ESTIMATE FOR THE CONSTRUCTION A BUILDING COMPRISING OF:

3 OFFICES, 1 STORE, 3 TOILETS,


1 CONFERENCE HALL; FROM FOUNDATION TO THE FINISHING LEVEL

A. Needed materials for masonry work


1. 3000 pcs of 6" block N330,000.00

2. 155 bags of cement N248,000.00

3. 10 trips of sharp sand N70,000.00

4. 8 trips of bush gravel N88,000.00

5. 6 trips of plastering sand N30,000.00

6. Water N10,000.00

Total N776,000.00

B. Needed materials for iron work


1. 33 length of 12mm iron rod N52,800.00

2. Binding wire N3,000.00

3. Quarter rod N15,000.00

Total N70,800.00

C. Needed materials for plumbing work


1. Plumbing material for piping N38,300.00

2. Plumbing material for fitting N25,000.00

3. 3 Set of W/C N24,000.00

Total N87,300.00

D. Needed materials for carpenter work


1. 180 pcs of 2x4x12 wood for roofing N63,000.00

2. 140 pcs of 2x3x12 wood N49,000.00


3. 30 pcs of lx12x12 wood N36,000.00
4. 120 pcs of 2x2x12 wood for ceiling (Batten) N26,400.00
5. 1 bag of 3" Nail ... N4,500.00
6. 1 bag of 4" Nail N4,500.00

7. bag of 2" Nail N3,500.00

8. 5 packet of zinc Nail N5,000.00

9. 15 Bundles of Zinc N165,000.00

10. 104 sheets of ceiling board N93,600.00


11. 64 pcs of lx12x12 wood for lintel N44,800.00

Total N495,300.00

E. Needed material for tiling work


1. 128 pcs of square tiles for toilets N102,400.00
2. 2 bags of white cement N3,000.00

Total N105,400.00

F. Needed material for painting work


1. 15 buckets of texicoat paint N100,500.00
2. 30 buckets of emulsion paint N87,000.00
3. 1 carton of putty filler N3,000.00

Total N190,500.00
G. Needed materials for doors and windows
1. 6 wooden door frames N15,000.00
2. 6 wooden doors N30,000.00
3. 2 iron doors N30,000.00
4. 12 windows N120,000.00

Total N195,000.00

H. Labour
1. Labour for mason work N215,000.00
2. Labour for Iron work N15,000.00
3. Labour for plumbing work N20,000.00
4. Labour for carpenter work N80,000.00
5. Labour for tiling work N32,000.00
6. Labour for painting work N20,000.00
7. Labour for digging of foundation/septic tank N40,000.00
Total N422,000.00

I. Electrification N90,000.00

J. Furnishing
Conference seats, Extra AC units & Ceiling fans N200,000.00

K. Contingencies N50,000.00

Grand Total N2,682,300.00