You are on page 1of 14

PROJECT:

SUBJECT:

ITEM NO. SCOPE OF WORK QUANTITTY

A. GENERAL REQUIREMENTS
1.00 Mobilization/Demobilization lot
2.00 Temporary Facilities
a. Field office (to include seperate office for PM and lot
Owner, conference room with internet access
b. Temporary warehouse lot
c. Temporary toilet (seperate from the workers) lot
d. Temporary enclosure lot
3.00 Materials handling lot
4.00 Transport handling lot
5.00 Tools and equipment lot
6.00 Water/power facilities
a. Temporary power connection lot
b. Temporary water connection lot
7.00 Permits and licenses
a. Building permits lot
b. Occupancy permits/ CEI lot
8.00 Bonds and Insurance
a. Surety bond lot
b. Performance bond lot
c. Guarantee bond lot
d. Contractor's all risk insurance lot

9.00 Meralco application and connection fees (legwork only) lot


10.00 Temporary water and power during construction lot
11.00 Others
a. As-built plans lot
b. Security lot
c. Stand by fire extinguisher lot
d. Material testing lot
e. Hauling out of debris and garbage lot
f. Survey of lot
Sub-total

B. PHASE 1

I. EARTHWORKS
1.00 Site clearing lot
2.00 Layout and staking lot
3.00 Excavation
a. Column footings cu.m.
b. Cistern tank cu.m.
c. Septic tank cu.m.
d. Retaining walls cu.m.
e. Sump pit cu.m.
f. Wall footings
4.00 Backfilling and compaction cu.m.
5.00 Disposal of excess soil/ debris lot
6.00 Gravel Bedding cu.m.
7.00 Soil Poisoning sq.m.
8.00 Others
a. Protection of adjacent structure
Sub-total

II. CONCRETING WORKS


1.00 Column footings cu.m.
2.00 Column pedestal cu.m.
3.00 R.C. Columns cu.m.
4.00 Slab on grade
5.00 Wall footings
6.00 Stairs cu.m.
7.00 Lintel Beam cu.m.
8.00 Suspended slabs
a. Upper ground floor cu.m.
9.00 Suspended beams
a. Upper ground floor cu.m.
b. Roof beams cu.m.
c. Concrete gutter cu.m.
10.00 Septic vault cu.m.
11.00 Cistern tank cu.m.
12.00 Retaining Wall cu.m.
13.00 Catch basin cu.m.
14.00 Trench drain cu.m.
15.00 Sump pit cu.m.
16.00 Others
a. Genset pad cu.m.
b. Meralco post cu.m.
Sub-total

III. REBAR WORKS


1.00 Column footings kgs
2.00 Column pedestel kgs
3.00 R.C. Columns kgs
4.00 Slab on grade
5.00 Wall footings
6.00 Stairs kgs
7.00 Lintel Beam kgs
8.00 Suspended slabs
a. Upper ground floor kgs
9.00 Suspended beams
a. Upper ground floor kgs
b. Roof beams kgs
c. Concrete gutter kgs
10.00 Septic vault kgs
11.00 Cistern tank kgs
12.00 Retaining wall kgs
13.00 Catch basin kgs
14.00 Trench drain kgs
15.00 Sump pit kgs
16.00 Others
a. Genset pad kgs
b. Meralco post kgs
c. Tie wire kgs
Sub-total

IV. FORMWORKS AND SCAFFOLDING


1.00 Column Pedestal sq.m.
2.00 R.C. Columns sq.m.
3.00 Stairs sq.m.
4.00 Lintel Beam sq.m.
5.00 Suspended slabs
a. Upper ground floor sq.m.
6.00 Suspended beams
a. Upper ground floor sq.m.
b. Roof beams sq.m.
c. Concrete gutter sq.m.
7.00 Septic vault sq.m.
8.00 Cistern tank sq.m.
9.00 Retaining Wall sq.m.
10.00 Catch basin sq.m.
11.00 Trench drain sq.m.
12.00 Sump pit sq.m.
13.00 Others
a. Genset pad sq.m.
b. Meralco post sq.m.
c. Assorted nails sq.m.
Sub-total
V. MASONRY WORKS
1.00 0.15m CHB with mortar sq.m.
2.00 0.10m CHB with mortar sq.m.
3.00 Others
a. Rebars kgs
b. Tie wire kgs

