You are on page 1of 12

Construction

and Building

Construction and Building Materials 20 (2006) 515–526


MATERIALS
www.elsevier.com/locate/conbuildmat

Construction and cost analysis of an FRP reinforced


concrete bridge deck
Adam C. Berg, Lawrence C. Bank *, Michael G. Oliva, Jeffrey S. Russell
Department of Civil and Environmental Engineering, University of Wisconsin–Madison, 1415 Engineering Drive, Madison, WI 53706, USA

Received 10 December 2003; received in revised form 15 February 2005; accepted 19 February 2005
Available online 7 April 2005

Abstract

This paper describes the use of FRP materials as reinforcements and formwork for a concrete highway bridge deck. It describes
the construction process and provides a cost analysis of the project. A continuing research program at the University of Wisconsin–
Madison is developing concepts for bridge decks reinforced with fiber reinforced polymers (FRP). This project involved the imple-
mentation of one of these concepts in a major highway bridge. Three forms of FRP reinforcing were combined to reinforce the con-
crete deck: FRP stay-in-place (SIP) forms, deformed FRP reinforcing bars (rebars), and a special prefabricated pultruded FRP
reinforcing grid. The research project, supported by the Innovative Bridge Research and Construction Program (IBRC) in the Uni-
ted States, resulted in the construction of a two-span highway overpass on US Highway 151 in Wisconsin. Based on the analysis of
the short-term material and labor costs it appears that given the savings in construction time and their potential long-term durability
and maintenance benefits, FRP reinforcements for bridge decks may be cost-effective, notwithstanding their currently high initial
costs. Optimization of FRP stay-in-place formwork is recommended to decrease the cost of the FRP reinforcing system in the
future.
 2005 Elsevier Ltd. All rights reserved.

Keywords: Concrete bridge deck; Cost analysis; Construction process; FRP reinforcing; Stay-in-place formwork

1. Introduction ventional steel in bridge decks. A review of recent appli-


cations of FRP reinforcements can be found in [1].
Corrosion of reinforcing steel is a main cause of While FRP stay-in-place forms and deformed rebar
deterioration of reinforced concrete bridge decks. have been used previously in a highway bridge deck
Freeze–thaw cycles cause concrete cracking followed [2], this is the first combination of those materials along
by corrosion and deterioration, limiting the lifespan of with a bi-directional FRP reinforcing grid panel selected
the bridge deck. The University of Wisconsin–Madison to reduce construction cost. In addition, this is the first
has worked in cooperation with the Wisconsin Depart- application where prestressed bridge girders were used
ment of Transportation (WisDOT), the Federal High- and where ‘‘composite action’’ was required between
way Administration (FHWA), and Alfred Benesch and the deck and the girders. Details of the design of the
Company on research projects to extend the lifespan two-span reinforced bridge deck using these FRP mate-
of reinforced concrete bridge decks by using non- rials and the development of special provisions that in-
corroding materials. The research projects involve the cluded a material specification for all FRP materials
use of Fiber Reinforced Polymers (FRP) in place of con- used have been described elsewhere [3,4]. That research
culminated in the work reported here on the construc-
*
Corresponding author. Tel.: +1 608 262 1604; fax: +1 608 262 5199. tion process and cost analysis of the FRP reinforced
E-mail address: bank@engr.wisc.edu (L.C. Bank). bridge deck.

0950-0618/$ - see front matter  2005 Elsevier Ltd. All rights reserved.
doi:10.1016/j.conbuildmat.2005.02.007
516 A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526

2. Description of the bridge

The FRP reinforced bridge deck is part of a major


new interchange on US Highway 151 (average daily traf-
fic – 18,600) over State Route 26 north of the city of
Waupun, Wisconsin. It is a two-span continuous bridge
with equal spans of 32.7 m (107 ft.) and carries two lanes
of traffic in the northbound direction. The bridge deck is
12.75 m (43 ft.) wide with a 32 horizontal skew and is
supported by five 1.37 m (54 in.) prestressed concrete
girders spaced at 2.65 m (8 ft. 8 in.) on center (Fig. 1).
The deck was reinforced with non-metallic glass–fiber
reinforced vinylester FRP parts, except for the cantile-
vered overhangs and the parapet walls which were rein-
forced with epoxy-coated steel as an FRP reinforced
parapet (or guardrail) has not yet been crash tested
and approved for use in the US. Constructed adjacent
to the FRP reinforced deck was a twin structure that
carries two lanes of southbound traffic. This second
bridge deck was reinforced with conventional epoxy
coated steel rebars. The only other difference between
these two bridges was in the thickness of the concrete

