BSH Qualification Process for Purchased Parts

CQP + ISIR

PRF/DE-ISQ

30.10.2014
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 1
BSH Qualification Process for Purchased Parts

Initial Situation and Objective

Target
All BSH suppliers
Group

Impact of quality of purchased parts on the product quality of


Initial BSH appliances.
Situation
Importance of collaboration between BSH and its supplier.

Leading process to ensure the necessary quality of delivered


parts.
Regulates the activities during the release phase.
Objectives
Communicates BSH requirements to the supplier.
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 2
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP: Q-Measure Page P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 3
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 4
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 5
Release
CQP
Process

1.1. CQP: Q-Measure Page

CQP: Component Qualification Planning

is Q-Measure Page in the Placement Protocol.

Provide a specific overview of BSH requirements.

Filled out by QMS.

Will be handed over to the supplier, when the


order is placed.
Early involvement of the supplier in the BSH
product development process.
Define due date for the release documents.

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 6
Release
CQP
Process

1.1. CQP: Q-Measure Page

1 Part Classification
1

carried out by the QMS according to the


anticipated part criticality.
defines the scope of required release documents.

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 7
Release
CQP
Process

1.1. CQP: Q-Measure Page


A Complex parts, difficult to manufacture, hardly manageable production processes.

B Individual classification by QM.

C Product to be manufactured easily, respectively, simple change.


A B C
X Requirements according part classification.

E Only for review on request.

X
1 Part Classification

E
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 8
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 9
Release
CQP
Process

1.2. Necessary Documents


Signed Quality Management Agreement (QMA)
Supplier declaration on prohibited or declarable substances
ISIR - Initial Sample Inspection Report
Signed Quality Specification
Alignment of documents
Process assessment (Audit) at the supplier 1
Proof of fulfillment of quality specific packaging
Necessary 2
Approval evidence for purchased parts from subsuppliers documents and
BSH Due date
Test coverage (e.g. for electronic components/modules)
requirements for
Test instruction BSH part
Advanced quality planning (Q-plan / APQP) approval

Feasibility study
Control plan
Process flow chart
P-FMEA
General Measurement System
PPM Values
Finish of required tests, inspections
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 10
Release
CQP
Process

Signed Quality Management Agreement (QMA)

ensures the agreed quality of purchased parts


and continuous improvement.
The general BSH quality assurance
requirements are described.

Signed QMA
Electronic version of this document:
http://orgdoku.bshg.com/pages/viewpage.action?pageId=4293276
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 11
Release
CQP
Process

Supplier Declaration on Prohibited or Declarable Substances

All related sections must be


filled in by supplier, signed and
shipment to BSH.

Email-address erkezky: CKY-Release-Refrigerator-Factory-Turkey@bshg.com;


Giengen: gin-declarations@bshg.com;
Electronic version of this document: http://www.bsh-group.com/index.php?page=1144
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 12
Release
CQP
Process

ISIR: Initial Sample Inspection Report


MPB Cover Sheet MPP Page 1 MPP Page 2

Material Report Process capability Componet List

All related sections must be


filled in by supplier and
samples must be sent to BSH
with ISIR.

Electronic version of this document:


http://www.bsh-
group.com/index.php?page=1144
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 13
Release
CQP
Process

Signed Quality Specification

Q-specification clarifies the required


technical and organizational general
condition for delivery of parts.

Signed Q-Specifications Electronic version of this document:


http://emea-
moss.bshg.com/sites/ztq/Public_ZTQ/Shared%20Docum
ents/Q-Lastenheft.pdf
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 14
Release
CQP
Process

Alignment of Documents, e.g. Specification, Drawings


If necessary,
Specification Info 3

If necessary,
4 Miscellaneous info

Part number acc.to


BSH sites / Detail info 1
MUST

Revision Level Part


Info 2
MUST

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 15
Release
CQP
Process

Process Assessment (Audit) at the Supplier

If required, process audit is done


under series production conditions
to evaluate production process of
purchased parts.

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 16
Release
CQP
Process

Other Necessary Documents

Proof of fulfillment of quality specific packaging

Approval evidence for purchased parts from subsuppliers

Test coverage (e.g. for electronic components/modules)

Test instruction
1
Advanced quality planning (Q-plan / APQP)
Necessary 2
Feasibility study documents and
BSH Due date
Control plan requirements for
BSH part
Process flow chart approval

P-FMEA

General Measurement System

PPM Values

Finish of required tests, inspections

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 17
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P56

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 18
Sample Release Process

PRF/DE-ISQ

30.10.2014
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 19
Release
CQP
Process

Release Process

Objectives and indicators

To assure a high quality standard for parts, components and materials.

To ensure that parts, components and materials, used within PRF, are
Objectives conform to specification.

To make all test results for parts, components and materials, as well
as a common database for all release documentation, available.

