You are on page 1of 1114

COPYRIGHT, 1991

Combustion Engineering, Inc.

Copyright under international copyright conventions


and under Pan American copyright convention

All rights reserved. This book, or parts thereof,


may not be reproduced in any form
without written permission of the publishers.

Library of Congress catalog card number 91-070223

International Standard Book No. 0-9605974-0-9

Disclaimer
The information in this book has been obtained by Combustion
Engineering, Inc. from sources that are believed to be reliable.
Neither Combustion Engineering, Inc., nor any of the authors
employed thereby, makes any warranty, express or implied, or
assumes any legal liability or responsibility for the accuracy, com-
pleteness, or usefulness of any information, apparatus, product or
process disclosed in this book, or represents that the use of any such
information, apparatus, product or process would not infringe
privately owned rights. This book is published with the under-
standing that Combustion Engineering, Inc. and the authors em-
ployed thereby are supplying information but are not attempting to
render engineering or other professional services. If such ser-
vices are required, the assistance of an appropriate professional
should be sought.

Layout, Artwork and Mechanicals


Joseph F? Amenta

RAND McNALLY
Printed in U.S.A.
Table of Contents
Introduction 1-1 to 1-6
1. Steam Power-Plant Design 1-1 to 1-37
2. Fossil Fuels 2-1 to 2-43
3. Properties of Coal Ash 3-1 to 3-34
4. Combustion Processes 4-1 to 4-35
5. Steam Generation - - - - --

6. Designing for Boiler Performance 6-1 to 6-62


7. Central-Station Steam Generators 7-1 to 7-51
8. Boilers for Process Use1 Power Production 8-1 to 8-64
9. Fluidized-Bed Steam Generators 9-1 to 9-32
10. Marine Boilers 10-1 to 10-22
11. Pulverizers and Pulverized-Coal Systems 11-1 to 11-37
12. Fuel-Firing Systems 12-1 to 12-27
13. Operational Control Systems - -

14. Steam-Generator Auxiliary Equipment 14-1 to 14-50


15. Control of Power-Plant Stack Emissions 15-1 to 15-76
16. Ash Handling Systems 16-1 to 16-33
17. Metallurgy and Materials 17-1 to 17-32
18. Steam-Generator Manufacture 18-1 to 18-18
19. Field Construction of Steam-Generating Equipment 19-1 to 19-21
4
20. Water Technology 20-1 to 20-48
21. Operation of Steam Generators 21-1 to 21-34
22. Performance Testinn of Steam Generators
-
22-1 to 22-30
23. Maintenance and Repair of Steam-Generating Equipment 23-1 to 23-23
24. Maintaining Availability: Condition Assessment and Remaining Life Analysis 24-1 to 24-16
25. Combustion Engineering Research and Development Facilities 25-1 to 25-16

APPENDICES

A. Coals of the World A-1 to A-55


B. Determination of Coal-Ash Properties B-1 to B-18
C. Combustion Calculations by Graphical Methods C-1 to C-40
D. Steam Tables
E. Engineering Conversion Factors E-1 to E-17
ACKNOWLEDGEMENT
We dedicate this edition of COMBUSTION, with thanks, to the many people who con-
tributed their talent and time, in great or small measure, to revising and updating its
technical base, and encouraging and supporting its publication.

A. A. Arstikaitis D. Frabotta W. S. Mikus


G. F. Barcikowski F. Gabrielli N. C. Mohn
T. J. Barker D. E. Gelbar K. W. Morris
T. K. Benton D. E. Gorski J. J. Moskal
J. D. B'ianca J. Grusha J. M. Niziolek
R. D. Blodgett G. l? Hammer A. L. Plumley
M. l? Borden R. W. Hanson E. A. Ramspeck
R. W. Borio J. P. Harmon J. H. Ratcliffe
C. R. Bozzuto D. J. Hart J. A. Ray
G. E. Bresowar C. F. Horlitz, Jr. J. W. Regan
H. E. Burbach G. D. Jukkola E. K. Rickard
G. M. Chase S. E. Kmiotek J. R. Rode
I. M. Clark R. F. Konopacki G. Sailer
M. B. Cohen R. C. Kunkel A. J. Seibert
J. R. Comparato A. A. Levasseur R. S. Skowyra
K. E. Crooke V. Llinares, Jr. R. T. Smuda
D. l? Davies G. R. Lovejoy l? L. Stanwicks
M. A. Delin R. E. Mahoney E. A. Steen
R. E. Donais J. A. Makuch G. R. Strich
R. E. Drake, I1 T. V. Malizewski W. R. Sylvester
W. B. Ferguson J. F. Mangold G. W. Thimot
J. D. Fishburn J. L. Marion W. E Walsh
J. C. Flynn, Jr. 0. Martinez, Jr. C. H. Wells, Jr.
A. E. Fournier T. l? Mastronarde J. E. Wilmoth
J. D. Fox M. S. McCartney E. A. Zielinski

To Mrs. Judith C. Gorski, who served as copy editor for the Third and Fourth Edi-
tions, we owe a debt of gratitude. Her concern for logic and clarity is reflected through-
out the text.

To T. E Gawlicki, we say thanks for expediting this edition to completion. Without


him, it never would have been printed.

To my wife, Alice, I submit an overdue apology for the three years of creeping disarray.

Note: In addition to the technical editing, rewriting, and proofreading of the entire
book, the Editor wrote much of Chapters 7, 15, and 24;most of Chapters 1 through
6, and 14; and all of Chapter 16, Appendices A and E, and the Index.
Preface to the Fourth Edition

The book COMBUSTION is intended to provide a thorough insight into the workings of the steam-
producing side of a modern high-efficiency power plant burning a wide variety of fossil fuels. We
have revised or added to over three-quarters of the material in the 1981 edition. We have made
several chapters even more generic than in the last edition, which should make it even more useful
to the engineers, developers, and operating people who regularly refer to those sections. It appears
that the principal value of this text to academia is as a supplemental reference for both class and
project work (which it is) and a source of information for writing textbooks on overall power genera-
tion, which it is not.
Because of the maturation of the fluidized-bed boiler since 1981, we have built an entire chapter
around that technology and its power-producing applications. We have not placed specific empha-
sis on this or any other way of burning coal, because economics aqd federal regulations will dictate
their usage. We have also included a new chapter on the C-E laboratory capabilities for research
and development in the fuel-burning, steam-generating, and emission-control fields. The chapter
illustrates the scope of equipment and talented personnel needed to back up the design and opera-
tion of today's large, high-pressure steam-generating equipment.
Engineers throughout the world have found the previous edition of this book useful in their day-
to-day activities to do with power plants. In revising and updating it, we anticipate that it will be
of even greater use in the unprecedented construction of fossil-fueled power-generation installa-
tions that will take place in the next 10 to 15 years. This edition looks forward to that design and
building program, and presents the total range of concepts and equipment that will be used to take
the universe of steam power generation into the twenty-first century.
The world community is making steady progress in converting to the SI-metric measurement
system (Systkme International des Unites). America will take a major step in 1992 when all govern-
ment procurement will be done in SI units only. However, the many duplicate 300- to 600-megawatt
units that are going to be ordered by American and other utilities in the next several years will be
built in U. S. Customary (USC) units, as were their prototypes. Consequently, spare and replace-
ment parts will continue to be furnished in USC dimensions well into the middle of the next century.
"Bi-lingualism" of measurement will be with us a long time; hence the substantial expansion that
we have made to the appendix on engineering conversions.
Note that the six chapters that are either new or that have been substantially rewritten have both
SI-metric and USC units. In the body of the text, numbers given in parentheses following a mathe-
matical value will be either close approximations or exact equalities, depending on the context. As
in the previous edition, the results of empirical testing are reported in the units in which the data
was generated.
It surprised me, during the 3 years that I have worked on this revision, that so much has changed
since 1980. The fact that very few major purchases of large boilers were made in that time did not
stop the brilliant engineering minds of the industry from refining, optimizing, and, in some areas,
completely changing designs for use in the upcoming campaign of power-plant construction. We
can only surmise that all competitive industries do the same-to continue to invent and grow and
update when things are slow-when management provides the encouragement and backing to do
so. I am proud to have worked for 45 years with such dedicated and ingenious people.
As we said in the Preface to the previous edition:
"Please note that throughout this book many illustrations and figures are used to explain physical
and chemical phenomena. The values in these figures are approximate and are for illustration only.
None should be used for design standards or other purposes where exact values are required. Al-
though extensive, the text is limited to introductory material on many of the subjects and is only
the 'tip of a large iceberg' that represents the accumulated experience of the technical personnel
of a major steam-generator supplier such as C-E."

Joseph G. Singer
Easter, 1991
INTRODUCTION

Combustion Engineering-An Introduction

u he world today faces a critical challenge


as nations strive to satisfy the basic
human needs of food, shelter, and clothing
which are so dependent on adequate supplies
marks a milestone for C-E. The organization
bearing the Combustion Engineering name was
formed in that year, although its roots had been
firmly planted in the 1880's.
of energy. The great increase in the use of The merger of the Grieve Grate Company and
energy has come at the expense of our fossil the American Stoker Company brought to-
fuels-coal, oil and gas-and people are more gether two well-known manufacturers of fuel-
aware that natural resources have finite limits. burning equipment to become Combustion
As we search'for the ultimate solutions to the Engineering Corp. The Grieve grate was a spe-
energy crisis, we must at the same time con- cialized grate capable of burning anthracite-
tinue to look for interim ways of meeting the coal screenings; the American Stoker Company
immediate growth in demand for energy. manufactured a screw-type stoker to burn
Technological improvements i n mining, mov- bituminous coal. Soon, the new organization
ing, processing and using fossil fuels can, of acquired a license to build a single-retort
course, stretch energy-resource reserves, as can underfeed stoker of English design. Known as
a determined effort at conservation. Similarly, the TypeE stoker, it remained popular for small
application of technologies such as coal gasifi- boilers for many years.
cation or fluidized-bed combustion can widen During the twenties, other stoker technology
the use of the world's vast coal resources. And was acquired as were manufacturing plants
finding n e w ways to make the best use of our along the Monongahela River south of Pitts-
energy supplies is what Combustion Engineer- burgh, Pennsylvania. C-E fabricated all its
ing's tradition is all about. stokers in this plant which was built about the
turn of the century. In addition to the Coxe
traveling grate and the Green chain grate, C-E
A NEW NAME offered several types of underfeed stokers in-
cluding the Type E, the Low Ram Stoker, the
AND RAPID GROWTH Skelly Stoker, and the C-E Multiple-Retort
To tell the story of Combustion Engineering Stoker.
is to trace the development of fossil power As the Company grew, new stoker designs
technology i n the United States. The year 1912 were developed such as the Lloyd Traveling
COMBUSTION FOSSIL POWER SYSTEMS
Combustion Engineering-An Introduction

Grate and the C-E Continuous Ash Discharge cally designed for pulverized-coal firing.
Spreader Stoker. But as grate surfaces grew to Acquisition of two boiler companies aug-
24-ft wide by 28-ft long in size, the traveling mented C-E's manufacturing capabilities. At
grate stoker reached a practical limit-and a the former Heine Boiler plant site in St. Louis is
unit this size burning anthracite could generate located one of C-E's manufacturing plants to-
only about 200,000 pounds of steam per hour. day, while the present major manufacturing
Despite its limitations, however, the continu- facility in Chattanooga is on the former
ous ash discharge spreader stoker remains in Hedges-Walsh and Weidner Boiler Co. site.
use today on boilers burning coal, wood, and Until this time, steam-generating units were
bark. an assembly of separate components bought
from different manufacturers. With the addi-
tion of these two boiler companies, C-E was
A QUANTUM JUMP able to combine all components (boiler, super-
IN COMBUSTION TECHNOLOGY heater, water-cooled furnace, fuel-burning
equipment and heat-recovery equipment) into
In 1918, C-E launched into the developing one coordinated design.
technology of pulverized-coal firing. Overcom-
ing the limitation placed on boiler capacity by
the size restrictions of stokers, pulverized-coal THE MOVE TOWARD MERGER
firing opened the door to a large expansion in Paralleling the growth of Combustion En-
capacity of coal-fired boilers. gineering i n this period was the Locomotive
Capitalizing on a pulverized-coal firing sys- Superheater Company, founded i n 1910 to fur-
tem for steam locomotives, Combustion En- ther the use of superheated steam in the boilers
gineering successfully adapted this technology of American locomotives. This company had
to stationary utility boilers at the Oneida Streetestablished a manufacturing facility in East
and Lakeside Stations of the Milwaukee Elec- Chicago, Indiana, where today Combustion
tric Railway and Light Co. This pioneering Engineering assembles coal pulverizing equip-
work, done jointly with Milwaukee Electric's ment. With the development in 1914 of a pat-
engineers and the Bureau of Mines, marks the ented forged return bend for joining two
most important single development in the art tubes, the Locomotive Superheater Co, pro-
of solid-fuel combustion in this century. As a duced heat exchangers that very quickly were
result, i n 1980, the Oneida Street Station, accepted as a standard in the railroad industry.
where pulverized coal was first put to use by a Virtually 611 of the steam locomotives sub-
utility, was named an Historic Engineering sequently built i n the U.S. were equipped with
Landmark by the American Society of Mechan- these superheaters. In 1917, The Superheater
ical Engineers. Company, as it became known, began design-
ing and building superheaters for use in sta-
MANUFACTURINGCAPABILITY tionary boilers and the superheater design
achieved prominence in the stationary boiler
EXPANDS field. It was here that the paths of Combustion
It was not until 1925 that C-E entered the Engineering and the Superheater Company
steam boiler business, beginning with a bent- crossed.
tube boiler design installed in the early twen- During the Great Depression, Combustion
ties at the Ford Motor Company's River Rouge Engineering was reorganized as a subsidiary of
plant. For this same installation,.Ccrmbustion The Superheater Company. Close ties devel-
had supplied the pulverizers and fuel-burning oped between these two organizations, leading
equipment. The Ford Company's 200,000 lblhr to the eventual merger of the two i n 1948 under
boilers were among the first large units specifi- the name of Combustion Engineering-Super-
COMBUSTION FOSSIL POWER SYSTEMS
Combustion Engineering--An Introduction

heater, Inc. In 1953 the name Superheater was As the search for higher efficiency of utility
eliminated and the Company took the name plants continued, operating pressures and
by which it's known throughout the world temperatures also rose. In the mid-1920's most
today-Combustion Engineering Inc. utility boilers supplied steam to turbines at 400
psig, with a few as high as 600 psig. By the late
20's, some boilers were sold for throttle pres-
C-E: PIONEER sures of 1200 pounds per square inch, includ-
IN BOILER DESIGN ing C-E boilers supplied to Milwaukee Electric
and Kansas City Power and Light. In this same
After its entry in 1925 into the steam- period, steam temperatures increased gradu-
generating equipment business, Combustion ally from between 500F and 600F to the 700F
made many significant contributions to fur- to 750F rangd, a substantial advancement con-
nace design and firing techniques. sidering the materials available at the time.
Traditionally, boilers had refractory-lined
furnaces. But with the advent of pulverized-
coal firing, refractory-lined furnaces could not
tolerate the high
PULVERIZED FIRING DEVELOPS
- heat-release rates without
severe ash-fouling and erosion problems. The pioneering work on pulverized-coal fir-
Consequently, it became necessary to cool the ing at Milwaukee was followed in 1927 by the
furnace, at,the same time protecting the refrac- introduction of tangential firing in which fuel
tory, by lining its inside surfaces with tubing and air are introduced into a furnace from its
through which water flowed as part of the four corners instead of through front or rear
boiler circulating system. Combustion was in walls. First installed commercially at the U.S.
the forefront of this development. Rubber Co. plant in Detroit, Michigan, this fir-
Initially, bottom water screens shielded only ing system provides the optimum in rapid and '
the furnace floor as in the Oneida and Lakeside intimate mixing of fuel and oxygen to promote
Stations of Milwaukee Electric in 1920. In 1923 efficient combustion. Later, in 1940, a major
at the Springdale Station of West Penn Power modification to the basic tangential firing idea
Co., water-tube use was extended to the rear was applied to a boiler at Duke Power Co's.,
furnace walls. The first installation of water Buck Station-the fuel and air nozzles in the
tubes on furnace side walls was also in 1923 at corners were made vertically tiltable. The new
Consolidated Edison's Hell Gate Station. In design permitted the flame envelope created by
1925 the Cahokia Station of Union Electric be- the tangential action to be moved up and down
came the first boiler with bottom, rear and within the furnace, thereby. changing the heat-
side-wall water tubing. absorption pattern of the furnace wall. The re-
Water-cooling technology matured from bare sulting variation in temperature of the hot
tubes on wide spacing to close-spaced tubes gases entering the superheater surfaces pro-
with welded fins, then to tangent tubes pre- vided a means of controlling steam tempera-
senting a completely water-cooled metal sur- ture. C-E has had such tangential firing as its
face to the flame. Today's modern boilers have preferred method of suspension firing of most
fusion-welded furnace walls, a C-E develop- fuels for over 50 years.
ment in 1950 at the Kearny Station of Public Another equipment design to become a stan-
Service Electric and Gas of New Jersey. During dard in the industry is the C-E Bowl Mill, intro-
this era steam generator sizes expanded duced commercially in 1933. Originally based
rapidly, until i n 1929 Combustion put into ser- on the Raymond technology, this pulverizer
vice at the East River Station of New York Edi- design has been modified and increased in size
son Co., (now Consolidated Edison) the first over the years from a coal capacity of 3500 lblhr
unit to develop steam at 1,000,000 lblhr. coal to more than 100 tonslhr to keep pace with
COMBUSTIONFOSSIL POWZR SYSTEMS
CombustionEngineering--An introduction

the requirement for supplying fuel to larger cept involved reheating steam in a section of
and larger steam generators. the boiler after some of its energy had been ex-
tracted through expansion in the initial section
WELDED DRUMS LEAD
of the turbine. The reheated steam, now at or
TO HIGHER PRESSURES, TEMPERATURES
near the initial steam temperature, was then re-
A major contribution to the development of turned to the final section of the turbine.
modern steam generators was the welded Although a few reheat units had been built in
boiler drum. Until the late twenties, heavy the 1920's, it was not until after World War I1
pressure vessels were made of formed plates that the surge toward reheat i n the utility in-
riveted together with the joints caulked to dustry began in earnest. Combustion sold the
prevent leakage. This construction physically first post-war reheat unit to Boston Edison Co.
limited operating steam pressure. for its Edgar Station in 1947. In the following
At its Chattanooga plant, Combustion de- years, reheat designs became the norm, with
veloped and perfected processes, techniques, C-E supplying more than 630 reheat units to
and machines for fusion welding of heavy plate utility users around the world.
to form cylindrical shells for drums. The first
such welded drum was dedicated as a National CIRCULATING SYSTEM ADVANCES
Historic Landmark by ASME on May 2, Combustion Engineering designed and in-
1980-50 years after the drum was successfully stalled its first Controlled Circulationa steam
tested. Welded construction permitted steam generator at Montaup Electric Co. in Somerset,
pressures to increase and, in 1931, Combustion Massachusetts in 1942. In this design, con-
installed the first boiler to operate at 1800 psig trolled circulation of water is assured by using
at the Phillip Carey Co. in Lockland, Ohio. By pumps to provide a positive flow through the
1953, C-E had designed the first 2650 psig unit heat-absorbing tubes in the furnace walls; the
for the Kearny Station of Public Service Electric available pump head permits the use of distri-
and Gas of New Jersey. bution orifices in the tube circuits. The Con-
With improved endurance of materials that trolled Circulation steam generator overcomes
could tolerate higher operating temperatures the problem of decreasing thermal-circulation
and pressures, outlet steam temperatures effect as the operating pressure approaches
began to climb from the 750F level. By 1939, the 3208 psia critical point. This positive-
steam temperatures reached 925F when C-E circulation design has been well accepted in
installed another pioneering unit at the River the utility industry around the world.
Rouge plant of Ford Motor Co. A license agreement was signed in 1953 with
The first unit to exceed 1000F total steam Sulzer Brothers of Switzerland for the rights to
temperature was sold to the Public Service build and sell their Monotube steam-generator
Electric and Gas of New Jersey for its Sewaren design in the United States. (The Monotube de-
Station in 1949. This boiler was designed to sign is a once-through type steam generator in
operate at 1050F at the superheater outlet. which the water that is introduced at the inlet
Steam temperatures continued to inch upward; of the unit passes continuously through the
the Kearny unit of the same utility, purchased tubing, where it is heated to the desired outlet
in 1953, was designed to operate at 1100F and temperature with no internal recirculation.) In
2376 psig at the superheater outlet and 1050F 1954, The Philadelphia Electric Company pur-
at the reheater outlet. In 1954, the C-E super- chased the first unit of this design for its Eddy-
critical pressure unit for Philadelphia Electric stone Plant. This unit was designed--too~perate
Co's. Eddystone Station was designed for out- at 5300 psig and 1210F at the superheater out-
let conditions of 1210F at 5300 psig. let, the highest pressure and temperature for a
In the search for higher efficiencies, the util- unit of commercial size ever. The unit went
ity industry adopted the reheat cycle. This con- into operation in 1959, followed by several
COMBUSTION FOSSIL POWER SYSTEMS
Combustion Englneerlng--An Introduction

other supercritical and subcritical pressure in- This air preheater design, manufactured in
stallations of the Monotube type. C-E's Wellsville, New York facility, has been
Combustion's next advancement in high- universally accepted in the industry and
pressure technology area was the Combined has been applied to steam generators of all -
CirculationB design which uses the principle manufacturers.
of Controlled Circulation in the furnace walls Combustion Engineering pioneered flue-gas
(recirculation of the fluid by pumps) super- scrubbers for sulfur-dioxide removal with re-
imposed on the once-through flow of the search and development work begun in 1963. A
Monotube design. This design eliminated the pilot facility was constructed in its Windsor,
Monotube-boiler requirement for a high Connecticut, development laboratory, followed
through-flow in the furnace walls during start- in 1966 and 1967 by experimental field work on
up and the necessity for a correspondingly a Detroit Edism Co. unit at the St. Clair Station.
large turbine bypass system. The first unit of C-E made the first commercial scrubber instal-
this design was installed at the Tennessee Val- lations in the United States in 1968 at Union
ley Authority's Bull Run Station and placed in Electric Co's Meramec Station and Kansas
operation in 1966. It was designed for 3650 psig Power and Light Co's. Lawrence Station.
superheater outlet pressure at 1003F super- In 1977, C-E Walther, Inc., a subsidiary of
heater and 1003F reheater outlet tempera- C-E acquired Pollution Control-Walther, an
tures. The steam capacity of 6,400,000 lblhr American company producing the Walther
served a turbine capable of generating 900 (Cologne, Germany) design of rigid-frame elec-
megawatts: Many similar units of this type fol- trostatic precipitators. With this acquisition,
lowed. Combustion broadened its scope of supply in
environmental control systems, which now in-
BROADENED CAPABILITIES, cludes fabric filters, dry sulfur-dioxide re-
moval systems, wet electrostatic precipitators,
Combustion Engineering developed and rod scrubbers and wet scrubbers.
produced air preheaters of the plate type in the It was also in 1977 that C-E re-entered the
early 1920's to provide heat recovery from the ash-handling field, a move aimed toward pro-
hot gases leaving boilers, thereby improving viding full-scope ash systems for pulverized
boiler efficiency. During the same time, the coal-fired boilers and associated precipitators,
Ljungstrom continuous regenerative-type air fabric filters, or dry scrubbers. Beginning with
preheater was developed, in connection with the Combusco water-sealed ash drag conveyor
the first turbine locomotive. In the U.S., the designed in 1919 by the Underfeed Stoker
first Ljungstrom installations for industrial Company, Ltd., Combustion furnished many
power plant boilers were made in 1923. bottom-ash hoppers and removal systems, and
In 1925, the Air Preheater Corporation was pyrite hoppers for C-E pulverizers. Today, it is
founded, jointly owned by the Ljungstrom a prime supplier of large submerged scraper
Turbine Manufacturing Co. of Sweden and conveyors, under license from its associated
the James Howden Co., Ltd. The Superheater company EVT of Stuttgart, Germany.
Company acquired this company after the De- Meanwhile in 1955, C-E's nuclear power ac-
pression, along with the exclusive license to tivity had begun with the design and construc-
manufacture the Ljungstrom@Air re heater in tion of a prototype marine nuclear propulsion
the United States and Canada. The Ljungstrom system. Going into operation in 1959, the SIC
Air Preheater utilizes a rotating heating ele- prototype operatedfor more than 10 years, both
ment made up of closely spaced metal plates as an R&D and as a Naval training facility. In
packed in baskets through which alternately 1967, another C-E reactor, the BONUS plant,
pass the hot gases leaving the boiler and achieved full operation as the first nuclear
the --cold combustion air going to the furnace. power plant in the United States with an inte-
COMBUSTION
Combustlon Engineering - An Introduction
gral superheating core. Also in 1967, the Com- electricity, industrial competitiveness, environ-
pany sold its first nuclear steam supply system mental protection, mass transportation, and a
to the utility industry with Consumers Power's variety of industrial services.
purchase of its Palisades nuclear station. C-E, as a member of the ABB Group, is well
During the years, C-E continued to diversify positioned to meet the world's energy challenges
into new markets while strengthening its posi- head-on by offering to energy-related industries,
tion in traditional ones. A case in point is the both nationally and internationally, equipment
Company's activities at the international level and services in a blend of technologies.
which began in 1923. Since that time, Combus- The combination of Asea Brown Boveri Inc.
tion-through direct sales, associated compa- and C-E brings together two companies with
nies, and licensees-has gained world-wide complementary capabilities and reputations as
reputation as a leading supplier of steam- industry and market leaders. The combined
generating equipment with installations in more U. S. operations of Asea Brown Boveri Inc. and
than 70 countries. Abuut 40 percent of the free C-E represent a total of 30,000 employees.
world's electric power currently is generated
by equipment of C-E design.
THE YEARS AHEAD
THE MODERN C-E: We have reviewed the history of C-E as the
GROWTH AND company came of age and matured in the utility
DIVERS1FlCATlON and industrial markets, and have examined its
many significant contributions. Advances made
Industrial expansion and general business over the last three quarters of a century in the
growth characterized the U.S. national economy development of energy conversion processes
during the 1950's and 60's. Reflecting confidence from fossil fuels have been great. Those individ-
in the strength of its position in the utility and uals who have worked in the industry during
industrial power fields, C-E took steps to expand some part of that time have witnessed not
its range of products and services for a chang- only tremendous growth in the art and science
ing and growing marketplace. of fuel burning and steam generation, but also
During these eventful years, C-E transformed remarkable changes in the lifestyles of people
from a manufacturer of steam supply systems throughout the world brought about in part by
into a multifaceted organization deeply involved that growth. There are underway today new
in building products, oil and gas exploration, developments which will open new vistas for
production, refining, and petrochemical plants. fossil fuels. That is what much of this book
Starting with The Lummus Company acquisi- is all about.
tion in 1957, Combustion Engineering has oper- As a member of the ABB Group, C-E contin-
ated with the policy that successful diversifi- ues to embrace the values that have kept it at the
cation is built upon technology or markets cutting edge of technology. A dedication to ser-
familiar to C-E. vice and the courage to lead-attributes which
In 1990, C-E became, by acquisition, a wholly- have been major influences throughout its his-
owned subsidiary of Asea Brown Boveri Inc., a tory-still guide the company's operations today.
Delaware corporation. Thus, C-E is now part of As it faces the technical challenges of our energy
the ABB Group, one of the world's largest elec- future, C-E, as a member of the ABB Group will
trical engineering companies. Backed by some continue to build on its reputation by supplying
215,000 employees in 140 countries worldwide, only the highest quality steam-generating and
the ABB Group is helping to provide affordable other energy equipment.
CHAPTER 1

Steam Power-Plant Design

u he design of equipment for a fossil-fueled


steam supply system starts with the appli-
cation of certain basic fundamentals governing
the relationship between properties of matter
THERMODYNAMIC CYCLES
FOR POWER PLANTS
that define the conversion of energy from one Historically, the roots of thermodynamics go ,bLn&,
form to another. Known as the first and second back to attempts to quantify instinctive%&
laws of thermodynamics, these cornerstones of cepts of systems designed to produce work from
power-plant design provide a quantitative various energy sources. For continuously con-
method of looking at the sequential processes verting heat into work, the first practical power
of working fluids as a function of temperature, systems used steam as a working fluid.
pressure, enthalpy, and entropy. The design of a By definition, a thermodynamic cycle is a
modern-day power plant represents, however, series of processes combined in such a way that
more than the application of thermodynamic the thermodynamic states at which the working
data. It is a synthesis of economic consider- fluid exists are repeated periodically. Custom-
ations with thermal performance criteria that arily, in an electric generating station, the fluid
govern the selection of steam-generating equip- is cycled through a sequence of processes in a
ment, whether the installation is for pro- closed loop designed to maximize generation of
ducing steam at an industrial site or utility electric power from the fuel consumed cons is^
&"^hi
power plant. tent with plant economics.
In this first chapter, which presents an over- The design of a specific power plant repre-
view of power-plant design, the opening sec- sents an optimization of thermodynamic and
tion explores basic thermodynamic cycles: economic considerations, the latter including
Carnot, Rankine regenerative reheat and co- initial, production, and distribution costs. In
generative cycles are covered. A second section this first chapter, basic thermodynamics and
describes certain general design approaches re- economics applicable to large utility and indus-
lating to industrial installations. The third sec- trial power plants will be presented. These form
tion deals with the principal factors involved in the basis for the selection of plant cycles and
the selection of steam-generating equipment for equipment. In this connection, it may be men-
electric utilities. Finally, the concluding sec- tioned that an outstanding treatment of the sub-
tion examines power-plant economics. ject is given in the Zerban and Nye book Power
COMBUSIIO?i
Steam Power-Plant Design

Plants, 1960 edition, particularly with refer- When changes in kinetic energy and elevation
ence to Chapter 2. of the fluid stream may be neglected, Eq. 3 re-
duces to the familiar W = m (hi, - houJ.
LAWS OF THERMODYNAMICS SECOND LAW
The first and second laws of thermodynamics
govern the thermodynamic analysis of fluid
cycles. These laws are stated in equation form
AS=
6)
9 +I+xS.
,
(4)
as follows:
FIRST LAW
where AS is change in entropy of system; (QIT) =
AE = Q - W + C ( 2 h l 2e,,)ml E,(Q,/T,)i.e. the sum over the system boundaries
I
of the heat transferred, Q,, at a position on the
(I) boundary where the local temperature is TI,and I
is irreversibility. (For consistency with other sec-
where AE is change in energy content of SYS- ond-law statements, I 2 0. For reversible pro-
tern*Q is heat transferred to system, w is work cesses or cycles, I = 0; for irreversible processes
transferred from system and ( h ~+ %)mi is or cycles,I > 0.) C, S, is the entropy flow into and
energy convected into or out of system by mass, out of system associated with mass flow, m,, into
mi, with e n t h a l ~h,,
~ , and extrinsic energy*ea. and out of system. For a reversible cyclic process
Extrinsic energy, em, is dependent on the involvingaclosedsystem,I= 0, AS = 0, E,S,= 0
fmme of reference. For a fluid system, em = and Eq. 4 reduces to
kinetic energy + potential energy = V,2/2, + zt,
in which V, is velocity and z is elevation above
,datum. (F) = o
(5)
This equation applies equally to processes and
cycles, steady- and transient-flow situations. For
The steady-flow,adiabatic expamion of a fluid
example, in a closed system where fluid streams through a turbine is governed by the following
do not cross the boundary, m, = 0, and if the
equation.
process is cyclic, then AE = 0 and Eq. 1becomes
I = - m,s, = -m(s - s out)
CQ= C W ,
c~cle cvcle = m(s out - s In )
(2) (6)

For reversible, adiabatic expansion, I = 0 and


This implies 100 percent efficiency. the process is characterized by the familiar isen-
As another example, if the Steady-State adia- tropic property, so,, = s,,. Turbine expansion is
batic expansion in a turbine is being analyzed, not wholly isentropic. This nonisentropicity is
then AE = 0, Q = 0, and Eq. 1 reduces to: taken into account by defining the turbine effi-
ciency. The primary advantageof writing the sec-
W = - 2 (h, + ex,)mi ond law in an equation (Eq. 4) rather than the
I
usual inequality is its usefulness in analyzing
= ml(h + e J l n - (h + e,)~ut] processes and cycles in a direct, quantitative,
manner, similar to the first-law analysis.'
W=m h+-+z
[( % )I; - -
Eqs. 1and 4 thus provide quantitative means
of examining all processes encountered in
power-plant analysis regardless of the fluids
13)
used or the specific cycle employed.
COMBUSTION
Steam Power-PIacS Design

CARNOT CYCLE The classic Carnot cycle is such, theli, that no


other can have a better efficiency between the
In 1824, Sadi Carnot, a French engineer, pub- specified temperature limits than the Carnot
.lished a small, moderately technical book, Re-
. value. Other cycles may equal it, but none can
flections on the Motive Power of Fire.z Carnot exceed it.
made here three important contributions: the
concept of reversibility, the concept of a cycle,
and the specification of a heat engine produc- Carnot efficiency = 3 = 1 - -T,
ing maximum work when operating cyclically Th Th,
(7)
between two reservoirs each at a fixed
temperature.
The Carnot cycle consists of several reversible where T, is \he temperature of the heat source
isothermal and isentropic processes, which and T, is the temperature of the heat sink, all in
may be viewed as occurring in either the non- terms of absolute temperature.
flow or flow device shown in Figs. 1A and 1B. Practical attempts to attain the Carnot cycle
In the first instance, the heat source and sink encounter irreversibilities in the form of finite
are placed in contact with the device to accom- temperature differences during the heat-trans-
plish the required isothermal heat addition fer processes and fluid friction during work-
(a-b) and rejection (c-d) respectively. The insu- transfer processes. The compression process
lation shown replaces the heat reservoirs for ex- d-a, moreover, is difficult to perform on a two-
ecuting the reversible adiabatic processes phase mixture and requires an input of work
involving expansion (b-c) and compression ranging from a fifth to a third of the turbine out-
(d-a). The process characteristics for good heat put. When realistic irreversibilities are intro-
transfer and work transfer are not the same and duced, the Carnot cycle net work is reduced;
are partially in conflict; Fig. lB, therefore, the size and cost of equipment increase.. Conse-
shows a flow system for executing the Carnot quently, other cycles appear more attractive as
cycle with the work and heat-transfer processes practical models. 3
assigned to separate devices. For both nonflow In relation to the Carnot efficiency, the high-
and flow systems, the state changes experi- temperature heat source cannot be defined in
enced by the working fluid are shown in the terms of maximum temperature. Instead, the
temperature-entropy diagram of Fig. 1C. weighted average of the temperature of the

High-Temperature
'
Heat Source

Fig. 1 Carnot cycle


COMBUSTION
Steam Power-Plant Design
- -
working fluid must be calculated, involving the sion work to a negligible amount, and makes
heating of the feedwater as it leaves the last the Rankine cycle less sensitive than the Carnot
heater, and the evaporation, superheating, and cycle to the irreversibilities bound to occur in
reheating processes. an actual plant. As a result, when compared
with a Carnot cycle operating between the same
RANKINE CYCLE
temperature limits and with realistic compo-
The cornerstone of the modern steam power nent efficiencies, the Rankine cycle has a larger
plant is a modification of the Carnot cycle pro- net work output per unit mass of fluid circu-
posed by W. J. M. Rankine4, a distinguished lated, smaller size and lower cost of equipment.
Scottish engineering professor of thermody- In addition, due to its relative insensitivity to
namics and applied mechanics. The elements irreversibilities, its operating plant thermal effi-
comprising the Rankine cycle are the same as ciencies will exceed those of the Carnot cycle.
those appearing in Fig. 1B with one exception:
REGENERATIVE RANKINE CYCLE
because the condensation process accompany-
ing the heat-rejection process continues until Refinements in component design soon
the saturated liquid state is reached, a simple brought power plants based on the Rankine cy-
liquid pump replaces the two-phase compres- cle to their peak thermal efficiencies, with fur-
sor. The temperature-entropy and enthalpy- ther increases realized by modifying the basic
entropy diagrams of Fig. 2 illustrate the state cycle. This occurred through increasing the
changes for the Rankine cycle. With the excep- temperature of saturated steam supplied to the
tion that compression terminates (state a) at turbine, by increasing the turbine inlet temper-
boiling pressure rather than the boiling temper- ature through constant-pressure superheat, by
ature (state a'), the cycle resembles a Carnot cy- reducing the sink temperature, and by reheat-
cle. The triangle bounded by a-a' and the line ing the working vapor after partial expansion
connecting to the temperature-entropy curve in followed by continued expansion to the final
Fig. 2A signify the loss of cycle work because of sink temperature. In practice, all of these are
the irreversible heating of the liquid from state a employed with yet another important modifica-
to saturated liquid. The lower pressure at state tion. In the previous section, the irreversibility
a, compared to a', makes possible a much associated with the heating of the compressed
smaller work of compression between d-a. For liquid to saturation by a finite temperature dif-
operating plants it amounts to 1 percent or less ference was cited as the primary thermody-
of the turbine output. namic cause of lower thermal efficiency for the
This modification eliminates the two-phase Rankine cycle. The regenerative cycle attempts
vapor compression process, reduces compres- to eliminate this irreversibility by using as heat

T
QA=HeatAdded=hb - h a
Q R = Heat Rejected =hc- h d
PW=PumpWork=ha-hd
W=NetWork = h b - h c - P W
17 = Thermal Efficiency = W
QA
S - - s
(A) Temperature-Entropy (B) Enthalpy-Entropy
(Mollier)
Fig. 2 Simple Rankine cycle (without superheat)
COMBUSTION
- Steam Power-Plant Design

Fig. 3 Idealized regenerative Rankine cycle

sources other parts of the cycle with tempera- generative heating" which is basic to all regen-
tures slightly above that of the compressed liq- erative cycles. Though thermodynamically
uid being heated. Fig. 3 is an idealized form of desirable, the idealized regenerative cycle just
such a procedure. described has several features which preclude
The condensed liquid at f is pumped to the its use in practice. Locating the heat exchanger
pressure P;, passes through coils around the around the turbine increases design difficulties
turbine, and receives heat from the fluid ex- and cost. Even if these problems were solved,
panding in the turbine. The liquid and vapor heat transfer could not be accomplished revers-
flow counter to one another and, by reversible ibly in the time available; further, cooling as de-
heat transfer over the infinitesimal temDerature scribed causes the vapor to reach excessive
difference d,, the liquid is brought to the satu- moisture content.
rated state at T, (process b-c) and then rejects The scheme shown in Fig. 4 permits a practi-
heat at the constant temperature T, (process cal approach to regeneration without encoun-
e-f). Such a system, by the second law, will have tering these problems. Extraction or "bleeding"
a thermal efficiency equal to a Carnot cycle op- of steam at state c for use in the "open" heater
erating between the same temperatures. avoids excessive cooling of the vapor during
This procedure of transferring heat from one turbine expansion; in the heater, liquid from
part of a cycle to another in order to eliminate the condenser increases in temperature by AT.
or reduce external irreversibilities is called "re- (Regenerative cycle heaters are called "open" or

Turbine

1kiP2
AT
S
(B) Temperature-
(A) Flow Diagram Entropy Diagram
Wp, =Workof First Pump Wp2=Work of Second Pump

Fig. 4 Practical single-extraction regenerativecycle

1-5
COMBUSTION
Steam Power-Plant Design

"closed" depending on whether hot and cold REHEAT CYCLE


fluids are mixed directly to share energy or kept
separate with energy exchange occurring indi- The use of superheat offers a simple way to
rectly through the use of metal coils.) improve the thermal efficiency of the basic
The extraction and heating substitute the fi- Rankine cycle and reduce vapor moisture con-
nite temperature difference AT for the infinites- tent to acceptable levels in the low-pressure
imal dT used in the theoretical regeneration stages of the turbine. But with the continued in-
process. This substitution, while failing to real- crease of steam temperatures and pressures to
ize the full potential of regeneration, halves the achieve better cycle efficiency, in some situa-
temperature difference through which the con- tions available superheat temperatures are in-
densate must be heated in the basic Rankine cy- sufficient to prevent excessive moisture from
cle. Additional extractions and heaters permit a forming in the low-pressure turbine stages.
closer approximation to tbe maximum effi- The solution to this problem is to interrupt
ciency of the idealized regenerative cycle, with the expansion process, remove the vapor for re-
further improvement over the simple Ran-kine heat at constant pressure, and return it to the
cycle shown in Fig. 2. turbine for continued expansion to condenser
Reducing the temperature difference between pressure. The thermodynamic cycle using this
the liquid entering the boiler and that of the sat- modification of the Rankine cycle is called the
urated fluid increases the cycle thermal effi- "reheat cycle." Reheating may be carried out in
ciency. The price paid is a decrease in net work a section of the boiler supplying primary
produced per pound of vapor entering the tur- steam, in a separately fired heat exchanger, or
bine and an increase in the size, complexity, in a steam-to-steam heat exchanger. Most
and initial cost of the plant. Additional im- present-day utility units combine superheater
provements in cycle performance may be real- and reheater in the same boiler.
ized by continuing to accept the consequences Usual central-station practice combines both
of increasing the number of feedwater heating regenerative and reheat modifications to the ba-
stages. Balancing cycle thermal efficiency sic Rankine cycle. Fig. 5 is a temperature-
against plant size, complexity, and cost for pro- entropy diagram of a single-reheat regenerative
duction of power at minimum cost determines cycle with two stages of feedwater heating. For
the optimum number of heaters.5 large installations, reheat makes possible an

QA = (hc:ha)-(i-ml)(he-hd)
QR = (1-ml-m2)(hg-hh)
w = (hc-hd)+(l-ml)(he-hf)
+(l-mi-m2)(hf-hg)-PW

Q A = Heat Added
Q R = Heat Rejected
W =Work
PW = Pump Work
0 t = Thermal Efficiency

Fig. 5 Regenerative cycle with single reheat and two feedwater heaters
COMBUSTION
. Steam Power-PlantDesign

High-pressure Turbine Intermediate-PressureTurbine

-----------
3.770.707 Lb. 1316.9 h.653 Psia

To Point B

Main Condenser

490 P s ~ a
~ h 1.8=

h = enthalpy. Btullbm
F = deg Fahrenhe~t

Fig. 6 Reheat regenerative cycle, 600-MW subcritical-pressure fossil power plant (U.S. units)

1-7
COMBUSTION
Steam Power-Plant Design

Hlgh-Pressyre Turblne Intermediate-PressureTurbine

3.38 MPa abs


A h=4
h = enthalpy, kJ/kg

7 Reheat regenerative cycle, 600-MW subcritical-pressurefossil power plant (SI-metric units)


COMBUSTION
Steam Power-Plant Design

improvement of approximately 5 percent in Philadelphia Electric Company's Eddystone


thermal efficiency and substantially reduces Unit 1, a double-reheat supercritical-pressure
the heat rejected to the condenser cooling unit with original outlet steam conditions of
water.6 The operating characteristics and eco- 5300 psig, 1210F (36.5 MPa gage, 654OC), was
nomics of modern plants justify the installation the high-water mark of cycle efficiency for con-
of only one stage of reheat except for units oper- ventional (non-binary cycle) steam plants.
ating at supercritical pressure. Although later operating at lower steam condi-
Figs. 6 and 7 show a flow diagram for a 600- tions, it produced electrical output with an in-
MW fossil-fueled reheat cycle designed for ini- put of less than 8200 Btu per kilowatt hour,
tial turbine conditions of 2520 psig and 1000F corresponding to an overall thermal efficiency
(17.4 MPa gage and 538C) steam. Six feed- of about 42 percent.
1
water heaters are supplied by exhaust steam
from the high-pressure turbine and extraction COGENERATIVE STEAM CYCLES
steam from the intermediate and low-pressure
turbines. Except for the deaerating heater In many instances, power and thermal-
(third), all heaters shown are closed heaters. energy needs may be combined in a single
Three pumps are shown: (1)the condensate power plant which will operate at a high annual
pump which pumps the condensate through oil load factor and higher thermal efficiency than
and hydrogen gas coolers, vent condenser, air obtainable by addressing the needs separately.
ejector, or vacuum pump, first and second Such a combined heat-and-power arrangement
heaters, and deaerating heater; (2) the conden- is termed a cogeneration plant, which will be
sate booster pump which pumps the conden- discussed in detail in the following sections.
sate through fourth and fifth heaters; and (3) For heating service (such as in a district-heat-
the boiler feed pump which pumps the conden- ing system),the steam is generated at a pressure
sate through the sixth heater to the economizer and temperature sufficiently high that the ex-
and boiler. The mass flows noted on the dia- haust from the steam turbine is at steam condi-
gram are at the prescribed conditions for full- tions suitable for delivery to the steam mains or
load operation. heat exchangers (for a high-temperature water
system) and distribution to the users. The needs
SUPERCRITICAL-PRESSURE CYCLE of industrial plants for process steam may be
A definite relationship exists between oper- met by similar arrangements using either tur-
ating temperature and optimum pressure bine exhaust or extracted steam from an appro-
of a cycle. The supercritical-pressure cycle is in priate turbine stage. The selection of optimum
use worldwide to obtain the highest possible exhaust or extraction conditions will depend
thermodynamic efficiencies with fossil-fuel on the proportions of power and process heat
steam-generation equipment. required of the particular plant. Process-steam
A regenerative-reheat cycle is used with 6 to requirements are usually in the low-pressure
8 stages of feedwater heating and, because of range with modest superheat required if at all;
the high inlet temperature and pressure, two consequently, initial steam pressure and tem-
stages of reheat can be justified and have been perature will be well within the limits of cur-
used in several installations. Figs. 8 and 9 show rent technology.
a typical supercritical-pressure steam turbine Cogenerative steam cycles have been applied
heat balance. Seven feedwater heaters are over a wide range of capacities extending from
shown with steam extractions from the various small industrial and institutional power plants
turbines supplying energy for the regenerative to large central stations serving the electrical
heating processes. For such supercritical pres- and heating needs of a metropolitan center or
sure plants, cycle efficiencies exceeding 40 per- the power/process requirements of a major
cent have been reached. petro-chemical installation. The food-process-
COYBrnTION
Steam Power-Planthsign

H~gh-Pressure
Turbine Int?n'tediate-Pressure
Turbine

h = enthalpy. Btullbm

I I
Flg. 8 Reheat regenerativecycle, 800-MW supercritical-pressurefossil power plant (U.S. units)
COMBUSTION
- Steam Power-PlantDesign

Primary Steam
High-PressureTurbine Inbnnedlate-PressureTurbine
I I
---------)-----
r 6 9 6 0 kg. 3292 h. 25 34 MPa gage 538 C
I
I
-----------
604 0 kg. 2935 h 4 93 MPa abs

126kg.3144h
To SSR

To Point A 2931 h
To SSR

1,

lO2kPa
Economizer To Condenser
I
800 834 kW

From Feed-Pump

h = enlhalpy. kJlkg

Fig.9 -Reheat regenerative cycle, 800-MW supercritical-pressure fossil power plant (SI-metric units)
COMBUSnON
Steam Power-Plant Design

ing, chemical, and paper industries are three REGENERATIONVERSUS COGENERATION:


THE THERMODYNAMICS
among the many industrial users of such cycles.
The principal purpose of a regenerative
COGENERATION: THE DEFINITION
power-plant cycle is the high-efficiency genera-
Cogeneration is the simultaneous production tion of electrical power, accomplished by ex-
of power (usually electricity) and another form tracting steam at multiple points from a steam
of useful thermal energy (usually steam or hot turbine, ahead of the condenser. As shown in
water) from a single fuel-consuming process. It the diagrams of Figs. 6 through 9 of this chap-
is also referred to by the terms combined heat ter, the extracted steam-flows heat the feedwater
and power (CHP), combined power and pro- in successive steps as it returns to the boiler
cess, or simply power/process. The fuel can be from the condenser. As described earlier, regen-
burned in a boiler, a gas turbine, or a diesel en- erative cycles are essentially closed cycles, as
gine. It is important to realize that cogenera- the working fluid constantly recycles through
tion, as a practical and time-honored the heat-exchange equipment. Makeup water is
technology, is a matter of design of cycles and added only to replace steam or water lost in
their piping and valving systems, and not of ba- gland sealing or other outward leakage. As also
sic differences in the boilers, turbines (steam or described earlier, single or double reheating
gas) and heat exchangers that are made part of can be added to the basic regenerative cycle to
the cycles. further enhance thermal efficiency. In large
A typical steam-based cogeneration plant electric-utility plants, 6 to 8 stages of feedwater
burns fossil fuel (coal, oil, or natural gas, for ex- heating are used to minimize heat rejection
ample) or a renewable resource such as plant or to the condenser, and there is'a minimum of
animal waste material (biomass) to generate one stage of reheat.
steam which is piped to a non-condensing tur- Although a cogenerative pcwer-plant cycle
bine to drive a generator. Since the steam uses a similarly efficient arrangement of cycle
leaving the turbine retains much of its energy, elements (steam generator, turbine or turbines,
it can be used further for heating or other feedwater heaters and other heat exchangers,
heat-absorbing applications. For instance, and some modified form of condenser) it has a
every naval or merchant ship that uses heat dual purpose. Not only does a cogeneration cy-
for cooking, space-heating, or laundry operat- cle produce electrical or shaft power, it also
ion, in addition to generating electricity and generates a stream or streams of thermal energy
driving propellers, is a cogenerator. for use in a heat-absorbing or heated-fluid-
The efficiencies of cogenerating steam and consuming process, all from the combustion of
electricity can result in significant energy-cost the same fuel.
saving for facilities as varied as a manufactur- By minimizing, or completely eliminating,
ing or processing plant, an office or apartment the energy loss that occurs in the water-cooled
complex, or a hospital. Steam or hot water can or air-cooled condenser of a regenerative cycle,
be used for heating or cooling of buildings, or cogenerative cycles can have significantly
for industrial processes. The power can be to higher overall thermal efficiencies than conven-
compress air or gas for a variety of industrial tional condensing regenerative systems. The
purposes. Cogenerated steam can be injected level of efficiency attained depends on the heat-
into the ground in steam-flood (enhanced oil to-power ratio and the type of process forming
recovery) projects, or can be used as the heat the basis for the cycle.
source in absorption-type refrigeration plants. Like a regenerative cycle, a cogenerative cycle
If the amount of energy produced exceeds the can be "closed'', with the heat energy being
cogenerator's own needs, either steam1 added to and taken from it in various pieces of
hot water, electricity, or both, can be sold for equipment. A cogenerative cycle can also be
use by others. semi-closed: in such a semi-closed or "expor-
COMBUSTION
Steam Power-Plant Deslgn

tive" cycle, some of the &acted heat leaves the (as Q,), so that QR = Q, + QNu,where a, is
cycle with fluid that is never returned from the "non-useful" heat rejected; there is, then, less
heat-using process. Substantial amounts of emphasis on maximizing thermal efficiency.
makeup water, then, may be needed in the But because electric power is a valued product
semi-closed cycle to allow for the loss of the (of greater value than useful heat rejected), a co-
treated water during the process. generator still may want to produce that elec-
Regenerative cycles are somewhat standard- tricity at minimum cost, so it is important to be
ized, differing only slightly from one cycle de- aware of the steps taken to improve conven-
signer to another. In contrast, cogeneration tional plant efficien~y.~
systems are unlimited in thermodynamic possi-
EFFICACY OF COGENERATION PLANTS
bilities, and thus in the configuration and siz-
ing of all the cycle elements.-To a significant There are many approaches to mathemati-
extent, then, the process determines the de- cally defining the true value of any given co-
sign, arrangement, and cost of components, as generative cycle. The energy utilization factor
well as their pressure and temperature levels. (EUF)of Porter and Mastanaiah9 is expressed as
Since in many geographical areas cogenerators the sum of the work-output (W) and the useful
are unregulated by public agencies in many as- rejected heat (QU)divided by the fuel fired (F),
pects of their operation, they are similarly un- all in consistent energy units. But since the
limited in economic possibilities. ' work (or electrical power) produced and the
useful heat will usuallv be of different mone-
Achieving High Thermal Efficiency tary value, the EUF is not satisfactory as a crite-
in a Fossil Power Plant
rion of economic performance. Horlock and
A principal thrust of the study of the thermo- others (references 8 through 12) have written
dynamics of fossil-fired power plants is the extensively on the subject of comparing the
maximization of thermal efficiency: that is, the economic values of various cogenerative cycles.
most efficient production of poker (usually
CLASSIFICATION OF
electrical) from a supply of fuel that has chemi- COGENERATION PLANTS
cal energy. In attempting to achieve such high
thermal efficiency, the designer of a conven- Cogeneration projects can be classified as ei-
tional Rankine cycle raises the temperature of ther topping or bottoming systems. In a topping
heat supply to a turbine and lowers the rejec- system, the steam produces electricity first and
tion temperature, the latter being done by drop- all or a part of the exhausted thermal energy is
ping the condenser pressure. The temperature then used in an industrial process, or to provide
of heat to the turbine is increased by space heating or cooling. Bottoming cogenera-
raising boiler pressure tion systems use the waste heat from industrial
reheating between turbine stages, and processes or other high-temperature thermal
processes to generate electricity by generating
regeneratively heating the boiler feedwater, steam in a waste-heat (heat-recovery)boiler.
all as described in previous sections. Fig. 10 shows a schematic diagram of a basic
Whether such modifications to achieve closed power/process cycle using a backpres-
higher efficiency justify the extra capital re- sure turbine. After superheated steam is gener-
quired is a matter for economic study; thermo- ated at a suitably high pressure, it is admitted to
dynamics is seldom the sole criterion. In the turbine, does useful work (W,), and emerges
maximizing the work output (W) for a given usually in the superheated state, c. After desu-
amount of fuel fired (F), the designer mini- perheating, saturated steam, d , enters the
mizes the heat rejection from the plant (QR). heater and is entirely condensed. Because the
The designer of a cogeneration cycle is inter- steam required for power generation will not
ested in using some of the heat rejected usefully equal at all times that required for process
' COMBUSTION
Steam Power-Plant Design
-
I

ler

(A) Flow Diagram (B) Enthalpy-Entropy


(Mollier)Diagram
. Closed p o w e r l p r ~ ~ cogenerative
~ i g 10 e~s cycle using a backpressureturbine

work, some means of controlling the exhaust cycle that it is part of. That is, the configuration
steam pressure must be employed to avoid vari- and sizing of a boiler are based on
ations in the pressure and, therefore, the steam generating a given amount of primary steam
saturation temperature. The control method de- and reheat steam (if any) at a specified temper-
pends on the circumstances. An ordinary cen- ature and pressure.
trifugal governor fitted to the backpressure beginning with feedwater entering at a stated
turbine will cause the quantity of available ex- temperature
haust steam to be controlled by the load on the with the reheat flow to the boiler being at a
turbine. Should the available exhaust be too given temperature and heat content
small, live steam may be passed through a re- burning a particular fuel or fuels
ducing valve into the desuperheater. If the The quantity of makeup water required by the
quantity of exhaust steam exceeds require- cycle will of course affect the amount of chemi-
ments, then the excess steam may be blown to cals needed for internal treatment of the boiler
atmosphere, into an accumulator, or into a feed water. But it is the cycle or process equipment
tank through the spill valve. ilhcild of and following the boiler that places
Figs. 11 and 1 2 illustrate a typical cogenera- the generating plant in one category or the
tion system based on the steam topping cycle. It other. The actual regeneration or cogeneration, ,
uses controlled-pressure automatic steam ex- then, takes place after the boiler steam-outlet
traction and a controlled-backpressure turbine. valves, resulting from the engineered ways in
This example has three closed feedwater which the steam or hot-water flows are used.
heaters plus a deaerating heater.13 The two types of cycles are, therefore, not
Such a steam-topping cogenerative cycle is rnutually exclusive: there are many regenera-
suitable when large quantities of process steam tive-cogenerative cycles in long-term operation
and electricity are called for. This type of plant throughout the world, from small shipboard
provides great potential for large industrial and installations to major district-heatinglpower-
power-producing installations, and incorpo- producing plants in Europe and America.
rates steam generators of the types described in
Chapter 8 of this text. COMBINED GAS-TURBINEISTEAM TURBINE
POWER CYCLES
- - -
STEAM-GENERA~ORDESIGN FOR A .SPECIFIC CYCLE
A combined cycle is understood to be (at least
in America) any one of a number of configura-
The design of a steam-generating unit is in- tions of gas turbines, steam generators (or other
dependent of the regenerative or cogenerative heat-rec&ery equipment), and steam turbines
COMBUSTION
Steam Power-PlantOIIign

Steam Turblne

b66,900 kW
Generator Output

'*
73.838 Lb
449 Psla
663 F
-
98,970 Lb
283 Psla
-
570 F 98,573 ~b
735 Ps~a 110 Psla

73,838 Lb 98,970 Lb 98,573 Lb


397 0 h 328.3 h 395 6 h
6w.000 Lb, 1M) F
7 t +To Deaerator

Fig. 1 1 Heat balance of a steam-topping cogenerative cycle (U.S. units).

Steam
Steam Turblne
I
I
kg = mass flow, kg/s
h = enthalpy, kJ/kg
C = degrees Celsius. 1
I

14.03 MPa gage


538 C b 66,900 kW

14.38 MPa gage Generator Output


(Or-)

93.2 kg, 4.48 MPa abs, 382 C


235 C
To Steam Generator
Economker

Condenaate Return
75.6 kg, 71 C
tTo Dellerator
L
Fig. 12 Heat balance of a steam-topping cogenerative cycle (SI-metric units).

1-15 A!!
COMBUSTION
Steam Power-PlantDesign

assembled for the improvement of cycle effi- pressure (supercharged or turbocharged)


ciency in the power-generation process.14 arrangements.
Analogous to mercurylsteam, potassium1 1. Gas turbine plus unfired steam generator
steam, or steam/ammonia cycles, the combined 2. Gas turbine plus supplementary-fired steam
gaslsteam power cycle is a binary cycle, al- generator.
though not normally thought of as such.15~16As
3. Gas turbine plus furnace-fired high-pressure,
a kind of marriage between the Brayton and
high-temperature steam generator.
Rankine cycles, it has the usual intent of in-
creasing t h e working-fluid temperature 4. Supercharged furnace-fired steam generator
through the high-temperature capabilities of plus gas turbine.
the internal-combustion (gas) turbine while us- The first three are essentially atmospheric-
ing the "external-combustion" (steam) turbine pressure designs, which use the heat energy, and
to reduce the temperature of heat rejection. The sometimes the oxygen, contained in the exhaust
penalty involved is the required work of com- of a combustion gas turbine; they take advantage
pression performed by the gas turbine. of the fact that the gas turbine is otherwise penal-
Note that such a cycle can be cogenerative if ized by the substantial heat loss associated with
the steam turbine is a non-condensing back- elevated stack-gas temperatures (in excess of
pressure type that further uses the exhaust 800F or about 430C). They are described in
steam for space heating, oil-field steam flood- greater detail in Chapter 8.
ing, or an industrial process. A cycle is not co- Gas Turbine Plus Unfired Steam Generator
generative if the final output of both turbines is
electrical power only, with no usable or used In this concept, a heat-recovery steam genera-
thermal byproduct. l7 tor (HRSG) is installed at the discharge of a gas
Gas turbines with integral combustion sys- turbine to recover the energy in the gas-turbine
tems fire natural gas, jet fuel, light distillate oil exhaust and supply steam to a steam turbine
or, with proper prefiring treatment, a wide (Fig. 13). All the fuel is fired in the gas turbine,
range of residual and crude oils. Open-cycle and the steam generator depends entirely on the
gas turbines commonly satisfy the peaking and gas turbine as its heat source. The steam genera-
reserve requirements of the power-producing tor is often designed for low steam pressures and
industry because of their quick-starting capa- temperatures, usually limited to approximately
bility and low installed capital cost. Their low 1500 psi and 900F.
thermal efficiency and use of prime fuels, how- Because the power from the steam turbine
ever, place them at economic disadvantage will be produced without any additional fuel
when operated for long periods of time. De- input and because there is only a small de-
pending on size, pressure ratio, and turbine in- crease in gas-turbine efficiency because of the
let temperature, heat rates ranging from 10,500 backpressure (draft loss] of the steam generator,
to over 14,000 BtuIkWhr (HHV) are obtained fir- the overall plant thermal efficiency will be im-
ing oil fuel in simple open-cycle machines; this proved over that of the open-cycle gas turbines.
corresponds to between 24 and 32 percent ther- Depending on the particular steam cycle and
mal efficiency on a high-heat-value basis. fuel, net plant heat rates below 9,000 BtuAWhr
(HHV) can be obtained (thermal efficiencies
above 38 percent, HHV basis).
TYPES OF COMBINED CYCLES
Gas Turbine Plus Supplementary-Fired Steam Generator
Combined-cycle installations can fall into
four broad classifications, primarily dependent Gas-turbine exhiuit contains as much as 18
on how the steam generator is used in conjunc- percent oxygen and may be used as an oxygen
tion with the gas turbine. There are both near- source to support further combustion. Therefore,
atmospheric-pressure and high-positive- amodification of the simple waste-heat applica-
COlCBUSTION
Steam Power-Plant Design

Fuel Fuel

'
Fig. 13 Gas turbine plus unfired heat-recovery Fig. 14 Gas turbine plus furnace-fired
steam generator (HRSG) steam generator

tion is the use of a supplementary firing system utilizes essentially all of the oxygen in the tur-
located in the connecting duct between the gas- bine exhaust to support further combustion.
turbine outlet and the inlet to the steam genera- Typical gas turbines operate with 250 to 400 per-
tor. The firing system will utilize a portion of the cent excess air and thus can support the combus-
oxygen contained in the gas-turbine exhaust and tion of approximately three'to four times as much
be selected to limit the maximum gas tempera- fuel in a downstream boiler as was burned in the
ture entering the steam generator to approxi- gas turbine. The majority of fuel can now be fired
mately 1400E in the boiler and 60 to 80 percent of thetotal plant
With a given gas-turbine size and this gas-tem- power generation will be supplied by the steam
perature limit, the steam generation can double turbine, with the remaining portion by the gas
that of a simple waste-heat application, and the turbine (Fig. 14).The gas turbine may be consid-
steam turbine will supply a greater proportion of ered as both an independent power supplier and
the plant load. The higher steam-generatorinlet a forced-draft fan for the boiler. Any of the high-
gas temperature will allow steam conditions to pressure, high-temperature steam conditions
be increased to levels of 2600 psig and 1000E utilized by modern steam turbines can be incor-
The steam turbine designs are nonreheat or re- porated into this combined cycle.
heat, and may be either condensing or noncon- And althoughthe gas-turbine fuel in the previ-
densing. For most arrangements the final steam ous arrangement is presently limited to gas and
conditions are primarily ba'sed on the steam-tur- oil, this cycle allows the use of any fossil fuel in
bine economics. Net plant heat rates of below the steam-generator.
8,000 BtukWhr (HHV) are possible with this Plant heat rates of 9,530 BtukWhr (HHV)have
combination of equipment (for thermal efficien- been obtained in a U.S. installation l8 ; thermal
cies above 42 percent, HHV). efficiencies higher than 36 percent (HHV) are
Gas Turbine Plus Furnace-Fired Steam Generator
now possible.

The previous cycle used only a small portion of


the available oxygen in the gas-turbine exhaust.
:~~G",~~~~~~rnace-Fired
Another adaptation is the design of aplantwhich Another configuration for a combined cycle
COMBUSTION
Steam Power-Plant Design

I Exhaust
INDUSTRIAL
POWER-PLANT DESIGN
This section focuses attention on the overall
design elements of the industrial or institu-
tional power plant, exclusive of the marine pro-
pulsion plant. Many of these elements are
involved also in the design of more complex
utility power plants, which is the subject of the
next section. In addition, other chapters of the
book will cover specifics of the design of boilers
Turbine together with their various components and
supporting systems.
The most elementary type of industrial power
plant incorporates a boiler as a heat source and
a heating system as a load to dissipate the ther-
mal energy released by fuel fired to the boiler.
From this concept onward, the industrial or in-
Fig. 15 Supercharged furnace-fired
steam generator plus gas turbine
stitutional power plant may encompass various
degrees of complexity, as discussed in the pre-
vious section on cogenerative steam plants. Cy-
includes the installation of a steam generator be- cles may range from the very simple, with low
tween the air compressor and the gas turbine thermal efficiency, to the most complex and ef-
(Fig. 15). The air compressor serves as a forced- ficient arrangements as proposed for central
draft fan and pressurizes the boiler, where all the stations, including combinations of steam and
fuel is fired; the products of combustion, having gas turbines. Boiler size may extend from the
been partially cooled within the boiler complex, generation of a few thousand pounds of steam
are then discharged through a gas turbine. Addi- per hour to several million in large installa-
tional heat is recovered by heat exchangers in- tions, and the same spread is true for steam tur-
stalled at the exhaust of the gas turbine. They are bines for industrial power generation. In short,
used as economizers or feedwater heaters. the industrial power plant can be used to illus-
Although conventior~allyfired gas turbines trate virtually every aspect of the thermal engi-
require high excess-air quantities, the firing neering involved with a fossil-fueled plant.
system for the supercharged furnace is de- TRENDS IN POWER-PLANT DESIGN
signed to operate with excess-air levels com-
mensurate with conventional units and the Up to this point the' term industrial power
air compressor is selected for such an air plant has been used without definition. In en-
capacity. The steam turbine supplies the ma- gineering terms, there is no physical difference
jority of the plant electrical generation, with between industrial and electric-utility central-
the gas turbine either selected to provide suf- station equipment, as is demonstrated in Chap-
ficient power to drive the air compressor ter 8: Steam Generators for Process UseIPower
(Velox or turbocharged cycle) or sized to supply Production. At one time, power generation was
additional power generation. Chapter 9 in- a part of virtually every industrial power plant,
cludes a description of the pressurized fluid- but this changed for several reasons:
ized-bed combustor (PFBC) employed in this 1. The public-utility systems are securely and
type of cycle, which is in active development effectively interconnected electrically, and pro-
in several countries.19 vide highly reliable service.
COMBUSTION
Steam Power-Plant Design

2. The cost of purchased electric power has re- plant is being built may have an engineering
sisted the effects of inflation better than almost staff of sufficient size and experience to make
any other commodity, largely through the econ- preliminary studies, develop the detailed de-
omies-of-scale in the large centralized power sign, evaluate bids, award contracts and- super-
plant. vise construction. But most often, a consulting
3. The demands for additional electrical power engineer is called upon to perform one or more
have generally grown faster than the demands of these functions.
for thermal energy for space heating or process In any case, a preliminary report must be
use, thereby exceeding the capabilities of back- written to obtain authorization of capital funds.
pressure generation. Not only does this report consider the total in-
The end result was that the majority of indus- vestment, but it also evaluates outlays for such
trial power plants built after World War I1 and items as operatjon, maintenance, depreciation,
until recently (with the enactment of the Public insurance, interest, and taxes. With its primary
Utility Regulatory Policies Act of 197B20)were emphasis on economic factors, the preliminary
for space heating and process steam. The excep- report must be written so as to be intelligible to
'
tions were in situations such as the following: those whose background may be in finance or
1. Coordinated demands for steam and power,
law rather than engineering.
accompanied by the availability of waste fuels A salient part of the preliminary report is the
suitable for combustion in boilers. Examples charting of anticipated loads for different con-
are found in the pulp and paper, chemicals, pe- ditions, such as daily load curves for winter
troleum-refining, food-processing, and steel and summer, weekdays, Saturdays, Sundays
industries. These five industries account for and holidays. Special consideration must be
almost three-quarters of all manufacturing given to any unusual operating conditions and
steam demand; in them, steam use is usually to the time of peak loads. If a manufacturing op-
the limiting factor in h e technical potential of eration is involved and if it incorporates some
such cogeneration. '3 process equipment with marked swings in de-
mand, a detailed study should be made of the
2. A balanced growth of electrical and steam- nature and frequency of the operation and its
heating requirements. This is found in many in- steam and power demands. As a part of load
stitutional settings, such as universities, studies of existing plants, the peaks and valleys
hospitals, penal institutions, and some district- should be investigated with the objective of de-
heating schemes in metropolitan areas. Here, termining whether corrective measures might
backpressure cogeneration can have marked be taken to level out the load to increase effec-
advantages. tive output.
It is estimated that, in the late 1970's, less Typical load curves, as shown in Figs. 16, 17,
than 5 percent of American electrical generat- and 18, help to determine the size of such
ing capacity was in the form of cogeneration. It equipment as boilers, turbines and auxiliaries.
is now recognized that, where it is applicable, Studies must then be made of the capability of
cogeneration is an important means of more ef- the equipment to meet not only the conditions
fectively using all kinds of fuels in industrial- plotted on the basis of past experience but also
power situations. those forecast for a limited time in the future.
POWER-PLANT STUDIES Load curves should be made for both power and
steam requirements, and due consideration
The starting point of an industrial power should be given to the relative growth of power
plant is an engineering study. Power and steam and steam in the future.
loads must be ascertained and costs estimated The engineer with the assignment to study
before construction can be considered. In some the power and steam requirements must be-
instances, the organization for whom the power come thoroughly acquainted with the operating
. COILBUSTION
Steam Power-Plant Design

Typical Winter Load

- A . M . - LP.M.-
Time
I I
Fig. 76 Summer and winter heating loads in a high-temperature water installation

characteristics of the proposed installation or independent power producer, the greatest regu-
the extension to existing facilities. In the case of latory influences on project feasibility will
a hospital supplied by an isolated power plant, most likely stem from regulations in the areas
dependability of service is of paramount impor- of electric power exchanges, fuel use, and envi-
tance. The same may be true of an industrial ronmental quality. Of these areas, electric
process of a continuous nature, where an emer- power exchanges are subject to a combination of
gency may be very costly and possibly haz- state and federal regulation; fuel use is regu-
ardous as well. On the other hand, some lated primarily by the federal government; and
installations may have firm electrical connec- environmental quality is likely to involve regu-
tions to outside sources. Here, the design em- lation at the federal, state, and local levels.
phasis might be on continuity of service Based on the definition of the problem and
despite outage of generating plant equipment. the detailed technical analysis, then, the pre-
In other situations, power and heating interrup- liminary report should offer conclusions and
tions may be inconvenient, but may not cause recommendations. These should include esti-
severe problems or losses. mates of the required capital investment along
Federal, state and local regulations affect the with operating costs and fixed charges. In most
installation and operation of all industrial fa- reports of this nature there will be a number of
'
cilities. In the case of a cogeneration plant or analyses of economic alternatives, to aid man-

- Time Hours

Fig. 77 Widely fluctuating processing load curve Fig. 78 Load curves for backpressure
steam and power generation
COMBUSTION
Steam Power-PlantDesign

agement in making decisions prior to authori- cost of plant services, including power
zation of construction. ifixed charges on fuel-handling and burning
DESIGN INVESTIGATIONS equipment
Detailed design follows acceptance of the
preliminary engineering study and authoriza- Careful study of these outlays, adjusted to an
tion to proceed. Some topics of the preliminary annual basis, will provide a foundation for fuel
report are investigated more thoroughly as part choice. Other less tangible factors should also
of the design process. The studies are coordi- be evaluated, such as reliability of supply, fu-
nated with the purchase of materials and equip- ture availability, individual fuel cost trends,
ment and the making of detailed architectural ease of conversion from one fuel to another, and
and construction drawings. extent of future plant expansion.
The number and scope of design investiga- Charges for byproduct fuels depend upon the
tions will vary from plant to plant. As a very method of accounting for process and power-
minimum, decisions must be made as to choice plant costs. In some industries, such as steel
of cycle, selection of fuel, number and types of and petroleum refining, byproduct fuels must
auxiliaries, extent of instrumentation and auto- be either burned @ power-plant boilers as fast
matic control, and plans for isolated or inter- as they are produced or consumed as atmos-
connected operation. pheric flares. Other byproduct fuels, such as
some types of wood and plant refuse, may be
CHOICE OF CYCLE stored for limited periods. The economics of
In the de$ign of a new plant, careful consid- such byproduct fuels can become very complex
eration must be given to the choice of thermal or be as simple as the necessity of disposing
cycle. If space-heating and process use consti- of them immediately by some form of com-
tute the entire load, then it is possible to make a bustion. In many instances, conventional solid,
choice between a steam and a high-temperature liquid, or gaseous fuels must be fired to
water cycle. Large industrial power plants with supplement byproduct fuels.
substantial process and electric loads are likely CHOICE OF AUXILIARIES
to make use of more advanced cogenerative cy-
cles, as covered above. No steam power plant is complete with
CHOICE OF FUEL merely a boiler and a turbine. Auxiliary equip-
ment is required in the form of fans, pumps,
Selection of fuel is based on a combined in- heaters, tanks and piping. In some instances,
vestigation of availability, cost, and operating heat-recovery equipment is added to boilers,
requirements. Most industrial power plants use and generally some form of water-conditioning
solid, liquid or gaseous fuels, either singly equipment will be required. Both fuel and ash
or in combination. Although generally these handling systems are necessary if solid fuel is
are commercially available fuels, sometimes fired. If all electrical requirements cannot be
they are byproducts of manufacturing satisfied through backpressure operation, a
and processing. condenser is a necessity.
When comparing fuel costs, the following The designer of an industrial power plant
factors should be tabulated: must investigate to some degree each of these
H base price of fuel auxiliaries. In the case of tanks and piping, the
H cost of fuel, delivered
investigation may be to determine optimum
sizes and selection from among alternative pip-
cost of handling and reclaiming ing and equipment arrangements. In other
cost of labor, including firing and disposition cases, the designer may decide only whether to
of refuse use the auxiliary equipment.
COMBWnON
Steam PowIT-PIant Design

Motor versus Steam-Turbine Drives data which must be available at all times to the
In most industrial power plants, the designer operator and must select the correct instru-
has a choice of steam-turbine or electric-motor ments to provide this information. Some of
drive for rotating auxiliaries. Electric drives are these instruments will be of the indicating type,
used commonly for such items as forced- and while others will record data over prolonged
induced-draft fans and pumps for boiler feed, periods. Both types are essential; some overlap-
condensate and fuel oil. Yet the possibilities ping and duplication of readings can be justi-
and advantages of turbine drives should not be fied because of the differing uses for operating
overlooked. These may contribute to improve- and recorded information.
ment of the plant heat balance and assure conti- Every industrial power plant will incorporate
nuity of boiler plant operation in the event of instrumentation to indicate boiler and turbine
power failure. Where more than one fan and loading. It is also common practice to provide
pump are installed for each plant auxiliary ser- instruments to show various steam and flue-gas
vice, the combination of motor and turbine temperatures, air and steam flow, feedwater and
drives becomes attractive, with provision for steam pressures, and electrical outputs. Chap-
automatic starting of the steam-driven auxiliary ter 13 describes the types of instrumentation
in the event of power failure. and controls currently being installed in indus-
Because continuity of service is absolutely trial power plants.
essential for t$e boiler feed pump, it is common
DRAWINGS AND SPECIFICATIONS
practice to provide a steam-driven pump for use
in the event of electric power failure. In addi- To build a power plant, drawings and specifi-
tion, provision may be made to start this pump cations must be prepared to obtain bids and ex-
automatically if there is a marked drop of pres- ercise proper supervision over purchasing and
sure in the boiler feed line. construction. The objective of such drawings
Unlike the case of the boiler feed pump, and specifications is to describe the work to be
the question of turbine drives for forced- and done, primarily from the point of view of the
induced-draft fans does not have a clear-cut results to be achieved. The engineer must use
answer. Consideration should be given to the extreme care to see that they are clear, concise,
probability of electric-power outage and the ne- and capable of but one interpretation. The
cessity for maintaining full-load output in the drawings describe the work graphically and di-
event of such outage. The economics of opera- mensionally while the specifications represent
tion must be weighed against the requirements verbal descriptions.
for service continuity. It is well to consider the specifications as the
rule book which governs the entire project. The
INSTRUMENTATIONAND AUTOMATIC CONTROL
drawings should indicate the location of equip-
Industrial power plants vary widely in their ment, including interconnecting piping and
use of instrumentation and automatic control. wiring. Between the two, the work to be done
Instrumentation may be installed as an aid to should be clearly set forth, with nothing essen-
operation, as a means of keeping records of use tial omitted and with a determined effort to
of fuel, steam and electricity, or for both pur- avoid inconsistencies and unnecessary overlap.
poses. Automatic controls may be specified to The specifications should set forth the func-
reduce operating personnel to a minimum and tions and limits of each item shown on the
to assist in maintaining operation at a high level drawings. By their very nature, specifications
of efficiency. are intended to be very detailed about what is to
Instruments assist in the operation of a power be done, even though they may include some
plant as well as in the collection of information general stipulation or conditions which relate
on the cost of steam and power consumption. to the work as a whole.
The designer must keep in mind the type of As an example, consider a piping system for
COMBUSTION
Steam Power-Plant Design

an industrial power plant. The drawings will cisions must be made at least that long before
_ show a piping layout, including detailed di- the capacity is needed.
mensions, and will indicate the pressure char- Management must find the best practicable
acteristics of the system. The specifications answers to four fundamental questions about
should list all design requirements: design the provision of additional capacity: When?
pressure and temperature; operating pressure How big? Where? What kind? In more formal
and temperature; the grade designation, some- language, the following steps must be under-
times called the schedule, of piping, fittings taken.
and valves; the type and pressure characteris- 1. Forecast of loads to determine timing and
tics of joints, including any special require- size of additions.
ments. These piping specifications should also 2. Selection of plant location.
contain provisions covering quality of materials
3. Selection of types of equipment.
and workmanship, including inspection and
acceptance requirements. Each step is the subject of a subsequent dis-
cussion and involves the careful weighing of
both economic and technical alternatives.
In the specifying of power-plant equipment, FORECAST OF LOADS
it is sometimes expedient to write a perfor-
mance specification, with only such descrip- The answers to When? and How big? are ap-
tions or physical limitations as are necessary to proached by making a forecast of future electric
provide for<the desired quality of materials and demands. Such activity is a continuous func-
workmanship. Within this framework, the man- tion in a major utility and is, necessarily, a mat-
ufacturer is given as much freedom as possible ter of judgment in interpreting company
to provide equipment which will best fulfill the records, economic trends, population shifts,
functional requirements of the installation. By technological changes and regulatory factors.
reason of specialized experience, a manufac- There are two significant characteristics of
turer frequently can best determine the detailed electric demand (usually called "load") in this
design of the particular equipment it supplies, connection: the peak load, which is,the maxi-
given all the factors for performing economic mum demand on the generating plant for a rela-
analyses of available alternates. tively short period, as 15 minutes or one hour;
and the average demand over a longer period,
usuallv a month or a vear. The ratio of the two is
ELECTRIC UTILITY called-the load factor and is typically in the
range of 40 to 60 percent. A system with a rela-
POWER-PLANT DESIGN tively high load factof is foitunate in that it
The objective of this section is to show the uses, on the average, more of its installed capac-
steps that must be taken and the decisions that ity profitably; it-spreads its investment costs
must be made in the preliminary design of a over a greater production than would be true of
central station for the generation of electric another system of the same size, having the
power. Most of the information applies equally same peak load, but with a lower load factor.
to installations being made by unregulated in- The high-load-factor system can therefore af-
dependent power producers. ford to spend more money for more efficient
Electric utilities are continuously thinking equipment that will reduce operating costs.
about generating facilities that must be in oper- The chief of these is the cost of fuel, expendi-
ation as much as ten or more years in the future. tures for which vary directly with station out-
The final permitting, design, and construction put. Improvements in station thermal efficiency
of new capacity will typically require not less are one way to reduce the outlay for fuel.
than four years. For these reasons, all basic de- The records of electric demands are usually
COMBmnON
Steam Power-Plant Design

kept in three major classifications: residential, its generating capacity, even if onlydfor a
commercial, and industrial. Special records ap- few minutes.
plying to unusually large users of power are Reserve for scheduled outages is generating
also available. capacity that is installed on the system but is
The forecaster studies the history of each not necessarily in operation at the time of peak
type of load but chiefly gathers all available load. Such reserve is needed because equip-
data on the growth of the area which is being ment must be inspected and overhauled at reg-
studied. The forecaster watches population ular intervals. The amount of this reserve must
shifts, growth of suburban shopping centers, be not less than the size of the largest unit that
trends toward air conditioning and electric will be overhauled during the peak-load season.
heating, changing processes in industry, devel-
opment programs to attract new employers, sta- DETERMINING SYSTEM RESERVE REQUIREMENTS
tistics on per capita use of electricity; in short,
every factor that bears on the future use of elec- A simplified example will illustrate the point.
trical energy in the area under investigation. Assume a system composed of twelve identical
The result of this process is a graph showing generating units, each capable of generating a
the expected peak loads and load factors for a continuous output designated as M k \ , where
period of years into the future. An example of a M is any number. The total installed capacity is
peak-load forecast is the line X-X in Fig. 19. 1 2 M kW. The spinning reserve is one unit, and
To be reasonably sure of carrying the peak the reserve for scheduled outages is another
load of any given year, the total generating ca- unit because an overhaul typically takes about a
pacity of the system must exceed the expected month. This system can be expected to carry a
peak load by a margin for reserve. The neces- peak load of 10 M kW, its firm capacity.
sary reserve is of two kinds. If the system consists of six units each of 2 M
Spinning reserve is the excess generating ca- kW capacity, the installed capacity is the same
pacity that is in operation and on the line at the as before, but deduction of the spinning reserve
time of peak load. It must be at least equal to the will bring its capacity down to 10 M kW, and
capacity of the largest single generating unit the further deduction of reserve for scheduled
in use at that time on the system or its inter- outages will leave a firm capacity of only 8 M
connections. It is necessary to provide spinning kW. However, it may be possible to schedule the
reserve to guard against the possibility of overhauls of six units wholly outside the peak-
a mishap to the largest unit causing loss of load season, depending on the character of the
system load variations through the year; this
would make the firm capacity of the system

z
5 .mvi
'O
10 M kW as before.
Another example is indicated in Fig. 19. The
system is assumed to consist of six identical
%5 units each of M kW capacity. Line A indicates
""a present installed capacity. Deduction of spin-
3 a
" .=
YO ning reserve gives line B, and further deduction
$3 of reserve for scheduled outages leaves the firm
E
2 .G
0 capacity, line C. Another unit must be in opera-
'"z tion before the peak-load season of the fourth
c%g year. If this unit is of M kW capacity, the new
z situation is indicated by lines E, F and G. Simi-
I Years larly, other M kW units must be added, one be-
fore the seventh year, one before the ninth year,
Fig. 79 Relationship between peak loads
and installed capacity and so on.
- CO&fBUSTION
Steam Power-Plant Design

If the seventh unit is twice the size of the ear- A system usually includes transmission lines
lier ones, the installed capacity in the fourth which are subject to interruption of service
year is shown by line D. Spinning reserve must from weather and other such causes quite dif-
now be 2M kW, the size of the largest unit. Re- ferent from those that affect generating units.
serve for scheduled outages will, however, be Outages from such interruptions may be greater
M kW, making the firm capacity line G, the than the loss of a single unit.
same as if unit seven were of the smaller size. It There is the possibility that not only one unit,
follows that installing a large unit increases but two or more, may suffer unexpected inter-
the firm capacity of a system only by an amount ruptions simultaneously or following closely
equal to the capacity of some smaller unit. upon one another.
IVhen the second larger unit is installed, as is The graph of Fig. 19 plots predicted annual
indicated for years seven to ten, the firm capac- peak loads forTcertainfuture years. Another in-
ity will increase by 2M kW if it is possible to formative graph is constructed by getting from
schedule outages of the two larger units out of system records the number of hours per year in
the peak-load season (lines H, I and 7). Other- which the load equalled oy exceeded a given
wise line K will give the firm capacity. amount. The system minimum load will corre-
Further additions of capacity are also indi- spond to 8760 hours per year, and the maxi-
cated on Fig. 19. Solid lines apply to M kW mum load will appear, in all probability, for
units and dash lines to the larger 2M kW size. only one hour. Such a graph is called a load-
The foregoing is known as the block system duration curve. Fig. 20 represents an idealized
of generating capacity addition. The objective example. The areas are energy units expressed
is to install the equivalent of two blocks more as kWhr, and the total area under the curve, di-
than the peak load, one to provide spinning re- vided by the area of the rectangle enclosing it,
serve and the other to permit scheduled outages is the annual load factor.
for maintenance and repair. The chief value of this curve is to emphasize
EVALUATING SYSTEM CAPACITY ADDITIONS the brief period during which peak loads must
be generated in the typical system. Even though
Several factors have led to modifications and the curve is drawn for a past year, its shape will
deviations from this simplified method of ca- not change markedly in the future unless the
pacity addition. Knowledge of system opera- character of the load changes materially. Load-
tion has become more complete, and reliability duration curves can, therefore, be drawn for fu-
of components is somewhat better understood.
ture years, subject to the uncertainty of the
This means that entire systems may be com-
predicted peak loads and load factors discussed
puter-simulated by mathematical models and
earlier in this chapter.
that unit outages may be predicted by probabil--
ity m e t h ~ d s . ~
Using
' this approach the neces-
sary system reserve requirements may be less L

than under the block system, but the largest sin- g 140
gle unit should not exceed 5 to 10 percent of the
total system capacity.
;120
6 C 100
In practice, these considerations for system g ti
capacity additions are far from clear-cut for a ;i 80
number of different reasons. 4 60
The units will be of different types, sizes, 8; 40
ages and vulnerability to accidental shutdown. % 200 20 40 60 80 100
The actual capacity of a plant varies with con- P %of Hours in Year
densing water temperature, and at times is sub-
ject to variations caused by changes in the fuel. Fig. 20 Load-duration curves

-25
COUBUSRON
Steam Power-Plant Design

It is apparent from the series of curves on a a capacity factor equal to their availability for
single set of axes in Fig. 20 that the system al- approximately the first 10 years of commercial
ready has enough equipment to generate all but operation. This relegated previously base-
a relatively small part of the predicted loads. loaded plants within the system to cyclic or
These peaks last a short time and involve only a lower load-factor operation.
small amount of generation above a horizontal Currently, several factors are operating to
line representing the system firm capacity. As- change this pattern. Improvements in heat rate
sume for the moment that all equipment in the have diminished. Utilities with a mix of nu-
system is in good condition and can be ex- clear and new fossil may require the fossil
pected to operate successfully throughout the plants to enter cycling service directly. Finally,
period under study. On this assumption, the although the new fossil units may be designed
problem of meeting the future growth in peak for an efficient thermodynamic cycle, tail-end
load can be solved simply by providing the emission control systems may have high para-
cheapest possible generating capacity large sitic power requirements. Similarly, the new
enough to take care of the growth in load; its plant may be fueled with low-sulfur coal trans-
fuel economy is not of prime importance be- ported great distances at considerable expense.
cause it will be used only a few hours per year, Such factors may result in the new fossil unit's
whereas investment costs go on continuously having higher generation costs than son?e of the
and must be kept to a minimum.= older plants, with a corresponding influence on
the selection and loading of equipment for the
CHOICE OF POWER-PLAN ADDITIONS
most economic dispatch.
Generally, load-distribution requirements for Final decisions as to size and timing may well
most utility systems follow the pattern of Fig. be tied in with decisions as to location and type
20. A typical utility may have three distinct of equipment, as well as licensing and regulatory
load requirements-base, intermediate and requirements that can result in exceedingly long
peak. Prior to the mid-1970's, the traditional construction lead times. As has been often dem-
methods of meeting these load requirements onstrated since the advent of longer plant-real-
were to have large nuclear and high-efficiency ization times resulting from the current extended
fossil-fuel steam plants designed for 6000 to permitting process, the risk of error in installing
8000 hours of operation per year supplying new facilities increases directly with the time of
base load. Specially designed fossil-fuel steam construction. This mitigates against the 1 2 - to
plants and former base-loaded fossil plants 15-year total time span of nuclear plants, and
would supply intermediate load. Low-effi- makes short-installation-tirne generating equip-
ciency installations required to operate for 500 ment (such as gas turbines), as well as power-
to 2000 hours per year would supply the peak- purchase scenarios, very attractive to system
load and reserve requirements of the system. planners. The analysis and study described to
Gas turbines, old steam plants, and hydro- this point will disclose a relatively small number
pumped storage plants would supply this latter of practical possibilities, each of which must
capacity. (It should be noted that there is no be studied in some detail to set up comparative
clean-cut line of demarcation between load cat- investment and operating costs over a period
egories. Plants designed for one mode of opera- of years.
tion may, in practice, be required to operate
SELECTION OF PLANT LOCATION
in other modes which were not originally
contemplated.) The location of an electric-generating station
Traditionally, utilities -purchased new addi- is determined by analysis of many factors that
tions of the largest and most efficient steam influence the selection in diverse ways. During
cycle available. These new units were assigned the study and forecasting of future loads, it will
to base-load service and expected to operate at usually become apparent that only a few attrac-
COMBUSTION
Steam Power-PlantDesign

tive sites are available. Each of these must be


studied to determine the effect of individual fac- ..L
Plant Thermal Efficiency, Percent
tors on its desirability. The object is to make an
engineering economic analysis that will disclose
the best choice, which in general is the location
that will result in the lowest total cost to the
owner in the long run.
CONDENSINGWATER SUPPLY

As is well known, a steam turbine requires a


relatively great quantity of condensing water for
its economical operation. Under average condi-
tions it is estimated that about 800 tons of water
are required for each ton of coal burned. The sup- T
ply of water should not vary through the year, its Net Plant Heat Rate, Btu/KWHr
temperature should be as low as possible, the
water should not be corrosive to the usual mate- Fig. 21 Heat rejected versus net plant heat rate
based on 1.5" Hg backpressure
rials, and it should not contain suspended mate-
rial that will interfere with the flow through
pumps and tubes. These considerations suggest PUBLIC OPINION
a river, a lake or an ocean, and central stations are
located whenever possible on the bank of some The effect of public opinion on the choice of a
such body of water. site can be profound. If the public thinks of a
The alternate to such a location is to provide power plant as an ugly, noisy, dirty place, spread-
cooling towers in which forced or natural-draft ing dust and ash around the neighborhood, it
circulation of air cools the condensing water instantly objects to admitting one to genteel sur-
nearly to the prevailing wet-bulb temperature. roundings. The remedy is to design and build
Although the investment in cooling towers is central stations that have good architectural
high compared to once-through cooling, this treatment, that are clean and as quiet as possible.
higher cost is somewhat offset by the smaller wa- Many utilities have done this quite successfully.
terfront construction and tunnels. OTHER CONSIDERATIONS .- "*..I%

The extent to which condensing water is avail-


able sets a limit on the amount of power that can Additional concerns include availability of
be generated at the site. Advanced steam condi- municipal services and suitable labor, appropri-
tions not only achieve greater cycle efficiencybut ate zoning, convenient access, climate, tax situa-
also result in less rejection of heat to the con- tion and the like. Room for growth and freedom
denser. For example, for the same initial steam fromundue riskof flood and earthquake are ordi-
conditions and a limited amount of condensing narily essential.
water, selection of areheat regenerativecycle per- The nature of surrounding installations may
mits greaterpower output than anonreheat cycle, play a part in the selection. For example, the
everything else being equal. This can be of con- height of stacks will be subject to Federal Aero-
siderable importance to central stations which nautics Administration regulations and would
are being redeveloped on sites having limited be restricted near an airport.
amounts of cooling water. Fig. 2 1 shows the re- In many site selection problems, one possibil-
duction of heat rejection to condenser cooling ity is that of adding to an existing station. To do so
water as cycles of increased thermal efficiency has obvious economies in making use of existing
and decreased net plant heat rate are incorpo- facilities, no matter how much new construction
rated in power plants.23 may have to be provided. If the existing station
COMBUSTION
Steam Power-Plant Design

site is large enough and has enough condensing similar characteristics." Only with experience
water, and especially if it was designed for expan- and judgment as a guide is it possible to keep the
sion, it is unlikely that a new site can compete combinations of variables within practical
successfully. Each case must be studied on its bounds. Even with the help of advanced methods
merits; the danger is in assuming that the "obvi- of analysis, the basic method of solution is to
ous" answer is the best. assume a reasonable set of conditions and calcu-
Finally, in all studies and analyses, it is essen- late the required investment in the central station
tial to remember that future conditions deter- and the resulting cost of operation under future
mine the best solution. All available data apply to load conditions. In some instances, the influ-
past yetars,or at best to the present, and must be ence of avariable can be isolated and analyzed by
reviewed critically to ensure that the most likely itself, but all too often a change in assumed de-
future conditions have been derived or projected sign conditions will be reflected throughout the
from them. This statement applies to every engi- cycle, resulting in an unexpected and perhaps
neering economic study. undesired change at another point.25
The sizes of the units will have been fairly well
SELECTION OF TYPES OF EQUIPMENT
determined by the studies of load growth and
Having determined the size, timing, and loca- estimated capital cost. The unit system, under
tion of the installation by the steps previously which a singleboiler serves a single turbine, each
described, we must tackle the question, What with its own auxiliaries, is rather generally ac-
kind? In practice, the steps are not taken sepa- cepted, but there may well be exceptions, espe-
rately and in succession; they overlap considera- cially when a station has a process steam load in
bly but may follow the sequence described in the addition to an electric load.
following text. At this point, anumber of subsidiary economic
The primary choice is between two plant fuel studies will be required; for example, heater and
cycles; that is, coal fuel or internal combustion condenser surface, turbine versus motor-driven
(diesel or gas turbine). The possible consider- auxiliaries, voltage of electric auxiliary drives
ation of nuclear, hydroelectric, or purchased and extent of building enclosure. The object is
power would take place before site selection, and always to reduce the initial investment without
is outside the scope of this book. Strictly on the increasing maintenance and operating costs.
basis of total economy, steam with coal fuel fre- Investment costs are initially determined by
quentiy will be preferred in the larger sizes, with making a preliminary design of the feature in
internal combustion having an advantage for question and estimating from quotations and
smaller units. past experience the cost of its purchase and in-
The size range within which each type of plant stallation, keeping in mind the fact that such
fits best is reasonably well defined by experience matters as building volume, foundations, steel
and will not be the subject of intensive study in work, steam and water piping, electrical wiring,
the typical instance. Capacity installed for peak- and controls cannot be ignored.
ing purposes may be subject to very different eco- Operating costs are estimated by calculating
nomic evaluation than is the case for base-load plant performance over the necessary range of
generating equipment. Heat rate economies loads under the assumed conditions and apply-
dominate the latter, while availability of peak- ing load duration data to find annual costs. It is
shaving capacity for short periods is of most im- generally necessary to include maintenance
portance in the former. costs for a complete comparison.
Assuming that a conventional steam cycle has The several assumed combinations are com-
been selected, studies will be made to find the pared by standard methods of engineering econ-
best conditions as to steam and reheat pressures omy to find the one that promises the lowest
and temperatures, number and location of ex- overall cost over the life of the station, giving due
traction stages, condenser pressure, and a host of regard to the time value of money.
COMBUSTION
S:aam Power-PlantDesign

considered, advantages arid disadvantages of


- SOME POWER-GENERATION TERMS each, comparative investment and operating
CAPACITY FACTOR: a measure of the output costs, and other data individual to each case.
of the plant over some time period. Capacity Management will be able to base its decision on
factor is the ratio of the energy generated by this material if it is complete and well presented.
the unit during the time period to the energy Then and only then does the detailed procure-
that could have been generated had the unit ment and design process begin. The steam-
run at its full rating over the entire period. turbinelgenerator and the boiler are purchased
(SeeChapter 24.) first, followed by other major components as dic-
NET PLANT HEAT RATE (NPHR):the fuel- tated by their respective design and fabrication
heat input required to generate a kWhr and lead times.
deliver the generated power to the trans- As the equipment is purchased, hundreds of
mission line leaving the plant. The term studies of comparative gconomics of the vendor
"net" implies that energy needed to supply offerings are made, based on capital costs, en-
auxiliary equipment must be deducted prior ergy costs, and probably costs of operation and
to calculating NPHR. Plant efficiency can maintenance. The following section describes
be calculated by dividing 3412 BtuIkWhr
by NPHR. how such conventional power-plant economic
studies are made.
REPLACEMENT POWER COSTS: the cost of
supplying replacement energy in the event
of a forced or scheduled outage. Replacement
power may be available within the utility's POWER-PLANT ECONOMICS
system by bringing into operation units with
high production costs, or may have to be pur- Costs associated with owning and operating
chased from other utilities. power-plant equipment are a basic concern of
AUXILIARY-POWER CHARGES: charges as- both the design engineer and the user. Often,
sessed to account for the effect of auxiliarv- the initial cost of the equipment must balance
power requirements on the net output from against the operating cost over the plant lifetime.
the plant to the utility's grid. A demand Before discussing how such comparisons are
charge, proportional to the cost of new gener- made, it is necessary to consider the two general
ating capacity, applies regardless of the dura- categories of power-plant costs.
tion such auxiliaries are ex~ectedto run. Much of the money spent by a power-plant
An energy charge is applied against the time owner is for goods and services consumed
the auxiliarieswill be in operation. The mag- within a relatively short time after acquisition.
nitude of the energy charge depends on
This category includes outlays for wages and sal-
fuel costs and other operating costs in the
utility system. aries, operating and maintenance supplies, and
fuel. Called expenses, such payments are nor-
mally made from revenue.
In contrast, other owner expenditures are for
See reference 24 for a typical engineering items whose usefulness continues for an ex-
economy study performed .for application to a tended period and which produce revenue in the
large utility system. future; money spent to construct a power plant is
The result of this engineering process will be a typical example. Termed capital investments,
to produce a set of preliminary arrangement expenditures of this nature are not ordinarily
drawings showing the station as it has been con- paid directly from revenue; this is because cur-
ceived; a set of abbreviated specifications cover- rent revenue most often would be insufficient to
ing the important equipment, structures and cover large capital expenditures, and because the
systems; a reasonably reliable construction cost equipment is expected to provide service well
estimate; and a report covering the alternates into the future.
COMBUSTION
Steam Power-Plant Design
-
POWER-GENERATINGCOSTS
C = IC x FCR1100
Total power-generating costs, or bus-bar = fixed charges, $lyr.
costs, are the sum of fixed charges, fuel costs,
and operation and maintenance (O&M)costs. IC = initial capital cost, $, and
The fixed charges are associated with the capi- FCR = annual fixed-charge rate, %
tal investment, whereas the fuel and operation (8)
and maintenance (O&M) costs are generally
treated as expenses. or, on a per-unit-of-energy-generatedbasis:
FIXED CHARGES

Capital costs are translated into annual costs


by calculating the fixed charges on the plant or
equipment. (9)
Fixed charges are those costs incurred during where c = fixed charges. millslk\Vhr, and
each year of the lifetime of a plmt, i~dependent G = energy generation, kwhrlyr.
of how much energy production takes place in
each year. Included in the fixed charges are usu-
ally all of the costs that are proportional to the In utility accounting, fixed-charge percent-
capital investment in the installation, which ages are applied annually to the depreciated
will include depreciation, required return on (book) value of the investment, and conse-
investment, property insurance, federal income quently, the amount charged to a specific plant
taxes, and state and local taxes. decreases from year to year. When this procedure
Some components of the fixed-charge rate, is followed for evaluations, it is necessary to cal-
such as depreciation, are bookkeeping expenses culate fixed charges and all other costs year-by-
which do not represent cash outflow during the year over the life of the plant, to discount each
operation period. Other fixed-charge compo- future year's total costs to obtain the correspond-
nents, such as property insurance and ad va- ing present worth, and to sum all these present
lorem taxes, represent annual outlays which are worths to obtain the grand-total "present-
in direct proportion to part or all of the initial worthed" cost of the plant being evaluated. This
investment. The required return on the invest- gives a single figure by which the relative eco-
ment and the income taxes associated with this nomics of proposed plants may be judged.
return are a major part of the annual fixed A simpler procedure giving the same result is
charges. Also included is an interim replace- to use levelized annual fixed charges; that is, to
ment allowance, which provides for any inter- apply a constant fixed-charge rate each year to
mittent replacement of equipment required the initial investment in such a manner that the
before the end of the scheduled plant life. Not present-worthed grand total of the constant
included in annual fixed charges are relatively charges equals the corresponding total of vari-
constant fixed costs, such as liability insurance able charges. The use of levelized fixed charges
or plant staffing expenses, which bear no direct does not yield the year-by-year forecast of costs
relation to the plant investment and are some- given by the more detailed approach, but such
what independent of the extent to which power is annual breakdowns are not usually required for
generated. (Such expenses are included in the evaluations. A conceptual approach to develop-
plant operation and maintenance category.) ing a fixed-charge rate is shown in Table I.
The proportionality constant that converts the
FUEL COSTS
initial capital cost of the plant to annual fixed
charges is the fixed-charge rate. Therefore, the For most economic evaluations, converting
fixed charges on the plant are fuel costs on an as-received basis at the plant to
COMBUSIION
Sttem Power-PlantDesign

fuel costs per kilowatt-hour of power produced is TlMdDEPENDENT COSTS


sufficient. The relationships to do this are The time it takes to complete a project affects
present-day direct costs (such as material and
labor) and indirect costs (such as construction
facilities and services) in two ways. Escalation
takes place between project initiation and actual
(10) delivery of equipment and services. The utility
where F = fuel cost, millslkwhr also incurs interest charges on payments that
FC = fuel cost, Pilob(mi1lion)iBtu
NPHR = net plant heat rate, BtulkWhr must be made before the plant is placed into ser-
or vice. The magnitude of these escalation and
interest-during-construction (IDC) costs on the
~ t e a m - ~ e n e r a tequipment
in~ depends, of course,
FC x NTHR on the vendor's escalation provisions and terms
F =
lo3 x B E (1 - APR) of payment. These charges can typically add 50
percent to the original cost of long-lead-time
(11)
where NTHR = net turbine heat rate, BtulkWhr equipment, such as boilers and turbine-genera-
BE = boiler efficiency, Ole tors. Therefore, changes in the present-day price
APR = auxiliary power requirements
of new equipment, either upwards or down-
(as a fraction of gross plant output)
wards, are highly leveraged in their impact on
the evaluated cost of the equipment installed in
the plant.
Although each equipment payment is subject
Thus, if fuel costs for a coal-fired unit are pro- to different escalation and IDC charges as a result
jected at 3ooa: per million Btu, and the net plant of the*timing of the payment, the net effect of
heat rate is 9300 BtuIkWhr, the fuel cost, F, is these charges can be represented by single fac-
28 millskwhr. tors. Each factor is a weighted-average of the
charges on individual payments. The final, fully
escalated cost of the equipment is greater than
the present day cost of equipment by the factor F,
where:
Table I.Typical Fixed-Charge Rate
for Depreciable Portion of Plant F = E d X Ec X IC
and where; (12)
Component Percent
F = total factor to be applied to present-day costs to
Interest or return on investment 8.6 *
account for escalation and interest during con-
Depreciation * * 3.3
struction
Interim replacements 0.4
Ed = escalation factor during design period to start of
Property insurance 0.5
construction
Federal income taxes 3.0 * * *
E, = escalation factor during construction period
State and local taxes - 2.4 * * *
- (See Fig. 22)
Total 18.2 1, = interest factor during construction period (See
Fig. 23)
'Levelized value: (50% debt @ 10% + 50% equity @ 14%) x .72
levelized average investment Figs. 22 and 23 depict graphically the values of
'straight-line for 30 years escalation and interest multipliers during the
' 'For investor-owned companies construction period based on typical cash-flow
patterns for power plants.
COXEDSTION
Steam Power-Plant Design

Consider a unit with a present-day cost of $800 crease at a slower rate, percentage-wise, than the
million. With construction beginning two years rate at which design plant output increases,
from now and commercial operation six years economies of scale are present. Power-plant con-
from now, escalation is expected to be 7 percent struction experience indicates that economies of
per year, and interest during construction, 8 per- scale exist in the steam-generatingplant, the tur-
cent per year: bine-generator, the condenser, and switchgear,
and consequently, in total plant costs.
Ed = (1.07)' = 1.145
E, = 1.135 (See Fig.22 for 48 months and 7%/yc) This type of cost behavior is often represented
I, = 1.16 (See Fig.23 for 48 months and 8%/yc)
by some form of power relationship, less than
F = 1.145 x 1.135 X 1.16 = 1.51
unity, and usually between 0.7 and 0.85. With a
power relationship "k," this would be expressed
This plant then would have a capital cost at the as follows:
commercial operation date of:
1.51 x $800 x i06 = $1,208 million

ECONOMIES OF SCALE where: IC,= capital cost of plant 1


Many of the cost components that make up total IC? = capital cost of plant 2
power-plant costs are fixed;that is, they ire inde- PO, = output of plant 1
pendent of plant size, or else they increase slowly PO2= output of plant 2 (13)
as plant size increases. If total plant costs in-

.36 r (Escalation Rate = e) e = .12 e = .ll e = .10

I Construction Period, Months I


Fig. 22 Escalation multiplier
COMBUSTION
Steam Power-Plant Deslgn

Thus, if the cost of a 300-MW generating unit is the basis for the statement. It has nothing to do
expectedto be $2,00okW, the total cost for a 500- with inflation or escalation of costs. It simply
MW unit will be, with k = 0.8 means that a doll? received today can be in-
vested and, by "tomomw," will be equal to a dol-
lar ~ l uinterest.
s
The concept of present worth or present value
is a corollary. The present worth of some future
expense (or revenue) is the amount that would
Economies of scale are only one factor involved have to equal that future expense (or revenue)
in the choice of unit size. Consideration must eventually. Total present-worth costs are simply a
also be made of such factors as reliability, mode way of combining payments made at different
of operation, financing requirements, availabil- times to accouht for the value of interest. All util-
ity of sites, and regulations. ity expenditures are in this category.
PRESENT-WORTH AND LEVELIZED COSTS Present-worth costs are calculated by simply
reversing the process of calculating compound
Present-worth and Ievelized costs are terms of- interest. Therefore, C; is the present worth of
ten used in discussing utility planning, evalua- some cost, C, occurring at time t in the future
tions, and engineering economics in general.
The concept of present-worth costs is frequently
-
explained by the statement that "a dollar today is
worth more than a dollar tomorrow." While this where r is the interest rate or discount rate.
sounds reasonable, it is important to understand

I I I
1.001 I I I I I I I I I
30 34 38 42 46 50 54 58 62 66 70 74 78
Construction Period, Months
Fig. 23 Interest multiplier
COMBUSTION
Steam Power-Plant Design
.-

The expression 2
(1 + r)t
is called the dis-
DEFINITION OF DISCOUNT RATE
count factor or preseit-worth factor.
The discount rate is usually defined as
Thus, the present worth of a payment of the desired after-tax return on investment.
$100,000to be made three years later, assuming a Generally, it is the minimum return that any
discount rate of 9 percent per year, is project must provide in order for the project
to be accepted.
$100,000 X 1= $77,200. The following formula takes into account
(1.09)~
In other words, a. payment of $77,200 now is that the interest payments on debt are tax-
deductible expenses:
equivalent to a payment of $100,000 three years
later, assuming the money can be invested to gen- r = f j l + (1 - t) f g b
erate a rate of return of 9%/yr. where: r = discount rate
The total present-worth costs (PWC) are the f, = frxtion of investment i n the
sum of all costs associated with a project prop- form of stock
erly discounted or present-worthed to a common fb = fraction of investment i n the
point in time. form of bonds
r, = t h e annual return to stock-
holders, %
rb = the interest rate on bonds, %
t = fraction of net income to be
paid out as income tax
Total present-worth costs can be used to com-
pare two alternatives that involve different cost
q e n d i t u r e s over the life of a project. levelized costs, using a 9%/yr discount rate, are
A closely related concept is levelized costs. shown in Table 11.
Levelizing is an averaging process which gives
more weight to costs occurring early in the life of ECONOMIC ANALYSES
the project. To obtain levelized costs, it is only Most evaluations involve comparisons be-
necessary to divide the total present worth of the tween different plant designs, alternative com-
payments involved by the sum of the present- ponents or various modes of operation. To
worth factors. For instance, levelized total costs perform a consistent evaluation, everything that
(LC) are given by: affects a power producer's cost of providing ser-
vice should be taken into account. Usually this
results in a study to determine which alternative
has the lowest combination of capital cost (or
fixed charges),fuel cost, and O&Mcost.
This discussion will be referring to the evalua-
tion between two different total power plants
and could apply equally well to the choice be-
The resulting levelized cost is one, constant, tween steam-supply systems, alternative pump
annual value which is equivalent (i.e. has the designs, or operating cycles. Most evaluations
same total present worth) as the non-uniform can be classified into one of two approaches. The
series of actual annual costs. first of these is what is often referred to as the
Thus, for non-uniform annual expenses of "revenue requirements inelhod:' This method
$157million; $165 million; $167, $163, and$170 leads to acomparisonof generating costs (or reve-
million over the first five years of operation of a nue requirements) on a millslkwhr basis,
new generating unit, the present-worth costs and between alternatives. An equivalent-revenue-
cOMBusTIoN
Steam Power-Plant W g n

requirements comparison can also be made by ized-cost method, just the opposite is done. An-
contrasting the total present worth of all costs, nual costs such as fuel and O&M are divided by
i.e. present worth of fixed charges on the capital the fixed-chargerate (i.e. capitalized) so that the
investment plus the present worth of fuel and result can be combined with capital costs. This
O&M costs. A comparison of present-worth gives a very quick way of comparing the differ-
totals, instead of millskWhr is only valid in ence in operating costs with the difference in
the case where each alternative produces the capital costs between various alternatives.
same energy. The system planner is still faced with the tradi-
The revenue-requirements method, therefore, tional problem of balancing plant capital cost,
necessitates that all capital costs first be con- expected capacity factor, andfuel cost in deter-
verted to annual fixed charges and then be com- mining which steam cycle to choose. A curve
bined with annual revenue requirements for fuel system (Fig. h), using the capitalized-cost
and O&M. It is then possible to calculate total method described previously, is useful in per-
present-worth revenue requirements for each al- forming such comparisons.
ternative or levelized annual revenue require-
ments. The alternative with the lowest revenue OTHER ASPECTSOF THE SELECTION
OF POWER-PLANTEQUIPMENT
requirements is the preferred choice in the
evaluation. Intensive economic and cost analyses of the
The second method of performing an eco- type described in the preceding section are very
nomic evaluation is what is often known as the important in choosing the size, type, and equip-
'kapitalized-cost" method. With the revenue- ment manufacturer for power and steam genera-
requirements approach, capital costs were con- tion. But there are other surprisingly potent
verted to annual costs by use of the fixed-charge variables influencing the eventual generation
rate. The fixed charges could then be combined economics of a given installation that the evalu-
with fuel and O&Mcosts which were already on ating engineer has to take into account. Among
a n annual basis. Conversely, with the capital- these variables are:

Table 11. Levelized Costs PRESENT WORTH


and Present-Worth Costs of a New
Generating Unit Present worth of a fixed annual cost, FC, for
n years at r %lyr. (If FC is equal to 1 , this ex-
Present-Worth Expenses Present-Worth pression is equal to the sum of the
Year Factor 106$ Expenses, lo6$ present-worth factors for n years.)

1 0.917 157 143.9 I. PW = " [I -(


1 + rL)"]
2 0.842 165 138.9 Present worth of an annual cost, AC, which
3 0.772 167 128.9 is escalating at e %lyr:
4
5
0.708
0.650
-
163
170
115.4
110.5
-
2. PW = AC ( r -e 1 I.)=(
1+ e
[I -)
where r is again the discount rate.
Totals 3.889 637.6
3. To obtain levelized annual costs (when
escalation is taking place), divide the results
$637.6 X lo6 obtained in expression 2 by the sum
Levelized Expenses =
3.889 of the PW factors from expression 1.
= $164 x 106/yr
COMBmnON
Steam Power-Plant Design

a. the reliability of the many critical compo-


A Heat Rate, nents associated directly with the generating
B~,,/KwH~ Capacity Factor, OO
/
process;
b. the reliability of fuel supply of a specific
type and heating value during the lifetime of
the plant;
c. regulatory obligations, present or future, that
a plant is bound to observe during operation
or, in the event of failure of equipment having
I
an actual or alleged effect on public health or
1 2 3 4 I safety, shut down the generating operation;
Fuel Cost,$/lO6 Btu I

Fixed Charge Rate,o/a/Yr - d. compatibility with future regulatory require-


ments, which have to be anticipated during the
siting and equipment-selection process; and
.-
a3 e. compatibility with future social and political
40'55 requirements.
06
G I So, in addition to the effects of inflation (esca-
20 20 d g lation and changes in interest rates) present-
- -- @%E ed above, there is no question but that we
2
must anticipate large but uncertain capital-
cost increases in the construction of all power-
Fig. 24 Breakeven capital cost changes versus producing plants because of federal and state
improvements in heat rate. EXAMPLE: Going from regulatory impact. Laws yet to be enacted in the
an 1800 psig, 1000"11000" cycle to a 2400 psig, areas of clean air, clean water, conservation,
1000"11000"cycle results in an improvement in cycle resource recovery, public-safety, public health,
efficiency of 160 BtulkWhr. What is the breakeven aesthetics (plant visual impact), and product
increase in capital cost? Given: 70 percent capacity
factor, $2/106 Btu fuel cost, and 16 percentlyr fixed liability can be expected to affect decision
charge rate. Solution: Enter at point A; read the making even more than purely economic and
result at point B, about $15/kW. equipment- availability considerations.

REFERENCES
C. A. Meyer, et a]., "Availability Balance of Steam Power
1 Edward Arthur Bruges, Available Energy and the Second Plants." Tmnsactions of the ASME. Journal of Engineering
Law Analysis. New York: Academic Press, 1959. for Power, 81, Series A:35-42, January 1959.
J. H. Keenan, "A Steam Chart for Second Law Analysis."
Mechanical Engineering, 54:195-204, 1932. E. Clapeyron and R. Clausius, "Memoir on the Motive
M. W. Thring, "The Virtue of Energy, Its Meaning and Power of Heat" in Sadi Nicolas Leonard Carnot, E.
Practical Significance." Institute of Fuel. Journal, 17:116- Clapeyron and R. Clausius, Reflections on the Motive
123,1944. Power of Fire; and other papers on the 2nd law of Thermo-
dynamics. Gloucester, Ma.: Peter Smith, 1962. Also pub-
C. Birnie and E. F. Obert, "Evaluation and Location of lished as a Dover paperback.
the Losses in a 60,000 KW Power Station," Proceedings of
the Midwest Polveer Conference, 11:187-193, 1949. ?.hi: 3 Edward F. Obert and Richard A. Gaggioli, Thermodynam-
cago: Illinois Institute of Technology, 1949. ics, latest edition. New York: McGraw-Hill.
Allen Keller. "Evaluation of Steam-Power-Plant Losses Newman A. Hall and W. E. Ibele, Engineering Thermo-
by Means of the Entropy-Balance Diagram." Transactions dynamics. Englewood Cliffs, N.J.: Prentice-Hall, 1960, pp.
of the ASME, 72:949-953, October 1950. 447-520.
COMBUSI?ON
Steam Power-Plant Design

4William J. M. Rankine, A Manual of the Steam Engine 1; "The Mercury Power Plant from South Meadow to Schil-
and Other Prime Movers, revised by W. J. Millar with a ler," General Electric Co. GER-246. Reprinted from Power
section entitled "Gas, Oil, and Air Engines" by Brian Generation, March 1950.
Duncan. London: Griffin and Co.. 1908.
16A. P. Fraas. "A Potassium-Steam Binary Vapor Cycle for
5C. D. Weir, "Optimization of Heater Enthalpy Rises in Better Fuel Economy and Reduced Thermal Pollution,"
Feed-Heating Trains." Institution of Mechanical Engi- ASME Paper No. 71-WAEner-9, Nov.-Dec. 1971.
neers. Proeedings, 174:769-796. 1960. Discussion by R.
W. Haywood, pp. 784-787. l7 D. H. Cooke. "Combined Cycle Thermodynamic Inquiries
G. Chiantore, et al., "Optimizing A Regenerative Steam- and Options," ASMEIIEEE Joint Power Generation Confer-
Turbine Cycle." Transactions of the ASME. Journal of En- ence, Paper 87-JPGCIPwr-61, 1987.
gineering for Power, 83, Series A: 433-443, October 1961.
'8 J. B. Stout, et al., "A m e Combined Gas Turbine-Steam
J. Kenneth Salisbury, Steam Turbines and Their Cycles. Turbine Generating Unit." Proceedings of the American
Huntington, N.Y.: Robert E. Krieger. 1974, Part 3: Cycle Power Conference, 24:404-411, 1962. Chicago: Illinois
Analysis. Institute of Te+nology, 1962.
6Anon.. "The Reheat Cycle-A Re-Evaluation." Combus- 19s. R. Wysk, H. H. Ropers, K. Janssen, and S. G. Drenker,
tion. 21(12): 38-40, June 1950. Papers given at the Sym- 'A Pressurized Circulating Fluidized Bed for Utility Ap-
posium on the Reheat Cycle sponsored by the ASME and plications," Eighth International Conference on Fluidized
held in New York, November 29-December 3, 1948. Bed Combustion, Houston, Texas, March 1985.
Transactions of the ASME, 71:673-749, 1949.
"PFBC Turbocharged Boiler Design a n d Economic
J. K. Salisbury. "Analysis of the Steam-Turbine Reheat Study:' EPRI Research Project RP-2428-2, December 1985.
Cycle." Transactions of the ASME 80: 1629-1642, Novem-
ber 1958. "PFBC Turbocharged Boiler Design and Economic
J. K. Salisbury, "Power-Plant Performance Monitoring." Study," Cost and Economic Data Package prepared by
Transactions of the ASME Journal of Engineering for Fluor Engineers for EPRI Research Project RP-2428-1, Feb-
Power. 83. Series A: 409-422. October 1961. ruary 1986.
7Cogeneration: Special Section; Power, June, 1987, Vol. 2OThis Act is Public Law 95-617, Nov. 9, 1978, 92 Stat.
131. No. 6. 3117, as amended; it is commonly referred to as PURPA.
8 J. H. orl lock, Cogeneration-Combined Heat and Power 21 AIEE Probability Applications Working Group. Applica-
(CHP): Thermodynamics and Economics. Pergamon tcion of Probabilitv Methods to Generatinrr C a ~ a c i t vProb-
Press. Oxford (England). 1987. lems.' AIEE paper CP 60-37. New 6 r k ; ~ i e r i c a n
Institute of Electrical Engineers, 1960. (Unpublished).
9R. W. Porter &d K. Mastanaiah, "Thermal-Economic
Analysis of Heat-Matched Industrial Cogeneration Sys- C. J. ~ a l d w i n ,"Modern Scientific Tools Used in the
tems:' Energy, 7, 2, 1982. Power Industry for Tomorrow's Problems." Proceedings of
the American Power Conference. 24: 94-105, 1962. Chi-
10 A. R. J. Timmermans, "Combined Cycles and Their Possi- cago: Illinois Institute of Technology. 1962.
bilities," Lecture Series, Combined Cycles for Power Gen-
eration, Von Karman Institute for Fluid Dynamics, Rhode 12R. D. Brown and D. A. Harris, Lage Coal-Fired Cycling
Saint Genese, Belgium, 1978. Units. Paper given at the ASME-IEEE-ASCE Joint Paver
Generation Conference, Portland. Oregon. Sept. 28-Oct.
111. Oliker, "Steam Turbines for Cogeneration Power 2, 1975.
Plants," Trans. ASME-Journal of Engineering for Power,
102,482-485.1980. Peter H. Benziger and Joseph G. Singer. "Design for Cy-
cling at Chalk Point." Proceedings of the American Power
12 M. P. Polsky, "Fuel Effectiveness of Cogeneration," Joint Conference, 34:415-423. 1972. Chicago: Illinois Institute
Power Generation Conference, ASME Paper 80-JPGCiPwr- of Technology, 1972.
8. 1980.
23 Stanley Moyer, "Industry's Water Problems." ASME Paper
I3M. S. Reddy, F. Afshar, and R. J. Hollmeier, "Evaluation of No. 6 WA-141. New York: American Society of Mechani-
Alternative System Designs in a Cogeneration Plant:' Pro- cal Engineers, 1961. Also in condensed form in Mechani-
ceedings of the American Power Conference, 44, 1982. cal Engineering, 84(3): 46-49, March 1962.
Chicago: Illinois Institute of Technology. 1982.
~4 James W. Lyons. "Optimizing Designs of Fossil-Fired Gen-
IdHenry J. Blaskowski and Joseph G. Singer, "Gas Turbine erating Units." Power Engineering, 83(2):50-56, February
Boiler Applications." Combustion, 28(11): 38-44, May 1979.
1957.
W. H. Clayton and Joseph G. Singer, "Steam Generator LV. A. Wilson, "An Analytic Procedure for Optimizing the
Designs for Combined Cycle Applications." Combustion, Selection of Power-Plant Components." Transactions of
44(10): 26-32, April 1973. the ASME, 79:1120-1128, July 1957.
CHAPTER 2

Fossil .Fuels

ossil fuels used for steam generation in util-


ity and industrial power plants may be FORMATION OF COAL
classified into solid, liquid, and gaseous fuels Coal forms as the result of a natural chemical
as in Table I. Each fuel may be further classified process in which plants absorb carbon dioxide
as a natural, manufactured, or byproduct fuel. from the atmosphere. Sunlight, moisture and
Not mutually exclusive, these classifications other factors convert carbon dioxide into com-
necessarily overlap in some areas. pounds containing carbon, hydrogen and oxy-
Obvious examples of natural fuels are coal, gen, such as sugars, starch, cellulose, lignin
crude oil and natural gas. Residual oils which and other complex substances that make up the
are fired in boilers might be considered as a plant structure. Under favorable conditions,
byproduct of the refining of crude oil. Wood, vegetation is converted into some of the many
although a natural fuel, is rarely burned in forms of coal now known to mankind.
boilers except in the form of sawdust, shavings, When organic matter begins to change to
slabs and bark which remain as a byproduct coal, peat is the first product. In a block of peat
after lumbering and pulping operations. Coal is one can often see, with the naked eye, woody
the natural fuel from which coke, coke-oven fragments of stems, roots, and bark. As peat is
gas, char, tars, chemicals and industrial gases buried, it is cut off from the oxygen in air, and
may be converted by carbonization. Coal may rapid decay of its organic matter is prevented
also be gasified to obtain industrial gases for by slowing bacterial action. The weight of more
heating, chemical reduction, and hydrogena- vegetation falling on the peat helps to com-
tion and synthesis reactions.' press and solidify it, as does the weight of water
Of all the fossil fuels used for-steam genera- when the deposit sinks below a lake or sea, as
tion in electric-utility and industrial power has often happened. Sometimes, mineral sedi-
plants today, coal is the most important. It is ments have settled from muddy flood waters
widely available throughout much of the while vegetable matter was accumulating and
world, and the quantity and quality of coal re- formed "partings" or layers of shale in the coal
serves are better known than those of other vein. At the end of coal-forming periods,
fuels. Many studies have been made of coal swamps remain flooded for a long time, and
availability and utilization and should be con- earthy sediments are deposited in thick beds
sulted for more detailed i n f o r m a t i ~ n . ~ over the peat, further compressing it and start-
COMBUSTION
Fossil Fuek

ing "coalification," the coal-making process. vegetal and mineral, with some sorting-and
Many kinds of coal are found in a natural de- stratification, and accomplished by chemical,
posit. In some, transitions from the extremes of biological, bacteriological and metamorphic
lignite to anthracite exist in a single bed. It is action. The organic chemical materials pro-
generally assumed that differences in rank of duce heat when burned; the mineral matter re-
c ~ a are
l not caused by different source mate- mains as the residue called ash.
rials but by the agencies of coal formation. -

THE FORMATION CYCLE CLASSIFICATION OF COAL


Geologists usually name time, pressure and Coals are grouped according to rank, the de-
temperature as the agents that change peat into gree of progressive alteration in the transforma-
different types of coal. Chemists include micro- tion from lignite to anthracite.
organisms as an additional important factor.
Time, it must be remembered, is in itself no
agent; it is merely the duration or period during Table I. Ciassification of Fuels
which an agent has an opportunity to act. It be- Manufactured or
comes crucial, however, because many organic Natural Fuels Byproduct Fuels
chemical reactions are slow. In fact, it is be-
Solid
lieved that reactions are going on slowly in
most complex organic substances. In a short Coal Coke and coke breeze
period the results of such reactions would be Coal tar
negligible, but over millions of years the total Lignite Lignite char
results must be large. Although the greatest Peat
Wood Charcoal
single factor in the process of formation was
probably time, other factors must also be Bark, saw dust and
wood waste
sought, because coals of the same age and, in Petroleum coke
fact, in the same bed may be of different rank.
Bagasse
Generally, pressure is considered to be the Refuse
factor of next importance, because coal of
higher rank is generally found in regions that Liquid
have been under high pressure. Anthracite, for Petroleum Gasoline
example, is associated with earth-folding or Kerosene
mountain formation, which processes bring Fuel oil
about great internal pressure. Experimentally, Gas oil
it has not been determined that pressure alone Shale oil
can change organic substances chemically. Petroleum fractions
Likewise, heat has played an important part and residues
in this great natural chemical industry. The
Gaseous
temperature need not be high, for time brings
about a relatively great change even at the low Natural gas Refinery gas
temperatures prevailing in the earth's crust. Liquefied petro-
leum gases (LPG) Coke-oven gas
Man completes the cycle by burning the var- Blast-furnace gas
ious products of the natural process to carbon Producer gas
dioxide, and then nature starts all over again. Water gas
There is no satisfactory definition of coal. It .- -Carburetted water gas
is a mixture of organic chemical and mineral Coal gas
materials produced by a natural process of Regenerator waste gas
growth and decay, accumulation of debris both
COMBUSTION
Fossll Fuels

For the purposes of the power-plant operator, anthracite subbituminous


there are several suitable ranks of coal: bituminous lignite

Table 11. Classification of Coals by Ranka


Fixed Carbon Volatile Matter CalorificValue Limits,
Limits, % Limits, % BNlb ( M ~ i s t , ~
(Dry, Mineral- (Dry,Mineral- Mineral-Matter-
Matter-Free Basis) Matter-Free Basis) Free Basis)
Equal or Equal or Equal or
Greater Less Greater Less Greater Less Agglomerating
Class and Group Than Than Than Than Than Than Character
- -- -

I. Anthracitic
1. Meta-anthracite 98 ... ... 2 ... ...
nonagglom-
2. Anthracite 92 98 2 8 ... erating
3. Semianthracitec 86 92 8 14 ... ...
11. Bituminous
1. Low-volatile
bituminous coal 78 86 14 22 ... ...
2. Medium'volatile
bituminous coal 69 78 22 31 ... ...
3. High-volatile commonly
A bituminous coal ... 69 31 ... 14,000d ... agglomeratinge
4. High-volatile
B bituminous coal ... ... ... ... 13,000~ 14,000
5. High-volatile
C bituminous coal ... ... ... ... 11,500 13,000
10,500 11,500 agglomerating
III. Subbituminous
1. Subbituminous
A coal ... ... ... ... 10,500 11,500 \
2. Subbituminous
B coal ... ... ... ... 9,500 10,500 I
3. Subbituminous
C coal
N. Lignitic
1. Lignite A
...

...
...

...
...

...
...

...
8,300

6,300
9*500

8,300
I nonagglom-
erating

2. Lignite B
--- -
... ... ... ... ... 6,300 /
"This classification does not include a few coals. principally nonbanded varieties. which have unusual physical and chemical properties and
which come within the limits of fixed carbon or calorific value of the high-volatile bituminous and subbituminous ranks. All of these coals either
contain less than 48% dry. mineral-matter-free fixed carbon or have more than 15.500 moist, mineral-matter-free Btu per pound.
Moist refers to coal containing its natural inherent moisture but not including visible water on the surface of the coal.
If agglomerating, classify in low-volatile group of the bituminous class.
dCoals having 69% or more fixed carbon on the dry, mineral-matter-free basis shall be classified by fixed carbon, regardless of calorific value.
'It is recognized that there may be nonagglomerating varieties in these groups of the bituminous class, and there are notable exceptions in
high-volatile C bituminous group.

Reprinted from ASTM Standards D 388, Classification of Coals by Rank.


COMBUSTION
Fossll Fuels
--
Being extremely broad, these terms fail to de- to calculate to a dry, ash-free basis. The ash,
fine rank completely. Many investigators have however, does not correspond to the mineral
attempted to set up some scientific system of matter in coal. Thus, if the ash-free basis is used
classification to accurately define the bound- when classifying coal according to rank, signif-
ary lines of variation. Some better known bases icanterrors may be introduced. Remarkablyuni-
for classification are those of Persifor Frazer, formresults,however,areobtainedfromheating
Jr., who made the earliest published classifica- values of coals of a given rank and source when
tion of American coals in 1877; M. R. Campbell calculated to a dry mineral-matter-free basis.
and S. W. Parr, who both published papers on In ASTM classification by rank, the agglom-
the subject in 1906; David White, with publica- erating index, or caking quality of a coal, indi-
tions in 1909 and 1913; and 0. C. Ralston, cates the dividing line between noncaking
whose graphic studies of some 3000 coal coals and those having weakly caking prop-
analyses were made in 1915. Each of these will erties. The noncaking designation applies only
serve to type a coal within narrow limits, but to coals that produce a noncoherent residue
the suitability of a given coal for a specific pur- which can be poured out of the crucible as a
pose is best established by actual trial in the powder or flakes that will pulverize easily with
equipment for which it is ~ e l e c t e d . ~ thumb and finger pressure.
The American Society for Testing and Mate- The transformation of vegetal matter through
rials (ASTM) has established perhaps the most wood and peat to lignite and finally to anthra-
universally applicable basis for classifying coal cite results in a reduction of volatile matter and
according to fixed carbon and heating value oxygen content, with a simultaneous increase
(calorific value) calculated to a mineral-mat- in carbon content. This is illustrated graphi-
ter-free basis. As shown in Table 11, this scheme cally in Fig. 1 in which moisture-and-ash-free
represents a further development of the propo- volatile matter, fixed carbon, oxygen content,
sals of S. W. Parr. The high-rank coals are clas- and high heating value are given for various
sified according to fixed carbon on the dry ranks of coals as well as wood and peat.
basis, and the low-rank coals according to Btu
on the moist basis. Agglomerating indices dif- RANKS OF COAL
ferentiate between certain adjacent groups. The method of "proximate analysis" iden-
In commercial practice, it frequently suffices tifies the degree of coalification of the higher

--

Fig. 1. Progressive stages of transformatkn of vegetal matter into coal


COMBUSTION
Fossil Fuels

rank coals. In this method, a chemical analysis nous coals. Anthracite is used principally for
determines four constituents in coal: (1)water, heating homes and in gas production.
called moisture; (2) mineral impurity, called Some semianthracites are dense, but softer
ash, left when the coal is completely burned; than anthracite, shiny gray, and somewhat
(3) volatile matter, consisting of gases driven granular in structure. The grains have a ten-
out when coal is heated to certain tempera- dency to break off in handling the lump, and
tures; and (4) fixed carbon, the coke-like resi- produce a coarse, sandlike slack.
due that burns at higher temperatures after Other semianthracites are dark gray and dis-
volatile matter has been driven off. For the tinctly granular. The grains break off easily in
lower rank coals, heating value and caking and handling and produce a coarse slack. The
weathering properties determine rank. The granular structure has been produced by smaII
coal rank increases as the amount of fixed car- vertical cracks in horizontal layers of com-
bon increases and the amounts of moisture and paratively pure coal separated by very thin
volatile matter decrease. (Moisture and volatile partings. The cracks are the result of heavy
matter were squeezed and distilled from coal downward pressure, and probably shrinkage of
during its formation by pressure and heat, rais- the pure coal because of a drop in temperature.
'
ing the proportion'of fixed carbon.) On an
BITUMINOUS
ash-free basis, the difference in constituents
between a typical lignite, the lowest rank of By far the largest group, bituminous coals
coal, and an anthracite, the highest rank, is derive their name from the fact that on being
clearly shoivn in the following analysis: heated they are often reduced to a cohesive,
binding, sticky mass. Their carbon content is
Lignite Anthracite less than that of anthracites, but they have more
Fixed Carbon (FC) 30% 92% volatile matter. The character of their volatile
Volatile ,Matter (VM) 33% 5% matter' is more complex than that of anthracites
Moisture (H20) 37% 33% and they are higher in calorific value. They
burn easily, especially in pulverized form, and
The following description of coals by rank
their high volatile content makes them good for
gives some of their physical characteristics.
producing gas. Their binding nature enables
ANTHRACITE them to be used in the manufacture of coke,
Hard and very brittle, anthracite is dense, while the nitrogen in them is utilized in pro-
shiny black, and homogeneous with no marks cessing ammonia.
of layers. Uglike the lower rank coals, it has a The low-volatile bituminous coals are gray-
high percentage of fixed carbon and a low per- ish black and distinctly granular in structure.
centage of volatile matter. Anthracites include The grain breaks off very easily, and handling
a variety of slow-burning fuels merging into reduces the coal to slack. Any lumps that re-
graphite at one end and into bituminous coal at main are held together by thin partings. Be-
the other. They are the hardest coals on the cause the grains consist of comparatively pure
market, consisting almost entirely of fixed car- coal, the slack is usually lower in ash content
bon, with the little volatile matter present in than are the lumps.
them chiefly as methane, CH,. Anthracite is Medium-volatile bituminous coals are the
usually graded into small sizes before being transition from high-volatile to low-volatile
burned on stokers: the "meta-anthracites" burn coal and, as such, have the characteristics of
so slowly as to require mixing with other coals, both. Many have a granular structure, are soft,
while the "semianthracites," which have more and crumble easily. Some are homogeneous
volatile matter, are burned with relative ease if with very faint indications of grains or layers.
properly fired. Most anthracites have a lower Others are of more distinct laminar structure,
heating value than the highest grade bitumi- are hard, and stand handling well.
.-
COMBUSTION
Fossil Fucrlr

High-volatile A bituminous coals are mostly generally found close to the surface, contain
homogeneous with no indication of grains, but more than 45 percent moisture, and are readily
some show distinct layers. They are hard and won by strip mining.
stand handling with little breakage. The mois- PEAT
ture, ash and sulfur contents are low, and the Peat is not yet a commercial fuel in many
heating value high. countries where it is found, because of its very
High-volatile B bituminous coals are of dis- high moisture content and low heating value. It
'tinct laminar structure; thin layers of black, is a heterogeneous material of partially decom-
shiny coal alternate with dull, charcoal-like posed organic matter (plant material) and inor-
layers. They are hard and stand handling well. ganic minerals that have accumulated in a
Breakage occurs generally at right angles and water-saturated environment over a period of
parallel to the layers, so that the lumps gener- time. Its color can vary from yellow to brownish
ally have a cubical shape. black, depending upon the degree of biological
High-volatile C bituminous coals are of dis- decay, mechanical disintegration of the plant
tinct laminar structure. are hard and stand fibers, and the presence of sediment. A water-
handling well. They generally have high saturated environment inhibits active biologi-
moisture, ash, and sulfur content and they are cal decomposition of the plant material and
considered to be free-burning coals. promotes the retention of carbon and oxygen
that would normally be released as gaseous
These coals are brownish black or black. products of the biological activity.
Most are homogeneous with smooth surfaces, The universal problem in utilizing peat is its
and with no indication of layers. They have high moisture content. Even zfter draining a
high moisture content, as much as 1 5 to 30 per- peat bog and solidifying the peat, it can still
cent, although appearing dry. When exposed to contain 70 to 95 percent water.
air they lose part of the moisture and crack with The sulfur content of peat is normally quite
an audible noise. On long exposure to air, they low, varying from negligible to less than 1 per-
disintegrate. They are free-burning, entirely cent in dried peat. On the other hand, the ash
noncoking, coals. content of peat can vary from 2 to 70 percent in
assays of dry peat from a variety of sources.
LIGNITE
Lignites are brown and of a laminar structure
in which the remnants of woody fibers may be COAL MINING
quite apparent. The word lignite comes from The two general methods of mining are
the Latin word lignum meaning wood. Their stripping (open pit) and underground. In un-
origin is mostly from plants rich in resin. so derground mining the coal is undercut, top-
they are high in volatile matter. Freshly mined cut, or sheared and then blasted. Loading may
lignite is tough, although not hard, and it re- be by hand or machine. If hand-loaded, the
quires a heavy blow with a hammer to break the miners remove most of the larger visible im-
large lumps. But on exposure to air it loses purities while shoveling the coal into mine cars
moisture rapidly and disintegrates. Even when or onto conveyors. With machine loading no
it appears quite dry, the moisture content may such removal of impurities in the mine is pos-
be as high as 30 percent. Owing to the high sible. In strip mining the overburden is re-
moisture and low heating value, it is not moved by large power shovels, and the coal by
economical to transport it long distances. smaller shovels. If the coal is hard it is blasted
Unconsolidated lignite-(B in Table 11) is also prior to loading.
known as "brown coal." (Further differentia- Most coal seams contain interstratified
tion between the various lignites and brown bands of impurities which must be removed in
coals is given in Appendix A.) Brown coals are a coal-cleaning plant. Few coal seams are clean
COMBUSTION
FossN Fuels

enough to be mined by mechanical means and and highly desirable. Coal from wet-process
the coal shipped directly to market without cleaners must be dried by drainage, cen-
mechanical cleaning. trifuges, filters, or heat dryers to avoid exces-
Small strip mines frequently load coal of in- sive water in the final ptoduct.
ferior quality. Outcrop coal from such mines is
weathered, frequently mixed with impurities,
and of low calorific value. COAL SAMPLING
On the other hand, the better strip mines do
not mine coal near the outcrop. Coal seams firm A sample must represent the bulk of the coal
up and become equal to deep-mined coal when from which it is taken. The items that should
the overburden reaches a depth of 10 to 30 ft, be most representative are ash and moisture
depending on rank of coal and character of content. ~ h e ' w e i ~ hoft the gross sample and
overburden. In general, coal resists weathering the method of collecting and handling it de-
with increase of rank. Some anthracites can be pend on the size of the coal,,the moisture and
mined to the outcrop, while low-rank bitumi- ash content, and the purpose for which the
nous coals usually are not acceptable if the sample is collected. After collection, the sam-
overburden is less than 20 ft. ple must be handled so that the moisture con-
Practically all large, mechanized mines (un- tent does not change. If the coal is very wet,
derground and strip) have preparation plants considerable moisture may be lost during the
in which the coal is sized, mechanically handling. It may be necessary to stabilize the
cleaned, and otherwise prepared to give a high- moisture in the gross sample by air drying be-
quality fuel conforming to size specifications. fore crushing and quartering. In such cases, the
air-drying moisture loss must be determined.
The standard methods for sampling coals
COAL CLEANING and preparing them for analysis are ANSI/
ASTM Standards D 2234, Collection of a Gross
The oldest methods of cleaning coal use Sample of Coal, and D 2013, Preparing Coal
picking tables, which consist of a horizontal Samples for Analysis.
conveyor over which the coal moves slowly in
comparatively thin layers. Workers on both
sides of the conveyor pick the impurities from
the coal. This is probably the best way to clean COAL ANALYSIS
lump coal.
Most mechanical cleaning processes depend Two types of coal analyses are in general
on differences in specific gravity of coal and as- use: the proximate and the ultimate analysis,
sociated impurities to effect a separation. Other both expressed in percent by weight.
physical properties of coal and refuse utilized The proximate analysis gives information
to a minor extent are shape, resiliency, coeffi- on the behavior of coal when it is heated; that
cient of sliding friction, electrical conductivity, is, how much of the coal goes off as gas and tar
and froth-flotation differences. Magnetic sepa- vapors, called the volatile matter, and how
rators are used widely to remove tramp iron and much remains as fixed carbon. The proximate
thus prevent such material from getting into analysis is easy and supplies useful informa-
pulverizer mechanisms. tion to assist in the selection of coal for steam
Coal-cleaning processes may be wet or dry, generation. Along with the determination of
depending on whether water or air is used as volatile matter and fixed carbon also given are
the medium. In general, wet processes are the moisture and ash contents and the heating
more efficient than dry. With coal for which value in Btu per pound or MJ per kilogram. Sul-
dry processes are suitable, the product is dry fur is given as a separate determination. ANSI1
--
Forril Fuels
-
ASTM Standards D 3172 is the basic method for sifying coals according to rank. Two formulas
proximate analysis of coal and coke. available for making such calculations fromthe
The ultimate analysis gives the elements of as-received basis, are the Parr and approxima-
which the coal substance is composed. These tion formulas. (See box.)
elements include carbon, hydrogen, nitrogen,
oxygen and sulfur. Ash content is determined
as a whole, and, when desirable, separate anal- PARR FORMULAS:
ysis is made on the ash. ASTM Standards Dry, Mm-free FC =
D 3176 is the standard method for ultimate
analysis of coal and coke.
Coal analysis may be given on several bases, Dry, Mm-free VM = 100 - Dry, Mm-free FC
and it is customary to select the basis to suit the Moist, Mm-free Btu =
application. Thus, for the purposes of classifi- Btu - 50s
x 100
cation, the dry or moist and mineral-matter- GO- (1.08A + 0.5-
free bases are generally used. In combustion Note: The above formula for fixed carbon
calculations the as-received basis is applicable. is derived from the Parr formula for vol-
AS-RECEIVED BASIS atile matter.4
APPROXIMATION FORMULAS:
The as-received analysis of a fuel represents
the actual proportions of the c:onstituents in the
fuel sample as received at the laboratory. The
sample may be fuel as fired, as mined, or in any
other given condition. Dry, Mm-free VM = 100 - Dry, Mm-free FC
Moist, Mm-free Btu =
MOISTURE-FREE (DRY) BASIS
---- Btu x 100
Moisture content is variable, even in the 100 - (1.1A + 0.1s)
same coal, under different conditions of han- where
dling and exposure. For example, coal as re- Mm = mineral matter
ceived at a plant may contain an amount of Btu = British thermal units per pound
(calorific value)
moisture different from that received at the
FC = percent of fixed carbon
laboratory for analysis, and both may vary with
VM = percent of volatile matter
weather conditions. Also, in a plant burning
M = percent of moisture
pulverized fuel, the coal may carry one per-
A = percent of ash
centage of moisture as delivered to the raw-coal
S = percent of sulfur
bunker, another as delivered to the pulverizer,
another as delivered to the pulverized-fuel The formulas can be used to check
bunker (in a storage system), and still another analyses and frequently to identify the
as fired. Furthermore, when a laboratory de- source and rank of the fuel. For example,
termines an ultimate analysis as wet, as- the heating value of coals of a given rank
received, or as-fired, the moisture can be and source are remarkably uniform when
reported as hydrogen and oxygen and added to calculated on a dry, Mm-free basis.
the hydrogen and oxygen of the coal itself. In commercial practice it frequently
suffices to calculate to a dry, ash-free basis
DRY MINERAL-MATTER-FREEBASIS
as follows:
As mentioned previously, because the ash
does not correspond in percentage to the min- Dry, ash-free FC = - (M + A)
eral matter in the coal, errors are introduced
which become significant in problems of clas-
COMBUSTION
fossll Fuels

ITEMS OF PROXIMATE ANALYSIS appearance. Coal also contains water that is


frequently but erroneously called "water of
Coal as mined and shipped contains varying combination," this water being concealed, as
amounts of water. A~curatedetermination of in hydrated salts, by the dry appearance of the
this water is not as simple as one would expect, material. The condition in which the so-called
since the sample frequently can lose moisture "water of combination" in coal exists is prob-
on exposure to the atmosphere. This is particu- lematical; in the true chemical sense the water
larly true during the reduction of the sample for is probably not "combined," that is, united
analysis. To prevent this loss, it is customary to with another substance in definite proportions,
air-dry the entire sample under specified con- as determined by its relative molecular weight
ditions before fine grinding for analysis. The and the number of molecules.
moisture is then determined by a standard pro- There is np sharp line of demarcation; the
cedure of drying in an oven, and the loss in "free" water cannot be separated with exact-
weight is corrected for the air-drying loss. The ness from the "combined" water by chemical
moisture in coal does not represent all of the analysis. Under all ordinary drying conditions,
water present, since water of dkcomposition there is a tendency for more than the "free"
(combined water) and water of hydration are water to leave the coal. But the "combined" or,
not given off under the conditions of test. The "inherent" water, is distinctly different from
moisture content of coals varies widely. In the the "free" water in its properties, as it has a
high-rank low-volatile bituminous coals it is subnormal vapor pressure and an energy
frequently under 5 percent. High-volatile bi- change is involved in its combination with, or
tuminous coals may have as much as 12 percent separation from, the coal substance. In other
and lignite, as high as 45 percent as mined. The words, the inherent water is held more te-
finer sizes will often retain more moisture than naciously and cannot be entirely removed by
the coarse sizes of the same coal subjected to drying the coal in ordinary air which contains
rainfall or wet-washing. relatively large quantities of moisture.
ASTM defines total moisture in coal as that
moisture determined as the loss in weight in an PRACTICAL EFFECTS OF WATER
air atmosphere under rigidly controlled condi-
tions of temperature. time and airflow as estab- As ordinarily found in the market, coal,
lished inASTM Standards D 3302. when su~erficiallv - contains water; an an-
" dry,

INHERENT MOISTURE thracitic or low-volatile coal in this condition


contains possibly 2 percent water; a high-
Inherent moisture in coal is that moisture volatile bituminous coal, 6 to 10 percent; and a
existing as a quality of the coal seam in its natu- subbituminous coal, 14 to 18 percent. Even
ral state of deposition and includes only that finely crushed or powdered coal does not be-
water considered to be a part of the deposit, and come dry in ordinary air and requires an arti-
not that moisture which exists as a surface ficially and thoroughly dried atmosphere to
addition. There are a number of other terms re- remove all of its water content.
lating to moikture in coal, including: bed mois- Humidity conditions may appreciably alter
ture, equilibrium moisture, air-dry moisture the weight of exposed coal, independently of
loss, free moisture, water of hydration and the actual fall of rain or snow. In other words,
others of lesser consequence. coal is frequently hygroscopic. After being
CONDITION OF WATER IN COAL transferred from storage in an atmosphere of 40
percent humidity to one of 7 5 percent hurnid-
Like many other substances of vegetable or- ity, a bituminous coal, for example, may gain 3
igin, coal contains water in the ordinary con- percent and a subbituminous 7 percent in
dition, which may give the coal a moist weight by absorption of moisture.
COMBUSTION
Fossil Fuels

FREE SUPERFICIAL WATER face to be wet, and therefore retains less water.
In wet coal, the water in excess of a certain See Table 111.
percentage (which depends on the kind of coal) There is no ready means of separating
is mechanically held in the free state, its va- sharply the superficial and the inherent water
por pressure and other properties being, for of coal. Unless the air is saturated, the superfi-
all practical purposes, normal. This excess cial water can all be removed by air drying, the
moisture may be termed superficial or acciden- rate of evaporation depending on the tempera-
tal moisture. All water in the coal above ap- ture, the humidity of the air, and the fineness of
proximately 3 percent in the anthracite coals, the coal. But at the same time, part of the inher-
12 percent in bituminous, and 22 percent in the ent water leaves the coal and continues to do so
subbituminous coals may be so classed, al- as long as its vapor pressure is higher than that
though this line of demarcation is more or less of the air.
variable even among coals of the same kind. By the expression "inherent water" in coal or
The percentage of superficial water retained in any material, therefore, is meant the water
by coal that has been wetted and the water which exists as such but which has a vapor
drained off is greatly affected by the size of the pressure less than the normal.
coal. In screenings or slack, which contains VOLATILE MATTER
pieces of many different sizes, the particles The volatile matter is that portion which, ex-
pack closely together and form small in- clusive of water vapor, is driven off in gas or
terstices which retain water by capillarity. vapor form when the coal is subjected to a
Screened lump, on the other hand, or run-of- standardized temperature test. It consists of
mine with a large proportion of lump, has hydrocarbons and other gases resulting from
much larger interstices and relatively less sur- distillation and decomposition.
- - -

Table 111. Water Retention After Draining1

Kind of Coal
- - - - -

Bituminous, New River, WV.:


Screenings a
Sized "buckwheat" b
Bituminous, Pittsburgh bed, PA.:
Screenings a
Sized "buckwheat" b
Bituminous, Macoupin County, IL.:
Screenings a 28.60 6.84 .32
Sized "buckwheat" b 16.71 6.63 3.40
Subbituminous, Big Horn County, in.:
Screenings a 32.58 14.24 6.38
Sized "buck~z~heat" b 18.70 13.79 6.65
From H. C. Porter and 0. C. Ralston, "Some Properties of the Water in Coal," U.S. Bureau of Mines, Technical Paper 113. \2'ashington; U.S.
Bureau of Mines, 1916.
*Total water content of coal after soaking and draining.
"Normal water content in commercially "dry" coal.
"'M'ater retained in coal after "air-drying" in laboratory at 35%.
o Through l/z inch mesh screen.
b From 'h inch to 1 inch in diameter.
COMBUSTION
Fouil Fuels

Volatile matter is determined by prescribed For high-calcium-content coals, however, the


methods which may vary according to the na- ash can be higher than the mineral matter due
ture of the material, but in the case of coal and to retention of the oxides of sulfur.5
coke Method D 3175 is used. The ASTM definition for coal ash is the inor-
Temperature and time are a vital concern in ganic residue remaining after ignition of com-
this test, since they actually determine the def- bustible substances, determined by definite
inition of volatile matter. Temperature must be prescribed methods. This definition is fol-
950C r 20C, and heating time must be ex- lowedby two notes, one of which states that ash
actly 7 minutes. may not be identical-in composition or
The main constituents of volatile matter in quantity-to inorganic substances present in
all ranks of coal are hydrogen, oxygen, carbon the coal before ignition. The second note
monoxide, methane and other. hydrocarbons, specifies thatt in the case of coal and coke, the
and that portion of moisture that is formed methods shall be those prescribed by ASTM
by chemical combination durlng thermal de- Standards D 3174.This method determines the
composition of the coal substance. The com- ash content by weighing the residue remaining
position of volatile matter varies greatly for after the coal is burned under rigidly controlled
different ranks of coal. conditions of sample weight, temperature, time
Volatile matter is used to establish the rank of and atmosphere, oxidizing or reducing.
coals, to indicate coke yield on carboniza- Although the definition of ash content used
tion processes, to provide the basis for purchas- in other countries is similar to the American
ing and selling, and to establish burning definition, the ashing conditions may be dif-
characteristics. ferent. Therefore, it is desirable to spell out the
Because of the arbitrary nature of this test, conditions used, particularly when the results
caution must be used in comparing the results from laboratories in different countries are to
of volatile analyses with those obtained from be comp'ared.
tests run in other countries. Details of the vari- During the burning process, various chemi-
ous national standards vary greatly. cal and physical changes take place. The con-
ditions of oxidation determine the number and
FIXED CARBON
extent of such changes; thus, a great degree of
The fixed carbon is the combustible residue variability can be expected in separate deter-
left after driving off the volatile matter. It is not minations of ash content even on portions of
all carbon, and its form and hardness are an in- the same coal sample unless standardized pro-
dication of the coking properties of a coal, and cedures are closely followed. In particular,
therefore, a guide in the choice of fuel-firing this is true of coals with relatively large
equipment. In general, the fixed carbon repre- amounts of carbonates or pyrite. ,
sents that portion of the fuel that must be Ash is usually considered the product of
burned in solid state, either in the fuel bed on a complete oxidation of coal. It is composed of
stoker, or as solid particles in the pulverized- the oxides formed from the mineral con-
fuel furnace. stituents of coal. However, these minerals may
The fixed carbon in a proximate analysis is a be present in two forms in coal: as visible im-
calculated figure obtained by subtracting from purities, or as minute impurities so finely di-
100 the sum of the percentages of moisture, vided and so intimately mixed that they may
volatile matter and ash. be considered a part of the coal structure.
ASH The term inherent or fixed ash content is
Ash is the noncombustible residue after used to designate that portion of the ash con-
complete combustion of the coal. The weight of tent that is structurally part of the coal and
ash is usually slightly less than that of the min- cannot be separated from it by mechanical
eral matter originally present before burning. means. This is a relative term, however, and
-
COMBUSTION
Fossil Fuels

will have different values, since mechanical SULFUR


separation is accomplished at varying levels Sulfur content of a fuel is useful in judging
according to the size of the coal. the corrosiveness of the products of combus-
In general, when the term inherent ash is tion. Combustion of sulfur forms oxides, which
used, it is assumed it refers to the residue that combine with water to form acids that may be
remains after coal has been broken to the size deposited when the combustion gas is cooled
at which it is to be used, cleaned by a mechan- below its dew-point temperature.
ical process, and incinerated. Probably the Sulfur in coal occurs mainly in three forms. It
first test developed for coal, the determination can be present in organic combination as part of
of ash content continues to be one of the most the coal substance; it can be present as the sul-
important of the tests performed. fide ion in pyrites and marcasite; or it can be
present as the sulfate ion. Rarely, sulfur may
ITEMS OF ULTIMATE ANALYSIS occur as elemental sulfur, but in insufficient
quantities to be appreciable. ANSIlASTM
Ultimate analysis is needed for the computa- Standards D 2492 gives a standard test method
tion of air requirements, weight of products of for the determination of the forms of sulfur in
combustion, and heat losses, on boiler tests. coal; sulfate sulfur and pyritic sulfur are first
The air requirements and the weight of prod- determined, and organic sulfur is found by de-
ucts of combustion determine fan sizes. The termining the difference from the total sulfur.
following are items of ultimate analysis as Two methods are generally accepted for total
determined byASTh4 Standards D 3176. sulfur determination. Eschka's method con-
verts all the sulfur present in the coal to the sul-
TOTAL CARBON
fate ion, which is then precipitated as BaS04.
Total carbon includes both the carbon in the The Eschka method requires a time period-
fixed carbon and in the volatile matter, and including sample preparation-of up to 24
will be proportionately greater than the fixed hours, so a more rapid method of high-tem-
carbon as the volatile content of the coal in- perature combustion has been adopted. Details
creases. All this carbon appears in the prod- and analytical procedures for both of these
ucts of combustion as C02when the fuel is methods, as well as the bomb-washing method,
completely burned. an alternate third method, may be found in
ASTIM Standards D 3177.
HYDROGEN
OXYGEN
All hydrogen in the fuel is burned to water-
and, together with the moisture in fuel, ap- The oxygen content of fuels is a guide to the
pears as water vapor in the waste gas. In the rank of the fuel. The amount of oxygen is high
publications of the U.S. Bureau of Mines, ul- in low-rank fuels like lignite. Oxygen in fuels is
timate analysis of coal on as-received basis in- in combination with carbon or hydrogen and,
cludes moisture in the hydrogen and oxygen therefore, represents a reduction in the poten-
items. The weight of the water vapor in the tial heat of a fuel. High-oxygen fuels have low
products of combustion is nine times the heating values.
weight of the hydrogen item. As there is no direct ASTM method of deter-
mining oxygen, it is calculated by subtracting
NITROGEN
from 100 the sum of the other components of
Nitrogen in most solid fuels is relatively low the ultimate analysis. Any errors incurred in the
and of little importance in combustion calcula- other determinations are placed on the oxygen,
tions. However, a portion of the fuel nitrogen and a material balance cannot be obtained to
may react during combustion to form nitrogen aid in checking the accuracy of the ultimate
oxides. analysis.=
COMBUSTION
Fossil Fuels

HEATING VALUE ASH-FUSION TEMPERATURE


The calorific or heating value of a solid fuel is When coal ash is heated, it becomes soft and
expressed in Btu per lb (or MJ per kg) of fuel on sticky and, as the temperature continues to rise,
as-received, dry, or moisture- and ash-free ba- it becomes fluid. A-STM-Standards D 1857 is
sis. It is the amount of heat recovered when the the method for measuring fusibility of coal ash.
products of complete combustion of a unit This test is an observation of the temperatures
quantity of a fuel are cooled to the initial tem- at which triangular pyramids or cones pre-
perature of the air and fuel. pared from coal ash and coke ash attain and
Heating values as determined in calorimeters pass through certain defined stages of fusing
are termed high or gross heating values, and in- and flow when heated at a specific rate in con-
clude the latent heat of the water vapor in the trolled, mildly reducing, and where desired,
products of combustion. The most common oxidizing atdosphere.
type of calorimeter in use today is the adiabatic This method is empirical, and strict obser-
bomb calorimeter, and ASTM Standards D vance of the requireme@ and conditions is
2015 covers this test. In actual operation of necessary to obtain reproducible temperatures
boilers, the water vapor in the combustion gas and to enable different laboratories to obtain
leaving is not cooled below its dew point, and concordant results.
this latent heat is not available for making Four stages of fusion temperature are usually
steam. The latent heat can be subtracted from reported in American practice:
the high, or gross, heating value to give the low, 1. Initial, or the first rounding of the cone
or net, heating value. 2. Softening, when the height has diminished
This deduction in Btu per lb of fuel is equal to until it is equal to the width at the base
the total pounds of water vapor per lb of fuel
3. Hemispherical, when the height of the lump
(moisture in the fuel, plus vapor formed by
equals one-half the width of the base
combustion of hydrogen of the coal substance)
multiplied by the latent heat of evaporation at 4. Fluid, when the mass is no higher than one-
the partial pressure of the vapor in the exit gas. sixteenth inch
The value used varies from 1030 to 1080 Btu The test for fusion temperatures may be run in
per lb of water vapor. Low or net heating values either a reducing or an oxidizing atmosphere.
are standard in European practice, and high The ash-fusion temperature given in most
heating values are standard in American prac- existing tables is the softening temperature
tice.' (H = W) in a reducing atmosphere. This sub-
For anthracite and bituminous coal, gross ject is expanded in Chapter 3.
heating value in Btu per pound of coal can be GRINDABILITY
calculated approximately by a formula of the
Dulong type. (See box below.) This test determines the relative ease of pul-
verization of coal in comparison with coals
DULONG-TYPE FORMULA chosen as standards. The Hardgrove method
has been accepted as the standard, and ASTM
HHV = 14,600 C + 62,000 (H--+) + 4050 S Standards D 409 is the Grindability of Coal by
where: HHV is in Btullb and C. H,,Or and S are carbon, the Hardgrove-Machine Method.
hydrogen. oxygen, and sulfur in the coal, respectively, Each Hardgrove machine is calibrated by use
expressed in fraction of a pound. usually as fired. The of standard reference samples of coal, having
results are approximate because the formula does not take grindability indexes of approximately 40, 60,
into account the heats of dissociation and similar 80 and 100. Standard coals may be obtained
phenomena occurring during combustion. For low-rank
coals, the heating values obtained by this formula are from the U.S. Bureau of Mines i n Pittsburgh for
generally too low. the purpose of calibration.
The Hardgrove-index number reported by
COMBUSTION
Fossil Fuek

the laboratory is based on an original soft coal ing characteristics exhibited when used on
chosen as a standard coal whose grindability different types of stokers. Of particular interest
index was set at 100. Therefore, the harder the in this edition is the behavior of coal when
coal, the lower the index number. burned in pulverized condition.
Since the grindability index varies, not only The combustion of pulverized coal is a very
from seam to seam but within the same seam, complex process consisting of a number of
grindability data are of utmost economic im- overlapping steps, including heating, ignition,
portance to the users of commercial grinding devolatization and char (carbonaceous residue)
and pulverizing equipment. burnout. The sequence of these events is de-
The results of grindability measurements picted in Figure 2. Char burnout occupies the
by the Hardgrove machine are affected by sev- majority of the time required for complete com-
eral factors, among them the ash and moisture bustion. This step, therefore, constitutes a bot-
content, temperature, and the presence of tleneck which dictates the overall combustion
different petrographic constituents (organic efficiency of pulverized coal. Each of these
components distinguishable by microscopic in- steps is briefly described below.
spection). Chapter 11 has more information. HEATING
TYPICAL COAL ANALYSES The cloud of relatively cool pulverized coal
U.S. Bureau of Mines publications contain particles entering a hot furnace is heated by
the proximate and ultimate analyses and soften- flame radiation and by mixing with recircu-
ing temperatures of ash of several coals from lated hot combustion products. This initial
various states. The coals are identified by coun- phase in the coal combustion process results in
try, mine, coal bed, and rank.6 the loss of moisture from and minor devolatiza-
Table IV (Pg. 2-16) gives analyses of several tion of coal particles.
typical U.S. coals and coke, ciassified by the
ASTM system of Table 11. Besides proximate
and ultimate analyses, high heating value and Upon further heating of the particle cloud, a
theoretical combustion-air requirements "A'' point is reached where ignition occurs. The
(on a pounds-per-million-Btu basis) are given. temperature at which ignition occurs is con-
Table V (Pg. 2-18) presents an overview of coals trolled by a balance between the rates of heat
from outside the continental U.S. generation and heat loss; hence it may vary de-
Appendix A gives extensive data on both pending upon the furnace design and operating
United States coals and coals from all the major conditions. Ignition stability exists when the
producing areas of the world. Also, in Appen- rate of heat generation is equal to the rate of
dix A, the International Systems for Classifica- heat loss.
tion of Hard Coals, Brown Coals and Lignites
are discussed in detail. Additional analyses of Heating And Minor Devolatilization
American, European, and Asian coals are
given, along with international classifications.
"I,
1
Ignition

Maior Devolatilization 1
BURNING CHARACTERISTICS
OF COALS
.
Coal is burned in power plants in either the
crushed and sized form, or in the crushed and
subsequently pulverized form. Previous edi-
b Time, Seconds -
tions of this text have concentrated on the burn- Fig. 2 Chronology of the combustion process
COMBUSTION
Fossil Fueh

cific conditions. Typical ranges of flammability


Table "Im
Typical Flammability Indices indices determined for coals of various rank are
Coal Flammability Index shown in Table VI. The flammability index of
Rank - - ("0 a fuel is useful in classifying relative ignition
behavior by virtue of comparison with those of
Anthracite 1450-1750
fuels with known commercial performance.
Bituminous 1050-1250
Subbituminous 900-1100 CHAR REACTIVITY
Lignite 800-1050
In trying to understand the burning charac-
teristics of coal, char reactivity is focused upon
because its burnout takes much longer than the
After ignition occurs, the devolatization rap- volatile mattgr release (i.e., devolatilization)
idly proceeds, typically requiring approxi- and burnout in the gas phase b>r approximately
mately 10 percent of the overall combustion one order of magnitude (Figure 2). Char reactiv-
time beyond ignition. Studies have indicated ity is affectedby the quantity and rate of volatile
that the volatile matter yields during the rapid matter released as well as other fuel aspects
heating rates (10' to 1OS0C)characteristic of (swelling, agglomerating tendency and mineral
dispersed particles in coal flames are generally matter).
significantly higher than those observed during Swelling and agglomeration affect the nature
slow heating rates encountered in ASTM proxi- of the pore structure of the residual char, thus
mate volatile-matter determination.9.10 The rate influencing the burning characteristics of this
of devolatization, the total quantity of volatile char. The mineral matter, depending on its
matter released, and the composition/calorific chemical nature and degree of dispersion in the
value of the volatile matter play significant coal matrix, may catalyze or hinder the chemi-
roles during the early stages of combustion. cal reactivity of the coal particular char.
Therefore, these characteristics have a strong A procedure has been developed at C-E for
impact on ignition stability. preparing coal chars under specific conditions
C-E has developed a simple bench-scale test and characterizing them from the standpoints
to directly assess the relative ignition stability of their specific pore structures and reactivi-
characteristics of a pulverized coal." This test ties.12
determines a Flammability Index which is the Char Preparation. C-E's Drop-Tube Furnace
ignition temperature of a suspension of pulver- System (Figure 3), which is a 2-inch inside di-
ized fuel in an oxygen atmosphere under spe- ameter laminar-flow reactor, is used to prepare
Primary Stream

-
1-Water-Cooled -' e--carrier Gas
Sample Injector
-Syringe Pump
-\& FIOW
-Secondary Gas
Stra~ghteners
Test Furnace

Water-Cooled Sampling probe


L

4
1r Drive
Suction pump

Fig. 3 Schematic of the Combustion Engineering Drop-Tube Furnace System


COmVSnON
Fostll Fuels
--

Table IV. Analyses of Typical U.S. Coals, as Mined


A at Zem
-%Proximate Analysis- % U l t i m a t e Analysis HHV, Excess Air,
State Rank Hz0 VM FC ASH Hz0 C Hz S 0 2 Nz BMb ~b/106Bt~*

AR Lvb 3.4 16.2 71.8 8.6 3.4 79.6 3.9 1.0 1.8 1.7 13,700 774
MD Lvb 3.2 18.2 70.4 8.2 3.2 79.0 4.1 1.0 2.9 1.6 13,870 761
OK Lvb 2.6 16.5 72.2 8.7 2.6 80.1 4.0 1.0 1.9 1.7 13,800 775
WV Lvb 2.7 17.2 76.1 4.0 2.7 84.7 4.3 0.6 2.2 1.5 14.730 767

PA Mvb 3.3 20.5 70.0 6.2 3.3 80.7 4.5 1.8 2.4 1.1 14,310 765
VA Mvb 3.1 21.8 67.9 7.2 3.1 80.1 4.7 1.0 2.4 1.5 14.030 778

AL Hvab
CO Hvab
KS Hvab
KY Hvab
MO Hvab
NM Hvab
OH Hvab
OK Hvab
PA Hvab
TN Hvab
TX Hvab
UT Hvab
VA Hvab
WA Hvab
WV Hvab
IL Hvcb
KY Hvcb
MO Hvcb
OH Hvcb
WY Hvcb
IL Hvbb 12.1 40.2 39.1 8.6 12.1 62.8 4.6 4.3 6.6 1.0 11,480 769
IN Hvbb 12.4 36.6 42.3 8.7 12.4 63.4 4.3 2.3 7.6 1.3 11,420 758
IA Hvbb 14.1 35.6 39.3 11.0 14.1 58.5 4.0 4.3 7.2 0.9 10,720 754
COMBUSTION
Fossll Fuels

Table IV. Analyses of Typical U.S. Coals, as Mined Continued -


A at Zero
-%Proximate Analysis- 40Ultimate A n a l y s i s HHV, Excess Air,
State Rank Hz0 VM FC ASH Hz0 C Hz S 0 2 N2 Bhkb Lbll06Bh*

co sub 19.6 30.5 45.9 4.0 19.6 58.8 3.8 0.3 12.2 1.3 10,130 756
WY sub 23.2 33.3 39.7 3.8 23.2 54.6 3.8 0.4 13.2 1.0 9,420 757

ND LigA 34.8 28.2 30.8 6.2 34.8 42.4 2.8 0.7 12.4 0.7 7,210 750
TX Lig A 33.7 29.3 29.7 7.3 33.7 42.5 3.1 0.5 12.1 0.8 7,350 752
I
'A is the air required for combustion under stoichiometricconditions (no excess air), with 0.013 Ib H,O per lb dry air.
"Orchard Bed. "'Mammoth Bed. '*"Holmes Bed. RANK KEY: Ma-Meta-anthracite.A-Anthracite. Sa-Semi-anthracite, Lvb-Low-Vol. Bituminous,
Mvb-Med.-Vol.Bituminous. Hvab-High-Vol. Bituminous A. Hvcb-High-Vol. Bituminous B, Hvbb-High-Vol.Bituminous C, Sub-Subbituminous, Lig A-
Lignite A

each coal char. This entails pyrolyzing a ratus (TGA)


. . in air at 1290F [70O0C) to deter-
70 + 2% through 200 mesh representative coal mine its burn-off under isothermal conditions
sample in nitrogen atmosphere at 2650F to as a function of time. These types of characteri-
drive off the volatile matter under heating rates zation give quick classifications of the pore nat-
which are commensurate with those encoun- ure and reactivity of a given coal char by virtue
tered in pulverized coal-fired boilers. The re- of comparison with the information in the data
sulting char is size-graded to 200x400 mesh. bank.
Char Characterization. This 200x400 mesh, Typical Results. TGA burn-off curves of chars
volatile matter-free, char is subjected to pore prepared from coals ranging in rank from lig-
structural analysis through measurements of its nite to anthracite are given in Figure 4 along
BET surface area in nitrogen at -196OC13 and with corresponding BET surface areas. In gen-
mercury and helium densities under specific eral, the reactivity of a char increases with in-
conditionslJ, which can be used to determine creasing BET surface area. Fuels whose chars
its total open porosity. This same char is also have BET surface areas greater than 50 m2/gare
burned in a thermo-gravimetric analysis appa- typically very reactive, and, hence, do not

100

80
BET Surface Area
60
Parent Fuel

40 * SubA
--- Lig A
-* hvAb
20 - Med. Vol. Bit.
Anthracite

'0 2 4 6 8 10 12 14 16 18 20
Time, M~nutes
1 I

Fig. 4 Thermogravimetric bum-off of 200x400 mesh LTTFS chars at 700C


COMBUSTION
Fogil Fuels

Table V. Typical Analyses of Coals of the World


TYPICAL ANALYSIS-AS RECEIVED HHV,
Country District or Mine Hz0 Vol FC Ash Sul MJIkg BtWLb

Argentina Turbio River 8.6 34.8 40.9 15.7 0.9 24.1 10,360

Australia New South Wales


Western Field 2.6 30.0 52.8 14.6 0.7 27.0 11,620
Southern Field 0.6 23.29 65.08 . 11.0 3.7 30.4 13,090
Queensland 1.5 37.0 49.9 11.6' ... 28.6 12,300
Victoria (Brown Coal) 66.3 17.7 15.3 0.7 0.1 8.6 3,700

Belgium Batterie and Vidette 1.0 8.5 63.5 27.0 ... 24.9 10,710

Brazil Sao Jeronimo 13.8 24.7 27.1 34.4 3.0 15.3 6,600
Sao Jeronimo-
Washed 16.0 23.1 32.9 28.0 0.9 17.6 7,570
Butia 11.5 32.0 42.9 13.6 1.3 ...
Canada Alberta-Drumheller . 20.0
Saskatchewan-Souris 35.0
British Co1.-Crows Nest 1.4
Nova Scotia-Emery 4.0

Chile Schwager 2.9


Lota 3.4
Mafil 12.6

China Kailin 2.5


Kew Loong Kieng 5.4
Kiaping 3.5

Colombia Bogota 5.3 23.4 63.7 7.6 0.8 33.1 14,220

France Bethune
Aniin
Germany Frimmersdorf-
Westfield 60.7 20.0 16.7 2.6 0.2 9.9 4,240
Saar 9.7 31.8 18.7 9.8 . . 25.7 11,040
Saxony 53.1 25.3 18.1 3.5 0.9 10.5 4,500
Westphalia 1.7 23.7 69.2 5.4 .. . 32.5 13,970
Lower Silesia 4.5 25.6 56.1 13.8 ... 27.4 11,770

United Kingdom
Wales Cardiff
Arley
England Durham
Scot-land Lanark
Greece Aliveri 31.0 30.0 21.0 18.0 ... 13.1 5,640
COMBUSTION
Fossil Fuels

Table V. Typical Analyses of Coals of the World-Continued

TYPICAL ANALYSIS-AS RECENED _ HHv,


Country District or Mine Hz0 Vol FC Ash -Sul - - MJlkg BNLb

India Bermo Seam 1.9 21.1 50.4 26.6


Damodar Valley 4.0 12.8 41.1 42.1
Trombay 7.2 20.8 44.7 27.3
Umaria Field 5.3 27.1 47.8 19.8
Palana 41.4 29.2 23.8 5.6
Italy Sardinia 3.6 39.8 33.0 23.6
r
Japan Hiyoshi-Anthracite 2.7 5.8 75.0 16.5
Hukuho 8.6 33.8 44.5 13.1
Niiura 19.0 24.8 31.2 25.0

Mexico Palu 1.3 21.0 59.0 18.7 0.7 28.4 12,200

Peru Goyllarisquisga 4.0 35.3 29.5 31.2 ... 20.7 8,910


Quishuarcancha 2.5 35.8 34.8 26.9 22.6 9,730
Poland Katowice
' Upper Silesia 4.0 31.6 58.4 6.0 ... 31.4 13,500

Russia Donetz Anthracite 2.0 3.5 83.0 11.5 0.8 30.0 12,910
Donetz Med. Vol. 3.5 21.0 71.0 4.5 3.6 33.8 14,530
, Donetz Long Flame 7.0 40.0 31.5 21.5 5.7 26.3 11,300

Spain Asturias
Asturias
Zaragoza
Turkey Raihenburg 17.1 34.9 24.8 23.2 0.5 15.5 6,660

South Natal 4.2 16.6 70.5 8.7 4.18 ... ...


Africa Orange Free State 5.6 28.4 50.4 15.6 1.5 24.7 10,640
Transvaal 2.2 27.0 57.5 13.3 0.7 28.2 12,120

Venezuela Barcelona 3.0 36.1 57.5 3.4 1.4 31.8 13,680


Yugoslavia hatolia 1.4 29.4 51.3 17.9 1.0 27.3 11,720

necessarily show a correlation with TGA reac-


tivities. Both the BET and TGA apparatus offer SOLID FUELS
quick means for classifying char surface prop- OTHER THAN COAL
erties and preliminary reactivity assessment,
respectively. Many solid or semisolid fuels other than coal
C-E has also developed an advanced method- are used in the steam-generating process. As
ology for more accurate prediction of car- described in this section, the majority of these
bon loss in commercial pulverized coal-fired fuels result from the production of primary in-
boilers." This methodology is described in dustrial goods; some are waste fuels that de-
Chapter 6 . pend upon local economic conditions for their
use as sources of energy. They occur in many "coke." Many varieties of bituminous coals, on
different forms (most of them not capable of the other hand, become plastic and "melt"
being pulverized like coal), have a wide range when heated to only 500-700F. Due to the res-
of calorific content, and many require special inous substances in these coals, the particles of
equipment for efficient burning. the molten mass stick together, forming a por-
ous coke which varies in color from dull gray to
COKE AND COKE BREEZE
light silvery gray.
Coke is the fused solid residue left when cer- The character of the coke residue is depend-
tain coals, petroleum, or tar pitch-are heated in ent on the kind of fuel distilled, the tempera-
an atmosphere excluding oxygen, so as to expel ture arid pressure to which the fuel is exposed,
their volatile content. The process of thus de- and the type of oven used.
composing these fuels into their gaseous and When the distillation process is carried on
solid fractions is known as destructive distilla- in temperatures over 700-900F, it is called
tion or carbonization. high-temperature carbonization, whereas low-
When anthracite is rapidly heated out of con- temperature carbonization takes place below
tact with air to, say, 1600F,it will evolve some 700-900F. Both the character and relative
volatile matter, but remain essentially un- quantity of solid and gaseous distillation prod-
changed in form. Lignites, when subjected to ucts depend on the temperature employed.
the same treatment, give off a large amount of This is best illustrated by a comparison be-
gas, while their solid, charry residue cracks tween Fig. 5 which shows the volume and kind
and shrinks, but does not fuse together to form of gas evolved by an English coal at high tem-
peratures and Fig. 6 which shows the same re-
lation for a U.S. coal at low temperatures. With
Temperature,' C an increase in temperature, there is a corre-
3.20 , 600
I
800
I ,
I
1000 sponding increase in the evolution of hydrogen
and carbon monoxide, at the expense of meth-
2.88 - ane and the higher hydrocarbons. Because of its
greater yield of gas, the high-temperature pro-
cess is preferred for fuel-gas-making purposes
and for metallurgical coke. Low-temperature
distillation, on the other hand, requires less
heat per ton of coke produced and is, therefore,
more economical for making domestic coke.
Good coke from this process is shiny, hard,
and uniformly porous. It has little volatile mat-
ter and is smokeless. If used for metallurgical
purposes, it must not have too much sulfur; in
foundry work, not much moisture; for domestic
use, as little ash as possible; and for making
blue-water gas, as high an ash-fusion tempera-
ture as possible. The proportion of ash in coke
is seen from Fig. 6 to be higher than the ash
content of the original coal.
For firing steam generators, good coke is
Temperature," F - normally considered uneconomical. But "coke
breeze," degraded-size coke with as much as 40
Fig. 5 Gaseous products of distillatiqn of Silk- percent passing through a %-inch mesh screen,
stone coal (Great Britain) at high temperatures is advantageously burned on certain types of

nrr
~\WIJ''
COMBUSTION
Fossil Fuels

Coke-Oven Gas.O'OI by Volume


(,Scrubbed and Cooled)

Coke-Oven Crude Tar, O


o/ by Volume
,
Commercial (90%) Benzol,% by Weight
I

Coal Tar Pitch, OO


/ by Weight

-
in Scrubbing
and Cooling

Fig. 6 Gaseous products from distillation of , I


Pittsburgh coal at low temperatures
Temperature,"C
stokers. As the typical analyses of Table VII in- 250 300 350 400 450
dicate, coke breeze usually has a higher ash
content than the rest of the coke.
Nearly all coke produced now is carbonized
at high temperatures in byproduct ovens of the
slot type; these have largely displaced the older
"beehive" ovens. The volatile products of the
process, consisting essentially of gas, ammo-
nia, tar and light oil, are recovered and sepa-
rated into their various fractions. Fig. 7 shows
diagrammatically the fuels taking part in and
resulting from the coke-making process, to-
gether with their respective typical analyses.
PETROLEUM COKE
Petroleum coke is a byproduct of a process in
which residual hydrocarbons are converted to
lighter, more highly valued distillates. Two
processes that produce these byproducts are in
use: delayed coking and fluid coking. Temperature, F O L-;S
DELAYED COKING
I I

In this process, the reduced crude oil is Fig. 7 Typical analyses of fuels involved in the
- rapidly and flows to isolated coking
heated manufacture of byproduct coke
COMBUSTION
Fossil Fuels

drums where it is coked by its own contained COAL TAR


heat. The process requires several drums to Coal tar is a byproduct in the carbonization
permit removal of the coke in one drum while of coal. The tar compounds are extremely com-
the others remain on stream. The residual plex and number in the hundreds. The solid
product which solidifies in these drums is material which is insoluble in benzene is con-
termed delayed coke. When first removed from tained as colloidal and coarse dispersed par-
the drum, it has the appearance of run-of-mine ticles and is known as "free carbon." The
coal, except that the coke is dull black. composition of the tar is dependent on the
The analysis of the coke varies with the crude temperature of carbonization and, to a lesser
from which it is made, ranging as follows: extent, on the nature of the coking coal. The fol-
Moisture 3-12% lowing is an example of a coal tar analysis.
Volatile matter 10-20% Carbon
Fixed carbon 71-88% Hydrogen
Ash 0.2-3.0% Sulfur
Sulfur 2.9-5.4% Oxygen
Btullb, dry 14,100-15,600 Nitrogen
(32.8 to 36.3 MJIkg) Moisture
FLUID COKING
Gravity, Baume
Two large vessels are used in fluid coking. Viscosity at 12ZF, SSF
One is known as a reactor vessel, and the other, Flash point
a burner vessel. In this process, fluid coke is Heating Value, Btullb, dry
both the catalyst and secondary product. The
seed coke is first heated in the burner vessel, Coal tar is burned in boilers only when it
either by adding air and burning a portion of cannot be sold for other purposes at a higher
the coke, or by burning an extraneous fuel such price than its equivalent fuel value. At ordinary
as oil. The heated seed coke then flows into the temperature, the viscosity of tar is very high
reactor vessel where it comes in contact with and must be heated for pumping. It burns like a
the preheated residual oil and the lighter frac- fuel oil and the same equipment can be used.
tions of the oil are flashed off. The coke which
is produced both deposits in uniform layers on COAL TAR PITCH
the seed coke and forms new seed coke. Thus Coal tar pitch is used to a small extent for
there is a constantly accumulating coke reser- generation of steam. It is the residue resulting
voir which is tapped off and is available as a from the distillation and refining of coal tar.
boiler feed. The pitch is solid at' ordinary atmospheric
The coke thus formed is a hard, dry, spherical temperature but becomes liquid at about 300F.
solid resembling black sand. It is composed of Generally, it is burned in pulverized form; i n a
over 90-percent carbon with varying per- few cases, it is melted and burned like oil or
centages of sulfur and ash, depending on the coal tar. When it is burned in pulverized form,
source of the crude oil. Typical analyses are it must be kept cool during pulverization and
Fixed carbon during delivery to the furnace. In some cases, it
is preferred to coal. Because of its very low ash
Volatile matter
content, the stack gas is practically free from-. . -
Ash 0.2-0.5% dust, and therefore there is no flue dust nui-
Sulfur 4.0-7.5% sance. When burned in liquid form, it must be
HHV, BtuAb, dry 14,100-14,600 kept very hot to prevent congealing. Table VIII
(32.8 to 34.0 MJIkg) shows analyses of coal tar pitch.
COMBUSTION
Fossil Fuels

Table VII. Analyses of Typical Cokes, as Fired


A at Zero
-%Proximate Analysis -%Ultimate Analysis - HHV, Excess Air,
Hz0 VM FC ASH H z 0 C H2 S 0 2 N2 BtulLb Lb1106 Btu

Kind
High-temperature
coke 5.0 1.3 83.7 10.0 5.0 82.0 0.5 0.8 0.7 10.0 12,200 798
Low-temperature
coke 2.8 15.1 72.1 10.0 2.8 74.5 3.2 1.8 6.1 10.0 12,600 763
Beehive coke 0.5 1.8 86.0 11.7 0.5 84.4 0.7 1.0 0.5 11.7 12,527 807
Byproductcoke 0.8 1.4 87.1 10.7 0.8 85.0 0.7 1.0 0.5'10.7 12,690 802
High-temperature
coke breeze 12.0 4.2 65.8 18.0 12.0 66.8 1.2 0.6 0.5 18.0 10,200 805

Gas Works Coke:


Horizontalretorts 0.8 1.488.0 9.8 0.8 86.80.60.70.2 9.8 12,820 808
Vertical retorts 1.3 2.5 86.3 9.9 1.3 85.4 1.0 0.7 0.3 9.9 12,770 809
Narrolv coke
ovens 0.7 2.0 85.3 12.0 0.7 84.6 0.5 0.7 0.3 12.0 12,550 802

WOOD
Table VIII. Coal Tar Pitch
Wood is a complex vegetable tissue com-
posed principally of cellulose, an organic Proximate Analysis
compound having a definite chemical compo- Moisture
sition. It would, therefore, seem reasonable to VM
assume that equal weights of different dry FC
wood species will have practically the same Ash
heat content. However, owing to the presence
of resins, gums and other substances in varying Ultimate Analysis
amounts, heat content is not uniform. Carbon 90.1%
Ultimate analyses showing the chemical Hydrogen 4.9%
composition of several different wood species Sulfur 0.9%
are given in Table IX. Because the substances Oxygen 0.6%
making up these fuels are complex organic Nitrogen 0.6%
chemical compounds, and complex thermo- Moisture 2.2%
dynamic changes take place when they are Ash 0.7%
burned in a furnace, it is not possible to make
use of formulas such as the Dulong type to pre-
dict their heating values. These analyses do not
indicate the amount of resins or similar sub- Most wood as commercially available for
stances present. But note that the heat content, steam generation is usually the waste product
on the dry basis, is greatest in the cases of resulting from some manufacturing process. Its
highly resinous woods as fir and pine. moisture content as received at the furnace will
The moisture content of freshly cut wood depend on (I)extraneous water from source or
varies from 30 to 50 percent. After air drying for storage or handling in the rain and (2) whether
approximately a year, this is reduced to be- it is "sap wood" or "heart wood," as well as on
tween 18 and 2 5 percent. the species and on the time of year it is cut.
COMBUSRON
Fo&I Fuek

The use of wet refuse wood for steam genera- Paper mills are in the third classification, as
tion falls into three broad classifications, each they must dispose of the wet wood refuse pro-
with its own specific combustion problems. As duced in their wood preparation plants. Their
both producer and user of byproduct fuel, principal problem is one of wet bark disposal.
sawmills are in the first category. Byproduct BARK
fuel for in-plant use is usually made up of saw- A common waste product in paper mills,
dust, shavings, bark and other wood waste in bark results from debarking tree trunks used in
varying percentages dependent on the nature making paper. The bark is peeled off the trunks
of the mill operation, the methods of stor- in long rope-like strips. This shape and size,
age and disposal of waste wood as well as combined with the high moisture content,
the arrangement of available fuel burning make the handling of the fuel difficult.
equipment. Bark as received from the barking drums con-
In the second classification are those plants tains 80 percent or more moisture, and in this
which purchase their wood fuel supply, usu- condition is of no value as a fuel. This fact is
ally composed of chips with little or no saw- best illustrated by Table X, the data for which
dust and shavings. have been prepared on the basis of a dry bark

Table IX. Typical Analyses of Dry Wood


A at Zero
%by Weight HHv, Excess Air,
C Hz S 0 2 N2 Ash BtdLb . Lb11o6Btu
Softwoodst
Cedar, white
Cypress
Fir, Douglas
Hemlock, western
Pine, pitch
white
yellow
Redwood
Hardwoods t
Ash, white
Beech
Birch, white
Elm
Hickory
Maple
Oak, black
red
white
Poplar

: _ -'Calculated from reported high heating value of kiln-dried wood assumed to contain 8-percent moisture.
tThe terms "hard" and "soft" wood, contrary to popular conception, have no reference to the actual hardness of the wood. According to the
Wood Hondbook, prepared by the Forest Products Laboratory of the U.S. Department of Agriculture, hardwoods belong to the botanical group
of trees that are broad-leaved whereas softwoods belong to the group that have needle or scalelike leaves, such as evergreens: cypress, larch,
and tamarack are exceptions.
COmuSnON
Fosdl Fuels

heating value of 8750 Btu per lb. Thus, at 80 The percentage of sawdust and shavings
percent moisture the heating value is only 1750 present may be quite high if the fuel is to be
Btu per lb (as received), and for every pound of burned at the sawmill. Table XI shows typical
dry substance there are 4 lbs of water which analyses of hog fuel. -
must be evaporated before any heat is available. A large paper producer conducted a series of
Under these conditions, the bark will not sup- tests to determine the moisture content, as well
port its own combustion, and it will be neces- as the unit weight, of waste wood produced
sary to supply heat from some other source if in its mill. The results of these tests, shown in
the wet material is to be disposed of in the fur- Table XII, illustrate the wide variation in
nace of any steam generating unit. weight that will exist between units of hog fuel
HOG FUEL because of moisture and different wood-spe-
In the manufacture of lumber, the amount of cies content.
material removed from the log to produce Hog fuel, as normally delivered to the fur-
sound lumber is approximately as follows: 18 nace, contains variable amounts of moisture,
percent in the form of slabs, edging and trim- averaging approximately 50 percent, most of
ming; 10 percent as bark; and 20 percent as which is in the cellular structure of the wood.
sawdust and shavings. While the total waste Storage of logs in the mill pond, water lubrica-
material will usually average 50 percent, dis- tion of saws, and exposure to rain because of
tribution of different types of waste may vary outdoor storage of the hog fuel all contribute to
widely from the approximations given above, the high total moisture content. In addition, the
owing to mill conditions as well as to the ulti- hog fuel, on dry-wood basis, contains approx-
mate finished product. imately 81 percent volatile matter and some-
The mills frequently use either the sawdust what less than 18 percent fixed carbon. The
or a mixture of sawdust and shavings for steam noncombustible residue, in the form of wood
production because these can be burned with- ash, is only a small fraction of 1percent.
out further processing. The remainder of the
so-called waste products requires further size Table XI. Analyses of Hog Fuels
reduction in a "hog" to facilitate feeding, rapid
combustion, transportation and storage. These Western Douglas Pine
Kind of Fuel Hemlock Fir Sawdust
newly sized products, together with varying
percentages of sawdust and shavings present, Hz0 AS Received 57.9 35.9 . ..
constitute hog fuel. Hz0 Air Dried 7.3 6.5 6.3

Proximate Analysis,
Table X. Relationship Dry Fuel
of Bark Moisture to Heat Content VM 74.2 82.0 79.4
FC 23.6 17.2 20.1
Lb water1
Ash 2.2 0.8 0.5
HHV, lb dry
96 Hz0 Btu/Lb Substance Ultimate Analysis,
Dry Fuel
Hydrogen 5.8 6.3 6.3
Carbon 50.4 52.3 51.8
Nitrogen 0.1 0.1 0.1
Oxygen 41.4 40.5 41.3
Sulfur 0.1 0 0
Ash 2.2 0.8 0.5
HHV, Btullb, dry 8620 9050 9130
COMBUSTION
Fossil Fuels

I
BAGASSE "bagasse," is sent through more roller mills for
Bagasse is a waste fuel produced when sugar further extraction. At the same time that the
is extracted from cane. The cane stalks grow in bagasse undergoes additional squeezing, it is
the field from 10 to 12 ft high. In Latin America, sprayed, or "imbibed," with plain water or di-
it is customary to cut the stalks again into luted juice to help dissolve more of the sugar.
smaller pieces, 2 to 3 ft long, before sending When hot water, generally taken from the
them through shredding machines or rotary boiler feed line, is used to soak the bagasse,
knives. The shredding, or cutting operation, is the operation is known as "maceration." On
called "disintegration" or "defibration," and leaving the last mill, a typical bagasse might
serves to open up the hard rind and thereby have 40 percent fiber, 2.5 percent sugar, 55
facilitate the squeezing out of juice in the cane. percent moisture and 2.5 percent ash. The
As in the case of wood, sugar cane consists of relatively high ash content in many bagasse
cellulose fiber which makes up the tissue en- samples is because of trash and dirt picked
closing such sugars as sucrose (C12E122011) and up in harvesting.
glucose (C&1?06).Ilrater and small quantities Table XI11 shows typical ultimate analyses of
of mineral ash are also present. On a moisture- bagasse from different countries, on a dry basis.
and ash-free basis, the cane contains from 10 to (As-received bagasse contains 40 to 60 percent
17 percent cellulose fiber and from 83 to 90 moisture by weight.) Carbon content is slightly
percent sugar. lower; oxygen a little higher than in wood, pos-
To separate the juice from the fiber, the disin- sibly due to the extraction of sugar.
tegrated. cane is crushed between rollers. After The size of bagasse pieces depends on the
this primary pressing, the issuing fiber, or machinery employed to disintegrate the cane.
A simple crusher will produce coarser bagasse
than is obtained by adding a shredder ahead of
Table Xll. Unit Weight the crusher. Aside from the special case where
and Moisture Content of Wood grindstones defibrate the cane, the finest size is
(as-received basis) obtained with rotating knives replacing both
shredder and crusher.
Weight-
Type of Wood % H20 'b'cUft FOOD-PROCESSING WASTES
Drum Barker (pressed) 63.4 19.3
The production of food from some fruits
Regular paper mill
waste wood 56.9 21.5
and vegetables results in burnable solids that
Hemlock 53.7 19.4
are available for energy production. Among
Douglas fir 44.4 17.4
these are nut hulls, with a fuel value of about
7700 Btullb (18 MJIkg) as fired; rice hulls, with

Table Xlll. Typical Analyses of Bagasse, Dry


A at Zero
% b y Weight HHV, Excess Air,
C Hz 0 2 NZ Ash BtuILb Lb1106 Btu

Cuba 43.15 6.00 47.95 ... 2.90 7985 629


Hawaii 46.20 6.40 45.90 ... 1.50 8160 68 7
Java 46.03 6.56 45.55 - 0.18 1.68 8681 65 1
Mexico 47.30 6.08 45.30 ... 1.32 8740 646
Peru 49.00 5.89 43.36 ... 1.75 8380 700
Puerto Rico 44.21 6.31 47.72 0.41 1.35 8386 62 7
COMBUSTION
Fossil Fuels

5200 to 6500 Btullb (12 to 15 MJkg); corn cobs, textiles, rubber, plastics, and leather; 7 to 24
with 7500 to 8300 Btullb (17 to 19 MJkg); and percent food waste; 1 to 7 percent wood; 5 to
coffee grounds, with between 4900 and 6500 1 2 percent glass and ceramics; 7 to 11 percent
Btullb (11to 15 MJkg). metal; and 1 to 33 percent grass, leaves and
dirt. Proximate and ultimate analyses of resi-
MUNICIPAL AND INDUSTRIAL REFUSE
dential solid waste with magnetic metals re-
Solid residential, commercial, and industrial moved are given in Table XIV. Further separa-
waste, or "municipal solid waste" (MSW), is a tion of heavy-density materials (nonferrous
fuel having some of the characteristics of wood, metals, stone, masonry, and glass) can in-
bagasse, and other "young" fossil fuels. It de- crease refuse heating value to between 7,000
rives most of its heating value from its cellu- and 8,000 Btu per pound (16 to 19 MJkg).
losic content. When shredded and separated
into light and heavy fractions, a fuel can be pro- LlQU1D FUELS
duced having thermal energy equal to lignitic
coals, with high ash, but low sulfur, content. Fuel oil used for "earn generation Purposes
This beneficiated product is known as ''refuse- may be defined as petroleum or any of its liq-
derived fuel" (RDF). uid residues remaining after the more volatile
The technical aspects of recovery of the have been removed.
enesy from this resource, as opposed to its Petroleum is sometimes burned in its crude
simple disposal, are well documented. (See form. In this condition, most of it will contain
references 15 through 25.) lighter gasoline fractions which lower the
Refuse is a highly time-, geography-, and flash point and present a fire hazard. Through
weather-dependent fuel. Its character varies limited fractional distillation, or topping, the
widely with the economic status of the people lighter gasoline can be removed and a safe fuel
generating it. It is extremely heterogeneous but, oil can be produced. If the refining process is
in general, has increased in paper and plastic carried through extended fractional distilla-
content and, therefore, heating value, through
the years. The garbage fraction has decreased, Table XIV. Analyses of Typical
as has the quantity of ash from coal-fired Residential Solid Waste
household furnaces. In suburban areas, it will With Magnetic Metals Removed
have greater or lesser content of leaves and
grass as a function of the day in the week, and YO
Proximate Analysis As Received
more or less moisture content as a function of
the weather. Urban refuse is characterized by H?O 19.7-31.3
large quantities of paper bags, cardboard, and Ash 9.4-26.8
similar dry combustible material. VIM 36.8-56.2
Similarly, industrial refuse has higher ther- 0.6-14.6
ma1 value today than earlier, because of the HHV*Btu'lb 3100-6500 (7 to 15 MJ/kg)
increased use of plastics and other synthetic ultimateAnalysis
materials, many of which have high heating H.,o 19.7-31.3
values with little or no moisture or ash. Typi- 9.4-26.8
cal high-calorific-value components of indus- Carbon 23.4-42.8
trial waste are rubber, wood, sawdust, fats. Hydrogen 3.4-6.3
oils, waxes, solvents, paints, and other organic Nitrogen 0.2-0.4
materials, many of them with heating values of Chlorine 0.1-0.9
10,000 to 19,000 Btu per lb (23 to 44 MJIkg). Sulfur 0.1-0.4
Raw municipal refuse will be typically from Oxygen 15.4-31.9
one-third to one-half paper; 2 to 1 2 percent
-

2-27 !id!
COMBUSTION
Fossil Fuels

Table XV. Detailed Requirements for Fuel OilsA


Water
and Carbon
Flash Pour Sedi- Residue DistillationTemp.
' Point, Point, ment on10 % Ash CeF)
"C "C Vol Bottoms Weight 10%
eF) ("F) % % % Point 90%Point
Grade of Fuel Oil Min Max Max Max Max Max Min Max

No. 1 38 or -18' 0.05 0.15 ... 215 ... 288


Distillate oil intended for legal (0) (420) (550)
vaporizing pot-type burners (100)
and other burners requiring
this grade
No. 2 380r -6' 0.05 0.35 ... ... 282' 338
Distillate oil for general legal (20) (540) (640)
purpose heating for use in (100)
burners not requiring No. 1
No. 4 55or -6' 0.50 ... 0.10 ... ... ..
Preheating not usually re- legal (20)
quired for handling or (130)
burning
No. 5 (Light) 550r ... 1.00 ... 0.10 ... ... ...
Preheating may be required legal
depending on climate and (1 30) . -
equipment
No. 5 (Heavy) 550r ... 1.00 ... 0.10 ... ... ...
Preheating may be required legal
for burning and, in cold (130)
climates, may be required
for handling
No. 6 60 G 2.0OE ... ... ... ... ...
Preheating required for (140)
burning and handling

" It
is the intent of these classifications that failure to meet any requirement of a given grade does not automatically place an oil in the next lower
grade unless in fact it meets all requirements of the lower grade.
"In countries outside the United States other sulfur limits may apply.
Lower or higher pour points may be specified whenever required by conditions of storage or use. When pour point less than -18C (0F)is
specified. the minimum viscosity for Grade No. 2 shall be 1.8 cSt (32.0 SUS) and the minimum 90 90point shall be waived.
"Viscosity values in parentheses are for information only and not necessarily limiting.
The amount of water by distillation plus the sediment by extraction shall not exceed 2.00 %.The amount of sediment by extraction shall not
exceed 0.50 1.A deduction in quantity shall be made for all water and sediment in excess of 1.0 OO.
Where low sulfur fuel is required, fuel oil falling in the viscosity range of a lower numbered grade down to and including No. 4 may be
supplied by agreement between purchaser and supplier. The viscosity range of the initial shipment shall be identified and advance notice
shall be required when changing from one viscosity range to another. This notice shall be in sufficient time to permit the user to make the
necessary adjustments. -- _ -
Where low sulfur fuel oil is required. Grade 6 fueloil will be classified as low pow +15"C(60F)max or high pour (no max.) Low pour fuel oil
should be used unless all tanks and lines are heated.
Excerpted from ASTM Standards D 396, Specifications for Fuel Oils.
COMBUSTION
Fossil Fuels

Table XV. Detailed Requirementsfor Fuel OilsA-Continued

Specific Copper
-Saybolt Viscosity, s D- -Kinematic Viscosity, cStD- Gravity Strip Sul-
Universal at 38C Fur01 at 50C 60/60F (deg Cor- fur,
(lOOF) (122F) At 38C (100F) At 50C (12ZF) API) rosion %
-

~Min Max Xlin Max Min Max Min Max Max Max Max

... ... ... ... 1.4 2.2 ... ... 0.8499 No. 3 0.5
(35 min) or
Y legal

(32.6) (37.9) ... ... 2.0C 3.6 , .. ... 0.8762 No. 3 0.5B
(30 min) or
legal
--

(45) (125) ... ... 5.8 26.4F ... .., ... ... legal

(>125) (300) ... ... >26.4 65F ... ... ... ... legal

(>300) (900) (23) (40) >65 194' (42) (81) . . . . ... legal

(>900) (9000) (>45) (300) >92 638' 50C (122F) ... ... legal

tion and cracking, such fuels as gasoline, dardization, specifications have been estab-
kerosene, gas oil, light fuel oils, lubricating lished, Table XV, for several grades of fuel oil.
oil, heavy fuel oil, residual tar, pitch and pe- Sometimes designated as light and medium
troleum coke are produced. domestic fuel oils, Grades No. 1 and No. 2 are
specified mainly by the temperature of the dis-
PROPERTIES OF FUEL OIL tillation range. Grade No. 6, designated as
The term fuel oil may conveniently cover a heavy industrial fuel oil and sometimes known
wide range of petroleum products. It may be as Bunker C oil, is specified mainly by viscos-
applied to crude petroleum, to a light petro- ity. The specific gravities of Grades 4, 5, and 6
leum fraction similar to kerosene or gas oil, or are not specified because they will vary with
to a heavy residue left after distilling off the the source of the crude petroleum and the ex-
fixed gases, the gasoline, and more or less of tent of the refinery operation in cracking and
the kerosene and gas oil. To provide stan- distilling.
COMEUSTION
Fordl Fuels
.-
Despite the multiplicity of chemical com-
pounds found in fuel oils, the typical analyses Btullb (high)= 17,660+ (69 x API gravity)
(2)
of these fuels, as shown in Table XVI, are fairly
constant.
For a cracked distillate,
SPECIFIC GRAVITY
Btullb (High)= 17,780+ (54 x API gravity)
This is the ratio between the weight of any (3)
volume of oil at 60F and the weight of an equal
volume of water at 60F. The common designa-
VISCOSITY
tion is Sp Gr 60160F and is expressed as a dec-
imal carried to four places. This is defined as the measure of the resis-
Gravity determinations are readily made by tance to flow. The greater this resistance, the
immersing a hydrometer into the sample and longer it takes a given volume of oil to flow
reading the scale at the point to which the in- through a fixed orifice. The Saybolt Universal
strument sinks in the oil. The specific gravity is viscosity is expressed in seconds of time that it
either read direct or the gravity is measured in takes to ruu 60 cc through a standard size
degrees API. orifice at any desired temperature. Viscosity is
Formerly, the gravity of oil was measured in commonly measured at 10o0F, 150F and
degrees Baume but confusion developed over 210F. The oil is held at constant temperature
the use of the two so-called Baume scales for within + 0.25"F during the test period.
light liquids. To overcome this, the American Fuel oil is very viscous, and it takes a long
Petroleum Institute, the U.S. Bureau of Mines, time to make a determination with the Saybolt
and the U.S. Bureau of Standards agreed to rec- Universal viscosimeter. For this reason, the
ommend, in 1921, that only one scale be used in viscosity of fuel oil is usually measured with a
the petroleum industry, and that it be known as Saybolt Furol viscosimeter, which is the same
the API scale. The relation between specific as the Saybolt Universal except that the orifice
gravity and "API is expressed by is larger. Viscosity of 62 seconds Saybolt Furol
is 600 seconds Saybolt Universal.26,
Another measure of viscosity sometimes
used is the so-called Engler degree or specific
viscosity. The Engler degree is the quotient of
time of outflow of 200 cc of oil, divided by the
time of flow of 200 cc of water; that is, the vis-
HEATING VALUE
cosity of oil is compared with that of water.
This may be expressed in either Btu per gal- Viscosity of fuel oil decreases as the tempera-
lon at 60F or Btu per pound. The heating value ture rises and becomes nearly constant above
per gallon increases with specific gravity, be- about 250F. Therefore, when fuel oil is heated
cause there is more weight per gallon, and to reduce the viscosity for good atomization,
ranges from about 135,000 to 150,000 Btu. The there is little gain in heating the oil beyond
heating value per pound of fuel oil varies in- 250F. Moreover, since burners operate most
versely with the specific gravity, because efficiently with oil of constantviscosity, it is de-
lighter oil contains more hydrogen; it ranges sirable to operate in the viscosity range where
from 18,300 to 19,500 Btu. temperature variations have the least effect.
The exact determination of the heat content This is illustrated in Fig. 8 for No. 6 Bunker C
-
of fuel oil is made in a bomb calorimeter. How- oil. Fig. 9 shows the viscosity-temperature rela-
ever, there is an approximate relationship be- tionships for the several grades of fuel. Table
tween specific gravity and the high heating XVI shows typical analyses.
value. For an uncracked distilate or residue, The relationship among specific gravity, deg
I COMBUSTION
Fossil Fueb

API, density in lb per gal, Btu per lb, and Btu which they are purchased commercially, is
per gal for petroleum products is graphically considerably greater.
shown in Fig. 10. Also included are the ranges in FLASH AND FIRE POINT
deg API for gasoline, kerosene, gas oil and fuel Flash point of fuel.oil is the lowest tempera-
oils. Knowing the value of any one of these ture at which sufficient vapor is given off to
characteristics, it is possible to determine all
the others quickly. For example, assume the 260 -
deg API to be 7 5 , then the intersection of this
240
value with the deg API curves is at a point A, LL
through which a horizontal line is drawn to o 220 Least Effect of Temp.
intersect the remaining curves. Then, by refer-
ring to their respective scales, it is possible to
read the specific gravity B as 0.685, the density
C as 5.675 lb per gal, and the higher heating
value at D as 20,550 Btu per lb, or at E as t- 140-
116,800 Btu per gal. Of particular interest is the
I I I I
fact that, although the high specific gravity fuel 0 200 400 600 800 1000
oils (15OAPI) have a lower heating value per Viscosity, SSU
pound than the lower specific gravity gasoline
(60API),the total heat per gallon, the basis on Fig. 8 Viscosity versus temperature, No. 6 fuel oil

Table XVI. Typical Analyses and Properties of Fuel Oils*


No. 1 No. 2 No. 4 No. 5 No. 6
Grade Fuel Oil Fuel Oil Fuel Oil Fuel Oil Fuel Oil
Distillate Very Light Light
Type (Kerosene) Distillate Residual Residual Residual
Color Light Amber Black Black Black
-

API gravity, 60F 40 32 21 17 12


Specific gravity. 60,'60F 0.8251 0.8654 0.9279 0.9529 0.9861
Lb1U.S. gallon, 60F 6.870 7.206 7.727 7.935 8.212
i'iscos., Centistokes. 100F 1.6 2.68 15.0 50.0 360.0
Viscos., Saybolt Univ., 100F 31 35 77 232 ...
Viscos., Saybolt Furol, 122F ... ... ... ... 170 .
Pour point, OF Below zero Below zero 10 30 65
Temp. for pumping, OF Atmospheric Atmospheric 15 min. 35min. 100
Temp. for atomizing. "F Atmospheric Atmospheric 25 min. 130 200
Carbon residue. SC Trace Trace 2.5 5.0 12.0
Sulfur, % 0.1 0.4-0.7 0.4-1.5 2.0 max. 2.8 max.
Oxygen and nitrogen, % 0.2 0.2 0.48 0.70 0.92
Hydrogen, OO/ 13.2 12.7 11.9 11.7 10.5
Carbon, % 86.5 86.4 86.10 85.55 85.70
Sediment and water, % Trace Trace 0.5 max. 1.0 max. 2.0 max.
Ash, % Trace Trace 0.02 0.05 0.08
Btu gallon 137,000 141,000 146,000 148,000 150,000
Courtesy Exxon Corporat~on
COMBUSTION
Fossil Fuels

form a momentary flash when flame is brought OIL REFINERY REFUSE FUEL
near the surface. The values vary with the ap- Byproducts from refinery operation consist
paratus and procedure; both must be specified. of a wide variety of refuse fuels. There are
Flash point specifications for the several solids, such as asphaltic pitch and petroleum
grades of fuel oil are.given in Table XV. Fire coke. The liquids, termed sludge, often have a
point is the lowest temperature at which the oil high specific gravity and contain variable
gives off enough vapor to burn continuously. amounts of solid matter in suspension.
SULFUR AND ASH The characteristics of the sludge are gov-
Sulfur is a very undesirable element in fuel erned by those of the crude oil used and the
oil because its products of combustion are manner in which it is processed. Many of the
acidic and cause corrosion in economizers, air suspended solids may be carbonaceous, in
heaters and gas ducts. Because of the high hy- the form of small particles of oil coke.
drogen content in fuel oil, and the resulting Perhaps the most troublesome of sludges, be-
high water vapor content in the products of cause of its frequent and widely varying
combustion, a given amount of sulfur in fuel oil characteristics, is acid sludge. Its gravity may
has the potential of doing more damage than rangebetween 5 and 14OAP1,and its viscosity is
the same amount of sulfur in coal. indeterminate. It contains changing quantities
Fuel oil contains all the solid impurities orig- of weak sulfuric acid that may run as high as 40
inally present in the crude oil. If these solids percent, and this, together with the suspended
contain a large proportion of salt, they are very carbonaceous material and flux, which must be
fusible and can cause considerable trouble. added to make the sludge flow, causes heat

ASTM Std Vlscoslty - Fuel 011 Cornpos~tion


Temperaturechartsfor Liqu~d Kerosene Stra~ght
Petroleum Products (D 341 )
SSU = Saybolt Umversal V~scos~ty Fuel 011s No. 4 Stralght and Up to 15% Residuals
d l {NO 5 Heavy D~stlllatesPlus Up to 40% Res~duals
No 6 Up to 100%Res~duals

-20 0 20 40 60 80 100 140 200 240 300


Temperature,"F
Fig. 9 Viscosity ranges for fuel oils
COMBUSTION
F o s s U F ~.

values to vary between 8,000 and 17,500 Btullb. Determinations can be made by selective ab-
Alkaline sludges, such as soda taF and neu- sorption in chemical solutions, by separation
tralized sludge, are less troublesome to fire of components through distillation, by infrared
since they are less .vaFiable in character than or mass spectrometry, or by means of gas chro-
acid sludge. matography. Typical analyses of various gases
-- are given under their specific headings.

GASEOUS FUELS HEATING VALUE


Gaseous fuels, when available, are ideal for The heating value refers to the quantity of
steam generation because of the ease of control, heat released during combustion of a unit
the presence of little or no solid residue, and amount of fuel gas. Determinations are made
the low excess-air requirement, which contrib- with a continuous flow (constant pressure) gas
utes to high efficiency. calorimeter. The heating value as determined
Properties of fuel gas considered to be of in calorimeters is termed high heating value
prime importance are composition, heating and is the quantity of heat evolved when the
, value, and specific gravity. products of combustion are cooled to 60F and
ANALYSIS the water vapor produced is completely con-
densed to a liquid at that temperature. The low
The analysis of fuel gas is expressed in terms heating value differs from the high heating
of volume percentages of the component gases. value by the latent heat of evaporation of water
r

Specific Gravity at 60' F


Referred to Water at 60F Btu/Gal. (In Thousands)
1.0 0.9 0.8 0.7 0.6 145 135 125 115

100 80 60 40 20 20.5 20.0 19.5 19.0 18.5


OAPl Btu/Lb (In Thousands)

Fig. 10 Chart showing the relationships of important characteristicsof liquid fuels


COMBUSIION
F o d l Fuels

formed in the combustion process, as described In Table XVII are shown the principal compo-
on Page 2-12. nents, together with their properties at 60F
The heating value of manufactured gas is ex- and 30 in. Hg, moisture-free. When present in
pressed as Btu per cu ft when measured at 60F different proportions, these make up various
and 30 in. Hg, saturated with water vapor. The fuel gases.
values for natural gas, however, are commonly ANSIIASTM Standards D 3588 gives a
reported at a pressure of 14.7 psia (pounds per method for calculating calorific value and spe-
' square inch absolute) or 30 in. Hg, at a tempera- cific gravity of gaseous fuels and includes a
ture of 80F, and generally on a dry besis. method for determining the repeatability and
The heating value of gaseous fuels varies reproducibility of the calculated values.
considerably, depending on the constituents
present. When not obtainable by test, H,can be SPECIFIC GRAVITY
calculated by summing up the heat evolved by Various methods for determining the spe-.
the individual combustible fractions of the gas. cific gravity of a fuel gas are available but three

Table XVII. Combustion Constants of Dry Gases at 60F and 30 In. Hg


01Reqd.1 COI Formedl Hz0 Formedl
Cu Ft Cu Ft Cu Ft Density
Chemical of Dry Gas, of Dry Gas, of Dry Gas, of Dry Gas, -HHV of Dry Gas -
Formula CuFt Cu Ft Cu Ft LblCu Ft BtulCu Ft* BtuILb

Gas
Oxygen 02 ... ... ... 0.08461 ... ...
Nitrogen (atmospheric) N2 ... ... ... 0.07439 ... ...
Air ... ... ... ... 0.07655 ... ...
Carbon dioxide co2 ... ... ... 0.1170 ... ...
Water vapor H20 ... ... ... 0.04758 ... ...
Hydrogen HZ 0.5 ... 1.0 0.005327 325 60,991
Hydrogen sulfide H2S 1.5 1.0** 1.0 0.09109 647 7,100
Carbon monoxide CO 0.5 1.0 ... 0.07404 321 4,323

Saturated Hydrocarbons
Mathane CH, 2.0 1.0 2.0 0.04246 1014 23,896
Ethane C2Hs 3.5 2.0 3.0 0.08029 1789 22,282
Propane C3Hs 5.0 3.0 4.0 0.1196 2573 21,523
Butane C4H10 6.5 4.0 5.0 0.1582 3392 21,441
Pentane C5HI2 8.0 5.0 6.0 0.1904 4200 22,058

Unsaturated Hydrocarbons
or Illurninants
Ethylene C2H4 3.0 2.0 2.0 0.07421 1614 21,647
Propylene C3H6 4.5 3.0 3.0 0.1110 2383 21,464
Butylene C4Hs 6.0 4.0 4.0 0.1480 3190 21,552
Pentylene CjHlo 7.5 5.0 5.0 0.1852 4000 21,600
Acetylene C2H2 2.5 2.0 1.0 0.06971 1488 21,344
Benzene C6H6 7.5 6.0 3.0 0.2060 3930 19,068 . -
Toluene C7H8 9.0 7.0 4.0 0.2431 4750 19,537
If gas is saturated with moisture at 60F and 30.0 in.i- g, reduce by 1.74%.
"S0,rather thanCO,
COMBUSTION
Fossil Fuels

methods have been adopted as ASTM Stan- in turn, lies over salt water. The relative density
dards D 1070, Test for Gravity, Specific, (Rela- of these substances accounts for their segrega-
tive Density) of Gaseous Fuels. tion, natural gas being lightest, water heaviest,
DIRECT WEIGHING METHOD and oil in between. But not all natural gas is as-
This involves the determination of the weight sociated with oil. At times it is found by itself,
differential between two equal volumes of gas or directly in contact with salt water, hermeti-
and air, both at identical conditions of tempera- cally sealed by the rock.
ture and pressure. Although whenever possible natural gas is
PRESSURE BALANCE METHOD
delivered at the required destination under
well pressure, it is also frequently transported
In this method, a flask containing the gas is over long distances by means of pipelines and
counterbalanced on a beam enclosed in a con- compressors. Thus, the furnace which uses this
tainer. The beam is brought to balance by ad- gas may be close to the well or at the end of a
justing the air pressure within the container pipeline and the conditions in the pipelines
which varies the buoyancy of the flask. The may change the composition of natural gas
procedure is repeated with air in the flask and going to the furnace. For instance, aside from
the specific gravity determined from the ratio the effect of compression, which liquefies the
of the required absolute pressures. heavy members of the hydrocarbon family,
DISPLACEMENT BALANCE METHOD water and oil are sometimes sprayed into the
The instrument consists of a balance beam on gas to keep it "moist." For this reason, any
each end of which two bells are suspended in a natural-gas analysis, as fired, should be taken
sealing liquid. One bell, containing air, is open at the point of use rather than at the well.
to the atmosphere through holes in its top; the
COMPOSITION OF NATURAL GAS
other bell, containing the gas, is open to the at-
mosphere through a 59-in. gas column connec- The characteristics of natural gas, as it comes
ted to the space under the bell. An unbalanced out of the earth's surface, depend to some ex-
force is produced which is equal to the pressure tent on its underground conditions. Generally,
differential above and within the gas-filled it is odorless and colorless. It burns with a blue
bulb. The magnitude of this force is an indica- flame and is highly explosive when mixed with
tion of the specific gravity. air in the correct proportions. The range in its
NATURAL GAS
chemical composition is indicated by Table
XVIII, where it is seen that methane, CH4,and
Natural gas is perhaps the closest approach ethane, C2H6,are its principal combustible
to an ideal fuel because it is practically free components. This is because in natural-gas
from noncombustible gas or solid residue. It is analyses it is customary to report the heavier
found compressed in porous rock and shale hydrocarbons in terms of CH4 and C2H6,or if
formations, or cavities, which are sealed be- this grouping is not satisfactory, in terms of
tween strata of close-textured rocks under the Cfi6and C P 8(propane).
earth's surface. When these so-called gas-bear- When sulfur is present in the oil deposit, the
ing sands of a pool are tapped by drilling wells, analysis of natural gas associated with this oil
the gas is found to be under rock pressure, often includes hydrogen sulfide. This hydro-
which may be as high as 2000 psig (pounds per gen sulfide is removed in most instances before
square inch gage). As gas is withdrawn, this distributing the gas because it is a potential
pressure gradually decreases until the field source of pipeline corrosion.
must be abandoned. In addition to its combustible constituents,
Natural-gas fields frequently exist in the natural gas may contain considerable amounts
neighborhood of oil deposits. Usually natural of carbon dioxide, C02,0rnitrogen, N2.It some-
gas occupies the space above the oil and the oil, times happens that gas is drawn from wells

nra
-35 E'2E
COMBUSTION
F o d l Fuels
--
under suction and that, because of this, air will have been removed. Analysis of sour and sweet
leak into the lines. The analysis of natural gas gases are shown in Table XIX.
will then show the presence of oxygen. HEATING VALUE
DRY AND WET NATURAL GAS The higher or gross heating value of natural
If natural gas has been in contact with oil, it gas is usually about 1000 Btu per cu ft, and it
will be impregnated with varying amounts of can be computed by adding together the heat
heavy hydrocarbon vapors, such as pentane, contributed by volumetric percentages of the
C,Hl2, and hexane, C6HI4,which are liquid at various component gases. This method will
ordinary pressure and temperature. Known as usually result in a lower value per cubic foot
"wet" natural gas, it is usually economical to than that obtained by calorimetric determina-
dry it by liquefying the heavy vapors, which tions, because the unsaturated hydrocarbons
are then collected and called casing-head are frequently grouped and reported with CgH6.
gasoline. In a complete chemical analysis of For the same reason, the corresponding den-
natural gas, a certain fraction of a heavy hy- sity, under standard conditions of 60F and 30
drocarbon is sometimes preceded by the letter in. Hg, will also be lower. The calculated Btu
"n," such as "n-butane," which means "nor- per pound, however, will be close to its actual
mal" butane, and the remainder uses the prefix value, because of the compensating effect of the
"iso," meaning "equal," as, for example, "iso- lower calculated density.
butane." The chemical formula is the same in
both cases as the prefix merely denotes a differ- LIQUEFIED PETROLEUM GAS (LPG)
ent arrangement of the atoms in the hydrocar- The term liquefied petroleum gas, LPG, is
bon molkcuie. However, the physical and applied to certain hydrocarbons which are
chemical properties of these so-called "iso- gaseous under normal atmospheric conditions,
mers" are not usually the same. but can be liquefied under moderate pressure at
"Dry" natural gas comes from wells away normal temperatures. LPG is derived from nat-
from oil deposits and is, therefore, compara- ural gas and from various petroleum-refinery
tively devoid of heavy hydrocarbons. sources such as crude distillation and cracking.
Natural gases are also classified as either The hydrocarbons in LPG are mainly of the
"sweet" or "sour." The sour gas is one which paraffinic (saturated) series, principally pro-
contains some mercaptans and a high percent- pane, isobutane and normal butane.
age of hydrogen sulfide while the sweet gas is The California Natural Gasoline Association
one in which these objectionable constituents has divided LPG mixtures into six standard

Table XVIII. Characteristics of Typical Natural Gases at 60" F and 30 In. Hg, Dry
A at Zero
%by Volume Density, -HHV - Excess Air,
C0z N2 HIS CHI C2H6 C~HB C ~ H I O CSHIZ LblCuFt BtdCuFta* BtdLb Lb1106Btu

*All hydrocarbons heavier than CsHI2areassumed to be CsHt2


'*If gas is saturated with moisture at 60F and 30.0 in. Hg, reduce by 1.74%.
gases from various sources in the plant are the raw coal and the length of time taken in the
blended together before being burned. roasting operation influence the exact compo-
Because it is specifically manufactured for sition of coke-oven gas.
commercial purposes, oil gas deserves special As the coke-oven gas comes from the oven at
mention, as the heat ,value standard for the high temperatures, it frequently contains vari-
locality where it is sold governs its final ous impurities in the form of tarry particles,
composition.
'
dust, benzol, and hydrogen sulfide. With rare
Oil gas is produced by spraying oil into a re- exceptions, however, it is always washed and
tort heated to about 1300F, causing thermal cooled before being sent to a storage tank and
decomposition. Cracking of the oil is then distributed for burning.
completed by passing the gas through a second Because of a breaking down of the heavy
retort, which converts the unstable hydrocar- hydrocarbons, carbonization at high tempera-
bons of low molecular weight into permanently tures generally results in calorific values vary-
gaseous hydrocarbons. In this manner about 85 ing from 400 to 600 Btu per cu ft. On the other
percent of the oil is recovered as gas. hand, low-temperature carbonization gives a
The wide range of characteristic analyses of smaller yield of coke-oven gas, but a higher
&ese gases is given in Table XXI. The last two heating value, ranging from 600 to 1000 Btu per
analyses are of oil gases; the others represent cu ft. Table XXII indicates a spread between
refinery gases. 477 and 829 Btu per cu ft in the high heating
COKE-OVEN GAS value of the analyses selected. The heating
As its name implies, coke-oven gas is a by- value of a coke-oven gas, when not given, may
product of the destructive distillation of bitu- be accurately determined by a summation of
minous coal in the manufacture of coke. The the heats evolved by the individual combusti-
raw coal is placed in ovens, which are exter- ble constituents of the gas.
nally heated until practically all the volatile PRODUCER GAS
matter is driven out. The coke-oven gas is made Producer gas is formed through the partial
up chiefly of hydrogen, methane, ethylene, and combustion of coal or coke by passing less than
carbon monoxide, with small percentages of stoichiometric air through a hot fuel bed. Be-
carbon dioxide, nitrogen, oxygen, and heavy cause of the use of air, the nitrogen content of
hydrocarbons or illuminants. The character of the gas is high, generally 50 to 55 percent by
- - --

Table XX. CNGA Standard Grade for LPG Mixture


Range of
CNGA Max Vapor Allowable Sp Gr
Standard Pressure 60160F
Grade Psig at 100F Hz0 = 1.0 Composition

Predominantly butanes

Butane-propane mixture,
largely butanes
Butane-propane mixture,
proportions approximately equal
.-Butane-propane mixture,
propane exceeds butane
Propane-butane mixture,
largely propane
Predominantly propane
COMBUSTION
Fossil Fuels

volume, and the heating value is rather low, perature and then "blasted" with steam. The
ranging from about 140 to 180 Btu per cu ft. The steam reacts with the hot carbon endothermally
ranges of component gases in this fuel are as follows:
CO 20-30s
H2 8-20%
CH 1 0.5-3 %
CO, 3-9 %
7
N :! 50-56Oh The gas is sometimes called "blue gas" be-
0 2 0.1-0.3% cause of the characteristic blue flame with
which it burns, the color resulting from the
WATER GAS (BLUE GAS) high percentage of hydrogen and carbon mo-
Water gas is made in a cyclic process, in noxide. A typical analysis shows this gas con-
which coke is "blown" with air to raise its tem- sists of the following components:

Table XXI. Characteristics of Typical Refinery and Oil Gases


at 60F and 30 In. Hg, Dry
% by volume

Density
LbiCu ~t 0.08676 0.08377 0.04845 0.13760 0.08102 0.09232 0.03631 0.02756

HHV
Btu/Cu Ft** 1898 1858 1136 2988 1696 1844 519 586
BtulLb 21,880 22,170 23,460 21,720 20,930 19,970 14,300 21,270

A at Zero
Excess Air
Lb1106 Btu 722 723 723 717 725 715 648 657

COz at Zero
Excess Air % 13.3 13.4 12.1 13.9 13.4 13.6 12.2 10.6

'Includes both iso-C,Hloand n-C,Hl,


tIncludes all saturated hydrocarbons heavier than C s H l , also both iso-C,H,?and n-C,Hlr.
*Includes all illurninants.
'*If gas is saturated with moisture at 60F a n d 30.0 in. Hg. reduce by 1.74%.
COMBUSTION
Fossil Fuek

Table XXII. Characteristics of Typical Coke-Oven Gases


at 60Fand 30 In. Hg, Dry
A at Zero
-%by Volume Density, -HHV - Excess Air,
do Hz CHI CzH4 C6H6 LblCu Ft BtulCu Ft* Btdb Lbl106Btu

31.6 2.7 1.0 0.0298 596 20,010


28.5 2.9 ... 0.0263 539 20,490
33.9 5.2 ... 0.0316 603 19,070
37.14 4.76 0.88 0.0359 663 18,500
50.0 13.0 ... 0.0393 829 21,100
28.15 ... . .. 0.0291 477 16,390
--- -

*If gas is saturated with moisture at 60F and 30.0 in. Hg.reduce by 1.74%.

CO, 5.6% cracking reaction the catalyst becomes coated


CO 37.0% with a coke deposit. To maintain catalyst activ-
ity, this material must be removed.
H2 47.3%
The spent catalyst is continuously removed
CH4 1.3% from the reactor and transported to a regener-
N2 8.8% ator vessel. In this unit compressed air fluidizes
HHV, Btulcu ft 287 the catalyst and burns off the carbon. To keep
CARBURETTED WATER GAS compression costs to a minimum, as well as to
keep the temperature inside the regenerator
Water gas enriched with fuel oil to raise its
restricted to a level which will not destroy
heating value is called carburetted water gas.
catalyst activity, the smallest amount of air is
The process involves the injection of oil into
used that will effectively clean the catalyst.
the carburetting chamber during the steam
blow; the water gas, passing into the car-
buretor, picks up the oil vapor which is then Table XXIII. Analyses
cracked into gases. The composition and heat- of Carburetted Water Gas
ing value of the carburetted water gas varies
with the amount of oil used, the latter property From From
Coke Anthracite
varying between 400 and 700 Btu per cu ft. Component Yo %
Table XXIII shows typical analyses of this gas.
Carbon dioxide and hydrogen
REGENERATOR WASTE GAS
sulfide 0.9
'The lighter hydrocarbons or gas oils pro- Nitrogen 6.8
duced i n the petroleum coking processes are Hydrogen 37.4
further refined in catalytic-cracking units. Carbon monoxide 35.0
These units fall into two general types: fluid Methane 8.1
units, i n which fine powdered catalyst flows Ethane 1.30
through the equipment with flow characteris- Ethylene 6.7
tics resembling a liquid, and moving-bed units, Propane 0.25
which use either spherical or pelleted catalyst Propylene 1.5
circulated by elevators or gas lifts. Butane 0.0
The cracking of the feed takes place in a Butylene 0.75
chemical reactor vessel. The preheated catalyst Liquid hydrocarbons 1.30
is maintained in a fluid state, and during the
COMBUSRON
Fossil Fueb

This combustion process, therefore, normally burned, now they are much more aware of the
produces an appreciable percentage of carbon economic value of a quality blast-furnace gas.
monoxide. Present-day furnaces burn this fuel in any
The gas, although at temperatures as high as one of three different states: (1) as raw gas with
112jF, has a heating value of not over 40 Btu some of the dust and dirt removed; (2) after the
per cu ft. A typical analysis of the constituents gas has had a "primary" cleaning or washing;
in regenerator waste gas follows: and (3)after it ha; been thoroughly dedusted or
Co 6.9% washed by means of "final" as well as "pri-
CO e 8.1% mary" cleaners.
DUST
02 0.8%
S2 65.8% The high velocity at which blasts of air sweep
H2 0 18.4% through the alternate layers of coke, iron ore,
and limestone causes many fine particles, and
BLAST-FURNACE GAS some fairly large lumps, to be carried along in
Since blast-furnace gas is one of the most im- suspension as dust. In some cases, as much as
portant byproducts in the smelting of iron ore 50 grains of dust per stahdard cubic foot (at
to obtain pig iron, its characteristics are best 60F and 30 in. Hg) have been measured in the
understood by examining what takes place in a gas leaving the top of the blast furnace. Burned
blast furnace when in operation. in this state, the gas would quickly plug the fir-
Iron ore, qoke, and limestone are alternately ing equipment and boiler passages, and require
charged into the furnace from the top at the almost continuous shutdown for cleaning.
same time that air, previously heated to be- Generally, therefore, many of the suspended
tween 1100 and 1300F, is blown into it solids are removed, before firing, by passing
through openings at the bottom. In moving the blast-furnace gas through a dry dust
down through the furnace, the mass of solid catcher. On exiting from this dust catcher as
raw materials is vigorously scrubbed by air "raw gas," it still contains 3 to 15 grains of dust
which sweeps upward at velocities up to 450 ft per standard cu ft, and, in this condition, it is
per sec. The process of extracting iron from its sometimes burned under steam-generating
ore begins when carbon in the coke unites with units.
oxygen in the air to form carbon monoxide, CO, More often, however, before being delivered
with the liberation of heat. Next, the presence to a boiler furnace, the gas is given an addi-
of more carbon together with this heat reduces tional, or primary, cleaning by means of either
the iron oxide and converts some of the carbon a dry separator or a washer, to reduce the dust
monoxide to carbon dioxide, C02. To facilitate content to 0.1-0.8 grain per standard cu ft. As
removal of impurities from the molten mass, desired, following the "primary" cleaners,
limestone is added and more C 0 2is formed. either dry or wet final cleaners further remove
Besides carbon monoxide and carbon remaining dust content to 0.005-0.05 grain per
dioxide, blast-furnace gas contains nitrogen, standard cu ft. When washed, blast-furnace gas
hydrogen, and sometimes, small amounts of can carry a considerable amount of water in
methane (Table XXIV). The last two are the suspension as fine droplets as well as water
result of high-temperature dissociation of vapor.
moisture which enters the furnace with the ma- TEMPERATURE
terials charged. whereas the nitrogen in the The temperature at which blast-furnace gas
analyses is almost exclusively derived from the reaches the boiler depends on the kind of clean-
air blast. ing apparatus employed. As raw gas coming
IVhile at one time iron and steel producers from the dust catcher, its temperature may be
concentrated their entire attention on getting anywhere from 300 to 800F. If the subsequent
the highest yield of pig iron per ton of coke cleaning is done with dry separators, the drop
COMBUSTIOX#
Fossil Fuels

Table XXIV. Characteristics of Typical Blast-Furnace Gases


at 60F and 30 In. Hg, Dry
-4 a t Zero
% b y Volume - Density, HHV - Excess Air,
COz Nl CO I& CHr Lb/Cu Ft BNCuFt* BtdLb Lb1106Btu

14.5 57.5 25.0 3.0 ... 0.0779 90.1 1150 576

* If gas is saturated with moisture at 60F and 30.0 in. Hg, reduce by 1.74%

in gas temperature through each separator may Furthermore, in some cases the distance from
be only 30 to 50F. On the other hand, washers, blast furnace to boiler is sufficiently great to
using sprays of water to precipitate the dust, cause a drop in temperature from radiation los-
lower the temperature of the gas to 70-120F. ses in the connecting piping.

REFERENCES AND FOOTNOTES


George Frederick Gebhardt, Steam Power Plant Engineer- Illinois University at Urbana-Champagne. Engineering
ing, Chapter I1 "Fuels," 6th ed. New York: John Wiley and Experiment Station Bulletin Series no. 180, "The Classifi-
Sons, 1925. cation of Coal," by S. W. Parr, 1928.
James A. Kent, ed. Riegel's Handbook of Industrial Chem-
istry, 7th ed. New York: Van Nostrand Reinhold Co. 1974. W. H. Ode and F. H. Gibson, "Effect of Sulfur Retentionon
Determined Ash in Lower Rank Coals," U. S. Bureau of
Sam H. Schurr and Bruce C. Netschert, Energy in the Mines, Report of Investigation 5931. \$lashington: U. S.
American Economy, 1850-1975: An Economic Study qf Bureau of Mines, 1962.
Its History and Prospects. Originally published by John
Hopkins Press, 1960. Reprinted 1977 by Greenwood Press, 6National Research Council. Committee on Chemistry of
Inc., Westport, CT; pp 57-83 and 302-346. Coal. Chemistry of Coal Utilization, Supplementary Vol-
ume, ed. by H. H. Lowry. New York: John Wiley, 1963.
A. J. Johnson and G. H. Auth, ed., Fuels and Combust~on
Handbook. New Yark: McGraw-Hill, 1951. Chapter 5, "Coal Analysis and Mineral Matter," by LIT. H.
Ode.
National Coal Association, Coal Facts. Washington:
National Coal Association, 1979.
H. Kreisinger, "High and Net Heat Values of Fuel," Com-
bustion, 2(2):25-26 and 47, Aug. 1930.
William Kent, "Classification and Heating I'alue of Amer-
ican Coals," Transactions of [he ASIME, 36: 189-209,
1914. SRoy F. Abernethy and Elsie M. Cochrane, "Fusibility of
Ash of United States Coals," U. S. Bureau of Mines, Infor-
A. C. Fieldner, "Constitution and Classification of Coal." mation Circular 7923. Washington: U.S. Bureau of Mines,
Transactions of the ASME, Paper FSP 50-51: 49-50, 1960.
1927-1928.
Henry Kreisinger and B. J. Cross, "Burning Characteristics Roy F. Abernethy and Elsie M. Cochrane, "Free-Swelling
of Different Coals," Transactions of the ASIIE, Paper FSP and Grindability 1-ndexes of United States Coals,'' U. S.
- 50-5.2: 49-50,1927-1928. Bureau of Mines, Information Circular 8025. Washington:
U. S. Bureau of Mines, 1961.
Illinois University at Urbana-Champagne. Engineering
Experiment Station. Bulletinseries no. 37, "Unit Coal and 9 Badzioch, S., and Hawksley, P.G.W., "Kinetics of Thermal
the Composition of Coal Ash," by S. W.Parr and \I. F. Decomposition of Pulverized Coal Particles:' Ind. Eng.
Wheeler, 1909. Chern. Process Des. Develop.. 9, 521 (1970).
COMBUSTION
FossilFuels

loNsakala, N., Essenhigh, R. H., and Walker, Jr., P. L., 18 John T. Pfeffer, Reclamation of Energy from Organic
"Characteristics of Chars Produced fmrn Lignites by Waste: Final Report. Report No. PB-231-176 (EPA-67012-
Pyrolysis at 808% following Rapid Heating:' Fuel, 57, 74-016), prepared under EPA grant No. EPA-1P-80766,
605 (1978). Department of Civil Engineering, University of Illinois,
Urbana, Illinois, Mar. 19,741 Springfield, Va.: National
11Pollock.W. H., Goetz,. G. J. and Park, E. D., "Advancing Technical Information Service.
the Art of Boiler Design by Combinirig Operating Experi-
ence and Advanced Coal Evaluation Techniques." Pre- 19 W. E. Franklin, D. Rendersky, L. J. Shanon, and W. R. Park,
sented at the American Power conference at Chicago, Resource Recovery: Catalogue of Processes, Report No.
Illinois, April 18-20, 1983; also as Combustion Engineer- PB-214 148, Midwest Research Institute, Kansas City,
ing publication TIS-7382. Mo., Feb. 1973. gpringfield, Va.: National Technical
Information Service.
12 Nsakala, N., Patel, R. L. and Borio, R. W., 'Rn Advanced
Methodology for Prediction of Carbon Loss in Commer- fOW. E. Franklin, D. Bendersky, L. J. Shannon, and W. R.
cial Pulverized Coal-Fired Boilers:' Presented at 1986 Park, Resource Recovery: The State of Technology, Report
ASbfEIIEEE Joint Power Generation Conference at Port- No. PB-214 149, Midwest Research Institute, Kansas City,
land, Oregon, October 19-23, 1986; also as Combustion February, 1973. Springfield, Va.: National Technical In-
Engineering publication TIS-8211.
formation Service.
:j Brunauer, S., Emmett, P.H., and Teller, E., 'fidsorption of
Gases in Multi-layers," J. Am. Chem, Soc., 60, 309 (1938). "Gerald E. Dreifke, David L. Klumb, and Jerrel D. Smith,
"Solid Waste as a Utility Fuel,",Proceedings of the Ameri-
14Nsakala. N., Patel, R. L., and Lao, T. C., "Combustion can Power Conference, Vol. 35: 1198-1206. Chicago: 11-
Characterization of Coals for Industrial Applications:' Fi- linois Ins~ituteof Technology, 1973.
nal Technical Report DOEIPC140267-5, Contract AC22-
81PC40267, March 1985. l2 D. Joseph Hagerty, et al., Solid Waste management. New
York: Van Nostrand Reinhold Co., 1973.
1s F. Nowak, "Considerations in the Construction of Large
Refuse Incinerators:' Proceedings of the 1970 National
Incinerator Conference, Cincinnati. May 17-20, 1970. L3Joseph G. Singer and Joseph F. Mullen, Closing the
Sponsored by ASME Incinerator Division. New York: Refuse Power Cycle, presented at the ASME-IEEE Joint
American Society of Mechanical Engineers, 1970, Power Generation Conference, New Orleans, Sept. 16-
pp 86-97. 19, 1973, ASME Paper-73-PWR-18; also as Combustion
Engineering Publication TIS 3612.
l6 J. \IV. Regan, "Generating Steam from Prepared Refuse,"
Proceedings of the 1970 National Incinerator Conference, 24 Robert A. Lowe,Enegy Recoveryfrom Waste: Solid Waste
Cincinnati, May 17-20, 1970. Sponsored by ASME In- as Supplementary Fuel in Power Plant Boilers, Report No.
cinerator Division. New York: American Society of PB-256 494 (EPA-SW-36d. ii), Grant No. S-802255, pre-
Mechanical Engineers, 1970, pp 216-223. pared by the City of St. Louis, Mo. in cooperktion with
Union Electric Co., St. Louis, Mo., 1973.
ASME 71-WAIInc-1
by A. D. ~ o n o ~ k a - s y s t e m sEvaluation of Refuse as a Low
Sulfur Fuel: Pt. 3-Air Pollution Aspects. 25 John H. Fernandes and R. C. Shenk, "The Place of Inciner-
ation in Resource Recovery of Solid Waste," Proceedings
IInc-2 of the 1974 National Incinerator Conference, Miami, May
by R. E. Sommerlad, et. a1.--Systems Evaluation of Refuse 12-15, 1974: Resource Recovery Through Incineration,
as a Lorr Sulfur Fuel: Pt. 2-Steam Generator Aspects. 1-10, sponsored by the ASME Incinerator Division. New
IInc-3 York: American Society of Mechanical Engineers, 1974.
by A. &I. Roberts and E. M. Wilson-SystemsEvaluation
of Refuse as a Low Sulfur Fuel: Pt. 1-The Value of Refuse l6 ASTM Standards, Parts 15, 24, and 140, D 2161, "Stan-
Energy and the Cost of Its Recovery. dard Method for Conversion of Kinematic Viscosity to
Presented at the ASME Winter Annual Meeting, Saybolt Universal Viscosity or to Saybolt Fur01 Viscos-
\Vashington, D. C., Nov. 28-Dec. 2, 1971. New York: ity." Philadelphia: American Society for Testing and Ma-
American Society of Mechanical Engineers, 1971. terials, latest edition.
CHAPTER 3

Properties of Coal Ash

A s mined, coal contains varying quantities


of mineral matter which, when the coal
is burned, results in the incombustible residue
other components present, oxides of sodium
and potassium are important only as they act as
fluxes in fusing the ash.
known as ash. Most of this mineral matter was
carried in by wind and water; only a small frac-
tion was inherent in the original vegetation. ASH IN COAL:
The mineral matter from which ash is formed is
an undesirable substance in the coal. An inert
PRINCIPAL DESIGN FACTOR
material on which freight must be paid, it must The management of this coal ash is one of the
be removed from the furnace as fast as it ac- major considerations in the design of a coal-
cumulates; otherwise, it may cause interrup- fired steam generator. The behavior of the
tion in operation. Also, provision must be made mineral matter in a coal, as it influences fur-
for handling and disposing of the ash, both nace-wall slagging during the combustion pro-
functions representing items of cost. cess, is a significant factor in furnace sizing in
The mineral matter of coal cannot be com- terms of volume, plan area, and fuel-burning
pletely separated by any physical method to zone. Mineral matter formed as tenacious de-
identify fully the individual minerals or to de- posits on waterwall surfaces insulates the heat-
termine them quantitatively. Therefore, to as- transfer portions of the furnace-thus, the ash
sess the amounts of the major elements present properties affect the disposition of both radiant
in coal, an analysis is made to determine the and convective heating surface, as well as the
percentages of the oxides' of these elements number of furnace-wall cleaning devices (usu-
present in the coal ash. ally known as sootblowers).
The ash analysis does not indicate the nature The behavior of this mineral matter, as it in-
or distribution of the mineral matter but, nev- fluences fouling of convection-type surfaces,
ertheless, provides information which is useful affects the amount of such surfaces, their spac-
in both the study and the utilization of coal. ing. and the quantity of sootblowers for clean-
Examination of many coal-ash analyses shows, ing these heat transfer surfaces.
in almost all cases, that oxides of silicon, And the percentage of this mineral matter in
aluminum, iron, calcium and magnesium ac- the coal is significant because of the amount of
count for 95 percent or more of the ash. Of the slagging and fouling that it can cause, the bur-
COLIBUSTION
Properties of Coal Ash

den that it places on ash-handling equipment presented and discussed-all as they relate to
and disposal facilities, the frequency and slagging and fouling of boiler surfaces.
length of sootblowing, and the rate of wear of Methods of ash analysis that have been devel-
pulverizer parts. Thus, for any given chemical oped recently are described; and the mech-
and physical properties of coal ash, their net ef- anism of fire-side metal loss by either corrosion
fect on the boiler during a given time period or erosion caused by fuel ash is covered. Ap-
will be directly proportional to the amount pendix B contains additional engineering data
fired in the furnace. on other significant ash properties. All such
A corollary of this observation on the mnn- information. is of vital concern to engineers
agement of ash is that completely de-ashed coal making decisions about furnace size and
of any type or rank can be burned in a furnace heating-surface arrangements.
designed specifically for oil or gas firing. That
is to say, ash is what gives a coal its "charac-
ter." Witl~outash, ail furnaces could easily be COMPOSITION OF COAL ASH
designed on the basis of heat transfer only. Coal ash consists almost entirely of metal
Students, designers, and users of large pul- oxides. The composition varies over a wide
verized-coal boilers must realize that since the range, and there is no "typical" ash analysis.
1920's, substantial work has been done to es-
CHEMICAL ANALYSES
tablish "scientific" methods for the sizing of
furnaces. Further, during these years, much Chemical analyses of coal ash provide data
has been learned about the ways in which cer- from which to estimate coal-ash and slag
tain coals (and their ash) act in different sizes characteristics, as well as calculate various cor-
and types of furnaces. relation parameters. Analyses are generally
But it must be understood and accepted that, performed on ash prepared toASTM Standards
as the art exists today, engineering judgment, D 3 174, Ash in the Analyses Sample of Coal and
based upon what we know about the ash in a Coke. Pulverized coal is burned i n a ceramic
coal (based on ASTM analyses and other para- crucible, in air, at 1290-1380F, to completion
metric data) and how that ash has "behaved" in (except for the ash residue). I

actual furnace operation, is the only guide to Chemical analyses of coal ash are reported as
sizing new and larger furnaces. the mass percent of each equivalent oxide and
In this chapter, then, most of the useful phys- are generally expressed as:
ical and chemical properties of ash are given.
Useful parameters for categorizing ash also are SiO, + A120:, + Fe20, + CaO + MgO + Na,O + K,O

Table I.Coal-Ash Chemical


.
+ TiO, + P 2 0 5+ S O , = l?OOh
7lj
Composition Ranges
Because it is usuallj~present in insignificant
Oxide Component Percentage quantities, PZO5is sometimes omitted.
SiO, 10- 70 Table I gives the ranges of the chemical com-
A1203 8-38 position of most coal ash.'
FeQ3 2-50 Research has shown that the chemical com-
CaO 0.5-30 position of coal ash prepared to ASTM Stan-
MgO 0.3-8 dards D 3174 is different from that of flyash,
Na,O 0.1-8 bottom ash, or waterwall slag as they occur in
K ,O 0.1-3 actual boiler furnaces. However, because few
TiO2 0.4-3.5
adequate alternatives have been established,
so, 0.1-30
coal ash and slag behavior commonly are esti-
mated using the chemical composition of the
COMBUSTION
Properties of Coal Ash

ash. Methods involving gravity separation of Thermal reactions among ashiforming rnin-
pulverized-coal fractions can be used in an ef- erals are an important, although very complex,
fort to simulate the segregation effects in an ac- subject. Fig. 1 gives an overview of important
tual furnace. (See the section of this chapter on steps during the heating of mineral matter.
Selective Deposition of Ash Constituents.) CHEMICAL REACTIONS
MINERALOGICAL ANALYSES DURING COMBUSTION
Mineralogical analyses of coal ash attempt to Most ash constituents will not be in the form
identify the original mineral-matter forms in shown in Table4 when the coal goes to the fur-
coal. The thermal behavior of coal ash in an
operating furnace largely depends on the reac-
tions between the ash-forming minerals, which Table 11. Typical Mineral Species
cannot be detected by the ordinary chemical Found in Coal
analyses. Accordingly, it can be argued that
coal-ash and slag behavior should be charac- Mineralspecies
terized by its mineralogical composition and Kaolinite Al,03 . 2Si02 ..H,O
not by its chemical composition. However, to Illite K 2 0 . 3Al2O3. 6 S i 0 2 - 2H,O
date, neither a standard procedure for the low- Muscovite K 2 0 . 3A1203. 6 S i 0 2 . 2 H s 0
temperature ashing technique nor a criterion Biotite K 2 0 . MgO . Al2O3 . 3Si0, . H 2 0
for mineral detection has been established. Orthoclase K1O . A1203.6SiO2
Mineralogical analyses of coal ash can be Albite Na,O - A1,O3 . 6 S i 0 ,
performed either on ash prepared according to Calcite CaC03
ASTlM Standards D 3174 or, preferably, on ash Dolomite CaC03 . MgC03
prepared according to the low-temperature Siderite FeC03
ashing technique. Low-temperature ash is pro- Pyrite FeSz
duced by placing pulverized-coal samples in Gypshm CaS04 . 2 H 2 0
an oxygen plasma at approximately 400F. The Quartz SiO,
oxygen will gradually break down the organic Hematite Fe203
matter without excessive thermal decomposi- Magnetite Fe304
tion of the inorganic mineral species. Kutile TiO,
At least a hundred mineral species are Halite NaCl
associated with coal. Table I1 lists the more Sylvite KC1
abundant mineral forms.

IReactions with FeS

Evolution of . Volatilization
COz,SOz, SO3 Volatilization of Alkalies
Slagging
and Clinkering Volatilization of SiOz

I Temperature,OF
I
Fig. 1. Effect of heating on coal mineral matter

3-3 !!A
CoLaBmnoN
Properlies of Coal Ash

nace. As has been pointed out, the bulk of the physical properties different from those of the
ash is mineral matter brought in by water, and ash carried by the gases.
is largely a mixture of the various compounds. In slagging- or wet-bottom pulverized-coal
These compounds change considerably as they furnaces, a considerable part of the iron com-
pass through the furnace and are subjected to pounds in the slag may be reduced to metallic
high furnace temperature. Chemical reactions iron, which sinks to the bottom of the molten
take place among these substances, and also be- slag and is difficult to remove in either hot or
tween them and the reducing gases and hot cold state.
carbon. They form new and more complex In some coals, the iron is in the form of pyrite,
compounds, usually containing less oxygen FeS2, which, while passing through the fur-
than the original constituents, because the ox- nace, undergoes various changes. Both the iron
ygen is taken away by the reducing gases and and the sulfur may combine with oxygen, iron
hot carbon. This is particularly true of the ferric forming the lower oxides and sulfur, SO2 or
oxide, Fe203,which occurs in the coal largely SO3. Sulfur may also combine with the
as pyrites, FeS2.This may be reduced to FeS or alkaline metals, Na and K. to form sulfur com-
to the lower oxides, Fe304and FeO, or even pounds, which have very low fusion temper-
metallic iron, Fe. The lower sulfide and oxides ature. In slagging-bottom furnaces, where the
have lower softening and fusion temperatures. molten ash remains in a liquid state over ex-
While going through the fusion state, the new tended periods of time, some of these sodium
compounds form solutions, and this change and potassium sulfur compounds are vapor-
further lowers the fusion temperature. ized, then condensed on watercooled furnace
As a rule, ash high in SiOp or alumina has walls, and may become an important factor in
high softening temperature, and this tempera- external corrosion of furnace-wall tubes.
ture is not greatly affected by reducing atmo-
sphere. The alkali metal compounds NanO and
K20,as well as the alkaline earth, magnesium COAL-ASH SLAGGING
oxide, tend to lower the softening temperature AND DEPOSITION
of the ash.
A number of parameters are used for evaluat-
IRON IN COAL ASH ing coal-ash behavior as they affect furnace
slagging and deposition on both the furnace
Iron compounds are responsible for much of walls and convection surfaces. Some of these
the misbehavior of coal ash. Therefore, coals parameters are
with ash high in iron are ahvays suspected of
ash-fusibility temperatures
causing trouble. If the ash, and particularly the
iron, is uniformly distributed through the coal, baselacid ratio
difficulties are more likely to occur than if the 1irodcalcium ratio .
iron compounds are in large pieces, separated 1silicalalumina ratio
from the coal. When the coal is pulverized, the ironldolomite ratio
larger and heavier pieces of ash are rejected by dolomite percentage
some pulverizers and do not go through the
1ferric percentage.
furnace. In screenings with a high percent of
fines, the ash is uniformly distributed through Such indices help organize the ash composi-
the coal, and therefore compounds of iron are tion into "building blocks" that lend insight to
likely to cause trouble. expected behavior under burning conditions.
In pulverized-coal firing, there may be a con- Some confusion exists between the terms
siderable separation of the different constitu- slag and deposits (or deposition). Definitions
ents of the ash. The ash deposited at the furnace as they apply to pulverized-coal firing are:
bottom will have chemical composition and 1. Slag-fused deposits. or resolidified molten
COMBUSTION
Properties of Coal Ash

material that forms primarily on furnace walls formed) is maintained inside the furnace. Dur-
or other surfaces exposed predominately to ra- ing the heating process, changes in the shape of
diant heat or high gas temperatures. the pyramid are observed, Fig. 2, and the fol-
2. Deposits-bonded (sintered or cemented) lowing four charact~rjsticdeformation tem-
ash buildup that forms primarily on such con- peratures are reported:
vection surfaces as superheater and reheater 1. Initial Deformation Temperature (IT): The
tubes but also on furnace walls at lower than temperature at which the tip of the ash pyramid
slag-producing temperatures. begins to showqany evidence of deformation.
A summary of ash properties in terms of Shrinkage of the cone is ignored if the tip re-
slagging and deposition is given in the follow- mains sharp.
ing sections of this chapter. 2. Softening Temperature (ST), H = W: The
MEASURING ASH-FUSIBILITY temperature at which the ash sample has fused
TEMPERATURES into a spherical shape i~ which the height is
equal to the width at the base. The H = W soft-
Ash fusibility has long been recognized as a ening temperature in a reducing atmosphere
tool for measuring the performance of coals re- frequently is referred to as the "fusion
lated to slagging and deposit buildup. It is still temperature."
perhaps the most basic means for predicting 3. Hemispherical Temperature (HT),H = 112W:
coal-ash performance. Other parameters are
The temperature at which the ash sample has
used primarily to explain or amplify ash-
fused into a hemispherical shape where the
fusibility temperatures. In general, high fusion
height is equal to 112 the width at the base.
temperatures result in low slagging potential
in dry-bottom furnaces, while low fusion 4. Fluid Temperature (FT): The temperature
temperatures are considered mandatory for at which the ash sample has fused down into
wet-bottom (slag-tap) furnaces. a nearly flat layer with a maximum height of
Many experimental methods have been de- 1116 inch.
veloped for measuring the fusion temperatures Prior to the revision of ASTM Standards D
of coal ash. Most tests are based on the gradual 1857, only three characteristic deformation
thermal deformation of a coal-ash sample, and temperatures (initial deformation, softening,
the characteristic fusion temperatures are re- and fluid) were observed with no dimensional
ported when the sample fuses into certain dis- (height-to-width) specifications for the soften-
tinctive shapes or heights. Most test methods ing and fluid points. Because of such differ-
are strictly empirical and have little theoretical
basis. The following descriptions characterize
some of the methods.
ASTM STANDARDS METHOD
I 1
ASTM Standards D 1857, Fusibility of Coal 1 2 3 4 5
IT ST HT FT
Ash, gives the experimental procedure for one
method of testing. The test is based on the 1. Cone Before Heating
gradual thermal deformation of a pyramid- 2. IT(or1D) Initial Deformation Temperature
shaped ash sample, 314 inch in height and 114 3. ST Softening Temperature (H=W)
inch in equilateral-triangular base width. 4. HT Hemispherical Temperature
Mounted on a refractory substrate, the sample (H ='/2W)
5. FT Fluid Temperature
is heated at a prescribed rate in a gas or electric
furnace. A controlled atmosphere (reducing or Fig. 2. Critical temperature points as defined
oxidizing, depending upon the tests to be per- in ASTM Standards D 1857
COISI)VSTION
ProperUes of Coal Ash

ences in definitions, earlier investigations have on a platinum-covered refractory substrate,


reported the softening temperatures without which is placed on an electric heating element.
distinguishing between their being spherical The heating element, together with the ash
or hemispherical. Unless specified otherwise, sample, is inserted into a small furnace and
the softening temperature may be assumed to heated at a prescribed rate. A controlled at-
represent the spherical point, where H = W. mosphere (either reducing or oxidizing) is
Although the earlier standard procedure maintained inside the furnace. An image of the
used only reducing atmospheres for the tests, sample is projected onto a graduated screen so
many studies give the ash-fusion temperatures that changes i n the shape of the ash can be ob-
without specifying the atmosphere; it thus served. The following three characteristic tem-
must be assumed that the tests were carried out peratures are reported:
in a reducing atmosphere. 1. Softening Temperature: The temperature at
BRITISH STANDARD METHOD
which the first indication of softening appears,
mainly in the form of rounding of the edges or
In principle, the British standard method is swelling of the sample.
similar to the ASTM method, but differs from it 2. Hemispherical Temperature: The tempera-
in several experimental specifications. B.S. ture at which the ash sample has fused into a
1016, Part 15, gives the procedure for this hemispherical shape where the height is equal
method of testing. The British method specifies to 1/2 the base width.
that the ash sample be a pyramid of 8 to 13 mm
in height with the height 2 to 3 times the width 3. Flow Temperature: The temperature at
of the triangular base. Mounted on a refractory which the ash sample has fused into a flattened
substrate, the sample is heated at a prescribed disk such that the height is reduced to 1/3 the
rate in an electric furnace with a controlled at- original sample height.
mosphere (either reducing or oxidizing) main- OTHER METHODS
tained inside the furnace. During the heating Similar to the German method in experimen-
process, changes in the sample shape are ob- tal procedure and specifications, the Inter-
served through a magnifying optical instru- national Standard Method, I S 0 540, requires
ment and the following three characteristic the observation of three characteristic tem-
deformation temperatures are reported: peratures-initial deformation, hemispher-
1. Initial Deformation Temperature: The tem- ical, and flow. However, a greater latitude is
perature at which the tip of the ash pyramid be- allowed in the shapes and dimensions of the
gins to show any evidence of deformation. ash sample, because it has been shown that
2. Hemispherical Temperature: The tempera- geometrical variations in the sample, within
ture at which the ash sample has fused into a certain limits, have little influence on the ob-
hemispherical shape where the height is equal served results.
to l/z the width. The Russian experimental procedure (GOST
3. Flow Temperature: The temperature at 2057-68) is similar to the German; characteris-
which the ash sample has fused into a flattened tic deformation temperatures reported during
disk shape such that the height is '1.5 the width. the heating of the sample are the deformation
temperature, the softening (hemispherical)
GERMAN STANDARD METHOD
temperature, and the temperature of beginning
German Standard DIN 51 730 describes the of liquid fused state.
procedure for this method of testing. The test is
RELATION BETWEEN CHEMICAL
based on the gradual thermal deformation of a
AND MINERALOGICALCOMPOSITION
cylindric sample of coal ash, 3 mm in height
and 3 m m in diameter, or a cubic sample of coal BarrettZ,Estep et a13, and Thiessenet a14have
ash with 3 mm edges. The sample is mounted shown that the fusion behavior of coal ashes is
COMBUSTION
Properties of Coal Ash

quite similar to that of the corresponding oxide perature spread from initial deformation to
mixtures. Barrett concluded that, if coal ashes fluid temperatures indicates that the wall slag
are finely ground, intimately mixed, and will be thin, running and tenacious. This type
brought to the same standard state before the of slag is extremely difficult to control by
fusion tests are made, then, (1) the fusion sootblowing. As the range from initial defor-
temperatures depend only on the composition mation to fluid temperature increases, the re-
and not on the manner in which the composi- sulting slag deposit will build up to thicker
tion is obtained; and (2) the softening tempera- proportions befye the surface becomes suffi-
ture is closely related to the equilibrium phase ciently liquid to run. The tube-ash bond is less
diagram of the corresponding oxide compo- adhesive and therefore responds better to re-
nents which make up the ashes. moval by sootblowing.
ASH-SOFTENING TEMPERATURE
RELATIONSHIP TO DEPOSIT REMOVAL PROPERTIES
If ash arrives at a heat-absorbing surface at a OF COAL-ASH COMPONENTS
temperature near its softening temperature, the
resulting deposit is likely to be porous in struc- The acidic oxide constituents SiOs, A1203,
ture. Depending on the strength of the bond, it and TiOl found in coal ash are generally con-
may fall off the metal surfaces from its own sidered to produce high melting temperatures.
weight or it can be removed by sootblowing. If Temperatures will be lowered proportionally
such a deposit is permitted to build up in a zone by the relative amounts of basic oxides, Fe203,
of high gas temperature, its surface (because of CaO, MgO, Na20,and K20 available in the ash
the insulating properties of the ash) can reach for reaction. Minerals associated with coals
the melting point and then run down the wall consist of multiple combinations of elements
surfaces in the furnace. listed in the first column of Table 111. If these
If ash particles arrive at the heat-absorbing elements were each exposed to air under the
surface at temperatures below the softening proper heat conditions, each nrould be con-
temperature, they will not form a bonded struc- verted to its highest form of oxide. Individual
ture, but instead, will settle out as dust. As melting temperatures of these oxides are listed
such, removal is comparatively simple. in the third column, and, assuming no interac-
On the other hand, if ash particles have been tion between them, the melting temperature of
subjected to temperatures higher than the soft- the ash would be represented by the weighted
ening temperature for a sufficient time to be- average of the oxides. But an interaction takes
come plastic or liquid, the resulting deposit place at elevated temperatures that produces
will be a coarse. fused mass condensed on the complex salts having entirely different physi-
cooler metal surface. The resolidified material cal constants. Among other changes, the melt-
is tightly bonded and difficult to remove. As ing temperatures of the compounds are usually
this material builds up on itself, its insulating lowered. The table lists some of the combina-
properties continuously increase the surface tions, with melting temperatures.
temperatures until the fluid temperature is The sum of the noted acidic components can
reached and slag runoff results. range from 20 to 90 percent of the ash. Gener-
ally, highly acid coal ashes have high ash-
INITIAL DEFORMATION-FLUID
TEMPERATURE DIFFERENTIAL
fusion temperatures and high slag viscosities.
The sum of the basic components can be be-
The temperature differential between initial tween 5 and 80 percent. Either high or low
deformation and fluid temperatures gives an basic values can result in high fusion tempera-
insight as to the type of deposit formation to tures. Minimum fusion temperatures occur at
expect on furnace tube surfaces. A small tem- about 30 to 40 percent basic component.
COMBUSTION
ProperUes of C w l Ash

BASEIACID RATIO used to describe the lowering in viscoiity of a


liquid mixture.)
This index is defined as: Also, an ash in which the major constituents
are alumina and iron will have different slag-
B Fe203 + CaO + MgO + Na20 + K 2 0
-
A
=
SiOl + A1203+ TiO,
ging characteristics from an ash in which the
components include higher percentages of
(2) silica and calcium and yet both can have the
same baselacid ratio.
Because most elements combine with each In any case, the baselacid ratio is a valuable
other according to their acidic or basic prop- supplement-to ash-fusibility temperatures and
erties, the baselacid ratio reflects a potential for other data in predicting the relative per-
ash-containing metals to combine in the com- formance of coal ash in the furnace. With most
bustion process to produce low melting salts. ash, a baselacid ratio in the 0.4 to 0.7 range
Extremes at either end of the baselacid ratio in- manifests low ash-fusibility temperatures and
dicate a minimum potential for forming com- a higher slagging potential.
binations with low fusibility temperatures.
SILICAIALUMINA RATIO
Note that the alkaline metals, sodium and
potassium, are exceptions in that they form The silicalalumina ratio is defined as:
low-melting ash regardless of the baselacid
combinations: therefore, their presence in an
ash composition in sufficient concentrations
significantly alters baselacid influences.
Although the baselacid ratio is an indication
of the fusion characteristics and slagging po- The general range of values is between 0.8
tential of a coal ash, it should not be used as the and4.0.
sole criterion of evaluation. A simple ratio such The silicalalumina ratio can provide addi-
as the baselacid ratio does not take into account tional information relating to ash fusibility. As
differences in fluxing action among the several both of these constituents are acidic and are,
bases nor does it recognize the degrees of in- therefore, considered high melting as oxides,
teraction with the acidic components. (Fluxing silica is more likely to form lower melting
property, in this connotation, is defined as a species (silicates) with basic constituents than
property of the component or substance which is alumina. For two coals having equal basel
lowers the fusion temperature of the mixture; acid ratios, tile one with a higher silicalalumina
the terms flux and fluxing property are also ratio should have lower fusibility temperatures.

Table 111. Properties of Coal-Ash Components

Element Oxide
Melting
Temp (OF)
Chemical
Property I Compound
Melting
Temp (OF)
Acidic I Na2Si03 1610
Acidic K2Si03 1790
Acidic A1203. NasO 6Si02 2010
Fe Fez03 2850 Basic A1203. KZO. 6SiOZ 2100
Ca CaO 4570 Basic FeSi03 2090
Mg MgO 5070 Basic CaO . F ~ , U ~
A 2280
Na Na,O Sublimes at 2330 Basic CaO . MgO - 2Si0, 2535
K K2 0 Decomposes at 660 Basic CaSi03 2804
COMBUSTION
Properties of Coal Ash

Effects of increasing amounts of alumina on IRONlCALClUM RATIO


the formation of the silicates depend on the
amount and the combination of bases present, This parameter, also known as the iron-
temperature and time of reaction, and other fac- oxidelcalcium-oxide ratio, is defined as:
tors. A finite evaluation is virtually impossible
because of the complex interactions. Fig. 3 il- Fez03
lustrates the effect of silicalalumina ratios on CaO
ash-fusibility temperatures. In laboratory in- 7
vestigations, varying proportions of silica and
alumina were mixed with an Illinois coal and As indicated, the baselacid ratio does not ac-
then burned in a mufflefurnace used to prepare count for differences in fluxing action. Among
ash for fusibility determinations. Fusibility the five basic-oxide components, iron and cal-
temperatures were determined in a reducing cium are the most important, primarily because
atmosphere. According to these data, no ap- they make up the largest amount of the basic
preciable change is noted between silical constituents. Iron oxides comprise 5 to 40 per-
alumina ratios of 1.7 and 2.8. At ratios less than cent of the ash and calciuin oxides make up 2
1.7, the softening and fluid temperatures both to 30 percent. The following statements, ex-
increase; at ratios greater than 2.8, the fluid tracted from ref. 5, relate the iron-calcium rela-
temperature decreases. Initial deformation tionship to the fusibility of ash.
temperatures were not affected by any wide "1. In the absence of lime, iron oxides do not
changes in'ratios. make the most fusible slags."
"2. Ferric oxide, up to about 20 percent, has a
fluxing effect which increases with the per-
Illinois Coal cenJage, but above 20 and up to 40 percent it
Ash Composition
does not materially increase the fusibility."
Si02 44.6 NazO 1.8
A1203 16.0 Kz0 2.4 "3. The combined fluxing effect of iron oxides
Fez01 21.5 Ti02 0.6 and lime has a complex relation to the percent-
CaO 4.1 PzOs 0.1 age of the two fluxes present. For ashes in
MgO 1.1 so3 5.5
which the percentage of iron oxide is over 14
I
percent, the addition of a given percentage of
A Initial Deformation lime produces a lowering of the fusion temper-
Softening Temperature atures greater than the same additional per-
centage of iron oxide."
'24. The quantity of magnesia present in coal
ashes is usually smaller than the lime; its flux-
ing effect with lime present is greater than that
of an equal additional amount of lime in about
the ratio of 3 :2 ."
Comparisons such as the following confirm
this decrease.

FezO~lCa0 Softening
Coal Fez03 CaO Ratio Temperature, "F
(1) 31.8 0.3 106.0 2360
(2) 24.8 2.0 12.4 2270
Fig. 3. Ash-fusibilitytemperatures as affected (3) 21.3 4.8 4.4 2130
by s~~calalumina ratios (C-E laboratory data)
COMBUSTION
Propertiesof Coal Ash

The ironlcalcium ratios of the three examples found to have similar fluxing properties, and
are 106,12.4 and 4.4 respectively. Fig. 4 shows the use of this ratio is recommended when the
the effect of limestone addition to fusibility MgO content of the ash is high.
temperatures on an Eastern U.S. coal. Based on Bituminous-type ash is characterized by an
these two data sources as well as observation of iron-oxideldolomite ratio greater than one,
other fusibility-ash composition relationships, while lignitic ash has Fe2031Ca0+ MgO in a
Fe2031Ca0ratios between 1 0 and 0.2 have a ratio that is less than one.
marked effect on lowering the fusibility tem-
peratures of coal ash. Extreme effects are evi- DOLOMITE PERCENTAGE(DP)
dent between ratios of 3 and 0 . 3 . This is defiked as:
IRONIDOLOMITE RATIO
CaO + MgO
The iron-oxideldolomite ratio is defined as; Dp = ( F e 2 0 3 + CaO + MgO + Na20 + K 2 0
x 100)
(6)

Fez03
This parameter is used primarily for coal ashes
CaO + MgO
with a basic-oxide content over 4 0 percent. It
Is) has been empirically related to the viscosity of
coal-ash slags.6 Its general range is from 4 0 to
This parameter is essentially identical to the 98 percent. At a given percent basic, a higher
Fe2031Ca0 ratio. CaO and MgO have been DP usually results in higher fusion tempera-
tures and higher slag viscosities.

Ash Composition Limestone EQUIVALENT Fen03


AND FERRIC PERCENTAGE (FP)
SiO2 51.2 Mg 0 1.0 Ign. Loss 43.4
A1203 24.7 Na2O 0.4 Ca 0 45.6 These parameters describe the degree of iron
Fez03 13.8 KzO 2.8 Mg 0 0.8 oxidation in coal-ash slags. They ,are defined
Ca 0 1.2 Ti02 1.0
Pzos 0.5 as:
-- -- .- -
... -

Fe20dCaO Ratio Equiv. F e 2 0 3= Fe20, + 1.11FeO + 1.43 Fe, and


0.7 0.5 0.3 0.2
FP = (Equiv. Fe203) X 100
(7)

These terms were introduced when it was ob-


served that the ash-fusion temperatures and
slag-crystallization temperatures were lower in
a reducing atmosphere than in an oxidizing
atmosphere. Experiments showed that this de-
viation was due to the different forms of iron
oxide that could exist depending on the sur-
2000~ 5 10 15 20 25 30 rounding atmosphere. It was concluded that
Limestone Added/l00 Lb Coal FeO and Fe are stronger fluxing agents than
Fe203and result in depression of ash-fusion
Fig. 4. Ash-fusibility temperatures of an Eastern and slag-crystallization temperatures. Thus,
coal as affected by limestone addition equivalent Fe203and FP depend on combus-
COMBUSTION
Propertiesof C-1 Ash

tion conditions and are usually determined by Many sodium compounds melt at tempera-
chemical analysis of actual furnace slags. tures below 900C (1650F). In addition, so-
In ASTM Standards D 1857, it has been dium solids manifest a property beyond
specified that a reducing atmosphere should melting temperatures alpne that contributes to
contain a mixture of oxidizing and reducing deposit building. Besides low melting tempera-
gases in which the content of the oxidizing gas tures, some sodium compounds volatilize at
is within the limits 20 to 80 percent by volume. relatively low temperatures. These disperse
In this range of gaseous composition, the iron is throughout the gas stream and subsequently
mainly in the ferrous state, FeO. Under condense on other ash particles and on metal
stronger oxidizing conditions, the iron is surfaces as heat is absorbed and gas tempera-
mainly in the ferric state, Fe203; under more tures are lowered. The condensed sodium pro-
reducing conditions, the iron is mainly in the vides a binding matrix for ash particles to fuse
metallic state, Fe. together and build up on tube surfaces. 7,879
Sodium oxide is transformed directly from a
SILICA PERCENTAGE (SP) solid to a gaseous state at 2330F. Because cer-
tain lignites and low-rank coals may have so-
This relationship is defined as: dium that is organically bound, they are
particularly susceptible to the formation of so-
dium oxide and consequent vaporization in the
SP = ( SiO, i.Equiu. Fe203
SiO,
+ CaO + MgO
combustion zone. The sodium is released to a
free state as the organics are consumed in the
flame and are immediately available for vapor-
ization into the gas stream. On the other hand,
sodium tied up as mineral salts must be first de-
SP, which has a range of 35 to 90 percent, has composed to a free state before it is available for
been empirically correlated with the viscos- vaporization and, therefore, may not be as pro-
ity of coal-asK slags. As SP increases, the slag portionally active.
viscosity increases. (Silica percentage is also A widespread distribution of sodium vapor
occasionally referred to as silica ratio or equiv- in the combusion gases assures contact with
alent silica content.) ash particles and metal surfaces as the gas cools
and the sodium condenses. Thus, particle
TOTAL ALKALIES (Na2O + K2O)
surfaces are "conditioned" for bonding and the
As previously noted, sodium and potassium resulting deposit forms rapidly. The rate of
metals join with other elements in combina- buildup is proportional to the amount of active
tions that produce low fusibility temperatures. sodium in the coal. This phenomenon applies
The influence of alkalies on fusibility and slag- particularly to high-alkali ash defined as West-
ging potential in the furnace is proportional to ern U.S. type ash. Because deposit buildup is
the quantity in the ash. rapid with such coals, tube spacing in convec-
With sodium-containing coals, the rate of tive passes must be maintained on wide centers
buildup and the ability to control deposits ef- to minimize bridging.
fectively seem to be related to the amount of
sodium present. This is particularly true of FORMS OF ALKALIES IN COAL
coals with lignitic-type ash (low iron, high al- Alkalies can be present in coal in various
kali, and high-alkaline earths) as found primar- forms. Alkalies which vaporize during combus-
ily in U.S. coals west of the Mississippi. The tion are often classified as active alkalies, be-
ash of such coals will contain CaO as high as40 cause they are free to react or condense
percent and the sodium oxide may range from 1 subsequently in the boiler. Active alkalies con-
to 15 percent, as extremes. sist primarily of simple inorganic salts and or-
mmOSTION
Properties of Coal Ash

ganically bound alkalies. More stable forms of Fouling


alkalies exist in impurities such as the clay and Potential ClOh,Coal Basis Equiv. Na %
shale minerals (silicates) which remain rela- High Greater than 0.5 Greater than 0.33
tively inert during combustion, and therefore Medium 0.3 0.2
are less influential in the ash deposition pro- Low Less than 0.1 Less than 0.07
cess. Fig. 5 summarizes the different categories
in which various alkali forms can be associated.
H. E. Crossley in his Melchett lecture to the Although the water-soluble sodium in a coal
Institute of Fuels in 1962 had this to say about is indicative of the sodium existing in an active
alkalies in coal: form, it may not represent all of the active so-
"It was known that alkalies existed in coal in dium in the coal. For many coals, in particular
two forms: chlorides and complex silicates. those of low rank, a high percentage of the so-
The chlorides could be expected to volatilize dium is present in an organically associated
readily during combustion but the silicates form; such organically bound alkalies are not
could be expected to retain alkali in the ashes. soluble in water.
Thus, if an attempt was madt: to r e l ~ t ethe forms
of alkali-rich deposits with alkali in coal, there A TECHNIQUE FOR DISTINGUISHING
could be presence of the complex silicates. It ACTIVE FROM INACTIVE ALKALI
was decided instead to use the amount of chlo-
rine as the index of volatile alkalies and this has To segregate the different categories of al-
been standard practice ever since. In conse- kalies, a technique has been developed utiliz-
quence, the determination of chlorine has be- ing a dilute acetic-acid medium. Leaching coal
dome an important item in the ultimate analysis samples in a dilute acetic-acid solution ex-
of coals."lO cr his statement does not include or poses the coal to a source of hydrogen ions. It
describe the mechanism of volatile sodium as appears that an ion exchange possibility exists
found in lignitic-type coals.) in which the hydrogen ions (H+) of the acid
The chlorine content itself can be used as an displace or exchange with metallic elements
indication of the fouling tendency of a coal, a associated with the organic coal molecules.
fact which has been recognized not only in this These elements include sodium,' potassium,
country, but in England. Crossley classifies calcium, and magnesium.
coals as follows: The weak acid used during leaching pro-
vides the hydrogen-ion source necessary to
-
Fouling Potential Chlorine O/O,Coal Basis displace organically bound elements, but does
High Greater than 0 . 3
not have the strong dissolving powers which
Medium 0.3 to 0.15
would be necessary to break down the complex
Low Less than 0.15
extraneous minerals. The constituents (in par-
ticular alkalies) removed from the coal essen-
American experience supports these conclu- tially consist of the organically bound material
sions, indicating that tightly bonded deposits along with the simple inorganic compounds.
in the convection areas can be expected when Alkalies present either in organic fractions or
the chlorine level exceeds 0.30. Rather than de- in simple inorganic salts can be expected to
pending on the measurement in the coal as the volatilize during combustion, and are therefore
yardstick for evaluating the ash fouling poten- of primary interest.
tial, another approach is ta measure the water- RESULTS OF WEAK-ACID ANALYSIS
soluble sodium in the-coal. The relationship of
water-soluble sodium as measured and the Analysis of acetic-acid-soluble alkalies has
chlorine, interpreted as sodium, is shown in been conducted on a cross-section of U.S. coals
the following table: for which performance characteristics are well
COMBUSTION
Properties of Coal Ash

established through commercial operation. times more than the soluble-potassium values.
Detailed data comparing the alkali contents In many U.S. coals, much of the potassium ap-
of the ash of seven U.S. coals are summarized in pears to be tied up in extraneous clay minerals
Table IV. The ash varies in fouling tendencies which do not break down readily when heated,
from severe to low or minimal. Values pre- making the potassium in this form less reac-
sented for sodium in the ash were determined tive. Although the potassium contents of these
by the conventional ashing and lithium tet- coals range from 0.5 to 1.9 percent K20 in the
raborate fusion procedure. ash, the acetic-acid-soluble potassium gener-
In general, the coals containing high alkali ally is equivalent to less than 0.1 percent K20in
contents and, in particular, high sodium con- the ash. Conversely, the acetic-acid-sodium
tents had the most severe fouling tendencies. content of the high-fouling coals represents
This is the expected trend. However, after virtually all of the NasO detected in the ash.
studying the acetic-acid-soluble alkaline con- The coals containing the most soluble alkali
tents of the coals, one is better able to relate were low-rank coals (subbituminous coals and
their fouling behavior. Past work has primarily lignites). It is believed that such coals can con-
focused on sodium as the bad-acting con- tain substantial quantities of alkali (as well as
'
stituent responsible for fouling. It is possible to alkaline-earth constituents) present as organi-
understand why sodium is frequently more in- cally bound humates. It appears that the poten-
fluential than potassium by comparing the rel- tial for having organically bound metallic
ative quantities of acetic-acid-soluble sodium compounds decreases as the coal rank in-
and potassium in Table IV. creases. The Utah high-volatile bituminous il-
What is believed to be the primary reason lustrates this tendency. This fuel contains a
that sodium has a greater influence is that relatively high sodium content ( 3 . 8 percent
sodium is frequently present in an active form, Na20 in ash). But the soluble sodium content is
whereas potassium is typically contained in a only about 40 percent of the "total" sodium and
less active form. Values for acetic-acid-soluble the overall fouling potential is low to moderate.
sodium in U.S. coals frequently range up to 10 In the case of the particular coals selected, all

I Alkali Contained in Coal I


Alkalies Alkalies

1. Simple Inorganic Salts: Clays and Shale Minerals:


Na CI, Na2S04, NazCO3 Complex Aluminum Silicates
Nan A12 Sis 0 1 6
2. Organically Bound Alkalies:
R-(H,O)-C-Na -.

Vaporize and/or Remain As Clays

I I

Fig. 5. Manner in which alkalies are contained in coal


COMBUSTION
ProprUes of Coal Ash
-
of the high-fouling coals had quantities of sol- RELATION OF FOULING POTENTIAL
uble sodium greater than the "total" quantity of TO ALKALI FORM
sodium detected in the ash by the conventional
technique. The lower values for "total" sodium The data in Table IV indicate that fouling po-
may be the result of a slight loss of organically tential of coal ash is related to both total quan-
bound material during'the ashing process. tity of acetic-acid-soluble alkali and to the

Table IV. Comparative Alkali Content of U.S. Coals -

Rank Lignite Sub B Lignite Lignite hvBb hvAb Lignite


Region ND MT TX (Yegua) TX (Wilcox) UT PA TX (Wilcox)
HHV, Btullb, Dry Basis 10640 12130 7750 9710 12870 13200 8420
Ash Composition (%)
SiO? 20.0 33.9 62.1 52.3 52.5 51.1 57.9
A1203 9.1 11.4 15.1 17.4 18.9 30.7 21.8
Fe 2 0 I 10.3 10.8 3.5 5.3 1.1 10.0 3.9
CaO 22.4 21.0 6.2 9.4 13.2 1.6 7.1
MgO 6.4 2.7 0.7 3.2 1.3 0.9 2.1
Na20 5.0 5.8 3.6 0.9 3.8 0.4 0.7
K20 0.5 1.6 1.9 1.2 0.9 1.7 0.8
Ti0 0.4 0.7 0.9 1.2 1.2 2.0 1.1
so3 21.9 12.0 6.1 9.6 6.2 1.4 4.4
Fouling Potential Severe High High Moderate Xioderate Low Low

Lb Ashl106 Btu, Dry Basis 9.0 4.6 43.3 20.1 7.9 10.2 \34.4
Acetic-Acid-Soluble
Sodium (Na, ppm) 3980 2680 9650 1030 1120 250 340
Potassium (K, ppm) ... ... 1230 85 85 ... 110

Alkali in Ash, Oh Wt.


Na20 5.0 5.8 3.6 0.9 . 3.8 0.4 0.7
K20 0.5 1.6 1.9 1.2 0.9 1.7 - 0.8

Equiv. Sol. Alkali in Ash,


O h Wt. of Ash

Na20 5.58 6.45 3.88 0.71 1.49 0.15 0.16


K2 0 ... ... 0.44 0.04 0.08 ... 0.05

OO
/Sol. Alkali of Total
(Equiv. Sol. N ~ * o ) /
(Na,O in Ash) 112 111 108 79 39 38 23

(Lbs Sol. Na)/


( l o 6Btu Fired) 0.373 0.221 1.245 0.106 0.087 0.M8- .040

(Lbs Sol. Na)/(lb ~ s h /


lo6 Btu Fired) 0.044 0.048 0.223 0.005 0.014 0.002 0.001
COMBUSTION
Propertles of Coal Ash

equivalent percentage of soluble alkali in ash. technique is the apparent sensitivity to the "ac-
The total volatile alkali is believed to be re- tive alkalies" present, which seem to be a pre-
flected by furnace input of soluble alkali listed dominant factor in high-fouling behavior.
in Table IV a s pounds of soluble sodium per
million Btu fired. It is postulated that the depo-
sition mechanism could involve the conden- SELECTIVE DEPOSITION
sation of the gaseous alkali species which OF ASH CONSTITUENTS
provides the sticky, bonding matrix to build
Several slagg;ng and fouling indexes to pre-
convection-pass deposits. The greater the
dict the behavior of coal ash in furnaces during
quantity of this "glue," the more severe the de-
position. Conversely, the greater the quantity the combustion of coal have been reviewed in
preceding text.Theseanalysesconsidera homo-
of ash particles, the thinner this "glue" would
geneous distribution of the mineral matter
be spread. Because this bonding matrix is a sur-
throughout the coal matrix. Such an assump-
face phenomenon, it would depend on both the
tion may be applicable to stoker firing, where
total quantity of vapor species znd the diluting
the coal particles, as fired, are relatively large,
influence of the ash. Therefore, a combination
but may not be applicable in pulverized coal
of pounds of soluble sodium per million Btu
where the composition of mineral matter of in-
fired and pounds of soluble sodium per pound
dividual particles can be quite different.". '*. l3
of ash per million Btu fired should be used
Because the behavior of an individual coal-ash
when evaluating the fouling potential of a fuel.
particle depends upon its composition, aver-
(See Table IV, bottom two entries.)
age properties may not be an accurate index of
VARIATION OF ASH PROPERTIES the slagging and fouling potential of a coal.
WITHIN A COAL SEAM Most evaluations of coal ash, including the
determination of fusibility temperatures, do
Note that it is possible to experience vastly not consider the phenomenon of selective de-
different ash properties within the same coal position when attempting to predict slagging
seam. This point is illustrated with the two and fouling behavior. The fractionation of a
comparative lignites mined in Eastern Texas coal prior to a determination of fusibility tem-
from the Wilcox formation. The sodium con- peratures can provide a better insight into what
tents of the two lignites are very similar (0.9 occurs within the furnace; i.e., individual par-
percent and 0.7 percent NazO in ash respec- ticles of ash can act independently of one
tively). However, the ash-fouling behavior another with respect to their physical state and
of these fuels is significantly different, as reactions in the flame. 7I-'
vividly illustrated by the acetic-acid-soluble
sodium contents of the coal. Roughly 80 per- THE DISTRIBUTION OF MINERAL MATTER
cent of the sodium in the moderate-fouling IN THE COAL MATRIX
Wilcox lignite could be considered active com- Ash-fusibility temperatures as determined
pared to only 23 percent for the low-fouling by ASTM procedures are the temperatures at
lignite. On a concentration basis (pounds of which the composite ash sample initially de-
sodium per pound of ash per million Btu fired), forms, softens, and becomes fluid. These val-
the moderate-fouling lignite has more than 10 ues, as well as such ratios as baselacid, iron1
times that of the low-fouling lignite because of calcium, and silicalalumina, provide a guide to
the ash dilution. the slagging and fouling characteristics of the
The acetic-acid-soluble technique is rela- coal being burned. But they do not predict how
tively new, such that the limited data thus far the various minerals behave during the com-
accumulated neither allow development of bustion process. Ash deposits on furnace walls
quantitative relationships nor define the relia- differ significantly from the ash of the as-fired
bility of the analysis. But the major value of the coal. Use of the coal-ash fusibility values and
COUBVSRON
Propedhs of Coal Ash
e -
the coaYash ratios does not explain the selec-
tive deposition of ash constituents noted on V*
furnace walls. of Ash Deposit Composition
Table V shows the composition of deposits with As-Fired Coal Ash
collected from a boiler burning a high-volatile
Ash As-Fired Lower Furnace
bituminous coal and compares it with the com- Composition Coal Ash Ash Deposit
position of the as-fired ash. The most notable
SiOz 47.0 33.3
difference in the composition of these two
A1203 26.7 18.0
samples is the iron content, the ash deposit
Fe203 14.6 43.5
having an iron content over three times as great
CaO 2.2 1.2
as the coal ash as-fired. The amount of differ-
MgO 0.7 0.5
ence between as-fired ash and that taken from
tube surfaces is a function of the distribution of Na 20 0.4 0.2
K2 0 2.3 1.6
mineral matter in the coal matrix.
These data suggest a mechanism that can ex- Ti02 1.3 0.8
p205 0.9 0.4
plain why some coals slag more than con-
ventional analysis would indicate. Coal is a so 3 1.1 0.5
heterogenous substance in terms of its organic to 40 percent are pure mineral matter (extrane-
and inorganic content. The coal-preparation ous only).
engineer makes use of this knowledge in most Comparing the composition of particles that
beneficiation processes. Density differences or result from pulverization can show an extreme
surface property differences are exploited difference in constituents. Because these parti-
when separating clean coal from the refuse or cles are fired in suspension, the behavior of the
high-ash-containing parts of the coal. Also the mineral matter in a given particle will depend
potential for liberating the inorganic material on the composition of that particle alone and,
increases as the coal is ground finer. of course, the makeup of the surrounding gases.
The pulverization of coal, then, increases the Each particle will reach a physical state (sticky,
potential for liberating inorganic particles. It sintered, or molten) related to its o,wn compo-
has been estimated by Moody and Langanls sition and reaction with surrounding gases; it
that 40 to 70 percent of the particles are pure will not be affected by the composition or phys-
coal (containing inherent mineral matter only), ical state of other particles in suspension.
20 to 40 percent occur as coal and mineral mat- Fig. 6 illustrates a hypothetical breakdown of
ter (extraneous as well as inherent), and 10 a lump of coal during pulverization. Certain

Pulverizer

Raw Coal Pulverized-Coal Particles


I I

Fig. 6. Segregation of mineral matter during grinding


COMBUSTION
Properties of Coal Ash

portions of the coal may be enriched with spe- particles, a gravity fractionation technique has
cific minerals. When the parent lump has been been developed.20
pulverized, the composition of any given parti- PROCEDURE FOR GRAVITY FRACTIONATION
cle will depend on the local composition of the -
lump and is not representative of the average The procedure requires that the coal be pul-
composition of the lump. When these particles verized to the same fineness as that during fir-
are fired in a furnace, their propensity for depo- ing; the coal particles then are separated by
sition will be a function of their individual density, using vbrious mixtures of organic liq-
physical states, aerodynamic properties, and uids having specific gravities of 1.3, 1.5, 1.7,
adhesive properties (or wettability). Ash parti- 1.9, 2.1, 2.5, and 2.9. Fewer separations might
cles with a high propensity for deposition are be adequate, but as the procedure was being
probably molten, highydensity, spherical par- developed a finer resolution of gravity frac-
ticles that do not follow gas stream-lines, and tions was found desirable. A 1-pound sample is
. that readily wet the heat-transfer surfaces they normally used and is well stirred into the 1.7
contact. ~sh-particles with a low propensity for gravity liquid using conventional separatory
deposition are probably dry (high-melting funnels. After separating the 1-pound sample
temperature), irregularly shaped particles that into the fraction that sinks and the fraction that
are more likely to follow gas stream-lines than floats in the 1.7 liquid, each fraction is filtered
to contact the furnace walls. and washed with a low-density organic sol-
As discussed earlier, iron compounds are vent. The float fraction is then taken to the next
among the materials having the lowest fusing lighter gravity liquid; the sink fraction is taken
temperatures found in coal ash.j. l 9 It is postu- to the next heavier gravity liquid as shown in
lated that particles high in iron form high- Fig. 7 . After separation, the eight fractions are
density molten spheres that have low drag air-dried at 250F and submitted for the follow-
coefficients, thereby facilitating their penetra-
tion through the gas stream to the tube wall.
Ash particles that have very high fusing tem- p E q
1.7Solutlon
peratures do not melt to form spheres; their ir-
regular shapes give higher drag coefficients
and allow them to follow gas stream-lines. 1.7 Sink (S)
Some particles having low melting tempera- 1.9Solution
tures contain carbonate compounds whose
gaseous evolution of COP generates ceno-
spheres, which, being hollow, are low in den-
sity and also follow gas stream-lines.

COAL ANALYSIS
AS A FUNCTION OF PARTICLE SIZE
2.5 Solution
In predicting behavioral tendencies of min-
eral matter during combustion, it is important
to analyze coal in the size range at which i t is
being used, because segregation of mineral
matter is a function of particle size. As each
particle is different, it would be ideal to analyze
and quantify individual particles; however,
this could prove to be difficult and costly. As a I I
practical
- alternative to analyzing individual Fig. 7. Gravity separation procedure
C O ~ V S n O N -,-
Properties of Cod Ash

ing analyses: percent ash, ash composition, ash FeSz FeS FeC03 FeO
fusibility, and, optionally, X-ray diffraction.
Specific Gravity 5.02 4.62 3.96 5.70
RESULTS OF ANALYSES Melting Temp ("F) 1382(d) 2182 1112(d) 2511
Table VI shows the analyses of three coals se-
lected for the gravity fractionation technique. Where d indicates that the compound decom-
Tables VII through IX present data for each of poses at the temperature shown. The com-
the coal gravity fractions. Compositional dif- pounds that reach the walls control the type of
ferences among the gravity fractions are deposit formed. The reactions below illustrate
thought to represent the most important data this point: --'

obtaked; fusibility temperatures of ash con-


tained in the gravity fractions would be con- initial
FeS2 (c) + 0: FeS(1) + SOz(g)
trolled by composition, for instance. Results
here primarily compare composition and be-
havior of the ash deposit. initial
FeC03 (c) reaction FeO(c, 1) + COz(g1
SLAGGING INFLUENCED BY IRON CONTENT OF ASH
where c = crystalline, g = gaseous, and 1= liquid
The role of iron is one of the more important
(10)
factors in assessing slagging potential. Fre-
quently, investigators use the total iron con-
centration in a coal ash to iissess the slagging Table VI. ASTM Properties
potential: however, this iron value could be of Test Coals
misleading as it does not account for distribu- Coal* A 'B C
-
tion of iron compounds in the coal matrix. In - - -

ASTM RANK hvA hvC SubbitC


addition to the importance of the distribution
of mineral matter within the coal matrix, the Proximate Analysis
type of minerals also plays a role in the ash de- Moisture 0.7 2.7 10.2
position process. For example, iron is fre- Volatile Matter 32.3 41.? 31.5
quently present as pyrites (FeS2) and carbo- Fixed Carbon 54.4 46.4 42.8
nates (FeC03)andlor as an impurity in calcite Ash 12.6 9.2 11.9
and dolomite, and less frequently as prochlor-
Fusibility Temperatures ("F)
ite (Fe2Mg2Al2SiZOl1), hornblende (CaFe3Si,
0 1 2 ) , hematite (Fe203),and others.21 Pyrites
IT 2430 2080 2130
will more likely exist as discrete particles ST 2510 2140 2170
within the heavier gravity coal fractions HT 2560 2170 2210
FT 2660 2300 2310
whereas carbonates are more likely to be dis-
seminated throughout the coal matrix and not Ash Composition
show a concentration with gravity fraction- SiOz
ation. The occurrence of these and other iron- A1203
containing minerals and their degree of segre- TiOz
gation in the coal matrix are functions of Fe203
coalification. CaO
Initial stages of the reaction of mineral matter MgO
in the flame can influence ash deposition. Na
Physical differences (such as density and-size) KzO
and, more importantly, melting temperatures PzOs
(and thus shapes of particles), are determined SO3
by the products of transient reactions in the *Reporting Basis: As-fired (pulverized)
flame, depending on the type of mineral:
COMBUSTION
Properties of Coal Ash

Table VII. Gravity Separations-Coal A


Gravity Fraction: - 1.3F 1.3 X1.5 1.5 x 1.7 1.7 X1.9 1.9 X 2.1 2.1 X2.5 2.5 X 2.9 2.9s
Wt%of Coal - . 11.32 56.!32 9.79 13.33 1.08 2.05 4.05 1.46
% Ash 2.3 7.4 20.4 14.6 51.1 79.1 88.2 71.0

Fusibility Temperatures ("F)


IT 2420 2700f 2700+ 2700f 2520 7 2320 2420 2010
ST 2520 2700f 2700+ 2700+ 2670 2400 2510 2040
HT 2690 2700f 2700f 2700f 2700+ 2470 2660 2070
FT 2700+ 2700f 2700f 2700+ 2700+ 2610 2700+ 2130

Ash Composition
SiOp
Alp03
TiO,
FerOR
CaO
blg0
NazO
K20
so3

Table VIII. Gravity Separations-Coal B


GravityFraction: 1.3F * 1.3 x 1.5 1.5 X 1.7 1.7 X 1.9 1.9 X 2.1 2.1 X2.5 2.5 X 2.9 2.9s
Wt%of Coal 0.13 45.45 45.52 3.87 2.83 1.20 0.44 , 0.56
% Ash 1.0 3.2 6.9 32.5 41.3 53.4 78.7 64.3

Fusibility Temperatures ("F)


IT 2030 2150 1950 1900 1930 2050 2020
ST 2110 2240 2060 1950 1960 2100 2040
HT 2230 2420 2150 1970 2010 2150 2050
FT . 24 70 2500 2230 2140 2150 2210 2210
--
Ash Composition
Si0, 55.1 57.7 50.1 44.4 39.3 22.4 12.7
A1?03 19.0 21.5 15.2 13.3 11.8 6.8 4.3
TiO, 2.1 1.2 1.0 0.6 0.6 0.4 0.5
Fe,03 13.2 13.5 24.9 30.5 26.0 22.0 57.3
CaO 2.3 1.9 1.7 3.7 9.5 20.1 9.7
MgO 1.1 1.2 0.9 0.7 0.5 0.3 0.2
NaZO 0.5 0.4 0.4 0.3 0.3 0.3 0.3
K20 il.1 2.2 1.8 1.4 1.1 0.4 0.3
so3 0.6 0.3 0.7 2.7 9.3 26.1 12.3
P20i < 0.1 < 0.1 ... ... ... ... < 0.1

"Insufficient sample
COMBUSTION
Properties of Coal Ash

The first reaction, the oxidation of iron pyrite


initially to pyrrhotite and SO2, is one of the FeO(1) + Si02(c,1) + FeSi03(c, 1)
(melting temp 2095F)
more significant reactions the mineral matter (12B)
experiences in the combustion zone. The prod-
uct FeS forms molten spheres which, through tively high melting temperature before decom-
less drag and higher density (compared to most
posing to FeO and 02.The presence of Fe304in
other particles in the fireball) are more likely to
the deposit would contribute toward a "dry"
contact the walls of the furnace. Depending on
deposit. Reaction 12A shows the formation of
the composition of ash deposits already pres-
FeO as an intermediate product which can
ent on the furnace wall, subsequent reactions
react with silica to form a low-melting iron sili-
involving F.eS may form a material that melts at cate (shown in 12B). The presence of iron sili-
a relatively low temperature. The reactions in cate would contribute toward a molten deposit.
( l l ) , (12A) and (12B) illustrate two possible Iron compounds in the "2.9 sink" are given
products with significantly different melting special emphasis as they often contain mostly
temperatures. Reaction 11shows the formation pyrites, which can cause slagging. The bar
of magnetite (Fe,O,) which will tolerate a rela- charts depicted in Fig. 8 show that iron com-
FeS(1) + F e 2 0 3(c, 1) .+ 312 Oz(g) pounds in coal B are more uniformly distrib-
+ Fe304(c, 1) + SO2 (gl uted throughout the coal matrix than in coal C.
(11) Thus, coal C has the high potential for slagging.
This agrees with observations made in the
field; a furnace burning coal C had more slag-
ging problems than a unit burning coal B.

Table IX. Gravity Separations-Coal C


GravityFraction: 1.3F* 1.3 X1.5 1.5 X 1 . 7 1.7X1.9 1.9X2.1 2.1 X2.5 2.5 X 2 . 9 2.9s
Wt% of Coal 0.2 62.76 32.28 1.56 1.09 0.62 0.45 1.05
%Ash 6.1 6.4 21.8 39.9 82.6 84.0 68.3
-- -

Fusibility Temperatures r F )
IT 2230 2260 2210 2310 2180 2350 2210
ST 2290 2370 2340 2380 2230 2440 2250
HT 2310 2390 2400 2430 2280 2490 2380
FT 2340 2420 2630 2550 2420 2530 ' 2530

Ash Composition
SiOz 41.1 43.7 54.5 53.4 51.0 37.0 6.8
A1203 18.5 24.2 25.7 20.7 10.3 3.0 0.7
Ti0 0.8 0.8 0.6 0.8 0.4 0.3 0.3
Fez03 3.2 2.0 7.1 5.9 3.5 3.7 79.0
CaO 19.6 16.1 7.0 8.2 11.9 22.8 3.9
MgO 5.1 4.3 1.4 1.0 0.6 0.8 0.3
Na 0.3 0.5 0.3 0.2 0.2 0.2 0.2
K20 0.3 0.3 0.4 0.2 0.4 0.4 - -0.2
so3 9.5 7.7 2.7 6.5 9.6 11.0 6.2
p205 < 0.1 < 0.1 < 0.1 < 0.1 0.2 0.3 0.2

*Insufficientsample
COMBUSTION
Properties of Coal Ash

Table X shows that the degree of segregation


of iron compounds within the coal matrix has Table X. Total lron Compared
no bearing on the total percentage of iron in the with Segregated lron
raw coal. If the coals are ranked solely by iron -

90Iron in Total % Iron in


content, there is a significant difference be- Coal Entire Coal Ash 2.9 Sink Fraction
tween the orders of ranking, influenced by
measurements of total or segregated iron.
The gravity fractionation technique has been
used to estimate the slagging potential of a
wide variety of coals. Table XI is a summary of
tests on sixteen U.S. coals, listing them in order fraction) varying between 74 to 79 percent. The
from severe to low potential.22 medium to high iron coals that exhibited lower
The slagging potential was established based (but still high) slagging potentials had less seg-
on the potential of a fuel to form molten ash regated iron, varying between 57 to 60 percent.
deposits that would be uncontrollable by con- The wide applicability of this test is indicated
ventional steam or air sootblowing. An exam- by the inclusion of several Western coals.
ination of the iron in the ash (expressed as Correlation of slagging potential with segre-
percent Fe,O,) indicates poor correlation with gated iron content (from gravity fractionation)
slagging potential. Several coals with low to is shown in Figure 9. This relationship has a
moderate (4 to 9 percent) iron contents (coals 2, very high level of confidence for fuels that ex-
5, 6) exhibit severe slagging potential. Several hibit 50 percent or more Fe,O, in the ash of the
coals with medium to high (13 to 16 percent) 2.9 sink fraction. In these cases the impact of
iron contents (coals 10, 11, 1 2 ) exhibit less se- segregated, reduced iron plays a major role in
vere, although still high, slagging potentials. slagging. Correlation of slagging potential with
Examination of the ash fusion temperatures this segregated iron has a much higher confi-
also reveals poor correlation. dence level than correlation with iron in the ash.
An examination of the gravity fractionation
data, however, shows excellent correlation with CORROSION BY FUEL ASH
slagging potential. The iron in the ash of the During normal operation of utility boilers,
2.9 sink fraction correlates very well with slag- metal wastage has occurred primarily (Fig. 10)
ging potential. The 2.9 sink gravity fraction
provides an excellent indication of segregated, on waterwalls near the firing zone
reduced (largely pyrite) iron. The low- to mod- in the high-temperature superheater and re-
erate-iron coals that exhibited severe slagging heater sections
potentials had high amounts of segregated iron in the low-temperature gas passes and air
(expressed as percent Fe,O, in ash of 2.9 sink heaters.