Fig. 1. Cross-Section through roadway.


decks. The steel reinforced deck was 200 mm (8 in.)
thick and the FRP reinforced deck was 215.9 mm
(8.5 in.) thick. The extra 12.7 mm (0.5 in.) of concrete
was needed in the FRP reinforced deck for non-struc-
tural reasons to develop the required top cover at the
crown of the bridge as will be discussed in what follows.

3. FRP Reinforcing materials

FRP reinforcing materials have been used in numer-


ous concrete structures over the last 20 years. Neverthe-
less, the combination of FRP materials used in this
bridge was unique. The system was developed to reduce
construction labor cost to offset the higher initial cost of
the FRP materials relative to conventional steel rein-
forcing. Additional, long-term cost savings due to de-
creased maintenance or increased service life of the
bridge deck in the future are also anticipated from the
FRP reinforcing system, however, an attempt to ac-
count for these cost savings are not documented at this
time. The possible long-term economic benefits of FRP
reinforcements in terms of constructibility and service
life extensions have been discussed elsewhere [5,6]. The
FRP reinforcing system consisted of three different com-
ponents (Fig. 2); stay-in-place (SIP) FRP pultruded
deck panels, pultruded FRP rebars, and bi-directional
FRP pultruded grids.

3.1. Stay-in-place (SIP) FRP pultruded deck panel

The SIP FRP deck panels were 457 mm (1 ft. 6 in.) by


2350 mm (7 ft. 10 in.). Each panel was stiffened by two
76 mm (3 in.) square hollow tubular ‘‘cells’’ spaced
A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526 517

Fig. 2. FRP reinforcement system.

229 mm (9 in.) apart. The deck panels spanned perpen- to control the failure mode (concrete crushing) and to
dicularly between the prestressed concrete girders and limit deflections [3]. Diversified Composites of Erlanger,
were discontinuous at the girders (Fig. 3). Their upper Kentucky produced the FRP SIP deck panels, which
horizontal surfaces were partially covered (30% per were supplied by Composite Deck Solutions (CDS) of
unit surface area) with a 6.35 mm (1/4 in.) limestone Dayton, Ohio. A total of 620.88 m2 of deck panels were
aggregate that was bonded to the surface with a con- purchased at a cost of $270.00 per m2 ($25.08 per ft2).
struction grade epoxy (Concresive 1090). The aggre- The total cost of deck panels was $167,637.60.
gate was used to assist in the development of
composite action between the deck panel and the con- 3.2. FRP reinforcing bars
crete slab through horizontal shear transfer. After the
concrete was poured, the deck panels served as the bot- The second component of the FRP reinforcing sys-
tom tensile reinforcement for the deck in the transverse tem was the FRP rebar (Fig. 4). The FRP bars were
direction. The panels were designed to be simply sup- used in the deck to provide negative moment continuity
ported between the girders so that the concrete slab for the girders over the center pier and as temperature
would act compositely with the girders. The panels were and shrinkage reinforcement elsewhere. The rebars came
designed in accordance with ACI procedures developed in three sizes, 13 mm, 19 mm, and 25 mm (#4, #6, and
for FRP rebars [7]. They were over-reinforced (qf > qfb) #8). The FRP bars were finished with a fine sand texture

Fig. 3. FRP deck panels over concrete girders.


518 A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526

Fig. 4. FRP deck panels, FRP rebars, and epoxy coated rebars during placement.

and had a helical deformation to develop bond with the 3.3. FRP reinforcing grid
concrete. Hughes Brothers, Inc. located in Seward, Ne-
braska produced the FRP rebars. 224 #4 bars, 112 #6 The third component of the FRP reinforcement sys-
bars, and 111 #8 bars were used at costs of $1.57 per me- tem was a prefabricated bi-directional FRP pultruded
ter ($0.48 per foot), $2.62 per meter ($0.80 per foot), and grid. The grid was assembled from 50 mm (2 in.) high
$4.36 per meter ($1.33 per foot), respectively. The total T-bars spaced at 100 mm (4 in.) on center and 13 mm
cost of the FRP rebars was $25,369.10. (0.5 in.) diameter three-part cross-rods spaced at

Fig. 5. Bi-directional FRP grid and mechanical splice connection.