The indicator is the release status


Not released
Indicators
Limited released
Released
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 20
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 21
Release
CQP
Process

2.1. Before the Release Process


DE
Creation and classification of new
part (DE+QM)
PU
Collecting of requests and decision- QM
making of placement meeting (PU)
Creation of purchase request
Implementation of placement (DE)
meeting (PU+DE+QM+SUP)

Creation of delivery plan Order creation (PU)


(PU)
Creation of BE&FR (DE)

Receiving of sample part

Implementation of sample
process(QM)

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 22
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation Phase (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 23
Release
CQP
Process

2.2. Part Evaluation Phase (BE / FR)


Every part without any exceptions should have Basic Evaluation and Factory Release to use in
production.

IMPORTANT:
The BE Letter is just as
information of the result of
the Basic Evaluation and
is NOT equivalent to a
release for serial delivery.

The release for delivery is


given by the Production
site through the Factory
Release.

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 24
Release
CQP
Process

2.2. Part Evaluation Phase (BE / FR)


BE Release Delivery Permission

BE FR Permission
Release Release for Delivery

Evaluation of technical Evaluation of factory-specific


requirements requirements such as
acc. drawing, handling, ability for assembly,
BOM, test specification, ... packaging, ...
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 25
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 26
Release
CQP
Process

2.3. Release Process


Not release > Release process begins again / (ReSampling).
1 Notification of Not release decision to the supplier (Quality).
2 Creation of purchase request and purchase order (DE and PU).
3 Creation of RP revision (PU/DE).
4 New samples are sent to the related Quality department (Supplier).
5 Measuring process begins again (Quality).
Remark: Process followed by purchasing department.

Limited release > Part is using but for improvement actions sample process begins again / (ReSampling).
. 1 Notification of Limited release decision to the supplier (Quality).
2 Creation of purchase request and purchase order (DE and PU).
3 Creation of RP revision (PU/DE).
4 New samples are sent to the related Quality department (Supplier).
5 Measuring process begins again (Quality).
Remark: Process followed by purchasing department.

Release > Part delivery can begin.


BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 27
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 28
Release
CQP
Process

2.4. When is a Release Necessary?

BE FR

New part in PRF (1) X X

Modification of existing part in FRFy (new drawing or specification revision) (X) X

Existing part to a new FRFy (e.g. part already supplied to FRFG will be purchased to FRFI) X
Existing part from new supplier part specification and drawings already exist but the part is
purchased from new supplier
X X
Existing part from existing supplier, with quality relevant changes to the process (e.g. new
production facility, new equipment/technology, new sub-supplier, etc..) (2)
X X

(1) The release process follows the Placement Meeting


(2) B/S/H/ requires to be informed by the Supplier in case of any changes.
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 29
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 30
Release
CQP
Process

2.5. Basic Evaluation: ISIR Documentation


Required documents:
1 Sample Inspection Report cover sheet
2 Sample Inspection Report dimensional report (MPP)
3 Component list
4 Material report
5 Process capability
6 Additional documents

The documents must be filled in properly and have to be sent in Excel format to the following email address:
Email-address erkezky: CKY-Release-Refrigerator-Factory-Turkey@bshg.com;
Email-address Giengen: gin-bemusterung@bshg.com;
.
Additionally, the signed documents and the technical drawing marked by number have to be sent per Email.

The Supplier is requested to use B/S/H/ templates.

Electronic version of the ISIR documents:

English language: http://www.bsh-group.com Purchasing Forms Quality


BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 31
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 32
Release
CQP
Process

2.6. First Sample Shipment


Identification:

1 Each sample has to be sent with First Sample Delivery Label.

2 In the Forwarding to field has to be written related QMS department e.g.FRFI1/QMS

3 First sample delivery label can be downloaded from B/S/H/ website.


http://www.bsh-group.com Purchasing Forms Product Group Refrigerator

Shipment conditions:

1 Initial samples should not be delivered together with regular shipments.

2 Initial samples must be shipped in a separate box or container with its own delivery shipping
ticket, to the address specified on the order.
3 The parts must be sufficiently protected against damage and environmental factors or sent in
the packaging which is defined at the placement meeting for the serial production.

If the measurements or tests at the Supplier uncover any deviations from the specifications,
such deviations must be amended before the shipment of the initial sample.

In exceptional cases, the supplier has to contact related B/S/H/ department.


BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 33
Release
CQP
Process

Remark: Label for Pre-Pilot-Series Material

Electronic version:
http://www.bsh-group.com
Purchasing Forms
Product Group Refrigerator

On the delivery note it has to be written that delivery is either first sample delivery or material for PPS
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 34
Release
CQP
Process

Content

1. CQP: Component Qualification Planning P.4

1.1. CQP (Q-Measure Page) P.5

1.2. Necessary Documents P.9

2. Sample Release Process P.18

2.1. Before the Release Process P.21

2.2. Part Evaluation-Release Process Phases (BE + FR) P.23

2.3. Release Process P.26

2.4. When is a Release Necessary? P.28

2.5. Basic Evaluation: ISIR Documentation P.30

2.6. First Sample Shipment P.32

2.7. Completion of the ISIR Documents P.35

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 35
Release
CQP
Process

2.7. Completion of the ISIR Documents


i. Sample Inspection Report cover sheet 1

2
Tick one option 1
3
Supplier
Information

2
4
Select a BSH plant in the
3 drop down menu

4
Reason for submisson: tick one option

Fill out by supplier


BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 36
Release
CQP
Process

2.7. Completion of the ISIR Documents


i. Sample Inspection Report cover sheet

Part information
2
1 customer submittal
information

Documents delivered
2 with Samples

Fill out by supplier


BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 37
Release
CQP
Process

2.7. Completion of the ISIR Documents


i. Sample Inspection Report cover sheet

Drawing, supplier and


1
delivery information
2
Tools
information
and
supplier
remark

Department information
3 and signature 1
2

3
Fill out by supplier
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 38
Release
CQP
Process

2.7. Completion of the ISIR Documents


ii. Sample Inspection Report -
dimensional report (MPP)

All the dimensions defined in the drawing


Like cover sheet
have to be measured. Remark: some information appears from cover sheet
automatically
For each cavity 5 parts have to be
measured and the min/max values have to
be reported (no average). The measured Cavity number and part weight

parts have to be submitted to B/S/H/.


.
The parts must be clearly marked in order
to create a link between the measured Remark:
values and the parts. Dimensions
Min/max for instance
(nominal Remark Meas. number of
In case of mould with more cavities >> values & measured
tolerances) values
the dimensional report has to be provided parts
for each cavity.

In case of assembly group >>


the dimensional report has to be provided
for the single parts.
Fill out by supplier
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 39
Release
CQP
Process

2.7. Completion of the ISIR Documents


ii. Sample Inspection Report -
dimensional report (MPP) Cavity Part
number weight

Nominal Min. value


values measured Number of
Measurement meaured parts
Upper characteristics
tolerance and measuring
device Max. value
measured
Lower
tolerance

Before lower tolerance (-) has to be put


BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 40
Release
CQP
Process

2.7. Completion of the ISIR Documents


iii. Component list
It has to be filled out only in case of assembly group

Like cover sheet


Remark: some information appears from cover sheet automatically

All fields must be filled out.

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 41
Release
CQP
Process

2.7. Completion of the ISIR Documents


iv. Material report

It must be accord with BOM. All fields must be filled out.


In case of assembly groups, the material for the single parts must be listed.

Additional declaration list of hazardous substances must be sent to the following e-mail address:
Email-address erkezky: CKY-Release-Refrigerator-Factory-Turkey@bshg.com;
Giengen: gin-declarations@bshg.com;

English language: http://www.bsh-group.com Purchasing Forms Environment

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 42
2.7. Completion of the ISIR Documents
v. Capability study

Capability study has to be made for:

1 control characteristics indicated in the drawing and

2 characteristics which are defined at the placement meeting.

Capability study has to be performed separately for each cavity.

Required values:

1 Cmk 1,67
based on the measurement of minimum 50 parts, produced continuously with one setup
2 Cpk 1,33

BSH spreadsheet:
http://www.bsh-group.com Purchasing Forms Quality

Own spreadsheet for capability calculation can be used.

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 43
2.7. Completion of the ISIR Documents
vi. Additional documents (required with ISIR)

1 Process Flow chart,

2 Control Plan (in English),

3 P-FMEA,

4 Measurement system evaluation study (e.g. Gage R&R),

5 working instructions (in English), etc..

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 44
Classification of dimensions

Symbol Definition Requirements Note


Cmk for the initial samples - to be It gives an indication about
125 0.2 SPC SPC dimension monitored during serial production the stability of the process
by SPC tools (Cpk, control charts..)

125 0.2 Critical dimension To be statistically monitored during It has a direct impact on the
serial production (e.g. gauges..) functionality of the part
125 0.2 Functional dimension To be measured for the initial
sampling
To be measured for initial sampling -
1.5
to be monitored during serial
Geometric dimensions production
1.5 To be measured for initial sampling

Surface symbol The parts must be conforming to the B/S/H does not require a
(e.g. roughness) specified characteristics for release measured value

BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 45
Communication
Please share
this presentation

BSH-Expectations of you at Sample Process

http://www.bsh-group.com/index.php?page=1144 and

Your knowledge and impression gained at this trainig

with everbody who is responsible for sample process at your company.

Thank You
BOSCH UND SIEMENS HAUSGERTE GRUPPE CQP and ISIR Training I 30 Ekim 2014 I Folie: 46