Fig. 8. lron content of various gravity fractions, coal B vs coal C

3-21
COUDUSTION
ProperUes of C w l Ash
-
- - - - - - - --

Table XI. Ash Slagging Potential of U.S. Coals as a Function of Iron in 2.9
Sink Fraction
-

Ash Ash Fusibility Temps. Fe,O, in FsO, in Ash


Coal Geographical Content, (Red. Atm.), OIO Ash, 2.9 Sink Fraction, Slagging
Coal Rank Region O
h I.D. S.T. ET. Oh O/o Potential
-
1 Hvb Midwest 13.0 2010 2100 2390 22.7 85 9.7 Severe
2 Sub Montana 11.7 2040 2120 2310 8.2 75 9.5 Severe
3 Mvb Penn. 16.8 2110 2350 2640 19.0 79 9.2 Severe
4 Hvb W. Kentucky 13.5 1980 2060 2270 27.2 78 8.8 Severe
5 Sub Montana 11.0 2130 2170 2310 8.9 79 8.7 Severe
6 Hvb Illinois 7.7 2330 2440 2570 4.0 74 8.4 Severe
7 Hvb Midwest 13.4 1940 2050 2250 22.9 72 8.3 Severe
8 Hvb Ohio 15.4 1970 2050 2370 22.6 62 6.6 High
9 Hvb Penn. 17.1 2310 2530 2700 9.5 59 6.5 High
10 Hvb Illinois 12.3 2050 2050 2140 13.0 59 6.5 High
11 Hvb hnn. 16.6 2360 2460 2700 12.7 60 6.3 High
12 Hvb Illinois 10.5 2080 2140 2300 15.9 57 6.1 High
13 Hvb Penn. 16.6 2570 2700 2700 9.8 58 5.2 High
14 Hvb Ky. & Tenn. 15.7 2700 2700 2700 4.2 50 4.5 Moderate
15 Hvb Arizona 13.3 2570 2700 2700 5.8 43 3.1 Moderate
16 Hvb Virginia 13.9 2350 2550 2700 8.3 40 1.4 Low

7
'I 1
I High-Temperature Corrosion I

Waterwall

Segregated Iron Compounds -


Presented as % Fez 03
in Ash of 2.0 Specific Gravity
Sink Fraction

Fig. 9: Slagging potential vs percent iron in 2.9


specific gravity sink fraction (Numbers in paren- Fig. 10. Steam-generator side elevation showing
theses correspond to coal numbers in Table XI ) areas where wastage has occurred
I
COMBUSTION
Properties of Coal Ash

To reduce failures in these areas, C-E has estab- sified as noncorrosive, however, temperature
lished the underlying causes of' major types of does not appear to be an important variable
corrosion and has developed practical proce- with regard to corrosion. If the coals are non-
dures for the control of waterwall and low- corrosive, there nee$ not be a greater corrosion
temperature wastage. concern as steam temperatures are increased
In recent years the most common tempera- above 1005F.
ture for the main steam and reheat on larger 3. The molten ash produced by corrosive coals
steam-generating units has been 1005F.As are- is highly aggres3ive and corrosion is not easily
sult, fundamental studies of high-temperature prevented.
corrosion begun in the 1960's have been dis- a. All poterltially viable pressure-part mate-
continued. Except for some very promising rials corrode at unacceptable rates. Currently,
work in identifying the corrosive constitu- no tube material has an adequate high-tem-
ents in c0als,~3little new information concern- perature strength to resist corrosion if the coal
ing high-temperature coal ash corrosion is ash is corrosive.
available.
b. Various tube coatings have been tried. Elec-
CONCLUSIONS FROM SERVICE troplated chromium has proven effective in
EXPERIENCE OF COAL-FIRED UNITS preventing corrosion, but it is an expensive so-
Although the U.S. utility industry has, in lution with an indeterminate adherence life.
general, abandoned the 1050F and higher Bi-metal tubes with an outer corrosion-re-
steam temperatures, there are a number of sistant clad high in chromium, such as alloy IN
steam generators operating at those tempera- 671 (50 Cr-50 Ni), show promise of having
tures from which the following has been adequate corrosion resistance, but the cost of
established: such tubing is high. In addition, these alloying
1. All coals do not produce an ash that is "cor- elements are expected to be in critically short
rosive." Only a small percentage of coal-fired supply in the future. Other less expensive
units experienced serious corrosion requiring corrosion-resistant coatings have been tried
major operating or maintenance corrections. without success.
Although the percentage is small, the actual The high-temperature corrosion that did
numbers of units that experienced serious occur was a liquid-phase coal-ash attack under
corrosion problems were substantial, and the tightly bonded deposits that was observed
concern and attention given to the coal-ash when surface metal temperatures exceeded
corrosion problem are certainly warranted. But 1100F. This attack affected superheaters and
it is important to know that many coal-fired reheaters made of austenitic (stainless) and
units operate at steam temperatures of 1050F ferritic stee1.23-39
with essentially no corrosion, or at acceptably
low corrosion rates. CONCLUSIONS FROM RESEARCH
ON COAL-ASH CORROSION
2. For coals that are "corrosive," metal tem-
perature is an important corrosion-rate vari- Research programs have attempted to deter-
able. As surface metal temperatures increase to mine causes and suggest remedies for this type
about 1200F, corrosion rates increase signifi- of wastage. Both austenitic (stainless) and fer-
cantly. A unit delivering steam at temperatures ritic steel are subject to this wastage, which
of 1050F or higher will have a greater corro- takes place under tightly bonded deposits.
sion problem than a 1005F steam unit if While this excessive deposit-type wastage of
the coal is corrosive. The corrosion rates will ferritic alloys increases with increasing tem-
be higher, and the amount of material perature, wastage of austenitic alloys is charac-
undergoing corrosion will be significantly terized as a function of temperature by the
increased. For the types of coal that can be clas- skewed "bell-shaped" curve shown in Fig. 11.
COmuSnOW
Properties of Corl Ash
-
Careful inspection at various temperatures re- posits, as a result of selective deposition, than
veals a thin white or yellow layer next to the in the coal ash or flyash from which these com-
tube surface. This layer, which is molten within pounds originate.
the 1000 to 1300F temperature range, con- An important explanation advanced by early
tains a high concentration of alkali and sulfur investigators is that the initial deposits may be
(Fig. 12). a powderlike material containing alkalies and
Simultaneous field and laboratory investiga- iron oxide which react with sulfur trioxide to
tions, including chemical and X-ray diffraction form alkali-iron-trisulfates.40 Concentration of
analyses, have shown that complex alkali-iron- alkalies on the tube surface may also occur by
trisulfates are major constituents of the white thermal migration of molten material through
inner layers associated with wastage on both the deposits to the tube surface.28
superheater and reheater tubes and on corro- On the basis of the selective deposition ob-
sion probes, as well as in controlled laboratory served, it was felt that individual particles of
wastage experiments. By means of laboratory flyash vary in composition and, therefore, have
weight-loss tests, the bell-shaped corrosion different fusion temperatures. Some of the par-
curve has been reproduced under the same con- ticles that are molten or semimolten at rela-
ditions needed for synthesis of the complex sul- tively low temperatures continue to stick to the
fate.28 As noted earlier, this same complex tubes. Sodium and potassium compounds re-
sulfate was formed as a byproduct of waterwall leased during the combustion process in a form
wastage.a.33 capable of reaction with SO3 in the flue gas,
With the principal corrosive defined, efforts may condense or deposit on the tubes as the ini-
turned toward establishing the mechanism of tial layer. This explains the formation of
complex sulfate formation to assist in recom- bonded deposits in regions where the gas
mendation of adequate protective measures. It temperature is significantly lower than the fu-
is- significant that the concentration of com- sion temperature of the total coal ash.
pounds thought to be responsible for corrosion Fig. 11 also shows a comparison of the
is considerably greater in probe and tube de- equilibrium curves and the "bell-shaped"
wastage curve for austenitic stainless steel. It
has been suggested that the potassiumlsodium
ratio in the coal ash or tube deposit is signifi-
-
--- Dry cant. The molar ratio of alkalies determines the
........Molten
Sticky temperature range over which the complex sul-

Flue-Gas Flue-Gas
riable Layer Direction

1025OF Isotherm

1"
Loosely Molten
Bonded White
Layer Layer
850 9 e m e u r e , 5 0 1250
. -.
1050FSteam
A

Fig. 1 7 . Physical state of complex alkali-iron-


trisulfates as a function of temperature and the Fig. 72. Effect of steam temperature
corrosion of austenitic alloys on deposit structure
COMBUSTION
Propertiesof CoalAsh

fates are molten. The equilibrium concentra- tacks the oxide to form complex sulfate at a
tion of sodium-iron-trisulfate was not molten higher rate than in the case of the dry reaction.
from 1150Fto 1275F. The greatest fluid range The melting point of a mixed alkali pyrosul-
appears to be the 1:1 molar sodiumlpotassium fate (K,.5Nao.5S,O,) is 535F when SO, is above
ratio. This corresponds to the 1030" to 1275F 7 ppm. The low-melting pyrosulfates, as well
region where corrosion was observed. This is to as the complex sulfates, are considered pri-
be expected because a molten corrosive is gen- mary agents in superheater corrosion, as was
erally more reactive than its solid counterpart. previously notr3d.
Consequently, an alkaline molar ratio of about 5 . The complex sulfate in the molten phase
1:l in a deposit is corrosive over a wider tem- then reacts with the tube metal:
perature range than any other combination be-
cause of the greater range of fluidity of the 2(K3or Na,) Fe(S04), + 6Fe -+

complex sulfate. ' ,I,FeS + 3/,Fe30, +


The roles of the various compounds neces- Fe,03 + 3(K2or Na,) SO, + 3/,S02
sary to forma corrosive deposit are placed in
proper perspective by the equilibrium curve. The reaction products shown in item 5 above
The steps that influence formation and growth tend to slow down the corrosion rate, but if the
of deposits from combustion products of coal deposit spalls, the reaction begins anew. The
may be summarized as follows: rate of spalling, then, affects the overall rate of
1. During combustion, pyrite (FeS,) and or- corrosion.
ganic sulfu'r react with oxygen:
PREDICTION OF COAL-ASH CORROSlVlTY
ZFeS, + 5l/2 0, + Fe,O, + 4S02 Based on an understanding of the corrosion
RS (organic sulfide) + C), -t SO2 process outlined above, work has been done to
SO, + %O, -, SO, quantify the effects of specific coal-ash con-
stituents on high-temperature ~ o r r o s i o n . ~ ~ * ~ 2
2 . In the high flame temperature, the Na and Certain relationships were developed be-
K in the clays and shales react to form Na,O tween coal-ash constituents and the degree to
and K,O. which they affect corrosion rates. The study
3. The NarO and K20 then react with SO, ei- has shown that the alkalies, alkaline earths,
ther in the gas stream or after deposition on iron, and sulfur are the most significant
the tube: constituents relative to high-temperature cor-
rosion. It is significant that the alkali concen-
tration had been measured by an acid leaching
(Na, or K2)0 + SO, -+ (Na, or K2)SO,
process. Such a procedure gives a better meas-
ure of the simpler forms of sodium and potas-
sium than total alkali measurements. These
4. The alkali sulfates, iron oxjde, and SO3then
simpler forms of the alkalies are thought to be
react to form the complex sulfate: more available for reaction in forming alkali-
iron-trisulfate, K, or Na, Fe(SO,),, the species
directly responsible for tube wastage according
to previous investigation by C-E and others.
Because the alkalies are generally the least
When the tube deposit contains a sufficiently plentiful of the four constituents mentioned,
high potassium-sulfatelsodi~~m-sulfateratio, they are usually the most sensitive corrosion
formation of liquid pyrosulfate could occur. indicators.
SO, reacts directly with the alkali-sulfate mix- The alkaline-earth materials are important as
ture forming pyrosulfate, which, in turn, at- they may preferentially retain the alkalies as
COMBUSTION
Propertiesof Coal Ash
-
sulfates or double salts of the type K2Ca2 urement approach is a simple and accurate way
(SO,),,thus preventing formation of the ag- of assessing the corrosive potential of coal ash.
gressive compound K3Fe(S04)3.43
METHODS OF MINIMIZING THE
SHORT-TERM PROBES AS CORROSION INDICATORS CORROSIVE POTENTIAL OF COAL ASH
During the study noted, probes were inserted Addition or removal of certain constituents
for periods of five minutes for purposes of may modify a potentially corrosive coal. The
measuring the acid-soluble sodium and potas- entire operating system at the supplier facility
sium during each test firing.23 These probes should be examined from the seam face, where
were inserted during tests in which raw coals mining is begun, to the point of loading for
and prepared coals were burned as well as dur- shipment. These operations may be summar-
ing tests in which additives were used. Acid- ized as follows:
soluble sodium and potassium values were 1. Mining: the coal is removed from the
expressed as a ratio and plotted against meas- ground by one of several mining methods and
ured corrosion rate and they showed a remark- transported from the mine.
ably good correlation (Fig. 13). It was noted 2 . Coal preparation: the run-of-mine (raw) coal
that the acid-soluble Na201K20ratio measured may now be processed by any combination of
from probe deposits is probably a closer ap- many preparation procedures.
proximation of the relative concentration of
3. Coal additives and blending: additives or
sodium and potassium-iron-trisulfate than that
other coals may be blended with the original
measured from the coal, for the following
coal prior to shipment.
reason:
The many physical and chemical phenom- MINING
ena that cause changes in the coal constituents Analysis of channel samples of coal removed
during combustion have already taken place from a seam enclosed on two sides by "barren"
when the resultant probe deposits are meas- material showed that the corrosion-affecting
ured for sodium and potassium content. There- minerals, as well as other mineral matter,
fore, an acid-soluble measure of the alkalies in originated primarily from the roof, floor, or
the deposit rather than in the coal would au- partings in the seam.23 Therefore, the corro-
tomatically consider the effects of combustion siveness of a coal may be reduced by mining so
on the mineral matter in the coal. that the concentration of alkaline-earth mate-
This short-term acid-soluble-alkalies meas- rials is increased with respect to the alkalies.
This can be accomplished by inclusion or ex-
clusion of seam roof material, floor material,
12-
and material contained in partings.
10 -
COAL PREPARATION
8-
The procedures used to prepare coals for
6- market should be examined. The results of
bench-scale chemical and physical tests
4- revealed that the individual chemical con-
2- I I
stituents of coal mineral matter often concen-
I I trate in specific size andlor weight fractions of
0 1 2 3 4 the coal. Thus,-preparation practices which
Acid Soluble Na201K20 Molar Ratio
(5Min Probe Deposits) employ sizing and gravity concentrating tech-
niques can be used to alter the chemical
Fig. 13. Acid soluble Na20IK20 molar ratio composition of the coal product. Because
vs observed corrosion rate high-temperature corrosion can be related to
COMBUSTION
Properties of Coal Ash

coal mineral-matter properties, it is possible to 'may take several paths. Chloride naturally oc-
reduce corrosive potential of many coals curs in coal as an inorganic material and may be
through the judicious application of con- carried over with the flyash or released by
ventional coal-preparation methods. In one strong sulfur acid as HC1. It can also be vol-
case, the corrosiveness of thecoal was reduced atilized as NaC1. In addition, chloride can enter
from 10.2 mglcmz-300 hr to 2.9 mglcmz-300 hr with refuse in either an organic or inorganic
because of the benefits derived from a benefici- form. The resulting chloride compounds usu-
ation process.23 ally are concentrated on cooled tube surfaces
where additional reactions may occur.
COAL ADDITIVES AND BLENDING
It is thought that two major adverse mech-
Adding materials such as dolomite and lime- anisms are involved in the potential increase in
stone, or blending two or more coals, can coun- corrosion rate in incinerators andlor fossil fuel-
teract the corrosive nature of a coal. fired boilers in the presence of chloride. One in-
The use of additives results in the preferen- volves formation of eutectics or complexes
tial formation of sulfates or double salts of the resulting in a lowering of .the melting point of
type K,Ca,(SO,j,. Additives can also have bene- deposits. This phenomenon is of particular
ficial effects in reducing problems from slag- concern in waterwall wastage where the tem-
ging and fouling. Tests have showed that, in perature of molten salts would increase.
most cases, ash deposits become more friable The second mechanism, probably of greater
when an additive is used and deposits become concern in the superheater, involves the reac-
easier to remove.23 tion of gas-phase sulfuric acid with deposit
chloride to release HC1 near the heated tube
CHLORIDE AS A FACTOR IN CORROSION
surface. Subsequent reaction may involve step-
The research establishing the mechanism of wise formation of volatile ferric chloride 46*
the liquid-phase-deposit high-temperature cor- andlor unstable chloride or oxychlorides of
rosion has not shown any significant corrosion other alloy components.
at the chloride levels of 0.1 to 0.2 percent nor- Heat-transfer surfaces installed in inciner-
mally encountered in coal firing.44 ators in both Europe and the U.S. have exces-
Investigations at C-E showed that the probe sive corrosion rates.48 It has been judged that
corrosion rate for clean coal increased by a fac- combinations of sulfur, chlorine, lead, tin and
tor of 3.3 when firing raw and clean coals from zinc have been the corrosive agents. In these
the same mine source. In this case, the coal had studies, where raw unprepared refuse is fired,
been cleaned by a gravity separation in carbon it has been thought that the concentration 6f
tetrachloride. Therefore, the residual chloride lead, tin, and zinc deposits results in a lower-
in the cleaned coal was 1.3 percent as opposed ing of the deposit melting point with an accel-
to a 0.05-percent level in the raw coal. This eration of liquid-phase corrosion.
corrosion rate was confirmed by subsequent Battelle researchers have conducted investi-
testing.23 gations that show opposing effects of chlorine
Chloride concentrations in American coals and sulfur in refuse.49-5O An increase in chlo-
range from 0 to 0.6 percent while coals from the rine increases the corrosion rates of low-alloy
United Kingdom peak at 0.8 percent. The 0.6 steels while an increase of sulfur decreases the
percent high for U.S. chloride levels is some- corrosion rates of all the steels investigated.
what misleading in that the majority of They reported that the major contribution to
U.S. coals have chloride levels less than 0.2 the corrosion reaction is in the type of com-
percent. Because of this, chlorine thus far has pounds that are deposited on the corrosion
not been implicated by U.S. investigators as a probe. Their investigation confirms the impor-
major contributing factor to tube wastage.45 tance of the chloride reaction as reported by
The role of chloride in increased corrosion other investigators of the corrosion process.
ConmnoN
Properties of Coal Ash
-
mentioned as participating in such corrosion.
CORROSION PROBLEMS Both melting and liquid temperatures on
heating and cooling have been determined for
FROM OIL ASH several sodium-vanadium compounds and
Although this chapter focuses primarily on sodium sulfate.51.s29 53 The data in Table XI11
the physical and chemical properties of coal show differences between the two liquidus
ash as they relate to slagging and fouling of curves for vanadium compounds, but not
boiler surfaces, fuel oil can also cause problems sodium sulfate. These differences are consid-
of corrosion. ered to be results of the absorption and evolu-
Burning residual fuel oil in utility steam gen- tion of 0xygen.b~the complexes when heated
erators has not resulted in wastage of waterwall to the melting point or cooled to the solidifica-
tubes. The principal wastage problems associ- tion point. These temperature differences
ated with boilers firing high-sulfur oils are (a) could be of importance both to the formation
high-temperature corrosion of superheater 2nd of deposits and subsequent high-temperature
reheater tubes by low-melting-ash deposits, corrosion by such deposits. Sulfur trioxide
and (b) low-temperature corrosion of air heatel; and nascent oxygen have also been suggested
ducts, and dust-collector equipment by con- as corrodents.
densed sulfuric acid in the flue gas. A review of the work on this subject results in
Analyses of typical residual oil ash as re- a curve relating metal wastage to the phase dia-
corded in Table XI1 show that the composition gram of NaQ versus V205.54 Fig. 14 plots the
of oil ash varies widely, and indicate that many results for an iron-base alloy. It can be seen that
elements may be found in the ash. However, the the greatest wastage occurs at a Na201V205
bulk of the ash contains compounds of vana- ratio of about 1:5. Molten-temperature range of
dium, iron, nickel, sulfur, and alkali metals. this ratio is 1150" to 1200F. However, as was
The compounds of particular interest are those noted previously, eutectics occur at iempera-
of vanadium, sodium, and sulfur which are as- tures considerably lower; metal wastage would
sociated with deposit formation and acceler- be possible at lower temperatures if the corre-
ated corrosion at high temperatures. The ash sponding ratio of Na201V205is present. In ac-
content of heavy-residual oil varies consider-
ably, but is usually not over 0.1 percent. Con-
centration of vanadium in the ash is related to Table XII. Analyses of Ash
the source of the crude. from Heavy Fuel Oils
Vanadium content of residual-oil ash may OO
/ by Weight
vary from a trace to 30 percent or more. Similar Mid-Cont. Texas Iran Venezuela
variations occur insodium content. Sulfur con-
SiOn 31.7 1.6 12.1 2.4

I
tents in oil have been reported from 0.7 to more
than 5 percent. Fe203
AI2O3 31.8 8.9 18.1 18.4
HIGH-TEMPERATURECORROSION TiO?
BY OIL ASH CaO 12.6 5.3 12.7 2.9
MgO 4.2
Opinion varies considerably on the exact MnO 0.4
mechanism of oil-ash corrosion, but most in- V20j TR
vestigators agree that accelerated corrosion NiO 0.5
occurs by the fluxing action of molten sodium- NaPO 6.9
-
vanadium complexes on the protective oxide
scale on the tube. Various compounds con-
K2 0 ...
so3 10.8
taining different sodiumlvanadium ratios fre- Chloride ...
quently considered oxygen carriers, have been
COMBUSTION
Properties of Coal Ash

. tual practice, diluents in the ash usually raise point temperature was established in a labora-
the melting point to llOOF or higher; corro- tory i n v e ~ t i g a t i o nIn
.~~this study a direct de-
sion of metal surfaces below llOOF is not usu- termination was made of SO3in the gas stream.
ally a problem. By maintaining a specially designed condenser
Boilers operating at steam temperatures of at a temperature between the acid dew point
1005F or higher will have some superheater
and reheater tubes operating at temperatures
above 1100F and will, therefore, be subject to Table XIII. LiquidusIMelting Points
corrosion. Field measurements of superheater Sodium and Vanadium
and reheater tubes wastage have indicated cor- Oil-Ash Constituents
rosion rates of as much as 0.030 in. per year.
Many approaches have been taken to prevent Compound Melting Point Liquidus Temp Ref.
high-temperature oil-ash corrosion. These in- Heating Cooling
clude oil treatment to remove vanadium, 1220F 1165OF 51,52
sodium, and sulfur from the oi15j956 ; the use of 185 1060 52
corrosion-resistant alloys and protective coat-
, ings; low-excess air operation; and the use of
magnesium metal, magnesium oxide, or dolo-
mite additives.
LOW-TEMPERATURE CORROSION
FROM OIL 'ASH
The greater part of the sulfur released in the
combustion of fuel oil appears in the products
%ofcombustion as SOz. A small percentage is
oxidized to SO3 which, in the cooled flue gas,
reacts with water in the vapor phase to form
sulfuric acid. The formation of SO3in boilers is
a complex process which is not thoroughly un-
derstood. Three possible mechanisms have re-
ceived the most attention: (1)oxidation of SO2
by molecular oxygen, ( 2 ) oxidation of SO* in
the flame by atomic oxygen, and (3) catalytic
oxidation of SOZ.Various authors have consid-
ered these m e c h a n i s r n ~ , ~but
' - ~ extensive
~ field
tests have indicated that catalytic oxidation in
the convection pass is a major source of SO3.
If metal temperature is below the acid dew
point, the sulfuric acid condenses on and cor-
rodes it. If the gas temperature falls below the
dew point, the sulfuric acid condenses on
flyash particles which can agglomerate to form
acid smuts. It follows that low-temperature
corrosion and acid smuts will be eliminated by
maintaining both metal and gas temperatures
above the acid dew point or by the reduction of
I O/O NazO Molar
I
SO3in the flue gas. Fig. 74. Effect of Na201V20~
mixtures
The relation of SO3concentration to acid dew on oil-ash corrosion
and the water dew point, sulfuric acid is con-
densed while all other flue-gas constituents -- P. Muller
-- Taylor Dew Point Meter
A.A.
Calculated
remain in the gas phase. 0 E.S. Lisle Experimental (Partial-
Acid dew point is defined as "the temper- Pressure Measurement)
ature at which the combustion gases are
saturated with sulfuric acid" and the dew-
310 -
point/ acid concentration relationship was de- 290 -
termined using the condensation sampling
method. Fig. 15 graphically illustrates the
agreement of dew-point determination of this
type with thermodynamically calculated data,
and shows electrical dew-point meter meas-
urements. In view of the uncertainties involved
with using dew-point meters, it is preferable to I
use the condenser analytical method together 0.01 0.1 1.0 10 100
with dew-point curves to predict the tempera- SOa(H2S04) in Flue Gas, ppm
tures at which the corrosive sulfuric conden-
sate will first appear.
Fig. 15. Dew point as afunction of
Although the low-temperature sections of a
HzS04 /(SO$ concentration
boiler can be protected against acid corrosion,
and acid-smut fallout eliminated by maintain- of sulfur-trioxide in the flue gas. Firing with
ing metal and gas temperatures above the dew low excess air plus alkaline additives to reduce
point, it is readily recognized that a more posi- SO3 concentration has been done extensively
tive solution to these problems is the reduction in the United States and Europe.61

REFERENCES AND FOOTNOTES


W. A. Selvig and F. H. Gibson, "Analyses of Ash from A. F. Duzy, "Fusibility-Viscosity of Lignite-Type Ash,"
United States Coals," U. S. Bureau ofMines Bulletin 567. ASMEPaper No. 65-WAIFU-7. New York: American So-
Washington: U.S. Bureau of Mines, 1956. ciety of Mechanical Engineers, 1965.
W. A. Selvig and F. H. Gibson, "Analyses of Ash from
Coal of the United States," U.S. Bureau of Mines Techni- G. H. Gronhovd, et al., "Study of Factors Affecting Ash
cal Paper 679. Washington: U. S. Bureau of Mines, 1945. Deposition from Lignite and Other Coals." ASME Paper
No. 69-WAIC1-1. New York: American Society of
2 Elliott P. Barrett, "The Fusion, Flow, and Clinkering of Mechanical Engineers, 1969.
Coal Ash: A Survey of the Chemical Background," Chap-
ter 15 of Chemistry of Coal Utilization, Vol. I, edited by 8 W. Beckering, et al., "Examination of Coal and Coal Ash
H. H. Lowry, pp. 496-571. New York: John MTileyand by >;-RayTechniques," Technology and Use of Lignite,
Sons and London: Chapman and Hall. Ltd.. 1945. Proceedings; by James L. Elder and Wayne R. Kube. Co-
sponsored by the U.S. Bureau of Mines and the Univer-
Thomas G. Estep, Harry Seltz, and William J. Osborn, sity-of North Dakota, Grand Forks, N.D., May 1-2, 1969,
"Determination of the Effect of Oxides of Sodium, Cal- pp. 89-102. (U.S. Bureau of Mines Information Circular
cium, and Magnesium on the Ash Fusion Temperatures 8471). Washington: U.S. Bureau of Mines, 1970.
by the Use of Synthetic Coal Ash," Miningand Metallur-
gical Investigations, Carnegie Institute of Technology, 9 J. R. Partington, Textbook of Inorganic Chemistry, 6th
Mining and Metallurgical Advisory Boards, Bulletin 74, edition, p. 689. London: MacMillan Co., 1950.
1937.
G. Thiessin, C. G. Ball, and P. E. Grotts, "Coal Ash and 'OH. E. Crossley, "The Melchett Lecture for 1962: A Con-
Coal Mineral Matter," Industrial and Engineering Chem- tribution to the Development of Power Stations." Insti-
istry, 28: 335-361.1936. tute of Fuel. Journal, 36 (269): 228-239, June 1963.

P. Nicholls and W. A. Selvig, "Clinker Formation as Re- fl James V. O'Gorman and Philip L. Walker, Jr., "Mineral
lated to the Fusibility of Coal Ash," U.S. Bureau of Mines Matter Characteristics of Some American Coals," Fuel,
Bulletin 364. Washington: U. S. Bureau of Mines, 1932. 50 (2): 135-151, April 1971.
COMBUSTION
Properties of Coal Ash

12 James V. O'Gorman and Philip L. Walker, Jr., "Thermal Washington: U. S. Department of ~ n t e h o rOffice
, of Coal
Behavior of Mineral Fractions Separated from Selected Research, 1969.
American Coals,"Fuel, 52 (1): 71-79, January 1973.
24 A. C. Corey, H. A. Grabowski, and B. J. Cross, "External
1-1 1, E. Payner and W. G. Marskell, "The Distribution of Corrosion of Furnace-Wall Tubes-In. Further Data on
Mineral Matter in.P-dverized Fuel and Solid Products Sulfate Deposits and the Significance of Iron Sulfide
of Combustion," The Mechanismof C:orrosion by Fuel Deposits," Transactions of the ASME, 71: 951-963
Impurities, proceedings of the International Confer- November 1949.
ence held at the Marchwood Engineering Laboratories,
Marchwood, near Southampton, Hampshire, England, Z5 A. L. Plumley. J. Jonakin, and R. E. Vuia. "A Review Study
May 20-24, 1963, H. R. Johnson and D. J. Littler, gen- of Fireside Corrosion in Utility and Industrial Boi1ers.Pai-t
eral editors. London: Butterworths, 1963, pp. 113-136. I-How to Lower Corrosion in Boilers," Canadian Chemi-
cal Processing, 51:52, June, 1967. Based on Combustion
14 G. B. Gouldand H. L. Brunjes, "Proportions of Free Fusi- Engineering publication TIS-2775.
ble Material in Coal Ash, as an Index of Clinker and Slag A. L. Plumley, J. Jonakin, and R. E. Vuia. "A Review Study
Formation," American Institute of iMining and Metal- of Fireside Corrosion in Utility and Industrial Boilers.
lurgical Engineers Technical Publication 1175; New Part 11-M,O. Injection to Lower Boiler Corrosion," Cana-
York: American Institute of Mining and metallurgical dian Chemical Processing, 51:70, July 1967. Based on
Engineers. 1940. Combustion Engineering publication TIS-2775.
15 R. W. Borio and R. R. Narciso, Jr., "The Use of Gravity 26 J. G. Koopman, et al., "Development a n d Use of a Probe
Fractionation Techniques for Assessing Slagging and for Studying Corrosion in Superheaters and Reheaters,"
Fouling Potential of Coal Ash." Transactions of the Proceedings of the American Power Conference, 21:
ASME Journal of Engineering for Polver, 101, Series A 236-245,1959.
(4): 500-505, October 1979; also in Combustion En-
gineering publication TIS-5823; and inASME Paper No. 27 James Jonakin, G. A. Rice, and J. T. Reese, "Fireside Corn-
78-\VA,CD-3. New York: American Society of Mechani- sion of Superheater and Reheater Tubing," ASME Paper
cal Engineers, 1978. No. 59-FU-5. New York: American Society of Mechanical
Engineers, 1959.
l6 R. W. Bryers, "Influence of the Distribution of Mineral
Matter in Coal o n Fireside Ash Deposition," Transoc- 28 Wharton Nelson and Carl Cain, Jr., "Corrosion of
tions of the ASME Journal of Engineeringfor Power, 101, Superheaters and Reheaters of Pulverized-Coal-Fired
Series A(4),506-515, October 1979; also inASMEPaper Boilers," Transactions of the ASME. Journal of Engineer-
No. 78-WAICD-4. New York: American Society of ing for Power, 82, Series A: 192-204, 1960
Mechanical Engineers, 1978.
29 J. T. Reese, James Jonakin, and J. G. Koopman, "How Coal
17H. R. Hazard, et al., "Coal Mineral Matter and Furnace Properties Relate to Corrosion of HighTemperature Boiler
Slagging," Proc'eedings of the American Power Confer- Surfaces," Proceedings of the American Power Confer-
ence, 41: 610-617, 1979. Chicago: Illinois Institute of ence, 23: 391-399,1961.
Technology, 1979.
30Carl Cain, Jr. and Wharton Nelson, "Corrosion of
'8 A. H. Moody and D. D. Langan, Jr., "Fusion Characteris- Superheaters and Reheaters of Pulverized-Coal-Fired
tics of Fractionated Coal Ashes," Combustion, 5 (4): Boilers IL" Transactions of the ASME. Journal of En-
15-17. October 1933. gineering for Power. 83, Series A: 468-474, October 1961.
I9 R. W. Bryers, "The Physical and Chemical Characteris- Wharton Nelson and E. S. Lisle, "A Laboratory Evaluation
tics of Pyrites and Their Influence on Fireside Problems of Catalyst Poisons for Reducing High-Temperature W-
in Steam Generators." ASME Paper No. 75-WAICD-2. Side Corrosion and Ash Bonding in Coal-Fired Boilers,"
New York: American Society of Mec:hanical Engineers, Journal of the Institute of Fuel, 37 (284): 378-384, Sep-
1975. tember 1964.

20 See Reference 15. J2 Wharton Nelson and E. S. Lisle, "High Temperature


External Corrosion on Coal-Fired Boilers: Siliceous
21 William T. Reid, External Corrosion and Deposits; Boil- Inhibitors," Journal of the Institute of Fuel, 38 (291):
ers and Gas Turbines. New York: American Elsevier 179-186, April 1965.
Pub. Co., 1971.
J3 R. C. Corey, et al., "External Corrosion of Furnace-Wall
L'W. H. Pollock. G. J. Goetz, and E. D. Park, "Advancing the Tubes-11. Significance of Sulfate Deposits and Sulfur
Art of Boiler Design by Combining Operating Experience Trioxide in Corrosion Mechanism," Transactions of the
and Advanced Coal Evaluation Techniques," Proceedings ASME, 67: 289-302.1945.
of the American Power Conference. 45: also as Combus-
tion Engineering publication TIS-7382. "H. R. Johnson and D. J. Littler, general editors. The
Mechanism of Corrosion by Fuel Impurities, proceedings
23 R. W. Borio, et al., "The Contml of High-Temperature of the International Conference held at the Engineering
Fire-Side Corrosion in Utility Coal-Fired Boilers," U.S. Laboratories, Marchwood. near Southampton, Hamp-
Department of the Interior, Office of Cool Research, Re- shire, England. May 20-24, 1963. London: Buttenvorths,
search and Development Report No. 41, April 1969. 1963.
COM6TJsnoN
Propdies of Coal Ash

35 5.A. Goldberg, J. J. Gallagher, and A. A. Orning, "A Labo- neers. Regular Technical Conference. Rosemont. Illinois,
ratory Study of High Temperature C:orrosion on Fireside October 11-12, 1972, pp. 44-51.
Surfaces of Coal-Fired Steam Generators," Transactions
of the ASME. Journal of Engineering for Power, 90, Series 'OR. E. Sommerlad, R. W. Bryers, and J. D. Shenker, "Sys-
A: 193-212.1968. tems Evaluation of Refuse as a Low Sulfur Fuel: Part
2-Steam Generator Aspects," ASME Paper No. 71-WAI
36 M. Weintraub, S. Goldberg, and A. A. Orning, "A Study of INCR. New York: American Society of Mechanical
Sulfur Reactions in Furnace Deposits," Transoctions of Engineers, 1971.
the ASME. Journal of Engineering for Power, 83, Series A:
444-450, October 1961. 49 H. H. Krause, D. A. Vaughan, and W. K. Boyd. "Corrosion
and Deposits from Combllstion on Solid Waste. Part III-
37 P. Sedor, E. K. Diehl, and D. H. Barnhart, "External Corro-
Effects of Sulfur on Boiler Tube Metal," Transactions of
sion of Superheaters in Boilers Firing High-Alkali Coals," the ASME. Journal of Engineeringfor Power, 97 (31, Series
Transactions of the ASME. Journal of Engineering for A: 448-452. JuIy 1975. Also published as ASME Paper
Power, 82, Series A: 181-193, July, 1960. No. 74-M'AICD-5. New York: American Society of Me-
H. E. Crossley, "External Boiler Deposits," Journal of In- chanical Engineers, 1974.
stitute of Fuel, 25 (145): 221-225, September, 1952. H. H. Krause, D. A. Vaughan, and W. K. Boyd, "Corrosion
39P. H. Crumley, A. W. Fletcher, and D. S. Wikon, "The and Deposits from Combustion of Solid Wastes. Part III-
Formation of Bonded Deposits in Pulverized-Fuel-Fired Effects of Sulfur on Boiler Tube Metal;," Transactions of
Boilers." Journal of the Institute of Fuel. 28 (170): 117- the ASME. Journol of Engineeringfor Power, 97 (3), Series
120, March 1955. A:448452, July 1975.
C. H. Anderson and E. Diehl, "Bonded Fireside Deposits 51 A. T. Bouden, P. Draper, and H. Rowling, "The Problem of
in Coal-Fired Boilers; A Progress Report on Manner of Fuel Oil Ash Deposition in Open Cycle Gas Turbines,"
Formation,"AS,MEPaperNo.55-A-200. New York: Amer- Proceedings of the Institution of Mechanical Engineers,
ican Society of htechanical Engineers. 1955. Abstracted in 167: 291-300.1953.
Mechanical Engineering, 78: 271,1956. 52Norman D. Phillips and Charles L. Wagoner, "Use of
R. W. Borio and R. P. Hensel. "Coal-Ash Composition as Differential Thermal Analysis in Exploring Minimum
Related to High-Temperature Fireside Corrosion and Sul- Temperature Limits of Oi! Ash Corrosion." Corrosion, 17
fur Oxides Emission Control," Transoctions of the ASME. (8): 102-106, August 1961.
Journal of Engineering for Power, 04, Series A: 142-148,
April 1972; also in. ASME Paper No. 71-WAICD-4. New 53T. Widell and I. Juhasz, "Softening Temperature of Re-
sidual Fuel Oil Ash,"Combustion, 22 (11): 51, May 1951.
York; American Society of Mechanical Engineers 1971;
and in Combustion Engineering publication TIS-3019. 54 J. J. MacFarlane and N. Stephenson, "Communication,"
R. W. Borio, et al.,"Control of High-Temperature Metal pp. 30T-31T of article by S. H. Frederick and T. F. Eden,
Wastage in Pulverized Coal-Fired Steam Generators," "Corrosion Aspects of the Vanadium Problem in Gas Tur-
Combustion Engineering publication TIS-5055. bines,"Corrosion, 11: 19T-33T, 1955. '

a3 A. Rahmel, "Influence of Calcium and Magnesium Sul- 55 A. Voorhies. Jr., et al., "Improvement in Fuel Oil Quality,
fates on High Temperature Oxidation of Austenitic I-Demetalization of Residual Fuels 11-Desulfurization
Chrome-Nickel Steels in the Presence of Alkali Sulfates of Residual Fuels." Mechanism of Corrosion by Fuel Im-
and Sulfur Trioxides," Mechanism of Corrosion by Fuel purities, proceedings of the International Conference held
Impurities; proceedings of the International Conference at the Marchwood Engineering Laboratories, Marchwood,
held at the hlarchwood Engineering Laboratories, near Southampton, Hampshire, England, May 20-24,
Marchwood near Southhampton, Hampshire, England, 1963. H. R. Johnson and D. J. Littler, general editors. Lon-
May 20-24, 1963. H. R. Johnson and D. J. Littler, general don: Butterworths. 1963.
editors. London: Butterworths, 1963.
s6 C. J. A. Edwards, Literature Survey Primarily Covering
44 A. L. Elumley, "Incinerator Corrosion Potential," ASME Fireside Deposits and Corrosion Associated with Boiler
Incinerator Division Corrosion Symposium. New York: Superheater Tubes in Oil-Fired Naval Steam-Raising
American Society of Mechanical Engineers, 1970. Installation with Some References Also to Similar Prob-
lems in Lond-Based Installations and Gas Turbines.
A. J. B. Cutler, et al., "The Role of Chloride in Corrosion British Petroleum Research Centre, 1964.
Caused by Flue Gases and Their Deposits,"ASME Poper
No. 70 WAICD-1. New York: American Society of G. Whittingham, "The Oxidation of Sulfur Dioxide in the
Mechanical Engineers, 1970. Combustion Process," Third Symposium on Combustion,
Flame, and Explosion Phenomena, sponsored by the
46 K. Fassler, H. Leib, and H. Spaun, "Corrosion in Refuse In- Combustion Institute and held at the University of M'is-
cinerators," Mittelungen der VGB, 48 (2):126-139,1968. consin, 1949, pp. 453-459. Pittsburgh: The Combustiorj
Institute, 1971.
"R. Baum and C. H. Parker, "Incinerator Corrosion in the
Presence of Polyvinyl Chloride and Other Acid-Releasing "A. B. Hedley, "Sulfur Trioxide in Combustion Gases,"
Constituents:' Plastecology 1972. Society of Plastic Engi- Fuel Society Journal, 43:45-54,1962.
COMBUSTION
Properties of Coal Ash

59 Arthur Levy and E. L. Merryman, " S 4 Formation in HZS bustiorr, 36 (7): 12-16, January 1965.
Flames," Transactions of the ASME. Journal of Engineer-
ing for Power, 87, Series A: 116-123, January 1965. 61 J. T. Reese, J. Jonakin, and V. Z. Caracristi. "Prevention of
Ibid., 374-378. October 1965. Residual Oil Combustion Problems by Use of Low Excess
Air and Magnesium Additive," ASME Paper No. 64-
60 E. S. Lisle and J. D. Sensenbaugh, !'The Determination of PWR-3. New York: American Society of Mechanical En-
Sulfur Trioxide and Acid Dew Point in Flue Gases," Com- gineers, 1964.

BIBLIOGRAPHY
Bassa, G. and B. Bator, "The Influence of Distribution of Garner, L. J., "The Formation of Boiler Deposits from the
Minerals in Pulverized Coals with High Mineral Contents on Combustion of Victorian Brown Coals,"Journal of the Insti-
the Working Conditions of Steam Generators," The tute ofFuel, 40(314): 107-116, March 1967.
,Mechanism of Corrosion by Fuel Impurities, proceedings of Goetz, G. J., N. Y. Nsakala, and R. )\I. Borio, "Develop-
the International Conference held at the Marchwood En- ment of Method for Determining Emissivities and Absorp-
gineering Laboratories, Marchwood, near Southampton, tivities of Coal Ash Deposits," paper presented at the 1978
Hampshire, England, May 20-24,1963, H. R. Johnson and D. Winter Annual ASME Meeting, December, 1978; also as
J. Littler, general editors. London: Butterworths, 1963, pp. Combustion Engineering publication TIS-5890.
90-101.
Goetz, G. J., N. Y. Nsakala, R. L. Patel, and T. C. Lao,
Bishop, R. J. and J. A. C. Samms, "Pilot Scale Investiga- "Combustion and Gasification Characteristics of Chars
tions of the Formationof Bonded Deposits," TheMechanism from Four Commercially Significant Coals of Different
of Corrosion by Fuel Impurities, proceedings of the Inter- Rank," EPRI Report AP-2601. September 1982; condensed
national Conference held at the Marchwood Engineering version presented at EPRI's Second Coal Gasification Con-
Laboratories, Marchwood, near Southampton, Hampshire, ference, October 20-20, 1982, Palo Alto. CA.
England, May 20-24, 1963, H. R. Johnson and D. J. Littler,
general editqrs. London: Butterworths, 1963, pp. 155-172. Hale, G. L., A. A. Levasseur, A. L. Tyler and R. P. Hensel,
Boow, J., "Sodium/Ash Reactions in the Formation of "The Alkali Metals in Coal: A Study of Their Nature and
Fireside Deposits i n Pulverized-Fuel-Fired Boilers," Fuel Their Impact on Ash Fouling," paper presented at Coal
51(3):170-173,July 1972. Technology '80. Houston, TX. November 1980; also as
Combustion Engineering publication TIS-6645.
Borio, R. bV., G.J. Goetz, and A. A. Levasseur, "Slagging
and Fouling Properties of Coal Ash Deposits as Determined Hedley, 4. B., et al., "Available Mechanisms for Deposi-
in a Laboratory Test Facility," paper presented at the ASME tion from a Combustion Gas Stream," ASME Paper No. 65-
Winter Annual Meeting. December 1977; also as Combus- WAICD-4. New York: American Society of Mechanical En-
tion Engineering publication TIS-5155. gineers, 1965.
Bryers, R. W., "The Physical and Chemical Characteristics Khrustalev, B. A., "Spectral Radiation Properties of Some
of Pyrites and Their Influence on Fireside Problems in Steam Materials at High Temperatures and Their Influence on the
Generators," ASME Paper No. 75-WA CD-2. New York; Integral Absorption and Radiation Properties," Heat
American Society of Mechanical Engineers, 1975. Transfer-Soviet Research, 5(2): 60-64, MarchlApril1973.
Bryers, R. W., and T. E. Taylor, "An Examination of the Re- Krzhizhanovskii, R. E., et al., "Influence of Particle Size of
lationship Between Ash Chemistry and Ash Fusion Temp- Ash on the Structure and Effective Thermal Conductivity of
eratures in Various Coal Size and Gravity Fractions Using Loose Deposits," Thermal Engineering (translation of T ~ Q -
Polynomial Regression Analysis." Transactions of the loenergetika). 19(10j: 3&39,1972.
ASIME. Journal of Engineeringfor Power. 98, Series A: 528- Kuleshova, I. A., et al.. "Investigation of Fraction Compo-
539, October 1976. sition and Propertics of Pulverized Coal," Thermal
Burbach. H. E. and E. A. Ramspeck, "Steam Generation Engineering (translation of Teploenergetika), 17(6):33-38,
Design for High-Sodium Subbituminous Coals," presented 1970.
at ASME-IEEE-ASCE Joint Power Generation Conference. Littlejohn, R. F., "Mineral Matter and Ash Distribution
St. Louis, MO. October 4-8. 1981; also as Combustion En- in 'As-Fired' Samples of Pulverized Fuels," Journal of the
gineering publication TIS-6867. Institute of Fuel, 39(301): 59-67. February 1966.
Crossley, H. E., "External Boiler Deposits. Paper 4- Littlejohn, R. F. and J. D. Watt, "The Distribution of Min-
Special Study of AshandClinkerinIndustry."lournalof the eral Matter in Pulverized Fuel." The Mechanism of Corro-
Institute of Fuel, 25(145): 221-225, September 1952. sion by Fuel Impurities, proceedings of the International
Dundersdale, J., et al., "Studies Relating to the Behaviour Conference held at the Marchwood Engineering Labora-
of Sodium During the Combustion of Solid Fuels." The tories, Marchwood, near Southampton, Hampshire, Eng-
Mechanism of Corrosion by Fuel Impurities, proceedings of land, May 20-24.1963, H. R. Johnsonand D. J. Littler, gen-
the International Conference held at the Marchwoad En- eral editors. London: Butterworths. 1963. pp. 102-112.
gineering Laboratories, Marchwood, near Southampton, Marskell, W. G. and J. M. Miller. "Some Aspectsof Deposit
Hampshire, England. May 20-24.1963, H. R. Johnsonand D. Formation in Pilot-Scale Pulverized-Fuel-Fired Installa-
J. Littler, general editors. London: Butterworths, 1963. pp. tions." Journal of the Institute of Fuel. 29(188):380-387,
139-144. September 1956.
C3US'RON
Properties of Coal Ash

Moody, A. H. and D. D. Langan, Jr., "Fusion Characteris- Raask, E., "Reactions of Coal Impurities During Ccmbus-
tics of Fractionated Coal Ashes," Combustion, 5(4):15-17, tion and Deposition of Ash Constituents on Cooled Sur-
October 1933. faces," The Mechanism of Corrosion by Fuel Impurities,
proceedings of the International Conference held at the
Moody, A. H. and D. D. Langan. Jr., "Fusion Temperature Marchwood Engineering Laboratories, Marchwood, near
of Coal Ash as Related to Composition," Combustion, Southampton, Hampshire, England, May 20-24.1963. H. R.
6(8):13-20. February 1935. Johnson and D. J. Littler, general editors. London: Butter-
worths, 1963. pp. 145-154.
Mulcahy, M. F., et al. "FiresideDepositsand TheirEffect Regan, 1. W., "Impact of Coal Characteristics on Boiler
o,n Heat Transfer in a Pulverized-Fuel-Fired Boiler, Part I: Design:' presented at Coal Technology '82, December 7-9,
The Radiant Emittance and Effective Thermal Conduc- 1982, Houston. TX; also published as Combustion Engi-
tance of the Deposits," Journal of the Institute of Fuel. neering publication TIS-7291.
39(308):385-394, September 1966. Smith, R. A. and L. R. Glicksman, "Radiation Properties
National Research Council. Committee on Chemical Utili- of Slag," ASME Paper No. 69-WAIPWA-7. New York:
zation of Coal. Chemistry of Coal Utilization, prepared by American Society of Mechanical Engineers, 1969.
the Committee on Chemical Utilization of Coal, Division of Tufte, Philip H., et al., "Ash Fouling Potentials of West-
Chemistrv and Chemical Technolonv, -- National Research ern Subbituminous Coals Determined in a Pilot-Plant Test
Council. H. H. Lowry, chairman, Supplementary v ~ l u m e . Furnxe."Proceedings of the American Power Conference,
New York: John \Iriley and Sons, Inc., and London: Chap- 38:661-671, 1976. Chicago: Ill. Institute of Technology,
man and Hall, Ltd., 1963. 1976.
CHAPTER 4

Combustion Processes

u his chapter includes the basic equations


used to describe how fuel and air injected
into a furnace are transformed into gaseous
products of combustion. A major section is
substance which sometimes was presumed to
have the property of negative weight and
which combined with a body to render it com-
bustible. First proposed by G. E. Stahl in 1697,
devoted to the mathematical background and the phlogiston theory dominated the chemical
experiential basis for the combustion reactions thought of the 18th century. Even such a per-
in furnaces. There is a summary discussion of ceptive observer as Joseph Priestly, who in
the physical mechanisms currently used for 1774 discovered the unique power of oxygen
burning coal and other solid fossil fuels. The for supporting combustion, accepted the
material concludes with the theoretical and phlogiston theory. In the years between 1775
empirical criteria for the formation of nitrogen and 1781, Antoine L. Lavoisier substituted for
oxides during combustion, and methods for re- it the theory of oxygenation and provided ex-
ducing their emission from a furnace. perimental evidence that combustion was the
union of the substance burned with the oxygen
HISTORICAL INTRODUCTION of the atmosphere. f
In 1755 Joseph Black discovered carbon
Although from his earliest existence on earth dioxide, and in 1781Henry Cavendish demon-
man has been fascinated by fire, he did not strated the compound nature of water. At about
achieve a quantitative understanding of the this same time Lavoisier made the precise
combustion process until about the year 1880. measurements and formulated the volume and
Prior to that date, one can trace the develop- weight relationships that underlie the modern
ment of many hypotheses concerning the na- theory of combustion.
ture and properties of fire, including some that Beyond this, in 1811 Amedeo Avogadro es-
were expressed in supernatural terms of fear tablished that the number of molecules in a unit
and awe. However, even the existence of the volume under standard conditions is the same
now discredited phlogiston theory of combus- for all gases. During this same period John Dal-
tion did not prevent enterprising engineers ton enunciated the law of partial pressures, and
from designing and constructing boilers to in 1803 his study of the physical properties of
generate steam for the earliest steam engines. gases led to formulation of the atomic theory,
Phlogiston was a hypothetical mysterious including the law of combining weights. A re-
-
lated observation was made by Gay-Lussac in presence is generally detrimental because of
1808 that gases always combine in volumes the corrosive nature of its compounds.
that bear simple ratios to each other. Air, the usual source of oxygen for combus-
tion in boilers, is a mixture of oxygen, nitrogen
and small amounts of water vapor, carbon
COMBUSTION FUNDAMENTALS dioxide, argon and other elements. The com-
To the engineer concerned with boiler de- positions of dry and wet atmospheric air are
sign and performance, combustion may be given in Table I.
considered as the chemical union of the com- In an ideal situation, the combustion process
bustible of a fuel and the oxygen of the air, would occur with the exact proportions of oxy-
controlled at such a rate as to produce useful gen and a combustible that are called for in
heat energy. The principal combustible con- theory (the stoichiometric quantities). But it is
stituents are elemental carbon, hydrogen, and impracticable to operate a boiler at the theoret-
their compounds. In the combustion process, ical level of zero percent excess oxygen. In
the compounds and elements are burned to practice this condition is approached by pro-
carbon dioxide and water vapor. Small quan- viding an excess of oxygen in the form of excess
tities of sulfur are present in most fuels. Al- air from the atmosphere. The amount of excess
though sulfur is a combustible and contributes air varies with the fuel, boiler load, and the type
slightly to the heating value of the fuel, its of firing equipment.

Tabk I.~ o m ~ o s i t i o
ofnCombustion Air
Dry Atmospheric Air
The volumetric composition of dry atmospheric air given in NACA Report 1235 (Standard Atmosphere-Tables
andData for Altitudes to 65,800 feet, November 20,1952),l and the molecular weights of the gases constituting
dry air are as follows:
Volume % Mol. Wgt.
!

Nitrogen 78.09 28.016

Oxygen 20.95 32.000

Argon 0.93 39.944

Carbon dioxide 0.03 44.010

(Neon, helium, krypton, hydrogen, xenon, ozone, and radon, combined, are less than,0.003%.)
Dry air with this composition has an apparent molecular weight of 28.97 lbllb mol and a density at 32F and 14.7
psia of 28.97 + 359 = 0.0807 lblft3. The oxygen content is 23.14% by weight. The lb dry airllb oxygen
= 1 + 0.2314 = 4.32.

Wet Atmospheric Air


Wet atmospheric air is defined in this text as the above air plus 0.013 lb of water vaporllb of dry air. (Air at 8o0F,
60% relative humidity, and 14.7 psia pressure contains 1.3% water vapor by weight. See Fig. 1.)
Wet air with this amount of water vapor has an apparent molecular weight of 28.74 lbllb mol and a density at
32F and 14.7 psia of 0.0801 lblft3. 1Ae-oxygen content is 22.84% by weight. The lb wet atmospheric airllb
oxygen = 1 + 0.2284 = 4.38.
The mass of nitrogen, argon, carbon dioxide and waterllb oxygen = 77.16122.84 = 3.38 lb.
COlllBUrnON
CombustionProcersw

COMBUSTION EQUATIONS
and pressure will occupy the same volume.
For combustion calculations, however, it is This relationship is very significant. The
customary to write the combustion reaction volume will, of course,-vary numerically for
equations on the- basis of theoretical oxygen different units of weight and for different con-
only, notwithstanding the presence of excess ditions of temperature and pressure. For com-
air and nitrogen. A partial list of these combus- bustion calculations, the pound and the cubic
tion equations and the approximate heat re- foot are the units commonly used in the U.S.
leased in the reactions are given in Table 11. and, unless otherwise stated, the temperature
All combustion calculations are based on and pressure are understood to be 32F and 14.7
fundamental chemical reactions shown in psia. Thus a molecular weight of 32 Ib of oxy-
Table 11. Not only do the equations indicate gen at 32F and atmospheric pressure will have
what substances are involved in the reaction,
but they also show the molecular proportions
in which they take part.
Each molecule has a numerical value that
represents its relative weight or molecular
weight. This molecular weight is the sum of the
atomic weights of the atoms composing the
molecule. For example, carbon, C, has a
molecular ,weight of 12; oxygen, 0 2 , has a
molecular weight of 2 x 16 = 32; and carbon
dioxide, C02, has a molecular weight of
1 2 + ( 2 X 1 6 ) = 44. These molecular weights
are only relative values and may be expressed
in any units. Note that the molecular weights in
Table I1 are the whole-number values of the
main isotopes of each substance. Temp of Air (Dry Bulb)"F
It has been established that a molecular
weight of any substance in the gaseous state Fig. 1 Moisture content of dry air a s a function of
and under the same conditions of temperature dry-bulb temperature and relative humidity

f
Table 11. Combustion Equations
Heat
Molecular Release,'
Combustible Weight Reaction Btuilb

Carbon 12 C+02 + COP 14,100


Hydrogen 2 H2+0.5 O2 -t H,O 61,000
Sulfur 32 S+OZ + so2 4,000
Hydrogen sulfide 34 H2S +1.5 O2 + S 0 2 + H 2 0 7,100
Methane 16 CH,+20, -t C0,+2H20 23,900
Ethane 30 C2H6+3.50, + 2C02+3H20 22,300
Propane 44 C3H,+5 0, -t 3 C 0 2 + 4 H 2 0 ' 21,500
Butane 58 C.&Ilo+6.5 0, + 4C02 + 5H20 21,300
Pentane 72 C&-11,+802 + 5 C 0 2 + 6 H , 0 22,000
'Higher heating ~alue/lb
of combustible
the same volume as a molecular weight of 44 lb Because there are 4.32 Ibs of dry airllb ofoxy-
of carbon dioxide under the same conditions. gen, the stoichiometric combustion of 1 lb of
This volume is 359 cu ft. carbon requires 11-52 lb of dry air, or 11.68 lb of
wet air (with 1.3 percent water vapor).
CONCEPT OF THE MOLE Each equation balances; there are the same
A molecular weight expressed in pounds is number of atoms of each element and the same
called a pound mole, or simply a mole, and the weight of reacting substances on each side of
volume that it occupies is called a molal vol- the arrow but not necessarily the same number
ume. Molal volume varies with changes in of molecules, moles or volumes. Thus, one
temperature and pressure according to Boyle's atom of carbon combined with one molecule of
and Charles' laws and may be corrected to any oxygen gives only one molecule of carbon diox-
desired conditions. Volume is directly propor- ide; two moles of hydrogen plus one mole of
tional to the absolute temperature and in- oxygen yield two moles of water vapor.
versely proportional to the absolute pressure. It will be evident from a consideration of the
Because combustion processes in steam boiler mole-volume relationship that percent by vol-
furnaces usually take place at practically con- ume is numerically the same as mole percent.
stant atmospheric pressure, pressure correc- Because a mole represents a definite weight
tions are seldom necessary. as well as a definite volume, it is a means of
Returning to the combustion equation for converting analyses by weight into analyses by
carbon and oxygen and applying these con- volume and vice versa. Volumetric fractions of
cepts, it is now possible to write this reactionin the several constituents of a gas can be multi-
several ways. For purposes of molar analysis plied by their respective molecular weights,
carbon may be treated as a gas. with the sum of the products then being equal
to the apparent molecular weight of one mole of
gas. The percent by weight of each component
can then be determined. Finally, the density of
any gas at any temperature is found by dividing
the molecular weight of the gas by the molal
volume at that temperature, Fig. 2. '
1molC + l m o l O 2 = ImolCO,
(2) 700 -

IZlbC + 321bo2 =441bC02


(3)

Dividing through by 12,

V= 0.7297t + 335.65

1 Ib C + 2.67 Ib 0 2 = 3.67 Ib C 0 2
(4)

1volume C + 1volume O2 = 1 volume COz


(5)
I' Temperature,OF - -

Fig. 2 Gas density determination


Less 0, in fuel 7.46132 = W l b mol
METHODS OF COMBUSTION 0, required = 6.13 lb mol
CALCULATIONS 0, in excess air 6.13 x 0.23 = X I b mol
Two methods of combustion calculations are Total 0, required1100 Ib fuel = 7.54 lb mol
presented in this text. The first is known as the Dry air required = [(7.54 Ib mol 0,) x
mole method and is based on the chemical rela-
(loo lb mol air' 1 = 36.0 lb mo1/100 ib fuel
tionships previously explained. The second (20.95 lb mol 0,)
method uses the firing of a million Btu as a 36.0 x 28.97 = 1043 lb dry air1100 lb fuel
basis for calculation. WEIGHT OF DRY PRODUCTSOFCOMBUSTION
THE MOLE METHOD The weight of gaseous products of combus-
Table I1 gives the basic combustion reactions tion can be calculated from the volumetric
for the carbon, hydrogen, and sulfur i n coal. analysis of flue gas. Not only the weight of the
Assume a high-volatile bituminous coal of flue gas1100 lb of coal but its analysis and vol-
the following analysis, burned at 23 percent ume can be calculated from the information
excess air; perform calculations on the basis of given in the preceding example.
100 lb of as-fired fuel. The fuel analysis as fired To obtain the wet products of combustion, or
is the following total wet gas when a fuel burns completely, the
%by Weight Mole Weight weight of the fuel is added to the weight of at-
c ' 63.50 12 mospheric air supplied for its combustion. If
HZ 4.07 2 some of the fuel is ash or, if because of incom-
s 1.53 32 plete combustion, some of the fuel does not
02 7.46 32 leave the furnace with the gases, then there will
NZ 1.28 28 be less burned-out fuel in the products.
Hz0 15.00 18 The wet products of combustion in the above
Ash 7.16 example, then, are the fuel (100 lb - 7.16 Ib
HHV 11,200 Btuilb ash = 92.84 lb1100 lb) plus the air required for
The calculation of air weight for combustion combustion or (rounded) 93 + 1043 = 1136
lb1100 lb of fuel.
must be made on the basis of an oxygen balance
because oxygen is the only element common to THE MILLION-BTU METHOD
all oxidizing reactions. Oxygen contained in This method for combustion calculations is
the fuel must be deducted from the calculated based on the concept that the weight of air re-
quantity needed because it is already combined quired in the combustion of a unit weight of
with carbon, hydrogen. or other combustible any commercial fuel is more nearly propor-
constituents of the coal. tional to the unit heat value than to the unit
The molar relations are as given in Table 11: weight of the fuel. Consequently, the weights
Mol MolOp MolC02 MolHpO M0lS0p of air, dry gas, moisture, wet gas, and other
C 1 1 quantities are expressed in pounds per million
Hz 0.5 1 Btu fired.
S 1 1
In connection with this calculation method,
the following items will be discussed:
AIR FOR COMBUSTION
1. Fuel in products, F
0, for C 63.5112 = 5.29 lb mol 2. Atmospheric air for combustion, A
0, for H, (4.07 x 0.5)/2 = 1.02 Ib mol 3. Effect of unburned combustible
0, for S 1.53132 = 0.05 1b mol 4. Products of combustion, P
Total for 100 lb fuel 6.36 lb rnol 5. Moisture in the combustion air, W,
-
6. Moisture from fuel in products of combus- moisture-and-ash free-and Ad,, is in lb1106
tion, Wf Btu fired.
7. Dry gas content of combustion products, P d For air with 1.3-percent moisture by weight
(80F and 60-percent relative humidity), the
The first four items are necessary for the cal- formula becomes
culation of the gas and air quantities. Items 5 to
7 form the basis of heat balance calculations,
in either the design or testing of a steam gen-
+ 4.38 (%S)
erating unit.
FUEL IN PRODUCTS, F
11.68 (%C) + 35.03 (%H - %0/8)
HHV 1
As defined earlier, F-is that portion of the fuel
fired which appears in the gaseous products
of combustion. Because all quantities are to be Values of A,,, range from 570 lb11o6Btu for
those required for, or resulting from, the fir- pure hydrogen to above 800 lbl106Btu for cer-
ing of 1,0oO,000 Btu, ? must be calculated on . tain cokes and meta-anthracite coals, as shown

that basis. If a fuel contains no ash, F is ob- in Fig. 3 for various fuels burned in steam gen-
tained by dividing 1,000,000 by the as-fired erators. Any calculated values of wet air for
heating value of the fuel. For solid fuels where combustion differing substantially from these
ash andlor solid combustible loss must be values should lead to a cross-verification of the
considered, ultimate analysis and the observed high heat-
ing value. The analysis and HHV of the fuel
104(100 - % ash - % solid combustible loss) have to be from the same sample to avoid errors
F = fuel heat value in air and gas weight determinations.
where: EFFECTOF UNBURNEDCOMBUSTIBLE
F = lbl106Btufired
% ash = percent by weight in fuel as fired
In the combustion of solid fuels, even in
solid combustible loss = percent by weight i n
pulverized form, it is not feasible to burn the
fuel as fired available combustible completely, Thus, the
fuel heat value (HHV) = high heat value as fired,
Btullb
(6)
/ Bituminous Coal
ATMOSPHERIC AIR FOR COMBUSTION, A fl. I, ,Natural Gas
In accordance with the molar method, the
theoretical weight of dry air (zero excess) may
be calculated from the fuel analysis and the
formula:
~i~nite',
Wood
-

' 1
,Refinery Gas

Bagasse
650

Atry =
Blast-Furnace Gas
+ 34.57 (%H - 90018) + 4.32 (%S)
[11.52 (%C)
HHV 1 550 - Hydrogen-'

(7)
- --
Increasing Hydrogen Content

Fig. 3 Combustion-air requirements for various


I
in which numerator and denominator are on fuels at zero excess-air-a range of values as an
the same basis-as-fired, moisture-free, or approximate function of hydrogencontent

A!!!!
COMBUSTION
Combustion Proceues

air requirement per million Btu fired has to be will not be exact. For high-carbon, low-volatile
reduced to the air required per million Btu fuels it will be nearly exact and will result in-
burned. This is done by multiplying the com- only a w a l l error even for fuels low in fixed
bustion air A by the combustible-loss correc- carbon and high in hydr~gen.~>The error in-
tion factor C. volved by using Eq. 10 in all cases is quite
The unburned combustible loss can be ex- within the limits of accuracy of all other com-
pressed either as percent carbon heat loss or bustion calculations.
the percent combustible weight loss. These Finally, C can be expressed as a function of
are related by the expression: percent heat loss by combining the above rela-
tionships:
14,600
% Carbon heat loss = ,m x % solid comb.
wgt. loss C=1-
% carbon heat loss HHV
(9) 100 14,600

in which 14,600 is the heat value for combus-


tibles in refuse recommended by A.S.M.E. Fig. 4 is a graphical solution of this equation.
Performance Test Code, and HHV is the high PRODUCTS OF COMBUSTION, P
heating value of the as-fired fuel.
If a fuel has carbon as its only combustible The total gaseous products of combustion, P,
constituent$,the factor C equals become the sum of F and A (as corrected for
combustible loss). Thus,

1 - % solid combustible
100
weight loss

(10)

where:
If, however, all heat in the fuel does not come P = total gaseous products of combustion,
from carbon alone (so that the air is not strictly I b l l ~ ~ Bfired
tu
proportional to carbon burned), the factor C F = fuel fired exclusive of ash or solid carbon
loss, lbllOBBtufired
A = atmospheric air consumed, 1bllOQtu fired
Carbon Heat Loss,%
C = combustible loss correction factor

MOISTURE IN COMBUSTION AIR, Wg

For heat-balance calculations, the moisture


in air will be 1.3 percent of the air weightl106
Btu, or W, = 0.013A, for ambient conditions of
80F and 60-percent relative humidity. For air
at a higher or lower temperature or relative
humidity, the moisture content will be as
shown i n Fig. 1;air per million Btu, A, and W,
must be adjusted appropriately.
4,0006,0008,00010,00012,00014,000
MOISTURE FROM FUEL, Wf
HHV of Fuel, As Fired
This item is separately reported both in an
Fig. 4 Graphical solution of equation 11
--
ASME Performance Test ~ i d e sheat balance
--
and in a predicted heat balance. In the case of the significant combustion calculations are
some fuels (such as natural and refinery gases), included to reinforce the above information.
the heat loss because of this moisture may be In the event that an ultimate analysis of a
the largest single item in the heat balance. Wf given coal is not available, the curves and data
includes the combined surface and inherent in Appendix C can be used to arrive at close ap-
moisture, W,, from a fuel, plus the moisture proximate solutions.
formed by the combustion of hydrogen, Wh.We One of the principal purposes of Appendix C
will vary from zero, or a mere trace in fuel oil, to is to enable an engineer required to perform
over 115 lb11O6 Btu fired in the case of green combustion calculations to obtain a "visual
wood; Wh will vary from zero or a trace in feel" for the order of magnitude of the calcu-
lamp-black to 100 lb1106Btufired in the case of lated values. Engineering judgments about
some refinery gases. Thus, such concepts are very difficult to make based
on calculations done on electronic computing
equipment. When used in commercial problem
W, = W, + Wh, where solving, the answers obtained from computers
10'
W, = H 2 0 x -
HHV
stand alone, with no reference to physical
104
input parameters. Thus, there is a lack of the
andWh = 9 X H X- judgmental development that can be gained
HHV
(13) from using graphical devices and one's skills
may be limited to computer inputting.

W, and Wh are in lb11o6Btu fired, H 2 0 is the


percent water by weight in the as-fired fuel, H THERMOCHEMISTRY .
is the hydrogen in the fuel (percent by weight Energy is associated with the forces which
as fired) and HHV is the high heating value of bind atoms together to form a molecule. A rear-
the as-fired fuel, Btullb. rangement of the atoms to form new molecules,
DRY GAS, Pd such as occurs in a chemical reaction, entails
the liberation or absorption of energy. The
The d r ~ - g a scontent of the prod- branch of thermodynamics which deals with
ucts is used in the the dr~-gas- this subject is referred to as thermochemistry,
loss item of a boiler heat balance. Unfortunately, the working definitions regard-
The dry gas may be determined by subtract- ing this aspect of thermal analysis are often
ing the water vapor from the total products,
obscurely stated and contradictory between au-
thus,
thors. The definitions which follow are there-
P, = P - (W,, + W,) (I4) fore not universal nor subscribed to bv all au-
where thors in this field. In the.main they will rely on
Pd =dry gas, lb11o6Btu fired the authoritative treatises by Wark2, Reynolds
P =total products of combustion and Perkins3, and Van \Vylen and Sonntag4.
W, =moisture in air DEFINITIONS OF TERMS
Wf =moisture from fuel Before proceeding, it is necessary to remark
COMBUSTION CALCULATIONS here that the reference datum for chemical
BY GRAPHICAL METHODS thermodynamic tabulations is usually taken to
be 1 atm pressure and 25C (29fI0K, 77"F, or
In Appendix C , we present a convenient 537"R). This is called the standard reference
graphical system for solving the equations state and, by convention, the enthalpy of every
of this million Btu method, for coal and elemental substance (such as H2, 02,N2, Cl) is
most other power plant fuels. Examples of all defined to be zero at the standard reference
COMBUSTION
Combustion Proceases

state. We will briefly review several other defi- on whether the enthalpy of combustion tabula-
nitions concerned with the emission or con- tion is on a liquid or vapor (HzO)basis.
sumption of energy accompanying a thermo- EXOTHERMIC HEAT
chemical reaction. .- -
A chemical reaction which liberates energy
INTERNALENERGY OF REACTION
(heat) is called exothermic and is denoted by
If a chemical reaction occurs at constant vol- AHR(see heat of reaction at constant pressure).
ume and at 25C initial temperature and the The sign convention adopted for the liberated
products of reaction are returned to 25"C, then energy is negative. This sign convention is not
the energy excess (liberated) or deficit (absorp- universal (not used in all textbooks).
tion) required to meet the conditions of this Use of the negative convention invariably is
system is known as the internal energy of reac- justified by the argument that heat is removed
tion. The symbol assigned this energy is A UR. from the system in order to return it to 25C.
Heat of reaction at constant volume is an alter- The negative convention fqr exothermic reac-
nate for the internal energy of reaction. By first tions is, in fact, physically correct and can be
1awanalysis.wecanwriteforthisitemQ' = AU. justified on a more convincing basis. For
ENTHALPY OF REACTION
example, in thermochemical terms:
Hz(gas) + M 0, (gas) -Hz0 (liquid):
If a chemical reaction is initiated at 25C and A HR, 25'C = -122,970 Btullb mol
the products are returned to 25C and this pro- A HR, 25OC = - 68.137 kcallg mol
cess is carried out at constant pressure, then the a reaction which is also the HHV for the com-
energy supplied or disposed of is referred to as bustion of hydrogen. Fig. 5 demonstrates the
the enthalpy of reaction. The symbol assigned principles introduced, on the basis of the for-
this energy is AH,. Heat of reaction at constant mation of a lb-mol of H,O, where one mole of a
pressure is a n alternate term for the enthalpy of substance whose molecular weight is M is de-
reaction. Although both A URand A HRcan be fined as M unit masses of that material.5
found tabularly listed, A HRis the more com-
monly encountered as it is conveniently meas-
ured in a steady-flow device. Heat of reaction is
a short form for heat of reaction at constant
pressure, and is tabulated on a basis of Btu per
mol of fuel burned. Heating value is synony-
mous with the heat of reaction, except that it is
always taken as being positive.
ENTHALPY O F COMBUSTION

This is defined, sometimes, as the negative of


the heating value. The symbol assigned the en-
thalpy of combustion is AHc.
Hz0 (Liquid Product)
I I

If water i n the products of combustion of a 298 373


fossil fuel is taken as being condensed and low- Temperature, O K
ered in temperature to 77F at 1 atm, the con-
densation heat release hfgis added to A Hc and
this is called the higher heating value (HHV).If
the Hz0 remains as a vapor, then hfg (1050.3 Fig. 5 Exothermic enthalpy of reaction for
Btullb, at 25C) is not added to LVIcdepending formation of H,O at 1 atm, constant pressure
-

4-9 -' A!!


--
ENTHALPY OF FORMATION to the enthalpy of all stable elements at 1 atm
Although the internal energy and enthalpy of and 25"C, the enthalphy Hiof any compound at
reaction are basic quantities in the solution of the same state is simply the enthalpy of forma-
thermochemical problems, the myriad chemi- tion of that substance, or
cal reactions effectively prohibit the over-
whelming task of tabulating AUR and AHR
values. Therefore, the concept of the enthalpy
Because the chemical enthalpy of a stable ele-
of formation was introduced. Applying the first
law to a chemical reaction in a closed system at ment is always zero, by definition, the enthalpy
of any compound is composed of two parts: that
constant pressure, we write
associated with its formation from elements
and the sensible enthalpy associated with a
P(uiHi) + AHR = Z(uiHi) change of state at constant composition. The
i readants i products
sum of these two parts is ca!led the absolute en-
thalpy of a substance.
where Hi is the molar enthalpy of any product The foregoing is illustrated by the reaction
or reactant at the pressure and temperature of
the reaction, and vi again is the stoichiometric
coefficient for each, based on the balanced
chemical equation. It is clear that many sensi- As solid carbon and gaseous diatomic oxygen
ble enthalpy tables for various gases account are the stable forms of these elements at 25C
for changes in temperature at constant compo- and 1atm, their chemical enthalpies are chosen
sition, whereas the thermochemical process to be zero. The enthalpy of reaction is easily
being considered is defined in terms of con- measured experimentally for this reaction, and
stant temperature with variable composition. It it is found to be -169,290 Btutlb mol, or
follows that sensible enthalpy tables are not -94i054 kcaltg mol. These values are also the
sufficient for evaluating energy transforma- enthalpy of formation of carbon dioxide, from
tions resulting from chemical reactions. which it follows that A H,, A H,, and A Hf are
To circumvent this difficulty, the concept of related but not synonymous. This is shown
an enthalpy of formation A Hf, is introduced. somewhat more clearly by Table 111.
This is defined as the energy released or ab- The usefulness of A H, values is based on the
sorbed when a specific chemical compound, assumption that the enthalpy of any compound
such as C020rH20,is formed fromits elements. is equal, arbitrarily, to its enthalpy of formation
The reactions, again, are such that initial reac- from stable ,elements. \k may, therefore, sub-
tant temperature and final product temperature stitute A Hf values for H, values:
are the same; written symbolically

This equation is completely general for any


reaction as long as the enthalpies of formation
In this case the reactants are taken arbitrarily as for all products and reactants are measured at
the stable form of the elements at the given ini- the same temperature and pressure. This equa-
tial state. For example, the stable forms of gases tion is widely used in thermochemistry. Its
such as hydrogen, nitrogen, and oxygen at 1 principal merit is, instead of requiring tabu-
atm pressure and normal temperatures are lations of thousands of values of A HR for all
H,(g), and 02(g).On the other hand, the stable conceivable reactions of interest, it is necessary
form of carbon under these same conditions is only to tabulate A Hf values for compounds of
C(s). Because a value of zero has been assigned interest. From the knowledge of A Hf values,
applying this equation leads directly to any de- thin&; must disappear . . . that something is
sired enthalpy of reaction. a minute amount of mass. We can quite readily
We have briefly presented several different calculate a conversion constant on a per Btu
definitions or labels; however, giving something and on a per kcal basis. We write the well
a label does not necessarily constitute a satisfac- known Einstein relation as:
tory explanation. If, in addition, we literally in-
terpret the words of Van Wylen4 "The justifica-
tion of this procedure of arbitrarily assigning the
value of zero to the enthalpy of the elements at
25OC, 1atm rests on the fact that, in the absence
of nuclear reactions, the mass of each element
is conserved in a chemical reaction. No conflicts For a AE of 1Btu, C of 9.8357 x 108ftlsec,the
or ambiguities arise with this choice of reference gravitational constant of 32.174 ft-lb,/lbf secz
state, and it proves to be very convenient in and the relationship for the mechanical-
studying chemical reactions from a thermo- equivalent of heat, 1Btu = 778.16 ft-lbf('ef')
dynamic point of view", then we are in a quan-
dary regarding the origin of the energy we are (1 Btu) X 778.16 ft-lbf X
tabulating. Btu
Obviously, no one is going to abandon the
law of conservation of mass as it is far too use-
ful. On the other hand, we do not create energy
out of thin air. The problem is resolved if we
recognize that the law of conservation of mass yields 2.588 x 10-141bJBtu
is a near exact approximation which has been
replaced by the law of conservation of mass- Using the more recent value of 777.649 for J
energy. There is nothing in Einstein's equation (see ref 6), we get 2.586 x 10.'~
lb,/Btu; on a
that prohibits or invalidates it outside the metric basis, we get 4.655 x 10-14kg/kcal. It
world of nuclear transition. For the HHV to be follows that we adopt 2.586 x 10.'~
lb,,/Btu and
extracted from the reaction and do work, some- 4.655 x 10-'%g/kcal as the mass equivalency

Table 111. Enthalpy of Formation vs. Enthalpy of Combustion1


at 25C and at 1 atm Pressure
Chemical Li Hf(25"C) A Hf(2SC) A H , (25C) O H , (25'C)
Substance Formula kcaUg mol BNlb mol kcaUg mol Btunb mol

Carbon C (solid) 0 0 -94.054 -169,290 I

Hydrogen Hz (gas) 0 0 -68.317 -122,970 I


Oxygen Oz (gas) o o o o
Carbon Monoxide CO (gas) . -26.417 -47,540 -67.636 -121,750
Carbon Dioxide COZ(gas) -94.054 -169,290 0 0
Water HzO (vapor) -57.798 -104,040 o o
Water H a (liquid) -68.317 -122,970 0 0
Methane CH4(gas) -17.895 -32,210 -212.80 -383,040
Propane c&8 (gas) -24.82 -44,680 -530.60 -955,070
Methyl Alcohol C H a H (gas) -48.08 -86,540 -182.61 -328,700
For AHcthe water in products of combustion is assumed to be liquid. The AH~valuesare therefore also HHV values (except that HHVvalues are
always given as positive).
-
constants. In the case of a power plant which degeneracy function g (not to be confused with
averages a heat fired of, say, 3000 x 106Btulhr the Gibbs function g) and is written as g(N, U).
then, over a 25-year operating lifetime we find For any meaningful system this is a very large
that number and therefore the physicist defines for
24 365 25 2.586 0-14s 171b convenience a smaller number u such that
So about 17 lb of matter have been converted
into energy, of which roughly 6.8 lb became
electrical energy. This loss of mass is true only, This definition is called the Entropy or Fun-
of course, in the case where we transfer energy damental Entropy and is related to the ther-
out of the system. In an adiabatic process where modynamic entropy S by the definition
the system is not cooled down to the standard
reference state, then no mass is lost because no S = KBu
energy is transferred.
where
THE GlBBS AND HELMHOLTZ FUNCTIONS K B = the Boltzmann constant = 1.381 X
10-ls erglK
The enthalpy of formation concept we have
just d i s c ~ s s e d ~ i m ~ that
l i e s the reaction under Taking two systems, not in contact, we define
consideration goes to completion. The disrup- system 1to have accessible states gland system
tive energies available in a flame as, for exam- 2 to have accessible states g,. Then the com-
pie, are high that this bined accessible states are glg2. The physicist*s
is not strictly true; thus, the reaction goes to enkopy of the combined system is
com~letionin a somewhat cooler region ad-
joinkg the bulk flame volume. his is com- u=In(g,gd =lng, +lng2 = u , + uz
monlv referred to as residual combustion. The
bulk flame composition in terms of the estab- The total entropy is, thus, the sum of the en-
lished product constituents (02,0, H,O, OH, tropies of the separate systems. From statistical
CO, C02,N2,N, SO2,SO, NH, NH3,CN, HCN) at- mechanics we find that a quantity called the
tains some equilibrium composition consistent Fundamental Temperature is defined in terms
with the prevailing temperature. of the fundamental entropy as
By thermodynamic calculations it is possible
to predict how far a reaction need go to reach
equilibrium at a specified temperature by con-
sidering the thermodynamic potential of the
reaction according to the Gibbs Free Energy Performing the operation,
Change AG. Because this includes entropy in
's8

its determination, it is appropriate at this point 1 - a~(r\r,u)- a ln g (N,u)


- = 1 ag
to dispel some of the confusion that historically 7 h au g h
has attended this quantity. In physics a system 1 lim g (N,u + Au) - g (N,u)
=-
is said to be in its most probable configuration g (N,u) LU+O Au
when the number of accessible states is a
maximum. As N+O, we conclude that g(N,u)-0 because
This is defined as followsg: for zero atoms we have zero accessible states, or
u = system energy & -+ mfmm which r-+ m. It follows that
N = number of atoms in the system

The number of accessible states is called the


COMBUSTION
Cornbudon Froccurss

We now define a quantity T such that 7 =


KBT.Then
- - - (17A)

which is called the Gibbs equation. Writing Eq.


which we write in engineering form as 17A as:

TdS = dU + Pdv
(17B)
In a more restricted sense, this is generally en-
countered as and assuming a system at constant volume
(dv = O), we get the definition

and is the entropy associated with the Gibbs


equation. We can write the first law in the form
(per unit mass)
Writing Eq. 15B as
dq = dU + Pdv
(15A) TdS = dh - vdP
(18)

and taking a system at constant pressure


(dP = 0) we also get the definition
where h is the usual classical thermodynamic
enthalpy function, defined as U + Pv, but is
evaluated in terms of T and P. By taking h =
h(T,P),we write
Writing Eq. 15A as
TdS = dU + Pdv
which introduces the definition for the specific Then at constant u (du = 0) it follows that
heat at constant pressure as:

We can write the second law in the Clausius


form as: We can then show the Gibbs equation from

dq = TdS
(16)

Combining
.- (16) and (Eq. 15A),we get
Substituting Eqs. 17C and 20 into 21, we get
1.0-
0.5-
0-
Now differentiate TS -0.5-
d(TS) = TdS + SdT -1.0-

TdS = - SdT + d(TS)


Since (15B)can be written as
TdS = dh - vdP - 3.5- I I I I I I I I I ~
we get 0 0.2 0.4 0.6 0.8 1.0
dh - vdP = d(TS) - SdT mol COz

then Fig. 6 The Gibbs function calculation shows that


dh - d(TS) = d(h - TS) = VdP - SdT = d(g) equilibrium is established at about 0.4 mol CO,

The definition a(h - TS) = a(h - TS) -


- a ~ a ~
- a ~ a ~ -33.
from which
(22)

is known as the Gibbs function (Fig. 6 ) and is


the Free Enthalpy but is also commonly called
the Gibbs free energy. The equation
Returning to Eq. 15B, we write the classic defini-
d[h - TS) = VdP - SdT tion of C p
(23)
or dq = Cp (dT)p = dh
gives
Then Eq. 15B becomes
Cp (dT)p = Tds - ?ti%,,
which yields an alternate definition for C pas

and

. - - For engineering-applications the entropy S is


("I given as a function of temperature and pres-
sure. (See Properties of Steam, Appendix D.)
a a
Taking aTof Eq. 24 and a p ~ f Eq. 25, we get Taking S = S(T,P),then .
COMBUSTION
Combwtlon Processes

Differentiating the enthalpy, h = u + Pv, we


get

dh = du + Pdv + vdP
Substituting Eqs. 2 6 and 27, we get (34)

and writing the Gibbs Eq. 17A as

du = TdS - Pdv
(35)
where Eq. 2 9 is a convenient forBfor calculat-
ing change in entropy at constant pressure.
If we combine Eq. 15A with the differential we get upon combining Eqs. 3 4 and 35
of TS, we get
d(TS) - SdT = du + Pdv dh = TdS + vdP
(36)

Differentiating the Gibbs function Eq. 22


d(u - TS) = - Pdv - SdT = d(f)
(30)
dg = dh - TdS - SdT
(37)
In Eq. 3 0 the definition

and combining Eqs. 3 6 and 37, we get a differ-


ential equation of state

is called the Helmholtz function and is also dg = vdP - SdT


known as the free energy property of the sys- (38)
tem. To distinguish this from Gibbs free
energy, it is customary to call this the Helm-
holtz free energy. At constant pressure we write Eq. 38 as
From the classical definition of enthalpy as
h = u + Pv, we write the Gibbs function as dg = - SdT
(39)
g=h-TS=u+Pv-TS
(32) In the JANAFIOform, this is written as
Combining Eqs. 3 2 with 31, we find that .the
Gibbs and Helmholtz functions are related as

g = f +Pv
(33)
where the circular superscript " indicates the
Eq. 33 possibly accounts for the fact that the thermodynamic standard of 1atm and 25C.
Gibbs function is also referred to as the Gibbs- The Gibbs and Helmholtz functions have
Helmholtz equation. negative values since TS is greater than u or h.
-
COMBUSTION
CombusUonProtosses
--
On a T-S diagram for steam, this is clearly illus- for equilibrium is based on constant tempera-
trated as shown (g = h - TS) (Fig. 7). ture and total pressure.
The equilibrium composition of a mixture Assuming ideal gases, we replace v in Eq. 41
reacting in an isothermal constant volume by v = RTIP, giving
enclosure is the composition with the least
absolute value of the Helmholtz function
(f = u - TS) (Fig. 8).
A chemical reaction proceeding at constant
temperature and pressure has the Gibbs func-
tion of the mixture decreasing to a minimum at Integrating from standard state To to T for the
the equilibrium composition. The Gibbs func- Gibbs differential and from standard state pres-
tion (Fig. 9) allows us to determine the equilib- sure of 1 atm to partial pressure Piat Gibbs con-
rium composition of any reactive mixture of dition gTattemperature T, and for any it*com-
known pressure and temperature, regardless of ponent of a multicomponent gas, we get
whether these were constant during the reac-
tion or not.
Pfatm
g r - TO = RT In -
1atm

The Equilibrium Coefficient


and the van't Hoff Equation Taking R to be the universal gas constant, ft-lbl
lb-mol-OR, and taking 1 as 778 ft-lb = 1 Btu
Eq. 38 is written as (mechanical equivalent-ofheat], then

. .
Writing this in terms of component i of a
mixture
for a constant-temperature process. We are in-
terested in this, as the Gibbs function criterion

Camposition

Fig. 7 Enthalpy h and free enthalpy g Fig. 8 Equilibriumat isothermal and constant
(Gibbs function). volume conditions(Helmholtz function)
COMBUSTION
CombustionProcesses

In Eq. 43, the value of giof the ithcomponent at The values of vi are, of course, always known
temperature T is found from the Gibbs function when the reaction is known. For an ideal gas
of the component at temperat.re.To (25C) and the properties of the components are indepen-
its partial pressure Pi (atm.) in the mixture. dent of one another (Gibbs-DaltonLaw),where-
fore the Gibbs function of the mixture is just the
STOlCHlOMETRlC COMBUSTION OF GAS sum of the Gibbs functions of the i components.
To introduce the next step, we consider the Then
combustion of natural gas and assume it to be
100 percent CHI.

where Ni is the number of moles of each con-


or in symbolic for stituent present in the enclosure. If a differen-
'%r tial amount of reactants A,B are combusted in
time dy to form products E,F (see Eq. 45) and
writing these mole amounts as dN,, dN,, dN,,
dN,, then the change in the Gibbs function ac-
cording to Eq. 46 is
where the viare called the stoichiometric coef-
ficients. Because we normally burn with air, we
can assume air to be 21 percent by volume
oxygen and take the balance as nitrogen.
21% 0,+ 79% N, -t 100% air

1 mol 0, + 3.76 mols N, = 4.76 mols air

We rewrite Eq. 44 as -
- ~ E , ~P N +E ~ F ,~T N -F~ A ,dN.4
P - g8.p dNB

A
From Eq. 45, we realize that the stoichiometric
coefficients specify the number of moles of
Equilibrium State reactants and products that are involved in the
process. For differential amounts of reaction,
we write

t
Composition

Fig. 9 Equilibrium at isothermal and constant which implies that instead of v4 moles disap-
pressure conditions (Gibbs function) pearing, we have k 4 moles disappearing. Or
-
EQUILIBRIUM CONSTANT

For ideal gas reactions, it is customary to de-


(")
fine an equilibrium constant, KP,such that
Here k is referred to as a urouortionality con-
stant. Substituting Eq. ' 4 9 (that is, kvE dNE
and so on) into Eq. 47A, we get
=
RT RT
[VE ( g E ' p + -Tln P E ) + uF (gF'r + r l n PI)
Or, in general (ireferr to products, j to reactants)

We are interested in the case of chemical


equilibrium (Fig. 9) and assume an infinitesi- Dropping the conversion constant J to the
rnal reaction around equilibrium to result in a usual textbook form, Eq. 5ZA.then becomes
net Gibbs function change of zero. For this
event we write Eq. 50 as AGTo = - RT In I(,
(53)

We now recast Eq. 22, taking into account the


constant temperature assumption, in the form

The quantity V E ~ E , T O + VF ~ F , T <- v.4 g.4,T0 -


v, ~ B , T Ois known as the standard-state Gibbs
function change for a reaction and is usually Substituting Eq. 54 into Eq. 53, we get
written as AGTO. Or, in general,

(55)

Differentiating Eq. 55 with respect to T, we get

I--,

Eq. 51A now is therefore written as


Now Eq. 18 for the case of constant pressure is
RT P g E p;*F
- AGTQ= I n
I TdS = dh
- COMBMTIOU
Combustion Procmsm

Writing Eq. 5 7 as TASp = and differ-


A H T O side of Eq. 61 is negative. This requires that
-
entiating with respect to T, keeping in mind Kp2<Kp,. Thus for exothermic reactions the
that T itself is held constant, rye get equilibrium constant Kp decreases with in-
creasing temperature. For endotber-mic reac-
Td(bSp) - d(AH F) tions one expects the opposite to be the case.
dT d? Eq. 61 also tells us, as well as the van't Hoff
equation in general, that Kp is a function of
temperature, but that this is physically mean-
As these terms in Eq. 56 cancc I, we get ingless unless the reaction is also specified.
How the stoichiometric equation is specified
is, unfortunately, also important. This is illus-
trated by the following identical reactions
1
(a) C O + O 2 +C 0 2
Since d ( l 1 ~ =
) - dTIT2,Eq. 5;ican also be writ- (b) Z C 0 +0 2 + 2CO2
ten as
The standard state Gibbs function change for
the preceding reaction is
AGrc = vcoz gcoz - (VCO~ C +
O ~ 0 got)
2

as well as AGr/cm = l g c o , - l g c o - %go2


"s ~ G T ' I ,=~2) . ~ -
0 2gco
~ - lgo,
AHF = RTZ--d(ln K P ) Thus AGTO/(b,
= 2AGTo/(a).Writing Eq. 53 as
dl

Eqs. 58,59, and 60 are knowr as the van't Hoff (62)


equation. Generally the enthalpy of reaction is
approximately independent of temperature. If and taking the ratio of K ~we ~get ~ ,
such is the case, then Eq. 59 ca Ibe integrated as ( I ( , , ) ~ - e - ? i ~ n ~ m ~ R re - 2 r
--
(K~),, -ACFII~.LQT= 7 . r

K 'IT, AHp
IK 1'0
' d ln ( K r ) = - d (11T) If we now square (Kp)., we get the ratio to be
1' 1 IT, equal to unity:

For exothermic reactions AHT- is negative by


( K P )=
~ (KP)n2
convention (heat or radiatior is carried away
from the system). By second law considerations Thus by doubling the stoichiometric equation,
one expects T2>TI. Therefor? the right-hand we have squared the equilibrium coefficient. If
--
we take the "backward-r~te" or dissociation where
reaction for (a), we write MT = mols total (products)
(c) CO, -,co + % o2 Then
and

Similarly, we take

Substituting ~ q 65. into Eq. 52C, we get

with the useful result tha the backward-rate


equilibrium coefficient is s mply the reciprocal
of the forward-rate equilib~iumcoefficient. By
use of the perfect gas law, 1he equilibrium con-
stant, K,, can be put in sorlewhat more useful
form than is given by Eqs. F 2B and 52C. Realis-
fi N;' (PdNmT)"'

tically speaking, if one had a cylinder contain- xvi - xu'


ing a mixture of gases at a tc~talpressure of 1000
psig, it would be difficult o invent a pressure
gage that would sequentially read the partial
n NY'

pressures and identify the orre responding com-


ponents. An Orsat analysis dentifying the com-
ponents and the volumetr c composition is a
more practical method.
For component i in volun~ev. we write by the
perfect gas law Using reaction 45 as an example, we would
write Eq. 66 as

Since P,,,,, = ZP,,

then M Ib
= N, APPLICATION TO
pi lb/mol
COMBUSTION CALCULATIONS
where:
The following calculations demonstrate the
Ni is the number of moles of each constituent application of the foregoing discussion.
present in volume v
BURNING PROPANE
Taking the ratio P@T, we get
Burn propane (C3H8)stoichiometrically (0%
excess air). The reaction on a molar basis is, as-
suming dry air,
COMBUSTION

The air-to-fuel ratio therefore is Then PHOO = 0.106 X 14.7 = 1.56 psia with a
28 1b corresponding dew point (saturation tempera-
32
3mo102 X -
mollb + 18.8 mol N2 X -rnol ture) of 117F. Converting this to a wet-air basis
= 15.7
44 lb of 80F,1 atm, 1.013 lb wet airllb dry air we
1 rnol C3H8 X -
mol calculate
or, equivalently 0.013 lb H 2 0 29 lb dry air 1rnol HzO
23.8 mol air x 29 lb air/mol air lb dry air rnol air 1 8 lb H 2 0
1 rnol C,H, x 44 lb C,H,/rnol C3He rnol H 2 0
= 0.021 -rnol air

Now suppose that we burn the propane sub- From the left-hand side of (70), we have 35.7
stoichiometrically at 80 percent theoretical dry mols air used in the reaction or 35.7 mols air x
air. To solve the problem of insufficient air, we 0.021 rnol H,O/mol air = 0.75 rnol H,O in-
make the assumption that Hz will always go to troduced with the air. Wherefore the products
H,O i n favor of C going to C02. (On the basis of [right-hand side of (70)] now contain 4 +
reaction kinetics this is a valid assumption.) 0.75 = 4.75 rnol H,O. Thus,
Reaction 68 now becomes
4 + .75
P H I O= -
37.7 + .75
= 0.1235 atm. = 1.816 psia

Now suppose that we have a volumetric (Orsat)


analysis of the products (COZ = 11.5 percent,
O2 = 2.7 percent, and CO = 0.7 percent) and
This reaction solves as we know we are burning propane. We then
write reaction (67) as

Reaction 69B is a n approximation as we have


implicitly assumed that the reaction goes to
completion. Continuing with the combustion The for reaction 71A is
of propane, we may assume, say, 150 percent
theoretical dry air and consequently write reac-
3X = 11.5 + 0.7 X = 4.0667 = 4.07
tion 68 as
The hydrogen balance for reaction 71A is

C3HB+ 7.502 f 28.2N2 -, 8X = 8 X 4.0667 = 2b b = 16.25


3C02 + 4 H p 0 + 2.502 + 28.2N2
(70) The oxygen balance for reaction 71A is

Products = 3 + 4 + 2.5 + 28.2 = 37.7 mols. 2a = 2 x 11.5 + 0.7 + 5.4 + 16.25


The product mole fractions an! a = 22.65
Substituting for x, a, b in reaction 7 1 A and
dividing through by 4.07, then we get

Here the formula is an average composi-


tion of the fuel components.
From reaction 72B the combustion air is
2 2 . 1 + 83.2 = 105.3 11101s per mol fuel. To
Comparing reaction 71B with the stoichiomeiric convert reaction (72B) to a stoichiometric basis
reaction (71A), it follows that the excess air we realize that, ideally, 0.9 CO should be 0.9
CO, and that 3.8 0, goes to zero; then the 0.9
determined by Orsat analysis is
oxygen supplies 0.45 0, to the 0.9 CO, so an
additional 0.45 0, must be supplied by the
e
5
5
x 100 = 111 percent theoretical air left-hand side.
Therefore, the 0, requirement on the left-
or 11 percent excess air. hand side of reaction 72B is

BURNING HYDROCARBON FUEL


Next we suppose that we have an Orsat anal- Hence, reaction 72B .becomes
ysis ( C 0 2 - 12.1%, O2 - 3.8%, CO - 0.9%)
and we suspect we are burning some hydrocar-
bon fuel. We then write

C,H, + a 0 2 + a3.76N2 12.1CO2+ 0.9CO +


+

83.2N2 + 3.802 + b H 2 0
from which it follows that the excess air per-
(724
cent is

"a" from the nitrogen component is


a 3.76N2 = 83.2N2, a = 83.2/3.76 = 22.1
GlBBS FUNCTION CALCULATION
Then, from the oxygen balance Consider the water-gas reaction

and apply the Gibbs function to the total sys-


From the carbon balance, we write tem. First, we assume the following reactions
1CO + l H 2 0 + 1 C O 2 + 1 H 2
+
1CO lH20+0.8CO, + 0 . 8 H 2 +
0.2 CO + 0 . 2 H z 0
For the hydrogen balance, we write
1 CO + 1 H ~ O+-0.6COz + 0.6 H2 +
0 . 4 CO'+ 0.4 H 2 0
1 CO + 1 Hz0 + 0 . 5 Cot + 0.5 Hz +
wherefore reaction (72A) becomes 0.5 CO + 0.5 H 2 0
COMBUSTION
Combustion Proceases

The Gibbs function for the total system is C In the JANAF tabkes, the entropy at tempera-
- products - Z reactants ture T for component i is tabulated at 1 atmo-
= 2 (hi - T U i ) products - C (hj-.TASj) renctants
sphere and we therefore make a "correction"
i 1 for component i at partial pressure Pistarting at
pressure Po = 1atm. Hence,
To apply the above to the-postulated reac-
tions, we use Eq. 29. From Pv = R,Tlp = RT, we
write

then

Substituting in Eq. 29 From the JANAFtables, we tabulate the follow-


ing values at 1000K and 1 atm, Table IV. We
assume the reaction to proceed at 1000K for
convenience, to simplify the calculations.
(74) HEAT GAS-PHASE REACTION
Consider the gas-phase reaction
Then, for component i,

and assume the reaction is in equilibrium at 1


atrn and 3000K. Assume negligible tempera-

Table IV. Gibbs Function Calculation-Step 1


AH; (lOOOK) SOIOM)

H?oM)-H& H&-H", H%w-H", Enthalpy Entropy


kcaUmol kcaUmol 31+ 11) of Formation at 1 atm.
Component I I1 Sensible Enthalpy kcaUmol caUmol-'K

Table V. Gibbs Function Calculation-Step 2


Hprd,,,satlmoleach 10.222 C 0 2
6.968 Hz
17.190 kcallmol
HreactantS at 1 mol each 7.255 CO
8.576 H 2 0
15.831 kcallmol
Hsemre = Hat 1 X fractional mol
COMBUSl'ION
CombuctionProcesses

Table V. Gibbs Function Calculation-Step 2 -(Continued)


Mol 0.8 0.6 0.5 0.4 0.3 0.2

C 13.752 10.314 8.595 6.876 5.157 3.438


Mol 0.2 0.4 0.5 0.6 0.7 0.8
co 1.451 2.902 3.627 4.353 5.078 5.804
Hz0 1.715 3.430 4.288 5.145 6.003 6.861
z 3.166 6.332 7.915 9.498 11.081 12.665
~ P T O ~ I I C ~ S 16.918 16.646 16.510 16.374 16.238 16.103

Hproducts - Hreuetunis Vs. mols C o t -


Mol
c02 1.0 1.08 0.6 0.5 0.4 0.3 0.2
Products 17.190 16.918 16.646 16.510 16.374 16.238 16.103
Reactants -15.831 -15.831 -15.831 -15.831 -15.831 -15.831 -15.831

Table Vl. Gibbs Function Calculation-Step 3


Calculating entropies according to Eq. 76,we get (at 100o0K)
Sco, = 1.0(63.444-1.986ln 0.5)
SH, = 1.0(39.702-1.986In 0.5)
Total Sprodurtsat
1 atm (& 1 mol Cod

Sco = 1.0(56.028-1.986In 0.5)


SH,O = 1.0(55.592-1.986ln 0.5)
Total S rearrantsat 1 atm

sco* = 0.8(63.444-1.986In 0.4)


SH, = 0.8(39.702-1.986ln 0.4)
Sco = 0.2(56.028-1.986In 0.1)
SH,O = 0.2(55.592-1.986In 0.1)
Total Sproducfsat
0.8mol CO,

Sco*
SH,
Sco
SH,O
Total
COMBUSTION
CombustionProcesses

Tabk VI. Gibbs Function Calculation-Step 3 -(Continued)


Calculating entropies according to Eq. 76,we get (at 100o0K)
sco,
SH,
sco
SH~O
Total
sco, 0.4(63.444-1.986 ln 0.2)
SH, 0.4(39.702-1.986 In 0.2)
sco 0.6(56.028-1.986In 0.3)
SH~O 0.6(55.592-1.986In 0.3)
Total SPrOdl,Cf8at
0.4mol CO?
Sco,
SH,
Sco
SH,
Total
SCO, = 0.2(63.444-1.986 In 0.1)
SH, = 0.2(39.702-2.986In 0.1)
SCO = 0.8(56.028-1.986ln 0.4)
SH~O 7 0.8(55.592-1.986 ln 0.4)
Total Sprodirclsat 0.2 mol CO2
Spro~lIclS
x 100o0K = Sproducls
in kcallmol
( -Sproducls +S rcactondT = -T A S
1= products - Z reactants
Mol
co2

-- - -

Table VII. Gibbs Function Calculation-Step 4


For the heat of formation (exothermic), we get, at 1000~K
& 1 atm total pressure

Mol
Cot 1.0 0.8 0.6 0.5 0.4 0.3 0.2
COMBUSTION
Combustion Processes

Table VII. Gibbs Function Calculation-Step 4 -(Continued)

For the heat of formation (exothermic), we get, at 1000K & 1 atm. total pressure

Finally
(z Hs + HF - TS) -
prodiicts
(z Hs + HF - TS) is tabulated in Table VIII
reactar~ts

"
as
[HS
prodrcts
- ~ s
reuclar~ts
]+~[HF
products
- HF
reactants I"
- ,rodlLcts
- TS
1
ref~ctflilts

where A means 2 products - z reactants


Table Vlll. Gibbs Function Calculation-Final Step
Mol
Cot 1.0 0.8 0.6 0.5 0.4 0.3 0.2

M
-
.
F O -9.304 -7.643 -5.982 -5.151 -4.321 -3.491 -2.661
Gibbs f0.529 -1.764 -2.755 -2.987 -3.060 -2.967 -2.681

- -- -
ture dissociation for 02.
For the reaction
co, * 1CO + ?/202
at 1 atm and 3000K, Ref. 2 gives the equilib-
rium coefficient as
Log,,Kp = -0.185 /1 atm. \'-"+t)

The equilibrium coefficient we need, accord- KP = 3.055 = (Ncozl' \NrnT)


(Nco)' (No?'
ing to Eq. 64, is therefore (78)
-- - -- - -. - -- -- -
(KP),, = ' / (-K P ) ~
- 2

As we anticipated that the reaction does not


(KP),, = - 1
10-0.485 = 100185 = 3.055 go to completion, we rewrite reaction (77) with
CO and 0, also on the right-hand side. We note
From Eq. 66, we have for (a) in Eq. 66 that the stoichiometric coefficients ap-
COMBUSTION
CombustionProceases

pear as exponents only; there are therefore no which is the equilibrium composition we
restrictions on the moles. We can therefore con- would expect for the specified reaction.
sider the case of an equimolal reaction (for con- CALCULATIONWITH AIR
venience) and write - - - Now let us do a more realistic calculation using
air instead of oxygen. We write Eq. 7 9 as
1co + 102 -. x CO + y o z + zC02
EQUIL. C O + 0 2 + 3 . 7 6 N 2 + ~ C O + y 0 2+ z C O 2 + 3 . 7 6 N z

The moles of mixture at equilibrium are

In this reaction the product moles are


We also note that N,, carried along as an inert,
has no effect in Eq. 66, that is,
Substituting the mixture [the right-hand side of
reaction 791 into reaction 78 we get

and, as before,
1 atm.
3.055 = x7
;I'2 (X + y + z + 3.76
In addition, the carbon balance demands that
1 = x + z and the oxygen balance requires that The carbon and oxygen balances remain the
3 = x + 2y + 22, then same
l=x+z, 3=x+2y+Zz
and

Thus
then

Substituting into Eq. 80, we get


Substituting for y and z

Squaring both sides and simplifying

squaring both sides and simplifying


By inspection x = 1/3 is an approximate solu-
tion. By additional calculation we find that x is
close to 0.34. Then By inspection, it is clear that Y3 < x < M ; by
z = l - x = l -.34 = . 6 6 successive approximations we determine that
and

and it follows that the equilibrium reaction is


Comparing this with the previous solution
COMBUSTION --
CombustionProcesses

with the inert nitrogen constituent dropped

We see that the presence of an inert (nitrogen)


I
decreases the amount of C02formed. If we now
, take a less drastic temperature, say 1000K,and which compares reasonably well with the
perform the equilibrium calculation, we find value of 766 given by Wark2. The van't Hoff
1
that for the reaction equation therefore gives a fair value in the ab-
sence of experimental data.

I Reference (2)gives the equilibrium constant as


Log loKp = -10.221.Then METHODS OF BURNING
1
(Kp)" = -
1 =- 1 =
10-10.z21
(Kp))
1010.221 SOLID FUELS
Of particular interest in the practical combus-
Taking Kp as 10 lo (for convenience) we get
tion of fuels are the physical processes em-
3 = =
(1 - x)Z(3 + x) ployed. Chapter 12 treats the firing of liquid
xZ + x3
(10'0)2 1020
I and gaseous fuels. Here we briefly discuss four
j Hence principal mechanisms currently used for burn-
ing coal and other solid fossil fuels. These
mechanisms differ in
which can be rewritten closely as w the place where fuel is introduced into the
10~0x3 + i o 2 0 ~+2 5x - 3 = o furnace
the way in which the fuel is injected
We can conclude that the x value is effectively the size of the fuel required by the process
zero. Thus, 8 the temperature of any transport or carrier air,
also called "primary air"
the relative upward velocity of the combus-
At 1000K, therefore, the reaction effectively tion air and the fuel particles in the furnace,
goes to completion which is far from being the while burning is taking place
case at 3000K. the amount of recirculation (if any) of solid
We used a K, for the reaction 1 CO + l/z 0,
- 1 CO, of 3.055at 3000K.To estimate the Kp
for the same reaction at 2000K, we use the
particles of ash, or fuel plus ash, from a point
beyond the furnace back into the furnace; this is
turn affects '

van't Hoff isobar Eq. 61. the residence time of the fuel and carbon-
bearing ash particles in the furnace; and, very
importantly,
Ithe average temperature of the fuel as com-

1 The universal gas constant, R, has units of bustion proceeds.


The following overview will summarize these
differences as they relate to firing solid fuel ei-
The enthalpy of reaction, A H T O , is given by ref- ther in suspension firing of pulverized fuel
erence (2)as -119,500 Btulmol at 2000K and (called open-furnace firing or entrained flow);
-117,200Btulmol at 3000K.Taking a numeri- on a slowly moving or fixed grate (generally re-
cal average of -118,350Btulmol, we get ferred to as stoker firing); iu a bubbling type of
fluidized bed; or in a circulating fluidized bed.
Stoker firing, historically the oldest way to
burn both coal and waste solid fuels, is still
very much in use. Pulverized-fuel suspension the volatile-to-fixed-carbon ratio of the fuel
firing, a very efficient and practical way to burn the as-fired fuel moisture content
very large quantities of coal and lignite, often the size of the fuel.
has the liability of requiring expensive flue-gas SUSPENSION FIRING
cleanup systems for sulfur-oxide reduction.
Fluidized-bed firing is ideal for handling low- Most large steam generators producing power
g a d e fuels where sulfur removal is accom- through the burning of solid fuels are of the
plished in-bed instead of in a post-combustion entrained-flow reactor type, most frequently
scrubbing system. called suspension fired; much of the material
in Chapters 6, 7, and 8 concerns this combus-
STOKER FIRING tion process. Chapters 11 and 1 2 cover the
Chapter 12 of this text describes in detail the equipment for pulverizing and firing the fuel
equipment for burning coal as well as other for such boilers; the flue-gas emission control
types of fuel on a grate. In the majority of coal- and ash-handling systems of Chapters 15 and
fired applications, the grate or fuel bed is con- 16, as well as the discussion on the formation
tinually in slow motion, usually from the rear of nitrogen oxides in the next section of this
to the front of the furnace bottom. (Grate motion chapter, are oriented in large toward this type
is from front-to-rear for mass burning of coal or of firing.
waste fuels.) Metering feeders either deposit In pulverized firing, coal is ground to the
the fuel directly on the grate, or spread it me- fineness of face powder, which a stream of pri-
chanically or pneumatically from points usu- mary air transports into the furnace; it ignites
ally 10 to 20 feet above the grate. With the latter as the fuel-air mixture enters the furnace, where
method, significant burning occurs while the it is joined by the bulk of combustion air (called
fuel is in suspension, with the remainder tak- the secondary air) which is heated to tempera-
ing place on the grate; the proportions will vary tures between 500 to 800F (260to 425OC). Res-
with fuel size, fuel reactivity, and the mode of idence time of the burning fuel in the furnace is
injection. measured in seconds; solid-particle recircula-
In stoker firing, heated air passes upward tion is not used; and radiation of heat to the
through apertures in the grate, with dampers furnace-wall tubing is the principal mode
often positioned in undergrate zones in order to of transfer.
achieve proper biasing of airflow. Over-grate air The following variables affect the average
(termed overfire air) adds turbulence to the temperature of both gas and solid particles in a
combustible-containing gases coming from the suspension-fired or entrained-flow furnace:
grate and supplies the required air for the por- the type of firing (cornerltangential/vortexor
tion of fuel that burns in suspension. As de- multiple wall burners)
scribed i n Chapter 12, a relatively small excess-air percentage
amount of recirculation of solid material in- fuel reactivity and moisture content
creases the residence time of the larger-sizepar- air distribution in the furnace
ticles. The principal mode of heat transfer in firing density (either heat released in the ac-
the furnace is radiation from both.the hot fuel tive firing volume, or per square foot or square
bed and the burning gas and char in the open meter of furnace plan area)
combustion chamber. furnace geometry
The average temperature of a stoker fuel bed, preheated-air temperature
which cannot be calculated, is a function of: the dirtiness of the furnace wall, partially a
the grate speed (for a moving grate) function of the soot-blowing cycle.
the temperature of the air flowing upward Although the maximum attainable tempera-
through the grate ture (the adiabatic flame temperature) in such a
the excess-air percentage furnace can be calculated, it will not be
COXDUSTION
CombustionPmcesses
-
achieved. The immediate long-beam radiative tion of combustion air, and the solids recycle
cooling that takes place in a water-cooled rate. Many of the variable described above for
chamber during the combustion process makes stoker and suspension firing also have an influ-
it impossible to attain the adiabatic tempera- ence. But, in contrast to those methods of fir-
ture. Furnace exit-gas temperature can be meas- ing, t h e temperature i n a fluidized-bed
ured. T h u s , some approximation to a n combustor is controllable in a narrow range, as
arithmetic or logarithmic average temperature further discussed in Chapter 9. Such control
,of the gas and ash particles passing through the helps to minimize nitrogen-oxide formation
furnace can be calculated. and allows the optimum temperature level for
In order to vary furnace exit temperature with calcining liniestone for the capture of sulfur
load, change in fuel, or furnace-wall dirtiness, oxides.
staged combustion, biased firing, or fuel-
nozzle tilt (in tangential firing) are used in large
open combustion chambers; such arrangements THE FORMATION AND
allow control of superheater or reheater outlet CONTROL OF NOx
steam temperature, or furnace nitrogen-oxide IN STEAM-GENERATING
production, or both. EQUIPMENT
FLUIDIZED-BED FIRING Nitrogen monoxide (NO) and nitrogen
Chapter 9 covers in detail the technology and dioxide (NO,) are byproducts of the combus-
design of equipment for the two distinct mech- tion process of virtually all fossil fuels. His-
anisms used for fluidized-bed firing in power torically, the quantity of these inorganic
plants: bubbling beds and circulating (some- compounds in the products of combustion was
times called recirculating) beds. In a bubbling- not sufficient to affect boiler performance, and
bed combustor, fuel size and vertical air their presence was largely- ignored. In recent
velocity are regulated to establish a discrete years, oxides of nitrogen have been shown to be
horizontal plane which divides the active bed key constituents in the complex photochemical
from the entrained-flow ''open furnace" above. oxidant reaction with sunlight to form smog.
In a circulating type fluid-bed unit, smaller fuel Today, the emission of NO, and NO (collec-
size and higher air velocities extend the zone of tively referred to as NO,) is regulated by both
high solids-to-gas density up to the top of the state and federal authorities and has become an
furnace, and beyond, into the process separator, important consideration in the design of fuel-
normally a cyclone. firing equipment.
With the bubbling fluid bed (BFB),the con-
duction/convection heat transfer is to furnace THERMAL NO,
wall tubes and other heating surface that may
be immersed in the bed; radiation transfer oc- The formation of ~ 0 ; i nthe combustion pro-
curs above the active bed. With the circulating cess is often explained in terms of the source of
fluid bed (CFB),the bulk of conduction/convec- nitrogen required for the reaction. The N2 can
tion heat transfer is to the combustor wall originate from the atmospheric air, in which
tubes. Further heat absorption can be by tubu- case the product is referred to as "thermal
lar heating surface outside the combustor, de- NO," or from the organically bound nitrogen
pending upon the specific application. components found in all coals and fuel oils
The basic mechanism for the control of bed which are termed "fuel NO," It is important to
temperature and heat transfer to the walls of the note that even though NO, consists usually of
combustor, and to any immersed heating sur- 95 percent NO and only 5 percent NO2, the
face in the bed of a fluidized-bed boiler, is the normal practice is to calculate concentrations
variation in total solids inventory, the distribu- of N0,as 100 percent NO,.
I
COMBUSTION I
CombusUon Processes
I
The mechanisms involving thermal NO,r From this equation, it can be seen that ther-
were first described by Zeldovichll and later mal NO can be decreased by reducing time,
modified to what is referred to as the extended temperature, and concentrations of N, and 0,.
Zeldovich mechanism. The fact that temperature in this equation is an
exponential clearly demonstrates its impor- -
tance in the control of thermal NOx. In practice,
the Zeldovich mechanisms demonstrated by
Eq. 84 are sufficient for predicting NO, only in
regions that are downstream of the flame front.
Fenimorel3 coined the phase "prompt NO"
to describe the NO generated within the flame
front region for which, because of the very
short residence time, the Zeldovich reactions
proved inadequate. Subsequent investigation
by DSoeto14 showed that, as in Zeldovich's
As the equilibrium values predicted by this reactions, temperature in all cases reduced
mechanism are higher than those actually prompt NO; however, additional 0, increased
measured, it is generally assumed that Eq. 81 is NO for fuel-rich flame fronts but decreased NO
rate-determining due to its high activation for fuel-lean flame fronts.
energy of 3 17 kJlmol. A better understanding of The effects of fuel-rich vs. fuel-lean flame
thermal NO, can be derived from bench-scale fronts on prompt NO can be seen from the for-
tests that measure NO, in a heated mixture of mation of NO from diffusion vs. premixed gas
N,, O,, and argon 12.These tests show that ther- flame. As shown in Fig. 10,the stoichiometry at
mal NO,. can be predicted by the following the premixed flame front is the same as the
equation: overall stoichiometry of the flame, since all the
air is mixed with all the fuel. In the diffusion
flame, fuel and air are introduced separately
[NO] = K,e(-K,1T)[N,][0,]112t and mixed by burner-induced turbulence. The
where [ ] = mol fraction
T = temperature flame front forms before mixing is complete
t = time and is, therefore, fuel-rich even though the
K,,K, = constants (84) total fuellair mixture may be air-rich. Tests by
Takahashi15 et al., Fig. 11, show the bell-

Diffusion Flame Premixed Flame

Fuelrair
Prem~xlng
Zone

I Air Ratio\ I I Operating :point


w-. -.a v.
..
. W".,",

Flame
Fuel Fuel Air Deficient - 1.0 -Air Excessive
I I
Fig. 10 Diffusion-flame and premixed- Fig. 11 NO, versus stoichiometry for
flame mechanisms premixedand diffusion flames
Cambudlon Processes
-
shaped curve characteristic of prompt NO for combustion of coal. Bench-scale tests, Fig. 12,
premixed flames, but the diffusion flame does burning fuel oils in a mixture of oxygen and
not show decreasing NO with increasing O2be- carbon dioxide (to exclude thermal NO,) have
cause the actual flame front is never air-rich. shown a remarkable correlation between the
It is interesting to note that Takahashi has percent N, in the fuel oil versus N0,:'Fig. 12
shown that two separate flames, one fuel-lean also illustrates the fact that the percent of fuel-
premixed flame, plus one fuel-rich diffusion nitrogen conversion is not constant, but de-
flame (points C l and C2, Fig. 11)can be com- creases with increasing fuel nitrogen.
bined to produce a lower NO(at C') than either Similar bench-scale tests run for various
type flame with the same overall stoichiometry coals have riot produced similar results. Fig. 13
(points A or B). illustrates the large contribution of fuel NO,,
yet there is no apparent correlation between the
FUEL NOx quantity of fuel-bound nitrogen and fuel NO,.
Although the kinetics involved in the con- Clexly, the fuel-nitrogen conversion rate is not
version of organically bound nitrogen com- constant, but will vary widely depending more
pounds found in fossil fuels are not yet well on coal rank than on actual nitrogen content.
understood, numerous investigators have One explanation of the fuel-nitrogen conver-
shown fuel N0,to be an important mechanism sion rate is shown in Fig. 14 which was ob-
in NO, formation from fuel oil, and the domi- tained by subtracting a calculated Zeldovich
nant mechanism in NO, generated from the thermal-NO, value from total NO, measured in
large tangentially fired utility units. The resul-
tant fuel-NO, correlated well with the fuel
nitrogenloxygen ratio which suggests that
fuel-bound oxygen, or some other fuel property
that correlates with fuel oxygen, influences the
percent conversion of fuel nitrogen to fuel NO,
Although there is little doubt that fuel-bound
nitrogen is an important contributor to total
NO, emissions from coal and oil, the mecha-
nisms involved in the transformation of fuel
nitrogen to NO appear to be every bit as com-
plex as the combustion process itself. On the

High-Vol.
Bit. c Med.-Vol.
. Bit.
.ignite
High-Vol. Lo~-Vol,
Subbit. Bit.
C Coal Bituminous
~igh-VOI.
Bit. A

% Fuel Nitrogen
- -
I I
I
% Nitrogen in Fuel (DAF)
I
I
Fig. 12 Fuel NO and percent conversion of Fig. 13 Fuel NO and percent conversion of fuel
fuel nitrogen to Fuel NO-liquid fuels nitrogen to fuel NO-pulverized coal, premixed
COMBVSTION
CombustionProcesea

other hand, several investigators have made In staging, a portion of the total air required
quantitative measurements in laboratory tests to complete combustion is withheld initially
that provide valuable insight to the potential and the balance of the air is mixed with the in-
control of fuel NO,." *. complete products of combustion only after the
Pershinglg isolated fuel NO,. by burning-coal oxygen content of the first-stage air is con-
in a synthetic oxidant mixture that had a spe- sumed. By varying the amount of first-stage air,
cific heat similar to air, containing 21 percent the suspension-fired combustion of a coal parti-
02, 18 percent COz, and 61 percent argon. On cle or oil droplet can be interrupted at different
the basis of four different coals, the studies stages of the reaction because of lack of oxygen,
showed that fuel NO,, unlike thermal NO,, and allowed to proceed further at such time as
was relatively insensitive to the range of tem- the balance of air (second-stage air) is intro-
peratures found in most flames. Levy19 et al. duced. For NO, control, the ideal quantity of
found that, under pyrolysis, 65 percent of the first-stage air would be that which is sufficient
fuel nitrogen remained in the char after all the to only generate the temperatures necessary to
volatile matter had evolved at the 1380F used drive the gaseous state, but insufficient to pro-
in the ASTM proximate-analysis test, and 90 vide sufficient oxidant to complete a reaction -

percent had evolved by 2400F. These tests, to NO.


then, suggest that the fuel-bound nitrogen be- Fig. 15 shows the effect of first-stage stoichi-
gins to evolve in the later stages of devolatiza- ometric ratio on outlet NO, levels for liquid
tion of coal and that subsequent high tempera- fuels with various nitrogen levels. Even though
tures do not significantly affect the conversion
to NO. 0 Unrefined Shale Oil (2.08% N2)
A most significant property of fuel nitrogen Alaskan Bunker C (0.51% N2)
conversion that affects the design of fuel-firing o Gulf Coast No. 6 (0.36% Nz)
equipment relates to the availability of oxygen A Indo/Malaysian No.6 (0.24O/0 Nz)

to react with the fuel-nitrogen compounds in o, o Alaskan Diesel Oil (0.007% Nz)
W
their gaseous state. Simply stated, the com- a
pounds that evolve from a coal particle such as
NCH and NH3, are relatively unstable and will
reduce to harmless N2 under fuel-rich condi-
tions, or to NO under air-rich conditions. The
technique used to demonstrate this is staging.

S Ratio of Coal Oxygen


to Coal Nitrogen
First Stage Stoichiometric Ratio
Fig. 14 Fuel-bound nitrogen conversion to NO,
in pulverized-coal combustion; the influence of Fig. 15 The effect of liquid fuel composition
the coal-oxygen to coal-nitrogen ratio on emissions-staged suspension firing
-
the tests used air for an oxidant and the total Chapter 12 describes the equipment used in
NO, levels represent both thermal and fuel large suspension-fired steam generators to min-
NO,, the increased effectiveness of staging imize the formation of NO, in the fuel-burning
with higher fuel-nitrogen content is clear. Fig. process in a furnace. In Chapter 1 5 , post-
16 shows a similar but less dramatic effect on a combustion (after-furnace)methods are given for
Utah bituminous coal. This and other tests have chemically or catalytically reducing the quan-
shown that for coal, unlike oil, decreasing the tity of nitrogen oxides passing to the atmos-
first-stage stoichiometric air below an op- phere. An optimum system for overall NO,
timum level will increase NO, levels, which reduction will result from the integration
suggests the possible requirement of an oxi- of both in-furnace and post-combustion
dant to reduce the intermediate HCN, NH,, and techniques.
other radicals. 1 I
The most important design criteria relevant to I 700r Premixed 1
the control of both thermal and fuel NOx for coal
firing can be summarized as follows:
Coals with the lowest fuel-nitrogen and the
lowest fuel oxygenlnitrogen ratios generally will
produce the lowest NOx.
m The fuel NO, can be minimized by control-
ling the quantity of air permitted to mix with
the fue1,inthe early stages of combustion.
The thermal-NOx contribution to total NOx
can be reduced by operating at the lowest prac-
First-Stage Stoichiometric Ratio
tical percentages, as well as by minimizing gas
temperatures throughout the furnace through the
use of low-turbulence diffusion flames and large Fig. 16 The effect of initial fuellair mixing-
water-cooled furnaces. staged, Utah bituminous coal

REFERENCES
' "Standard Atmosphere Tables and Data for altitudes to It may be noted that the term Gibbs Free Energy is in com-
65,800 feet," National Advisory Committee for Aeronau- mon use. Strictly and historically speaking it is incorrect.
tics Report 1235 International Civil Aviation Organiza- The Gibbs function of the system is termed the "Free En-
tion (ICAO), hlontreal, Canada and Langley Aeronautical thalpy" property. The Helmholtz function of the system
Laboratory, Langley Field, VA. 1952. is more properly called the "Free Energy" property. See,
for example, E. Schmidt*.
Kenneth Wark, Thermodynamics, 2nd ed., McGraw-Hill,
1971. E. Schmidt, Thermodynamics, translated from 3rd Ger-
'William C. Reynolds and Henry C. Perkins, Engineering man edition, Oxford University Press, London, England,
1st English ed., 1947.
Thermodynamics, 1st ed., McGraw-Hill, 1970.
C. Kittel, Thermal Physics, John Wiley & Sons., New York,
Gordon J. Van Wylen and Richard E. Sonntag,Fundamen- 1969.
tals of Classical Thermodynamics, 2nd ed., John Wiley &
Sons, Inc., 1973. I0JANAF (Joint Army, Navy, Air Force Project), Ther-
". U. Condon and Hugh Odishaw, Handbook of physics, mochemical Tables, 2nd ed., 1970 issued 1971, NSRDS-
2nd ed., New York: McGraw-Hill, 1967. NBS 37, U.S. Government Printing Office, Washington,
D.C.
R. E. Bolz and G. L. Tuve, eds., Handbook [of Tables for) Ya. B. Zel'dovich, "The Oxidation of Nitrogen in Combus-
Applied Engineering Science, Publ. by the Chemical Rub- tion and Explosions:' Acta Physicochimica U.S.S.R., 21:
ber Co., Cleveland, Ohio, Copyright 1970. 577-628, 1946.
11 D. J. MacKinnon, "Nitric Oxide Formation at High Tem- 17 W. W. Habelt and B. M. Howell, "Control of NO, Forma-
perature," Air Pollution Control Association Journal, tion in Tangentially Coal-Fired Steam Generators" Pm-
24(3): 237-239,,pIa~h1974. ceedings of the NO, Control Technology Seminar, San
13 C. P. Fenimore, Formation of Nitric Oxide From Fuel Ni- Francisco, February 5-6,1976. Special Report. Report no.
trogen in Ethylene Flames," Combustion and Flame, PB-253 661 (EPRI SR-39). Springfield, VA: National
19(2):289-296, October 1972. Technical Information Service, 1976.
14 G. De Soete, "Mechanism of Nitric Oxide Formation From 1s D. W. Pershing and J. 0. L. Wendt, "The Effect of Coal
Ammonia and Amines in Hydrocarbon Flames:' Revue Composition on Thermal and Fuel NO, Production from
de L'lnstitut Francais du Petrole et Annuales Des Com- Pulverized Coal Combustion:' Central States Section,
bustible Liquides, 26(1): 95-108, 1973. The Combustion Institute Spring Meeting, Columbus,
1s Yasuro Takahashi, et al., "Development of Super-Low Ohio, April 5-6, 1976, Pittsburgh: The Combustion
N0,PM Burner," Mitsubishi Technical Bulletin No. 134. Institute, 1976.
Mitsubishi Heavy Industries, Ltd., 1979. 19 J. M. Levy, et al., Combustion Research on the Fate of

16 W. W. Habelt, "The Influence of Coal Oxygen to Coal Fuel-Nitrogen Under Conditions Of Pulverized Coal
Nitrogen Ratio on NO,, Formation," Presented at the Combustion. Final Task Report. Report no. PB-286 208
70th Annual AIChE Meeting, New York, November (EPA-60017-761165).Springfield, VA: National Technical
13-17,1977. Information Service, 1978.
CHAPTER 5

Steam Generation

high-pressure furnace, along with the basic


F)
D revious chapters have covered steam power-
plant cycles, and general engineering and
economic decisions related to the purchase of a
principles of thermally induced and pumped
circulation. The important aspects of the sepa-
steam-geneiating unit. Also discussed were ration of steam from the steam-water mixture
fuels and their evaluation for use in a boiler fur- entering the upper drum of a subcritical-
nace. The characteristics of coal ash were cov- pressure boiler and the general types of me-
ered in great detail to emphasize the significant chanical drum internals are covered.
influence of mineral matter 'in solid fuels on the
sizing and satisfactory operation of a large STEAM AS A WORKING FLUID
boiler. This earlier material, which also The theoretical amount of work that can be
"burned" the fuel and determined the products obtained from steam used in a prime mover is
of combustion, as well as presenting some of equivalent to the change in its total heat con-
the principles of combustion in a furnace, es- tent from its condition at the entering state to
tablished the theory behind the hardware. that at the exhaust state.
This chapter will cover steam generation by The efficiency of the prime mover in convert-
considering the r6les of the different compo- ing the heat energy to mechanical effort gov-
nents that make up a steam generator. erns the actual work obtained.
Included are the properties of steam used to For economic studies involved in the selec-
perform basic heat-balance and sizing calcula- tion and design of all steam- and power-genera-
tions. Also examined are the criteria involved tion equipment, it is necessary to understand
in the configuration of boiler pressure parts thoroughly the properties of steam, the use of
and auxiliaries as a function of .system pres- steam tables and the use of superheat. A brief
sures and temperatures. Generically intro- review of these fundamentals that apply to the
duced are the various parts of a reheat-cycle generation of steam will be helpful.
steam generator and an explanation of their
functioning as heat-absorbing apparatus. (More PROPERTIES OF STEAM
specific information in the following four Steam results from adding sufficient heat to
chapters will supplement and amplify these water to cause it to vaporize. This vaporization
descriptions.) Also presented is the vital func- occurs in two steps: first, by adding heat to the
tion of water-steam circulation in a modern water to raise it to the boiling temperature; sec-
COMBUSTION
Steam Generation

ond, by continuing the addition of heat to saturated steam, because vaporization is in-
change the state from water to steam. complete. The percentage of dry vapor by
When heated at average atmospheric pres- weight in the mixture is known as the quality
sure at sea level, each pound of water increases of the steam. Thus, with 3-percent moisture in
in temperature about 1F for each Btu added steam, the quality is 97 percent. The total heat
until 212F is reached. Additional heat does of wet steam is equal to the heat of the liquid
not cause the temperature to rise but, if con- plus the percentage of latent heat of vaporiza-
' tinued, results in boiling, and the water tion represented by the steam quality. The
changes its state from a liquid to a vapor. temperature of wet steam is the same as dry
When water is heated to the boiling point in a steam at the corresponding pressure.
closed vessel, the vapor released causes the Steam with a temperature higher than that of
pressure in the vessel to rise. With the rise in saturated steam at the same pressure is called
pressure, the temperature at which the water superheated. Accomplished by maintaining
boils also will rise. It has been determined ex- the pressure and adding heat to the steam after
perimentally that during the change in state of its removal from contact with water, superheat-
any substance from a liquid to a vapor at con- ing results in an increase in temperature and
stant pressure, the vapor in contact with its liq- volume. The total heat of superheated steam, or
uid will remain at constant temperature until its enthalpy, is equal to the total heat of dry
the vaporization has been completed. Thus, the saturated steam plus the heat of superheating.
temperature at which boiling occurs for any The term total heat is the general engineering
given pressure is constant and is called the sat- expression applicable to any steam condition,
uration temperature. This temperature is the whether wet, dry saturated, or superheated.
same for the water as it is for the vapor with Also known as the enthalpy of steam, it is the
which it is in contact. amount of heat that must be added to a unit
weight of water at 32F to produce the end.state
DEFINITIONS
under consideration.
The heat of the liquid is the heat used to raise The properties of steam have been the subject
a unit weight of water, normally one pound, of considerable research in many of the coun-
from 32F to the saturation temperature corre- tries of the world for many years, as stated in
sponding to a given pressure. Also called the Appendix D. The Mollier diagram, constructed
enthalpy of the saturated liquid, this is stated as an enthalpy-entropy chart to show the steam
in Btu per 1b or kilojoules per kilogram. tables graphically, is particularly useful in the .
The latent heat of vaporization is the heat analysis of .power-plant cycles. It visualizes the
added to a unit weight of water at saturation process of expansion of steam through the vari-
temperature to vaporize it completely and pro- ous sections of a steam turbine and helps in the
duce dry saturated steam. This is the enthalpy quick but approximate~solutionof many other
of evaporation or vaporization. thermodynamic problems. Appendix D tells
Dry saturated steam contains no moisture, how to obtain a C-E Mollier chart based on
and is at saturated temperature for the given steam propertigs calculated by C-E.
pressure. Its total heat content, or enthalpy of
SUPERHEATED AND SATURATED STEAM
the saturated vapor, is equal to the heat of the
liquid plus the heat of vaporization. The properties of superheated steam approx-
Steam which contains water in any form, imate those of a perfect gas. One important
either as minute droplets, mist, or fog, is called characteristic is the dependence of internal
wet steam. Wet steam may result from the en- energy on temperature; thus, the closer steam
trainment of water in boiling or from partial approaches a perfect gas, the better it does its
condensation. In either case, the total heat con- work. In addition, it contains no moisture, nor
tent of the mixture is less than that of dry can it condense until its temperature has been
COMBUSTION
Steam Generation

lowered to that of saturated steam at the same ture and pressure. There has been considerable
pressure. This particular characteristic is of development in the metallurgy of steel alloys
considerable value because, with the correct and in the manufacturing of both the tubing
amount of superheat, it is possible to.elimipa!e and the finished sections of the superheater.
condensation in steam lines and to decrease the These have made possible the design of super-
moisture in the steam turbine exhaust. heaters and reheaters for high-temperature and
With saturated steam, the heat available de- high-pressure boiler installations, as have im-
pends entirely upon pressure, while with provements in the art of welding. While those
superheated steam there is additional heat, installations which border on the limitations of
proportionate to the degree of superheat. This available materials may be more interesting,
additional heat is obtained through increased and perhaps more sensational, the large major-
expenditure of fuel, but the economic benefits ity is in the 750" to 1050F temperature range.
derived result in a net efficiency gain of con- Although commonplace, they represent the
siderable magnitude (seeChapter I).By using a places where the greatest savings are made.
comparatively small amount of superheat, it is A study of steam temperatures accompany-
possible to reduce moisture at exhaust condi- ing installations using 2400 psig throttle pres-
tions and to effect an increase in the percentage sures discloses that in the 1950's, 1050F was
of heat utilized. overwhelmingly selected as the primary tem-
perature. The trend since that time has been in
LIMITS OF STEAM TEMPERATURE AND
PRESSURE
the direction of 1000F primary temperature,
and is a well established-but surely not
The materials of superheater construction exclusive-pattern, Again, experience has
govern the practical limits of steam tempera- proved to be the arbiter. First, the initial cost of
1600-

1000-

Pressure (Ps~a)
Fig. 1 Variation in heat content (enthalpy) of steam as a function of pressure and temperature
..
boilers and turbines for the higher temperature heat is of utmost importance as the absence of
level proved to be less attractive as experience moisture in steam decreases friction losses and
accumulated. In addition, even though accu- erosion of turbine blades. If dry saturated steam
rate and conservative methods of superheater is used in a turbine, condensation rate in-
metal selection are used, problems do arise creases as the steam passes through the suc-
during sustained elevated temperatu-e opera- ceeding stages. The friction losses increase
tion because of the adverse effects of certain rapidly, because the condensate is actually
fuel constituents on unit availability. Some inert material which acts to check the speed of
owners therefore decided to reduce primary the turbine rotors. By using superheated steam,
steam temperatures while continuing to lower the condensation can be limited to a relatively
capital cost through larger units. Other utilities few stages in the turbine discharge end, thus
chose to take advantage of the thermal gain reducing windage loss and friction between
from higher primary steam temperature and rotor and vapor because of lower density and
maintained the established 1050Flevel. absence of moisture in the initial stages.
Units employing the nominal 3500-psi cycle Pipelines carrying steam lose heat by radia-
most commonly use 1000F superheat and tion. Thus, if steam entering a line is dry satu-
1000F reheat. About 30 percent of existing rated, any loss in heat will immediately cause
supercritical-pressure units have a second re- condensation which is usually discharged
heat stage at 1000F, justified by high fuel cost from the line through traps, and is frequently
and high anticipated load factor. wasted. So, in addition to the heat loss from
The curves in Fig. 1 show the variation in radiation, there is also loss of the heat in the
heat content of steam at different pressures. condensate. Of course, if the condensate is re-
Also included are the heat of the liquid and the turned to the hotwell, a portion of the heat in
temperature of saturated steam. The values the liquid is recovered. By adding a sufficient
used in plotting these curves are from the 1967 amount of superheat to the steam, it can be
ASME Steam Tables in Appendix D. When piped without condensation loss.
using the steam tables, or charts prepared from Using saturated steam in industrial pro-
them, note that pressure is stated as absolute cesses often results in minute quantities of
(psia). The steam gage on a boiler indicates the moisture in the steam at the point of use. The
pressure in the vessel above that of the atmo- use of dry saturated steam translates into a con-
sphere. For these conditions, the absolute pres- siderable savings in steam consumption and
sure is equal to atmospheric pressure plus gage frequently increased output. As explained pre-
pressure. Condensers and similar equipment viously, these advantages accrue from suffi-
operate under vacuum, and their gages usually ciently superheating the steam to overcome
read in inches of mercury (in. Hg) or kPa. For condensation in process-steam pipelines.
these conditions, absolute pressure is equal to The installation of a superheater in a boiler
atmospheric pressure minus vacuum. has the effect of reducing the amount of work
that must be done by the evaporative surfaces
REDUCING STEAM CONSUMPTION to produce the same power. In other words,
BY SUPERHEATING
installing a superheater has the effect of in-
Previous paragraphs have touched on the creasing plant capacity.
value of superheated as compared with satu-
rated steam. A further discussion will serve to
illustrate more clearly the manner in which FUNDAMENTALS OF
superheating reduces steam consumption, par- STEAM-GENERATOR DESIGN
ticularly in regard to industrial and marine-
boiler installations. Water-tube boilers range in capacity from
In the case of a steam turbine, high super- small low-pressure heating units generating a
COMBUSTION
Steam GenenUon

few thousand pounds of steam per hour to large cooled, such as with waterwalls, or uncooled,
reheat steam generators operating in the super- with a refractory lining.
critical pressure region and serving turbine- Furnaces developed originally from a need to
generators in the million kilowatt range. In fire pottery (4000 B.C.) and to smelt copper
slightly different terms, capacity may be mag- (3000 B.C.). Hastening and improving combus-
nified more than a thousand times from the tion by the use of bellows to blow air into the
smallest to the largest, pressure may extend furnace were used about 2000 B.C.
from just above atmospheric to values as high Closely associated with the furnace is the
as 5000 psig, and steam temperatures may vary corresponding steam boiler. Such boilers ap-
from the boiling point to a highly superheated pear to be of Greek and Roman origin and were
condition at 1050F or above. employed for household services. The Pom-
What are the common elements in boilers peiian water boiler, incorporating the water-
having such a diversity of design parameters? tube principle, is one of the earliest recorded
To answer this question it may be well to define instances of boilers doing mechanical work
the primary function of a boiler which is simply (130 B.C.). It sent steam to Hero's engine, a hol-
to generate steam at pressures above the at- low sphere mounted and revolving on trun-
mospheric. Steam is generated by the absorp- nions, one of which permitted the passage of
tion of heat produced in the combustion of fuel. steam, which was exhausted through two right-
In some instances, such as waste-heat boilers, angled nozzles that caused the sphere to rotate.
heated fluids serve as the heat source. This was the world's first reaction turbine.
en era ti on of steam by heat absorption from For the next 1600 years, furnaces in general
products of combustion suggests that a boiler and waterwall furnaces in particular were es-
must have a pressure-parts system to convert sentially a neglected technology. This can be
incoming feedwater into steam; a structure partly ascribed to the fact that steam as a work-
within which the combustion reaction may ing fluid had no application until the invention
take place, at the same time facilitating heat of the first commercially successful steam
transfer and supporting boiler components; a engine by Thomas Savery in 1698. 1n 1705,
means of introducing fuel and removing waste Newcomen's engine followed and by 1711, this
products; and controls and instruments to reg- engine was in general use for pumping water
ulate and monitor operation. A boiler designer out of coal mines. Self-regulating steam valves
has to work with such things as drums, headers were incorporated in 1 7 13.
and tubing, which make up the pressure-parts Many varieties of firetube boilers, were in-
system and enclose the furnace in which com- vented in the second half of the 18th century,
bustion takes place; burners and related fuel culminating with the Scotch marine boiler. As
and ash-handling equipment; and fans to sup- the name implies, in the firetube boiler the
ply combustion air and exhaust waste gases. tubes may be considered to be a component part
Various types of instruments and controls link of the furnace, with the combustion process
these elements together in a physical and an completed within the tube bundles. But such
operational sense. units were limited to operating pressure of
about 150 psig, because of available steel-plate
A BRIEF HISTORY OF STEAM GENERATION thicknesses. The development of the modern
A furnace for firing a fossil fuel is a device for water-tube furnace for steam generation at
generating controlled heat with the objective of higher pressures and in larger sizes than avail-
doing useful work. The work application may able with firetube boilers is the subject of
be direct, as with rotary kilns, or indirect, as in the various chapters of this book which cover
boilers for industrial or marine use, or for the central-station steam generators, industrial-
generation of electric power. A further differ- type boilers, and fluidized-bed and marine
entiation is whether the furnace enclosure is boilers, respectively.
COMBUSTION
Steam GeneraUon

BOILER OUTPUT reduce the gas temperature leaving the unit to


The output or capacity of a steam generator is a level that satisfies the requirement for high
either expressed in pounds of steam per hour or thermal efficiency and at the same time is suit-
in the power output of a turbine generator in able for processing in the emission-control
those cases where a single boiler provides the equipment downstream of the boiler
entire steam supply for an electric generating BOILER EFFICIENCY
unit. Neither term is a true measure of the ther- A diagram is one of the best ways to com-
mal energy supplied by the boiler. prehend the significance of boiler efficiency as
Actual boiler output in terms of heat energy it is affected by the heat absorption pattern in a
depends on several factors other than quan- steam generator. Fig. 2 shows the distribution
_ tity of steam. These include temperature of feed- of heat energy in a reheat boiler for utility use. It
water entering the economizer, steam pressure is apparent that the primary source of heat is
and steam temperature at the superheater out- the fuel (supplemented by thermal energy from
let, and the quantity, temperature and pressure fans, pumps, and pulverizers), but that the pre-
of steam entering and leaving the reheater. heated air for combustion adds directly to the
Similarly, because turbine and generator ef- total heat in the furnace. The amount of heat in
ficiencies affect the boiler output, the generator the preheated air corresponds to that extracted
output in kilowatts is not entirely a true mea- from the exhaust gases by the air heater. This
sure of the energy output of the boiler alone. concept is discussed further i n both this chap-
These elements vary with the size and pur- ter and Chapter 6.
pose of the power plant in which the boiler is Of the total heat entering the furnace, the
installed. A large central station in which high major portion is absorbed as sensible and latent
thermal efficiency is a primary requisite has heat of vaporization in the heating surfaces of
many more refinements and auxiliaries than a the economizer, furnace, superheater and re-
small heating plant in which minimum capital heater. This absorbed heat represents the boiler
investment may be an important criterion. No output in the form of superheated and reheated
matter how many of these elements may be steam. Losses which account for the remainder
present, however, the boiler designer must in- of the heat supplied to the furnace consist of the
tegrate them so that the boiler as a whole can heat contained in the flue gas leaving the air
function as a carefully adjusted, complex sys- heater (principally the sensible heat of the gas
tem which is capable of efficient operation over- and latent heat in the moisture from the fuel),
a wide load range. smaller losses from less-than-perfect combus-
STEAM-GENERATOR FUNCTIONS tion, and radiation from the boiler and its ancil-
In addition to its primary function of evapo- laries. A description of these losses and how
rating water to steam at high pressure, the they are calculated is giyen in Chapter 6.
modern boiler has to HEAT-ABSORBING SURFACES
produce that steam at exceptionally high pur- The objective of the boiler designer is to ar-
ity, using stationary mechanical devices to re- range heat-transfer surface and fuel-burning
move impurities in the boiling water equipment to optimize thermal efficiency and
superheat the steam generated in the unit to a economic investment. One may select from wa-
specified temperature, and maintain that tem- terwalls, superheaters, and reheaters, each of
perature over a designated range of load which absorbs heat from the furnace gas as it
re-superheat (reheat) the steam which is re- performs its respective function of heating
turned to the boiler after expanding through water to the saturation point and of superheat-
the high-pressure stages of the turbine, and ing and resuperheating steam. Also to be cho-
maintain that reheat temperature constant over sen are air heaters and economizers to recover
a specified range of load . heat from the furnace exit gases to preheat com-
COMBUSTION
Stwm Generation

bustion air and increase the temperature of cycles: the single-reheat 1800 psig cycle at
incoming feedwater. 5-percent overpressure; the 2400 psig, 1000F
The boiler designer must proportion heat- cycle with single reheat to 100o0F,again at 5-
absorbing and heat-recovery surfaces to make percent overpressure (2620 psig at the-super---
best use of the heat released by the fuel. Wa- heater outlet); and a single-reheat and a dou-
terwalls, superheaters, and reheaters are ex- ble-reheat supercritical cycle, both at 1000F at
posed to convection and radiant heat, whereas the turbine throttle. Such heat-absorption pro-
convection heat transfer predominates in air files will vary with entering feedwater tempera-
heaters and economizers. ture, cold-reheat temperature, and relative size
The relative amounts of such surfaces vary of furnace and economizer.
with the size and operating conditions of the FACTORS INFLUENCING BOILER DESIGN
boiler. A small low-pressure heating plant with
In addition to the basics of unit size, steam
no heat-recovery equipment has quite a differ-
ent arrangement from a large high-pressure pressure, and steam temperature, the designer
unit operating on a reheat regenerative cycle must consider other factors that influence the
and incorporating heat-recovery equipment. overall design of the steam generator.
Fig. 3 shows how the proportion of energy FUELS
absorbed varies with different types of boilers. Coal, although the most common fuel, is the
In a heating-plant boiler operating with a most difficult one to burn. The many types of
minimum ,of feedwater heating and no coal and their characteristics are covered thor-
superheater it is evident that most of the heat oughly in Chapter 2 and Appendix A.
absorbed is utilized in evaporating water to As described in Chapter 3 , the ash in coal
steam. In a large reheat unit with feedwater consists of a number of objectionable chemical
heaters and heat-recovery equipment, heat for elements and compounds. The high percentage
evaporation is comparatively small, whereas of ash that can occur in coal has a serious effect
heat for superheating and reheating accounts on furnace performance.
for more than half of the total input. ' At the high temperatures resulting from the
Fig. 4 is a plot of temperature vs. heat absorp- burning of fuel in the furnace, fractions of ash
tion for four different high-pressure steam can become partially fused and sticky. Depend-

Fig. 2 .Steam generator energy flow

n l)l)
C'A'!
COMBUSTION
Steam Generation

ing on the quantity and fusion temperature, the water-cooled tubes to form complete metal cov-
partially fused ash may adhere to surfaces con- erage of the furnace enclosure. Similarly, areas
tacted by the ash-containing combustion gases, outside of the furnace which form enclosures
causing objectionable buildup of slag on or for sections of superheaters, reheaters and
bridging between tubes. Chemicals in the ash economizers also use either water- or steam-
may attack materials such as the alloy steel cooled tube surfaces. Present practice is to use
used in superheaters and reheaters. tube arrangements and configurations which
In addition to the deposits in the high- permit essentially complete elimination of re-
temperature sections, the air heater (the coolest fractories in all areas that are exposed to high-
part of a boiler) may be subject to corrosion and temperature gases.
plugging of gas passages from sulfur com- Waterwalls usually consist of tangent or
pounds in the fuel acting in combination with nearly tangent vertical tubes connected at top
moisture present in the flue gas. and bottom to headers. These tubes receive
their water supply from the boiler drum by
THE FURNACE
means of downcomer tubes connected between
Heat generated in the combustion process the bottom of the drum and the lower headers.
appears as furnace radiation and sensible heat The steam, along with a substantial quantity of
in the products of combustion. Water circulat- water, is discharged from the top of the water-
ing through tubes that form the furnace wall wall tubes into the upper waterwall headers and
lining absorbs as much as 50 percent of this then passes through riser tubes to the boiler
heat which, in turn, generates steam by the drum. Here the steam is separated from the
evaporation of part of the circulated water. water, which together with the incoming feed-
Furnace design must consider water-heating water, is returned to the waterwalls through the
and steam generation in the wall tubes as well downcomers.
as the processes of combustion. Practically all Tube diameter and thickness are of concern
large modern boilers have walls comprised of from the standpoints of circulation and metal

Q) ";-5- 5 Sensible Heat in Feedwater

.$ $ $ EZ3 Latent Heat of Evaporation


p sgs
:
-
.- -a,
.-
oL
$5 55 E
HSuperheat
~ S B ~ B
~ E C E ~ Em R e h e a t
8 2 0-J ~g l?g $
:
Heating Oil 60,000 125 Sat - 212
I I

V l t I I I I I I I J

0 10 20 30 40 50 60 70 80 90100
Percent Absorbed
Fig. 3 Heat absorption by various types of subcritical-pressureboilers
COMBUSTION
Steem Generation

temperatures. Thermo-syphonic (also called of the radiant type, can then be used. Fig. 5
thermal or natural) circulation boilers gener- shows an-arrangement of such platen and panel
ally use larger diameter tubes than positive surfaces. A relatively small number of panels
(pumped) circulation or once-through boilers. are located on horizontal centers of 5 to 8 feet to
This practice is dictated largely-by the need for permit substantial radiant heat absorption.
more liberal flow area to provide the lower Platen sections, on 14" to 28" centers, are
velocities necessary with the limited head placed downstream of the panel elements; such
available. The use of small-diameter tubes is an spacing provides high heat absorption by both
advantage in high-pressure boilers because the radiation and convection. (These modes of heat
lesser tube thicknesses required result in lower transfer are discussed further in Chapter 6.)
outside tube-metal temperatures. Such small- Convection sections are arranged for essen-
diameter tubes are used i n recirculation boilers tially pure counterflow of steam and gas, with
in which pumps provide an adequate head for steam entering at the bottom and leaving at the
circulation and maintain the desired velocities. top of the pass, while gas flow is opposite. As
Circulation of water and steam in both sub- explained in Chapter 6, this arrangement al-
critical and supercritical boilers is discussed lows a maximum mean temperature difference
further in other sections of this chapter. between the two media and minimizes the
SUPERHEATERSAND REHEATERS heating surface in the primary sections.
The function of a superheater is to raise the Metallurgy
boiler steam temperature above the saturated Superheaters and reheaters designed for high
temperature level. As steam enters the super- pressures and temperatures above 1000F
heater in an essentially dry condition, further require high-strength alloy tubing. Besides
absorption of heat sensibly increases the steam selection of materials for strength and oxida-
temperature. tion resistance, the use of high steam pressure
The reheater receives superheated steam requires very thick walls in all tubing subject to
which has partly expanded through the tur- steam pressure. Such thick tubes will have high
bine. As described earlier, the r6le of the re- outside metal temperatures and, because chem-
heater in the boiler is to re-superheat this steam ical action is accelerated at high temperatures,
to a desired temperature. the tube metal is more likely to experience ex-
Superheater and reheater design depends on ternal corrosion. This is of particular concern
the specific duty to be performed. For relatively when burning fuels containing objectionable
low final outlet temperatures, superheaters impurities. The designer takes account of such
solely of the convection type are generally conditions in selecting material and tube sizes.
used. For higher final temperatures, surface See-Chapters 3, 6, and 17 for information relat-
requirements are larger and, of necessity, ing to corrosion from coal ash, selection of
superheater elements are located in very high superheater and reheater surface, and mater-
gas-temperature zones. Wide-spaced platens or ials used for commercial construction of this
panels, or wall-type superheaters or reheaters equipment.

400 400 400


Econ Furnace SH -RH Econ Furnace SH-RH Econ Furnace SH -AH Econ Furnace SH-RH
Heat Absorption,Percent of Total
Fig. 4 Heat absorption variation with cycle pressure

5-9
ECONOMIZERS gas and water results in maximum mean tem-
Economizers help to improve boiler effi- perature difference for heat transfer. (See Chap-
ciency by extracting heat from flue gases dis- ter 6 for more on this temperature difference.)
charged from the final superheater section of a Upward flow of water helps avoid water ham-
radiantheheat unit, or the evaporative bank of mer, which may occur under some operating
a non-reheat boiler. In the economizer, heat is conditions. To avoid generating steam in the
transferred to the feedwater, which enters at a economizer, the design ordinarily provides
temperature appreciably lower than that of exiting water temperatures below that of satu-
saturated steam. Generally, economizers are ar- rated steam during normal operation.
ranged for downward flow of gas and upward As shown in Fig. 5, economizers of a typical
flow of water. utility-type boiler are located in the same pass
Water enters from a lower header and flows as the primary or horizontal sections of the
through horizontal tubing comprising the heat- superheater, or superheater and reheater, de-
ing surface. Return bends at the ends of the tub- pending on the arrangement of the surface.
ing provide continuous tube elements, whose Tubing forming the heating surface is gener-
upper ends connect to an outlet header that is ally low-carbon steel. Because steel is subject to
in turn connected to the boiler drum by means corrosion in the presence of even extremely
of tubes or large pipes. Tubes that form the low concentrations of oxygen, it is necessary to
heating surface may be plain or provided with provide water that is practically 100 percent
extended surface such as fins. Frequently, they oxygen-free. In central stations and other large
are arranged in staggered relationship in the plants it is common practice 'to use deaerators
gas pass to obtain high heat transfer and to for oxygen removal.
lessen the space requirements. Small low-pressure boilers may have econ-
Designing the economizer for counterflow of omizers made of cast iron, which is not as sub-

Superheater Junction Header


Platen-Type Superheater or Reheater

Fig. 5 Arrangement of superheater, reheater and economizer of a pulverized-coal-fired steam-generator


COMBUSTION
Stwm Gemwallon

ject to oxygen corrosion. However, the design heaters in the pulverization process. Some of
pressure for this material is limited to approx- the available types of air heaters are described
imately 250 psig. Whereas cast-iron tubes find in Chapter 14. Establishing inlet air and outlet
little application today, cast-iron fins shrunk gas temperatures to minimize corrosion of air-
on steel tubes are practical and can be used at heater surface is considered in Chapter 6 .
any boiler pressure. In sizing air heaters, note that, while the cost
of pressure parts of a unit increase as the steam
AIR HEATERS
pressure increases, the air-heater cost is inde-
Steam-generator air heaters have two impor- pendent of pressure. Consequently, it is not dif-
tant and concomitant functions: they cool the ficult to justify the cost of larger air heaters on
gases before they pass to the atmosphere, boilers operating at higher pressure levels.
thereby increasing fue1;firing efficiency; at the
same time, they raise the temperature of the in- CONTROL OF STEAM TEMPERATURE
caming air of combustion. Depending on the Maintaining turbine efficiency over a wide
pressure and temperature cycle, the type of load range and avoiding fluctuations in turbine
fuel, and the type of boiler involved, one of the metal temperatures require- constant primary
two functions will have prime importance. steam and reheat temperatures over the antic-
For instance, in a low-pressure gas- or oil- ipated operating load range. To satisfy this re-
fired industrial or marine boiler, combustion- quirement, a boiler must be equipped with
gas temperature can be lowered in several means for controlling and maintaining such
ways-by a boiler bank, by an economizer, or steam temperatures over the desired range. If
by an air heater. Here, an air heater has princi- uncontrolled, steam temperatures will rise as
pally a gas-cooling function, as no preheating the steam output increases. This is particularly
is required to burn the oil or gas. characteristic of convection-tyge superheaters,
If the boiler is a high-pressure reheat unit which account for the major share of heat
burning a high-moisture subbituminous or lig- absorbed by the superheater.
nitic coal, high preheated-air temperatures are To provide an economical installatidn that
needed to evaporate the moisture in the coal be- operates at minimum metal temperatures,
fore ignition can take place. Here, the air- superheaters and reheaters should be designed
heating function becomes primary. Without to provide exactly the specified steam tempera-
exception, then, large pulverized-coal boilers ture at maximum output. An optimum design
either for industry or electric-power generation is one in which all the gas leaving the furnace
use air heaters to reduce the temperature of the passes over all the installed superheater and
combustion products from the 600"-800F reheater .surface at 100 percent boiler rating,
level to final exit-gas temperatures of 275F to without need of either superheater or reheater
350F. In these units the combustion air is spray-water. To satisfy this the means of con-
heated from about 80F to between 500F to trol must maintain full steam andkeheat tem-
750F, depending on coal calorific value and peratures over the total control range.
moisture content.
TECHNIQUESOF STEAM-TEMPERATURECONTROL
In theory, only the primary air- that used to
actually dry the coal in the pulverizers -must Steam-temperature control devices must be
be heated. Ignited fuel can burn without pre- incorporated in the original design of a boiler
heating the secondary and tertiary air. But there firing system, in the superheater or reheater
is considerable advantage to the furnace heat- circuitry, or in arrangements of dampers for gas
transfer process from heating all the combus- bypass. The following are the most frequently
tion air; it increases the rate of burning and used means of control.
helps raise flame adiabatic temperature. Firing-system manipulation, in which the ef-
Chapter 11 presents the various uses of air fective release of heat from the fuel-burning
COMBVSnoN
Steam G e ~ r a t l o n

process is made to occur at a higher or lower Desuperheating Control


portion of the furnace; this affects the heat ab- Desuperheating is the reduction of tempera-
sorption pattern in the furnace and, con- ture of superheated steam accomplished by
sequently, the furnace exit-gas temperature. spraying water into the piping either ahead of
Desuperheating by water sprayed into piping or behind a superheater or reheater section. To
ahead of, in between, or following superheater minimize the amount of water used in the pro-
. or reheater sections. cess, most large boiler installations use de-
Recirculation of gas, in which a portion of the superheating in combination with one of the
combustion gases are brought back to the fur- other temperature-control methods. This is be-
nace and are added to the "once-through" flow cause of water-treatment and pumping-power
of gas passing over superheater and reheater. considerations.
Rising temperature with increasing output
Gas bypass around some of the installed heat- characterizes the performance of a superheater
ing surface that is "excess" in certain parts of or reheater which receives its heat by convec-
the load range; the purpose is to prevent such tion from gas flowing over it. With desuper-
surfaces from absorbing heat from the bypassed heating control only, the superheater must be
gas so that the desired steam temperature is designed for full temperature at some partial
achieved without using any other means. load. As a result, there is excessive heat-
Subsequent sections describe in more detail transfer surface, with corresponding excess
these different methods of control, used in one temperatures, at higher loads. A desuperheater
form or another by all manufacturers. can be used to remove this excess in tempera-
Firing-System Manipulation ture. If located beyond t h e outlet of t h e
superheater, a desuperheater will condition
There are two common ways to vertically the steam before it is passed along to the tur-
displace the zone of highest heat release in a bine. Although this arrangement is practical
furnace to achieve a change in the outlet gas for steam temperatures of 825F and lower, the
temperature. The first, often used with front- preferred location of the desuperheater, espe-
or rear-wall fixed burners, is to insert or with- cially for temperatures above 850Ef is between
draw levels of burners as a function of load; sections of the superheater. In such interstage
removing lower levels and firing through the installations, the steam is first passed through
remaining upper levels effectively moves the one or more primary superheating sections,
high-heat-release zone higher in the furnace. where it is raised to some intermediate temper-
This method necessitates backup by spray de- ature. It is -then passed through the desuper-
superheating for vernier control. heater and its temperature controlled so that,
Tilting fuel and air nozzles, used in corner after continuing through the secondary of final
(tangential) firing systems are a positive means stage of superheating, 'the required constant
of controlling outlet gas temperature smoothly outlet temperature is maintained.
without cycling equipment iri and out of Desuperheating of reheat steam is generally
service. Superheater or reheater steam temper- not desirable because of the deleterious effect
atures are regulated by changes in nozzle posi- on plant heat rate. To evaporate the water that is
tion. Directing the flame toward the upper part added to the reheat flow (usually ahead of the
of the furnace maintains a higher gas outlet point where the reheat steam is introduced into
temperature during light load-or when the the steam generator) requires firing additional
walls are clean-than is the case if the flame fuel in the boiler. There also results an in-
were directed horizontally into the furnace. At creased condenser loss for the same primary
higher loads, or when the walls are coated with steam flow. Consequently, reheat outlet temper-
ash or slag, nozzles can be positioned horizon- ature is best controlled using some means other
tally or angled downward. than water spray, unless it is unavoidable.
CO~nsnON
Steam Gomation

The heat given up by the steam during a in heat absorption. The heat available to the
temperature reduction is picked up by the cool- sup~rheaterand reheater increases, as does the
ing water i n three steps. First, its temperature is quantity of gas passing over the surfaces. Both
raised to that of saturated water; then the water of these factors increase steam tempefature.
is evaporated; and finally, the steam thus gen- Bypass-Damper Control
erated is raised to the final condition of tem-
perature at the desuperheater outlet. By setting An arrangement of bypass dampers i n a rela-
up a simple heat balance, it is possible to de- tively cool gas zone downstream of superheater
termine quickly the quantity of water required or reheater sections provides an acceptable
to desuperheat for any given set of conditions. means for maintaining constant steam temper-
Desuperheaters are either the indirect or di- ature; automatic controllers adjust the dampers
rect (mixing) type. The water available for use to provide the required degree of temperature
as the temperature-regulating medium governs control. If load changes are abrupt, frequent,
the selection for any specific installation. This and of considerable magnitude, there is likely
is not so important with the indirect (non- to be some hunting in positioning the damper.
contact) type, where a tubular heat exchanger is As there is also some lag in the response to
used, since the steam to be desuperheated is temperature changes, final temperature varies
separated from the cooling medium, and the over a plus or minus 10F range. This variation
heat is transferred through the separating tube is characteristic where the regulation of steam
wall. In the direct type, however, the cooling temperature depends solely on control of gas
medium is injected into, and mixed with, the flow through bypass-damper operation.
superheated steam to reduce the temperature. During the early damper-opening periods,
To be used for this purpose, the desuperheating the gas flow rapidly increases and then falls off
water must be of condensate quality, containing as the full-open position is approached (see
very few solids. Fig. 6). The data were taken from an operational
In industrial or marine practice, to help re- test during which the capacity of the unit was
duce costs, non-contact desuperheating coils held constant and the effect of variable by-
may be installed in one of the boiler drums. The pass-damper opening against steam temper-
principal objection to this design is its rela- ature was recorded. There is an increase of 15F
tively low capacity. Through necessity, all in steam temperature for a change in damper
parts must be sufficiently small to be con- from 100 percent to 40 percent open. However,
veniently handled through the boiler-drum the temperature increase from 40 percent open
access opening. The coils must therefore be to fully-closed damper is 50F. It is apparent
compact, and made in sections to permit as- -
sembly and installation within the drum space
limitations. If large or bulky, and if the number
of parts are many, the assembly of the coils may
become almost impossible.
Gas Recirculation
In this temperature-control means, described
further in Chapter 6, a portion of the flue gas is
diverted from the main stream at a point follow-
ing the superheater and reheater (usually be-
tween the economizer .outlet and the air-heater Percent Damper Opening
inlet) and is recirculated to the furnace. The gas
passes through a recirculating fan and mixes ~ i g6. Chart illustrating steam temperature
with-the gas in the furnace, causing a reduction change with respect to damper opening
COMBVSRON
Steam Generation
-

that sensitive responses, resulting in more uni- point, the major portion of the evaporator oper-
form temperatures, are obtainable when the ates at a saturation temperature established by
regulator operation is confined to the early the pressure of the furnace-wall system. At
stages of damper opening. In other words, any supercritical pressures, the wall system has no
changes in capacity that would normally re- fixed fluid temperature; a continuous tempera-
quire the bypass damper to operate above 50 ture increase occurs in the furnace-cooling
percent open should also incorporate another fluid between the furnace-wall inlet and outlet.
means of control so as to keep within the sensi- The most critical circulating system in a large
tive control range. boiler is that of the furnace walls; they are at the
same time the area of highest heat-absorption
rates and a major structural component of the
WATERISTEAM CIRCULATION unit. This present section, and Chapter 7, dis-
The t e r n circulation, as applied to steam cuss the various types of furnace-wall circula-
generators, is the movement of water, steam, or tion that the designer can use, their differences,
a mixture of the two, through heated tubes. The and the advantages of each.
tubes can be in furnace walls, boiler banks, CIRCULATION IN FURNACE WALLS.
economizers, superheaters, or reheaters. Ade-
quate circulation results in the cooling fluid There are four types of furnace-wall circula-
absorbing heat from the tube metal at a rate tion systemsused for present-day steam genera-
which maintains the tube temperature at or tors. Their application depends on pressure,
below design conditions. Adequate circulation unit size and planned operating mode, required
also keeps the tube within the other physical maneuverability, and the manufacturer's de-

.
and chemical limitations required by the inside sign philosophy. Fig. 7 shows the four types
and outside environment. In boilers, circula- diagrammatically; they are:
tion through the varied systems of heated tubes thermally induced, also called thermal,
can involve just the flow entering and leaving thermo-syphonic, or "natural", with inherent
the system (called the once-through flow), a recirculation
means of recirculating the fluid, or some com- .thermally induced, pump-assisted, with

.
bination of these two circulation concepts. recirculation
Steam generators of all manufacturers have once-through, with no recirculation
similar pressure-part systems. For any given
once-through. with superimposed pumped
steam-power cycle, the economizer contains
recirculation
fluid in the lowest temperature range, with its
inlet temperature being that leaving the top Because of the influence that pressure has on
feedwater heater. The superheater contains the behavior of water in the steam-generating
fluid in the highest temperature range, with process, it is necessary to distinguish between
its outlet temperature essentially fixed. The the different circulation systems at subcritical
evaporator contains the middle range of fluid and supercritical pressures.
temperatures. THERMAL CIRCULATION
Circulation in economizers, superheaters The first type, thermal circulation, is a recir-
and reheaters is most commonly of the once- culating system at subcritical pressure. It de-
through type. The furnace-wall system of pends on the static-head difference between
high-pressure units uses either once-through the water in the downcomers (usually un-
or recirculation Qow, or some combination. By heated) and the steam-water mixture in the
convention, these modes of circulation have heated generating tubes to produce circulation
become terms of reference for the complete and maintain sufficient mass velocity and mix-
steam generating unit. ture quality for adequate furnace-wall cooling.
At pressures below the 3208-psia critical Circulation begins only after heat is applied to
the vertical generating tubes and, when once duced by one or more low-pressure-differential
begun, is proportional to the amount of heat pumps located in the downtake system, to sup-
locally supplied. To maintain the overall ws- plement the thermal head. The thermal-
tern pressure drop as low as possible, boilers circulation circuitry may now include pump-
using this principle for cooling the furnace en- isolating valves and, in many designs in this
closure need large flow areas in downcomers, category, waterwall-circuit flow-control ori-
supply tubes, generating tubes, and relief tubes fices. The orifices are varied in size to insure
to the drum. uniform circulation under changing furnace
Thermal-circulation boilers are the domi- conditions. In general, waterwall tubes of boilers
nant choice of all manufacturers for low and having positive-circulation systems of the type
medium subcritical-pressure operation, as they described are smaller in diameter than those of
have been since the early development of the thermal circulation units; in the thermal units,
water-tube boiler. Theoretically, thermal circu- large tubes minimize friction losses and take
lation can be used at any waterwall operating maximum advantage of the limited head pro-
pressure below the critical pressure of 3208 vided by density difference.
psia, as long as there is some finite density dif- Pump-assisted thermal circulation units find
ference between the water in the downcomers particular application at the high subcritical-
and the saturated steam-water mixture in the pressure levels, where there is reduced fluid
heated circuits. Practically, the maximum static-head energy available to recirculate the
furnace-wall pressure that has been used is furnace-wall fluid. The reduced driving force is
about 400 psi below the critical pressure. of concern where a very large number of paral-
Later in this chapter are discussed the prin- lel tube circuits makes even heat distribution a
ciples of thermal circulation including some problem, such that some tubes can overheat un-
of the mathematical bases for subcritical- der certain operating conditions; also, if there
circulation calculations in this mode. Also is less circulation energy available, it limits the
covered is the design background for different boiler maneuverability.
types of drum internals used to separate steam Note that the only difference between the
from the recirculating water so that it can pro- basic thermally induced boiler and the
ceed on to the superheater as a heatable vapor. pump-assisted is in the circulating systems.
Otherwise, both types share the same kind of
PUMP-ASSISTEDTHERMAL CIRCULATION firing methods, means of superheating and
This type of subcritical-boiler recirculation reheating and controlling superheater and
system uses an external mechanical force, pro- reheater outlet temperatures, heat-recovery

Thermal Thermal, Pump-Assisted Once- Once-Through with

Furnace Furnace
Drum Walls Walls

Circ.
Pump Vessel

Fig. 7--Steam-generatorcirculationsystems
equipment and structural support. A C-E tion of the working fluid is provided whenever
developed positive-circulation design is de- the unit is fired, the once-through cooling flow
scribed in Chapter 7. is essentially proportional to the firing rate and
is inadequate to provide waterwall tube protec-
ONCE-THROUGH CIRCULATION
tion during startup and at low loads. That is, in
In a once-through boiler, there is no recircu- an elemental once-through unit, the design
lation of water within the unit. In elemental does not permit internal recirculation; never-
form, the boiler is merely a length of tubing theless, a through flow has to be established at
through which water is pumped. Heat is least in the'highly heated portions of the cir-
applied, and the water flowing through the cuitry. The operation of the power-plant feed-
tube is converted into steam and superheated to water system, including the boiler feed pump,
the desired temperature at the outlet. In actual is needed to produce the once-through flow,
practice, the single tube is replaced by numer- and suitable means must be provided to dis-
ous small tubes arranged to provide effective pose of the circulated flow without incurring
heat transfer similar to the arrangement in loss of heat or working fluid. This is normally
drum type boilers. Note that the economizer done with a steam-turbine bypass system.
and superheater operate on the once-through The once-through design has been success-
principle even in drum-type boilers. The fun- fully applied to both the high-subcritical and
damental differences lie only in the heat- supercritical pressure ranges. In this connec-
absorbing circuits or evaporating portion of the tion, it is useful to point out some differences in
unit. The word evaporating includes boiling boiler operation in the two pressure regimes.
at subcritical pressures and heating into the
compressible vapor region at supercritical Supercritical Versus Subcritical
Once-Through Operation
pressures.
In the typical reheat unit, the evaporating When water is heated at a pressure above
surface consists of waterwalls which form the 3208 psia it does not boil. Therefore, it does not
major part, if not all, of the furnace enclosure. have a saturation temperature, nor, does it pro-
The principal distinguishing features of a once- duce a two-phase mixture of water and steam.
through boiler, then, are related to the design Instead, the fluid undergoes a transition in the
and operation of the waterwalls. enthalpy range between 850 and 1050 Btullb
The distinctive design requirements stem (Fig. 1).In this range its physical properties (in-
partly from the temperatures that may exist in cluding density, compressibility and viscosity)
the waterwalls of a once-through unit, in which change continuously from those of a liquid
there is a considerable rise in temperature from (water)to that of a vapor (steam). The tempera-
waterwall inlet to outlet. Even greater differ- ture rises steadily; the specific heat and rate of
ences may exist during start-up or upset condi- rise varies considerably during the process.
tions. And there can be significant differences The nature of supercritical steam generation
between adjacent individual tubes. The fur- rules out the use of a boiler drum to separate
nace design and construction must take into steam from water; drumless units are universal
account the relative thermal expansions pro- for supercritical operation.
duced by these temperature differences in var- During the boiling process at subcritical
ious parts of the furnace and between tubes, pressure, individual molecules break out of the
casing, and buckstays. The first distinguishing dense liquid clusters and, as the physical sur-
haracteristic of once-through boilers, then, is roundings permit, form a separate vapor phase.
iheir furnace-wall temperature patterns. At supercritical pressure, as heat is added to
The second principal characteristic concerns the liquid, the clusters gradually divide into
means of preserving furnace tubing integrity. smaller clusters and the spacing of the
Unlike a drum-type boiler, in which circula- molecules gradually becomes less dense until
COMBUSTION
Steam Generation

the transition to the wide-spaced, random ar- furnace wall to operate at pressure above the
rangement of a vapor is completed. 3300 psig level while allowing the superheater
The most important result of this situation is to operate at a subcritical pressure level during
that all impurities in the feedwater must either start-up. The system also lends itself to vari-
be deposited in the furnace and superheater able-pressure operation through the super-
surfaces or must be carried over into the tur- heater and steam turbine over any specified
bine. As described in Chapter 20 only the best load range. Chapter 7 presents more detail on
possible feedwater treatment can be considered such start-up equipment.
acceptable. Because blowdown from the drum
and furnace walls (as is possible with drum- COMPARISON OF BOILER DESIGNS
type units) is not available to remove impurities FOR SUBCRITICAL STEAM CYCLES
from the system, not only the makeup water but Turbines for 2400 psig operation are usually
also a portion of the condensate must be puri- designed for steam pressures of 2520 psig at the
fied. Otherwise the concentration of impurities turbine throttle-a condition of 5 percent over-
in the system will build up gradually until in- pressure. A boiler-drum operating pressure of
tolerable conditions or tube failures force an between 2750 and 2850 psig is required to
outage for cleaning or repairs. allow for pressure drop through the super-
More information on the development of the heater and the main steam line. As indicated
once-through boiler and its operation at both earlier, with the densities of steam and water
subcritical a n d supercritical pressures can be rapidly approaching each other above this
found in the 1 9 6 7 edition of this text.' pressure level, it represents a reasonable
limit for a drum-type boiler incorporating
ONCE-THROUGH FLOW
WITH SUPERIMPOSED RECIRCULATION
steam separation and recirculation.
An advantage of drum-type units over once-
This fourth common type of boiler circula- through designs is their ability to operate with
tion, used for supercritical service, involves the marginal quality feedwater. Steam separation
superposition of pump-assisted circulation, as permits elimination of undesirable solids by
previously described, on the once-through blowdown without affecting steam purity. The
flow. Superposition means that the pumps are tendency of solid constituents to remain with
permanently installed, but with a local bypass the water phase makes this possible.
system, to allow them to be in-line or in the Because water is converted completely to
bypassed position as a function of load. The steam in a once-through unit, solids in the
pumps then operate to assist circulation as re- feedwater must ultimately deposit in either the
quired, on start-up and at low loads. boiler, the superheater, or the turbine. Al-
By adding to the once-through flow as neces- though high-quality makeup water can be
sary, the boiler-water circulating pumps act to provided consistently, the condenser always
protect the furnace-wall system from excessive represents a possible threat of contamination.
metal temperatures. At loads that are between Demineralization of the condensate is neces-
about 60 percent and 100 percent. of maximum sary in systems with once-through boilers if
continuous rating, the pumps are no longer power production is not to be curtailed during
needed for wall-tube protection, and the unit condenser leaks.
operates on once-through flow. The furnace-wall tubes of the majority of
With this type of unit, it is usual to supply a coal-fired, drum-type, steam generators are vir-
start-up system that contains shutoff and tually always some type of carbon steel. Its use
throttling valves (arranged between the fur- is possible because the waterwalls are used ex-
nace wall and the superheater) which can be clusively for steam generation (evaporation).
bypassed through a low-pressure system with a As a result, the fluid temperature in these tubes
waterseparator. This arrangement permits the is constant and predictable. Even with very
COMBUSTION
Stoam Generation

high furnace heat-transfer rates, mean-wall At DNB, the bubbles of steam forming on the
tube-metal temperatures seldom exceed 800F. hot tube surface begin to interfere with the flow
TWO-PHASE FLOW of water to the tube surface, and eventually coa-
lesce into a film of steam which effectively
The design of boiler furnaces in the subcriti- blankets the hot tube surface. The indication of
cal pressure range requires close attention to this departure is defined as tube metal tempera-
the adequacy of coolant flow necessary to keep ture fluctuations of 20F or greater at frequen-
the evaporative process in waterwall tubes cies of 10 seconds per cycle or slower. The
within the nucleate boiling range. The impor- transition from this point of departure from nu-
tance of this aspect of two-phase flow has been cleate boiling to the point of steady-state film
brought about by the elevated steam pressures boiling is unstable because of the sweeping
and better steam qualities for which boilers are away of the coalescing bubble groups. This un-
being designed. Conditions are aggravated by stable phenomenon exhibits itself first with cy-
the increased and varying absorption rates to clical tube-metal temperature fluctuations of
which some furnaces are s u b j e ~ t e d . ~ 10" to 20F at a frequency appreciably slower
In simplest terms, the design probiem cen- than that of nucleate boiling bubble generation
ters on the choice of a physical arrangement (something in the order of seconds per cycle
that provides the coolest waterwall at min- versus tens of cycles per second for nucleate
imum pump power. To accomplish this the boiling). As this unsteady transition ap-
designer must know the conditions under proaches full film boiling, metal temperature
which the evaporative process passes from fluctuations of 50" to 100F at even slower fre-
nucleate to transitional and finally to film boil- quencies are observed. Fig. 9 is another way of
ing. Also necessary is information on the man- illustrating the phenomenon.
ner in which waterwall metal temperature can CIRCULATION IN A SUBCRITICAL
be expected to change as these phases occur. WATER-TUBE CIRCUIT
An understanding of what is involved in In recirculation-type boilers, the difference
two-phase flow under these conditions is pos- in density between steam and water is utilized
sible from observing the changes that are pro- to provide (or assist in providing) hater circu-
duced in the film conductance, as indicated lation. (See Fig. 10) Generally, the downtakes
most directly by the inside tube-metal tempera-
ture when the heat flux, coolant mass flow, en- -
thalpy and pressure are varied. Transitional Boiling
If a tube were heated uniformly along its
length while water at a sufficiently high mass
flow were passed through it at a given pressure,
the inside metal temperature would follow a
-f
plot as described by the solid line in Fig. 8. If tE
the flow rate were reduced, a point would be r-"-
reached along the mixed or quality phase sec- m
tion of the plot where the metal temperature
rises, as indicated by the dashed line in the il-
s
C

lustration. The point of departure from the Enthalpy


horizontal is known as DNB or the point of de-
parture from nucleate boiling. The maximum -
~i~uidl Mixture I
*
Gas
point on the curve can be referred to as the
point of film boiling or the minimum conduc-
tance point. Between DNB and the film-boiling Fig. 8 inside tube-metal temperature as
point is the region of transitional boiling. a function of two-phase flow conditions
COMBVSTION
Steam Generation

external to the furnace serve as the high-den- cal, and the flow is against gravity. Because the
sity leg of the system. The heated furnace walls water is heavier, it tends to separate and recir-
or the forward portion of a boiler bank, contain- culate. The degree of such steam-water slip: -
ing a mixture of steam and water, constitutes page and consequent recirculation depends on: ;

the low-density leg. The avairable head to pro- the relative densities of steam and water, the
mote circulation is reduced by frictional and relative amounts of steam and water in the mix-
entrance and exit losses in the several circuits. ture, the steam flow velocity, and the internal
The "adequate circulation" referred to earlier area of the riser tube. As might be expected,
can be achieved only if the losses are low and maximum slippage is found in boilers having
make available a sufficient circulating head. large-diameter tubes, high ratios of water to
Before proceeding to the analytical and steam, and low flow velocities.3
quantitative calculations of boiler circulation, CIRCULATION RATIO
consider what happens in a water-tube of a Circulation ratio is defined as the mass rate of
subcritical boiler. A steam-generating circuit water fed to the steam-generating tubes di-
(Fig. ll), for the velocity and resistance in- vided by the mass rate of steam generated. If
volved, will circulate as much water as the dif- steam is condensed in the drum by coming in
ferential head will allow. The resistance is the direct contact with the feedwater, the mass of
sum of that due to steam flow and that due to steam for the above calculation will be greater
water flow. Because the downcomer head is than the net output of the steam drum. In a
constant, the downcomer flow is a function of boiler with drum internals capable of separat-
the sum of the downcomer head and the riser ing steam from water without condensing
tube losses. Steam flow is a function of the steam in the drum, the circulation ratio is the
firing rate, and the water-to-steam ratio in total circulation mass rate divided by the total
the riser circuit will vary for each operating steam mass rate leaving the steam drum.
condition. The average mass of water per pound of
The water in the mixture does not necessarily steam leaving the steam-generator circuits and
flow uniformly or at the same velocity as the entering the steam drum, then, is the circula-
steam, as most riser tubes are more or less verti- tion ratio minus one.

Steam-Water Mixture
b
I I

Film Boiling

Transition Boiling
------------
Nucleate Boiling
-
--LAJ
I 675 850
Tube Metal Temperature,'F
1050
Water

Fig. .9-- Effect of DNB on tube metal temperature


Fig. 10 Chart showing relationshipof steam and water mixtures

I 1

Gage Pressure, Lb/Sq In.


I I I I I I I I I I I
0 2 4 6 8 10 12 14 16 18 20
Gage Pressure, MPa
1

GENERAL BOILER CIRCULATION


There are two distinct but related ways to
consider boiler circulation. The primary view
Steam Out sees circulating fluid transmitting heat from an
external source to a machine for conversion of
thermal energy into mechanical energy. In this
view the boiler is regarded as a thermal trans-
Wat former in which heat-transfer functions are of
In
first importance and are controlled essentially
through fluid circulation.
A second viewpoint emphasizes circulation
as a means of protecting the structure of the
boiler by moving fluid rapidly through its
drums, tubes and headers to prevent overheat-
ing. This places circulation also in the impor-
tant role of a structural-protective mechanism.
- * - Ideally these viewpoints are combined in a
design in which efficiency of heat transfer is
- maximized while cost is minimized.
Fig. 1 1 Typical steam generating circuit in From a physical standpoint, there are three
a subcritical-pressurewater-tube boiler principles involved in the study of thermally

AID
Llc.-.M.~
~ 7 n
COUBUSRON
Steam GonoraUon

induced circulation of fluid: equation for frictional flow, the equation of state
differential pressure from expansion of a for the fluid is needed, namely,
fluid by the application of heat to some po- ion
of a circuit causes circulation - dE +*p J = TdS
with equilibrium established, the work avail-
(3)
able from expansion balances the work done
against resistances to flow in the circuit
and the fact that for frictional flow
mass flow of fluid in a closed circuit is con-
stant throughout the circuit and unaffected by
volume expansion resulting from a steady-state TdS = dq + dW
J
Pf

heat input (4)


A unified analysis of subcritical-pressure
boiler circulation proposed by R. W. Haywood where S is entropy of the unit, and Wf is the
in 1951 incorporated revisions of the hydraulic mechanical work- dissipat.ed by friction per
theory proposed by W. Y. Lewis and S. A. unit mass of fluid.
Robertson in 1940, the thermodynamic ap- The substitution of Eq. 3 and Eq. 4 in Eq. 2
proach proposed by R. S. Silver in 1943, and the gives
expansion approach set forth by R. F. Davis in
1947. Following is the Haywood analysis with VdV
dW,+vdp + - + g d ~ = o
changes in wording and terminology.4 go go
FLUID FLOW IN HEATED PIPES

The classical analysis of frictional flow of a All the terms in Eq. 5 represent energy quan-
homogeneous fluid along a heated pipe must tities per unit mass of fluid, and dwfis that part
be understood.before it can be applied to the of the available mechanical energy which is
special case of circulation, without bubble slip, dissipated by friction. In the simple case of skin
in a subcritical boiler U-tube circuit. friction in a straight pipe
The general energy equation relating to a
unit mass of a homogeneous fluid in steady
flow in a heated pipe is:

Jdq = Jdh +d (Z)z : ;


+
where f is a dimensionless friction coefficient;
d is the inside diameter of t.he pipe and 1 is
length of pipe.
= JdE + pdv + vdp + VdV
80
g
-+ -dZ
go
The substitution of this in Eq. 5 would give
the momentum equation for frictional flow in a
(2)
straight pipe, but this is only a special case of
the more general equation. For other "losses",
where q is heat flow into the fluid; h is enthalpy such as in bends, etc., dWfmay usually be ex-
of the fluid; V is velocity of the fluid; Z is height pressed as some function of the kinetic energy
above a datum level; J is mechanical equivalent at the point, namely,
of heat; go is standard gravitational accelera-
tion; g is acceleration; E is internal energy; p is
pressure and v is specific volume.
This equation applies whether the flow is
frictional or frictionless. To develop from it the
COMBUSTION
Steam Generation

All the terms in Eq. 16 represent energy


quantities (e.g. ft lb force of energyllb,of fluid).
For integration around the steam generation
circuit, E ~ 16
: may be written

where AFE is the increase in flow energy pv;


AKE is the increase in kinetic energy and APE is
the increase in potential energy.
from which the velocity of circulation is given
Applying this to the circuit of Fig. 12
nondimensionally by the expression
AFE - ps (vz - vl); AKE = 0;APE = 0
1 - v*lo~ev~vl
-v:-- Also, p = p, + p', where p' is the local ex-
2 ~ 1 C cess of pressure at any point above the drum
(I3) pressure. Substitution of these relations in Eq.
1 7 gives
where

C = ~ ( K A+ IVZIVI]KF)
+ (zflld) (v2lv1+ 3) + ( v ~ v -, I)]
(14)

THERMODYNAMIC(EXPANSION)METHOD
The thermodynamic or expansion analysis of
OF CIRCULATION circulation may thus be expressed as:
When unit mass of fluid flowing around the
For the case in which fluid is assumed to flow circuit expands by an amount dv at a point
as a homogeneous mixture, the thermodynamic where the pressure is (p, + p'), it does an
(or expansion) analysis of circulation is of inter- amount of work (p, + p') dv against the sur-
est. Resulting from an essentially thermody- rounding fluid, but the work done at the
namic approach, it is at the same time very boundaries of the system in consequence of this
expressive of the physical nature of the process expansion is only psdv.
to describe it as an expansion theory. Its devel- Thus an excess of mechanical work equal to
opment depends on an understanding of the p'dv is available for overcoming friction (or
significance of the expansion work term, pdv, which, in the more general case, would also
in the frictional steady-flow process. This is be available for imparting increased kinetic
found by substituting in Eq. 5 the relation and potential energy to the fluid). This excess
of mechanical work may be termed the work
vdp = d(pv) - pdv available for circulation, and the rate of circu-
(15) lation adjusts itself until a state of equilibrium
is established between the work available for
giving circulation and the mechanical energy dissi-
pated by friction in the circuit.
v +gdz As they are derived from a common equation,
pdv = dW, + d(pv) + d - go it is evident that both thermodynamic and hy-
(16) drodynamic analyses give the same answer for
the rate of circulation. But the hydrodynamic
approach is simpler to apply because the ther- The mechanical energy dissipated in friction
modynamic approach requires a knowledge of in the whole circuit is given by
the pressure at all points in the circuit where
expansion is taking place, and this pressure
must first be calculated by the procedure used : v ?,
V + 4fLid -
d ~ v ,= K , -
2g 0 2go
in the hydrodynamic method. The steps in-
valved are outlined as follolvs: v:
+ aB , v 2 d v + K,- 2go
1'1

l
In evaluating p'dv, the integration is nec-
essary only over that part of the circuit with a
-
1 ' -
change in volume, namely, in the heated riser. where a = -
(vt - ~ 1 ) '
Thus
Thus

where p" = (p - p,), and is evaluated.from Eq.


8 to give
Equating (22) and (23) results again in Eqs.
(13) and (14) thus giving the same answer for
the rate of circulation as was given by the hy-
drodynamic method. Although the thermody-
,
+ aB (v:
&
- v')
namic analysis may clarify the physical pro-
cesses involved in circulation, evaluating the
(20) rate of circulation by this means is con-
- siderably more complicated than by the hy-
where B = 2fG21g,d and G is mass velocity, Vlv. drodynamic method, and the latter is therefore
Also much preferred for practical use.

SEPARATION OF
STEAM AND WATER
Water technology for steam generators is not
Substituting Eqs. (20) and (21) in Eq. (19) and limited to conditioning gr treatment of makeup
integrating, and, feedwater, as discussed in detail in Chap-
ter 20. It is also concerned with the phase trans-
formation of water to steam, and the separation
"work available"
r
= IIpldv =EL 1
of liquid and gaseous constituents. The study of
these phenomena considers physical chemistry,
fluid flow and mechanical design.
Despite many theoretical analyses of steam
and water separation and a great number of hy-
potheses to explain these phenomena, steam
and water separation in boilers retains many
aspects of an engineering art and has thus far
defied completely rational understanding. Ex-
perimental work on both model and full-scale
COMBUSTION
Steam Generation

apparatus continues to provide useful informa- over, solids carryover and boiler-water concen-
tion. Engineering criteria for the design of tration is best illustrated by an example. For a
separators for subcritical-pressure steam and 0.01 percent moisture carryover of boiler water-
water separation, require correlation of these having 1000 ppm concentration, the solids iil ;

laboratory results with widely varied experi- the steam would be 1000 x 0.0001 or 0.1 ppm.
ence, as evidenced by the successful operation Conversely, the moisture carryover can be cal-
for many years of effective and efficient separa- culated if the boiler-water concentration and
tion devices. But the challenge remains to de- the steam impurity content are known.
velop a verifiable theoretical structure that BOILER DRUM
provides an analytically rigorous explanation
of the phenomena of steam and water separa- The drum of a subcritical boiler serves two
tion in terms of the mass flows and physical functions, the first being that of separating
equipment size found in large boilers. steam from the mixture of water and steam dis-
charged into it. Second, the arum houses
THE REQUIREMENT FOR STEAM equipment to "dry" steam after being separated
SEPARATION from the water.
Steam generated in a subcritical-pressure As the quantity of water contained in the
recirculation-type boiler is intimately mixed boiler below the water level is relatively small
with large and variable amounts of circulating compared to the total steam output, the matter
boiler water. Before the steam leaves the boiler of water storage is not significant. Primarily,
and enters the superheater, practically all of the space required to accommodate steam-
this associated boiler water must be separated separating and purifying equipment deter-
from the steam. This separation must be done mines drum size. Drum diameter and length
within a limited space in the drum, within a should be sufficient to provide accessibility for
matter of seconds, and under a variety of veloc- installation and inspection. Length generally
ity, pressure and other operating conditions. depends on furnace width; in the case of high-
The pressure drop across the steam and water capacity units, it is controlled by the space re-
separators must not be sufficient to affect boiler quired for the steam-separating devices.
circulation or water-level control. The weight of water in the mixture delivered
Nearly all of the liquid and solid impurities to the drum for separation depends on the cir-
in the steam and water mixture must be sepa- culation and may range from less than two to
rated from the steam before it is suitable for over 25 times the weight of steam. To reduce
use. Any unseparated liquid in the steam con- this water to the small fraction found in the
tains dissolved and suspended boiler-water steam requires a high efficiency of water sep-
salts which appear as a solids impurity in the aration. The equation indicating the percent of
steam when the moisture is evaporated in the water separation necessary to give a steam im-
superheater or directed to a turbine or other purity may be expressed as:
steam driven apparatus.
100 P,
The moisture content in a saturated steam is Percent of water separation = 100 --
defined by its quality, which is a measure of the NCb
(24)
percent by weight of dry steam in a steam-water
mixture. The solids content in a saturated where
steam is defined by its purity, a measure of the P, = ppm of impurity in steam
parts per million of solids impurity in the N = circulation ratio, Ib of waterllb of steam
steam. Solids content in steam from high Cb= boiler-water concentration
subcritical-pressure or supercritical boilers
is measured in parts per billion. DRUM INTERNALS
The relationship between moisture carry- Drum internals in subcritical-pressure boil-
COMBUSTION
Steam GeneraUon

ers separate water from steam and direct the steam as a function of pressure. The density
flow of water and steam to establish an op- of water at 1200 psia is approximately 16
timum distribution of drum metal temperature times that of steam. At 2800 psia, the density of
during boiler operation. Such apparatus may water is about three times that of steam. Thus,
consist of baffles which change the direction of as pressure increases, separating water from
flow of a steam and water mixture, separators steam with simple devices becomes more dif-
which use a spinning action for removing ficult and requires more efficient apparatus to
water from steam, or steam purifiers such as achieve primary separation in a confined area.
washers and screen dryers. These devices are WATER SEPARATION STAGES
used singly or in consort to remove impurities The stages of water separation are designated
from the steam leaving the boiler drum. as primary separation, secondary separation,
Numerous factors affect the separation of and drying. The devices used are primary
water from steam in a boiler, among which are separators,' secondary separators and dryers.
8 the density of water with respect to the steam The term dryer was established during the
8 the available pressure drop for drum-internal course of development of water-tube boilers on
design the basis that the final stage of separation de-
8 the amount of water in the mixture delivered livered a "dry" and saturated steam.
to the steam drum PRIMARY AND SECONDARY SEPARATORS
8 the quantity or total throughput of water and Primary and secondary separation reduces
steam to be separated the water content of the steam from the boiler
8 viscosity, surface tension and other such fac-
tube circuits to a moisture level that a final-
tors affected by pressure stage dryer can handle. Frequently, the design
of equipment for primary and secondary sep-
8 water level in the drum
aration is influenced as much by the boiler de-
8 the concentration of boiler-water solids
sign as by the basic function of separating the
There is a considerable difference in the water from the steam.
density of water and steam as pressure in- Practically all drum internals consist of plate
creases toward the critical point. This relation- baffles, banks of screens, arrangements of cor-
ship is shown in Fig. 13 which is a plot of the rugated or bent plate, and devices using radial
ratio of the density of water to the density of acceleration to disengage water from steam.
Baffle plates are generally used to change or
reverse a flow pattern to assist gravity separa-
tion in the open drum space. Fig. 14 illustrates

Normal Water
Level (N.W.L.)

Pressure,Psia

Fig. 13 Waterlsteam density relationship Fig. 14 Baffle plates in a steam drum


COMBUSTION
Steam GenemUon

an example of simple baffle arrangements. Baf- screens, This equipment can be relatively small
fle plates change flow direction of water and for the same steam flow velocity.
steam and act as impact plates. Water separat- Bulk separators, Fig. 17, deflect large quanti-
ing out on such plates normally will drain-off ties of water directed into the drum from active
through or adjacent to the steam flow, and a risers. The apparatus reduces the bulk water en-
controlling factor in design and operation is the trained with the steam and directs it below the
steam flow velocity through such drainage. water level. This design has allowed higher
Areas under and around baffles must be suffi- evaporation rates per unit of drum length since
cient to prevent excessive re-entrainment of it satisfactorily removes the bulk of the spray
spray. Limited in their impact-separating ca- water from the steam. The bulk separator re-
pacity, the chief purpose of plate baffles is to duces moisture by providing impact surface, a
direct flow to make maximum use of the gravity change of direction for the mixture, a drain
separating capacity available from any low- trough, and a screen layer for reduction of
velocity steam space in the drum. fine spray.
Screens of wire mesh material are generally Reversing hoods, shown in Fig. 18, combine
satisfactory for secondary separators or dryers. all the desirable design features of baffle and
The limiting factor for screen separators is the change-of-direction principles. As indicated,
steam flow velocity through the free area of steam and water from the active generating .
the screen and the water drainage capacity of tubes are directed behind a baffle into the slot-
the screen. Screens are effective in separating ted reversing hoods. These primary separators
spray. Riser mixtures normally have too much are simply an arrangement of baffle plates to
water in them for screens to handle as primary guide steam and water in a manner to give
separators. Other factors affecting performance maximum utilization of gravity separation in
of screens as primary separators are circulation open drum space. By accelerating the gravity
ratio, size of screen, and steam flow velocity flow of water and by reversing the flow of
through the screen. Examples of screen ar- steam, normal gravity potential is increased
rangements as primary or secondary separators and separation enhanced.
in boiler drums are shown in Fig. 15. At higher pressures, water and steam are
Bent and corrugated plates are commonly separated most efficiently in a drum internal
used for all three stages of separation. Fig. 16 il- utilizing radial acceleration to disengage the
lustrates an example of a corrugated plate as- entrained particle from the steam. Guide vanes
sembly which has the advantage of a higher impart spinning action to the turbulent mix-
ratio of free area to projected area than do ture, and the circular motion causes the heavier

Corrugated
Plates

I
Fig. 75 Use of screens for secondary separation Fig. 16 Corrugated-plateassembly
Fig. 17 Bulk separators for removal Fig. 19 Turbo separators followed by
of spray water from steam corrugated-plate assembly

water particles to move radially outward sures up to the critical operating point.
through the steam and to impinge upon the As the water and steam mixture circulated
outer wall of the separator where they can be from the waterwalls is introduced into the
collected: The efficiency of separation is re- drum, it sweeps the drum shell on its path to
lated to pressure in that the relative densities the bottom. The confining baffle concentric
of water and steam determine the resistance with the drum shell creates effective velocities
to particle motion due to buoyant effects. As and rapid heat transfer. The mixture enters the
operating pressure is increased, and as the den- separators arranged along the length of the
sity of saturated steam approaches that of wa- drum. Vanes spin the mixture as it travels up-
ter, relative motion is more difficult to achieve ward through the separators and thus create a
and separation efficiency is decreased. separating force. The concentrated layer of
The turbo separator, shown in Fig. 19 uses water flowing upward along the surface of the
the radial acceleration principle. Equipped primary tube is skimmed off and directed
with a corrugated plate assembly at the outlet downward through an outer concentric tube for
of the separator, it provides primary and sec- discharge below the waterline with minimum
ondary separation of water from steam at pres- disturbance to the water level.

Screen
Dryer

( I Fig. 20 Screen dryer for removal of


Fig. 18 Reversing-hood primary separators residual moisture from steam
COMBUSTION
Stwm GonrmUon

The steam and the remaining entrained boiler water in the dryer. The free surface areas
water continue upward through a steam collec- are reduced significantly, increasing the local
tor nozzle and turn horizontally into the se- velocity and facilitating re-entrainment of
condary separator. The velocity at this point is boiler water and carryover. Dryers in boilers
low and water cannot be re-entrained from wet- operating with foamy boiler water or large
ted surfaces and runs off the plates. Leaving the amounts of suspended matter in the boiler
separator, the steam flows upward into the water should be inspected periodically and
final dryer which facilitates handling of spray cleaned as necessary. Fig. 20 is a simplified
and dehydration of foam. The turbo separator representation of a screen dryer for final drying
has no inherent capacity limit because there is of steam.
no water seal under a high differential pres- AUXILIARY DRUM INTERNALS
sure. Changes in water level do not affect the ef- Feedwater lines, blowdown lines and chem-
ficiency of the turbo separator5. ical feed lines are also installed in the boiler
drum. In some marine boilers, desuperheaters
DRYERS
may also be installed. Although feedwater,
A component of drum internals, dryers func- blowdown and chemical feed lines normally
tion to remove residual moisture from steam do not take up much drum space, their location
after primary and secondary separators have can be a minor complication in the overall
eliminated most of the circulating water. They internals arrangement. To give satisfactory dis-
are designed to have a large surface area on tribution of flow, these lines are usually run to
which moisture can deposit and from which it the center of the drum where they feed other
can drain back into the drum by gravity. Flow branch lines that are perforated.
velocity through the free area of a dryer must be Feedwater lines are submerged in the drum
restricted to limits above which deposition or water but must be arranged so as to avoid dis-
drainage may be inhibited. charge of cold feedwater against the bare drum
Closely spaced corrugated or bent plates, shell, as temperature variations can cause se-
screens or mats of woven wire mesh can be used vere thermal stress in the thick drum shells. In
as dryer surface materials. The screen dryers are some cases, it is desirable to concentrate the
a practical compromise of performance and colder feedwater flow into the downcomer
drainability that have given satisfactory service tubes to condense steam entrained in the down-
for many years. comer flow and improve boiler circulation. It is
The design of dryers requires consideration also necessary to prevent water hammer which
of a number of factors. Space limitation in the can occur readily if steam leaks back into the
drum restricts the dryer size. Other factors as feedwater system. The inflow of cold water may
sturdiness, leak-proof installation, drainage fa- suddenly condense the steam and create a vac-
cilities and provision for cleaning due to possi- uum. Water hammer results when water rush-
ble plugging of dryer free areas must also be ing into the vacuum stops suddenly.
considered when selecting a steam dryer. The To control scale, sludge, and corrosion,
pressure drop across a dryer is normally low chemical feed lines introduce chemicals in
because of the low flow velocities and rela- a manner which insures rapid mixing with
tively small amounts of water involved. the feedwater. The chemicals are generally
Dryers operate on a low-velocity deposition added in a concentrated form, and it is neces-
principle, not on a velocity separation princi- sary to flush the lines periodically with clean
ple. Formation of insoluble residues on the dry- water to prevent plugging due to reaction
ers from boiler water entrained with the and deposition.
steam decreases the free area, increases the Blowdown lines periodically or continu-
local velocity, and promotes carryover. Similar ously remove a portion of water from the boiler.
results are noted by the filming action of foamy Sufficient high-solids boiler water is re-
Treated Boiler Water
pH> 10.3
m

3 Volatile Treatment
Boiler Water
pH = 9.0

0.4 -
Fig. 21 Dry-box construction
0 15'00 ' ld00 ' 23b0 2&0
moved and replaced by low-concentration Psig
feedwater to maintain a desired concentration
in the boiler water. These lines are located to Fig. 23 Relationship ofsilicain
minimize the occlusion of feedwater and chem- boilerwater to operating pressure
ical feed, and are designed to prevent entrain-
ment of steam.
ers at pressures from 600 to 1200 psig, they be-
Perforated plates, or tapered-plate restric- came obsolete as water treatment improved and
tions at the top of the drum, distribute steam pressures increased. Interest in steam washers
flow. Not a steam dryer, this dry-box arrange- has been renewed however because of their po-
ment distributes the flow to allow a minimum tential for reducing the amount of silica va-
of steam outlets to assure a satisfactory velocity
porized with the steam. This reduction is not
distribution to a steam dryer. Fig. 21 shows a
possible with mechanical devicqs used for
dry box construction.
steam separation.
STEAM WASHERS Vaporization of silica increases with pres-
Steam washers are special drum internals in sure, as illustrated in Fig. 22. At 2500 psia, the
which low-concentration feedwater is sprayed silica in the steam is about 10 times the quan-
into the steam space to dilute the solids content tity at 1500 psia, for the same concentration in
in the moisture being carried over to the steam the boiler watera6Boiler-water pH affects the
dryer. Originally used in multiple-drum boil- vaporization of silica, as shown in Fig. 23. Con-
trolling silica at recommended values such as
l.0g these will assure less than 20 ppb in the steam.
8
& r' Laboratory results and field data conclusively
E5 indicate that silica reduction by steam washing
32 0.1,
Z
UJ .** in boilers above 1800 psig is ineffective. Im-
r 0 proving the quality of makeup water, then, is
;'
m
.u .E the only effective means of controlling the sil-
P- O.O1 ; ica problem above 1800
3
o.oolo I
l t l t 1 VAPOROUS CARRYOVER
1000 2000 3000
Steam Pressure,Psias As operating pressures increase, the steam
phase exhibits greater solvent capabilities for
the salts that may be present in the water phase.
Fig. 22 Distribution of silica in steam and water These salts will be partitioned in an equilib-
COMBUSTION
Steam Generation

Although silica was the first material found _


Table I.Summary of Laboratory Results to exhibit significant vaporous carryover, it is
--
now realized that such carryover coqtributes a
major proportion of total solids in thesteam as
Drum pressure (psig) - 2600 2800 3000
drum operating pressures increase above 2600
Concentration i n boiler water, p p m 15 15 15
S o d i u m sulfate, OO/ 0.02 0.04 0.28
psig. And it is recognized that controlling the
Disodium phosphate, % 0.01 0.03 0.41
amount of vaporous solids in the boiler water
Trisodium phosphate, % 0.02 0.04 0.35
will be required for these other salts as it was
S o d i u m chloride, % 0.04 0.09 0.39
for silica.
S o d i u m hydroxide, % 0.02 0.08 0.55
Table I shows results of a laboratory experi-
ment conducted in 1973-1974to study vapor-
rium between the steam and water. Known as ous c a r r y ~ v e rFor
. ~ various salts, it lists percent
vaporous carryover, this phenomenon will con- vaporous carryover, which is the ratio of the
tribute additional boiler-water solids directly salt concentration in the steam and boiler wa-
to the steam, independent of the efficiency of ter. In each case, sodium was measured and
steam-water separation ~omponents.~ then converted to the concentration value.

REFERENCES
Glenn R. Fryling, ed., Combustion Engineering: A Refer- R. S. Silver, "A Thermodynamic Theory of Circulation in
ence Book on Fuel Burning and Steam Generation, Rev, ed. Water Tube Boilers." Proceedines of the Institution of
New York: Combustion Engineering, Inc., 1966, pp. 25-1- Mechanical ~ n ~ i n e e r153:
s , 261-281, i945.
25-27.
R. F. Davis, "Expansion Theory of Circulation in Water
Warren M. Rohsenow and H. Choi, Heat, Mass and Tube Boilers,"Engineering, 163: 145-148.1947.
Momentum Transfer. Englewood Cliffs, NJ: Prentice-Hall,
1961, pp. 211-236. Ravese, "The Application and Development of the
Turbo Steam Separator," Combustion, 26(1),:45-47, July
Samson S. Kutateladze, Fundamentals of Heat Transfer, 1954.
2nd rev. and augm. ed. Translated by Scripta Technica,
Inc.. and edited by Robert D. Cess. New York: Academic E. M. Powell and H. A. Grabowski, "Drum Internals and
Press, 1963, pp. 342-379 and 380-398. High-Pressure Boiler Design." ASME Paper No. 54-A-242.
New York: American Society of Mechanical Engineers,
3 G. A. Nothman and R. C. Binder, "Slip Velocity in Boiler- 1954.
Tube Circuits," Combustion, 14(12):40-42, June 1943.
F. G. Straub and H. A. Grabowski, "Silica Deposition in
R. W. Haywood, "Research into Fundamentals of Boiler Steam Turbines," Transactions of the ASME, 67: 309-316,
Circulation Theory." Proceedings of the General Discus- May 1945.
sion on Heat Transfer, jointly sponsored by the American
Society of Mechanical Engineers and the Institution of 'H. A. Klein, "Evaluation of Steam'Washers in Power-Plant
Mechanical Engineers, London, Sept. 11-13,1951, and At- Boilers," Transactions of the ASME. Journal of Engineer-
lantic City, Nov. 26-28, 1951, pp. 63-65. London: Institu- ing for Power, 83, Series A: 343-353, October 1961.
tion of Mechanical Engineers, 1951.
El? Gabrieili and H. A. Grabowski, "Steam Purity at High
W. Yorath Lewis and S. A. Robertson;"The Circulation of Pressure:' Presented at the ASME-IEEE-ASCE Joint Power
Water and Steam i n Water Tube Boilers and the Rational Generation Conference, Charlotte, NC, Oct. 8-10.1979.
Simplification of Boiler Design," Proceedings of the In- 9 S.L. Goodstine, "Vaporous Carryover of Sodium Salts in
stitution of Mechanical Engineers, 143: 147-178,1940. High-Pressure Steam," Proceedings of the American
S. A. Robertson, "Communication on the Circulation of Power Conference, 36: 784-789,1974. Chicago: Illinois In-
Water and Steam i n Water Tube Boilers and the Rational stitute of Technology, 1974.
Simplification of Boiler Design," Proceedings of the In-
stitution of Mechanical Engineers, 144: 184-190,1940.
CHAPTER 6

Designing for Boiler Performance .

u o design a large steam generator, manufac-


turers 'follow a step-by-step process that
begins with establishing basic output-steam
tics must be defined because of their important
role in performance, accessibility, and mainte-
nance of the boiler and because they directly
conditions and systematically building to the interface with the primary steam-generating
structural design of furnace walls, headers and equipment. Only when the owner asks for
supporting steel. expanded-scope "boiler islands" will the
So that each manufacturer can develop a manufacturer design such peripherals to the
competitive bid that will give reasonably simi- steam generator as walkways and stairs, steam
lar steam- and water-side performance, owners and feedwater piping, the boiler building, and
issue a set of design criteria that form the basic the coal silos or bins. The steam-generator
ground rules. Generally, the scope-of-supply supplier can also be responsible for the design
specifications issued to a boiler manufacturer of precipitators, flue-gas desulfurization sys-
cover the pressure parts, the pulverizing and tems, and complete ash-handling equipment.
fuel-burning equipment, the air heaters, the
sootblowers, the furnace containment and duct-
work, and the furnace safeguard supervisory
system. "Standard versions" of specifications OF DESIGN BASICS
include
rn primary-steam and reheat-steam pressures One of the first steps in the boiler design pro-
and temperatures cess is to calculate boiler efficiency by using
feedwater temperature the required excess-air percentage for the fuel
to be burned. Working in a systematic fashion,
complete fuel and ash analyses the designer next determines fuel, air and
rn ambient-air and outlet-gas temperatures gas quantities, selects pulverizers, and estab-
Often, the mechanical-draft fans, structural lishes a preliminary configuration of furnace
steel, and furnace-bottom ash-handling equip- windboxes.
ment are also part of the scope of supply. But From analysis of pulverizing-air require-
even if these items are not included, their re- ments, the feedwater temperature, and the
quired performance and physical characteris- variation of these and other factors over the
COMBVSRON
Designing For Boiler Performance
-
normal operating range of the unit, the de- applied to the circulation-system design for
signer arrives at air-heater inlet and outlet gas which a general approach was outlined in
and air temperatures. In turn, this determina- Chapter 5. Usually, the waterwall tubing diam-
tion allows calculation of net heat input, eter, spacing and thickness are predetermined
furnace size, and outlet gas temperature. from design experience with units of the same
size and pressure level. To arrive at the desired
SELECTING HEAT-ABSORBING EQUIPMENT system performance, therefore, the designer's
Having settled on the basic "box size" and effort centers on proper sizing of downtakes,
gas temperature leaving the furnace, the de- supply tubes, risers, and circulating pumps.
-
signer now calculates the gas-temperature SELECTING
drops for all of the superheater, reheater and NON-HEAT-ABSORBING EQUIPMENT
economizer sections up to the air-heater inlet.
A graphic representation of the design calcula- At this point the design of the basic heat-
tions to this point gives the skeleton unit absorbing circuitry is complete and the design
shown in Fig. 1. engineer proceeds with specifications for
By an iterative process, the several high- drums, headers, desuperheaters, and con-
pressure heat-transfer components are "sur- necting piping (discussed later in this chapter)
faced." That is, the designer assumes a total the ignition system (see Chapter 12) air heat-
physical configuration, including tubing di- ers, pumps, and sootblowers (see Chapter 14)
ameters and spacings, then defines the net area ductwork and fans (the sizing of which are
for gas flow between the tubes (called the free covered in this chapter and the mechanical fea-
gas area) and determines heat-transfer rates for tures of which are described in Chapter 14)
each section. When a satisfactory arrangement
of surface is determined, the designer calcu- the furnace-wall structure, which has to con-
lates the steam- and water-side pressure drops, sider both explosive and implosive forces (see
and gas-side pressure losses (also referred to as Chapter 13)
draft losses). Finally, metal temperatures are ash-handling equipment (see Chapter 16)
calculated and tubing diameters, materials, the structural support system, 'including
and thicknesses are chosen. hanger rods, columns, girders, and beams
With the overall steam-generating unit shape platforms, walkways, and stairs
now developed, the cut-and-try strategy can be other balance-of-boiler-island items, such as
specialized chemical-recovery-boiler auxilia-
ries, emission-control equipment, and stacks.
Superheater and Except in the case of marine boilers and some
Reheater Radian retrofit situations, an owner usually does not
and Convective
Surface severely restrict the physical space made avail-
able for a major boiler installation. Although
the designer has a free hand to establish an op-
Windbox (Fuel timum configuration by using existing com-
Nozzles and pany's standards, costs of building volume and
Air-Admission auxiliary-equipment power consumption will
Ports) often lead to consideration of several options in
both basic pressure-part and pulverizer ar-
rangement- as well as the selection of the
Fig. 1. Skeleton arrangement of radiant-reheat unit
boiler-related auxiliaries. The process of select-
showing superheater, reheater and economizer ing the equipment will be described in greater
downstream of furnace. detail in subsequent sections.
coaa8usnI
Designing For Boiler Performance

This introductory look at the design process electrical output on the basis of stated condens-
- - has viewed its basis, its scope, and its se- ing conditions. Boilers are properly rated on
quence. The next section explains step-by-step their steam output(s) at certain pressures and
how to calculate unit heat absorption, effi- temperatures.
ciency, and fuel fired. HEAT ABSORBED
With the outlet steam conditions identified,
HEAT ABSORPTION the heat content or enthalpy, h, in Btu per lb,
is read from steam tables (Appendix F) by
AND EFFICIENCY interpolating as necessary. The heat in the
CALCULATIONS feedwater, hfi is read from tables or charts
The first calculation in the boiler-design for compressed water such as Fig. 2. For a
process is that of the heat absorbed by the work- nonreheat unit, if W, represents the steam
ing fluids-the primary steam flow and the produced in pounds per hour, the total boiler
reheated-steam flow. The purchaser estab- output or heat absorbed, Qabs, will be
lishes these flows at one or more load points,
and gives the steam-generator supplier the
pressures and temperatures at the inlets and
outlets of the primary and reheat headers. For a unit with one or more stages of steam
Boiler capacity is given in terms of the mass reheating, the heat absorbed in the reheater(s)
flow of primary steam at maximum continuous is added to the primary-steam heat absorption
rating (MCR). In this and other texts, nominal to arrive at the total Qabs. Fig. 3 emphasizes that
boiler size is commonly expressed in "mega- this total heat absorption takes place between
watts", an approximation used for conve- point A, where the fuel and preheated combus-
nience-steam-turbine generators are rated in tion air enter the furnace and burn, and point B,
where the gases leave the economizer, which is
usually the final primary-working-fluid heat
absorber. The heat of the products of combus-

I Water Temperature,"F

Fig. 2. Enthalpy of Compressed Water (to obtain


Fig. 3. Total heat absorption by the primary working
fluids in a steam generator-the water and steam-
enthalpy in Btullb (above 32F) for any water tem- takes place between points A and B. The theoretical
perature and pressure, add or subtract the value or adiabatic temperature at point A includes the
on the ordinate from the water temperature. Exam- heat added to the combustion air in the air heater.
ple: 400F water at 4000 PSIG, read - 20 from (Heat is not absorbed in the air heater, but is trans-
curve. h, = (400 - 20) = 380 Btullb) ferred only.)
-

6.
COMBUSTION
Designhg For Boiler Performance

tion passing through the air heater is picked up the heat in the gases going to the stack. In-
by the air and transferred immediately to the cluded in that lost heat to the stack is the latent
furnace, essentially without loss. heat of vaporization of the water in the fuel and
the water formed by the combustion of hydro-
HEAT FIRED
gen, which is impossible for the boiler to ab-
The fuel fired, Qf,
in Btu's per hour, is given sorb. Thus, efficiency becomes a function of the
by the relation type and analysis of fuel fired, the excess air at
which it is burned, the air temperature entering
and the gas-temperature leaving the air pre--
heater, and several other factors described
later. Based on the fuel and the above tempera-
tures, heat losses and credits are calculated as a
percent of the heat input, and the efficiency
where q i s the overall chemical efficiency of the becomes
steam generator. (See Chapter 21, Testing and
Measureme~ts,for more infcrmation on the
definition of chemical-heat efficiency.)
The quantity of fuel to be burned, the amount
of air to be supplied, and the products formed
The process of accounting for all the heat
are all calculated from Qf.These three quan-
losses, as well as the heat available in the steam,
tities largely determine the size of the furnace
is known as a heat balance. The heat balance
and the other components.
method is frequently used to test for the effi-
The amount of fuel fired, sometimes called
ciency of an operating unit. Unlike the test engi-
the combustion rate, is found by dividing Q,by
neer who can measure these losses accurately,
the high heating value of the fix1 (to give the the designer must assign values tosome of them
mass of fuel fired per hour) or, for gaseous
based on experience.
fuels, the volumetric rate which is the cubic
feet of gas fired per hour.
.. The following losses are those which must be
known before the efficiency can be determined.

.
STEAM-GENERATOR EFFICIENCY loss in dry products of combustion
The efficiency of a boiler is most frequently loss due to moisture in air

.,
taken to be the ratio of the heat absorbed by the loss due to moisture from fuel
water and steam to the chemical heat in the fuel loss due to water vapor in gaseous fuels
fired. It is not a measure of the efficiency with loss due to moisture from hydrogen in fuel
which the coal or other fuel is fired into the

..
sensible heat loss in as,
combustion chamber or onto a grate, although
loss due to unburned combustible
the carbon heat loss item in a heat balance will
account for this. Modern suspension-burning loss due radiation and convection
systems reduce this carbon heat loss ineffi- other losses and heat credits
ciency to minimal amounts. Nor is boiler effi-
COMBUSTION CALCULATIONS
ciency the net rate at which an electrical
generating plant produces power, called the With the fuel analysis given, the excess-air
net plant heat rate in BtulkWhr. But boiler effi- percentage decided on (see subsection Excess
ciency must be known to determine the "Btu" Air for Combustion, which follows), and the
consumed so that the net plant heat rate can be moisture content of the air stated or assumed,
established for a given boiler turbine unit. the designer can perform the combustion cal-
Simplistically, a boiler absorbs most of the culations as delineated in Chapter 4. By using
heat in the fuel fired but is unable to "capture" the combustion equations or the graphical
COYB(ISR0N
Designing For BoilerPsrfonnance

methods presented in Appendix C, the air for


combustion, the dry weight of products, the Table I. Excess Air at Furnace Outlet -

weight of water resulting from burning the Fuels % Excess air


fuel, and the other items required for heat-
balance work are determined, Also, a check is Coal (pulv6rizedj '15-30
made of the ultimate fuel analysis supplied Coke 20-40
versus the high heating value, to discover early Wood 25-50
any discrepancy in this correlation (see Chap- Bagasse 25-45
ter 4 for more on that aspect of the calculation). Liquid Oil 3-15
Gaseous Natural gas 5-10
EXCESS AIR FOR COMBUSTION
Refinery gas 8-15
Perfect or stoichiometric combustion is the Blast-furnace gas 15-25
complete oxidation of,all the combustible con- Coke-oven gas 5-10
stituents of a fuel, consuming exactly 100 per-
cent of the oxygen contained in the combustion AIR TEMPERATURE FOR COMBUSTION, t,
air. Excess air is any amount above that theoret- Efficiency calculations are based on the air
ical quantity. temperature that will actually be entering the
Commercial fuels can be burned satisfacto- air heater, not on the ambient temperature (t,,)
rily only when the amount of air supplied to nor the specified reference air temperature (t,).
them exceeds that which is theoretically calcu- The increase in temperature of the air as it
lated as required from equations showing the passes through the forced-draft (FD) fan and
chemical reactions involved. The quantity of the steam or hot-water air heater must be added
excess air provided in any particular case de- to t,, to arrive at t,.
pends on A function of the power consumed by the fan,
the physical state of the fuel in the combus- air temperature rise through an FD fan can be
tion chamber calculated from
fuel particle size, or oil viscosity
the proportion of inert matter present
.the design of furnace and fuel burning 10,30O(HP)
AT,, = --
equipment W"
(4)
For complete combustion, solid fuels require
the greatest, and gaseous fuels the least, quan-
tity of excess air. Fuels that are finely sub- where ATfdis in OF, HP is the brake horsepower
divided on entering the furnace burn more to the fan shaft, and W, is the weight of air
easily and require less excess air than those in- being handled in Iblhr. The relation is based on
duced i n large lumps or masses. Burners, stok- conversion to heat of the air horsepower and
ers and furnaces having design features pro- the horsepower corresponding to the ineffi-
ducing a high degree of turbulence and mixing ciency of the fan. This heat must be stored in
of the fuel with the combustion air require less the air. The formula includes a small correction
excess air. required for velocity pressure at the fan out-
Table I indicates the range in values for the let but the formula cannot be used to predict
excess-air percentage commonly employed by the temperature rise at the no-flow or shut-off
the designer. These are expressed in percent of condition.
theoretical air, and are understood to be at the AIR TEMPERATURE RISE
design load condition of the boiler. (At lower BY STEAM OR HOT-WATER HEATING
loads, both in design and in operation, higher It is common in power plants to provide
percentages are sometimes used.) heating coils ahead of the main air heater inlets
CONBumO~
Designing For Boiler Performance

'to preheat the air entering those heaters. Al- flow through the high-pressure turbine blading
though primarily used to reduce the potential can be greater for a given electrical output.
for corrosion on the heating surfaces of the air Thus, steam-turbine efficiency is improved by
heater, preheating air with steam or hot water extracting steam for air heating just as it is im-
can substantially improve the overall plant ef- proved with feedwater heating.
ficiency. Preheating increases the heat content AIR HEATER COLD-END PROTECTION
of the incoming combustion air which helps The part of an air heater called the cold end is
increase unit efficiency and thereby decrease the section in which the incoming "cold" air
the fuel that is fired in the boiler. meets the exiting cooled products of combus-
The economic and practical limits to im- tion. The sum of these temperatures divided by
proved boiler efficiency by lowering the unit's 2 is called the average cold-end temperature
exit-gas temperature, have essentially been (ACET). Since cold-end fouling and corrosion
reached. Corrosion andlor plugging of air heat- can be related to the ACET level, it is usual
srs and dust-collection equipment generally practice to work to such a temperature to estab-
determine the lower temperature limit, which lish the exit-gas temperature aod the required
depends largely on the sulfur content of the air temperature leaving the steam or hot-water
fuel being burned. Efforts to design and operate heater. A guide for setting the cold-end tem-
modern units for sustained periods with 250F perature is given in Fig. 4.2
final flue-gas temperature at full load generally For subbituminous and lignitic coals having
have been unsuccessful with many fuels, and the sum of the lime (CaO)and magnesia (MgO)
usually the design objective' is at least 25OF greater than the ferric oxide (Fe203)in the ash,
higher, or 275F. Extraction-steam air preheat- the sulfur content used for reading the curve
ing has both increased the efficiency and pro- should be adjusted to equivalent sulfur, ES.
tected air heater surfaces because the steam -

Material Specifications:
Carbon-Steel Components
Corros~on-Resistant, where S is the percent sulfur in the coal as fired
I.L Low-Alloy-Steel and HHV isthe high heating value of the coal as
'- Cold-End Element fired.
0
3
5
Thus, for a low-rank coal with an HHV of -

g2 7,000 Btullb and an as-fire.d sulfur content of 1


5 $190-- percent, the curve must be read at an ES of 2
percent, for an ACET of 163OF.
5-180- EXIT GAS TEMPERATURE-
-
.E 23 CORRECTED VS. UNCORRECTED
.t 170 -
E a, - Note that the ACET in Fig. 4 is termed "un-
U Q corrected". That means that the gas tempera-
B E 160-
m r-" ture used in the averaging calculation is not
5 2 150- I
1
I
2
I
3
I
4
I
5
adjusted for the leakage from air- to gas-side of
CnY the air heater. Because of the differential pres-
0 Sulfur Content of Coal sure between the air entering and the gases
0
0.- - (O/O As Fired) exiting an air heater (the latter being below
atmospheric pressure in most instances), there
Fig. 4. Recommended minimum average is a flow of cooling and diluting air over to the
cold-end temperature for coal firing gas-side of the heater.
COMBUSTION
Designing For Boiler Performance

The dilution raises the excess-air percentage The heat loss, in percent of heat input, equals
that is measured in the exiting flue gases. The
measured exit temperature at the preheater is
lower than the _uncarrected (actually un-
measurable) temperature because of this air
leakage. In efficiency calculations, designers
use the uncorrected (theoretical) temperature
and the excess-air percentage entering the air LOSS DUE TO MOISTURE IN FUEL
preheater as the basis for the heat losses. The
result would be the same if the corrected tem- This loss represents the difference in the heat
perature and the corrected excess air were to be content of the moisture in the exit gases and
used in the calculations. that at the temperature of the ambient air. If
It is important to realize that the more input H20includes both the surface and hygroscopic
parameters specified, the less the potential for moisture in percent by weight... of fuel fired,
differences i n fuel fired and air and gas quan- then
tities when bids are taken. The preceding
groundwork is fundamental to the calculation
of the several heat losses.
LOSS IN THE DRY PRODUCTS
OF COMBUSTION For T, higher than 575"F,the loss due to fuel
moisture equals
Frequently the largest of all, the loss in dry
products of combustion represents the differ-
ence between the heat content of the dry
exhaust gases and the heat content these gases
would have a t the temperature of the ambient
air. The dry gas (Pd)is calculated by subtracting
the water vapor in the products from the total and for T,lower than 57s0F,
products of combustion (P) with all quantities
expressed in pounds per million Btu input (see
Chapter 4). Knowing Pd, the percent dry-gas
loss is found from

in which T, corresponds to the temperature of


the fuel received at the pulverizers or the oil or
gas guns. This temperature is ordinarily taken
as 80F or the reference air temperature if the
LOSS DUE TO MOISTURE IN AIR actual temperature is not known.
It should be understood that W, does not in-
The moisture in the combustion air (W,) is clude water vapor as found in gaseous fuels.
determined for specified conditions of temper-
ature and relative humidity, as described in LOSS DUE TO WATER VAPOR
Chapter 4. For an atmospheric air requirement IN GASEOUS FUELS
(A) in pounds per million Btu fired and typical Moisture is also present in many gaseous
conditions of 80F and 60-percent relative fuels, particularly in blast-furnace gas and
humidity, W, will be 0.013 CA, where C is the coke-oven gas, which are frequently dedusted
combustible-loss correction factor. by passing them through sprays of water. This
COMBUSTION
Designing Fw Boiler Performance

moisture exists in the gas in two separate an empirical relation between the hydrogen in
forms, each requiring different treatment in the fuel and the volatile matter, such as is found
calculating the heat balance. in Appendix C. But remember that, in deriving
Washed gas contains entrained water in the the hydrogen moisture from a proximate analy-
form of suspended globules. Where exception- sis, the loss due to the water loss may be in error
ally clean gas is not required, the entrained as much as 1.5 percent-equal to or greater
moisture, W,, averages 7 lb per million Btu. No than some other items in the heat ba!ance.
entrained water is in unwashed gas. For Tg higher than 575"F, the loss due to
In addition to the visible moisture i n a liquid -
moisture from hydrogen in fuel equals
state, nearly all gaseous fuels contain some
water vapor. In natural gas, the water vapor is
there because of salt water that has been in con-
tact with the gas in the ground, or because of
rehydration. In refinery gas, blast-furnace gas,
and coke-oven gas it is present either owing to and for Tglower than 575"F, the loss equals
the nature of the process of which these gases
are byproducts, or because of subsequent
cleaning operations.
The water vapor (WJ in pounds per million
Btu is of such magnitude that it can usually be
neglected in heat-balance calculations for nat-
ural gas, refinery gas, or coke-oven gas. For in which T, is the air temperature entering the
blast-furnace gas saturated with moisture at air preheater; that is, the ambient air tempera-
60F, W, may be taken as 8 lb per million Btu ture plus the FD fan and steam-air-heater tem-
without serious error. perature rises. The above relationships apply to
In a heat balance for gaseous fuels, W, must solid, liquid and gaseous fuels.
be considered separately from W,, and W,, since
SENSIBLE HEAT LOSS IN ASH
it exists as a vapor which already has the latent
heat of vaporization, and therefore requires no Hot ash from the burning of a solid fuel can
heat evolved by the fuel to vaporize it. In every represent a substantial heat loss, dependent on
respect it is similar to W,, so that the percent the quantity and the temperature at which ash
loss due to its presence is is rejected from the steam generator or auxiliary
---- equipment. The significant locations of ash ex-
traction from most boilers are the furnace bot-
tom and the hoppers under the economizer, the
air heater(s) and the flyash-collection device,
usually an electrostatic precipitator or a fabric
filter. Flyash leaving an air heater at a tempera-
LOSS DUE TO MOISTURE ture such as 300F, for example, represents a
FROM HYDROGEN IN FUEL heat loss whether it is collected in a precipita-
tor or not. Further, even if it is cooled below
This loss includes the sensible and latent 300F in the collection process, such cooling
heats of the moisture from the combustion of has to be accounted for.
the hydrogen in the fuel above the ambient The ASME Performance Test Code PTC 4.1
or reference air temperature. The water from provides fo? the measurement of the sensible
hydrogen (Wh) equals 9 x H x 1O4/HHV, as heat lost in the ash leaving a boiler. The only
previously defined. When only the proximate specific method given (at this writing) is for
analysis is available, it is necessary to resort to solid-fuel-fired units in which the ash or slag
COMBUSRON
Designing For Boilet Performance

falling from the walls of a furnace is caught in a


wet receiver. The heat loss of this ashlslag is de-
termined by measuring the temperature in-
crease and flow of the cooling water in and out
of the bottom-ash hopper, and making the indi-
cated corrections for evaporation and sluice-
gate leakage. Flyash heat is Code-designated as
L,, the heat loss due to sensible heat in the flue
dust; this is different and distinct from any loss
attributed to unburned carbon in the ash.
For the majority of pulverized-fuel boilers fir-
ing low- to medium-ash coals, the heat loss is
well below 1 percent of the fuel fired, and is not
accounted for explicitly either in a predicted
heat balance or in an M M E Short Form effi-
ciency test. Since it is both difficult and expen- 0 50 100 150 200 250
sive to measure, the ash heat loss on dry-bottom Lb Ash Rejected / 1 0 q t u Fired (HHV)
pulverized-fuel boilers with wet ash receivers
usually is considered part of the unmeasured Fig. 5 Heat loss of ash rejected from stoker grate
and unaccounted-for losses described below. or fluidized bed above 80F reference temperature.
For stoker-fired and fluidized-bed boilers, Ash here includes fuel ash plus rejected limestone
which maintain as much of the ash as possible or other additivelsorbent.
in a high-temperature moving or circulating I
bed, the hot ash and other solids leaving the Btu fired. Thus, to determine an overall value
bottom of the unit, for high-ash fuels, may con- for the heat loss attributable to the hot ash leav-
tain a large amount of heat representing well ing a boiler, the temperatures at all rejection
over 2 percent of the heating value of the fuel points, as well askhe quantities at all points,
fired. See Figure 5, which indicates the mag- have to be established by calculation or estima-
nitude of this heat loss as a function of the tion. A summation of the weighted values of
pounds of ash per million Btu fired and the re- the rejects will give the total heat loss due to the
jection temperature. The correlation is based on sensible heat in ash-plus-additive.
specific heats varying with temperature, for ash
of an assumed composition. (The specific-heat LOSS DUE TO UNBURNED COMBUSTIBLE
variation does not consider the effect of phase
changes of certain ash constituents which can This loss comprises unliberated thermal en-
. occur in the range of 800 to 1200F.) For con- ergy due to incomplete oxidation of the com-
tract efficiency determinations, the boiler sup- bustible matter in the fuel. The loss can be from
plier and owner must agree both on the specific unburned carbon that is trapped in.the flyash or
heats to be used and the means of determining the furnace-bottom ash deposited in the ash re-
reject-ashlsolids quantity and distribution. ceiver of a pulverized-fuel fired or fluid-bed
Note that the ash-removal temperature, for boiler, or it can be from the incomplete combus-
heat-balance purposes, is the temperature be- tion of the carbon in the fuel as evidenced by
low which no heat is added to any of the steam- the presence of carbon monoxide (CO) in the
generator working fluids-fuel, air, water, or gaseous products leaving the furnace. For de-
steam. Also, for fluid-bed combustion, there is sign calculations, liquid and gaseous fuels are
usually an additive solid, such as limestone, to generally presumed to burn with zero combus-
facilitate operation and,'or capture sulfur, that tible loss; CO loss is assumed to be zero, regard-
adds to the effective ash quantity per million less of the fuel.
COMBUSTION
hsignhg For Boiler Performance

For suspension firing of pulverized coal and necessary, achieved through acquisition of field
other solid fuels, control of unburned carbon data taken during combustion of the same fuels
heat loss is an important objective in design as tested in the laboratory. The validity of the
and operation. Carbon burnout is dependent on predictive technique was tested by comparison
fuel properties, furnace and firing system de- between carbon-loss values generated by the
sign, and unit operating conditions. Major fac- laboratory and those directly measured in oper-
tors influencing complete combustion of ating full-scale units using the same fuel.
carbon are:
LOSS DUE TO RADIATION
fuel reactivity AND CONVECTION
fuel finenesslparticle size
efficiency of fuel-air mixing This loss is a comprehensive term used in a
excess air available for combustion heat balance calculation to account for heat
residence time in the furnace, and losses to the air through conduction, radiation,
and convection. The heat emanates from the
the furnace temperature profile.
boiler. ductwork. and ~ulverizers.Because it is
The designer must carefiilly match these pa- very difficult to measure on large operational
rameters with fuel characteristics to minimize boilers, this is the only significant loss for
carbon heat loss. In most instances, the loss which computation is not based on test meas-
due to unburned carbon is controllable to below urements in the Performance Test Code for
1' 2 percent of the fuel fired. boilers.
C-E has developed a methodology for pre- Fig. 6, used for both design work and per-
dicting solid carbon loss during the suspension formance tests on fully watercooled furnaces,
firing of pulverized coal using advanced labora- was extrapolated by the American Boiler Manu-
tory characterization and mathematical furnace facturers Association from data obtained from
modelling techniques. The methodology is de- some relatively small boilers. The curve values
scribed in Reference 3; it involved a compre- were later checked by the ASME Test Code
hensive reactivity study of a wide range of solid committee against actual measured losses on
fuels in C-E's Drop Tube Furnace System several large boilers and were found to be
(DTFS), which incorporates an entrained consenlatively high.' Note that this item does
laminar-flow reactor. The DTFS is described in not account for or include radiation, convec-
further detail in Chapter 3 of this text, and in tion, or infiltration losses from a precipitator
References 4, 5, and 6 of this chapter, located ahead of the air heater(s).
The fundamental information obtained from For boilers having ratios of external surface to
this study comprises physical and chemical volume, or surface temperatures, that vary con-
characteristics and combustion kinetics of siderably from those used in establishing these
many coals, chars, coal-derived synfuels, and curves, direct calculation of radiationlconvec-
refuse-derived fuels. In devising this improved tion loss can be done.
method for predicting combustion efficiency, it
UNACCOUNTED-FOR LOSSES
was determined that better accuracy could be
achieved if coal pyrolysis and volatile-matter This item represents unclassified, conten-
combustion were separated from the dominant tious, and difficult-to-measure losses that are
heterogeneous char-burning phase of coal com- included in a heat balance to arrive at a guaran-
bustion. An accurate simulation of tempera- teed contractual efficiency.
tureltime history to which coal particles are The value used consists of three components,
exposed was of primary importance; this was of unstated weight. First, there are the unmea-
accomplished in the Drop Tube Furnace. Fi- sured losses which, because of the difficulty or
nally, it was recognized that meaningful cali- the great expense of measurement, are best in-
bration of a mathematical model would be cluded in a convenient margin. Typical is the
COMBUSTION
Designing For Boiler Performance

sensible-heat-in-ash loss for pulverized-coal and other potential areas of disagreement.


boilers covered in the previous section. Approx- The third component, grouped with instru-
imation of such a loss by calculation frequently ment-error, is the manufacturer's tolerance in
will be a more satisfactory approach than set- making an efficiency guarantee.
ting up and operating the very complicated
testing equipment and instrumentation to ob- HEAT CREDITS
tain meaningful results.
Second, the loss includes some unstated tol- A heat credit is any energy obtained from out-
erance for instrument error. Whether the short- side the envelope of the steam generator (see
form performance test is made, or the fully Fig. 7, Chapter 22) and added to the working
detailed and very costly long-form procedure is fluid or fluids, the air, or the gas inside the en-
followed, it is important to arrive at an effi- velope boundary. This is over and above the
ciency that can be accepted both by the owner chemical heat in the fuel fired and is usually in
and the supplier. Chapter 22 on field testing the form of electrical energy.
and measurement covers the probable, and As a practical matter only major credits are
rather large, measurement error that can be ex- considered in most heat-balances. These in-
pected in performance testing. Having some clude the heat from the power conversion in
"room for error" will often eliminate the need pulverizer motors, primary-air-fan motors, gas-
for retests on the basis of faulty instrumenta- recirculating-fan motors, and circulating-pump
tion, poor placement or operation of probes, motors.

90
80
70
60
50 Note Use These Llnes for U n ~ t
Outputs Below the Maxlmum
-2 30 40
Continuous Ratlng

-g 20
-C

I,
V)
9
10
S 08
07
1; 06
-1
g 05
= 04
'i
D
ffi 03
11I

02

01
100 200 400 600 1000 2000 4000 6000 10,000
Actual Output lo6Btu/Hr

Fig. 6. Radiation loss for completely water cooled furnaces. The radiation loss values obtained from this
curve are for a differential of 50F between surface and ambient temperature and for an air velocity of 100
feet per minute over the surface. The curve is based on an analysis done by the American Boiler Manufactur-
ers Association (ABMA), and is published in the original format in the ASME PerformanceTest Code PTC-4.1.
CO%mn1ION
Designing For Boiler Performance

Credits are calculated by determining the such leakage can be anticipated and quantified,
power input to the motor (or steam turbine if it should be given special consideration be-
the steam is supplied from outside the enve- cause of its effect on air-heater heat transfer (the
lope) and dividing by the heat fired (Q,) if the lower gas temperature entering the air heater
power is applied to the air or gas, or by the heat reduces the heat head for thermal transfer) and
absorbed (a,)
if the power is applied directly its effect on the ID-fan performance and power
to the working fluid; the quotient is then ex- consumption.
pressed in percent of fuel fired for use in the
heat-balance calculation. HEAT-BALANCE CALCULATION
HEAT LOSS IN INTEGRAL PRECIPITATOR The heat balance of Table I1 for a boiler to
serve a 500-MW turbine is based on firing a bi-
It has been demonstrated that there is a sub- tuminous coal of the analysis given in Chapter
stantial gas-temperature drop in the ductwork 4, page 4-5, at an excess-air percentage of 23
a d through the walls of a precipitator located percent. The carbon loss, FD-fan temperature
between the boiler economizer and the air rise, and heat credits are assumed forth':s exam-
heater(s). This temperature drop results from ple, and will vary from case to case. Combus-
radiation, convection, and air inleakage. No tion air has 0.013 lb of water vapor per lb of air
tests have been performed to categorize these (80F and 60 percent relative humidity). Fuel
contributors to the problem. temperature is taken as equal to ambient air
Logically, there is a loss of energy which has temperature.
to be charged someplace. Because the precipita-
tor is not part of the steam-generator circuitry
and because the heat is not returned to the air or
gas, the loss should not be charged to the boiler. FIRING SYSTEM DESIGN
The most satisfactory approach is to consider With combustion and heat-balance calcula-
the integral precipitator as another "heat ab- tions completed, and the overall steam-
sorber", similar to a second reheater, and take generator heat absorption fixed, !he designer
the energy absorbed as an additional output. can now arrive at the weight of fuel fired.
Using the higher Q,,,,, will give the correct Q, ---- -- ---
and the correct air and gas weight without
penalizing the steam-generator efficiency. Fuel fired, lblhr = Qr
-
The heat "lost" or "absorbed" in such a pre- HHV
cipitator can be calculated by (15)

W, x cn x AT, where Qf is in Btulhr. and the high heating


Li, = *oO value, HHV, is in Btullb.
Q .

PULVERIZER SELECTION I

where It is customary in pulverizer selection to pro-


W, is the gas flow through the precipitator, vide one or two "spare" or standby mills to
I
lblhr allow for on-line maintenance at boiler full
c, is the specific heat of the gas, Btullb-OF load. (See Chapter 23 for more comments on
A T, is the gas-temperature drop through pulverizer maintenance with the unit in opera-
the precipitator, O F , and tion.) If there are "n" number of pulverizers in-
Qfis the heat fired, Btulhr stalled then (n - 1) mills will be capable of full
Note that this method does not take into ac- boiler load grinding the worst fuel that the
count the air leaking into the precipitator. If unit must handle; with an average more
COMBUSTION
Designing For Boiler Performance

value, moisture content and grindability, the


Table 11. Heat-Balance Calculations -
greater must be the overall pulverizer capacitv.
Exit gas temperature, uncorrected for
- The statistical probabiliiy of all the unfavor-
285
able characteristics occurring at the same time,
leakage, t,, "F - ' -
80
and the total possible period of operation at full
Ambient air temperature, t,,, O F
10
boiler load with the worst fuel, have to be
Temperature rise, FD fan, h tfd, O F
weighed against the cost and complexity of
Air temperature entering air heater, T,, O F 90
0,20 multiple installed-spare pulverizers.
Solid combustible loss, O/O by weight
Combustible loss correction factor, C 0.9985 WINDBOX DESIGN
Fuel in products, F, lb110~Btu 83 With tangential or corner firing, each pulver-
Air for combustion, A, lb/106Btu 936 izer installed delivers ground coal to a row of
Air in products, C x A, lb110~Btu 934 fuel nozzles located at different levels in the
Total products, P = (F + CA) lbl10~Btu 1017 furnace. A row will contain 4 or 8 nozzles de-
tvater in air, W, lb11o6Btu pending upon whether the furnace is of the
Water in fuel, W , l b l l ~ ~ B t u 13.4 open type or of the divided type; the latter usu-
Water formed in combustion, Wh :bllo6Btu 32.7 ally has a full or partial between the
Dry gas i n products, Pnlb/106Btu 959 two firing chambers, with 4 nozzles per hori-
zontal row in each of the two chambers. In an
Heat loss in dry gas % 4.49 open furnace with six pulverizers, there will be
Heat loss fro,m water in fuel 0/0
four fuel nozzles arranged in six horizontal
Heat loss from combustion of Hz % 3.70 rows for a total of 24. Further detail about tan-
Heat loss from moisture in air O.ll
gential windboxes and associated ignition
Heat loss from unburned carbon % O." equipment is given in Chapter 12. Fuel-
Radiation and convection loss % Firing Systems.
Unmeasured losses* % 1.50
Total losses. 11.71
O/O
With front- or rear-wall firing using fixed
Less heat credits* *
% 0.25 round burners, the piping from the pulverizers
Net losses, % 11.46 to the burners is configured in various ways
Efficiency (100 - net losses) 88.54 depending upon the manufacturer's prefer-
ence. steam-temperature control means, and
'Unmeasured losses Include tolerance for ~nstmmenterror and
manufacturer's margln
nitrogen-oxide reduction strategy.
"Heat credits here are the sum of motor Inputs to pulverizers. Windbox sizing for either tangential or wall
primary-a~rfans, and boiler-\\rater c~rculatingpumps. determined firing must recognize the effect of plant 81-
In a separate cal~ulation.
titude on airflow velocity, both in primary-air1
fuel piping and in secondary-air compart-
favorable fuel, (n - 2) mills can accommodate ments. Air volume and corresponding velocity
the maximum load. In either case, pulverizer vary linearly with the elevation correction fac-
selection is done using capacity curves similar tor (barometric pressure at sea level divided by
to those given in Chapter 11, allowing for the the barometric pressure at altitude; see Fig. 7).
wearing parts being in worn condition. Pressure drop through a given windbox open-
The capacity of a given size pulverizer varies ing or burner throat varies as the square of the
significantly with coal moisture, the grindabil- actual velocity divided by the elevation correc-
ity of the coal (its "ability to be ground"), and tion factor; this must be taken into account in
the fineness required for satisfactory, low- fan sizing, covered later in this chapter.
carbon-loss burning. Chapter 11, Pulverizers
and Pulverized-Coal Systems, covers these AIR-HEATER DESIGN
parameters and their effects on pulverizer per- Having designed the windbox and selected
formance. The wider the range in coal calorific the pulverizers to accommodate the least fa-

6-13 /JA!lB
COMBUSTION
Darigning For Boiler Performance
-

exit-gas temperature is the key to the per-


formance of all the very expensive superheater
1SO- Constant Temperature and reheater surfaces installed behind it, that
temperature is not amenable to calculation.
8 Temperature Varying Only through field experience with similar
1.40 - Approx. 3.5iF/1 000 Ft
LL fuels and generally the same mode of furnace
c
operation can such temperatures be deter-
mined with confidence. And despite using the
most sophisticated computer techniques in the
analysis of the upper and lower furnace regions
as heat-transfer entities, the data input to those
computers is based on a subjective judgment
of the slagging character of every coal burned.
We will discuss heat transfer in general as a
0 2000 4000 6000 8000 10,000
brief introduction to the subject of furnace heat
Elevation, Ft Above Sea Level
transfer. We will then show a portion of the
analytical approach we take to furnace per-
,
Hg. Volumetric cornction for above
see level (Calculated from the data of Standard
formance, and will refer to other publishedma-
terial for the interested reader.
Atmosphere-Tables and Data to 65,800 Feet, Finally, we leave the reader with the percep-
NACA Report 1235) tion that furnace outlet temperature determina-
tion, while not a secret process, is certainly and
vorable present or future fuel, the designer necessarily a proprietary one.
now has sufficient information to define the air
preheater requirements. HEAT TRANSFER
The gas flow is the primary determinant in
A necessary step in the design of boilers is a
sizing an air heater, since the pressure drop
detailed engineering analysis of heat transfer
through the gas side varies predictably with
load (being essentially proportional to the to estimate the cost, practicability and size of
equipment to interchange a specified amount
square of the gas flow and linear with absolute
of heat in a given time. A steam-generating-
gas temperature). Primary and secondary
airflows are additive to the total airflow re- unit furnace wall, for example, can be operated
successfully over extended periods only if sur-
- quired, but each will change with fuel
face temperatures can be maintained within
moisture, load, and the number of pulverizers
acceptable limits by removing heat continu-
in operation. The maximum primary airflow
ously and at rapid rates, The size and geometry
and pressure required by a certain size air
of a boiler furnace depend not only upon the
heater will be important factors in primary-air
amount of heat to be transmitted but also on the
fan and motor selection.
rate at which it can be absorbed or transferred.
Air heater design is covered in detail in
Chapter 14. The use of the trisector and other MODESOF HEATTRANSFER
air-heater configurations is treated in connec- Most textbooks on heat transfer define three
tion with pulverizing systems in Chapter 11. modes of heat flow: convection, conduction
and radiation. These three encompass much of
the field of physics including medhanics, heat,
FURNACE PERFORMANCE acoustics, optics and electricity. For gases,
The following section deals with the thermal conduction takes place by elastic impact; for
performance of a large steam-generator fur- solid nonconductors, in longitudinal vibra-
nace. Although the determination of furnace tion; and for metals, in electronic movement.
COMBUSTION
Designing For B o l k Performance

The laws of aerodynamics and hydrodynamics from an ideal radiator or black body. It was de-
govern convection which involves the trans- rived theoretically by Ludwig Boltzmann in
portation and exchange of heat due to the mix- 1884, and may be expressed as follows:
ing motion of different parts of a fluid.
Radiative heat transfer is an electromagnetic
event which in fossil-fuel-fired furnaces occurs
mainly in the infrared range.
Usually, heat is transferred simultaneously
by more than one of these modes. where u is the Stefan-Boltzmann constant for
Convection total black radiation, A, is the heat-transfer-
Authorities differ as to whether Sir Isaac surface area, and T is the absolute temperature.
Newton formulated a'definition of convection (See equations 23 and 23A.)
or a law of cooling when he first expressed the The Stefan-Boltzmann equation represents
following relationship in 1701: the total radiant energy emitted by a black body
in all directions, but it does not reveal the dis-
tribution of energy in the spectrum. The distri-
bution of emissive power among the different
wave lengths was derived by Max Planck in
1900, using the quantum concept.8
Heat transfer in boilers will be covered in
where q denotes the time rate of heat flow, h i s
more detail after furnace performance is dis-
the surface or film coefficient of heat transfer,
cussed. In a later section this chapter covers
A, is the heat-transfer-surface area and AT is a
fluid-to-fluid transfer rates and convection
temperature difference between a surface and a
heat-transfer in detail.
fluid in contact with it.
Conduction FURNACE DESIGN CONSIDERATIONS
More than a century later, in 1828,the French
physicist and mathematician J. B. J. Fourier The furnace of a suspension-fired steam gen-
formulated the basic law of heat conduction, erator is a large water-cooled chamber in which
which may be expressed as follows: fuel and air are mixed and burned. Its purpose
is to generate heat under controlled conditions
with the objective of doing useful work in a
steam turbine or other machine. In a thermal-
circulation (non-pumped circulation) furnace,
some of the heat absorbed is used to move the
water-steam mixture against the internal fric-
tvhere k is the thermal conductivity, A, is a tional resistance of the 1-in. to %in. diameter
constant cross-sectional area, and dTidx is the furnace-wall tubing.
temperature gradient at the section. The minus FURNACES FOR PULVERIZED COAL FIRING
sign signifies that the heat is flowing in the
Furnaces for burning coal are more liberally
direction of decreasing temperature, in accord-
sized than those for oil or gas firing. This is
ance with the second law of thermodynamics.
necessary to complete combustion within the
Radiation confines of the furnace and to prevent the for-
mation of objectionable ash or slag deposits.
In 1879, Joseph Stefan empirically discov- Furnace-wall heat-absorption rates are low
ered the third fundamental law of heat transfer, enough that tubing metal temperatures do not
the basic equation for total thermal radiation greatly influence the furnace size.
COrnVSTION
Designing For Boiler Performance
--
The furnace dimensions of a unit to fire pul- Once the furnace size has been established,
verized fuel have a major influence on the ar- (based principally on experience with similar
rangement of firing equipment, the location fuels burned in other units), and the windboxes
and quantity of convective heat-transfer sur- have been located in relation to the panels and
faces, the quantity and length of soot blow- platens i n the upper furnace, an analysis is
ing equipment, the amount of supporting made to arrive at the outlet gas temperature.
structural steel, the extent of platforms and FURNACE ANALYSIS
stairways, and the arrangement of ductwork. A
furnace must be properly proportioned, with Analysis here means the engineering solu-
adequate height between the top row of coal tion to yield the information required by an
nozzles and the furnace arch, to assure engineer for the design of tangentially fired
adequate retention time for the gaseous com- utility furnaces. The gas-side requirement is
bustion products. The upper furnace area uses two-fold: (1)selection of the requisite grade of
widely spaced superheater or reheater panels water-wall steel requires, quantitatively, the
and platens to further cool the gases. These axial absorption profile, and (2) the furnace
measures insure that the furnace outlet tem- outlet temperature must be known to within
perature at the entrance to the close-spaced about -C5OoF to correctly size the sequence
convection surfaces will be sufficiently low to of superheaters, reheaters, economizers and
avoid excessive ash accumulations. air heater.
A designer determines the furnace plan area Since analysis of radiative transfer between
by carefully studying all of the coals antic- parallel planes is not trivial, study of a vortex-
ipated to be burned and arriving at an appro- fired utility furnace becomes a project of fair
priate value of net heat input to plan area magnitude. This may be verified by a scan of
(NHIIPA). Values presently used for a wide the family of "Parallel Plate" p a p e r ~ g -Thus,
~~.
range of coals are from 1.4 to 2.0 million Btul the analysis of industrial furnaces has devel-
hr-sq ft. oped on an overall phenomenon basis. An early
FURNACES FOR OIL AND NATURAL-GAS FIRING
example of this is the Rosin Equation (1925) for
coal dust flames, discussed by Essenhigh in
Oil does not require, at what has been normal References 24, 26, 27 and 32.
excess-air requirements, as large a furnace The engineering approach to various aspects
volume as coal to achieve complete combus- of furnace behavior, as distinguished from the
tion. However, the rapid burning of and high theoretical approach, is reasonably well charac-
radiation rate from oil results in high heat- terized by24-31 and also well represented by
absorption rates in the active burning zone of Thekdi et al.32 An excellent survey of the cur-
the furnace. The furnace size must, therefore, rent state-of-the-theoretical-art is given by Beer
be increased above the minimum required and Siddall.33
for complete combustion, to reduce heat- A promising approach is the Hottel zoning
absorption rates and avoid excessive furnace- method,34-36 which is intended as a realistic
wall metal temperatures. scheme for calculating radiant heat exchange
Natural-gas firing permits the selection of with respect to volume-distributed heat release.
smaller furnaces than for oil firing primarily Although from the literature it is clear that the
because a more uniform heat-absorption pat- zoning method has gained widespread accep-
tern is obtained. tance, rigorous solutions for utility furnaces are
This brief discussion of furnace sizing relates not yet available.37
primarily to tangential firing. Some of the EMlSSlVlTY O F THE COMBUSTION PRODUCTS
statements made do not necessarily apply to
furnace and firing-system combinations em- Furnace heat-transfer calculations must deal
ployed by manufacturers other than C-E. on a quantitative basis with the emissivity of
COMBUSTION
Designing For Boiler Performance

the gaseous products of combustion, gas-to- Similarly, the radiation contribution by the
gas absorptivity, and metallic-surface-to-gas unburned fuel itself, if the ignition tempera-
absorptivity. tures are high, may not be insignificant either.
Because about 95 percent of the heat transfer At this time, neither the chemical and reaction
in large combustion chambersis by radiation, it kinetics nor the individual spectra are estab-
is important to evaluate the radiative power of lished or even known completely.
the gaslfuellflame media. If heat transfer re- Only the main products of combustion, COz
quires quantification, the emissivity of the and H 2 0 ,have accepted emissivity values. An
radiating components in the furnace must be engineering approach based on COz and H 2 0
known. To make this identification, however, radiation with an allowance for other con-
demands the capability to predict the forma- tributors constitutes an acceptable alternative
tion, space-dependent concentration, and life- because the design engineer is interested in the
time of transient species such as OH, C, CO, CN, effective overall gas emissivity as it results
HCN, N, NO, HCO, H, C2,CH and other radicals from the interacting radiating components.
which may be present. Not the least problem in This requires establishing a relation by which
the determination is predicting soot formation the total effect can be expressed in terms of
(size, distribution, and density) in hydrocarbon known components.
flames or particle radiation in coal flames.

DEFINITIONSUSED IN FURNACE DESIGN

Effective Projected Radiant Surface (EPRS) Heat Available or Net Heat Input
Effective projected radiant surface is the The thermal energy above a fixed datum
total projected area of the planes which that is capable of being absorbed for useful
pass through the centers of all wall tubes, work. In boiler practice, the heat available in
plus the area of a plane which passes per- the furnace is usually taken to be the higher
pendicular to the gas flow where the fur- heating value of the fuel corrected by sub-
nace gases reach the first convection tracting radiation losses, unburned combus-
superheater or reheater surface. In calculat- tible, latent heat of the water in the fuel or
ing the EPRS, the surfaces of both sides of formed by the burning of hydrogen, and ad-
the superheater and reheater platens ex- ding sensible heat in the air (and recircu-
tending into the furnace may be included. lated gas if used) for combustion, all above
Furnace Volume an ambient or reference temperature.
The cubage of the furnace within the ~valls Furnace Release Rate
and planes defined under EPRS. Furnace release rate is the heat available
Volumetric Heat Release Rate per sq ft of heat absorbing surface in the fur-
The total quantity of thermal energy nace (the EPRS)'
above fixed datum introduced into a fur- Furnace Plan Heat-Release Rate
nace by the fuel, considered to be the prod- Furnace plan heat-release rate is usually
uct of the hourly fuel rate and its high heat based on the net heat input at a horizontal
value, a n d expressed in Btu per hour per cross-sectional plane of the furnace through
cubic foot of furnace volume. This value, the firing zone, expressed in million Btul
does not include the heat added by pre- hr-sq ft. The area of thefplan is calculated
heated air nor the heat unavailable through from the horizontal length and width of the
the evaporation of moisture in fuel and that furnace taken from the centerline of the
from the combustion of hydrogen. waterwall tubes.
COMBUSllON
Designing For Boiler Perfonnanco

MODIFIED EMlSSlVlTY
AND ABSORPTIVITY FACTORS

An assumption that fuel and air are ideally


and instantaneously converted to CO, and
H,O seriously underestimates the waterwall
heat-absorption rates. That is, the Hottel emis- where FAis the gas-to-gas radiation factor for
sivities34 used for calculating radiative trans- combustion products.
fer, even though they have been confirmed time The F, factor, as defined, is not related to fac-
and time again (see Ref. 39), constitute only tors published elsewhere.42 The behavior of F,
a partial contributor to the emissivity in a is physically what one would expect for a tran-
tangentially fired furnace. It is clear that an sition region from a Hottel radiation, FE = 1,
additional emissivity factor i s necessary. dependent on beam length, pressure, and tem-
Bueters4k41 showed that the source condition perature, to the black-body limit, FE -+ a,
required "blackening", which led to the de- where emissivity is independent of beam
velopment and use of the "FEoperator". length, temperature, and pressure. This is illus-
trated by Fig. 8 where (FE= 1) is taken at typi-
=
energy actually radiated by the system cal Hottel values for industrial furnaces of 0.2,
energy radiated if the system were black, 0.3, and 0.4,all at temperature T. The F, "oper-
ator" has therefore been adopted as being fun-
the combustion-product emissivity is related to damentally preferable to using a multiplying
Hottel emissivity according to the equation factor or corrective addition on
To determine and correlate source descrip-
tors such as FE,the heat-absorption profile and
E = FE -FE
1 + EH, I I F E < " furnace outlet temperature are measured on
operating steam-generating units. The result-
(19)
ing data is processed by a computer which uses
it as a boundary condition to solve for source
It follows that the wall-to-gas re-radiation ab- descriptors.41
sorptivity is blackened accordingly, or F, values for large natural-gas-fired furnaces
are about 1.2. Applying this to a Hottel emissiv-
FE - 1 + CYH
g,a =
FE
(20)
Blackbody Limit-
1.Or
where,
E = combustion products emissivity
FE =a value which modifies Hottel emis-
sivities to yield combustion-
products emissivity
EH = the combined emissivity for CO, and
H,O as given by Hotte138
a
,, = gas absorptivity with respect to
bounding-surface radiation
a, = gas absorptivity as given by Hottel38

The gas-to-gas absorptivity, a,,,, is analog- Fig. 8 Combustion products emissivity (ii)
ously defined as (for radiating components) vs FE .
CoMnusnoN
Designing For Boiler Performance

ity of about 0.34 for gas temperatures in the where


range of 3000E one arrives at E = 0.45:This q = heat given up by flame Btulhr
accounts for additional contributions by con- 0.17134 X Bt~lft~-hr-(OR)~is the Stefan-
vection, transient species,-and soot. An altered Boltzmann constant,
Hottel emissivity of about 0.39 would be esti- = effective exchange factor to account
6
mated from the work of Ludwig and Boyton on for infinite number of reflections and
water vapor.43 Assuming that this is a more ex-
re-radiations; written in terms of sur-
act value and that convective transfer is 4 to 5 face emissivity (dimensionless)
percent, we can postulate roughly
eg = radiative (combustion products)
emissivity, dimensionless
0.45uT4= Hottel radiation + convection = effective surface area of flame en-
+ additional radiation A,
velope and receiving surface when
equal, sq ft
a, = fraction of bounding-surface radia-
tion which is absorbed by the gas, as
For a rather typical temperature of 3500R1 above
we would arrive at a convective coefficient of T, = gas temperature, OR
T, = cold-surface temperature, OR
This equation is used to formulate the gas-to-
gas radiation exchange and gas-temperature
distribution inside a furnace by means of a hor-
izontal slicing technique.41
In Eq. 23A, the area of the flame will vary
This value is in the range of values for combus- substantially with furnace design and fuel
tion chambers given by Steward and Cannon.44 fired. The type of firing used affects the rate at
When quantitative convective correlations which gas sweeps over heating surface, and the
for tangentially-fired furnaces have been de- area of the flame varies with the rate of firing,
termined along the lines established by Kottel, other things being constant. Flame emissivity
the FE value for fuels on which no operating ex- depends on many factors including
perience is available may be predetermined. flame luminosity due to burning particles
RADIATION FORMULATION the concentration of water vapor and carbon
dioxide in the flame
Hottel and Egbert4s give a Stefan-Boltzmann
form of equation for net radiation as the volume of flame and its temperature.
The temperature of the flame envelope will be
neither constant nor uniform in a watercooled
furnace of a steam-generating unit. Combus-
tion characteristics of different firing equip-
ment vary widely. Some produce a short,
but intense and highly turbulent flame, while
Modified by FE, this equation becomes combustion with others is relatively slow,
thereby producing a comparatively long flame
of greater volume.
Although for any given furnace the area of
cold surface is fixed, slag accumulation may in-
fluence its effectiveness. The emissivity of the
watercooling installed depends on the material
COMBUSTION
DesigningFor Boiler Performance

used and its condition. For an oxidized steel


furnace, however, the emissivity will approach
unity at high temperatures.
Generally, the temperature of the cold surface
may be taken as that of the water and steam in- where c, is the mean specific heat at constant
side the tube, without introducing an apprecia- pressure from 70F to the leaving temperature,
ble error. But depending on its area, thickness T, is the gas temperature leaving the furnace,
and density, slag accumulation will affect not and M is the mass flow rate of gas.
only the area but also the temperature of the The heat absorbed by the radiant heating sur-
cold or receiving surface. (See Appendix B, De- face exposed to the furnace gas is the difference
termination of Coal-Ash Properties.) between the net heat liberated in the furnace
DESIGN APPROACH available for absorption and the heat content of
the gas leaving the furnace.
From the foregoing discussion of the vari-
ables affecting the temperature field and TYPICAL FIELD TEST RESULTS
radiant heat transfer in the boiler furnace, the Reference 46 reports a full scale field study of
reasons why the designer does not usually ap- the foregoing design approach. The study in-
proach the problem in a purely theoretical volved a 600-MW tangentially-fired boiler
manner should be apparent. In practice, the de- burning a highly slagging high-volatile bitu-
signer resorts to the use and interpretation of minous coal in pulverized form.
empirical data collected from boilers of similar The boiler furnace, shown in outline in Fig.
design operating under similar conditions. 9, is 56-ft wide, 49-ft deep, and 183-ft high.
Known theories of heat transfer are applied to During the tests the net heat input on the plan
the empirical data so that they may be used for area was 2.1 x lo6 Btulsq ft-hr. Furnace temp-
conditions differing from those tested. This is eratures were measured using aspirating,
necessary to improve and advance the art of de- single-shield high-velocity thermocouples on
signing boiler furnaces. Furthermore, to pre- 15-ft water-cooled probes extending 14 ft into
dict the temperature of flue gas leaving a given the furnace.
furnace in advance of actual operation requires
a background of accumulated-data, experience
and judgment generally possessed only by
manufacturers of the equipment involved.
In the simplified empirical design approach,
traverses are made of the gas stream leaving
-Elev. 138'
the furnace to determine the weighted average
temperature. Such measurement of boiler fur-
nace performance is simple in principle but
difficult to attain in practice. There are many
problems in taking measurements at high Windbox
temperature in a complex equipment config-
uration of large size.
The average outlet temperature, along with
the calculated mass flow of the products of
combustion and the mean specific heat above -Eiev. 0'
an arbitrary datum, will give the heat content of . -

the gas leaving the furnace above the datum.


This may be done according to the following Fig. 9 Test furnace outline, showing
equation: test-probe elevation 138 ft.
COMBUSTION I
Designing For Boiler Psrlormance

Table I11 summarizes the gas temperatures FLOWOFHEATTHROUGH FURNACETUBES


measured at the 138-ft level through 7 sighting The heat which is given up by the furnace
ports opposite the furnace nose. The average gas, and which results in the generation of
gas temperature reported in this test program steam within the tube exposed to that gas, must
for the 7 traverse lines is 223ZF, with a maxi- pass through a series of resistances: the gas film
*
mum variation of 150F. (Temperaturesmeas- adjacent to the tube; slag on the tube surface;
tube wall; internal scale deposited by the water
ured in ports 2, 3, and 4 were done on one day,
and are higher than those measured in ports 5, evaporated; the water and steam film. If the slag
6, 7 , and 8 on the next day.) As is to be ex- and scale are not bonded intimately to the tube
pected, temperature levels anywhere in a large surface,two more resistances may be added: the
furnace firing pulverized coal will vary gas film between the slag and tube, and the
throughout a day, and through a week. This oc- steam film between the internal scale and the
curs as a function of the thickness of slag and tube wall. Fig. 10 illustrates the temperature
ash on the furnace walls, the sootblowing pat- gradient resulting from the flow of heat through
tern, slag falls during the night, and burner some of these series resistances.
flow and mixing patterns.4: Heat transfer through the gas film and the
evaporating film does not follow the simple
equation for conduction. The temperature gra-
ELEMENTS OF dient through the other resistances, however, is
BOILER HEAT TRANSFER inversely proportional to the thermal conduc-
Earlier, this chapter introduced the concepts tivity. For conductance through a body having
of heat transfer by various models. Ref. 47 gives flat parallel plane surfaces, the following equa-
much of the historical background of their de- tion may be used:
velopment. From an understanding of these
concepts, it is apparent that the calculation At - (9'Av) x
of heat transfer occuring in superheater, re- k
heater, and economizer sections downstream (25)
of the furnace has a first-order dependence on where
the furnace-outlet gas temperature. And, after
the different types of surfaces are installed and At is the temperature drop across any single
the unit goes into operation, the furnace leav- thermal resistance,
ing temperature has a similarly significant ef- qlA,is the heat flux per unit of surface area,
fect on how they perform. xis the thickness of the resistance, and

Table ill. Gas temperatures at elevation 138 ft


Temperature,"F
Traverse
Distance'"' ZI~I 3 4 5 6 7 8

(a) Distance in feet from boiler inside wall.


(b) Port number (typical).
COMBUSTION
Designing For Boiler Performance
--
k is the thermal conductivity for unit thick- FLUID-TO-FLUID HEAT-TRANSFER RATES
ness, The fundamental theory of heat-transfer in
all expressed in consistent units. the steady state is analogous to, and based on,
For radial heat flow in a tube wall we write: the same concept as Ohm's law, namely: That
flow varies directly as the potential and in-
versely as the resistance. Thus in Fig. 10, the
potential between the two fluids is the tempera-
ture difference (& - t,), and there are five resis-
tances in series-the hot fluid (gas) film, the
where r 2 is the outside radius, r, is the inside slag or ash layer, the metal separating the
radius, and qlA, is the heat flux at the outside fluids, the internal scale or sludge layer, and
tube surface, again in consistent units. the cold-fluid evaporating film.
The temperature gradient shown in Fig. 10 is
typical of furnace tubes exposed to radiant heat. Applying the Ohm's law analogy, the flow of
heat, Q, will equal the temperature difference
From inspection, the resistance having the
divided by the resistance. In each instance,
dominating influence on heat-transfer rate is as with Ohm's law the resistance is the re-
that through the gas film. Thus, for many prac-
ciprocal of the thermal conductance.
tical purposes, the temperature of the receiving
In a boiler bank or economizer the tempera-
surface may be taken as equal to that of the
ture difference, A t,, between cold fluid and
water and steam within the tube. This approxi-
clean heating surface will be very small com-
mation can be closer to fact when studying
transfer in convective zones than it is for fur- pared to A t,, because the thermal conductance
nace-wall tubes. Accumulations of slag or ash of the water film is high. But in a superheater or
on the outside surface of furnace tubing, or reheater the dry steam becomes the cold fluid,
scale on the inside, may easily become the con- and the temperature gradient across the film
will be higher because the thermal conduc-
trolling resistance to any heat transfer if allowed
tance of these films is lower.
to form unchecked.
The designers of boiler banks and economiz-
As described in Chapter 20, Power Plant
ers, therefore, are interested only in the overall
Water Technology, inside scale can cause suffi-
cient increase in tube metal temperature to pro- thermal conductance or heat-transfer rate, and
are not greatly concerned with the intermedi-
duce overheating and rupture.
aterates ortemperatures,becausethe metal tem-
perature will be close to that of the cold fluid.
On the other hand, designers of superheaters,
furnace waterwalls, and reheaters-arealso con-
cerned about the metal temperatures.

Whether the gas flows parallel or transverse


to the tube-bank axis has a major effect on the
rate of heat transfer. When gas flows through
tubes, the flow is parallel to the axes for their
entire length. When flowing outside tubes,
however, there is usually a combination of
parallel-flow convection and cross-flow con-
vection, in addition to local radiation.
Fig. 10 Temperature gradient for furnace- Equations for heat transfer with parallel flow
wall tubes exposed to radiant heat, with slag contain a factor for inside tube diameter, but
accumulation the actual tube diameter can be used only when
COMBUSTION
Designing For Boiler Performance

the gas actually flows through the tubes. For convection rate, it will be understood to in-
flow outside the tubes, an equivalent diameter clude this radiation, and the expression-pure
is used: convection will be used in connection with all
data or curves not includinnkthisallowance.
An analysis of pure convection will show
that the heat-transfer rate per unit area of heat-
ing surface will be affected by numerous vari-
ables given in the following expression.
where d, is the equivalent diameter, A, is the
Rc = f(D,V, P, EL,CP, k, a)
free gas passage area and P is the gas-touched
perimeter of tubes, all in consistent units. where:
When calculating the heat transfer in a R, = film conductance, fluid to solid, for pure
parallel-flow pass of a boiler, coefficients for convection
flow parallel to the axis of the tubes should be D = linear dimension of solid surface
applied only to those portions where the gas is V = linear velocity of fluid stream
confined between parallel baffles and forced to - p = density of fluid
, travel with minimal turbulence along the axis p = viscosity of fluid
of the tubes. For the portions at the ends of such
passes, cross-flow transfer rates may be used c, = specific heat of fluid at constant pres-
for the effective surface opposite the entrance sure
and exit openings. Consideration should be k = conductivity of fluid
given to the variation of mass velocities in a = geometric relation ratio or combined
those portions, if any. ratios to cover the effect of spacing,
In general, the convective heat-transfer coef- width, depth and length
ficient with flow across tube banks is con- Investigators have found that good correla-
siderably higher than with parallel flow. Under tion of test data has resulted when these vari-
some conditions it is twice as much for compa- ables are combined into dimensionless groups
rable velocities. Fig. 11 shows the approximate or ratios, as follows:
variation. The upper limit represents flow Nusselt number or group = Nu = R, Dlk
across small diameter tubes, and the lower Reynolds number or group = Re = DV plp
limit, flow parallel to tubes that are spaced on Prandtl number or group = Pr = c, CJk
relatively wide centers.
FACTORS AFFECTING CONVECTION
HEATTRANSFER FROM GAS
Among most designers of steam-generating 20
L-

equipment, the convection heat-transfer rate in P


those parts of the apparatus not exposed to ELL15
2 O,

luminous radiation is the overall rate between I-%


-L
the fluid giving up and the fluid receiving the 3 ~ 1 0
~h
za =
heat. It has been shown that the gas film con-
ductance may be used instead of the overall rate
without much error in certain parts of the
-
a
5 5

equipment. But even the gas film conductance 0' 2 4 6 8 10 12


must include a factor or an addition to allow for -
Mass Velocity 1000 Lb/Hr-FtZFree Area
nonluminous radiation from hot gases, such as
carbon dioxide and water vapor, both of which Fig. 17 Chart showing the range of convective
are present in the products of combustion of all heat-transfer rate between conditions of parallel-
common fuels. Therefore, when we speakof the and cross-flow of gas
--
COYImnON
hdgnlng For &Nor kdonnance
-
For forced convection it may, therefore, be perature has been allowed when this group is
written that omitted. In general, heat-transfer equations
containing no temperature term, or containing
none of the fluid properties which vary with
R D l k = f[(DV PIP), (c, ~ l k l (all
,
(28)
temperature, are to be considered only for lim-
ited application i n the range for which the
heat-transfer equations are derived.
Expressed in terms of power functions, this In regard to tube arrangement and spacing, it
becomes has been definitely established that, in banks of
tubes, the depth of the bank affects the heat-
transfer rate. here is a marked increase for
each row up to about the fifth, and gradually
less and less increase to the tenth. This is
in which caused by increased turbulence from row to
= constant proportionality factor to be row. For one particular Reynolds number, and
k,
experimentally determined other variables kept constant, Pierson48 found
approximately 2 5 percent lower cross-flow
Fa = arrangement factor replacing a, to be heat-transfer rate for two rows than for ten rows
experimentally determined
for both in-line- and staggered-tube arrange-
M = V x p = mass velocity of fluid ments, but the difference between five rows
m, n = power functions to be experimentally and ten rows was about 9 percent. Experiments
determined of other would indicate that a very turbulent
The factor, a, and Fa in the two foregoing gas stream, on approaching the bank, may af-
equations could probably be eliminated if all fect these comparisons and produce higher
parts and dimensions of all heat-transfer ap- heat-transfer rates for shallow banks than indi-
paratus were geometrically similar. This is im- cated in previous text.
possible in commercial practice, and has not It is obviously incorrect to expect staggered
always been done in designing apparatus for tube rows to give better cross-flow heat transfer
research purposes. Therefore, where D in these than tubes in line without considering the ef-
equations is merely taken as tube diameter, fect of depth spacing in the direction of flow.
complete agreement between data from differ-
ent sources is not to be expected. This may Mean Gas Temp. O F
partly explain the disagreement in values of m,
n and k as determined by different inves-
tigators. Higher values for n have been found
for flow parallel to the axis of tubes than for
flow transverse to the axis.
The numerical value of the Prandtl group, c,
plk, is nearly the same for all the constituents of
flue gas, and, therefore, is practically constant
for all flue gas at a given temperature. There is
little opportunity to determine by experiment
to what extent this group enters into heat trans-
fer from gas, and some investigators do not in- I l l I I I I I
clude it in their equations. However, there is 2000 4000 6000 8000
considerable variation in the specific heat of G Mass Velocity - Lb/Ft2-Hr
gases at high temperature, and there is no
certainty that proper correction for gas tem- Fig. 12 Convection transfer rate
COMBUSTION
Designing For Boiler Performance

When the depth spacing is great in both cases, equation forming the basis for either curves or
so that the stream has a chance to expand fully computational programs is
after passing each row, there can be no possible
advantage with staggered rows, and the two
s h o u l d be equal. The method used by
Grimison49 for correlation of Pierson's and where
Huge's50 data indicates this to be true under R, = pure convection heat transfer, gas to
certain conditions, but it is also affected by the
metal
gas velocity when tube diameter and tempera-
ture are maintained constant. kc = a constant
CONVECTIVE HEAT-TRANSFER RATES
c, = specific heat of gas at constant pressure
In day-to-day calculations of superheater M = gas mass velocity through the free area
and reheater heat transfer, it is convenient to between the tubes
work from curves that synthesize the above D = tube diameter, all being in consistent
factors. For convection transfer, the general units
and x and yare exponents; the constant and the
exponents must be determined empirically and
depend on tube arrangement and spacing.
From tests on large steam-generating units or
other heat-recovery equipment, it is difficult to
ascertain the precise effect on heat transfer of
variations in velocity, tube diameter, distribu-
tion and direction of flow, tube spacing, or gas
temperature. But it is, nevertheless, necessary
to adjust the various coefficients and expo-
1 2 3 nents in such basic relations as Eq. 30 to reflect
Tube Diameter, Inches operational experience.
Typical parametric curves based on test data
Fig. 13 Convection transfer-rate correction are shown in Figs. 12, 13, and 14. The overall
factor'for tube geometry convection rate is R, = R', x F, x Fa.

I
% (Saturation +Mean

Gas
Flow

u
Mass Velocity - Fa
1O3 Lb/Ft2-Hr
I I
Fig. 14 Convection transfer-rate correction factors, Reynolds number and tube geometry
D.Jgning For Boiler Performance

beam length is calculated according to Fig. 17


Carbon dioxide and water vapor are the prin- and is entered into Fig. 18 to obtain the beam-
cipal radiating components of boiler flue gas; length correction factor, F,,. The basic non-
their combined radiating effect has historically luminous rate from Fig. 15 is multiplied by F,
been referred to as nonluminous radiation. (Fig. 16)and F, to get a corrected rate to be used
Transfer rates and radiant beam lengths for in subsequent calculations.
nonluminous radiation are to a great extent EFFECT OF VARIATION IN TEMPERATURE DIFFERENCE
based on work done by Hottel and others previ-
ously referenced. The temperature difference between gas and
In all cases where the flue-gas temperature is steam, water, or air produces the flow of
high and the tube spacing relatively great, the heat; the logarithmic temperature difference
nonluminous radiation will be of considerable (LMTD) represents the effective difference be-
magnitude and should be added to the pure tween two fluids. The LMTD depends on the
convection rate. Figs. 15 through 18 show typi- relative directions of flow of the fluids as they
cal rates and correction factors. The radiant pass through or over the surface. That is, do

8 12 16 20
Mean Gas Temperature,O F % Moisture in Products by Weight
-
Fig. 76 Fuel correction factor for
Fig. 75 Transfer rate - nonluminous radiation nonluminous radiation

Lb = 0.09( ' a ) - 0.07D


D
Lb = Feet
ST, SL, D = Inches
I)
LC I.'///, ,
Gas Flow - 0.1
0.1 1 .o 10
0 0 - Beam Length, Lb-Ft

Fig. 77 Radiant beam length, in-line tubes Fig. 78 Correction factor, radiant beam length

6-26
COMBUSTION
Designing For BoilerPerformance

they flow counter to, parallel to, or across one clean heating surface will be very small com-
another. For parallel or counter flow pared to the temperature difference between
the clean surface and the mean gas temperature
greatest difference - least difference because the thermal conductance of the water
LMTD = reatest difference film is high. In a superheater or reheater, on the
loge(8least difference ) other hand, the temperature gradient across the
or, cold film will be higher because the thermal
conductance of these films is lower.
In the design and proportioning of waterwall
and economizer surface, interest is primarily in
the overall thermal conductance or heat-
where AT, and AT2 are given in Fig. 19. These transfer rate. The intermediate rates or temper-
figures show that for a given heat recovery the atures are of secondary concern because the
greatest temperature difference will be ob- metal temperature will be close to that of the
tained, and the least heating surface required, cold fluid. Design of superheaters, reheaters
when the two fluids flow counter to each other. and waterwalls must also consider the metal
Furthermore, with parallel flow, the highest temperatures. In the case of superheaters,
temperature of the heated fluid can only ap- knowledge of metal temperature is necessary
proach but not equal the lowest temperature of for the most economical use of alloy material.
the heating fluid. The designer of a heat-transfer device such as a
In waterwalls or economizer surface, the tubular air heater, on the other hand, must
temperature difference between cold fluid and know the temperature of the metal separating
the two fluids to combat condensation of

1 r p p e r i t u r e
L 9
a ATI -
L

I- c
Surface - Surface --
(a)Counter Flow (b) Parallel Flow

t t Saturated Steam
r

5f
-
CI

$ ATI
I- water ~ezperature
e
e'
L/rn~era~'"

Surface
(c) Boiling
- Surface -
(d) Coqdensing

Fig. 19 Fluid temperatures in heat exchangers


COXBUSTION
Designing For Boiler Performance
-
moisture and acid vapors, or to minimize the ef- surface will equal the heat given up by the gas:
fect by selection of noncorrosive materials.
APPLICATION OF HEAT-TRANSFER RATES q = M s p AT
TO BOILER CALCULATIONS (33)
As discussed, superheater and reheater tubu-
lar surfaces in the upper furnace and beyond, where M, is the mass flow-rate of gas, c,, is the
(loosely termed the "convection pass") absorb mean specific heat at constant pressure, and AT
heat in three ways: by direct radiation from the is the gas temperature drop, all in consistent
flame; by nonluminous radiation, chiefly from units. Figs.20 and 2 1 give specific heats at con-
the carbon dioxide and water vapor in the com- stant pressure of the products of combustion of
bustion gases; and by heat transfer through several solid, liquid, and gaseous fuels, burned
pure convection. at usual excess-air percentages. Fig. 22 with
The contributions from these sources are ad- specific heats of air at varying noisture con-
ditive and directly affect both heat absorption tents is useful for air-heater calculations.
and metal temperatures. That is, a superheater When heat transfer in commercial apparatus
in a high-temperature gas zone that "sees" the is calculated from changes in fluid temperature
fireball may have the same convection rate, R,, determined by test measurements on similar
as a low-temperature superheater section in a apparatus, several additional errors may be in-
1000F zone. But the effective overall transfer troduced. In taking the temperature readings,
rate, in this instance including the long-beam- the gas stream is large, and simultaneous read-
length-radiation, may be double the Re ings at many points are necessary. If there is
From the second law of thermodynamics, we stratification or nonuniform flow, the arithme-
know that a given surface will absorb heat tic average of these readings may introduce an
proportionally to the temperature difference error which may be much larger than any error
and the transfer rate. in the temperature readings themselves. An in-
correct specific heat value will introduce
another error which can be eliminated in the
qlA, = R, (LMTD)
(32)
research laboratory by supplying the heat in
some way which can be measured with a high
degree of accuracy.
where q is the heat absorbed per unit time, A,is
For any heat-transfer surface, then, the gas
the area of the heating surface, R f is the overall
temperature drop is
transfer rate, and LMTD is as previously
defined-all in consistent units.
The logarithmic mean temperature differ-
Rt49,(LMTD)
ence must be used in Eq. 32 because the reduc- AT, =
MSCP
tion in temperature between T I and T2is not
directly proportional to the amount of surface
passed over. For small surfaces, and for values
of AT2 greater than half AT1,the arithmetic where the transfer rate and the heating surface
mean temperature difference can be used are defined on the same basis-tubing inside
without appreciable error. diameter, outside diameter, or mean-wall di-
Also, for a closed system in which the weight ameter. Rt is the total rate, equal to pure convec-
of gas entering is equal to the weight leaving, tion rate plus nonluminous transferrate. A

and in which losses due to radiation and con- Where luminous or "long-beam" radiation
vection from the boundary walls can be ne- from the fireball is to be taken into account,
glected, the quantity of heat absorbed by the curves such as in Fig. 2 3 are used to give
Bagasse, 50% Moisture
Wood, 50% Moisture .-
Wood, 30% Moisture
Lignite
SubbituminousCoal
High Volatile Bituminous Coal
Low Volatile Bituminous Coal

. ,4 8 12 16 20 24 28
Temperaturex 10-2,OF
I I
Fig. 20 specific heat at constant pressure for products of combustion of solid fuels

Coke Oven Gas

Blast Furnace Gas, Saturated at 60'

Temperature x 10-2," F

Fig. 21 Specific heat at constant pressure for products of combustion of liquid and gaseous fuels

4
3
2 Moisture
1 Curve L-, H~OIL-, Approximate Atmospheric
No. Dry Air Equivalent at 29.92 In. Hg

1 Dry Air
2 0.013 60% Rel. Humidity at 80F

3 0.025 60% Rel. s urn id it^ at 100F


0 2 4 6 8 10 12 14 16 18 20
Temperature x 10-2.0F 4 0.043 100% Rel. Humidity at 100F

Fig. 22 Specific heat at constant pressure of air at varying moisture contents


COMBUSTION
W g n i n g For Bdler Porfonnmc
-
radiant-heat absorption on flat projected areas Enthalpy of steam at 1005F and 488 psig =
of banks of tubing; they are to be corrected for Hz = 1523 Btullb
view factor and depth of tube bank. Enthalpy of steam at 680F and 500 psig =
H, = 1345 Btullb
CALCULATION OF A REHEATER Heat absorbed by reheater per lb of steam =
An over-simplified example of a single- AH = 178Btu
section reheater will tie together much of the Total heat absorbed by reheater = W,AH =
preceding discussion. Assume the section is 3,500,000 x 178 = 623 x l o 6 Btulhr. Sub-
located in a moderately high gas-temperature tracting the radiant heat absorbed (25 million
zone, with both inlet and outlet steam condi- Btulhr.),
tions known. It is then possible to calculate in
one step without assumption of intermediate
temperatures. Since q, is also the heat absorbed from the
gas, the following relationship, leading to the
KNOWN DATA solution of T2,may be expressed.
Tube diameter 2% in. OD
Free gas area, FGA 1675 sq. ft.
Number of assemblies, N 90
Steam temperature leaving, tz 1005 OF
Steam pressure leaving, P, 488 psig For solution of T2all values are known in the
Steam temperature entering, t, 680F above equations except c, which for an as-
Steam pressure entering P, 500 psig sumed temperature of 1790F, firing high-
Steam flow, W, 3,500,000 l b h r volatile bituminous coal, is 0.308 (from Fig. 19)
Gas mass flow, 1M, 4,600,000 l b h r
Gas temperature entering T, 2000F

CALCULATION OF HEATING SURFACE


Heating surface, A,, is the only remaining
The reheater section is counterflow and its unknown in connection with this reheater sec-
entering gas temperature, T,, is the same as the tion. This can be determined from
gas temperature leaving the superheater surface
upstream, previously calculated. A, = M,cAT,
------
To find the gas temperature leaving the re- R, (LMTD)
heater, T,, and the heating surface, S, required
to raise the steam temperature from 680F to
1005"F, the following steps are required. .-
The amount of direct furnace radiation which
passes through superheater surfaces ahead of
the reheater is first determined using the pro-
jected area of the tubing and a correlation such
as Fig. 23. Assume that the direct radiation ab-
sorbed by the reheater is 25 million Btu per I
I
hour. The total heat to be absorbed is now estab-
lished from the steam conditions in and out of
the reheater. The direct radiation is deducted to $k Gas Temperature Leaving Furnace, 'F
obtain the convective plus non-luminous heat
transferred, q,. Fig. 23 Radiant heat absorption at furnace outlet
COMBUSTION
Designing For Boiler Performance

From Fig. 24, which shows the temperature DRAFT LOSSES


gradient across the reheater, we calculate the AND THE SPECIFICATION
LMTD.
OF FANS
(TI - t 3- (Tz - tl) -& - -
LMTD = Intimately tied to the physical arrangement
TI - tz
Loge -
T? - tl of tubular heating surfaces and the determina-
tion of convective and nonluminous heat-
transfer rates is the draft loss, or pressure drop,
of the gases passing over them.
Although there is no direct mathematical re-
lationship between heat transfer and draft loss,
R, = Rn + Rc it can be said in general that convection trans-
R, =R:,XFbXFr . fer rates and draft losses are directly propor-
TI,, = t,,., + LMTD tional, but to an unknown power function. That
T I, = .+680 + 946 = 178gF is, the rate of heat transfer can seldom be in-
2 . creased'tvithout producing an increase in pres-
sure differential.
Assume a radiant beam length of 1 . 2 ft The engineer designing superheater, re-
heater, boiler bank, economizer, and air heater
surfaces has to balance the cost of heating sur-
R',, = 10.5 Btulhr-sq ft-OF face against the power penalty for pressure
(from Fig. 15)
drop and draft loss to arrive at an economic
Fb = 0.45 (from Fig. 18)
configuration. And because the several differ-
F, = Use 1.05
= 10.5 x 0.43 x 1.05 = 5.0 Btulhr-sqft-OF
ent transfer surfaces (depending on their de-
R,, sign pressure level and operating temperature)
R, = R: x F,, x F,
have widely varying costs per unit of surface
Mass velocity, G, is required to evaluate R', area, they too have to be evaluated carefully to
W2 -4,600,000 arrive at the optimum mix. It is because of this
G =---
FGA 1675 relationship of transfer rate and draft loss that it
= 2750 lblhr-sq ft is necessary to include here terminology and
R; = 9.5 Btulhr-sq ft-OF calculation methods for draft losses through
(from Fig. 11based on T , = 1789F tube banks and power-plant stacks.
Fd = 1.0 (from Fig. 13)
DRAFT
Use 0.95 for Fa (Fig. 14 would be used for Although often used in many ways, the term
actual tube spacings.) draft is defined here as pressure difference
below that of the atmosphere. The absolute
R, =R'.xF,xF, pressure of the atmosphere at mean sea level is
= 9.5 X 1.0 X 0.95
29.9 in. Hg, or 14.7 psia under conditions refer-
= 9.0 Btulhr-sq ft-"F
= R, + R, = 5.0 + 9.0
red to as normal barometer. Without any change
R,
= 14.0 Btuihr-sa ft-OF in elevation above sea level, barometric pres-
M, x c, x AT, sure may vary as much as 3 in. Hg from normal
S =
R, x LMTD conditions. Thus, as the absolute pressure cor-
responding to zero, or balanced draft, is quite
variable, it is customary, and more convenient,
to express draft values in terms of gage pressure
rather than absolute pressure.
C O ~ U S Z I O N..
Designing For Boiler Performance
--

"Hot" (Reheated) "ColdReheat-

. 1005F

Fig. 24 Schematic arrangement and temperature gradient across reheater


For example, a simple U-tube half filled with ously defined. The term induced draft is indi-
water may be used as a draft gage, by connect- cative of an absolute pressure lower than that of
ing one leg to a duct or furnace in which the the atmosphere, but the word induced is
pressure of draft is to be measured, and leaving somewhat superfluous when using the previ-
the other leg open to atmospheric pressure. If ous definition of draft. Nevertheless, these ex-
the absolute pressure in the furnace is exactly pressions are in common usage and are used in
equal to the absolute atmospheric pressure out- this text, despite these inconsistencies.
side the furnace, the water level in the two legs PRESSURE DROP AND DRAFT LOSS
of the U-tube will remain at the same elevation.
This is known as a balanced-draft condition, The difference between pressure gage read-
and the draft is said to be zero. On the other ings in parts of a system operating with a posi-
hand, if the absolute pressure in the furnace is tive pressure relative to that of the atmosphere,
less than that of the outside atmosphere, the is generally called pressure drop; whereas the
level in the tube leg exposed to the atmosphere difference between gage readings in parts of a
will move down, and the level in the other leg system operating with a negative pressure rela-
will move up. The difference in level is then the tive to that of the atmosphere, is generally
draft measured in inches of water, and gener- called draft loss. The actual gage readings are
ally written inches water gage ('WG). referred to as pressure or draft, as the case may
In recording draft readings it is not necessary be, except that in reporting data taken at a point
to place a minus sign ahead of the numerical where there is normally a draft, it'i's called draft
value of draft when the pressure at point of even when there is a pressure, but a plus sign
measurement is lower than that of the atmos- should be used as a prefix to the figures given.
phere. But if the absolute pressure at the point
of measurement is greater than that of the at- PRESSURE
mosphere, it should preferably be called pres- When the fluid to be measured has motion, it
sure. If it is called draft, the numerical values has a velocity pressure in addition to its static
should be preceded by a plus sign. pressure. The total pressure is the algebraic
FORCEDAND INDUCED DRAFT sum of velocity pressure and static pressure.
Static pressure is the force per unit area exerted
The term forced draft is indicative of an on a wall by adjacent fluid which is at rest, or
absolute pressure higher than that of the which is flowing without disturbance along the
atmosphere, and this expression is therefore wall of a conduit. To obtain the static pressure
not consistent with the word draft as previ- of a fluid at rest, use any pipe or tube having an
COMBUSTION
DesigningFor Boiler Performance

opening at the point in question. Generally, a STACK EFFECT


tube with a special construction at the end, Flow of hot gas or hot air in a vertical duct
called a "static tube," is used to determine the introduces a factor of correction for elevation.
static pressure of fluid moving i n a straight Because the fluid in the duct has a lower den-
conduit of sufficient length.. Sometimes, a sity than the outside air, stack or chimney effect
static hole in the wall of the conduit is used. (or thermal static draft) exists. The pressure
In the case of fluids flowing in curved paths, drop for downward flow increases, and it de-
such as near elbows, centrifugal force of the creases for upward flow, compared to what the
fluid affects the pressure. Care must be taken to pressure drop would normally be under the
locate static holes and impact tubes so that they same conditions in a horizontal duct. This
are not affected by curved paths, eddies, or tur- stack-effect correction may be of considerable
bulence; otherwise the determination of static magnitude when determining the true pressure
pressure or total pressure will be inaccurate. drop or draft loss in a tall piece of apparatus,
MEASUREMENT OF TOTAL PRESSURE
and can be of particular significance &a series
of boiler passages and flues, with the direction
Total pressure is measured with an open- of the gas flow alternately up and down.
ended tube (known as an impact tube) pointed The static draft, as this difference in pressure
upstream. The excess of total pressure as can be properly called, must be calculated,
shown by the impact tube over the static pres- since simple draft-gage readings indicate the
sure is the qxact equivalent of the energy rep- combined values of stack-effect and frictional
resented by the velocity. This difference is flow losses. The following formula is used:
known as velocity pressure or velocity head.
P
When static pressure is below atmospheric,
and therefore negative, the total pressure will
static Draft = 27.7 Z,
G. - PC)
Rd.
(35)
be a numerically smaller negative number, or
may even be pcsitive, depending on the mag- where static draft is in inches of water, the
nitude of the draft and the fluid velocity. height under consideration is Z, feet, pa and p,
Any statement of pressure should be accom- are the absolute pressures (psia) of the ambient
panied by an indication of whether it is static or atmosphere and the combustion gas, respec-
total, whether it is gage or absolute, and at what tively, T, and T, are the average absolute tem-
base plant altitude, if greater than 1000 ft above peratures, and R, and R, are the respective gas
sea level. After correction for difference in local constants. The value of R, is 5 3 . 3 , while that of
elevation, the difference in total pressure be- R, depends upon the composition of the gases.
tween two points in a closed system is a At usual excess-air percentages, R, is 52.2 for
measure of the pressure loss between them; the bituminous coal, 53.2 for fuel oil, 55.6 for natu=
difference in static pressure between the same ral gas, and 49.3 for blast-furnace gas.51
points will give the same result only if the fluid Note that the equation for static draft in-
velocities at both points are the same. When the volves only one dimension, the height of the
velocity of a fluid stream in a horizontal con- gas pass or stack, and that the static draft is the
duit is decreased by a diverging section, the maximum that can be produced by any such
velocity head is decreased and the static head pass of a given height when filled with station-
increased. Thus it is quite possible to have a ary gases of a given density and surrounded by
downstream static pressure that is higher than a still atmosphere of a given density.
upstream, even though there is a loss in total
pressure in the direction of flow. DRAFT-LOSS CALCULATJONS
See Chapter 22 on testing and measurements The variables in the pressure differential
for draft-loss observations in the field. across the convection surface of a steam-
COMBUSTION
Designing For Boiler Performance

generating unit include friction due to flow ameter, and inversely proportional to the vis-
across tubes; loss of head in turns; friction due cosity of the gas. Of the two main variables, the
to flow though, or parallel to, tubes; and stack tube arrangement is by far the more important.
effect. Named in order of magnitude, they Generally the friction loss from flow across
occur in practically all steam generating units. staggered tubes is considerably greater than for
Gas and air velocities in steam-generating tubes in a line. When tubes are in line, however,
units will always be such as to produce turbu- the friction loss will increase as the spacing in
lent flow, particularly at high unit ratings. the direction of gas flow is increased. When
Under these conditions friction loss, when that spacing reaches approximately four times I

measured in terms of inches of water, will vary the tube diameter, the friction loss will be I

directly as the square of the mass velocity, and the same, whether the tubes are in line or
inversely as density, which also means directly staggered. It is not within the scope of this text I

with the absolute temperature. Eqs. 36, 37, and to discuss in detail the variation of friction fac-
38 show the mechanics of friction loss for the tor with tube arrangement. A c!ose approxima-
I
three types itemized above. tion, however, is 0.24 when the tubes are in
--A
line, and 0.36 for staggered tubes.
Flow across tubes PD = fN H, The number of restrictions will be equal to
(36) the number of tube rows crossed over, unless
Turn loss PD = Kt x H,, the tubes are so staggered that the minimum
(37) free area for the passage of air or gas is deter-
mined by the diagonal clearance between adja-
L cent tubes. If that is the case, the number of
Flow along tubes PD = f -
D x H,
restrictions will be the number of tube rows
(38)
minus one.
where: A calculation of draft loss across 22 rows of
PD = pressure drop, " WG tubes in a convection bank, with the tubes on a
square pitch of 3*/2" is as follows:
f = friction factor, dimensionless
N = number of restrictions - Transverse
SDT = Outside diameter of tube -
Spacing 2%" -
3%"
Kt = constant, depending on type of turns
L = length of tube in ft
D = inside diameter, or equivalent diame-
ter in ft
H, = velocity head, " WG
The velocity head is calculated from Eq. 39.

where: 8000 12,000


G = mass velocity, lblhr-sq ft free area 3 Mass Flow, Lb/Hr-Sq Ft
d = density lblcu ft G=Mass Flow-Lb/Hr-Ft2
For flow across tubes, the friction factor will Re=? where -
D = E~uiv.Dia, ~t -. -
depend on the tube diameter and arrangement, P =viscosity- Lb/Ft Hr
and on the Reynolds number, which is in turn
directly proportional to velocity and tube di- Fig. 25 Mass flow versus Reynolds number.
COMBUSTION
Designing For Boiler Performance

sL=
- Longitudinal Spacing - 3l/2" primary-air ducts from the primary-air fans to
D Outside diameter of tube 2%" = the air heaters and on to the pulverizers.
Reynolds number (from Fig. 25) = Smaller ducts are needed for sealing air to pul-
21/2"
20,000 X -
10
= 5000 verizers and other equipment,
- and ignitor and
scanner cooling air.
Friction factor, f (from Fig. 26) = 0.092
To determine the size and performance of
Draft loss per restriction (from Fig. 27) = 0.027
these ducts, the designer must first establish
Draft loss through bank =
the predicted maximum flows, the allowable
(0'092)(22)= 0.55"WG
(0.027)- duct velocities (based on company standards
(0.100)
and parasitical-power costs), and both the am-
DRAFT LOSSES IN DUCTWORK bient barometric pressure and the effect of
Ductwork systems form a substantial part of a localized pressures in the ducts above or below
pulverized-coal steam'generator, both in phys- the ambient barometric pressure.
ical size and in cost. The principal elements are AIR AND GAS VOLUME CALCULATIONS
(a) the main cold- and hot-air ducts from the Air and gas weights result from the com-
forced-draft fans to the air preheaters, and then bustion calculations plus considerations of
to the furnace; (b) the hot gas ducts from the tempering air, air-heater leakage, and casing
economizer to the air heater(s) and then to infiltration. To convert gas weight to cubic feet
the emission-control equipment and on to the per minute (CFM) at sea level (14.7 psia), use
induced-draft fans; and (c) the high-pressure this relation.

Temperature," F for Evaluation


0.100
0.080
0.060

C
0.040
.-0
C
.-0
L.
C1

$ 0.020
F
a
3 0.010
v-
8
5 0.005
6

0.002

1 2 3 4 5 6 810
Mass Velocity, 1000 LbIHr-Ft2
I
Fig. 26 Friction factors for in-line tube banks Fig. 27 Draft loss across tube banks
COMBUSTION
Designing For Boiler Performance
-
Cold-air ducts 2000 to 2500 ftlmin
W, (T + 460)
CFM = (MW), 82.2 Hot-air ducts 3000 to 3500 ftlmin
(40) Gas ducts 3500 to 4000 ftlmin
Velocities can be higher at higher temperatures
where CFM is the cu ftlmin of air or gas at temp- because the gas is less dense and therefore has
erature T in OF, W, is the air or gas weight in less impact energy; lower static-pressure loss
lblhr, and MW is the apparent molecular results for a given temperature.
weight of the air or gas mixture in pounds.
This volumetric flow rate at 14.7 psia has to DUCT-LOSS DETERMINATION
be corrected for plant elevation above sea level Air pressu;e and gas draft losses are a power
using Fig. 7 and for local pressure in the function of velocity (approximately the square)
ductwork system. Fig. 28 illustrates the varia- and an inverse function of the specific volume
tion in pressure that exists in a ductwork sys- of the fluid. The most significant losses occur
tem from FD-fan inlet to ID-fan outlet. Actual in turns and at abrupt changes in flow area.
gas volumes at each point of interest must be Vaning is often necessary to reduce losses
calculated using a correction curve like Fig. 23. where there are tight turns or large variations in
VELOCITIES IN DUCTS
cross-section, such as between an air-heater
outlet and a precipitator inlet (where the gas
As a general rule, the following velocities are velocity drops below 10 ftlsec).
used in arriving at the cross-sectional flow Curves such as those in Figs. 30 and 31 are
areas of boiler ducts. used to proportion ductwork for desired pres-

Fig. 28 Profile of air and gas pressures through a steam generating unit

ABB
---"I
6-36
COMBUSnON
Designing For Boiler Performance

. 10,000 Ft (20.58" Hg)


5000 Ft (24.90 Hg )

0
m
LL
5 1.10-

I I I I I I
0 . -5 -10 -15 -20 -25 -30 -35 -40
Pressure - "WG Below Local Barometric Pressure

Fig. 29 Volumetric correction factor for negative pressure below the local barometric pressure. This pro-
vides an additional correction to the basic elevation correction curve, Fig. 6, to adjust for pressures in a
steam generator that are below the local atmospheric pressure. Calculated from the data of Standard
Atmosphere-Tables and Data to 65,800 feet, NACA Report 1235
sure or draft losses. They show that, for very The gas quantity calculation must make al-
large ducts, the resistance may be practically lowance for the number of boilers connected to
independent of length and almost wholly de- the stack, the maximum excess air at which
pendent on the design of bends. they may be operated, and the air leakage
DRAFT LOSS IN STACKS through idle units as well as through the many
A stack can operate to produce a net static duct connections.
draft or flow of gas because it contains acolumn The gas-density calculation involves a
of heated gas and is connected at its base, in- knowledge of the gas temperature from each
directly through the breeching and boiler, to unit, and the effect of air leakage on the total
the cooler outside air. To do so, the acceleration mixture temperature. Heat losses in emission-
loss of the gas and the friction loss from boiler, control equipment, ductwork, and the stack it-
ductwork, and stack must be overcome by the self must also be considered, because it is
theoretical differential static head between the the mean density in the stack that must be
hot and cold column, which in turn depends on calculated.
the height of the hot column and the density of The barometric pressure at plant elevation
the gas. (See Eq. 35.) must be taken into account, because it affects
Stack performance curves are usually plotted the density of both the heated column inside
for sea-level gas density, and corrections are the stack and the cold column of outside air.
made for elevations above sea level. It is obvi-
ous, however, that weather conditions which Fig. 32 is a convenient graphical method of
reduce barometric pressure have the same ef- analyzing a stack of given diameter and height
fect in reducing the capacity of a stack as if it for the net effect of thermal draft versus friction
were located at a higher altitude. Stack selec- loss. It is plotted for an 80F ambient tempera-
tion, or calculation of its performance, requires ture and sea level pressure of 29.92 in. Hg. The
the determination of: net gain or loss must be divided by the eleva-
tion correction factor (Fig. 7) for elevation
gas weight to be handled
above sea level, or for a depressed barometer
mean gas density within stack at elevation from atmospheric conditions that have to be
air density outside the stack, at elevation taken into account.
COMBUSTION
Designing For oiler .kdonnance

Ratio R/D=O

0.8
0
0.7 3
0.6 $
0.5 g Factor FRL W/D
0.4 5 R/D '12 1 2 4
Temperature, OF 1 o 0.0 1.23 1.00 0.88 0.70
0.3z 0.2 1.28 1.00 0.86 0.70
0.2 2 0.4 1.32
0.6 1.30
1.00
1.OO
0.88 0.72
0.97 0.70
0.1 0.8 1.33 1.OO 1.OO 0.73
1.O 1.38 1.OO 1.08 0.77
500 1000 1500 2000 2500 3000 3500
Velocity, FVMin. Elbow Loss = HL FTLFRL

Fig. 30 Chart for determining draftlpressure loss for 90" elbows

0
1.0 3
0.9 ;
0.8 2
0.7 %
0.6
8
0.5 7
'
V)
0.4 $
Ratio W/D

a 4.0 2
500 1000 1500 2000 2500 3000 3500 1
Veloc~ty,Ft/Min. Duct LOSS = H D F ~ ~ F(L/100)
RD

Fig. 31 Chart for determining friction loss for straight runs of ductwork

The effective height of the stack, rather than left to the boiler manufacturer. The fan mar:-
the actual height, is used with Fig. 32 as in any ufacturer assumes responsibility for producing
stack-effect calculation. If allowance has been the volume and pressure specified although
made for static draft in all apparatus and con- limited by the fact that standard fan test codes
nections between the boiler and the stack, then specify certain conditions which can be main-
the effective height is the distance between the tained in a formal testing setup but which are
top of the stack and the centerline of the open- seldom if ever duplicated in an actual installa-
ing in the stack where the gas enters. tion. It is thus practically impossible, or at least
very expensive, to determine comparable per-
SPECIFYING POWER-PLANT FANS - - formance of laboratory and field conditions.
Specifying the required operating condi- Furthermore, the connections made to a fan
tions for fans at various load points is generally may affect its performance to such an extent
COMBUSTION
Designing For Boiler Pedotmance

Base Line
-.2
0
3 -.l
x-
%8
51
5: 0
cc
85
C m
g +.I
12
8%
:6 +.2
a0
cz
5 - +.3
25

2 - ! I
40
+4 1 1 1 1 1 1 1 1 1 1 1 ! ~ : 1
200300400500 600 8 9 10 1 1 12 13 14 15 16 17 18 19 20 21 22
Avg. Gas Stack D~ameter,Feet
Temperature, OF

Fig. 32 Net draft (thermal static draft minus friction loss) versus gas velocity
and stack diameter at 80F ambient temperature and 29.92" Hg
that it would be unwise to select it without rea- with life, operation and maintenance of the
sonably large pressure and volume tolerances unit. Moisture in the fuel determines temper-
unless it were shop tested with inlet and outlet ing air which is high with dry coal and low
connections identical to those to be used under with wet coal. In assigning values for infiltra-
service conditions. In this connection it is al- tion and tempering note that too high an esti-
ways desirable to submit the layout of mate of airflow through fan and air preheater
ductwork connected to fans to the fan manufac- results in low predicted exit-gas temperature.
turer for evaluation and comments. Effect of Air Temperature
FORCED DRAFT FANS The temperature and elevation of the fan
The requirements of FD fans are calculated above sea level both affect the density of the air,
from the fuel fired and the excess air. For pres- which in turn affects the capacity of the fan.
surized firing, the calculation is quite accurate The moisture content of the air, especially for
as all air passes through the FD fans. For tropical conditions, also has to be taken into
balanced-draft units, the calculation is more account (see Fig. 1,Chapter 4).
complicated as the excess air measurement If air preheater protection such as a steam
does not usually correspond to the air through coil is provided ahead of the fan, the air tem-
the FD fans. Other sources of airflow into the perature leaving must be considered. If hot-air
unit are setting infiltration and tempering air. recirculation is used fsr air preheater protec-
Infiltrationand Tempering tion, then both temperature and extra volume
must be considered.
Determined by tightness of expansion joints,
observation and access doors and other pene- Pressure Specification
trations of the Eoiler, casing infiltration varies On balanced-draft units the required static
COMBusnON
Designing For Boiler Performance
-
head is the sum of all series resistances in the after, the dust collector. Sometimes it is an in-
secondary air system, including cold air duct, tegral part of, and built into, the stack base.
steam air heater, air preheater, air metering de- This fan therefore must handle the gas result-
vice, hot air duct, dampers and burner pressure ing from combustion of the fuel as well as all
drop. On pressure-fired units the additional infiltration occurring u p to the fan inlet, in-
loss from the furnace,to the stack outlet must cluding leakage in the air preheater.
also be included in determining total system Volume Specifications
resistance. Where stack effect is present, it The volume requirements of ID fans are fig-
must also be considered in determining total ured at the calculated density existing at the
head requirement of the fan. fan inlet. Based on the flue-gas temperature en-
Selection tering the fan, density should also be corrected
The volume and static pressure calculated for elevation above sea level and, of course, be
according to the foregoing give the actual re- based on the actual specific volume of the
quired fan capacity under predicted operating products of combustion at the excess air per-
conditions. The calculation assumes excess air, centage leaving the last piece of heat-transfer or
steady load, tight casing, normal fuel and com- emission-control equipment.
mercially clean surfaces as might be expected Flue-gas weight on which the volume is
during an acceptance test. These actual condi- based is calculated from the fuel requirements
tions are needed to evaluate power consump- and excess air. This gas weight should include
tion at the various loads, select the control moisture from fuel, from combustion of hydro-
equipment and provide a fan that will operate gen, and from the air or any other source.
at maximum efficiency at the desired normal The flyash carried in the flue gas from a
output of the steam-generating unit. pulverized-coal fired unit does not appreciably
These actual calculated operating condi- increase the total volume of the mixture han-
tions should not be used as maximum require- dled, even though it does increase density. The
ments in purchasing the fan. At times it may be presence of ash may increase the power re-
necessary and desirable to operate with more quirements of the drive for a given speed and
excess air, or the actual temperature at the fan capacity. But since ash will generally be less
may be higher than anticipated, or the fan may than five grainslcu ft, no allowance need be
not be up to expectations because of poor inlet made other than for fan excess factors recom-
and discharge conditions. Therefore, when mended in "Selection" subsection below.
specifying conditions for fan selection, liberal Pressure Specification
excess factors SUCK as the following are gener- The ID-fan must provide a static head equal
ally applied to both volume and pressure: to the series resistance from the furnace to stack
balanced-draft unit, 25 percent excess vol- outlet, including resistance of superheater, re-
ume, 50 percent excess static pressure heater, boiler bank, economizer, air preheater,
8 pressure-fired unit, 2 0 percent excess vol- dust collector and all ductwork. Besides resis-
ume, 25 percent excess static pressure tances, the net stack effect must be included to-
These values may, of course, be modified if gether with required furnace draft in arriving at
extreme conservatism was used in arriving at the total draft requirement of the ID fan.
the so-called actual requirements, or if they Selection
were calculated for an unusual peak load well The vo!ume and static pressure calculated in
above the desired continuous rating. accordance with the foregoing give the actual
INDUCED-DRAFT FAN required fan capacity under good operating
The induced-draft fan is usually positioned conditions, with assumed excess air, commer-
at the outlet of the terminal heat recovery ap- cially clean surfaces and normal leakage val-
paratus. It may be located either ahead of, or ues. As with the FD fan, such conditions are
COMBUSTION
Designing For Boiler Performance
I

needed for evaluating power, setting controls D, automatically closes when the fan stops.
and providing a fan that will operate at However, even the best shutoff damper has
maximum efficiency at desired normal output some leakage, so higher pressure air is tapped
of the boiler, but the actual calculated operat- off the main duct at point E. The shut-off damper
ing conditions should not be used as maximum F is ordinarily shut, but opens automatically
requirements in purchasing the fan. Operation with closing of the other shutoff damper. There
at higher excess air may be advisable; higher will then be a small flow of air i n both
amounts of gas recirculation may be used; directions from point G thus protecting all
leakage and infiltration may be higher than es- equipment that might be damaged.
timated: surfaces may be dirty, which will in- Volume Specifications
crease temperature as well as resistance; and
the fan may not perform to expectations be- The amount of recirculation needed to make
cause of poor inlet and. discharge connections. steam temperature at the control load deter-
Therefore, in specifications for ID fans, liberal mines the volume requirements of the GR fan.
excess factors are generally applied to both Specifying the flue-gas volume to be handled
volume and pressure, as follows: 20 percent ex- together with the gas temperature is a matter
cess volume and 30 percent excess static pres- for the superheater designer to determine.
sure. As with the FD fan, these figures may be However, it must be given at both the upper and
modified if extreme conservatism was used in lower end of the operating range of the gas-
arriving at the so-called actual requirements, or recirculation requirement.
if they ~cere~calculated
for an unusual peak load
Pressure Specifications
well above the desired maximum continuous
rate of operation. Gas-recirculation flow results in pressure
drops throughout the GR system, including
GAS RECIRCULATION FAN ducts, dampers and dust collector. Because the
For the same size unit and the same amount amount of gas recirculated adds to and is com-
of heat released by the fuel, oil firing requires mon with the main gas flow through the
much larger heating surfaces in the superheater superheater, reheater and economizer, it also
and reheater than for coal firing. Much of this increases the drops through these. It is these
relatively expensive surface can be eliminated latter resistances which generally dominate in
by increasing the gas mass flow through the establishing the total head requirements of the
convection passes, using gas recirculation. This recirculation fan.
is common on straight oil-fired units and is a At control load or some other partial boiler
good solution for combination coal and oil load, GR requirements are maximum. But be-
units. The gas recirculating duct system is cause the main gas flow is low, the total head
shown in Fig. 3 3 . Gas is tapped off the main gas requirements of the recirculation fan are
duct at point A, passes through the gas recircu- moderate. At full boiler load, little or no gas re-
lating fan and enters the bottom of the furnace circulation may be required. However, since
at B. Damper C controls the flow and is part of the main gas flow through the boiler is high, the
the steam temperature control system. pressure differential across the superheater,
The gas recirculation fan is necessary to reheater and economizer is high and the recir-
overcome the pressure differential between the culation fan must produce a high static head to
furnace and the economizer outlet. If for any balance this differential. In selecting the fan,
reason the fan is shut down while the boiler is the relationship of fan heqd to the differential is
in operation, high temperature furnace gas a critical factor to consider.
would flow backward through the fan and If at any point over its operating range the fan
ducts, which are not designed to withstand could not develop enough head to overcome
such temperatures. Therefore shutoff damper the differential developed by the boiler,
COLII)OSTION
DesigningFor BoNer Performance

Fig. 33 Typical gas-recirculatingsystem

tackflow of furnace gas will result through the headers, and tubing withstand all the pressure
fan with very serious consequences. stresses under hostile conditions of high temp-
To protect against this condition, it is usual erature and, frequently, corrosive atmospheres,
to specify as a minimum point on the fan but they must also retain their positions, con-
characteristic a pressure at least 2 in. wg. above tour. and roundness under a variety of exter-
the maximum superheater-reheater-economi- nally imposed loads. Extremely sophisticated
zer differential at full load on the boiler. Nor- analyses Of the stresses be made
mally, control-load requirements dictate fan of both the pressure-retaining parts and their
size. The following are usual excess per- hanger U-boltsl lugs. and
centages applied to the calculated require- members.
ments at this load: 1 5 to 20 percent volume ex- This section describes the important aspect
cess, with the static pressure boost adjusted to of the boiler design engineer's work that can be
accommodate the increased volume. called "designing for structural performance."