A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526 519

100 mm (4 in.) on center and resembled a pultruded 4. FRP Specifications and quality control
FRP walkway grating (with wider spaces than normal
between the bars). The grid served as the top rein- According to the construction specifications for the
forcement of the concrete deck and carried tensile project detailed in the Special Provisions, each FRP
stress over the girders caused by negative bending mo- material manufacturer was required to submit certified
ments in the transverse direction of the deck. The test reports that provided strength, stiffness, and physi-
FRP grids came in two sizes, 1224 mm (4 ft. 1 in.) cal properties of each FRP component. Shown in Tables
by 2650 mm (8 ft. 10 in.) and 1224 mm (4 ft. 1 in.) by 1–3 are the specifications for the FRP deck forms, FRP
4230 mm (14 ft. 1 in.). They were joined in the positive grids, and FRP rebars. The FRP deck panel and FRP
moment region of the slab between the girders. A grid were classified into two material classes while the
mechanical splice connection (i.e., a pultruded coupler) FRP rebars were classified as a single class [8]. Class 1
was used at the ends of the grids to hold them in po- FRP material was required to have a total fiber volume
sition during construction. The coupler was not de- fraction of 55% or greater and a total longitudinal fiber
signed to provide tensile load transfer between two volume (relative to the total fiber volume) of 95% or
adjacent grids. During construction, three to four pul- greater. Class 2 FRP material was required to have a to-
truded couplers were used per grid pair. In addition to tal fiber volume fraction of 45% or greater and a total
the couplers, epoxy coated tie wires were used to hold longitudinal fiber volume (relative to the total fiber vol-
the grids together during casting (Fig. 5). Strongwell ume) of 75% or greater. Class 3 FRP material was re-
of Chatfield, Minnesota, produced the bi-directional quired to have a total fiber volume fraction of 45% or
FRP pultruded grid and the couplers. A total of 162 greater and a total longitudinal fiber volume of (relative
bi-directional FRP grid pieces were used at a cost of to the total fiber volume) 40% or greater.
$90.00 per m2 ($8.36 per ft2). The total cost of FRP For the FRP deck panel, GV2 (i.e., glass vinylester
grids was $64,922.40. class 2) materials were specified for parts less than or
The material cost for the entire FRP reinforcement equal to 8 mm (0.32 in.) thick and GV3 materials were
system was $370.17 per m2 ($34.39 per ft2) for a total specified for parts greater than 8 mm (0.32 in.) thick.
cost of $257,929.10. Although the SIP deck panels were For the FRP grid, GV1 material was specified for the
the most expensive FRP components, they were inten- three-part cross rod and GV2 material for the main
tionally selected as a means of reducing construction load-bearing T-bars. For the FRP rebars only GV1
time and labor costs. Steel SIP forms reduce construction material was specified. As noted in Tables 1–3 the three
costs in a similar manner. Unfortunately, they are subject different FRP components had different property
to corrosion and deterioration when used in overpass requirements even for the same classification. Detailed
structures where significant salt spray from de-icing salts test data for the FRP materials may be found in [9].
exists in northern climates, and are therefore not used by In addition to the manufacturerÕs test reports, the
the Wisconsin Department of Transportation. University of Wisconsin–Madison (UW) performed

