You are on page 1of 9

Structural Details Links

http://www.planningplanet.com/wiki/422384/rates-norms-durations
https://www.scribd.com/doc/12971085/International-Productivity-List
https://www.scribd.com/doc/151591149/Productivity-Rate-Labor-Eqpt
https://www.scribd.com/doc/51294202/Work-Item-Productivity
https://www.scribd.com/doc/124477240/Production-Rates-Table
https://www.scribd.com/doc/63804908/Production-Rate
https://www.scribd.com/doc/258990870/Productivity-Rates
http://www.homewyse.com/services/index.html
-norms-durations
al-Productivity-List
ity-Rate-Labor-Eqpt
-Productivity
n-Rates-Table
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

Dismantling of Existing Structures (Pavings) Machine- court dimesions taken 28 x 15m 0.571 m3/hr 1.8 hrs/m3 L/s m3 42.0 73.5 1.0 9.2

PREPARATION OF STRUCTURAL WORKS

Clearing of Building Area & Disposal Clearing Site of bushes, shrubs, roots 25.00 m2/hr 0.040 hrs/sf 21,675 m2 2013.5 80.5 1.0 10.1

Bulk Excavation Hydraulic Excavator, 0.4m3 bucket, Sand/Soil 28.6 m3/hr 0.035 hrs/cf 56,623 cu.m 1603.2 56.1 1.0 7.0

Removal of Loose earth & ramming Soil 58.82 m2/hr 0.017 hrs/sf 21,675 m2 2013.5 34.2 1.0 4.3

Anti-Termite treatment under Footings 1 Helper+2 Technicans 20.25 m2/hr 0.049 hrs/m2 13,130 m2 1219.7 60.2 2.0 3.8

Anti-Termite treatment-sides of Footings 1 Helper+ 2 Technicans 20.25 m2/hr 0.049 hrs/m2 23,851 m2 2215.6 109.4 2.0 6.8

Anti-Termite treatment under floors 1 Helper+2 Technicans 20.25 m2/hr 0.049 hrs/m2 13,130 m2 1219.7 60.2 2.0 3.8

PCC Placing Direct From Readymix Lorry (03), Blinding 1.3 m3/hr 0.8 hrs/cf 4,377 m2 123.9 95.3 3 4.0

STRUCTURAL WORKS UPTO PLINTH

Formwork in Footing 8.0 m2/day 1.00 hrs/m2 4,578 m2 425.3 425.3 7.0 7.6

Reinforcement in Footing & columns Steel fixing below ground. (Dia #4-#6) 0.086 tonn/hr 11.5 hr/Ton 71.132 Ton 71.132 818.0 6.0 17.0

Concerete in Footing Placing Direct From Readymix Lorry, Pile Caps 1.5 m3/hr 0.667 hrs/m3 25,933 m3 200.00 133.333 40.0 0.4

Formwork in Columns (Upto Plinth) 6 m2/day 1.67 hrs/m2 2,535 m2 235.4 392.401 7 7.0

Reinforcement in Columns (Upto Plinth) Steel fixing below ground. (Dia #4-#6) 0.086 tonn/hr 11.5 hr/Ton 18 Ton 17.8 204.5 6.0 4.3

Concrete placement in Columns (Upto Plinth) Placing Concrete, By Wheelbarrow over 1-10m 2.3 m3/hr 0.435 hrs/m3 950 m3 26.91 11.6998 1 1.5

Formwork in Plinth Beams 8.0 m2/day 1.25 hrs/m2 5,173 m2 480.5 600.618 7 10.7

Reinforcement in Plinth Beams Steel fixing at ground. (Dia #4-#6) 0.091 tonn/hr 11.0 hr/ton 71.132 Ton 71.132 782.5 6.0 16.3

Placement of concrete in Plinth Beams Placing Concrete, By Wheelbarrow over 1-10m 2.3 m3/hr 0.435 hrs/m3 4,503 cu.m 127.50 55.4344 3 2.3

Water Proofing Asphalt coatings, horizontal surfaces 4.2 m2/hr 0.24 hrs/m2 27,752 m2 2577.9935 613.808 10 7.7

Sand filling & compaction Manual Filling??? 1.02 m3/hr 0.980 hrs/m3 10,140 m3 287.09079 281.462 5 7.0
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

DPC Bitumen DPC, horizontal 100mm wid 2.9 m2/hr 0.345 hr/m2 202.5 m2 18.81103 6.48656 1 0.8
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

RCC WORKS - PLINTH TO 1ST SLAB

Formwork in Columns upto 1st slab 6 m2/day 1.67 hrs/m2 6,894 m2 640.4 1067.33 15 8.9

