CONSORCIO NIPPON KOEI CO.

LTD- CESEL
S.A. - OIST S.A

CONTRATO : CONTRATO DE OBRA N 14-2010-CW-32930 / JICA - SEDAPAL

OBRA : MEJORAMIENTO SANITARIO DE LAS AREAS MARGINALES DE LIMA LOTE 6 - ORAS

PROPIETARIO : SEDAPAL

CONTRATISTA : GALVAO ENGENHARIA S.A. SUCURSAL PERU

SUPERVISION : CONSORCIO NIPPON KOEI CO., LTD.- CESEL S.A. - OIST S.A.

SUSTENTO DE M
CONCRETO f"c=100 kg
I
Fecha de ejecucion: -- de Marzo del 2011
Frente de trabajo: Camara CR-118
Zona de abastecimiento: Mariscal Caceres
Responsable: E. Elias Verstegui Minaya
Elaborado: Ray Martinez Torres

1.- TIPO

CONCRETO PARA SOLADO

2.- SUSTENTO GRAFICO


I

ESTRUCTURA CCP-01 N Area (m2)


Solado
Cimientos 1
1
1
1
1
1
Z1 2
Z5 2
Z2 2
Z3 2
Z4 2
TOTAL DE CONCRETO f"c=100 PA
NALES DE LIMA LOTE 6 - ORAS COMPLEMENTARIAS A LOS LOTES 1,2 Y 3

USTENTO DE METRADOS DE
ETO f"c=100 kg/cm2 PARA SOLADO

NCRETO PARA SOLADO DE CIMENTACION


L (m) a (m) h (m) Total (m3)

1.36 1.00 1.15 1.57


1.36 1.00 1.62 2.21
0.46 0.90 1.15 0.48
0.46 0.90 1.62 0.67
4.95 1.00 1.15 5.69
7.35 0.60 1.15 5.07
1.40 1.40 1.62 6.35
1.40 1.40 1.15 4.51
1.60 1.60 1.62 8.29
3.20 1.60 1.15 11.78
3.20 1.60 1.62 16.59
CONCRETO f"c=100 PARA SOLADO 63.21
DE
SOLADO
PLANILLA DE METRADOS DE
ESCALERA DE ACCESO Y CERCO RE-02

COD. DESCRIPCION N Area (m) L (m) a (m) h (m) PARCIAL Und. TOTAL

1.00 CONSTRUCCION DE ESCALERA DE ACCESO A RE-02

MOVIMIENTO DE TIERRAS

EXCAVACION CORTE EN TERRENO ROCOSO SIN EMPLEO DE EXPLOSIVOS m3 40.52

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 20.26 2.00 40.52

REFINE, NIVELACION Y COMPACTACION EN TERRENO ROCOSO m2 122.36

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 60.88 1.00 60.88
1.00 10.19 1.00 10.19
1.00 10.61 1.00 10.61
1.00 14.01 1.00 14.01
1.00 15.53 1.00 15.53
1.00 6.12 1.00 6.12
1.00 5.02 1.00 5.02

ELIMINACION DE DESMONTE EN TERRENO ROCOSO R=10 km CON MAQUINARIA m3 60.78

N VOL ESP PARCIAL


1.00 40.52 1.50 60.78

OBRAS DE CONCRETO

CONCRETO f'c=175 kg/cm2 PARA GRADA Y/O PISO SIMPLE m3 27.81

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 27.81 1.00 27.81

ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 55.62

N Area (m) L (m) a (m) h (m) PARCIAL


2.00 27.81 55.62
ACABADOS

FROTACHADO DE PASOS Y CONTRAPASOS m2 117.34

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 60.88 1.00 60.88
1.00 10.19 1.00 10.19
1.00 10.61 1.00 10.61
1.00 14.01 1.00 14.01
1.00 15.53 1.00 15.53
1.00 6.12 1.00 6.12

ADIMENTOS VARIOS

BARANDA DE MADERA CEDRO PUCALLPA m 234.68


N Area (m) L (m) a (m) h (m) PARCIAL
2.00 60.88 1.00 121.76
2.00 10.19 1.00 20.38
2.00 10.61 1.00 21.22
2.00 14.01 1.00 28.02
2.00 15.53 1.00 31.06
2.00 6.12 1.00 12.24

CERCO PERIMETRICO TIPO MURO CONFINADO PARA RP-02

MOVIMIENTO DE TIERRAS

EXCAVACION DE ZANJA EN ROCA PARA CIMENTACION(INC. REF. Y LIMPIEZA) m3 134.32

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 83.95 1.60 134.32

REFINE, NIVELACION Y COMPACTACION EN TERRENO ROCOSO m2 49.76

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 82.94 0.60 49.76

ELIMINACION DE DESMONTE EN TERRENO ROCOSO R=10 km CON MAQUINARIA m3 201.48

N VOL ESP PARCIAL


1.00 134.32 1.50 201.48

OBRAS DE CONCRETO

CONCRETO f'c=210 kg/cm2 PARA ZAPATAS CORRIDAS m3 39.81

23/8"
0.25 0.15
VS (.15 x .20)

0.20
0.05 0.20 V S (.15 x .20)

RESTO 4@.10
1/4" 4@.10
@.20 0.05

RESTO
1/4"
@.20
0.50 0.50 3.00
VARIABLE
(3.00-3.60) m.
VARIABLE
2 ALAMBRES N8 CADA 3 HILADAS
(3.00-3.50) m.

3/8"@.30
CENTRADO

11@.10
NT+ ( 0.90)m.
( 0.90)m. SOBRECIMIENTO

0.40

CIMIENTO
1.00
0.80
0.80
0.10
0.20

0.60

DISTRIBUCION DE ACERO
EN COLUMNAS
E SCALA=1/25 SECCION 1-1
E SCALA= 1/25
CIMIENTO
1.00
0.80
0.80
0.10
0.20

0.60

DISTRIBUCION DE ACERO
EN COLUMNAS
E SCALA=1/25 SECCION 1-1
E SCALA= 1/25

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 82.94 0.60 0.80 39.81

ACERO DE REFUERZO fy=4,200 kg/cm2 - CIMIENTO CORRIDO kg 954.93

VECES N @ L varilla kg/m PARCIAL


1.00 276.47 1.75 3/8 0.56 484.38
1.00 5.67 82.94 3/8 0.56 470.55

ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2 149.29

N Area (m) L (m) a (m) h (m) PARCIAL


2.00 82.94 0.90 149.29

CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3 22.39

N Area (m) L (m) a (m) h (m) PARCIAL


2.00 82.94 0.15 0.90 22.39

ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 32.40

N Area (m) L (m) a (m) h (m) PARCIAL


36.00 0.25 3.60 32.40

CONCRETO PARA COLUMNAS m3 8.10

N Area (m) L (m) a (m) h (m) PARCIAL


36.00 0.25 0.25 3.60 8.10

ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 1,253.45

VECES N @ L varilla kg/m PARCIAL


36.00 4.00 4.55 1/2 0.99 648.65

VECES N @ L varilla kg/m PARCIAL


36.00 30.00 1.00 3/8 0.56 604.80

CONCRETO f'c=210 kg/cm2 PARA VIGAS Y DINTELES m3 2.49

0.15

0.20 VS (.15 x .20)

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 82.94 0.15 0.20 2.49

ENCOFRADO Y DESENCOFRADO PARA VIGAS RECTAS Y DINTELES m2 33.18

N Area (m) L (m) a (m) h (m) PARCIAL


2.00
3.00 82.94 0.20 33.18

VARIABLE
ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 476.73
VECES N @ L varilla kg/m PARCIAL
1.00 4.00 82.98 3/8 0.56 185.88

VECES N @ L varilla kg/m PARCIAL


1.00 414.70 0.70 3/8 0.56 290.85

ALBAILERIA

MUROS DE LADRILLO KK DE ARCILLA DE CABEZA CON MEZCLA 1:4 X 1.5 cm m2 207.35

N Area (m) L (m) a (m) h (m) PARCIAL


1.00 82.94 2.50 207.35

VARIOS

JUNTA ANTISISMICA 3 cm m 61.20

N Area (m) L (m) a (m) h (m) PARCIAL


17.00 3.60 61.20

PINTURA IMPERM. BITUMASTICA m2 248.82

N Area (m) L (m) a (m) h (m) PARCIAL


2.00 82.94 1.50 248.82

PUERTA METALICA unid: 1.00


PLANILLA DE METRADOS DE
ESCALERA DE ACCESO Y CERCO RP-02

COD. DESCRIPCION N Area ( L (m) a (m) h (m) PARCIAL Und. TOTAL

1.00 CONSTRUCCION DE ESCALERA DE ACCESO A RP-02 m3 10,000.00


MOVIMIENTO DE TIERRAS
EXCAVACION CORTE EN TERRENO ROCOSO SIN EMPLEO DE m3 10.00 10.00 10.00 10.00 10,000.00
REFINE, NIVELACION Y COMPACTACION EN TERRENO ROCOS m2
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R=10 k m3
OBRAS DE CONCRETO
CONCRETO f'c=175 kg/cm2 PARA GRADA Y/O PISO SIMPLE m3
ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2
REVOQUES
TARRAJEO EXTERIOR CON MORTERO 1:5 X 1.5 cm (INCLU m2
REVESTIMIENTO DE CONCRETO R=37 m/da m
ADIMENTOS VARIOS
BARANDA DE MADERA CEDRO PUCALLPA m
CERCO PERIMETRICO TIPO MURO CONFINADO PARA RP-02
MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJA EN ROCA PARA CIMENTACION(INC. REFm3
REFINE, NIVELACION Y COMPACTACION EN TERRENO ROCOS m2
ELIMINACION DE DESMONTE EN TERRENO ROCOSO R=10 k m3
OBRAS DE CONCRETO
CONCRETO f'c=210 kg/cm2 PARA ZAPATAS CORRIDAS m3
ACERO DE REFUERZO fy=4,200 kg/cm2 - CIMIENTO CORRIDO kg
ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2
CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS m3
ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2
ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg
CONCRETO f'c=210 kg/cm2 PARA VIGAS Y DINTELES m3
ENCOFRADO Y DESENCOFRADO PARA VIGAS RECTAS Y DINT m2
ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg
ALBAILERIA
MUROS DE LADRILLO KK DE ARCILLA DE CABEZA CON MEZCLAm2