ACCOUNTING FOR

CONSTRUCTION CONTRACTS

Topic 3 - Construction contract 1


To understand the nature of Construction
Contracts (CC)
To discuss the accounting issues related with
treatment and recognition in Construction
Contracts industry
To know the presentation and disclosure
requirement of the CC financial statements

Topic 3 - Construction contract 2


Introduction
Definitions of terminology
Nature and activity of industry
Current Regulations and Standards
Types of Contract
Fixed Price Contract
Cost Plus Contract
Combining and Segmenting Construction
Contract
Combining Construction Contract
Segmenting Construction Contract
Contract Costs

Topic 3 - Construction contract 3


Contract Revenues
Determination and Valuation
Recognition
Presentation and Disclosure Requirement
Conclusion
References
Discussion Questions
Tutorial Questions

Topic 3 - Construction contract 4


Comprise of a complex combination of peoples, plants,
materials, locations, technology and knowledge of the
law.
Covers a wide range of activities from the building of
dams to office blocks, housing, infrastructure project,
etc.
Involved many parties includes construction owner, sub-
contractor, architect, engineer, lawyer, etc.
Because of their nature, normally this industry covers
more than one accounting period.
The main issue facing by the accountant in this industry
are related with the allocation of costs and revenues
derived to the particular period in which construction
work is performed.

Topic 3 - Construction contract 5


Construction contract a contract specifically
negotiated for the construction of an assets or
combination of assets that are closely interrelated in
term of design, technology and function or their
ultimate purpose or use.
Fixed price contract a construction contract in
which the contractor agrees to a fixed contract price
or a fixed rate per unit of output.
Cost plus contract - a construction contract in which
the contractor is reimbursed for allowable or
otherwise defined costs, plus a percentage of these
costs or a fixed rate.
Contract revenue consist of initial amount of
revenue agreed in the contract and variation in
contract work, claims and incentive payment.

Topic 3 - Construction contract 6


Claims an amount that the contractor seeks
to collect from the customer or another
party as a reimbursement for costs not
included in contract price.
Incentives additional amount paid to
contractor if specific performance standard
are met or exceeded.
Progress billing amounts billed for work
performed on a contract whether or not the
customer has paid them.
Advances are amount received by the
contractor before the related work is
performed.

Topic 3 - Construction contract 7


Normally involved various parties.
Covers wide range of works.
Complex combination of people, plant, technology,
machine, materials and knowledge of law.
Starting date and completion/end date usually fall
into different accounting period.

Topic 3 - Construction contract 8


The current effective accounting standards is
MFRS 111 which is become operative starting
1st January 2012.
is FRS 111, Accounting for
Previously
Construction Contract
IAS11 (revised) and MASB 7.
Main purpose of the MFRS 111 is to prescribe
the accounting treatment of revenue and costs
associated with construction contracts.

Topic 3 - Construction contract 9


A fixed price contract - is a construction
contract in which the contractor agrees to a
fixed contract price, or a fixed rate per unit of
output, which in some cases is subject to cost
escalation clauses.
A cost plus contract- is a construction contract
in which the contractor is reimbursed for
allowable or otherwise defined costs, plus a
percentage of these costs or a fixed fee

Topic 3 - Construction contract 10


Contract revenues comprises of:
(a) the initial amount of revenue agreed in the
contract
(b) variations in contract work, claims and incentive
payments:
(i) to the extent that it is probable that they will
result in revenue; and
(ii) they are capable of being reliably measured.
Contract revenue is measured at the fair value of
the consideration received or receivable.
The measurement of contract revenue is affected
by a variety of uncertainties that depend on the
outcome of future events.

Topic 3 - Construction contract 11


Variation Claim Incentive Payment
A variation is an A claim is an amount Incentive payments
instruction by the that the contractor are additional
customer for a change seeks to collect from amounts paid to the
in the scope of the the customer or contractor if specified
work to be performed another party as performance
under the contract. reimbursement for standards are met or
Examples of costs not included in exceeded.
variations are changes the contract price. For example, a
in the specifications A claim may arise contract may allow
or design of the asset from, customer for an incentive
and changes in the caused delays, errors payment to the
duration of the in specifications or contractor for early
contract. design, and disputed completion of the
variations in contract contract.
work.

Topic 3 - Construction contract 12


In the case of a fixed price contract, the outcome of
a construction contract can be estimated reliably
when all the following conditions are satisfied:
(a)total contract revenue can be measured reliably;
(b)it is probable that the economic benefits
associated with the contract will flow to the entity;
(c)both the contract costs to complete the contract
and the stage of contract completion at the balance
sheet date can be measured reliably; and
(d)the contract costs attributable to the contract can
be clearly identified and measured reliably so that
actual contract costs incurred can be compared with
prior estimates.