Reinforcement in Columns Steel fixing at ground. (Dia #4-#6) 0.091 tonn/hr 11.0 hr/ton 17.78 Tonn 17.78 195.6 6.0 4.1

Placement of concrete in Columns Placing Concrete, By Wheelbarrow over 1-10m 2.3 m3/hr 0.435 hrs/m3 2,585 m3 73.19 31.8235 1 4.0

Formwork in Beams & Slab 8.0 m2/day 1.25 hrs/m2 26,000 m2 2415.2 3019.05 15 25.2

Reinforcement in Beams & 1ST Slab Fixing Steel Above Ground Level - Hoisted By Hand. (Dia #4-# 0.096 tonn/hr 10.4 hr/ton 80.02 Tonn 80.02 832.246 6.0 17.3

Placement of concrete in Beams & Slab Placing Concrete, By Wheelbarrow over 10-20m 1.8 m3/hr 0.556 hrs/m3 14,316 cu.m 405.32 225.179 7 4.0

RCC WORKS- 1ST SLAB TO 2ND SLAB

Formwork in Columns upto 2nd slab 6 m2/day 1.67 hrs/m2 6,083 m2 565.1 941.763 15 7.8

Reinforcement in Columns Fixing Steel Above Ground Level - Hoisted By Hand. (Dia #4-# 0.096 tonn/hr 10.4 hr/ton 17.78 Tonn 17.78 184.944 6 3.9

Placement of concrete in Columns Placing Concrete, By Wheelbarrow over 10-20m 1.8 m3/hr 0.556 hrs/m3 2,281 m3 64.58 35.8794 1 4.5

Formwork in Beams & Slab 8.0 m2/day 1.25 hrs/m2 26,000 m2 2415.2 3019.05 15 25.2

Reinforcement in Beams & 2ND Slab Fixing Steel Above Ground Level - Hoisted By Hand. (Dia #4-# 0.096 tonn/hr 10.4 hr/ton 80.02 Tonn 80.02 832.246 6.0 17.3

Placement of concrete in Beams & Slab Placing Concrete, By Wheelbarrow over 10-20m 1.8 m3/hr 0.556 hrs/m3 14,316 cu.m 405.32 225.179 7 4.0

RCC WORKS- 2ND SLAB TO ROOOF SLAB

Formwork in Columns upto roof slab 6 m2/day 1.67 hrs/m2 6,083 m2 565.1 941.763 15 7.8

Reinforcement in Columns Fixing Steel Above Ground Level - Hoisted By Hand. (Dia #4-# 0.096 tonn/hr 10.4 hr/ton 17.78 Tonn 17.78 184.944 6 3.9

Placement of concrete in Columns Placing Concrete, By Wheelbarrow over 10-20m 1.8 m3/hr 0.556 hrs/m3 2,281 m3 64.58 35.8794 1 4.5

Formwork in Beams & Slab 8.0 m2/day 1.25 hrs/m2 26,000 m2 2415.2 3019.05 15 25.2

Reinforcement in Beams & Slab 0.096 tonn/hr 10.4 hr/ton 71.13 Tonn 71.13 739.775 6.0 15.4

Placement of concrete in Beams & Slab Placing Concrete, By Wheelbarrow over 10-20m 1.8 m3/hr 0.556 hrs/m3 14,316 cu.m 405.32 225.179 7 4.0
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

FINISHING WORKS

BRICK MASONARY & PLASTERING

9" thick Brick Masonary Walls English Bond, 1.0 Brick thick 0.8 m2/hr 1.25 hr/m2 29,494 m2 3653.0865 4566.36 10 57.1

4 1/2" thick Brick Masonary Walls English Bond, 0.5 Brick thick 0.8 m2/hr 1.25 hr/m2 5,620 m2 1566.1924 1957.74 10 24.5

Plastering on Beams & Slabs Plastering Ceilings, 1 Bonding, 1 Skimming 1.7 m2/hr 0.59 hr/m2 41,776 m2 3880.7386 2282.79 10 28.5

Plastering on Columns & Interior Walls Walls over 2.5m high 1.87 m2/hr 0.53 hr/m2 69,655 m2 6470.5297 3454.42 10 43.2

Plastering on Columns & Ex-Walls Walls over 2.5m high 1.87 m2/hr 0.53 hr/m2 30,073 m2 2793.6005 1491.42 10 18.6