Table 1
Limiting physical and mechanical properties for FRP deck panel
Material property ASTM test GV2 material GV3 material
Mechanical property
Strength property
Longitudinal tensile strength (min) D3039, D5083, D638 80.0 ksi (552 MPa) 60.0 ksi (414 MPa)
Transverse tensile strength (min) D3039, D5083, D638 4.0 ksi (28 MPa) 4.0 ksi (28 MPa)
Longitudinal compressive strength (min) D3410, D695 80.0 ksi (552 MPa) 60.0 ksi (414 MPa)
Transverse compressive strength (min) D3410, D695 10.0 ksi (69 MPa) 10 ksi (69 MPa)
Longitudinal flexural strength (min) D790 80.0 ksi (552 MPa) 60.0 ksi (414 MPa)
Long. short beam shear strength (min) D2344 5.5 ksi (38 MPa) 5.0 ksi (35 MPa)
Stiffness property
Longitudinal tensile modulus (min) D3039, D5083, D638 4.5 Msi (31 GPa) 4.0 Msi (28 GPa)
Longitudinal compressive modulus (min) D3410, D695 4.0 Msi (28 GPa) 3.0 Msi (21 GPa)
In-plane shear stiffness (min) D5379 0.40 Msi (3 GPa) 0.30 Msi (2 GPa)
Major (longitudinal) Poisson ratio (min) D3039, D5083, D638 0.25 0.25
Physical property
Fiber volume fraction (min) D3171, D2584 45% 45%
Barcol hardness (min) D2583 50 50
Glass transition temperature (min) E1356, D3418 203 F (95 C) 203 F (95 C)
Water absorption (max) D570 (immersion at 50 C for 48 h) 1.5% 2.0%
Long. coeff. of thermal expansion (max) D696 6 · 10 6/F (11 · 10 6/C) 6 · 10 6/F (11 · 10 6/C)
Trans. coeff. of thermal expansion (max) D696 30 · 10 6/F (54 · 10 6/C) 30 · 10 6/F (54 · 10 6/C)
520 A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526

Table 2
Limiting physical and mechanical properties for FRP grid
Material property ASTM test GV1 material GV2 material
Mechanical property
Strength property
Longitudinal tensile strength (min) D3039, D5083, D638, D3916 100.0 ksi (690 MPa) 80.0 ksi (552 MPa)
Transverse tensile strength (min) D3039, D5083, D638 NA 4.0 ksi (28 MPa)
Longitudinal compressive strength (min) D3410, D695 75.0 ksi (517 MPa) 80.0 ksi (552 MPa)
Transverse compressive strength (min) D3410, D695 NA 10 ksi (69 MPa)
Long. short beam shear strength (min) D2344, D4475 7.0 ksi (48 MPa) 5.5 ksi (38 MPa)
Stiffness property
Longitudinal tensile modulus (min) D3039, D5083, D638 5.5 Msi (38 GPa) 4.5 Msi (31 GPa)
Longitudinal compressive modulus (min) D3410, D695 NA 4.0 Msi (28 GPa)
in-plane shear stiffness (min) D5379 NA 0.40 Msi (3 GPa)
Major (longitudinal) Poisson ratio (min) D3039, D5083, D638 0.25 0.25
Physical property
Fiber volume fraction (min) D3171, D2584 55% 45%
Barcol hardness (min) D2583 50 50
Glass transition temperature (min) E1356, D3418 203 F (95 C) 203 F (95 C)
Water absorption (max) D570 (immersion at 50 C for 48 h) 1.0% 1.5%
Long. coeff. of thermal expansion (max) D696 6 · 10 6/F (11 · 10 6/C) 6 · 10 6/F (11 · 10 6/C)
Trans. coeff. of thermal expansion (max) D696 NA 30 · 10 6/F (54 · 10 6/C)

Table 3
Limiting physical and mechanical properties for FRP rebar
Material property ASTM test GV1 material
Mechanical property
Strength property
Longitudinal tensile strength (min) D5083 90.0 ksi (620 MPa)
Longitudinal compressive strength (min) D3410 68.0 ksi (465 MPa)
Long. short beam shear strength (min) D2344 5.5 ksi (38 MPa)
Stiffness property
Longitudinal tensile modulus (min) D3039, D5083, D638 5.5 Msi (38 GPa)
Longitudinal compressive modulus (min) D3410 4.1 Msi (28 GPa)
Physical property
Fiber volume fraction (min) D3171, D2584 55%
Barcol hardness (min) D2583 50
Glass transition temperature (min) E1356, D3418 203 F (95 C)
Water absorption (max) D570 (immersion at 50 C for 48 h) 1.0%
Long. coeff. of thermal expansion (max) D696 6 · 10 6/F (11 · 10 6/C)
Trans. coeff. of thermal expansion (max) D696 30 · 10 6/F (54 · 10 6/C)