Topic 3 - Construction contract 13


In the case of a cost plus contract, the
outcome of a construction contract can be
estimated reliably when all the following
conditions are satisfied:
(a)it is probable that the economic benefits
associated with the contract will flow to the
entity; and
(b)the contract costs attributable to the
contract, whether or not specifically
reimbursable, can be clearly identified and
measured reliably.

Topic 3 - Construction contract 14


Contract costs shall comprise:
(a) costs that relate directly to the
specific contract
(b) costs that are attributable to
contract activity in general and can
be allocated to the contract
(c) such other costs as are
specifically chargeable to the
customer under the terms of the
contract
Topic 3 - Construction contract 15
Costs that relate directly (DC) to a specific contract include:
(a) site labour costs, including site supervision;
(b) costs of materials used in construction;
(c) depreciation of plant and equipment used on the
contract;
(d) costs of moving plant, equipment and materials to and
from the contract site;
(e) costs of hiring plant and equipment;
(f) costs of design and technical assistance that is directly
related to the contract;
(g) the estimated costs of rectification and guarantee work,
including expected warranty costs; and
(h) claims from third parties.

Topic 3 - Construction contract 16


Coststhat may be attributable (indirect cost)
to contract activity in general and can be
allocated to specific contracts include:
o (a) insurance
o (b) costs of design and technical assistance that
are not directly related to a specific contract
o (c) construction overheads
o (d) borrowing costs
The allocation is based on the normal level
of construction activity.

Topic 3 - Construction contract 17


Costs that cannot be attributed to contract
activity or cannot be allocated to a contract are
excluded from the costs of a construction
contract(non-allocated cost-NAC). Such costs
include:
(a) general administration costs for which
reimbursement is not specified in the contract
(b) selling costs
(c) research and development costs for which
reimbursement is not specified in the contract
(d) depreciation of idle plant and equipment that
is not used on a particular contract.

Topic 3 - Construction contract 18


The requirements of this Standard are usually
applied separately to each construction
contract. However, in certain circumstances, it
is necessary to apply the Standard to the
separately identifiable components of a single
contract or to a group of contracts together in
order to reflect the substance of a contract or a
group of contracts.

Topic 3 - Construction contract 19


When a contract covers a number of assets, the
construction of each asset shall be treated as a
separate construction contract(SCT) when:
(a)separate proposals have been submitted for
each asset;
(b)each asset has been subject to separate
negotiation and the contractor and customer
have been able to accept or reject that part of
the contract relating to each asset; and
(c)the costs and revenues of each asset can be
identified.
Topic 3 - Construction contract 20
A group of contracts, whether with a single
customer or with several customers, shall be
treated as a single construction contract when:
(a)the group of contracts is negotiated as a
single package;
(b)the contracts are so closely interrelated that
they are, in effect, part of a single project with
an overall profit margin; and
(c)the contracts are performed concurrently or
in a continuous sequence.

Topic 3 - Construction contract 21


A contract may provide for the construction
of an additional asset at the option of the
customer or may be amended to include the
construction of an additional asset. The
construction of the additional asset shall be
treated as a separate construction contract
when:
(a)the asset differs significantly in design,
technology or function from the asset or
assets covered by the original contract; or
(b)the price of the asset is negotiated
without regard to the original contract price.

Topic 3 - Construction contract 22


The estimates often need to be revised as events occur and
uncertainties are resolved. Therefore, the amount of contract
revenue may increase or decrease from one period to the next.
For example:
(a) a contractor and a customer may agree to variations or
claims that increase or decrease contract revenue in a
period subsequent to that in which the contract was
initially agreed;
(b) the amount of revenue agreed in a fixed price contract
may increase as a result of cost escalation clauses;
(c) the amount of contract revenue may decrease as a result
of penalties arising from delays caused by the
contractor in the completion of the contract; or
(d) when a fixed price contract involves a fixed price per
unit of output, contract revenue increases as the number
of units is increased.