- MATERIALS SELECTION FOR


SUPERHEATERS AND REHEATERS
STRESS ANALYSIS
AND STRUCTURAL DESIGN From the view point of thermodynamics,
OF STEAM GENERATOR the power-plant cycle efficiency is related to
primary and reheat steam temperatures. A
COMPONENTS - - - steam temperature increase improves the cycle
Ina steam generator design, the structural in- efficiency, everything else being the same.
tegrity of the pressure parts and their supports However, superheater and reheater outlet con-
is of major concern. Not only must the drums, ditions are limited by the ability of materials to . I
COMBUSTION
Designing For Boiler Performance

withstand physical stress and by economic


breakeven points.
In the high-temperature region of boilers, al-
lowable stress goes down as materials are ex-
posed to high flue-gas temperatures necessary (2) Total heat absorption rate per unit area,
to superheat and reheat steam to high tempera- q
tures. At the same time, more costly grades of -is calculated from
A0
alloy steel are required to withstand the physi-
cal stress imposed by elevated temperatures
and pressures.
As an example of temperature increase effect,
the allowable stress for a material known as
SA-213 T-11 drops from 11,000 psi at 950F to
6600 psi at 1000F. Up to 850F it is usually By knowing Rt, t, and T, the localized heat
possible to specify carbon steel, but beyond absorption rate per unit area can be obtained.
this point more costly alloys are required. If the superheater or reheater tube in ques-
In view of these facts, selection of materials is tion is subject to direct furnace radiation, this
a most important consideration in superheater should be taken into consideration in Eq. 42.
and reheater design. Proper material selection Fig. 34 is a polar plot of a reheater tube facing
requires knowledge not only of metal tempera- the furnace, showing the higher metal tempera-
ture conditions but also of the economics of ture rise on the front face of the tube compared
manufacture and fabrication of various steel to the back or downstream side.
alloys. These aspects are amplified in Chapters (3) Steam side film conductance of heat
1 7 and 18 on materials and metallurgy, and transfer h,:
steam-generator manufacture. A systematic pro- After the heat absorption per unit is de-
cedure to calculate the metal temperatures of termined, the next step is to establish steam-
superheater and reheater tubing is explained in side film conductance of heat transfer, h,. By
the following subsection. dimensional analysis and experimental work, a
general relationship is developed to calculate
SUPERHEATER AND REHEATER METAL the film conductance for forcid convection in
TEMPERATURES fluids. This may be evaluated from the equation
(Nu) = a(Rejb(PrjC,where a = 0.023, b = 0.8,
Before to make tempera- c = 0.4 and the terms are respectively Nusselt,
ture calculations, the- designer assumes the Reynolds and Prandtl numbers. The correla-
following data to be known for the point in tion may then be expressed as follows.
question:
gas temperature, T,
steam temperature at the point in question, t,
- G,
mass velocity- of gas,
mass velocity of steam, G, - (43)
tubing size and estimated thickness
m tubing material where D is an expression of applicable diame-
steam pressure ter, k is the thermal conductivity of the fluid, G
heat absorbed, q, Btulhr. is the mass velocity, p i s the absolute viscosity
of the fluid and c, is the specific heat at con-
(I) Total heat-transfer rate, Rt (as defined in stant pressure. The values of a, b and c are de-
previous section on boiler calculations): termined experimentally and should be used
COMBUSRON
Designing For Boiler Performance

Gas
Flow

Gas Flow -

butside Metal Temperature

Fig. 34. Metal temperature distribution in a reheater tube


with discretion, taking into consideration re- where k is the thermal conductivity of the tube
sults available in heat-transfer literature. for which the temperature is being calculated.
(4) Steam-side film temperature drop, At,: The tube metal temperature at any given
By knowing the heat absorption rate per unit point in the tubing will be the sum of the steam
area and steam-side film conductance of temperature, the film temperature drop and the
heat transfer, the steam-side film temperature tube wall temperature drop.
drop can be obtained from the foilowing METALTEMPERATURETOLERANCES
relationship.
The preceding represents an ideal case based
A~ =L1% on the assumptions that the steam flow rate and
A. h, Di temperature and gas flow rate and t'emperature
(44) are uniform for all the elements. These condi-
tions actually are never experienced in the per-
where Dois the outside diameter of tube and Di
formance of the steam generator. It is necessary
is the inside diameter of tube. The D,IDi term
appears in the above formula because qlA, was therefore to provide so called "imbalances" or
based on outside diameter of tube. tolerances that are anticipated. These include
(5) Tube wall temperature drop, AT: the following:
Temperature drop through a tube can be cal- Desuperheaterallowancewhich is the number
culated from the conduction equation: of degrees that the steam temperature will rise
at the particular point upstream of the super-
heater when the full use of the desuperheater is .
made. Usually the design is such that little or
no desuperheating is required. However, when
a desuperheater is installed all pressure parts
COMBUSTION
Designing For Boiler Pcrhmance

ahead of the desuperheater are designed to in- selection of materials in previous paragraphs is
clude the desuperheater allowance. the steam or water pressure drop that occurs in
Steam temperature imbalance which allows operation. Just as there is a semi-proportional
for the increase in expected steam temperature relationship between transfer rate and draft
at a given point caused by the unbalanced dis- loss, as previously explained, there is a similar
tribution in steam flows, gas flows and gas connection between pressure drop and metal
temperatures. temperature. That is, the fluid film thickness
Film and metal drop imbalance which is the inside a heated tube is affected by the mass flow
increase in the film and metal temperature drop of fluid through the,tube. And pressure drop is
caused by the imbalance distribution in the gas roughly a square function of the mass flow.
flows and gas temperatures. In evaluating whether a given pressure drop
The maximum metal temperature at any is too high through any proposed circuitry, the
given point in the tubing will be the sum of the principal concerns most often are (a) the design
steam temperature, the film and metal tempera- pressure of upstream pressure parts, and (b) the
ture drops, the desuperheater allowance - if power penalty for any increment of pressure
any, the steam temperature unbalance and the drop versus the cost of using more expensive
film and metal drop imbalance. alloys in superheater or reheater tubing to re-
After the metal temperature is established, duce wall thickness and, thereby, the pressure
the selection of material is made in accordance drop. An example of the first situation is the in-
with the ,ASME Boiler and Pressure Vessel fluence on boiler drum and waterwall tubes
Code. Section I of the Code covering power boil- and headers of the superheater pressure drop:
ers gives details for calculating tube wall thick- the superheater drop is added to the required
ness and the allowable stress values for the superheater-outlet pressure to arrive at the
various materials. In superheater and reheater operating pressure in the drum, the furnace
design it has been found desirable to limit wails, the risers, and the downtakes. With tol-
the use of various materials according to the erances specified by the ASME Code, the actual
oxidation-resistance limits in Table IV, which design or working pressure of the steam
are in all cases lower than the maximum permis- generator is established. The higher the super-
sable metal temperatures established by the heater pressure drop, the higher the ASME de-
ASME Boiler and Pressure Vessel Code. sign pressure for the entire unit, which has a
direct effect on the thickness and cost of the
PRESSURE-DROPCALCULATIONS pressure parts. .
Another aspect of the design of superheaters, Basic Pressure-Drop Equations
reheaters, and economizers that relates to the The following equations are used for water

Table IV. Maximum Outside-Surface Metal Temperatures


- - -- --

ASME Code Oxidation


Alloy Specification Nominal Composition Limit, O F

SA-213 Carbon Steel


SA-213 T-1 Carbon- 1/2 Mo
SA-213 T-11 l%Cr- %Mo
SA-213 T-22 2 % Cr- 1 % M o
SA-213 T-9 9 C r - 1 Mo
SA-213 Type 304H 18Cr- 8 N i
SA-213 Type 347H
COMBUSTSON
Designing For Boiler Performance
..,
and steam pressure-drop calculations on sub- return bend is one with a bend radius less than
critical-pressure boilers, and are similar to the tube outside diameter (OD). A 90" short-
those for supercritical units. radius elbow is defined as having a bend radius
Water flowing through pipes and tubing: less than 3 times the pipe OD. Anything greater
is considered a long-radius elbow.
MECHANICAL STRESSES
- - -
IN DRUMS, HEADERS AND PIPING
where Industrial safety codes, such as the ASME
F = flow per path, 1000 lblhr Code, provide the designer with acceptable
L = length of tube plus equivalent length of formulas for sizing various components of a
bends, ft pressure vessel. Typical formulas making use
D = inside diameter in inches of equations from the basic theory of elasticity
for specific shells of revolution presented here
Steam flowing through tubing, up to 6" O.D.:
are taken from Section I, Rules for Construction
of Power Boilers, of the ASME Code.52
SPHERICAL SHELL
The minimum thickness, t, of a spherical
Steam flow through pipes: shell of inside radius, R, for a design maximum
allowable working pressure, P, and a maximum
allowable working stress, STall in consistent
units, is
where
F = flow per path, lblmin
V = specific volume, cu ft/lb
and L and D are as defined above. on an elastic shell basis.
For determining the total equivalent length Eq. 49 gives the correct thickness for thin-
of a circuit, the following factors are used, walled shells, but when the thickness of the
where the equivalent length is equal to the fac- shell is greater than about 0.36 R, the elastic
tor multiplied by the inside diameter (ID) of the theory requires that thickness be calculated on a
tubing. Thus, a 180" bend i n a tube with 2 in. ID thick-walled basis. The formula for thickness is
has an equivalent length (for use in Eq. 46,47,
48) of 30 X 2 = 60 in. = 5 ft.
Equivalent Lengths
MULTIPLYING FACTOR
ON ID
Entrance loss 30 CYLINDRICAL SHELL
Exit loss 30
The minimum thickness for a thin-wall
Squeezed return bend 50
cylindrical shell for piping, drums, and head-
180' bend 30
ers in the steam generator is
90"bend 25
4S0bend 15
90"short radius elbow 21
90"long radius elbow 12

Entrance and exit losses are applied to the junc- where C is an additional allowance for thread-
tions between tubes and headers. A squeezed ing and structural stability and y is a tempera-
cowusno N
Designing For Boiler Performance

ture coefficient, as in Table V. The strength of those ligaments between tube


For thick-wall cylinders, in which the thick- holes that are subjected to alongitudinal stress
ness is greater than one-half the inside radius, shall be at least one-half the required strength
the elastic theory requires that the shell wall of the4igarnents coming between the tube holes
thickness be determined from which are subjected to a circumferential stress.
When tubes or holes are arranged in a drum or
shell in symmetrical groups along lines paral-
lel to the axis and the same spacing is used for
each group, no group efficiency shall be less
than that on which the maximum allowable
In this equation, E is the efficiency, expressed working pressure is based.
as a decimal, and called the ligament effi-
ciency. It is based on the pitch. diametral size, HEMISPHERICAL HEAD
and configuration of the holes in a drum or The formulas for a hemispherical head are
header. For openings that form a definite.pat- identical to those for a spherical shell. Either
tern in pressure parts, the efficiency of liga- industrial-code rules or the theory of elasticity
ment between the tube holes is determined per give the required thicknesses for these shells.53
paragraph PG-52 of Section I of the Code. If a pressure vessel consists of a cylindrical
When the pitch of the tubes on every tube row shell capped with a hemispherical head, the
is equal, as in Fig. 35, the formula is
--

~I-herep is the longitudinal pitch of adjacent


openings and d is the diameter of the openings.
in consistent dimensions, and E is the effi-
ciency of ligament, as a decimal. For a pitch of
Longitudinal Line -
(A) Pitch of Holes Equal in Every Row
3l/1 in. and tube-hole diameter of 39/32 in., effi-
ciency is (5.25 - 3.28)/5.25 = 0.375.
When the pitch of the tube holes on any one
row is unequal, the formula is
- -- - ---

Longitudinal 'Line -
(8)Pitch of Holes Unequal in Every Second Row

where p , is the pitch between corresponding


openings in a series of symmetrical groups of
openings and n is the number of openings in
length p ,. The pitch in these equations is mea-
sured either on the flat plate before rolling or on
the median surface after rolling.
Longitudinal Line
(C) Pitch of Holes
-
Varying in Every Second and Third Row
For the spacing shown in Fig. 35 B, the effi-
ciency is (12 - 2 x 3.281) :12 = 0.453. For the
spacing in Fig. 35 C, ligament efficiency is
cFig. 35 Examples of tube spacings in
i19.23 - 5 x 3.281)/29.25 = 0.439. drums or headers
COMBUSTION
Designing For Boiler Performance

FLAT HEAD
Table V. Temperature Coefficient y A flat head can be considered as a circular
used in Design Calculations plate which is uniformly loaded by pressure.
UP 901'
The amount of end fixity depends on the
Design to to Above method of mounting and the stiffness of the
Temperature 900F 950F 950F cylindrical shell to which the flat head is at-
y factor tached. If the plate is assumed to be simply
for ferritic 0.40 0.50 0.70 supported, then no moments are transferred to
steels the shell, and the maximum plate stress occurs
at the center of the plate. The stress is:
From Section 1,ASME Boiler Code. Between temperatures listed, de-
termine y by interpolation.
-

component sizes can be determined by codes or


by the theory of elasticity usicg the simple
membrane formulas. The degree of end fixity is determined by
SEMIELLIPSOIDAL HEAD applied edge moments,
The standard semiellipsoidal head recog- M, = C,P R2
nized by the ASME Code has half the minor
axis, or the depth of the head, at least equal to and superposed stresses,
one-quarter the inside diameter of the head. By
elastic theory this head requires a thickness of
By substituting allowable stresses in these equ-
ations, the required thickness of the plate can
be expressed as:
The R in the above equation is either the 'I:!
length of the major axis, or the radius of the
j
mating cylinder. (58)

TORISPHERICAL HEAD where d is the inside diameter of the header at


the flat end plate, and Cpisa factor that depends
A torispherical head is a shell which com- on the method of attachment of the head and
bines part of a torus with a spherical cap. In the other items in Code paragraph PG-31.4.
ASME Code the knuckle, or torus, radius is re- Eq. 58 gives the thickness of a flat head as re-
quired to be 3 times the head thickness, but not quired by the ASME Code. The constant Cpin
less than 0.06 times the diameter of the shell, the equation is a factor depending on the
and the crown radius may not exceed the out- method of attachment of the head, and on the
side diameter of the head flange. There are no shell, pipe or header dimensions. It must be
directly applicable formulas based on elastic found from appropriate tables in the Code, and
theory but any given head shape can readily be these tables usually specify the end fixity of the
calculated from basic equations. The ASME flat plate. In the industrial code, the constant is
Code specifies the thickness to be usually greater than that required by elastic
theory, thereby adding another factor of safety
to the code design.
DISCONTINUITY STRESSES

where L is the radius to which the head is When a pressure vessel is subjected to inter-
dished, measured on the concave side. nal pressure, redundant forces and moments
COMBUSTION
Dsigning For Boiler Performance

are induced in areas of structural discontinuity


such as the intersection of a cylindrical shell
and a hemispherical head. This can best be vi-
sualized, Fig. 36, by assuming that the shell
and head act as separate units with internal
pressure applied to the individual, simply
supported parts. Because the deflections of the
components differ, shear forces and moments
must be applied at the edges to rejoin the
components for a compatible structure. The re-
sulting stresses (usually bending stresses) in-
duced by these shear forces and moments are
called discontinuity 'stresses. The bending
Fig. 36. Discontinuity forces at a head-cylinder
stresses reach a maximum at, or near, the dis- junction under internal pressure
continuity, but they attenuate with distance
from the joint.54 A commonly accepted ap- fect would be localLed at the edge of the hole
proach to the derivation of these discontinuity and could cause some plastic deformation with
stresses is the theory of beams on an elastic an inherent redistribution of stresses.
foundation.53.55 The ASME Code requires that, for holes
If a pressure vessel with a hemispherical larger than a certain diameter, reinforcement to
head is designed for minimum thickness of the the opening should be added by the nozzle at-
mating components, then the maximum stress tachment, increased shell thickness, or the pad
in the pressure vessel will be 27 percent higher for a cover plate if the opening is to be used for
than the circumferential stress in the cylindri- future servicing operations.
cal shell away from all discontinuities. On the The Code's rules specify that the area re-
other hand, for a vessel of uniform thickness, moved for the penetration in a given cross sec-
the maximum stress is only 3 percent higher tion be reinforced within specified boundaries.
than in the same size cylindrical shell. At best this is a crude method; however, ex-
A pressure vessel with a standard semiellip- perience has shown that the stresses do not
soidal head of the same thickness as a mating cause failure at nozzles if the level of stress in
cylindrical shell exhibits a maximum stress 13 the shell is at a reasonable limit.57 The best type
percent higher than the circumferential mem- of reinforcement is one in which the reinforce-
brane stress in the cylinder.56 Unfortunately, ment is equally distributed on each side of the
membrane stresses and discontinuity stresses shell, that is, equal amounts of reinforcement
are very sensitive to changes in curvature. extend inside and outside the she11.58 This
REINFORCED OPENINGS method of reinforcement is not always practi-
cal; most commonly, then, it is necessary that
For very small unreinforced circular holes, all the reinforcement must be on the outside of
the theory of elasticity shows that a stress con- the shell.
centration factor of three will exist around the
hole under a n uniaxial tension. The stress con- STRESS ANALYSIS
AND STRUCTURAL DESIGN
centration is reduced to two for the state of OF FURNACE WALLS
biaxial tension. In a cylindrical shell under
pressure, the state of stress is such that the cir- Welded furnace walls are one of the most
cumferential stress is twice the longitudinal important components of boilers. They may be
stress. Under this condition the stress concen- incorporated into the design of small shop-
tration at an unreinforced penetration would assembled boilers as well as in the largest
reach a peak of 2.5. The stress concentration ef- utility-type units. Furnace walls, also fre-
--
CObfnuSnON
Designing For Boler Performance

quently referred to as waterwalls, provide the for proper thermal performance of the fiknace.
enclosure around the major parts of a boiler and Since the tubes are a part of the pressure system
are integrally concerned with all of its essential of the steam generator, the determination of
functions. As a link in the steam generating cy- wall thickness is within the jurisdiction of Sec-
cle, they are components of the pressure parts tion I of the ASME Code.52 Thus the equation
system. The support of the furnace-wall system used for tube thickness is
is linked to that of other components and will
be discussed in the final section of this chapter
dealing with structural design of boilers.
Welded furnace walls must be safe and reli- (59)
able over a range of operating conditions. The
furnace-wall tubes have the highest heat-flux where t is thickness, P is fluid pressure, D is
rates in the boiler and are subjected to the outside tube diameter and S is the allowable
most extreme fluctuations in temperature and stress according to Table PG 23.1 of Section I,
pressure. During boiler startup the walls ex- ASME Boiler and Pressure Vessel Code.
perience considerable overfiring and variable Following this procedure satisfies the ASME
pressure conditions are encountered as the unit Code requirements for minimum tube wall
is brought u p to its normal operating level. The thickness and gives a wall panel with the re-
furnace-wall enclosure must be designed to quired flexibility to keep the thermal stresses
withstand both positive and negative inside within reasonable limits on severe thermal
pressures. In addition, special conditions transients. Except under special conditions, a
sometimes occur in which the enclosure must thicker wall tube does not improve the overall
withstand wind and earthquake loadings. stress condition. As the pressure stress be-
The crucial feature i n the protection of a comes smaller because of thicker tube, the
furnace-wall tube against failure is the assur- therzal stress increases rather rapidly with
ance of adequate circulation of fluid within the greater wall thickness. A change to a better ma-
tube under all operating conditions. For this terial is the most satisfactory method of gaining
reason, the thermodynamic requirement for the improvement in strength requirements.
particular type of furnace determines the Other mechanical loads also act on the fur-
internal diameter of the wall tube. For some nace wall and must be analyzed to assure its
furnaces the wall will contain small-diameter reliability. Some of these additional loads are
tubing with thick walls while for other fur- furnace firing pressure, dead-weight loads,
naces the tubing will be large diameter and wind loads, earthquake loads and reactive loads
relatively thin walls. Thus, mechanical be- that exist between the furnace wall and the
havior of furnace walls will vary greatly for rigid buckstay system.
different types of furnaces. DETERMINATION
OF FURNACE STRESSES
MECHANICAL LOADING OF FURNACE WALLS
The straight analytical determination of
Analytical and experimental techniques stresses in the furnace walls is difficult because
make it possible to determine the stresses in the of the complex geometry of the panel. To begin
furnace wall in considerable detail. With this the calculation, it is necessary to assume a fin
knowledge and the realization that different size. For a furnace panel with normal heat-
stresses have different degrees of significance, absorption rates, the fin width will be about
the furnace walls are designed to give the de- one half inch. With this close tube spacing, the
sired thermal behavior, at the same time being wall can be considered a stiffened orthogonal- . -
safe and reliable.59 plate. Using the notation of Timoshenko,53 the
As a starting point, the tube thickness is de- differential equation of equilibrium for small
termined to give the required internal diameter displacements of an orthotropic plate is
COMBUSTION
Designing For Boiler Performance

where W is the lateral displacement,

E"h3 Gh3
Dl = 7'. D,, = 12'

q is uniform lateral load, E is the modulus of


elasticity and h i s wall thickness. Fig. 37 Orthotropic plate subjected to
The numerical computer techniques of finite in-plane and lateral loads
elements are used to solve Eq. 60. The tube and flux, inside film coefficient and the type of
fin geometry of the furnace wall is transformed boiler. Fig. 38 gives an example for a Controlled
into an equivalent orthotropic plate by the use Circulation@boiler of the performance of the
of equivalent load functions as developed by four critical temperatures: at the outside, mean
C-E engineers. The mechanical loads such as and inside diameter on the crown of the tube,
furnace pressure, dead weight, buckstay load- and at the fin tip, as a function of inside film
ing, wind and earthquake and the thermal coefficient. The curves illustrate the impor-
loads from temperature distributions are ap- tance of maintaining a minimum inside film
plied to an orthotropic finite element plate coefficient to keep the tube cool. Using the rela-
model of the furnace walls. The transformed tionship between heat flux and nucleate boiling
equivalent orthotropic plate elements are used coefficient shown in Fig. 39, the actual maxi-
to model the furnace wall and beam elements mum temperatures in the tube and fin above the
are used for the buckstay system. The finite saturation temperature are plotted against flux
element mathematical model of the furnace is rate in Fig. 40. This relationship is essentially
solved using one of the finite element computer proportional and demonstrates the range of ab-
programs such as "MARC-CE Nonlinear Finite sorption to which tubing and fin material may
Element Program" or the "STRUDL Finite be exposed.
Element Program". The computer program Temperature Distribution
findings are resultant forces and moments act-
The first step in determining the thermal
ing on the various equivalent orthotropic plate
stress in the fin and tube is to obtain a tempera-
elements of the furnace-wall mode (Fig. 37).
ture distribution, T. The tube and fin respond
BALANCED THERMAL LOADING
with sufficient speed so that, at any given con-
dition, this relationship can be approximated
Balanced thermal loading is a condition by the steady state.
which results in a local variation in tempera-
ture that produces thermal stresses in tubes and Thus , V2T = 0
fins; this condition occurs because of balanced 87'' aT2
heat absorption from one side of the wall. The where V2T = +7
av-
local metal temperatures existing in a tube and
fin depend on the panel geometry, the heat
COMBUSnON
Designing Fbr Boiler Performance

I 1
Fig. 38 Furnace-wall tube temperature plot

Numerical computer techniques are used to purpose computer program which will provide
solve this differential equation. The CEWIND a transient heat transfer analysis with non-
computer program for calculating temperature axisymmetric loading on a symmetric tube and
distributions is based on the finite difference fin cross section. This program has the capabil-
method and provides directly the surface tem- ity of making plastic and creep strain calcula-
perature and the internal temperature distribu- tions if they are required.
tions. Fig. 41 shows some thermal isotherms
Thermal Stresses I
generated by this program. Often a special I
computer tape will be made of the thermal re- Thermal stresses occur in the tube and fin be- I
sults so that temperatures may be directly input cause the elements cannot deform freely. Some I
to computer thermal stress programs. of the thermal stress results from differences
The MARC-HEAT Computer Program will between the mean temperature of the section
solve the same equation with a finite element and the local temperature. The remaining ther-
type of analysis and has the advantage that the mal stress is imposed on the tube and fin by the
same finite element model may be used for comparatively stiff buckstay systeq.
I
both the thermal and stress analysis programs. A finite element model is made of the tube
However, stresses or strains require an extrapo- and fin geometry as shown in Fig. 42. If the
lation procedure. temperature distributions of the tube and fin
The CE-NOAXCYL Nonlinear Axisymmetric (Fig. 41) are input into one of the finite element
Finite Element Analysis Program is a special computer programs such as "MARC-CE Non-

Nucleate Boiling (2850 PSIG) Allowable Design Temp.

5%0 20 40 60

I r=
Heat Flux, a(103 Btu/Ft2-Hr) 0' 20 40 60 80
Heat lux-a(103 Btu_/Ft2
- . Hr)
100
-

Fig. 39 Correlation between heat flux Fig. 40 Temperatures above saturation


and nucleate boiling versus heat flux
COMBUSTION
Designing For Boller Performance

):t)x2
-
571b 5O{b
40
& L
- -3-

65
260 -50
-50 -40
1
416 39

0.1
0.2 0.1
50 50 50 Q(103Btu/Ft2-Hr)
25 5 10 h(103Btu/Ft2-Hr-OF)
25 19 16 AT Sect~on.Mean (O F)

Fig. 47 Temperature distribution in finned furnace-wall tubes


linear Finite Element Program" or "STRUDL" given tube. Further investigation reveals a very
with proper boundary conditions, the com- complex interplay between heat absorption
puter will calculate thermal stresses and and flow rates for some types of furnaces with
strains in the tube and fin geometry. conditions that can lead to large temperature
The forces and moments from the computer
solution of the orthotropic furnace walls (Fig.
37) are applied to the tube and fin geometry as
shown in Fig. 4 3 . These forces and moments
when used with the finite element model
shown in Fig. 42 will generate additional local
stresses in the tube and fin geometry. The same
finite element model is used to calculate the
stresses and strains from the internal pressure
applied to the tube. Combining and evaluating
these stresses is covered later in this chapter.
UNBALANCED THERMAL LOADING
Unbalanced thermal loading is defined as
temperature distribution which varies in either
direction along the furnace wall. The variation
in heat-absorption rates longitudinally and
transversely across the wall is one reason for
unbalanced temperaure distribution. Fig. 4 0
shows how the metal temperatures vary with
different heat absorption rates. Unbalances in
the flow rate either in neighboring tubes or in
different areas of the wall will give unbalanced
temperatures. Flow rates in some boilers are
very dependent on the heat absorption for a Fig. 42 Finite element model of tube and fin
COMBUSTION -
Designing For Boiler Performance

to the furnace model and the resultant forces


and moments determined with finite element
analysis. Local effects of the resultant forces
and moments on the tube and fin geometry are
obtained by using the tube and fin finite-
element model shown in Fig. 42.
SIGNIFICANCEOF CALCULATED STRESSES
The accurate and detailed determination of
the mechanical and thermal stresses in the fur-
nace wall is of little value until the designer
knows how these stresses affect wall failure. A
measured value of stress or strain has little
meaning until it is associated with location and
distribution in the panel and with the type of
loading which produced it. For example, the
Fig. 43 Geometrical configuration of tube and fin average hoop stress in the tube from internal
pressure has a different influence on the life of
unbalances. Fig. 41 shows temperature distri- the panel than that of the peak stress at the in-
butions for three different inside-film coeffi- tersection of the fin and tube from a redundant
cients, which are strongly dependent upon moment. An excessive hoop stress produces an
flow rates. A third condition that will result in instability in the tube, which continues to ex-
temperature variations in a furnace wall is that pand and get thinner and thinner until rupture.
of varying fluid temperatures. In boilers of the On the other hand, the peak stress at the notch
once-through type, the fluid temperature con- will relieve itself by yielding and has a bearing
tinually varies as the fluid progresses from only on fatigue life or stress-rupture life.
inlet to outlet. In each case there is a very com- To help evaluate the different types of
plex interaction between these conditions, and stresses that may act on the wall, the various
it is the responsibility of the boiler designer to stresses are classified as primary, 'secondary,
select a suitable set of parameters so that the and local or peak stresses.
temperature unbalances will be within reason- Primary Stress
able limits. A primary stress is a normal or shear stress
An experimental technique has been used to developed by the imposed mechanical loading
determine the stresses from the unbalanced which is necessary to satisfy the laws of equi-
thermal loadings. As an example, Fig. 44 shows librium of external and internal -forces and
a furnace wall panel under test at C-E's moments. The basic characteristic of a primary
Kreisinger Development Laboratory. In this stress is that it is not self-limiting. Primary
test controlled temperature distributions were stresses which exceed the yield strength will
imposed on the panel. To identify the influence result in failure or gross distortion.
of each type of discontinuity, electric strain Secondary Stress
gages placed on the outside surface of the A secondary stress is a normal or shear stress
panel, at its end, at its center, at the top bend, developed by the constraint of an adjacent part
and at the soot blower opening determined the or by self-constraint of a structure. The basic
resulting strains.@ characteristic of a secondary stress is that it is
This experimental data has been used to self-limiting. Local yielding and minor distor-
evaluate the procedures for the equivalent or- tion can satisfy the conditions which cause the
thotropic plate modeling of the furnace walls. stress. Thermal stresses which produce gross
Unbalanced thermal distributions are applied distortions are secondary stresses.
COMBUSTION
Designing For Boiler Performance

Local or Peak Stress subjected to multiaxial stress, and a direct


- Local or peak stress is a normal or shear stress comparison of the stress in the wall with the
which is the highest in the region under con- characteristic strength value of the material is
sideration and is developed by changes in not directly admissible. Only with the aid of a
geometry such as a notch. Thermal stresses strength hypothesis is it possible to calculate
which are caused by self-constraint are treated an equivalent stress for comparison with the
as local stresses. The basic characteristic of a characteristic strength value as determined by
local or peak stress is that it causes no signifi- the conventional tension test.
cant distortion and is objectionable only as Maximum Shear Theory
a possible source of either a fatigue failure, The maximum shear stress theory is used as
brittle fracture, stress-corrosion cracking or the failure criterion for the furnace walls. The
stress-rupture failure. These categories also selection of the maximum shear stress theory is
differentiate between a membrane stress (aver- based on the use of a good ductile steel for the
age value across a section) and a bending stress furnace walls. According to the maximum
(linearly variable across a section). shear theory, if the principal stresses are cr,, cr,,
cr3 and further if a,> u2> u3,the maximum
COMBINATION OF STRESSES
shear stress is
The characteristic material values on which
strength calculations are based are determined
under uniaxial tension. Usually this is the
common tension test. The furnace walls are

The equivalent stress to that of a simple ten-


sion or compression test would be

Called stress intensity, the equivalent stress


is not a single stress quantity. Rather, it repre-
sents the combined stress of the three principal
stresses or their equivalent. The addition of
stresses from different categories must be per-
formed at the component level, not after
translating the stress components into stress
intensities. Similarly the calculation of mem-
brane stress intensity involves the averaging of
stresses across a section and this averaging
must be performed at the component level.
The allowable stresses (except for the mem-
brane stress) have been derived from the same
considerations that were used in writing Div 2
of Section VIII of the ASME Boiler and Pressure
Vessel Code. It is an application of limit design
theory tempered by engineering judgment and
some conservative simplifications.
Allowable Membrane Stress
The first stress limit to consider is primary
Fig. 44 Furnace-wall test apparatus at membrane stress. In this case the value is lim-
C-E Kreisinger Development Laboratory ited to the values as given in Table PG 23.1 of
. --

6-
COmmON
Designing FoiBoNer Performance

the Section I Rules for Construction of Power the values from Table PG 23.1 for temperalures
Boilers of theASME Boiler and Pressure Vessel below 700F.
Code, since the tubing is part of the pressure If the temperature is greater than 700F, the
system in the boiler. influence of creep strains must be considered.
Stress intensities are not determined because Control of the secondary stresses is to limit de-
this section of the ASME Code is based on formations and to provide a valid basis for
maximum stress theory. the elastic procedure for the fatigue analysis.
Allowable Local Membrane or Bending Stress When creep alters the stress distribution and
increases the strain range, a high-temperature
In the remaining evaluation, the stress inten- design procedure is required. For the low-alloy
sities are determined for comparison with the ferric materials the temperature range may in-
stress limits. The next limit is the sum of the crease to 850F without serious creep strain.
primary membrane stress plus the primary Allowable Peak Stress
bending stress plus any local membrane stress.
These stresses are combined at the component For the next evaluation all the stresses - pri-
level and then the stress intensity determined. mary, secondary and local - are combined for
This limit is set at 1.5 times the stress limits as both the maximum and minimum conditions of
given in Table PG 23.1 of Section I of ASME an operational cycle. From these values the
Code. In addition, if the temperatures are at the maximum and minimum stress intensities can
level where stress rupture is the mode of fail- be determined. Using these stress intensities
ure, the combined value is limited to those val- the alternating stress is calculated. These
ues given in the Table. stresses are usually evaluated on a fatigue basis
which will be discussed in the next section.
Allowable Secondary Stress Where loads are at steady state or of very low
In the next consideration, the primary cycle frequency and the temperatures are in the
stresses (membrane and bending) are com- realm of stress rupture, the total stresses can be
bined with the secondary stresses at the com- limited by yield stresses. In this region each
ponent level and the stress intensities deter- material has a different behavior as influenced
mined. These values are limited to three times by notches and metallurgical changes. There-

Fig. 45 Stress limits


COMBUSTION
Designing For Boiler Performance

fore, a survey of the literature on the material furnace design can be found in Section I11 of the
should be made as an aid in the final evalua- ASME Boiler and Pressure Vessel Code. These
tion. Fig. 45 summarizes the stress limits for are believed to reflect a conservative design.
the various stress categories. In the furnace wall the stresses on both sides
FATIGUEANALYSIS of the wall must be determined: The trend of
The first step i n the fatigue analysis is to es- the decrease in fatigue life as the temperature
timate a stress history for the expected life of increases is shown in Fig. 47. Thus, because of
the unit. From this stress history, the different the temperature influence on fatigue life, the
operating cycles, such as startups, shutdowns, hot face of the tube or fin may fail although the
load changes and other changes which cause higher stresses may be calculated elsewhere.
the stress level in the wall to vary, can be de- CUMULATIVE DAMAGE
termined. In each of these cases, the maximum
and minimum stress. intensities are deter- The furnace wall is subjected to a wide vari-
mined. Alternating stress intensities can then ety of operating conditions, some of which
be calculated by produce no significant stresses and some of
which will produce stresses worthy of con-
sideration. When a design is for either static
loads or for a large number of cycles, it is suffi-
cient to design for the condition which pro-
If these stresses are significant, they will use duces the highest stresses and to ignore all oth-
up part of the life of the unit. The number of ers. In this case, design is for infinite life, and
times the significant alternating stresses can be all stress must be below the damaging level.
repeated is determined from a design fatigue Usually the number of operational stress cy-
curve as shown in Fig. 46. In these curves the cles which the furnace wall must withstand is
alternating stress is plotted as a function of the not large, but the value of the operational stress
cycles to failure with suitable safety factors. is large unless severe restrictions are imposed.
Because safety factors vary considerably and As soon as the existence of strains beyond the
are dependent upon the mechanical behavior elastic limit is accepted, the design is based on
of the material, the uncertainty of the assumed finite life and the damaging effect of all signifi-
loads and the uncertainty in the material (scat- cant strains must be considered. The relation-
ter of data), specific values of the ordinate of ship between the alternating stress and cycles
typical curves are not given. Curves such as to failure can be determined from the design
these are determined by experimental methods fatigue curves, and the number of required cy-
and may be found in the literature. Some fa- cles can be estimated from the anticipated
tigue curves for materials normally used in stress history. With these relationships estab-

10 lo2 lo3 lo0 105 lo6 167


Number of Cycles Number of Cycles
Fig. 46 Design fatigue curve Fig. 47 Decrease in fatigue life
--
COMBUSTION
Designing For Boiler Performance

lished, the expected life can be estimated with overall boiler design. But it is unforturGtely
fair accuracy by adding together the "cycle true that the fundamental importance of heat
ratios" produced by each operating condition. transfer and fluid flow tends to obscure the role
of the boiler structural designer whose taskis to
i=n 5 analyze the many internal and external loads
Cumulative Damage Index = and to select suitable structural members.
i-1 Ni
(64) Structural design of boilers shares much in
common with bridge and building design.
There is a long history of progressive advance-
where Piis the number of times operating cycle
ment in this engineering art.61 Yet there is little
will occur and N i is the number of times alter- evidence of a specialized literature of boiler
nating stress can be withstood, based on the
structural design, and almost no consideration
fatigue design curve.
is given to structural problems in the most
Fatigue tests have shown that the cumulative widely used works on power-plant design.62
damage'index can vary over a range of 0.6 to 5.
If the most damaging stresses are applied first, STRUCTURAL DESIGN CONDITIONS
the cycles ratio may be as low as 0.6. If the lower
stress values are applied first and followed by Structural design of boilers involves the con-
sideration of many factors. The type of boiler,
progressively higher stresses, the cycles ratio
its location, and its method of construction all
can be as high as five. These are extreme condi-
have a bearing, as do design specifications,
tions. For the instance of random distribution of
cycle ratio as for a furnace wall, the cumulative codes and ordinances, protective coatings, and
sum will be close to unity. Thus the imposed type of structure, including choice of members
limiting condition is and connections.
Supports for boilers vary greatly, depending
upon size and function. Utility boilers and the
larger industrial units, including recovery
units for pulp and paper mills, are top-
supported. Contrarily, shop-assembled boilers
including those for waste-heat recovery and
Welded furnace walls must be safe and re- high-temperature water are bottom-supported,
liable for a wide range of boiler operating as are those for marine service. This section,
conditions. The analytical techniques and however, will be specifically concerned with
experimental procedures discussed in this sec- the structural design of a top-supported central-
tion give the boiler designer the necessary tools .station boiler.
to make an evaluation of the strength of furnace
LOCATION OF INSTALLATION
walls and to assess the suitability of furnace
wall design to withstand any of the various Boiler location has various effects upon
operating conditions. structural design. It may determine whether
indoor or outdoor construction is used. It has a
bearing on the specification of domestic or
DESIGN OF BOILER foreign steel shapes. It may require special con-
STRUCTURAL SUPPORT sideration for climatic conditions, including
both natural occurrences and those artifically
SYSTEMS induced, as in a chemical plant or oil refinery.
Because the combustion process must be It will establish wind loads, seismic conditions
confined within a complex structure capable of and soil bearing capabilities for foundations.
supporting many static and dynamic loads, Local ordinances and regulations may impose
structural design is an important sector of special requirements, including restrictions on
COMBUSTION
Designing For Boiler Performance

materials and limitations of structural size. protective coatings for steel may be found in
Indoor boilers for utility service are a part of the Steel Structures Painting Manual.@
the power-plant structure, using the building The American Institute of Steel Construc-
columns for vertical support.-Lateral support is tion's Manual of Steel Construction covers
provided by the bracing system of the building, most routine design work. This manual in-
which is completely enclosed and roofed. cludes the "AISC Specification for the Design
Boiler platforms for access and maintenance Fabrication and Erection of Structural Steel for
are coordinated with the elevations of power- Buildings" plus an extended cornrnentary.65
plant floors. Structural design of a large boiler involves
Although outdoor units may have the boiler the solution of many simultaneous equations
completely exposed to wind and weather, and can most efficiently be done by using a
many are built with a full or partial roof and a structural-design computer program such as
protective enclosure , around the fuel-firing STRUDL.66 Such structures are very large, often
equipment. Special consideration must be exceeding 200 feet in height and involving the
given to the waterproof design of casings and design and erection of several thousand tons of
insulation for outdoor units. structural steel.
Top-supported boilers have many hangers
SOURCES OF DESIGN INFORMATION which carry the loads of the various component
Many decisions must precede calculations pressure-parts to the structural steel framing.
for structural design. For example, will the unit The boiler is allowed to expand downward
be designed for indoor or outdoor construc- from the main supports at the top of the struc-
tion? Should the frame be rigid; simple, or ture; both structural-steel members and hanger
semirigid? Related to this is the choice of alter- rods are used. In high-temperature areas, the
native connections: riveted, bolted, or welded. hangers may be water-cooled or steam-cooled
It is also wise at this time to consider protective tubing operating at high pressure and designed
coatings and their application. to theASME Code.
There are many codes, standards and spec- A distinctive feature of boiler structural de-
ifications pertinent to and helpful in making sign is the buckstay system, which protects the
these decisions. One useful publication is pressure parts against transient internal or ex-
Minimum Design Loads in Buildings and Other ternal forces. The pressure parts, including
Structures63 which lists design loads for many waterwall tubing and wall radiant surface, are
materials, gives estimated weights of snowfall attached to and must therefore deflect with the
and wind loads for practically all geographical buckstays. Spacing of buckstays is determined
areas of the United States, and includes seismic from furnace pressure, tube diameter and spac-
factors relating to the most common occur- ing, and that part of the allowable stress in the
rences of earthquakes. Detailed information' on tubing which can be allotted for bending.
COMBUSTION
Designing For Boiler Perlormance

REFERENCES
M. K. Drewry. "Economy of Efficient Air Preheating with 13 J. R. Branstetter, Formulas for Radiative Heat Transfer Be-
Extraction Steam," Transactions of the ASME Journal of tween Nongray Parallel Plates of Polished Refractory
Engineering for Power, 84:l-8. January 1962; also ASME Metals. Report No. NASA-TN-D-2902 (N65-27550).
Paper No. 60-WA-94. New York: American Society of Springfield, VA: National Technical Information Service.
Mechanical Engineers, 1960. 1965.
2"Cold-end Temperature and Material Selection Guide 1.J. D. Buckmaster, Radiative Heat Transfer and Conduc-
for Ljungstrom Air Preheaters:' the Air Preheater Com- tion Between Parallel Walls. Report No. AD-619 419.
. pany, Inc., Wellsville, NY (request latest edition). Springfield, VA: National Technical Information Service,
1965.
'Nsakala ya Nsakala, Ramesh L. Patel, Richard W. Borio;
An Advanced Methodology for Prediction of Carbon Loss 1s R. Viskanta, "Heat Transfer by Conduction and Radiation
in Commercial Pulverized Coal-Fired Boilers; for Presen- in Absorbing and Scattering Materials:' Transactions of
tation at the 1986 ASMEIIEEE Joint Power Generation the ASME Journal of Heat Transfer, 87343-150, February
Conference, Portland, Oregon, October 19-23, 1986, 1965. Also: ASME Paper No. 64-HT-33. New York: Ameri-
Combustion Engineering's Publication TIS-8211. can Society of Mechanical Engineers. 1964.
'Goetz, G. J., Nsakala, N., Patel, R. L., and Lao, T. C., EPRI "H. M. Hsia and T. J. Love. "Radiative Heat Transfer Be-
Final Report AP-2601, September 1982. tween Parallel Plates Separated by a Nonisothermal
'Nsakala, N., Patel, R. L., and Lao, T. C., DOE Final Medium with Anisotropic Scattering." Transactions of
the ASME Journal of Heot Transfer, 89:197-204, August
Report, DOElPCl40267-5, March 1985.
1967. Also: ASME Paper No. 66-WAiHT-28. New York:
GNsakala, N., Patel. R. L., and Lao, T. C., The 189th Ameri- American Society of Mechanical Engineers, 1966.
can Chemical Society National Meeting, Miami. Florida,
17D. K. Edwards and K. E. Nelson, "Rapid Calculation of
April 28-May 3, 1985. Combustion Engineering's Publi-
Radiant Energy Transfer Between Nongray Walls and
cation TIS-7877.
Isothermal H,O or C02 Gas:' Transactions of the ASME
"Steam Generating Units," ASME Performance Test Journal of Heat Transfer, 84:273-278, November 1962.
Codes, PTC No. 4.1. New York: American Society of Also: ASME Paper No. 61-WA-175. New York: American
Mechanical Engineers, latest edition. Society of Mechanical Engineers, 1961.
a Josef Stefan, "Uber Die Beziehung Zeischen der Warmes- laMichael A,. Lutz, Radiant Energy Loss From a Cesiurn-
trahhung und der Temperatur," Akademie der Wis- Argon Plasma to an Infinite Parallel Enclosure; Avco-
senschaft. Sitzungs Berichte, 79:391-428,1879. Everett Research Laboratory Report 175. Report No.
Ludwig Boltzmann, "Deduction of Stefan's Formula for AD-431 640 (BSD-TDR-64-6). Springfield, VA: National
Radiation from Maxwell's Electromagnetic Theory of Technical Information Service, 1963.
Light:' Annalen der Physik und der Physikalischen
Chemie, 22:291-294, 1884. 19Yuan-Siang Pan, Temperature Discontinuities a n d
Max Planck, Theory of Heot Radiation, 2nd ed. Trans- Energy Transfer in One-Dimensional Problems. Report
lated by Morton Masius. New York: Dover Publications, No. AD-618 220. Springfield, VA: National Technical
1959. Service, 1965.

9C. M. Vsiskin and E. M. Sparrow, "Thermal Radiation Be- 20T. J. Love and R. J. Grosh, "Radiative Heat Transfer in Ab- ,
tween Parallel Plates Separated by an Absorbing-Emitting sorbing, Emitting, and Scattering Media," Transactions of
Nonisothermal Gas," International Journal of Heat and the ASME Journal of Heat Transfer, 87:161-166, May
Mass Transfer, 1(1):28-36, 1960 1965. Also: ASME Paper No. 64-HT-28. New York: Ameri-
can Society of Mechanical Engineers, 1964.
lo Thomas H. Einstein, Radiant Heat Transfer to Absorbing
Gases Enclosed Between Parallel Flat Plates with Flow 2lJohn R. Howell, Radiative Interactions Between
and Conduction. Report No. NASA-TR-R-154 (N64- Absorbing-Emitting and Glowing Media with Internal
11558). Springfield, VA: National Technical Information Energy Generation. Report No. NASA-TN-D-3614 (N66-
Service, 1963. 36426). Springfield, VA: National Technical Information
Service, 1966.
l1 J. R. Howell and M. Perlmutter, "Monte Carlo Solution of
Thermal Transfer Through Radiant Media Between Gray 22 E. M. Sparrow and A. Haji-Sheikh, "A Generalized \'aria-
Walls:' Transaction of the ASME Journal of Heat Trans- tional Method for Calculating Radiant Interchange Be-
fer, 86316-122, February 1964. Also in: ASME Paper No. tween Surfaces," Transactions of the ASME Journal of
63-AHGT-1. New York: American Society of Mechanical Heat Transfer, 87:103-109, February 1965. Also: ASME
Engineers, 1963. Paper No. 64-HT-11. New York: American Society of
Mechanical Engineefs, 1964.
I2J. R. Branstetter, Radiant Heat Transfer Between Nongray
Parallel Plates of Tungsten. Report No. NASA-TN-D-1088 23R. Viskanta and R. J. Grosh, "Heat Transfer in a Thermal
(N62-71662). Springfield, VA: National Technical Infor- Radiation Absorbing and Scattering Medium," Inter-
mation Service. 1961. national Developments in Heat Transfer, Proceedings of
COMBUSTION
Designing For Bo.ler Performance

the 1961-62 International Heat Transfer Conference, 3". C. Hottell, "The Melchett Lecture for 1960: Radiative
Boulder, Colorado, August 28-September 1, 1961 and Transfer in Combustion Chambers," Institute of Fuel
London, January 8-12, 1962, Part IV, Section B- Journal, 34(245):220-234, June 1961.
Radiation, Thermal Properties and Instrumentation, 36H. C. Hottell and A. C. Sarofim, Radiative Transfer. New
Paper 99, pp. 820-828. New York: American Society of York: McGraw-Hill, 1967.
Mechanical Engineers, 1963.
37 D. B. Spalding, "Mathematical Models of Continuous Corn-
24 Masayoshi Kuwata and Robert H. Essenhigh, "Compara-
bustion:' Emissions from Continous Combustion Systems,
tive Influence of Turbulence and Convention in Combus- Proceedings, Symposium, Warren, MI, Sep-
tor Performance" Proceedings of the Second Conference tember 27-28, 1971. New York: Plenum, 1972.
on Natural Gas Research and Technology, Atlanta, June
5-7, 1972, Session IV, Paper 3. Chicago: Institute of Gas 38 William H. McAdams, Heat Transmission, 3rd ed. New
Technology, ND. York: McGraw-Hill, 1954.
2sMehty A. E. Zeinalov, Masayoshi Kuwata, and Robert H. BS. S. Penner and P. Varanasi, "Simplified Procedures for
Essenhigh, "Stirring Factors in Combustion Chambers: A Estimating Band and Total Emissivities of Polyatomic
Finite-Element Model of Mixing Along an 'Information Molecules," Eleventh Symposium [International) on
Flow Path'," Fourteenth Symposium (International) on Combustion, University of California at Berkeley, August
Combustion, University Park, PA, August 20-25, 1972, 14-20, 1966, pp. 569-576. Pittsburgh: The Combustion
pp. 575-583. Pittsburgh: The Combustion Institute, 1973. Institute, 1967.
26Satvanaravana T. R. Rao and R. H. Essenhigh, "Experi- 40K. A. Bueters, "Combustion Products Emissivity by FE
mental ~kterminationof Stirring Factors Generated by Operator," Combustion, 45(9):12-18, March 1974.
Straieht and Swirling lets in Isothermal Combustion-
- ,
~ h a i b e h.Iodels,"
r Thirteenth Symposium (Inter- 41 K. A. Bueters, J. G. Cogoli, and W. W. Habelt, "Per-
national) on Combustion, Salt Lake City, August 23-29, formance Prediction of Tangentially Fired Utility Fur-
1970, pp. 603-615. Pittsburgh: The Combustion Institute, naces by Computer Mode," Fifteenth Symposium [lnter-
1971. national) on Combustion, Tokyo, August 25-31, 1974, p p
1243-1260. Pittsburgh: The Combustion Institute, 1974.
ZlRobert H. ~ s s e n h i ~ A
h ,New Application of Perfectly
Stirred Reactor (P.S.R.) Theory to Design of Combustion 42H. F. Mullikin, "Evaluation of Effective Radiant Heating
Chambers. Report No. AD-812 114. (Pennsylvania State Surface and Application of the Stefan-Boltzmann Law to
University, Department of Fuel Science Technical Report Heat Absorption in Boiler Furnaces:' Transactions of the
No. FS67-1(U) ). (Contract 656(29) ). Springfield. VA: ASME, 57:517-529, 1935.
National Technical Information Service. 1967.
Frederick P. Boynton and Claus B. Ludwig, "Total Emis-
43
18 A. M. Godridge, "Heat Transfer in the Furnace Chamber of sivity of Hot Water Vapor-11. Semi-Empirical Charts
Pulverized-Fuel-Fired Water-Tube Boilers:' Institute of Deduced from Long-Path Spectral Data," International
Fuel Journal, 40(318):300-310, July 1967. Journal of Heat and Mass Transfer, 14(7):963-973, July
1971.
29V. A. Lokshin, I. E. Semenovker and Yu. V. Vikhrev,
"Calculating the Temperature Conditions of the Radiant " F. R. Steward and P. Cannon, "The Calculation of Radia-
Heating Surfaces in Supercritical Boilers:' Thermal En- tive Heat Flux in a Cylindrical Furnace Using the Monte
gineering [Translation of Teploenegetika], 15(9):34-39, Carlo Method:' International Journal of Heat and Mass
September 1968. Tmnsfer, 14(2):245-262. February 1971.
30s. S. Filimonov, et al., "Calculation of Average Tempera- 45 H. C. Hottel and R. B. Egbert, "Radiant Heat Tmnsmission
ture and Thermal Resistance of Heating Surfaces in Fur- from Water Vapor," AIChE Transactions, 38(3):531-568,
nace Chambers," Thermal Engineering [Translation of June 1942.
Teploenergetika], 15(9):40-44, September 1968. "H. R. Hazard, et al., "Field Studies of Slagging in Tangen-
31 E. S. Karasina, 'Allowance for Fouling of Radiant Heating tially Fired Boiler Furnaces- Part I, Labadie Field Trial,"
Surfaces." Thermal Engineering [Translation of Teplo- ASME Paper No. 78-WalFu-10. New York; American Soci-
energetika]. 15(6):17-22, June 1968. ety of Mechanical Engineers, 1978.
3ZR. H. ~ s s e n h i ~ h , 'al..
e t Furnace Analysis: A Compamtive 4 l LV. E. Dalby, "Heat Trdnsmission:' Institution of Mechan-
Study. Pennsylvania State University, Department of Fuel ical Engineers Proceedings, Parts 3-4:921-1071, 1909.
Science Technical Report No. FSICGSSC-12165-4. Univer- \V. J. Wohlenberg, et al., 'An Experimental Investigation
sity Park. PA: Pennsylvania State University, 1969. of Heat Absorption in Boiler Furnaces," Transactions of
33 J. M. Beer and R. G. Siddall. "Radiative Heat Transfer in the ASME, 57541-554, 1935.
Furnaces and Combustion," ASME Paper No. 72-WAl Osborne Reynolds, "On the Extent and Action of the
HT-29. New York: American Society of Mechanical En- Heating Surface for Steam Boilers," Manchester Literary
gineers, 1972. and Philosophical Society Pro~eedin~s. 14:7-12, October
6,1874.
YH. C. Hottell and E. S. Cohen. "Radiant Heat Exchange in a L. M. K. Boelter, R. C. Martinelli, and Finn Johanssen,
Gas-Filled Enclosure," ASME Paper No. 57-HT-23. New "Remarks on the Analogy Between Heat Transfer and
York: American Society of Mechanical Engineers. 1957. biomentum Transfer," Transactions of the ASME,
COYllUSllON
D.dgn/ng For Performance

63:447-455,1941. 59 Miklos I. Hetenyi, Handbook of Experimental-Stress


W. F. Davidson, et al.. "Studies of Heat Transmission Analysis. New York: John 'M1iley and Sons, 1950.
Thmugh Boiler Tubing at Pressures from 500 to 3300 A. J. Durelli, E. A. Phillips, and C. H. Isao, Introduction
Pounds," Transactions of the ASME, 65:553-591. 1943. to the Theoretical and Experimental Analysis of Stress
Max Jakob. Heat Transfer, Vol. 11. New York: John \Viley and Strain. New York: McGraw-Hill, 1958.
and Sons, 1957, pp. 373-381. Albert Kobayahsi, ed., Manual on Experimental Stress
Analysis, 3rd ed. Westport, CT: Society for Experimental
@Orville L. Pierson, "Experimental Investigation of the In- Stress Analysis, 1978.
fluence of Tube Arrangement on Convection Heat Transfer Society for Experimental Stress Analysis, Experimental
and Flow Resistance in Cross Flow of Gases Over Tube Stress Analysis; Proceedings of the Society for Experimen-
Banks," Tmnsactions of the ASME, 59:563-572,1937. tal Stress Analysis, V.l-.Westport, CT: Society for Exper-
49E.D. Grimison. "Correlation and Utilization of New Data imental Stress Analysis, 1943.
on Flow Resistance and Heat Transfer for Cross Flmv of 60C. C. Perry and'^. R. Lisner, The Strain Gage Primer, 2nd
Gases Over Tube Banks," Transactions of the ASME, ed. New York: McGraw-Hill, 1962.
59~583-594,1937. Frank G. Tatnall, Tatnall on Testing: An Autobiographi-
cal Account of Adventures Under 13 Vice Presidents. Met-
5OE. C. Huge, "Experimental Investigation of Effects of als Park, OH: American Society for Metals, 1966.
Equipment Size on Convection Heat Transfer and Flow
Resistance in Cross Flow of Gases Over Tube Banks:' 61 L. E. Grinter, Theory of Modern Steel Structures, revised
Tmnsactions of the A W E , 59:573-581,1937. ed. New York: Macmillan, 1949.
H. M. Westergaard, "One Hundred Fifty Years Advance
51 Clarence F. Hirshfeld, William N. Barnard, Frank 0.
in Structural Analysis:' American Society of Civil En-
Ellenwood, Elements of Heat-Power Engineering, Part 111;
gineers Transactions, 94:226-246, 1930.
Auxiliary Equipment, Plant Ensemble, Air Conditioning,
Stanley B. Hamilton, "The Historical Development of
and Refrigeration 3rd ed. New York: John Wiley and Sons, Structural Theory," Institution of Civil Engineers Proceed-
1933. ings, 1, Part 3:374-419, 1952.
QAmerican Society of Mechanical Engineers. Boiler and
"A. H. Palmer, et al., "Integrated Structural Steel Design
Pressure Vessel Committee, ASME Boiler and Pressure
Program," American Society of Civil Engineers Proceed-
Vessel Code. New York: American Society of Mechanical
ings, Journal ofthe Power Division, 89(PO-1):67-82, Sep-
Engineers, latest edition.
tember 1963.
53Stephen Timoshenko and S. Woinowsky-Kmiger, Theory
63"Building Code Requirements for Minimum Design
of Plates and Shells, 2nd ed. New York: McGraw-Hill,
1959. Loads in Buildings and Other Structures:' ANSI Standard
No. A58.1. Sponsored by the National Bureau of Standards
"G. W. Watts and W. R. Burrows, "The Basic Elastic Theory and approved by the American National Standards Insti-
of Vessel Heads Under Internal Pressure," Transactions of tute. New York: American National Standards Institute,
the ASME Journal of Applied Mechanics, 71:55-73, latest edition. \
March 1949.
64 "Steel Structures Painting Manual", Volume 1 covers
~ M i k l o sHetenyi, Beams on Elastic Foundation; Theory methods of surface preparation and paint systems.
with Applications in the Fields oy Civil and Mechanical Volume 2 lists all types of important paint systems used
Engineering. Ann Arbor, MI: University of Michigan Press, in various industries; it also includes a guide with
1946. indexes for selection of suitable systems for various
structures ad exposures, specifications for- surface
SG. K. Cooper and L. W. Smith, Final Report of PVRC Proj- preparation and pretreatment, paint application and
ect of the American Welding Society, Purdue University, paints. Obtained from the Steel Structures Painting
August 1952. This report can be obtained from Pressure Council, Pittsburgh, PA.
Vessel Research Council, United Engineering Center. New
York. 6S1'Manual of Steel Construction", latest edition;
American Institute of Steel Construction, N.Y.
57 Julien Dubuc and Georges Welter, "Investigation of Static
and Fatigue Resistance of Model Pressure Vessels:' I\'eld- MRobert D. Logscher, et al., ICES STRUDL-11: The Structural
ing Journal, 35:329s-337s, July 1956. Design Language Engineering User's Manual, Vol 1; Frame
Analysis, 1st ed. Massachusetts Institute of Technology,
58G. J. Schoessow and E. A. Brooks, Analysis of Experi- Department of Civil Engineering, Structures Division and
mental Data Regarding Certain Design Features with Pres- Civil Engineering Systems Laboratory Research Report
sure Vessels:' Transactions of the ASME; 72:567-577, R68-91. Cambridge, MA: Massachusetts Institute of
July 1950. Technology, 1968.
CHAPTER 7

Central-Station Steam Generators

ost of the fundamentals on boiler design, The C-E product line and C-E's desire for ex-
fuels, ash, coal pulverization, materials cellence extend from the central-station de-
selection, manufacture, field construction, and signs to industrial and marine boilers. But it is
operation in this book are common in whole or for the development of its large high-pressure
in part to the technology of boiler designers steam generators that C-E has built and staffed
and manufacturers worldwide. The engineer- some of the finest research laboratories in the
ing information in this chapter departs from world dedicated solely to the development and
that commonality. improvement of equipment for steam genera-
This chapter presents the C-E design philoso- tion at the efficient high-pressure levels.
phy as it applies to large high-pressure steam
generators for service in electrical-power pro-
duction. Specifically covered are tangentially IMPACT OF FUEL
fired subcritical- and supercritical-pressure
boilers - their design and the ways they are in-
ON BOILER DESIGN
tegrated into the overall power plant to obtain The most important item to consider when
maximum reliability and flexibility. The units designing a utility or large industrial steam
described are categorized in Chapter 4 as the generator is the fuel the unit will burn. The fur-
entrained-flow-reactor, suspension-fired, or nace size, the equipment to prepare and burn
open-furnace type; fluidized-bed boilers for the fuel, the amount of heating surface and its
power generation are covered in Chapter 9. placement, the type and size of heat-recovery
Since WWII, manufacturers have developed equipment, and the flue-gas treatment devices
diverse designs for generating steam at the are all fuel dependent.
high subcritical and supercritical pressures. The major differences among those boilers
The diversity is particularly apparent in large that burn coal or oil or natural gas result from
high-pressure units for which the individual the ash in the products of combustion. (See
proprietary designs become both the hallmark Chapter 3.) Firing oil in a furnace results in rel-
and raison d'btre for each manufacturer. Like atively small amounts of ash; there is no ash
fingerprints, the arguments made for the super- from natural gas. For the same output, because
iority of a circulation or firing system character- of the ash, coal-burning boilers must have
ize and differentiate all boiler desi,oners. larger furnaces and the velocities of the com-
COMBUSTION
CentralStatlonSteam Generators

I . - -

Fig. 1 Typical coal-burning central-station reheat steam generator of the CUEtangentially fired
Controlled Circulation@design
COMBrnON
CentraCStatlon Steam Generators

bustion gases in the convection passes must be considerable space. (Fig. 1).
lower. In addition, coal-burning boilers need Table I lists the variation in calorific values
ash-handling and particulate cleanup equip- and moisture contents of several coals, and the
ment that adds a- great-dealto cost and requires mass of fuel that mustbe handled and fired to

Table I.Representative Coal Analyses


Med.-Vol. High-Vol. Subbitum- Low-Sodium Med.-Sodium High-Sodium
Bituminous Bituminous inous C Lignite Lignite Lignite

Total H,O,% 5.0 15.4 30.0 31.0 30.0 39.6


Ash, % 10.3 15.0 5.8 10.4 28.4 6.3
VM, '10 31.6 33.1 32.6 31.7 23.2 27.5
FC, 1'0 53.1 36.5 36.6 26.9 18.4 26.6

Ash analysis, OO/


SiO, 40.0 46.4 29.5 46.1 62.9 23.1
A1,O, 24.0 16.2 16.0 15.2 17.5 11.3
Fez03 16.8 20.0 4.1 3.7 2.8 8.5
CaO 5.8 7.1 26.5 16.6 4.8 23.8
MgO 2.0 0.8 4.2 3.2 0.7 5.9
Na,O , 0.8 0.7 1.4 0.4 3.1 7.4
K2O 2.4 1.5 0.5 0.6 2.0 0.7
TiO, 1.3 1.0 1.3 1.2 0.8 0.5
p20, 0.1 0.1 1.1 0.1 0.1 0.2
so3 5.3 6.0 14.8 12.7 4.6 17.7
sulfur, Oo/ 1.8 3.2 0.3 0.6 1.7 0.8

Fusion (reducing), F
Initial Deformation 2,170 1,990 2,200 2,080 2,120 2,030
Softening 2,250 2,120 2,250 2,200 2,380 2,090
Fluid 2,440 2,290 2,290 2,310 2,700 2,200

Fusion (reducing), C
Initial Deformation 1 190 1090 1200 1140 1 160 1110
Softening 1 230 1 160 1230 1200 1 300 1 140
Fluid 1 340 1250 1250 1270 1480 1 200

Btullb, as fired
Btullb, MAF
Lb AshlMillion Btu
*Fuel Fired, 1000 lbhr
*Ash Fired, 1000 lblhr
MJlkg,as fired
MJlkg, MAF
kg Ash Million kJ
*Fuel Fired, kgls
*Ash Fired, kgls
'Constant Heat Output, Nominal 600-MW Unit. Adjusted For Effect of Moisture Content on Efficiency
COMBmnON
Csntr8Ist.Uon Steam Generators

generate the same electrical-power output. tics are fired.


These values are important because the quan- Fig. 2 is a simplified characterization of ac-
tity of fuel required helps determine the size of tual furnaces built to burn the fuels in Table I.
the coal storage yard, as well as the handling, Wide variations exist in fuel properties within
crushing, and pulverizing equipment for the coal ranks, as well as within several subclassifi-
various coals; the amount of ash in the coal di- cations (e.g., subbituminous A, B, C), each of
rectly affects the sizing of the ash-handling and which may require a different size furnace. Note
flue-gas cleaning equipment. that, in general, high-sodium lignites tend also
to have high slagging tendencies.
FURNACE SIZING
Among the most important design criteria in
As stated in Chapter 6, the most important large pulverized-fuel tangentially fired fur-
step in coal-fired unit design is to properly size naces are the net heat input in Btulhr-sq ft or
the furnace. Furnace size has a first-order influ- W/m2 of furnace plan area (NHIIPA) and the
ence on the size and cost of the convective heat- vertical distance from the top fuel nozzle to the
transfer surface, the structural steel framing, furnace arch. Furnace dimensions must be ade-
the boiler building and its foundations, as well quate to establish the necessary furnace reten-
as on the quantity and length of sootblowers, tion time to properly burn the fuel as well as to
the extent of platforms and stairways, and the cool the gaseous combustion products. This is
arrangement of steam piping and ductwork. to ensure that the gas temperature at the furnace
Three very important parametric influences outlet plane is well below the ash-softening
on furnace sizing are : temperature of the lowest quality coal burned.
fuel reactivity (discussed in Chapter 2) Specifically, the furnace outlet plane is the en-
gaseous-emission limitations (particularly trance to the closed-spaced convection surface;
those concerning oxides of nitrogen), and the latter is defined as non-platen surface on
fuel-ash properties. less than 1 2 inch (300 mm) horizontal centers.
Among the ash properties discussed in Chap- In addition to the tilting of fuel and air nozzles,
ter 3 and Appendix B, those that C-E considers the heat-absorption characteristics of the walls
particularly important when designing and are maintained using properly placed wall
establishing the size of coal-fired furnaces blowers to control the furnace outlet gas tem-
include: perature by removing ash deposited on the fur-
8 the ash fusibility temperatures (both in terms
nace walls below the furnace outlet plane.
of their absolute values and the spread or differ- To arrive at an appropriate value of NHIIPA
ence between initial deformation temperature and furnace plan area requires thorough evalua-
and fluid temperature) tion of all fuels expected to be burned in the
the ratio of basic to acidic ash constituents unit. Depending on the analyses and range of
the ironlcalcium ratio coals to be burned, large pulverized-fuel units
the fuel-ash content in terms of lbs of ash1 have an NHItPA that generally varies from 1.4 to
million Btu or kg of ashlmillion joules 2.0 x lo6 Btulhr-sq ft (4.4 to 6.3 x lo6 W/m2).
the ash friability. The distance from the upper fuel nozzle to
the furnace arch is a function of furnace width
These characteristics translate into the typi- and depth, the upper-furnace superheater and
cal furnace sizes shown in Fig. 2, which are reheater surface arrangement, and, of course,
based on the six coal ranks shown in Table I. the fuel and ash characteristics.
This size comparison illustrates the C-E philos- Widely spaced steam-cooled platen-type
ophy of increasing the furnace plan area, vol- heating surface i s usually required in the upper
-,. . -ume, and the fuel burnout zone (the distance furnace to provide further cooling of furnace
from the top fuel nozzle to the furnace arch), as gases before entering the convection surface.
lower grade coals with poorer ash characteris- These sections potentially are subject to the
COMBrnON
Centfaf-Station Steam Generaton

Medium-Volatile High-Volatile Low-Slagging Medium- High-Slagging


Bituminous Bituminous Lignite Slagging Lignite
or Lignite
Subbituminous
I I

Fig. 2 Effect of coal rank on sizing of a pulverized-fuel furnace (constant heat output)

most severe fouling conditions and wide spac- The vertical distance from the lowest coal
ing helps prevent ash plugging caused by nozzle to the point where the furnace walls are
bridging. To perform satisfactorily in this bent to form the hopper section of the furnace is
environment, the platens are constructed with a function of furnace width and depth and the
the tubes tangent to each other in the direction slagging potential of the fuel. This dimension
of gas flow to minimize ash deposition. is generally between 1 2 and 20 feet (3-'12 and
A furnace design parameter sometimes speci- 6 meters) in a tangentially fired furnace. The
fied is burner-zone heat release. This term does hopper section typically slopes at 50' to the
not have the same significance in tangential fir- horizontal.
ing as in other firing systems. In tangential fir- With the exception of dry-bottom pulverized-
ing not all of the fuel is consumed in the coal units in sizes between approximately 50
windbox zone because of the manner in which and 100 MW, the furnace volumetric heat-
the fuel and air are introduced into the furnace. release rate (in Btulhr-ft3 or W/m3) generally is
In a unit designed for wall firing, the fuel and not a controlling design parameter. For such
air are intimately mixed at the burner throat units, the release-rate range is from 15,000 Btul
and consumed directly in front of the burner. hr-ft3 for very good bituminous coals to about
With a wall-fired boiler, then, burners can be 10,000 Btulhr-ft3 for lignites (150,000 to about
moved farther apart or more burners can be 100,000 Wlm3).Similarly, the burner-zone volu-
added to give any value of burner-zone release metric heat-release rate in Btulhr-ft3 or Wlm3
rate as there is no interaction between rows is not a meaningful design parameter for tan-
of burners. gentially fired boilers.
COMBUSRON
CcntnlStrtion Steam Generators

DRY-BOTTOM VERSUS WET-BOTTOM FURNACES the furnace. Each of these configurations has
All current pulverized-coal reheat units are its advantages and allows for customer prefer-
of the dry-bottom type; the ash dislodged from ence as a factor in the final arrangement of
the furnace walls is below the ash-melting heating surface.
point and leaves the furnace bottom in a sub- ADVANTAGES OF THE PENDANT PANEL DESIGN
stantially dry condition. The wet-bottom or
slagging-bottom furnaces are offered today only The support elements for the pendant surface
for special applications, such as in furnaces for are out of the gas stream, above the furnace
gasifying coal. roof; this eliminates the exposure of load sup-
In the wet-bottom design, the lower part of ports and seals to high gas temperatures and
the flame has to sweep the furnace floor at all flyash erosion. Superheater and reheater tubes
loads to maintain the fluidity of the ash. This are free to expand downward, and have only
requirement imposes a definite limitation in simple alignment devices in the gas stream.
the use of slag-tap furnaces. Slag-tap freezing There is no relative motion between the fur-
can occur during operation at low load or when nace tubing and the superheater or reheater
fuel is fired only in the upper furnace for steam tubes where the latter penetrate the enclosure.
temperature conttol. In addition, wet-bottom Thus, the area of penetration can be seal-
units have higher nitrogen-oxide production. welded for maximum gas tightness, thereby
The dry-bottom furnace, on the other hand, eliminating the need for pressurized header
particularly those designs using tilting fuel enclosures.
nozzles, can provide a wider steam temperature The above support and sealing arrangement
control range and can handle coals with widely favors shop modularization of tubes, headers,
varying ash characteristics. It is this latter char- attachments, and supports. Field construction
acteristic, more than any other, that was origi- consists of lifting these modules into position,
nally responsible for the greater application of butt-welding adjacent header sections, and
dry-bottom units. seal-welding small areas of skin casing after the
In the usual dry-bottom furnace, the hopper horizontal furnace-roof tubes are in place.
is formed by bending the front- and rear-wall The lower height of the pendant boiler can be
tubes at their lower ends. The tube slope is expected to result in lower costs of the boiler
greater than the angle of repose of the ash, and building, elevators, platforms and stairways,
thus forms a self-cleaning, u~atercooledhopper. structural steel framing, and foundations, par-
Ash is discharged to the ash receiver through a ticularly in high seismic- and wind-load areas. ,

transverse opening in the hopper, about 4-ft In field erection, major pressure-part con-
(1.2m) wide on large units. struction can be carried out in several areas
simultaneously. Also, the pendant panel steam
ARRANGEMENT OF generator is not as tall, as the horizontal type,
UPPER-FURNACE HEATING SURFACE which reduces construction costs.
Any required replacement of, or modifica-
Combustion Engineering uses two principal tions to, heating surfaces are greatly simplified.
arrangements of upper-furnace heating surface, Widely spaced panels (6 to 8 feet or 2 to 2'12
which can be called the pendant panel and hor- meters horizontal centers), along with steam-
izontal-surface designs. The reheat steam gen- cooled wall sections in the upper furnace, have
erators shown in Figs. 1, 6, 11, 17, and 22 of high radiant-heat absorption, resulting in im-
this chapter illustrate the pendant panel de- proved steam-temperature control range.
sign as it is applied to large coal-fired units.-
The boiler in Fig. 3 is also a large coal-fired - *ADVANTAGESOF THE HORIZONTAL-SURFACEDESIGN
unit, but using <he horizontal arrangement of rn The essentially vertical gas flow through the
superheater and reheater surface -in the top of superheater and reheater tube banks minimizes
COMBUSTION
Central-Station Steam Generators

Fig. 3 Large pulverized-coal fired Controlled Circulation@unit with horizontal superheater and reheater
surface in top of furnace
COMBmnON
CenW-SWion Steam Genenrton

the potential for localized tube erosion that the tube section, at the maximum continuous
might result when gases take a 90" turn into the rating (MCR) of the steam generator fired at nor-
rear gas pass. mal excess-air percentage.
Horizontal tubing facilitates designing for Considering the above factors in furnace siz-
drainability, which simplifies freeze-protection ing and convection-pass design, it is impracti-
procedures, boilout, and hydrostatic testing. cal to propose a steam generator capable of
Large fused ash deposits that are removed by burning any kind of coal, nor would such a unit
sootblowers will usually drop through wider- be economically feasible. For example, con-
spaced tube sections below, directly to the fur- sider the wide variation in pulverizer size
nace bottom. and primary-air-temperature requirements for
Note that the horizontal arrangement requires a high-calorific-value, low-moisture, low-ash
that operators take care in start-up to ensure coal versus a subbituminous coal or lignite
that there is adequate cooling flow through the with a high moisture and ash content. Selecting
vertical hanger tubes that support and align the an optimum preparation and firing system for
horizontal tube bundles. Thermocouples one rank of fuel can result in a much less favor-
should be used to monitor hanger-tube temper- able situation for some other rank of fuel.
atures on start-up, especially in tubes with Operating experience on units firing certain
downward flow. coals shows the need for wide transverse tube
spacing throughout the unit to reduce the foul-
ing rate and possible bridging of ash deposits
CONVECTION-PASS DESIGN between adjacent assemblies. This arrange-
A number of coal-ash properties have a sig- ment minimizes serious fouling problems
nificant influence on superheater, reheater, and which have an adverse effect on fan power re-
economizer convection-surface design, and the quirements and unit availability.
associated considerations of fouling and ero- As the gas temperature is reduced along its
sion. Included are : flow path to well below the ash-softening
ash-softening temperature temperature of the worst coal expected to be
baselacid ratio burned, the transverse spacing of the convec-
ironlcalcium ratio tion - pass tube banks is also reduced-
sodium and potassium content depending on fuel type and the ash characteris-
silica and alumina content tics. The tube spacing selected at the entrance
chlorine content to the convection pass depends mainly on the
ash friability maximum gas temperature possible in this
In sizing and locating these sections within zone under upset conditions and the propen-
the unit, a proper balance is required to main- sity of the ash to adhere.
tain a thermal head with which to transfer heat In the superheater and reheater sections be-
from gas to steam as the heating-surface use is yond the ash-adhesion temperature zone, the
optimized and undesirably high metal temper- tube spacing is further reduced to the minimum
atures are avoided. Also, to limit pressure-part for effective penetration of sootblower jets. In
erosion from flyash, the flue-gas velocity must addition, gas velocities are maintained suffi-
not exceed reasonable limits. Depending upon ciently low to prevent erosion. To avoid serious
the ash quantity and abrasiveness, the design plugging, the transverse spacing in this area
velocity is generally 40 to 60 ftlsec. (12 to 18 must be wide enough to allow pieces of ac-
m/s). A boiler that burns coals yielding a heavy cumulated ash loosened by sootblowers to pass
loading of erosive ash (usually indicated by a through the tubebank and not bridge the span
high silicalalumina content) would use the between adjacent tube rows.
lower velocities. Such velocities are based on Table I1 is a guide for establishing transverse
the predicted average gas temperature entering clearances for platen and spaced convection
CentralStation Steam Generators

its circulating system is a function of two


Table 11. Transverse Clearance Guide distinct design parameters: the complete com-
bustion of the fuel andthe preservation of satis-
Temperature - .
Range - . -Inches of Clearance factory furnace-wall metal temperatures. To
this end, furnaces for burning pulverized solid
O F Nonfouling Coal Fouling Coal fuels must be configured to prevent the forma-
2000-2400 Platen -22 Platen -22 tion of objectionable slag deposits, which can
1750-2000 Spaced- 7 Platen -12 increase the furnace outlet-gas temperature
1450-1750 Spaced- 3 Spaced- 6 above design values. Generally, the large fur-
Up to 1450 Spaced- 2 Spaced- 3 naces and the wall deposits associated with
coal firing result in relatively low furnace-wall
absorption rates, so that tube-wall metal
surfaces. The guide is based on fouling and temperature does not influence furnace size.
nonfouling coals and gas temperatures at When firing oil, the larger amount of fuel
maximum boiler load. reaction surface available for combustion
produces complete combustion in a smaller
I COAL PROPERTIES USED FOR DESIGN
Coal properties to be used in a boiler design
furnace volume. The higher consequent heat-
release rate per unit area of furnace-wall sur-
are established by the purchaser's specifica- face can cause high localized heat-absorption
tions. It is preferable to show an analysis that rates. Furnace sizing for oil burning, then, must
represents an actual coal as the performance account for the effect of high absorption rates
coal and include low, average, and high analy- on both metal temperatures and circulation,
ses to confirm limits for the boiler design. Im- and these factors usually determine the dimen-
portant items of the analysis are calorific value, sions of an oil-fired furnace.'
moisture and ash contents, grindability index, Gas-fired furnace design is similar to oil-
and the ash analysis. If the fuel specifications fired, except for the fact that gas firing inher-
are stated as ranges, it is customary to consider ently results in lower localized heat-absorption
the average as the performance fuel but to rates. This allows designing somewhat smaller
design the u n i t to handle fuels with the furnaces with even higher heat-release rates
.worst analysis. than used for oil firing.
If coals from two or more sources may be
BURNING REFUSE IN UTILITY BOILERS
fired, individual analyses rather than a calcu-
lated average are desirable, with "low" and Chapter 8 describes methods of burning
"high" representing the composite. Justifica- municipal refuse and other cellulosic wastes in
tion for using individual analyses comes from industrial boilers. In such units, large per-
the necessity to evaluate pulverizer capabilities centages of mixed commercial and household
as well as ash influences on unit performance. refuse are burned; in some, a small startup
The "worst" coal can become the design coal burner is the only fossil fuel consuming device.
when there is a good probability that the power For several important reasons large pulver-
plant will use a significant amount of the ized-coal units primarily generating electricity
"worst" coal. Finally, if coals are to be blended, should limit refuse firing to 1 0 to 20 percent of
information must be provided on both the sepa- the full-load fuel firing rate. The following are
rate analyses and the possible blends, includ- some of these reasons.
ing values for eutectic fusibility temperatures. Even shredded and air-separated refuse is not
completely homogeneous, because refuse
FURNACE DESIGN
composition and moisture content vary con-
FOR OIL & GAS FIRING
siderably from season to season, and day to day.
Selecting a furnace size, its wall tubing, and This nonhomogeneity will result in much
.-
COMBUSllON
CentralStation Steam Generatom

wider fluctuations in the heating value than cised to insure that each tube receives a suffi-
that experienced with coal firing. cient flow of water to prevent overheating
Fired alone, refuse is potentially more corro- individual waterwall tubes as well as to prevent
sive than most coals and fuel oils. It appears an excessive temperature difference between
that the corrosion potential from burning ref- adjacent tubes. Flow instability, which can oc-
use is nearly linear with the percentage burned. cur in furnace circuits, is considerably more
It seems prudent, therefore, to limit the amount difficult to control when a large number of
of refuse burned in reheat units. tubes operate in parallel. The designer must
Generally speaking, the moisture content of calculate the heat absorption per furnace tube
prepared refuse will be more than triple that of from a forecast of the normal absorption pattern
bituminous coal (on a pounds-per-million-Btu of the entire furnace. This forecast depends on
basis) and will vary widely from day-to-day- the height and width of the furnace, but most of
as will its heating value. In addition the rela- all, on the manner in which the fuel is fired.
tively high moisture content.of refuse and the The anticipated pattern of heat absorption
corresponding decrease in fuel-firing effi- might not, however, be reproduced in service;
ciency will increase the combustion gas mass moreover, it will fluctuate from time to time due
compared to the primary fuels being burned in to load changes, transient conditions, and be-
any given plant. Limiting the percentage of re- cause the thickness of ash covering the walls
fuse burned minimizes the effect on superhea- will not always be the same. With certain firing
ter and reheater outlet steam temperatures, and systems the number of pulverizers and burners
on the air-heater exit gas temperature. in service also will vary the pattern.
At intervals ash deposits will drop off, or be
removed by sootblowing, and this will give rise
to further considerable variations. Misjudging
THE DESIGN OF the intensity or distribution of heat absorption
LARGE HIGH-PRESSURE may cause circulation difficulties that are im-
possible to correct except by decreasing the
FURNACE-WALL SYSTEMS rating and operating pressure of the boiler.
The design of the various heat-absorbing As the boiler operating pressure' approaches
equipment described in previous chapters in- the critical point (Chapter 5) the difference in
volves a finite pressure drop or resistance to the density of water and steam to produce
fluid flow. Air heaters, economizers, superheat- circulation approaches zero. Designing tube
ers and reheaters all have a multiplicity of par- circuits of low enough resistance to insure
allel flow paths or circuits through which the adequate velocities and adequate water-to-
fluid being heated must pass; the uniformity steam ratios in all tubes at all loads, with all
of the flow distribution depends largely upon fuels, under varying slagging conditions, and at
the magnitude of the pressure drop across the all firing rates becomes proportionately more
apparatus. difficult at the 2750 to 2850 psig (19.0 to 19.7
The watercooled furnace, in general, handles MPa gage) drum and waterwall operating-
the fluid it is heating in many more parallel cir- pressure level.
cuits than are found in the other heat-transfer Achieving proper circulation becomes in-
devices; therefore, the problem of distributing creasingly difficult not only with higher operat-
water to each tube and providing adequate cir- ing pressures, but also with increased unit
culation for cooling all the tubes is correspond- capacity. In units with high megawatt ratings,
ingly more difficult. the fuel fired per lineal foot of furnace perimeter
The tubes which form the furnace walls are of increases markedly compared to earlier 100 to
different lengths and are subject to varying 200 MW units. This has led the boiler industry
heat-absorption rates. Great care must be exer- to adopt internally rifled tubes for furnace walls
COMBUSTION
Central-Station Steam Generators

because higher percentages of steam can be tol- ACQUISITION OF


erated in the steam-water mixture in rifled fur- CIRCULATION DESIGN DATA
nace tubes, at lower mass velocities. The furnace enclosure is one of the most crit-
In any case, the difficulties of designing a ical components of a steam generator and must
satisfactory furnace-wall circulating system be conservatively designed to assure high
involve all these considerations: boiler availability. The circulation objective is
8 operating pressure level to assure sufficient cooling of the furnace tubes
during all operating conditions with an ade-
furnace physical arrangement
quate margin of reserve for transient upsets.
the Presence of non-heat-absorbingtubes near Adequate circulation prevents excessive metal
the fuel nozzles or burners temperatures or temperature differentials that
manufacturing tolerances of commercially could cause failures-in the furnace-wall tubes
available tubing (which affect inside diameter due to overstressing or corrosion.
and consequent pressure drop tube-to-tube) The design of a furnace-wall circulation sys-
allowance for different heat pickup in different tem is a procedure requiring knowledge and
portions of the furnace data obtained both from field operating units
and laboratory testing. The field data from
the possibility of internal or external deposits operating units is required to understand and
provision for the necessary pressure drop for characterize the heat-absorption characteris-
steam-water separation in the drum tics for a particular type of furnace configura-
tion and firing system, throughout a wide range
TANGENTIAL FIRING of load and water-side operating pressures, and
AND CIRCULATION SYSTEM DESIGN the effectthat fuel variation has on furnace heat
absorption.
With C-E tangential firing and its mode of Furnace absorption/distribution standards
introducing the fuel, the furnace is used as are developed by correlating test data from
the burner; thus, heat-absorption patterns are many operating units. The following important
much more uniform and more definable than parameters are considered in this work: fur-
with any other type of firing. As further de- nace geometry, fuel, excess air, type of firing,
scribed and illustrated in Chapters 11 and 12, disposition of fuel nozzles, heat input, and
the fuel and combustion air are introduced in furnace-wall cleanliness. By using these stan-
the corners of the furnace, but the actual burn- dards, it is possible to calculate the vertical
ing process takes place in the main body of the absorption-rate profile, the lateral heat-absorp-
furnace. Therefore, heat is not liberated in a tion distribution and other furnace heat ac-
concentrated form in the area of the fuel admis- cumulation patterns to properly engineer the
sion assemblies, nor is it concentrated on one furnace-wall circulation system.
side of the furnace. The laboratory data is required for a knowl-
As the load on the steam-generating unit edge of the physical properties of the furnace-
varies, the amount of heat admitted into the wall tubing under actual furnace heat-transfer
furnace is either increased or decreased uni- conditions. In the laboratory, flow versus qual-
formly, and i n such a manner that the heat ab- ity criteria have been established to predict
sorption pattern remains basically unchanged. DNB (departure from nucleate boiling) in a fur-
This is because each pulverizer feeds one hori- nace tube containing boiling water. This has
zontal level of fuel nozzles. These two features been done in C-E's high-pressure test loop at
of C-E's tangential firing, coupled with inher- the Kreisinger Development Laboratory. The al-
ently low flame temperatures, are an asset to lowable combinations of pressure, mass flow,
the successful design of and operation of the local bulk quality, and local crown absorption
furnace circulation system. rate have been calculated from correlations
COademnON
Central-SWon Steam Generators

based on the laboratory data. Additionally, the proaches the critical pressure of 3208 psia (22.1
derived engineering standards take into account MPa abs.). This could be done only by going to
data scatter, dimensional tolerance, instru- extremely large diameter furnace-wall tubes of
mentation error, and boiler water chemistry, all high-alloy materials and essentially zero pres-
to provide sufficient margin to accommodate sure-drop downcomer systems, risers, and
actual field operating conditions. drum internals. The highest practical thermal-
C-E researchers have tested both full-size circulation pressure that has been designed for
smooth and rifled tubes; this forms the basis for is 2800 psig (19.3 MPa gage) in the drum and
the design engineering of high-pressure boilers waterwall circuitry; this limits the available
using either type of furnace-wall tubing. pressure drop for superheater cooling when the
required superheater outlet pressure is above
2650 psig (18.3 MPa gage).
As furnace-wall operating pressures and fur-
FURNACE-WALL CIRCULATION nace sizes increase, a designer must have sub-
IN SUBCRITICAL-PRESSURE stantially greater knowledge of waterwall
heat-absorption patterns that result from firing-
STEAM GENERATORS system characteristics. Predictability and re-
Combustion Engineering uses two types of. peatability of such heat-flux patterns must be
circulating systems for subcritical-pressure ap- achievable on a positive, long-term basis. Oper-
plications-thermal (thermosyphonic or "natu- ator intervention or equipment malfunction
ral") circulation and its Controlled CirculationB must not permit a different distribution of heat
system. (Fig. 4). Each is designed to meet spe- input to the furnace walls other, than that for
cific power-plant requirements and to provide which the unit was designed.
certain advantages. CONTROLLED FORCED RECIRCULATION
THERMAL CIRCULATION In Chapter 5 , the concept of subcritical-pres-
sure controlled forced recirculation was intro-
Thermally induced circulation, in theory, duced. It was stated that a boiler with such a
could be used in the design of a boiler that ap- circulation system incorporates a recirculating

THERMAL CONTROLLED
d y r h e a t e r

Steam Drum
/
, Furnace
Walls

Orifices
Circulating Pump- Distribution
Header

Fig. 4 C-E drum-type subcritical-pressure circulating systems


COMBUSPION
CentrslStation Steam Generators

pump between the drum and waterwalls, there is a throttle-pressure level above 2200
thereby freeing the designer from dependence psig (15.2 MPa gage), particularly in large pul-
upon the difference in steam and water densi- verized-coal units, where a Controlled Circula-
ties to provide circulating head. Using a recir- tion system becomes -prudent. A 2850-psig
culating pump means that the designer is (19.7 MPa gage) drum-pressure limit has been
assured of positive circulation even before heat established for Controlled Circulation steam
is applied. Because the pump helps to over- generators. This limit permits operation of the
come friction loss in the waterwall tubes, it is 2400-psig (16.6 MPa gage) throttle-pressure cycle
possible to substitute smaller diameter tubes at 5 percent overpressure, or 2520 psig (17.4
for the larger diameter tubes required with a MPa gage) at the turbine, and as high as
limited thermal circulation head. The net result 2680 psig (18.5 MPa gage) at the boiler super-
is a lower-tube-weight, lower-metal-tempera- heater outlet.
ture wall with lower thermal stresses.
Another advantage to incorporating a recir-
culating pump is the greater flexibility of boiler THERMAL-CIRCULATION
layout. Also, more freedom exists in the arrange-
ment of boiler heating surface because, with
FURNACE DESIGN
assured positive circulation, horizontal evapora- Thermal circulation results from a density
tion surface may be used to any extent desired. difference between the mixture of saturated
The C-E system for controlled forced re- water and feedwater in the downcomers (down-
circulation at the high subcritical-pressure level takes) and the lighter steam-water mixture in
is called Controlled Circulation. C-E does not the furnace-wall tubes. The temperature and
presume to select that pressure which sharply corresponding density in the downtakes can be
differentiates between the possibility of using changed somewhat in the initial design of a
thermally induced circulation from the ad- unit by varying the water temperature leaving
visability of using a Controlled Circulation the economizer. Fig. 5 shows how the furnace-
system. However, C-E designers believe that wall operating pressure and the percent steam

Operating Pressure
20oopsig
2200 psig
2400 psig
2600 psig
2800 psig
3000 psig

I I I I 1
20 40 60 80 100
O/O Steam (Mass Basis) Leaving Top of Furnace
I 1
Fig. 5 Typical available static head for circulation based on 200-ft. high furnace; this available head is inde-
pendent of type of circulation
COLBUSITON
Centnl-SMon Steam Generators

in the mixture in the wall tube affect the avail- Tangential fuel nozzles are located 2 five
able thermal head for circulation. The available elevations in the four corners of the boiler fur-
head is the difference between the weight of nace. Vertical downcomers connecting the
water i n the unheated downcomer and the steam drum to the bottom waterwall header
static head of the steam-water mixture in the system supply the boiler water. Lower ends of
heated waterwall tubes. the front, rear, and side wall tubes connect to
Fig. 6 shows a typical C-E thermal-circula- the bottom waterwall headers and the upper
'tion reheat steam generator for burning pulver- ends connect to the upper headers. Relief
ized subbituminous coal, for low to medium (riser) tubes transport the mixture of steam and
sub-critical pressures. water from the waterwalls to the drum, where

J
Fig. 6 C-E thermal-circulationtangentially fired pulverized-coalsteam generator
COMBmTION
CentaCStationSteam Generators

the steam is separated from the boiler water. To Shown in Fig. 7 is a cross section of a drum
insure uniform distribution of steam and water, used in C-E thermal-circulation boilers. In this
the connecting tubes are spaced evenly along drum, the steam-water mixture from the fur-
the drum and headers. Steam which has been nace passes through the centrifugal separators
separated from the steam-water mixture in the where a spin is imparted. This forces the water
drum passes on to the first superheater stage. to the outer edge of the centrifugal separator
The first superheater stage is located in the where it is separated from the steam. Nearly
vertical gas pass to the rear of the furnace. Satu- dried, the steam passes through corrugated
rated steam from the drum passes through the plates where, by low-velocity surface contact,
roof of the furnace, then down the walls enclos- the remaining moisture is removed by wetting
ing the rear pass to the lower ring header. From action on the plates and final screen dryers.
this point the slightly superheated steam flows The cross-sectional area of the drum limits
through the horizontal superheater tubes in a the size and arrangement of the internal steam
generally counterflow direction to the down- separators and dryers and, consequently, the ac-
ward flow of the products of combustion. From ceptable rating in terms of mass flgw per hour
the first superheater stage, the steam passes to per unit of length. A drum with a large diame-
the finishing or outlet stage which is a platen ter affords more free area for water content at
section located at the gas outlet of the furnace. norinal water level, and reduced moisture en-
The reheater is located between the finishing trainment in the larger steam space. Within the
platen superheater and the initial superheater limits of available pressure drop for steam/
stage. The flow of furnace gas over the reheater water separation, higher-capacity separators
is essentially counterflow to the flow of steam. and increased dryer surface can be provided to
The economizer is located directly below the achieve a higher rating per unit of length.
first-stage superheater. Water flows upward in For a specific diameter and arrangement of
the economizer to provide counterflou- of fur- internal components, the drum capacity is pro-
nace gas and feedwater. Outlet tubes of the portional to length. The diameter and length,
economizer section extend vertically upward then, are determined by
to form the supporting hanger tubes for the n unit generating capacity
horizontal superheater and the economizer. operating pressure in the drum
These tubes then connect to a header above the t h e practical considerations of the spacing
roof; connecting piping conducts the feedwa- and arrangement of connecting tubes and pip-
ter from this header to the drum. ing with respect to drum-shell ligaments
This boiler is of the balanced-draft type. Pul- the requirement to insure a uniform distribu-
verizers are pressurized by primary-air fans. tion of steam and water flow entering and leav-
Ljungstroma trisector air preheaters with verti- ing the drum
cal shafts are located at the economizer gas out- The percent of boiler-water solids that will
let. The gas ducts connecting the economizer to be carried over by moisture entrained in the
the air preheater and at the air preheater outlet steam leaving the drum is proportional to
are arranged with hoppers for ash collection as the boiler-water solids concentration and to the
well as to collect the drain-off wash water. percent moisture carried over. Moisture is
With the exception of the air preheaters, the removed sequentially by the steam separa-
entire boiler is supported from steel located at tors, followed by gravitational separation of
the roof elevation. Expansion joists are pro- droplets in the steam space, and finally by the
vided in the gas duct below the economizer and steam dryers, arranged to prevent moisture
in the air ducts between the air preheaters and reentrainment.
the windboxes to accommodate the downward A high water level in the drum reduces the
expansion of the boiler pressure parts in their steam space available for gravitational separa-
heated condition. tion of moisture. An excessively high level can
COMBUSPION
Central-StationSteam Generators

Superheater Connecting Tubes

Secondary Separator

Continuous Blowdown Piplng


Downtake Nozzle

Fig. 7 Steam-drum internals for C-E thermal-circulation radiant and reheat steam generators

impair efficiency of primary and secondary


separators, resulting in an increased moisture
content entering the dryers and a correspond-
ing increase in carryover~moisturein which C-E's first Controlled Circulation boiler in an
there are entrained solids. American central station went into service in
The dissolved solids in the boiler water 1942 at the Somerset Station of Montaup Elec-
should be held as low as practicable, consistent tric Company. Since then, the Controlled Circu-
with the recommended chemical treatment for lation principle has been widely accepted for
boiler-tube corrosion protection. This assures boilers ranging from waste heat, marine, and
that solids carryover during high water-level industrial units up to the largest central station
excursions will be negligible (see Chapter 20). installations. The reliability and safe operating
Vaporous carryover of certain boiler water records of Controlled Circulation boilers have
constituents, such as silica and sodium, is de- justified their selection in power stations
termined by the respective volatility of these throughout the world.
unwanted coilstituents, or their solubility in
THE CONTROLLED CIRCULATION SYSTEM
steam, as discussed in Chapter 5. They must be
controlled by limiting thi boiler-water solids Water flow through the economizer is gener-
concentration at high drum pressures. (See ally the same with either a thermal-circulation
Chapter 20). or a controlled recirculation boiler. Water from
COMBusrrON
Central-Station Steam Generators

the economizer enters the drum, is mixed with the available pump head permits more efficient
the water discharged from the steam-water sep- use of the centrifugal devices. One distinct ad-
arators, and is directed to the large downcomers vantage of the Controlled Circulation design is
which are evenly spaced along the drum. From the internal shrouding of the drum. This water-
this point on, a C-E Controlled Circulation unit tight shrouding directs the flow of steam and
(Fig. 1)differs from a thermal-circulation boiler water returning from the furnace around the
in five respects: inside surface of the drum, providing uni-
I. Circulating pumps are placed in the down- form heating. This uniform heating effectively
take circuit to provide sufficient head to insure eliminates thermal stresses from temperature
adequate, positive upward circulation under all differences through the thick wall of the drum,
operating conditions. between the submerged and unsubmerged por-
2 . Orifices are installed in the inlets of water- tion of the shell, and from end to end. This fa-
wall circuits to assist i n obtaining a predeter- cilitates rapid start-ups, shutdowns, and cyclic
. mined, proportioned flow of water to tubes of operation.
varying length and heat absorption. In operation, a Controlled Circulation boiler
3. Furnace-wall tubing is of smaller diameter has positive circulation established before any
and has lower metal temperatures than that for heat is introduced into the furnace, which then
thermal circulation, all made possible by the permits rapid start-up with virtually no time
head available from the pumps. restrictions because of circulation i n the
4. The drums are internally shrouded to pro- pressure-part system.
vide uniform heating and cooling of the drum
shell, for maximum maneuverability during CONTROLLED CIRCULATION
PUMP AND PIPING SYSTEM
start-up, load changes, and shutdown.
5. Controlled Circulation boilers have an econ- Fig. 1 shows the overall arrangement of the
omizer recirculation line which provides a pos- boiler circulating pump and downcomer piping
itive flow from the boiler-water circulating system. Downcomers installed on the steam
pump (BWCP) discharge through the econo- drum carry the recirculated boiler water, mixed
mizer to the drum. Under start-up conditions, with the feedwater, into the circulating pumps.
with the feedwater valve closed, this feature These pumps are connected through a common
minimizes any steaming in the economizer and suction manifold that insures a flow through all
precludes the need for blowdown with its asso- the downcomers regardless of the number or lo-
ciated heat loss. cation of the circulating pumps in service. This
The boiler circulating pump suction is taken feature minimizes the water level difference
from a suction manifold, which is supplied by along the length of the steam drum and contrib-
the downtakes. From the boiler circulating utes to good performance. of the steamlwater
pumps the water discharges into the waterwall separation equipment independent of the num-
inlet ring header through the pump discharge ber of pumps in service.
lines. In the inlet header, the water passes The downcomers are straight vertical pipes
through strainers and then through orifices connecting the steam drum and the suction
feeding the furnace-wall tubes, .the extended manifold; the circulating pumps are mounted
sidewall tubes and the water-cooled element on the suction manifold. Using the boiler as
spacers. The mixture of steam and water leav- the support for the pumps is a feature that
ing the evaporative circuits is discharged into eliminates any need for external supports and
the upper drum, in which the steam is sepa- prevents undue stresses which might affect
rated from the water. pump alignment.
In the drum of a Controlled Circulation unit, The head developed by the circulating
Fig. 8, the basic separation process is similar to pumps is only that required to supplement the
that of thermal-circulation drums except that thermal head and, for a typical Controlled Cir-
COb%BWZION
Csnbal-SbtionSfeam Generators

Fig. 8 Steam-drum internals for C-E Controlled CirculationBsteam generators

culation boiler is 25 psi (175 kPa) or less; for the orifices at the entrance to the, generating
this, a single-stage impeller is adequate. Boiler circuits. The strainers are particularly valu-
water circulating pumps and their design are able during the initial start-up of a new unit
described further in Chapter 14. because, during this period of operation, for-
eign material is brought into the boiler from
ORIFICES FOR
FURNACE-WALL TUBES
preboiler-cycle feedwater piping and aux-
iliary equipment.
The orifices used for optimizing flow distri-
bution to the furnace-wall tubes are shop-fitted DESIGN OF A CONTROLLED CIRCULATION
to adapters welded to the internal header wall. FURNACE-WALL SYSTEM
A keying arrangement insures that each orifice The orificing and selection of pump head for
is installed in its proper tube circuit once the a Controlled Circulation boiler are best under-
correctness of the initial installation of the ori- stood by first reviewing a non-pump-assisted
fice mount adapter has been established. Ori- thermal circulation unit design.
fice size varies for different circuits or groups of The designer of a thermal circulation furnace
circuits, depending on their length, arrange- of a given plan area determines the total num-
ment, and heat absorption. ber of parallel vertical tubes making up the
Strainers or screens between ihe circulating outer walls of the furnace; a common selection
pump discharge and the orifices prevent large is to use 2%-inch OD tubes on %inch centers.
particles of foreign material from plugging The next step, based on experience with units
COMBUSPlON
Central-Statlon Steam Generators

of similar physical size and heat duty, is to es- 8 amount of tubing "shaded" from heat
tablish the size and number of unheated down- 8 location relative to feeder tubes - -
comers from the steam drum to the lower 8 orifices (if used)
waterwall-header system. Along with this, it is
Tube A, for instimince, may be longer, but have
necessary to establish the arrangement, diame-
a lower overall heat absorption than the "aver-
ter and number of relief tubes connecting the
age" tube B; without orificing, it will have a
upper waterwall headers to the drum. An aver-
lower flow than B. Tube C, if shorter than B but
age overall percent steam leaving the furnace is
fully exposed for its entire length to a high heat,
then calculated, based on the heat absorbed by
will have a higher flow than the average tube
the "average" furnace tube and on the flow (B). But all tubes must have the same differen-
resistances in that tube, the downcomers, the
tial pressure from header to header.
relief tubes, the drum internals, and all associ-
An equilibrium condition will always result
ated entrance and exit losses.
in the flow-plus-orifice losses being additive to
Within the limits of available thermal head
the weight of the saturated mixture in each
and physical space, adjustments in downcomer
tube, at any given moment. This is because the
and relief-tube size and flow resistances can be
header-to-header differential is comprised of
made at this time to increase or decrease the av-
8 the weight of the steamlwater mixture in each
erage circulation to achieve satisfactory cool-
ing of the furnace-wall. tube
Tubes in the furnace enclosure have different 8 the pressure drop due to the resistance to flow
lengths, dissimilar configurations, and receive of the steamlwater mixture in each tube
varying amounts of heat. Any tube absorbing 8 orifice pressure drop (if any).
more heat than the average tube has a higher The flow may or may not be enough to cool
circulating water flow, but probably also ahigh the tube properly and it may even reverse (from
percent steam leaving; typically, a 50-percent upward to downward, and vice versa) from
increase in absorption above the average, time to time, dependent upon the variables act-
equally received throughout the length of a ing on it.
tube, produces a 10 to 20 percent increase in
water flow entering. For every tube receiving
more than the average tube, there is another
tube receiving less water. Each tube must be
analyzed on the basis of its individual heat ab-
c Upper
) Header
sorption to arrive at its own mass percerltage of
steam (quality) leaving.
Realize that, in designing a waterwall
-section-a group of parallel tubes having a "Average"
common (bottom) inlet header and a common
upper (outlet) header, Fig.9-the pressure drop
or head loss between the headers has to be iden-
tical for every tube. This situation exists irre-
spective of any pump assistance. Flow in each
tube, and percent steam in the mixture leaving,
differ depending upon
8 heat absorption (overall and local) c > Lower
Header
8 effective inside diameter of tubing (as af-
I I
fected by manufacturing tolerances) Fig. 9 Schematic of furnace-wall section; head
8 effective tube length (accounting for bends) loss between headers is identical for each tube
COMBrnON
CemhStation Steam Generators

For unorificed parallel tubes, the flow-rela-


ted pressure drop equality can be expressed
approximately as
f LAmA2VA = f LBmB?VB = fLcmc2Vc
where f is a common friction factor, mAVis mass 3
flow in the Nth tube, L,is the effective length of
any tube, and VNisthe average specific volume
of the steam-water mixture in the Nth tube.
5 Thermal Circulation
In tubes where mass flow is lower because of
lower heat absorption, the specific volume is 9
correspondingly higher to compensate for the 100
flow resistance of a high-absorption tube with Heat Absorption,OIO
higher mass flaw. For any given overall steam
content, water between lower and upper head- S Flow in Least
ers redistributes from tube to tube according to 5
.-
Favorable Tube
the above relationships. $ --- - -- -------
Fig. 10 gives a comparison between thermal-
circulation and Controlled Circulation perform-
,
5 100-
V)

ance. In the upper curve, average mass flow in 5a


furnace-wall tubes is shown as a function of de- Thermal Circulation
sign heat absorption. Note that the circulating
pumps move the maximum mass of water be- s 100
fore firing commences, because the water is
Heat Absorption,OO
I
, most dense at that time. The lower curve shows
that the designer of a Controlled Circulation
unit can preferentially increase the flow in Fig. 10 Comparison of fumacemwall performance -
thermal circulation versus Controlled Circulatione
tubes with less favorable configurations to pro-
vide more cooling at all loads.
The orifice pressure drop designed into Con- CONTROLLED CIRCULATION
STEAM GENERATORS
trolled Circulation circuits is additive to the
heated-circuit resistance loss and static head. Fig. 11shows a Controlled Circulation reheat
Orificing individual tubes or groups of tubes boiler designed to provide steam to a large
provides either adequate mass flow or a desired high-subcritical-pressure turbine generator.
exit quality unde: a wide range of postulated This is a single open-furnace unit. It has a
operating conditions. superheater with both pendant and horizontal
The orifice pressure drop has a dampening surfaces and a reheater.with both radiant wall
effect on the almost random behavior of a and pendant surfaces.
purely thermal-circulation unit. Because the This boiler has superheater outlet conditions
orifice drop occurs at the beginning of a circuit, of 2620 psig and 1005OF (18.1 MPa gage and
before heat has been added in the furnace, the 541C), with single reheat to 1005OF (541C).
principal variable is mass flow through the It is designed to burn high-volatile bitumi-
opening, with no effect of differential specific nous coal and is of the balanced-draft type,
volume. This is a very significant difference be- with forced- and induced-draft and primary-
tween pure forced circulation, in which most air fans.
of the pressure drop is in the heated tube cir- Six C-E pulverizers supply coal to tangential
cuits themselves, and C-E's selectively orificed fuel nozzles located in the four corners of the
pump-assisted controlled circulation. furnace. The supply of water to the waterwalls
COMBrnON
CentraIStattonSteam Generators

--

- -

A .
Structural Steel Framing

Furnace Steam-Cooled Roo ressure-Part Support Steel

Furnace Rear Wall

Economizer Inlet

Windbox

Induced-Drafl Fans

Lower Waterwall Ring Header


" \ 'Bottom-Ash

Primary Air Ducts to Pulverizers


Hopper
I ' Forced Draft Fans

,Primary Air Fans

Fig. 77 Large C-EControlled Circulation@tangentially pulverized-coal-fired reheat steam generator


COMnUsTION
CmtmISWion Steam Generators

begins with the steam drum. The water travels choice of electric-power generators throighout
down through the downcomers to the suction the world.
manifold and into the circulating pumps from Some of the advantages of Controlled Circula-
which it is discharged to the lower ring header tion systems are covered in Chapter 5; however, a
which has flow-distributing orifices. The mix- primaryreason for selecting a steam generator of
ture of steam and water that flows up through the Controlled Circulation type is its character-
the various heated circuits is collected in an ar- istic of high dynamic maneuverability. The fact
rangement of waterwall outlet headers located that furnace-wall flow is positively established,
just above the furnace roof. The steam-water in an upward direction, before heat is applied,
mixture passes through connecting tubes to the enables an operator to fire such a furnace at any
drum, where steam is separated from boiler rate desired-that is, Controlled Circulation
water and passes on to the superheater. furnace walls and steam drums are never a lim-
The first-stage superheater is located in the iting factor in building or changing load. Thus,
vertical pass at the rear of the furnace. Saturated Controlled Circulation units are inherently bet-
steam from the dmm passes through the fur- ter suited to operate under cycling conditions
. nace radiant roof, backpass roof and walls, and (particularly those demanded by two-shift op-
then enters the lower inlet header of the first eration) than other boiler types. This important
stage. The steam flows upward through the aspect of the design is covered in depth in
first-stage superheater and into the second the subsection Design Features for Variable
stage, comprised of pendant double-loop pan- Load Operation of large steam generators later
els located at the top of the furnace. The final in this chapter.
superheater is of the vertical pendant-platen
OPTIMUM CHEMICAL CLEANING
type, and is also in the upper furnace, between
the panels and the furnace nose. Circulating pumps on a boiler facilitate both
Reheat steam enters the reheater radiant-wall ' pre-operational cleaning and operational scale
inlet header and travels upward through the ra- removal. Laboratory testing with circulation at
diant wall tubes. After leaving the radiant-wall velocities of 0.5 to 1.0 ftlsec (0.15 to 0.30 m/s)
outlet header, the reheat steam enters the low- or greater has indicated that complete scale re-
temperature rear pendant, and continues into moval can be accomplished in 10 to 20 minutes
the finishing reheat pendant. following initial solvent contact. A significant
The horizontal bare-tube economizer is lo- reduction from the usual 4- to 6-hour hydro-
cated directly below the first-stage superheater. chloric-acid contact period can be obtained in
Vertical outlet tubes from the economizer senre pumped-circulation boilers where desired ve-
to support both the economizer banks and first- locity conditions and uniform cleaning are as-
stage superheater. The tubes then terminate in sured in all tube circuits.
an economizer outlet header above the roof In a thermal-circulation boiler, solvent inter-
from which connecting piping transports the change or mixing from section to section is
water to the drum. slow or does not occur, and significantly differ-
Two vertical-shaft regenerative type (Ljung- ent levels of ion concentration can be noted in
stromm) trisector air preheaters are located be- samples taken from various locations in a unit.
neath the economizer. A reasonably complete picture of what is
occurring in such a unit can be obtained by
ADVANTAGES OF A multipoint sampling. Although multisam-
CONTROLLED CIRCULATION SYSTEM ple monitoring is important during pre-
The C-E proprietary design of subcritical operational cleaning to establish local ion
pump-assisted recirculation boiler, with the equilibrium, it is of even greater- interest
registered Controlled Circulation trademark has in operational scale removal to guard against
many features that have made it a preferred solvent depletion or hide-out in local areas. In
COMBUSPION
Central-Station Steam Generators

units where positive recirculation can be tubing than thermal circulation boilers, and in-
maintained, uniform solvent concentration is corporate orifices at the entrance to the tubes
rapidly established in all portions of a unit, for optimum flow distribution. The two act to
and one sample point will give an indication control and reduce the amount of water that can
of conditions throughout the unit. pass through a tube leak of a given size, result-
Under a short solvent-contact procedure that ing in a significantly lower damage potential to
is used with Controlled Circulation boilers, adjacent tubes than in a thermal unit.
then, the solvent contact time is no longer than There are many recorded instances in which
30 minutes; with positive circulation, rapid an operator has kept a Controlled Circulation
and complete cleaning is assured with a mini- unit in service through a peak period or until a
mum exposure time of pressure parts to the weekend, when it became convenient to shut
cleaning solvent. This also minimizes boiler down. An additional capability, that of forced
downtime and, utilizing the rapid shutdown furnace-wall cooling with the pumps, allows
and start-up capabilities of such boilers, it boiler cooldown with uniform stresses without
makes it possible to complete the entire proce- using the feedwater pump or'dumping feed-
dure during a weekend outage. water to the condenser.
DETECTING DETERIORATION OF FEEDWATER QUALITY OPERATING-PRESSUREFLEXIBILITY

Carryover of metallic oxides and other im- The curve in Fig. 12 shows that a Controlled
purities from the preboiler system may cause Circulation steam generator can be oper-
deposits o n heated water circuits of any ated through a wide range of pressure at full
boiler. In severe cases such deposits can lead to load. Operation within the permissible area
tube failures. allows great latitude in establishing a desirable
The Controlled Circulation boiler offers an sliding-pressure pattern.
advantage for detecting deposits without re-
moving the unit from service, by observing the WATER-TREATMENT CONSIDERATIONS
circulating-pump differential pressure between In comparison to once-through boilers, Con-
the pump suction manifold and either the dis- trolled Circulation boilers have numerous ad-
charge manifold or the waterwall lower header.
Observation of the differential pressure pro-
vides a convenient external means of detecting
internal waterwall system deposits and antici- X
pating more serious operation difficulties.
The actual differential across the pump at
normal full-load operation is established dur-
ing initial operation, when the boiler is free of
deposits. The differential pressure is then
checked periodically during full-load opera-
tion. If a substantial difference is seen be-
tween the baseline and later data, the boiler
load may be reduced until an outage presents
the opportunity to inspect and clean internal
surfaces of water circuits, as described in
Chapters 20 and 21. Pressure in Steam Drum, Psig

OPERATION WITH WATERWALL TUBE LEAKS


Fig. 12 Maximum permissible capacity as a
Because of the available pump head, Con- function of operating pressure in drum, for C-E
trolled Circulation units use smaller diameter Controlled Circulation@boilers
COMBmnON
CentnI-SfationSteam Genentors

vantages in water treatment: group of tubes. Flow reversal can occur, with
Drum boilers can remain "on line" during a local overheating a possibility.
condenser leak because the drum gives added Controlled Circulation and thermal-circula-
protection. In the event of a condenser leak tion boilers have the same thermal circulating
(greater than 0.5 ppm solids in the hot well), head available if they have the same furnace
desuperheating must be discontinued and height, the same economizer water-leaving
steam temperature limited by lowering fuel- temperature, and the same circulation ratio
nozzle tilt or possibly a drop in load. Under (Fig. 5). The pumps and orifices incorporated
similar hot-well conditions, a once-through in Controlled Circulation units do not destroy the
unit must be shut down. (See Chapter 20.) available thermal head or lessen the density dif-
During normal operation, polishers may leak ference between furnace-wall tubes and un-
small amounts of solids, which may be basic or heated downcomers.
acidic. In a once-through unit, these solids will 8 To assure that there is adequate available head
continue to the turbine unchanged. There have under all operations of firing and maneuver-
been cases of turbine corrosion damage from ing the boiler, C-E adds orifices so that all tubes
these.solids which are concentrated by the tur- will receive water under all conditions and
bine. In a drum boiler, chemical treatment of shrouds the thick-walled steam drum to cool it
the boiler water renders these solids harmless. or heat it in a controlled manner under all rates
Base-loaded drum boilers are not as restricted of load change. The circulating pumps comple-
on start-up as once-through units in regard to ment these engineered modifications to the
feedwater quality. Once-through units should basic thermal-circulation design, and provide
have a cleanup loop associated with the polish- the pressure head to overcome the incremen-
ers to remove iron oxide and reduce silica in tally increased resistance. A most important
feedwater before start-up. Base-loaded drum point is that flow increases are created with
'
boilers do not require this loop. pump assistance that are much greater than
those available through the thermosyphonic
THERMAL CIRCULATION phenomenon. This point is illustrated (Fig. 13)
VERSUS CONTROLLED CIRCULATION by comparing the pressure drops in the various
In choosing between thermally induced cir- components of typical thermal-cil.culation and
culation and a Controlled Circulation system Controlled Circulation steam generators.
the following must be taken into account: The net power consumption of the circulating
Although thermal circulation does in fact in- pumps is small compared to that in other cir-
crease in response to heat applied, the increase cuitry of the boiler for accomplishing basically
in flow is not directly proportional to the in- the same objective of equalized flow distribu-
crease in heat flux. That is, although there is tion with variation in load, firing conditions,
usually a larger amount of water circulated in and heat-absorption patterns. The feedwater-
an individual tube when more heat is applied, pump power charged to a unit, because of its
the increase may not be completely adequate to superheater and economizer pressure drops, is
provide proper tube protection. substantially higher than the small power loss
Slag can form heavily, and does form unpre- of the circulating pumps.
dictably, on different areas of the furnace at dif-
ferent times; it can be removed by sootblowers,
or shed because of its mass, equally unpredict- SUPERCRITICAL-PRESSURE
ably. It is common to have a major part of the
heat input to a furnace-wall tube in ifs upper
STEAM GENERATORS
half, because of sootblower cleaning or shed- C-E supercritical steam generators can be
ding, which can result in a calculable decrease classified in three basic design categories ac-
in circulation rate in an individual tube or a cording to their operating-pressure regimes.
COMBVSnON
Central-StationSteam Generators

'
In the first, for units designed for constant- to operate central-station steam generators at
pressure operation, supercritical pressures are both high subcritical pressures- and in the
maintained in both furnace walls and super- supercritical-pressure range. A later section
heater over the normal operating range. The of this chapter addresses the subject of slid-
furnace-wall arrangement and the use of boiler ing (or "variableu)-pressure operation in de-
throttling valves are as described under C-E tail, and covers the significant advantages to
Combined Circulation@units. the steam generator and turbine while operat-
For units that are to have partial sliding- ing in such a mode.
pressure capability, supercritical pressures The three C-E steam-generator designs to
are maintained in the furnace walls; only meet user requirements for throttle pressures
the superheater follows a sliding-pressure above the 3800 psig (26 MPa gage) level are de-
program. The boiler throttling valve arrange- scribed in the following sections.
ment is modified from the basic Combined
Circulation design to allow for increased throt- CONSTANT-PRESSURE
SUPERCRITICAL-PRESSURE UNITS
tling. For units designed for full sliding pres-
sure, t h e furnace-wall a n d superheater The C-E Combined Circulation? system is a
pressures may vary with load, including opera- once-through steam generator with a superim-
tion at subcritical pressure. posed controlled forced recirculation system for
Sliding pressure is a highly desirable way the furnace walls. The furnace-wall system is

Drum lnternals
Riser (Relief)Tubes

-------
Drum lnternals
Heated Furnace-Wall
Tubes, Incl. Orifices

Heated ~urnacekall

Thermal Controlled .
Circulation Boiler Circulat~onBoiler

Fig. 13 Comparison of component pressure drops and available static head - thermal-circulationboiler versus
Controlled Circulation@boiler
C0MBnSn:ON .-
.
CantmIStationSteam Generators

automatically protected by recirculation of sure (3208 psia or 22.1 MPa abs.) to avoid the
fluid with a boiler circulating pump when film boiling and tube overheating which can
once-through flow is insufficient at low loads. occur at the transition to subcritical pressure.
The recirculation pump eliminates the need for Boiler throttling valves are used at the furnace-
a high-capacity bypass system for furnace-wall wall outlet to keep the wall system pressurized
protection, while still allowing once-through (Fig. 14). The superheater operates in the slid-
supercritical flow at higher output. This type of ing-pressure mode below approximately 30-
design permits furnace-wall tubes of sufficient percent load. Above that range, turbine load
inside diameter to maintain an adequate mass control is accomplished by using the turbine
flow through the tubes at all operating condi- throttle valves.
tions. The recirculating pump handles both re-
SYSTEM INTEGRATION
circulated flow and feedwater flow and thereby
assists the feedpump, reducing some of its The simplified flow diagram (Fig. 15) illus-
power requirement. trates several features that have significantly ad-
In the Combined Circulation design, all fur- vanced system integration.
nace walls are single-pass upflow, with no mix- First, the supercritical once-through steam
ing headers. Proper design tolerances and the generator closes the steam and feedwater con-
use of tube orifices compensate for flow unbal- nections of the steam-power cycle in a continu-
ance or uneven heat absorption. The mixing ous heat-addition loop without the division
vessel or sphere is substituted for the conven- established by the water level in the drum of
tional drum to properly mix the recirculated subcritical recirculating units. This fact is rec-
flow from the furnace walls with the unit ognized by an automatic, non-interacting, feed-
throughput. forward control system, geared to the dynamic
The constant-pressure Combined Circulation characteristics of the entire plant.
supercritical units, then, are capable of operat- Second, system integration permits starting
ing with once-through flow, but cannot be oper- the turbine and steam generator simultaneously
ated with full sliding pressure. The furnace under conditions that provide an optimum of
walls must be kept above the supercritical pres- turbine protection for accelerated cold and hot

BT Valves -Turbine
I I
Throttle Valves-=

urnace-Wall Outlet Pressure

.4? 3000 -
8
8 Throttle
Ej
8 Pressure S H Inlet Pressure
2 2000 -
'4 (BT Valve Outlet)
V)
P!
a
-
1000 -

I I 1
25 50 75 100
Synchronization Steam Flow, % MCR
1
Fig. 14 Constant-pressure program for C-E Combined Circulationmsteam generators
COMBUSIlON
Central-Station Steam Generators

starts. This facility is combined with unique generator through the feedwater valve (FW).
features to remove solids and-oxides from both From the economizer the feedwater passes
preboiler and boiler systems. through the recirculating pump and its associ-
Third, the. Combined Circulation principle ated isolating -mlves to the furnace, where it
eliminates the basic requirement of other once- flows in series through the centerwall and the
through systems for minimum feedwater flow outerwalls, then through the enclosure walls of
through the furnace. Heat removed from the the rear gas pass. At this point the steam passes
steam-generating system during any operation through a system of throttling valves (BTB and
is determined only by functions other than BT) and continues through four sections of hor-
furnace-wall protection. The feedwater heating izontal and pendant superheater before reach-
system, therefore, need not be used to reduce ing the steam leads to the turbine through an
start-up heat losses. This in turn avoids con- outlet piping system. Steam is returned to the
tamination of this system by start-up flow and steam generator for reheating in a two-section
makes the system very simple. Eliminating the reheater, then returned to the turbine. The con-
minimum flow requirement also greatly facili- densate passes through a demineralizer and a
tates use of the turbine-driven feedpumps for series of low-pressure heaters to an open deaer-
start-up and avoids complications from sepa- ator. The turbine-driven feedpump then returns
rate start-up pumps. the feedwater through a string of high-pressure
heaters to the feedwater valve.
BOILER-TURBINE SYSTEM
The diagram also shows the main compo-
In Fig. 15, the feedwater enters the steam nents of a simple start-up system within which

Fig. 15 Simplified flow diagram of C-E Combined Circulation@steam generator


COb5USlTON
ContnlSiaNon Steam Genentors

the throttling valves (BT and BTB) belong. COMBINED CIRCULATION RECIRCULATING SYSTEM
Upstream of these valves, piping connects The components of the Combined Circula-
the furnace-wall system with the extraction tion recirculating system are shown in a sim-
valves (BE) and the start-up separator. The plified isometric view i n Fig. 16. Mixing
steam side of the separator is connected to the feedwater flow with recirculated flow (as takes
superheater system through a steam admission place in the drum of a subcritical unit) occurs
valve (SA)and to the condenser through a spill- here in the spherical mixing vessel. A single
over valve (SP). Water from the separator is dis- downcomer brings the fluid to the two recircu-
- charged to the condenser through the water lating pumps which hang from a sjmrnetrical
drain valve (WD). The steam drain valve [SD), tee connection on the downcomer. Only one
close to the turbine valve chest, discharges the pump is needed for low-load operation, the
steam for superheater cooling and heating of other being a spare on hot standby. Neither is
steam leads to the condenser and an injection required at high loads. The pumps discharge to
valve (IC) regulates desuperheating water flow a common header from which supply piping
for condenser protection. runs directly to the furnace-wall headers.
Auxiliary superheated steam is furnished to The subcritical-pressure drum (which func-
turbine seals, the deaerator, and the main feed- tions to separate steam and water) is eliminated
pump turbine from separate start-up boilers. at supercritical pressure. The recirculated flow

Economizer Outlet Headers

Roof Mixing Header

Economizer Outlet Link

Mixing Chamber

Downcomer to Circulating Pumps

Circulating Pumps

I J
Fig. 16 Flow diagram of furnace-wall and startup system for Combined Circulation@centerwall unit
COMBUSTION
CentralStation Steam Generators

is returned from the outlet of the furnace-wall With single-pass flow, all tubes in a welded
enclosure to the mixing vessel through a single panel have the same inlet temperature.
recirculating line. A stop-check valve in this Centerwall flow and outerwall flow are in
line automatically prevents bypassing the series on divided-furnace units. - -
furnace-wall system when recirculation has
ceased at the upper load range. Because down- All components of the recirculating system
comer, pumps, and piping to the center-wall all except the recirculating line are in series with
handle mixed or through flow at low tempera- the once-through flow.
tures, they are fabricated of carbon steel. The All walls are formed by drainable, welded-
recirculating line and the mixing vessel use tube panels.
chrome-alloy material.
From the furnace-wall outlet headers, the These characteristics provide a number of
fluid is piped to the backpass, where it cools important advantages, among which is the de-
the walls. From the backpass outlet header, the sign flexibility available from the presence of a
total boiler through-flow goes through the BT circulating pump with which the flow quantity
and BTB valve complex to the superheater. Dur- through the parallel tubes around the furnace
ing waterwall recirculation conditions, a por- periphery can be distributed. Other benefits are
tion of flow in excess of the steam generator improved temperature performance over the en-
through-flow is recirculated back to the mixing tire load range and the elimination of the bypass
chamber-this flow is extracted ahead of the system as a requirement of the furnace wall.
BTtBTB valve complex. These advantages will be most clearly under-
stood after considering the flow performance of
TYPICAL COMBINED CIRCULATION UNIT
a typical furnace-wall system, with the volu-
The most common type of supercritical metric flow at the furnace-wall inlet a function
steam generator in operation in the United' of load (Fig. 18). The through-flow as main-
States is the C-E Combined Circulation design. tained by the feedpump increases in direct pro-
About 75 percent of the operating units are in portion to load. The recirculated flow as
the 600 to 900 MW size range, most having sin- maintained by the circulating pumps supple-
gle reheat to 1005O (541C).A Combined Circu- ments the through-flow over the low load range
lation unit in this size range is shown in Fig. in a manner which protects the furnace walls by
17. It is designed for balanced-draft firing of raising the actual flow to a safe level regardless
sub-bituminous A coal, and has superheater of feedwater flow.
outlet conditions of 3590 psig and 1005F At low loads the recirculated flow is high, but
(24.8 MPa gage and 541"C). The reheated steam decreases as the load increases. At about 60-
has an outlet temperature of 1005F from inlet percent load, the pressure drop through the
conditions of 583F and 676 psig (306C and furnace-wall system equals the head produced
4.7 MPa gage). by the circulating pump; the stop-check valve
Seven C-E pressurized pulverizers supply in the recirculating line automatically closes.
coal to the seven elevations of fuel nozzles; The circulating pump then ceases to add to the
two centrifugal fans furnish the primary air to quantity of furnace flow but continues to con-
the pulverizers. tribute its positive head on the once-through
flow and so acts as a booster to the feedpump.
FURNACE-WALL SYSTEM
At this time, the pump may be shut down.
The arrangement of the Combined Cir-
Combined Circulation Performance
culation furnace-wall system has several
characteristics: Fluid temperatures, both primary and reheat,
Flow in all furnace and backpass enclosure throughout a typical Combined Circulation
walls is in the upward direction only. supercritical steam generator at maximum con-
--
COMBvsrrON .u

Ce~~tml-Staion
Steam Generaion

I
Fig. 77 C-E combined-circulation@tangentially coal-fired reheat steam generator
COMBUSIlON
Central-Station Steam Generators

tinuous load are plotted against the percentage


of heat absorption in Fig. 19.
The primary fluid takes about 83 percent of
total output, showing a gradual and continuous
rise of fluid temperature from the feedwater in- 60-
let to the superheater outlet. The curve of these
temperatures follows the characteristic line of
Once-Through
supercritical fluid in which any heat absorption Flow
or change of heat content is accompanied by a 5 20- /
>
change in fluid temperature.
Desuperheating occurring at the outlet of the 20 ;o ioLoad,
;o do ;o ;o slo 160
panel superheater provides vernier control of OO
/

average steam temperature. It also adjusts for un-


Fig. 18 Flow in typical Combined Circulation@
balance of pickup across the width of the unit, fumace-wall system
as four individually temperature-controlled
sections are installed in each furnace. The pla-
ten and finishing superheater sections add the the turbine and is a factor in establishing per-
balance of superheat. missible load-change rates. This design is
extremely well suited for base-load operation.
PARTIAL SLIDING-PRESSURE DESIGN
However, cycling and two-shifting units may
Combined Circulation supercritical designs require greater flexibility at reduced unit load
with boiler throttle valves (to keep the furnace- to protect the steam generator and turbine
wall system pressurized above, say, 3500 psig during the increased number of load swings.
or 24 MPa gage) can operate in the sliding- Fig. 20 shows the re-arrangement of a con-
pressure mode only below approximately stant-pressure boiler-throttle-valve set to obtain
30-percent rating (Fig. 14). Above this point, sliding-pressure turbine operation to 80-per-
turbine load control is achieved through the cent rating while maintaining the furnace walls
steam-turbine throttle valves. This causes the at supercritical pressure. This design has the
usual temperature changes in the first stage of usual advantages of operation of the turbine in

1000-

900 - Horizontal S H
LL Initial

2
P)

I I I I
I I I I I I I I I
1 I I I 1 I I I l l I I
0 10 20 30 40 50 60 70 80 90 100
Heat Absorption,OO/

Fig. 19 Fluid temperatures through Combined Circulation@steam generator at full load


--
kB
-T Valves Turbine
BEValve - BTB? Throttle Valves
4000 - Valves

-p 3000 - Furnace-Wall /
B
i
:2000 -
rn
SH Inlet Press (BT Valve Outlet)
2
a
1000 -
-.-
I I
Oo5 " 50 75 100
Synchronization Steam Flow, O/O MCR

Fig. 20 Sliding pressure operation oi C-E Combined Circulation@steam generators

a s1iding:pressure mode, including increased full-arc admission below 80-percent load.


reheat-temperature control range, reduced ther- Note that the boiler feed-pump power is the
mal stresses, and improved turbine heat rates as same for this modified design as for constant-
a result of variable-pressure operation with pressure operation. However, with the use of
boiler throttle valves at all loads below 80-per-
cent, some increased wear and maintenance of
Supercritical- them can be expected. This design, then, is of-
4000 - ten well-suited as a field modification to exist-
ing Combined Circulation units which are now
required to cycle, or for new units which will
cycle a minimal number of times during their
operating lives.
FULL SLIDING-PRESSURE DESIGN
The third once-through design eliminates
the boiler throttling valves and adopts a full
sliding-pressure approach (Fig. 2 1). The fur-
nace walls are allowed to enter the subcritical
pressure range along with the superheater cir-
cuits, over the entire load range as shown.
Benefits to plant operation, in addition to
1000 - those described above, include:
<
1) Reduced pressure levels at lower loads un-
load all cycle components pressure-wise,
from the feedwater pump to the HP turbine,
Boiler Load, OO/ MCR -- I thereby prolonging life span.
Fig. 21 Pressure versus load for full sliding- 2) Improved overall power plant heat rates
pressure supercritical design when considering power consumption of
COMBrnON
Central-StationSteam Generators

the boiler feed pump and other auxiliaries. performance, and cost advantages to each
3) Simplified and faster start-up procedures which must be considered in selecting one or the
may be employed in the design. other for any given application.
The superheater circuitry for the full sliding-
pressure design, as well as the start-up system, VERTICAL VERSUS SPIRAL OR HELICAL
FURNACE WALLS
the operational controls, and the auxiliary
equipment, are essentially the same as for The principal concern with a sliding-pressure
the constant-pressure and modified constant- supercritical-pressure design is the require-
pressure designs. ment for once-through operation. The mass
For start-up and low-load operation below 30 flow in the furnace-wall tubes must be suffi-
to 35 percent, the unit utilizes a pumped recir- ciently high to avoid overheating or departure
culation system (similar to the Combined Circu- from nucleate boiling (DNB) while generating
lation unit) to provide an adequate mass flow steam at subcritical pressures, and to avoid ex-
through the-furnace walls and the economizer. cessive metal temperatures and uneven steam
This mass flow is required to provide satisfac- outlet temperatures when operating at super-
tory cooling of the furnace-wall tubes and to critical pressure at higher boiler loads.
avoid circuit stability problems. It also avoids To accomplish these objectives, the spiral-
flashing and steaming in the economizer. The wall design is used for smaller size units. The
basic advantage of a pumped recirculation sys- principle of the spiral- or helical-wall furnace
tem is that no heat is rejected in the recirculated is to increase the mass flow per tube by reduc-
water, but is all returned to the system. ing the number of tubes needed to envelop the
Fig. 22 shows a side elevation of the C-E super- furnace without increasing the spacing be-
critical steam-generating unit for full sliding- tween the tubes. This is done by arranging the
pressure operation. tubes at an angle and spiralling them around ,
The unit has the following features: the furnace. For instance, the number of tubes
An integral water separator is placed between required to cover the furnace wall can be re-
the furnace-wall outlet and the superheater in- duced to one half by putting the tubes at a 30-
let. During start-up and low load, the separator degree angle (Fig. 24). Note that the centerline
operates with a water level, or wet. Under these spacing or pitch (P) is made the same as on a
conditions, the excess water from the furnace vertical wall to prevent fin overheating. Addi-
walls is recirculated through the furnace walls tionally, by spiralling around the furnace, every
and the economizer. tube is part of all the walls, which means that
In the once-through mode of operation, the each tube acts as a heat integrator around the
water separator is dry and serves as a junction four walls of the combustion chamber (Fig. 23).
header between the furnace walls and the The spiral-wall concept thus addresses two
superheater. The principal advantage of this ar- major challenges of the full-sliding-pressure
rangement is that the water separator remains supercritical-pressure boiler: '
in the circuit at all times, thereby eliminating 8 Achieving the required mass flows to avoid
the multitude of valves associated with pre- overheating and excessive metal temperatures
vious designs. by reducing the number of tube circuits
The furnace-wall configuration of a full Minimizing differences in tube-to-tube heat
sliding-pressure supercritical steam generator absorption by exposing each tube to all four fur-
will vary depending on unit size. Two arrange- nace walls
ments are available, the vertical tube-wall and Spiral-wall furnaces have been in operation
the spiral-wound or helical-tube furnace. in Europe for many years and have given sat-
Vertical tube-walls are shown in the steam gen- isfactory performance, the majority of them
erator in Fig. 22. The spiral-wound design is being used with the 2900-psig (20 MPa gage)
shown -- conceptually in Fig. 23. There are design, turbine cycle.
COmmoN
CentraCStaUonSteam Generators

Fig. 22 C-E supercritical-pressure coal-fired steam generator for full sliding-pressure operation
COMBvmON
Central-Station Steam Generators

There is one major performance penalty with times as many tube-to-tube butt welds in the
spiral-wound furnace designs. Because of the furnace walls due to the spiralling arrange-
high mass flow, the pressure drop in the lower ment. It is customary with this design to revert
furnace walls is generally much higher than for to vertical tube construction in the upper por-
conventional supercritical or .subcritical units, tions of the furnace where the heat-absorption
which increases the boiler feed-pump power rates are lower. This requires the use of an inter-
requirements. mediate header or bifurcatedltrifurcated sec-
Because the furnace-wall tubes are at an tions of tubing, which further multiplies the
angle, the furnace-wall support system is more number of butt welds. Spiral-wall configura-
difficult to build. The load must be transmitted tions also entail difficult tube routing around
through the fins between the tubes by means of all openings for the firing equipment in the
weld attachments and tension strips; conse- lower furnace.
quently, the spiral-wound furnace is more ex- As an alternative to the spiral-wall design for
pensive to manufacture and erect than a larger-size steam generators, C-E offers a tan-
vertical-tube unit. There are typically four gentially fired unit with vertical tube walls for
ease of fabrication, erection, and maintenance.
As described in Chapters 12 and 13, a stable
fireball is formed in the center of the furnace
with tangential firing, with essentially equal
distribution of the lateral heat absorption on all
furnace walls. Unbalances are minimized and
lateral heat-absorption patterns are predictable
over the entire load range.
Rifled tubing is used in the furnace walls as
in the Controlled Circulation design, to avoid
overheating or DNB at subcritical pressures. As
mentioned earlier, C-E has characterized the
behavior of rifled tubing for this application by
testing different tube diameters and configura-
tions and subjecting full-size tubes to the heat

L I

Fig. 23 Spiral-wall furnace for supercritical


pressure Fig. 24 Basic principle of spiral-wall furnace
CO-ON
ChtraMWon Steam Generators
-
flux rates, pressures, and mass flows associated heaters. In the example shown in Fig. 25A, the
with these designs.' boiler is equipped vr-ith a heat-recovery system
The vertical-wall design has individual tube effective at start-up and inlow-load operation. In
orifices to control the heat absorption in each this load range, which is run with a minimum
circuit, in the same manner as has been used in feed rate of 30 percent, the surplus water from the
Combined Circulation units. Analyses based on separator passes through a start-up heat ex-
operating experience and design practices for changer into the feedwater tank. During pres-
Combined Circulation units have proven that sureless start-up after a longer shutdown, in
satisfactory temperature differentials through- the first phase .the separated water must be led
out the entire operating load range are achieved. into an expansion vessel until the pressure in the
Thus, the two problems-of DNB (tube over- separator reaches the level in the feedwater tank.
heating) and waterwall steam-temperature un- In the second example, Fig. 25B, a recircula-
balance-can be addressed in a vertical-wall tion system is used simultaneously as a start-up
design by employing a. tangential firing system and low-load system. The surplus water occur-
and rifled tubing. ring in the separator during start-up, due to the
difference between the minimum feed and satu-
Start-up Systems
rated steam generation or to the water swell,
Both boiler types are started up with sliding is recirculated to maintain minimum flow for
pressure and sliding temperature, and dry super- furnace-wall protection.

1 Feedwater Tank
2 Feed Pump
3 High-Pressure Preheater
4 Feedwater Control Valve
5 Economizer
8 6 Start-up Heat Exchanger
7 Circulation Pump
8 Waterwall
9 Water Separator
10 Drain System
11 Water Separator -
7 Level/Control Valve

Fig. 25 Comparative start-up systems: full sliding-pressuresupercritical-pressure units


COMBOSRON
CentraCStatlon Steam

Though the starting losses on the water side purchased new boiler additions that were the
are quite different in the two instances, they are largest and most efficient equipment available.
an order of magnitude lower than the starting These new units were base loaded for the first
losses on the steam side (which would arise several years of use. But as capital became more
from turbine bypass operation) and are the difficult to acquire and requirements for emis-
same for both examples. sion control equipment increased, this pattern
gradually changed.
HEAT RATE-THE WHY As more of the older base-loaded plants are
OF SUPERCRITICAL PRESSURE relegated to cyclic or low-load-factor opera-
In Chapters 1 and 5, we pointed out the ad- tion, it is no longer valid to assume that new,
vantages in thermodynamic cycle efficiency to large units are the most cost-effective to oper-
be gained by using high steam pressures and ate. On one hand, new units are designed with
temperatures. The data in Table I11 give some features for operating in the two-shifting and
insight into. the relative improvement of net other cycling regimes. On the other hand, they
plant heat rate with several of the available cy- may have parasitic environmental control
cles. Large incremental decreases in plant heat equipment that impacts negatively on their
rate (improved efficiency) are very difficult to overall plant efficiency. In any case, there is a
achieve. Increasing the superheat temperature need for maximum system flexibility and using
of a sub-critical unit to 1050F (565C) in lieu the older equipment for peak loads is not com-
of 1000F (540C) provides only 0.8-percent pletely reliable because there are strict limits to
improvement in the heat rate. Increasing pres- the cycling capability of any boiler not specifi-
sure to 3500 psi (24 MPa) at 1000"/1000"F, cally designed for that kind of service. This sec-
yields an improvement of 1.5 percent, and the tion discusses such design limitations.
double-reheat ramp cycle improves 4.1 percent
above 2400 psi (17 MPa) at 1000/10000F.3 DEFINITION OF CYCLING
Many factors affect plant heat rate besides the In the past, a conventional cycling unit
cycle itself, such as load regime, fuel, condenser (either an oil- or natural-gas-fired peaking unit)
temperature, and steam-generator exit-gas tem- was described as one designed for rapid rates of
perature. These and other items noted in Chap- load increase and a significantly larger number
ters 1, 5, and 6 must all be considered when of start-up and shutdown cycles compared to
selecting a pressure and temperature. conventional base load-operation.
A detailed history of the development of the Acoal-fired cycling boiler is one that can op-
once-through steam generator and large super-' erate for long periods of time at reduced ca-
critical units is given in Chapter 25 of the 1966 pacities ( G 20 percent of MCR) and reduced
edition of this text.4 pressures (such as 1000 psig) while burning
only coal. Such a unit is also capable of base-

DESIGN FEATURES
FOR VARIABLE-LOAD Table 111. Heat Rate Improvement
OPERATION -Net Plant-
As pointed out in Chapter 1and elsewhere, it 2400 PSI 3500 PSI
is extremely important for large pulverized-
Temperature, O F --BtulkWhr-
coal-fired steam-generating equipment to have . .
100o,lOOO . . . . . . . . . . . . 9,000 8,860
the capability to operate satisfactorily as the lojOlloOo . . . . . . . . . . . . . . 8,930 8,800
load varies widely. .
10001102511050 . . . . . . . . . - 8,630
Traditionally,
- electric utility companies
COMMrmON
CenWStrtlon Steam Generators

load operation for extended periods. Operation To properly consider these operational
(Fig. 26) is further defined. modes during the design stage, it is necessary
Base-load mode-The unit is entirely base to take into account the effect of this type of
loaded. boilerlturbine loading on furnace sizing, pul-
.Weekend mode-The unit is base loaded verizing and firing systems, operational con-
during weekdays and removed from service trol systems, turbine start-up systems, and

.
each weekend. In this mode. there is a cold water treatment.6
start-up at the beginning of each work week.
DESIGNING COAL-FIRED BOILERS
Cycling mode-The boiler plant operates FOR VARIABLE LOAD
weekdays at full load during the day and at
minimum load (=20 percent MCR) at night. It The performance and cost of equipment for
may be removed from service each weekend. boilers dedicated to variable-load senlice are

'.
This method of operation may also involve fast greatly influenced by the sizing of the furnace
load changes. and the selection of the pulverizers.
Two-shifting mode-The boiler plant oper-
FURNACE SIZING
ates weekdays at full load and is taken off line
every night for 8 to 10 hours. In addition, the In recent years, furnace sizing requirements
unit is removed from service each weekend. for coal-fired boilers have become very con-
After an 8- to 10-hour nonfiring period, start- servative. This trend occurred to permit fur-
ups on weekday-morning are usually cate- naces to handle the worst possible ash-content
gorized as "warm" starts. coal that might become available at a particular

Weekly Weekly
100 100

-0 -0
m m
0 0
-I -I

o O S M T W T F S
Days Days
BASE LOAD WEEKEND

100 100

P0 -0
m
0
J J

O S M T W T F S O S M T W T F S
Days Days
CYCLING TWO-SHIFTING
-

Fig. 26 Modes of variable-load operation


COMBUSI?ON
CenttaCStation Steam Generators I

site. When a conservatively designed furnace is ment, special consideration should be given to
supplied with coal that produces gas-side obtaining hot air as quickly as possible. This
conditions much cleaner than anticipated by can be done either by directly firing supple-
the design of the furnace, the result can be mental fuel into the ducts to the pulverizers or
a lower-than-design steam temperature or re- preheating the air with steam heaters.
duced temperature control range. One factor that has a definite effect on the
Additionally, several days to several weeks start-up characteristics of the boiler is the
normally are required to "season" the furnace purge airflow requirements. Although purge
of a coal-fired unit so that the unit can produce airflow is essential, it acts to cool furnace walls
design outlet steam temperature(s). When load and reduce steam temperature; therefore, every
is reduced substantially, or when the boiler is attempt should be made to assure light-off and
taken off the line, the furnace sheds its accum- continued operation after thefirst purge.
mulation of ash. After restart, additional time is
required for the furnace to season. UNIT START-UP
Start-up rates for generator-turbine units be-
PULVERIZER SELECTION
come increasingly important when system op-
eration departs- from-base loading. If a unit
Designing a boiler for cycling operation re- start-up from a cold condition takes eight
quires special attention to select and properly hours, but the unit is started only two or three
size the pulverizing and firing-system compo- times a year, there is little economic impact
nents. Unless these components are flexible from using the more expensive warm-up fuel
and reliable over a wide range of conditions, and the direct labor cost also is minimal. But
the boiler capability to cycle will be severely warm-up and stabilizing-fuel costs can be con-
limited. Pulverizing equipment must be able to siderable if the unit is continually two-shifted
deliver fuel to the unit at low loads, as well as or cycled at low loads.
respond to the usual considerations of ca- The designs described in the following sec-
pacity, fineness and turndown. The alternative tion can assist in matching superheat and re-
is to use large amounts of some stabilizing fuel heat temperatures, and pressure ramp, to the
such as oil or natural gas. turbine start-up requirements.
To obtain maximum flexibility and reliabil-
ity, it is advantageous to use a greater number TEMPERATURE
of pulverizers, of lower capacity, rather than AND PRESSURECONTROL
use a smaller number of larger capacity pul-
verizers, thereby limiting the turndown ratio. For a hot restart following an overnight out-
The larger number of pulverizers, however, age, high-enthalpy steam is required. For acold
will generally increase initial capital costs. restart following a weekend outage, low-
enthalpy steam is preferred to reduce thermal
Primary Air Temperature to Pulverizers
shock in the first stages of the.high-pressure
The effect of the hot primary-air temperature and intermediate-pressure turbines.
on pulverizer performance is well known. Par- Although the steam-temperature control sys-
ticularly during start-ups and low loads, pri- tems as designed for base-load operation gen-
mary air temperature can be a factor in the erally have been adequate for such cycling, a
operation of the firing equipment. While a prob- simple start-up system can provide the neces-
lem of low air temperature might be alleviated sary flexibility in stea'm temperature control.
somewhat on warm restarts following overnight Fig. 27 shows an arrangement of valves and pip-
shutdowns, cold starts still are required after ing connecting the backpass ring header of a
weekends and other outages. Therefore, in the subcritical-pressure drum-type unit to the con-
selection and arrangement of air-heating equip- denser. The arrangement is sized to pass ap-
--
COMBUSIlON
C.ntnCSMion Steam Gematom

Fig. 27 Backpass drain system for superheater temperature and pressure control, drum-type unit

proximately 5-percent flow at 1000 psig. This up conditions for an overnight shutdown of
system controls pressure rise on start-up, per- eight hours and a weekend outage of 55 hours,
mitting increased firing rates to achieve higher on a high-subcritical-pressure Controlled Cir-
superheat and reheat temperatures. The motor- culation boiler. From light-off to synchroniza-
operated steam-drain bypass valve also preheats tion, the unit can be fired at a rate to produce
turbine leads before synchronization. A spray gas temperatures necessary to develop the
desuperheater in the line from the bypass valve proper superheat temperature. At the same time
to the condenser provides for thermal protec- the gas temperature at the first section of re-
tion of the condenser. heater is limited to approximately 1000F (or
REHEAT TEMPERATURE CONTROL 540C) until steam flow through the reheater is
established. The gas-temperature probe in front
When high primary and reheat steam tem- of the reheater monitors the gas temperature.
peratures are required for hot-start conditions
(to match turbine metal temperatures), valved ALLOWABLE START-UP
-. A connections from the saturated steam circuits AND LOAD-CHANGERATES
- - to the reheat outlet can be added to the back- Disregarding any firing limitations that may
pass drain system. exist, the boiler component that limits start-up
Figs. 28 and 29 illustrate typical boiler start- rate on Controlled Circulation units is the final
COMBUSPION
Central-StatlonSteam Generators

SHO Pressure SHO Pressure

,SH Temp SHTemp, /

~ n i t ' ~ r i ~ Unit ired nu'~y~chronization


I
Fig. 28 Start-up curves for operation of a Controlled Circulation@unit following &hour shutdown. Hatched
areas indicate temperature control achievable with steam-temperature matching systems.

Fig. 29 Start-up curves for operation of a Controlled Circulation@unit following a 55.hour shutdown.
Hatched areas indicate temperature control achievable with steam-temperature matching systems.
-
COMBUSTION
Cmtd-StaUon Steam Generators

superheater outlet (SHO) header. There are limits the boilerlturbine during cyclic opera-
several reasons why this header, rather than the tion and start-up. Large reheat turbines have
thicker-wall steam drum, has such an effect on start-up and loading rates compatible with rea-
start-up rate. sonable cyclic life expenditure (CLE).
8 SHO headers expe~ienceboth fatigue and C-E has developed analytical procedures to
creep damage, while the drum experiences generate CLE curves for boiler pressure parts.
only fatigue damage due to its lower operating Fig. 30 shows a CLE curve for a 20'' OD, 4.25 in.
temperature. wall-thickness, 2% Cr-1 Mo superheater outlet
There is a great difference in fatigue life at header. The. calculation procedures used to
1000F and 680F (the temperatures of SHO construct the SHOICLE curve employ a cyclic
header and drum plate, respectively). elastic/plastic creep analysis of the SHO header
m The temperature change the drum experi-
tee. It is very informative to compare CLE
curves for a typical steam turbine (Fig. 31) and
ences on a typical hot start is approximately
400F less than the SHO header. CLE curves for the SHO header tee (Fig. 30).
The SHO header has much more cyclic capabil-
Controlled Circulation drums have a nomi- ity than the turbine.
nal ramp-rate limit of 400Flhr and a fast tran- The start-up rates indicated for an overnight
sient limit of 150F temperature change during shutdown (8 hours) are approximately 55 min-
any 15-minute period. This fast transient limit utes from synchronization to full load (Fig. 28).
is extremely important, as illustrated by the fol- Start-ups after weekend or holiday shutdowns,
lowing example. If the unit is operated in a in contrast to overnight shutdowns (Fig. 29).
modified sliding pressure mode with approxi- are generally limited by the steam-turbine
mately 1500 psig drum pressure at 50 percent thermal stresses.
load, a rapid increase from 50 percent to 100 When lighting off a drum-type Controlled Cir-
percent load will increase the saturated tem- culation unit and raising the steam pressure, the
perature from approximately 600F to 680F, or saturated steam temperature increases about
a change of 80F. During such transients, the 100F(about 55 "C)from first fire to synchroniza-
drum can tolerate the rapid 80F change an un- tion, a period of approximately 30 minutes for a
limited number of times. coal-fired unit. This time is not restricted by
The internal shroud in Controlled C:rcula- steam-generatorpressure parts as the ramp rate is
tion drums (Fig. 8) promotes heat transfer that only 200F/hr (95"CIhr) and can be readily in-
is even around the circumference and along the creased provided the firing system and turbine
length of the drum. This even heat transfer conditions permit. From synchronization to full
minimizes through-the-wall and top-to-bottom load in 55 minutes is an increase in saturation
thermal gradients. Thermal-circulation boiler temperature of 130F (70C)or a rate of 142OFIhr
drums cannot tolerate such ramp rates because (about 80C/hr). This ramp rate is significantly
of the drum metal temperature differentials less than that permitted by either the steam drum
that would be generated. In actual practice, or SHO header.
they are limited to less than one half the allow-
able rate of a Controlled Circulation unit. TURBINE BYPASS SYSTEM
(Thermal-circulation units cannot use an effec- The turbine bypass system permits operation
tively shrouded drum because the circulation of the steam generator independent of the tur-
system cannot accommodate the additional bine at any rating up to the bypass capacity.
pressure drop.) This permits turbine start-up with essentially
Although the superheater outlet header. zero temperature mismatch. Bypass systems
(SHO)usually is the limiting boiler component such as shown schematically in Fig. 32 are usu-
on Controlled Circulation units, it would be a ally rated for 50 to 100 percent bypass flow
mistake to assume that the SHO header always under full-pressure conditions. The major
CO'hbBrnON
Central-Station Steam Generaton

..

0.10 (1,000)
-
L
*
- Values on Curves are
I 0.05 (2,000) Life Expenditure in

::
$ 400 PercentICycle - Values
0.02 (5,000) in Parentheses are Total
ai Number of Cycles to
2 300
a 0.01 (10,000) Initiate a Crack
Q
E 200
m
a
100 - 0.001 (100,000)
0 - I l l 1 I I
0 100 200 300 400 500 600
SHO Header lnner Surface Temperature Change, OF

Fig. 30 Cyclic life curves for typical superheater outlet header

Values on Curves are


Llfe Expenditure in
Percent/Cycle - Values
in Parentheses are Total
Number of Cycles to
ln~tatea Crack

First-Stage Shell lnner Surface Metal Temperature ChangeSoF


Fig. 37 Cyclic life curves for high-pressure steam turbine

advantages of a bypass system are its The disadvantages of a .turbine bypass sys-
flexibility of operation tem are
ability to hold the generator output during increased plant cost
start-up without undesirable turbine cooling complexity of control
ability to recover following a load rejection
before restarting or reloading the turbine additional valve maintenance
ability to match turbine metal temperatures possibility of turbine or condenser damage
on hot restart due to malfunction or failure of components in
Also, there is evidence that exfoliated super- the bypass system
heater or reheater material which bypasses the increases in plant heat rate because of greater
turbine during start-up greatly reduces exfolia- condenser heat loss during periods of bypass
tion damage to turbine blading. system operation
.-
COMBrnON
Centfal-Station Steam Generators

I I
Fig. 32 Steam-turbine bypass system, drum-type subcritical-pressure unit

The temperature-matching potential of a in the steam turbine. One operating regime that
bypass system depends upon its sizing; is useful in reducing thermal stresses is vari-
maximum steam temperature capability can be able or sliding-pressure operation.
found from the steam temperature curves f the To controlload on a steam turbine, the pressure
boiler at the maximum rating of the bypass sys- level in the first stage must be varied. Base-
tem. If the desired' temperature matches be- loaded units of traditional design provide con- .
tween the superheat and reheat steam and the stant pressure at the boiler outlet. Throttle
turbine metals can be achieved with other valves at the turbine inlet are used to vary pres-
start-up techniques, such as a temperature sure and thus load.
matching system, no additional saving in start- This mode of operation generates large dif-
up time on a hot start can be achieved with a ferences in temperature inside the first stage
bypass system. of the turbine because of the throttling losses
Supercritical units require a start-up system at the inlet and the outlet (Fig. 33). A boiler
to protect the furnace walls during start-up and designed to operate at variable pressure over
low loads. These systems then function as tur- the load range can match the requirements that
bine bypass systems to varying degrees depend- the turbine demands. With sliding pressure, the
ing on their design. differences in temperature are essentially elimi-

SLIDING-PRESSURE OPERATION
nated because there are no throttling losses.2
The principal advantages of sliding-pressure
o~erationare:
- - . -

The requirement for daily cycling andlor two- 1. Minimal variation of first-stage shell temper-
shifting can create undesirable thermal stresses ature of the turbine under varying load condi-
COlrLBDSPION
CentralStatlonSteam Generators

tions. By reducing the temperature difference


that the first-stage components must endure
during significant load changes, operating con-
straints we minimized.
2. Improved overall power-plant heat rates con-
sidering boiler-turbine, feed pump, and other
auxiliaries. Fig. 34 indicates the effect on tur-
bine heat rate of the various operating modes. It
can be seen that the two hybrid pressure pro-
grams offer better heat rates over the load range
than the other alternatives.
3. During start-up, the reduced steam pressure 20 30 40 50 60 70 80 90 100
results in smaller heat-transfer coefficients and Load, % WVO
correspondingly lower thermal stress levels for Fig. 33 Typical steam-turbine first-stage shell tem-
the same temperature differential between perature
steam and metal components.
4 . Extended control range (full steam tempera- As their main goal these various start-up
ture at lower loads) of both the primary and re- methods protect the turbine. The steam gen-
heat steam temperatures (Fig. 35). erator must also handle the thermal loads and
5. Improved steam flow distribution at lower ensuing thermal stresses that result from temp-
loads in the superheater and reheater because erature differences and gradients imposed by
of the higher specific volume of the steam at start-up and shutdown, cyclic operations, and
lower pressures. the heat-absorption process. As previously
6 . The reduced pressure level at lower loads emphasized, Controlled Circulation furnace-
unloads all cycle components between the wall systems provide protection throughout
feed pump and high-pressure turbine, thereby start-up and shutdown, pressure raising, and
prolonging life span and reducing auxiliary full-load operation by insuring positive water
power consumption. flow to all furnace-wall circuits independently

4-

3 -2 Admissions -Constant Pressure


--- Variable Pressure

pm 0.

(PartialArc Admission)
-2-. I I I I I I I I
20 30 40 50 60 70 80 90 100
WVO Load, %

Fig. 34 Effect of admission modes and throttle-pressure programs on heat rate-typical 2400 psig
(16.6 MPa gage), 10001 1000F (540/5400C) turbine with 7-heater cycle and turbine-driven boiler feed-
water pump

---
ABB
COMBUSRON
Centnl-SWon Stnm Generators

2400 psig, 1000F/lOOOoF (16.6 MPa gage, I

I l1
-Constant
Wr --- Pressure
Variable Pressure I
54O0C/54O0C).The turbine has a partial-arc-
admission first stage with 4 nozzle groups,
each controlled by a separate valve. Three differ-
ent operating-pressure programs are considered
(Fig. 36). They are:
full variable pressure, with turbine control I
valves wide open
constant pressure when on control valve
No. 4; variable pressure below the point where
No. 4 valve closes
Steam-Generator Load, % constant pressure when on valves Nos. 3 and
4; variable pressure below point where No. 3
1 I

Fig. 35 Typical superheat and reheat temperatures valve closes


in constant. and variable-pressure operation Operating with the first pressure program has
the advantage of essentially eliminating first-
of heat-input rate, thereby permitting acceler- stage temperature changes inside the turbine-
ated start-ups and cool-downs. as long as the initial and reheat temperatures
Finally, regardless of whether variable pres- are held constant. However, the response of the
sure is used during normal operation, it can be boiler-turbine combination to changes in load
advantageous for start-up and shutdown by demand is relatively slow and may not satisfy
providing better turbine temperature match- the power-system control requirements. Some
ing, especially with units subjected to cycling operating companies prefer to have the turbine
and two-shifting. It is normally unnecessary to speed governor contributing to system control,
go below half the maximum operating pressure and therefore choose a hybrid pressure pro-
to obtain the benefits of temperature matching. gram such as shown by curves 2 or 3 in Fig. 36.
SUBCRITICAL-PRESSURE This overcomes the main disadvantages of full
SLIDING-PRESSURE OPERATION variable-pressure operation, while still retain-
ing most of the benefits.
As an example, choose a boiler-turbine com- I
bination with nominal steam conditio: of SUPERCRITICAL-PRESSURE
SLIDING-PRESSURE OPERATION

r The first design condition that must be


considered is the mode of variable-pressure
operation versus load.
.{2400- Fig. 37 shows a series of typical variable-
g @ 2000 - pressure programs for supercritical boilers.
E z;3 These programs are determined for a different
5a
I- 2 number of turbine control valves in operation.
.5 1000- Operating pressure program Number 1 reflects
3; 600, the maximum number of control valves in oper-
e I I I 1 I ation, and this is essentially constant-pressure
operation for a typically base-loaded supercriti-
20 40 60 80 100
VWO Load, O/O cal unit. Operating program Number 5 shows
- full variable pressure, with the turbine valves
wide open.
Fig. 36 Sliding-pressureprograms for Operating in accordance with program Num-
subcritical-pressuredrum-type boilers ber 5 has the advantage of effectively eliminat-
COMBUSTION
Central-Station Steam Generators

ing first stage temperature changes inside the


turbine, as with subcritical sliding-pressure op-
eration. A hybrid pressure program is shown by
Curves 2, 3, and 4 in Fig. 37. As above, this
overcomes the main disadvantages of full
variable-pressure operation.
Curve Number 3 in Fig. 37 shows a variable-
pressure program in which the turbine control
.-
valves are throttled above 70 percent of maxi- -
mum boiler load. f
Fig. 21 showed a comparison between wa- 0 "
0 20 40 60 80 100
terwall pressure and turbine throttle pressure; Load, % VWO
below approximately ,60-percent boiler load,
the furnace walls operate at subcritical pres-
'Fig. 37 Sliding-pressure programs for supercritical
sure, that is; with a mixture of steam and water. boilers
Above 60-percent boiler load, the furnace walls
operate at supercritical pressure. It illustrated dealt with; on the other hand, flow distribution
that the potential for departure from nucleate to the back pass and the superheater becomes
boiling is only at the lower boiler loads where the much more straightforward because a single-
furnace heat-absorptionrates are lower. At higher phase fluid is present.
loads, the furnace walls handle a single-phase Below approximately 35 percent, the recir-
fluid and DNB cannot take place. In other words, culation system goes into operation and the
at the higher loads, the unit operates like a Com- furnace-wall outlet conditions become satu-
bined Circulation unit.' rated. The recirculation system is sized to stay
Fig. 38 shows the performance characteristics in service, if required, up to 45 to 50 percent of
of a once-through sliding-pressure supercriti- maximum boiler load.
cal unit plotting enthalpy vs. load; a standard
enthalpy vs. pressure diagram has been used
with load substituted for one of the ordinates in
order to give a more realistic representation of
the performance of the unit.
The following should be noted:
The outlet of the economizer has been kept
substantially below the saturation condition.
Steaming of the economizer would create flow >
-
a
m
distribution problems entering the furnace 5
walls. This is the reason why the economizer 5
has been included in the recirculation system.
For low-load operation (below 35 percent) the
increased mass flow through the economizer
prevents flashing and steaming, which are com-
mon problems in operating such units, particu-
larly under fast-start conditions. 35 100
The furnace-wall outlet conditions are above Steam-Generator Load, %
the saturation point at subcritical pressures.
Therefore, superheated steam is present leaving Fig. 38 Performance characteristics of once-
the waterwalls. As previously stated, this can through sliding-pressure supercritical steam
cause temperature differentials which must be generator
cobmlsmON
Centnlstation Steam Generators

PRESSURE-PART DESIGN ... furnace-wall tubes and attachments

...
FOR CYCLIC DUTY buckstays
In addition to the design and performance steam'water separators
reauirements for which base-loaded units are pumps and
sefected. two additional, reauirements must be
A

considered for the cycling boiler. These are


rapid rates of load increase and a significantly
greater number of and 'Y-
.
pulverizer structure and drive train
duct expansion joints
hanger rods and supports
Such components are evaluated using vari-
'les. The present of Section I theASME ous factors, chief being the operating pressures
governing pressure-part design and fabe and operating conditions that minimize ther-
rication do not provide specific guides for mal stresses in the steam-turbine rotor, Simi-
dealing with the thermal-stress and fatigue larly, it is necessary to minimize thermal
problems encountered in this type of unit. The stresses in all boiler components.
Code do", however*'hage the manufacturer Expansion stresses that result from steady-
with the responsibility ofattending to and ac- state operation are relatively simple to accom-
counting for these effects. modate in a design, but thermal gradients
The first step in an evaluation of this type of produced by temperature transients greatly
operation is making a conservative estimate of complicate the design. As faster start-up and
the number 'perating a plant must shutdown rates become necessary, thermal
undergo. The second in a good gradients increase and the thermal design of a
design is to develop and adopt a set of design component may well run counter to the re-
criteria to allow the intelligent assessment of all
quired design for mechanical loads, such as
Of loading (pressure*
pressure and dead load. Attachments to pres-
mal, and cycling) to insure long-term compo-
sure parts normally are sized by the mechanical
nent integrity. This subject was discussed in loads they carry. To reduce the size of such an
Chapter 6.
attachment [so as to reduce a thermal differ-
COMPONENT DESIGN ence) may invalidate its design. Heavy thick-
AS INFLUENCED BY CYCLIC OPERATION walled components, such as the SHO tees or
steam drums, are sized according to pressure
Understanding the definitions of cyclic re- requirements. Wall thicknesses, then, cannot
quirements and boiler design criteria, the de- be decreased to reduce thermal gradients and
signer can assess the various temperature and thermal stresses.
loading conditions in terms of stresses, and can Pressure and thermal stresses combine to
determine the capabilities of the steam- produce a total stress. Fig. 39 shows an ideal
generator components to satisfy system re- operational cycle in which the pressure and
quirements. The major factors affecting these steam-temperature curves have the same rate
design considerations are for start-up as for shutdown. The stresses pro-
duced in a cylinder with the pressure and
8 number of cycles
thermal loading cycle are shown in Fig. 40. Of
heating and cooling rates interest is the relationship of the thermal and
component thickness, diameter, and material pressure stresses on the inside surface of the
8 operating temperature level cylinder. During the entire cycle, the pressure
Analytical and test methods are used to stresses are tensile. Thermal stresses are com-
evaluate specific performance capabilities of a = .pressive during start-up and tensile during

.variety of components such as


8 drums, including downcomers
headers, including tees and nipples
- shutdown. The pressure and thermal stresses

oppose each other during start-up but are addi-


tive on shutdown.
COMBDSTION
Central-Statlon Steam ene ex
The stress range shown in Fig. 40 determines
the amount of fatigue damage represented by
this cycle. The greater the stress range, the
greater the fatigue damage. One possible way of
reducing the stress range is to reduce pressure Pressure Stress
during a cooldown while maintaining the
steam-temperature level.
The sliding- or variable-pressure mode of op-
eration allows main steam and reheat steam Thermal Stress
temperatures to be maintained at a given set- -6
point lower into the load range. Although it is 2 4 6 8 10 12
Time, Hrs
for this reason and others discussed earlier that
variable pressure is used, there is an added ben-
efit. During a cooldown, the pressure stresses
I
Pressure and thermal stress versus time
Fig. 40
are additive as shown in Fig. 41. Therefore, the . ,
combined pressure and thermal stresses are used on cycling units. This requirement places
lower than the stresses that would have been a special burden on the steam-generator con-
generated if pressure had been maintained and trol system, with the steam-temperature con-
the temperature dropped. trols being the most severely affected.
The stored energy in a steam generator (metal
CONTROL CONSIDERATIONS
FOR VARIABLE-LOAD OPERATION
temperature and steam enthalpy, both as a
function of mass) is higher at full load than at
The thermal inertia of steam generating any partial load. Increasing the load, therefore,
equipment relates directly to its size. It is requires temporarily raising the firing-ramp
necessary to understand when designing oper- rate above the load ramp to provide the re-
ational control equipment that, combined with quired increase in stored energy. During load
increases in unit size, present practice is to de- increases on a variable-pressure unit, the slope
sign for variable-load operation. On constant- of the stored energy is substantially steeper
pressure units, it is only necessary to deal with than the load output curve.
the energy-storage changes associated with the Overfiring to satisfy the energy storage re-
changes in steaming rate. But, as previously quirements of the waterwalls generally results
discussed, turbine considerations virtually in excessive heat pickup in the superheater and
demand that variable-pressure operation be reheater, which have lower storage capacity.

a
E 800 Heat-Up
Pressure

Temperature
2500

Cool-Down looO
U)
"b/
V)

I
i -2
i
Pressure
~hermalStress !\
+4
0
f7M)
2 4 6 8 1 0 1 2 ~ F -411111CIIIIIII
Time, Hrs 2 4 6 8 10 12
Time, Hrs

Fig. 39 Idealized operating cycle Fig. 47 Combined pressure-/thermal-stress cycle


--

7-49 A!
COMBDSTION
Cant&-Station Steam Generators
-
Further complicating the situation is the fact scanner viewing area is also essential.
that the distribution of heat between water- In a two-shifting mode, the major impact on
walls and superheater of a typical subcritical- the control system is the need for more automa-
pressure drum-type unit varies significantly tion. Bringing in additional plant operators to
with pressure because of changes in the vapor- control various subloops manually on every
ization heat of water and the specific heat of start-up may be acceptable on a base-load unit,
superheated steam as a function of pressure. but is not likely to be so for a two-shifting unit.
Traditional superheater temperature-con- Traditional boiler-following control systems
trol systems use cascade-type spray controls, place too much of the burden on plant oper-
in which the final-temperature error resets the ators to coordinate both changing conditions of
setpoint for the desuperheater outlet tempera- temperature, pressure and flow in the boiler
ture. This is a type of feedback control and is and turbine. The use of a coordinated control
inadequate for even moderate rates of load system, with its plant-master concept, then,
change in a sliding-pressure mode. Any work- is virtually essential to satisfy the control
able steam-temperature control configuration requirements of cycling operation.
must include both careful timing of any overfir- Using boiler start-up systems or turbine
ing and a sophisticated anticipation signal in bypass systems adds an additional set of
the superheat and reheat control loops. Pro- control loops that must also be carefully
gramming the desuperheater outlet tempera- coordinated with the steam-generator and
ture as a function of load and rate-of-change of turbine-generator controls.
load is one example of the use of feed-forward
temperature control. WATER TREATMENT FOR CYCLING UNITS
In a subcritical unit operating at constant Any power plant operation that requires a
pressure, shrink and swell of drum level occur great number of start-ups, shutdowns, and idle
during a load change because of the change in periods will be subject to inleakage of air, espe-
steaming rate. With sliding pressure, however, cially in the condensate and low-pressure
there is also a mass-inventory chan,oe as- feedwater systems. This increases the potential
sociated with the pressure change. Feed- for preboiler and boiler internal cor~osionand
forward signals are used to help the drum-level over-heating from deposition of corrosion
controller distinguish between shrink and products in internal tube surfaces. The
swell effects and feedwaterlsteam-flow mis- mechanism by which this occurs is oxygen cor-
matches. Regulating the speed of the boiler rosion of feedwater heaters and interconnect-
feed pumps is the most common control of ing piping, plus the formation of corrosion
feedwater flow rate. The reduced pressure at byproducts such as iron-oxide and copper;
low loads with sliding-pressure operation re- these are subsequentlj7 transported to the boiler
quires that the stable speed control range on where they will deposit on the inside of the
the pumps be significantly wider or that furnace-wall tubes. High oxygen concen-
supplementary valve control be used. trations in the feedwater and boiler water can
The specific cycling mode that involves also produce corrosion pitting, which can
holding minimum load overnight presents directly promote tube failures. Proper pre-
some additional concerns associated with cautionary measures are necessary in cycling
keeping supplementary-fuel use to an absolute units to prevent corrosion damage.
minimum. Improved flame-scanning systems Units for 2400 psi two-shifting and cycling
incorporating higher sensitivity scanners operation, and all supercritical pressure units
andlor increased quantities of scanners are should have condensate polishing equipment
mandatory. More precise control of fuel and air to control corrosion-products, condenser in-
distribution to maintain the fuel ignition point leakage contaminants, and make-up water im-
at each fuel-admission location within the purities. Its design and operation should keep
COMBUSTION
Central-StationSteam Generators

feedwater contamination within boundaries of facilitate reaching operating pressure without


limiting criteria for all modes of operation. Ion experiencing undue delays to control silica.
exchange to process at least 25 percent of full- Detailed information on cycling-service pre-
load condensate flow is required in two-shift boiler cleanup, condensate deaeration, and
drum-unit operation to process feedwater con- condensate polishing is given in Chapter 20
taminants and impurities from the turbine and and Chapter 21.
condenser. Cleanup of condensate will also

REFERENCES
1 W. H. Clayton, J. G. Singer and kV. H. Tuppeny, Jr., "Design 5 L. W. Cadwallader,E. M. Powell, and J. G. Singer, "ANew Look
for PeakingICycling" presented at the Joint Power Generation at Peaking Power," Proceedingsof the American Power Confer-
Conference, September, 1970 American Society of Mechan- ence, 28:413-421,1966. Chicago, IL; Illinois Institute of Tech-
ical Engineers Paper No. 70-PI\X-9, New York, 1970. nology, 1966.
2 0.Martinez, Jr. and J. A. blakuch, "Supercritical SteamGener- 6H. E. Burbach, J. D. Fox, T.B. Hamilton, "Steam Generator
ator Designs for Sliding Pressure Operation:' Proceedings of Design Features for Variable Load Operation:' Proceeding of
the American Power Conference. 43; Chicago, IL; Illinois Insti- The American Power Conference, 41: 561-579. Chicago. IL:
tute of Technology, 1981. Illinois Institute of Technology, 1979.
I. Fruchtman et al., "Cycling of Supercritical Power Plants in
J H. E. Burbach and G. E Shulof. "The Cycle Option," Proceed- the U.S.," presented at the loint ASMEIIEEE Power Generation
ings of the American Power Conference, 42: Chicago, IL; Illi- Conference,Miami Beach, FL, October 4-8.1987; American
nois Institute of Technology 1980. Society of Mecliancial Engineers Paper No. 87-JPGC-PWR-50,
G. R. Fryling, "Combustion Engineering:' Revised Edition New York, 1987.
1966. Library of Congress Catalog Number 66-23939, 1966.
CHAPTER 8

Boilers for Process UselPower Production

T" is chapter is about a wide range of fossil-


fueled steam generators often designed to
operate at steam temperatures and pressures
in the next chapter. Boilers with characteristics
particular to the marine industry are found in
Chapter 10. Finally, Federal legislation that
that are suitable for electrical-power generation redefines the relationships between central-
by a steam-turbine generator. But, because they station owners and other power generators sig-
can also be used solely for the processes of nificantly affects the incorporation of industrial
the several manufacturing industries, co-t boilers in combined cycles, which we have dis-
generatively or not, they have come to be called cussed in Chapter 1,and further in this chapter.
industrial boilers, a term which we use freely
in this text. In fact, the versatility of most of
these steam generators makes them part of every PERFORMANCE
conceivable type of process-steam, steam-for- REQUIREMENTS OF
power, or cogeneration cycle. MODERN INDUSTRIAL BOILERS
This definition of an industrial power-plant
boiler, then, is as arbitrary as previous ones Industrial boilers for process-plant service
have been and is based on the physical charac- are ordinarily designed to fire many different
teristics of the equipment rather than on its fuels,.each of which influences sizing and con-
ultimate application: it is a stationary (not figuration of the boiler and its auxiliaries. In.
shipboard) watertube steam generator, without addition, the primary fuel may vary over the life
steam reheat; most often, it has a drum operat- of the unit. Also, many manufacturing/process
ing pressure below 2,000 psig (13.8 MPa gage), plants are sources of byproducts that are valu-
is below 100 megawatts in electrical generating able as fuel. The need for industrial boilers to
capability, and is multifuel fired. Neither cycle be fuel-flexible, while meeting stringent fed-
or boiler efficiency, sophistication of opera- eral, state, and local emissions standards, re-
tional controls, nor the level of government- quires special design considerations and
legislated emission-control systems are sophisticated ancillary equipment.
pertinent to this definition. Understandably, there is a preference to de-
Obviously, this definition does not exclude sign industrial boilers for burning clean liquid
fluidized-bed boilers which, for the purpose of and gaseous fuels when such are available at
better delineating the technology, are covered reasonable cost-the boilers and auxiliaries
C O ~ O N
goifen for Pmcess Use/Powar Production

will be of minimum size and cost. Unfortu- the high cost to dispose of waste make rgfuse,
nately, world demand for such prime fuels can biomass, waste acids, and sludge more attrac-
be expected to outpace the long-term supply tive as fuels for steam generation; they provide
and will result in a decline in oil- and gas-burn- a viable disposal alternative. A growing number
ing steam generators. The eventual shift to solid of new boiler designs will use waste fuels.
fuels will require boilers that are not only ini- Low Operating Costs: The cost of fuel and
tially more expensive, but also operationally auxiliary power can in a short time exceed the
more difficult. Thus, as more coal and other original cost of a steam generator. Therefore,
solid fuels are burned, there will be an in- new equipment must be efficient and have a
creased need for pulverized-coal, stoker, and low auxiliary-powerconsumption.
fluid-bed firing. 8 Cogeneration Potential: Simultaneous gener-
Owners and operators of industrial boilers ation of electrical power and process steam, as
must consider such developments and adapt described in Chapter 1,is also common as users
unit performance to: strive to extract maximum heat from their fuel.
Multifuel-Burning Capabilities: During the Industrial firms will more frequently select the
70's some industrial concerns had to convert more efficient high-pressure and high-temper-
boilers from firing coal to gas, to oil, and back ature steam cycles to optimize the amount of
to coal as the environmental requirements, fuel electrical power and steam produced.
costs, and fuel availability changed. To protect
an investment in the steam-generating facility, BOILER DESIGN AS A FUNCTION OF
the owner may more frequently request multi- OPERATING PRESSURE
ple-fuel capability in new units. As Fig. 1 shows, the percentage of total heat
Waste-Fuel Utilization: Rising fuel costs and absorbed in a boiler bank is reduced signifi-

200 psig 600 psig, 750F at 1800 psig, 1005F at 1800 psig, 1005 F at
Saturated Steam SuperheaterOutlet Superheater Outlet SuperheaterOutlet
240' F Feedwater 240' F Feedwater 350" F Feedwater 350" F Feedwater

Fig. 1 Heat-absorption distribution for pulverized-coal suspension-fired boilers

1~r n
e!!!'!!! 8-2
COMBUSTION
Boilers for Process UsefPowerPfuducbon

cantly at higher pressures by two factors: other hand, with coal and refuse firing the de-
I. In the superheater, the greater heat absorp- sign gas velocities, together with gas tempera-
tion required to heat the steam to a higher tem- tures, influence the ability of the boiler to
perature reduces the gas temperature entering operate continuously without shutdown.
the boiler b a a Although convection tube spacing is not crit-
2. The water temperature in the boiler bank is ical in boilers designed to fire gas or distillate
essentially at the saturation temperature corres- oil, it is very important when the fuel is a resid-
ponding to the boiler operating pressure. As the ual oil, municipal refuse, or coal. This is espe-
operating pressure increases, the temperature cially so with coals that have low ash-fusion
of the water inside the tubes rises thereby temperatures or high ash-fouling tendencies
reducing the logarithmic mean temperature and with low-rank coals such as subbitumi-
difference available for heat transfer. nous coals or lignite.

DESIGN CRITERIA FOR INDUSTRIAL


BOILERS _ - COAL-FIRING SYSTEMS
~ ~designs ~ to the
i areltailored ~ fuels and fir- Many industrial boilers are designed for less
than 25G,000 lb steamhr (32 kg steamfs). For

.
ing systems involved. Some of the more impor-
tant criteria are many years most of these units used a spreader
stoker to fire coal because it was less expensive
furnace heat-release rates, both Btuhr-cu ft
than installing pulverizers. In this size range,

.
and Btuhr-sq ft of effective projected radiant
the other benefits of pulverized-coal (PC) did
surface (EPRS)
not warrant the increased costs. In today's mar-

.
heat-release rates of grates ketplace, the choice is not as obvious. With the
flue-gas velocities through tube banks advent of tighter emission regulation, higher

I , tube spacings

Table I gives typical values or ranges of these


fuel costs, and the commerciaiization of fluid-
bed boilers, the advantages of each system must
be evaluated thoroughly before selecting a fir-
criteria for gas, oil, biomass, refuse-derived fu- ing system.
els, and coal, all fired in suspension or on
EVALUATING STOKER AND
grates, to illustrate the differences for the fuels
PULVERIZED-COAL FIRING SYSTEMS
and not necessarily to represent specific recom-
mendations. The furnace heat-release rates are A reduced efficiency due to the carbon loss is
important from several viewpoints. The proper a major factor in comparing a stoker-fired boiler
Btuhr-sq ft of EPRS value, along with adequate to a PC-fired boiler. A properly designed PC
flame-to-heat-absorbing-surface clearance, will boiler can maintain an efficiency loss due to
keep maximum local absorption rates within unburned carbon of less than 0.4 percent. On
safe limits and avoid "hot spots." Also, with the other hand, a continuous-ash-discharge
coal and refuse firing, this aspect of design is spreader-stoker fired unit will typically have a
important to prevent excessive slag accumula- carbon loss of 4 to 8 percent, depending on the
tions on furnace walls and convection tube amount of reinjection. The PC unit offers a
surface at the furnace outlet. The furnace heat- lower carbon loss because of the increased com-
release rate in Btuhr-cu ft directly influences bustion efficiency obtained with the finer coal
completeness of combustion. Limiting grate particles that enter the furnace (normally 70 to
heat-release rates to these values minimizes 80 percent will pass through a 200-mesh
carbon loss, controls visible emissions, and screen). In contrast, the coal particles entering
avoids excessive flyash. the furnace with a spreader stoker are much
The need to limit draft loss controls flue-gas coarser. These coal particles have a 314-inch
velocities for gas- or oil-fired boilers. On the (about 20-mm) top size and not more than 50
C O ~ O N
Bolkn for Process UsoPower Ruduction

Table I.Some Typical Boiler Design Parameters


Furnace Btulhr-sqA of EPRS Btulhr-cu A
Natural gas 200,000 N/A
Oil 175,000-200,000 N/A
Biomass NIA 15,000-20,000
Refuse Derived Fuel (RDF) NIA 12,000-15,000
Municipal Solid Waste (MSW) N/A 6,000-10,000
Coal-pulverized 70,000-120,000 15,000-22,000
Coal-spreader stoker 80,000-130,000 20,000-25,000
Stoker, grate heat-release rate, Btuh-sq A
Continuous ash discharge [CAD), coal 650,000-700,000
CAD - Biomass 900,000-1,200,000
CAD -Refuse-Derived Fuel 750,000-800,000
Dump grate spreader, coal 450,000-550,000
CEIdb Pusher Grate (MSW) 270,000-300,000
Flue-gas velocity, Wsec
Single-Pass Boiler Baffled Boiler Economizer
Gas or distillate oil 100 100 100
Residual oil 100 75 100
Bituminous coal
Low ash 50-60 50 50-60
High ash 40-50 N/A 40-50
&fuse Derived Fuel 25-30 N/A 30-35
Municipal Solid Waste 20-25 N/A 20-25
Biomass 50-60 40-50 50-60
Tube spacing perpendicular to gas flow,inches clear
Superheater Boiler Economizer
Front Rear Front Rear
Gas or distillate oil 2 2 1 1
Residual oil 4-6 2 11/2 1
Bituminous coal
Low ash 8 3-6
High ash 10-16 4-6
RDF 6-7 3-6
MSW 9-10 4-5
Biomass 7 2112

percent will pass through a %-inch (6-mm) coarse and fine particles. Normally, double-
screen (Fig. 2). screened coal is purchased to obtain the proper
The coal itself also affects the total fuel cost mixture as run-of-the-mine coal generally does
difference between these firing methods. Effi- not have the optimum balance of coarse *and -
cient operation of a spreader-stoker-firedboiler fine material.
requires that the coal has the proper mixture of The fine coal particles are burned in suspen-
COmmON
Boilen for Process Use/Power Production

Equivalent Particle Diameter, Micrometers


I I

U.S. Std Sieve Designation !squareMesh, in. Fig. 3 Size distribution for flyash leaving the furnace

1
I
I
I
necessary
. to provide hot'air to dry the coal to
-

the proper moisture for pneumatic delivery.


Fig. 2 Coal sizing (as delivered to the furnace)
The need for an air heater, additional ductwork,
and a more complicated control system has
sion. If the amount of fine particles is too great, to be measured against the fuel savings of
there will be excessive suspension burning pulverized-coal firing.
which can produce The furnace of a PC-fired system must be de-
signed to prevent ash from slagging on the wa-
higher stack particulate-matter loading
terwalls whereas high-ash coals with low
furnace pulsations ash-fusion temperatures can create a clinkering
possible heat damage to the distributors problem when burned on a stoker. In Ref. 1,
higher carbon loss and visible emissions Pollock gives a detailed comparison of annual
If the amount of coarse coal is too great, there fuel and power costs for pulverized and
will be insufficient burning in suspension, spreader-stoker coal firing.
with the potential for loss of flame stability.
EMISSIONS
If double-screened coal is not used, the day-
to-day efficiency of operation will be reduced Control of particulate epissions, sulfur ox-
as the coal sizing varies from optimum. The ides, and nitrogen oxides must also be evalu-
question of whether the higher cost for double- ated i n the comparative installed costs of
screened coal offsets the reduced efficiency different types of coal-fired equipment.
with unsized coal cannot be answered on a gen- Formerly, a stoker-fired boiler had a definite
eral basis. The answer depends on the degree of advantage in controlling particulate-matter
coal sizing variation, quality of operators, and emissions. This type of firing produces large
boiler or stoker size. particles that can be removed easily with inex-
A pulverized-coal-fired industrial boiler re- pensive mechanical dust collectors (see Fig. 3).
quires that the coal entering the mill be 111~-in. Today, all industrial, commercial, and institu-
(not over 40-mm) top size. If the proper size is tional units firing at or above 100 million Btul
unavailable at the mine, coal of any size can be hr (30 MJIs) must meet strict particulate-
purchased and crushed at the plant site. Con- emission standards. Compliance will necessi-
siderable horsepower is necessary to pulverize tate the use of electrostatic precipitators, fabric
and transport the coal to the furnace. It is also filters, or equivalent high-efficiency removal
devices regardless of the method by which coal value coal with the lowest grindability will de-
is fired. termine pulverizer size. If the coals vary i n
Likewise, federally mandated New Source moisture, the boiler convective surface (boiler
Wrforrnance Standards (NSPS) for 100 million bank, economizer, air heater) must provide
and higher B t u h (30 MJ/s) sources require sul- the proper air temperature to dry the coal in
fur-oxide removal equipment on all coal-fired the pulverizer so it is surface-dry and can be
steam generators. PC boilers with bowl mills transported pneumatically to the furnace.
can be expected to have less sulfur in the prod- If, for example, the moisture ranges from 3 to
ucts of combustion than stoker-fired units. Dur- 35 percent, the air temperature required by
ing the pulverizing process, the bowl-mill the pulverizer will vary from 300 to 700F
tramp-iron spout may reject up to 40 percent of (150 to 370C).
the pyritic sulfur. Because pyritic sulfur may Stoker requirements: Coals with low ash and/
approach 60 percent of the fuel sulfur, a reduc- or moisture will tend to have high grate-metal
tion of nearly 25 percent could be obtained un- temperatures. For such fuels, maximum allowa-
der optimum conditions. With a stoker-fired - ble undergrate air temperature will be less than
unit, some pyritic sulifur may remain on the 300F (150C) and, in the worst case, mini-
grate and be deposited in the stoker ash hopper. mum moisture and ash contents should be
Both firing systems are equally capable of specified. High-ash coals or those with low
meeting NSPS NO, emission levels. In some ash-fusion temperatures can clinker and dis-
cases, PC systems may require combustion air rupt the proper flow of undergrate air for effi-
to be staged in various configurations to reduce cient combusion and grate-bar cooling. The
NO, to these levels, while stoker-fired boilers actual physical size of a stoker is, however, far
can use varying proportions of undergrate and less sensitive to coal properties then is the
overfire air to minimize production of NO,. sizing of pulverizing equipment.
Superheater sizing: The specific fuel and ash
FUEL FLEXIBILITY
components determine the heat-absorption
Coal-fired boilers can be designed to burn a characteristics of the furnace and superheater.
wide range of coals. For suspension-fired non- But generally the best fuel, which produces the
reheat units, tilting tangential fuel nozzles and1 lowest gas weight and consequently the lowest
or spray desuperheating can control the effect heat-transfer rates and LMTD, will set the su-
of varying furnace heat absorption on the su- perheater size. A wide range of fuel moistures
perheater. But during design, coal and ash will require a spray desuperheater to control
properties for all of the coals to be fired must be final steam temperature when firing high- A

considered. The major factors in designing a moisture coal.


boiler for a wide range of coals are Fans and gas-cleaning equipment: The high-
Furnace sizing, convective surface spacing, est-moisture coal to be fired in a boiler gener-
and sootblower coverage: Coals with a lower ates the largest volume of ,flue gas. The fans and
ash-softening temperature require a larger fur- ductwork must be designed for these condi-
nace to assure the ash is in solid form before it tions. If a wide variation in flue-gas volume is
enters the convective tube surface. A furnace anticipated during normal operation, variable-
that is appropriately sized for the poorest ash speed motors or turbine-driven fans should be
properties will operate successfully with the considered to reduce parasitic power consump-
better coals. In designing for multiple fuels, it tion (see Chapter 14). Gas-cleaning-equipment
is not uncommon for one fuel to set the furnace size may not necessarily be set by flue-gas
size while another dictates the minimum allow- volume, but rather by the removal efficiency or
able convective-surface spacing and sootblower the absolute level of emissions in accordance
requirements. with applicable regulations, whichever is the
Pulverizer requirements: The lowest heating- controlling variable.
COMBUSnON
Bollen for Process UseIPower Pmduction

PROVISIONS FOR A WIDE RANGE OF COALS function of the mill size. Enlarging the pulver-
Some special considerations can be made in izers has the effect of reducing mill turndown
the original boiler design to accommodate a when firing a coal with a higher heating value
wide range of coals. With a 3 to 35-percent and grindability than the mill design values.
moisture variation in the coals to be fired, a pri- More smaller-size pulverizers may be needed to
mary-air preheater may be used to preheat the obtain the required turndown with a system de-
mill air to 700F (370C) from the nominal signed for a wide range of coals.
550F (290C) temperature leaving the second- Except for the pulverizers and air tempera-
ary-air preheater. When firing low-moisture tures, the design of stoker-fired boilers involves
coals, the primary-air preheater is not used and the same considerations for multiple-fuel fir-
there is a minimal requirement for parasitic ing. A stoker-fired boiler requires an air tem-
cold tempering air at the pulverizer inlet. Fig. 4 perature of less than 400 O F (200C) to maintain
shows a 650,000 lblhr (82 kgls) pulverized- adequate grate cooling for high-moisture coals
coal-fired boiler designed using this principle and less than 300F(1500C)for low-moisture
for various coals. coals. Because many high-ash coals with low
Although increasing the pulverizer size to ash-softening temperatures cause clinkering on
handle a wide range of coals is common, it has the grate, they cannot be ~sed'e'fficientl~. To
several drawbacks. The turndown capacity of a maintain the required bed height, high-ash
pulverized-fuel firing system is principally a coals require a faster stoker speed which may
increase the unburned carbon content of the
stoker ash. Using a large quantity of ash reinjec-
tion also aggravates grate clinkering.
BURNING LIQUID, GASEOUS, AND OTHER FUELS

Besides a range of coals, an owner may con-


sider firing other liquid, gaseous or solid fuels
(presentpr future). Because pulverized coal is
suspension-fired as are conventional liquid and
gaseous fuels, the furnace is already propor-
tioned for this function. Similarly, the required
piping, combustion co&ols, and fuel-firing
equipment are in place as part of oil or gas sys-
tems for unit warm-up. These fuels can be fired
to cairy full boiler load with little or no design
or equipment modifications.
Up to 20 percent or more of the total heat in-
put can be obtained from well-prepared solid
wastes burned in suspension. Biomass, sludge
and municipal refuse have all been successfully
suspension-fired in a PC-fired boiler. To burn
liquid or gaseous fuels in a stoker-fired boiler,
the firing equipment must be located relatively
I
Secondary-Air high above the grate surface to protect it from
Heater the radiant heat produced by the auxiliary
burners. For long-term operation, it may be
Fig. 4 A pulverized-coal-fired boiler rated 650,000 necessary to cover the stoker with refractory. For
Iblhr, 1550 psi9 and 955OF (82 kgls, 10.7 MPa gage short-term operation, undergrate air dampers
and 513OC)at superheater outlet are left partially opened to cool the stoker.
COMEvmON
BdIen forproees U s d P o w Production "

The stoker is ideally suited for firing unsized nace enclosure that eliminates refractory and its
solid fuels other than coal, as shown in Table II. attendant maintenance problems.
Normally, biomass, sludge, or refuse can sup- Complete furnace sidewalls, with inlet and
plement the coal with only a minimum amount outlet headers shop-welded to the fusion tube
of additional equipment. Also, in a stoker-fired panels, are available whenever maximum shop
boiler, the total heat input can come from a assembly is desired. Also included are seal
larger percentage of waste fuels than in a PC- boxes, miscellaneous attachments and insula-
fired boiler. tion pins.
The drop-bottom furnace of the W - 4 0 may
THE C-EVU-40 BOILER be designed for any vertical dimension and may
include a corner tangential-firing system with
The C-E Type VU-40 boiler (Fig. 4) is afield- either fixed or tilting nozzles, the latter to assist
erected, top-supported, single-gas-pass, ther- in achieving steam-temperaturecontrol. It also
mal circulation,. two-drum boiler. Its features may have a horizontal fuel-firing system in the
make it particularly suitable for the range of front or rear walls or may be fired by a mechani-
steam and'fuel conditions of both large indus- cal stoker either alone or in combination with
trial and small central-station installations. other types of firing equipment.
Boiler applications cover steam capacities from
100,Oooto 1,000,000l b h (13 to 125 kgls), de- CIRCULATION
sign pressures from 200 to 1800 psig (1.4 to Fig. 5 shows the circulation of water and
12.4 MPa gage), and design steam temperatures steam in the VU-40 boiler. A high furnace and
from saturated to 1005OF (541OC). Virtually any large unheated downcomer pipes provide a
solid, liquid or gaseous fuel can be fired. thermosyphonic circulation effect resulting in
DESIGN FEATURES liberal water flow to the furnace waterwall
The W - 4 0 is produced in sizes and types for tubes' The steam-water mixture the wa-
every capacity, pressure, fuel, space condition, terwall tubes is conveyed to the steam drum
or method of firing encountered in municipal through (1) the furnace roof tubes, (2) the relief
and industrial power and steam plants. It can tubes from the sidewall upper headers and (3)
be arranged for tangential, horizontal, or stoker the front-row tubes in the main boiler bank.
firing of single and multiple fuels. Steam-drum sizes vary from 54 to 78 in.
11370 to 1980 mm) inside diameter, with suit-
FURNACE ible internals of the baffle or centrifugal type
Completely water cooled, the VU-40 furnace (Figs. 6 and 7) to separate the steam from the
uses welded tube panels which are constructed water. As it leaves the drum and flows to the su-
with 2x12-in. (64-mm) outside-diameter tubes perheater, or to the main steam line-in the case
on %in. (76-mm) centers joined by %-in. (13- of saturated-steam units, the steam has ex-
mm) wide fins or fusion-welded webs. This tremely low moisture content and is conse-
construction forms an air- and gas-tight fur- quently quite pure.

Table 11. Supplemental Waste Fuels Suitable for Firing with a Spreader Stoker
Fuel Waste Fuel% Sbing Max. Moistun? Limiting Factor
Biomass 100 1OO0h<6" -55% None
Shredded rubber 10-20 1"XI"x1/4" - Smoke caqmer, emissions
Dried sludge 20-30 100% < 2" 75% Fouling, erosion, carryover
CObLBUSTION
Boilers for Process UsdPower Production

F~nalStage

continuous'
Blowdown Piping

m
-
Fig. 6 Steam drum internals baffle type

*Fig. 5 Circulation system on a C-E VU-40 industrial


boiler

TOP SUPPORT

VU-40 boilers are top-supported from a


structural-steel grid above the unit, with provi-
sion for lateral and downward expansion. The
furnace section and superheater are suspended
from the grid by hanger rods, while the boiler
section is hung from two large-diameter U-
bolts that cradle the upper drum. The structural
steel which supports the grid also supports
auxiliary equipment, platforms, and walkways.
Suspending the boiler from structural steel per-
mits use of a drop-bottom furnace with a fur-
nace height that is independent of t h e
boiler-bank height.
The boiler size and structural support ar-
rangement necessitate field erection. However,
a number of components other than the wa-
terwall panels, such as superheater assemblies, -
Fig. 7 Steam drum internals perforated centrifugal
economizers, air heaters, fuel-burning equip- type
C O ~ O N
Boikn tor Pmwsa Use/PowerProduction

ment, and ductwork, can be shipped with vary-


ing degrees of shop preassembly in order to Table 111. Fuels and Burning
facilitate erection and to reduce costs. Equipment
Fuel Burning Equipment
SINGLE-PASS CONVECTIONSURFACES
Fmnt Tangential
Pendant platen and spaced superheaters in Fuels P i g firing Stoker
combination with the baffleless boiler bank Gases
result in a single-pass crossflow arrangement of Natural gas X
heat-transfer surfaces. The vertical tubes are ar- Refinerygas X
ranged in-line to facilitate inspection and **Carbon .
cleaning. Tube sizes and spacings can be varied monoxide X
to achieve the highest possible heat-transfer *Blast furnace
rates with the least potential for gas-side foul- gas X
ing. This convection heating-surface arrange- Coke oven
ment is especially suitable where the flue gases gas X
contain high dust loadings. Because there are Hydrogen X
no baffles on which to concentrate and stratify Liquids
the d&or flyash, the likelihood of gas-side Oil X
plugging and-tube erosion is substantially re- Tars X
duced as compared to multi-pass convection Pitch X
surfaces. It also has an inherent low draft-loss *Waste sulfite
characteristic because of the lack of gas turns. liquor
Installed across the entire furnace width, su- Black liquor
perheater surface takes advantage of the uni- "Liquid wastes X
form distribution of combustion gases as they Solids
leave the furnace. Superheater assemblies are Coal X
supported from their respective inlet and outlet * *Shredded tires
headers located outside the gas stream above Biomass
the furnace roof. The superheater headers, in * *Sludge
turn, are supported by hanger rods attached to Unsized refuse
the internal grid steel. Sized refuse
* Usually burned with supplementary fuel.
FUELS AND FIRING EQUIPMENT * * Always burned with supplementary fuel.

Diversity of fuels and fuel-firing systems typ-


ifies industrial steam generation. All grades of Fig. 8 illustrates lower-furnace variations for
conventional fossil fuels-plus numerous by- different types of fuel-burning equipment. The
product andlor waste fuels-have been fired in water-cooled furnace bottom can be equipped
industrial units. The list of waste fuels is ever- with a dump grate, as illustrated in Chapter 12,
growing with the decreasing availability and in- to insure complete burnout of relatively large
creasing cost of fossil fuels. The list also is fuel particles of biomass or sized municipal
affected by the increasing difficulty and ex- refuse when these fuels are fired tangentially
pense in disposing of industrial and municipal in suspension.
waste materials in an ecologically acceptable With the C-E tangential firing system, two or
manner. The versatility of the top-supported more of these fuels can be burned in combina-
drop-bottom furnace to accommodate all types tion, which is especially desirable if one fuel is
of fuel-burning equipment permits the burning a waste material of insufficient quantity to meet
of a wide variety of fuels as shown in Table 111. steaming requirements or is of a low calorific
CO~u5l'iun
Boilen for Process Use/Power Production

. .

Water-Cooled
Hopper Bottom

S t o k e
0
Stoker Grate i,
0) '

Water-Cooled
Hopper Bottom ,
with Dump Grate

Fig. 8 Lower-furnace variations of the VU-40 boiler

value or high-moisture content so as to require


supplementary firing.
Fig. 9 illustrates a 500,000 lblhr (63 kgls) VU-
THE C-E RADIANT BOILER
40 boiler installed in a paper mill. The boiler The C-E radiant boiler (Fig. 10) is a field-
can fire pulverized coal, heavy oil, and natural erected, top-supported, single-gas-pass, ther-
gas through the tilting tangential firing system. mal circulation boiler designed for industrial
A row of nozzles located in the front wall di- and small central-station applications for the
rectly below the tangential windboxes, intro- 1800-psig (12.4 MPa gage) or higher-pressure
duces a mixture of 65-percent moisture sludge steam cycle. The size ranges from 400,000 to
and 50-percent moisture woodwaste for flash over 4,000,000 lbhr (50 to over 500 kgls) for
drying and partial suspension burning. The fir- non-reheat steam cycles requiring steam tem-
ing system also includes a continuous-ash-dis- peratures of 1000F (538OC) at the turbine.
charge stoker to burn stoker coal and future This radiant boiler is designed primarily for
woodwaste through combination distributors pulverized-coal firing, but waste fuels such as
- located on the lower front wall. The tilting tan- sawdust, sewage sludge, or prepared municipal
gential fuel nozzles, supplemented by an inter- refuse can be fired in combination with the
stage spray desuperheater, make it possible to coal. An economizer section is substituted for
achieve the design steam temperature of 900F the boiler bank to facilitate efficient heat trans-
(482C) with many combinations of fuels. The fer when operating at 1850-psig (12.8 MPa
location of the tangential windboxes, posi- gage) or higher superheater-outlet pressure.
tioned high in the furnace, affords protection to Welded-wall construction and external pipe
the grate should there be occasion to burn downcomers complete the circulation system.
heavy oil or pulverized coal alone. Not only In addition to the above type of boiler, there
does the stoker provide the flexibility to burn are many reheat-cycle steam generators produc-
stoker-quality coal to 40 percent of full boiler ing electricity for large industrial firms, partic-
load, but it also provides retention time in the ularly those involved in the production of basic
furnace to completely combust any oversized or metals. These units are identical to those de-
high-moisture sludge and woodwaste pieces scribed in the previous chapter and are found
that fall to the bottom of the furnace. in sizes above 100 MW.
COLdemnON
Bdhrr for Pmce8s UWPowerProduction

Fig. 9 VU-40 boiler for a paper mill, for pulverized-coal, stoker-coal, heavy oil, suspension-fired wood waste
and sludge, future natural gas and stoker wood waste
COMBUsnON
Boilers for Process Use/Power PducUon

Fig. 10 Pulverized coal-fired radiant boiler, rated 800,000 Iblhr, 1850 psig and 1005F (100 kgls, 12.8 MPa gage
and 541O C ) at superheater outlet
COMBrnON
BdIem tor Pmcess Uur/Powf Production

cumferential butt welding without springing


THE C-E VU-60 BOILER adjacent tubes.
The W - 6 0 is a custom-designed boiler that SUPERHEATER DESIGN
is built from pre-engineered, modular compo-
For steam temperatures above 825F (440C),
nents (Fig. 11)and is used to fire clean liquid
the superheater is arranged in two stages, with
and gaseous fuels and many waste and by-
interstage desuperheating for control of outlet
product fuels. This bottom-supported, natural-
temperature. Multiloop pendant-type elements
circulation steam generator is available in
and a center connection in the large-diameter
capacities from 100,000Ibhr to 1,000,000 I b h
(13 to 125 kgls), design pressures to 1800 psig outlet header assure even distribution of steam
(12.4 MPa gage), and superheater-outlet steam throughout the superheater surface. The con-
temperatures to 1005OF (541OC). struction requires a minimum number of
Fig. 12 shows the VU-60 arranged for front- header joints. Superheater elements are sup-
ported from headers located out of the gas
wall round-burner firing. Fig. 19, later in this
stream above the furnace roof; these headers are
chapter, is an example of a tangentially fired
supported by furnace walls and drum.
VU-60 unit suitable for firing waste liquid and
.gaseous fuels in addition to natural gas-or oil. ACCOMMODATING SOLID FUELS
The VU-60 is most often designed for pres-
surized firing, without an induced-draft fan. When solid wastes must be burned along
The waterwalls consist of panels of 3-in. (76- with gaseous or liquid wastes, a modification of
mm) diameter tubes on 4-in. (102-mm)centers, the VU-60 modular boiler incorporates a con-
between which metallic fins are placed and tinuous-ash-discharge spreader-type stoker
welded, producing a completely tight furnace and is bottom-supported (Fig. 13). The VU-60s
("S" signifying a stoker-firing system) has a
enclosure. Insulation and lagging are applied
directly over the tube panels. This construction normal range of steam production between
virtually eliminates refractory maintenance be- 75,000 and 300,000 I b h (9 and 38 kgls) with
operating pressures up to 1550 psig (10.7 MPa
cause the only refractory material is the floor
tile and a small amount around the water- gage) at the superheater outlet and total steam
cooled burner openings. Also, tube replace- temperatures up to 955OF (513OC). 'Stoker coal,
ment in the welded wall is simplified because sludge, biomass or other cellulose fuels suit-
the 1-in. fin between the tubes allows cir- able for stoker firing can be burned. Supple-
mental oil, gas or other waste fuels are fired
a
with either tangential-firing system or front-
wall round burners.

FIRING REFUSE IN INDUSTRIAL


BOILERS
Chapter 2 included a discussion of munici-
pal refuse as a fuel. Its value as an alternate en-
ergy source is proportional to the effort spent in
"refining" or beneficiating it. And, to a certain
extent, the cost of the boiler that can burn a pre-
pared refuse will be inverse to the amount of
money spent on the removal of metals and glass
Fig. 7 1 Pre-engineered modular components of C-E and on the size reduction and homogenization
VU-60 field-erected steam generator - of the refuse.2-13
COMBUSIlO_N
Boilen for Process Use/Power Production

I I

Fig. 12 VU-60 unit with front-wall (round) burners for liquid and gaseous fuels

The following describes three distinctly dif- suspension firing of prepared refuse
ferent systems for handling and burning refuse, ~ ~ b l ~the boiler performance of
and the types steam-generating all three refuse systems when burning 600 U.S.
best suited for the specific method. The differ- tons/day (545 tonnes/day) of refuse. This
ent systems are: mance is for the boiler and emission-control
mass-burning of unprepared refuse equipment combined. When comparing com-
spreader-stoker firing of prepared refuse plete systems, the initial cost and power re-
colmlsnON
Bdkrr for h c o s s IhePower Production

quirements of all installed equipment mnst be


evaluated. Other factors such as revenue from
electrical power generated and products recov-
ered, as well as operation and maintenance
costs, must also be considered to determine the
true cost-effectiveness of the various systems.

MASS-BURNING OF UNPREPARED REFUSE


A major refuse-firing system (Fig. 14) is that
for the massiburning of unprepared refuse.
Usually residential and industrial wastes, this
refuse will be referred to as MSW (municipal
solid waste), as described in Chapter 2. As com-
pared to conventional biomass fuels, MSW con-
tains quantifiable amounts of heavy metals and
an unusually high concentration of sulfur and
chlorine. These fuel components dictate that
Fig. 13 C-E VU-60s bottom-supported stoker-fired the design requirements of MSW Steam genera-
boiler for firing liquid, gaseous, or solid fuels tors be extremely different from conventional

Table IV. Systems Comparisons*


Suspension
Spreader-Stoker Mass-Burning of Firing of
Firing of Prepared Unprepared Refuse Prepared
Refuse (RDF) Ww) Refuse
Fuel Analysis:
% By Weight
Carbon 34.00 26.47 34.00
Hydrogen 4.10 3.08 4.10
wFn 23.47 17.62 23.47
Nitrogen 0.50 0.45 0.50
Sulfur 0.23 0.15 0.23
Moisture 23.00 38.50 23.00
Chlorine 0.70 0.23 0.70
h h 14.00 13.50 14.00
Total 100.00 100.00 100.00
HHV, BTUflb. 5785 4500 5785
Steam Flow, L b h 205,000 150,000 210,000
Ekcess Air, O h 50 100 30
Efficiency, % 75.0 70.4 76.1
Temp. to FGCE, OF 350 400 350
FDIOFA Horsepower 340 545 335
ID Fan Horsepower** 300 420 295

600 U.S.tonstday of fuel fed to each unit;outlet steam conditions: 825OF TST,900 psig; 300F feedwater
** Includes flue-gas cleaning equipment m)
I
COMBUSIlON
BdIm for Process UsdPowerProduction I

Emission Control System -


r \
Scrubber Precipitator or

Ferrous Ash

Fig. 14 Flow diagram for mass-burning of municipal refuse

fossil-fuel units. The heating value of munici- complex chemicals within the flyash catalyze
pal solid waste can vary from 2,000 to 7,000 corrosion reactions involving the sulfur and
Btullb (4.7 to 16.3 MJkg) with a mean value of chlorine present in the flue gases. These sulfa-
4500 Btullb (10.5 MJkg). As a general rule, pro- tion reaction rates are also temperature-depen-
duction of a given quantity of steam requires dent. Therefore, the design of an MSW steam
that nearly 3 times as much MSW be burned as generator should attempt to reduce flyash car-
coal (by weight). Use of municipal refuse for ryover and maintain low metal temperatures.
energy production conserves the remaining Combustion Engineering employs a top-sup-
supply of fossil fuels and reduces an imposing ported, multiple-pass, natural-circulation
mountain of garbage threatening to overwhelm steam generator design to fire MSW (Fig. 15).
landfills. However, to insure an adequate life of The first gas pass is the furnace and is located
a boiler firing MSW, the designer must have an directly above the sloped mass-burning grate.
understanding of the impact of this non-homo- The second, third, and fourth passes contain re-
geneous fuel on the steam generator. spectively the evaporator, superheater, and
An MSW steam generator has an inherently economizer heat-transfer surfaces necessary to
unique design. The heterogeneous nature of achieve the specified steam conditions and
MSW requires long furnace residence time heat-absorption requirements. Currently, MSW
prior to flue-gas contact with heat-transfer sur- boilers are available in sizes up to 750 U.S. tons
faces in order to completely oxidize the fuel. (680 tonnes) of refuse per day. A waste-to-en-
Complete oxidation will also reduce the poten- ergy plant ordinarily will use two, three, or
tial for corrosive attack of the heating surfaces. more such steam-generatorunits.
Metal temperatures above 900"F (480 C) accel- Located at the front of the steam generators is
erate corrosion rates. As a result, the design of a large refuse storage pit common to all of the
the MSW steam-generator heat-transfer surfaces units. The pit is sized to provide for the proper
should maintain the metal temperatures below inventory of fuel, generally three-days storage
this value. Flyash which deposits on the heat- of the entire plant capacity. Refuse haulers
transfer surfaces as it leaves the furnace ini- dump the MSW either directly into the pit or
tiates a secondary corrosion reaction. The onto a tipping floor for fuel sorting before enter-
.* C O ~ O N
Bdkn tor Pm.# U s e P o w w Production
-
ing the pit. Positioned above the pit is a crane. non-combustibles (white goods, tree stumps,
Normally a clamshell or "orange-peel" type, engine blocks, etc.) from the waste stream if a
this crane is used both to charge the feed chute tipping floor is not used. The crane operator is
of the steam generators and to remove large generally located in an air-conditioned control

Auxiliary Burner

--
Fig. 15 Multiple-pass steam generator with CEIdb grate for mass-burning of municipal refuse
COMBUSPION
Boilers for Process Use/Power Pmduction

booth directly above the refuse pit. This allows carpeting. The varying size, moisture, and com-
the operator to observe the pit area and to visu- bustibility of each item require different
ally-inspect the fuel sent to the steam genera- lengths of time to burn. Therefore, the MSW fir-
t o r ( ~ for
) non-combustibles and hazardous ing system must provide sufficient agitation,
materials. Since MSW is a .highly heteroge- adequate exposure to oxygen, and long enough
neous fuel, the crane also mixes the fuel into a time within the combustion zone of the grate to
more homogeneous state. During this process, maximize fuel burnout.
the operator can detect non-combustibles and Normal operation of an MSW steam generator
other unacceptable components. Some oper- requires approximately 100-percent excess com-
ators stockpile paper and cardboard in a corner bustion air. This much air is needed to ensure
of the pit to be used if high-moisture fuel is de- that the heterogeneous MSW has sufficient air
livered, in order to balance the heating value of to efficiently oxidize the available carbon and
the fuel charged to thesteam generator. hydrogen. Combustion air is drawn from the pit
and enters the steam generator through one of
FUEL-FIRING SYSTEM
two places. Approximately 40 to 60 percent of
As illustrated in Fig. 15, the fuel fed to the the total combustion air is introduced through
charging hopper of the steam generator drops the grate surface and is called undergrate air
by gravity through the charging chute onto the (UGA). The balance of the combustion air en-
front of the grate. The charging chute is the ters through nozzles or ports above the stoker
transition from the charging hopper to the and is called overfire air (OFA).
steam-genekator furnace. During normal opera- The undergrate air can be preheated to aid in
tion the chute is filled with fuel. This head of the drying of the fuel on the grate. This is nec-
fuel provides the seal between the charging essary only for extremely wet MSW. A steam-
hopper and the furnace, preventing air infiltra- coil air heater after the FD fan is one method
tion. The charging chute is water-cooled to pro- used, because it provides the flexibility to pre-
vide equipment protection should burning heat the air as the fuel conditions warrant.
occur within this area. The chute is equipped The overfire air can also be preheated; how-
with a cut-off gate to provide a positive seal ever, cold overfire air is more dense; than hot
during boiler start-up and shutdown. A recip- OFA and will be able to penetrate deeper into
rocating ram feeder located directly beneath the the furnace. OFA nozzles are located in the fur-
charging chute controls the refuse flow rate nace front and rear walls above the top of the
onto the grate. This device regulates the quan- fuel bed; the OFA is pressurized to 20-30" WG
tity of MSW fuel fed to the grate for combus- (5 to 7.5 kPa) to ensure air penetration and pro-
tion. The ram feeder function is similar to a mote thorough mixing of the air with the vola-
fuel-oil flow-control valve. The feeder is oper- tile combustibles leaving the fuel bed.
ated hydraulically and the stroke length, speed,
FURNACE SECTION
and frequency can all be controlled and varied
independently of the grate controls. The furnace is composed of water-cooled
The CE/db grate, described in detail in Chap- tubes to form a gas-tight enclosure. Approxi-
ter 12, is sized for a heat-release rate of 270,000 mately 60 percent of the unit's steam capacity is
to 300,000 BTUlhr-ft2(850,000to 950,000 W/m2) generated within the furnace section.
based upon gross heat input. This low heat- Before introduction of overfire air, approxi-
release rate is necessary to provide for long resi- mately 15 feet (4.6m) above the grate surface,
dence time of the fuel on the grate, long grate there exist local reducing environments in the
life, and good carbon burnout. The fuel is ex- lower furnace. This is because of the incom-
tremely heterogeneous; at any time it can con- plete combustion of the volatiles driven off the
tain such varied items as cardboard boxes, tires, MSW fuel on the grate. From a thermal stand-
grass clippings, leaves, clothes, mattresses or point, carbon-steel tubing can be used in the
--
COL5WllON *-,
Boilers for Pmceas UseIPower Ptuduction

lower furnace since the tube metal tempera- purpose. First, it absorbs heat from the fl%e gas
tures are kept low by choosing operating pres- to generate nearly 30 percent of the steam ca-
sures in the range of 650 to 900 psig (4.5 to 6.2 pacity, while lowering the flue-gas temperature
MPa gage); corresponding furnace wall temper- to below 1200F or 650C (under clean condi-
atures are 500 to 550F (260 to 290C). How- tions). Second, the evaporator mixes the flue
ever, due to the reducing environment, some gas, promoting further oxidation and reducing
type of waterwall protection, such as a layer of stratification.
castable refractory, is required to physically The evaporator tubes are constructed of car-
keep the corrosive gases away from the furnace bon steel and are set on wide transverse spac-
waterwalls. ings, which-prevent particulate carried over
The refractory applied to the lower furnace from bridging between the evaporator assem-
waterwalls is high-conductivity silicon carbide blies. To prolong the life of the tubing, conser-
(Sic). This material, which provides excellent vative flue-gas velocities in the range of 15 to 20
heat-transfer characteristics, reduces waterwall ftlsec (4.5 to 6 mls) are used. Additional tube
slagging and is extremely erosion-resistant. thickness above ASME Code requirements pro-
With increased residence time in the furnace vides for extra corrosionlerosion protection.
and additional oxidation achieved with the Through normal operation, the furnace walls
OFA injection, the flue gases become more oxi- of the MSW steam generator will become
dizing, eliminating the need for refractory lin- fouled. This causes an increase in the flue-gas
ing of the upper furnace. temperatures entering the second pass. The
The furnace is sized to provide a low flue-gas evaporator acts as a buffer between the furnace
velocity and a low exit-gas temperature. A con- and the superheater, dampening out the tem-
servative velocity of 18 to 20 ft/sec (5.5 to 6 m/s) perature increases due to furnace fouling.
will provide long residence times and low par-
ticulate carryover. Less particulate carried over SUPERHEATER
into the second pass will reduce corrosion and
erosion of the evaporator tubing. A furnace exit- The superheater of this multiple-pass boiler
gas temperature of 1450F or 790C (under follows the evaporator section. The flue-gas
clean furnace-wall conditions) will limit the temperature entering the superheater should be
corrosion of downstream heat-transfer surfaces, below 1200"F (650OC) under clean conditions.
since the corrosion reaction rate is very temper- This low gas temperature entering the super-
ature dependent. heater provides for low metal temperatures and
Auxiliary fuel-firing equipment located in reduced corrosion potential, while still suffi-
the furnace can be used to warm the- boiler cient for superheated steam temperatures of
before light-off of the MSW; it can also main- 800 to 830F (425 to 445 OC). A corrosion allow-
tain exiting flue-gas temperatures at necessary ance is applied to the superheater tubing thick-
levels for proper performance of the emission- ness, and low flue-gas velocities between
control apparatus. 20-25 ft/sec (6 to 7.5 m/s) control erosion.
The design of the multiple-pass MSW steam

I SECOND PASS

As shown in Fig. 15, the flue gas leaves the


generator combines a number of mechanisms
that serve to reduce drastically the erosive and
corrosive nature of the flue gas before it enters
upper furnace, making a 180" turn through a the superheater. The two 180-degree flue-gas
waterwall screen section before entering the turns and the upstream evaporator section mix
second pass. The watercooled second pass con- the flue gas and- minimize CO stratification.
tains convective heat-transfer surface, called an The low velocities drop out a substantial por-
evaporator, arranged in serpentine tube bun- tion of the flyash into the hopper under the su-
dles. The evaporator surface serves a two-fold perheater. Therefore, less flyash deposition will
C 0 ~ ' X N
Bollnrs for Process Use/Powethdu~Wn

occur on the superheater tubing. Since the su- REFUSE-DERIVED-FUEL SYSTEM


perheater is not exposed to luminous radiation, The refuse-derived-he1 (RDF) waste-
the surface metal temperatures will be lower. to-energy system burns prepared refuse. The de-
Experience has shown that unit performance gree of ref;se preparation may vary from simple
degrades with time. This degradation must be removal of bulky material and shredding to an
accounted for in the initial boiler design. As the extensive processing system yielding a highly
unit begins to "season", the fouled heat-transfer combustible fuel. One type of processing
surfaces become less efficient and flue-gas tem- system, as illustrated in Fig. 16, is used in con-
peratures become elevated; the unit will then junction with the Rc-continuous-ash-dis-
have to be shut down for cleaning. Multiple- charge spreader stoker described in Chapter 12.
pass units can run for 4,000 to 5,000 hours be- The resultant fuel from such a system is nor-
fore elevated gas temperatures require such mally 100 percent less than 6 inches (150'mm).
shut down. To illustrate this: the flue-gas tem- 95 percent less than 4 inches (100 mm), and 50
perature entering the superheater may be percent less than 3 inches (75 mm) in size. The
1150F (620C) under clean conditions. After high heating value of spreader-stoker-fired RDF
4000 hours of operation, the temperature will can range from 5,000 to 7,000 Btullb (11.6 to
be approximately 1250F (675C). The 100F 16.3 MJkg). The ash content ranges from 5 to
(55C) increase must be taken into account 15 percent; the moisture content will be from
when selecting the superheater metallurgy and 20 to 30 percent by weight, subject to seasonal
desuperheater capacity. The advantage of the variation.
multiple-pass design is that the evaporator acts Unlike the MSW steam generator, the RDF
as a buffer between the furnace and the super- steam generator appears similar to a biomass or
heater, and limits the impact of the fouling on coal-fired unit with a stoker, as illustrated in
the superheater. This lengthens the time be- Fig. 17. The design features a large single-pass
tween outages, thereby increasing unit avail- furnace with pendant superheater surface lo-
ability and reducing maintenance costs. cated at the furnace outlet.
The RDF steam-generator system operates
ECONOMIZER in concert with a fuel-processing system. The
processing system takes raw refuse and elimi-
The final heat-recovery component of the nates a portion of the non-combustibles and
steam generator is the economizer. On a multi- sizes the resulting fuel. The prepared fuel is
ple-pass unit, the economizer is located in a then delivered into the furnace for combustion
non-watercooled pass following the super- on a stoker.
heater. The ductwork forming the walls of this
FUEL-FIRING SYSTEM
pass is of either carbon steel or low-alloy steel
depending upon the entering flue-gas tempera- Conveyors transfer the RDF from the fuel stor-
ture. The economizer is constructed of bare, in- age area to the steam-generator area. The RDF
line, carbon-steel tubes. The flue-gas velocity metering system is located at the front of the
entering the economizer ranges from 20 to 25 ft/ steam generator. A number of devices may be
sec (6 to 7.5 mls). Generally, the economizer is effectively used to meter the fuel. One such de-
sized to reduce the exit-gas temperature to vice is an auger bin. The bin is equipped with
about 400F (200C), suitable for optimum op- a series of screws at the bottom to regulate
eration of the flue-gas treatment and cleaning the flow of RDF into the chutes leading to the
equipment. The large heat duty required of the distributors. The distributors are a pneumatic
economizer may result in a steaming condition; type using high-pressure air to project the fuel
this will be determined in the design stage and into the furnace. Even distribution of fuel on
will affect piping and steam-drum internal the stoker is essential for efficient operation of
arrangements. the unit.
C O ~ O N
Bolkn forhcess Use/Power Production

Receiving Ferrous Material Secondary


ondary
a& storage
Storage MagnetOo 1 Shredder

Ref use
Residue
I I Storage I

Emission Control System


T
\
s
Precipitator or
Fabric Filter
)+Metering

Stack

F&J. 16 preparation system fo7 spreader-stokerfiringof refuse-derived f "el

The stoker is sized for a 750,000 to 800,000 produce proper penetration into the furnace.
Btulhr-ft2 (2,370 to 2,520 kW/m2) grate heat- The UGA and OFA are normally preheated so
release rate based upon gross heat input. This is that all of the combustion air passes through
slightly more conservative than a normal the air heater to increase u n i t t h e r m a l
stoker-fired boiler burning wood because of the efficiency.
potential for clinkering and slagging of the
FURNACE
non-combustible ash on the grate. It also results
in less slagging on the lower furnace walls. The furnaces of the first-generation RDF
Combustion air is introduced as either under- steam generators were designed with the same
grate air (UGA) or overfire air (OFA) as on an criteria as conventional biomass units. This re-
MSW unit. Normal operation of an RDF steam sulted in units that were far too small for the
generator is with 50- to 60-percent excess air. desired output. When operated at their rated
About 50 to 70 percent of the total combustion maximum capacities, the units experienced se-
air is introduced as UGA with the balance being vere plugging, erosion, and corrosion. These
OFA. One method of introducing the OFA is problems demonstrated that an RDF unit needs
through four separate windboxes located in the its own unique set of design guidelines.
corners above the stoker. The tangential OFA The furnace of the unit in Fig. 17 is com-
system promotes horizontal mixing and mini- posed of water-cooled tubes forming a gartight --
mizes flue-gas stratification thereby improving enclosure. The tubing is carbon steel, with typ-
combustion. Such a system will use an OFA ical operating pressures in the range of 850 to
pressure of about 10 to 12" WG (2.5 to 3kPa) to 950 psig (5.9 to 6.2 MPa gage).
COMBUSTION
Bdlers for Pmcess Use/Power Pdilctlon

Fig. 17 Single-pass steam generator with C-E RC grate for burning refuse-derivedfuel
.-
--
The furnace is sized for a conservative com- parallel-flow arrangement is most often used in
bustion rate of 12,000 to 15,000 Btulhr-ft3 the first stage to lower the metal temperatures; a
(125,000 to 155,000 W/m3) and a flue-gas tem- counterflow arrangement will experience
perature entering the superheater of approxi- higher metal temperatures but will also maxi-
mately 1550 to 1600F (840 to 870C). These mize heat transfer. The decision as to which ar-
criteria are more conservative than conven- rangement to use must be made based upon the
tional biomass-unit designs with values of particular steam-temperature control range re-
20,000 Btulhr-ft3 (205,000 w/m3) for combus- quirements.
tion rate and approximately 1700 to 1800F BOILER BANK..'
(925 to 980C) gas temperature entering the su-
perheater. The low combustion rate provides Following the superheater is the next heat-
approximately 40 percent more furnace volume recovery component, the boiler bank. This sec-
than a biomass-unit allowing more retention tion acts as a heat sink to reduce the flue-gas
time for gas mixingand complete combustion. temperature to below 850F (450C) so that the
In the RDF steam generator, the first heat- backpass of the steam generator does not need
transfer surface is normally the superheater, but watercooled walls. The boiler bank contains a
may in some cases be waterwall screen surface. steam-water mixture; the heat it absorbs gener-
The furnace is sized to meet the conservative ates approximately 30 percent of the steam ca-
combustion rate; however, this may not provide pacity of the unit.
the desired flue-gas temperature entering the The drum centerline distances and tube spac-
superheater. The addition of waterwall screens ings may be varied to provide for a maximum
before the superheater is a means to drop,the velocity entering the boiler bank of approxi-
flue-gas temperature entering the superheater mately 30 ftlsec (9 m/s). A minimum clear
without increasing furnace height. The screens space of 2112 in. (65 mm) is recommended be-
also act as a buffer to maintain the gas tempera- tween the boiler tubes perpendicular to the gas
ture entering the superheater after dirtying of flow. An erosion/corrosion tube-thickness al-
the furnace takes place, similar to the action lowance above the ASME Code-required thick-
of the evaporator tubes in an MSW unit. ness can be used to extend tube life.
The screen assemblies are placed on wide
HEAT-RECOVERY EQUIPMENT
transverse spacings and the tubes are tangent
in the direction of gas flow to minimize Economizers for RDF units are the in-line
ash deposition. bare-tube type. Carbon-steel tubing is used be-
cause of the relatively low gas temperature. A
SUPERHEATER
transverse clear spacing of at least 2 in. (50 mm)
To reduce metal temperatures in the super- is provided to maintain an entering velocity of
heater, it is located above the furnace nose arch about 35 ftlsec (10.5 d s ) to minimize erosion
to shield it from the direct radiation of the fur- and reduce the potential for pluggage. Again,
nace. The flue-gas velocity entering the super- thickness above that dictated by the ASME
heater is about 25 ftlsec (7.5 mls) to minimize Code is recommended to prolong tube life. The
erosion. The superheater may be either a one- economizer should be arranged in banks separ-
or two-stage design depending upon the outlet ated by large access cavities for maintenance ac-
steam conditions specified. The two-stage cess and sootblower locations. Rotary
design is normally employed for outlet steam sootblowers are used due to the low flue-gas
temperatures above 725 OF (385"C) and incor- temperature encountered in this area. Counter-
porates an interstage desuperheater for final flow of water to flue-gas maximizes heat trans-
steam-temperature control. The two stages may fer. Depending upon the incoming feedwater
be arranged in either counterflow or parallel temperature and the exit-gas temperature speci-
flow of steam with respect to flue-gas flow. A fied entering the flue-gas cleaning equipment,
COMBUSIlON
Bollers for Process Use/Power Production I

this may be the final heat-transfer surface. For this firing system, boilers able to burn up
Otherwise, a tubular or regenerative air heater to 1500 U.S. tonstday (1360 tonnes) of refuse
will be the terminal heat-recovery device. can be designed for steam conditions to 825OF
(440C) total steam temperature. Once again, -
SUSPENSION FIRING OF PREPARED REFUSE the total-steam-temperature limitation is im-
For suspension firing, refuse must be re- posed to avoid excessive superheater corrosion
duced to a maximum size of 2 in. x 2 in. (50 which increases significantly as the tube metal
mm x 50 mm) so that it burns uniformly in sus- temperatures approach 900" F (480C).
pension. Such size reduction also allows pneu- The superheater temperature limitation ap-
matic conveying to the furnace. plies to 100-percent refuse-fired boilers regard-
Fig. 18 illustrates a typical preparation sys- less of the type of firing systems used. In units
tem for suspension firing. C-E uses its tangen- deriving 20 percent or less of the total heat from
tial system for 100-percent suspension firing. refuse when fired in combination with pulver-
As described in Chapter 12, the refuse and ized coal, the superheater metal temperature
heated air are directed tangent to a circle in the may be higher without developing excessive
center of the furnace. Fuel and air are mixed in corrosion rates. It is believed that the reduced-
a single fireball, aiding in even distribution corrosion rate with PC firing is a result of the
wfthin the furnace. The lighter fraction of the neutralizing effect of the coal ash in combina-
refuse quickly burns in suspension. The larger tion with the reduced refuse-fuel quantity.
and more dense refuse material will not remain
FURNACE AND CONVECTIVE SYSTEM DESIGN
suspended'by the air and will fall to the furnace
bottom, where a grate is provided to complete The furnace of a suspension-fired boiler is
the combustion of this material. Several rows of sized for a gas temperature at the superheater of
tangentially directed air nozzles are located be- 1600F (870C)to avoid ash build-up and plug-
tween the fuel compartments and the stoker. ging of the convective heating surface. The con-
These nozzles maximize the suspension burn- vective surface must therefore be designed with
ing of the heavier refuse material as it falls to wide tube spacing so ash build-up between
the grate at the furnace bottom. sootblowing cycles cannot bridge from tube to

Emission Control System

Fig. 18 Preparation system for suspension firing of municipal refuse


.-
COMBUSRON
Boilem lor Plocess Use/Power Pmdudon
-
tube. In-line tube arrangements will assure the fuel gases with heat contents higher than 500
cleanability of all tube surfaces using retract- Btulcu ft (18.6 MJ/m3) are easily handled by
able sootblowers. burners of the same type as used for natural gas.
When it is not possible to lower the flue-gas With gases of heating value less than 250 Btul
temperature of the boiler bank to about 600F cu ft ( 9 . 3 ~ J / m ~
consideration
), should be given
(315"C), an economizer cools the combustion to firing systems of high volumetric capacity,
gases. The final heat-recovery equipment is an such as tangential firing.
air preheater designed to provide the optimum The large percentages of inert gases or dust
temperature for the gas-cleaning equipment. carryover differentiate waste gaseous fuels from
natural gas and from each other. Most problems
involved with these gases are typified in the
BOILERS FOR FIRING handling of steel and copper reverberatory
BYPRODUCT FUELS gases, blast-furnace and open-hearth furnace
+ - Many boilers used for process purposes and gases, catalytic-cracker regenerator gas, and
power production can be designed to fire waste gases from cement kilns. The degree to which
byproduct fuels in order to the inerts are present, and the quantity, size,
and character of the solid, strongly influence
reduce disposal cost the boiler design for a given application.
meet environmental requirements, or
BOILERS FOR BLAST-FURNACE GAS
reduce usage of high-cost prime fuels
Blast-furnace gas is a dust-laden byproduct of
The VU-40, VU-60, and shop-assembled the iron reduction process. It is valuable for its
boilers (described later in this chapter) have high carbon-monoxide content, which varies
a long history of being used in this ri3le. This widely with the furnace charge and affects the
section covers only a few of the many byprod- heating value of the gas, which can range from
uct fuels and their associated impact on steam- 65 to 110 Btu/cu ft (2400 to 4100 KJ/m3).
generator and firing-system design. Others The dust carried over is mostly iron oxide
are found in Chapter 8 of the 1981 Edition of which can foul gas mains, firing systems, boiler
COMBUSTION: Fossil Power Systems. furnaces, and convection heating surfaces. To
extend and improve availability of equipment,
CATEGORIZATION OF WASTE AND the blast-furnace gas may undergo as many as
BYPRODUCT FUELS
three stages of cleaning. The first stage is a sim-
Waste gases and byproduct fuels may be char- ple mechanical separation; the second, a pri-
acterized as solid, liquid, and gaseous in terms mary spray washing; and the third, either a
of the state in which they are fired. Data on more vigorous washing or an electrostatic sepa-
their chemical composition and calorific value ration. The dust load .after the first stage of
are included in Chapter 2. Solid waste fuels are cleaning may range from 5 to 8 grains/cu ft. (11
generally handled and burned in stoker-fired, to 18 grams/mk3).This is reduced to 0.3 to 1.0
fluidized-bed, or suspended-fuel-fired arrange- grainlcu ft (0.7 to 2.3 g/m3) in the second stage
ments: liquids, in atomized form. Except for and, in the final stage, to 0.005 to 0.01 grain1
special cases, these do not differ appreciably cu ft. (0.01to 0.02 g/m3).
from the handling of coal or oil. Gaseous waste Boilers designed for steel-making service
and byproduct fuels, on the other hand, may re- must be able to respond to very rapid load
quire special treatment. changes. When fired by blast-furnace or coke-
Relatively clean, and differing from natural - oven gas, they are further subject to quick

gases mainly in volumetric heat content, refin- changes in the availability of these fuels. For
ery gas and coke-oven gas require only minor this reason, a supplemental fuel is required.
changes in firing-system design. In general, The fuel must rapidly pick up load to maintain
COMBUSTION
Boilers for Pmcess UsdPowerPmductlon

continuity of steam-generator operation. coke deposited on the catalyst in the cracking


Unlike designs for fossil fuels, the design of a operation. It is accomplished in a regenerator, a
boiler for blast-furnace-gas operation involves large vessel in which compressed air circulates
many variables. As a first consideration, the- andscours the hot catalyst to burn off the coke
quantity of solid carryover in the gas may per- and return the catalyst to the reactor for reuse.
mit a unit which is as simple and as compact as For this cleaning, large quantities of air must be
those used exclusively for natural-gas or oil fir- raised to a pressure as high as 25 psig (170 kPa).
ing. Conversely, it may require a unit of large At the same time, to minimize compression
size, freely hoppered and provided with as costs and to keep the temperature within the re-
many soot-cleaning devices as a pulverized- generator to a level which will not destroy cata-
coal-fired boiler. lyst activity, the quantity of air is limited to the
Second, the low calorific value results in smallest amount that will effectively clean the
1500 to 1600 l b h r of combustion products for catalyst.
each million Btu fired (645 to 690 kg/hr per These combustion conditions produce an ap-
million joules fired). This compares with the preciable amount of carbon monoxide. This
850 to 950 l b h r of products per million Btu for gas, which may leave the regenerator at temper-
oil and gas (365 to 410 kghr per million joules) atures as high as 1125OF (610C), contains a
and 950 to 1050 l b h r of products per million large amount of sensible heat, although it may
Btu (410 to 450 k g h r per million joules) of coal have a heating value below 40 Btulcu ft (1500
fired. For a given evaporation, the quantity of kJ/m3) with a carbon monoxide content from
products passing through a boiler varies con- 4 to 10 percent. Unable to support its own
siderably as fuels are changed. This means that combustion under ordinary conditions, regener-
the control of the steam temperature for units ator waste gas, also called "CO gas'', requires
having high-temperature superheaters becomes a supplemental fuel such as refinery gas, oil,
a critical consideration. Design conditions are or natural gas.
made more difficult because of the erratic avail- Boilers have been designed to burn this re-
ability of the blast-furnace gas, which creates generator gas to supply steam at pressures and
the need to hold steam temperature constant temperatures suitable for power generation and
under conditions in which it would tend to process use. At the same time, these boilers
swing as much as 100F (5s0C) in seconds. reduce the potential for atmospheric pollution
This problem is normally handled by steam- by oxidizing the carbon monoxide and hydro-
temperature control devices such as spray or carbon content of regenerator waste gas. A tan-
gas-recirculation. gentially fired VU-60 boiler for burning this
There is an additional problem of handling gas is shown in Fig. 19.
the simultaneous burning of a number of fuels The main differences between boilers burn-
in the same furnace with blast-furnace gas. ing regenerator waste gas and conventional
Tangentially-fired units of the type shown in fuel-fired units stem from the nature of the gas
Figs. 4 and 19 can be adapted easily to fire and the fact that its full flow must be handled
blast-furnace gas along with several other fuels. by the boiler at all times. A conventional boiler
generally maintains a fixed fuel-air ratio
BOILERS FOR REFINERY
REGENERATOR GAS
throughout its load range and is capable of
wide variation within this range. On the other
In the petroleum-refining industry, one of the hand, a boiler handling regenerator waste gas
major processes for producing gasoline is cata- begins with a minimum steam output corres-
lytic cracking. It is necessary to regenerate the ponding to the minimum fuel fired for stable
catalyst continuously to maintain optimum out- and complete combustion. Steam output can be
put in steady-flow catalytic processes. The pro- varied from this minimum condition in only
cess of regeneration involves the removal of one direction, that is, upward.
.-
COh5USllON
Boilem lorPmcess UsePower Production

An important feature of the waste-regenerator ner positions assures positive ignition during
gas boiler is the use of fixed tangential firing. all operating modes.
The waste gas, stabilizing fuel, and air are di- BOILERS FOR SLUDGE
vided into several streams which are directed
from the corners of the lower furnace. Concen- The disposal of various sludges in boilers is
tration of the windboxes in the lower part of the receiving increased attention as conventional
furnace provides more heat for ignition as well sludge disposal methods become energy in-
as longer gas travel; location in quiescent cor- tensive and dumping is banned. There are a

I
Fig. 19 VU-60 unit with tangentialfiring system suitable for firing liquid and gaseous prime and waste fuels
COMBUSPION
- Bdlen for Process UsdPower Production

variety of sludges produced as process or sew- Fig. 20. Hot flue gas is taken from the boiler
age-treatment residue; they are very high in convection-bank outlet and routed to a flash
moisture content, and contain lignins, fibers, drier where it is used to reduce the moisture
- - combustible organic compounds and ash. It is content of the sludge. Moisture can be reduced
possible to dispose of most of them in solid- from 80 to 15 percent under optimum condi-
fuel-fired boilers. There can even be a net gain tions. The dried sludge and cooled gas at ap-
in heat delivered to the boiler; i.e., the chemical proximately 300F (150C) are separated in a
heat in the sludge exceeds the latent heat of va- cyclone. The dried sludge is conveyed pneu-
porization required to evaporate the moisture in matically to the furnace for suspension burning
the sludge. The quantity of sludge that can be and the cooled gas is ducted to the furnace
disposed of will be maximized by removing the where it is deodorized by the combustion pro-
greatest amount of moisture before delivering it cess. The high volatile, low fixed-carbon, and
to the boiler. If the moisture is removed me- low moisture contents of flash-dried sludge
chanically, the boiler thermal efficiency will be make this an ideal material for suspension
increased. burning.
Another way to maximize the quantity of BURNING OF SHREDDED RUBBER
sludge to be fired is by the incorporation of a
flash-drying system. This system is shown in Another category of solid waste fuels that are

I
Steam Drum- B
I , , i $?8oiler Tube Bank

Cage ill

L I
Fig. 20 Flash-drying and suspension-firing system for burning process or sewage sludge
COrnrnON
Boilem lor PlDcess 0s-r PmducUon

available is shredded rubber from scrap tires. Combined-cycle power plants for industrial
Rubber tires are a nuisance in that they work power-generation applications have much
their way to the surface in sanitary land fills so higher thermal efficiencies than conventional
they present a continual disposal problem. steam power plants with the same steam condi-
Shredding the tires solves this problem, but the tions. In general, the high thermal efficiency of
tires still add a considerable volume to our a combined-cycle plant can be economically
shrinking solid waste disposal areas. It has been exploited if liquid or gaseous fuels are readily
estimated that the tire scrappage rate averages available and the unit can be operated contin-
250 million tires a year. With an average heat- uously or operated on an interruptible basis at
ing value of 15,000 Btullb (35 MJkg), shredded least 50 percent of the time at full power. Chap-
rubber has a considerable potential as a fuel. ter 1 identified the four major classifications of
Currently, the most common method to burn combined cycles and their associated heat
shredded tires is by mixing them with biomass rates. The two most commonly used cycles for
or co,al to be fired on a spreader stoker. The up- industry employ unfired or supplementary
per limit for tires in this case is 15 to 20 percent fired heat-recovery steam generators (HRSG's).
on a weight basis. Supplementary fired heat-recovery steam
generators use firing equipment located in the
INCINERATION OF PULP-MILLWASTE exhaust gas stream in the boiler inlet transition
STREAMS
duct. Since gas-turbine exhaust contains 75 to
To reduce effluent discharge, various waste 80 percent of the oxygen normally found in at-
gases and liquids in pulp mills are often inciner- mospheric air, fuel may be burned without the
ated in the plant's steam generators. These can need for additional fresh air. By using duct
include total reduced sulfur (TRS) compounds, burners, gas-turbine exhaust temperatures can
stripper gas, liquid methanol, and turpentine. be increased to 2500 to 1600F (815 to 870C)
Most often, the quantities are small and can be with a consequent reduction in the oxygen con-
accommodated by modest changes in the fuel- tent of the exhaust gas from 15 percent to 11
firing system and its associated control and percent. Supplementary firing generally dou-
safety system. bles the steam output of the heat-recovery
boiler by providing a mechanism for varying
STEAM GENERATORS FOR steam production and matching process-steam
demand, independent of the gas-turbine elec-
GAS-TURBINE HEAT RECOVERY tricity production.
Gas turbines have been widely used to pro- Most applications of HRSG's to gas-turbines
vide standby or peaking power for electric utili- of greater than 20 MW generate steam at two or
ties, or for unattended service in remote three pressure levels. High-pressure steam (600
locations. As described in Chapter 1,the ther- to 1800 psig, or 4.1 to 12.4 MPa gage) usually
mal efficiency is low because of high exit-gas drives a steam-turbine generator. Intermediate-
temperatures (800 to 1000F, or 425 to 540C) pressure steam (200 to 400 psig, or 1.4 to 2.8
and high excess-air levels (220 to 300 percent) MPa gage) is used for process steam in a plant
in the combustion products. The thermal en- or is injected into the gas-turbine combustor to
ergy remaining in the exhaust gas can be recov- reduce NO, emissions. Low-pressure steam (5
ered in a heat-recovery boiler to produce psig to 120 psig, or 35 to 825 kPa gage) is used
additional electricity using a steam-turbine for plant processes or feedwater heating in a de-

- generator. The combined output of electricity


from-the gas turbine and the steam turbine is
- 30 to 50 percent greater than that obtained
aerator. An increasing number of installation~
induce intermediate-pressure steam for addi-
tional power recovery in the low-pressure
from the gas turbine alone, with no additional stages of a steam turbine. Certain gas-turbines
fuel input. can accept steam into the power turbine to en-
Boilers for Pmess Use/Power Production

hance power output when plant steam demand BOILER CONFIGURATION


is low, but electrical demand is high. The heat-
recovery steam generator may also incorporate Waste-heat boilers in gas-turbine exhaust ser-
additional water-heating sections for conden- vice can be configured with gas flow in the hor-- .-
sate preheating or for high-temperature water izontal or vertical direction. Vertical gas-flow
for fuel heating or other plant processes. units permit an arrangement of equipment in
In some locations, air-quality authorities the exhaust flow path that occupies less floor
have imposed very stringent requirements for space but requires extensive steel support struc-
NO, emissions from gas turbines. In many ture. Horizontal gas-flow units generally cover
cases, these requirements virtually mandate the a greater plan area, but afford much better ac-
use of NO,-reduction catalysts in the turbine ex- cess for maintenance of boiler parts, duct burn-
haust steam. These catalyst assemblies operate ers, catalyst elements, and other equipment
in a narrow temperatufe range that is lower than that may be associated with the HRSG.
the turbine exhaust-gas temperature. The pres- Boilers with vertical gas flow usually employ
ence of an HRSG is an asset in the strategy to horizontal tubes connected by return bends
control emissions since the NO,-reduction cata- with the tubes supported at several locations
lyst may be located in the appropriate tempera- along the length of the tube by tube sheets, as
ture zone between sections of heat-exchange illustrated in Fig. 21. Most of these applications
surface in the boiler. require a circulating pump in the steam-gener-
ating sections of the boiler. The circulating
STEAM-GENERATOR DESIGNS pump ensures uniform distribution of water to
multiple parallel steam-generating circuits.
The basic principles for selecting heat-recov- Pumps are usually sized to maintain a circula-
ery steam-generating equipment are similar to tion ratio of 4 to 1 at the maximum steaming
those for conventional utility and' industrial condition.
boilers. However, the designer must be aware of Boilers with horizontal gas flow use vertical
the entire system arrangement in order to intd- tubes connected to headers at the top and bot-
grate the steam generator properly within the tom (Fig. 22). The tube and header assemblies
overall plant. Although cycle efficiency and may be either top-supported or bottom-sup-
economics generally determine the basic cycle ported. Although the tubes are self-supporting
conditions, the designer is typically faced with in the vertical direction, lateral restraints are re-
a matrix of conditions which determine the op- quired to control gas-flow-induced vibrations.
timum design. These conditions include a Natural circulation in the steam-generating sec-
wide range of thermal performance parameters, tions provides high circulation ratios without
dictated by varying ambient conditions and the use of pumps.
steam load requirements, limitations on capital A simplified flow diagram (Fig. 23) for a
cost, and restrictions on available space. In pur- triple-pressure HRSG illustrates the way in
suing a solution to the demands of a specific which heat-absorbing sections operating at
application, three aspects of the-boiler design certain temperature levels are located in the gas
process dominate: (1) extensive use of exter- stream to minimize the amount of heat-transfer
nally finned tubing for maximum convective surface required. There are ten discrete heat-
heat recovery, (2) an emphasis on low gas-side exchange sections distributed in descending
pressure loss to limit the gas-turbine fuel-rate order based on the gas temperature available
penalty associated with increased backpressure and the fluid temperature requirements. Note
on the gas turbine, and (3) distribution of heat- that the intermediate-pressure generating
recovery surface in multiple sections to achieve bank and economizer sections are intermeshed
optimum heat transfer at each temperature level with sections of the high-pressure economizer
through the boiler. to optimize boiler performance.
CO-ON
Boilers for Pmcess UsePower PfvducUon
-

Economizer Section

Evaporator Sections

Superheater Section

as Turbine ~xhabst
- -

Fig. 21 Unfired steam generator for recoveringheat from gas-turbine exhaust

The two critical temperature differences that peratures. Current HRSG economizers have
influence the amount of heat-transfer surface approach temperatures in the 15 to 25F (8 to
and the overall steam generated at each pres- 14C)range at the design point. Many other op-
sure level are the: erating conditions can occur at off-design
Pinch point: The difference between the gas points, including start-up. Some conditions
temperature leaving an evaporating section and will result in steaming at the exit of the econo-
the temperature at which boiling is occurring mizer, such that it acts as evaporative surface.
(saturated-water temperature). Specific provisions to accommodate steam-
Approach temperature: The difference be- ing at levels up to 5 percent of total flow in an
tween the saturated-water temperature in an economizer include: (1) careful control of water
evaporating section and the incoming feed- distribution in the last downflow passes of the
water temperature. economizer to cause that portion of the econo-
The pinch point strongly influences the mizer to behave as a forced-circulation evapora-
amount of heat-transfer surface in the evaporat- tor, or (2) configuring the last few passes of the
ing section. Current HRSG designs use pinch economizer as entirely upflow, with relief by
points in the 15 to 25 " F (8 to 14C) range. In natural circulation into the steam drum.
general, these boilers have 50 percent more sur- The triple-pressure HRSG temperature dia-
face in the evaporating section than boilers with gram shown in Fig. 23 illustrates the distribu-
pinch points of 40 to 50F (22 to 28C). tion of heat-exchanger sections and t h e
The approach temperature also influences associated temperature differences between ex-
the amount of surface required for an econo- haust-gas and water and steam temperatures.
mizer section, with exponentially increasing Pinch points can be observed as a relatively
amounts required for very low approach tem- small temperature difference at the right-hand
COMBDSTION
Boilen for P m e s s Usefpower Production

duct Burner

I I
Fig. 22 Horizontal-gas-flow heat-recovery steam generator with supplemental firing in duct
from gas turbine
COMBOStlON
Soilen lot Pmcess UsdPower Production

--- SteamMlater Temperatures


Gas-Turbine Exhaust Temperature
High-Pressure

ter
er

\
Percent Heat Transferred From Exhaust Gas LP Evap.

Fig. 23 Temperature profile of unfired heat-recovery steam generator with three operating-pressure levels

side of each evaporating bank section. Ap- sections and boiler casing sections, thereby al-
proach temperatures are illustrated as the dif- lowing the use of carbon steel casing plate and
ference between the water temperature leaving stiffeners, and minimizing the thermal growth
the last section of each economizer and the sat- of the overall boiler structure. A system of inter-
urated-water temperature. Note that the high- nal liner plates protects the insulation from gas
pressure economizer is divided into three flow. These plates are segmented for individual
separate sections to provide appropriate tem- thermal expansion and overlapped 'in the direc-
perature zones for the intermediate-pressure tion of gas flow. All boiler pressure parts are
superheater, evaporator and economizer. supported in ways that allow complete freedom
for thermal expansion relative to the casing and
TYPICAL CONSTRUCTION FEATURES
support structure.
The triple-pressure HRSG shown in Fig. 22
illustrates equipment normally included in the FIRED STEAM GENERATORS SUPPLIED
scope of supply of the boiler supplier: WITH GAS-TURBINE EXHAUST
expansion joint at gas-turbine exhaust inter- Normally containing 75 to 80 percent of the
face oxygen found in free atmospheric air, gas-tur-
single-blade exhaust diverter valve bine exhaust can concurrently supply to the
bypass stack with silencer furnace of a steam generator both sensible heat
inlet transition duct with flow corrective and oxygen for the combustion of a fuel. The
devices design and operation of such boilers vary con-
duct burner siderably, depending upon the ratio of the total
heat-recovery steam-generator modules exhaust flow to .the amount necessary for oxi-
steam drums dizing the supplementary fuel needed for a
access ladders and platforms given evaporation. Combustion air preheaters
exhaust stack are not used because of the already high level of
Insulation is placed on the inside of all duct preheat represented by the 700" to 900F (370"
Boilers for Process Use/PowerPruduction

Fig. 24 Boiler designed for supplementary firing in conjunction with gas-turbine combined cycle

to 480C) temperature of the exhaust gases. uate performance of combined-cycle boilers on


Supplementary-fired steam generators (Fig. the basis of stack temperature. The overall sta-
24) using most of the oxygen in the turbine ex- tion heat balance is determined using the cal-
haust are of the same design and size as units culated value of fuel fired in the boiler (rather
using outside air through forced-draft fans. The than boiler efficiency as such), in addition to
stack temperature on such a unit can be the fuel fired in the gas turbine.
dropped economically to within 100F (5s0C)
of the incoming feedwater temperature. Since HRSG'S FOR INCINERATOR GAS
the boiler is sized for a flue gas weight based
on fresh-air firing, a portion of the gas turbine Some firing systems for municipal refuse use
exhaust is by-passed. This portion of the ex- grates or rotary kilns in conjunction with re-
haust is cooled by passing over a separate steam fractory furnaces. In the past, quench chambers
generating bank, to the same temperature as the were often used to cool the gases before they en-
gases passing through the boiler, and then pro- tered the particulate-removal device. An alter-
ceeds to final heat recovery in the economizer. native is to incorporate a waste-heat boiler with
In such a cycle, gas-turbine and boiler sizes the capability to recover sensible heat in order
must be matched closely to obtain a high ratio to generate steam for power or process needs.
of feedwater flow to gas-turbine exhaust flow. Energy-recovery boilers designed for this
Because all gas-turbinehoiler applications purpose [Figure 25) include a water-cooled
involve the recovery of sensible heat, the usual chamber to reduce the flue gas to below its ash-
concept of boiler efficiency loses its signifi- softening temperature. The flue gas from the in-
cance. Customary practice, therefore, is to eval- cinerator will have the same physical and
Fig. 25 Heat-recovery boiler with water-cooled furnace for temperature reduction of gases from
refuse-fired incinerator

chemical properties as previously discussed for SHOP-ASSEMBLED BOILERS


refuse-fired boilers. Therefore, it is important
that conservative tube spacings, low velocities, The growth of oil and gas suspension-fired
proper erosion and corrosion tube-thickness al- shop-assembled boilers since their introduc-
lowances and other refuse-boiler guidelines be tion in the early 1950's has paralleled industry's
used diligently in the design of these waste- demand for higher capacities, pressures and
heat boilers. temperatures. The evolution of the boiler line
COMBUSIlON
Boilem for Process Use/PowerProduction
I,
I
I
I
I
1
i
I
I

I
I

!
1

Fig. 26 Size and capacity growth of the VP boiler

has been from 20,000 lb of steam per hour (2.5 ways possible or desirable to furnish the higher-
kgls) before 1950 to approximately 600,000 Ibsl capacity boilers in a single package. With
hr (75 kgls) in the late 1970's. As an example, higher capacity units it may also be desirable to
Fig. 26 shows the evolution of the VP (D type) use heat-recovery equipment which is shipped
boiler. Steam pressures and temperatures have as a separate package.
kept pace with this capacity growth, from the Most shop-assembled water-tube boilers use
saturated-steam conditions of the 1950's to to- thermal circulation and are designed for pres-
day's operating pressures of 1650 psig (11.4 surized firing. Shipping clearances determine
MPa gage) and steam temperatures of 950F the allowable height and width dimensions of
(510O C) . an assembled unit. Usually, the allowable ship-
As compared with a field-erected unit, the ping length is greater than can be effectively
most significant advantage of the shop-assem- used. One of the problems of the designer,
bled boiler is its lower installed cost. This dif- therefore, is to use the available height and
ferential comes from the development of width to best advantage.
standard designs with maximum use of stan- The burnerlfurnace design must be properly
dardized fabrication procedures and minimum coordinated, and burners have been developed
field-installation costs. specifically for shop-assembled boilers. Having
Shop-assembled boilers can be furnished a relatively narrow flame pattern, these burners
with integrated auxiliary equipment. The lower are designed to burn the fuel completely within
capacity units are shipped completely pack- the necessarily limited, though sufficient,
aged with fuel-burning equipment, safety and clearance dimensions from the burner center-
combustion controls, and boiler trim. m2ause line to the furnace walls.
of shipping clearance limitations, it is not al- Shop-assembled boilers typically use exten-
COMBUSION
Boilen for Process UsePower Production
--
sive water-cooled surface. This heat-absorbing in transit, and at the installation site. Perma-
surface that "sees" the flame determines the nent or detachable lifting lugs are provided to
temperature of the combustion gases leaving facilitate handling. Many oil- and gas-fired as-
the furnace. Liberal use of water cooling on the sembled units require only a suitably rein-
furnace walls, roof, and floor not only reduces forced-concrete slab or curb for foundation.
the furnace temperature but also minimizes fur-
nace refractory and its attendant maintenance. THE C-E VP AND A-TYPE UNITS
With a completely welded tube-wall enclosure,
A typical shop-assembled boiler configura-
the result is highly desirable uniform cubical
tion (Fig. 27) is the C-E VP, which is a D-shape
thermal expansion.
The amount of furnace volume or heat- design with a two-drum, vertical bent-tube
release ratelcu ft of furnace volume bears no di- boiler bank, and water-cooled furnace. These
rect relationship to the furnace exit tempera- units can be designed to generate as much as
tures; the amount of water-cooled furnace 600,000 pounds per hour (75 kgls) of steam.
The VP has welded-wall construction, un-
surface or the heat-release rate per sq ft or mZis
heated downcorners, and a combination radi-
the valid criterion for determining furnace con-
ditions. Typically, the furnace heat-release ant-convection superheater which produces a
flat steam-temperature characteristic. It can be
rates when firing oil and gas range from
rail-shipped in two sections for capacities up to
175,000 to 200,000 Btulhr-ft2 (550,000 to
630,000 W/mZ)of EPRS (effective projected ra- 240,000 lblhr (30 kgls); larger VP units are
diant surface). shipped over waterways on large barges.
Size and furnace configuration for these Another shop-assembled boiler is the A type
package boilers result in a ratio of radiant sur- (Figs. 28 and 29) which can generate as much
face to furnace volume which is greater than for as 300,000 pounds of steam per hour (38 kgls).
The A boiler is a three-drum design with one
the larger field-erected units. This permits con-
siderably higher furnace liberation rateslcu ft of upper (steam) drum and two lower drums. Its
symmetry makes the A design ideal for rail
furnace volume.
shipment because ballast is not needed. This
The need to limit gas-side draft loss usually
simplifies off-loading and handling.
determines the flue-gas velocities for gas- or
oil-fired shop-assembled boilers. Velocities can Both the A and VP designs have boiler banks
with a multiplicity of simple tube circuits start-
go as high as 100 fps (30 mls) and result in draft
ing at the lower drum(s) and terminating in the
losses of 10 to 15" WG (2.5 to 3.8 kPa).
Convection tube spacing is not critical in steam drum. Expanded tube joints have proven
most practical to connect these relatively close-
shop-assembled units as the f u d s generally
spaced tubes into the drums. One factor which
have little or no ash. However, the designer still
determines the thickness of drum tube sheets is
must be cognizant of peculiarities in certain fu-
the width of the ligaments between tube holes,
els such as high-sodium, high-vanadium resid-
as described in Chapter 6. To achieve the maxi-
ual oils which can form tacky deposits at
mum ligament efficiency and minimum drum
approximately 1100F (590OC). In this case,
thickness with these close-spaced tubes, the
tube spacing and sootblower arrangement must
tube ends are frequently swaged to a smaller di-
be properly factored into the design.
ameter in order to reduce the required tube-
The enclosing casing structure of shop-
hole size.
- base
assembled boilers, including- the integral
plate, serves several functions. It is designed to
HEAT-RECOVERY EQUIPMENT
eliminate objectionable gas leakage under
maximum pressure conditions. Also, it must Most shop-assembled boilers include equip-
have sufficient structural strength for the neces- ment to increase overall boiler efficiency and
sary handling and lifting during manufacture, save substantial fuel by recovering heat from the
COMBrnON
Boilen for Process Use/Power Production 1

Fig. 27 C-E VP, a D-type shop-assembled boiler I


t
flue gases leaving the generating equipment. In
most cases this heat-recovery equipment can be
shipped as a complete, but separate, package. ,
A counterflow arrangement of flue gas and
feedwater for an economizer, or of flue gas and
combustion air for an air preheater, results in
the most effective use of the heat-recovery sur-
face (see Chapter 6). With high-sulfur fuels, the
possibility of corrosion of the cold-end surfaces
should be considered, with either an econo-
mizer or an air preheater.
Because the gas-side transfer rate in an econ-
omizer is relatively low compared with water-
side rate, the metal temperature of the cold-end
of a counterflow economizer is only slightly
above the entering feedwater temperature. With
high-sulfur fuels, an economizer is usually not
advisable unless the feedwater temperature
exceeds 250F (220C).
The degree and frequency of partial-load op-
eration are most significant in establishing the
optimum air-heater selection. Packaged regen-
erative air preheaters are designed with revers-
ible and replaceable cold-end layers fabricated Fig. 28 C-E Type A shop-assembled boiler
-
ComWmN
Bdkn fur ~ O S Use/pow*r
s ProducUon

Fig. 29 Shop-assembled units like this A boiler are manufactured under controlled indoor conditions

of corrosion-resistant material to minimize fan overcomes resistances to gas flow through-


maintenance. out the boiler, whereas with many waste-heat
SHOP-ASSEMBLED WASTE-HEAT
units these resistances are overcome by an in-
duced-draft fan. The usually large volume of
Although applied primarily to fuel-fired gases to be handled makes dksignfor low draft
boilers, shop assembly is also applicable to losses desirable to minimize the power require-
-
heat-recovew steam generators and waste-heat ments of the ID-fan driver.
boilers. Unless there is some special consider-
ECONOMICS OF SHOP-ASSEMBLY
ation, such as auxiliary firing, these units are
built without a furnace preceding the boiler Installation of two or more shop-assembled
convection surface. units instead of a single large field-erected unit
The temperature of waste gas and the constit- aids in load flexibility and scheduling mainte-
uents in gas must be carefully evaluated in es- nance. Other factors such as limited available
tablishing the design of waste-heat boilers. The headroom for the installation of a field-erected
chemical analysis, dust loading, and slagging boiler, or much shorter delivery time for a shop-
characteristics all affect arrangement of the assembled unit, are also important consid-
boiler surface. erations. But the main reason to select
Because most oil- or gas-fired shop-assem- a shop-assembled boiler is its low overall
bled boilers are pressure fired, the forced-draft installed cost.
COMPmTION
Boilersfor Pmcess Use/Power ProducUon

Fig. 30 Type A boiler loaded on Schnabel car

Standardization is the key to reduced costs: and time. Most units require only a simple con-
most shop-assembled boilers are pre-engi- crete slab foundation. And, as the boiler is
neered. In setting up a line of standard boilers, shipped assembled, no erection space or mate-
it is necessary initially to consider all possible rial storage space is required at the site.
variables. Design conditions such as capacity
a n d operating pressure are varied in in- SHIPMENT
crements. Physical variables such as terminal
connection locations may be varied to some Smaller shop-assembled units have been
limited extent. shipped short distances by truck or in combina-
tion with rail. The development of new ship-
SAVINGS IN MANUFACTURINGAND ERECTION ping methods contributed significantly to the
Standarization of design, then, saves time rapid growth of large capacity shop-assembled
and money prior to actual fabrication of a shop- boilers in the 1970's.
assembled unit. But the greatest savings with The first VP boilers had a fixed cross section
shop-assembled boilers is in manufacturing. and achieved size flexibility by varying the
Standard shop-assembled boilers are built un- depth of the boiler. The cross section was lim-
der controlled conditions which permit a high- ited to standard clearances for American rail-
quality product at low cost (Fig. 29). The roads and permitted shipment in standard flat
enclosed assembly area is arranged for opti- cars to almost any location. Further investiga-
mum materials flow both of parts fabricated for tion determined that clearances to some loca-
individual units and for parts and materials to tions were larger. In addition, special railroad
be taken from stock. Likewise, delays from ad- cars were available or could be designed,
verse weather conditions are not encountered. among which is the C-E patented Schnabel
Aside from the obvious elimination of field (Fig. 30) to accommodate boilers up to 20 ft
erection costs, there are supplementary advan- high x 13 ft wide x 55 ft long (6m high x 4m
tages that further reduce the installation costs wide x 17m long).
-
--
Barge shipment has paved the way for deliv- Further description of HTW boilers is found
ery, to overseas and domestic markets, of shop- in Chapter 8 of the Third Edition of Combus-
assembled boilers with steam flows as high as tion: Fossil Power Systems (1981).
600,000 l b h (75 kgls). Any shop-assembled
boiler can be shipped by barge, since equip-
ment so delivered is generally not limited by PULP AND PAPER INDUSTRY
physical dimensions. Boilers up to 30 ft wide x
35 ft high x 70 ft long (9m wide x l l m high x CHEMICAL RECOVERY BOILERS
21m long) weighing up to 950,000 lb (430,000
kg) can be shipped on virtually any existing Although the chemical recovery boiler (Fig.
commercial waterway with available barge 31) shares its general appearance and many of
equipment. its physical components with power-boilers, it
is unique in the power-generation field in that
its purpose is twofold: the first is to recover in-
organic chemicals from black liquor to be recy-
HIGH-TEMPERATURE-WATER cled in the pulping process; the second is to
BOILERS combust the organic constituents in the black
liquor to produce valuable steam. The efficient
Heating systems using high-temperature recovery of the inorganic pulping chemicals
water (HTW) became popular after World War and the efficient generation of steam from the
11. These systems usually operate in a pressure chemical recovery boiler are both essential
range from 120 to 300 psig (0.8 to 2 MPa gage) elements in the economic and environmental
with supply temperatures to the distribution aspects of the kraft pulping process.
system from 350 to 420F (180 to 215OC). The THE KRAFT PULPING PqOCESS
higher temperature range affects cost because
water-flow rates and resulting pumping costs This is a chemically closed process that pro-
are reduced and system exchangers can be duces pulp for paper making from a variety of
made smaller. On the other hand, the lower organic materials. Wood is by far the most com-
temperatures permit lighter and less expensive mon source of pulp used with the'kraft process,
materials. although bagasse, straw and other nonwood fi-
High-temperature water systems are closed bers can also be used. The name kraft, from the
systems with makeup required only to restore Swedish and German word meaning strength,
water that leaks out of the system at valve stems, is a term often applied to sulfate mills, which
pump shafts, and similar packed joints. Obvi- produce long-fiber pulp for making high-
ously the average water temperature in the sys- strength paper.
tem varies depending on the load, and an
PRODUCING PULP
expansion drum permits expansion or contrac-
tion of the water volume. A small makeup Fig. 32 illustrates the pulp-making process.
pump automatically adds the necessary As the diagram shows, wood enters the haft cy-
makeup to hold the water level in the expansion cle at the digester for pulping. Within the di-
drum above a predetermined level. gester, sodium hydroxide and sodium sulfide
For heat consumers such as unit heaters, radi- dissolve the ligneous substances that bind the
ant panels, and coils of absorption refrigeration cellulose fibers of the wood together. The cellu-
equipment, HTW may be used directly. As with lose fibers, which form the pulp, resist the
steam, it is used indirectly for domestic hot action of the chemicals. In the cooking process,
water. 'low-pressure steam or low-pressure hot approximately one half of the wood substance
water, if required, may be produced in suitable is dissolved in the cooking liquor to form what
heat exchangers. is called black liquor. Two types of digesters are
- COMBrnON
8dIem for PIOC~SS
Usa/Power Ploductim

Fig. 31 C-E chemical recovery boiler


.-

8-43
COMBVSIlON
Roilem for Pmcess UsePower Pmductlon

Wood Chips - \
Slaker and
t
Ume Kiln

Water
Blow Tank
\ G m n Liquor
Storage

I
DhoMng
Ligwr Storage Tank ,
\ ~ollen'
Evaponlor
'.
Strong ~ i . c k
Cbmical
/
Re*vw
--4.L
Liquor ~tonga- F l u e Gas
!
Make-Up Salt Cake

Fig. 32 Principal processes in kraft pulping and chemical recovery

currently in use in the industry: the continu- sealed and raised to operating pressure and
ous-type digester and the batch-type digester. temperature according to a pre-determined
In continuous cooking, the system being in- schedule. Once the digester is at the proper
stalled in most new mills today, the chips are pressure and temperature, the charge is cooked
preheated in a steaming vessel before entering from two to six hours, depending on the grade
the digester. Pre-steaming removes air, non- of pulp desired.
condensible gases, and volatile constituents Direct steam injection is the most common
such as the terpenes. After entering the contin- method used to bring the batch digester to
uous digester, the chips are impregnated with cooking temperature, although for some instal-
cooking liquor at a controlled temperature to lations the heating is performed in part or en-
ensure uniform penetration of the liquor. After tirely by indirectly heating white liquor and
adequate impregnation, the temperature is recirculating it to the digester. Batch-type di-
raised to the cooking temperature of around gesters using direct steam heating require large
330" F (165"C) by indirect heating of circulated quantities of steam to,bring them to cooking
cooking liquor and is held there for about one temperature and pressure. As a result, mills us-
hour. The pulp is then quenched to about ing this type of digester have a heavy intermit-
260F (125"C) with wash liquor. In most cases, tent demand from the boilers compared to mills
diffusion washing which is then carried out in using indirect heating. Batch digesters are in-
the lower region of the digester removes a con- stalled in groups of at least three and operate in
siderable proportion of the spent chemicals. sequence, with each digester preparing 6 to 20
The wash temperature in the lower zone of the tons (5 to 18 tonnes) of pulp per cook.
digester is 175 to 185F (80 to 85OC). This en- After the cook, the mixture of pulp and spent
sures suitable blow conditions with little or no cooking liquor is discharged to the blow tank.
mechanical damage to the fibers. The next major step in the process is washing,
In batch cooking, the chips and cooking liq- in which pulp fibers are separated from the
uor are charged into the digester which is then black liquor. Most mills use countercurrent ro-
COMBUSPION
Boilen for Process Use/Power Pmduction

tary vacuum washers in which the pulp is is recuperated in the following effect. The va-
washed with progressively weaker black liquor por from the last effect is condensed and sent
and finally fresh water. More recently, continu- for treatment to the foul-condensate disposal or
ous diffusion washers have been used to com- recuperation system. Fresh steam is fed only to - - -
plement or replace rotary vacuum washers. the first effect and the clean condensate from
After washing, the pulp is further refined and is the first effect is returned to the feedwater sys-
subsequently sent for conversion into a final tem. Steam economies of up to 7.5 can be
product. The weak liquor which was separated achieved with multiple-effect evaporators; i.e.,
from the pulp goes on for further processing. for each pound of fresh steam supplied, 7.5
The kraft process is economically attractive pounds of moisture can be removed from the
because it is possible to recover and reuse the black liquor.
cooking chemicals, and to generate large quan- Modern installations have concentrators as
tities of steam and power from the dissolved part of, or following, the multiple-effect evapo-
carbonaceous matter in the black liquor. How- rator. Concentrators are specially designed
ever, the black liquor leaving the washers con- evaporators capable of raising the solids content
tains far too much water to be burned. The next of the liquor to the 65-75 percent level, which is
step removes most of this water. suitable for firing in the recovery boiler. Most
recovery boilers installed prior to the early
RECOVERING THE SPENT CHEMICALS
1970's used a direct-contact evaporator to con-
Water removal from the weak black liquor is centrate the black liquor. The operating princi-
accomplished in large multiple-effect evapora- ple in a direct-contact evaporator is that hot
tors. Before the black liquor can be fired in the recovery-furnace flue gases which make direct-
recovery boiler, the concentration of dissolved contact with black liquor evaporate moisture
solids in the black liquor must be increased from the liquor. The evaporated vapors are dis-
from an initial 16 to 18 percent to greater than charged to the atmosphere along with the com-
60 percent. In most mills, the black liquor bustion gases. Direct-contact evaporators have
is fired at a solids concentration of 65 to ,. been almost completely replaced by concentra-
75 percent. tors in performing the final concentration of the
Multiple-effect evaporators are used to raise black liquor.
the solids concentration of the black liquor The next step of the haft chemical-recovery
from the initial 16 to 18 percent to approxi- process takes place within the recovery boiler
mately 50 percent. An evaporator is a specially and involves five essential functions in which:
designed vertical heat-exchanger in which con- black liquor is prepared for firing,
densing vapor provides the heat required to carbonaceous matter is burned out,
evaporate moisture from the black liquor. A sulfur compounds are converted to Na,S,
multiple-effect evaporator consists of a series of
evaporator bodies in which the black liquor inorganic salts are smelted for removal, and
concentration is progressively increased in heat is efficiently recovered to produce
each of the stages or effects. The bodies and steam.
heat-exchange surfaces are designed so that the The hot smelt (inorganic salts) produced in
pressure drops successively from the initial the recovery furnace flows in a continuous
steam-supply pressure to a vacuum. The black stream into the dissolving tank, where it is
liquor generally flows countercurrent to the quenched and dissolved in weak wash to form
steam. Steam economy is achieved by taking "green liquor". This is a solution consisting
the vapor evaporated from the black liquor in mainly of sodium carbonate, Na,CO,, and so-
one effect and condensing it in the following ef- dium sulfide, Na,S. After the non-soluble mate-
fect. Therefore, most of the heat used to evapo- rials (dregs) are removed, the green liquor is
rate moisture from the black liquor in one effect pumped to the causticizing system in which
COMBUSPON
Bdlm for Pmcess Use/Fbwer Production

slaked lime, Ca(OH),, is reacted with sodium solids produced can vary from 5,000 t o 7,000
carbonate, Na,CO,, to produce a solution of so- Btullb (11.6 to 16.3 MJkg).
dium hydroxide, NaOH. The sodium sulfide in Obviously, the thermal process load which is
solution remains unchanged. After this treat- imposed on the recovery boiler depends on the
ment, the liquor becomes "white liquor" and is specific conditions in a particular mill and can-
returned to be reused as cooking liquor in the not be related to a nominal mill requirement.
digester. Thus, recovery boiler capacity must be related
The calcium carbonate sludge formed in the to the following factors:
causticizing reaction is converted to calcium dry solids produced per day
oxide in the lime kiln and is then hydrolized to percent solids concentration from multiple-
calcium hydroxide for reuse in causticizing effect evaporator/concentrator
green liquor to white liquor.
high heating value (HHV) of the dry solids
This completes the kraft cycle. The chemicals
needed for cooking are recovered and reused. elemental fuel analysis of the dry solids
Calcium oxide required for causticizing is re- A typical elemental analysis of black liquor
formed, and the dissolved wood substance is solids derived from a combined hardwood-
burned as a source of heat for steam and power softwood cook, in percent by weight, is
generation. Carbon 39.4
Hydrogen 3.6
PRODUCING POWER Sulfur 3.4
In most integrated pulp and paper mills, the Sodium 21.2
waste materials generated by the process fur- Inert Mineral Oxides 1.0
nish a large percentage of the total energy re- Oxygen 31.4
-
quired to produce steam and power. The Total 100.0
recovery boiler uses the heat energy from burn- High Heating Value 6,400 Btullb (14.9 MJIkg)
ing the carbonaceous matter in the black liquor, The above values were derived using the stan-
while the bark-fired boiler consumes other dard as recommended by the Technical Associ-
waste materials such as sawdust and planer ation of the Pulp and Paper Industry (TAPPI);
shavings, as well as bark from the debarking this procedure should be used as others may
drums. When more steam is required than is give varying results.
available from these waste streams, auxiliary
fuels can also be fired in the bark or recovery
boilers to increase their steam product into the BLACK LIQUOR FUEL PREPARATION
desired maximum continuous rating (MCR). Before the strong black liquor leaving the
MILL CAPACITY AND ITS RELATION multiple-effect evaporators can be introduced
TO RECOVERY BOILER CAPACITY into the furnace for burning, the liquor must
undergo several important changes.
The capacity of a mill is based on the tons of
If it is not already at the proper firing con-
pulp that are produced in 24 hours. A mill will
also produce a certain amount of spent chemi- centration coming out of the multiple-effect
cals, that is, black liquor solids. On an average, evaporator, the liquor must be concentrated to
3000 pounds of black liquor solids will be pro- sufficient strength for firing.
duced for each U.S. ton of pulp produced (1500 Ash in the precipitator and the
kg for each metric tonne). A 1000-U.S. ton (907- boiler hoppers must be returned to the incom-
tonne) mill will then produce about 3,000,000 ing liquor stream.
lb (1,360,000 kg) of dry solids per day --the ac- 8 Makeup chemicals must be introduced if not
tual quantity can vary plus or minus 10percent. added elsewhere in the process.
Likewise, the higher heating value of the dry 8 The liquor must be brought up to the proper
CObdBmTION
Boilers for P w e s s Useh'ower Production

pressure and temperature required at the spray compounds in the liquor so that odorous emis-
nozzles. sions from dire-ct-contact evaporators are
The final fuel preparation will be done dif- greatly reduced.
-
ferently depending on whether the liquor is at After the liquor passes through the oxidizer,
firing concentration as it leaves the multiple; i t i s pumped to the precipitator area. Ash col-
effect evaporator plant. lected in the precipitator is mixed into the liq-
uor stream in either of two ways. The ash can be
BOILERS USING DIRECT-CONTACT allowed to fall directly into the liquor as occurs
EVAPORATION in a wet-bottom precipitator, or the ash can be
Direct-contact evaporators are still commonly collected dry and conveyed from the precipita-
used on boilers burning very viscous black liq- tor to a chemicallash mixing tank, where the
uors such as those produced by bagasse pulp- ash is thoroughly mixed with the black liquor.
ing. Because of the direct contact of the flue The liquor is then evaporated to a firing con-
gases with black liquor, the sulfur compounds centration of about 68 percent solids in a cas-
in the liquor can chemically react with the car- cade evaporator by bringing hot flue gases into
bon dioxide in the flue gas to form foul-smell- direct contact with strong black liquor as
ing gaseous compounds which might then be shown by Fig. 34. The evaporator consists of
discharged into the atmosphere. To avoid the one or two wheels of rotating tube sheets be-
generation of odorous gases, the liquor in di- tween which are many horizontal parallel
rect-contact evaporator systems is first passed tubes. Part of the tubes are submerged in liquor;
through a black liquor oxidizer in which air or the rest are in the gas stream. Those that are in
oxygen is bubbled through the liquor (Fig. 33). the gas stream are completely coated with wet,
The oxidizer chemically stabilizes the sulfur dripping liquor. The slowly rotating cascade

Ox~d~zer
Vent Gas

Oxidizer Air

Black Liquor
at 50% Dry Sol~ds
Boiler Feedwater
Prec~pitatorReturns SuperheatedSteam
Combustion Atr
Flue Gas to Stack

Steam Coil Air Heater

Salt Cake Makeup

I Fig. 33 Chemical-recovery unit with oxidizer and cascade evaporator


COMB~ON
Bdlm for Process Use/Power Production

Black Liquor (BL) Inlet

BL Flow in Tank

B L Outlet to Flowbox

Out of Side Channel


Liquor Flows into Side Channel
Section Through Wheel

Fig. 34 Pattern of cascade-evaporator liquor flow

.
.
=
. To B L Pump,
Sec. BL Heater and Furnace

- Fig. 35 Black-liquor flow diagram

ABB
..ui.Ioll-
COMBUSTION
Bdlsrs for Process Use/Power Pmdudh

wheel causes the tubes to be alternately washed power required by the black liquor pump.
in the liquor bath, and exposed to the hot flue Following the salt-cake mixing tank, the liq-
gases where water is evaporated. It also induces uor flows to the heavy black liquor pump, and
-liquor circulation in the bottom of the cascade then on to a secondary black liquor heater
which causes the liquor to be well mixed at all where the temperature is raised to about 240F
times. The tubes never dry out in the gas stream (115OC). From here the liquor flows through the
and are, therefore, good collectors of ash parti- spray nozzles into the furnace.
cles entrained in the gas stream.
As shown in Fig. 35, the liquor travels from EXTENDED ECONOMIZER BOILER
the cascade evaporator to a flow box located The advances in evaporator technology de-
next to the cascade tank. Within the flow box is scribed earlier permitted the development of
a rotating cylindrical screen through which all concentrators capable of producing black liquor
the liquor must flow. .The screen blocks the at firing strength without the use of a direct-
larger lumps which are deposited in the box contact evaporator. The better thermal effi-
where they dissolve. ciency a n d reduced-odor e m i s s i o n s of
From the flow box, the liquor moves into the multiple-effect evaporators over direct-contact
salt-cake mixing tank where pulverized sodium evaporators caused them to almost completely
sulfate can be added to compensate for the replace such evaporators on new chemical re-
chemical losses in the mill. The black liquor is covery boilers. To remove the heat from the flue
thoroughly mixed with a paddle-type agitator. gas that would have normally been picked up in
A horizontal screen within the tank prevents the direct-contact evaporator, the economizer
lumps of salt cake from flowing into the black was made larger. Therefore, this type of boiler
liquor piping. Within the tank a primary black is referred to as extended-economizer or
liquor heater raises the liquor temperature to low-odor system. Fig. 36 shows a schematic of
about 210 F (10o0C), thereby minimizing the liquor preparation system.

uperheated Steam

To Precipitator and Stack

Boiler Feedwater
Return Ash From Precipitator Combustion Air

Heavy Black Liquor


ChemicaVAsh Tank Molten Smelt
Indirect Liquor Heater

Liquor Heater

I
Fig. 36 Extended-economizer chemical recovery boiler with schematic of black' liquor preparation system
COMBUSTION
BoIkrs for Pnmws Use/Power Production
--
The liquor from the heavy liquor storage tank mands, the air and liquor delivery systems on
or the last evaporator effect is sent to the chemi- the recovery boiler are designed to provide dis-
callash mix tank, where the ash collected in the tinct process zones within the furnace, as illus-
precipitator and economizer is mixed with the trated in Fig. 37. The black liquor is sprayed
black liquor. In dry-bottom precipitators and into the furnace at an elevation of 17 to 21 feet
economizer hoppers, a dry-ash conveying sys- (5.2 to 6.4 m) above the furnace floor so that it
tem removes the ash from the bottom of the will dry in flight, before reaching the char and
hoppers. Dry-ash conveyers can transport it di- smelt bed. This first zone around the fuel entry
rectly to the mix tank, or it can be sluiced with is, therefore, referred to as the drying zone.
black liquor in sluice bowls, before being sent Once the fuel is dry, pyrolysis of the organic
to the mix tank. An agitator in the mix tank pre- constituents in the liquor will begin; accord-
vents ash settling. In wet-bottom precipitators ingly, the next zone in the furnace is referred to
and economizer hoppers, black liquor flowing as the pyrolysis zone. Char gasification and re-
through the bottom of the hoppers removes the duction of the inorganic chemicals take place
ash. The liquor leaving the hoppers is returned in the lower part of the furnace and this region
to the mix tank. Salt-cake makeup can also be is called the bed zone or hearth of the furnace.
added in the chemicallash tank. In some sys- The inorganic chemicals are recovered from
tems, however, the salt-cake makeup is mixed this zone in smelt form. Finally, the partially
in a separate, independent mix tank. The chem- combusted gases rise up in the furnace and
icallash mix tank is equipped with a paddle- pass through an oxidizing zone where combus-
type agitator and a horizontal screen. It also tion is completed.
contains a direct-type heater. However since Proper zone control in a chemical recovery
the strong liquor from storage is already at boiler is required to achieve a desirable temper-
pumping temperature, it is only used during ature profile similar to the one shown in Fig.
upset conditions. 37. Higher gas temperatures in the lower fur-
From the chemicallash mix tank, the liquor is nace optimize the drying, pyrolysis, char-
pumped to the black liquor heater where its gasification and chemical-reduction processes.
temperature is raised to between 240F and Achieving a lower furnace-leaving, temperature
260F (115 to 125OC) by indirect heating will reduce the plugging potential in the con-
through a heat exchanger or through direct vective sections of the boiler.
steam injection. From the heater, the liquor
BLACK LIQUOR DELIVERY SYSTEM
goes to the spray nozzles.
BURNING THE BLACK LIQUOR
The first priority in achieving optimized zon-
. ing in the furnace is to obtain .consistently
Ths diial purpose of the recovery boiler is: coarse black liquor spray droplets which are
to recover inorganic chemicals from the black evenly distributed across a narrow vertical band
liquor in a form in which they can be recycled that covers the entire furnace cross section. The
in the pulping process, and flat-spray nozzle held in a fixed position is used
to combust the organic constituents in the for this purpose (Fig. 38). The nozzle will pro-
black liquor to produce valuable steam. duce a flat spray of coarse droplets over a wide
The chemical recovery efficiency of the boiler range of liquor conditions. A second type of
is measured in the smelted chemicals which nozzle which can be used to produce a flat spray
leave the boiler from the bottom of the furnace. of coarse liquor droplets is the splash-plate noz-
This efficiency is measured in terms of the con- zle also shown in Fig. 38. For both nozzles, the
version of sodium sulfate (Na2S0,)to sodium angle of the nozzle .support can be adjusted to
sulfide evaporated before either the chemical optimize the liquor distribution in the boiler fur-
recovery or the combustion process can begin. nace to allow for optimum drying and pyrolysis
As a result of these multiple-process de- in flight.
COMBUSRON
Boilen for m e s s UsalPower ProducUon

Boiler Stationary Firing Zones Temperature Profiles

------
Drying Zone
------
Hot Zone
(Pyrolysis)
------
Bed Zone
------

I
L
Fig. 37 Process zones in a chemical-rectvery-unit furnace
Temperature, " F
I
I

CHEMICAL RECOVERY BOILER AIR SYSTEM carbon on the bed and thereby liberate heat to
maintain the optimum bed temperature, shape,
The three-level air system installed on chemi- and size. This stream must not disturb the bed
cal recovery boilers is designed to optimize the as this could result in excessive carryover; how-
processes occuring in the lower furnace ever, it must make contact with the bed surface
through improved zone control. Each level is to react with the char. To achieve this, the opti-
independently controlled and monitored. Pri- mized primary-air stream should enter the fur-
mary air is admitted at the bed level, secondary nace through small ports located on all four
air is admitted just above the bed, and tertiary walls of the furnace. The velocity of this air
air is admitted above the black liquor spray stream should not be excessive but should be
guns. Each stream serves a distinct function. sufficient to provide approximately 4 to 6 feet of
Primary air is required to partially oxidize penetration (1.2 to 1.8 m) towards the center of
ComoSTION
Boilem for Pmcess Use/Power PrvducUon
-
the bed. The ports should be equally spaced ports are larger in size than the primary-air
and directed slightly downward to provide even ports, are fewer in number, and are angled hor-
coverage of the bed around all four walls. Pri- izontally into the furnace. This, along with the
mary air is preheated to 300 to 400F (150 to slightly higher velocity, provides the momen-
200C) in a steam-coil air heater to help main- tum necessary to penetrate the furnace cross
tain the high temperatures required to optimize section. The optimum location of the second-
the chemical processes in the lower furnace. ary-air ports is 4 to 6 feet (1.2 to 1.8 meters)
Secondary air is required to supply oxygen to above the primary-air ports which ensures that
burn some of the combustibles liberated from the bed surface will not be disturbed. Carryover
the bed in support of the requirement for high is minimized and the oxygen concentration at
temperatures in the lower furnace. It also en- the surface of the bed is not increased so as to
sures positive smelt bed height control. The adversely affect reduction efficiency. Second-
secondary-air stream must, therefore, penetrate ary air is also preheated to 300 to 400F (150 to
the furnace to reach all the combustibles to pro- 200C) to help maintain high temperatures in
mote chemical-reaction activity. At the same the lower furnace.
time, it should not disturb the bed or greatly in- Tertiary air is required to supply oxygen to
crease the local oxygen concentration on the complete combustion of the organics liberated
bed surface. To achieve this, the secondary-air from the bed and to burn any reduced sulfur
gases to minimize odors from the unit. A con-
trolled minimum quantity of excess air is re-
quired in this stream to ensure that t h e
combustibles (carbon monoxide and total re-
duced sulfur-TRS) in the flue gas leaving the
unit are oxidized. Increased air quantities will
reduce the boiler efficiency and lower the total
steam generation. The tertiary-air stream must
provide the necessary turbulence to generate
intimate mixing of air with the gases liberated
from the lower furnace. It must also generate an
even gas-flow distribution across the width of
the furnace at the gas-outlet plane. Ambient air
is used for tertiary air because it provides a
cooling effect on the flue gases entering the
convection zones. It also has a greater momen-
tum and, therefore, greater mixing potential.
Two types of tertiary-air injection systems are
used on chemical recovery boilers: concentric
injection and interlaced injection (Fig. 39). The
concentric arrangement has four windboxes lo-
cated in the corners of the furnace. The upper
compartment of each windbox is aimed tangen-
tially to the large circle. During normal opera-
Detail of Detail of tion, each elevation receives 50 percent of the
Flat Spray Nozzle Splash Plate Nozzle air at MCR. The interlaced arrangement uses a
series of nozzles located on the front and rear
walls as shown.
Fig. 38 Black liquor firing showing available Both the concentric and interlaced arrange-
nozzle types ments provide an even gas-temperature profile
COMBDSPION
Bollem for Process Usa/PowerPmduction

Rear
- -

Tertiary-Air Nozzles
Front
- Plan Vlew of C-E Concentric Plan View of C-E Interlaced
Tertiary-Air Admission Tertiary-Air Admission

Fig. 39 Alternative tertiary-air admission systems for C-E chemical recovery boilers

at the outlet of the furnace. They also provide cient to generate the full-load steam produc-
good mixing of the gases to complete the com- tion, or to produce steam when there is no
bustion of the gases and to minimize emissions black liquor available. Load-carrying burners
from the furnace at a relatively low excess-air are used for this application.
requirement. Concentric tertiary-air admission Oil, gas or a combination of both can be used
is normally preferred for new chemical recovery as auxiliary fuel in the recovery boiler.
boilers since load-carrying burners can be in- Starting burners (Fig. 40) provide heat input
cluded directly into the tertiary-air windbox. to the lower furnace. At start-up, the heat from
With interlaced-air admission, a separate eleva- the starting burners dries and ignites the black
tion of load-carrying burners and windboxes liquor before a bed is developed. At shutdown,
are required. In addition, unlike the interlaced starting burners burn down the bed. At low
arrangement, the concentric arrangement uses loads, and when the black liquor is likely to
lower injection velocities to achieve proper mix- burn poorly, starting burners stabilize the com-
ing. This requirement leads to lower static-pres- bustion conditions. Four starting burners are
sure requirements at the windbox and lower fan provided to fulfill these requirements, one lo-
power requirements. cated near each corner about five feet (1.5m)
above the floor tubes. They are located close to
AUXILIARY FUEL FIRING IN RECOVERY BOILERS the bed to minimize auxiliary-fuel require-
ments while still maintaining the required heat
Auxiliary fuel is fired in recovery boilers for input to the bed, and they are angled to provide
one of two reasons: good coverage of the bed.
to provide the heat required in the lower fur- Because of their location close to the floor of
nace for warming the unit, stabilizing the char the furnace, the starting burners are not suitable
bed during low-load operation or under upset for the large heat input required for steam pro-
conditions, and burning down the bed during duction. ~oad-carryingburners can be located
shutdowns. Starting burners are used for these at the tertiarv-air elevation to Drovide the heat
applications, or input required to produce additional steam at
to raise the steam production from the boiler reduced black liquor flow, or for steam produc-
when the supply of black liquor is not suffi- tion when no black liquor is available.
. COMBrnON
BoiIsm for PIWCOSSUsdPower PducUon

Burner Air

Gas Front Ignitor Assembly

Gas Connection

ObservationIRodding Door

Fig. 40 Recovery boiler starting burner arrangement

DESIGN BASIS FOR RECOVERY BOILERS surface in the generating bank in a very eco-
Combustion Engineering offers two chemical nomical fashion. For higher pressure units, the
recovery boiler arrangements: the classic two- requirements for evaporative surface is reduced
drum design and the single-drum design. Typi- and a single-drum design becomes more eco-
,iIlv, the optimum recovery boiler arrangement nomical. There are positive features unique to
wil' be selected based on the operating pressure each arrangement.
of the boiler. The two-drum design uses rolled The two-drum recovery boiler design pro-
joints for the boiler-bank tube penetrations into vides better access to the boiler tubes a n d ,
the drums. The practical limit for operating therefore, is easier to inspect, maintain and
pressures using rolled joints is approximately repair. The arrangement provides a larger
1500 psig (10.3 MPa gage). Alternatively, the water inventory which makes it less sensi-
single-drum design features an all-welded con- tive to water-level fluctuations -in the drum
sfruction. With this type of construction, all and to feedwater-flow upsets. This arrangement
sub-critical pressures can be accommodated. also eliminates the need for a hopper and asso-
The boiler operating pressure also influences ciated ash-removal system below the boiler
the effectiveness of heat-transfer surfaces bank. See Fig. 41.
within the boiler, as described earlier in this The single-drum recovery boiler design,
chapter. As the pressure increases, the satura- shown in Figure 3 1,has the generating bank lo-
tion temperature increases and the latent heat cated outside the furnace. This location reduces
of vaporization of the water decreases. There- the potential of water entering the furnace cav-
fore, the need for large evaporative surfaces in ity from the generating tubes. Locating the
addition to the furnace waterwalls decreases steam drum external to the gas stream elimi-
with increasing operating pressures. At tradi- nates the potential for corrosion of the drum
tional recovery boil& operating pressures of metal. The drum also has fewer penetrations
600 to 900 psig (4 to 6 MPa gage), the two-drum and, as a result, thinner drum plate. This thin-
design provides a large amount of evaporative ner tube sheet, coupled with the fact that .it is
COMBVSPION
Boilers for Process U,ne/PowerPducUon

Fig. 41 Two-drum C-E chemical recovery boiler for operating pressures to 1500 psig (10.5 MPa gage)

8-55
not in the gas stream, allows faster start-up and sions, is the gas temperature entering the con-
shutdown times. Since the single-drum ar- vective sections of the boiler. Typical recovery
rangement is a fully welded design, it is not boiler ash deposits have a first melting tempera-
susceptible to weeping at rolled joints follow- ture or "sticky" temperature of 1300 to 1400F
ing emergency boiler draining. The two-drum (700 to 760C); however, studies haw shown
design can also be made a fully welded flow ar- that the first melting point of the ash can be de-
rangement by seal welding the rolled joints pressed to as low as 1000F (540C)by the pres-
in both upper and lower drums. ence of impurities such as chloride and
potassium in the black liquor or by high liquor
FURNACE SIZING
sulfidities. -1n chemical recovery boilers, the
Several factors influence the selection of the transition region in which the ash changes from
furnace dimensions for a chemical recovery molten to sticky to a dry powdery form nor-
boiler, including the nature of the fuel, the mally falls in the superheater zone. The super-
characteristits of the black liquor, and the heater radiant surfaces are, therefore, designed
chemical recovery and steam generation func- to be cleanable under these conditions. The
tions of the boiler. The principal characteristics first closely spaced convective section in the
of black liquor as a fuel are its relatively high gas path is the generating bank. In a recovery
ash content (up to 45 percent of the dry solids), boiler, the gas temperature entering the generat-
its relatively low heating value (HHV between ing bank is, therefore, a critical design parame-
5,000 and 7,000 Btullb, or 11.6 and 16.13 MJ/ ter, since it must be maintained below the first
kg of dry solids) and its relatively high mois- melting point of the ash to prevent the ash from
ture content as fired (25 to 35 percent). accumulating on the tubes.
The hearth heat-release rate (HHRR) is the The furnace heating surface, based on the re-
first important factor in sizing the furnace. It is quired combustion volume, and the super-
defined as the black liquor gross heat input di- heater surface, based on the required steam
vided by the furnace plan area. The HHRR is temperature control, are not normally sufficient
important because it affects the temperature in to lower the temperature of the flue gas entering
the lower furnace and it can be used to optimize the convection sections to an acceptable value.
the reduction efficiency, the combustion stabil- The designer of the recovery boiler has three al-
ity, pollutant emissions from the lower furnace ternatives to reduce the gas temperature to
(TRS and SOz)and the turn-down stability of these sections:
the unit. The optimum value for the HHRR Make the superheater larger to increase the
must be selected based on the liquor character- heat absorption upstream of the convection sec-
istics, the anticipated boiler operating-load var- tion
iations, and the required future load capacity. Make the furnace taller
The combustion volume is the second impor- Use radiant furnace panels.
tant design variable in selecting the furnace di-
mensions. The combustion volume establishes The first option consists of making the super-
the residence time and the degree of combus- heater much larger than what is required to pro-
tion in the furnace. Sufficient combustion vol- vide steam temperature control over the
ume must be present in the furnace to allow for specified load range. Steam-cooled screens
complete mixing and combustion of the gases generally fall under this category since they
rising from the lower furnace. Since the HHRR add superheater surface. This option is usually
governs the plan area of the furnace, the re- practical on high-temperature, high-pressure
quired combustion volume usually establishes units where the required- superheater surface
a minimum furnace height. will absorb a large amount of heat and, there-
The third, and possibly the most important fore, the additional superheater surface
variable which influences the furnace dimen- required is minimized.
COmUSPlON
Boilers for Process Use/PowcvRuduction

The second option is to increase the furnace smelt on the bottom of the furnace. The molten
height to add sufficient heating surface in the smelt flows through the smelt spouts into the
furnace to reduce the gas temperature entering main dissolving tank. The floor of the recovery
the convection sections to an acceptable value furnace must form a complete seal to prevent -
without oversizing the superheater. On low- smelt from leaving the furnace other'-than
steam-temperature, low-pressure units for through the spouts. A decanting furnace bot-
which t h e superheater heat pick-up is tom, Fig. 42, is used for the following reasons:
not very large, this could lead to extremely tall 1. It equalizes the heat distribution in the
furnaces. As a result, this option is usually lower furnace and, therefore, optimizes the re-
applied in conjunction with a slightly over- duction efficiency, minimizes the SO, and TRS
sized super-heater and is generally the pre- emissions, and optimizes the gas distribution
ferred option for moderate-temperature, leaving the furnace.
moderate-pressure units. 2. It reduces the risk of main dissolving-tank
The last option is to use radiant furnace pan- explosions caused by uneven smelt run-off from
els to remove heat from the gas before it reaches the furnace.
the superheater. These panels consist of water-
3. It eliminates the potential for corrosion of
cooled tube panels. In addition to reducing the
the floor tubes by ensuring the continuous pres-
gas temperature, they also serve to protect the
ence of a frozen smelt layer on the floor. The
superheater from direct furnace radiation. This
frozen smelt layer also minimizes the potential
arrangement is usually the preferred option for for stress assisted water-side corrosion at the
low-temperature, low-pressure units since it floor tube-to-header attachments by minimiz-
provides a reliable and economical method of
ing the operating stresses at these attachments.
adding heating surface in the furnace.
4. It favors positive circulation through all the
FURNACE-BOTTOM DESIGN waterwall circuits by reducing the potential of
A major difference between chemical recov- boiling in the floor tubes.
ery boilers and other types of power boilers is 5. It strengthens the floor tubes.
the presence of the char bed and the molten 6. It eliminates the complicated floor tube-to-

Fig. 42 Decanting bottom of recovery-boilerfurnace


COMBu!jnON
BdIwm tor Procrrs Uswmwer Production

header design and thereby ensures a positive by adequate spacing between the tubes based
smelt seal. on the gas temperature, and by a vertical tube
7. It reduces the potential for char carryover arrangement.
in the smelt leaving the furnace.
8. It protects the floor tubes from slag falls CORROSION
from the upper furnace.
Unprotected pressure-part surfaces in kraft
ARRANGEMENT OF THE HEATING SURFACES recovery furnaces have historically been sensi-
As previously mentioned, the nature of the tive to wastage in specific regions including
ash in chemical recovery boilers requires the waterwall aild convection section tubing.
designer to make special provisions in the de- WASTAGE LOCATIONS
sign of the heating surfaces to ensure that they
will be easy to clean. A pattern of watenvall wastage has been ob-
Because the gas temperature entering the su- served in certain kraft recovery furnaces operat-
perheater will usually be higher than the first ing above 900 psig (6.2 MPa gage) although it
melting point of the ash, the superheater has to has also been identified in units operating at
be designed to make it cleanable under that pressures as low as 600 psig (4.1 MPa gage). In
condition. A tangent-tube pendant-platen de- a furnace with unprotected tubing, significant
sign on wide spacing is the optimullr arrange- wastage-up to 30 milslyr (0.75 mm1year)-has
ment to ensure cleanability under sticky-ash been observed in the primary-air port region,
conditions. The tangent-platen design prevents and up to 10 milslyr (0.25 mmlyear) in the liq-
the deposits from wrapping around the individ- uor spray-gun area (Fig. 43).15 Wastage in the
ual tubes. This situation is similar to the condi- leading tubes of the finishing superheater of
tion at the furnace walls, where the ash 30 to 40 milslyr (0.75 to 1.0 mmlyr) has been
deposits build up until they fall off under their reported.
own weight. The wide transverse spacing Wastage rates, a function of both environ-
(12 in., or 300mm) prevents the deposits ment and metal temperature, have been ob-
from bridging between elements. These vertical served to increase with operation at higher
platens combined with judicious spacing of pressure, more efficient steam cycles.
the sootblowers ensure the cleanability of WASTAGE MECHANISMS
the superheater.
The chemical recovery boiler is designed to The two most common methods of pressure-
ensure that the gas temperature entering the part wastage in recovery boilers are sulfidation
generating bank and economizer is well below and liquid-phase sodium hydroxide attack ag-
the first melting point of the ash. Under normal gravated by the presence of oxygen.
conditions, the ash in the generating bank is ex-
Sulfidation
pected to be mostly sodium sulfate in a pow-
dery form, and it is easy to remove from the The primary mode of attack on both upper
tubes. However, recovery boiler ash can also be- and lower waterwalls is sulfidation; the unpro-
come hard through sintering.14 Sintering is a tected carbon steel conventionally used for con-
molecular diffusion process that can occur at struction of waterwalls is vulnerable at metal
temperatures below the deposit first-melting temperatures exceeding 625 OF (330OC).
point. During furnace operation, tubes in the af-
Under suitable conditions, sintering can turn fected areas are covered with a sheet of frozen
soft deposits which are easily removed into very "smelt" or wall deposit (Fig. 44). The deposit is
hard deposits. Deposit control in the generating generally separated from the tube surface by a
bank and economizer is achieved through judi- thin layer of irregularly spaced porous material,
cious location and operation of the sootblowers, probably dried black liquor. This provides a
o m
O,.Ol
Inch Per Year
Extent of Wastage
Section A - A

Fig. 43 Typical recovery-unitfurnace-wall corrosion

space of about 1mm (0.04 in.) which may serve that the corrodent is nascent sulfur formed by
as a passageway for corrosive gases. On the the reaction of furnace gases with the frozen
outer surface of the frozen deposit, there is a smelt on the tube surfaces.
pulsating flow of molten smelt. Depending on
the ash-bed configuration, this molten outer Fe + S+ FeS
layer may be in contact with the glowing ash (1)
bed and/or bathed in a gaseous stream of
widely varying concentrations of primary air A series of laboratory tests has suggested the
and combustion products. probable reactions involved in formation of the
The principal corrosion product is FeS (see corroding sulfur.16 When metal specimens were
Eq. 1).Laboratory and field studies have shown submerged in powdered sodium sulfide and
carbon dioxide was passed through the reaction
tube, severe corrosion was observed. Large
quantities of sulfur were deposited on the reac-
Tube Wall tion tube and carbon monoxide was detected by
gas chromatography. This suggests that, at
Porous Layer 700F (370C), sodium sulfide is oxidized to
Frozen Smelt sulfur by carbon dioxide:
Adherent Layer

Increased corrosion in the presence of CO,


was also reported as one of several significant
reactions in papers by the Finnish and Swedish
Corrosion Committees.17.18
Also studied was the effect of sulfur dioxide
Fig. 44 Cross section of recovery-unit furnace-wall on the corrosion of a metal specimen sub-
deposits merged in powdered sodium sulfide. While the
corrosion observed in this test was less than the Sodium HydroxideIOxygenAttack
rate for the carbon-dioxide/sodium-sulfide test, A second mechanism of tubing material loss
the corrosion was very severe and large quanti- occurs when sodium hydroxide evolved from
ties of sulfur collected on the cool ends of the the bed condenses and reacts with the base
reaction tubes. metal (see Eq. 5).
2 Na,S + 3S0,+2 Na,SO,,+ 3 s
(3)

Furnace gas analyses in recovery units show


large amounts of carbon dioxide (from 7 to 19 Historically this type of wastage, prevalent
percent) in the area near the tube walls below in 900 psig (6.2 MPa gage) boilers, was control-
, the ~ r i m a r y ~ aports.
ir Only small concentra- led with the advent of fin- and fusion-welded
tions of sulfur dioxide were found (less than walls which seal out the oxidizing (0,-in-air)
0.05 percent). component.
Another way that sulfur may be generated in Some higher-pressure boilers (1200 psig or
recovery boilers is by the oxidation of hydrogen 8.3 MPa gage) equipped with composite stain-
sulfide. Fig. 45 shows that the corrosion rate of less tubes that are intended to resist sulfidation
carbon steel under powdered Na,S rises rapidly attack have been found nevertheless subject to
until the stoichiometric oxygen concentration "air-port corrosion" which is observed in crev-
is reached. ice areas where hydroxides can condense. At
many non-gas-tight locations in the lower fur-
nace (smelt openings, burners, air ports, or ob-
servation doors), the stainless layer seems '
highly susceptible to attack by the liquid-
In the absence of H,S, the effect of the oxygen sodium/potassium-hydroxide phase. Since
concentration is less pronounced. this wastage is confined to a narrow area
around the air ports, the present approach is to
provide air-tight furnace penetrations so that
only high-velocity air enters the furnace and
Percent COz In NZ does not meet hydroxides prior to conversion to
5 10 15 20 25
6oo0 I I I I 5 1 carbonate and/or sulfate.19 Some form of lorver-
furnace waterwall protection is, therefore, nec-
4
essary for operating pressure above 900 psig
C % Oxygen
(6.2 MPa gage) where saturation temperatures
400 - exceed 540F (280C) and skin metal tempera-
ui tures are 600F (315C)or greater.
8 300 -
METHODS OF PROTECTION
Ecr, 200-
.-
Several mechanical and metallurgical ap-
P Hz S: Oz Ratio proaches to protecting recovery-boiler wa-
(Air) terwall tubing and convection-pass heating
surfaces are successfully applied. They are de-
scribed in the subsequent sections.
Percent OZi n Nz -
Studs and Refractory

Fig. 45 Effect of furnace gas composition on Chrome refractory or frozen smelt is retained ,

corrosion of carbon steel by pin studs on the water-cooled tubes. Molten


CO-ON
BoIIers for Pnxess UsdPower Pmductlon

smelt is thus prevented from contacting the lowed by 0.004 inch (0.10 mm) of aluminum
tube metal. Experience with studded tubing on and then a layer of silicate-aluminum sealer.
1250 psig (8.6 MPa gage) C-E recovery_boilers After several years experience, bonding layers
both in the U.S. and Finland have indicated that were developed to reduce the spalling tendency
extensive repairs and replacement are required of these coatings; consequently, a revised coat-
after three to seven years. Because of the ing procedure was developed using the follow-
stud spacing, monitoring of wall thickness in ing proprietary products: undercoat layer-
these units has been extremely difficult. In 0.002 to 0.005 inch (0.05 to 0.13 mm) of Metco
addition, the labor and fabrication costs can be 405 nickel titanide adjacent to the grit-blasted
prohibitive. tube surface; middle layer-0.007 to 0.009 inch
10.18 to 0.23 mrn) of Metco #1(300 series stain-
Weld Overlav less); outer layer-0.003 to 0.004 inch (0.08 to
0.10 mm) of ~ e t c oSuperfine (aluminum). A
Protection by weld overlay on the lower 6 layer of Metco SA silicate-aluminum sealer is
to 9 feet (2 to 3 m) of high-pressure units has sprayed or painted on to fill the naturally occur-
been satisfactorily employed for several years in ring pores in the metallized coating.
Finland, Japan, France and, to a limited extent Annual inspection and repair of spalled areas
in the U.S. Austenitic alloys usually containing are required, but it is still not possible to pre-
18 percent Cr (or more) have been used. There dict where and when coating loss will occur.
is considerable hand labor involved in this More recent trends have been to apply single-
method al@ough satisfactory corrosion protec- layer coatings using plasma-powder spray or
tion has resulted. wire-arc spray techniques. While these coatings
The weld overlay may be done manually. are reported to be more dense and monolithic,
More recently, some suppliers are using auto- they still are porous and are not metallurgically
mated systems. Prebending and other special bonded. Although the time of application is
handling is required to produce flat waterwall significantly reduced with the single layer coat-
panels. Surface repair can be done readily in ings, they remain subject to spalling andlor un-
the field, although tube replacement is dif- dermining by oxide or sulfide formation at the
ficult. Seventeen to twenty years operating ex- tube interface.
perience has been accumulated by users in During the time that single-layer coatings
various countries. have been used, they have apparently not re-
quired as extensive touch up-& repair during
Metallizing
outages as is the practice with the multi-
The earliest development of field applied coat process.
protection was in the form of multi-coat metal-
Composite Tubing
lizing. Since these coatings are not metallurgi-
cally bonded, the most important aspect of Composite tubing (bimetallic type 304 stain-
flame or plasma spray metallizing is that the less over carbon steel) is manufactured by sev-
tube surfaces be absolutely clean.and dry. The eral companies. This development foliowed
tubes should be cleaned by steel or grit blasting successful demonstrations in which C-E partic-
(0.005-inch or 0.13-mm size) and spraying ipated, where stainless-steel weld overlay was
should follow immediately. Sand blasting is shown to control recovery-unit wastage.
not recommended because of dust residue left The resistance of type 304 composite tubing
on tubes. More than one blast-cleaning opera- to sulfidation is very high; however, recent
tion may be necessary. experience has shown that the more localized
The original multi-coat layers consisted of air-port attack (attributed to condensation of
0.008 inch (0.20 mm) of 200-series stainless sodium hydroxide) may not be controllable
steel adjacent to the cleaned tube surface, fol- with this tubing. Fabrication techniques require
--
additional handling and setup. Carbon-steel that are fabricated before chromizing can also
fins require austenitic stainless overlay. Mainte- be chromized, hereby providing protection to
nance or repairs of composite tubing require the total surface. The enrichment occurs "in"
double scarfing and the use of multiple weld- and not "on" the surface; consequently, appli-
ing rods. The material cost of the composite cation of the coating does not change the physi-
tubing is much greater than that of carbon- cal dimensions of the component. Being a n
steel, so that the subsequent cost of boilers with integral part of the base metal, the metallurgi-
' this tubing is considerably higher than with the cally bonded, diffused-chromium structure is
other forms of protection discussed. not subject to peeling or spalling. The 30 to 40
percent chromium in the chromized coating is
significantly higher than the 18 to 20 percent
Chromizing chromium level in commonly used austenitic
Chromizing is a high-temperature diffusion alloys, and thus is considered to be equal to or
coating process in which solid-state diffusion perhaps more resistant to sulfidation than the
produces a chromium-rich metal surface that is 18-8 austenitic stainless steels.
resistant to corrosion in a variety of environ- Welding of chromized components is a sim-
ments. Carbon-steel and numerous alloys can ple, straight-forward procedure. Butt welds are
be chromized, including the following steam- made after preparatory machining of tube ends,
generator tubing materials: SA-192, SA213, T-11, which is done after chromizing. Filler metal is
T-22 and T-91. Typically, the chromized struc- the same as if welding a non-chromized tube. If
ture in SA-192 carbon-steel is approximately 10 protection from wastage is desired, an E309
to 15 mils (0.75 to 0.375 mm) thick, and is up to electrode is used as a cover pass. Attachments
20 mils (0.5 mm) thick with SA-123, T-11 or T- that must be made to the chromized surfaces
22 base metals. This outer layer contains from use the same procedures that would be speci-
30 to 40 percent chromium at the surface, de- fied for welding non-chromized surfaces.
creasing almost linearly to between 10 and 15 Field and laboratory analyses indicate that
percent at the base-metalldiffusion-zone inter- chromized carbon-steel and chromized low-
face. At the surface, a very thin 0.6 to 1mil (15 alloy tubing is resistant to external'corrosion of
to 25 pm) chromium carbide layer contains 70 waterwall and superheater surfaces in chemical
to 75 percent Cr. While the total thickness of the recovery boilers and has proven itself to be a
coating is important, it is more important that cost effective alternative to the use of composite
the outer portion of the coating contain at least tubing and field applied coatings.20
20 to 25 percent chromium.
SMELT-WATER EXPLOSIONS
The coating process consists of several steps
including placing the part to be chromized in a When water contacts molten smelt, the ele-
metal box, covering the part with the chromiz- ments exist for a potentially violent physical ex-
ing mixture, and heating the box and contents plosion. Unlike chemical explosions, physical
at an elevated temperature. After chromizing, explosions do not involve a reaction between
the component is heat treated; the exact proce- two substances. Rather, a physical explosion
dure is a function of the alloy identity. The pro- results from the very rapid expansion of gas and
cess, as developed at Combustion Engineering can be powerful, destructive, and costly. Smelt-
and also described in Chapter 17 on Materials water explosions are more violent than typical
and Metallurgy, can accommodate large heat nondetonative explosions in furnaces which in-
exchangers, such as waterwall panels and su- volve conventional fuels such as coal, oil, or gas
perheater and reheater assemblies. in air. Whereas the latter develop much lower
Both external and internal surfaces of these peak pressures and travel at the speed of sound,
tubular components can be chromized. More smelt-water explosions, like other physical ex-
important, however, the attachments and fins plosions, produce higher pressures, perhaps by
COMBUSPION
Boilers for Process Use/Power fkduction

a factor of 10 or more, and travel at supersonic drain the furnace to 8 feet (2112 meters) above
speeds. They are, by definition, shock-wave the furnace floor, thereby stopping the leak
phenomena. while at the same time preventing overheating _
A smelt-water explosion results from water of the lower-furnace tubes. - -
changing suddenly to steam. This rapid change Furnace Framing and Structure:
is caused by an extremely high heat-transfer The furnace-framing system is designed to re-
rate that can exist between molten smelt lieve excess pressure in a safe location such as
and water. The seriousness of a smelt-water the upper furnace in the event of an explosion.
explosion is not related to the amount of Zipper corners on the front wall will open to re-
smelt or water involved; a teaspoon of molten lieve furnace pressure to minimize damage to
smelt in a cupful of water can produce a the pressure parts. Also, the furnace structure
powerful explosion. has added strength to reduce the risk to operat-
Weak black liquor can also produce an explo- ing personnel.
sion when brought into contact with smelt. Furnace Bottom Design:
concentrations above 58 percent, however, are The decanting hearth arrangement ensures that
considered safe to fire into the furnace. Many a frozen smelt layer constantly covers the floor
'
recovery boilers are equipped with solids me- tubes. This arrangement eliminates the poten-
ters which continuously monitor the black liq- tial for corrosion of the floor tubes, protects the
uor solids concentration. Should the solids floor tubes from physical damage due to large
concentration fall to an unsafe level, the liquor ash deposits falling from the superheater re-
is automatically diverted from the furnace. gion, and eliminates hot spots on the floor
SAFETY CONSIDERATIONS IN CHEMICAL RECOVERY tubes which assures positive circulation
BOILER DESIGN through all circuits. The decanting hearth also
adds to the strength of the floor and reduces the
Because of the potential 'for considerable risk of main dissolving-tank explosions result-
damage and the.threat to the safety of operating ing from uneven smelt run-offs.
personnel in the event of a smelt-water explo-
sion, the chemical recovery boiler design in- RELIABILITY AND MAINTAINABILITY OF THE
cludes several safety features. Some special CHEMICAL RECOVERY BOILER
features which minimize such risks are as In addition to safety, reliability and main-
follows: tainability are also very important aspects of
8 Corrosion-resistant materials in the lower the design of chemical recovery boilers. The re-
furnace and very conservative corrosion covej boiler often constitutes the bottleneck in
allowances: the pulp mill production. Keliability is there-
In modern boilers, some form of corrosion- fore very important since an unscheduled out-
resistant materials, composite tubing with age usually translates into lost production for
stainless-steel overlay of the fins, or chromized the mill. Also, maintainability is important
panels are used to eliminate the potential for since reduced shutdown time means increased
tube thinning in the critical high. temperature mill production.
zone of the boiler. In addition, the tubes in the Combustion Engineering addresses these is-
rest of the furnace are selected with very con- sues with conservative materials and equip-
servative corrosion allowances to reduce the ment selection during engineering of the boiler,
potential of water leaking into the furnace. and high standards of quality and inspection
Emergency Drain System: during manufacturing and erection to ensure
The recovery boiler is equipped with a rapid the reliability of the unit. Maintainability is im-
drain system to allow the operator to drain the proved by providing easy access for inspection
furnace rapidly if it is thought that water may and standardizing the equipment to reduce the
be leaking in the furnace. This system will amount of spare parts required.
R.E. Sommerlad, et al., "Systems Evaluation of Refuse
as a Low Sulfur Fuel: Part 2, Steam Generator Aspects:'
William H. Pollock, "Coal-Fired Industrial Boilers for the ASME Poper no. 71 -WAIInc-2. New York: American Soci-
1980's:' Proceedings of the American Power Conference, ety of Mechanical Engineers. 1971. (This information can
41:835-841, 1979. Chicago: Illinois Institute of Technol- also be found in NTIS publications PS-209 271 and PB-
ogy. 1979. 209 272, Springfield, VA: National Technical Information
1 L. J. Cohan and J. H. Fernandes, "Potential Energy Con- Service.)
version Aspects of Refuse:' ASME Paper no. 67-WAIPID-6. R. M. Roberts and E. M. Wilson, "Systems Evaluation
New York: American Society of Mechanical Engineers, of Refuse as a Low Sulfur Fuel: Part 1, The Value of Refuse
1967. Energy and the Cost of Its Recovery," ASME Paper no.
71 -WAllnc-3: New York: American Society of Mechanical
3 J. W. Regan. J. F. Mullen, and R. D. Nickerson, "Suspen- Engineers, 1971. (This information can also be found
sion Firing of Solid Waste Fuels," Proceedings of the in NTIS publications PB-209 271 and PB-209 272,
American Power Conference, 31:599-608, 1969.?hicago: Springfield, VA: National Technical Information Service.)
Illinois Institute of Technology, 1969.
fl Paul D. Miller and Horatio H. Krause, "Corrosion of Car-
4 J. W. Regan, "Generating Steam From Prepared Refuse," bon and Stainless Steels in Flue Gases From Municipal
Proceedings ~f the Fourth National Incinerator Confer- Incinerators," Proceedings of the 1972 National Incinera-
ence, Cincinnati, May 17-20, 1970, pp. 216-223. New tor Conference, New York, June 4-7, 1972, pp. 300-309.
York: American Society of Mechanical Engineers, 1970. New York: American Society of Mechanical Engineers.
1972.
v o s e p h F. Mullen, "System for Pneumatically Transport-
ing High-Moisture Fuels such as Bagasse and Bark and an "E Nowak, "Considerations in the Construction of Large
Included Furnace for Drying and Burning Those Fuels in Refuse Incinerators:' Proceedings of the 1970 Notional In-
Suspension Under High Turbulence:' U.S. Patent no. cinerator Conference, New York, May 17-20, 1970, p p 86
3,387.574, assigned to Combustion Engineering, Inc., -92. New York: American Society of Mechanical Engi-
June 11,,1968. neers, 1970.
Gerald E. Dreifke, David L. Klumb and J e m l D. Smith, 13 Karl-Heinz Thoemen, "Contribution to the Control of
"Solid Waste as a Utility Fuel:' Proceedings of the Ameri- Corrosion Problems on Incinerators with Water-Wall
can Power Conference, 35:1198-1206. 1973. Chicago: Illi- Steam Generators," Proceedings of the 1972 National In-
nois Institute of Technology, 1973. cinemtor Conference, New York, June 4-7, 1972, pp. 310-
318. New York: American Society of Mechanical Engi-
7 H. Eberhardt and W. Mayer, "Experiences with Refuse In- neers, 1972.
cinerators in Europe: Prevention of Air and Water Pollu-
tion, Operation of Refuse Incineration Plants Combined "H. Tran, "How Does a Kraft Recovery Boiler Become
with Steam Boilers, Design and Planning:' Proceedings of Plugged?': 1988 TAPPI Krafl Recovery Operation Semi-
the 1968 National Incinerator Conference, New York, May nar; Orlando, FL, 1988.
5-8, 1968, pp. 73-86. New York: American Society of Me-
chanical Engineers, 1968. 1". L. Plumley, E. C. Lewis, and R. G. Tallent, TAPPI 49
(I), pg. 72A, 1966.
8 H. Hilsheimer, "Experience after 20,000 Operating
Hours: The Mannheim Incinerator," Proceedings of the 16R. G. Tallent and A. L. Plumley, TAPPI 52 (lo), pg. 1955,
. 1970 National Incinerator Conference, New York, May 17- 1969.
20, 1970, pp. 93-106. New York: American Society of Me- 170. Stelling, "What Reactions Cause Corrosion in Soda
chanical Engineers, 1970. Plant Boilers:' Annual Nordic Recovery Boiler Confer-
J. G. Singer and J. R. Mullen, "Closing the Refuse Power ences, 1965 - 1967.
Cycle:' ASME Poper no. 73-PWR-18. New York: American '80. Moberg, "Recovery Boiler Corrosion," Pulp and Poper
Society of Mechanical Engineers, 1973. Industry Corrosion Problems, NACE, 1974, pg. 125.
1OA. P. Konopka, "Systems Evaluation of Refuse as a Low '9T. Odelstam, "BLRB Composite Tubes- 15 Years of Expe-
Sulfur Fuel: Part 3, Air Pollution Aspects," ASME Paper rience," TAPPl Opemtions Seminar, 1988.
no. 71-WAIInc-I. New York: American Society of Me-
chanical Engineers, 1971. (This information can also be 10A. L. Plumley, et al., "Chromizing for Recovery Boiler
found in NTIS publications PB-209 271 and PB-209 272, Corrosion Protection," BLRBAC, Atlanta, October 1988;
Springfield, VA: National Technical Information Service.) also as Combustion Engineering publication TIS-8417.
CHAPTER 9

Fluidized-Bed Steam Generators


For decades, fluidized-bed reactors have been petroleum products, a Fluidized Catalytic
used in non-combustion reactions in which the Cracking (FCC) process was developed during
thorough mixing and intimate contact of the the early 1940's. This process greatly increased
reactants in a fluidized bed result in high prod- both the quantity and quality of the refined
uct yield with improved economy of time and product. Over the years many improvements
energy. Although other methods of burning were made to the original FCC process and, to-
solid f ~ e l salso can generate energy with very day, various types of fluid-bed processes are
high efficiency, fluidized-bed combustion can used in the refining of petroleum and the pro-
burn coal efficiently at a temperature low duction of other chemical feedstocks.
enough to avoid many of the problems of com- During 1953, patents were assigned to Com-
bustion in the other modes. (See the discussion bustion Engineering for combustion of oil and
in Chapter 4 that compares the physical mech- natural gas in a fluidized bed composed of par-
anisms presently in use for burning coal and ticles of alumina, as a means to increase heat-
other solid fossil fuels in steam generators.) transfer rates to boiler heat-absorbing surfaces.
C-E also conducted experiments using a fluid-
ized bed to combust coal. However, with low
HISTORICAL PERSPECTIVE prices for oil and gas during the 60's. there was
Fluidization and observations of phenomena little incentive to pursue this work in the U.S.
related to fluidization have been referenced in During the 1960's, much of the work of ap-
the literature since the late 1800's. Here, we will plying fluidized-bed technology to boiler ap-
try to give the reader a flavor for the origins of plications was carried out in England by the
fluidized-bed technology and the progress that Central Electricity Generating Board (CEGB)
has been made in the last two decades in apply- and the British Coal Utilization Research Asso-
ing it to steam generation. ciation (BCURA). The overall emphasis was to
The person most often cited as initiating flu- develop fluidized-bed combustion (FBC) for in-
idized-bed technology is Fritz Winkler, who in dustrial steam generation. The FBC technology
the 1920's developed the Winkler coal gasifier developed in England found its way to the U.S.
employing fluid-bed concepts; he received a in the 1960's. Pilot-plant research work was
patent for his work in 1928. With a knowledge conducted that was later used to develop con-
of Winkler's work, and a wartime demand for cepts for the construction of a 30-MW fluid-bed
COmussION
fluidkod-Sed Steam GenMton

boiler demonstration plant at Rivesville, West to a consortium agreement with Lurgi in 1983
Virginia in 1975. This plant was about 15 times for the joint commercial offering of CFB boilers.
larger than any other FBC facility in operation. Between 1983 and 1987 C-E sold a large number
Spurred on by the oil embargoes of the of CFB units for industrial and utility applica-
1970's, FBC technology was considered a tions ranging in size from 150,000 lblhr to
potential solution to the energy crisis. Many 1,100,000 lb/hr (with reheat), and firing fuels
studies and several demonstration projects were ranging from bituminous coal and lignite to an-
funded in the U. S. by government agencies, thracite waste, wood waste, and other biomass.
with C-E involved in several of them. In 1987, C-Ebigned an agreement to license the
In 1976, C-E was awarded a contract by the CFB process technology from Lurgi.
Energy Research and Development Administra- This involvement in both BFB and CFB tech-
tion (ERDA), now DOE, to design, construct, nology, with small- and large-scale units of
and test a 50,000 lb/hr FBC demonstration each type in successful operation, makes C-E
boiler for industrial applications. The boiler unique as a supplier to the boiler industry. C-E
was installed at the Great Lakes Naval Station can provide the optimum FBC boiler design for
near Chicago, Illinois, and supplied steam for any application.
space heating. A pilot plant was built at C-E's
Windsor, Connecticut, facility for process and
equipment development.1 The demonstration GENERAL DESCRIPTION
plant began operation in 1981 and showed OF FLUIDIZED-BED
promising results.2
In 1977, Combustion Engineering completed
COMBUSTION
a preliminary design study of a large-scale FBC "Fluidization" refers to the condition in ,
boiler for utility applications, funded by the which solid materials are given free-flowing,
Tennessee Valley Authority (TVA), involving fluid-like behavior. As a gas is passed upward
the design of a 200-MW demonstration unit through a bed of solid particles, the flow of gas
and an 800-MW commercial unit.3 Three years produces forces which tend to sepqate the par-
later, C-E completed a follow-on study to de- ticles from one another. At low gas flows, the
velop the final design for the 200-MW demon- particles remain in contact with other solids
stration unit.4 In 1984, a contract was received and tend to resist movement. This condition is
to provide the 160-MW FBC demonstration referred to as a fixed bed. As the gas flow is in-
boiler for installation at TVA's Shawnee Steam creased, a point is reached at which the forces
Plant in Paducah, Kentucky. This plant began on the particles are just sufficient to cause sepa-
operation in 1988. ration. The bed then becomes fluidized. The
Simultaneously with FBC development in gas cushion between the,solids allows the parti-
England and the United States, Lurgi GmbH cles to move freely, giving the bed a liquid-like
in West Germany had developed various fluid- characteristic.
bed processes for roasting of ores and various The transition from fixed bed to fluid bed is
other materials. In 1965 Lurgi developed a illustrated in Fig. 1, which plots the gas pres-
new type of fluid-bed process called a Circu- sure drop through the bed versus gas velocity.
lating Fluidized Bed (CFB), as distinct from For a fixed bed, pressure drop is proportional to
the more conventional Bubbling Fluidized the square of velocity. As velocity is increased,
Bed (BFB). This process was initially applied the bed becomes fluidized; the velocity at
to processes such as alumina calcination and which this transition occurs is called the mini-
later to steam generation. -- mum fluidization velocity, V,,. V,, depends on
In 1980, C-E was awarded a study by TVA to many factors including particle diameter, gas
develop the design of a 200-MW CFB boiler and particle density, particle shape, gas viscos- .
based on the Lurgi technology.5 This study led ity, and bed void fraction.l.6 At velocities above
COMBUSnON
Fluidized-Bed Steam Generators
I

Fixed Bubbling Turbulent Circulating


Bed Bed Bed Bed
a II I I
Increasing Flue Gas
2
n I
I
I I
Recycle Rate
Bed
?? I
......
.r
Fuel
Sorbent
- ....
.......
...........
................
......;.......
.....
............l...:
- .............. , . . a

:.:....::.:*:.
0 Tube
Bundle
I I .......................
I
Minimum
Velocity - Air --
Fluidization Velocity

Fig. 1 Plot of gas pressure drop through a fluidized Fig. 2 Generalizedfluidized-bed combustor
bed versus gas velocity

V,,,, the pressure drop through the bed remains bed. In applications where sulfur capture is re-
nearly constant and is equal to the weight of quired, limestone is used as the sorbent and
solids per unit area, as the drag forces on the forms a portion of the bed. Bed temperature is
particles just overcome the gravitational forces. usually maintained at or near 1550F (840C)
Further increases in velocity bring about by the use of heat-absorbing surface within or
changes in the state of fluidization, to be dis- enclosing the bed, because this temperature is
cussed later in this chapter. optimal for the chemical processes needed to
capture sulfur and control NO, emissions. It
CHARACTERISTICS OF FLUIDIZED-BED also avoids ash softening in nearly all fuels. At
COMBUSTION this temperature, efficient combustion can be
Fluidized-bed combustion (FBC) offers the achieved because of the relatively long resi-
power engineer design versatility for burning a dence time of fuel in the bed and the good gas/
wide variety of fuels, including many that are solids contact there.
too poor in quality for use in conventional fir- The above characteristics lead to the major
ing systems. Fuels which contain high concen- advantages of FBC:
trations of ash, sulfur, and nitrogen can be ABILITY TO BURN LOW-GRADE FUELS
burned efficiently, while meeting stringent re-
quirements for the control of stack emissions The high thermal inertia of the bed mass pro-
without the use of flue-gas scrubbers. Fig. 2 vides for stable ignition and combustion of very
shows a generalized fluidized-bed combustor. low grade fuels such as fuels high in ash and/or
In fluidized-bed combustion, fuel is burned moisture. Fuels with up to 70-percent ash and
in a bed of hot incombustible particles sus- JO-percent moisture have been successfully
pended by an upward flow of fluidizing gas. burned in a fluid bed. The high thermal inertia
Typically, the fuel is a solid such as coal, al- of the bed also provides for good performance
though liquid and gaseous fuels can be readily when firing low-volatile fuels such as anthra-
used. The fluidizing gas is generally the com- cite, anthracite culm, and petroleum coke.
bustion air and the gaseous products of com- FUEL FLEXIBILITY
bustion. Where sulfur capture is not required,
the fuel ash may be supplemented by inert ma- Because levels are held below the ash-soften-
terials such as sand or alumina to maintain the ing level, the FBC boiler is not sensitive to fuel
C0LQ)mnON
RuidW-Bed Steam Genemtors

ash characteristics. A wide range of fuels with TYPES OF FBC SYSTEMS


varying ash contents and properties can be
The state of fluidization in a fluid-bed-boiler
burned in a single boiler.
combustor depends mainly on the bed-particle
LOW NITROGEN-OXIDE PRODUCTION diameter and-fluidizing Glocitv. As shown in
Fig. 3, there are two basic fluid-bed combus-
NO, emissions are considered to come from tion systems, each operating in a different state
.two sources: oxidation of ni'bgen in the air of fluidization. At relatively low velocities and
(thermal NO,) and oxidation of nitrogen and/or with coarse .bed-particle size, the fluid bed is
nitrogen components in the fuel (fuel NO,). At dense, with a uniform solids concentration,
the low temperatures in FBC, thermal NO, is es- and has a well-defined surface. This system is
sentially zero; design features such as staged called a bubbling fluid bed (BFB), because the
combustion can significantly reduce fuel NO,, air in excess of that required to fluidize the bed
leading to low total NO, emissions. passes through the bed in the form of bubbles.
The BFB is further characterized by modest bed.
IN-SITU CAPTURE OF SULFUR DIOXIDE
solids mixing rate, and relatively low solids en-
SO, emissions are controlled within the trainment inthe flue gas. ~ h i l ~ l i t trecycle
le of
combustor by addition of a sorbent material, so the entrained material to the bed is needed to
a stack-gas SO, scrubber is not requhed. The maintain bed inventory, substantial recycle
sulfur sorbent can also react with other fuel rates may be used to enhance performance.
constituents such as vanadium, reducing down- At higher velocities and with finer bed-parti-
stream corrosion potential. cle size, the fluid bed surface becomes diffuse

Stoker Firing Fluidized-Bed Firing Pulverized Firing


(Fixed Bed) BFB CFB (Entrained Bed)

.. .. .. . . . .
.... , . .,".
)
.

