Project Code: 4YG - 04700 Report Date : 27-Jun-2017 Tuesday No. of Day Report No. DPR- 657
Proj Start Date 2014 Contract Period 1 Year Calendar Day AM PM Fine
Weather
Estimate Completion Date 14-Nov-2017 Remain Period 141 Calendar Day 6~8 8~10 10 ~12 12~2 2~4 4~6 Rain
Work Force
Office
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Site Store Driver Surveyer Geotech Workers Mason Carpenter Smith Welder
Staff
Today 1 3 1 1 3 2 1 25 22 35 74 7
Steel Roofing D&W Ceiling Water
Trades Scaffolder Painter Aluminium Total
Erector worker Installer worker Proofing
Today 3 3 177
Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
Excavator 60 Ton Crane Car Crane
Dozer 50 Ton Crane 13 tons Back Hole
1.5 Ton Roller 25 Ton Crane Rummer 1
Boom Lift Generator Truck
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total
Sand (river) suds 4.52
Shingle suds 1.13
Project Code: 4YG - 04700 Report Date : 27-Jun-2017 Tuesday No. of Day Report No.
Test Item Remarks
Sampl
e
LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT Conducted
HSE Waste Plan Management For Construction Recycling.
742460 0 0 0 0 0 By Safety Officer
Visitors Site
Purpose
on Site Instruction
Project Manager Project Engineer Prepare By: Site Engineer
Name Name Sai Thing Nun Name Lin Naing Soe
Project Code: 4YG - 04700 Report Date : 27-Jun-2017 Tuesday No. of Day Report No.
Excavation For Stair of Retaining Wall (near Block-B) Rebar Fixing Work For Main Fish Tank Formwork installation & Rebar Fixing Work at 2nd Floor (GL :B-9 to B13'
Rebar Fixing Work at Exhibit 1.2 Kalzip Wall Clading installation Formwork installation For Main Fish Tank