Topic 3 - Construction contract 23


When the outcome of a construction contract can be
estimated reliably, contract revenue and contract
costs associated with the construction contract shall
be recognized as revenue and expenses respectively
When the outcome of a construction contract cannot
be estimated reliably:
(a) revenue shall be recognized only to the extent of
contract costs incurred that it is probable will be
recoverable; and
(b) contract costs shall be recognized as an expense in
the period in which they are incurred.
Contract costs that are not probable of being
recovered and expected loss on the construction
contract shall be recognized as an expense
immediately.
Topic 3 - Construction contract 24
Anentity is generally able to make reliable
estimates after it has agreed to a contract
which establishes:
Each partys enforceable rights regarding the
assets
The consideration to be exchanged
The manner and terms of settlement

Topic 3 - Construction contract 25


The recognition of revenue and expenses by reference to the stage of
completion of a contract is often referred to as the percentage of completion
method.
Under this method, contract revenue is matched with the contract costs
incurred in reaching the stage of completion, resulting in the reporting of
revenue, expenses and profit which can be attributed to the proportion of work
completed.
The stage of completion of a contract may be determined in a variety of ways.
The entity uses the method that measures reliably the work performed.
Depending on the nature of the contract, the methods may include:
(a) the proportion that contract costs incurred for work performed to date
bear to the estimated total contract costs; Cost Based Method
(b) surveys of work performed; or
(c) completion of a physical proportion of the contract work.
(b) and (c) - Value Based Methods

Progress payments and advances received from customers often do not reflect
the work performed.

Topic 3 - Construction contract 26


Expected losses occur when total contract costs
exceed total contract revenue.
An expected loss shall be recognized as an
expense immediately in accordance with
paragraph 36 of MFRS111.
The amount of these expected losses is
determined irrespective of;
Whether work has commenced on the contract
the stage of completion of contract activity
the amount of profits expected to arise on other
contracts which are not treated as a single
construction contract in accordance with paragraph
9.

Topic 3 - Construction contract 27


Anyeffect from the changes of the contract
revenue or costs due to the determination of
the percentage of completion should be
treated as a changes in accounting
estimation (MFRS 108 Accounting Policies,
Changes in Accounting Estimates and Errors).

Topic 3 - Construction contract 28


Must be accordance to MFRS 101
The Balance sheet should classify the assets and
liabilities based on current and non current.
Thestatement of comprehensive income should
present:
Revenues
Finance costs
Share of profits and losses of associates and joint
ventures accounted
Tax expense
Profit or loss

Topic 3 - Construction contract 29


Disclosure Requirement
An entity shall disclose:
a) The amount of contract revenue recognized as
revenue in the period.
b) The method used to determine the contract
revenue recognized in the period
c) The method used to determine the stage of
completion of contracts in progress.

Topic 3 - Construction contract 30


Examples of Accounting Policy
Disclosures
The following are examples of accounting policy
disclosures:
Revenue from fixed price construction contracts is
recognised on the percentage of completion method,
measured by reference to the percentage of labour hours
incurred to date to estimated total labour hours for each
contract.
Revenue from cost plus contracts is recognised by
reference to the recoverable costs incurred during the
period plus the fee earned, measured by the proportion
that costs incurred to date bear to the estimated total costs
of the contract
Topic 3 - Construction contract 31
Disclosure of construction Contracts in Progress
For contracts in progress, at the balance sheet date, para 41
of FRS111 stated that an entity shall disclose:
a) The aggregate amount of costs incurred and recognised
profits (less recognised losses) to date.
Note that if the net amount of the above is a positive
figure, the construction in progress should be shown
under the current assets, otherwise it should shown
as current liability.
Also, if one contract has a positive figure, i.e. gross
amount due from customer, and another has a
negative figure, i.e. gross amount due to customer
for contract work they should be shown seperately
b) The amount of advances received
c) The amount of retentions.
Topic 3 - Construction contract 32
Retentions
-the amounts of progress billing that are not paid until the
satisfaction of conditions specified in the contract for the
payment of such amounts or until defects have been
rectified.
Progress billings
-the amounts billed for worked performed for work
performed on a contract whether or not they have been
paid by the customer..
Advances
-The amounts received by the contractor before the
related work is performed

Topic 3 - Construction contract 33


Presentation of Construction Contract
An entity shall present:
a) The gross amount due from customers for contract work as
asset.
b) The gross amount due to customers for contract work as
liability.

The gross amount due from customers for contract work is the
net amount of:
a) Costs incurred plus recognized profits
b) The sum of recognized losses and progress billings
for all contracts in progress for which costs incurred plus
recognized profits (less recognized losses) exceeds progress
billings.

Topic 3 - Construction contract 34


The gross amount due to customers for contract work is
the net amount of:
a) Costs incurred plus recognized profits
b) The sum of recognized losses and progress billings.
for all contracts in progress for which progress billings
exceed costs incurred plus recognized profits (less
recognized losses).

Topic 3 - Construction contract 35


Disclosure
An entity also shall discloses any contingent
liabilities and contingent assets in accordance
with FRS 137 Provisions, Contingent Liabilities
and Contingent Assets. Contingent liabilities
and contingent assets may arise from such items
as warranty costs, claims, penalties or possible
losses.