Air Ash Air Ash Air Ash Ash

Velocity 8-10 ft/sec 4-10 ft/sec 15-30 ft/sec 15-30 ii/sec


(2.3-3.0 m/s) (1.2-3.0 m/s) (4.6-9.1 m/s) (4.6-6.1 m / ~ )
Average Bed
Particle Size 6,000 pm 1,000p m 100-300 pm 50 pm' -'

..

..

. Fig. 3 Relationships between stoker, fluidized-bed, and pulverized firing of solid fuels
COMBUSTION
Fluidized-BedSteam Genemtors

as solids entrainment increases, such that there The combustible loss from an FBC boiler is
is no longer a defined bed surface; recycle of predominantly a function of the amount of char
entrained material to the bed at high rates is re- that escapes the system without burning. Gen- -
quired to maintain bed inventory. The bulk den- erally, the loss from unburned volatiles is insig- =
sity of the bed decreases with increasing height nificant. The char particles are entrained
in the combustor. A fluidized-bed with these (elutriated) from the bed in the flue gas or are
characteristics is called a circulating fluid bed drained from the bed in the bottom ash.
(CFB) because of the high rate of material circu- In a BFB, the carbon loss by elutriation alone
lating from the combustor to the particle recy- can be on the order of 10 percent. Recycle of the
cle system and back to the combustor. The CFB elutriated material to the bed is an effective
is further characterized by very high solids- means for retaining the char within the system
mixing rates. long enough for efficient combustion. Combus-
Fig. 3 also shows the'typical velocity and bed tion efficiencies of 90 to 98 percent for low-
particle size for BFB and CFB combustors. Also reactivity fuels, and 99 percent for. reactive fuels,
illustrated is the relationship between FBC sys- can be achieved with recycle.
tems (BFB and CFB), stoker firing, and pul- In a CFB, there is no distinct bed as in a BFB
verized-fuel firing. As described in Chapter 4, unit. The conditions within the CFB combustor
stoker firing incorporates a fixed bed, having provide vigorous mixing as a result of the rela-
lower velocity and coarser particle size than the tively high fluidizing velocity. The very high
BFB. Pulverized firing incorporates an en- recycle rate, attained with a high-efficiency
trained bed having higher velocity and finer cyclone, provides for relatively long solids resi-
particle size than the CFB. The performance dence time within the system. Combustion effi-
differences between BFB and CFB, to be dis- ciencies of 95 to 99 percent are achievable even
cussed later, will reflect this relationship. with unreactive fuels such as petroleum coke.
CHEMICAL PROCESSES SULFUR CAPTURE

Within the bed, several interrelated chemical The use of limestone as a sulfur-capture sor-
processes occur, including combustion, sulfur bent allows sulfur emissions to be controlled
capture, and nitrogen-oxygen conversion. within the fluidized bed during the combustion
process. Limestone consists of calcium carbon-
FUEL COMBUSTION
ate (CaCO,) and various impurities. Lime (CaO)
Even at the relatively low temperatures asso- is formed by calcining the limestone to drive off
ciated with fluidized-bed combustion, the carbon dioxide [CO,).
combustion of fuel in a fluid bed is a rapid pro-
cess. The combustion rate is a function of the
reactivity of the fuel and the fuel surface area
available. Solid fuel can be considered to con-
sist of volatile matter and fixed carbon (char)
Sulfur in the fuel is converted to sulfur diox-
which remains after the volatiles are driven off.
ide (SO,) during the combustion process. Al-
Volatile combustible matter generally burns
though nearly all of the sulfur is oxidized, some
more rapidly than the residual char and can be
of the inorganically bound sulfur may be re-
viewed as a separate process from the char com-
tained in the ash. The sulfur dioxide combines
bustion. The concentration of char within the
with the calcined lime in the reaction:
fluidized bed at any given time is typically a small
percentage of the total bed material. Because
sulfur dioxide is released during the combus- SO, + CaO + 112 O2 + CaSO,
tion process, fuel-burning characteristics can (2)
significantly influence sulfur capture.
Eqs. 1and 2 indicate that a mole of calcium is The calcination process begins at around
required to capture one mole of sulfur. Then, 1300F (700C) and, as does the sulfation pro-
defining the CaIS molar ratio as moles of cal- cess, improves with temperature increases.
cium in the limestone feed to moles of sulfur in However, the most favorable combination of cal-
the fuel feed, the theoretical minimum CaIS re- cination and sulfation occurs at about 1550F
quired for a given level of sulfur removal is 111, (840C). Above this temperature, less-than-
which assumes 100-percent utilization of the optimum porosity forms, limiting the sulfation
sorbent . capacity of the lime particles. Fig. 4 indicates the
In practical systems, 100-percent utilization dependence of sulfur capture on temperature.
is impossible to attain. Because the sulfation There is considerable speculation as to why
process takes place on the surface of the lime the sulfur-capture performance falls off so rap-
particles in the bed, the lime contained in the idly with increasing temperature. One theory is
particle core is generally not utilized. Also, that sulfate material becomes fluid and coats
some SO, will escape capture if the total sor- the particles with a thin, unreactive layer which
bent surface within the unit is insufficient. shields the interior of the particle from further
Consequently, CaIS mole ratios greater than one sulfation. Another is the declining rate at
(1)are necessary. which SO, is oxidized to SO, falls off at temper-
The porosity of the particle surface formed atures above 1600F (870C). The general
during calcination is a strong factor in sulfur shape of the sulfation efficiencyltemperature
capture. Slow calcination results in a highly po- curves is common to all types of FBC systems,
rous particle with an exposed surface larger in thus suggesting a fundamental relationship.
area than that of a smooth particle of similar di- Because sorbent particle size is smaller in
ameter. As it forms, calcium sulfate tends to CFB systems (thus exposing more surface area
block the pores. Deep pores provide large surface ' per unit mass), sorbent utilization is generally
area but may plug with sulfate before being filled. better in a CFB than in a BFB. However, BFB
The optimum particle size provides the maxi- units with high recycle rates can closely ap-
mum surface that can be fully sulfated. The pres- proach the sorbent utilization of a CFB.
ence of magnesium carbonate (MgCO,) tends to
NITROGEN-OXYGENCONVERSION
enhance limestone utilization, even though it
does not participate in the sulfur-capture process NO, emissions from an FBC boiler are gener-
in the bed. This is because, in calcining to MgO, ally less than 0.3 lblmillion Btu (0.13 kg/nJ).
the MgCO, increases the porosity of the stone. Values below 0.1 lblmillion Btu (0.04 kg/nJ)
have been achieved.
1
Although at the low temperatures typical of
- FBC no atmospheric nitrogen is converted to

rn
-m 100 Increasing Ca/S NO,, laboratory data have shown that nearly all
of the fuel nitrogen is converted to NO, during
the burning process. For a typical coal contain-
OC

::!
L ing 1 percent nitrogen, the potential NO, re-
2 70 lease is roughly 3 lbslmillion Btu (1.3 kg/nJ).
3 60 Thus, secondary processes are responsible for
s the low NO, emissions.
015bO 1;50 1800 Id50 Carbon monoxide (CO) and char are strong
Temperature, O F reducing agents and appear to be the principal
factors in lowering NO,. These agents strip oxy-
gen from the NO, in a reduction reaction that
Fig. 4 Sulfur removal versus fluidized-bed produces elemental nitrogen (N,). In a CFB sys-
temperature tem, a significant portion of the total air is intro-
--
COMBmnON
Fluidized-Bed Steam Generators

duced above the grate. Fuel is normally fed be-


low these air ports, creating a substoichiome-
tric zone in the lower combustor with resulting
high concentrations of char and CO. The-reduc- - 0, 10.OF
ing conditions in the lower combustor enable
the attainment of NO, emissions of 0.1 lblmil-
4
c
0
lion Btu (0.04 kgInJ) and below. i
a,
A similar but less extreme condition can be
1.0
established in a BFB by diverting some of the 5 Band of Test Data
total air into the freeboard as overfire air. In the
bed, the carbon content is around 1percent and
z
--S
V)
the CO levels are on the order of 5000 ppm. The
CO is produced by the burning char in the bed, = 0.1
1.ox102
l l ( l l l l !

1.OXIO=
lllllUl
1.oxio4
with burnout completed within the freeboard. (Ar) (Pr)
Overfire air can be used to redistribute the com-
bustion air, although this must be done with
care to avoid the corrosion problems in the bed
that would result with substoichiometric firing Fig. 5 Correlation of particle convection Nusselt
and yet provide mixing in the freeboard. number with Archimedes number
There is also evidence indicating that NO,
emissions hcrease with increasing CaIS, espe- given emissivity radiating to the surface. The
cially at high SO, removal rates.' Thus, mini- particle convection term is usually the largest
mizing CaIS is important to NO,-emissions as term, and describes the heat transferred to the
well as to limestone cost. surface by particle contact. In practice, the
overall heat-transfer coefficient is measured,
HEAT TRANSFER the gas convection and particlelgas radiation
IN FLUIDIZED-BED BOILERS terms are calculated, and the particle convec-
Heat transfer to surfaces immersed in, or tion term is determined by difference. Then, the
bounding, an active fluidized bed occurs by particle convective component is correlated to
means of three mechanisms acting in parallel: certain physical variables for design purposes.
gas convection, radiation, and particle convec- In BFB units, the particle convective compo-
tion. The heat-transfer coefficient to the bed- nent for the active bed area can be correlated
touched surface is: reasonably well with the Archimedes number
(Ar):

H, = HI, + ' K d + Hpc (3)


where H, = total outside heat-transfer coefficient
H, = coefficient of gas convection
H
, = coefficient of particle and gas -

radiation where d, = mean particle diameter


H, = coefficient of particle convection g = gravitational constant
p, = gas density
p, = particle density
p, = gas viscosity,
The gas convection term is the smallest and all in consistent units
refers to the transfer of heat from the gas to the
surface assuming no solids present. The radia- Fig. 5 is a curve of the Nusselt number versus
tion term is usually the second-largest term and the product of the Archimedes and Prandtl
treats
. ..
the particle "cloud" as a grey body of numbers derived from experimental test
C O ~ O N
Ruidirrd-Bed S t n m 0.nUclton

results. The curve represents the following


correlation: TABLE 1. Relative Magnitude of
- Heat-Transfer Components in
Nu =
hd
= 0.31 (Ar)' Z7 (Pr)' 33
Fluidized-Bed Steam Generators
k, (5)
BFB
Bed
where
d, = the harmonic mean particle diameter H,e 0-2 Btulhr-ftZ-OF
= the total outside heat-transfer coefficient H,d 8-12 Btuhr-ftZ-OF
(excluding radiation) HPC 30-50 Btuhr-ftZ-OF
k, = the gas thermal conductivity CFB (same units)
Nu = the Nusselt number Combustor FBHEIFBAC
Pr = the Prandtl number, and
Ar = the Archimedes Number

Eq. 5 indicates that the outside convective


heat-transfer coefficient is a weak function of
particle size and that there is no significant de- dust loading is much higher. Field data indi-
pendence of the heat-transfer coefficient upon cate that such high dust loading improves the
the superficial gas velocity through the bed. convective-pass heat-transfer rates.
In CFB units, work is currently on-going to
correlate particle convective component in the
combustor with various parameters. The main There are several differences in the calcula-
determinant of combustor particle convection tion of boiler efficiency for a fluid-bed boiler as
coefficient is the bed density, which varies with compared to a stoker or pulverized-fuel boiler.
combustor height. Factors affecting the density For discussion purposes, the loss method is
profile include fluidizing velocity, velocity pro- used, as described in Chapter 6.
file, total solids inventory, bed particle size, An additional loss term is required for the net
fuel, and combustor geometry. heat loss or gain from the calcination and sulfa-
Note that CFB units sometimes use a bub- tion processes in the bed. The calcination loss '
bling-bed heat exchanger to cool ash, called a is that heat lost in calcining CaC03 to CaO, an
fluidized-bed heat exchanger (FBHE) when endothermic reaction. The sulfation heat gain
used in the main ash-circulating loop and a flu- is that from combining the SO, with O2 and
idized-bed ash cooler (FBAC) when used to CaO to form CaSO,, an exothermic reaction.
cool bottom ash. Work is being done to test the Typically at CaIS ratios above 2 , the calcina-
match between the BFB heat-transfer correla- tionlsulfation term is a net heat loss, while at
tion and calculation methods and FBHEIFBAC CalS below 2 , the term is a net heat gain.
field data. The ash sensible heat loss can be large, con-
Table I indicates the relative magnitude of the sidering the high-ash fuels frequently fired and
various heat-transfer components i n and the presence of sorbent products in the ash. On
bounding the bed, in typical BFB and CFB a high-ash fuel, the ash sensible heat loss can
steam generators. exceed 5 percent of heat input, as shown in

- The draft loss in the backpass of CFB units is


-similar to that in stoker or pulverized-fuel boil-
- ers; therefore, heat-transfer coefficients are es-
Chapter 6 . Therefore, the ash sensible heat loss
should be calculated rather than included as an
unaccountable loss.
sentially the same. However, for BFB boilers For CFB units, the use of large refractory-
operating at high recycle rates, convective-pass lined cyclones increases the radiation loss

Ad!!! 9-8
COMBUSIlON
Fluidized-Bed Steam Generatom

above that calculated from the ABMA standard most applications both BFB and CFB are tech-
curve in Chapter 6. This loss should also be cal- nically feasible. Defining the lowest-cost option
culated based on the surface area and skin tem- requires estimating capital and operating costs
perature of the refractory-lined components. for each; the comparison will vary depending
Fan heat credits should also be determined on unit capacity, steam cycle, fuel, sorbent,
and included in the heat balance. The high fan- space requirements, and emission limits.
discharge pressures used with fluidized-bed The next two major sections of this chapter
boilers result in significant thermal-energy ad- describe C-E's fluidized-bed steam-generator
dition to the boilers. Other loss terms are the designs in more detail, including process de-
same for fluid-bed boilers as for other types of sign parameters and typical equipment.
boilers, as covered in detail in Chapter 6.
BFB VERSUS CFB ,
BUBBLING FLUIDIZED-BED
The question of which system, BFB or CFB, is
best for a given application is frequently asked
STEAM GENERATORS
but is usually difficult to answer. In certain ~ i ~ .illustrates
-6 a general form of BFB steam
cases, such as very low SO,/NO, emission generator. Crushed fuel and sorbent are fed to
limits, CFB may be the only choice. Also, there the top or bottom of the bed. Fluidizing air is
is currently more commercial experience with supplied to the bottom of the bed through a
CFB units\on a wide range of unit capacities, plenum and air distributor. Combustion and
steam cycles, and fuels which can influence sulfur capture (presuming a sulfur sorbent is
user selection for new projects. However, for used) take place in the bed, with the flue gas

- Flue Gas

Convective Pass -
Dust Collector
- 0

FuelISorbent Feed
(Overbed) Ash to
............
7. Recycle Disposal
: . .: ...<.
....':.; ..... :,, ... .: ...;
. . . . . . . . . . ........:.. ....... 0
::.;: ::;:::'.';:'.. .:',' ..........
Bed ......................... . ( .
.. .. ....... .. .. ....... .. . :..,,.......... 0 Air Distributor

Air - .; . . . . . . . . . .: .... ...:,-:;,: 7


.-- ..'..'..--..'... /*:

Fuel/Sorbent Feed
(Underbed)
- Ash Cooler

Bottom Ash

Fig. 6 Typical bubbling fluidized-bed(BFB) steam generator


.-
COrnON
FluMIzod-8.d Steam Generators

and some entrained solids passing into the sec- released from the fuel can also escape through
tion of the combustor above the bed surface, the bubbles without fully contacting the sor-
called the freeboard. In the freeboard, addi- bent materials in the bed.
tional combustion and sulfur capture can take The selection of system parameters is impor-
place. From the freeboard, the gas and solids tant in achieving good mixing without promot-
enter the convective pass where they are cooled ing gas bypassing. This is accomplished by
before entering a mechanical dust collector designing the bed so that the gases in the bub-
(MDC). The MDC collects the entrained solids bles are rapidly exchanged with gases from the
for recycle to the bed or for disposal. Flue gas non-bubbling regions of the bed. The non-bub-
from the MDC passes to an air heater, fine-par- bling part of the bed is essentially at the mini-
ticulate collector, and induced-draft fan. Bed mum fluidization condition and is referred to
temperature is maintained at the optimum for as being in the emulsion phase.
sulfur capture and combustion efficiency, usu- The bubbles rise through the emulsion and
ally by means of the water-cooled walls of the produce agitation. The effectiveness of gas in-
combustor andlor a tube bundle immersed in terchange between the bubbles and emulsion is
the bed. Bed level is controlled by draining and a function of the bubble size and apparent vis-
cooling an appropriate amount of material from cosity of the emulsion phase.
the operating bed. One parameter that can be modified in de-
signing the fluidized bed for efficient gas mix-
PROCESS CONSIDERATIONS
ing is the mean bed particle size. At a given gas
At minimum fluidization velocity, a cushion velocity, the volume of gas in the bubbles de-
of gas separates the bed particles from one an- pends upon the minimum fluidization velocity,
other. Increasing the velocity does not signifi- which is affected by particle characteristics.
cantly increase the separation distance. Rather, The particle size and density influence the ap-
the gas volume in excess of that required for parent viscosity of the bed which, in turn, af-
minimum fluidization forms bubbles in the fects the average bubble size and rate of bubble
bed. Bubble formation provides a lower resis- growth. With a mean bed particle size of 1000
tance path for gas flow. The shape, size, and micrometers (1millimeter), near-optimum con-
growth of the bubbles significantly affect bed ditions can be maintained over a range of oper-
performance. ating conditions with fluidizing velocities from
The volume of the bubbles causes the bed about 2 ftlsec to about 10 ftlsec (0.6 to 3.0 mls).
depth to increase over that of minimum fluid- For a specific application, it may be desirable
ization. The ratio of operating bed depth to the to choose a finer or coarser bed-material sizing.
depth at minimum fluidization is called the ex- For example, a low-reactivity, high-sulfur fuel
pansion factor. An expansion factor of 1 . 5 to 2 such as petroleum coke may require a deep bed
is typical. with a low design superficial velocity; this
The bubbles provide an important function would serve to increase the residence time for
in mixing the bed. At minimum fluidization ve- both the fuel-burning and sulfur-capture pro-
locity, there is very little particle movement. Re- cesses. In such an instance the bed particle size
active feed materials such as coal and limestone could be reduced while still maintaining desir-
would not be well dispersed within the bed. able bubble conditions. As a secondary benefit,
The bubbles agitate the bed and induce mixing. the smaller particle size results in a greater sur-
On the other hand, the bubbles can provide a face area per unit mass for the sorbent bed ma-
path for the bypassing of gases through the bed. terial. Improved sulfur-capture efficiency is a
If the system is improperly designed, a major possible advantage as a trade-off to lower heat
portion of the air required for combustion can release per unit of bed plan area.
pass through the bed as bubbles without ade- In the freeboard, large solids that are ejected
quately contacting the fuel. The SO, and NO, from the bed surface separate from the gas flow
COMBUSTION
Fluidized-Bed Steam Generators I
l

and fall back into the bed. The freeboard is con- and overbed. Underbed systems include pneu-
sidered to terminate at the level at which the matic as well as mechanical means such as
gas velocity significantly increases, usually on screw feeder; and ram injectors. The common
entering a convective heat-transfer section. feature is that the fuel is introduced at the bot- -
The freeboard can be considered as a second tom of the bed. On the other hand, overbed sys-
reactor in series with the fluidized bed. The tems use devices such as spreaders to throw the
freeboard serves as an important region in fuel onto the bed surface. Both types of feed sys-
which additional combustion and sulfur cap- tems are shown in Fig. 7.
ture occur. Solids which leave the bed and free- Underbed feed is the method which takes
board are captured in an MDC downstream best advantage of the bubbling-bed dynamics.
of the combustor. These solids can be recycled The fuel is typically introduced by a pneumatic
back to the bed, providing additional reaction feed system through nozzles located just above
time for the char and sorbent particles. The the air distributor. For adequate fuel distribu-
amount of recycle is generally described as a re- tion, generally one feed nozzle is provided for
cycle ratio, -equal to the recycle mass flow di- each 20 ft"(1.9 my of bed area. The nozzles are
vided by the fuel mass flow. For BFB systems designed to inject the fuel laterally with a
burning typical bituminous coals, the recycle velocity of about 50 ftlsec (15 mls) to increase
ratio is usually selected in the range from 1:1 to dispersion. The fuel is usually limited to a top-
3:l. 1.Vhen firing a typical bituminous coal, size in the range of to 112 inch (6 to 13 mm) to
with flue-gas flow about ten times coal flow, a facilitate pneumatic conveying. This size range
recycle ratio of 1:1 gives a solids concentration also provides a large number of fuel particles
in the freeboard of approximately 10 percent by per unit mass which contributes to a nearly
weight. This solids concentration provides uniform distribution of fuel within the bed.
high sulfur capture and combustion efficiency As compared to overbed, the benefit of under-
as the SO,, char, and combustioh air react. bed feed is improved performance, particularly
with regards to sulfur capture. With the fuel in-
FEED SYSTEMS
troduced upstream of the bed, most SO, (espe-
The fuel feed system has a major impact on cially that from the fuel fines) is released in the
the performance and design of BFB units. Two bed and so has an opportunity to contact the
basic types of feed systems are used, underbed sorbent in the bed. Thus sorbent utilization is

Underbed (Pneumatic) Overbed (Spreader) -

Storage
Bin I 4
.,::.; :. .:;. ""':'
Freeboard
Feeder
Storage

$ .. .. ..,:.::'; ,:.. :: Bed Freeboard


'

Feed
Nozzle Plenum Spreader ~::..:;~,.:..'; :. ~~d
Feed
Bin . ... ..'.::.:
Plenum

Feeder

Compressor

Fig. 7 Fuellsorbent feed systems for BFB boilers


--
C O ~ O N
Ruidked-Bed Steam Generators

generally better with underbed feed. Also, un- formed during combustion, will sink to the bot-
derbed feed is more tolerant of fuel fines, which tom of the bed. A layer of large, dense particles
are generally burned in the bed. Further, in- can form at the bottom of the bed and disrupt
creasing bed depth can provide acceptable per- fluidization.
formance for fuels of low reactivity andlor of Overbed feed is most appropriate for highly
high sulfur content. reactive fuels with low sulfur content and for
The drawback of underbed feed is its in- fuels very high in ash. With reactive low-sulfur
creased complexity. Relatively small pneumatic fuels (such as certain subbituminous coals and
conveying lines limit the surface moisture of lignites) the combustion efficiency can be quite
the material being transported to about 6 per- high even with minimal recycle. Also, because
cent maximum in order to avoid line pluggage. the required sulfur capture is low, SO, bypass-
This will usually require a dryer in the fuel- ing the bed is not a concern. With high-ash
preparation system. Also, the point of fuel in- coals and oil shales, the fuel is relatively dense
troduction at the base of the bed is typically at a and contains sufficient inerts so that a small
positive pressure of 40 to 50 "WG (11/2to 2 psi, particle such as 314 inch (20 mm) or smaller can
or 10 to 12.5 kPa). Adding to this the pressure be uniformly spread. Sulfur-capture efficiency
lost in the conveying lines and splitter, the feed can still be a problem, but often the fuel ash can
system must move the fuel from atmospheric contain a large amount of calcium. The lime-
pressure to 5 to 10 psig (35 to 70 kPa gage). stone additive required for sulfur capture may
The main benefit of overbed feed is that it is then be negligible or no greater than in the sys-
much simpler than underbed methods. The tem designed for high-sulfur fuel. Overbed feed
fuel is sized as in typical spreader stoker appli- is also more appropriate where simplicity
cation to 1to 2" (25 to 50mm) topsize. With the rather than performance is the main concern.
type of equipment involved, this size material
is much easier to feed when wet, so fuel drying
DISTRIBUTION OF HEAT RELEASE
is not required.
The principal limitations in using overbed Within the BFB combustor, fuel heat is re-
feeding arise where high performance is re- leased both in the bed and in the frdeboard. Bed
quired, especially for sulfur capture. From a temperature is maintained at the desired level
process point of view, overbed feed injects the usually by heat transfer to furnace-wall tubes
coal downstream of the primary reactor. For and other tubes immersed in the bed. As indi-
combustion, this may not be a major problem cated previously, the heat-transfer rate to these
because high recycle rates and overfire air can tubes is very high. Thus it is cost-effective to
enhance fuel burnout in the freeboard. But the maximize the amount of heat released in the
bed is ineffectively used in a system where sul- bed. The amount of heat released in the free-
fur capture is a main objective. Larger particles board is expressed as a'percentage of the gross
which settle on the bed will liberate volatiles, a heat fired, and is referred to as the freeboard
large source of SO,, at the top of the bed. Fines heat release (FBHR). With an underbed feed
will burn before reaching the bed and liberate system and a bed designed to minimize gas by-
SO, in the freeboard. All of this SO, bypasses passing, the FBHR is typically in the range of
the sorbent in the bed. Screening of the coal to 10 to 15 percent. With an overbed feed system,
eliminate fines, and water sprays to avoid fines the FBHR is in the range to 20 to 30 percent,
burning in the freeboard have been tried to off- thus shifting heat duty to the freeboard and
set this limitation. convective pass- where heat-transfer rates are
Overbed feed also requires closer attention to much lower than in the bed.
removal of rock and other inert material fed to
HEAT-DUTY DISTRIBUTION
the bed. With overbed feed, this material can be
quite large and, along with any ash particles The location of evaporator, superheater, and

All!
COMBUSPION
Fluidized-Bed Steam Generators

reheat heating surface within the combustor bles, avoids excessive erosion, and retains a
and convection pass is designed to minimize margin in fluidization velocity above minimum
total cost while providing the proper perfor- fluidization for turndown purposes.
mance characteristics over the complete range- Bed particle size depends on the fuel and sor-
of unit operation. bent sizing and the decrepitation characteris-
Usually, the combustor enclosure is com- tics in the bed. For a given design velocity,
posed of welded water-cooled tubing and does bed particle size then determines the state of
evaporative duty. In-bed tube bundles are used bed fluidization.
for evaporation and for superheater and re- Bed depth is usually set at 2 ft. (0. 6 m) in the
heater service. The convective pass contains su- slumped condition, which results in about 4 ft
perheater, reheater, economizer, and air heater
surface. With a reheater, a split backpass can be
used, with reheat steain temperature controlled
TABLE 11. Typical BFB
by gas-biasing dampers.
Process Parameters
PROCESS PARAMETERS
Fuel . Overbed Feed Underbed
Table I1 contains a list of typical BFB process Feed
design parameters.
Feed size affects both operation and perform- Top size 25-50 mm 10 mm
ance. For overbed feed, fines must be limited as Moisture - < 6 percent
they will be entrained in the gases leaving the (surface)
bed and so not come in contact with sorbent, Fines < 25 percent < 2 0 percent
leading to higher SO, emissions. Excessive fines minus minus
16 mesh 30 mesh
can also lead to more-than-desired burning
in the freeboard or localized hot spots near Sorbent
the feeder. For underbed feed, the fuel must be
properly sized for pneumatic conveying. High Top size 5 mm
topsize leads to a requirement for excessive * d50 800-1400 micrometers or pm
transport line velocity and, as a result, poten- Combustor
tial for erosion. The fuel must have surface
Bed Temperature 1560-1650F
moisture less than 6 percent to avoid pluggage
in the transport lines. Sorbent size is selected Bed Velocity 4-10 ftlsec
Bed Particle Size 500-1200 micrometers (pm)
to maximize sorbent utilization; striking a bal-
ance between bed solids residence time and Bed Depth
(slumpedlactive) 24"/4BW
surface area.
In the combustor, bed temperature is con- Bed Pressure Drop 20-50"WG
trolled in the range of 1560 to 1 6 5 0 F (850 to Recycle Ratio 0 to 511
9 0 0 C ) , for good combustion efficiency and Performance
sulfur capture. The lower temperatures are used
Carbon Loss 2 to 5 percent or lower
with higher sulfur fuels, such as bituminous
coal, to maximize sorbent utilization. The Ca/S 2.3 to 3.0 (for 9 0 percent .

higher temperatures are used with high-ash SO, capture)


fuels, such as anthracite culm, to maximize so, 300 ppm or less
burnout. Freeboard temperature is designed to Co 250 ppm
NO, 150 ppm or less
the same temperature range as the bed.
Design bed velocity is usually 8 ftlsec (2.4 mls). 'd,, is the diameter at the 50 percent point of a Rosin-Rammler
logarithmic probability plot of particle size versus percent passing
This velocity provides a reasonable plan area, thmugh a given sieve size.
avoids excessive airlgas bypassing via the bub-
.-
(1.2 m) active bed height, and an expansion fac- surface is present, bed level generally is re-
tor of 2. Design bed depth is adjusted (along duced before start-up to avoid having the tube
with bed velocity) to match fuel characteristics. bundles in the active bed. This minimizes both
A deeper bed and lower velocity are used with heat losses from the bed and bed heat-up time.
harder-to-burn fuels, or fuels requiring high When the start-up section is heated ade-
sulfur capture. quately, solid-fuel feed is started. An increase
Bed pressure drop is mainly a function of bed in bed temperature verifies solid-fuel ignition,
depth. Deeper beds, while yielding better per- and fuel and air flows are raised to bring bed
formance, also require more fan power. Recycle temperature -up to design. With a multi-zone
of entrained material to the bed improves car- bed, load is increased by fluidizing a zone adja-
bon burnout and sorbent utilization. Given the cent to the start-up zone, bringing the newly
fineness of the entrained material and the fluidized one to the solid-fuel ignition tempera-
multi-cyclone collection efficiency, optimum ture, and then firing additional solid fuel. This
recycle rates are in the range of 111to 511. process is repeated until all zones of the bed are
at temperature on solid-fuel.
PART-LOAD OPERATION
SYSTEMS AND COMPONENTS
Turndown, or part-load operation, of a BFB
is achieved by one or both of two methods. The The following sections cover the major sub-
simplest is called velocity turndown. In this systems within the BFB boiler island. Typical
method, fuel and airflow are reduced to the en- equipment is described, along with the major
tire bed. The bed cooling bundle is designed so performance criteria affecting design.
that as airflow and, therefore, active bed level FUEL PREPARATION
are reduced, bed temperature is maintained at Selection of fuel-preparation equipment de-
or near the optimum. This method alone is usu- pends on the type cif feed system. Overbed feed
ally effective down to 70-percent load only. The systems can tolerate relatively high-moisture
other method is called bed zone slumping. The content fuel, so the preparation system is lim-
air plenum is divided into zones so that the ited to a primary crusher providing 1 to 2 in.
air supply to each zone is separately controlled. (25 to 50mm) topsize material. ~ n h e r b e dfeed
As load is reduced, sections of the bed are systems with pneumatic transport must limit
slumped (defluidized). This allows the main- both topsize and surface moisture to avoid
taining of temperature at the required levels in pluggage of conveying lines. Thus, the fuel- -,
the active zones. With this method, turndown preparation system contains a crusher supply-
to 25-percent load and below is easily achieved. ing '14 in. (6mm) topsize material followed by a
dryer. The dryer can take several forms. One
START-UP
type is the flash dryer, in which the crusher
Start-up of the unit is accomplished by start- product is fed to a drying column containing an
up burners firing oil or gas. These burners can upward flow of hot gas (typically boiler flue
be located underbed in the air plenum, or over- gas). The fuel is dried in the column, separated
bed. Underbed burners heat the bed to solid- from the drying gas, and conveyed to the feed
fuel ignition temperature (typically 1000F or system (see reference 8).
540C for coal) by first preheating the air to be- An alternate system under development seeks
tween 1200 and 1400F (650 and 760C). Over- to eliminate the dryer for underbed systems by
bed burners fire onto the bed surface, thereby mixing the wet fuel with recycle material (that

-
heating the bed material directly.
-Because only a portion of the bed is usually
heated during start-up, the gas or oil heat-input
material collected by the multi-cyclone for re-
cycle to the bed).g.lO The hygroscopic compo-
nents of the recycle material, CaO and CaSO,,
requirement is minimized. The start-up section react with the water in the fuel to yield a free-
may or may not have in-bed surface. If in-bed flowing material. .
coMBUSTION
Fluidized-Bzd Steam Generators

SORBENT PREPARATION
.-

Limestone may be purchased with the de- Coal & Limestone


Inlet
sired feed-size specification or may be prepared
directly at the plant. Smaller.instal1ations will
typically purchase properly sized limestone
and have it pneumatically conveyed into storage
tanks. Larger plants will prepare the limestone
in a separate yard facility with the system in-
cluding an impact crusher and size classifiers
with the required conveyors. The sized lime-
stone is transported to storage tanks.

FUEL FEED

The fuel feed system introduces the fuel ei-


ther above the bed (overbed)or at the base of the
bed (underbed).
The overbed feed system uses mechanical
spreaders to distribute the fuel uniformly
across the top of the bed. Underbed systems
To Fluidized Bed
typically use a pneumatic transport system to
distribute the fuel (and often sorbent mixed
with the fuel) uniformly throughout the bed. A Fig. 8 Fluidized splitter for dividingfuel flow to bed
lock hopper, solids pump, or similar device is feed lines
required to bring the fuel from atmospheric
pressure up to conveying-line pressure. the bed. The air may be preheated in an air
Fuel feed nozzles must be located every 20 to heater. A positive-displacement or rotary
30 ft"(1.9 to 2.8 my of bed plan area for good blower supplies conveying air at a higher pres-
fuel distribution. The main-fuel stream from sure level for pneumatic transport.
the lock hopper or solids pump must then be Fluidizing-air nozzles, or bubble caps, are
split into several streams. For this purpose, C-E located at the base of the bed for proper distri-
uses a fluidized splitter (see Fig. 8) which bution of fluidizing air to the bed. The nozzles
fluidizes the incoming fuel stream in a low- are designed to avoid backsifting of bed mate-
velocity bed. The fuel overflows uniformly into rial into the air plenum. Nozzle pressure drop
the individual feed lines within the bed. Splitter is selected to ensure adequate air distribution
fluidizing air becomes the feed-line conveying air. during low-load operation.
SORBENT FEED COMBUSTOR

The simplest way to feed limestone is to the The combustor includes the bed and free-
top of the bed through a gravity feed chute. board regions. The enclosure is usually water-
Such a system does not show significantly dif- cooled and formed from gas-tight finned or
ferent sorbent utilization compared with under- fusion-welded panelled tubing, including the
bed feed. bed floor which contains the air nozzles and
the fuel/sorbent/recycle feed nozzles (if an un-
AIR SUPPLY
derbed feed system is used).
A forced-draft fan supplies fluidizing air to a To maintain bed temperature at the required
plenum which is usually partitioned to allow value, horizontal tube bundles are immersed in
control of the airflow to individual sections of the bed. Proper design and layout of the tube
-
C0)dBDSZlON .
Fluidized-Bed Steam Generators

bundle and the tube-bundle supports are criti- RECYCLE SYSTEM


cal to long-term performance. The bottom tube For units with recycle, a mechanical dust col-
in the tube bundle is usually located about 2 ft lector collects material entrained from the bed.
(0.6m) above the fluidizing nozzles, to avoid The device most often used is a multiple-tube
erosion from the air nozzles and to allow for ac- cyclone. To provide a substantial recycle ratio,
cess between the floor and bundle. The lower- collection efficiency must exceed 90 percent.
most tubes in the bundle are frequently coated Material collected by the MDC is either sent
with erosion-resistant material or are studded to disposal or recycled to the bed. Like the fuel
or finned to avoid erosion. Vertical or inclined and sorbent, the recycled material can be fed
tubing in the bundle is especially susceptible to overbed or underbed. With overbed feed, the re-
erosion. A C-E developed coating called Extend- cycle material is pneumatically injected from a
alloy has proven quite effective in preventing few locations just above the top of the bed. 127ith
such erosion. The tube-bundle supports must underbed feed, the recycle material is elevated
accommodate the gravity and vibrational forces to conveying-line pressure by a lock hopper.
on the tube bundle without allowing differen- solids pump, or seal pot (also called a J-valve).
tial movement between bundle and support. For reasonable distribution, recycle feed noz-
C-E has developed several proprietary tube- zles must be located every 40 ft2(3. 7 m2)of bed
bundle support designs, both mechanical and area. Thus, a splitter is also required on the re-
fluid-cooled, which have demonstrated thou- cycle feed system. C-E uses the fluidized split-
sands of hours of trouble-free service. ter for recycle material as well as feed material.
The combustor can be top-supported, bot-
tom-supported, or a combination of the two. AIR HEATER
The high mass of the bed material makes bot- The relatively high airlgas pressure differen-
tom support of the bed area attractive. tials affect air-heater selection for BFB applica-
Circulation Systems tions. Low-leakage designs such as tubular,
heat-pipe, and plate-type air heaters have been
The walls of the combustor are cooled by nat- considered. Also, the development of advanced
ural (thermo-syphonic) circulation of the leakage-control systems for Ljungstrom@ air
steam-water mixture. In-bed evaporator surface heaters, as described in Chapter 14, has led to use
can also have natural circulation, as long as the of such on several BFB units.
tubing is inclined. On larger units, inclined Use of steam or hot-water preheaters, or a
tubing is not practical, because the element cold air bypass, is required to maintain air-
lengths dictated by the bed depth and the angle -heater average cold-end temperature (ACET)
of incline are much shorter than large beds re- above typical limits. While theoretically the
quire. On such units, the in-bed evaporator ACET could be reduced for fluid-bed boilers
bundle uses horizontal tubing and assisted (because of the low SO,/SO, in the flue gas from
(positive) circulation. sorbent addition and unreacted lime in the fly-
ash) more operating experience on a wide range
CONVECTIVE PASS of fuels is needed to verify this.
The convective pass is of the same basic de- ASH REMOVALICOOLING
sign as used in a pulverized-fuel or stoker-fired
unit. The enclosure walls are water or steam- The ash-removal/cooling system includes
cooled tubing, or duct plate, depending on gas both _thebottom-ash and flyash systems.
temperature. Retractable or rotary sootblowers Bottom-Ash Removal System
are used to keep convective surfaces clean, al-
though the ash is powdery with little tendency The main function of the bottom-ash removal
to adhere to tubing surfaces. system is to maintain the desired bed level, or
COMBrnON
Fluidized-Bed Steam Genentom

inventory. Bed inventory affects performance in system can be used to transport the material to
a number of ways, as described earlier. To de- an intermediate hopper from which the ash can
fine bed level, a series of pressure taps are used be conveyed penumatically to storage. - . _
to locate the active bed surface, while to define
Flyash Removal System
bed inventory the total pressure drop across the
bed is used. The rate of bottom-ash flow is then Most fluidized-bed boilers have fabric filters for
adjusted to give the desired value of levellin- final particulate cleanup. Flyash from the econ-
ventory. The bottom-ash system can also con- omizerlair-heater hoppers, MDC, and baghouse
trol the accumulation of oversize material, or ESP is typically handled with a vacuum
which in turn can result in poor fluidizing and pneumatic system. No ash cooling is necessary.
nixing, as well as localized defluidization. The bottom-ash and flyash streams can be
LVith an overbed feed system, there is a greater stored separately or together. An ash condi-
possibility for feed of oversize, and so greater tioner (see Chapter 16) is used to prepare the
care must-be taken to provide a sufficient num- ash for transport to disposal.
ber of properly located bed drains which can Chapter 16 describes the complete scope of
accommodate relatively large material. With an ash-handling equipment available for use on
underbed feed system, the opportunity to feed FBC boilers.
oversize is much less. Providing a bed drain for There have been many studies of the possible
every 100 to 200 ft"9 to 19 m') of bed area is uses for flyash and bottom ash. Its free-lime
generally qdequate for control of bed level1 content has led to testing of FBC ash as a substi-
inventory and oversize. tute for cement, with some success. Other uses
Particularly with an overbed feed system, it investigated include: extender in asphalt mix,
may be advantageous to classify the bed-drain substitute for gypsum in gypsum board and
material by reinjecting the fines and passing conditioner for soil.1 Most often, however, the
only the coarsest fraction to the bottom-ash sys- ash is disposed of as land fill.
tem. This arrangement helps remove rocks and
such from the bed without excessive ash flow to
INDUSTRIAL APPLICATION
downstream equipment. The classifier can op-
erate continuously or in batch mode and can Fig. 9 is an example of a C-E BFB design for
also provide some cooling of the ash. industrial application. This type of unit is
The bottom ash must be cooled from combus- called the Fluidized Bed Modular (FBM) unit
tor temperature to 250 to 450F (120 to 230C) as it is designed for shop fabrication and ship-
before entering the bottom-ash conveying sys- ment in a minimum number of large sections.
tem. Bottom-ash cooling is accomplished gen- The FBM unit can operate over a wide load
erally by water-cooled screws. Where it is range while maintaining superheated steam
economical to recover the sensible heat in the temperatures close to the design value. A boiler
bottom-ash stream, an air-cooled multi-tube firing oil, natural gas, coal, or waste fuel can be
heat exchanger can be used. In this device the designed for capacities from 70,000 to more
ash leaves the bed and flows down into the than 350,000 pounds of steam per hour (10 to
cooler, which consists of several tubes in paral- more than 45 kgls). The boiler uses an in-bed
lel over which air is blown. Heat from the ash is superheater, a bottom-support design, and an
transferred to the air which is then mixed with overbed, underbed, or combined feed system.
the main fluidizing air. The large freeboard allows the use of overbed
From the cooler, the ash passes to the bottom- feeding for suitable fuels.
ash conveying equipment for transport to stor-
UTILITY APPLICATION
age. The transport system can be either a
mechanical system with flight conveyors or a An example of a C-E BFB design for utility
pneumatic system. Alternately, a mechanical applications is the TVA 160-MW demonstration
CoXBmnON
FMdizuf-Bed Steam Generators

Recycle Tank Dust Collectors

Fig. 9 C-E bubbling fluidized-bed (BFB) boiler for Fig. 10 Arrangement of TVA 160-MW BFB
industrial applicatidn steam generator

boiler, located at TVA's Shawnee Steam Plant Ljungstrom air heater is used. Fuel, sorbent,
near Paducah, Kentucky. The boiler is designed and recycle material are pneumatically fed un-
to produce 1,100,000 lblhr (139 kgls) main derbed. Further details of the design are con-
steam at 1005OF (541C), 1800 psig (12.4 MPa tained in references 1 2 , 13, 14, 15.
gage), firing a Kentucky bituminous coal. The
boiler is the largest fluidized-bed boiler in the
world. The plant utilizes the existing steam tur- CIRCULATING FLUIDIZED-BED
bine, condenser, feedwater system, coal yard,
fabric filter: induced-draft fan, stack, and flyash
STEAM GENERATORS '-

transport equipment. Fig. 10 is an isometric Fig. 11 shows a typical CFB steam generator.
view of the boiler. Crushed fuel and sorbent are fed mechanically
The combustor consists of a single large bed or pneumatically to the lower portion of the
with freeboard above. The air plenum below the combustor. Primary air is supplied to the bot-
bed is divided into twelve zones, with the air- tom of the combustor through an air distributor,
flow separately controllable to each zone. The with secondary air fed through one or more ele-
bed contains several sections of evaporator and vations of air ports in the lower combustor.
intermediatelfinishing superheater tube bun- Combustion takes place throughout the com-
dles, with mechanical bundle supports. The bustor, which is filled with bed material. Flue
convective pass which is located above the free- gas and entrained solids leave the combustor
board in a tower configuration is split, with the and enter one or more cyclones where the
reheater on one side. Downstream gas-biasing solids are separated and fall to a seal pot. From
dampers control reheat steam temperature. An the seal pot, the solids are recycled to the com-
MDC collects flyash for recycle or disposal. A bustor. Optionally, some solids may be diverted
COMBVSIlON
Fluidized-BL~Steam Generators

- 0
0
Combustor Convective Pass
-0

Air
Fuel/Sorbent Feed

Air Distributor

Bottom Ash

Fig. 1 7 Typical circulating fluidized-bed (CFB) steam generator

through a plug valve to an external fluidized- ties greater than 10 ftlsec (3 mls) with mean bed
bed heat exchanger (FBHE) and back to the particle size smaller than 500 micrometers. A
combustor. In the FBHE, tube bundles absorb large fraction of the bed mass is small enough to
heat from the fluidized solids. be entrained in the gas stream. This material
Bed temperature in the combustor is essen- must be collected and recycled to maintain bed
tially uniform and is maintained at an optimum inventory. The distinction between bed and
level for sulfur capture and combustion effi- freeboard has faded, and bubbles are no longer
ciency by heat absorption in the walls of the apparent. The pressure drop from the bottom to
combustor and in the FBHE (if used). Flue gas the top of the combustor follows a smoothly de-
leaving the cyclones passes to a convection clining gradient, as illustrated in Fig. 12.
pass, air heater, baghouse, and ID fan. Solids Even though the gas velocity is above the en-
inventory in the combustor is controlled by trainment velocity of most particles in the bed,
draining hot solids through an ash cooler. the entire bed is not entrained out of the com-
bustor. This is because the particles tend to
form "clusters" which break-up, reform, and
PROCESS CONSIDERATIONS
move up and down within the combustor.
Circulating fluidized-bed conditions (also (Clusters in a CFB are somewhat analogous to
called fast fluidization or lean phase fluidiza- bubbles in a BFB. )The gas velocity is below the
tion) are achieved as fluidization velocity is in- entrainment velocity of the cluster. The clusters
creased past the bubbling regime (see Fig. 1). thus allow maintaining considerable bed inven-
CFBconditions are generally attained at veloci- tory at usual CFB velocities, and also account
!

rklAi
I
Top of Cornbustor- i
C
r
Outlet

solids Inlet
Upper Secondary Air-
I
Refractory 1
Bed Pressure Drop

I I
Fig. 12 Circulating fluidized-bed combustor pres-
sure profile

for considerable internal bed recirculation. The


entrained material is of a large enough size to
be captured by a cyclone for transport back to
the bed. This process results in substantial ex- Compartment I
ternal recycle and leads to excellent mixing and
gas-solids contact with high performance in
terms of combustion efficiency and sorbent uti-
i
Fig. 13 Typical fluidized-bed heat exchanger
lization. Recycle ratios of 10 to 100 and greater (FBHE) with refractory-lined steel-plate enclosure
are typical and are required to maintain the de-
sired high solids concentration in the combus-
tor. When firing a typical bituminous coal with tageous.16 The FBHE is a bubbling-bed heat ex-
flue-gas flow ten times the fuel flow, a recycle changer with one or more compartments
ratio of 10 provides a solids loading of 1 Ib containing immersed tube bundles, as illus-
solidsllb gas at the combustor outlet, while a re- trated in Fig. 13.
cycle ratio of 100 provides a solids loading of 10
lb solidsllb gas at the combustor outlet. At these Additional Heat Duty
solids loadings, the temperature is essentially The FBHE is an alternate means to remove
uniform throughout the combustor and cy- heat from the hot solids in the primary solids
clone, and the mixing rates are extremely high. recirculation loop (primary loop), and can re-
Because of the high mixing rates, only a simple duce the combustor size. Combustor plan area
fuellsorbent feed system with a few feed points is proportional to unit capacity since design
is required. fluidizing velocity is fixed. As capacity in-
FLUIDIZED-BED HEAT EXCHANGER
creases, the combustor must get taller in order
to absorb the required heat in its walls. At some
For smaller units (less than, say, a steam flow capacity (in the range of 500,000 l b h steam, or
of 500;000 l b h or 63 kgls) with a single design 63 kgls), a combustor height of 100 to 110 ft (30
fuel, an FBHE is not needed. For larger units, to 33 m) is reached. Combustor heights greater
particularly with reheat cycles or with a wide than this offer diminishing returns because
range of design fuels, an FBHE is highly advan- heat-transfer rates are low 'in the upper combus-
COlldBUSIlON
Fluldlzed-Bed Steam Gememtors I

tor and additional fan power is required to heat leaving the primary loop (hence more pri-
achieve a desired solids loading at the combus- mary-loop duty) at optimum firing conditions.
- - - tor outlet. C-E normally supplies an FBHE on The FBHE can be used to adjust primary-loop
units above about 500,000 l b h (63 kg/s) capac- heat absorption when switching fuels, allowing
ity. The alternative to the FBHE is surface the same combustor to maintain optimum fir-
within the combustor bed such as pendant or ing conditions on each fuel. For example, when
horizontal surface. Precautions must be taken to switching from wood to anthracite, solids flow
avoid excessive erosion of this surface. to the FBHE is increased to augment primary
loop duty, while combustor temperature and
Alternate Fuels
excess air can be maintained at optimum levels.
Different fuels produce different volumes of This is illustrated in Fig. 14.
flue gas per unit of heat fired. For maximum
efficiency, it is necessary to fire each fuel at
optimum conditions for sulfur capture and Total
combustion efficiency. This can require a sig- 100-
C
nificant variation in the heat absorption re- 0
quired from the primary loop for a wide range
of fuels. Table I11 shows various fuels along 8
with the flue gas each produces. Also shown
for each fuel is a term defining the heat in the
flue gas leaving the primary loop as a percent of
heat input. As indicated, a low-grade, high-
moisture fuel such as wood produces large vol- s
umes of gas and a relatively large percentage 0 I I I I 1 I
0.35 0.40 0.45 0.50 0.55 0.60
of heat leaving the primary loop (hence lower Btu Products (at Combustor Outlet)
primary-loop duty) at optimum firing condi- per Btu Fired
tions. At the other end of the fuel spectrum, an-
thracite produces relatively low flue-gas
volumes and a relatively small percentage of Fig. 14 Total heat-duty distributionfor various fuels

TABLE 111. Relative Flue-Gas Volumes and Heat-Absorption Patterns for


Various Fuels
Optimum Lb. Combustion BTU Combustion
Combustion Products (Wet] per Products*
Fuel Temperature0F 106BTU Fuel Fired BTU Fuel Fired

Wood Waste 1560 1,329 0.571


Spent Sulfite Liquor - 1560 1,181 0.562
Anthracite Culm 1650 1,035 0.447
Anthracite 1650 1,015 0.436
Lignite 1560 1,031 0.431
No. 6 Oil 1560 1,006 0.417
Petroleum Coke 1560 1,004 0.403
Bituminous Coal 1560 992 0.400
Natural Gas - 925 0.391
'At the combustor outlet
COMBUSRON
FfuMIzed-Bed Steam Genedon

Turndown while the convective pass typically contains


low-temperature superheater and low tempera-
Turndown is accomplished by reducing fuel
ture reheater, along with the economizer and
and air flows to the unit. However, it is a char-
airheater. One FBHE then contains the finish-
acteristic of a CFB that the combustor heat-
ing superheater and the other contains the fin-
transfer rate is not reduced proportionally to a
ishing reheater. This arrangement allows
drop in airflow. Consequently, without an
control of reheat steam temperature by means of
FBHE, combustor temperature drops as load is
solids flow to the FBHE containing the reheat
dropped. The FBHE can be used to maintain
surface. Either or both FBHE's may contain
combustor temperature at the optimum level
evaporator surface as well.
over a wide load range, by reducing solids flow
The split reheater (part in convective pass,
to the FBHE as load is decreased. This feature
part in FBHE) is designed to put heat into the
is especially important when firing certain
reheat circuit at low loads (when hot solids may
low-grade fuels. In such situations, maximum
not be available to the FBHE) for turbine steam-
combustor temperature must be limited because
temperature matching; without requiring a tur-
of the potential for ash softening, thereby leav-
bine bypass.
ing only a narrow temperature range for
The heat-duty distribution described above
acceptable combustion.
minimizes the heating surface and cost in a
subcritical drum-typecycle without a turbine
Reheat
bypass (the most common cycle in the U.S.).
Reheater surface can be located in the FBHE, Other heat-duty distributions may be best for
and the flow rate of solids to the FBHE can be other cycles and to meet certain special per-
used to control reheater outlet steam tempera- formance requirements. One example would be
ture. The FBHE can also heat air or other pro- a once-through steam cycle with a turbine by-
cess streams, depending on the application. pass, where all reheat surface could be located
in one FBHE.
HEAT-DUTY DISTRIBUTION
Process Parameters
The distribution of evaporator, superheater,
and reheater duty within the primary loop Table IV shows a list of typical CFB process
(combustor and FBHE) and convective pass is design parameters.
set to minimize cost while providing the re- Proper fuel feed size is extremely important .,
quired performance over the load range. The to both operation and performance. If the feed
major considerations in selecting the heat-duty is too coarse, there will be insufficient material
distribution are described in reference 17. in circulation, and reduced burnout, sorbent
In a unit without an FBHE, the combustor utilization and combustor heat transfer will
walls do evaporative duty, and the convective result. In the extreme, the solids circulation rate
pass contains the superheater, economizer, and will be low enough to cause large temperature
air heater. In a unit with an FBHE, the combus- gradients in the combustor. This condition can
tor does evaporative duty and the convective lead to clinkering and defluidization. Further,
pass typically contains the low temperature su- the coarse material which resides in the lower
perheater and economizer plus the air heater. combustor adds unwanted pressure drop. If the
The FBHE then contains the finishing super- feed is too fine, excessive material will be en-
heater and may contain additional evaporator trained from the combustor, thereby producing
surface. When fluid-cooled, the walls of the insufficient material in circulation and a resul-
FBHE do evaporative duty. tant negative impact on performance.
With a reheat cycle, there are usually two In general, high-ash fuels must be crushed
FBHE's. The combustor does evaporative duty, finer than low ash-fuels. This is for two rea-
COMBVSIlON
Fluidized-Bed Steam Generators

sulfur capture characteristics of a given lime-


stone. Occasionally a very fine material, having
TABLE IV. Typical CFB high surface area but low retention time in the -
Process Parameters - .
bed, gives the best performance.
The management of the particle size of both
Fuel fuel and sorbent to achieve adequate solids cir-
Top size culation rates is critical to CFB performance,
and must take into account the feed particle
d50
size, ash content, decrepitation rates, and cy-
Sorbent clone efficiency.The bed particle size shown is
Top size that which can be circulated through the sys-
tem at the design velocity. Larger particles must
d50
be drained from the combustor, while finer par-
Combustor . ticles are carried through the cyclone. Fuel and
Temperature 1560-1650F sorbent feed size must be set to provide an ade-
Velocity 18-20 ftlsec quate inventory of particles in this size range for
Particle Size 100-1000 pm
acceptable combustor performance.18
Pressure Drop 40-80"WG Within the combustor, gaslsolids tempera-
Recycle Rate 10 to 10011
tures are typically maintained in the range of
1550 to 1650F (840 to 900C). High-sulfur
Performance fuels are usually fired at 1550F (840"C), which
Carbon Loss 1-2 percent or less is the optimum temperature for SO, capture
CaIS 1.5-2.5 (for 90 percent with limestone. High-ash fuels such as anthra-
SO, capture) cite culm are generally fired at 1650F (900C)
100 ppm or less
for improved carbon burnout; these fuels are
SO2 often low in sulfur.
100 ppm or less ..
100 ppm or less
Design combustor velocity is established at
18 to 20 ftlsec (5.5 to 6m/s). This velocity level
provides reasonable combustor heat-transfer
surface for a given height, low erosion rates,
and an acceptable turndown range with ade-
sons. First, high-ash fuels tend to decrepitate quate bed stability.
less and so smaller feed size is required to pro- - Bed pressure drop is generally in the range of
duce the optimum bed particle size. Second, if 40 to 80" WG (10 to 20 kPa). The indicated level
high-ash fuels are not adequately crushed, car- of inventory provides for high internal and ex-
bon will be encapsulated by ash and the carbon ternal solids recycle rates, and leads, in turn, to
loss will be unnecessarily high. Very high ash good carbon burnout, effective sorbent utiliza-
fuels such as anthracite culm (which may con- tion, and bed stability.
tain up to 70-percent ash), are typically Performance in terms of carbon burnout and
crushed to 11s-inch (3mm) topsize, while lower- emissions is excellent. For high-ash, low-reac-
ash fuels such as bituminous coals are typically tivity fuels such as anthracite culm, carbon loss
crushed to 'k-inch (6mm) topsize. More reac- can be as low as 1to 2 percent, while for high-
tive fuels such as lignites are typically crushed reactivity fuels such as lignite, carbon loss is
to 318-inch (10rnm) topsize. typically below 0.5 percent. SO, emissions can
Proper sorbent size is also important for good be reduced below 100 ppm, with 90-percent
performance. Limestone is generally crushed to SO, capture at CalS of 1.5 to 2.5 (depending on
1millimeter topsize, although the optimum siz- fuel sulfur levels, limestone reactivity, etc.);
ing depends on the actual decrepitation and sulfur capture above 95 percent has been re-
COlMmRON
fiidizd-Bed Steam Genentom

quired and achieved in several commercial subsystems within the circulating-bed boiler
plants. CO levels are generally in the range of and discuss typical equipment and major per-
100 to 200 ppm. NO, levels below 100 ppm are formance criteria.
typical.
FUEL PREPARATION
PART-LOAD OPERATION
Fuel preparation usually consists of one or
Turndown is accomplished by reducing both two stages of crushing, with the system design
fuel and air to the unit. In the process, grate and and layout dependent on such fuel characteris- '

combustor velocity should be kept above a min- tics as moisture and ash content, and required
imum level in order to produce adequate mix- fuel sizing.
ing and solids recirculation for reasonable fuel Fuels such as anthracite culm generally re-
combustion and to avoid severe temperature quire two crushing stages. Because the final
maldistribution and backsifting of bed material product must be sized to a topsize of 11s inch (3
into the air plenum. This usually implies ex- mm), or smaller, the material leaving the sec-
cess-air levels holding constant as load is de- ondary crushers is typically fed directly to the
creased until the minimum velocity is reached, combustor to avoid hopper pluggage from the
after which excess air percentage increases to fines. Fuels such as bituminous coal permit the
maintain velocity. Combustor temperature material leaving the secondary crushers to be
drops, the solid fuel permissive temperature is stored in day bins for feed to the combustor.
reached, and the start-up burners must be used. Many types of crushers, including impact
With an FBHE, combustor temperature can mills, hammer mills, and cage mills, have been
be maintained at high levels through a wide applied. Cage mills can limit oversize as the
load range. As load is reduced, solids flow mills wear and so are used with culm firing
to the FBHE is lowered, which adjusts the where oversize fuel is of concern. Feed size is
primary-loop heat absorption to the required varied by changing mill speed. Hammer mills
level without affecting combustor temperature have changeable grate bars for adjusting fuel
so that combustor performance is maximized at sizing. Alternately, air-swept crushers have
part load. At reduced load the solids to the been very successfully applied in Europe and
FBHE are stopped; below this point combustor have been considered for several projects in the
temperature will drop with decreasing load. U. S. They allow for direct pneumatic feed to
START-UP the combustor. While air-swept crushers also
strictly limit oversize and allow adjustment of
Start-up is accomplished by means of start- fuel sizing, they are usually more expensive
up burners located in the lower combustor than the other types.
walls and/or in the primary air duct. Minimum
primary-air flow is established and the start-up SORBENT PREPARATION
burners are used to heat the bed material Sorbent can be purchased to the correct size
slowly, at a rate dictated by refractory heat-up specification, or can be crushed on site. Sizing
limits (100 to 200 F/hr or 55 to 11O0CIh).When equipment usually consists of an air-swept
solid-fuel permissive temperature is reached roller mill with fan, a cyclone collector, and a
(typically 1000 to 1300F, 540 to 700C, for crushed-product storage bin.
coal), solid fuel is added. Temperature is fur-
ther increased by adding solid fuel and backing FUEL FEED
out start-up fuel. At about 30-percent load, the The solid-fuel feed system usually consists of
boiler can run on solid fuel alone. a pressurized belt feeder (typically gravimetric)
CFB SYSTEM AND COMPONENTS
followed by a rotary airlock valve and a fuel
chute or pipe leading to the side of the lower
The following sections' describe the major combustor. Fuel from the feeder falls by gravity

A!! 0
COMBUSTION
Fluidized-BedSteam Generators !

through the airlock valve, into the combustor. can thus be obtained on liquid or gaseous fuels
The feeder is pressurized with cold primary air, with adequate lance capacity. Because these
and the head of fuel in the standpipe of the fuels have much shorter bed residence time
feeder inlet forms the pressure seal between bin than solid fuel, they require more feed points
and feeder. At least one completely redundant for proper fuel distribution and performance.
feed system is recommended. The lances can be either retractable or sta-
Alternately, the fuel can be dropped into an tionary. In either case, lance fuel feed can be
air stream and injected pneumatically into the initiated very quickly on a switch from solid fuel
combustor. This approach will help fuel disper- to liquidlgas, or to regain load on a temporary
sion in the combustor and offers the possibility loss of a portion of the solid-fuel feed system.
of using secondary-air ports for fuel feed, Liquid and gaseous fuels for start-up are fired
thereby reducing the total number of openings in start-up burners, located in the primarylsec-
required in the walls of the combustor. ondary air ductwork andlor in the lower com-
High-moisture fuels, shch as wood or lignite, bustor. The burners located in the combustor
are generally fed to the combustor through the are retractable.
discharge side of the seal pot to mix the fuel
SORBENT FEED
with hot solids, thereby partially pre-drying
the fuel. This feed location also has the advan- The sorbent feed system usually consists of a
tage of eliminating a separate opening in the day bin for storing sized limestone, followed by
combustor for fuel feed, and so the seal-pot a rotary airlock feeder which drops the sorbent
feed may be used for any fuel when deemed into a pneumatic conveying line for transport to
convenient and economical. the lower combustor. Gravimetric feeders can be
Various pneumatic feed systems can also be used for a more accurate measurement of lime-
used, including air-swept crushers. Fuel from stone flow. To provide the desired number of
the feeder drops into a pressurized mill, where feed points to the combustor, multiple bin out-
the fuel is dried, sized, picked up in an air lets and feed systems can be used or the convey-
stream, and pneumatically conveyed to the ing line from a given feed system can be split.
lower combustor. Dense-phase conveying sys- The sorbent can also be mixed with the fuel just
tems are also available. Typically, because of before entering the combustor. This is typically
the high internal mixing rates, only a few feed done with fine limestone feed, where the lime-
points are required for adequate mixing and stone is likely to have short residence time in
dispersion of the solid fuel within the combus- the combustor and so would not be effective if
tor. For smaller units (100,000to 70U,000 l b h r fed far from the fuel.
steam, 13 to 90 kgls), one or two feed points are '
usually provided, while for larger units three or AIR SUPPLY
more feed points can be required. Of course, Primary and secondary air are supplied to the
fuel heating value can influence the number of combustor by separate centrifugal fans, gener-
feed points. Low-grade fuels with high volu- ally arranged in parallel. Either or both of these
metric flows, such as certain biomass, require streams may be preheated in an air heater, de-
more feed points because volumetric flow pending on the design feedwater and stack tem-
through certain system components is limited. peratures, the economics of air-heater heat
Liquid and gaseous fuels for load carrying are recovery versus heat recovery by water or steam
fired in lances, fuel-feed pipes which carry heating surface, and whether an air-swept mill
only fuel plus an atomizing medium but no is used. An alternate to the above fan arrange-
combustion air and which are located in the ment is two fans in series with the second fan
lower combustor. The lance is intended to dis- supplying the higher-pressure primary air.
perse the fuel within the bed, where it is com- With an air-swept crusher, secondary air is
busted-- in the fluidizing air stream. Full load generally used for mill air. To overcome the
C O ~ O N
RuidW-Bsd Steam Generators

pressure losses through the mill and conveying walled, formed from finned or fusion-welded
lines, the air pressure may need to be slightly waterwall tubing, and unlined to maximize
higher than without such a mill. heat absorption.
Fluidizing air for the seal pot, FBHE, and The air distributor (grate) containing the air
FBAC is supplied by 'either positive-displace- nozzles can be uncooled or water-cooled, as
ment or centrifugal blowers. Depending on the can the air plenum below the grate. Water-
flow rates, it may be economical to preheat cooling the grate and plenum provides a seal-
these air streams in an air heater. welded, gas;tight combustor, and minimizes
Fluidizing-air nozzles (bubble caps) are pro- the size (and thus the maintenance concerns) of
vided in the bottom of the combustor, seal pot, expansion joints connecting the primary-air
FBHE, and FBAC for proper distribution of flu- ducts to the combustor.
idizing air. These nozzles are designed to avoid If necessary on large units, two tapered lower
backsifting of solids into the air supply system. combustors can be used with a single upper
combustor, forming a so-called "pantleg" con-
COMBUSTOR figuration. This configuration improves fuel
and air distribution within large combustors.
The combustor corresponds to the furnace in The combustor can be top-supported or bot-
a pulverized-fuel or stoker-fired boiler. The tom-supported. Top supporting is the more tra-
combustor consists of two zones: lower com- ditional approach but requires that significant
bustor and the upper combustor. differential expansion be taken in the solids-
The lower combustor is that portion contain- recycle lines connecting the combustor to the
ing the fuel, primary-air distributor, secondary- cyclones and FBHE, both of which are
air ports, fuel feed ports, and solids-recycle bottom-supported. Bottom,-supportingpresum-
ports. The density of the bed in this region is ably requires less steel, but often a significant
relatively high on average, being highest at the load still must be carried at the top of the struc-
elevation of the air distributor and dropping off ture by the use of constant-load springs, be-
rather rapidly with increasing combustor cause the number and size of lower combustor
height (see Fig. 12). Due to the staged air feed, openings will not permit the carrying of the en-
this region is substoichiometric. Physically, tire unit load from below.
this section is usually rectangular, tapered,
Circulation System
formed from finned or fusion-welded water-
wall tubing, and lined with refractory to pro- The walls of the combustor are cooled by
tect the tubing from erosion by the dense bed thermo-syphonic (natural) circulation. At high
and corrosion in the substoichiometric atmo- steamlwater pressures, the walls of the combus-
sphere. The optimum refractory lining is hard (to tor may incorporate assisted circulation. When
minimize erosion), thin (to minimize weight), provided, an FBHE evaporator bundle can be
and reasonably conductive (to maximize com- cooled using pumped (assisted) circulation.
bustor heat absorption). Use of natural circulation generally requires in-
The upper combustor, the section above the clined tubing and, therefore, less bundle sur-
refractory-lined lower combustor, contains the face per unit of bed plan area. Yet when the
gas outlet or outlets to the cyclones. The den- total bed plan area required is not excessive,
sity of the bed in this region is relatively low, natural circulation is more economical overall.
and drops off very slowly with increasing com- C-E has established the flow requirements for
bustor height. - both horizontal and inclined evaporator tubing
Because all air has been fed in the lower corn- in laboratory tests.
bustor, the upper combustor operates under
-. CYCLONE COLLECTOR
excess-air (oxidizing) conditions. Physically,
this section is usually rectangular, straight- One or more high-temperature cyclones are
COMBUSTION
Fluldbed-Bed Steam Generators

used to collect the solids entrained in the gas ing immersed tube bundles (see Fig. 13). Hot
leaving the combustor. The cyclone is designed solids from the seal pot enter the FBHE, where
to collect essentially all particles with a diame- they are fluidized and transfer heat to the heat-
- ter greater than about 100 micrometers. Given ing surface within, and then flow back to the
the relatively large particle sizing entering the combustor. The tube bundles immersed in the
cyclone, the separation efficiency typically is FBHE compartments can be evaporator, super-
over 99 percent. When needed, a vortex finder heater, or reheater surface. Here again, proper
(also called a re-entrant throat) can be added to design of the tube-bundle supports is essential.
the cyclone gas outlet to improve the collec- Fluidizing velocity is low (Ito 2 ftlsec, approx-
tion efficiency. imately 0.3 to 0 . 6 mls), the fluidizing medium is
Cyclone Construction
air, the particle size is small, and the carbon con-
tent of the material is negligible. All these condi-
The cyclone is typically constructed of steel tions lead to essentially no erosion or corrosion
plate with a multiple-layer refractory lining. of the in-bed tube bundles. Also, because of the
The hot face of the lining is a dense erosion- high bed density, heat-transfer rates are very
resistant material, backed up by lighter-weight high. Containment can be either refractory-lined
insulating materials. Proper selection, installa- steel plate or water-cooled construction.
tion, and subsequent operational care of the re-
fractory materials are essential to ensure CONVECTIVE PASS
long-term lining performance. Alternate con-
struction using water cooling, steam cooling, or The convective pass is of the same basic design
air cooling is feasible. as used in a pulverized-fuel or stoker-fired boiler.
The enclosure walls are usually formed from
SEAL POT
finned or fusion-welded tubing, steam or water-
The seal pot is a non-mechanical valve which cooled. Where gas temperatures are sufficiently
moves the solids collected by the cyclone back low, duct plate can be used to form the enclosure.
into the combustor against the combustor back- The convection pass can contain superheater,
pressure. Solids flow down on the inlet side, up reheater, boiler bank, and economizer surface.
the outlet side, then back to the combustor. The Gas velocities are kept low to avoid erosion from
bottom portion of the seal is fluidized so that the relatively high dust loading. Retractable or
material in the seal can seek different levels on rotary sootblowers can be used to keep heat-
each side of the seal, with the difference in transfer surfaces clean.
level corresponding to the pressure difference
across the seal. Then, solids entering the seal RECYCLE SYSTEM
inlet displace solids out of the seal on the outlet
side. Sometimes an MDC is used to collect fine ma-
The seal pot is constructed of steel plate or terial leaving the cyclone for recycle to the com-
pipe with a multiple-layer refractory lining. bustor. Such recycle can improve carbon burnout
Fluidizing nozzles along the bottom of the seal and sorbent utilization. Collection efficiency is
provide the fluidizing air. usually on the order of 50 percent, given the rela-
On units with a FBHE, a plug valve is located tively small incoming particle size and the need
in the lower portion of the seal pot, to regulate to limit collector pressure drop. Devices used in-
the flow of solids from the seal pot to the FBHE. clude a multi-tube cyclone and a knock-out box
(a hopper with chevrons). The collector can be
FBHE located at any convenient point in the gas pass,
As described earlier, the FBHE is a bubbling- such as between the economizer and air heater,
bed heat exchanger, consisting of one or more or downstream of the air heater.
compartments separated by weirs and contain- Provisions should be made for controlled, con-
--
COMBnsnON
Fluidized-Bed Steam Generators

tinuous (or near-continuous) feed of recycle to heating, hot-water preheating, or air bypass is
the combustor, as well as for transporting col- usually required to maintain the air-heater
lected solids not being recycled to disposal. Ash ACET above typical limits under conditions of
transport equipment will generally be of the low ambient temperature andlor low-load oper-
pressure pneumatic type. Lock hopper systems ation. As mentioned earlier, while there is
and solids pumps have been successfully used. potential for the ACET to be reduced for fluid-
ized-bed boilers due to low SO,ISO, in the flue
AIR HEATER
gas (from sorbent addition and lime in the fly-
A prime consideration in selecting an air ash), more-operating experience on a wider
heater type for CFB applications is the high air- range of fuels is needed to substantiate this
to-gas pressure differential resulting from the approach.
high primary-air pressures required. This has
ASH REMOVAUCOOLING
resulted in use of low-leakage designs, such as
welded tubular air heaters and heat-pipe air The ash-removal system includes both the
heaters (see Chapter 14). bottom-ash and flyash systems.
Size of the air heater is then based strictly on
Bottom-Ash Removal System
economics, since preheated air is not needed by
the process. The exception is where an air-swept The main function of the bottom-ash system
mill is used and sufficient air preheat is needed is to control bed inventory. Bed pressure drop is
for fuel drying. the measure of inventory, and bottom-ash flow
Generally, two separate air heaters are pro- is adjusted to maintain the desired bed pressure
vided, one for primary air and one for secondary drop. The bottom-ash system can also help con-
air. These can be arranged in series or in parallel trol accumulation of oversize material. In a
with the gas stream. With large amounts of fluid- CFB, such accumulation can produce an unfa-
izing air for FBHE's, it is sometimes economical vorable pressure profile with most of the mate-
to provide a separate air heater for fluidizing air. rial in the lower combustor and little in the
This is because the primary and secondary air upper combustor, resulting in poor perform-
heaters become large to achieve a given stack ance. However, the best and most direct way to
temperature if a significant amount of the total control oversize accumulation is with proper
air bypasses these heaters. design of the fuel-sizing equipment to avoid
With tubular air heaters, the most common de- oversize. One or two ash drains per combustor
sign for CFB applications is a gas-over-tube lair- are usually sufficient.'A grizzly mounted over
through-tubes design. The dust-laden gas the ash drains can keep large material from
passes over the tubes and, because the tubes are plugging downstream equipment.
arranged in-line, they can be easily cleaned with Ash classifiers may also be used, to remove
sootblowers. Gas-throughlair-over designs, oversize and adjust pressure profile, without re-
though somewhat more difficult to clean, have quiring excessive bottom-ash flow rates. Such
also been used successfully. classifiers can operate continuously, in batch
Heat-pipe air heaters, described in detail in mode, and can also cool the ash.
Chapter 14, have been used on many CFB proj- The bottom-ash must be cooled from com-
ects, due to attractive economics, essentially bustor temperature to between 250 and 450F
zero-leakage, and other favorable characteris- (120 to 230C), before entering the bottom-ash
tics. For CFB applications, a maximum of 3 fins conveying system. On high-ash fuels, the heat
per inch on the gas side, retractable soot- in the batt0.m-ash stream may represent a sig-
blowers, and provision to add future surface nificant percentage of boiler heat input. Conse-
have been incorporated into the design to ac- quently, it can be desirable to recover this heat.
commodate the relatively high dust loading. - Fluidized-bed ash coolers (FBAC's) are gener-
Cold-end protection by means of steam pre- ally used for this purpose. The FBAC is a BFB
COMBDSTION
Fluidized-Bed Steam Generators

heat exchanger identical in design to the FBHE. trial-scale applications are described here, to
Cooling coils immersed in the bed cool the ash illustrate major component design and ar-
and transfer heat to condensate or boiler feed- rangement. The first is a 220,000 l b h r 95s0F,
water. Ash flow from the combustor to the FBAC 1255 psig (28 kgls, 513OC, 8.7 MPa gage) wood-- -I
is controlled by a cone valve, as with the FBHE. fired steam generator (see Fig. 15). The unit has
The FBAC design must accommodate the accu- a single combustor with cyclone and seal pot,
mulation of coarse material which can lead to but no FBHE. The convective pass includes a
sintering andlor defluidization. C-E has devel- superheater, boiler bank, economizer, and heat-
oped successful FBAC designs, which have pipe air heater.19
been proven on high-ash-fuel applications. On I 1
low-ash fuels, there is no incentive to recover
heat in the bottom-ash, so water-cooled screws
are typically used. '

Cooled ash from the ash cooler passes to the


bottom-ash'handling system for transport to
storage. This is usually a mechanical system
consisting of flight conveyors, although a pres-
sure pneumatic system can also be used. Alter-
nately, a mechanical system can be used to
transport bottom-ash to an intermediate hop-
per, from which a pneumatic system conveys
the material to storage.
Flyash Removal System

As with BFB boilers, fabric filters (bag-


houses) and electrostatic precipitators (ESP's)
are used for final particulate cleanup. ,
Flyash from the economizer and air-heater
hoppers, the MDC, and the fabric filter or ESP Fig. 15 Small C-E CFB steam generator for
is typically handled with a vacuum pneumatic industriallpower-productionapplication
system, although flight conveyors are also used.
No ash cooling is necessary. The bottom-ash The second is an 825,000 lb/hr,lOOOF, 1800
and flyash streams can be stored for disposal to- psig (104 kgls, 540C, 12.4 MPa gage) boiler,
gether in the same silo or in separate silos. Ash designed to fire anthracite culm (see Fig. 16).
conditioners then mix in sufficient w8ter for The unit has a single combustor, two cyclones
proper handling and transport to the ultimate with seal pots, and an FBHE containing an
disposal area. evaporative bundle. The convective pass in-
An alternate to the dust collector and recycle cludes a superheater, economizer, and heat-
system described earlier is to recycle material to pipe air heater.
the combustor from the baghouse-or ESP. Such
UTILITY APPLICATION
a system has the advantage of avoiding an addi-
tional dust collector in the system, although One example of a C-E CFB design for utility
care must be exercised not to overload the con- applications is a 150-MW unit for the ~ e x a s r
vective pass and baghouse or to exceed emis- New Mexico Power Company producing
sion levels. 1,000,000l b h r (126 kgls) main steam at 1005OF
(541C), 1800 psig (12.4 MPa gage), with re-
INDUSTRIAL APPLICATION
heat, designed to fire lignite. Fig. 17 is an iso-
Two examples of C-E CFB designs for indus- metric view of the boiler.
--
CoLQmSnON
Fluidized-BedStwm Generators

Fig. 16 Large C-E non-reheat CFB steam generator Fig. 17 C-E 150-MW CFB steam generator
for industriallpower-productionapplication with reheater

The unit has a single combustor with dual In addition to the reduced emissions of sulfur
grates (pantleg configuration), four cyclones and nitrogen oxides that are possible with fluid-
with seal pots, and two FBHE's. The FBHE's bed combustion, PFBC offers the potential for a
contain evaporator, finishing superheater, and significant gain in overall thermal efficiency be-
finishing reheater surface. The convective pass cause of the incorporation of a gas turbine in
contains low-temperature SH and RH surface, the cycle. Another advantage of the PFBC system
an economizer and a heat-pipe air heater. Fuel is that all oi the equipment operating at the
is fed from a feeder through an airlock to the plus-10-atmosphere pressure level is smaller in
seal pot discharge. Reference 15 contains addi- size than it would be at normal atmospheric
tional design information. pressure, making shop-assembly and barge de-
livery of components an attractive option.
?Lvo of the many approaches to the pressur-
PRESSURIZED FLUIDIZED-BED ized cycle are the PFBC turbocharged cycle and
the PFBC combined cycle; even these two have
COMBUSTION SYSTEMS many possible variations, which are being inves-
This chapter has introduced all the concepts tigated throughout the world, in both design
involved in the design of fluidized-bed steam studies and operational units.
generators, and has described the implementa- In the turbocharged cycle, hot flue gas from
tion of that design for boilers operating at or a PFBC boiler (at approximately 800F or
near atmospheric pressure. Combustion in that 425OC) is expanded through a gas turbine that
regime is referred to as atmospheric fluidized- produces enough power to drive the turbocharg-
bed combustion (AFBC). Fluidized-bed opera- ing compressor. One version of the higher effi-
tion at pressures 10 to 20 times atmospheric ciency power-producing PFBC concept has the
pressure, taking place in large cylindrical or gas leaving the pressurized fluidized-bed com-
spherical pressure vessels, in combination with bustor at about 1600F (about 870C). The gas
axial compressors and gas turbines, is termed is cleaned in tandem high-temperature cyclones;
pressurized fluidized-bed combustion (PFBC). and is then sent to the gas turbine. The turbine
COMBUSFION
Fluldlzed-Bed Steam Generators

exhaust is further reduced in temperature by trated schematically in Fig. 15 of that chapter.


passing through heat-recovery equipment, such Reference 19 of Chapter 1 and reference 20 of
as evaporative and feedwater-heating surface. this chapter describe work done by Combustion
The supercharged furnace-fired combined Engineering and others in the development of
cycle was introduced in Chapter 1, and is illus- this promising technology.

REFERENCES 1G. D. Jukkola et al., 'Application of Coal Drying Systems


1 S. L. Goodstine et al., "Industrial Application of Fluid- Using Recycle Material at the TVA Demonstration Plant:'
ized Bed Combustion, Phase I, Task 4-Sub-scale Unit Proceedings of the 1986 EPRI Seminar on AFBC Technol-
Testing and Data Analysis. Vinal Report, Volume 1:' pre- ogy-Utility Applications," Palo Alto, CA. April 1986.
pared for the U.S. Department of Energy under Contract "A. M. Manaker, PH.D. and G. D. Jukkola, "Atmospheric
EX-76-C-01-2473, December 1979; published by the U.S. Fluidized Bed Combustion Development at TVA," Pro-
Department of Energy (NTIS) DOE/ET/10389-T3. ceedings of the 1988 Joint AMElIEEE Power Generation
2Combustion ' ~ n ~ i n e e r i nInc..
~ , "Great Lakes Fluidized Conference, Philadelphia, PA, September 25-29, 1988.
Bed Combustion. Final Report, Volume 1," prepared for 12A.Stathoplos et al., "System Developments for Fluid Bed
the U.S. Energy Research and Development Administra- Boilers," presented at the International Symposium on
tion under Contract EX-76-C-01-247, December 1985. Coal Combustion, Beijing. China. September 1987.
Windsor, CT: Combustion Engineering, 1985.
IJR. V. Jacobs, "Design of the TVA 160 MW Atmospheric
JCombustion Engineering, Inc., "Preliminary Design Fluidized Bed Steam Generator," Proceedings of the 1986
Study for a Fluidized Bed Demonstration Unitw-Final Joint ASMEIIEEE Power Generation Conference, Portland.
Report to the Tennessee Valley Authority under TVA con- OR, October 19-23, 1986; also as Combustion Engineer-
tract 45723A. funded by the U.S. Department of Energy ing publication TIS-8219.
under DOE Interagency Agreement EF-77-A-01-6013.
June 1, 1978. Windsor, CT: Combustion Engineering, I4J.W. Regan et al. "Design of the 160 MW AFBC Demon-
1978. stration Unit at TVA's Shawnee Stea Plant," Proceedings of
the Eighth International Conference on Fluidized Bed
4Combustion Engineering Inc.. "TVA Utility AFBC Proj- Combustion, Houston, TX, March 18-21, 1985; also as
ect, Phase 11, Final Report; Volume 1-200 MW Demon- Combustion Engineering publication TIS-8023.
stration Plant Final Design; Volume 2-800 MLV
Commercial Plant, Proposed Design and AFBC Research 15 J. W. Regan and H. Beisswenger, "Utility Applications of
and Development Requirements"; prepared under TVA AFBC." Windsor, CT, Combustion Engineering publica-
Contract 51863~4,January 18,1981. Windsor, CT: Combus- tion TIS-8244.
tion Engineering, 1981. 16S. A. Pierzchala and B. W. Wilhelm, "Design Require-
SCombustion Engineering, Inc., "Preliminary Design ments for Circulating Fluid Bed Units with Reheat," Pro-
Study for a Circulating Fluidized Bed Commercial and ceedings of the 1990 Joint ASMEIIEEE Power Generation
emo on strati on Unit, Final Report, Revision 1," prepared Conference, Boston, MA. October 21-25, 1990. ASME
under TVA Contract 53907A. December 31, 1980. Wind- Paper No. 90-JPGCIPwr-70.
sor, CT: Combustion Engineering. 1980. I7 E. J. Gottung et al., "Design Considerations for Circulating
6D. Kunii and 0. Levenspiel, Fluidization Engineering, Fluidized Bed Steam Generators," Proceedings of the Tenth
ISBN 088275-542-0. ,Malabar. FL: Robert E. Krieger Pub- International Conference on Fluidized Bed Combustion, San
lishing Co., Inc.. 1969. Francisco. CA, May 1-4, 1989.
B. Leckner and L.-E. Amand. "Emissions from a Circulat- 'OH. Herbertz et al.. "Effects of Fuel Quality on Solids Man-
ing and a Stationary Fluidized Bed Boiler: A compari- agement in CFB Boilers," Proceedings of the Tenth Inter-
son," Proceedings of the Ninth International Conference national Conference on Fluidized Bed Combustion," San
on Fluidized Bed Combustion. Boston, MA, May 4-7. Francisco, CA, May 1-4, 1989.
1987.
'9 R. V. Jacobs and E. Gershengoren. "Design and Operation
'G. C. Dunn, G. D. Jukkola, and R. C. Kunkel. "Fuel Prepa- of a Wood Fired CFB Steam Generator." Proceedings of the
ration Systems for T V ' s 160 M W Demonstration Plant," Tenth International Conference on Fluidized Bed Combus-
Proceedings of the 1988 Joint ASMEIIEEE Power Genera- tion, San Francisco, CA, May 1-4, 1989.
tion Conference. Philadelphia, PA. September 25-29,
1988. R. Wysk et al., "Technical and Economic Aspects of a
Pressurized Circulating Fluidized Bed Combustion Sys-
9R. McKinsey et al.. "Coal Drying Using Recycle Fly Ash:' tem," presented at Second Biennial PFBC Conf.. Milwau-
Proceedings ofthe 1986 EPRI Seminar on AFBC Technol- kee, WI, and 79th Annual Meeting of the Air Pollution
ogy-Utility Applications." Palo Alto, CA, April 1986. Control Association, Minneapolis, MN, June 1986.
--
COLQIUSPION
Fluidhd-Bad Steam Genenrtors

BIBLIOGRAPHY
Barner. H. E., Beisswenger, H., and Barner, K. E., Conference, Philadelphia, PA, September 25-29, 1988,
"Chemical Equilibrium Relationships Applicable in Fluid ASME Paper Na 88-JPGCIPwr-9.
Bed Combustion," Proceedings of the Ninth International
Conference on Fluidized Bed Combustion, Boston, MA, Patel, R. L. et al., "Reactivity Characterization of Solid
May 4-7. 1987. Fuels in as Atmospheric Bench- Scale Fluidized - Bed
Combustor" presented at the 1988 joint ASMEIIEEE
Bashar, M. and Czarnecki, T. S., "Design and Opera- Power Generation Conference, Philadelphia, PA, Septem-
tion of a Lignite-Fired CFB Boiler Plant:' Proceedings of ber 25-29, 1988; also as Combustion Engineering publi-
the Tenth International Conference on Fluidized Bed cation TIS-8391.
Combustion, San Francisco, CA May 1-4, 1989. Sainz, F. A. et al., "Chatham Circulating Fludized Bed
Beisswenger, H., Krittel R., and Ploss, L., "The 95.8 Demonstration Project," Proceedings of the First Interna-
MWe CFB Utility Boiler of the Duisburg Municipal Power tional Conference on Circulating Fluidized Beds, Halifax,
Company:' Lurgi Publication. Nova Scotia, Canada, November 18-20, 1985. Toronto,
Pergamon Press, 1986.
Gendreau, R. J. and Raymond. D. L., 'Atmospheric Flu- m i n , m!, yqow ~~~~~i~~ of p,tmoSpheric ~ l ~ ~~d
i d
idized Bed Combustion Update-Status and Applica- Combustion Systems and their effect on SO, capture and
tions," presented at the 1987 Joint ASMEIIEEE Power NO^ suppression:' by ~~~~i from VGB M ~ ~ ~ -
Generation Conference, Miami Beach, FL, October 4-8, zinc, ~~b~~~~~ 1985, pp. 319-123.
1987, ASME Paper Na 87-JPGC-FACT-11.
Wilhelm, B. W. et al., "100 MW Anthracite Culm CFB
Gottung. E. J. and Sopko, S. J., "Design and Operation Small Power Producer," Proceedings of the American
of a CFB Steam Generator Firing Anthracite Waste:' pre- Power Conference, Vol. 50. Chicago, IL: Illinois Institute
sented at the 1988 Joint ASMEIIEEE Power Generation of Technology, 1988.
CHAPTER 10

Marine Boilers

u he many limitations and unique require-


ments applicable to shipboard power
plants make the marine boiler a very special-
the boiler efficiency can be set at a given value
for any one evaporating rate, but heat-balance
calculations at other evaporating rates must be
ized form of steam generator. Customarily, based upon the corresponding boiler efficien-
marine boilers must meet the following overall cies as set by the performance characteristic of
conditions: high level of dependability, lim- a particular boiler design.
ited space, wide range of steam output ca- Normal power is a specified characteristic of
pacities, ability to change load rapidly, good a given merchant ship and generally corre-
accessibility, aiid limited weight. In addition, sponds to 100 percent rating of the boiler. For
because most ships are designed for specific naval vessels, 100 percent boiler rating corre-
trades, propulsion machinery for a certain ship sponds to fill power.
must be selected to meet the operating condi-
tions encountered in the trade that the vessel LOAD PATTERN AND BOILER DESIGN
is intended to serve. Not only do the conditions set by the quan-
tities which are readily defined by numerical
SERVICE REQUIREMENTS values directly influence boiler design, ,but
operating conditions which will be encoun-
Marine-boiler design properly starts with a tered in service also affect it. Although two
review and study of the service requirements ships might have the same shaft horsepower
for the particular ship under consideration. (shp) and the same evaporating rates for the
Only after an economic evaluation of potential boilers, one ship might be in a trade which calls
propulsion-plant and cogenerative.cycles does for prolonged periods of steady steaming, and
the ship designer set the evaporation rate and in contrast, the other ship might be in a service
the required steam pressure and temperature. which requires the boilers to be changing load
The plant heat balances, calculated at vari- frequently. As examples, the former would be
ous steady steaming conditions, establish cer- typical of a tanker, and the latter, a dredge or a
tain operating conditions which the boiler ferry boat.
must meet. In this connection, it must be rec- Analyses of boiler load variations during a
ognized that boiler performance is a parameter series of voyages make it possible to graph the
in the heat-balance calculations. For example, load pattern for the boilers in a particular trade.
-
Marine Boilers

In designing new ships, it is customary to plot


these graphs with averages compiled over an
extended period from data of ships that have
been in the same trade that the new vessels will
serve. Fig. 1 illustrates the boiler load pattern
typical of a dry-cargo ship during a single
round-trip voyage between the West Coast of
the United States and the Orient.
Obviously. a dry-cargo boiler has a load pat-
tern which differs from that of a tanker or a de-
stroyer. Although the design of a ship and its
machinery must take into consideration possi- Percent of Boiler Capacity
ble changes in service conditions, the prime
objective is to get the optimum design for the Fig. I Boiler load pattern during voyage of
.trade in which the vessel will initially serve. drytargo ship
Fortunately, most marine boilers have the inher- restriction which actually dictates the boiler
ent characteristic of being versatile to a degree. design on many ships. To the boiler designer, it
If later service conditions do bring about would be ideal if adequate space could be pro-
changes in the boiler load pattern, the boiler vided in the fireroom so that no limitations on
usually will be able to meet the new conditions size or shape had to be considered. Table I and
within the limits determined by the other me- Fig. 2 show the principal dimensions of one
chanical components of the propulsion plant standard series of boiler designs. Although the
and the cogenerative cycle. ship owner and marine architect usually try to
Not only is the load pattern an important fac- design the ship so that, as nearly as possible,
tor in deciding some of the principal charac- space will be provided for the optimum boiler
teristics of marine-boiler design, but it will also design, it is almost inevitable that space re-
determine some of the detailed features which strictions will be imposed. From the outset of
must be included. Consideration must also be the preliminary ship design to the time when
given to various other service conditions, such the boilers are installed and accessibility has
as ship sailing schedule and quality of operat- been satisfactorily proved, the boiler designer
ing personnel. Some of the boiler design fea- must constantly consider the space problem.
tures which may be decided entirely, or in part, Frequently, the very purpose of the ship es-
by service conditions are tablishes limiting dimensions for the fireroom
8 number of boilers per ship
type of firing system Table I.principal Dimensions
8 furnace dimensions for Standard V2M8,Marine Boilers
---

8 overall boiler dimensions Boiler Capacity* Dimensions, Ft


Design 1000 lblhr A B C D
8 extent of control systems
8 size of steam drum V2M8-6 132 21 24.9 12.7 15
V2M8-7 154 21 24.6 16.3 15
8 type of steam generator
V2M8-8 176 23.6 27.7 14.5 16.5
relative amount of waterwall generating V2M8-9 198
23.5 27.3 15.9 16.5
surface V2M8-10 221 26.2 25.2 18.4 19
SPACE LIMITATIONS V2M8-11 243 26.5 26.5 19 19
AND BOILER DESIGN ~ 2 ~ 8 - 1 2 265 27.1 28.4 19.8 19
Up to this point there has been no discussion - -V2M8-13 287 26.2 25.2 23 19
'Varies with cycle conditions
of the extremely basic condition of space
COMBUSTION
Marlno Boilers

I circulation
interrelationship of furnace dimensions
with main generating-bank dimensions, and
amount of waterwall surface - -

The burners must be located in positions that


will be readily accessible from the firing aisle.
The prescribed minimum burner clearances
must be carefully maintained to avoid flame
impingement on furnace-wall, floor, or screen
generating tubes.
Selection of furnace dimensions must in-
clude provisions for the proper flow pattern of
the combustion gases within the furnace and
Fig. 2 Principal dimensions applicable to Table I
into the tube bank. It would be ideal if the gis
flow could be controlled to the extent that the
mass flow rate and the gas temperature both
space. For example, the train ferry must have as would be uniform at all points where the gas
many continuous decks as possible. This fea- enters the screen tubes. But achieving this
ture immediately sets a limit upon the height theoretical condition is not generally possible.
allowed for the boiler space. For many ship The boiler designer must, therefore, be guided
types, the Btructural members of the ship hull by the results of past experience obtained dur-
present the most common reason for limiting ing the testing and operating service of designs
the boiler dimensions. similar to the one under consideration.
In selecting the preliminary design for a
marine boiler, detailed calculations on the cir-
SELECTION OF DESIGN culation of the boiler circuits are usually un-
When the service conditions have been necessary, if the design is reasonably similar to
properly evaluated, the boiler designer deter- previous designs of the same general type for
mines the physical design characteristics which complete circulation calculations have
which will best meet requirements. Ideally, the been performed. It is important to note that the
preliminary design should be completed in maximum thermal circulation effect isdob-
time for use by the ship designer in establish- tained when the major portion of the heat ab-
ing the machinery arrangement and the layout sorbedis applied to the lower portion of a tube.
of the main hull structurals passing through Most types of boilers have the arrangement
the fireroom. Space is generally the first item to and dimensions of their generating banks re-
be considered. If the optimum boiler design- lated to some degree to furnace dimensions.
the one which has the arrangement and physi- For example, in early designs of two-drum
cal characteristics most suitable for the service bent-tube boilers, limitations on the draft loss
conditions and performance requirements- through the main bank would frequently set the
has any dimension that is definitely in excess main-bank dimensions, and the furnace height
of the space allowed, then a compromise has to would be fixed accordingly. With some boiler
be made. In designing the boiler furnace, the designs, the furnace dimensions can be set at
major factors to be considered are as follows: the optimum point, and the main-bank dimen-
sions are essentially independent. This is made
firing-equipment accessibility possible by having the distributing header lo-
burner clearance to heating surfaces cated several feet away from the lower drum, as
gas flow and flame travel discussed later in this chapter in the section on
COMBUSRON
Marine Bolkn

bent-tube boilers. In most instances, boilers are changes have been made throughout theyears,
now designed with the maximum practical its design has remained much the same and its
amount of waterwall heating surface. qualities of ruggedness, reliability, ease of
maintenance, and ability to stand abuse made
it-until recently-the most popular boiler in
DEVELOPMENT the marine field.
OF MARINE BO'ILERS The boiler shown in Fig. 3 is coal-fired with a
In tracing the history of the development and spreader stoker and has two furnaces. A close
application of marine boilers, it is interesting look at the illustration reveals two separate
that some of the basic requirements have al- combustion chambers, each stayed to the other.
ways applied, although from time to time the Tubes used as flues for returning products of
emphasis has shifted from one requirement to combustion from the combustion chambers to
another. At the outset, space and weight lim- the smokebox covering the upper front of the
itations were not considered to be as important boiler are also shown.
as other factors, and yet at later stages the em- Even though the Scotch marine boiler proved
phasis on those items brought about the de- to be popular and well-suited for shipboard in-
velopment of new types of boilers. Generally, it stallations, the fact that its pressure was limited
has been the economic or military need for in- to 300 psig retarded progress. There was a
creased propulsion power that has instigated realization that advanced boiler designs with
significant advances in boiler design. greater generating capacity, higher pressure,
The earliest types of marine boilers were rel- and increased efficiency were needed to meet
atively large pressure vessels, with furnaces lo- the changing requirements brought about by
cated underneath them.' But it soon became the development of turbine propulsion ma-
apparent that such exterior furnaces were far chinery. Stiff commercial competition among
from satisfactory, and they were then located merchant fleets as well as various naval powers
inside the boiler shell. The boiler exterior had made these developments most urgent. Marine
now developed into an approximate cube and, engineers began to adapt various types of
no matter how heavily stayed, its flat exterior water-tube boilers to fit into the restricted
placed very low limits on the steam pressure space available for installations on shipboard.
that could be carried and also left much to
be desired from a maintenance and safety
standpoint. The internal furnaces and tubes,
however, were cylindrical and entirely satis-
factory for the pressure demands of their time.
By 1870, marine-boiler pressures had reached
only 60 psig; by 1900 they had increased to
about 300 psig.
SCOTCH MARINE BOILERS
To overcome the structural weaknesses and
at the same time reduce cost of fabrication, the
boiler shell was made cylindrical (replacing
the earlier box construction) with provision to
install one or more combustion chambers be-
tween the two flat sides of the shell. Known as Airto Windbox
the Scotch marine boiler, this boiler as finally ..

developed met with wide and enthusiastic ap-


proval by marine engineers. Although minor Fig. 3 Scotch marine boiler fired by spreader stoker
COMBUSTION
Marine Bollen

Some adaptations proved highly advantageous main-bank generating tubes without the need
with respect to heat transfer and weight, and of- for a person to enter the steam drum. Appre-
fered a variety of designs suitable for pressures ciably heavier than presently available boiler
in excess of the maximum of firetube types. designs, the sectional-header boiler was used
Thus, new possibilities were presented for the during World Wars I and I1 on many classes of
utilization of steam aboard ship.2 merchant ships. The design was ideally suited
for mass production.
SECTIONAL-HEADER BOILERS
The C-E Type SM sectional header boiler as
As an early water-tube boiler, the cross-drum shown in Fig. 4 was designed for capacities up
type had generating tubes extending between a to about 150,000 lb of steam per hour and pres-
row of rear headers arranged vertically and sures up to 850 psig. Steel corner columns in-
connected to the drum, and a row of uptake corporated into the casing members form a
headers at the front of the boiler. Vertical wa- boxlike structure which supports the boiler.
terwall tubes were arranged at both sides of the An insulated casing encloses the entire unit.
furnace. At a later stage of development, the Where good accessibility is necessary, the cas-
downtake headers in the steam drum were re- ing panels are removable and are held in place
located to the front of the boiler and that basic by bolted batten bars. At other locations the
arrangement is known today as the cross-drum casing panels are welded in place. Generally,
sectional-header boiler. the side and rear walls of the furnace have ver-
The handhole plates in the headers of this tical waterwall tubes. Superheaters may be
type of boiler provide ready access and make it either interdeck or overdeck, depending on the
possible to turbine-clean the water sides of the steam temperature required.

Air Heater Bypass Damper


Drum lnternals
Risers

Sectional Header
Superheater Elements
Screen Tubes i Downcomers
Outer Casing
Junction Header
Rear Waterwall Tubes
Setting and Insulation

Waterwall Downcomers
Rear Waterwall
Headers

Fig. 4 C-E SM sectional header boiler, principal parts identified


BENT-TUBE BOILERS would be available. Because of improved re-
Just as the need for increased steaming fining processes coupled with the natural
capacities within fixed space and weight lim- motivations of profitable marketing, it was to
itations spurred the development of the earlier be expected that the crude oil was to be pro-
water-tube-type boilers, so did the same need cessed to the fullest, and the resulting residual
precipitate the advance to boiler designs of the oil which normally goes to bunkers of ships
bent-tube type. would be progressively of lower quality. The
The most compelling reasons for the de- prewar boilers were particularly vulnerable to
velopment of higher capacity boilers came fireside damage caused by slag deposits from
from the naval designers who, at about the end burning such poor;quality fuels.
of the nineteenth century, were charged with A comprehensive analysis of these problems
developing the torpedo boats which were the led to the development of the C-EV2M Vertical
forerunners of modern destroyer-type vessels. Superheater Boiler. Fig. 5 shows a typical ar-
The term bent-tube boiler covers a wide rangement of this design. By providing a sepa-
range of boiler designs characterized by the rate drum or distributing header at the lower
ability to raise steani pressure within a short end of the screen tubes, it is possible to set the
period of time. This means smaller tube diame- floor of the furnace independently of the loca-
ters, fewer headers, increased furnace ratings tion of lower drum and main bank. Not only
and wider application of watercooled furnaces. does this allow greater latitude in establishing
The boilers of this category also became known optimum furnace dimensions, but it also per-
as multidrum type, express type, or by various mits the superheater tubes to be parallel to the
other names corresponding to the designers of generating tubes. The access space within the
particular arrangements. superheater contributes to ease of maintenance
With advanced designs available for naval and inspection.
vessels, it was a quite logical step to utilize V2M8 AND V2M9 DESIGNS
adaptations of those designs for high-powered
passenger ships. Thus during the 1930's, the Fig. 6 shows the V2M8 Vertical Superheater
two-drum bent-tube design was developed Boiler whose major design featdres are the
for application to merchant ships with power single-cased welded-wall furnace and the ver-
plants ranging up to about 10,000 shp. tical in-line inverted U-loop superheater, fully
After World War 11,ship operators and boiler drainable. The boiler shown is top-fired with
designers became acutely aware that marine- resulting improved gas distribution over the
boiler designs would have to be modified to entire superheater furnace. Both the main-bank
avoid some of the difficulties that were being tubes and superheater elements are in-line for
encountered with the prewar designs. During improved tube cleaning. Normally, sootblow-
the war, with the emphasis upon standardiza- ing equipment includes retractable blowers in
tion and multiple production, time was not the superheater and rotary blowers in the main
available for the development of improved bank and economizer. Typical heat-recovery
designs. equipment consists of a small economizer fol-
Another factor which prompted the devel- lowed by a regenerative air preheater or, in
opment of new boiler designs stemmed from some cases, a regenerative air preheater only.
competitive and economic pressures compel- The welded-wall construction provides a fur-
ling shipowners to look toward higher steam nace with gas-tight integrity without the need
pressures and temperatures, and also propul- for double casing or heavy refractory bricks be-
sion plants of-greater power, as a means of hind the tubes. All that is required for insula-
achieving more profitable operation. It was tion behind the walls is blanket insulation.
_ also realized that ship boilers would have to be Some boilers of this type have been built with
designed to burn efficiently whatever fuel oils "double" or "twin" superheaters. With the
COMBUSnON
Marine Boilers

.-

Superheater Elements

Main Generating Bank

Setting and Insulation


Superheater Access Space

..
Water Drum

Superheater Headers

Rear Waterwall Tubes


Side Waterwall Tubes
Distributing Header
Burners Outer Casing

Fig. 5 C-E V2M Vertical Superheater Boiler with main parts called out

Steam ~ r " m
Windbox
Drum lnternals
Burner
Control
Desuperheater Air Register

External Furnace Sidewall/


Downcomer Roof Tubes

Generating Superheater
Bank Screen Tubes

Rotary Vertical
Sootblowers Superheater

- Auxiliary Retractable
Sootblowers
Desuperheater
Casing
Water Drum & Insulation
Superheater Lower Waterwall
Headers Header

Fig. 6 The V2M8 Vertical Superheater Boiler design featuring the single-cased welded-wall furnace and
the vertical in-line inverted U-loop superheater, fully drainable
COMBUSPION
Marine Bolhn

double superheater, the elements are more


widely spaced so that cleanliness is easier to
maintain. Tube metal temperatures are also re-
duced, both because of the lower mass gas flow
across the superheater and the location of the
secondary superheater, which is furthest away
from the furnace. The total surface, overall size,
and weight of a double superheater are, how-
ever, much greater than that of the single
superheater because of the reduced mass gas
flow and consequent lower transfer rate.
To generate the much higher evaporations
required by increasingly larger ships, the fur-
naces were required to be made very large. To
keep the main bank at essentially the same ver-
tical dimension as the V2M8 boilers, it was
necessary to lengthen the furnace in a vertical
dimension. The boiler then became a vertical
two-drum dropped-furnace boiler. Because the Fig. 7 The C-E V2M9 vertical two-drum
lower part of the furnace (see Fig. 7) was unen- dropped-furnace boiler
cumbered, it became clear that the boiler could
be tangentially fired. The fuel nozzles are all times the register is in operation, while the
placed in each corner of the furnace, and fire at secondary-air dampers are modulated to main-
a target circle in the center of the furnace. This tain a constant register draft loss. In this way,
lengthens the fuel-particle residence time in good combustion efficiency can be maintained
the furnace, and allows for complete combus- over a wide boiler range.
tion and operation at very low excess air. Fig. 7 Fig. 8C shows a typical draft-loss curve for
shows the boiler configuration; Fig. 8A, a dia- tangential firing. The registers can be operated
gram of tangential firing. Major design features to cycle on and off for either a two- or four-
include single-cased welded-wall construc- register operation based on steam flow and
tion, tangential firing, and vertical in-line dou- drum pressure, or they can operate with four
ble superheater, inverted U-loop, fully drain- registers on whenever the vessel is under way.
able. The boiler is supported at its midpoint, The oil guns are of the steam-atomizing type
under the water drum and center headers. utilizing constant steam pressure at 150 psig
In some of the larger designs of single-boiler with fuel pressure up to about 350 psig. Flame
ships, a nondrainable superheater has been monitoring is accomplished by scanning along
used, because the boiler would be on the line
from drydocking to drydocking.
Table II summarizes typical performance data Table 11. Typical Performance Data:
for a regenerative air-heaterhoiler. Regenerative Air-HeaterIBoiler
The registers of a tangentially fired marine
boiler are of a straight-throat type with pri-
Evaporation 220,000 lblhr
mary- and secondary-air zones. The primary
airflow is through the center compartment, Total steam temperature 955F
where the oil gun and diffuser are also located. Feedwater temperature 424OF
Secondary air is above and below the center Superheater outlet pressure 865 psig
Excess air 3%
compartment. See Fig. 8B. Under normal oper-
- Efficiency 90.7%
ation, the primary-air damper is fully open at
COMBUSTION
Marine Boilers

the axis of the flame and also scanning the


flame across the furnace corner, with both
scanners showing NO FLAME required to close
the fuel-oil solenoid valve. Scanners will scan . - -
the individual flame up to about 30 percent
boiler rating, after which they will scan the
furnace as a whole. If the boiler rating is above
30 percent, the "fireball" in the furnace is large
enough to ignite any incoming oil.
STOKER-FIRED DESIGNS
Fig. 9 shows a modern stoker-fired marine
boiler designated as a V2M9S boiler. The boiler
is a single-cased welded-wall design with sin-
gle-cased uptakes; some areas around super-
heater headers, access doors, and windbox
are double cased. Table I11 compares typical
performance data of a coal-fired design with an
equivalent fuel-oil-fired design.
By comparing the furnace release rates, it can
readily be appreciated that the coal furnace has
about 3 times the volume of the oil furnace for
the same power output. To minimize furnace
and superheater problems, furnace tempera-
ture when burning coal is kept lower than the
ash-fusion temperature. This temperature can
be readily achieved with a totally watercooled
furnace by limiting the grate release and fur-
nace heat release. Overfire-air jets and cinder
reinjection nozzles are located above the stoker
grate, with one line of nozzles serving to r e
duce the carbon loss by about 4 percent. A
cinder hopper is located between -the two
superheater sections. In addition to the stoker,

Table 111. Comparison ..


of Performance Data for
Coal- and Oil-Fired Designs
Coal Oil
Furnace release rate,
-
I Load Btulhr-cu ft
Grate release rate,
Btdhr-sq ft
25,000

700,000
75,000

...
L 1 Furnace absorption rate,
Fig. 8 Diagram of tangential firing. Fuel nozzles Btulhr-sqft 37,000 70,000
located in each corner of the furnace Furnace outlet temp., OF 1900 2500
fire at a target circle in the furnace center.
Stoker Floor Line

Fig. 9 A V2M9S stoker-fired marine boiler with a single-cased welded-wall design and single-cased uptakes

a fuel-oil burner is incorporated in the upper outside the gas passage with a gas-tight tube
furnace for in-port firing or take-home pur- sheet separating them from the gas duct. This
poses. When the burner is in use, a layer of ash type of extended-surface heat exchanger is es-
is retained on the grate to protect it from over- sentially of the same construction as a marine-
heating. Tube spacings in both the superheater boiler economizer. The combination of
and main bank and the economizer fin spacings large-diameter tubes with welded helical fins
are increased over the fuel-oil-fired spacings to for extended heat-transfer surface is simple,
keep gas velocities low for minimum erosion. rugged, and compact.
WASTE-HEAT DESIGNS - An important consideration in !he design of a
waste-heat boiler of this type is to configure a
Many vessels powered by diesel engines and heat exchanger that will produce the required
gas turbines extract waste heat from exhaust amount of steam within a limited amount of
gases to create efficient cogenerative cycles. space, with acceptable gas-side pressure drop.
The recovered heat provides shipboard energy A large gas-side backpressure on either a diesel
in the form of steam for fresh-water production, engine or a gas turbine will result in significant
water heating, fuel heating, cargo heating, gal- degradation of engine performance.
ley and laundry services, and, in some in- Fig. 11 shows a waste-heat steam generator
stances, to drive a turbogenerator to supply the system as installed in a typical naval vessel.
electrical load of the ship.3,4.5,6,7There are vari- The five modules, each of which is supported
ous shapes and sizes of waste-heat boilers; Fig. on its own foundation, include the steam-
10 shows a typical waste-heat steam generator generating bank, the drum module, the con-
composed of horizontal finned tubes connected denser, the control panel, and the feedwater
by return bends. The return bends are installed pump. Each module can be situated to optimize
COMBUSTION
Marine Boilers

Outlet Transition Duct


Structural Braces
utlet Turning Vanes

Exhaust 4
Gas Outlet External Return Bends

Handhole Acces
Outlet Header
Vestibule Access
Dual Water lnlet
Handhole Access
Traverse Expansion Plates Individual Packing

Inlet Vane System Sprial Finned Alloy Tubing


lnlet Transition Duct

Fig. 70 Steam generating bank module

maintenance access on the ship. The following circulated through the waste-heat bank and re-
specific design features of the waste-heat boiler turned to the steam drum of the auxiliary-
system illustrated promote ease of maintenance boiler. Controls are then arranged to
access. automatically fire the auxiliary boiler so that
drum pressire is maintained with varying
rn Generating bank headers are external to the
loads. If the steam generation by waste-heat gas
casing.
alone is too high, a steam dump to a condenser
Headers, inspection doors, and access doors or gas bypass damper can be installed. If re-
.are accessible by removing .portable insulat- quired, a waste-heat bank can also be arranged
ing pads. to run as an independent unit with its own
rn Full size header handholes are provided, steam drum and circulating-pump system.
with one handhole for each two tubes. The need for oxygen removal on low-pres-
Individual generating bank tubes are remov- sure auxiliary systems is just as great as in main
able; each tube is easily handled by one per- propulsion systems. The direct-contact feed-
son. The entire generating bank need not be water heater is a reliable and effective device
removed to replace one tube. for continuously maintaining feedwater at ac-
Individual condenser tubes are removable; ceptable low levels of oxygen and should be in-
each tube is easily handled by one person. stalled. The advisability of using a deaerating
rn Large access-way is provided in steam drum feedwater heater has been recognized by not
for access to drum internals. only boiler-water chemistry consultants, but
also designers who have experienced problems
The boiler bank shown in Fig. 10 can be used with corrosion caused by poor water chemistry
in series with an auxiliary boiler, with water in waste-heat boiler systems.
I
Fig. 11 Marine waste-heat boiler system modules

DESIGN PRINCIPLES FOR ments, and burner arrangement also influence


the furnace layout. The furnace arrangement
MARINE-BOILER FURNACES must also conform to criteria which are pre-
A number of factors determine the configura- requisites for proper thermal and circulation
tion of a marine-bpiler furnace. First of all, the performance. The amount of waterwall sur-
type of boiler under consideration sets some of face determines the furnace exit-gas tem-
the furnace dimensions. As already discussed, perature which, in turn, is most significant in
- fireroom space limitations, service require- the design of the superheater. Practical re-
COMBUSTION
Marine Boilen

quirements must also be considered; for in- furnace. Although such a boiler design permits
stance,..the firing equipment must be located a wide range of control, there are inherent
where it can be easily operated. complications in the operating procedures.
Two-drum bent-tube boilers are always-fur- Most two-drum bent-tube boilers are de-
nished with watercooled surfaces on the side and signed with the superheater within the gen-
roof and, for the majority of designs, both front erating bank and with either horizontal or
and rear waterwalls are included. vertical superheaters. Positive means must be
provided to keep superheaters clear of slag
deposits. To permit convenient access for in-
spection, cleaning, and maintenance, modern
designs include access spaces within the
SUPERHEATERS superheater banks.
Superheaters are essentially a series of tubu- The advantageous features of the vertical
lar elements connected JO headers. The satu- superheater, as shown earlier in Fig. 6 , result in
rated steam enters the inlet header from piping reduced maintenance and optimum service ef-
connected to the steam drum. In a single-pass ficiency. Because.the elements are arranged
, superheater, the saturated steam flows from the parallel to boiler tubes, clear lanes between
saturated header through the superheater ele- generating and superheater tubes present the
ments into the superheater outlet header. In the best arrangement for effective action of the
multipass superheater, the headers are dia- sootblowers. With the superheater tubes in a
phragmed to allow the steam to make as many vertical position, it is difficult for slag to ac-
passes as necessary to assure good steam dis- cumulate. Bulky supports are eliminated as it is
tribution through all elements. possible to support each superheater tube from
Marine superheater design requires a ju- the superheater headers which are outside of
dicious balancing of economic and practical the gas pass. Small slip spacers attaching
factors. There must be a sufficiently large tem- superheater elements and adjacent generating
perature difference between the combustion tubes maintain the upper ends of the super-
gas passing over the superheater surface and heater elements in the correct lateral position.
the steam within the surface to result in a su-
perheater of economic proportions. At the same
time, there are practical limitations on su- For most modern marine boilers, all of the
perheater metal temperatures, and provision steam generated by the boiler is passed through
must be made to arrange superheater elements the superheater. Auxiliary steam requirements
to resist slag accumulation. Screen tubes are are met by desuperheating the required quan-
located ahead of superheaters to obtain reason- tity of auxiliary steam. Because the superheater
able metal temperatures while at the same time is located in a relatively high-temperature gas
allowing a certain amount of direct radiation to zone and overheating may occur if any substan-
be absorbed by the superheater tubes. This re- tial proportion of steam were taken directly
sults in a flatter steam-temperature curve at the from the steam drum to the auxiliary steam
superheater outlet. line, this arrangement is necessary to maintain
Some boiler designs have the superheater a flow of steam through the superheater at all
behind the main generating bank. Such an ar- times. To provide low-temperature steam for
rangement requires a relatively greater amount auxiliaries and for other purposes, such as
of heating surface and an elaborate system for heating, Butterworthing (a special system for
controlling superheater outlet temperature. An steam-cleaning cargo tanks), and evaporators,
alternative arrangement incorporates a second steam from the superheater outlet is passed
furnace for controlling the steam temperature through a desuperheater which absorbs some
by varying the firing rate of the superheater of the heat in the superheater steam.
COMBUSTION
Marinc Boilem

Desuperheaters can be of the internal or the


external type. The internal type contains tubu-
lar elements with necessary terminal connec-
tions to be installed within the boiler drum.
Fig. 12 shows a typical arrangement of an inter-
nal-type desuperheater as installed in a boiler
drum. Note that the unit is arranged so that it
may be passed through the drum manhole as a
complete assembly. The external type includes
C 950F,
Curve A

Curve B

a direct or indirect heat exchanger mounted in


the steam line, with feedwater most generally
0 25 50 75 100 125 150
used as the cooling medium. Percent Rat~ng
STEAM-TEMPERATURECONTROLS
For high-temperature applications, design- Fig. 13 Superheater characteristic curves
ing for a constant steam temperature over a rela- perature tends to rise above the set temperature,
tively wide load range may be desirable, as the control valve opens to permit a portion of the
indicated by the superheat characteristic Curve steam to flow to the desuperheater and have its
A in Fig. 13, or for nominal temperature appli- temperature reduced. The control valve has a
cations to limit the steam temperature at infre- hand jack for manual operation.
quent overload ratings, as shown by Curve B.
With the exception of manual operation of
The dashed-line extensions of characteristic
the automatic control valve, the same general
curves show- expected temperatures without
control. Fig. 14 shows a typical arrangement arrangement is used to accomplish the limit-
ing-type of temperature control, as shown in
which will provide close control of steam tem-
perature and, in so doing, protect the last passes curve B of Fig. 13. At higher boiler ratings,
when the temperature starts to exceed the pre-
of the superheater, turbine, and connecting steam
determined maximum, the control valve is
piping from high metal temperature. The steam
opened fully, accounting for the temperature
temperature at the superheater outlet actuates an
drop just beyond normal rating and the contin-
air-operated control valve. Below the set temper-
uing rise to maximum rating.
ature, all steam passes through the orificed line,
the control valve being closed. When the tem-
!
I

in Headers
Desuperheater
- * -

fig. 14 Steam-temperaturecontrol
Fig. 12 Internal-type desuperheater arrangement for marine boiler
Marine BoNers

greater temperature difference between the gas


HEAT-RECOVERY EQUIPMENT and water. Under these conditions, the heat-
FOR MARINE BOILERS transfer rate cannot be increased without in-
The general classification "heat-recovery curring a substantial resistance to gas flow, and 'I
equipment" covers heat exchangers which are the use of extended surface to increase the heat-
located such that heat is absorbed from the ing surface per lineal foot is desirable. What-
combustion gases after the gases have passed ever the arrangement of economizer, ample
through the superheater and steam-generating provision must be'made to assure that the heat-
sections of the boiler. Economizers, tubular air ing surface can be kept free of deposits. The
heaters, and LjungstromB regenerative-type air coexistence of deposits and moisture can cause
heaters, are the types most commonly used for corrosion; accordingly, the spacing of the ele-
marine boilers. ments, the quantity and effectiveness of the
sootblowers, and the design of the breeching
ECONOMIZERS above the economizers must a1.l-be carefullv
The economizer is a series of horizontal tubu- considered. Moisture can come from a number
lar elementshy means of which heat is recov- of sources:
ered from combustion gas leaving the boiler 1. Rain or spray down the stack
and added to the incoming feedwater. The
amount of heat absorbed in an economizer de- 2. Leaks in economizers or other pressure parts
pends on the temperature difference between 3. Condensation of moisture in gases because
gas and water, the heat-transfer rate, and the of the gas coming into contact with cold heat-
amount of heating surface. It is the normal prac- transfer surfaces and cooling to below the acid
tice to use some form of extended surface on dew-point temperature. Also, dependent on
tubes to increase the heating surface per unit of the sulfur content of the gas, this condensation
tube length. forms a corrosive sulfuric-acid solution which
Economizers can be categorized as bare tube attacks the metal surfaces.
and extended surface types. The bare tube usu- Although a leak in an economizer pressure
ally includes varying sizes which can be ar- part cannot go undetected for very long, substan-
ranged to form hairpin or multiloop elements. tial corrosion-erosiondamage can result quickly
Because the coefficient of heat transfer is if a leak is allowed to persist. Therefore, it is
relatively low on the gas side of an economizer advantageous to design economizers with the
tube as compared to that on the waterside, it is
desirable to have some form of extended heat-
ing surface on the outside of the tube so as to in-
crease the overall rate of heat transfer. Many
different configuratiosls of extended surface
are used, each with characteristics of a specific
standard adopted by a particular boiler manu-
facturer. In turn, each type of extended surface
economizer has a heat-transfer rate that is pecu-
liar to the shape and finish of the surface, the
material employed, and the method of fabrica-
tion. Fig. 15 shows a widely used type of ma-
rine economizer extended surface.
Most marine economizers are designed for
counterflow of gas and water, that is, water
down through elements and gas up outside of . Close-up view of economi+er
~ j g 15
elements. This is done to take advantage of the spiral steel surface
minimum of joints and handhole plates consis- that there is generally an increase of total steam
tent with proper provision for replacing an temperature because of the higher fuel firing rate
element. Generally, the header tube joint is and increased furnace temperature.
made up as a full welded joint or, as an alternate AIR HEATERS
construction, the elements are welded to nip-
ples in the headers. . Using air heaters to improve the performance
Although the economizer is designed prin- of steam-generating units began in marine
practice prior to 1880. At that time, practically
cipally for steady steaming conditions, proper
consideration must be given to the design of the all the heaters were of the tubular type with var-
elements so that steam will not be generated ious arrangements of vertical or horizontal
within the economizer during maneuvering. banks of tubes. In some, the gas passed through
This means that there must be suitable water the tubes, while in others the tubes served as a
velocities and pressure drops to assure ade- passage for the air. Most marine tubular air
quate circulation in each element. Under most heaters are of the horizontal type, preferable be-
conditions, there is sufficient differential be- cause of its simplicity and the ease of incorpo-
tween saturation and feedwater temperatures rating it into the boiler arrangement.
to prevent the generation of steam. But there Most marine tubular air heaters are located
may be some maneuvering conditions, such as immediately above the boiler gas exit where the
the sequence from stop to full ahead, in which unit can be fitted conveniently into the boiler
design. For a two-pass heater, air both enters
steaming may become a problem. This is par- and exits at the rear side of the boiler, present-
ticularly true if the water level is high at the ing an efficient arrangement for transporting
start of the maneuver and the boiler control sys- air to the fuel burners.
tem is of the single-element (water-level) type.
Usually, an economizer is installed at the REGENERATIVE AIR HEATERS
boiler outlet adjacent to the stdam drum with Regenerative air heaters for marine service
elements parallel to the drum. In most fireroom are designed for horizontal or vertical flow of
arrangements, sufficient space is available for a the combustion air and stack gases, In this
good economizer arrangement. However, to ob- type of heat exchanger, as described further in
tain the required economizer heat absorption, Chapter 14, the heating elements are contained
the economizer length, width, and number of in a slowly turning rotor of cellular construc-
tubes high may have to be varied to obtain the tion. As the rotor turns, heat is absorbed con-
best arrangement for the space conditions tinuously by the heating elements from the flue
available and to meet thermal performance gas, while a like amount of heat is released
conditions. In addition, the allowable gas-side simultaneously to the combustion air, as these
pressure loss and water pressure drop must be fluids flow axially through the rotor. The rotor
considered. is enclosed in a gas-tight housing which is
Today, it is common practice to design fitted at each end to make connections with
marine economizers so that they can be by- the air and flue-gas ducts.
passed if a leak occurs, thereby allowing the Dampered integral air and flue-gas by pass
boiler to remain in service until the necessary ducts are incorporated in the four corners of
repairs can be made. The economizer then must the structure. Parallel air by-passes offer a way
withstand entering gas temperatures without of controlling cold-end heating-element temper-
any feedwater flow through the economizer tubes. ature during operation at reduced steaming rate.
With the economizer bypassed, the feedwater The flue-gas bypasses in parallel, together with
enters the boiler directly at a lower temperature, the air bypasses, provide a means of limiting
which results in an increased fuel firing rate, in- overall pressure loss at steaming rates above
creased draft losses, and overall loss of boiler the corresponding to normal power. Fig. 16
efficiency. Another important consideration is shows a typical regenerative air heater for
CONBUSTION
Marine BoNem

marine service.
A vertical-flow regenerative air heater can be
located directly above the boiler outlet or in the
area above the boiler, and connected with con-
ventional ductwork. From the top of,fhe air -
heater on the gas side, an uptake is led to the
suck in the usual manner. Forced-draft fans
may be located conventionally and connected
to the air side of the heater by means of duct-
work. Various arrangements can be utilized to
suit the conditions (See Fig. 17).
STEAM AIR HEATERS

Both the boiler operating conditions and the


efficiency required of a boiler unit affect the
selection of the heat-recovery equipment to be
incorporated in the design of a boiler. These are I I
related to the specification of a suitable steam Fig. 77 Arrangement of regenerative
cycle for a marine installation. The best steam air heaters aboard ship
cycle for one installation may not be advan-
tageous to another. Therefore, for certain extracted from the feedwater heater or aux-
installations, an air heater alone may be iliary exhaust. This reduces the flow of steam to
optimum. Where feedwater temperature and the condenser and improves cycle efficiency.
pressure conditions permit, an economizer or a An alternative method is to extract low-
combination of an economizer and a steam air pressure bleed steam from the main turbines.
heater is used to obtain the boiler efficiency re- In the condensing of the bleed steam or
quired, with no gas-to-air heater. auxiliary exhaust, heat is transferred to the air
One method to improve the steam-cycle effi- used for combustion. Because the condensing
ciency is by means of the feedwater heating sys- steam-film coefficient of heat transfer is high,
tem, and here the steam air heater uses steam extended surface is used to advantage. Closely
pitched tubes and fins can be utilized, as both
the air and heating fluids are clean, eliminating
entirely the necessity for cleaning.
In most steam-air-heater'installations, bleed
steam at 10 to 45 psig is used. Although a feed-
water heater uses steam at relatively high
pressure, the steam air heater uses auxiliary
exhaust or low-pressure bleed steam. Utilizing
the lower pressure bleed steam is a good
method of improving cycle efficiency.
Another point to be considered is that the
auxiliary exhaust can be used to advantage in a
steam air heater while boilers are steaming
in port, thereby improving low-load boiler
operating conditions. Suitable air temperature
for good combustion is readily maintained,
Fig. 76 Regenerative air heater whereas with a tubular or regenerative-type air
for marine service heater, a bypass system around the heater is
necessary to avoid cold-end corrosion. The primary and secondary economizer ele-
ments are all of spiral steel-fin construction
FLUID REGENERATIVEAIR HEATER
which has been proven by many years of marine
Fig. 18 shows an arrangement of a fluid re- service (Fig. 15).
generative air heater. This is an arrangement For a 45,000shp plant, in changing from a
where the feed pump takes suction from the de- steam-air-heaterleconomizer cycle to a straight
aerating feedwater heater and discharges to the regenerative air-heater cycle, there is an overall
secondary economizer where the 285F feed- plant efficiency increase of about 4 percent. Of
water cools the stack gases to approximately this 4 percent increase in efficiency, about 1.5
310F'.In this process, the water is heated to percent is from the decrease in stack tempera-
about 340F.The feedwater is then routed to an ture, usually from 310F to about 250F; the
air heater where it is cooled by the incoming other 2.5 percent is from the additional re-
combustion air to its original temperatufe of generative feedwater heating of the high-pres-
285F and, in this process, the combustion air sure heaters (less heat rejected to the condenser
is heated to approximately 310F. The water cooling water). From the standpoint of effi-
then passes through the fourth and fifth-stage ciency, the regenerative air preheater is the
heaters, entering and leaving at temperatures of more attractive. Some shipowners, however.
285"F and 423 O F respectively. still prefer the economizerlsteam-air-heater
From the heaters, the water enters the pri- cycle because of longer life of economizer sur-
mary economizer and then goes to the boiler. face when compared to the cold-end heating

310"F Combustion
Stack Gas Air Main Steam -a-
Feedwater -- -- -
Turbine Bleeds-
Condensate ----
-----

IL m e - - - - - - - - - -

Fig.-I8 Component arrangement of a closed-loop fluid regenerative air heater


COMBUSTION
Marine Bollers

surface of an air preheater. consists of a burner atomizer which converts


Under such a constraint, the use of a closed- the potential energy of the oil pressure into a
loop fluid regenerative air preheater can be flow of atomized oil particles. The register in-
considered for the following reasons: troduces and mixes the air with the oil spray
I. The plant efficiency will be increased by ap- produced by the atomizer. The oil flow is regu-
proximately 2.5 percent because of the use of lated by varying the supply pressure. On some
high-pressure feedwater heaters; installations this is accomplished manually; on
2. The stack gas temperature will remain the others, it is automatically performed. Airflow
same as is presently used in a steam-air- is regulated by manual adjustment of the
heaterleconomizer cycle; maintenance, there- forced-draft fan output or by the automatic ad-
fore, will remain at the standards that are justment of the combustion control. This type
acceptable today; of burner has a range or turndown ratio of be-
tween 1.5 and 3.0, depending on the pressure of
3. Gas inerting systems can utilize the cool
the fuel-oil service system.
stack gas after the economizer because there is The return-flow type of burner functions
no air leakage in an economizer system; with a constant-pressure oil supply, and the
4. Forced-draft fans can be selected smaller atomizer barrel contains a passage to permit a
than in the equivalent regenerative air pre- portion of the oil to return to the fuel-oil service
heater plant because there is no air leakage in pump suction. Regulating the control valve in
the economizer system. the return line varies the firing rate. This type
of burner achieves a much wider range than the
FUEL BURNING straight mechanical burner.
The steam-atomizing-type burner uses a flow
Oil burners for marine boilers must have fea- of steam which mixes in the atomizer tip with
tures and operational characteristics consistent the oil flow. A portion of the<energy in the
with the service requirements of the propulsion steam serves to break up the oil particles, and
plant. The burner must also be capable of pro- better atomization results. This type burner
ducting efficient firing over a wide range of oil offers a high turndown ratio and the advan-
flow rates and be able to change load rapidly to tage of being able to burn low-quality fuel
meet the maneuvering requirements. For ships efficiently.
which maneuver for a substantial proportion of
the operating time, it is essential that the boil-
ers be fitted with burners capable of varying the
firing rate over a wide range without the need of
changing atomizer tips.
Before the fuel oil can be burned, the oil must
be changed from a liquid to an atomized condi-
tion. Simultaneously, it must be mixed with an
ample supply of air to permit combustion. A
burner actually consists of two parts; the atom-
izer or burner barrel which serves to deliver a
flow of atomized oil to the furnace (see Fig. 19),
and the register which serves to supply a uni-
form flow of air to the furnace. The burner Atomizing Tip Oil Tube
barrel contains a sprayer plate, or swirl cham-
ber, and an orifice tip which act together to
produce the spray of fine oil particles. Fig. 19 The atomizer or burner barrel delivers
The straight mechanical type of oil burner a flow of atomized oil to the furnace
COMBUSTION
Llrrine B o k s
--
COAL single-cased boiler, must be designed to ac-
Although the vast majority of shipboard commodate the refractory and insulation.
boilers are fired by oil fuel, there remain some These materials must be arranged to protect the
ship trades where economic conditions make it casing from exposure to gases and must insu-
very desirable to burn coal. Modern coal-fired late the casing from high temperatures. Struc-
marine boilers use stokers. Although many tural members should preferably be located
types of stokers (including chain grate, under- outside the inner casing. Whenever this is not
feed, overfeed and spreader types) have been possible, as may be the case for some supports
used for marine service, the spreader stoker has of furnace insulation and refractory, alloy ma-
p m n itself over a long period of operation to terial should be used if there is any possibility
be best suited and most efficient in meeting the of exposure to high temperature.
requirements. It is capable of burning a wide The space between inner and outer casings of
range of bituminous coals and has the ability to a double-cased boiler provides a convenient
respond quickly to load changes. These fea- duct system by which the air for combustion
tures make spreader stokers attractive for ves- can flow to the burners. Because there can be a
sels that will continuously serve in trades wide choice of locations for the air inlet con-
which have a readily available source of c ~ a l . ~ .nection,
~ the arrangement presents consider-
Chapter 12 gives further descriptive material on able flexibility to the design of the forced-draft
the spreader stoker for coal firing. system. Those sections of the air space not sus-
-
taining the main flow of combustion air are
provided with a flow of cooling air which ulti-
BOILER CASINGS mately discharges into the windbox. Thus, all
The primary function of a marine-boiler cas- of the inner casing is pressurized. Because the
ing, Figs. 20 and 21, is to contain the products airflow absorbs a large proportion of the heat
of combustion in such a way that the gases flow given off by the inner casing, there is a reduc-
from the furnace through the steam-generating, tion in boiler radiation losses.
super-heater and heat-recovery tube banks, and In laying out the arrangement of casing, cal-
out the breeching. Although both single and culations must be made to determine that the
double-cased designs may be used, the func- air pressure-drop values are not excessive and
tion of containing the products of combustion
takes place in that casing which is immediately
exterior to the refractory and insulation wall.
Many modern boilers are built double cased.
In this arrangement, air pressure in the space
between the inner and outer casings is greater
than the pressure within the furnace. Accord-
ingly, if there are any open joints in the inner
casing, there will be an airflow into the furnace
instead of an outward flow of gas and soot. But
this advantage should not be overexploited to
the extent of disregarding the maintenance of a
tight inner casing. If the flow of air through
inner casing leaks is allowed to become sub-
stantial, boiler efficiency will be impaired and
other detrimental effects will accrue.
DESIGN OF INNER CASING
Fig. 20- Exterior view of marine boiler showing
The inner casing, or the only casing in a casing arrangement
COMBUSTION
Marine Boilem

that the velocities and airflow pattern in the usually separately mounted to the structure of
windbox will be suitable for the even distribu- the ship.
tion of air to the registers. In determining the When it is necessary to obtain a better layout
dimensions of the air space, allowance must be of the breeching when there is a narrow fidky
made for the restrictions imposed by down- which limits the space directly above the boiler,
comers, structural members and fittings such the heat-recovery equipment may be mounted
as sootblower sleeves. directly on the boiler. The Ljungstrom air heater
is usually located on a deck or platform above the
METHODS OF SUPPORT boiler with the ship structure providing support.
For some types of boilers, the casing struc-
For most designs of bent-tube boilers, the ture must also support the pressure parts, and
weight of the pressure parts, and the included this requires that heavier structurals be in-
water, is carried by the water-drum saddles and cluded at the points of loading. The sectional-
waterwall header saddles. Steam and tubular- header-type boiler has column-type supports
type air heaters are generally supported by built into each -corner of the casing, as de-
the boiler casing. Heat recovery equipment is scribed earlier. -

Fig. 21 Details of boiler casing as fabricated in the assembly plant


--
common

The loadings from connecting piping, par- demand, and boilers may be operated for
ticularly main-steam piping, can produce ex- sustained periods of a year or longer between
cessive stresses in the boiler connections. shutdowns for inspection and maintenance.
According to accepted procedure, the boiler
manufacturer specifies the maximum allow-
able forces and moments which can be taken by
the connections, and the shipbuilder designs
the piping to stay within the limits. REFERENCES
1 Robert E Latham, Naval Boilers. Annapolis, Md.: U.S.
NavalInstitute. 1956.
COMMON AlTRlBUTES 2 Otto de Lorenzi, editor, Combustion Engineering: A
OF MARINE AND STATIONARY Reference Book on Fuel Burning and Steam Genemtion.
New York, Combustion Engineering,. Company, Inc.,
DESIGN".PRACTICE 1947.
The special considerations required for the See also the 1966 edition, edited by Glenn R. Fryling
design of m i n e boilers have been discussed in and published by Combustion Engineering, Inc.
this chapter. Many relate to the differences in 3 Thomas P. Mastronarde, "Energy Conservation Using
operating conditions between land and marine Waste Heat Boilers: The Challenge, Problems, and Solu-
tions", presented at ASNE Day 1982, sponsored by Ameri-
practice. For example, the output of a marine can Society of Naval Engineers, May 6 and 7, 1982,
power plant is basically a function of the speed Washington, D.C. and originally published in Naval
and the displacement of a ship, and there is no Engineers Journal, April 1982, also as Combustion
Engineering Publication TIS-7039.
exact counterpart to this in industrial or utility
power plants. In addition, the majority of ma- 4 Breaux, D. K. and Cdr. K. Davies, "Design and Service of a
Marine Waste Heat Boiler," Naval Engineers Journal,
rine boilers are integrated into a cogenerative Volume 90, No. 2 (April, 1978). Pages 165-175.
cycle. 5 Graf, T. E. and J. E. Nagengast, "DD-963 Class Waste Heat
Marine boilers operate successfully at very Recovery System Experience:' ASME Publication 79-GT-
much higher heat release rates and smaller box 159.
volumes than field-erected stationw boilers. 6 Abbot, J. W., Published Comments on Papkr by Dr. Eugene
This is partly accounted for by the nature of Brady titled "Energy Conservation for Propulsion of Naval
marine power-plant operation. For one thing, Vessels:' NavalEngineers Journal, Volume 92, No. 3 (June,
1981).
feedwater is of high quality because, at sea,
evaporators furnish makeup. In addition, two or 7 Csathy, D., "Heat Recovery From Dirty Gas:' presented at
Sixth National Conference on Energy and the Environ-
more boilers are generally installed, and al- ment, Pittsburgh, Pennsylvania, May 24, 1979.
though one will operate at rated capacity while
8 Fukugaki, A., et al, "Design of a N& Generation Coal
the ship is at sea, at least one can be shut down Fired Marine Steam Pmpulstion Plant:' presented to the
for inspection and maintenance while in port. Society of Naval Architects and Marine Engineers
This is in marked contrast to the operating con- (SNAME) Annual Meeting, New York, November 17th-
ZOth, 1982.
ditions in some types of industrial and utility
power plants which have what amounts to an 9 Horlitz, Carl F. and Sabo, Steven E., "Coal Fired Boilers
for The 1980's': presented to SNAME at the Shipboard En-
almost continuous base load. Under these con- ergy Conservation Symposium, September 22nd-23rd,
ditions there are rarely periods of low-load 1980, New York.
CHAPTER
-
11 .

Pulverizers and Pulverized-Coal Systems

he main reason why pulverized-coal firing


is favored over other methods of burning HISTORICAL PERSPECTIVE
coal is because pulverized coal burns like gas One of the most significant engineering
and, therefore, fires are easily lighted and con- achievements of the twentieth century is the
trolled. Almost any kind of coal can be reduced commercial perfection of methods for firing
to powder and burned like gas. coal in pulverized form. In fact, the devel-
"A change of coal upsets the operation of a opment is one of the cornerstones making
pulverized-coal plant to a much smaller degree possible the extremely large, modern, steam-
than it does a stoker-fired plant. Pulverized- generating unit with its high thermal effi-
coal furnaces can be readily adapted to burn ciency, reliability, and safety.
other fuels that burn like gas, and in that re- Worldwide, practically every coal mined is
spect are capable of burning almost any fuel being burned with complete success in pul-
which is used for making stearn."' Henry verized form. Similarly, many other types of
Kreisinger, former Director of Research at low-grade, waste, and byproduct solid fuels
Combustion Engineering, made this statement may also be fired economically and efficiently
at a 1937 meeting of the American Society of in this manner. As pulverized-fuel firing has
Mechanical Engineers in Windsor, Canada. contributed to the reduction of labor costs in
Today, over 40 years later, pulverized-coal steam power plants, it has also increased opera-
burning has so dominated the utility market tional flexibility and practicable usage of an
that power generation by stoker firing is no extremely wide range of fuels.
longer a consideration. A major reason for the Over the years, the concept of pulverized-
success of pulverized-coal burning is the abil- coal firing has attracted the attention of some of
ity to adapt operating conditions to all coal the finest engineering minds. Familiar with
ranks from anthracite to lignite. While certain early nineteenth century French experiments,
considerations must be made to accommodate Sadi Carnot provided a critical thermodynamic
fuels with such a wide range of properties, the analysis of the pyr6olophore, an engine fired by
years of experience since Kreisinger's state- powdered coal, in his 1824 engineering classic,
ment have simply served to prove the versatil- Reflections on the Motive Power of Fire.2
ity and advantages of pulverized-coal firing. During the 1890's Rudolf Diesel conducted
COMBTXTION
P u h d m n end Pulverized-CoalSystems

his first experiments on the internal combus- iments relating to the use of pulverized coal in
tion engine bearing his name with pulverized 1894, and in the following year it was success-
coal as the primary fuel. At this time pulver- fully applied to a rotary cement kiln. Since that
ized-coal firing was achieving its first real time, pulverized coal has been the dominant
commercial success in the cement industry.3 In fuel in the cement industry.
the early 19001s,Thomas A. Edison made im- By the time of World War I, powdered coal-
provements in the firing of pulverized coal in the term then generally used for what is now
cement kilns, greatly increasing their effi- designated as pulverized coal-had gained suf-
ciency and o u t p ~ t . ~ ficient acceptance for the ASME to sponsor a
In all fairness, however, recognition must be symposium bringing together the accumulated
given also to hundreds of engineers of lesser experience in the several fields of application.
renown who have made equal or greater tech- Reading the record of this symposium will give
nical contributions. Since the first information a clear understanding of the empirical nature of
attributed to the Niepce brothers was pub- the wide variety of equipment available for var-
lished in France in the early 18b0's, there have ious types of pulverized-coal firing.5
been many examples of engineers whose vi-
sions of future developments in pulverized- PIONEERING UTILITY INSTALLATIONS
coal technology have far outreached the mate- By the end of the war, pulverized coal still
rials and technical understanding of their time. had not achieve'd its full potential despite an
Largely developed as an empirical art, pul- increasing number of applications which
verized-coal firing progress has been marked spread from the cement to the metallurgical in-
by the efforts of devoted engineers whose dustry, to the steam locomotive and to several
success may be attributed to persistence de- stationary boilers. Although all of the elements
spite many discouraging obstacles. Gener- for outstanding success appeared to be present,
ally, theoretical understanding has followed someqne was needed to integrate the many
rather than preceded practical accomplish- ideas and to provide a new thrust for pul-
ment in the field of pulverized-coal firing. verized-coal firing in the central-station indus-
try. No one can lay more claim for initiating
INCENTIVES FOR DEVELOPING this impetus than John Anderson, then chief
PULVERIZING TECHNIQUES
engineer of power plants of what is now Wis-
Some elements of engineering reasoning consin Electric Power Company. He effectively
which have stimulated invention and im- enlisted the support and active participation of
provement of devices to burn coal in pul- exceptionally able engineers from his own or-
verized form include the following: (1)Coal is ganization, the public-utility industry, equip-
widely available for combustion purposes. (2) ment suppliers, and the U.S. Bureau of Mines.
Burning gas appears to be a simpler process Anderson's pioneering efforts resulted in
than consumption of large pieces of coal. (3) If pulverized-coal installations in the existing
coal can be finely divided and burned like a Oneida Street Station and the bold new concept
gas, it becomes an even more attractive fuel, of Lake~ide.~
promising greater boiler efficiency and sim- Although American research in this field
plicity of combustion. stems from the establishment of the U.S.
In the U.S., the rapid increase i n oil prices in Bureau of Mines in 1910 with its extensive pro-
the 1890's was the principal incentive for de- gram of boiler and equipment testing,' there
veloping the use of pulverized coal for firing was also earlier work in this country and
cement kilns-the first industrial application abroad on the inflammability of dust clouds
to achieve outstanding commercial success. causing explosions in coal mines. Empirical
E. H. Hurry-and H. J. Seaman of the Atlas Port- progress in the art of pulverized-coal firing
land Cement Company began a series of exper- linked these two areas of research, and brought '
COMBDEN
Pulverlzen and Pulverized-Coal Systems

forth a series of reports and investigations rang- coal pulverizers which are different.
ing from power-plant tests to studies of particle The energy that is required to effect pulveri-
flow and the thermodynamics of combustion. zation is dissipated in a number of ways. It can-
Two outstanding test reports stand as en- not be accounted for in the specific manner
gineering classics. Based on experimental which is applicable to a boiler or power-plant
work at the Oneida Street and Lakeside Sta- heat balance. For this reason, both pulverizer
tions, these reports contain important basic design and application have retained many of
information on pulverized-coal firing and the elements of an engineering art.
establish a pattern for subsequent research,
including many of the activities of the ASME PULVERIZING PROPERTIES
Furnace Performance Factors C~mmittee.~ OF COAL
Studies on velocities and characteristics of
pulverized-coal particles were reported by To predict pulverizer performance on a spe-
E. Audibert9 and John Blizard,lo who a few cific coal with some degree of accuracy, the
years earlier had published a comprehensive ease with which the coal can be pulverized
study of the state of the pulverized-coal art.ll must be known.
Research linking studies of inflammability of GRlNDABlLlTY.
coal-mine dust to desired combustion prop-
erties appears in an article by Henri Ver- A grindability index has been developed to
dinne.12 W. Nusselt published results of measure the ease of pulverization. Unlike
research on coal-particle ignition times in moisture, ash, or heating value, this index is
1924,13and P. Rosin reported on studies of heat not an inherent property of coal. Rather, it rep-
liberation based on thermodynamic data in resents the relative ease of grinding coal when
1925.14The first of a series of papers on boiler tested in a particular type of apparatus. The
heat-transfer studies at Yale University by W. J. consistency of grindability test results permits
Wohlenberg and his colleagues was also pub- the pulverizer manufacturer to apply the find-
lished by ASME in 1925.15 ings to a particular size and, to a lesser degree,
Despite the extensive theoretical studies that type of pulverizer.
were made in the 1920's, much of the progress Grindability should not be confused with the
was achieved on an empirical basis of trial and hardness of coal. (See also Tables IV and V and
error with boiler installations of ever-increas- related text.) The same coal may have a range of
ing size. This was particularly true in the de- grindabilities depending on other constituents
velopment of pulverizers, where the theory of in the coal. Fig. 1gives typical curves for North
the underlying principles had not advanced Dakota lignites and shows the variation in
very rapidly. Even today, the laws for crushing Hardgrove grindability as the moisture content
materials are subject to much dispute. changes. Typically, anthracites and some lig-
Rittinger's law of crushing dates back to a nites have at least one point where their grind-
book published in Germany in 1867. It states abilities are very close. Anthracite, however, is
that the work required to produce material of a a very hard coal whereas lignite is soft, yet both
given size from a larger size is proportional to are difficult to grind.
the new surface produced. This expression Pulverizing a small air-dried sample of
finds more general acceptance than Kick's law, properly sized coal in a miniature mill deter-
which was first published in 1885 and which mines its grindability. Results may then be
states that the energy required to effect crush- converted into a grindability-index factor
ing or pulverizing is proportional to the vol- which, with appropriate correction curves, can
ume reduction of the particle. While Rittinger's be used to interpret mill capacity.
law is a closer approximation, neither of these The Hardgrove method was developed to
laws can be used for comparing efficiencies of measure the quantity of new material that will
COMDumON
Pulverlzom and Pulverized-CoalSystems

pass a 200-mesh sieve. The apparatus for this Frequently, too much emphasis is placed on
method, shown in Fig. 2, is extremely simple. A grindability while other factors affecting mill
50-gram sample of air-dried coal, sized to less capacity, such as moisture, are almost entirely
than 16 and greater than 30 mesh, is placed in overlooked.Pulverizer capacity is proportional
the mortar of the test machine along with eight to the grindability index of the coal, but correc-
1-in.-diameter steel balls. A weighted upper tions must also be made for fineness of product
race is placed on the ball and coal charge, and is and moisture of the raw feed.
turned 60 revolutions. The sample then is re-
MOISTURE
moved and screened.
The quantity passing the 200-mesh sieve is Usually a reference to moisture in coal per-
used in the preparation of a calibration chart, tains to the total moisture content. This is
from which the grindability of the coal sample comprised of what is commonly termed equi-
is determined in accordance with ASTM Stan- librium moisture and surface or free moisture.
dards D 409, Grindability of Coal by the Hard- Equilibrium moisture varies with coal type or
grove-Machine Method. Four coal samples. rank and mine location, and would be more ac-
obtained from ASTM, ~tanda~dized especially curately called "bed" or "seam" moisture. In
for this purpose and representing grindability reality, surface moisture is the difference be-
indices of 40,60,80, and 100, are used for cali- tween total moisture and bed moisture.
bration of each grindability machine and Surface moisture adversely affects both pul-
associated apparatus, before the equipment is verizer performance and the combustion
used to test coals. process. The surface moisture produces ag-
glomeration of the fines in the pulverizing
zone, and reduces pulverizer drying capacity
because of the inability to remove the fines effi-
Moisture Range ciently and as quickly as they are produced.
in Which
Pulverlzlng Agglomeration of fines has the same effect as
Is Done coarse coal during the combustion process, be-
90
cause the surface available for thk chemical
reaction is reduced. Since in-mill drying is the
80 accepted method of preparing coal for pul-
verized-fuel burning, sufficient hot air at
'
u
70 adequate temperature is necessary in the mill-
-
c

f 60
m
P Revolution Count
3 50
40

30
0 10 20 30 40 50
O/o Moisture Content
- . -
Fig. 1. Variation of grindability index with moisture
content, North Dakota lignites (average of standard
and corrected values) Fig. 2. Hardgrove grindability machine
COMBUSTION
Pulverizers and Pulverized-CoalSystems

ing system. Curves such as those shown in differences between a commercial pulverizer
Figs. 3 and 4 indicate the air temperature re- and a grindability test machine which, with no
quired to dry coal of varied total moistures and provision for continuous removal of fines, is of
coal-air mixtures. the batch type rather than the continuous type.
The achieving of rated pulverizer capacity The crushing pressure of the test equipment is
depends upon having sufficient heated air also considerably less. As a result, some of its
available to dry the coal. If there is a deficiency energy is dissipated in deforming the coal parti-
of hot air, the mill output will be limited to the cles without breaking them.
"drying capacity" and not the "grinding ca- Although the test equipment does not indi-
pacity." Thus, it may be possible to obtain more cate a direct proportion of capability between
capacity with a relatively dry coal of lower hard and soft materials, the value of these tests
grindability than with a high-moisture coal of is not reduced. Correction factors developed
higher grindability. , by pulverizer manufacturers on commercial
equipment provide for overcoming these dis-
RELATION OF PULVERIZER CAPACITY crepancies. Fig. 5 gives correction curves for
TO GRINDABILITY
variations in fineness, .grindability, and mois-
As stated previously, mill capacity is not ture. As a rule of thumb, for every point the
directly proportional to grindability. Thus, if grindability index of a particular coal changes,
the actual capacity of a pulverizer with 50 there will be a corresponding change of 1 Y 3
grindability is 10,000 lb per hr, then with 100 percent in pulverizer capacity. Similarly, for
grindability it will be about 17,000 lb per hr, every percentage point of change in fineness
and not 20,000 lb per hr. This is because of the from the basic design point of a pulverizer,

180F Leaving M~xtureTemperature


1 170F Leaving Mixture Temperature
I

200 I I I
1 2 3 4 5
Lbs of Air Leaving Mill/Lb of Coal
I
I
Lbs of Air Leaving Mill/Lb of Coal
I
I
Fig.4 Temperature of air to mill, midwest-U.S.
Fig.3 Temperature of air to mill, eastern U.S. coals coals
COIBUSPION
PuhrIzerr and Pulverized-Coal Systems

there will be a corresponding change of 1% ceived to be the moisture level that exists in the
percent in capacity. grinding zone. Thus grindability vs. moisture
indices above the equilibrium level are of little
VARIATION OF LIGNITE GRINDABILITY
WITH MOISTURE
interest. Hardgrove indices therefore have
meaning to the pulverizer designer only
The Bureau of Mines at Grand Forks, North below the equilibrium-moisture level and in
Dakota, and others have reported the grindabil- the general range of moisture contents between
ity of lignites at various moistures, and the re- 10 and 25 percent.
sults show a wide variation, as in Fig. 1. Some The actual choice of the grindability index
feel that such curves are of little value because for pulverizer design capacity requires con-
it seems impossible to select the proper index sideration of total moisture, equilibrium (bed)
from them; others feel that they do have moisture, and the selected hot-air temperature.
significance. With theincreased use of lignites,
RELATIONSHIPOF COAL RANK
solution of this problem is important. TO REQUIRED FINENESS
In setting up the present ASTM code for
grindability, the test specifies use of an air- Successful pulverized-coal firing depends
dried sample. In the C-E bowl mill, all of the on recognizing differences in coals and on
surface moisture and some of the equilibrium making whatever modifications are necessary
moisture are evaporated during pulverization to provide the optimum conditions for efficient
with a hot-air sweep. The moisture content of combustion. Experience over the years has es-

*
the pulverized product leaving the mill is con- tablished that a relationship exists between

Low- and Medium-Volatile Bit.,


and Hiah-Volatile A Bit.- r High-Volatile B and C Bit. (Midwestern US.) Coals
astern
Coals 10O0/0 Capacity Is at
55 Grindability and
70% Through 200 Mesh

Coal

% Base Mill Capacity

Fig. 5. Mill correction factors for grindability, fineness, coal type, and moisture-
bituminouscoals with preheated air
COMBUSTION
Pulverizers and Pulverlnd-Coal System

rank of bituminous coals and degree of fineness on ignition temperature and particle burnout.
required for successful operation. - - Because lower flammability temperatures are
To insure complete combustion within the experienced primarily with lignitic and sub-
furnace confines for minimalcarbon loss, high- bituminous coals, it is reasonable to ask what
rank coals must be pulverized to a finer size property is common to lower rank coals. Ex-
than coals of lower rank. Although in part de- clusive of heating value, the most obvious
pendent on the type of firing system used, difference between the two groups is that
the approximate limits within the following property known as "agglomerating char-
ranges-have been established through operat- acter"-subbituminous coals and lignites do
ing experience. not agglomerate. As applied to coals, agglom
eration is the property of particles fusing into a
Passing Retained on cokelike mass or bonding together into a firm
Coal ZOO Mesh SO Mesh
Rank (741) (297~) cake when the particles are heated to tempera-
Wt% Wt% tures of 10QOFor above.
While the determinations of both volatile
Subbituminous C coal
and Lignite 60-70 2.0 matter and heating value are well defined,
tests for establishing the agglomerating char-
High-Vol. Bit. C, acter of coals are less commonly known.
Subbituminous A and B 65-72 2.0 ASTM Standards D 388, Specifications for
Classification of Coals by Rank, describes
Low and Medium-Vol.
Bituminous: agglomerating character as: "The test carried
High-Vol. Bit. A and B 70-75 2.0 out by the examination of the residue in the
platinum crucible incidental to the volatile-
When firing certain coals in the low-volatile matter determination. Coals which in the vol-
group in small pulverized-coal furnaces, the atile-matter determination produce either
fineness percentage may be increased to as an agglomerate button that will support a
high as 80 p e r ~ e n to
t insure adequate burnout 500-g weight without pulverizing, or a button
of the carbon content. showing swelling of cell structure, shall be
SPECIFICATIONS FOR CLASSIFYING COALS
considered agglomerating from the standpoint
of classification."
Table I lists the specifications as set by Since the agglomerating property of coals is
ASTM for classifying coal by rank. Rank clas- the result of particles transforming into a plas-
sifications are based on varying combinations tic or semiliquid state when heated, it reflects
of volatile-matter content, heating value, and a change in the surface area of the particle.
agglomerating properties. This surface change is manifested by a trans-
After the predrying step is accomplished in formation of the particle from an angular, ir-
the pulverizing operation, the low-rank sub- regular shape into a spherical or sphere-like
bituminous coals and lignites manifest a particle. Also, the surface character of the par-
higher degree of reactivity than do the higher ticle changes from a porous, irregular, absorp-
rank bituminous coals. Recent investigations tive surface to a glasslike nonporous surface.
confirm that this increased reactivity results Thus, with the application of heat, agglom-
primarily from the lack of agglomerating erating coals tend to develop a nonporous sur-
properties and increased O2 content.16 Data face, while that of nonagglomerating coals
from these investigations are summarized in becomes even more porous with pyrolysis.
Table 11, Coal Properties. This explanation indicates why agglomerating
A comparison of flammability indices with coals require a correspondingly finer particle
volatile matter and heating value suggests that size to maintain an equivalent surface area for
factors other than these have a great influence efficient, rapid ignition and burnout.
colarusn0.y
Pukerfzenand PuiverlzedCoal Systems

- - - - --- - - -

Table I.Classificationof Coals by Ranka


-
Fixed Carbon Volatile Matter Calorific Value Limits,
Limits, % Limits, % Btunb (Moist,
(Dry,Mineral- (Dry,Mineral- MineraEMatter-
' Matter-Free Basis) Matter-Free Basis) Free Basis)
Class and Group Agglomerating
Character
Equal or Less Equal or Less Equal or Less
Greater Than Greater Than Greater Than
Than Than Than

I. Anthracitic
... ... ... ...

1
1. Meta-anthracite 98 2
nonagglom-
2. Anthracite 92 98 2 8 ... ... erating
3. Semianthracite' 86 92 8 14 ... ...
11. Bituminous

I,
1. Low-volatile
bituminous coal 78 86 14 22 ... ...
2. Medium volatile
bituminous coal 69 78 22 31 ... ...
3. High-volatile
A bituminous coal ... 69 31 ... l4,00Od ... commonly
agglomeratingr
4. High-volatile
B bituminous coal ... ... ... ... 13,000d 14,000
5. High-volatile
C bituminous coal ... ... ... ... 11,500 13,000
10,500 11,500 agglomerating
111. Subbituminous

i
I. Subbituminous
A coal ... ... ... ... 10,500 11,500
2. Subbituminous
B coal ... ... ... ... 9,500 10,500
3. Subbituminous nonagglom-
C coal ... ... ... ... 8,300 9,500 erating
IV. Lignitic
1. LigniteA ... ... ... .,. 6,300 8,300
2. LigniteB ... ... ... ... ... 6,300
"This classification does not include a few coals, principally nonbanded variet~es,~vhichhave unusual physical and chemical properties and
which come within the limits of fixed carbon or calorificvalue of the high-volatile bituminous and subbituminous ranks. All of these coals either
contain less than 48% dry, mineral-matter-free fixed carbon or have more than 15.500 moist, mineral-matter-free Bntish thermal unlts per
pound.
"Moist refers to coal containing its natural inherent moisture but not including visible water on thesurface of the coal.
If agglomerating, classify in low-volatile group of the bituminous class.
"Coals having 69% or more fixed carbon on the dry, mineral-matter-free basis shall be classified according to fixed carbon, regardless of calorific
value.
'It is recognized that there may be nonagglomerating varieties in these groups of the bituminous class, and there are notable exceptions in
high-volatilec bituminous group.

Reprinted from ASTMStondords D 388, Classification of Coals by Rank.


COMBUSTION
Puhrizers and Puhrerfiud-CoalSystems

In addition to the correlation of agglomerat- appreciable quantity of extremely fine particles


ing properties with coal reactivity, an equally to insure rapid ignition. Conversely, to obtain
strong correlation exists between the ulti- maximum combustion efficiency, a minimum
mate-analysis oxygen level of coals and their amount of coarse particles in this same fuel-air
response to reactivity as reflected in the flam- mixture is desirable. The former condition is
mability temperatures. Data in Table I1 show usually expressed as percentage through a
ranges in oxygen from 4.8 to 14.8 percent for 200-mesh screen (74 microns), while the latter
agglomerating coals, moisture- and ash-free is designated as percentage retained on a 50-
(MAF), and from 18.7 to 26.6 percent MAF for mesh screen (297 microns).
the lower rank coals that are nonagglomerat- The number of openings per linear inch des-
ing. Seemingly, the higher the inherent or or- ignates the mesh of a screen. Thus, a 200-mesh
ganically bound oxygen content of the coal, the screen has 200 openings to the inch or 40,000
more reactive the coal. These data do not con- per square inch. The diameter of the wire used
flict with the observed correlation with in making the screen governs the size of the
agglomerating character:.In fact, deliberately openings. The U.S. Standard and W. S. Tyler
varying degrees of oxidation temper or destroy are the most common screen sieves. The mesh
the agglomerating properties of caking coals. and opening of these and other international
Apparently, the breaking point between ag- screens are shown in Table I11 and Fig. 6.
glomerating and nonagglomerating coals is a CLASSIFICATIONAND SIZE CONSIST
14-15 percent oxygen level, MAF.17 In some reactions, such as setting of cement,
STANDARDS FOR MEASURING FINENESS surface area is of extreme importance. In the
When burning solid fuels in suspension, it is combustion of pulverized coal, however, while
essential that the fuel-air mixture contain an it is important to have a proper percentage of

Table 11. Coal Properties


Bituminous Subbituminous Lignite
High Volatile
Low Medium
Volatile Volatile A B C A B C A

Agglomerating Non Non Non Non


character %
4. 4%. Agg. Agg. * 41%. Agg. Agg. Agg.
Proximate, %
Moisture (seam) 2.0 2.0 4.0 7.0 10.0 14.0 19.0 25.0 40.0
Volatile matter, VM 21.1 32.3 38.4 33.8 35.9 35.3 34.5 25.8 25.9
Fixed carbon, FC 68.6 55.8 51.5 47.3 43.3 41.2 37.5 40.9 27.4
Ash 8.3 9.9 6.1 11.9 10.8 9.5 9.0 8.3 6.7
HHV,BNlb, As-fired 13,150 13,210 13,410 11,610 10,590 9,840 8,560 7,500 5,940
Flammability index, F 1,010 1,030 950 1,030 990 970 970 990 890
Ultimate (MAF), %
Hydrogen 5.0 5.5 5.6 4.6 5.5 5.4 5.1 5.6 4.3
Carbon 88.5 84.1 82.5 81.0 74.3 74.2 69.8 66.4 67.0
Sulfur 0.4 1.1 2.5 0.9 4.0 0.5 0.8 0.6 0.9
Nitrogen 1.3 1.7 1.5 1.3 1.4 1.2 1.1 1.3 1.2
Oxygen 4.8 7.6 7.9 12.2 14.8 18.7 23.2 26.1 26.6
* Agglomerating but noncaking
COmmnON
Pulverizem and Pulveriz&-Coal Systems
.-

fine particles having a large surface area, it is 99.5%-50 mesh


equally necessary to eliminate the oversize on 96.5% -100 mesh
the coarser screen. Despite the percentage less 80.0%-200 mesh
than 200 mesh (-200 mesh), as little as 3 to 5
This represents a surface area of approximately
percent greater than 50 mesh (+50 mesh) may
1500 sq cm per gram, with over 97 percent of
produce furnace slagging and increased com-
the surface in the -200 mesh portion.
bustible loss, even though combustion condi-
By overgrinding and poor classification it
tions are excellent for the finer coal. The small
amount of oversize represents very little addi- would be possible, on a commercial-sized mill,
tional surface if it is pulverized to all -50 mesh to have a sample of the following analysis:
and all +200 mesh. 95% -50 mesh
As an illustration, assume a typical screen 90% -100 mesh
analysis of a high-volatile bituminous coal sam- 80%-200 mesh
ple, pulverized to 80 percent -200 mesh:

Table 111. Comparison


of Sieve Openings
Mesh Inches mm
U.S. Standard Sieve

20 0.0331 0.84
30 0.0234 0.595
40 0.0165 0.420
50 * 0.0117 0.297

Mesh Inches mm .

* W. S. Tyler Sieve

400 0.0015 0.037


- I
_I -
'Institute Mining B Metallurgy
British Engineering Std. Association
?GermanIndustry Norm
I
"Commonly used screens in pulverized-coal practice for combus- $Association Franpa~sde Norm
tion purposes.
Fig. 6. Internationalscreen opening comparisons
COMBUSTION
Pulverizersand Pulverized-CoalSystems

This is not a satisfactory grind, because of the movement must be uniform. Samples must be
high percentage retained on the 50 mesh, even taken in both directions for the same period.
though the surface area is still 1500 sq c d g . Currently, the industry has further refined
In the pulverizing process, then, classifica- these sampling techniques for greater accu-
tion plays a major role in matching the particle racy. In this refinement,-th-epipe traverse with
size to the reactivity of the fuel. Both fine and the coal-sampling device is timed to obtain an
coarse particles must be controlled within lim- isokinetic coal sample. The method uses the
its by the use of mechanical classification tech- proportion of coal-pipe area to the sample-
niques. Careful attention, therefore, must be probe-opening area in conjunction with the
paid to both the design and the operation of the pulverized-fuel loading in the individual
classification system. transport pipe. Because pulverized fuel in a
transport pipe is not a homogeneous mixture,
SAMPLING PULVERIZED COAL
another sample taken at the same time at a dif-
It is apparent that product fineness has a con- ferent location in the same pipe may yield dif-
siderable bearing on pulverizer performance. ferent results.
Fineness samples should, therefore, be ana- With collection completed, the pulverized-
lyzed periodically. In a storage system, this coal samples from each mill are thoroughly
sample may be taken directly from the mill cy- mixed. Fifty grams of the sample is placed in
clone discharge. the top sieve of a nested stack of 50-mesh,
On a direct-fired system, obtaining the sam- 100-mesh, and 200-mesh sieves. The nest is
ple is more difficult because it must be taken then shaken either by hand or by a mechanical
from a flowing coal-air stream. A sampling de- shaking device until the procedure has sepa-
vice, consisting of a small cyclone collector, rated the coal particles by size. The results of
sample jar, and sampling nozzle with connect- the percentages of coal passing through the in-
ing hose, may be utilized. See Fig. 7. dividual screens plot as a straight line on a typ-
The sample is obtained by traversing the pipe ical sieve distribution chart. (See Fig.8.) ASTM
across its diameter, from two points in the same Standards D 197, Sampling and Fineness Test
plane and at 90" to each other. The entire pipe of Pulverized Coal and ASME PTC, 4.2, Coal
diameter must be traversed, and the rate of Pulverizers, give additional information on
recommended sampling techniques.
CLOSED-CIRCUIT GRINDING
Flexlble Hose Air Valve CompressedAir When a large piece of coal is reduced to a
number of. smaller ones by any method, a great
number of fine particles will be produced
simultaneously. Therefore, it is not possible for
a pulverizer to produce a product that will pass
a 50-mesh screen without also obtaining a large
percentage of material finer than 200 mesh.
Cyclone Collector
Thus, if a quantity of coal at one stage of pul-
verization contains 50-percent material that
Pulvenzed-Coal
Ptp~ngto Furnace will pass through a 50-mesh sieve, and if this
- 50-mesh material is removed from the grind-
ing zone, it will contain a smaller percentage of
-200-mesh material than if it had been per-
mitted to remain in the grinding zone until
Fig. 7 Pulverized-coal sampling device
the total quantity had been reduced to pass a
and aspirating fittings 50-mesh sieve.
COMBUSTION
Puiverizen and Pulverized-Coal Systems
--
As already noted, an abundance of fine parti- sand, and pyrites, commonly found in coal as
cles is necessary to insure prompt ignition of mined, are quite abrasive. These are the unde-
coal in suspension burning. Substantial energy sirable constituents that produce rapid and
consumption is required in the production of sometimes excessive wear in pulverizing ap-
this fine material. However, when grinding paratus. The economics of coal cleaning to re-
finer than necessary, power is wasted and the move such abrasive foreign materials depends
pulverizing equipment must be larger than ac- on many variables and must be determined for
tually required. Removal of the fines from the each individual application.
pulverizing zone as rapidly as they are pro- The resistance of a smooth plane surface to
duced and return of the oversize for regrinding abrasion is called its hardness. It is commonly
eliminates unnecessary production of fines recorded in terms of 10 minerals according to
and reduces energy requirements. Better prod- Mohs' scale of hardness, Table IV. There is no
uct sizing and increased capacity result from quantitative relation between these, the dia-
the removal of the fines, a process called mond being much greater in hardness above
closed-circuit grinding. The pulverizing sys- sapphire than sapphire is above talc. Hardness
tem component which accomplishes this size of selected common materials is shown in
control is known as the classifier. Table V; the relatively low hardness of pure
coal is compared to the abrasive impurities
ABRASION
usually found in the commercial product.
Pulverizing results in an eventual loss of
grinding-element material. Balls, rolls, rings,
races, and liners gradually erode and wear out COAL PREPARATION
as a result of abrasion and metal displacement Coal should be prepared properly for its safe,
in the grinding process. Thus, the power for economical, and efficient use in a pulverizing
grinding and the maintenance of the grinding system. Controllable continuity of flow to the
elements make up the major costs of the pul- pulverizer must be maintained. Organic for-
verizing operation. eign materials such as wood, cloth, or straw
In itself, "pure coal" is relatively nonabra- should be removed. Such materials'may collect
sive; however, such foreign materials as slate, in the milling system and become a fire hazard,
or they may impair material or airflow patterns
in the mill. Although many mills are designed
to reject, or are not adversely affected by, small
inorganic or metallic materials, a magnetic
separator should be installed in the raw-coal
conveyor system to remove larger metallic ob-
jects. If this is not done, these objects may dam-
age the pulverizer coal feeder or obstruct the
coal flow.
The raw coal should be crushed to a size that
will promote a uniform flow rate to the mill by
the feeder. Favorable size consist will mini-
mize segregation of coarse and fine fractions in
the bunker, and result in a more uniform rate of
feed to various pulverizers being supplied from
a given bunker. When mixed with relatively

L
U.S. Standard Sieve Designation
I
I
dry lump coal, fine coal with high surface
moisture accentuates the segregation problem
Fig. 8. Typical fineness sample results in bunkers. Crushing by size-reduction of the
COMBUSTION
Pulverizers and Pulverized-Coal Systems

dry lumps exposes additional dry surfaces for liners or spaced grate bars in the bottom of the
the adsorption of moisture from the wet fines, casing. The degree of size reduction depends
thereby producing a more uniform size and on hammer type, speed, wear, and bar spacing.
moisture distribution in the raw-coal mass. The latter is usually somewhat greater than the
Most commonly, direct-firing of pulverized desired coal size. These crushers produce a uni-
coal is the method used for steam generation. In form coal sizing and break up pieces of wood
this application, an uninterrupted and uni- and foreign material with the exception of
formly controllable supply of pulverized coal metallic objects. Foreign material that is too
to the furnace is an essential requisite. A steady hard to crush is caught in pockets.
and continuous flow of raw coal to the pul- Roll crushers have been used but are not en-
verizer will insure this. tirely satisfactory because of their inability to
An ideal feed is one that is closely sized and deliver a uniformly sized product. Probably the
double-screened; e.g..3/-1in. x '14 in. Coal of this most satisfactory crusher for large capacities is
size will permit excess water to drain off; it will the Bradford breaker. This design, Fig. 9, con-
flow freely from bunkers and can be fed uni- sists of a large-diameter,-slowly revolving (ap-
formly. However, such favorable sizing can be proximately 20 rpm) cylinder of perforated
obtained only at a considerable price premium steel plates, the size of the perforations deter-
and this usually precludes its use. In most mining the final coal sizing. In diameter, these
cases, power plants will receive coals classified openings are usually 1% in. to 11/2 in. The
as run-of-mine or screenings with lumps; breaking action on the coal is accomplished as
therefore, crushing equipment must be in- follows: the coal is fed in at one end of the cyl-
stalled to provide uniform raw-feed sizing. inder and carried upward on projecting vanes
Generally coal-feed sizing up to 2 in., as sieved or shelves. As the cylinder rotates, the coal cas-
through a round screen, is permissible with cades off these shelves and breaks as it strikes
large pulverizers. the perforated plate. As the coal drops a rela-
tively short distance, coal crushing occurs with
COAL CRUSHERS the production of very few fines. Coal broken to
Although there are numerous types of the screen size passes through the perforations
crushers commercially available, the type to a hopper below. Rocks, wood, slate, tramp
generally used for smaller capacities is the iron, and other foreign material are rejected.
swing-hammer type. This crusher has proved This breaker produces a relatively uniform
satisfactory for overall use and has demon- product and uses very little power.
strated reliability and economy. The swing-
hammer crusher consists of a casing enclosing Table V. Common Materials
a rotor to which are attached pivoted hammers
or rings. Coal is fed through a suitable opening
and Their Mohs' Hardness
in the top of the casing and crushing is effected Coal
by impact of the revolving hammers or rings Slate
directly on, or by throwing the coal against, the Mica
Pyrite
Table IV. Mohs' Scale of Hardness Granite
Marble
1-Talc 6-Feldspar
Soapstone
2-Gypsum 7-Quartz
3-Calcspar 8-Topaz Kaolin clay
4-Fluorspar 9-Sapphire Iron ore
5-Apatite 10-Diamond Carborundum
C0YI)USTION
htverlzen md Pulverized-CoalSystems
-
Fig. 9. Bradford breaker COAL FEEDERS
A coal feeder is a device that supplies the
pulverizer with an uninterrupted flow of raw
coal to meet system requirements. This is espe-
cially important in a direct-fired system. There
are several types, including the belt feeder and
the overshot roll feeder.
THE BELT FEEDER

The belt feeder uses an endless belt running


on two separated rollers receiving coal from
above at one end and discharging it at the other.
Varying the speed of the driving roll controls
the feed rate. A leveling plate fixes the depth of
the coal bed on the belt.
The belt feeder can be used in either a vol-
umetric or gravimetric type of application (see
Fig. 10). The gravimetric type has gained wide
popularity in the industry for accurately meas-
uring the quantity of coal delivered to each

Coal Inlet

Demand Digital Totalizer


S~gnal Scale Control
Feedback Signal

Fig. 10. Schematic of belt-type gravimetric coal feeder.


COMBUSTION
Pulverizem and Pulverized-Coal Systems

individual pulverizer. ~ e n e r a l l ~ , - t are


h e ~ap-
plied to steam generators having combus- METHODS OF PULVERIZING
tion-control systems requiring individual coal AND CONVEYING COAL
metering to the fuel burners.
There are two accepted methods of continu- Early coal-pulverizing installations received
ously weighing the coal on the feeder belt. One undried coal and utilized ambient air in the
method uses a series of levers and balance mill system. Because no heat was added to the
weights; the other, a solid-state load cell across system, the coal feed was limited to that of very
a weigh span on the belt. Both are very accurate low moisture content; therefore, maximum pul-
mechanisms and both are well accepted by verizer capabilities were not realized. Subse-
utilities. This same belt feeder design can also quently, external coal dryers were added to the
be used for volumetric measurement. system. Because of the lack of cleanliness, high
initial cost, fire hazard, and space require-
THE OVERSHOT FEEDER, ments, these dryers were replaced with the now
The oyershot roll feeder, Fig. 11, has a universallyaccepted in-mill drying.
multi-bladed rotor which turns about a fixed, Three methods of supplying and firing pul-
hollow, cylindrical core. This core has an open- verized coal have been developed: the storage or
ing to the feeder discharge and is provided with indirect system, the direct-fired system, and
heated air to minimize wet-coal accumulation the semidirect system. These methods differ on
on surfaces and to aid in coal drying. A hinged, the basis of their drying, feeding, and transport
spring-loaded leveling gate mounted over the characteristics.
rotor limits the discharge from the rotor TH E STORAGE (INDIRECT) SYSTEM
pockets. This gate permits the passage of over-
size foreign material. In a storage system, Fig. 1 2 , coal is pulver-
Feeders of this type may be separately ized and conveyed by air or gas to a suitable col-
mounted, or they may be integrally attached to lector where the carrying medium is separated
the side of a pulverizer. from the coal which is then transferred to a
The roll feeder and the belt feeder, by virtue storage bin. The hot air or flue gas introduced
of their designs may be considered highly effi- into the mill inlet provides for system drying
cient volumetric feeding devices. requirements and is vented to rid the system of .

Cyclone Collector Vent To


Collector Atmosphere

lving Blade

Hot-Air Slot

Hot Air or Flue Gas

Fig. 11. Overshot roll feeder Fig. 12 Storage (indirect) pulverizing system
--
COYBU~OIY
Pulyerinn and Pulverized-CoalSystems
--

stability of ignition, it is necessary, when using


hot gas, to draw it from a point of low CO, con-
centration and high temperature. This prevents
the use of flue gas for drying in direct-firing.
Fig. 14 illustrates a schematic arrangement
of the primary-air system for a pulverizer using
a LjungstromBtrisector air heater. As the name
implies, this air heater has three sections: flue
gas, primary air (the air that dries and conveys
the coal to the furnace) and secondary air (the
Pulverizer balance of the air that goes to the furnace). The
primary-air section is located between the
Fig. 73 Direct-fired pulverizing system .
openings for the secondary air and the flue gas
(Fig. 15). With this design, a higher primary-air
moist~re'eva~orated from the fuel. From the temperature can be obtained. If there is a large
storage bin, the pulverized coal is fed to the variation in primary airflow, there is relatively
furnace as required. little effect on heat recovery, because heat not
recovered in the primary section will be picked
THE DIRECT-FIRED SYSTEM up subsequently in the secondary section.
In a direct-fired system, Fig.13, coal is pul- THE SEMIDIRECT SYSTEM
verized and transported with air, or air slightly
diluted with gas, directly to the furnace where In a semidirect system, Fig. 16, a cyclone col-
the fuel is consumed. Hot air or diluted furnace lector located between the pulverizer and fur-
gas supplied to the pulverizer furnishes the nace separates the conveying medium from the
heat for drying the coal and transporting the coal. The coal is fed directly from the cyclone to
pulverized fuel to the furnace. Known as pri- the furnace in a primary-air stream which is in-
mary air, this air is a portion of the combustion dependent of the milling system. The drying
air. As a reduction in oxygen concentration in medium, therefore, can be the samelasin a stor-
this primary-air stream affects the rapidity and age or bin system.

Pulverizer - Fans Fans

Fig. 14. Primary-air system of balanced-draft furnace. Air pressures shown are illustrative only.
COMBUSTION
Pulverizers and Pulverized-CorlSy8toms

SOURCE OF HEATED AIR design depends on the extent of circulating


The best source of hot air for mill drying is load within the mill, the ability to-rapidly mix
either a regenerative or recuperative air heater the dry classifier returns with incoming raw,
using combustion gas as the source of heat. wet, coal feed, and the air weight and air tem-
Those used in connection with large boiler in- perature which the design will tolerate. C-E
stallations usually provide sufficiently high pulverizers are designed to operate satisfac-
temperature for almost any fuel moisture torily with inlet air tempertures up to 750F.
condition. On small installations, where the High-rank bituminous coals have a relatively
moisture in the coal is not high, steam air dense structure and appear dry only when con-
heaters may dry the coal. For higher moisture taining less than 2 or 3 percent total moisture.
conditions a furnace-gas supplement may be The inherent moisture of these fuels varies
necessary. Direct-fired air heaters, properly in- from 1 to 2 percent. Extremely low-rank fuels,
terlocked and protected, may also be used to such as lignite, are of a relatively porous or cel-
supplement air-heating requirements. lular structure and contain inherent moisture
All the moisture contained in coal must be of from 15 to 35 percent. These same fuels with
evaporated before ignition can take place. For 3 percent surface moisture (18 to 38 percent
rapid ignition, therefore, surface moisture must total moisture) still appear dry. For both the
be removed before the fuel is injected into the pulverizing and ignition processes, it is neces-
furnace. This same drying process facilitates sary to reduce the total moisture contained in
pulverization. The type of fuel and its surface the fuel to the inherent moisture level.
moisture govern mill-drying requirements. If a particular pulverizer design requires low
The drying capability of a given pulverizer airflow for fineness maintenance, wet coal
cannot be utilized without a considerable re-
duction in mill capacity. The design should
permit high-temperature incoming air in suffi-
cient volume to maintain a condition of relative
humidity below saturation at the mill output
temperature. A pulverizer designed for a larger
volume of low-temperature inlet air for normal
moisture fuel will require the admission of

Exhauster
Hot Air Fan

Fig. 15. Ljungstrom" trisector air heater Fig. 16 Semidirect pulverizing system
--
COWUSTION
PuIYerizenand PulveHzed-Coal Systems

Table VI. Allowable Mill Outlet Temperatures, O F


System Storage Direct Semidirect

High-rank, high-volatile bituminous


Low-rank, high-volatile bituminous
High-rank, low-volatile bituminous
'Lignite
Anthracite
Petroleum coke (delayed)
Petroleum coke (fluid]

*160DF~ermissiblewith inert atmosphere blanketing of storage bin and lowaxygen-concentration conveying medium.

large quantities of cold tempering air when method utilizes a fan behind the pulverizer,
grinding dry coals. while the other has a fan ahead of it. The former
The type of fuel and the kind of system being is a suction system and the fan handles coal-
used will determine the mill outlet tempera- dust laden air, while the latter is a pressure sys-
ture. As Table VI indicates, outlet temperatures tem and the fan handles relatively clean air.
for storage-systems mills are lower than for With direct firing, the exhauster or blower
direct or semidirect firing, because most coals volume requirement will depend upon the
will not store safely at the temperatures used in pulverizer size, and is usually fixed by the base
direct firing. Storage-bin fires caused by spon- capacity of that pulverizer. The pressure or
taneous combustion of the fuel may result from total head requirement is a function of the pul-
inadequate mill outlet temperature control. verizer and classifier resistance and the fuel
These may be inhibited by maintaining an distributing system and burner resistances.
oxygen-deficient atmosphere, such as flue-gas These resistances are in turn affected by the
inerting, over the bin coal level. Oxygen limits system design, the required fuel-line velocities
for various fuels are shown in NFPA 69, "Ex- and density of the mixture being conveyed.
plosion Prevention Systems". In a storage system, the fan is located behind
Mill capacity is based on coal input, and out- the dust collector and handles only a very small
put on a given coal on a dry basis will decrease quantity of extremely fine (-200 mesh) dust
with increasing moisture content. Thus, in se- at a relatively constant temperature (approx-
lecting a mill size, if too much reduction of ca- imately 130F).These fans are, therefore, de-
pacity is experienced with high-moisture fuels, signed for high efficiencies and need not be
the mill can be too large under normal condi- designed for a head higher than their operating
tions of moisture or too small under excessive temperature requires.
moisture conditions.
INDIRECT COAL-STORAGE
PULVERIZING SYSTEMS
PULVERIZING AIR SYSTEMS Initial attempts at utilizing pulverized coal as a
All coal-pulverizing systems utilize air or utility fuel led to the development of the indirect-
gas for drying, classification and transport fired system (Fig. 12). In this system, a cyclone
purposes. Two methods are utilized for supply- collector separates the coal from the air used in
ing the air requirements and overcoming sys- the pulverizer for drying, classifying, and con-
tem resistance. In a direct-firing system, one veying. The pulverized coal is conveyed either
COMBUSTION
Pulverizers and Pulverized-Coal Systems

mechanically or pneumatically to storage hop- feeder should equal 1 ft for every 3 in. of
pers or bunkers. Mechanical, controllable feed- primary-air mill-inlet pressure. If the pri-
ers at the bunker outlets deliver the required mary-air-fan inlet pressure is 30 in., then the
quantity ofLcoal to the fuel lines. At or near coal-column height will be 10 ft.
these- feeders, the coal is reentrained in air There are three basic air conveyance systems
called "primary air" in the proper proportions used by C-E for direct firing: (1)the suction sys-
for transport to the furnace. tem in which an exhauster induces airflow
The indirect-fired pulverizing system is de- through the pulverizer and discharges the
scribed in greater detail in the previous edi- coal-air mixture under pressure to the furnace;
tion of this book. (2) the pressurized-exhauster system in which
the pulverizer is pressurized by the forced-
DIRECT-FIRING ARRANGEMENTS draft fan with both hot and ambient air and
Most direct-fired pulverized-coal systems discharges the coal-air mixture through an ex-
are for furnaces operated under suction (bal- hauster, acting as a booster fan, to the furnace
anced-draft). Fig. 1 7 shows an arrangement of (this system is used only in conjunction
equipment for a suction-type mill when ap- with pressurized furnaces); and (3)the cold pri-
plied to a furnace of this design; Fig. 14 shows mary-air system in which e primary-air fan
a pressure-type mill for a similar furnace. forces air through an air heater, ductwork, and
With a suction mill, the coal feeder dis- pulverizer and then forces the coal-air mixture
charges against a negative pressure, whereas in into the furnace.
the pressurized mill, the feeder discharges SUCTION SYSTEM
against a positive pressure of 18 to 2 1 in. WG. The suction system has a number of advan-
No coal feeder can act as a seal; thus, the head of tages. It is quite easy to keep the area around the
coal above the feeder inlet must be utilized to pulverizer clean. To control the airflow through
prevent backflow of the primary air. As a rule of '
the pulverizer a damper is placed in the con-
thumb, the height of the coal column above the stant-temperature coal-air mixture just prior to
the exhauster entrance. Control of the coal-air
mixture temperature is by a single hot-air
damper and a barometric damper through
which a flow of room air is induced by the suc-
tion in the pulverizer. With this control, the fan
is designed for a constant, low-temperature
mixture and has a low power consumption,
even though such material handling fans have
a relatively low efficiency of 55 to 60 percent.
The main disadvantage of the suction system
is the maintenance required on the exhauster.
On the other hand, by using proper design
techniques and wear-resistant materials, the
maintenance on an exhauster can be min-
imized. Exhauster maintenance costs are more
Mill Airflow 'Atmospheric From than offset by the power and capital savings
Regulator Pyrites Hopper F.D. Fan of the system; this justifies the continued use
of the suction system on smaller units.
PRESSURIZEDEXHAUSTER SYSTEM

Fig. 17. Balanced-draft furnace with suction mill. To obtain sufficient pressure for firing a
Air pressures shown are illustrativeonly. pressurized furnace, the pressurized exhauster
COMBUSTION
Pulverizersand Pulverized-Coal Systems

system was developed; there are a number of a function of the number of pulverizers in oper-
these systems in operation. This system retains ation. This permits the use of a simple control
the advantages of the suction system in the de- for the airflow requirements. Because of possi-
sign of the fan for constant, low-temperature ble variations of load and coal moisture content
mixture and the relative ease of airflow control. between pulverizers, it is necessary to control
Two dampers, one in the hot-air duct to the mill not only the total airflow but the temperature of
and one in the cold-air duct to the mill, control the air to individual pulverizers. This is ac-
the amount of pulverizer airflow. This flow var- complished with a system similar to that out-
ies with, but is not proportional to, the amount lined under the pressurized exhauster system,
of fuel being fed to the pulverizer. Biasing the which uses a hot primary-air duct and a cold
hot- and cold-air dampers controls the tem- primary-air duct with a damper in each for each
perature of the mixture leaving the pulverizer. mill. The airflow requirement for a pulverizer
One advantage of the pressurized exhauster is met by operating both dampers, while con-
system is that the low pressures in the pul- trolling temperature by properly proportioning
verizers do not present as severe a problem of the flow between the hot- and cold-air ducts.
sealing the head of coal over the raw-fuel feeder When very wet coals are pulverized in the
as with pulverizers under direct blower pres- suction systems described, the exhauster
sure. The disadvantage of the system, as with supplies less air at the very time maximum
the suction system, is exhauster maintenance. airflow is required for maximum drying. In the
suction and pressurized systems with the
COLD PRIMARY-AIR SYSTEM exhauster located between the pulverizer and
In this system the primary-air fan handles the furnace, the high evaporated-water vapor
only ambient air. The fan is located ahead of the content in the coal-air mixture will reduce the
air preheater, with a separate primary-air sys- exhauster air-handling capacity. In the pres-
tem through the air heater. Although not as surized exhauster system only, this can be par-
simple as the other two systems, its chief ad- tially overcome if the forced-draft-fan head
vantage is in fan power and maintenance. As capability is adequate. These disadvantages
the fans handle cold air, they can be smaller, can be corrected by over-designing the fans,
run at higher speeds, and use highly efficient but this produces inefficiencies when the unit
airfoil blade shapes. Inlet vanes can control is operating with normal moisture coal. Con-
airflow and further add to fan efficiency. versely, the cold primary-air system may pro-
Some other advantages of this system are duce a higher capacity at any time it is needed.
that, with high-efficiency fans handling am- The cold primary-air system offers numerous
bient air, design for higher pressure differ- advantages. As compared with the other sys-
entials is possible and larger mills with longer tems, the total savings with this system. from
fuel-pipe runs are practical. Thus, mills may be elimination of exhauster maintenance and re-
located farther from the boiler. Because indi- duction in fan power, may be 35 to 40 percent of
vidual fans for each pulverizer are not neces- the cost per unit of coal pulverized. This
sary, the space requirements for the pulverizer operating saving is partially offset by the capi-
bays can be reduced. Morever, experience has tal charges for additional ductwork, dampers,
proven that metering airflow on the inlet-air and controls. With larger units and pulverizers,
side of the pulverizer is most desirable. With the use of the cold primary-air system becomes
the higher fan head available, the airflow can economically favorable.
be quite easily measured by installing aventuri
-or.other metering means.
- Even with fewer pulverizer fans, controlling By definition, the cold primary-air system
airflow to the various pulverizers is still rela- requires independent primary-air heating ac-
tively simple. The total primary air required is complished in the past by several different
COMBUSTION
Pulverlzem and Pulverized-Coal Systems

methods. Several systems have been installed


using a separate primary tubular air heater with PRINCIPAL TYPES
Ljungstrom@air heaters for secondary air, while OF PULVERIZERS
some have been installed using separate pri-
mary Ljungstroma air heaters. These systems are To effect the particle size reduction needed
expensive and become rather complicated in for proper combustion in pulverized-coal fir-
ductwork design. With the cold primary-air ing, machines known as pulverizers or mills
system, the trisector Ljungstroma air heater are used to grind or comminute the fuel. Grind-
shown schematically in Fig. 15 is now being ing mills use either one, two, or all three of the
used as a basic design. As the name implies, basic principles of particle size reduction,
the flow channels of this heater have been di- namely, impact, attrition, and crushing. With
vided into three sections, with the primary-air respect to speed, these machines may be clas-
section being located between the secondary- sified as low, medium and high. The four most
air and flue-gas sections. With this arrange- commonly used pulverizers are the ball tube,
ment, primary -air temperatures higher than the ring-roll or ball-race, the impact or hammer
that of secondary-air can be obtained. Further, mill, and the attrition type; their speed charac-
the efficiency of heat recovery is no! signifi- teristics are shown in Table VII.
cantly affected by variations in pulverizer hot- BALL-TUBE MILLS
air requirements, because the secondary air
recovers that heat which is not recovered by the A ball-tube mill (Fig. 18) is basically a hol-
primary air,sections. low horizontal cylinder, rotated on its axis,

Raw

I
I
Fig. 18. Arrangement of ball-tube mill
. -.
COMBUSTION
Pulverizers and Puhrized-Coal Systems
-
whose length is slightly less to somewhat During operation, the relatively large quan-
greater than its diameter. Heavy cast, wear- tity of pulverized coal in the grinding zone of a
resistant liners fit the inside of the cylindrical ball-tube mill acts as a storage reservoir from
shell which is filled to a little less than half which sudden increases in fuel demand are
with forged steel or cast alloy balls varying supplied. The power consumption of ball-tube
from 1 to 4 in. in diameter. Rotating slowly, 18 mills, kW per unit of coal pulverized, is very
to 35 rpm (about 20 rpm for an 8 ft diameter high, particularly at partial loads. Relatively
mill) the balls are carried about two thirds of large physically per unit of capacity, they re-
the way up the periphery and then continually quire considerable floor space. Because of their
cascaded towards the center of the cylinder. size and weight, the initial capital cost is quite
Coal is fed into the cylinder through hollow high. The presence of a high circulating load
trunnions and intermingles with the ball within the mill results in an overproduction of
charge. Pulverization which is accomplished fines within the mill charge. Using an adequate
through continual cascading of the mixtures external classifier permits the removal of the
results from (a)impact of the falling balls on the fine product from the grinding zone and re-
coal, (b) attrition as particles slide over each duces the production of extreme fines. The
other as well as over the liners and (c) crushing comparatively poor mixing of heated air with
as balls roll over each other and over the liners the partially pulverized material reduces the
with coal particles between them. Larger drying efficiency of this type of mill. High-
pieces of coal are broken by impact and the fine moisture coals produce a large reduction in
grinding is done by attrition and crushing as mill capacity.
the balls roll and slide within the charge. Ball-tube mills are not well suited to inter-
Hot airflow is passed through the mill to dry mittent operation as the large amount of heat
the coal and remove the fines from the pulveriz- stored in the coal and ball charge may produce
ing zone. In most designs used for firing boilers overheating and fires when the mill is idle. The
or industrial furnaces, an external classifier mass of this mill type makes it necessary to use
regulates the size or degree of fineness of the high-power, high-starting-torque motors. In
finished product. The oversize or rejects from addition, these mills are very noisy. Most in-
the classifier, sometimes called tailings, al- stallations require that insulated "dog houses"
ready dried in the pulverizing and classifying be erected over each mill for noise attenuation.
process, are returned to the grinding zone with Maintenance in the grinding zone of ball-
the raw coal. This type pulverizer is particu- tube mills is relatively easy to perform. Period-
larly susceptible to reductions in capacity from ically, a ball charge is added to the mil1 to make
surface moisture of the coal. Reducing the av- up for metal lost in the grinding process. It may
erage moisture content of the mixture is very take years to wear out the cast liners, but con-
important in maintaining a continuous flow of siderable downtime i s necessary for their re-
coal through the feed end. The recirculation of placement. Over the long run, maintenance
dried tailings, then, reduces the tendency for costs per unit of coal ground are about the same
wet coal to plug the feed end. as for ring-roll type pulverizers.
IMPACT MILLS
Table VII. Pulverizer Types An impact mill consists primarily of a series
Speed: Low Medium High
of hinged or fixed hammers revolving in an en-
closed chamber lined with cast wear-resistant
Type: Ball-Tube Ring-Roll or Impact or plates. Grinding results from a combination of
Mill Ball-Race Mill Hammer Mill hammer impact on the larger particles and at-
Attrition Mill trition of the smaller particles on each other
and across the grinding surfaces. An air system
COMBVSTION
Pulverlzen and Pulverized-Coal Systems

with the fan mounted either internally or ex- plus a very small amount of impact to obtain
ternally on the main shaft induces a flow size reduction of the coal. The grinding action
through the mill. An internal or external type of takes place between two surfaces, one rolling
classifier may be used. (See Figs. 24 and 25) over the other.-The rolling element may be
This class of mill is simple and compact, low either a ball or a-roll, while the member over
in cost and may be built in very small sizes. Its which it rolls may be either a race or a ring. The
ability to handle high inlet-air temperatures, ball diameter is generally from 20 to 35 percent
plus the return of dried classified rejects to the of the race diameter, which can be as large as
incoming raw feed, makes it an excellent dryer. loo1! If the element is a roll, as in the C-Ebowl
However, the high-speed design results in mill, its diameter may be from 50 to 60 percent
high maintenance and high power consump- of the ring diameter, which can be as much as
tion when grinding fine. Progressive wear on 110". Its face width, depending upon mill size,
the grinding elements, produces a rapid drop- will vary from 15 to 20 percent of ring diameter.
off in product fineness, and it is difficult if not When the rolling elements are balls, Fig. 19,
impossible to maintain fineness over the life of they ape confined between races. In the ma-
the wearing parts. Using an external classifier jority of designs, the lower race is the driven
permits maintenance of fineness, but only at rotary member, while the upper race is station-
the expense of a considerable reduction in ca- ary. Some designs also utilize a rotating upper
pacity as parts wear. The maximum capacity race. The required grinding pressure is ob-
for which such mills can be built is lower than tained by forcing the races together with either
most other types. heavy springs or pneumatic or hydraulic cyl-
AlTRlTlON MILLS
inders. Some additional grinding pressure is
obtained from centrifugal force of the rotating
No true attrition mill is used for coal pul- balls.
G verizing because of the high rate of wear on There are two general classes of mill that use
parts. A high-speed mill which uses consider- rollers as the rolling elements. In one, Fig. 20,
able attrition .grinding along with impact the roller assemblies are driven and the ring is
grinding is, however, used for direct firing of stationary, while in another, Fig. 21, the roller
pulverized coal. In this mill, the grinding ele- assembly is fixed and the ring rotates.
ments consist of pegs and lugs mounted on a Perhaps the most frequently used applica-
disc rotating in a chamber; the periphery of the tion of the first class is the C-ERaymondBroller
chamber is lined with wear-resistant plates and mill, used in storage systems. Grinding pres-
its walls contain fixed rows of lugs within sure is obtained from centrifugal force result-
which the rotating lugs mesh. The fan rotor is ing from rotation of these rolling elements.
mounted on the pulverizer shaft. Instead of an
external classifier, a simple shaft-mounted re-
jector type is used. This design utilizes wear-
resistant alloy lug and peg facings and casing
linings to reduce the wear effect on fineness
and extend the periods between parts replace-
ment. This mill type exhibits all the charac-
teristics of the impact mills. Grinding Bal
RING-ROLL AND BALL-RACE MILLS
Ring-roll and ball-race mills comprise the
largest number of pulverizers used for coal ~rivin~ in^- I

grinding. They are of medium speed and utilize


primarily crushing and attrition of particle Fig. 19. Diagram of ball-race mill
COMBUSTION
Pukerlsrs and Pulverized-Coal Systems

The other classification of ring-roll mills, mills are extremely quiet in operation. Fine-
namely those in which the ring rotates, consti- ness of the product is relatively uniform
tutes the largest number of mills used for grind- throughout the life of the grinding elements.
ing coal; they are manufactured by the major Several references have been made to the abil-
boiler companies. The C-E bowl mill is of this ity of the various types of pulverizing equip-
latter type. The vertical driving shaft of these ment to grind different coals economically and
mills operate between 20-70 rpm, with larger efficiently. This capability is a reflection of the
mills running at the slower speeds. grinding pressures available, the method of ap-
Generally, such mills are equipped with plication of this force, speed of moving ele-
self-contained or integral classifiers to regulate ments, abrasion, and power and size
the fineness of the finished product. In some limitations of the particular units. A list of ma-
cases, this device may be external to the mill it- terials capable of being commercially pulver-
self and is then termed an instream classifier. . ized by the mill types described could be
Primary-air fans or exhausters create a flow extended indefinitely; therefore, the scope of
of heated air through the mills. This heated air Table VIII covers combustible materials of pri-
dries the coal, removes it from the grinding mary concern in power generation.
zone, carries it through the classifying zone,
and conveys it to its point of use, whether this
is a direct-fired furnace or the dust collector of a C-E PULVERIZER DESIGN
storage system. In the following sections, C-E pulverizers
When this type of mill is provided with suffi- corresponding to the generic types are de-
cient air at a temperature to produce a satisfac- scribed. Their detailed design, constructionand
tory mill outlet temperature, it can handle very operational features, and fields of application
wet coals with only, a small reduction in ca- are given.
pacity. The high ratio of circulating load (clas-
sifier rejects returning to the grinding zone for
further size reduction) to output, with the re-
sulting rapid reductibn of average moisture
content, facilitates the grinding process. These Journal Assembly
mills require less power than any others.
Physically, these mills are compact and oc-
cupy a relatively small amount of floor space
per unit of capacity. Some designs of ring-roll -

Main
Vertical
.Shaft

I
1
rindin in^ Roll Assembly 1 I - -
Grinding ~ i n g

Fig. 20. Diagram of roller-typering-roll mill Fig.21 Diagram of bowl-type ring-roll pulverizer
journal assembly journal assembly
COMBUSTION
Pulverizers and PulverJzed-CoalSystems

C-E RAYMOND ROLLER MILL ing operated successfully. when, after World
The period between 1895, when the first pul- War I, pulverized coal gained a foothold in the
verizers were installed in a Pennsylvania ce- central-station industry, this machine was a
ment plant, and 1919, when a successful boiler fully developed and standardized pulverizer
installation wgs-made at Oneida Street Station specified for many pioneering installations.
in Milwaukee, was a testing time for this type of The early mills were built for a maximum ca-
equipment. Early during this period the C-E pacity of 6 tons per hour of 55 grindability coal
Raymond roller mill, Fig. 22, was developed to when grinding to a fineness of 65 percent -200
pulverize coal for storage systems serving mesh. By 1930. the maximum capability of this
metallurgical furnaces and cement kilns. By mill design had been increased to 25 tons per
1919, several hundred of these mills were be- hour. Nearly all used external dryers to predry

I I
Fig. 22 Sectional view, C-E Raymond roller mill
COMBUSTION
PvlverIzen and Pulverized-Coal Systems

the coal before use in the pulverizer. The larger capacities (Fig. 241, utilizing an integral
economic disadvantages of these dryers helped fan but external classifier. The other design
to bring about internal mill drying, now the ac- (Fig. 25) was for smaller outputs, in which the
cepted practice. However, the original feature grinding elements, classifying means, and fan
of air-separation and classification inherent in were all mounted on a common shaft rotating
the roller mill has become the accepted stan- at 1800 rpm. Both designs were provided with
dard of ring-roll pulverizer design. a mill-housing clearance space or tramp-iron
A typical grinding and drying system incor- pocket for accumulation and periodic removal
porating a roller mill is shown in Fig. 23. bf foreign material. The whizzer or rejector
C-E RAYMOND IMPACT MILLS blades for fineness control were first used on
these mills. These mills are excellent drying
The increase in possibilities for direct pulverizers because high-temperature air can
pulverized-coal firing resulted in the de- '
be utilized and there is very violent turbulence
velopment in 1923 of a series of C-E Raymond of the mlxture passing through the pulverizer.
impact mills with two basic designs: one for the They are best suited to soft, relatively nonabra-

Table VIII. Types of Pulverizersfor Various Materials


Ball- Impact and Ball Ring
Type of Material Tube Attrition Race Roll

Low-volatile anthracite
High-volatile anthracite
Coke breeze
Petroleum coke (fluid)
Petroleum coke (delayed)
Graphite
Low-volatile bituminous coal
Med-volatile bituminous coal
High-volatile A bituminous coal
High-volatile B bituminous coal
High-volatile C bituminous coal
Subbituminous 4 coal
Subbituminous B coal
Subbituminous C coal
Lignite
Lignite and coal char
Brown coal
Furfural residue
Sulfur
Gypsum
Phosphate rock
Limestone
Rice hulls
Grai* - -
Ores-hard
Ores-soft
COMBUSTION
P~lverlzerCi
and Pulverized-Coal Systems

Fig. 23 Equipment for a complete grinding Fig. 24 C-E Raymond impact mill with external
and drying system for C-E roller mill classifier and exhauster integrally mounted

Whiuer or Fineness '

Mill Drive
Shaft

"I

Fig. 25 C-E Raymond impact mill with hammers, classifier, and fan on common shaft
CObfBVSTION
Pulverizers and Pulverized-Coal Systems
-

sive coals and for use on small boilers and fur- trunnion in response to increasing coal feed,
naces. Life of grinding elements is short; the spring is compressed and the force for grind-
maintenance and mill power are quite high. ing is increased.
The partially pulverized coal passes over the
rim of the bowl and is entrained by the rising
C-EBOWL MILLS hot-air stream and is flash-dried. The pyrites
The positive-pressure type C-E HP ring-roll and tramp iron that enter the mill with the coal
bowl mill is shown in Fig. 26. It is a medium- follow the same path as the coal until they pass
speed type, similar in size and performance to over the rim of the bowl; being denser than coal,
the prior C-E "R" series mills. When fitted with they cannot be carried upward by the air stream
an exhauster (such that the pulverizer operates and fall into the millside. Once there, these re-
below atmospheric pressure), it is designated an jected materials are swept around by a set of
HPS or HPPS mill, a cross-sectional view of pivoted scrapers until they reach the tramp-iron
which is' given in Fig. 27. Table IX shows the opening. They then fall into a hopper external
type of mill used with different furnaces and air to the mill; this rejects hopper can be emptied
systems, for the two pressure regimes in which with the mill in service.
these mills can operate. The air-transported partially pulverized coal
enters the vane-wheel assembly, where initial
OPERATION OF THE HP PULVERIZER
size classification occurs, with the heaviest par-
When in operation, raw coal enters the center ticles falling back into the bowl. The balance of
of the pulverizer through a center feed pipe. It the coal and air stream passes up through the
falls onto a rotating bowl which has a replace- separator body until it reaches the classifier.
able wear surface composed of bull-ring seg- Here, the coal-air mixture begins to spin in a
ments. Centrifugal force causes the coal to move cyclonic path. Externally adjusted vanes control
outward from the center and under the three the amount of spin. Because of the differing
journal assemblies, where it is crushed by large mass of the particles and the amount of spin,
rolls. To prevent physical contact of the rolls the oversize particles fall into the cone and slide
and bull-ring when the mill is run without coal, downward until they mix with the incoming raw
a stop limits the downward movement of the coal. In this way, only the desired size of coal
journal assembly. The force to pulverize the leaves the pulverizer. The HP mill has a venturi
coal is applied to the journal assembly by an ex- where the flow is split into four equal streams
ternal spring. As the journal rotates about its before exiting through the discharge valves. With

Table IX. C-E HP Pulverizer Application


Mill fipe Furnace fipe Mill Pressure Air System ' Capacity*
HP Balanced Draft Positive Primary Air 16,200 to
Fan 200.000 Iblhr
HP Pressurized Positive Primary Air 16,200 to
Fan 2o0,ooo lblhr
HPS Balanced Draft Negative Exhauster 16,200 to
Fan 87,200 lblhr
HPPS Pressurized Positive - Exhauster 16,200 to
Fan 87,200 lblhr
*Pulverizer capacitites are based on a 55-grindability coal pulverized to 70 percent through a 200 mesh sieve, having a
12 percent moisture content with low-rank bituminous coals or 8 percent with high-rank bituminous coals.
COMBUSTION
Pu1verizerse:~dPulverized-Coal Systems

I I
Fig. 26 C-EHP ring-roll bowl mill for positive-pressure operation
--
COMBUSTION
Puhrerizera 8nd Puhrerlzed-Coal Systems
--

I
Fig. 27 C-E HPS or HPPS ring-roll bowl mill for use with exhauster
I
COMBUSTTON
Pulverizers and Pulverized-Coal Systems

an exhauster mill, there is only one discharge on its concrete foundation. They are: the static
pipe, which conducts the pulverized product to weight of the machine itself; dynamic loads that
the exhauster. The fineness of the pulverized are the result of the grinding process; and ther-
product leaving this type of pulverizer is af- mal loads from the heating of the pulverizer by
fected by-the grindability of the coal, the amount the hot primary air, which results in expansion
of wear that has taken place on the grinding rolls forces on the foundation. The engineer who de-
and ring, the air flow and temperature, and the signs the foundation must take these loads into
grinding force-both the spring rate and the ini- account in both anchor-bolt and concrete-
tial spring compression. reinforcement sizing and placement. The mill
and its drive motor are both mounted on the
PULVERIZER SHELL DESIGN REQUIREMENTS
same foundation so there is no relative vibra-
All pulverizing equipment containing coal- tion or settling between the two, which could
dust laden air is designed and built according to affect component alignment.
the recommendations of the National Fire
REMOVABLE GEAR DRIVE
Protection Association (NFPA), their Standard
NFPA 85F: Installation and Operation of Pulver- A distinctive feature of theC-E HP pulverizer
ized Coal Systems. The pressure-containing shell is its removable planetary-gear drive (Fig. 28).
of the pulverizer, the exhauster, and the rejects This drive is lighter in weight yet stronger than
hopper are designed to contain a 50-psig pres- similar capacity worm-gear or triple-reduction
sure. This requirement is independent of any spiral-bevel helical gear drives. The HP gear
lower design or operating pressure in the unit is independent of the mill housing structure
equipment. and can be removed for inspection or mainte-
nance, Fig 29. Its size and weight make it prac-
PULVERIZER FOUNDATION DESIGN
tical to move it to a maintenance area away from
The HP pulverizer exerts three types of loads the pulverizer bay. Mill outage time will be mini-

Input Gear Set

Fig. 28 Removable planetary-gear drive of C-E HP pulverizer


I COMSUSIION
Pulverizem and Puhnrizd-Coal Systems

ciation (AFBMA) B-10 life of 100,000 hours


minimum.
Mill grinding forces are carried by a hydro-
dynamic tilting-pad thrust bearing assembly
located above the planetary stage. There are mul-
tiple bearing pads, four of which have dual-
element sensors to measure pad temperature.
The pad temperature is interlocked with mill
operation to prevent damage to the thrust bear-
ing. The thrust-bearing pad pitch-circle diam-
eter is the same as the gear-housing outer struc-
tural wall, to maximize thrust-bearing support
and to transfer grinding forces directly to the
foundation without affecting gear meshes.
LUBRICATION SYSTEM

An external lubrication system supplies cooled


and filtered oil to the roller bearings, the gear
meshes, and the hydrodynamic thrust-bearing
pads. All major components of the system are
shop-mounted on an oil reservoir tank. An
isolation device allows maintenance of the sys-
Fig. 29 Shop assembly of C-E HP pulverizer and tem skid assembly without draining the gear-
planetary-gear drive
unit hydrodynamic bearing reservoir, which is
at a higher elevation. A duplex filter assembly
ma1 if a spare gear unit is available at the site. provides for maintenance of a standby filter
Since the gear unit does not penetrate the mill while the pulverizer is operating.
housing, it is not exposed to the pulverized coal After filtering, the oil passes through an oil-
entrained in the primary air, The input-shaft to-water shell-and-tube heat exchanger. Electri-
and output-table seals are of the non-contacting . cal temperature and pressure sensors monitor
labyrinth type operating at local ambient pres- the lubrication system; mill starting, operation,
sure. The mill-housing penetration seal is on the and stopping are all interlocked to prevent run-
grinding-bowl support hub, above the gear unit. ning the gear unit without proper lubrication.
Any heat load on the gearing is substantially re- Low watt-density oil heaters installed in thermo-
duced by its physical separation from the hot-air wells in the reservoir bring the oil up to mini-
inlet, allowing the gears and bearings to run as mum operating temperature before mill ener-
cool as possible. gization.
Internally, the gear unit consists of a right- MILLSIDE AND LINER ASSEMBLY
angle spiral-bevel reduction input stage and a
planetary reduction output stage. The sun gear The millside and liner assembly (Figs. 26 and
is connected to the bevel-gear shaft by a crowned 27) is a weldment which supports the upper sec-
gear-type coupling to allow both axial and radial tion of the pulverizer and receives the hot pri-
movement. Floating sun and planet gears assure mary air from the combustion-air preheater. It
equalized loads on the meshing teeth; this acts is mounted on sole plates and is secured to the
to distribute the total horsepower equally among foundation by anchor bolts. Since the hot pri-
the three planets. Input-gear, bevel-gear, and mary air could produce thermal stresses in the
-. planet-gear shaft bearings are all designed millside and foundation, the millside is inter-
for Anti-Friction Bearing Manufacturers Asso- nally insulated with ceramic-fiber blankets. Re-
COMBUSTION
Pulverizers and Pulverized-Coal Systems

placeable liners and wear plates cover the insu- structed of abrasion-resistant plate, segmented
lation. for convenience in assembly and maintenance.
A tramp-iron spout in the floor of the millside Removable liners control the upward airflow
conducts rejected material to the external rejects- past the bowl rim, to adjust pressure drop across
conveying system. Doors in ?he millside give the grinding zone and optimize transport of the
access to the underside of the bowl and provide coallair mixture to the final classifier.
for a ventilating airflow when maintenance is
HP PULVERIZER JOURNAL ASSEMBLY
being done.
BOWL, BOWL HUB, AND VANE-WHEEL ASSEMBLY
The roll-assembly bearing system consists of
two identical tapered roller bearings in an op-
Figs. 26 and 27 show these components*lo- posed arrangement (Fig. 30). The system is de-
cated above the gearbox. The and hub signed for an AFBMA B-10 life of 100,000 hours
carry the skirts%the the vane-whee1seg- minimum, under a severe duty cycle,An oil bath
ments, and the bull ririg segments. lubricates the grinding-roll bearings. To prevent
The bull ring is subject to abrasive wear as a of the oil, seal air flows through
result of the-grinding that takes place on it; re- internal mll-assembly ports, then
placement is necessary when the wear becomes through a roll air seal. No parts of the seal-air
excessive. C-E furnishes segmented bull rings for supply system are exposed to the coal/primary-
ease of handling, and uses high-chrome white air
iron for the segments for most applications. HP mills have a unique grinding-roll tilt-out
The vane-whee1segments are made heat- feature, as depicted in Fig. 30. Each roll assem-
treated abrasion-resistant steel plate. Removable bly can be rotated out of the mill on its trunnion
air restriction rings provide for adjustment of the mounting shafi, using a tilting fixture and an
pressure differential across the bowl. These overhead mill hoist or crane, as shown in Fig. 31.
rings, welded to the vane-wheel segments, have
a weld overlay to protect them from wear.
The pyrites (mill-rejects)hopper is normally
opposite the mill drive motor. In this case either
the motor or the hopper must be removed to
slide the gear unit out. If the hopper is placed
to the side of the mill, then the gear box is re-
moved away from the motor. The standard HP
mill setting height permits mounting of the
hopper and the pyrites handling system without
pits or entrenchment.
SEPARATOR BODY AND VANE-WHEEL ASSEMBLY
As described above, initial coal-particle classi-
fication is done in the grinding zone by the
bowl-mounted rotating vane wheel and the
housing-mounted stationary coallair deflectors.
The vane wheel, the primary classifier on HP
mills, promotes uniform distribution of the coal
and carrier air while it also lessens erosion of
mill internals by the coallair stream. Large coal
particles return immediately to the bowl for
regrinding before entering the main classifier
above. Fig. 30 C-E HP pulverizer journal assembly with
The rotating part of the vane wheel is con- tilt.out feature
Co~mo*
k t h r h . n and P u l v ~ C o aSystems
l

large ungrindable material to under the


rolls until it is rejected from the mill. A positive
spring-preload locking device prevents any
change in spring setting during operation. The
entire spring assembly is a cartridge type to re-
duce changeout time, and to allow for stocking
of spare assemblies, and convenient inspection
and refurbishing.
The spring.gssembly, as well as the journal as-
sembly and the main bowl-hub air seal, have
labyrinth-type seals that use air for sealing
between stationary and moving parts. The pres-
sure-ofthe filtered seal air is 8 to 16 in. WG above
the mill-inlet pressure, with the flow rate a
function of mill size.
CLASSIFIER AND DISCHARGE-VALVEASSEMBLIES

The top of the mill is made larger than the main


body to redme coallair stream velocity, to reduce
mill aerodynamic pressure drop, and to optimize
classifier efficiency.
Fig. 31 HP roll assembly tilted-out of pulverizer Plant personnel can adjust the position of the
classifier vanes when the pulverizer is operat-
With the roll locked in this vertical service- ing, by use of two manually operated levers on
access position, several inspection and mainte- the mill top, each lever operating half of the
nance tasks can be performed without removing vanes. Particle separation is accomplished in a
the assemblies from the mill: worn grinding rolls stationary-cone cyclone classifier. As described
can be removed and new ones installed; roll- before, oversized coal particles are>returnedto
bearing end play can be inspected and adjusted; the grinding zone through the return spout at the
oil seals can be inspected or replaced, and oil can bottom of the cone, where they mix with the
be changed; the entire roll stem assembly can be incoming raw coal feed to increase drying
removed and taken to another area for bearing efficiency.
maintenance.18 All areas of the classifier section subject to
Maximum roll life is a primary goal of the C-E abrasion wear are lined with cast nitride bonded
HP pulverizer design. It is accomplished by silicon carbide. The inside of the cone is lined
incorporating large rolls to increase the total vol- with 90-percent-alumina tile to protect it from
ume of wear material available, and by using roll wear by the sliding oversize coal particles.
material with high wear resistance. Combustal- Four knife-gate valves at the outlet of a posi-
loyTMwear material, a C-E proprietary weld tive-pressure HP pulverizer isolate it from the
overlay, provides effective wear life five times fuel piping leading to the furnace, as recom-
greater than standard Ni-Hard. mended by NFPA. Each valve has a set of
The externally mounted spring assembly (Figs. replaceable valve seats, coated to minimize wear.
26 and 27) has a major advantage in that main- Pneumatic cylinders operating in unison open
tenance personnel do not have to enter the pul- and close the valves. They are actuated by a single
verizer to inspect or adjust springs. Since the solenoid valve that also controls the supply of
assembly is located away from the coal flow, ero- purgelseal air to the fuel piping. Fig. 26 shows
sion is eliminated. Spring travel can be maxi- the seal-air header located downstream of the
mized with an external mechanism, to allow discharge valves.
COY BUSTION
Pulverlzen and Pulverized-CoalSystems

Fan Casing
/

Fig. 32 Centrifugal material-handling exhauster for C-E suction-type pulverizer

COALlAlR EXHAUSTER FANS tain conditions explosions may take place.


Notwithstanding these dangers, the industry
For suction-type HP pulverizers, C-E supplies has achieved a remarkable safety record since
material-handling fans to match the mill and the inception of pulverized-coal firing. To
fuel-piping system requirements. These exhaust- protect property and life, all pulverizing
ers are horizontal-shaft straight-bladed centrifu- equipment and related auxiliaries, including
gal fans (Fig. 32) operating at constant speed and strength of equipment, valving and inerting,
temperatures between 150" and 180F (65" and are designed in accordance with NFPA 85F.
80C).They are designed in accordance with Various controls and safety devices are
NFPA standards. There are replaceable liners on
utilized for the correct and proper operation of
the housing scroll and sides. The fan spider is the equipment. Pulverizer output is controlled
removable if fan blades are to be replaced.
by regulation of feed rate in response to load
The fan wheel is supported by anti-friction signal. Airflow and air temperature are propor-
bearings mounted in an external bearing hous-
tioned to feed rate by automatic control. Also
ing located between the exhauster and its driv-
included are permissive interlocks for the
ing motor. Exhausters used with HP pulverizers
proper sequential operation of equipment, flow
are driven by separate motors. The pulverizer
alarms to indicate cessation of coal flow to and
and exhauster motors are interlocked logically
from feeders, and load-limiting devices to pre-
to insure coal transport out of the mill. Fan bear-
vent overfeeding the mills. Anticipating ac-
ing lubrication is independent of the mill lubri- tions and more responsive feedback may often
cation system. be included with the above in pulverizer con-
SAFETY AND CONTROLS trol systems. Control systems and instrumenta-
tion are covered in detail'in Chapter 13.
The production and of PULVERIZER INERTING AND FIRE EXTlNGUlSHlNG
fuels can be hazardous. Because fine particles
in suspension or deposition are readily vol- To supplement the above operational controls,
atilized and become combustible, under cer- current practice is to install systems to detect and
.-
comumott
Pulwrinn mdPulveritsd-Coal Systems

extinguish miH fires, and to reduce the possibil- system includes the following features:
ity of destructive positive pressures. The pulverizer is automatically inerted when
An ideal inerting system continuously purges conditions exist for a fire or potential explosion.
any combustible volatiles from the pulverizer to
Steam is used as the primary inerting me-
the furnace and avoids "bottling up" of the pul-
dium, with CO, or other cold inert gas used to
verizer; also, it allows a mill to be returned to nor-
cool the pulverizer.
mal service quickly after the inerting takes place.
9 The inerting system is capable of supplying
C-E's pulverizer inerting and fire-fighting sys-
tem is designed to provide an early warning of steam in such quantities to transport the com-
a potentially hazardous situation: it uses readily bustible contents of the pulverizer to the furnace
available plant steam as the inerting medium be- while maintaining an inert atmosphere within
cause steam is less damaging to equipment than the mill.
other inerting media and makes for easier pul- Multiple water-spray nozzles are strategically
verizer restart. Plaht water is used as the fire- installed in the pulverizer to provide complete
extinguishing agent; it is hard-piped to fixed internal fire-extinguishing coverage.
water spray nozzles installed in the pulverizer. T h e system monitors the entire pulverized-
The purposes of such a system are fuel system from the feeders through the fuel
to dilute the oxygen content of the mill when piping.
there is risk of explosion; Audible and visual alarms are activated in all
to transport pulverized fuel to the furnace by critical areas and in the control room upon de-
means of an inert medium when transport by air tection of a hazardous condition.
may be hazardous; Provision is made for interfacing with exist-
9 to extinguish fires in the pulverized-fuel ing plant control systems.
system. In Chapter 21 on power-plant operation, we
C-E SYSTEM DESIGN FEATURES
give further information on the efficient and
proper operation of pulverizer inerting and
The C-E pulverizer inerting and fire-fighting fire-extinguishing systems.

REFERENCES
1 Henry Kreisinger, "Combustion of Pulverized Coal:' "Symposium on Powdered Fuel," Spring Meeting. '
Transactions of the ASME. 60 (Paper No. FSP-60-8): American Society of Mechanical Engineers. St. Paul-
289-296.1938. Minneapolis, Transactions of the ASME. 36: 85-169.
1914.
'Nicolas Leonard Sadi Carnot, E. Clayperon, and R.
Clausius, Reflections on the Motive Power of Fire; and R. C. Carpenter, "Pulverized Coal Burning in the Cement
other Papers on the Second Law of Thermodynamics; Industry," Transactions of the ASME, 36: 85-107.1914.
edited with a n introduction by E. Mendoza. New York: William Dalton and W. S. Quigley, "An Installation for
Dover Pubs., 1962. Powdered Coal Fuel in Industrial Furnaces," Transac-
tions of the ASME, 36: 104-121, 1914.
'Rudolf Diesel, Theory and Construction of a Rational
Heat Motor, trans. by Bryan Donkin. London: Spon, F. R. Low, "Pulverized Coal for Steam Making," Transac-
1894. tions of the ASME, 36: 123-136, 1914.
Friedrich Klemm, A History of Western Technology. "Topical Discussion on Powdered Fuel." Transactions of
Cambridge, Mass.: MIT Press, 1964, pp. 342-347. the ASME, 36: 137-169, 1914.
C. F. Herington, Powdered Coal as a Fuel. New York: Van John Anderson, "Pulverized Coal Under Central-Station
Nostrand, 1918, pp. 68-72. Boilers," Power, 51(9): 336-339, March 2, 1920.
Frank Lewis Dyer and Thomas Commerford Martin, Paul W. Thompson, "Pulverized Fuel at Oneida Street
Edison-His Life and Inventions, with collaboration of Plant," Power, 51(9): 339-340, March 2, 1920.
William Henry Meadowcraft. New York: Harper and "Four-Day Test on Five Oneida Street Boilers Burning - .
Bros., 1929, Vol. 11. pp. 953-957. Pulverized Coal," Power, 51(9): 354-357, March 2, 1920.
COMBUSTION
Pulverlzera and Pulverized-Coal Systems

"Pulverized Coal at Milwaukee," Power, 51(9): 341-342, Powdered Coal Falling in Air or Other Viscous Fluid,"
March 2, 1920. Journal of the Franklin Institute, 197(2): 199-208, Feb-
"The New Lakeside Pulverized-Coal Plant, Milwaukee," ruary, 1924.
Power, 52(10): 358-360, September 7, 1920. John Blrzard, "Transportation and Combustion of Pow-
"Largest Station Using Pulverized Coal," Power, 55(16): dered Coal," U. S. Bureau of Mines Bulletin 217.
- 604-61U. April 18, 1922. Washington: Government Printing Office, 1923.
Henry Kreisinger and John Blizard. "Milwaukee's Con- l2 Henri Verdinne, "The Technique of Powdered Fuel Fir-
tribution to Pulverized Coal Development," Mechanical ing," Fuel in Science and Practice, 2: 146-151, 1923.
Engineering, 61: 723-726 and 737. October. 1940.
F. L. Dornbrook. "Developments in Burning Pulverized l3W. Nusselt, "Der Verbrennungsvorgang in der
Coal-Thirty Year Review of Experience in Milwaukee Kohlenstaubfeuerung (The Combustion Process In Pul-
Plants," Mechanical Engineering, 70: 967-974, De- verized Coal Furnaces)," VDI Zeitschrift, 68(6): 124-1213.
cember, 1948. February 9, 1924.
Henry Kreisinger, F. K. Ovitz, and C. E. Augustine. 14 P. Rosin. "Die Thermodynamischen und Wirtschafthi-
"Combustion in the Fuel Bed of Hand-Fired Furnaces," chen Grundlaaen der Kohlenstaubfeueruna (Thermodv-
U. S. Bureau of Mines Techriical Paper 137. Washington: namic and ~ c o n o m i cBases of Pulverized &a1 ~iringj:'
U. S. Bureau of Mines, 1916. Braunkohle. 24(11): 241-259. June 13. 1925.
Walter T. Ray-and Henry Kreisinger. "The Flow of Heat
Through Furnace Walls," U.S. Bureou of Mines Bulletin Walter 1. Wohlenberg and Donald G. Morrow, "Radiation
8. Washington: U. S. Bureau of Mines, 1911. in the Pulverized-Fuel Furnace," Transactions of the
ASME, 47: 127-176,1925.
Henry Kreisinger and Walter T. Ray, "The Transmission
of Heat into Steam Boilers," U.S. Bureau of Mines Bulle- MR. P. Hensel. "Coal Combustion," presented at the Engi-
tin 18. Washington: U. S. Bureau of Mines, 1912. neering Foundation Conference on Coal Preparation for
Henry Kreisinger and J. F. Borkley, "Heat Transmission Coal conversion. 1st. Franklin Pierce College, Rindge.
Through Boiler Tubes," U. S. Bureau of Mines Technical N.H.. 1975. Paper updated in 1978. Combustion Engi-
Paper 114. Washington: U. S. Bureau of Mines, 1915. neering publication TIS-4599.
8 Henry Kreisinger. John Blizard, C. E. Augustine, and B. J. 17R. P. Hensel, "The Effects of Agglomerating Characteris-
Cross, "An Investigation of Powdered Coal as Fuel for tics of Coals on Combustion in Pulverized Fuel Boilers."
Power-Plant Boilers-Tests at Oneida Street Power Sta- Symposirrrn on Coal Agglomeration and Conversion.
tion. Milwaukee, Wisconsin," Ll. S. Bureau of Mines Bul- Morgantown, W.V.. 1975. Sponsored by the West Virginid
letin 223. Washington: U. S. Bureau of Mines, 1923. Geological and Economic Survey in Cooperation C\/ith the
Henry Kreisinger, John Blizard. C. E. Augustine, and B. J. Coal Research Bureau. Combustion Engineering publica-
Cross, "Tests of a Large Boiler Fired with Powdered Coal tion TlS-4353.
at the Lakeside Station, Milwaukee," U. S. Bureau of V. F. Parry, "Production. Classification and utilization of
Mines Bulletin 237. Washington: U. S. Bureau of Mines. Western United States Coals," Economic Geology, 45(6):
1925. 515-532, September-October, 1950.
9E. Audibert, "Etude de I'Entrainement du Poussier de
D. Magnum and P. L. Stanwicks, "HP Series Pulverizer De-
Houille par I'Air," Annales de Mines. l(3): 153-101.
March. 1922. sign, Testing, Maintenance Cost", Proceedings of POWER-
GEN '89 Conference, Book 2, POWER-GEN '89, New
loJohn Blizard. "The Terminal Velocity of Particles of Orleans, LA, December 5-7, 1989.
Fuel-Firing Systems '

0 n the process of steam generation, fuel-


burning systems provide controlled, efficient
conversion of the chemical energy of fuel into
m high equipment availability with low
maintenance
In actual practice, some of these characteris-
heat energy which, in turn, is transferred to the tics must be compromised to achieve a reason-
heat-absorbing surfaces of the steam generator. able balance between combustion efficiency
To do this, fuel-burning systems introduce the and cost. For example, firing a fuel with the
fuel and air for combustion, mix these reac- stoichiometric air quantity (no excess above
tants, ignite the combustible mixture and dis- the theoretical amount) would require an infi-
tribute the flame envelope and the products of nite residence time at temperatures above the
combustion. ignition point at which complete burnout of the
An ideal fuel-burning system fulfilling combustibles takes place. Thus, every firing
these functions would have the following system requires a quantity of air in excess of
characteristics: stoichiometry to attain an acceptable level of
8 no excess oxygen or unburned combustibles unburned carbon in the products of combus-
in the end products of combustion tion leaving the furnace. This amount of excess
8 a low rate of auxiliary ignition-energy input air is an indicator of the burning efficiency of
to initiate the combustion reaction the firing system. (Further discussion of the im-
8 an economic reaction rate between fuel and
pact of excess-air percentage on boiler design is
oxygen compatible with acceptable nitrogen- found in Chapter 6; included is a table of com-
and sulfur-oxide formation monly used excess-air percentages.)
8 an effective method of handling and dispos-
ing of the solid impurities introduced with the THE COMBUSTION REACTION
fuel
The rate and degree of completion of a chem-
m uniform distribution of the product weight ical reaction, such as in' the combustion pro-
and temperature in relation to the parallel cir- cess, are greatly influenced by temperature,
cuits of heat-absorbing surface concentration, preparation and distribution of
8 a wide and stable firing range the reactants, by catalysts, and by mechanical
fast response to changes in firing rate turbulence. All of these factors have one effect
in common: to increase contacts between tal factors influencing rate and completeness of
molecules of the reactants. combustion must be considered along with the
Higher temperature, for instance, increases degree of heat-transfer efficiency.
the velocity of molecular movement permitting There are two methods of producing a total
harder and more frequent contact between flow pattern in a combustion chamber to pro-
molecules. A temperature rise of 200F at some vide successful molecular contacts of reactants
stages can increase the possible rate of reaction through mechanical turbulence. One is to di-
a million fold. vide and distribute fuel and air into many
At a given pressure, three factors limit the similar streams and to treat each stream inde-
temperature that can be attained to provide the pendently of all others. This provides multiple
greatest intermolecular contact. These are the flame envelopes. In contrast, the second pro-
heat absorbed by the combustion chamber en- cess provides interaction between all streams
closure, the heat absorbed by the reactants in of air and fuel introduced into the combustion
bringing them to ignition temperature, and that chamber tagroduce a single flame envelope.
absorbed by the nitrogen in the air. The first concept requires that the total fuel
The concentration and distribution of the and air supplied to a common combustion
reactants in a given volume are directly related chamber be accurately subdivided. It also lim-
to the opportunity for contact between interact- its the opportunity for sustained mechanical
ing molecules. In an atmosphere'-containing mixing or turbulenceparticularly in the early
21-percent oxygen (the amount present in air), stages of combustion. The necessity of obtain-
this rate is much less than it would be with ing and sustaining good distribution of fuel
90-percent oxygen. As the reaction nears com- and air is a design as well as an operating prob-
pletion, the distribution and concentration lem. There must be sufficient opportunity for
of reactants assume even grea'tef importance. contact of fuel and oxygen molecules as well as
Because of the dilution of reactants by the uniform distribution of product temperature
inert products of combustion, the relative and mass in relation to the combustion
distribution-and opportunity for contact- chamber. On the other hand, the single-flame-
approaches zero. envelope technique provides interaction be-
Preparation of the reactants and mechanical tween all streams of fuel and air introduced
turbulence greatly influence the reaction rate. into a common chamber. It allows more time for
These are the primary factors available to the contact between all fuel and air molecules, and
fuel-burning system desigber attempting to mechanical turbulence is sustained through-
provide a d.esirable reaction rate. out the chamber. This avoids stringent fuel and
The beneficial effect of mechanical turbu- air distribution accuracy requirements.
lence on the combustion reaction becomes ap- Firing systems representative of these two
parent when it is realized that agitation permits concepts are horizontally wall-fired systems
greater opportunity for molecular contact. Agi- (characterized by individual flames) and tan-
tation improves both the relative distribution gentially fired systems (which have a single
and the energy imparted. Agitation assumes flame envelope). There are other types and
greater significance if achieved later in the combinations; one such is the vertically fired
combustion process when the relative concen- system, which uses characteristics of both pre-
tration of the reactants is approaching zero. viously descfibed systems.
HORIZONTALLY FIRED SYSTEMS
PRACTICAL FUEL-FIRING - A

In horizontally fired systems the fuel is


SYSTEM DESIGN mixed with combustion air in individual
In the practical application of a burner and burner registers (Fig. 1).In this design, the coal
fuel-burning system to a boiler, all fundamen- and primary air are introduced tangentially to
C O ~ O N
Fud-Firkg Systems

I I
Fig. 1. Burner for horizontal firing of coal

the coal nozzle, thus imparting stroig rotation


within the nozzle. Adjustable inlet vanes im-
part a rotation to the preheated secondary air
from the windbox. The degree of air swirl,
coupled with the flow-shaping contour of the
burner throat, establishes a recirculation pat-
tern extending several throat diameters into the
furnace. Once the coal is ignited, the hot prod-
ucts of combustion propagate back toward the
nozzle to provide the ignition energy necessary
for stable combustion.
The burners are located in rows, either on the
front wall only (Fig. 2) or on both front and rear
walls. The latter is called "opposed firing."
Because the major portion of the combustion
process must take place within the recircula-
tion zone, it is imperative that the airlfuel ratio
to each burner is within close tolerances. The
rate of combustion drops off rapidly as the reac-
tants leave the recirculation zone and interac-
tion between flames occurs only after that Fig. 2. Flow pattern of horizontal (wall) firing
comumON
Fud-FirhgSystems

point. The degree of interaction depends on ble to vary the velocities of the air streams,
burner and furnace configurations. change the mixing rate of fuel and air, and con-
trol the distance from the nozzle at which the
TANGENTIALLY FIRED SYSTEMS coal ignites.
The tangentially fired system is based on the The vertical arrangement of fuel and air noz-
concept of a single flame envelope (Fig. 3). zles provides great flexibility for multiple-fuel
Both fuel and combustion air are projected firing. It is possible to provide for full-load ca-
from the corners of the furnace along a line tan- pability with gas or oil by locating the addi-
gent to a small circle, lying in a horizontal tional nozzles for t h e s e fuels i n the
plane, at the center of the furnace. Intensive secondary-air compartments adjacent to the
mixing occurs where these streams meet. A coal nozzles. In addition, separate nozzles for
rotative motion, similar to that of a cyclone, is injecting municipal refuse and other waste fu-
imparted to the flame body, which spreads out els are frequently provided in both utility and
and fills the furnace area. industrial boilers.
When a tangentially fired system projects a As illustrated in Fig. 5, fuel and air nozzles
stream of pulverized coal and air into a furnace, most commonly tilt in unison to raise and lower
the turbulence and mixing that take place along the flame in order to control furnace heat ab-
its path are low compared to horizontally fired sorption and thus heat absorption in the super-
systems. This occurs because the turbulent heater and reheater sections. In addition to
zone does not continue for any great distance, controlling the furnace exit-gas temperature for
since the expanding gas soon forces a stream- variations in load, the tilts on coal-fired units
line flow. The significance of this factor on the automatically compensate for the effects of ash
production of oxides of nitrogen is discussed deposits on furnace-wall heat absorption.
later inthis chapter. However, as one stream im- As wall blowers clean ash deposits from the
pinges on another in the center of the furnace, furnace walls, the furnace exit-gas temperature
during the intermediate stages of combustion, tends to decrease because of the increase in
it creates a high degree of turbulence for effec- overall furnace absorption. The windbox noz-
tive mixing. zles are then automatically tilted 'upward at a
The fuel and air are admitted from the verti- controlled rate, and combustion is completed
cal furnace corner windboxes (Fig. 4). Dampers higher in the furnace. The repositioning effec-
which control the air to each compartment tively reduces the absorption in the lower part
make it possible to vary the distribution of air of the furnace, and increases the furnace exit-
over the height of the windbox. It is also possi- gas heat content to maintain steam at design
temperatures. .
Conversely, as furnace walls are again gradu-
ally covered with ash deposits and furnace heat
absorption decreases due to the insulating ef-
fects of the ash, the tilts are gradually de-
pressed and combustion is completed lower in
the furnace. This exposes the hot gases to a
greater proportion of furnace wall surface and
effectively controls furnace exit-gas tempera-
ture and steam temperature until ash is again
removed from the furnace walls.
VERTICALLY FIRED SYSTEMS
I I The first pulverized-coal systems had a con-
Fig. 3. Tangential firing pattern figuration called vertical or arch firing. They are
-

Nozzles

Secondary Air

Damper

Fig. 4. Arrangement of corner windbox for tangential firing of coal

L
Fig. 5 Selective furnace utilization and steam temperature control are accomplished by tilting noales
in a tangentially fired system.
-
now used principally to fire coals with mois- This arrangement has the advantage of heating
ture-and-ash-free volatile matter between 9 and the fuel stream separately from a significant
13 percent. They require less stabilizing fuel portion of its combustion air to provide good ig-
than horizontal or tangential systems, but have nition stability. The delayed introduction of the
more complex firing equipment and, therefore, tertiary air provides needed turbulence at a
more complex operating characteristics, point in the flame where partial dilution from
, The firing concept and the arrangement of the products of combustion has occurred. The
the burners in the arches are shown in Figs. 6 furnace flow pattern passes the hot product
and 7. Pulverized coal is discharged through gases immediately in front of the fuel nozzles to
the nozzles. A portion of the heated combus- provide a ready source of inherent ignition en-
tion air is introduced around the fuel nozzles ergy which raises the primary fuel stream to ig-
and through adjacent auxiliary ports. High- nition temperature. The flow pattern also
pressure jets are used to avoid.short-circuiting ensures that the largest entrained solid-fuel
the fuellair streams to the furnace discharge. particles,- with the lowest surface-area-to-
Tertiary air ports are located in a row along the weight ratio, have the longest residence time in
frcint and rear walls of the lower furnace; the combustion chamber.
The firing system produces a long, looping
flame in the lower furnace, with the hot gases
discharging up the center. A portion of the total FIRING SYSTEMS
combustion air is withheld from the fuel stream THAT MINIMIZE
until it projects well down into the furnace. NITROGEN-OXIDE FORMATION
In-furnace firing systems to minimize NO,
formation are designed so that the fuel-bound
nitrogen conversion is controlled by driving the
major fraction of the fuel nitrogen compounds
into the gas phase under overall fuel-rich condi-
tions. In this atmosphere of oxygen, deficiency,
there occurs a maximum rate of decay of the
evolved intermediate nitrogen compounds to
N,. Following the admission of the remaining
air, the slow burning rate reduces the peak
flame temperature, to curtail the thermal NO,
production in the latter stages of combustion.
The final section of Chapter 4 on the forma-
tion of NO, in fossil-fired steam-generatingunits
is a useful treatment of thermal and fuel
NO,, and the design criteria relevant to their
control.
TANGENTIALLY FIRED LOW-NO, SYSTEMS
Early studies of NO, emissions from all types
of steam generators indicated that those from tan-
Furnace Enclosure getially fired units were about half the values
4

(RefractoryLined) of those from horizontally fired systems.


The reduced formation of nitrogen oxides
results from the relatively low rate of mixing be-
Fig. 6. Flow pattern of vertical firing tween the parallel streams of coal and second-
COMBusrrON
Fuel-FMng Systems

Oil and Secondary Air


-----------------------
Upper Frpnt Wall

Jet Air

Coal and Secondary Air


Front Wall

Fig. 7. Burner arrangement on the front arch of the furnace shown in Fig. 6

ary air emitted from the corner windboxes. position. This decreases the available oxygen
Thus, ignition and partial devolatization occur below the OFA ports in even greater proportion
within an air-deficient primary combustion to the change in total excess air.
zone that exists from the fuel nozzle to a point
'
within the furnace at which the stream is ab-
sorbed into the rotating mass of gases termed
the fireball.
The fireball itself is rich with oxygen because
it contains all the air required for complete
combustion of the fuel. Because the balance of
the devolatization occurs after the coal stream
enters the fireball, fuel nitrogen-oxide forma-
tion is limited.
Two significant modifications in the design,
and operation of the C-Etangential firing sys-
tem have resulted in further extension of the
oxygen-deficient combustion zone.
TANGENTIAL FIRING WITH OVERFIRE AIR

As shown in Fig. 8, the first modification


added air compartments within the windbox
above the uppermost coal nozzle. Termed over-
fire air (OFA) ports, these compartments divert
approximately 20 percent of the total combus-
tion air to a burning zone above the windboxes.
As a result, the fireball at windbox level is at or
near stoichiometric air conditions. ..
Fig. 9 shows the effect on NO, production of
varying quantities of overfire air. Note the effect
of total excess air on NO, levels. This is due pri-
marily to the reduction in available oxygen
within the fireball adjacent to the windboxes.
With a constant windbox-to-furnace differen-
tial, reducing total excess air increases the pro- ~ig8. Tangential-firing windbox with overfire air
portion of overfire air at any given OFA damper (OFA) ports and high energy arc ignitors
COMBUSRON
Fwl-Firing Systems
--

0 OO
/ Excess Air Coal, Primary Air Auxiliary
27
p 10

Q&
.-
C
c
0
.E
0
20
3
B
s 30
400 Overfire
20I Air
40
I Damper,
60
I / Open
OO 80
I 100
J

Fig. 9. Effect of overfire air on NO, production


Angle (Typical) Windbox
LOW NO,. CONCENTRIC FIRING SYSTEM

The second modification was the develop- Fig. l o phn


ment of a firing-system concept called the Low
NO,,Concentric Firing System (LNCFS). The of "flame attachment" nozzle tips to accelerate
LNCFS proportions the secondary airflow the devolatization process, Fig. 11.
through the windbox so as to effect a decrease Fig. 12 presents typical results which indi-
in the amount of fuel air while increasing the cate an approximate 20% reduction from the
amount of auxiliary air. In addition, the auxil- standard tangential-firing mode with OFA. The
iary air is directed away from the fuel towards tests clearly show that the NO, reductions from
the adjacent furnace wall in order to reduce the LNCFS are additional to those already achieved
entrainment of auxiliary air by the expanding through OFA.
primary-airlcoal jet.
In the plan view, Fig. 10, LNCFS leaves the
fuel and fuel air aimed at the tangent of the IGNITION SYSTEMS
small circle central in the furnace. The second- Modern steam generators are very dependent
ary air, however, is directed 2 5 O away from the on their ignition systems for safe start-up and
direction of the fuel. Like OFA, air is effectively shutdown operations. The need to insure reli-
withheld from the fuel; unlike OFA, LNCFS af- able and safe firing conditions has caused the
fects the very early stoichiometry of the fuel- evolution from simple ignitors to highly sophis-
burning process. Both techniques are examples ticated ignition systems. Such advanced sys-
of staging, as discussed in Chapter 4. OFA is a tems require the following features:
type of "vertical staging"; LNCFS can be a timed spark-ignition sequence
thought of as a "horizontal staging" technique
unique to tangential firing. a device to create turbulent fuellair mixing
As a practical matter, LNCFS affects the and sufficient hot gas recirculation to insure
"early stoichiometry" for a very limited amount flame stability .
of time. The cross-mixing patterns inherent in a device to detect and monitor the ignitor
tangential firing are massive and the separation flame, and
of both streams are qui-ckly lost as they pene- a device to monitor ignitor fuel flow as an
trate the furnace. Thus, LNCFS requires the use indication of ignitor heat-energy release
COMBrnON
Fuel-Firing Systems

correct amount of ignition energy to fulfill ei-


ther function is a challenging task. The correct
Adjustable combination of ignition-energy quantity, qual-
Flame
ity, and location is affected by many factors,
some of which vary with time; what constitutes
sufficient ignition energy at one instant may be
insufficient the next. From the rate-igniting
standpoint, there is never excess ignition en-
ergy: the more stable a fire, the more likely that
the ignition energy substantially exceeds the
minimum necessary to maintain ignition.
Years of experience with various fuels and fir-
ing systems have led the National Fire Protec-
tion Association (KFPA) to establish practical
guidelines for defining ignition-energy require-
ments based on fuel type and ignition-system
Plan View (A-A) function. For NFPA definitions, see the accom-
Side Elevation of Auxiliary Air panying box Ignitor Functional Definitions.
Compartment
IGNITION-SYSTEM DESIGN

Fig. I I Air nbule tip for LNCFS


An electrical spark is the typical initiating
source of fuel ignition. High-voltage free-air
sparks can reliably ignite high-calorific-value
gases and light (distillate) oils. High-energy
Field Test Data: surface-shunted arcs are used to reliably ignite
Full Load (390-420 MW) distillate and heavy (residual) oils. Safety con-
3 500 - Full Overfire Air siderations dictate that only a limited quantity
of fuel be exposed to the electrical spark be-
0
s
c9
cause of its relatively low ignition energy. The
0
C
400- heat released from this initial fuel input then
7 becomes the ignition energy for a different and/
or large fuel input. Essentially, the ignition sys-

-5300-
a
tem provides for a controlled transition from
spark to main-fuel firing through an incremen-
6z 200- tal increase in ignition energy.
Not to make too large a step increase in fuel
I input is also important in order to avoid unde-
2.0 3.0 4.0 5.0 -6.0 sirable furnace pressurization during lightoff.
ExcessAir (% 0 2 ) Fig. 13 shows two methods of achieving a step
increase in fuel input for tangential firing. In
the example on &;left, the lowest elevation of
Fig. I 2 No,, vs excess air with and without LNCFS ignitors is fired first and, after a suitable time,
the elevation of oil warm-up guns is ignited. As
The primary function of the ignition system furnace temperature stabilizes, the main coal
is to light off the main fuel input to the furnace. nozzles adjacent to the oil guns are brought into
Often, the ignition system is designed also to operation. Thereafter, additional ignitors can
stabilize the main fuel flame under potentially come into service to light off elevations of main
unstable firing conditions. Determining the coal nozzles directly.
C-ON
Fwl-FJffngSystems

In the alternative on the right of Fig. 13, igni- tally fired systems include Ionic Flame Moni-
tors light off successive elevations of warm-up toring and High Energy Arc.
oil guns. Adjacent elevations of main coal noz- These ignitors use a wide variety of gas and
zles are then ignited by the oil guns. oil fuels. The Ionic Flame Monitoring (IFM) ig-
Experience indicates that firing by these step- nitor fires medium to high-heating-value gases
input methods will ininimize furnace pressur- or distillate oils, while the High Energy Arc
ization and unnecessary over-pressure trips. (HEA) ignitor fires distillate to residual oils.
The type of system selected depends on fuel
C-E IGNITION SYSTEMS
availability-and cost. High-quality gas and dis-
Ignitors available for tangential and horizon- tillate oil are preferred for both ignition systems

IGNITOR FUNC'rIONAL DEFINITIONS


To fully understand the hardware, it may be necessary to review definitions contained in
NFPA 85E, "Standard for Prevention of Furnace Explosions in Pulverized Coal-Fired Multi-
ple Burner Boiler-Furnaces, 1985 Edition", from which we quote.
Ignitor Types:
Class 1(Continuous Ignitor)
'An igniter applied to ignite the fuel input through the burner and to support ignition
under any burner light-off or operating conditions. Its location and capacity are such that it
will provide sufficient ignition energy (generally in excess of 10 percent of full load burner
input) at its associated burner to raise any credible combination of burner inputs of both
fuel and air above the minimum ignition temperature."
Class 2 (Intermittent Ignitor)
'An igniter applied to ignite the fuel input through the burner under prescribed light-off
conditions. It is also used to support ignition under low load or certain adverse operating
conditions. The range of capacity of such igniters is generally 4 percent to 10 percent of the
full load burner fuel input. It shall not be used to ignite main fuel under uncontrolled or
abnormal conditions. The burner shall be operated under controlled conditions to limit the
potential for abnormal operation, as well as to limit the charge of fuel to the furnace in the
event that ignition does not occur during light-off. Class 2 igniters may be operated as Class
3 igniters."
Class 3 (Interrupted Ignitor)
'A small igniter applied particularly to gas and oil burners to ignite'the fuel input to the
burner under prescribed light-off conditions. The capacity of such igniters generally does
not exceed 4 percent of full load burner fuel input. As a part of the burner light-off proce-
dure the igniter is turned off when the timed trial for ignition of the main burner has ex-
pired. This is to ensure that the main flame is self-supporting, is stable and is not
dependent upon ignition support from the igniter. The use of such igniters to support igni-
tion or to extend the burner control range shall be prohibited."
Class 3 Special (Direct Electric Ignitor)
"A special Class 3 high energy electrical igniter capable of directly igniting the main .- - .
burner fuel. This type igniter shall not be used unless supervision of the individual main
b u r n e ~flame is provided."
stabilizing burner device, flame detection, and
I fuel-input monitoring. A high-voltage spark or
Auxiliary-Air high energy arc source can be used for ignition.
Compartment Either gases ranging from coke-oven gas to bu-
tane or No. 2 fuel oil, is used with this type of .
E l
Coal system. Flame detection is achieved with the
Compartment Ionic Flame Monitoring device. Flow switches
0 monitor fuel input. The IFM design (Fig. 14)
Warm-up Oil follows the traditional C-E philosophy of pro-
Compartment
viding both qualitative and quantitative indica-
rn
lgnitor tion of flame.
The IFM system takes advantage of the pro-
duction of ions and charged particles generated
Fig. 73 Alternative step-ignition processes for
tangential firing during the combustion of hydrocarbon fuels. A
hydrocarbon-fuel flame, then, will conduct
and for boiler warm-up; they arceasier to han- electricity. Another characteristic of turbulent .

dle and cleaner burning in cold furnaces. flames is that they continuously pulsate at some
constant frequency. The quantity of ions and
IFM IGNITORS charged particles generated varies as the flame
The IFM ignitor is a complete ignition system pulsates. Thus, the conductivity of the flame
containing ,an electrical spark source, a self- also changes with the pulsation of the flame.

lgnitor Combustion Air


to Next Elevation of Ignitors

Eddy Plate
Spark Plug

Atomizer

Flame kod

Horn

Fig. 14. Ionic Flame Monitoringside ignitor


When a DC potential is placed across a flame, The complete HEA Ignition System consists
the electric current flow varies at the same fre- of
quency as the flame pulsation. a high energy arc ignitor
The IFM system operates by imposing a DC 8 a warm-up oil compartment capable of pro-
potential on an electrode called the flame rod, ducing a stable flame at all loads
which is in contact with the flame. When there a flame-detecting system sensitive only to its
is "no flame'', the DC voltage remains at the associated oil gun
Miginally imposed level and no current flows. a control system coordinating all the compo-
When there is "flame", the DC voltage drops as nents and providing unit safety
current flows, generating what is called an AC
The High Energy Arc ignitor can ignite
feedback signal. This AC signal is filtered, am-
warm-up fuel oils ranging from No. 2 to No. 6
plified, and modified by the IFM electronics to
and crude oils. The ignitor is a self-contained
drive a flame-indication relay. The electronics
electrical discharge device which produces a
are designed to be fail-safe. If there is compo-
high-intensity spark. Use of a high-resistance
nent failure (a short circuit in the flame rod or
transformer, to produce a full wave charging cir-
signal- lead wire, or an external AC interfer-
cuit and to control spark rate, enables the
ence), a "no flame" indication will occur.
sealed power supply to store maximum energy
The most common application of IFM igni-
and to deliver a greater percentage of this en-
toEs is consistent with the NFPA Class 2 defini-
ergy through insulated cables to the ignitor tip.
tion. IFM ignitors have been used as Class I,
A high spark energy also eliminates coking of
and could be used as Class 3; however, addi-
the ignitor tip. The HEA ignitor consists of four
tional burner-control logic and discriminating
basic components: the exciter, flexible cable,
flame scanners would be required. (Refer to
spark tube and guide pipe, and retractor assem-
Chapter 13 for more information on flame scan-
bly (Fig. 1s).
ners,) A Class 3 application would be made
A key to the successful application of spark-
only when a limited amount of ignition fuel is
ignition is the presence of a strong recirculation
available, such as with a bottled-gas supply
pattern in the primary combusti0,n zone (Fig.
system.
16). The recirculation provides the energy re-
quired to vaporize and heat the oil to its igni-
tion point, thus maintaining stable ignition
after the spark has been deactivated.
The High Energy Arc (HEA) ignitor was de-
veloped specifically for residual oils, as it elim-
inates dependence on premium fuels such as
natural gas and No. 2 oil for main-fuel ignition ~ i (or~~ l~ ~ d~ i ~Ignition
l ~ )Exciter
and boiler warm-up. The HEA ignitor directly Spark Rod . /
lights off a heavy-oil warm-up gun which, in
turn. ignites the main coal nozzles. The HEA
ignitor is used with a discriminating scanner,
which verifies the operation of the warm-up
gun. The warm-up gun is designed for a proven
oil flow of about 10 percent of an adjacent coal
nozzle, with the discriminating scanner prov-
ing the presence of a flame. The combination of
- - an MEA ignitor and No. 6 oil-fired warm-up
gun satisfies the NFPA definition of a Class 1or
I ~ u i b pipe
e / I
Class 2 ignitor. The HEA ignitor alone would be I ~lex~ble
Cable I
a Class 3 ignitor. Fig. 15. High Epergy Arc ignitor
COMBUSTION
Fuel-Firfng Systems

The discriminating flame scanners operate in UNDERFEED STOKERS


the visible-light range, which provides for ex-
In an underfeed stoker, the incoming fuel,
cellent sensitivity to the presence of a flame.
usually coal, is pushed through one or more
These scanners, therefore, can discriminate be-
troughs, called retorts, which are located below -
tween different flames based on both frequency
the burning fuel bed and air emission grates.
and intensity. This insures safe operation of the
Here, moisture is driven off and volatile constit-
overall HEA system.
uents are distilled, passing up through the in-
candescent bed. As the retorts are recharged,
STOKERS the char from the previous fill is pushed into
Stokers are, by modern definition, mechani- and becomes part of the burning bed. On both
cal devices which feed and burn solid fuels in a sides of the retort, the "overflow" burns to com-
bed at the bottom of a furnace. In all cases, the pletion on air-admitting grates or tuyeres. Ash
fuel is burned on some form of grate, through is removed by dumping grate sections (see Fig.
17). Boilers with underfeed stokers of the single
which some or all of the air for combustion
retort-design have been built in capacities rang-
passes. The grate surface can be stationary or
moving. Stokers are classified according to the ing from 5,000to 50,000 lblhr steam flow. Mul-
tiple retort stoker units have been built for
way fuel is fed to the grate; the three general
boilers ranging from 40,000 to 300,000 lblhr
classes in use today are underfeed stokers, over-
steam flow.
feed stokers, and spreader stokers.

I I OVERFEED STOKERS

In an overfeed or traveling-grate stoker, grav-


ity feeds the fuel (again, primarily coal) at one
end of the air-admitting grate surface (see Fig.
18). The incoming bed depth is adjusted by a
(A) Flame pocket is Created on Ignitor Tip gate under which the coal passes before enter-
ing the furnace. The rotating grate surface
moves away from the feed end through the fur-
nace; combustion is completed as air passes up
through the grate. The ash residue is contin-
uously discharged as the grate rotates around to
its return run. Traveling-grate stokers can burn
every type of coal that is mined with the excep-
(B) Flame Pocket Becomes Entrained tion of caking bituminous coal. In addition, by-
in Recirculation Zone and product and waste fuels, such as coke breeze or
Expands Towards Oil-Gun Tip
anthracite dredged from river bottoms, can be
burned effectively. This machine has also been
used as a part of chemical process operations
which produce coke and carbon dioxide.
Steaming rates ranging from 10,000 to 300,000
Ibhr are achievable.
For more detailed discussions about the de-
(C) Flame Pocket Reaches Oil-Gun signs and performance of these first two classes
Tip and Stabilizes of stokers, the reader is referred to the First Edi-
tion of Combustion Engineering -A Reference
Fig. 16. Flame pocket is created on ignitor tip Book on Fuel Burning and Steam Generation.'
CO%BUSlON
Fuel-RrlngSystems
-

A A Active Combustion Zone . .

Fig. 17 Cross-section through underfeed stoker showing stages of combustion

I I

Fig. 18 Arrangement of C-E traveling-grate stoker


COMBUSTION
Fuel-Firing Systems

SPREADER STOKERS Two important designs used for spreader-


stoker firing are thedump grate and continuous
The third major class of stokers, and the ma- ash discharge (CAD) grate. The dump-grate ma-
chine of choice in modern steam-generation ap- . chine has one or more independent sections
plications, is the spreader stoker (Fig. 19). It which open like venetian blinds to discharge
combines the principles of suspension burning the accumulated ash. When ash builds up on
and thin-bed combustion. Feederldistributor one section, the coal feed is stopped and the
devices continuously project fuel into the fur- fire is burned down. The undergrate air is then
nace above an ignited fuel bed on the grate. shut off to that section only, and the ashes are
Fines are burned in suspension while larger dumped. After the fire is reestablished, the pro-
particles fall and burn on the grate. cess repeats in another section. Dump-grate
The spreader stoker method of fuel firing pro- stokers have been built for boilers ranging from
vides quick response to changes in boiler de- 20,000 to 80,000 lb steamlhr.'
mand, and generally never has more than a few The most popular type of spreader stoker is
minutes of fuel inventory on the grate. Flash that incorporating the CAD grate '(Figs. 19 and
drying and rapid release of tarry hydrocarbons 20). This machine, unlike the traveling grate
enable this system to fire caking-type coals stoker, moves toward the fuel feeders, which are
without concern of matting or clinkering. The throwing new fuel towards the back of the unit.
air-cooled, non-agitated ash bed forms few All the fuel is burned before reaching the front
clinkers despite low fusion temperature fuels. end, from which ash is continuously dumped.
Particulate loadings for spreader stokers are The return side of the grate carries siftings,
higher than for previously described designs in which fall through the topside, to the rear and
which the fuel quiescently enters the burning discharges them into a hopper. Grate speed is
zone. Practically all types of coal (except an- regulated to maintain an ash bed depth of 2" to
thracite) and a wide variety of cellulose fuels, 4" at the discharge. Typical operating speed
including wood wastes, bagasse, furfural resi- ranges from 2 to 20 ftlhr, and is varied via gear
due sludge, rice hulls, and coffee grounds have or hydraulic drive units.
been successfully burned on spreader stokers. The C-E CAD stoker grate surface is sectional-

Tangential Overfire Air

Carbon-Recovery Nozzles
Drive Shaft Back-Stop Assembly

Grates

Return Rails
/ \
Drag Seals ldler shaft' \ +siftings Hopper

Fig. 19 Spreader stoker with continuous ash discharge grate


COMBUSION
Fuel-Firlng Systems

!
Grate Seal !
I

i
Fig. 20 C-Econtinuous ash discharge grate

ized. Each section is of the bar-and-key con- of conventional grease-lubricated stoker main-
struction (Figs. 21 and 22) and has independent and idler-shaft bearings. Therefore, self-
idler shafts. The grate bars are mild-steel fabri- lubricating bushings rated at 750F in an oxi-
cated I beams, while the grate keys are the duc- dizing environment are used exclusively.
tile-iron type having a maximum working The combustion-air chamber is located belolv
temperature of 1400F. Constant load springs the fuel-supporting surface; the air passes
maintain proper grate tension. Thermocouples through the keys. Undergrate air is zoned front-
in the stationary castings between the moving- to-back by adjusting manual damper assem-
grate sections monitor temperatures and signal blies at t h e entrance to t h e u n d e r g r a t e
overheat conditions that require corrective compartments. Sealing between compartments
action. is maintained by drag seals and, for cellulose
Current boiler designs that include high- units, by an undergrate sand seal. Thus, under
temperature combustion air preclude the use compartmented areas uniform air pressure is

Carrier Bar Stoker Grate Chain

i
Frame Protective Castings

Fig. 21 Sectionalized grate assembly for continuous ash discharge stoker


COMBUSPION
Fuel-Firmg Systems

maintained without air leakage. of which are identified in Fig. 23), is'of utmost
One of the outstanding characteristics of importance, because it controls the uniformity
spreader-stoker firing is the ability to handle _with which fuel is supplied to the furnace.
-r_apid load swings with little or no change in When the coal is fine and dry, cascading over
steam temperature and pressure. Turndown of the feeder may occur; when it is wet, the parti-
4:l is readily achievable. It is not unusual for a cles may cohere or stick to the feeder, causing
spreader-stoker installation to go from 25 per- an erratic supply of fuel to the distributor. For
cent to 100 percent of rated capacity in less all conditions, including these governing ex-
than two minutes. Also, if fuel is shut off, the tremes, the rotary feeder provides a positive
fire goes out almost immediately. control of the fuel feed rate. The feeding unit
permits positive regulation of the fuel supply
COAL FIRING ON SPREADER STOKERS
over a wide range of operation by either man-
Firing coal with a sp'reader stoker is accom- ual or automatic control.
-plished by using one or more coal spreaders The coal is measured out of the feeder at a
(Fig. 23) mounted on a front plate. These in- rate necessary t6 carry the boiler load. It then
clude a.feeder that regulates the flow of coal in falls in a practically continuous stream into the
proportion to the load, and a distributor rotor path of the revolving distributor blades. These
that spreads the coal over the grate. blades are usually mounted in rows parallel to
the axis of the distributor rotor. The projection
COAL-SPREADER DESIGN
of fuel from a single distributor or from a com-
The desigh of the coal spreader (major parts bination of distributors results in uniform dis-

Fig. 22 Bar-and-key grate construction for CAD stoker


Hopper Shut-Off Gate
Coal Inlet r Water InleVOutlet

Access

Feeder

Fig. 23 Feeder-distributor for firing of coalon a spreader stoker

tribution on the grate, which may be of the a small percentage of fines, boiler response to
dumping or continuous-discharge type. load variations will be affected because fuel ig-
nition depends on the fines. In general, the
FUEL SPECIFICATIONS FOR SPREADER-STOKER
FIRING
spreader-stoker coal consistency should follow
the ABMA recommendation per Fig. 24, which
Spreader stokers were developed to burn the shows that 95 percent of the coal delivered to
lower grades of coal, but they are capable of the coal spreader will, pass through a 314-inch
handling all ranks from semianthracite to lig- round-hole screen. Top size should not exceed
nite as well as numerous waste and byproduct 111-1inches.
fuels. As might be expected, spreader-stoker
OVERFIRE AIR
performance is best when fuel quality and siz-
ing are good. The thin, quick-burning fuel bed In stoker-fired furnaces in which bituminous
requires a relatively small size fuel. Because 25 coals are burned, overfire air is necessary to im-
to 50 percent of the fuel is burned in suspen- prove combustion efficiency by turbulent mix-
sion, the size consistency of coal for spreader ing of air with the unburned gases. Optimum
- stokers has a direct bearing on boiler efficiency mixing results are achieved through proper
-- A and on the tendency of the installation to emit pressure and volume of the air. The quantity of
particulates. Coal with a large percentage of overfire air should be between 5 and 20 percent
fines will have high particulate emissions and of the total quantity of air needed for fuel com-
high carbon loss. If the coal is coarse, with only bustion. The amount of overfire air will be a
C O ~ O N
Fusl-Firng Systems

quite different from the main coal supply. In


some instances, dat, will indicate that a rein-
Fuel To Be Delivered Across jection system woulc not be appropriate.
Stoker Hopper Without Size Segregation - *

CELLllLOSE FUEL F.'lRING


- ON SPREADER STcKERS
Spreader-stoker firing systems have been ap-
plied to a number of boilers burning a variety of
waste products such as bark, refuse, bagasse,
and furfural residue. In general, cellulose fuel
has a higher moisture and volatile content than
coal, and the combustion process involves three
phases: drying, distillation of volatiles, and
Too Coarse burning of fixed carbon. These phases take
place in rapid succession. For complete com-
200 100 50 30 16 8 4 1'14 3/s'/z 3/4 1 2 bustion of the volatile gases formed, 30 to 50
U.S. Std Sieve ~esi~nationl
Round Mesh percent of the air supply is furnished as tangen-
Screen, in. tial overfire air. This system effectively in-
creases burn-out and reduces particulate
carryover. The center lines of the overfire air
Fig. 24 ABMA-recommended limits of coal sizing
for spreader stokers nozzles are tangent to a firing circle in the cen-
ter of the furnace. All nozzles are oriented in
the same direction to establish the same rota-
function of the coal rank and the amount of ex- tion as that of the tangential windboxes located
cess air in the furnace. Relatively small jets of above the overfire air zone. This continuity of
air at pressures up to 25 or 30" WG are used in rotation throughout the lower furnace assures a
most installations for improving combustion in strong vortex, promoting particulate burnout
the furnace, and for reducing visible emissions and reducing carryover into the exiting gases.
and cinder carryover. Distributors for cellulose fuels may be either
mechanical or pneumatic. A mechanical dis-
CINDER REINJECTION
tributor (Fig. 25) is essentially a rotating drum
A carbon-reinjection system can improve with blades placed at an angle to establish uni-
boiler efficiency. The reinjection system re- form fuel distribution over the grate surface.
claims carbon separated from the flyash by us- The speed of the rotating dru? is adjusted for
ing vibrating or rotating screens. Once the fuel conditions and the throw required to prop-
carbon has been separated from the flyash, car- erly cover the grate.
bon-recovery nozzles reinject it into the high With the pneumatic distributor (Fig. 26)
temperature zone of the furnace, just above the high-pressure air projects and distributes the
fuel bed. fuel uniformly over the grate. The fuel enters
The proper design of a carbon-reinjection the furnace in a uniform, dispersed stream.
system requires that the boiler designer know Most is burned in suspension with the remain-
the percentage of combustibles remaining in der consumed after falling to the grate. As with
various screen-sizes of the coal residue to be coal-fired spreader stokers, the grate surface
reinjected. The combustion potential of this may be of the dumping or continuous-ash-
material also is important. This knowledge can discharge type. A carbon-recovery system with
only be obtained from test data gathered from sand-separation screens and steam injection is
operating units. It is probable that the rein- often incorporated to increase the boiler effi-
jected carbon particles will exhibit properties ciency.
that most of the fuel burning occur completely
Feed Control Plate in suspension. In general, low-density mate-
rials such as diffuser bagasses, shredded paper
wastes, and dry lumber mill waste can be fired
at a larger top size or higher percentage of total
heat input than higher-density, high-moisture
wood waste.
The solid waste fuel is metered to four high-
pressure pneumatic transport systems which
convey it to tilting nozzles located in compart-
ments of the corner windboxes. The light parti-
cles are flash dried and burned in suspension.
Larger dense particles are partially dried and
burned in the lower furnace before falling to a
1 V-Belt rive Distributor Rotor I
I I
Fig. 25 Mechanical distributor

SUSPENSION FIRING OF CELLULOSE FUELS

Another proven option for burning some cel-


lulose fuels is suspension firing. Here, like pul-
verized coal firing, the prepared fuel is
pneumatically conveyed to the four corners of
the furnace and injected into the fireball (Fig.
27). Depending on fuel sizing and moisture, a
small dump grate may be affixed at the bottom
of the furnace in the coutant throat (Fig. 28).
The application of this firing system requires

1. PneumaticTransport System. Each of four


systems include a positive displacement blower.
silencers, air lock, and conveying Ilnes:
The solid-waste fuel is metered to thls system
for direct transport to the windbox nozzle.
2. WindboxNoule. Adjustablenoules are incorpor-
ated in the tilting'tangential windboxes. The
arrangement permits optimization of firing
conditionsfor the best burn out of the solid-waste
fuel.
3. Tangential Overfire Air. Multiple elevations of
tanaential overfire air sustain the susDension
burning of the waste fuel.
4. Dump Grate. This feature allows burn out of the
relatively small percentage of solid-waste fuel
which does not burn in suspension.
5% ~otai~ornbustion 5. Grate Air System. Undergrate air provides most
Air At 30" WG Pressure of-theair for burning fuel which falls to the grate.
Overgrate air is introduced from both ends of the
Adjustable Fuel Retention grate to aid in distributing concentrations of fuel
on the grate surface.

Fig. 26 Pneumatic distributor Fig. 27 Pneumatic firing system


COMBUSIlON
Fuel-Fidng Systems

Fig. 28 Dump grates at furnace bottom: closed position on left, open position on right

small dump grate. Burning on the grate adds blow down any piles that may occur.
heat to the lower furnace. This added heat in- Grate castings and support bars argsimilar to
creases the suspension drying and burning of CAD stoker design to maximize component life.
incoming fuel. Pneumatic cylinder assemblies actuate the
The cellulose-fuel nozzle (Fig. 29) is part of grates. This simple design has had a record of
the windbox assembly. The bucket at the end of very low maintenance and high availability.
the nozzle can be tilted 30" along with the C-E TYPE RC SPREADER STOKER
adjacent auxiliary air and supplemental fuel
nozzles. The Combustion Engineering Type RC
The dump grates (Fig. 28) are suspended in (refuse combustion) stoker has been designed
the hopper throat formed by the pressure parts. specifically for prepared-waste-burning facili-
The shafts and bearings are located under the ties that fire refuse-derived fuel (RDF) alone or
pressure parts where they are protected from in combination with coal. The need for such a
the radiant heat of the furnace. Undergrate air is design grew from operating experience at
introduced into the ash hopper; overgrate air plants using conventional grates designed for
nozzles are provided at each end of the grate to burning woodwaste and coal.
-.
COLdsDSTION
W - F i d n g Systems

moval from outside the grate and by replace-


Tilting Mechanism
ment only of those keys that are broken or
oxidized instead of complete assemblies.
The undergrate air is split to each grate half
and then into five compartments along the
length for a total of ten individual zones. Each
compartment has its own damper control to
regulate the amount of air to that zone. The air
passes around the sifting trough, then up
through the free area of the grate surface.
Ash siftings and molten aluminum that fall
through the grate are contained within trough
assemblies and removed by a compartment
screw conveyor which discharges into a com-
mon transfer screw. Each transfer screw dis-
charges into the main ash system. While it is
recognized that additional moving parts add to
the complexity and maintenance needs of the
stoker, there are two compelling reasons for the
troughtscrew conveyor system. First, and most
Cellulose Fuel important, is that molten aluminum which
flows through the grate will not freeze on the
Fig. 29 Tangential corner windbox assembly underside of the grate keys, plugging air pas-
sages or hindering grate motion. Second, the
moving grate surface does not readily allow the
TYPE RC STOKER DESIGN DESCRIPTION siftings to pass through into the siftings hopper.
Both the drive and idler shafts are supported
Fig. 30 illustrates the RC stoker. It is a contin-
by self-lubricating bushings. Eacs bearing is
uous-ash-discharge grate design that uses a cat-
sealed around its exposed circumference by
enary formed by the return side of the grate to
graphite fiber packing held in place by a single-
maintain chain tension. The moving grate sur-
piece seal ring bolted to the bearing housing. In
face is divided along the grate width to facili-
addition, lightweight covers enclose the entire
tate grate maintenance and to a l l o w f o r
housing assembly to minimize sifting contami-
temperature monitoring by means of thermo- nation. A triple-reduction worm gear is sup-
couples located within the stationary grate-seal
plied to drive each half of the grate. A 3-HP,
castings. These grate surfaces are a bar-and-key 1200-RPM motor is integrally mounted to a
design similar in construction and method of speed variator that allows continuous drive mo-
assembly to that of the CAD 'stoker (Fig. 22).
tion over a 9: 1 speed range.
The RC key profile, shown in Fig. 31, offers the
following distinct advantages: CEIdb MASS-BURNING GRATE
1. The grate-surface metallurgy is designed
with oxidation-resistant keys and cart,on-steel Combustion Engineering is the exclusive li-
grate bars which support the grate keys. censee for the DeBartolomeis (db) mass-burn-
ing pusher grate in North America. This unique
'. Warpage due high-tem~eraturecreep is grate system, developed by DeBartolomeis over
not a problem since the steel grate bars do not 35 years ago, has been used in ltaly, Switzer-
see high temperatures. land, France, Japan, North America and South
3. Grate maintenance is facilitated by key re- America.
I
- COMBrnON
Fuel-Firing Systems

Overfire Air
RDF Distributors- 11~

Grate Surface -Water Seal

Drive Shaft Idler Shaft

Siftings Trough

Undergrate
Compartment
+Y 6/T\
4 U
x s i f t i n g screw conveyor

Fig. 30 RC stoker firing system

CUdb SYSTEM DESIGN allow for thermal expansion.. A remote-con-


trolled, hydraulically operated, shut-off gate al-
In the CE/db mass-burning system, overhead lows the furnace to be isolated'from ambient air
traveling cranes transfer unprocessed munici- during normal shutdowns. The walls of the
pal solid waste (MSW) from a storage pit to the steel feed chute are diverging to prevent bridg-
furnace-charging hopper of the steam-generat- ing and are designed to promote uniform mass
ing unit. With a clear view of the storage pit, flow of MSW to the ram feeder (see Fig. 32).
the crane operator selectively removes such Thermal protection of the feed chute is ac-
bulky items as tree trunks and domestic appli- complished by a water-cooled jacket. Inside the
ances from the pit. chute is a low-level alarm to advise the operator
The MSW falls by gravity into the feeding of the need for more fuel in order to maintain
chute to form a natural seal between the furnace the seal between the furnace and ambient air.
and ambient air and thereby prevent air infiltra- A hydraulically operated ram feeder
tion. The charging hopper is top supported by equipped with three steps is located at the base
the building steel and joins with the bottom- of the feed hopper. The reciprocating ram
supported feed chute by means of a seal joint to feeder moves waste from the feed chute onto a
-Stationary Key

Fig. 31 Design key action at sprocket, C-E RC stoker bar-and-key grate surfa,ce

multiple-zone burning grate surface consisting adjustment, it is possible to vary the fuel-bed
of alternating rows of moving and stationary height and combustion conditions on the grate
cast stainless-steel grate bar assemblies. This to allow for the variable characteristics of the
device follo~vsthe steam-flow demand by regu- waste. Forward movement of MSW fuel on the
lating the quantity of MSW fed onto the grate grate surface is accomplished by the reciprocat-
for combustion. ing motion of the movable rows of grate bars. ,
The pusher grate consists of three or more The stationary rows of grate bars for each
grate sections inclined slightly downward grate section are directly supported by the steel
toward the discharge end. Drying and devolati- framework of the grate. The reciprocating grate
lization of the MSW occur on the initial portion bars are fastened to a frame which slides on
of the grate, and are followed by active combus- support rollers. Stationary and reciprocating
tion and final burnout on the subsequent sec- grate bars are exactly alike (see Fig. 33).
tions. The movement of each grate section is The design of the grate bar assembly requires
separately and independently controlled by hy- the undergrate air to flow along the underside
draulic drive cylinders, allowing adjustment of of the surface plates before entering the MSM1
frequency, speed and stroke. The stroke and fuel bed through the air gaps at the front of the
speed can be adjusted in place: stroke displace- grate bar assembly (Fig. 34). The position of the
ment can vary from 2 to 10 inches, and speed free area occurs vertically between the nose of
can vary from 3 to 30 feet per minute. Fre- the plate and the scraper and provides protec-
quency can be adjusted automatically in the tion from problems caused by siftings and mol-
control room from one stroke every 30 seconds ten materials which might obstruct the regular
to one stroke every 5 minutes. With each grate flow of undergrate air. The scraper is protected
section being equipped with such independent from radiation by the surface plate and acts as a
COMBUSTION
Fud-Flring Systems

I
Fig. 32 CEldb stoker in a mass-burning MSW furnace

sealing element against the surface of the lower face and is called undergrate air (UGA). The
adjacent surface plate. The free area between balance of the air enters through nozzles above
the precision-ground cast stainless steel plates the grate and is called overfire air (OFA).
and the pivoting scrapers is approximately 2 The undergrate air can be preheated to aid in
percent of the total grate surface. The sides of the drying of the fuel on the grate. This is nec-
t h e surface plate contain a n overlap1 essary only for extremely wet MSPV. A steam-
underlap feature minimizing siftings and air coil air heater after the forced-draft fan is one
leakage between the plates. method of preheating which is flexible to vary-
ing fuel conditions. Each grate section has its
CUdb AIR SYSTEM
own plenum to provide a controlled quantity of
Approximately 60 percent of the total com- primary combustion air for optimizing combus-
bustion air is introduced through the grate sur- tion of the MSW. Dampers located in the duct-
COIdBOSIION
Fud-Firfng Systems
-

Moving Row
.Fixed Row

\
Operating Shaft

I
I
Fig. 33 Typical CEIdb grate section

+ Moving Assembly
1
1Stationary Assembly

Support Box
- 3ustlon
and Cc)oling Air

I I
Fig. 34 Undergrate air flow pattern of CEldb grate
COmmoN
FueCFldng Systems

work to each plenum chamber provide control tion of nitrogen oxides are further described in
for the undergrate air distribution. Chapter 4. Chapters 7 and 8 cover the integra-
Strategically located in the front and rear tion of the firing system and furnace in utility
walls, the OFA nozzles provide turbulence for and industrial boiler designs. The equipment
mixing and ensure complete combustion of the for injecting fuel into fluidized beds is de-
volatile gases. The OFA is at a pressure of 20 to scribed in Chapter 9. Firing equipment exclu-
30" W G for sufficient penetration. sively oriented to shipboard service is included
in Chapter 10, Marine Boilers.
Chapter 11, Pulverizers and Pulverized-Coal
MORE ON FUEL FIRING Systems, focuses primarily on how coal is re-
Other aspects of preparing, transporting, fir- duced in size and transported to furnaces.
ing, and burning fuel in steam-generator fur- Chapter 13,OperationalControl Systems, deals
naces are covered in complementary chapters of at length with safety and flame-detection systems
this text. that are so important to the modern firing equip-
The processes of combustion and the forma- ment that has-been presented in this chapter.

REFERENCES Annual AICHe Meeting, New York, November 13-17, 1977;


published as Combustion Engineering publication TIS-
'Otto De Lorenzi, ed., Combustion Engineering - a Refer- 5140, windsor, CT:Combustion ~ ~ ~ , 1977.
i ~ ~ ~ ~ i
ence Book on Fuel Burning and Steam Generation, First
Edition, Nelv Yo&: Combustion Engineering-superheater, Heap, M. R , et a]., "Burner Design principles for ~ i n i -
Inc., 1947. mum NO.,. Emissions," Proceedings, Coal Combustion Sem-
inar, Research Triangle Park, NC, June 19-20, 1973, Report
No. PB-224 210 (EPA 65012-73-021). Springfield, VA: Na-
BIBLIOGRAPHY tional Technical Information Service. 1973.
Bartok. William; A. R. Crawford: and G. J. Piegari. "Sys- Marshall, J. J. and A. P. Selker, "The Role of Tangential
tematic Investigation of Nitrogen Oxide Emissions and Firing and Fuel Properties in Attaining Low NO, Operation
Combustion Control Methods for Power Plant Boilers:' R. for Coal-Fired Steam Generation:' presented at the EPRI
W. Coughlin, A. F. Sarofin, and N. J. Weinstein, (eds.), Air NO, Control Technology Seminar, Denver, November 8-9,
Pollution and Its Control, AICHe Symposium Series, No. 1978; also as Combustion Engineering publication TIS-
126, Vol. 68, 1972, pp. 66-74. New York: American Insti- 5623A.
tute of Chemical Engineers, 1972. Pershing, D. W. and J. 0. L. Wendt, "Pulverized Coal
Bartok, William, et al., Systems Study of Nitrogen Oxide Combustion: The Influence of Flame Temperature and Coal
Control Methods for Stationacy Sources. Volume 11. Final Composition on Thermal and Fuel NO,:' Sixteenth Sympo-
Report. June 20, 1968-November 20, 1969. Report No. PB- sium (International) on Combustion, Massachusetts Insti-
192 789 (GR-2-Nos-69). Springfield, I!%: National Techni- tute of Technology, Cambridge, MA, August 15-20, 1976,
cal Information Service, 1969. pp. 389-399. Pittsburgh: The Combustion Institute, 1976.
Bueters, K. A., et al.. "NO, Emissions from Tangentially Sarofim, A. F., et al., "Strategies for Controlling Nitrogen
Fired Utility Boilers-A Two Part Paper:' Part I, "Theory," Oxide Emissions During Combustion of Nitrogen Bearing
by K. A. Bueters and W. W. Habelt; Part 11, "Practice:' by C. Fuels," AICHe Symposium Series No. 175, 74, 67. (1978).
E. Blakeslee and H. E. Burbach, presented at the 66th An- Selker, A. P. and R. L. Bunington, "Overfire Air Technol-
nual AICHe Meeting, Philadelphia, November 11-15.1973. ogy for Tangentially Fired Utility Steam Generators Burn-
Chen, S. L., McCarthy, J. M., Clark. \V. D.,Heap, M. F?, ing Western U. S. Coal:' presented at the 2nd Symposium
Seeker. W. R.. and Pershing. D. W.,"Bench and Pilot Scale on Stationary Source Combustion, New Orleans, August
Process Evaluation of Reburning for In-Furnace N0,Reduc- 29-September 1,1977; published as Combustion Engineer-
tion," Twenty-First Symposium (International) on Combus- ing publication TIS-5242, Windsor, CT:Combustion Engi-
tion. Pittsburgh: The Combustion Institute, 1986. neering, Inc., 1977.
Frey, D. J. and M. S. McCartney, "The Formation. Meas- Taylor, B. R., "Reactions of Nitrogen Species In Fuel-Rich
urement, and Control of Nitrogen Oxides in Existing Fossil Flames", Sc.D., Department of Chemical Engineering.
Fuel Fired Steam Generators," presented at the 28th Engi- M.I.T., 1984.
neering Conference, TAPPI, Boston, October 9-11, 1973; Zel 'Dovich, Ya. B., P. Ya. Sadarnikov, and D. A. Frank
also as Combustion Engineering publication TIS-3598. Kamenetskii, Oxidation of Nitrogen in Combustion. Trans-
Habelt, W. iV.. "The Influence of the Coal Oxygen to Coal lated by M. Shelef. Moscow-Leningrad: Academy of Sci-
Nitrogen Ratio on NO, Formation," presented at the 70th ences of the USSR, 1947.
CHAPTER 13

Operational Control Systems

AA power plant may be thought of as an


electricity factory. In that context, modern
power plants are among the most highly
availability of equipment is needed to stem ris-
ing operating and maintenance costs. Protec-
tion of both personnel and equipment must be
automated a n d centrally controlled and achieved, and unscheduled shutdowns have to
monitored production facilities in the world. be kept to a minimum.
As power plants began to grow in size and While obviously instruments and controls
complexity many years ago, local monitoring cannot of themselves satisfy such concerns, the
and regulation of the plant systems in a timely problems have resulted in a substantially in-
manner became impossible. Thus, instrumen- creased requirement for sophisticated instru-
tation and controls in power plants came into mentation and automatic control systems.
being to provide the ability to operate the major This chapter deals primarily with the major
plant systems from a central location (Fig. 1). control and diagnostic systems associated with
Historically, meters, gages, and lights dis- fossil-fuel-fired utility steam generators. Con-
played equipment status to the operator, while trol systems for the various types of steam
recorders made a permanent record of plant generators use$ in stationary industrial appli-
performance. Remotely operated air cylinders cations are also discussed.
and electric motors gave plant operators the ca-
pability of responding quickly and efficiently
to changing plant requirements. More recently,
INTERLOCKS AND SAFETY
cathode-ray tubes (CRT's) have _replaced the SYSTEMS
panel-board instrumentation, to link the oper- The concept of a centralized control room
ator with past and present process information was a big step forward in power-plant control.
through sophisticated microprocessor-based Nevertheless, as first conceived and executed,
distributed control hardware. remote-manual systems relied entirely upon
Since the early days of remote operation, the operator judgment and response.
generation of electricity has become a very The multiplicity of operating steps required
complicated business. High energy costs de- for safely and properly admitting fuel to a fur-
mand that as much electricity as possible be ex- nace (or the removing of incompletely burned
tracted from the fossil fuel consumed. Higher fuel from a furnace) leaves considerable lati-
--
COmuslmN
OpurdknrlControlSystems

Rg.7 Instrumentation and controls permit operation of major power-plant systems from a central loca-
tion. Control-room meters, gages, lights, and CRT's display equipment status; recorders permanently
chronicle plant performance; and diagnostic systems monitor and evaluate both status and performance.

tude for operator error, if left solely to her or mulated in only one to two seconds, it is appar-
his judgment. Determining the adequacy of ent that human reaction time is inadequate, to
igngtion-energy levels is another area that say nothing of the need for an instantaneous
should not be left to operator discretion. Con- decision-making capability.
sidering that a major furnace explosion can The recognition of these limitations to a com-
result from the ignition of unburned fuel accu- pletely operator-dependent mode of operation
COMBUSTION
Operational Control Systems

led to the development of automatic protection ture, decreased p cessure, excess fuel, inert
systems that are designed to minimize the risk gases) reduces the ossible explosion pressure.
of furnace explosions. Furnace-exploston prevention should be
aimed at limiting tlie quantity of diffusedflam-
mable fuel-air mixture that can be accumulated
in a furnace in proportion to the total volume
FURNACE EXPLOSIONS and the mechanical strength of the furnace.
Furnace explosions are rare and unlikely. While fuel and air are being admitted to a
When compared with the total number of unit furnace, there are only three possible methods
operating hours, the hours lost because of ex- of preventing excessive flammable diffused
plosions are minimal. This desirable situation accumulations:
exists because (a) furnaces are supplied with an I. Igniting all flammable mixtures as they are
explosive accumulation only during a small formed, before their excessive accumulation.
percentage of their operating lives and (b)just a
minute part of those explosive charges receive 2. Diffusing all flammable mixtures with suffi-
sufficient ignition energy to actually cause an cient additional air, prior to ignition, to a point
explosion. beyond the diffused flammable-mixture ratio;
In suspension burning. the primary control and accomplishing this with a sufficient degree
of the combustion process is the admission rate of diffusion before a critical percentage of the
of fuel and air to a furnace, independently of furnace volume becomes occupied by the flam-
each other.!The dynamic response of the com- mable mixture.
bustion reaction, however. depends on the dif-
fusion of the fuel and air to a flammable limit, 3 . Supplying an inert gas to diffuse simulta-
and the elevation of this diffused mixture to its neously with the fuel and air, thereby diluting
kindling temperature. The aerodynamic diffu- the oxygen content of the mixture below the
sion of fuel and air results from both the rate flammable limit.
and method of admission. This admission flow Implementation of these preventative meth-
pattern produces diffusion mechanically by in- ods requires operator action beyond the re-
terscrubbing of the fuel and air masses. Molec- sponse, memory, and judgment capabilities of
ular diffusion is also present as a result of the the normal operator controlling a plant in the
elevated temperature level at which the com- manual mode. A fireside safeguard system must
bustion process takes place. supervise the flow and processing of fuel, air,
Furnace explosions result from a rapid rate of ignition energy, and the products of cambus-
volume increase of the gaseous combustion tion. Satisfactory boiler operation requires that
products when too great a quantity of fuel and these four ingredieItts be properly prepared, ra-
air reacts almost simultaneously in an enclo- tioed, directed and sequenced so that the fur-
sure with limited volume and strength. Avoid- nace cannot contain an explosive mixture. At
ing furnace pressures in excess of furnace the same time, the combustion process must be
enclosure design pressure is, therefore, neces- supervised to check the results. Combustion
sary to prevent furnace rupture. - must be kept efficient or the unconverted chem-
The basis for any explosion-prevention sys- ical energy may accumulate and subsequently
tem must be to limit the quantity of flammable become explosive.
fuel-and-air mixture that can exist i n the fur- The following factors influence the effective
nace at any given instant. The rate of maximum composition change of an explosive charge:
pressure rise possible during the reaction is a
function also of the available oxygen per unit The facility for mixing
volume of reactants. The effect of any oxygen- The inert material in the fuel
density diluent (nitrogen, increased tempera- The fuel-air ratio (a near-stoichiometric ratio
COMBUSllON
OponUom! Gontrd Systems
-
dmlops the highest explosion pressure) scribe the furnace opepations which provide the
The kind of fuel explosive accumulations. Ideal furnace opera-
A furnace explosion requires both sufficient tion continuously converts reactive furnace in-
explosive accumulation within the furnace and puts into unreactive products as fast as the
sufficient energy for ignition. The ignition re- inputs enter the furnace-this precludes fur-
quirements for an explosive charge are very nace explosions. However, in practical furnace
small, making it impossible to protect against firing, unfavorable operations that create explo-
all possible sources of ignition, such as static sive situations are difficult to avoid completely.
electricity discharges, hot slag, and hot furnace Several correctly timed events precede a dam-
surfaces. Therefore, the practical means of aging furnace explosion. The furnace explosion
avoiding a furnace explosion is the prevention event itself is the rapid change in composition
of an explosive accumulation. of the furnace atmosphere (not the furnace in-
The factors determining the magnitude of a puts). The change in furnace composition is
furnace explosion-mass, change in composi- not'spontaneous, and suitable ignition energy,
tion, and reaction time-are related in the ex- which can be substantially less than that re-
plosion factor. quired for continuous furnace-input ignition,
must be supplied after the explosive composi-
tion is attained.
Mass The potentially reactive furnace accumula-
Explosion Factor = tion must be formed from an earlier buildup
Furnace Volume
process which introduces reactive inputs not
Composition Change converted by oxidation to nonreactive or inert
X
Elaosed Time products. This buildup process must continue
long enough to create a damaging accumula-
tion. The accumulation composition, which
must be within the limits of flammability for
that particular fuel, is formed in one or more
Each furnace has a limiting explosion factor. basic ways.
If the conditions create an explosion factor ex-
w A flammable input into any furnace atmos-
ceeding this limit, a catastrophic explosion can
result. Any lesser reaction will produce a fur- phere (loss of ignition)
nace "puff' (a nondestructive explosion) or a A fuel-rich input into an air-rich atmosphere
temporary upset. (fuel interruption)
To protect a furnace from an explosion, a An air-rich input into a fuel-rich atmosphere
safety system must insure a minimum reactive (air interruption)
mass accumulation with a minimum available Furnace firing systems are designed to start
composition change and with a maximum reac- up air-rich by introducing fuel into an air-filled
tion time required. Only control of the compo- furnace. Main fuel is introduced after the inte-
sition of t h e furnace atmosphere offers gral ignition system has satisfied permissive
complete coverage in minimizing the explosion main-fuel interlocks that it can provide more ig-
factor. After firing has begun, furnaces always nition energy than the main fuel requires to be
contain sufficient mass to have an explosion ignited or to remain ignited. Additional air is
and control of the time factor is impossible. introduced around the primary-aidfuel mixture
Therefore, the composition change must be to take it beyond-flammable limits, if it has not
controlled to prevent furnace explosions with been ignited and reacted to inert combustion
any assurance. products; this is done to avoid a critical portion
The mechanics of furnace explosions, al- of the total furnace volume being occupied by a
though defining the actual process, do noi de- flammable mixture.
COMEUSllON
OperationalControl Systems

FLAME DETECTORS spectrum. The shape of the emission versus


- wavelength plot for rassil-furnace flames gener-
In the prevention of furnace explosions, the ally resembles the b!ack-body curve, with peak
detection of the absence of flame-while fuel is emissions being nokd which are characteristic
being admitted is the only>roper criterion for of the fuel being fired.
any control a c t i o n initiated by a flame- The light emitted by these furnace flames is
monitoring system. furth?r characterized by a fluctuating intensity,
Flame-monitoring hardware must be reliable, commonly called flicker frequency, which de-
must be sensitive enough to discern the mini- pends on the area of the flame being viewed, as
mum flame envelope, and must have fail-safe well as physical conditions at the fuel nozzle.
characteristics to avoid unnecessary trips. Reli- Fuellair ratio, fuel velocity, air velocity, and the
ability is improved by fault-detection circuits. location and effectiveness of turbulence-pro-
Various methods are.used to determine cir- ducing diffusers all influence the frequency of
cuit component failures which could cause a the pulsating intensity.
false indication of flame. Reaction time of the
ULTRAVIOLET D E T E ~ I O N
flame-detecting device must be an absolute
, minimum to prevent the accumulation of dif- In the early 196OPs,the use of ultraviolet (UV)
fused flammable reactants in the furnace fol- detectors for proof of fossil flames became prac-
lowing a loss of flame, before the furnace tical when the GeigerIMueller-tube principle
protection system can initiate corrective action was applied to flame detection. Fig. 2 shows the
to prevent an explosion. Unnecessary trips are ultraviolet detecting tube.
avoided by proper flame-safety control logic. The UV detector had a distinct advantage
The burning process exhibits many character- over previous light sensors with cadmium-
istics which can be sensed as indicators of ex- sulfide or lead-sulfide cells which were respon-
isting flame. Heat sensors, for example, in the sive to very broad bands of light intensity and
form of thermocouples and bimetallic strips
have been used successfully for many years in
small space-heating systems, though the appli-
cation of these devices to larger installations Magnetic Shutter
has generally not been practical.
Another characteristic of the burning process
used for flame detection is the electrical-con-
duction capabilities of the ionized gases of a
flame. An electrical-conduction path is estab-
lished by a flame rod which extends into the
flame envelope; the ionized gases themselves
and the boiler tubes serve as the ground return
of the system. This flame-rod concept is also in
use today on smaller burners fueled by oil or
gas, but the erosive nature of suspension-fired
pulverized coal makes this type of flame detec-
tion impractical for that fuel.
Especially in large suspension-fired burner1
I I \I I I
I I
furnace installations, the most practical charac-
Fig. 2. An ultraviolet detecting tube. The hterior
teristic to sense for proof of flame has proven to tube atmosphere is helium at low pressureand the
be the light emitted by the burning process. electrodes are extremely pure tungsten. m a u s e
The light emission covers a very broad spec- the special glass envelope has a low attwation,
trum and it is a continuous, rather than a line, quartz is unnecessary.
COMBUSTION
O p ~ U o n rControl
l Systems
-
had peak responses in the infrared (IR) range tion. A large voltage difference accelerates pho-
(Fig. 3). The infrared was certainly a character- toelectric electrons to the opposite electrode;
istic of the flame, but it was also emitted by hot these electrons collide with molecules of hy-
refractory, hot metal, and hot gases, any of drogen and helium, freeing additional elec-
which could cause the IR detector to falsely in- trons that collide with more molecules, setting
dicate flame intensity present. Contrarily, the off a chain reaction. This process is called a
UV radiation which is abundant in fossil flames Townsend avalanche, and the very large current
is not emitted in significant quantities from hot flow it generates is readily sensed with elec-
bodies at the temperatures encountered in tronic circuits.
boiler furnaces. UV detectors respond well to natural gas and
The UV tube works under the photoelectric- oil flames. At times, intensity reduction has
emission principle whereby the tungsten elec- been needed because of the overabundance of
trode will emit an electron when struck by a UV generated from natural gas flames as com-
photon with energy (E,,) in excess of the photo- pared to others.
electric work function (E,) of tungsten. Since a common failure mode of the tube
Because each photon of light results in only is to electrically short out, thereby giving the
one electron being freed from the electrode, am- appearance of seeing a flame, a shutter-check
plifying the electron flow to a detectable level is circuit is often used. When a pair of magnetic
necessary. The combination of hydrogen and shutters close off light in front of the detector,
helium gases in the UV tube performs this func- there should be no indication of flame.

A, Wave Length in cm
1o6 1000 'loo 10 1.0 0.1 0.01 0.001 10-6 10-9 IO-'~

-
I I
I I I I I I 1 1 1 1
I I
I I I I I I I
Micrometers I Nanometers
10,0001000100 10 1.0 0.1 10 1.0 0.1 0.01
I I I 1 1 1 1 I 7
Meters Angstrom Units X-Units
, \-

10,0001000100 10 1.0 0.1 100,00010,0001000100 10 1.0 100 10 1.0 0.1


1 1 I1 1I I
I I
1
/ / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / J ' / / / / / / / / / / / / / / / / / / / / / / / / T
---r'

I I
I I I I 1 I I I I I I I I I I I I I I I I
10-9 10-6 loo 1000 lo5 lo6 lo7
Eph. Electron Volts per P h o t o n 1 10,000
Cadmium Red Line, 6438 A
1 Micrometer (pm)=10-6meter
1 Nanometer (nm),= 10-9meter
1 Angstrom Unit (A) =lo-lometer
1 X Unit (X.U.)=lo-licm

Fig. 3. Total electromagnetic radiation spectrum, logarithmicscales


COMBUSIION
Operational Control Systems

SOLID-STATE DETECTION gases as indicative of flame. To overcome this


Solid-state light sensors transfer the light en- problem, modern scanners monitor both light
ergy of the flame to a semiconductor device intensity and frequency to detect the presence
such as a photodiode or phototransistor. Here, of flame. The frequency of the fluctuations is
the light energy raises an electron of the semi- generally accepted as being between 2 and 600
conductor to the conduction band rather than hertz. The higher frequenries are evident at the
emitting an electron from an electrode as in base of the flame or the ignition point; lower
the UV tube. Because the electrical potential frequencies originate at the more distant areas
barrier of the semiconductor is easily var- or in the "fireball", where fuel streams from
ied, a solid-state light detector can be devised many admission nozzles combine and burn in
which responds to different portions of the large tangentially fired furnaces.
light spectrum. Reliable flame-scanner design includes self-
Most commercial solid-state devices have low checking features to assure that sensor failures
allowable ambient temperatures (around 70C do not result in false information. This empha-
or 160F), whereas burner windbox tempera- sis on assuring the validity of the "flame" or
tures can run above 260"C (500" F). For this rea- "no-flade" output of the detector is a vital step
son, they are usually mounted in the cooler part in preventing furnace explosions.
(at the back) of the burner. To transmit flame Proper and accepted proof of flame requires
light from the hot burner front to the cooler lo- the simultaneous generation of three permis-
cation, a fiber-optic cable is sometimes used. sives: (1)no fault, (2) a threshold intensity and
This transmission distance is generally not (3) a specific flicker characteristic. Fig. 4 shows
more than 6 ft. Commercially available fiber- these operational principles.
optic cables exhibit good transmission in the
visible and near-IR spectrum. Special high-
priced cables are available for the transmission
of UV and for the IR spectrum. In those in-
stances where line-of-sight transmission is
available, as with fixed burners, fiber-optic ca-
bles might not be required. To assist in keeping
scanner-head temperatures low and to prevent ------
Remote Scanner
particulate matter from getting into the scanner,
purge or cooling air is often used.