independent quality assurance tests for the client (Wis- April. The FRP materials arrived on the construction
DOT). The six quality assurance tests performed were: site in mid-March of 2003. The quality assurance tests
longitudinal tension, longitudinal short beam shear, fi- were conducted in March and April and the placement
ber volume fraction, water absorption, dimensional tol- of the FRP deck panels began at the end of May 2003.
erance, and aggregate distribution. The first four tests After the concrete girders were placed, a haunch was
were performed on each FRP material. The remaining developed to create the required elevation of the FRP
two tests were performed on the FRP deck panels only. deck forms and to maintain a uniform thickness of the
After all of the materials were shown to have met the deck. When conventional steel reinforced decking is
material specifications, the resident engineer gave ap- used, the haunch is formed with the removable plywood
proval for placement of the FRP materials. forms. Since the FRP deck panels served as stay-in-place
forms, an alternative method of haunching was needed.
This was accomplished by supporting the deck panels on
5. Construction process the girders using a variable height rigid cellular polysty-
rene foam, which was installed prior to placing the con-
Construction of the bridge began early in 2003. The crete. The polystyrene haunches were attached to the
abutments and center pier were completed in February edges of the top flange of the concrete girders (Figs. 6
and the prestressed concrete girders were placed in early and 7) with an epoxy adhesive, except for the outsides
A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526 521

tween the deck panels to prevent concrete from leaking


between the panels during the pour. The bead was not
intended to provide load transfer in the longitudinal
direction between the panels. The epoxy-coated screws
were installed to secure the ends of the panels to pre-
vent uplift in the event of high winds prior to the pour.
The screws were not intended to provide any fixity be-
tween the panels or between the panels and the girders.
Laboratory testing of the FRP reinforced deck sys-
tem was conducted prior to the construction. Punching
shear, negative and positive moment bending, and fati-
gue tests were conducted to determine the capacity of
the deck system and the load transfer capacity at the pa-
nel splice [3], [10]. Freeze–thaw tests were conducted to
Fig. 6. Haunch detail. investigate deterioration in the FRP to concrete bond
in the FRP deck panels [11]. The testing indicated that
of the exterior girders where conventional plywood the FRP reinforcement system could reliably carry the
formwork was used for the cantilevered overhang and design loads and was expected to be durable in freeze–
parapet. thaw conditions.
The FRP deck panels were then placed on the foam During preconstruction meetings, the bridge con-
(Fig. 8). To account for the 32 skew, the end panels tractor expressed concern over the ability of the con-
were precut to the required angle prior to placement. crete (specified to have a maximum large aggregate
The hollow tubular cells at the ends of the panels were size of 18 mm (3/4 in.) and a nominal compressive
filled with expandable polyurethane foam to prevent strength of 28 MPa (4000 psi)) to flow into the gap
wet concrete and mix water from flowing into the cav- between the top of the girder and the bottom of the
ities. All of the individual components were light en- deck panel to provide permanent support for the deck
ough for two construction workers to carry. Prior to panel. To solve this problem, a flowable grout was
a deck panel being positioned, a bead of silicone caulk used to fill the cavity between the foam haunches
(Fig. 9) was placed on the lip of the previously placed prior to the concrete deck being poured. Following
deck panel. An epoxy-coated screw was installed at the the installation of all of the deck panels, the grout
end of each deck panel at the lap splice (Fig. 10). The was placed up to the bottom lip of the deck panel
bead of silicone caulk was placed to provide a seal be- (Fig. 11) and vibrated to ensure it filled all of the

Fig. 7. Concrete girders and rigid cellular polystyrene haunches.


522 A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526

Fig. 8. SIP FRP deck panel placement.

Fig. 9. Silicone bead application.

voids below the FRP form. The surface of the grout The rebars were cut and placed to accommodate the 32
was roughened to provide sufficient friction between skew. The 25 mm (#8) rebars were spaced at 100 mm
the girders and the concrete deck to ensure composite (4 in.) on center at the center pier. Larger spacing and
action (together with the steel stirrups protruding smaller bars were used at further distances from the cen-
from the top flange of the girders.) ter pier. The epoxy coated steel bars used in the parapet
The FRP rebars were then placed parallel to the con- and deck cantilever were installed at the same time as
crete girders and were supported by continuous plastic the FRP bars. The continuous plastic chairs supported
chairs, which sat on the tubular cells of the deck panels. the steel rebars.
A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526 523

Fig. 10. Installation of epoxy coated screw.

