RIG ACCEPTANCE CHECKLIST PRIOR TO SPUD (NEW WELL)

The rig is moved to the new location BB-961. The substructure and mast are rigged-up. The rotary table
centre is centred with the conductor pipe.Rig accepted on 1500 hrs on 8th Oct 2012.

Confirmation of task Acceptance of task


Item Description of the critical Task completed by NDC completed by
no. RM ADCO DS

Rigged up the following : 1. Mud pumps 2.Mud system


1 3. Water tanks 4. Power units 5. Fire fighting unit 6.
Workshop 7. Fuel tanks 8. Koomey unit 9. Pipe racks
with minimum 2 sets and 10. Catwalk. Yes Yes

Available on location : Drill collars 9 ", 8 ", 7" or 6 "


2 and HWDP. BHA and handling equipment as required for
top hole and one drill pipe bin to make atleast 15 - 20
stands. Yes Yes

3 Cement unit. One or two cement silos. Surge tank.


Compressor. Cement line to rig floor. Water supply line
from mud system to cement unit. Yes Yes

4 Fly camp. RM/DS office skid and mudlab skid. fly camp not
available.Crew stay in RM/DS/mud lab rig
central camp up & power OK.
5
Adequate mud chemicals available to mix spud mud. Yes Yes

6 Reda pumps installed for water supply and the lines to


the mud system. Yes Yes

7 Function tested mixing hoppers, degasser, solids control


equipment, mud agitators, PVT system and the cellar jet. Yes Yes
8 Nipple up the flow line with the conductor pipe. Yes Yes

9 A quantity of 1000 bbls spud mud being mixed with


water as the make up fluid. 1500 BBls available yes
10 Tested stand pipe manifold and pump lines. 3000 psi OK Yes

11 electrical pump Repaire back up


Tested the fire fighting system (units and spray nozzle OK,mech engine not engine at the
system) working. earliest
12 Function tested all driller console gauges and controls
Yes Yes
13 Function tested crown-O-matic. Yes Yes
14 Function tested stabbing board. Yes Yes
RM and DS HSE tour, HSE meeting with crew and rig
15 acceptance. Yes Yes
Rig Manager Drilling Supervisor