Maintenance Schedule for Substation Equipments.

1) Circuit Breakers

Sl No Activity Period

1 Cleaning of Poles, Checking of Terminal Connections M

2 C.B. Opening Timings Y

3 Contact Resistance Y

4 Contact Travel, Contact Speed, etc Y

5 Checking of Pole Discrepancy, Relay Y

6 Functional Check, Duty Cycle Operation, including re- Y


closing

7 Checking of lock-outs Y

8 Checking of inter-locks Y

9 Cleaning of breaker interrupter, grading, capacitors, etc. Y

10 Checking close / trip coil currents Y

11 Checking Operation Counter Y


12 Capacitance and tan delta measurement of capacitors Y

13 Checking of Marshalling kiosk, door sealing, gaskets, Y


space heaters, repainting of kiosk, etc.

14 Checking tightness of cable terminations HY

1. Cleaning of insulator, Checking of terminal M


connection tightness, etc.

2. IR value measurement, Polarisation Index, Die- Y


electric Absorption Test

3. Measurement of Tan Delta and Capacitance (if 2Y


test tap is provided)

4. Measurement of CT Secondary resistance Y

5 Magnetisation Characteristics Y

6 CT Ratio Test Y

7 Testing of parameters of oil (if not hermetically 2Y


sealed)

8 Checking of Marshalling Kiosk, healthiness of M


gaskets, space heater,

9 Checking tightness of connections including Y


earthing, repainting of kiosk etc.

Sl No Activity Period
1. Cleaning of insulator, Checking of terminal M
connection tightness, etc.

2. Checking of earthing terminal of primary neutral M


point

3. IR value measurement, Polarisation index, Die- Y


electric Absorption Test

4. Ratio Test Y

Sl No Activity Period

5 Testing of parameters of oil (if not hermetically 2Y


sealed)
6 Checking of Marshalling Kiosk, healthiness of M
gaskets, space heater
7 Checking tightness of connections including Y
earthing, repainting of kiosk etc.

Sl No Activity Period

1. Checking of earthing of HF point (if CVT is not M


used for PLCC)

2. Checking of bushing, Oil leakage, if any etc. M

3. Checking of terminal connection tightness, etc. M

4. Measurement of Tan Delta and capacitance (if 2Y


test tap is provided)

5. Measurement of voltages at metering points, and M


at CVT terminals
Sl No Activity Period

6 Thermo-vision scanning of Capacitor stacks Y

7 Testing of BDV of Oils 3Y

8 Checking of Marshalling Kiosk, healthiness of M


gaskets, space heater

9 Checking tightness of connections including Y


earthing, repainting of kiosk etc.

Sl No Activity Period

1 Cleaning of support insulators and checking of M


terminal connections

2 Checking of Mechanical linkage system Y

3 Checking of stopper bolts Y

4 Cleaning of auxiliary switch contacts, greasing HY


with silicon grease
5 Checking of Electrical / Mechanical inter-locks HY

6 Lubricating of operating mechanism, hinges, HY


bearings, etc.

7 Cleaning and lubricating of main contacts HY

8 Checking of alignment of blades HY

Sl No Activity Period

9 Main and Earth Switch contact resistance Y


measurement

10 Tightening of bolts, nuts, pins etc. HY

11 Checking and alignment of earthing blades HY

12 Checking of flexible connection of earth HY


switch

Sl No Activity Period
13 Checking of Space Heaters HY

14 Checking of healthiness of gaskets of HY


Marshalling kiosks

15 Checking of earthing connections of structure M


parts,Operating handle, etc.

Sl No Activity Period

1. Checking of leakage current by current analyser Y

2. Testing of Counters Y

3. Cleaning of insulators, checking of tightness of M


terminals, earthing connections

1. Measurement of station earth resistance. M

2. Cleaning of insulators in buses, checking for any HY


cracks

3. Checking of terminal connections, jumper HY


connections, etc.
4 Switch yard de-weeding (More frequently if HY
required)

5 Rust removal of structures, equipment,etc. and 2Y


repainting

6 Checking of switch yard lighting system. HY

Sl No Activity Period

1 Leakage of Oil HY

2 Over heating HY

3 Tightness, corrosion and breakages of HY


connections

4 Condition of Bushing HY

5 Condition of container / body HY

6 Condition of discharge resistance HY

Sl No Activity Period

1 Cell voltage of Pilot Cells D

2 Specific gravity of Pilot Cells D

3 Cell voltage of all cells M

4 Specific gravity of all cells M

5 Check for any excessive gassing (Over heating D


of cells)
Sl No Activity Period

6 Battery earth leakage D

7 Battery cleaning to remove dust accumulated W

8 Tightening of terminal bolts, applying contact M


grease
9 Capacity measurement Y

Sl No Activity Period

1 Calibration of energy meters HY

2 Checking of multiplication factors with respect to HY


CT & VT ratios

3 Testing and calibration of Ammeters, Volt meters, HY


Watt meters, Var meters

4 Testing of Power factor meters, frequency meters HY

5 Checking of Ammeter selector switches HY

6 Testing of Semaphores HY

7 Testing of switches HY

Sl No Activity Period

1 Effectiveness of earth connection of various M


equipment neutrals
2 Effectiveness of earth connection of M
structures and metallic bodies