The FRP grid was then placed on top of the re- 6. Construction costs
bars. The T-bars for the grid were laid perpendicularly
to the FRP rebars (Fig. 12). The grids were placed in During construction, data on the materials and labor
three segments across the bridge width, the two longer were recorded to provide a comparison between the two
sections on the outside and the shorter section in the bridges. The total material costs for the FRP reinforced
middle. The thickness of the concrete deck was in- bridge were $632,718. The material costs for the steel
creased from 200 mm (8 in.) as originally planned to reinforced bridge were $391,649.53. This translates to
215.9 mm (8.5 in.) to allow for the required top cover over a 60% materials cost increase over the conventional
over the grid at the center of the bridge. The grid was construction (i.e., the materials for the bridge with the
stiff and it was thought it would not bend sufficiently steel deck cost 3/5 that of bridge with the FRP deck).
to form the center crown so extra concrete cover was The cost of the individual FRP components was
required. The ends of all FRP materials were sealed $167,637.60 (deck panels), $64,922.40(grid), and
prior to the pour with the same epoxy that was used $25,369.10(rebar) for a total FRP material cost of
to adhere the aggregate to the horizontal surfaces of $257,929.10. The cost of the steel reinforcement was
the deck panel. $37,060.10. Since this was the first time FRP materials
The deck pour (Fig. 13) began at 6 a.m. on June had been used as bridge deck reinforcement in Wiscon-
11th 2003 and was completed by 10 a.m. (4 h total). sin, the FRP manufacturers and cost of the material
A total of 179 m3 (234 yd3) of concrete were placed. were predetermined. They were both set in the FRP
The concrete pour for the steel reinforced bridge took specifications prior to when the project was let for bid-
5 h. About 145 m3 (190 yd3) of concrete was placed. ding. With competitive bidding between FRP manufac-
There were approximately 10 other bridges at this site turers, increased use, and further design optimization,
of similar size. The FRP reinforced bridge deck was the cost of the FRP system, especially the deck panel
the fastest of the deck pours. Several workers com- (which accounted for over 26% of the total bridge cost),
mented on the ease of working on the level grid as could decrease in the future.
opposed to the uneven rebars of conventional steel An advantage in the use of FRP materials was seen
reinforced decks. The parapets were poured about in labor savings. Five hundred and eighty five man-
one week after the deck. To do this fully loaded con- hours were required to install and remove the formwork
crete trucks were driven up onto the deck giving it its on the steel reinforced bridge. The steel reinforcement
first unofficial load test. The completed bridge is was placed in 128 man-hours. Two hundred and six
shown in Fig. 14. It was opened to traffic in the sum- man-hours were required to place the polystyrene
mer of 2004 when the approach ramps and connection haunches and set the FRP deck panels in place. The
roadways were completed. two other components of the FRP reinforcement, the
524 A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526

Fig. 11. Roughened grout between SIP FRP deck panels.

grid and rebars, were placed in 104 man-hours. A total struction labor over a nominally identical steel rebar
of 713 h were spent on the decking and placement of reinforced deck. Material costs for the FRP reinforced
reinforcement on the steel reinforced bridge deck com- deck bridge were 60% higher than that of the steel rein-
pared to 310 h on the FRP reinforced bridge deck. This forced deck bridge. At this time the long-term benefit
translates to a 57% savings in labor costs. An advantage due to the anticipated superior durability of the FRP
was also seen in the productivity of the concrete pour. reinforced deck is not possible to ascertain. Long-term
The rate of concrete placement on the FRP reinforced monitoring of this and other FRP bridge deck projects
deck was 51.15 m3 (66.9 yd3) per hour compared with in the State of Wisconsin will be conducted to develop
29.05 m3 (38.0 yd3) per hour for the steel reinforced this data, which will be reported periodically. It appears
deck. that given the savings in construction time and the po-
tential long-term benefits, FRP reinforcements for
bridge decks should be cost-effective, notwithstanding
7. Conclusions their currently high initial costs. Future optimization
of the design of FRP stay-in-place formwork and com-
The construction of an FRP reinforced concrete petitive bidding between FRP manufacturers is recom-
bridge deck using conventional construction technology mended to decrease the cost of the FRP reinforcement
and labor was accomplished with a 57% savings in con- system. In addition, the use of larger prefabricated
A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526 525

Fig. 12. SIP FRP deck panels, FRP rebars, and bi-directional FRP grid during placement.

