MINUTES OF MEETING FILE NAME: QLASSIC

M.O.M. NO : QLASSIC MEETING

PROJECT TITLE:
CADANGAN PEMBANGUNAN SATU (1) BLOK PEJABAT 92 TINGKAT DAN
LIMA TINGKAT (5) TINGKAT PEJABAT ANNEX YANG MENGANDUNGI: SATU ISSUE DATE:28.06.2017
TINGKAT RETAIL / KOMERSIL DI TINGKAT LG, LAPAN TINGKAT TEMPAT
LETAK KERETA DI TINGKAT BAWAH TANAH P6 HINGGA LG MEZZANINE.

PREPARED BY : Nethiyaa
DATE OF MEETING: TIME: PLACE OF MEETING:
23.06.2017 10.30 am CHINA STATE CONSTRUCTION
MEETING ROOM, Jalan Tun Razak,
Kuala Lumpur.

NO DESCRIPTION ACTION

Mr. Wong Yew Peng chaired the meeting.

Mr.Murali from the CIDB QLASSIC department was welcome by the


chairperson.

1 The chairperson introduces the member present during the meeting. INFO

The agenda of the meeting is as below:


Introduction/opening about QLASSIC and Signature Tower Project
Inspection of mock up unit
Closing on the inspection

1.1 The inspection of mock up unit Level 5 and 6 started at about 10.45am. CIDB

CIDB informed that the criterias constraint to be complied in order to obtain a


1.2 CSCEC/MULIA
good score.

2.0 Design Matters

CIDB point out the area that could obtain easy score for the inspection that will
2.1 CIDB
conduct at the end of project completion.
2.2 The items that are stressed out during the inspections are as below: INFO
a) Wall
- alignments to be inspected
- to check if any hollow present
- ensure the wall is not dented
b) Columns
- Check on alignment
- Ensure the columns are even
- Tolerance accepted for the columns angle 300 for 4mm
- Ensure the columns are clean and free from dirt/dust
c) Ceiling
- Ensure the ceiling installed has no any hand prints on the
ceiling panel
- Alignments to be checked
- Tolerance
d) Door
- Ensure the door is not dented
- Ensure door is in good condition
- The knobs used ensure it is from good quality and function
ability.
- The door knob is not rusty and all the screws are in place
e) Toilets/Facilities

Page 1/2
- Ensure the toilets has the designated space
- Ensure disabled toilets are more spacious than the normal
toilet.
f) M& E works
- Basic M&E works which comprises of sockets
- Must be properly sealed
- No visible damaged to the sockets
- Ensure no paint drop from the socket
- Ensure the function ability of the socket
- Face plate to properly tucked in
- Ensure no gaps visible around the socket installation.

g) External Facade
- No issues
h) Roofing
- Ensure the roof is either in landscape design or filled with
artificial stones
- Gondola- metal floor as finishing
- Avoid water ponding
- Gradients

i) Road & Drainage


- Ensure road signage is clear
- Good lighting

The CIDB score are based on the percentage of principal, services and
2.3 INFO
circulation.
The percentage of each floor will be based on 60% principal area(retail, office),
2.4 INFO
25% of service areas(washrooms,etc) and 15% circulation area.
CIDB informed that, the scores would be submitted within a week based on the
2.5 CSCEM/MULIA
progress of mock unit inspected.

3.0 Adjournment

Meeting adjourned at 12.00pm

Prepared by;

Nethiyaa Rajendran

Page 2/2