3 Measurement of earth resistance M

4 Checking for corrosion of earthing 2Y


materials, connections, welding joints (To
the extent possible

5 Watering of Plate earthing and pipe


earthing locations (As required)

Sl No Activity Period

1 Checking of meters, switches, contacts, M


terminals, etc.

2 Checking of earth connection of metallic M


body

Maintenance of Substations
Circuit breakers
Circuit Breakers Contd.
Current Transformers
Current Transformers Contd.
Voltage Transformers
Voltage Transformers Contd.
Capacitance Voltage Transformers
Capacitance Voltage Transformers
Isolating Switches
Isolating Switches Contd.
Isolating Switches Contd.
Isolating Switches Contd.
Lightning Arresters
Switchyard
Switchyard
Capacitor Banks
Station Battery
Station Battery
Meters and Instruments
Meters and Instruments
Earthing
LT Panels , DC Panels, battery Charger
Power Cables
Control Cables
Substation Building
Fire Protection System
INSTALLATION GUIDE
Drying out
By drying out the transformer, the Insulation resistance of the windings and
the BDV of the oil are improved.
All newly erected transformers (including re-erected old ones) shall be dryed
out properly before energisation.
General practice is to circulate hot oil in the transformer with an oil filter
incorporating oil heaters and vaccum chamber.

Maintenance Schedule for Substation Equipments.

1) Circuit Breakers

Sl No Activity Period

1 Cleaning of Poles, Checking of Terminal Connections M

2 C.B. Opening Timings Y


3 Contact Resistance Y

4 Contact Travel, Contact Speed, etc Y

5 Checking of Pole Discrepancy, Relay Y

6 Functional Check, Duty Cycle Operation, including Y


re-closing
7 Checking of lock-outs Y

8 Checking of inter-locks Y

9 Cleaning of breaker interrupter, grading, capacitors, etc. Y

10 Checking close / trip coil currents Y

11 Checking Operation Counter Y

12 Capacitance and tan delta measurement of capacitors Y

13 Checking of Marshalling kiosk, door sealing, gaskets, Y


space heaters, repainting of kiosk, etc.
14 Checking tightness of cable terminations HY

2) Current Transformers .

Sl No Activity Period
1. Cleaning of insulator, Checking of terminal M
connection tightness, etc.

2. IR value measurement, Polarisation Index, Die- Y


electric Absorption Test
3. Measurement of Tan Delta and Capacitance (if 2Y
test tap is provided)

4. Measurement of CT Secondary resistance Y

5 Magnetisation Characteristics Y

6 CT Ratio Test Y

7 Testing of parameters of oil (if not hermetically 2Y


sealed)

8 Checking of Marshalling Kiosk, healthiness of M


gaskets, space heater,

9 Checking tightness of connections including Y


earthing, repainting of kiosk etc.

3) Voltage Transformers.

Sl No Activity Period

1. Cleaning of insulator, Checking of terminal M


connection tightness, etc.

2. Checking of earthing terminal of primary neutral M


point
3. IR value measurement, Polarisation index, Die- Y
electric Absorption Test

4. Ratio Test Y

5 Testing of parameters of oil (if not hermetically 2Y


sealed)
6 Checking of Marshalling Kiosk, healthiness of M
gaskets, space heater
7 Checking tightness of connections including Y
earthing, repainting of kiosk etc.

4) Capacitor Voltage Transformers.

Sl No Activity Period
1. Checking of earthing of HF point (if CVT is not M
used for PLCC)

2. Checking of bushing, Oil leakage, if any etc. M

3. Checking of terminal connection tightness, etc. M

4. Measurement of Tan Delta and capacitance (if 2Y


test tap is provided)

Sl No Activity Period

5 Thermo-vision scanning of Capacitor stacks Y

6 Checking of Marshalling Kiosk, healthiness of M


gaskets, space heater
7 Checking tightness of connections including Y
earthing, repainting of kiosk etc.