Fig. 13. Pouring and vibration of concrete at FRP reinforced bridge deck.

FRP grids in place of the FRP rebars may yield yet more that include both material and construction specifica-
labor and time savings. tions for the FRP components is a vital part of the pro-
The importance of close communication between the cess. Manufacturer quality control testing and
FRP material manufacturers, the construction contrac- independent client quality assurance testing of the as-
tor, the bridge designers, and the local authorities can- delivered (as-received) FRP materials is necessary to en-
not be over-emphasized with regard to successful sure compliance with specifications and to develop the
completion of a novel FRP project of this type. Further- required regulatory approvals for large infrastructure
more, the development of detailed special provisions, projects of the type reported in this paper.
526 A.C. Berg et al. / Construction and Building Materials 20 (2006) 515–526

Fig. 14. Completed FRP reinforced bridge deck.

Acknowledgements [4] Bank LC, Oliva MG, Russell JS, Dieter DA, Dietsche JS, Hill
RA, et al.. Details and specifications for a bridge deck with FRP
formwork, grid and rebar. In: Tan KW, editor. Proceedings of
The authors acknowledge the following people for FRPRCS-6, Singapore, July 8–10, 2003. p. 1301–10.
their contributions: John Hooks and Tom Strock [5] Nystrom HE, Watkins SE, Nanni A, Murray S. Financial viability
(FHWA), Gerry Anderson, Mark Klipstein, and Stan of fiber-reinforced polymer (FRP) bridges. ASCE J Manage Eng
Woods (Wisconsin Department of Transportation), 2003;19(1):2–8.
Jay Carter, Bernie Gallagher, and Rich Hill (Alfred [6] Shapira A, Bank LC. Constructibility and Economics of FRP
reinforcement cages for concrete beams. ASCE J Compos Constr
Benesch and Company), Ceci Peroni (CH2MHill), 1997;1(3):82–9.
‘‘Cricket’’ (Lunda Construction), and the financial [7] ACI 440.1 R-01. Guide for the design and construction of
support from the Innovative Bridge Research and concrete reinforced with FRP bars, ACI International, Farming-
Construction Program (IBRC). ton Hills, Michigan, 2001.
[8] Bank LC, Gentry TR, Thompson BP, Russell JS. A model
specification for FRP composites for civil engineering structures.
Constr Build Mater 2003;17(6–7):405–37.
References [9] Dietsche JS. Development of material specification for FRP
structural elements for the reinforcing of a concrete bridge deck,
[1] Rizkalla S, Nanni A. Field applications of FRP reinforce- MS Thesis, University of Wisconsin–Madison, 2002.
ment: case studies, SP-215. Farmington Hills, Michigan: ACI [10] Dieter DA. Experimental and analytical study of concrete bridge
Int; 2003. decks constructed with FRP stay-in-place forms and FRP grid
[2] Reising RMW, Shahrooz BM, Hunt VJ, Lenett MS, Christorper reinforcing, MS Thesis, University of Wisconsin–Madison, 2002.
S, Neumann AR, et al.. Performance of five-span steel bridge [11] Helmueller EJ, Bank LC, Dieter DA, Dietsche JS, Oliva MG,
with fiber-reinforced polymer composite deck panels. Transport Russell JS. The effect of freeze–thaw on bond between FRP stay-
Res Rec 2001;1770:113–23. in-place deck forms and concrete. In: Benmokrane B, editor.
[3] Dieter D, Dietsche J, Bank L, Oliva M, Russell J. Concrete bridge Proceedings of the 2nd international conference on durability of
decks constructed with fiber-reinforced polymer stay-in-place fiber reinforced polymer (FRP) composites for construction,
forms and grid reinforcing. Transport Res Rec 2002;1814:219–26. Montreal, Canada, May 29–31, 2002. p. 141–52.

You might also like