YM-SAJCO JV

CTW 130 SADARA RAIL


PROJECT &
JUBAIL RAILWAY NETWORK
PROJECT

Permit to Work (PTW)

Project Name: CTW 130 Sadara Rail Project & Jubail Railway Code: CTW130-YMS-PTW-02
Network Project

Consultant: TYPSA CONSULTING ENGINEERS & ARCHITECS Edition: E01

Contractor: YM-SAJCO JV. Date (month in letters) 20/07/2017

Description of the work: Test Pile Works and Test Pile Access Roads Works

Location of the work: Package 5: KP 10+900 & 11+550

Start date: 24-07-2017 Date of completion: 18-09-2017

1.- Reference/Shop Drawings:

CTW130-SYS-FD-MAS-DWG-6927-A0
CTW130-SYS-FD-MAS-DWG-6928-A0
CTW130-SYS-FD-GEO-SPE-0199-E0 - Pile Load
Tests
CTW130-SJR-LET-SH-YMS-CR-17-00724
CTW130-SJR-LET-TYP-YMS-PM-17-00678

2.- Method Statements:

CTW130SJRTYPYMSMSPLW000014REV.03
CTW130SJRTYPYMSMSOGI000009REV.03
CTW130SJRTYPYMSMSOCT000010REV.03
CTW130-SJR-TYP-YMS-MS-GEW-00004-REV.01

3.- Stake Holders/Third Parties Affected:

ROYAL COMISSION FOR JUBAIL & YANBU CTW130-SJR-LET-TYP-YMS-PM-17-00678


ARAMCO CTW130-SJR-LET-SH-YMS-CR-17-00724

CTW130-QAC-TYP-PTW-E01 Page |1
Permit To Work
YM-SAJCO JV
CTW 130 SADARA RAIL
PROJECT &
JUBAIL RAILWAY NETWORK
PROJECT

Permit to Work (PTW)

4.- Subcontractors:

CTW130-LET-TYP-000633-E01 Kasktas Arabia Ltd as Subcontractor for Piling Works


CTW130-LET-TYP-000344-E01 Fountain Gulf

5.- Suppliers and Materials:

Sub-Grade
Base coarse
Rebar
Reinforced Concrete C35 (35 MPa)
O-Cell Equipment

6.- Manpower: 7.- Equipment:

PILING WORKS EARTH WORKS PILING WORKS EARTH WORKS


1 Site Manager 1 Engineer 1 Drilling Rig 1 Grader
1 Site Engineer 1 Foreman 1 Crawler Crane 1 Roller
1 Foreman 2 Operator 1 Loader
3 Operator 2 Flagman
4 Worker
1 Driver
1 Surveyor
2 Rigger

CTW130-QAC-TYP-PTW-E01 Page |2
Permit To Work
YM-SAJCO JV
CTW 130 SADARA RAIL
PROJECT &
JUBAIL RAILWAY NETWORK
PROJECT

Permit to Work (PTW)

8.- Work Planning/Schedule:

Construction Of Access Roads 24/07/2017 08/08/2017


Test Pile Equipment Mobilization 11/08/2017 21/08/2017
Pile Drilling 1st Test Pile 22/08/2017 29/08/2017
Pile Test 1st Test Pile 07/09/2017 12/09/2017
Pile Drilling 2nd Test Pile 02/09/2017 09/09/2017
Pile Test 2nd Test Pile 13/09/2017 18/09/2017

9.- Health, Safety and Environment:

Below documents are submitted for Heavy Equipment:


1. Equipment:
Brand Name
Model
Equipment ID
Plate Number
2. Operator Certificates:
Driving license
Iqama
Third Party
3. Equipment:
Vehicle Registration
Third Party Certificate
Insurance
Risk Assessment is included in the MS for General Earthworks
Risk Assessment is included in the MS for Piling Works
Risk Assessment is included in the MS for Installation and Load Testing of Pile Using the OCT
Risk Assessment is included in the MS for Lateral Loading Test

Author: Author: Approved By:

HSE Manager QA/QC Manager Construction Manager

CTW130-QAC-TYP-PTW-E01 Page |3
Permit To Work
YM-SAJCO JV
CTW 130 SADARA RAIL
PROJECT &
JUBAIL RAILWAY NETWORK
PROJECT

Permit to Work (PTW)

Supervising Consultant's Report:

Approved (Work may proceed)


Approved with Comments (Work may proceed to incorporation of comments and resubmit again this format)
Rejected (Revise and resubmit - Work cannot proceed)
Supervising Consultant Representative:
Name:_______________________Position:______________________Signature:_______________Date:___________

CTW130-QAC-TYP-PTW-E01 Page |4