8. Measurement of voltages at metering points, and M


at CVT terminals

5) Isolating Switches

Sl No Activity Period

1 Cleaning of support insulators and checking of M


terminal connections

2 Checking of Mechanical linkage system Y

3 Checking of stopper bolts Y

4 Cleaning of auxiliary switch contacts, greasing HY


with silicon grease

Sl No Activity Period

5 Checking of Electrical / Mechanical inter-locks HY

6 Lubricating of operating mechanism, hinges, HY


bearings, etc.

7 Cleaning and lubricating of main contacts HY


8 Checking of alignment of blades HY

9 Main and Earth Switch contact resistance Y


measurement
10 Tightening of bolts, nuts, pins etc. HY

11 Checking and alignment of earthing blades HY

12 Checking of flexible connection of earth switch HY

13 Checking of Space Heaters HY

14 Checking of healthiness of gaskets of HY


Marshalling kiosks
15 Checking of earthing connections of structure M
parts,Operating handle, etc.

6)Lightning Arrester
Sl No Activity Period

1. Checking of leakage current by current Y


analyser

2. Testing of Counters Y

3. Cleaning of insulators, checking of M


tightness of terminals, earthing
connections

7)Switch Yard

Sl No Activity Period
1. Measurement of station earth resistance. M

2. Cleaning of insulators in buses, checking HY


for any cracks
3. Checking of terminal connections, jumper HY
connections, etc.
4 Switch yard de-weeding (More frequently HY
if required)
5 Rust removal of structures, equipment, 2Y
etc. and repainting
6 Checking of switch yard lighting system. HY

8)Capacitor Bank.

Sl No Activity Period
1 Leakage of Oil HY
2 Over heating HY
3 Tightness, corrosion and breakages of HY
connections
4 Condition of Bushing HY
5 Condition of container / body HY
6 Condition of discharge resistance HY

9) Station Battery.

Sl No Activity Period

1 Cell voltage of Pilot Cells D

2 Specific gravity of Pilot Cells D


3 Cell voltage of all cells M
4 Specific gravity of all cells M
5 Check for any excessive gassing (Over D
heating of cells)

6 Battery earth leakage D

7 Battery cleaning to remove dust W


accumulated
8 Tightening of terminal bolts, applying M
contact grease
9 Capacity measurement Y

10) Meters

Sl No Activity Period

1 Calibration of energy meters HY


2 Checking of multiplication factors with HY
respect to CT & VT ratios

MAINTENANCE OF SUBSTATION EQUIPMENT


Important Notice Boards
to be maintained at substations.
1. Substation Name Board
2. Prohibited Area Notice Board with GO No.
Maintenance Schedule.
4. Single Line diagram.
List of Authorised Persons.
6. Station Statistics.
Grid Map.
First Aid, Fire protection etc. Guides
MAINTENANCE OF SUBSTATION EQUIPMENT
Important Registers and Records
to be maintained at substations
A. To be always available with operators:
Operators Diary. 2. Attendance Register.
Operating Instructions. 4. Daily Log Sheet / Log Book.
Battery Maintenance Register. 6. Permit to Work Book.
7. Phone message book. 8. Telephone call register.
Shift Duty Posting Register. 10. Interruption Register.
11. Inspection Register. 12. Energry Meter reading register.
13. Copies of all essential drawings.
14. Copies of Manuals of Equipment.
MAINTENANCE OF SUBSTATION EQUIPMENT
Important Registers and Records
to be maintained at substations
B. Station Engineer to maintain:

1 Equipment Register. 2. Asset Register.


3. Materials Register. 4. T & P Register.
5. Fixed Charge Register. 6. Register of Drawings & Manuals.
7. M Book Register. 8. Equipment Maintenance Register.
9. Daily Maintenance Register. 10.Maintenace Schedule Register.
11. Fire Extinguisher Register. 12. Casual Leave Register.
13. Case study Register.
Complete set of Drawings, Manuals, Wiring Schedule, Wiring Diagrams etc. shall be
perfectly maintained.

Sl No Activity Period
3 Checking of Ammeter selector switches HY

4 Testing of Semaphores HY

5 Testing of switches HY
6 Testing and calibration of Ammeters, Volt HY
meters, Watt meters, Var meters
7 Testing of Power factor meters, frequency HY
meters

11) Earthing System

Sl No
Activity
Period
1
Effectiveness of earth connection of various equipment neutrals
M
2
Effectiveness of earth connection of structures and metallic bodies
M
3
Measurement of earth resistance
M
4
Checking for corrosion of earthing materials, connections, welding joints (To the
extent possible
2Y
5
Watering of Plate earthing and pipe earthing locations
(As required)