FLOORING

Placing Crushed Stone in Floors 50 sf/hr 0.020 hr/sf 10,140 sf 20280 405.6 6 8.5
100 Sf in 2 manhrs (4.6 m2/hr)
PCC under Floor-GF Placing Concrete, By Wheelbarrow over 1-10m 2.3 m3/hr 0.435 hr/m3 4,377 m3 123.9 53.9 3 2.2

PCC under Floor-FF Placing Concrete, By Wheelbarrow over 1-10m 2.3 m3/hr 0.435 hr/m3 4,377 m3 123.9 53.9 3 2.2

PCC under Floor-SF 1.8 m3/hr 0.556 hr/m3 4,377 m3 123.9 68.8 3 2.9
Placing Concrete, By Wheelbarrow over 10-20m
Water Proofing with Bitumen coat 3.5 m2/hr 0.286 hr/m2 20,280 m2 1883.9 538.3 5 13.5
Bituminous Brushed application, 3 coats
CEILING WORKS

Providing Gypsum Ceiling 2.6 m2/hr 0.385 hr/m2 28,911 m2 2685.6577 1032.95 5 25.8
Suspended Ceilings, office situations

Providing Acoustic Panel False Ceiling 2.6 m2/hr 0.385 hr/m2 2,365 m2 219.69425 84.4978 5 2.1
Suspended Ceilings, office situations
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

WALLS AND FLOORS FINISHES

Granolithic Flooring (Chips) Using one machine 3.1 m2/ hr 0.323 hrs/m2 1,825 Sq.m 169.5315 54.6876 1 6.8

Brick Flooring in Patios (Yards) Clay, quarry Tiles, small areas, much cutting 0.8 m2/ hr 1.250 hrs/m2 1,900 Sq.m 176.49855 220.623 5 5.5

Stone Cladding on Walls & Columns Fix 0.75-1.0m2 Stones to Metal Support Frame (A team of one
1.08
fixer
m2/hr
and one mate)
0.926 hrs/m2 25,656 m2 2383.2878 2206.75 8 34.5

Placing Porcelain Tiles on Walls & Floors Ceramic Tiles 150x150mm, Areas over 2.5m 1.7 m2/ hr 0.588 hrs/m2 38,587 Sq.m 3584.4997 2108.53 10 26.4

Providing 4" Porcelain Tile skirting on walls Ceramic Tiles 150x150mm, Areas over 2.5m 1.7 m2/ hr 0.588 hrs/m2 1,233 Sq.m 114.53827 67.3755 5 1.7

Providing Pre-polished Granite on Floors & Walls 0.595 m2/ hr 1.681 hrs/m2 15,125 Sq.m 1405.0213 2361.38 5 59.0

Providing Granite skirting on Walls Granite Wall Panels 0.595 m2/ hr 1.681 hrs/m2 585.87 Sq.m 54.423792 91.4686 2 5.7

Providing Granite Slab on stairs 0.8 m2/ hr 1.250 hr/m2 ? Sq.m 54.342974 67.9287 ` #VALUE!

Grey Granite placement on Walls & Columns Granite Panels 0.595 m2/ hr 1.681 hrs/m2 6,405 Sq.m 594.9859 999.976 5 25.0

PAINT AND POLISH WORKS

Applying Plastic Emulsion/Synthetic Paint on Interior Team of 1 Painter , 1 Material hoist operator 5.50 m2/hr 0.182 hrs/m2 120,293 Sq.m 11174.495 2031.73 7 36.3
Walls

Providing Weather Shield Paint to Exterior Walls 8 m2/day 1 hrs/m2 1,973.63 Sq.m 183.34 183.338 7 3.3
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

WOOD WORKS

Providing of Deodar wood solid core Doors- GF 0.31 No./hr 3.226 hrs/No. 1216.11 No. 22 70.9677 1 8.9

Providing of Deodar wood solid core Doors-FF 0.31 No./hr 3.226 hrs/No. 1216.11 No. 11 35.4839 1 4.4

Providing of Deodar wood solid core Doors-SF 0.31 No./hr 3.226 hrs/No. 1216.11 No. 13 41.9355 1 5.2

Providing Vision Panel/Glazing Doors-GF 0.31 No./hr 3.226 hrs/No. 829.5 No. 3 9.67742 1 1.2

Providing Vision Panel/Glazing Doors-FF 0.31 No./hr 3.226 hrs/No. 829.5 No. 12 38.7097 1 4.8

Providing Vision Panel/Glazing Doors-SF 0.31 No./hr 3.226 hrs/No. 829.5 No. 7 22.5806 1 2.8

Providing cabinets of Laminated Board 0.5 No./ hr 2.000 hrs/No. 1,221 No. 20 40 1 5.0

Providing Sound Proofing System in Walls Glass Fibre, low pitch 12 m2/hr 0.083 hr/m2 2,889 m2 268.37069 22.3642 1 2.8

ALUMINIUM & GLASS WORKS

Providing Aluminium Glass Doors-GF 0.8 m2/day 10.00 hrs/m2 269.50 m2 25.03 250.349 2 15.6

Providing Aluminium Glass Doors-FF 0.8 m2/day 10.00 hrs/m2 49.00 m2 4.55 45.518 2 2.8

Providing Aluminium Glass Doors-SF 0.8 m2/day 10.00 hrs/m2 73.50 m2 6.83 68.2771 2 4.3

Providing Double Glazed Aluminium Windows Windows, Aluminum, 7.0-10.0m2 0.5 m2/day 16.00 hrs/m2 3,199.50 m2 297.21 4755.43 7 84.9

Providing Glass Doors in Glass Walls 0.344 No./hr 2.90 hrs/No. 392.00 No. 5.00 14.5 1 1.8

Providing Tempered Glass Curtain Walls For general curtain walling 30 m2/day 0.33 hr/m2 736.60 m2 68.43 22.8086 1 2.9

Providing Double Glazed Curtain Walls For general curtain walling 30 m2/day 0.33 hr/m2 2,581.89 m2 239.84 79.9473 1 10.0

Providing Glass Partition Walls 29.25 sf/hr 0.03 hr/sf 2,285.50 sf 212.31 78.1368 3 3.3
CALCULATION OF DURATION OF ACTIVITIES BASED ON STANDARD MANHOURS

TOTAL NO OF
PRODUCTIVITY/ MANHOURS/ BOQ QTY Qty Unit DAYS
ACTIVITY DESCRIPTION CONDITIONS INVOLVED Prod. Unit (Used) QTY IN MKS MAN MEN/
UNIT TIME UNIT QTY (FPS) (10hrs)
HOURS TEAMS

STEEL WORKS

Providing of Steel Doors with M.S Tubing 0.285 No./hr 3.5 hrs/No. 245.00 No. 14 49 1 6.1

Providing of Steel Louvered Doors-GF only 0.285 No./hr 3.5 hrs/No. 56 No. 2 7 1 0.9

Providing of G.I. Sheet Rolling Shutters-GF on 72"x48" unit in 2.1 hrs 11.428 sf/hr 0.088 hrs/sf 270 Sf 25.08 23.6262 2 1.5

Providing Metal / Steel Stairs & handrails Handrail = 189+313+431 RFT = 933 Rf 4.23 Rf/hr 0.236 No. 6 Rf 933 220.567 3 9.2

MISCELLANEOUS WORKS

Construction of Mop Sink No. /hr 5 hrs/No. 2 No. 2 10 1 1.3

Providing Library Counter 100 Sf for each counter No. /hr 14.7 hrs/No. 2 No. 2 29.4 1 3.7

Providing Low Height Partition Walls Fix Timber Studding and Hills Duraboard Partition 3.5 m2/hr 0.286 hr/m2 375 m2 34.83524 9.95293 1 1.2

Providing Terracota Brick Tiles on Terrace @ Lecture 1.5m2/hr 0.667 hr/m2 2,950 m2 274.03722 182.691 5 4.6
Theatre

Providing Tufed Textured Loop Carpet Carpeting, Fully Fitted 2.0 m2/hr 0.5 hr/m2 2,356 m2 218.88142 109.441 3 4.6

Providing PVC coated Rubber Flooring 2000 sf per 84.2 hours 23.75 sf/hr 0.042 hr/sf 2,433.93 sf 226.09743 102.481 4 3.2

ROOF FINISHING WORKS

Placing Water Proofing Membrane Bituminous Sheets, horizontal surfaces 4.0 m2/hr 0.250 hr/m2 17,000 m2 1579.2 394.799 7 7.0

Polystyrene board Expanded Polystyrene Boards 8.55 m2/hr 0.117 hr/m2 17,000 m2 1579.2 184.701 7 3.3

Polythene Sheet Polythene Sheets, horizontal surfaces 20 m2/hr 0.050 hr/m2 17,000 m2 1579.2 78.960 7 1.4

Brick Tiles Laid in Mud 2.2 m2/hr 0.455 hr/m3 17,000 m3 481.3 218.780 7 3.9
Clay,quarryTiles,largeareas,littlecutting
Apply White Paint to Roof 5.50 m2/hr 0.182 hrs/m2 17,000 m2 1579.2 287.127 7 5.1