PROJECT: REPAIR AND REHABILITATION OF COLLEGE OF AGRIBUSINESS MANAGEMENT BUILDING, PHASE 2 AT URS TANAY CAMPUS (COMPLETION) LOCATION: UNIVERSITY OF RIZAL SYSTEM, TANAY CAMPUS
WEEK 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 I MOBILIZATION AND DEMOBILIZATION 140,623.29 1.716 II TEMPORARY FACILITIES, WATER & ELECTRICITY 28,805.40 0.352 III SAFETY & HEALTH REQUIREMENTS 53,086.88 0.648 IV EARTHWORKS 247,151.87 3.017 V REBAR WORKS 2,259,592.27 27.579 VI MASONRY & CONCRETING WORKS 2,144,729.84 26.177 VII STEEL WORKS 364,144.57 4.444 VIII TINSMITHRY WORKS 272,769.29 3.329 IX PAINTING WORKS 386,221.33 4.714 X TILING WORKS 850,014.12 10.374 XI DOORS AND WINDOWS 401,936.27 4.906 XII CEILING WORKS 144,027.00 1.758 XIII ELECTRICAL WORKS 753,285.83 9.194 XIV MISCELANEOUS 146,919.85 1.793 TOTAL 8,193,307.80 100 16% 13% 22% 4% 4% 20% 7% 14% 29% 55% 79% 100% 1,310,929.25 1,065,130.01 1,802,527.72 327,732.31 327,732.31 1,638,661.56 573,531.55 1,147,063.09 2,376,059.26 4,506,319.29 6,472,713.16 8,193,307.80
PREPARED BY : S. B. SORIANO CONSTRUCTION DATE: 7/3/2017