REINFORCEMENT INSTALLATION ACTIVITY

Footing Pcs L&W #L-W #bars kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
F1 10 4.2 53 371 5498.2 10 300 10 100 5498.2 6.9 20,618.33
F2 4 3 33 66 978.1 5 300 10 50 978.1 2.4 3,667.95
F3 10 3.6 42 252 3734.6 10 300 10 100 3734.6 4.7 14,004.90
14.0 38,291.18

Footing Tie
Beam Pcs main web stir kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
FTB 38 304 76 494 7054.5 25 300 10 250 7054.5 3.53 26,454.56
3.5 26,454.56

Beam (2nd
Floor) Pcs main stir length kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
B1 6 48 21 5 789.1 3 300 10 30 789.1 3.3 2,959.13
B2 32 316 112 5 5097.7 5 300 10 50 5097.7 12.7 19,116.54
B3 11 69 39 5 1165.1 4 300 10 40 1165.1 3.6 4,369.15
b3 3 8 3 1.6 131.0 3 300 10 30 131.0 0.5 491.25
b3 3 13 7 3.4 219.1 3 300 10 30 219.1 0.9 821.60
b3 2 8 4 2.75 132.8 3 300 10 30 132.8 0.6 498.05
B4 1 5 3 4 84.5 3 300 10 30 84.5 0.4 316.75
CB1 13 59 31 3.4 988.9 4 300 10 40 988.9 3.1 3,708.45
CB2 6 16 7 1.6 262.0 3 300 10 30 262.0 1.1 982.49
CB3 1 4 2 2.5 65.8 3 300 10 30 65.8 0.3 246.59
26.5 33,509.99

Man-hour rate = kg/hr per worker


hr. rate = kg/hr
Qty of Work = kg
Duration = days (8hrs/day)

Page 1
Sheet1

Footing Pcs L&W #L-W #bars kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price

Beam
(Roof deck) Pcs main stir length kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
B1 6 48 21 5 789.1 3 300 10 30 789.1 3.3 2,959.13
B2 33 328 116 5 5288.5 5 300 10 50 5288.5 13.2 19,832.03
B3 11 69 39 5 1165.1 4 300 10 40 1165.1 3.6 4,369.15
b3 3 8 3 1.6 131.0 3 300 10 30 131.0 0.5 491.25
b3 3 13 7 3.4 219.1 3 300 10 30 219.1 0.9 821.60
b3 2 8 4 2.75 132.8 3 300 10 30 132.8 0.6 498.05
B4 1 5 3 4 84.5 3 300 10 30 84.5 0.4 316.75
CB1 13 59 31 3.4 988.9 4 300 10 40 988.9 3.1 3,708.45
CB2 6 16 7 1.6 262.0 3 300 10 30 262.0 1.1 982.49
CB3 1 4 2 2.5 65.8 3 300 10 30 65.8 0.3 246.59
27.0 34,225.48

Beam
(Roof Plan) Pcs main stir length kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
B2 1 10 4 5 161.2 2 300 10 20 161.2 1.0 604.34
B3 1 7 4 5 116.7 2 300 10 20 116.7 0.7 437.61
B4 3 16 8 4 268.2 2 300 10 20 268.2 1.7 1,005.81
B5 11 79 39 5 1313.3 5 300 10 50 1313.3 3.3 4,924.90
CB1 1 4 2 3.4 68.1 2 300 10 20 68.1 0.4 255.34
CB2 3 8 3 1.6 131.0 3 300 10 30 131.0 0.5 491.25
CB3 1 4 2 2.5 65.8 2 300 10 20 65.8 0.4 246.59
8.1 7,965.85
Man-hour rate = kg/hr per worker
hr. rate = kg/hr
Qty of Work = kg
Duration = days (8hrs/day)

Page 2
Sheet1

Footing Pcs L&W #L-W #bars kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price

Column
(Footing to
GFFL) Vert. Ties kg pc height Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
C1 240 174 4201 10 2.7 15 300 10 150 4200.9 3.5 15,753.56
C2 168 192 3201 14 2.7 15 300 10 150 3200.5 2.7 12,002.04
6.2 27,755.60

Column
(GFFL to
2nd FFL) Vert. Ties kg pc height Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
C1 240 227 4397 10 3.9 15 300 10 150 4397.2 3.7 16,489.33
C2 168 251 3419 14 3.9 15 300 10 150 3419.0 2.8 12,821.11
6.5 29,310.44

Column
(2nd FFL to
Roof Deck) Vert. Ties kg pc height Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
C1 240 227 4397 10 3.9 15 300 10 150 4397.2 3.7 16,489.33
C2 168 251 3419 14 3.9 15 300 10 150 3419.0 2.8 12,821.11
6.5 29,310.44
Column
(Roof Deck
to Roof
Level) Vert. Ties kg pc height Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
C3 72 91 1404 6 4.7 13 300 10 130 1403.9 1.3 5,264.71
C4 32 62 703.76 4 4.7 8 300 10 80 703.8 1.1 2,639.12
2.4 7,903.82
Man-hour rate = kg/hr per worker
hr. rate = kg/hr
Qty of Work = kg
Duration = days (8hrs/day)

Page 3
Sheet1

Footing Pcs L&W #L-W #bars kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
Bars kg Workers Worker Cost Man-hour rate Hr. rate Qty of Work Duration Price
Slab (fill) 375 1388 10 300 10 100 1388.3 1.7 5,205.94

Slab (2nd) 1310 4850 15 300 10 150 4849.6 4.0 18,186.08

Slab (Roof) 1310 4850 15 300 10 150 4849.6 4.0 18,186.08

Roof Plan 390 1444 10 300 10 100 1443.8 1.8 5,414.18

Walls 797 2950 15 300 10 150 2950.5 2.5 11,064.35

Stairs 461 6832 15 300 10 150 6832.0 5.7 25,620.08

Roof plan is Slab (Roof Plan) Slab total 11.6 46,992.26


Slab & Walls 10mm dia. Wall & Stair total 8.2 36,684.43
Stairs 20mm dia.

Summary

Footing
FTB
Column
Beam
Slab
Stairs and Wall