Ref: SB016/BLDK3/02/UMB/PC06/SR01 Date of Inspection: 20 June 2017

Contract Title: Construction ad Completion of 2 Blocks of L3 Staff Quarters at Kabang Estate 3,


Sibu.
Contractor : United Metal Builder Company

All the defects have been cleared. Tilted water tank supports were re-levelled and the damaged
wooden base repaired and changed to concrete pad footing. During the joint inspection, estate
representatives are satisfactory with the defects work repaired. Other than that, there is no issues
with the structure.

Site Photos

Figure (a): Front View

Prepared By,

__________________________________________
(William Ting)
PROJECT ENGINEER, KTSR PD3, SIBU
Ref: SB016/BLDK3/02/UMB/PC06/SR01 Date of Inspection: 20 June 2017

Figure (b): Front View

Figure (c): Rectified Concrete Pad Footing

Prepared By,

__________________________________________
(William Ting)
PROJECT ENGINEER, KTSR PD3, SIBU
Ref: SB016/BLDK3/02/UMB/PC06/SR01 Date of Inspection: 20 June 2017

Figure (d): Rectified Concrete Pad Footing

Figure (e): Rectified Concrete Pad Footing

Prepared By,

__________________________________________
(William Ting)
PROJECT ENGINEER, KTSR PD3, SIBU
Ref: SB016/BLDK3/02/UMB/PC06/SR01 Date of Inspection: 20 June 2017

Figure (f): Living Room View

Prepared By,

__________________________________________
(William Ting)
PROJECT ENGINEER, KTSR PD3, SIBU
Ref: SB016/BLDK3/02/UMB/PC06/SR01 Date of Inspection: 20 June 2017

Figure (g): Kitchen View

Figure (h): Bathroom


Prepared By,

__________________________________________
(William Ting)
PROJECT ENGINEER, KTSR PD3, SIBU