GENERAL SCANNER PERFORMANCE

For the past two decades, ultraviolet flame


scanners have been the most widely used flame
detectors on large tangentially fired boilers.
During the oil crisis of the 1970's, operating
coal-fired boilers at low loads without the use
of expensive support fuel became necessary.
When firing coal at low rates, the emission of
UV radiation is reduced; also coal dust and
combustion products absorb UV. As a result it
is difficult at low firing rates to detect a coal
Intensity Fault Int. IxF Freq. Freq. Flame
flame with a UV scanner.
As indicated earlier, infrared and visible- ~ i g4. Furnace corner functional diagram showing
light detectors may falsely sense hot material or principle of operation of SAFE FLAMEmI
. COMBVSllON
OpemtIo~IControlSystems

A complete scanner system for tilting burners This task can be performed adequately only by
includes a scanner-chassis assembly as in Fig. a dedicated protective system such as a furnace
5, a scanner-head assembly as in Fig. 6, and a safeguard supervisory system.
cable to electrically connect the two. A guide THE ROLE OF THE SUPERVISORY SYSTEM
tube provides both a cooling-air and a semi- IN THE STEAM-GENERATING PROCESS
rigid path for the scanner-head assembly.
The scanner-head assembly consists of a Experience has shown that the furnace safe-
light-collecting head, a flexible hose that moves guard supervisory system cannot be treated as
with the tilts of the fuel nozzles, and a housing an auxiliary function of the steam-generator
which contains the scanner-head electronics. process (e.g: combustion, feedwater, and steam
The flexible hose contains a fiber-optic cable temperature) control systems. Rather, the fur-
which passes the flame light from the head nace safeguard supervisory system is a separate
back to a photodiode in the scanner-head elec- and distinct system, more closely allied to the
tronics circuit for signal conditioning. firing-system digital actions than to the process
The scanner-chassis electronics evaluates the controls.
flame-signal levels for intensity and frequency, The most important design criterion of a
to determine the presence of flame. Also, it con- fuel-firing protective system is that it be tai-
tains fault-detection circuitry. Chassis outputs lored specifically to the requirements and oper-
include a flarne-relay contact and fault-relay ating characteristics of the firing system.
contact as well as intensity and frequency SYSTEM ORGANIZATION
flame-signal outputs. These signals monitor
the flame status. The components of the FSSS system can best
As some of the basics of furnace explosion be divided, for discussion purposes, into four
prevention have been discussed, protection sys- sections (Figs. 7 and 8): (1)the operator's panel,
tems can now be described in more detail. (2) driven devices, (3) sensing elements, and (4)
the logic system.
The operator's panel contains all the com-
FURNACE SAFEGUARD mand devices (panel insert with lights and
switches, or CRT a n d keyboard interface)
SUPERVISORY SYSTEM required to manipulate t h e firing-system
One of the control systems furnished on al- equipment and to monitor the status of
most all modern fossil-fuel-fired steam genera- this equipment.
tors is a protective system which may be called The driven devices are primarily those by
burner control, burner management, fuel-firing which fuel and air are admitted to the steam
safety, or, when supplied by Combustion Engi- generator. Typical examples are valve operators
neering, an FSSS@furnace safeguard supervi- (oil and gas firing). feeder and pulverizer motor
sory system. For a fluidized-bed boiler, the starters (pulverized-coal firing), air-damper
protective system is designated the FBSSB fluid- drives, and fan-motor starters.
ized-bed supervisory system. The main Sensing devices include not only position in-
function of such a system is to prevent the for- formation on the driven devices, but also such
mation of an explosive mixture of fuel and air items as fuel pressures, temperatures and flow,
in any portion of a boiler during any phase of and the presence of flame.
operation, including start-up and shutdown. The heart of the furnace safeguard supervi-
Preventing damage to the steam generator sory system is the logic system. All operator-
andlor the firing-system-components requires initiated commands are routed to the logic
simultaneous, continuous monitoring of a sub- system, and the status of all sensing elements is
stantial number of pammeters and, at times, in- monitored continuously by the logic system.
stantaneous reaction to a hazardous situation. Operator commands are passed on to the driven
COMBUSnON
Opentionat Control Systems

a& fault-alarm outputs

Fig. 6 SAFE FLAME Iflame-scanner head assembly for tilting fuel nonles
COMBrnON
Opedona1 Control Systems

m flame failure
loss of logic power to FSSS system
m loss of primary and redundant processors
(if applicable)
m operator's emergency -trip push buttons
depressed

Flame Scanner DEGREES OF AUTOMATION


The FSSS arrangement discussed so far is
commonly called a remote-manual system.
With this type of system, the operator initiates
Flame Scanner the start-up and shutdown of each individual
piece of equipment from a remote operating
panel. The system logic insures that the oper-
ator commands are performed in the correct se-
quence and intervenes only when required to
prevent a hazardous condition.
Higher levels of automation commonly speci-
fied are "automatic" and "automatic with load
Flame Scanner programming." An automatic system allows an
operator to place in service or remove from ser-
vice a related group of firing equipment (a sub-
loop) in the proper sequence by initiating a
single command. A typical example of a sub-
Fig. 7 Typical air and fuel nozzle arrangements loop would be the feeder, air dampers, and
within a windbox
other equipment associated with a single coal
pulverizer.
In the automatic mode of operation, a single
devices only if its logic verifies that the proper operator command to start a pulverizer would
safety permissives have been satisfied. On the initiate the following appropriately timed se-
other hand, the logic will shut down equip- quence of events [provided all of the required
ment automatically whenever continued opera- permissive conditions are established):
tion would jeopardize the safety of this 8 associated ignition system placed in service
equipment or the steam generator. pulverizer motor started
A list of the typical conditions that would
hot-air gate opened
cause an emergency shutdown (trip) of a recir-
culation-type steam generator is as follows: m pulverizer airflow and temperature controls
released for automatic operation
a low airflow
m feeder started
m loss of all forced-draft fans
feeder speed control released for automatic
m loss of all induced-draft fans
operation
loss of all primary-air fans
associated windbox dampers released for au-
turbine trip
inadequate waterwall circulation
tomatic operation .- _ A

As the required load on the steam generator is


high furnace-gas-side pressure varied over a wide range, firing system sub-
m high superheater-outlet pressure loops are placed in, or removed from, service to
COMBmTlON
Operational Control Systems

: Operator Panel
CE
for Mounting on Control Room
Purchaser's Console

I I I I I I
Inputs-J I I I I I
I I I I- -C-E lgnltors I
C-E Scanners Local
Hardware
Feedback Devices- J 1 L-Positioning Devices (at Bo~ler)
I I
L - Outputs(ToAnnunciator, Etc.)

Fig. 8 FSSSO (furnace safeguard supervisory system) arrangement

maintain the most stable flame conditions and out of prescribed safe sequences and will shut
make the most efficient use of the firing-system down equipment if prescribed operating prac-
components. With the inclusion of the load- tices are not followed. Removing ignitors too
programming feature, the FSSS system will take early, for example, would result in the shut-
care of this function automatically as steam- down of the associated main fuel.
generator load demand changes. The specific safety interlocking included in
the furnace safeguard supervisory system de-
BASIC SAFETY FUNCTIONS
pends on the physical characteristics of th6 fir-
Although the furnace safeguard supervisory ing system and type of fuel or fuels being fired.
system does not regulate the fuel and airflow All safety systems of this type, however, are con-
auantities and does not, in most cases, initiate cerned with the following functions:
t-he start-up or normal shutdown of firing-sys-
a prefiring purge of the furnace
tem components, it does exercise authority over
both the operator and the process cant 01s establishment of the appropriate permissives
,

through its safety interlocking features. for firing the ignition fuel (i.e., purge complete,
If, for example, the combustion control Pressure within limits)
should drop the airflow below the minimum rn establishment of the appropriate permissives,
value (typically 30 percent) permitted during including ignition permissives, for the main
start-up, the safeguard supervisory system (load-carrying) fuel
would trip the fuel automatically. Similarly, it m continuous monitoring of firing conditions
will not permit the operator to start equipment . and other key operating parameters

13-11 !!!I!!
COMBUSTION
Operational Control Systems

emergency shutdown of portions or all of the firing conditions during the steam-generator
firing equipment when required start-up phase of operation.
m a postfiring purge of the steam generator FLAME MONITORING
The purpose of the prefiring purge is to be The C-E tangential-firing configuration
sure that any unburned fuel that may have accu- (Fig. 9) operates during start-up with a separate,
mulated in the furnace is completely removed independent flame emanating from each operat-
prior to initiating firing. To do this, an airflow ing fuel-admission point (nozzle).Each flame is
is passed through the steam generator at a mini- monitored independently by the use of continu-
mum rating (usually 30 percent of that required ous, self-flame-proving ignitors.
for rated steam-generator capacity) for 5 min- As soon as any elevation is fired at a rate ex-
utes. At the same time, windbox dampers (Fig. 7)
are maintained in a particular configuration, the
fuel-admission devices are proven closed (or
off), and the flame-monitoring devices indicate
"no-flame." This combination of conditions will
provide the proper velocities and number of air
changes through the furnace and convection
pass to assure the removal of any fuel accumula-
tions. These purge-permissive requirements
also provide a check on the proper operation of
the air-damper, fuel-admission, and flame-
monitoring sensing devices just prior to firing.
Upon completion of the purge, the steam gen-
erator is ready to be fired. The 30-percent mini-
mum airflow requirement is maintained until the
steam generator reaches 30-percent load in order
to assure an air-rich furnace mixture during the
entire start-up phase. Fig. 9 Tangential-firing pattern at low-firing rates
Initial firing is accomplished with a group of
ignitors that have the capability of lighting the
ignition fuel with an electric spark. A flame de-
tector must be provided with each ignitor to Fuel
determine the presence or absence of a stable
flame. In the case of the C-E ignitor, the flame de-
tector is an integral part of the ignitor, and a
fuel-flow measurement is included to insure Dampers
the proper quantity of ignition energy.
Depending on the choice of load-carrying
fuel and the firing-system arrangement, the
load-carrying fuel may obtain its ignition en- Air
ergy directly from the ignitors or an elevation of Plenum
ignition fuel guns may be used as an intermedi-
ate step. On coal-fired units, for example, igni-
tion fuel is normally kept in service until two
adjacent coal elevations are being fired at 50
percent of their rated capability, thereby assu-
ring sufficient ignition energy to maintain stable Fig. 10 Tangential-firing pattern: fireball condition
COMBUSTION
Operational Control Systems

ceeding 30 percent of its design rating, the char- the dust, temperature variations, and electrical
acteristics of this firing configuration change noise encountered in a power plant. -
dramatically (Fig. 10). The thorough mixing of The normal method of powering the FSSS
fuel and air producedby the rotating fireball (vor- logic is to provide redundant AC sources to a
tex) permits ignition energy produced at one lo- transfer switch w?th the output of the transfer
cation in the furnace to support the combustion switch going to the system. To prevent a boiler
of fuel admitted at other locations. shutdown during operation of the transfer
The furnace, in effect, becomes a single switch, the AC-powered field devices are of the
burner. Under these firing conditions, multiple "energize-to-trip" type: that is, they require the
flame detectors monitor the furnace on a statisti- presence of power to close. DC power from the
cal basis. No individual fuel nozzles are shut plant battery system is also provided to the FSSS
down because of an adjacent flame detector indi- system to assure the capability of shutting off
cating "no-flame." But should insufficient flame the fuel input in the event of a loss of both AC
detectors confirm the presence of flame, the en- sources.
tire firing system is shut down. Electromagnetic relays, which have been the
The transition from start-up firing characteris- traditional building blocks of furnace safeguard
tics to fireball conditions is a padual transforma- supervisory system logic in the past, are now
tion as elevation loading is increased. The rarely built. Hard-wired solid-state logic was a
selection of the 30-percent elevation-loading successor to electromagnetic relay systems and
condition as the point where the logic is trans- has been applied to FSSS design for many years,
ferred to fireball monitoring is based on field ex- but did not assume a dominant position until the
perience and assures a completely adequate late sixties and early seventies. For a long period,
margin of safety between the two different firing the utility industry continued to judge the tradi-
conditions. tional advantages of solid-state logic (less power
During the fireball phase of operation, suffi- drain, less space required, greater speed, and no
cient ignitors in service at specified locations moving parts to wear out) to be less important
constitute proof of stable firing conditions. To than the disadvantages (higher susceptibility to
eliminate the need to keep ignition fuel in ser- electrical noise and temperature variations,
vice, however, optical flame detectors are used as more complexity, and higher cost).
the normal means of monitoring the fireball. Fig. 11 shows a typical solid-state FSSS logic
Front-fired (horizontal-burner) systems ex- cabinet. The built-in simulator provides mainte-
hibit, at all firing rates, the individual burner nance personnel with a fast, convenient method
characteristics which the tangential configura- to check the operation of the system logic with-
tion exhibits at low firing rates; that is, the flame out disturbing field wiring or, inadvertently,
produced at onefiring location does not provide operating equipment.
ignition energy for.fuel admitted at the other lo- Solid-state logic then evolved such that the
cations. The flame-monitoring system for such electrical noise and environmental problems
burners must be designed accordingly. Attempts were mastered. The widespread use of solid-
to use front-fired flame monitoring techniques state process controls has resulted in the ability
on tangential-firing configurations and vice of plant maintenance people to handle solid-
versa have met with little success. state problem-solving easily. Plug-in solid-state
modules provide an on-line repair capability not
LOGIC ACCOMPLISHMENT available to relay systems.
The logic portion of the furnace safeguard su- The additional expense of a solid-state system
pervisory system may be implemented with elec- versus an electromagnetic relay system results
tromagnetic relays, solid-state electronics, or primarily from the need to convert all incoming
computer-based programmable controllers. All signals h m the sensing-device voltage level to
these implementations must be able to tolerate the logic voltage level and back from the logic
COtdBVSllON
OpwatbuI b n t r o l Systems

Fig. 11 The solid-state-logic cabinet of an FSSS system includes a built-in simulator.


The system currently provides protection and automation for an 850-MW unit.

level to the voltage level required by the driven possible to program the system directly from
devices. (Logic devices cannot provide either logic diagrams. They are also configured to
the voltage or the current level required by the be strong in logic capability and can be pack-
field devices.) As systems become more auto- aged ruggedly enough for the power-plant
mated, however, the ratio of logic functions environment.
(inexpensive) to inputs and outputs (expensive) Although this technology has been in exist-
increases and the differential expense versus ence for a number of years, further improve-
relay logic decreases. ments, increased versatility, and wide accept-
ance of PLC's in coming years are anticipated.
PROGRAMMABLE CONTROLLERS As a result of their general popularity, a wide
Currently the predominate technique for im- range of data-communication interfaces will
plementing furnace safeguard supervisory be available so ?he PIX will be easily adapt-
system logic is the microprocessor-based able to atotally integrated informationsystem.
programmable-logic controller-(PLC).See Figs. A distributed, fault-tolerant architecture is
12 and 13. These devices are minicomputers used in a microprocessor-based FSSS system.
with a built-in compiler (translator)that makes it The distributed architecture has a multiplicity of
Operational Control Systems

Fig. 12 Inputloutput channels for a programmable system

Fig. 13 The central processing units for the programmable system in Fig. 12
--

-.13-15
COMBrnON
0 p . n t l o ~ Control
l Systems

logic controllers in modular fashion to match safety,maximum availabilityis also a target, with
the functional process modules it serves; for "on-line" maintenance capability built-in. Fig.
example, pulverizer equipment groups, fuel- 14 is a representative schematic configuration for
firing elevations, or unit functions. In this a coal-fired utility steam generator with four
architecture, each controller and associated logic controllers in the ring. Each controller
inputloutput module is considered a component serves two pulverizer equipment groups and also
with a statistically remote probability of failure. contains the logic for overallunit control. (This is
The basic design criterion of this distributed, a flexible configuration and is adjustable to suit
fault-tolerant architecture is that failure of a sin- individual plant requirements.)
gle controller, with all its logic capability, or an The functions contained in each processor
inputloutput module, will not jeopardize the module consist of two sections. One (shown as
steam-generator safety. In addition, a failure will white space) is concerned with the control and
not require the steam generator or even the given safety of the associated equipment group. The
fpnctional process module to be shut down. This other section (showncrosshatched) is concerned
design criterion is satisfied by the ring-type ar- with the redundant safety of the neighboring
rangement shown in Fig. 14. equipment group to the left. The arrows in the
Fig. 14 represents non-switched fault-tolerant ring schematic indicate the direction of proces-
architecture featuring distributed modular re- sor-to-processor redundant coverage, such as 1
dundancy. The ring-type arrangement illustrates providing back-up to 4,2to 1,3 to 2, and 4 to 3.
the concept of distributed modular redundancy The total arrangement, in viewing the ring
with identical, universal software in each mod- counterclockwise, results in having one proces-
ule. Although the primary objective is maximum sor-controlsection and two redundant safety sec-

Primary and Redundant


Data Communication Link

Software Back-Up
0Primary Control/Safety A- Scanner
System Power Distribution Redundant Safety I - Ignitor
I
Fig. 14 Typical ring-type logic-processor architecture, with distributed redundancy
CORdBVSTION
Operational Control Systems

tions per equipment group distributed i n between the low-level internal I10 bus and exter-
modular fashion. nal I10 bus served by each processor. The proces-
All combinational logic required to produce sors are, in general, operationally independent
the redundant safety action is derived indepen- of each other and obtain their information inde-
dently. Also, all field-status information to sub- pendently from their own set of dedicated 110's.
stantiate these safety actions is connected in Also, redundant 110's do not share common con-
parallel to and is processed by an independent nector structure or any other elements having the
set of input-conditioning modules. Similarly, an potential of common-mode failure. A failure
independent set of output drivers processes all of any one processor is localized and does
safety output command signals. These output not, therefore, cause misinformation in another
drivers act in parallel with the respective output processor.
drivers from the other machines to actuate the The modular system is designed so that any
selected field-driven devices. processor in the ring imposes control on its asso-
The distributed, selective modular redun- ciated equipment groups only. Furthermore,
dancy is, therefore, active onafull-time basis. No since a neighboring processor.is monitoring the
fail-over circuits are requi~edfor switching to critical safety aspects of the equipment group, an
backup sections because the backup section is already operating (different)group does not have
always in operation "on-line:' covering safety- to be shut down because its processor or associ-
related functions. Typically, each pulverizer- atedI/O has failed. Processor and interface main-
equipment group includes a pulverizer and its tenance can, therefore, be accomplished with the
motor, a coal feeder and its motor, a primary-air unit and given equipment group in operation.
supply, a secondary-air supply, associated Should both primary and redundant processors
valves and drives, dampers and drives, and feed- fail, an external monitoring circuit will initiate a
back sensing elements. trip, independent of the processor logic and con-
The notations A, B, C, D, E, F, G, and Ht fined to the associated equipment only. Emer-
shown on processor sections of the ring con- gency-trip pushbuttons can shut down the
figuration of the diagram correspond to the driven devices from plant DC battery power.
designations given the individual coal-firing The on-line replacement of a failed processor
physical arrangement. The unit section con- with a spare unit is accomplished in bumpless
tained in each processor (but used in only one), fashion using an updating technique which is
has control and safety sections dedicated to sew- automatically activated at the time of com-
ing the overall unit. The corresponding safety ponent replacement. Updating of the "new"
section in another processor provides redundant processor encompasses all the necessary
backup for all the critical unit functions. This historical data.
redundancy will, among other functions, It is important to note that, generally, redun-
backup the overall-flame-failureprotection in its dancy structures should be built in simple,
entirety, including 110. straightforward fashion in order to avoid the
The ringtype architecture (Fig. 14) provides a inadvertent introduction of common-mode
frameworkfor a very versatile range of redundant failure elements.
coverage options, both processor and 110,to suit OPERATOR INTERFACE
requirements, while maintaining the concept of
universal software in each module. Traditionally, the operator's panel located in
The principle of fault-tolerant partitioning in the control room contains the command devices,
the example given is applied in comprehensive such as switches and pushbuttons for initiating
fashion. Consequently, no common bus exists operation of firing-system equipment, and feed-
between the I10 processors of individual control- back indicators, such as lights or lighted panels,
lers. Each processor is electrically and function- which display the status of the equipment to be
ally independent and there is also isolation controlled. The availability of a communication
COMBusn.ON
Opntlonol Control Systems

link allows enhancement of the operator-ma- may be specified as a backup feature.


chine interface with a colorgraphic display. The Comprehensive error-checking procedures
framework for the CRT displays should be ar- are utilized. To further assure system integrity.
ranged in two categories: Message Silmrnaries a software buffer zone is inserted into the logic
and Colorgraphic Animated Schematics. processor application program to provide addi-
Message Summaries are primarily dedicated tional isolation between the base working
to diagnostic information allowing the operator system and the communication bus. Greater-
to identify problem areas blocking orderly start- flexibility is an additional benefit of this fea-
up or shutdown. The Colorgraphic Animated ture, which virtually sectionalizes and allows
Schematics (see Fig. 15)allow operator observa- the independent engineering and maintenance
tion of the start-up, shutdown, and operational of the base control system from the display col-
progress in graphic form, with special tech- orgraphics. The software buffer also helps to re-
niques for device simulation. duce traffic on the communication network and
Often for comprehensive visual effect, Mes- prevent overloading.
sage Summaries and Colorgraphic Animated
Schematics are combined on the same visual. It
is important to specify complete coverage with PROCESS CONTROLS
frames (pages)arranged in functjmally modular Plant operators retain the ultimate responsi-
fashion with clear directions from overview to bility for the operation and protection of both
detail. Process alarms should be grouped sepa- utility and industrial steam generators. But as
rately from hardware alarms. discussed, automatic safety systems are cus-
While the static data for the colorgraphics re- tomarily installed to relieve operators of the
sides in the graphics processor,the dynamic data task of instantaneously analyzing and reacting
resides in the Burner Management Logic proces- to a rapidly developing hazardous condition.
sors. The logic processor transmits the dynamic safety systems improve unit availability by
data to the graphics processor by real-time preventing improper operating sequences and
communication links. This data is then super- by automatically shutting down equipment be-
imposed u p o n the static display image. fore damage can occur. But acceptable avail-
Limited-scope hardwired control panel inserts ability can only be achieved by installing

Push Key to
Display Detailed
Graphics
6 Bo~lerW-U Guns Aux Air M/A
01I/Pump Fan M/A Fuel/Atr M/A

Fig. 15 Typical FSSS CRT Animated Schematics Screen


COMBUSTION
Operational Control Sfitterns

control systems to prevent the plant-controlled Ideal for supercritical units, the coordinated-
variables from reaching the deviation from nor- control system is also well-suited for subcritical
mal values which result in safety system action. drum-type units. Its fundamental objective is to
The continuous, automatic regulation of con- operate the steam generator and turbine genera-
trolled variables is the functi-on of the process toras an-integrated unit in order to maintain the
control systems. process control variables (unit generation,
Although it is still common to divide the steam pressure, flue-gas oxygen, furnace draft,
process controls for a large steam generator and steam temperatures) within acceptable
into subsystems (such as combustion control, limits. The system operates the unit in an inte-
feedwater control, and steam temperature), a grated (coordinated) manner by developing a
coordinated approach to process control has unit load demand (ULD) signal in the unit load
proven to be the most effective technique to control (ULC),and transmitting the ULD signal
achieve optimum boiler performance. simultaneously to both the steam-generator fuel
and air control and the turbine governor-valve
BOILER-FOLLOW SYSTEMS
.. control. Fig. 16 shows a typical control-room
For many years, the most common process operator interface for the unit load control in a
control system employed on subcritical drum- coordinated-control system.
type units was the "boiler-follow" system which Fig. 1 7 shows the functional design arrange-
relies heavily on feedback control principles. ment of a coordinated-control system. This de-
With a boiler-follow system on a subcritical- sign illustrates that the ULD signal, which
pressure qnit, a change in required electrical represents generation demand, goes directly to
generation results in the following events: the steam-generator input variable as well as to
the turbine governor. This parallel control ar-
1. The turbine control valves are repositioned
rangement is based on the principle that the
to establish the new generation level, at the ex-
only way to permanently change unit genera-
pense of a change in steam-generator energy
tion is to change the energy output of the
storage level.
steam generator.
2. Changes in steam flow initiate changes in the
The presence of any error between required
flow of feedwater, fuel, and air on a feed-
output and actual generation will bias the
forward basis. Fuel and air are further modified
steam-generator and turbine-demand signals in
by the feedback of throttle-pressure -deviation
order to recalibrate the system for cycle
from setpoint, which is an indication of the en-
changes. Similarly, throttle pressure error is
ergy balance between the steam generator and
used to recalibrate the balance between steam
the turbine. Feedwater is adjusted by drum:
production and steam usage. Both of these error
level deviation, which is a measure of the
signals operate on a transient basis to compen-
feedwater-flowlsteam-flowbalance.
sate for the difference in response time of the
The large energy storage of drum-type units boiler and turbine, allowing the faster respond-
allows boiler-follow systems to be very effective ing turbine to minimize generation errors by
as long as generation-level (load) changes are modifying boiler energy storage levels.
small or are accomplished slowly. Today's modern coordinated-control systems
are designed to accommodate both the U.S. tra-
COORDINATED-CONTROL SYSTEMS
ditional fixed-pressure type of operation and
The advent of the supercritical unit in the also sliding-pressure type of operation. Slid-
1960's, with its relatively small energy storage, ing-pressure operation has long been popular
quickly demonstrated the limitations of the in Europe because of Europe's smaller grid sys-
boiler-follow system. The solution to this prob- tems and the resulting need for cycling and
lem was the development of the coordinated- two-shift units. Now, in the U.S., because older
control system. large units, once base-loaded, are being cycled
OpenUonal Control Systems

I I
Fig. 76 Typical operator interface for the unit load control of a coordinated-controlsystem ,

and two-shifted, sliding-pressure operation is fluenced during a unit load change by the rate
becoming more common. of change of ULD.
In fixed-pressure operation, the coordinated-
THE C-E COORDINATED CONTROL SYSTEM
control system regulates throttle pressure to a
fixed setpoint for the entire range of unit load The preceding discussion summarizes the
after start-up. The turbine governor valving basic differences between boiler-follow and co-
strokes open as unit load increases. Fixed pres- ordinated-control-type systems. The C-E Coor-
sure provides for boiler storage and thus the ca- dinated Control System (CCS) contains a
pability of the unit to more effectively respond number of additional features designed to pro-
during transient load changes without suffer- vide several layers of defense between the direct
ing excessive process-variable deviations. regulation of the variables and the automatic
In sliding-pressure operation, throttle pres- shutdown actions of the furnace safeguard
sure setpoint is ramped over most of the unit supervisory system.
load range. The turbine governor valving is Each major subsystem, such as fuel, air, or
fixed at a near-open position (normally 90 per- feedwater, contains a flow tie-back loop to in-
cent open) throughout the ramp. The 10 percent - sure the process variable will quickly match re-
position reserve allows for moderate unit load- quired output. Redundant transmitters and
change accommodation. The fixed position of comparison networks transfer the loop auto-
the turbine governor valving is temporarily in- matically to manual if a transmitter malfunc-
COMBUSTION
Operational Control Systems

devices before emerging as unit load demand.


Remote Control Room The first such device is the operator-setrate-of-
Demand
change limiter. This device prevents the unit
from accepting a load demand change at a rate
which would create instability and a resulting
MW ~ r r o r ~ r e ~ u e Bias
nc~
unit trip.
-unit Load Demand (ULD) Turbine governors automatically change unit
steam flow in response to an electrical-grid fre-
quency disturbance. To prevent the CCS from
fighting the governor, and to match the boiler
demand to the turbine action, the frequency
bias conditioner is required. This circuit sim-
ply adjusts required output to match the gov-
ernor action.
Follow Follow
Limit actions occur when the CCS detects
Turbine Fuel Air
I that one or more process variables cannot fol-
Governor Control Control low the output adjustment demand signal. If,
Control for example, a feedwater pump were out of ser-
Transfer
0 Function
vice, the limit circuit would not allow required
output to exceed the capability of the pumps
Fig. 17 Coo,rdinated-controlsystem, signal flow in service. Without this limit, firing rate would
diagram be allowed to exceed feedwater flow, resulting
in loss of drum level. The limit circuits also
tion occurs. Bypass switches permit automatic act whenever such process variables as genera-
operation while one transmitter is being cali- tion and throttle pressure deviate from their
brated. Ahead of the flow loops are the ratio required values by a preset mount. These devia-
correction loops. Flue-gas oxygen corrects h e l l tions are indications that the steam generator
air ratio. or turbine, or both, are unable to follow the
When all process loops are well tuned and desired output.
calibrated, and are functioning properly on au- An extension of the limit circuits, which is not
tomatic, the controlled variables will be main- shown on Fig. 17, is the run-up and run-down
tained well within acceptable limits. circuits. These circuits act to return the required
Various limit circuits are provided to take output within fhe capability of the unit when a
care of the times when this desirable condition change in boiler-unit conditions occur. For ex-
does not exist. ample, if all coal feeders are operating near maxi-
In the case of fuel and air matching, a cross- mum output and one feeder trips, the unit cannot
limit circuit is provided which does not permit maintain its existing load. The run-down circuit
fuel demand to exceed measured airflow (plus would automatically reduce load to a value
tolerance) and does not permit airflow demand within the capability of the existing feeders.
to drop below measured fuel flow (plus toler- The run-back actions shown next are simply a
ance). This circuit is most commonly activated more dramatic version of a run-down. The loss of
when a malfunction causes airflow and fuel- a major piece of auxiliary equipment such as a
flow regulating devices to follow demand at feed pump or forced-draft fan may reduce the
different rates. load-carrying capability of the unit to 50-60 per-
Referring again to Fig. 17, note that the "output cent of maximum continuous rating. When such
adjustment signal" (the desired generation value an equipment loss is detected, the run-back cir-
established by the operator or the load-dispatch cuit very rapidly reduces the required output sig-
system) must pass through several conditioning nal to a value within the capability of the
COMBUSTION
OpenUond Control Systems

remaining equipment. Without such a circuit, a separate and independent calculations of fuel/
unit trip would almost certainly result. air ratio. Fig. 18illustrates the fuellair ratio mon-
One final protection circuit, which is the last itoring concepts. If both calculations verify that
line of defense designed to act before the safety- this ratio has exceeded allowable limits, the devi-
system limits are reached, is the deviation-limit ation-limit system directly operates the control
system. This system cpntinuously makes two loops torestoreapermissibleratio. This system,
which overrides manual control, would nor-
100- mally activate only when the operator has made a
serious mistake or an automatic-control compu-
tational element has failed.
75 -
STEAM-TEMPERATURE CONTROL
Steam-temperature control is accomplished
on C-E suspension-fired pulverized-coal units
by a combination of fuel-nozzle tilt positioning
and superheater (SH)and reheater (RH) desuper-
heating sprays.Steam temperature is maintained
by allowing fuel-nozzle tilts to respond to the
lower of either SH or RH outlet temperatures,
0 25 50 75 100 with sprays responding to the higher.
% Fuel Flow Desuperheating spray control is a cascade type
Fig. 18 The deviation-limit system is a protection control. An "outer-loop" controller associated
circuit which continuously monitors fuellair ratio with final steam outlet temperature sets the set-
and, if needed, directly takes action to restore a point for an "inner-loop" controller, which con-
permissible ratio. trols desuperheater steam-outlet temperature.
Fig. 19 shows a typical primary steam-tempera-
To ture control scheme.
Temperature Turbine Basic boiler design provides for the reheater to
Measurement
be controlledby heat redistribution devices. The
several boiler manufacturers have developed nu-

1 I
Finishing merous mechanisms for this purpose, including
Superheater
flue-gas bypassing, gas proportioning, and ex-
cess-airvariation. Fig. 20 shows three techniques
Temperature which C-E uses most commonly: tilting nozzles,
Measurement desuperheating sprays, and on oil-and-gas fired
units, gas recirculation. Only during unusual
conditions is reheater desuperheating by water
spray used, because of its deleterious effect on
Desuperheater Spray heat rate. On coal-fired units, fuel-nozzle tilting
I
To Control Angle is the most common mechanism.
of Tilting Fuel Nozzles
(If Needed to Raise AN OVERVIEW
Finishing Superheater Initial
Outlet Temperature) Superheater Primary measuring devices, transmitters, in-
dicators, recorders, annunciators, indicating
lights, and CRT -graphic displays can be inte-
I I grated into a syste& which permits plant oper-
Fig. 19 Coordinated-control system, primary- ators to continuously and conveniently monitor
steam-temperature control plant operating conditions. Push buttons,
COIdBUSllON
Operational Control Sphmrs

rl Reheater
Setpoint

Reheater

-"
-I I
Nozzles

Recirculat~onFan M
(Optional)
yf=-kl

Block Valve
Setpoint
Measured Value (Feedback)
Positioning

High-Pressure Turbine

Fig. 20 Three reheat temperature control techniques commonly used by Combustion Engineering

switches, manual-loading stations, and CRT key- A well-designed automation system, with
boards can be combined with pneumatically and both firing system and process controls, will op-
electrically powered regulating devices (such as erate the unit in the same manner that the plant
valves and dampers) to provide the capability of equipment designers would operate it, if they
starting up, maneuvering, and shutting down a were given the opportunity to do so. It is vital,
steam generator from a central location. therefore,that the control-systemdesigners thor-
Using process control systems results in more oughly understand the process requirements
precise control, thus increasing plant productiv- and limitations and that the control systems are
ity and reducing cycling-life expenditures tailored to the specific equipment and plant-
caused by process variable excursions. When a operational requirements.
sophisticated process control is employed, such
as the described Coordinated Control System, INDUSTRIAL BOILER
the steam generator and turbine generator act as a
coordinated unit to further improve unit tran- OPERATIONAL CONTROLS
sient response and productivity. The CCS also Controls for industrial boilers of the types de-
provides several layers of limit systems designed scribed in Chapter 8 serve the same overall pur-
to improve unit availability by preventing a pro- poses as controls for utility boilers. Designers of
cess deviation from reaching a safety-system both types of systems are concerned with balanc-
limit. Today's modern designs implement the ing boiler inputs and outputs of mass and energy,
CCS using computerized distributed systems. remote operation, precise control, transient re-
Safety systems, such as the FSSS system de- sponse, and operating ease, as well as efficiency,
scribed earlier, also contribute to plant automa- safety and reliability. The principal differences
tion while performing their primary function of between utility and industrial control systems
protecting both plant personnel and equipment. result from industrial plant steam requirements,
COMBmnON
Operational Control Systems

types of fuels and firing equipment, and histori-


cally divergent design practices. The following
sections describe these distinguishing charac-
teristics in greater detail.
PLANT STEAM REQUIREMENTS
Industrial-plant steam requirements serve lo-
cal needs for direct process use, thermal power,
and mechanical power (which may include
power to drive electrical generators). The re-
quired steam conditions vary from low-pressure
saturated steam to high-pressure superheated
steam depending on the application.
Process plants, which often have many steam
consumers encompassing all of the above uses,
supply steam to the Grious users through a sys-
tem of steam distribution headers. Steam is
generated at conditions to meet the highest-
pressure requirements and then is cascaded
from the main steam header through pressure-
regulating valves to intermediate- and low-
pressure headers.
A cogeneration cycle, is described in Chapter
1,uses steam generated at high pressure and tem-
perature for expansion through a hck-pressure
turbine generator to produce electrical power. Fig. 21 Cross-limited-metering combustion-
The turbine exhausts into distribution headers control system, single fuel
for plant thermal and mechanical power needs.
In effect, the turbine generator acts as a pressure- consumers in an industrial plant, it ii usually not
reducing valve for the plant steam consumers, practical to feed-forward a load demand to coor-
and the industrial-plant consumers, by using en- dinate boiler control with the control of steam
ergy that is lost in a typical utility generating consumers. The concept of a coordinated control ,
station, function as condensers in the steam cy- system is generally not applied to industrial boil-
cle. In other plants, a condensing turbine with ers because they are not dedicated to a tyrbine
controlled extraction may be the economical generator. Figs. 2 1 through 24 show typical
choice, depending on such factors as seasonal operational-control sub-systems. In the indus-
plant steam demand and prices negotiated with trial plant, the main steam header pressure is an
the electrical utility for purchasing the cogenera- index of plant load, and a master pressure con-
tor's excess electrical power. troller sets the demand for firing rate for boilers
Load swings in industrial plants vary accord- supplying steam to the header (see Fig.2 1).This
ing to plant needs and, in some plants, may be is a feedback control loop similar to the boiler-
quite severe, exceeding 10 percent of maximum follow system described earlier in this chapter.
continuous rating per minute. Industrial boilers Note that industrial plants commonly have mul-
must have greater maneuverability than utility tiple boilers supplying steam to the same main
boilers in responding to load changes without steam header. In many plants a form of feed-
great upsets in steam pressure, drum level, and forward control is incorporated in the master
steam temperature. controller scheme in which the total steam flow
Due to the multiplicity of steam andlor power from all boilers is the feed-forward demand.
COMBUSTION
Operaticnal Control Systems

Furnace- Furnace- Steam Feedwater


Dray Airflow Draft Flow Drum-Level Flow
Transmitter Transmitter Transmitter - Transmitter Transmltter Transmitter

Control
Point

Damper Operator

Single-,Element Two-Element

Fig. 22 Furnace-draft control system Fig. 23 Three-element feedwater-flow control


system

SH Outlet lnterstage SH Outlet lnterstage SH Outlet Airflow


Temp.Trans Temp. Trans. Temp. Trans. Temp.Trans. Temp. Trans. Trans.

Outlet-Temp.
Controller

,To Spray Water Control Valve


@ Single-Element @ Two-Element @ Three-Element

Fig. 24 Qpical steam-temperature control systems

In m u l t i p l e - b o i l e r p l a n t s , t h e o p e r a t o r load-allocation schemes in use that vary in


usually establishes the sharing o f l o a d among complexity up t o a n d i n c l u d i n g the lowest-
b o i l e r s . T h e r e are a l s o several a u t o m a t i c operating-cost energy-management scheme.
COMBUSI?ON
-onrl Control Systems

INFLUENCE OF FUEL match combustion air and fuel for economical


ON CONTROL SYSTEMS operation. Measuring steam flow and relating it
to heat input and combustionairflow are the con-
The type of fuel fired in a boiler has a great trol strategies commonly used to surmount this
effect on the combustion-control system. Con- difficulty. Controlling steam-flowfairflow ratio
trols on boilers firing gas, oil, coal, wood or bark approximates fuelfair ratio control, but it should
are designed to respond to plant load swings. be noted that there are limitations to this method.
Boilers firing municipal or industrial refuse, For example, changes in energy storage during
black-liquor recovery boilers, and certain waste load swings temporarily alter the relationship of
fuel boilers are usually operated base-loaded to heat input to steam flow. Changes in boiler effi-
optimize combustion of these difficult fuels. ciency, feedwater temperature, or boiler outlet
Waste-heat boilers usually are operated to the steam conditions also affect the relationship.
extent of waste-heat availability. This type of control system is often adapted to
Gas- and oil-fired boilers are probably the most adjust the airflow automatically to trim fuelfair
effectively controlled because the fuels are prac- ratio by flue-gas analysis.
tically homogeneous and of nearly constant den-
sity and heating value as delivered to the plant.
Continuous and nearly instantaneous flow CONTROLS FOR CHEMICAL RECOVERY BOILERS
measurement of the fuel is possible, and the fuel- Black liquor recovery boilers in pulp and pa-
firing rate is readily and precisely controlled by per mills, described in Chapter 8, are operated
control-valve adjustment. to recover spent chemicals from black liquor
The most commonly used combustion-control and to produce steam by burning the carbona-
system for gaseous and liquid fuels is the cross- ceous matter contained in it. Black liquor is
limited metering system illustrated in Fig. 21. fired in recovery boilers at a rate that is automat-
The fuel and airflow control loops in this system ically controlled to a value determined by 'the
compensate automatically for changes in air- or operator. The black liquor forms a char bed at
fuel-system resistance to flow. Continuously ac- the furnace bottom and burns in a reducing at-
tive safety constraints automatically limit fuel mosphere which promotes chemical reactions.
flow to available airflow. This control system is To maintain the reducing atmosphdre at the fur-
readily adaptable to automatic adjustment of air- nace bottom and to complete the combustion of
flow for fuellair ratio trim by flue-gas analysis. the evolved gases higher in the furnace, air is
This basic control system strategy has also been admitted to the furnace through primary, sec-
adapted to simultaneous firing of multiple fuels. ondary and tertiary air ports. The three airflow
When combustible plant-process byprod- streams are each automatically controlled
ucts can be used as a boiler fuel, burning the to maintain a fixed ratio to black liquor flow
byproducts instead of purchased fuels may be rate. Proper adjustment of each ratio establishes
economical. In such instances, the combustion- the distribution and quantity of combustion
control system may be adapted to fire the byprod- air, which is a critical factor in contfolling
uct gas or liquid fuels automatically on a prefer- the chemical-recovery process as well as the
ential basis to the extent of their availability. Such combustion efficiency.
a control strategy has beenused in many plants to It will be noted that, due to the nature of the
fire as many as four fuels in the same boiler. process, the black liquor flame is not moni-
Firing solid fuel presents a challenge because tored, but an FSSS furnace safeguard supervis-
the effective fuel firing rate and the correspond- ory system does monitor the auxiliary fuel
ing heat input and combustion air requirements burners. Oil- or gas-fired starting burners in the
cannot be directly and continuously measured. lower furnace of the recovery boiler are fired to
This difficulty requires that an inferential meas- initially dry and ignite the black liquor before a
urement of fuel-firing rate be made in order to char bed is established. These burners are also
COMBUSTION
Operatlonal Control Systems

fired to stabilize combustion conditions at low with interrupted ignitors, usually direct electric
load and-at times when the black liquor is not ignitors. For these units the FSSS system allows
burning well. For normal black liquor firing a short timed trial for ignition, after which the
- . conditions, the starting burners are not in use. ignitor is turned off and flame detectors monitor
- - However, they are subject to operation on very the auxiliary burner flame. Failure to detect
short notice, if necessary, to stabilize combus- flame any time after expiration of the time trial
tion conditions. For this reason, the furnace safe- results in immediate closing of the associated
guard system distinguishes between an auxiliary auxiliary burner safety shutoff valves.
fuel trip and an orderly shutdown of auxiliary
FIRING-EQUIPMENT CONTROL
fuel burners. Following an orderly shutdown of
the auxiliary burners, as long as airflow through As has been seen in the previous chapter,
the furnace exceeds purging airflow and as long some fuels may be burned by more than one
as all operating permissives are within limits, type of firing equipment, and the control sys-
purge credit should be maintained and it tem must be designed accordingly.
should be permissible to initiate an auxiliary For example, oil, gas, and pylverized coal can
burner start sequence when required. be either tangentially or horizontally fired.
Some recovery boilers include auxiliary-fuel- Flame monitoring of tangentially fired indus-
fired load burners located in the oxidizing zone trial boilers is as described for utility boilers in
high in the furnace. The load burners augment an earlier section. For multi-burner horizon-
steam production when black liquor is insuffi- tally fired boilers, however, each burner flame
cient for plant needs or is unavailable for firing. envelope must be monitored individually at all
The load-burner firing rate is usually controlled firing rates. The significance of this is that a
to a setpoint adjusted by the operator, and the "no flame" indication by the flame detector will
recovery boiler continues to be operated base- cause individual shutdown of the associated
loaded. Some units have combustion-control burner. Burners with flame detectprs confirming
systems designed for load burners to respond the presence of flame are continued in opera-
automatically to load swings as demanded by tion. If the combustion-control system is in auto-
the plant master controller. The control systems matic operation, it will compensate for the
automatically introduce additional air into the reduced number of burners in operation by in-
oxidizing zone of the furnace in excess of black creasing fuel heat input at each operating
liquor requirements specifically for combustion burner. In order to distribute combustion air to
of the auxiliary fuel fired at the load burners. the burners in operation, the individual burner
The FSSS flame monitoring and interlocking dampers or burner vanes must be closed at burn-
extend to load burners as well as to starting ers that are shutdown. The FSSS system can be
burners. The recovery-boiler supervisory system designed to coordinate the operation of the
is designed to operate these auxiliary burners burner air-dampers automatically.
with continuous ignitors (described in Chapter The various means of firing may require >on-
12). The interlock system requires proof that trol either of the firing equipment or closely
adequate ignition is produced by the ignitor as a associated distinctive fuel-preparation proces-
permissive to admit fuel to the auxiliary burner. ses. For example, steam-atomized oil firing re-
Loss of ignition at an ignitor results in immedi- quires control of oil temperature and atomizing-
ate closing of the safety shutoff valves at the as- steam pressure. Black liquor water content,
sociated auxiliary burner. temperature, and pressure must be controlled.
There are some exceptions to the use of con- Pulverizer coal-feed rate, primary airflow, and
tinuous ignitors for recovery-boiler auxiliary mill outlet temperature are regulated. For
burners. In response to the scarcity of premium spreader stokers, feed rate and overfire air are
fuels for ignitors in the mid-197o1s,some recov- controlled; undergrate air distribution, grate
ery boilers were equipped with burners started speed, and distributor speed are also adjusted
COMBVSnON
0p.nUon.I Control Systems
-
by the operator. combustor. The combustor differential pressure
The chosen fuel and means of firing it can is measured and controlled by varying the rate
also affect the boiler control system by its dy- at which ash is drained from the FBHE.
namic responsiveness. Consider the inventory Oil- or gas-fired starting burners operate to
of unburned fuel resident in a furnace in nor- increase the combustor temperature gradually
mal operation at any given instant. At equiva- and at a low rate in order to protect the refrac-
lent firing rates, it can be seen that pulverized tory during start-up. The starting burners are
coal (fired in suspension) results in a far horizontal burners which are operated with
smaller inventory than spreader stoker firing flame monitoring and safety interlocks similar
over a grate, and several orders of magnitude to those reqtiired for horizontal burners in con-
smaller than for underfeed, traveling grate, and ventional boilers. The starting burners are re-
mass-burn refuse firing. The response of the quired to raise the combustor temperature to a
boiler to changes in fuel feed rate to the furnace level exceeding the auto-ignition temperature of
is much faster for firing systems with a small the main fuel. This is a key firing permissive for
inventory of finely divided fuel than for firing the main fuel interlock in the fluidized-bed
systems with a large inventory of large pieces of FBSS@supervisory system.
fuel in various stages of drying, devolatiliza- The CFB combustor includes oil- or gas-fired
tion, and burning. Firing systems with a large burner lances designed to provide a fuel input
fuel inventory are more responsive to changes to the combustor in the event of problems with
in combustion airflow than in fuel flav, so it is the solid-fuel feed system. The combustor tem-
desirable to apply firing-rate demand changes perature must exceed the auto-ignition temper-
to the air input first and to retard changes in the ature of the boiler lance fuel as a permissive to
fuel input. fire the burner lances.
Key safety functions of the FBSS system are
CONTROL OF CIRCULATING FLUIDIZED-BED BOILERS
a prefiring purge of the furnace,
Circulating fluidized-bed (CFB) boilers, establishment of the appropriate permissives
which are described in detail in Chapter 9, in- for firing the starting burners,
clude many significant features of operation
8 establishment of the appropriate'permissives
that the control system designer must consider.
for firing the main fuel,
In its basic elements, the combustion-control
system for a CFB unit is a cross-limited meter- establishment of the appropriate permissives
ing system similar to that shown in Fig. 21. Pri- for firing the burner lances,
mary air and secondary air are individually continuous monitoring of firing conditions
controlled combustion-air streams that are and other key operating parameters, and
staged as a fun'dtion of firing rate for 'effective emergency shutdown of portions or all of the
distribution. Seal-pot and fluidized-bed heat firing equipment when required.
exchanger (FBHE) fluidizing air streams pro-
DIVERGENT DESIGN PRACTICES
vide additional combustion air and are meas-
ured but not modulated. Oxygen in the flue gas Industrial boilers are usually smaller in scale
is measured and automatically adjusts fuel feed and less complex than electric-utility boilers.
rate for fuelfair ratio trim. It is important to In many industrial plants, an individual boiler
maintain the combustor temperature within a may be less critical to the plant operation than a
narrow band. The combustor outlet tempera- utility boiler is to power-system operation. In
ture is controlled by regulating the flow of ash the continuing evolution of boiler control de-
to the FBHE, thereby affecting the distribution signs for industrial and utility boilers, it is un-
of heat absorption in the unit. Sulfur dioxide in derstandable that some divergence in design
the flue gas is measured and controlled by ad- practices has occurred. As might be expected,
justing the rate of alkaline-sorbent feed to the then, control systems for most industrial boilers
COMBUSPION
Operational Control Systems

are less complex than for utility boilers. tion head than the boiler structure is capable of
One of the fundamental differences is the withstanding. Next, through control malfunc-
frequent application of "de-energize-to-trip" tion andlor operator error, establish circum-
design to industrial boiler controls. The vari- stances that result in this pressure capability
ous control elements to be used in a control sys- being applied to the structure. An-exaniple
tem are analyzed to determine their behavior would be opening the dampers on an operating
during loss of power and during their most ID fan with the forced-draft (FD) fan dampers
probable mode of failure. The control system is closed, which can result in a destructive nega-
then designed with components selected to tive pressure with the boiler not being fired.
position the final elements in a process "safe" The second mechanism, the so-called flame
position or to shutdown in case of loss of power collapse or flameout effect, is not generally
or component failure. understood. As a matter of fact, the unfortunate
In many multiple-boiler industrial plants, the use of such terms as flame collapse has led to
shutdown of one boiler does not greatly affect many distorted conceptions of the physical
plant operation, so redundant boiler controls reality.
and auxiliary equipment have generally not It is vitdly important that the following ex-
been applied to industrial boilers. It follows planation for the negative-pressure excursion
that runup, rundown, and runback circuits also which follows a fuel trip and loss of furnace
have little application in most industrial-boiler flame be understood, because only through a
control systems. basic knowledge of this mechanism can pitfalls
Nevertheless, each boiler application must be and preventive techniques be realistically
carefully evaluated because, in some cases, the evaluated.
boiler is so critical to plant operation that ex- The physical state of the gases in a furnace or
ceptions to usual design practice are warranted other subsystem at any instant in time can be
in order to increase availability of the unit. In- described by the Perfect Gas Law as follows:
deed, for this reason, many industrial-boiler
control systems have been designed according
to utility-boiler control practice. PV = MRT
where: P = absolute pressure
V = volume of system under consideration
M = resident mass (not mass flow)
FURNACE IMPLOSIONS R = the universal gas constant
T = absolute temperature,
Earlier in this chapter, furnace explosions all in consistent units
and the techniques to prevent their occurrence (21
were discussed. In the mid-1970's, a new prob-
lem, which came to be known as a furnace
implosion, appeared. Before discussing the im- Because V is fixed and R is approximately con-
pact of the implosion phenomenon on steam- stant, P is directly proportional to the product
generator control systems, the fundamental MT. Thus, for two different conditions of pres-
nature of the problem should be examined. sure and temperature in a given boiler system,
this approximate relationship holds:
THE IMPLOSION PHENOMENON
Two basic mechanisms can cause a negative-
pressure excursion of sufficient magnitude to
cause structural damage. The first of these
mechanisms is well understood.
Simply attach to a boiler an induced-draft During steady-state operation, P is held con-
(ID) fan that is capable of producing more suc- stant at approximately atmospheric pressure
COMBUSTION
Opniioml Control Systems
-
by balancing the resident mass M and the exist- perature drop, the pressure in the furnace starts
ing temperature T. Furnace temperature in a to decrease (Fig. 25).
steam generator is not directly controlled and If the resident mass were to remain constant
depends on the thermal balance between the in quantity, the absolute pressure in the fur-
heat in (in the form of burning fuel and heated nace would drop in direct proportion to the ab-
air) and the heat out (in the flue gas and heat solute temperature drop. A gage pressure of
transferred to the pressure parts). The resident -1.0" WG is equivalent to 406" WG absolute.
mass is automatically balanced by controlling Thus, with a constant resident mass, a 10 per-
the flue gas flow out of the boiler to maintain a cent change in absolute temperature would
given furnace pressure. cause a 10 percent change in furnace pressure;
When the fuel input is terminated, this bal- that is, 40.6" WG.
ance no longer exists. The flue gas being pulled Fortunately, the natural characteristics of
out of the furnace by the ID fan is now being re- forced-draft and induced-draft fans and their
placed only by preheated air rather than by the control devices are such that a constant-
products of combustion in the firing zone. As a resident-mass situation is virtually impossible
result of this situation, the average temperature to achieve.
of the gases resident in the furnace (or other Assume, for the moment, that all FD and ID
subsystem) at any given time following the fuel fan dampers are fixed in position. As the fur-
trip will decrease rapidly. Because of the tem- nace pressure begins to decay because of the

P^

Convection Stack

Flow1 Flow2 Flow2 Flow1

Atmospheric Pressure

L---
Pressure Profile at the Peak of the Excursion

Fig. 25 Pressure profile in a balanced-draft unit before and after trip. Notice that the magnitude of the
drop in furnace pressure at the peak of the excursion is higher than those at the FD fan discharge and the
ID fan inlet. This is because of the difference in flow conditions at the time of the excursion.
COMBUSIION
Operational Control Systems

temperature decay, the fans will move to dif- Law does notrecognize the difference between:
ferent operating points on their respective per- w types of firing systems (corner, front and rear,
formance curves. The FD fan will move in the dry-bottom, or slagging bottom);
direction of increasing volume; the ID fan, in coal firing, oil firing, or gas firing; and -
the direction of decreasing volume (Fig; 26). w balanced-draft or pressurized operation.
The airflow through the windbox will increase To understand, then, why the most serious
because the lower furnace pressure appears to implosion problems have been experienced
the FD fan to be a reduced system resistance. with oil-fired, balanced-draft boilers, it is nec-
T h e fluegas flow will decrease because the essary to keep in mind that the key to holding
lower furnace pressure appears to the ID fan to furnace pressure constant is to maintain
be an increased system resistance. the product of resident mass and temperature
The net effect of this increase in airflow and constant.
reduction in gas flow is to increase the resident On a pressurized boiler, the action of the FD
mass in the furnace, which tends to compen- fan during normal operation pushes the flue
sate for the temperature decay. This natural gases out of the furnace.
corrective action taken by the FD and ID fans is When the combustion process in such a pres-
a key ingredient in the ability to contain surized unit is terminated, the resulting tem-
furnace-pressure excursions to values that are perature decay causes the furnace pressure to
within tolerable limits. drop rapidly. As soon as the furnace pressure
It should be apparent that the Perfect Gas drops below atmospheric pressure (ignoring

Time
X
-
Static
Pressure
System Resistance IJK
I\/
Time X-0
Volume
Furnace PF Induced-Draft Fan
Pressure

Volume System
Change VG Gas static
Pressure

Time 0 -X
Volume
Forced-Draft Fan
co~.moN
Opurtional Control Systems

stack effect), the flue gas will no longer leave Centrifugal-type ID fans customarily are
the furnace but the airflow will continue to en- equipped with inlet vanes or inlet louver
ter. Moreover, any additional decrease in fur- dampers for control of the volumetric flow of
nace pressure will cause a reverse flow7 down gas through them. (See Chapter 14.)
the stack, back into the furnace. These devices have similar control charac-
When firing is terminated on a balanced- teristics (as compared to outlet dampers or
draft unit, flue gas (with its mass at furnace variable-speed drives), but can have widely
temperature) will be pulled out of the furnace varying time-constants depending upon the
until the pressure there reaches a negative type of actuator used to move them.
value which is directly related to the cutoff Fig. 27 shows the effect on the pressure1
pressure of the ID fan corresponding to the tem- volume curve of such a fan when either vanes
perature entering the fan. The higher the head or dampers are closed to reduce the gas
capability of the ID fan, the larger the pressure through-flow. On this curve, fan static-pres-
excursions that may be experienced. sure capability is plotted against rated volume,
Thus, although some authors have attempted and a system-pressure curve is shown-a sim-
to treat the ID fan characteristics and the fuel ple square relationship of static pressure to
cutoff as two independent effects, they are ac- volume (SP a V2).The control device is regu-
tually inseparable. lated so that the required static pressure to
With respect to pulverized-coal and oil fir- satisfy the resistance of the physical system is
ing, the difference is one of therate of tempera- developed at any given volumetric flow rate.
ture change. This rate depends on how fast a But, at the same time, for the particular vane
given percentage of the furnace volume under- position, a fan characteristic curve is estab-
goes a replacement of combustion products lished such that the fan is capable of an infinite
with preheated air. Coal-fired units have the number of discrete static-pressure values yer-
following characteristics that produce a slower sus any given volumetric flow.
temperature decay: If we consider an operating mode in which
the induced-draft-fan control vanes or dampers
1. The fuel cutoff is generally more gradual
are capable of infinitely fast response, any
than with oil firing, because of the pulverized-
change in the furnace pressure of a balanced-
fuel residual in the pulverizer and fuel piping.
draft unit that is sensed by the system will
2 . The ratio of resident mass to mass-flow rate is cause the vanes to change position to maintain
higher than for an oil-fired boiler, because the required system static pressure exactly, and
coal-fired furnaces are significantly larger in along the system-pressure curve. For instance,
size than oil-fired-only furnaces. if there should be a reduction in furnace pres-
THE "CULPRIT," THE INDUCED-DRAFT FAN sure (caused,say, by a decrease in the fuel fired
and the corresponding. combustion airflow),
I n connection with the implosion phe- the vanes will immediately close to reduce the
nomenon, it is most important that engineers gas flow handled by the fan before the furnace
responsible for draft-system and furnace- pressure drops any further. With such infi-
framing-system design understand how an in- nitely fast vane control assumed, even with an
duced-draft fan operates, how it is controlled, instantaneous very large drop in furnace-
and how it responds to changes in the inlet pres- pressure level (such as there could be if there
sure that it "sees." were a master fuel trip or if the forced-draft-fan
Induced-draft fans are used singly, or in mul- dampers were to accidentally close), the sys-
tiples of 2, 3, or 4, to evacuate the products of tem curve will always be followed and the
combustion from a boiler-furnace while main- induced-draft fan will make instantaneous cor-
taining the pressure at the top of such a furnace rections to maintain furnace pressure at the
about 0.2" WG below atmospheric pressure. level preset (below atmospheric).
COMBUSFION
OperationalControl Systems

Static Pressure- Vanes or Dampers Wide Open


120-

.-0 Static Pressure - Vanes or Dampers


Set for 75% Rated Volume
u
Static Pressure - Vanes or Dampers
Q)
r;; 40-
Set for 50% Rated Volume

0 10 20 30 40 50 60 70 80 90 100
OO
/ Rated Volume

Fig. 27 The effect on a centrifugal-type ID-fan pressurelvolume curve when either vanes or dampers are
positioned to reduce the gas through-flow

Another condition can be postulated, in der this condition of vanes-maintained-in-


which the control vanes or dampers are main- position. Assume further that the forced-draft
tained in a fixed position as boiler load varies; fan dampers close quickly, so that there is a
this is equivalent to a zero rate of damper re- rapid decrease in the gas available to the
sponse. When boiler load decreases (and fuel induced-draft fan. The induced-draft fan will
flow, airflow, and gas flow decrease corre- immediately ride up along the characteristic
spondingly), the developed fan static pressure curve to the cutoff point; after reaching the
increases following a static-pressure versus cutoff point, reverse flow of gas down the stack
volume curve sloping upward to the left; will occur (at some indeterminable flow rate)
furnace suction (pressure below atmospheric) until the furnace suction that has been estab-
increases rapidly. The obvious limit to the lished by the decrease in the average gas tem-
furnace suction that can be developed is the perature is satisfied. .
highest static-pressure value on the curve, If the rate of reverse flow is not high enough,
which for damper settings below 50 percent, the furnace will fail structurally if the framing
appears to be at or about the fan no-load cutoff system is not capable of withstanding the low
value (the static head developed by a fan when absolute pressure that results from the fuel trip.
its volumetric delivery is zero). Of course, what happens during a master fuel
Under normal load-changing -conditions, if trip in which equipment is on automatic con-
fan vanes are maintained at a given position, trol is somewhere between the above two pos-
either accidentally or purposely, furnace suc- tulated situations. Fan dampers or vanes close
tion will vary, with the maximum static- in an effort to reduce the gas flow leaving the
pressure capability of the fan being the limit. furnace, restricting the magnitude of the fur-
Under these conditions, of course, forced-draft nace pressure-level reduction. With good
airflow continues, but is automatically varied mechanical response to the control signal (par-
with boiler firing rate. ticularly if an "early" signal has been received
Assume that a master fuel trip occurs un- through the use of a feed-forward arrange-
COMBVmON
0pvrthwI.I Control systivns

ment), fan static-pressure capability will match and maintained, and that plant operators con-
the furnace suction being developed as a result sider these control systems to be vital.
of the reduction in furnace gas temperature, all
while the volumetric gas flow through the fan
is being reduced to zero. Ultimately, this frus- POWER-PLANT
trates any implosion tendency.
The above analysis applies to constant-speed
DIAGNOSTIC SYSTEMS
centrifugal-type or vane-controlled axial-flow The need for performance diagnostic systems
fans. A similar approach can be used in asses- and their high cost-effectiveness are discussed
sing the implosion potential of variable-speed in Chapter 24. Although the study referenced
centrifugal, or variable-pitch axial-flow fans. in that chapter was aimed at improving the
availability and performance of existing steam-
CONTROL IMPLICATIONS generation equipment, the application of diag-
Implosion cancerns have resulted in many nostic systems is equally important for new
new control-system developments. The search units. Beginning with plant start-up, perform-
for the ideal implosion-prevention control ance monitoring and diagnosis can provide a
scheme is still proceeding. Each steam- consistency of unit operation and can mini-
generator manufacturer has recommendations, mize, if not totally avoid, those operating con-
and the National Fire Protection Association ditions that may have adverse effects on the life
has issued NFPA 85-G on the subject. of the equipment. Further, because fuel costs
constitute the major portion of the cost of elec-
Space does not permit going into the spe-
tricity, plant heat rate, especially as it is influ-
cifics of the control-system designs which are
enced by boiler efficiency, must be a primary
outlined in such recommendations. However,
consideration in all modes of operation.
the following must be provided in any
furnace-draft and combustion-control system: SYSTEM STRUCTURE
1.The airflow to a furnace must be maintained The purpose of diagnostic systems is to con-
at its pretrip value and must not be prevented tinuously monitor, evaluate, and interpret dur-
from increasing by following natural fan ing operation the thermal, structural, and
curves; but positive control action to increase chemical conditions of the entire power-plant
airflow is not allowed by NFPA. complex in real time. The information obtained
2. The flow of combustion products from a fur- is displayed in a meaningful manner to operat-
nace must be reduced as quickly as possible fol- ing personnel and provides them with the op-
lowing a unit trip. portunity for appropriate action to improve
performance and to avoid conditions which
3. If the removal of fuel from the furnace can be
may adversely impact equipment life. Further,
over a 5- to 10-second period (rather than in-
operating conditions (in the form of data sets)
stantaneously),there will be a reduction in the
are date- and time-stamped, and archived for
magnitude of the furnace-pressure excursion
off-line recall at a future time. This chronicling
that follows a unit trip.
allows the opportunity for detailed analysis by
Obviously, even the most carefully designed results engineers, and the setting of long-term
control system will be of limited value if all its operating strategies consistent with manage-
components are not completely installed, if it ment objectives. In addition, the archiving of
has not been properly checked out or is in data sets with the ability to review operation
"poor tune", or if it has been inadequately conditions based on various, parameters (such
maintained. It is essential, therefore, that pro- as load, fuellair ratio, water chemistry, temper-
tective control systems for large, high draft-loss ature excursions, sootblowing frequency, and
boilers be properly designed, installed, tested, the names of operators on duty) can provide in-
COMBUSTION
Operational Conirol Systems

sights into long-term degradation of equipment 8 Tube Temperature Monitoring System -im-
performance or the necessity for additional proves availability by reducing superheater and
operator training, which may not be readily ap- reheater element temperature excursions..
parent during on line-operation. 8 OPSIZE - reduces carbon loss, lessens slag-
The sophistication of the installed diagnostic ging and fouling, and optimizes pulverizer and
system will, of course, depend on the type and precipitator performance by measuring and
cost of the equipment and software selected. A controlling coal-particle fineness.
range of systems is available, from off-line per-
sonal-computer-based programs to advanced Although each system functions on a stand-
mini-computer types that allow interactive alone basis, they work in combination to com-
communication for on-line changes in operat- plement each other by sharing a common data
ing parameters. base. For example, optimizing pulverized-coal
fineness can improve thermal efficiency, and so
on. Fig. 28 illustrates the integrated concept; it
DESIGN STRATEGY shows how each diagnostic module can com-
The modern power plant obviously will in- municate with plant data-acquisition systems,
clude all the means to generate power; that is, it the station control room, and engineering work
will have a boiler, a turbine, a generator, pri- stations, as desired.
mary sensors for monitoring operation and for Two of the modules above are intended to im-
data acquisition, a data highway, and opera- prove boiler efficiency as well as the overall
tional-control equipment. Adding appropriate plant heat rate.
diagnostic programs, as needed, can improve
C-E ON-LINE THERMAL INFORMATION SYSTEM (OTIS)
the efficiency and reliability of power genera-
tion. Although the calculated results of on-line Thermal-performance-optimization software
analysis can be used to directly affect unit oper- assists operators in selecting controllable pa-
ation, diagnostic systems are better employed to rameters of boiler and steam cycles. For coal-,
provide adequate feedback information for op- oil-, and gas-fired plants, the controllables in-
erators to make intelligent and well-considered clude excess air, burner tilt, desuperheating-
decisions to improve unit performance. In order spray flows, and feedwater heaters in service.
to so improve thermal performance, increase
plant availability, and to promote equipment
longevity, an integrated system can be built
from one of more of the currently available
diagnostic modules'described below.
8 On-Line Thermal Information. System - im-
proves plant thermal-cycle efficiency and opti-
mizes sootblowing frequency.
Boiler Stress and Condition Analyzer - ex-
tends unit life and improves availability by re-
ducing damage to heavy-walled components.
8 Interactive Chemistry Management System -
improves availability by minimizing water and
steam chemistry excursions.
8 Acoustic Steam-Leak Detection System - re-
duces forced-outage time by early detection and
location of leaks in boiler pressure parts and Fig. 28 Combustion Engineering Total On-Line
feedwater
-- heaters. Performance System
COMEUSRON
O p ~ U o n aContml
l Systems

For coal-fired plants, special importance is


placed on sootblowing. Thermal-performance
software also assists operators and plant techni-
cal staff in diagnosing long-term trends of con-
ditions that can erode heat rate. Examples of
such effects are turbine blade erosion, con-
denser fouling, feedwater-heater leakage or
fouling, and air-heater leakage.
Thermal-performance-optimization software
is evolving for four distinctly different levels of
plant operation. These levels are as follows:
1.Gross plant, boiler, and turbine efficiency.
2. Component-level berforrdance with trending
compared to baseline tests. The components
analyzed are the boiler, steam turbine, con-
denser, and feedwater heaters. O/O Excess Air
I
3. Subcom~onent-levelperformance, with on- Fig, 29 Sensitivity of carbon loss to coal fineness
line optimization strategies. The subcompo-
nent-level diagnostics address, for instance,
individual heat-exchanger elements and dis-
crete turbine expansion stages in addition to carbon loss. Fig. 29 shows the sensitivity of car-
overall component performance. Optimization bon-conversion efficiency t~ coal fineness for a
strategies are based on achieving original de- boiler firing low- to medium-volatile bituminous
sign thermodynamic conditions or on iterative coal.
searches to optimize overall heat rate. Pattern- The degradation in fheness usually results
recognition techniques are employed to diag- from one or more of the following problems:
nose the causes of long-term heat rate degra- worn separator body liners
dation. Predictive modeling allows operators
to evaluate alternative control strategies without damage to one or more classifier vanes
actually changing operating parameters. excessive ring-to-roll clearance
variations in coal grindability resulting from
4. Bona fide expert systems employing heuristics blending or switching sources
' '

to isolate problems and recommend action. infrequent fineness measurement and adjust-
These diagnostics are mostly experimental at ment
this time; in them, standard engineering models
based on the conservation equations, heat trans- The C-E OPSIZE system addresses these prob-
fer, and thermodynamics interact with a heuris- lems by performing on-line real-time measure-
tic process. ment and control of coal fineness.
COAL FINENESS CONTROL
PLANT AVAILABILITY IMPROVEMENT
Minimizing carbon loss is widely recognized
as an important factor in improving boiler effi- Pressure-part failures are generally found to be
ciency. Even though a new boiler operates with the single most important contributor to steam-
excellent carbon-conversion efficiencies, older generator forced outages. Interactive chemistry-
equipment may not do as well. Inadequate coal management systems and acoustic steam-leak
fineness control is amajorcontributor to elevated detectors address this problem area.
COMBDSPION
.Operational Control Systems

C-E INTERACTIVE WATER-CHEMISTRY chemistry, and the effect of corrective actions.


MANAGEMENT SYSTEM (ICMS)
G E ACOUSTIC STEAM-LEAK
This diagnostic tool is designed to _improve DETECTION (ASLD) SYSTEM
boiler availability through better control of water
and steam chemistry, as described further in The ASLD system allows plant operators to
Chapter 20 on power-plant water technology. detect leaks early and locate them more accu-
Continuous on-line water-chemistry manage- rately. Both features help minimize the cost re-
ment assists operators by providing alarms and sulting from a tube leak. Early detection can
recommending corrective action as soon as a minimize the damage that can occur when a
water or steam chemistry excursion is detected. leak washes nearby tubes; accurately locating
Fig. 30 shows a schematic diagram of the sam- the leak will reduce repair time.
pling requirements f0r.a typical waterlsteam cy- The Acoustic Steam-Leak Detection System
cle. For feedwater: pH, oxygen, ammonia, consists of a number of tuned listening chan-
hydrazine, and condenser leakage are monitored nels which are strategically located along the
and displayed; for boiler water: pH, phosphate, furnace walls of a steam generator. Boiler size .

total solids, silica, and blowdown; for steam: and configuration determine the required num-
cation conductivity, sodium, and carryover. ber of listening channels per system. The sound
Pattern recognition, trend analysis, and solu- produced by a leak is picked up by the listening
bility data are used to diagnose phosphate hide- channels and is transmitted to a head amplifier
out and condenser leakage. Analyses are which filters and boosts the signal for transmis-
performed on-line to determine the magnitude sion to the signal-conditioning unit control-
of the occurrences, their impact on system room display.

Preboiler Recirculation

Polishers - Condensate-

* Cation
Cat~onConductivity Conductivity

Fig. 30 ICMS sampling requirements


CO%~BUSI~ON
Operational Control Systems

LIFE CONTINUATION C-E TUBE-TEMPERATUREMONITORING SYSTEM (TTMS)

A major area of concern in prolonging the life This system is designed to assist the plant
of existing steam-generators is in the avoidance operators and engineering staff in making intel-
of damage to heavy-walled components. The ligent operating decisions which will minimize
life of headers, tees, drums, and high-energy loss of tube life and increase unit availability
piping is critical because of the high costs and The importance of monitoring tube tempera-
long times associated with obtaining replace- tures is illustrated in Fig. 31, which shows
ments for damaged components. stress-to-rupture data for 2-114 Cr 1 Mo steel.
A second aspect of continuing unit life is con- This data indicates that increasing the tempera-
cerned with preventing superheater and re- ture of a given superheater element by just 12 F
heater tubing failures, which represent nearly can reduce its time-to-failure from 115,000
half of all boiler tubing failures. hours to 76,000 hours.
One of the most cost-effective ways of con- The Tube-Temperature Monitoring System
tinuing equipment life is to make it possible monitors the metal temperatures of superheater
for plant personnel to avoid damaging opera- and reheater tubing. The measured tempera-
tions. To do this, operators need accurate on- tures are compared against predetermined
line information, provided in the control room alarm levels, which are based on oxidation
through a stress-and-condition analymr and a limits and stress-rupture limits. Current data,
tube-temperature monitoring system. including alarm conditions, are presented to
operators on a menu-driven display. Using this
C-E BOILER STRESS AND CONDITION ANALYZER information, personnel can modify boiler oper-
(BSCA) ation to achieve optimum unit performance
The BSCA is an on-line diagnostic system de- consistent with minimizing damage to tubing.
signed to assist operators in avoiding damaging In addition, the TTMS maintains a historical
data base which the engineering staff can uti-
operating conditions. During plant start-up,
lize to develop strategies for extended operation
shutdown, and cycling operation, temperature
transients are imposed on the headers, tees, and maintenance based on economic criteria.
drums, and steam lines. The resulting thermal
loadings cause significant stresses which can
increase creep damage and cyclic fatigue. The 10OO0F
BSCA monitors the unit operation in real time,
alerts operators to damaging transients as they 1012OF
occur, and calculates accumulated damage to
critical components.
The BSCA continually collects plant operat- .-
2
ing data including temperature, pressure, and $9,000 - ----
flow data. The effects of pre-existing opera- P!
tional practices on the state of damage in the FI
thick-walled pressure parts are accounted for
either by initializing the damage arrays based 10250\ I II II
on historical unit operating data or by a variety
of material analysis techniques. Alarm set-
- 50.000 76,000 115,000
points for differential _temperature and over- Time to Rupture, Hrs
temperature are established based upon
initialized damage arrays, expected mode of -
unit operation in the future, and optimum com- Fig. 37 Minimum stress-to-rupture of 2% Cr 1 Mo
ponent life. steel
COMBrnON
Operational Control Systems

The power industry cannot be expected to play


OTHER POWER-PLANT a significant role in the development of mi-
croelectronics. But the industry will take advan-
CONTROL SYSTEMS tage of new developments, particularly in the
This chapter has dealt solely with stearn-gen- area of distributed computer-based systems, as
erator related control and diagnostic systems. they become available.
Given sufficient space, similar chapters could Increasing demands for higher productivity
be written about the controlsfor flue-gas-desulfuri- and availability of steam-generating plants will
zation systems, precipitators, and ash-handling provide new challenges for designers of opera-
systems, all of which can be in the "steam- tional-control and diagnostic systems. The elec-
generator island." Increased controls sophistica- tronics industry will provide the tools; the
tion istaking place in .such areas, for the same power-generation controls engineers must pro-
reasons as outlined above. vide the imagination.
CHAPTER 14

Steam-Generator Auxiliary Equipment

u his chapter describes power-plant equip-


ment such as fans, air heaters, sootblowers,
and the boiler-water circulating pumps. This
equipment is usually designated as boiler aux-
water pumps are part of the power-plant cycle.
In general, valves required for boiler operation
are boiler auxiliaries, but steam stop valves,
turbine throttle valves and most other valves
iliaries. Power-plant noise, which applies par- related to the steam turbine and feedwater
ticularly to these and most other equipment heaters are not.
peripheral to the boiler, also is covered. Other Equipment is described here to help
such components described in detail elsewhere familiarize the reader with the different com-
include pulverizers, Chapter 11; ash-handling ponents and their specific applications in
equipment, Chapter 16; and structural-steel boiler work. The calculation of volumes han-
design and erection, Chapters 6 and 19. Opera- dled and static pressures to be encountered
tional control system philosophy and design with fans are given in Chapter 6 . For soot-
are included in Chapter 13, and the entire scope blower selection, the designer must take into
of boiler-related emission-control equipment is account the boiler configuration and the prob-
presented in Chapter 15. able dirtying characteristics of the coal ash, as
Although boiler auxiliary components are referenced in Chapters 2, 3, 6, 7, 8 , and Appen-
secondary to the design of the boiler itself, they dix B. For air-heater sizing, air and gas flows
are absolutely essential to its operation. To- and temperatures have to be calculated, as will
gether, they represent a very sizable portion of allowable static pressure losses; for more in-
the overall steam-generator cost. As differ- formation on such calculations see Chapter 6.
entiated from equipment considered auxiliary It is important to realize that there are in-
to the remainder of a steam power plant, a boiler stances in which some of this peripheral
auxiliary is equipment which is an integral equipment is purchased separately from the
part of, or is required for the operation of, the steam-generator contract. However, the boiler
boiler. For example, compressors for air soot- manufacturer has to be relied on heavily to
blowers and certain sealing requirements, are provide basic steam generator performance
part of the overall power-plant equipment and data. The data is necessary for the proper selec-
are not boiler auxiliaries. Pumps within the tion and design of the peripheral equipment
boiler circuit are boiler auxiliaries, but feed- and other auxiliaries.
COMBUrnON
Steam-Generator Auxiliary Equipment

plant. They are particularly well-suited for


POWER-PLANT FANS high-speed operation. Most FD fan installa-
tions have inlet silencers for noise reduction
Regardless of fuel and method of firing, all with screens to protect the fans from any en-
boilers for electrical, industrial, or marine trained particles in the incoming air.
power generation use mechanical draft fans
(Fig. 1).They supply the primary air for the pul- EFFECT OF AIR TEMPERATURE
verization and transport of coal to the furnace. Both the air temperature at a power plant and
They also supply the secondary and tertiary air its elevation above sea level affect air density,
to the windboxes for completion of combus- which in turn has a direct influence on the
tion. Fans also remove the products of combus- FD-fan capacity. If steam coils or other means
tion from the furnace and move the gases of heating the air ahead of the FD fans are pro-
through heat-transfer equipment and flue-gas vided, the consequent air temperature to the
desulfurization equipment. Sometimes, gas fans must be taken into account. If hot-air recir-
fans control steam temperature. Numerous culation is used for air-heater protection, then
small fans are used for sealing and cooling both the added volume of air and its higher
of ignitors, scanners, and other equipment. temperature must be considered. As mentioned
Power-station fans are among the largest in the calculation sections of previous chap-
made: static pressures of 60" WG and in- ters, if air moisture exceeds 2 percent by weight
dividual fan volumes of 1.5 million cu ftlmin (as can occur in high-temperature tropical in-
are common. And, usually, they are custom- stallations) the resulting greater volume calls
designed with blade configuration and control for increases in size of all fans on a unit.
systems highly sensitive to both owner prefer-
ence and the evaluated cost of installed pnd PRIMARY-AIR FANS
operating power. Applications that require the
largest fans (and thereby use the greatest Large high-pressure fans supply the air
amount of plant power) on a boiler fall into four needed to dry and transport coal either directly
categories which combined account for more from the pulverizing equipment to,the furnace,
than half of the total boiler power requirements. or to an intermediate storage bunker. As de-
The four fan categories are: forced-draft, pri-
mary-air, induced-draft and gas-recirculation.
FORCED-DRAFT FANS
Forced-draft fans supply air necessary for
fuel combustion, as calculated in Chapters 4
and 6 , and must be sized to handle the stoi-
chiometric air plus the excess air needed for
proper burning of the specific fuel for which
they are designed. In addition, they provide air
to make up for air-heater leakage and for some
sealing-air requirements. Forced-draft (FD)
fans supply the total airflow except when an
atmospheric-suction primary-air fan is used.
Radial airfoil (centrifugal) or variable-pitch
axial fans are preferred for FD service. FD fans
operate i n the cleanest environment asso- Fig. 1. construction view of four axial-flow type
ciated with a boiler, and are generally the induceddraft fans serving a large pulverized-coal
quietest and most efficient fans in the power steam generator
COMBUSllON
Steam-Generator Auxiliary Equipment

scribed in Chapter 11, primary-air fans may be tive pressure in the equipment downstream
located before or after the milling equipment. of the furnace and by any seal leakage in air
The most common applications are either preheaters. Chapter 6 gives the method of es-
pulverizer exhauster fans or_ cold (ambient
~ tablishing volume and pressure specifications
temperature) primary-air fans. and tolerances.
The mill exhauster fan draws hot air from the As ID fans are now typically located down-
secondary-air duct and through the pulverizer. stream of any particulate removal system, they
The coallair mixture from the pulverizer then are a relatively clean service fan. In most in-
passes through the fan and discharges into the stances, therefore, radial-tip or solid-reinforced
fuel pipes which carry the mixture to the fur- blade centrifugal fans are not required. Typi-
nace for ignition. One fan is usually supplied cally, airfoil-bladed centrifugal or variable-
for each pulverizer. pitch axial fans are used for this service
A materials-handling fan of the straight- because of their inherent high efficiency. These
blade type, the mill exhauster is sized for the fans have high capacities, in excess of 1.5 mil-
maximum airflow needed by the pulverizer. It lion cu ftlmin, and their airfoil blades mini-
must develop sufficient pressure at maximum mize turbulence and noise. The blades and
airflow to overcome the resistance of the air center plates may also be fitted with wear pads
ducts, dampers, the pulverizer, and the fuel and replaceable nose sections for greater wear.
pipes to the furnace. Structural strength, particularly important in
Located before the air heater, the cold larger sizes, is excellent with these designs.
primary-airsfan draws air from the atmosphere Where greater wear resistance is needed be-
and supplies the energy required to force the cause of dust burden or where a very conserva-
air through the ducts, air heater, pulverizer, tive approach is desirable, a modified radial or
and fuel piping. Usually two fans are supplied forward-curved, backward-inclined design is
for each steam generator. used. With some sacrifice in efficiency, these
Cold primary-air fans for ambient-air duty blade shapes minimize dust build-up and re-
are of the centrifugal airfoil or multi-stage axial duce downtime for cleaning. They have low
type and, like FD fans, have silencers. In situa- noise characteristics, and their relatively sim-
tions involving severe particulate concentra- ple design allows fabrication in special alloys
tions or high temperatures, straight radial or should they be required for service downstream
modified radial fans are recommended. of a wet scrubber.
With a cold-air system, the air volume han- The ID fan is sometimes used as a booster fan
dled by the primary-air fan is subtracted from with flue-gas desulfurizing (FGD)scrubbers. In
the amount of air that must be handled by the one such arrangement, ID fans follow the pre-
forced-draft fan. Therefore, if coal is the only cipitator or baghouse and another set of fans-
fuel being fired, the forced-draft fan may be the booster fans-follows the scrubber. With
made smaller because of the amount of air han- pressurized scrubbers, the booster fans are
dled by the cold primary-air fan. placed directly behind the ID'S and ahead of
the scrubbers, acting to "push" the gases
INDUCED-DRAFT FANS .-. through the FGDS.
Induced-draft (ID) fans exhaust combustion
GAS-RECIRCULATION FANS
products from a boiler. In doing so, they create
sufficient negative pressure to establish a slight Gas recirculation fans draw gas from a point
suction in the furnace (usually from 0.2 to 0.5" between the economizer outlet and the air-pre-
WG). This condition gives rise to the name heater inlet, and discharge it (for steam-tem-
"suction firing" or "balanced-draft" operation. perature control) into the bottom of the furnace.
These fans must have enough capacity to ac- When controlling steam temperature on coal-
commodate any infiltration caused by the nega- fired units, a high-efficiency, high draft-loss
.-
COMB~ON
Steam-GeneratorAuxiliary Equipment

mechanical dust collector must be installed pressure is the air pressure that exists by virtue
ahead of the fan. If the recirculation fan on a of the degree of compression and the rate of mo-
coal-fired unit is only for standby or emergency tion. When applying these definitions to fan
oil firing, the dust collector is omitted. performance, there are distinct relationships
Gas-recirculation duty provides the most se- that exist between each variable.
vere test of a power-plant fan. The combination Fan total pressure is the difference between
of heavy dust loads and rapid temperature the total pressure at the fan outlet and the total
changes demands the utmost in rugged, reli- pressure at the fan inlet. Fan velocity pressure
able fan design. Particularly important is how is that corresponding to the average velocity at
the fan hub is mated with the shaft; the often- the specified fan outlet area. Fan static pres-
used shrink-fit may not be adequate. To cope sure is the difference between the fan total
with temperature excursions, fans with an inte- pressure and the fan velocity pressure. Thus, it
gral hub are preferable. Straight or modified ra- is the difference between the static pressure at
dials or forward-curved, b a c k ~ a ~ d linclined
y the fan outlet and the total pressure at the fan
centrifugal wheels meet these needs the best. inlet. Static pressure rise, sometimes mistaken
Turning gears are supplied on gas-recircula- for fan static pressure, is the static pressure at
tion fans to turn them at slow speed when the the fan outlet minus the static pressure at the
main drive motor is not in operation. If a gas- fan inlet. The difference between fan static
recirculation or ID fan is exposed to gases above pressure and static pressure rise is the inlet
400F,the turning gear should be energized to velocity pressure.
prevent thermal distortion of the motor. POWER
HOW FANS WORK With the equation for fan work and some
A fan is a volumetric machine which, like a basic physical constants, the equation that'ex-
pump, moves quantities of air or gas from one presses air horsepower can be developed.
place to another. In so doing, it overcomes re-
sistance to flow by supplying the fluid with the V x H
Ahp = -
energy necessary for continued motion. Physi- 6356 '
cally, the essential elements of a fan are a
bladed rotor and a housing to contain the in-
coming air or gas and direct its flow. where V is the volumetric flow through the fan
ENERGY FACTORS in cu ftlmin and H is the head or pressure differ-
Because a fan does work it demands energy ence (in inches of water) across the fan. The air
to operate. The amount of energy depends on horsepower may also be designated as either
the volume of gas moved, the resistance against static or total. Because the resistance to be
which the fan works, and machine efficiency. overcome in fan application is primarily static
Chapter 6 gives the method of calculation of air pressure, the fan pressure developed is usually
and gas volumes. It is important to calculate referred to in terms of static head. On this basis,
such volumes at the actual pressure or suction the calculated fan power is known as static air
existing at the fan inlet. horseporzrer (Ahp,). When the power calcula-
tions are based on total head, fan power is re-
FAN PRESSURE RELATIONSHIPS ferred to as the total air horsepower (AhpJ and
Draft, pressure, draft loss and pressure loss is equivalent to the power output.
were defined in Chapter 6 which also differ-
entiated between velocity*pres.iiureand static Ahpt
pressure: total pressure was stated to be the Fan Mechanical efficiency (q,)= power input
algebraic s u m of velocity pressure and static
pressure. Specifically related to fans, total
Steam-Generator Auxiliary Equipment

or, transposing, fluid pressure (br directly with fluid den-


sity)-and that adjustments often must be made
Power input (brake or shaft hp) =.&p, for pressure and temperature variations when
71 calculating performance or selecting a fan for a
--V H,
- particular application.
6356qt
SPECIFYING FAN OPERATING CONDITIONS
(3)
The problem of specifying the required oper-
T h e power input formula assumes that air is ating conditions for fans at various load points
a n incompressible fluid. But the fact that air is is usually the responsibility of the boiler, FGD-
compressible must be recognized when design- system, and particulate-removal-equipment
ing for high pressure differentials. The fan suppliers. The fan manufacturer assumes re-
power formula then becomes sponsibility only for producing the volumetric
flow and pressure specified. If the fan and sys-
k,Y H, tem are incorrectly matched, the fan will not
Power input, hp = -
6356v, deliver the desired flow or pressure. Once the
fan has been installed, it is difficult to increase
its capability significantly because of physical
ivhere kc can be taken from Fig. 2 , which is
limitations such as motor and impeller size. To
based on adiabatic compression.
select the appropriate fan for a given applica-
Density ' tion, the fan vendor needs to know the density,
Because they affect gas density, pressure and flow and pressure requirements of the system at
temperature of the air or gas also influence various points of operation and whether there
power output and efficiency. A change in are any fan speed !imitations. If any of these
density changes total and static pressure and variables change, it can affect the fan selection.
their subsequent conversion into inches of FLOW
water at standard conditions. Remember that The gas flow through the fan is usually ex-
head and horsepower vary inversely as abso- pressed as a volumetric flow rate. It is neces-
lute fluid temperature and directly as absolute sary to determine the flow rate in actual cu
ftlmin (acfm) at the inlet to each fan from the
density at the fan inlet and the mass flow rate
(lblhr). Proper corrections for plant elevation
and actual conditions of local pressure at fan
inlets must be made to the calculated air and
gas volumes, as described in Chapter 6 .
PRESSURE
On balanced-draft units, the required static
head for the FD fan is the sum of all the se-
ries resistances in the secondary-air system,
including cold-air duct, steam air heater, air
1.00 1.04 1.08 1.12 1.16 1.20 1.24 preheater, air metering device, hot-air duct,
dampers and windbox pressure drops. For pres-
--Outlet - Pressure Ratio surized units, the additional loss from the fur-
P inlet
nace to the stack outlet must also be included
Fig. 2. Compressibility hctor for use in calculating in determining total system resistance. ID fans
fan power consumption, assuming adiabatic corn- must provide a static head equal to the series
pression resistance from the furnace to the stack outlet,
.-
COMBmnON
St--Generator Auxiliary Equipment

including resistances of superheater, reheater, Fans are broadly classed as either centrifugal
boiler bank, economizer, air preheater, dust- or axial, according to the flow direction. The
collecting equipment, scrubbers and all duct- centrifugal (radial) fan moves air perpendicu-
work. For primary-air (PA) fans, static pressure lar to the rotational axis of the impeller; the
requirements are determined by the resistances axial-flow fan moves air parallel to the rota-
through the inlet duct and air preheater, tional axis of the impeller.
the pressure drop through the pulverizer,
CENTRIFUGAL FANS
and the resistance through the fuel piping to
the furnace. Centrifugal fans use blades mounted on an
"SPECIFIED" CONDITIONS impeller (or rotor) which rotates within a spiral
or volute housing. Blade design determines fan
The volume flow (acfm) and static pressure characteristics, so by using blades of different
("WG) calculated by the boiler or scrubber shapes, a fan engineer can select an appropriate
manufacturer, as previously discussed, give fan design. Basic blade types are the radial.
the actual required fan capacity under ideal radial tip (forward curved), and backwardly
operating conditions. Besides the require- inclined (solid or airfoil). A velocity vector
ments at full load, the boiler or scrubber man- diagram at blade tip (Fig. 3) indicates that back-
ufacturer should also calculate performance ward curved blades produce low velocities for a
requirements at several other partial load given tip or peripheral speed, and that forward
points to evaluate power consumption, select curved blades give high velocity. Radial blades
the control equipment, and assure a fan that and radial-tipped blades lie between these two
will operate at maximum efficiency at the de- extremes. The back~vardlycurved blade type,
sired normal output of the steam-generating therefore, operates at greater motor speeds than
unit. Also, the fan manufacturer must have a the other types for a given duty and is u~ell
clear understanding of the system resistance adapted to direct drive with motors or steam
over its entire range to ensure that a fan will turbines.
operate at all points along its curve from the Fig. 4 shows some commonly used blade
point of view of stability, sound, and efficiency. shapes. In general, blade type limits fan speed.
Usually a margin or safety factor is added to Thus, the backward-blade machines can oper-
the maximum continuous (MCR) volume and ate at a relatively higher speed than the for-
pressure requirements to arrive at maximum
design or "specified" rating. Fan tolerances
ordinarily used by C-E are given in Chapter 6.
TYPES OF FANS
From the point of view of fluid mechanics,
fans represent a class of turbomachines de-
signed to move fluids such as air, gases and
vapor against low pressure. From the point of
view of mechanical design, fans have a very
light casing because inlet pressures are atmos-
pheric or lower. Simplified hydraulic forms Forward Curved Backwardly Curved
and welded steel plate are generally encoun-
tered in fans.
Direct-connected drives most often are used Fig. 3. Velocity vector diagrams comparing for-
ward-curved and backwardlycurved centrifugal-fan
in power-plant work with control obtained blades. At same tip velocity (Vb) each type blade
through variable-speed motors, hydraulic cou- produces different air velocity (Va). Vector Vab is air
plings, or variable inlet vanes. velocity relative to the blade
COMBUSTION
Steam-Generator Auxiliary Equipment

ward-curved design. Blade selection depends speed of the fan. Two-speed motor drives, tur-
on speed limitations, allowable noise levels, bine drives and fluid couplings all have been
efficiency demanded by specified load condi- used with varying success on centrifugal fans,
tions, and desired fan performance characteris- and have helped to increase their efficiency at
tics in the most likely range of operation. In lower loads. These arrangements do, however,
addition, the maximum attainable mechanical add more moving parts to the fan system, with a
efficiencies and tolerance of the blade to corro- potential negative effect on reliability.
sion and erosion are selection factors. Table I The variable-speed and the variable-fre-
shows the effect of blade type on both quency wound rotor motors are fan drives that
maximum possible efficiency and fan resis- allow varying the speed from full to zero in in-
tance to flyash erosion. Notice that increasing finite intervals; they improve dramatically
the efficiency of a centrifugal fan sacrifices its low-flow efficiencies. As discussed elsewhere
erosion resistance. in this chapter, speed variation is the ideal way
Once the optimum fan has been determined, to change fan operating characteristics; thus,
the aerodynamic selection process yields for centrifugal fans, these motor designs are of
width, diameter and speed of the fan wheel. great interest.
These parameters then become factors for sub- Centrifugal-Fan Construction
sequent elements of the fan design. In general,
Fan scrolls and inlet boxes are of welded steel
the fan wheel dimensions determine the basic
dimensionsof the fan housing and inlet boxes. construction. The housing and the inlet boxes
have either removable sections or are split for
Centrifugal-Fan Design access and removal of the rotor (Fig. 6). The
A very common centrifugal fan arrangement rotor wheel is of all-welded construction. After
(Fig. 5 ) is a single-speed motor drive which final machining, the rotor is usually statically
controls flow by inlet vanes or inlet louvers. and dynamically balanced and installed on its
The centrifugal fan in this instance is sized for shaft in the manufacturer's plant (Fig. 7).
"specified" conditions and is throttled by the AXIAL-FLOW FANS
inlet vanes to allow the fan to provide the flow
and pressure required at lower operating loads. Axial fans at various boiler loads can main-
As fuel costs and equipment efficiency have tain far higher efficiencies than constant-speed
become increasingly important, new arrange-
ments for centrifugal fans have developed. Be-
cause the welded blades of a centrifugal fan are rh
not easily adjusted, the only other means of
controlling flow and pressure is to vary the

Table I.Effect of Blade Type Backwardly Backwardly


on Erosion Resistance and Efficiency Inclined Inclined
Solid Blade Airfoil
Tolerance to
Typical Max. Erosive rh
Blade Type Static Eff., % Environment
-
-

Radial 70 High
Radial
Tip 80 Medium to High
Backrvardly Radial Tip Radial
lncli~ledSolid 85 hledium
Airfoil 90 Low
Fig. 4. Centrifugal (radial)fan blade types
COMBUSTION
Steam-Generator Auxiliary Equipment

Fig. 5. Airfoil-blade centrifugalfan with inlet-vanecontrol

Fig. 6. Airfoil-bladed centrifugal fan showing inlet boxes and housing split for rotor removal
COMBUSTION
Steam-GeneratorAuxiliary Equipment

centrifugal fans. As fuel costs continue to-rise, Axial-Fan Construction


their higher initial expense has been offset by Variable-pitch moving blades provide a wide
operational cost savings over the life of the range of flow with satisfactory operational effi-
plant. However, a detailed evaluation is re- ciency. Because the fan and its built-in compo-
quired to show the advantages of using axials nents work under high peripheral speed, and
in any given situation. thus great centrifugal force, mechanical relia-
In the most common axial arrangement (Fig. bility is as important as aerodynamic perfor-
8), the fan operates at constant speed and the mance. The centrifugal force of a moving blade,
angle of the blades on the hub is adjusted to for example, can be more than 150,000 lbs.
vary flow; n o inlet vanes are required for con- Fig. 9 shows the structure of a typical two-
trol. This enables the axial fan to develop, for stage axial ID fan. An overhung hub, with
each point of operation, a unique aerodynamic blade-actuating levers and an oil hydraulic pis-
configuration that is as efficient as possible. ton and cylinder, supports the moving blades.
Either a mechanical or hydraulic mechanism At the free end of the rotating cylinder a control
adjusts blade pitch while the fan operates at its valve is attached.
design speed. Mechanical type pitch-change The variable-pitch scheme shown in Fig. 10,
mechanisms are, however, usually insufficient includes an oil-hydraulic control that can be
to properly control fans of the size required for operated both manually and automatically. In
utility applications. Variable-pitch axials are automatic operation, an electric drive responds
best suited to PA, FD, ID or booster-fan applica- to a signal from the automatic plant controller
tions on large industrial and utility boilers. As and moves the control spool in the control
stated earlier, axial fans are not appropriate for valve through a linkage of levers. The control
small fan requirements or for gas recirculation. valve consists of a rotating sleeve attached

Fig. 7...Centrifugal-fan rotor undergoing static balancing in manufacturer's shop


COMBUSTION
Steam-Generator Auxiliary Equipment

Gas Flow Inlet Box

Rotor Assembl

Removable Upper Fan Housing

Removable Variable-Pitch
Rotating Blades

Main Bearing Assembly

lade Pitch Control Mechanism

Fig. 8. Two-stage variable-pitch axial-flow fan for induced-draft service

directly to the hydraulic cylinder and a non-


i
rotating spool linked to the external control
unit. With the displacement of the spool, pres-
surized oil flows, accompanying the cylinder
movement; the oil is fed back directly to the
control valve. Thus, an accurate location of the
blade pitch is obtained.
A thrust ball bearing at the blade root sup-
ports the blade, and is subject to high centrifu-
gal force. The bearing is one of the most critical
elements, as it fluctuates under severe static
loading. Such working conditions are most
strenuous on such bearings, which require sub-
stantial attention in design, with life tests man-
datory to simulate actual operating conditions.
FAN CHARACTERISTIC CURVES
Fig. 11 shows a typical sit bf constant-speed
characteristic curves for a centrifugal fan with
backwardly inclined blades. Although by ap- Fig. 9. Construction view of two-stage axial-flow fan
plying principles of geometric and dynamic with upper housing not yet in place
COMBUSTION
Steam-Generator Auxiliary Equipment I

similarity, the performance of a single fan of a


given type may be used to determine the char-
acteristics of a complete line of sizes, each sep-
arate type must be tested independently. The
curves are for one speed only; when a constant-
speed motor drives the fan, it will operate
somewhere on the characteristic curves, de-
pending on the resistance imposed by the sys-
tem through which the air passes. The system
resistance, therefore, acts as an automatic con-
trol on the fan and will limit the amount of
overload that can be developed, despite the flat-
ness of the pressure characteristic. The amount
of overload depends also on the shape of the
horsepower curve.
To fully appreciate the significance of fan
characteristic curves, realize that every fan is
restricted to that performance defined by its
curve. The fan must operate at a point that lies
somewhere on the characteristic plot. For
example, if the head required for a given vol-
ume is less than that specified by the curves,
additional resistance must be placed in the
system; otherwise, the fan will put out more
capacity until it reaches a point on the char-
Fig, 10. Schematic arrangement Of pitch acteristic curve at Tvhichthe head matches sys-
for adjustable blade axial-flow fan
tem resistance. The fan has no choice; it must
operate at a point on the curve where head, ca-
pacity and system resistance balance.
DEVELOPMENT OF PERFORMANCE CURVES

Fan performance curves are normally de-


veloped from base test curves, which, in turn,
are developed from test data recorded under
controlled laboratory conditionsl. For continu-
ity throughout industry, as well as'for ease
of understanding and ready comparison, test
data are corrected or adjusted to what is known
as standard conditions. Standard conditions
for fan design work denote that all flow, pres-
sure and power values are at 70F and sea
Flow Volume, O/O level, with air density of 0.075 lb per cu ft.
Normal curve format consists of a graph
which has the air or gas volumetric flow nu-
Fig. 11 Chart showing typical constant-speed char- merically on the abscissa or horizontal axis,
acteristics for a fan with backwardly curved blades.
Pressure decreases as fan capacity goes up; this with both static pressure and brake horse-
expands the range of stable operation. Horsepower Power numerically on the ordinate or
characteristic is non-overloading. axis. Two separate curves-volume versus sta-
Stwm-Genemtor Auxiliav Equipment

tic pressure, and volume versus power-are operating at the same speed and density, is rep-
plotted on each performance curve. resented by line FG in Fig. 12. Then it is appar-
Several other variables can be incorporated ent that this size fan would be selected by the
on the constant-speed performance curves. manufacturer if the purchaser specified 24-
such things as static or mechanical efficiency, percent excess volume. At the same time the
the horsepower or pressure at various tempera- fan would satisfy the requirement of point E,
tures, altitudes, or densities, can all be plotted which requires 8-percent excess volume and
to illustrate actual conditions. Finally, in rating 17-percent excess pressure. The only advan-
from a curve, the same fan design must be re- tage in attempting to define point E on the ex-
tained. That is, a radial-blade centrifugal-fan trapolated system resistance curve, instead of
test curve cannot be used to determine the point F or G, is that the power requirement
rating of a backwardly-inclined-blade fan. given by the manufacturer will then represent a
closer estimate of the larger fan under actual
APPLICATION OF CHARACTERISTIC CURVES
operating conditions than if point F or point G
Fig. 12 illustrates the application of typical had been defined for fan selection. The fan
centrifugal-fan characteristic curves to a fan finally chosen can, however, satisfy the re-
problem in which points A, B, C, and D are cal- quirements of all three points, if sufficient
culated requirements at four load points on a power is available from the drive.
given boiler. The line through them defines the Speed Variations
system resistance. The point where this line in-
For a given fan, a family of characteristic
tersects the static pressure characteristics of any
curves can be obtained by varying the fan
fan, at any given speed, determines the point r
on the characteristic at which the fan will oper-
ate, if both curves are plotted for the same den-
sity. However, the fan can operate only on its Maximum Calculated
Actual Requirements
characteristic curve. If any error has been made
in calculating point D-in volume or pressure,
or temperature-that point will not fall on the
characteristic curve and the fan may not meet
the requirements when operating at that partic-
ular speed.
For example, if 10 percent more volume is
needed at the same pressure, point D will be
displaced to the right, but the available pres-
sure at the fan head at the same time drops 14
percent and the fan cannot satisfy the require-
ments. Similarly, if the volume is correct but 10
percent more pressure is needed, the volume
that the fan would deliver at the greater pres-
sure would be only about 90 percent of the re-
quirements, because the fan can operate only Volume Entering
on its characteristic curve for a given speed and Fan, Percent
density condition. Maximum Calculated
To provide excess capacity it is customary to -
Actual Requirements
specify the volume and pressure in excess of
-the actual calculated requirements and thereby
obtain a larger fan. Suppose a portion of the Fig. 12 Use of characteristic curves as applied to
pressure characteristic of this larger fan, a problem of centrifugal fan selection
Steam-Generator Auxi1i;ry Equipment

speed.' The nature of each curve remains the VARIABLE INLET VANES
same because the change in operating speed Sometimes variable inlet vanes (Fig. 14) are
merely shifts the curve by a proportionate used to control fan performance by providing
amount. A graph like that of Fig. 13 results if swirl to the fan impeller; -saving significant
system resistance is plotted on the same grid as power. Variable inlet vanes tend to be slightly
the family of curves for different fan speeds. more effective in saving power than paral-
lel blade inlet box dampers. When furnishing
FAN CONTROL variable inlet vanes for either centrifugal
Very few applications permit fans to operate or fixed-pitch axial fans, fan manufacturers
continuously at the same pressure and volume. provide a complete performance envelope
Therefore, to meet the requirements of the sys- showing the effect of vane position on fan per-
tem, some means of varying fan output be- formance and power. Fig. 15 shows the typical
percentage range in power reduction along a

.
comes necessary. Capacity control of a fan can
be achieved in two ways: constant system resistance line as a percentage
of design flow for a backwardly-inclined airfoil
controlling the aerodynamic flow into or
centrifugal fan.
within the fan
An inlet-vane-controlled centrifugal fan is
controlling the speed of the fan selected to produce full specified flow and
The first method refers either to altering the pressure with no inlet vanes present. Inlet
flow of gas into the eye of a centrifugal-fan vanes then throttle down this maximum per-
wheel as with inlet vanes, or changing the formance capability so that the fan can operate
internal aerodynamics by altering internal over the range of normal boiler operating load
geometry as with controllable pitch axial fans. points. Fig. 16 illustrates the effect of this type
The second method refers to any speed- of control system, which is extremely sensitive
changing device such as a turbine, fluid drive, at the lower load conditions. Extremely minor
multiple-speed motor or an electronically changes in inlet vane openings have a dramatic
adjustable motor drive connected to the fan. effect on the flow produced by the fan, whereas
at higher loads it requires increasingly larger
movement of the inlet vanes to have any effect
Static on the flow produced by a centrifugal fan.
Pressure Rise AXIAL-FAN BLADE PITCH CONTROL

The axial-flow fan can control flow at con-


stant speed by varying the blade angle of the fan
(Fig. 17). The effect is to create a unique
aerodynamic configuration for the fan at each
point of operation so that the fan is operating at
maximum possible efficiency. As the blade
angle is adjusted from minimum to maximum
position, the flow change is nearly linear (Fig.
16). Another aspect of control rests in the re-
sponse time of the fan. Most axial-flow fans can

I Flow - I
move the blades a full stroke, from the
maximum open to fully closed position in 30
m
Fig. 13 Fan speed of a centrifugal fan can be varied
seconds. This means that under the normal
boiler operating range, an axial fan can respond
so that output pressure matches system resistance or move from maximum continuous conditions
for desired volumetric flow; this conserves energy. to zero flow in approximately 20 seconds.
COMBUSTION
Steam-GeneratorAuxiliary Equipment

Fig. 14. Inlet vanes give an initial spin to air entering a centrifugal fan. By adjusting angle of vanes, the degree
of spin and volumetric output are regulated.

Air Flow

Specified Conditio

0' 10 20 30 40 50 60 70 80 90 100 110 120130140 150160 170


Percent Volume

Fig. 15. Typical airfoil blade centrifugal-fan performance characteristics-constant-speed with variable
inlet-vane control
COAdBUSRON
Steam-GeneratorAuxiliary Equipment

SURGE OR STALL LIMIT the upper end of the several blade-pitch lines,
The surge limit of a centrifugal-fan is that with the dotted lines extending downward and
point near the peak of the pressure curve corre- left to the recovery point, where another rever-
sponding to the minimum flow rate at which sal takes place. At Iow blade angles, the fan
the fan can beoperated without instability. The tends to get noisy and somewhat unstable, but
stall limit of an axial fan is that point near the it no longer is subject to stalling. (A detailed
peak of the pressure curve at a particular blade discussion of stalllair separation is beyond the
angle corresponding to the minimum flow rate scope of this text.)
at which the fan may be operated without sep- FAN SPEED CONTROL
aration of airflow over the blades. Operation in Controlling the fan speed is potentially the
the surge or stall region for any length of time most efficient form of capacity control. The
should be avoided. Such operation can result in only significant inefficiency that a speed con-
a substantial reductionin fatigue life. trol system can introduce to a fan results from
An aerodynamic characteristic of all axial the inefficiencies of the speed control system.
fans (just as with an airplane), stall is under- All speed control systems yield certain
stood by few. A stall occurs when the angle of operationallreliability improvements to large
attack of the fan blade (or airplane wing) ex- fans in induced-draft servick. They include
ceeds a certain value in relationship to air reduction in erosion approximately propor-
velocity. When this angle of attack value is ex- tional to the ratio of the squares of the impact
ceeded, airflow becomes separated from the velocities
convex side of the blade. Centrifugal force then
throws air trapped in this separated portion in a
radial direction, to the outer tip of the blade. At
this point, pressure builds up until it is relieved
through the blade tip clearance. This process
creates a very unstable and oscillating pressure
force on the blade, and can cause very severe
vibrations throughout the entire fan. A reduc-
tion in fan flow and head capability also occurs
when operating in this mode.
In Fig. 18, the flow separation points occur at

100- -100
s

25 50 75 100
Volume, OO/
-
Fig. 16 Comparison of inlet-vane flow control ver- Fig. 17. Close-up of adjustable airfoil blading
sus blade-angle flow control of an axial-flow fan
COMIlUmON
Steam-GenentorAuxiliary Equipment

reduction i n mechanical shock at start-up operation, an impeller attached to the driving


adjustability of speed to any point within the motor accelerates oil particles and i~npinges
operating speed range them against a runner attached to the driven
fan. Speed is adjusted by changing the volume
reduction in potential fan system-oriented of oil in the system and thus the transmittable
problems (fanlfoundation, fanlductwork, fan torque. The hydroviscous method is similar in
noise) at reduced running speeds principle, but relies for speed change upon the
reduction in electrical power surge on motor increase in torque transmitted by the oil used
start-up between alternate rows of driverldriven plates
that are forced closer together.
The primary disadvantage of adjustable- Fluid drives have been used extensively
speed drives is their cost which, depending on where speed changing was required on large
unit size, can be significantly more than a centrifugal fans. They are more efficient than
single-speed motor drive with inlet-vane con- single-speed inlet-vane control as volume out-
trol. Also, adjustable-speed drives add addi- put drops below about 75 percent. They are.
tional components to the drive train which however, the least efficient adjustable speed
require more careful consideration of sys- method of gas volume control, giving away es-
tem dynamics to avoid torsional oscillations sentially a percent of efficiency for each per-
or other undesirable phenomena. cent of speed reduction. They also add another
mechanical device in the drive train which in-
Fluid-Drive Speed Control
creases the cost of installation, requires cool-
For speed adjustment, fluid drives are either ing equipment, and possibly increases initial
hydrokinetic or hydroviscous. In hydrokinetic fan size due to slip at full speed.

iI

Specified Cond~t~ons 1
II
I

0' 10 20 30 40 50 60 70 80 90100110120130140150160170
Percent Volume

Fig. 18. Typical axial-flow fan performance characteristicswith variable-pitch bladecontrol


COMBUSTION
Steam-Generator Auxiliary Equipment

Two-Speed Motor Drives .current during start-up. This lower current


As a centrif ! fan is vaned or dampered characteristic can provide significant savings
down f r o r Jecified point, its efficiency in the electrical distribution system. It also
falls off r ,pidly. If, however, at the nor- eliminates the need for long intervals between
mal ope1 goint, fan speed is changed to a motor starts which are needed to dissipate the
lgwer E speed and the vanes or dampers heat generated by the high starting current.
?openi:d, a system efficiency is achieved Wound-rotor motor current is essentially pro-
~ h i c hmatches the original full load levels. portional to the load torque.
'his is the principle of application of two- Synchronous motor adjustable-frequency
peed motors to power fans. Many two-speed systems use static electronic control equip-
notors have been applied to fans to gain the ment to adjust frequency and voltage. The syn-
overall high efficiencies available from two chronous motor is an AC device with two sets
running speeds. Also, the two-speed motor of windings, one fixed in the stator (frame) and
drive is the least expensive and least complex the other wound around field poles which are
speed control method. An objection frequently fixed to the rotor in pairs. For a given fre-
voiced is that operators hesitate to change to quency, the number of poles determines the
the lower speed until far below the designed speed of the motor. To run the synchronous
load limit, which of course negates the planned motor, the stator windings are energized by
economy of the system. connection to an AC power source. The rotor
field pole windings are excited by a DC power
Variable-Speed Drives
source. A magnetic coupling then exists be-
A variable speed system significantly im- tween the stator and the DC field pole windings
proves fan efficiency during periods when the which are separated only by a small air gap.
boiler is operating at less than its maximum The windings in the stator when energized
load. A centrifugal fan can be equipped with an with an AC power source set up a rotating mag-
adjustable-speed drive, a control and monitor- netic field around the stator. The magnetic DC
ing system. The speed control range can be fields on the rotor couple with the rotating AC
tailored to a particular installation and drive field and, thus, mechanically follow the rotat-
system costs can be optimized. By equipping ing AC stator field. This causes the rotor to turn
a fan with both adjustable speed capability and at the same speed as the rotating AC field.
inlet vanes, the fan output can be tailored to Sometimes, when a supply of exhaust steam
match all possible boiler operating conditions. is available, boiler fans can be driven by steam
Slip-ring (or wound-rotor) motors provide turbines. Such an arrangement is frequently
step changes in speed by connecting the motor used in industrial plants to achieve an efficient
windings to an adjustable external resistance heat balance-as well as drive the fan. Speed
through slip rings and brushes. By changing variation is feasible down to about 35 percent
rotor circuit resistance, the motor speedltorque of rated turbine speed.
characteristics can be adjusted to fit changes in
FAN SELECTION
load conditions. With no resistance in the rotor
circuit (rings-shorted condition), the wound- Once the boiler or scrubber engineer deter-
rotor motor will operate exactly the same as a mines the pressure and flow required by the
squirrel-cage motor. system at rated load, at the specified condition
Another important difference is the starting (with margin) and at various load points, this
characteristics of the motor. The wound-rotor information can be plotted and the fan selected.
motor inrush current can be as low as the mag- A centrifugal fan will have its specified point
netizing current-normally about 30 percent of fall within the area of maximum efficiency. At
rated current. Most other induction motors this point, the fan is operating wide-open with
draw a very high (600 to 700 percent of rated) no restrictions. To achieve the lower load
COMBUSTION
Stem-Generator Auxiliary Equipment

points, inlet vanes are closed to throttle the individual load points for the entire life of the
maximum capability of the fan. As the fan per- unit must be multiplied by the associated
formance moves down the system resistance power consumptions of the fans being com-
line, it moves through areas of constant effi- pared. Maintenance costs also must be consid-
ciency that fall perpendicular to the system re- ered by analyzing available historic data.
sistance line.
The characteristic curve for an axial fan is FAN SIZE SCALE-UP
considerably different from that of a centrifugal Most fan designs are developed using
fan. Given exactly the same system resistance models of moderate size and input power.1 The
curve, an axial-fan designer will select a fan performance obtained from the model provides
that operates at maximum efficiency at boiler an information base to calculate the per-
full load. If normal fan performance tolerances formance of larger fans that are geometrically
have been used, the fan will usually have the similar to the model. If only the basic fan laws
capacity to achieve the specified requirements. are used to make these conversions, (with no
If higher-than-normal tolerances have been correction for compressibility of air) the larger
applied, a less-than-optimum selection will fan, in many cases, will perform better than
have to be made, in which full boiler load does predicted, providing that all geometric, kine-
not fall inside the maximum efficiency area. matic, and dynamic similarity requirements
The oblong or egg-shaped areas on the axial-fan are satisfied. Geometric similarity requires not
curve are the areas of constant static efficiency. only linear proportionality but also requires
It is important to note that these areas for the complete angular similarity without omission
axial fan are oblong in a direction approxi- or addition of parts.2
mately parallel to the system resistance line The three main performance factors of flow,
rather than perpendicular to it, as with the cen- speed, and head are linked in the concepts of
trifugal fans. Changes in flow requirements specific speed and specific diameter.
along the system curve cause only slight Specific speed is that rpm at which a fan
changes in efficiency compared to the signifi- would operate if reduced proportionately in
cant changes in efficiency for constant-speed size so that it delivers 1 cfm of air at standard
centrifugals. The lines that are perpendicular conditions, against a 1" WG static pressure.
to the system line on the axial curve depict the
angle of the blades at that point of operation.
Speed Control (Actual)
COMPARISON OF FANS AND FAN CONTROLS and Variable-Pitch AxialA
100-
Table I1 summarizes the available fans and Inlet Vanes at
operational control equipment; generally, with '
increasing efficiency of either draft equipment
or controls, cost increases. Fig. 19 shows the
power consumed by the various designs over
the full range of capacity.
In comparing the several types, both capi-
tal and operating costs must be established
over the anticipated load range. The cost of
fans, controls, drives, silencers, foundations,
switchgear and other auxiliaries, plus any dif-
ferences in ductwork, have to be obtained for - . Flow Volume, O/O
equal specified capacities and sound-pressure
levels. Based upon the relative power- ~ i g 19. . Comparative fan power consumption ver-
consumption curves, the operating hours at the sus volumetric flow with various types of control
COMBVSIION
Steam-Generator Auxiliary Equipment

Specific diameter is the fan diameter re- where flow in cfm is at standard conditions, SP
quired to deliver 1 cfm standard air against a 1" is static pressure (in. of water), and D is the di-
WG static pressure at a given specific speed. ameter of the fan in inches.
From the fan laws we get these equations: Table I11 shows the parameters for designing - -.

to "specified" pressure and volume.


rpm (cfm) ' I 2 In the case of axial fans, maximum flow can
Specific speed (N,) = (SP) 314 be achieved by proper selection of the rota-
(5) ting-blade tip diameter, so an increase in tip
size results in a shift of the entire fan curve
D (SP) 'I' along the flow (horizontal) axis to the right.
Specific diameter (D,)= -
[cfm) 'I2 Maximum pressure can be achieved by selec-
tion of the proper hub diameter, so an increase
in hub size would result in a shift of the entire
- - fan curve along the pressure (vertical) axis up-
Table 11. Available Types of Fans ward. The system-resistance requirements
and Fan-Control Equipment given the fan designer remain the same, so by
selecting the proper hub and blade sizes, the
Centrifugal Fans fan characteristic can be shifted along the sys-
Radial tem resistance, so that boiler full-load condi-
Radial-tip tions occur in the area of maximum efficiency.
Backwardly Inclined Solid Increasing A centrifugal fan's characteristic similarly can
Backwardly Inclined Airfoil Efficiency be shifted along the system resistance line.
Over Normal FAN LAWS
Operating
Axial Fans How a change in any operating condition af-
Range
Fixed Pitch fects a fan can be predicted by a set of rules
Adjustable Pitch ,
,, known as the fan laws. These are summarized
Variable Pitch in the box on the next page and apply to fans of
Flow Control the same geometric shape and operating at the
Single-Speed Motor same point on the characteristic curve.3
Outlet Damper FANS OPERATING IN SERIES
Inlet Louver Increasing
Inlet Vane Efficiency Infrequently it is necessary to install two or -
Two-Speed Motor At more fans in series in the same system. very
Fluid Coupling Partial-Loads fan in series handles the same weight of air or
Variable-Speed Turbine Drive gas, assuming negligible air loss or infiltration
Variable-Speed Motors / between stages.
In theory the combined volume-pressure

Table Ill.Effect of Fan Parameters on Performance Capabilities


Axial Centrifugal

To increase volume: increase blade tip diameter increase wheel width


increase rotational speed increase rotational speed
To increase pressure: increase blade-root diameter increase wheel diameter
increase rotational speed increase rotational speed
increase number of stages
Steam-Geneator Auxiliary Equipment

I 1. For a given fan size, system resistance, and


FAN LAWS
I
and pressure vary directly as the air den-
air density: sity; that is, directly as the barometric
A-When speed varies, pressure, and inversely as the absolute
(a) Capacity varies directly as the speed temperature.
ratio.
4. For constant mass flow:
(b) Pressure varies as the square of the
speed ratio. A-When density of air varies,
(c) Horsepower varies as the cube of the (a) Capacity, speed and pressure vary in-
speed ratio. versely as the density; that is, inversely as
B-When pressure varies, the barometric pressure, and directly as
(a) Capacity and speed vary as the square the absolute temperature.
root of the pressure. (b) Horsepower varies inversely as the
(b) Horsepower varies as the 1.5 power of square of the density; that is, inversely as
the pressure. the square of the barometric pressure, and
2. For constant pressure: directly as the square of the absolute
When density varies, speed, capacity and temperature.
horsepower vary inversely as the square B-When both temperature and pressure
root of the density; that is, inversely as the vary,
square root of the barometric pressure, (a) Capacity and speed vary as the square
and directly as the square root of the abso- root of (pressure x absolute temperature).
lute temperature. (b) Horsepower varies as the square
3. For constant capacity and speed: root of (cube of the pressure x absolute
When density of air varies, horsepower temperature).

I
I
curve of two fans operating in series is obtained parallel are selected in the region of this pos-
by adding the fan pressures at the same volu- itive slope, unstable operation can occur. Fig.
metric flow. (Fig. 20). In practice there is some 2 1 shows the combined volume-pressure curve
reduction in volume due to the increased air of two such fans in parallel. The closed loop to
density in the later stages. There also can be a the left of the peak pressure point is the result of
significant performance loss from non-uniform plotting all the possible combinations of
flow into the second stage fan. volume flow at each pressure. If the system
FANS OPERhTING IN PARALLEL
curve intersects the combined tolume-pres-
sure curve in the area enclosed by the loop,
Fans commonly operate in parallel in the more than one point of operation is possible.
same system, particularly when large volumes This may cause one of the fans to handle more
of air or gas must be moved. The combined air than the other and could cause a motor over-
volume-pressure curve in this case is obtained load if the fans are individually driven. This
by adding the volumetric capacity of each fan at unbalanced flow condition tends to reverse
the same pressure (Fig. 21). Each fan handles readily and fans will intermittently load and
only part of the volumetric capacity. The total unload, with the possibility of damage to the
performance of the multiple fans will be less fans, ductwork or driving motors.4
than the theoretical sum if inlets are restricted When paralleling two variable-pitch axial-
or the flow into the inlets is not straight. flow fans, care must be taken to keep both units
Some centrifugal fans have a pressure- out of the stall region. Since this area generally
volume curve with a positive slope to the left of is not near the boiler resistance line, avoiding a
the peak pressure point. .If fans operating in stall situation is relatively easy. With two fans
Steam-Generator Auxiliary Equipment

.-0
+-' Characteristic
c

I I I Y I I I I
0 40 80 120 - 160 200
Volume Flow Rate, OO/

Fig. 21. Parallel fan operation

sity, hardness, shape, surface texture, velocity


and impact angle-as well as impeller material,
100
hardness, and use of wear plates-influence
erosion rates.5 Chapter 23 covers the repair of
Volume Flow Rate, O/o eroded fan blades in detail.
It is significant that fans for induced-draft
Fig. 20. Typical Characteristic curve of two fans service have become progressively more effi-
operating in series cient as more efficient dust-collection devices
have been installed. Airfoil bladed fans could
operating, the resistance line for one fan is in- not be used with particulate-collection ef-
fluenced by the other fan, as well as by boiler ficiencies below 95 to 97 percent; axial-flow
conditions. This means that the two fans to- fans required even higher efficiencies. Now,
gether will develop the pressure required to with dust loadings as low as 0.03 grains1
overcome the boiler resistance, but that their standard cu ft, the use of more sophisticated
volume flow need not be equal. - equipment is practical. During this same
period of development, there had been techni-
GAS-FAN EROSION AND CORROSION
cal developments on erosion-resistant mate-
Erosion is the loss of fan material through rials for fan blades, as well as the increased
mechanical action of particulate matter in the usage of variable speed drivers, which results
flue gas impinging on or abrading the fan sur- in further reduction of erosion.
faces during operation. FAN EROSION
Corrosion is the loss of material through the
reaction of various chemicals in the flue gas The loss of fan wheel material poses two
coming in contact with the fan. serious threats to fan' reliability. First, any
Erosion is determined not only by tip speed, change in the rotor mass distribution, espe-
but also by the properties of the impeller and cially at the outer extremities, can cause unbal-
the particulate matter in the gas. Factors such anced forces and. high vibrations. Second, a
as ash loading, particle size, composition, den- loss of material on highly stressed fan elements
-.
C0MIIUFIX)N
Steam-GeneratorAuxiliary Equipment
.-
such as blades and side plates can cause struc- environment. Note that, when axial-fan blades
tural damage and lead to catastrophic failure. erode, they normally lose material at a greater
The centrifugal fan designer can consider rate in the tip area than in other areas. This is a
several alternatives one of which is modifying less serious situation in terms of overall
the fan-blade type and speed. As described ear- strength and balance than with a centrifugal fan
lier, some fan blades are more resistant to ero- because the blade actually gets lighter, and
sion than others. Also, the ability of any given blade root stresses reduce.
fan to resist erosion is proportional to at least Because coatings can affect the physical
the square of the relative velocity of the gas properties of fan structural material, and cracks
passing the blading. The principal fan wheel in coatings can propagate into critical fan
areas attacked by erosion are the blades and the members, tests must be performed using pro-
center plate. Heaviest erosion occurs in the area posed spray coats and actual fan structures be-
where blade and center plate are joined. Ero- fore such coatings are used.
sive wear on these critical parts can be reduced
by applying a larger fan running at loker speed
FAN CORROSION
.
The problem of chemical corrosion of fans
which can meet aerodynamic requirements at has to be accounted for in the design and opera-
lower gas velocities. tion of ID and booster fans downstream of wet
Another alternative would be to modify the scrubbers. Although early experience with cor-
fan inlet conditions where it appears that duct- rosive gases entering fans was limited to chem-
work design has led to differential erosion of a ical process plants, the use of FGD systems has
fan. It is possible for flyash leaving a pre- brought the problem to the utility industry.
cipitator to be channeled down a particular leg
of a duct and to concentrate in one fan of a
multiple-fan installation, or even in one of the
inlets of a particular fan.
As a third alternative, repairable liners can
be used to control erosive effects on airfoil fans
(Fig. 22). This method consists of designing
blades with two layers of material, the outer
layer being easily repaired in the field with
welding. Periodic inspection is required to de-
termine when repairs are necessary. In addi-
tion, airfbil blades can be furnished with extra
,. thick nose pieces.
As a fourth alternative, replaceable liners to
bear the brunt of erosive forces can be provided
on fan blades. It is essential that, in the design
of a fan, the added weight of the liner plates be
accounted for in the stress calculations for the
structural members such as the blade and side
plates, as well as in specifying the moment of
inertia of the motor.
The axial-fan designer generally uses renew-
able coatings on blade leading edges and sur-
faces. In-s.0- doing, it is important that the
designer consider the strength and durability of
_ the blade base material in terms of both the ero- Fig. 22. Airfoil blades of a centrifugal fan
siveness and the temperature of the operating with repairable weld-metal liners .
COMBUSRON
Steam-Generator Auxiliary Equipment

Experience has been excellent with fans of heaters also make pulverized-coal firing practi-
standard carbon-steel or low-alloy-steel con- cal by providing the drying and transporting
struction, where the entering flue gas has been medium.
properly dehumidified and heated above the Three principal types are in use: the tubular
temperature of adiabatic saturation (which is recuperative, the rotary regenerative (Ljung-
about 130F).On the other hand, "wet" fans strom@),and the heat-pipe ((2-pipe@)air heater.
handling scrubber effluent gas without reheat- The choice of the size and type of air heater de-
ing to at least 30F above saturation tempera- pends on economic and engineering factors.
ture have undergone severe corrosion. High- The economic factors include the original cost
alloy metals used to manufacture such rotating of the air heater, the maintenance costs, the cost
equipment have proven a very expensive alter- of the fuel, and the cost of the fan power re-
native to flue-gas drying and reheating. sulting from air-heater draft losses. The engi-
ACOUSTICS neering factors include the air temperature
required for combustion andlor pulverized coal
Controllable-pitch axial fans exhibit a much
drying, as well as unit reliabilty and installa-
different noise characteristic than centrifugal
tion space requirements.
fans for similar duty. As shown in Fig. 23, a
controllable-pitch axial-fan noise signature TUBULAR AIR HEATERS
contains more acoustic power in the high fre-
quencies due to the large number of rotor Fig. 10 in Chapter 8 shows a typical applica-
bladelstator blades passages in fan operation. tion of a tubular air heater to an industrial
This factor must be considered in the design of boiler. The heater is arranged for vertical gas
any noise suppression devices for the axial fan. flow through the tubes. Air flows horizontally
Because axial fans have a slightly higher total across the tubes, usually 2 to 3 inches in diame-
noise sound-power level than centrifugal fans, ter, and in a staggered relationship for optimum
more acoustical treatment is sometimes heat transfer. The air passes over all the sections
needed. Power-plant noise and attenuation are of the air heater in sequence, the effect of which
discussed further later in this chapter. is to provide counterflow heat transfer. Tube
sheets at top and bottom support and guide the
AIR HEATERS tubes. Most frequently, the bottom tube sheet or
sheets form the structural support; the upper
The functions of combustion-air heaters have tube sheet is welded to the outside casing; and
been described in Chapters 5, 6 and 11. Al- the tubes pass throygh slightly oversize holes
though justified by the increased efficiency re- in the upper sheet which allows for expansion
sulting from lower exit-gas temperature, air when the equipment is brought up to tempera-
ture. Many designs for use with sulfur-bearing
fuels have separated cold-end sections, as
E.
shown, to reduce the cost of tube replacement
in the event of excessive corrosion.
In contrast to regenerative and heat-pipe de-
signs, tubular or recuperative type air heaters
m Centrifugal have more severe cold-end corrosion problems.
With variations in cleanliness of the tube wall,
~-I ~ 1 1 1 1 1 1 1 1 , entering air temperature, and flow intensities
on gas and air sides, very low metal tempera-
1 2 3 4 5 6 7 8 tures and correspondingly severe corrosion can
3
0
a Octave Bands occur. Although the tube-metal temperature
L I may be considered to be the arithmetic average
Fig. 23. Fan sound power level comparison of the air temperature entering the air heater
comwsnON
Stnrn-Gmmtor Auxiliary Equipment

and the gas temperature leaving, actual field ing a completely wetted surface for maximum-
measurements have shown metal temperatures possible heat transfer. (Without a wick, the
as low as 120F below the mean of the air and fluid would puddle in the bottom portion of the
gas temperatures. Such conditions can result in tube, making evaporation less efficient.) In the
deposits that reduce heat transfer and increase air section, the wick provides a roughened
draft loss until they are removed, usually by surface and, therefore, higher heat-transfer
water washing .6 coefficients.
HEAT-PIPE AIR HEATERS ADVANTAGES OF THE HEAT-PIPE AIR PREHEATER
The C-EQ-Pipeo heat-pipe air preheater is a The technology incorporated in Q-Pipe air
highly efficient heat-transfer device with no preheaters offers several benefits. Specific ad-
moving parts. It consists of many individual vantages include
heat-pipe tubes formed into an exchanger for no air-to-gas leakage
transferring heat from flue gases to incoming
minimum cold-end corrosion
combustion air. Each heat pipe is a finned steel
tube which has been evacuated, partially filled excellent cleanability
with a heat-transfer fluid, and permanently no maintenance requirements
sealed at both ends (Fig. 24). compact size
MODE OF OPERATION low weight per unit of heat transferred
short time and low cost for installation
Heat absorbed from the flue-gas stream
vaporizes the fluid within each of the self- design flexibility to suit the needs of a wide
contained heat pipes. The vaporized heat- variety of applications
transfer fluid travels up the tube, transporting the individual operation of each heat pipe, so
heat to the cooler combustion-air side. In the that the loss of a single pipe has minimal
combustion-air end, the working fluid releases impact on the overall efficiency of the pre-
its heat energy, is condensed, and returns to the heater system
flue-gas side. As long as a temperature differ-
ence is maintained externally between those
two areas, and the hotter temperature is ade- The function of the working fluid inside the
quate to vaporize the working fluid, a heat pipe heat pipe is to absorb the heat energy received
is a self-operating and self-regulating device. at the evaporator end, transport it through the
Q-Pipe heat pipes are installed at a slight an- pipe, and release it at the condenser end. It is
gle (4 to 7 .degrees), with the flue-gas ends this process that is called vapor heat transfer.
lower than the combustion-air section to gravity- When a liquid vaporizes, two things happen.
assist the return flow of the liquid. First, a large quantity of heat is absorbed from
A unique feature of the Q-Pipe heat pipe is its the heated area. This takes place because en-
ability to enhance heat transfer by means of a ergy is needed to separate molecules that are in
patented internal capillary wick. This wick is a contact in the liquid state; the energy required
circumferentially spiralled groove that is an for evaporation at a given temperature is the la-
integral part of the inner wall surface of the tent heat of vaporization. Second, as the work-
tube; it is continuous along the entire length of ing fluid vaporizes, t h e pressure at the
each heat pipe. In creating the wick, no mate- evaporator end of the pipe increases; this is
rial is removed; the metal is merely displaced, caused by the thermal excitation of the mole-
as shown in Fig. 25. cules comprising-the n&vly created vapor. The
The wick serves two different purposes. In higher vapor pressure sets up a pressure differ-
the gas section, it distributes the liquid around ence between the ends of the pipe which causes
the entire inner circumference, thereby provid- the vapor, and thus the energy, to move toward
COMBUSllON
Steam-GeneratorAuxiliary Equipment

Flue Gas
Combust~onAs

I Fig. 24 Heat-pipe tube for C-E Q-Pipe air preheater

the condenser end. There, it encounters a tem-


perature lower than that of the evaporator. The
vapor then reverts to a liquid and releases the
thermal energy stored in its heat of vaporiza-
tion. In addition, as the fluid' condenses, the
vapor pressure created by the molecules de-
creases, so that the necessary pressure differen-
tial for continual vapor heat flow is maintained.
The condensed liquid returns by gravity to the
evaporator to complete the cycle.
It is important to note that the vaporized fluid
stores heat energy at the temperature at which
the vapor was created, and that it will retain the
energy at that temperature until it meets a
colder surface. The result is that the tempera-
ture along the entire length of the heat pipe
tends to remain constant-essentially isother-
mal. It is this tendency to resist any difference
in temperature within the heat pipe that is re-
sponsible for its high thermal conductance.
There are four properties of the heat pipe
that serve to define the areas for its practical
application:
Devices that operate on the principle of vapor
heat transfer can have a much greater heat-
transfer capability than the best metallic con-
ductors. Fig. 25 Patented capillary wick improves efficiency.
MMBUSnON
Steam-GeneratorAuxiliary Equipment

A second property is called "temperature flat- both sides, with sleeves supporting them at the
tening'', which provides a uniform temperature outboard ends. The Q-Pipe preheater is, then,
over a large surface area. for all practical purposes, a zero-leakage heat
The evaporation and condensation functions exchanger, one that is especially suitable where
are essentially independent operations con- there are very high air-to-gas-differential
nected only by the streams of vapor and liquid pressures.
in the pipe. Thus, the process occurring at one
CORROSION AND FOULING
end of the pipe can take place uniformly or
nonuniformly, over a large or small surface Cold-end corrosion when handling sulfur-
area, without significantly influencing what is bearing flue gases occurs at the juncture of the
going on at the other end. cooled-gas outlet and the incoming cold air.
The heat source can be separated from the Typically, at least a portion of every tube in the
heat sink. It is often inconvenient or undesir- cold end of a tubular air heater will have a
able to have the heat source and the consumer metal temperature below the acid dew point,
of heat in close contact. leading to corrosion of the carbon-steel tubing.
Although the heat pipe is a highly versatile Because a Q-Pipe air preheater operates to-
device, it must operate within certain design tally on counterflow principles and the pipes
limitations. Four limiting factors govern its op- are isothermal, cold-end corrosion is minimal.
eration: the maximum total thermal power that Air- and gas-stream temperatures along the row
can be transferred in a device of a given size; of pipes are essentially uniform, with a much
the maximum power per unit of evaporator area smaller percentage of the total tube bundle at a
that can be handled safely; the maximum and temperature below the acid dew point. Also the
minimum useful temperatures for a given work- lack of turning baffles (which can add to the
ing fluid; and, the extent of operation in a gravi- thermal stratification) effectively eliminates
tational field or other acceleration. Detailed temperature gradients in the gas and air outlet
treatment of these factors is beyond the scope of ducts under all load conditions.
this text.' The drier the surfaces of an air heater, the less
flyash accumulation throughout the operating
COMPARISONTO A TUBULAR AIR HEATER range of the boiler. Furthermore, as a deposit
begins to form at the cold corner of a tubular
As described in a previous section of this heater, the problem accelerates. The insulating
chapter, a tubular air preheater is constructed effect of the initial deposit extends the area of
by connecting tubes between tube sheets; the undesirably cold temperatures, thereby increas-
connections'are made most commonly by ing the potential area of flyash fouling.
means of either tightly or loosely rolled joints.
FLEXIBILITY OF DESIGN OF HEAT-PIPE PREHEATERS
As gas and air flow through the tubular ex-
changer, the thermal gradients that are gener- Q-Pipe heat pipes are presently available in
ated demand that the various tubes grow in lengths up to 42 feet (12.8 meters). The pipes
length at different rates and amounts. Either by can be manufactured as bare pipes without fins,
design or by thermal action, joints loosen and or with segmented or solid spiral steel fins that
the higher pressure air leaks into the gas are attached by a continuous weld.
stream. Such leakage results in increased The fin spacing can range from one to six fins
pumping costs for both the gas and air streams. per inch, depending on the range of fuels to be
The tube bundles of a Q-Pipe preheater are fired in the boiler. To increase heat recovery
made up of a number of heat pipes completely while still maintaining ease of cleaning, fins
seal-welded to the structure dividing the air can have a closer spacing on the air side.
and gas streams (see Fig. 26). The ends of the If specified, a configuration incorporating re-
heat pipes are free to expand independently on movable tubes at the cold end can be provided.
COMBUSTION
Steam-Generator Auxiliary Equipment

Also, the Q-Pipe counterflow design accommo- A heat pipe, by design, operates on the satu-
dates space for future heat-transfer surface to ration curve of its working fluid. The internal
increase the gas drop through the preheater if pressure, then, is a function of the temperature;
later desired. - - -the higher the temperature, the higher the pres-
sure. To provide maximum service life, operat-
CHOICE OF WORKING FLUID ing-temperature limits of 550F (290C) for
Prior to the charging of the heat-transfer toluene, and 800F (430C) for napthalene,
fluid, each heat pipe is evacuated to a pressure have been established. These have correspond-
of 100 micrometers of mercury or less, at ambi- ing maximum internal pressures of 405 and 398
ent temperature. After charging with an aro- psig, respectively (2.79 and 2.74 MPa gage).
matic hydrocarbon, usually toluene or The tubing thicknesses selected for air-
napthalene, the fill tube is closed off by a radi- preheater heat pipes are in strict accordance
ally symmetric cold weld, followed by a fusion with the allowable pressures stipulated by
weld to assure an absolute and reliable seal. the ASME Boiler Code for the material used.

I Heated I
Combustion Air

ccess/lnspection Door

Cooled Flue Gas

Fig. 26 Assembly of C-E 0-Pipe zero-leakage air preheater


COrnrnON
Steam-Generator Auxiliary Equipment

INSTALLATIONOF Q-PIPE AIR PREHEATERS The air preheater design can accommodate
The time required and costs associated with any steam-generator duct arrangement. The air
the field installation of Q-Pipe preheaters are preheater ducts and heating surface can be po-
substantially less than those of tubular heaters. sitioned for either vertical or horizontal flow.
Normally, a tubular preheater is shipped as The vertical-shaft air preheater can be arranged
side and end panels, tube sheets*baffle plates, for flue-gas flow upward or downward, while
and loose tubes. Each tube must be rolled or the horizontal air preheater can be arranged for
welded in place on the job site. A Q-Pipe pre- gas-over-air or air-over-gas at the option of the
heater is compact in size and is shipped in two plant designer.
to six shop-fabricated modules, as governed by The electric motor provides drive action
shipping limitations. Freight and site installa- through a speed-reducer pinion gear which en-
tion costs are thus much lower; the modules are gages a pin rack attached to the periphery of the
simply set in place and seal-welded together. rotor.
Ljungitrom air heaters are designed with
REGENERATIVE AIR HEATERS rotor diameters from 7 to 65 feet. The smaller
units are completely shop assembled, while the
The Ljungstrom air re heater transfers semi- larger utility size units are arranged for conven-
ble heat in the flue gas leaving the boiler to the ient field assembly.
combustion air, through regenerative heat-
transfer surface in a rotor which turns contin- HEATING SURFACE DESIGN
uously through the gas and air streams at from
1to 3 rpm (depending on diameter.) The princi- The heating surface of a Ljungstrom preheat-
ple is illustrated in Fig. 27. er uses combinations of flat or formed pressed-
Fig. 27 also illustrates the major components
of a large vertical-shaft Ljungstrom air pre-
heater designed for gas flow downward and air- AIR HEATER TEMPERATURE TERMINOLOGY
flow upward. The rotor, packed with efficient Exit-Gas Temperature with Leakage (cor-
heat-transfer surface, is supported through a rected)-This is the observed or measured
lower bearing at the cold end of the air preheater exit-gas temperature and includes the dilution
and guided through a guide-bearing assembly effect of leakage through the air-heater seals.
located at the top or hot end. Exit-Gas Temperature, No Leakage (uncor-
Depending on its size, the rotor has either 12 rected)-This is the temperature at which the
or 24 radial members, which are attached to a gas would leave the heater if there were no
center post. The rotor compartments are closed leakage in the heater. This temperature cannot
with a shell plate as shown in Fig. 27. The rotor be measured directly, but is arrived at by ac-
sealing system contains simple leaf-type counting for the cooling,effect of the leakage
air by calculation. (See Chapter 6.)
labyrinth seals bolted to the rotor radial mem- Gas Drop-Temperature of the gas entering
bers at both the hot and the cold ends. The ra- heater minus temperature of the gas leaving
dial seals compress against radial plates, again heater (not including leakage).
located at both the hot and the cold ends of the Air Rise-Temperature of the air leaving
rotor. To complete the system, axial seals are heater minus that of the air entering heater.
positioned at the peripheral end of the radial Temperature Head-Temperature of the gas
members of the rotor. There are also leaf-type entering heater minus air temperature enter-
labyrinth seals used with axial sealing plates. ing heater.
This systeineffectively separates the air stream Gas Side Efficiency, percent =
from the flue-gas stream. Both the radial and Gas Drop
axial sealing plates can be adjusted during op- Temperature Head
_
eration for maximum effectiveness.
COEdBUSRON
Steam-GeneratorAuxiliary Equipment

steel sheets with corrugated, notched or undu- Normally, the heating surface is divided into
lated ribbing. When in combination, they form two or more layers (Fig. 27). Advantages result-
longitudinal passages of the most desirable ing from layering include the ability
contour for the predetermined spacing. The to provide a field-removablecold-end section,
- surface design and arrangement provides only usually 12" (300mm) in height, that can un-
point contact between adjacent plates. Al- dergo severe corrosive duty and be first reversed
though the gas and airflow are turbulent, the in position, and then replaced;
smooth path for their travel through the rotor to vary the configuration of surfaces through-
offers low resistance. As an approximate rule. out the preheater to satisfy different operating
one inch in height of this highly efficient heat- demands: and
ing surface recovers about as much heat as two to make sheets in each layer of different mate-
feet of surface in a tubular heater with equiva- rials, each to accommodate the temperature
lent resistance to gas and air flow. The compact and other conditions particular to its zone.
arrangement of light metal sheets permits a Large rotors have 24 self-supporting compart-
large amount of effective heating surface to be ments extending the full length of the heater ax-
placed in a relatively small rotor. The metal ially and fabricated as separate modules; the
sheets are factory packed in containers. 15%ompartments consist of two side plates

Cold-End Eleme

~ Fig. 27. Ljungstromregenerative air preheater, bisector design for vertical air and gas flow
COMEUSTION
Steam-GeneratorAuxiliary Equipment

FACTORS AFFECTING REGENERATIVE AIR-HEATER PERFORMANCE

Entering Air Temperature A decrease in the HCR results in an increase


A change in entering air temperature will in the exit-gas temperature. A 10 to 12 percent
cause the exit-gas temperature to change in the change in this ratio may alter exit-gas tempera-
same direction. Changes in entering air temper- ture by as much as 30' to 35F (15" to 20C).
ature result in a change in temperature head Factors that affect the HCR include tempering
which directly affects the drop in gas tempera- air, overall boiler-system infiltration, and air-
ture. For example, if the entering air tempera- heater bypass for cold-end protection.
ture increases l o 0 , the exit-gas temperature Pressure Drop Across Air Heater
will increase by 10 x (gas-side efficiency/
The air and gas side pressure drops will
100)O. change approximately in proportion to the
Entering Gas Temperature square of the air and gas weights through the
A change in entering gas temperature causes heater. If excess air is greater than anticipated,
the exit-gas temperature to change in the same the air-heater pressure drop will be greater than
direction. Changes in entering gas temperature expected. A build-up of heating element depos-
result in a change in temperature head which its will result in higher air heater resistances
directly affects the drop in gas temperature. For ~viththe consequence of an increase in pressure
drop. Pressure drop will also vary directly with
example, a l o 0 increase in entering gas tem-
the mean absolute temperatures of the fluids
perature will cause the exit-gas temperature to
passing through the heater as a result of
increase by 10 x [ I - (gas-side efficiency1
changes in density.
lO0)l0.
.Iir Heater Leakage
Gas Weight
A change in the temperature of the fluid leak-
An increase in gas weight to the heater will
ing past the seals will. by reason of density
result in a higher exit-gas temperature. while
change, have a slight effect on the amount of
conversely, a lower exit-gas temperature results
leakage. Variations in pressure levels between
from a lon~ergas weight entering the unit.
the high and low pressure sides of the heater
Heat-Capacity Ratio will, Gkewise, alter the air heater leakage. An
Also called the ratio, the heat-capacity increase in the pressure differential will in-
ratio (HCR) = crease the leakage while a decrease in pressure
differential will reduce the leakage. Improper
mass flow of air x avg. specific heat of air settings of the heater radial and circumferential
mass flow of gas x avg, specific heat of gas seals will also result in an increase in leakage.
I I

connected by a series of circumferential stay used to transport the pulverized fuel to the fur-
plates and grating. With this rotor design, the nace. This portion of the total air for combus-
rotor post is placed upon its bearings and the 24 tion is called the primary air (Fig. 28).
rotor modules are then pinned in place, a tech- The trisector air ?reheater is used on large
nique that eliminates any field welding. The coal-fired boilers where a cold primary-air fan
basketed heating surface is usualljr installed in is desirable. The preheater is designed so that
each module before the unit is shipped. by dividing the air-side of the preheater into
TRISECTOR AIR PREHEATERS two sectors (Fig. 291, the higher pressure pri-
In Chapters 5 and 11, the discussions of the mary air and the lower pressure secondary air
direct-fired pulverized-coal system included may be heated-by a-single air preheater. Some
the necessity of air heating for coal pulveriza- advantages of the trisector over arrangements
tion. Ordinarily, hot air supplied to the pulver- having separate primary- and secondary-air
-
izers furnishes the heat to dry the coal and is preheaters include
COMBUSTION
Steam-Generator Auxiliary Equipment

no gas-biasing dampers and controls


B because average cold-end temperatures can be
maintained using only secondary-air preheater
coils, the requirement for primary-air steam
coils is eliminated
fewer sootblowers and water-washing devices
are required with one heater in lieu of two
even with a large variation in primary airflow,
there is relatively little effect on overall heat re-
covery, because heat not recovered in the pri-
mary section will be picked u p i n the
secondary section. ,

The trisector is equipped with an additional


radial sealing plate and an axial sealing plate
separating the primary and secondary air
streams. The trisector heater is readily adapt-
able to varying coal moisture content. The size
of the primary-air opening depends on the coal
being fired and its moisture content, with a
3 5 3 503 on 72" primary-air opening normally
Fig. 28 Trisector air heater arrangement
furnished.
EFFECT OF THERMAL GRADIENTS ON cant metal temperature gradient through the air
REGENERATIVE-PREHEATER STRUCTURAL preheater which, in turn, leads to a predictable
DEFORMATION deformation in the shape of the cylindrical ro-
The continuaus process of heat exchange be- tor. The hot or entering gadexiting (hot) air side
tween cold air and hot gas result: in a signifi- expands radially becoming larger in diameter

Gas Sector

Secondary Air Sector

Primary Air Sector

Fig. 29 Ljungstrom trisector air preheater, vertical-shaft arrangement


--
COMNlsnON
Stwm-Generator AuxiIiary Equipment

and convex. The cold or entering aidexiting the hot-end radial seal clearance increases as
(cooled) gas side end remains smaller in diame- the rotor approaches its operating temperature
ter and becomes concave. and these seals move away from the sealing
To compensate for this thermal distortion, the plate.
radial and axial seals are set, in the cold condi- Controlling the hot-end radial seal clearance
tion, a prespecified distance from their respec- during operation requires the installation of a
tive sealing plates. During normal operation, in drive system to move each sector plate, and a
the hot condition, these preset gaps are reduced control system to automatically operate the
to near-zero. drive. (Fig. 30).
The shape of the stationary housing is also af- The sector.plate drive assembly is comprised
fected by the temperature it attains. To further of an electric motor, speed reducer, and two me-
enhance the effectiveness of the sealing system chanical screw actuators mounted to a welded
the radial and axial sealing plates are attached steel base. The electric motor is operated by the
to the housing structure through pinned con- control system in response to changes in seal
nections. The sealing plates are thereby freed clearance detected by a rotor position sensor.
from the effects of the thermal distortion of the The rotor sensors are attached to each hot-
housing. The pinned attachments also serve as end sector plate and are actuated upon contact
adjusting mechanisms: the sealing plates can by a sensing lobe that is located on the outer
be accurately positioned relative to the rotating circumference of the rotor.
leaf seals, on-line if necessary, to achieve an op- When the system is in the "auto" mode, the
timum running clearance. drives independently move the outboard ends
The Ljungstrom Air,Preheater Leakage Control System
of the sector plates approximately 1/16"
(1.5mm) per min. toward the rotor. Upon con-
On larger air preheaters, a leakage control tact with the rotor lobe, the sensor signals the
system is furnished. This system acts to mini- drive to stop and retract the sector plate a small
mize the air-to-gas leakage which occurs when distance from the rotor, leaving a nominal clear-

eal Access Door

Fig. 30 Sector-plate drive assembly for Ljungstrom air preheater leakage control system
COMBSIION
Steam-Generator Auxlllary Equipment

ance at the periphery. If the seal clearance Moisture can be introduced as drainage from
changes as a result of temperature change in the waterxooled gas analysis probes, economizer
rotor, the drive system will automatically main- and boiler tube leaks, and unprotected FD fan
tain an acceptable clearance. - - -: inlets through which rain can enter the air
heater. Leaking steam-sootblower and water-
Effect of Rotary Regenerative Air Preheater Leakage
washing shutoff valves add to the problem. But
Even with such provisions for minimizing the most frequent source of external moisture is
the air-to-gas leakage as described in the previ- the sootblowing steam. Moisture in this blow-
ous two sections, such leakage is a design factor ing medium can be eliminated by selecting a
that must be taken into account in the sizing of steam source with controlled pressure and tem-
boiler fans. The leakage is defined further as perature to provide dry steam to the sootblowers
follows. at all times.
Direct leakage is that quantity of air that Air-heater element fouling also can result
passes into the gas stream between the radial from the carryover of material from the econo-
and circumferential seals and sealing surface as mizer and the subsequent lodging of the larger
a result of the static pressure differential be- particles in the heating surface, particularly at
tween the air and gas streams. The leakage the air-heater hot end.
across the sealing system is directly propor- Regenerative air preheater fouling can be lim-
tional to the square root of the pressure differ- ited by controlling the cold-end temperature
ential but also depends on the air and gas level and by the use of proper maintenance pro-
density. ' cedures and cleaning equipment. The primary
Entrained leakage is that quantity of air con- requisites for this purpose are sootblowing and
tained in the rotor as it passes from the air side washing equipment, a dry blowing medium,
to the gas side and from the gas side to the air an adequate water supply, and a well-engi-
side. The quantity of entrained leakage de- neered drainage system.
pends on the rotor depth, rotor diameter, and
Sootblowing
rotor speed.
Whether direct or entrained, leakage has no Three types of sootblowing equipment are
effect on the heat-transfer efficiency of the furnished on Ljungstrom air preheaters. Power-
Ljungstrom air preheater. There is no difference driven sootblowers w h i c h have nozzles
in the heat transferred to the air stream from the mounted on a swinging arm are used exten-
gas stream because of leakage, as discussed in sively, while a stationary multi-nozzle type is
Chapter 6. However, the gas temperature leav- used on package air preheaters.
ing the preheater is decreased by 1O0Fto 20F Retractable blowers of the same type as used
(5C to 11"C) by the mixture of the cooler air in boiler convection passes (see the next section
with the hotter gas stream. of this chapter) are installed on air preheaters
above 32 ft (10m) in diameter. The equipment is
CLEANING REGENERATIVE AIR HEATER most often located at the gas-outlet side to eIim-
HEAT-TRANSFER SURFACES
inate flyash from being carried into the wind-
Cold-end deposition occurs when boiler flue boxes. They are installed either as an integral
gases reach the condensation temperature. The part of the air-preheater duct or in the gas-
flyash in the flue gas can combine with mois- outlet ductwork immediately adjacent to
ture and sulfur derivatives to form a fine- the unit.
grained deposit or scale on the cold-end Air-Heater Sootblowing Media
heating surface. Sootblowing can remove and
control regenerative air-heater cold-end depos- Superheated steam (approximately 300F
its provided those deposits are not subjected to superheat) or dry compressed air is the recom-
moisture. mended cleaning medium. Although saturated
--
COMIIVETION
Steam-GonMlorAuxiliary Equipment

steam, which contains some moisture, has been Out-of-service washing is simply washing the
used occasionally, superheated steam has been preheater in a cold state during periods when
found to be more effective for sootblowing. the boiler has been shut down. During shut-
Although compressed air is considered to be down is the best time to control the washing op-
the premium cleaning medium, its merits do eration and to make a thorough inspection of
not stem from an inherent cleaning ability, but the heating surface, both during and after wash-
from its dryness as compared with steam. In ing. The rotor can be turned at normal speeds.
fact, under dry discharge conditions, the ki- If it is necessary to restrict the discharge of
netic energy of a steam jet at 1.4 MPa abs. is water to one side of the air heater, however, an
approximately twice that of air at the same auxiliary drive will be required to reduce rotor
blowing pressure. But a steam source must be speed. Surfaces should be examined frequently
selected to have pressure-temperature condi- during the washing process. After the deposits
tions which, by proper control measures, may are removed, the unit should be allowed to dry
be used to provide dry steam to the air- completely before being returned to service.
preheater sootblower.
In-service isolated washing consists of reduc-
Steam blowing pressure should be 200 to 250
ing boiler load and isolating one preheater by
psig (1.4 to 1.7 MPa gage). A steam-sootblowing
means of dampers while the boiler remains on
piping system should include an automatic
the line by using the other preheater(s) and
drain valve, thermocouple, and an automatic
fan(s). After the isolated air preheater is com-
admission valve to the blowers. The automatic
pletely washed, the procedure is reversed al-
drain valve is open to free drain discharge until
the temperature-sensing thermocouple indi- lowing all the gas and air to flow through the
clean preheater while another preheater is iso-
cates steam of adequate quality.
lated and washed in the same manner. The iso-
When using air, care should be taken to in-
lated method of washing air preheaters has
stall a proper line of traps and separators to re-
been found to produce excellent results both
move moisture from the blowing medium. Air
from the standpoint of cleanliness and time.
at a pressure of 180 psig [1.25 MPa gage] is
Normally, about "13 boiler load can be main-
recommended.
tained during isolation of one preheater for
Water Washing washing. Fig. 31 shows the arrangement for the
isolated washing procedure. The rotor speed is
In cases where sootblowing cznnot readily re- controlled in a manner similar to that used for
move residual deposits, it sometimes becomes out-of-service operation.
necessary to water wash the heating surface to
maintain acceptable draft losses through the air On-stream in-service washing is carried out
preheater. In some instances this may be re- while allowing gas and air to pass through the
quired more frequently than during the sched- preheaters. This is only feasible where drains
uled boiler outages. are located to eliminate the moisture entering
Most deposits forming on the air-preheater the dust collectors, precipitators, windboxes,
heat-transfer surface are highly soluble in water and boiler. The preferred location for operation
and, therefore, are easily removed by washing is in the air side, especially with an electro-
with a sufficient quantity of water. A high- static precipitator. On-stream washing should
penetration, stationary multi-nozzle device is not be done when gas passes are plugged.
the standard washing apparatus and is available The speed of the air-preheater rotor should be
for all air-preheater types and sizes. reduced to 1/15 rpm by means of an auxiliary
Adequate drainage is necessary before plan- drive unit before admitting water to the wash-
ning to wash an air heater. Washing can be on ing devices. The slow speed permits the wash
- either the air or gas side, depending upon water to drain from the rotor and heating sur-
which has best drainage. face before the wash water enters the other
COMBUSRI
Seam-Generator Auxiliary Equipment

stream. To insure coverage of all heating sur- are moved radially 'across the surface, allowing
-
face, the washing cycle must consist of at least sufficient time for the rotor to complete at least
one revolution of the preheater rotor. one revolution between each movement of the
An intermediate-pressure, high-volume nozzle of the sootblowers.
wash is sometimes necessary-to remove parti- INFRARED HOT-SPOT DETECTION SYSTEM
cles of insoluble material that are carried from
the boiler by the gas stream, the larger ones be- C-E Air Preheater's infrared detection system,
coming wedged in the flow passages of the installed on a rotary regenerative air heater,
hot-end heating surface. These obstructed triggers an alarm if the amount of infrared radi-
passages then fill up with flyash, which ation emitted within the air preheater should
restricts flow. This type of deposit accumula- ever exceed levels encountered in normal opera-
tion is difficult to remove with the usual wash- tion. The system operates on the infrared prin-
ing equipment. Special equipment using a ciple, in the 0.9- to 2.5-micrometer wavelength
- high-energy jet has been developed for this range, where the detector sensitivity is at its
purpose. The procedure is similar to that fol- maximum.
lowed i n a regular out-of-service washing An infrared syste& is used because it is easily
using standard washing devices. Water nozzles adaptable to high-speed solid-state electronics.

Isolated Area
Closed Dampers

\ Fan Shut Down


\
\ ,
Fan Shut
Down
I

Air Preheder

I I
Fig.31 Arrangement for in-service air-preheater washing with one preheater isolated
--
C0Idi)osnON
Steam-GeneratorAuxiliary Equipment

For example, a six-inch (15~~nm)-diameter hot The acid dew point varies with the concen-
spot in the rotating heat-transfer surface will tration of sulfur trioxide in the flue gas. High-
pass a given point in about 150 to 1000 milli- sulfur coals result in the existence of a dew
seconds; the response time of the detector is point at a higher temperature, thus exposing
less than 100 milliseconds. Also, the lead- more of the air-heater surface to corrosion and
sulfide sensing chips used in the equipment are fouling. Typical acid dew points for coal are be-
very sensitive to small changes in background tween 280" and 320F (135" and 160C).
temperature. The sensitivity is electronically For coal firing, fouling potential increases as
adjustable and is normally set so that hot spots the temperature decreases. Water condensation
of 200 to 300F (90 to 150C)above the gas inlet causes a marked increase in dew-point meter
temperature will trip the alarm. response at 140F (60C) or below. This does
During the early stages of deposit heat-up, ex- not necessarily mean as severe corrosion in the
ternal effects are not very apparent. The deposit water dew-point range, as compared to the acid
restricts the flow of gas or air so that very little condensation range, although rapid fouling
of the heat generated is carried away from the would likely take place at the water dew point.
area of origin; most of the heat is absorbed by With low-sulfur coal, the corrosion and fouling
the metal heat-transfer element nearby. If the potential is low and restricted to the extreme
condition can be detected during the initial cold end of the air preheater.
period when temperature buildup is slow, the A number of means have been developed to
amount of water needed to reduce the tempera- minimize the rate of corrosion, as well as pro-
tures to a safe level is much less. The C-E infra- vision for replacement of corroded surface.
red system is designed to detect excess heat Because corrosion occurs on the lowest temper-
during this early period. ature surface, air-heater designs have been de-
DESIGNING FOR LOW EXIT-GAS veloped which incorporate replaceable
TEMPERATURE cold-end sections. Other means to minimize
Combustion of sulfur in coal results in the corrosion are aimed at increasing the metal
formation of sulfur dioxide, and about 3 to 5 temperature. One such arrangement directs a
percent of the SO, is oxidized to SO.,, depend- portion of the preheated air to the inlet of the
ing on the oxygen content, moisture, and tem- forced-draft fan and recirculates it through the
perature of the flue gas. The SO, and SO., may air heater. Thus, the temperature of air leaving
then combine with moisture in the flue gas to the fan and entering the air heater is increased,
form sulfurous and sulfuric acids. Sulfurous correspondingly increasing the cold-end metal
acid will not form above the water dew point temperature.
temperature, and is seldom a problem. How- Air bypass around the air heater is used to a
ever, sulfur trioxide is hygroscopic and will ab- limited extent. With reduced airflow, metal
sorb moisture at temperatures well above the temperatures within the air heater are higher
water dew point, resulting in the formation of a because of the influence of the higher gas-to-air
sulfuric-acid mist. The temperature at which ratio. Also, because the overall recovery is less
this acid mist condenses to form sulfuric acid is as a result of the reduced airflow, gas outlet
called the acid dew point.8 temperature rises, causing a rise in the cold-
While boiler efficiency can be improved by end metal temperature.
adding surface to reduce the air-heater exit-gas The prevalent means of increasing cold-end
temperature, this practice lowers the cold-end metal temperature, discussed in detail in Chap-
metal temperatures, possibly below the acid ter 6, is the use of steam air heaters located in
dew point. Consequently, steel construction the cold-air duct between the FD fan and the air
materials are subject to corrosion from the sul- heater. These increase the temperature of the air
furic acid in the flue gas. entering the heater, correspondingly causing an
COMBUSIlON
Steam-Generator Auxiliary Equipment

increase in the metal temperature. Steam bled and accumulate. The percentage of ash in the
from the turbine is used as the heating medium coal is another factor in the design of the
in the steam air heater. In supplying heat to the furnace wall-blower system, with higher-ash
cold air, steam is condensed and the conden- coals requiring greater and more -
- concentrated
sate returned to the appropriate stage of the coverage.
feedwater bleed heating system. FURNACE-WALL SOOTBLOWERS
To assist specifiers and operators in arriving
at reasonable cold-end temperatures, average A short single-nozzle retractable blower,
cold-end temperature (ACET) guides for regen- called a wall blower, removes the ash deposited
erative air preheaters are published. These on furnace walls (Fig. 32). It is a short-stroke
guides take into account the variables of fuel lance which penetrates the wall one to two
type, sulfur content, and the effect of excess air. inches. Supported by wall boxes welded to the
A guide for coal firing,was presented as Fig. 4 furnace tubes, it follows both vertical and hori-
in Chapter 6. zontal movements of the furnace walls as they
expand and contract. The single nozzle at the
tip directs a supersonic high-energy jet of su-
BOILER SOOTBLOWERS perheated steam 'or air parallel to the furnace
face of the water-wall tubes, dislodging the slag
One of the most important boiler auxiliary deposits. The lance rotates through 360" and
operations is the on-line fireside cleaning of cleans approximately a five-foot radius; the ef-
heat-absorbing surfaces. Not only is it impor- fective radius depends upon how tenacious the
tant for proper heat transfer, but also to prevent deposit is. Some coals with difficult-to-remove
sections of the boiler from becoming severely slag require wall-blower spacing to be closer;
plugged. Plugged sections can restrict gas flow the maximum cleaning radius may be only 3 to
and cause load limitation. Tube erosion due to 4 ft. Blowing frequency depends on the rate of
high local velocitigs also can occur. slag build-up, but frequencies in the 4- to 8-
Sootblowing, systems are required on coal hour range are common.
and oil-fired furnaces. Oil had a low ash content
which ~roducesa thin water-soluble deposit CONVECTION-SURFACE SOOTBLOWERS
on the furnace walls that is normally removed Superheater, reheater, and economizer sec-
by annual water washing. Furnace-wall soot- tions of large boilers are cleaned with long,
blowers are, therefore, not required on oil-fired fully or partially retractable lances which pene-
units. In the superheater and reheater sections trate the cavities between major heat-absorbing
of an oil-fired unit, ash deposits do accumulate sections. Smaller boilers may use nonretract-
on the tubing surface. This is especially true of able blowers with multiple nozzles, which ro-
high-vanadium oils where additives are used to tate, allowing each nozzle to clean a tube row.
combat highAemperature corrosion. But with
the use of solid-powder additives, ash deposits
in the high-gas-temperature areas increase
markedly. Ordinarily quite friable, such depos-
its are easily removed with sootblowers.
Coal-fired units require large complements of
permanently installed sootblowing equipment.
In the boiler furnace, the concentration of wall
blowers depends upon such factors as the ash-
fusion temperatures, as described in Chapter 3.
The lower these temperatures are, the more
likely the ash will adhere to the furnace walls Fig. 32 Typical retractable furnace-wall sootblower
COMBUsnON
Steam-GenentorAuxiliary Equipment

The long retractable type sootblower is the say, one complete cycle per 8-hour shift. After
most effective way to clean radiant and convec- observing fouling patterns either through ob-
tive heating surface. It normalIy uses two 18O0- servation doors (on line), or by gas-side inspec-
opposed cleaning nozzles at the tip which emit tions during shutdowns, the operator can
a high-energy jet of superheated steam or com- modify the blowing pattern to that which best
pressed air perpendicular to the lance. While suits the boiler for the coal being fired. It is
the lance traverses the boiler, it rotates, forming common for certain retracts to be blown more
a helical blowing pattern (Fig. 33) which effec- frequently than others, either singly or in
tively cleans the tubes and spaces between groups. Once the pattern is established, it can
tubes in a superheater, reheater, or economizer be programmed in the sootblower system and
bank. In widely spaced platenized sections, run automatically. '
these nozzles are angled slightly, leading and The air preheaters are also cleaned by soot-
lagging the perpendicular to gain more dwell blowing as described in the previous section on
time on the tube surface. The effective range of air preheaters. The ash at this point in the sys-
retracts depends upon the gas temperature in tem is usually dry and the particles small
the area to be cleaned and the ash characteris- enough to pass through air preheater elements.
tics of the particular fuel being fired. Therefore, BLOWING MEDIA
the maximum effective cleaning radius varies
from 4 to 9 feet. It is difficult to relate cleaning The two blowing media are steam and com-
radius to blowing pressures because of various pressed air, with both being equally effective in
nozzle combinations. Blowing pressures de- deposit removal. The utility normally makes
pend not'only on supplying a flow for cleaning the choice based on plant economics. In the
but, in high-temperature zones, supplying an case of air, large compressors must be installed
with an integrated piping system around the
even greater flow for cooling the lance.
boiler. Steam systems are usually supplied
Fig. 34 sho\vs a retractable blower on one side
of a large utility boiler; this blower penetrates from the boiler through a pressure-reduction
station so that, after pressure reduction, dry
half the width of a 90-ft wide boiler. The blower
superheated steam is available at the soot-
typically uses a two-point support which al-
blower nozzle. Steam has the advantage of
lows for boiler expansion. A wall box welded to
availability whenever the boiler is in operation.
the tubes supports the front of the lance; the
platform structure supports the rear through a
slot-and-pin connection.
SOOTBLOWER OPERATION
The type of deposits in the radiant and con-
vection sections of the boiler can vary from
very hard tenacious slag to a dry powdery coat-
ing. The most important coal properties affect-
ing the severity and rate of ash build-up are ash
softening and fluid temperatures, percent ash
in the coal, and the percent sodium in the coal
ash. Coals with high percentages of ash, low
ash-fusion temperatures, and high percentages
of sodium in the ash are the most difficult to
keep clean. The blowing sequence and fre-
quency of the retract system must be adjusted
during initial operation by starting with an as-
sumed sequence of blowing and a frequency of, Fig. 33 Retractable sootblower cleaning pattern
COMBUSTION
Steam-Generator Auxiliary Equipment

Fig. 34 Long retractable sootblower for cleaning convection surface of a 750-MW steam generator

I
Fig. 35 Retractable probe for measuring furnace gas temperature
6
C O ~ O N
Stum-Omntor Auxlll.y Equipment

With air, there is always the possibility that the used. On the other hand, large industrial and
blowing medium will be lost if the compressor central-station boilers can justify various de-
is out of service. grees of automatic control.
Water as a medium is not generally recom- In systems with over 200 sootblowers, pro-
mended for sootblowing and is considered as a grammable controllers frequently are installed
last resort for particularly troublesome slag de- so that proper automatic sequential operation
posits. Thermal shock from water may reduce of the system can be accomplished after
,tube life due to cyclic fatigue. ash-deposition patterns are established under
operating conditions. With properly pro-
FURNACE TEMPERATURE PROBES
grammed blowing ,sequence, ash deposits on
Fig. 35 illustrates a typical retractable fur- the furnace walls are minimal and the combus-
nace probe for monitoring gas temperatures at tion gases are cooled to the required tem-
the top of a furnace. The probe is inserted dur- perature before entering the convection pass.
ing the lighting-off period and remains in the Sootblower control panels are now designed
furnace until reheater steam flow has been es- for easy modification of the automatic sequen-
tablished. Its design is based on that of the long tial operation. This gives the operator maxi-
retractable sootblower, but without the rotating mum flexibility in maintaining the cleanliness
feature. It traverses back and forth across the of a unit. Essential parameters for such a soot-
furnace or convection pass as it is driven by a blower control package include
single electric motor. equipment to automatically start each soot-
As a probe senses temperatures, it also trans- blower in the system
mits its position. A thermocouple mounted a method to cancel the operation of any soot-
on the end of the lance measures gas tempera- blower in the system
tures. The standard thermocouple is suitable
for temperatures to 1850F. a way to determine easily which sootblowers
For lance extensions below 16 ft and gas have been selected to operate, and their pro-
temperatures of 1200F or lower, there is no grammed operating sequence
need for cooling the lance. Automatic retrac- the complete capability to monitor and dis-
tion from the recorder alarm Drotects the lance play the operation of each sootblower
at excessive temperatures. When air cooling is the capability to monitor all the essentials of
required, the lance is supplied with an inner the sootblowing system and prevent continued
lining for optimum cooling. sootblower operation if the system is not func-
Introduced into the traveling carriage, the tioning properly and abort the operation of any
cooling air passes through a small annular sootblower if a malfunction occurs.
space between the lance wall and the inner a method to select and alter various blowing
liner. It then is discharged from a nozzle into routines as required by the boiler cleaning
the furnace. Mounted back from the end of the requirements
lance, the nozzle is slanted away from the the ability to operate certain of the soot-
thermocouple, so that discharged air will have blowers simultaneously
no effect on the temperature readings. rn a means of manually overriding the auto-
SOOTBLOWER CONTROL SYSTEMS matic routines
The mode of sootblower operation depends Ideally, a sootblower control system would
upon the size and capacity of the boiler unit respond automatically to conditions of load,
and the number of blowers installed. Small in- temperature, pressure and fuel to provide for
dustrial boilers using few sootblowers cannot the most efficient boiler operation. However,
economically justify the use of automatic con- because of the number of input variables and
tfol systems; manually operated blowers are the questionable validity of signals and the
COMBUSTION
Steam-Generator Auxiliary Equipment

complexity of process manipulation, this has tions for station services of seal water, cooling
not been technically feasible to date. Sequen- water, and electric power supply must be flexi-
tial control with the boiler operator as the deci- ble to accommodate pump expansion move-
sion maker has been used for the majority of ments. The pump drives share the basic
sootblower systems. With the advent of more electrical characteristics of low starting torque,
complex blowing operations, the hard-wired induction squirrel-cage motors, designed for
solid-state logic systems have taken over some full-voltage across-the-line starting.
of the decision making. It is extremely benefi- DESCRIPTION
cial to minimize operator attention and still OF BOILER CIRCULATION PUMPS
operate the sootblowers efficiently. Effec-
tive performance of any soot-blowing control Pumping water at or near saturated tempera-
system depends on its ability to make complex ture and at high pressure requires pumps of
decisions with a minimum of operator input. special design because of the possibility that
shaft seal leakage water may flash rapidly into
steam. For this service, three types of boiler cir-
culating pumps have been used. The zero-
BOILER-WATER leakage pump is driven by a wet motor, cooled
CIRCULATING PUMPS and lubricated by recirculated water at system
pressure. The stator windings are immersed
Boiler circulation pumps are an integral part
of the furnace-wall circulation system on the
~ontrolled~irculation@and Combined Circula-
tion@units. By using pumps in the circulation
flow path, the total quantity of water circulated
can be apportioned and distributed throughout
the furnace heat-absorbing surfaces to suit all
the conditions of operation. Boiler circulation
pumps also give the operator the capability of
insuring positive circulation for a wide variety
of pre-operational procedures and off full-load
plant cycling conditions.
Most boiler circulation pumps have cer-
tain basic similarities. All are vertical, single-
stage, centrifugal type with overhung impeller
and are designed for constant-speed operation
without throttling. The hydraulic erid consists
of a single vertical suction and either single or
double horizonlal discharge (Fig. 36).
The pump casing and associated isolation
valves are entirely supported -by the boiler
downcomer piping, thus permitting unre-
stricted expansion movement during boiler
start-up and shutdown. Butt-weld joints be-
tween pump nozzles, valves, and piping are de-
signed to withstand the combined moments
and forces resulting from dead weight loads
and the expansion differential between the fur- . Vertical single stage centrifugal pump
~ i g 36
nace and the downcomers. Only the connec- for boiler-water circulation
-.
COMBvmON
Steam-GeneratorAuxiliary Equipment

in the high-pressure water. This unit is also restriction of conduction and convection be-
known as a glandless submerged motor pump. tween pump and motor by reduced cross-
The second type employs a canned motor sectional areas, and by mounting the pump
housed within a pressure vessel common to the above the motor
pump itself. It too is a glandless or zero-leakage heat exchange through a closed-circuit pipe
type of pump. The third type employs a con- system and external heat exchanger
ventional motor drive. Shaft sealing is ac- The electrical leads exit the motor casing
complished by a stuffing box with packing or a through pressure-tight sealed glands to an ex-
shaft mechanical seal, supplemented by an in- ternal terminal box at atmospheric pressure.
jection sealing-water arrangement. The main supply cable is connected to the
ZERO-LEAKAGE motor phases inside this terminal box.
BOILER-WATER PUMPS The entire pumping element-the drive
motor, pump shaft, thermal barrier and over-
Controlled Circulation boilers of the type de-
hung impeller-can be installed or removed
scribed in Chapter 7 are designed with gland-
from the pump casing without disturbing the
less pumps in which the electric motor and the
casing or its piping connections.
pump are enclosed in a common pressure cas-
The pump shown in Fig. 38 is of the diffuser
ing (glandless meaning that there are no stuff-
type with a spherical casing. The materials and
ing boxes or mechanical seals around the pump
construction of the pressure-retaining parts-
shaft). These zero-leakage pumps are of two
pump casing, heat barrier, forged motor case,
main types: those with stator enclosures, but
and all bolted flanges-are in accordance with
with the rotor immersed in water (known as dry
A SME Section I requirements.
stator or "canned" pumps) and those in which
The motor shaft of this pump is fitted with
water at system pressure is circulated through
the stator windings (known as wet stator or two chromium-plated chrome-steel sleeves
"submerged motor" pumps). In both designs, running in water-lubricated journal bearings.
the high-pressure water in the motor is recircu- A double-acting Kingsbury-type thrust bearing
lated through an external heat exchanger and locates the rotor assembly axially and takes up
then through the rotor gap and acts as a lubri- any residual thrust. Both the radial journal
cant for both thrust and journal bearings, and as bearings and the axial thrust bearings are self-
a cooling medium for removing the heat gener- adjusting, thus ensuring equal bearing loads.
ated by the motor losses. CANNEDMOT0.R PUMP
SUBMERGED MOTOR RECIRCULATINGPUMPS
The canned-motor boiler-circulating pump is
The motors of these pumps are wound with a zero-leakage pump designed to circulate
waterproof insulated cable. The motor power boiler water at high temperature and high pres-
is supplied through pressure-tight cable inlets. sure. No shaft seals are required. The motor and
As shown in Fig. 37, the internal high-pressure pump components are designed as an integral
water content is circulated through an external pressurized unit, sea!ed by a gasket and studs.
heat exchanger to keep the motor cool and pro- The impeller is rotated by an AC polyphase,
vide bearing lubrication. Circulation is ac- squirrel-cage induction motor. The spaces be-
complished by an auxiliary impeller, integral tween the stator'and rotor and around the bear-
with the thrust disc and located at the base of ings are filled with the cooled system water.
the motor. The design also includes a thermal A heat barrier between the pump and motor
barrier for minimizing the flow of heat from the limits the conduction of heat from the high-
pump to the motor. Provision is made for con- pressure hot water being pumped, to the
trolling the temperature within the submerged high-pressure internal motor water. The dry
motor by stator winding is completely isolated from the
Steam-GeneratorAuxiliary Equipment

high-pressure water by a corrosion-resistant The rotor assembly contains a shaft, squirrel-


"can" lining the stator bore. cage type rotor body, auxiliary impeller, rotor
The stator assembly consists of the bearing journals, and thrust runner. The main impeller
assemblies, the stack of laminated steel punch- is mounted on the rotor shaft extension. Se-
ings, the three-phase insulated copper wind- cured to the lower end of the shaft, the thrust
ing, the outer pressure sheli, and stator can. runner carries the weight of the rotor assembly

Inlet
(Suction)
0

y Impeller

Reverse Thrust Bearing

Fig. 37 Schematic of a typical glandless wet-motor boiler-water circulating pump


COIQlllmION
Stwm-Generator Auxiliary Equipment
.-
and absorbs the axial hydraulic thrust. The Low-pressure cooling water is circulated
pump motor with its integral pump shaft and through the external heat exchanger. When
impeller can be withdrawn from the pump cas- the pump is idle, but pressurized with high-
ing without disturbing the casing or its piping. temperature boiler water in the pump casing,
In operation, high-pressure cooling water in conducted heat is removed by motor-fluid
the motor cavity is circulated by the auxiliary convection flow through the heat exchanger.
impeller mounted on the rotor shaft. This water
is circulated from the auxiliary impeller up INJECTION-SEAL PUMP DESIGN
through the gap between the rotor and stator, This controlled-leakage boiler-water circu-
through the upper guide bearing, out to the ex- lating pump'is mounted vertically with a rigid
ternal heat exchanger, back into the motor shaft designed to carry its own thrust. No thrust
through the piping connections to the auxiliary load is transmitted to the motor, which is en-
impeller suction in the hollow shaft end. Some tirely supported by the pump. The internal
of the auxiliary impeller discharge is circulated pump materials are selected to accommodate
down through the lower guide bearing and the expansion encountered at high temperatures,
thrust'bearing and then back to the auxiliary and to provide corrosion resistance.
impeller suction. Essentially, the pump contains the following
main components: casing, stuffing box, pres-
sure breakdown assembly, bearing assemblies
and pump shaft with impeller. The pump cas-
ing is supported by the suction and discharge
piping to which the casing nozzles are welded.
A direct-drive coupling connects the pump
motor to the pump shaft. Thevertical induction
motor is of open drip-proof construction for in-
door installation, or a weather-protected type
for outdoor installation.
The suction pressure and temperature at the
pump are virtually the same as the boiler
operating conditions. The injection seal re-
duces the pressure and temperature at the
stuffing box packing by injecting cool water at
high-pressure into the annulus formed by the
shaft running clearance. The injection water
serves as a thermal barrier against conducted
heat and as a means of keeping the boiler water
from entering the close clearances of the
throttling sleeve and floating seals. The float-
ing seals and the packing control the leakage at
the stuffing box. The injection water, free and
clear of foreign particles, can be supplied from
the discharge of the boiler feed pump or any
other source that can supply a pressure differ-
ential of 50 to 100 psi over the discharge of the
boiler circulating-water pump. A supplemen-
Fig. 38 Single discharge spherical-type pump tary booster pump of limited capacity is pro-
for supercritical-pressure steam generator. vided with a takeoff point from the boiler
Pump casing design pressure is 4500 psig. feed-pump discharge to supply the additional
COMBUSTION
Steam-Generator AuxNiary EquQment

pressure necessary for sealing the boiler cir- Boilers operating at supercritical pressures
culating pump. The booster injection pump has involve special considerations that differ from
a bypass system for operation at partial loads. ASME Boiler and Pressure Vessel Code re-
quirements for subcritical-pressure bailers.
OTHER AUXILIARY EQUIPMENT
Although this chapter has discussed fans, air POWER-PLANT NOISE
heaters, sootblowers, and boiler-water circulat-
ing pumps, it has only scratched the surface as This final section discusses the problem of
far as the multiplicity of ancillary equipment noise and its suppression in a large pulver-
involved in a large steam-generator installa- ized-coal fired power plant. Generally, the
tion. For instance, hundreds of valves for high- motors, and the rotating equipment they drive,
pressure steam, water,, compressed-air and oil are the source of most noise.
duty are part of the scope of most boiler con- Noise is unwanted sound with a severity that
tracts. The ASME Boiler and Pressure Vessel varies with.sp$ce and time. For example, it is
Code and ANSI Code B31.1 for power-plant worse at night when the masking effect of
piping govern the design and application of background sounds is reduced-.
most of the valves. The human ear is more sensitive to high than
Because boiler valves experience extremes of to low-pitched sounds. Because of this, high
temperature and pressure as well as widely frequency noise is normally the greatest of-
varying conditions of operation, the valve fender, particularly if it contains a pure note.
manufacturer must give close attention to the An essential feature of the human sense of
materials of construction. For valve parts these hearing is that to perceive a just noticeable dif-
may range from low-carbon steel through the ference in volume requires a discrete change of
low and medium chrome alloys to stainless about 10 percent in the subjective noise level
steel, in both castings and forgings. on the decibel (dB) scale. Therefore, worth-
Safety valves are regulated by the ASME while reductions in noise levels should proba-
Code. For boilers operating below the critical bly involve 5- to 10-fold decreases.
pressure, superheater safety valves are cus- PHYSICAL LEVEL SCALES OF NOISE
tomarily set to pop before boiler safety valves. The human ear is a frequency meter, a sound
This assures maximum possible flow through analyzer, and an intensity meter. Conven-
the superheater, thus protecting the tubes. iently, we describe our sensations,.sometimes
Feedwater valves contain stop and check in physical, sometimes in psycho-physical
valves near the economizer inlet. Ordinarily terms, but neither provides terminologies that
these valves are wide open. Blowoff valves are alone seem suitable for classifying all sounds.
located at low points in the boiler, such as the Physically, a pure note is a single harmonic
lower waterwall supply header, for rapid re- wave. Sound is produced by adding together
moval of sludge collected at these points. Con- several, but not too many, pure notes. Too
tinuous blowdown and chemical feed valves many produce noise. The human ear, to some
serve to limit and control concentration of im- degree, can separate sound into pure notes, but
purities in the water in the main steam drum. apparently only if the frequencies involved are
Sampling valves provide a continuous record well separated. The intensity of specific fre-
of steam and water purity. quencies then becomes important.
Modern Controlled Circulation boilers have The quantity usually measured in acoustics
three 50-percent capacity pumps, with outlet is the RMS-root-mean-square sound pressure
stop-check valves. With such an installed spare (P).The weakest sound pressure perceptible to
pump, suction valves are not required at the the average human ear is very small, about
pump inlets. 0.0002 microbar. In comparison, the greatest
C O ~ O U
Stum-Gwtontor Auxiliary Equipment

sound pressure perceived without pain is about LOUDNESSAND NOISE NUISANCE


1000 microbars. The human sense of hearing There is no simple relationship between the
covers a wide dynamic range. physical measurement of a sound pressure
The human ear responds to changes in sound level and the human perception of sound. In
pressures, but it is the ratio rather than the ab- Fig. 39, each curve represents one of constant
solute difference between two intensities or subjective loudness equal to the physical dB
two frequencies that produces the distinct sub- level at a standard noise frequency of 1000 Hz.
jective sensation. In noise measurement, it is These "equal loudness contours" are an inter-
practical, therefore, to adopt a relative scale of national standard. Sound-level meters are
sound pressure, such as the decibel (dB) scale. made with electronic filters which can inte-
The decibel is defined as 10 times the logarithm grate sound energy in such a way that the filter
to the base 10 of the ratio between two quan- characteristics (Fig. 40) reflect the subjective
tities of power. (The factor 10 converts bels to response of human hearing. The ensuing noise
decibels.) Thus, as sound power is related to level (measured in decibels on the A-scale,
sound pressure squared, the common scale for dBA) is then a good measure of the subjective
noise measurement becomes: loudness of the sound provided there are no
discrete tones.
Sound Pressure Level (SPL) = Prolonged exposure to noise results in a tem-
porary threshold shift, TTS. It has been
I0 log ,.-$ 0
P
( d ~=) 20 log ,. - [dB]
p suggested that 1 2 dB TTS (Po-0.0002microbar)
(7) should be the maximum permissible short-
term noise exposure for given noise ratings (N)
where P is the actual pressure measured and Po as a function of TTS at 2000 Hz. For example,
some reference value, conventionally the exposure to noise rating N-90'should not ex-
threshold of human hearing (0.0002 microbar ceed 2 hours. If the subject becomes exposed for
or 20 micropascals). The use of this equation any longer periods, hearing-conservation aids
reduces the range of sound pressures to 0 to 120 should be provided.
dB, 0 dB indicating the reference value and 120
dB an approximate "maximum" level for pain- NOISE MEASUREMENT
free stimuli (during short exposures). Most sound-level meters are now equipped
NOlSE CRITERIA with frequency weighting networks to deter-
mine overall sound pressure levels at a certain
The dB term, unfortunately, is also used to location. However, for abatement purposes,
designate levels of sound power, sound inten- more thorough investigations are often re-
sity, and in ratings simulating human response quired. Therefore, the next step is to make a
such as the A, B, and C "weightings" and the frequency analysis of the noise. Usually, the in-
Noise Criteria Curves. To avoid confusion, ref- struments are provided with filters that divide
erence values should never be omitted. the noise spectrum into 8 to 10 electronically-
Some common sound levels are listed in controlled, well-separated bands. The fre-
Table IV. Most daily activities take place quency analysis is then simplified to discrete
within 1/4 of the scale, from 50 to 85 dB. This dB measurements for each band.
covers any sensation between pleasantly quiet In noise studies, the position of observation
and annoyingly noisy. A noise attenuation of a with respect to the source is of utmost impor-
few dB will be most pronounced within this tance, and so is a detailed knowledge of the sur-
narrow range. At the top and the bottom of the roundings. The effects of reflections from wall
-
scale, as much as 10 or 15 dB attenuation (i.e., surfaces and the contribution of the other
10% of full-scale) is hardly noticeable. sources must be known. In fact, to do a noise
COrdBUrnO~
Steam-GeneratorAuxiliary Equipmtnt

~ _ Table IV. Typical Sound Pressures and Sound Pressure Levels


SPL - -

(dB ref. Source Distance


0.0002 p bar) (long time average) (fl)
2,000 140 Threshold of pain

Pneumatic clipper 6
Threshold of discomfort

Automobile horn 20

New York subway train Inside

Motor bus Inside .'

1 Traffic on street corner


70
Conversational speech 3
0.2 60
Typical business office Inside
50
Quiet residence Inside
0.02 40
Library Inside
30
Whisper 5
0.002 20
10
0.0002 0 Threshold of hearing

study properly, one should operate in a free


field and, in a standardized way, locate the ob-
servation points around the source to account
for sound directivity. As measurements usu-
ally cannot be made under these conditions, it
is extremely important, from the point of view
of noise guarantees on equipment, to stipulate
not only the noise spectrum, but the exact loca-
tion at which it applies. Specifying distance
from casing or center of the noise source is gen-
erally inadequate, as the sound spectrum invar-
Normal Binaural iably changes around the source.
Minimum Audible Field
In specifying noise ratings, it must be
Fig. 39 Normal equal loudness contours realized that at the present state of the art there
for pure tones are no set regulations, only suggested ones, and
COMBUSTION ...
Stwm-Genemtor Auxiliary Equipment

verizers. High-frequency noises dominate at


positions where gas or steam is emitted at high
velocity through valves and vents.
There are two principal sources of sound
within a fan. The first source is the blade pass-
ing tone which is generated by the impeller
blades. The frequency of the blade passing tone
is equal to the number of times per second a
blade passes a stationary object.

(rpm) (number of blades)


Frequency in Hertz (Cycles Per Second) FBP = 60

Fig. 40 The standard weighting curve


for sound level meters The loudness of the blade passing tone de-
pends on the width of the fan impeller and
that each of the several possible ratings has the distance between a blade and the cutoff or
limitations. No sound measurement is that ac- the stator vanes. The second major source is
curate. Plus or minus 2 dB or less in sound the turbulence created by the fan while add-
power level is insignificant, particularly in the ing energy to the airstream. This sound is gen-
low frequency bands where differences of up to erally broad band in character.
4 dB should be disregarded.9 There are three primary paths by which
There seems to be a trend toward the use of sound radiates from a fan; namely, through the
sound power level ratings. These indicate the inlet, the outlet, and the fan housing. Sound
actual acoustic power radiated from a source. radiated from the fan inlet and outlet is approx-
From these data, the audible sound pressure imately at the same sound power level. Sound
levels can be predicted with an accuracy de- radiated by the housing is normally at a lower
pendent on how well the physics of the sur- sound power level than that radiated from
roundings is understood, and one can predict either the fan inlet or outlet. If the fan inlet(s)
the need for extra abatement measures such as andlor outlet are ducted, some of the sound is
silencers, barriers or plenum chambers. radiated into the system while some of the
References 10, 11, 12, and 1 3 are publica- sound is transmitted through the duct'wall to
tions applicable to fan sound ratings, methods the surroundings. In the case of FD fans with
of calculating fan sound ratings from laboratory open inlets or inlet boxes, sound passes
data, and methods of testing sound power from directly through the openings to the surround-
air-moving devices. ings. The sound radiating from the fan housing
is transmitted directly to the surroundings. For
NOISE SOURCES effective sound control, it is necessary to con-
To determine the nature of an offending sider all three of the sound paths in accordance
noise and to make silencing worthwhile, it is with the amount of sound power being trans-
necessary to examine the spectral distribution mitted from each.
of sound levels at various frequencies. In a NOISE REDUCTION
power station, nearly every frequency within
the audible area is represented. The dominat- Basically, there are two ways of abating
ing frequencies differ at different locations noise. One is to assumethe existing process
within the plant. Where low frequency noise cannot be modified and to isolate the sound
dominates, the offender is likely to be the fur- from nearby inhabitants by enclosures, bar-
nace, fans, reciprocating compressors, or pul- riers, etc. The other is to examine thoroughly
COUBUSRON
Steam-Generator Auxiliary Equipment

the nature of the noise and to modify the pro- build-up of reverberant sound levels. However,
--
cess or replace the offending component with a the structure must be leaktight. With 30 dBA
less noisy one. In practice, both methods may reduction, for example, only one thousandth of
be required since 10 to 20 dBA reductions are the noise energy that hits thejnsid.e.of an en-
difficult to obtain except early-in the design. closure escapes to the outside. A similar quan-
In most cases, separation of source and re- tity would be emitted through a hole 111OOO of
ceiver is also only possible during the early de- the wall area. Therefore, small leaks between
sign stage. Doubling the distance halves the panels and around openings for supply pipes
sound pressure, i.e., reduces the sound pres- must be avoided. Also, the wall must be vi-
sure level by 6 dB. For this reason, it may be at- brationally isolated from the mechanical
tractive to include a "buffer zone" rather than sound-source, or, because of its larger area, the
silencing equipment. noise emission produced by the vibration may
In general, most problem noises are at a fairly be worse than the initial noise.
high frequency. Therefore, the best results are An example of the noise attenuation that can
obtained with double structures (inner steel be achieved by enclosing two 500,000-CFM FD
and outer lead linings with porous glass fibre fans for a 500-MW boiler in 30 ft x. 45 ft x 35 ft
material between). This method prevents the enclosures of 8-in. block masonrl is shown in

;;j 1307

.-C

V)
p! 20-
I
o Frequency Band, Hz
V)

1. SPL - Inside Enclosure


2. SPL - Outside Wall
3. SPL - Silencer Outlet
4. SPL -600-Ft Away, Both Fans
at Full Load
sFig. 41 Calculated abatement of sound pressure
levels for two FD fans for a 500-MW boiler. Each fan
is housed in a 30-ft wide x 45-ft long x 35-ft high Fig. 42 Large centrifugal forced-draft fan
enclosure of 8-in. masonry. with silencers mounted on inlet boxes
-
COMBUSTION
Steam-Generator Auxiliary Equipment

Fig. 41. At 600 ft (free field assumed), the noise to the inlet boxes of an airfoil-type centrifugal
is reduced to a mere whisper. FD fan. Such silencers are often used in lieu of
Fig. 42 shows inlet silencers attached directly acoustical enclosures.

REFERENCES
1 "Laboratory Methods for Testing Fans for Rating," NAS5-23406; U.S. Dept. of Commerce. Springfield. VA:
ASHRAE Standard 51-75lAMCA Standard 210-74. New National Technical Information Service, 1979.
York: American Society of Heating, Refrigerating and Air
Conditioning Engineers; Arlington Heights, IL: Air *Manuel Cadrecha, "Preventing Acid Corrosion in Air
Movement and Control Associations. Heaters:' Power Engineering. January, 1980.
'ASME Performance Test Codes: ANSIIASME PTC 11- 9 Air Movement and Control Association, Power Plant Fans:
1984, "Fans" (directions for full-scale site testing of fans), Specification Guidelines, AMCA Publication 801.
New York: American Society of Mechanical Engineers, Arlington Heights, IL: Air Movement and Control Associ-
1984. ation, 1977.
IRobert Jorgensen, ed., Fan Engineering, Eighth Edition, lo "Test Code for Sound Rating Air Moving Devices" AMCA
Buffalo, NY: Buffalo Forge Co., 1983. Standard 300. Arlington Heights, IL: Air Movement and
'Air Movement and Control Association, Fans and Sys- Control Association, 1967.
tems, AMCA Publication 201. Arlington Heights. IL: Air
Movement and Control Association. "Methods of Calculating Fan Sound Ratings From Labora-
tory Test Data," AMCA Standard 301. Arlington Heights.
5 R. Kotwal and \V. Tabakoff., 'A New Approach for Erosion IL: Air Movement and Control Association, 1976.
Prediction Due to Fly Ash,'' ASME Paper No. 80-GT-96.
New York: American Society of Mechanical Engineers, ]:Air Movement and Control Association, Application of
1980. Sound Power Level Ratings for Ducted Air Moving De-
vices, AMCA Publication 303 (Application Guide).
6E. F. Rothemich and G. Parmakian, "Tubular Air-Heater Arlington Heights, IL: Air Movement and Control Associ-
Problems:' ASME Paper No. 52-A-124. New York: Ameri- ation, 1979.
can Society of Mechanical Engineers, 1952. Also in:
Transactions of the ASME, 75:723-728. July 1953. l3 "Methods of Testing In-Duct Sound Power Measurement
Procedure for Fans:' ASHRAE Standard 68-78. New York:
7 Heat Pipe Design Handbook, prepared for NASA Goddard American Society of Heating, Refrigerating and Air Con-
Space Flight Center by B&K Engineering, under Contract ditioning Engineers, 1978.
CHAPTER 15

Control of PowermPlant Stack Emissions

u his chapter presents the various types of


commercially available equipment for the
control of particulate and gaseous effluents. No
reference is made to national or local legisla-
the electric-utility industry. Discounting infla-
tion, the cost of installation of a major facility
has more than doubled since the imposition of
environmental laws. Because of permits
tion or regulations because of the probability of needed to satisfy environmental statutes, and
change from year to year. Such regulations are the delay occasioned by debating these in pub-
best found in the U.S. Federal Register or ob- lic, the time required to construct a fossil plant
tained from the local environment-regulating has increased by as much as 2 to 3 years.
agencies in other countries. Besides the emission-control equipment de-
scribed in this chapter, a coal-fired power plant
must have
ENVIRONMENTAL FACTORS IN very high static-pressure induced-draft fans
POWER PRODUCTION or additional FGD booster fans to accommodate
draft requirements
The installation of highly efficient electro-
FGD solid-waste beneficiation, handling,
static precipitators, fabric filters (baghouses),
and disposal systems
and flue-gas desulfurizaiion systems (FGDS)
has become increasingly necessary; power- more sophisticated treatment of raw water,
plant owners must include them in their plan- makeup water, and waste water
ning to obtain permission to start construction condenser cooling-water systems that do not
of a new facilitv. Additional controls that are add heat to inland or coastal waters.
applied to other gaseous emissions such as ox- The auxiliary power requirements of equip-
ides of nitrogen, and to liquid and solid wastes ment to satisfy environmental regulations will
that result from the processing, handling, and demand a significant percentage of the total in-
disposal of fossil fuels and their products of stalled capacity of a power plant.
combustion add considerably to the complex- POWER-PLANT EMISSIONS
ity and cost of installation, operation, and
maintenance of power plants. Three classes of emissions from fuel-burning
Changes in fuel availability as well as air- processes are judged significant from an air-
quality standards have significantly impacted quality standpoint: particulate matter, sulfur
--
" C O ~ O W
ConW ot Power-Plant Stack Emissions

oxides, and nitrogen oxides. Historically, par- tent coals and very low effluent ash levels.
ticulate matter has received the greatest atten- As flyash is nonhomogeneous in properties
tion because it is easily seen and often labeled a such as specific gravity and particle shape, size
public nuisance. The concern about sulfur ox- is very difficult to describe in absolute terms.
ide comes from its possible health effects and Methods for determining this property include
from its potential to damage vegetation and photomicrographs, sedimentation, elutriation
property. Oxides of nitrogen are also signifi- and inertial impaction devices. Flyash is the
cant because they participate in complex chem- combination of inert or inorganic residue
ical reactions that lead to formation of i n pulverized-coal particles with varying
photo-chemical smog in the atmosphere. Addi- amounts of carbon or coke particles resulting
tionally, both sulfur and nitrogen oxides have from incomplete combustion. In general, the
been implicated as precursors to acidic deposi- inorganic ash particles consist primarily of sili-
tion, more commonly called acid rain. cates, oxides, and sulfates, together with small
quantities of phosphates and-other trace com-
pounds. Particle size varies from below 0.01
Emissions from coal-fired boilers vary con- micrometer diameter to over 100 micrometers.
siderably depending on the ash content of the Fig. 2, based on test data,l shows the size distri-
coal and the type of firing. A pulverized-coal- bution between the 2 and 50 pm diameters.
fired unit can be expected to have 60 to 80 per-
SULFUROXIDE
cent of the coal ash leaving the furnace with the
flue gas. The balance of the ash leaves through As fuels burn, most of the sulfur is converted
the boiler bottom-ash removal system, hoppers to sulfur dioxide (SO,) and sulfur trioxide
under economizers and air heaters, and pul- (SO,). As explained in Chapter 2, the quantity
verizer rejects hoppers. Fig. 1 illustrates the of sulfur varies widely for different coals and
exceedingly high efficiency required of partic- may range from less than 0.5 to over 5 percent.
ulate-collection equipment for high-ash-con- In general, 90 percent or more of the sulfur in

Effluent /lo6Btu Fired

Effluent /lo6Btu Fired

Lb Ash Entering Collector/106Btu Fired LessThan Size Indicated


-. - O/O

Fig. 7 Required particulate-collectionefficiency Fig. 2 Flyash particle-size distribution in


versus inlet ash concentration pulverized-coal-firedboilers
COhIEtETION
Control of Power-PlantSfack Emissions

the fuel will oxidize to gaseous sulfur oxides. nace NO, control in this chapter, refer to Chap-
Typically, concentrations will be 0.05 to 0.30 ter 4 for a discussion of NO, formation during
percent by volume in the products of combus- combustion, and to Chapter 12 for techniques
tion. The further conversion of SO, to SO, to reduce NO, in furnaces.
ranges from 1 to 4 percent. T h e formation of
INTEGRATED EMISSIONS CONTROL
SO, in a boiler is a complex process and is be-
lieved to be influenced by the oxidation of SO, For decades, utilities and large industrial
by molecular oxygen, oxidation of SO, in the power producers in the United States have
flame by atomic oxygen, and catalytic oxida- been routinely purchasing electrostatic precip-
tion of SO,. itators (ESP's) or fabric filters (FF's) to control
particulate emissions from their boilers. Since
NITROGEN-OXIDE EMISSIONS
the enactment of the 1970 Clean Air Act requir-
During the combustion process in a conven- ing control of sulfur dioxide, utilities have also
tional steam generator, oxides of nitrogen (col- been installing flue-gas desulfurization (FGD)
lectively referred to as NO,) form i n the systems. More than 100,000 MW's of FDG sys-
high-temperature region in and around the flame tems have been purchased in the United States.
zone. The oxidation of both atmospheric nitro- Wet FGD systems have accounted for about 80
gen (thermal NO,) and nitrogen contained in the percent of those purchased; dry-scrubbing FGD
fuel (fuel NO,) is the cause. The rate of forma- systems over 10 percent; and all other types of
tion is influenced by the temperature and the FGD systems, under 10 percent. Nitrogen-ox-
oxygen present. Reducing the flame tempera- ide emissions have been almost exclusively
ture and the excess air can help control ther- controlled in the combustion process, although
mal-NO, formation. Fuel NO, is related to the selective reduction of nitrogen oxides will be
available nitrogen in the fuel and is most sig- applied more widely in the future, to compIy
nificantly influenced by the oxygen concentra- with the 1990 CAA.
tion in the combustion region. Fig. 3 illustrates the mosf common and typi-
In addition to the information on post-fur- cal integration of the particulate, nitrogen-ox-

High-Dust SCRICold Side ESPIWet FGD


- Wet
Boiler - SCR - Htr. - orESP
-t
Air
FF
Fan
FGD
-- Stack

-
High-Dust SCRISpray Dry Scrubbing

- - -
Fan
Boiler
;
SCR
-
Air
Htr.
ESP
orFF. 9 L
Stack

Low-Dust SCRIHot Side ESPMlet FGD


Fan

-- - --
Boiler
Hot
BP
SCR
Air
Htr.
Wet
FGD
-C

1
Stack

1 1

Fig..3- -.Typical power-plantflue-gas cleaning systems


COMBu
sTI
m
Control of PMverPIant S W k Emissions

ide, and sulfur-dioxide control systems. SCR moval efficiency of particulates. The variation
equipment, if used, can be designed for either in ash content, ash composition, ash resistiv-
high or low dust contents, thus dictating the ity, and particle size distribution requires an
position of the electrostatic precipitator. See engineering evaluation of collection principles
reference 2 for a generic description of the vari- to reduce emissions to required levels.
ous gas-cleaning systems, and other sections of
this chapter for detailed discussions of the wet INFLUENCE
and spray-drying desulfurization processes. OF VOLUMETRIC GAS FLOW
No matter what type of flyash collector is to
be installed on a steam generator, it is essential
PARTICULATE EMISSION that it be designed for the correct gas volume.
CONTROL Manufacturers design and size their equip-
ment based upon their experience with this
Particulate emission control deals with equipment. This experience includes tests on
methods of removing particles dispersed in ef- both laboratory or pilot-plant equipment, and
fluent gases of power, industrial process, and full-scale equipment. The joint American
commercial plants. These dispersions have Boiler Manufacturers Association (ABMA) and
through general use come to include all parti- Industrial Gas Cleaning Institute (IGCI) survey
cles in air or other gases. has shown there to be a difference in the vol-
Dispersoids are characterized by their physi- ume of flue gas that is measured by pitot tube
cal, chemical, and electrical properties, their and the volume of gas that is calculated from a
particle size and structure, rate of settling un- stoichiometric balance.'
der gravity, optical activity, the ability to ab- The pitot tube consistently indicates a higher
sorb a n electrical charge, the surface- volume. The manufacturer of the dust-collec-
to-volume ratio, and the chemical reaction tion or desulfurization equipment, therefore,
rate. Particles larger than 100 pm are excluded must ascertain if the gas volume for equipment
from consideration because they settle rapidly. design has been stoichiometrically calculated
Dispersoids are generally classified as dust, and be aware that the value may differ from a
smoke, fumes, and mists. Fig 4A indicates the volumemeasured by pitot tube in the operating
common dispersoids and the typical particle installation. It is vital that proper corrections
size for each classification. Fig. 4B shows the be made for plant elevation and local negative
devices for collecting the various classifica- pressure ahead of the induced-draft fan, to ar-
tions of dispersoids. Note that methods relying rive at the actual gas volume. (See Chapter 6
on gravity or centrifugal forces are effective for and reference 3 .)
removal of particles larger than 10 micrometers Performance testing required to demonstrate
radius. Efficient collection of 1 pm and sub- compliance with air-quality regulations uses
micrometer particulate requires devices that pitot-tube techniques as proscribed by EPA
depend on electrical force, impaction, inter- Reference Methods 1,5 and 16.5 See Chapter 22
ception, or inertial diffusion; these are the cap- for more on gas-volume measurement.
ture mechanisms at work in electrostatic
precipitators, fabric filters, and high-energy MEASUREMENT TECHNIQUES
wet scrubbing. It is difficult to analyze size distribution of
INFLUENCE OF COAL fine particulate matter because flyash is non-
AND COMBUSTION CHARACTERISTICS homogeneous. The. varying specific gravity
and particle shape make it difficult to describe
The varying coal characteristics described in size in absolute terms. Many methods, includ-
Chapter 2 have a dominant effect on the re- ing photomicrographs and various sedimenta-
Control of Power-Plant Stack Emissions

tion and elutriation techniques, have been used gravity. Determination of terminal velocity for
to determine size distribution. The ASME Per- a centrifugal classifier is included in ASME
formance Test Code Committee has selected ter- Performance Test Code 28.
minal settling velocity to characterize flyash Flyash characterization also -includes meth-
particulate emissions from furnaces. ods for bulk electrical resistivity, in-situ resis-
tivity, and particle size.
TERMINAL VELOCITY
BULK ELECTRICAL RESISTIVITY
Particle terminal velocity is a significant pa-
rameter in the design of mechanical separators Particulate resistivity can be determined in a
that use inertial or centrifugal forces to separate high-voltage conductivity cell in which a sam-
dust from a gas stream. It includes the effect of ple of known thickness is placed between two
particle shape and specific gravity for each par- oppositely charged electrodes. Guard rings
ticle. Its determination is important for heter- eliminate fringe effects. The potential between
ogeneous dusts of varying shape and specific the two electrodes is increased and the voltage

0.001 0.01 0.1 1 10 100 1 000 10 000


(A) Dispersoids, Diameter in Microns (micrometers,prn)
I I
I Settling Chambers
I I
Centrifugal (Mech.) Dust Separators
1
Fabric Filters 1
Electrostatic Precipitators
I I
Microporous Filters I --Common Air Filters
I I
I Liquid Scrubbers

(B) Methods of Collections


I I

Fig. 4 Classification of dispersoids and methods of collection


COrQjuSTION
ConW of PoworSlant Stack Emissions

and current noted until an electrical break- This inner vortex has an axially upward com-
down occurs. The resistivity is then calculated ponent which carries the spirally flowing gas
and reported in ohm-cm at 85 to 95 percent of to the outlet pipe at the upper center of the sep-
the average breakover. arating unit. Because these collectors depend
IN-SITU RESISTIVITY primarily on differential inertia, collection effi-
ciencies vary with particle size, particle den-
A combination high-voltage and ground- sity, gas temperature, and pressure drop
potential probe, inserted in the gas stream, has through the apparatus. Efficiencies are very
a negative high-voltage probe consisting of a high on material greater than 20 micrometers
flat disc concentric about a needle-point elec- (20pm) in size, but drop off rapidly for smaller
trode. The needle-point electrode precipitates particles. The overall collection efficiency of a
the particulates electrically from the disper- cyclone can be estimated when the particle-
soid. The flat charged disc is separated from size distribution and specific gravity of the
the needle point so as not to affect the precipi- dust and the allowable pressure drop are
tation of particulate onto a grounded electrode. known. Fig. 6 relates collection efficiency to
After a short time, the charged disc is lowered particle size. In normal boiler operation, differ-
to entrap the precipitated particulate between ential-pressure requirements for mechanical
it and the grounded electrode. Calculation is collectors are from 2 to 5" WG.
the same as for bulk electrical resisti~ity.~
WET SCRUBBERS
DUST COLLECTION
BY MECHANICAL MEANS In the analysis of particulate scrubbing, a
number of important facts are known. First, the
Although- cyclone-type
- mechanical collec-
tors have a long history-in boiler service, their
use is now limited to stoker-fired and fluid-
ized-bed units. Mechanical collectors can be Clean
Gas
either dry cyclone collectors or wet scrubbers. Outlet
MECHANICAL CYCLONE COLLECTORS Dust Laden Gas Inlet
These devices achieve particulate removal by
centrifugal, inertial, and gravitational forces Whirl Vanes
developed i n a vortex separator. The dust-
laden gas is admitted either tangentially or axi-
ally_over whirl vanes (Fig. 5) to create a high
velocity in the cylindrical portion of the de- Central Vortex Sink
vice. Particles are subjected to a centrifugal
force and an oppositely directed viscous drag.
The balance between these two forces deter- Downwardly-Directed
mines whether a particle will move to the wall Peripheral Flow
or be carried into the vortex sink and be passed
on to the clean-gas outlet tube.
The high-velocity, downwardly directed
vortex is reversed at the bottom of the cylindri-
cal section. In this reversal, inertia and gravity, Dust
as well as centrifugal force, inject the dust into to
the hopper. The action of the reversed-gas cir- Removal System
culation takes place over a small diameter but
at a relatively great velocity. Fig. 5 Principle of cyclone-separator operation
COMBUSPION
Control of Power-Plant Stack Emissions

_ - - _

Typical for Dust


Specific Gravity of 2.50

I
30 35 40
Dust Particle Size, Micrometers (pm)

Fig. 6 Form of mechanical cyclone dust-collector efficiency curve versus particle size

dust particle must impact on the water droplet. Fig. 7 shows a typical efficiency curve for a
The im~actionefficiencv is a function of the wet scrubber operating at 6" WG pressure drop.
dimensionless group @where V, is the rel- VENTURISCRUBBERS
DE!
ative velocity between &e water droplet and In a venturi scrubber, dust-laden gases are
the dust particle, V, is the settling velocity for wetted continuously at the venturi throat.
the dust particle, D is the diameter of the water Flowing at 12,000 to 18,000 fpm, the gases pro-
droplet in micrometers, and g is the accelera- duce a shearing force on the scrubbing liquor
tion of gravity. As g and V, are constant for a due to the initial high velocity differential be-
dust particle of given size, target efficiency is a tween the two streams. This shearing force
direct function of the relative velocity and an causes the liquor to atomize into very fine
inverse function of the droplet diameter. If the droplets.
collection efficiency depends critically on rela-
tive velocity and droplet size, then collection
efficiency must also be a function of the power
supplied to the unit.
Capture of small particles requires high en-
ergy inputs, usually in the form of greater pres-
s u r e drops across the scrubber. Low- .- 6" WG Pressure Drop
.g 60
pressure-drop scrubbers, such as-spray towers, 5
collect coarse dust in the range of 2 to 5 mi- r 40
.-
0
crometers. High-pressure-drop venturi scrub-
-8
C

20-
bers are effective in removing 0.1 to 1.0 -
micrometer particles. S o 1
0.5
1 1
1.0
'
1.5
1 '
2.0
1

Typically, a scrubber operating at 6" WG EffectiveParticle Size, pm


pressure drop should capture practically all of
the particles greater than 5pm and about 90
percent of the particles in the 1to 2pm range. Fig. 7 Wet-scrubber fractional efficiency curve
- am5usnON
CunM of Pawer-Piant Stack Emissions

Impaction takes place between the dust en- vibrators removed particulate from the collect-
trained in the gas stream and the liquid drop- ing plates.
lets. As the gas decelerates, collision continues To meet a demand for ultra-high efficiency
and agglomerated dust-laden liquor droplets collectors of rugged construction and high reli-
discharge through a , diffuser into the lower ability, European manufacturers in possession
chamber of a separator vessel. Impingement of of the basic patents disseminated by Frederick
the stream into the liquid reservoir removes Gardner Cottrell developed the rigid-frame pre-
most of the particulate. cipitator. Actually, this design more closely
A- venturi-type scrubber operating in the approximated Cottrell's original design than
pressure range of 30 to 40" WG can collect did the U.S.-style weighted-wire designs. The
nearly 100 percent of 0.2 to 1.0 pm particles. term rigid-frame refers to the rugged pipe-
frame or mast-construction discharge elec-
ELECTROSTATIC PRECIPITATION OF DUST trode, which largely precludes wire breakage.
In electrostatic precipitation, suspended par- The basic design incorporates segmented col-
ticles in the gas are electrically-charged, then lecting plate configurations and profiles, for
driven to collecting electrodes by an electrical close fabrication tolerances over heights up to
field; the electrodes are rapped to cause the 52 feet; rigid discharge electrodes; and much
particles to drop into collecting hoppers. This greater division of rapping, often with individ-
process differs from mechanical or filtering ual rapping for each discharge frame.
processes in which forces are exerted directly
on the particulates rather than the gas as a ELECTROSTATIC COLLECTION TECHNIQUE
whole. Effective separation of particles can be
achieved with lower power expenditure, with Fig. 8 shows in simple fashion the principle
of electrostatic precipitation. The pr,ocess ap-
negligible draft loss, and with little or no effect
plies an electrostatic charge to dust particles
on the composition of the gas.
In the United States, the control of emissions with a corona discharge and passes them
through an electrical field where the particles
began with preventing or minimizing nuisance
are attracted to a collecting surface. The basic
smoke. Such control required equipment capa-
elements of a precipitator include a source of
ble of only 70- to 90-percent efficiency. Later,
unidirectional voltage, corona or discharge
the need to protect induced-draft fans from ero-
electrodes, collecting electrodes, and a means
sion by reducing entrained flyash emitted from
of removing the collected matter.
utility boilers led to precipitators being built
Single-state (Cottrell type) precipitators com-
for power plants. The first such application
bine the ionizing and collecting step (Fig. 9A).
was 1923.7-
In the more common plate type, the electrodes
The early users of electrostatic precipitators,
are suspended between plates on insulators
then installed them to
connected to a high-voltage source. A voltage
recover a valuable product, such as lead, cop-
differential created between the discharge and
per, or saltcake
collecting electrodes develops a strong electri-
eliminate a nuisance, either visual or damag- cal field between them. The flue gas passes
ing to crops through the field and a unipolar discharge of
protect process equipment, such as induced- gas ions, from the discharge electrode, attaches
draft fans. to the particulate matter.
As initially applied, precipitators were de- The unipolar discharge of gas ions (normally
signed to provide-a minimum plate area at low negative charge) occurs at a critical voltage at
cost; designs used interlocking or opzel col- which gas molecules are ionized. The ioniza-
lecting plates and hanging weighted-wire dis- tion is visible as a corona at the discharge elec-
charge electrodes. Roof-mounted gang-rapping trode. The negative ions move towards the
COrnrnON
Control of Power-Plant Stack Emissions

Electrical Field Charged Particles


Collector Electrode Discharge Electrode
at Positive Polarity at Negative Polarity

Particulate-Laden Gas Exit


Gas Flow
High Tension Supply
Uncharged Particles from Rectifier

Particles Attracted to Collector Electrode


and Forming Dust Layer

Fig. 8 Principle of electrostatic precipitator operation '

positive collecting electrode; the positive ions and collecting stages are separated (Fig. 9B).
migrate toward the discharge electrode. In this This design is used for low particulate loadings
movement, the ions become attached to parti- and minimum ozone generation.
cles carried by the gas stream. The charge is the Single-stage precipitators can be either
force that moves flyash to the appropriate elec- weighted-wire or rigid-frame units. Weighted-
trode. The particles attached to the positive wire units work well on high-sulfur coal and
electrode dissipate their charge and become easily removed particulates and have economic
electrically neutral. The particulates on the col- designs. The rigid-frame precipitator is better
lecting electrode are removed mechanically by suited to applications where high-resistivity
rapping or washing. ash is to be collected and large collecting areas
In the two-stage precipitator, the ionizing are needed.

or Pre-Ionizing

(A) Rigid-Frame Single-Stage Precipitator (B) Two-Stage Precipitator

Fig. 9 Single-stage and two-stage precipitators


C O ~ O N
Control of Power-Plant Stack Emissions

PRECIPITATORDESIGN FACTORS velocities between 3 and 4 fttsec. For high-sul-


Precipitator designs consider fur, high-sodium coals, velocities on the order
specific collection area of 5 fps are used.
8 treatment time Electrode Configuration and Spacing
gas velocity The shape and spacing of the electrodes can
electrode configuration and spacing drastically affect the amount of peak voltage
' 8 number of fields and current achieved in the precipitator before
automatic voltage control sparking occurs. The selection of transformed
hopper size and slope rectifier (T/R) sets with adequate kVA ratings
and sensitive controls can affect this voltage
and current.9
Specific Collection Area (SCA)
Number of Fields
The SCA relates the size of one precipitator
to another in terms of the effective collecting- For reliability, precipitators are divided into
electrode surface area in square feet per thou- fields, each of which is composed of one or
sand cfm (cubic ftlmin) of gas treated. The area more independent electrical sections in the di-
considered is the flat projected surface of both rection of gas flow. The amount of plate area
sides of the collecting electrodes; the gas vol- per transformedrectifier set can affect the peak
ume is the actual volume at the design operat- current and voltage achieved in a n electrical
ing temperature and power-plant elevation. section. Systems with a large number of fields
Depending upon the physical, chemical, and (5, 6, or more) are not seriously impaired by the
electrical characteristics of the coal ash, precip- loss of a single field.
itator SCA's range from 300 to 1,000 for collec-
Automatic Voltage Control (AVC)
tion efficiencies above 99.5 percent.8
Treatment lime The AVC system keeps the precipitator oper-
ating at its optimum voltage. Such control sys-
This refers to the length of time a particle tems can be either analog or digital. Digital
will spend in the presence of the electrical control systems are able to maintain higher pre-
field, at design velocity, if it were allowed to cipitation voltage potential between the dis-
traverse the entire length of the precipitator. charge electrode and the collecting plate than
The treatment length is not the total front-to- analog systems.
Microprocessor-based AVC systems can be .
rear dimension of the"'box," but is rather the
horizontal dimension from the plane of the designed to reduce overall ESP power con-
front face of the first collector to the rear plane sumption during load changes. Such a system
of the last surface less any space for walkways. can provide users with features such as inter-
mittent energization-blocking selected AC-
Gas Velocity voltage half cycles to decrease power
Superficial gas velocity is a critical design usage-and automatically modulated ramp rate
parameter. It is calculated by dividing the ac- to maintain present spark rates.1
tual gas volume (at design temperature and Hopper Sire and Slope
plant elevation) by the face area of the precipi-
tator immediately in front of the first collecting The proper design of the collecting hoppers
electrode. Effective plate height is multiplied forming the floor of s precipitator is important
by the inside face-tozface dimension between because a breakdown in hopper outflow that
the side-wall casings to give the face area. results in overfilling can severely damage the
Designs for low-sulfur, low-sodium coals use electrical internals. C-E has made comprehen-
COMBUSTION
Control of Power-Plant Stack EmiWons

sive recommendations concerning the design tion velocity and has led to the development of
and heating of precipitator and fabric-filter a modified equation:
hoppers, and their flyash-removal systems.11
These recommendations, some of which are -
detailed later in this chapter, help the industry
avoid costly outages attributable to these por-
tions of the collection/transport complex.
(2)
PRECIPITATOR DESIGN ANALYSIS
where w, is now the empirical migration veloc-
It is traditional to consider the semi-empiri-
ity at an observed lower efficiency, and k is a
cal Deutsch-Anderson equation in the analyti-
constant, approximately 0.5 but varying be-
cal design of a precipitator for efficiencies up to
98 percent. Above that level, performance can
tween 0.4 and 0.6 depending on the specific
ash and application. The other terms are as de-
be predicted accurately by a modified form of
fined for equation 1.
the Deutsch-Anderson formula.
Electrostatic-precipitator collection effi- Migration or Drift Velocity
ciency is related to the total surface of the col-
lection electrodes per unit volume of gas (the The drift velocity w, also called the "precipi-
SCA) and is directly proportional to the parti- tation rate," is determined by the magnitude of
cle migration velocity. Efficiency, in the the particle charge, the strength of the electri-
Deutsch-Anderson equation, is determined by cal field, and by Stokes law for the drag of the
particles.7.12 There is a significant discrepancy
between theoretical and practical values of w,
with the theoretical being about twice the ac-
tual, or more.13.14 This loss of performance is
caused by such factors as uneven gas flow, par-
ticle diffusion, electric wind, particle charging
time, and loss of particles from collecting sur-
faces by reentrainment.
where Because of these uncertainties, and the ef-
7 = efficiency of collection, percent fects of performance of concentration varia-
e =base of natural logarithms (2.718 . . .) tion in SO, and sodium in the flue gas and the
A = collecting-electrode surface area, ft2 flyash, it is necessary to rely upon field ex-
w =migration velocity, fps, and perience with a variety of precipitator installa-
V = actual volumetric gas-flow rate, in 1000 tion~.7~*.13.1s.l6,17
Where experience is limited,
ft3/sec (at temperature and elevation) designs are established by means of experimen-
Although important to an understanding of tation and pilot-plant testing.'". 20. 21
199

the precipitation process, the Deutsch-Ander- EFFECT OF ELECTRICAL PROPERTIES


son equation does not satisfactorily predict per-
formance for a known ash at higher or lower The electrical conductivity of flyash and the
efficiencies than an actual test point. That is be- dielectric strength of the bulk ash are two prop-
cause it relies entirely on Stokes law and is erties important to the electrostatic-collection
properly applied only to average-size particles process. For effective operation, a small but
that are effectively the same size and experi- definite electric current, in the form of charges
ence the same force. The lack of correlation of carried by gas ions and particles, flows be-
analytical and field-performance data has been tween the high-tension discharge electrodes
found to be specific to the variation in migra- and the collecting electrodes. This current
-
COMBUSPION
Conbol of Power9Iant Stack Emissions
-
must pass through the layers of collected ash dium, potassium, calcium, carbon, alumina,
which normally coat the plates. The ash, there- silica, and iron oxide.
fore, must be able to conduct the ionic current Ash resistivity is inversely proportional to
to the grounded metal surfaces of the plates. the concentration of sulfur trioxide and water
The electrical conductivity required is very in the flue gas and the sodium, potassium, and
small: about 10'' mho. In practice, it is usually carbon in the ash. It is directly proportional to
more convenient to express this in terms of re- the ash constituents of calcium, magnesium,
sistivity, which is the inverse of conductivity. alumina, and silica. Peak ash resistivities occur
The dielectric strength of the collected ash on between 250" and 450F, depending upon
the plate electrodes is also an important electri- coal-ash and flue-gas characteristics. Above
cal property of the ash. The build-up of charge 450F to 550F, the ash resistivity is inversely
on the ash layer produces a voltage or potential proportional to the absolute temperature, while
drop across the layers in accordance with below 250F to 300F, the resistivity is directly
Ohm's law. When the resistivity of the ash is in proportional to the absolute temperature.
the critical zone (near 2 x 10" ohm-cm), the Low-resistivity ash is a problem because the
voltage drop across the ash layer can amount to ash easily loses its charge after being collected
several kV. The existence of this voltage drop on the plates. The uncharged particles may
across the layer may be sufficient to cause it to then be reentrained in the flue gas. High-resis-
break down electrically. tivity ash does not readily lose its charge when
When this happens, a spark flashes through collected on the plates and the agglomerated
the dust layer and is propagated to the dis- ash can be very difficult to remove. When a
charge electrode. This is the source of the in- deep enough layer of high-resistivity ash col-
tensified sparking which occurs with dusts of lects on the plate, back-corona develops on the
excessive resistivity. Clearly, the higher the di- ash surface and the precipitator can no longer
electric or breakdown strength of the dust collect efficiently.
layer, the higher the resistivity which may be Back-corona is extremely detrimental to pre-
tolerated for a given amount of corona current. cipitator performance. It occurs when a particle
Thus, dusts of relatively high breakdown migrates to the collecting surface)but fails to
strength are less sensitive to resistivity effects dissipate its charge, causing a high potential
than dusts of low dielectric strength. gradient in the dust layer on the surface of the
For flyash, the dielectric strength of the bulk plate. This layer disrupts the electrical field
ash in 114 to l/z in. thick layers ranges from as that induces migration, and repels particles of
low as a few hundred V/cm up to as high as 20 like charge attempting to migrate to the collect-
kV/cm. The average value of dielectric strength ing surface.
is in the 5 to 10kV/cm range.
Measurement of Dust Resistiyity
Ash Resistivity
Dust resistivity, to have any possible value to
Experience has shown that coal ashes with a precipitator design engineer, must be meas-
resistivities above 5 x 10" ohm-cm are difficult ured with the dust under the same gas and tem-
to collect. Low resistivity (less than log ohm- perature conditions as those at which the
cm) ash tends to suffer from excessive reen- precipitator will operate. Also, the packing
trainment, but such low resistivities are rarely density of the dust should be the same as that of
encountered. The area between 10' and 5 x 10" the dust layer deposited on the precipitator col-
ohm-cm usually is normal for satisfactory and lectors. It will be appreciated, then, that the
predictable precipitator design. measurement of dust resistivity is subject to
The factors that affect resistivity are the sul- considerable problems, making it very difficult
fur content of the coal, flue-gas temperature in practice to relate absolute precipitation effi-
and moisture, and such ash constituents as so- ciency to dust resistivity.
COMBUSTION
Control of Power-Plant Stack Emissions

Fig. 10 indicates the in-situ bulk resistivity ents and allow for differential expansion if
of a variety of fuels as related to temperature. such temperature gradients cannot be avoided.
Although there is a significant difference be-
Gas Conditioning
tween many of the ash samples tested at tem-
peratures below 4 0 b 0 ~it, appears that, above Migration velocity declines as resistivity in-
600F, most ash will have resistivities below creases (Fig. ll),as is characteristic of many
the level of 5 x loll ohm-cm. low-sulfur subbituminous coals. Adding SO, to
For this reason some precipitators have been flue gas can reduce ash resistivity.26 For some
located between the boiler economizer and the western-U.S. low-sulfur coals, an increase of
air heaters, in what is called the "hot" posi- 30 ppm of SO, in the gas has reduced the flyash
tion, instead of downstream of the air heaters, resistivity from between 10"and 1012to 5 x log.
the ordinary "cold" position. Hot precipitators
are used to avoid back corona, to minimize the COHESIVE AND ADHESIVE
PROPERTIES OF FLYASH
heavy rapping that is sometimes needed at
lower temperatures, and'to increase the effec- These properties of flyash are important for
tive migration velocity.22.2s collection by electrostatic precipitators, where
The structural and mechanical design of hot the ash forms in compacted layers on the elec-
precipitators is more critical than that of equip- trode surfaces. Typically, these layers are less
ment to be operated at the 300F temperature than 0.5 in. thick, but may in some cases build
level. Designs should minimize thermal gradi- up to 1 in. or more. Although some ash falls

1 0 1 5 ~ ,Hunter Valley, Australia

estern Australia

Northern Australia
Arizona &WyomingSubbituminous
0.5-1.OO/o S Eastern U.S.Bituminous
.5-2.0%S Eastern U.S. Bituminous
lo1'-

10'O -
Wyoming Subbituminous
109-
Flyash at High Tempe1
("Typical Flyash," Ref.
lo8 -

I I

Fig. 70 Composite of in-situ flyash resistivity data versus temperature, from several sources (Refs 18,22,
23,24)
. COMBUSllON
Contrd of Power-Plant Sbdc Emissions

decreasing particle size. But other factors such


as particle shape and composition also influ-
ence the adhesion and cohesion of particles.
The presence of condensed moisture, with pos-
sible cementing effects, can also profoundly in-
fluence the build-up of particles on electrodes
and other surfaces.
In electrostatic precipitators the accumula-
tion of ions .on the collected dust layers pro-
duces an additional retention force of major
importance. These ions tend to charge the col-
lected particles so that they are attracted to the
collecting plates by relatively strong electric
- 0 forces. Further, any particles that do escape
1o9 10'0 lo1* from the collected layers of ash tend to be im-
Resistivity,ohm-cm mediately recharged electrically by the corona
I I
ions and forced back to the collecting plates.
Fig. 11 Precipitation rate versus resistivityfor The particle-retaining force of the corona cur-
representative group of flyash precipitators rent increases with the electrical resistivity of
the particles and with the strength of the cur-
rent. Thus it is often advantageous to operate
into the hoppers because of either the mechani- precipitators at relatively high-corona current
cal vibrations frequently present in plant struc- densities-particularly the outlet sections.14
tures or its own weight, rapping or jarring of Agglomerated masses of particles, removed
the electrodes is usually necessary to effec- from the electrodes by rapping, fall into the
tively remove the collected ash layers. The ash hoppers by the force of gravity. These agglom-
generally breaks away in isolated patches, so erated masses are bound together by molecular
that the collecting-plate surfaces present a cohesive forces. For best performance, these
somewhat spotty appearance.14 falling agglomerates must be relatively stable
It is well known that fine solid particles tend and fall with as little loss of particles as possi-
to cohere and to form agglomerated masses ble. If the falling agglomerates have little co-
which have a small but definite stability. The herence, some may break u p and be
coherence of the particles is caused by molec- redispersed in the gas stream, thus partially
ular attractive forces at the points of contact of nullifying the collecting action of the
the particles. The degree of coherence is appre- precipitator.
ciable only for relatively fine particles of less The presence of coarse particles tends to re-
than about 20 to 40pm. Coarse or granular par- duce the cohesive and adhesive forces and,
ticles such as sand, for example, do not cohere therefore, the agglomerating effect which holds
in the dry state. On the other hand, fume parti- masses of fine particles together. Excessive
ticles, which typically are less than 1pm in amounts of coarse, gritty particles in an ash
size, usually show a high degree of coherence. make the ash difficult to hold on the collecting
The adhesion of particles to the collecting plates and also lead to loose, unstable agglom-
electrodes is also the result of molecular attrac- erates when the plates are rapped. On the other
tive forces, and, similar to cohesion, the adhe- hand, the elimination of all coarse particles
sive forces are rarger for fine particles. Thus, above 10 to 20pm may in some cases make re-
the adhesion and retention of the collected lay- moval of the ash difficult. As there also will be
ers of ash on the electrodes are determined ba- a much greater tendency for the particles to
sically by particle size, and increase with build up on the discharge electrodes, a very
COMBUSITON
Control of Power-Plant Stack Emissions

fine ash containing no coarse particles presents quired treatment length is figured. Selection is
a more difficult rapping problem.14 now complete if the equipment fits the allo-
cated space envelope. Should the equipment
CONSTRUCTIONOF
ELECTROSTATIC PRECIPITATORS
extend beyond width constraints, alternative
selections must be made.
The weighted-wire type of precipitator has There are four basic arrangements for locat-
been well described in references 2 , 7, 27, 28 ing precipitators in a given plot plan (Fig. 12):
and 29. Features of the rigid-frame design can in-line
be found in references 2, 17, 21, and 29. cross-flow
In the rigid-frame design, the carbon-steel piggyback
collecting plates are constructed of profiled
segments approximately 18 to 19 in. wide and chevron
up to 52 ft long. They attach at the top to back- The preferred arrangement is in-line because
to-back channels spanning the insulator hous- of such advantages as:
ing, usually on 12-foot centers. At the bottom, lowest capital cost
anvil or spacer b x s maintain plate alignment good flow balance between chambers
and act as anvils for plate rapping. The collect- best gas distribution within a chamber
ing-electrode plates are rapped individually by
lowest system pressure drop
mechanical hammers indexed on a shaft driven
from outside the precipitator shell. easy removal of internals in event of damage
Made from steel tubing, the individually sus- due to fires, explosion, or corrosion
pended and rapped discharge frames are typi- ease of erection and shortest time span to in-
cally up to 26 ft long and are located one above stall a precipitator system.
the other. The discharge wire itself can be star- In laying out a plant, rigid-frame precipita-
shaped; thin, flat wire with barbs; or have an- tors have a decided advantage over weighted-
other profile depending upon t h e wire units because field heights can be 52 ft for
manufacturer. Insulators carrying the high-ten- the rigid-frame, and a maximum of 36 ft for the
sion support steel-work are located in the insu- weighted-wire. In many instances a rigid-frame
lator housing. There is no high-tension framing unit will fit in-line, whereas the weighted-wire
and, therefore, no access above the collecting design must be arranged in one of the other,
plates. The discharge frames are individually less desirable, ways.
rapped by mechancial hammers driven from
FLYASH RECEIVING HOPPERS
outside the precipitator and are restrained front
and rear to maintain electrical clearances. With During operation, the flyash accumulated on
top suspension for all internals, expansion al- the collecting surfaces of the precipitator is pe-
lowances are provided in the lower alignment riodically shaken loose, and dropped into to
steel work. the hoppers. The level of dust in each hopper
will rise until that particular hopper is emp-
PRECIPITATOR ARRANGEMENT
tied. If for any reason, emptying the hopper is
After calculating the total collecting area of a delayed until the dust level approaches the ele-
precipitator, the application engineer must de- vation of the bottom of the discharge elec-
termine the shape of the box required to house trodes, they will be electrically short-circuited
the internals. The beginning point is the com- to ground through the mass of collected dust.
putation of precipitator frontal area (width x The affected precipitator section will cease
height) using an acceptable gas velocity to the functioning in a normal manner, but will con-
unit-ordinarily 3 to 5 fttsec for a coal-fired tinue to collect some dust by acting as a settling
boiler application. Once field height and num- chamber.
ber of gas passages have been determined, re- If the dust and flue gas entering the precipi-
In-L~neArrangement Cross-Flow Arrangement

Piggyback Arrangement Chevron Arrangement

Fig. 12 Basic precipitator arrangements

tator are reasonably well distributed, all pre- gases. Applications range from nuisance-par-
cipitator hoppers in any row perpendicular to ticulate collection (for the control'of silo dust
the gas flow will collect substantially the same emissions or conveyor transfer station dust
quantity of dust per unit time. However, much control) to process applications where the fab-
more flyash will be collected in the rows of ric filter equipment is an integral piece of pro-
hoppers closer to the precipitator inlet than in cess equipment used to capture the product [as
the rows toward the rear of the precipitator.
The quantities can be approximated with rea-
sonable accuracy by use of the Deutsch equa- Table I.Percent of Flyash Collected In
tion, An example is shown in Table I for four Each Row of Hoppers
precipitators having overall efficiencies of 99.6
percent and from 3 to 6 rows of hoppers in the Total number of rows, front to rear
direction of gas flow. In modern flyash precipi- Row No. 3 4 5 6
tators, then, the inlet row of hoppers can col- 1 84.1 74.9 66.9 60.2
lect from 40 to 100 times as much flyash as does 2 13.4 18.8 22.2 24.0
the rearmost row .30 3 2.1 4.7 7.3 9.3
FABRIC FILTRATION 4 - 1.2 2.4 3.9
5 - - - 0.8 1.6
Fabric filters, or baghouses as they are com- 6 - - - 0.6
monly called, have a long history of applica- TOTAL 99.6 99.6 99.6 99.6
tion in the capture of particulate from process
COMBUSTION
Control of Power-Plant Stack Emissions

with carbon-black manufacturing), and to sulting from the combustion process, i.e.,
strictly particulate capture for environmental boiler applications.
compliance (as with coal-fired boiler applica- TYPES OF FABRIC FILTERS _
tions). In general, fabric filters have found in-
creasing acceptance in applications where Fabric-filters have a reiatively constant col-
gas-borne particulate must be efficiently and lection efficiency and exhibit a varying pres-
dependably removed from gas streams. sure drop dependent upon the degree of cake
Fabric filtration is presently considered by thickness at any point of reference. Electro-
many as the best available control technology static precipitators, on the other hand, have a
to control particulate emissions from a gas relatively constant pressure drop, but will vary
stream. The development of new and improved in overall removal efficiency dependent on in-
fabrics and finishes since the early 1970's has let loading. Another way of expressing this re-
had a dramatic effect on the application poten- lationship is to say that the fabric-filter is a
tial of fabric filters, which in early years were constant-emission device (as measured by the
limited primarily to the natural material cloths mass of particulate emitted per unit of fuel
available at that time. These new cloths and fired), whereas the electrostatic precipitator is
finishes have greatly extended the allowable a constant-efficiency device (as measured by
operating-temperature window, the expected the percentage removal of inlet loading).
service life, the resistance to chemical attack, When dirty gas flows through a fabric, the
and the cake-release properties. captured particulate matter forms a cake on the
The preference of fabric filtration over other surface of the fabric. This deposit increases
types of particulate-removal equipment, pri- both the filtration efficiency of the cloth and its
marily electrostatic precipitators and high- resistance to gas flow. Thus, for continuous op-
energy wet scrubbers, is generally because of eration, a fabric-filter must have some mech-
the superior performance of fabric filters in the anism for periodic cleaning of the deposited
following areas: cake, and the mechanism chosen must be capa-
Outlet emissions are nearly independent of ble of maintaining a reasonable pressure drop,
the magnitude of the inlet dust loading. consistent with the operational pressure drop
Special fabrics and fabric finishes can signifi- limitations of the system in which it is in-
cantly reduce outlet emissions below the capa- stalled. The cleaning mechanism used fre-
bilities of the electrostatic precipitators and quently represents the generic name of the type
wet scrubbers. of equipment.
In addition to the above, the magnitude of
Particulatelgas chemical reactions can occur
the gas flow will have a bearing on the cleaning
in the fabric-filter system; thus, in the case of
mechanism or fabric-filter design selected.
dry flue-gas desulfurization systems, overall
Also, the intended service of the fabric-filter
sulfur-dioxide removal efficiency is improved
will have an additional influence on equip-
by as much as 15 to 20 percent because of the
ment selection, with more aggressive cleaning
interaction of the flue gas with the fabric-filter
mechanisms being used for more-difficult-to-
dust cake. dislodge cake. The designer of the system must
Captured particulate and chemical reaction address the merits of each filter type and
products removed from the filter bags (cake) re- choose the appropriate design for the system
main dry for ease of handling and disposal. requirements.
Although fabric-filters can be used in a wide
Shaker Type Fabric-Filters
variety of applications to control particulate
emissions, the emphasis in the following dis- In this oldest of filter designs, the cleaning
cussion is primarily on those applications in mechanism is a vigorous shaking of the filter
which the fabric-filter controls emissions re- bag to remove the deposited cake. The shaking
C-ON
Control of Power-Plant S h c k Emissions

action causes the cake to fracture and fall into be consistent with the cleaning mechanism, as
the collection and disposal hopper (Fig. 13). well as the chemistry and temperature of the
This method of cleaning has been applied to filtered gas.
both inside collectors (those collecting partic-
ulate matter on the inside of the individual Reverse-Air Type Fabric-Filters
filter bags) and outside collectors (those col-
lecting the particulate matter on the outside of Originally developed to accommodate the
the individual filter bags). relatively fragile fiberglass cloths selected for
The cleaning mechanism is a very aggressive fabric-filters operating at higher boiler flue gas
system limiting filter-bag cloth selections to or process' off-gas temperatures, this cleaning
those materials and weaves that can withstand method is generally associated with inside-
the rigors of cleaning without premature cloth type collection units, although some variation
failure, andlor where special precautions have of this design can be found in limited and
been taken to address the forces acting on the unique applications. The name reverse-air is
filter bags during the cleaning cycle, such as really a misrepresentation; properly named the
the amplitude of shake, t\e frequency of shake, cleaning mechanism should be called reverse-
and bag tension. gas, since the cleaning mechanism is a reverse
Shaker designs, being the oldest type, have flow of gas through an isolated compartment to
been used in a variety of applications from am- cause an inward collapsing of the filter bag and
bient-condition nuisance-dust collection (those thus the fracturing of the filter cake [Fig. 14).
typically seen on bin vent filters and dust-sup- Low airlcloth (AIC) ratios characterize re-
pression systems on conveyor transfer points) verse-air units, with typical gross ratios (with
to small industrial-boiler applications (those all compartments in service) ranging between
using the outside-collector type designs) and 1.5 and 2.0. The airlcloth ratio given for any
large utility applications (those using inside- operating condition represents the cubic feet of
collector-type designs on coal-fired boilers). In gas filtered divided by the square feet of filter
all cases, the fabric cloth is carefully selected to cloth currently in service.

Damper
Closed

Released
Cake

I Operating Cycle Cleaning Cycle


I
Fig. 73 Schematicarrangement of shaker-type fabric filter
COldBDSnON
Control of Power-Plant S W k Emissions

Filter-bag attachment hardware consists of a partments required, to insure a reasonable AIC


cap installed in the upper top portion of the ratio under all operating conditions. Of con-
bag. This arrangement allows for attachment of cern in these calculations is the effective AIC
the bag to the tensioning device which is hung ratio during the cleaning mode, and the maxi-
from the compartment bag hanging frame. An mum ratio in the event of full-load operation
adjustable clamp or a sewn-in band fastens the with one compartment isolated for any mainte-
bottom cuff of the bag to the tube-sheet. Both nance activity plus one additional compart-
arrangements allow direct attachment to the ment in the cleaning mode. Generally, the
tube-sheet thimble. Filter bags for reverse-air maximum AIC ratio with two compartments
service contain multiple rings sewn in the bag out of service, and with one in the cleaning
length to prevent total collapse during the mode, is limited to 2.5 for these types of units.
cleaning cycle (Fig. 14). The cleaning frequency of the individual
Although the bag hardware represents only a compartments will depend, in part, upon the
small fraction of the total cost of the fabric-filter resistivity of the filter cake formed and the inlet
system, this- hardware can cause problems if grain loading being experienced. As the inlet
not properly selected with respect to both de- grain loading increases, all other parameters
sign and material. Any component that con- remaining equal, the frequency of cleaning will
tacts the cloth needs to be carefully chosen to also increase, which results in a greater time of
insure that premature cloth damage will not oc- operation of the filter unit in the net (less than
cur during normal operation of the unit; that is, full complement of compartments operating)
edges need to be smooth and excessive como- condition. Ideally, a properly designed fabric-
sion should be prevented. filter unit should operate in the gross condition
Depending on the inlet grain loading and the majority of the time as this represents the
particle-size distribution, the designer of the most efficient filtering mode (lowest AIC ratio)
fabric-filter unit will adjust the design airlcloth and lowest differential system pressure-drop.
ratio andlor the total number of system com- This fabric-filter design using appropriate

Reverse "Air" In

Collected

Operating Cycle Cleaning Cycle

Fig. 14 Schematic arrangement of reverse-air type fabric filter


--
C O ~ O N
Control of Power-Plant Stack Emissions

cloth materials has been applied to a wide tem- to the inside of the bag through the venturi to
perature range, from near ambient to more than the clean-gas plenum, and exits through the
500F. An advantage of this particular system compartment outlet damper. The individual
is the ability to use fiberglass cloth which can bags and support cages are installed and re-
withstand wide ranges in temperature without moved from the top of the compartment
physical damage. The reverse-air system, being through the clean-gas plenum. The clean-air
the most gentle method of filter bag cleaning, is plenum can be either a full height walk-in type,
compatible with most available bag materials. an extension of the compartment casing, or a
top hatch-c~verdesign, which has removable
ShakelDeflate Fabric-Filters top hatch covers to reach the venturis and bags.
This type of unit combines the features of the Bag cleaning is by short pulses (50 to 100
shaker unit and the reverse-air unit in its de- milliseconds) of high-pressure air directed
sign. The unit is an inside type of collector downward into each bag in the row being
which uses shaking and mild reverse gas flow cleaned. Radial acceleration of the fabric and
during the cleaning cycle. dust cake causes a portion of the dust to be sep-
An advantage of the shakeldeflate unit is its arated from the bags. Gravity allows the re-
ability to operate at somewhat higher airlcloth leased cake to fall down between the bags into
ratios than pure reverse-air units due to the the discharge hopper. Within a single pulse-jet
more vigorous cleaning action of the shaking unit, or single compartment, rows of filter bags
mechanism. Following the shaking sequence
the filter bags are exposed to a mild reverse-air
deflation which further assists in cake removal
from the bags. This type of cleaning system is
sensitive to cloth selection and the parameters
of the cleaning cycle, as previously noted for
the pure shaker units, and has generally not
demonstrated the bag-life expectancy charac-
teristic of pure reverse-air units.
Pulse-Jet Fabric-Filters

The pulse-jet unit is an outside collector type


wherein the particulate-laden flue gas flows
from the outside to the inside of the filter bag.
Fig. 15 shows a generic pulse-jet collector with
the incoming flue gas entering the hopper and
flowing upwards and through the filter bags.
Wire or mesh-frame cages support the filter
bags to prevent their collapse during the filter-
ing period. Cages vary in both design and con-
struction material depending u p o n the
composition of the gas being filtered, the sup-
port requirements necessary for the filter-bag
construction, and customer preference with re-
spect to ease of handling and - the
-
potential re-
use of components. .--
The filtered particulate (cake) is trapped on i J
the outside of the bags while the clean gas Fig. 15 Generic pulse-jet fabric filter, with one
flows through the cake and cloth. It travels up filter bag being cleaned on-line
ComUSTION
C o n W of Power-Plant Stack Emissions

are pulsed sequentially under the control of a air operating scheme to smaller industrial boil-
solid-state programmer which is usually ers produced the modular reverse-air systems,
mounted adjacent to the collector casing. those that are made up of totally shop-assem-
The original operating concept for all pulse- bled compartment modules; these designs sub-
jet type of collectors was on-line pulse clean- stantially reduced field erection-labor costs.
ing; that is, the gas flow through the collector This same concept was then applied to the
was continuously maintained and the rows of pulse-jet units using shop-assembled modular
filter bags were pulsed sequentially either on a units and off-line cleaning. This allowed for
timed sequence or under control of the collec- pulse-jet systems composed of totally shop-as-
tor differential-pressure monitor. Although sembled modular systems including the extra
still an established practice in many nuisance- module for off-line cleaning. With this method
dust collection applications, this cleaning of operation, the features include:
method is a very inefficient cleaning process
1. Off-line cleaning, which is more effective as
when compared to off-line pulse cleaning. Con-
there is little tendency for the dust to mi-
sider only these facts:
grate to adjacent filter bags. Instead, the cake
The pressure pulse is from 50 to 100 millisec- has an opportunity to fall downward into the
ond in duration, and it is only during this pe- collection hopper(s).
riod that the gas flow through a row of bags is
stopped. 2. Pulsing pressure can be reduced as there is
no need to overcome the operating-system
Dust pulsed from one bag row is immediately
forward momentum.
reentrained on an adjacent bag row and, there-
fore, does not reach the hopper. 3 . Lower pulse pressures improve filter bag
Only after repeated pulsing will the captured life without sacrificing fabric-filter
cake gravitate to the hopper. performance.
The only logical explanation for the success The pulse-jet fabric-filter units, then, can be
of on-line pulse-jet cleaning is dust agglomera- cleaned in either an on-line mode, where the
tion. The dust particles form agglomerates compartment is not isolated from the system
which are heavy and dense enough to resist at- during the cleaning cycle, or an off-line mode,
traction to adjacent bags and, therefore, can fall where the compartment to be cleaned is re-
through the rising gas stream into the hopper. moved from on-line service by closing the com-
With the advent of large collectors to control partment outlet dampers prior to and during
emissions from hot processes (such as boilers), cleaning. Generally, the off-line mode is the
the on-line pulse-jet filter has been shown to preferred for boiler particulate-control installa-
have several disadvantages: tions, whereas the on-line mode would be cbm-
monly used for nuisance-dust applications. In
On-line maintenance and inspections are not the on-line mode, fewer filter bags are required
practical. in the total system. In the off-line mode, multi-
Compressed-air requirements are very large, ple compartments are required, including an
with increased filter area needed to maintain extra compartment to allow for the removal of
the required pressure-drop. one compartment, without affecting the overall
The physical properties of fiberglass fabrics system performance, during cleaning.
required for hot boiler processes are inconsis- Pulse-jet module designs have evolved over
tent with the harsher cleaning mechanism of the years, with numerous design modifications
on-line pulsing at high pulse pressures. providing improved performance over the ge-
Reverse-air systems, as previously described, neric design of Fig. 15. Some of these major dif-
are essentially multi-compartment units with ferences are illustrated in Fig. 16.
off-line cleaning. The carryover of the reverse- In place of a dirty-gas inlet in the module
--
comusmN
Contrd dPower9lant Stack Emissions

knowledge of the process on which equip-


ment is to be installed and a knowledge of the
High-Pressure Cleaning Air limiting factors of the choices available for
application.31
Fabric-filter designs have some established
criteria such as typically acceptable air/cloth
ratios and bag aspect ratios. As noted previ-
ously in the discussion of reverse-air systems,
the gross airlcloth ratio generally acceptable for
the reverse-air system is at or less than 2.0,
with a maximum of 2.5 in the net condition of
two compartments off-line with one of the com-
partments in the cleaning mode. In the design
of a reverse-air unit, or any off-line cleaning
unit, the number of compartments will affect
the value of the net condition as, with fewer
compartments, the removal of one compart-
ment from service has a greater effect than with
a greater number of compartments.
In the design of the reverse-air unit, bag as-
pect ratios are typically limited to 32 to 1,with
a maximum of 35 to 1 under any conditions.
Bag aspect ratio is defined as the ratio of the
Fig. 16 Improved design of pulse-jet fabric filter bag length divided by the bag diameter. Here,
with high side inlet, shown in filtering mode the concern is the ability to clean effectively the
upper section of the bag on this inside-collec-
hopper, gas entry is into the side of the module tor-type unit if the length becomes too long.
casing. An internal baffle and impact plate pro- Most designs have used the more common bag
tect the filter bags from direct impact of the in- lengths of 32 feet in the typical boiler flue-gas
coming gases and dust-particle stream. application.
Advantages of this arrangement include: Similar design criteria have also developed
Better gas and dust distribution to all module for the pulse-jet units in defining acceptable ra-
filter bags. tios or component designs. As an example, typ-
8 A gas-inlet location consistent with a com- ical filter bag lengths range from 12 to 16 feet,
bined manifold design in which the system in- although some designs have been up to 20 feet
let and outlet manifolds are formed by a single in length. The application of felted cloths on
rectangular duct with a diagonal splitter plate pulse-jet is quite typical; however, the use of
forming the two gas paths. woven fiberglass cloth is acceptable especially
Greater hopper storage capacity, which is im- for the higher boiler flue gas operating temper-
portant on high-inlet-loading systems. atures. Filter bag cage materials are commonly
of carbon steel with galvanized coating, but
DESIGN OF EQUIPMENT
other coatings are available, as is alloy con-
Overall system designs involve the selection struction. High-side inlet collectors have ad-
of the cleaning mechanism and type of fabric- vantages with respect to hopper capacity and
filter to be used for a particular service, along hopper reentrainment; however, designs hav-
with the selection of a suitable cloth and cloth ing the gas entering hoppers are acceptable and
finish to be installed in the unit. To make this allow for lower equipment setting heights in
selection, the designer needs a complete overall system design.
COMBUSTION
Control of Power-Plant Stack Emissions

' The selection of the cleaning mechanism de- FABRIC-FILTER PERFORMANCE


sign, the number of compartments needed, the Unlike fabric-filters, most other kmission-
airlcloth ratio necessary, the cloth type and fin- control devices depend upon either pressure
ish, the maximum bag length and a variety of drop or collection surface area to reach the re-
other design considerations, are specific to the quired collection efficiencies. Upsets to pre-
service intended and the user's preference. dicted gas volumes or particulate loadings will
FABRIC-FILTER MATERIALS typically cause these other types of equipment
to have higher emission rates, despite their
Specification of the weave, thread count, maintaining the same fractional efficiency. The
weight, and finish of the cloth for a required fabric does not behave in this fashion, because
filter bag lists only a few of the possible combi- the material collected on the filter bags is the
nations of manufacturing procedures or design filtering medium that captures the incoming
that ultimately will describe the finished filter particulate. Although upset conditions may
bag for a particular application. Fabric specifi- change the flange-to-flange pressure drop, re-
cations include such properties as tensile sulting in an excessively fast build-up of cake,
strength, abrasion resistance, chemical attack these conditions do not materially change the
resistance and limitations of operating temper- final emission. It can be said, as stated in an
ature ('Ibble 11). Tensile strength measures the earlier section, that a fabric-filter represents a
ability of the yarn or fabric to resist breaking constant-emission device.
when in direct tension. Abrasion resistance is The actual performance of a fabric-filter de-
the fabric's ability to withstand externally pends on specific items such as airlcloth ratio,
caused abrasion or that resulting from internal permeability of the fabriclcake (particulate
rubbing of the fabric fibers. Some cloths exhibit bleed-through), the loading and nature of the
excellent resistance while others are damaged particulate (irregular-shaped or spherical), par-
quite easily. Coatings applied to some cloths ticle size distribution (fine versus coarse) and,
not only improve their abrasion resistance, but to some extent, the frequency of the cleaning
also their ch'emical resistance, as in the case of cycle. By careful selection of design compo-
fiberglass cloth, which would self-destruct nents, fabric-filterscan achieve emission levels
without a suitable coating. of higher than 99.9-percent removal of incom-

Table 11. Fabric Material Properties


--

Fiber Property Chemical Resistance Recommended


Operating Temp., OF
Tensile Abrasion
Fiber Strength Resistance Acids Bases Continous Short-time
Cotton Good Average Poor Excellent
Polyethylene Excellent Good Excellent Excellent
Glass Excellent Poor Good Poor
Nylon Excellent Excellent Poor Excellent
Dacron* Excellent Excellent Good Fair
Acrylic* Average Average Very Good Fair
Nomex* Very Good Very Good Fair Very Good
Teflon* Average Below Average Excellent Excellent
'Trademark E.I. DuPont
C-ON
Control of Power-Plant Sfack Emissions

ing particulate, or an outlet loading of less than ation outside the design temperature range
0.005 grain per dry standard cubic foot. (either high or low), or operation in excess of

~ FABRIC-FILTER OPERATING PROBLEMS

A primary concern in the operation of a fab-


the design volumetric flow, or a significant var-
iation in the chemistry of the flue gas being fil-
tered. Any of the above could cause premature
ric-filter is bag life and bag replacement cost. deterioration of the cloth selected for service.
Since the initial cost of the filter bags, exclud-
FLYASH HOPPER PLUGGING
ing installation, can represent 10 percent or
more of the total cost of the equipment, a sig- The reliability and availability of electro-
nificant operating expense can occur if bag life static precipitators and fabric filters are affected
is shorter than expected. And, since typical bag adversely by problems in the dust-receiving
life is 3 to 5 years (depending on the type of hoppers and equipment beneath those hoppers
cleaning mechanism selected and the design for transporting flyash to disposal. A signifi-
parameters used in that selection), this operat- cant portion of the downtime of such dust-col-
ing expense item can represent a significant lecting equipment stems from problems with,
cost over the life of the equipment. Shortened and malfunctions of, ash evacuation systems."
bag life can be caused by various operating and There is a paradox in the design of equip-

.
design problems among w h i c h ' are the ment for removing the collected flyash from the
following: bottom of precipitators and fabric filters and
Bag blinding, usually caused by operating a conveying it away. Suppliers of ash-handling-
fabric-filter for frequent or long periods at or systems design their equipment for "dry and
below the dew point; such operation tends to free-flowing" material at the inlets of the ash-
plug or blind the cloth. Bag blinding results in removal equipment. Yet, dust-collecting equip-
unacceptable unit pressure drop which will'ul- ment can have mud or water flowing out of
timately become fan- or process-limiting and hoppers any time the hopper metal tempera-
require filter-bag replacement. The effect on tures are below the water dew point (loo0 to
the filter cloth is that material builds up in the 130F, depending on fuel type and excess air
passages of the cloth body and restricts the gas in the products of combustion). his condition
passage such that, even after repeated clean- occurs commonly during boiler cold start-up.
ings, the lodged material cannot be removed. when many metal surfaces in the gas stream are
Bag erosion, resulting from high-velocity at ambient temperature.
streams of flyash-laden gases where the gas en- When sub-dew-point conditions occur, the
ters the filter-bag or impacts the cloth in any hygroscopic flyash absorbs the acid or water
way. Proper selection of the airtcloth ratio and produced and may agglomerate and cement
filter-bag length controls the high entry veloc- into large pieces that either cannot pass
ity at the bag inlet inside collectors. Higher air/ through the hopper outlets or are too heavy to
cloth ratios with longer filter bags tend to be conveyed.
increase this velocity in the entrance or "neck"
EFFECT ON COLLECTING EQUIPMENT
area of the bag. Metal thimbles are provided in
this area to minimize abrasive action. Veloci-
ties are generally limited to less than 300 feet Undetected uncorrected hopper plug-
per minute at the bag neck. ging can cause one or more of the following
deleterious effects on precipitators:
Filter-bag deterioration, often caused by a
poor selection of cloth or finish, or by
abnormal operation of the system, resulting in
damage to the cloth or components of construe-
.
' be" Or misaligned collecting surfaces
discharge-electrode burning
distorted or broken discharge-electrode
tion. Abnormal operation would include ope!- frames
CoMBvsnON
Control of Power-Plant Stack Emissions

broken anvil bars Maintenance of Flyash Intakes


broken shaft or drive insulators- It is estimated that some flyash intakes may
shorted high-voltage bus sections open and close nearly a quarter of a million
lowered electrical-power output from bent or times per year. It is completely reasonable to
misaligned collecting- and discharge-electrode expect, under such conditions, that solenoids
components will fail and that valve seats will become worn,
the formation of large, difficult-to-remove resulting in an inflow of air into the hopper.
clinkers by high-temperature electrical fusing With a pressure-pneumatic system, air can be
of the ash overflowing a hopper. forced into the hopper at pressures as high as
With fabric filters, plugging can increase the 100 psig (in a dense-phase system). With vac-
gas velocities as hoppers fill above the inlet uum systems, the motive force for inducing air
level, resulting in the .possiblity of reentrain- into precipitator hoppers or baghouse hoppers
ment of dust. This can result in excessive bag is the suction maintained in the precipitator or
abrasion. With a completely blocked hopper, " baghouse by the boiler induced-draft fans,
the compartment will no longer accept gas which can create a suction of as much as -20
flow, and the other compartments will have to in.WG. in the precipitator or baghouse. With
handle the volume, resulting in increase gas- either a pressure or vacuum system, then, there ,

side pressure drop. is a pressure differential that can result in the


With both precipitators and fabric filters, if a introduction of large quantities of cool air into
plugged hopper cannot be cleared and dis- precipitator hoppers, which can lead to the
charged through the ash system in a normal condensation of moisture in the flue gas.
manner, the ash must be emptied onto the hop- Actual field temperature measurements on
per-room floor or the ground (creating a fire both "hot" and "cold" precipitators have
and safety hazard) and be manually removed.30 shown that even very active hoppers can have
low (essentially ambient) temperatures. One
SOLUTIONS TO THE PROBLEM plausible explanation for such a low internal
The problem can be solved by: temperature is leakage of air into the hoppers
1. Removing the ash as continously as possible through the flyash intake valves located at the
so that it can remain hot and uncompacted, bottom of the hoppers. Very seldom have such
such that the hoppers are not used for stor- valves been considered "maintenance items"
age of the.lnJlgrosopic flyash. that should be inspected and considered for re-
2 . preventing air in-leakage that cools the placement on some time schedule. But it has
- flyash below the acid or water dew point, become apparent in plant after plant that such
by regular inspection and maintenance or valves cannot be expected to last forever and
replacement of flyash intakes. that they are the source of the low-temperature
3. Modifying hopper design for improved fly- conditions occurring in many hoppers.11
ash out-flow.
Heating of Precipitator and Fabric-Filter Outlet Hoppers
4. Enclosing hopper areas and using adequate
insulation thickness to minimize heat losses The ABMAfIGCI Committee stated that the
and cooling of ash-system hardware. heating of hoppers has not been sufficiently
5 . Heating hoppers such that the walls do not emphasized in the purchase, design, and con-
drop in temperature and have condensation struction of precipitator and baghouse dust
form. outlets. They recommended that,. along with a
These suggestions, and other recommenda- redesign of the dust-conveying equipment, im-
tions on the design and sizing of flyash hop- proved hopper heating and insulation has to be
pers, are discussed further below and in the accomplished, all with the purpose of facilitat-
following chapter on ash-handling systems. ing the emptying of the dust outlets.
COMBnsnON
Contrd of Power-Plant Stack Emissions
-
The principal variables in the application of pers to the top, by chimney action. This
hopper heating are: situation is aggravated by severe local weather
conditions and exposed hoppers facing a pre-
external (ambient) design temperature vailing wind, and can result in localized con-
internal design temperature densation and wetting of collected ash.11
presence of an inteinal ash layer Normally, only the lower one-third or one-
the extent and placement of heating elements half of a hopper is heated to minimize costs and
to avoid the problem of heating elements ob-
the design electrical-heat density structing access to the equipment; also, most
the thickness of insulation outside the heat- plugging is expected to occur in the constricted
ing equipment outlet region. But the hopper plate does not
readily conduct heat to other parts of the hop-
Design operating temperature for hopper- per, especially when the interior gas tempera-
heating equipment for boilers firing low- to me- tures are low. If such areas cannot be
dium-sulfur coals should be a minimum of heat-traced, they must be completely insu-
270F, based on an ash layer inside the hopper. lated, including doors, poke holes, strike pads,
This is 10 to 15 degrees above the normally ex- and other protrusions.
pected acid dew point. For units firing high- Because heater vendors may interpret heat-
sulfur oils, the hopper plate should be kept ing needs very differently, precise heater speci-
above 350F. The heating equipment must be fications or hopper heat loads in kilowatts must
capable of maintaining such temperatures un- be made directly to the vendor, both to ensure
der the worst expected ambient conditions of adequate heating and to prevent the possibility
temperature and wind velocity (for 97 to 98 of damage from overheating. Heat loads as high
percent of the time) and for the lowest antici- as 32 kW per hopper have been specified on
pated interior gas temperature. some large coal-fired-boiler precipitators. This
Test reports of temperature measurements in is two to three times as much as in many exist-
operating precipitator hoppers indicate that ing installations.
gas or air temperatures as low as 90F some- In most current installations, if the flue-gas
times occur inside the hoppers, with the pre- temperature falls below the acid dew point, or
cipitator and boiler operating at essentially full if air or gas in the hopper falls below the water
load. Under such conditions, most of the heat dew point, there is little that can be done by
loss from the hopper plate is not to the outside hopper heaters to prevent condensation inside
atmosphere, but rather to.the inside of the hop- either precipitator or fabric-filter hoppers. This
per.30 The heat-transfer and the mass-transfer is because their proper function-is to heat the
situation in such a precipitator can in no way steel wall of the hopper and not the air or gas
result in the occurrence of such low tempera- inside."
tures by a normal heat loss/transfer mech-
anism. The greatest probability is that the low
temperatures in such hoppers result from the
CONTROL OF GASEOUS
inleakage of relatively cool air from the pneu- EMISSIONS
matic transport system serving the hoppers. Sulfur in coal exists in two forms: organic
Even when bulk gas temperatures in collect- and inorganic. The inorganic compound py-
ing equipment are above the acid dew-point rite, FeS,, is present as discrete particles within
(240 to 350 F), hopper skin temperatures at the the fuel, and typically accounts for 20 to 50
critical throat can be very loy, due to the heat- percent of the total sulfur. Fig. 17 is illustrative
sink effect of the ash-system hardware (strike of the variety of pyritic sulfur occurring in just
pads, poke holes and vibrators) and the convec- one small area of the United States. The coals
tive transfer of heat from the bottom of the hop- forming the basis for the plot are all from the
COMBUSIlON
Control of Pw~er-Plant
Stack Emissions

state of Kentucky, which has two separate ba- In addition to SO,, lesser quantities of sulfur
sins of formation. Pyrite as a percentage of total trioxide, SO3,are formed during combustion.
sulfur is from less than 10 to over 55 percent for
the low-sulfur Appalachian basin coal, and
from about 25 to 70 percent for the higher sul- SO, + '12 0, -c SO,
fur Illinois basin fuel. The milling and classify- (4)
ing operations associated with pulverized-fuel
steam generators using pulverizers similar to
the C-E Bowl mill separate a substantial por- Typically, the ratio of S02/S03in combus-
tion of the pyritic sulfur from the coal. (See tion gases ranges from 20:l to 80:l. The chemi-
Chapter 11.) An additional amount of inorganic cal reactions that form sulfur dioxide and
sulfur is retained in the bottom ash and the fly- trioxide are substantially more complex than
ash leaving the boiler in solid form. the overall reactions represented by Eqs. 3 and 4.
Explicit emission standards for the control of
FORMATION OF SULFUR OXIDES
SO3 do not exist. But as SO, is highly reactive
contained in the molecular structure of the and extremely hygroscopic compared to SO,, it
coal, organic sulfur is oxidized during the com- is capable of readily combining with water to
bustion process and emitted from the furnace form sulfuric-acid aerosol. The reaction is en-
as gaseous oxides of sulfur. hanced by the presence of fine particles which
The principal oxidizing reaction leads to the serve as condensation nuclei; the resulting
formation of sulfur dioxide. aerosol is a principal constitutent of visible
stack plumes. Thus, opacity and particulate-
S + 0, + SO, emission regulations are an indirect method of
restricting SO3emissions.

0.8-

0.7 -
0.6 - 0 '
..
0
.
5 5 0.5
-
. .. ... .go

......
5 =
L
0

'.-2 2 0.4 -
r B
-0

m0

h o.s -
0.2 -
Q'o

o o
0
0 0
0

. o Eastern Kentucky
(Appalachian Basin)
o
o0
0
. Western Kentucky
(Illinois Basin)
0O
O.l
- g
0' I I I I I
0 1 2 3 4 5
O/O Sulfur in Dry Coal

Fig. 17 Pyrite content of Kentucky coal


C O ~ O N
Contd of Fower-PIant Sack Emissions
-
Studies show flue-gas desulfurization sys- alkaline Thames River water for scrubbing
tems intended principally for SO, control are power-plant flue gas until the visibility of the
moderately effective in curtailing SO3 emis- stack plume caused abandonment of the pro-
sions. Tests indicate that a venturi/spray tower- cess early in World War 11. The technology re-
scrubber removes approximately 60h of the mained dormant until the mid-1960's when it
SO, in flue gas, with the removal efficiency es- became active primarily in the United States
sentially independent of the SO3concentration and Japan. Since then, over 50 FGD processes
or scrubber operating variables.32 have been developed, differing in the chemical
reagents and the resultant end products. In the
CONTROL OF SO, EMISSIONS
following section, we will describe some of the
Historically, gaseous sulfur-dioxide emis- more prominent, with particular emphasis on
sions have been controlled by either dispersion those processes which are commercially signif-
or reduction. Dispersion of SO2and other pol- icant. References 32, 34, 35, and 36 provide a
lutants through tall stacks is the oldest form of comprehensive overview through the mid-
control. Under favorable meteorological condi- 1980's.
tions tall stacks can effectively limit ground- In the flue-gas scrubbing process, water
level SO, concentration to local ambient evaporates from the scrubbing liquid as the
air-quality standards. Thermal inversions or flue-gas is cooled to the adiabatic saturation
comparable short-term meteorological condi- temperature. Under equilibrium conditions, a
tions can impair the effectiveness of dispersion quantity of water must be added to the system
as a control method. A further and more critical to make up for the water loss.
concern over control by dispersion is the accu- In a recirculation type wet-scrubbing system
mulating scientific evidence that oxides of sul- where scrubbing liquid is not bled from the
fur and nitrogen are the principal precursors to system, the salts in the incoming make-up
' acid precipitation.33 water gradually concentrate. In any scrubbing
Reduction of sulfur emissions has been system involving solids present in the flue-gas
achieved through one or a combination of the stream as flyash or as solids from the sorption
following: of sulfur dioxide, a stream must he bled off to
switching to lower-sulfur fuels remove the solids and similarly prevent their
use of fuel desulfurization methods buildup to excessively high values in the sys-
use of flue-gas desulfurization systems tem. The specific concentration of various
Switching to lower-sulfur fuels is not possi- chemicals in the scrubbing liquid in any given
ble for many large fossil-fired steam-generating system depends on the sulfur in the coal, the
plants. Additionally, current air pollution flyash in the flue gas entering the scrubber, and
regulations for new power plants require a per- the type of additive.
centage reduction in SO2 emissions regardless The evaporation that occurs in the wet flue-
of the fuel sulfur content. gas scrubbing process, then, results in essen-
Fuel desulfurization processes range from tially pure water being discharged to
conventional coal washing to coal liquefaction atmosphere, and simultaneously, a concentra-
and gasification. Coal washing is effective in tion of solids in the bleed stream leaving the
reducing the pyritic sulfur in the coal. It cannot scrubbing system. Of these solids, the sulfates,
remove the organic sulfur from the coal matrix, sulfites, and chlorides are of the greatest
and as such it is limited to sulfur reduction of significance.
-
less than 50 percent. One approach in categorizing FGD processes
is to differentiate between nom7egenerable, or
FLUE-GAS DESULFURIZATIONSYSTEMS "throwaway ", and regenerable, or recovery -
Flue-gas desulfurization (FGD)began in Eng- type, processes. Throwaway systems produce
land in 1935; the Battersea process used the waste products of various sulfur compounds
COMBUSIlON
Control of Power-Plant Stack GnIssions

that must be stored in ponds or treated for use was used to remove the flyash, limestone, and
as landfill. Regenerable systems recover the SO, from the flue gas. Several systems-were
SO2in some commercially useful form such as placed into operation between 1968 and 1970,
elemental sulfur or sulfuric acid. A further dif- but persistent difficultieswith scaling, poor ad-
ferentiation can be made between wet pro- ditive utilization, and plugging of boiler con-
cesses and dry processes: wet processes vection surfaces prompted C-E to revert to the
saturate the flue gas with water vapor and dry older Howden tail-end process.
processes do not. In a typical limellimestone wet FGD system
(Fig. 18), boiler flue gas enters the scrubber
NON-REGENERABLE FGD PROCESSES (spray tower) and contacts the absorbent slurry
In the U.S., the overwhelming majority of while sulfur dioxide and lesser amounts of o G -
commercial FGD systems are of the throwaway gen are simultaneously absorbed. The spent ab-
type. Included in this category are the lime or sorbent returns to the reaction tank, or
limestone wet scrubbing, the double or dual al- scrubber-effluent hold tank, where the dis-
kali, and the lime dry-scrubbing systems.
'' solved sulfur compounds are precipitated as
calcium salts. Fresh limestone or lime slurry is
LimelLimestone Wet Scrubbing added to regenerate the spent absorbent.
The size of the reacti'on tank provides suffi-
Lime or limestone scrubbing is the oldest cient time for precipitation of sulfur com-
and most common method of flue-gas desulfur- pounds and the dissolution of additive. The
ization. Thb first successful closed-loop lime1 rate of additive feed is pH-controlled. From the
limestone process is credited to the English reaction tank, the regenerated absorbent slurry
firm of J. Howden and Company. During 1931- is recycled to the absorber. The slurry typically
1933 pilot-plant tests were conducted in which contains from 5 to 15 percent suspended solids
the scdbber effluent was recycled to the ab- consisting of fresh additive, absorption reac-
sorber; initially, scale formed in the absorber.37 tion products, and lesser amounts of flyash. To
The critical breakthrough in system chemistry regulate the accumulation of solids, a bleed
came in 1933 when the problem was identified stream from the reaction tank is routed to the
as one of excessive gypsum (CaSO;ZH,O) su- solidlliquid separation equipment.
persaturation in the scrubber. The solution was Typically, the bleed is routed to a gravity
to add a crystallization tank and increase the thickener where the suspended solids settle to
liquid-to-gas (LIG) ratio. Adding a crystalliza- the bottom and the clear liquid is drawn off the
tion tank operating at high solids concentration top and returned to the scrubber loop. The
allows calcium-sulfur compounds to precipi- thickener underflow containing 25 to 45 per-
tate outside the scrubber. Becauseof precipita- cent solids can be pumped to a pond or may be
tion reactions, the absorbent recycled to the further dewatered through vacuum filtration.
scrubber has a lower concentration of scale- Alternative liquid-solid separation equipment,
forming gypsum. A high LIG ratio minimizes such as wet cyclones and centrifuges, may be
the increase in supersaturation across the used to dewater the bleed stream. The filtrate is
scrubber and thereby further diminishes the returned to the scrubber loop. Alternately, the
potential for scale formation. bleed from the reaction tank can be pumped di-
In the mid-1960's, Combustion Engineering rectly to a settling pond where solids accumu-
developed and marketed the limestone-injec- late and clear liquid is recycled to the scrubber.
tion scrubbing process. In this variation, pul- Make-up water is added to the system to re-
verized limestone was injected into the furnace place water evaporated by the hot flue gas and
simultaneously with the coal. The resulting water entrained in the waste stream. The water
calcined limestone (CaO) was entrained in the is added as mist-eliminator wash, and as the
flue gas along with flyash. A water scrubber additive slurrying medium.
CoMamnON
Control of Pomr-flant S t a k Emissions

I
I

--- Gas Stream


-Liquid or Slurry Stream

Fig. 18 Process flow diagram for limellimestonewet scrubbing

Double Alkali Systems cause they offered significant advantages over


Like lime/limestone processes, in double al- limellimestone slurry processes. First, there
kali (or dual alkali) processes, lime or lime- are no suspended solids in the absorbent to
stone is consumed and a calcium sulfite/sulfate contribute to scaling and plugging of internal
wet solid is produced as waste. They differ scrubber components. Second, because of a
from the lime/limestone in that SO, is absorbed high concentration of dissolved alkali species,
and waste-products are formed in separate there is minimal resistance to liquid-phase
components. The absorption and waste genera- mass transfer. The practical implication of
tion are separated by using an intermediate sol- these factors is excellent SO, removal efficiency
uble alkali such as Na2C03,NaOH, or Na,S03. achieved with a simple scrubber at lower
The separation serves two objectives. First, it liquid-to-gas ratios.
permits scrubbing the flue gas with a clear so- Fig. 19 shows a typical double-alkali pro-
lution, allowing the rate of SO, absorption to cess. Clear alkali solution is circulated through
proceed independently of lime or limestone the scrubber where SO, absorption and some
dissolution rate. Second, it permits better con- oxidation take place. The absorbed SO2 reacts
trol of the calcium-sulfur precipitation reac- with sulfite to form bisulfite:
tions in equipment specifically designed for
this function. In theory, this improves the use Na2S0, + SO, + H20 -+ ZNaI-ISO,
of lime or limestone. (5)
Double alkali FGD processes developed be-
COMBUSPION
Control of Power-Plant Stack Emissions

r--- Stack
- Scrubber Feed
Scrubbet

Make-Up NazCO3

i2i
Bleed
Flyash-Free ---
Flue Gas Thickener
Wash Tank
Holding

Waste Calcium Salts

Filter
. -
Fig. 19 Simplified process diagram for double alkali system

The pH of the absorbent is typically between versible oxidation of sulfite to sulfate.


6 and 8.5. !$rubber effluent, which contains a
lower ratio of sulfite to bisulfite than the scrub- Na,S03 + 1/20, -+ Na2S04
ber feed, is collected in the absorber sump. A (8)
bleed stream from the sump is pumped to the
regeneration system where it is treated with
When active sodium sulfite is converted to
lime or limestone. The absorbed SO, is precipi-
inactive sulfate, the capacity to absorb addi-
tated as calcium solids as follows:
tional SO, is diminished. To restore dissolved
scrubbing capacity, the inactive sulfate must be
removed from the system while the sodium re-
mains in solution. A direct purge of sodium
sulfate from the system is unacceptable be-
cause it contributes to surface and ground
water contamination. Additionally, the cost of
replacing the lost sodium is further incentive
against direct purge.
The methods for removing sulfate depend on
The bisulfite is neutralized and active sulfite the concentration of sulfite in the system. If the
is regenerated. The sulfite-rich clear solution is sulfite concentration is low, the system is said
separated from the precipitates in conventional to operate in the dilute mode. In a dilute dou-
solidlliquid separation equipment such as ble alkali system, sulfate may be removed ac-
thickeners and vacuum filters. Waste calcium cording to the following reaction:
and sulfur compounds are disposed of and sul-
fite solution is returned to the scrubber loop.
Sodium lost as a result of entrainment in the
waste solids is replaced with fresh sodium-
carbonate addition.
Technically, the most serious difficulty with In a concentrated double alkali system with
double alkali processes arises from the irre- a high sulfite concentration, this reaction will
--
CO&mlsTxoN-
Contrd of Rwer-Pbnt Stack EmirrPions

not proceed appreciably and other techniques purge or bleed stream in order to prevent the
must be used to regenerate the inactive sulfate. accumulation of excessive reaction products.
In Japan, sulfuric acid is added in a separate re- The bleed stream must be treated to separate
actor to force the following reaction: the water from the solids, to prepare the solids
for their final disposition, and to return the
water to the scrubbing process.
In the late 1960's, researchers at Rockwell In-
ternational conceived spray dry-scrubbing as a
simple alternative to the bleed stream with its
This mode of operation is often referred to as required treatment steps.
low-pH crystallization because the reactor op- Initially, the. spray dry-scrubbing process
erates at a pH of 2 to 3. Low-pH crystallization was proposed as an enhancement to dry injec-
often :an be combined with simultaneous tion of nahcolite or trona ahead of a fabric
forced oxidation to yield a marketable gypsum. filter. As a result, the original absorbents were
Double alkali desulfurization systems in solutions of soda ash and its related com-
large plants are limited because of the cost pounds. It was soon discovered that lime slurry
of sodium reagents, requirements for large also produced very good results when used as a
solidlliquid separation equipment, and reagent in the spray dryer. The first commer-
leaching problems associated w i t h the cial utility system, the 410-MW Coyote Station
disposal of wastes containing entrained near Beulah, North Dakota, used soda-ash solu-
sodium compounds. tion. Because lime slurry is more economical
than soda ash, subsequent installations' have
Spray Dry-Scrubbing
used lime slurry for the alkaline reagent.
A principal characteristic of wet limellime- Fig. 20 illustrates the spray dry-scrubbing
stone scrubbing is the requirement for a wet process in which flue gas from the air preheater

Particulate-
Flue Gas from Collection
Air Preheater

u Lime Silo
I
L-L-L-A
I I I

I-~I-,
Slurry

Water
Recycle
Solids Silo.
1

Make-Up Water

-- - --- Gas
Liquid/Slurry
--- Solids
Fig. 20 Flow schematic of spray dry-scrubbing flue-gas cleaning system
COb4EmnON
Control of Power-Plant Stack Emisdons

is passed into a spray dryer. Spray drying is a which dre always present in the pebble lime.
unit operation used for more than eighty years Both pug-mill and detention slakers use a
in the food and chemical manufacturing indus- screen or settling unit to remove grit or rock-
tries. It replaces the spray tower in order to si- like impurities from the milk of lime. Pug-mill
multaneously achieve both absorption of the slakers, which allow the highest ratios of peb-
sulfur dioxide and thorough drying of the reac- ble-lime to water, can most reliably achieve the
tion product. The amount of reactant slurry in- high slaking temperatures so important for the
troduced to the spray-dryerlabsorber (SDIA) is spray dry-scrubbing process.
controlled to insure that the reaction products The reagent slurry is prepared by mixing the
leaving the SDIA will be completely dry. No milk of lime with additional process water as
crystallization tank is required: crystallization required to achieve a suitable degree of dryness
of the reaction products occurs quickly in the of the solid effluent leaving the spray dryer.
droplets as they dry and pass through the SDIA. Reactant solids from the particulate collecting
The crystallized reaction products, together device may also be mixed into the reagent
with any entrained flyash from the boiler, slurry. The practice of employing recycled
are collected in a fabric filter or electrostatic solids in the reagent slurry tends to reduce the
precipitator. It is a typical, but not necessary, amount of fresh lime required for a given sul-
practice to drop-out some reaction products fur-dioxide removal. Most often, the recycled
and flyash in a hopper at the bottom of the SDIA. solids are first pre-mixed in a separate slurry
The alkaline reactant for the spray-drying tank and pumped to the reagent preparation
process is prepared by slaking pebble lime tank. The reagent preparation tank may be lo-
to produce a slurry of calcium hydroxide as cated at ground level with pumps for supply-
follows: ing the slurry to the atomizers or at a high
elevation above the atomizers to facilitate grav-
ity feed. Some systems do not use a reagent
CaO + H,O + Ca(OH), + Heat preparation tank: the milk of lime, recycle
(11) slurry, and makeup water are mixed in the line
supplying the atomizing device or directly in
The slaking reaction must take place at temper- the device itself.
atures above 170F, which cause the reaction to The most important unit operation in the
occur quickly. The pebbles of CaO "explode", spray dry-scrubbing system is atomization. Ei-
forming a very finely divided milk-of-lime ther air-assisted nozzles or rotary atomizers are
suspension with high particle surface area. commonly used. There are two major types of
Because absorption, dissolution, and recrystal- air-assisted nozzles, differentiated by where
lization processes must all occur very quickly the slurry is mixed with the atomizing air-
in the spray-dryerlabsorber, the lime-slurry inside or external to the atomizer body.
particle surface area significantly affects how Internal-mix nozzles generally are more en-
much reagent is required for a given sulfur-di- ergy-efficient, although more expensive to fab-
oxide removal. The requirement for relatively ricate, than the external-mix types. Rotary
fast dissolution of the reagent solids precludes atomizers are comprised basically of a high-
the use of less costly pulverized limestone. speed rotating atomizer wheel coupled to a
High slaking temperatures are achieved by drive device. In order to protect the load-bear-
maintaining the highest practical ratio of peb- ing components of the drive device, the cou-
ble lime to water in the slaker reactor. The reac- pling is usually designed to absorb vibrations
tor is usually one of three types: a paste mixer induced by imbalanced operation. Generally,
or pug-mill, a detention unit, or a ball mill. the drive device is a two- or four-pole, three-
The ball mill provides for slaking while simul- phase electric motor with a speed-increasing
taneously reducing the size of impurities gearbox, although in some systems a high-
COMBusllON
Coniro/of Power-Plant Stack Emissions

speed electric drive is used without a gearbox. chemical plants generally unattractive to elec-
Rotary atomizers offer some significant ad- tric-power producers.
vantages over air-assisted nozzles for large in- Limited application of this technology
dustrial and utility systems. They are results from several factors. First, regenerable
more energy efficient for achieving a uni- processes are energy-intensive as reducing sul-
formly fine degree of atomization fur compounds to elemental sulfur requires
more capable of handling large slurry flow thermal energy. Second, the decomposition
rates while at the same time producing a uni- processes require substantial amounts of reduc-
form spray pattern ing gases including hydrogen sulfide, carbon
more suitable for atomizing highly abrasive monoxide, or hydrogen derived from natural
slurries, especially those which contain recy- gas or other hydrocarbon feed stock.
cled solids. Aside from the availability problem, there is
Almost as important as the quality of atomi- a reluctance to handle large quantities of poten-
zation is the mechanism for contacting the tially toxic reductants like hydrogen sulfide in
atomized slurry and flue gas in the spray-dryer1 the power plant. Also, regeneration processes
absorber. Commercial systems can have as are difficult to justify unless it is impractical to
many as three spray machines and inlets in one dispose of large quantities of wastes, or there is
SD/A. Using multiple spray machines reduces a secure market for the sulfur. Examples of
the individual power requirements for each some regenerable FGD systems follow; others
machine without appreciably affecting SDIA were described in the Third Edition of this text.
performance.
Magnesium Oxide
REGENERABLE (RECOVERY) PROCESSES
The magnesium-oxide FGD process, a wet-
Although regenerable FGD systems can pro- slurry regenerable/recovery system, is shown
duce marketable sulfur or sulfuric-acid end as a simplified flow diagram in Fig. 21. As with
products instead of essentially valueless all regenerable processes, the flue gas must
wastes, such systems are more expensive and have the particulate matter removed to prevent
complex. They result in highly sophisticated buildup of inert solids and contamination of

r------ Stack
C

Scrubber SOr

Flyash-Free -
Flue Gas
- Bleed
-
Centrifuge Dryer
f 1500"F
-Coke
t Liquor
MgO t
Mg(OW2
Slurry Slurry Tank
Sulfur or Acid Plant
Recovered Sulfur - I
Fig. 21 Simplified process diagram for magnesium-oxide recovery system
COMBUSPION
Control of Power-Plant Stack Emissions

the'final product. Ash-free flue gas is scrubbed Power Company's Dickerson station and Phila-
with a slurry of magnesium oxide and water in delphia Electric Company's Eddystone-station.
a suitable absorber. Depending upon specific
Sodium Sulfite -
process conditions, sulfur dioxide reacts with * .

magnesium oxide, magnesium sulfite, or mag- The sodium-sulfite process (Fig. 22) is a
nesium hydroxide to yield soluble magnesium regenerative FGD process which combines
bisulfite. absorption of soluble SO, with thermal
regeneration of sodium sulfite to produce
MgO + 2S02 + HZ0 -+ Mg(HS03)z either elemental sulfur or sulfuric acid.38 A
sodium-sulfite solution absorbs SO, from the
(12) flue gas, thereby forming sodium bisulfite.

A bleed stream is sent to the evaporatorlcrys-


tallizer where sodium bisulfite is thermally
decomposed to form solid sodium sulfite and
gaseous SO,.
In the prodess, some oxygen is also absorbed
into the slurry, an action that forms magnesium
sulfate.
The magnesium bisulfite is neutralized with
magnesium oxide to produce a magnesium bi-
The sulfur dioxide is stripped with steam to
sulfite precipitate.
yield a concentrated product stream containing
approximately 90 percent SO, and 10 percent
Mg(HSO,), + MgO + 11H,O -+ 2MgS03' 6H20 water. This stream is further processed to re-
(15) cover sulfuric acid or elemental sulfur. Sodium
sulfite crystals are dissolved in water and recy-
The magnesium-sulfite/sulfate crystals are cled to the absorber. Sodium sulfate formed as
withdrawn in a bleed stream from the absorber a result of oxidation does not decompose in the
loop and sent to a centrifuge for dewatering. evaporator and must be purged.
The product from the centrifuge is thermally The sodium-sulfite process has been applied
dried and the liquor is recycled to the scrubber. since 1971 in Japan on several oil-fired indus-
Dried magnesium-sulfite/sulfate crystals are trial and utility boilers. The only sodium sul-
calcined, usually under a reducing atmosphere fite processes prior to 1979 in the United States
at approximately 1500F, to regenerate magne- controlled SO, emissions from Claus sulfur and
sium oxide and produce a gas stream concen- sulfuric-acid plants. Early in 1980 three sys-
trated in sulfur dioxide. The calciner exit gas is tems were installed on coal-fired boilers, all
treated for particulate removal and then used as designed to produce elemental sulfur for ulti-
the feed stream to produce sulfuric acid or mate use in sulfuric-acid manufacture.
elemental sulfur. The magnesium oxide is Activated-Carbon Absorption
recycled to the scrubber. Commercial magne-
sium-oxide FGD systems were built at Boston Activated-carbon processes are dry regenera-
Edison's Mystic station, for an oil-fired boiler, ble FGD processes in which SO, is absorbed on
and for coal-fired units at Potomac Electric activated-carbon granules in either fixed or flu-
C O m ~ O N
Cantrol of Power-PIant Stack Emi&ons

r----- Stack Cooling Water


I \

Surge
1 Purge Steam
I
Flyash Purge
t
SO2 to
Sulfur
"Ifate Treatment Plant

Fig. 22 Simplified process diagram for the sodium-sulfite system

idized-bed reactors. Sulfur dioxide is catalyti- The reactor off-gas, consisting of sulfur vapor
cally oxidized to SO, which then under- and hydrogen sulfide, is cooled to condense
goes hydrolysis and forms sulfuric acid in the out the sulfur.
carbon pores. The ability of the process to consistently re-
move SO, with acceptable carbon degradation
Activated has to be demonstrated at the prototype and
SOz + M02+ H a arbo on H2S0, (Sorbed) commercial ~cale.3~
(la) WET LIMEILIMESTONE FGD-SYSTEMS

~h~ carbon, loaded with sulfuric acid, In the U.S., the ~nvironmentalProtection
bines with hydrogen sulfide in a separate reac- Agency (EPA) regulations require substantial
tor to yield sulfur. reductions in gaseous ' and particulate emis-
- sions from power-producing facilities, depend-
ing on plant size, age, and the fuel being
H2S04+ 3H$ -,4 H P +4s (191
. . burned. To meet such standards, and depend-
ing on additional local regulations and other
site-specific conditions, utilities and large in-
A third the absorbed dustrial boiler operaters have to consider all of
upon the carbon by reaction with hydrogen at the available flue-gas cleaning processes.
1000F. The viable options for particulate collection
consist of electrostatic precipitation, fabric fil-
Activated
4 s + 3H2 Carbon * 3 H S + S (Product) (20) tration, and high-energy wet scrubbing. The
preferred options for SO2 removal are lime1
C O ~ O N
Control of Power-Plant Stack Emisblono

limestone wet scrubbing and lime dry scrub- is less sensitive to such changes. Thus, fabric
bing. Integrated flue-gas cleaning systems filters give the power generator the option of
consist of various combinations of particulate switching fuels without modifying the partic-
and SO, removal systems, as shown in Fig. 3. ulate collection system. The major disadvan-
tages of fabric filters include gas pressure drops
WET PROCESS VARIATIONS of 4 to 6" WG and more maintenance compared
Limellimestone wet-scrubbing systems for with precipitators.
pulverized-fuel boilers fall into three catego-
Two-Stage Scrubbing
ries, as described in the following sections.
Two-stage wet scrubbing, as shown in Fig.
ESPISingle-Stage Wet Scrubbing
23, can remove not only gaseous emissions but
The most common flue-gas cleaning system particulates as well. To collect flyash by wet
uses an electrostatic 'precipitator (ESP) fol- scrubbing, a liquid is atomized to fine droplets
lowed by a lime/limestone wet SO, scrubber. which are then dispersed and mixed thor-
After the flue gas has been treated in the pre- oughly with the flue gas. Atomization takes
cipitator, it passes through the induced fans place by accelerating the gas through a venturi
and enters the SO, scrubber. If the required SO, and using the momentum of the gas to shear
removal efficiency is less than 85 percent, a the liquid into fine droplets. The initial large
fraction of the flue gas can be treated while by- velocity differential between the liquid drop-
passing the rest to mix with and reheat the sat- lets and the flyash particles provides ideal con-
urated flue 'gas leaving the scrubber. ditions for collecting flyash by impaction and
For higher sulfur fuels requiring SO, removal interception. Simultaneously with flyash col-
efficiencies of 90 percent or greater, the entire lection, some of the SO, is absorbed in the
flue gas stream must be treated. Upon leaving venturi scrubber. A second-stage absorber
the SO, absorption section, the flue gas is accomplishes final SO, removal.
passed through entrainment separators to re- Two-stage wet scrubbing is particularly at-
move any slurry droplets mixed with the gas. tractive when collecting flyash containing ap-
The saturated flue gas may be reheated ap- preciable amounts of calcium, magnesium, and
proximately 25 to 50F above the water dew sodium. To a certain degree, the alkali content
point before it is vented to the stack. of the flyash reacts with the absorbed SO, and
reduces lime or limestone consumption.
BaghouselSingle-StageWet Scrubbing
The primary advantage of particulate wet
For certain types of fuels, the size of an elec- scrubbers is low initial cost compared to elec-
trostatic precipitator to meet current partic- trostatic precipitators and fabric filters. A sig-
ulate emission standards becomes so large that nificant disadvantage is the high gas-side
fabric filters are a technical and economic alter- pressure drop. For very low emission levels,
native. The principal advantages of fabric fil- pressure drops in excess of 20" WG are re-
ters (baghouses) are quired for most applications.
very high removal efficiency .
ability to collect fine particles WET-SCRUBBER DESIGN FACTORS
insensitivity of collection efficiency to fuel Limellimestone-additive scrubber processes
characteristics commonly use spray towers to absorb SO, from
This latter advantage is significant because, the flue gases. whether operated in the coun-
contrary to the performance of a fabric filter, tercurrent, co-current, or cross-current modes,
electrostatic precipitator performance is af- such towers typically have few internals and
fected by the characteristics of the flue gas and very low liquid-residence time.
flyash particles while fabric filter performance The scrubbers designed by the British in the
-
COMBmON .-
Conbd of P o w e r P h t Stack Emissions

Gas
to Stack

Mist Eliminator

Venturi/Quencher

- Make-Up Water

Fig. 23 Two-stage scrubbing flow schematic

1930's reflected the belief that high mass-trans- maximum turndown ratio
fer rates were required to absorb slightly solu- high allowable gas velocities
ble SO, gases. Thus, towers were designed low gas-side pressure drop
with internals to promote liquid hold-up. In
the 1960's, U.S. firms, acting on the British ex- low plugging potential
perience, adopted packed towers for simulta- simple mechanical construction
neous SO, and particulate removal. The most common spray-tower design is the
More restrictive effluent-discharge regula- vertical countercurrent type in which the gas
tions together with more effluent dewatering of enters the bottom of the absorber and flows up-
waste solids made it necessary to operate FGD ward through the absorptionlspray zone.
systems at higher concentrations of dissolved In the typical absorber, multiple stages of
solids. In general, as the level of dissolved atomizing nozzles distribute absorbent slurry
solids in limellimestone slurries increases, the into the gas. Designs usually have an optional
potential for scaling also increases. Scale for- spare- stage. Depending upon the particular
mation in packed scrubbers can shut down a FGDS vendor, the nozzles are either hollow or
desulfurization system due to excessive gas- full-cone spray type with capacities that range
side pressure drop. The consequences of scale from approximately 250 to 1000 U.S. gallons
formation in spray-tower absorbers are consid- per minute in large installations. Nozzles are
erably less severe. designed to produce fine droplets over a large
. . area at minimum spray-water pressure.
Spray-Tower Design
The sprayed slurry falls by gravity to the bot-
Among the advantages of spray towers for tom of the absorber and is drained to a reaction
limellimestone FGD processes are tank. In the spray tower, above the spray
COMBUSTION
C o n W of Power-Plant Stack Emissions

stages, entrainment separators (mist elirnina- For any different element of spray-tower
tors) separate suspended slurry droplets from height dz, Eqs. 21 and 22 may be equated to
the gas stream. Zig-zag baffles are the most give
common type of entrainment separators be-
cause they offer low pressure drop,-simple con-
struction, and good cleanability.
GSdy = Kg (a) (S) dz (y - y*)
(23)
Mass-Transfer Concepts
where
Sulfur dioxide absorption in countercurrent dy =differential change in SO, gas-phase
spray towers involves mass transfer from the concentration, mole fraction
gas phase to the liquid phase. The design of dz = differential increment of tower height, ft
spray towers and other FGD wet absorbers re- a =available interfacial area per unit vol-
quires an understanding of mass-transfer.40 ume of spray tower, ft2/ft3
The rate of mass transfer, N, is determined by Rearrangement of equation .23
the mass-transfer driving force, y - y*, and the - gives
resistance to mass transfer, l/K$. Symboli-
cally, the relationship may be expressed as

where
N = (y - y*) + (lIKgA) = K,A (y - y*) Kga = overall gas-phase mass-transfer coeffi-
(21) cient, molhr-ft3
Eq. 24 may be expressed in integral form as
where
N =rate of mass transfer across interface,
m o l h ..
y =concentration of SO, in gas phase, mole
fraction
y* =concentration of SO, in gas phase in
equilibrium with the existing liquid- where
phase composition, mole fraction H, =height of gas-phase transfer unit, ft
Kg = gas-phase mass-transfer coefficient, N, =number of gas-phase transfer units
mol/hr-ft2 Z =total height of tower, ft
A =total interfacial area available for mass
transfer, ft" The overall mass-transfer coefficient, K,a,
may be evaluated by rearranging Eq. 25 to:
From material-balance considerations, the
rate of mass transfer may also be expressed by

and then graphically solving the integral for


where the appropriate limits of y.
G =molar gas flux, molthr-ft2 For spray-tower design it is essential to
S = cross-sectional area of tower, ff know the relationship between K,a and design
Ay =change i n SO, concentration across variables such as gas velocity, tower height,
tower, mole fraction number of stages, stage spacing, nozzle charac-
.-
COb0USTION
Contrd of Power-Plant Stack Emissions

teristics, and LIG. This information usually lished. One such correlation developed by
must be developed through pilot- a n d Combustion Engineering" is
prototype-plant experiments. Fig. 24 illustrates
how such experiments help. Cd AP
The operating line, AC is based on test data. Kga [
=K~(Yin)a(z)b([UG)c T I
(Lra)p(Mg9C1)'
where points C and A are the gas-phase inlet . .
(271
and outlet SO, concentrations respectively. The
slope of the line equals the liquid-to-gai ratio, where
L/G. The gas-liquid equilibrium line, BD, ex-
presses the equilibrium relations between SO2 Kga - = overall mass-transfer coeffi-
cient, molhr-ft3
in the liquid and gas phases and is a function of
y tn =actual SO, concentration at
variables such as temperature and liquid inlet, mole fraction
composition. Z = spray tower height, ft
As mentioned, K,a may be obtained by L/G = liquid-to-gas ratio, gpm/1000
graphically determining the integral in Eq. 25 cfm (actual) at the outlet
to obtain N,. Although details of this integra- =coefficient of discharge of the
tion procedure are not included here, under- Cd
spray nozzle
stand that if the operating line AC and AP =pressure drop of liquid across
equilibrium line BD are close (due to changes the nozzle, psi
in position of either the operating line or equi- D = Sauter mean droplet diameter
librium line), the number of transfer units (N,) of the spray liquid, pm
will increase and make the removal process
vg = superficial gas velocity, ft/sec
more difficult. As seen in Eq. 26, this situation
Mg,C1 = concentration of magnesium
, would require an increase in Kga (G and Z being
and chloride in spray liquid
constant), or an increase in tower height, Z (K,a &, a, . . . , f = correlation constants
and G being constant). If the operating and
equilibrium lines are further apart, the oppo- Eqs. 26 and 27 are used simultaneously with
site relationships will exist. mathematical models of lime/limestone slurry
Through a series of parametric experiments, chemistry to select the optimal spray tower.
a mathematical correlation between Kga and Other models for prediction of SO, removal are
spray tower design variables can be estab- available in the literature.41
LlMElLlMESTONE
FODS PROCESS CHEMISTRY

The chemistry of wet scrubbing of SO2 from


flue gas with lime/limestone consists of a
complex series of kinetic and equilibrium-
controlled reactions occurring in the gas, liq-
uid, and solid phases. Although the overall
reactions are commonly expressed as:

Lime: CaO + SO,+CaSO,


CaSO, + ~ / ~ 0 , + C a S 0 ,
(28)
- _
. -
-
Limestone: CaCO, + SO,+CaSO, + CO,
Mole Fraction SO2 in Liquid
CaS0, +-1/202+CaS0,
(29)
Fig. 24 Determination of K,a
COMEmTION
Contml of Power-Plsnt Steck Emissions

considerably more detail is required to empha- Replacing Eqs. 33 and 34 with the following re-
size and understand the effect of several key generation reactions makes it possible to de-
process variables such as pH and soluble magne- scribe limestone scrubbing:
sium and chloride concentration on the chem- -
istry of lime/limestone scrubbing.
The chemical reactions occurring in lime/ Regeneration:
limestone systems can be written in several CaCO, + HSO; + Caf+ + SO; + WCO,-
different forms, depending on which aspects (39)
are being discussed. For this discussion, the
reactions have been categorized as absorption,
neutralization, regeneration, oxidation, and
precipitation. Although written sequentially,
many of these reactions occur simultaneously
in an actual system. Significant reactions are
- --
The following text relates this chemistry to
Absorption: key aspects of FGDS design. Specifically cov-
SOz + Hz0 + H S 0 3 [ H S O + H+) ered are the effects of absorbent composition on
(30) SOz removal, scale control, oxidation, and ad-
ditive utilization.
Absorbent-CompositionEffect

Vapor-liquid equilibrium between SO, in the


gas and the absorbent liquid governs the
amount of SO, absorbed from flue gas. If no sol-
uble alkaline species are present, the liquid
quickly becomes saturated with SO, and ab-
sorption is limited.
Regeneration: The neutralization reactions 31 and 32 re-
Ca(OH)2+ 2HS0; -* CaC++ 2SO;+ 2Hz0 move sulfurous acid, H2SO3,from solution and
(33) allow the absorption reaction to proceed. In a
Ca(OH), + 2H&03 + Ca++ + 2HC0; + 2Hz0 spray tower, the soluble alkaline species in the
spray slurry performs most of the neutraliza-
(34) tion due to the extremely short liquid residence
time. If an absorber has greater liquid holdup,
Oxidation:
HSO; + l/202 + SOT+ H+ additional neutralization can be expected from
(35)
dissolution of solid calcium sulfite or lime-
stone. Thus, factors affecting soluble alkalinity
so; + %02 + so: in the spray slurry impact on the overall
(36) SO, removal capability of a lime/limestone
FGDS. In the development of these processes,
Precipitation: it is apparent that the three major factors af-
(m + n ) C a + + + m S O ; + n S O ; + x H 2 0 + fecting the soluble alkali level are pH, soluble-
Ca(, + ,,,[ S O S ) ~ ~ , xHQ
(S~~~,~ magnesium concentration, and soluble-chlo-
(37) ride concentration.
Effect of pH
Ca++ + SO; + 2HQ + CaSOi.2H20
(38)
In general, with a lime/limestone FGDS, the
higher the pH, the greater the SO, removal effi-
COMBmRON
Contrd of Pow-Plant Stack Emissions
--
ciency. Two factors are involved. First, by defi- the total input from the various sources and
-- -
nition, a high pH increases the hydroxyl-ion upon the rate at which liquid leaves the sys-
(OH-) concentration, which acts similar to sul- tem. In closed-loop operation, the accumula-
fite and bicarbonate reactions 31 and 32. But at tion increases until a magnesium compound,
the pH ranges experienced in commercial sys- such as magnesium hydroxide, precipitates. In
tems-between 5 and 8-the impact of hy- a commercial system some liquid containing
droxyl-ion neutralization is negligible. So it is magnesium leaves with the solids. Thus, the
the second factor, the impact that pH has on the degree of solids dewatering affects the concen-
sulfitehisulfite and bicarbonatelcarbonic-acid tration of magnesium in a wet-process FGDS.
equilibrium reactions, that has the primary Systems with vacuum filters or centrifuges
beneficial effect on SO, removal. for final solidlliquid separation operate at
Figs. 25 and 26 illustrate the impact of pH on higher magnesiu%itd.~elsthan those with a
these equilibria. In the range of pH from 5 to 8, thickener 0nly.42
increasing pH shifts the sulfite-bisulfite equi- Commercial operation of FGD systems has
librium in favor of sulfite. Shifting the equilib- shown that soluble Mg in the absorbing slurry
. rium towards the sulfite region by increasing significantly improves SO, removal efficiency
pH is beneficial to SO, removal. A similar con- (Fig. 27). The increase is attributable primarily
dition exists with the carbonic acid (H,CO,)/bi- to the higher soluble-alkali levels in the pres-
carbonate equilibrium. Increasing pH favors ence of magnesium. In normal limellimestone
existence of the bicarbonate ion which can neu- spray-tower operation, little of the additive dis-
tralize sulfurous acid (reaction 32). solves within the tower because it remains
there such a short time. Thus, the amount of
Effect of Magnesium
sulfur-dioxide absorbed depends principally
Magnesium enters the SO2 scrubbing system upon soluble-alkali content. If the alkali con-
through several mechanisms: centration in any region of the liquid drops, the
as a constituent in limestone and lime rate of the neutralization reactions 31 and 32
8 from coal-ash constituents solubilized in the also drops. Ultimately, a static equilibrium
scrubbing liquor condition between gaseous and liquid SO, con-
in the makeup water added to compensate for centration is approached.
evaporation and other liquid losses. Where magnesium exists, the soluble alkali
The magnesium concentration depends on level of the absorbent increases primarily be-

Fig. 25 Bisulfite-sulfiteratio versus pH Fig. 26 Bicarbonate-carbonate ratio versus pH


COMBmTION
Control of Power-Plant Stack Emissions

cause of the presence of sulfite and bicarbonate While magnesium improves SO, removal ef-
salts of magnesium. As these magnesium alka- ficiencies by increasing the soluble alkalinity
lies are significantly more soluble than the level of the scrubbing slurry, chloride has an
corresponding calcium alkalies, there is opposite effect. Chloride ions combine with
an increase in the sulfur-dioxide absorption available magnesium and displace soluble
capacity of the slurry. The solubility of mag- sulfite and bicarbonate from solution. Many
nesium alkali compounds depends on pH. In a investigations have correlated SO, removal
lime-additive FGDS, therefore, the proper sys- efficiency to "effective" magnesium concentra-
tem operating pH is very important to take full tion not "actual" magnesium concentration.
advantage of the magnesium. Examination of "Effective" magnesium concentration is de-
the sulfite-bisulfite and carbonate-bicarbonate fined as:
equilibria and the magnesium solubility curve
(Fig. 28) indicates the optimum pH to be in the
7 to-8 range. System operation at pH higher
than 8 reduces the magnesium solubility and
may prevent full use of the additive. Operation
below a pH of 7 decreases the concentration of where
neutralizing bicarbonate and sulfite and the Mg, = effective Mg concentration, mg/P
beneficial effect of magnesium on SO, removal. Mg = actual blg concentration, mglP
Effect of Chloride C1 = actual Cl concentration, mglP

Chlorides generally find their way into an Using Eq. 41, it can be shown that, in the
FGD system by one or both of the following: presence of 10,000 mglP of chloride, the benefi-
from the chloride present in the coal burned cial effect of 5,000 mg/P of magnesium is re-
and subsequently dissolved as a hydrogen duced to the equivalent of only 1575 ppm
chloride gas (or as a salt in the scrubbing liq- magnesium. In the absence of magnesium, it is
uor), or with the makeup water, especially generally accepted that increasing chloride-ion
when cooling-tower blowdown or other plant concentration reduces SO, removal efficiency
waste water is used. through a pH-lowering effect. Some research-

95 -
Inlet SO2 Concentration

g 75-
?.