Topic 3 - Construction contract 36


-construction contract is a contract specifically
negotiated for the construction of an asset or a
combination of assets that are closely interrelated or
interdependent in terms of their design, technology and
function or their ultimate use or purpose.
-Normally, the construction activities involve more than
one accounting period.
-Main accounting issue in this industry is related with
the allocation of contract revenue and contract costs to
the accounting periods in which construction work is
performed.

Topic 3 - Construction contract 37


1. MFRS 111
2. The Nature of Construction Contract. Retrieved on November 19,
2011 from http://www.palgrave.com/PDFs
3. Introduction to Construction Contract Administration. Retrieved on
November 19, 2011 from http://media.wiley.com

Topic 3 - Construction contract 38


Example 1 - Construction Contract Accounting using
Value Based Approach
ABC Builders Bhd is a construction firm. It enters into a 2
year contract for the construction of a building for one of its
customers. ABC Builders Bhd estimates stage of completion
on the basis of value of work completed. Following
information is available in respect of the contract at the end
of first year:

Topic 3 - Construction contract 39


RM

Total Contract Price 2,000,000

Total Expected Costs 1,200,000

Costs incurred to Date 800,000

Value of work certified as complete 1,000,000

Amount billed to customer 900,000


Progress payments received from
700,000
customer

Topic 3 - Construction contract 40


Step 1 - Determine Expected Outcome of the Contract
As the total contract revenue (RM2m) exceeds total
expected contract costs (RM1.2m), the contract is
expected to be profitable. Therefore costs and revenue
be accounted for using stage of completion method.
Total Profit under the contract is expected to be
RM800,000.

Topic 3 - Construction contract 41


Step 2 - Calculate the Stage of Completion
Stage of completion may be calculated as
follows:
Stage of Completion % = [ RM1,000,000 /
RM2,000,000] x 100 = 50 %

Topic 3 - Construction contract 42


Step 3 - Determine the amounts to be recognized
in Income Statement for Profit, Revenue and Cost
When stage of completion is calculated using
value based method, revenue to be recognized is
equal to the value of work certified as complete.
Profit is calculated based on the percentage of
completion of the contract whereas cost
recognized in the income statement is the
balancing amount arrived by calculating the
difference between revenue and profit.

Topic 3 - Construction contract 43


RM

Revenue (Value of work Certified) 1,000,000

Profit (800,000 x 50%) 400,000

(Balancing Amount: [1,000,0000 -


Cost (600,000)
400,000])

Topic 3 - Construction contract 44


Step 4 - Calculate amounts to be
recognized in the Balance Sheet for Gross
Amounts due to/ from Customers and Trade
Receivables
Trade Receivables are calculated finding the
difference between amount billed to the
customer for progress payments and the
amount of progress payments received from
the customer.
Trade Receivable of ABC Builders Bhd should
therefore be calculated as follows:

Topic 3 - Construction contract 45


Trade Receivable = 900,000 (Amount Billed) - 700,000
(Amount Received) = RM200,000
Gross Amount due from Customers is calculated by
deducting the amount billed to customer (along with
any losses recognized) from the sum of profit
recognized and costs incurred to date.
Gross Amount due from Customers of ABC Builders Bhd
must therefore be calculated as follows:
Gross Amount due from Customer = 400,000 (Profit) +
800,000 (Cost Incurred) - 900,000 (Amount Billed) = RM
300,000

Topic 3 - Construction contract 46


Step 5 - Prepare Extracts of Financial Statements in respect of
Construction Contracts

ABC Builders Bhd


Income Statement (Extracts for the Year 1)

RM

Revenue 1,000,000

Cost (600,000)

Profit 400,000

Topic 3 - Construction contract 47


ABC Builders Bhd
Balance Sheet (Extracts at the end of the Year 1)

Current Assets RM
Trade Receivables 200,000
Gross Amount due from Customers 300,000

Topic 3 - Construction contract 48


Step 6 - Prepare Construction Contract
Control Account
Although not a part of the double entry
system, control accounts may be useful to
confirm the overall accuracy of accounting
entries relating to construction contracts.
ABC Builders Bhd's control account would
appear as follows:

Topic 3 - Construction contract 49


Contract Control Account
Debit RM Credit RM
Revenue
1,000,000 Cost Recognized 600,000
Recognized
Amount Received
Costs Incurred 800,000 700,000
from customer
Trade Receivable 200,000
Amount due from
300,000
customer
1,800,000 1,800,000

Topic 3 - Construction contract 50