Sub-total

VI. STRUCTURAL STEEL AND OTHER METALS


1.00 Steel trusses and rafters kgs
2.00 Steel purlins kgs
3.00 Stainless steel handrail l.m.
4.00 Cistern tank cover lot
5.00 Trench drain cover lot
6.00 Consummables kgs
7.00 Others
Sub-total

VII. THERMAL AND MOISTURE PROTECTION (Waterproofing)


1.00 Water stop for RC walls l.m.
2.00 Waterproofing
a. Cistern tank sq.m.
b. T&B sq.m.
c. Retaining wall/ elevator wall sq.m.
3.00 6 mil Vapor barrier sq.m.
4.00 Others
Sub-total

VIII. PLUMBING WORKS lot


1.00 Sewer line lot
2.00 Drainage line lot
3.00 Vent line lot
4.00 Water line lot
5.00 Hangers lot
6.00 Installation of plumbing fixtures and accessories lot
7.00 Installation of water heater lot
8.00
Installation of water pumps, accessories and controls lot
9.00 Installation of grease trap lot
10.00 Sump pumps and controls lot
11.00 Floor drains lot
12.00 Testing and commissioning lot
13.00 Others
a. ACU drain
Sub-total

IX. ELECTRICAL WORKS lot


1.00 Service entrance lot
2.00 Telephone & CATV Service Entrance lot
3.00 Roughing-ins of PVC Conduits and Fittings lot
4.00 Wire and Cables lot
5.00 Wiring Devices lot
6.00 Roughing-ins and Wiring for PABX, CATV, BGM lot
7.00 Roughing--ins and wiring for generator set lot
8.00 Roughung-ins and wiring for alarm system units lot
9.00 Panel Board Assembly lot
Installation of lighting fixtures and other electrical
10.00 fixtures lot

11.00 Testing and commissioning including consumables lot


12.00 Others
a. Hangers and support lot
b. Consumables lot
Sub-total

C. PHASE 2

I. MASONRY WORKS
1.00 Plastering sq.m.
2.00 Concrete topping sq.m.
3.00 Others
a. Rebars kgs
b. Tie wire kgs
Sub-total

II. FLOOR FINISHES (Indicate the kind of floor finish)


1.00 Hallway sq.m.
2.00 Rooms sq.m.
3.00 Common areas sq.m.
4.00 Toilets sq.m.
5.00 Deck/ balcony sq.m.
6.00 Stair steps sq.m.
7.00 Others sq.m.
Sub-total

III. WALL FINISHES (Indicate the kind of wall finish)


1.00 Toilets sq.m.
2.00 Interior walls sq.m.
3.00 Exterior walls sq.m.
4.00 Others
Sub-total

IV. CEILING FINISHES


1.00 12mm Gypsum board on LGS framing sq.m.
2.00 12mm MR Gypsum board on LGS framing sq.m.
3.00 Skim coat (rubbed concrete) sq.m.
4.00 Ceiling eaves sq.m.
5.00 Others
Sub-total

V. CARPENTRY WORKS
1.00 Ceiling cornice bd.-ft
2.00 Baseboards bd.-ft
3.00 Door casings, wood moldings bd.-ft
4.00 Wood treatment lot
5.00 Others
Sub-total

VI. PAINTING WORKS


1.00 Concrete walls
a. Interior walls sq.m.
b. Exterior walls sq.m.
2.00 Ceiling
a. Gypsum board sq.m.
b. MR gypsum board sq.m.
c. Rubbed concrete sq.m.
d. Ceiling eaves sq.m.
3.00 Others sq.m.
Sub-total

VIII. DOORS AND JAMBS (Wood)


1.00 Door jambs set
2.00 Doors set
3.00 Locksets and hardware set
4.00 Others
Sub-total

IX. GLASS AND GLAZING


1.00 Glass doors lot
2.00 Windows lot
3.00 Mirrors lot
4.00 Others
Sub-total
TOTAL DIRECT COST
VAT
MARK-UP AND CONTINGENCIES

GRAND TOTAL
UNIT COST TOTAL AMOUNT
Materials Labor Materials Labor TOTAL

You might also like