70 3 I I I I I
0 1000 2000 3000 4000 5000
Magnesium Concentrat~on,
ppm

Fig. 27 Effect of magnesium on SO, Fig. 28 Magnesium solubility at various


removal efficiency pH values
COMBVSllON
Control 01 Power-Plant S t a k Emissions
-
ers, howevers, have failed to observe any SO, flue gas, it is in intimate contact with gases
removal reduction for chloride-ion concentra- containing typically 3 to 5 percent oxygen. The
tion up to 40,000 mg/L43 reaction between the oxygen, which is ab-
sorbed, and the sulfitehisulfite in the liquid
Scale Control
leads to sulfate formation. Since there may be
The principal compounds crystallizing in a no accumulation of material at steady-state,
flue-gas desulfurization system are calcium sulfate must be continually purged from the
sulfite and sulfate (reactions 37 and 38). The system. Although sulfate may theoretically be
major concern with crystallization of these purged entirely in the liquid phase, this mode
compounds is the potential for scale formation is generally unacceptable from an environmen-
on scrubber internals. Uncontrolled scale can tal standpoint-large quantities of sulfate
plug the spray nozzles, mist eliminators, pip- would be discharged into the local water.
ing, and other equipment. Plugged systems In practice, sulfate is generally purged from
must be shut down and cleaned. limetlimestone wet scrubbers as relatively in-
As the crystallization of calcium sulfite is soluble calcium salts which are dewatered and
pH-sensitive, abrupt pH increases (especially disposed of as solid waste. Thus, it is ex-
in lime systems) must be avoided. Control of tremely important to control the reactions of
the spray slurry pH has curtailed sulfite scaling crystallization which form the calcium-sulfate
in commercial systems. salts. If these reactions are not properly con-
Control of calcium-sulfate scaling is more trolled, serious plugging can occur because
difficult, and the normal 5-8 pH range encoun- of a hard scale of calcium-sulfate dihydrate
tered in operation is not a factor influencing (CaSO, 2H20, gypsum) that may form.
calcium-sulfate saturation or crystallization. The equilibrium and kinetic factors in crys-
Control of calcium sulfate relative saturation tallization reactions involving calcium sulfate
depends on seed-crystal concentrations and are complex. Slurries containing high concen-
crystallization time. Any increases in the trations of salts behave as non-ideal solutions
relative saturation of calcium-sulfate to high and the relationship between the concentration
values can be conducive to heterogeneous of calcium sulfate and its equilibrium solubil-
nucleation and the consequent scaling of scrub- ity is best defined in terms of activity coeffi-
ber components. cients. Activity coefficients are factors which,
Work on scale-control techniques performed when multiplied by the concentrations of the
by C-E and others in 1974 and 1975 revealed respective ions, yield their activities. In a
that there was an alternate mode of FGDS oper- slurry, calcium sulfate does not behave ideally,
ation-subsaturated operation.42.44 Under some hence the use of the activity in defining the sol-
conditions, coprecipitation of sulfite within ubility product, K,.
the calcium-sulfate crystal lattice can occur to
such an extent that it removes all the sulfite
formed through oxidation. When this occurs,
the scrubbing slurry does not become saturated
with calcium-sulfate, and scale cannot form.
The following sections will discuss various as- where
pects of scale control including relative satura- Kc- = baAso4 = solubility product of CaSO,
tion a n d scale potential, supersaturated A, = activity of calcium ion
operation, and subsaturated operation.44 Aso4 = activity of sulfate ion
- _ -
If the activity product of the calcium and sul-
Relative Saturation and Scaling Potential
fate ions is less than the solubility product, the
-.
As the scrubbing liquor absorbs SO, from solution is said to be subsaturated. If the prod-
COMBUSRON
Control of Power-Plant Stack Emissions
I

uct is greater than K,, the solution is supersat- tion rate expression.
urated. The ratio of the activity product to the A crystallization rate equation was devel-
solubility product is called the relative satura- oped from bench-tests
tion (RS)and is used as a measure of the satura- -
tion level of a solution with respect to gypsum. R = knS
(44)

RS = K,,c~so,.-~H~o (43)
. .
where
R = reaction rate
k = rate constant
when
n = number of seed crystals
RS < 1.0, solution is subsaturated;
S = driving force
RS = 1.0, solution is saturated;
RS> 1.0, solution is supersaturated. Interpretation of the data collectgd suggested
a driving force term of the form (RS - 1). It also
The importance of gypsum relative satura-
showed that the rate was directly
tion in designing lime/limestone wet-scrub-
to seed-crystal concentration.
bing systems for scale-free operation is shown
Further work was performed to calibrate the
in the following discussions.
rate expression with data from full-scale, com-
Supersaturated Operation-Gypsum Crystallization mercial FGD systems.44.45 The rate expression
may be used to predict the seed-crystal concen-
Formation of calcium-sulfite and calcium- tration required to prevent calcium-sulfate
sulfate scale on scrubber internals can be a se- scaling. The rate of calcium-sulfate precipita-
vere problem and, while control of calcium- tion in the reaction tank, R, can be computed
sulfite scaling is possible by avoiding rapid by material balance if the following informa-
increases in slurry pH, control of calcium- tion is known: SO, absorption rate, fraction
sulfate scaling is not a function of slurry pH. SO, oxidized to SO,', and reaction tank resi-
Considerable effort was made in the early dence time. Sulfur dioxide absorption rate and
1970's to establish an expression to describe reaction tank residence time are design pararn-
the desupersaturation rate of calcium sulfate as
a function of appropriate system design and
operating parameter^.^^
In addition to developing a crystallization-
rate equation, it was necessary to determine the
level of calcium-sulfate supersaturation that , 1.35
could be tolerated without causing scaling of
internal surfaces in any operating scrubber.
-P
2
3
A series of experiments to determine the crit- 1.0
0)
ical supersaturation above which scaling can
occur revealed that a high probability of scal-
ing exists if the absorber effluent relative satu-
-
m
-
2.-!
a,
upersaturated Operation
a:
ration exceeded 1.35. Thus, Fig. 29 shows the Subsaturated Operation
supersaturated operating range between rela-
tive saturation 1.0-1.35 where scale formation
0
is unlikely and operational difficulties slight.
After establishing a calcium-sulfate relative
saturation region for scale-free operation, the Fig. 29 Relative saturation of gypsum as
industry worked on developing a crystalliza- an indication of scaling potential
CoMBosnON
ConW of Power-Plant S t a k Emissions

eters, and fraction SO2 oxidized can be pre- studying this phenomenon led to the develop-
dicted from various design models. The ment of mathematical correlations which re-
maximum relative saturation allowable in the lated the amount of sulfate coprecipitated to
absorber effluent is 1.35; values above this criti- various system parameters. An example of one
cal level will result in scale formation. By us- of the more useful correlations is shown below:
ing information on the absorbent composition
(such as magnesium and chloride concentra-
tions), rates of oxidation, ionic strengthlactiv-
ity coefficient correlations, and the level of
saturation entering the absorber which will
result in an absorber effluent saturation of 1.35 where
can be calculated. This value and the rate of MR = mole ratio of SO4to SO, in the
calcium-sulfate precipitation are used in Eq. 44 co-precipitated solid
to predict the seed-crystal concentration re- A,,Aso, =activities of calcium and sulfate
quired in the reaction tank to maintain the ab- ion, respectively
sorber effluent relative saturation below 1.35. K,x,y = experimental constants
Thus, the solids concentration circulated to Numerical values for the experimental con-
prevent scaling can be computed and used as stants were determined to be
an operating point. K =231
x = 0.54
Subsaturated Operation-Coprecipitation y =0.76
Because crystallization is thermodynami- Fig. 30 is a plot of over 60 bench-scale experi-
cally impossible from subsaturated solutions, ments and several data points taken from
the potential for scaling can be eliminated by full-scale commercial installations. The
operating the system at a relative saturation dependency of mole ratio (MR) on the activities
less than 1.0. Until recently, the only tech- of calcium and sulfate has been demonstrated
nique known to accomplish this was liquid over a wide range of solution c~mpositions
blowdown. However, discharging large quanti- and kinetic conditions. The ranges studied
ties of process water to the environment is included:
unacceptable. Work by EPA suggested an
alternate method for purging sulfate from solu- Calcium 60-6,000 mgl e
tions that are subsaturated with respect to gyp- Sulfate 600-20,000 mgl f?
Sulfite 100-6,000 mgl f?
sum: coprecipitation of sulfate with calcium Magnesium 0-5,000 mgl f?
sulfite to form a mixed crystal.46 Although the Chloride 0-14,000 mgl C
exact nature of this mixed crystal is not fully Sodium . 100-5,000 mgl P
understood, several interesting facts have Sulfite precipitation rate 0.15-2.3
evolved: millimoll f-min.
significant amounts of sulfate can be copre-
cipitated with calcium sulfite from solutions The mathematical model can be used to
which are subsaturated with respect to gypsum predict the effect of oxidation on the level of
the mole ratio of sulfate to sulfite in the gypsum saturation in a subsaturated lime1
mixed crystal can be as high as 0.2-0.3 limestone FGDS.
x-ray diffraction analysis of samples of the The left side of Eq. 45 consists of the term,
mixed crystal indicates only the presence of MR, the mole ratio of sulfate to sulfite in the
calcium-sulfite hemihydrate (CaS03.11~H20); copiecipitated solid. Because nearly all forms
no known calcium-sulfate forms are observed. of sulfur leave the system in the solid phase,
Bench and pilot scale experiments aimed at the ratio of sulfate to total sulfur in the solids
COMEDSTION
Control of PowerSlant Stack En?isslons

equals the oxidation in the system. It can be saturation to system oxidation. As oxidation
shown that the following relationship exists can be predicted by other design models, the
between MR and system oxidation: level of gypsum saturation can be predicted
using Eq. 45. Furthermore, the relationship is
direct and by increasing the oxidation we
increase the saturation.
Maximum Tolerable Oxidation
One particularly useful concept is that of
where so4 maximum tolerable oxidation (MTO) which is
OX = fraction oxidized = SO, SO,
the oxidation level that will cause a limellime-
+

stone FGD system to run saturated with respect


The right side of Eq. 45 contains terms for to gypsum (RS = 1.0). Maximum tolerable oxi-
calcium and sulfate activities similar to the def- dation can be calculated using the proposed
inition of RS. Thus, design equation. By using an equilibrium pro-
gram or other experimental or theoretical tech-
MR = KA,,". A,,,Y niques, the activities of calcium and sulfate for
(relatedto (relatedto a saturated solution can be calculated. If these
oxidation) relative saturation) values are inserted into Eq. 45, it is possible to
(45) calculate the mole ratio of sulfate to sulfite in

~ Eq. 45 can, therefore, be used to relate relative


the coprecipitated solids in equilibrium with
this solution. Oxidation can then be calculated

0.25-

4 0.20 -
-
.-
c2
P.- 0.15 -
c

-
.2 0.10-
m
-
a:
ao
2 0.05 -
* *
/*% 0 o o Bench
Pilot Plant
Data
o FieldData
Data

I I I I I I I I I
1 2 3 4 5 6 7 8 9 10
A&% ::A
; ~ 1 0 - ~

Fig. 30 A c , ~A. S
~O~ ~ versus
~ . ' ~ mole ratio of SO, to SO,
--
COmmnON
Conird d Power-Plant Stack Emissions

from Eq. 46. For example, in a solution con- positions (i.e., magnesium/chloride concentra-
taining no magnesium or chloride, the activi- tions and saturations) and temperatures. Using
ties of calcium and sulfate in a saturated these activities it is possible to calculate the
solution are approximately 0.0049 and 0.0039 mole ratio of sulfate to sulfite in the coprecipi-
mollPrespectively at 50C;this translates to ap- tated solid and, thus, the oxidation required to
proximately 16-percent oxidation (Eq. 46). produce that mole ratio.
If the system operates at 16-percent oxida- Fig. 31 is a plot of relative saturation versus
tion, the reaction tank will operate saturated oxidation as a function of varying magnesium
with respect to gypsum, assuming that the pre- and chloride concentrations obtained by this
cipitation reaction occurs in the reaction tank. method. The presence of chloride shifts the
Higher oxidation levels will result in supersat- curves to the left resulting in high saturations
urated operation; lower oxidations will result for the same oxidation, while magnesium
in subsaturated operation. Thus, the MTO for a has the opposite effect.It also can be seen that
system containing no magnesium or chloride is the presence of chloride diminishes the benefi-
16 percent. cial effect of magnesium. In addition, the oxida-
The design equation can be used to predict tion that corresponds to relative saturation
the relative saturation of gypsum for subsatura- of 1.0 represents the maximum tolerable oxi-
ted systems as a function of magnesium and dation for subsaturated operation at these
chloride concentrations, and temperature. As a conditions.43
consequence, it can also be used to predict
Oxidation
whether a system will operate in the subsatura-
ted mode. Calcium and sulfate ion activities In lime/limestone FGD systems, solutions
. can be predicted for solutions of various com- containing sulfite (SO,-)come in intimate con-

1.3r 7
\

1.2 - -
1.1 - -
.-5 1.0- 0 Mg, 5000 mg/k CI
+d

0.9 - , mgll CI
0 ~ g2000 2000 mg/!Mg,7000 CI
5 0.8 - 2000 mg/lMg, 5000 CI

-
.-$ 0.7
4 0.6 -
- OMg, OCI

II:
5 0.5 -
0.4 -
6 0.3 - 2000 mgkMg, 0 CI

0.2 - 5000 mg/AMg, 0 CI 2000 rng/tMg, 0 CI

1 I I I I I -1
0 8 10 12 14 16 186 8 10 12 14 16
Oxidation, OO
/ Oxidation,%

1
Fig. 31 Effects of Mg and CI on gypsum rekative saturation as a function of oxidation
COMBUSIlON
Control of Power-Plant Stack Emissions

tact with flue gas containing typically 3 to 7 oxygen and sulfite in the aqueous phase is very
percent oxygen. As a result, significant quanti- complex and can be greatly influenced by the
ties of SO,- (S+,)are oxidized to SO,' (S+6).The presence of catalysts and inhibitors. The rate of
rate at which sulfate is formed directly deter- the oxidation reaction is nearly always much
niines the required rate of sulfate purge at faster than the rate of oxygen transfer to the liq-
steady-state which in turn influences the level uid phase. Thus, oxidation in FGD systems is
of calcium-sulfate saturation. The relative generally mass-transfer limited and the rate of
amounts of sulfate and sulfite formed in the chemical reaction can be assumed to be instan-
process also have implications in the ultimate taneous. Mathematical models of the oxidation
disposal of FGDS waste product. In general, process can then be expressed in terms of clas-
sludges containing high sulfate to sulfite ratios sical two-film mass-transfer theory.
are more easily dewatered and result in a more An example of the type model which has
stable disposal product. Thus, the rate of sul- been developed to describe the rate of oxida-
fate ion formation (rate of oxidation) has wide- tion in a spray tower absorber is
spread implications on the performance and
reliability of wet SO, scrubbing processes. A
quantitative understanding of the factors
which contribute to sulfate ion formation is es-
sential if lime/limestone wet scrubbing is to
have optimum performance. where
Two major oxidation process options exist: r,, = rate of natural oxidation, mollmin-gal
natural and forced. In natural oxidation, con- G = gas flow rate, mollmin
version results primarily from a reaction be- C, = oxygen content in flue gas, mollgal
tween soluble sulfite in the scrubbing slurry R = gas constant, gallatm-mol-OR
and oxygen in the flue gas. Only a minute T = gas temperature, OR
amount of oxidation occurs from contact with P = total pressure of gas, atrn
atmospheric oxygen in open tanks, overflow KLa= overall volumetric mass-transfer
weirs, and the like. coefficient, min-'
Several factors influence the rate of oxida- V, = volume of liquid in absorber, gal
tion: oxygen concentration in the flue gas, V,= absorber volume, gal
ionic strength and pH of the absorbent slurry, H = Henry's law constant, gallatm-mol
and the liquid-to-gas ratio in the absorber.
In forced oxidation, on the other hand, com- All variables in Eq. 47, except KLa,are design
pressed atmospheric air is injected into the pro- parameters which are known or may be esti-
cess [usually in the reaction tank) to promote mated. The overall mass-transfer coefficient
oxidation and achieve oxidation efficiencies of cannot be determined on theoretical grounds
90 to 99 + percent. Forced oxidation improves except in the most simple cases and must there-
the dewatering and structural characteristics of fore be determined experimentally. C-E has de-
the waste product and consequently reduces veloped mathematical correlations which
disposal costs. The following text discusses predict KLaas a function of operating and de-
factors which influence oxidation in limellime- sign parameters for various absorber types. An
stone scrubbing systems. example of the equation form used to predict
KLafor spray-tower absorbers is
Natural Oxidation

The major source of oxidation in a naturally


oxidized FGDS is the absorber in which the ox- K,a = a (L/G)* (I)" (pH)d(V,)" (ZY(CAP
ygen in flue gas reacts with the soluble sulfite (48)
in the scrubbing slurry. The reaction between
-moN
Control of Power-Plant Stack Emitsions
-
where forced-oxidation system is as follows:
LIG = liquid-to-gas-ratio
I = ionic strength of absorbent ~ K,(hIa (IIb(PHI'
K L= ( v a i d d (Dle (Pdf
slum (50)
pH = pH of spray slurry
where
V, = superficial gas velocity in
absorber
K, = experimental constant
Z = height of contactor
,V = superficial air velocity in tank
a,b,c,d,e,f,g= experimental constants
D = tank diameter
P, = mixer power input to tank
With the oxidation rate known, the fraction It is generally accepted that oxidation is in-
of SO, oxidized can be calculated by dividing creased by decreasing pH, increasing mixer
the oxidation rate by the SO, absorption rate. power, increasing ionic strength, and increas-
The fraction oxidized can then be used in the ing tank height.
various scale-control models to arrive at appro- Note that the total oxidation achieved in a
priate operating conditions, and to predict the forced oxidation FGDS is a function of the nat-
characteristics of the disposal product. urally occurring oxidation, for which credit
may be taken.
Forced Oxidation
ADDITIVE UTILIZATION IN WET SCRUBBERS
Forced oxidation uses atmospheric air in-
jected into the reaction tank of FGD systems. To Minimizing the amount of alkali additive re-
achieve the best efficiency, the injected air quired to obtain a desired SO, removal effi-
must be finely divided into tiny bubbles to ciency reduces the operating cost of an FGD
maximize the interfacial area. The dispersion is system. To determine the factors influencing
usually accomplished by using either sparge additive use, it is ne'cessary to understand the
rings and radial turbine mixers, or jet educ- additive dissolution process and the effect of
tors. With either arrangement, the ultimate system operating conditions, design, and addi-
problem is to define and predict the impact of tive properties on this process.
various process design and operating parame- In a lime or limestone SO, scrubbing system,
ters on the oxidation rate. This can be achieved the addition of alkali is controlled to neutralize
in a manner similar to predicting the level of the SO2absorbed and precipitate the calcium-
natural oxidation occurring in an absorber. The sulfur salts. Although in theory the amount of
two-film mass-transfer approach is: lime or limestone required is stoichiometri-
cally equal to the amount of SO, removed, the
kineties of the limestone dissolution process
dictates the use of excess additive to achieve
the desired SO, removal efficiency.
Additive stoichiometry is usually defined as
the mols of additive fed (excluding impurities)
where to a scrubber per mol of SO, absorbed (although
r, = rate of forced oxidation it can be, and sometimes is, defined as the mols
GA= airflow rate of additive fed per mole of SO, entering the
h = height of reaction tank scrubber). Additive utilization, then, can be ex-
Similar to the absorber natural oxidation pressed by the following relationship:
model, all of the variables except K,a are
known OF may be estimated. A correlation de- 1 moles SO, absorbed
Utilization =
scribing K,a as a function of pertinent process Stoichiometrv = moles additive fed
variables for a sparge ringlradial turbine
COMBUSTION
Control of Power-Plant Stack Emisslom

Although not usually significant, the absorp- sulfur dioxide. The following summarize the
tion of other acid gases such as HC1 can influ- effectof CO, absorption:
ence utilization of the additive. Utilization
then could be more broadly defined as the frac- CaO + C02+CaC03(aq)
tion of additive converted to reaction products
in the scrubber. However, unless a detailed ma-
terial balance is done, it is more straightfor-
ward to use Eq. 51 to calculate utilization from
system operating data.
From Eq. 51 it can be seen that, to increase
utilization, one must either reduce the additive Data from a full-scale commercial FGDS in-
feed rate while maintaining constant SO, ab- dicate that a decrease in utilization from 95
sorption efficiency or i,ncrease the SO, removal percent to 85 percent may occur as pH is in-
efficiency for a given limestone feed rate. creased from 7.5 to 9.0. To reduce waste of the
The dissolution rate of alkali additives is in- relatively high-cost lime, the pH of lime sys-
versely proportional to the solution pH; there- tems should thus be held below 8.5.
fore, better utilization is possibIe by operating
Limestone Utilization
a system at low pH levels. However, as pointed
out earlier, reducing the pH also can reduce Limestone is usually less reactive than lime
SO, removal efficiency. Therefore, it is usually in FGD systems operating under identical con-
more productive to increase the absorber per- ditions. For this reason, system modifications
formance for the same system pH, or increase are needed to produce limestone utilizations in
the additive dissolution and utilization at a excess of 90 to 95 percent.
constant system pH. Limestone dissolution is a function of sur-
face area of the suspended limestone and hy-
Lime Utilization
drogen-ion concentration (i.e., pH) of the
Lime or calcium oxide (CaO) is obtained from solutions as follows:
calcination of limestone (CaC03). The condi-
tions under which the limestone is calcined or
"burned" can have a great impact on the reac-
tivity of the lime produced. If the limestone is
where
calcined at too high a temperature, the lime
r = rate of limestone dissolution, moll!-s
may become dead-burned and unreactive,
K = experimenta.1constant, s/cm2
making it unsuitable for FGDS use.
A = surface area of suspended limestone,
Because of the high reactivity of most com-
cm2
mercially available lime, it is possible to
Hi =hydrogen ion concentration
achieve high utilization (as much as 95 per-
moll!
cent) with minimum impact on the remainder
of the system. The main design parameter in Use of Eq. 54 suggests two methods of in-
maximizing utilization is the pH of the scrub- creasing the limestone dissolution rate and,
bing slurry. With pH maintained above 8.5, thus, utilization: first, by increasing the surface
considerable carbon-dioxide absorption occurs area, A, and second, by increasing the hydro-
because of the 10 to 15 percent by volume of gen-ion concentration (reducing pH).
CO, in the flue gas. Carbon dioxide reacts with Large surface areas can be produced by finely
lime in a manner similar to sulfur dioxide to grinding the limestone before it is injected into
form calcium carbonate. Calcium carbonate, the system. Limestone is typically ground to 80
being insoluble at high pH, precipitates and to 90 percent through 325 mesh in FGDS appli-
thus prevents the calcium from reacting with cations. Finer grinds are possible, but more
COMBUSRON
Control of Powar-PIant Stack Emissions

pulverizer power is required. This is many reliability and performance in a corrosive and
times cost-effective. erosive environment.
Limestone utilization can also be improved
Tower Shell
by operating at reduced pH's. As mentioned
previously, this impairs efficiency-to main- Velocity considerations dictate the tower
tain the same removal at reduced pH, the ab- cross-sectional area (Fig. 32). Although higher
sorber design must be modified. For example, gas velocities through the absorbing section
WG may be increased (with higher pumping improve SO2removal, the maximum allowable
costs) or tower height may be increased (with velocity through the close-coupled mist elimi-
higher capital costs). The cost-effectiveness of nator section (about 10 to 11ftlsec) sets a practi-
any such adjustments must be examined. cal limit of 12 to 13 ftlsec through the absorbing
It is also possible to use a two-stage opera- section. A short transition piece with a gradu-
tion in which the primary stage is operated at ally expanding area connects the mist elimina-
reduced pH.to optimize 1imeJlimestone use, tor section to the absorber section. The number
and the second stage is operated at high pH to of absorbing stages required to obtain the de-
accomplish the required SO, removal. In this sired level of SO, removal governs the overall
operation, limestone is fed to the second stage tower height.
and the spent slurry from the second stage is The corrosive and erosive environment
fed to the primary stage before being bled off. within the tower requires special materials.
A final technique for improving limestone Type 316L and 317L stainless steels have been
utilization is to increase residence time-at a successfully applied in numerous instances.
fixed rate of reaction, the longer a limestone Under certain conditions of scrubber-slurry
particle remains in the absorberlreaction-tank pH, temperature, and chloride concentration,
loop, the greater will be the fraction of the par- the use of nickel-based alloys with higher mo-
ticle that dissolves. lybdenum and chromium contents can provide
The residence time of the solid particles in superior corrosion protection.47 The use of such
the process is a function of the particle inven- high-grade alloys requires very careful fabrica-
tory and the solids bleed rate. Because the tion. In general, failures of high-grade alloys
bleed rate is fixed by the SO, absorption rate at incorporated in the tower shell and internal
steady-state, only the inventory can be ad- support members occur primarily because of
justed. The solids inventory can be made faulty welding rather than corrosion.
greater by increasing the reaction-tank volume In contrast to the spray-tower shell, the gas
andlor the solids concentration. Because the ducts upstream and downstream of spray
slurry is abrasive, the solids concentration has towers represent much more severe corrosive
a practical upper limit of about 15 percent. The environments. Absorber inlet and outlet ducts,
relatively low cost of tanks and low mixer and reheat mixing zones, require special con-
power requirements suggests that, in many sit- sideration with respect'to material selection.
uations, it is less expensive to increase the tank Protective linings such as inorganic cements or
size to improve limestone use. borosilicate glass blocks over carbon or stain-
less-steel are typically used for the ab-
SPRAY-TOWER COMPONENTS
-
sorber inlet ducting.
In addition to viable process chemistry, suc-
Pumps, Piping and Nozzles
cessful spray-tower performance requires the
proper selection of system components. These Fig. 32 shows independent absorption
consist principally of the tower shell, the slurry stages, eachxonsisting of a spray pump, pip-
delivery subsystems (pumps, piping and noz- ing, manifold, headers, and spray nozzles. If a
zles), the mist eliminator, and the gas reheater. spare pump is included, a complete spare ab-
Each must be designed with materials for good sorption stage is also provided. This arrange-
COMBUSIlON
Control of Power-Plant Stack Emissions

Fig. 32 Typical spray-tower absorber module


-.

15-53
CmmUmON
Conbo/of PomPlu,t Sbck Emissions
-
ment provides maximum flexibility and allows keep slurry velocities within allowable values
tailoring the spray flow to system requirements (nominally 5 to 10 ftlsec).
by removing absorption stages from operation The spray nozzles at each absorption stage
in steps. are arranged to provide full spray coverage
Rubber-lined centrifugal spray pumps pro- over the tower cross-section. The nozzles pro-
vide erosion resistance and protection against vide a full-cone, wide-angle spray pattern, and
unexpected process upsets in pH control. A tall are typically made of a wear-resistant cast re-
reaction tank provides a large net-positive- fractory containing silicon carbide.
suction head to prevent pump cavitation
Mist Eliminator
which can damage rubber pump liners.
Fiberglass-reinforced plastic (FRP) spray The cleaned flue gas passes through a separa-
piping with a abrasion-resistant internal liner tion section with two stages: the bulk entrain-
provides both abrasion and erosion resistance. ment separator (BES) and the mist eliminator
The FRP is an inert material used for its corro- (Fig. 33). The BES consists of six-inch FRP
sion resistance. FRP piping is easily fabricated vanes mounted at a 45-degree angle on two-
and, unlike rubber-lined pipe, can be readily inch parallel spacing. It extends across the en-
repaired in the field. tire face area of the spray-tower absorber.
The manifold and headers are built of FRP The mist eliminator located above the BES is
for the flow and geometry requirements of each made from vee-shaped FRP vanes arranged in a
application. Tapered manifolds and headers series of chevrons across the gas flow path.

Chevron Vanes

Washer Lance

Bulk Entrainment Separator (BES)

Fig. 33 Spray-tower mist-eliminator system


COMBUSTION
Control of Power-Plant Stack Emissions

Two rows of chevrons assure droplet impinge- single-inlet designs have ready spare machines
ment and minimize mist carryover. which can be installed in thirty minutes or less
Retractable lances, which rotate 360 degrees, after an unplanned spray-machine shutdown.
.. have pairs of opposed nozzles at the ends and -
When on-line redundancy is desired, the three
-midpoints; they are located between the BES machines are usually designed for handling
and the lower level of chevrons. These lances one-half the rated load, thereby allowing one
provide high-energy jets of water to clean each machine and inlet to be isolated if necessary.
vane. Efficient cleaning prevents excessive Three-inlet vessels can even be designed to
droplet carryover which would result from operate with only one machine and inlet in
deposition on the vanes. service, thereby amplifying the turndown
capability.
Flue-Gas Reheater
DROP-SIZE REACTOR
Combustion Engineering recommends in-
line carbon-steel gas reheaters for full-flow Inside the SDIA, the slurry is introduced as a
heating of treated flue gas before discharge to very finely divided spray, often with a mass
atmosphere.48 Compared to austenitic-stain- median diameter below 35 micrometers and a
less-steel reheaters, they are the least expensive largest droplet well below 150 micrometers.
to install; with proper maintenance, they are Each droplet, in effect, becomes a miniature re-
also the least costly to operate. C-E uses spiral- actor. Sub-micrometer particles of lime dis-
wound finned-tube heat exchangers identical solve according to the reaction
to those installed in many high-pressure boil-
ers. Staggered tubes combined with shallow
overall depth ensure high heat-transfer effi-
ciency as well as easy cleaning of the reheater.
C-E has had excellent experience with its car-
bon-steel reheaters placed immediately down- thereby making OH-, or hydroxyl, ions avail-
stream of the scrubbing equipment. T h e able in the liquid phase for neutralization o f ,
mist-eliminator system described above ex- hydrogen ions (H'). Hydrogen ions are pro-
poses the reheater to extremely small quantities duced as sulfur-dioxide molecules diffuse
of liquids and solids. Any solids that do collect across the droplet surface, dissolve in the liq-
on the reheater are removed easily by conven- uid, and dissociate according to the reaction
tional air or steam sootblowers.
SPRAY DRY-SCRUBBER DESIGN
The heart of the spray dry-scrubber process is
the spray-dryerlabsorber (SDIA). Vessels have
been built with single inlets and single rotary
atomizers, as well as with three inlets and at- The dissolution of sulfur dioxide tends to
omizers; from a process standpoint, the three- lower the pH (or raise the hydrogen-ion activ-
inlet u n i t s perform identically to t h e ity) in the liquid phase, while the dissolution
single-inlet designs. of lime tends to raise the pH. Slaked lime has
The amount of flue gas to be processed dic- an equilibrium pH of about 12.0, while sulfur
tates the choice of one or three inlets. Single- dioxide at 1,000 ppm by volume in the gas
inlet designs are generally limited to no more phase in equilibrium with pure water will
than 300,000 cubic feet per minute at the inlet lower the pH to about 2.5. Reactions 55 and 56
conditions, while a three-inlet vessel can han- characterize the acid-base neutralization which
dle three times as much flue gas. Another im- occurs in each droplet as it passes through the
portant factor is redundancy, even though the spray-dryertabsorber.
CO-ON
Control of Pow-Phnt Stack Emisions

--
Although it is clear how the OH- ions in re- where
action 55 are removed through neutralization,
dC/dt = the rate of SO, mass transfer
it is not immediately apparent what happens to
A = the droplet surface area
the Ca+ . The calcium ions must also be purged
+

from the solution in order to allow more lime to Bab = the diffusivity of SO,
C,,,,, = the concentration of SO, in the bulk
dissolve. One of the most important reactions
gas phase, that is, in the well-mixed
is the precipitation of calcium and sulfite ions
gas surrounding the droplet
to form calcium sulfite crystals.
C* = the equilibrium concentration of SOz
that would exist in the gas at the
droplet surface
Ca* + + SO,- CaSO,(s)
(57)
As the droplet first enters the gas phase, the
equilibrium SO, concentration (C*) is zero for
all practical purposes, because of the high pH
It has been observed, as expected, that some of in the droplet liquid. In the liquid phase, the
the SOs- is oxidized to SO;. In turn, SO,- pre- droplets quickly become saturated with SO2
cipitates with the calcium ions to form gypsum and further mass transfer is limited by the rate
(CaSO, 2H20) crystals. Both calcium sulfate of SO, removal from the liquid phase, accord-
and sulfite are relatively insoluble, and in the ing to Eq. 56.
absence of significant chloride ions, calcium- The mass transfer of SO2requires a wet me-
ionic activity is sufficiently small over the life- dium. Once the droplet is dry, a different and
time of the droplet to assure an acceptable rate less understood mechanism influences the rate
of lime dissolution.
of mass transfer, and this new mechanism is in-
Several other reactions also significantly im- ferior to the wet mechanism. consequently, it
pact the perf~rmanceof the process. Among is important that the droplet remain wet long
these are reactions with SOz and calcium sili-
enough to allow the required mass transfer of
cates formed by the chemical combination of SO2to take place.
lime and flyash. Further, the presence of chlo-
The gas-phase heat transfer to the surface of
ride ions in the droplet not only impacts dra- the droplet and the mass transfer of water mole-
matically the ionic activity of calcium, but also cules away from the surface govern the rate of
impacts the vapor pressure of water and of the water evaporation. The rate of heat transfer is
dried reaction products. modeled, in the classical-sense, by
MASS AND HEAT TRANSFER "

Many interrelated factors govern the rate of


SO, mass transfer from the gaseous phase to the
solid crystal (CaSO,.*hH,O) or the dihydrate of
.
gypsum (CaSO, 2H20). In the classical sense,
SO, must diffuse across a laminar gas-phase
boundary layer surrounding the droplet as it is where
passed through the SDIA. This effect is mod-
T = the gas-phase bulk temperature
eled by an SO2diffusion equation
T, = the adiabatic saturation temperature
of the gaslliquid system, generally
assumed to be the temperature at
the surface of the droplet
h = the heat-transfer coefficient
Q = heat content
COMBUSION
Control of Power-Plant Stadc Emiulons

The rate of water mass transfer is modeled by percent of the mass transfer is complete in the
first second of gastslurry contact. It should also
dM/dt = B,, A (H, - H) be obvious that larger droplets (with more
(60) mass) take longer to dry than smaller droplets. - - .
It is the largest droplets which principally con-
cern designers of SDIA vessels, because, if
where these droplets are not dry before the spray
B,,,,,= the diffusivity of water in the gas
cloud intersects the vessel boundaries, then
phase
wet deposits can occur.
H = the absolute humidity of the gas
H,= the saturation humidity of the gas1 PROCESS EFFECTS IN THE SDlA
liquid system
Various process parameters affect the effi-
For a pure waterlair system, the heat and
ciency and economics of the spray dry-scrub-
mass-transfer driving forces are related by
bing process: the type and quality of the
additive used for the reactant, the degree of
H,-H = Q,/X(T - T,) "dryness" achieved by the spray dryer, the
amount of heat available for drying, the relative
amount of solids product recycled to the atom-
where izer, and a host of lesser process variables. The
Q, = the humid heat of moist air impact of these parameters is so important that
X = the,latent heat of vaporization of water it is nearly impossible to estimate the process
This well-known relationship, upon which performance and economics without a sophis-
psychrometric charts are based, has prompted ticated model. Designers thus rely heavily on
some practical designers to simplify or com- performance models derived from pilot-plant
bine the heat- and mass-transfer Eqs. 59 and 60 data. Fortunately, spray dryer pilot-plant drop-
to the form lets look and behave exactly like commercial-
scale droplets. For predicting SO, removal, it
has been determined that process performance
can be scaled up greater than 100 to 1 without
significant risk. On the other hand, physical
scale-up is not as straightforward. Such scale-
where K is a pseudo or combined heat- and up has been the source of most difficulties in
mass-transfer coefficient. In general, K must be the commercial application of spray dry-scrub-
experimentally determined from pilot and full- bing. The following section describes the major
scale operating data, and depends somewhat factors impacting the-process performance..
upon the numerical method used to integrate
Additive Type and Quality
Eq. 62. The integration is usually done through
a finite range of droplet sizes to compute a Any dissoluble base can be used as an addi-
value of T along the droplet trajectory. Integra- tive for the spray dry-scrubbing process; the
tion from initial to final moisture content pro- most important factors are the degree or rate of
vides adequate time for wet-phase SO, mass dissolution and the pH of alkalinity of the dis-
transfer to occur. solved additive. Soda ash and ammonia are
Such integrations provide the system de- both very soluble in water and buffer at rela-
signer with much useful information and afford tively high pH values., Correspondingly, these
the serious student of the process a means to additives have shown to be very efficient when
grasp a deeper understanding of the observed reacting with SO, in the spray-dry process. Of
phenomena. For instance, it can be calculated course, lime is also an acceptable additive,
that, in most practical systems, more than 90 even though it is only slightly soluble. The rate
COMB~ON
Contrd of Powar-Piant Stack Emissions
-
of lime dissolution accelerates when the pH of producing a white (NI-I,),SO:, fume which can
the liquid phase decreases; therefore, lime evade capture in the fabric filter.
works well in the SDIA, though not as well as Lime is available as either a hydrate powder
soda ash or ammonia. In field tests, lime, soda or an unslaked CaO product called "pebble
ash, ammonia, and magnesium hydroxide lime". In general, for moderately sized and
were evaluated in a 7-foot diameter, 3500-acfm large industrial applications, hydrated-lime
pilot-plant SD/A and pulse-jet fabric filter. As costs make pebble lime more attractive, even
shown i n Fig. 34, ammonium hydroxide though a slaking facility is required to hydro-
achieved the highest SO, removal at a stoi- lyze the CaO to Ca(OH),. A further advantage of
chiometric ratio barely half that of the other ad- pebble lime is its higher reactivity. Pilot testing
ditives tested. Soda ash is slightly better than indicates that freshly slaked lime exhibits a su-
lime at equivalent stoichiometric ratios and ap- perior reactivity over powdered hydrate mixed
proaches to saturation temperature. Magne- in water; this has been attributed to the much
sium hydroxide, by itself, is a very poor higher surface area of the freshly slaked lime
performer. slurry over the hydrate mix.
In most parts of the world, the favorable cost
StoichiometricRatio
of lime compared to soda ash and/or ammonia
has dictated its almost exclusive use as the ad- Additive stoichiometric ratio is the most im-
ditive of choice for this process, despite the su- portant parameter affecting the removal of SO,.
perior performance of soda ash or ammonia. Its importance is not because of the magnitude
Soda ash, is competitive only where abundant of its effect on process performance, which is
and easily accessible supplies make it commer- substantial, but more to its effect on process
cially viable. Ammonia could be competitive, economics. In general, control systems of spray
perhaps, in isolated areas where a gasification dry-scrubbers automatically adjust the additive
plant or other chemical plant is located to pro- feed rate (i.e., stoichiometric ratio) to achieve a
vide the ammonia feedstock. Ammonia, how- targeted level of SO, removal. .
ever, has the additional drawback of sometimes
Approach to Saturation

The closer the SD/A operates to saturation


temperature at the outlet, the longer the aver-
SDIA age droplet exists in the SDIA. The behavior of
0SDIAand FF the gas is best understood by examining a con-
100- - ventional psychrometric -chart, Fig. 35. The
flue gas enters the SD/A at temperature Tin and
C
c - humidity H,. As the water from the evaporat-
8 80- ing droplets enters the gas phase, the gas tem-
t
n
-- 60- perature decreases and the humidity increases,
following the adiabatic operating line. The gas
leaves the SDIA at temperature T,, and humid-
a ity H,,, with practically all the water from the
droplets evaporated. The maximum humidity
that the gas could attain is H, and the minimum
temperature is T,, the saturation values. How-
ever, in practice, conventional SD/A's cannot
Typeof Additive
-operate at saturation because the droplets will
Fig. 34 Relative reactivity of dry-scrubbing not all be sufficiently dry. In fact, the drying ef-
additives from test data, also showing the effect of ficiency is directly related to how closely an
downstream fabric filtration SD/A can approach saturation at the outlet.
COAdBUSTION
Control of Power-Plant Stack Emissions

More -important, the SO, removal efficiency Spray-down temperature has a significant
and the additive utilization are inversely re- and direct effect on the SO, removal efficiency.
lated to how close the SDIA is operated to satu- As shown in Fig. 37, there are conditions in
ration conditions. which-an increase of 50F in spray-down tem-
The impact of approach to.saturation is dra- herat'ure can mean a decrease in stoichiometric
matic. Fig. 36 shows that, at a lime stoichiome- ratio from 1.4 to 1.2 at 75-percent SO, removal
tric ratio of 1.4 mols Ca(OH), per mol SO, in the SDIA, all other significant variables be-
entering the SDIA, the SO, removal will im- ing held constant.
prove from 62 to 77 percent in the SD/A simply
by adding sufficient additional water in the Recycle of Solids
slurry to reduce the outlet approach to satura- The practice of mixing some of the fabric-
tion (AT,) from 50" to 25OF. Note that the stoi- filter or ESP solids product with the fresh lime
chiometric ratio can be decreased from'l.4 to slurry has been shown to be beneficial for lime
1.0 at 65-percent SO, removal in the SDIA. utilization. There are several possible reasons:
Spray-down Temperature Some of the, unreacted lime in the recycled
solids is available as it passes through the
The spray-down temperature is the differ- SDIA again.
ence between the SD/A inlet and outlet temper-
atures. It is directly related to the amount of The flyash usually has some alkaline proper-
water supplied to the atomizing system. It is ties which are made more effective when the
also a key indicator of how much evaporative flyash is dissolved in the slurry.
heat is available in the flue gas. Normally, the The silica in the flyash reacts with the cal-
spray-down temperature is not a controlled cium in the lime to form a very reactive cal-
variable unless air-heater flue-gas bypass is cium-silicate compound; andlor
available for this purpose. Most often spray-
The calcium sulfite in the reslurried solids
down temperature is set by the requirements
product serves effectively as seed crystals in
for maximizing boiler efficiency-the lower the
the droplets, which aid in the precipitation of
SDIA inlet temperature, the higher the effective
fresh calcium sulfite (Reaction 57).
boiler efficiency, but also the lower the spray-
down temperature. All of these mechanisms probably play some

Saturation
-
c
80- SRz1.4
Humidity,
Lb Hz0
Line g 75-
70-
-
2 65-
5
a
60-

p "-
50
0 10 20 30 40 50
Ts TOUT TIN Approach to Saturation. " F
Temperature, O F
Fig. 36 Effect of approach to saturation
Fig. 35 Temperature and humidity conditions temperature and stoichiometric ratio on
in a spray dryer absorber spray-dryer absorber SO,-removal efficiency
COMBUSl'ION
Contrd of PowerSI.nt Stack Emissions
-
part in the observed performance improvement Inlet SO2 Concentration
seen with the use of recycle. The performance Inlet SO, concentration has a surprisingly
effect of using a ratio of up to 2 lbs of recycle weak effect on overall system performance. In-
solids for each lb of fresh Ca(OH), solids in the dividual pilot test programs often produce con-
atomizer feed is shown in Fig. 38. For a 2.5- flicting data, usually because the range of
percent sulfur coal, the stoichiometric ratio de- testing is necessarily narrow for any single pro-
creases from 1.2 to 1.0 at 74-percent SO2 gram. Analyzing data from a range of test pro-
removal in the SDIA. grams, however, does show some trends. Fig.
Atomization Quality 39 is a plot of additive utilization from several
independent test programs with other effects
The quality of atomization qffects absorber factored out. There is a slight trend of increas-
performance in two ways: the first and most ing SO, removal efficiency in the SD/A and in
significant is the impact on drying and dryer the combined SDIA and fabric filter as the inlet
efficiency, that is, the minimum AT, achieva- concentration increases. This is not a large ef-
ble; the second is the impact on gas-side mass fect, however, considering that inlet SO2 con-
transfer of SO2and water. Depending upon the centration varies by a factor of 5.
shape of the entrained spray cloud and the ge-
Chlorides
ometry of the SDIA vessel, along with other op-
erating parameters such as the trajectory time The presence of chloride ions in the spray
for the largest droplets and droplet mass- and slurry has a dramatic impact on SD/A perform-
heat-transfer coefficients, an SDIA will have a ance. Chloride ions are not normally present
range of deposit-free operation. in significant quantities in coal- or oil-fired
The minimum achievable operating T, de- applications, but they are a large factor in
pends on the largest droplet in the spray cloud. municipal-solid-waste, some types of
For instance,'a droplet of 120 pmwill result in a hazardous-waste, and refuse-derived-fuel ap-
safe operating AT, of 20F above saturation plications. Hydrogen-chloride concentrations
temperature. By comparing Fig. 38 with Fig. in the flue gas can range from 300 to 800 ppm
36, it can be seen that the operational penalty by volume for municipal-waste flue gases to
associated with poor atomization can have a greater than 10,000 for chlorine-laden hazard-
significant impact on process economics. ous wastes. Often, both SO2 and HC1 are

*
C
9Or -C
90-
g 85- g 85-
SR = 1.2
2
- 80-
SR = 1.1
g 75-
S R = 1.4 SR = 1.0
5
a
70-
SR = 1.2
SR = 0.9
$ "- SR = 1.0
60- I
0 100 200 300 0 1 2 3
SD/A In-Out, O F Recycle Ratio, Lb Recycle/Lb Lime, Dry Basis

Fig. 37 Effect of spray-dryerlabsorber spray- Fig. 38 Effect of recycling of collected solids


down temperature and stoichiometric ratio on on spray- dryerlabsorber SO,-removal -
SOrremoval efficiency efficiency
COMBUSTION
Control of Power-Plant Stack Emissions
t

present together, with removal requirements gas components, as well as with the use of re-
established forboth species. In other instances, cycle solids to improve efficiency.
chlorides are introduced through the use of
high-chloride makeup water and are concen- - PROCESS EFFECTS IN THE
- - PARTICULATECOLLECTOR
bated in the feed slurry when solids recycling
is employed. The spray-dry process employs a particulate
Chlorides in the feed slurry impact operation collecting device after the SDIA to collect the
in two important ways: (1) by changing the ap- dried reaction products and flyash. Through a
parent saturation temperature of the gas leav- mechanism not completely understood, the
ing the SDIA, and (2) by increasing the relative particulate collector is also a reasonable ab-
solubility of Ca+ ions in the slurry liquid.
+ sorber of SO, (and HC1, should any escape col-
Spray-dryerlabsorbers operating with chlo- lection in the SDIA).
rides present in the slurry respond to a different The two types of particulate collectors most
saturation line than systems with only rela- often applied to spray dry-scrubbing are the
tively insoluble salts. This sime type of behav- fabric filter and the electrostatic precipitator.
ior is observed with sodium and ammonium
additives which form soluble salt products
with SO,; however, the deviation in saturation
Fabric Filter ,
I
temperature from the pure-water system is not The fabric filter can be expected to achieve,
on average, from 10- to 20-percent SO, removal
as severe as that when both calcium and chlo-
(based on system inlet concentration) during
rides are present.
An unfortunate corollary of this situation normal operation, with wide variations de-
pending on the operating history immediately
with chlorides is that the apparent saturation
temperature, T,, depends on the concentration prior to a particular measurement.
of C1- ions in the slurry. Hence, the operating Increasing the system stoichiomet~icratio
SDIA outlet temperature needed to assure an from 0.8 to 1.3 causes an increase in fabric-
appropriate approach to saturation temperature filter performance from an average of less than
11percent SO, removal to nearly 14 percent. Of "
(and a corresponding SO, removal efficiency)
varies with the concentration of chlorides. This course, the absorber SO, is also increasing with
concentration varies with the amount of HC1 in increasing stoichiometric ratio, so that the total
the gas entering the SDIA relative to other acid- system removal can easily exceed 90 percent.
The longer the time between cleaning of fab-
ric-filter compartments, the greater will be the
c.
100 - SO, removal; this is because more reactive cake
is available for contact with the flue gas. A dif-
C
. 90- ferential-pressure signal. initiates the cleaning
i? cycle for most fabric filter installations. The
-- 80 - SD/A value of this signal affects the average length of
8E / and FF time between compartment cleaning at a spe-
70-
a
a y S D I A
cific plant load.
60-
P I I
Electrostatic Precipitator

500 1000 2000 Precipitators also remove SO,, although not


Inlet SO2 Concentration, ppm (Vol.),Wet as well as fabric filters. Test data from a number
of sources show an increasing SO, removal
Fig. 39 Effect of inlet SO, concentration on with precipitator specific collecting area
spray-dryerlabsorberSO,-removal (SCA); for example, system SO, removal will
efficiency increase from an average of 5-6 percent to an
ColmJmON
bnbd of PMm-Pknt Stack Emissions

average of 7-8 percent as SCA is increased possible to find a market for all or a large por-
from 190 to 260 ftz/lOOOacfm. tion of the spray dry-scrubbing products for
Since SDIA's were first intended to improve concrete aggregate or road bases. Usually,
the SO, removal of the dry injection process though, the availability of suitable landfill is
(which historically employed a fabric filter), often the deciding factor.
precipitators have only recently been consid- When disposal options are available for
ered as a competitive substitute for fabric filt- either wet or dry scrubbing products, the eco-
ers. This is because of the large number of nomics are driven largely by the other items on
existing precipitators on utility and industrial the list, the most significant being the sulfur
coal-fired boilers; the retrofitting of acid-gas level in the fuel. Since spray dry-scrubbing re-
controls on existing boilers makes a significant quires more reactive additives such as lime or
potential market for SDIA's. soda ash, while the cheaper pulverized lime-
In retrofit applications, it is important not stone can be used for wet scrubbing, the addi-
only to be able to predict the SO, removal per- tive costs of wet over dry scrubbing decrease as
formance of the ESP, but also to project accu- the sulfur level in the fuel increases. Often, de-
rately the new migration velocity in the ESP in pending on the other cost factors, the two pro-
order to predict the retrofit-system particulate cesses can become economically equivalent at
penetration and to determine the need for ESP a fuel sulfur content of 2 to 3 percent by
modifications. Data from a number of SD/A- weight. Below this level, spray dry-scrubbing
ESP test programs show that the SDIA tends to usually has an economic advantage.49
have a centralizing effect on particulate size
REAGENT PREPARATION SYSTEMS
distribution and average resistivity. As a result,
ESP's with poor migration velocities before ret- The reagent preparation systems for flue-gas
rofit are improved, while those with reasonably desulfurization include the handling, storage,
good migration velocities are not improved grinding, slurrying, and feeding of the additive
much, if at all. Consequently, ESP's with good after it has been delivered to the plant site. Ad-
migration velocities but of marginal size will ditives such as lime, limestone, magnesium ox-
probably require some additional collecting ide, and sodium carbonate are prepared with
area in order to accommodate the added partic- such systems. Preparation of the 'most com-
ulate loading from a retrofit SDIA. monly used additives, lime and limestone, will
be described in detail.
ECONOMIC CONSIDERATIONS
LIMESTONE
The economics of wet versus dry scrubbing
involve a great many factors, with these being Limestone is received as crushed rock, typi-
the major ones: cally sized to about l l / z " x 0 or smaller,
waste-disposal options shipped, unloaded, and stored like coal. The
sulfur level in the fuel rock is ground to a fine powder (about 90 per-
8 cost of additives
cent passing through 3 2 5 mesh) i n wet
cost of labor pulverizers.
A closed-circuit wet-grinding system (Fig.
Waste disposal is becoming the most influen- 40) is customarily used to prepare limestone.
tial factor in deciding between wet-limestone The system includes classification so that over-
and dry scrubbing. In many instances, facility sized particles are recycled to the mill. The
planners cannot be assured of adequate land for pulverized limestone is slurried and stored in
waste-product disposal for the life of a power large tanks where the slurry is continuously ag-
.-plant. When the flyash and scrubber products itated. Limestone grinding is generally a batch
must be sold as useful byproducts, spray dry- process and the mill operates at maximum ca-
scrubbing often is not feasible. Sometimes, it is pability until the storage tanks are full.
COMBVSIlON
Control of Power-Plant Stack Emissions

LIME trations in the flue gas. This requires that the


Lime is generally available as pebble lime additive feed rate be metered and matched to
produced in 314" and '12" mesh sizes by the the demand. For process control, a variable
calcining processes. Commercial lime is typi- slurry feed system is desirable.
cally 85 to 95 percent calcium oxide with 0 to 5 The control of a slurry feed does, however,
percent magnesium oxide and 0 to 10 percent have constraints to consider when designing
inerts. The lime is generally fed from the silo to the feed system. A settling slurry, of lime or
a slaker by a variable-speed gravimetric belt limestone, is susceptible to pipe plugging dur-
feeder. The slaker controls adjust the water ing low flow, thus mitigating against large
flow rate to provide a 5 to 15 percent solids turndown ratios. High slurry velocities cause
mixture of slaked lime which is pumped to excessive component wear, which limits slurry
an additive storage tank for use in the desulfur- design velocities.
ization system.
SCRUBBER SYSTEM WASTE DISPOSAL
REAGENT FEED SYSTEMS
Depending on the pFocess used, a number of
FGD operation requires reagent feeding to ' reaction products can result when SO, is ab-
the system at a rate proportional to the mass of sorbed from boiler flue gases. Some of these by-
SO, removed. The feed rate should be varied to products may be marketable while others may
maximize the additive utilization during par- be waste products valuable only as landfill.
tial load operation or changes in SO, concen- When selecting a sulfur-removal process, it is

Limestone a Cyclone Classified Product

Fig. 40 Closed-circuitwet-grinding flow diagram


-.

15-63
coMBl7sXI'ON
ConW of P o w - f I r n t S t r k Emissions

important to consider local sales markets, ap- Variations in waste-solid chemical composition
plicable disposal regulations, and available cause corresponding variations in dewatering
land for disposal. Markets for saleable products and handling which affect the design of dis-
such as sulfuric acid, sodium sulfate, sulfur, posal systems.
and commercial grade gypsum are usually lim-
ited and may be distant from the power plant. DISPOSAL PROCESS SELECTION
Processes that produce a throwaway waste Fig. 41 diagrams several waste-disposal op-
product are relatively simple; and, because the tions for wet FGD systems. The different alter-
plant must already dispose of ash, it can often natives in ponding, landfilling, thickening,
accommodate disposal of FGDS byproducts. and filtering, as well as the structural proper-
CHARACTER OF SOLID WASTE ties of untreated, physically stabilized, and
chemically fixed sludges were presented in de-
The solid byproducts of a desulfurization tail in Chapter 17 of the Third Edition of this
system consist primarily of calcium sulfite, cal- book. Estimates of the relative costs of different
cium sulfate, and flyash, along with minor options and discussions of the impact of waste-
quantities of unreacted additive. Calcium-sul- treatment systems on FGS system design are
fite particles are generally present as thin plate-given in references 50 and 51.
lets which often form aggregates with a When evaluating disposal alternatives, the
rosette-like structure. Calcium-sulfate crystals potential of using waste as raw material in
are thick and rod-shaped while flyash particles other processes should be considered. Al-
are predominantly spherical. though many uses have been proposed, most
The morphology of the waste solids strongly are limited by technical or economic factors.
influences activities such as dewatering of wet- The most promising appear to be
process sludge. For example, the thin platelike gypsum as a wallboard material or a retarder
sulfite crystals settle slowly and tend to retain in cement
water in their clustered structure. The sulfite treated wet-process sludge in roads, dams,
crystalline structure causes a pseudo-thixotro- embankments and the like.
pic behavior; sulfite solids which appear dry Two determinators are involved in consider-
and stable may reliquefy and flow if vibrated. ing waste as a raw material: first, is it possible
The rod-shaped sulfate crystals, on the other to use the relatively large volume of waste ma-
hand, settle more rapidly and retain less water terial produced by a power plant; second, is the
than sulfite solids. Also, sulfate solids do not product competitive with established sources
exhibit thixotropic properties. Fly ash particles of the material? Use of wastes has not become
appear to respond to dewatering somewhere widespread, but a limited number of markets
between that which takes place with sulfite and may exist in selected areas.
sulfate crvstals.
The exHct composition of the waste solids CONTROL OF OXIDES OF NITROGEN
from a particular desulfurization system de-
pends on several operating parameters. The ra- The reduction of NO, emissions from station-
tio of sulfite to sulfate in the waste solids ary combustion sources has .become a critical
depends on the degree of oxidation in the issue in most industrialized nations. As a
FGDS, while the quantity of unreacted additive result, the technology associated with the con-
is a function of additive utilization. Flyash con- trol of nitrogen oxides (NO,) from fossil-fuel-
centrations in the solids may be very low-if fired steam generators has matured and
produced by a system with an efficient partic-= expanded significantly.52.53*54
.
ulate collection device upstream of the FGDS-' - The NO, reduction processes available
or very high if produced by an FGDS which through both in-furnace NO, control, e.g.,
removes both particulate and sulfur dioxide. overfire air, gas recirculation, reduced-excess-
COMBDSTION
Control of Power-Plant Stack Emissions

air firing, gas mixing, low-NO, concentric tan- to coal-fired boilers. To complement existing
gential f i r i n g , staged combustion, and C-E NO, reduction technology, C-E has a li-
fluidized-bed firing; and post-combustion NO, cense agreement with Mitsubishi Heavy Indus-
control (primarily selective catalytic reduction, tries making their low-NO, technology and
or SCR) provide several alternatives for meet- products available to C-E for steam-generator
ing strict nitrogen-oxide emission levels. De- applications.
pending on the NO, emission level required, an
SCR POST-COMBUSTIONNO, REDUCTION PROCESS
optimum NO, reduction system may result in
the integration of several of the above tech- The selective catalytic reduction system uses
niques in the overall plant design. a catalyst and a reductant (ammonia gas, NH,)
After in-furnace NO, control has been imple- to dissociate NO, to nitrogen gas and water
mented, as described in Chapter 1 2 , post- vapor. The catalytic process reactions are as
combustion controls can result in further follows:
NO,-emission reduction. With dry selective
catalytic reduction systems, NO, reductions of
80 to 90 percent are achievable.
4N0,
(9) -
+ 4NH, + OqQ,catalyst 4N%)+ 6H2qQ,
(63)
The SCR process was originally developed in
Japan where strict NO, emission requirements + 4NH3(#,+ 0 catalyst 3NqQ,+ 6H20fQj
2NOqQj
t
-
dictate the use of post-combustion NO, tech- (64)
niques. The SCR system was a developmental
process in which the catalytic systems were Since NO, is approximately 95-percent NO
first applied to natural-gas-fired units, then to in the flue-gas of steam generators, equation 63
low- and high-sulfur oil-fired units, and finally dominates.

Fig. 41 Wet FGDS waste-disposal alternatives


.-
The SCR catalytic-reactor chamber is typi- Catalyst selection is based on the following
cally located between the economizer outlet criteria:
and air heater flue-gas inlet (see Fig. 42). This resistance to toxic materials
location is typical for steam-generating units resistance to abrasion
with SCR operating temperatures of 575 to mechanical strength against sootblowing
750F (300 to 400C).
Upstream of the SCR chamber are the ammo- resistance to thermal cycling
nia injection pipes, nozzles, and mixing grid. resistance to the oxidation of SO2to SO,
Through orifice openings in the ammonia in- resistance to plugging
jection nozzles, a diluted mixture of ammonia Each criterion is the subject of a subsequent
gas in air is dispersed into the flue-gas stream. discussion and involves careful weighing of
After the mixture diffuses, it is further distrib- both economic and reliability characteristics.
uted in the gas stream by a grid of carbon steel Resistance to Toxic Materials
piping in the flue-gas duct. The ammonialflue-
Toxic materials such as alkali metals (specif-
gas mixture then enters the reactor where the
ically sodium and potassium), alkaline-earth
catalytic reaction is completed.
metals, and sulfur oxides carried by dust in the
CATALYST SELECTION flue gas can impair the performance of the cata-
lyst. It is imperative to select.catalysts which
Selection of the proper catalyst for an SCR achieve high NO,-removal performance with-
system is essential not only for economic rea- out significant deterioration from these harm-
sons but also for the reliability of the total sys- ful substances.
, tem. To reduce operating and maintenance
costs, the catalyst should be durable and pro- Abrasion Resistance
vide high activity over a long period of time. Erosion of catalyst surfaces from flyash in

Steam Generator

NH3 Injection Point

To FGDS and
Particulate
Collector

Fig. 42 General arrangement of an SCR system for a pulverized-coal-fired steam generator


COMBUSTION
Control d Power-Plant Stack Emissions

coal-fired boilers decreases the service life of a ammonium bisulfate during operation at low
catalyst. By using a-catalyst with high erosion flue -gas temperatures. The temperatures at
resistance, as well as a dummy catalyst layer which ammonium bisulfate forms vary with
- upstieam of the active catalyst, erosion prob- the amount of SO, in the flue gas. Typically, if
lems can be reduced. It is also appropriate to there is 1ppm of SO, present, a minimum oper-
design SCR systems for low flue-gas velocities ating temperature of 575OF (300C) is recom-
because erosion potential increases as an expo- mended to avoid formation of ammonium
nential function of the gas velocity. bisulfate. As SO, and unreacted ammonia con-

~ Mechanical Strength Against Soot Blowing

Sootblowers for SCR systems are generally


centrations increase, the allowable minimum
operating gas temperatures also rise.
Ammonium-bisulfate deposits on catalyst
required for coal and high-sulfur oil-fired ap- surfaces will cause a reduction in NOx-removal
plications. The catalyst must be designed to performance. Usually, this can be avoided by
withstand the pressures from superheated- either operating the SCR system above forma-
steam or compressed-air sootblowing. tion temperatures or by halting the injection of
ammonia when temperatures are below recom-
~ Resistance to Thermal Cycling

The catalyst must be selected for thermal sta-


mended levels. To minimize the detrimental ef-
fects of ammonium-bisulfate formation on
downstream equipment, adequate clear spac-
bility under all expected operating conditions. ing for heating surfaces, sufficient sootblowers
The ideal SCR operating temperature range is and washing-devices, as well as corrosion-
generally 575 to 750F (300 to 400C). When resistant materials, are recommended.
operating temperatures fall below 575 F, the
potential for ammonium-bisulfate formation on Resistance to Plugging
catalyst surfaces increases. Ammonium-bisul- It is essential to select catalysts with o p k -
fate formation can cause permanent catalyst ac- ings that will not become plugged by the flyash
tivity deterioration when low-temperature in coal-fired combustion gases.
operation is maintained over a period of time. Proper operation of the steam generator as
Typically, an economizer flue-gas bypass is well as careful selection of catalyst material
provided on utility boilers to maintain inlet play significant roles toward achieving high
SCR gas temperatures above acceptable levels NO, removal and low ammonia slip over a long
during low-load operation. Above 750F, am- period of time.
monia gas may dissociate, thus reducing the ef- Once the catalyst material is selected, such
fectiveness of the SCR process. If temperatures criteria as the mol ratio of ammonia to NO,, the
exceed 900 to 1000 (480 to 540C), the cata- volumetric flow of gas to be treated, the enter-
lyst activity may be permanently impaired, due ing flue-gas temperature, the inlet NO, concen-
to sintering of the active catalyst material. tration. and the oxvnen concentration in the
Resistance to Oxidation of SO, to SO, flue gas will affect S-ckNO, concentration, and
the oxygen concentration in the flue gas will af-
It is important to select catalysts that mini- fect SCR N0;removal performance. Each of
mize the oxidation rate of SO, to SO,. The for- these parameters must be considered for the
mation of SO, by the catalyst, combined with proper design of a catalyst system.
unreacted ammonia ("ammonia slip") from the
SCR system, can cause serious plugging and CATALYST MAINTENANCE
corrosion problems on such downstream
equipment as air heaters, electrostatic precipi- A routine maintenance program will help ca-
tators, fabric filters, and ductwork. These prob- talystic reduction systems to achieve high sys-
lems may occur from t h e formation of tem availability. Visual inspection of the
.-
COMBmRON
Control of Pow(~PkntS1Kk Emissions

reactor chamber is recommended during nor- frequently for possible plugging and corrosion
mal boiler outages to ensure that misalignment to assure the reliability of the arnmonia-injec-
of catalyst elements, gas-seal cracks, element tion control system.
clogging by soot or dust, and chipping of ele- The catalyst modules may be moved in and
ment material have not occurred. Another rec- out of a vertical chamber by removing cover
ommendation is the periodic testing of sample plates on the side of the chamber. To facilitate
sections of the catalyst elements to determine handling of the catalyst modules, platforms are
the degree of activity deterioration. When provided at each catalyst stage (see Fig. 43). A
deterioration significantly alters NO,-removal slow-speed hoist attached to the overhead sup-
efficiency, partial catalyst replacement is porting structure lifts each module to the
indicated. Sampling lines of NO, and ammonia proper catalyst floor. The module is then
monitoring equipment must also be checked placed on a trolley which moves on rails per-
manently installed in the reactor chamber. A
suitable number of soot blowers are provided
for each catalyst stage. Each blower is located
eactor Chamber Shell
at a right angle to the direction of module
removal.
SELECTIVE NON-CATALYTIC REDUCTION (SNCR)

SNCR post-combustion methods require the


injection of a reagent into the flue gas stream of
a combustion source to reduce NO, to elemen-
tal nitrogen and water vapor. The predominant
SNCR technologies utilize ammonia gas and
aqueous urea, CO(NH& as the reagents.
The ammonia-based process involves the in-
jection of a diluted ammonia gas with a carrier
medium such as compressed air or steam. The
process is highly dependent upon flue-gas tem-
perature and residence time for achieving high
NO, removal efficiency. An effective temperature
window ranging from 1600-2000F (870-1090C]
is required for these systems. The primary chem-
ical reaction for the process is as follows:

Flow Direction
of Flue Gas
The addition of hydrogen gas will allow the
reaction to proceed effectively down to 1300F
(700C).If ammonia is injected at too high a tem-
perature (above 2000F),it will oxidize forming
additional NO,. .Injection of ammonia below
optimum temperatures will result in increased
levels of unreacted ammonia (ammonia slip)
I exiting the system. Consequently, the location ..
Fig. 43 Typical SCR reactor chamber of ammonia injectors is critical in order to obtain
COMBUSI?ON
Control of Power-Plant Stack Emissions

high NO, removal efficiency across the expected


operating load range. FLOW-MODEL TESTS
Similar to the ammonia process, a second
method requires the injection of an aqueous urea
OF EMISSION-CONTROL
solution over a defined flue gas temperature SYSTEMS
range, typically 1600-2000F.The governing pro- Volumetric gas flow is a fundamental design
cess reaction is as follows: parameter for emission-control systems (elec-
trostatic precipitators, scrubbers, and fabric
filters). It affects not only the system working
efficiency but also the engineering design. The
purpose of a model study is to investigate the
flow characteristics, pressure loss, gas mixing,
and temperature distribution. Usually, a three-
Enhancers or chemical additives can be used dimensional model to 1116th scale or larger is
to extend this window down to 1300F.The ef- used to obtain design information and to insure
fectiveness of this process will be significantly that performance predictions are met (Fig. 44).
reduced if urea is injected outside this tempera- With a flow model, the potential gas-flow prob-
ture range. lems of a design can be identified and engi-
Additional process-design considerations in- neering modifications recommended. A
clude actual flue-gas velocity gradients, boiler flow-model study also can analyze field prob-
geometry, and flue-gas constituents. Careful eval- lems, and is an economic way to decide on
uation of these parameters allows for the proper modifications quickly and accurately.ss
location of urea injectors in order to optimize
MODELING THEORY
reagent utilization for effective NO, reduction
capability. Whenever the flow of a fluid through a

Fig. 44 Precipitator flow model for test of flow-control devices


..
comUsl0N
bnbol d PoworPIant Stack Emissions

model is studied, there must be some assurance velocity changes magnitude or direction. The
that the flow pattern in the model will closely boundary layer in the modeled system will, in
correspond to the actual flow pattern at full general, be proportionately larger than the
scale. To attain the desired similarity, one boundary layer in the full-scale system. This
should attempt to keep the Reynolds number tends to make frictional pressure losses in the
for the flow in the model equal to the Reynolds model higher than full-scale losses. Losses due
number for the full-scale flow. The Reynolds to momentum changes are similar for both
number (Re) is a dimensionless ratio between model and full-scale systems because velocity
the inertial and viscous forces existing in the patterns are similar. For these reasons, pres-
flow pattern and is defined as ~e =qg sure losses predicted by the model tests are
where p is gas density, V is its velocity, its dy- usually conservative.
namic viscosity, and D is the hydraulic diame- In model studies, a number of different
ter of the model. The flow is usually considered instruments are used to measure such vaii-
laminar if the Reynolds number is less than ables as velocity, static pressure, conductivity
2,000; it is twbulent if the Reynolds number is and the like. Many of the devices are similar
above4,OOO. - or identical to the measurement equipment
The combustion gases flowing through a described in Chapter 22, and include hot-
commercial FGD system normally have a den- wire anemometers, pitot tubes and pressure
sity and a viscosity on the same order of magni- transducers, and thermal-conductivity gas
tude as density and viscosity for the air in the analyzers.
model. Therefore, to have the same Reynolds
GAS-FLOW CONTROL DEVICES
number in the scale model as the full-scale
unit, the velocity of the air in the model must In precipitator modeling, flow-control-
be 10 to 20 times greater than it is in the actual devices such as vanes and perforated plates are
unit. This causes difficulties and uncertainties studied. Vanes are placed in the turns of the
in the model study. ductwork ahead of the precipitator to smooth
Because of the large size of most gas-clean- the gas flow and lower the pressure-loss coeffi-
ing systems, the Reynolds number is usually cient.%.s7Perforated plates are veryeffective de-
well into the turbulent region. Experience indi- vices used at the precipitator inlet to reduce
cates that flow pattern and pressure losses for turbulence and improve uniformity of gas flow.
an FGD system can be reasonably predicted if Basically, they provide the essential transition
turbulent (essentially incompressible) flow is from large-scale persistent turbulence to small-
maintained in the model. scale nonpersistent turbulence. Horizontal or
To predict full-scale pressure losses from vertical vanes or gas-distribution panels may
model studies, it is important to consider all also be installed to obtain a desi~ableuniform-
correlating parameters. The physical flow ity in flow.
boundaries and any devices inside the duct In the final stage of modeling, flow visualiza-
work must be modeled to very close tolerance. tion tests that use smoke traces, ground cork,
The flow must be in the incompressible region and string tufts are conducted to locate gross
and, most important, the Reynolds number ef- flow aberrations, to study dust deposition in
fect must be determined. the ducts, and to study hopper sweepage. Vari-
In studying the pressure losses in closed ous configurations of flow-control devices are
channels, it is helpful to note that the losses evaluated until one is found that yields accept-
generally occur from two effects: loss due to able system flow characteristics. Fig. 44 shows
viscous forces and those due to a change in the a precipitator flow model with flow-control
momentum of the gas. The viscous losses occur devices being tested.
in all segments of the duct, while losses due to Flue-gas scrubbers and fabric filters are mod-
a momentum change are present only when gas eled using the same techniques as for precipi-
COMBmTION
Contm! of Power-Plant Stack Emissions

tators except that pressure drops across air as the parcel moves with the existing wind.
demisting elements and filter bags are simu- Vertical dispersion results from a stack's dis-
lated by perforated plates. The experienced charging a warm parcel upward to mix with
modeler will determine optimum turning-vane fresh air at higher elevations.
and baffle arrangements, as well as the size and Certain phenomena restrict dispersion and
configuration of gas inlet and outlet plenums. must be considered when evaluating plant dis-
A front view of a fully instrumented fabric- persion capability. One of the most severe nat-
filter model is shown in Fig. 45. ural impediments is thermal inversion of the
atmosphere. This atmospheric condition re-
stricts vertical dispersion and, as there is gen-
DISPERSION OF EMISSIONS erally little wind during an inversion, it tends
Control of air pollution is not entirely a ques- to trap and concentrate emissions. Further
tion of the quantity of emissions. It is also complicating dispersion is topography such as
related to the ability of the atmosphere to valleys, where emission concentrations can
assimilate them without adverse effects. Emis- reach dangerous levels.
sion control by dispersion requires the opti- To disperse emissions from boilers, very tall
mum combination of such factors as stack stacks have been constructed; their height can
height, buoyancy, climate, and topography. be augmented by a high efflux velocity of 75 to
Such control requires a study of atmospheric 100 feet per second. These factors, coupled
conditions surrounding a power plant to deter- with the buoyancy of the hot flue gas, produce
mine airflow patterns and ventilating capabili- an effective stack height substantially greater
ties of the region. Model studies provide than the physical stack height (Fig. 46). The ef-
valuable assistance to predict the dispersion of fective stack height is the sum of the actual
combustion products and thereby maintain
particulate or gaseous concentrations to pre-
scribed levels.
Dispersion refers to the movement of parcels
of gases, either vertically or horizontally, and
their simultaneous dilution with fresh air.
WIND DIRECTION AND VELOCITY
Emissions are dispersed horizontally into the

Fig. 46 Effective stack height equals actual stack


Fig. 45 A front view of a fabric-filter flow model height plus velocity and buoyancy factors.
stack height plus the height effects due to ve- ume release, they require a different calculation
locity and buoyancy. If the effective height is treatment. Under stable conditions Ah is
g e a t enough, the effluent can "punctur~" an
inversion to disperse at higher elevations.
"Stack meteo~ology"has been used to study
the factors affecting dispersion of gases from
stacks or chimneys. For power plants, the dis-
persion of particulates and SO, must be esti-
mated and compared to federal, state, and local where .
ambient air-quality criteria and regulations. F = buoyancy flux =
Three different calculations are generally re- P -P
quired to estimate a time-averaged concentra- g~.(:r ( y )
(mbec3]
tion of a gas at a location downwind from = stability parameter (sec-2)
stack. First, the plume rise above the stack
g = acceleration of gravity (mlsec2)
must be established; second, the dispersion of
the gas before it reaches the downwind loca- = density of stack gas at stack top (mgl
tion must be found; and third, it is necessary to m31
calculate the time average of the ground-level Po = density of ambient air at stack top
concentration. (mglm3)

DISPERSION CALCULATIONS These equations include the plume-rise


forces attributable to the thermal buoyancy of
The rise of plumes above the top of a stack the plume and the velocity momentum. The
can be calculated with many formulas, but effective stack height (theoretical gas-release
results vary widely if these equations are ap- height) is the sum of the actual stack height and
plied to sources substantially different from the calculated plume rise.
those used in the original testing. Effective Theories based on the assumption that the
plume rise can be obtained from equations mean concentration of material dispersed in a
such as those given in reference 58. diffusion cloud follows a three-dimensional
Small-volume sources having an appreciable Gaussian distribution have been developed. A
exit velocity-but little temperature excess Gaussian formulation proposed by Cramer59 is
above ambient - are essentially momentum jets generally accepted by industry, although other
in a crosswind and the plume rise Ah may be models are available.60,61,62,63,64
calculated as:
OPTICAL PROPERTIES OF FLYASH
Although the optical properties of sus-
pended particles do not affect collector per-
formance, they are important because of their
relationship to the visual appearance of stack
where, in consistent units emissions. Fine particles suspended in gases
D = diameter of stack and exposed to a light beam scatter the light in
V, = vertical efflux velocity at release temper- directions other than that of the original beam
ature (mlsec) and obscure or darken the light as viewed
Us = mean wind speed at actual stack height toward the light source. The visibility of stack
(mlsec) emissions is due to both these effects.
It has been shown both theoretically and ex-
As buoyant plumes have temperatures above perimentally that the light-scattering and ob-
that of the ambient air and involve a large vol- scuring effects increase with the specific
CoMEmON
Control of Power-Plant Stack Emissions

surface of the particles and the size or thickness The light path for a flue-gas plume is the
of the stack plume. The specific surface is de- plume depth (the stack effluent diameter). The
fined as the total exposed surface area of the extinction coefficient includes the absorption
particles per unit mass of dust or dispersoid. It coefficient, and scattering and diffraction fac-
is a function of particle size and increases rap- tors that are known for small solid particles, oil
idly with decreasing size of particles. For fly- mist, and gases.65
ash, the specific surface usually will be The required reduction of flue-gas loading
between about 2,000 and 15,000 cm2/g. As the due to opacity restrictions becomes the govern-
fine ash emitted by most pulverized-coal boil- ing requirement when the stack diameter is in-
ers has relatively high specific surface, it is creased beyond a critical dimension. This is
very effective in its light-scattering and obscur- because the light path x in the above equation
ing properties. The high-volume gas flows becomes larger and, with a constant dust con-
associated with large' steam generators also centration, the opacity increases as the stack
contribute to emissions that have high visibil- exit diameter increases. O q large units, then,
ity above the stack. the required degree of dust loading reduction is
Removing the coarser fractions of flyash usu- greater than on small units. Fig. 47 gives the
ally will not appreciably reduce the visibility of relationships between the Ringelmann num-
stack emissions. For example, an inertial col- ber, opacity and transmittance in percent, and
lector which removes 75 percent of the ash optical density.
only slightly improves stack-discharge appear-
ance. The finer particles below about 10 or 20
pm are not collected, and it is these particles
with their high specific surface which cause
most of the visibility.14
/ 100 80
Transmittance, %
60 40 20 0

OPACITY

Opacity is the percent reduction of light in-


tensity and is defined as:

I, - I
Opacity = -x 100
10
(69)

where
I = intensity of light reaching the observer
I, = original intensity of the light
The reduction of light intensity when the
light is x feet in length is the following:

where
b = extinction coefficient
I
I
Ringelmann
I
I

Fig. 47 Relationshipsbetween various optical


g = concentration of gases emission-measuringunits
a = extinction coefficient for particles (in-
cludes dust concentration)
REFERENCES
"Criteria for the Application of Dust Collectors to Coal-Fired June19-24,1983, Atlanta, GA; alsoasCombustionEngineer-
Boilers: The Results of an IGCVABMA Joint Technical Com- ing publication TIS-7402.
mittee Survey," Proceedings of the American Power Confer-
ence, 29: 572-580, 1967. Chicago: Illinois Institute of 1IKenneth Wark and Cecil F. Warner, Air Pollution: Its Origin
%chnology, 1967. and Control. New York: IEP, 1976.
IndustrialGas Cleaning Institute, Inc. publications: EP-1, Ter- 1%. W. Penney, "Weaknesses in ConventionalTheory of Elec-
minology for ElectrostaticPren'pitators;EP-5, Factors to Con- trostatic Precipitation," ASME Paper no. 67-WAIAPC-I. New
sider When Selecting Electrostatic Precipitators; EP-7, Gas Yo* American Society of Mechanical Engineeis, 1967.
Flow Model Studies; EP-8, StructumlDesign Criteria for Elec- l4 Harry J. White, "Effect of Fly Ash Characteristicson Collector
trostatic Precipitator Casings; EP-9, Power Consumption Performance:' ASME Paper no. 54-A-259. New York: Arneri-
Measurement for Electrostatic Precipitators;F2, Fundamen- can Society of Mechanical Engineers, 1954. Also in: Air Re-
tals of Fabric Collectors and Glossa? of Brms; F-3, Operation pair, 5: 37-50,62,1955.
and Maintenance of FabricCollectors; FGD-1, Flue Gas Desul-
furization Terminology: Gl. Gaseous EmissionsEquipment: 'Sabert Oglesby,Jr.andGrady B. Nichols. A Manual of Electro-
ProductDefinitionsand Illustrations: M-2. CvclonicMechmi- static Preci~itatorTechnolonv. Part I-Fundamentals. Re~ort
cal Dust ~ d l l e d ocriteria;
r M-5, standardized Method ofpar- no. PB-196'380(AFTD-OGIG. Springfield,VA: National ~ e c h -
tide Size Determination and CollectionEfficiencv: WS-I. Wet nical Information Service, 1970.
Scrubber Terminology; WS-3, Basic of W& scrubbers; SabertOglesby,Jr. and Grady B. Nichols, A Manual of Electro-
WS-4, Wet Scrubber System- Major Auxiliaries. Washing- static Precipitor Technology. Pafi 11-Application Areas. Re-
ton, JX,IndustrialGas Cleaning Institute, Inc. port no. PB-196 381 (APTD-0611). Springfield, VA: National
3 John G. Yost and Philip M. Gerhart, "Field PerformanceTest- Technical Inforrnation Service, 1970.
ing of Large Power Plant Fans Using ASME PTC 11," pre- 6' J. P. Gooch andG. H. M&ant, Jr., "Electrostatic Precipitator
sented at ASME-IEEE Joint Power Generation conference, Rapping Reentrainment and Computer Model Studies," Elec-
October 20-24,1985, Milwaukee, IVI; ASME Paper no. 85- tric Power Research Institute Report FP-792, Vol. 3, August
JPGC-m-1. 1978;Palo Alto, CA,1978.
Several sources, including Characteristics of Particles and 17G.W. Driggers, L. A. Hawkins, and R. W. Gray, "Applying
Particle Dispersoids, Stanford Research Institute Journal, Performance Results of C-E Rigid Frame Precipitators over a
Thiid Quarter, 1961:StanfordResearchInstitute,Menlo Park, Wide Range of Coal Characteristics," presented at ASME-IEEE
CA,1961. JointPower Generation Conference, September 25-29.1983,
SCode of Federal Regulations, Title CFR 40, Parts 53 to 80, Indianapolis,IN; alsoas CombustionEngineeringpublication
"Protection of the Environment," rewised as of July 1, 1985. TIS-7418.
Office of the Federal Register, National Archives and Records '8 Kenneth J. McLean, Sunay of Australian Experience in Col-
Administration, U.S. Government Printing Office, Washing- lecting High Resistivity Fly Ash with Electrostatic Precipita-
ton, DC,1985. tors. Final Report. Report no. PB-221 139 (EPPrR2-73-258).
6R. E. Bickelhaupt, ''A Technique for PredictingFly AshResis- Springfield, VA: National Technical Information Service,
tivity," U.S. Environmental Ftection Agency Report EPA- 1972.
60017-79-204, August 1979; Washington, DC,1979. l9 Kenneth J.McLean, "Some Effects of HighResistivityFly Ash
7 H w J .White, IndustriolEIectrostaticPrecipitation.
Reading, onElectrostaticPrecipitatorOperation," Electrostatic Precipi-
MA: Addison-Wesley. 1963. tator Symposium,EPA, Birmingham, Alabama, 1971. Author
address: University of IYollongong, P.O. Box 1144, IYol-
8G. W. Driggers, A. A. Arstikaitis, and L. A. Hawkins, "Com- longong, New South Wales, Australia 2500.
puter Model Use for Precipitators Sizing," Proceedings of
Fourth Symposium on h s f e r and L'tilizotion of Particulate Z. HercegandKenneth J. McLean, "Efficiency of Electrostatic
Control Technology, October 11-14.1982. Houston, TX; also Precipitators and Relationship to Corona Voltage-Current
as Combustion Engineering publication TIS-7252. Characteristics," Presented at the 64th Annual Meeting of the
Air Pollution Control Association, Atlantic City, June 27-
9RalphA. Altman, et al., "Technical Eraulation of Plate Spac- July 1, 1971, Paper no. 71-178. Pittsburgh: Air Pollution
ing Effects on Fly Ash Collection in Precipitators," presented Control Association, 1971.
at Fifth Symposium on b f e r and Utilization of Particulate
11 L. A. Hawkins and H. L. Wheeler, "Characterization of Dis-
Control Technology, August 1984.
charge ElectrodePerformance:Results of Laboratory and Pilot
IOB. Phelan and T. Farmer, "Top ESP Performance Demands Plant Experiments,''-presented at Sixth Joint EPA&PRI Sym-
More Than Opacity Feedback:' Power, September 1989,Vol. posium on Transfer and Utilization of Particulate Control
133, No. 9; McGraw-Hill, New York, NY, 1989. Technology,NewOrleans,LA, February25-28,1986; alsoas
Combustion Engineering publication TIS-PSG86-001.
JosephG. Singer, "Design for Better ESPRabric-Filter Hopper
Operationand Maintenance," presented at Air PollutionCon- ~2 Alan B. Walker, "Operating Experience With Hot -pita-
trol Association '83, 76th Annual Meeting and Exhibition, tors on Western Low-SulfurCoals:' Proceedings of the Ameri-
COMBUSTION
Control of Power-Plant Stack Emissions

can Power Conference, 39: 582-594,1977. Chicago: Illinois pheric l h k p o r t and Chemical 'hmsformation in Acid Pre-
M t u t e of Technology, 1977. cipitation,National Academy Press, Washington, M=, 1983.
Harry J. White, "Electrostatic Precipitation of Fly Ash; Part 11, YC. C. Leivo, Flue Gas Desulfurization Systems; Design and
Section 3: Fly Ash and Furnace~GasCharacteristics," Air Pol- Opemting Considerations. Volume II. Technical Report.
lution Control Association Journal, 27(2): 114-120, Pitts- March 1978. Report no. PB-280 254 (EPA60017-781030B).
burgh 1977. Springfield, VA: National Technical Information Service,
1978.
UC. C. Shale, J. H. Holden, and G. E. Fasching, "Electrical
Resistivity of Fly Ash at Temperatures to 150ooF.," U.S. Bu- 'SF. A. Ayer, comp., Proceedings: Symposium on Flue Gas
reau ofMines Report oflnvestigations7041. Washington: U.S. Desulfurization,Hollywood, FL, 1977.Report no. EPA-60017-
Government Printing Office, 1968. 781058. Springfield,VA: National Technical InformationSer-
vice, 1978.
2' W. F. Frazierand W. Bomwy, "EvaluationofUtility Cold-Side
Electrostatic Precipitators," presented at ASME-IEEE Joint 36G. P. Behrens, et al., "The Evaluation and Status of Flue Gas
Power Generator Conference, October 20-24,1985, Milwau- Desulfurization Systems." EPRI Report no. CS-3322. Project
kee, WI;ASME Paper no. 85-JPGC-APC-3. 982-28, prepared by Radian Corporation,January, 1984.
l6Harry J. White, "Resistivity Problems in Electrostatic Precipi- 37 J. L. Pearson, G. Nonhebel, and P. H. N. Ulander, "The Re-
tation,'' Air Pollution Control Association. Journal, 24(4): moval of Smoke and Acid Constituents from Flue Gases by a
313-338, April, 1974. Non-Effluent Water Process," Institute of Fuel. Journal, 8:
119-156.1935.
Gilbert G. Schneider,et. al., "Selecting and SpecifyingElec-
trostatic Precipitators," Chemical Engineering, 82(11): 94- F. W. Linkand W. H. Ponder, "Status Report on the Wellman-
38
108, May 26,1975. LordIAllied Chemical Flue Gas Desulfurization Plant at
NorthernIndiana Public ServiceCompany's Dean H. Mitchell
28 Y. Goland, "Mechanical and Structural Design Consideration
Plant." Proceedings: Symposium on Flue Gas Desulfuriza-
for Internals in Electrostatic Precipitators," ASME Paper no. tion held at Hollywood, Florida, November 1977. Volume II.
76-WAIPwr-7. New York: American Society of Mechanical Report no. PB-282 091 (EPk60017-78-058b),pp. 650-664.
Engineers, 1476. Springfield, VA: National Technical Information Service,
19 Jason Makansi, "Particulate Control: Optimizing Precipita- 1978.
tors and Fabric Filters for Todav's Powemlants:' Power S D ~ - 39E.F. Aul, et al., EvaluationsofRegenerableFlueGasDesulfir-
l l , York, NY,
cia1 Report, December 1986; ~ c ~ r a w - H i New izationhcedures. Volume 11. Final Re~ort.Report no. EPRI-
1986. (Contains listing of 38 references and papers as sug- FP-272 (V.2). Palo Alto, Ca: Electric ~ower~ese-arch
~nstitute.
gested reading.) 1977.
30 Joint k h n i c a lCommittee of the American Boiler Manufac- "D. C. Borio, et al., "Design of Spray of Tower Absorbers for
turers Associationand Industrial Gas Cleanina Institute, Inc., L i e h e s t o n e Wet Scrubbers:' ASME Paper no. 79-WAI
"Design and Operation of Reliable central-station Flyash Fu-9. New York: American Society of Mechanictd Engineers.
Hopper Evacuation Systems," Proceedings of the American 1979.
Power Conference, 42: 74-85, 1980, Chicago: Illinois Insti-
tute of Technology, 1981. D. A. Burbank and S. C. Wang, "EPA Alkali Scrubbing Test
Facility:Advanced Program - Final Report" (October 1974to
3' J. A. Hudson, et al., "Design Considerations and Initial June 1978),EPk60017-80-115, PB80-204241, May 1980.
StartupofShawneeBaghouses:' Proceedings ofthe American 42DanteFrabotta and Philip C. Rader, "LimeLimestone Air
Power Conference, 42,1980. Illinois Institute of Technology, QualityControl Systems: Effect of MagnesiumonSystemPer-
Chicago, 1981. formance:' ASME Paper no. 76-WAIAPC-10. New York:
Gordon J. Floyd and A. Vandewalle. "Australian Experience American Society of Mechanical Engineers, 1976.
with Fabric FiltersonPowerBoilers," presented at Conference
on Fabric Filter Technology for Coal Fired Power Plants spon- '3 Philip C. Rader, David C. Borsare, and Dante Frabotta, "Pro-
sored by the Electric Power Research Institute (EPRI), July cess Design of LimeLimestone FGD Systems for High Chlo-
15-17.1981. Denver, CO. rides," presented at Coal Technology '82. 5th International
Coal Utilization Exhibition and Conference, December 7-9,
R. C. Carr and W. B. Smith, "Fabric Filter Technology for 1982,Houston, TX; also as Combustion Engineering publica-
Utility Coal-Fired Power Plants, Part 11: Application of Bag- tion TIS-7293.
house Technology in the Electric Utility Industry," Journal of
the Air PollutionControlAssociation,Vol. 31,No. 2, February Philip C. Rader. M. R. Gogineniand K. Poglitsch, ''Coprecipi;
1984; includes 53 references. tation: A Method for Gwsurn Scale Prevention in LimelLime
stone Flue Gas ~ e s u k a t i o nSystems," presented at the
32H. N. Head, EPA Alkali Scrubbing Test Facility: Advanced 72nd Annual Meeting of the American Institute of Chemical
Program. Third Progress Report. September 1977. Report no. Engineers, San Francisco, November 25-29,1979.
PB-274 544 (EPk60017-771105). Springfield, VA: National
Technical Information Service, 1977. "Philip C. Rader, et al., "The Role of Crystallization in the
Design of LieLiiestone Wet Scrubbing Systerns for Flue
33 "Acid Deposition: Atmospheric Processes in Eastern North Gas Desulfurization," Presented at the Symposiumoncrystal-
America," National ResearchCouncil, Committee on Atmos- lization and Energy Systems. 83rd National Meeting of the
CO~oSnON
Contrd of PowerPhnt Stack Emissions

American Institute of Chemical Engineers, Houston, March Rain, March 27-28,1984, Washington, DC;also as Combus-
20-24.1977. tion Engineering publication TIS-7660.
Benjamin F. Jones, Philip S. Lowell, and F d S. Meserole, 33 Suyama, K., et al, "Operating Experience on a Selective Cata-
Experimental and Theoretical Studies of Solid Solution For- lytic Reduction System for Steam Generators," presented at
motion in Lime and Limestone Scrubbers. Volumes I and 11. 1985Joint Symposium on Stationary Combustion NO, Con-
Final Report. Report nos.. PB-264 953 (EPAl60012-761273a) trol, May 6-9.1985, Boston, MA.
and PB-264 954 (EPAi60012-761273b). respectively.
Springfield, IN: National Technical Information Service, " "Selective CatalyticReduction for Coal-Fired Power Plants -
1976. Pilot Plant Results," Report no. CS-4386, Electric Power Re-
search Institute. Palo Alto. CA.April 1986.
C. Lewis, G. W. Driggers, and K. Mr.Malki, "Laboratory
Evaluation of Several Alloys in High Chloride FGD Enviro- 55C. L. Burton-imd R. E. Willison, "Application of Model
ment -Progress Report," presented at Solving Corrosion Studiesto1ndustrialGa.s-FlowSystem.:'ASME Paper no. 59-
Problems in Air Pollution Conh.01 Equipment, sponsored by A280. New York: American Society of Mechanical Engi-
APCA, IGCI, and NACE, Denver, CO. August 11-13,1981; neers, 1959.
also as Combustion Engineering publication TIS-6950. 'Lewis F. Moody, "Friction Factors for Pipe Flow," Tmnsac-
tions ofthe ASRE, 66: 671-684, New York. 1944.
"R. P. Van Ness and'^. C. Bdrsare, "Design and Initial Opera-
tion of Hiah Sulfur Flue Gas Desulfurization Svstems with ST 1. E. Idel'chik, Handbook of Hydraulic Resistance - Coefi-
Lime or ~ i k e s t o n at
e Louisville Gasand ~lectric5
g ill Creek cients ofhcal Reistmce and of Friction. Report no. AEC-TR-
Units 1and 2." ~resentedat75thAnnualMeetinnand Exhibi- 6630. Springfield, VA: National Technical Information
tion of the Air bollution Control Association, r5kw Orleans, Service, 1966.
LA, June 20-25, 1982; also as Combustion Engineering
publication T1S-7140. "Recommended Guide for the Prediction of the Dispersion
ofAirbomeEffluents,sponsored by ASME Aii Pollution Con-
49 G. E. Bresowar, D. C. Born, andK. W. Malki, "Dry Scrubber trol Division, New York: American Society of Mechanical
Design and Application: The C-E Approach," presented at Engineers.
ASME-IEEE-ASCE Joint Power Generation Conference, St.
Louis, MO, October 4 ~ 8 , 1 9 8 1 . 59H. E. Cramer, "A Practical Method for Estimating the Disper-
G. E. Bresowar. P. E. Traccarella, and W. B. Ferguson, "FGDS
sal of Atmospheric Contaminants," Proceedings of the 1st
Selectionand Design for Retrofit Applications," presented at Notional Conference on Applied Meteorology, Hartford, CT,
October 28-29, 1957, pp. C-33-4-55. Boston, MA: Ameri-
CoalTechnology 85, Pittsburgh, PA, November 12-14.1985;
also as Combustion Engineeringpublication TIS-7869. can Meteorological Society, 1957.
W. B. Ferguson, Jr., D. C. Borio,andD. L. Bump, "Equipment G. Sutton, "A Theory of Eddy Diffusion in the Atrnos-
Design Considerations for the Control of Emissions from phere," Proceedings of the Royal Society of London, 135,
.
Waste-to-Enerav Facilities.". ~ m e e d i i n of
lution ~ o n t r o ~ ~ s s o c i a tannual
s the 1986Air Pol-
i o n meGing; also as Combus-
Series A: 143-165.1932.

tion Engineering publication TIS-8189. 61 C. H. Bosanquet and J. L. Peason, "The Spread of Smoke and
Gases From Chimneys," h s o c t i o n s of the Famday Society,
M. D. Mirolli, \IT. B. Ferguson, and D. L. Bump, "Mid-Con- 32: 1249-1263,1936.
necticut Resource Recovery Project," presented at ASME-
IEEE-ASCE Joint Power Generation Conference, Portland, 62 H. Moses and M. R. Kraimer, "Plume Rise Determination - A
OR, October 19-23, 1986; also as Combustion Engineering New Technique\\'ithout Equations," presented at 64th APCA
publication TIS-8194. - Annual Meeting, June 27-July 2, 1971, Atlantic City, v ,
Paper No. 71-61.
PR. G. Knight, et al., FGD Sludge Disposal Manual, Second
Edition, EPRlCS 1515,1980. 63 M. E. Smith and I. A. Singer, "An Improved Method of Esti-
mating Concentrationsand Related Phenomena from a Point
st Paul E. Traccarella and Nancy C. Mohn, "Disposing of FGD Source Emission." Journal of Applied Meteorology, Vol. 5.
Wasteusing Stabilizationand FitionProcesses," presented NO.5, Oct. 1966, pp. 631-639.
at ASME-IEEE-ASCE Joint Power Generation Conference,
Denver, CO, October 17-21,1982; alsoas CombustionEngi- 64 J.S. Touma, "Dependence ofthe Wind Profile Law on Stability
neering publication TIS-7169. for Various Locations:' Iournal of the Air Pollution Control
Associotion, Vol. 27, No. 9, Sept. 1977,pp. 863-866.
53 Michael S. McCartney and Mitchell B. Cohen, "Techniques
for Reducing NO, Emissions from Coal Fired Steam Genera- 6sPhilip A. Leighton, Photochemistry of Air Pollution. New
tors," Proceedings of First International Conference on Acid York: Academic Press, 1961.
CHAPTER 16

Ash Handling Systems -

hapter 3 presented both the physical and the furnace depends on the dust-bearing ca-
chemical properties of coal-ash and the ef- pacity of the combustion gases, on the size and
fects that ash in its various forms can have on shape of the particles, and on the density of the
the operation of a boiler. This chapter describes ash relative to that of the upward flowing gas.
some of the equipment being used for the col- Fig. 2 shows the effects of particle size on ter-
lection and transport of ash, particularly from minal velocity' which is the rate at which par-
pulverized-coal-fired steam generators.
- Heat ticles of various diameter settle in still air.
losses, power consumption, and water use in
operating this equipment also are considered.
Only through complete understanding of the
design and operation of ash-handling equip-
ment, as well as the comparative features of the
many available types, can the large systems cur-
rently being installed be made both more reli-
able and more economical to operate.
There are essentially two types of ash pro-
duced in a suspension-fired furnace: bottom
ash and flyash. Bottom ash is slag which builds
up on the heat-absorbing surfaces of the fur-
nace, superheater, and reheater that eventually
falls either by its own weight or as a result
of load changes or sootblowing. With low ash-
fusion temperatures, a large amount of molten
slag can adhere to the furnace walls and subse-
quently fall through the furnace bottom. {See
Fig. 1) Other ash becomes entrained with, and
carried away by, the flue gas stream and is
Fig. I A large pulverizedcoal-fired furnace viewed
collected i n economizer or dust-collection from above. Ash and slag falling from the walls
equipment hoppers. This is called flyash. pass through the bottom opening into a bottom-
The amount of air-borne ash passing through ash hopper or submerged scraper conveyor.
COLPIlSTION
Ash Hurdling Systems

Coarser particles fall more rapidly than fine. factor) are used to size ash-handling and trans-
Thus, for a given upward velocity, fine parti- port systems. On the other hand, average ash
cles will leave the furnace and coarse particles production rate, which considers the projected
either will drop to the bottom or be thrown from plant capacity factor over the operating life of
the center of the furnace toward the bounding the plant, is used to size disposal sites.
furnace walls. For example, according to the
curve, particles larger than 0.011 in. diameter FUEL SOURCE AND ASH CONTENT
'(not passing through a 50-mesh screen) can be A major factor affecting the choice of an
expected to fall to the bottom when the vertical ash-handling system is the type of fuel to be
velocity of the gases in a furnace is 10 ftlsec. fired. Fig. 3'shows the wide variation in ash
In this regard, a situation occurs in the de- "fired" into a furnace as a function of fuel ash
sign and operation of large pulverized-fuel content and moisture. For example, a boiler fir-
furnaces that is qf interest. As furnace plan ing a 15-percent ash subbituminous coal gen-
areas increase for a given quantity of heat input erates almost three times the total ash as the
(NHUPA), to accommodate a very poor fuel, for same size unit burning a 10-percent ash, high-
example, the upward gas velocities corre- calorific-value, medium-volatile coal.
spondingly decrease. At the same time, the fur- It is usually more meaningful to define ash
nace wall area becomes greater, leading to the content as it relates to energy input rather than
possibility of larger accumulations of slag or on the basis of a weight percentage of the coal
ash on the walls for a given heat input. The alone. The pounds of ash per million Btu fired
greater ash deposits and lesser upward veloci- is arrived at by the formula:
ties that result mean that more ash will fall to
the furnace bottom.
ash (asa %) x 10,000= lbs ash1106 Btu
- HHV (Btullb)

FACTORS
IN SYSTEM SELECTION Relating the ash to be handled directly to the
required heat input gives a realistic relation-
Many factors determine the method of han-
dling and storing coal-fired power-plant ash.
They include Diameter of Particle, Microns (rm)
fuel source and ash content 0 50 100 150 200 250 300
8 plant siting (land availability, presence of 10 -
aquifers, adjacent residential areas)
8 environmental regulations
8 steam-generator size
8 cost of auxiliary power
8 local market for ash
8 cementitious character of the ash
Ash quantities and properties, both physical
and chemical, determine the type and size of an
ash-handling, storage, transport, and disposal
system. They also provide an indication of the
environmental impact associated with ash, dis-_ - -
-
Diameter of Particle,Thousandthsof an Inch
325 200 140 100 60 50
- Equivalent in U.S. Mesh

posal, establish overall system constraints, and


influence disposal site design, Peak ash pro- ~ i g2.. Velocity of air borne particles (specific
duction rates (based on 100 percent capacity gravity 1.2) falling through still air at 70F
COMBDSIlON
Ash Handling Systems

ship to the amount that must be handled as bot- The TSS (total suspended solids) limitations
tom ash as well as that handled as economizer- usually are the most difficult to meet, resulting
and precipitator ash. It also gives an insight to in a trend toward dry flyash systems2. But this
the potential rate of ash..thathas-to be handled consideration does not preclude storage ponds
in the furnace and on convective surfaces. to which flyash can be trucked or conveyed
PLANT SITING pneumatically. Dust is controlled with water
sprays and no net effluent is created.
The available water supply and locations of
an ash disposal site, relative to the power plant, ASH COLLECTION POINTS
can greatly affect the design and cost of ash
disposal. An ample water supply and a great After the combustion process in a suspen-
deal of land are prerequisites of many ash- sion-fired solid-fuel furnace, the ash collects or
handlingsystems. ,
is collected in several areas (Fig. 4).
If land for a plant is limited, ash storage bins Hoppers or conveyors in troughs are used
or small dewatering ponds can be used for tem- under the furnace bottom to collect the material
porary holdup. Trucks or rail cars then are used hlling from the furnace heat-absorbing sur-
to carry the ash away. If there is insufficient wa- faces. This material can be in either a dry or
ter, the flyash must be collected by one of the molten state. If dry, it can be collected in
available dry systems while bottom-ash is col- water-impounded or dry receivers. If molten
lected in a recirculated water system. (from wet-bottom furnaces) it must be directed
into a water impoundment.
ENVIRONMENTALREGULATIONS Hoppers also are used under the pulverizer-
Federal, state and local effluent regulations rejects discharge spout. These collect high-
probably have the greatest impact on installa- density pyrites and tramp iron separated from
tions today and in the future. For example, the coal during pulverization.
Table I lists typical limitations for bottom-ash Hoppers under the rear convection pass and
and flyash transport water. air heater(s) of the boiler are commonly called
economizer and air-heater hoppers. ,It is here
that coarser particles drop from the gas stream
-a,
.- with directional changes in the gas flow.
-
-8 15- Subbituminous
Lignite Moisture)
I
Q (40%
Flyash hoppers included under the pre-
(30%Motsture) cipitators or baghouses collect the material ex-
0'-
13- High-Volatile
rj 11
tracted from the flue-gas stream by these
Q) Bituminous particulate-removal devices.
2 a 11 - (15%Moisture)
EQ
2 $ 9 - Low-Volatile TABLE I.Typical Effluent Limitations
c5 B~tum~nous
; .z 7 - (5%Moisture) Bottom-Ash
Oil and 1 mgl e x Flow (max)
. 3 5 Grease 0.75 mgle x Flow (avg)
LL 0
f .r 3 -
2> .g5 1 I I
Transport pH 6-9
.- 10 20 30 40 5 mgl e x Flow (max)
-a
I

Q) %Ashin Coal (AsReceived) Water TSS 1.5 mgle x Flow (avg)


a:
Oil and
Flyash Grease
0
Fig. 3. Relative ash amounts with various types of
coals, compared to Eastern bituminous coal with Transport
10% ash as a base (corrected for boiler efficiencv). PH 6-9
Figures in are as-received moistdie water TSS 0
contents (by weight) in the coal
. -
CO~VSTIOW
Ash HendNng Systems

QUANTITIESOF ASH Note that the sum of all the assumed


Most pulverized-coal-fired steam generators collection-point values can exceed the total ash
are dry-bottom units in which 20-40 percent of in the coal by 50 percent or more because of the
the ash from the coal falls to the furnace bot- lack of precision of the individual factors, and
tom. Sixty to 80 percent of the ash leaves the to allow for variation in fuel quality.
furnace as flyash. Most of the flyash is collected
ASH DENSITY
in economizer hoppers and one of several
available dust collection systems. Flyash density depends primarily on particle
However, with some fuels less than 20 per- size, particle structure, and-carbon content. In
cent bottom ash has been measured, while with general, the relatively large, coarse particles
certain lignites more than 45 percent bottom containing a high percentage of carbon have a
ash has been reported. As a guide to establish- low density. These particles commonly have a
ing the size of the equipment in the total ash- porous or lace-like structure and result from
handling system, typical collection quantities the partial combustion of the pulverized coal. It
(mass basis) are used. appears that the volatile portion burns out,
For example, the 20-40 percent figure can leaving black coke-like particles. These parti-
vary according to experience with the type of cles have densities of about 35 to 65 lblft3 (true
fuel burned. With low- and medium-volatile density). The finer ash particles, which tend to
bituminous coals, a 15-20 percent bottom ash be low in carbon content. have much higher
figure is appropriate. With a high-volatile densities, usually ranging from 90 to 180 lblft3
bituminous coal a 20-30 percent bottom ash (true density).
figure is used. Systems for subbituminous coal In the hot state, freshly collected ash is nor-
and lignite are sized using a 30-50 percent bot- mally very fluid with a lower density than cold
tomsashfigure. ash-generally between 30 to 50 lblft3 bulk den-
The economizer and air heater ash hoppers sity. The freshash is aerated as the individual
each are sized to collect about 5 percent of the particles are exposed to the gas. With standing
flyash while a precipitator, fabric filter or other and cooling, de-aeration occurs and the ash
equipment would be sized to extract 80 to 100 compacts. It becomes less fluid and can ap-
percent of the flyash from the flue gas. proach bulk densities as high as 90 lblft3.When

Precipitator
Fabric-Filter,

Fig. 4. Ash must be collected and transported from at least the five points shown. In each location,the physi-
cal and chemical characteristicsof the ash vary
Ash Handling Systems

cold, subbituminous coal ash, which is very c. Submerged scraper conveyor-continu-


fine, will usually have loosely packed bulk den- ous, mechanical
sities between 65 and 85 lblft3. Bituminous 2. Pyrites (Pulverizer Rejects)
coal ash, on the same basis, will have a density a. Hoppers with wet sluicing (pipeline or
between 60 and 70 lblft3. open trough)-intermittent, hydraulic
The bulk density of dry bottom ash, as ini- b. Hoppers with manual removal-inter-
tially dropped into an ash receiver, can be as mittent, mechanical
low as 4 0 to 45 Iblft3, but it can compact to
c. Hoppers with dry vacuum removal (in-
above 75 lblft3. A value of 55 lblft3 bulk density
frequently used)-intermittent, pneumatic
is used for establishing bottom-ash hopper
storage capacity. Pulverizer rejects, when prin- 3. Economizer
cipally iron pyrites (iron disulfide, FeS2),will a. Dry pipeline-intermittent, pneumatic
have a bulk density of at least 135 lblft3. b. Dry flight or screw conveyor-continu-
ous, qechanical
,c. Wet pipeline using receiving tanks
TYPES OF SYSTEMS below economizer hoppers-continuous,
The three principal methods of moving ash hydraulic
from the collection points to the on-site dispo- d. Dry pipeline using receiving tanks
sal or storage location are hydraulic, pneu- below economizer hopper-continuous,
matic, and mechanical. In a hydraulic system, a pneumatic
stream of hater conveys the ash in a closed 4. Flyash
pipeline or open sluiceway. Commonly, a jet or a. Dry pipeline, vacuum-intermittent,
centrifugal pump provides the motive force. A pneumatic
pneumatic system transports the ash in a b. Dry pipeline, pressure-intermittent,
stream of air or flue gas induced by either an pneumatic
upstream pressure or a downstream vacuum.
c. Drylwet pipeline, vacuum-intermittent,
The oldest technique for ash removal is the
pneumaticlhydraulic (water exhausters)
mechanical method, the most rudimentary
form being a shovel or hoe, with the more d. Dry, screw or flight conveyor-continu-
sophisticated type being mechanical scraper or ous, mechanical
flight conveyors.
Two basic philosophies have evolved
throughout the world for removing ash from BOTTOM ASH SYSTEMS
pulverized-coal-fired boilers:
A wet bottom-ash system collects and hy-

.
collection, storage and periodic removal, draulically or mechanically removes ash fall-
usual'ly called intermittent removal systems ing from the furnace heat-transfer surfaces.
collection and continuous removal, com- One type-a water-impounded hopper (Figs. 5
monly termed continuous removal systems and 6)-receives, quenches, and stores ash
Ash-handling systems are further differ- from the furnace. In this system the ash is in-
entiated by their conveying frequency and the termittently drained by discharging the water-
conveying medium. The major systems are: ash mixture through an outlet gate to clinker
1. Bottom ash grinders that reduce the size of the materials to
a. Water-impounded hopper with wet pipe- facilitate transport to disposal by jet or cen-
line or sluiceway, to a pond or closed recir- trifugal pumps.
culation system-intermittent, hydraulic The principal reasons for water-impounding
b. Dry hopper, dry pipeline-intermittent, include the following:
pneumatic to break up large pieces of slag by thermal
COMMJ!3'ION
Ash Handling Systems

Drip Shield
\
,Boiler Seal Plate '
I\

t I
Fig. 6 Cross section of water-filled ash hopper under a large.pulverized-coal boiler
COMBUSTION
Ash Handllng Systems

shock as they fall into 'the pool of approxi- pers once each 8-hour shift. Depending upon
mately 140F water the fuel ash content and the boiler load, the
to keep the ash and slag submerged so that usual time required to evacuate a bottom-ash-
they do not fuse into large unmanageable mas- hopper is one to three hours. The hopper vol-
ses that would result if they were exposed to umetric capacity is measured below a mean ash
furnace heat level which is usually 1 2 to 24 inches below the
8 to provide a resilient medium to decelerate
normal water level, depending on the bottom-
the large pieces of slag ash hopper width (see Table I1 and Fig. 7).
It is important to realize that the ash falling
t o assist in the evacuation of ash (from the
from the furnace walls does not pass through
intermittent-removal type of hopper) by reduc-
the furnace bottom opening in equal incre-
ing its effective angle of repose
ments along the length of that opening. Fig. 8
INTERMITTENT-REMOVAL shows that, for a large "open" furnace (one
BOTTOM-ASH HOPPER without a center wall), all of the ash from each
On most pulverized-coal-fired units above sidewall falls through the first 3 or 4 fg6t of the
400,000 lbs of steamlhr, intermittent-removal bottom opening; the ash falling from the front
bottom-ash hoppers are of the V, W, or triple-V and rear walls can be assumed to distribute
design. This design has hopper floors sloping fairly equally along the furnace width. Thus, as
at angles of 35 to 55 degrees allowing gravity shown by the figure, about 25 percent of the
to help remove ash from the hopper. During total ash to the furnace bottom will go through
ash removal the high-pressure water to the the 3 to 4 ft portion near the side wall, and less
jet pump is turned on and the clinker grinder than 2% of the bottom ash will go through each
is started. The control system opens the remaining foot of the bottom "slot". It is of ut-
hydraulic-cylinder-controlled sluice gate and most importance to take this distribution into
the ash flows from the hopper through a grin- account when designing bottom-ash receiving
der into the jet pump, then to a transfer tank, equipment. The normal water level should be
dewatering system, or settling pond. Alterna- at least 30" below the horizontal plane of the
tively, a centrifugal materials-handling pump furnace tubes forming the furnace throat open-
evacuates the hopper and transports the ash to ing (A in Figs. 7 and 9); this dimension is with
the disposal system. the boiler pressure parts in the hot (expanded)
Operating experience with water-filled hop-
pers has shown that most of the ash will flow
toward and through the sluice gates by gravity; TABLE 11. Determination
however, large slabs of fused ash do occur that of Effective Ash Level* -

will not move by gravity alone. Their removal


HopperWidth Inside
requires the assistance of high-pressure (125 Refractory Effective Ash Level (EAL)
psig) water-jetting nozzles located on the slop- (See Fig. 7) Below NWL,ft
ping floors of the hopper. In addition, jetting 71-13'' 0.8
nozzles in the wall opposite each sluice gate 8'-0" 1.0
break up the arching and packing of the ash that 9'-0" 1.2
may occur at the gate. 10'-0" 1.4
Whenever practical the hopper should have
a volume corresponding to the ash produced
during 12 hours of operation at full boiler load
while firing the lowest-heating value and
highest-ash-content fuel for which the boiler is - -

designed. This guideline is based on the nor- 'An interpolation can be made for other hopper widths.
mal practice in the U.S.of emptying ash hop-
COYIrnON ,b

Ash Handling Systems


--
should be designed so that the entire hopper
Water-Cooled and its discharge equipment are located above
Furnace Bottom grade. Pits must be avoided, but if they are used
to put the sluice piping below basement floor
level, their depth should be limited to a
Normal Water maximum of 3 feet.
Effective Ash Level (NWL) OVERFLOW WEIRS
Level (EAL)
To maintain the normal water level (NMTL)in
Ash Hopper Width the hopper;an N\ITLoverflow should be pro-
(Inside Refractory) vided. The bottom opening of the weir is at the
normal water level, Fig. 10. To protect from
Fig. 7. Effective ash level below normal water level
overfilling the hopper and possibly wetting the
varies as a function of ash hopper width (SeeTable II) I boiler tubes, there is a second, independent
"high-water-level" overflow. The opening at
condition. This distance minimizes the amount the bottom of this weir is a minimum of 6
of water that may splash on the furnace tubing. inches above the NWL weir. A conductivity
The hopper is designed with 5 to 10 feet end- device in the outlet box from the high-level
wall submergence to provide a deep pool of overflow provides an alarm when high over-
water at this critical portion of the hopper. flow occurs.
Depending upon the boiler width and head- ASH-HOPPER CONSTRUCTION
room available, the hopper configuration
should adequately provide the needed storage Ash hoppers are constructed of carbon-steel
capacity. Centerwall boilers must have an odd plate with structural framing similar to that of
number of sections. This places the center of a the furnace walls. A high-temperature water-
hopper section underneath the centerwall so resistant gunned or cast refractory, supported
that there is maximum submergence to collect by stainless-steel anchors, lines the sides and
the ash properly from both sides of the wall. bottom slopes. Alternatively, on the sloped bot-
For ease of maintenance, the ash hopper tom portions of the hopper, acid-resistant
bricks backed by concrete can be used.

Sidewall Furnace

I
at Each End - - -.

Fig. 8. Approximate distribution of pulverized-coal


bottom ash along the furnace hopper opening
I
I
~opp& Slope
(Outside) Furnace & Ash Hopper
I
(2

Fig. 9. Schematic arrangement of half of a triple-vee


water-impounded bottom-ash hopper. Dimension A
is defined with boiler in hotlexpanded condition.
I
COmUmON
Ash Hwndllng Systems

A water seal-trough around the upper


periphery of the ash hopper, together with the
High Water Level seal plates hung from the boiler tubes, provides
\
a seal against furnace pressure fluctuations and
accommodates the downward expansion of the
furnace. Nozzles located throughout the seal
trough periodically flush accumulated sludge
and sediment from the trough bottom.
REFRACTORY COOLING
At the top of the hopper is a water-
distribution assembly for cooling the hopper
refractory that extends above the normal water
level (Fig. 11).The curtain of water flowing
over the refractory face aJso retards refractory
.deterioration during extended periods when
the hopper is drained'of water during boiler
operation. The water distribution pipe must be
equipped with a deflection shield to prevent
water from being sprayed on the furnace tubes.
Periodic flushing of this pipe with a high-
volume water flow through a drain connection
in each section insures that pieces of ash do not
clog the holes.
I I Fig. 12, a flow diagram for a single-V type
Fig. 10. Arrangement of bottom-ash hopper bottom-ash hopper, shows all of the water-
overflow weirs and piping flows entering and leaving this hopper. Op-

Deflection
Shield
Distribution P i ~ e
Hopper

Refractory ?not shown)

L I
Fig. 11. Distribution-pipe system for refractory cooling water
COrnrnON
Ash Handling Systems

Refractory Cooling Sections (8) Seal Trough Overflow (2)

Low-Pressure
Supply -
($0 -
Normal Overflow
/&&
A - Slope Nozzle Supply
B -Rear Nozzle Supply
C - Sluice Gate Nozzle Supply
Emergency 0verfloG D - EnclosureWater Supply
E -Clinker Grinder Seal Water
-
F Makeup/CoolingWater
Sluice Nozzles G- Jet Pump Water Supply
H - Seal Trough Supply
J - Refractory Cooling Water
K - Obsewation Port Cooling
L - Seal Trough Drain

High-Pressure ~ u p p-kSeal
l Water~ ~
I I
Fig. 12. Flow diagram of single-vee bottom-ash hopper

timum operation of a water-impounded hopper has to be lowered with this arrangement is


can be achieved by maintaining the water level when it's necessary to visually inspect the
at all times, even while discharging the ash. In hopper interior or to remove over-sized pieces
this way, the design makes use of all the advan- manually. Each end of the hopper should be
tages of water impounding and establishes the equipped with access doors for maintenance.
maximum possible net-positive suction head
on the jet (or centrifugal) pumps at the op- HOPPER SLUICE GATES
timum moment. The only time the water level Bottom ash hopper sluice gates (Fig. 13)
(usually 24" x 24") allow for periodic removal
of bottom ash from the hopper. Around the dis-
charge gates are water-tight steel enclosures
which flood when ash is being discharged.
These enclosures are equipped with access
doors, observation ports, and floodlights and
are designed to withstand negative and posi-
tive pressures. A vent pipe equipped with two
vacuum breakers provides vacuumlpressure
protection. Positive-pressure protection is
achieved by allowing the water in the enclo-
sures to enter the vent pipe to discharge into
the bottom-ash hopper. A loop in the vent-pipe
above the hopper water level prevents water
backflow from the hopper to the enclosure.
Vacuum protection is provided by air check
Frame Renewable Gate Seat valves located at the top of the vent-pipe loop. -
The gate is hydraulically lifted by a cylinder
designed for water service. Limit switches in-
Fig. 13 Bottom-ash-hoppersluice gate dicate a fully open or fully closed position.
COMBUSTION
Ash Handllng Systems

High-wear areas in the sluice gate enclosure are


often made of ceramics or stainless-steel. Removable Access Panel
CLINKER GRINDERS
Single- or double-roll clinker grinders are
provided at the outlet of each sluice gate. The
grinding elements are made from heavy-duty
abrasion-resistant materials,such as work-hard-
ened manganese steel or heat-treated high-
chrome steel. Ash is ground by a shearing,
splitting or crushing action to facilitate hydrau-
lic or pneumatic transport (Figs. 14 and 15).
Because of the severe duty, relatively fre-
quent replacement is required for the wear-
Rake
prone internals of these crushing machines. It Housing
is important to provide easy access for their
removal while the steam generator is operat-
ing. The design shown in Fig. 14 and 15 pro- Fig. 14. Single-roll clinker grinder for reducing size
of bottom-ash; hammers and anvils are replaceable
vides an easily removed front panel for such through removable access panel
access allowing maintenance personnel to re-
place worn grinding elements without entering trifugal pump can be used. The accompanying
the enclosure. box lists the advantages of each.
Shaft bearings are spherical roller type with As more high-ash coal is used for steam-
provisions for forced lubrication. Shaft seals generator fuel-producing greater ash loading
have continuous seal-water flow during on bottom-ash systems-suppliers recommend
periods of both grinder operation and shut- another sluice gate, grinder and pump for each
down. A close-tolerance throttling bushing hopper section. The purpose of this redundant
impedes the flow of small ash particles into the equipment is two-fold: first, to increase the
stuffing box. overall system reliability and, second, to in-
JET PUMPS
A jet pump is a venturi-type solidslfluids
transport device with no moving parts (Figs. 16
and 17). The pump has an inherent low effi-
ciency but this is offset by its non-overloading
characteristic, ease of maintenance, and lack of
rotating parts. For these reasons, the majority of
hydraulic bottom-ash and mill-rejects systems
use jet pumps instead of centrifugal pumps.
To minimize the effects of abrasion, the jet
pump is made of abrasion-resistant alloys. The
inlet section is heat-treated nodular iron
(minimum Brinell hardness of 400); the com-
bining tube (diffuser), high-hardness cast
chrome-nickel alloy material, to a minimum
Brinell of 550.
A jet pump is supplied at the outlet of each Fig. 15 Advanced design of single-roll clinker
clinker grinder; alternately, a mechanical cen- grinder showing external tripod bearing supports
COMBUSnON
Ash HandlingSystems

Ash &Water from Hopper

High Pressure Ash &Water


Water Input Discharge

Nozzle Holder Pump Body

Fig. 16. Schematic arrangement of jet pump for handling abrasive solids

crease the rate of ash-removal when quicker- pipe. Directly downstream of elbows, piping
than-design evacuation is desired. wear is higher than in straight runs because of
the turbulence and impact created at the elbow;
PIPING, FITTING, AND VALVES this calls for more frequent replacement of

. Ash slurry piping is supplied in several downstream runs.


forms. Included are Whenever there is a change in direction in
centrifugally cast chrome-iron alloy with the slurry piping, the fitting located at the

.
hardness ranging from 280 to 400 BHN (Brine11 change of direction will undergo accelerated
hardness number) wear as a result of turbulence and solids-
impact erosion. Thus, fittings, such as 45" and
surface-hardened carbon-steel piping
90" elbows and laterals, are normally con-
fiberglass-reinforced plastic pipe lined with structed from alloy castings that range from
abrasion-resistant material 450 to 550 BHN (Fig. 18).
basalt-lined steel pipe Material hardness alone cannot.provide long
Ash in a water slurry usually travels along life at points of change in direction. To add ad-
the bottom portion of pipes in saltation flow;
that is, it alternately "rests" (settles out) and
"jumps" (becomes re-entrained in suspended
flow). Thus, most wear on slurry piping is on
the bottom third (the lower 120" arc) of the

2
Fig. 18. Chrome-nickel alloy 90" elbow with integral
wearback helps reduce wear from solids-impact
erosion and turbulence experienced with changes
Fig. 17 Jet pump for bottom-ashtransport in flow direction
COMBUSTION
Ash Handling Systems

ditional life to the fitting, the impact area has a loads of the conveying medium. Bevelled-end
thicker cross-section than the normal convey- fittings do not require friction-type couplings
ing pipeline. This thicker section is commonly to secure the fitting to the pipe.
termed an integral wearback. In conveying water-ash slurries, it-may 6e
Fittings can have connections that are either necessary to divert flow or isolate branch lines
plain-end or bevelled-end. When plain-end when multiple sluice lines exist. Industry prac-
sections are used, piping harnesses prevent the tice is to provide heavy-duty knife gate valves
fitting from dislodging due to the reactive for this service because of their profile charac-
teristic. That is to say, when the knife-gate
valve is open, its orifice matches the diameter
COMPARISON OF JET PUMPS VS. of the sluice pipe in which it is installed.
CENTRIFUGAL PUMPS Minimizing the turbulence through the valve
reduces erosion. In addition, the insertion of
ADVANTAGES OF JET PUMPS the valve in the line requires no special adap-
A jet pump is a simple device. There are nG tors or fittings. Also, knife-gate valves can have
moving parts; it is made up of only three prin- bonnets to prevent -leakage from the packing,
cipal components: nozzle. body. and diffuser.
This makes maintenance and replacement and flushing ports for cleaning the seat and the
easier and less expensive than for a centrifugal gate before closing. Manual handwheels or
pump. pneumatic operators are commonly used to
A jet pump can handle air without any de- open and close knife gates. Automatic knife-
leterious effects; lack of suction head is never a gate systems can have limit switches to provide
problem.
feedback to the control system.
A jet pump is self-regulating. The amount of
suction material depends on the discharge When the sluice conveying line is made of
head. The higher the discharge head, the less alloy cast pipe, the couplings between fittings,
suction material will be taken-cvhen there is valves, and plain-end pipe are manufactured
no suction flow, the only flow through the by ash-system suppliers. Where two sections of
pump is the motive (clear water) flow. This plain-end pipe meet, commercial pipe cou-
makes for a self-cleaning action. If the dis-
charge line becomes clogged, the flow of more plings can be used.
material into the pump is limited so that the Any slurry piping system must be designed
motive flow can flush the line. with minimum and maximum velocities in
There are no rotating parts subject to erosive mind. The minimum velocity is that required to
ash. convey the particle in the pipeline without
settling. This velocity is a function af the spe-
ADVANTAGES OF A CENTRIFUGAL PUMP cific gravity of the material being conveyed, the
A centrifugal pump can obtain much higher pipeline size, and 'the slurry concentration.
volumetric capacities than a jet pump. A typi- Typical ash-slurry pipeline velocities are
cal jet pump has a practical limit of about 3,500
gpm discharge flow. Centrifugal pumps can 8 bottom ash-7 to 8 ftlsec
produce flows of 35,000 gpm and higher. 8 economizer ash-6 ftlsec
A centrifugal pump has a higher.efficiency pyrites-9 to 10 fffsec
than a jet pump. Stated in another way, the
power required for a centrifugal pump to con- 8 flyash-4 fffsec
vey a given flow at a given head is con- DISPOSAL OF BOllOM ASH
siderably less than the power required to give FROM HYDRAULIC SYSTEMS
the jet-pump motive fluid the required head
and flow to convey the given mixed water1 Hydraulic ash systems dispose of the ash-
slurry head and flow. and-water slurry in various ways, depending
No separate motive-water pump is required. on the overall plant layout, ecological con-
siderations, and available disposal areas.3 As
previously mentioned, the ecological con-
-.
C0YI)mnON .
Ash Handling Systems

siderations are presently a major influence on normally has vibrators to aid in removing the
decisions made about the means of disposal of dewatered ash.
ash and slurry.
CONTINUOUS-DEWATERINGEQUIPMENT
Most steam-generating plants require either
a recirculating system or monitoring (and In lieu of the intermittent-dewatering bins
treatment, if required) of pond blowdourn. just described, continuously operating dewa-
Recirculating systems frequently include de- tering systems are available using equipment
watering equipment for the mechanical separa- similar to the submerged scraper conveyor,
tion of bottom ash and water. discussed later in this chapter. With continu-
DEWATERING SYSTEMS ous-dewatering apparatus, ash is periodically
removed and sluiced from a batch-storage
Ash from a conveying sluice line can be de- (intermittent-removal) ash hopper to the re-
posited into dewatering bins. As the ash settles, mote dewatering scraper conveyor. The con-
it displaces water which overflows into a veyor dewaters the ash to the same extent as
trough extending around the circumference of with a dewatering bin and places it on a belt
the bin top. The overflow water drains by grav- -conveyor for further handling. Water from the
ity to the recirculation basin or waste drain. dewatered ash overflows the conveyor vessel
A series of baffle plates, concentric with the and is treated further as with dewatering bins.
outer shell of the bin, prevent ash carryover and
undesirable turbulence in the overflow trough. SETTLING AND STORAGE TANK
Submerged beneath the water level, the inner The discharge water from the dewatering de-
baffle inhibits the finer material from reaching vice normally is routed into a settling basin or
the overflow. The second baffle, extending tank. To separate the ash fines, low velocities
above the overflow trough, creates a barrier to are maintained throughout the basin or tank,
retain the floating material before it reaches the which are designed for maximum retention
overflow trough. Eventually, floating material time. Any agitation is confined to a small area.
settles and is discharged through the sluice Water and ash fines are deposited into the
gate after the bin is dewatered. center of the settling tank after passing through
Dewatering bins are installed in pairs. When a cyclone-type separator and baffles. As the ash
one bin is filled, the input flow is diverted to fines settle into the tank, the displaced water
the empty bin. After a short period of natural overflows into a trough which extends around
settling, a level of surface water will exist. This the circumference of the top of the tank. The
surface water is drained off through vertical overflow water drains into the center of the
decanting pipes or floating decanters. ash-water storage tank. As in the case of the
After the surface water is drained, the lower dewatering device, it is important to protect
drain valves in the decanting pipes are au- the settling tanks from freezing.
tomatically opened, resulting in a slow, con-
STORAGE OR SURGE TANK
trolled draining of water from the ash in the
bin. Depending on the composition of the ash In a recirculating system, an ash-water stor-
and the desired moisture content, this process age tank provides sufficient volume to absorb
generally takes less than eight hours. With the volumetric fluctuations of the hydraulic
proper filtration, settling, and chemical treat- ash removal system. In addition, this tank pro-
ment, the overflow water can be recycled to the vides further separation of fines by maintain-
bottom-ash system in what is essentially a ing a low velocity. Again, freeze protection
. -
closed loop. *
must be provided. Centrifugal pumps recircu-
It is important to protect dewatering bins late the discharge water from the surge tank to
from freezing by providing heaters at the bot- supply the jet pumps and other requirements
tom. Also, the lower cone section of the bin for water in the system.
COMBUSTION
Ash Handling System

PONDS OR FILL AREAS With the submerged scraper conveyor (SSC),


Where geological and siting conditions per- ash is evacuated mechanically on a continuous
_
mit, ash can be pumped to ponds or fill areas. . basis so there is no long-time storage in the
Any ash-receiving pond needs a large capacity - water impoundment beneath the furnace. After
to permit the ash to settle by-gravity. The de- discharge from the SSC in a dewatered condi-
sign of such ponds can include recovery and tion, ash is transported by belt conveyors. The
reuse of the water in the ash removal system. major advantages of the SSC are
8 reduced water usage (no transport water)
DRY BOTTOM-ASH HOPPER SYSTEM
reduced power consumption (by eliminating
Dry bottom-ash hopper systems for intermit-
tent removal are used when there is no need to the high-pressure sluicing water required by
the jet pumps)
provide for water impoundment-and less au-
tomation is acceptable', A rule of thumb is that low boiler setting height
dry bottom-ash hoppers are generally practical The C-E Combusco submerged conveyor was
on units rated below 400,000 lbslhr of steam. used in the 1920's for ash removal from stoker-
Customarily constructed of carbon-steel fired boilers. Presently, the C-EIEVT SSC offers
plate, these hoppers, like the hoppers used similar continuous ash removal from pulver-
in a wet system, have a water-seal trough, ized-coal units4 It serves the same functions
complete with flushing nozzles. Unlike water- as the intermittently emptied refractory-lined
impounded hoppers, dry hopper slopes must ash hopper, that is, it seals the furnace bottom,
be steep to 'insure that the dry ash flows to the quenches the falling ash and removes it from
discharge openings. under the furnace.
The inside of the hopper steel plate is lined The most widely accepted SSC configuration
with several inches of insulation. Anchors, has two separated compartments in which the
normally of stainless-steel and welded to the flights and chains move (Fig. 19). The upper
hopper plate, are used to hold 4 to 6 inches of (wet) chamber, containing three to six feet of
gunned refractory lining forming the inside of water, receives the ash falling from the furnace
the ash hopper. and conveys it up the dewatering slope. At the
Ash is periodically removed from the hopper top of the dewatering slope, the flights reverse
through a series of water-cooled discharge direction, dumping the conveyed ash. They
gates. Each gate has a sealed enclosure, a then return through the dry chamber below;
pneumatic operator, an access door, observa- this has open sides to facilitate inspection
tion port, and floodlight. while the equipment is operating (Fig. 20).
At the discharge of the ash gates, grinders Generally, the maximum speed of the scraper
may be provided to reduce any large clinkers to conveyor is about 20 feet per minute, with a
a size that can be handled by a pneumatic or 4-to-1 or 6-to-1 turndown ratio. Operation at
hydraulic conveying system. The grinders are low speed, as a function of low boiler load or
similar in construction but normally smaller low ash content, reduces power consumption
than the grinders under the wet bottom-ash and abrasive wear on both flights and support-
hoppers. Instead of grinders, sizing grids for ing surfaces.
manual handling may be placed at the dis- Travel wheels, when furnished, support the
charge gate outlet. entire conveyor; they ride in tracks or on rails
located in the power-plant floor. The dewater-
THE SUBMERGED SCRAPER CONVEYOR
ing slope on the ash-removal conveyor leads to
FOR CONTINUOUS REMOVAL
a transfer chute or hopper, in which a con-
Another method of bottom-ash removal uses ventional clinker grinder reduces the size of
a flight conveyor of heavy construction sub- the ash. From the transfer chute, the size-
merged-- in a water trough below the furnace. reduced ash is deposited on a belt conveyor.
COMBUSTION
Ash Handling Systems

CONVEYOR CHAIN DESIGN and 45 degrees. The actual physical configura-


tion depends on the unobstructed space avail-
A common SSC chain is the double-stranded
able, boiler-house structural-steel design con-
round link or ship's-type chain made from
siderations, and the method of handling the ash
alloy steel, annealed and carburized to a 550-
after it leaves the conveyor.
600 BHN hardness. Chain couplings, of the
same material as the chain, are designed for SETTING HEIGHT OF STEAM GENERATORS
ash-handling service. The chain is supplied in AS AFFECTED BY THE BOTTOM-ASH SYSTEM
matched sets and undergoes stringent quality
control and testing to insure a long service life. The operation and maintenance of bottom-
Useful life is a function of chain lengthening ash hoppers and associated auxiliary equip-
caused by wear of the inner portion of the links. ment are easier and better when no equipment
The lengthening can result in a mismatch of the is located in sub-basement-floor pits. But, by
chain to the driving sprocket. eliminating such pits it is sometimes necessary
to have boiler setting heights up to 35 feet to
OTHER DESIGN FEATURES
accommodate the intermittent-removal, water-
The flights are commercially available struc- impounded bottom hopper. (Setting height is
tural angles attached to the chains by fittings the vertical distance from the basement floor
provided by the chain manufacturer. level to the centerline of the horizontal
The upper trough of the conveyor has over- furnace-wall tubing directly above the ash-
flow boxes to regulate the height of the water removal equipment; this dimension is meas-
above the flights. Cooling water is added to ured with the steam generator in the "cold"
maintain a normal 140F (maximum 160F) condition, before expansion has taken place.)
temperature. In this respect, the submerged Such generous setting heights are not neces-
scraper conveyor uses exactly the same amount sary with the submerged scraper conveyor.
of cooling water as a water-impounded hopper When SSC's are specified before the boiler is
because the heat presented to the equipment is purchased, the setting height can be adjusted to
exactly the same. save substantial amounts in the cost of t d . . ~
Dewatering slopes are at an angle between 25 structural steel, piping, and ductwork.

Transfer
Chute

Clinker
Grinder

Fig. 19. Submergea scraper conveyor tor bottom-ash removal (C-EIEVT SSC)
COMBUSTION
Ash Eandllng Systems

COMPARISON facilitates access to the interior of the furnace


OF CONTINUOUS- AND through the furnace bottom opening; nor are
INTERMlllENT-REMOVAL the high-pressure pumps or water piping of the
- BOTTOM-ASH EQUIPMENT intermittent hopper (Fig. 12) required.
Continuous mechanical removal permits Because the SSC is designed for continuous
lighter equipment, reduced power consump- removal, provision must be made for continu-
tion compared to hydraulic evacuation, and ous receiving of the ash dropping from the top
eliminates the need for coliveying water. It's of the dewatering slope by belt conveyors or
also possible to observe the ash-removal pro- other similar mechanical devices. The usual
cess without drawing down the water-level. intermittent-removal hopper system in the U.S.
Continuous removal provides "auto-dewater- is operated only 20 to 30 percent of the time;
ing" without the use of dewatering vessels. there is thus a period during which the equip-
In addition, operational control systems for ment is not in operation and is available for in-
continuous removal are simpler than are those spection and maintenance.
on an intermittent-removal system. Moreover, Redundancy of mechanical conveying equip-
the reduced height of the boiler above the ment downstream of the scraper conveyor
basement floor has a savings potential in fuel should be considered to assure continuous ash
piping, duct~vork,structural steel, and build- removal. However, despite the fact that ash-
ing costs. There is also an advantage in being storage is not considered in designing an SSC,
able to move the conveyor to the side at times it can be shut down for short periods to repair
when the boiler is out of operation. This feature downstream equipment.

Fig. 20. C-EIEVT submerged scraper conveyor for 520-MW sub-bitumincus-coal-firedsteam generator is
shown assembled for test operation.
--
demands that the pulverizer-reject system be
PULVERIZER-REJECTS operable simultaneously with the main bottom-
SYSTEMS ashWhen
system.
pressurized mills are used, it is a re-
The pulverizer-rejects system collects and quirement of NFPA 85F-1988, Para. 2-6.1.4(e) to
transports pulverizer rejects (principally py- design the rejects hoppers to withstand 50 psig
rites and tramp iron) hydraulically from the (Fig. 22). To seal out pulverizer pressure during
pulverizers (also called mills). A typical system normal operation, a water-seal overflow box is
(Fig. 21) uses an enclosed pyrites-reject hopper used. This seal box is sized for 120 percent of
located next to each pulverizer to receive and the static pressure specified for the primary air
store the pulverizer rejects for intermittent re-
moval. Removal and transport from the pyrites
hopper is by a jet pump similar to the jet pumps
used in bottom-ash sluicing, but smaller in size
.
fan.
Eachrejects hopper must be equipped with a
level indicator
8 steel grate with approximately 1 ~ square ~ "

..
and conveying capacity. openings to capture large particles for manual
Although the mill rejects may be pumped removal
directly to a dewatering bin or pond, it is more floodlight (for pressurized hopper
common to have all the pyrites-removal jet
pumps discharge to a local collection or trans-
fer tank (Fig. 21). This arrangement permits
emptying more than one hopper at a time.
From this central collection tank, jet or cen-
.inspection port
panel
8 discharge chute to connect the reject outlet
on each pulverizer to the hopper. A pneumati-
trifugal pumps remove the pyrites-rejects to cally-operated gate valve is located in the dis-
the dewatering equipment. ,Discharging charge chute for isolation of the hopper. The
rejects into bottom-ash equipment is not ac- pyrites slurry piping and fittings are similar to
ceptable unless a method can be provided to that ~rovidedforthebottom-ash systems.
prevent splashing of ash-hopper water onto the With suction-type mills, the pyites hopper
boiler tubes above the pyrites injection point. is an open tank to store and collect the rejects
This splashing has caused stress-cracking fail- (Fig. 23). On open hoppers, accessories such as
ure of these tubes. With an SSC, it is practical to floodlights and inspection ports are elimi-
introduce mill rejects outside the water-seal nated. On small steam generators equipped
plates, obviating the problem. with suction mills from which there wcl not be
Plant maintenance and operating flexibility a large amount of pulverizer rejects, a simple

To Fill Area or
Dewatering
Equipment
Jet Pump Jet Pump

Fig. 21. Mill-rejects (pyrites) hydraulic transport system for mill-rejects (pyrites) uses individual pipelines
from each pulverizer to the transfer tank

&!!!a!! 16-1 8
COMBUSTION
Ash Handling System

wheelbarrow may substitute for hoppers. tinuous removal gets the ash out of the hot en-
The amount of rejects from a pulverizer var- vironment of the hopper and prevents further
ies greatly as a function of the type of coal, the combustion of any carbon it may contain. For
type of firing system, the mill, and the way the low-calcium-content bituminous coals, water- . - -
mill is operated. filled tanks beneath each economizer-hopper
outlet, Fig. 24, should be used. The ash is
stored in these tanks for intermittent removal.
REMOVAL OF Unfortunately, wet holding is not feasible
ECONOMIZER-HOPPER ASH with economizer-hopper ash produced by cer-
Economizer ash is usually over 700F, and tain high-calcium lignite or subbituminous
frequently coarse. It sometimes contains com- coal. Some such ash shows pozzolanic and
bustible material. This ash can have the physi- cementitious properties when dropped into or
cal characteristics of furnace-wall ash and the mixed with water, and may require very fre-
chemical characterktics of hygroscopic flyash. quent evacuation from wet tanks to obviate the
It is collected in a row of pyramidal hoppers possibility of plugging. Utilities burning such
beneath the boiler economizer section, usually "concrete-making" high-calcium coals have
at the point of the 90-degree turn in the com- used dry transfer tanks below the economizer
bustion gas flow. hoppers to achieve continuous removal
Formerly, economizer ash was most often without tank or line plugging problems.
handled dry, as an extension of the dry pre- It is important, then, to recognize that such
cipitator flyash system; but, exposed to in- flyash has the potential of producing synthetic
leaking air, it could combust and form clinkers
making it impossible for the ash to flow Inlet Chute from Pulverizer
through the hopper outlets which usually were
only 8 inches in diameter.
Economizer ash should be removed continu-
ously, in a method analogous to the continuous
removal of bottom ash from a hot furnace. Con-

Fig. 22 Mill-rejects hopper for pressurized pulver- Fig. 23.Open-top rejects hopper for
izers, in accordance with NFPA 85F-1988 suction pulverizers
COBQVSllON
Ash Hrndling Systems

silicate rocks that cannot be redissolved and hopper to avoid plugging the discharge line.
flushed out of tanks or transport lines. The ash Because the system operates on a vacuum, only
is in the category of a pozzolan-siliceous or one flyash intake and one conveyor branch line
aluminouslsiliceous material which in itself operate at any given time. As each hopper is
possesses little or no cementitious value but emptied of flyash, the system will step to the
which will, in finely divided form and in the next hopper in the same branch line. When all
presence of moisture, chemically react with hoppers i n a branch line have been emptied,
calcium hydroxide to form compounds having the system will step to the next branch line. The
cementitious properties. system logic. insures the proper sequence of
The best solution to the handling of econ- events and positioning of valves.
omizer ash having concreting characteristics is The intake shown in Fig. 26 uses a micropo-
to remove it continuously from the hoppers rous stainless-steel filter cloth which passes hot
under the high-temperature gas zone into dry fluidizing air into the body of the intake at a
holduplcollecting tanks located beneath the controlled rate. The metallic fluidizing material
economizer hoppers, so as to prevent burning is used because it does not plug or crack easily,
or sintering. The ash can be removed from these as do some other media.
tanks on a n intermittent basis as a branch of the When a mechanical blower produces the nec-
precipitator or baghouse pneumatic removal essary vacuum, flyash is taken to a silo where a
system. Alternatively, the flyash can be re- cyclone separator and bag filter, in series, sepa-
moved continuously from the hoppers by rate the air-ash mixture. To protect the blower it
means of mechanical removal equipment, as is important to collect most of the ash, which is
discussed later in this chapter. then emptied from the silos into enclosed
trucks or railcars.
The water exhauster (Fig. 279 is another
FLYASH REMOVAL SYSTEMS method of transporting flyash through the con-
veying line. High-pressure water supplied to
Flyash from the hoppers serving air heaters, the water-exhauster inlet nozzles creates the
precipitators, and baghouses is removed in-
termittently by either vacuum (negative-pres-
sure) or pressure (positive-pressure) pneumatic
type systems, or combinations of the two. In
addition, several types of continuous-removal
systems such as flight conveyors or screw con-
veyors can be used.
VACUUM SYSTEMS
A vacuum system (Fig. 25) uses a mechanical
blower, water exhauster, or a steam exhauster
to create a vacuum which removes the flyash
from the hoppers. A flyash-intake valve located
at each hopper regulates the flow of the flyash.
Flyash intakes have carbon-steel or cast-iron
bodies and a swing disc which seals against a
hardened seat. For maintenance, the outlet of
each hopper hSs a manual isolation gate.
Each intake is actuated mg. 24, Water-filled tank beneath economizer h o p
by the system logic which controls both the per receives low-calcium-content ash for cooling
flow rate and quantity of flyash leaving the and intermittent flushing
COMBUSTION
Ash HandNng Systems

Cyclone Separators -

Fig. 25 Dry pneumatic vacuum flyash system

transport vacuum; flyash, air, and water are Following the water exhausters, a n air
mixed in the exhauster venturi. Water exhaus- separator is provided to separate and vent the
ters normally have hardened ductile iron air from the flyash-water-air mixture (Fig. 28).
bodies, wear-resistant liners and stainless-steel Separators are made of cast iron or carbon steel
nozzles. Diffusers are hardened ductile iron. with an abrasion-resistant basalt or ceramic
\
liner. The separator discharge is elevated suffi-
ciently to allow the ash-water slurry to flow by
gravity to a pond or disposal area. Flyash slurry
Removable is never discharged to a dewatering bin because
Microporous Fluidizing-Air it is very difficult to settle out the fine flyash
Stainless-Steel particles i n the dewatering bin; most fine parti-
cles would pass over the overflow weir.
PRESSURE SYSTEMS
In a pressure system (Fig. 29). an air-lock
feeder transfers flyash from a hopper at a low
pressure to a pipeline conveyor at a higher pres-
sure. Compressors or blowers provide the air-
flow and pressure.to convey the flyash.

u
Flyash Out

Fig. 27 Water exhauster for vacuum removal of fly-


Fig. 26 Fluidizing-type flyash intake for regulating ash (ash and water are combined in exhauster for
flyash flow from collection hoppers (fluidizing-air transport as a slurry to disposal; upper flange is
plenum is removable for precipitator washdown) high-pressure water inlet; dry ash enters left end)
--
- .

Ash Handllng Systems


--
These feeders are designed with a storage ca- port cycle begins. This exposes the ash to the
pacity based on the desired conveying rate, ash unheated tank metal for the shortest possible
density and number of hoppers to be conveyed time, but keeps the ash in the collecting hop-
in a given unloading sequence. The volumetric pers for the longest possible time.
feeders are controlled to empty each selected In dense-phase transport, the inlet valves of
group of hoppers on a staggered cycle, thus the pressure tanks are kept open whenever the
providing uniform loading into the conveyor tanks are not full. The ash, then, leaves the area
system. Fluidizing air at the inlet and outlet of that is heated by flue gas and drops into the
each feeder insures ash flow. tanks, normally unheated, until the tank level
Vacuum transport systems usually move fly- indicator causes the inlet valve to close; the
ash in a quite "airy" mixture (dilute phase), but filled tank remains at essentially atmospheric
the consistency of the mixture can vary with a pressure until its turn in the transport "queue"
positive-pressure system. For example, the mix- is signalled. The time that the ash remains in
ture might.be in a dilute phase, a dense phase the tank before fluidization and transport will
(in which there is much more ash than air), or depend on the fillinglemptying status of any
the mixture may begin as a dense phase and other tanks on the same conveying line.
gradually change to a dilute phase at the dis-
charge end. COMPARISON OF VACUUM
Many low-velocity, dilute-phase systems AND PRESSURE SYSTEMS
operate at some time in a dense phase because Selecting a vacuum or pressure flyash re-
dense phase occurs whenever saltation takes moval system for a given unit depends on an
place in a pipeline. evaluation of
conveying rate
AIR-LOCK FEEDER OPERATION
altitude
It is customary in dilute-phase flyash trans- a mmber of hoppers to be evacuated
port to use the collecting hoppers for storage; distance to be conveyed
the air-lock tank is used only during the actual Avacuum conveying system is norn~allypre-
ash-moving process. Thus, the inlet valve to ferred over a dilute-phase pressure system be-
the pressure tank is kept closed until the trans- cause less equipment is used under each hop-

Air Heater Hoppers Precipitator Hoppers


Maintenance
Gates Flyash
lntakes
- Fluidizing Air Heaters
Maintenance
Gates
Flyash lntakes
-L,- L --,------
,-------- -- - ---------
I Air Intake I I
M

f
Air lntakes
Water Exhausters
Air Separator L---- High-Pressure Water
- -

TO Ash Storage Pond


I I
Fig. 28 Dry pneumatic flyash transport system using water exhausters as vacuum producers
COMBUSTION
k h Handllng !Systems

full, empty, plugged or ratholed. This is not


possible with a pressure system as multiple
(AlternateBag Filter)-- -1 hoppers are being evacuated simultaneously.
I
I However, the practicality of a vacuum sys-
Vent to Precipitator Inlet
,-------------------- I
I tem is limited by the amount of pressure dif-
I
ferential that is available for conveying. The
actual pressure drop increases as the convey-
ing rate increases; thus, if all else is constant,
higher conveying rates may require a pressure
system. (Theoretically, a vacuum system can
almost always be used by installing many
vacuum-producing devices and pipe-lines i n
Mechanical Air-Lock parallel.) When plants are at high elevations,
Blower or Feeders the available pressure decreases (at 7000 feet,
Compressor' approximately 5" Hg. are lost over that of sea
level), thus limiting the'application of vacuum
systems. In addition, the pressure will drop as
Fig. 29 Dry pneumatic-pressureflyash system conveying
- - distance increases, making a pres-
sure system the more feasible.
per: one flyash intake versus two flyash intakes
and an air-lock tank. Also, a vacuum system To understand a pneumatic transport sys-
tem, it is important to realize that conveying
uses the more positive means of suction to
distance is the total developed length of the
evacuate the flyash from the hoppers whereas a
pressure system uses gravity alone to move the pipeline. In pneumatics, the pressure drop
through an elbow can easily be the equivalent
ash from the hopper to the feeders. Of course
of 50 feet of pipe; therefore, th( optimum sys-
fluidization and rappers are available, but to be
tem would have a minimum number of elbows.
effective they must be used properly.
A vacuum system also has the advantage of VACUUM~PRESSuRESYSTEMS
being able to indicate, from the conveying-line When the number of precipitator or bag-
vacuum switches, whether' a given hopper is house collection hoppers is relatively high

.m
1
Vent
I or ~ a b i i cFilter (
1. A

1
Bag Filter - '
n Primary &
Intake
A; h1.I I secondary
rcyc~Ones
Surge
I Flyash
Silo
lash Intakes 1 Airsln7 Transfer
Tank Mechanical
Exhauster
Mechanical Blower 1
Air-Lock ~ e e d e k 4
n
- - Spray Alternate:
To Fill Area
L I

Fig. 30 Vacuum-to-pressuredry pneumatic flyash system


COMBUSTION
Ash HandIIng Systems

(say, 20 to 40, or more) and the conveying dis- must have no clinkers formed as the result of
tance dictates a pressure system, it is usually oxidation of any combustibles in the ash
economical to provide a vacuum-pressure sys- In power-plant operation, it is frequently dif-
tem, Fig. 30. In this system, a transfer silo is lo- ficult to keep the ash free-flowing. With the
cated close to the precipitator or baghouse and boiler at full load, temperatures as low as 90F
the flyash moves by vacuum from the hoppers have been reported in hoppers of cold pre-
to the transfer silo. At the discharge of the silo, cipitators (those that follow the boiler air heat-
a set of air-lock feeders forms the pressure sys- ers). Similarly, temperatures 20" to 40F above
tem to convey the flyash by pressure to the ambient have been recorded in the hoppers of
main ash storage silos. The capital and mainte- "hot" precipitators (those located ahead of the
nance cost is reduced because of less equip- boiler air heater).
ment under the hoppers (one flyash intake per The problem in the industry is even more se-
hopper vs. two flyash intakes and the air-lock vere with the high-calcium ash associated with
tank). This reduction in equipment under the certain subbituminous coals and various lig-
hoppers can more than offset additonal costs nites. In addition to being highly hygroscopic,
associated with the transfer silo and the posi- such ash shows pozzolanic and cementitious
tive pressure blowers. On the other hand, a properties when exposed to moisture.
vacuum-pressure system uses more power than
a straight pressure system. HOPPER SIZING
FLYASH HOPPER DESIGN Hoppers under precipitators and baghouses
should be considered only as funnels. Because
Problems have been experienced in the re-
of difficulties with removing flyash that has
moval of powdery flyash from hoppers, particu-
been stored for a long time while exposed to
larly with large precipitators on utility steam
flue gas containing moisture and sulfur, rec-
generators. Because of the very high ash con-
ommendations state there be no specified stor-
tent found in many coals, and increasingly
age time in collecting-equipment hoppers.5
stringent particulate-collection regulations,
Minimum hopper outlet size should be 12
precipitators on a large pulverized-coal-fired
inches (diameter or square). In any kase, 6-inch
unit commonly have more than 40 hoppers
or 8-inch outlets should be avoided wherever
(sometimes as many as 128). Research has
possible, unless with identical fuels such sizes
shown that the incidence of hopper operational
proved successful.
and maintenance problems is directly related to
The ideal hopper is square in horizontal
the number of hoppers on a precipitator.5
cross section. Minimum outlet-chute or hopper
Pneumatic ash-removal systems are not de- valley angles should be 5 5 degrees from the
signed to handle wet material. Thus, it is criti- horizontal; 60 degrees if space allows. In any
cal in the design and operation of hopper case, hopper sides should have a minimum
systems to maintain collected material suffi- slope of 60 degrees. In addition, for pre-
ciently above the water or acid dew point cipitators, rounded inside valleys are desirable
to keep it absolutely dry, so that it will be with approximately a 4-inch inside radius.
free-flowing . Such rounded corners are not as necessary with
Dry dust in hoppers ordinarily will flow fabric filters because the continuous air
freely by gravity and be transported pneumati- changes promote ash movement.
cally without difficulty. But to do so, it Stainless-steel linings at hopper corners or
must be kept essentially at the temperature at along the hopper's entire lower portion facili-
which it was collected tate emptying. Because of size of fields, or
must not be exposed to any moisture where a given row of hoppers serves more than
must not compact from its own weight to one field, it may be necessary to include baffles
cause bridging above the hopper outlet in the precipitator. Such baffles should be prop-
COMBUSRON
Ash Handlhg Systems

erly designed and positioned with respect to WEATHERPROOF ENCLOSURES FOR HOPPERS
hopper outlets to prevent bridging. Generally, Many owners add skirts to precipitators or
the baffle plates should terminate 18 inches or baghouses to keep wind and weather from re-
more above the hopper outlets.6 - ducing the hopper metal temperatures. Such
enclosures are highly recommended, although
HOPPER FLUIDIZING DEVICES reducing the heat loss from the hoppers can be
accomplished equally well by judicious use of
A flyash fluidizer, as it is used in a conical or insulation and lagging.
pyramidal hopper, is a porous membrane Skirts also are instrumental in preventing
which allows pressurized airflow through it to hopper plugging. They
be uniformly distributed to the material above, .keep ash-handling hardware from being
filling the voids between the particles at a slight chilled to low ambient temperatures
pressure and changing'theeffective angle of re- provide warmed air from the "hopper room"
pose of the material to promote gravity flow. for pneumatic transport of the flyash, particu-
Properly located fluidizing devices can help larly with vacuum systems
evacuate hoppers (particularly precipitators) , allow inspection and maintenance under
if these devices are ~vell-maintainedand reli- protected conditions
ably supplied with dry air preheated above provide a plenum for hot air ducted from the
dew-point temperatures. If not, fluidizers will top of the boiler house, which then makes
only aggravate evacuation by caking the ash, heated transport air available without addi-
and provide unwanted surface areas for ash ac- tional energy con~umption.~
cumulation and bridging. Where significant
percentages of combustibles are present in the CONTINUOUS REMOVAL OF FLYASH
collected flyash, the fluidizing-medium sup-
ply must be non-oxidizing to prevent destruc- The ideal flyash-removal system is one that
tive hopper fires. takes ash from the receiving hoppers at the
The fluidizing devices referred to are those same rate as it enters. The hoppers then effec-
located inside the hopper, away from the walls tively become chutes and there is no time for
-1~1 extending out into the dust stream; they are cooling, deaeration, or compaction to occur.
i t > ! those in the hopper walls or those integral
There are virtually no such systems in U.S.
with the flyash intake valve^.^ utility power plants, and only a few in certain
industrial boiler or process applications. The
HOPPER VIBRATORS majority of multiple-dust-outlet precipitators
and baghouses have their removal systems in-
When their operation is properly controlled, tentionally designed for intermittent removal
hopper vibrators can help prevent bridging and to miniirlize the power consumed by the ash-
ratholing. In the automatic operation of vac- transpor i system. Such an approach ignores the
uum pneumatic systems, vibrators should be harmful impact on the reliability of collection
regulated by ash-evacuation controls to insure equi 1mt:nt when hoppers are used for storage.
operation only when an "empty hopper" signal Ut lit:/ plants in Europe report good experi-
is generated and the evacuation cycle is com- ence with continuous removal as have some
pleted. Routine use of the vibrators during evac- industria1 installations in the U.S. In these sys-
uation of damp ash will further compact the tems fly ash is transported by either mechanical
ash and make evacuation difficult.' or air-fluidized conveyors, instead of by
It should be possible to manually operate pneumatic-con eying equipment. It appears
the vibrators from each hopper to assist that a princil; 11 feature of such continuous-
maintenance personnel during emergency removal devices is that, with proper valving,
evacuation. they do ni)t allow any substantial amount of air
c0mmRow
Ash Hmdllng Sy.rms

to leak into the precipitator or baghouse hop- AlRlFLYASH SEPARATION EQUIPMENT


pers. This feature maintains the gas tempera- Dual-cyclone continuous-separation mod-
tures in those hoppers above the dew point.5 ules are the primary mechanism to sepa-
Air-fluidized conveyors can be used only if rate the flyash from the conveying air. The
the flyash remains fluid under all conditions of module contains a primary and secondary cy-
start-up, normal load, or shutdown. Although clone separator (Fig. 31). The centrifugal
these conveyors are a form of continuous re- action exerted by the cyclone forces the flyash
moval, there have been numerous problems in to drop as the lighter airflow is extracted from
keeping the ash completely dry during start- the top. By using an airlock the storage silo
up. Also, if ash clinkers form, they are impossi- is never under vacuum and the module can
ble to fluidize and transport. function continuously.
Two types of mechanical conveyors have The bag filter receives the flow from the sep-
been used for conveying flyash-screw convey- aration modules and acts to precipitate the re-
ors and flight conveyors. Often prone to wear, maining flyash from the conveying air stream.
screw conveyors are usually used for ash trans- This tertiary separation protects the vacuum
port only when conveying a relatively small pump from unnecessary particulate carry-over.
quantity of material. Flight conveyors move the The bag filter usually features reversed-air
ash in a dust-tight casing using elements linked cleaning with a good air-to-cloth ratio.
by a single or double strand of chain..The units The vacuum-producing device (blower, vac-
are sized either on a volumetric basis or on an uum pump, exhauster) which has pulled the
en masse basis in which the material is con- flyash air mixture down the pipeline and
veyed in bulk, without agitation. Flight convey- through the discharge equipment, is located at
ors have been successfully operated for many the side or underneath the silo.
decades on coal-fired units, both in North On a pressure system, somewhat simpler fil-
America and Europe. When properly designed, tration equipment is used. Vent fans and motor
they are relatively insensitive to problems such drives are mounted on top of the storage silo.
as moisture in the flyash and flyash clinkers The vent fan should be designed to handle not
(which may force outages in other types of only all the air displaced in the silo'by the con-
systems).8 veying input stream and silo fluidizing air, but
With continuous conveying devices, the sys- also the static head required to transport it back
tem can combine the mechanical conveyor to the precipitator inlet duct. The vent fan
with a pneumatic pipeline. Mechanical devices places the silo under a slight negative pressure,
have the ability to move the ash "uphill" to the eliminating the possibility of blowing dust out
top of a storage silo. of the silo. Vent-fan operation can b e synchro-
nized with that of the conveying blowers. Alter-
FLYASH RECEIVING AND STORING nately, the vent fan can discharge to a bag filter
EQUIPMENT atop the silo.
Flyash storage silos and their related acces- SILO FLUIDIZATION
sories form an integral part of ash-handling Flyash, when not allowed to agglomerate
equipment. Silos are made of concrete or steel, and when fluidized with heated air, takes on
depending upon size, seismic condition, and the flow properties of a fluid. To expedite
plant economics. flyash removal, troughs with fluidizing air are
On vacuum systems, equipment is required provided at the bottom of the silos. Tradition-
to separate the-flyash-from the conveying air ally, the fluidizing element was constructed
stream before it can be discharged into the silo. of canvas or porous stone. But recently, the in-
This equipment, located on top of the silo, dustry has been using porous laminates of sin-
normally has several stages of separation. tered stainless-steel-wire cloth such as used in
COMBUSRON
Ash Handllng Symms

flyash can be removed dry into enclosed vehi-


-
cles, or so that it can be moistened (to 12-15
percent moisture by weight) for transport in
open vehicles. It is increasingly common for
flyash to be sold for use in landfills, roads and
the cement industry.
Primary Telescoping ash discharge chutes convey fly-
Separator ash dry from the storage silo to a removal vehi-
Secondary cle stationed below. Normally, each chute is
Separator capable of extending a full eighteen feet using a
Primary motor-driven-winch retract system. A blower
Receiver and piping in each chute vent, back into the
silo, any fugitive dust released during the un-
loading process. An air-operated gate controls
Fluidizing the inlet flow to the chute and is placed just be-
Manifold low a manual maintenance gate. A clean-out
compartment should be included between the
maintenance gate and control gate. This com-
Dump
Valve partment should contain a grid to trap large
clinkers that may form in the silo, and a n access
door for their subsequent removal.
FLYASH CONDITIONERS
Rotary ash conditioners, Fig. 32, add mois-
Fig. 31 Dual-cyclone module for continuous sepa- ture to the flyash discharged from the storage
ration of flyash and transport air (used on vacuum- silo into open-top vehicles. The conditioning
pneumatic systems) and moisture prevent any fugitive-dust nui-
some flyash intakes. This provides a micropo- sance. An orifice feeder controls the rate at
17s filter that allows controlled amounts of which the dry material moves from the silo into
lted air to pass and fluidize the flyash. The the mixing drum of the conditioner. A series of
;ibility of stress cracking that is common atomizing nozzles within the drum spray the
mth fluidizing stones is eliminated with this material with water as the drum rotates. A lon-
metallic material. Because of the microporous gitudinal scraper bar along the full length of
construction, the metallic cloth is highly resis- the drum plows damp material from the side of
tant to blinding; in addition, water will not the drum, causing it to be mixed thoroughly .
penetrate into the porous openings. This will with 'he spray water. The continuous tumbling
allow washing of equipment with water with- actio , of he wetted material within the drum
out having to remove the fluidizing element. resulc , in ninimal dust at the conditioner out-
let. S: ~p plates prevent any tendency for dry
Fluidizing-air blowers and associated heat-
mater 11 to cascade through the drum before
ers provide the required air to the fluidizing air
being horoughly mixed with water. Mounted
troughs. Care must be taken to properly size the
on a c ntial support, the scraper bar and stop
blowers to account for a full head of flyash in
plates sre readily removed.
the silo.
Fluidizing hoods, normally one above each
silo discharge opening, minimize the possibil-
OPER 4PIOF.IAL CONTROLS
ity of avalanching, which would adversely af- Ash-hondlin,: controls range from com-
fect the operation of the unloading equipment. pletely manual to completely automatic sys-
Silo discharge equipment is designed so the tems of either the relay, s o l i d state, or
--

. 16-27 ---
ABI
COMDDSRON
kh H ~ d l l l t gSystems

/
Thrust Roller
Trunnion Bearing
Discharge Chute
I
Fig. 32 Sectional side elevation of rotary-type flyash conditioner
1

programmable-controller type. section to record the amount of time it takes to


When selecting the type of control system empty each section. By comparing the time to
and the degree of automation that should be empty one section with that of other sections,
employed, many factors should be considered. it's possible to spot signs of trouble.
First; the more automated the plant, the less Similarly, on a vacuum pneumatic system,
attention paid by the plant operators. If little the operator can make a check b y examining
attention is paid to ash systems, breakdowns the strip chart that records the vacuum in the
are inevitable and, when breakdowns occur, pneumatic pipeline. As vacuum can be related
the operators may lack enough knowledge of to the ash flow, the operator can easily deter-
the system to take corrective action. For mine the removal rate and time required to
intermittent-removal bottom-ash and pyrites empty each hopper. Inconsistencies in removal
systems many utilities select a push-button au- time andlor removal rate per hopper are signs of
tomatic system in which the operator, at a local a problem.
panel, performs the ash-removal sequence. The On multifield precipitators, programmable
operator can judge by the crushing sound of the controllers can be used to advantage. As the
grinder, whether each hopper section has been front fields will collect ash at a much faster rate
emptied. If a problem arises, the operator is on than the rear fields, the operator may choose to
hand to analyze itand take action. alter the sequence in which hoppers are "vis-
In some cases density meters are installed in ited" by the ash removal system. Such adjust-
the discharge line of each bottom-ash hopper ments accommodate unequal distribution
COMBUSTION
Ash Handling System

across the fields, or compensate for fields being overflow or leakage points
removed from service. 8 the heat removed with the accumulated bot-
Continuous removal systems obviously re- tom ash as it is discharged
quire the least sophisticated controls, but onloff 8 the heat loss by radiation and conveciion
switches, indicating lights, and alarms should from the outside metal surfaces
be provided. Programmable controllers are
The last loss is small and is usually neglected
rarely justified with such systems.4
in view of the unknown accuracy of some of the
other assumed factors.
MATERIAL- AND ENERGY- Fig. 33 is a simplified heat-balance diagram
BALANCE CONSIDERATIONS around a bottom-ash receiver, in this case, a
Water-impounded ash-receiving equipment submerged scraper conveyor with continuous
beneath a furnace, as previously stated, helps to ash removal. The heat balance forms the basis
quench the ash as it falls from the furnace and for the calculation of the cooling-water flow
to transpoG'it to a disposal point. The thermal needed to maintain a temperature of about
140F (60C). In Fig. 33
shock to the hot ash as it enters the low-
temperature water helps to break up the large
pieces, while submerging the ash prevents sin- Q i n = Q out
tering during the time that it may be stored (2)
(with intermittent-removal systems).
where
Part of the heat released in the furnace is
transmitted to the ash hopper by radiation from Q i n = Q ash entering + Q furnace radiation f
the burning fuel, but most of the heat input is +
Q inlet water = Qae Qfr + Qiw
from the sensible heat given up to the water by and
the hot bottom ash falling from the furnace. The +
Q out = Q overflow water Q ash Icaving f Q evaporation
ash-systems engineer must perform a heat bal- +Q external radiation loss + Q water i n ash leaving
ance to determine the flow of cooling water = Q o w +Qar +Qe +Qer +Qaw
rrT*ilired to absorb the incoming heat and
lntain the water temperature at a predeter-
led level.
Field experience indicates that the tempera- Bottom- Furnace
Ash Flow Radiation
ture of the impounded water should be opti-
mally about 140F, and should not be higher
than 160F. Temperatures at this level are effec-
tive in rapidly cooling and fracturing the fall-
ing ash. Lower temperatures require more
cooling water; higher temperature may prove
uncomfortable or unsafe in the area around the
bottom-ash receiver.
BOTTOM-ASH
COOLING SYSTEM DESIGN
Heat is removed from bottom-ash hoppers or Radiat~onand
Convection Overflow
submerged conveyors by Loss Water Out
evaporation of water from the surface of the
water pool Fig. 33 ,te:idy-? ate heat-balance diagram for
8 the heat removed in the water going out the furnace Sotiom-, 3h receiver
--
kh Handling Systwns

MASS AND ENERGY TERMS FURNACE RADIATION TO THE IMPOUNDED WATER


Furnace radiation passing through an open-
Before equating and simplifying the above ing in the hopper bottom varies with firing rate,
inputs and outputs so that they can be mathe-
matically manipulated, it is necessary to define furnace and firing-system configuration, and
and discuss them further. the effective center of the fuel-admission noz-
zles or burners in operation (measured verti-
HEAT IN THE BOlTOM ASH cally above the furnace-bottom opening). The
The mass of bottom ash, Mba,is the collection heat transfer is
rate, lbhr or kglhr.

Qac =Mbo C ash, (Thotash - Tr)


(3)
where:
where Af, = furnace hopper-bottom aperture above
C ash, = specific heatof the ash at the mean the ash receiver
temperature between T hot ash and T, Rf = radiation rate through furnace aper-
T hot ash = the temperature of the falling ash or ture, Btulhr-sq ft
slag as it enters the water pool F,, = fraction of radiation transmitted to
T, = reference temperature for defining water surface through the space be-
heat contents tween the furnace bottom and the wa-
The temperature of ash leaving the bottom of ter, Fig. 34.
a furnace depends on the thickness of the A typical value for R,, the heat radiated
pieces dislodged from the walls, the face-metal through the bottom aperture to the space above
temperature of the furnace walls, the tempera- the impounded water, is 20,000 Btukr-sq ft.
ture of the sootblowing medium, the distance Fig. 34 shows that the radiation reaching the
of fall, and the average gas temperature sur- water surface decreases as that surface is lo-
rounding the material during its fall. For pul- cated farther away from the aperture, as would
verized coal fired in suspension (without the be expected.
use of furnace-bottom grates), the temperature HEAT IN COOLING WATER
is estimated to be between 1200Fand 1800F, The mass of incoming cooling water, from '
averaging 1500F. Obviously, the validity of all sources (including any refractory-cooling
the heat-balance cal~ulationdepends on this water or SSC bearing-flush water), is desig-
temperature to a great extent. nated Mi,.
The heat of the cooled bottom ash exiting the
collection device is

Qal = Mba X C ashl X (t out - Tr)


(4)
where:
Ti, = incoming water temperature
where Ci, = incoming water specific heat
C ash, = specific heat of the ash at the mean The mass of cooling water leaving, Mom in-
temperature between t and T, cludes any outward leakage, but not the water
where entrained by the exiting bottom ash; the latter is
-
t out = temperature of the water and ash shown as Ma, the mass of heated water leaving
leaving with the ash.
COMBmoN
Ash Handling Systems

where
Qow = Mow X Cow X (tow- Tr) and A, = total area of ash-receiver water surface
Qaw = Maw x Cow X (tow - Tr) - Re = evaporation rate per unit of surface
- - > (71 area
h,, = latent heat of vaporization of water at
where Tow
Cow= specific heat of water leaving
tow = temperature of the impounded water SIMPLIFICATION
OF THE HEAT-BALANCE EQUATION
HEAT LEAVING IN EVAPORATEDWATER If T, the reference temperature, is equal to
The rate of evaporation from a water pool to, the water temperature in the water pool,
below a large coal-fired furnace is a complex Qal, Qow, and Q,, go to zero, then,

function of the water temperature, the tempera-


ture of the radiating gas, and the other factors Qae + Qjr + Qir = Q11
involved in the determination of the radiation or
' =+ LMiw X Ciw X (tow - tiw)]
Q~~ + Q ~ ~ Qe
rate. In general, rates between 4 and 10 U.S. (9)
gallonslday-sq ft are to be expected. Large
pieces of slag falling into the water can result Note that the mass of water leaving, Mow must
in additional localized evaporation, which is not be less than zero; that is,
neither calculable or separable from the overall
effect. It is calculated by Mow = (Miw- Mow - MA 20
(10)

where
Me = mass rate of evaporated water

Curve is for VW 25 ,

Wats Si, 1

z r1=11
O e { h $ h 5 6 7 8
HAN
--
Fig..34
. Curve to determine faction of radiation transrr,.ttedto as.3-re~h e r water surface
In a closed-loop cooling-water system, M,,is incoming ash (not taking into account the radi-
the amount of water that must be cooled and re- ation and evaporation heat exchange), to point
circulated. The extent of physical cleanup and out how great is the difference between the two
chemical treatment applied to this recirculated postulated conditions.
water is principally a function of what the sys- If the ash-system was designed to provide the
tem heat-transfer and'pumping equipment can maximum cooling water at all times, the pump-
.tolerate. Generally, the cleanup required for the ing power consumption would be considerably
low-pressure cooling stream of an SSC is much greater than needed. Because the purpose of the
less than that for an intermittent-removal hop- cooling water is to maintain the ash-hopper
per with slope jetting nozzles, which use water water at a temperature such as 140F,it is logi-
at high pressure. cal to regulate the flow on a demand basis. This
Recirculation equipment size and cost are is done by monitoring the overflow water
sensitive to the ash temperature and quantity, temperature and modulating a supply valve.
the furnace radiation absorbed, and the evap- Tlie system design has to provide for the worst
oration rate, as shown above. It is important case (maximum cooling water), but the actual
that economic comparisons of such loops be water use will only be as required, thereby sav-
based on equivalent boundary conditions, ing pumping power and the cost of cleanup of
which include, in addition, the inlet water and the ash-receiver overflow water under many
impounded water temperatures. load conditions.
It is fairly accurate, for these heat-balance
calculations, to use 0.25 Btullb-OF for the spe- PROPER INSTALLATION
cific heat of ash, 1.0 as the specific heat of wa- It is important to state that any ash-removal
ter, and 1014 Btullb as hhat 140F. system must be installed, set up, checked out,
COOLING-WATER FLOW VARIATION and deemed ready for use by1a plant startup
Two inputs to the equation can vary widely, crew. There have been many reports of damage
greatly affecting the cooling-water flow. First, to boiler pressure parts and precipitator ele-
the bottom-ash collection is a function of ments, with consequent unit shutdowcs caused
quantity of fuel burned (boiler load and heat- by well-designed ash-removal systerhs that were
ing- value of the coal) not ready for use.9
percentage of ash in the fuel Also, ash, by nature, is a very abrasive ma-
terial and wear and replacement of worn com-
p e r c e n t a g e of the total ash that falls to the ponents are inevitable. Plant personnel must
furnace bottom perform regular inspections of these wear com-
Second, the cooling water temperature can ponents and make replacements as necessary.
vary substantially from summer to winter, and
with geographical area.
TABLE 111. Cooling Water Usage*
The designer is faced with the problem of de-
ciding what should be used for ash-collecting High Use Low Use
rates and the water temperature to the hopper.
The common design approach requires excess Coal burned, lblhr 750,000 200,000
water because the designer uses maximum Ash content, percent 25 10
values for all calculations. Systems so designed Cooling water temperature, O F 90 50
will pump and treat excessive quantities of Ash down, percent 50 30
water when the unit is burning a good fuel Bottom ash collection, lblhr 93,750 6,000
in winter when thecooling water is cold. Cooling water flow, U.S.GPM 1,275 45

The potential difference in cooling water *Approximate, based on absorbing heat from incoming ash at
1500'F only: no radiation or evaporation considered. Ash receiver
usage is illustrated in Table 111. This data con- water temperature l40P.
-
siders only the water necessary to cool the
Ash Handllng System1

REFERENCES
1 E. H. Tenney, "Pulverization and Boiler Performance," SJoint Technical Committee of the American Boiler Manu-
FSP-54-7, Proceedings of the Fourth National Fuels Meet- facturers Association and Industrial Gas Cleaning Insti-
ing, Feb 11 to 13,1931, pp. 55-65. Chicago, Illinois: The tute, Inc., "Design and Operation of Reliable Central
American Society of Mechanical Engineers. 1931. Station Flyash Hopper Evacuation Systems:' Proceedings
E. G. Bailey, "Present Status of Furnace and Burner Design of the American Power Conference, 42:74-85, 1980. Chi-
for Pulverized Fuel," FSP-50-72, Transactions of the cago: Illinois Institute of Technology. 1980.
American Society of Mechanical Engineers, September to 6J. G. Singer, "Design for Better ESPIFabric Filter Hopper
December 1928, p. 177. New York: The American Society Operation and Maintenance:' presented at Air Pollution
of Mechanical Engineers. Control Association 76th Annual Meeting and Exhibition.
2 W. E. Loftus, "Ash Handling, Storage and Utilization." Atlanta, June 19-24. 1983; also as Combustion Engineer-
Proceedings of the American Power Conference, 38:707- ing publication TIS-7402.
717,1976. Chicago: Illinois Institute of Technology. 1976.
'J. G. Singer and A. J. Cozza, "Ash-Handling Options on
3 J. G. Singer and A. J. Cozza, "Material and Energy Balances Retrofitted and Converted Steam Generators," presented at
of Ash-Handling Systems," presented at the Joint Power ASME-IEEE-ASCE Joint Power Generation Conference, St.
Generation Conference. Dallas, Sept. 10-13, 1978; also as .Louis, October 4-8, 1981; also as Combustion Engineering.
Combustion Engineering publication TIS-5822. publication TIS-6869. .,
4 J. G. Singer and A. J. Cozza. "Design for Continuous Ash
Removal: Alternative Concepts in Ash Handling:' Pro- 8J. C. Fleming and D. M. Rode. 'Ash Removal from Indus-
ceedings of the American Power Conference, 41: 544-553, trial Boilers-the Changing Scene," Power, Vol. 126, No. 9,
1979. Chicago: Illinois Institute of Technology. 1979; also September 1982. New York, McGraw-Hill, 1982.
as Combustibn Engineering publication TIS-6211A.
9M.B. Caron, A. J. Cozza, J. G. Singer, and J. R. Young, Jr.,
J. E. Horne and A. Bosso, "Southwestern Public Service "Steam-Generator Availability as Affected by Ash-
Company Pioneering in Continuous Bottom Ash Re- Handling Equipment," Proceedings of the American Power
moval,'' presented at Frontiers of Power Conference, Octo- Conference, 44:214-225, 1982. Chicago: Illinois Institute
ber 11 a n d 12, 1982, Stillwater, OK; published as of Technology, 1982; also <as Combustion Engineering
Combustion Engineering TIS-7261. publication TIS-7118.
CHAPTER 17

Metallurgy and Materials

u he aim of the designer of a large steam-


generating unit is to use materials and
fabricating methods in the most economical
way to produce a unit that will perform
sign and details of construction, there needs
to be a close interaction between the designer
and such material-performance disciplines as
metallurgical, corrosion, welding, and mate-
properly for its planned useful life. Achieving rials engineering. All available materials data
these objectives requires a fundamental evolved through experience and research must
knowledge of material properties and behavior be used in order to properly select materials
under a wide range of manufacturing and ser- and to specify construction details, fabrication
,'
vice conditions. procedures, destructive and nondestructive
With only a few exceptions, steel is the mate- tests, and operating limits and controls neces-
rial used in the construction of pressure parts sary for satisfactory service.
and support members for boilers. Selection of This chapter presents some of the many con-
the appropriate type of steel involves the fol- siderations relating to the selection of materials
lowing considerations: and their operation in service, and describes
typical field-service difficulties. Chapter 26 de-
the degree of difl-icultyor ease with which a scri5es the type of laboratory facilities that are
particular materi*.!canbefabricatedorwelded use to \)btainthe materials and metallurgical
mechanical properties of the material such dat -eq' ired for boiler design. .
as strength (including tensile, yield, fatigue, --
creep, and creep-rupture strengths), ductility,
and toughness
SP :C FICA-UONSAND CODES
compatibility with the expected service envi- TI fi st boiler explosion took pl :around
ronment 1701 in a British mine in which a primitive
effect of fabrication practices on mechanical steai I-o.,erated pump had been installed. Over
and corrosion-resistance properties the I 2x 100 years, there was increased use of
possible degradation of properties caused by boilers t i s Latior:aryinstallations, but it was the
long-time service exposure. loss of :sfe resu Ltingfrom marine boiler explo-
sions i~ the ear' y 1800's that led to a pioneering
Because these material-related consid- Am~ricuninve ;tigation by the Franklin Insti-
erations are so fundamental to both basic de- tute of Perlnsylvania in 1830.
COmmON
Met8llugy and M8terials

Many state laws subsequently were enacted these materials specifications, either as written
to regulate boiler construction and operation, or with modifications, to establish recognized
but not until the period 1911-1914 did the grades of materials applying to their code rules
ASME Boiler Code develop.' Originating ba- for design, allowable stresses, fabrication
sically as a safety code to prevent boiler explo- methods, and inspection.
sions, the ASME Code today promotes the The American National Standards Institute
acceptance of properly designed equipment on (ANSI) publishes a variety of standards, many
a national and international basis by assisting of which apply to boiler and pressure vessel
in the standardization of safety rules. construction or related uses. Standards such as
As formally adopted in 1915 and since ad- ANSI B31.1 (Code for Pressure Piping), the
ministered by the ASME, the Code included ANSI B16.5 (Steel Pipe Flanges and Flanged
many of the earlier regulations and resolved Fittings) and ANSI B16.34 (Steel Valves) are
many of the conflicts in the rules. Since that frequently used. Several agencies of the United
time, a majority of the American states, as well States government also publish codes and
as the Canadian provinces, have adopted boiler specifications for certain equipment used in
laws which make the ASME Boiler and Pres- their power plants and other facilities.
sure Vessel Code the basis of their legal re- A basic limitation of all codes is that their
quirements. The rules of the ASME Code are rules must be expressed in sufficiently general
kept up to date by continuing review of the terms to cover a wide range of applications.
Boiler and Pressure Vessel Committee, a group Because they define only reasonable mini-
representing a balance of material suppliers, mum standards, there are sure to arise cases in
fabricators, users, insurers, and enforcement which a power-plant designer must make
jurisdictions. This group sponsors regular re- further investigation and exercise additional
visions of the Code to keep up with technical effort. A great variety of supplementary infor-
advancements and responds to questions of in- mation is available from publications of the
terpretation of the rules. various engineering societies and from techni-
In America, administration of code require- cal bulletins of equipment suppliers.
I
ments is the responsibility of the individual
state in which the boiler is to be installed, and MATERIALS OF CONSTRUCTION
the National Board of Boiler and Pressure Ves-
sel Inspectors coordinates this effort. Fossil boiler equipment in electric-gener-
Another technical group, the American So- ating service operates at high pressures and
ciety for Testing and Materials (ASTM), in- temperatures, generally between 2000 and
corporated in 1902, prepares and publishes 4000 psig, and 1005" and 1055"F, at the
specifications for purchase, testing, and exam- primary-steam outlet. The material grades
ination of a variety of materials. This activity, listed in Table I are widely used in boilers de-
which is directly related to the Society objec- signed in North America; there are extensive
tive of promoting knowledge of engineering data and both shop and field experience with
materials, is carried on through committees these ferritic and austenitic steels.
which include representatives-of producers, RAW MATERIAL FORMS
fabricators and con~urners.~ Similarly, Com-
mittees of the American Welding Society write The product forms of steel available to the
specifications for welding consumables. designer include plates and sheets, forgings,
Such specifications are widely used to pro- castings, seamless and welded tubing and pip-
cure and acceptance-test materials to meet de- ing, and rolled and extruded shapes. All are
fined levels of quality, thereby promoting both limited in size by the facilities and capabilities
safety and economy. Groups such as the ASME of the various material suppliers. Table I indi-
Boiler and Pressure Vessel Committee also use cates several product forms with specifications
COMBUSTION
Metallurgy and Materials

covering the procurement from the ASME terms of outside diameter and minimum wall
Boiler and Pressure Vessel Code, Section 11, Ma- thickness.
terials, and from the ASTM specifications. Pipe sizes and wall thicknesses are standard-
-. ized with consideration of threading ends
PLATES - - .
for joining together lengths with such fittings as
Plates are used in the fabrication of boiler flanges, nipples, valves, tees and the like. Such
drums and plate-formed headers. The plates fittings are generally not installed with tubing.
used to fabricate the shell and heads of these Where pressure-tight connections must be
drums are as thick as 8 inches. Boiler drums are made, tubes are welded together, or their ends
made of carbon-steel plate, usually either SA- are expanded into tube sheets.
515 Grade 7 0 or SA-299. Selection of the material used depends upon
During the plate-rolling process in the pro- the actual metal temperature to be sustained.
ducing steel mill, discontinuities and heter- The steam-generation tubes are primarily of
ogeneities i n the ingot are elongated i n carbon-steel material in recirculation-type
the direction of rolling. Because of this, plates subcritical-pressure units. In low-temperature
may exhibit what is called directional or regions the superheater and reheater tubing is
anisotropic properties and may be weaker also of carbon-steel analysis. As steam temp-
when tensile tested across the thickness than erature increases to the outlet value, selection
when tested parallel or transverse to the direc- then progresses through carbon-molybdenum
tion of rolling. These directional discon- steel, then low chromium-molybdenum steel,
tinuities bare generally not harmful except intermediate chromium-molybdenum steel,
when they are large enoughin size to affect heat and finally austenitic stainless steel, depend-
transfer or are excessive in quantity so as to af- ing upon the design metal temperatures in
fect weldability. The customary practice for the various areas. Austenitic stainless steel
heavy plates used in boiler applications is to contains sufficient amounts of such alloying
apply selective magnetic-particle and ultra- elements as nickel and chromium to retain
sonic examinations to determine that the austenite, a solid solution of carbon in gamma
material is free of excessive discontinuities i n iron.
ar u s where welding will be performed. See For many years, Grades TP 321 and TP 321H
C,iiapter 18, "Steam Generator Manufacture" for austenitic stainless steel had been used for
d .tails on drum fabrication and testing. high-temperature service. But changes in the
ASME Boiler Code allowable stresses have fa-
TUBING
vored Grades TP 304H and TP 347H, with these
Steam is generated, superheated, and re- latter grades most widely used at present. Al-
heated in steel tubing, commonly between 11/2 t h igh
~ Grade TP 316H is seldom used in the
and 3 in. outside diameter. Large units may re- tu! 1g qrtions of the superheater, it has been
quire as much as 300 miles of such tubing. The an ~ i continue
l to be used when austenitic
tubing is designed to last thelife of the unit (upto sta es: piping and headers are required for
30 or more years) even though, in the case of ster; I tc lperatures of 1100F and higher.
superheated-steam tubing or po-vver-plantpip-
ing, it is operated atavisibly "red-hot" tempera-
FOF 311 GS
ture sometimes above 1100F. Bc le drums and similar vessels may use
From the standpoint of geometrical shape forg ng for reinforcing rings around openings
and physical construction, there is no essential and nt zzles; some moderately sized high-
difference between pipe and tubing. Pipe sizes pressur: vessels are made entirely by ! ging.
are generally designated by their nominal in- In mos Gases, .he largest opening requirc d for a
side diameter for a particular type of service. boiler rurnis ,in access opening of about 16 in.
Tubes, by contrast, are usually specified in inside di: ~neter,which is reinforced by a forg-
.-
COrnrnON
'* Metallurgy and Materials

ing welded to the drum head. Forgings are also supported by developments in nondestructive
used for fittings, valves and flanges. testing such as radiography and ultrasonic
examination. Some parts and attachments in
CASTINGS boiler service are exposed to high temperatures
Castings have not been widely used as boiler approaching the local gas temperature. Heat-
pressure parts except in special applications resistant alloys such as 25% Cr -12% Ni (AISI
such as valve or pump bodies, where the rela- type 309) are required for such items. As is
tive ease in forming thick-walled spherical and common in many industry publications, steel
other special shapes has been an advantage. of this type will be referred to throughout this
Techniques in casting steel have improved, chapter without the percentage qualifier as 25

Table I.Materials Used in Boiler Construction

ALMY Pmdud ASME Grade Minimum Minimum Composition, % (a)


Form or Tensile Yield
ASTM Strength Strength
Spec. ksi C hIn P S Si Si Cr hlo

Carbon Sled Tubes SA-192 . . . (47) (26) 0.06-0.18 0.27-0.63 0.048 0.058 0.25 ... ... ...
Low-Strengfi Tubes (ERW) SA-178 A ... ... 0.06-0.18 0.27-0.63 0.050 0.060 ... ... .., ...
Tubes(ERW) SA-226 . . . (47) (26) 0.06-0.18 0.27-0.68 0.050 0.060 . . . ... . ~. . ..
Intermediate Tubes SA-210 A-1 60 37 0.27 0.93 0.048 0.058 O.1OMin . . . ,.. . ..
Strength Tubes (ERW] SA-178 C 60 37 0.35 0.30 0.050 0.060 . . . ... ... ...
Pipe SA-106 B 60 35 0.30 0.29-1.06 0.048 0.058 O.1OMin . . . ... ...
Castingslb) SA-216 WCA 60 30 0.25 O.iO 0.040 0.045 0.60 .. . ... ...
Structural
Shapes A36 .. . 58 36 0.26 . .. 0.040 0.05 .. .
Hilh Strength Pipe SA-106 C 70 40 0.35 0.29-1.06 0.048 0.058 O.1OMin . .. ... ..,
Plate SA-299 ... 75 40 0.30 0.86-1.55 0.035 0.040 0.13-0.33 .. . ... ..,

Plate SA.515 70 70 38 0.35 0.90 0.035 0.04 0.13-0.33 ... . .. . ~.


Forging SA-105 .. . 70 36 0.35 0.60-1.05 0.040 0.050 0.35 ... ,.. .. .
Casting (b) SA-216 ~VCB 70 36 - 0.30 1.00 0.04I1 0.045 0.60 :,, .,. ...
FERRITICALLOYS
CO.5Mo Tubes SA-209 T1 55 30 0.10-0.20 0.30-0.80 0.045 0.045 0.10-0.50 .,. . ... 0.14-0.65

1Cr-0.5 Mo Forging SA-336 F12 70 40 0.10-0.20 0.30-0.80 0.040 0.040 0.10-0.60 ... 0.80-1.10 0.45-0.65
Tubes SA-213 T12 60 30 0.15 0.30-0.61 0.045 0.045 0.50 . .. 0.80-1.25 0.44-0.65
Pipe SA.335 PI2 60 30 0.15 0.30-0.61 0.045 0.045 0.50 ... 0.80-1.25 0.44-0.65
Plate SA.387 12C12 65 40 0.17 0.36-0.69 0.035 0.040 0.13-0.32 ... 0.71-1.21 o.-~O-o.tij
Forging SA.182 F12 70 40 0.10-0.20 0.30-0.80 0.040 0.040 0.10-0.60 ... 0.80-1.25 0.44-0.65

1 1.25Cr-0.5Mo Tubes SA.213 TI1 60 30 0.15 0.30-0.60 0.030 0.030 0.50-1.00 . . . 1.00-1.50 0.444.65
Pipe SAX5 PI1 60 30 0.15 0.30-0.60 0.030 0.030 6.50-1.00 . . . 1.00-1.50 0.44-0.65
Plate-- ' SA-387 11C12 75 45 0.17 0.36-0.69 0.035 0.040 0.44-0.86 . . . 0.94-1.56 0.40-070
Forging SA-182 F11 70 40 0.10-0.20 0.30-0.80 0.040 0.040 0.50-1.00 . . . 1.00-1.50 0.44-0.65
Castinglb) SA.217 WC6 70 40 0.20 0.50-0.80 0.040 0.045 0.60 .. . 1.00-1.50 0.45-0.65
COMBUSTION
Metallurgy and Materials

Cr - 12 Ni. Many of these parts are cast, but forg- damping characteristics. Ductile-iron and steel
ings and plate have also been used. castings are also frequently used. Where wear
Castings are also advantageous in such boiler resistance is a major requirement, special alloy
components as stokers and pulverizers where iron castings and forgings of hard, abrasion-
parts can be made to desired shapes with little or resistant materials are available for liners, grind-
no machining. Composition of the iron or low- ing rings, rolls and other parts.
alloy steel may be varied to match the severity STRUCTURAL MATERIALS
of the specific temperature service. For exarn-
ple, gray cast iron is often used in many items of A considerable amount of steel in structural
power-plant equipment because of its vibration- and sheet form is used for support and gas-

Table I. Materials Used in Boiler Construction -Continued


ALLOY Product ASME Grade Minimum Minimum Composition, %(a)
Form or Tensile Yield
ASM Strength Strength
Spec. ksi C Mn P S Si Ni Cr Mo

2.25 Cr-1 Mo Tubes S.\-213 T?? 60 30 0.15 0.30-0.60 0.030 0.030 0.50 ... 1.90-2.60 0.87-1.13
Pipe Sh-335 P?2 60 30 0.15 0.30-0.60 0.030 0.030 0.50 ... 1.90-2.60 0.87-1.13
i Plate SA.387 22Cll 60 (c) 30 (c) 0.17 0.27-0.63 0.035 0.035 0.50 ... 1.88-2.62 0.85-1.15
SA-387 C12 75 (d) 45 (dl
Forging SA-182F22 75 45 0.15 0.30-0.600.0400.0400.50 ... 2.00-2.50 0.87-1.13
Castinglb) SA-217 WC9 70 40 0.18 0.40-0.70 0.040 0.045 0.60 ... 2.00-2.75 0.90-1.20

5b 4 . 5 MO Tubes S.4-?I3 T5 60 30 0.15 0.30-0.60 0.030 0.030 0.50 . .. 4.00-6.00 0.45-0.65

9 CC-1 MO Tubes SA-213 TY 60 30 0.15 O:JQ0.60 0.030 0.030 0.25-1.00 .. . 8.110-10.00 0.90-1.10
- -

AUST- iC Tubes SA-213 TP 304H 75 30 0.04-0.10 2.00 0.040 0.030 0.75 8.00-11.00 18.00-20.00 . ..
3 ALLOYS P ~ p e SA-376 TP304H 75 30 0.04-0 10 2 00 0 040 0.030 0.75 8.00-11.00 18.00-20.00 . ..
Plate S.\-240 304 75 30 0.08 2.00 0.045 0.035 1.00 8.00-10.50 18.00-20.00 .. .
S.4-210 304H 75 30 0.04-0.10 2.00 0.045 0.030 1.00 8.00-12.00 18.00-20.00 .. .
Forging SA-182 F304H 75 30 0.04-0.10 2.00 0.040 0.030 1.00 8.00-11.00 18.00-20.00 . ..
18Cr-lONi-Ti Tubes jL S.i.213 TP321H 75 30 0.04-0.10 10 0.040 0.030 0.75 9.00-13.00 17.00-20.00 . ..
-
18Cr-lONi-Cb Tubes(fl SA-213 TP347H 75 30 0.04-0.10 7.040 0.030 0.75 9.00-13.00 17.00-20.00 . ..
-
16G-12Ni-2Mo Tubes SA-213 TP316H 75 30 0.04-0.10 L 040 0.030 0.75 11.00-14.00 16.00-18.00 2.00-3.00
Pipe SA-376 TP316H 75 30 0.04-0.10 2.11 '040 0.030 0.75 11.00-14.00 16.00-18.00 2.00-3.00
Forging SA.182 F316H 75 30 0.04-0.10 2.0' MO 0.030 1.00 10.00-11.00 16.00-18.00
Plate S.4-240 316H 75 30 0.04-0 10 2.01 1.045 0.030 1.00 10.00-14.00 16.00-18.00 2.00-3.00
Structural 10.00-14.00 16.00-18.00 2.00-3.00
Sheet A167 3161 70 25 0.0'3 2.01 0 045 0.03 1.00
- --
25 Cr-12 Ni Casting S A X 1 CH20 70 30 0 20 1.5L 0.060 0.04c. 2.00 12.00.15.00 22.00-26.W
-- -
la1 Singlevaluesshocvnare maximums. Id1 Surmalizd.
Ibl Rwidualelernentsnuttoexceed I.W'h. Irl litaniam contrnt nut lessthan burlimescarbun ~untentand I: .num~i!anO!: .,>.
[cl Annealed. If1 (b t Tanut lessthanri~htlimesIhecarboncon!-ntand nut rn .<elha,: I.UU'%.
COMBUSTION
Metallurgy and Materials

enclosure purposes. The basis of selecting the I 1


appropriate steel involves design consid-
erations similar to those used for pressure-
containing service.
Generally, large utility boilers are suspended
from large girders at the top of the unit to al-
low the unit to expand downward with an in-
crease in temperature. Supporting extremely
heavy loads, the girders operate at ambient
temperatures which may be quite low, say
-40F. Therefore, they must be designed and
fabricated to exhibit adequate toughness for re-
sistance to brittle fracture. The precautions de-
scribed in the later sectionon heat treatment Fig. I Solid-solution random distributionof atoms
are applicable to these structures as they are to are commercially pure. This is true of copper
the pressure vessels. for electrical wiring. Deliberatelq combining
In some instances, as with flue-gas scrubber elements to form an alloy can enhance mechan-
systems, compatibility with a corrosive service ical or physical properties. Some combinations
environment is of critical importance to the result in a single-phase, solid-solution alloy. It
selection of the appropriate grade of steel. is called single
- phase
- because the atoms are
WELD METALS dissolved in the structure such that visual,
The metals used in welding drums, headers, microscopic and X-ray observations reveal a
tubing, ducts and other platework must be de- single crystal structure. Such a solid solution
signed to exhibit properties compatible with most readily forms when the two components
the base metals. The composition of the weld are similar in atomic size and in electronic
filler metals and fluxes, when these are re- structure. The distribution of the at0n.s may br
quired, must be tailored to each different weld- random (Fig. I),ordered (Fig. 2), or interstiti<I
ing process used in the shop and field. (Fig. 3).
Element combinations may result, however,
in a mixture of two or more phases. Fig. 4 shows
METALLURGICAL a two-phase structure of sigma phase in type
FUNDAMENTALS 321 austenitic material. Sigma phase is a hard
For purpose of classification, the science of and brittle intermetallic compound of var-
metallurgy is ,generally divided into turofields:
process metallurgy, the science of obtaining
metals from their ores, and physical metal-
lurgy, the science concerned with the physical
and mechanical characteristics of metal and al-
loys. These fields, in turn, are part of the basic
sciences of chemistry and physics involving
the study of the structures of atoms-their sizes
and forces of attraction and the arrangements of
these atoms in forming molecular structures,
grain structures, and grain boundaries of mul-
ticrystalline materialsa3
PHASE DIAGRAMS
Some metals used for engineering purpc s Fig. 2 ' !id-solution ordered distributionof atoms
LUMbUarLUAY

Metallurgy and Materlals

iable composition that adversely affects the


room-temperature ductility of stainless steel.
Fig. 5 shows a two-phase structure of pearlite
(alternatelamellae of cementite and ferrite) and
ferrite (carbon steel SA-192 of Table 1).emen-
tite is a compound of iron and carbon known as
iron carbide of the approximate formula Fe3C,
characterized by an orthorhombic crystal struc-
ture; ferrite is a solid solution i n which alpha
iron is a solvent, characterized by a body-
centered cubic crystal structure.
The phase relationships depend upon tem-
perature. Fig. 6 shows a phase diagram for a
simple system of lead and tin at equilibrium
conditions. This diagram can be used as a map
Fig. 3 interstitial distributionof atoms in solid solu- to determine the phases present at any particu-
tion of carbon in iron (face-centered'cubic struc- lar temperature and composition. For example,
ture) at 50 percent tin and 21ZF, the phase diagram
indicates two solid phases. Alpha is a solid so-
lution of lead with some dissolved tin; beta is
almost pure tin with very little dissolved lead.

, . " _
Fig. 4 Two-phase structure of sigma phase in austen-
.
'\ Z I /
itic type 321 material at 500X. Ten-percent Fig. 5 i- ,vo->ha:-;: structure of pearlite an., rrite in
potassium hydroxide etch, one half second 'ow carboxr steel at 500X. Two-percent nital dch
1800r p+Y Austenite Irl

~ e e r " : j "n9e-
Pb 20 40 60 80 Sn Ferrite (a),andCarbide (C)
Weight %Tin 8000 0.2 0.4 0.6 0.8 1.0 1.2 1.4
1
Fig. 6 Equilibrium diagram for a simple system of % Carbon
lead and tin
I
At about 400F, an alloy of 10 percent tin and 90 Fig. 8 A portion of the iron-carbon phase diagram
percent lead lies in an area which is entirely in showing temperature of importance to the heat
treatment of carbon steel
the alpha phase. It is a solid solution of lead
with some tin dissolved in it. At the same for a ternary alloy become more complex as
temperature, but for 30 percent tin and 70 per- shown for an iron-carbon-chromium alloy in
cent lead, the phase diagram indicates a mix- Fig. 9. Such phase relationships are used in
ture of liquid and solid solution. If this latter regulating heat treatments in alloys.
, composition were heated to a temperature of
5 7 5 T , it would become all liquid.
The phase fields in equilibrium diagrams, of
course', depend on the particular alloy systems.
When copper and nickel are mixed, the phase
diagram is as shown in Fig. 7. This phase dia-
gram is comparatively simple, as only two
( 3aar a+Yg~id
Liquid
-

phases are present. In the lower part of the dia-


gram, all compositions form only one solid so-
. lution and therefore only one crystal structure.
Fig. 8 shows a portion of the phase diagram
for the iron-carbon system. The phase relations

1 1455C Atomic % C O D D ~ ~ 1

Ni 20 40 60 80 CU
1
Weight Oh Copper
I % Carbon

Fig. 7 Simple two-phase equilibrium diagram of Fig. 9 Iron-chromium-carbon alloy phase diagram
nickel and copper (15% chromium)
COMBUSTION
Metallurgy and Materials

T-T-T CURVES GRAIN STRUCTURE


-
The phase relations such as shown in Figs. 6, A grain is a single crystal usually without a
7, 8, and 9 are representative of equilibrium regular external crystalline shape. In a solid,
conditions obtained as a result of slow heating, the presence of surrounding grains usually
slow cooling and long time at temperature. controls its shape. Within any particular grain,
Time is required for change from one phase to all of the atoms are arranged in one pattern,
another. Energy change is involved. Reaction characterized by the unit cell. But at the grain
rates are usually faster at higher temperatures boundary between two adjacent grains, there is
except near the temperature of transformation a transition zone not directly aligned with
from one phase to another where extra energy is either grain. Fig. 11shows this transition zone.
required to nucleate a new phase. When a metal is observed under a micro-
Temperature-time:transformation curves scope, although the individual atoms can-
(T-T-T) exemplify reaction rates for phase not be seen, the grain boundaries can be readily
changes. The Fig. 10 T-T-T curve is for a steel of located if the metal has been smoothly polished
0.8 percent carbon content shown in the Fig. 8 to a mirrorlike surface and etched with an acid.
equilibrium diagram. It can be seen that rapidly The grain boundaries will 6e attacked differ-
cooling this steel to low temperature allows the ently from the body of the grain and become
gamma phase (austenitic material) to be pres- visible. Different phases will also become visi-
ent down to low temperature for a considerable ble. The grain boundaries of the single-phase
time period before transformation occurs. The austenitic alloy (Fig. 12) shows fine and
transformation product at this low temperature coarse-grained material (ASTMA-213-TP 321).
differs from what it would be if transforma- Thermal treatment can regulate the grain
tion occurred at a higher temperature, and size. An increase in temperature causes in-
is of higher hardness and strength with suf- creased thermal vibration of the atoms. This vi-
ficiently high. carbon content. This trans- bration facilitates transfer of atoms across the
formation product is a hard material called grain boundary from small to large grains. A
martnnsite. Such a phenomenon is one of the subsequent decrease in temperature slows or
bac methods of varying properties of steel by
' L . stops the process, but does not reverse it.
1 treatment. Each alloy subject to phase Grains may grow through mechanical working,
ct 1.1yes with temperature change exhibits a by the use of heat treatment, through phase
cfiaracteristic T-T-T curve. changes, or a combination of these methods.
The only way to refine the grain size is to dis-

r Stable
1500 A1 (1330')

n
$ 500
I-

0.01 1.0 10 100 1000


Time, Sec (LogScale)

Fig. 10 Time-temperature-transformtion (T-T--0 - ---


I 2
curves for steel in Fig. 8 with 0.8 percent of carbon . 7 ,torn,);ttl ansition at grain boundary be-
(eutectoid) 1w-r: ON J grel,IS
ConusnoN
Metrlluqy and Yllrrials

tort, break, or remove the grains which have


grown and start new grains. The process de-
pends upon the characteristics of the particular
alloy involved. Grain growth will occur only
above certain temperatures and depends upon
time at temperature. This temperature may be
quite low with some materials which have been
critically cold-worked.
The ASTM has standardized a grain-size
index in which the grain-size number, n, i s ob-
tained as follows.
N =2"-I
(1)
where N is the number of grains observed per
square inch at a linear magnification of 100X.
For most metals, the grain size ranges from
number one to number eight, number one being
a large grain and number eight a small grain.
Because the properties of metals vary greatly
depending upon grain size, proper control
must be exercised.

As discussed previously in the section on


T-T-T curves, plain carbon steel is hardened by
quenching in water to cool the piece rapidly,
thereby avoiding transformation at the fastest
reaction rate temperature of 1000F ,("nose" of
Fig. 10 T-T-T curve). This is possible if the
thickness of material is small enough to cool
completel~~ at the required rate. But a large
thickness piece cannot be cooled fast enough at
the center of the thickness, and transformation
will take place more rapidly and at a higher
temperature at the center. This results in a
softer transformation product.
Alloy additions to this steel retard the trans-
formation rate (shift the curve of Fig. 10 to the
right) and allow hardening to greater depths.
This also permits less severe quenching and re-
sults in lower thermal stress with reduced pos-
sibility of cracking. Highly alloyed steels may
be hardened by air cooling. Because steels
hardened to high values are also brittle as hard-
Fig. 12 Grain-size boundaries of single-phase aus- ened, a reduction of hardness is generally ac--
tenitic alloy showing fine and coarse grained mate-
rial (ASTM A-213-TP321). Grain-size number eight complished by reheating to an intermediate
and smaller (top) and fourto seven (bottom) at 1OOX. temperature. This markedly improves tough-
Sixty percent nitric acid etch ness. This process is called tempering.
COMBUSTION
Metallurgy and Materials

HEAT TREATMENT denum steels), strain-induced precipitation


- Table 114 helps to understand some of the
cracking (particularly possible with the
processes whereby metallic structure can be stabilized austenitic steels), aging embrittle-
changed through heat treatment. Thermal ment, large grain size (which may cause exces-
treatment can markedly affect ductility and sively low ductility) and low stress-rupture
toughness of base metal, weld metal, and heat- strength or creep-rupture ductility.
affected zones; the type of treatment is selected Some steels are susceptible to very low
with knowledge of the material property needs ductility in a narrow range of elevated tempera-
during fabrication and in service. ture. Such a condition, combined with the
Thermal treatment is often required to soften presence of stress, can produce sufficient strain
zones which become cold-worked in local to exhaust the ductility and result in cracking.
areas during the forming operations. Whether This can occur with operation in the low-
such treatment is necessary depends on the ductility temperature range, or in passing
degree of cold work, the likelihood of sub- through the low-ductility temperature range
sequent strain aging, and the potential for during application of a postweld heat treat-
controlling the degree of cold work devel- ment. The latter is known as stress-relief crack-
oped during processing. ing or reheat cracking. The characteristics of
such susceptible materials must be established
Though careful handling of large parts can
sometimes prevent the development of heavily- for proper handling.
cold-worked surface areas, this is not usual. With steels to be used at low temperature,
And heavily cold-worked zones can act as thermal treatment may be advisable to ensure
crack starters, causing brittle failures below the resistance to brittle fracture. Carbon steels im-
nil ductility temperature. On a finished part, properly deoxidized are subject to loss of
such zones can also senre as nuclei for starting toughness and ductility by quench aging. If not
cracks at low temperatures under shock condi- corrected, this deficiency can result in failure
tions. Heat treatment minimizes this effect. during fabrication or operation. Small defects
During fabrication, welds may require ther- (such as cracks at arc strikes) can exhibit re-
mal treatment to eliminate cracking. Heavy sidual stresses as high as the yield point at the
plates of carbon steel (more than 5 in. thick) defect and may act as crack starters with addi-
and lighter plates of low-alloy steels have been tional loading. If thermally treated, such areas
known to crack if allowed to cool to room are generally relatively harmless. For some
temperature after welding. Steels such as these combinations of conditions, the use of careful
may require heat treatment before cooling from nondestructive tests to prove freedom from
preheat temperatures. This treatment, which macroscopic defects may allow the thermal
may be at a relatively low temperature (600' to treatment to be eliminated.
1000F) for a short time, eliminates cracking.
Necessary for certain structures, it is generally MECHANICAL PROPERTIES
termed an interstage thermal treatment. This is OF STEEL
because it is applied to individual parts of
-an assembly or after partial welding of Certain mechanical properties of steel affect
subassemblies. its fabrication and service. Among these are
When processing steels for high-temperature tensile properties, hardness, toughness, fatigue
operation, it is important to tailor the thermal strength, and high temperature characteristics.
treatment so that the material will remain sta- TENSILE PROPERTIES
ble during the service life. Such custom treat-
ment will avoid the development of serious de- The standard tension test provides data on
fects, such as "eyebrow" or "chain-type" yield strength, tensile strength, and ductility.
graphitization (of carbon and carbon-molyb- When metals are pulled (stressed) with a uni-
--
COAQWSTION
ktallurgy and Materials

-- --

Table 11. Heat-Treating Processes


Process Example Purpose Procedure

Annealing Cold-worked To remove strain harden- Heat above recrystallizationb


metals ing" and increase ductility temperature
Annealing Steel To soften Heat into austeniticcrange and
slow cool
Normalizing Steel Homogenization and strain . Heat into austentic range and air
reliefff cool
Process Steel To soften and toughen Heat close to, but below, the
annealing and eutectoidd temperature
stress-relieving
Spheroidizing Steel To soften and toughen Heat for a sufficiently long time
close to, but below, the eutectoidd
temperature
Quenching Steel To harden Quench from austenite to marten-
sitee. (This is followed by
tempering.)
Tempering Quenched To toughen Heat briefly at low temperature ,.
steel

Austempering Steel To harden without devel- Quench from austenite to a low


oping brittle martensite temperature below the noser
of the transformation curve, but
above the martensite transformation
temperature. Hold until trans-
formation is complete.
Marquenching Steel To harden without quench Quench from austenite to a tem-
cracking perature below the nose of the
transformation curve, but above
the martensite transforming tem-
perature. Hold until temperature
- has equalized. Cool slowly to
martensite. (This is followed by
tempering).
Solution Stainless To produce a single phase Heat above the solubility curve
treating steel alloy into a single phase area and
quench to room temperature.
Age-hardening Various ferrous To harden Solution treat. Cool to provide
L and nonfer- supersaturation. Reheat to an in-
rous alloys termediate temperature until the
initial precipitation starts. Cool
A - to surrounding temperatures.

"When a sufficient stress is applied to a metal such that the piece does not return to its original dimensions, the yield strength has been ex-
ceeded. Because most metals are weaker in shear than in pure tension. they yield by plastic shear or slip of one plane of atoms over another.
This slip occurs most readily along planes containing the greatest number of atoms per unit of area. These parallel planes are more widely
COMBUSTION
Metallurgy and Materlab

separated than other planes. Plastic movement along these planes causes distortion of the planes because of restraint of surrounding metal
and allows added amount of slip to occur less readily. This resultant increase in strength is called strain hardening.
Because plastic deformation at low temperatures causes distorted crystal patterns, the tendency is for the atoms to return to a more perfect
unrestrained condition. Heating to a higher temperature increases thermal vibration of the atoms which allows readjustment to take place.
As such readjustment also results in decreased hardness. the temperature of marked softening is called the recrystallization temperature.
Recrystallization temperature depends upon degree of plastic deformation (cold work), time at temperature, material, and mserial purify.
Generally, it is between 1/3 and YZ of the melting temperature (degrees absolute). Plastic deformation at temperature below therecrystalliza-
tion temperature is called cold working whereas above the recrystallization temperature is called hot working.
A solid solution in which gamma iron is the solvent: characterized by a face-centered cubic crystal structure.
See Fig. 8. Eutectoid temperature is 1330F. Eutectoid carbon content is 0.8 percent.
A n unstable constituent isquenched steel, formed without diffusion and only during cooling below acertain temperature known as the M,
temperature (see Fig. 10). The structure is characterized by its acicular or needlelike appearance on the surface of a polished and etched
specimen. Martensite is the hardest of the transformation products of austenite. Tetragonality of the crystal structure is observed when the
carbon content is greater than about 0.5 percent.
'SeeFig. 10. "Nose" of curve is at approximately 1000F. The start of martensite transformation on cooling for this steel is approximately
500F.

axial increasing load, the material stretches -


deformation the steel will sustain before break-
(strains). Diagrams such as Fig. 13 show the ing. It is usually expressed as a percentage
relationship between stress and strain for elongation or reduction in cross-sectional area
specific materials. With increasing load, the of the test specimen. How much plastic strain a
material strains elastically until it reaches the steel will exhibit is quite variable and is gener-
yield point. During this period of elastic be- ally inversely related to the tensile strength of
havior, there is no permanent deformation; the material. High-strength steels typically will
strain is directly proportional to the stress. This exhibit much less ductility than softer, lower-
relationship is described by Hooke's Law strength steels.
which states that stress' equals strain multi- Because the true yield point is difficult to es-
plied by the modulus of elasticity (Young's tablish with any accuracy, most current tensile
Modulus) of the material. testing of steels involves the determination of
Continuing to increase the loading beyond yield strength rather than yield point. Yield
the yield point results in plastic strains and strength, which can be easily established, is de-
eventual breakage of the test specimen. fined as the stress necessary to produce a
Ductility is a measure of the amount of plastic specified value of plastic elongation, usually
0.1, 0.2, or 0.5 percent as measured over the
gage length of the tensile specimen.
I Steel Most of the specifications covering the steels
used in the construction of a boiler require
room-temperature tensile testing with min-
imum values of tensile strength, yield strength
Yield Point or Proportional Limit and ductility specified. But for design pur-
... poses, the tensile and yield strength of each
grade of steel used needs to be determined at
A to YP Elastic Deformation temperatures up to the creep range of the grade.
YP to X Plastic Deformation Various organizations including the producers
X Breakage of Tensile and fabricators of steel perform such tests and
Specimen
the data from these tests are used by the ASME
A Strain - Boiler and Pressure Vessel Code to set maxi-
mum allowable stresses.
Fig. 13 Stress-strain curve for two steels with dif- Some of the many product form specifica-
ferent strength and ductility tions-most noticeably those for pipe and
conusmow
Mot.llurgy and Materials

tube-require various deformation tests such men is related to the height of rebound-and is
as flattening, flaring, or bending. These addi- expressed as ft-lbs.
tional tests of ductility provide evidence of the The mode of failure in the impact test
ability of the steel to withstand fabrication or changes from ductile (shear) to brittle (cleav-
installation operations such as bending, swag- age) as the temperature is lowered. The tem-
ing and tube expansion. perature range at which this occurs is called the
transition range. Material within or below its
HARDNESS transition temperature range may crack ex-
The hardness of a material is a measure of re- tensively if subjected to an impact load, or if
sistance to plastic deformation and is related to construction'details are such that localized
the tensile strength of the steel. It is also used as yielding is prevented.
an indicator of the machinability and abrasion The transition temperature range depends
resistance of a steel. Usually, hardness is de- upon the particular metal composition and
termined by Brinell, Rockwell, or Vickers tests melting practice as well as the subsequent
in which a small ball or pyramid-shaped point working and heat treatment. For many types of
is pressed into the surface of the metal with a carbon or low-alloy steels, the transition tem-
specified force for a specified time. The size of perature may be as high as 70F or above. The
the indentation is measured automatically or possibility of brittle fracture must be consid-
by microscope and is expressed as a hard- ered in the fabrication of materials (bending
ness number. The smaller the indentation, the and forming in various manners), in testing the
higher the hardness number. finished structure, and in any service involving
The use of hardness testing is permitted in operation below the transition temperature.
some material specifications to approximate Care in design, fabrication, inspection and,
tensile strength. ASTM Specification A-370 when necessary, field repair, is required to
contains hardness-to-tensile-strength conver- eliminate conditions which might promote
sion charts for different groupings of steels. In brittle fracture.
some material specifications, particularly Fig. 14 shows the impact strength versus
those in which the ductility of the steel is im- temperature for a material having a,high transi-
portant to its workability, maximum hardness tion temperature. Also shown are the broken
values are specified. surfaces of the impact specimens in which there
is a ductility variation with the temperature
TOUGHNESS of testing. The material tested at the lower tem- ,
perature has broken in a cleavage fracture
Under most circumstances, steel can tolerate along crystallographic planes and shows a
localized stresses above the yield point by plas- shiny-grain appearance which at one time led
tically absorbing and redistributing these to the mistaken impression the material had
stresses. But under certain conditions, even crystallized. Actually, what appears in the fig-
steels having considerable ductility are subject ure is the progression from a brittle-cleavage
to a brittle (cleavage) mode of failure when sub- fracture to a ductile-shear fracture as the tem-
jected to concentrated stresses at low tempera- perature of testing is increased. Corrosion-
tures. The property of toughness is the ability resisting pressure vessels of this material may
of a material to resist this failure. be successfully fabricated and used provided
Various impact tests evaluate the property of sufficient consideration is given to this prop-
toughness. One of the more commonly used erty. The importance of the degree of stress-
tests is the Charpy V-notch impact test. In this concentrating mechanical notch in this type - 7
-

test, a swinging pendulum strikes a single blow material is shown in Fig. 15.
to a notched horizontal specimen supported on The examples given are for chromium-iron
both ends. The energy absorbed by the speci- materials having a particulady high transition
COMBUSTION
Metallurgy and Materiab

peratures. Austenitic stainless steels and met-


als such as copper and aluminum, in general,
do not change abruptly in toughness as a func-
tion of temperature and may be used to temper-
atures as low as that of liquefied air.
FATIGUE STRENGTH
The stress a material can withstand under re-
60- peated application and removal of load is less
O 0
than that it can withstand under static condi-
tions. The yield strength, which is a measure of
static stress a material can sustain without ap-
preciable permanent deformation, can be used
as a guide in design only for material subjected
to static loading. Dynamic, cyclic loading
causes slip and cold-working in minute areas
localized at grain boundaries and at stress-
I I I I I (
concentrating notches of various types.
-1 00 0 100 200 300 400 500 600 As sufficient work-hardening develops, mi-
Temperature, O F
croscopic cracking develops and grows until
Fig. 14 Relationship of impact strength to tempera- complete fracture results. Fatigue strength is
ture for a material having a high transition tempera- the magnitude of a cyclic stress which a mate-
ture. (16% Cr weld metal) rial can resist for a specified number of cycles
before failure. But at sufficiently low stress
temperature. Steels used in boilers have transi-
levels, many materials can tolerate an almost
tion temperatures considerably below that infinite number of cycles. Fig. 16 shows the en-
shown in the example. Metals to be stressed in durance limit for one material.
operation at low temperatures are selected
Areas of peak stress such as changes in sec-
based upon these considerations and pur- tion or stress-concentrating notches promote
chased to specified impact requirements. the localized concentration of cyclic strains.
Heat-treatable steels in the quenched and
Fig. 17 shows the photoelastic distribution of
tempered condition may have considerably stress in a welded waterwall tube panel when
improved transition-temperature properties. subjected to an in-plane tensile load. Fatigue
High-nickel steels exhibit low transition tem-
evaluations of welded walls have included
cyclic-loading testing of full-size panels under
a bending and in-plane loads.'With such testing,

- 110
20 100 Endurance Limit
87
90
ui
U)
80
9 70
tj
60
Radiusof Notch, Inch 104 lo5 lo6 lo7 10'
Fig. 15 Effect of radius of notch (shown by stress Number of Cycles
concentration) on impact values of 18 percent Cr
weld metal Fig. 16 Endurance limit for a hot-worked bar stock
COMBUSTION
Mot8IIurgy and Materhls

and yield strength. At still higher tempera-


tures, the strain in a material is a function not
only of the applied stress but also of the time
under stress at temperature. In this high-
temperature range, the metal will deform
(creep) continuously even at stresses much
lower than the short-time yield strength. If held
for sufficient time under these conditions, the
material will rupture.
Because no way has been found to predict
this behavior quantitatively from short-time
Peak Stress tests, it is necessary to perform tests of creep
and stress rupture at several stress levels,
temperatures, and over time periods as
long as possible. Such tests, and extrapola-
tions as necessary, establish values of creep
strength and stress-rupture strength. The creep
strength of a metal at a certain temperature is
the steady stress that produces a specified low
rate of elongation. For long-time service, such
as ASME Boiler Code applications, a creep rate
,of 0.01 percent in 1000 hours is used. The
stress-rupture strength is the steady stress re-
quired at? particular temperature to cause rup-
ture in a specified long period of time.
Fig. 20 illustrates how creep and rupture
strengths for a 2% Cr-1 MOsteel are established
from test data. Creep-rate data for 100O0,1100

a
Fig. 17 Photoelastic pattern showing peak stress in
and 1200F are plotted versus stress. The inter-
section of these data lines with that for 0.01
percent in 1,000hours sets the respective creep
strengths of 7,800 psi, 5,000 psi and 2,400 psi.
The other curves show rupture life versus
welded waterwall tubes stress for the same three temperatures. Lines
through these data are extrapolated to 100,000
endurance limits for the actual as-built compo- hours to establish rupture strengths of 13,000
nent have been established. psi, 7,000 psi and 3,300 psi respectively.
Figs. 18 and 19 present an example of fatigue Paragraph A-150 of Section I of the ASME
cracking. The cause of the crack was an unan- Boiler and Pressure Code lists the following
ticipated gas-flow-induced vibration of the criteria for consideration by the Code Commit-
superheater tube. Antivibration restraints have tee in establishing allowable stresses:
been applied to correct this type of problem.
1/4 of the specified minimum tensile strength
at room temperature
HIGH-TEMPERATURE 1/4 of the tensile strength at elevated tempera-
- PROPERTIES tures
At temperatures exceeding about 650F, .2/3 of the specified minimum yield strength at
most steels suffer a gradual decrease in tensile room temperature
COMBUSTION
Metallurgy and Materials

Fig. 18 Fatigue crack in horizontal superheatertubeat end of plate support members. Vibration in the length
of tube to the right side of the spacer eventually caused the fatigue crack to initiate at the attachment and
propagatecircumferentially.
2/3 of the yield strength at elevated tempera-
tures.
100 percent of the stress to produce a creep -

rate of 0.01 percent in 1,000 hr


.
67 percent of the average stress to produce
rupture at the end of 100,000 hours, or 80 per-
cent of the minimum stress for rupture at the
end of 100,000 hours as determined from the
extrapolated data, whichever is lower.
Fig. 2 1 applies these criteria to establish the,
allowable stress for a 2% Cr-1 Mo steel. For this
material, item 1controls up to 800F. At 950F
and above, the creep strength and rupture
strength, the fifth and sixth items, require a
Fig. 19 Through-the-wall nature of the Fig. 18 rather sharp decrease in the allowable stress.
fatigue crack. Typical of fatigue, there is a single, The relative influence of the different criteria
tight trans-granular crack varies with materials as well as with tempera-
-
ture. Fig. 22 shows the effect of temperature on of steel may be strongly affected by grain size,
ASME Boiler Code allowable stresses for a cold working, heat treatment and other vari-
number of alloys used for high-temperature ables. Material suppliers and equipment man-
service. The carbon steels begin to lose strength ufacturers must give careful consideration to
above 700F, and by 850F are down to about these factors in their manufacturing and fabri-
one-half their room-temperature values. The cation procedures.
low-chromium ferritic alloys start to lose
strength above 800F and are down to half CREEP AND FATIGUE INTERACTION
strength at about 1000F..The austenitic stain-
less steels decline somewhat from room tem- When melals are exposed to cyclic loadings
perature to 1000F because of reduction in while operating at temperatures within their
yield strength; above 100O0F,creep and rup- creep range, creep effects can reduce fatigue
ture strength cause a rapid decrease to half life. Fig. 23 indicates how the fatigue behavior
strength or less by 1200F. of a steel varies for different testing conditions
The high-temperature strength and ductility at elevated temperat~re.~ The introduction of

7800 PSI

- 6000

6
V)

g
[I)
2000

1000-
0.001 0.002 0.004 0.01 0.02 0.04 0.1
Creep Rate, % in 1000 Hours

Material: 2% Cr-1 MoSteel


Specification: SA-213GradeT22

Time to Rupture, Hrs

Fig. 20 Creep rate (upper) and rupturestrength (lower) for a 2% Cr-1 Mo steel
COMBUSTION
MeiiNurgy and Materials

Material: 2%Cr-1Mo Steel 1 Carbon Steel SA-192


Specification: SA-213 Grade T 22
2 Carbon Steel SA-210 A-1
3 C-'12 MO SA-209 T-1

2000 -of 0.01% in 1000 ours


-
0 ' ~ ' ~ 1 ~ 1 ~ 1 ' 1 ~ 1 ~
0 400 800 1200 200 400 600 800 1000 1200 1400
Metal Temperature,' F Metal Temperature, O F

Fig. 21 Use ofASME Boiler Codecriteria to establish Fig. 22 Effect of temperature on ASME Boiler Code
allowable stress for a 2% Cr-1 Mo steel allowable stresses fo'r grades of steel tubing

30 Min. HoldTime

10 102 1o3 1o4 1O5 1O6


Cycles to Failure

Fig. 23 Effect of temperature and creep-relaxation hold time on number of cycles to failure.
Material 2XCr-1 Mo
CO%BUSTION
Metallurgy and Materials
< -

periods of hold time at temperature, while In the USA, organizations involved in coop-
under maximum strain, causes the slope of the erative research include the Pressure Vessel
curves to change considerably. The periods of Research Committee, the Metal Properties
hold time allow creep relaxation to occur to the Council and the ASME B&PV Committee.
detriment of fatigue life.
DISSIMILAR WELDS
The problem of creep and fatigue interaction
is complex both in the formulation of a realistic Fig. 24 is an example of cracking damage be-
design basis consistent with proven past prac- cause of interaction between creep and fatigue.
tice of successful cyclic operation within the Welds using type 309 austenitic stainless
creep range and in the obtaining of material- filler metal have been used to join ferritic tubes
property data which can be used in design. At- to austenitic stainless tubes. The austenitic
tention is being given to the subject worldwide. steels have a coefficient of thermal expansion

Fig. 24. Typical interface cracking associatedwith Grade TP 309 dissimilar metal weld
COMBUSTION
Metallurgy and Materials

approximately 40 percent greater than the fer- interface cracking associated with nickel-base
ritic steels. This mismatch results in high shear filler metals is primarily a function of strain or
strains at the interface between the austenitic metallurgical changes. Further research is re-
filler metal and the ferritic tube. With cy- quired to provide an unde;standing of the fac-
cling, these strains can cause intergranular tors that promote cracking, such as testing of
cracking within the weaker ferritic material. full-size tubular specimens of various dissimi-
Field repairs of type 309 dissimilar-metal lar metal welds under pressure and tempera-
welds are made by rewelding with nickel-base ture cycling conditions (Fig. 25).
filler-metal welds. The nickel-base metals have Fig. 26 shows another example of interaction
a coefficient of thermal expansion similar to cracking from creep and fatigue. Differences in
the ferritic steels, and the expansion-mismatch thermal expansion of superheater terminal
strains imposed on the ferritic tube are signifi- tubes which are welded to the outlet headers
cantly reduced. Ho'wever, the nickel-base and seal welded at the furnace enclosure have
filler-metal welds, while giving better service caused circumferential cracking in the tubes at
performand6 than the'type 309 welds, are not to- the toe of the tube-to-header weld. Strain cy-
tally free of interface cracking problems. d i n caused these cracks to initiate and prapa-
There is some uncertainty as to whether the gate in a fatigue manner.

Fig. 25 Thirty-two individual creep-rupture tubular specimens, each containing one or two dissimilarwelds,
before being inserted into furnace on the right. Specimens, which have been thermally aged, are exposed to
internal pressuresat temperatures somewhat higher than would be encounteredin service and cycled, with
a 3 4 a y hold time at temperature, to simulate long-time service exposure.
and low-cycle high-strain loading i n the
creep range will likely produce intergranular
rather than transgranular cracking.

SERVICE EXPOSURE
CONSIDERATIONS
Proper selection and usage of materials re-
quire knowledge of the expected service con-
ditions and an understanding of how the
material will behave under those conditions.
Dependent on its environment, material be-
havior can differ significantly. Austenitic
stainless-steel tubes, for example, are widely
used for steam service. In this service, essen-
tially all of the common grades of austenitic
stainless can be considered equally compatible
with the service environment, and there is no
concern about resistance to pitting or inter-
granular corrosive attack (see the subsection
"Sensitization" later in this section). But in the
aqueous environment of boiler flue-gas wet
scrubbers, only grades of stainless steel con-
taining niolybdenum (type 317LMN and other
high-nickel alloys) and so forth can tolerate the
corrosive environment without excessive pit-
ting. (See Fig. 27.) Also, because of the poten-
tial for acidic aqueous conditions in the
scrubber, grades of extra-lowlcarbon stainless
type 3161, notably type 317LMN, are used to
Fig. 26 Intergranular creep and fatigue cracking at avoid the possibility of intergranular corrosive
toe of tube-to-superheater outlet-header weld attack.
caused by repeated exposure to thermal expan- Although type 317LMN stainless is widely
sion strains used in flue-gas wet scrubbers, austenitic stain-
less steels are not suitable for the heat-exchange
Note the similarities in appearance between surface which reheats the scrubbed gases to
this cracking and that described in the earlier temperatures 25" to 40F above the adiabatic
discussion of fatigue and shown in Figs. 18 and saturation temperature. In this wet-to-dry ser-
19. But there is a significant difference in the vice environment, austenitic stainless steels
nature of these two cracks which occurred as can and reportedly have experienced stress-cor-
a result of fatigue cycling. The vibration- rosion cracking. (See "Stress-Cdrrosion Crack-
induced crack is transgranular (across grains) ing,'' this chapter.) Because of this, carbon-steel
which is typical of fatigue, but the cracking tubes and fins have been used for the reheaters
in the tube at the superheater outlet header is in scrubber systems.
intergranular (along grain boundaries). In- As the foregoing examples demonstrate,
tergranular cracking is typical of that which knowledge of the environment and its effect on
occurs i n longer-time creep or stress rupture, the material is a key to the proper use of the ma-
COMBOSTION
Metallurgy and Materials

may take place preferentially along heat-


affected zones of welds, or along stress lines, to
form chain-type graphitization, an example of
which is shown in Fig. 27.
Carbon-steel pipe and carbon-molybdenum
pipe in long-time service, particularly when
operated at temperatures well above 800F and
875"F, respectively, have experienced num-
erous instances of chain-type graphitization
resulting in failure or requiring repair or
repla~ement.~
Because of these problems, C-E has for many
years avoided the use of carbon molybdenum
for piping components and has limited the use
of carbon-steel pipe to 800F. For higher
temperature service, the use of steels con-
taining one-half percent or more chromium
eliminates the danger of graphitization.
Carbon-steel and carbon-molybdenum tub-
ing has not shown a similar tendency to
graphitize as has piping. The graphitization
occasionally found in tubing is usually in the
form of well-dispersed nodules (Fig. 27) which
do not weaken the steel. Carbon-steel and
carbon-molybdenum tubing may, therefore,
be used in applications when the temperatures
reach 850F and 900F respectively.
* RESISTANCETO HIGH-TEMPERATURE
OXIDATION AND CORROSION

Chromium is the most useful alloying ele-


Fig. 27 ~ x a k ~ l eofschain-type graphitization at
ment for imparting oxidation and cp~rosionre-
1 0 0 X (upper) and random graphite nodules at SOX sistance to steel. Fig. 28 shows. the degree of
(lower). Unetched oxidation scaling versus temperature for a
number of steels with a range of chromium
terial. The next section presents some of the from 0 to 18 percent. Similarly, chromium
service exposure conditions that affect the per- additions improve resistance of a steel to
formance of boiler materials. - molten-ash corrosion (see Chapter 3). Low
levels of chromium, in the range of 1/2 to 2114
GRAPHITIZATION percent, provide a useful improvement in
high-temperature-corrosion resistance. Within
At temperatures above 800F, carbon steel this chromium range, high-temperature
is subject to graphitization; above 875OF, strength accompanies the trend of somewhat
carbon-molybdenum steel is similarly affected. improved corrosion resistance.
The carbon normally present in the steel in the For these reasons, there is widespread use of
form of carbides may transform over a long the family of low-chromium alloys, up to 2%%
period
-- of time to graphite. This transformation Cr, for intermediate temperature-range appli-
COMDUSTION
Metallurgy and Materials
-
cations, where carbon steel and carbon 1075"F, alloys with high-temperature strength
molybdenum are not used because of their low and oxidationlcorrosion resistance are needed.
high-temperature strength (see Fig. 22) and There has been some past use of tubing with 5
their tendencies to graphitize. The tempera- percent chromium, but these alloys did not
tures at which these alloy grades are used provide a significant improvement in corro-
involve considerations of high-temperature sion resistance and have lower high-tem-
strength and corrosionloxidation resistance. perature strength than the T-22 grade.
For superheater and reheater tubes in the gas SA-213 T-9 (9 Cr-1 Mo) has been, and con-
pass, alloy grades SA-213 T-11 (11/4% Cr) and tinues to be, used in some reheaters. The mate-
T-22 (2%% Cr) are limited by C-E to gas-side rial has good oxidationlcorrosion resistance
surface temperatures of 1025F and 1075"F, and may be used to outside surface tempera-
respectively. These temperatures, well below tures as high as 1175"F, but at these tempera-
the point at which oxidation scaling is signifi- tures the high-temperature strength (ASME
,, cant, were established based on reviews of allowable mid-wall stresses) is quite low, less
external-wastage-rate data from units in ser- than that for the T-22 (2% Cr-1 Mo) grade.
vice experiencing coal-ash corrosion. With Austenitic stainless steels (grades TP 304H
these limits, excessive external corrosion metal and TP 347H) are used for most of the tubing
loss is not expected even when coals with a cor- operating at surface metal temperatures above
rosive tendency are burned. 1075OF. Not only do these materials have ex-
Generally, the 2% Cr-1 Mo steel is the highest cellent high-strength properties which are
alloy used for pressure-part components out- characteristic of austenite, but they also have
side of the gas pass because the metal has excellent oxidation resistance because of their
good strength and oxidation resistance at out- 18-percent (nominal composition) chromium
let steam temperatures between 1005F and content. But it is important to recognize that no
1055F. But because some gas-touched por- tube alloy operating above 1000Fis immune to
tions of the superheater and reheater are ex- oil- or coal-ash corrosion. By virtue of their
posed to metal temperatures in excess of higher operating temperatures, the austenitic
stainless steels will experience metal loss if
there are molten ash deposits (see Chapter 3).
However, because molten coal-ash deposits
do not exist at temperatures exceeding about
1300F (see bell-shaped curve Fig. 11,Chapter
3, "Properties of Coal Ash"), materials for tube
shields, spacer attachments, supports, baffles,
and other nonpressure parts normally operat-
ing at temperatures above 1300F can be used
without excessive concern for corrosion. Ex-
perience has shown that oxidation behavior in
normal boiler flue gas is similar to that in air.
Table III shows the temperature levels at which
oxidation scaling becomes significant for a
number of alloy grades.
OXIDE SCALES AND EXFOLIATION
Oxides form on the outside surfaces of boiler
Fig. 28 Amount of oxidation (scaling) of carbon, components as a result of direct combination
low-alloy, and stainless steels in 1000 hours in air with oxygen in the air or in the flue gases. Oxi-
at temperatures from 1100" to 1700F dation also occurs in the internal wetted sur-
COMBUSTION
Metallurgy and Materials

from the inside surfaces of ferritic tubes and


Table 111. Maximum Temperature pipes is a cause of solid particle erosion (SPE)
Without Excessive Scaling* damage in steam turbines. So the term exfolia-
tion, as it is widely used in the steam-power-
Alloy AISI Maximum Temp0FWithout generation industry, is in connection with the
Nominal Analysis Grade Excessive Scaling
concern for SPE caused by spalled steam-side
17 Cr 430 1550
oxides.
2 7 Cr 446 2000
OXIDE SCALE ADHERENCE

In many instances, tubes removed from


25 Cr-20 Ni 310 2000
long-time service exhibit little or no exfoliation
'ASTM, Data on Corrosion and Heat-Resistant Steels and or poorly adhering scale. This is typical of most
Alloys--Wrought and Cast. ASTM. Slay. 1950.
samples removed from superheaters, Figs. 3 0
and 32. Conversely, ferritic reheater tubes fre-
faces of the furnace walls and steam-touched quently demonstrate severe exfoliation, or large
surfaces of the superheater and reheater as a re- areas of non-adhering scale, Figs. 31 and 33.
sult of iron-water and iron-steam oxidation Examinations of main and hot-reheat steam
reactions. piping and final outlet headers indicate that
Those oxide scales that form on boiler tube these large diameter components tend to exfoli-
surfaces are thin and protective. In fact, the ate significantly.
oxide t h a i forms o h wetted surfaces- EFFECT OF TEMPERATURE AND SCALE THICKNESS
magnetite - is critical to the compatibility of
steel and boiler water. Because of the funda- Although engineering intuition may suggest
mental importance of magnetite, the half- that exfoliation would tend to be more severe as
joking description of a boiler as a thin layer of temperatures and scale thickness increase, ex-
magnetite supported by steel has been quoted aminations of numerous ferritic tubes from
by many. Chapter 20 or water technology de- service indicate th'at this is not the case. In fact,
scribes the boiler-water chemistry control the exfoliation tendency seems to be greatest
necessary to maintain this protective layer. on the thinner scale. (Erosion damage to the
Oxides forming on the steam sides of the turbines, of course, would be more severe with
superheater and reheater tubes inhibit oxida- thicker scale. But precise knowledge as to the
tion by reducing the diffusion process. Oxida- variables of importance to SPE, including the
tion rates decrease with time in a manner variable of steam temperature, is lacking.)
shown in Fig. 29. This formed-in-place oxide
scale should not be confused with deposits-
o n tube surfaces such as salt, debris, or
t r a n s p o r t e d oxides. Oxide s c a l e that
forms in-situ does not measurably affect
heat transfer as deposits can. Under certain
conditions, oxide scale that forms on the out-
side and inside surfaces of superheater and re-
heater tubes and pipes may break loose and
exfoliate. Because of the conservative tem- 1 1 . 1 I I I I
perature limits on the usage of these steels 0 4000 8000 12,000
adopted by manufacturers such as C-E, exfolia- Time, Hrs
tion does not present a problem of excessive
metal loss which might lead to rupture of tubes Fig. 29 Oxidation metal loss versus time for 1%Cr-1
or piping. However, the exfoliated oxide scale Mo steel in steam at 11OU'F
COYIIlSRON
m y and Materials

Fig. 30 Superheater tube (2% Cr-1 Mo) after 158,000 hours in service. Maximum scale 20 mils

Fig. 31 Severely exfoliated reheater tube (2% Cr-1 Mo) after 39,000 hours service. Maximum scale 9 mils

Fig. 32 Tube cross section showing typical two-


layer oxide structure adhering well to internal sur-
face of superheater tube (tube base metal is the Fig. 33 Tube cross section showing exfoliated
white portion) at 15X oxides on reheater tube at 15X
COMBUSTION
Metallurgy and Materials

POSSIBLE CAUSES OF EXFOLIATION SOLUTIONS TO EXFOLIATION


Several explanations have been offered as Industry has considered, and is exploring
possible causes of exfoliation. C-E investiga- further, a range of possible solutions for avoid-
tors have postulated a thermal-quench explana- ing or minimizing exfoliation and SPE damage.
tion which appears to best fit the presently The following discussion is not intended to
available facts. During start-up of reheat-type provide an all-inclusive listing of these various
steam generators, there is no cooling steam possibilities, but rather will review what can be
flow through the reheater. Gas temperatures done to the steam-touched surfaces in operat-
are limited to 1000F during start-up, and re- ing units and in units yet to be designed.
heater tube temperatures will approach this
limit. When steam is first admitted to the tur- EXISTING UNITS
bine and reheater, its .temperature is signifi-
At present, chemical cleaning is.the only op-
cantly lower than that of the tubes, and the
tion available for existing units. With proper
steam thermally quenches the scale. It appears
that the quenching acts to separate the cylin- care the steam-touched materials can be safely
der of internal scale from the tube and to pro- cleaned to remove all oxide scaling. But chemi-
mote separations along planes of weakness cal cleaning, if not correctly performed, can be
within the scale. damaging to the materials, and a decision to
chemically clean should only be made with a
This thermal-quench explanation is consis- full understanding of the inherent risks and the
tent with the different exfoliation behavior of precautions to be taken.
reheater and superheater tubes. It also fits well A decision of whether chemical cleaning
with the observation that thin scale tends to should be performed, and to what extent, in-
have a greater exfoliation tendency. Under volves cosffbenefit considerations specific to
equal thermal-quench conditions, the temper- the individual circumstances. In this connec-
ature differentials and separation strains be- tion, it should be noted that particles other
tween scale and base tube will be greatest with than exfoliation scale, such as maintenance re-
the thinner scale. During hot restarts, with pair debris, may cause some SPE damage. So
boiler parts still at elevated temperatures, careful assessment of the damage and its likely
scale on non-gas-touched tubing and piping is source is also needed.
exposed to thermal-quench transients similar The Electric Power Research Institute has
to that described for gas-touched reheater funded studies as to the efficacy and feasibility
tubes. Reports from Europe attribute the ab- of applying a chromium-rich oxide coating to
sence of turbine SPE damage there to the use of the inside of tubes following chemical clean-
turbine bypasses, which allow the boiler to ing. Such a chromate treatment process may
be fired with steam flow passing from the negate the need for repeat cleanings or may in-
superheater outlet piping directly to and crease the operating time between cleanings.
through the reheater to the condenser. In such
NEW UNITS
units, cold- or hot-restart thermal transients
which can act to weaken scale-to-tube adher- For units not yet designed, steps can be taken
ence are avoided. These turbine bypasses may to avoid significant ferritic tube and pipe ex-
divert any exfoliated scale during start-up foliation. The exfoliation-prone ferritic por-
directly to the condenser. However, bypass tions of the superheater and reheater can be
valves and steam distributors in the condenser upgraded to austenitic stainless steel. There is
reportedly do not suffer any noticeable erosion no established temperature at which exfolia-
damage, which further supports the vieiv that tion is not considered a problem, but at 950F
these bypasses may prevent or minimize the ex- and lower steam temperatures the scale is quite
foliation process. thin even after long-time service. The 1075F
Metallurgy and Mwtorkls
--
outside-surface-temperature limit that C-E has
imposed on the usage of T-22 (2%% Cr) tubing
to minimize external corrosion, also minimizes
the quantity of exfoliated scale by reducing the
amount of ferritic material.
Austenitic stainless materials can be applied
to the inside surfaces of pipes and headers by
weld-deposit cladding. C-E and others have ex-
tensive experience using these weld cladding
techniques in the fabrication of nuclear and
chemical-process vessels.
The same internal surfaces of ferritic tubes,
pipes and headers which can be replaced or
clad with stajnless may alternatively be
"chromized." This high-temperature diffusion
Fig. 34 Stress-rupture failure of carbon steel tube
process is described further in the final section caused by overheating over a long time period (top)
of this chapter. and a stress rupture failure because of overheating
for only a few minutes (bottom)
OVERHEATING
The term overheating describes creep-rup-
ture failure. This term can be misleading in graph of Fig. 36 had occurred in the tube a short
the sense that it may convey the incorrect distance away from this cross-sectional slice.)
thought that temperature alone was somehow On the half of the tube exposed to the furnace,
metallurgically damaging to the steel. Ac-
tually, overheating describes an exposure to
temperatures too high for the operating stress.
A T-22 tube, operating at a stress level of 5,000
psi, will give long life at a temperature of
1075OE but the same tube would fail by over-
heating at 1000F if operated at a stress of
15,000 psi.
Overheating failures can be categorized as
either short-time or long-time. Fig. 34 sho~vs
examples of such failures.
SHORT-TIME OVERHEATING

Such failures result from exposure to tem-


peratures significantly (hundreds of degrees F)
above design and indicate a severe abnormality
such as a loss of normal water or steam flolv.
Short-time tube failures exhibit considerable
creep elongation which shows itself i n large
increases in diameter, particularly the inside
diameter, and considerable reduction in wall
Fig- 35 Cross section of tube exposed to short-time
:
. - thickness at the fracture surface. Fig. 35 shol,ys overheating. Furnace side of tube at top has thinned
a cross section through a waterwall tube which and ovalized as a result of exposure to excessively
experienced short-time overheating. (A rup- high temperatures while the tube is under internal
ture typical of that shown in the lower photo- pressure.
COMBUSTION
Metallurgy and Materials

MICROSTRUCTURE

When exposed to temperatures above 9oaF,


but less than the lower transformation tempera-
ture (the A, temperature of Fig. 8, which is
1330F for carbon steel), carbon and low-alloy
steels are subject to spheroidization. See Fig.
37. The carbides present in the annealed condi-
tion are not in their lowest free-energy state,
and exposure to temperature results in the
coalescence of these carbides into spheroidal
form. This natural change is both time- and
temperature-dependent, with less time re-
quired to spheroidize as temperatures increase.
Because manufacturing heat treatments can
cause spheroidization, and in view of its time-
Fig. 36 Macrostructure of a heavy wall carbon- temperature dependence, spheroidizarion is
molybdenum steel pipe which has failed because of
stress rupture over a long period of time. 2X
not a good means by which to estimate the ser-
vice exposure temperature of overheated tubes.
there is creep thinning caused by the combina-
tion of intwnal pressure and a temperature too
high to resist the pressure forces. The egg-
shaped inside of the tube is a typical condi-
tion associated with short-time overheating
failures. These physical conditions of thin-
ning and diametral growth provide the best
and easiest moans of assessing the degree of
damage sustained. Under short-time condi-
tions, tubes that have not experienced signif-
icant thinning or creep swelling have not
been measurably damaged as a result of the
overheating.
LONG-TIME OVERHEATING

Tubes which accumulate many hours of ex-


posure to temperatures moderately above their
long-time strength capability are also vulnera-
ble to creep rupture. Creep elongation effects
(swelling and wall thickness reduction) are
much less pronounced in long-time overheat-
ing failures. The upper photo in Fig. 36 shows a
long-time overheating failure and the thick
rupture edge typical of this failure mode.
Long-time creep-rupture failures usually show
evidence of considerable secondary cracking
(intergranular) in addition to the main crack Fig. 37 Photomicrographs showing an annealed
associated with rupture. Fig. 36 shows an structure at top and a spheroidized structure at bot-
example of such cracking. tom at 500X. Nital etch
conmow .
L

M.1.llwgy n d Materials

But by comparing microstructures within the


tube (for example, the sides exposed to and
away from the furnace) spheroidization can be
useful as a indicator of differences in, and
probable range of, exposure temperature.
When heated to higher temperatures, the -
ferrite in carbon and low-alloy steels trans-
forms into austenite (see subsection "Phase %
Diagrams" in this chapter). The temperature at
which austenite begins to form is called the
lower critical temperature, and the upper criti-
cal temperature is that at which there is com-
plete transformation to austenite (A, and A,
temperatures of Fig. 8).
If a tube is heated above the lower critical
temperature and then ruptures, the quenching
effect of the escaping steam will result in the
transformation of the austenite into martensite
and other product forms. See Fig. 38. Because
of this, exposure temperatures can be estab-
lished with reasonable accuracy if the lower
critical temperature has been exceeded.
STRESS-CORROSION CRACKING
Steels, as well as other metals, are subject to a
form of cracking called stress-corrosion crack-
ing. When under tensile strains, the austenitic
are this to between the lower and upper critical tempera-
of cracking if exposed to aqueous solutions tures (1330' to 160VF)for carbon steel tube material
containing caustic or halides, particularly (top) and to above the upper critical temperature
chlorides. See Fig. 39. Because the austenitic (bottom) both foliowed by rapid cooling because of
rupture. 500X nital etch
stainless steels are used most frequently in
superheated-steam environments, there is little
likelihood of exposure to damaging environ-
ments in service. But during the initital start-up
of a plant, the increased potential for exposure
to water contaminated with caustic or chloride
requires that precautions be taken to avoid "'

such contamination (see Chapter 21).


CAUSTIC EMBRllTLEMENT
Under certain exposures to high levels of
sodium-hydroxide, ferritic boiler steels can
experience a form of stress-corrosion cracking '\

which has been given the specific name of


caustic embrittlement. Leakage of caustic--- -
treated boiler water through crevices such as
rolled joints-which have residqal stresses in- Fig. 39 Very rapid failure of TP 316 austenitic steel
troduced during rolling-can concentrate through stress-corrosion cracking
COMBUSTION
. Metallurgy and Materials

caustic and result in cracking of the type shown stainless can provide protection against sensiti-
in Fig. 40. When boilers were of riveted con- zation and IGA. Those steels greatly reduce the
struction and crevices were the rule, it was tendency for grain-boundary depletion of chro-
much more commonly found than in today's mium. As indicated earlier, wet flue-gas scrub-
welded construction. Proper water treatment bers also need a type of stainless steel that is
can prevent caustic embrittlement. resistant to pitting attack; 317LMN satisfies this
SENSITIZATION requirement.
Austenitic stainless steels, when exposed to
elevated temperatures, may lose some of their CHROMlZlNG
corrosion-resistant properties at the bound-
aries between individual grains. (See subsec- Chromium is the most important alloying el-
tion "Grain Structure," this chapter.) The ement in steel for resisting oxidation and the
chromium in the steel has a tendency to com- various forms of corrosion encountered in
bine with the carbon and migrate into the boiler applications; this characteristic of chro-
grains, causing a depletion of chromium at the mium was discussed on. page 17-23. Chromiz-
grain boundary. This condition is called sen- ing, o n e means of providing the levels of
'
sitization. If sensitized steels are exposed to chromium necessary to resist such corrosive at-
corrosive aqueous solutions such as acids, the tack, is a high-temperature diffusion process in
grain boundaries can corrode preferentially re- which the surfaces to be treated are alloyed
sulting in intergranular attack (IGA). with chromium. Chromizing as used for the
In superheater and reheater service, sensiti- avoidance of exfoliation of steam-touched sur-
zation which occurs naturally as a result of ser- faces [page 17-28) is also useful for reducing
vice exposure presents no problem. But in maintenance costs and prolonging the life of
aqueous applications, such as wet flue-gas other boiler, components. C-E's shop-applied
scrubbers, IGA is a possibility at heat-affected chromizing process was specifically developed
zones of welded joints, which can become sen- for pressure parts installed in utility, industrial,
sitized by the heat of welding. and chemical-recovery boilers.
In these low-temperature applications, either In the diffusion process, an iron-chromium
a n extra-low-carbon grade of stainless steel, alloy is formed with a composition of 35 to 45
such as type 317LMN. or stabilized grades of percent Cr, approaching that of AISI 442 stain-
less steel. The depth and quantity of chromium
enrichment is a function of time at temperature.
The process is used for chromizing the outside
or inside, or both, of superheater or reheater
tubing, waterwall panels, piping, or headers, to
achieve high levels of Cr enrichment for depths
in the 10 to 15 mil range.
Coal-fired utility boilers, especially those of
the supercritical-pressure type, have suffered
from reducing-atmosphere attack of the fireside
of waterwall tubes. A number of owners have
installed chromized tubing panels with very fa-
vorable results. Chromized tubing, even when
Fig. 40 Caustic embrittlement, a type of stress-
located in areas having severe metal loss (up to
corrosion cracking associated with crevices in 60 mils per year) has shown itself to be highly
which caustic can concentrate. It is generally an in- resistant to sulfidation attack.
tergranular attack, although it can also proceed The firesides of tube with a high front-to-
transgranularly. back temperature differential sometimes suffer
CO~VsnON
Metallurgy and Materials

circumferential cracking. CZ'hile this cracking is wall tubing in a supercritical coal-fired unit
induced by thermal strain, the mechanism of suffered severe corrosion-fatigue cracking lvhile
penetration appears to be the result of repeated an adjacent chromized panel was found free
cracking or degradation of the semi-protective of such cracks after four years of service.
oxidation product formed on the tube surface. High-temperature ash corrosion and oxida-
The supercritical boilers experiencing sulfida- tion in superheaters and reheaters can often be
tion problems also have corrosion-fatigue addressed by upgrading the tubing material to
cracking in portions of the furnace walls out- the stainless steels. But there are instances
side the regions of most severe metal loss. Radiant- where it may be necessary or desirable to con-
wall reheater tubes of coal-fired units have also tinue to use a ferritic alloy such as T-22. In such
had this type of cracking. a circumstance, chromizing will be of benefit in
Chromized tubing has proved to be quite resis- providing resistance to ash corrosion and will
tant to this kind of thermally induced corrosion- significantly raise the effective oxidation limit
fatigue cracking. For example, bare T-11 water- of the material.

REFERENCES
5H. G. Edmunds and D.J. White, "Observations of the Effect
'Arthur M. Greene, Jr., History of the ASME Boiler Code. of Creep Relaxation on High-Strain Fatigue:' Journal of
New York; American Society of Mechanical Engineers. Mechanical Engineering Science, 8(3):310-321, Sept.
"merican Society for Testing and Materials, ASTM 1966.
Directory. Philadelphia: American Society for Testing and '#Graphitization of Steel Piping, presented at the annual
Materials, latest edition. meetings of the American Society of Mechanical Engi-
'Lawrence H.Van ~ l a b k ,Elements of Materials Science: neers, New York, NY, Nov. 29-Dec. 3, 1943; Nov. 27-Dec.
An Introductory Text for Engineering Students, 3rd ed. 1, 1944; and Dec. 2-6, 1946; under the auspices of the
Reading, MA Addison-Wesley Publishing Co., 1977. joint ASTM-ASME Research Committee on the effects of
temperature on the properties of metals. New York: Ameri-
'Lawrence H. Van Vlack, Elements of Materials Science, can Society of Mechanical Engineers, 1944, 1945 and
2nd ed. Reading, MA: Addison-Wesley Publishing Co., 1947, respectively. Issued as pamphlets and bound at the
1964, Table 11-1, Common Heath Treating Processes, pp. end of the Transactions of the ASME, Vols. 66. 1944; 67,
308-309. 1945; and 69, 1947; respectively.
CHAPTER 18

Steam-Generator Manufacture

anufacturing boiler components requires


M extensive equipment, machinery, and fa-
cilities. ~ o s of
t these fabrication operations
design objectives. The personal and computer-
driven lines of communication between design
and manufacturing functions must be main-
involve the use of steel tubing and plate. As the tained if overall production economy and high-
tubing and plate are built into furnace-wall quality products are to result.
panels, superheaters and reheaters, drums, New-product design needs have significant
headers, pulverizers, ductwork, and structural effects upon manufacturing processes. Stan-
members, various forms of welding are used. dardized production equipment may not be sat-
Heavy hydraulic presses are required to form isfactory, and new machines may have to be
segments of boiler drums and other pressure developed. The design of such equipment re-
vessels, and machining likewise plays a vital quires knowledge from many specialized
part in the manufacture of boilers. Heat treat- fields, including production practices, com-
ment, materials handling, inspection, and ponent design, materials, metallurgy, and
quality control are important adjuncts of the controls.
manufacturing operations. Since it is obvious that a large utility or
industrial boiler must be transported to the
jobsite in relatively small assemblies and sub-
THE INTERRELATIONSHIP assemblies, most shipments are made by rail
BETWEEN PRODUCT DESIGN car. A large utility-type unit will have 10,000
AND MANUFACTURE tons of boiler parts and equipment and more
... than4,OOO tons of structural steel supports, and
The steam-generator engineer must be con- will require about 200 railroad cars and 100
tinually aware of the interrelationship between trucks for shipment to the site.
product design and manufacture. A design re-
ASME CODE
sulting in improved heat-transfer efficiency
may be useless if the component cannot be fab- All U.S.-installed utility and industrial boil-
ricated economically and within the tolerances ers are designed and manufactured in accor-
proposed. On the other hand, savings in man- dance with the rules of applicable sections of
ufacturing costs cannot be justified if they re- the American Society of Mechanical Engineers
sult in finished elements which do not meet Boiler and Pressure Vessel Code, which is the
professional standard in the United States and selecting materials, welding process and pro-
in many other parts of the world. The ASME cedures, types of inspection, and thermal
Code is a set of regulations and guidelines in- treatments of welded assemblies.
corporating many details for design, manufac-
turing, and field construction to assure safe FABRICATION
construction of pressure parts of boilers. It is OF STEAM-GENERATOR
not a thermodynamic performance code. There PRESSURE PARTS
is nothing in it that tells how big a furnace must
be to burn a fuel or how large a drum is needed Welding is the basic tool for fabricating
to get dry steam. The Code does concern itself boiler components. While elements of a skilled
with the materials of construction, the design art are retained in some aspects, welding is a
aspects from a structural or pressure-parts recognized technical specialty that requires
standpoint, the fabrication rules (primarily substantial background in the fields of metal-
welding), the rules for nondestructive exam- lurgy, electrical,.and mechanical engineering.'
ination. and certain rules for certification In applying the welding process, metallurgi-
(which include third-party inspection). cal skills are necessary to determine the effects
This third-party inspection has been a fea- of chemical composition and metal structure
ture of the Code since its inception. It is this on the weld properties. Electrical engineering
which enables it to be a code rather than a stan- skills are required in designing the welding
dard. Construction of Code-stamped compo- power supply, welding controls, and related
nents must be by a manufacturer holding an equipment. Particularly in automatic fusion
ASME certificate of authorization. One re- welding, there must be precise control of the
quirement for such a certificate is the manu- welding arc as well as the welding machine,
facturer's arranging for the services of an and such control usually involves electronics.
authorized inspector to verify that the compo- Skills in mechanical engineering are essential
nents are constructed in accordance with Code to design automatic welding equipment, where
rules. The inspector performs such inspections the machine designer must have knowledge of
as he considers necessary in the shops of the mechanics, hydraulics, pneumatics, and heat
boiler manufacturer, and when he is satisfied transfer.
he so indicates by countersigning a certifica- In the sections that follow, the principal fab-
tion sheet (the manufacturer's data report). rication and welding operations for drums,
The materials in the pressure-retaining parts headers, furnace walls, superheaters and re-
of the entire boiler structure range from carbon heaters will be described.
steel for drums, headers, and tubular products
STEAM DRUM
to the high-chromium, high-nickel austenitic
stainless steels for "fire-exposed" parts of the The steam drum is a heavy-wall pressure
superheater and reheater assemblies. Each ma- vessel having hemispherical ends, with noz-
terial used in the pressure-retaining parts- zles and nipples attached for incoming and
drums, headers, tubing, piping, forgings, or outgoing water and steam. Fig. 1A illustrates a
castings-conforms to all the requirements of typical drum for a large boiler. In this figure,
an applicable ASME Boiler and Pressure Vessel the drum is fabricated in three cylindrical sec-
Code material specification. Furthermore, dur- tions, called courses, each welded to one
ing fabrication of each material used, the rules another and with a hemispherical head welded
relating to welding, material forming, and in- to each end of the three-course cylinder. Fig. 1B
q-ection of materials and the welds in them are and 1C show that each cylindrical section is
dictated by the ASME Code. Within the made up of a thick plate (called the tube sheet)
framework of the Code's establishing quality and a thin plate (called the wrapper sheet). The
standards there is considerable latitude for tube sheet is designed to withstand the
COMBUSTION
Steam-Generator Manufacture

(C Hemispherical Head

(A) Boiler Drum Consisting of Three (3) Course Cylindrical Sections

(Thick Shell) (Thin Shell) (Thick Shell) (Thin Shell)

(B') Preparation of Drum for (C) Drum Weld After Welding,


Longitudinal Weld, Section A-A Section A-A

Fig. 1 . Details of a large boiler steam drum


,

Fig. 2. The internals separate water from steam, direct the steam to the outlets leading to the superheater,
and provide an exit forthe water to be recirculated through the furnace-wall system.
COMBUSTION
Steam-GeneratorManufacture

--
Fig. 3. Ultrasonic tests are used to inspect plate material. Basically, this form of nondestructive testing uses
ultrasonic sound waves to detect flaws in materials and welds.

Fig. 4 Mammoth presses can bend and form steel plate 20 feet wide and 15 inches thick. Here a 6,000-ton
hydraulic-beam press is used for cold- and hot-working of plates.
COMBUSTION
Steam-GeneratorManufacture

specified pressure and temperature as well as (stee'l-making defects). The ultrasonic test is
the necessary additional reinforcement to com- conducted using a 2.25-megahertz longitudi-
pensate for the weakening effect of the multiple nal wave directed from one plate surface to the
holes drilled for the nipple attachments. The other. In this manner, the entire volume of a
wrapper sheet is designed to withstand the 12-inch band completely around the plate and
same pressure and temperature parameters but, a 24-inch-wide strip centered on the longitudi-
where openings are required for nozzles, the nal axis is tested. Fig. 3 shows the ultrasonic-
extra strength or reinforcement is provided by testing equipment being used for examination
extra thickness in the nozzle forging. This type of a thick drum plate. The forming operation
of steam-drum design provides the most eco- begins only after the plate soundness has been
nomical use of materials. The internals are assured by such ultrasonic tests and following
welded and installed as shown in Fig. 2. These a review of the test reports received from the
internals separate water from steam, direct the steel supplier.
steam to the outlets leading to the superheater,. The plates are heated in a furnace at 1650F,
and provide an exit for the [\rater to be recircu- and each plate is then moved to the 6,000-ton
lated through the furnace-\\.all system. hydraulic-beam press where it is incrementally
hot-worked into the required shell-course seg-
The Drum Plates
ment based on the nominal inside diameter of
The drum plate, which is carbon steel con- the drum. When the bent plate has cooled to be-
forming to ASlME Specification SA 299 or SA low 30OoF, but not less than 7ZF, it is then
515-70 (both carbon steels), is first ultrasoni- cold pressed to a specified, more precise con-
cally tested to assure required quality through tour than is possible to attain during the hot-
the absence of large laminations or seams pressing operation (Fig. 4).

Fig. 5. Each of the longitudinal edges of the bent plate is machine weid-beveled.

18-5
C0LII)USTION
Seam-GeneratorManufacture

The next step is to machine the weld bevel on using manual metal-arc welding with low-
each of the longitudinal edges as shown in Fig. hydrogen covered electrodes.
5. To make up a cylinder or shell course, a
Joining the Courses
series of tack welds join one bent plate with its
slightly thinner (wrapper) counterpart. The A three-course drum, as we have described,
longitudinal seams are welded using the au- is assembled by first joining two of the courses
tomatic tandem submerged-arc process to with a girth seam. Follo~ringthis, these two
deposit a succession of thin layers from the joined courses and the remaining course each
outside, all with a preheat of 300F. In the weld- have a hemispherical head welded to one end.
ing process, a blanket of granular fusible mate- The circumferential welds are ground, mag-
rial completely covers and shields the welding netic-particle inspected, and radiographed.
zone. Although referred to as flux, the material When the welds have passed inspection, each
performs functions in addition to those of flux. of the two assemblies is stress-relieved at
Visibly, there is no evidence of current passing 1150F a 25F. After the internals are put into
between the welding electrode and the compo- place, a final girth weld is made; this is locally
nent being welded. The electrode is not in ac- stress-relieved, followed by magnetic-particle
tual contact with the component. The welding testing of all welds. Fig. 8 shows a typical
current is carried across the gap through the steam drum ready for shipment.
molten flux which is supplied automatically
HEADERS
along the seam to be welded. The entire weld-
ing action takes place beneath the flux without Headers may be considered small-diameter
sparks, spatter, smoke or flash. When the outer versions of the steam drum just described, ex-
welding is completed, the inner side of the cept that headers do not have steam-separation
weld is back-gouged to,sound metal using the equipment in them. They collect water or steam
electric arc-air process. Next, the weld is fin- from a group of tubes assembled either in panel
ished on the inside using the automatic form or as a group of individual tubes. Headers
submerged-arc process, Fig. 6. As the outside are made from plate-formed pipe, seamless
portion of each weld is applied, about 20 per- pipe, or centrifugally cast pipe. The materials
cent of the weld is deposited in one seam. The usually employed are low-carbon steel, carbon-
shell is then rotated so that a similar amount of molybdenum steel and three types of chro-
weld can be deposited, with the required pre- mium-molybdenum steel.
heat, in the other seam; such a procedure helps Fabricating the cylinder or shell from plate
to control distortion. for headers differs somewhat from fabricating
Each cylindrical course is fabricated in the the drum shell course. To make a "plateformed"
same way. After welding, both the inside and header, the plate, after the required inspection,
outside of each longitudinal seam are ground is cut to a predetermined size and the long
flush and magnetic-particle inspected. This edges of the plate are bent in a 2,000-ton
operation is followed by radiography using a hydraulic pull-down forming press. This bend-
4-MeV (million electron volts) linear ac- ing operation may be done hot or cold, depend-
celerator, Fig. 7. If necessary, repairs are made ing upon the plate thickness and subsequent
using low-hydrogen covered electrodes at shell diameter.
300F preheat. Repairs are re-radiographed After the plate edges have been bent and (de-
until the welding is completely satisfactory. pending upon the material) the plate has been
Drilling for Nipples and Nozzles
heated in a furnace to between 1600 and
1750F, the plate is pressed into a U-shape and
Next, each course is drilled for the nipples: then into a cylinder, slightly larger than the re-
first, the holes for nozzles are oxy-gas cut; then, quired size. The two longitudinal edges are -
both nozzles and nipples qre welded into place trimmed and the cylinder is again heated and
COMBUSTION
Steam-Generator Manufacture

Fig. 6. An automatic submerged-arc welder finishes the inside long-seam of the cylindricalcourse.

Fig. 7. Each cylindrical course is inspected by radiography. Any subsequent necessary repairs are re-
radiographed until the welding is satisfactory.
COMBVSRON
Steam-GeneratorManufacture

--
Fig. 8 A typical steam drum is readied for shipment. High-pressure steam drums range in length to over 100
feet and weigh more than 500,000 Ibs. Shipment of these drums requires utilization of multiple rail cars.

set in dies in a 2,000-ton hydraulic four-post


press for final closing and sizing to specified
1) Shielded Metal outside diameter. (The long seam has yet to be
welded.) The formed shell is then cleaned by
Seal-Weld Pass grit-blasting and the long seam is fitted-up by
depositing a continuous manual weld outside.
Next, the shell is moved to the internal lon-
gitudinal seam welder, where the inside is
finish-welded under the specified preheat
conditions, Fig. 9A.
Seal-Weld Pass Machiningthe Shell

The longitudinal seam of the shell is then


machined to produce a welding groove on the
outside. During this machining, the manually
deposited seal weld is removed and the inside
automatic weld is machined to clean, sound
metal, Fig. 9B. Later, with the specified pre-
heat, the outside portion of the longitudinal
seam is completed using the automatic sub-
merged-arc process, Fig. 9C.
Upon completion of the inspection and upon
acceptance of the weld quality, the cylinder is
Outside Passes machined inside and outside to final required
dimensions.
Depending upon the length of the finished
header, cylinders and fittings are welded to-
gether and the ends may be closed in any one of
three ways, by: -
1. B ~ t t ~ w e l d i nang elliptical or hemispherical
cap on each end,
2. Welding a flat plate into each end of the cyl-
Fig. 9. Header longitudinal welding sequence. inder assembly,
COMBUSTION
Steam-Generator Manufacture

Fig. 70 Drilling and checking of tube holes in a pressure vessel

3 . Forging each end of the cylinder closed (an


operation called "wobbling").
The holes for nozzles and nipples are drilled
in the headers (Fig. 10) and then the nipples of
the desired shape are welded into the sockets
previously machined during the drilling oper-
ation. After all welding has been completed,
the assembly is stress-relieved. Fig. 11 shows a
completed header with nipples, ready for
rail-shipment.
FURNACE WALLS

C-E furnace walls are constructed of p.anels


made of tubes joined by fusion welding. This
construction provides a gas-tight "box" which
contains the burning fuel and hot gases. Gener-
ally, panels are built up with four tubes, each
75-feet long, welded together simultaneously;
single tubes and four-tube subassemblies are Fig. 77. Completed header for large boiler issecurely
added successively to make up about loadedon a rail car for delivery to utility destination.
5-feet wide. Details of this fabrication and of
the panel-processing welding machines (PPM) form the web between the tubes. Optimum
are shown in Figs. 12 and 13. web widths are in the 3/8 up to % in. range, and
the welder can fabricate panels of 7/8 to 3-1/2 in.
Fusion-Panel Welding
diameter tubes. The machine is capable of
In the PPM, three welding arcs simultane- welding carbon and alloy tubing at raies up to
ously deposit molten metal which solidifies to about two feet per minute.
--
COMBUSTION
Steam-Generator Manufacturn

The fusion panel welder shown consists of a during the welding cycle, the operator may
frame, three welding heads, tube drive, pres- stop or start one, two, or all three welding
sure rollers, copper chill bars, flux recovery heads.
and dispensing unit, filler-wire feed, tube After the three webs are welded, the panel
feed-in rack and conveyor, and feed-out and moves under automatic scaling hammers
storage racks. which remove the fused flux from the top of the
The feed-in rack and conveyor position tubes weld. The panel is then discharged from the
and panel segments against a gate which aligns machine onto the feed-out racks where it is
the tube ends. The alignment gate is then low- mechanically transferred to storage racks.
ered and the tube drive activated. Held in
Provision for Openings in Tube Walls
alignment by contoured pressure and drive
rollers, the tubes and panel segments pass It is necessary to provide openings in the
under the three welding electrodes where weld tubular walls for sootblowers, insertion of in-
wire and filler wire are fed into each arc. A struments, and access. A special machine
water-cooled .copper chill bar, under .each called an integral offset-bender makes small
welding arc and between the tubes, supports openings equal in width to one or two tube di-
the individual weld puddles until they solidify ameters. This machine actually cold-distorts
to form the webs between the tube. At any time tubes after the fusion-weld web joint between

Tu bes /--Contoured

Fig. 12. Schematic arrangementof fusion panel welder.


COMBUSTION
Steam-Generator Manufacture

Fig. 13. In panel welding, three welding arcs simul- bent-tube assembly is welded back into the
taneously deposit molten metal which solidifies to
form the web between the tubes. The machine can
opening to permit steam or water flow to con-
weld carbon and alloy tubing at rates up to about tinue through the panel but in a path that pro-
two feet per minute. vides the required opening as shown in Fig. 15.
These 75-foot panels, containing attachments
for buckstays and other structurals and for at-
taching insulation, are welded together in
place in the field to the required height, width,
and depth of the furnace. Generally, the field
welds are made by manual shielded-arc weld-
ing or tungsten-inert-gas welding, individu-
ally or in combination. It should be noted that
the welds joining the tubes lengthwise in the
panel are intentionally slit in the shop for ap-
proximately 18 in. at one end to facilitate the
precise alignment of one tube in a panel with its
counterpart in the panel above or below, or for
joining the tubes to headers or other connect-
ing tubes already in place.
Solid and Peg Fins
Fig. 14. An integral offset-bender makes small open-
ings by cold-distorting tubes after the fusion-weld Although the fusion-welded panel c3nstruc-
web joint between two tubes is cut. tion makes a gas-tight furnace enclosure, the
CONDUSTION
Seam-Generator Manufacture

space between tubes in the area of the furnace section is an assembly of such tubes, each bent
arch and in areas not exposed directly to fur- to a particular pattern. C-E uses an electric in-
nace radiation are filled by either a solid fin or a duction pressure-welding process to form butt
peg fin. The solid fin is a flat strip of steel welds on the long prebent tubes to form ele-
welded lengthwise to adjacent tubes where ment assemblies, Fig. 19. The induction pres-
spacing greater than 5/8-in~hcan be tolerated. sure welds are inspected by ultrasonic testing.
The fins are joined to two tubes at one time by a In continuous-fin construction, two strips of
. machine having four separate automatic sub- steel are welded longitudinally to the tube on
merged-arc welders. The fins are welded on diametrically opposite sides. Fig. 20 shows the
one side, then turned over; the back side of each fin detail and the fin welding operation.
previously made weld is again welded to pro-
vide a complete penetration weld. Peg fins, car- Shop Optimization
bon steel pieces approximately 1'12 in. wide To save time and labor at the jobsite, panels
with varying height, are electric-flash-welded such as superheaters and reheaters are joined to
to the outside of the tube. The "pegs" provide their respective headers in the shop prior to
heat transfer to the tubzand fill the space be- shipping in a process called "optimization"
tween adjacent tubes to retain refractory. that is intended to make the most economical
Rather than by bending individual tubes assembly for erection upon its arrival at the job-
which are then welded together, welded-wall site. To achieve this, the panels are welded to
panels that make up the furnace arch, bottom, the tube extensions or nipples on the header by
and roof section of the boiler are bent after they a miniature automatic welding machine that ro-
are formed into panels. Fig. 16 shows how tates about the two tube ends, the axis of which
these panel sections are mounted and bent on is horizontal. This is called "orbital" welding;
the shop floor during fabrication. a photo of the orbital welding machine is
shown in Fig. 21.
SUPERHEATERS, REHEATERS,
AND ECONOMIZERS
Unquestionably, optimizing shop work on
superheater and reheater sections has led to
These assemblies are made up of carbon lower forced-outage rates, which directly
steel, low-alloy steel, and nickel-chromium translates into higher availability. Modules up
stainless-steel tubing. Material choice depends to 11-feet wide are available that require only
upon gas and steam temperatures to which the field girth welds on the headers themselves.
'
tubing is exposed; it is selected in accordance All field welding of tubes to header nipples has
with ASME Code rules and the boiler manufac- been eliminated. Moreover, shipping and erec-
turer's design standards. tion rigs designed for use with these optimized
sections have virtually eliminated any damage
Shop Fabrication of Superheaters during either the shipping or erection stages.
To use materials effectively and economi-
The Economizer Section
cally, tubes up to40-feet in length are joined by
automatic metal inert-gas arc-welding to form a The boiler economizer section is another
single tube up to 150-feet long, Fig. 17. The butt type of tubular assembly, which may have its
welds on this assembly are examined by heating surface extended by fins. The amount
fluoroscopy and, when acceptable, the tube en- of heat transfer and the type of fuel usually dic-
ters an automatic bending line. Controlled by a tate the type of heating surface. C-Edesigns in-
previously prepared tape, this equipment clude spiral-finned tubes, continuous-finned
bends the long tube at the required location tubes, and bare tubes (those without-fins). The
(Fig. 18) and can be programmed to make either latter type is fabricated very much like a bare-
cold or hot bends. A superheater or reheater tube superheater or reheater.
COMBUSTION
- -
Steam-Generator ~anufact&

Fig 15 To make larger or wider openings than shown in Fig. 14, sections are cut from the panel. A prefabri-
cated bent-tube assembly is welded back into the opening.

Fig. 16. Entire tube assembliesthat make up, say, the furnace bottom or nose section, are bent in panel form
rather than by bending individual tubes.
COMBUSTION
Steam-GeneratorManufacture

Fig. 17. Automatic metal inert-gas arc-welding


NONDESTRUCTIVE machines join 40-foot lengths of tubes to form a
single tube up to 150-feet long.
EXAMINATION
OF BOILER COMPONENTS
In describing the operations performed in the
C-E boiler shops, reference has been made to
the several types of nondestructive testing
(NDT) for determining the integrity of the fab-
ricated components. By definition, NDT is a
means of inspecting an item without destroy-
ing its usefulness.
Several factors must be considered prior to
selecting an NDT method:
1. Type of imp~fectionexpected to be found:
deterioration, cracking, surface, volumetric;
2. Surface condition of areas to be inspected
(inside and outside surfaces);
3 . Orientation of defects: vertical to wall
thickness or horizontal to wall;
4. permitted severity of imperfections: e.g., 2
percent wall, 5 percent wall, serviceable
component;
5. Suspected cause of defect: improper chem-
ical cleaning, water treatment, draft, stress-
associated, improper welding.
Once the above conditions have been eval-
uated, the method of inspection can be de-
termined. Table I lists the most universally
used methods. All methods have limits and de-
pend on the ability of the performing inspector.
Yet regardless' of the inspector's qualifications,
destructive examination may sometimes be
required.
Of the four methods, radiography is the ac-
ceptance tool for conformance of pressure parts
to ASME Code requirements. Ultrasonic, liquid
penetrant, and magnetic-particle testing, on
the other hand, are used primarily to assure
quality in manufacture.
RADIOGRAPHY
Radiographic inspection is the most com-
- man volumetric inspection method used in the Fig- 18. After examination by fluorosco~y,tubes
which have passed inspection enter an automatic
to determine the bending line. Pmgrammable for either hot or cold
Many factors can affect the value of a operation, this equipment bends the long tube at
radiograph as an inspection method; a few are: required locations.
COMBUSTION
Steam-GeneratorManufacture

Table I.NondestructiveTesting Methods


Method Definition Uses Limitations
Radiographic Uses electro-magnetic Used on any metal stock High initial cost. Requires
rays @-rays and gamma or articles as well as a electrical power source.
rays) to penetrate material, variety of other materials Potential radiation hazard
recording on film to detect (and record on to personnel.
imperfections in the film) surface or subsurface
material. imperfections. Film
provides a permanent
record of the
discontinuities.
Ultrasonic Uses ultrasound to Used on metal, ceramics, Moderately high initial
penetrate material, plastics to detect cost. Interpretation of test
indicating imperfections surface and subsurface results requires highly
on an oscilloscope screen. imperfections: Wh'en '* trained personnel.
automated, permanent
records are available.
Also measures material
thickness.
Magnetic Particle Uses electrical current to Used on metal that can be Cannot be used on metal
create a magnetic field in magnetized (ferro- that cannot be
a specimen while magnetic) to detect magnetized. Requires
magnetic particles surface or subsurface electrical power.
indicate where the field imperfections. Simple to
is broken by an use. Equipment is portable
imperfection. for field testing.
Liquid Penetrant Uses a penetrating liquid Used on metal, glass, Does not detect
to seep into a surface and ceramics to locate imperfections beneath the
imperfection, thus surface imperfections. surface of a specimen.
providing a visible Simple to use and does
indication. not require elaborate
eaui~ment.

1. Thickness of the part 22). Normally, the radiation is produced by one


2. Radiation emitter physical size of two methods:
3. -llype radiation 1. Man-made radioactive isotopes, produced
4. Radiographic film selection
by placing an element into a nuclear reactor
and bombarding it with radiation; for example,
5. The distance the radiation source is placed the stable element iridium 191 becomes
from the subject radioactive iridium 192 after bombardment by
6. Quality of photographic processing radiation in a reactor.
7. The ability and experience of the Person 2. X-rays are produced by the sudden stopping
evaluating the radiograph of high-speed electrons in a vacuum tube.
8. Nature of. flaw and degree of acceptance
criteria ULTRASONIC TESTING
A radiograph, by definition, is a shadow pic- Ultrasonic testing (UT) is based on compari-
ture produced by the passage of X-ray or sons of the times it takes ultrasonic waves to
gamma rays through an object onto a film (Fig. travel through materials. After the test operator
Fig. 19. To form element assemblies, an induction pressure welder makes butt welds on the prebent tubes.
As part of standard quality assurance procedure, ultrasonic tests check welds for flaws.

Fig. 20. In continuous-fin construction, two strips of Fig. 21. Miniature orbital welding machines join
steel are welded - longitudinally to the tube on superheater elements to header nipples to makeop-
diametrically opposite sides. timized superheater modules.
COMBUSTION
Steam-Generator Manufacture

establishes the time for an ultrasonic wave to


pass through a good specimen of test material,
flaws are detected by deviations from the stan-
dard time pattern. In Fig. 23, Time A corre-
sponds to the wave entry into the material.
Time B corresponds to wave reflection at the
extremity of the test specimen. If a void within
the component interrupts the sound wave, a
portion of the sound is reflected back to the
transmitter (transducer) as a mechanical sig-
nal. A piezoelectric element in the transducer
changes the signal from mechanical to electri-
cal. The electrical signal created by the element
is then processed through the instrument and
eventually will be produced as an electronic
spike on the CRT of the ultraso6ic instrument.
In Fig. 2 3 , an internal void would cause a wave
disturbance to propagate to the surface (and the
transducer) sooner than waves reflecting from
the extremity at Time B. The electronic spike
would show up on the CRT between Times A
andB.
Ultrasonic testing is used for volumetric ex-
amination of welds and base materials for
flaws. When inspecting materials, the sound
Fig. 22. Schematic diagram showing the fundamen- wave is introduced into the part either normal
tals of a radiographic exposure. The dark region of to the surface or at predetermined angles,
the film represents the more penetrable part of the providing what is known as angle-beam
object; the light regions, the more opaque. (From
Radiography in Modern Industry, published by inspection.
Radiography Markets Division, Eastman Kodak Many factors affect the results of the ul-
Company.) trasonic inspection:

Ultrasonic Transducer ' Ultrasonic Machine

El\,
A-B

Time
Cathode
Ray Tube

Fig. 23. An ultrasonic transducer changes electrical energy to mechanical energy and mechanical energy to
electrical energy.
COMBUSTION
Steam-Generator Manufacture

1. Selection of calibration reflectors viewed in normal white light or a fluorescent


2. Ultrasound transmitterlreceiver selection dye that must be viewed under black light.
3. Material composition In contrast to the magnetic-particle testing
method, which normally is used on ferrous ma-
4. Surface condition (smooth vs. pitted)
terials, the liquid-penetrant method is primar-
5. Choice of equipment ily applied to austenitic stainless-steel and
6. Ability of the inspector other non-magnetic materials. In providing as-
In addition to ultrasonic testing of super- sistance to manufacturing and quality-control
heater and reheater tubes and electric-resis- people in a boiler shop, its major field of use is
tance-welded boiler tubes, ultrasonic tests are in giving indications of the length of imperfec-
performed on plate material over four inches tions that are open'to the tested surfaces of such
thick, induction pressure welds, base material materials.
in lifting-lug areas, and nozzle welds (which Among the present uses of liquid-penetrant
are tested on a sample basis). testing are (a) checking of austenitic weld de-
posits between composite austenitic-ferritic
MAGNETIC-PARTICLE TESTING
tubes in furnace-wall panels; (b) checking of
Magnetic-particle testing is a dry-powder, induction pressure welds where stainless steel
magnetic-field technique to detect surface de- is used on one side or both sides of the joint;
fects in and (c) as a check method for classification of
welds of fusion-welded panels ghost indications that have been detected by
butt joints on plates 1% inch or less in thick- magnetic-particle testing.
ness OTHER MANUFACTURINGPROCESSES
.back grooves of multipass submerged-arc
welding Many aspects of the fabricating process have
been omitted in this brief description of a typi-
machined longitudinal weld preparations of
cal steam-generator supplier's pressure-part
plate-fabricated pipe manufacturing facilities. Details of many types
longitudinal and circumferential drum welds of welding, of heat-treating methods of welded
after interstage and following final heat treat- assemblies, and of the inspection and quality-
ment control procedures must, for example, be
nozzle welds, and treated as separate subjects outside the scope of
internal and external attachments this text. Particularly lacking is reference to the
proprietary systems of computer-aided design
LIQUID-PENETRANT TESTING and fully computer-integrated manufacturing
Liquid-penetrant testing is a widely used that ark being installed by major manufacturers.
non-destructive test applied to nonporous ma-
terials. Its success depends on the ability of a
penetrating liquid to enter a surface opening by
capillary action, and remain in the opening
after the surplus penetrant on the surface is re-
moved. A developer is then used to draw the
penetrant out of the opening, back to the sur- REFERENCES AND FOOTNOTES
face of the nonporous material.
The visibility of surface imperfections to the An authoritative work on this subject is the Welding
Handbook issued ih several volumes andsevised period-
operator is increased by the addition of a dye, ically by the American Welding Society, United En-
which may be either a visible dye which can be gineering Center, New York.
CHAPTER 19

~ Field Construction of Steam-Generating Equipment

u his chapter describes the field-construction


activities associated with the erection of a
coal-burning steam generator and some of the
other associated power-plant equipment. The
components-the steam generator, turbine-
generator, condenser, emission-control equip-
ment, ash-handling equipment, fans, pumps,
piping, and valves. After equipment selection
information is of a general nature and does not and purchase, the owner frequently will have
reflect the detailed design and construction of a the engineer-consultant continue as the con-
specific unit. Rather, it represents common fea- structor, supervising the several contractors
tures of many of the large utility units being in- and subcontractors.
stalled throughout the world. Fig. 1 shows such Some of the crafts involved in the, erection
a large Controlled Circulation coal-fired unit as work are boilermakers, ironworkers, pipefit-
will be referenced repeatedly in this chapter. ters, millwrights, electricians, insulators,
operating engineers, sheet metal workers,
carpenters, teamsters and laborers. These per-
PLANNING AND ORGANIZING sonnel are hired at the local jobsite at the
FOR FIELD CONSTRUCTION beginning of the project or as the work pro-
An electric utility or large industrial organi- gresses i d are released once the portion of
zation will prepare the design criteria and work requiring their craft is completed.
scope documents, the detailed engineering The erection of a utility steam generator is a
specifications, and other technica1 data needed major portion of the work in the total plant. In
for a complete plant. This work is accom- many instances, the company that supplies the
plished either by a consulting-engineering boiler also constructs it. Early in the project,
firm retained to do the architectural and en- the erecting company sets up a field organiza-
gineering design, or by in-house personnel per- tion headed by a construction manager who is
forming all or part of it. experienced and knowledgeable in boiler erec-
On most projects, many different vendors tion and who holds the,authority to make deci-
supply equipment and services; some of them sions necessary to the operation. The
do their own erection on the plant site. As a re- construction manager's staff consists of con-
sult, the owner or engineer issues many spec- struction and welding supervisors, field engi-
ifications to the various suppliers of the plant neers, planninglscheduling and quality-control
--
C O ~ O N
FieM ConsCrucUon of StearnCenerating Equlprnent

\ \
Primary Air Ducts to Pulverizers Primary Air Fans

I
Fig. 1. Side elevation of large coal-fired steam generator for high-subcritical-pressure operation
COMBrnON
Fleld Construction of Steam-Generating Equipment I

engineers, field accountants, and clerical per- STRUCTURAL STEEL ERECTION


sonnel. Although all construction personnel Since a boiler structure is sometimes 250 feet
are charged with maintaining a safe operation, high, very large cranes are needed for erection.
a safety-engineer may also be employed as well Main cranes with boom heights of 280 ft and
i s a labor-relations specialist, if deemed neces- lifting capacities of 250 tons or more are com-
sary by the contractor. mon. One crew of ironworkers can erect about
It is the responsibility of this organization to 25 tons of steel a day with one such crane.
plan and schedule the work in accordance with Because of the large quantity of boiler steel
the overall project requirements; to perform the (often greater than 4000 tons for a 600-MW
work as designed in a safe and timely fashion, unit), boiler components, and other plant
assuring an adequate flow of materials, man- equipment and materials, it is usually impos-
power, and money to avoid any delay; to verify sible or uneconomical to store all the boiler
the attainment of specification and code re- items within reach of the main crane. A multi-
quirements; and to provide the documents and acre storage yard and adequate warehouse stor-
reports necessary to monitor the work. age are necessary for the material; such
additional equipment as lighter capacity
FIELD CONSTRUCTION OF A cranes, cherry pickers (small, rubber-tired
mobile cranes), and flatbed trucks are required
BOILER for moving the material to and from the storage
One of the first activities of the field- areas.
construction phase is the verification of the ac- There are basically two ways of erecting
curacy of all concrete foundations for the boiler. boiler steel. One is the tier method, shown in
All column-to-column dimensions, anchor-bolt Fig. 2. The other is the cube method. In the tier
locations, and concrete elevations are measured method, each elevation is completed to the
and verified against the drawings. splice point before another elevation is started.
In the cube method; sections of the steel are
built up to different elevations starting from the
turbine deck and progressing back toward the
stack. The structure is built in a horseshoe
Note: shape, leaving an open area for the crane to
Erection Sequence
Completes Entire back out as work is completed.
Steel Structure to The large sizes of some of the boiler compo-
the Same Tier Level
Before Proceeding nents, such as the ductwork, deaerator tank,
and sootblowers, require that these compo-
nents be installed as the building structure is
erected. For this reason, close coordination be-
tween the material suppliers and the construc-
Air Heater Loc tor is essential.
It is desirable in many instances for the boiler
erector also to erect the boiler support steel.
This facilitates the planning of erection se-
quences, and firm dates for finishing elevations
can be planned with a minimum of coordina-
tion problems or schedule disruptions. If the
steam-generator supplier does not erect the
structural steel, it is important that the supplier
be consulted so that steel erection and boiler-
Fig. 2. Tier method of steel erection
CO-ON ,

Field Construction of Steam-Genemting Equipment

Fig. 3 Erection sequence of a main boiler girder: 3A, main girder being lifted off the ground; 38, main
girder at an angle to the steel; 3C, main girder being set on the support columns; 3D, main girder in place,
ready for tie-in steel
COMBUSTION
Field Construction of Steam-Generating Equipment

components installation are coordinated, to has been erected. The drum, shown in Fig. I, is
preclude structural-steel blocking of the com- hung just below the main girder steel by means
ponent installation. of huge U-bolts that encircle the drum. Steam
The steel erection begins with the main drums currently being used may be 7 feet in -
boiler columns, usually starting on the turbine outside diameter, over 100 feet long, and weigh
and steam-drum sides of the unit. Then the as much as 300 tons.
main girders are erected. They support the
RAISING A DRUM
main boiler sections and the steam drum from
the top of the unit. There are usually 5 or 6 main As shown in Fig. 4, the drum is often raised at
girders spaced about 24 feet apart. Girder sizes an angle to the ground, because the bay may not
range from 6 to 20 feet high, 100 feet long, with accommodate the full drum length. Based on
weights approaching 160 tons. For structural the lifting lugs welded on the drum in the shop,
members of these sizes,,shipping to the jobsite the location of the support steel for the load
becomes a problem, since railroads have height blocks can be determined before construction
and weight limitations. is started. A set of "cat heads" (a temporary
MAIN-GIRDER ERECTION support for the upper portion of the-block-and-
Main-girder erection is one of many rigging tackle arrangement which is used to raise the
problems of the structural-steel erection pro- load) rests on top of the support steel, through
cess. The most accepted method of lifting the which the upper load block is pinned. The
heavier girders is to use two cranes in the fur- block can rotate according to the angle of the
nace cavity.'Lifting lugs are bolted to the top drum. The rigging usually consists of 1-inch
flange of the girder to attach it to the crane's cable with up to 1 7 parts of line on each set of
load blocks. Fig. 3A shows such a girder raised blocks.
off the ground with the two cranes. Because the The steam drum is usually brought inside the
girder rests on top of the structure columns, its furnace cavity on a railroad car and off-loaded
total length is longer than the open area be- with the lifting blocks. In the absence of a rail-
tween the columns. This requires the girder to road track, the cranes used for steel erection
go up at an angle to fit between the steel. This can off-load the drum and "walk it" to the lift
can be seen in Fig. 3B. Once the girder is raised area. The line-pull two-drum hoist that is used
above the column tops, one of the cranes moves for lifting is usually located on the ground with
the two load lines following a column line up to
-
its boom forward while the other noes back-
ward to bring the girder parallel to the front of
the boiler. The girder can then be set down on
the column tops as seen in Fig. 3C. At this time,
the top flange of the girder is very close to the
tubular framing on the boom. If the girders
begin to swing and touch the boom, the boom
could collapse. Once the girder is in place, (Fig.
3D),intermediate steel can be installed to tie a11
of the upper steel together. Coordinated radio
communication, highly experienced operating
engineers and rigging supervisors, and first-
class equipment are imperative for successful
girder erection.
STEAM-DRUM INSTALLATION
The steam drum can be raised into position at ~ i g4.. Lift of steam drum in boiler cavity.
the top of the boiler once the main girder steel (Note deaerator tank already in place)
COMBUSTION
Reid Construction of SteamGenerating Equipment

the top blocks hanging in the cat heads. Be- boiler suspended by hanger rods from the main
cause of the inner dimensions of the structural girders. This permits the boiler to expand
steel and the location of the cat heads, an out- downward as much as 15 inches as it heats up
haul such as that shown in Fig. 4 may be used to during the start-up of the plant. The correct set-
keep the drum from drifting into the steel work. ting of the pressure-parts support steel is very
Proper location of all rigging is important be- important because every part of the boiler is lo-
cause of the height of the boiler and the lifting cated with respect to this steel. It controls all
distance, which can be well over 200 feet. elevations and is continually used as a refer-
"DRIFTING" A DRUM
ence to align the different components as they
are erected. -
On some jobs, it is advantageous to erect the
platform steel that is under the steam drum INSTALLATION
OF UPPER HEADERS AND LINKS
along with the boiler structural steel. This can
involve steel in excess of 200 tons that can be Next, the upper headers and links are hung
put up more efficiently at that time. just b e l o ~ rthe pressure-parts support steel.
When steel has been erected such that the They may include the main steam lines to the -

drum cannot be lifted vertically from the turbine, the crossover links from the different
ground, the steam drum must be raised up in stages of the superheat and reheat systems, the
the boiler cavity to a height just below its final economizer lines to the steam drum, and the
elevation and then drifted into the drum-bay riser tubes from the waterwall outlet headers.
area. This will require 2 sets of cat heads and By the time these components are raised, the
blocks, and an extra set of lugs on the drum. crane used to erect the boiler steel has usually
Fig. 5A shows the drum located in the boiler been moved to the back of the unit and cannot
cavity with the first set of rigging attached to reach the areas where these components will be
the drum. To the left of the drum is the platform located. Therefore, most are raised from the
steel that the drum will be drifted over. Fig. 5B ground inside the furnace cavity using block
shows the drum up to the drift elevation with and tackle (a set of pulleys in a frame). The
the second set of rigging being attached to the components are then hung on their respective
second set of lugs while the first set still sup- hanger rods, which support the different boiler
ports the load. The temporary planks on the components, or are lashed temporarily to the
platform steel provide a work area and also pressure-parts support steel. The sequencing of
support the hanger rods. Fig. 5C shows the load component installation requires extra care on
being transferred from the boiler cavity to the units where there are multiple riser tubes to the
drum bay, with the load equally distributed in steam drum from the side-wall headers. These
all four blocks. In Fig. 5D, the drum is being pipe sections are usually 6 inches in diameter
raised to its final elevation, with the second set and as long as 40 feet. They are very flexible
of rigging supporting the entire load and the and may contain several compound bends.
first set slacked off. Other pipes between the various superheater
and reheater headers are often 30 inches in di-
PRESSURE-PARTS
ameter, with sections weighing as much as 10
SUPPORT-STEEL ERECTION
tons. They require proper sequencing because
While the steam drum is being erected, the of the difficulty of moving them once they have
pressure-parts support steel (upper region of been positioned between the existing hanger
Fig. 1)can be installed. This steel, located at the rods. Fig. 6 shows some completed main steam
top of the unit, supports all of the weight of the and reheat piping to the turbine. At this point
boiler. Unlike conventional structures that are in the installation of the boiler, no-pressure-
built from the ground up, most modern boilers part final welding has been started. All work
are built from the top down, with the whole has involved the placement of equipment.
COMBumoN
Field Construction of Steam-Generating Equipment
W d Constructionof Steam-Generating Equipment

The downcomers from the steam drum to the of the most difficult rigging on the boiler,
suction manifold, as shown in Fig. 1and Fig. 7, contain sections of tubes bent in complex con-
are raised into place after the above-mentioned figurations and welded together on a common
work is completed. Usually arriving on the job- section of header. Each module can measure as
site in 60-foot sections, downcomers are about much as 10 feet square and 55 feet long and
16 inches in diameter and weigh as much as 7 weigh up to 70 tons. They arrive on the jobsite
tons per section. Each downcomer requires partially encased in shipping rigs that are also
about 3 sections. Rigging must be located un- used to upend the module to a vertical position.
derneath the steam drum itself, because the A large crane and a cherry picker are needed
downcomers are welded directly to the drum to off-load the modules from the railroad car to
nozzles. Clips are welded on the ends so that a flatbed truck, which brings them into the fur-
threaded rods can be inserted to raise or lower nace area. A set of 75-ton capacity blocks are
the downcomer a few inches for proper po- rigged above the final position of the module.
sitioning for welding. The lower block is attached to a special
As soon as the downcomers are in place, spreader beam, shown in Figs. 8A and 8B. The
boilermaker welders can begin the fit-up and lower end of the module is picked up with a
welding procedures that will ultimately join cherry picker, while the main load blocks raise
the downcomers to the drum. A joint can be the header end. The flatbed trailer is removed
finished in about 1 M days if a two-person crew and the main blocks continue to raise the upper
works on each weld. end of the module, while the cherry picker
lowers the other end, thus orienting the module
SUPERHEATER AND REHEATER
MODULES INSTALLATION
in a vertical position for final raising. Rotation
to the vertical position is accomplished quite
The next boiler components to be installed easily with specially designed rods between
are the superheater and the reheater pendant the high-crown end bar of the module and the
modules. Fig. 1 shows their locations within spreader beam. The cherry picker and shipping
the boiler. These modules, which require some frame are then removed and the module is

Fig. 6. Main steam and reheat piping to the turbine Fig. 7. Downcomer piping from steam drum
COMBrnON
Field Constructionof Steam-Generating Equipment

lifted with the 75-ton blocks (Fig. 9). furnace cavity. This necessitates changing the
Because of the thick-wall tubes required to location of rigging almost every time a pick is
retain high-pressure steam, the superheater made. It is often helpful to locate a crawler
- modules are much heavier than reheater mod- crane inside the furnace area that has the ca-
ules. When a complete section of superheater pacity to boom in and out and swing around to
modules is in place, the header sections are fit- change its location. A crawler is very useful
ted together and prepared for welding. Girth and can be used throughout much of the steam-
welds made on the header sections connect generator construction.
the different superheater modules. (Fig. 10). The elevation of the previously erected pen-
Depending on the location of the modules in dant sections limits the height of the crane.
the furnace and the structural steel under- Upfront planning is necessary so sufficient
neath them, it is sometimes necessary to drift a structural steel is left out to allow access for the
module into place. To transfer the load to its crane into and out of the furnace. As the crane
final position, this lift requires two sets of is being brought in, the boom is laid all the way
blocks attached to a steel plate pinned to the down, parallel to the groand. A line is dropped
module. Generally. this procedure is required down inside the-furnace and attached to the
when the load is raised or "picked" inside the end of the'boom. The two lower pins on the
boiler cavity with the final location of the front boom section are removed and the section
component in the back pass of the boiler. is lifted with the line and rotated around the
upper two pins. This puts the top section at a
90-degree angle to the rest of the boom. The rig
is driven further into the furnace area for the
COMPONENT LIFTING length of another section and two more pins are
CONSIDERATIONS removed. The second section is raised to the
vertical position and the first two pins are re-
During the erection of the boiler compo- placed. This is repeated until all of the crane is
T
nents, hundreds of lifts are made inside the in the furnace cavity with the boom reassem-

Main Lifting Second Lifting


Dev~ce Front End
(Blocks)

Spreader
Beam

Header End Lugs

Tail End Lugs

Fig. 8A. Rigging for superheater and Fig. 88. Raisingof superheater and
reheater modules reheater modules
COMBUSrlON ,.
Rdd Construction of Steam-Generating Equipment

Fig. 9. Superheater module lilt within boiler bled in the vertical position. It is removed in the
same way. Fig. 11 shows a completed crane
within the furnace.
When most of the boiler is completed and
there is no more head room available for the
crane (about the time that the two lower head-
ers are attached), it is removed.
Another method of lifting inside the furnace
is with a guyed derrick located on top of the
unit above the main girders. Guyed derricks
can rotate 360 degrees on a bull wheel (the
lower support for the derrick) and can boom
out in any position. A system of guy wires
is tied off to boiler steel at different points
to support the mast from'which the boom is
rigged. When the boom is needed on the orher
side of a guy wire, the boom must be brought
up to the vertical position parallel to the mast.
Then, by rotating the bull ring, the complete
crane is moved to a new position and the boom
again lowered.
Other rigs used for lifting in the boiler.area
are stiff-leg derricks, Sky-horse cranes, ringer
and crawler cranes, and travel lifts. All these
are used in different ways and in varying
capacities.
Some units presently being erected have
very tall furnace heights, with top ,of structural
steel in excess of 350 ft, which no conven-

Fig. 10. Last module being fit into place. Girth Fig. 11. A completed crane boom within the furnace.
welds will be made between the header sections. Note the waterwall panels enclosing the furnace.
COMBUSRON
Field Construction of Steam-Generating Equipment

tional crawler crane can reach. These heights Fig. 12A. Tower section and tie-offs
sometimes require a "kangaroo" tower crane for the "kangaroo" crane
that sits in the center of the furnace opening
and can be used to erect the structural steel
and some of the boiler components. The tower
rests on a poured concrete base, held down
with anchor bolts and tied off to the structural
steel in several different places. The tower is a
square structural member and, with the crane,
can free-stand 160 ft above any tie-offs. The
crane is then capable of jacking itself in the air
14 ft and inserting another section of tower for
the crane to sit on. Fig; 12A, looking up inside
the furnace cavity, shows the tower with its 2
tie-offs to the steel and the crane on top.
Fig. 12B shows the crane after it has erecfed
the main girders and some of the fill-in steel.
While the structural steel has been going up,
the coal bunkers, ductwork, air heaters and
other components have also been erected. The
crane has 160 ft of boom and can reach almost
all sections of the boiler area. With the crane lo-
cated on top of the boiler, most of the steel can
be erected in the tier method.
BUCKSTAY ERECTION
Once the primary crane has been installed
inside the furnace, one of its first jobs is setting
buckstays at different elevations. The buck-
stays are structural shapes or trusses that
restrain movement of the waterwalls caused by
fluctuation in furnace pressure (see Fig. 1).
Buckstays may be all horizontal or may form a
system of large vertical steel members com-
bined with small horizontal members.
On boilers with both types, the main vertical
buckstays, which are sometimes 3 feet wide
and come to the jobsite in 60-foot sections, are
hung from the pressure-parts support steel. Be-
tween these are smaller horizontal buckstays
that are supported by the vertical buckstays.
SOOTBLOWER ERECTION
A crawler crane raises the long-retractable
and furnace-wall sootblowers and sets them on
the grating at their correct elevations. The type
of fuel to be burned determines the number, fig. 126.Crane on top of the unit with
type, and location of the blowers. Mounted hor- the main girders in place
COMBVSTION
Rdd Construction of Steam-Generating Equipment

izontally, they have a round tube or lance that is between header nipples and the panel tubes.
rotated by a driving motor. The sootblowers Such shop prefabrication can reduce the con-
clean the walls and elements of the steam gen- struction schedule and costs by eliminating
erator during operation. field welds, which are often performed under
One type of sootblower is the wall blower, adverse weather or logistic conditions. Other
which extends into the boiler only a few inches examples of shop prefabrication of waterwall
to clean the fireside of the waterwalls. A second panels include welding of buckstay stirrups, in-
type is the long retractable blower, which can stalling insulation pins, and fitting seal boxes
be inserted up to a distance of either full boiler on the observation openings.
width, or one half the width of the boiler, Another helpful shop procedure is the appli-
depending upon available space and owner cation of white paint to each panel to brighten
preference. These blowers extend between the interior of the boiler during erection. This
the sections of the superheater, reheater and technique, as shown in Fig. 13, improves work-
economizer to' clean the convection heat- ing conditions.
absorbing surfaces. Typically about 12 feet wide and 80 feet long,
waterwall panels are brought into the furnace
WATERWALL ERECTION
on a flatbed truck. Because they are so long and
Once the sootblowers have been laid on the flexible, the biggest problem with these panels
grating temporarily, the waterwalls which is upending them. Two lines are needed. The
form the sides of the furnace can be erected. crane in the hole lifts the top line; a cherry
The waterwalls are sections of tubes that are fu- picker, the other, in much the same way the
sion welded together into a gas-tight panel. superheater modules are upended.
They conduct a mixture of steam and water Sometimes, a special lifting device distrib-
upward as heat is applied from the furnace utes the weight so the panel will not buckle.
' side. The walls extend from the base of the This requires that several slots be cut in the
boiler (just above the ash hopper) up to the welded web between the tubes. A bar welded
steam-drum level. to a small T-beam is inserted and pinned on the
Waterwall panels may come from the shop back. This device assists in keeping the panel
with the upper headers already attached. When straight along its width during upending pro-
two panels are joined in the field, only one cess. When the panel is vertical, it is lifted up to
girth weld is then needed on the header. This its final position.
eliminates the need for numerous field welds The desuperheater (or desuperheaters) is

Fig. 13. Installation of waterwall panels. Fig. 14. Installationof roof tubes within
Vertical and horizontal buckstays are visible. furnace cavity
COMBUSRON
Field Constructionof Steam-GeneratingEquipment

raised and put in place at this time. Before the SUPPLEMENTARY FRAMING
superheated steam goes through the finishing
superheater assemblies, it passes through the Fig. 15 shows the structural framing between
desuperheater. Through a system of spray noz- the furnace "nose" and the vertical front wall of
zles that inject water into the steam, the de- -the convection pass of a large high-pressure
superheater controls the temperature of the steam generator. All of the steelwork shown is
steam delivered to the turbine. supported by the pressure parts; both the pres-
sure parts and these structural members have to
ROOF-TUBE ERECTION be designed to withstand the loads imposed, as
well as both positive and negative gas pres-
After the waterwalls are in place, the roof
sures as dictated by codes and owner spec-
tubes, see Figs. 1 and 14, can be erected usually ifications. The horizontal tubing in the top of
in either of two ways. One approach uses single the picture forms the floor of the gas pass
tubes that fit betweenthe vertical elements. In directly behind the furnace nose.
other areas with larger openings, full roof-tube
panels can be raised from the ground with a set 'AIR PREHEATER ERECTION
of blocks and a tugger, rather than with a crane.
While the roof tubes are being fitted into While the rest of the work is being done on
place, the intermediate waterwall panels are the boiler, the air preheaters, usually two per
lifted and fitted below the upper panels. Gen- steam generator, can be erected at the rear of the
erally, they are attached to the upper panels by unit. (See Fig. 1 for their locations.) The air
a system of threaded rods and clips that are preheaters are heat exchangers made of heat-
welded to the welded webs between the panel absorbing metal baskets assembled on a rotor
tubes. When this temporary hanging system is that is turned by a drive. Hot flue gases leaving
used, final panel spacing for weld-out can be the boiler pass through one side of the heater.
done with the threaded rods. Incoming cold air from the forced-draft fans
passes in counterflow through the other side.
The baskets are heated by thehot flue gases and
rotate into the cold air stream to raise the tem-
perature of the incoming air. Various seals pre-
vent the gas and air flows from mixing.
The air preheater is most often oriented with
a vertical shaft. Its main parts are the bearing,
bearing supports, baskets, oil circulating sys-
tem, drive motor, seals, casing and insulation.
On some projects, it is economical to fabricate
the main sections of the preheater on the
ground and raise them into place in the struc-
tural framework with a crane from behind the
unit. This method is very satisfactory if a large
capacity crane, such as the one shown in Fig.
16, is available. The extremely accurate meas-
urements required are performed by mill-
wright$. These include setting the clearances
between the rotor and seals, aligning the bear-
ing and support structure and setting the rotor
Fig. 15. The structural framing betweenthe furnace motor and roller pins. Boilermakers erect the
"nose" and the vertical front wall of the convection main housing and raise the air preheater into
pass of a large high-pressure steam generator place. They also level and set the preheater in
COMBUSTION
Field Construction of Steam-Generating Equipment

its final position in the boiler, as shown in Fig. welded to the bottom of the intermediate head-
17. Once the preheater rotor and other parts ers. Because the economizer tubes are often
are assembled, the heat-absorbing baskets are fabricated in a staggered pitch to increase heat
raised and moved into place. transfer and minimize space requirements, fit-
ting the last few elements sometimes presents a
ECONOMIZER ERECTION rigging problem. It is difficult to pass hoisting
While the air preheater is being erected, the falls through the staggered tubes. This often
economizer, located just above the air preheater means that the already installed elements must
(see Fig. I ) , can be erected. This is a heat re- be spread apart and the side walls must be
covery device designed to transfer heat from moved out.
the exiting flue gases to the incoming boiler WINDBOX-ASSEMBLY ERECTION
feedwater. The economizer consists of an in-
terconnected horizontal tube array. The upper After the intermediate waterwall panels are
ends of each economizer assembly connect to in place, the windbox assemblies, shown in
the outlet header, which is already in place Fig. 18, can be brought into the furnace and po-
above the roof tubes. sitioned for lifting.
Two types of economizer heating surface are The rigging of a furnace windbox assembly is
in common use on coal-fired units: one consists one of the most difficult tasks on the project be-
of a pair of longitudinal fins located 180 de- cause of the weight, shape and balance points
grees apart along the top and bottom of the hor- of the assembly. When the windbox comes
izontal tube; the second is bare tubing, similar from the shop, sections of waterwall tubing are
to horizontal low-temperature-superheater sur- attached to it, with the bends in the tubing pre-
face. Spiral-finned economizers are used on oil- fit around the windbox. These are welded into
and gas-fired units. the already erected wall panels and help sup-
Finned economizer tubes require careful port the windbox. Additional hanger rods sup-
handling because of the heat-absorbing fins. port the back side of the assembly. The average
They are grouped together in modules of 3 to 8 weight of the assembly is 25 to 30 tons. It is
elements, each with saddle supports installed raised in place using the crane in the furnace.

Fig. 16. Assembly of air preheaterson the ground Fig. 17. Air preheatersin place inside the building
COMBUmON
Field Construction of Steam-Generating Equipment
i
Because the back side of the windbox contains one pulverizer on each side is left out u'ntil
control arms, ductwork and insulated panels, it most of the required components have been
must be cribbed up on the low-boy truck when moved into the furnace cavity.
,.it is brought into the furnace cavity. A typical bowl mill (Fig. 19) contains about 6
Special lifting lugs are also installed in the sections, the first of which is the poured con-
shop to make the windbox assembly hang as crete foundation with four large anchor bolts.
close to plumb as possible while it is being The mill base, which contains the gear case on
raised. To ensure that the tip of the crane boom many mills, is set on top of the foundation. The
does not hit the waterwall panel above, special mill side assembly, where the grinding bowl is
care must be used when attaching the assembly located, is installed on top of this. The sep-
to the hanger rods. arator body, which contains the 3 roller jour-
nals and covers, goes on top of this. The
PULVERIZER ERECTION
separator, where the coal is classified cycloni-
Coal feeders, coal pulverizers, and the coal cally to the desired fineness, is next. The very
piping to the windbox are usually erected as top of the mill is the multiple-port discharge
part of the steam-generator contract. assembly. Here, coal is fed into the mill from
If shipping schedules permit, coal pulveriz- a central feeder and pulverized coal is
ers such as those shown in Fig. 1 can be set in discharged to the coal piping through the
place in sections as the structural steel is set. peripheral ports.
On a large unit, there are usually 6 to 10 coal Mills weigh up to 150 tons and are up to 30
pulverizers which are located on both sides or feet high. The crane that erects the structural
in front of the boiler at ground level. Generally, steel can easily set the heavy sections of each

Fig. 18. Windbox assemblies erected in place Fig. 19. Erection of bowl mills
--
COMBUSTION
Field Construction of Steam-Generating Equipment

mill. The lighter internals can be installed The suction manifold is hung from the down-
later. If the use of a crane is impractical, the dif- comers, which are welded to the steam drum.
ferent mill parts can be rolled into place on a The downcomer leads join the top of the man-
track and jacked into position. Ironworkers and ifold. Lugs are provided on the downcorners,
millwrights do most of the construction work (and also on the nipples of the manifold), so
on the mills, with the latter doing all of the that threaded rods can be inserted to hold the
alignment and settings because of the close tol- manifold after it is lifted. These can also be
erances that are required. used to adjust the weld gap for proper fit.
Simultaneously with the work on the bowl The manifold is usually lifted into place
mills, hanging and setting of the coal piping to using the crane in the furnace cavity. If the
the furnace can also be progressing. Welded crane is not used, blocks must be rigged under
joints and Victaulic couplings join sections of the steam drum with the rigging reaching
the pipe. Fig. 20 shows the final tightening of a down the full height of the boiler to hoist the
Victaulic coupling on an elbow that connects to manifold into place.
a windbox assembly. The boiler circulating pump assemblies are
usually raised and temporarily rigged before
SUCTION-MANIFOLD ERECTION the manifold is raised. As the lift is only about
8 tons for each pump assembly, the crane in
The suction manifold, also shown in Fig. 1,is the furnace can be used for this operation.
raised into place next. It is the collecting It is often advantageous to fit a number of
header that distributes the water from the pump components together on the ground
downcomers to the boiler circulating pumps. first. The discharge valves can be welded onto
the pump casings (Fig. 21) before erection.
The pump casing is a volute-shaped chamber
into which the pump impeller fits. The pumps
force the water from the manifold through dis-
charge links into the lower waterwall headers.
Check valves at the pump outlets prevent
water flow from backing up into an idle pump.

