Professional Documents
Culture Documents
www.huawei.com
Notes:
If the power cable length(between RRU and DCDU) >100m,
please contact Huawei Site Engineer for special solution
1) FDD LTE BBU should install under the TDD LTE BBU which already existed on the site.
2) Power cable of RRU from Sector A/B/C connected Load 3/4/5; Power cable of BBU
connected to Load 7.
3) CPRI Fiber of RRU from Sector A/B/C connected to CPRI 0/1/2 on LBBP board.
4) Transmission Fiber connected to SFP 0; Transmission Ethernet Cable connected to GE/FE 0
5) CPRI Fiber should be tied with Hook & Loop Mechanical Fastener.
6) 1 U space should be reserved between 2 BBUs.
-45
+45
ANT0
ANT1
3
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 7
1) Label of ANT_0A, ANT_0B, ANT_0C is connected to +45
Antennas Labeling 2) Label of ANT_1A, ANT_1B, ANT_1C is connected to -45
RRU 0
1 0
ANT_1A
ANT_0A
Feeder Label
ANT_1A
ANT_0B
ANT_1B
ANT_0C
ANT_1C
Feeder Label
Notes
Safety cap is needed for the working on the site. And the safety belt is needed for working on the tower
or poles.
Notes
1. Power cable of RRU for sector A/B/C should be connected to LOAD3/4/5, label with LTE PWR
RRU0/1/2
2. BBU should be connected to LOAD7, label with PWR BBU
Notes
The black shield of the power cable near the power connector of DCDU should be cut and tied up.
Notes
The CPRI fiber should be tied with Hook & Loop Mechanical Fastener. Dont use cable tie.
Notes
The redundant fiber should be circled and put on the bottom of the transmission rack. Dont put it
outside the tower or on the cable tray.
Notes
The power cable should use the heat-shrink tube. And it should be done well.
Notes
Ground the DCDU on the Transmission cabin. ( Use 6mm grounding cable. )
Notes:
Follow the label on the bracket assembly carefully. And make sure the bracket assembly of the RRU is
installed on the right direction.
Notes
The metal shield of RRU power cable should be cut and grounding on clip inside RRU cabling cavity. The
metal shield can not be cut too long and it go outside the cabling cavity.
Notes
The water plugs should be filled in the vacant troughs of the RRU cabling cavity.
Notes
Use Label ANT_0A and ANT_1A for Sector A;
Use Label ANT_0B and ANT_1B for Sector B;
Use Label ANT_0C and ANT_1C for Sector C.
Notes
Oil paint of tower is not removed on earth grounding point.
electric ability surge protection will be decreased.
Notes The power cables of the RRU should be grounded by the grounding clip on the grounding bat
before routed into the Roxtec.
Notes
BBU and DCDU should be fixed with screws. Cable ties is forbidden to use for fixing equipment.
Notes Keep the environment of the site neat and clean. Dont leave any boxes, cables, bottles
inside and outside the shelter. Take all the garbage away the site.