement = Rs. 257


Cost of Sand = Rs. 85.71429
Total Cost = Rs. 343

Cost of Water and Sundries (C)

Cost of Water And Sundries = Rs. 40

work (D) Contractor Profit (E)

Contractor Profit = Rs. 209.3696

Total Cost

Cost per sf = Rs. 23

orking hours
Rate Analysis of Cem
Data Re

Unit Quantity = 100 cf

Rate of Cement = Rs. 450 per bag

Rate of Sand = Rs. 20 per cf

Rate of Mason = Rs. 700 per day


Rate of Labour = Rs. 400 per day

Quntity of Material

Quantity of Cement = 12 bags


Quantity of Sand = 105 cf

Cost of Labour (B)

Cost of Mason = Rs. 0


Cost of Labour = Rs. 1500
Total Cost = Rs. 1500

Cost of Scaffolding and Formwork (D)

Cost of Scaffolding & Formwork = Rs. 275.4

Total C

Total Cost = Rs. 10401

* In this problem the complete working day comprises of 8 working hours


Rate Analysis of Cement Sand Mortar
Data Required

Mortar Mix = 1 : 7

per bag Mason Effort = 0 hrs

per cf Labour Effort = 30 hrs


Cost of Water and Sundries = 2 % of (A+B)
per day Cost of Formwork and Scaffolding = 3 % of (A+B+C)
per day Contractor Profit = 10 % of (A+B+C+D)

Cost of Material (A)

Cost of Cement = Rs. 5400


Cost of Sand = Rs. 2100
Total Cost = Rs. 7500

Cost of Water and Sundries (C)

Cost of Water And Sundries = Rs. 180

work (D) Contractor Profit (E)

Contractor Profit = Rs. 945.54

Total Cost

Cost per sf = Rs. 104

orking hours
Rate Analysis o
Data Re

Unit Quantity = 1000 cf


Labour Effort = 80 hrs
Rate of Labour = Rs. 400 per day

Cost of Labour (A)

Cost of Labour = Rs. 4000


Total Cost = Rs. 4000

Contractor Profit (C)

Cost of Scaffolding & Formwork = Rs. 408

* In this problem the complete working day comprises of 8 working hours


Rate Analysis of Earth Work
Data Required

Cost of Water and Sundries = 2 % of (A)


per day Contractor Profit = 10 % of (A+B)

Cost of Water and Sundries (B)

Cost of Water And Sundries = Rs. 80

Total Cost (E)

Total Cost = Rs. 4488


Cost per cf = Rs. 4.5

orking hours
Rate Analysis of Plai
Data Re

Unit Quantity = 100 cf

Rate of Cement = Rs. 450 per bag


Rate of Sand = Rs. 20 per cf
Rate of Stone Ballast = Rs. 40 per cf
Rate of Mason = Rs. 700 per day
Rate of Labour = Rs. 400 per day

Quntity of Material

Quantity of Cement = 17.6 bags


Quantity of Sand = 44 cf
Quantity of Stone Ballast = 88 cf

Cost of Labour (B)

Cost of Mason = Rs. 175


Cost of Labour = Rs. 2400
Total Cost = Rs. 2575

Cost of Scaffolding and Formwork (D)

Cost of Scaffolding & Formwork = Rs. 455.79

Total C

Total Cost = Rs. 17214

* In this problem the complete working day comprises of 8 working hours


ate Analysis of Plain Cement Concrete
Data Required

Concrete Mix = 1 : 2 : 4

per bag Mason Effort = 2 hrs


per cf Labour Effort = 48 hrs
per cf Cost of Water and Sundries = 2 % of (A+B)
per day Cost of Formwork and Scaffolding = 3 % of (A+B+C)
per day Contractor Profit = 10 % of (A+B+C+D)

Cost of Material (A)

Cost of Cement = Rs. 7920


Cost of Sand = Rs. 880
Cost of Stone Ballast = Rs. 3520
Total Cost = Rs. 12320

Cost of Water and Sundries (C)

Cost of Water And Sundries = Rs. 298

work (D) Contractor Profit (E)

Contractor Profit = Rs. 1564.869

Total Cost

Cost per cf = Rs. 172

orking hours