Fig. 20. Fuel pipe connections being made Fig. 21. Volute and pump assembly with a
to furnace windbox - discharge valve on each side
COMBUSTION
Field Constructionof Steam-GeneratingEquipment

A rigging beam can be used to install the the air preheater. It also includes the ductwork
electric motors and pump rotors. Millwrights from the air preheater to the induced-draft fans,
perform.the critical alignment of motors and to the gas cleaning equipment, and to the stack.
pumps. Most of this ductwork is installed after the air -
preheater is in place, usually with the same
DUCTWORK ERECTION
crawler crane that set the air preheater.
Ductwork erection must be completely inte- Dampers to isolate equipment or regulate
grated with boiler erection to avoid problems airflow or gas flow to and from the boiler are in-
in fitting ductwork sections into the structural stalled with the ductwork.
steel framework.
The boiler ductwork, as indicated in Fig. 1, LOWER WATERWALL HEADER ERECTION
consists of two main .systems, the air-supply
system, which includes the primary and sec- Typically, the lower waterwall headers are the
ondary air and the furnace-windbox ducts, last major lifts made inside the boiler and are
and the flue-gas system, which includes the installed after most of the pressure-part weld-
backpass ash hopper and ductwork to the air ing has been completed. The headers are up to
preheater, precipitators, absorbers (if in- 3 ft in diameter, extend the full width and
cluded), induced-draft fans, and stack. depth of the furnace, and weigh as much as 60
The hot-air ductwork from the air preheater tons each. During boiler operation, once the
to the windboxes, along with the burner con- water reaches the suction manifold from the
nection duct, contains some of the biggest downcomers, it is pumped into these headers
pieces of equipment on the boiler. Because of and up the waterwalls. Because these headers
the sizes involved, ductwork is generally as- are so heavy, a large cherry picker is brought to
sembled on the ground (Fig. 22) with septions the furnace to help the crane make this final
installed simultaneously with the structural lift. Once headers are in position, they are hung
steel. Hanger rods and expansion joints in the with hanger rods from the waterwall structure.
,
ductwork allow for thermal expansion. Some
ductwork sections are 20 feet by 30 feet in cross
section. At this size, temporary internal stiffen- WELDING
ers are often needed to provide strength during OF ERECTED COMPONENTS
shipping and erection.
The gas-system ductwork extends from the Thus far, as the boiler erection has pro-
bottom of the economizer to the exit side of ceeded, the different components have been
raised and hung by hanger rods or temporary
rigging. After a group of components is in-
stalled, the fit-up and welding must be per-
formed. Except for the structural steel, which is
most commonly bolted together, almost every-
thing else on the boiler is welded.
Several different welding processes are used
in the field. One such process is gas tungsten
arc welding (GTAW), in which a bare filler rod
is fed into the molten weld. The tungsten elec-
trode, which is not consumed, provides heat to
the workpiece. An externally supplied shield-
ing gas excludes the atmosphere from the weld
puddle. Argon is usually the shielding gas. al-
Fig. 22.
-- Ductwork fabricated on the ground though other gases or combinations of gases

19-
Field Constructionof Steam-Generating Equipment

may be used. Historically, this relatively slow facility.) For this .analysis, radiographic film is
process is used to put in the root (first) pass in placed on one side of a weld and a radioactive
pressure-part butt welds. source is temporarily placed on the other side.
The most extensively used process i s (Sometimes the source is placed inside a pipe
shielded metal arc welding (SMAW), more weld for a panoramic shot and other times the
commonly referred to as the "stick electrode" source is placed on the outside of a tube or pipe
process. In this process, the flux-covered elec- weld for a double-wall shot.) When the film is
trode is consumed in the weld. The flux coating developed, discontinuities may be disclosed re-
produces the shielding gas which is externally quiring interpretation by a qualified radiogra-
supplied in the GTAW process; it also promotes pher. Any discontinuity which is interpreted as
electrical conductivity across the arc column, a defect must be ground out and rewelded.
adds slag forming materials that help prevent Depending on the material specification of
rapid oxidation of the weld metal and, in many the component and the diameter and thickness
cases, adds alloying materials to the weld. This of the weld, postweld heat treating may be re-
process follows the GTAW root pass and com- quired to reduce the residual stresses induced
pletes the pressure-part butt weld. It is also by the welding. This stress-relieving process
used to weld ductwork, waterwall seams, and involves the placement of electric elements or
other plate and pipe components. coils, or gas burners, around the weld area of
The third process frequently used during the the component. A band around the weld joint is
field construction of boiler components is the brought up to a predetermined temperature,
gas metal arc ~velding(GMAW) process. In this typically 1100 to 1300F, at a controlled rate,
process, a machine feeds bare of flux-cored and is held there for a time period that is a func-
(flux-filled tubular) wire from a spool into the tion of the weld thickness. Thermocouples at-
weld. The wire is the consumed electrode as in tached at the outside of the heat band, or
SMAW. The shielding gas may be externally temperature-indicating crayons, are used to
supplied (as with GTAW) or may be supplied by monitor the temperature. The component is
the flux (as with SMAW) if flux-cored wire is then lowered to ambient temperature at a con-
used. This process is also used for ductwork, trolled rate.
waterwall seams, and other plate welding.
With increasing frequency, machine welding
is being performed in the field. In field ma- ADDITIONAL
chine welding, the equipment performs the CONSTRUCTION WORK
welding operation under the constant observa-
tion and control of'a welding operator. Ma- When the lower headers have been set in
chines which make pressure-part welds are place, the cherry picker and the crane are re-
called orbital-welding machines. They usually moved from the furnace,. Then the lower wa-
employ the GTAW process, although the GMAW terwall panels are brought i n and raised into
process is in the early stage of development for place, and the downtake system from the suc-
use in the field. The main advantage of orbital tion manifold discharge valves is installed.
welding is the higher quality of the deposited Additional work that can proceed simul-
weld. The improved quality results from the taneously in other sections of the boiler is
repeatability of the machine and the decreased attaching the buckstays to the waterwalls,
fatigue of the operators over manual welders. bolting the sootblowers to the waterwalls, con-
Field welds are radiographically examined as necting the piping for the sootblowers, and
required by code, contract, and self-imposed welding safety valves to the steam drum and
quality control standard requirements. (See outlet leads to the turbine. At this stage, a
Chapter 18 which describes radiography re- "punch list" of work that must be completed
quirements in a steam-generator manufacturing before the hydrostatic test should be compiled,
CoMBuSTIoN
Field Construction of Steam-GeneratingEquipment

so that all responsible contractors can be aware lations necessitating removal of 'sulfur oxides
of unfinished items. from the stack gases. Because of the large
amount of ductwork and tanks, it is usually eas-
ERECTION OF STEAM GENERATOR ier-to erect the absorber at the same time as its
AUXILIARY EQUIPMENT structural-steel support framing. Fig. 25 shows
Other equipment that is worked on during the tanks with much of the ductwork in place.
boiler erection are precipitators, absorbers, Once the main sections are up, the internal pip-
fans and the stack. The precipitator is located ing and spray sections can be installed. Be-
downstream of the steam generator proper and cause of the potentially corrosive atmosphere
removes the solid particulate from the flue inside the absorber, a noncorroding material,
gases. It rests on a structural-steel frame which such as austenitic stainless steel, is usually
is also tied into the main support members for used. Such stainless steel requires special han-
the precipitator. The hoppers are erected first dling and welding requirements not needed on
and lowered into the steel from above with a carbon-steel equipment.
crawler crane. The hoppers are usually subas- On large utility units, there are usually two or
sembled on the ground and erected as one more forced-draft fans that move combustion
piece. The main supports, sides and internal air through the air preheater and into the boiler
bracing are put up next along with the inlet and through the windboxes and two or more in-
outlet ductwork. The collecting and discharge duced-draft fans that pull the hot gases from the
electrodes, or other types of internals, are then boiler and direct them to the stack.
erected. The inner roof, weather roof, and elec- Fig. 26 shows two centrifugal induced-draft
trical components finish the main sections. fans partially completed. Once the support
Work on alignment, wiring and checkout is re-
quired before the unit is complete. Fig. 23
shows a nearly finished precipitator.
Absorbers, such as the one shown in Fig. 24,
are installed as.required by environmental regu-

1 Fig. 23. Precipitator during final construction Fig. 24. The erection of a stainless-steel absorber I
COMBVSnON
Field Constructionof Steam-Generating Equipment
--
foundations are poured, the lower rotor hous- HYDROSTATICTESTING AND INSULATION
ing, bearing supports, and rotor are installed.
Then the remaining inlet chambers and outlet During hydrostatic testing, water is pumped
boxes are put together and connected to the into the complete water and steam circuits of
supply and discharge ductwork. Millwrights the boiler and raised to the pressure of 1112
set and align the rotor, a critical job because of times the maximum allo~iableworking pres-
the close tolerances required. sure (MAWP). The pressure is held for a speci-
fied period of time and then lowered to the
MAWP and held there for another period. The
entire boiler, including piping, valves, wall
panels, and drums; is then inspected for leaks.
If any are found, the pressure is dropped, the
water is drained out, and the leak is repaired.
The entire process is then repeated until no
more leaks are apparent. A steam-generating
unit is "built-in accordance with the ASME
Boiler Code" only when it has successfully
passed such a hydrostatic test of the entire unit,
either in the shop or in the field.
The erector engages the services of a steam-
boiler inspection agent who is responsible for
verifying the inspection and assuring the integ-
rity of the boiler to the owner. The owner usu-
ally has its own insurance representative on the
job at the same time to look over the records and
ensure that proper inspection and tests are per-
formed.
Fig. 25. Section of absorber steel and ductwork

Fig. 27. Turbine pedestal with most componerits


Fig. 26. Induced-draft fans under construction set in place
COWBUSPlON
FieldConstructionof Steam-GeneratingEq~llpment

Once the hydrostatic test is complete, the in- proceeds while the boiler is being erected and
sulation and lagging installation can proceed. includes the turbine generator, miscellaneous
Insulation blankets or blocks are installed on pumps and valves, the water-treatment systems,
a[ piping, waterwalls, drums and ductwork. the boiler feed pumps, and the condenser to
~ i t a lagging
l is installed over the insulation name but a few. The turbine generator is a large
for protection of equipment and personnel. A section of the mechanical work and requires al-
coating of refractory is troweled on the top side most the same time span for erection as the
of the roof tubes and a steel "skin" casing is boiler. Fig. 27 shows a turbine under construc-
welded over the top. tion with most of the components already in
If the unit is an outdoor unit, the lagging place. The overhead gantry crane (upper left
serves to protect the boiler from the weather as corner of Fig. 27), one of the first pieces of
well as to provide a satisfactory appearance. If equipment erected, is used to raise and set most
the unit is an indooranit, the boiler is com- of the turbine except the stator.
pletely enclosed by an outer building. This is Because the stator is so heavy (200 to 400
desirable in cold climates, making initial erec- tons), a special lifting rig is usually brought to
tion and subsequent maintenance easier in the the site just for this one lift. Fig. 2 8 shows a
winter months. stator entering through an access opening from
the ground. This rig uses a system of grip-type
ERECTION OF MECHANICAL EQUIPMENT
jacks with steel cables to lift the stator from the
The installation of mechanical equipment railroad car and up to the turbine-pedestal
floor. Once the stator is up to elevation, special
rolling beams are put under the stator. The
stator can be lowered a few inches onto special
heavy-duty rollers and rolled from the lift frame
onto the concrete turbine floor. The stator is
transferred to the generator hole and lowered
again using the upper section of the same ,
lift rig.
ERECTION-COMMISSIONING INTERFACE
With most of the major work done on the
boiler, boilout and acid cleaning of the inside
of the tubes can be done. Chemicals are circu-
lated through the boiler for prescribed lengths
of time and then drained from the boiler. These
procedures remove internal scale from water-
bearing systems and assure free water passage
in all tubes, headers and drums. (See Chapter
21 for a description of boilout and acid-
cleaning of high-pressure steam-generators.)
Installation of boiler-drum internals may
now be completed and access openings closed.
The contractual responsibility for the erec-
tion phase is usually complete at this point;
however, support crafts for assisting test and
start-up engineers may be necessary to take
Fig. 28 Stator lift rig with grip-type jacks used to
care of items that require modification andlor
raise stator from ground level to turbine floor replacement during commissioning.
--
CHAPTER 20

Water Technology .

w ater is a basic engineering material used


in the production of steam for power gen-
eration and process use. Effective treatment
or conditioning of water has made possible
nonscaling composition. If water were pure
''H20" and nothing else, or were of a constant
solids composition, the conditioning of water
for industrial use would be uniform and simple.
the use of more efficient steam cycles in the Because this is not the case, the conditioning of
subcritical and supercritical pressure ranges. water contains elements of both a specialized
Many industrial processes have special re- science and an engineering art.
quirements for high quality water, free from ob- In using water for generation of steam for
jectionable contaminants. process or electric power, consideration must
These statements are indicative of the signif- be given to water treatment for the prevention
icant role of water technology as an interdis- of corrosion, scaling, and contamination of
ciplinary professional field which comprises steam. Such attention must involve the treat-
elements of basic chemistry as well as chemical ment of the raw water introduced into the cycle
and mechanical engineering. This chapter will and, in many cases, the conditioning of the
discuss specific boiler applications of water water present in the preboiler cycle and in the
technology, but many of the same consid- boiler itself. How much consideration is given
erations hold for various types of process oper- to the contaminants present in water depends
ations. In practically every instance, a careful largely upon the end use of the water. The pres-
review of sources of water and its condi- sure of a boiler is used to classify particular
tioning is required to avoid economic losses boiler designs. Therefore, the water quality nec-
because of slowdown in production, damage to essary for a particular application is by conven-
equipment, and increased costs of operation. tion related to boiler pressure, even though it is
The sources of water supply to an industrial realized that the corresponding fluid temperature
site differ and can originate from a polluted is the real factor influencing the reactivity of
river or stream, mountain runoff, wells or a chemical and corrosion processes. The quality
lake. The composition of impurities in water of the water in a plant becomes more critical as
varies over a wide range. Water may be pol- the cycle advances from low-pressure industrial
luted with sewage, chemical or organic wastes, type boilers to high-pressure utility boilers.
bacteria, dissolved gases, suspended mineral As major causes of forced outages, internal
matter and dissolved solids of both scaling and corrosion and deposition cost electric utili-
-
Table I.Common Impurities Found in Water
Constituent Chemical Formula Difficulties Caused Means of Treatment
Turbidity None-expressed in Imparts unsightly appearance Coagulation, settling and
analysis as units. to water. Deposits in water- filtration.
lines, process equipment, etc.
Interferes with most process
uses.
Color None-expressed in May cause foaming in boilers. Coagulation and filtration.
analysis as units. Hinders precipitation methods Chlorination. Adsorption by
such as iron removal and sof- activated carbon.
tening. Can stain product in
process use.
Hardness Calcium and magne- Chief source of scale in heat Softening. Demineralization.
sium salts expressed exchange equipment, boilers, Internal boiler water treatment.
as CaC03. pipelines, etc. Forms curds Surface-active agents.
with soap, interferes with
dyeing, etc.
Alkalinity Bicarbonate (HCO3), Foaming and carryover of sol- Lime and lime-soda softening.
carbonate (Cod, and ids with steam. Embrittlement Acid treatment. Hydrogen
hydrate (OH),ex- of boiler steel. Bicarbonate and zeolite softening. Demineral-
pressed as CaCO,. carbonate produce CO, in ization. Dealkalization by
steam, a source of corrosion in anion exchange.
condensate lines.
Free Mineral H,SO,, H a , etc. ex- Corrosion. Neutralization with alkalies.
Acid pressed as CaC03.
Carbon co2 Corrosion in waterlines and Aeration. Deaeration. Neutral-
Dioxide particularly steam and conden- ization with alkalies.
sate lines.
PH Hydrogen ion con- pH varies according to acidic pH can be increased by alkalies
centration defined as: or alkaline solids in water. and decreased by acids.
pH = log - 1 Most natural waters have a ph
/H +I of 6.0-8.0.
Sulfate (so,) - - Adds to solids content of water, Demineralization.
but in itself, is not usually sig-
nificant. Combines with calcium
to form calcium sulfate scale. .
Chloride C1- Adds to solids content and Demineralization.
increases corrosive character
of water.
Nitrate (NO,) - Adds to solids content, but is Demineralization.
not usually significant industri-
ally. Useful for control of boiler
metal embrittlement.
Silica SiOI Scale in boilers and cooling . Hot process removal with mag-
water systems. Insoluble tur- - nesium salts. Adsorption by
bine blade deposits because of highly basic anion exchange
silica vaporization. resins, in conjunction with
- demineralization.
COMBUSTION
Water Technology

Table I. Common Impurities Found in Water -Continued


Constituent Chemical Formula Difficulties Caused Means of Treatment
Iron Fe ++ (ferrous) - ~iscoiorswat& on precipitation. Aeration. Coagulation and
Fe +++ (ferric) Source of deposits in waterlines, filtration. Lime softening.
boilers, etc. Interferes with dye- Cation exchange. Contact fil-
ing, tanning, papermaking, etc. tration. Surface-activeagents
for iron retention.
Manganese 1Mn-+ Same as iron. Same as iron.
Oxygen 0 2 Corrosion of waterlines, heat Deaeration. Sodium sulfite.
exchange equipment, boilers, Corrosion inhibitors.
return lines, etc.
Hydrogen HIS Caus; of "rotten egg" odor. Aeration. Chlorination. Highly
Sulfide Corrosion. basic anion exchange.
Ammonia NH3 Corrosion of copper and zinc Cation exchange with hydrogen
alloys by formation of complex ze6lite. Chlorination. Deaera-
soluble ion. tion.
Dissolved None "Dissolved Solids" is measure Various softening process, such
Solids of total amount of dissolved as lime softening and cation
matter, determined by evapo- exchange by hydrogen zeolite,
ration. High concentrations of will reduce dissolved solids.
dissolved solids are objection- Demineralization.
able because of process inter-
ference and as a cause of
foaming in boilers.
- -

Suspended None "Suspended Solids" is the meas- Subsidence. Filtration, usually


Solids ure of undissolved matter, preceded by coagulation and
determined gravimetrically. settling.
Suspended solids cause deposits
in heat-exchange equipment,
boilers, waterlines, etc.
Total Solids None "Total Solids" is the sum of See "Dissolved Solids" and
dissolved and suspended solids, "Suspended Solids."
determined gravimetrically.

'Adapted from Betz Handbook of Industrial \Voter Conditioning 8th Edition. 1980 Betz Laboratories. Inc.. Philadelphia. Pa.

ties millions of dollars in repairs and lost ter to minimize corrosion and formation of pre-
availability. This is both unfortunate and un- boiler corrosion products, which end up as de-
necessary; the causes of corrosion are generally posits on heat-transfer surfaces in the boiler.
known and there are effective means of Pre- .Comply with operating procedures during
venting or reducing damage from corrosion: start-ups, shutdown, and outages to minimize
rn Maintain recommended water treatment for
corrosion and to avoid the entry of corrosion
both the boiler-water and feedwater systems. products into the boiler.
Maintain boiler free from significant amounts
C o n t r o l oxygen concentrations in the feedwa- of deposits by periodic chemical cleaning.
--
CO~OSI?ON
Water Technology
-
boilers requiring very pure water, the term
TECHNIQUES parts per billion (ppb) is now in use. One ppb
OF WATER TREATMENT equals 0.001 ppm.
RAW-WATER PROCESSES
The extent of water conditioning or treat-
Raw water contains various gaseous and
ment depends both on the original supply
solid impurities which must be reduced before
source and the ultimate end use of the product.
the water can be supplied as makeup to a boiler.
Table I lists common impurities found in water,
This is particularly true if the water is taken
sets forth some of the resulting problems, and
indicates common treatment methods. from a river .which may be contaminated with
mine washings, gases, organic and chemical
The techniques of water treatment cover a
wastes as well as silt and other minor impuri-
wide variety of raw-water preparation schemes.
ties. To reduce these substances, the processes
This is covered in detail in established refer-
of aeration, settling, coagulation, and filtering
ences.' Some of the basic chemical reactions
are commonly used. A brief description of each
involved in the treatment of raw water to pro-
method follo~\.s.
duce suitable makeup for boilers will be dis-
AERATION
cussed in a general manner.
Any evaluation of water conditioning must This process (Fig. 1) removes such undesir-
consider the impurities present in power- able gases as carbon dioxide and hydrogen sul-
station raw-water makeup in relation to tenden- fide from water by admixing water and air to
cies toward scaling, corrosion, and deposits. reduce the solubility of the objectionable gas in
Raw water contains many contaminating ele- water. The removal of gas follows Henry's Law
ments including (a) mud, clay and silt; (b) oxy- which indicates that the solubility of a gas in
gen, carbon dioxide and hydrogen sulfide; (c) water is directly proportional to its partial
sewage, bacteria and 'algae; (d) scale-forming pressure in the surrounding atmosphere. The
compounds of calcium, magnesium and silica; partial pressure of a gas such as carbon dioxide
(e) oil; (f) iron compounds; (g) organic wastes; is low in a normal atmosphere. Establishing an
(h) sulfuric, hydrochloric and other acids; (i) equilibrium between water and air by aeration
normally soluble compounds, such as sodium results in saturation of the water with oxygen
bicarbonate, sodium carbonate, sodium hyd- and nitrogen and results in the practical elimi-
roxide and sodium chloride. nation of such gases as carbon dioxide and hy-
Table I1 gives typical analyses of water drogen sulfide. Increasing the temperature, the
_ supplies of the U.S. The river water analyses aeration time and the surface area of water im-
are of filtered water, and for the most part rep- proves the removal of gases.
resent yearly averages. River waters change COAGULATION
considerably with the seasons, and the max- Adding chemical coagulating materials re-
imum and minimum concentrations may be 50 duces surface-water contamination in the form
percent above and 50 percent below the aver- of coarse suspended solids, silt, turbidity, color
age. Spring and well waters and waters from and colloids. The chemicals form a floc which
large lakes have a fairly constant c~mposition.~ assists in agglomerating impurities. Settlement
The usual unit for reporting dissolved and of the particles permits a clear effluent from the
also suspended solids in feedwater and boiler coagulating chamber. Fig. 2 illustrates a typical
water is parts per million (ppm). This is a ra- clarifier. Removal of colloids requires a careful
tional unit which is easily understood and analysis of the - impurities to establish the
which avoids misunderstanding. In other nature of their electrical charge, one of the
words, one million pounds of water will con- principal factors contributing to their remain-
tain so many pounds of solids. With high ing in the suspended state. Some chemicals.
subcritical-pressure and supercritical-pressure used for coagulation are filter alum, sodium
COMBUSTION
Water Technology

aluminate, copperas, ferrisul, activated silica, Copperas (formation of ferrous hydroxide)


and various proprietary organic compounds. +
FeSO, Ca(HC03),
Temperature, pH, and mixing affect the effi- CaS04 + Fe(HC03),
- ciency of coagulation. Some of the reactions Fe(HC03), + 2Ca(OH), +
involved are Fe(OH), + 2CaC0, + 2H@
Ferrisul
Filter alum (formation of aluminum hydroxide) Fe2(SOd3+ 3Ca(HC03),%
A12(S04)3+ 3Ca(HC03), -* 2Fe(OH), + 3CaS04 + 6CO2
3CaS0, + 2Al(OH), + 6C02
FILTRATION
Sodium aluminate
6NaA10, + A12(S04)3.1 8 H a + Filters separate coarse suspended matter
E A ~ ( O H+) ~3Na,S04 + 6H20 from raw water, or remove floc or sludge com-

Table 11. Analyses of Typical Surface and Ground Waters in the. United States
AnalysisNumbeP ......... 1 2 3 4 5 6 - 7 8 9 10 11 12 13
Silica (SiOd . . . . . . . . . . . . 2.5 0.4 2.3 8.2 1 3 8.0 8.4 9.6 16 23 34 12 39
Iron (Fe) ............... 0.03 0.05 .09 .12 0.04 0.15 0.04 0.0 2.1 .09

Calcium (Ca) ........... 5.3 27 32 1.7 72 79 40 3.4 7.2 70 26 72 7.2


Magnesiuml(Mg) ....... 1.7 7 10 0.4 6.4 28 16 1.5 2.5 24 10 33 4.2
Sodium (Na) ........... 1.4 3.5 1.9 41 147 12b 138
99 94 5.6 3 5 ~7.5 ~
Potassium (K) .......... 0.6 3b 1.0 0.7 4.7 4 0.4 1.6

Carbonate (CO,) ........ 0 1 0 0 0 4 0 0 0 0


Bicarbonate (HCO,) . . . . .10 99 138 3 174 137 46 21 328 179 170 293 50
Sulfate(S0,) ...........11 13 17 4.4138 290 298 3.3 2.6135 70 560 .0.8
Chloride(C1) ........... 2.6 7 6.5 2.6 9.5 79 14 3.6 51 8 139 ,195 6.8
Fluoride (F) ............ 0.1 0.1 0.6 0.4 0.4 0.1 0.2 0.8 2.5 0.0
Nitrate (NO,) ........... 0.3 0.2 0.2 4.0 0.2 3.6 0.7 0.0 0.0 1.1 0.0

Dissolved solids ........34 130 171 23 386 661 554 42 392 392 503 1380 90'

TotalhardnessasCaCO, .20 98 121 6 206 315. 166 15 28 276 106 316 35


Noncarbonate hardness.. 6 16 8 3 64 197 128 0 0 126 0 76 0

Specific conductance .. .53.4 263 29.5 575 1040 822 55.5 651 867
(micromhos at 25 C)

Color .................. 1 3 15 5 6 4 10 0 2.5


pH ....- ................ 6.9 8.1 8.2 5.8 7.7 8.4 7.6 7.0 8.0 7.6 7.9 7.5
" Analyses numbers are identified as follows: 9 = Houston,TX. !\'ell 1932 ft deep.
1 = New YorkCity, NY,Catskillsupply (reservoir-finished). 10 = Jacksonville, FL, \Yell 1064 ft deep.
2 = Detroit. MI. Detroit River (raw). 11 = El Paso. TX. Well 703 ft deep.
3 = Chicago. IL. Lake Michigan (raw). 12 = Galesburg.IL, Well 2350 ft deep.
4 = Fitchburg. MA. Pond (finished). 13 = Bremerton, WA. Anderson Creek.
5 = Omaha. NE,Missouri River (raw). 'Computed by differencein epm and reported as sodium.
6 = Los Anaeles, CA. ColoradoRiver (raw). Sum of determined constituents.
7 = Pittsburgh. PA, Monongahela River (finished).
8 = Macon, GA. Ocmulgee River (raw). Values are in parts per million where this unit is appropriate.
COMBUSTION
Wator T.chnology

Fig. 1 Forced-draft aerator ponents from coagulation or process softening


systems. Generally, gravity and pressure-type
filters as shown in Figs. 3 and 4 are used for this
purpose. Beds of graded gravel or coarse an-
thracite are the common materials used in the
filter bed. Diatomaceous earth and special pre-
coat filters are generally used to remove oil and
Distributors reduce color in feedwater makeup.

CHEMICAL SOFTENING PROCESSES

Nonscaling feedwater can be obtained with


proper pretreatment of raw water. Various
chemical combinations can remove hardness,
silica and silt from makeup water. Economics
and boiler operating conditions dictate the tech-
nique selected for the application.
LYE-SODA SOFTENING

To soften water by this process, lime (cal-


cium hydroxide) is added to precipitate the
calcium bicarbonate as calcium carbonate and
magnesium salts as magnesium hydroxide.
Soda ash (sodium carbonate) is added to react
Air Seal with calcium chloride and calcium sulfate to
Water Outlet form calcium carbonate. The general reactions
are as follows:

and Reaction Zone

--
Fig. 2 Solids-contact clarifier
Fig. 3 Gravity filter

Rate of Flow Loss of Head

Because of the increase in reaction rate and the


decrease in solubility of calcium carbonate,
this process is more efficient at hot tempera-
tures. The hardness in the effluent of a cold
lime-soda process depends upon the excess of
soda ash and is generally above 33 ppm. Alka- ", .
linity reduction depends on the removal of
Rate of Flow Unit magnesium and calcium bicarbonates. In the
Loss of Head Unit hot lime-soda process, the hardness residual in
the effluent ranges from 17-25 ppm.

Backwash Line
and Rate Set Valv

Rinse Line
and Rate Set Valve

Fig. 4 Vertical-type pressure sand filter


--
COYIVSTION
Water Technology

HOT-PROCESS PHOSPHATE SOFTENING hardness water is handled in a two-stage soft-


In this process, phosphate chemically pre- ener arrangement. The hot-process phosphate
cipitates calcium and magnesium salts. The softener is particularly suited for turbid waters,
calcium hardness is precipitated in the form of which are low in hardness and alkalinity. Soft-
tricalcium phosphate and the magnesium as ening, turbidity control, deaeration and silica
magnesium hydroxide. Chemical reactions are reduction can be combined in a single unit.
completed at a temperature of 212OF or above. Fig. 5 shows a typical hot-process settling
The reactions can be controlled to reduce the tank. Usually, surface-acting organic agents are
hardness to nearly zero. added to stabilize the precipitates formed in
Normal low hardness, below 60 ppm, can be the softener. Anthracite-coal filters are best for
eliminated in a single stage. Generally, high- removal of turbidity from the effluent. Some of

Direct-Contact Gas Concentrat

Multiport Relief Valve

Raw-Water Inlet
Steam Inlet -

Overflow to Waste

Treated-Water Outlet

Wash-Water Retur

Wash-Water Outlet

Sampling Connection Sludge Recirculating Pump

Sludge BlowoffValve

-
Fig. 5 Hot-process phosphate softening
COMBSTION
Water Technology

the chemical reactions in the softener to reduce hydroxide, dolomitic lime and magnesium
calcium and magnesium hardness are oxide aids in the reduction of silica. Removal of
silica from solution is accomplished by adsorp-
3CA(HC03), + GNaOH-. tion by the presence of magnesium hydroxide
3CaC0,l + 3~a,&, + 6 ~ , 0 formed in the softener.
3CaC0, + 2Na3P0,-
ZEOLITE SOFTENING
Ca,(PO,),I + 3Na,CO,
Mg(HCO,), + 4NaOH- The name zeolite refers to a group of water-
Mg(OH),L + 2Na,C03 + 2H,O softening chemicals capable of exchanging
ions with which they come in contact. These
Addition of magnesium sulfate, magnesiun~ materials may be natural compounds (green

Raw-Water Inlet

Underdrain System

Fig. 6 Sodium zeolite softener


..
COMBrnON
Wafer Tec/~nology

sand) or synthetic compounds such as sulfo- zeolite, turbidity must be low. The cost of the
nated coal, phenolic and polystyrene resins. chemicals, acid and salt, may be considerable.
Hard water is passed downward through a bed Handling of acids introduces a hazard to
of sodium-regenerated zeolite contained in a operators, and corrosion resistant pipe must be
steel pressure vessel. See Fig. 6. As the water used to transport the water to the degasifier.
passes through the ion-exchange material, the Synthetic zeolites are used with other
calcium and magnesium ions are exchanged water-softening equipment in preparation of
for sodium in the zeolite (Z). makeup water. The hot-lime zeolite softener is
The reactions are a widely used technique in preparing water for
intermediate-pressure industrial boilers.
Using chemicals at temperatures about 250F
facilitates reduction of hardness, alkalinity,
and silica. The hot-lime softening reduces the
Regeneration of the zeolite bed is accom- carbonate and magnesium hardness as well as
plished by passing a salt solution through the the total solids in the raw water. If the mag-
softener. nesium content in the raw water is below the
level to reduce silica, activated magnesium
CaZ + 2NaCl + Na2Z
+ CaClZ oxide or dolomitic lime is added for reaction.
Use of the hot-lime zeolite produces a water
The calcium chloride is passed to waste and the of 0-2 ppm hardness, 20-30 ppm alkalinity and
zeolite bed is ready for further softening. 0.5-1.0 ppm of silica.
Salt (sodium chloride) or acid can regenerate
synthetic zeolites. Acid- and salt-regenerated
zeolites can be used in combination to reduce In demineralization, ion exchange removes
alkalinity in waters having a high bicarbonate ionized mineral salts. Cations as calcium,
hardness. The reaction in the hydrogen zeolite magnesium, and sodium are removed in the
may be written as follows: hydrogen cation exchanger and anions as
bicarbonates, sulfates, chloride, a'nd soluble
silica are removed in the anion exchanger.
Synthetic cation and anion exchange resins
are used in demineralization of water. Sul-
The mixed effluent from the hydrogen and fonic, carboxylic, and phenolic hydroxyl com-
sodium zeolites is deaerated to remove the car- pounds are used for cation exchange; amino or
bon dioxide. Generally, the exhausted acid quartenary nitrogen, for anion exchange. The
zeolite is regenerated with sulfuric acid. cation exchanger is regenerated with acid
Zeolite softening of makeup is the most while the anion exchange material is regener-
common way to prepare water for use in indus- ated with caustic. If the cation resin is desig-
trial boilers. It is simple to operate and control. nated as Z and the anion material as R, the
While sodium zeolite softening is very attrac- simple reactions in a two-stage demineralizer
tive, it must be applied with understanding of may be expressed as:
its limitations. Turbid waters are unsuited;
Cation: H2Z+ CaSO,+CaZ + H2S0,
total solids are not reduced and, with high
Anion: H2S04+ R (OH),+R (SO,) + 2Hz0
bicarbonate water, high quantities of carbon
dioxide can be expected in the steam. Silica is Demineralization can yield a pure water, equal
not reduced by zeolite softening. or superior to the best evaporated vapor. The
Although using hydrogen zeolite reduces anion and cation resins can be arranged in vari-
solids, the equipment operator must recognize ous combinations to produce the best water -

a number of disadvantages: As in the sodium most economically. Two-, three- or four-bed


COMBUSTIOH
Water Technology

units or a single mixed-bed demineralizer can Use of finely sized'resins in demineralizers


-be used to accomplish the required result. Fig. requires a water source low in turbidity and
7 illustrates possible combinations of these sys- organic matter. Clarification, filtration and
tems to produce a specific water quality. As chlorination are generally required to reduce
strong base exchangers are temperature sensi- organic matter to a low level. Failure to reduce
tive, they should not be used above 120F. Cat- the organic level in the water results in a
ion exchange resins can tolerate temperatures marked reduction in capacity of the exchangers
of 250F. because of fouling of the resins.
The advance of demineralization to provide
a high-purity makeup water may be partly
attributed to the development of highly basic
anion exchange resins which allow the re-
moval of soluble silica from raw water. Mixed-
bed demineralizers, in which the cation and
anion r a i n s are intimately interspersed (see
Figs. 8 and 91, have successfully provided a
high-quality makeup water as well as for
polishing purposes in cleaning up impurities
in condensates of utility units. Fig. 10 is a
schematic of a complete makeup water system
for a utility power plant.

WATER TECHNOLOGY
FOR BOILERS +

Water technology for steam power plants en-


compasses the production of make-up water
--

Fig. 7 Ten major demineralizer systems: black,


strong-acid cation exchanger; white, strong-base
anion exchanger; shaded, weak-base anion ex-
changer; half black and half white, mixed-bed; bro-
ken rectangle, decarbonator or vacuum deaerator.
(1) Two-bed with weak-base; (2)' two-bed with
strong-base; (3) three-bed; (4) four-bed, primary
with weak-base; (5) four-bed, primary with strong-
base; (6) parallel two-beds, as in system 2, or four-
bed as in system 5 (except for size of secondary
unit); (7) mixed-bed; (8) cation bed, decarbonator,
and mixed-bed; (9) two-bed, as in system 1, and
mixed-bed; (10) two-bed, as in system 2, and
mixed-bed. The secondary units in systems 4 and 5, Fig. 8 Mixed-bed demineralizer. It houses mixture
which are used only for polishing, may be smaller of cation and anion exchange resins. Air for mixing
than the primary, as indicated. enters through bottom distributor.
COMBUSTION
Water Technology

and the treatment of the water (boilerwater and solids. As described in previous sections, make-
feedwater) after it enters the cycle. Requirements up water of excellent quality can be produced
for make-up water quality and internal treat- by ion exchange systems at reasonable costs.
ment may vary depending on many factors such The internal treatment is then designed to main-
as system design, operating conditions, and tain a chemical environment which provides
type of materials of construction. Modern high corrosion protection, surfaces free of deposits,
pressure power cycles require water of high and high purity steam.
,purity, essentially free of soluble and insoluble Plants with boilers operating below 600 psig
have less stringent requirements. Therefore, it is
Fig. 9 Regeneration of mixed-bed, from initial often more economical to provide make-up water
backwash to end of rinse and return to service, only partially demineralized (softened) and de-
takes from 2 to 3 hours. pend on internal chemical treatment to avoid
potential problems due to the increased soluble
solids concentration in the cycle.
The greatest incidence of problems in steam
generating equipment is related to (a) scale or
deposits, (b) corrosion, and (c) carryover of sol-
1. In Service 2. Backwash 3.Cation ids with the steam. In the next several sections,
various chemical treatment schemes and the
corresponding chemical agents will be reviewed.
SCALE AND DEP,OSlTS
Major contributors to the formation of a heat
deterrent scale or deposit are (1)contaminating
elements present in the makeup water, (2) metal
oxides transported to the boiler with feedwater,
(3) contaminants from process equipment intro-
duced into the condensate returned to the boiler,
7.Air Mix 9. Rinse and (4) solids present in condenser leakage.

Chlorinator

-.
Fig. 10 Demineralizer and pretreatment flow diagram
COYllVSRON
Water Technology

Low-presshre boilers with high makeup and a centrations is greatly diminished. Also, the use
small heat-recovering preboiler system are more of caustic is inappropriate because of its corro- -
prone to deposits from the precipitation of sivity at high concentrations. With demineral-
chemical compounds. Substances such as cal- ized quality boilerwater, caustic. (pjesent either
cium bicarbonate if not properly removed from as a treatment chemical or contaminant) can
the makeup water will decompose in the boiler reach high concentrations due to the absence of
water to form calcium carbonate as follows: large quantities of other competing ions.
Ca(HCO,), - CaCO, + CO, + H,O Whirl and Purcell recognized the ability of
sodium phosphate to suitably alkalize and con-
Calcium carbonate has a very limited solu- trol pH in boilerwater without the negative
bility and thus, the precipitated particles will reaction associated with the use of caustic.
agglomerate at the heated surfaces to form a They developed the pH-control method termed
scale. Other substances such as calcium sul- "the coordinated phosphate pH control". This
phate are also scale producing. In this case, the method is illustrated by the relationship of pH
scaling mechanism is, however, a function of a and the phosphate concentration in boiler water
retrograde solubility or a decrease in solubility shown in Fig. 11. Values noted on the curve rep-
in water with an increase in temperature. resent pH values obtained by dissolving stoichio-
These substances have a low thermal conduc- metrically pure trisodium phosphate (Na3P04).
tivity, and if left untreated, even a thin scale Conditions below the curve represent solutions
will overheat the boiler tube. of trisodium phosphate and disodium hydrogen
phosphate (Na,HPO,). The area above the curve,
USE OF PHOSPHATES
FOR INTERNAL TREATMENT which represents solutions of trisodium phos-
phate and caustic, is to be avoided.
The work of R. E. Hall and associates led to In the coordinated phosphate pH control,
the use of phosphates as an internal boilerwater specifications can be maintained by adding
treatment for converting residual concentrations trisodium phosphate (Na3P04),disodium phos-
of calcium and other hardness salts to their phate (Na,HPO,), or monosodium phosphate
respective phosphate compounds. These com- (NaH,PO,). Combinations of trisodium phos-
pounds can be more readily dispersed and re- phate and disodium phosphate are preferred.
moved by blowdown, although if present in large Alkalinity control is attained by the addition
concentrations, these will also form scales on of phosphate ions to water to produce a captive
boiler tubes. Several phosphate compounds such quantity of hydroxide (OH) by the reversed
as trisodium phosphate, disodium phosphate hydrolysis reaction as follows:
and monosodium phosphate in conjunction with PO4 f H 2 0 *OH- + HP04 =
sodium hydroxide (caustic) can be used for this
purpose. Some of the reactions are
To Avoid Excess Caustic,
the pH Value Must Be Maintained
Below This Line

The phosphate-caustic treatment is limited to


low pressure boilers utilizing softened makeup. 0 40 80 120 160 200
It's recognized that for boilers using demineral- PO4 Concentration, ppm
ized makeup, the need for high phosphate con- Fig. 11 Coordinated phosphate pH Control
COYllUSllON
Water Technology

This reaction is complete at pH levels below step in the overall reaction. Schikorr estab-
11.0. The hydrolysis reaction of dibasic phos- lished a mechanism which accounted for the
phate also proceeds in water as follows: production of magnetic oxide of iron. In sim-
- plest form, the reactions would be
HPO, - + H20 OH- + H,PO,-
The latter reaction is complete at low pH
levels (5 to 7) but is less than 0.1 percent at a pH
level of 10. Thus, dibasic phosphate neither From a consideration of physical chemical
hydrolyzes nor dissociates in the normal relationships, it can be shown that the forma-
boiler-water pH range. Additions of disodium tion of iron hydroxide is the rate-controlling
phosphate have little effect on pH in the range step in the Schikorr hypothesis. Therefore, the
10 to 11.0. rate of the overall reaction is based on the solu-
Monobasic phosphate dissociates to the di- bility and stability of this product.
basic form, and the addition of one mol of The initial reaction above is pH- or
monosodium phosphate (NaH,POJ is capable alkalinity-controlled since, by the laws of
of neutralizing one mol of sodium hydroxide. chemical equilibrium, addition of alkalinity
As one mol will increase boiler-water pH would reverse the reaction to the left. Corey
equivalent to the addition of one mol of sodium and Finnegan found that iron placed in contact
hydroxide, trisodium phosphate assures pH with deaerated and chemically pure water will
control. Adding monosodium phosphate can produce an equilibrium pH of approximately
reduce excess caustic. 8.3. Increasing the alkalinity reduces the solu-
bility of the iron corrosion product and inhibits
SIGNIFICANCE OF IRON-WATER REACTION reactivity. The control of this reaction has been
A number of influences characterize the reac- well established in the protection of metal sur-
tion of boiler steel and water: the chemical con- faces existing ahead of the b ~ i l e r . ~
stituents present in solution, the quantity of The reaction of water and steel is spontane-
dissolved gases, the structural characteristics ous and rapid at high boiler temperatures. The
of the steel, and the rate of heat input to the only reason that boiler steel can survive normal
boiler metal. Although the reaction is under- operating conditions is that the corrosion end
stood, in general there is insufficient informa- product, magnetite (Fe304),forms a protective
tion to explain the mechanism in exact detail. barrier on the metal surface to stifle further cor-
Many theories have been forwarded to clarify rosion. In the simplest analysis, the function of
a

this problem. But despite lack of fundamental alkalinity control is to maintain an environ-
data, experience and experimental evidence ment in which the oxide film is stable and pro-
have permitted the development of controls tective. The objective of water treatment in
which satisfactorily contain the corrosive ac- boilers is to protect this film against the aggres-
tivity. This section will deal with existing sive action of impurities introduced into the
techniques developed to understand and con- boiler with the feedwater.
trol reactions in boilers. The work of Berl and Van Taack (Fig. 1 2 )5has
The fundamental reaction of iron and water been used to relate corrosion of steel over a
is to produce iron hydroxide and hydrogen as range of pH values. In interpreting the results
follows: of Fig. 12, it may be concluded that the protec-
tive oxide is solubilized at pH values below 5.0
Fe + 2H,O -+ Fe(OH), + H?
and above 13.0; Minimum corrosion is indi-
It is an established fact that the end product cated at pH-values of 9.0 to 11.0, although cor-
of reaction in boilers is magnetic oxide of iron. rosion is low over a wide band of pH values.
(Fe304).The control of corrosion, therefore, is .. These data are valid, but they were obtained in
based on the knowledge of the rate-controlling autoclave tests where boiling, and thus concen-
COMBUSTION
WaW Technology

tration of the alkalinity, did not occur. Unfor- cold-worked sections, and at surface discon-
tunately, corrosion occurs by concentration at tinuities in the metal.
the local tube wall and not by concentrations Power plants employing tight cycles to pre-
existing in the bulk boilerwater. The attack of vent oxygen infiltration and condenser leakage
the protective oxide film and base metal occurs are generally free from corrosion problems. On
beneath deposits if the chemical constituents in the other hand, many cycles are vulnerable to
the boilerwater become corrosive when con- oxygen leakage into the feedwater as a result of
centrated. design or operation.
ROLE O F OXYGEN Efficient operation of boilers requires the ex-
The presence of oxygen accelerates the com- clusion of oxygen from the feedwater. The
bining of iron and water. Oxygen can react with normal guaranteed value of oxygen leaving the
iron hydroxide to form either a hydrated ferric deaerating heater or a deaerating condenser is
oxide or magnetite. Generally localized, this re- less than 0.005 ppm. To achieve low residual, it
action forms a pit in the metal. Severe attack is necessary to exclude air leakage into the
can occur if the pit becomes progressively an- condenser, to judiciously control the addition
odic in operation. Oxygen reacts with hydrogen. of undeaerated water to the condensate or
at the cathodic surface and depolarizes the sur- feedwater, to prevent the addition of aerated
face locally. This permits more iron to dissolve, heater drips into the condensate, and to assure
gradually creating a pit. the exclusion of air into the feedwater cycle
The most severe corrosion action occurs during short outages of the boiler.'
when a deposit covers a small area. The crea- One major problem in curtailing corrosion
tion of a differential aeration cell about the de- from oxygen is the exclusion of air upon boiler
posit can lead to a severe local action. The start-up. Normally, pressure in a deaerator is
metal beneath the deposit is lower in oxygen not attained until steam is admitted to the tur-
than areas surrounding it, becomes anodic and bine and bleed steam is available for heating. It
is attacked. Pitting is most prevalent in stressed is possible to introduce more oxygen into the
sections of boiler tubing, such as at welds and boiler at this time than in several months of
normal operation. Admitting auxiliary steam
to a deaerator to pressurize the unit to 3-5 psig
can prevent much of this problem. In this con-
dition, air is excluded and the feedwater deliv-
ered to the boiler is low in oxygen during
start-up operation.
REMOVAL O F RESIDUAL OXYGEN
Chemical agents added to the feedwater or
boilerwater are generally used to remove small
residual quantities of oxygen. Hydrazine (N,H,)
and sodium sulfite (Na,SO,) are the most com-
monly used "oxygen scavengers".
Sodium sulfite, when added to the boiler-
water reacts with oxygen to form sodium sulfate
as follows:
2Na,SO, + 0, -- 2Na, SO,
Temperature affects the reactivity and stabil-
ity of sodium sulfite (as well as hydrazine). Gen-
Fig. 12 Relative general corrosion rate of erally, a cobalt catalyst is added with the sodium
carbon steel versus pH sulfite solution to speed up the reaction at lower
--
temperatures. Sulfite decomposition increases in the preboiler cycle. Copper oxide is reduced
with temperature and local concentration in with hydrazine at temperatures as low as 150F.
boiler water. Sodium sulfite decomposes in Iron oxide (Fe203)can be reduced at a tempera-
boiler water as follows: ture of 250F.
Normally, hydrazine is added to the cycle at
the outlet of the condensate pump at a rate to
assure a residual of 10-20 ppb (parts per bil-
Sulfur dioxide (Sod is an acidic anhydride lion) at the inlet of the economizer.
which increases corrosion of metals when it is Some of the reactions of hydrazine in the
dissolved in condensate films formed on wet- feedwater cycle and boiler are
ted surfaces of a turbine or condenser. Decomposition
Concentration of sulfite must be controlled 3N2H4-f N2 + 4NH3
to minimize decomposition at elevated pres- 2N2H4+ N2 + H2 + 2NH3
sures. Recowended limits are shown in Table
Reduction
111. For this reason, sulfite should not be used
6F&03+ N2H4+4Fe,0, + N2+ 2H20
for reducing oxygen in boilers at pressures
4Cu0+ N2H,+2Cu20+ N2+ 2H20
above 1200 psig.
Sodium sulfite is an effective reducing agent Reducing agents aid in curbing corrosion but
on boiler water. Besides its reaction with oxy- will not prevent metal attack when oxygen is
gen, the chemical reduces oxides of iron and present in the boiler feedwater. At higher tem-
copper as follows: peratures, the reaction rate of oxygen with steel
exceeds that of the reducing agents.
FEEDWATER pH CONTROL
Its consumption in boiler water is a measure Besides the control of oxygen, it's important
of oxygen and oxidized substances added with that the pH of the water be maintained in the
the feedwater into a boiler. The reduction of proper range. In high pressure units, feedwater
cupric oxide begins at about 280F and is com- is sprayed into superheated and reheated steam
plete at about 400F.Reduction of ferric oxide to help in controlling final temperatdres. There-
begins at about 440F and is complete at 540F. fore, to assure protection to preboiler equip-
Hydrazine reacts with oxygen to form nitrogen ment, volatile alkaline chemicals have been de-
and water as follows: veloped to control the pH of the water without
forming solid residue in parts of the boiler
N,H, + O2 Nz + 2H20
where evaporation takes place. Classed as neu-
Hydrazine reacts with oxygen very slowly'at tralizing amines, the most common'of these are
temperatures below 350OF. Above 450OF, hydra- ammonia (NH,), morpholine (C,H,NO) and cy-
zine is decomposed rapidly to nitrogen, hy- clohexylamine (C,H,,NHJ. These compounds
drogen and ammonia. The principal benefit of volatilize with the steam and can react with
hydrazine is its ability to reduce the oxidized gases like carbon dioxide to neutralize any acid-
forms of copper and iron. In this state the gen- ity in the condensate system. The selection of
eral corrosion of the metal surfaces is reduced any of these chemicals are based on obtaining
an optimum fit between their chemical and
Table 111. Sodium Sulfite Limits physical characteristics (volatility, solubility,
stability, etc.) and the particular application.
Boiler Pressure, psig Concentration, ppm Table IV lists the stability characteristics of
volatile amines. -Both morpholine and cyclo-
Below 600
hexylamine have temperature stability limits.
600-900
Ammonia, hydrogen and carbon decomposition
COMBUrnN
Water Technology

products are formed in the dissociation of these hydrolysis depends on a relatively high pH
amines at high temperatures. Ammonia is stable level. The anionic chelant has reactive sites
and has been used at steam temperatures as that attract coordination sites on cations. These
high as 1200F. As a result, ammonia is the coordination sites are areas on the ion that are
recommended compound for use in controlling receptive to chemical bonding. In this manner,
pH of condensate in high-pressure, high tem- cations (hardness salts) entering the boiler as
perature boiler systems. However, it's important contamination from the condensate system,
to maintain ammonia levels generally below combine with the chelant to form a stable che-
1 ppm to avoid copper alloy attack. A copper late. Deposition of hardness on boiler internal
ammonium complex is formed in the presence surfaces may therefore be prevented.
of high ammonia concentrations and the reac- Although many substances have chelating
tion can be further accelerated by the presence properties, EDTA (Ethylene Diamine Tetra-
of abnormal concentrations of oxygen. Typical cetic Acid) is the most suitawe for boiler feed-
reactions are as follows: water treatment. As with any internal chemical
treatment, however, the application and
limitations must be clearly understood. Cur-
rently, chelants are limited to boiler pressures
It has been established that an ammonia con- of less than 1000 psig because of their thermal
centration of less than 0.5 ppm will assure a decomposition at saturation temperatures cor-
protective pH in the cycle without attacking responding to higher pressures. In addition,
copper surfaces. overfeeding of chelants can lead to corrosion of
Morpholine and cyclohexylamine are pre- boiler tubes as chelation of the protective
ferred to ammonia for pH control in situations magnetite (Fe303 film can occur. For a more
where excessive decomposition of these chemi- detailed discussion, see reference 1.
cals does not occur and an extensive condens-
ing system or process piping network exist.
CORROSION DAMAGE
USE OF CHELANTS IN POWER PLANTS
FOR INTERNAL CONTROL
The major purpose of feedwater and boiler-
Chelants are weak organic acids with the water treatment is to avoid corrosion and as-
capability of complexing or binding many cat- sociated tube failures. Most materials that form
ions (calcium and magnesium hardness as well boiler deposits originate in the preboiler sys-
as heavy metals) into a soluble organic ring tem. Adherence to recommended operating
structure as illustrated in Fig. 13. Chelants are procedures during start-up, normal operation,
in the neutralized sodium-salt form. They hy-
drolyze inboiler water to an organic anion. Full

Table IV. Stability of Volatile


Water-Treating Materials
Percent
Pressure Temp Decom-
Chemical Formula psig OF posed

Ammonia NH, 4270 1202 0


Cyclohexy-
lamine CcHIINH2 4270 1202 88
Morpholine O(C1H4)ZNI-i4270 1202 100
Hydrazine N2H, 4270 1202 100
-- Fig. 13 Calcium bonded with EDTA
" COMBUSTION
Wmter Technology

shutdown, and outages of a power plant is vital EXAMPLES OF PITTING CORROSION


to minimize corrosion and to avoid the entry of
corrosion products into the steam generator. Figs. 14 through 23 show a variety of corro-
Corrosion damage may be in the form of a gen- sive attack attributable to pitting. Generally,
eral attack of the metal surface, pitting, or the term pitting denotes localized crater-like at-
localized attack of the metal surface beneath tack of a type shown in Figs. 1 4 and 15. But
internal deposits. there are failures in which individual pits join,
producing crack-like penetrations of the type
GENERAL SURFACE ATTACK
indicated in Fig. 16. In the absence of a corro-
One type of corrosion is oxygen attack of sion or metallurgical term describing this type
ferritic materials of construction. Such corro- of corrosion penetration, the condition has
sion may take place throughout the preboilerl been included under the broad category of pit-
boiler cycle. Corrosion from oxygen can occur ting attack.
during any period of the power-plant lifetime, The orientation and location of the crack-like
from erection to operation, as well as standby indications shown in Fig. 1 7 can best be ex-
conditions. plained by pitting preferential to an area of
Another type of general overall corrosion is somewhat higher strain than the surrounding
caused by lack of boiler water pH control dur- metal. Differences in strain promote the forma-
ing system operation. Improper condensate and tion of anode-cathode cells and the resulting
feedwater pH levels also cause this type of gen- corrosion at the anode is oriented perpendicu-
eral attack within the preboiler system. lar to the direction of maximum residual or
applied strain.
PITTING AND LOCALIZED ATTACK
The pitting attack shown in Figs. 18 and 19
Pitting of various types can affect the internal affected the entire tube circumference, but was
surfaces of all tubes and components. Pitting is deepest under the welded fin. In this instance,
electrochemical in nature, with the pitted area differences in metallurgical structure may also
anodic to the surrounding nonpitted metal sur- have been a factor in promoting the elec-
face. If conditions favorable to pitting exist trochemical cell.
-such as excessive dissolved oxygen in the This type of pitting attack has also been
boiler waterlfeedwater or an acidic chemical found in some lower waterwall drums. Fig. 20
environment-one of several normally in- shows an example of that attack.
nocuous factors can cause severe local attack. The overall character of these cracklike indi-
Crevices, such as those formed by deposits or cations are not typical of fatigue cracking. The
minor variations in metallurgical structure, bottom of the penetrations show no evidence
may act to promote localized corrosion. Nor- of cracking and the shape of the void indicates
mal, but higher-than-average, peak stress also they were formed as a result of corrosion. When
can contribute to preferential pitting. tubes exhibiting internal surface cracklike indi-
There has been the increased trend in fossil cations (Fig. 21) have been reverse flattened and
systems toward peaking, variable-pressure, bent to force fracture along these linear indica-
low-load, and two-shifting operations, with tions, the penetrations show themselves to be
frequent shutdowns-all which have contrib- a series of aligned corrosion pits (Fig. 22). The
uted to increased numbers of failures associ- evidence strongly suggests that a pitting mech-
ated with peculiar corrosion patterns related anism can initiate and propagate cracklike pene-
to frequent introduction of oxygen during out- trations. In some instances the penetrations
age and start-up periods: A look at several in- appear to be a series of pits atop one another,
stances of pitting attack will provide a better giving the impression of separate time periods
appreciation for the need in developing protec- when pitting attack has resumed at the bottom
tion when the corrosion potential is high. of the penetrations as shown in Fig. 23..
COMBUSTION
Water Technology

Fig. 14 Pitting on internal surface of Fig. 17 Sectional view across cracklike


waterwall tube (mag 314X) ' penetrationshown in Fig. 1 6

Fig. 15 Sectional view of one pit shown in


Fig. 14 (mag 3-112X)

Fig. 18 General pitting attack from inside surface


of waterwall tube. Pitting affected entire tube cir-
Fig. 16 Cracklike corrosion penetrations on cumference but was more severe under external
internal surface of waterwall tube fin (mag 8X).
COxBumON
Water Technology

.
does not change and the tubing retains its
CORROSION DAMAGE ductility. Fig. 24 illustrates ductile gouging.
IN BOILERS Hydrogen damage-This type corrosion
Deviations from recommended chemistry damage usually occurs beneath a relatively
dense deposit. Although some wastage occurs,
limits which result in depressed or elevated pH
the tube normally fails by thick-edge fracture
values promote failures of boiler tubing. Al-
before the wall thickness is reduced to the
though there are many variations, the majority
point where stress rupture would occur. Hy-
of failures can be classified into one of the fol-
drogen, produced in the corrosion reaction,
lowing two categories: -.
Ductile gouging-Normally, irregular wast- Fig. 20 Cracklike corrosion penetration at inside
age
" of the tube metal beneath a porous deposit
surface of lower waterwall drum at toe of nozzle weld
characterizes this type damage. The damage
progresses to failure when the tube wall thins
to a point where stress rupture occurs locally.
In this process, the microstructure of the metal

Fig. 19 Pitting attack similar to Fig. 18 with deep,


clearly corrosion-related, localized, cracklike pene- Fig. 21 _Internalsurface of tube with longitudinally
tration under external fin (mag 8X) oriented, cracklike indications (mag 3X)

-20
COMBUSTION
Water Technology

diffuses through the underlying metal, causing fissuring of the structure. Brittle fracture oc-
-
decarburization and intergranular micro- curs along the partially separated boundaries,
and in many cases, an entire section is blown
Fig. 22 Sectional through-the-wall view of Fig. 21 out of an affected tube. Examples of these fail-
tube after flattening and bending to promote frac-
ture along a penetration. Inside diameter (ID) sur- ures are shown in Figs. 25 and 26.
face is at bottom, and darker craters from the ID sur-
face are pits. (The remaining wall portion is sound
metal which fractured as a result of the flattening
and reverse bending.) The cracklike penetrations
result from aligned pits.

Fig. 24 Ductile gouging

Fig. 25 Thick-edge waterwall tube failure


caused by hydrogen damage

--

Fig. 23 Crack-like corrosion penetrations halfway


through tube wall, strongly suggesting that propa-
gation results from separate time periods of pitting Fig. 26 Another typical waterwall failure
at the root of the penetration. from hydrogen damage
COMBUSTION
W8t.r Technology

Internal metal-oxide deposits which permit fusion barrier and in so doing increases the
boiler-water solids to concentrate during the probability of high local concentrations being
process of steam generation accelerate both reached.
types of attack. When the boiler water contains Because porous deposits may exist, boiler-
highly soluble alkaline treatment chemicals water chemicals should be of a type that will
such as sodium hydroxide or potassium salts, not become highly corrosive when concen-
ductile attack is more probable. Hydrogen trated. Experience indicates that caustic soda
damage, on the other hand, is more likely to and potassium salts are particularly objection-
occur when a low pH boiler-water environment able. Alkalinity can be produced with sodium
results from condenser leakage or some other phosphate (coordinated phosphate treatment)
type of system c~ntamination.~ without the risk of extremely high pH values
According to an ASMEIEEI-sponsored labo- being present upon concentration. Alkalinity
ratory research programlo, clean tubes are not control of boiler water may also be achieved by
susceptible to corrosion even under high heat- adding avolatile amine such as ammonia and is
transfer conditions 'unless unusually high required for once-through units.
concentrations of acid or alkali are present. In Condenser cooling waters represent a poten-
addition, fouled tubes do not appear to be sus- tial source of contamination of the boiler water.
ceptible to corrosion when contaminants are Depending on the chemical constituents dis-
present if proper boiler-water treatment is solved in the cooling water, highly acid or al-
maintained. These observations can be ex- kaline materials may be formed in the boiler
plained by the "concentrating film" theory. environment as a result of condenser leakage.
The Berl and Van Taack curve (Fig. 1 2 ) illus- Because of its poor buffering capability, vola-
trates the relative corrosion of carbon steel tile treatment provides little protection against
under various acid and alkaline conditions.
Bulk boiler-water concentrations ' are always
well within the range of low corrosion rates.
But, as heat is transferred through the boiler
tube wall to a water-steam mixture, a tempera-
ture gradient is established, and the internal
tube metal temperature must reach a value
slightly higher than the bulk fluid temperature.
As boiler water is converted to steam, the dis-
solved solids concentrate in a residual film as
shown in Fig. 27. The solids concentration in
this film increases until the boiling point of the
solution is elevated to the temperature at the
tube wall.
It is improbable that such high concen-
trations can be reached in a clean tube under
normal boiling conditions. Theoretically, the
bulk of the film-temperature drop is experi- Fig. 27 Illustration of "concentrating film" theory.
enced within a laminar film of about 0.001-in. Film temperature gradient of 15" is developed be-
thickness. Free diffusion of ions into the turbu- cause of heat transfer. Soluble solids in boiler water
lent fluid would prevent the establishment of a are concentrated in the surface film during steam
concentration gradient. Only when porous generation to produce"nonboilingequilibrium." Al-
though the caustic concentration in the boiler water
internal deposits are formed in areas of heat ab- is only 100 ppm, the concentration in the surface
sorption is it possible to produce very high film must equal 220,000 ppm to elevate the boiling
concentrations. The deposit itself acts as a dif- point 1 6 .
COIlBIISTION
Water Technology

acid attack of boiler tubing. With a stronger al- rosion of boiler tubes, it should be emphasized
kaline additive, coordinated phosphate treat- that deposits also promote the majority of tube
ment results in a more highly buffered boiler failures caused by overheating.
water, one in which acid-producing reactions Fig. 28 illustrates the temperature conditions
from salt inleakage are better suppressed. Op- existing in a typical furnace-wall tube. The
timum treatment programs based on this heat flux of 100,000Btulft2. hr is established by
method are discussed in the following section. the furnace flame-temperature spectrum and
the bulk fluid temperature of 640F is fixed by
TUBE FAILURES boiler pressure. The temperature profile is then
CAUSED BY OVERHEATING established by the AT required to drive the
While the preceding discussion focused on 100,000 flux through each segment of resis-
the role played by internal deposits in the cor- tance. With nucleate boiling on a clean tube,
the AT across the fluid film is quite small (lOF)
Fig. 28 Furnace wall tube-nucleate boiling and the overall temperature differential (90F)
Fig. 30 Furnace wall tube-film boiling

Radiant Heat
4

TF > 2800F

Nucleate Boiling

Film Boiling

Radiant Heat 140,000 Killed Carbon Steel


(0.12 - 0.17C)
Q=100,000
-
Btu/Hr Ft2
n 840"F
-!
V) loooF
2 1,400
120O0F
1400F
~ z l e a tB
e G~ 140+100 1 , m l O . 0 ~100,000
with Internal Deposit Rupture Time, Hours

Fig. 29 Furnace wall tube-nucleate Fig. 31 Stress and temperature versus


boiling with deposit time-to-rupture
results from the resistance of the tube metal. from the normal condition to a higher value
Fig. 29 shows what happens to the tube- consistent with the upset.
temperature profile if an internal deposit If the temperature excursion is great, the tube
exists. Approximately 60F is required to drive may fail very quickly. For instance, if a tube
the 100,000 heat flux through the deposit, so is completely blocked during operation, the
both the inside and outside metal temperatures tube temperature will rise immediately to the
must rise correspondingly. failure-point temperature. The rapid plastic de-
Fig. 30 illustrates the temperature profile formation of these very short-term ruptures
under a film-boiling condition. The reduced- produces very thin-edged fractures. In the case
film coefficient increases the AT across the film of major flow interruptions, the tube bulges
to 310F and the metal temperatures rise corre- over an extended length and fails like a balloon
spondingly. It should be noted that the flux is bursting.
constant at 100,000 Btulft2. hr for all cases. If a DNB excursion places the tube-metal
temperature in the range of 840 to 1020F, the
tube will take a longer time to fail. During
STRESS RUPTURE this period, intergranular oxidation of the
The strength of carbon steel tubing is nearly metal will occur and will weaken the structure.
constant to about 840F, at which point it be- Long-term failures, therefore, tend to be thick-
gins to lose strength rapidly. If tube metal edged. The higher the temperature and stress
temperature is gradually increased beyond this conditions are above the creep limit, the
temperature, it will plastically deform (creep) shorter the time to failure and the thinner the
and then rupture. The approximate time-to- metal edge at the fracture. Fig. 32 presents
rupture is a function of the hoop-stress and the examples of a short, an intermediate, and a
temperature (Fig. 31). The hoop stress (S) long-term failure.
equals the product of the internal pressure (P) Metallographic analysis is an important tool
times the tube radius (r) divided by the wall for analyzing tube-temperature history. The
thickness [x). normal pearlitic microstructure of carbon steel
boiler tubing can be seen in Fig. 33. The light
areas are iron, and the dark areas are pearlite
consisting of alternate layers of iron and iron
carbide. The normal operating temperature of a
boiler tube will not alter this structure. If the
Simple visual examination of a failed section temperature of steel is maintained in the range
reveals a great deal about the tube-temperature of 930 to 1340Ffor an extended period of time,
history. In deposit-caused overheating, local carbon migrates from the pearlite to form
tube temperatures rise gradually so that spe- spheres of carbon. This process, known as
cific points begin to creep before others (blis- spheroidization, progresses slowly at 930F
tering). Deposits tend to form nonuniformly, and rapidly at temperatures near the lower crit-
and even a 20F difference in temperature can ical range (1340F).Fig. 34 shows carbon steel
have a pronounced effect on localized creep. with various degrees of spheroidization.
Blistering is almost always caused by internal If the tube is heated to a temperature greater
deposition, and conversely, overheating be- than 1340Fand is then allowed to cool slowly
cause of deposits will almost always be evi- to below 930F, the normal pearlitic structure
denced by blisters. will be re-established. But, if the tube is heated
When an upset of-boilingxonditions, such as above 1340Fand is cooled very rapidly, a mar-
departure from nucleate boiling (DNB) elevates tensitic structure (Fig. 35) will be produced.
tube temperature, a temperature excursion will This type of microstructure is likely to be found
occur. Metal temperature will jump quickly in very short-term overheating failures in
COMBUSTION
Water Technology

which the water escaping through the rupture corrosion was instrumental in bringing an un-
suddenly quenches the overheated tube metal. derstanding to the various corrosion mech- -
anisms discussed in the previous sections. The
RESEARCH STUDY
following recap of the more important conclu-
ON INTERNAL CORROSION
sions includes our interpretation of their prac-
The previously referencedASMEIEE1- spon- tical significance:
sored laboratory research Program On 1, When heat-transfer surfaces are free of de-

w"- 3. Corrosion will not occur when coordinated

hideout of sodium phosphate will occur if


heat-transfer surfaces are fouled andlor DNB
conditions exist.
5 . There appears, however, to be no relation-
ship between hideout and corrosion of tube
metal.

Fig. 33 Photomicrograph-
normal pearlitic structure of carbon steel Fig. 34 Spheroidization: left, mild; right, extensive
.-
COYBUSTION -
Water TKhndogy

corrosion was the fault of either the operator or


the designer. It demonstrated that both chemi-
cal and mechanical factors are involved and
that they are largely interdependent. A change
in one variable will affect the manner in which
other variables influence corrosion. Normally,
several factors must be simultaneously out-of-
line to produce corrosion. As a result, corrosion
is a fairly low probability event despite the
fairly large- number of potentially adverse
physical and chemical conditions which tem-
porarily exist.

UTILITY BOILER-WATER
AND FEEDWATER TREATMENT
IN THE PREVENTION
OF CYCLE CORROSION
Fig. 35 Martensitic structure
If extensive corrosion during outage condi-
6. Caustic soda concentrations ranging from tions is to be avoided, proper wet lay-up meth-
10-20 ppm in the boiler water (with a pH of ods are essential. Because large utility boilers
from 10.5 to 10.8) can cause serious cor- cannot be successfully dried to produce an
rosion if internal surfaces are fouled with internal atmosphere free of moisture, wet lay-
deposits. Corrosion is rapid even under nuc- up procedures are recommended even for long
leate boiling conditions, and complete penetra- outage periods.ll
tion of a 5-mm tube wall can occur in several PROTECTION
days. DURING OUTAGE CONDITIONS
7. With certain types of condenser cooling
For any outage longer than four days, the
water, a condenser leak will cause a pH re-
preboilerlboiler cycle should be filled, to the
duction in the boiling water. With fouled sur-
greatest extent possible, with a solution inhib-
face conditions, hydrogen embrittlement may
ited to prevent corrosion, and pressurized with
then occur. The rate of attack is rapid and of the
nitrogen to prevent air inleakage. Excellent re-
same order of magnitude described in item 6.
sults have been obtained with condensate con-
8. The analysis of cooled samples can be very taining appropriate amounts of hydrazine and
deceptive in interpreting behavior in high- ammonia for lay-up periods of several years.
temperature boiler-water environment; a sam- As both materials are volatile, there is no objec-
ple which is alkaline at room temperature may tion to their use even in nondrainable super-
be acidic at high temperatures, and vice-versa. heater and reheater sections of the boiler.
Understanding the behavior of each specific Where freezing is a problem, it is sometimes
contaminant which can be introduced by way necessary to drain portions of the steam
of condenser leakage is essential. generator. This should be accomplished under
9. The rate of deposition of preboiler corrosion a positive nitrogen pressure. Nitrogen blanket-
products increases with increasing heat-flux. ing is recommended even when the boiler can
Deposition is substantially greater on the hot be maintained full of inhibited condensate.
side of the tube where boiling occurs. The success or failure of standby protection
The research program did not conclude that also depends upon the proper design and selec-
COMBUSTION
Water Technology

-
Table V. Recommended Lay-Up Procedures C-E Drum-Type Utility Units
Type of Procedure Notes
Shutdown
Preoperational tvith the economizer, waterwalls, super- I. All nondrainable sections to be hydro-
Period heater, and reheater filled to overflowing statically tested should be filled with de-
Post Hydro pressurize the unit with nitrogen to 5 mineralized or condensate quality water
(See Note 1) psig pressure (See Notes 4 & 6). containing 10 ppm of ammonia and 200 ppm
of hydrazine. This should produce a solution
Preoperational Introduce Or conden- pH of approximately 10.0. The superheater
Period sate quality water containing 10 ppm of should be filled first, to overflow into the
Post Chemical ammoniaand 200 ppmof hydrazine boiler drum. Then the economizer and wa-
Cleaning the reheater*feedwater terwalls can be filled through normal fill
heaters, (tube side) and associated pip- connections (See Note 2) with demin-
in& economizer and waterwalls (Referto eralized or condensate quality water, or if
Notes 3 & 4). not available, any source of clean, filtered
2. Nitrogen cap the superheater, feed- water may be used. This water should also
water heaters (shell side) and drum. contain 10 ppm of ammonia and 20.0 ppm of
Maintain 5 psig nitrogen pressure (See hydrazine.
Notes 5 & 6). 2. Hydrazine and ammonia should be added
Short Outage- 1. blaintain the same hydrazine and in a manner that results in a uniform COnCen-
4 Days or Less ammonia concentrations as those pre- tration throughout. They may be added to
sent during normal operation. the system in several ways, as for example:
2. Establish and maintain a 5 psig nitro- a. BYpumping concentratedsolutions
gen cap on the superheater and the steam through the chemical feed equipmentand
drum (See Notes 5 & 6). blend filling to achieve the desired concen-
3. Nitrogen cap the shell side of the trations.
feedwater heaters. b. If condenser leakage is not a cause for
shutdown, concentrated solutions can be in-
Short Outage- 1. Drain and open only troduced directly into the hotwell where
4 Days or Less, requiring repairs. they can be mixed to achieve the desired
Unit Partially 2. Isolate remainder of unit under 5 psig concentrations. If condensate demineraliz-
Drained for Repair nitrogen pressure where possible (See ers are used, they must be bypassed during
Notes 5 & 6). this operation.
3. Maintain the same hydrazine and It is important to have the fluid temperature
ammonia concentrations for water re- in the cycle below 400F before addition of I
maining in the cycle as those present hydrazine. If this temperature is exceeded,
during normal operation. the hydrazine will decompose.
4. Nitrogen cap the shell side of the 3. The tube side of copper alloy feedwater
feedwater heaters. heaters should be filled with demineralized
water containing 0.5 pprn of ammonia and
Long Outage- I. Fill the superheater and reheater with
50 pprn of hydrazine.
Longer than demineralized or condensate quality
4 Days water containing 1 0 pprn of ammonia 4. If freezing is a problem, the water in
and 200 pprn of hydrazine. The pH of the drainable circuits can be displaced with ni-
solution should be approximately 10.0. trogen and the unit laid up under 5 psig ni-
Add the fill water to the outlet of the trogen pressure. Auxiliary heat may be
nondrainable sections (See Note 4). applied to keep the nondrainable sections
from freezing.
2. Increase the hydrazine and ammonia
concentration in the waterwalls, 5. If the reheater can be isolated, it should
economizer and feedwater heaters (tube also be capped with 5 psig nitrogen. When
side) and associated piping to 200 pprn the outage is expected to extend beyond 2
and 10 pprn respectively (See Notes 2,3, months, provisions should be made to iso-
and 4). late and nitrogen cap the reheater, if this was
not done previously.
conmnoN
Waier Technology

Table c~ecommendedLay-Up Procedures- C-E Drum-Type Utility Units


Type of Procedure Notes
Shutdown
3. Establish and maintain a 5 psig nitrogen 6. Nitrogen cap should be applied through
cap on superheater and drum (Notes 5 & 6). the drum vent and superheater outlet header
4, Nitrogen cap the shell side of the feedwa- hainlvent*as the unit is cooled*when Pres-
ter heaters. sure drops to 5 psig. Admission of air
through atmospheric vents should be
Long Outage- 1. Drain and open only those sections re- avoided.
Longer than quiring repairs.
4 Days, 2. Fill the superheater and reheater (if not
Unit Partially requiring draining for repairs) with de-
Drained mineralized or condensate quality water
for Repairs containing 10 ppm of ammonia and 200 ppm
of hydrazine. The pH of the solution should
be approximately 10.0. Add the fill water to
the outlet of nondrainable sections (Note 4).
3. Increase the hydrazine and ammonia
concentrations in the tube side of the feed-
water heaters and the undrained circuits of
the economizer and waterwalls to 200 pprn
and 10 pprn respectively (See Notes 2 , 3 & 4).
4. Establish and maintain a 5 psig nitrogen
cap on the undrained sections of the unit,
where possible (See Notes 5 & 6).
5. Nitrogen cap the shell side of the feedwa-
ter heaters.
6. After completion of the repairs fill the
drained sections with demineralized or con-
densate quality water containing 10 pprn of
ammonia and 200 pprn of hydrazine. Cap
with nitrogen (See Notes 2,3,4, & 5).

Table VI. Recommended Lay-Up Procedures C-E Combined Circulation Units


Post Chemical 1. Introduce demineralized or condensate 1. Hydrazine and ammonia should be
Cleaning quality water containing 10 pprn of am- addedin a manner that results in a uniform
Preoperational monia and 200 pprn of hydrazine into the concentration throughout. They may be
Period feedwater heaters (tube side), economizer, added to the system in several ways as for
furnace walls, superheater and reheater (Re- example:
fer to Notes 2 & 3). a. By pumping cbncentrated solutions
2. Nitrogen blanket the shell side of the through the chemical feed equipment
feedwater heaters, superheat, and furnace and blend filling to achieve the desired
wall sections. Maintain 5 psig nitrogen pres- concentrations.
sure (Refer to Note 4). b. If condenser leakage is not a cause for
Short Outage I. Maintain the same hydrazine and am- shutdown, concentrated solutions can be in-
4 Days or Less monia concentrations as those present dur- troduced directly into the hotwell where
ing normal operation. they can be mixed to achieve the desired
concentrations. The condensate polishing
2. Establish and maintain a 5 psig nitrogen
system must be bypassed.
cap on the superheater and furnace wall sec-
tions (Refer to Note 4). During hydrazine and ammonia introduc-
tion, circulation should be maintained
3. Nitrogen blanket the shell side of the
through BE and WD valves to insure
1 feedwater heaters.

AWL
---I
COMBDSTION
Water Technology

Table VI. Recommended Lay-Up Procedures- C-E Combined Circulation Units


I
Type of Notes
Procedure
Shutdown
Short Outage 1. Drain and open only sections requiring adequate mixing in the system. If the
4 Days or Less, repairs. superheat section is to be laid up wet, circu-
Unit Partially 2. Isolate remainder of unit under 5 psig ni- lation should be maintained through the BE,
Drained for trogen pressure where possible (Note 4). SA and SD valves. Furnace wall outlet Pres-
Repairs 3. blaintain the same hydrazine and am- sure should not exceed 1000 psig while
mania concentration for water remaining in
maintaining circulation during introduction
the cycle as during normal operation. of hydrazine and ammonia.
4. Nitrogen blanket the shell side of the
It is important to have the fluid temperature
in the cycle below 400F before the addition
feedwater heaters. of the hydrazine. If this temperature is ex-
Long Outage 1. ~ I ithe
i superheater and reheater with ceeded, the hydrazine will decompose.
Greater than demineralized or condensate quality water 2. All sections to be hydrostatically tested
4 Days containing 10 ppm of ammonia and 200 Ppm should be filled with demineralized or con-
of hydrazine. The pH of the solution should densate quality water containing 10 ppm of
be approximately 10.0. Add the fill water to jmmonia and 200.ppm of hydrazine. This
the outlet of nondrainable sections (Note 3). should produce a solution p~ of approxi-
2. Increase the hydrazine and ammonia mately 10.0.
concentrations in the economizer, f ~ r n a c e 3, If freezing is a problem, the water in the
walls, and feedwater heaters (tube side) and drainable circuits can be displaced with ni-
associated piping to 200 PPm and 10 PPm trogen and the unit laid up under 5 psig ni-
respectively (Refer to Notes 1& 3). trogen. Auxiliary heat may be applied to
3. Establish and maintain a 5 psig nitrogen keep the nondrainable sections from
cap on the furnace wall and superheat sec- freezing.
tions (Refer to Note 4). 4. If the reheat section can be isolated, it
4. Nitrogen cap the shell side of the feedwa- should also be capped with 5 psig nitrogen.
ter heaters. When the outage is extended to 2 months or
longer, provisions should be made to isolate
Long Outage 1. Drain and open only those sections re- and nitrogen cap the reheat sections, if this
Greater than quiring repairs. was not done previously.
4 Days, 2. Fill the superheater and reheater (if drain-
Unit Partially ing for repairs is not required) with demin-
Drained for eralized or condensate quality water con-
Repairs taining to 10 ppm of ammoniaand 200 ppm
of hydrazine. The pH of the solution should
be approximately 10.0. Add the fill water to
the outlet of nondrainable sections (Note 3).
3. Increase the hydrazine and ammonia
concentrations in the tube side of the feed-
water heaters and the undrained circuits of
the economizer and furnace walls to 200
pprn and 10 pprn respectively. (Notes 1& 3).
4. Establish and maintain a 5 psig nitrogen
cap on the undrained section of the unit,
where possible (Refer to Note 4).
5. Nitrogen cap the shell side of the feedwa-
ter heaters.
6. After repairs, fill drained sections with
demineralized or condensate quality water
containing 10 pprn of ammonia and 200
pprn of hydrazine. Cap with nitrogen (Notes
1& 3).
-
--
tion of chemical-feed equipment and the abil- start-up, with the necessary degree of con-
ity to provide an inert gas blanket.'2 Utilities denser vacuum and fluid temperature.14. l6- l7
with operating units that are predominantly (See Fig. 36.) This requires connection of a re-
base-loaded may get along with simple, inex- cycle line from the discharge of the feedwater
pensive manual systems for introduction of heaters back to the deaerating section of the
lay-up additives and nitrogen. Systems having condenser to prevent the air-rich condensate in
load characteristics that result in frequent the condenser from being introduced into the
boiler shutdowns require more elaborate, fool- boiler. The turbine must be sealed and a con-
proof, wet lay-up protection systems if prob- denser vacuum established prior to recycle.
lems are to be avoided. Tables V and VI detail Including a preboiler recycle line has an ad-
recommended procedures to be utilized on all ditional benefit when part-flow condensate
high-pressure utility units. demineralization is employed in the cycle.
MINIMIZING CORROSION Demineralization permits filtration of corro-
DURING START-UP OPERATION sion products from the recycling feedwater,
During the Start-up of a high-pressure boiler, and will further permit cleanup of the drains
deaeration and pH adjustment must be pro- from the shell sides of the feedwater heaters
vided to assure that low feedwater-corrosion- during start-up. Characteristically,these heater
product levels are achieved. Plant start-ups drains contain the highest levels of crud in the
without deaeration will promote continued system. A condensate demineralizer system
corrosion of feedwater-system materials of designed for about 25 percent of full-load con-
construction. 13.14,15 This will result in signifi- densate flow provides all of the benefits de-
cant quantities of corrosion products being car- scribed.l3
ried into, and depositing within, the steam gen- Tables VII and VIII list the recommended
erator. The supply of undeaerated feedwater feedwater control limits for start-up operation
will also increase corrosion of steel compo- of drum-type cycling units.
nents within the steam generator. Deaeration of HIGH-PRESSURE DRUM-TYPE UNITS
condensate during start-up operations can be
obtained by use of deaerating condensers or by Although base-loaded utility drum-type
\

external deaerating heaters. Since deaeration units suffer from corrosion more during opera-
should be accomplished early in the start-up tion than during start-up, attention must still
sequence, auxiliary steam must be available for be directed toward procedures to prevent ex-
turbine-seal and deaeration requirements. cessive corrosion during start-up periods. It
CYCLING UNITS
1210 8 7 6 5
An adequate source of auxiliary steam
should be available to the deaerating heater 28
while the unit is starting up. If this is unavail- q 24
able, pegging-steam directly from the drum :
s
20
should be provided until turbine extraction
steam is available. As an alternative, a blow-
-@ 16
down flash tank designed for 5 percent of the 2 12
V)

maximum steaming rate of the boiler can also E


a
8
be used. In units without a deaerating heater, 4
deaeration is achieved solely by the condenser.
For the condenser to effectively deaerate cold 0' 30 60 90 120 150 180 212
feedwater, a significant vacuum must be main- Temperature, " F
tained. A reasonable approach is to recycle and Fig. 36 Solubility of oxygen in water from
deaerate the condensate in the system prior to air saturated.with water vapor
COMBUSTION
Water Technology

has not been found necessary to install special operation can bring with it a multitude of new
preboiler recirculation lines or condensate problems.
demineralization equipment on base-loaded SUPERCRITICAL CYCLES: FEEDWATER
high-pressure drum-type units. Normal start- A .

up sequence which includes the initiation of Start-up specifications &e important in su-
light steaming rates early in the start-up opera- percritical cycles, and neglect in this area may
tion, coupled with boiler drum blowdown, result in considerable deposit-caused diffi-
have been found effective in reducing the im- culties. Combustion Engineering has placed
pact of standby corrosion-product deposition. primary emphasis on the development of
As already noted, conversion of the base- start-uplcleanup procedures which assure
loaded drum-type unit to peaking or cycling steam-generator cleanliness over long periods

Table VII. Initial Start-Up and Restart After Long Outages*,


Cycling Drum-Type Boiler-see Fig. 37
Flow Expected
Phase Path O~erations Control Limits Cleanup Time

1 Flush to waste at approx. 25% 3 ppm (rnax.) suspended solids, Hours


MCR measured at HP heater outlet
2 Pressurize deaerator to 10-15
psig with auxiliary steam, estab-
lish condenser vacuum, and
place demineralizer in service. Total suspended solids 250 (max.)
Preboiler Oxygen 10
Cleanup Using condensate or feed pump Hydrazine 20 Time depen-
' and preboiler recirculating valve, Copper-alloy system 8.8-9.2 dent on run-in
clean up cycle maintaining 25% pH Copper-free system 9.2-9.4 of equipment
MCR deaerated flow.
Blowdown deaerator storage (All concentrations in ppb, meas-
tank as necessary to prevent ured at HP heater outlet; oxygen
recontamination of system. measured at deaerator outlet.)
Normal
Feedwater
Limits
Close preboiler recirculating
valve, place boiler feed pump in Total solids 50 (max.)
service and fire unit for turbine Total iron . 10 Normal limits
System warrnup roll, and synchroniza- Total silica 20 should be ob-
tion. Proceed to normal feed- Copper 10 tained before
in water control limits. Oxygen 5 exceeding
Service Hydrazine 10-20 one-third unit
Cascade heater drains to con- Copper-alloy system 8.8-9.2 load.
denser for polishing until unit pH Copper-free system 9.2-9.4
load exceeds 25%.
(All concentrations in ppb, meas-
ured at HP heater outlet; oxygen
measured at deaerator outlet.)
Note: Suspended solids concentration measured by Millipores filters with appropriate color comparator charts.

'Duration of outage longer than 4 days


COMBDSTlON
Water Technology
-
of time. A sub-loop cleanup philosophy is condensate purification equipment readily
utilized in which the crud level in the preboiler removes magnetite. Additionally, the low-
system is reduced to a low value before passing oxygen environment prevents further oxide
feedwater to the steam generator. This proce- generation.
dure assures the delivery to the boiler of feed- When performed at a sufficiently high veloc-
water which is low in iron, silica, copper, and ity, preboiler recirculation completely removes
oxygen. contaminants prior to furnace-wall cleanup.
Keeping oxygen values below 10 ppb en- Based on experience, a velocity of 2 feet per
hances effective and rapid contaminant reduc- second is recommended for this purpose and is
tion within the preboiler cycle. Hydrated iron obtained at approximately 25 percent maxi-
oxide, exposed to high-oxygen values, pre- mum continuous rating (MCR) with currently
cipitates readily and delays cleanup time. Con- designed feedwater heaters. When employing
version of this material by deaeration to black the recommended cleanup program, contami-
magnetite is essential for fast cleanup because nant reduction to specified feedwater quality

Table VIII. Cold Restarts After Short Outages*, Cycling Drum-Type Boiler (Fig. 37)
Flow Expected
Phase Path Onerations Control Limits Cleanup Time

2 Pressurize deaerator to 10-1 5 4 hours if C-E


psig with auxiliary steam, estab- recommended
lish condenser vacuum, and lay-up proce- ,

place demineralizer in service. Total suspended solids 250 (max.j dure has been
Oxygen 10 employed.
Using condensate or feed pump Hydrazine 20
Preboiler Copper-alloy system 8.8-9.2 Does not
and preboiler recirculating valve,
Cleanup clean up cycle maintaining 25% pH copper-free system 9.2-9.4 represent a
MCR deaerated flow. delay; this
cleanup may
Blow down deaerator storage (All concentrations in ppb, meas- b'e completed
tank as necessary to prevent ured at HP heater outlet; oxygen before boiler
recontamination of system. measured at deaerator outlet.) is available.
Normal
Feedwater
Place boiler feed pump Limits
in service.
Total solids 50 (max.)
Fire unit for turbine warmup, Total iron lo Normal limits
roll, and synchronization. Total silica 20 should be ob-
System Copper 10 tained before
in Proceed to normal feedwater Oxygen 5 exceeding
Service control limits. Hydrazine 10-20 one-third unit
Copper-alloy system 8.8-9.2 load.
Cascade heater drains to con- Copper-free system 9.2-9.4
denser for polishing until
load exceeds 25%. (All concentrations in ppb, meas-
ured at HP heater outlet; oxygen
measured at deaerator outlet.)
Notes: 1. No cleanup is required if feedwater quality meets recommended limits.
2. Suspended solids concentration measured by Millipore" filters with appropriate color comparator charts.
'Duration of outage maximum 4 days,
..

(1 ) Flow Path for Flush-To-Waste

Economizer

Deaerator Blowdown

( 2 ) Flow Path for Preboiler-System Cleanup

q=rFz%!bi
Superheater

Reheater
Economizer Boiler ne

Deaerator Blowdown

Fig. 37 Procedure for sub-critical unit start-up


-
CONBUSTION
Water Techndogy

I (1 ) Flow Path for Feedwater-System Cleanup


I

FedPumd I
L++ - - - - -Drip
- -~-u-m
- -d-~eminerakzer Pump
- - - - - - -Coddenser
---- 1
Deaerator Blowdown

( 2 ) Flow Path for Steam-Generator Cleanup

Feedpump' I Drip ~ u m d ~emineraiizer F,":pr


L* -------- - ----- ---- ----,---A
Deaerator Blowdown

Fig. 38 Procedure for supercritical unit start-up after a short outage


COMBUSTION
Water Technology

limits takes less than eight hours on start-up culation is completed. A delay in start-up will
following long outages. Preboiler cleanup fol- occur only when the condensate is badly con-
lowing short outages (up to four days) can be taminated; under these conditions, such a
accomplished in three to-four hours. No pre- delay can always be justified.
boiler cleanup is required for a hot restart if the A discussion of the complete procedures and
quality of the condensate meets the established feedwater control limits recommended for start-
standards of purity. up and normal operation of Combined Circu-
SUPERCRITICAL STEAM GENERATOR
lation units is beyond the scope of this chapter.
For illustrative purposes, however, Table IX
Cleanup of the furnace-wall system in a and Fig. 38 detail the procedure employed for
Combined Circulation supercritical unit is per- start-ups after short outages. Start-up cleanup
formed reliably and quickly because the boiler operations after long-duration outages require
recirculation pumps provide effective scrub- more time and additional flow paths and steps.
bing velocity. Particulate contamination is The effectiveness of this cleanup philosophy
maintained in suspension and is easily re- has assured that operational chemical clean-
moved through the start-uplseparator system. i n g ~have not been required more often than
This blowdown flow through the start-up sys- every three to four years. '8.19
tem rapidly reduces furnace-wall contamina-
PREVENTIVE CHEMISTRY
tion. Experience shows that the boiler furnace
DURING OPERATION, DRUM-TYPE UNITS
walls can be cleaned effectively if supplied
with a deaerated feedwater at about 250F. Two basic types of boiler-water treatment
Furnace-wall cleanup after long outages will can be successfully utilized in high-pressure
normally take less than three hours. Cleanup drum-type boilers: coordinated phosphate and
operations after outages up to four days will not volatile-based treatment. Volatile treatment
require a furnace-wall cleanup step if appro- does not requike the direct addition of any
priate wet lay-up procedures have been em- treatment chemicals to the boiler. The am-
ployed. The unit should be capable of being monia used for feedwater pH adjustment
fired as soon as any necessary preboiler recir- controls boiler-water pH. Fig. 39 illustrates a
I

10.0 - Na/P04

G
9.5

5
O

L
9
-
LD
CU
as
a
9.0 Optimum Control Range

-3
3 -
5 8.5 -
--

8.0 -
0 1
I
2
I
3 4 5 6
I I
7
I
8
ppm PO4

Fig. 39 Recommended coordinated phosphate treatment curve for operation between 2601 and
2900 psig
COMBUSTION
W . i v TechnOIogy

Table IX. Recommended Start-UpICleanup Procedure, C-E Combined


Circulation@Units (with Deaerating Heater) see Fig. 38 -
Cold Restarts After Short Outages I

Flow ' Expected


Phase Path Operations Control Limits Cleanup Time
1 Pressurize deaerator to 10-15
psig with auxiliary steam, estab-
lish condenser vacuum, and 4 hours if C-E rec-
place demineralizer in service. Total Solids 250 (ma.) ommended lay-up
Total Iron 50 procedure has been
Utilizing condensate or Total Silica 30 employed.
Feedwater booster pump and preboiler Copper 20
System recirculating valve, clean up Oxygen - 10 Does not represent
Cleanup a delay; this clean-
cycle maintaining 25% MCR Hydrazine 20
deaerated flow. PH 9.2-9.4 u p may be com-
pleted before boiler
Blow down deaerator storage is available.
tank as necessary to prevent (All concentrations
recontamination of system. in ppb.)

Transition Period: When control limits are met at HP heater outlet, close preboiler recirculating valve and es-
tablish BE and WD through-flow, using condensate or booster pump. To prevent excessive pressure drop across
BE valve, furnace wall outlet pressure should not exceed 1000 psig during cold water operation.
--

2 Continue BE and WD through-


flow until cleanup is complete.
Furnace-wall circulating pump
on during this phase. Less than 1hour
Steam Total Solids 750 ( m a . ) if C-E recom-
Generator Blow down deaerator storage Total Iron 500 mended lay-up
Cleanup tank as necessary to prevent Total Silica 30 procedure has
contamination of system. Copper 20 been employed.

When control limits are met, (All concentrations


proceed to next step. in ppb, measured at
furnace-wall outlet.)
Normal
Place boiler feed pump Feedwater
in service Limits

Fire unit for turbine warmup, Total Solids 50 (max.)


roll, and synchronization. Total Iron 10 Normal limits
System Total Silica 20 should be ob-
in Proceed to normal feedwater Copper 2 tained before
Service exceeding limits. Oxygen 5 exceeding one-
Hydrazine 10 third unit load.
Cascade heater drains to con- PH 9.2-9.4
denser for polishing until
load exceeds 25%. (All concentrations in ppb, meas-
ured at HP heater outlet; oxygen
measured at deaerator outlet.)
COMBUSTION
Water Technology

Table X. Typical Criteria for Operation of Drum-Type Boilers (2601-2900 psig)


Control Limits
Hotwell Conditions Operational Limitations Phosphate-pH* Volatile ~ i i l e r - ~ i tContml
di '

Total Solids < 0.05 ppm None TS < 15 ppm TS <2 ppm Normal
(Recommended) pH 9.1-9.6 pH 8.5-9.0
PO, 2-6ppm
Total Solids < 0.1 ppm Volatile treatment TS <15 ppm If on volatile treatment,
(Acceptable) of boiler water not pH 9.1-9.6 change to coordinated
suitable. PO, 2-6ppm phosphate-pH control.
Total Solids Limited operation. TS <50ppm Immediately start chemi-
0.1-1.0 ppm Schedule inspection pH 9.1-10.1 cal injection pumps to
(Abnormal) - . and repair of condenser PO4 5-20 ppm maintain excess phos-
as soon as system load phate and pH conditions.
requirements permit. Do not continue to oper-
ate unit if pH cannot be
maintained above 8.0 or
the total solids below 50
ppm. Increase blowdown
to limit total dissolved
solids concentration.
Avoid use of desuper-
heating spray water
by (1)permitting reheat
temperature to fall, or (2)
reducing load.
Total Solids > 1.0 pprn Emergency operation. TS < 50 pprn See above. Prepare to es-
(Excessive) 1. Immediately reduce pH 9.1-10.1 tablish chemical condi-
load as necessary to PO4 5-20 pprn tions for wet lay-up of
permit isolation of boiler unit and auxiliary
damaged condenser. equipment during con-
2. Prepare for orderly denser repair.
shutdown of the unit
if hotwell concentra-
tion cannot be quickly
reduced below 1.0
PPm. 'Maintain sodiudphosphate ratio 52.6

typical low-level coordinated phosphate curve Table X illustrates a philosophy of boiler op-
for use i n high-pressure boilers above 2600- eration with respect to level of contamination
psig drum operating pressure. Operation with entering the cycle. The recommendations and
pH and phosphate values which are below the guidelines presented i n this table, coupled
curve establishes that no free hydroxide exists with recommended feedwater quality, repre-
within the boiler water. The recommended op- sent t h e chemistry specifications which will
erating chemistry shown in Table X is reflective result in long-term steam-generator integrity
of this fact. Because free hydroxide does not ex- and cleanliness. It should be noted that coordi-
ist under these specified conditions, ductile nated phosphate boiler-water treatment must
tube failures from caustic attack, as discussed be employed during periods of condenser leak-
previously, will not occur.20 age. Volatile treatment does not have enough
W* Technology

buffering ability to maintain pH control under be reduced within eight hours to values below
these conditions. 2.0 ppm.
Certain deviations from normal chemistry
specifications may occur on occasion during PREVENTIVE CHEMISTRY
plant life, with little or no effect on component IN OPERATION OF SUPERCRITICAL UNiTS
integrity. These deviations are designated as Because a supercritical unit requires the ul-
abnormal conditions in Table X. Other possible timate in feedwater quality, a condensate de-
' deviations may result in extensive corrosion mineralizer must be included in the preboiler
problems. The serious nature of such devia- cycle to prevent condenser leakage salts from
tions requires immediate action, and this is entering thi feedwater. The normal feedwater
noted where applicable. limits for supercritical units are presented in
Table XI.
FEEDWATER CONTROL
Utility operators who have followed recom-
The steam generator acts as a concentrating mended start-up cleanup procedures, as well as
device during operation. Soluble feedwater recommended lay-up procedures, have main-
impurities which enter the boiler become con- tained a high degree of cycle cleanliness. Vir-
centrated in the boiler water because the steam tually all Combined Circulation units are ex-
leaving the drum carries off negligible quan- periencing operational chemical-cleaning fre-
tities of solids. The recommended feedwater quencies of from three to four years.
impurity limits given in Table XI cover a The successful operation of a supercritical
number of constituents. The total solids limit is unit with respect to water technology is
specified to minimize boiler fouling. The silica coupled to the proper operation of the in-line
concentration limit in normal operation is suf- condensate demineralizer system. Table XI1
ficiently low to assure that silica carryover to summarizes information on the operation of a
the turbine by the vapor or steam solubility supercritical unit during condenser leakage.
phenomena does not occur. The oxygen and pH The methods of limiting operation and control-
specifications should limit the pickup of iron ling the condensate demineralizer presented in
and copper from the preboiler equipment to this table, if properly implemented, will assure
those feedwater levels necessary for long-term steam generator and turbine cleanliness.
steam-generator cleanliness.
As long as feedwater total solids (TS)concen- Table XI. Recommended Feedwater
tration is less than 0.5 ppm, boilerlturbine cycle Limits, High-Pressure
operation is considered normal. Coupled with
Drum-Type Units
this is the requirement that pH value, oxygen ---

level, and copperliron levels are within the Total solids 50 ppb m a ~ .
values shown on Table XI. There are no opera- Total iron , ' 10 ppb max.
tional limitations, and the boiler-water control Total copper 10 ppb max.
is normal. Total silica 20 ppb max.
Operation with feedwater TS concentration Oxygen 5 ppb max.
between 0.5 and 2.0 ppm should be limited, Hydrazine 10-20 ppb residual
and condenser repairs should be scheduled as pH 8.8-9.2 (copper-alloy system)
soon as practical. Values of feedwater solids 9.2-9.4 (copper-free system)
concentration above 2.0 ppm TS are considered
emergency levels. Unit load should be imme- All measurements made at high-pressure heater out-
diately reduced, the damaged condenser set= letor economizer inlet.
tion isolated, and necessary repair work
Oxygen can be measured at deaerater outlet if cycle is
scheduled. The boiler-turbine cycle should be equipped with deaerating heater.
shut down if feedwater concentration cannot
COMBUSTION
Water Technology

ANALYTICAL METHODS alyzers for maximum sensitivity. Now, with the


The implementation of control methods to availability of computers for powerplant water-
minimize corrosion-product release, as well as chemistry control, monitoring and diagnosing,
the detection of contaminant inleakage, re- as well as automatic control, arepractical.21
quires a continuous analytical program. All au- Table XI11 gives a recommended frequency of
tomatic analytical instrumentation should be analysis for high-pressure utility steam genera-
maintained operational and calibrated. tors if continuous analyzers are not available.
If chemical auto-analyzers are not opera-
tional, greater emphasis must be placed on lab-
oratory analyses. Membrane-filter testing may
INDUSTRIAL BOILER-WATER
provide an adequate indication of water quality TREATMENT
with respect to corrosion products. But pri- Internal chemical treatment systems are pri-
mary reliance must be placed on laboratory marily designed to prevent scale formations re-
analytical methods for contaminant and sulting from residual amounts of calcium and
corrosion-product-level determinations. The magnesium hardness in the feedwater. Exter-
findings of chemical analyses should deter- nal treatment and control must provide a feed-
mine whether, for example, cleanup circula- water low in hardness, alkalinity, silica, metal
tion should continue on a supercritical unit, or oxides, and oxygen. Because of their extreme
whether silica values are low enough in a solubility, sodium salts are of concern only
drum-type unit to allow a pressure increase. to the extent of their contribution to the total
On any high-pressure utility boilerlturbine dissolved solids concentration. However,
cycle, the condenser leak detection system is boiler-tube scale consisting of calcium and
particularly important. Leakage instrumenta- magnesium components is not uncommon in
tion should be installed such that, if the con- units operating below 900 psig. These scales
denser has segmented compartments, each often are the direct result of loss of chemical
compartment can be analyzed for leakage indi- control, permitting dense calcium precipitates
vidually. Cation conductivity offers good sensi- such as calcium sulfate or calcium silicate to
tivity for detecting condenser leaks. Many form. They may also be a more subtle result of
plants are also being equipped with sodium an- porous-hardness sludge or metal oxides which

Table XII. Criteria for Operation of Supercritical Unit During Condenser Leakage
Hotwell Salt Leakage
Concentration Description Operational Limitations Demineralizer Control

<0.5 ppm Normal None. Normal -.

0.5-2.0 ppm Abnormal Limited operation. Schedule in Control demineralizer sequence to


spection and repair of condenser assure that tanks will not exhaust
as soon as system load require- simultaneously. If ammonia cycle is
ments permit. employed, override ammonia step.

>2.0 ppm Excessive Emergency operation. Prepare for Place all available tanks in service .
orderly shutdown of the unit. Im- immediately. If reduced load operation
mediately reduce load as neces- is assumed, transfer resin which is
sary to permit isolation of dam- most exhausted and bring in spare
aged condenser section. Initiate charge. Override ammonia regenera-
shutdown if hotwell concentra- tion step.
tion cannot be quickly reduced
below 2.0 ppm.
Table XIII. Recommended Frequency of Analysis for High-Pressure Utility Units
-
Should condenser leak-detection equipment be out of service, manual conductivity readings should be taken at
the condensate pump discharge three times dailv.
-
Supercritical-Type Drum-Type
Feedwater at Economizer Inlet Feedwater at Economizer Inlet
pH, per shift Same as supercritical units
02,per shift
Silica, twice weekly Boiler water
Copper, twice weekly pH, per shift
Total iron, twice weekly PO4,per shift
Total solids, per shift
Silica, twice weekly

Table XIV. Typical Phosphate Control Limits for Industrial Units


Pressure (psig) 450-600 600-900
Hydroxide Alkalinity as OH (ppm) 50-100 25-50
Phosphate as PO, (ppm) 2040 5-10
Sodium Sulfite as Na,SO, [ppm) 20--40 5-1 0
' Silica as SiO, (ppb) 50 (max.) 1 0 (maximum)

permit boiler water to penetrate to the tube sur- tion of calcium as a calcium hydroxyapatite,
face precipitating complex silicate scales. Ca,,,(PO,),(OH), and magnesium as serpentine,
Formation of scale, below 900 psig, is gener- 3Mg0 ~ 2 S i 0 , 2H,O.
ally more of a concern with respect to causing In contrast to low-pressure operation, boiler
overheating failures than promoting corrosion tube failures in units above 900 psig can be
attack. Two basic systems are now available for caused by corrosion. Accordingly, the coordi-
prevention of internal hardness scales: the nated phosphate pH system is used to control
conventional phosphate-hydroxide methods boiler-water chemistry as with utility high-
and the more recently adopted substitute sys- pressure boilers.
tems ,involving chelating agents. Both are
proven systems, but the success of either de-
pends on the diligence with which they are Chelating agents have received wide accep-
applied. tance as a substitute system for the con-
PHOSPHATE-HYDROXIDE METHOD ventional phosphate-hydroxide treatment
methods. The most common is the sodium salt
The phosphate-hydroxide methods can be of ethylenediaminetetraacetic acid (EDTA). As
segregated into one that maintains an excess of briefly explained in a previous section, these
hydroxide alkalinity and one that involves no organic agents act with the residual calcium
* excess or "free" hydroxide content. The former and magnesium in the feedwater to form sol-
has a long history of use and is still the most uble complexes. Ideally, this should result in
prevalent system for low-pressure operation. boiler surface conditions which are completeiy
Table XIV presents typical control limits. free of any hardness deposits. The soluble
The intent of phosphate control systems is to hardness complexes will be removed through
provide conditions conducive to the precipita- the continuous blowdown line. With con-
COMBUSTION
Water Tlchndogy

ventional phosphate treatment, it is difficult to research efforts, there is incomplete under-


maintain all of the hardness end products in standing and much empiricism remains in the
suspension. As a result, some accumulations techniques for correcting problems resulting
normally are found in drums and headers. from incomplete separation of steam and water
Most experience with this treatment method in boiler equipment.
has been limited to operating pressures of 900
psig and below, but some use on 1250- and CLASSIFICATION OF CARRYOVER
1350-psig units has been reported. Economi- Carryover of boiler water in steam leaving
cally, justification for its use is limited to feed- the drum provides a path for introducing solid
waters of low hardness concentrations (1 to 2 materials into the steam. Modern separator
ppm). Such evaluation usually considers the designs can mechanically reduce the mois-
savings realized by the elimination or reduced ture content of the steam to 0.2 percent or less.
frequency of chemical'cleaning. But in addition to mechanical carryover of
Chemical additions are made in a continuous boiler water, another mechanism exists that re-
mode, withthe amount based on the concentra- sults in the contamination of steam with solid
tion of hardness salts in the feedwater. The materials.
chelants must be injected after the boiler feed- As operating pressures increase, the steam
water pump to prevent corrosion of the pump phase exhibits greater solvent capabilities for
components. Earlier attempts to utilize the the salts that may be present in the water phase.
chemical-feed line to the boiler drum also These salts will be partitioned in an equilib
resulted i n severe corrosion of this line. High- rium between the steam and water, a phenom-
oxygen concentrations in the feedwater drasti- enon known as vaporous carryover. Vaporous
cally increase the corrosivity of the chelants. carryover will contribute an additional quan-
Thus, it is imperative that good deaeration of tity of boiler water solids directly to the steam,
the feedwater be maintained. independent of'the efficiency of steam-water
A chelant program can be effective in pre- separation components.
venting deposits or damaging boiler tubes Silica was the first material found to exhibit
depending primarily on the knowledge and significant vaporous carryover. Silica fouling
experience of the user. Of course, before in- of turbines was common until it was recog-
itiating such a program on any boiler, guide- nized that successful control of the amount of
lines, control limits, and analytical procedures silica in the steam could only be accomplished
must be established with the cooperation of the by controlling the amount of silica in the boiler
chelant supplier or water-treatment consultant. water. A similar solution will be required for
other solids when operating at high pressures.
CARRYOVER vaporous carryover contributes a significant
proportion of total solids in the steam as drum
AND STEAM SAMPLING operating pressures increase above 2600 psig.
The mechanical aspects of steam and water Table XV shows findings of a laboratory study
separation are covered in Chapter 5, in which on vaporous carryover.22 For various salts, the
drum-internal design for utility and industrial table lists percent vaporous carryover, which is
boilers is described. This section deals with the the ratio of the salt concentration in the steam
phenomenon of carryover, methods of steam and boiler water. In each case, sodium was
sampling, and techniques of steam-purity de- measured and then converted to the appropriate
termination. Once again, these subjects cannot salt concentration.
be understood solely by rigorous theoretical When calculating total solids in the steam,
analysis. Knowledge of laboratory testing pro- vaporous carryover is assigned a value of 0.1
cedures and ability to interpret field operating percent at drum operating pressures above
experience are required. Despite intensive 2600 psig.
Table XK Summary of Laboratory Results
Pressure (psig) 2600 2800 3000
C.oncentration (ppm) 15 500 15 500 15 500
Sodium Sulfate 0.02% 0.03% 0.04% 0.07% 0.28% 0.4890
Disodium Phosphate 0.01% 0.07% 0.03% 0.18% 0.41% 0.74%
Trisodium Phosphate 0.02% 0.11% 0.04% 0.30% 0.35% 1.3 ?O
Sodium Chloride 0.0401' 0.18% 0.09% 0.36% 0.39% 1.2 k
Sodium Hydroxide 0.02% 0.31% 0.08% - 0.69% 0.55% 2.2 90

Mechanical carryover may be classified un- installation of drum internals. At times, the
der four headings: priming, spray, leakage, and local contamination may not be sufficient to be
foam carryover. Each results. in troublesome reflected in steam-purity measurements of total
deposits in the superheater or on the steam- steam flow. A careful inspection of drum inter-
turbine blades. n a l ~will usually reveal this source of car-
Priming is the development of excessive ryover. Where the leakage is sufficient to regis-
moisture in the steam because of spouting or ter impurity tests of steam, it will be found that
surging of boiler water into the steam outlet. the impurity increases slowly with rating and
This is a rare, easily identified type of car- is relatively insensitive to changes in water
ryover. It is usually promoted by the mainte- level and boiler-water concentration.
nance of too high a water level in the drum, Foam carryover is the development of exces-
spouting of a submerged riser or sudden swel- sive moisture in the steam from carryover of
ling of the water in the boiler on a drop in pres- foam from the drum. It is the most common
sure, or sudden increase in rating. Priming is form of carryover in low-pressure units, in
rarely, if ever, associated with boiler-water which the boiler water may contain high con-
concentration. centrations of dissolved solids, and is the most
Spray carryover, mist or fog are degrees of troublesome and most erratic type.
atomization of the boiler water. Mist is carried Foam forms in the steam-generating sections
from the drum by the steam as dust is carried by of the boiler when the water-films around the
air currents. This carryover is present to a de- generated steam bubbles are stabilized by the
gree in all boilers, and it is the function of drum impurities in boiler water. Boiler circulation
internals to separate and filter out such spray carries this foam up to the boiler drum where it
before the steam leaves the drum. Development tends to accumulate at the water level. The
of spray carryover indicates failure of the drum foam produced may entirely fill the steam
internals because of exceeding the velocity space of the boiler drum or it may be of a rela-
limitations of the purification equipment. It is tively minor depth. Although foaming in boil-
characterized by initial development below the ers has been recognized for many years, its
full rating of the boiler and it continues to in- causes are not clearly defined and are worthy of
crease with boiler load. Spray carryover is not further investigation.
sensitive to boiler-water concentration below The bulk water in the circulating mixture en-
the foaming range. Improved drum internals tering the drum is readily separated, but the
are capable of reducing the steam-borne mist to wet emulsion of very small foam bubbles col-
avalue as low as a few parts per billion of solids. lects at the water level to a depth largely de-
- . Leakage is a general term applied to bypass- pendent on the rate of drainage of excess water
ing of impure steam or boiler water through the out of the foamy mass. A considerable amount
drum internals. Normally localized, this form of moisture is trapped in the foam. When foam
of carryover is directly related to poor design or carryover occurs, it is frequently sudden and
COMBDSTION
Water Techn2Iogy

excessive, akd the steam sample registers a sol- interpreted to determine the specific source of
ids content characteristic of boiler water. a carryover condition.
IDENTIFICATION OF CARRYOVER Steam flow establishes the velocity distribu-
tion in the boiler drum. -~xces&vesteam flow
A systematic field investigation can identify can increase steam velocity to a point that en-
carryover. A variety of factors which may be trained mositure can overload the dryer.
classified as mechanical, water or operating High water can create spouting and excessive
conditions affects the sources of carryover and carryover. This can occur at low steaming rates
the carryover itself to different degrees. As and boiler-water concentrations.
noted previously, foaming in the boiler is the
most common type of carryover and is most Foaming is a characteristic of boiler-water
troublesome and erratic. Special test methods concentration. With water level and steaming
have been devised to demonstrate the presence rate at recommended values, any carryover
of foam blankets and for obtaining boiler per- which can be precipitated or eliminated by a
formance without danger of serious carryover to change in boiler-water concentration can be at-
the superheater and turbine.23 tributed to foaming.
Steam flow, water level and boiler-water Fig. 40 illustrates the development of foam-
concentration are the three major factors that ing in a drum. The plot indicates purity values
can create carryover. By varying these three of steam samples taken ahead of the steam
factors, one at a time, test results can usually be dryer and at the outlet of the boiler drum for a

TEST 1 TEST 3

I
I I I I I I I I I I I I I l l !
0 I

500 I
0
50
40-
- It
30 - i
20 -
I
0 I I I I I
-430-500
T--01 -
5 C
d
e
s
a
O-
TJ w
- Boiler Outlet L. 1
$5 9h 9 1 idlo i i r iilm ii&,,~io i b Z ~ Y;z 3:ii &I,,& i b do 2k 3:; 3 3
A. M P.M. P.M.
TIME
I 1
Fig. 40 Development of foaming in a boiler drum
constant level of water in the drum and a typi- than 650 pprn in one boiler and, in another
cal steam load. The principal change is in the case, no carryover troubles developed with
boiler-water concentration. concentrations as high as 15,000 ppm. Al-
At a boiler-water concentration of about 550 though these inconsistencies exist, it is neces-
ppm, the sample ahead of the dryer was about 5 sary to maintain a lower value of foam-
mmhos (1 mmho is approximately 0.5 pprn of producing chemicals in boiler water or add
solids) and the sample at the boiler outlet was foam dispersing chemicals to the water.
about 7 mmhos. Increasing the boiler-water Organic antifoam agents have been de-
concentration to about 1800 to 2000 pprn did veloped to dispel certain foams at higher steam
not alter the purity of the steam leaving the pressures. Ordinary tannin and starch com-
boiler drum. But the sample ahead of the steam pounds are only effective at low pressures.
dryer increased gradually to a value of about 40 Lignin sulfonates, alkaline polyamides, poly-
mmhos. Thus, with an established steam flow, merized esters and alcohols have been effective
and a similar water level, there was a marked foam dispersing agents. The function of an effi-
increase i n solids content of the steam entering cient antifoam agent is to reduce the number of
the dryer. This is indicative of the presence of a small. bubbles and to confine steam-bubble
mildly foamy condition in the boiler drum as formation to a small number of large bubbles
the only change was in the concentration of which will exhibit the tendency to coalesce and
boiler-water solids. grow larger. Under these conditions, the bub-
Increase of boiler-water solids to about 2800 bles are unstable and tend to break easily. Anti-
to 3000 pprn in the boiler water, at the same foam agents are not equally effective with all
steam load and water level as in the prior two boiler waters. It is necessary to select an anti- ,
tests, produced severe foaming in the boiler. foam compatible with the chemical charac-
The space between the water level and the teristics of the boiler water, and trial of several
dryer was practically filled with a foam blanket compounds may be necessary before the foam
on the water. This is evident in the high solids can be neutralized satisfactorily.
content of the sample entering the dryer. Se- Foam will fill the free surface area of a
vere foam carryover occurred when the water separating device increasing local velocities
level in the drum was at or above drum center. and promoting a serious carryover of boiler wa-
This was not a factor in the prior tests. Thus, a ter. Foam carryover may be stopped by a quick
small change in water level was sufficient to reduction in boiler-water concentration or
push the foam blanket into the drum internals lowering the drum level. Centrifugal devices
creating a severe case of foam carryover. have shown a greater ability to handle foamy
waters than simple internals. The basic func-
CAUSES OF FOAMING.
tion of a centrifugal device is to dehvdrate the
Foaming is basically a result of chemical foamy emulsion. The dehydrated-foam bubbles
conditions, and boiler-water concentration and can be easily broken up by screens or other
composition are important factors involved. simple devices. Foam in this type of separator
High total solids and high suspended solids will decrease the water-separating efficiency of
aggravate the formation of foam. High caustic the device.
alkalinity, oil, organic contamination and ex- In general, foam carryover from a boiler can
cess phosphate also increase the foaming ten- be avoided by keeping boiler-water concen-
dency in boiler water. While the general effect trations within the range suggested by the
of a component upon foaming may be antic- American Boiler Manufacturers Association
ipated, it is impossible to predict whether faam - (ABMA). These specifications, of course, can-
formation will occur by a cursory examination not be a guarantee against foaming which, as
of boiler water. Extreme cases are on record indicated previously, is primarily a chemical
where excessive foamover occurred with less problem.
COMBUSRON
Water Tachnology

Table XVI. Recommended Boiler Water Limits and Associated Steam Purity
(at Steady-State, FulCLoad Operation)
Dm-Type Boilers
Drum Range of Range of Suspended Solids Range of
Pressure Total Dissolved Solids' Total ~ l k a l i n i t ~ z in Boiler Water, Total Dissolved Solids "'
psi8 in Boiler Water, in Boiler Water ppm (Maximum) in Steam,
(Actual) ppm (Maximum) ppm P P (Maximum
~
Expected Value)
0-300 700-3500 140-700 15 0.2-1.0
301-450 600-3000 120-600 10 0.2-1.0
451-600 500-2500 100-500 8 0.2-1.0
601-750 200-1000 40-200 3 0.1-0.5
. 751-900 150-750 30-150 2 0.1-0.5
901-1000 125-625 25-125 1 0.1-0.3
1001-1800 100 Note (3) 1 0.10
1801-2350 50 Note (3) NIA 0.10
2351-2600 25 Note (3) NIA 0.05
2601-2900 15 Note (3) NIA 0.05
Once-Through Boilers
1400 and above 0.05 NIA N/A 0.05
Notes: 1. Actual values within the range reflect the TDS in the feedwater. Higher values are for high solids; lower values are for low solids in
the feedwater.
2. Actual values within the range are directly proportional to the actual value of TDS cf boiler water. Higher values are for the high
solids; lower values are for low solids in the boiler water.
3. Dictated by boiler water treatment.
4. These values are exclusive of silica. Source: American Boiler Manufacturers Association

Concentration limits as a function of pressure ple that is representative of a large mass of ma-
are shown in Table XVI. terial always presents a difficult problem. The
In both utility and industrial plants, adher- sample size, particle-size distribution and den-
ence to the ABMA specifications has produced sity relationship are some factors which must
satisfactory operation because of marked im- be considered where there is a question of lack
provements in water technology and boiler de- of homogeneity. In a homogeneous sample of
sign. Normally, the steam-purity-specification fine particle size, sampling is a relatively easy
limit for low-pressure boilers is less than 0.5 operation.23
percent moisture in the steam. With the use of In sampling steam, the impurities may be
superheaters and higher pressures, the boilers solid, liquid, and gaseous. The solid may be in
must deliver a steam product containing less the form of a finely divided sludge particle.
than 1.0 ppm of solids entrained in the steam. Liquid impurity may be in the form of fog or
Steam purity of high-pressure boilers has been mist in minute droplets, possibly having a
markedly improved and values of less than 0.01 solid particle as a nucleus. More adversely, it
ppm of impurity are achieved. may be in a form of a surface film on a pipe wall.
Moisture itself is not involved in the concept of
STEAM SAMPLING METHODS steam purity except that it may carry solids in
Steam samples for measuring purity are usu- solution or suspension.
ally taken ahead of the superheater. These are Sampling impurities in steam is analogous to
condensed and cooled. Collecting a true sam- the difficulty of locating a needle in a haystack.
.-
At a sampling rate of 100 pounds per hour, the DETERMINATIONOF STEAM PURITY
impurity content of 1ppmis represented by the Steam purity isnormally determinedbymeas-
withdrawal of 0.7 grains of solid per hour. uring either the electrical conductivity or so-
Steam lines contain bends, elbows, valves and dium content of the condensed steam sample.
other fittings which can disturb the flow and Measuring electrical conductivity is widely
segregate the impurities. used to monitor steam purity in industrial
B. J. Cross has outlined the assumptions low-pressure boilers. This method is described
reached in the design of the steam sampling in ASTM Standards D 1125, Electrical Conduc-
nozzle described in ASTM Standards D 1066, tivity and Resistivity of Water.
Sampling Steam. The velocity front must be Gases dissolved in a condensed sample affect
reasonably flat, and the density difference of conductance and indicate an erroneous level of
steam and mist or fog carried along with it must solid impurity. These gases may be removed by
be in the same order of magnitude as that of degasification. Methods suggested for estab-
water and steam at the pressure .and tempera- lishing the content of solids impurity in steam
ture of the steam in the line. Basic prerequisites are described in ASTM Standards D 2186,
for use of the ASTM nozzle design are that the Deposit-Forming Impurities in Steam, which
velocity of the steam entering the ports is the provides four alternative techniques. The ref-
same as the line velocity of the steam and that eree method for establishing the total solids in
each port of the sampling nozzle shall represent the steam is by evaporation, as specified in
an equal area of the sampling section.Z4 ASTM Standards D 1888, Particulate and Dis-
Turns and other irregularities of the steam solved Matter, Solids, or Residue in Water.
, line influence distribution of solid and liquid Determination of solids in steam by conduc-
impurities. The sample point should be as tance is not sensitive to impurities in the parts
remote as possible from a source of distur- per billion range, which is the range required
bance. It should also be located where there is a for determination of steam purity in high-
run of at least ten diameters of straight piping. pressure utility boilers. Analysis of the steam
The preferred location with respect to position, sample to determine the sodium content in the
in order of decreasing preference, is impurity, by flame spectrophotorhetric tech-
nique, is the most accurate method developed
(a) vertical pipe, downward flow
to establish solids content. This technique is
(b)vertical pipe, upward flow described in ASTM Standards D 1428, Sodium
(c)horizontal pipe, vertical insertion and Potassium in Water and Water-formed
(d) horizontal pipe, horizontal insertion Deposits by Flame Photometry.

REFERENCES 2 E. W. Lohr and S. K.Love, The Industrial Utility of Public


\lraterSupplies in the United States, 1952:parts 1 and 11,
Eskel Nordell, Water Treatment for Industrial And Other Geological Survey Water supply Papers 1299 and 1300,
Uses, second edition. New York: Reinhold Publishing respectively. Washington: U.S. Government Printing Of-
Corp., 1961. fice. 1954.
Sheppard T. Powell, Water Conditioning For Industry,
first edition, N~~ york: McGraw-Hill publishing Go,, R. E. Hall, et al., "Phosphate in Boiler Water Condition-
1954. ing," Journal of the American Water Works Association,
21(1):79-100,January 1929.
Betz Laboratories, Inc., Betz Handbook of Industrial
Water Conditioning, seventh edition. Trevose, Pa.: Betz, " Richard C. Corey and Thomas J. Finnegan, "The pH, Dis-
1976. solved Iron Concentration and Solid Product Resulting
P. Harner, et al., eds., Industrial Water Treatment Pmc- the Between Iron and Pure Water at Itoam
tice. London: Butterworths, 1961. .- Temperature," Proceedings of the American Societffor
Testing and Materials, Preprint no. 101,1939.
The NALCO Water Handbook, sponsored by The Nalco
Chemical Company, Second Edition. New York: McGraw- E. Berl and F. van Taack, " ~ b &die Einwirkung von
Hill Publishing Company. Laugen und Salzen auf flusseisen unter Hochdruck-
COMSTION
Water Technology

bedingungen und uber die Schutzwirkung von combustion' Engineering publication TIS-5859. F. Ga-
Natruimsulfat gegen den Angriff von Aetznatron und von brielli, N. C. Mohn, and W. R. Sylvester, "Water Chemis-
Chlormagnesium," (The Action of Caustic and Salts on try Aspects of Cyclic Operation for Older High Pressure
Steel under Conditions of High-pressure and the Protec- Drum-Type Boilers", Proceedings of the American Power
tive Effect of Sodium Sulfate against the Attack of Sodium Conference, 45:989-999, 1983. Chicago: Illinois Institute
Hvdroxide and Magnesium Chloride). Forschung- of Technology, 1983; also as Combustion Engineering
&beiten, no. 330. ~ e r f i nVDI,
: 1930. publication TIS-7383.
6 S. F. Whirl and T. E. Purcell, "Protection Against Caustic F. Gabrielli, N. C. Mohn, and B. C. Teigen, "Deposit
Embrittlement by Coordinated Phosphate-pH Control," and Water Chemistry Studies with Rifled Tubing," Pro-
Proceedings of the Third, Annual Water Conference, ceedings of the American Power Conference, 46:973-
Pittsburgh, November 9-10,1942, pp. 45-60. Pittsburgh: 984, 1984. Chicago: Illinois Institute of Technology,
Engineers' Society of Western Pennsylvania, 1942. 1984. Also as Combustion Engineering Publication TIS-
7530.
H. A. Grabowski, et al., "Problems in Deaeration of Boiler
Feedwater," Combustion, 25(9):43-48, March 1955. J. J. Kurpen and D. L. Dixson, "Operating Experience in
Samual Glasstone, "Overvoltage and Its Significance in Cycle Cleanup for Supercritical Pressure Units," Proceed-
Corrosion," Corrosion and Material Protection, 3(6): ings of the American Power Conference, 30: 883-896,
15-18, J u n e J u l y 1946. 1968. Chicago: Illinois Institute of Technology, 1968.

H. A. Klein and H. A. Grabowski, "Corrosion and Hydro- l9 K. L. Atwood and G. L. Hale, "A Method For Determining
gen Damage in High Pressure Boilers", Presented at the Need for Chemical Cleaning of High-Pressure Boilers,"
Second Annual Educational Forum on Corrosion, Proceedings of the American Power Conference, 33:
National Association of Corrosion Engineers, Drexel In- 710-720, 1971. Chicago: Illinois Institute of Technology,
stitute of Technology, Philadelphia, September 15-17, 1971.
1964. Combustion Engineering publication TIS-2652. 20 H.A. Klein, "Use of Coordinated Phosphate Treatment to
lo P. GoldsteinandC. L.Burton, "Research Study onInterna1 Prevent Caustic Corrosion in High Pressure Boilers,"
Corrosion of High-Pressure Boilers," Transactions of the Combustion, ~ ( 4 )45-52,
: October 1962.
ASME. Journal of Engineering for Power, 91, Series A: 21 R. J. Barto, D. M. Farrell, F. A. Noto, and S. L. Goodstine,
75-101, April 1969; also in ASME Paper No. 68-PWR-7. "Intelligent Chemistry Management System (1CMS)-A
New York: American Society of Mechanical Engineers, New Approach to Steam Generator Chemistry Control'',
1968. Proceedings of the American Power Conference,
48:1025-1031, 1986. Chicago: Illinois Institute of Tech-
" J. A. Armantano and V. P. Murphy, "Standby Protection nology, 1986.
of High Pressure.Boilers," Proceedings of the 25th In-
ternational Water Conference, Pittsburgh, September 2& 22 S. L. Goodstine, "Vaporous carryover of Sodium Salts in
30, 1964, pp. 111-124. Pittsburgh: Engineers' Society of High Pressure Steam." proceedings of the American
Western Pennsylvania, 1964. Power Conference, 36:784-789. Chicago: Illinois Institute
of Technology. 1974; also as Combustion Engineering
12 L. H. Vaughn and C. V. Runyan, "Corrosion Protection of publication TIS-3973.
Boilers and Associated Equipment During Idle Periods,"
Proceedings of the American Power Conference, 33: 2JP. B. Place, "Carryover Problems and Identification of Car-
721-729.1971. Chicago: Illinois Institute of Technology, ryover Types:' Combustion, 18(9):29-34, March 1947.
1971.
P. B. Place, "Steam Purity ~etermination.Part I. Evalua-
l3 B. T. Hagewood, et al., "The Control of Internal Corrosion tion of Test Results," Combustion, 25(10): 62-65, April
in High-Pressure Peaking Units," Proceedings of the 1954. -
American Power Conference, 30: 939-948,1968. Chicago: P. B. Place, "Steam Purity Determination. Part 11. Methods
Illinois Institute of Technology, 1968. of Sampling and Testing," Combustion, 25 (11): 41-44,
14 H. A. Grabowski, et al., "Problems in Deaeration of Boiler May 1954.
Feedwater," Combustion, 25(9): 43-48, March 1955. P. B. Place, "Steam Purity Determination. Part 111. In-
terpretation of Test Results." Combustion, 25 (12): 43-46,
l5 A. F. Kelly, et&, "Modify Base-Load Turbines for Peak- June 1954.
ing Service," Power, 115(4):62-63. April 1971.
3 B. J. Cross, "The Sampling of Steam for the Determina-
16 F. N. Speller. "Control of Corrosion by Deactivation of Wa- tion of Purity:' Proceedings of the Eleventh Annual Water
ter," Franklin Institute Journal, 193(4): 515-542, April Conference, Pittsbugh, October 16-18. 1950. pp. 71-82.
1922. Pittsburgh: Engineers' Society of Western Pennsylvania,
1950.
17 F. Gabrielli and bV. R. Sylvester, "'1Vater Treatment Prac-
tices for Cyclic Operation of Utility Boilers," Proceedings "Standard Method of Sampling Steam," ASTM Standards
of the Internationd LVater Conference, Pittsburgh. Oc- D1066.Annual Book of ASTM Standards, Part 31: Water.
tober 31-November 2.1978. pp. 193-208. Pittsburgh: En- Philadelphia: American Society for Testing and Mate-
gineer's Society of LVestern Pennsylvania, 1979; also in rials. latest edition.
C O ~ 0 1 S
water rechnology

BIBLIOGRAPHY Klein. H. A., "A Field Survey of Internation Corrosion in


High Pressure Utility ~ o i l e r s , " ~ r o c e e d i nof~the
s American
Atwood, K. L., "Solvent Selection for preoperational and
Operational Cleaning of Utility Boilers," Combustion, 42
-
Power Conference. 33: 702-709. 1971. Chicano: Illinois In-
stitute of Tkchnology, 1971.
(3): 16-21, September 1970.
Atwood, K. L. and J. A. Martucci, "The Application of Klein, H. A. and K. L. Atwood, "Chemical Cleaning of
Hydrochloric Acid and Ammonium Bromate for Scale Re- Utility Boilers."Proceedings ofthe American Power Confer-
moval i n Utility Boilers," Proceedings of the 28th Inter- ence, 26: 762-778, 1964. Chicago: Illinois Institute of
national Water Conference, Pittsburgh, December 11-13, Technology, 1964.
1967. pp. 167-179. Pittsburgh; Engineers' Society of West- Klein. H. A. and P. Goldstein, "The Effects of Water Qual-
e m Pennsylvania, 1967. ity on the Performance of Modern Power Plants." Presented
Brown, R. D. and D. A. Harris, "Large Coal-Fired Cycl- at the 24th Annual Conference bf the National Association of
ing Unit," paper presented at the ASME-IEEE-ASCE Joint Corrosion Engineers, Cleveland, Ohio, March 18-22, 1968,
Power Generation Conference, Portland, OR, September Paper No. 12; also in Combustion Engineering publication
2 W c t o b e r 2, 1975. Combustion Engineering publication TIS-2891.
TIS-4558. Kurpen, J. J., "Externally Regenerated Condensate De-
mineralization Systems for Once-Through Steam
Chojnowski, B. and R. D. B. Whitcutt, "Corrosion Failure:
Generators." Presented at the Liberty Bell Corrosion Course,
One Cause and a Cure in an Operational Boiler," Combus- Philadelphia, PA., Sept. 16-18, 1969. Sponsored by Natl.
tion, 48 (5): 28-33, November 1976. Assn. of Corrosion Engineers and Drexel Institute of
Clayton, W. H., J. G. Singer, et al., "Design for Peakingi Technology; also in Combustion Engineering publication
Cycling:' paper presented at the Joint Power Generation TIS-3071.
Conference, Pittsburgh, September 27-30, 1970; also in Levendusky, J. A. and L. Olejar, "Condensate Purification
ASME Paper No. 70-PWR-9. New York American Society for
Applications of the Power Process in High-Pressure Utility
Mechanical Engineers, 1970. Also in Combustion Engi-
neering Publication TIS-2927. Plant Cycles." Proceedings of the American Power Confer-
ence, 29, 840-856, 1967. Chicago: Illinois Institute of
Gabrielli, Frank, et al., "Contamination Prevention of Technology, 1967.
Superheaters and Reheaters During Initial Startup and Op- Rivers, H. M., "Concentrating Films: Their Role in Boiler
eration," Proceedings of the American Power Conference, Scale and Corrosion Problems." Proceedings of the Twelfth
38: 296-310,1976. Chicago: Illinois Institute of Technology Annual Water Conference, Pittsburgh, Oct. 22-24,1951, pp.
1976.
131-145 Pittsburgh: Engineers' Society of Western Pennsyl-
Gabrielli, F., et al., "Prevent Corrosion and Deposition vania, 1951.
Problems in High-Pressure Boilers:' Power, 122 (7): 85-92
July 1978. also i n Combustion Engineering Publication Stocky, D. G. and K. L. Atwood, "Non-destructive Testing
TIS-5271. for Location of Corrosion Damage in High Pressure Boilers.
Presented at the Meeting of the Southeastern Electric Ex-
Goodstine, S. L. and J. J. Kurpen, "Corrosion and Corro- change, New Orleans, April 29-30, 1971; also in Combus-
sion Product Control in the Utility Boiler-Turbine Cycle," tion Engineering publication TIS-3246.
Combustion, 44 (11): 6-18, May 1973.
Ulmer, R. C. and H. A. Klein, "Impurities in Steam from
Greene, N. D.and M. G. Fontana, "A Critical Analysis of High Pressure Boilers." Proceedings of the ASTM, 61:
Pitting Corrosion,"Corrosion, 15 (1):41-47, January 1959. 1396-1411,1961.
Kennedy, C. M., et al, "Experience with High Rate Am- Wages, C. W. and C. W. Smith, "Operating Experience of a
moniated Mixed Beds for Condensate Polishing of CIPSCO Deep-bed Condensate Polishing System." Proceedings: 38th
Coffeen Station." Combustion, 39 (9): 19-30 Mafch 1968. International Water Conference, Pittsburgh, PA, Nov. 1-3,
Klein, H. A., "Corrosion of Fossil Fueled Steam Gener- 1977, pp. 111-121. Pittsburgh, Engineers' Society of West-
ators." Combustion 44 (7): 5-20, January 1973. ern Pennsylvania, 1978.
CHAPTER 21

Operation of Steam denerators

u he operation of a multi-million-dollar
steam generator and its associated power-
plant equipment requires the constant ex-
tive an operator must know not only what he or
she is doing but why it is done and what results
from the operator's action.
-
ercise of intuitive reasoning and sound en-
gineering judgment. It is inoperation that all of
the factors that went into the design and con- SAFETY,
struction of the facility are put to the test. A PRIME OPERATING
A principal objective of proper operation is
sustained service between outages while, at the
CONSIDERATION
same time, obtaining the highest possible effi- The prime consideration for all operation is
ciency from all the plant components. the safety of people and equipment. Whenever
Operation of a steam generator is a balance of there is any doubt about an unsafe condition,
inputs to outputs: the better the balance, the the operator must take immediate action to re-
smoother the operation. Producing steam from turn the unit to a known safe condition even if it
a boiler requires that the weight of water enter- means tripping the unit.
ing the boiler equal the steam leaving, and fir- As the loss of a unit even during peak-load
ing the furnace requires a balance of fuel and requirements is not as important as a human
air. To equalize these inputs and outputs, one life or the downtime for a major repair, the two
must understand the system, not just the net- most dangerous conditions remain the same to-
work of hardware that comprises the system. day as throughout the history of steam genera-
This understanding is the principal ingredient tion: the loss of water or the explosive mixture
of successful operation. of fuel and air. Both result from an imbalance:
Too often in recent years, operators have the fist from less water than steam produced,
confused operation with control-system man- even if some of that steam is escaping through a
agement. The operator must realize that a con- tube leak; the second, from too little air for the
trol system is hardware assembled to make fuel present.
operation easier, faster, and safer. All large Safe operation, then, is a result of compre-
steam generators require operators, and the hensive training programs for operators, well-
control of all major functions can be switched designed furnace safeguard systems, and an
from-.automatic to operator control. To be effec- effective preventative-maintenance program.
COMBUSTION
OpenUon of Stem Generators

operation of certain blowers can improve


BASICOPERATINGPRINCIPLES overaUunitoperation.~tcansavevaIuableblaYina -
medium and reduce required maintenance by
In this section, certain basic operating
minimizing the number of blowing cycles.
guidelines for overall effective operation of a To be most effective, a sootblower program
large coal-fired unit are discussed.
requires periodic furnace observations. Based
STEAM TEMPERATURES on such observations and performance results,
selective sootblowing can lead to better steam-
Maintaining desired primary and reheat temperature control and reduce the possibility
steam temperatures requires considerable of troublesome accumulations in the furnace
operator attention. Even the best control sys- and convection passes.
tems do not anticipate all of the factors affect-
ing steam temperature. Despite the equipment BOILER EFFICIENCY
installed for contro.lling superheater and re-
heater steam temperatures, certain conditions An effective operator is constantly striving to
may produce abnormal steam temperatures. obtain maximum efficiency from a unit. To do
For instance, with a new coal-fired unit, it this, he or she must be aware of the effect of all
may be necessary to operate for a considerable operating variables, and the adjustments re-
time before normal furnace seasoning allows quired to maximize efficiency.
the unit to make predicted steam temperatures. Two items within operator control that af-
"Norma1,furnace seasoning" is often defined as fect boiler efficiency are dry-gas loss and
the condition of furnace-wall slag or ash depos- unburned-fuel loss.
its which remains after sootblower operation.
Low steam temperatures may also result from: DRY-GAS LOSS
insufficient excess air Usually the largest factor affecting boiler ef-
higher-than-design feedwater temperature ficiency, dry-gas loss increases with higher
reheater inlet temperature lower than exit-gas temperatures or excess air values.

..
specified Every 35" to 40F increment in exitdgastemper-
an externally fouled superheater or reheater ature will lower boiler efficiency by 1 percent.
leaking desuperheater spray water A 1-percent increase in excess air by itself only
decreases boiler efficiency by 0.05 percent. On
poorly adjusted controls. most boilers, however, increased excess air
On the other hand, high steam temperature leads to higher exit-gas temperature. Con-
may result from: sequently, increases in excess air can have a

..
an "over-seasoned" furnace twofold effect on unit efficiency.
too high an excess-air percentage Usually, coal-fired units are designed to op-
feedwater temperature lower than specified erate with 20 to 30 percent excess air. To oper-
reheater inlet temperature higher than ate a boiler most efficiently, therefore, an
operator must have a reliable means of asses-
specified
sing the quantity of excess air leaving the
irregular ignition or delayed combustion boiler. In-situ oxygen recorders that measure
poorly adjusted control equipment. the oxygen at the boiler or economizer outlet
An operating variable with a very great effect are the best information source. They must,
on steam temperature is the cleanliness of however, be checked daily for proper calibra-
the radiant and convective heating surfaces. t i o n and maintained as necessary. The operator
Although all modern coal-fired steam gener- should maintain the required excess air by mak-
ators are equipped with automatic sootblower ing sure the controls are in the correct mode or
systems, the judicious supplemental manual by manual bias of the fuel-to-air ratio.
COMBUSTION
Operation of Steam Generators

UNBURNED-FUEL LOSS percent at full load. As essentially the same to-


On gas- or oil-fired units unburned-fuel loss tal heat is lost throughout the load range, radia-
should be negligible, whereas unburned loss tion loss increases with decreasing loads.
on coal-fired units can be-appreciable. The Considering only radiation losses, operating
boiler manufacturer will predict unburned- several units at low load may be less economi-
fuel loss and these values can usually be main- cal than taking one off. But other things must
tained with correct operation. There is no easy be considered such as sudden additional load
way to continuously monitor unburned carbon demands and the amount of fuel required to re-
in the ash. Obtaining such values involves the turn the unit to service.
time and manual effort of laboratory analysis of See Chapters 4 and 6 for further discussion of
a flyash sample. The significant point is that the above heat-loss items.
the laboratory feed back the information to the
AIR HEATERS
operators. If values are consistently high, the
. . plant operations department sbould develop a As already noted, lower exit-gas temperature
program to pinpoint what is causing the high is the most positive means for increasing boiler
unburns and how to improve the condition. efficiency. The limiting factor is usually the air
Usually, high unburns can be traced to the heater; for purposes of this discussion, observa-
mixing process of the fuel and air in the fur- tions will be focused on the LjungstromO type
nace. Once the source is found, attention must of regenerative air heater.
be focused on what corrects it. For example, For maximum effectiveness the air heater
one cause of poor mixing of fuel and air could must be kept clean, the baskets must be re-
be inadequate windbox to furnace pressure. If placed when acid corrosion has deteriorated
this is so, monitoring pressure to keep it inline is enough material to affect performance, and the
easier than waiting for the periodic feedback of seals must be adjusted to minimize air and gas
laboratory results. leakage. Proper operation of air heaters re-
There are two other items having an effect on quires certain instrumentation. Pressure-drop
boiler efficiency that an operator can do little indicators across both the air and gas sides
about. These are the moisture-in-fuel and must be available to the operator as well as
hydrogen-in-fuel losses, and the steam- temperature indicators for gas and air, both en-
generator radiation loss. tering and leaving. Pressure drops are the best
MOISTURE LOSS guide on the need to operate the air-heater
sootblowers. Once pluggage progresses too far,
Although the moisture loss of the stack gases
sootblowers will not remove the deposits and
is considerable, the loss comes from fuel mois-
ture and hydrogen, and the moisture in the air, the air heater will have to be removed from ser-
vice for cleaning. (see Chapter 14.)
which are realities not within operator control.
Faulty operation causes most air-heater cor-
The moisture in coal consists of inherent
rosion. The air-heater manufacturer supplies a
moisture and surface moisture. Although at-
chart with recommended average cold-end
tention to the care of coal from the mine to the
temperatures to keep the metal above the dew
coal bunker can minimize the surface-moisture
point corresponding to the sulfur in the fuel.
pickup with resultant increase in boiler effi-
The "average cold-end temperature" is defined
ciency, this is seldom within the boiler
as the arithmetical sum of the temperature of
operator's control. A reduction in exit-gas
the air entering the air heater plus the gas tem-
temperature will decrease the moisture loss as
perature leaving the air heater, divided by two.
well as the dry-gas loss.
Consistent operation below the dew point rap-
RADIATION LOSS idly corrodes air heater baskets. Steam or water
On large, well-insulated steam generators, air heaters or bypass ducts control the cold-end
the efficiency loss due to radiation is about 0.2 temperature. (See Chapter 6.)
COLQmnON
O p t b n of Steam Generatots

High exit-gas temperatures leaving the air operations should inspect the unit exterior. All
heater are often an indication of air bypassing doors should be checked, cleared of tags, and
the air heater. This can be from poorly adjusted then shut. Valves should be correctly po-
seals or excess pulverizer tempering air. Pul- sitioned for start-up in accordance with the
verizer systems for example, are designed to steam-generator manufacturer's valve operat-
dry coal of a specified moisture. If the coal has ing diagram. All areas must be free of debris
less than designed-for moisture or the mills are that will hinder expansion. If repair work was
at partial capacity, mill tempering air will done during the outage, special care must be
bypass the air heater and result in higher exit- taken to assure that no permanent ties were
gas temperatures leaving the air heater. made to the furnace structure which will im-
THE ECONOMIC IMPACT OF OPERATION pair expansion. Account for all personnel.
At this point, safety tags can be removed from
The most effective way to achieve maximum
breakers. As the boiler is filling with treated
boiler efficiency in day,to-day operation is to
water, all vents should be open, as noted on the
embqk upon an education campaign for plant
manufacturer's valve operating diagram. On a
management, supervisory staff, operators and
thermal-circulation unit, the water level
maintenance personnel. If everyone knows the
should be brought to where it just shows near
economic impact of operational variables on
fuel costs, this knowledge can lead to signifi- the bottom of the water glass. On a Controlled
Circulationa unit, the water level should be
cant fuel savings.
Too often campaigns to improve efficiency brought near the top of the gage glass; this will
prevent the water from dropping from sight
are carried out by only one group. Tests are per-
when the first boiler-water circulating pump is
formed to collect data rather than to establish
started. The drainable portions of all steam-
"bogies" for day-to-day operation. The people
circuit headers, connecting links and piping
p,erforming the tests do not communicate the
should be drained through lines free from back
results to the rest of the plant, but rather to the
pressure. Reheater drains and vents are opened
company files. It is important, then, to review
so that residual moisture will be boiled off.
test results with the unit operators and to estab-
lish operating procedures that will take advan- These reheater drains and vents will have to be
closed prior to raising a vacuum in the con-
tage of what is learned from the tests.
Re-starts are expensive. It requires consider- denser.
able fuel to get a unit up to pressure and bring it During warm-up and until the unit is carry-
on line. Extra maintenance and on-line atten- ing load, there will be little or no steam flow
tion that keeps downtime to a minimum can through the superheater and reheater. To pro-
pay off in fuel savings. Retaining heat in the tect the superheater and reheater metals, the
boiler during a weekend shutdown when there temperature of the gas leaving the furnace
is no demand for steam can save fuel. A boiler should be limited to the manufacturer's rec-
can retain a good deal of heat if its isolation ommendation, usually 1000F.The firing rate
dampers are in good condition and are closed must be limited to satisfy this requirement.
Thermal-circulation boilers can be warmed up
tightly. One word of caution-purging re-
quirements both before bottling and prior to at a rate that does not exceed a saturated-steam
light off must be adhered to. The loss of the unit temperature rise of 200F per hour. Controlled
because of an explosion will be infinitely more Circulation boilers have no saturation steam
costly than any heat saving from failing to temperature rise limitation, only the furnace
perform a proper purge. exit-gas limitation previously stated: Most
modern boilers have traversing thermocouples -
START-UP to monitor furnace exit-gas temperature during
FROM COLD CONDITION: GENERAL warm-up; older units may use temporary ther-
Prior to light off of any boiler, a supervisor of mocouple probes for each start-up or have con-
COldBmTION
Operation of Steam Generaton

servatively established firing limitations based START-UP .


on prior testing. FROM COLD CONDITION:
Before light off, the operator should check all DRUM-TYPE UNITS
instrumentation and furnace safety systems. On drum-type units, maintaining drum
Steam-generating units differ too much to be water level is of prime importance. Normally,
able to give detailed start-up procedures. The the operator carries out this function in the
operator must be familiar with all manufac- manual mode until pressure is raised. Before
turer's instructions and the plant operating light off, drum water level should be brought in
procedures. sight. It is best to start firing with a low water
Usually the equipment will start in this se- level because, as the water starts heating, it will
quence. Air heaters and boiler-water circulat- expand. Drum vent valves should be wide open
ing pumps (on positive-circulation units) will so that the air will vent from the drum.
be started first. Next the induced-draft fans, fol- Superheater and reheater should be drained of
lowed immediately by the forced-draft fans. On any condensate wherever possible and then the
most units, furnace draft will be established valves opened or close8 according to the valve
and then transferred'to automatic draft control. operating instructions.
Airflow is raised to at least 30 percent of full For a Controlled Circulation boiler, two of
load airflow, and the unit purged for at least the circulating pumps are started to initiate cir-
five minutes to remove any unburned fuel or culation. To minimize flashing of steam in the
combustible gases. downcomers, additional pumps are not started
During start-up, airflow should be main- until the boiler water reaches 250F.
tained at 30 percent of full load airflow to as- The unit is now fired in accordance with the
sure an air-rich furnace mixture and to prevent established furnace safeguards. During the
any settling out of explosive mixtures. Once warming period, the economizer recirculating
the unit is purged, oil pumps may be started line valves are open. The water will swell as it
and gas or oil trip valves opened. At set inter- is heated and the operator will manually blow
vals, the operator should check the proper down the boiler as required to maintain sight of
functioning of any furnace safeguard system. the water in the gage glass.
Regardless of how much urgency there is for The firing rate will be controlled to keep the
getting the unit returned to service, no inter- furnace exit-gas temperature below the rec-
lock should be jumpered or bypassed. ommended value, usually between 900F and
Never attempt to light off any fuel nozzle 1000F.
without the required ignition-energy source for When drum pressure reaches 25 psig, it can
that nozzle. Any time an operator has doubt be assumed that all air has been purged from
about safe combustion in the furnace, he or she the drum and water circuits. The operator can
should trip the fuel and purge the furnace be- close the drum vent valves. As pressure in-
fore relighting. creases, it is necessary to progressively throttle
As pressure is raised, periodic inspections the superheater drains and vents and to
are necessary to assure that the unit is expand- increase the firing rate as required.
ing as it should. If oil is the warm-up fuel, air- If there is evidence of steaming in the
heater sootblowers should be operated fre- economizer by erratic drum control during
quently to keep the heating surface clear of feeding of water, the operator must be certain
flammable deposits. that the recirculation line is open. On thermal
Once the unit is on line, load may be picked circulation units it may be necessary to feed
up as swiftly as pulverizers can be brought into more water than required to maintain level in
service. The usual restriction in most power sight and to blow down to control water level.
plants is the warm-up and load-rise limitations Start rolling the turbine as soon as the
of the turbine. (See Chapter 7.) minimum permissible start-up pressure and
temperature, specified by the turbine manufac- down) and whether the unit is to be entered.
turer, are reached. When bringing the turbine For a scheduled shutdown, steam pressure
to speed, the firing rate must continue to be can be reduced to the limit of the turbine before
controlled to prevent the furnace exit gas from the unit is taken off line. Thermal circulation
exceeding its temperature limit. Once the tur- units should not exceed a cool-down rate of
bine is synchronized and minimum load estab- 150F per hour of saturated steam temperature
lished, this limit can be removed. The gas decrease. Controlled Circulation units can be
temperature probe is withdrawn and the firing rapidly cooled if the circulating pumps are left
rate increased as required. Usually by this time in service. Normally, the drum vents are
all superheater and reheater vents and drains opened at 2 5 psig and the boiler is not drained
are closed. If drum water level is still under until water temperature is below 200F.
manual control, it should now be placed on au-
tomatic control.

LOAD AND PRESSURE CONTROL: SUPERCRITICAL-PRESSURE


. DRUM-TYPE UNITS BOILERS
Opening or closing the turbine control valves Although much of the discussion of drum-
increases or decreases the load on a drum-type type operation pertains also to supercritical-
unit. Changing the firing rate regulates the pressure boilers, there are some differences.
pressure. In theory, for increasing load the The supercritical boiler needs an even more
operator will open the turbine control valve. If precise balance of inputs to outputs, because it
no other action were taken, the flow to the tur- does not have the flywheel effect that the boiler
bine would increase and the superheater outlet drum affords the subcritical-pressure unit.
pressure would decrease. Upon seeing the out-
let pressure drop, the operator would increase START-UP
the fuel and air inputs. Although the firing system start-up and op-
Because of the increased steam flow, the eration are the same as for a drum-type unit, the
water level in the drum would change. Ini- fluid system start-up is completely different.
tially, the level would rise due to surging. but The supercritical boiler is furnished with an
shortly it would fall rapidly because more integral start-up system. The unit is initially
steam is removed than water enters. fired, warmed up, and brought to partial load
A trained operator will anticipate these inter- on the bypass system.
actions. As the turbine control valve is opened, The Combined CirculationBunit, one type of
the operator will simultaneously increase fuel, supercritical-pressure steam generator, iso-
air and feedwater flow. A well-designed and lates the waterwalls fram the superheater with
executed operational control system will per- boiler throttling (BT) valves (Fig. 1).To gain
form the same as will such a trained operator. good control at low flow, there are boiler
The more experienced and better trained the throttling bypass (BTB) valves around the BT
operator, and the more sophisticated the control valves. For initial warm-up and supply of
system, the higher the expectation that smooth steam to the turbine, the BT and BTB valves are
operation will result. closed. To vent fluid, a separator is installed,
SHUTTING DOWN DRUM-TYPE UNITS external to the boiler, witha line from the wa-
terwall to the separator valved off by a boiler
- Time requirements and procedures for shut- extraction valve (BE). Since it is advantageous
ting dowm a boiler depend on the nature of the to start the turbine with low-pressure steam,
shutdown (normal shutdown to cold, normal steam pressure is reduced through the BE valve
shutdown to hot standby, emergency shut- to the separator. There is a line from the top of
cornusnow
Operationof Steam Generators

the separator to bring the steam to the super-


heater, with a check valve to prevent backflow RECOMMENDED SUPERCRITICAL-UNIT -

during high-load operation. The check valve is START-UP PROCEDURE


referred to as a steam-admission valve (SA). 1. The feed pump establishes a flsw (5 per-
A line to the condenser called a water drain cent of maximum continuous rating)
valve (WD) removes water and controls water through the economizer and the waterwall.
level in the separator tank. The BT and BTB valves are closed. The flow
As the boiler is warming up, steam is pro- is brought through the BE down to the
duced in the separator tank, but very little separator. The flow continues through the
steam goes to the turbine. A line from the top of WD valve to the condenser. The WD main-
the separator tank to the condenser carries the tains level in the separator.
excess steam from the separator. A control 2. The boiler circulating pumps are running
valve called the spillover (SP) regulates sep- to provide protection for the waterwall.
arator pressure during start-up. For detailed 3. The boiler is lit off and gradually the wa-
guidelines on the start-up of supercritical units terwall temperature is raised to the point
see the adjoining box, "Recommended Super- that the turbine can be rolled.
critical Unit Start-Up Procedure." 4. As the temperature of the fluid from the
waterwall rises, steam will be generated in
LOAD CONTROL the separator. Steam will flow through the
The method of controlling the operation of SA valve and through the superheater. This
Combined circulation supercritical boiler dif- excess steam is bled off through the SP
fers from that of a d m - t y p e boiler. The turbine valve to the condenser. The SP controls the
control valves do not regulate the load; rather steam pressure in the separator.
the load is regulated by flow. To raise or reduce 5. When the waterwall reaches the proper
load, the operator varies flow with the boiler temperature, the turbine can be rolled and
feed pump. put on the line using steam from the sep-
arator. The flow is now through the econ-
PRESSURE CONTROL omizer, the BE valve, the separator, the SA
The pressure on a supercritical boiler is con- valve, and out through the superheater.
trolled by the turbine valves, which operate 6. The next step is to raise the waterwall
initially as back-pressure valves. The only temperature high enough to prevent a dip
in steam temperature when the boiler is
transferred to once-through operation.
7. When the waterwall temperature reaches
this point, the flow is transferred from the
BE to the BTB valves. The boiler is now
operating as a once-through boiler and the
separator is no longer in use. The pressure
in the waterwalls is controlled by the BTB
valves.
8. The turbine valves are set for approxi-
mately 30-percent flow. As the load in-
creases, the superheater pressure will
gradually rise until it reaches full throttle
pressure.
9. When the throttle pressure reaches the
design value, the turbine valves are placed
on automatic to control boiler pressure.
Fig. 1. Schematic diagram of a supercritical boiler
--
variable that the turbine valves monitor is the condenser. The water is monitored for iron
throttle pressure, approximately 3500 psig for concentrations with the flushing continuing
most operating supercritical units. In normal until the manufacturer's limits are obtained.
operation (above 30 percent), these valves are
the only boiler pressure control. To raise pres-
sure, the valves close and to decrease pressure PULVERIZER OPERATION
the valves open. Although several types of pulverizers are
STEAM-TEMPERATURE CONTROL used to grind coal for power-plant service, the
majority are of the rotating bowl-type for use in
The superheater outlet temperature on a direct-fired systems. Refer to Chapter 11 for a
supercritical-pressure boiler is controlled with description of this pulverizer.
firing rate, which is increased to raise outlet In op.eration, four areas must be understood
temperature and decreased to lower it. Al- and monitored: lubrication of the gearing and
though this is an effective means of tempera- bearings, airflow, mixture temperature leaving,
ture control, the response time to correct a and product fineness.
temperature deviation is too long for smooth
operation. LUBRICATION
To improve the response, desuperheater
water is injected between superheater stages. With the exception of the roller journals and
The injection water is taken from the econo- exhauster (if so equipped), the mill is com-
mizer inlet at full boiler feedwater temperature pletely lubricated from one system in the worm
so there is no cycle efficiency loss. Although gear housing. The worm-shaft bearings are
the injected water gives fast response, the ulti- flood oiled from a bath of oil in the gear case.
mate temperature control is balancing firing The circulation is either by an external pump-
rate to feedwater rate. ing system or by an internal pump that is a part
The injection water essentially bypasses the of the gearing system. The lubricant must meet
waterwalls and economizer. When the super- the manufacturer's specifications and be non-
heater temperature is high, the operator or con- foaming and noncorrosive (see Fig, 2).
trol system will reduce the firing rate and open Periodic inspection of the gear-housing oil
the spray valves simultaneously until the
temperature returns to the desired level.
Usually, for a Combined Circulation unit,
adjusting the reheater outlet temperature fol-
lows the same procedure as for a drum-type
unit. With a C-E tangentially fired unit, the
process involves tilting the fuel and air noz-
zles and maintaining furnace cleanliness by
sootblowing.
~! CLEANUP
Because a supercritical unit has no steam
drum to separate the impurities in the wa- A -Gear Case Level Gage
terwalls from the essentially pure steam in the -
B Optical Oil Flow Indicator
superheater, a waterwall cleanup procedure C - Oil Supply Header Pressure Gage
D - Oil Supply Header Pressure Switch
must precede each start-up. The procedure in- E - Sump Oil Temperature Thermometer
volves circulating condensate through the I

polisher, feedwater heater train, economizer, Fig. 2. Simplified pulverizer diagram


waterwalls, separator, and drain system back to showing lube-oil system
COMBUSTION
Opemuon of Steam Genemtors

temperature is required. For most of the verizers; or excessive accumulations of pyritic


recommended lubricants, oil temperature is material or coal in the mill base area.
maintained at about 150F. If it is above this Early detection of fires enhances the safety of
temperature, the oil level may be too low; if so, plant personnel. An automatic system is recom-
it should be promptly refilled with oil of the mended. Using visual or other sensory means
same manufacture and type as already in the to detect such fires is arbitrary, slow, and worst
housing. High oil temperature could also result of all, requires the presence of a person in the
from a breakdown of the lubricant or sludging. immediate hazard area. Temperature-detection
If so, change the oil. It could also be because of devices should be used as the primary indicator
scale formation i n the cooling coil, insufficient of a fire in progress.
quantity of cooling water, or temperature of the There are five types of pulverizer fires which
inlet cooling water being too high. are categorized by where in the fuel-preparation
The operator should check the oil in the re- system they occur: feeder fires, above-bowl fires,
turn glass after each mill start-up, and daily for under-bowl fires, exhauster fires, and fuel-
mills in continuous service.. piping fires. Upon detection of a pulverized-
fuel sj~stemfire, the fire-extinguishing system
MILL OPERATION
is operator-activated. A spray of water is
To place a mill in service, start the mill, allow introduced into the system at multiple loca-
it to come up to speed, and bring mill outlet tions; the timing is at the discretion of the oper-
temperature up to recommendations before ator. However, the pulverizer must be kept inert
starting tlie feed of coal. Make sure there is until the water-injection sequence is over.
proper ignition energy adjacent to the fuel noz- When the pulverizer is empty of its contents, it
zles supplied by the mill being put in service. can be shut off and isolated. Water injection
Start the feeder with a fairly high feed rate set- should continue until all evidence of fire has
ting. After the mill begins to grind, reduce the disappeared. Entry for clean-up is allowable
feed rate to the desired amount. The feeder only after the mill and its contents have cooled
drive must be interlocked with the mill motor to ambient temperature. Caution should still be
so that, if the mill power is interrupted, the exercised because smoldering pockets of fuel
feeder will shut down. may be present.
Mill-outlet temperature should be main- Before restart, the entire milling system
tained as high as possible without exceeding should be inspected and cleaned of any accu-
the safe limits of the type of coal ground. This mulations. Check the lubricants in the mill
temperature may be as low as 130F with lig- base and rolls for any evidence of carboniza-
nites and as high as 180F for low-volatile tion. Recheck compression of journal springs
bituminous coals. Low mill-outlet tempera- by means of a hydraulic jack. If everything is
tures often indicate mill overload which is satisfactory,the mill may be returned to service.
usually accompanied by other indications such EXPLOSIONS IN PULVERIZERS
as high motor amperage or high mill differen-
tial pressure. Pulverizer fires occur more often than pulver-
izer explosions; if properly handled, they are
PULVERIZER FIRES
not overly dangerous. If, however, a fire is not
Pulverizer fires can range from nondestruc- brought under control effectively and expedi-
tive to highly destructive, dependent mainly tiously, an explosive condition can occur. Ex-
on how soon the fire is detected and what ac- plosions also can occur without the presence of
tion the operator takes. Basic causes of pul- an obvious fire, if the necessary conditions to
verizer fires are excessive mill temperatures; support an explosion are present.
foreign combustible material such as rags, All explosions are initiated by fires, but fires
paper or wood; settling out of coal in the pul- do not always initiate explosions. Because of
COmDSIlON
Opwrrion of Stwm Generators
--
this difference, there are available indepen- nous coals, which are frequently high in iron
dently designed and operated systems to content, there is a significant difference i n fu-
h a n d l e e a c h condition safely. The C-E sion temperatures measured in reducing
explosion-prevention system uses an automatic (oxygen-starved) and oxidizing (oxygen-rich)
steam-inerting sequence to reduce the potential atmospheres. Subbituminous coals normally
for pulverizer explosions when hazardous oper- contain less iron and exhibit a smaller differ-
ating conditions exist. The system can also ence in melting temperatures produced in
,safely transport the pulverized coal remaining oxidizing and reducing environments. This
in the mill to the furnace, while maintaining an means that, if slagging is a problem with high-
inert atmosphere inside the pulverizer. The iron coals, furnace deposits can be reduced
fire-control system detects fires in operating dramatically by increasing the amount of
pulverizers and alerts control-room operators. excess air. As a rule of thumb, the higher the
The operators can then initiate fire-extinguishing fusion temperature, the drier the slag in the
procedures which include water-spray injec- furnace, and the easier it is to remove.
tion and steam-inerting and transporting. A FUEL FINENESS
combination mill inerting and fire-fighting sys- Slagging conditions often can be improved
tern integrates the into One by proper control of pulverizer fineness and
complete package.' classification. Since coarse coal particles take
longer to burn, they are more prone to produc-
SLAGGING AND FOULING ing slag. High retention on the +50 mesh often
increases slagging tendencies. See Chapter 11
Chapter 3 describes ash characteristics and for a detailed discussion of the fineness rec-
their effect on slagging and fouling. This section ommended for optimum pulverized firing of
will cover what the operator can do to control various ranks of coal.
slagging and fouling. Successfulboiler operation
depends to a significant extent on the ability of SECONDARY-AIR DISTRIBUTION
the operating staff to understand how certain Because several different types of firing sys-
operating variables relate to fuel properties and tems are in use, it is difficult to generalize on
furnace-sizing criteria. Those operating varia- the subject of air distribution in the combustion
bles that influence slagging and fouling are unit zone. Basically,the objective is to provide good
load, excess air, fuel fineness, and secondary-air mixing of fuel and air so that combustion is ef-
distribution. ficient and local zones with reducing atmos-
LOAD pheres are avoided. In units with tangential
firing, for example, slagging sometimes can be
The higher the load, the higher the heat input reduced by increasing secondary airflow to fuel '
to the furnace, and the greater the potential for compartments.
slagging and fouling; therefore, the most direct
OTHER OPERATIONAL MEASURES
way to reduce slagging is to curtail load. But
this is not always possible, because the rated If the coal contains a substantial amount of
output may be necessary to meet electric- ash with a tendency to slag andlor foul heat-
generation or process requirements. Changes transfer surfaces, particular attention must be
in excess air, fuel fineness, and secondary-air given to equipment capable of cleaning the
distribution are less-drastic methods for furnace walls and convection-tube banks. Fail-
minimizing slagging and fouling. ure to remove deposits at the proper time may
result in a chain reaction of deteriorating
EXCESS AIR . . - events. For example, excessive furnace slag-
At high oxidation states, iron compounds in ging results from not using the wall blowers
the ash melt at a higher temperature than at at proper intervals. This condition imposes
lower oxidation states, Therefore, for bitumi- higher gas temperatures in the convection sec-
COMBUSTION
Operation of Steam Generators

tions because of the reduced rate of heat ab- sootblowers. Observation of furnace condi-
- sorption in the furnace. tions at least twice per shift helps eliminate un-
In turn, the higher gas temperature causes expected problems (Fig. 3).
the flyash to become sticky, increasing deposi- For maximum effectiveness, the blowing se-
tion in the convection sections. Depending on quence must be established to favor those sec-
gas temperature and ash properties, the retract- tions of the furnace that foul most easily. Only
able sootblowers may not be able to remove by careful observation can these areas be iden-
these deposits. Ultimately, sections of the con- tified. If some areas of the furnace are par-
vection pass may become plugged. Unless load ticularly prone to fouling, supplemental
is reduced at this point, it may not be possible remote-manual operation of selected blowers
for the induced-draft fans to maintain the can save valuable blowing medium and reduce
proper amount of excess air. This causes addi- system maintenance by minimizing the number
tional slagging, and the cycle repeats. of blowing cycles.
Modern sootblower systems have program- Because the sootblower system is so impor-
ming techniques so proper sequential operation tant for reliable, full-power operation of a coal-
of the blowers-on an automatic basis-can be fired unit, this equipment must be maintained
, established after ash-deposition patterns are in good operating condition. Realize that blow-
verified during preoperational tests. Through ing pressure can change, especially if valve
programming, ash deposits on the furnace travel is used for pressure regulation. Thus, air
walls generally can be held to a minimum, and or steam pressure should be checked frequently
combustion gases cooled sufficiently before with blowers of this type, especially when fur-
they enter the convection pass. nace observation shows a buildup in deposits.
Sootblowers with adjustable orifices are not so
SOOTBLOWER OPERATION
sensitive and will usually retain their settings
A major guideline to reliable sootblower op- indefinitely.
eration is that plant personnel should not wait
until large deposits develop before operating
blowers. Waiting too long between operations FEEDWATERIBOILER WATER
can seriously hamper the effectiveness of
Because internal tube corrosion and deposi-
tion are major causes of costly forced outages,
operators must be continually alert to the
hazard of water neglect. All plants must estab-
lish and adhere to a feedwater and boiler-water
treatment and control for the!: system. Chapter
20 describes the chemistry of water treatment in
detail. Rather, the following section describes
the cautions that must be taken to minimize
corrosion and deposition.
OXYGEN CONTROL
Oxygen control is the most important ele-
ment in feedwater control. Oxygen concentra-
tion in the feedwater must be regulated to
minimize the formation of preboiler corrosion
products which inevitably end up as deposits
on heat-transfer surfaces in the boiler.
Fig. 3. Operators must observe fires, Oxygen levels are more likely to exceed rec-
evaluate slagging, and listen for tube leaks. ommended limits during start-up, shutdown,
and low-load operation. At these times low- CAUSES OF HIGH AND LOW PH
pressure feedwater heaters and related extrac- The primary cause of acidic and caustic
tion piping are often under negative pressure, boiler-water conditions is condenser leakage.
and any leaking valves, pumps or flanges will Raw cooling water that leaks into the con-
provide a path into the system. denser eventually ends up in the boiler water.
Excess oxygen is removed from the system by The water source determines whether the in-
the deaerator, not through chemical additives. leakage is either acid-producing or caustic-
Such deaerators have manufacturer's guaran- producing. Fresh water from lakes and rivers,
tees for levels of oxygen leaving the deaerator. for example, usually provides dissolved solids
Oxygen leaving the deaerator should meet that hydrolize in the boiler-water environment
these guarantees at all times or the manufac- to form a caustic, such as sodium hydroxide. By
turer should be contacted for his recommen- contrast, seawater and water from recirculating
dations to bring it back in line. Adequate steam cooling-water systems with cooling towers
should be available to the deaerator during unit contain dissolved solids that hydrolize to form
start-up so oxygen is purged from the feedwa- acidic compounds.
ter. If adequate auxiliary steam is not available Strict tolerance levels on condenser leakage
because there are no other sources of steam in should be established for all high-pressure
the station, peg the deaerator with steam from boilers. Set a limit of 0.5-ppm (parts per mil-
the boiler drum until turbine extraction steam lion) dissolved solids in the feedwater for nor-
is available. mal operation; allow from 0.5 to 2 ppm for short
To minimize the formation of preboiler cor- periods only. Shut down the steam generator
rosion products, the oxygen concentration in immediately if the surface-condenser leakage
feedwater should be maintained at less than produces more than 2 ppm of dissolved solids
about 5 parts per billion (ppb) during unit op- in the feedwater.
eration. But acceptable feedwater oxygen Another potential source of acidic and caus-
levels during steady-state operation do not tic contaminants is the makeup demineralizer,
necessarily mean that oxygen concentration is where regenerant chemicals such as sulfuric
within safe limits. During various phases of acid and caustic may inadvertently enter the
operation, conditions can exist that may result feedwater system. Chemicals incorrectly ap-
in excessive amounts of oxygen. Thus, use of plied during boiler-water treatment also can be
dissolved-oxygen monitors is important, par- corrosive, as for example sodium hydroxide
ticularly during load swings and start-up oper- used in conjunction with sodium-phosphate
ations. And do not be lulled into a false sense of compounds to treat boiler water. Corrosion can
security if oxygen levels are excessive only for occur if the sodium hydroxide and sodium
a short time. Considerable damage can still phosphate are not added to the water in the
occur, a fact that those responsible for plant proper proportion.
operation must be aware of. Periodically, plant
procedures and controls should be evaluated to IMPORTANCEOF WATER ANALYSIS
ascertain that all sources of oxygen contarnina- A comprehensive water-analysis program
tion have been eliminated. should be maintained to assure that feedwater
and boiler-water chemistry is held within pre-
pH CONTROL scribed limits. Continuous, automatic analyti-
Of equal importance with oxygen is the con- cal instrumentation is preferred. If automatic
trol of boiler-water pH. Small deviations from analyzers are unavailable or are not opera-
the recommended boiler-water limits will re- tional, conduct water tests daily for pH and -
sult in tube corrosion. Large deviations can oxygen in the feedwater and for pH, PO4 and
lead to the destruction of all furnace wall tubes total solids in the boiler-water. A condenser
in a matter of minutes. leak-detection system is of particular impor-
- COMBUSTION
Operationof Steam Qammtom

tame in any high-pressure steam cycle. When 2. Gross flushing to waste to remove the bulk of
installing this type of system on multishell loose material.
condensers, individual analyzers must be pro- 3. Preheating of circulation water to increase
vided for each shell. temperature to 200F. - -
The must remember that many Po- 4. Circulation of alkaline solution at 200F (0.5
tential tube failures can be avoided by continu- percent tri-sodium phosphate, N ~ , P o ~ ) .
ual attention to the control of the water and
5 . Rinse to remove alkaline material.
steam environment throughout the station.
. - solution addition and circulation
6. Wet lav-up
to protect metal surfaces until initial operation.
COMMISSIONING FUNCTIONS Cleaning the preboiler cycle normally re-
Before a new unit can bs put in service, the quires the installation of temporary piping to
entire system must be cleaned to remove oil, establish circulation through the system. It is
grease, siliceous material, mill scale, rust, and also desirable to install temporary piping to
any other debris. The.condensate and feedwa- bypass portions of the system, such as the
ter systems are cleaned before the boiler so that boiler feed pump and deaerator storage tank,
none of the debris or dirt is carried into the which may be damaged by or trap large quanti-
boiler. These two systems are mechanically ties of loose particulate material. Circulation is
cleaned, then given an alkaline flush and some- normally established with a condensate pump
times, an acid wash. which takes suction from the condenser hot-
The economizer and boiler will be given an well, or a special pump of equivalent capacity.
alkaline boilout followed by an acid cleaning. Flow is through the condensate and feedwater
Finally, the superheater, steam piping and systems and is returned to the hot-well through
reheater will be qleaned by a three-phase scav- temporary piping or through the shell side of
enging with steam. It is important that each of heaters. Strainers are placed at the suction of all
these processes be conscientiously undertaken pumps used during cleaning to protect them
and result in as clean a system as is possible. If from suspended particles. The strainers are
not, operating problems are sure to develop checked periodically during the circulation
when the unit goes into service. period and cleaned if necessary.
The condenser, condenser hot-well and dea-
PREBOlLER CYCLE
erator storage tank have to be mechanically
All preboiler systems of high-pressure boil- cleaned to remove loose debris before any
ers must be thoroughly flushed with a hot chemical cleaning -is started. Mechanical
alkaline solution to remove oils, siliceous cleaning will consist of sweeping and hosing
materials and particulate matter which are down all surfaces, and removing all loose mate-
present following fabrication, storage and erec- rial by vacuuming, shoveling, or any other
tion. It is important that these materials be re- convenient means.
moved prior to initial operation; otherwise, A solution containing 5,000 ppm tri-sodium
they will be carried into the boiler. Optimum phosphate (5 lbs Na3P04per1,000 lbs H20)and
plant operating conditions will be realized a detergent are recommended for the hot al-
rapidly after start-up if the preboiler equipment kaline cleaning of the preboiler cycle. The
is satisfactorily cleaned. cleaning is carried out at about 200F. Samples
The condensate system, feedwater system are obtained periodically and tested for silica
and the shell side of all heaters should be in- and oil concentrations. The cleaning is con-
cluded in the alkaline cleaning. This cleaning tinued until the chemical checks indicate no
involves the following basic operations: further increase in the silica and oil concen-
1.Manual cleaning of the condenser, all feed- trations. This process is normally accom-
water heaters and the deaerator storage tanks. plished in 6 to 8 hours.
COY1)USRON
Operation of Steam Generatom

Following the alkaline cleaning, the system ties into the boiler from oil-lubricated equip-
is thoroughly rinsed to remove the alkaline ment and workers' clothing. Every effort should
material, and refilled with condensate of de- be made to minimize the introduction of oil and
mineralized water containing 100 pprn hydra- grease into the boiler because the quantity of
zine for wet lay-up of those systems containing these materials determines the length of clean-
copper alloys. ing and the degree of difficulty in obtaining
In completely copper-free systems (super- clean surfaces.
critical boilers), 200 pprn hydrazine and 10 Sand, loose mill scale and corrosion prod-
pprn ammonia should be added to the water for ucts formed.on the tube surfaces during erec-
wet lay-up. The system should be isolated and tion and following the hydrostatic test are
stored wet under nitrogen until ready for the removed by blowdown during boilout.
next phase of start-up, usually chemical clean- Chemicals Used for Boilout
ing of the boiler.
The chemicals used for boiling out a steam
CHEMICAL CLEANING OF BOILERS generator vary in composition. Generally,
The internal surfaces of a boiler in contact some combination of the following chemical
with water or steam must be kept clean to as- compounds is used during an alkaline boilout:
sure an efficient transfer of heat in the genera- caustic soda, soda ash, sodium phosphate,
tion of steam. Several cleaning procedures are sodium sulfite and sodium nitrate. Sodium
available to assure a removal of foreign matter sulfite reduces oxygen corrosion and sodium
introduced into the boiler during the manufac- nitrate is added to prevent the possibility of
turing process, erection of the equipment and caustic embrittlement. Soda ash and sodium
in operation. The general cleaning processes phosphate are most commonly used because of
are alkaline boilout and acid washing. the ease of handling. Potassium salts can be
Alkaline boilout removes contaminants su'bstituted for the sodium form.
commonly found in a boiler following its shop Organic detergents are added to improve the
assembly or field erection: lubricants, oil, rust, effectiveness of the alkaline boilout. These ma-
sand, metal fragments and assorted debris. terials must be used with care and according to
Acid cleaning removes scales and deposits the supplier's recommendation. Their indis-
formed on internal heat-transfer surfaces in criminate use may lead to foaming and car-
contact with water. This procedure dissolves ryover of chemical to the superheater. The
compounds resulting from contaminants in the temperature stability of the organic detergent
feedwater delivered to the boiler. Acid clean- should be ascertained before use in a boiler.
ing is also used to remave mill scale and corro- The amount of detergent normally used
sion products. ranges from 0.05 to 0.1 percent by volume.
ALKALINE BOILOUT The use of sulfite and,nitrate is a refinement
The basic reason for an alkaline boilout of a in the boilout procedures. Using them has not
boiler is to remove water- and alkali-soluble been shown to be a prime necessity. The prin-
and saponifiable compounds from the water- cipal chemical action is the reaction of the al-
side surfaces of the unit. These compounds kaline chemicals with non-water-soluble oils
may include lubricants used in the erection of and greases. Experience has shown that an effec-
the boiler and, in some instances, protective tive boilout for drum-type boilers can be at-
coatings applied to prevent atmospheric rusting tained by any of the following combinations:
following shop fabrication. 1. Sodaash . 4000 pprn
Most lubricants used in boiler construction Sodium phosphate 4000 ppm
are water soluble and do not offer any difficulty 2. Sodium hydroxide 2000 ppm
in removal during boilout. Non-water-soluble Sodium carbonate or
oils and greases are introduced in small quanti- Sodium phosphate 2000 ppm
COMBUSTION
Operation of Steam Generators

3. Sodium phosphate 5000 ppm recommended for lower-pressure industrial


Caustic soda 500 ppm _ boilers. Excellent results have been obtained in
4. Sodium carbonate 2000 ppm boiling out at a pressure range of a few pounds
Sodium phosphate - 4000 PPm to 100 psig with positive-circulation boilers, in
Caustic soda - 2060 ppm which the ability to circulate is not related to
The first combination is most commonly rec- pressure.
ommended for boilout of high-pressure boilers. The quantity of oil and grease found in a
In some instances, a chemical such as sodium boiler determines the duration of the boilout,
silicate is included in the boilout formula. Al- with boilout periods of 8 to 24 hours being
though this is an effective additive, it is not common. During the pressure-holding period,
recommended for use in high-pressure boilers. boiler-water solids are purged by blowdown at
High silica concentrations have been observed about 4-hour intervals. A chemical balance is
during initial operation when metasilicate was re-established at the end of each purging of
used in the boilout formula. boiler water if the chemical concentration de-
For once-through boilers, the boilout solu- creases to below one-half of the initial value. At
tion is composed of 5,000 to 10,000 ppm of the completion of boilout, the boiler is cooled
sodium phosphate. Other formulations and slowly, drained, flushed free of residues, and
combinations of chemicals can be satisfactorily inspected for cleanliness. If the boilout was un-
employed for boilout, as dictated by local successful and oil and grease are still present,
water-pollution control requirements. Such subsequent acid cleaning of the boiler will be
revised formulations should be reviewed by the ineffective. If an internal inspection still shows
boiler manufacturer prior to use. oil or grease in the drum, the boilout proce-
dures should be repeated.
Bollout Procedure
ACID CLEANING
Preparatory to boiling out, the chemicals to
be added to the boiler should be dissolved As an important part of the commissioning of
completely before introduction into the unit. a new unit, initial acid cleaning is included in
In thermal (natural) circulation units, these this section. But as there will be future needs
chemicals are most suitably introduced into for acid cleaning to remove operational depos-
the boiler by blending them with water as the its, the discussion incorporates both initial
unit is being filled. This insures a homoge- acid cleaning and future acid cleanings.
neous concentration throughout the boiler. In Removal of preoperational and operational
positive (pumped) circulation boilers, the boil- deposits from the internal surfaces of steam-
out chemicals may be pumped into the boiler generator tubing and other components has be-
without concern about proper mixing with the come an increasingly important maintenance
fill water. The boiler-water circulation pumps problem in modern equipment. Because me-
will insure proper mixing. chanical cleaning is virtually impossible in
Gradual heating of the boilout solution in the modern boilers, the effective application of
boiler is accomplished by the use of ignitors chemical-cleaning solvents has become a nec-
and warm-up burners. This assures a more even essary tool of the power-plant operator.
heating of the boiler surfaces. Steam pressure is The primary reasons for boiler chemical
raised to increase the saturation temperature cleaning are to prevent tube failures and to im-
and, thereby, the thermal circulation of the prove unit availability. Tube failures in low-
boiler water; this promotes good mixing of pressure boilers are normally the result of creep
chemicals i n the boiler circuits. The boiler which occurs when internal deposits produce
pressure is raised to about one fifth of the nor- excessive metal temperatures. A much smaller
mal operating pressure, or 300 psig, which ever quantity of deposit will create difficulties in
is lower. A pressure of not less than 100 psig is high-pressure boilers. Caustic corrosion and
hydrogen damage, which only occur in the sequently redeposited in critical areas. Preop-
presence of deposits, can cause tube failures at erational acid cleaning removes the mill scale
temperatures well below the creep limit. De- and serves to remove atmospheric rust which
posits originating both from fabrication and inevitably accumulates during erection.
during operation must be considered potential The type of operational scale found in steam
problems. generators is related to the quality of feedwater
Boiler manufacturers recommend that boil- supplied to the boiler. In industrial boilers, the
.ers operating above 900 psig be acid cleaned principal deposits are calcium and magnesium
prior to initial operation. Also, because of the phosphates, calcium and magnesium silicate,
nature of chemical-recovery-boiler operations, complex silicates as acmite or analcite, quartz,
the recommendation dictates that the lower oxides of iron and copper, and organic matter.
450 and 600 psig units be acid cleaned initially. In utility boilers, the principal deposits are cor-
Mill and Operational Scale rosion products, and iron and copper oxides.
All ofthe pressure parts of a steam generator Chemical Cleaning Procedures . .
may be subjected to heat treatment of some sort
during fabrication or erection-during forming Only experienced personnel with up-to-date
operations, stress relief, welding, or bending. equipment and a detailed procedure to follow
Whenever carbon or low-alloy steels are sub- should perform chemical cleaning operations.
jected to high temperatures in the presence of The procedure should include:
air, oxidation occurs; the oxide produced is 1. The system layout with proper identification
known as mill scale Fig. 4. Mill scale on boiler of all equipment to be used.
tubing is normally very thin with the exception 2. A step-by-step description of the functions
of areas near welds and bends. Even where mill to be performed. These should be specific for
scale is initially uniform, its brittleness upon the solvent used for the cleaning.
cooling can produce flaking. The resulting 3. Precautions to be taken against possible in-
non-uniform surface is undesirable from the advertent contamination of equipment not in-
standpoint of corrosion susceptibility. During cluded in the cleaning system.
operation, mill scale can be readily eroded The boiler operators, cleaning vendor, and
from the steam-generating surfaces and sub- boiler manufacturer must coouerate closelv for
a successful operation. Mutual prior approval
of cleaning procedures and assignment of re-
sponsibility are desirable. Although respective
responsibiIities may vary from job to job, they
can be generally classified as follows:
1. Normally, the cleaning vendor will supply
all of the chemicals and equipment necessary
to deliver the solvent to the boiler at a con-
trolled concentration and temperature. Vendor
personnel will generally operate the equip-
ment and supervise the overall cleaning. They
will perform the necessary chemical analyses
during solvent introduction and monitor the
spent solvent to determine when the cleaning
has been completed.
. .
Fig. 4. Typical mill-scale thickness on tubes in- 2 . Plant p ~ ~ s ~ n must
n e l operate all perma-
stalled in modern high-pressure boilers. Scale nent plant equipment. They are responsible for
thickness illustrated 0.3 mils, at 75X determining metal temperatures and maintain-
COMBUSTION
Operation o f Steam Generaton

ing proper temperatures throughout the clean- a destruction of any inhibitor due to localized
ing period. The owner normally supplies the application of heat. A similar precaution is re-
necessary water and steam and sets up the quired when organic acids are used for clean-
solvent-delivery and waste-disposal systems. ing purposes. The only exception is when an
An important operator responsibility is to as- organic alkaline solvent (e.g.; such as am-
sure that the solvent is not inadvertently intro- monium EDTA) is used for cleaning the boiler.
duced to any other part of the steam plant. The boiler is fired to raise the solvent tempera-
3. The boiler manufacturer has the responsi- ture to approximately 275OF.
bility to provide a boiler that can be cleaned Selection of Cleaning Solvents
safely and effectively. The boiler must be de- Solvents are selected for their ability to re-
signed with an adequate filling, draining, and move boiler deposits. Hydrochloric acid re-
venting capacity. The boiler manufacturer mains the principal solvent used in chemical
should establish a standard cleaning procedure cleaning. Its wide use is largely related to its
for the specific boiler that should emphasize lower cost, its availability, and its versatility. It
the hazards involved and the limitations on the has the ability to remoye most of the various
use of specific components. They should be in- deposits normally encou$ered in boiler tubes
formed of any unusual use of boiler components even in a stagnant condition.
and be ready to review any cleaning procedures Although hydrochloric acid is commonly
that involve unusual steps or solvents. employed for dissolving iron oxide, some or-
The precautions relative to acid cleaning are ganic acids and organic alkaline solvents can
common to all solvents currently used in prac- also effectively perform the same function.
tice. The metal temperature of the boiler is These latter solvents are particularly useful in
raised either by heating water using auxiliary situations where specific circumstances pro-
burners or by circulating water which has been hibit the use of hydrochloric acid. Some of the
increased in temperature by the addition of live solvents which have been developed, exten-
steam. The addition of heat by the use of burn- sively evaluated, and employed in boiler clean-
ers is prohibited when the boiler is filled with ings are (I)ammoniated citric acid (ammonium
inhibited hydrochloric acid. This is to prevent citrate), (2) formic-hydroxyacetic (glycolic)

Table I.Effect of Velocity on Scale Removal of Various Solvents


Solvents and Velocity
Cleaning Conditions Static 0.03 fps 0.1 fps 1 fps 2 fps 3 fps

Hydrochloric acid (5%)


6 hrs, 160-170F

Phosphoric acid (3%)


6 hrs, 212F

Ammonium citrate (3%)


6 hrs, 200-220F

Formic hydroxyacetic acid (3%)


6 hrs, 275-280F

Ammonium EDTA (3%)


6 hrs, 275-300F
NOTE:U = Scale not removed (estimated 20-100% of scale remaining)
C = Scale completely removed [estimated 95-100% of scale removed)
All samples 5-10 mils scale
CO~mnON
Opetattonof S f e m Generators

acid, (3) ammonium EDTA, and (4) sodium quire special attention to assure removal-bf all
EDTA. air pockets and positive flow in all circuits.
In general, the criteria used to select solvents 4. Methods of Disposal-Environmental regu-
include: lations can greatly affect disposal. The costs
1. Materials of Construction-The inhibited and methods of disposing cleaning wastes have
solvent selected must be compatible with the a strong influence in the selection of a solvent.
tube material. For example, hydrochloric acid Tube samples should be taken and given to a
cannot be used to clean superheaters andlor re- chemical cleaning vendor to allow determina-
heaters because of the possibility of stress- tion of the best solvent and cleaning procedure.
corrosion cracking of stainless-steel materials. The thickness, porosity, texture, and composi-
2. Deposit Compositions-Deposit composi- tion of the deposit all may affect individual
tions could include iron oxide, copper, zinc, solvent effectiveness and normal cleaning pro-
nickel, aluminium, silica, as well as solids from cedures may have to be modified. It is also a
condenser cooling water. Large amount's of good practice to remove additional tube sam-
silica in the deposit present problems. Am- ples after the cleaning to verify that the clean-
monium bifluoride i s one additional chemical ing was successful.
(in conjunction with the solvent) used to re- Determining the Need for Chemical Cleaning
move silica-based materials. Copper com- Utility boilers should be cleaned at least once
plexors must be used with hydrochloric acid to every 3 to 5 years. The empirical relationship
avoid copper plating during the cleaning if given in Table I1 correlates the amount of depo-
small amounts of copper are present. If there is sit on a tube with the cleanliness of the boiler.
a large amount of copper in the deposit (greater Tube samples should be taken at yearly inter-
than 10 percent by weight) a multi-step proce- vals from the high-heat-flux areas of the boiler
2 dure will be necessary. Ammonium bromate (for example, several feet above the windbox)
has been shown to be an effective solvent to re- or other areas that have in the past been prone
move deposits with significant amounts of to deposition.
copper. The information obtained from inspecting
3. Geometries-Organic solvents are effective the tube samples, in conjuction with opera-
under dynamic conditions, usually when ve- tional factors, is used to aid in deciding the
locities are greater than 1 ftlsec. The effect of need for cleaning. These factors include the
velocity and circulation on various solvents is number of start-ups, the number of periods
illustrated in Table I. Complex circuits such as with condenser leakage, chemistry deviations,
found in some superheaters and reheaters re- and length of outages.

Table 11. Relationship of Analyzed Deposit Quantity to Uhit Cleanliness


Internal Deposit QuantityLimits*
Boiler Type Clean Moderately Dirty Very Dirty
Surfaces, Surfaces, Surfaces,
mglcm2 mglcm2 mglcm2

Supercritical units Less than 15 15-25 More than 25

Subcritical units Less than 15 15-40 More than 40


(1800 psig and higher) .= -_ -
*All values are as measured on the furnace side of tube samples and include soft and hard deposits.
-
Note: For all practical purposes, 1 mglcm2 = 1 glft2.
COMBUSTION
Operation of Steam Generaton

Chemical cleaning of industrial boilers of acid to prevent the spillage of the solvent to
should also be performed on a periodic basis. this section. Thermal circulation boilers are
The primary purpose for cleaning these units is generally cleaned by the soaking process.
to prevent buildup of deposits to the point Samples are taken periodically t o check the de-
-
where overheating may occur. gree of reaction in the boiler. -
In cases where deposits consist of hardness Boilers are soaked for a period of 4 to 6 hours.
salts, it is imperative to periodically examine The acid is drained by pressurizing with nitro-
tube samples from the unit to establish the need gen. This step is taken to prevent the oxidation
to clean. of cleaned surfaces during this time. Water is
In those units where iron oxide and copper used to displace nitrogen in rinsing the metal
are the main impurities in the feedwater, the in- surfaces of acid. The rinse water is sub-
formation in Fig. 5 can be used as a guide in de- sequently displaced with nitrogen. Two rinses
termining the need to clean. However, good are usually sufficient to attain a pH that is be-
practice would still dictate periodic examina- tween 5 and 6.
tion of tube samples to confirm the analytical The boiler is then filled with water contain-
evaluation. ing soda ash, 1.0 percent solution. The water is
adjusted to the operating level and the temper-
Acid Cleaning Procedure
ature is raised to correspond to a pressure of
In thermal (natural)circulation boilers, no ef- about 100 psig. About 2 hours are required to
fective circulation can be obtained at the low effect neutralization of the acid and passivation
solvent temperature of 150F to 170F. There- of the metal. The boiler is drained and in-
fore, the distribution of acid strength and spected at the conclusion of the wash period.
temperature is obtained by blending concen- Controlled Circulation and Combined Circu-
trated inhibited acid and hot water as the solu- lation boilers can be cleaned efficiently be-
tion is injected into the boiler. Superheaters are cause the circulation pumps can be used to
flooded with condensate prior to the addition equalize acid temperatures and concentrations
throughout the boiler. The acid is circulated in-
termittently with one pump during the clean-
ing, which normally requires 4 to 6 hours.
Organic-type acids are frequently used to
clean once-through boilers. At the conclusion
of such a cleaning, the boiler is rinsed with wa-
Unless lnltlal
3- Condensate Is ter. When the system has then been purged of
Discarded. Assume acid, condensate containing ammonia and hy-
Each Outage
Equ~valentto 3 drogen is circulated to effect neutralization.
Months of Operation
Because of the close proximity of the
I I I I I I superheater to the drum and the potential of '
100 200 300 400 500 600 700 corrosion from the cleaning solvents, particu-
Rated Steam Capacity,1000Lb/Hr
1. Determine Feedwater lron and Copper Concentration Weekly
larly on the austenitic alloys, avoiding con-
2. Assume All lron and Copper Deposit in Boiler tamination of the superheater is important. If
3. Multiply No. Million Pounds of Feedwater by lron
Concentration (ppm) the superheater is known or suspected to be
4. Determine Cleaning Interval from Maximum Permissible
lron (See Note)
contaminated, the cleaning should be tem-
5. Total Copper Level Dictates Chem~calSolvent System
6. Maximum Cleaning Interval Not t o Exceed6 Years
porarily halted and the superheater flushed to
remove the contaminants. The boiler should
never be fired with suspected contaminants in
Fig. 5. Operational chemical cleaning guide for the superheater. For precautions necessary to
industrial-type boilers (based on demineralized or avoid superheater contamination see the box on
evaporated makeup water) the following page.
COYI~STION
Opntion of Steam Genentors

scale on tubing is thin, adherent, and notread-


AVOIDING SUPERHEATER ily eroded by dry steam. Particulate matter and
CONTAMINATION construction debris constitute the major por-
1. The entire cleaning piping layout should tion of the foreign material present in any
be examined to identify all possible areas superheater or reheater at this point in its life.
where any solutions from the boiler could Because solvents do not efficiently dissolve
enter the superheater or reheater. Such con- most particulates, this method of cleaning is
nections should be eliminated so contami- not considered completely satisfactory for
nation of the superheater does not occur. placing a superheater and reheater in condition
Possible leaking valves and Pressure 'eve's for operatiofi. As steam blowing has proven ef-
that might result in backflow must be
avoided.
fective in removing particulate matter, debris,
loose oxide, and atmospheric rust, it is recom-
2. Control and monitoring of drum level is of
mended for any pre-operational cleaning of
paramount importance.
superheaters and reheaters regardless of other
3. Water used to fill or "backflush" the proceduresemployed.
superheater should be demineralized or of
The need to clean a superheater or reheater at
condensate quality.
some point in its operating life by using well-
4. Possibility of re boiler (feedwater train) engineered programs containing solvent tech-
cleaning solutions "hiding-out" in lines, niques or water flushing cannot be overlooked.
manifolds or tanks to be used, in, or inter-
connected to, water fill-lines should be Because of the geometry, superheater and re-
considered before starting preboiler heater cleaning requires special attention. Fre-
cleaning operation. quently, these sections contain nondrainable,
5. Suspicion of warrants a nonventable sections that are difficult to clean
careful assessment of water (or condensate) unless the operator has a clear understanding
quality at appropriate locations in the of flow mechanics.
superheater (e.g., locations nearest point of The problem in cleaning superheater or re-
suspected entry). If evidence of contamina- heater surfaces is to assure that there is positive
tion exists, firing should be discontinued flow through all the parallel circuits. This is
until a judgment can be made as to the seri- necessary for (1) effective cleaning, and (2)
1
ousness of the contamination. If doubt assurance that the solvent can be completely
exists, the prudent course of action is to displaced at completion. This requirement
water-flush (condensate quality) the SUPer- , applies even when simple water washing is
heater and/or reheater. I
employed for removal of soluble salts. Positive
flow can be assured with a relatively low flow
of water if the entire section can be initially
SUPERHEATERIREHEATER filled. When a portion of the loop is nonvent-
CLEANING AND FLUSHING able, the difficulty exists because of trapped air.
Air blockage which develops in nonventable
Although pre-operational cleaning of the areas will prevent effective cleaning and make
steam-generating section in a high-pressure it impossible to completely flush unless special
boiler is strongly recommended, superheater procedures are employed to assure complete
and reheater cleaning is not. The need to elimi- filling. Fig. 6 illustrates the filling problem. A
nate deposit-forming materials is related pri- well-engineered fill-flush program for the in-
marily to their effect on the corrosion problems dividual unit undergoing the cleaning, and the
that are common in waterwalls. We know of no confirming of effective filling prior to cleaning
case where the presence of initial mill scale has solvent injection, are required if desired clean-
contributed to failures in superheaters and re- ing results are to be obtained and damage
heaters or difficulties in turbines. Normal mill prevented.
COYWSRON
Operetlon of Steam Gonemton

POST-ACID-CLEANING ACTIVITIES recommended procedures, with all control sys-


Before the main steam-lines are blown, the tems and protective interlocks functioning.
steam and lower drums should be inspected. The design,fabricationand installation of any
The drums should be flushed of any loose sed- temporary piping system used for the purpose
iment. The internals to the gage glass should be of steam-line blowing, as well as protection
flushed and then blown out. Accessible head- against overpressure or overtemperature, re-
ers should be inspected and flushed with clear quire careful attention by qualified engineers.
water. GENERAL
If the primary and secondary separators were
not placed in the drum, they are installed. On Ideally, to obtain optimum cleaning, the flow
Controlled Circulation units, each orifice and conditions in the system during steam-line
screen is installed in the lower drum. Each blowing should equal those during normal op-
orifice is then checked with a golno-go gage. eration at maximum load. Because it is impos-
Any header handhole caps which were re- sible to exactly duplicate these conditions
moved or not previously welded are welded in when blowing through the piping to atmo-
place. sphere, it is desirable to produce equivalat
Acid cleaning connections are removed or conditions by using lower pressure steam with
valved off, and temporary piping removed. The a flow rate such that the product of steam flow
chemical feed and continuous blowdown pip- times velocity will equal that under normal
ing should be flushed and blown out. When all full-load conditions. The determination of the
work is completed in the upper and lower total obtainable flow quantity must be based on
drums, they must be inspected to ensure that flow resistances in the entire system, including
there is no foreign material remaining. New the temporary piping. Customarily the de-
gaskets should be installed on all drum man- signer of the blowing system makes this deter-
holes before closing. mination. Most high-pressure units obtain
Next, the boiler circulating pumps are pre- satisfactory results with blowing pressure in
pared for operation as called for by the man- the 600- to 800-psig range. The actual steam
ufacturer's instructions.
STEAM-LINE BLOWING
The purpose of blowing the main-steam lines
and the reheat-steam lines before starting up
a new unit is to remove any foreign material
remaining in -tie superheater, reheater and
steam piping after erection is completed. Con-
siderable damage can result if such material en-
ters the turbine during initial operation.
On older units, the need for steam-line blow- Circuit 1 Circuit 2
ing should be considered following major (A) (B)
pressure-parts repairs which introduce the
possibility of foreign material into the system. Fig. 6. Typical schematic of a nondrainable, non-
RESPONSIBILITY ventable superheater section where air blockage
will occur. (A) The air-blocked circuit@) will remain
Because prevention of damage to the turbine stagnant because the unsupported water column H
is the prime concern, the responsibility for de- produces a pressure equal to and opposite to the
termining the effectiveness of the steam-line pressure drop between headers PI and P2. (B) Air
blockage will be eliminated only when the flush rate
blowing operation rests with the turbine man- is such that the pressure drop between the inlet and
ufacturer's representative. During this process outlet headers because of flow exceeds the height
the unit should be operated in accordance with of the unsupported water column H.
--
blow is executed in three phases: main steam,
cold reheat and hot reheat. PRECAUTIONS DURING STEAM-LINE
To prevent foreign material from being BLOWING OPERATION
transported from one section and deposited in
1.The process of steam-line blowing im-
the next, it is important that the system be
poses abnormal and severe conditions upon
blown in sections, each section being blown
the steam generator and steam piping. Large,
separately. Particular care must be taken when rapid temperature changes occur during
blowing the reheater. If the reheater were to be each blowing cycle. This cycling of tempera-
blown immediately in series with the super- ture is far more severe than is incurred in
heater, material too large to pass through the normal operation. Thermal stresses may be
reheater tubes would remain lodged in the re- excessive in the heavy-wall portions of the
heater inlet header and cause blockage of re- system, such as drums, headers and piping.
heater tubes, with resulting overheating and It is prudent to consider this fact when per-
failure of reheater tubing when the unit goes forming the blowing procedure and to limit
into operation. For this reason it is recom- the number of blowing cycles ("blows") to
mended that the temporary piping be arranged the minimum consistent with cleaning the
system.
such that the main steam lines can be blown to
atmosphere first. Similarly, the cold-reheat 2. Firing of all main fuel must be discon-
lines should be blown to atmosphere before tinued during all blows. It is permissible to
keep ignitors andlor warm up guns in service
they are connected to the reheater inlet header.
during the blows in order to speed up rees-
Only after these precautionary measures tablishment of the desired blowing pressure
should steam be admitted to the reheater for after a blow is completed. On Controlled Cir-
blowing through the hot reheat lines. culation boilers, circulating pump(s) must
The temporary piping is often equipped with be kept in service during the entire blowing
shutoff valves which are used as blowing process. If a boiler circulating pump loses
valves. With this arrangement, the superheater suction because of low drum water level, it
and the upstream portion of the temporary pip- must be shut down. If all pumps are stopped
ing are maintained at drum pressure at all times because of loss of suction, the blow must be
when not actually blowing. If the unit is terminated immediately.
equipped with main-steam stop valves, these 3. Since the temporary steam-line blowing
may be used as blowoff valves, if the valve de- piping may be designed for lower pressure
sign permits this type of service. When more than the steam generator, care must be used
than one steam line is provided in any section, to prevent overpressuring this piping during
the entire steam-line blowing operation. The
consideration should be given to arranging the
pressure in the temporary piping should be
temporary piping so that each line may be monitored continuously and the operators
blown separately. In such situations, the pip- should be alert to prevent overpressure.
ing system should be investigated to ensure It is recommended that a means of overpres-
that flow unbalances and expansion stresses at sure protection be provided in the temporary
connections do not become a problem. piping, such as safety valves set at the design
Impact specimens, installed in the blowoff pressure of the temporary piping.
piping during the final blows, give an indica- 4. It is difficult to avoid carryover from the
tion of the cleanliness of the section. Polished steam drum to the superheater during the
square bar stock suitably mounted and sup- steam-line blowing operation. Therefore, to
ported has been used effectively for this pur- avoid deposits of solid materials into the
pose. The degree of pitting of the specimen superheater, boiler w a t e ~should not be
surface following a blow determines the end treated with non-volatile chemicals during
point of the blowing cycle for the particular this process.
section.
COMBUSEN
Operation of Steam Gencrmton

OPERATING PROCEDURES
- The unit is started in the normal manner, fol- BLOWINGTHE MAIN-STEAM LINE-
lowing the cold start-up procedures. All nor- PHASE l
mal recommendations and limitations with The actual blow is started when the unit
respect to pumps, fuel-firing equipment, ash- reaches the specified blowing pressure, usu-
handling equipment, drains, and vents should ally 600 to 800 psig. However, the first blow
be followed, as if the unit were being started for is always at reduced pressure to check out
synchronizing the turbine. Before starting the the temporary piping system and its sup-
first blow in each section, the economizer re- ports and anchors. All main-fuel firing
circulating line valves should be closed. Be- is discontinued. The temporary valve or
cause the steam-blowing operation is the first main-steam valve is opened fully to blow
occasion that the unit is fired at any significant through the superheater, main-steam piping
rate, the start-up as well as the steam-line blow- and the temporary blowoff piping to waste.
ing must be conducted with great care. When the drum pressure drops to about
The unit must be brought up much slower 200 psig, the blowoff valve is closed. The fir-
than during subsequent normal start-ups, while ing rate is increased, and the cycle repeated
as often as necessary until cleaning is satis-
all equipment is checked and expansion move- factory as indicated by inspection of the im-
ments monitored closely. When the unit is pact specimen.
fired, the furnace exit-gas temperature limita-
tion must not be exceeded. BLOWING THE COLD-REHEAT LINE-
During the blows, the drum water level will PHASE ll
be subject to extreme fluctuations. As the tem-
The blowoff piping is now modified with a
porary blowoff valve is opened, the drum water temporary connection from the main-steam
level will rise rapidly and may disappear from piping around the high-pressure turbine to
sight in the gage glass. As the blow progresses, the inlet of the cold-reheat piping. Tempo-
the drum water level will reappear and may rary blowoff piping is installed at the re-
drop out of sight so it is important that the drum heater inlet. Blowing is executed in the same
water level is established at or slightly above manner as the main-steam line, but now the
normal operating level before the start of each blow is through the superheater, main-steam
blow. Feedwater flow must be established as line, cold-reheat line and the temporary
soon as the water level drops back in sight, to blowoff piping to waste. Again, the first
prevent excessive low water level with result- blow is at reduced pressure, with subsequent
ing suction loss of the boiler circulating ones from 600 to 800 psig down to 200 psig
drum pressure. This cycle is also repeated
pumps. After the procedure is completed the
until the impact specimens are satisfactory.
temporary piping is removed, and final piping
connections are made. The unit is now ready BLOWING THE HOT-REHEAT L I N E S
for the next commissioning function-setting PHASE Ill
safety valves.
The temporary blowoff line at the outlet of
SAFETY-VALVESETTING . the cold-reheat piping is removed, and the
cold-reheat piping is permanently con-
All safety valves installed on boilers or other nected to the reheater. A temporary blowoff
pressure vessels should be test-operated before connection is installed at the hot-reheat pip-
the boiler or vessel is placed in service. This ing as close to the turbine as possible and
test should involve a check of the proper func- piped to waste. The same blowing procedure
tioning of the valves as to correct opening pres- is used as in phases I and 11. When the speci-
sure, correct blowdown, proper mechanical men results are satisfactory, the steam blows
operation without chatter, and clean closure can be considered successful.
without leakage.
.-
In checking opening pressure and blow- m i l scale, weld beads, and other such dirt is
down, a calibrated pressure gage must be used common during initial testing. Adequate steam
and the location of its connection on the vessel, blowing prior to popping values will mini-
header, or other component must be such that mize possible damage. Valves mounted on the
the pressure it indicates is a true indication of dead end of headers are particularly prone to
the pressure existing at the safety-valve inlet, this damage. Inspection and manual clean-
both when it opens and when it closes. When
valves are located on headers or steam lines PROCEDURES PRIOR TO SAFETY-VALVE
through which steam is flowing, the test pres- SETTING
sure gage should be connected near the valve to Before firing the unit for setting the valves,
eliminate any effect of pressure drop resulting check the following:
from the flow. In some cases the flow of steam 1. That hydrostatic test plugs have been re-
being relieved through the valve itself could moved from the safety valves. If a problem of
produce a significant pressure drop. scheduling a valve vendor's representative
For high-pressure boilers (above approxi- for removal of hydrostatic test plugs is in-
mately 1200psigoperatingpressure) amanufac- volved, the plug from one valve must be re-
turer's representative should initially test and moved prior to the first fire. All plugs must
adjust safety valves. Certain local codes require be removed before the unit is brought up to
that only licensed people may make adjust- full pressure for the first time.
ments on safety valves. Check with the insur- 2. That there is no physical interference
ance carrier before making any adjustments which would prevent functioning of the
on safety valves. The setting or adjustment of safety valves. Expansion of the unit should
safety valves should be done only by a compe- be considered in this check.
tent person familiar with their construction, 3. That the exhaust stacks from the valves are
operation, and maintenance. A written report firmly supported and restrained and that no
should be made of all testing and adjustment of physical interference which will put exter-
safety valves. This should record the opening nal stresses on the valves exists between
pressure, closing pressure and/or blowdown exhaust stacks and the valves in the cold po-
sition, hot position or in between.
and give an indication of correct functioning of l

the valves as they are left. In addition. it should 4. That the exhaust elbow attached to the
include the name and title of the responsible valve body is not of excessive length in the
horizontal run (maximum recommended-
plant observer and the name and title of any in-
24") which may result in abnormal stresses
surance inspector, or state or local boiler in- being put on the valve body due to the reac-
spector who witnesses the test and adjustment. tion force when the valve is blowing.
The name of the valve vendor's representative
5. That the drain piping from the valve body
making adjustments, if any, should also be in- and drip pans, elbow, etc. is installed and
cluded as well as the nameplate data (serial discharges into a location which will pre-
number, set pressure, blowdown, and valve lo- vent injury to personnel when the valve is
cation) of each valve on the unit. The operating blowing.
company should retain the report as a perma- 6. That, if flexible hoses are used between
nent part of their records. the exhaust elbow and exhaust stack, they be
Before testing safety valves for the first time of sufficient length and installed so that they
on new units, the steam lines will have been do not become "solid" in any position of the
blown to eliminate as much of the foreign valve.
material as possible from the superheater and 7. That all components of the safety valves
reheater and from the connecting piping to are in place and secure, such as manual lift-
prevent damage to the safety valves. Damage to ing gear and adjusting ring pins.
the valve seating surfaces from grit blasting by
COMBUSTION
Operation of Steam Generators

ing of the header by vacuum hose andlor mag- some of the safety-valve spring force so that the
nets through the valve nozzle, with top works valve may be set at lower steam pressures. -
removed, is sometimes necessary. With maxi- This method has also been used widely on
mum attention given to removing debris before reheater safety valves as well as with high-
initial popping of the valve, better success will pressure valves (drum and superheater) on
be obtained with initial valve setting. drum-type boilers. But it must be remembered
Leakage of safety valves in operation usually that this method only tests the popping pres-
results from one or more of the following: sure, not blowdown or the valve action itself.
I. Seating-surface damage The disadvantages of not testing actual blow-
2. Externally imposed stresses on the valve down and the valve operation are outlined in
body which distort the seating surfaces the adjoining box, "Problems Avoided by
Blowdown Testing."
3. Operation at pressure too close to the set
Safety-valve manufacturers indicate that
pressure of the valve. The valve manufacturers
they check each valve with steam for blow-
recommend a minimum difference between
down, and that a cold setting of the blowdown
popping pressure and operating-pressure of 5
rings can be made extremely close if the in-
percent of the popping pressure. With less than
struction manual is followed closely. However,
5 percent difference on a continuous basis,
C-E recommends the hydraulic jack method for
problems with leakage and resulting high valve
supercritical or reheater applications.
maintenance may be expected.
Safety of personnel and prevention of
PROBLEMS AVOIDED
equipment damage should be the prime con- BY BLOWDOWNTESTING
cern when testing and adjusting safety valves. 1.Insufficient blowdown can result i n chat-
Tremendous forces are involved when these ter, which can produce extensive damage to
valves operate. All precautions necessary to the seating surfaces and other valve parts.
contain these forces and prevent accidents 2. Excessive blowdown can result in
must be taken. For the initial popping of each operating problems in getting a valve to
valve all personnel should be kept at a safe dis- close above the normal operating pressure
tance from the valve. A rope should be attached once it pops. The ASME Boiler Code re-
to the manual lifting gear so that an uncontrol- quires that the low-set drum valve shall
lable valve chatter can be prevented from doing have no more than 4 percent blowdown and
serious damage if it should occur. that other drum valves may have longer
Before starting the actual setting, refer to the blowdowns but none shall close lower than
latest section of the ASME Boiler and Pressure 96 percent of the set pressure of the lowest-
Vessel Code applicable to safety valves. set drum valve.
3. The valve could fail to reach full lift be-
HYDRAULIC.-JACK METHOD cause of some mechanical problem. This
FOR SAFETY-VALVE SElTING would not be known and hence its capacity
might be restricted when it was really
The use of a hydraulic jack has made setting needed.
safety valves easier. These jacks can be bought 4. The valve could hang open because of a
or rented from the valve manufacturers. This mechanical problem and bleed the pressure
method was developed originally for setting completely off the boiler during operation.
supercritical pressure valves so that the lift 5 . The exhaust-stack, arrangement would
could be limited to reduce damage to the seat- not be subjected to a full-flow test before the
ing surfaces. unit goes on the line. Serious problems and
The hydraulic-jack system contains a pump, possible damage can result if sizing is in-
hydraulic piston, yoke, turnbuckle and pres- sufficient or the supports are not adequate.
sure gage. The hydraulic piston overcomes
C O ~ O N
Opcrrath of Steam Generstors

START-UP
Cold start-up times are generally 8-12 hours
to full load. In a circulating fluid-bed (CFB)
boiler, this is because of the refractory lining
that is integral to several components, such as
the high-temperature cyclones. The rate of re-
fractory temperature change must be limited to
approximately 100 to 200F/hr to avoid crack-
ing and spalling from thermal shock. In a bub-
bling fluid-bed (BFB) unit, start-up times are
determined either by the refractory-lining con-
siderations or by the time needed to heat the
bed material, which, in a multi-zone bed, re-
quires the transfer of heat frpm a start-up zone
to adjacent zones. Note that the boiler will not
usually delay plant start-up on a cold start, be-
cause steam flow is available for turbine warm-
ing relatively quickly, a n d most turbines
require many hours of thermal soaking.
Before start-up, if the bed had been drained
for maintenance or inspection, a new charge of
bed material is needed. This is usually sand,
Fig. 7. Check each sootblower during spent bed material (from the ash-disposal silo
weekly walk down. or a separate bed-material silo), limestone, or a '
After the unit has been chemically cleaned, mixture of these. Fluidizing airflow is started
steam lines blown and safety valves set, the and the bed is preheated, using overbed and/or
boiler is ready for supplying steam to the underbed burners, to the temperature required
turbine. for fuel admission. Bed temperature is the prin-
One of t h e necessities of effective operation cipal permissive for main-fuel firing; with suf-
is the periodic "walk down" of a steam genera- ficient bed temperature. burners or ignitors are
tor during operation. This requires that the not required to light-off incoming solid, liquid,
operator keep his or her eyes and ears open for or gaseous fuels, as the heat of the bed will en-
unusual conditions and report any findings sure fuel ignition.
(Fig. 7). Potential damage to equipment can be
avoided if abnormal conditions are detected in NORMAL OPERATION
time. T h e operations department should de- In normal operation, a fluidized-bed boiler
velop a checkoff list specific to the station. behaves similarly to other solid-fuel-fired boil-
ers. Firing rate is a function of outlet steam
OPERATION OF pressure; load swings will result in changes in
pressure and, hence, in rates of fuel and air
FLUIDIZED-BED BOILERS flolvs. In a CFB, combustor temperature is regu-
Many operational aspects of fluidized-bed lated by variation in excess air, the primary-air
steam generators are identical to those of other to secondary-air-ratio, total bed inventory, and
solid-fuel-fired units. This- description, there- (with a fluid-bed heat exchanger) solids flow to
fore, will be limited to the major differences in the FBHE. Combustor inventory is set by the
operation between fluid-bed and other solid- rate of bottom-ash flow. Superheat and reheat
fuel boilers. outlet steam temperatures are controlled by de- .
COMBUSTION
Operation of Steam Generators

superheater spray and reheat FBHE solids flow, to generate steam even after fuel flow stops. In a
respectively. In a BFB, bed temperature control - CFB, stored heat in the cyclone refractory con-
is by change in excess air, bed level, and recycle tributes to steam generation; precautions must
rate. As in a CFB, bottom-ash flow determines be taken to prevent damage to backpass steam-
bed inventory. Superheat and reheat steam tem- cooled surfaces from this heat source. Drum
peratures are controlled by spray desuperheat- level should be maintained by slow feed of
ing and by biasing of gas dampers that direct water to the drum following an MFT. If cyclone
gas flow to the reheat side of a split backpass, cooling is not possible in any other way, a small
respectively. steam flow can be induced through the back-
In general, heat distribution is facilitated in a pass by opening a steam vent to cool the back-
fluidized-bed steam generator because the com- pass tubing. Steam-cooled surfaces i n the
bustor temperature (equivalent to the furnace combustor and/or FBHE are protected on loss of
temperatures of stoker-,or PC-fired units) can be steam flow in accordance with the manufac-
more easily regulated. Operation is usually turer's instructions, which may call for depres-
very stable-because of the large thermal-fly- surization or a small cooling-steam flow by
wheel effect of the bed mass; thus, wide varia- means of a steam vent or turbine bypass.
tions in fuel quality can be tolerated. The bed LOSS OF POWER
prevents gas-side transients occasioned by loss
or interruption of fuel flow, thereby improving During a power loss, feedwater flow to the
boiler safety. In most instances, there is no con- boiler stops. As a result, stored heat can evapo-
cern about'furnace-wall slagging, because bed rate significant amounts of the water inventory.
temperatures are held below ash-softening tem- Whether this will damage the boiler depends
peratures to ensure fluidization and to optimize on the specific design. The conservative ap-
sorbent utilization. proach is to provide an emergency feedwater
The importance of maintaining proper fuel pump, which allo~vswater to be fed to the boiler
sizing cannot be overemphasized. Fuel size during a power interruption.
strongly influences bed particle size which, in
TUBE RUPTURE
turn, affects most aspects of boiler perform-
ance. The required fuel sizing and its influence When limestone is used as the sulfur sorbent,
on both design and performance of a FBB are the heated bed material will contain significant
discussed in Chapter 9. amounts of calcined, dehydrated calcium ox-
ide. If this lime comes in contact with sufficient
SHUTDOWNIRESTART
water, such as from a tube leak, it will harden
The shutdown procedure will depend on when allowed to dry, and will make cleanup
whether a hot restart is anticipated. If a hot re- and repair difficult. The leaking water or steam
start is planned, the fuel and air are stopped: may also. damage relatively sensitive refractory
bed temperature can remain above the firing linings. Quick action by the operators can mini-
permissive level for several hours, such that no mize outage duration and reduce the extent of
purge is required on restarting. On a hot restart, cleanup. When a tube leak is detected, it is im-
the unit can be brought back to fill load within portant to maintain fluidization and to drain
a few hours, depending on the bed temperature the bed material as soon as possible. Acoustic
level. If no hot restart is planned, the fuel and steam-leak detectors are an asset for timely de-
air flows are gradually reduced, so that the rate tection of tube leaks.
of refractory temperature change is kept within
the limits of 100 to 200F/hr.
PROBLEMS IN OPERATION
PLANT MAIN-FUEL TRIP (MFT)
In spite of adherence to the general proce-
Stored heat in the bed material will continue dures and observance of the cautions presented
-
CO?dnVrnON
OpetaUmof Stwm Generators

in this chapter, operational problems still oc- temperature of the mixture to the ignition
cur. Tube ruptures can happen from a variety of point. Unburned fuel which causes such fires
reasons. The size and location of the break will can accumulate in the furnace in several ways:
determine what action is necessary. On a at leaky fuel inlet valves on idle windbox com-
drum-type unit, the best method for shutting partments; when the fire is extinguished and
down will be dictated by the ability to maintain the fuel is not shut off promptly; when the fuel
normal water level in the boiler and the need doesn't burn as rapidly as it enters the furnace;
for the boiler in service. or if difficulty occurs in establishing ignition.
If water level can be maintained, the unit can
EXPLOSION PREVENTION
be kept in service until after a peak, or service
may be stretched to a weekend outage. There is, Because most explosions occur during per-
however, the ever-present danger of high- iods of low fuel input, maintaining a min-
pressure water from a break cutting other tubes. imum of 30 percent of full-load airflow is
If the rupture can be visually observed, to ascer- important to insure an air-rich mixture and to
tain that it is blowing out into the furnace and sweep out any accumulation of unburned fuel.
not damaging other tubes, the unit may be able Other preventive measures include
to operate for a long time providing sufficient
treated make-up water is available. 8 Be sure that all liquid or gaseous fuel valves
Unlike a waterwall tubing leak, a leak in a are tightly shut on idle fuel compartments
superheater, reheater, or economizer element Watch the fires closely at low loads and shut
requires greater attention. Because of the phys- off all fuel immediately if proper combustion is
ical arrangement of such surfaces, steam cut- not maintained. Most modern units have flame
ting of adjacent tubes can result in making a scanners to trip the unit automatically when
major repair job out of what might have been a poor ignition occurs. The scanners must be
simple and short one. Economizer ruptures, if properly maintained. They should never be
left unattended, can lead to plugging of the removed from the safety system or their outputs
economizer and air heater, as the water mixing defeated
with the flyash can set similar to concrete. .Always use the required ignition energy
A leak in a waterwall of a supercritical unit source when placing any pulverizer in service
can result in rapid and extensive damage, not
8 During low-load operation keep adjacent
only to the leaking tube, but also to nearby pulverizers in service
tubes. Thermocouples are installed on indi-
vidual outlet tubes and representative inlet Regularly check the proper functioning of
tubes to alert the operator to such leaks. Any any furnace safeguard system
decision to operate a once-through unit with a N e v e r defeat any portion of a safeguard or
known waterwall tube leak must be made with interlock system
the full knowledge of the serious damage that On a unit trip, purge the furnace before shut-
may be incurred. ting off the fans
Empty the pulverizers of all coal before bot-
FURNACE EXPLOSIONS
tling up the unit.
Furnace explosions usually occur during
start-up, shutdown, or low-load operation. UNINTENTIONAL FIRES EXTERNAL
TO THE FURNACE
Generally, they result from the accumulation of
unburned fuel in the furnace because of in- One of the most destructive events in steam-
complete combustion, loss of ignition, or fuel- generator operation is uncontroned ignition of
valve leakage. An explosion occurs when the fuel in an area external to the furnace. Such
proportion of unburned fuel and air is in explo- fires have taken place in air heaters, ductwork,
sive range, and some heat source increases the windboxes, precipitators, hoppers, and fans. In
COMBUSTION
Operation of Stearn Genemtom

the immediate vicinity of the boiler, such fires volatilize as temperature increases, and can ig-
- have occurred when oil is being burned. nite. Once such a fire starts, extinguishing it is
Generally, fires in air heaters, back-end duct- difficult. The metal baskets in an air heater, for
work, precipitator and induced-draft fans take example, will continue to burn even after the
place when a unit is being brought up to load oil is consumed. The only method of putting
after a start-up from cold. With inadequate out such a metal fire is to flood it with as much
fuel-oil atomization andlor poor mixing of the water as possible.
oil with combustion air, unburned oil distil- Combustion Engineering has always rec-
lates will carry to the back of the unit and de- ommended air-atomized light oil or steam-
posit on the relatively cold back-end surfaces. atomized heavy oil for light offs of a cold unit.
Later, when load is raised, these deposits will If mechanical atomization of oil is the only

' TYPICAL OPERATOR WALK-DOWN CHECKLIST


Look for unusual traces of either coal dust, Inspect furnace just above ash pit to make
oil, flyash or water. sure there is no bridging across bottom.
Look for valve and valve packing leaks. Check level of water in ash hopper and
8 Look for any unusual conditions such as
bottom seal trough.
discoloration, hot spots on casing and At the pulverizers-

.
ductwork, or vapor leaking out.
Open all inspection doors and note any
slag accumulations.
a. Check gear-case oil temperature, flow
and level.
b. Check for excessive spillage or malfunc-
Listen for tube leaks in the furnace. (This tion of pyrite system.
is only possible to do on balanced-draft c. Look for any indication of mill fires.

.
units.)
Check for unusual noises, overheating,
and adequate lubrication of all motors and
d. Listen for unusual noise.
e. Check for coal leaks.
At the airheater-
driven equipment.
a. Check the air-heater sootblower to make
8 Look for leaks in gage glasses and water sure that it is not leaking when the control
columns. valve has closed.
Check that no sootblowers are stuck in the b. Check drive motor, support and guide-
unit and that there are no leaks in the bearing lubrication and cooling water.
sootblower lines. c. Inspect cleanliness of air side through
On tilting tangential units, make sure that observation door.
the tilt setting is the same on all corners. .At least once a week, a more extensive
Check the secondary-air damper settings checking should be done such as:
to make sure that all dampers are the same a. Listen for badly leaking safety valves.
on a given elevation.
b. Check the sootblower cycle by walking
At the firing levels, check for coal, fuel oil down the unit as each blower operates to
or gas leaks. See that warm-up guns are re- make sure it is functioning correctly and
tracted. Note any flyash leaks. Report any the packing is tight. Make sure all blowers .
oil spills so that they can be cleaned up be- are blown during a cycle.
fore a fire occurs. c. Put all ignitors and retractable oil guns in
Check with a hand touch all vertical coal service and check to make sure they are
piping for possible plugging or overheat- operating correctly.
ing. A cold pipe on a mill in service is a d. Start and stop any idle equipment to
good indication of plugging. make sure it is ready if needed.
means available, special observation of the fur- keep the problem out of the boiler room by lim-
nace outlet is necessary when firing with a cold iting moisture pickup in the coal yard and re-
furnace. One method of detecting the carryover moving all large debris before the coal arrives at
of distillates involves air-cooled probes at the the bunkers.
furnace outlet which can be periodically ex- Coal usually arrives from the supplier reason-
tracted and examined. ably dry and, if properly stored, will remain
Anytime there is doubt as to the quality of an that way. If a small portion gets wet, it can be
oil fire during a cold light off, the air heater and moved aside for drying and later use. On the
other back-end surfaces should be examined. If other hand, to minimize fugitive dust, coal is
oily deposits are found, all firing should cease sometimes wetted before shipment from the
until the surfaces can be thoroughly cleaned mine. Additional moisture pickup during trans-
with a hot detergent solution. port can result from leaky barges or rain. Sta-
Uncontrolled ignition occurring around the tions receiving coal with a substantial moisture
windbox area, external to the unit, usually re- increase from mine to plant should consult
sults from oil spills when guns are removed or with the producer and the shipper to see if im-
- when valves or gaskets are permitted to leak. provements are possible.
Therefore, oil spills should be cleaned and
leaky oil valves or gaskets should be corrected
immediately. Any plant which tolerates ac- GUIDELINES ON COAL PILING
cumulation of spilled oil around the burner AND RECLAIMING
area is in danger of a serious destructive fire.
rn Compact the coal; loose coal picks up
moisture and encourages fires in the coal
pile.
COAL HANDLING
Pile the coal for maximum run-off of rain;
IN POWER PLANTS piles should be rounded or pyramid-
Improved coal storage and methods of load- shaped, with the steepest slopes possible.
ing bunkers can often result in substantial sav- Keep the coal pile free of valleys and
ings in power-plant operations. Continuous pockets; water will collect in them and
production of steam requires steady flow of coal sink down into the coal.
from the bunkers. Interruption of coal feed to Reclaim deep into the pile, not along wide
the furnace not only causes loss of production, areas of the top. When properly piled and
but can also lead to furnace explosions. compacted, only the top layers will be high
Perhaps the greatest factor impeding continu: in moisture. This top layer can be re-
ous coal flow is excessive moisture. Coals con- claimed during drier spells.
taining clays pack easily when moisture As coal is removed, rework the pile to fill in
content increases; the packing can occur in the reclaimed area and to eliminate gul-
leys, pockets, and rivulets.
bunkers, feeders, or pulverizers. In addition,
foreign materials such as rocks, metal, slate, During reclaiming, do not push coal onto
wood, and other debris in the coal can block or any water deposits or muddy coal in the
stall mill or stoker feeders. area of the coal conveyor belt.
Some plant operators learn to live with the Minimize fine coal, as it absorbs water
problems associated with wet coal and foreign more readily than coarse coal. Wet, fine
coal does not flow easily; it will stick to
material by fighting stoppages inside the pow-
bunkers and feed pipes. Coarse particles
erhouse with vibrators, manual sledge ham- will help to eliminate bunker plugging
mers, poke rods, sluice systems, air cannons, and keep the coal moving.
heaters, or coolers. These methods do not stop
plugging; they only free plugs. Other operators
- COMBUSTION
Operationof Steam Generators

COAL-YARD DESIGN AND MANAGEMENT clude responsibility for the continuous feed of --
fuel to the mills. In any case, the supervisor
Good coal yards should be carefully planned. should be informed of all coal hang-ups.2- -
Proper drainage is a must. The yard should be
properly graded, and all mcks, wood, and
metal removed. A base layer of coal, to a mini- OPERATOR TRAINING
mum depth of 2 feet, should be spread; this A well-trained operations crew means max-
base should never be reclaimed, and should not imum plant availability and optimum unit effi-
be included in the stockpile records, even for ciency. Such a crew is developed by a carefully
emergency use. The coal yard should be fenced designed training program which should be a
or otherwise isolated from material storage, step-by-step learning process. First, there must
scrap, or trash; only coal and equipment be an understanding of the fundamentals and
needed to handle it should be allowed in the principles involved. The individual equip-
area. Workers should be encouraged to look for ment components and subsystems that com-
foreign material in the yard and to hand-remove prise the unit must be taught in detail. And, fi-
it; the screens should not be depended on to re- nally, overall generating-unit operation must
, move all debris. be discussed fully.
Avoid crushing coal until it is ready to enter To be effective, a program should be ver-
the bunkers. Wait until immediately before the satile; new operators as well as more experi-
boiler is ready to burn coal before filling bun- enced personnel should be able to benefit from
kers. There is a tendency in new plants to fill it. Flexibility is important too; a program that
the bunkers as soon as the coal-handling system can be used individually or in classroom situa-
is ready; this is understandable, since start-up tions has a distinct advantage. Programs geared
personnel want as much of the equipment to be to specific equipment should be accurate and to
operational and ready as possible. However, the point. See Figs. 8 and 9.
coal will gradually pack in bunkers and will
not flow easily when needed. Also, coal stored THE SYSTEMS APPROACH
in bunkers or silos for long periods can ignite
and smolder. Finally, during initial operation, A well-planned operator-training program
fill only those bunkers that feed the pulverizers looks at the energy supply system as a "sys-
required first. tem," not just as a network of hardware. Part of
In preparation for a scheduled long-term out- that system is the people who manage, operate,
age, all bunkers should be emptied, and should and repair the network of hardware and
not be refilled until the unit is ready for restart- equipment for the owner. -
ing. If a unit has an unscheduled shutdown and Many operating cost variables can be con-
it becomes apparent that it will be off line for trolled by plant operating personnel through-
some time, serious consideration should be out the useful life of the facility. Good
given to emptying the bunkers, especially if the operating techniques, for example, extend
coal moisture content is high. Temporary wearing-part cycles. Fuel usage also depends
chutes to trucks can be provided in some upon operating technique, as does effective
plants, and the coal can be returned to the stock preventive maintenance.
pile. If major maintenance is to be done on a The question of operating-personnel quality
single pulverizer, its bunker should be run is of great concern today, because of the in-
empty before removal for service. crease in unit size, complexity, and automa-
It is important that the coal-yard supervisor tion. The trend is for fewer personnel to be in-
become familiar with the needs of the boiler volved in responsible operation of fossil power
operators, so that his or her responsibility is plants.
more than just filling the bunkers; it should in- The elements necessary to establish a suc-
C0YI)USIION ,.
Opcndion of Steam Generators

Fig. 8. Part of operator training includes classroom designed to meet these requirements. System-
presentations covering fundamentals of system atic verification of training program effective-
equipment and unit operation. A well-planned ness is vital. Experience has taught that, if the
operator training program looks at the energy sup-
ply system as a "system," not just as a network of above elements have been successfully
hardware and equipment joined together. applied, it is reasonable to expect demonstra-
tion of student operating competence and a
high level of student retention of new knowl-
edge and skills.
A prerequisite to a successful program is a
cooperative understanding of the objectives
and program goals. This is generally accom-
plished by giving presentations outlining the
program goals and methods to station man-
agement personnel and officials of the produc-
tion and maintenance unions. C-E's experience
is that these presentations have resulted in ex-
cellent dissemination of program information,
a high degree of interest, and active participa-
tion and cooperation at all levels of plant peo-
ple. The inclusion of union management has
achieved the same resultant support and coop-
eration and helps to assure cooperation and
support for subsequent training activities.
THE NEEDS ANALYSIS
The training requirements analysis is gener-
ally based upon data gathered from question-
naires provided to all operating personnel and
from a survey of the power station. The survey
includes a review of plant configuration, tech-
nical documentation, operating procedures
and directives, operator job requirements, and,
where applicable, review of licensing require-
ments. These data are analyzed by educational
psychologists and training specialists who
then prepare a population description of the
average student, identify job-knowledge re-
Fig. 9. Experiencedtraining specialists provide on- quirements and performance objectives, and
the-job training, an essential part of any com- identify motivational factors to be considered
prehensivetraining program. - in training systems design.
The availability of operators for training,
cessful systems training program include pre- with the exception of a new station starting up,
requisite conditions such as knowledge of the represents a significant factor to be considered
system, what it is, how it works, who uses it, in a training system design. The complexi-
and what it is for. This is followed by a needs ties of current manning levels, rotating shift
analysis that tailors the program to the specific schedules, and overtime opportunities com-
requirements of the system and the student plicate the arrangement of an effective training
population. Then tlie training program must be schedule.
COMBUSTION
Operation o f t e a r n o en era tors

Performance measurement criteria applied Fig. 10 Simulators provide a highly effective dem-
to training design are: onstration of plant operational concepts and the
application of problem solving logic to determine
8 Evaluate the effectiveness of instruction and corrective action to be taken when equip-
course material .- - . ment malfunctions.
Evaluate the level of each student's achieve-
ment and provide necessary additional assis-
tance if required
8 Review and reemphasize important areas of
course material
Establish procedures for scoring individual
students to avoid possible union conflicts

THE ROLE
OF THE POWER-PLANT SIMULATOR
Training material, equipment, and facility
requirements necessary to support the training
program should be specified in the design of
the program. Of great value to any operator
training program is a power-plant simulator de-
signed to demonstrate the concept of a total op-
erating plant.
Simulators allow dynamic demonstrations of
overall power-plant systems operation; auto-
matic combustion control system operation;
turbinelgenerator control system operation; and
operation of feedwater and fuel control systems.
Practice exercises can be provided through the
insertion of selected malfunctions and load var-
iations to improve operator ability to diagnose
abnormal conditions and initiate corrective
action. The application of simulators to the
training program is always in the context of spe-
cific power-plant operating procedures and as a
reinforcement of the training material being
taught at the time, Fig. 10.
OTHER SUPPORT MATERIALS
An audiovisual training program is also very
effective. Fig. 11. It combines sight and sound
which greatly increases retention. Such a pro-
gram can be used throughout the life of the unit
for retraining operators and initial training of
replacement operators.
COMPLETENESS Fig. 11 The equipment used with an audiovisual
training program is portable and easy to operate;
The training Program design is complete at any time operators can use it individually for
when the following components have been ac- plant system reviews.
COMBrnON
Opetation of Steam Genetaton

counted for: curriculum, lesson plans, training tent, length of lessons, emphasis, and overall
aids, note-taking guides, simulator, study time schedules and objectives. Validation is
texts, quizzes, tests, practical exercises (plant accomplished by administration of pretests at
walk down and simulator operation), and the course start to establish operator entry knowl-
teaching team has . demonstrated practice- edge, and post-tests at course completion to
teaching exercises. measure gain in knowledge. Evaluation of
PROGRAM VALIDATION
training effectiveness through course audit by
technical specialists, analysis of test results,
The next step in the process is to provide for and review of student course critiques are addi-
program validation. In general, an initial tional validation measures. Course material
course instruction is provided to a "pilot" should be revised as necessary based on the re-
class. This is to validate training course con- sults of validation measures.

- - - - -- - - - --

REFERENCES "Installation and Operation of Pulverized Fuel Systems,"


I S.E. ~ ~ i ~ R.E t ~~ i k ~ "coal
k ~pulverizer
~ , ti^^ NFPA 85F. National Fire Protection Association. Inc.;
and Fire Fighting System;" Windsor. CT:Combustion En- Q u i n c ~MA*latest
gineering. Inc.. publication TIS-8256. 'George Thimot, "Want Better Coal Firing? Improve Coal
"Explosion Prevention Systems:' NFPA 69, National Fire Handling:' Electrical World, August 1, 1972. New York,
Protection Association, Inc.; Quincy, MA, latest edition. NY:McGraw-Hill, Inc., 1972.
CHAPTER 22

Performance Testing of Steam Generators

n the modern power plant, measurements are dures and instruments are used and to try to
made for several reasons: change them if they can find better methods or
to monitor such phases of power-plant opera- equipment. Most importantly, engineers must
tion as input and outlet flows, inlet and outlet become skillful in interpreting test results and
water and steam temperatures, and power con- in drawing appropriate conclusions.
sumption of auxiliaries
to test individual equipment or systems for
initial acceptance POWER-PLANTTESTING
to verify compliance with federal, state, and AND MEASUREMENT
local requirements regulating plant emissions CHARACTERISTICS
to check following a period of
operation. Power-plant testing differs in one important
This chapter concerns the latter types of meas- respect from product quality control, to which
urement, many of which are governed by the it is sometimes compared: most tests fall into
ASME Performance Test Codes' and the U.S. the single-sample category. Unlike the repeti-
tive tests made of product dimensions, most
Environmental Protection Agency Code of Fed-
power-plant tests consist, for example, of indi-
eral Regulations2. Supplemented by additional
vidual readings taken over a period of time dur-
tests of special character, the ASME Perform-
ing which some unwanted variations may be
ance Test Codes are of considerable interest to
introduced. Some well-equipped laboratories
manufacturers and users of power equipment,
and the results of such tests aid i n the evalua-
may have boilers that can be rigorously tested.
But, in general, most large-scale power-plant
tion and improvement of designs.
tests cannot be repeated a sufficient number of
Engineers participating in power-plant test-
times to gain the statistical reliability expected
ing must become aware of the nature of experi-
for quality control. Furthermore, the cost of
mental error, learn how a single error may
conducting certain full-scale tests can be in the
influence the results calculated from multiple
hundreds of thousands of dollars.
measurements, and -gain some knowledge - of
the effect of instrument selection in minimizing ANALYSES
measurement uncertainty. For best results, they
must be willing to question why certain proce- When tests are costly in terms of staffing,
--
COMBUSTION
Pertormmce Testingof Steam Generators

time, and equipment, the uncertainty analyses as a design tool.


made in advance help establish procedures and Tests and measurements, as indicated earlier,
manpower assignments. They can also help de- require a great deal of engineering thought.
termine how uncertainties propagate into the Their value is greater if engineers are willing to
results. In their pioneering article on this sub- ask searching questions and make all possible
ject, "Describing Uncertainties in Single- analyses before testing is begun. Finally, skill
Sample Experiments,"3 S. J. Kline and F.A. in reporting test results is crucial, particularly
McClintock show that a given reduction in a in the interpretation of what was observed. Im-
large uncertainty is far more important that the portant advances in engineering and science
same numerical reduction in a small uncer- have resulted from skepticism of "obvious"
tainty. This technique also guides selection of results and perception of new factors that previ-
appropriate measuring instruments prior to the ously went unnoticed.
start of experimental work. But consideration
must also be given to adequate cross checks
while the experiment is being conducted.4 ' . STEAM-GENERATOR TESTING
ADVANCE PLANNING OF FIELD TESTS
When applied to boiler study, testing ac-
Advance planning of field tests is becom- tivities range from daily performance observa-
ing increasingly important. Under some cir- tions using station supervisory instruments to
cumstances, it is possible to set forth a fixed unusual conditions with specialized measur-
objective for overall accuracy and plan in- ing apparatus. In this latitude, the scope of any
strumentation accordingly. single test and the measurement techniques
More often, however, field tests are per- used depend upon the kind of testing informa-
formed under less than ideal conditions, so the tion being sought.
engineer must be capable of making a judicious Since individual phases of a design prob-
selection of existing and special measuring lem may range from a completely scientific
instruments. If the objectives and desired end solution with exact relationships between var-
results are well defined, some of the plant iables to empirical approaches with variables
control-panel instrumentation may be used, only generally related, test work for design in-
perhaps jointly with special calibration or by formation is intended either to determine
checking against standard sources. magnitudes and limits of these variables or to
Large sums of money may be spent in devis- establish their cause-and-effect relationships.
ing special measuring equipment for a particu- Although a research laboratory can supply ex-
lar part of a test, but these expenditures may perimental information for basic investigations
be largely wast6d if supporting measurements and observe behavior in many types of models,
are substantially less precise. Minimally there- testing on full-scale units is vitally necessary to
fore, the engineer should be familiar with the verify data thus obtained. Although tests of
main sources of error and their effect upon the small industrial boilers may actually be carried
results of the test performed.3 out in a laboratory, for large utility-type boilers
By making an error analysis in advance of the power plant itself becomes the testing labo-
conducting tests, engineers can determine the ratory. In some cases where unusual fuels are
crucial points of measurement and select the being studied, large quantities of that fuel may
instruments accordingly.5 They can also predict be shipped long distances so that tests con-
effects of propagation of errors on calculated ducted in a boiler will have the desired firing-
results and obtain a much greater overall con- equipment and design characteristics.
sistency in testing activities. In test reports, the Although emphasis is on the testing of large
combination of an error analysis with interpre- central-station boilers, many of the measuring
tation of results adds to the usefulness of tests techniques are equally applicable to smaller
COMBUSTION
Performance Testing of Steam Generatom

units installed in marine, industrial, and in- older and smaller equipment. consequently, in -
stitutional power plants. the past, new unit design emphasized steady-
state operating characteristics. In recent years,
OPERATIONALTESTING however, the relationship between .required
After a design has been completed and a short-term peak capability and off-peak ca-
boiler erected, the initial operating period pro- pacity has changed. Because peak load has
vides the first opportunity to determine out-distanced off-peak load growth, there is in-
whether it meets performance guarantees. creasing interest in transient characteristics of
Handled as a normal function of a technical- the largest and most modern units. Many will,
service organization, this acceptance workmay at times, operate at reduced load, and may even
include such items as determination of unit ca- be shut down for weekends and other periods
pacity, steam-temperature control range, draft of low electrical demands.
losses and pressure drops, and overall effi- Constant-load testing is needed for evalua-
ciency. If deficiencies exist, some additional tion of unit heat absorption, heat-transfer
testing may be necessary to guide corrective ac- parameters, unit efficiency, and heat rates.
tion to meet contractual performance. Transient testing is required for controls-
When a unit in a central station goes into response study and adjustment, and in con-
commercial operation, it becomes an inte- nection with quick start-up and shutdown
grated part of a system. It is normal utility procedures.
practice to determine the unit heat-rate charac- TESTING MEASUREMENTS
teristics at this time and periodically later. In
these days of high costs, optimum system effi- Steam-generator design and operation re-
ciency is important, and information from volve about three basic premises, any one or all
these incremental-10,ad cost studies on each of which may be involved in a test program:
unit provides the basis for determining daily heat liberation
load distribution among system plants. heat absorption
In some central stations, a control-room mechanical means to accomplish heat libera-
data-logging computer calculates heat-rate in- tion and absorption.
formation almost instantaneously. Not only
does such rapid information availability per- HEAT LIBERATION
mit more detailed analysis of performance, it Heat liberation results from combustion of a
also supports decision-making for optimal unit fuel with oxygen in the air. This implies testing
operation under such conditions as extreme to obtain knotvledge of fuel properties and com-
low loads or loss of a feedwater heater. bustion characteristics; it leads to establishing
In addition to evaluating performance and the theoretical fuel-air-products relationships
results, operational testing covers the more de- from fuel analysis and combining equations
tailed aspects of routine operation such as and from the actual combustion requirements
start-up procedures, adjustment and mainte- in an operating furnace. Together with the com-
nance of unit control systems, and safedimit bustion efficiency, such things as pulverizer (or
monitoring of operating variables. other fuel-burning equipment) power and ca-
DETERMINING TEST CONDITIONS pacity requirements, ignition stability, and ash
deposits must be evaluated. Testing for heat lib-
The test objective governs the test condition eration requires considerable attention to fuel
which can be at either constant or transient and flue-gas sampling to obtain representative
load. Historically, the role of the newer, larger data.
units in utility-system steam plants has been
HEAT ABSORPTION
one of base loading at design rating, with sys-
tem load fluctuations being taken care of by the Heat absorbed by unit components reduces
COmVSIlON
PerfommcaTesting of Steam Generators

the flue-gas heat level. The reduction can be de- suitable for test purposes, between the coal-
termined from gas-temperature measurements storage silos and the pulverizers. These scales
and specific-heat data. Similarly, the unrecov- or feeders must be calibrated before and after
ered heat quantity entering the stack is a loss tests, in accordance with PTC 19.5, Measure-
and must be determined. Solid and gaseous ment of Quantity of Materials, Chapter 1.
stack emissions are other factors receiving con-
METHODSOF MEASURING FUEL FLOW
siderable attention because of flyash disposal
'problems and air-quality considerations. To For general test purposes, fuel oils are me-
size fans and exhausters adequately, system re- tered with volumetric instruments of the dis-
sistance appearing as pressure and draft losses placement rotating-disc type. Heavy grades of
must be known. In summary, these are the most oil must be heated for proper atomization in
common areas of test work in the fuel-air cycle. burners, and where moderate accuracy is satis-
For a successful design, heating surface must factory, the resultant viscosities permit use of
be properly allocated among furnace, super- such meters even with these oils. On the other
heater, reheater, economizer, and air heater in hand, if flow error of less than 4 percent is
order to achieve the desired heat absorption and required; meter calibration is necessary using
yield the expected relationships of capacity and the intended oil at operating temperature and
steam temperature. Since in modern boilers the with a similar piping arrangement. The foam-
furnace represents the most important part of ing tendency and volatilization of some oils
the evaporative surface, its performance is a key may prevent their accurate metering by this
factor. The furnace must be sized to be capable method.
of maximum design evaporation yet provide Using level change in large uncalibrated
flue gas at the temperature level necessary to storage tanks as a flow index is at best an ap-
superheat and reheat the steam to a desired proximate method. For efficiency tests, weigh
level over the operating range. Because of the tanks are the most accurate means of direct
series-type processes involved, miscalculation measurement, but their use is generally re-
at any point will upset performance in all the garded as impractical with large flow rates.
other sections. Their cost also prohibits widespread use.
TESTING OF MECHANICAL EQUIPMENT
For gaseous fuels, orifice-flow measurement
is most common. It gives highly accurate re-
High availability and low maintenance costs sults if the actual installation has sufficient ap-
are prime requirements for steam-generating proach straight lengths and if it conforms to
equipment. Therefore, materials have to be design of pressure taps and orifice-pipe size
selected for long-life operation at elevated relationships .6
temI;kratures and pressures. Since in-ser-
vice pressure parts and structural-mechan- TECHNIQUES FOR FUEL SAMPLING
ical equipment are subjected to erosion, In arriving at a representative sample, the in-
abrasion, expansion, and vibration, their de- homogeneity of most fuels requires careful at-
sign requires knowledge of the magnitudes and tention to sampling techniques. Accepted
character of these factors. Only field and lab- standard practices may be found in the latest
oratory experience will yield this information. revisions of ASTM Standards D 2013, Prepar-
ing Coal Samples for Analysis and D 2234, Col-
MEASUREMENTS RELATED lection of a Gross Sample of Coal.
TO HEAT LIBERATION
In general, solid-fuel sampling procedures
Fuel-flow measurement depends upon the involve collecting small increments at regular
fuel state and the desired accuracy. Solid fuels, intervals over the test period, and reducing
such as coke and coal, can be measured by their aggregate to obtain laboratory-size sam-
scales. Many plants have gravimetric feeders, ples by successive quartering or riffling. For
COMBVSTION
Performance Testing 01 Steam Generators

some coals, intermediate steps include crush- pressure in the steam generator, the high heat
ing to definite screen sizes and mixing. value at constant volume as determined in the
Since surface moisture of coal may vary con- bomb-calorimeter must, therefore, be convert-
siderably, separate samples are tagen and ed to a constant-pressure high heat value.
sealed immediately for moisture-only deter- Throughout the Codes, this high heat value for
minations when high test accuracy is required. constant pressure combustion is referred to as
This practice is mandatory for efficiency tests the high heat value. (When testing by the input-
and desirable for any high-moisture fuel tests output method, only the high heat value and
because the normal handling in aggregate re- the moisture content of the fuel are required.)
duction can produce significant moisture loss Generally, fuel sizing refers to crusher-
of the sample. Aggregate analysis is then ad- prepared coal sizing measured with screens of
justed for the average special moisture value to %-inch opening and larger, and is of impor-
arrive at the as-fired an'alysis. The need for such tance mainly for fuel-bed distribution prob-
care is readily apparent in weighed-coal tests lems in stoker firing. Coal fineness usually
when the heat input is directly affected by such means suspension-burning sizes and, for pul-
moisture loss. verized coal, involves sieving of 50- to 200-
Sampling of other solid fuels such as wood mesh (openings per inch) particle sizes. In both
and bark should be made with similar care to cases, a series of screen sizes is used, with the
avoid moisture loss. fractions retained or passed by each size being
With most pumped-liquid and gaseous fuels, reported. Knowledge of the size consist or
the problem is one of possible overall change overall fraction relationship rather than just
during the test period rather than inho- one size is required. For example, in pulver-
mogeneity at any instant. Thus, sampling at ized-coal firing, combustion efficiency (carbon
a single point with fixed extraction rate for the loss) can be more affected by larger size consist,
entire test period should be adequate except whereas grinding power is more closely related
where known stratification exists as in waste to the finer size percentages.
fuel ducts or in residual fuel lines. Another physical property related to pulver-
izer performance is ease of grinding,or grind-
ANALYZING FUEL CHARACTERISTICS
ability index. This is determined from the
In its broadest sense, fuel analysis refers to amount of power required to pulverize a pre-
determination of all physical and chemical pared sample of the test coal in the laboratory.
properties of a fuel. The results are then compared with a standard
Solid Fuels
sample. In the Hardgrove method, the standard
is 100, with decreasing numbers indicating
The basic type of chemical analysis for coal is progressively harder grinding coals.
the proximate, which describes the fuel in
Liquid Fuels
weight percent of fixed carbon, volatile mate-
rial, ash, and moisture contents. In the ultimate Oil fuels are reported in an ultimate analysis
analysis, the fixed carbon and volatile material together with higher heating value and sample
contents are reported in terms of total carbon, density, viscosity, and flash point. Density can
hydrogen, oxygen, nitrogen, and sulfur, this be stated as either standard specific gravity, re-
form being required for calculation of fuel-air ferred to water, or degrees API, the two terms
quantities. being readily convertible. Additional proper-
Fuel analysis and high-heat-value determi- ties are pour point, sediment, and the presence
nation are made in accordance with the Test of solid impurities such as metallic salts.
Code for Solid Fuels PTC 3.2 and ASTM Stan- These properties may influence pumping,
dards.' This is a constant-volume determina- storage, slagging, and corrosion problems.
tion. Because the fuel is burned at constant In general, the ultimate analysis is sufficient
CoMBmnON
Perfomanw Testing of Steam Generators

to determine fuel-air relationships for by- amounts for the fuel rate being burned.
product liquid fuels such as pulp-mill black Operating indexes, therefore, are designed to
liquor, refinery wastes, pitch and others. But show the percent excess-air or relative percent
operating problems may require special tests total-air quantities. On the other hand, for en-
in addition to the standard physical property gineering design purposes, these air and gas
determinations. rates are necessary to properly size fans, ducts,
Gaseous Fuels
and heat-transfer equipment.
In routine operation, airflow measurement is
Gaseous fuels are usually combinations of accomplished through pressure or draft differ-
saturated and unsaturated hydrocarbons, and ential sensing of a gas or air-side component, or
their analysis is reported as a mol or volume by means of flue-gas analysis. In either case,
percent of these constituents. Common anal- field calibration of the metering equipment is
yses include low-temperature distillation, ultimately based upon test flue-gas analysis.
mas's-spectrometer, and adsorption methods. Flow measurement by pitot-tube techniques is
From this constituent analysis, high heating somewhat restricted in boiler air and gas flow
value at standard volumetric conditions and problems because duct configuration and low
saturated or dry can be calculated by using static-impact pressure difference generally
standard heating values of constituents. limit the resulting accuracy. More importantly,
Where gas samples of large volume can be the flue-gas analysis method is superior be-
provided easily, the classical method of heat- cause of its simple interpretation for overall
ing-value determination, by calorimeter, is airflow. However, pitot measurements become
feasible. For instance, recording calorime- necessary for study of air of flue-gas distribu-
ters are often found at transmission-line entry tion within a system.
points to users' plants for billing purposes.
Excess-Air Determinationby Flue-Gas Anaiysls
Fuel-Air Proportioning
A simple method of volumetric flue-gas anal-
Combustion airflow measurement and regu- ysis is by Orsat apparatus, Fig. 1, in which a
lation are requisite to good operation because known volume of gas is sequentially exposed to
of the desire to burn a fuel with optimum air absorbent solutions for carbon dioxide and oxy-
quantity. Some air in excess of the theoretical gen. Measuring sample volume between stages
quantity for complete combustion is always re- indicates the constituent volume percentages
quired, the amount depending upon the fuel and the remaining nitrogen. Trace gases such
and firing method. Although ideally the lowest as argon are included with nitrogen, while sul-
excess air is desirable, there are many condi- fur compounds such as sulfur dioxide and tri-
tions under which high excess air results in oxide are absorbed together with carbon
more economical plant operation. If, for exam- dioxide. For most fuels, their effect on the
ple, constant steam temperature is to be main- gas-analysis results is negligible in excess-air
tained at 10iv ratings, increased gas mass flow determination.
may be required over heat-transfer surfaces. In- The resultant gaseous products for complete
creasing excess-air is one way of accomplish- combustion of a fuel using several excess-air
ing this. values are calculated from the ultimate fuel
analysis and chemical combining equations.
Airflow Measurement
Plotting the volume percentages of carbon di-
Knowing the quantities of air required and oxide and oxygen thus formed permits excess-
fuel products formed in terms of weight or vol- air deterinination by volumetric gas analysis.
ume rates is not necessary from an operating As a matter of fact, within certain restrictions,
point of view. The operator wants to know excess-air can be determined without the fuel
these quantities relative to the theoretical analysis, because the available oxygen in
COMBOSRON
Performance Testing of Steam Genera-

products is a direct measure of excess-air and, Detecting UnburnedCombustibles


_ when compared to the nitrogen, will indicate In modern fuel-burning practice, unburned
percent excess-air. For fuel oil or many gaseous combustibles in flue gas are generally
bituminous coals, oxygen measurement using nonexistent; however, they can occur with cer-
graphical means such as Fig.. 2 is sufficient to tain operating conditions. Even in these cases,
indicate excess-air with acceptable accuracy. the extremely low quantities to be found [less
The practical uniformity of this oxygen- than 0.10 percent) are usually beyond the accu-
excess-air relationship over a wide range of racy of Orsat work and require detection by
fuels makes it extremely useful in both single chemical reaction-calorimetric methods or
and combination fuel firing. Moreover, it is re- laboratory analysis of small samples by mass-
sponsible for the widespread use of flue-gas spectrometer and adsorption techniques. In
oxygen analyzers for operating and test pur- either case, to avoid misleading results, the
poses. These devices ,employ either catalytic samples must be collected with extreme care to
combustion of a known gas and the uncom- circumvent sample contamination; For exam-
bined oxygen in a flue-gas sample within a ple, the sampling probe should be a quenching
temperature-sensitive electrical circuit, or type since hot-probe materials may act as com-
magnetic-field distortion due to paramagnetic bustion catalysts in the flue gas, thus indicat-
qualities of the oxygen in the flue-gas sample. ing no combustibles when they are present.
In both cases, the effect is proportional to sam-
ple oxygen content, and permits calibration of
the instruqent-output signal in terms of oxy-
gen percent.

Percent COa (+CO)

Fig. 1 A basic means of volumetric flue-gas analy- Fig. 2 Percentage relationship of oxygen (Oz), car-
sis is by Orsat apparatus. In this method, a known bon dioxide (COZ) and excess air. (Orsat analyses
volume of gas is exposed to absorbent solutions for a given fuel should plot on a straight line parallel
for carbon dioxide and oxygen. to the guidelines.)
COMBUSTION
Performance Testing of Steam Generators

Conversely, probes and sample containers thermoelectric effect, a phenomenon whose al-
should be free of oil films, high-vapor-pressure ternate effects were first observed respectively
stopcock grease and the like, since these mate- by Seebeck and Peltier in 1821 and 1834. An
rials may indicate traces of combustibles when electromotive force (emf) is developed if a cir-
there are none in the flue gas. cuit comprising two different wires has the two
junctions at different temperatures. The mag-
TEMPERATURE MEASUREMENTS
nitude of the emf depends on the wire materials
Temperature-measurement techniques differ and is proportional to the temperature differ-
depending upon temperature level, fluid ence between the junctions. Thus, knowing the
stratification, physical accessibility, and accu- temperature at one junction and considering
racy d e ~ i r e d . ~ the wire materials, the temperature at the other
Generally, two methods are common in junction can be determined. Special laws gov-
steam-generator testing: ern the effects of intermediate metals and
1. filled-system thermometers and temperatures.9 See Fig. 4.
2. thermoelectric and electrical resistance Numerous metals are available for ther-
effects. mocouple materials with selection being based
on emf developed, expected mechanical life in
These two methods are direct in that they in-
the atmosphere and temperature involved, cali-
volve fluid-temperature level attainment by the
bration constancy, and cost. The most common
sensing element. On the other hand, calibra-
types are copper-constantan, iron-constantan,
tion difficulties arising from variations with chromel-alumel,10 and platinum-platinum-
different fuels and furnace equipment prevent rhodium; their upper limit temperature ratings
frequent use' of indirect techniques, such as for general service are 400, 1100, 1800 and
utilization of optical or radiation effects ac- 2700F respectively.
companying temperature level of the fluid. Several engineering societiesll have de-
The most common of the filled-system ther-
mometers, mercury and other liquid-in-glass
thermometers use volume expansion. Their
use in gas and air work is restricted to ambient-
level temperatures and, when stratification
does not exist, in ducts. As a variation of the
volume-expansion class, gaseous-bulb type in-
struments, commonly found in operating in-
strumentation, also measure accompanying
pressure change. Although this type instru-
ment permits remote indication, it is a fixed-
position device, usually requiring field
calibration by another means. See Fig. 3.
The most versatile temperature-measure-
ment devices are those in the second group.
Both thermoelectric and electric-resistance
type techniques are readily adaptable to remote
measurement, thus enabling monitoring of
many points from a single location. Of the txvo,
the thermocouple is more widely used because
of its simplicity and low cost.
Fig. 3 Mercury and other liquid-in-glass thermom-
THE THERMOCOUPLE eters are used in gas and air work for sensing low-
Thermocouple measurement employs the and moderate-temperature levels.
COMBUSTION
Performance Testing of Steam Generators 1
veloped detailed specifications covering extremely accurate and is used in temperature
temperature-emf relationships and standard standards work. However, the high cost of sens-
accuracy limits. Experience with chromel- ing elements and measuring circuit restricts its
constantan thermocouples also indicates suit- use to laboratory calibration w o ~ kor field test
ability of this combination for measurements work where high precision is required, such as
up to 1600F with high emf developed. measurement of fractional parts of degrees.
Thermocouple emf can be measured with
either a millivolt galvanometer or a null- USING THERMOCOUPLE PROBES
balance potentiometer. However, in the gal-
vanometer system, the thermocouple circuit Generally, flue-gas temperature measurement
resistance is an additional factor and com- is made with thermocouple probes. Such meas-
plicates t h e measurement, whereas in the urement requires that the hot junction of the
null-balance system no current flows in the thermocouple reaches the fluid temperature
thermocouple circuit, the measurement be- level. Thus, the fluid contacting the thermo-
ing of the opposing emf. Being simpler, the lat- couple must be flowing at a sufficient rate to
ter system is more widely used. supply heat lost by conduction from fhe hot
junction along lead wires and by radiation to
THE RESISTANCE-BULB METHOD
colder surfaces. The magnitude of these heat
The resistance-bulb method involves known losses will depend upon probe design, includ-
temperature-electrical resistance change char- ing probe temperature and relative orientation
acteristic of a material, usually nickel or of the hot junction, and temperature differen-
platinum, using a Wheatstone bridge type tial between the hot junction and the heat re-
measuring circuit. This method can be made ceiving surfaces.
Thermocouple measurement of gas-air
temperature in most ducts is simplified for the
following reasons.
1. Temperature level is below 700F and does
not require water-cooling of probes for me-
chanical strength.
2. Ducts are insulated to prevent heat loss and
the interiors of ducts are essentially at fluid
temperature.
At a temperature level .of 700F,an error of
15F is commonly found with bare thermo-
couples 'in proximity to economizer heating
surface at 500F.
At gas temperatures higher than 700F,
watercooling of probes is necessary for me-
chanical strength reasons, and the leadwire
conduction heat-loss increases. More signifi-
cantly, higher temperature levels correspond
to areas with heat-transfer surfaces such as
economizer, waterwalls, superheater, and re-
Fig. 4. Resistance thermometers have as their sens- heater, the surface temperatures of which vary
ing element a resistor usually made of pure-metal
wire. a diagram of a typical simple balanced- between 500 and 1100F.As a result, the radia-
bridge type of instrument using a Wheatstone tion error of a bare thermocouple junction in-
bridge is shown. creases severely until at the furnace outlet
C O ~ O N
Performance Testing of Steam Generators

(with gas temperature of 2000F)the bare ther- across flow nozzle or thin-plate orifice sec-
mocouple error is about 200F. tions. The two flows are equal except for losses
To compensate for radiation and conduction such as blowdown and injection leakoff. Of the
heat loss in furnace gas-temperature work, the two, however, feedwater measurement is gen-
thermocouple junction is shielded with a thin erally more reliable than steam flow because
ceramic cylinder through which a high gas orifice coefficients are more positively estab-
flow is induced. In turn, the shield is subject to lished for the former.
the same heat-loss effects and, by increasing The recording flow meters found in most
the number of annular shield layers, the ther- plants employ commercial orifices or flow noz-
mocouple junction can be brought to within zles. Overall accuracy is usually plus or minus
+ 5F of true gas temperature. Usually the fuel 2 percent of full scale, unless the installation
determines the limit to the size and number of has been calibrated against a special test
shield openings. With high-ash coals serious orifice. These test orifices are plant primary
plugging can occur in a short period when standards, usually installed in low-pressure,
shields with small openings are used. low-temperature condensate points in the
feedwater cycle to avoid undue extrapolation
THE ORIFICE PROBE
of original calibration data. Their calibration is
Another type of furnace gas-temperature performed with laboratory weigh tanks, and
measuring device is the orifice probe, in which extrapolation of flow coefficients to the con-
the hot gas is drawn through two metering densate conditions of flow, temperature and
orificesin series, with deliberate cooling of the pressure is usually accomplished on the basis
gas occurring between them. By measuring the of Reynolds number and other dimensionless
two orifice-flow rates and cold-gas tempera- criteria.
ture, the initial gas temperature can be calcu- While a few central stqtions have reheat
lated since weight flow is constant and the steam flow meters, it is more common to de-
orifice-flow differentials indicate volume flow, termine this quantity from primary steam-
which is a function of temperature. The advan- water flow, high-pressure heater heat balance
tage of this type measurement is that it elimi- and the appropriate turbine gland corrections.
nates thermocouple radiation error. For test of heat-absorption surface char-
acteristics, it is usually sufficient to use the
MEASUREMENTS RELATED operating feedwater recorder as these charac-
TO HEAT ABSORPTION teristics are essentially constant for rating
changes within meter accuracy, and the fuel-
Heat absorption values are used in develop- air-gas flow data are related to this base value
ing the surface heat-transfer relationships and by heat balance.12
are determined from test steam-temperature Another method of flow measurement some-
and flow measurements, together with gas times used is pitot-tube technique. Variations
temperatures and flows. Additional perfor- of the standard air-gas type are usually pre-
mance items in the water-steam cycle are pres- ferred for manufacturing reasons, and these are
sures, pressure drops, and qualitylpurity commonly used in some circulation studies
determinations. Circulation studies in furnace where a low-resistance measuring element is
waterwalls and flow distribution between cir- required. These devices are usually not suit-
cuits are other examples of water-steam cycle able for total unit flow measurement because
testing. of structural and flow-pattern uncertainty
reasons.
WATER AND'STEAM FLOW
Weigh tanks are rarely found in large utility
-.
Both steam output and feedwater flow are ob- installations because of unit size and conse-
tained by pressure-differentia1 measurement quent cost. Flow nozzles and orifices are taking
COMBUSTION
Performance Testlng of Steam Genemtors

over their functions. However, the weigh- column heights which are practical, the fool-
ing facilities are necessary as primary refer- proof-simplicity of the method is the reason for
ences in standard laboratories where the nozzle its retention as a reference. Glass-faced .mer-
calibration work is performed. - - - cury manometers are used for pressure-dif-
ferential workup to line pressures of 2000 psig,
T EMPERATURE MEASUREMENT
especially for orifice-flow nozzle differential
The common devices for temperature meas- measurements. Some range flexibility exists
urement are thermocouples, resistance-bulb through use of liquids whose densities are be-
elements and thermometers. The general tween those of water and mercury. A variation
statements on this subject made previously of the visible column, used for pressures over
under gas and air measurements also apply to 2000 psig, is a column inside a tube or jacket
steam and water measurements. with a float indicating liquid level through
Some aspects, however, present more serious mechanical linkage or magnetic pointer.
problems than in the gas-air work. Since in this Deadweight instruments employ incremen-
case the fluid pressures are also high, the tal weights acting on a given-sized piston
measuring elements are rarely exposed directly which floats when the liquid and weight pres-
to the fluid stream. Measurement is commonly sures are equal. In deadweight gages, the liquid
made by bottoming contact with a metal well
which projects into the stream and provides the
necessary mechanical strength. Several well
designs are'shown in the ASME Performance
Test Code, Supplements on Instruments and
Apparatus, PTC 19.3 and in a paper by J. W.
Murdock.lJ
Another method of fluid-temperature deter-
mination is surface-temperature measurement
of the containing steam or water tubing. This
method is only possible where there is no heat
transfer because of temperature gradient effects
from hot gas and steam-film. In these zero
heat-flux areas, the tube-wall gradient usually
presents no problem in measurement, although
even here precautions should be taken against
boundary effects. See Fig. 5 .
Thermocouples are commonly peened di-
rectly into the tube metal or attached by
welding the hot junction to the metal. In a
well application, spring loading of the element
is more practical. In both these cases, the ther-
mocouple is grounded and measurement of a
number of points must be by separate circuits l O l ~ l ~ 1 # J
since series connections can form unknown 0 5 / 4 % % 1 2
loops using boiler metal as a third wire. Inches
PRESSURE AND PRESSURE DIFFERENTIALS

The fundamental Pressure and pressure- Fig. 5. Thermocouples are used for surface-
differential measuring device is the visible temperature measurement of tubing containing
liquid column. Although its use is limited to fluids at high pressure.
COMBVSRON
Performance Testing of Steam Generators

pressure is line pressure, its value determined ADDITIONAL


from the weight total. In deadweight testers, PERFORMANCE MEASUREMENTS
the liquid is in a closed system with the pres-
The steam-generator pressure parts are the
sure acting on the instrument to be calibrated
means by which heat liberated in combustion
and on the weight piston from which the pres-
of the fuel is absorbed by the steam-water fluid.
sure value is determined.
Since the process is one of heat flow, it must be
A common steam-water pressure measuring
apparent that temperatures of the various
device is the Bourdon gage, Fig. 6 , the simplest
equipment items are the basic criteria for de-
form of which is a bent flattened tube that tends
sign once the desired pressure is stated.
to straighten itself when internal pressure is ap-
The thermocouple is by far the most-used
plied. Motion of the tube end is transmitted
piece of test apparatus in steam-generator
through linkage to a pointer which sweeps a
study. Its adaptability for remote measurement
graduated scale. The concept of mechanical
of many widely separated points permits inves-
motion or distortion due to fluid pressure is
tigations and control otherwise impossible.
common to all pressure elements; the differ-
Usage is not limited to pressure parts but in-
ences occur in the way this force is translated
cludes structural parts as well.
into a signal. Development of this idea is found
Aside from temperature considerations,
in diaphragms, bellows and cylinders whose
steam-generator equipment is subjected to
motions are linked to and described by
abrasion and erosion and to vibration forces.
pointers, strain gage wires, varying resistance
The first two are generally long-term processes
bridges, differential transformers, and other
requiring correlation of metallurgical labora-
mechanical or electrical signal generators.
tory studies with prolonged operating experi-
Such combinations of devices are known as
ence. The main function of field-test activity
pressure transducers. Their sensitivity, linear-
in this area is to establish the magnitudes of
ity, repeatability, and hysteresisare characteris-
existing factors such as temperature, gas-flow
tics to be evaluated in selecting a combination
velocity patterns, ash-fuel character and
for any specific application.
concentrations.
With the increase in unit size an'd desire for
balance between strength and weight, vibra-
tion forces have received considerable atten-
tion because of their destructive effects.
Standing waves in flue-gas passages induce
structural and pressure-parts vibrations. Test
activity in this area is required for corrective
work and to provide design criteria to avoid
susceptible arrangemerits. Gas vibrations are
measured with traversing pressure transducers
and oscillographic measuring circuits or me-
chanical vibration graphing devices, depend-
ing upon conditions. The latter are also used
for structural and casing members.
Another problem related to temperature fac-
i&
tors is equipment expansion between hot and
Fig. 6. In its simplest form, the Bourdon gage, a
cold positiorls: These movements are generally
common steam-water pressure measuring device, measured with trams or dial gages depending
is a bent flattened tube that tends to straighten itself .. upon the application. For instance, since lower
when internal pressure is applied. waterwall headers on certain units will move
COmUSTION
Performance Testing of Steam Generators

downward as much as 15 to 20 inches, and


other parts lesser amounts, unrestrained move-
1
ment is essential. TABLE I.Principal EPA Methods
for Measuring Flow Rate and
Sample ~ r o d i c t s
of Fossil-Fuel
GAS-FLOW ME~SUREMENT Combustion
AND SAMPLING TECHNIQUES
Measurement and sampling of the gaseous EPA METHOD Application
and particulate products of combustion are es-
1 Layout of sampling/measurement
sential for verification of compliance with points in a duct or stack.
emission regulations; assessment of the per- 2 Determination of duct or stack gas
formance of emission-control systems; and in velocity and volumetric flow rate
evaluating the potential for corrosion, erosion, using a Stauscheibe pitot tube.
and deposit formation on internal surfaces such 3 Determination of the carbon-dioxide,
as ducts and stack liners. The principal method oxygen, and carbon-monoxide
of determining the concentrations of partic- content of a gas sample using an
Orsat or Fyrite analyzer.
ulate material and of the oxides of nitrogen and
4 Determination of the percentage
sulfur in a gas stream is gas sampling. Other moisture in an extracted gas sample.
gaseous products of combustion that are meas- 5 Determination of the particulate
ured, particularly in municipal-waste-fired concentration of a gas stream. This
plants, include: hydrogen chloride, hydrogen test method employs a filter enclosed
fluoride, heavy metals, and certain organic spe- in a heated housing, external to the
cies. Measurement of the gas volumetric and gas stream.
mass flow-rate is required to assess equipment 6 Determination of the moisture-free
sulfur-dioxide concentration of an
performance and to determine the total mass extracted gas sample.
emission rates. 7 Determination of the moisture-free
nitrogen-oxide concentration of an
TECHNIQUES OF MEASUREMENT extracted gas sample.
8 Determination of the moisture-free
The Environmental Protection Agency (EPA) sulfur-dioxide and sulfuric-acid
Methods publications describe those tech- concentration of an isokinetically
niques most widely used in the United States extracted gas sample. A multipoint
for measuring the products of fossil-fuel com- traverse is employed with this
method.
bustion, These test procedures appear in the
9 Determination of stack-emission
Code of Federal Regulations, Title 40, Part 60, opacity through visual observation.
Appendix A, and are printed by the Office of 10 Determination of the
the Federal Register, National Archives and Rec- carbon-monoxide concentration of an
ords Administration. Table I lists the principal extracted sample using a
EPA methods applicable to the products of fos- nondispersive infrared analyzer.
sil-fuel combustion. The following sections 17 Determination of the particulate
will cover commonly used EPA procedures for concentration of a gas stream using an
in-situ filter.
measuring gas flow, particulate matter, sulfur di-
19 Calculation methods for determining
oxide, sulfuric-acid mist, and nitrogen oxides. system sulfur-dioxide removal
GAS FLOW RATE QUANTlFlCATlON
efficiency, and particulate,
sulfur-dioxide and nitrogen-oxide
Test Methods 1 through 4 detail an approach emission rates from electric utility
for measuring the gas mass or volumetric flow- steam generators.
rate using a pitot-static probe, described later in
C0MBUSTI0W
Pertonnmmx rating of Steam Generators

the chapter. These methods employ a technique Once the gas sample has been extracted, it
of subdividing the duct cross section into passes through a glass fiber filter which cap-
equal-area zones. The number of zones re- tures a majority of particulate larger than 0.3
quired is a function of the distance of upstream micrometers. The remaining particulate travels
and downstream disturbances relative to the through a heated sample line to a series of
measurement plane. From point gas velocity chilled-water impingers and a desiccant, which
measurements i n each of these equal-area remove all remaining particulate and water va-
zones, the mean duct velocity can be used por from the gas sample before it reaches a dry-
to determine the gas volumetric flow-rate as gas meter and sample pump. The particulate
follows: loading in the gas stream is typically reported
Q=AXV as grains of particulate per actual or dry stan-
dard foot of gas, (gr/acf or gr/dscf). Stack emis-
where sions are reported to regulatory authorities as
Q - gas volumetric flow-rate the pounds of constituent per million Btu heat
A-measurement plane cross- input to the boiler. This may be calculated as
- sectional area follows:
V -mean duct velocity
Mass flow can be determined from the volu-
metric flow-rate if the gas composition, abso-
lute pressure, and gas temperature at the
measure'ment plane are known. Methods 3 and
4 detail test procedures for determining the
principal products of fossil fuel combustion,
including carbon dioxide, carbon monoxide, where
oxygen, and water. E = amount of pollutant in an
The equal-area zone technique is also speci- extracted gas sample
fied by ASME PTC 19.5, Fluid Velocity Meas- C, = pollutant concentration
urement. This Code discusses errors produced O2 = volume percent oxygen on a
in non-uniform velocity distribution. Also, sev- water-free basis
eral analytical methods of velocity averaging CO, = volume percent carbon diox-
are presented and evaluated. side on a water-free basis
F, = oxygen fuel factor
MEASUREMENT OF-PARTICULATELOADING F, = carbon-dioxide fuel factor

Procedures for the determination of the par- Fuel factors can be determined from an ulti-
ticulate concentration in a gas stream are de- mate analysis of a fuel sample or an estimated
tailed in EPA Methods 5 and 17. As specified by value is provided in EPA Method 19. These
these test procedures, a sample of gas and par- equations are applicable in reporting the emis-
ticulate is isokinetically extracted, with a sharp sion rate of most gaseous or particulate pollu-
edged nozzle, from equal-area zones. Isokinetic tants.
sampling simply means that the gas/p&iculate The principal difference between Methods 5
sample is extracted at a rate equal to the flow and 17 is the location of the glass fiber filter.
rate of gas i n that zone. The extraction rate of Method 17 uses a thimble-type filter located at
the gaslparticulate sample is measured by a pitot- the end of the probe just upstream of the noz-
static tube and must be adjusted, or verified, zle, Fig. 7. Method 5, Fig. 8, employs a flat
for each sample point. These methods require filter enclosed in a heated housing on the end
that the rate of sample extraction should be of the probe, external to the gas stream. Method
within 90 to 110 percent of isokinetic. 17 is preferred for high particulate loadings,
COMBUSRON
Performance Teuting of Steam Gemfators

such as upstream of a particulate collection de- maintaining proper temperature in the sample
vice, because a thimble filter can accept much probe and filter. Insufficient heating of the
more ash before blinding. probe and filter can allow sulfuric acid conden-
Both Methods require the extraction of at sation. Acid which is deposited on the filter
least 30 dry standard cubic feet (dscf) of gas will be reported as particulate. Heating the
over a period of not less than 60 minutes. The probe too hot can also affect the accuracy of test
amount of gas sampled, however, is often de- results. If the probelfilter temperature is too
pendent upon the anticipated particulate load- high, the particulate sampled may be volatil-
ing. For instance, it is not uncommon to extract ized. For this reason, EPA limits the probetfilter
as much as 60 dscf over 120 minutes at the out- temperature to less than 320E
let of a high efficiency particulate-collection
device. This provides a larger particulate catch MEASUREMENT OF SULFUR-DIOXIDE AND
SULFURIC-ACID CONCENTRATION
and, therefore, a more accurate result.
An accurate result is also dependent upon Procedures for measuring the concentration

Temperature Sensor

Type-S Pitot Tube In-Stack Filter Holder Thermometer

Pitot Manometer

Thermometers

Orifice Manomete
/
Dry-Gas Meter

Fig. 7 Typical particulate-samplingtrain, equipped with in-stack filter.

A!!
- COMBUSION
hrformmce Twting of Steam Generators

of sulfur dioxide in a gas stream are outlined in tered. Preceding sampling, or i n between
EPA Method 6, Fig. 9. As described in this sample runs, the gas train is purged with air for
method, a sample of gas is extracted through a at least 15 minutes. Gas sample times are at
heated probe and sample line and then passed least 20 minutes although longer sample times
through a series of ice-water-chilled impingers. are desirable when measuring low sulfur-
The first of these impingers contains an 80 per- dioxide concentrations.
'
cent isopropanol (IPA) solution. The successive The sulfuric acid in the gas stream can also
two impingers contain a 3 percent hydrogen be measured with this type of gas train if iso-
peroxide solution. Sulfuric-acid mist is prefer- kinetic sampling from equal-area zones is used
entially absorbed in the first IPA impinger (EPA Method 8). Isokinetic, multipoint sam-
while the sulfur dioxide is absorbed in the fol- pling is also necessary if sulfurdioxide stratifi-
lowing two peroxide impingers. Following the cation is present. Stratification is most likely in
impingers, the gas sample is further dried us- ductwork runs downstream of the absorber
ing a desiccant and the dry gas volume is me- module. Gas entering a flue-gas desulfurization

S<
E Zy
? ' Temperature Sensor

'probe ,Thermometer Thermometer,

Pitot Manometer
Thermometers
Orifice

Main Valve

2-1 '~ir-Tight Pump


Dry-Gas ~ e t e i
-
.
. - -

*
Fig. 8 Particulate-sampling train
COMBUSTION
Performance Testing of Steam Generators

system is usually well mixed so that a single- Method 6C. An extracted sample of gas is dried
point sample, Method 6, is acceptable. to remove all water, and is then introduced into
Following extraction of a gas sample, the sul- an analyzer. The analyzer must undergo cali-
fur dioxide or sulfuric acid absorbed in the im- bration checks to verify its .ac_curacypreceding
pingers is titrated. From the -titrant volume and following each sample run. Instrumental
required, and the dry gas volume sampled, the methods of measuring gas sulfur-dioxide con-
concentration of sulfur dioxide and sulfuric centration can provide results in a shorter
acid in the gas stream can be calculated. As length of time and can readily identify duct-
with the particulate loading, sulfur-dioxide work sulfur-dioxide stratification.
and sulfuric-acid concentrations are usually re-
MEASUREMENT OF NITROGEN-OXIDE
ported on a pounds of pollutant per million Btu CONCENTRATION
heat-input basis.
An instrumental procedure for measuring the Both absorbent and instrumental techniques
sulfur dioxide concentration can also be used, have been developed by the EPA for measuring

Temperature Sensor

Pitot Manomete

Thermometers

Dry-Gas ~ e t e i

Fig. 9 Sulfuric-acid mist-sampling train


C o m ~ O N
P o d m n o Testing of Steam Generators

the concentration of nitrogen oxide in a gas W. Hawksley defines the approach of the
stream. Instrumental Method 7E has gained the British Institute of Fuel14.This publication dis-
widest use because results can be obtained im- cusses the effects of nonsymmetrical gas-flow
mediately following gas sampling. Method 7 distribution and boundary-layer profiles. It
requires six?een (16) hours between collection should be noted that the equal-area zone
of the gas sample and analysis of the absorbent method, as typically used, can easily miss the
to determine the nitrogen-oxide concentration. boundary-layer flow profile. Very small incre-
In both Methods, a sample of gas is extracted mental areas would be required for the velocity
through a heated probe. Isokinetic sampling is probing device to "see" all of the boundary
usually not necessary unless there is reason to layer. However, traversing time can be reduced
suspect NO, stratification. As specified in if the boundary layer is evaluated in detail for
Method 7, a sample of gas is collected in a two- one test only and then used to correct coarser
liter boiling flask with 25 milliliters of absorb- subsequent traverses. This approach is justifi-
ing solution. After contacting the absorbing able since each flue or stack will have its own
solution with the gas sample for at least 16 characteristic boundary layer which is a func-
hours, an aliquot of the absorbing solution is tion of the specific system geometry and flow
analyzed using spectrophotometry. The absorp- turbulence. There have been occasions where
tion of NO, by the spectrophotometer can then boundary layers representing 5 percent of the
be related to the NO, concentration of the gas flue diameter have produced flow errors of
sample. some 10 to 20 percent.
In Method 7E, the NO, in the extracted sam-
ple is first converted to NO. A chemilumines- VARIATION IN RESULTS
USING PITOT-STATIC MEASUREMENT
cence analyzer is then used to determine the
N0,concentration. As with the SO2instrumen- Pitot-static tube velocity measurements have
tal method, calibration checks are necessary to been coupled with the equal-area technique for
verify the accuracy of the indicated results. many years. The results of total gas flow can be
THE NEED FOR ACCURATE MEASUREMENT
quite varied and misleading, if care is not given
OF GAS FLOW to the selection of the measureqent plane, or
consideration given to the selection of the
The information in the final portion of this proper type of flow-measurement device for the
chapter is included because of the profound ef- flow directionality that is present. Table 11'5
fect that the quantity of gas being handled has presents the results of several total gas-flow
on the sizing and cost of the gas-treatment measurements using the pitot-static tube and
equipment. equal-area techniques as called for in the above
The determination of total quantities of standards. The results listed are derived from a
gaseous and solid constituents in the gases typical utility steam-generator installation op-
leaving a steam generator depends upon an ac- erating at constant load. As noted, the flow as
curate quantitation of the gas flow itself. For in- measured can vary from 104 to 150 percent of
stance, in the sampling of dust, the amount of rated value.
material caught in a sampler is reduced to a
dust concentration of, say, pounds of dust per POWER-PLANT FLOW PATTERNS
1000 pounds of gas. The total quantity of dust
being emitted by the source, then, is the prod- Industrial ductwork and flues are designed
uct of dust concentration and total gas flow by to connect pieces of equipment at the minimum
weight. cost and minimum space requirements. The re-
sultant flow patterns quite often deviate from
BOUNDARY-LAYER EFFECTS
-
the desired uniform and unidirectional condi-
Measurement of Solids in Flue Gases by P. G. tion required for accurate quantitation of,flow.
COMBUSTION
Performance Testingof Steam Generators

measurement of fluid velocity has been by pitot


Table 11. Gas-Flow Measurement: tube. Several referencesl"l9 are available which
Gas flow measured at different locations in accor- describe the developing history of this device.
dance with methods given in ASME 27 and by
Appendix E of the 1981 edition of this text, Ve-
using a pitot-static tube. Observe the gross locity Calculations by Graphical Methods,
divergence of measured values and the necessity for presents graphs that can be used for quick de-
careful choice of measurement point. termination of gas velocities from pitot-tube
readings.
Gas Flow Percent THE TUBE
Measurement Point CFM Rating
The typical flow-measurement device is the
Rated Value 300,000 100 pitot tube shown in Fig. 10. The impact or total-
Mechanical-Collector Inlet 383,000 128 pressure hole is the most useful part of the
Mechanical-Collector probe. Hydraulically, the impact pressure is
Outlet 449,000 150 the true sum of the local static and dynamic
Induced-Draft Fan Inlet (velocity) heads. Also, the impact hole can
(Precipitator Outlet) 313,000 104
have a cone of response of some 60 to 70 de-
Induced-Draft Fan Outlet 424,000 141
grees. Therefore, accurate angular positioning
of the probe for total (impact) pressure meas-
urements is not critical. However, positioning
Flow separation and reverse flows, often found of the probe parallel to the flow direction is
in the major runs of flues, are corrected only by very critical for static-pressure measurement.
major pressure drops such as an air heater or The static-pressure-tap reference surface
excessively long runs of duct work. should be parallel to the flow stream-lines.
Flow patterns in stacks and fans frequently Also, ideally, the flow stream-lines should be
are highly productive of vortex energy. A basic straight and parallel. Any flow stream-line
problem associated with vortex formation is
that vortices will persist for many diameters
downstream from the source. Vorticity has a
very strong effect on dynamic-flow measure-
ment devices.
Occasionally, reverse or negative flow may
be encountered. A question then arises as to
how to calculate the total volume flow rate from
this type of data. Fluid-flow continuity re-
quires that all velocity points, both normal
direction and reverse flow, be arithmetically
averaged and applied to the total cross- Total Pressure Hole
sectional area of the plane of measurement. If
this is not done, the recirculated gas flow (the Total Pressure
negative values), which can represent 5 to 15
percent of volume throughput, will increase
the positive flow values by the same amount
and produce a measured flow that is high.

VELOCITY MEASUREMENT Fig. 10 A pitot tube for fluid-velocity measurement


with pressure connections and readout shown
The classical and long-term approach to the schematically
COMBDSnON
Performance Testing of Steam Generators
-
which is not parallel to the static surface will for velocities of 20 fttsec and higher. Cole shows
induce an impact or reverse-impact, dynamic that there are many variations of C, with probe
pressure at the static hole and create an as- manufacture; thus, each Type S probe should
sociated error. be calibrated in a known flow stream and a
One practical problem associated with the curve of C,vs velocity prepared.
pitot tube is the right-angle bend and probe tip
length. This configuration requires large holes THE FECHHEIMER PROBE
in the flue, or duct wall, or some awkward
probe handling by the user. The bend also A directional pitot tube, see Fig. 12, has been
makes it difficult to probe the flow at the near developed using the work of Fechheimer.19
side, or access wall, of the flue. Large holes in This probe is basically a reverse impact probe,
the flue wall are, in turn, difficult to seal to pre- but makes use of properties of the flow field
vent leakage errors. Another problem asso- around a cylinder. Two additional static, or
ciated with the standard pitot .tube is the Fechheimer, taps are located on the "forward"
tendency for the small holes to plug in flues face of the cylinder. Two sets of differential
with heavy dust loadings. readings are required. The probe is rotated in
the gas stream until the velocity taps read posi-
THE STAUSCHEIBE PITOTTUBE tive and the two additional static taps are
nulled. The probe is then "looking" directly at
To eliminate such problems, stack samplers the flow-velocity vector and the angle can be
have used the "Stauscheibe" or Type S pitot recorded.
tube shown in Fig. 11. Because the reverse- The Fechheimer probe is very sensitive to the
impact method is used to read the static pres- problem of flow moving along the length of the
sure, this probe will produce a new velocity stem when the stem is not exactly perpendicu-
head reading h = KV2/2g where K will be lar to the flow field. Folsom evaluates this con-
greater than 1.0. A velocity correction factor C,, dition, called "stem effects," in reference 19.
where V = c,- is 0.855. However C, is not The probe used in C-E's laboratory places the
constant, but it is a function of velocity. Cole18 sensing cylinder at the end of the airfoil stem
recommends C, = 0.870 at 10 Wsec and 0.885 which will tend to bleed off stem flow before it
at 3 ftlsec. C-E has found that C, is 0.855 only reaches the pressure sensing holes. This mod-

Gas or Air Flow


5/16"OD x 0.035" Wall
Stainless Steel Tubes

Weld

Surfaces
Must Be Parallel
to Each Other

L I
Fig. 11 The Stauscheibe or Type S pitot tube
COMBUSTION
Performance Testing of Steam Generators

ification minimizes, but does not eliminate, the Each probe head has its own calibration curve
induced stem errors. The veIocity correction which is a function of Reynolds number.
factor, C,, for this probe is not as dependent on The use of a five-hole probe is most impor-
small differences in manufacture as is the Type tant where there is significant directionality of
S probe. In this case, the value of C,is typically the gas flow. That is, the flow-velocity vector is
0.78 for probe Reynolds numbers in excess of not parallel to the duct axis. Most pitot probes
100. are insensitive to flow directionality less than
15 percent. The Fechheimer probe measures di-
THE FIVE-HOLE PROBE rectionality only in the plane normal to the
Another type of directional pitot tube is the probe; a five-hole probe measures directionality
five-hole or three dimensional probe; see Fig. in planes normal and parallel to the probe.
13. This probe is similar to the Fechheimer If the flow vector at a point is known, then the
probe; however, it has an additional two pres- component of flow normal to the plane of tra-
sure-sensingtaps which allow measurement of
the pitch angle of the velocity vector. As with
the Fechheimer probe, the static pressure taps
are nulled so that the probe is "looking" di-
rectly at the flow velocity vector. The pitch an-
gle is determined from a calibration curve
which relates pitch angle to a pitch pressure
coefficient, C,. This coefficient is the ratio of
the pitch tap differential pressure over the
flow-velocity pressure.

