You are on page 1of 5

Version Control

Version Implemented Revision Approved Approval Reason


# By Date By Date

1.0 Muneeb Ul Haq 08/07/2017 Mr. Sher 08/07/2017 Initial Version


1) Project Description

Project Project Project Description Project Justification


# Name
1 DHA Mega Construction of a 4 storey This Project addresses commercial needs of the
Mall commercial building residents of DHA Islamabad, as well as it will
preserve the green areas and it will help DHA
organization in generate handsome revenue

2) Project Scope Statement


To address the commercial needs of residents of DHA Islamabad, a 4 storey commercial building is constructed in
DHA Islamabad, having all the allied facilities like parking basement, lift, and escalator and trolley ramp

2.1) Project In-scope


The following are considered In-scope for this project.

Construction of a 4 Storey commercial building located on an area of 10,000sqft


All the structural work containing RCC, will be the part of the project
All the Steel used in the Structure will be of Grade 60
The compressive strength of concrete should be 3000psi
All the concrete should be made in Batching plant
Procurement and fixing of tiles/ marbles on corridor area is the part of the project.
All the necessary Plumbing and Electrical Conduits embedded in RCC, should be done
Railing along the stairs is the part of the project.
Procurement and installation of washroom tiles and fitting are included in the project
The building should have a parking basement with a capacity of 500 vehicles and all the allied
facilities of lift, escalator and trolley ramps
Safety of Labor working at the site is contractors responsibility.
The contractor should get security clearance of all the labor and staff working on the site from
DHA security department.
The building should follow DHA by-laws
2.2) Project Deliverables
The following are the deliverables for this project.

Deliverable Description
ID#
1 Construction of 4 storey commercial building
1.1 Grey Structure
1.1.1 Basement
1.1.1.1 Raft
1.1.1.2 Columns of Basement
1.1.1.3 Retaining Walls of Basement
1.1.1.4 Basement Lift Well
1.1.1.5 Basement Slab
1.1.2 Ground Floor
1.1.2.1 Ground Floor Columns
1.1.2.2 Ground Floor Lift
1.1.2.3 Ground Floor Slab
1.1.3 1st Floor
1.1.3.1 1st Floor Columns
1.1.3.2 1st Floor Lift
1.1.3.3 1st Floor Slab
1.1.4 2nd Floor
1.1.4.1 2nd floor Columns
1.1.4.2 2nd Floor Lift
1.1.4.3 2nd Floor Slab
1.1.5 3rd Floor
1.1.5.1 3rd floor Columns
1.1.5.2 3rd Floor Lift
1.1.5.3 3rd Floor Slab
1.2 Finishing
1.2.1 Ground Floor Finishing
1.2.2 1st Floor Finishing
1.2.3 2nd Floor Finishing
1.2.4 3rd Floor Finishing

2.3) Project Out-scope

The following are considered Out-scope for this project.

Getting services (water, electric, plumbing) is not a part of the scope, as it is a clients
responsibility
Work permits required for execution of work is clients responsibility
Interior of shops are not the part of our scope
Marketing of building for shops, food court and cash and carry is not the part of our scope.
HAVC is not the part of the scope.
Electrical and Mechanical connections and fittings are not the part of the project.
Internal paint and External cladding wont the be part of the projects scope
Firefighting fittings procurement and Installation wont be in the scope of the project

2.4) Project Assumptions


The following assumptions apply to the DHA Mega Mall Project. As project planning begins and more
assumptions are identified, they will be added accordingly.

Payments will be made, without any subsequent delays.


DHA organizational body will provide alternative route for material dumping and storage.
DHA will provide security.
Project has executive-level support and backing.
All department heads will provide necessary support for successful project completion.
The weather will remain pleasant throughout the excavation period
No health and safety mishap will take place at site

2.5) Project Constraints


The following constraints apply to the DHA Mega Mall Project. As project planning begins and more
constraints are identified, they will be added accordingly.

Time is the biggest constraint in this project and a time period of 9 months is given for this
project.
The budget for construction of DHA Mega Mall is 200 Million PKR.
As the site is located in DHA Islamabad, the traffic police of Islamabad dont allow the HTVs from 6am to
12am. Hence the transportation of all the material including Sand, Crush, Cement and Steel should be
done during 12am to 6am at night.
As Rawalpindi and Islamabad is having a military set up, so security clearance of all the labor coming to
construction site should be done.

2.6) Project Deliverable Acceptance Criteria

Deliverable Acceptance Method of Testing


Deliverable
ID # Criteria
Construction of 4 Storey commercial
1
building
1.1 Grey Structure
1.1.1 Basement
Concrete 3000psi, 28days cylindrical test,
1.1.1.1 Raft
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.1.2 Columns of Basement
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.1.3 Retaining Walls of Basement
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.1.4 Basement Lift Well
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.1.5 Basement Slab
Steel G-60 Yielding test of Steel
1.1.2 Ground Floor
Concrete 3000psi, 28days cylindrical test,
1.1.2.1 Ground Floor Columns
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.2.2 Ground Floor Lift
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.2.3 Ground Floor Slab
Steel G-60 Yielding test of Steel
1.1.3 1st Floor
Concrete 3000psi, 28days cylindrical test,
1.1.3.1 1st Floor Columns
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.3.2 1st Floor Lift
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.3.3 1st Floor Slab
Steel G-60 Yielding test of Steel
1.1.4 2nd Floor
Concrete 3000psi, 28days cylindrical test,
1.1.4.1 2nd floor Columns
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.4.2 2nd Floor Lift
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.4.3 2nd Floor Slab
Steel G-60 Yielding test of Steel
1.1.5 3rd Floor
Concrete 3000psi, 28days cylindrical test,
1.1.5.1 3rd floor Columns
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.5.2 3rd Floor Lift
Steel G-60 Yielding test of Steel
Concrete 3000psi, 28days cylindrical test,
1.1.5.3 3rd Floor Slab
Steel G-60 Yielding test of Steel
1.2 Finishing
As per Architectural Physical Inspection
1.2.1 Ground Floor Finishing
Drawing
As per Architectural Physical Inspection
1.2.2 1st Floor Finishing
Drawing
As per Architectural Physical Inspection
1.2.3 2nd Floor Finishing
Drawing
As per Architectural Physical Inspection
1.2.4 3rd Floor Finishing
Drawing

2.7) Project Scheduled Time


Estimated days required
270 days
to complete project

2.8) Project Cost


Estimated cost required
200Million PKR
to complete project

2.9) Project Approvals


Role of Approver Submitted for Approval on: Approval Received on:
1. CEO (M/s TAAMEER 10th July 2017 21th July 2017
Associates)
2. DHA Administrator 12th July 2017 27th July 2017

Attach any additional documentation.

Office Use Only: