Professional Documents
Culture Documents
Copyright 2009 NCSEA. ALL RIGHTS RESERVED. Accessed by Kevin Kirkland on May 28, 2016 11:35:44 AM pursuant to License Agreement with NCSEA. No further
reproduction or distribution authorized. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE
LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
ISBN: 978-1-58001-790-9
Copyright 2009 by
NCSEA
Published by
ICC
Cover photos taken by Caroline Tsang and provided courtesy of Dublin Unified School District, Dublin,
California.
ALL RIGHTS RESERVED. This publication is a copyrighted work owned by the National Council of Structural Engineers
Association (NCSEA). Without advance written permission from the copyright owner, no part of this book may be
reproduced, distributed or transmitted in any form or by any means, including, without limitation, electronic, optical or
mechanical means (by way of example, and not limitation, photocopying or recording by or in an information storage
retrieval system). For information on permission to copy material exceeding fair use, please contact: ICC Publications,
4051 West Flossmoor Road, Country Club Hills, IL 60478. Phone 1-888-ICC-SAFE (422-7233).
The information contained in this document is believed to be accurate; however, it is being provided for informational
purposes only and is intended for use only as a guide. Publication of this document by the ICC should not be construed as
the ICC or NCSEA engaging in or rendering engineering, legal or other professional services. Use of the information
contained in this book should not be considered by the user to be a substitute for the advice of a registered professional
engineer, attorney or other professional. If such advice is required, it should be sought through the services of a registered
professional engineer, licensed attorney or other professional.
First Printing: March 2009
Second Printing: August 2009
PRINTED IN THE U.S.A.
Copyright 2009 NCSEA. ALL RIGHTS RESERVED. Accessed by Kevin Kirkland on May 28, 2016 11:35:44 AM pursuant to License Agreement with NCSEA. No further
reproduction or distribution authorized. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE
LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
iii
Preface
The discussion and examples in this guide are based on the structural
provisions of the 2006 International Building Code (IBC) and the
American Society of Civil Engineers Minimum Design Loads for
Buildings and Other Structures (ASCE/SEI 7-05) standard. Although
the 2009 IBC references the 2008 edition of the ACI 318 standard, there
are only minor changes from ACI 318-05 in regards to the design of
concrete diaphragms, chords and collectors. Because the 2009 IBC ref-
erences ASCE/SEI 7-05, the design examples in this publication are
applicable to the 2009 IBC as well.
Acknowledgments
The authors recognize and thank the above individuals sincerely for their
immense contribution, which has resulted in the publication of this
guide.
The authors are also highly thankful to the following individuals for re-
viewing the design examples presented in this guide. Their useful
suggestions have resulted in enhancing the clarity of this guide.
NCSEA has made every reasonable effort to ensure that the information
presented in this document is accurate. In the event that corrections or
clarifications are needed, these will be posted on the NCSEA web site
(www.ncsea.com). NCSEA, at its sole discretion, may choose to publish
written errata.
Table of Contents
Preface iii
Acknowledgments v
Comments and Suggestions vii
Introduction to Diaphragms 1
Design Example 1: Concrete Diaphragm DesignFour-Story
Building 11
1. Determination of Diaphragm Demands for Seismic Design
Category B. 19
2. Design of Diaphragm without Opening for Seismic Design
Category B. 37
3. Design of Diaphragm with Opening for Seismic Design
Category B. 39
4. Collector Design for Seismic Design Category B. 40
5. Brief Discussion of Seismic Design Categories C through F. 43
6. Determination of Diaphragm Demands for Seismic Design
Category D. 44
7. Design of Diaphragm without Opening for Seismic Design
Category D. 56
8. Design of Diaphragm with Opening for Seismic Design
Category D. 57
9. Collector Design for Seismic Design Category D. 58
10. Design of Slab as Collector Element for Seismic Design
Category D (Alternate Approach for Collector Design). 63
Design Example 2: Wood Diaphragm (Flexible Diaphragm) for Seismic
Design Category B, C & DThree-Story Building 77
1. Determination of Diaphragm Demands for Seismic
Design Category B. 80
2. Diaphragm Design without Opening for Seismic
Design Category B. 86
3. Diaphragm Design with Opening for Seismic Design
Category B. 93
4. Collector Design for Seismic Design Category B. 113
5. Brief Discussion on Seismic Design Category C, D, E and F. 128
6. Determination of Diaphragm Demands for Seismic Design
Category D. 129
7. Diaphragm Design for Seismic Design Category D. 132
Introduction to Diaphragms
The diaphragm provides the structure with global stability against collapse
due to applied lateral loads from sources such as earthquakes or wind.
Diaphragms
Typical Vertical Elements
(Gravity Load Only System)
Those vertical elements that are not part of the lateral-load-resisting system,
the gravity load only vertical elements, are laterally supported at each
elevation point within the structure where they are attached to a diaphragm
(see Figures I and II). The gravity load only vertical elements are
typically columns, but can include walls that are not part of the LLRS. All
gravity and LLRS vertical elements will buckle sideways when a large
enough axial load is applied. Vertical elements that extend the structures
entire height uninterrupted are considered as being continuous through all
diaphragm levels of the structure. The continuous vertical members
unbraced buckling length is reduced from being the full height of the
structure to the distance between diaphragm attachment points when there
are multiple diaphragm levels between the base and top of the structure.
The reduced buckling length thereby increases the continuous vertical
elements ability to support larger applied axial loads.
Figure II. Floor diaphragm bracing a continuous vertical element from buckling
Diaphragm Stiffness
As shown in Figure III, the deflection of the diaphragm between the sup-
ports due to lateral loads results in the generation of shear forces (parallel to
the x-axis) within the plane of the diaphragm. This is often best visualized
thinking of a single span, simply supported, wood, glu-lam beam deflecting
under an applied load, and the individual laminations of the member trying
to slide back and forth (horizontal sliding shear), but resisted by the glue
interface between the laminations.
One edge of the diaphragm is now stretching due to tension forces while the
other edge is attempting to shorten due to compression forces. The applied
in-plane forces are transferred by means of shear to the diaphragm end sup-
ports (shear parallel to the transverse y-axis). If the diaphragm is made up
of many individual elements (multiple sheets of plywood, for example),
then there are more joint locations for sliding shear to occur between the
diaphragm elements. Since there are in-plane compression forces, there can
be potentially out-of-plane buckling of the diaphragm element.
Diaphragm Construction
Behavior of Diaphragms
such as concrete shear walls, then the behavior of the diaphragm ap-
proaches that of a flexible element.
Section 12.12.2 of ASCE/SEI 7-05 addresses the fact that the deflection of
the diaphragm should not exceed the allowable deflection of the elements
attached to the diaphragm. Another aspect to keep in mind is that the de-
flection of the diaphragm has a direct impact on the out-of-plane deflection
capacity of the walls that are perpendicular to the direction being analyzed.
For wood diaphragms, Section 12.11.2.2.3 requires that the continuous ties
should be in addition to diaphragm sheathing. As explained in the 2000
NEHRP Commentary (FEMA 369), during the San Fernando earthquake,
separation of the walls from the roof diaphragm in many industrial build-
ings was due to inadequate anchorage development of the ties into the
diaphragm. Connection of the crosstie to resist out-of-plane wall anchorage
forces should be detailed such that cross-grain bending and cross-grain
tension in wood members is avoided. Subdiaphragms are allowed in
accordance with Section 12.11.2.2.1 with the limitation that maximum
length to width ratio should be not greater than 2.5 to 1.
Section 1602 of the 2006 IBC defines a diaphragm chord as, a dia-
phragm boundary element perpendicular to the applied load that is assumed
to take axial stresses due to the diaphragm moment.
Along the flexural edges of the diaphragm, the floor/roof framing members
serve as the chord elements of the diaphragm, resisting the flexure-induced
compression and tension forces that can tear a diaphragm apart if the
deflections are too extreme (exceed the diaphragm element tensile capacity
resulting in tensile fracture starting at the edge of the diaphragm and mi-
grating inward).
Note that the definition of diaphragm chord states that the chord is a
boundary element. The terms boundary element and boundary
member are defined in Section 11.2 of ASCE/SEI 7-05 as follows:
Introduction to Collectors
Collector elements (also called drag struts or drag elements) a) collect and
transfer diaphragm shear forces to the vertical lateral-force-resisting ele-
ments or b) distribute forces within a diaphragm. They include the
connections between the floor or roof diaphragms and lateral-force-resisting
elements. For SDC C through F, it is required that the collector elements,
splices and their connections be designed to have the strength to resist 0
times the specified seismic design forces in accordance with Section
12.10.2.1. The purpose of this requirement is to ensure that the inelastic
energy dissipation occurs in the ductile lateral force-resisting elements
(frames, braces and walls) rather than in collectors, diaphragms and their
connection to the LLRS.
It should be mentioned here that the global ductility system reduction fac-
tor, R, that is used to reduce the elastic response spectrum demands on the
LLRS implies that adequate overstrength is provided in diaphragms,
collectors and connections to ensure these remain essentially elastic. Thus it
is essential that these elements do not yield, and that yielding and inelastic
energy dissipation occurs primarily in LLRS to be consistent with design
assumption in reducing the elastic base shear using R.
Design Example 1
Concrete Diaphragm DesignFour-Story Building
Overview
Outline
This example will illustrate the following parts of the design process:
Given Information
Building data:
A computer program has been used to calculate the self-weight of the slabs,
beams, girders, columns and shear walls. All member sizes assumed in the
analysis are shown in Figures 1-2 and 1-3. The following are the modeling
assumptions incorporated into the computer analysis:
An exterior cladding load of 20 psf, which acts along the perimeter of the
floors and the roof, was used in generating the seismic loads. The typical
story height is 15 feet. The following are the total seismic weights tributary
to each floor level, as calculated by the computer program:
W roof = 3,149 k
W 4th floor = 3,442 k
W 3rd floor = 3,442 k
W 2nd floor = 3,271 k
W = 13,304 k
Note: Seismic weights are equal for both the north-south and east-west
directions.
Typical slab: 61/2-inch-thick with #5 @ 12 inch o.c., top and bottom in the
east-west direction. Temperature and shrinkage reinforcement: #4 @ 12
inch o.c. in the north-south direction. See Figure 1-1 below.
Interior beams 21 x 24
Perimeter beams 21 x 24
Interior girders 24 x 28
Exterior columns 21 x 21
Interior columns 24 x 24
Figure 1-3. Third and fourth floor plan (roof plan similar)
Figure 1-4. Typical E-W elevation (Grid Line 1; Grid Line 4 similar)
Figure 1-5. Typical N-S elevation (Grid Line B; Grid Line F similar)
Determine the approximate building period (see Figures 1-4 and 1-5 for
typical elevations):
Ta = C t (hn ) = 0.020(60)
x 3/ 4
= 0.43 s (12.8-7)
North-south direction:
T = 0.51 s (from computer model)
East-west direction:
T = 0.38 s (from computer model)
100325887
= 0.69 s
For this example, the building period as calculated in the computer analysis has
been used as allowed in accordance with 12.8.2. However, the designer can
use the approximate fundamental period, Ta, calculated above as an alternative.
Seismic data:
Values for SS and S1 can be determined from the maps in ASCE 7-05 or
from the USGS web site, which calculates the values by either zip code or
latitude and longitude coordinates.
2 2
S DS = S MS = (0.45) = 0.30 (11.4-3)
3 3
2 2
S D1 = S M 1 = (0.192) = 0.128 (11.4-4)
3 3
TL = 4 s Figure 22-15
I = 1.0
V = C sW (12.8-1)
where
S DS 0.30
Cs = = = 0.075 (governs in east-west direction) (12.8-2)
R 4.0
I 1.0
North-south direction:
S D1 0.128
Cs = = = 0.063 (governs in north-south direction) (12.8-3)
R 4.0
T 0.51
I 1.0
East-west direction:
S D1 0.128
Cs = = = 0.084
R 4 .0
T 0.38
I 1 .0
for T TL
C s = 0.01 (12.8-5)
V = 0.063(13,304 k ) = 838 k
V = 0.075(13,304 k ) = 998 k
The design base shear must be distributed to each floor level, as follows:
Fx = C vxV (12.8-11)
where
w x hxk
C vx = n
(12.8-12)
w h
i =1
i i
k
and
Table 1-1. Vertical distribution of seismic forces for the north-south direction (SDC B)
Table 1-2. Vertical distribution of seismic forces for the east-west direction (SDC B)
COM
COM
COR Fix
0.05Ly Ly
COR ey
ex 0.05Lx
Fiy
Lx
Case I - COM displaced in positive x-direction; force in positive y-direction Case V - COM displaced in positive y-direction; force in positive x-direction
ey
COM COR 0.05Ly
COR
Ly
Fix
ex
COM
0.05Lx
Fiy
Lx
Case II - COM displaced in negative x-direction; force in positive y-direction Case VI - COM displaced in negative y-direction; force in positive x-direction
Fiy
COM
COM Fix
COR
0.05Ly Ly
COR ey
ex 0.05Lx
Lx
Case III - COM displaced in positive x-direction; force in negative y-direction Case VII - COM displaced in positive y-direction; force in negative x-direction
Fiy
0.05Lx
COM ey
COR 0.05Ly
COR
Ly
Fix
ex
COM
Lx
Case IV - COM displaced in negative x-direction; force in negative y-direction Case VIII - COM displaced in negative y-direction; force in negative x-direction
Note: The locations of the COM and COR above are shown exaggerated for illustration purposes.
F
i=x
i
F px = n
w px (12.10-1)
w
i=x
i
The diaphragm design force at each level shall not be less than:
Table 1-3. Diaphragm design forces for the north-south direction (SDC B)
From the computer analysis, to calculate the diaphragm force at the third-
floor level for walls on lines B and F, subtract the cumulative shear in each
wall at the third floor level from the cumulative shear in the corresponding
wall at the fourth floor level (see Figures 1-11 and 1-12).
F3rd diaphragm (Line B) = V3rd (wall at Line B) V4th (wall at Line B) (1d-1)
F3rd diaphragm (Line F) = V3rd (wall at Line F) V4th (wall at Line F) (1d-2)
F3rd diaphragm (total) = F3rd diaphragm (Line B) + F3rd diaphragm (Line F) (1d-3)
For the particular case where both the lateral system and the floor plan are
symmetrical about the centerline of the building and the wall stiffnesses are
the same, the force calculated from Equations 1d-1 and 1d-2 along lines B
and F will be equal for the center of mass analysis (i.e. ignoring accidental
torsion). This implies that the diaphragm force at the second-floor level will
be a constant, uniformly distributed load along the entire length of the
diaphragm.
Figures 1-13 through 1-16 present detailed shear and moment calculations
for the 3rd floor diaphragms. Since accidental torsion must be considered in
accordance with 12.8.4.2, the forces obtained at lines B and F will be un-
equal and the diaphragm force obtained from Equation 1d-3 when
distributed along the length of the diaphragm will be trapezoidal in shape as
shown in Figure 1-17. It should be noted that all load cases (i.e. positive
and negative accidental torsion as illustrated in Figure 1-10) must be con-
sidered when calculating shear wall and diaphragm demands.
where
> 1.0
Once the factored diaphragm load is calculated, the diaphragm can then be
analyzed as a continuous beam with pinned supports representing the shear
walls below. The resulting internal shear diagram calculated by the beam
model can be used to determine the total diaphragm shear at any location
along the length of the diaphragm.
M
T =C = (1d-5)
D
where
Diaphragm shear:
Total wall shears at each level for concrete shear walls in the north-south
direction are as follows (these values represent the resulting wall shears
with the mass displaced 5 percent to the east of the COM; if the mass is
displaced 5 percent to the west of the COM then the wall shears on Grid
Lines B and F would be switched):
146.68 k
266.85 k
348.42 k
383.56 k
171.89 k
310.57 k
404.21 k
443.40 k
RL RR
a b c
w1
w2
L
Known values:
Sum the forces in the direction of the load and sum moments about the left
support point, RL (two equations and two unknowns):
w1 + w2
(1) L = RL + RR
2
L 1 2
(2) w1 L a + ( w2 w1 ) L L a = R R b
2 2 3
Applying the factor to the distributed load (Figure 1-14a) gives the dia-
phragm load at the Fpx force level (Figure 1-14b). Analysis of the beam
model yields support reactions that represent the shear wall forces shown
above, multiplied by the factor. This can serve as a computational check
of the accuracy of the beam model by dividing out the factor and com-
paring the resulting beam reactions to the wall shears shown in Figures
1-11 and 1-12.
VudF 91.0 k
vudF = = = 1.01 klf
LdF 90ft
Therefore, the ultimate shear in the third floor diaphragm in the north-south
direction occurs at Grid Line F when the mass is offset to the east of the
COR.
Chord forces:
The maximum chord forces will occur at the location of maximum moment.
Based on the moment diagram shown in Figure 1-16, the maximum mo-
ment occurs at the point of zero shear, which in this case is near the mid-
point of the center span. Assuming an approximate center-to-center distance
between chord elements of 95 percent of the total diaphragm depth, the
chord forces are calculated as follows:
Mu = 1958.2 k-ft
D = 0.95(90ft ) = 85.5 ft
M u 1,958.2 k - ft
Tu = = = 22.9 k
D 85.5 ft
It should be noted here that one could use the center-to-center distance be-
tween perimeter beams as D. If this is used, the chord reinforcement should
be located at the top of the perimeter beam.
B F
R L = 81.57k R R= 93.64k
a = 30 ft b = 120 ft c = 30 ft
R L = 121.54k R R= 139.52k
a = 30 ft b = 120 ft c = 30 ft
Figure 1-15. Shear diagram (nonlinear) for third floor beam model, fpx force level (k)
Figure 1-16. Moment diagram for third floor beam model, fpx force level (k-ft)
fx
f px = f x
Figure 1-17. Plan view of third floor diaphragm showing loading at base shear (fx) and
diaphragm force (fpx) levels
tension chord, T
compression chord, C
direction of
force
Figure 1-18. Plan view of third floor diaphragm showing flexural behavior and resulting
chord forces
Diaphragm shear:
Using the procedure outlined in Part 1d, the total diaphragm force at each
grid line is calculated as:
The diaphragm will be checked at two locations: (1) the shear wall line with
the higher diaphragm shear demand (Grid Line F); (2) the side of the
opening with the higher shear demand (Grid Line E).
VudF 63.9 k
(1) vudF = = = 0.71 klf
LdF 90 ft
V 31.5 k
(2) vudE = udE = = 0.45 klf
LdE (90 ft 20 ft )
B F
R L = 35.14k R R= 39.19k
a = 30 ft b = 120 ft c = 30 ft
Figure 1-19a. Beam model of second floor diaphragm with fx loading applied
R L = 87.50k R R= 97.58k
a = 30 ft b = 120 ft c = 30 ft
w 1= 0.916 klf
w 2= 1.14 klf
Figure 1-19b. Beam model of second floor diaphragm with fpx loading applied
31.5 k
Edge of opening
Figure 1-20. Shear diagram (nonlinear) for second floor beam model, fpx force level (k)
Figure 1-21. Moment diagram for second floor beam model, fpx force level (k-ft)
Chord forces:
The primary chord forces at midspan of the diaphragm are calculated in a
manner similar to that described in Part 1d, as follows:
D1 = 0.95(90 ft ) = 85.5 ft
M u1 1,388.6 k - ft
Tu1 = = = 16.2 k
D1 85.5 ft
The secondary chord forces are calculated based on the internal moment in
the diaphragm segment adjacent to the opening. Idealizing the segment
above the opening as a beam with fixed ends, the applied loading is ap-
proximated based on the relative mass of each segment. Since the building
is symmetric and the opening is located directly in its center, the applied
loading on each segment will be equal to half of the overall applied trape-
zoidal load over this portion of the diaphragm as shown in Figures 1-22 and
1-23 (see calculation below). The moment diagram is then derived as
shown in Figure 1-24.
The trapezoidal load on the diaphragm segment above the opening is cal-
culated as follows:
180 ft 57 ft
1 2 = 0.53 klf
w2 ' = 1.14 klf (1.14 klf 0.916 klf )
2 180 ft
w1 w2
w1 w2
w1
w2
Figure 1-22. Plan view of second floor diaphragm showing distribution of overall trapezoidal
load to diaphragm segments adjacent to opening
57 ft
(opening)
Figure 1-24. Moment diagram for second floor diaphragm segment above opening (k-ft)
The secondary, T2, and total chord forces near midspan are then calculated
based upon the maximum positive moment as follows:
D2 = 0.95(35ft ) = 33.3 ft
M u 2 69.7 k - ft
Tu 2 = = = 2.09 k
D2 33.3ft
Direction of
secondary tension force, T3 EQ force
secondary compression force, C3
Figure 1-25. Plan view of second floor diaphragm showing flexural behavior and resulting
primary and secondary chord forces for the diaphragm segments near midspan
D2 = 0.95(35 ft ) = 33.3 ft
M u 3 140.2 k ft
Tu 3 = = = 4.21 k
D2 33.3 ft
Note that this force will govern in the design of the chord nearest the open-
ing. Based upon the moment diagram in Figure 1-24, the seismic force
when reversed will induce a maximum negative moment near midspan of
the diaphragm segment equal to 69.7 k-ft, which is less than the maximum
positive moment of 140.2 k-ft at the end of the segment. Thus, the dia-
phragm chords will be designed based upon a maximum moment of 140.2
k-ft since the area of chord steel provided is constant over the full length of
the diaphragm segment. However, additional reinforcement may be pro-
vided locally in the diaphragm segment if the demands are significant.
Note that, although not shown here, the above approach shall also be used
for the design of the chords in the east-west direction.
The design shear strength of the 61/2-inch-thick concrete floor slab is cal-
culated as follows:
where
12 in. 1 k
Vc = (0.75) 2 4,000psi (6.5 in.) = 7.4 klf
1ft 1000 lbs
The slab reinforcement required for the chord forces must be calculated.
The design tension strength of the reinforcement is calculated as:
Tn = As f y Tu
where
Tu = 22.9 k
Tu 22.9 k
As = = = 0.42 in.2
f y (0.9)(60 ksi)
Alternatively, the reinforcement provided at the top of the beam (i.e., com-
pression reinforcement) can be utilized to meet the demand of chord forces.
However, only the reinforcement provided in excess of that required for
gravity demands alone may be used to resist lateral loads (i.e., as chord re-
inforcement).
Note that elements that resist chord forces due to seismic loading in one
particular direction may act as collector elements for seismic forces in the
perpendicular direction. In such cases, these elements must be designed for
the highest forces resulting from seismic loading in either direction. Provide
Class B splices for all chord and collector reinforcement (see ACI 318-05
21.9.8.2 and 12.15 for splice requirements).
The slab thickness and reinforcement is the same as the third floor. There-
fore, the design shear strength of the diaphragm is:
The additional slab reinforcement required to resist the chord forces is cal-
culated using the same procedure outlined in Part 2b. The total chord
reinforcement required for primary and secondary chord forces:
Tutot 18.3 k
As = = = 0.34 in.2
f y (0.9)(60 ksi)
Note that since one #6 bar is required for both primary and total chord
forces near to midspan of the opening, this reinforcement shall be used
continuously along the full length of the edge of the diaphragm. If extra re-
inforcement were required at the edge of the opening to carry the additional
load due to the secondary chord force, this reinforcement should be
provided along the length of the diaphragm adjacent to the opening and
should extend a distance equal to the development length, ld, of the bar be-
yond each end of the opening.
Tu 3 4.21 k
As = = = 0.08 in.2
f y (0.9)(60 ksi)
provide one #5 ( As = 0.31 in.2 ) bar at the inside slab edge adjacent to
the opening
The load combination used in the collector design for Seismic Design Cate-
gory B is in accordance with 12.4.2.3:
(1.2 + 0.2S DS )D + QE + L
where
= 1.0
Q E (1.0)(139.52 k )
v diaph = = = 1.55 klf
Ldiaph 90ft
QE (1.0)(139.52 k )
v wall = = = 4.65 klf
L wall 30ft
Note that the above calculation of the distributed diaphragm force as-
sumes a uniform mass distribution across the diaphragm and hence a lin-
ear distributed diaphragm force, which is indeed the case in this example.
Nonuniform mass distribution must be accounted for in the determination
of the distributed diaphragm force where it occurs. The collector diagram
is calculated as follows:
46.5 k
-46.5 k
Figure 1-26. Distributed diaphragm force and collector diagram for third floor collector on
Line B (k)
Based on the collector diagram in Figure 1-26, the maximum axial force
(QE) on the collector is:
Tu = C u = 46.5 k
Flexure:
The flexural demand on the collector beams is due to gravity loading. Based
on the (1.2D + 1.6L) load combination and equations in ACI 318-05 for the
flexural design of reinforced concrete beams, the loading and required
longitudinal reinforcement for the beam on Line B assuming simply
supported end conditions is as follows:
For the seismic load combination used in Part 4a, the load effects due to
gravity and lateral loads are:
Tension:
Tn = Fy As
where
Compression:
The design strength of a nonprestressed reinforced concrete section in
compression with ties is:
[
Pn = 0.80 0.85 f c' (Ag Ast ) + f y Ast ] ACI 318-05 10.3.6.1 (10-2)
Axial-Flexure Interaction:
The collector must be designed as a beam-column. In order to determine the
interaction of flexural and axial load effects an axial load-moment interac-
tion, or P-M, diagram is typically constructed either by hand or by using a
computer program. The construction of a P-M diagram requires that the
section size and reinforcement be previously known or assumed with the
final design being achieved through iterative analysis. Four major points
including the strength in pure compression (Pn), the balanced point (Pb,
Mb), the strength in pure flexure (Mn) and the strength in pure tension
(Tn) must be determined in order to construct the P-M diagram.
A computer program has been used in this example and the resulting P-M
diagram is shown in Figure 1-27. Points 1 and 2 plotted on the diagram rep-
resent the factored axial and flexural loads determined in Part 4a. Both
points fall within the P-M curve indicating that the section is adequate to
carry the design loads.
Use six #8 longitudinal bars at bottom with two #8 corner bars at top
Figure 1-27. P-M diagram for third floor collector on Line B (k)
The rigid diaphragm assumption used for the example in Seismic Design
Category B is also valid for Seismic Design Category C, since it meets the
requirements of 12.3.1.2, and the horizontal irregularity Type 3 in Table
12.3-1, which addresses openings in the diaphragm, is not applicable for
this category. From the three dimensional analysis results, it has been veri-
fied that horizontal irregularity Type 1a does not exist. If torsional
irregularities do exist, then the design forces determined from the analysis
must be increased by 25 percent for the design of diaphragm connections to
the vertical elements in accordance with 12.3.3.4. The redundancy factor
can be taken as equal to 1.0 in accordance with 12.3.4.1.
Note: this section follows the procedure presented in Part 1 and is a con-
densed version.
Seismic data:
Values for SS and S1 can be determined from the maps in ASCE 7-05 or
from the USGS web site, which calculates the values by either zip code or
longitude and latitude coordinates.
2 2
S DS = S MS = (1.5) = 1.0 (11.4-3)
3 3
2 2
S D1 = S M 1 = (0.54 ) = 0.36 (11.4-4)
3 3
TL = 4 s Figure 22-15
I = 1.0
R = 5 .0 Table 12.14-1
V = C sW (12.8-1)
where
S DS 1.0
Cs = = = 0.200 (12.8-2)
R 5 .0
I 1.0
North-south direction:
S D1 0.36
Cs = = = 0.141 (governs in north-south direction) (12.8-3)
R 5.0
T 0.51
I 1.0
East-west direction:
S D1 0.36
Cs = = = 0.189 (governs in east-west direction)
R 5.0
T 0.38
I 1.0
for T TL
C s = 0.01 (12.8-5)
V = 0.141(13,304 k ) = 1876 k
V = 0.189(13,304 k ) = 2514 k
Table 1-4. Vertical distribution of seismic forces for the north-south direction (SDC D)
Table 1-5. Vertical distribution of seismic forces for the east-west direction (SDC D)
Redundancy Factor, :
The redundancy factor, , for SDC D, must be calculated based upon the
requirements in 12.3.4.2. According to this section, shall equal 1.3
unless one of two conditions is met, in which case shall equal 1.0.
(1) Since all of the shear walls in the example building have a height-to-
length ratio less than 1.0 (15 ft/30 ft = 0.5), item 12.3.4.2.a is automatically
met and therefore equals 1.0 in this example.
(2) To check if item 12.3.4.2.b is met, the number of bays, which is calcu-
lated based upon the definition of a bay given in this section, must be
greater than two. Based on Tables 1-4 and 1-5, only the roof level resists
more than 35 percent of the base shear in both directions and is therefore
the only level that needs to be checked for compliance with item 12.3.4.2.b.
By inspection, the north-south direction will govern since there are only
two walls in this direction.
(30 ft )
No. bays = = 2 bays 2 bays
15 ft
= 1.0
Note that the code requires that only one of the above conditions must be
satisfied in order for to equal 1.0.
F
i=x
i
F px = n
w px (12.10-1)
w
i=x
i
The diaphragm design force at each level shall not be less than:
Table 1-6. Diaphragm design forces for the north-south direction (SDC D)
Note that for buildings assigned to SDC D through F, the structure must be
checked for horizontal structural irregularities listed in Table 12.3-1 in
accordance with 12.3.3.4. Since the example building is symmetrical in
both mass and lateral system, it has neither Torsional Irregularity (1a) nor
Extreme Torsional Irregularity (1b) by inspection. For structures with rigid
or semirigid diaphragms, the method for checking for torsional
irregularities is as shown in Figure 1-28 as follows:
+ b
Type 1a applies if: max > 1.2 a
2
+ b
Type 1b applies if: max > 1.4 a
2
330.03 k
600.42 k
783.94 k
863.02 k
386.75 k
698.78 k
909.46 k
997.65 k
Based on Figure 1-32, the ultimate shear at Grid Line B is calculated as:
VudB 220.6 k
vudB = = = 2.45 klf
LdB 90ft
VudF 241.9 k
vudF = = = 2.69 klf
LdF 90 ft
Therefore, the ultimate shear in the third floor diaphragm in the north-south
direction occurs at Grid Line F when the mass is offset to the east of the
COR.
Chord forces:
In accordance with Figure 1-33, the maximum moment at midspan of the
diaphragm is:
Mu = 5202.8 k-ft
D = 0.95(90ft ) = 85.5ft
M u 5202.8 k ft
Tu = = = 60.9 k
D 85.5 ft
Figure 1-31. Beam model of third floor diaphragm with fx loading applied
Figure 1-31a. Beam model of third floor diaphragm with fpx loading applied
Figure 1-32. Shear diagram (nonlinear) for third floor beam model, fpx force level (k)
Figure 1-33. Moment diagram for third floor beam model, fpx force level (k-ft)
For the diaphragm with an opening (second floor), the diaphragm design
forces are calculated using the same procedure as described in detail in Part
1e.
Due to the large opening at the center of the second floor diaphragm in this
example, the Diaphragm Discontinuity Irregularity (3) in Table 12.3-1 must
be checked in accordance with 12.3.3.4. This is done as follows:
1,140 ft 2
= 0.07 < 0.50 Irregularity 3 does not apply
16,200 ft 2
Since the area of the opening in the diaphragm is only 7 percent of the gross
enclosed diaphragm area, by inspection there is no change in diaphragm
stiffness of more than 50 percent from the second floor to the adjacent lev-
els. Therefore, in accordance with 12.3.3.4, the seismic design forces need
not be increased.
The diaphragm will be checked at two locations: (1) the shear wall line with
the higher diaphragm shear demand (Grid Line F); (2) the side of the open-
ing with the higher shear demand (Grid Line E).
VudF 204.0 k
(1) vudF = = = 2.27 klf
LdF 90ft
VudE 96.0 k
(2) vudE = = = 1.37 klf
LdE (90ft 20ft )
Figure 1-34. Beam model of second floor diaphragm with fx loading applied
Figure 1-34a. Beam model of second floor diaphragm with fpx loading applied
96.0 k
Edge of opening
Figure 1-35. Shear diagram (nonlinear) for second floor beam model, fpx force level (k)
Figure 1-36. Moment diagram for second floor beam model, fpx force level (k-ft)
D1 = 0.95(90ft ) = 85.5ft
M u1 4428.7 k ft
Tu1 = = = 51.8 k
D1 85.5ft
The trapezoidal load on the diaphragm segment above the opening is cal-
culated as follows (see Figure 1-37):
180ft 57ft
1 2 = 1.584 klf
w1 ' = 2.923 klf + (3.638 klf 2.923 klf )
2 180 ft
180ft 57ft
1 2 = 1.697 klf
w2 ' = 3.638 klf (3.638 klf 2.923 klf )
2 180 ft
Figure 1-37. Beam model of second floor diaphragm segment above opening with fpx loading
applied
Figure 1-38. Moment diagram for 2nd floor diaphragm segment above opening (k-ft)
D2 = 0.95(35ft ) = 33.3ft
M u 2 222.1 k ft
Tu 2 = = = 6.67 k
D2 33.3ft
D2 = 0.95(35ft ) = 33.3ft
M u 3 447.2 k ft
Tu 3 = = = 13.4 k
D2 33.3ft
The slab thickness and reinforcement is shown in Figure 1-1. For Seismic
Design Category D, the diaphragm shear strength shall be in accordance
with ACI 318-05 21.9.7 and is calculated as follows:
where
Note that the diaphragm shear strength calculated above shall not exceed
8 Acv f ' c in accordance with ACI 318-05 21.9.7.3.
For the 61/2-inch concrete slab (ignoring the steel reinforcement in the
slab):
12 in. 1k
Vn = (0.75)(6.5 in.) ( 2 4,000psi ) = 7.4 klf
1ft 1000 lbs
Tu = 60.9 k
Tu 60.9 k
As = = = 1.13 in.2
f y (0.9)(60 ksi)
For SDC D, the chord must also be checked for compressive stresses in
accordance with ACI 318-05 21.9.5.3. Assuming a 2-foot strip,
C u = 60.9 k
60.9 k
= 0.390 ksi = 0.10 f ' c
(6.5 in.)(24 in.)
Since the maximum chord compressive stress is less than 0.2f c special
transverse reinforcement is not required.
The additional slab reinforcement required to resist the chord forces is cal-
culated using the same procedure outlined in Part 2b. The total chord
reinforcement required for primary and secondary chord forces:
Tutot 58.5 k
As = = = 1.08 in.2
f y (0.9)(60 ksi)
Note that since three #6 bars are required for both primary and total chord
forces near to midspan of the opening, this reinforcement shall be used
continuously along the full length of the edge of the diaphragm. If extra re-
inforcement were required at the edge of the opening to carry the additional
load due to the secondary chord force, this reinforcement should be
provided along the length of the diaphragm adjacent to the opening and
should extend a distance equal to the development length, ld, of the bar be-
yond each end of the opening.
Tu 3 13.4 k
As = = = 0.25 in.2
f y (0.9)(60 ksi)
F px 370.80 k
v diaph = = = 4.12 klf
Ldiaph 90ft
F px 370.80 k
v wall = = = 12.36 klf
Lwall 30ft
123.6 k
-123.6 k
Figure 1-39. Distributed diaphragm force and collector diagram for third floor collector on
Line B (k)
Based on the collector diagram in Figure 1-39, the maximum axial force on
the collector is:
Tu = C u = 123.6 k
Since the current code requirement for collector design in accordance with
ASCE 7-05 12.10.2 and 12.10.2.1 leads to overly conservative collector
demands, this example follows the latest (August 2008) SEAOC
Seismology Committees draft recommendations, which are as follows:
According to the revised ASCE 7-05 12.10.2.1, the collector forces are
calculated as:
(2.5)(123.6 k )
1) 0 Fx = = 176 k
1.76
0.168
2) 0 F px = (2.5)(123.6 k ) = 260 k
0.200
3) 115 k
Note that in this example the minimum diaphragm shear at the third level
governs as shown in Table 1-6. As a result, the collector design load in
Item 2 above must be factored down to the actual diaphragm shear level
as shown above.
To calculate collector demand using Item 3 noted above (115 k), take the
weight tributary to the diaphragm at the level under consideration in
accordance with Table 1-4 (wpx = 3442 k) and derive the collector load
based upon a seismic coefficient of 0.2SDSIwpx as follows (note that due to
the symmetrical nature of the building the weight tributary to each of the
3442 k
W pxB = = 1721 k
2
1791 k
w pxB = = 19.1 klf
90ft
The design of the collector follows the same procedure as explained in Part
4b using the seismic load combination in accordance with ASCE 7-05
12.4.3.2 as follows:
(1.2 + 0.2S DS )D + 0 QE + L
The gravity demands and design for 1.2D+1.6L load combination are the
same as those calculated in Part 4b. For the seismic load combination
above, the load effects due to gravity and lateral loads are:
An interaction diagram has been has been created for the collector as shown
in Figure 1-40.
Use six #9 bars at bottom; four #8 bars at top; two #8 bars each side
Cu 260k
fc = = = 0.52 ksi = 0.13 f c' 0.5 f c'
Ag (21in.)(24 in.)
Figure 1-40. P-M diagram for third floor collector on Line B (k)
10. Design of Slab as Collector Element on Third Floor, Line B for Seismic
Design Category D (Alternate Approach for Collector Design).
The following example is provided to illustrate an alternate approach for
concrete slab collector design. Please refer to the 2008 SEAOC Blue Book:
Seismic Design Recommendations, Article 05.02.030 and the paper titled,
Concrete Slab as Collector Element, by SEAONC Concrete Subcom-
mittee (see Reference 11), for a more detailed description of the theory and
methodology. Figures 1-41 through 1-44 present design methodology and
details.
10a. Calculate Collector Forces and Effective Slab Width on Each Side of
the Wall.
As calculated in Part 9a, the ultimate collector forces with the over-
strength factor applied are:
Cu = Tu = 260 k
Since this is an interior condition, the collector force must be broken into
components, which are then applied to each side of the collector line (see
Figure 1-42). The components are calculated in proportion to the
respective diaphragm shear on each side of the collector line as follows:
V BL
FBL = FC
RL
V
FBR = BR FC
RL
where
128.9 k
FBL = ( 260 k ) = 90.4 k
370.8 k
241.9 k
FBR = ( 260 k ) = 169.6 k
370.8 k
These forces, FBL and FBR, will be applied at the midwidth of the effective
slab section on either side of the collector line. For the purposes of this ex-
ample, the effective slab width will be assigned assuming a 30 influence
line on both sides of the collector line originating at the point of zero force
on the collector diagram, which in this case occurs at midlength of the wall
in accordance with Figure 1-42. Note that 45 is recommended in the Blue
Book but in order to reduce the eccentricity, 30 is used here. The total
effective width is then calculated as:
L 1 ft 30 ft
B EFFTOT = t wall + 2 wall tan 30 = (12 in.) + 2 tan 30 = 18.3 ft
2 12 in. 2
B EFFTOT 18.3 ft
B EFF = = = 9.15 ft
2 2
The effective slab area on each side of the collector line is:
12 in
AC = (B EFF )(t slab ) = (9.15 ft ) (6.5 in.) = 714 in.
2
1 ft
The amount of steel required to resist collector tension must now be cal-
culated. Since there is no prestressing force on the slab, the net collector
tension force, TNET, is equal to the collector force as calculated above.
TNETL 90.4 k
AsL = = = 1.67 in.2
Fy (0.9)(60 ksi)
1.67 in.2
= 0.18 in.2/ft
9.15ft
TNETR 169.6 k
AsR = = = 3.14 in. 2
Fy (0.9)(60 ksi)
3.14 in.2
= 0.34 in.2/ft
9.15ft
Note that this reinforcement shall be placed symmetrically about mid-depth of the
concrete section so as to prevent additional out-of-plane bending stresses in the slab.
The slab must now be checked for the compression stress on the effective
width. As with designing the slab for tension forces, the net compression
force, CNET, is equal to the collector force as calculated above since there
is no prestressing force on the slab. As discussed in Part 9a, special
transverse reinforcement must be provided if the resulting compression
stress on the effective slab width exceeds 20 percent of f'c in accordance
with ACI 318-05 21.9.5.3.
C NETL 90.4 k
= = 0.13 ksi = 0.032 f ' c < 0.5 f ' c
AC 714 in.2
C NETR 169.6 k
= = 0.24 ksi = 0.060 f ' c < 0.5 f ' c
AC 714 in.2
Figure 1-42. Free body diagram for slab element on left and right sides of collector Line B
where
and
FBL 90.4k
v dL = = = 1.00 klf
Ldiaph 90ft
Therefore,
The collector force, FCL , is then applied at midwidth of the slab element as
shown in Figure 1-42, thus inducing an in-plane bending moment, Me, in
the slab due to the eccentricity of the slab element midwidth to the collector
line. The slab reinforcement must be designed to resist the seismic shear
and in-plane bending moment due to this eccentric collector load. Note that
the slab reinforcement provided to resist gravity loads is not used here to re-
sist seismic loads, and all slab reinforcement calculated below is to be
provided in addition to the gravity reinforcement consisting of #5 at 12
inches o.c. top and bottom.
B EFF 9.15 ft
e= = = 4.58 ft
2 2
M eL = VeL L*wall + M 1L + M 2 L + M 3 L
where
In this case, since the eccentricity, e, is small relative to the wall length (30
ft), the moments M2L and M3L may be neglected (see the Blue Book article
for explanation). Thus, the equation reduces to:
M eL = VeL L*wall + M 1L
where
Since the added steel As1 is distributed evenly over the length of the slab
segment, the moment arm j1.Lwall is assumed to be equal to 75 percent of the
wall length. Also, since the additional reinforcement, A*s, begins at the end
of the wall in this example, the moment arm j*.Lwall is assumed to be equal
to 90 percent of the length of the wall. Referring to Figure 1-42, the mo-
ment arms j1.Lwall and j*.Lwall are thus calculated as follows:
Try #5 at 12 inches o.c. along the full length of the wall for As1 and solve
for A*s (note that both As1 and A*s are perpendicular to the wall):
M1L VeLL*wall
in.2
As1 = (#5 @ 12" o.c.)(0.5)( Lwall ) = (0.31 )(0.5)(30 ft ) = 4.65 in.2
ft
M 1L = (0.9)(60ksi)(4.65 in. 2 )(20.3ft ) = 5,097 k ft >> 965.5 k ft
Since the moment capacity of the slab element with the added As1 rein-
forcement greatly exceeds the required moment, MeL, this reinforcement is
unnecessary and shall be neglected. Only the added steel at the end of the
wall, A*s, shall be used to resist the required moment. (Note: this is true
only for this particular example. The user should check for additional
reinforcement, As1, due to moment, M1L. In the case where M1L is less than
MeL, both As1 and A*s may be required.) The required steel, A*s, is
calculated as follows:
M eL (965.5 k ft )
As* = *
= = 0.66 in.2
F y ( j .Lwall ) ( 0 . 9 )( 60 ksi )( 27 ft )
use two #6 bars at each end of the wall (As = 0.88 in.2)
For the right side of the collector line (similar to the procedure used for
the left side):
where
and
FBR 169.6 k
v dR = = = 1.88 klf
Ldiaph 90ft
Therefore,
B EFF 9.15ft
e= = = 4.58ft
2 2
By inspection, only the added reinforcement at each end of the wall is re-
quired since MeR exceeds M1L as calculated above. Therefore, the rein-
forcement required at the end of the wall, A*s, is calculated as:
M eR (1811.8 k ft )
As* = *
= = 1.24 in. 2
F y ( j .Lwall ) (0.9)(60 ksi)(27ft )
use three #6 bars at each end of the wall (As = 1.32 in.2)
Since two #6 bars are required at the end of the wall for the collector forces
on the left side of the wall, these bars will run continuous through the wall
and be used at the right side of wall as well. Additionally, one #6 bar is
provided at the right side, which extends beyond the wall to the left side a
distance equal to the development length of the bar as shown in Figure 1-
43. Note that since the layout of the wall is symmetrical, the same amount
of steel will be required at the opposite end of the wall when the load is
reversed.
(
Vu Acv f ' c + n F y )
where
Vu = FCL = 210.8 k
= 0.75
12 in. 2
Acv = (t slab )( Lwall ) = (6.5 in.)(30 ft ) = 2,340 in.
ft
B 9.15 ft
= EFF = = 0.305
Lwall 30 ft
Calculate the amount of steel (n) required to resist the diaphragm shear:
1 Vu
n = f 'c
Fy Acv
1 210.8k 1 ksi
n = 2
(0.305) 4000psi = 0.0017
60ksi (0.75)(2,340 in. ) 1000 psi
12 in. 2
Asreq'd = n bd = (0.0017)(6.5 in.)(30ft.) = 3.98 in.
ft
Since two #6 bars are provided perpendicular to the wall at each end as cal-
culated in Part 10d (four #6 total, As = 1.76 in.2), calculate the additional
amount of steel required the resist the diaphragm shear. This additional
steel will be distributed over the length of diaphragm in between the two #6
bars at each end.
(
Vu Acv f ' c + n F y )
where
Vu = FCR = 395.6 k
(all other parameters are the same as for the left side)
Calculate the amount of steel (n) required to resist the diaphragm shear:
1 395.6 k 1 ksi
n = 2
(0.305) 4000psi = 0.0034
60ksi (0.75)(2,340 in. ) 1000 psi
12 in. 2
Asreq'd = n bd = (0.0034)(6.5 in.)(30ft ) = 7.96 in.
ft
Since three #6 bars are provided perpendicular to the wall at each end as
calculated in Part 10d (six #6 total, As = 2.64 in.2), calculate the additional
amount of steel required the resist the diaphragm shear. This additional
steel will be distributed over the length of diaphragm in between the three
#6 bars at each end.
Since #4 @ 12 inches o.c. is required for the left side, this reinforcement
will extend across the wall line to be used as diaphragm shear
reinforcement for the right side of the wall as shown in Figure 1-43.
Figure 1-43. Plan detail at slab collector on third floor, Line B (see Figure 1-44 for Section E)
References
Department of the Army, Navy and the Air Force, Seismic Design for
Buildings.
Design Example 2
Wood Diaphragm (Flexible Diaphragm) for
Seismic Design Category B, C & DThree-Story Building
Overview
This example is not a complete building design. Many aspects have not
been included and only selected steps of the seismic design related to por-
tions of the diaphragm and representative collectors have been illustrated.
Outline
This example will illustrate the following parts of the design process:
Given Information
Where DOC PS-1 or DOC PS-2 are the U.S. Department of Commerce
(DOC) Voluntary Product Standards for Plywood and OSB.
In Figure 2-1 the engineered wood I-joists run east-west spanning to the
GLB girders running north-south at 26 feet on center along the numbered
grid lines.
The second and third floor diaphragms will be analyzed in the north-south
direction. Concrete masonry unit shear walls are located at grid lines 1, 2, 4,
9, 11 and 12 (Figures 2-1 and 2-3).
Building is regular and qualifies for the equivalent lateral force procedure
to be used.
Determine building period (see Figure 2-2 for section through structure),
using the ASCE 7-05 equation as opposed to being calculated from a com-
puter model.
Ta = C t (hn ) = 0.020(42.0)
x 3/ 4
= 0.33 sec Eq. 12.8-7
This building has an independent steel frame supporting the floors and roof
and is considered a building frame system. Note that the R-value would be
lower for load-bearing intermediate reinforced masonry shear walls.
V = C sW Eq. 12.8-1
S DS
Cs = Eq. 12.8-2
R
I
where
I = 1.0
R = 4.0
Values for Ss and S1 can be determined from ASCE 7-05 maps or from the
USGS web site which calculates the values by either zip code or longitude
and latitude coordinates.
S s = 0.28
Figure 22-1
S1 = 0.08
Figure 22-2
2 2
S DS = S MS = (0.45) = 0.30 Eq. 11.4-3
3 3
2 2
S D1 = S M 1 = (0.192) = 0.128 Eq. 11.4-4
3 3
Values for TL (long-period transition period) are obtained from ASCE 7-05
maps and are used in formula 12.8-3 for determining the cut-off value of Cs
below.
TL = 4 sec
Figure 22-15
0.30
Cs = = 0.075
4.0
1.0
S D1 0.128
Cs = = = 0.097
R 4.0
T 0.33
I 1.0 (12.8-3)
For T TL
C s = 0.01
Eq. (12.8-5)
V = 0.075W
W = 4600 k
W = 3448 k
The base shear must be distributed to each level. This is done as follows:
wx hx
C vx = n
Eq. 12.8-12
w h
i =1
i i
k
Table 2-1. Vertical distribution of seismic forces for the north-south direction of forces
wx hx
Fx
Level w x (k) h x (ft) w x h x (k-ft)
w h i i
Fx (k)
wx
Ftot (k)
(%)
Roof 1126 42 47,292 39.3 135.6 0.120 135.6
3rd Floor 1737 28 48,636 40.5 139.7 0.080 275.3
2nd Floor 1737 14 24,318 20.2 69.7 0.040 345.0
4600 120,246 100.0 345.0
Table 2-2. Vertical distribution of seismic forces for the east-west direction of forces
w x hx
Fx
Level w x (k) h x (ft) w x h x (k-ft)
wi hi Fx (k) Ftot (k)
wx
(%)
Roof 794 42 33,348 37.4 96.9 0.122 96.9
3rd Floor 1327 28 37,156 41.7 108.0 0.081 204.9
2nd Floor 1327 14 18,578 20.9 54.1 0.041 259.0
3448 89,082 100.0 259.0
Tables 2-1 and 2-2 are needed to determine building forces to the shear
walls and will be compared with the diaphragm design forces shown in
Table 2-3.
The floor diaphragm must be designed to resist seismic forces in each di-
rection. The following formula is used to determine the total seismic force,
Fpx, on the diaphragm at a given level of the building.
F
i=x
i
F px = n
w px Eq. 12.10-1
w
i=x
i
For forces in the north-south direction, the second-floor seismic force using
the distributed forces from Table 2-1:
Fxfloor = 69.7 k
For forces in the north-south direction, the third-floor seismic force using
the distributed forces from Table 2-1:
Fxfloor = 139.7 k
The diaphragm design force at each level shall not be less than:
Table 2-3. Vertical distribution of diaphragm seismic forces for the north-south direction
Minimum Code
Diaphragm Force
w x (k) w Fx F i
F px
Level i
(k) (k ) F x
Fpx =
Fx
(k )
w x (k )
Roof 1,126 1,126 135.6 135.6 0.120 135.6 1.00
3rd Floor 1,737 2,863 139.7 275.3 0.096 166.7 1.19
2nd Floor 1,737 4,600 69.7 345.0 0.075 130.3 1.86
4,600 345.0
Note that the Fx and Fpx values at the roof level are the same.
Note that the minimum and maximum forces of Section 12.10.1.1 do not
control.
Diaphragm Flexibility:
Since IBC Section 1613.6.1.3 requires the vertical elements of the lateral-
force-resisting system to be light framed, and this building has masonry
shear walls, it does not meet the requirement for assuming flexible
diaphragms. In addition, since the diaphragms have light-weight concrete
topping, the diaphragm deflection will need to be checked for verification
of flexible diaphragm assumptions. This verification is done in section 2d.
Span-to-Depth Limitations:
The IBC places limits for wood diaphragms. The limit for wood structural
panel diaphragms is 4:1. These limits not only apply to the diaphragm as a
whole, but also to individual segments of the diaphragm. These segments of
the diaphragm can be individual spans, such as Diaphragms I, II and III (see
Figure 2-3), but also the solid areas adjacent to openings, such as the seg-
ments between grid lines 4 and 5 at the second floor opening (see Figure 2-
4). The depth of the diaphragm is taken in the direction of the load and the
span is the distance between supports that are providing support for the
diaphragm. These supports may be vertical lateral force resisting elements
or collectors and cross-ties.
Diaphragm III:
Span 130.0 ft
= = 1.44 < 4.0 OK
Depth 90.0 ft
Span 26.0 ft
= = 0.86 < 4.0 OK
Depth 30.0 ft
For diaphragm analysis with openings totaling less than 10 percent of the
floor area, the entire floor area is usually used (for simplicity).
166.7 1,000
f pfloor = = 6.75 psf
24,675
The maximum diaphragm shear occurs on the east side of line 4 (and on the
west side of line 9) is (Diaphragm III):
39,520 lb
v= = 440 plf
90 ft
The diaphragm shear on the west side of line 4 and the east side of line 9 is
(Diaphragm II):
15,600 lb
v= = 210 plf
(90 ft 15 ft )
Where 15 is the length of the stairwell opening that is subtracted from the
diaphragm length.
Due to the large depths of diaphragms and their small span-to-depth ratios,
their behavior differs slightly from the usual shallow beam analogy. Dia-
phragm shear stresses have been proven to be essentially uniform across the
depth of the diaphragm, as opposed to the parabolic distribution that would
occur in a sawn wood beam.
The floor diaphragm is sheathed with 23/32 inch DOC PS-2-rated (wood
structural panel) OSB sheathing. The loading case is 2 for a staggered panel
layout. The diaphragm shears are strength level loads. The designer has the
choice of using the ASD allowable unit shear capacities or LRFD factored
unit resistance capacities. The nominal unit shear capacities (vs) are ob-
tained from NDS Table 4.2A. The nominal capacities are converted to ASD
capacities by dividing by a factor of safety of 2.0 and are converted to
LRFD capacities by multiplying by a D factor of 0.80 (NDS 4.2.3)
Diaphragm Blocking:
Diaphragm Nailing:
The following will determine the required edge spacing for the nails.
(Maximum nail spacing at intermediate supports or field nailing is 12
inches on center).
1
= 1 .4
0 .7
Assuming that designing for a lower level force is advantageous, this would
give a 14 percent advantage to using LRFD capacities over the traditional
ASD capacities. Since the loads to the diaphragms and shear walls are al-
ready strength level loads (from the ASCE 7 seismic equations), it makes
the designers decision rather easy to use the LRFD capacities and utilize
the advantage at the same time avoiding converting to ASD capacities.
At Line 4, the maximum diaphragm shear is 440 plf. For ease in using the
NDS Table the diaphragm shears will be divided by a D factor of 0.80:
440 plf
vs = = 550 plf
0.80
For Load Case 2, the maximum vs for a blocked diaphragm with 3-inch
nominal framing members is 720 plf > 550 plf, (or 0.80 x 720 > 440); there-
fore, a blocked diaphragm with 10d common nails (0.148 inch diameter)
having a penetration of at least 11/2 inches into framing members spaced 6
inches on center at edges is adequate.
Converting to ASD:
For Load Case 2, the allowable vs for a blocked diaphragm with 3-inch nominal
framing members is:
440 plf
vs = = 360 plf > 310 plf
2 .0
Therefore a blocked diaphragm with 10d common nails (0.148 inch diame-
ter) having a penetration of at least 11/2 inch into framing members spaced 6
inches on center at edges is adequate.
Converting to ASD:
For Load Case 2, the allowable shear for a blocked diaphragm with 3-inch
nominal framing members is:
The maximum chord force occurs at the longest diaphragm span (Dia-
phragm III) between line 4 and line 9.
M 1, 284 , 400 ft - lb
C =T = = = 14 ,300 lb
d 90 .0 ft
Chord members for the diaphragm will utilize steel reinforcing bars in a
horizontal bond beam of the CMU wall near the diaphragm location.
5vL3 0.25 vL ( xc )
dia = + +
8 EAW 1000 G a 2W SDPWS Eq. 4.2-1
where
L = 130 feet
v = incurred unit shear in diaphragm
F px
= = 1.19 (See Table 2-3 at third floor)
Fx
1
v = 440 plf = 370 plf
1.19
W = diaphragm width
W = 90 feet
X = distance from chord splice to nearest support (inches)
c = diaphragm chord splice slip. Since our diaphragm will utilize steel
reinforcing bars (lapped spliced), the slip distance equals zero
inches
dia = maximum midspan diaphragm deflection determined by elastic
analysis (inches)
By inspection, the concrete masonry shear walls are going to drift less than
one half of 1.0 inch and hence, the flexible diaphragm assumptions apply.
Note the actual drifts of the masonry shear walls should be computed but
are not part of this design example.
The diaphragm is first analyzed without the effects of an opening (or open-
ings) to determine the chord and web forces of the diaphragm (beam).
130.3 1,000
f pfloor = = 5.28 psf
24,675
The uniform loads W1, and W2, in the north-south direction are computed
using the diaphragm depths.
3a. Determine Diaphragm III Shears at Interior Boundaries at Grids 4 and 9 (see Figure
2-4).
The maximum diaphragm shear occurs on the east side of line 4 (and on the
west side of line 9) is:
wl 475(130)
V4 = R = = = 30,875 lb
2 2
30,875 lb
v= = 345 plf
90'
The diaphragm shear on the west side of line 4 and the east side of line 9 is:
wl 475plf (51.33ft )
V4 = R = = = 12,190 lb
2 2
12,190lb
v= = 165 plf
(90ft 15ft )
Where 15 is the length of the stairwell opening that is subtracted from the
diaphragm length.
Figure 2-5. Partial second floor diaphragm plan with diaphragm segments
3b. Determine Diaphragm III Chord Forces at Lines A, F and Web Shears at Lines 5, 5.5,
6 and at the Center of the Diaphragm at Line 6.5 (see Figure 2-5).
Since the applied force on the diaphragm is to the south, the chord force
along grid A will be in compression and the chord force along grid F will
be in tension.
At line 5:
L 130
V 5= w x = 475 plf 26 = 18,525 lb
2 2
18,525 lb
v5 = = 309 plf
60 ft
18,525 lb
v5 = = 206 plf
90 ft
2
wL
M= (x ) wx = wx (L x )
2 2 2
M5 =
wx
(L x ) = 475 26 (130 26 ) = 642,200 ft - lb
2 2
M 642,200
F5 @ A = = = 7,135 lb = C
d 90
At line 5.5:
12,350 lb
v5.5 = = 206 plf
60 ft
M 5.5 =
wx
(L x ) = 475 39 (130 39) = 842,887 ft - lb
2 2
M 842,887
F5.5 @ A = = = 9,365 lb = C
d 90
At line 6:
L 130
V6 = w x = 475 plf 52 = 6,175 lb
2 2
6,175 lb
v6 = = 103 plf
60 ft
6,175 lb
v6 = = 69 plf
90 ft
M6 =
wx
(L x ) = 475 52 (130 52) = 963,300 ft lb
2 2
M 963,300
F6 @ A = = = 10,700 lb = C
d 90
L 130
V6 .5 = w x = 475 plf 65 = 0 lb
2 2
M 6.5 =
wx
(L x ) = 475 65 (130 65) = 1,003,400 ft lb
2 2
M 1,003,400
F6.5 @ A = = = 11,150 lb = C
d 90
At line 7:
L 130
V7 = w x = 475 plf 78 = 6,175 lb
2 2
6,175
v7 = = 69 plf
90 ft
The diaphragm areas adjacent to the opening are subdivided into four seg-
ments (Segments 1, 2, 3 and 4 in Figure 2-5). The midpoint of the opening
is assumed to be an inflection point for the chords (see Figure 2-7). The
shear forces, chord forces and diaphragm shears of the segments are deter-
mined by using free-body sketches (see Figure 2-6), and summing forces
and moments to equal zero of the free-body segments to maintain static
equilibrium. Seismic forces are applied in the southern direction.
Segment 1:
Since the opening is at the center of the diaphragm width, the forces are
split to each side of the diaphragm. If the opening was not centered on the
diaphragm width, the force ratios would be based upon their respective
segment widths. The segment widths (30 feet) have been included below
illustrating this.
w 475
= = 237.5 plf
2 2
F5.5 @ C = 0 lb
30 30
V5 = V5 = 18 ,525 = 9262 .5 lb
60 60
9,262 .5
v= = 309 plf
30.0
12 ,350
V 5.5 ( A C ) = = 6,175 lb
2
M 5 .5 @ C = 0 :
13 .0 2
(9,365 30 .0 ) (9, 262 .5 13 .0 ) + ( 237 .5 plf
2
F5 @ A =
30 .0 ft
Note: chord freebody forces usually will not equal chord forces when effect
of opening was not considered. See Section 3d below.
F5 . 5 @ C = 0 :
Segment 2:
w 475
= = 237.5 plf
2 2
F5.5 @ C = 0 lb
30 30
V6 = V6 = 6 ,175 = 3,087 .5 lb
60 60
M 5 .5 @ C = 0 :
3,087 .5
v= = 103 plf
30 .0
13 .0 2
(9,365 30 .0 ) (3,087 13 .0 ) ( 237 .5 plf
F6 @ A =
2
30 .0 ft
= 11,372 lb C > 10,700 lb
Note: chord freebody forces usually will not equal chord forces when effect
of opening was not considered. See Section 3d below.
F6 @ C = 0 :
Note that due to symmetry, the forces in the segments 3 and 4 are equal to
and opposite of segments 1 and 2 respectively.
The 26-foot wide opening with a depth of 30 feet in Figure 2-5 is 33 per-
cent of the total width of the diaphragm. Large openings such as this one
can significantly alter the shear distribution and chord forces. ASCE 7-05
Table 12.3-1 states that diaphragm openings exceeding 50 percent are clas-
sified as a horizontal structural irregularity Type 3 and require increased
The effect of an opening in the diaphragm both increases and decreases the
chord forces at the diaphragm boundary. In addition, the opening also ap-
plies point loads into the diaphragm edge adjacent the opening (see
Figures 2-7, 2-8, 2-9 and 2-10). The first step is to determine the resultant
chord force and applied forces by summing the diaphragm chord forces
without the opening with the chord forces with the opening as tabulated in
Table 2-4.
Table 2-4. Resultant diaphragm III chord forces and applied forces
The chord force values in the column Without Opening (Table 2-4) were
previously determined in Section 3b. The chord force values in the column
With Opening Using FTAO (Table 2-4) were previously determined in
Section 3c. And the values in the column Resultant Due to Opening (Ta-
ble 2-4) are determined by taking the difference between the two columns.
Forces calculated at Grid 6.5 show that chord forces extend beyond just the
corners of the opening. If the chord member were spliced at Grids 6.5 and
C, the connection would have to be designed for a tension force of 663
pounds.
Figure 2-8. Resultant diaphragm III forces and shears at Grid 5 due to opening
M 5C = 0:
1,115 lb (30 .0 ft )
R 4 C = = 1, 287 lb
26 .0 ft
1, 287 lb
v= = 43 plf
30 .0 ft
M 5 D = 0:
( + 3,345 lb 1,115 lb )( 30 .0 ft )
R4 D = = + 2,573 lb
26 .0 ft
+ 2,573 lb
v= = + 86 plf
30 .0 ft
Figure 2-9. Resultant diaphragm III forces and shears at Grid 6 due to opening
The maximum chord force (from Table 2-4) is 11,486 pounds. Chord forces
at lines A and F will be resisted by either steel reinforcing bars in the CMU
wall (they could also be resisted by the ledger at the diaphragm boundary).
The resultant forces at lines C and D (from Table 2-4) will need special
framing members and connectors designed to resist these forces. The de-
signer should consider how far the point load forces need to be developed
into the diaphragm (forces at grid 6.5). The framing plans (and possibly a
special detail) also need to specify a double row of nails (fasteners) for
these opening reinforcing collectors/chords.
Diaphragm Shear
Grid Location (plf)
Without Opening With Opening Using FTAO Resultant Due to Opening
The values in the column Without Opening (Table 2-5) were previously
determined in Section 3a for line 4 and Section 3b for lines 5, 6 and 7. The
values in the column With Opening using FTAO (Table 2-5) were previ-
ously determined in Figures 2-8 and Figure 2-9. The values in the column
Resultant Due to Opening (Table 2-5) are determined by taking the
difference between the two columns.
Note that the diaphragm shears for the collectors at line 4 (A to C and D to
F) have been reduced from 345 plf to 302 plf as a result of the opening in
the diaphragm. The design engineer has the choice of using either the re-
duced force from the opening or the higher force without considering the
effects of the opening. This design example will not utilize the reduced dia-
phragm shears.
Note that the sign convention changes at grid line 7 due to location is on
other side of diaphragm center.
For diaphragm shears between grid Lines 5 and 6, see Figure 2-6.
Statics Check:
(The slight differences in numerical results are due to rounding of the unit
shears)
Line 4:
F N S :
Line 5:
F N S :
Line 6:
F N S :
Line 7:
F N S :
V 7 = 6,175 lb 6,180 lb OK
When designing the structural use panel diaphragm, the vertical (gravity)
loading need not be considered in conjunction with the lateral diaphragm
shears. In accordance with 12.3.4.1, for typical diaphragms, the
redundancy factor equals 1.0. Where there are vertical irregularities with
offsets, where the diaphragm is used to transfer the horizontal forces
between the offsets, the redundancy factor () must conform to 12.3.4 and
12.10.1.1. In this design example, equals 1.0 for the diaphragm.
The floor diaphragm is sheathed with 23/32 inch DOC PS-2-rated (wood
structural panel) OSB sheathing. The loading case is 2 for a staggered panel
layout. The diaphragm shears are strength level loads. The designer has the
choice of using the ASD allowable unit shear capacities or LRFD factored
unit resistance capacities. The nominal unit shear capacities (vs) are ob-
tained from NDS Table 4.2A. The nominal capacities are converted to ASD
capacities by dividing by a factor of safety of 2.0 and are converted to
LRFD capacities by multiplying by a D factor of 0.80.
The difference between the two conversions is 1.6 and conversion in ASCE
7 is:
1
= 1 .4
0. 7
Assuming that designing for a lower level force is advantageous, this would
give a 14 percent advantage to using LRFD factored unit resistance capaci-
ties over the traditional ASD capacities. Since the loads to the diaphragms
and shear walls are already, strength level loads (from the ASCE 7 seismic
equations), it should make the designers decision rather easy to use the
LRFD factored unit resistance capacities and utilize the advantage at the
same time avoiding converting to ASD capacities.
This design example will follow the conventional approach using ASD val-
ues and the diaphragm values listed in the IBC (Tables 2306.3.1 and
2306.3.2).
At Line 4, the maximum diaphragm shear (431 plf) occurs between grid
lines C and D. Since one segment has a larger shear value, design entire
diaphragm width between grids A and F for 431 plf and not the average
force of 345 plf.
Converting to ASD:
For Load Case 2, the allowable shear for a blocked diaphragm with 3-
inch nominal framing members is 325 plf > 302 plf, therefore a blocked
diaphragm using 10d common nails (0.148 inch diameter with 1 inch
penetration in framing member) with 6-inch boundary and edge nail
spacing is adequate. Maximum nail spacing at intermediate supports
(field nailing) is 12 inches on center.
The diaphragm shear between grid lines 4 and 5 is the higher shear between
grid lines C and D. The diaphragm shear between A-C and D-F is 302 plf
(Table 2-5). The designer may choose to provide different nailing zones at
these locations.
The diaphragm shear at grid line 6 of 95 plf is the higher shear between
lines A-C and D-F, note that the diaphragm shear between C-D is 18 plf
(Table 2-5).
See section 8 of this design example for additional comments and require-
ments about diaphragm nailing, blocking, framing members and special
inspections.
The total diaphragm shears for the collector are 345 plf + 165 plf = 510 plf
(see section 3a).
Note that this design example has chosen to use the diaphragm shear value
of 345 plf and is not using the value using the reduction of 43 plf shown in
Table 2-5. The larger value has been conservatively selected for the collec-
tor design.
Since the inertial forces for the diaphragm were calculated using Eq. 12.10-
1, and there are no transfer diaphragm forces, the redundancy factor, , is
1.0.
The collector force (Figure 2-12) at 4-C, 4-D, 9-C and 9-D is:
The NDS-05 has design provisions for both ASD and LRFD for the design
of wood members. The method illustrated in this design example will be
ASD.
4b. Load Combinations for Collector Design Using ASCE7-05. 12.4.2.3
Since this building structure is in SDC B, the load combinations with over-
strength factor do not apply.
where the dead load, D, is increased for vertical accelerations by the SDS
coefficient.
Since H, F, Lr, S and R are not present on the collector, the simplified load
combinations are:
Note that for the ASCE 7-05 load combinations, the traditional one-third in-
crease for allowable stress design is no longer permitted except for the load
duration factor (CD) in NDS. However, the load combination using 0.525
QE in lieu of 0.7 QE has reduced the strength load by the same amount
resulting in designing for an equivalent force.
1
0 .7 = 0.525
1.33
As stated above, since there are no transfer diaphragm forces, the redun-
dancy factor, , is 1.0.
Where
Collector Analysis:
The diaphragm distributes a uniform force along the collector. The maxi-
mum axial force (F) in the collector is where the collector connects to the
shear wall (Figure 2-12). At this location, the moment (M) in the collector
is zero. Since the collector supports gravity loads and is a simple span beam
the location of maximum moment (M) is at the center of the collector, at
this location the collector force (F) is half the end force. An exact analysis
of the collector would entail checking the combined axial and bending
stresses at many locations where the moment (M) and the collector force
(F) are variant along the beam length. This type of collector analysis can
easily be done with a spread sheet program. Some design engineers will use
the maximum moment and the collector force at location of maximum
moment. While this may satisfy the analysis requirements for a collector
with a large moment (M) and a small collector force (F), it may be uncon-
servative for larger collector forces. For simplicity and illustrative purposes,
this design example will use the maximum collector force (F) and the
maximum moment (M) for the combined bending and axial load checks.
Alternatively, some engineers will argue that the transfer of the diaphragm
to the shear wall is assumed fully stressed and the remaining stresses (force)
are collected resulting in a nonuniform diaphragm shear stress distribution
and hence, have smaller collector forces. This would mean that the dia-
phragm is acting as a collector (and not the collector itself). This design
example will utilize the uniform shear stress distribution.
15
L = Lo 0.25 + Eq.4-1
K LL AT
15
L = 50 0.25 + = 32 psf
2 754
For Equation 5:
For Equation 6:
For Equation 8:
wl 2 655plf (29.0) 2
M= = = 68,800 f - lb
8 8
Horizontal earthquake load on collector:
Q = 15,300 lb
For Equation 6:
IBC Section 1605.3.2 has alternate basic load combinations to ASCE 7-05.
For allowable stress design, the basic load combination is:
E
D+L+S + IBC Eq.16-20
1 .4
Since S is not present on the collector, the simplified load combination is:
E
D+L+
1 .4
1,170 plf
832 plf
15 ,300 lb
F = = 10 ,930 lb
1 .4
Note that this load combination produces a higher vertical load and higher
axial force on the collector:
F = 10,930 vs 8,035 lb
These loads are IBC alternate load combination; the load combinations used
for this design example will use the ASCE7-05 ASD load combinations.
The typical floor girder is 6 3/4 x 341/2 glu-laminated beam (GLB). Try
using typical beam for collector. The equations used for the combined
loading are:
ft fb
+ * 1 .0 NDS Eq. (3.9-1)
F '
t Fb
fb ft
1 .0 NDS Eq. (3.9-2)
F **
b
2
fc fb
+ 1.0 NDS Eq. (3.9-3)
Fc ' f
Fb ' 1 c
FcE
However, since the collector connections are not concentric to the centroid
of the collector (see Figure 2-16), the collector is subjected to a combina-
tion of bending from the eccentricity and the vertical loads. The equation
for the loading condition is NDS Eq. 15.4-1:
e fc
2
f b + f c 6 1 1 + 0.234
fc d1 FcE
+ 1 .0
Fc ' f
Fb ' 1 c
FcE
where
Compression:
The collector has different unbraced lengths (see Figure 2-14) about the x
and y axes. Since E'x min and E'y min are different material properties, a full
analysis of the column stability factor (Cp) is necessary for each axis.
34.5 in.
e1 = 4.5 = 12.75 in.
2
e1 12.75 in.
= = 0.369
d1 34.5 in.
Ke1 = 1.0
l e1 = 29 12 = 348 in.
l e1
= 348 = 10.0
d1 34.5
Beam bottom edge will be braced at midspan to prevent local buckling (see
Figures 2-13 and 2-14).
Ke2 = 1.0
*
Fc = FC C D C M C t = 1,650 1.6 1.0 1.0 = 2,640 psi
FcE 7,645
* = = 2.896
Fc 2,640
F FcE
2
FcE
1 + cE * 1+ *
Fc
F c F * c = 0.953
Cp =
2c 2 c c
NDS Eq. 3.7-1
Analyze collector buckling about y (weak) axis:
*
Fc = FC C D C M C t = 1,650 1.6 1.0 1.0 = 2,640 psi
FcE 1,025
* = = 0.3883
Fc 2,640
F FcE
2
FcE
1 + cE *
Fc
1 +
F *c F * c = 0.367
Cp =
2c 2c c
NDS Eq. 3.7-1
The y axis produces the smaller value of the column stability factor; hence
the y axis is critical for column (collector) buckling.
Likewise, the y axis produces the smaller value of the critical buckling de-
sign value for compression members, FcE.
Tension:
Bending:
If the combined stress (bending plus axial compression) on the bottom edge
is tension, then CL may be assumed to be 1.0. However, if the combined
stress is compression, a bending analysis is required to determine CL.
lu = 174 inches
l u 174
= = 5 .0 < 7
d 34.5
le d
RB = < 50 max
b2
358 x34.5
RB = = 16.46 < 50 NDS Eq. 3.3-5
6.75 2
FbE 3,675
* = = 0.957
Fb 3,840
F Fb E
2
FbE
1 + bE * 1+ *
Fb
F b F * b = 0.798 1.0
CL =
1 .9 1 . 9 0.95
NDS Eq. 3.3-6
1 1 1 1 1 1
21 x 12 x 5.125 x
21 10
12 10
5.125 10
CV = = = 0.847 1.0
L d b 29 34.5 6.75
NDS Eq. 5.3-1
CL<CV
CL = 1.0
5 6 8
F (kips) 10.71 8.035 10.71
ft=fc (ksi) 0.046 0.034 0.046
Ft (ksi) 1.760 1.760 1.760
Fc (ksi) 0.970 0.970 0.970
M (ft-k) 128.3 192.3 68.8
fb (ksi) 1.150 1.723 0.617
Fb (ksi) 3.250 3.250 3.250
CL 1.0 1.0 1.0
CV 0.847 0.847 0.847
* **
Fb = Fb (ksi) 3.840 3.840 3.840
fc/FcE 0.045 0.034 0.045
Eq. 3.9-1 0.325 0.468 0.187
Interaction
Check Eq. 3.9-2 0.288 0.440 0.149
Eq. 15.4-1 0.406 0.574 0.234
Note: when fc < fb the bottom edge of the beam still remains in tension and
CL is assumed to be 1.0. However from a technical perspective, the l e /d in
the weak axis (unbraced) would be 51.6 > 50 maximum, therefore a brace
to the bottom of the beam at midspan will be added. With a brace at
midspan (Figure 2-13), the l e /d is now 25.8 < 50. Where le = (Ke)l.
Since fc < fb the value of CL = 1.0 is used with the higher value of Fb.
1. The force of 15,300 pounds must be developed into the CMU wall, and
the CMU stresses be checked to complete the connection detail.
2. Grouting of blockout pocket and treatment of jamb reinforcing steel at
wall boundary needs to be considered to complete connection detail.
3. Diaphragm cross-tie connection (if necessarysee section 5) at grid
lines C and D and connection to steel column needs to be considered to
complete connection detail.
diaphragm chords whereas the design example for Seismic Design Cate-
gory B would not require these. Since the GLB girders run north-south
across the building, these in themselves could be the continuous struts.
However, the east-west direction would require strut lines at lines C and D
(or at some other locations at the discretion of the design engineer).
The continuous tie requirement would classify the collectors at lines 4 and
9 as having to meet both requirements. Section 12.10.2.1 requires collector
elements, their splices and connections to be designed with load combina-
tions with the overstrength factor (0). This requirement is also repeated in
Section 12.14.7.3.
IBC Section 2305.1.4 states that toenail connections shall not be used in
Seismic Design Categories D, E and F when calculating transfer of lateral
forces in excess of 150 plf from diaphragm to shear walls.
Note: This section and subsequent sections are condensed versions, for am-
plification of the following, see sections 1 through 4 of this design example.
V = C sW Eq.12.8-1
S DS
Cs = Eq.12.8-2
R
I
where
I = 1.0
R = 4.0
Values for Ss and S1 can be determined from ASCE 7-05 maps or from the
USGS web site which calculates the values by either zip code or longitude
and latitude coordinates.
2 2
S DS = S MS = (1.50 ) = 1.0 Eq. 11.4-3
3 3
2 2
S D1 = S M 1 = (0.54 ) = 0.36 Eq. 11.4-4
3 3
TL = 12 sec
Figure 22-15
1.0
Cs = = 0.250
4.0
1.0
S D1 0.36
Cs = = = 0.273 Eq. 12.8-3
R 4.0
T 0.33
I 1.0
For T TL
V = 0.250W
W = 4600 k
W = 3448 k
Table 2-7. Vertical distribution of seismic forces for the north-south direction of forces
w x hx
Fx
Level w x (k) h x (ft) w x h x (k-ft)
wi hi Fx (k) Ftot (k)
wx
(%)
Roof 1126 42 47,292 39.3 452.0 0.401 452.0
3rd Floor 1737 28 48,636 40.5 465.7 0.268 917.7
2nd Floor 1737 14 24,318 20.2 232.3 0.134 1150.0
4600 120,246 100.0 1150.0
Table 2-8. Vertical distribution of diaphragm seismic forces for the north-south
direction
Minimum Code
F
Diaphragm Force
Fx
Level w x (k) w i
(k) (k )
i
F x
Fpx =
F px
(k ) Fx
w x (k )
Roof 1,126 1,126 452.0 452.0 0.401 452.0 1.00
3rd Floor 1,737 2,863 465.7 917.7 0.320 555.8 1.19
2nd Floor 1,737 4,600 232.3 1,150.0 0.250 434.3 1.86
4,600 1,150.0
Note that the Fx and Fpx values at the roof level are the same.
7. Diaphragm DesignSDC D.
434.3 1,000
f pfloor = = 17.60 psf
24,675
The uniform loads W1 and W2 in the north-south direction are computed using the
diaphragm depths.
The diaphragm shear on the east side of line 4 for Diaphragm III (and on
the west side of line 9) is:
wl 1,584(130)
V4 = R = = = 102,960 lb
2 2
102,960 lb
v= = 1,144 plf
90 ft
The diaphragm shear on the west side of line 4 for Diaphragm II (and the
east side of line 9) is:
wl 1,584(51.33)
V4 = R = = = 40,655 lb
2 2
40,655 lb
v= = 542 plf
(90 ft 15 ft )
7c. Determine Diaphragm Chord Forces at Lines A and F and Web Shears at Lines 5,
5.5, 6 and at the Center of the Diaphragm at Line 6.5 (see Figure 2-5).
At line 5:
L 130
V 5= w x = 1,584 plf 26 = 61,775 lb
2 2
61,775 lb
v5 = = 1,030 plf
60 ft
61,775 lb
v5 = = 686 plf
90 ft
M5 =
wx
(L x ) = 1,584 26 (130 26) = 2,141,568 ft - lb
2 2
M 2,141,568
F5 @ A = = = 23,795 lb = C
d 90
At line 5.5:
L 130
V 5.5 = w x = 1,584 plf 39 = 41,185 lb
2 2
41,185 lb
v 5.5 = = 686 plf
60 ft
M 5.5 =
wx
(L x ) = 1,584 39 (130 39) = 2,810,810 ft - lb
2 2
M 2,810,810
F5.5 @ A = = = 31,230 lb = C
d 90
At line 6:
L 130
V6 = w x = 1,584 plf 52 = 20,590 lb
2 2
20,590 lb
v6 = = 343 plf
60 ft
20,590 lb
v6 = = 229 plf
90 ft
M6 =
wx
(L x ) = 1,584 52 (130 52 ) = 3,212,350 ft - lb
2 2
M 3,212,350
F6 @ A = = = 35,690 lb = C
d 90
L 130
V6 .5 = w x = 1,584 plf 65 = 0 lb
2 2
M 6 .5 =
wx
(L x ) = 1,584 65 (130 65) = 3,346,200 ft - lb
2 2
M 3,346,200
F6.5 @ A = = = 37,180 lb = C
d 90
At line 7:
L 130
V7 = w x = 1,584 plf 78 = 20,590 lb
2 2
20,590
v7 = = 229 plf
90'
Table 2-9. Resultant diaphragm III chord forces and applied forces
Chord Force/Applied Force
Grid Location
With Opening
Without Opening Resultant Due to Opening
Using FTAO
The chord force values in the column Without Opening (Table 2-9) were
previously determined in Section 7c. The chord force values in the column
With Opening Using FTAO (Table 2-9) were previously determined in
Section 7d. The values in the column Resultant Due to Opening (Table 2-
9) are determined by taking the difference between the two columns.
Diaphragm Shear
(plf)
Grid Location
With Opening Resultant Due to
Without Opening
Using FTAO Opening
Statics Check:
(The slight difference in numerical results are due to rounding of the unit
shears)
Line 4:
F N S :
V 4 = 102 ,960 lb OK
Line 5:
F N S :
V 5 = 61,775 lb 61,740 lb OK
Line 6:
F N S :
V 6 = 20 ,590 lb 20 ,580 lb OK
Line 7:
F N S :
V 7 = 20 ,590 lb 20 ,580 lb OK
The maximum chord force (from Table 2-9) is 38,295 pounds. Chord forces
at lines A and F will be resisted by either steel reinforcing bars in the ma-
sonry wall or by the ledger at the diaphragm boundary.
The resultant forces at lines C and D (from Table 2-9) will need special
framing members and connectors designed to resist these forces. The
framing plans (and possibly a special detail) also need to specify a double
row of nails (fasteners) for these opening reinforcing collectors/chords.
Grid 4 to 5:
At line 4, the maximum diaphragm shear occurs between grid lines C and
D.
The diaphragm in this zone will require multiple lines of fasteners (high
load diaphragm). High load diaphragms are not listed in the NDS Special
Design Provisions for Wind and Seismic; therefore, the design engineer
must use IBC Table 2306.3.2 where values are listed in allowable values
(ASD).
Nailing zone A
Using two lines of 10d common nails (0.148 inch diameter with 11/2 inch
penetration in framing member) spaced at 21/2 inches at boundaries and 3
inches at other panel edges has an allowable shear of 1,255 plf > 1000 plf.
The joist width may need to be increased (changed) for this area. See split-
ting of framing members comments below Table 2-11.
For panel layout, load case 2 for a blocked diaphragm and Structural I
sheathing with 3-inch nominal framing members is 720 plf > 615 plf, there-
fore a blocked diaphragm using 10d common (0.148 inch diameter with 11/2
inch penetration in framing member) with 21/2 inch boundary spacing and
4-inch edge spacing at other panel edges is adequate (Nailing Zone C).
Grid 9:
For panel layout, load case 2, the allowable shear for a blocked dia-
phragm with 3-inch nominal framing members is 820 plf > 800 plf,
therefore a blocked diaphragm using 10d common nails (0.148 inch
diameter with 11/2 inch penetration in framing member) with 2-inch
boundary spacing and 3-inch edge spacing at other panel edges is adequate
(Nailing Zone B).
At some locations, nailing Zone D (480 plf) will become acceptable as the
diaphragm shears reduce farther from the diaphragm boundary. The dis-
tance between nailing zones B and D may be located as follows using ASD
allowable shears.
where
x = 26.0 ft
Since the diaphragm consists of 4-foot wide panels, the distance is in-
creased to the next 4 foot increment or x = 28.0 feet.
A similar process is done to determine the distance locations for the other
nailing zone areas of the diaphragm.
The above nailing pattern is required for seismic forces in the north-south
direction. A nailing pattern still needs to be determined for the seismic
forces in the east-west direction.
Nails are to be located at least 3/8 inch from the edges of the panels. At ad-
joining panel edges, 3-inch nominal framing members (wood I-joist, beams
and blocking) and nails are to be staggered when both conditions are met:
(1) 10d common nails (0.148 inch diameter) having penetration into fram-
ing of more than 11/2 inches and (2) nails are spaced 3 inches on center or
less.
The design engineer should consider the type of chord in the joists and the
manufacturers recommended maximum nailing to avoid splitting of the
chords. This may require special joists (or even glu-laminated beams as
joists) at areas of heavy nailing.
The design engineer should consider and specify the type of blocking mate-
rial to be used. It is recommended for this diaphragm that a blocking
material be made of engineered lumber (LVL or LSL) to avoid splitting of
the blocking members. For instance if the joist spacing is 16 inches on
center and the joist flange width is 21/2 inches, the actual length of the
blocking would only be 131/2 inches long and could receive multiple rows
of 10d nails at 2 inches on center. The shorter the length of the block and
the larger the nail diameter, the more likely the block may split.
Special inspection of diaphragm nailing and shear walls (IBC 1707.3) for
SDC C, D, E or F is required when the nail spacing is 4 inches on center or
less. Periodic special inspection is required for nailing and bolting of the
diaphragms and collectors. A higher level of special inspection is required
for high-load diaphragms (IBC 1704.6.1). Special inspection is required for
grade and thickness of wood structural panels, nominal size of framing
members at adjoining panel edges, nail diameter and length, the number of
fastener lines and the spacing between the fasteners in each line and at edge
margins agree with the approved plans (drawings must show this informa-
tion).
It should be noted that there is a code requirement for the special inspec-
tion, but at the present time, there isnt a certification available for special
inspectors in this category.
The length of the collectors is 30 feet (span length is 29.0 feet). See Figure
2-12 for similar collector framing layout.
The total diaphragm shears for the collector are 1,144 + 542 = 1,686 plf
(see section 7b).
Since the inertial forces for the diaphragm were calculated using Eq. 12.10-
1, and there are no transfer diaphragm forces, the redundancy factor is
1.0.
9a. Load Combinations for Collector Design Using ASCE 7-05. 12.4.3.2
Where the dead load, D, is increased (or decreased) for vertical accelera-
tions by the SDS coefficient.
Since H, F, Lr, S and R are not present on the collector, the simplified load
combinations with overstrength are:
0 = 2.5
For Equation 5:
For Equation 6:
For Equation 8:
QE = 50,580 lb
For Equation 6:
The typical floor girder is 63/4 x 341/2 glu-laminated beam (GLB); try using
typical beam for collector. The equations used for the combined loading
are:
ft fb
+ * 1 .0 NDS Eq. (3.9-1)
Ft ' Fb
fb ft
1 .0 NDS Eq. (3.9-2)
F **
b
2
fc fb
+ 1 .0 NDS Eq. (3.9-3)
Fc ' f
Fb ' 1 c
FcE
where
Note that the additional allowable stress increase (CD) for load combina-
tions with overstrength is permitted in section 12.4.3.3.
Compression:
The collector has different unbraced lengths (see Figure 2-14) about the x
and y axes. Since Ex min and Ey min are different material properties, a full
analysis of the column stability factor (Cp) is necessary for each axis.
Ke 1 = 1.0
l e1 = 29 x 12 = 348 in.
l e1
= 348 = 10.0
d1 34.5
Beam bottom edge will be braced at midspan to prevent local buckling (see
Figures 2-13 and 2-14).
Ke 2 = 1.0
*
FC = FC C D C M C t = 1,650 1.92 1.0 1.0 = 3,170 psi
FcE 7,645
* = = 2.412
Fc 3,170
F FcE
2
FcE
1 + cE * 1+ *
Fc
F c F * c = 0.940
Cp =
2c 2 c c
NDS Eq. 3.7-1
*
FC = FC C D C M C t = 1,650 1.92 1.0 1.0 = 3,170 psi
FcE 1,025
* = = 0.3233
Fc 3,170
F FcE
2
FcE
1 + cE *
Fc 1 +
F *c F * c = 0.309
Cp =
2c 2c c
NDS Eq. 3.7-1
The y axis produces the smaller value of the column stability factor; hence
the y axis is critical for column (collector) buckling.
Likewise the y axis produces the smaller value of the critical buckling de-
sign value for compression members FcE.
Tension:
Bending:
If the combined stress (bending plus axial compression) on the bottom edge
is tension, then CL may be assumed to be 1.0. However, if the combined
stress is compression, a bending analysis is required to determine CL.
lu = 174 in.
l u 174
= = 5 .0 < 7
d 34.5
le d
RB = < 50 max
b2
358 34.5
RB = = 16.46 < 50 NDS Eq. 3.3-5
6.75 2
FbE 3,675
* = = 0.799
Fb 4,600
F Fb E
2
FbE
1 + bE * 1+ *
Fb
F b F * b = 0.711 1.0
CL =
1 .9 1 . 9 0.95
NDS Eq. 3.3-6
1 1 1 1 1 1
21 x 12 x 5.125 x
21 10
12 10
5.125 10
CV = = = 0.847 1.0
L d b 29 34.5 6.75
CL = 1.0
5 6 8
F (kips) 88.5 66.4 88.5
ft =fc (ksi) 0.380 0.285 0.380
Ft (ksi) 2.100 2.100 2.100
Fc (ksi) 0.980 0.980 0.980
M (ft-k) 140.3 201.8 56.80
fb (ksi) 1.257 1.809 0.509
Fb (ksi) 3.900 3.900 3.900
CL 1.0 1.0 1.0
CV 0.847 0.847 0.847
* **
Fb = Fb (ksi) 4.600 4.600 4.600
fc/FcE 0.371 0.278 0.371
Eq. 3.9-1 0.454 0.529 0.292
Interaction
Check Eq. 3.9-2 0.191 0.331 0.028
Eq. 3.9-3 0.663 0.727 0.358
Note: when fc < fb the bottom edge of the beam is still in tension and CL is
assumed to be 1.0. However from a technical perspective, the le/d in the
weak axis (unbraced) would be 51.6 > 50 maximum; therefore, a brace to
the bottom of the beam at midspan will be added. With a brace at midspan
(Figure 2-13), the le/d is now 25.8 < 50, where le=(Ke)l.
Since fc < fb the value of CL = 1.0 is used with the higher value of F'b.
2. The designer must develop horizontal drag force into the CMU wall
with the proper number of bolts and check the CMU shear stress to
complete the connection detail.
3. The designer must develop the load path from the GLB to the steel
channels by the through bolts to complete the connection detail.
4. Diaphragm cross-tie connection at lines C and D at connection to steel
column needs to be considered to complete connection detail.
5. Ledger for floor framing is not shown in detail and needs to consider
possible interference with MC 10x below.
6. Floor framing into GLB is not shown and needs to consider possible
interference with MC 10x below.
References
Breyer, Donald E., Kenneth J. Fridley, David G. Pollack, Jr. And Kelly E.
Cobeen,. Design of Wood Structures ASD/ LRFD. McGraw-Hill Book Co.,
New York, NY, 2007.
Dolan, J. D. and C.P. Heine, Monotonic Tests of Wood Frame Shear Walls
with Various Openings and Base Restraint Configurations. Timber
Engineering Report No. TE-1997-001, Virginia Polytechnic Institute and
State University, Blacksburg, VA, 1997a.
Example 3
Steel Deck Diaphragm with Opening (Flexible Diaphragm)
for Seismic Design Category DFour-Story Building
Example
Overview
This design example illustrates the design of the roof diaphragm and its
components for a four-story office building structure using the provisions
of the 2006 International Building Code. Figure 3-1 shows the roof plan of
the building, and the braced-frame elevations are shown in Figures 3-2 and
3-3. The lateral system utilizes buckling restrained braced frames (BRBF)
to carry the inertial forces from the diaphragms down to the foundation.
The gravity system consists of steel columns, beams and girders. The roof
is made of bare metal deck while all of the floors are concrete fill over
metal deck. Example 3 covers the design of the untopped diaphragm at the
roof; Example 4 covers the design of the diaphragm with composite deck at
the third floor.
Note: No lateral-resisting system has been provided along gridline E for the
purpose of demonstrating cantilever diaphragm design, specifically for this
design example. A well-designed building should always have a minimum
of two lines of parallel lateral-resisting-system elements in each orthogonal
direction of the buildings footprint.
Outline
This example will illustrate the following parts of the design process:
4. Collector Design.
Given Information
Site Class B
Ss = 1.50 g
S1 = 0.624 g
TL = 12 sec.
Buckling-restrained braced frames (BRBF), nonmoment-resisting beam-
column connections
R = 7.0 ASCE 7 Table 12.2.1
o = 2.0
Roof Loading:
Dead Load = 40 psf
Live Load = 20 psf (Reducible)
Typical Floor Loading:
Dead Load = 80 psf (includes 10 psf seismic
weight for partitions) ASCE 7 12.7.2
Live Load = 50 psf (Reducible)
Exterior Cladding = 25 psf
(Accounts for floor/roof slab framing weight from perimeter beam
centerline to edge of slab)
Wroof = 977 k
W4th floor = 1953 k
W3rd floor = 1953 k
W2nd floor = 1953 k
Wtotal = 6836 k
Roof Deck:
vall = 800 plf 16 gage deck with 11/2 rib height, 4-weld pattern
per sheet to supports, with 1 top seam welds at
side laps @ 24o.c. for beam spans of 10-0
vall = 1500 plf 16 gage deck with 11/2 rib height, 7-weld pattern
per sheet to supports, with 1 top seam welds at
side laps @ 12o.c. for beam spans of 10-0
Floor Deck:
vall = 4350 plf 16 gage deck with 2 rib height, 31/4 lightweight
concrete fill, and headed shear studs at 12 o.c.
Analytical results:
Tx = 1.072 sec.
Ty = 0.940 sec.
Torsional Irregularity 1a in accordance with ASCE 7 Table 12.3-1
applies.
Torsional Irregularity 1b in accordance with ASCE 7 Table 12.3-1
does not apply.
To determine building period for minimum design base shear, the calcu-
lated periods (in the Given section) are compared to the approximate
period (Ta) which is identical in each direction:
Ta = C t (hn ) = 0.030(60)
x 3/ 4
= 0.647 sec ASCE 7 Eq. 12.8-7
V = C sW ASCE 7 Eq.12.8-1
S DS
Cs ASCE 7 Eq. 12.8-2
R
I
where
I = 1.0
R = 7.0
S s = 1.5
Fa = 1.0
ASCE 7 Table 11.4-1
Site Class B
S DS 1.00
Cs = = 0.143 (upper bound for Cs)
R 7.0
I 1.0
The lower bound value of Cs used for computing base shear must conform
to the largest of four minimum values:
S D1
Cs ASCE 7 Eq.12.8-3
R
T
I
For T TL
TL = 12
S1 = 0.624
Controls
S 0.416
C s D1 = = 0.0657
R 7.0
T 0.905
I 1.0
0.5S1
Cs = 0.0446 ASCE 7 Eq. 12.8-6
R
I
V = C sW = 0.0657(6836k ) = 448.9 k
The static base shear must be distributed to each level as a preliminary step
in determining diaphragm forces. This is done using the procedure for an
equivalent lateral force analysis, regardless of the analysis used for the de-
sign of the vertical elements of the lateral load resisting system.
k
wx hx
C vx = n
ASCE 7 Eq. 12.8-12
w h
i =1
i i
k
k
wx hx Story
k
Fx
w x (k) h x (ft) w x h x (k-ft)
w h
Level k (k) Shear
i i
Fx (k)
(%)
Roof 977 60 134,314 27 122.6 122.6
4th Floor 1953 45 189,972 39 173.5 296.1
3rd Floor 1953 30 116,665 24 106.5 402.6
2nd Floor 1953 15 50,693 10 46.3 448.9
6836 491,645 100 449
F
i=x
i
F px = n
w px ASCE 7 Eq. 12.10-1
w
i=x
i
F px , max = 0.4 S DS Iw px
F px , min = 0.2 S DS Iw px
The roof diaphragm will first be analyzed without the effects of an opening
(or openings) to determine the forces acting on it.
The maximum shear along each beam occurs at a support, and so the dia-
phragm is designed for this maximum shear. For north-south loading,
Although 12.8.4.2 does not require the inclusion of accidental torsion for
flexible diaphragms, it is recommended here that it be considered in all
cases for the same reason that it is considered for rigid diaphragms: to pro-
vide some capacity to resist load redistributions resulting from nonuniform
inelastic behavior of lateral-load-resisting elements.
For a simply supported beam a five percent offset in the centroid of the load
results in a 10 percent change in the reactions (45 percent and 55 percent in
the offset case; 50 percent and 50 percent in the centered case). Therefore,
For a cantilevered beam an offset in the centroid of the load does not affect
the shear reaction at the base at grid A. Therefore in the east-west direction,
A diaphragm is designed for unit shear, that is, it is designed for the total
shear divided by its depth. The unit shears in each direction are:
V max 107 k
v1 = v 7 = = = 0.895 klf
L1, 7 120 ft
V A 195.3 k
vA = = = 1.09 klf
LA 180 ft
The chord forces are a result of the moment imposed upon the diaphragm
by the applied distributed seismic load. This moment resolves itself in a
tension-compression couple with an arm equal to the depth of the building.
The maximum chord forces will occur at the location of maximum moment.
For North-South loading, based on the moment diagram shown in Figure 3-
6, the maximum moment occurs at the midpoint of the span at grid 4. The
chord forces, which occur in lines A and E, are calculated as follows:
wL2 2
Qe = C = T = M = 8 = 1.09 klf (180 ft) = 36.6 k
D D 8 120 ft
Figure 3-6. Simple span diaphragm moment diagram for north-south loading
For east-west loading, based on the moment diagram shown in Figure 3-7,
the maximum moment occurs at the support at grid A. The chord forces,
which occur in lines 1 and 7, are calculated as follows:
wL2 2
Qe = C = T = M = 2 = 1.63 klf (120 ft) = 65.6 k
D D 2 180 ft
Figure 3-8. Conceptual diagram of forces along a combined chord and drag beam
The primary chord forces along lines 1 and 7 increase geometrically from
grid E to grid A, as one would expect for a cantilever diaphragm with shear
resisted at the boundary (grid A). This primary chord force diagram is
shown below in Figure 3-10. However, the moment corresponding to these
chord forces is resisted by braced frames on Lines 1 and 7. These braced
frames exert their forces at C.5 and D.5 (where the braces attach to the
chord beams). At each line (Lines 1 and 7) the sum of these two braced-
frame forces is equal to the maximum chord force.
As shown in Figure 3-9 below, the location of the braced frames on grids 1
and 7 determines for each chord whether the diaphragm loading in a given
direction causes tension or compression. In Figure 3-9a, tension develops in
Line 1, the top chord of the cantilevered diaphragm. However in Figure
3-9b, which more closely resembles the design example, Line 1 goes into
compression because of the location of the reaction.
80.0
60.0
Primary Chord force
40.0
20.0
Force (kips)
-40.0
Braced-Frame Force
-60.0
-80.0
Location (ft.)
The maximum chord force occurs along lines 1 and 7 in the braced-frame
beam at grid C.5 and is 56.3 kips. The maximum chord force occurs in a
nonbraced-frame beam at grid C is 49.1 kips.
The BRBFs on each braced-frame line have equal stiffnesses, so the shears
in each frame are considered to be equal (neglecting collector axial
deformation):
195.3k
V Brace, A = = 65.1 k
3
107.4k
V Brace,1 = V brace, 7 = = 53.7 k
2
Figures 3-11 and 3-12 are the collector diagrams for loading in the east-
west and north-south directions, respectively. Minimum and maximum
forces are reported, as are forces at connections.
Collector Forces
140
120 113.9
100 97.7
80 81.4
60 65.1 65.1
Kips
48.8 48.8
40
32.6 32.6
20 16.3
0 0.0 0.0
-20 0 15 30 45 60 75 90 105 120 135 150 165-16.3
180
-40
Drag Line
Collector Forces
80
67.1
60
53.7
Qe (Kips)
40 40.3
26.9 26.9
20
13.4
0 0.0 0.0
0 15 30 45 60 75 90 105-13.4 120
-20
Drag Line (Feet)
The maximum collector force occurs at 90 feet along Line A at grid 4: 97.7
kips. The 113.9 kip force that occurs at the beam mid-span between grids 4
and 5 is neglected since the beam is part of the BRBF bay. The collector
force will be combined with the corresponding chord force acting on the
same line using the methods defined in ASCE 7 12.5. For simplicity the
maximum chord forces and collector forces are combined, although these
do not occur at precisely the same location.
At Lines 1 and 7:
C = 1.0C collector + 0.3C chord = 53.7 k + 0.3(49.1 k) = 68.4 k
At Line A:
C = 1.0C collector + 0.3C chord = 97.7 k + 0.3(36.6 k) = 109 k
The design example will show the design of one beam of the collector at
Line A. The design of other collector and chord beams is similar.
These overstrength forces correspond to the base shear calculated using the
R factor for the ductile system. They do not apply to the maximum and
minimum diaphragm forces (0.2SDSIwpx and 0.4SDSIwpx), which are inde-
pendent of the system, but they do apply to Eq. 12.10-1. Therefore, the
controlling collector design force is obtained by comparing the diaphragm
forces (considering the maximum and minimum) with the R-based collector
forces amplified by the overstrength factor . In this example the mini-
mum diaphragm force governs at all levels. The diaphragm analysis can
simply be scaled to obtain the collector force at a level of Fp corresponding
to Eq. 12.10-1 (instead of the minimum).
F px = 122.6 k
F px (min) = 195.3 k
Pu Q FP min = 109 k
122.6 k
Pu o Q FP = 2.0 109 k = 136 k
195.3 k
Pu = 136 k
Note that the collector force along this line need not exceed the adjusted
brace strengths at this level (as this is the roof level and braces receive load
only through the collector). It is given here that the adjusted brace strengths
(including appropriate overstrength factors) are reached at a collector force
of 180 kips.
The beam shown in Figure 3-13 represents the collector beam, with axial
forces as calculated above, combined with transverse loading due to the
supported beams and cladding. It will be conservatively designed for the
maximum axial force and the maximum moment acting on it. Note that
these will not actually occur at the same location along the beam. The
maximum moment occurs at the center of the beam while the maximum
axial load occurs at the end of the beam. The beam is a W24 62. Second-
order moments must be calculated for the beam.
M nt = 11.0 k 10 ft = 110 k - ft
This moment is not due to lateral translation and is magnified only by the
axial force present in the beam:
B1 = Cm AISC 360 Eq. C2-3
P
1 u
Pe
PE = 2 EA
[KL r ] 2
1.0
B1 = = 1.04
(
1 136 k
3420 k
) 2
M u = B1 M nt = 114k - ft
v1 = v 7 = 0.895 klf
v A = 1.09 klf
65.6 k
v 1Chord = v 7Chord = = 0.547 klf
120 ft
v1 = 1.0v1 + 0.3v1Chord = 0.895 klf + 0.3(0.547 klf ) = 1.06 klf
In accordance with Section 104.11 of the 2006 IBC, design values are ob-
tained from a properly certified evaluation report produced by an accredited
service. ABC-ES Report #1 for ACME Steel Deck Company specifies that
their 16 gage deck vall = 800 plf (see given information).
The capacity of the deck, based on the attachments to the supporting mem-
bers, is 1500 plf at allowable stress level; the diaphragm is OK (see given
information).
For simplicity, only the analysis of the effects of the opening in the north-
south direction will be performed, but the effects in both directions must be
considered. An opening in the diaphragm creates a concentration of forces
at the portions of the diaphragm adjacent to the opening. The unit shear
within the diaphragm is increased because there is a shorter segment of dia-
phragm to distribute the shear. At this opening, the highest unit shear is
along line 5.6 (on the north side of the opening) because this is the line
closest to a support of all of the lines affected by the opening. At line 5.6
the total diaphragm shear is computed based on the linear shear diagram
between zero shear at gird 4 and maximum shear at grid 7:
54,300 lbs
v 5.6 = = 603 plf v all
(120 ft 30 ft)
Next, the local chord forces from the portion of the diaphragm adjacent to
the opening will be analyzed. A local uniform load, equal to the weight of
that portion of the diaphragm divided by the depth of that portion, is ap-
plied to this portion of the diaphragm, as shown in Figure 3-14.
This portion of the diaphragm will be treated as a beam with fixed ends
on each side, and the resulting chord forces, which occur in lines C and E,
are
wL2
12 = (9.042 psf 30 ft ) (20 ft) = 0.3 k
2
C =T = M =
D D 12 30 ft
The addition of these local chord forces to those calculated for the dia-
phragm as a whole is negligible.
4. Collector Design.
The chord and collector forces have been determined in the diaphragm
analysis. Now the W24 62 collector will be checked for the combined ef-
fects of axial and flexural forces.
Check beam web and flanges for slenderness based on Table B4.1:
b E
= 5.97 0.38 = 9.15 AISC 360 Table B4.1
t Fy
Therefore, flanges are compact for bending and are not slender for
compression.
h E
= 50.1 1.49 = 35.88 AISC 360 Table B4.1
tw Fy
Therefore, the web is slender for compression and compact for flexure.
Buckling in the y-direction governs. Note that because the steel deck layout
(longitudinal direction of steel deck flutes) is parallel to the beam being de-
signed, it does not brace the beam. Only perpendicular beams provide
bracing in this design example. The perpendicular beams are spaced at 10
feet on center. The connection of the perpendicular beams should be de-
tailed to provide bracing of the top and bottom flanges.
The torsional buckling length equals the minor-axis buckling length; under
these circumstances torsional buckling need not be checked for an I-shaped
member as minor-axis buckling has a lower value for design strength.
kl E
= 86.96 4.71 = 113.43 AISC 360 E3
r Fy
2E
Fe = 2
= 37.85 ksi
Kl
r
Fy
Fe
Fcr = 0.658 Fy = 28.76 ksi
QF y
F
Fcr = Q 0.658 e Fy AISC 360 E7
where Q = QsQa
Aeff
Qa =
A
h E
1.49
tw f cr
E 0.34 E
be = 1.92t w 1 b
f cr h f cr
tw
In this case,
Aef = A [(h 2tf)tw be tw] = 18.2 in.2 [9.684 in.2 8.843 in.2 ]
= 17.4 in.2
17.4 in. 2
Qa = = 0.954
18.2 in. 2
Q = QsQa = Qa = 0.954
QF y
F
Fcr = Q 0.658 e Fy
Lb L p
M n = C b M p (M p 0.7 F y S x ) = 441.8k ft M p
L r Lb
The value for Cb is 1.0 for the center portion for this loading condition.
Pu 136 k
= = 0.30 0.2
Pn 461 k
Pu 8 Mu
+ 1.0 AISC 360 H1
Pn 9 M n
136k 8 114 k - ft
+ = 0.52 1.0
461k 9 441 k - ft
Therefore the W2462 can adequately resist the combination of axial and
flexural loads. The member is assumed to have adequate shear strength.
This design example will illustrate the design of a simple welded shear tab
connection, shown in Figure 3-15, to resist vertical and horizontal loads.
For forces greater than the ones used in this example, connections with
greater strength will be necessary. There are many ways to design such
connections. Refer to Steel Tips and AISC Steel Design Guides for some
examples.
Pu = 136 k
Vu = 12 .0 k (given)
Plate yielding is checked for the combined effects of shear (vertical) and
axial (horizontal) forces. The axial force also causes an eccentric moment in
the weak axis of the plate due to the offset between the centerline of beam
web and centerline of shear plate.
2 2
Vu P 8 Mu
+ u + 1.0
V n Pn 9 M n
KL 1.0 3 in. E
= = 20.8 4.71 = 133.68
r 1 in. Fy
2
12
2E
Fe = 2
= 663 ksi
KL
r AISC 360 J4
Fy
Fcr = 0.658 Fe F y = 48 .4 ksi
1 in.
M u = Pu t = 136 k 2 = 34 .0 k - in.
2 2
M n = d t
2
Fy
(1 in.)
= 0.9 21 in . 2
2
50 ksi = 59 .1 kip - in .
4 4
2 2 2 2
Vu P 136 k 8 34 .0 k in .
=
12 k
+ u + + = 0.66 1.0
V n Pn 315 k 458 k 9 59 .1 k in.
2 2
Vu Pu
+ 1.0
V n Pn
[ (
Anet = 1 in. 21 in. 7 3 in. + 1 in. 1 = 7.44 in. 2
2 4 8 2
) ]
V n = 0.6 Fu Anet = 0.75 0.6 65 ksi 7.44 in. 2 = 218 k
2 2 2 2
Vu Pu
=
12 k 136 k
+ + = 0.14 1.0
V n Pn 218 k 363 k
2 2
Vu + Pu = 12 2 + 123 2 = 137 k
AISC 360 Eq. J3-1
The beam web controls over the shear plate because tpl = 1/2 in. > tbw =
0.430 in.
1
(
1.2 Lc = 1.2 2 in. 3 in. + 1 in. = 1.875 in.
2 4 8
)
2.4d b = 2.4 3 in. = 1.8 in. < 1.2 Lc
4
Therefore bearing controls:
Block Shear:
Block shear is checked in accordance with Section J4.3 of the 2005 Specifi-
cation for Structural Steel Buildings. Because the axial force is so large
compared to the shear force, block shear in the vertical direction can be
neglected, and block shear will be checked for the horizontal direction only.
Also, because the shear tab is thicker than the beam web, the beam web will
govern for block shear. Failure planes for the block-shear limit state are
shown in Figure 3-16.
where
therefore
1
(
Anv = 0.430 in. 2 2 in. 3 in. + 1 in. = 1.34 in. 2
2 4 8
)
[ (
Ant = 0.430 in. 6 3 in. 3 in. + 1 in. = 5.48 in. 2
4 8
)]
Agv = 2 0.430 in. 2 in. = 1.72 in. 2
The shear plate connection is therefore adequate to resist the required col-
lector force. Note that the calculations are simplified by the fact that the
shear is quite small compared to the collector force. Where the shear is
significant, the block-shear calculations must take this into account. See
Astaneh (2005) for a more detailed method.
References
Astaneh-Asl, A., Design of Shear Tab Connections for Gravity and Seis-
mic Loads, Steel Technical Information and Product Report. Structural
Steel Educational Council, CA, 2005.
Example 4
Steel Deck with Concrete Fill Diaphragm for
Seismic Design Category DFour-Story Building Example
Overview
This design example illustrates the design of the floor diaphragm with steel
framing members and composite metal deck. It is a continuation of the de-
sign of the building in Design Example 3. In this example the design of the
third-floor diaphragm will be addressed.
Outline
This example will illustrate the following parts of the design process:
1. Diaphragm Analysis.
4. Diaphragm Design.
5. Collector Design.
Given Information
From Example 3, Fp = 391.0 k (the force from Eq. 12.10-1 is 161 kips, but
the minimum of 0.2 SDSIwpx governs). The redundancy factor, , is equal to
1.0 in accordance with 12.10.1.1 because the inertial forces were
calculated in accordance with Equation 12.10-1.
(calculated by dividing the seismic force by the floor area) multiplied by the
depth of the diaphragm.
The maximum shear along each beam occurs at a support, and so the dia-
phragm is designed for this maximum shear. For north-south loading,
centered case). In other, more typical cases, the increase due to torsion can
be calculated using a rigid-diaphragm analysis; the 10 percent increase is
the upper bound when frames are at the diaphragm boundaries (that is, the
increase is 10 percent when orthogonal frames do not provide torsional
resistance and is less when they do). Therefore,
For a cantilevered beam an offset in the centroid of the load does not affect
the reaction. Therefore in the east-west direction,
A diaphragm is designed for unit shear, that is, it is designed for the total
shear divided by its depth. The unit shears in each direction are:
Vmax 215 k
v1 = v7 = = = 1.79 klf
L1, 7 120 ft
V A 391 k
vA = = = 2.17 klf
L A 180 ft
Chord forces are determined similar to Design Example 3. For a more thor-
ough discussion of the analysis see that example.
wL2 2
Qe = C = T = M = 8 = 2.172 klf (180 ft) = 73.3 k
D D 8 120 ft
Figure 4-6. Simple span diaphragm moment diagram for north-south loading
For east-west loading, based on the moment diagram shown in Figure 4-7,
the maximum moment occurs at the support at grid A. The chord forces,
which occur in lines 1 and 7, are calculated as follows:
wL2 2
Qe = C = T = M = 2 = 3.258 klf (120 ft) = 130 k
D D 2 180 ft
160.0
140.0
120.0
100.0 Primary Chord force
80.0
60.0
40.0
Force (kips)
20.0
0.0 Net Chord Force
-20.0 0 15 30 45 60 75 90 105 120
-40.0
-60.0
-80.0
-100.0 Braced-Frame Force
-120.0
-140.0
-160.0
Location (ft.)
Figure 4-8. Chord force diagram along lines 1 and 7 (between Grids E and A)
The maximum chord force occurs along lines 1 and 7 in the braced-frame
beam at grid C.5 and is 113 kips. The maximum chord force occurs in a
nonbraced-frame beam at grid C is 98.3 kips.
The BRBFs on each braced-frame line have equal stiffnesses, so the shears
in each frame are considered to be equal (neglecting collector axial
deformation):
391 k
Vbrace, A = = 130 k
3 bays
215 k
Vbrace,1 = Vbrace, 7 = = 113 k
2 bays
Figures 4-9 and 4-10 are the collector diagrams for loading in the east-west
and north-south directions, respectively.
Collector Forces
250
228.1
200 195.5
162.9
150
130.3 130.3
Kips
Collector Forces
150
134.4
100 107.5
Qe (Kips)
75.6
50 53.8 48.8
21.9
0 0.0
-10.0
0 15 30 45 60 75 90 105 120
-36.9
-50
Drag Line (Feet)
The maximum collector force occurs at 90 feet along Line A at grid 4: 195
kips. The collector force will be combined with the corresponding chord
force acting on the same line using the methods defined in ASCE 7 12.5:
At Lines 1 and 7:
C = 1.0C collector + 0.3C chord = 107 k + 0.3(98.3 k) = 136 k
At Line A:
C = 1.0C collector + 0.3C chord = 195 k + 0.3(73.3 k) = 217 k
The design example will show the design of one beam of the collector at
Line A. The design of other collector and chord beams is similar.
These overstrength forces correspond to the base shear calculated using the
R factor for the ductile system. They do not apply to the maximum and
minimum diaphragm forces (0.2SDSIwpx and 0.4SDSIwpx), which are inde-
pendent of the system, but they do apply to Eq. 12.10-1. Therefore, the
controlling collector design force is obtained by comparing the diaphragm
forces (considering the maximum and minimum) with the R-based collector
F px = 161k
F px (min) = 391k
Pu Q FP min = 217 k
161 k
Pu o Q FP = 2.0 217 k = 177 k
391 k
Pu = 217 k
Note that unlike in Design Example 3 the collector force along this line
cannot be determined from the adjusted brace strengths at this level. The
braced-frame strength will be well in excess of the collector force because
braces are sized for the story shear, which far exceeds the story force except
at the roof.
The beam shown in Figure 4-12 will be conservatively designed for the
maximum axial force and the maximum moment acting on it. Note that
these will not actually occur at the same location along the beam. The
maximum moment occurs at the center of the beam while the maximum
axial load occurs at the end of the beam. The beam is assumed to be a
W24 62 acting compositely with the 2-inch deck and 3-inch fill.
The concrete flange on the exterior is 6 inches. The effective flange on the
interior is limited by:
Therefore
V' = 0.85 f 'c A c = 0.85 (3 ksi)(55 in.)(3.25 in.) AISC 360 EQ. I3-1a
= 456 kips
The deck area includes the topping only; a marginal increase can be ob-
tained considering the area of concrete in the ribs.
Sufficient shear studs will be placed on the beam to transfer this force.
These will be supplemented by studs necessary to transfer diaphragm shear.
The shear stud capacity is calculated in accordance with Section I1g of the
2005 Specification for Structural Steel Buildings. Figure 4-11 below shows
a section through a composite beam.
Asc =
3
4
(4
2
)
in. = 0.44 in. 2
1 .5
E c = wc f ' c = (115pcf )1.5 3 ksi = 2136 ksi
Rg = 1.0 for deck parallel with wr/hr=3.5 in./2 in. = 1.75 > 1.5
Rp = 0.75 for deck parallel with wr/hr=3.5 in./2 in. = 1.75 > 1.5
Fu = 65 ksi
Q n = 0.5 0.44 in. 2 3 ksi 2136 ksi 1.0 0.75 0.44 in. 2 65 ksi
= 17.6 k 21.5 k
First compare the steel tension strength with the concrete compression
strength calculated above.
T = A s Fy = 910 kips
Because T > C, the plastic neutral axis is located in the beam and not in the
slab. Assume the plastic neutral axis falls in the flange of the steel beam.
Calculate the distance x from the top of the flange to the plastic neutral axis
by setting compression equal to tension:
0.85 f ' c be t + Fy b fl x = Fy As Fy b fl x
0.85 3 ksi 51 in. 5.25 in. + 50 ksi 7 in. x = 50 ksi 18.2 in. 2
50 ksi 7 in. x
x = 0.354 in.
x tf
Therefore the plastic neutral axis is in the beam flange, as assumed.
M n = 0.85 f ' c be t (t / 2 + x ) + 2 F y b fl x( x / 2) + Fy As (d / 2 x )
Mp = 984 kip-ft
The load factor for live load is 0.5 because Lo is less than 100 psf.
M nt = 25.8k 10 ft = 258k - ft
This moment is not due to lateral translation and is magnified only by the
axial force present in the beam:
Cm
B1 = P
1 u
Pe
2 EA
2 EI
PE = ( )
KL
r
2 =
(KL )2
2 (29,000 ksi)(2905 in 4 )
PE = = 6415 kips
(360 in )2
1.0
B1 = = 1.04 AISC 360 Eq. C2-3
(
1 217 k
6415 k
)2
M u = B1 M nt = 268 k ft
4. Diaphragm Design.
Vmax 215 k
v1 = v 7 = = = 1.79 klf
L1, 7 120 ft
V A 391 k
vA = = = 2.17 klf
L A 180 ft
130 k
v1Chord = v 7 Chord = = 1.08 klf
120 ft
v1 = 1.0v1 + 0.3v1Chord = 1.79 + 0.3(1.08 klf ) = 2.11 klf
In accordance with Section104.11 of the 2006 IBC, design values are ob-
tained from a properly certified evaluation report produced by an accredited
service. ABC-ES Report #1 for ACME Deck Company specifies that their
16 gage deck with 2-inch rib height with 3 1/4-inch lightweight concrete fill
with shear studs at 16 inches o.c. has vall=4350 plf.
Neither ASCE 7 nor AISC 341 require shear studs to be designed for the
amplified seismic load (which includes the overstrength factor o ), but it is
good practice to do so because of the limited ductility of this connection.
Thus the seismic shear required to be resisted by the studs within this span
is:
5. Collector Design.
The flexural strength of the collector has been calculated previously in the
determination of collector forces.
Check beam web and flanges for slenderness based on Table B4.1:
b E
= 5.97 0.38 = 9.15 AISC 360 Table B4.1
t Fy
h E
= 50.1 1.49 = 35.88 AISC 360 Table B4.1
tw Fy
Note that because the composite deck provides bracing against minor-axis
flexural buckling. It does not, however, fully restrain torsional buckling. In
most cases the torsional buckling length equals the minor-axis buckling
length; under these circumstances it is common to calculate the minor-axis
buckling strength in lieu of the more complicated torsional-buckling equa-
tions. In this example torsional buckling is checked explicitly and compared
to the major-axis compressive buckling stress.
For torsion,
2 EC w 1
FE = + GJ AISC 360 E4
(K z l ) I x + I y
2
kl E
= 39.0 4.71 = 113.43
r Fy
2 E
Fe = 2
= 188ksi
kl
r
Fy
Fe
Fcr = 0.658 Fy = 37.1 ksi AISC 360 E3
Consider slenderness effects:
QF y
F
Fcr = Q 0.658 e Fy AISC 360 E7
where Q = QsQa
Aeff
Qa =
A
h E
1.49
tw f cr
E 0.34 E
be = 1.92t w 1 b
f cr h f cr
tw
In this case,
h
= 47.4
tw
E 29,000 ksi
1.49 = 1 .4 9 = 41.7
f cr 37.1 ksi
16.6 in. 2
Qa = = 0.910
18.2 in. 2
QFy
F
Fcr = Q 0.658 e Fy = 34.7 ksi
Pn = Fcr Ag = 0.9 34.7 ksi 18.2 in. 2 = 568 k
Pu 217 k
= = 0.38 0.2
Pn 568 k
Pu 8 Mu
+ 1.0 AISC 360 H1
Pn 9 M n
217 k 8 268 k - ft
+ = 0.61 1.0
568 k 9 1058 k - ft
Therefore the W2462 can adequately resist the combination of axial and
flexural loads. The demand-to-capacity ratio would have been calculated to
be approximately 10 percent higher had minor-axis buckling been used in
lieu of torsional buckling. The member is assumed to have adequate shear
strength.
References
McCormac, J., Structural Steel Design (4th Edition). Prentice Hall, Upper
Saddle River, NJ (2007).
Badri K. Prasad
Douglas S. Thompson
Doug received his BS degree from Cal Poly-San Luis Obispo in 1976
and is a partner at STB Structural Engineer in Lake Forest, California.
He is a registered SE in California, Arizona and Nevada, the author of
three design examples in the Structural/Seismic Design Manual, and a
coauthor of timber manuals for license review classes for the
Professional Engineer and Structural Engineer license exams. He also
teaches timber design. Mr. Thompson is a past director of the SEAOSC
and is a past chair of the SEAOSC Code Committee, and has been
involved with code changes to the UBC and IBC for over 20 years.
Rafael Sabelli
STRUCTURAL MUST-HAVES
FROM ICC
Full color
Hundreds of drawings and figures
CD-ROM INCLUDED!
2006 IBC HANDBOOK: STRUCTURAL PROVISIONS
The updated bestseller with expanded, detailed, and in-depth discussion.
Authors S.K. Ghosh, Ph.D.; R. Chittenden, S.E.; and ICC code expert John Henry, P.E., discuss Chapters 1623 of the IBC.
The new edition of the popular Handbook offers expanded, completely detailed, and in-depth discussion; contains valuable
commentary; traces the historical background and rationale of codes; and clarifies the application and intent of the code
provisions. Its easy-to-reference layout follows the order of the code for your convenience. A bonus CD-ROM contains the
complete Handbook, numerous FEMA documents, and CodeMaster: Seismic Design.
#4001S06
Copyright 2009 NCSEA. ALL RIGHTS RESERVED. Accessed by Kevin Kirkland on May 28, 2016 11:35:44 AM pursuant to License Agreement with NCSEA. No further
reproduction or distribution authorized. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE
LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
CD-ROM INCLUDED!
EARTHQUAKE ENGINEERING: THEORY AND IMPLEMENTATION, SECOND EDITION
A modern discussion of the theoretical and practical sides of engineering.
Author Nazzal Armouti, Ph.D., P.E., documents his quarter century of engineering experience. The books first part is
theoretical and discusses the nature of earthquakes and the dynamic aspects of their effect on structures. The second part
treats, in detail, the design aspects of earthquake-resistant structures (both buildings and bridges) within the scope of seismic
provisions of the latest IBC, ACI, AISC, and AASHTO codes. The third part tackles special topics pertinent to the safety of
structures under seismic excitations such as geotechnical aspects, foundations, synthetic earthquakes, and seismic isolation.
The book is rich in illustrations and examples that make the design concepts easy to follow. Its discussion of theoretical as
well as practical sides of the subjects will benefit graduate and advanced undergraduate-level students, as well as practicing
professionals. A bonus CD contains the text, numerous FEMA documents, and CodeMaster: Seismic Design. (550 pages)
#4035S2
CD-ROM INCLUDED!
PERFORMANCE-BASED PLASTIC DESIGN: EARTHQUAKE-RESISTANT STEEL STRUCTURES
The first practical design book for the structural engineer using the new Performance-Based Plastic Design (PBPD) method.
This innovative design guide discusses the Performance-Based Plastic Design (PBPD) method for earthquake-resistant steel
structures recently developed by authors Subhash C. Goel and Shih-Ho Chao and their associates. PBPD is a direct design
method that produces final designs requiring no or minimal iteration, as opposed to what is generally required in current
practice. The PBPD method produces structures with targeted and predictable response in a direct manner.
The text is filled with formulas, tables, and drawings to assist the practicing engineer as well as the graduate student in
understanding this highly technical, yet innovative and effective, design method. Detailed examples assist with understanding
the process. A bonus CD-ROM is included that contains the complete text, as well as numerous FEMA and AISC documents.
#7032S
Copyright 2009 NCSEA. ALL RIGHTS RESERVED. Accessed by Kevin Kirkland on May 28, 2016 11:35:44 AM pursuant to License Agreement with NCSEA. No further
reproduction or distribution authorized. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE
LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.