Document #9C.1
Board of Library Trustees Meeting
July 26, 2017
Capital Projects Report
Project Milestones
Project Start Date May 2016
Library Close for Construction Winter 2017
Interim Library Open N/A
Interim Library Close N/A
New or Renovated Library Open Summer 2018
Active Contractor(s):
Broughton / R.McGhee & Associates
Project Description/Status
Significant interior renovation project that will upgrade mechanical, electrical and plumbing systems. Project will upgrade furniture, fixtures
and equipment. Construction is currently underway.
Summer 2017: Project expanded to include exterior landscaping and hardscaping (2.0M) and an interim library at Nalle Elementary School
(.7M). Opening deferred to Spring 2018 to allow completion of exterior work.
Project Milestones
Project Start Date March 2015
Library Close for Construction Fall 2016
Interim Library Open Fall 2016
Interim Library Close Spring 2018
New or Renovated Library Open Spring 2018
Active Contractors(s):
Gilbane/Perkins Eastman
Project Description/Status:
Demolition and construction of a new library on the same site. Full construction underway.
Project Milestones
Project Start Date 2018
Library Close for Construction TBD
Interim Library Open TBD
Interim Library Close TBD
New or Renovated Library Open TBD
Active Contractor(s):
TBD
Project Description/Status:
Project will be funded in FY18. RFP for site survey and related due diligence will be awarded in August 2017.
Project Milestones
Project Start Date August 2014
Library Close for Construction Spring 2017
Interim Library Open Spring 2017
Interim Library Close Spring 2020
New or Renovated Library Open Summer 2020
Active Contractor(s):
Martinez+Johnson/Mecanoo
Jair Lynch Development
Smoot / Gilbane
Project Description/Status:
Project Milestones
Project Start Date October 2015
Library Close for Construction March 2017
Interim Library Open N/A
Interim Library Close N/A
New or Renovated Library Open Fall 2017
Active Contractor(s):
Project Description/Status:
Major renovation project that will upgrade roofing, mechanical, electrical and plumbing systems. Project will upgrade furniture, fixtures and
equipment. Construction underway.
Page 6
Southeast Neighborhood Library Project Information
Ward 6
Address 403 7th Street SE
Councilmember Charles Allen
Branch Manager Maria Escher
Project Manager Lisa Deanes
Project Milestones
Project Start Date 2019
Library Close for Construction TBD
Interim Library Open TBD
Interim Library Close TBD
New or Renovated Library Open TBD
Active Contractor(s):
TBD
Project Description/Status:
Planned major renovation or new construction starting FY19. A due diligence study to analyze the addition of a new sublevel to the library
under 7th St to Eastern Market Metro Park has been completed.
Project Milestones
Project Start Date Summer 2017
Library Close for Construction Fall 2018
Interim Library Open Fall 2018
Interim Library Close Summer 2020
New or Renovated Library Open Summer 2020
Active Contractor(s):
Turner Construction / Perkins+Will
Project Description/Status:
Project is funded in FY2017 thru FY2019 for a new LEED certified branch library. Contract awarded to Turner Construction on June 24, 2017.
Design Underway.
Project Budget
Project Milestones
Project Start Date June 2013
Library Close for Construction June 2014
Interim Library Open June 2014
Interim Library Close Fall 2017
New or Renovated Library Open Fall 2017
Active Contractor(s):
Eastbanc / Clark Construction
Project Description/Status:
The West End Neighborhood Library will be rebuilt as part of a mixed use project being built by EastBanc real estate development company that
features a 21,000 square foot library on two levels, with eight stories of residential housing above. Project is under construction.