Gas or Air Flow

Potentiometer

Static
Pressure

Fig. 72 A Fechheimer directional pitot tube Fig. 73 Five-hole probe


COMBUSRON
Perlomance Testing of Steam Generators

verse can be calculated. The duct gas flow can typically desirable only in aerodynamic wind-
then be expressed as: tunnel studies, it is rarely needed for industrial
n flow evaluation.
Q, = A $ C Vi (cos 4)(cosJ/)
1.1 INSTRUMENT CALlBRATlON

where All devices should be calibrated to insure a


Q, = gas flow rate normal to the reasonable level of accuracy. The standard
plane of travers pitot tube will deviate from the theoretical Ber-
A = duct cross-sectional area noulli response of C, = 1.0 as a function of
V = gas velocity at one point wear. The Stauscheibe and Fechheimer probes
4 = yaw angle of flow-velocity produce values of C, which will also vary as a
vector function of velocity and wear. The hot-wire and
II.= pitch angle of flow-velocity hot-film response is typically some function of
vector V" where n is less than 1.0 and will vary with
n = total number of traverse dirtiness. Also, each device is dependent on
points - gas composition. Using these dynamic devices
i = any one point requires that the gas density be known and the
As shown by this equation, pitot probes which hot-wire requires the further evaluation of gas
do not account for flow directionality.can indi- thermal properties. Fortunately, the probes can
cate gas flow rates which are higher than are ac- be calibrated in air and analytically corrected
tually present. Selection of a probe should be for gas proper tie^.^^
based upon the directionality of the flow stream
at the measurement plane. Typically, in most
large boiler installations, the stack is the only To simplify energy calculations, flow turbu-
location where the directionality of the gas flow lence is usually considered to be a random, but
in both planes is less than 15 percent. However, isotropic process. Typically, flow in industrial
if a duct has less than this amount of flow direc- flues produces two distinct turbulence charac-
tionality along the pitch plane, the Fechheimer teristics described as rolling and' vortex flow.
probe can be used.
ROLLING FLOW
THE HOT-WIRE ANEMOMETER
Many installations include sharp corners , .
A device now often used for measurement of and other abrupt discontinuities which will
industrial fluid velocities is the hot-wire or produce the turbulent roll. This roll is charac-
hot-film anemometer. A single hot-wire system terized by fluctuating velocity components p
is described in PTC 19.5. The hot-wire ane- and v usually coplanar with the major flow vec-
mometer has the advantage of high sensitivity tor. A third component w is perpendicular to
at very low velocities, producing an electric the main-flow vector and is usually of smaller
readout and a measurement of turbulence. A magnitude. Isotropic turbulence, which is de-
disadvantage is its incapability of measuring fined as p = v = w, is difficult to find in indus-
directional flow in complex flow fields. It is trial work.
also fragile and can easily be broken in flues VORTEX FLOW
with heavy dust loading. This last problem can
be overcome by the use of a hot-film anemome- Although vortex flow can be produced by
ter. The hot-film anemometer operates with the stack entrances and fan discharges, it can also
characteristics- of the hot-wire, but sacrifices be produced by two rolling turbulence patterns
the ability to measure very high turbulent fre- intersecting at an angle. It is difficult to charac-
-quencies. Since high-frequency response is terize vortex flow in linear-velocity vector
COMBUSTION
Performance Testing of Steam Generators

notations. Typically, all turbulence is charac- the probe, close coupling of the readout device
terized when possible by the combined values to the probe, and a readout device of Tow dis-
of intensity (AU), frequency, and scale or size placement volume and inertia. The readout de-
of the major eddies. vice should also be caipable of producing an
electrical output signal. The signal can be re-
EFFECTS ON VELOCITY MEASUREMENTS
corded, for later analysis of the mathematical
Turbulence, when applied to a dynamic de- RMS effect on the velocity reading.
vice such as the standard pitot tube, will intro- An approach to the mathematical evaluation
duce a series of basic errors in the interpreted of turbulent effects on velocity readings is
reading. The first is mathematical in that the given in theASME Performance Test Code 19.5
reading produced by the pitot tube is a "head" Paragraph 57, which specifies isotropic turbu-
of V2/2g,while the result required is the veloc- lence and the RMS approach. It is relatively
ity or V.l.O Fig. 14 shows that, when measuring easy to apply this guide if the signal is sinusoi-
a turbulent or fluctuating velocity, the head dal. However, if the signal is not sinusoidal,
measured will be the root mean square (RMS) turbulence effect is difficult to evaluate. This
value of the wave form and will always be problem can be resolved by using a true RMS
higher than the head produced by the "aver- voltmeter to produce a true RMS reading inde-
age" velocity. Second, this problem is compli- pendent of the applied wave form.
cated by the flow dynamics of the resistance of The effect of flotv-streamvorticity has just the
the small-size pressure taps and tubing, the reverse effect on the velocity readout. Vorticity
compressi6ility of air or gas in the tubes (where represents a well-ordered flow field of signifi-
applicable), and the inertia of the indicating cant curvature. Flow curvature, in turn, pro-
fluid. These effects are additive such that, in duces a very definite radial pressure gradient. If
turbulent flow fields, when using fluid dy- the radius of curvature of the flow is of the same
namic devices, the velocity as read will always order of size as the measuring device, the de-
be higher than the actual velocity being vice will not be measuring either the correct
measured. ' dynamic or static pressures. Vorticity of small
size and high intensity can, therefore, contain a
VELOCITY READOUTS significant amount of dynamic or pressure en-
The problem of flow resistance can be par- ergy which will not be read if the measuring de-
tially corrected by using large sensing holes in vice is physically larger than the size of the
turbulent vortices being produced.
Unfortunately, there is no easy way to eval-
uate the effect of vorticity on measurements of
dynamic flow. Therefore, vorticity.shou1d be
minimized or eliminated by egg crates or
screens if no other flow-traversing station
Vel. without vorticity is available.
or
Vel. UMean Vel. Head Recommendations on reducing the major
Head sources of error in obtaining total gas-flow
rates, based on the above, are given in "Quanti-
Time tation of Stack Gas Flow" by C. L. Burton.21
Vel. Head =u2/2g= ( U ~ t A u ) ~ / 2 g DRAFTS AND PRESSURE LOSSES
- (AIR AND GAS)
.:~ . H . ~ / 2 g > U ~ ~ / 2 g
Draft and pressure losses in steam generators
Fig. 14 Pulsing-flow wave forms obtained in meas- and gas-treament equipment are recorded in
urements of fluctuating velocities routine and special test operations because
CoMBQsrION
Performance Testing of Steam Generators -

they indicate the system resistance which fans mon source of error in draft measurement, the
must overcome. importance of adequate line pitch, drain con-
Test measurement is usually of draft differ- nections and blowout fittings cannot be over-
ential rather than draft alone. Aside from con- emphasized.
venience in direct reading, a restriction must
be observed i n that draft measurement is with
reference to some atmospheric pressure. Since STEAM-GENERATOR
atmospheric pressure changes with elevation EFFICIENCY
(approximately one-inchwater gage per 100 ft),
all draft gages must be at the same elevation or The desire to achieve Process completion
readings corrected for elevation; otherwise, with ~ ~ x i economy
~ u m is basic in any tech-
an error of as much as 10 percent can be nical effort. One measure of performance in
introduced. steam generators is overall or gross efficiency
Measurement is with inclined and U-tube defined as the ratio of heat output (heat ab-
liquid manometers. Duct walls and casing con- sorbed) to heatinputa2*A heat-balance diagram
nections are usually suitable; the maximum as shown in Fig. 15 indicates the corollary is ef-
error due to impact would not exceed one ve- ficiency = 100 - percent losses.
locity head which is less than 0.1-inch water The ASME Performance Test Code for Steam
gage in most cases. Since condensation and ash Generating Units allows efficiency tests that
plugging in connecting lines are the most corn- use only the chemical heat in the fuel as input.
It does not, however, give an explicit definition
of boiler efficiency on such a chemical-heat
basis where heat credits are to be taken into ac-
count. In such practice, the heat diagram and
efficiency become as in Fig. 16.
Heat Input Heat Output
(Heat Absorbed) Present day units are large, and the wa-
ter, steam and fuel quantities associated with
them are so great that their measutement with
Losses
high accuracy is extremely difficult. Weighed
From the Heat-Balance Diagram
water and fuel tests are seldom feasible on
Input = Output + Losses these units, and the results with operating in-
strumentation are subject to commercial meter
By Definition. Output accuracies. Hence, the input-output method is
Percent Efficiency = lnput x 100 often unsuitable for an accurate -test of very
large stationary boilers, because it requires ac-
Input - Losses
- x 100 curate measurement of.the quantity and heat-
lnput
ing value of the fuel, and of the heat absorbed
Losses by the steam generator.
=k--)x100 Besides costing less, efficiency measurement
by the heat-loss method has several advantages
= 100 -(-x 100) over the input-output method. It is more infor-
mative since it establishes the individual losses
= 100 - Percent Losses for comparison with expected performance.
Regarding accu~acy,the_total losses are only
10 to 20 percent and fuel sampling and analysis
errors affect the end results slightly, whereas
Fig. 15 Basic heat-balance diagram in the input-output method these errors are
and efficiency relationships at least four or five times as significant. Also,
COMBUSTION
Performance Testing of Steam Generators

the basic losses measurements are simple: fuel measured, and the heat credits and losses to be
analysis, exit gas temperature, entering air assigned where not measured. In addition, al-
temperature, and refuse combustible content. location of responsibility for all performance
Minor items in the-heat losses can be obtained and operating conditions affecting the test
from sources suc5 as ASME Performance must be established, as well as acceptable
Test Code PTC 4 which contains detailed in- operating conditions, number of load points,
structions on test procedures and results the direction of test runs, and any basis for re-
calculations. jection of runs.
In order to achieve the objectives of a boiler Before a test is started, it must be determined
test i n accordance with PTC 4 , agreement must whether the fuel to be fired is substantially as
be reached, before the test, on the definition of intended. A reliable, accurate efficiency test for
efficiency, the general method (heat loss or purposes of equipment acceptance depends
input-output), the heatmedits and losses to be upon the fuel being in close agreement with
that for which the steam-generating unit tvas
designed. Significant deviations-in fuel con-
stituents and heating value can result in ap-

F' '
preciable inaccuracies in heat-loss calculations
and resulting efficiencies. Although the mag-
Chemical-Heat nitude of deviation that is tolerable is difficult
Input (CHI) Output
+ Heat,Credits (Heat to establish, it should be recognized that fuel-
analysis variation producing changes in heat-
Losses ing value on the order of 10 percent can alter
final calculated efficiency about 1 percent.
The Test Code does not include consid-
CHI + Heat Cred~ts eration of overall tolerances or margins on per-
= Output Losses formance guarantees; test results are to be
reported as computed from test observations,
with proper corrections for calibrations. Al-
By Definition, CH Efficiency
lowances for errors of measurement and sam-
-- Output 100 pling are permissible provided they are agreed
- CHI
upon in advance and are clearly stated in the
test report. The limits of probable error on cal-
- Chem~cal-HeatEfficiency, Percent culated steam generator efficiency are to be
taken as the square root of the sum of the
- CHI + Heat Credits - Losses x 100
CHI squares of the individual effects on efficiency.
Whenever allowances for probable errors of
measurement and sampfing are to be taken into
= (l +

CHI
)
H e a i y i t s - Losses
x loo
consideration, the reported test results shall be
qualified by the statement that the error in the
results may be considered not to exceed a given
plus or minus percentage. Table I11 taken from
= 100 - (Percent Losses - Percent PTC 4 is included as a guide to show the effect
Heat Credits)
on efficiency of measurement errors (exclusive
of sampling errors). The measurement-error
range in the table is not intended to be au-
Fig. 16 Chemical-heat input (CHI) is the higher thoritative but conforms approximately with
heating value of the fuel fired in the boiler above a experience. The values in the table are not in-
stated reference temperature. tended for calculation of test results.
COLdBUSPloN
k r t o m n c e Testing of Steam Genenton

Table 111. Probable Measurement Errors and Resulting Errors


in Efficiency Calculations*

Measurement Error in calculated


emr, Steam Generator
Measurement percent Efficiency, percent

Input-Output Method
(1) Weigh tanks (calibrated scales)
(2) Volumetric tanks (calibrated)
(3) Calibrated flow nozzle or orifice including
manometer
(4) Calibrated flow nozzle or orifice including
recorder
(5) Coal scales-batch or dump (calibrated) - 20.25 20.25
(6) Uncalibrated flow nozzle or orifice including +1.25 21.25
manometer
(7) Uncalibrated flow nozzle or orifice including 21.60 21.60
recorder
(8) Fuel heating value (coal) 20.50 20.50
(gas and oil) 20.35 20.35
(9) Reheat flow (based on heat balance calculations) 20.60 20.10
(10) Superheater outlet temperature (calibrated 20.25 20.15
measuring device)
(11) Superheater outlet pressure (calibrated 21.00 20.00
measuring device)
(12) Reheater inlet and outlet temperature 20.25 20.10
(calibrated measuring device)
(13) Reheater inlet and outlet pressure k0.50 20.00
(calibrated measuring device)
(14) Feedwater temperature (calibrated measuring 20.25 20.10
device)

Heat-Loss Method

(1) Heating value (coal)


(gas and oil)
(2) Orsat analysis
(3) Exit gas temperature
(calibrated measuring device)
(4) Inlet air temperature (calibrated measuring
device)
(5) Ultimate analysis of coal (carbon)
(hydrogen)
(6) Fuel moisture
COMBUSRON
Parformame Testing of Steam Generators

I ASME T E S T FORM
1
SUMMARY SHEET FOR A B B R E V I A T E D E F F I C I E N C Y T E S T PTC 4.1-a (1964)

1OWNEROF PLANT
TEST NO
LOCATION
BOILER NO. DATE
I
TESTCONOUCTEOBY OBJECTIVE O F TEST DURATION
BOILER MAKE 6 TYPE RATED CAPACITY
STOKER T Y P E A SIZE I

I WO I I I
30 H E A T OUTPUT IN BLOW.DOWN WATER bB~hr

~~~:L(tam26.11.n10)r(lt.m27-11.m21)ti~rm 30 k B / h r
OUTPUT 1000 'Not R.qu8r.d for Elfnco.no, T.stanp
F L U E GAS ANAL. (BOILER)(ECON) (&IR HTR) O U T L E T
32 1 CO, 15 VOL I t For Poant o f Ulesur.o.nt 5.. Po,. 7.2.8.I-PTC 4.1-1964
.
1
J4
I n
"2
- --
lrvnl I
34 co r. VOL
35 N, (BY DIFFERENCE) 5 VOL
36 EXCESS AIR
~ h f .Te.1 lo- (c-36) -7 b. o b l m MY.. 14)
Mm L. 47 SL. N.r Yo*. 1.Y. tW17
Pr1nl.d m U.S.A. (10174)

I I

ASME Performance Test Codes: Since its first publicationin 1915, ASME Performance Test Code 4.1, Steam
Generating Units, has been a recognizedguide for proceduresof boilertesting.The boiler boundary diagram
as well as the forms on the following pages are reproducedfrom the 1964edition of PTC 4.1.
. CoMBDSIlON
h d o m a n c e Testing of Steam Generators

PTC 4.1-b (1964)


ASME T E S T FORM
CALCULATIONSHEET FOR ABBREVIATED E F F I C I E N C Y TEST Reviredkptt&r,J96S

OWNER O F P L A N T TEST NO. BOILER NO. DATE

30 I H E A T OUTPUT I N BOILER BLOW-DOWN WATER = L B OF WATER BL0W.OOWN PER HR x I .---


ITEM 17
..... 1. ....... L B h

I
I L J
If inpmcticol to weigh refuse, this
item con he estinated as follows I ....
I I DRY REFUSE PER L B OF AS FIRED F U E L =
100
% A W I N AS F l R E O COAL
- %COMB. I N REFUSE SAMPLE \ NOTE: I F FLUE DUST 6 ASH
PIT REFUSE DIFFER MATERIALLY

t
t24 ITEM 43 FTEM
11 ITEM 2 3 1 { IN COMBUSTIBLE CONTENT. THEY
SHOULD BE ESTIMATED

II CARBON BURNED
PEZLBASFIREO
FUEL

DRY GAS PER L B


= --
100

IlCO, + 8 4 7lN, + COI


14.500
"'..'J= . . . . . . SEPARATELY. SEE SECTION 7.
COMPUTATIONS.

AS FlREO F U E L = x I L B CARBON BURNED PER L B AS FlREO FUEL + 5)


BURNED 3(CO, + COl
ITEM31 ITEM 33 + (ITEM 35 +
= llX..... ..... ......
267
.....
- co
3 x

EXCESS --
0, - ITEM)I
I T E M 33
AIR t = 100 x
1
.2682N2 - (0, - CO 1
= 100 x .........
1 ,2681 (ITEM 35) - (ITEM 33 - I

Blu/lb ' LOSS &'

UEAT LOSS EFFICIENCY AS FIRED


FUEL
nnv LOSS
%
1~ =

65
H E A T LOSS DUE
T O DRY GAS
L B DRY GAS
PER L B A5 XCp X (fIr9 - 'oar1 = ITEM
25 x0.24 (1TEM13)-(1TEM11'= -
65 X l W .
FlREO FUEL unit ............................... 41 ......
~~:STT~~~:~UF::Lo = :!$:GGBL
x [ (ENTHALPY OF VAPOR A T I PSIA L T GAS LVGI
-1ENTHALPY DF L I O U I D A T T AIR)] = ~ [ ( E N T H A L P YOF VAPOR
100
AT 1 PSI* b T ITEM 13) -(ENTHALPY OF L I Q U I D AT T ITEM l l ] ] ' ............ ......
67 H E A T LOSS DUE TO n,o FROM COMB. OF H~ = PH, x [(ENTHALPY OF VAPOR A T 1 PSI* 6 T GAS
LVG) - (ENTHALPY OF LIQUID A T T AIR]] 67
=
= 9 x lTEM [ENTHALPY OF VAPOR A T I PSIA 6 T ITEM 13)
...........
- IENTHALPY OF LIQUID A T
......
-r
41
lOG

......
1 1
loo 1 ITEM l l f l . .

68 H E A T LOSS DUE TO ITEM 22 ITEM 23


=
COMBUSTIBLE I N REFUSE
. . . . .x . . . . . . . . . . .
II 69 H E A T LOSS DUE TO
RADIATION'
- TOTAL BTU RADIATION LOSS PER HR
L B AS FIRED F U E L - ITEM za

1 1 70 UNMEASURED LOSSES " 1 ...... ...... 1


1 71 TOTAL
- I
..................
I I

71 EFFICIENCY = (100 - ITEM 71) .................

t For r8porou. d.l.mminot;on of ..r.rs ow .e Appendox 9.2 PTC 4.1.1964 -


.' I f loss..
Unm.osvr.d
o9,e.d
or. no, m.esu.d, us. ABMA Stondo,d Rodsolton Lo..
1ors.s lis1.d i n PTC 4.1 bul not teb~1ot.d obo..
upon rdu. for I1.m 70.
Chor,. Fip. 8, P T C 4.1-1964
me" by rrovided for by os%opninp0 muluolly

Thls Test Form rC-37) n a y be obtained from ASME, 34s E. 47 St.. W.c York. Y.Y. 10017
Printed xn U.S.A. (10/74)
-. - _ -
COMBUSTION
Performance Testing of Steam Genemtors

WASTE MEAT
OR LOW LEVEL HEAT OUT
ECONOMIZER

.ATER lNIECnO* OFF

FIG 1 STEAM GENERATING UNIT DIAGRAM

I
This diagram for boiler tests serves as a key to the numerical subscripts used throughout
Performance Test Code 4.1, Steam Generating Units
-
COMBVSTION e

Pwfomum Testing of Steam Generators

REFERENCES 9P. H. Dike, Thermoelectric Thermometry, 3rd ed.


Philadelphia: Leeds and Northrup Co., 1958.
'ASME Performance Test Codes: PTC 1. "General Instruc-
tions," P R 2, "Code on Definitions and Values"; PTC 3.1, 1Chromel and alumel are chromium-nickel and
"Diesel and Burner Fuels"; PTC 3.2, "Solid Fuels"; PTC aluminum-nickel alloys respectively. Constantan is a
3.3, "Gaseous Fuels"; PTC 4.2, "Coal Pulverizers"; PTC copper alloy.
4.3, "Air Heaters"; PTC 11, "FANS"; FlC 21, "Dust Sepa- llASTM Standards, Part44, "Magnetic Properties; Metallic
rating Apparatus"; PTC 27, "Determining Dust Concen- Materials for Thermostatic; Electrical Resistance, Heat-
tmtion in a Gas Stream," New York: American Society of ing, Contacts; Temperature Measurement; Illuminating
Mechanical Engineers, latest edition. Standards," Philadelphia: American Society for Testing
and Materials, latest edition.
2Code of Federal Regulations, Title 40, Parts 53-80, latest
edition. 12 American society of Mechanical Engineers, Fluid Meters.
3s. J. Kline and F. A. McClintock, "Describing Uncertain- Their Theory and Application, New York: American Soci-
ety of Mechanical Engineers, latest edition.
ties in Single Sample Experiments," Mechanical Engi-
neering, 75(1): 3-8, Jan. 1953. l3J. W. Murdock, "Power Test Code Thermometer Wells,"
Transactions of the ASME. Journal of Engineering for
4W.A. I.\'ilson, "Design of Power Plant Tests to Insure Reli- Power, 81, Series A:403-416,1959.
ability of Results:' Transactions of the ASME, 75: 405-
408, May 1955. l4 P. G. Mr. Hawksley, et al., Measurement of Solids in Flue
Gases, 2nd ed. London: The Institute of Fuel, 1977.
L. W.Thrasher and R. C. Binder, "A Practical Application
of Uncertainty Calculations to Measured Data," Tmnsac- '5 Harry James White.Industria1 Electrostatic Precipitation.
tions of the ASME, 79: 373-376, Feb. 1957. Reading, Mass: Addison Wesley, 1963.
S. Baron, "The Effect of Measurement Errors on Plant Per- 1614'. B. Gregory, "The Pitot Tube." Transactions of the
formance Tests:' Combustion, 25(8): 49-54, Feb. 1954. ASME, 25:184-211, 1904.
SJ. H. Born, Jr., "The Effect of Measurement Errors in the 17\tr. C. Rowse, "Pitot Tubes for Gas Measurement:' Trans-
Accuracy of Steam Generator Efficiency Calculators," actions of the ASME, 35:633-703, 1913.
ASME Paper 60-WA-301. New York: American Society of
Mechanical Engineers, 1960. IUE. S. Cole, "Pitot Tube Practice," Transactions of the
ASME, 57:281-294, 1935.
6"Orifice Metering of Natural Gas" ANSLIAPI 2530. AGA
Report no. 3. New York: American National Standards ln- '9R. G. Folsom, "Review of the Pitot Tube,'' Transactions of
stitute, latest edition. the ASME, 78:1447-1460, Oct. 1956.
American Petroleum Institute, Oil Pipeline Construction *O C. J. Fechheimer, "Measurement of Static Pressure,"
and Maintenance, 2nd ed. Austin: University of Texas, Transactions of the ASME, 48: 965-977,1926.
1973. 21 C. L. Burton, "Quantitation of Stack Gas Flow," Reprint
ASME Performance Test Codes, PTC 19.5, "Supplements from Journal of the Air Pollution Control Association,
on Instruments and Apparatus:' New York: American So- 22(8): 631-635, Aug. 1972.
ciety of Mechanical Engineers, latest edition. 22ASMEPerformance Test Codes, PTG4.1, "Steam Generat- '

'ASTM Standards, Part 26,,Gaseous Fuels; Coal and Coke; ing Units," New York: American Society of Mechanical
Atmospheric Analysis. D 2015, "Test for Gross Calorific Engineers, latest edition.
Value of Solid Fuel by the Adiabatic Bomb Calorimeter";
D 2961, "Test for Total Moisture in Coal Reduced to No. 8 BIBLIOGRAPHY
Top Sieve Size (Limited Purpose Method)"; D 3172,
"Proximate Analysis of Coal and Coke"; D 3173, "Test for Buna, Tibor, "Combustion Calculations for Multiple
Moisture in the Analysis Sample of Coal and Coke"; D Fuels," Transactions of the ASME, 78: 1237-1249, Aug.
3174 "Test for Ash in the Analysis Sample of Coal and 1956.
Coke"; D 3177, "Test for Total Sulfur in the Analysis Sam- Bostic, J. A., and Long, W. F., "Code Testing of Large Boil-
ple of Coal and Coke"; D3178, "Test for Carbon and Hy- ers: Input-Output or Heat-Loss Method," ASME Paper No.
drogen in the Analysis Sample of Coal and Coke"; D3180, 60-PWR-5. New York: American Society of Mechanical En-
"Calculating Coal and Coke Analyses from As-Deter- gineers, 1960.
mined to Different Bases"; D 3286, "Test for Gross Calo-
rific Value of Solid Fuel by the Isothermal-Jacket Bomb Cohen, L., and Fritz, W. A., Jr., "Efficiency Determination
Calorimeter"; D 3302, "Test for Total Moisture in Coal"; of Marine Boilers: Input-Output Versus Heat-Loss Method,"
Philadelphia: American Society for Testing and Mate- Tmnsactions of the ASME. Journal of-.Engineering for Power,
rials, latest edition. 84, Series A: 39-43, Jan. 19Q2:
ASME Performance ~est-codes,PTC 19.3, "Temperature Vuia, R. E., "Performance Testing of Large Steam
Measurement," New York: American Society of Mechani- Generators,"ASMEPaperNo. 62-WA-267. New York: Arner-
cal Engineers, latest edition. ican Society of Mechanical Engineers, 1962.
CHAPTER 23

Maintenance and Repair of Steam-Generating Equipment

AA good maintenance program is one of the


keys to reliability of any steam generator.
To be successful, such a program requires man-
nance should be designed into the plant rather
than retrofitted. All high-maintenance items
should have adequate laydown and work areas
agerial ability, expertise, imagination, plan- adjacent to the equipment. Models can help the
ning, training, and the commitment of top designer plan for accessibility (Fig. 1).
management. In addition, maintenance must Designers responsible for piping and electri-
be closely integrated with both the operation cal work must be aware of areas requiring
and power-station engineering functions. accessibility for maintenance. Often piping
and wiring are field-run from drawings having
notes advising construction personnel of spe-
MAINTENANCE FORESIGHT cial maintenance requirements.
Because plant layout can either facilitate or EQUIPMENT MANUALS: AN ASSET
impede a maintenance program, maintenance TO EFFECTIVE MAINTENANCE
personnel should be a part of the initial design
team to insure the plant layout facilitates main- It is important at the time equipment is pur-
tenance. Ideally, the person who will be ulti- chased to specify operation and maintenance
mately responsible for plant maintenance manuals which are complete, detailed, and
should be a member of the design team. specific to the piece of equipment supplied.
Only during the design stage can truly ad- Material that does not contribute to an under-
equate space be allocated for maintenance. As standing of the design, care, operation, and
equipment is located, maintenance personnel maintenance of the equipment should be ex-
must have space to remove the largest replace- cluded. Manuals should include
able part easily. The steam generator should a step-by-step disassembly procedures
have enough access doors so that all areas may step-by-step reassembly procedures
be entered easily for inspection. Access doors
and aisles also must be large enough to accom- preventive maintenance and lubrication in-
modate components that must be moved to a structions
maintenance area. Sufficient headroom is a lists of all special tools required and instruc-
must. tions on their use
- Overhead trolleys and cranes for mainte-
COMDWSTION
M.b,tonmce and Repair of Seam-GeneratingEquipment
--
.tabulated dimensional data on settings, cause different local conditions can alter wear-
clearances, and adjustments ing life drastically.
As orders arrive, responsible personnel
DETERMINING THE NEED FOR SPARE PARTS should inspect maintenance material carefully.
Often, a complement of spare parts is ordered A defective part may sit in a storeroom for years
with the initial purchase. If not, spares should before the defect is discovered-just at the time
be purchased before the equipment is placed of need. Also, to assure correctness and com-
in service. Items critical to plant production pleteness, all the incoming parts should be
should receive special consideration and, for checked against purchase orders before the
these items, it may be prudent to maintain parts are stored.
spare subassemblies. At time of purchase, the
owner should ask for complete instructions
from the manufacturer for error-proof ordering IN-SERVICE MAINTENANCE
of replacement parts. Catalogs specific to the To insure that a unit is available on demand
equipment and with exploded view drawings requires a constant effort by the maintenance
help in selecting appropriate spare parts. staff. They must implement a day-to-day pre-
In addition, there should be a system for ventive program while the unit is in opera-
tracking spare parts. Many large plants main- tion, establish a well-planned and properly
tain a replacement-parts inventory on a com- executed inspection program for scheduled
puter. If establishing an in-plant program is outages, and be prepared to handle all forced
not feasible, equipment manufacturers are pre- outages or equipment breakdowns as soon as
pared to rent computer services for tracking they occur.
spare parts supplied by them. On-line maintenance functions are just as
Manufacturers can provide guidelines for important as those performed during an out-
ordering spare parts based on field experience. age. If properly undertaken, not only do they
Even so, one must realize that all equipment of add to unit reliability, but they also save valu-
a given type does not wear at the same rate, be- able downtime. On-line maintenance includes
lubrication, seal and packing replacgment, and
repair of any component that has been removed
and replaced with a spare.
Proper lubrication is critical for rotating aux-
iliaries. Usually, the most complete part of any
correlated -maintenance manual is its lubrica-
tion instructions. The manufactuyer's recom-
,mendationsfor lubrication should be followed,
with substitute oils or greases used only if they
meet all specified properties. Each plant must
develop and adhere to routine lubrication
schedules. Major lubricant suppliers will work
with a plant staff to develop a program which
allows the most flexibility. Such a program
would minimize the types of necessary lubri-
cants, the amount of each kept in the plant, and
the best reordering schedules. This lubrication
is such an important part of any maintenance
-- .- program that records of work that has been
Fig. 1 Models help lay out a pulverizer done should be kept by using checkoff sheets.
lane for optimum maintenance access Good communications between the opera-
COMBUSTION
Maintenance and R e p L of Steam-GeneratingEquipment

tions and maintenance groups is essential. The PULVERIZER MAINTENANCE


day-to-day in-service maintenance program Although it is beyond the scope of one chap-
must be closely coordinated with plant op- ter to describe the maintenance of the various
erators, who are to inform the maintenance equipment that can be overhauled while a
crew of problems and potential problems. For generating unit continues in service, a major
example, maintenance should be informed of component usually overhauled on-line is a
slight drops in pressure or temperature which pulverizer. The life of mill parts depends on
could indicate inefficient operation or deterio- many factors which vary considerably from one
ration of machinery. In addition to such visual plant to another. The main factors are the abra-
signals, operators inspecting equipment often sive characteristics of the coal, operating hours
detect problems by unusual sounds, smells, or of individual mills, and mill loading as a per-
tactile sensations. cent of maximum capacity. Although plants
Similarly, the maintenance crew must in- usually install spare pulverizers, two or more
form operators of any equipment being re- of which may be idle at reduced boiler loads,
paired. Often in the case of several sootblowers pulverizer outage time for maintenance should
needing repair; the operator decides which be kept to a minimum so that all pulverizers are
blower is crucial to operation and requests always ready for service.
maintenance to give that blower priority. Because an effective pulverizer maintenance
program must be adjusted on the basis of actual
plant operating experience, it is essential to
maintain an accurate log of each pulverizer's
running time, stoppages for removal of foreign
material, maintenance work and inspections.
Maintenance must be staggered so that all pul-
verizers do not require work at the same time.
Rolls and grinding rings are the major re-
placeable items. [Later in this chapter, there is a
further discussion of roll and ring wear.) With
good planning and preparation, it is possible to
overhaul a pulverizer, renewing the ring and
rolls as well as repairing or replacing other
wearing parts, in a few days.
As part of its spare-parts complement, a plant
should have three complete journal assemblies
(Fig. 2). Frequently, such assemblies are inter-
changeable on all mills in the station and can
be stored on transport dollies in the mill over-
haul area. Following a mill overhaul, worn jour-
nal assemblies that have been removed are
rebuilt. The worn grinding rolls may be re-
placed, or may be resurfaced with weld mate-
rial to recreate the original shape. A weId
material such as COMBUSTALLOY" can give
four to five times the life of the original
NI-HARD roll material.
To accommodate transport of worn journals
Fig. 2 A plant should have three complete journal and overhauled assemblies simultaneously, six
assemblies stored on transport dollies transport and storage dollies should be on
hand. Storing segmented bowl-ring assemblies maintenance program. Although subsequent
on pallets (one complete ring per pallet) per- annual outages will concentrate on repair
mits hoisting to the mill platform in one lift. work, a review of these three procedural items
Frequently used bolts, nuts, and washers are must be part of every outage.
kept in bins in the mill overhaul area. Whether accomplished by plant personnel or
Once a mill has cooled and been tagged a maintenance contractor, a well-planned out-
out-of-service, access doors are removed. To age program begins as much as a year before the
further cool mill parts, an air mover often scheduled downtime. The planning and the
is used to ventilate the mill. When all three jobsite organization must include well-defined
journal assemblies have been removed, communication channels (Fig. 3). With an out-
there is free access to the inside of the mill, side contractor, advance communication with
and a worn bull ring or worn liners can be the plant staff is crucial to the success of
removed rapidly. When all obviously worn the operation. The plant staff must follow the
parts have been stripped from the mill, the re- contractor's work closely so that spare parts,
maining parts are carefully inspected for repair engineering changes, and new material selec-
or replacement. tions are expeditiously handled.
When the repair work inside the mill has THE PRE-OUTAGE STAGE
been completed, the overhauled journal as-
semblies are installed. All access doors are Several months before a scheduled outage,
closed, the mill is cleared of all "hold" tags, the group responsible for the inspection and
and it is started without coal to facilitate ad- the work must jointly plan the inspection
justment of the grinding-roll-to-ring clearance. schedule with plant personnel. In preparation
When this adjustment has been completed, the for the outage, personnel assemble tools, scaf-
mill is released for normal service. folding, spare parts and other required mate-
rials. Also during this period, the engineers in
charge of work during the outage examine
THE ANNUAL OUTAGE existing unit operating and maintenance rec-
For any power plant, the major part of its uni- ords, and discuss with all plant, personnel
fied maintenance program is the scheduled those areas requiring particular attention.
annual maintenance outage. The objectives of
PRE-OUTAGE INSPECTION ITEMS
the first-annual planned outage are to inspect
equipment, recommend repairs, and establish a Usually, while the unit and its auxiliaries are
data base from which to develop a preventative still operatingia complete visual inspection is

Outage Coordinator
I
I I
Construction Services Vendor Engineering Technical Services
Construction Manager Representatives Writer Lead Service
- Engineer

Construction Service Engineers


Superintendents Field Accountant Field Cost
Engineer Days
- Nights
Days- - Nights
-

Fig. 3- - A successful outage must include a good organizationwith well-defined communication channels
CObLBUSRON ,
Mahtenance and Repair of Steam-Generating Equlpment

performed to detect any obvious items requir- wall panel outlets, are checked to isolate any
ing maintenance or more detailed investiga- defects requiring repair during the outage.
tion during shutdown. All items are noted and Readings from expansion trams in important
a list compiled. areas should be recorded for comparison with
Operational checks of certain equipment and readings taken during the outage when the unit
systems also are conducted to ensure each is is cold, and after its return to service. These
functioning properly--or requires adjustment, readings are used to confirm free and proper
repair or replacement. Included are expansion of the unit.
8 fuel-burning equipment such as tilting mech- SCAFFOLDING
anisms, windbox dampers, coal gates, and oil For outages in which extensive inspection
or gas valves and repairs to the furnace are planned, fixed
8 furnace-safety-control and ignition systems scaffolding temporarily installed both outside
and inside the furnace can save time and
8 combustion and feedwater-control systems
money. In the past, craft personnel have ex-
8 sootblowing equipment * perienced considerable difficulty using sky-
In addition, the settings on safety valves are climbers and have questioned their efficiency
checked. Control and isolation valve perform- and safety. When extensive repairs are planned
ance is verified and any packing leaks re- for furnace and penthouse areas, scaffolding
corded. The condition of activators is checked rental fees are more than offset by savings in
to be sure oil seals are secure and lubricating oil working-hours. Adapted for quick installation,
is not contaminated with water or flyash. such scaffolding is modular and made of tubu-
All permanent thermocouples, such as those lar carbon steel with steel loops at the end of
on superheater and reheater tubing and water- each section (Fig. 4). Fixed-length sections are

Fig. 4 Interior view of unit with modular scaffolding system. Note easy entrance and access to all areas.
-
COMBUSTION
M.Menance and RepaC of Seam-Generating Equipment

safety-locked to one another by inserting steel links, at the sootblowers for lance removal, and
wedges into the loops. at the economizer outlet ductwork.
Basically, the scaffolding for interior access As typical views of scaffolding show (Fig. 4
provides a solid platform near the top of the and 5),maintenance and repair personnel have
furnace. Typically, ten or more scaffold towers, easy access to the unit during a n outage. This
each with three working platforms, are po- provides two significant improvements over
sitioned at the front of the furnace adjacent to previous methods. Repair personnel can enter
each side of the superheater division panels. the interior more safely than by using cable-
Scaffolding is also provided across the unit at hung equipment. Equally important, continu-
the front and rear of the superheater or reheater ous access to'all areas is possible and various
pendent assemblies. crafts do not have to compete for access. This
Furnace waterwalls are scaffolded from the significantly reduces the time required to
lower slopes to a point approximately 6 feet transport personnel and materials to areas to be
below the lowest element tubing of the repaired. Finally, scaffolding allows a more
superheater division panels. Walkway levels complete and thorough inspection.
are provided at approximately 7-foot intervals, THE OUTAGE STAGE
beginning at the bottom wall-blower elevation
and continuing to the top elevation of wall During the outage, every portion of the unit
blowers. An extension of the waterwall plat- requires inspection. Scheduled repairs are then
form at convenient working elevations pro- accomplished by a critical-path analysis to as-
vides interior access to the windbox. Exterior sure all repairs are completed. Key areas to be
scaffolding also can be used at the penthouse inspected are the pressure parts, the fuel-firing
front wall near the roof header and superheater and transport equipment, boiler casing and

Fig. 5 View of vertical modular scaffotding system


COMBUSITON
Maintenance and Repair of Steam-Generating Equlpment

structural supports, and such sub-systems as Any lower waterwall headers large enough
ash-handling and sootblowing equipment. to have access ways should be inspected.
PRESSURE PARTS: EXAMINATION Waterwall distribution orifices and screens are
OF EXTERNAL SURFACE-S examined closely for deposits. Orifices are
Within the furnace, external surfaces of tub- checked for proper size with golno-go gages.
ing are examined for erosion, metal wastage, Samples of furnace-wall tubing may be re-
swelling or developing problems in critical moved from various locations a short distance
areas such as the firing zone and near soot- above the uppermost fuel nozzles. Such sam-
blowers. Suspicious areas are investigated fur- ples are examined internally to determine sur-
ther by cleaning with sandblasting and then face condition and to detect any deposits.
checking wall thicknesses by micrometer, or
measuring thicknesses ultrasonically. See Fig. FIRING EQUIPMENT
6. This type inspection also covers During the internal inspection of the furnace,
w critical superheater and reheater sections the condition of the fuel and air nozzles is de-
8 economizer tubing termined and any serious deterioration (Fig. 7)
w steam-cooled-wall surfaces and waterwall noted for replacement or repair.
hanger tubing in the gas passes. Tilting fuel and air nozzles should be oper-
PRESSURE PARTS: EXAMINATION ated through their range while being observed
OF INTERNAL SURFACES from inside the furnace. Binding, nonparal-
The steam drum must be entered and lelism or other malfunctions should be cor-
thoroughly inspected for deposits, loose parts, rected. The tilt mechanism is also inspected
erosion, and areas that may allow internal by- from inside the windbox to determine the con-
passing of water or steam. Conditions dition of the linkage.
found in the boiler drums may dictate inspec- Windbox dampers are inspected from within
tion of waterwall headers and other internal to determine that they operate through their
surfaces for evidence of corrosion or deposits. normal stroke and that damper-blade move-
ments correspond correctly to external linkage
movement. No binding should be evident.
If there are retractable oil guns, the retracting
cylinders must be operated to verify proper
movement. The clearance of oil guns and con-
dition of the ignitor-horn also should be
checked from inside the furnace.
Extensive pulverizer maintenance is not al-
ways scheduled during an outage. In any case,
a general inspection of the mills must be made.
Particularly, inspect all shutoff dampers re-
lated to the pulverizers for proper operation.
Coal-pipe elbows in critical locations are ex-
amined internally for wear. In particular, the
final elbow at the fuel nozzle must be inspected
and the wear pattern noted. Defective kicker
blocks should be replaced or relocated. Riffle
distributors throughout the system are in-
spected for wear and replaced or rotated as
Fig. 6 Tubing is measured ultrasonically necessary. Coal-pipe orifices are checked for
for wall thickness signs of wear.
COAQVSEION
M.brtmance m d Repair of Steam-Generating Equipment

The feeders must be inspected as recom- OTHER AREAS OF CONCERN


mended by the manufacturer to implement any Drip shields and seal plates at the furnace
necessary adjustments and maintenance. bottom must be inspected and repaired. The
bottom-ash hopper and the balance of the
CASING AND ROOF ENCLOSURE
ash-handling system are inspected as recom-
The roof enclosure also is inspected and the mended by the manufacturer.
condition of pressure parts, hangers, and other To the extent possible, all gas and air ducts
pressure-part supports is recorded. Any dam- are examined internally and externally for cor-
age or leakage of the furnace roof casing and rosion, erosion and leakage (Fig. 8).
seals should be corrected. Condition of insula- The entire sootblon~ingsystem is checked-
tion and pipe seals should be recorded. any malfunctioning equipment noted during
The roof support steel and hanger rods with- the pre-outage operational check is further in-
in the air space between the roof deck plates vestigated. During the internal furnace inspec-
and insulation are checked for corrosion. tion, sootblower effectiveness and any tube
Any leaks or damage of the external casing of erosion from sootblower operation are noted so
the entire unit noted during the pre-outage that sootblowers can be adjusted as necessary.
stage are repaired as necessary. Boiler-water circulating pumps are in-
The skin casing and seals within the dead air spected to manufacturer's recommendations.
space behind the deflection arch are inspected Air-heater elements, seals, bearings, drives,
as are the casing, seals, and support steel with- and lubrication systems are checked.
in the dead air space beneath the sloping fur- Malfunctioning or leaking safetyvalves noted
nace bottom. All are inspected to determine during the pre-outage operational check must
general conditions and to note any mainte- be investigated and corrected.
nance that should be performed. The control system inspection includes

Fig. 7 Fuel and air nozzles are inspected Fig. 8 Look for corrosion, erosion or
from inside the furnace leakage on fan casings
COMBUSTION
Maintenance and Repair of Steam-Generating Equlpment

calibration checks, stroking of drive units, and All valves repaired or repacked during the
a general inspection of system components. outage should be observed for proper operation
Any malfunctioning components of the fur- and performance. Re-tighten all packing nuts
nace safety system found during the pre-outage with extreme care after each valve has reached
operational check are further investigated. normal operating pressure and temperature. Do
Flame-scanner tubes are removed, inspected, not touch a valve if there is any indication that
and cleaned thoroughly. the valve was not packed properly.
All fans must be inspected (Fig. 9) for the Take an inventory of all recommended spare
condition of the bearings and their lubrication parts and forward a list of shortages to plant
as well as the rotor and the associated dampers purchasing for ordering.
andlor inlet vanes. In addition, the induced-
draft fans are examined for erosion, corrosion
andlor deposits. Finally, all observation ports
and access doors are checked for tightness. -
THE POST-OUTAGE STAGE
After the unit is returned to service, the re-
pair work is checked under operating condi-
tions. For example, all permanent thermo-
couples on superheater, reheater, and wa-
terwall individual tubes are observed to
confirm proper operation.
As the unit is brought on the line, all control
systems should be observed functionally to
make any necessary adjustments (Fig. 10).

Fia. 10 Control svstems are adiusted


Fig. 9 Fan rotor is removed for inspection asthe unit is retumed to service
COMBUSTION
Maintenance and Repair of Steam-Generating Equipment

DOCUMENTATION methods. It is the basis for all subsequent out-


Documentation is an important phase of any ages. It is the source of spare-part requirements.
maintenance program. All findings, both good Outage documentation includes detailed
and bad, should be noted in a comprehensive reports, both quantitative and qualitative, de-
report which covers all pre-outage, outage, and scribing conditions of both pressure and non-
post-outage inspection and repair. pressure parts of the unit. Fig. 11 shows a
typical section of an outage report.
'THE PRE-OUTAGE REPORT The engineer in charge of the outage should
The pre-outage-inspection documents con- compile the report. An effective report might
tain a review of unit history, visual inspections, include sketches, marked prints, or photo-
a walkdown of the unit while in operation, graphs which can be useful where ideas or con-
a checkout of all thermocouples, ignitors, cepts rather than physical objects are being
fuel-burning equipment, safety valves, and described for the record.
sootblowers. Any items requiring further in- THE POST-OUTAGE REPORT
spection or repair are noted.
The post-outage documents describe con-
THE OUTAGE REPORT ditions immediately after restart, such as
The outage report is tangible evidence of all thermocouple temperature measurements and
that transpired. It is the basis for any neces- expansion data. The final and most important
sary changes in operation, design or repair documentation lists the recommendations of

Elevation

Corner
1&2

Corner
3&4

Corner
5&6

Erosion
11/2" Less Than 1" Erosion
1" Erosion X Warped Distributor Plates

Fig. 7 1 Typical section of outage report


COMBUSTION , -
Mahtenance and Repair of Steam-Generathg Equipment

the inspection team, as well as an engineering tant that the cables be cooled if they are to pass
department review of those findings. Such rec- through the hot enclosure; compressed air is
ommendations include spare parts to order in the usual cooling medium. If the damage is ex-
preparation for the next outage. tensive and requires-major repair work, more
After all the planning, inspection and doc- elaborate scaffoldtng-may be necessary.
umentation have been completed, a critique The importance of failure records cannot be
provides all those involved in the outage over-emphasized. The cause of a single failure
an opportunity to review their findings and de- may not always be determined and an isolated
termine improvements for future outages. A random failure may be of little significance. But
frank, open exchange sets the stage for the next several similar failures may indicate serious
outage and also the plan for continuing work problems affecting future availability. Good
throughout the coming operating period. maintenance, then, requires not only that a
failure be repaired but also that every effort be
made to determine the root cause of the failure.
THE FORCED OUTAGE To retrieve information easiIjr, an effective
record-keeping procedure separates the logs.
A forced outage requires as much or more for the superheater, reheater, economizer and
planning than a scheduled outage, but by its waterwall. Patterns and trends are easily spot-
nature, it allows the least time for planning. ted when presented graphically such as on
Consequently, a plant maintenance group must sketches showing elevation and plan views
be prepared with an emergency plan formu- (Fig. 12). Numerals or dates of the chronolog-
lated before a failure occurs. This plan should ical occurrence of a failure can be added.
be in writing and periodically updated.
The plan-shou-ld list alternatives such as
qnother division or utility, use of alternate
REPAIR WELDING
production methods, or purchase of power. Be- FOR PRESSURE PARTS
cause dow,ntime is critical, plan details and Plant management and maintenance super-
schedule must be worked out immediately. visors must bear in mind the legal formalities
Plant personnel should have lists of other criti- involved in the repair of boiler pressure parts.
cal work that can be done during an outage. In the United States, the National Board In-
Pressure-part failure is a major cause of spection Code (NBIC) provides guidelines and
forced outages. Since the unit must be cooled rules for repairs and alterations to boilers and
before it can be entered, the cooling time can be pressure vessels after they have been placed in
used for planning. As the repair of the failure service. NBIC rules, including the involvement
-
will be the critical path in returning the unit to of the Authorized Inspector (AI), are only man-
service, other maintenance must be done only datory in those states, cities, and provinces
if it does not interfere with the repair. which have adopted the NBIC, or where re-
To save time during cool-down, crews can quired by the owner or the insurance carrier.
move parts, tools and scaffolds close to access Jurisdictional requirements involving the A1
doors. Usually, it is possible to determine the vary widely. Most jurisdictions require the
area of the failure and its general magnitude owner to obtain the AI's acceptance before re-
from the outside and, if a leak is small, sky- pair or alteration. However, the NBI Co.de
climbers, bosun chairs, or two-man scaffolding places the responsibility of coordinating the
are generally adequate. If the steam generator acceptance inspection on the contractor.
has cable holes extending through the roof en- Anyone that is required to do pressure-part
closure, considerable time can be saved be- welding-owner, contractor or manufac-
cause the roof enclosure does not have to be turer-must use approved welding procedures
cooled for entry. For safety reasons, it is impor- done by qualified welders.
COMBUSTION
Maintenance and Repair of Steam-Generating Equipment

GUIDELINES FOR WELDING REPAIR Use a clamp or guide lug to hold one end of
OF LOW-CARBON STEELTUBES the replacement tube in alignment while the
first weld is made. Do not tack weld both ends
A damaged tube should be cut out at least
of the replacement tube, particularly if the
2 in. on each side of the defective area. The
existing tubes are rigidly supported. As a gen-
minimum replacement tube length should be
eral rule, first complete the weld at the lower
no less than 6 in.
Backing rings must not be used to weld any end of the replacement tube. Do not start weld-
ing the upper end of the replacement tube until
heat-absorbing tubes carrying water or a mix-
ture of steam and water. Without a backing both the replacement and existing tubes have
cooled to ambient temperature.
ring, the first pass of the weld must be made by
gas tungsten arc or oxy-acetylene. The weld GENERAL GUIDELINES
passes may be completed by either process, or FOR ALLOY TUBE REPAIRS
by shielded metal arc.
Window welds may be used.for repair work if If a damaged alloy tube must be replaced, it is
access is difficult (Fig. 13). The first pass of a always preferable to weld the replacement tube
window weld must be made by gas tungsten arc to an existing tube end of the same alloy and the
or oxy-acetylene, same wall thickness.
Fit-up of the weld joints is important. Al- Before removing the damaged tube, check
though it is difficult to obtain accurate cuts on the manufacturer's material diagram and locate
furnace tubes, it is important to get the existing shop welds used to join the damaged length to
tube ends squared and correctly chamfered, tubes of different material or different wall
and to cut the replacement tube to the correct thickness. If at all possible, make the cuts to
length. A tube-end scarfing tool should be used remove the damaged tube at least 6 in. from the
when possible. shop weld, thus leaving a "safe end."
Allow for shrink in welding. Remember that CUTTING OUT A SHOP WELD
the weld metal and parent metal are melted in
the welding process and the molten metal If necessary to cut out a shop weld joining
shrinks as it solidifies. (A butt weld in a tube tubes of different material andlor wall thick-
will shorten the total tube length about 1116 in.) ness, special attention must be paid, since all

Front Left Rear

Sootblower El 740'-0"
Assy. No. 219 from Front
Assy. No. 219 from Front
Right Sidewall

Fig. 12 Waterwall failure locations (viewed from inside boiler)


COUUSTION
Maintenance and Repair of Steam-Genemtlng Equipment

qualified butt-welding procedures require the made for expansion from preheating which
two tube ends to have the same internal diame- will close the root gap slightly.
ter (ID) at the weld root. In some cases, the For shielded metal-arc welding with a back-
thicker wall tube may be bored to match the ID ing ring, it is essential that the root-gap open-
of the thinner w.alLtube as shown in Fig. 14. But ing be sufficient to assure full penetration and
the thicker wall tube may be bored only if the fusion with the backing ring during the first
strength of the tube, after reducing the wall pass. For gas tungsten arc welding, a zero
thickness, is at least equal to the strength of root-gap opening is permitted. However, there
the thinner wall tube at the same operating must be no pressure exerted between the two
temperature. tubes. It is advisable to allow enough clearance
A ferritic-alloy tube must not be bored to to avoid actual contact at the root-gap opening
match a thinner-wall austenitic alloy tube. The after the two tubes are preheated.
only satisfactory method is to use a connector REPAIR OF TUBES
of austenitic alloy tube having the same wall ROLLED INTO HEADERS OR DRUMS
thickness as the ferritic-alloy tube. One end of If a replacement length of tubing requires a
the connector is bored to match the wall thick- weld within 2 or 3 feet of the rolled end, remov-
ness of the existing austenitic-alloy tube. ing the rolled joint and cutting the replacement
FIT-UP AND SHRINK ALLOWANCE tube to fit into the tube hole will avoid the
Shrinkage in welding alloy tubes is similar to stresses from weld shrinkage. This procedure
that for carbon-steel tubes. Allowance must be is particularly effective in straight tubes or

I Defective 1

Flame Cuts to
Remove Defect~veTube

I Section A-A I

kwindow w i d t h b
Must Allow for Weld~ng
Access at Sides

Fig. 13 Window welds may be used to repair Fig. 14 Fitup detail to install replacementtube
damaged tubes when access is difficult section with wall thicker than existing tube
COMBUSTION
Maintenance and RepakofSteam-Generating Equipment

tubes welded to adjacent tubes. In cutting the blisters can be worked d o ~ v nto the original
replacement tube, allow for the normal projec- tube radius. Follow these general guidelines:
tion through the tube hole plus 1116 in. for Remove the damaged tube, then carefully cut
shrinkage of the weld. Complete the weld in the away enough of the bar or fin to allow chamfer-
replacement tube, allow the tube temperature ing the tube end for welding around the sides of
to cool to ambient, and then roll the replace- the replacement tube joint (Fig. 15).
ment tube end into the header. After the tube welds are completed, weld the
bar or fin to the replacement tube. If the gap be-
REPLACING A TUBE LENGTH
IN A FIN-WELDED FURNACE WALL tween bar or fin is too great for easy bridging,
insert a 1ow:carbon-steel welding rod for a
First, the bar or fin along the damaged tube filler. The spaces in the bars or fins, at the tube
length must be removed by flame cutting. Be- joints, are built up with deposited weld metal.
cause it is difficult to make a clean flame-cut in Be sure no cracks exist in these deposits before
the weld attaching a bar or fin to a tube, it is making the final weld to the tubes.
preferable to make the cut just at the edge of
the weld, approxiniately 118 to 114 in. from the REMOVAL OF TUBE SAMPLE
damaged tube. FOR METALLURGICAL
Overheating of the tube may have caused a OR CHEMICAL EXAMINATION
longitudinal crack. In this case, the tube has When a metallurgical or chemical examina-
swollen and the wall thickness reduced. If vi- tion is necessary to determine the cause of tube
sual inspection indicates swelling and reduc- failure, special precautions are required to re-
tion of the tube-wall thickness at the crack, a move a defective tube from any type of
complete replacement of the damaged tube welded-wall furnace. The defective portion of
length is the best solution. On the other hand, a the tube should not be heated by flame cutting.
circumferential crack suggests a failure due to To avoid such heating, the tube should be
excessive stress applied by expansion restric-
tion, bending, or fatigue. Although such cracks
can be repaired by welding, unless the cause of Good Replace Good
failure is diagnosed and corrected it is possible
for a similar failure to occur at or near the origi- one,,,$;
nal crack. weld to adjacent
REPAIR OF TUBE BLISTERS
tubes. Do not weld
to replacement
tube. Similar pair of l
Internal deposits cause blisters on the fur- bars may be used at
nace wall or boiler tubes. Generally, they occur lower end of replace- I

in boilers operated with a high percentage of ment. Wedges be-


. tween tube and fin
make up in the feedwater. A blister forms be- will maintain
cause an internal deposit increases tube metal alignment.
temperature until metal creep occurs. As the
heated area swells, the internal deposit cracks Flame cut just out-
off and the tube metal temperature returns to side \veld bead
normal. The process may be repeated several defective tube.
times before the blister ruptures. Reweld fins after
Commonly, a large number of tubes are completing tube
welds.
blistered and not noticed until one of the
blisters cracks open. To avoid a massive ..

tube-re~lacementjob* particularly where re- Fig. 15 Welding detail forreplacing a tube length in
placement tubes are not immediately available, a fin-welded furnace wall
COMBUSTION
Maintenance and Repair'of Steam-Generating Equipment

flame-cut at a point at least 6 in. away from the PUMP MAINTENANCE


damaged area. In a furnace wall with bars or
Various types of pumps are used with a steam
fins welded between tubes, it is preferable to
generator. For high-pressure recirculation-
cut the bars or fins with a saber saw or thin disc
metal-cutting wheel. If these tools are not type boilers, single-shaft centrifugal pumps
available, the bars or fins may be flame cut ap- driven by a wet-stator induction motor move
proximately 112 in. from the tube length re- boiler water at pressures and temperatures ex-
ceeding 4000 psig and 650F. Because the
quired for the sample.
After removing the damaged tube from the motor is enclosed within the pump casing and
is filled with boiler water at full system pres-
furnace, the ends may be cut off to reduce ship-
sure, no seals are used between the pump and
ping weight of the sample. Use a dry hacksaw.
motor. A baffle, plus close clearances between
Cutting oil will contaminate any deposits and
the shaft and motor casing, prevents solids in
render a useful chemical analysis impossible.
the boiler water and hot water from passing
Be sure the sample is clearly marked to show
into the motor. Through an-external heat ex-
which end was at the top and which side was
changer, recirculating water in the motor cav-
toward the fire (Fig. 16).
ity cools the submerged motor.
Although manufacturers generally recom-
COMPONENT MAINTENANCE mend an annual inspection for such pumps,
local conditions help determine the proper
Although it is beyond the scope of this treat- interval for a given unit and installation.
ment to describe the overhaul of all steam- Periodic inspection of the pump in service usu-
generator components and auxiliaries, a brief ally reveals when an overhaul is needed. Some
discussion of pump, fan, and control-system indications are an above-normal noise level,
maintenance is offered for general information. high motor temperature, vibration, unusual
starting or fluctuating current, reduced head
across the pump, leaks from the pressure cas-
ing, or a drop in the winding resistance.
At most stations, one of the pumps is disman-
tled every few years. During disassembly, the
motor and pump impeller are lowered as one
assembly. The impeller can then be removed
from the shaft and the rotor assembly taken
from the housing. The assembly is placed
horizontally on V blocks at floor level. An
inspection is made with as much disassembly
of subsections as observation dictates.
Although other pumps on steam generators
might handle a cooler liquid at essentially
ambient conditions, they may require much
higher maintenance if the fluid being handled
is more corrosive or erosive than pure boiler
water. For example, heavy-duty centrifugal
pumps are used to move a slurry solution of
limestone and flyash in flue-gas desulfuriza-
tion systems. The wear rate of these pumps can
Fig. 16 Make sure tube samples be substantial and is a function of the severity
are clearly marked of the pumping duty and of the abrasive
COMBUSTION
Maintenanceand Repair of Steam-Generating Equipment

properties of the materials handled. The life of flyash can penetrate the bearing lubricant,
wear parts such as impellers and liners varies damper bearings must be inspected frequently
greatly. For instance, steel impellers and and cleaned when the lubricant is contami-
bodies have had very short life with highly nated. Dampers not in constant use, such as
acidic and abrasive solutions. If a new make or isolation dampers, may freeze in place and
different type of pump is used, it should be become useless. Exercising idle dampers can
opened regularly and the parts inspected to es- avoid this condition.
tablish the life of wear parts. Some erosion of induced-draft fans on coal-
When handling abrasive fluids, parts other fired boilers is to be expected. For centrifugal
than the impeller and housing are also subject fans, erosion is generally most severe at the
to excessive wear. Shafts and gland seals and leading edge of the blades and at the joint be-
even the bearing must be inspected much more tween the blades and center plate. Axial-flow
frequently. Bearing housings should be opened fans have the heaviest erosion on the front
and inspected at least once a year. outer tip of the blade. Erosion primarily affects
the structural integrity of the fan, but it can also
FAN MAINTENANCE
cause imbalance of centrifugal fans.
Steam generators require many types and For severe duty, replaceable wear plates are
sizes of fans. The largest are used for forced- bolted or welded to centrifugal fan blades. At
and induced-draft ser;ice, and for moving pri- each outage the wear plates are checked and are
mary air to pulverizers for drying the coal. replaced when worn halfway through. If wear
These fans can be of either centrifugal or axial- plates are allowed to erode to a point that dam-
flow design, as described in Chapter 14. Bear- age occurs to the blade material, repair cost and
ing failure, one of the biggest problems with
fans, usually is caused by either poor lubrica-
tion or excessive vibration. As stated previ-
ously, it is important to follow the lubrication
requirements specified by the manufacturer.
If it occurs when a fan is initially started, vi-
bration may be the result of inadequate foun-
dations or unsuitable ductwork configuration
or design. On the other hand, after operation,
rotor imbalance often causes vibration. The
imbalance can be a result of flyash accumula-
tion in eroded blades, water, blade erosion, or
uneven thermal growth of the wheel. But the
possibility of changes in alignment or shifting
foundations cannot be discounted.
An outage inspection program permits
correction before a dangerous condition exists.
The blades and associated ductwork systems
should be examined for erosion, corrosion, or
cracks (Fig. 17). If cracks are found in any
blade, it is wise to magnetic-flux all of the
blades for cracks. Fan dampers are as important
as the fan itself, for deteriorated dampers can
cause poor fan control.
Damper bearings are exposed to the same
hostile environment as the fan wheel. Because Fig. 17 Fan rotor blades with heavy erosion
COMBUSTION
Maintenance and Repair of Steam-Generatlng Equipment

outage time can be greatly increased. Such a program should begin with a con-
Although wear plates can reduce the effects tinuous process of recalibration, repair or
of erosion, it is controlled best by flyash re- replacementwhile the unit is on the line. By re-
moval upstream of the fans. Again, an effective lying on a redundant component, transferring
maintenance program determines and corrects a confrol loop to manual, or by temporarily
the cause of maintenance sometimes initiated defeating the component's function, most con-
by equipment other than that actually ex- trol system components can be recalibrated,
periencing the problems. repaired or replaced on line (Fig. 18). Periodic
A most important part of any fan repair is the maintenance can prevent unit high or low
rebalancing and final cleanup. Besides the furnace-pressure trips caused by drifting cali-
normal dangers of rotating equipment, fans bration of transmitters and switches, or by
present an additional hazard in their ability to plugged sensing lines between the furnace tap
draw in, not only air or gas, but loose material. and the transmitters.
Solid objects can pass through the fan and A power-plant annual outage offers the op-
either damage the rotor or discharge the debris portunity to perform a more complete overhaul
as projectiles. Therefore. upon job completion, of the control system. Usually scheduled well
all ductwork must be inspected to.16cate any in advance, this work includes the recalibra-
foreign material so it can be removed. tion of field devices such as transmitters;
pressure, temperature, and position switches;
CONTROL-SYSTEM MAINTENANCE control valves; speed controllers; damper
Historically, because of limited manpower drives; and thermocouple inputs. If there are
and funds, power-plant control-system main- known problems in the control system, addi-
tenance has been limited to repair of known tional work is done. For example, a dry-run of
deficiencies. With greater emphasis on plant the furnace supervisory safety system should
reliability and availability, preventive mainte- be conducted if some digital logic is not per-
nance programs have grown. forming correctly, or a calibration and retuning

Fig. 18 Periodic maintenance of control hardware can prevent costly trips


COMBUSTION
Maintenance and Repair of Steam-GeneratingEquipment

of an analog loop may be in order if poor control rolls are fairly easily removed from their jour-
is observed during previous operation. nal assembly for replacement.
Because the control system is the power- The rate of abrasive wear of the grinding
plant component that, as its proper function, parts depends on the type and quantity of im-
trips a unit off line, its role is critical to plant purities in the coal. Considerable laboratory re-
operation. Often, unit trips are attributed incor- search and field development of materials have
rectly to control-system malfunctions when, in reduced the wear and increased the availability
fact, the control system has sensed an abnormal of these components. An abrasion-resistant
condition and responded correctly. nickel-chromium white cast iron is used for the
pulverizer grinding parts. Depending on the
abrasiveness of the particular coal being
EROSION AND ABRASION ground, rolls and rings may both have to be re-
placed at the same time or it may be possible to
On coal-fired units, one of the biggest obtain twice the life from a ring as from a set of
maintenance requirements is the repair or re- rolls (Fig. 20).
placement of parts worn by the erosion or For highly abrasive coals, a hard-surface weld
abrasion of coal and ash. Abrasion is the
overlay which is applied to either new or worn
"sandpaper" effect of solid particles moving
parts has proven effective in increasing roll and
parallel to, and in contact with, a boundary sur-
ring life. The overlay must be at least I12 in.
face. Abrasion tends to occur at the high spots
thick. For used rolls, overlays up to 2'14 in.
on the boundary surface and has little effect on
thick are possible to return the roll to its origi-
the surface matrix. Therefore, a boundary sur- nal diameter.
face containing a small hard-particle matrix
Other pulverizer parts subject to wear in-
will give the best life.
clude the various liners fabricated of abrasion-
Erosion, on the other hand, occurs from the
resistant steel plate, high-nickel castings, or
impact of energy particles. The solid particles
ceramic material. These must be checked for
strike the wall freely, and cut portions of the
material loss at the same time as the rolls and
boundary or wall material. Hard or erosion-
rings.
resistant particles in the wall matrix will not
protect the less-resistant balance of the matrix. COAL TRANSPORT PIPING
Consequently, many abrasion-resistant mate- With more frequent use of highly abrasive
rials are not erosion resistant (Fig. 19). coals, pulverized-coal pipeline wear can be-
PULVERIZER WEAR come a significant problem. The rate of wear
generally is a functi0.n of
In coal-fired steam generators and auxili-
aries, the major wear is from erosion, which oc-
curs in the fuel preparation and delivery sys-
tem and in the backpass convection section. Al-
though the grinding parts of the pulverizer
wear from abrasion, wear in the other parts of
the coal milling and transport system is princi-
pally due to erosion. The wear in the steam
generator itself is almost all by erosion.
As discussed in Chapter 11, the C-E bowl
mill pulverizes coal by subjecting it to a grind- Elbow Without
ing force between a rotating bowl and spring- - -DeflectorBlocks
loaded stationary rollers. The bowl has a seg-
mented wear-ring for easy replacement and the Fig. 19 Erosion and abrasion in coal piping

.18
COMBUSTION
Maintenanceend Repair of Steam-Generating Equipment

8 particle characteristics: hardness, sharpness, Because erosion potential is greater at and


and size after bends, wear-resistant nodular-iron deflec-
8 particle velocity tor blocks are positioned in selected elbows to
angle of attack of particle-s -- both absorb coal particle impingement and re-
properties of the piping material distribute solids flow concentrations (Fig. 21).
Experience dictates initial location of deflector
Fig. 21 shows the standard material selection blocks but they can be repositioned in the field
for the coal-transport piping which provides to match the elbow wear pattern. System
cast-iron elbows at the pulverizer or exhauster pressure-drop considerations limit the number
outlet and at the windbox inlet. All straight of deflector blocks that may be installed.
piping and bends between these points are of Sometimes, pipeline flow characteristics are
commercial carbon-steel pipe. All bends and so complex that deflector blocks cannot be
elbows are designed. to a two-pipe-diameter completely effective. In these installations, the
radius, except the windbox inlet elbow, which more serious pipeline erosion usually occurs in
has a one-pipe-diameter radius. specific bends and in the first 2 to 3 ft of straight
Rockwell couplings are used on the toggle pipe directly following the bends. In such
sections provided to accommodate the vertical areas, special wear-resistant components are
expansion of the boiler, and Victaulic couplings used for highly abrasive coals.
for connecting to the cast-iron elbows and ori- Such wear-resistant materials have been in-
fices. The balance of the piping is welded. stalled in, or in place of, elbows and bends on

Fig. 20 Checking roll wear


--
COMBUSTION
Mahtenanco and Repair of Steam-GeneratingEquipment

Elbow With
Deflector Blocks
- ( Basalt

Fig. 21 Coal-piping elbow with deflector blocks Fig. 22 Typical lined 90-degree steel elbow

operating units and have been evaluated for bricks, usually one-inch thick. The bricks are
erosion losses. Some are installed in a fabricated mitered elbow row by
w steel elbows lined with alumina row. The taper of the bricks is such that the
w steel elbows with silicon carbide brick in any given row support each other, as in
w steel elbows lined with basalt a brick arch. Mortar is used to fill the void be-
w double wall steel elbows with "lobster-back" tween the flat-faced brick and the curved steel
wear surface shell. The inside diameter of the lined bend is
w heat-treated (carburized) steel elbows identical to the pipeline I.D., with the O.D. be-
ing substantially greater.
EXPERIENCEWITH WEAR-RESISTANT Other ceramic materials such as silicon
PIPING MATERIALS
carbide (Sic) have also been successfully used
Brittle nickel-chromium nodular cast-iron, as fuel-pipe bend liners, but alumina brick
previously used to prolong the life of piping el- has been found to be the most economical
bows and bends, is no longer offered; this is in selection.
accordance with the 1988 NFPA 85F standard A volcanic rock, basalt, is fused and.annealed
prohibiting the use of brittle materials in pul- into liners of various shapes and thickness. It
verized-fuel piping. has excellent abrasion resistance and is good
Fig. 22 shows a typical ceramic lined elbow for straight coal pipes. But as basalt has poor
which may be a fabricated mitered elbow or a erosive-impact wear resistance, ' i t is not
modified standard steel bend. A steel casing recommended as a lining for elbow or bend
encloses the wear-resistant lining and satisfies installation.
code pressure requirements. The lining is se- Fig. 23 shows a double-backed elbow with a
cured in place with a high-temperature cement. wear-resistant concrete filling the void be-
An advantage of the steel-casing design is that tween the two surfaces. The steel elbow and the
the ends can be prepared for any attachment de- outer containment cover are made from elbow
sign including welding, flanging, or machined- torus fabricating dies. Such elbows have been
end preparation. in service for years with no sign of wear.
The most widely used ceramic for fuel-pipe Disadvantages of the "lobster-back" elbow
applications is alumina (Al,O,). This material are cost and space requirements. It takes two
is capable of improving wear-life 5 to 7 times complete elbows and considerable shop labor
that of carbon steel or nodular cast iron. The to construct one wear-back elbow, and results
alumina is manufactured in wedge-shaped in a component 2 in. greater in outside radius.
COMBmTION
Maintenance and Repair of Steam-Generating~ ~ u i ~ n G t

can occur. Although some erosion is experi-


enced on superheaters and reheaters, most ero-
to Be Altered as Shown sion has been on economizers, which usually
After Filling are horizontal tubes with closer spacing than
Carbon Stl. Die the superheaters and reheaters.
Formed Elbow
Section at Ends ECONOMIZER EROSION
of Elbow In general, predicting where excessive flyash
May Bea Weld erosion might occur for any given unit is dif-
End or Flanged
ficult, because such erosion is related to
e T y p . Both Ends
nonuniform flow of flue gas and uneven distri-
Fill from Both Ends After Filling bution of flyash in the backpass area associated
With Ava~lableHard Wear Concrete with centrifugal forces acting on the ash parti-
- cles during gas-turning.
Fig. 23 Double-walled wear-back outlet elbow Many factors affect flyash erosion, which is a
assembly in steel coal-piping very complex process. It is directly propor-
tional to ash loading and is influenced by the
Two steel elbows carburized to 700 Brine11 relative amounts of abrasive constituents-the
hardness, installed for test evaluation, showed silica, alumina, and iron oxide compounds-in
excellent abrasion and erosive-wear resistance. the flyash. Most investigators have found that
However, welding the elbows or attachments to the erosion rate is an exponential function of
the elbows is difficult and flange weld failures particle velocity to between the 3rd and 4th
have been experienced. Also, the costs of car- power. Gas-side pressure drop (which is a
burizing large elbows appear prohibitive. combined function of gas velocity, turbulence,
and heating-surface configuration) also influ-
EROSION AND ABRASION FROM FLYASH ences erosion.
Approximately 60 to 80 percent of the ash Gas velocity through a tube bank is a function
resulting from the burning of coal leaves the of unit operating load, excess-air level, and the
furnace with the combustion gases. Gas amount of free (net) gas-flow area within the
velocities must not exceed specified limits in bank. Therefore, unit operation much above
order to control erosion from the ash particles. maximum continuous rating and design excess
Depending on both the quantity of ash and its air aggravates the potential for flyash erosion.
composition, the velocity is generally limited Also, any action that results in the reduction of
to 50 to 60 ftlsecond. flow area, such as localized flyash plugging,
Two components in flyash that appear to will increase gas velokity and the erosion po-
contribute most to flyash erosion are silica tential by concentrating flyash in an area adja-
(SiOz) and iron oxide (Fe203),both relatively cent to the plugged area.
hard abrasive oxides. While silica is ordinarily When a unit develops an economizer erosion
present at higher percentages than iron oxide, problem, it is necessary to establish the cause.
iron oxide is more dense and, consequently, To add more localized baffling, tube shields,
produces a greater impact influence. or other devices without regard to the causes, '
Flyash erosion is a term that, in general use, may produce only short-term improvements.
includes flyash abrasion. All tubing erodes If examination of the unit and its operation
when subject to a flyash-laden gas stream. As indicates that such factors as operating load,
long as the wastage rate (the loss of metal in a excess-air level and presence of plugging
given time) is low, the polishing effect is not are not abnormal, then the addition or
considered significant. When the wastage rate modification of baffles or tube shields or other
becomes excessive, premature tubing failures devices is justified.
- -
COLomON
Maintenance and Repair of Steam-Generating Equipment

major overhauls. Some utilities have roving


crews to supplement plant labor when re-
quired. Whether to use outside labor or be self-
sufficient can only be determined by plant
management. But no matter how much outside
contract labor is employed, the final responsi-
bility must rest with the station staff. Unless the
station staff oversees the work done, there is lit-
tle chance for a cohesive maintenance program.
Horizontal & Vertical TRAINING FOR MAINTENANCE
Training maintenance personnel is vitally
Baffling for Tubing important to the successful operation of any
plant. Many months before a plant goes into
Economizer service, maintenance crews should be selected
and trained.
Although there are fewer available programs
Fig. 24 Erosion reduction methods in economizer for maintenance people than for operators, the
plant should explore all training aids and
On some economizers where excessive ero- methods. Many manufacturers have courses
and workshops in equipment inaintenance and
sion has occurred across the rear of the back-
the use of special tools and procedures.
pass, a combination of erosion-control methods
The plant maintenance staff should be used
has been used (see Fig. 24). Collectively, they
for initial setup of equipment because working
have abated excessive erosion. Some methods
with the manufacturers' representatives pro-
used include
vides invaluable training. Money spent on
8 adding filter baffles to obtain a more uniform vendor servicing can be wasted if no one in the
flyash distribution across the economizer plant knows what is being done. Thus, a plant
a d d i n g slag fences to prevent economizer maintenance supervisor, as well ,as mainte-
plugging nance mechanics, should be assigned to each
installing plates or screen to block open areas vendor representative.
and stop channeling of the flyash LONG-RANGE PLANNING AND SCHEDULING
8 adding additional sootblo~~er equipment to Nothing is more important in maintaining a
maintain cleanliness of the econbmizer section plant than scheduling maintenance intervals.
The more crowded and busy the maintenance
8 sequencing the sootblower in the upstream chief's schedule is, the more the need to take
convection sections to blow from top to bottom time for long-range planning and scheduling.
and rear to front Such forward thinking includes asking ques-
tions which define future needs:
What jobs are next in line?
MAINTENANCE STAFFING On what dates do they have to be started or
completed?
The size of a plant maintenance staff varies
with the number and size of units, fuel used, Which person is going to do what?
quality of the labor, and extent of outside What equipment and material are needed to
supplemental help. Large coal-fired stations get the work done?
may have several hundred people employed in What problems or roadblocks will they run
maintenance and still hire contractors for into?
COMBUSTION
Maintenance and Repair of Steam-GeneratingEquipment

Equally important, an optimum maintenance under the general designation of "maintenance


program calls for replacing some parts before and repair", has to do with the day-to-day, month- -
they are completely worn out so as to take ad- to-month, and year-to-year actions of inspection,
vantage of scheduled outage time. A cost1 monitoring, and testing (such as of oil or water)
benefit analysis is one way to decide when to to ensure that a ~team-~enerating unit and its
change critical parts; that is, the cost of the auxiliaries will keep running between scheduled
life remaining in the component is weighed annual or bi-annual outages. Strange sounds,
against the cost of subsequent loss of produc- visible leaks, higher pressures or temperatures
tion if that equipment is out of service again. than normal, all tell the alert operator or main-
For fast-wearing or particularly vulnerable tenance person that something has to be done
parts, consider substituting new materials or quickly or unit availability will suffer. Unfortu-
redesigned parts. Improved materials can pro- nately, this type of maintenance is reactive, but
. long life and lead to.much less maintenance is vital to keeping equipment in service for ex-
labor. With higher labor costs, materials once tended periods of time.
considered too expensive are now cost savers. The second type that has been described is an-
Even plants that seldom rely on manufacturers' ticipatory, or preventive, maintenance-the kind
representatives for aid in maintenance should that prevents the strange, noises and other unde
periodically ask the manufacturer about new sirable indications. Based on manufacturers'
developments in materials and techniques. For recommendations, in-plant experience, and seat-
instance, high-nickel material or tungsten- of-the-pants judgment, preventive maintenance
carbide ovgrlays on steel have been most effec- is done at planned intervals while equipment is
tive in prolonging life of steel parts. Ceramics operating satisfactorily; its purpose is to elimi-
are used in many applications. Initially these nate unscheduled outages due to component dis-
were used only on stationary parts but, with tress. With this type, the timing is arbitrary and
improved epoxies, some can now be used on consensual; it is not based on rigorous testing,
rotating equipment as well. but on an accumulation of favorable experience.
Wise maintenance supervisors, then, will in- The third type is now called predictive rnain-
vestigate new materials or other ways to cut tenance. This has the same aim as preventive
maintenance costs. And they will allot some maintenance, but employs more sophisticated
time for discussions with vendors' salespeople computer-assisted methods of timing the actions;
to find out what new products may be a solu- it is intended to achieve the same or better re-
tion to difficult maintenance problems. sults at lower cost.
Maintenance and repair activities beyond these
three categories lead us into the realm of life
BEYOND MAINTENANCE continuation, which is discussed in the next
chapter. Major efforts to obtain higher availabil-
AND REPAIR ity and indefinite continuation of equipment
Maintenance activities, as they have been ad- life are in the area of upper-management deci-
dressed in this chapter, fall into three overlap- sion-making, beyond the proper activity of the
ping, not-too-well-defined categories. The first, maintenance-engineering staff.
Maintaining Availability:
Condition Assessment and Remaining Life Analysis

n many respects, the electric utility or inde- ating capacity and the cost of replacement power.
pendent power producer is unique. Its prod- As one measure of reliability, published avail-
uct, the day-to-day output of electric energy, is ability statistics are of considerable interest as
supplied on demand with no opportunity to be the power industry emphasizes producing the
inventoried or stored. Thus, the network of gener- most energy for the least cost.
ation, transmission and distribution equipment The importance of high plant availability has
through which the electricity is delivered must spurred the U.S. Department of Energy (DOE),
have high operating integrity to assure optimum the Edison Electric Institute (EEI),and the Elec-
reliability of supply, which is the power indus- tric Power Research Institute (EPR1)-the latter
try's highest priority. acting as the research arm for participating utili-
In addition, because of the long lead time re- ties-to pursue programs that identify means of
quired to add or contract for new capacity, it is improving plant performance.' Some state and
necessary for the industry to plan to build gener- federal laws concerning electrical-plant reliabil-
ating equipment years in advance of service dates ity already have been enacted.
to supply future electric loads. Further, the power In very dramatic terms, the world energy crisis
industry ranks among the most capital-intensive reinforces the tremendous importance of power-
in terms of dollars of investment per dollar of generating plant availability. Fluctuations in fuel
revenue. This chapter explores the implications costs are felt in virtually all energy sources with
of reliability of supply in the generation of steam- a significant impact on the political, social, and
electric power by fossil-fired plants. economic status of the U.S. and most other
countries.
AVAl LAB1L l N PRODUCTIVITY INDICES
The availability of an electric power plant is The utility industry uses several indices to eval-
important to both system reliability and generat- uate power-plant productivity which, in essence,
ing-company profit. Improving availability only is a measure of the ability of a plant to produce
slightly can save considerably on reserve gener- electricity on demand. As defined by the North
COMBUSTION
Maintaining Availability

American Reliability Council (NERC),five major Service Hours = the total number of hours the
power-plant performance indices are: unit is electrically connected to the transmis-
sion system.
Net Capacity Factor (NCF),percent = Forced Outage Hours = the sum of all hours
Total Net (Actual)Generation in MWh during which a boiler or other major equip-
ment is unavailable because of a forced
Period Hours x Net Maximum Capacity
outage, which is the occurrence of a compo-
nent failure or other condition requiring that
the unit be removed from service immediately,
Service Factor (SF),percent = or up to and including the next weekend.
Service Hours
Period Hours
(2) MEASURING AVAILABILITY
Each equation identifies only a portion of per-
Availability Factor (AF), percent - formance measurement for a generating unit. No
single index teIIs the overall performance story
Available Hours -x for a unit, a fact that is apparent from Fig. 1.
Period Hours Capacity factor, for instance, is not a true indi-
cator of a unit's reliability,because actual gener-
ation may be limited by economic or environ-
Equivalent Availability Factor (EAF), percent = mental dispatch as well as forced and scheduled
[Available Hours - (Equivalent Forced outages and deratings. This is particularly true
+ Planned Derated Hrs)] x 100
with older units, which typically have higher
Period Hours heat rates (lower thermal efficiencies)than more
(4) modern units. The annual availability factor es-
tablishes only the percentage of time during
Forced Outage Rate (FOR),percent = the year that the unit was capable of producing
power. This factor includes time when the unit
Forced Outage Hours x 100 was capable of generating power, biit was not in
Service Hours + Forced Outage Hours service because more efficient units were being
used. Thus, the availability factor does not mea-
sure the ability of a unit to operate at a specific
where: power level when called upon by the dispatcher.
Net Maximum Capacity (NMC) = the net sus- Rather, it measures only the capability of the unit
tainable unit capacity when not restricted by to produce at a power level ranging from 0 to 100
ambient conditions. percent of its rated capacity.
Available Hours = the period of time during The equivalent availability index provides for
which a unit or major piece of equipment is an adjustment of the availability factor by ac-
capable of service whether it is actually in counting for the effect of partial deratings (losses
service or not. in electrical-power output capability) from partial
Period Hours = the number of clock hours that forced and scheduled outages. Essentially, the
the unit is in the "active state" (usually taken index is equivalent to the percentage of the year
as one year). The active state includes both the during which the unit was available for operation
available condition (with the unit operating at full capacity.
from zero to full load) and the no-load condi- What equivalent availability does not indicate
tion during forced or scheduled outages. It is whether an outage is either forced or planned.
does not include any period in which a unit is A forced outage is generally more costly in terms
on inactive reserve, moth-balled, or retired. of both replacement power and the ability-of the
producer to supply system loads. The forced out- generation in the US.
- age rate measures this performance. Net capacity Note that coal-, oil-, and gas-fired steam gen-
factor is, in effect, the "bottom line" result and erators have lower availability factors than jet
also includes discretionary cutbacks in output by engines [aircraft-derivativegas turbines), gas tur-
a generating company. bines (stationary industrial type), and diesel en-
Each index, therefore, is limited to defining a gines. This is because of the extended planned
specific aspect of power-plant performance. To outages taken on such boilers for repair, mainte-
evaluate the overall performance of a power plant nance, and upgrading, usually in anticipation
requires subjective and collective review of these of major power-generation campaigns. The in-
and other indices. ternal-combustion equipment-which is smaller
on average than the boilers-is closer to the
AVAl LAB1LlTY STATISTICS ground, often has many replaceable modules,
and inherently has shorter preventative-mainte-
Table I is a small sample of the Generating Unit
nance time; and the less time down for mainte-
Statistics given by the Generating Availability .
nance, the higher the AF.
Data System (GADS) of NERC for the five-year
period 1985-1989.The GADS-IEEE Standard 762
and equations and definitions are taken from the THE POWER-PRODUCER'S VIEW
GADS short-form summary of its Generating OF AVAILABILITY
Availability ReporL2 This tabulation illustrates
the differences in five performance factors for A major reason for improving availability in
equipment currently chosen for electrical power electricity production is a matter of economics,

Rated
Capacity

t
z
a

Period Hours
Service Hours Outage Hours
Available Hours/ForcedJ
Outage Hours
PFO - Partial Forced Outage (Operating Problems Force Unlt Derating
PSO - Partial Scheduled Outage (Unrt Derating to Permit Maintenance)
ESD - Economy Shutdown (Not Economical to Generate)
FO - Forced Outages (Equipment Failures, Accidents, Environmental Factors)
SO - Scheduled Outages (Routine or Planned Maintenance, Inspection, and so on)

Fig. 1 Factors affecting productivity of power plants2


-.
C O ~ I I O N
Maintaining AvaNability

Table 1. 1985.1989 Generating Unit Statistics


from the North American Electric Reliability Council (NERC)
Generating Availability Data System (GADS)
Unit '&pe MW Rating No. of Units NCF SF AF EAF FOR
Coal Primary 1-1,000+ 887 58.2 70.5 83.1 80.2 6.6
Oil Primary 1-999 244 30.9 47.1 84.4 81.5 7.7
Gas Primary 1-999 472 30.9 42.3 84.8 82.4 7.0
Nuclear (All) 400-1,000+ 125 62.1 69.2 69.2 65.7 13.8
Jet Engine 1-20+ 347 1.9 2.6 91.8 85.5 55.3
Gas lbrbine 1-50+ 575 1.8 2.7 91.1 85.1 60.6
Diesel All Sizes 180 1.9 2.3 95.7 95.6 50.5
Combined Cycle All Sizes 26 32.5 49.1 85.1 76.8 6.8

which essentially relates to the high cost of con- ability and obtain maximum reliability from
structing power-generating facilities. (The basics steam generators, C-E at one time formed an
of power-plant economics are discussed in Availability Task Force to investigate how best
Chapter 1.) to use EEI, NERC, and other data-gathering sys-
Better plant availability could have a signifi- tems. A study showed that these data were capa-
cant effect on plans for the construction or ble only of providing the component cause for
deferment of new plants. On the other hand, outages and load reduction and were not able
long-term outages from repeated boiler tube to provide information)as to why a component
leaks, turbine-blade losses, or other plant equip- failed. Without information on the cause of the
ment problems, could force a utility either to component problem, it was not possible to deter-
install additional capacity or to purchase replace- mine whether there existed a deficiency in de-
ment power-if it is available-at high cost. sign, manufacturing, maintenance, or operation.
Therefore, C-E established its own program to
RESERVE MARGINS
provide the necessary information.3
One measure of adequate generating capacity This program gathered information on the
is the reserve margin in excess of the peak load cause of outages and load reductions in nine
demand. This margin offers protection against major equipment categories related to steam
unanticipated demand growth, forced outages, generators. Included were
derating, and other contingencies. In the United waterwalls
States, a reserve margin of about 20 percent is superheaters and reheaters
generally considered acceptable. Because of reg-
economizers
ulatory andlor political factors, certain geograph-
ical regions have much less reserve than others, m furnace sootblowinglbottom-ash removal
accentuating the requirement for highly reliable equipment
generating facilities and adequate transmission convection-section sootblowing and
interconnections. In all cases, outages of large, flyash-removal equipment
highly efficient, base-load equipment increase m boiler controls
generating costs. m fans
-
AN -APPROACH pulverizers
TO AVAILABILITY IMPROVEMENT m boiler circulating pumps
To help electric utilities improve on unit avail- This information helped to identify trends in
*-
-
&
COMBUSTION
Maintaining Avallabillty

problems that occur from deficiencies in design, neither cure a power-plant "disease" nor correct
-
fabrication, operation, or maintenance. Derived a disorder which may, in some instances, be a
from these data is the knowledge that waterwall, design or construction deficiency. Chapter 23
superheater, reheater, and economizer tubing emphasized the importance of determining the
leaks account for 80 to 90 percent of all forced root cause of incidents causing forced outages.
outages, whereas coal-pulverizing systems ac- In the case of waterwall tube ruptures, poor
count for approximately 50 percent of equivalent feedwater quality is often the major contributing
downtime hours in load reductions. factor. With high operating pressures, feedwater
The program was limited to coal-fired units of quality becomes even more critical. The recom-
390-MW capacity and larger in consideration mendation is a maximum of, for instance, 50
of the amount of effort required in data recording ppm of total dissolved solids in high-pressure
by the utilities. It helped to improve the perfor- drum-type units. Most operators follow this prac-
mance of the large capacity coal-fired units then tice, as well as all others given in Chapter 20,
operating, and thereby set the pattern for opti- Power-Plant Water Technology.
mal performance of generating capacity in the Degradation of coal properties adversely af-
future.4 fects the capkbility of boiler auxiliaries, but its
direct effect on availability is difficult to quantify.
PROBLEMS AND THEIR ROOT CAUSES
A valuable study on this subject was done by the
The underlying causes of equipment prob- Tennessee Valley Authority and is presented in
lems producing forced outages may be difficult Fig. 2. The capability of components such as
to identify,'but their correction requires such pulverizers, fans, economizer, and air heaters
an identification. Peatment of symptoms will frequently limits unit capacity and reduces gen-

% O/o
Btu/Lb F.O.R. Ash
12500- 10.0- 20-
- - - Source: TVA Study Forced

12060- 7.5- 18-


- -

11500- 5.0- 16-


- - -

11000- 2.5- 14
- -

10500-0.0-12 I ' ' I I ' " ' I " ' I


1963 65 67 69 71 73 75 1977
Fiscal Year

Fig. 2 Boiler forced outage rate vs coal quality5


COMBUSRON
Maintaining Availability

erating reserves. If auxiliaries are operated con- effective lives for at least 15 years more-than
tinuously at or near their peak capability without originally anticipated. This is because of the very
proper maintenance, problems will generally high capital costs and licensing complications of
develop. building new plants, and the difficulty of ob-
Furnace-framing structural design to with- taining land-use options. Thus, there is often a
stand negative pressures can be increased sig- genuine interest in keeping older plants in oper-
nificantly to provide greater protection against ation, compared to the other available or devel-
implo~ion.~ opable possibilities.
Damage to fan housings, duct work, and stack Many large fossil plants were originally de-
liners, resulting from fan-induced duct vibra- signed as base-load units, intended to run stead-
tions caused by pressure pulsations in centrifu- ily with as few starts and stops as possible. But
gal fans, also can be a significant problem. To many of these large units have been relegated to
avert this, C-E has specified equipment that does cycling duty, which requires an increase in the
. not emit damaging pulsations. An example is its number of start-ups, shutdowns, and load swings
calling for vane-controlled fans instead of lou- above those contemplated in the origfnal design.
vered-damper-controlledfans whenever possible. Thick metal parts, for example, experience sub-
Damper-controlled fans are more susceptible to stantially increased thermal stress due to cycling.
stalling and consequent large emitted pressure These stresses, in turn, affect the material prop-
pulsations. A second example is the specifica- erties of the components and make them more
tion of dorsal fins or an equivalent in all vane- susceptible to failure through fatigue, creep, and
controlled fans. Without this corrective device, other conditions. Water-chemistry effects on in-
some installations experience destructive levels ternal corrosion, external gas-side corrosion,
of vibration. Stipulating equipment with these erosion, and other mechanisms can also signifi-
features limits the selection, but markedly re- cantly affect boiler life.
duces fanlduct vibration incidents.' Owners, therefore, need to have qualified engi-
neers examine for the presence of these anoma-
lies on an existing boiler and determine how they
AVAlLAB1LINIRELlABlLITY might influence the performance of both indi-
AND LIFE CONTINUATION vidual components and the boiler in general.
Once this is done, a judgment can be made as
In consideration of many factors, electric to the remaining life of the critical components
utilities and owners of large industrial boilers and whether or not it would be economically
havepften redirected their resources to the im- feasible to keep the unit operational for some
provement and the continuation of life of exist- additional period of time.
ing e q ~ i p m e n t . ~ While there are uncertainties with any life-
For many years, the practical life of power prediction method, an objective assessment is a
plants was taken to be 30 to 40 years. The ration- prerequisite in any plant life-continuation pro-
ale for this was based, in part, on the very arbi- gram. The combination of sound pre-planning,
trary material lives indicated in the ASME Boiler inspection, examination, and the use of the best
Code. It was felt that major components would available life-predictionmethodology will permit
be nearing the end of their design lives after such meaningful conclusions to be drawn as to the
a time, and that the plants would become less current condition of a steam generator and its
economical as their efficiency (relativeto newer ancillaries, and of its capability to operate be-
units), availability, and reliability decreased. yond its originally planned retirement date. Com-
Now, plants over 30 years of age that would bustion Engineering believes that often the most
have been scheduled for retirement are studied effective approach is a combination of opera-
as to the advisability of regeneration to maintain tional and maintenance changes, and material
or enhance their availability and to continue their or component modifications. Details of its life-
-? COMBUSTION
Maintaining Availability

continuation methodology and a differentiation the cost of environmental compliance equip-


of the several assessment techniques are given ment-versus the investment for replacement
by Gelbar and de Mello, reference 9. equipment. The engineering analysis that pre-
cedes a life continuation program has to be very
MAINTAINING NAILABILITY thorough and positive in its prediction of re-
maining life of the components that are not to
In this book we have already discussed many be modified or replaced. The engineers respon-
approaches in design and operation that can sible for the replacement or upgrading of pres-
contribute to sustaining the performance and sure parts and other components subject to
availability of large steam-generating units: in thermal or pressure stress, or to corrosion or
Chapters 6 and 7, we went into detail on the de- erosion, must assure the owner that the life of
sign of boiler pressure parts and how the design the unit will in fact be continued as intended.
is affected by cycling operation; in Chapter 13, It behooves owners to continue in-service, pre-
we emphasized the importance of diagnostic ventive, and planned maintenance on a timely
evaluation of boiler on-line performance using basis, in order to prevent any loss in capacity of
modern computer techniques; Chapters 2 1 and power-plant equipment that would result from
23 covered the influence that operation and plant the deferral of such work. In other words, any
maintenance can have on the ability of boilers reductions in capacity must be avoided lest they
and their auxiliaries to respond when they are are made effectively "permanent" through legal
called upon to generate power on demand and interpretations of environmental regulations. In
to do so efficiently, this context, many owners are understandably
In this section, we will go beyond what we reluctant to undertake any actions that could be
have presented in the last chapter, so as to intro- construed as being "beyond" standard mainte-
duce techniques of continuing the intended life nance, to the point that removal of safety hazards
of power-plant equipment. As we have intimated, and efforts to improve plant reliability may be
a decrease in the availability of any mechanical frustrated.*O
or electrical equipment is most often the result
of a conscious owner decision to let that happen. ASSESSMENT OF
The process of life continuation-keeping a
steam-electric plant in good condition so that it
REMAINING LIFE
can continue to operate in active and efficient OF STEAM-GENERATOR
base-load or peaking service for some undefined COMPONENTS
length of time-is similarly a management de-
cision to repair, replace, rebuild, or upgrade only Condition assessment, the evaluative process
as necessary to accomplish that end. Any activ- that precedes any actual life-continuation ac-
ities exceeding that represent a judgment to tivity, is essentially a review of plant operational
extend life to, say, 55 or 60 years, which is greater and maintenance records plus an inspection that
than the executives originally purchasing the leads to a prediction of expected safe operating
equipment contemplated. life left after the date of the inspection. The
process might pin-point the most sensitive com-
WHY A NEED FOR LIFE CONTINUATION? ponent-the one that will probably run out of
For a variety of reasons, the construction of life first-but the estimate of remanent life is
base-load type electrical generating capacity in strictly an engineering judgment and is not a
the U.S. has not kept pace with the projected calculated value. Any repairs that are indicated,
need for it; this is indicated both by projections or any upgrading of components or subsystems
of load growth and expected plant retirements. to the state-of-the-artthat are recommended, are
Currently, power producers have to evaluate only to allow the unit to continue in operation
the cost of life continuation-which may include in what is felt to be a safe manner.
c O ~ O 1
Maintaining Availability
--
A condition-assessment study will identify First, the Codes are design tools. They are also,
components having time-independent or time- in a very real sense, some of the earliest expert
dependent characteristics that will affect their systems. Their purpose is the enforcement of
service life. Life predictions in the time-inde- design rules that ensure a low probability of
pendent regime involve knowledge of when effec- failure by specifying the minimum allowable
tive tube-wall thickness will be reduced to the thicknesses of components made of approved
point of failure. There is essentially no deterior- materials fabricated in a stated manner.
ation of material strength properties over time; Secondly, the philosophy of the Codes is based
that is, creep does not occur. The rate of corro- on such concepts as:
sion, erosion, or crack propagation must be
established to predict life, taking into account Allowed materials are ductile and, therefore,
safety factors in the ASME Boiler Code as well in many cases, forgiving.
as realistic long-term future operating condi- Life, operational effects, material variability,
tions. In instances where observable distress is local stresses and other similar effects are not
incident-related (rather than time-related), such directly considered but are expected to be ac-
as with caustic attack, hydrogen damage, or pit- counted for by the conservatism applied in
ting, life predictions are not practical. setting the allowable material properties.
The situation in the time-dependent regime is Design rules are developed by consensus
much different. Because of creep damage along within groups of acknowledged experts and
grain boundaries, components in the time- are subject to multiple levels of review. Being
dependent temperature range can rupture with developed in this way, there may be no precise
essentially no wall loss. Such components have physical justification for some of the rules.
a finite life because their strength-retaining
capability is diminishing with time. Uncertain- The result of this type of approach is that the
ties in life-continuation studies often relate to actual stress in a local region of a properly de-
predicting metal behavior in the time-dependent signed component may exceed the allowable
regime, especially for thick-walled pressure-con- stress given in the Code being used. This does
taining elements. not mean that the component is unsafe, but only
that the published values of allowable stresses
DESIGN-CODE ASPECTS for the material are sufficiently conservative to
ensure that the resulting component will be safe,
Before discussing what is involved in the re- even without considering local effects that may
maining-life analysis of thick-wailed compo- occur in design, manufacture, field construc-
nents, it is important to understand what is not tion, or operation.
involved. Life analyses are not a simple review Unfortunately, the simplifications that make
of the design vis-a-vis the ASMEIANSI Codes for an excellent design tool destroy the useful-
and a rubber stamp to say that the design meets ness of the Codes as devices for predicting the
the Code and is therefore satisfactory. The fact life of a component with any precision. The fact
is that, if the unit met the Codes when it was is that the life of a component is intimately re-
designed, then, unless there are such effects as lated to the actual local stresses, temperatures,
thinning present, it will meet the Codes now. and material properties. Ignorance of any one of
The reason for this is that the Codes which thick these has a significant effect on the precision
components are built to, do not explicitly con- with which life can be predicted. The Codes
sider the effects of time, nature of service, and ignore all of these and, as a result, while it is
fluctuations in load. To understand the reasons possible to manipulate such a Code to obtain a
for this, it is necessary to consider what these value for the life of a component, any life ob-
Codes are and some of the philosophy behind tained from such an approach may be in errar
their development. . by orders of magnitude."
CDMBUSTION
Maintaining Availability

FAILURE MECHANISMS considers a component designed such that its


thickness is just equal to that required by the
In a well-designed and well-manufactured Code for operation at 1000F (540C).If, in any
high-pressure component, failure can be caused part of such a component, the local stress is a
by unexpected loading andlor environmental mere 12% greater than the Code allowable value,
situations. A simple design review and an evalu- then the life of the component will be halved.
ation of inspection results will generally confirm As an example, consider both unpenetrated and
the quality of the design and manufacturing. penetrated cylinders designed such that their
The loading and environmental situations thicknesses are precisely that required by ASME
that can adversely affect components are: Section I. As far as the Code is concerned these
1. Water chemistry effects two components are equivalent. However, a
2. External corrosion detailed stress analysis shows that the local
3. External wastage dqe to erosion stresses are significantly different. High local
4. Change in thermal conductivity due to scale . stresses will be somewhat relaxed over time by
buildup creep effects and, in fact, the location of the high
5. Service at temperatures andlor pressures stress areas will move from the inner surface to
above design conditions the outer surface. However, it is a fact that the
6. Changes in the behavior of support structures
lives of the two components are not the same and
are probably significantly different.
7. Abnormal conditions such as temperature Assuming the same parameters as in the above
and flow maldistributions or defective support example, then a 17F (9.5OC) increase in local
systems '
temperature above the design assumptions will
8. In-service origination of corrosion sites also reduce the life of the component by half.
9. Non-linear temperature and pressure start-up This is due to the change in material properties
ramps with temperature. As an example, temperature
10. Faster-than-design start-ups and shutdowns variations along a header can be significant and
11. Excessive cycling some allowance is made for this in the design
process. However this temperature distribution
Items 1 and 2 are not in general amenable to is not precisely predictable nor is it reproducibIe
analytical approaches as discussed in previous between similar units. Aside from the safety
chapters, and are beyond the scope of the present aspect, from the user's point of view it is just as
treatment. Items 3 and 4, although they can be bad to underestimate the remaining life as it
analyzed, are usually associated with tubular is to overestimate it. The percentage of devia-
components in the gas pass and, as such, are tions from design stress and design temperature
not generically considered as relevant to thick- required to halve the life of a typical compo-
walled components. The principal situations to nent are shown in Fig. 3 as functions of design
be considered are therefore Items 5 through 11. temperature.
Some of these, such as thermal transients result- The third variable involved is the material of
ing in cracking of internal scale and exposure the component itself. The properties of any
of corrosion sites, are not presently capable of single material specification are extremely vari-
being analyzed, and will therefore not be con- able, particularly those which affect the life of
sidered here. a component.
The parameters that affect the life of a compo- For instance: at 1000F,there is a factor of five
nent are the local values of stress and tempera- between the predicted life of a component ob-
ture, and its material properties. Life does not tained using minimum properties and that
only depend on these parameters, it is extremely obtained using mean properties. The difference
sensitive to variations in them. between mean properties and maximum proper-
The effects of stress can be appreciated if one ties would involve an additional factor of five.
Design Temperature, O F
I
Fig. 3 Effect of deviations from design for 21/4% Cr, 1% Mo steel, to reduce component life by half

If one has no information about the material tremely non-linear as various subsystems are
other than its specification, then the minimum modulated. In addition, although the shutdown
material properties have to be used to predict is assumed to be a mirror image of the start-up,
life. Using this approach the predicted life may the transients in this situation are often even
be underestimated by as much as a factor of 25, more severe than in the start-up. The effect of
purely as a result of the variability of material transient loadings, particularly in temperature,
properties. Fig. 4 shows the minimum and mean can be very severe and result in local cyclic
lives of a component as a function of operating plastic deformation which can lead to fatigue
temperature assuming the actual stress is the failure in a relatively low number of cycles."
allowable ASME Code value. As described earlier, there are two principal
The above effects apply even if the component types of situations that can be considered in the
is operated purely in steady state; that is, with determination of the lif6 of thick-walled compo-
no variation in thermal, mechanical andlor pres- nents. The first, in the time-dependent regime, is
sure loadings. In fact, the component under- the high-temperature pseudo-steady-state load-
goes fluctuations in these loadings both in a ing where the creep of the material is the phe-
gross fashion during start-up and shutdown of nomenon that leads to failure. The second, in the
the system and, in a minor way, during opera- time-independent regime, is the cyclic plasticity
tion. Although the Code does not require it, the that occurs during start-up and shutdown which
manufacturer of a boiler specifies a start-up rate can lead to low-cycle-fatigue failures.
to limit potential damage to the system. How-
ever, ihis start-up is assumed to be smooth and, CREEP

-- for stress-analysis purposes, linear. In fact, the Creep is the degradation of material properties
change in loadings during start-up can be ex- that occurs with time at temperature. It hap-
COMBUSTION
Maintaining Availability

0.4 - Minimum Properties .. -


-
0.2 -
- -
-
Operating Temperature, O F

I I
Fig. 4 Life versus temperature at ASME code allowable stress (material: 29'4% Cr, 1% Mo steel)

pens even at low temperatures and somewhat nents of high-pressure boilers, the principal
differently in the heat-affected zone of a weld loading that can cause damage is produced by
than in the base metal. An analysis that does the transient thermal effects that occur during
not correctly include the effects of creep may start-up and shutdown. These events are severe
well predict failure in an incorrect location. This but, fortunately, relatively infrequent. When the
is because the damage resulting from creep transient events within a start-up or shutdown
occurs throughout the life of a component and are considered, the total number of cycles during
is exhibited as permanent deformation. This the life of a unit tends to be below 10,000. If
permanent deformation allows a highly stressed fai!ure occurs in fewer than 10,000 cycles, it is
area to shed load to a less highly stressed area. termed "low-cycle fatigue". It is characterized by
Such a redistribution of load can be significant. local strains in the region of failure that are in
In the case of a cylinder under internal pressure, excess of the yield point of the material, with the
if creep is not present the highest stress will be result that the material undergoes plastic flow.
on the inside surface. If the cylinder is operat- (Chapter 6 has a section on fatigue analysis.)
ing at creep temperatures, however, the highest Whenever fatigue failure occurs, it is initiated
stress area will, after time, be on the outside sur- at a free surface even though this free surface
face and that is where failure will originate. may be at a subsurface flaw. In low-cycle fatigue
Chapters 6, 7, 17, 20, and 21 cover other design this initiation is followed by crack growth through
and operational aspects of creep in more depth. a region of previously plastically strained mate-
rial. Finally, the crack propagates through the
FATIGUE
rest of the component, through regions that orig-
Fatigue is the process in which materials fail inally saw only elastic strains, and the compo-
under cyclic loading. For thick-walled compo- nent fails.
Crack initiation occurs at a very early time of complexity involved, is therefore the determi-
in life (<~ O / O of the number of cycles to failure). nation of what are the critical components.
The surface defect is usually located at a per- The initial step in the determination of criti-
sistent slip band where material extrusions or cality is an assessment of the consequences of
intrusions occur as a result of cyclic plastic flow. a failure. If the consequences of the loss of a
These slip bands occur on planes of maximum component are significant, then that compo-
principal shear stress although the direction of nent meets the first test of criticality.
opening will be that of the maximum principal If the component is one of many similar com-
normal stress. ponents with-similar loadings and the failure of
Although slip bands occur adjacent to the any one of these components does not result in
crack, as soon as the crack starts to open the significant consequences, then it may be that
stress on these adjacent defects is relieved and this class of component need not be considered
crack growth is generally limited to a single critical. The reasoning behind this is that there
crack. This is different from the creep situa- will be a distribution in the actual lives of these
tion where gross material degradation occurs components and the actual failure rate can be
throughout the region adjacent to the main crack. used as the input to the decision as to whether
METAL-TEMPERATURE DETERMINATION
or not it is necessary to replace a system made
up of these components. This is usually the case
Without reasonably accurate estimates of metal in systems that consist primarily of tubing. The
temperature, stress-rupture life predictions, failure of most other components containing
whetherbased on minimum or average strength high-pressure water or steam would be con-
properties, cannot be accurate. There is research sidered significant.
data on the growth of steam-side oxide scales
Design Parameters
on the low-alloy ferritic steels used in steam
generators.12 The basic parameter to be considered in evalu-
At elevated temperatures, the internal surfaces ating the criticality of a component is its design
of pressure parts will slowly oxidize and form temperature. The fact that a part is designed to
an indigenous oxide scale. The rate of oxidation operate in the time-dependent regime identifies
is a function of the internal surface temperature, it as having a finite life and tentatively places it
the type of material, and the time at tempera- within the class of critical components. Gener-
ture. It is possible to infer a "historical" tubing . ally, this includes the final superheater outlet

metal temperature of a tube sample by measure- header and the hot reheater-outlet header.
ment of the oxide scale thickness, when there ~eometricParameters
is knowledge of the rate of heat transfer, scale
conductivity, scale growth rate, and the length Components that are excessively thick may
of service. Using such data, the past temperature well be sensitive to even relatively slow tran-
exposure of a tube can be approximated if the sients. This is generally not a problem with com-
age and thickness of the oxide scale are known. ponents fabricated by boiler manufacturers, but
Estimates of this kind of necessity assume un- there may be a problem with purchased fittings
changing heat input to the tube, and constant (tees and elbows) and components such as valves
steam-side conditions.12 and pump casings.13
A second geometric consideration is that of
DETERMINATION OF configurationalcomplexity. Geometrically simple
CRITICAL COMPONENTS components can often be eliminated from the
It is not feasible, for economic reasons, to eval- list of critical components because of an ad-
uate in detail the life of every component in a jacent one that is more geometrically complex.
boiler; neither is this necessary. The first step The reason for this is that, because of the way
in any life-continuation study, whatever the level that design codes handle these, a more complex
..- COMBUSTION
. Maintaining AvaNabillty

geometry will generally have higher local stresses APPROACHES TO ANALYTICAL EVALUATION
than a simple one.
There are many different ways to evaluate
Experience -. what has happened to a component and what its
- expected remanent life will be, with the strategy
The principal guide to determining which of
different for pressure vessels and piping. There
the components that passed the first tests of
are five general levels of complexity:
criticality are in fact critical is experience, either
generic or plant-specific. The design-basis approach
Generic experience is that knowledge that has The operating-records approach
been gained from other studies and from obser- The pressure and temperature test-data
vations both within the operating company, the approach
manufacturer's organization, and in the tech- The material-sampling approach
nical community as a' whole. On-line monitoring and analysis
Plankspecific experience involves contractors'
As the level of analysis increases, confidence in
personnel and records, as well as those of ,the
the results increases, as does cost.
owner, and includes such items as knowledge
of previous failures and over-temperature op- Design-Basis Approach
eration. It also involves any inspection results;
Manufacturers design boilers to the customer's
this suggests that the criticality of a component
specificationsof pressure and temperature. Each
can change following the inspection portion of
a life-continuation program. Evidence of dis- manufacturer has its own design procedure. As
torted or discolored components, cracks in un- with the Boiler Code, this process is an expert
usual areas, and missing or defective support system in that it uses constants and coefficients
based on experience. Using this procedure, a
structures would all cause reassessment of
design is made with the Code used as a design
associated components.
tool to ensure that its requirements are met. In
Principal Critical Components other words, the stresses for the design condi-
in Steam Generators tions, calculated in the way that the Code re-
Experience indicates that there are a number quires, are confirmed to be no greater than the
of components that should be considered as Code-allowable stresses for the specified material
candidate critical items. The first three of these at the design temperature. What this means is
have experienced difficulties very frequently and that the sections will always be at least as thick
should always be considered; an examination of as the Code requires and often much thicker. In
plant records may remove some of the others particular, it is frequently standard practice to
from the list. make the thickness of a cylindrical component
equal to the next commonly~availablesize above
The final superheater outlet header and the the precise thickness required by the Code.
main-steam piping system Having arrived at knowing what the design
The economizer inlet header criteria were for any given component, and what
should be its minimum allowable thickness, we
The high-temperature reheater outlet header
can, with some confirmation from plant records
and the hot reheat piping system
of operational conditions, arrive at a first-order
Other reheater outlet headers and piping assessment of plant life. In most cases this will
Other superheater outlet headers and de- say that the majority of high-temperature com-
superheater systems, particularly where there ponents are close to, or have passed, their useful
are indications of higher-than design levels of life and that the low-temperature components
desuperheating are satisfactory-this despite the fact that there
Superheater and reheater inlet headers may be physical evidence of damage. In most
comusnoN
M~lntalnlngAvallabllity

instances, this approach is just a screening tool of components and incorporates the other results
at best. of an inspection program.15 Apart from the un-
certaintfthat thetest data may not be represen-
Operating-Records Approach
tative of past operations, the only other question
This level uses the design-basisapproach with in this type of approach is the lack of actual
augmentation by plant records. Because of now- material data. As a result, minimum material
reasonable costs of analytical modelling, we in- properties have to be used to provide a lower
clude this type of evaluation although it uses bound for remaining life.
assumed linear ramp rates as input loading data. The use of actual test data allows the predic-
Minimum material properties and nominal tion of the effects of changes in future operation
sizes are used. and also identifies possibly unknown sources of
The analytical tool used is a sophisticated heat- problems such as condensate-flow events.
transfer and stress-analysis computer program
which includes the effects of creep and plasticity. The Material-SamplingApproach
'AS such it can overcome the problems of the
design-based approach by evaluating the effects The next level of sophistication is to take
of start-ups and shutdowns. However, since these samples of the material present in the compo-
transients are assumed to be linear, this level still nents and, after performing accelerated creep
ignores their non-linear nature and is therefore tests on these samples, to incorporate these data
non-conservative. This problem can be overcome into the evaluation. This testing is fairly expen-
to some extent by using generic data taken from sive and care needs to be taken to ensure that
similar units but, because of the idiosyncrasies these results are used correctly.
of individual units, a high level of uncertainty First, it is part of the requirement for apply-
remains. In general this approach is not recom- ing accelerated creep test results to actual com-
mended because it is frequently assumed, by ponents, that creep testing be performed at the
people not intimately concerned with the proc- stress level that the component sees during oper-
ess, that, since a sophisticated analysis is per- ation. It therefore introduces errors to perform
formed, a reliable answer is obtained. This is not these tests at stresses that derive from a design
the case and care should be taken to understand approach. The difficulty is that, during operation
this concern.14 at elevated temperature, the stress in the com-
ponent is redistributed by creep relaxation and
The Pressure and Temperature as a result the operating stress will be signifi-
Test-Data Approach
cantly different from the design stress. Another
This uses transient pressure, temperature, and aspect of this approach is that, in general, to
flow data, taken during operation, as input for avoid creating problems with the component, the
the computer program mentioned above. The material sample has to .be taken from an area
data is obtained by installing thermocouples and removed from geometrical discontinuities. Un-
pressure transmitters on the components under fortunately, in most cases, the critical areas are
consideration and operating the unit specifically precisely those areas that have to be avoided
to obtain this data. A more cost-effective ap- during sampling. As a result, unless miniature
proach is to temporarily install a data-acquisition samples can be taken from the highly stressed
and analysis system so that the evaluation can be areas, it is necessary to translate the results of
done on-line during normal operation. Such an the accelerated creep testing into the remaining
approach avoids the costs of a special test and life at the critical areas. This means that, by the
the associated data handling, and provides the use of plant history and analytical techniques,
owner with immediate information about what the original creep properties of the material have
aspects of unit operation are most damaging. to be obtained. These can then be applied to the -
This analysis also uses the measured thickness analysis of the critical areas.
COMBUSTION
Maintaining Availabilq

Finally, it is unfortunately a fact that high- beyond ,the originally intended life, with these
pressure components are fabricated from sub- considerations in mind:
structures made u p of different heats of mate- Through rehabilitation or upgrading tech-
rial. Unless the material sample is taken from niques, the steam generator can be restored to
the critical substructure, the use of accelerated an operational level of availability, reliability,
creep test results is inappropriate. In the worst and capacity factor as practically close to "as
case, if the accelerated creep test results indicate new" status as possible.
that the material properties are at the top end of Currently available "state of the art" compo-
the scatter-band, and the critical area is in an- nent designs can be incorporated in full or in
other substructure where the material proper- part, to improve the performance level and
ties happen to be at the bottom end of the safety of a steam generator.
scatterband, then the life estimate will be non- Sophisticated analytical techniques can be
conservative by a factor of about 25. Here, al-
applied to estimate the remanent life of boiler
though an analysis might indicate that the components.
component has mony years of remaining life, in
fact the critical area may have totally exhausted Future eperational requirements may change
its useful life. from past or current practice-design changes
Despite these cautions, when applied properly may therefore be indicated for some of the
this approach does provide the highest level of components subject to rehabilitation.
confidence currently possible, for a single- Because of aging, or service-related destruc-
outage evaluation. tive mechanisms, replacement of some parts
may be required. Such replacement can be
On-Line Monitoring and Analysis programmed over a period of time based on
the calculated remaining life of specific com-
The ultimate level of assessment is similar to ponents. ,
that described previously except that on-line A life-continuation study is not solely a boiler
monitoring, analysis, and evaluation are accom- inspection program, or just non-destructive test-
plished by a device such as the C-E Boiler Stress ing of unit components, or only a prediction of
and Condition Analyzer described in Chapter 13. remaining life of critical items. Although ele-
Such a device monitors temperature, pressure, ments of these are present, timing is also an
and flow, and uses this data together with mate- important issue in the plant life-continuation
rial and geometry information to assess damage concept. A proper program is an on-going
on a real-time basis. It makes no assumptions process in which the owner and the equipment
about repeatability of operations. An option to manufacturers work togetherclosely over a long
the use of this device is to incorporate "what-if" period of time to solve technical and operational
capabilities such that the effects of changing problems. Any modifications that are decided
operational modes can be evaluated. on should be phased over as long a time period
as possible, for maximum economy. Recommen-
SUMMARY dations for any boiler unit will be owner- and
site-specific, and will require a significant degree
Life continuation of a steam-generating system of owner participation to result in a productive
implies an objective of operating the equipment outcome.

REFERENCES
1 "Availability Patterns
in Fossil-Fired Steam Power Plants", "1985-1989 Generating Unit Statistics", North American
EPRI Report No. FP-583-SR, November 1977, Electric Electric Reliability Council Generating Availobility Data Sys-
Power Research Institute, Palo Alto, CA. tern, Princeton. NJ, 1990.
cot.musnolo
Malntalning Availebllity

W. H. Clayton, V. Llinares, and G. C. Thomas, "C-E Availa- tinuation Needs': Proceedings of the 1988Joint ASMEIIEEE
bility Data Program", Proceedings of the American Power Power Generation Conference, Philadelphia, PA. September
Conference, Vol. 42. Chicago, IL: Illinois Institute of Tech- 25-29, 1988, ASME Paper No. 88-JPGC-Pwr-37.
nology, 1980.
10 J. S. Baylor, "Acid Rain Impacts on Utiliw Plans for Plant
V. Llinares, M. B. Caron, E. 1. Schmidt, and F. J. Szela, Life Extension", Public Utilities Fortnightly, March 1. 1990.
"The C-E Availability Data Program 1982: Furthsr Develop-
ments on MTTR and MTBF Analysis", presented at Ninth J. D. Fishburn et al., "Approaches for the Determination
Annual Engineering Conference on Reliability for the Elec- of Remaining Life in High Energy Piping Systems", P m
tric Power Industry, Hershey, PA, June 16-19, 1982. ceedings of the American Power Conference, %I. 50, Chicag~
IL: Illinois Institute of Technology, 1988.
V. Llinares and A. B. Lutz, "Long Range Forecast and
Availability Improvement Program", Proceedings of the 1985 T. McColloch, J. D. Fishburn, G. E. Roberts, and G.
Joint ASMEIIEEE Power Generation Conference, ASME Hunter, "Evaluating the Structural Integrity of High Energy
Paper No. 85-JPGC-Pwr-9. Piping Systems on Fossil Boilers", presented at the Second
EPRI Fossil Plant Inspections Conference San Antonia TX,
5 "Availability Improvement Program", Division of Power November, 1988.
Production, Tennessee Valley Authority, Knoxville, TN,
1977. '
1' R. !I Aubrey, B. A. Hawkins, and T. D. Jamison "The Use
of Oxide Scale Thickness Measurements in Life Exten-
6 S. S. Blackburn and D. E. Lyons, "Design for Availability- sion Analysis", presented at ASNT 1989 Spring Confer-
An Update", Proceedings of the American Power Conference, ence, Charlotte, NC, March 22, 1989.
Vol. 39349-368, Chicago, IL: Illinois Institute of Technol-
ogy, 1975. l3 J. D. Fishburn and R. W. Loomis, "Life Extension of Thick-
Walled Components", presented at 11th International Con-
C. H. Gilkey and J. D. Rogers, "A Summary of Experiences ference of the AMIME, Irapuato, Mexica November 2-4.
with Fan-Induced Duct Vibrations on Fossil-Fueled Boil- 1988.
ers'', Proceedings of the American Power Conference, Vol.
37:728-734, Chicago, IL: Illinois Institute of Technology, l4 F. V. Ellis, R. W. Loomis, and S. Tordonata "Life Extension:
1975. The C-E Approach to the Analysis of Thick Walled Com-
ponents'', presented at Conference on Life Extension and
"Extending the Lifespan of Fossil Plants", EPRI Journal, Assessment of Fossil Plants, EPRI, Washington, June, 1986.
June 1983, Electric Power Research Institute, Palo Alto, CA.
"Generic Guidelines for the Life Extension of Fossil FueI
l5 B. W. Roberts, I? V. Ellis, and R. Viswanathan, "Utility Sur-
vey and Inspection for Life Assess'ment of Elevated Tem-
Power Plants", EPRI Report No. CS-4778, November, 1986, perature Headers", Proceedings of the American Power
Electric Power Research Institute, Palo Alto, CA. Conference, Vol. 47:259-301, Chicago, IL: Illinois Institute
D. E. Gelbar and S. J. deMello, "Assessing Boiler Life Con- of Technology, 1985.
- -.

CHAPTER 25

Combustion Engineering
Research and Development Facilities

T is chapter will describe the laboratory facil-


ities that Combustion Engineering has as-
sembled for conducting research and develop-
programs sponsored by private organizations,
including its customers, as well as those funded
by the federal Department of Energy, the Elec-
ment in the power generation field. The facilities tric Power Research Institute, the Environmental
range from small, sophisticated devices for ex- Protection Agency, the Gas Research Institute,
amining the microstr,ucture of various fuels and and other similar governmental and institu-
materials, to large furnaces which permit testing tional organizations.
of full-scale commercial components such as The implementation of most research and de-
firing systems. The focus of C-E research and velopment programs requires the integration of
development is quite broad, covering such areas efforts from many disciplines within the labora-
as troubleshooting for customers who are expe- tory complex. For example, if the owner of a
riencing problems, improvement or optimization large steam generator is contemplating a switch
of present designs, and the investigation and de- to a new fuel, know-how is required in the areas
velopment of new concepts. - . .. of fuel combustion and fireside effects, heat
A common goal in most of the work conducted transfer, and environmental consequences. The
in these laboratories is the generation of less- C-E facilities are structured so that the appro-

..
expensive electrical power in an environmentally priate expertise exists in the following func-
acceptable fashion. More efficient fuel utiliza- tional groups:
tion, greater component availability, and longer Fuels Technology
component life represent some of the specific R Fuel Systems Development
and D objectives which support the overall goal.
Combustion Engineering strongly believes
. Mechanical Systems Development

.
that a well-equipped laboratory which is staffed Chemical Systems, including Water Tech-
with highly skilled personnel is mandatory to nology

.
stay at the forefront of power-generation tech- Chemical Analytical Services
nology. The C-E laboratory facilities are used 4 Materials Technology
for conducting company-sponsored projects and Electrical Systems
COMBSnON
.
Combustion Engineering Research and Development Facilities

The equipment and facilities described in this and gaseous reaction products. The combustion
chapter are located in the C-E Kreisinger Devel- kinetics of a broad range of coals, petroleum
opment Laboratory (KDL) in Windsor, Con- coke, coal-derived synthetic fuels, and refuse-
necticut. The laboratory is named after Henry derived fuel (RDF) have been studied in the
Kreisinger, Combustion Engineering's first Di- DTFS, as described in Chapter 2 under Char Re-
rector of Research. Past accomplishments of activity. Knowledge gained from this facility has
KDL have directly led to the development and been used in conjunction with C-E's computa-
improvements of the steam-generation, fuel- tional boiler models to successfully predict
burning, fluidized-bed, ash-handling, and emis- carbon loss in large coal-fired boilers (see Chap-
sion-control technologies that are presented in ter 6).The DTFS has also provided basic data on
this book. For example, KDL's work on water-side the formation and control of emissions such as
technology associated with high-pressure steam nitrogen oxides, dioxins (from RDF firing), and
generators forms the basis for our entire Chap- organic hydrocarbons.
ter 20 on power-plant water technology. FIRESIDE PERFORMANCE TEST FACILITY
Fuel properties that affect suspension-fired
FUELS TECHNOLOGY boiler performance are evaluated in the Fireside
Performance Test Facility (FPTF), a 4-million
The Fuels Technology group performs basic Btulhr (1.2 MW) pilot-scale combustion facility
and applied research which focuses on the char- (Figs. 2, 3, and 4). Performance areas addressed
acterization of fuel properties and the impacts include solid-fuel handling and pulverization,
of these properties on the design and perform- combustion, ash slagging and fouling, fireside
ance of steam-generating equipment. Work in corrosion, flyash erosion, and gaseous and par-
fuels technology centers on the broad areas of
combustion, and the handling and processing of
fossil fuels. Typical projects range from bench-
scale determination of combustion kinetics to
pilot-scale evaluation of boiler fireside effects
and flue-gas emissions. Such bench- and pilot-
scale evaluations provide detailed quantitative
fuel performance data that can be applied to the
setting of key boiler design parameters, or that
can be used to predict significant operating and
performance changes when switching fuels on
existing units.
DROP-TUBE FURNACE SYSTEM
Fundamental studies of the reaction kinetics
of solid fuels during combustion and gasification
processes are conducted in KDL's Drop-Tube
Furnace Systems (DTFS),Fig. 1.Two DTFS's are
available to provide controlled high-temperature
environments representative of suspension-fired
commercial systems. A schematic diagram of a
DTFS is given in Fig. 3 of Chapter 2. The devola-
tilization, combustion, and gasification reac-
tions that take place in the furnace can be
detected and by analysis of the solid Fig. 1. Drop-Tube Furnace System (WFS)
.... .- COMBUSTION I

Combustion Engineering Research and Development Facilities I

ticulate emissions. The facility operates through- sion activity, ash-deposit buildup rates, the
out the range of conditions actually found in influence of deposits on heat transfer, and the
large central-station boilers, regarding flame and ease of deposit removal. Flyash erosion rates are
gas temperatures, furnace residence times, and measured in a high-velocity test section down-
gas velocities. Testing typically focuses on estab- stream of the convection test section. An elec-
lishing fuel-related operational limits in the var- trostatic precipitator (ESP) follows the erosion
ious performance areas. section to evaluate flyash collectibility and
In the radiant section of the test furnace (Fig. resistivity; a more detailed description of the
3), a series of simulated waterwall panels collect ESP is given later in this chapter. A by-pass loop
slag deposits which are studied for their physi- is also available for conducting tests on selective
cal and chemical properties, their ease of re- reduction of various regulated gaseous emis-
moval, and their heat-transfer characteristics. A sions. Continuous-sampling and analysis equip-
series of probe banks in the convection-passsec- ment allows measurement of particulate and
tion (Fig. 4) is used to determine fireside corro- gaseous emissions.
The quantitative performance data obtained
from the FPTF is used with C-E's computational
boiler models to optimize new designs and to
predict performance of existing boilers under
other-than-design conditions. The FPTF has
Erosion Probe been used to predict the burning and ash-
deposition characteristics of many U.S. and for-
Flyash Erosion Duct eign coals, coal blends, synfuels, beneficiated
coals, and coal-water mixtures.
FLUIDIZED-BED TEST FACILITIES
Fuel and sorbent performance during fluid-
ized-bed combustion are characterized in a
I Superheder Probe Banks
4 Banks

Burner
Secondary Air

Bottom Ash Discharge ---/ PriAav Air


and Fuel
Fig. 2. Fireside Performance Test Facility (FPTF) Fig. 3. Waterwall test panel in lower furnace of FPTF
comnoH
Combustion @neeringResearch and Development Facilities

Fig. 4. Upper furnace section and convection-pass sections of FPTF

4-inch (100 mm) diameter: fluidized-bed reactor. plex designed to develop advanced firing-system
This apparatus provides highly controlled con- concepts and to evaluate the combustion per-
ditions for assessment of devolatilization rates, formance of a wide range of fossil fuels. The sup-
char reactivity, and fragmentation and attrition port equipment provides maximum, investigative
properties of various solid fuels and additives. flexibility in preparing and handling conven-
The reactivity and attrition attributes of dif- tional fuels such as pulverized coal, fuel oil, and
ferent sorbents for sulfur capture can also be natural gas, as well as alternative fuels such as
established under actual fluid-bed operating coal-water and coke-oil mixtures; water-in-oil
conditions. emulsions; coal-derived solids, liquids, and
gases; and muni'cipal solid wastes, A pulveriza-
tion facility which is part of the research com-
FUEL SYSTEMS DEVELOPMENT plex produces commercial-size pulverized coal
for the test furnaces. Located adjacent to the pul-
Fuel systems development work focuses on verization facility is a pilot plant for producing
large-scale handling, processing, and combus- coal-water fuel (CWF) and for the storage and
tion characterization (including gaseous emis- pumping of CWF.
sions control] for a wide range of fossil fuels. FULL-SCALE BURNER FACILITY
%pica1 projects range from designing and assess-
ing oil-atomizer performance to full-scale firing Commercial scale suspension-firing systems
systems development. are developed and optimized in this facility. It
has a maximum firing rate of 100 million Btulhr
FIRING SYSTEMS DEVELOPMENT COMPLEX (29 MWJ heat input on coal and 300 million
This installation, Fig. 5, integrates three com- Btulhr (88 MWJ heat input on liquid fuels. Fur- _.

mercial-scale test furnaces into a research com- nace configuration and heat absorption can be
COMBUSTION
Combustion Engineering Research and Dewlopment Facilities

FSBF Particulate
Full-Scale Burner

Stack Sampling Shed

Pulverized Coal Storage


Rod Scrubber System

uxiliary Pneumatic Storage


and Feed System

Fig. 5. Arrangement of firing systems development complex

adapted to simulate various commercial furnace (20 MJ on liquid fuels and 25 million Btulhr
applications. (7 MJ on coal. It is used to develop smaller scale
The primary use of this installation is to de- central-station o t large-scale industrial ignition
velop and test central-station scale single-register and firing systems, and to allow measurement of
burners and fuel-admission assemblies. Typical pertinent combustion-related phenomena.
test programs carried out in the full-scaleburner
facility center on characterizing burner combus-
tion performance in terms of gaseous and par-
ticulate emissions, combustion efficiency, flame
stability and shape, and other commercially im-
portant parameters such as turndown capability.
Associated instrumentation provides the means
for monitoring both in-flame and downstream
flue-gas combustion-related phenomena. New
firing systems are optimized through iterative
testing and modification, with support often
given by other segments of the complex such as
the Atomizer Test and the Burner Aerodynamics
Facilities discussed below.
SUB-SCALE BURNER FACILITY

This facility (Fig. 6) has essentially the same


capabilities as the full-scale burner facility, ex-
cept for the firing rate, which is 70 million Btulhr Fig. 6. Sub-scale bumer facility
-.
COMBmIIOW
Combustion Engineering Research m d D~wlopmenfFacilities

ATOMIZER TEST FACILITY late the inflowing combustion air stream-so as


to promote ignition and flame stability, and to
This equipment is used to characterize the per-
produce the correct flame shape. One prime
fornance of full scale liquid-fuel atomizers (up method of obtaining burner ignition stability is
to 10 U.S. gallons per minute or 0.6 litersls capa- to employ swirled airflow, which generates in-
city) in a non-combustion environment. The ternal recirculation of hot combustion gas. The
facility is uniquely designed to provide optical
magnitude of swirled combustion air in the
access to the fuel spray. This facilitates the deter- burner also has an important bearing on NO,
mination of droplet size distribution, droplet
emissions. A swirler test apparatus is used to
velocity, and droplet trajectory using non-
measure the angular momentum of the swirled
intrusive instrumentation such as double-spark air and to thereby quantify the performance of
photography and laser-diffraction techniques. various designs of swirlers.
This installation has proven to be a valuable tool
The overall aerodynamic characteristics of
in designing high-performance atomizers for
burners and fuel-admission assemblies are also
many liquid and slurry fuels. Atomizer design is
studied in the burner aerodynamics facility,
further enhanced by the use of proprietary per-
Fig. 7. Full-scale and partial-scale transparent
formance-prediction software.
~lasticmodels facilitate flow measurement and
BURNER AERODYNAMICS TEST FACILITY visualization in cold flow experiments. Burner
aerodynamics are evaluated first with flow-
A key function of wall-fired steam-generator visualization techniques that are recorded on
burners, as described in Chapter 12, is to manipu- videotape and film, and second, quantitatively

Fig. 7. Flow visualization evaluation of a single-elevation fuel-admission assembly


COMBUSnON .&.
Combustion Engineering Research and Development Facilities

by three-dimensional velocity- and pressure-


mapping.
Aerodynamic data is used in the development
of new burners through the interpretation of
velocity-vector maps, to calculate the total areas
and velocities of near-field recirculated flows,
and to compute pressure-loss coefficients.
BOILER SIMULATION FACILITY

This large facility is designed to accurately


model the furnace and convective-pass sections
of a large suspension-fired steam generator (see
Figs. 8 and 9). It can be configured alternately
with 3 to 6 elevations of tangential fuel-injection
assemblies, for a total of between 12 and 24 as-
semblies. The unit has a nominal rating of 50
million Btulhr (15 MW,) when burning pulver-
ized coal and 100 million Btulhr (30 MWJ when
burning oil or gas. The firing system can also be
arranged to demonstrate a multiple burner array
for wall-fired systems, or with a stoker for indus-
trial and refuse-fired applications. The facility
also has additive-injection, flue gas recirculation,
and reburn-fuel injection capabilities.
The boiler simulation facility is specifically de-
signed for the study of total boiler phenomena. Fig. 8. Boiler Simulation Facility (BSF) arrangement
This includes SO, capture by sorbent injection,
and advanced in-furnace combustion and post-
combustion techniques for NO, emissions con- of either dry pulverized coal or wet filter cake.
trol, such as reburning, air staging, or flue-gas Capabilities exist to produce CWF prepared from
treatment using urea or ammonia injection, as coal ground to usual boiler standards (approxi-
described in Chapter 15. The facility will accu- mately 70 percent through 200 mesh) or to fur-
rately model the timeltemperature history, heat ther grind the coal feedstock to produce CWF
release, and heat absorption of a large central- using micronized coal (with particle size below
station boilea It incorporates all the major as- 10 micrometers).
pects of such a large unit, including the lower fur- The pilot-plant CWF production equipment
nace, ash hopper, firing zone, nose section, and allows evaluation and scale-up of specific fuel
upper-furnace. The unit also includes waterwall formulations developed in the laboratory, as well
panels and convective heat-transfer surfaces that as assessment of various processing-component
duplicate the thermal and aerodynamic condi- design. Process parameters can be optimized
tions of commercial boilers. with respect to fuel handling and combustion
performance. Complete analytical capabilities
COAL-WATER FUEL PILOT PLANT
support the CWF research activities and pro-
This facility is used to study the formulation vide CWF-product quality control. CWF's made
of coal-water fuels (CWF) and to produce CWF in this pilot plant have been used in numerous
test samples for research applications. It has a research and development programs, includ-
processing capacity of approximately 1,000 lblhr ing those addressing boiler, gas-turbine and
(0.13 kgls) of fuel. The facility can use feedstocks diesel-engine applications.
COMBUSRON
-
Combustion Engineering Research and Development Facilities
-
FLOW MODELING
Flow modeling at KDL uses both physical and
computer methods (see Fig. 10). Physical model-
ing requires the design, construction, and test-
ing of prototypical models using an appropriate
fluid. Working fluids can be air, water, or some
other medium-including multi-phase fluids or
components such as solid particles or liquid
droplets-depending on the problem under
study. Flow modeling is used for analyzing pul-
verized-coal and fluidized-bed boilers, heat-
recovery steam generators, gasifiers, flue-gas
desulfurization spray towers, fabric filters, elec-
trostatic precipitators, and dry scrubbers. De-
pending on the specifics of the problem, two
dimensional water-table models or three-dimen-
sional airflow models are employed.
Qualitative flow visualization plays a dominant
role in analyzing many process-equipment situ-
ations. This technique is used in conjunction
with two- and three-dimensional physical model-
ing. The two-dimensional technique is a valuable
tool in reducing the design effort necessary to
achieve optimum equipment performance. Based
Fig. 9. Boiler Simulation Facility in operation on qualitative results and the complexity of the

MECHANICAL SYSTEMS
The mechanical systems group performs basic
and applied research in areas of heat and mass
transfer, fluid dynamics, thermal hydraulics
and two-phase (steamlwater) flow, erosive wear,
pulverization, bulk-material handling, two-com-'
ponent flow, and particle separation. Customized
engineering studies provide cost-effective solu-
tions to design, operational, or maintenance
problems at existing boiler plants.
Mechanical-systems research revolves around
process modeling, using a combination of exper-
imental and analytical methods. Extensive use is
made of physical modeling and statistical tech-
niques, in conjunction with computational
modeling. Mechanical design and testing of var-
ious power-plant components support programs
for steam-generator upgrading and improve- Fig. 70. Large-scale furnace aerodynamic
ment of plant performance. test facility
COMBUSTION
Cotnbustion Engineering Research and Development Facilitles

process configuration, field implementation may mation generated, the erosivity of a coal flyash,
follow; alternatively, three-dimensional flow test- process solid, or other material can be deter-
ing is conducted for the most promising solu- mined and recommendations made to lessen
tions. Flow-visualization methods include the use wastage of pressure-part tubing or other boiler
of smoke injection, 'yarn streamers, or particle components.
seed material. Design changes are first screened FURNACE AERODYNAMICS TEST FACILITY
visually before quantitative data is collected. This large-scale test facility (Fig. 10) is a focal
Quantitative component optimization is point in the ongoing study of suspension-fired
achieved through evaluation of changes in flow furnace aerodynamics at C-E. It has been used
fields due to geometric alterations within process for many applied research and development pro-
equipment. Flow-field changes are arrived at
grams, including the design of retrofitable low-
using pressure and temperature measurements excess-air firing systems for NO, reduction and
combined with gas sampling. Sampling devices the evaluation of upper-furnace sorbent injection
are controlled by one of many host computers systems for SO, removal.
-
located throughout the laboratory. A central data-
HEAT-TRANSFERAND ..
acquisition system configures the information
into permanent files and loads it into the KDL CORROSION TEST LOOP
mainframe computer. The principal measure- This major laboratory installation (Fig. 12) is
ment system is called the Automatic Probe used to investigate heat-transfer or corrosion on
lkaversing Device ( Fig. 11)and is used for secur- the water or steam side of steam-generator tub-
ing quantitative data from &dimensional models. ing. The pumps, piping, and instrumentation can
ASH-EROSION TEST FACILITY operate at up to 800F and 4,000 psig (430C and
28 MPa gage) in order to test at supercritical pres-
In this test stand, furnace-tube material speci- sure and temperature conditions. Heat input is
mens are eroded in crossflow conditions that are electrically controlled by four separate circuits,
both controlled and measured using state-of-the- with a total capacity of 1.5 megawatts. The loop
art instrumentation and controls. From the infor- controls are fully automatic, which permits con-
tinuous operation with minimal operator atten-
tion. This loop has been used to test commercial
boiler tubing for applications to fossil-fuel
boilers, nuclear steam generators, and solar-
receiver boilers.
ELECTROSTATIC PRECIPITATOR PILOT PLANT
A pilot-scale ESP at the flue-gas discharge of
the Fireside Performance Test Facility (FPTF) is
used to compare the characteristics of two or
more different coal flyashes under similar ESP
operating conditions; see Fig. 13. The length,
plate spacing, electrode design, rappers, power
supply, and specific collecting area (SCA) simu-
late a commercial ESP, as described in Chapter
15. Since the aspect ratio is significantly differ-
ent from a full-size ESP, the results from this pilot
facility cannot be directly applied to the design
or performance of a commercial unit, but must
be used in a design program with appropriate
Fig. 11. Automatic Probe Traversing Device scale-up factors.
--
COMnusnoli
Cornburtior Engineering Research and Development Facilities
.-

Fig. 72. Heat-transfer and corrosion test loop

The exhaust flue-gas stream from the FPTF HIGH-PRESSURE TEST FACILITIES
passes through a gas cooler to provide a desired C-E has several high-pressure steam-water test
inlet-gas temperature to the ESP. Isokinetic sam- facilities for steam-generator component test
ples of the flue gas and flyash are taken at the and evaluation, incorporating a 30-MW, high-
inlet and outlet to determine dust loading, and pressure boiler capable.of operating at pressures
gas flow rate, temperature, and moisture content. to 3,000 psig (21 MPa gage). Steam-water mix-
In-situ ash resistivity and gaseous SO, measure- tures from the boiler are used to provide operat-
ments can be made during testing, as well as the ing environments to evaluate components of
electric power consumption of the ESP. After fossil and nuclear steam supply systems.
testing, the isokinetic dust sample and dust sam- Components tested have included:
ples collected in the hopper beneath each ESP steam-water separators
field are analyzed for resistivity and particle size
pilot-scale nuclear steam generators
distribution. This data is analyzed to determine
dust-collection efficiency as a function of the safety and isolation valves
above variables. The efficiencies obtained in the one-fifth scale nuclear circulating pumps
facility are then used to verify or adjust efficiency W Combined Circulation@ boiler circulating
calculations by utilizing ESP design programs. pumps
h COMBUSTION
Combustion Engineering Research and Develc~pmentFacilities

The chemical systems group is responsible for


Flue-Gas Inlet developing water-treatment procedures essential
to maximizing fossil-fired steam-generator avail-
ability. Their experimental work includes the
investigation of ion-exchange technology, opera-
tional and out-of-service corrosion protecticn,
chemical cleaning, and water treatment methods.
Boiler owners can take advantage of Kreisinger
Development Laboratory consulting services to
have tube failures analyzed, to resolve operating
problems, or to be brought up-to-date on cur-
rent technology in the above areas.
As described in Chapter 20, steam-generator
tubes collect internal deposits during operation.
Because these deposits may promote corrosion
or cause t u b ~ sto overheat, it is necessary to
remove the deposits periodically by chemical
cleaning. A Chemical Cleaning and Coatings-
Evaluation Test Loop is used to evaluate new
chemical solvents and to test the effectiveness of
standard solvents on unusual deposits. Testing
is done under dynamic conditions to simulate
actual boiler operation and to find out if a cer-
tain chemical-cleaning operation will be effective
in the field:
Fig. 13. Electrostatic precipitator test facility: plan and
elevation views .

The facility shown in Fig. 14 was used to test a


family of nuclear primary-system safety valves.

CHEMI'CAL SYSTEMS
Work in this area focuses on water and steam
chemistry, internal and external boiler-tube cor-
rosion, and both basic and applied research in
the area of environmental control systems. Typi-
cal projects may deal with boiler cleaning and
pressure-part materials testing, the determina-
tion of thermal conductivities of water-side tube
scale, and the development of new technologies
for flue-gas cleaning. Controlled-temperature
probes and integral tubing samples are used to
provide design information on external corrosion
for alternative pressure-part material selections.
These efforts are coordinated with the activities
of the metallurgical and materials specialists in
the laboratory. Fig. 14. High-pressure steam-water test facilities
COWBVSTlON
Combustion Engineering Research and Development Facilities

FLUE-GAS CLEANING arate SO, or H,S from flue gas, coal-gasification


PROCESS DEVELOPMENT product gas, or natural gas, using electrical po-
Much of the process development work for the tential as the driving force. The electrochemical
wet-scrubbing flue-gas desulfurization system process operates at high temperature and is simi-
lar in many ways to molten-carbonate fuel-cell
described in Chapter 15 was done by the chemi-
technology. A bench-scale facility (Fig. 16) has
cal systems group in both pilot and bench-scale
facilities. Test programs provided information been assembled to investigate this process.
needed to quantify gas-to-liquid absorption, prod- Many of the development tasks or process
uct crystallization, absorbent reactions, and questions addressed by chemical systems person-
product properties affecting sludge disposal. nel may use such bench-scale apparatus, or infor-
Interpretation and correlation of the generated mation may be obtained from more conventional
data was facilitated by the developmeht of mathe- chemical laboratory equipment. As an example:
matical models which describe unit operations. data on calcination and sulfation of limestone in
These models later became part of the design fluidized-bed combustors were obtained on a
procedure now used for commercial FGD standard thermogravimetric analyzer. The infor-
systems. mation on reaction rates, temperature effects,
The process of removal of SO, and other acid and particle-size effects was then used to develop
equations for overall modeling of sulfur capture
gases such as HC1 and HF in a spray-dry absorber
in the coal-fired fluidized beds.
has been described in detail in Chapter 15. A
pilot-scale facility (Fig. 15)in KDL has been used
to advance the development of dry scrubbing for
application to central-station, industrial, and CHEMICAL ANALmlCAL
municipal-refuse burning boilers. SERVICES
Chemical systems development work is also
dedicated to advanced concepts for gas cleaning This group utilizes a modern chemical labora-
such as the use of permeable membranes to sep- tory to provide comprehensive chemical and

Fig. 15. Dry-scrubbing pilot-scale facility for flue-gas desulfurization development


COMBUSTION % j
Combustion Engineering Research and Development Facilities
I

support field start-up, performance testing,


and maintenance activities -

provide analytical and consultative services to


C-E equipment owners ';

The highly qualified staff of chemists and tech-


nicians actively participates in TAPPI and A S M E
committees, and in ASTM committees on coal
and water analysis.
The analytical laboratory has a full comple-
ment of state-of-the-art instruments to provide
accurate data on a whole range of sample analy-
sis, including:
graphite furnace atomic absorption
thermogravimetric anaIysis (Fig. 17)
differential thermal analysis
.
Fig. 16. Bench-scale facility for investigating elec- ion chromatography
trochemical gas cleaning process x-ray diffraction and fluorescence (Fig. 18)
physical testing of fuels and boiler-related struc- inductive-coupled plasma spectrometry
tural materials. The prime functions of this group (Fig. 19)
are to: mercury porosimetry
support the fossil-fuel research and develop- BET surface area measurement
ment activities particle size analysis

Fig. 17. Therrnogravimetric analyzer


-
COMBUSTION
.
Combustion Engineering Research and Development Facilities

The analytical laboratory is a fully equipped


fuels laboratory that can provide a full-spectrum
analysis on any type of solid or liquid fuel. It has
capabilities in water analysis, boiler tube exami-
nationlfailure analysis, and metal analysis.
The chemical analytical services group is fre-
quently called upon to support activities in the
following areas:
life-assessment programs on boiler pressure
parts
fuel-blending studies
pulverizer abrasion
environmental and industrial-hygiene aspects
of steam-generating-unit operation
analyses of refuse fuels, black iiquor;boiler-
tube deposits, fuel additives, and chemical recov-
Fig. 78. X-ray diffractometer for compound identifi- ery unit byproducts, besides the analysis of con-
cation of crystalline materials ventional fuels.

Fig. 79. Inductive-coupledplasma spectrometer for determining inorganic elements in solution


COMBUSTlON
Combustion Engineering Research and Development Facilities

failure analyses, and life-continuation pre-


MATERIALS TECHNOLOGY. dictions.

The close interaction of materials technology


with all phases of materials usage is essential for
ELECTRICAL SYSTEMS
the successful design, fabrication, and service The electrical systems group develops instru-
behavior of a boiler and its associated equip- mentation and software for the power industry,
ment. To attain this end, a laboratory works as well as for internal C-E research and develop-
closely with engineering, manufacturing, quality ment programs. In addition, it provides engineer-
control, and field services. A continuous process ing and technical service support for KDL's
of feedback and information exchange between instrumentation, data-acquisition, control, and
laboratory and functional departments assures electrical-power requirements.
that material-related needs and problems are
properly addressed. This process has resulted in LASER LABORATORY
the materials technologists at C-E contributing The laser laboratory develops specialized opti-
to achievements that include: cally based measurement sy9tems. These are
Production of the first welded boiler drum in intended principally for commercial use, such as
America fabricated to ASME Code specifications the OPSIZETMin-situ system for measuring the
Development of the low-hydrogen welding particle size of solids flowing in pneumatic trans-
electrode, which has since become a universally port pipes (shown in Fig. 20 and described in
used electrode in industry Chapter 13). Examples of research tools used
Successful welding of the first stabilized in other KDL projects include such instruments
stainless-steel pressure vessel as a Laser Doppler Anemometer (LDA),a Laser
Design and fabrication of the first commercial Methane Pacer system (LMT), and a Void-
reactor for nuclear power generation Fraction Measurement system (VFM). The LDA
non-intrusively measures velocity in flow-
Development of the large welded-wall water- modeling, erosion, and component-development
wall panel, a design innovation later adopted in programs. The LMT measures mixing and resi-
boiler manufacture throughout the world
dence time in flow models, and the VFM deter-
8 Development of the modified 9Cr-1Mo ferritic mines the void fraction in liquidlair systems.
alloy for high-temperature service, which has
been widely adopted for pressure-containment
components
Formulation and development of a superior
hardfacing alloy for use in coal pulverizers
8 Development of surface-modification proce-
dures, chromizing in particular, for protecting
metallic boiler components against hostile
environments
The laboratory facilities available to C-E mate-
rials personnel make the continuation of such
achievements possible. Modern equipment and
highly skilled specialists in the areas of analyti-
cal chemistry, metallography, and mechanical
properties determination- all fundamental tools
in the study of materials-are continually em-
ployed in alloy development, surface protection, Fig. 20 C.E OPSIZE" in-situ particle size analyzer
COIQIUSnON
Combustion Engineering Research and Development Facilities

INSTRUMENTATION LABORATORY acquisition and reduction network. This n&ork


is Ethernet-based, with the central computer act-
This is a multi-functional laboratory used to ing as a file server for all KDL test-facility data-
satisfy several needs within KDL. It is used for the acquisition computers and the many engineer-
initial bench testing of specialized measurement ing work stations. The central computer simul-
systems which are not optically based. Instru- taneously provides printing services to the
ments developed by Electrical Systems for com- various output peripherals such as plotters and
mercial offering, such as the Mach ThermTM printers.
acoustic temperature-mapping system, an en- The central computer is also a development
hanced acoustic leak-detection system, and re- machine for -several Combustion Engineering
cently, a new digital flame-scanner system, were Total On-Line Performance System (CETOPS)
all initially tested in the instrument laboratory. modules. The Interactive Chemistry Manage-
This laboralory is also used to test, calibrate, ment System (ICMS) used to monitor and con-
and repair instruments and electronic compo- trol boiler water chemistry was developed in KDL
nents used in KDL facilities. Electronic test using this facility, as were various parts of the
equipment and calibration standards which are On-Line Thermal Information System diagnos-
traceable to the National Institute of Standards tic module (OTIS)and the Boiler Stress and Con-
and Technology (NIST) are maintained by a quali- dition Analyzer module (BSCA), all of which
fied technical staff for this service. Such stan- were described in Chapter 13.
dards are maintained in temperature, pressure,
force, and displacement. Pressure calibrations ELECTRICAL ENGINEERING SERVICES
from 0.01 in.WG to 12,000 psig (2.5 Pa to 83 MPa Electrical Systems also provides electrical engi-
gage), including differential pressure at 4,500 neering services to KDL; these center around the
psig (31MPa gage) static pressure, are performed. design, construction, and maintenance of in-
Temperature'calibrations are done for the entire strumentation, data-acquisition, control, and
International Practical Temperature Scale (except power systems for the various test facilities. Staff
for the cryogenic range), force to 200,000 pounds members design these systems, which cover a
(445 kN), and displacement to 20 inches (500 range from high-speed data-acquisition systems
mm). for transient fluid dynamics studies to megawatt-
sized electrical heating systems. By having this
CENTRAL COMPUTER FACILITY capability in-house, the Kreisinger Laboratory
Electrical Systems designed and installed, and can respond quickly to facility design changes
now operates and maintains, KDCs central com- necessary to satisfy research-program and cus-
puter facility, the hub of the laboratory's data tomer needs.
Appendix A. Coals of the .World

This appendix is comprised of two sections. The estimates of economically recoverable


The first has reference data on all the coals of all coal are at best approximate, and depend just
producing countries of the world; approximate as much on economic and political con-
reserves are given, along with some historical siderations as they do on exploratory tech-
and geographical information. Analyses of the niques. There are no universally agreed upon
coals and their ashes, along with fusibility definitions of reserves and resources, many of
data, are included to be used in preliminary de- them being a function of quantity of overbur-
sign of boilers to burn coals from these coun- den or depth of mining. And, depending upon
tries. The data are not intended and are not the source of data and the purpose for which it
adequate for the actual design of a steam was gathered, the values may represent undue
generator to burn a specific local fuel. Mine or optimism or conservativeness.. In any case,
core samples, or detailed fuel analyses, are they should be read in the context of this state-
needed for that purpose. ment by Carroll Wilson (Future Coal Prospects:
The International Systems of coal classifica- Country and Regional ' Assessments-the
tion are described in the second section. These World Coal Study, 1980):". . . the use of differ-
systems result from a significant effort to ent fuels is heavily constrained by decisions
categorize in a consistent, rational manner all made in the past and by the fact that new energy
the different coals (excluding peat) found facilities being planned now cannot be brought
worldwide. This is vitally important where en- to completion in less than 5 to 10 years. The
gineers from one country are involved in the substantial shift to coal will therefore begin in
design of fuel-preparation-and-burning equip- the mid to late 1980's based on decisions made
ment, steam-generating equipment, or ash- in the early,1980's. Major effects of this expan-
handling systems for another country where sion will be felt in the 1985-2000 period.. .
coals may be designated by local custom rather The full effects of the switch to coal will, how-
than on a useful engineering basis. ever, not be seen until the early decades of the
Sources of information for the statistical and next century."
analytical data in this chapter have been fuel
investigations by the C-E Kreisinger Devel-
opment Laboratory; publications of the U.S. ANALYSES BY CONTINENT
Bureau of Mines and the Canadian Department AND COUNTRY
of Energy, Mines and Resources; the National
Coal Association, Washington, DC; the World Coal is found on all continents and in most
Energy Conference Surveys of Energy Re- countries throughout the world. Hgwever,
sources; the Report of the commission of In- some countries, such as Italy and Sweden, have
quiry into the Coal Resources of the Republic of resources so meager in proportion to their
South Africa (1975);and COAL-Bridge to the energy demands as to be inconsequential. By
Future, summary report of World Coal Study. far, the largest world coal deposits are located
* * * * in the Northern hemisphere.
In this Appendix, high heat values are given in both Btu Economically recoverable reserves are those
per pound and megajoules per kilogram. Tonnages of coal that can be successfully exploited and used
resources or production are in metric tonnes (2,204.6
pounds). Where a tonne of coal equivalent is shown, it is a within the foreseeable future; they represent
metric tonne of coal with a heating value of 12,600BtuAb, about 1115th of the total world geological re-
7,000kcalkg, or 29.31 MJkg. Because coals vary signifi- sources of solid fuel. The estimated total of such
cantly in calorific value, much more than 1 tonne of subbi-
tuminous, lignitic, or brown coal is required to produce the resources for the entire world is in excess of
energy of 1tonne of coal equivalent (1tce). 600,000 million tce; over 95 percent is found
COMBUSTION
C4aI.sof the World
-
in just 1 3 countries, approximately as follows: BASIS FOR ANALYTICAL DATA
United States 28% A most important consideration in the use of
U.S.S.R. 17% coal analyses is the determination of coal type
People's Republic of China 16% or rank from the data presented. The selection
United Kingdom 7% of pulverizing equipment, for instance, de-
Western Germany 5% pends upon characteristics related to coal rank,
India 5% as does establishing the heat transfer require-
Australia 4% ment and size of an air heater.
Republic of South Africa 4% For the best use of world coal data, the tabula-
Poland 3% tions in this Appendix make it easy to ascertain
Canada 2% coal rank. Volatile contents and high heating
Brazil 1% values are normalized to a moisture- and ash-
Yugoslavia 1% free basis; ash and moisture contents are given
Eastern Germany 1% on an as-analyzed basis.
The preceding tabulation may very well over- Ash analyses, some of them available from
state the resources of such countries as the U.S. Bureau of Mines and Canadian Depart-
United States and Western Germany in com- ment of Energy, Mines and Resources publica-
parison to the others, because exploration has tions, but mostly done in C-E's laboratory, are
reached a higher level. The eventual resources, given for use in furnace sizing, determining
which disregard climate and other factors mak- convection-pass fouling potential, and design-
ing recovery difficult, of both Russia and China ing ash-transport and storage equipment. All
may be greater than shown. Also, there can be ash fusibility figures are for ASTM reducing
considerable loss in recovering coal, particu- atmosphere, as described in Chapter 3 .
larly in deep mining-and there can be great Regarding the moisture contents shown,
differences between run-of-mine coal and a realize that there can be no assurance that sam-
marketable, ash-reduced product. ples received for analysis have their moisture-
Further general information on the reserves sealing intact, so there can be some air-drying
of all coal-producing countries of the world is before tests occur. In using the moisture con-
found under the individual country headings. tents for pulverizing-system, boiler, and air

Table I.Correlation of Coal Properties (Based on Typical Analyses)


Bituminous .' High-Volatile Bit. Subbituminuus Lignite and
Low VM. Med.141. A B C A B C Brown Coal

Volatile 45 and
Matter (VM) higher
MAF
C
- +H 2.7 and
0 2
lo~ver
(Typical)

Btullb,
MAF

:MJlkg, -
MAF

MAE = moisture- and ash-free


COMBUSTION
Coals of the World

heater design, values must be corrected to CANADA


probable "as-received at the power-plant" Canada (Fig. 1)has over 9,000 million tonnes
moisture. This is particularly important with of economically recoverable coal reserves,
coals that are transported long distances before ranging from anthracite to- lignite. Table I1
analyses, as is frequently the case. shows measured resources (for which tonnages
CORRELATION OF COAL PROPERTIES
have been computed) of immediate interest for
exploration or exploitation activities; gener-
In addition to the ASTM Standards D388, ally, for most regions, coal seams have to be at
Classification of Coals by Rank (Table 11, Chap- least 5-ft thick to be included in this category.
ter 2), a review of the actual coal analyses The resources in the table exclude coal that
presented in this Appendix will produce a cor- may be present north of 60" North latitude and
relation that is useful in preliminary ranking small occurrences known in Newfoundland
of coals based on pr,oximate and ultimate and Manitoba.
analyses. Table I is such a correlation, based on Ninety-five percent of the recoverable re-
a study of analyses of many typical coals. For serves are in western Canada (British Colum-
such preliminary ranking, refer ako to Fig. 1, bia, Alberta, and Saskatchewan), of which
Chapter 2, which is a graphical presentation of about 80 percent can be open-pit mined. As in
ranking parameters. the United States, coals in western Canada are
COAL DEPOSITS OF NORTH AMERICA low in sulfur content, rarely exceeding 0.6 per-
cent on a mass basis, but are high in ash. East-
This section describes the coalfields of ern Canadian coals generally have high
Canada, the United States, and Mexico, with sulfur, particularly those from Nova Scotia.
Alaska being given separate treatment. Approximately 14 percent of the Canadian

Subbituminous
aLignite and Brown Coal
Bituminous and Semianthracite
Fig. 1 Coal Map of Canada
.-
COMBUSTION
Coals of the World

coal produced is bituminous coal from under- are located in four definable regions.
ground mines; the balance is bituminous, 1. The Mountain Region:
subbituminous and lignitic coals taken by Most of the bituminous coal resources are in the
strip-mining. Over 70 percent of the domestic provinces of Alberta and British Columbia
consumption is for power generation; most of (BC),extending in a belt up to 50 km wide from
the balance, for metallurgical uses. the U.S. border, northwest into the East
Production of coal in the year 2000 is esti- Kootenay region of southeastern BC, north into
inated to be between 75 and 115 million tonnes Alberta (in the Crowsnest Pass area) and into
coal equivalent per year. A steadily growing northeastern BC (Fig. 1). The main center of
portion of the production will be used at deposition is located in southeastern BC. Large
mine-mouth plants in the West. In Alberta, for resources are also being found in the Peace
instance, coal is planned to supply about 95 River area to the north.
percent of the province's electrical needs at 2. The Foothills Region of Alberta:
the turn of the century. Canada's coal deposits Coals from this area are mainly of high-volatile
bituminous B and C rank. Mining conditions
Table 11. Measured Canadian Coal are not as severe as in the mountain region, but
Resources of Immediate Interest eventually most of the resources will have to be
(1978) extracted by underground methods.
Millions 3. The Plains Regions of Saskatchewan and
Province and Area Coal Rank of tonnes Alberta:
The four lignite deposits of Saskatchewan are
Nova Scotia
Sydney hvb located along the U.S. border and form the
Other hvb northern fringes of the main lignite zone cen-
Subtotal hvb tered in North Dakota. The subbituminous
New Brunswick seams of Alberta underlie the southern part of
Minto hvb that province from the Rocky Mountains in the
Other hvb west to their outcrops about 250 km farther
Subtotal
east, and form an immense arc from the U.S.
Ontario lig
border up to about 56"N latitude, passing east
Saskatchewan
Estevan lig of the cities of Calgary and Edmonton.
Willow Bunch lig 4. The Atlantic Region:
Wood Mountain. lig The Cape Breton Island coalfield in Nova
Cypress lig Scotia is the most important of the region,
Subtotal
although a small quantity of - high-sulfur
Alberta
Plains sub bituminous coal is produced by surface mining
Foothills hvb in the province of New Brunswick. The Cape
Mountains lvb-mvb Breton field is located on the north shore of the
British Columbia island, facing the Cabot Strait and the Atlantic
Southeastern lvb-mvb Ocean. The coal is mostly of high-volatile
Northeastern Ivb-mvb bituminous A rank, varying from medium to
Other mainly lig
some sub-hvb high in sulfur content.
Canada total lig Canadian reserves of peat, which have not
sub been surveyed, are thought to be approximately
hvb equal to those of the United States.
lvb-mvb
Table I11 gives the analyses of typical Cana-
lig = lignitic; sub = subbituminous; hvb = high-volatile bituminous:
mvb = medium-volatile bituminous: lvb = low-volatile~bituminous.
dian coals. For the ultimate analyses and ash
constituents, see Analysis Directories of Cana-
.~ COMBUSTION
Coals of the World

Table 111. Analyses of Typical Canadian Coals


-Moisture- and ash-free - ..

Province and Area - - - As received - -H H V Ash ST, Hardgrove


or seam Rank %Ash %H20 % VM 96 S Btullb MJlkg Red., "F Grind.

Nova Scotia
Thorburn Hvab
Broughton Hvab
River Hebert Hvab
Phalen Hvab
Harbour Hvab
Westville Hvab
Sydney Hvab
Joggins Hvab
Inverness Hvcb
New Brunswick
Wnto Hvab
Chipman Hvab
Coal Creek Hvab
Saskatchewan
Bienfait Lig A
Roche Percee Lig A
Alberta
Cascade Sa
Crowsnest Mvb
Coalspur Hvcb
Lethbridge Hvcb
Pembina Subc
Drumheller Subb
Castor Subb
Edmonton Subc
Taber Suba
Camrose Subc
British Columbia
East Kootenay Mvb
Vancouver Island Hvab

dian Coals published by the Canadian Depart- about 30 percent of the currently recoverable
ment of Mines and Technical Surveys, Mines coal reserves. Peat is located in low-lying
Branch, Fuels Division. coastal areas, in the flatlands of the Great Lakes,
and in Alaska.
UNITED STATES
The electric utilities of the U.S. consume 78
Coal is found in 36 of the states and is cur- percent of all the coal produced in the states.
rently mined in about 26. Six states contain The U.S. Geological Survey has divided the,
more than 75 percent of the estimated 245,000 coal-bearing areas of the contiguous U.S. into
million tonnes of economically recoverable re- six main provinces designated as (1)Eastern, (2)
serves: Montana (28%), Illinois (16%), Wyom- Interior, (3) Gulf, (4) ~ o i t h e r nGreat Plains, (5)
ing (13%), West Virginia (9%), Pennsylvania Rocky Mountain, and (6) Pacific Coast. The
(7%) and Kentucky (6%), Fig. 2. provinces are subdivided into coal regions,
The reserves of peat, not detailed in this text, coal fields, and coal districts. (Alaska is treated
are estimated to be equal in heating value to as a separate province.)
--
COMBUSTION
Coals of the World

The Eastern Province gion consisting of the coal field of Michigan;


This includes the anthracite regions of the Eastern region, or Illinois basin, compris-
Pennsylvania and Rhode Island; the Atlantic ing the fields of Illinois, Indiana and western
Coast region, including the Triassic fields of Kentucky; and also the Western region embrac-
Virginia and North Carolina; and the Appalac- ing the coal fields of Iowa, Missouri, Nebraska,
hian region extending from Pennsylvania Kansas, Arkansas, Oklahoma, and the south-
through eastern Ohio, Kentucky, West Vir- western region of Texas. With some excep-
ginia, western Virginia, and Tennessee into tions, the bituminous coals of this province are
Alabama. The Appalachian basin contains the of lower rank and higher sulfur content than
largest deposit of the high-grade bituminous those of the Eastern province. Much of the
and semibituminous coals. The Triassic depos- surface-minable coal in the Illinois basin hav-
its of central Virginia and North Carolina occur ing low chlorine and sodium content has been
in irregular pockets rather than in seams and mined or committed to be mined. Much of the
are at present of little commercial value, be- remaining coal, with high chlorine content
cause of expensive mining and rather low- (above 0.15 percent as fired), will have to be
-grade quality of coal. deep-mined and will comprise a large propor-
The Interior Province
tion of the future production.
The Gulf Province
This province includes all the bituminous
coal area of the Mississippi Valley region and This consists of the Mississippi region in the
the coal fields of Texas and Michigan. This east and the Texas region in the west. The
province is subdivided into the Northern re- Mississippi region includes the lignite fields of

Bituminous
Subbituminous
Lignite
Anthracite and Semianthracite

Fig. 2 Coal Map of United States


COMBUSTION
Coals of tho World

Table IV. Source, Analysis and Classification of U.S. Bituminous Coals -Continued
Moisture- and ash-free
State, County, - As received - H H V - - Classification -
and Bed %Ash %HrO %VM % C % H %O % N % S Btdlb MJlkg FSIA A-ADB ASTMC ICNo.D

Maryland
(Continued)
Allegany,
Tyson 9.1 2.8 21.4 89.0 4.9 2.8 1.9 1.4 15,650 36.4 8% 110 Lvb 434
Ohio
Belmont,
Pittsburgh
No. 8 9.1 3.6 45.8 80.9 5.7 7.4 1.4 4.6 14,730 34.3 6 200 Hvab 635
Morgan,
Middle Kittan-
ing No. 6 8.5 -8.7 45.8 79.4 5.7 10.9 1.5 2.5- 14,340 33.3 4% 2 Hvbb 733
Pennsylvania
Allegheny,
Pittsburgh 7.6 2.6 39.5 84.3 5.6 6.7 1.7 1.7 14,870 34.6 8% 180 Hvab 635
Butler,
LowerFreeport 8.0 3.7 42.0 82.2 5.6 7.3 1.6 3.3 14,970 34.8 5% 75 Hvab 634
Cambria,
UpperFreeport 7.5 1.1 20.0 89.5 4.8 2.9 1.5 1.3 15,660 36.4 9 75 Lvb 334
Clearfield,
LowerFreeport 7.9 2.1 35.4 85.3 5.4 3.8 1.6 3.9 15,360 35.7 7 , 300 Hvab 635
Fayette,
Lower Kittan-
ning 8.8 1.7 29.4 87.8 5.2 3.2 1.5 2.3 15,500 36.0 9 310 Mvb 535
Greene,
Pittsburgh 8.2 1.8 40.6 84.1 5.6 6.4 1.7 2.2 15,160 35.3 9 250 Hvab 635
Indiana,
LowerFreeport 9.7 2.3 24.6 88.5 5.1 3.7 1.5 1.2 15,680 36.5 9 150 Mvb 435
Lawrence,
Brookville 10.1 5.2 42.9 81.5 5.7 7.3 1.7 3.8 14,830 34.5 4% 75 Hvab 634
Washington,
Pittsburgh 5.1 1.6 40.5 84.2 5.6 7.2 1.6 1.4 15,070 35.0 7% 180 Hvab 635
Tennessee
Campbell,
Jordon 3.8 4.7 38.1 83.2 5.4 8.6 2.0 0.8 14,820 34.5 3 -21 Hvab 622
Utah
Carbon, D 7.3 3.3 47.2 80.7 5.8 11.7 1.4 0.4 14,330 33.3 2 -45 Hvbb 711
Carbon, Lower
Sumyside 5.6 4.1 42.9 82.1 5.6 9.3 1.8 1.2 14,770 34.3 5 5 Hvab 633
Emery, Lower
Sunnyside 6.4 5.2 43.2 79.8 5.6 11.8 1.7 1.1 14,260 33.2 3 -35 Hvbb 721
Washington
Kittita3,No. 1
(Big) 8.8 3.7 42.4 81.8 6.0 9.7 1.9 0.6 14,710 34.2 4 5 Hvab 623
Kittitas, No. 5
(Rosl~n) 9.9 2.9 45.1 82.7 6.2 8.6 2.0 0.5 14,920 34.7 4 35 Hvab 623
b i r COMBUSTION
Coals of the World

Table IV. Source, Analysis and Classificationof U.S. Bituminous Coals -Continued
Moisture- and ash-free
State, County, - As received - -HHV - Classification -
and Bed % ~ s h90H,O YO.VM % c % H 400 9/o N 40s ~ t d l b ~ j k gFSIA-A-AD> ASTMC IC NO.^

West Virginia
Boone,Alma 9.8 2.3 42.5 83.5 5.7 6.3 1.5 3.0 15,110 35.1 6 120 Hvab 634
Boone,
Chilton 7.8 4.2 40.2 83.8 5.5 7.5 1.7 1.5 14,930 34.7 6 10 Hvab 633
Boone,
Hernshaw 7.2 2.0 38.0 86.0 5.5 6.0 1.6 0.9 15,320 35.6 6% 140 Hvab 634
Fayette,
Fire Creek 6.2 3.0 20.2 90.0 4.7 2.9 1.3 1.1 15,540 36.1 7 10 Lvb 433
Fayette,
Lower Eagle 4.8 1.8 33.4 87.7 5.5 4.4 1.7 0.7 15,610 36.3 8*/2 310 Hvab 635
Greenbrier,
Fire Creek 10.2 3.6 24.2 88.5 5.0 3.6 1.6 1.3 15,540 36.1 8% 150 Mvb 435
Greenbrier,
Sewell 3.2 3.2 29.1 88.0 5.3 4.3 1.8 0.6 15,540 36.1 9 220 Mvb 535
Kanawha,
Winifrede 9.5 4.8 41.5 83.35.6 8.6 1.7 0.8 14,88034.6 4 -5 Hvab 622
Logan, '
Cedar Grove 9.3 2.4 39.2 84.2 5.5 7.1 1.6 1.6 15,180 35.3 7 150 Hvab 635
McDowell,
Beckley 10.3 2.7 18.4 89.8 4.7 3.2 1.6 0.7 15,630 36.3 7l/2 25 Lvb 333
McDowell,
Bradshaw 6.7 1.9 26.5 88.9 5.1 3.4 1.7 0.9 15,690 36.5 8% 240 Mvb 435
McDowell,
Pocahontas
No. 3 6.2 3.3 18.7 89.4 4.6 4.1 1.3 0.6 15,690 36.5 8% 10 Lvb 333
McDowell,
Pocahontas
No. 4 7.3 2.8 26.1 89.4 5.0 3.7 1.3 0.6 15,610 36.3 9 170 Mvb 435
McDowell,
Douglas 4.0 2.5 25.6- 89.3 5.0 3.1 1.7 0.9 15,680 36.5 9 230 Mvb 435
Marshall,
Pittsburgh 10.5 4.1 45.6 81.2 5.6 6.8 1.4 5.0 14,790 34.4 7 230 Hvab 635
Mercer,
Pocahontas
No. 3 7.1 4.4 17.4 90.7 4.6 2.7 1.2 0.8 15,730 36.6 6 5 Lvb 333
Mercer,
Pocahontas
No. 6 7.9 5.1 20.8 90.3 4.8 3.0 1.3 0.6 15,710 36.5 7 65 Lvb 434
Mingo, Lower
CedarGrove 5.0 1.7 37.5 85.6 5.5 6.4 1.6 0.9 15,390 35.8 8 160 Hvab 635
Mingo, Upper
Cedar Grove 9.1 5.1 36.3 85.5 5.5 6.6 1.6 0.8 15,090 35.1 6% 30 Hvab 633
Monongalia,
Pittsburgh 6.6 2.3 37.5 85.5 5.5 5.8 1.8 1.4 15,310 35.6 9 250 Hvab 635
~Monongalia,
Redstone 12.4 2.6 36.6 84.5 5.5 6.3 1.7 2.0 15,090 35.1 71/2 180 Hvab 635
COMBUSTION
Coals of the World

Table IV. Source, Analysis and Classificationof U.S. BituminousCoals -Continued


Moisture- and ash-free
State, County, ..A s received - -HHV - - Classification-
and Bed %Ash %Hz0 %VM % C % H %O % N % S Btullb MJlkg FSIA A-ADB ASTMC ICNO.~
West Virginia
(Continued)
Nicholas,
Eagle 6.8 4.0 36.2 85.6 5.5 6.4 1.7 0.8 15,270 35.5 7% 140 Hvab 634
Raleigh,
Beckley 5.3 1.5 20.0 89.4 4.8 3.5 1.5 0.8 15,660 36.4 8112 60 Lvb 334
Randolph,
Sewell 5.4 1.5 31.2 87.4 5.3 5.2 1.4 0.7 15,420 35.9 8 180 Mvb 535
Wyoming,
Campbell Creek 2.0 2.2 31.7 86.8 5.4 5.5 1.5 0.8 15,570 36.2 8% 280 Hvab 535
Wyoming,
Eagle 3.6 1.9 29.9 88.5 5.3 4.0 1.5 0.7 15,530 36.1 8% 230 Mvb 535
Wyoming,
Sewell 2.4 1.5 23.8 89.8 5.0 3.1 1.6 0.5 15,700 36.5 9 170 Mvb 435
Wyoming
Sweetwater,
NOS. 7,71/2,9,15 4.1 10.3 47.0 79.3 5.6 12.2 1.8 1.1 13,900 32.3 1% -22 H V C ~ 811
A-FSI IFree Swelling Index
B-A-AD = Audibert-Amu dilatation index
C-ASTM Classifications: Lvb = low-volatile bituminous;Mvb = medium-volatilebituminous;
Hvab = high-volatile A bituminous:Hvbb = high-volatileB bituminous: Hvcb = high-volatileC bituminous
D-IC = International Classifications

Alabama, Mississippi, and Louisiana. The T h e Rocky Mountain Province


Texas region comprises the lignite fields of Ar- This comprises the coal fields of the moun-
kansas and Texas. The lowest rank coals in the tainous districts of Montana, Wyoming, Utah,
U.S.are found in this province, with equilib- Colorado, and New Mexico. It possesses a great
rium moisture contents as high as 55 percent. variety of coals, ranging from lignite through
Lignites from Texas can have moisture con- subbituminous and high grade bituminous
tents to 40 percent, low grindabilities, and coals to anthracite. The subbituminous coals
heating values, as received, below 4000 Btullb. range in moisture from 10 to 30 percent, with
Some of the Louisiana lignites are very similar calorific-values (HHY) from 6500 to 10,000
to those of North Dakota, having moisture to 36 Btullb. Several sources in this province have
percent and sodium levels of 5 to 8 percent. high sodium-oxide in ash, ranging to 15 per-
The Northern Great Plains Province cent.
This includes all the coal fields of the great T h e Pacific C o a s t Province
plains east of the eastern front range of the
Rocky Mountains. In this province are im- This area is largely confined to the State of
mense lignite areas of the two Dakotas, and the Washington, which contains the largest coal
bituminous and subbituminous fields of north- fields on the Pacific Coast. It also embraces the
ern Wyoming and northern and eastern small fields of Oregon and California. The coals
Montana. Lignites from this province can be of in this province range from subbituminous
very low rank, having moisture content to 45 through bituminous to anthracite.
percent and sodium oxide as high as 15 percent The coals of Oregon and California rank
of the ash. somewhat lower than those of Washington.
2 1
COMBUSTION
Coals of the World

Those of California consist mainly of noncok- dices, the Audibert-Arnu dilatation, and the
ing bituminous coals in the southern part of the ASTM and International classifications.
State, lignite in the northern, and subbitumin- ALASKA
ous in the center. The fieldsare scattered and Coal is distributed widely throughout Alaska
limited in area. in fields differing greatly i n size and in
Estimates of U.S. coal production in the year geologic environment; much of it is lignitic or
2000 vary from 1200 to 2000 million tonnes per subbituminous in rank. Its total reserves are es-
year, depending upon the amount of nuclear- timated to be 15 percent bituminous coal and
power generation and the extent of coal ex- 85 percent subbituminous coal and lignite.
ports. Appalachia, which now produces about Only fields close to main lines of transportation
half of the nation's coal, will decrease to 30 have been developed; major reserves occur in
percent; the Midwest will produce 11 percent more remote parts of the State. The most impor-
and the West, 50 percent; the balance will be tant fields, in terms of production and known
s u r f a c e - ~ n e dGulf lignite. Surface mining reserves, are the lower Matanuska Valley,
will predominate at that time and is expected to nbrtheast of Anchorage, and t h e Nenana,
be over 60 percent of the total output. southwest of Fairbanks. In addition to coal,
Table V of Chapter 2 gives analyses of some Alaska has a greater area of peat than all the
U.S. coals. Ash analyses of representative U.S. contiguous states combined.
coals are included in Tables IV, V, and VI of Alaskan coal deposits are in several regions
Chapter 3. (Fig. 3). The Northern Alaska and Seward
Table IV CPage A-10) gives detailed analyses Peninsula regions contain mostly subbitumi-
of U.S. bituminous coals, with free-swelling in- nous and bituminous coal. The biggest Alaskan

Fig. 3 Coal Map of Alaska


COlSllmRON
&ah of the World

Table V. Analyses of Typical Alaskan Coals


Region, Moisture- and ash-free
District -As received - -HHV - Ash ST,
And Mine % Ash % Hz0 % VM %s Btullb MJfl<g Red., "F

Northern Region
Wainwright
Yukon Region
Broad Pass Field
Costello Creek
Eagle
Nenana Field
Suntrana
Kuskokwin Region
Nelson Island
- Southwestern Region
Chignik Bay
Cook Inlet Region
Matanuska Field
Chickaloon
Coal Creek
Eska
Jonesville
Moose Creek
Gulf Region
Bering River Field
Katalla
Southeastern Region
Admiralty Island
Harkrader

deposits are in the Arctic slope region, in an Mines (1946), Analyses of Alaska Coals, pre-
area 300 miles long (east and west), and 75 sents proximate and ultimate analyses, and
miles wide; the coal is low-volatile bituminous fusibility data, for coals from all the major
to lignite. The Yukon basin coal, lignite and Alaskan coal deposits. Table V gives analyses
bituminous, occurs in small, scattered areas of some typical Alaskan coals.
that have been inadequately explored.
MEXICO
The Nenana deposits are subbituminous
high-rank lignite, primarily strip-mined. The Mexico has coal deposits in 16 of the 38 Fed-
Cook Inlet-Susitna region contains some of the eral States (Fig. 4). Estimated production by the
most important fields of lignitic and sub- year 2000 is 55 million tonnes. Only three de-
bituminous rank, in thicknesses up to 40 ft. The posits presently have economically recover-
Matanuska Valley is divided into the lower able coal reserves: Barrancas basin (Central
field, containing the Moose Creek and Eska Sonora), Oaxaca basin and Coahuila basin. In
fields, and the upper field, comprising the the Coahuila basin, the most significant coal
Chickaloon and Anthracite Ridge. The Mat- deposits are located within the two largest dis-
anuska fields produce high-volatile B bitumi- tricts of Sabinas and Rio Escondido.
nous coal from beds 18 to 20 ft. in thickness. Brown coals and hard coals are deposited in
Technical Paper 682 of .the U.S. Bureau of the Sabinas basin, which is about 35 miles long
~ ~ M T I O N
Coak of the World

and 15 miles wide. The hard coals are of any economic importance are known to occur
medium rank and have ash contents from 14 to are Brazil, Chile, Colombia, Peru, and Ven-
35 percent. These coals are cokable. High- ezuela. Argentina has small resources of low-
volatile brown coals are deposited in the Rio rank coal. Owing to inaccessibility of most of
Escondido basin. Most of the-coals in the Bar- the deposits and lack of transportation, coal
rancas basin are of high rank, some of these mining has not been developed. Lack of capital
coals are anthracitic. and skilled labor also limits development.
Table VI gives coal and ash analyses of Mexi-
ARGENTINA
can bituminous and subbituminous coals.
CENTRAL AMERICA Argentina's only coal deposit is located in
the Southwest of the country, in the Rio Turbio
The coal resources of Costa Rica, Guatemala, ~ ~near the
~ chilean
i border.
~ , ~h~ seams are
Honduras. Panama and Puerto Rice (Fig. 4, 1 m to 2 m thick. The coal is gsnerally high in
comprise subbituminous and lignitic coals. but, after heatment or blending with im-
The extent is generallyunknown in 'Oun-
ported coal, it is suitable for steam generation.
tries, and the deposits are not currently of Mixed with high-grade coal, Argenti-
economic importance. nian coal is made available for steelmaking.
COAL DEPOSITS OF SOUTH AMERICA The Port of Rio Gallegos is used for shippi&
coal to other parts of the country. Today, the
Compared to those of North America, South main consumer is the Hydro and Electric
America's coal deposits are very small (Fig. 5). Energy Agency. Annual coal production of
The only Southern countries where deposits of about 9 million tonnes is anticipated by the

Fig. 4 Coal Map of Mexico and Central America


--
C O ~ R O N
Gods of the World
COMBUSnON
Coals of the World

Table VI. Analyses of Mexican Coals -

Nava -
Rio Escondide --
District
--

As received:
% Ash
% Moisture
Moisture & Ash-Free:
% Volatile (VM)
% Carbon (C)
% Hydrogen (H)
% Oxygen (0)
% Nitrogen (N)
O/O Sulfur (S)

HHV, Btullb
HHV, MJlkg
Fusibility Temperature,
reducing atmosphere,OF:
Initial deformation
Ash Composition:
% Si02
% A1203
O/O Fe20s

% CaO ,
O/O MgO
% Na20
% K,O
% TiOz
% P205
OhSo3
Baselacid Ratio
Hardgrove Grindability

year 2000. Analyses of typical Argentinian some proximate analyses of bituminous coals
coals are given in Table VII. from Brazilian mines.
Large brown coal deposits have been discov-
BRAZIL
ered near the border of Peru; also, there are
The principal explored and developed coal large deposits of lignite in Amazonas, as yet
deposit of Brazil extends south from southern unquantified. Annual production in the year
Sio Paulo, through the states of Parana, Santa 2000 is expected to be about 19 million tonnes.
Catarina, and Rio Grande do Sul, to the CHILE
Uruguay frontier. The seams are thin and lie in
flat formations. The coal is classified as Chile is the largest producer of coal in South
bituminous, but is of low-grade because of its America. The deposits occur in the low-lying
high ash content. It is not easily separated from land along the ocean, and hence are easily ac-
the shale partings and must be crushed to small cessible. The average thickness of the main
size to make washing effective. Table VIII gives coal seam is 150 cm. The Province of Concep-
I COMBWSRON
Coals of the World

production in 2000 is planned to approach 6


Table VII. Coals of Argentina - million tonnes.
Rio Turbio Area COLOMBIA
Hvcb Suba Colombia has the largest coal resources in
As Received: Latin America, but as yet no comprehensive
% Ash survey has been made of their extent and qual-
% Moisture ity. Estimates of the total geological resources
Moist. & Ash-free: range from 40 to 80 billion tonnes. The coal-
/ Volatile (VM)
OO
fields are situated mainly in the Eastern Cor-
% Carbon (C) dillera; some coal deposits are located in the
% Hydrogen (H) Western and Central Cordillera region. All coal
% Oxygen (0) ranks are available, from brown coal to anthra-
% Nitrogen (N) cite. A considerable portion of the coal has
% Sulfur (S) good coking properties. Most of the coking
HHV, Btullb coals have ash contents of less than 10 percent
HHV, MJlkg and low sulfur contents of 0.3 to 1 percent,
making them suitable for export.
Fusibility Temps.,
reducing at., O F : In the deposits of El Cerrejon, open-cast min-
Initial deformation ing produces coal low in ash and sulfur con-
Softening (H =W) tent, and high in calorific value. This coal is
Fluid well suited for power stations, but can also be
used for coking. The deposits producing the
Ash Composition:
largest coal output are situated i n the district of
% Si02
Paz del Rio. Further deposits occur in Cun-
% A1203
dinamarca, Boyaca, the Cauca River basin, and
% Fe203
Samaca. Colombia plans to increase its present
OO/ CaO
coal production, ensuring the domestic energy
% MgO supply, and anticipating future exports up to 30
% Na20 million tonnes. Table X gives analyses of typi-
% K2O cal Colombian coals.
OO/ Ti02

% P205 ECUADOR
Oo/ SO,
Considerable coal deposits occur in various
I Baselacid Ratio 0.23 0.20 sections of Ecuador; estimated coal deposits
Hardgrove Grind. 49 44 are 13 million tonnes. The bulk of the deposits
contain subbituminous coal and low-grade lig-
cion and the deposits near the Bay of Arauco nite, high in ash. In some localities, coals of bet-
have thus far yielded the best coal in Chile. ter quality, approaching anthracite, have been
Table IX gives the proximate analyses of the found. However, the general low quality, high
representative coals of these regions. In addi- cost of mining, and lack of transportation deter
tion, considerable low-sulfur brown coal de- exploitation of Ecuadorian resources.
posits exist in the south of the country, in the PERU
province of Magallanes.
In 1971 the private Lota-Sweiger'Coal Com- Coal deposits have been detected in a num-
pany was nationalized. The Empresa National ber ofplaces along the Andean ranges, mainly
del Carbon S.A. (ENACAR) was founded to op- in the Oyon area. The coals are both anthracite
erate the state-owned coal mines. ~ n n u a l and bituminous. Two coal deposits in Peru
COMBUSTION
Coals of Ute World

-
Table VIII. Analysis of Typical Brazilian Coals
Moisture- and ash-free
- As received - HHV -
District or Mine %Ash - % Hz0 %vM 7'0' S Btullb Wk3
Butia 13.6 11.5 42.7 1.7 ... ...
Jacuhy 21.2 9.6 28.0 1.3 ... ...
TubarHo 28.2 1.9 41.6 1.6 ... ...
Santa Catarina 27.0 1.3 43.1 5.3 15,060 35.0
Lauro Miiller 18.0 2.0 38.8 2.5 14,500 33.7
Rio Deserto 13.8 2.0 35.6 1.2 15,320 35.6
Rio Negro 39.5 7.0 36.1 2.6 12,600 29.3
Cambiu 18.4 2.5 40.6 ... 14,600 34.0
Rio De Peixe 15.5 6.3 35.7 ... 14,710 34.2
SBo Jeronimo , 29.0 7.3 36.3 ... 13,500 31.4

Table IX. Analyses of Typical Chilean Coals


Moisture-and ash-free
A s received- HHV-
City or Mine % Ash % Hz0 % VM %S BNlb MJlkg

Lota*
Schwager
Lebu
Rios
Arauco
Buen Retiro
Mafil
Quila Coya
* Chemical Composition of Ash From Lota Mine
Si02 42.9% MgO 1.490
AlzOI 26.3% P20s 0.2%
Fe203 14.6% So3 4.8%
CaO 7.2%
Ash Softening Temperature-2260F

have been developed. Those of Rio Santa the quality of coal is low. The analyses of Table
mainly consist of anthracite; production XI are of typical Peruvian coals.
ceased in 1962. At present, cokable coals are
VENUUELA
worked in the district of Cerro de Pasco. Peru
plans to bring annual production to about 6 The main Venezuelan coalfields are in the
million tonnes by 2000, to meet its future de- Eastern Cordillera and in the region of
mand for both coking and non-coking coals Naricual, in the State of Anzoategui. The coal
with no importing required. industry is government-owned. The deposits
The mines at Goyllarisquisga and Quishuar- are in detached basins, some of which cover
cancha account for the bulk of the Peruvian hundreds of miles. Although most of the coal is
production. The seams are generally thick, but of bituminous and lignite rank, some deposits
COMBUSTION
Coals of the World
-
of semianthracite occur in the Coro district of
Table X. Analyses of Typical the State of Falcon.
Colombian Coals Of the six coal districts of economic impor-
tance, Zulia has the largest coal resources;
Hvbb Subb
1,500 million tonnes. The districts of Labotera,
As Received: with 100 million tonnes, and of Naricual, with
% Ash about 50 million tonnes, as well as Unare,
'% Moisture Taguay and Tachira, are also of economic im-
Moist. & Ash-free: portance. By 2000, Venezuela's total coal
% Volatile (VM) production will be about 16 million tonnes,
% Carbon (C) which may satisfy domestic needs. Table XI1
% Hydrogen (H) gives analyses of some Venezuelen coals.
% Oxygen ( 0 )
O/O Nitrogen (N) COAL DEPOSITS OF EUROPE
% Sulfur (S)
Most of the European countries, excluding
HHV, Btullb
Scandanavia, possess coal resources. Scan-
HHV, MJlkg
danavia (including Iceland) has substantial
Fusibility Temps.,
reducing at., OF: quantities of peat, which increases in value as
Initial deformation oil prices rise and as there is more uncertainty
Softening (H =W) with regard to other fossil fuels.
Fluid In continental Europe, the bulk of coal is
Ash Composition: found in Germany,Czechoslovakia, Poland, and
O/O SiOt
Yugoslavia (Fig. 6). Many other countries with
O/o A1203
reasonable reserves have allowed their mines
% Fe,O, to become idle. French, Belgian, and Spanish
O h CaO
coal is expensive to mine. Austria, Denmark,
O/o MgO
Italy, Luxembourg, the Netherlands, and Swit-
'
% NazO zerland produce little or no coal.
% K,O The resources of European Russia are in-
% TiO2 cluded in the section on the U.S.S.R. and Asia.
O h p203 0.2 ... AUSTRIA
%so, 1.6 9.5
Baselacid Ratio 0.17 0,32 Coal production from small bituminous coal
Hardgrove Grind. 48 40 deposits has been abandoned. Some brown
coal deposits, however, have economic impor-

Table XI. Proximate Analyses of Peruvian Coals


Moisture- and ash-free -..--
-As received - . HHV -
Kind of Coal %Ash % H20 % VM BTUllb wkg

Goyllarisquisga, Raw 31.5 3.1 54.5 14,710 34.2


Goyllarisquisga Steam, Washed 17.3 4.0 54.8 15,150 35.2
Goyllarisquisga Coking 17.9 4.0 4919 15,110 35.1
Quishuarcancha, Raw 26.9 2.5 - 50.7 13,780 32.1
Santa River Valley 7.1 3.9 7.9 15,560 36.2
Paracas Peninsula 9.0 3.1 39.9 15,530 36.1 -
*,
).it
COMBUSTION
Coals of the World

Table XI/. Analyses of Typical Venezuelan Coals


Moisture- and ash-free -
-As received - HHV -
Region Rank % Ash % Hz0 % Vol. Btullb MJlkg

Naricual Hvbb 2.3 2.5 46.5 14,460 33.6


Santa Rosa Hvab 2.4 1.5 40.1 14,520 33.8
Barcelona Hvab 3.4 3.0 38.6 14,620 34.0
Simplicia Mvb 4.3 3.8 27.9 ... ...

YUGOSLAVIA A~BANIA

Fig. 6- - Coal Map of Europe


COMBUSTION
CoJc ofthe World
--
tance. There are deposits of glance brown coal domestic market, while the lignite mines sup-
as well as of lignite. The most important lignite ply coal mostly to power plants.
district is situated near Koflach-Voitsberg, CZECHOSLOVAKIA
where two 10 to 15 m thick seams are being ex-
tracted, partly by open-cast mining, partly by There are economically important bitumin-
deep mining. There are further brown coal de- ous and brown coal deposits in Czechoslova-
posits near Wolfsegg-Traunthal and in the Sal- kia. Technically and economically recoverable
zach district near Trimmelkam. Apart from reserves exceed 4,000 million t.c.e. The wide
local needs, lignite produced in the country is Upper Silesian hard-coal deposits in the dis-
nearly exclusively used in power plants. trict OstravalKarvina and the Lower Silesian
deposit of Walbrzych, near Zaclkr, are being
BELGIUM
mined. In addition to these two large hard-coal
In Belgium, two main bituminous-coal de- deposits, there are the two districts of Plzefi
posits occur, forming part of the northwest and KladnolRakovnik and a small hard-coal
European coal belt. The southern coal deposits deposit near Rosice. In North Bohemia, there
comprise the districts of Liege and Namur (Bas- are large and econo~~ically very important
sin de Liege) and Charleroi (Bassin du Hain- brown coal deposits. The largest district is
ant). The northern coal deposits include the situated near Teplice and Chomutov on the
district of the Campine. There are no brown border of the Krusnehory, with a further de-
coal deposits i n Belgium. posit of economic importance in the district of
The South basin extends through the valley Sokolov. Smaller brown-coal deposits exist in
of the Sambre and Meuse rivers, running east to West Bohemia near Cheb, in the south of
the German frontier and west to the French Moravia, and in Slovakia near Handlova.
border. The Campine basin, with large re- The coals from the districp of Plze6 and
serves, stretches in a westerly direction from Kladno are mostly low-rank types. All types of
the German border, through the Provinces of brown coal, from glance brown coal to lignite,
Limburg and Antwerp. The Belgian coals range are produced in the country; most of them are
from high-volatile bituminous to anthracite. used for electricity generation. ,
Belgium produces about half of the coal FINLAND
necessary for domestic consumption; the bal- Finland has no coal reserves and thus no in-
ance is imported. Only one-fourth of the coal digenous coal production. But there are large
consumed is used for thermal power plants. reserves of peat with about one-third of the
BULGARIA country considered peatland. Peat, used
mainly for industrial steam production and
The country has only small bituminous coal cogenerating district heat and electricity, cur-
deposits. There is a deposit of anthracite coal rently supplies about 3 percent of the fuel for
north of Sofia. Cokable types of coal (cretace- energy consumption in Finland. Production is
ous coal) exist in the small district of Ojabrovo expected to exceed 2 million tonnes coal equi-
and in the Dobrudsha. The brown coal deposits valent by 2000, corresponding to about 20 per-
of Bulgaria are economically more important cent of the total energy consumption.
than the hard coal deposits, being estimated at
greater than 2,000 million t.c.e. Deposits of FRANCE
glance coal and of dull brown coal (cannel French coal deposits consist of a large
coal), most of which are extracted by deep min- number of small-fields distributed over the
ing, occur near Pernik, in the Pirin Mountains, northern, central, and southern parts of France.
and in Tscherno. Larger lignite deposits in the The deposits are generally deep, jagged, and
_ district of Maritsa can be extracted by open-cast difficult to mine. Usable deposits are between
mining. The brown coal mines mainly serve the 700 and 1250 meters deep. The most important
COMBUSTION
Coals of the World

Table XIII. Analyses of Typical French Coals -

Area
Mining
District
or Seam .
- As received -
YOAsh % H20 % VM
-HHV
Btullb
_
- Moisture- and ash-free--.
MJlkg
Ash ST,
Red., O F
Hardgrove
Grind.

Nord and Pas-De-Calais


Basin
Auchel Marles 26.5 1.2 35.0 15,570 36.2 2100 86
Bethune Bethune 47.3 1.0 33.1 14,300 33.3 1920 75
Noeuds-Les-Mines 32.7 1.5 38.1 14,930 34.7 2120 87
Bruay Bruay 27.9 1.8 39.0 14,700 34.2 1940 83
Douai Douai
Somain
Henin-Lietard Henin-Lietard
Lens Lens IV
Lens VII
Oignies Oignies
Valenciennes Anzin
Agache
Lorraine Basin
Petite Rosse'lle Simon 5.9 3.3 44.2 13,880 32.3 1970 ...
St. Charles 34.8 1.8 40.5 13,450 31.3 1970 76
Wendel 29.5 3.2 40.0 13,710 31.9 2060 57
Saare & Moselle Merlebach 6.1 2.8 43.0 14,110 32.8 1920 . ..
La Houve 35.0 3.2 40.6 13,330 31.0 2060 . ..
Faulquemont Faulquemont 8.6 4.0 41.9 14,750 34.3 2010 . ..

are the district of Lorraine adjoining the Saar in mined hard coal are expected to go from 320
Western Germany, the district of Nord and Pas- million tonnes in 1985 to 120 million tonnes in
de-Calais and some scattered deposits in the 2000; brown coal, from 50 million in 1985 to 20
district Centre-Midi. In the long term, only coal million in 2000.
production in the Lorraine district will be
GERMANY (EASTERN)
.- maintained. The smaller brown coal deposits,
most of which are in the southwest of the coun- The coal output from the hard coal districts
try in Provence and near Arjuzanx, have only of Zwickau and Lugan--0lsnitz in Saxony has
local importance for electricity generation. been stopped because of the properties of the
Most of the French hard coals represented are coal deposits. Eastern Germany, however has
not cokable. While the mines in the Pas-de- large lignite deposits in the two principal dis-
Calais still produce mostly high-rank types of tricts in Lasatia near Cottbus-Senftenberg and
coal and coking coal, the coals from the Lor- near Halle-Merseburg. A third smaller lignite
raine and the Centre-Midi are usually low-rank district is situated between Magdeburg and
and only part of them can be used for coking. Helmstedt. Germany is the largest lignite pro-
The low brown coal production is exclusively ducing country in Europe. (See Table XIV.)
used in power plants. Table XI11 gives analyses Most of the hard coal from the Saxonian dis-
of typical French coals. tricts have unfavorable coking properties and
Economically recoverable reserves of deep- can be used only as a blending coal to the im-
COMBUSTION
Coals of the World

Table XIV. Analyses of Typical Eastern German Coals


Moisture- and ash-free
-As received - H H V -
District %Ash %H20 %VM %C %H %O %N %S Btullb Wlkg

Sachsen 5-12 2-6 38.0 81.4 5.5 10.4 1.8 1.0 14,690 34.2
Ostelbe 2-5 58-60 56.5 68.2 5.5 24.9 1.1 0.3 11,390 26.5
M'estelbe 5-8 52-56 61.0 70.8 6.1 21.3 0.9 0.9 12,110 28.2
Halle-Bitterfeld 5-7 52-56 57.5 72.0 5.5 18.3 0.8 3.4 12,820 29.8

ported coking coal, or as industrial and trict stretches through parts of Alsace-Lorraine.
power-plant coal. German lignites are suit- The coals contain considerable ash, particu-
able as power-plant coal, for briquetting and, larly in small sizes, whi-ch are usually washed.
by employing special methods of coking, they The recoverable hard-coal resources of West-
can be used as input coal for coke ovens. ern Germany amount to about 24,000 million
tonnes, with about 85 percent of that concen-
trated in the Ruhr. The balance comes from the
Western Germany has large deposits of bitu- Saar, Aachen, and Ibbenbiiren districts. All
minous (stein) coal and brown (braun) coal, the hard coal is deep mined. Production in excess
latter being unconsolidated lignite. About 60 of 100 million tonnes annually is expected by
percent of the currently economical recover- 2000.
able deposits have sulfur below 1 percent, as Economically recoverable brown coal totals
received at the power plant. about 35,000 million tonnes, all from open-pit
The principal districts where bituminous mining. An annual production of 150 million
coal occurs in greatest abundance are: the tonnes is anticipated by the end of the century,
Lower Rhine and Westphalia, Silesia, the practically all of which will be consumed in the
Rhenish district and the Saar district. In central country, mainly for power generation. Table XV
north Germany, brown coal occurs in the Rhine lists typical analyses of Western German coals.
Province between Cologne and Aachen (Aix-
GREECE
la-Chapelle). Further economically important
brown-coal deposits are in Lower Saxony Greece does not have any bituminous coal
(Helmstedt) and Lower Bavaria (Schwandorf). deposits of economic importance. Holvever,
The Westphalian and Rhine district fields there are important lignite deposits in the
include the Ruhr Basin, the most important districts of Ptolemais and Megalopolis. The
coal field in Germany. These coal districts are production of brown coal was about 18 million
connected with those of southern Holland, tonnes in 1975, and increases steadily to form
Belgium, and northern France. The coal ranges an important basis for the production of elec-
from medium to high volatile, and the ash var- tric energy. The Greek brown-coal mining in-
ies considerably from mine to mine. The bulk dustry provides 50 percent of the country's
of the entire German output comes from the energy demand. Analyses of Greek lignites are
Lower Rhenish Westphalian fields. given in Table XVI.
The Silesian district extends through the
HUNGARY
province of Silesia, which, geographically,
is divided between Germany, Poland and Hungary has.soke bituminous-coal deposits
Czechoslovakia. The bulk of the coal in this dis- in the districts of Pecs and of Komlo, and sev-
trict is of first-class coking quality, and is eral brown-coal deposits of national impor-
widely used in steel industries. The Saar dis- tance, both totalling about 1,000 million t.c.e.
COMBUSTION
Coals of the World

A large brown-coal deposit is situated in the Most of the coal produced is used for electricity
Budapest district. Glance brown coal is ex- generation. The use of Hungarian hard coal for
ploited by deep mining in the districts of coke production is very limited. Table XVII
Tatabanja and Oroszliny. Large lignite depos- gives analyses of Hungarian brown coal.
its, extracted by open:cast mining, exist in the IRELAND
district of Gyongyos; in the Combinate Borsod,
brown coal is extracted by deep mining. A new There are 8 coalfield areas in Ireland (the Re-
brown coal district near Biikkabrlny projects public of Ireland and Northern Ireland), all of
an annual output of about 20 million tonnes. limited size. Only two are currently being

Table XV. Analyses of Typical Western German Coals


Moisture- and ash-free
-As received - -HHV-
District %Ash %H,O %W %C %H %O %N %S Btdlb MJlkg
Ruhr (Anthracite) 4-7 3-5 7.7 91.8 3.6 2.6 1.4 '0.7 .15,440 35.9
Ruhr (Low-Vol. Bit.) 6-9 7-10 10.5 90.8 3.8 2.7 '1.7 0.8 15,500 36.0
Aachen (Low-Vol. Bit.) 6-9 8-10 13.8 89.8 4.8 2.8 1.5 0.5 15,410 35.8
Ruhr (Med-Vol. Bit.) 6-9 7-10 24.4 88.7 5.0 4.1 1.6 6.7 15,550 36.2
Saar (Med-Vol. Bit.) 7-9 8-10 32.5 86.9 5.2 5.4 1.3 1.1 15,320 35.6
Ruhr (High V\ol. Bit.) 6-7 8-10 33.7 85.9 5.5 6.2 1.6 0.8 15,160 35.2
Saar (High Vol. Bit.) 5-8 3-5 38.2 82.7 5.2 9.4 1.2 1.5 14,220 33.0
Peissenberg (Lignite) 12-20 8-12 52.0 74.0 5.5 14.5 1.4 4.6 12,780 29.7
Helmstedt (Brown Coal) 12-22 42-46 59.4 72.6 5.8 16.7 0.4 4.4 12,790 29.7
Rheinland (Brown Coal) 5-20 50-62 55.0 68.3 5.0 27.5 0.5 0.5 11,340 26.4
Schwandorf (Browncoal) 6-20 50-58 55.0 63.6 5.0 26.1 1.3 4.0 10,890 25.3

Table XVI. Analyses of Greek Lignites


Moisture- and ash-free
-As received- H H V -
Region %Ash %Hz0 %VM %C %H %O %N %S Btdlb MJlkf3

Kimi - 5.9 23.0 55.6 ... ... ... ... 2.3 11,560 26.9
Aliveri 8.6 33.5 57.7 ... ... ... ... 1.4 11,330 26.3
Aegean 18.6 34.9 57.6 ... ... ... ... 6.4 10,650 24.8
Attica 15.0 42.0 59.1 ... ... ... ... 6.7 11,740 27.3
Ptolemais 6-22 52-60 57.0 65.3 5.3 26.5 1.6 0.5 10,850 25.2
Megalopolis 13-17 6&64 62.0 60.5 6.2 30.6 1.3 1.4 10,510 24.4

Table XVII. Analyses of Typical Hungarian Coals


Moisture-and ash-free
-As received - H H V-
Region %Ash %H20 %VM %C %H %O %N %S ~tdlb MJk
GyongyoslVisonta 15-30 46-54 63.0 63.8 4.8 26.8 1.1 3.5 10,670 24.8
Tatabanya 6-12 12-14 52.0 73.0 5.8 17.7 0.9 2.6 13,500 31.4
COMBUSTION
Coals of the World

worked; the Connaught (Arigna) field, which NETHERLANDS --


contains semi-bituminous coal with high ash The most important of the Netherlands coal
content, provides fuel to an adjacent generat- areas lies in the province of Limburg, where it
ing station; the Leinster (Castlecomer) field links up with the Campine basin of Belgium,
produces high-grade anthracite for domestic and extends in a northwest direction into the
heating purposes. Brown coal occurs in two province of North Brabant. The Netherlands
localities in northeast Ireland, with large re- have ample geological resources that are not
serves in the Thistleborough area. economically recoverable because of the large
Peat bogs cover 15 percent of the country; Dutch resources of natural gas.
over 3 million tonnes of peat are used yearly for There is an estimated resource base of 100
generating electricity and domestic heating. billion tonnes of hard coal, related to coal
Milled peat powers 8 stations that generate 23 seams more than 0.8 m thick and 1500 m deep.
percent of the national electrical demand. Until 1950 indigenous coal provided more
Irish peat in its natural state contains about than 70 percent of national coal consumption
95 percent moisture; by long-term air drying, and about 50 percent of total energy demand, at
this can be reduced to 20 to 40 percent to pro- a production level of some 12 million tonnes
duce a commercial fuel. Dried peat has a vol- per year. Production reached a maximum of 13
atile content between 55 and 70 percent, and million tonnes in 1961 but declined sharply
ash from 2 to 10 percent. Lower heating value at after 1965 as a consequence of the development
30-percent moisture is 6000 Btullb (14 KJlkg); of world energy prices and low-cost domestic
ash softening temperature is about 2100F. natural gas supply. Coal mining was stopped in
Current State-owned reserves of peat are 1974, while coal consumption dropped to less
equivalent to 40 million tonnes of coal. than 5 percent of total energy demand.
ITALY NORWAY
Italy has no economically important hard
coal deposits. The once-mined deposits in Sar- Economically important hard-coal deposits
dinia are to be used again in future. Larger de- occur on the arctic island of Spitsbergen; these
posits of brown coal and partly also of glance deposits are currently being worked. The coal
brown coal exist in Toscana, in Calabria, and in produced is used mostly in the north of Nor-
the south-west of Sardinia. Outputs are low, way, for district heating.
about 2 million tonnes annually. The largest POLAND, PEOPLE'S REPUBLICOF
open-cast mine is situated in the Valdarno
Basin of the district Arezzo. Table XVIII shows In Poland, there are several rich and easily
analyses of Sardinian coals. accessed hard-coal and brown-coal regions.
Hard coals, which are all deep-mined, occur in
three basins: the Upper Silesian basin has
Table XVIII. Range of Analyses about 93 percent of the economically recover-
of Italian (Sardinian) Coal able reserves; the Lower Silesian has about 1
(As received basis) percent, found in thin seams (0.4 to 1 m thick)
near the towns of Walbrzych and Nowa Ruda.
Ash, % 15 to 20 The Lublin basin, with about 6 percent of the
Moisture (H20) Oh 1 2 to 15
reserves, is under development; there, the
Volatile matter (VM) % 32 to 45
thickness of the seams ranges from 0.7 to 3.6 m.
Sulfur (S) % 2to7
Most of these coals are high-volatile bitumi-
HHV, Btullb 9960 to 11,500
nous in rank, high in calorific value and with
HHV, MJlkg 23.2 to 26.7
sulfur contents about 1percent.
Ash softening temp.,
approx., O F 2000 Brown coal deposits, mined by open-pit
-
methods, occur in the Konin and Adam6w dis-
3 COMBUSTION
Coals of the World

tricts, and near Tur6w, Legnica, and Bel- ROMANIA


chat6w. Brown coal production is solely for Romania has numerous small coal deposits,
consumption inside Poland, primarily for the especially along the outskirts of the Carpathian
generation of electricity. (See Table XIX.) Mountains. Hard coal deposits are mined near
Economically mineable reserves of hard coal Schela, Anina and Cozla. The most important
are said to be 74,000 million tonnes, to a depth district is situated near Petrosani in the South-
of 1,000 m; of brown coal, 9,000 million tonnes, ern Carpathian Mountains. Here, the sub-
all to be won by open-cast mining. Production bituminous coal seams reach thicknesses of 6 m
of hard coal is expected to be between 250 and to more than 10 m deposited in depths from 150
300 million tonnes by 2000, with an additional m to 1000 m. Further deposits of brown coal
200 to 250 million tonnes of brown coal. and lignite are situated near Bacau and in the
basins of Oltenio, Rovinari Motru and Iilt, most
of which are extractable by open-cast mining.
Table XIX. ~nalyses Most of the brown coal mined in the country is
of Typical Polish Coals used in power plants.
High-Volatile Subbituminous SPAIN
B Bituminous A
Spain has considerable bituminous coal and
As Received: lignite deposits although, in several deposits,
% Ash geological conditions render exploitation dif-
% Moisture ficult. The economically important hard coal
Moist. & Ash-free: deposits are concentrated in the province of
O/O Volatile (VM) Asturia in the northwest-the districts of
O h Carbon (C) Oviedo and Lecin account for nearly 90 percent
%Hydrogen (H) of the total Spanish production of hard coal. A
% Oxygen (0) secon'd large hard coal deposit is in the district
% Nitrogen (N) of Mariannica, with individual mines in the
O/O Sulfur (S) provinces of Cordoba and Sevilla. The lignite
HHV, Btullb deposits are in the northeast of the country be-
HHV, MJlkg tween Teruel and the Pyrenees. With its present
Fusibility Temps., production, Spain can supply more than 75
reducing at., O F : percent of its demand. (See Table XX.)
Initial deformation
SWEDEN
Softening (H =W)
Fluid Swedish coal deposits are small and of low
Ash Composition: quality; technically recoverable reserves have
% SiO, been estimated to be 30 million tonnes. At
% A1203 present, there is no coal being produced except
% Fe203 small amounts obtained from clay produced for
% CaO the ceramics industry. This coal is consumed
O/o hfgO locally, and production is expected to increase
% Na20 slightly. Sweden has large resources of peat-
% K?O estimated at about 15 percent of the country's
O/O TiO, total area-which are yet to be developed.
O/o P 2 0 5
UNITED KINGDOM
% so3
Baselacid Ratio
The coal fields of the UK may be grouped into
Hardgrove Grind. three principal areas designated as the south-
ern, the central, and the northern coal fields.
CO~UrnON
Coalsof the World

Table XX. Analyses of Typical Spanish Coals


Anthra- Low-Vol. High-Vol. Sub Sub Bmwn
cite Bitum. Bitum. bituminous bituminous Coal

As Received:
% Ash
% Moisture
Moist. 81Ash-free:
% Volatile (VM)
% Carbon (C)
% Hydrogen (H)
% Oxygen ( 0 )
% Nitrogen (N)
% Sulfur (S)
HHI', Btu'lb
HHV, MJIkg
Fusibility Temps.,
reducing at., OF:
Initial deformation
Softening (H =W)
Fluid '

Ash Composition:
% SiO,
% A1203
% Fe203
% CaO
% MgO
% NapO
Oh K,O
%Ti02
% P203
Oh so3
Baselacid Ratio:
Hardgrove Grind.:

The southern area embraces the fields known East Leicestershire, with coal of geological dis-
as South Wales, Forest of Dean, Bristol and turbance and at relatively shallow depths.
Kent. The central area includes the fields of Also, over 200 million tonnes of workable coal
Lancashire, North Wales, Yorkshire, Derby- have been discovered in an area of Coventry
shire, Nottinghamshire, Staffordshire and and north of Kenilworth, at depths between
Warwickshire. The northern area comprises 1000 and 2500 ft.
the fields of Northumberland, Durham, Cum- The coal of the southern area varies, from
berland, and the fields of Scotland. bituminous coal through the well-known
Intensiv~exploration in recent years has re- Welsh steam coal to anthracite of notable pur-
vealed l e g e new areas for development, par- ity. The bulk of the central-area coal fields lies
ticularly in the Selby district (a major eastward in the south of Lancashire. Coals in this field
extension of the Yorkshire field) and North- contain 30 to 35 percent volatile matter. Some
LUI"LYUJII"*I

i Coals ot the World

Table XXl. Analyses of Typical British Coals


Moisture- and ash-free
- As received - H H V -
District 4oAsh %Hz0 %VM %C %H 460 % N % S a . Btullb MJIkg

Durham (Mvb) 6.9 2.6 29.4 87.8 5.3 4.6 1.4 0.9 15,660 36.4
Yorkshire (Hvab) 6.8 2.0 34.4 84.3 5.2 8.0 1.7 0.8 14,980 34.8
West Midlands (Hvbb] 4.9 9.8 39.6 80.5 5.5 11.9 1.4 0.7 14,180 33.0
Scotland (Hvbb) 4.6 13.8 41.5 81.4 5.4 10.3 2.1 0.8 14,580 33.9

Table XXII. Proximate Analyses of Welsh Coals


Moisture- and ash-free
A s received- -HHV-
District % Ash % H,O % VM %S Btullb MJlkg
- - --

Aberpergwm 4.0 - 1.3 7.4 0.9 15,820 36.8


Ynisarwed 4.2 1.5 11.3 2.5 15,370 35.7
Bwllfa 4.8 1.1 12.0 0.7 15,560 36.2
Cyfarthfa 4.9 0.8 14.0 0.9 15,430 35.9
Blaenclydach 4.2 0.9 21.3 0.6 15,230 35.4
Meiros 4.4 1.8 36.9 1.2 15,600 36.3

of them yield good coke. In the northern area, enje, as well as in Bosnia and Serbia. The
the Durham and Northumberland fields are economically recoverable deposits, with more
among the most important in Great Britain. The than 6.8 x lo9tonnes coal equivalent, are most
character of the coal varies considerably. It is of important to Yugoslavia. Only part of the hard
exceptionally fine quality for steam, coking, coals of the country are suitable for coking. The
household, manufacturing, and gas-producing vast majority of the coal output is used for elec-
purposes. Tables XXI and XXII provide tricity. generation. Table XXIII gives complete
analyses of typical British and Welsh coals. analyses of several Yugoslavian brown coals.
Coal production in the UK is nearly equal to
its domestic consumption, with nearly two- COAL DEPOSITS OFTHE U.S.S.R. AND ASIA
thirds being burned in power-generating sta-
The largest countries of this continent in
tions. Total recoverable reserves are on the
terms of territory, size and population-the
. order of 45,000 million tonnes; production may
U.S.S.R. (Union of Soviet Socialist Republics,
be as high as 200 million tonnes annually by
also called the Soviet Union or Russia), includ-
the turn of the century, 95 percent deep mined.
ing the European part, the People's Republic of
YUGOSLAVIA China, and the Republic of India-are also the
There is only one hard coal deposit in Yugo- countries with the biggest coal deposits. The
slavia, with limited economical importance- total technically and economically recoverable
on the Istria peninsula in the district of Rasa. Of reserves are estimated at greater than 200,000
higher economical importance to Yugoslavia million tonnes coal equivalent; over 10 percent
are the brown coal deposits in the districts of of this is lignite or subbituminous coal, nearly
Zagorje, Trbovlje, Hrastnik, Kakanj, Jenica, and all of which is found in the U.S.S.R. The bal-
Nis, with glance brown coals as well as several ance, as described under the individual coun-
lignite deposits in Slovenia, such as near Vel- tries, is mostly bituminous coal.
Table XXIII. Analyses of a Range of Yugoslavian Brown Coals

As Received:
% Ash 17.8 9.0 19.0 18.7
% Moisture 49.7 49.5 47.8 48.5
Moist.& Ash-free:
Oh Volatile (VM)
% Carbon (C)
% Hydrogen (H)
% Oxygen ( 0 )
% Nitrogen (N)
% Sulfur (S)
HHV, Btullb
HHV,MJlkg
Fusibility Temps.,
reducing at., OF:
Initial deformation
Softening (H =W)
Fluid ,

Ash Composition:
% SiO,
% A1203
% Fe203
% CaO
Oh MgO
% Na10
'10K20
% TiOt
% PtOs
% so3
Baselacid Ratio:
Hardgrove Grindability A B

A: 84 at 35% H 2 0 ; 75 at 30% HaO; 68 at 22% H 2 0 ; 55 at 16% HIO: 90 at 7.5% H 2 0


B: 58 at 36% H20;47 at 31% HaO: 48 at 27% HzO; 45 at 15% H20; 53 at 10% H 2 0

Fig. 7 is a map of European Russia (that por- eastern fields are difficult and expensive to de-
tion of the U.S.S.R. west of the Ural mountains) velop, and have high transportation costs to the
and Asia, showing the coal-bearing areas. using areas.
U.S.S.R. Total economically recoverable reserves are
The Union of Soviet Socialist Republics is estimated at 110,000million tonnes coal equiv-
divided by the Ural Mountains into European alent, of which 75 percent is bituminous coal
Russia and Asiatic Russia, the latter comprised and the balance lignite and brown coal.
principally of Siberia. The accessible coal re- Eighty-percent of the presently recoverable re-
serves of western and central U.S.S.R. have sources are located east of the Urals, mostly in
been largely depleted, while the Siberian and northern Siberia. (See Table XXIV.)
COMBUSTION
1
Coals of the World

Fig. 7 Coal Map of U.S.S.R. and Asia

European U.S.S.R. those of the bituminous. The quantity of good


There are three main coal fields in European coking coal is comparatively small, hence the
Russia: the Donetz basin, the Pechora basin, utilization, on a considerable scale, of anthra-
and the Moscow coal fields. All are of limited cite for blast furnaces and boilers. The fact that
life. The Donetz basin, which lies directly reserves of coal, iron, manganese, and lime-
north of the Sea of Azov, in the Ukraine, has stone are all within a short distance creates
both anthracite and high-grade bituminous an unusual economic situation in the Donetz
coal. The anthracite deposit is extensive, with territory.
estimated reserves of about two and a half times The Vorkuta field, in the basin of the Pechora
COWUSTION - 1

Coals of tho World

Table XXIV. Analyses of Typical U.S.S.R. Coals


Province Location Moisture-and ash-free
or or -As received- H H V -
District Name of Coal %Ash %Hz0 %VM %C %H %O %N I S Btdb MJlkg
Ukraine Aleksandrisk
Kirovsk
Grusine Tkribulsk
Tkvarchelsk
Ural Cheliabinsk
Bogoslovsk
Egroshinsk
Poltavsk
Kazachsky Karagandinsk
Berchogursk
Kirgiz Kizil-Kia
Syliutka
Siberia Minusinsky
Kansky
Trans-Baikal Chernovsky
Bukachachisky
Far East Kirdinsky
Artemovsky
Suchansky
Kuznetsk Anzhero-
Sudzhesky
Leninsky
Kamerovsky
Prokopiersky
Kiselevsky
Osinovsky
Donetz Anthracite
Semi-Anthracite
Low-Vol. Bitum.
High-Vol. A Bit.
High-Vol. B Bit.
High Vol. C Bit.

River, contains one of the biggest fields in the sulfur content. Coal also occurs in the Konban
U.S.S.R. It is located beyond the Arctic circle, territory and in the Province of Kontais in the
as far north as the 68th parallel, with the almost Caucasian region.
unaccessible North Ural mountains to the east. In the U.S.S.R. there has been considerable
The Vorkuta coal is of high calorific value and development in the use of local lour-grade
is easy to coke. fuels, such as peat and oilshale, for generation
The Moscow field has a large reserve, but the of power. The U.S.S.R. has developed tech-
coal is of low-rank and low-grade. It is lignitic nologies for peat dewatering and harvesting,
in character, and has high moisture, ash and including the milled-peat harvesting tech-
,..j
COMBUSTION
Coals of the World

Table XXV. Proximate Analyses of Chinese Coals


-Moisture- and ash-free -
-As received - HHV -
Province DistrictIMine YOAsh 9b Hz0 40 BNlb MJlkg
Liaoning Fushun
Sian
Jilin Muling
Jehol Chaoyang
Fusing
Heilongjiang Tang yuan
Lubing
Hebei ~intsin~
Wanping
Henan Anyang
Liho
Shen Xien
Shandong Yih Xien
Poshan
Shanxi Dahdong
Gansu Yong Don
Hunan Tzehsin
Siangtan
Ningshian
Hubei Tayei
Tzequai
Jiangxi Po-Loo
Gao Jeng
Jian
Anhui Dahdong
Wheizhou
Jiangsu Xiaohsien
Zhejiang Shangshin
Sichuan Weiyuan
Pahsien
Guizhou Tungtze
Guiyang
Yunnan Shuanwei

nique that accounts for 90 percent of the peat shale contains 50 to 55 percent of ash, which is
won in that country. used as cement for construction purposes. The
Russia consumes 80 million tonnes of peat heating value of the shale is 3200 to 3600 Btullb
annually-about 4 percent of the total electri- (7.4 to 8.4 MJlkg)as fired.
cal output is from stations fueled by peat. In the
Asiatic Russia
Leningrad district and in White Russia, oil
shale and peat are used for generation of power. The largest coal deposit in Siberia is the
Oil shale is also used in the Volga Region. The Kuznetsk Basin in south central Siberia, which
Table XXVI. Chinese Coals With Ash Analyses
An-Shan Shang Shan
Mine Guangdong District
Liaoning Province Province South China
Hvbb Lvb Lvb

As Received:
% Ash 1.5 22.5 16.7
% Moisture 2.3 0.5 1.9
Moisture & Ash-free:
% Volatile (VM) 50.3 13.0 20.1
% Carbon (C) ... ... 87.0
% Hydrogen (H) ... ... 4.4
. % Oxygen ( 0 ) ... ... 2.9
% Nitrogen (N) ... ... 0.8
%Sulfur(S) - 0.5 1.6 4.9
HHV, Btullb 14,290 14,870 15,100
HHV, MJIkg 33.2 34.6 35.1
Fusibility Temps.,
reducing atmosphere, OF:
Initial deformation ... 2700 + 2470
Softening (H=W) ... 2700 + 2550
Fluid ... 2700 + 2700 +
Ash Composition:
%sio, 39.7 52.2 51.2
% A1203 42.7 34.3 29.2
% Fez03 6.2 6.6 4.6
% CaO 2.7 0.8 4.3
% MgO 1.6 1.1 0.7
% NaZO 1.3 0.4 0.7
%K20 1.6 2.5 0.8
% TiO, 1.8 1.2 1.8
% pzo5 0.3 0.3 ...
% so, 1.4 0.5 6.4
Baselacid Ratio 0.16 0.13 0.14
Hardgrove Grindability ... 95 120

produces 20 percent of the U.S.S.R. total. Next large area is in northern China, extending over
in importance are the Tungus, Kansk-Achinsk, most of the southern part of Shanxi, and one in
Irkutsk and Minusinsk basins, and the the south extending over southern Hunan,
Karagandinsk and the Saghalin deposits. To Guiahou, Yunnan and Sichuan. In variety,
transport coal to European Russia from many of Chinese coals range from hard anthracite to
these fields requires journeys averaging over lignites of pronounced woody structure. The
900 miles, with some up to 1860 miles. bituminous coals are of medium and high vol-
CHINA, PEOPLE'S REPUBLIC OF
atile rank, the medium volatile being rather
high in ash. Table XXV gives the proximate
Coal deposits of China are extensive, coal analyses of many Chinese coals; XXVI includes
being found i n almost every province. One very ash analyses; and XXVII shows coals presently
2 -4
COMBUSTION
Coals of UIS World

Table XXVIJ. Coals in Use in Chinese Power Stations


Subc Hvb Mvb= Lvb
--

As Received:
% Ash 32.8 37.0 29.7 27.7
% Moisture 22.6 3.3 10.3 9.6
Moisture & Ash-free:
% Volatile (VM) 46.8 39.3 22.7 17.0
% Carbon (C) 74.7 79.6 80.8 83.9
% Hydrogen (H) 4.8 5.4 6.0 4.5
Oh Oxygen (0) 18.6 12.4 10.7 5.1
% Nitrogen (N) 1.3 1.7 1.4 1.4
% Sulfur (S) 0.6 0.9 1.1 5.1
HHV, Btullb 10,890 13,090 13,810 ' 14,030
HHV, MJlkg 25.3 30.4 32.1 32.6
Fusibility Temps.,
reducing atmosphere. OF:
Initial deformation 2070 2700 + 2280 2280
Softening (H =W) 2120 2700+ 2660 2510
Fluid 2280 2700+ 2700 + 2550f
Hardgrove Grindability 45 44 70 86

in use, categorized by rank. INDIA


Most of the coal in China is produced by the India's coalfields are extensive and they con-
longwall retreat method. Hydraulic mining is tain economically recoverable reserves esti-
used in Kailan, with over 3 million tonnes an- mated to be between 10,600 and 33,000 million
nually being produced by this method, and in tonnes of hard coal, and from 500 to 900 million
Fujian in Shandong province. Most of the coal tonnes of lower grades. The coals vary greatly
is found in plains areas rather than in mountain in quality, but are generally low in sulfur-less
ranges, but have thick overburden. The geolog- than 1 percent sulfur, as fired, for most of the
ical condition of the western part of China is production. Ash contents are high, ranging
similar to that of the western U.S. Surface pro- from 15 to-45percent from most mines.
duction is about 4 percent of the total. The main coal deposits are located in a
Coal provides two-thirds of China's total triangle, of which the western edge is in the
energy requirements. Its reserves, estimated to center of India and the eastern corner is about
be about 99,000 million tonnes coal equivalent, 150 kilometers west of Calcutta. Most of the ac-
are exceeded only by those of the U.S. and the tive mining areas are in Andhra Pradesh,
U.S.S.R. It ships substantial amounts of steam Maharashtra, Madhya Pradesh, Orissa, Bihar,
and coking coal to Japan. and West Bengal. The oldest coalfields, those
New projects in the design and construction of Raniganj and Jharia in the east, produce both
are the 1540-20 million tonneslyear surface high-quality metallurgical and nonmetallurgi-
mines in Shanxi province (the An T'ai Pao cal coals. The trend now is toward more de-
mine) and in Heilongjiang province (the Yi Min velopment in the western part of the Indian
mine). coal-belt triangle.
By the year 2000, Chinese coal production is Brown coals are found mainly in the district
projected to be on the order of 2,000 million of Neyveli and in Tamil Nadu. Sixty percent of
tonnes--annually. the brown coal reserves have sulfur contents
- CONBUSllON
Coals of the World

Table XXVIII. Analyses of Typical Indian Coals


Area and Jharia Uttar P. Renusagar Singrauli Neyveli
Rank -, Mvb Hvbb Hvbb Subb Subc Lig A

As Received:
% Ash
% Moisture
Moist. & Ash-free:
% Volatile (VM)
% Carbon (C)
% Hydrogen (H)
% Oxygen (0)
% Nitrogen (N)
% Sulfur (S)
HHV, Btullb
HHV, MJlkg
Fusibility Temps.,
reducing at., OF:
Initial deformation
Softening (H =W)
Fluid
Ash Composition:
% SiO,
% A103
% FeQ3
% CaO
% MgO
% Na,O
Oh KO
% Tion
%Pa5
% SO3
Baselacid Ratio
Hardgrove Grind.
Hardgrove Grindability: 98 at 10% HD:134 at 18% H?O:
135 at 29% Ha;148 at 38% H P

below 1 percent; the rest can be as high as m in thickness. Production is expected to be be-
3-percent sulfur. tween 300 and 400 tonnes annually by the year
Coal mines in India are generally shallow, 2000. Analyses of typical coals from several
with depths to within 300 meters of the surface; areas are included in Table XXVIII.
the deepest mine is about 800 meters. Between
JAPAN
35 and 40 percent of the future production of
bituminous and- subbituminous coal will be Coal is widely distributed throughout all the
mined by open-cast methods, the balance being islands and territories of the Japanese Empire.
by-deep mining. Much of the coal is in thick The islands of Kyusku and Hokkaido are by far
seams-75 percent appears in seams above 4.8 the most important for quantity and .quality.
L
COMBUSTION
Coak of the World

Table XXIX. Analyses of Typical Japanese Coals


-Moisture- and ash-free -
- in& District -As received - -HHV - Hardgrove
Area or Seam %Ash %H20 %VM Btuilb MJk3 Grind.
Kyushu Tagawa 35.4 3.9 51.2 13.660 31.8 45
Iizuka 22.1 2.2 48.3 14,410 33.5 44
Hiyoshi 24.5 3.0 40.0 14.700 34.2 49
Kokura 39.1 6.1 53.6 13,160 30.6 37
Onoura 23.8 2.4 46.2 14,440 33.6 46
Yamano 51.3 2.2 45.8 13,400 31.2 43
Meiji-Saga 15.4 2.2 51.7 14,800 34.4 47
Shinhokusho 23.3 3.6 46.9 14,690 34.2 51
Shikoku Takamatsu 29.7 4.4 47.6 14.040 . 32.6 38
Yamaguchi Sanyo 31.7 2.2 9.5 14.900 34.7 72
Hokkaido Sunagawa 38.0 1.6 49.7 13,710 31.9 49
Bihai 15.1 3.6 45.9 14.330 33.3 47
Yubetsu 21.6 2.4 44.9 14.740 34.3 53
Akama 30.8 2.6 46.4 14,390 33.9 54
, Hahoro 16.8 12.9 55.8 14,510 33.7 36
Horonai 8.2 3.4 48.4 14,490 33.7 38

There are two minor deposits on the main is- TURKEY


land of Honshu. ~ c o n o m i c a l recoverable
l~ re- Considerable deposits of coal and lignite
serves of coal are about 1,000 million tonnes occur in Turkey, the most important so far
equivalent, all extractable by deep mining; being those in the northwestern regions of
nearly half of this will come from the Ishikari Anatolia. Commercial development, however,
coalfield on Hokkaido. Production in the year has been practically confined to the Erigli Ba-
2000 will be on the order of 20 million t.c.e., sin. The Erigli coal, when properly cleaned, is
which will be less than 10 percent of the suitable for most purposes, and compares
national consumption at that time. favorably wih the bulk of European bitumi-
The Japanese coals range from anthracite to nous. It contains 40 to 45 percent volatile mat-
lignite, but the bituminous outweighs all other ter, and is utilized by steamships, railways and
in quantity and value. The greater portion of factories. Table XXXI gives analyses of two
bituminous is of the high-volatile rank contain- coals from Turkey.
ing 6 to 9 percent ash with a high-heat-value
range of 12,000 to 13,000 Btullb (28 to 30 VIE1 NAM
MJlkg). Table XXIX gives the proximate The only known coal deposits i n Viet Nam
analyses of many of the more typical Japanese are anthracitic, chiefly from the Nong-Son area.
coals. As-received ash content ranges from 15 to 27
KOREA percent, with sulfur from 2 to 3.5 percent. Vol-
Although imported bituminous coal is atile matter (VM) is between 8 and 11 percent,
burned in Korea, all of the coal mined in Korea with high heating value (HHV) from 13,800 to
is high-ash-content anthracite. Table XXX 14,600 Btullb (32 to 34 MJlkg), both on a
gives analyses of several anthracites; as- moisture- and ash-free basis. Hardgrove grind-
received sulfur contents range from 0.1 to 0.5 ability is usually between 32 and 53, with some
percent. samples as high as 73.
--
CoumsnoM
Coalsof the World

Table XXX. Analyses of Typical Korean Anthracites


-Moisture- and ash-free -
-As received - -HHV - AshSt, Hardgrove
Area or Mine %Ash %Hz0 %VM BMb Mllkn Red., "F Grind.
Kum-Chun
Dan-Gok (Hamback Field)
Hung-Jun
Bang-Je (Hamback Field)
Chengsun
Cholarn
Dogye
Yonawol
A representative ash composition is
%Si02 -65.0 % MgO -1.0
% AltOa-20.1 % NarO-0.5
%Fe203- 5.3 %K20 -5.0
%CaO - 1.0 % Ti02 -0.9

Table XXXI. Analyses of Typical Turkish Coals


Moisture- and ash-free '.
-As received - -HHV -
Area or Mine %Ash %Hz0 %VM %C %H %O %N %S Btuflb MTlkn

Tuncbilek Subbituminous 14-22 14-24 44.5 76.4 5.8 13.8 2.5 1.5 13,840 32.2
Elbistan Brown Coal 8-24 48-62 67.0 61.4 5.1 29.6 0.8 5.1 10,190 23.7

AFRICA poration and a local nickel-copper mine. The


Both the geological coal resources and the annual production is projected to reach up to 1
economic all^^recoverable coal reserves are million tonnes in the future.
concentrated in the southern part of the conti- MOROCCO
nent. They are preponderantly bituminous
coal. Technically and economically recover- The coal, mainly anthracite, is mined by the
able reserves are estimated to be in excess of state-owned SocietB des Charbonnages Nord-
30,000million tonnes coal equivalent; the Re- Africains (CNA) at Dje,rada in the east. There
public of South Africa has nearly 75 percent of are plans to increase the production to over 2
these; Botswana, 10 percent; Swaziland, about million tonnes by 2000. Nearly 80 percent of
5 percent; and Rhodesia, 2 percent. the annual production is burned in the power
station at Djerada. In future, limited quantities
BOTSWANA, REPUBLIC OF of anthracite could be for export.
Most of the coal reserves are in the eastern
MOZAMBIQUE
part of the country. Coal qualities are poor and
there are no existing coking-coal deposits. The Since early 1978 thepnly existing mining
present coal output is low, but increases in company, ~ o r n ~ a n hCarbonifera
ia de Mozam-
production have recently taken place at the bique (CCM),has been state owned. The annual
Morupule Colliery near Palapye. Consumers of output is about 700,000tonnes and considera-
coal production are the Botswana Power Cor- tion is being given to its expansion. A great part
COMBUSTION
Coals of the WoM

ZIMBABWE--RHODESIA

DEMOCRATIC
REPUBLIC OF
MADAGASCAR

Fig. 8 Coal Map of Africa

of the annual production consists of coking per year. The coal is produced by the state-
coal. It is possible to increase production up to owned Nigerian Coal Corporation, with re-
7 million tonnes, with a coal export potential of coverable reserves being on the order of 90
about 5 million tonnes before the end of the million tonnes. A peak production of 1.5 mil-
century. Today Romania, Japan, Malawi and lion tonnes is anticipated by the end of the cen-
the German Democratic Republic are importing tury. Exports to Ghana are mainly for railways.
coal from Mozambique. SOUTH AFRICA, REPUBLIC OF
NIGERIA The Republic of South Africa (RSA) has
Coal production is now some 300,000 tonnes about 75 percent of all the coal resources of the
--
COMarnON
-1s of the World

African continent. Most of the coal deposits are the coal successions.
situated at shallow depth; more than 10 percent The main Witbank field is the center of the
of the RSA coal output is obtained by open-cast coal-mining industry in the RSA: it produces
mining. In the future, many abandoned "deep" more than half of the coal consumed in the
mines will be reworked from the surface with country. Highveld is the biggest of the coal
modern heavy equipment. fields in area, but exploitation on a large scale
South African coal production consistently has just begun. Waterberg adjoins the Bots-
exceeds the country's domestic requirements; it wana coal field where the Morupule open-cast
exports both bituminous and anthracite coals. is in operation; although it has been intensively
At this time, the Republic of South Africa is one prospected and contains 7 seams of workable
of the 10 largest coal producers and exporters in quality, there are formidable obstacles to
the world. economic extraction at this time. Vereen-
The proportion of total coal consumption for iging-Sasolburg is an important field, with
the generation of electricity has grown stead- three thick seams. In many of the smaller fields,
ily, with approximately 60 percent presently coal is still being prospected or its mining is yet
for that purpose. All new thermal stations are to be fully developed.
located at minemouth, with boilers and pul- Economically recoverable reserves in the
verizers designed to use run-of-mine coal. RSA are variously stated to be between one-
South African coal is deposited in relatively third and 80 percent of the proven reserves
small, isolated basins. The coal seams are thick- shown in Table XXXII. Estimates of South Afri-
est and of best quality in the middle of each ca's coal production in 2000 range from 155 to
basin, but pinch out and increase in ash content over 230 million tonnes annually. The quantity
toward the periphery. The biggest single draw- of coal to be mined for export is a major vari-
back of the coals of the RSA,, particularly for able; an unfavorable political climate toward
export, is that much of the inert mineral matter the RSA will tend to restrict exports below a
present is so intimately associated with the or- physically attainable level.
ganic matter that its reduction to reasonable Two bituminous coals from South Africa, to-
levels is generally difficult and costly. gether with their ash analyses, are given in
The lowest rank coals in South Africa are Table XXXIII.
found in the Orange Free State; the fields there
SWAZILAND
may be regarded as the southern extension of
the Transvaal fields. They have a dry ash-free The Swaziland Collieries Ltd.. a subsidiary
carbon content of 77 percent; the highest rank of Anglo-American Corporation, produces coal
coals are the anthracites southeast of Vryheid, for railway, industrial and domestic markets.
with a dry ash-free carbon content of 91.6 per- Only a small quantity is exported. Future pros-
cent. The ranks of all the other coals fall be- pects are considered to be good as recoverable
tween these two limits. Aside from a few minor reserves are in excess of 1500 million tonnes of
peat and lignite occurrences, all coals vary in bituminous coal; production of about 6 million
rank from about the lower limit of high-volatile tonnes, nearly 4 million for export, is possible
bituminous (or upper limit of subbituminous) by 2000. Coking coal is exported to Kenya.
coal to anthracite. The higher rank coals are Japan and Mozambique.
largely confined to Natal, where the fields are
ZAIRE
essentially an extension of the Transvaal fields.
The coal-bearing areas of the Repubjic are The coal is produced by Charbonnages de la
first subdivided into coal provinces, which in Luena S.A., Briissel, a subsidiar~rof Union
turn are split into coal fields, based either on MiniBre. The consumers of the coal are the
physical separation of the areas or on con- power stations and the copper industry. A part
spicuous or slight stratigraphical differences in of the coal is blended with Rhodesian coking
COMBUSTION "'

Coals of Un World

'coal for producing a coke suitable for copper OCEANIA


.-
smelting. Production of over one million
tonnes by 2000 is expected. Oceania is usually considered to include the
lands of the central.and south Pacific, includ-
ZAMBIA ing ~ u s t r a l i a ,~ e Zealand,
w Tasmania, and
The coal is produced by Maamba Collieries sometimes, the Malay archipelago. For con-
Ltd., Lusaka, in the south of the country. With venience, we have included coal data from In-
capital aid from the African Development Bank donesia and the Phillipine Islands in this sec-
and the Federal Republic of Germany, the tion. Fig. 9 shows the coal fields of Australia,
mines at the Maamba region are to be modern- New Zealand, and Tasmania.
ized. The main uses of Maamba coal are in cop-
per smelting, cement and fertilizer production, Table XXXIII. Analyses of Typical South
and for steam generation. By the year 2000 African (RSA) Coals
production is anticipated at about 3 million
tonnes. Bieminous Coal
and Ash Analyses
ZIMBABWE (RHODESIA)
As Received:
Coal is mined by Wankie Colliery Company % Ash
Ltd., Salisbury, a subsidiary of Anglo-Amer- % Moisture
ican Corporation. Economically recoverable Moist. & Ash-free:
bituminous-coal reserves approximate 800 % Volatile (VM)
million tonnes. The export potential depends % Carbon (C)
on political considerations. Production at pre- % Hydrogen (H)
sent is largely geared to satisfy home consump- % Oxygen (0)
tibn, but coal is exported also to Zaire and % Nitrogen (N)
Zambia. The coal has excellent steaming and % Sulfur (S)
coking qualities. The average analysis is: HHV, Btullb
HHV, MJIkg
Hz0 VM FC Ash S Btunb MJlkg
0.7 21.0 66.8 11.5 2.8 12,750 29.7 Fusibility Temps.,
reducing at., OF:
Initial deformation
Softening (H =W)
Table XXXII. Proven Resources of Fluid
Mineable Bituminous Coal (In Situ)
Ash Composition:
Millions of tonnes % SiOp
Witbank, including Springs-Vischkuil 14,186 % AlQ,
Highveld 7,231 % FeQS
Waterberg .-. 6,386 % CaO
Vereeniging-Sasolburg 1,232 % MgO
Carolina-Wakkerstroom "
% NaQ
(Eastern Transvaal) 805 %K20
%Ti02
Newcastle-Dundee (Klip River) 748
South Rand 600 % P205
Other fields, below 600 x 106tonnes % SO3
each 1,034 Baselacid Ratio 0.22 0.24
Total 32,222 Hardgrove Grind. 46 50
--
COMBUSION
Coals of the World

AUSTRALIA

I
Fig. 9 Coal Map of Oceania

AUSTRALIA depth of 200 meters and a minimum seam


Australia's large coal resources are concen- thickness of 15 meters. The coal is used pre-
trated in the Eastern States. The largest and dominantly for power generation. The average ,
economically most significant deposits of moisture content is 62 percent and the lower
bituminous coal are found in the Bowen Basin heating value, as received, ranges from 6.0 to
of Eastern Queensland and the Sydney Basin in 12.5 MJlkg (2,580to 5,370 Btullb).'

New South Wales. Nearly half of the country's The coal resources in other States are rela-
production is from underground mines in New tively small, in most cases comprising isolated
South Wales; another 30 percent is from open- deposits of subbituminous coal or lignite. The
cut mines i n Queensland. The Galilee Basin in major use for these coals in South Australia and
Queensland also contains a large resource and Western Australia, such as from the Collie ba-
the Surat and Clarence-Moreton Basins are of sin, is in power stations.
significance. In Australia, a depth of 1,000 me- Australia's economically recoverable re-
ters is generally taken as the current limit for serves are in excess of 25,000 million tonnes,
bituminous coal to be regarded as economi- about 60 percent of which is bituminous coal
cally extractable, - and the balance,-lowerranked types. About 20
Major browncoal deposits are located in Vic- percent of the bituminous coal is capable of be-
toria where the Latrobe Valley contains proved ing surface-mined. Production of all types of
recoverable reserves of some 35,000 million coal is anticipated to be as high as 300 million
tons within the limits of a maximum mining tonnes coal equivalent in the year 2000.
I
COMBUSTION
Coals of the World

Table XXXIV. Analyses of-TypicalAustralian Coals


Fanells Bayswater Liddell Foxbrook Puxtrees Yallourn
- C.K. Seam

As Received:
% Ash
% Moisture
Moist. & Ash-free:
% Volatile (VM)
% Carbon (C)
% Hydrogen (H)
% Oxygen (0)
% Nitrogen (N)
% Sulfur (S)
HHV, Btullb
HHV, MJIkg
Fusibility Temps.,
reducing at., O F :
Initial deformation
Softening (H =W)
Fluid
Ash Composition:
% Si02
% AlD3
% Fe203
% CaO
% MgO
% Na20
%K D
% TiO?
/ P
OO

% SO,
ase el acid Ratio
Hardgrove Grind.

Table XXXIV gives analyses of Australian INDONESIA


coals from several mining areas. Since 1972, only two state-owned coal mines
are in active production: Ombilin in West
NEW ZEALAND
Sumatra and Bukit Asam in South Sumatra.
Coal ranging from anthracite to lignite oc- Coal deposits of economic significance are
curs in many sections of New Zealand. The confined to the western part of Indonesia, on
Buller-Mokihinui is the best known bitumi- the islands of Sumatra and Kalimantan. Esti-
nous field. The coal is of good quality and makes mates of measured reserves of bituminous coal
an excellent steam fuel. It is coking, but the and lignite on these islands are 200 million and
coke produced is not rated high. Table XXXV 100 million tonnes respectively.
gives complete coal and ash analyses of two Ombilin coal is a hard bituminous to sub-
New Zealand coals. bituminous coal. It is excellent steam coal with
.-
COMBUSTION
Coals of the World

mild coking properties. Detailed explorations


carried out in some parts of the Ombilin basin Table XXXV. Analyses of Typical New
have indicated about 35 million tonnes of Zealand Subbituminous Coals
mineable coal reserves.
Maori Farm Ohinewai
The proximate analysis of a typical Ombilin Area
coal sample is as follows:
As Received:
Moisture : 6.0% % Ash
Ash : 1.5% % Moisture .

Sulfur : less than 0.5% Moist. & Ash-free:


Volatile Matter : 46% m.a.f. basis % Volatile (VM)
Calorific Value : 14,590 Btunb (33.9 % Carbon (C)
.. MJlkg) % Hydrogen (H)
% Oxygen (0)
The coal in the region of Bukit Asam ranges
% Nitrogen (N)
from lignite through bituminous, subbitumin-
O/O Sulfur (S)
ous to anthracitic coal and anthracite. The Air
HHV, Btullb
Laya opencast mine of Bukit Asam remains the
HHV, MJlkg
field with the most potential. Recent studies
indicate that there is a reserve of close to 100 Fusibility Temps.,
reducing at., OF:
million tonnes of coal in this field.
Initial deformation
The average proximate analyses of the vari-
Softening (H =W)
ous coals presently produced in Bukit Asam are
Fluid
Air Laga subbituminous coal Ash Composition:
Moisture : 18.0% to 23.2% % SiO,
Ash : 4.4% to 8.9% % AID,
Sulfur : 0.16Oh to 0.41% % FeD3
Volatile Matter : 29.4% to 32.1% as Oh CaO
received % MgO
Calorific Value : 10,800 to 11,700 Btullb % NaD
(25.1 to 27.2 MJlkg), as Oh K,O
received % Ti0,
% so,
Suban low-volatile bituminous coal
Baselacid Ratio
Moisture : 0.5% to 1.2%
Hardgrove Grind.
Ash : 3.6% to 4.4%
Sulfur : negligible
Volatile Matter : 15% to 19% the lignite is black, and seldom displays a
Calorific Value : 14,400 to 14,760 Btullb woody structure or brown color. The bitumi-
(33.5 to 34.3 MJlkg), as nous coals are black, hard and lustrous. They
received are generally noncoking.
A typical Philippine coal, from Liguan, has
PHILIPPINE ISLANDS an as-received ash content of 11.5%, and mois-
Coal is mined in eight localities in the ture of 9.4%. On a moisture- and ash-free basis,
Philippine Islands, namely: Bataan, Cebu, volatile matter-is.45.3%, sulfur is 0.8%, and
Zamboanga, Politti, Masbati, Mindoro, Luzon HHV is 13,480 Btullb (31.3 MJkg).
and Mindanao. The basins are small and dis- Ash softening temperature of such a coal,
continuous. The deposits contain lignite, sub- i n a reducing atmosphere, is approximately
bituminous and bituminous coals. The bulk of 2190F.
.. COMBUSTION
Coab of the World

termined by tests in which the coal is heated


INTERNATIONAL COAL slowly.
CLASSIFICATION DIVISIONOF HARD COALS INTO CLASSES

As the international trade in coal increased Hard coals are first classified in the inter-
following World War 11, the Coal Committee of national system according to their volatile- .
the Economic Commission for Europe estab- matter content, calculated on a dry, ash-free
lished a Classification Working Party in 1949 to basis. These classifications are:
develop an international system for classifying Class No. VM dry, ash-free %
coal. The system for classifying hard coals was 1A 3 - 6.5
published in 1956 as a document of the United 1B > 6.5-10
Nations.* In 1958, the U.S. Bureau of Mines 2 >10 -14
published the results of its study of how this 3 >14 -20
classification system would apply to American 4 >20 -28
coals. Two years later the classification system 5 >28 -33
was applied to brown coals and lignite^.^,^ 6-9 - ' >33
Based on European terminology, the expres-
sionhard coal as used in the international clas- As volatile matter is not an entirely suitable
sification system is defined as coal with a gross parameter for classifying coals contailling
calorific value of more than 10,260 Btu per lb more than about 33 percent volatile matter,
(5,700 kg-cal per kg or 23.86 MJlkg) on the calorific value on a moist, ash-free basis is used
moist, ash-free basis. Coals classified by the for such coals, as follows:
Approximate
American Society for Testing Materials as Gross calorific value, limits of
anthracitic, bituminous, and higher rank sub- moist., ash-free basis, VM, dry,
Clasp No. Btullb ash-free %
bituminous are included in the hard-coal cate-
6 >13,950 33-41
gory. Brown coals and lignites are those coals
7 >12,960-13,950 33-44
having gross calorific values below 10,260 Btu
8 ><0,980-12,960 35-50
per lb, moist but ash-free.
9 >10,260-10,980 42-50
Excerpts from the two referenced classifica-
tion sysiems are included in the following text. The gross calorific Value of coal on the moist,
These excerpts will assist users of various types ash-free basis means the calorific value of the
of coals world-wide, in relating such coals to coal in equilibrium with air at 30C aria 96 per-
the American types referred to frequently in cent relative humidity, calculated to an ash-
this and other engineering references. free basis. For practical purposes, the moisture
in the equilibrated sample is considered equiv--
CLASSIFICATION OF alent to the natural bed moisture of the coal,
HARD COALS BY TYPE that is, the coal moisture at freshly exposed bed
faces free of visible water.
Table XXXVI shows the international system
DIVISION OF HARD-COAL CLASSES INTO GROUPS
of classifying hard coals according to their vola-
tile-matter content, calculated on a dry, ash- The nine classes of hard coal, based on
free basis, resulting in nine classes of coals. volatile-matter content and calorific value, are
The nine classes of hard coal, based on volatile- divided into groups according to their caking
matter content and calorific value, are then di- properties. Caking properties, as used in the
vided into groups according to their caking classification system, are a measure of the be-
properties, as measured by tests when the coal havior of coal when heated rapidly. Either of
is heated rapidly. The coal groups are further two methods-the free-swelling test (crucible-
subdivided according to coking properties de- swellingstest) or Roga test-may be used to
-.
-

Table XXXVl. International classification of hard coals by type (Ref.2)


Groups Subgroups
(determined by coking properties) Code Numben (determined by coking properties]
Alternative The first figure of the code number indicates the class of coal, de- Alternative
Group termined by volatile matter content up to 3396 VM and by calorific Sub. Subgroup Parameters
Ekr Free-swelling in-
dm i . Q
parameter above 33% VM.The second figure indicates the group of
coal, determi~~ed by coking properties. The tbird figure indicates the
Group
Number .latometer Gny-King
swelling number) subgroup, determined by coking properties.
435 535 635 5 >I40 >G,
334 434 534 634 734 4 >50-140 GrG,
3 >4 >45
333 433 533 633 733 3 >0-50 G,-G,

3F3i2432 532 632 732 832 2 20 E-G

323 423 523 623 723 823 3 >0-50 GI-G,

2 2%-4 >20-45 322 422 522 622 722 822 2 50 E-G

Contraction
321 421 521 621 721 821 1 B-D
only
212 312 412 512 612 712 812 2 1 0 E-G
1 1-2 >5-20
Contraction
211 311 411 511 611 711 811 B-D
onl!l
100 Non-
0 O-I/2 0-5 200 300 400 500 600 i O O 800 900 0 A

Class Number 0 1 2 3 4 5 6 7 8 9
As an indication, the t o l l ~ \ ~ i n g
- classes have an approximate VM

Class
"'latile matter'
.(dry, ash-free)
'' 0.3 .
> 3 10

In
3 3 ~ 3 3 >3] >31
content of
Class 6 33~41%ilM
85
7 33-44Yo \'M
Param- ' 8 35-50% \'M
Calor~fic - - - - - - >IZPBO- >12910 >lozm 9 42-50/o VM
'139YI
13954 12 gBO l 0 W
parameter

CLASSES
(Determined by volatile matter up to 33% VM and by calor~f~c
parameter above 33% VM)
A

Note: [i) \+'here the ash content of coal is too high to allow classification according to the present qstems. it must be reduced by laborntoq float-and-sink method lor any other
appropriate means). The specific gravity selected for flotation should allotv a maximum yield of coal with 5 to l v p e n e n t of ash.
(ii) 332a.. . >14-36% VM
.
332b.. . >16-20% \'M
-

[iii) Gross calorific value on moist, ash-free basis [30C., 96% relative humidity). Btuflb
coaeusTior
Coak of the World

measure caking properties. The division of belongs in class 6, which becomes the first fig-
classes into groups, according to free-swelling ure of the code number. The free-swelling
index or Roga index, are: index is 6; alternatively, the Roga index is 85,
Free- so the coal belongs in group 3, which becomes
swelling Roga the second figure of the code number. As the
Group No. index index maximum dilatation is 60, or the Gray-King
0 0-% 0-5 coke type is G,, the coal belongs in subgroup 4,
1 1-2 >5-20 which is the third figure of the code number.
2 2%-4 >20-45 Therefore the code number of the coal is 634.
3 >4 >45
CLASSIFICATON
Division of Groups into Subgroups
OF LOWER-RANK COALS
The hard-coal groups are further subdivided
according to coking properties, as measured by Table XXXVII shows the international sys-
tests in which the coal is heated slowly. Coking tem of classifying brown coals and lignites,
. those fuels having gross calorific values below
properties are measured either by maximum
dilatation, using the Audibert-Arnu method, or 10,260 Btu/lb (5,700 kcalkg or 23.86 MJkg).
by Gray-King coke type. The division into sub- The parameters for classifying these coals are
groups follows: their total moisture and yield of low-temper-
Gray-King ature tar. As a correlation exists between the
Subgroup No. Maximum dilatation coke type total moisture and calorific values of the lower
0 Nonsoftening A rank coals, the moisture parameter indicates
1 Contraction only B-D the value of the coal as a fuel; the tar indicates
2 0 and less E-G the value of the coal for chemical processing.
3 >O to 50 G1 4 4 DIVISION OF LOWER-RANK COALS
4 >50 to 140 G&R INTO CLASSES
5 >I40 >Gs
The coals are first classified according to
CODE NUMBERS their total moisture content as ash-free coals.
A three-figure code number is used to ex- Total moisture is that contained in freshly
press the classification of a hard coal. The first mined coal. The class numbers and corre-
figure indicates its class, the second figure the sponding range of moisture values are:
group, and the third figure the subgroup. An Total moisture,
example of the use of the system follows, based Class No. ash free, 96
on a coal with the following characteristics: 10 20 and less
11 >20 to 30
Volatile matter, dry, ash-free, % 37 12 >30 to 40
Calorific value, moist ash-free Btullb 14,510 13 >40 to 50
Caking properties: 14 >50to 60
Free swelling index 6 15 >60 to 70
Roga index 85
Coking properties: The numbering system starts with 10 to fol-
Maximum dilatation 60 low consecutively after the classes numbered 0
Gray-King coke type GG to 9 in the international classification of hard
coals by type.
As the volatile-matter content on a dry, ash-
free basis is greater than 33 percent, the class Division of Classes in Groups
number is determined by the gross calorific The lower-rank coals divided into classes ac-
value on a moist, ash-free basis. As the gross cording to total moisture are subdivided into
calorific value is more than 13,950 Btu the coal groups by yield of low-temperature tar, calcu-
--
COMBUSIION
Corls of tho World

lated dry and ash-free. Group numbers with the above indices. The methods are sum-
corresponding range of tar yields are: marized in the following text.
Tar, dry,
Group No. ash free, % EQUILIBRIUMMOISTURE CONTENT
10 and less
In the international system, coals with more
>10 to 15
than 33 percent volatile matter on the dry, ash-
>15 to 20
free basis are classified according to calorific
>20 to 25
value on the moist, ash-free basis. The term
>25
moist refers to coal containing its natural bed
CODE NUMBERS moisture but no visible water on the surface. It
is assumed that the natural bed moisture of coal
A four-figure code number indicates the in the ground represents the moisture-holding
classification of lower-rank coals. The first two capacity of the coal when in equilibrium with
figures identify the class; the last two, the air at approximately 100 percent relative
group. For example, if total moisture, ash free, humidity. Because of the difficulty of equili-
-is 35 percent, the coal is placed in class 12; if brating samples in such an atmosphere, the
the yield of tar is 11 percent, the coal is as- equilibrium moisture content or moisture-
signed to group 10 and the code number of the holding capacity is determined at 96 to 97 per-
coal is 1210. cent relative humidity, which for practical
METHODS OF COAL ANALYSIS AND TEST purposes is considered to represent the mois-
ture in the coal bed.
The international classification system pro- The test is essential for classifying wet Sam-
vides that standard methods of the Inter- ples of coal in order to bring the coals to their
national Organization for Standardization > natural-bed-moisture condition. The proposed
(ISO)shall be used when such methods become IS0 method for moisture-holding capacity is
available. Much progress has been made in the equivalent to the ASTM method for equilib-
work of standardization, although the methods rium moisture of coal. The method also can
have not been approved in final form. Until restore partially air-dried samples of all coals
standard methods are adopted, it is provided except lignites to virtually bed-moisture state.
that national standards may be used. The fol- To conduct the test, a sample of coal crushed
lowing provisional tolerances are to be used for to pass a number 16 sieve is wetted, drained of
the parameters pending adoption of inter- '
excess water, and equilibrated in a reduced-
national methods of analysis and test: pressure vessel charged with a pulp of potas-
Volatile matter, VM sium sulfate crystals arid water. The saturated
20% or less 2 1.0 unit solution of potassium sulfate at 30C maintains
More than 20% + 5.0% of value a relative humidity of 96 to 97 percent in the
Free-swelling index 2 %unit vessel. After moisture equilibrium is reached,
Roga index + 5 units which usually is within 48 hours, the coal Sam-
Maximum dilatation: ple is covered, removed from the vessel, and
Subgroups 0, 1, 2 , 3 -C 5 units weighed. The moisture content of the con-
Subgroup 4 + 10 units ditioned sample is then determined.
Subgroup 5 2 15 units
FREE-SWELLINGINDEX TEST (CAKING)
Gray-King coke type 2 1 type
Gross calorific value + 110 Btullb The test for free-swelling index of coal,
The appendix to reference 2 includes meth- which is a measure of the coal's caking
ods for determining equilibrium moisture con- properties, was originally developed in Great
tent (moisture-holding capacity) and several of Britain and is called there the crucible-
COMBUSTION I

Coalsof the World

Table XXXVII. International Classification of Brown Coals and Lignites


Group parameter
Group - taI yield Code Numbers
No. (dry, ash free), 40 -

40 >25 1040 1140 1240 1340 1440 1540


30 >20 to 25 1030 1130 1230 1330 1430 1530

10 >lo to 15 1010 1110 1210 1310 1410 1510


00 10 and less 1000 1100 1200 1300 1400 1500
Class no. 10 11 12 13 14 15
Class parameter 20 >20 >30 >-I0 >50 >60
total moisture, ash-free, and
percent less -30 -40 -30 -60 -70
Moist, ash-free basis (30C and 96 percent relative humidity).
Total moisture content refers to freshly mined coal. For internal purposes, coals with a gross calorific value over 5,700 kcaUkg (maf), considered
in thecountry of originas brown coals but classified as hard coals for international purposes, may beclassifiedunderthis system, to ascertain. in
particular. their suitability for processing. \\'hen total moisture content is over 30 percent, gross calorificvalue is always belon, 5,700 kcallkg

swelling test. It is a standard method used in


several countries, including the United States.
The test consists of heating a 1-gram sample
of pulverized coal to 8 2 0 ~ 2 ;n 5 ~a ~covered (1)
crucible and comparing the size and shape of
the coke button obtained with the outlines of a where:
set of standard profiles numbered in half units Q = weight of residue after carbonization,
from 0 to 9. The number of the profile most a = weightofoversizebeforefirstscreening,
closely corresponding to the cmss section of b = weight of oversize after first screening,
the coke button is the free-swelling index or,
= weight of oversize after second screen-
in British terms, crucible-swelling number.
ing,
- and
ROGA-INDEX TEST (CAKING) d = weight of oversize after third screening.
-
The alternative method for determining cak- American coals in combustion processes. As
ing properties is the Roga test, developed and there is an approximate correlation between
used in Poland. The test is conducted by car- the results of the free-swelling-index and
bonizing a mixture of 1 gram of coal and 5 Roga-index tests, the Roga index probably is
grams of a standard anthracite at 850C for 15 about as significant as the free-swelling index
minutes. The mechanical strength of the result- for measuring caking properties.
ing coke button is measured by an abrasion test
AUDIBERT-ARNU DILATOMETER TEST (COKING)
in a special rotating drum. At the end of the
tumbling period, the residue is screened on a Better known in Europe than in the United
sieve with 1-mm round openings and the over- States, the Audibert-Arnu dilatometer test is
size weighed. This process is repeated twice. used i n studies of coking properties of coal.
The index is calculated from the results of the A briquetted pencil of coal is carbonized in a
screening test by the following formula. vertical tube topped by a steel rod that slides in
No information is available on the use of the the bore of the tube. The pencil, which is
Roga index for measuring caking properties of formed in a die, is lightly tapered; its diameter
COMBUSTION. "

Coah of the World

averages 6% mm, and its length is 60 mm. The phism or progressive alteration in the natural
maximum displacement of the rod measured coalification series from lignite to anthracite.
on an external scale is reported as a percentage The ASTM classification system is based on
of the original length of the pencil. The dilata- the parameters of fixed carbon or volatile
tion is calculated as follows matter and calorific value calculated on a
mineral-matter-free basis. Higher-rank coals
Displacement of piston, mm x 100
are classified according to fixed carbon or vol-
Dilatation, % =
60
atile matter on the dry basis, and the lower-rank
(2)
coals according to calorific value on the moist
or bed-moisture basis. Agglomerating and
GRAY-KING COKE-TY PE TEST weathering indexes are used to differentiate be-
tween some adjacent groups.
Developed in Great Britain, the Gray-King
coke-type test was used at firs't as a bench-scale, COMPARISON OF INTERNATIONAL
low-temperature ~Gbonizationassay for de- AND ASTM SYSTEMS
termining yields of coke, gas, tar and liquor.
The Coal Survey adopted the test for indicating The ASTM system provides for classification
coking properties. The method was then stan- of all ranks of coal while the international clas-
dardized by the National Coal Board for classi-
sification is based on two systems: one for the
fying coals of the United Kingdom. hard coals and the other mainly for brown coals
The test is conducted by carbonizing a 20- and lignites. The borderline between the two
gram sample of coal progressively to 600C in a
international classifications occurs at 10,260
horizontal tube furnace. The carbonized res- Btullb (5,700 kcallkg or 23.86 MJlkg) moist and
idue is classified as to volume, coherence, fis-
ash-free and is nearly the midpoint of the sub-
suring, and hardness by comparing it with a bituminous B group of the ASTM system.
series of residues. For coals that form powdery
Therefore, some subbituminous B coals and all
to hard coke residues that occupy the same subbituminous A, bituminous, and anthracitic
volume as the original coal (standard coke),the
coals of the ASTM system are identified ac-
type of residue is assigned letters ranging from
cording to the international classification of
A to G. For coals that swell to fill the cross sec-
hard coals by type. The other subbituminous B
tion of the tube, electrode carbon is mixed with
and all subbituminous C and lignitic coals are
the coal to obtain a strong, hard coke of the covered in the international classification of
same volume as the original coal-electrode car-
coals with a gross calorific value below 5,700
bon mixture. The coke type is indicated by thekcallkg. .
letter G with a subscript figure, that is, G, G,,To divide lower rank coals into classes, the
etc. The subscript shows number of parts of international system uses the total moisture
electrode carbon needed in the mixture with parameter while the ASTM uses the calorific
coal to give a G-type (standard) coke. Reference
value. Fig. 10 shows that a good correlation
2 gives the Gray-King scheme for examining exists between total moisture and calorific
and classifying coke types. - is based on
value of low-rank coals. The figure
analyses of exchange samples of coal given in
INTERNATIONALSYSTEM APPLIED
TO AMERICAN COALS
Table XXXVIII.
Fig. 11 compares the class numbers and
The American Society for Testi~gMaterials group boundaries of the international system
system of classification of coals by+rank-was for hard coals with those of the ASTM classifi-
discussed in Chapter 2. The ASTM Standard cation. As the figure shows, the group bound-
Specification of Coals by Rank D-388 groups aries in the two schemes are quite similar; thus,
coals according to their degree of metamor- class numbers in the international system are
COMBUSTION
Coals of the World

Table XXXVIII. Source, Analysis and classification


of Exchange Samples of Low-Rank Coal
Moisture- and ash-free Equilib. -
- As received - -H H V M o i s t ~ r e -Classification-
,~
Source of Sample % Ash % H20 90VM % C %H % 0 % N % S Btullb MJlkg % ASTMB IC No.

Belgium
Florennes 2.2 63.3 53.8 70.1 5.0 23.5 0.7 0.7 11,910 27.7 39.8 LigB 1510
Canada
Alberta 7.3 24.2 39.2 76.6 5.5 15.8 1.6 0.5 13,150 30.6 24.4 Subb 1100
Czechoslovakia
Northern Bohemia 2.7 20.2 49.0 77.6 5.8 14.7 1.0 0.9 13,890 32.3 20.9 Suba 800
6.4 31.2 50.5 76.0 6.0 15.7 1.1 1.2 13,560 31.5 30.7 Subc 1220
Central Bohemia 5.9 21.1 38.1 79.5 5.0 13.1*1.2 1.2 13,770 32.0 20.4 .- Subb 900
15.9 23.2 43.6 77.1 5.2 '11.1 1.5 5.1 13,640 31.7 25.9 Subb 1110
SouthernBohemia 7.4 44.6 56.5 70.2 5.4 19.5 0.9 4.0 12,240 28.5 43.5 LigA 1310
WesternBohemia 6.0 39.7 51.7 76.6 6.1 15.2 1.2 0.9 13,680 31.8 37.0 LigA 1330
Slovakia 12.2 36.1 51.3 69.6 4.9 19.5 1.5 4.5 11,870 27.6 39.0 LigA 1300
Federal Republic
of Germany
Rhine Region 3.3 62.2 55.3 69.1 4.9 24.1 0.9 1.0 11,580 26.9 48.4 LigB 1510
Bavaria,Peissenberg 11.9 9.7 52.8 72.8 5.4 12.4 1.6 7.8 13,200 30.7 12.0 Suba 800
Greece
Athens Area,
Peristeri 6.5 22.4 46.9 71.8 4.7 '19.8 1.9 1.8 12,140 28.2 27.4 Subc 1100
Island of Euboea,
Aliveri 11.3 33.3 56.1 68.0 5.2 23.9 0.9 2.0 11,600 27.0 36.8 LigA 1210
West Macedonia,
Ptolemais 12.2 59.0 57.9 65.4 4.3 27.3 1.9 1.1 10,340 24.0 50.0 LigB 1500
Italy
Lucania,Mercure 10.1 58.8 58.6 65.4 5.2 25.3 1.8 2.3 11,020 25.6 51.7 LigB 1500
Toscana,Pietrafitta 9.9 60.8 57.3 70.5 4.8 19.9 1.9 2.9 11,840 27.5 51.7 LigB 1500
Toscana,Valdarno 5.3 51.9 56.8 66.5 5.2 26.3 1.0 1.0 11,350 26.4 47.2 LigB 1420
Umbria, Spoleto 7.8 31.8 60.4 64.8 5.3 27.3 1.1 1.5 11,140 25.9 34.1 LigA 1210
Federation of Maylaya
Selangor,BatuArang 7.5 17.7 48.7 77.1 5.8 15.1 1.6 0.4 13,840 32.2 19.1 Suba 800
Poland 7.3 53.9 60.8 71.4 5.8 20.2 0.6 2.0 12,510 29.1 42.2 LigB 1420
6.7 17.6 44.0 77.7 5.1 14.3 0.9 2.0 13,540 31.5 21.0 Suba 800
U.S.S.R.
Chelyabinsk Basin 9.9 17.8 43.6 76.2 5.2 16.2 1.9 0.5 12,910 30.0 18.9 Subb 900
Rhiczechinsk 6.9 37.0 43.7 72.2 4.3 22.1 1.1 0.3 11,910 27.7 34.8 LigA 1200
Borneo-Sarawak
Upper Rajang Valley 1.3 23.3 48.1 72.4 4.9 21.2 1.4 0.1 12,390 28.8 22.9 Subc 1110
East Germany
Niederlausitz 2.5 59.8 55.6 68.1 4.7 25.8 0.7 0.7 11,720 27.3 44.7 LigB 1510
Bautzen 3.9 63.4 57.6 70.1 5.3 21.9 0.7 2.0 12,100 28.1 43.3 LigB 1510
Oberlausitz 3.2 58.3 54.4 67.7 5.2 26.0 0.6 0.5 12,020 28.0 47.2 LigB 1510
COMBUSTION
C0.k at the World

Table XXXVIII. Source, Analysis and Classification


of Exchange Samples of Low-Rank Coal-Continued

Moisture- and ash-free Equilib.


received-
-AS -HHV - Moisture,* Classification
Source of 'Sample %Ash %HZ0 %VM %C % H % 0 % N % S Btullb MJlkg % ASTMB IC No.
'Aschersleben 5.0 44.5 72.2 76.4 7.9 12.0 0.4 3.3 14,680 34.1 37.3 LigA 1340
Bitterfeld 5.8 54.6 55.6 71.3 5.1 18.0 0.6 5.0 12,560 29.2 49.3 LigB 1410
Halle 6.0 54.6 58.9 71.6 5.6 17.2 0.6 5.0 12,770 29.7 50.2 LigB 1420
Geiseltal 4.3 55.0 58.0 71.05.7 16.50.8 6.0 12,92030.0 48.5 LigB 1420 i
Borna 4.5 55.1 60.3 72.5 5.9 18.1 0.7 2.8 13,000 30.2 44.2 LigB 1420
United Kingdom 4.0 17.6 43.6 77.6 5.1 13.8 1.4 2.1 13,610 31.7 17.8 Suba 800
United States
Colorado, Weld County 4.8 25.2 40.8 78.6 5.1 14.1 1.7 0.5 13,630 31.7 24.8 Subb 1110
Montana,
Musselshell Co. 7.0 13.9 39.6 80.9 5.1 12.2 1.3 0.5 14,110 32.8 14.1 Suba 800
North Dakota,
Burke Co. 4.2 37.2 43.4 74.1 4.7 19.3 1.2 0.7 12,470 29.0 37.5 LigA 1200
North Dakota,
Mercer Co. 4.1 38.1 45.3 72.7 4.9 20.8 0.9 0.7 12,330 28.7 37.7 LigA 1200
Texas, Mi'lam Co. 9.4 36.0 49.9 74.7 5.4 16.4 1.5 2.0 12,980 30.2 37.6 LigA 1210
Mrashington,
Lewis Co. 7.1 28.5 50.7 74.6 5.4 18.0 1.3 0.7 12,800 29.8 29.6 Subc 1210
, Wyoming, Campbell Co. 5.0 28.2 49.0 74.0 5.6 18.6 0.9 0.9 12,970 30.2 30.8 Subc 1110
Wyoming,SheridanCo. 3.6 25.9 42.8 75.9 5.1 17.0 1.6 0.4 13,10030.5 25.3 Subb 1110
Yugoslavia
Bosnia, Banovici 10.4 17.9 45.6 75.6 5.4 14.7 2.3 2.0 13,310 31.0 19.2 Subb 900
Bosnia, Breza 8.8 17.2 46.9 75.3 5.2 13.6 1.9 4.0 13,330 31.0 18.3 ,Subb 900
Bosnia, Kakanj 12.5 6.1 49.0 77.2 5.4 11.4 2.3 3.7 13,720 31.9 7.3 Suba 800
Bosnia, Kreka 3.3 39.8 52.0 69.7 5.2 23.7 0.9 0.5 12,110 28.2 37.2 LigA 1310 I
Serbia, Senjski 10.0 15.6 54.3 71.7 5.6 19.5 1.4 1.8 13,010 30.3 17.1 Subb 900 1
Slovenia, Trbovlje 7.3 24.9 48.4 71.0 5.0 18.4 1.3 4.3 12,520 29.1 25.9 Subc 1110 ,

d-Equilibrium moisture, %, is on an ash-free basis


B-Abbreviation's'are listed in Table I1
'-IC No. is the International Code Number

nearly equivalent to group names in the ASTM 8 ~ i ~ h - J o l a t iCl bituminous


e coal
classification. For example, and subbituminous A coal
9 Subbitminous B coal
Class number in Group name in
international system ASTM system The international classification system for
0 Meta-anthracite hard coals differs from the ASTM classification
1 Anthracite in that parameters of caking and coking
2 Semianthracite properties are introduced to indicate how the
3 Low-volatile bituminous coal coal can be used in combustion and carboniza-
4, 5 Medium-volatile bituminous tion processes. This concept is followed in sex1-
--
coal era1 European national systems of classifica-
6 High-volatile A bituminous coal tion. While the ASTM classification of coal was
7 High-volatile B bituminous coal being developed, the feasibility of classifying
COMBUSTION
Coals of tho World

Fig. 10 Relationship of Total Moisture coa1s according to use was studied. It was de-
and Calorific Value cid~
ed that this was impractical because many
coa1s can be used for various purposes and the
0 Coals with Gross Calorific Value tYPe of equipment in which the coal is used
Less Than 10,260 Btu/Lb probabfy is as significant as the kind of coal. On
Coals with Gross Calorific Value the other hand, the caking and coking tests give
Greater Than 10,260 Btu/Lb genieral information on the characteristics of
coa 1s so they should prove of value in consider-
13,000 ing a coal for a specific use.
I]
-I
3 12,000 INTERNATIONAL CLASSIFICATION
m' OF AMERICAN BITUMINOUS COALS
ai 11,000
9?
LL As little information is available on the cok-
10,000 ing properties of American coals by the Gray-
V)
King coke-type test or the Audibekt-Arnu di-
2.-
V) 9,obo
latameter test, tests were made on samples of
0
8,000 bituminous coal of varous ranks from nearly
ai every coal-producing state. About 80 coals
7,000 were tested.2 They were selected to obtain good
> geographic representation of seams that con-
0
5 6,000 tain large reserves, are being mined in quan-
b
3- 5,000 tity, or are entering the export market. The
Audibert-Arnu dilatometer test was selected
5
V)

4,000 for the coking test. Of the 62 code numbers


shown in Table XXXVI, American coals occur
3,000 in 26.
0 10 20 30 40 50 60 70
OO
/ Total Moisture, Ash-Free Table IV in the front of this appendix shows
the analytical data and the classification of each
coal by the ASTM and international systems.

lnlernallonal
~lrs~Lcatlon. 0 1 2 3 4 5 6 7 8 8
C l w Number
1 ' " ' " " I " " ' " ' 1 1 1 " "' " " " " 1 ' " ' " " I "
10 15 25 13AWValue Paramdsr#
12,000
Volallls-Maner Paramelary 20 14W0 calwinc ''.OW lo'?
, , I t , I l l , , I I I I I I I , 1 1 1 1 1 1 1 1 1 1 1 1 1 1 ,
!''"Anlhracllc
I , , 1 1 1 1 1 1 1 1 I,-

ASTM H1gh-~la'ile H1gbVO1allleCBi'uminws


ClastlLclllon~ Semlanthraclle Lo~.VoIallIa MedIum.Volltik Hlgh-VoB1IIeA Coa~andsubbi~uminousA Subbllumlnour B
Bllumlnous Coal B~lum~nousColl Blluminour Coal 81tumlnous Coal
Grwp Name ",:' Coal Coal

y Parameters In lnlernallonal System Are an AsbFrea Bans. IN ASTM SyslamThey I r a on Mlneral.Mancr.Frae Basis.
No Upper Llmll 01 Calorlllc Value lor Clara 6 and High-Voiat~leAB~lum~nous~oalr

Fig. 11 Comparison of classnumbers and boundary lines of InternationalSystem for Hard Coals with group
names and boundary lines of ASTM System
COMBUSTION
Coals of the World

Symbols used in the table for the rank of coal low-volatile and the better grades of- high-
according to the ASTM system are: volatile bituminous coals. All coals of these
Lvb =low-volatile bituminous, classes that were tested have code numbers of
Mvb =medium-volatile bituminous, either 435 or 535.
Hvab=high-volatile A bituminous,
Class 6. This class includes most of the high-
Hvbb =high-volatile B bituminous,
volatile A bituminous coals. Many of these
Hvcb =high-volatile C bituminous.
coals can be carbonized without blending
Based on this data, American bituminous to produce well-fused, medium- to coarse-
coals are classified in the international system grained, though somewhat fingery coke. Usu-
for hard coals as: ally they areblended with 10 to 30 percent of
Class 0. Although no code number is indicated low-volatile bituminous coal to improve the
in the system for coal of this class, coals clas- yield, size, structure, and strength of the coke.
s i s i d in the U.S.as meta-anthracite would have Code numbers of coals tested in this class are
a code number of 000, as these coals we non- 635,634,633,623,and 622.
caking and noncoking. The only known depo-
sit of meta-anthracites is in Rhode Island. Class 7. This class includes coals classified in
Class 1. This class includes most of the anthra- the ASTM system as high-volatile B bitumi-
cites found in the United States, of which nous coals. If carbonized alone they usually
Pennsylvania has the most abundant reserves. produce small, fingery, highly fissured coke
It includes most of the Sullivan County (PA) with low shatter and tumbler indexes. The rela-
coals classified as semianthracites in the tively poor coke structure is typical of cokes
ASTM system. The code numbers of the coals made from high-oxygen coals. If heated rapidly
are 100A and 100B. at high oven temperatures, high-oxygen coals
Class 2. The coals included in class 2 are yield better coke. In American coking practice,
mainly the semianthracites of Arkansas and high-volatile B bituminous coals are always
Virginia. As they are noncaking and noncok- blended with more strongly coking coals. The
ing, their code number is 200. high-volatile B bituminous coals that were
tested have code numbers as follows: 734, 733,
Class 3. This class includes most of the coals 723,721,711, and 823.
classified in the ASTM system as low-volatile
bituminous. In general, these coals are strongly Class 8. This class includes high-volatile C
coking; if coked alone their coke would be well bituminous coals and subbituminous A coals.
fused, blocky, and fine-grained, with few fis- Coals in this class range from noncoking to fair
sures. However, they cannot be carbonized coking. The noncoking coals include all the
alone in commercial slot-type ovens because subbituminous coals and some of the high-
they expand excessively. In American practice, volatile C bituminous coals that are nonslack-
10 to 30 percent of low-volatile bituminous ing on exposure to the weather. Their code
coal is usually blended with high-volatile coal number is 800. The other high-volatile C
to produce blast-furnace coke. The code num- bituminous coals range from virtually noncok-
bers of most of the low-volatile bituminous ing to fair coking. Their cokes range from weak
coals for which data are available are 333 and and pebbly to small, fingery, and highly fis-
334; coals near the borderline of the medium- sured. No American coals in class 8 are coked
volatile group are coded 433 and 434. commercially at present, even in blends with
Classes 4 and 5. These two classes include all more strongly coking coals. The code numbers
coals classified in the ASTM system as of the coals in class 8 that show some caking
medium-volatile bituminous. If coked alone and coking properties are 823,821, and 811.
they form strong, blocky cokes. Their coking Class 9. This class includes subbituminous
properties generally are between those of the coals with a gross calorific value of more than
COMBUSTION
Coals of the World

10,260 Btu on the moist, ash-free basis. The and one from Washington. Coals of this rank
code number of these noncoking coals is 900. also occur in Colorado, Montana, and Oregon.
Table XXXIX shows a moisture range of about
CLASSIFICATION 27 to 34 percent for the samples tested. The
- OF AMERICAN LOW-RANK COALS
coals are placed in classes 11or 1 2 depending
To classify American low-rank coals by the on whether the moisture content is less or more
international system would require informa- than 30 percent.
tion on total-moisture content and yield of tar. Tar yield ranges from 6 to 15 percent, which
Although a standard method for determining groups the coals into 00 and 10. The table
yield of low-temperature tar has not been shows that code numbers for the subbitumi-
adopted internationally, it probably will be nous coals include 1100,1110,1200, and 1210.
based on the Fischer-Schrader method4used in American lignites have an ash-free moisture
many countries. Such a method is used in the content that ranges from about 35 to 45 percent.
Pittsburgh laboratory of the U.S. Bureau of Their class number is 1 2 or 13, depending on
Mines, and a somewhat modified procedure in whether the moisture is less or more than 40
its Denver and Grand Forks laboratories.5 Data percent. Lignites of the Fort Union formation in
on yields of tar from typical American coals by Montana, North Dakota, and South Dakota
the Fischer-Schrader6 and modified method7.8 yield 4 to 9 percent tar, placing them in group
have been published. Although precise infor- 00; code numbers are 1200 and 1300.
mation is not available on correlating the re- Tar yields of the Texas lignites range from 11
sults by the two methods, a statistical study of to 15 percent; their code numbers would be
the relation of the chemical analysis of the either 1210 or 1310, depending on total
coals with tar yields indicates that the yields moisture content.
are similar enough to be used in a survey for The Arkansas lignites gave a tar yield of
applying the international classification sys- about 20 percent; their code numbers are either
tem to American coals. 1320 or 1330, depending on whether the tar
Table XXXIX summarizes the total moisture yield is less or more than 20 percent. Because
and tar yields for 73 low-rank American coals some Arkansas lignites have a total moisture
having calorific values of less than 10,260 Btu/ content of less than 40 percent, these coals will
lb moist and ash free.The data were taken from have a code number of 1220 or 1230 if their
the reports listed in references 6 and 7, un- yields of tar are of the same order as for the
published data, and supplemental information samples tested. High tar yields from Arkansas
obtained from American exchange samples lignites probably are due to their relatively
tested in developing the international classifi- large amount of wax and resin.?
cation system. Included in the table are the
WORLD CLASSIFICATION
international code numbers of the coals based
OF LOW-RANK COALS
on the total moisture and the tar yields.
The subbituminous B coals for which data on Early in its study the Classification Working
both moisture and tar are available have a Party found little available information regard-
moisture content ranging from 22 to 27 percent. ing the different types of brown coals and
The class number therefore is 11.The tar yield lignites occurring in the various countries.
is about 7 to 11percent, which places the coals Therefore, an extensive exchange of samples
in groups 00 or 10. The coals with less than was arranged by the laboratories cooperating in
10-percent tar yield have a code number of the international classification work. Accord-
1100; those with 10 percent or more are num- ing to the plan of the Classification Working
bered 1110. Party, the coals selected were to be freshly
For the subbituminous C coals, data were mined and representative of the various types
available on several samples from Wyoming of brown coals and lignites in each country.
colramnoN
Coals of the World

Table XXXIX. International Code Numbers of American Subbituminous B, C


Coals and Lignites
Number Range of total Range of tar
State of moisture, ash-free yields, dry, ash-free Code No.
samples % %
Subbituminous B
Colorado 2 22.7-25.2 7.4-8.8 1100
1 26.5 11.4 1110
Montana 1 23.7 6.6 1100 I

Utah I 21.7 11.2 1110


Wyoming 2 23.5-26.3
, 2 23.5-26.9
Subbituminous C
Washington 1 30.7 14.8
Wyoming 3 27.4-29.3 6.9-9.0
1 29.7 12.2
2 30.4-34.2 6.3-7.5
1 32.4 12.0
Lignite
Arkansas 1 41.0 19.8
1 41.2 20.5
Montana 1 39.9
5 40.0-42.3
North Dakota 12 36.0-39.9
25 40.0-47.7
South Dakota 1 34.4
1 43.6
Texas

Washington 1

Also, samples of transition coals were re- the moisture in the air-dried samples were de-
quested that would be close to the borderline of termined by either xylene or toluene distilla-
the brown coalllignite class. tion as requested by the Working Party.
Table XXXVIII shows the source of the coals, Total moisture is used rather than moisture-
some of the analytical data obtained by the holding capacity (equilibrium moisture) spec-
Bureau of Mines, and classification of the coals ified in the classification of hard coals. For
according to the ASTM and International sys- practical purposes, moisture-holding capacity
tems. The proximate and ultimate analyses, is equivalent to natural bed moisture for all
calorific value, and moisturelholding capacity ranks of American coals including lignite."
(equilibrium moisture) were determined by However, total moisture and bed moisture are
ASTM methods, except that total moisture and not equivalent for certain European brown
COMBUSTION
Coals of the World

coals of higher total moisture content than


.- American lignites. Fig. 1 2 compares the
moisture-holding capacity with total moisture
for the exchange samples. The figure shows a -
linear relationship between moisture-holding
capacity and total moisture for coals in the
International system with class number 8 to 1 2
and possibly 13; that is, coals having as much
o Class Numbers as 40 percent total moisture. For classes 14 and
8,9,11,and 12 15, the relationship is poor, with moisture-
a Class Number 13 holding capacity averaging 10 to 15 percentage
0 Class Number 14 points lower than total moisture for the coal
. Class Number 15 samples examined.

% Moisture-Holding Capacity, Ash-Free Basis

Ng. 12 Relationship of moisture-holding


capacity and total moisture

REFERENCES J.J. Hoeppner, et. al., "Carbonication Characteristics of


Some North-Central United States Lignites," U.S. Bureau
United Nations Economic Commission for Europe, Inter- of Mines Report of Investigations 5260. Washington: U. S.
national Classification of Hard Coals by Type. Document Government Printing Office, 1956.
No. EIECEl247, EIECEICOALI110. Publication sales no.
1956 I1 E.4. New York: Columbia University Pcess, Inter- W.A. Selvig, et. al., "American Lignites: Geological Oc-
national Documents Service, 1956. currence Petrograpic Composition, and Extractable
Waxes," U.S. Bureau of Mines Bulletin 482. Washington:
W.H. Ode and W.H. Frederic, "The International Systems "'
U. S. Government Printing Office, 1950.
of Hard-Coal Classification and Their Application to
lo W.A. Selvig and W.H. Ode, "Determination of Moisture-
American Coals," U.S. Bureau of Mines Report of Investi-
gations 5435. Washington: U. S. Government Printing Of- Holding Capacity (Bed Moisture) of Coal for Classification
fice, 1958. by Rank, U. S. Bureau of Mines Report of Investigations
4968. Washington: U. S. Gov.1 Printing Office, 1953.
W.H. Ode and F.H. Gibson, "Intefnational System for
Classifying Brown Coals and Lignites and Its Application BIBLIOGRAPHY
to AmericanCoals," U.S. Bureau of Mines Report of Inves- V.F. Parry, "Production, Classification, and Utilization of
tigations 5695. Washington: U. S. Government Printing Western United States Coals," Economic Geology, 45: 515-
Office, 1960. 532,1950.
.I F r a u Fischer and Hans Schrader, "Crude-Tar Determina- W.A. Selvig and F.H. Gibson, "Analyses of Ash From United
tion with an Aluminum Distillating Apparatus," States Coals," U. S. Bureau of Mines Bulletin 567.
Zeitschrift Fuer Angetvandte Chemie, 33 (1): 172-175, Washington: U. S. Government Printing Office, 1956.
1920.
R.F. Abernethy and E.M. Cochrane. "Free-Swelling and
"ohn B. Goodman, et. al., "Low-Temperature Carboniza- Grindability Indexes of United States Coals," U.S. Bureau of
tion Assay of Coal in a Precision Laboratory Apparatus." Mines Information Circular 8025. Washington: U. S. Gov-
U.S. Bureau of Mines Bulletin 530. Washington: U. S. ernment Printing Office, 1961.
Government Printing Office, 1953.
R.F. Abernethy and E.M. Cochrane, "Fusibility of Ash of
6 W.A. Selvig and W.H. Ode, "Low-Temperature Carboni- United States Coals," U. S. Bureau of Mines Information
zation Assays of North American Coals:' U. S. Bureau of Circular7923. Washington:U. S.Gov.PrintingOffice. 1960.
Mines Bulletin 571. Washington: U. S. Government Print-
ing Office, 1957. "Analyses of Tipple and Delivered Samples of Coal;" Re-
ports of Investigations of the Bureau of Mines, U. S. Dept of
'Manuel Gomez and J.B.Goodman, "Distillation Assays of the Interior; comprise analytical data showing composition
Missouri River Basin Coals," U. S. Bureau of mines Report and quality of coal samples collected by the Bureau for
of Investigations 5009. Washington: U. S. Government nearly every year since 1948. U. S. Government Printing Of-
Printing Office. 1953. fice, Washington, D.C.
Appendix B. Determination of Coal-Ash Properties

This appendix supplements the data on prop- quirement of a reasonably accurate knowledge
erties of coal ash included in Chapter 3. Mate- of slag-surface emissivities.
rial properties useful in the design of furnaces THERMAL CONDUCTIVITY
and ash-handling systems are given. Methods The curves of Fig. 3 show thermal conduc-
of calculating fusion temperatures and vis-
tivities as a function of temperature. Separate
cosities of coal ash, as well as further descrip-
curves are given for fused and particulate
tions of these properties are outlined, with
states, because thermal conductivity differs
curves to assist in the determinations.
with the physical structure of the deposit. The
given conductivities are averaged values of
MATERIAL PROPERTIES composite data obtained from Australian,
Soviet, and U.S. investigations.
OF COAL-ASH SLAG DEPOSITS The particulate deposit referred to is a fine,
There are several properties of slag deposits dry powder that forms anuncompacted layer on
that are of use in performing such calculations the metal surface. The outer deposit layers vary
as those of furnace heat-absorption and ash- considerably in character from being porous or
hopper cooling-water flow. sintered to being dense, fused, or molten. The
conductivity, which will vary with the physical
SURFACE EMlSSlVlTY properties of the specific deposit, is expected to
The curves of Figs. 1 and 2 plot surface emis- increase as the deposit density increases and the
sivity of coal-ash slags as a function of tempera- deposit becomes more molten.
ture. Separate curves are given for fused and Heat transfer through a coal-ash deposit to
particulate states because emissivity differs waterwalls is calculatedby a conduction model;
with the deposit structure. Such emissivities this requires that the thermal conductivity of the
are averaged values of composite data from deposits be known.
Australian, Soviet, and U.S. investigations. SPECIFIC HEAT AT CONSTANT PRESSURE
Heat transfer from the flame to the surrounding Vargaftik and Oleschuckl have measured the
surfaces in utility furnaces is predominantly by specific heat of coal-ash slags at constant pres-
radiation. It follows that meaningful heat- sure with a reference temperature of 60F.
transfer calculations should include the re- Table I lists these specific heat values.

0.9-

9.
2
.-
-2 0.8 -
-I
E
UJ 0.7 -
a
%
'f 0.6 - Vertical Bars Represent 95% Confidence Intervals
v)

0.5 I I I I I I I I I I I
600 1000 1400 1800 2200 2600
Temperature, O F

Fig. 1. Surface emissivity of fused coal-ash deposits


COMBUSTION
Dotermination of CoaCAsh Properties

Vertical Bars Represent 95% ConfidenceIntervals

A.

I I I I I I I I
lo00 1400 ? 800 2200 2600
Temperature, " F

I I
Fig. 2. Surface emissivity of particulate coalash deposits

A method for estimating the specific heat of For the temperature range of 20"to 1350C
slag from its chemical composition has been
developed for blast-furnace slags. Because of
the compositional similarity between coal-ash
and blast-furnace slags, the method should be
applicable to coal-ash slags and is described where cp = specific heat (caUgm "C)
below. To perform cool-down, ash-hopper t = temperature ("C)
evaporation, and transient calculations, knowl- H = SiO, + A1,0, + FeO + MgO + MnO
edge of the slag specific heat is required. , 11)
Using a reference temperature of 20C,Vos-
koboinikov2 derived the following empirical For the temperature range of 1350 to 1600C
equations for estimating the specific heat of
blast-furnace slags: .

where cp = specific heat (callgm "C)


t = temperature (C)
2 = SiO, + Alto, + FeO + MgO + MnO
12)

Foerster and Weston3 sho~vedthat their ex-


perimentally measured values for liquid and
solid slags agreed well with the calculated val-
ues from Voskoboinikov's equation. Experi-
mental values for liquid and solid slags were
500 1000 1500 2000 2500
Temperature," F slightly higher than the calculated'valu6s.
The densities of various forms of coal-ash
Fig. 3. Thermal conductivity of fused and slag deposits were averaged from several inves-
, particulate coal-ash deposits tigations and are as listed in Table 11.
- COMBUSTION
Determinatloa of Coal-Ash Properties

SURFACE TENSION absorbed by deposit-laden waterwall titbes,


Surface-tension forces are involved in many while the emissivity of ash deposits determines
important stages of the slag-deposition pro- how much heat will be reradiated by the tubes.
cess;such as ash fusion, slag adhesion, and slag The emissivity and absorptivity of ash deposits
flow. he methods of estimating surface ten- are a function of the wavelengths of the ab-
sion of oxide systems have been developed in sorbed and emitted radiation, the surface tem-
the ceramic and glass industry; they should be perature of the deposits, the physical state of
applicable to some extent to coal-ash slags the deposits, and the properties of the coals
because of the similarity in their chemical from which the deposits originated.
compositions. Surface tension of liquid slags THEORY
can be estimated according to the following
procedure: In Eq. 4, the rate of radiative beat transfer
from a flame to a unit area of deposit-laden wa-
1. Surface tension of liquid slags at 1400C in
air can be approximated from the chemical
composition using the foltowing equation de- Eble I.Specific Heat .
veloped by L y ~ n . ~ at Constant Pressure (Ref. 1)
Temperature ("F) Cp(BtullbO F )
y = 3.24 SiOz+ 5.85 A l t o 3 - 4.4 Fe20S+ 4.92 CaO
+ 5.49 MgO + 1.12 NatO - 0.75 KtO
where y = surface tension of slag (dynelcm) 2190
(3) 2370

2730 0.300
2. To estimate surface tension of slags at
2910 0.303
different temperatures, a temperature coeffi- 3090 0.310
cient of -0.017 dynelcm "C is recommended by
Parmelee and Harman.s Table 11. Density
3. To estimate surface tension of slags in dif- of Various Coal-Ash Slag Deposits
ferent atmospheres, Table I11 has been derived
from data by Parikh.6 Deposit Fonn Density (lblff
In general, surface tension of slags does not Liquid Slag 150-180
vary greatly and is within the range of 300 to Dense, Solid Slag 140-170
400 dynelcm at 1400C in air. A lower slag Solid Ash 120-160
surface tension will usually lead to more rapid Loose, Powder Ash 15-35
fusion and flow properties, and better wetting Fine, Ground Slag 60-90
characteristics. Good wetting is a necessary, but
not sufficient, condition for stronger adhesive Table 111. Surface Tension of Slags
properties. in Different Atmospheres
Reduction in Surface Tension (%)
RADIATIVE PROPERTIES Atmosphere (Based on Nitrogen Atmosphere)

OF ASH DEPOSITS Nitrogen 0


Hydrogen 1
Radiative heat-transfer properties of ash de- Air 3
posits are important in determining heat trans- Carbon Dioxide 7
fer to lower-furnace waterwall tubes when Sulfur Dioxide 27
burning coal. The absorptivity of ash deposits Water Vapor 35
plays an important role in determining the heat
COYIlUSTION
Uetormi~tionof Coal-Ash Properties

terwall tube (qlA) depends upon the overall where a T,4is introduced using Planck's law.
emissivity ( E ) and overall absorptivity (a)of the The overall deposit absorptivity (a) depends
deposit, the flame temperature (TI) and the de- upon the monochromatic absorptivity (a,) at
posit surface temperature (T,). This heat is surface temperature (TJ and the distribution of
conducted through the ash deposit of thickness monochromatic intensities of incident radia-
k having a temperature drop ATash and a tion (IA):
thermal conductivity, k, and transferred to
water flowing through the tubes. This simpli-
fied energy balance on a unit area of tube (Fig.
4) can be written as:

Net Conduction -
-

energy trans- = Coal flame - Deposit = though


radiation emission where I, is dependent on W,,, the monochroma-
fer to water deposit tic blackbody emission per unit area at flame
temperature (T,) and the monochromatic emis-
sivity (E,,):

where u is the Stefan-Boltzmann constant and


is the flame emissivity. It should be noted
that the above relationship is simplified and
Employing Planck's law and the assumption

-
does not consider the view factor from the
flame to the wall, nor wall reflection,, that a coal flame is nearly black at all wave-
As in Eq. 5 the overall deposit emissivity (E) lengths (that is, ef, 1) gives
depends upon the monochromatic emissivity
(EA) at surface temperature (T,) and the .fm WfAd~
f f ~

monochromatic blackbody emission per unit a=


a Tf
area (W,,) at surface temperature (T,): (8)

When the radiation from the flame is in


steady state with the surface, Kirchoff's law
(EA= aA) applies and Eq. 8 can be written as:

Convection to Water

From Eqs. 5 and 9, it is seen that both the


overall emissivity and absorptivity depend
upon the deposit surface temperature and the
monochromatic emissivities; absorptivity is
also dependent upon flame temperature. From
these equations, it can also be deduced that the
overall absorptivity can differ significantly
from the overall emissivity, particularly if the
monochromatic emissivities vary significantly
Fig. 4. Section of lower-furnace waterwall depicting with wavelength and the flame temperature is
heat-transfer mechanism through coal-ash deposit significantly different from the deposit surface
COMBUSTION
Determhatlon of Coal-AshProperties

temperature. Thus, experimental measurement coal ashes. This tendency is expected on the
of only the overall emissivity can result in a basis of chemical composition; that is, mate-
significant error i n prediction of absorptivity. rials composed mainly of oxides of iron, mag-
The experimental determination of the emis- nesium, and silicon tend to be better emitters
sivity and absorptivity of coal ash deposits and absorbers than those containing high
involves a fair amount of procedural and in- sodium or c a l c i ~ m . ~
strumentational complexity. Early investiga- As the physical state of the deposit tends
tions in this field by Agababov,' Becker8 and toward a molten condition, emissivity and ab-
Mulcahy, Boow and Goard9 assumed that de- sorptivity approach 1.0, and differences be-
posits were "gray bodies." This assumption tween Eastern and Western coals would be
says that the spectral emissivities and ab- expected to become less significant. The data
sorptivities E A and ah did not vary with also indicate that molten deposits have higher
wavelength, A, and were equivalent to the over- emissivities and absorptivities than powdery
all emissivity and absorptivity (&anda)respec- deposits. It can be generalized that the emissiv-
tively. Hehce, they measured either overall ity of the ash deposit of a given physical state
emissivity or absorptivity. Later investigations decreases with increasing surface temperature
'
, by Khrustalev et al.1 and Smith, Glicksmanfl throughout a wide temperature range.
proved the "gray body" assumption wrong and
employed spectral scans to determine EA. Over-
all emissivities and absorptivities of ash de- METHODS OF ESTIMATING
posits were calculated by integrating their ASH-FUSIBILITY
respective spectral emissivities and their
absorptivities.
TEMPERATURES
C-E has developed a laboratory technique Many investigators have attempted to calcu-
employing such spectral spans, and a computa- late characteristic fusion temperatures of coal
tional procedure, to determine the emissivities ash from its chemical composition. Most of the
and absorptivities of furnace ash deposits.12 methods require assumptions that tend to
Table IV summarizes ash-deposit emissivity over-simplify the composition of the ash. Also,
and absorptivity results. Here deposits are a common inadequacy among many of the rela-
categorized by physical state (initial deposit, tions is that their validity is usually limited to a
inner layer, and outer deposit), as well as by certain range of coal-ash compositions. The
parent coal source (Eastern and Western U.S.). methods described in this section are those that
On the basis of the limited data, it appears can be applied to a relatively wide range o f .
that for initial deposits and inner layers, West- coal-ash compositions. The references should
ern coal-ash emissivities and absorptivities be consulted for further information on the ac-
tend to be significantly below those of Eastern curacy and applicability of the correlations..

Table IV. A Summary of Emissivities and Absorptivities of Ash Deposits


Physical state Parent Coal Region Emissivity Absorptivity

Initial deposit Eastern U.S. 0.75-0.76 0.71-0.76


Initial deposit Western U.S. 0.37-0.56 0.52-0.61
Inner layer Eastern U.S. 0.79-0.93 0.67-0.84
Inner layer Western U.S. 0.68 0.62
Outer deposit Western U.S. 0.66-0.87 0.62-0.82
Molten inner layer Western U.S. 0.90 0.91
COMBUSTION,
Determinationof Coal-Ash Properties

I OO
/ CaO + MgO Content

Fig. 5. Hemisphericaltemperature of coal-ash free of FeaOj, NazO, andKzO

It is very unlikely that calculation of ash-


softening temperatures will replace the deter- SiO, + A1O3 + Ti0, + FeO3 + CaO + MgO +
mination. Nevertheless, using correlations of NaZO + K O = 100%
this type permits conclusions to be drawn as to (11)
the relative influence of each component on the 5. Correct for the presence of NazO and K 2 0 in
ash-softening temperature and the probable ef- the ash by reducing the estimated hemispheri-
fect of addition of reagents. cal temperature by 25OC (45OF)for each percent
METHOD OF DUTTA, RAI, AND of Na20 + K 2 0 present.
CHAKRAVORTY13 6. Additional corrections for the presence of
Assuming the British Standard experimental F e 2 0 3in the ash are given in the references.
conditions, this method is used to estimate the METHOD OF GAUGERl4
hemispherical temperature in either a reducing
or oxidizing atmosphere. It is based on ash from This method, which assumes ASTM Stan-
Indian coals and synthetic ash mixtures. The dards experimental conditions, is used to esti-
procedure is as follows: mate the softening temperatures'in a reducing
atmosphere of ash from Eastern U.S. coals. The
1. Calculate the ~ i 0 ~ / ( +~Ti02)
1 ~ ratio.
0 ~ procedure is as follows:
2. Obtain the percentage of CaO + MgO based 1. Calculate S, A, and T, which are defined as:
on

SiO, + A120, + TiO, + CaO + MgO = 100% (12)

A =
3. From Fig. 5, estimate the hemispherical (13)
temperature of the coal ash free. -of Fe203,Na20, -
and K20.
T = CaO + 0.7 MgO + 2.25 NapO + 1.5 KO
4. Obtain the percentage of Fe203 and (14)
N a P + K20ba&d on the following equation
COMBUSEN
Determination of Coal-Ash Propsfties

Fig. 6 Softening temperature of coal ash free of iron oxide, degrees Fahrenheit

i: Obtain the percents S, A, and T, which are


expressed as:

5. From Fig. 7, estimate the lowering of the


softening temperature due to the preselice of
Fe20,; this will give the softening temperature
of the ash.
METHOD OF SCHAEFERIS
This method, which assumes ASTM Stan-
dards experimental conditions, is used to esti-
mate the softening temperature in a reducing
atmosphere of ash from Eastern U.S. Coals. The
procedure is as follows:
I. Calculate R,, which is expressed as:
3 . From Fig. 6 , estimate the softening tempera-
ture of the coal ash free of iron oxide, using the A1203 SiO? + A1.03
above designated percentages. R,=-
SiO? FeO + 0.6 (CaO + MgO + Na,O + K20)
4. Define I = Fez03andcalculate the percent I,
which is expressed as:
.-
Dcterml~tlonof Coal-Ash Properties

Fig. 7. Lowering of the softening temperature from iron oxide

'-, 1000
Percent lron

B
-
0
2

p-
8 0 0 ~ 10 20 30 40 50 10 20 30 40 50 10 20 30 40 50 10 20 30 40 50
Percent lron

k o ; h - 2 4 0 0 2300 and Lower


0" 400
-u
6 0 0 ~ 10 20 30 40 50
10 20 30 40 50
Percent lron
I I

3000- 2. Using the value for R,, estimate the soften-


ing temperature of the coal ash from Fig. 8.
2900-
METHOD OF ESTEP, SELTZ, BUNKER,
AND STRICKLER16; AND ESTEP, SELTZ,
AND OSBORN17
This method, which assumes ASTM Stan-
dards experimental conditions, is used to esti-
mate the hemispherical temperatures in a
reducing atmosphere of ash from Eastern U.S.
coals and synthetic ash mixtures. If the coal-
ash composition contains mainly SiOn,A1203,
Fe203,and CaO, then the hemispherical tem-
perature of the ash can be estimated according
to the following procedure:
1. Obtain the percentage of CaO based on:

S i 0 2 + A12 + 0, + Fe,O, + CaO = 100/~


(20)
2000 I I I I I
1 3 5 7 9 1 1
Rs ,
2 . Typical ternary diagrams are given in Figs. 9
Fig. 8. Softeningtemperature of coal ash and 10, which are to be used for calcium-oxide
as a function of R, contents up to 8.5 percent.
- COMBUSTION
Determination of CoaCAsh Properties

Fig. 9. Softening temperature isotherms P F ) at CaO = 0-2.5%


I - 1
CompleteTernary Showing
Section Actually Plotted
SiOz ..

Complete Ternary Showing


Section Actually Plotted
SiOz

L I
Fig. 10. Softening temperature isothermsP F ) at CaO = 7.6-8.5%
CO~OSnON
htumlmtion of Coal-AshProperties

3. Locate the corresponding composition point t 2 = 1094 + 42.5 KIM


inside the Si02-A1203-Fe203 diagram which is
based on the following equation
.-
124)
-,
tB= 1139 + 48.6 K,,,
(25)
SiO? + + Fe2Os = 100%
(211 where
t2 = softening temperature ('C)
This gives the estimated hemispherical
t3 = temperature of beginning of liquid
temperature of the coal ash.
fused state ("C).
For ashes with CaO content above 8.5 per-
cent, diagrams showing vertical planes This relation is claimed to be valid for the fol-
through the prism are presented which give lowingrange of Kfu:
~ l o t s - fc a d versus F & O ~at constant Gos/ For t,: 1.8 5 K,,, 5 9 . 9
X1203ratios. For t . , : 1 . 8 < K , , , < 7 . 5
For ashes with substantial amounts of MgO METHOD OF MAJUMDAR, BANERJEE,
or NazO,the following correctibns apply: AND LAHIRI
1. The fluxing effect of MgO is identical to that This method, which assumes British Stan-
of CaO up to 10 percent MgO; therefore, CaO + dard experimental conditions, is used to
MgO can be considered as a single variable. estimate the hemispherical temperature in a
2. The presence of Na20 should be corrected reducing atmosphere of ash from Indian coals.
by reducing the estimated hemispherical The procedure is as follows:
temperature by 50F for each percentage of 1. Calculate R,,,:
NasO based on: '
+ 1.96 Al10,)/(2.5Fe,O, +
R,,, = (3.3 SiO,
SiOP + Al2O3 + Fe203 + CaO + MgO + 3.57 CaO + 5.0 MgO + 3.22 Na,O + 3.22 K1O)
NasO = 100% (26)
(22)

METHOD OF KOVITSKII, KARAGODINA,


AND MARTYNOVAt8
This method, which assumes Soviet Stan-
dard experimental conditions, is used to esti-
mate the softening temperature (t2) and the
temperature of the beginning fused state (td in
a reducing atmosphere, of ash from Russian
coals. The procedure is as follows:
1; Calculate Kfuwhich is expressed as:

2. Estimate the softening temperature and the


temperature of the beginning of liquid fused Fig. 11. Hemisphericaltemperature of
state from the following relations: coal ash as a function of R ,
COMBUSTION
Determination of Coal-Ash Properties

2. From Fig. 11, estimate the hemispherical VISCOSITY OF COAL-ASH SLAGS


temperature of the coal ash. IN THE COMPLETE LIQUID PHASE
This relationship was independently tested The viscosity of coal-ash slag in the complete -
on 75 ashes from U.S. coals. The difference be- liquid phase can be measured or estimated at
tween the corresponding estimated and mea- any temperature above its crystallization tem-
sured values is as follows: perature. Above this temperature range, slag
1. In 66.6 percent of the cases the estimated viscosity is mainly a function of temperature
value is within +-100Fof the measured value. and chemical composition. Actual measure-
2. The average difference between the two cor- ment of slag viscosity is usually .expensive
responding values is +84"F. and difficult; therefore, several methods of
The original report describing this relation is estimating slag viscosity from the composi-
not available. The curve in Fig. 11was derived tion-temperature relationships have been de-
from calculations carried out on ashes from veloped. This method should be used only
Eastern and Western U.S. coals. The original when the slag temperature is above the crystal-
relation was said to be based on molecular per- lization temperature, referred to asthe tempera-
centages and not on ~veightpercentages. How- ture of critical viscosity.
ever, the independent tests indicated that the METHOD BY REID AND COHENls
divergence of the estimated values from the
corresponding measured values was much The viscosity of coal-ash slags from Eastern
smaller when weight percentages were used. U.S. coals in the complete liquid phase can be
estimatedaccording to thefollowing procedure:
1. Calculate the silica percentage,
ASH COMPOSITION
AND VISCOSITY-TEMPERATURE
RELATIONSHIPS , SP = ( SiO. + Equiv.100FeQ3SiO,
X
+ CaO + M a 0
As early as the 1930's, the Bureau of Mines
and others conducted studies to measure the
flow characteristics of molten ash in wet- 2. Read the viscosity at a given temperature, or
bottom furnaces; a method for relating ash the temperature at a given viscosity, from the
composition to viscosity of the molten ash was experimentally derived nomogram shown in
developed. By placing the ash composition Fig. 12. Scale C on the nomogram shows -a
data into such specific arrangements as equiva- direct relationship between SP and the liquid
lent ferric oxide, silica equivalent, and calcium viscosity at 2600F. To find viscosity and any
oxide percentage, and by developing a series of other temperature: (a)connect the 2600F point
curves based on relationships of laboratory on scale A with the desired SP or viscosity on
viscosity to ash composition, viscosity-tem- scale C; (b) note the pivot point on line B and (c)
perature relationships can be established. draw a line through the desired temperature on
These viscosity-temperature relationships scale A, through the pivot point, to obtain vis-
permit the construction of viscosity curves of cosity on scale C.
the ash in both the fluid and plastic states. Al-
though definite predictions are difficult to METHOD OF HOY, ROBERTS, AND WILKINSZO
make from the viscosity curves alone, such
plots are particularly useful for predicting the The viscosity of coal-ash slags from British
slag characteristics of specific coals by com- coals in the complete liquid phase can be esti-
paring the viscosity-temperature relationships mated according to the following procedure:
with coals of known performance. 1. Calculate the silica percentage,
conusno# ,
DetermimUm of Coal-Ash Properties

METHOD OF WATT AND FEREDAY2I


100 x SiO, The viscosity of coal-ash slags from British
SP = ( SiO, + Equiv. F e Q 3 + CaO + MgO ) coals in the complete liquid phase can be esti-
(28) mated according to the following procedure:
1. Normalize the chemical composition of the
2. Estimate the slag viscosity from the follow- ash such that:
ing equation:
Si02 + A I D 3 + Equiv. FeQ3 + CaO + MgO = 100%
(SP1100)2+ 1.265 (1041T)- 7.44
= 4.468 (301
logloq
where 77 = slag viscosity (poise)
T = temperature (OK) 2. Calculate M, defined as:

M = 0.00i335Sio2 + 0.00601A1Q3 - 0.109


The Hoy, Roberts, Wilkins relationship was (31)
based on the following range of coal-ash chem-
ical composition: 3. Calculate C, defined as:

Si02
A103
Equiv. F e O 3
CaO
MgO
Na20 + K a 4. Estimate the slag viscosity from the follow-
SP ing equation:
SiO2/A1P3

where 77 = Slag viscosity (poise)


T = temperature ("C)
(33)

The Watt-Fereday relationship was based on


the following range of coal-ash chemical
composition:

SiO,
A1203
Equiv. F e D 3
CaO
MgO
NaQ + KQ
SP
SiO$A1Q3

II I
I
FLOW
-. TEMPERATURE

Fig. 72 Nomogram for estimation of The flow temperature is defined as the tem-
coal-ash slag viscosity. See also reference 19. perature at which slag has sufficient fluidity to
COMBUSTION
DetermlnaNon of Coal-Ash Properties

allow free flow without difficulty. Normally Generally, for wet-bottom furnaces, Tzso
the flow temperature corresponds to a slag vis- should not exceed 2600F. For dry-bottom
cosity of approximately 80 poise. For coal-ash units, high values of Tzso.arerecommended for
slags of known chemical composition, the flow easier removal (sootblowing) of waterwall
temperature can be calculated by letting r) = 80 deposits.
poise and obtaining the corresponding T,, When estimating slag viscosity in the com-
value. It is used to predict the ease of slag re- plete liquid phase, the existence of the crystal-
moval in wet-bottom furnaces. It also can be lization temperature should be considered. T,,
used to estimate the maximum steady-state which is referred to as the temperature of criti-
thickness of furnace-wall deposits, because no cal viscosity, is found as follows:
accumulation of slag is expected beyond this If Tgs, > T,, then s!ag-removal temperature = T,,,
point. If TZSO< Tm,then slag-removal temperature = T,,
When estimating slag viscosity in the com-
Method of Sage and Mcllroy22
plete liquid phase, one should consider the
existence of the crystallization temperature, The Tzjo value for slags from Eastern U.S.
which is referred to as the temperature of criti- coals can be estimated from the curves in Fig.
cal viscosity (T,). The relation between Tgoand 13. The method is said to be valid for bitu-
T,, is as follows: minous-type ash and for lignitic ash with
If T,, > T,,, then flolv temperature = T,o acidic content over 60 percent.
If T,, < T,,, then flow temperature = T,,
Method of DuzyZ3
Prior to the development of the viscometer,
the flow temperature was determined manu- The TZ50value for slags from Western coals
ally by stirring the liquid slag with a platinum can be estimated from Fig. 14. The method is
rod. This stirring helped establish a standard said to be valid for lignitic ash having an acidic
"feel" for the flow temperature. An empirical content under 60 percent.
relation was then developed between the flow TEMPERATURE OF NORMAL SLAG REMOVAL
temperature of coal-ash slags and the ASTM
ash-fluid temperature (FT). For a coal-ash slag The temperature of normal slag removal, t,,,
with a ferric content of about 10 percent, an ap- is defined as the recommended temperature for
proximate relation is expressed as: easy slag-tapping from a furnace. Usually, it
corresponds to a slag viscosity of 200 poise.
This concept has been widely used in Russia
-
Flow temperature ( O F ) = 1.2 (FT 470) and is identical, in prineiple, to the U.S. criter-
(34)
ion of the slag removal temperature. For coal-
ash slags of known chemical composition, the
SLAG-REMOVAL TEMPERATURE . temperature of normal slag removal can be cal-
The slag-removal temperature is the temper- culated from the relations described above by
ature corresponding to the maximum viscosity letting 7 = 200 and obtaining the correspond-
at which slag can be tapped from a furnace. ing TZOO value. Alternatively, it can be esti-
This upper limit for fluidity of slag is approxi- mated by the follotving method.
mately 250 poise. For coal-ash slags of known When estimating slag viscosity in the com-
chemical composition, the slag-removal tem- plete liquid phase, the existence of the crystal-
perature can be calculated from the relations lization temperature should be considered.
described above, by letting r) = 250 poise and The relationship between TZo0and T,,, the
obtaining the corresponding TZj0value. Tzjo temperature of critical viscosity, is as follows:
can also be estimated from the two graphical If TZW> T, then T, = Tzo0
methods described later. If Tzoo< T , then T,, = T,
COXBUSTION
Detenninwiionof Coai-Ash Properties

'20ooO - I I I I
0.2 0.4 0.6 0.8 1.0
Base/Acid - Fe203 + GaO + MgO + Na2O + K20
Ratio Si02 + A1203 + Ti02

Fig. 13 Estimation of T250 value according


to baselacid ratio (Ref. 22) % Base
According to the method developed by
Kovitskii, Karagodina, and Martynova,18the T200
value for coal-ash slags from Russian coals can
be estimated by the following procedure: Fig. 14 Estimation of 7250 value according
to dolomite percentage and percent base
1. Calculate K, which is expressed as (Ref. 23)

SiO, + Pa, EFFECT OF EQUIVALENT Fez03


I
K, = A 1 a 3 + Fe2O3+ CaO + M g O AND FERRIC PERCENTAGE
It has been observed that coal-ash slag vis-
cosity in the complete liquid phase can differ
2. Estimate the TZo0
value from the following between reducing and oxidizing atmospheric
equation conditions. This difference implies the effect of
variation in ferric percentage. However, the
difference in viscosity is usually small.
Nicholls and Reidz4initially observed that the
entire slag-viscosity profile was raised as the
This relation is claimed to be valid for the fol- ferric percentage decreased. Sage and M ~ I l r o y ~ ~
lowing chemical composition range (with K, indicated the opposite; that is, the viscosity
between 0.42 and 2.03): profile was lowered as ferric percentage de-
creased. In either case, the effect of ferric per-
centage on slag viscosity in the complete liquid
SiO, 20.9-63.1% phase seems to be small and can usually be ne-
14.1-29.0% glected. Accordingly, the original Fe,O,content
Fez03 3.2-36.3%
CaO 1.2-27.3% of the ash can be substituted for the-equivalent
MgO 0.8-7.6% Fe20, when estimating slag viscosities accord-
pzos 0.1-2.9% ing to the methods described above.
To obtain results which reflect actual furnace
COMEUSTION
Determination of CoaCAsh Properties

Several methods of estimating T,, from the


chemical composition have been developed
and are described below.
The temperature of critical viscosity, then,
provides the limiting temperature below which
Freezing Temperature slag viscosities cannot be calculated using the
methods described earlier. It also allows the
prediction of the boundary temperature at
which molten slag ceases to flow on furnace
waterwall deposits.
Typical cooling curves for four' different
coal-ash slags are shown in Fig. 16. The expla-
nation of the four curves is as follows:
-1
Curve 1. Represents a true glass which does
not have a distinct crystallization temperature.
Very few coal-ash slags are of this type.
Curve 2. Represents a slag which is close to
glass in behavior. Separation of solids begins
after a long cooling period. T,, is usually very
I , low. Slags of this type are frequently referred to
Temperature as "long" slags.
I I
Curve 3. Represents a slag with a long freezing
Fig. 15. Effect of cooling and reheatingon the range. Separation of solids begins at high
viscosity-temperaturerelation of coal-ash slag temperatures at low rates and freezes to essen-
tially a solid at much lower temperatures. T,,is
conditions more closely, it is suggested that es- usually high.
timations be carried out at a ferric percentage of Curve 4. Represents a slag with rapid crystal-
20 percent. lization and freezing characteristics. T,, can be
either high or low. Slags of this type are fre-
VISCOSITY OF COAL-ASH SLAGS quently referred to as "short" slags.
IN THE PARTIAL-LIQUID
(CRYSTALLIZATION) PHASE METHOD OF SAGE AND MclLROYa2

As coal-ash slags in the complete liquid T,, of coal-ash slags from Eastern U.S. coals
phase are gradually cooled, the logarithm of at a ferric percentage of 20 percent can be esti-
viscosity will increase nearly linearly with mated from the following equation:
decreasing temperature. But at a certain tem-
perature, the viscosity departs from this
approximate straight line and tends to increase
rapidly as temperature decreases. The tempera-
ture at which this almost discontinuous transi-
tion occurs is referred to as the temperature of where HT is the hemispherical temperature of
critical viscosity, T,,, illustrated in Fig. 15. T, coal ash ("F).
is believed to be the temperature at which solid METHOD OF WATTZ1
phases begin to crystallize and separate out
from the liquid and, hence, it can be considered T,, of coal-ash slags from British coals can
as a crystallization temperature. Actual mea- be estimated according to the following
surement of T,, is expensive and difficult. procedure:
COYllUSl3ON
Determination of Coal-Ash Promrties

t Freezing to Solid
o Critical Viscosity
A Freezing Temperature
where t2 is the softening temperature of coal
1 2 3 4 ash according to the Soviet standard ("C).
100,000r
VISCOSITY OF COAL-ASH SLAGS
IN THE SOLID PHASE
As coal-ash slags are cooled beyond the
10,000 -
temperature of critical viscosity, a certain
temperature is reached where the movement of
the slag is completely terminated. The temper-
aa
.g 1,ooo- ature at which this transition occurs, referred to
4- as the freezing temperature, Tm is the point of
E

1 im-
solidification of the slag, as Figs. 15 and 16 il-
lustrate. Only one method of estimation of T,
is available, that by Reid and Cohen19.

10 I I I I COAL-ASH SLAG
1600 1900 22002500 2800
Temperature,O F
DEPOSIT ACCUMULATION
AND STRUCTURE
Molten to semimolten coal-ash slag deposits
Fig. 16. Typical cooling curves for different
types of coalash slag
usually will not form on clean waterwall tubes
since, upon approaching the relatively cooler
1. Normalize the chemical composition of the tube surface, the slag particles become less
ash, such that: adhesive because of rapid cooling in the wall-
adjacent area. Accordingly, coal-ash deposi-
S i 0 2 + A1203+ Equiv. F e 2 0 3+ CaO + MgO = 100% tion is generally considered to be a two-stage
(38) process. A primary layer of deposit first forms
- on the waterwall tube surface. The resulting
2. Estimate T,,.from the following equation: rise in the surrounding surface temperatures
subsequently allows the adherence of rigid
plastic secondary deposits.
T, ("C) = 2990 - 1470
MECHANISM
- 14.7 (Equiv.F e 2 0 3+ CaO + MgO) OF COAL-ASH SLAG DEPOSITION
+ 0.15 (Equiv.F e 2 0 3+ CaO + Mg0)2 The following two types of primary deposits
(39)
are most commonly observed:
METHOD OF MARSHAK AND RYZHAKOV 1. Primary deposits that result from the set-
FOR SOVIET COALS25 tling of the finer fractions (smaller than 30 mi-
The temperature of critical viscosity is re- crons) of flyash. This type of primary deposit is
ferred to as the temperature of the true liquid loose in structure and does not provide strong
state, t, in the Soviet literature. It has been cohesive or adhesive bonds.
shown that tocan be estimated from the follow- 2. Primary deposits that result from the selec-
ing empirical equation: tive deposition of certain reactive components
4
COMBUSTION
Determination of CoaCAsh Properties

of the ash (iron, calcium, or alkalies). These


components can be present in the deposit in TS TCV Tfr TW
high concentrations as oxides andlor sulfur C I I C
compounds, leading to the formation of low-
melting eutectic mixtures. This type of pri-
mary deposit is more dense in structure and
has stronger cohesive and adhesive bonds. Heat Flow
The properties of the primary layer, which *
provides the link between the rigid secondary
deposits and the tubes, have an appreciable in-
fluence on the ease of removal of the deposits
by sootblowing.
During the deposition process, there is a
transitional stage where the plastic secondary Ts: Slag Deposit Surface Temperature
deposits begin to stick on tKe primary layer. TCV: Temperature of Critical Viscosity
These secondary deposits are strengthened by Tfr: FreezingTemperature
time and increasing temperatures. Tw: Tube Surface Temperature
. .

INITIAL SLAGGING TEMPERATURE


Fig. 17. Cross section of a typical
The transition from primary to secondary furnace-wall slag deposit
deposits has been shown to be a function of the
immediate gas temperature outside the de- coal-ash from Soviet (Kansk-Achinsk) coals
posit. The temperature at which the secondary showed the following results:
deposits begin to form has been referred to as 1. ti, corresponds to a temperature of approxi-
the initial slagging temperature, ti, Methods of mately 950C.
estimation of ti,are described below. , 2. ti, is not strongly affected by the local gas
METHOD BY ALEKHNOVICH, BOGOMOLOV, velocity.
NOVITSKII, AND lVANOVAZe
DEPOSIT STRUCTURE AND MAXIMUM
The ti, of a coal-ash deposit from Soviet THICKNESS
(Kuznetsk) coals can be estimated from the
chemical composition of the ash according to Fig. 1 7 shows a cross section of a typical wa-
the following procedure, using constituents on terwall slag deposit that has reached a max-
a weight-fraction (not percentage) basis: imum steady-state thickness. The slag surface
1. Calculate K. temperature, T,can vary depending on furnace
conditions and deposit characteristics. How-
ever, in general, T, should not exceed the flow
K = (Na20 + Ka)2
+ 0.048 (Ca0 + Fe20d2 temperature. From the flow and depositional
(41)
characteristics of coal-ash slags described in
previous sections, it is possible to estimate an
2. Estimate ti, from the following equation: approximate structure profile of slag deposits.
By knowing the heat flow into the deposit from
the furnace flame and +e thermal conductivity
of the slag, it is also possible to calculate the
maximum thickness of a waterwall deposit.
METHOD BY DIK AND SIKHORAZ'
This can give an indication of the degree of
slagging of different coal types and the effect
Experimental investigations on deposits of on heat transfer.
comusm~ '.
hIvmin8Uom of CoaCAsh Properties

REFERENCES 14 A. W. Gauger, Progress During the First T~velveYears of


Cooperative Research on Bituminous Coals. Report from
N. B. Vargaftik and 0. N. Oleschuck, "Thermal Capacity Mineral Industries Exp. Station, Pennsylvania State Col-
of Slags of Various Fuels:' Teploenergetika. 2(4): 13-17, lege. 1951.
1955.
a* R. L. Schaefer, The Relation Between the Chemical Con-
V. G. Voskoboinikov, "The Heat Capacity of Blast-Furnace stituents and the Fusibility of Coal Ash, Ohio State Univ.,
Slags at High Temperatures:' Teoriya Prabtiba Metallur- 1933.
gii. 12 (10): 3-5, 1940
16 T. G. Estep, H. Seltz. H. L. Bunker, Jr., and H. S. Strickler,
'3 E. E Foerster and P. L. Weston, Jr., "Heat Content of Some "The Effect of Mixing Coals on the Ash Fusion Tempera-
Blast-Furnace and Synthetic Slags" U.S. Bureau of Mines ture of the Mixture," Mining and Metallurgical Investiga-
Report of Investigation 6886, Washington: U.S. Bureau of tions, Carnegie Inst. of Technology, Mining and
Mines, 1967. Metallurgical Advisory Boards, Coop. Bulletin 62, 1934.
4 K. C. Lyon. "Calculation of Surface Tension of Glasses:' 17 T. G. Estep, H. Seltz, and W. J. Osborn, "Determination of
Journal of the American Ceramic Society, 27: 186-189, the Effect of Oxides of Sodium, Calcium, and Magnesium
1944. on the Ash Fusion Temperature by the Use of Synthetic
Coal Ash:' Mining and Metallurgical Investigations.
C. W. Pdrmelee and C.. G. Harman, "Effect of Alumina on Camegie Institute of Technology, Mining and Metallurgi-
Surface Tension of Molten Glass:' Journal the Ameri-
a n Ceramic Society, 20: 224-230,1937.
05 cal Advisory Boards, Cooperative Bulletin 74, 1937.
19 N. V. Kovitskii, N. V. Karagodina, and M. I. Martynova.
6 N. M. Parikh, "Effect of Atmosphere on Surface Tension' "Investigation of the Influence of the Chemical Composi-
of Glass:' J. Amer. Ceramic Society, 41: 18-22, 1958. tion of the Ash of Power Coals in Its Fusibility and Viscos-
ity:' Solid Fuel Chemistry (Translation of Khimipa
S. G. Agabobov, "Emissivity of Boiler Furnace Slag:' Tep- Tverdogo Topliva), 9(3): 59-63,1975.
loenergetika, 8, 1958, pp. 56-60.
19 W. T. Reid and P. Cohen, "The Flow Characteristics of .
8 H. Becker, "The Effect of Ash Fouling on Heat Transfer to Coal-Ash Slags in the Solidification Range:' Transactions
Boiler Tubes, Part 2: Thermal Properties of Particulate of the ASME, 66, Furnace Performance Factors: ,83-97,
Brown Coal Ash," Report No. 252, State Electricity Com- 1944.
mission of Victoria-Scientific Division, Australia, 1972.
a H. R. Hoy, A. G. Roberts, and D. M. Wilkins, "Behavior of
9 M. F. R. Mulcahy, J. Boow, and P. R. C. Goard, "Fireside Mineral Matter in Slagging Gasification Processes," Insti-
Deposits and Their Effect on Heat Transfer in a Pulver- tution of Gas Engineers, Journal, 5(6): 444-469, 1965.
ized-Fuel-Fired Boiler, Part I: The Radiant Emittance and
Effective Thermal Conductance of the Deposits:' Institute 21 J. D. Watt and F. Fereday, "The Flow Properties of Slags
ofFuel Journal, 1966, pp. 385-394. Formed from the Ashes of British Coals: Part I. Viscosity
of Homogeneous Liquid Slags in Relation to Slag Compo-
10 B. A. Khrustalev, "Spectral Radiation Properties of Some sition:' Journal of the Institute of Fuel, 42(338): 99-103.
Materials at High Temperatures and Their Influence on March 1969.
the Integral Absorption and Radiation Properties," Heat
Msfer-Soviet Research, 5, (2) Mar-Apr 1973,pp. 60-64. 22 W. L. Sage and J. B. McIlroy, "Relationship of Coal Ash
B. A. Khrustalev and A. M. Rakov, "Methods of Deter- Viscosity to Chemical Composition," Combustion, 31(5):
mining the Integral and Spectral Radiative Properties of 41-48, November 1959.
Materials at High Temperatures:' Heat Transfer-Soviet 23 A.F. DUZY,"Fusibility-Viscosity of Lignite-Type Ash."
Research, 1, (4),Jul 1969, pp. 163-177. ASME Paper no. 65-WAIFU-7.New York: American Soci-
R. A. Smith and L. R. Glicksman, "Radiation Properties ety of Mechanical Engineers, 1965.
of Slag:' Report No. DSR-70332-61, MIT, Feb 1969. .r P. Nicholls and W. T. Reid, "viscosity of Coal-Ash Slags:'
'2 G. J. Goetz, et al., "Development of a Method for Deter- Transactions ofthe ASME, 63: 141-153, 1940.
mining Emissivities and Absorptives of Coal-Ash Depos- Y.L. Marshak and A. V. Ryzhakov, "Flow of Slag Film
its:' ASME Paper 78-WAIFU-6. New York: American When Affected by Gas Flow," Thermal Engineering
Society of Mechanical Engineers, 1978; also Combustion (Translationof Teploenergetika),16(10):12-16, 1969.
Engineering publication TIS-5890.
~6 A. N. Alekhnovich, V. V. Bogomolov, N. V. Novitskii, and
13 B. K. Dutta, B. Rai, and K. R. Chakravorty, "Fusion Char- N.I. Ivanova, "A Study of the Slagging Properties of
acterization of Coal Ashes; Softening Temperature of Coal Kuznetsk Coal Ash:' Soviet Power Engineering (Transla-
Ashes in Oxidizing Atmosphere:' Journal of Scientific tion of Elektricheskie Stantsii), 6: 509-513, September
and Industrial Research, 19B: 206-212,1960. 1977.
B. K. Dutta, et al, "Study of the ~ u s i o ~ ~ h a r a c t e ~ i soft i c s
Coal Ashes: Softening Temperature of Coal Ashes in Mild 27 E. P.Dik, and R. A. Sikhora, "Study of the Conditions of
Reducing Atmosphere:' Journal of Scientific and Indus- Formation of Ash Deposits When Burning Nazarova
trial Research, 21D (2): 44-48, February 1962. Coal;' Thermal Engineering (Translation of Teplo-
energetika), 16(10):23-27, 1969.
Appendix C. Combustion Calculations by Graphical Methods

Besides presenting a unique method of ac- items are needed for the calculation of gas and
complishing detailed calculations of combus- air quantities. Items five to seven form the basis
tion products of many fuels, this appendix of heat-balance calculations in either the de-
supplements information from Chapter 2 on sign or the testing of a steam-generating unit,
the production, transportation, and physical when theASMEPerformance Test Codes, Short
condition of these fuels as they are received in a Form, is used. The last item, carbon dioxide,
steam-generating facility. Many of these factors and its relationship to excess air, is important
(particularly temperature and water content) in combustion c~lculationsbecause in test
influence the calculation of air and gas work the C02inthe gases is measured and from
weights, as well as the boiler efficiency itself. it the excess air is calculated. The equipment
For the reader's convenience, some of the fuel- designer works with excess air even though he
analysis data of Chapter 2 appear again in this may appear to have based his estimates on the
appendix. The order of presentation parallels percentage of C02.
that of Chapter 2, "Fossil Fuels": first, solid The charts make allowance for all the impor-
fuels; then, liquid fuels; finally, gaseous fuels. tant variables in the analysis. For practical pur-
poses, therefore, they are as accurate as more
iaborious methods of calculation. On the other
THE GENERAL METHOD hand, even in working with a complete ulti-
FOR ALL FUELS mate analysis and calculating the combustion
Combustion calculations by the designer are requirements and products of combustion of
one of the first steps in proportioning a steam each constituent, gross errors may result if, say,
boiler. For example, the gas weight that results the heat value used is not correct for and corre-
from fuel combustion is required to determine spondent to the given analysis.
proper arrangement and extent of heating The method employed here is based on the
surface in furnace, boiler, economizer, and concept that the weight of air required in the
air heater. The gas weight is also necessary combustion of a unit weight of any commercial
for proportioning gas ducts, dust-collection fuel is more nearly proportional to the unit heat
equipment, induced-draft fans, and stacks. Air value than to the unit weight of that fuel. Con-
weight is used to set the size of air heaters, air sequently, the weights of air, dry gas, moisture,
ducts, fuel-burning equipment, and forced- wet gas, etc., are expressed in pounds per mil-
draft fans. lion Btu fired. In the case of solid fuels, it is dif-
This appendix ivill discuss the following ficult to burn 100 percent of the combustible, so
items in detail and will present graphical cal- a correction for solid combustible loss must be
culation methods for each. made.
Before considering in detail the terms found
1. Fuel in products
on the charts and in the sample calculations, a
2. Atmospheric air for combustion quick review of the combustion process of a
3. Effect of unburned combustible fuel is necessary. Take, for example, a fuel with
4. Products of combustion no ash; when this fuel burns cbmpletely, the
5. Moisture in the combustion air weight of the fuel is simply added to the weight
6 . Moisture from fuel of atmospheric air supplied for its combustion
to obtain the wet products of combustion or
7' gas 'Ontent of the products total wet gas. Thus: fuel (F) + air (A) = pro-
8. Carbon dioxide in products ducts (P).But, if some of the fuel is ash, or, if be-
In the method outlined here, the first four cause of incomplete combustion, some of the
CO~USIION
ComburUon&lculaUons by Graphic Methods

fuel does not pass out of the furnace with the of the various combustible constituents may be
gases, then F in the above equation will be less employed. Considerable difference may exist
and both A and P will also be reduced. This between the analysis "as received" and "as
concept of adding F and A to get P is the basis of fired," even though nothing is intentionally
the method. done to the fuel between the time it is received
FUEL IN PRODUCTS, F and the time it is burned. Contrarily, certain
fuels are purposely dried before they are fired
By definition, fuel in products, F, is that por- and others take on moisture hygroscopically or
tion of the fuel fired which reappears in gas- are purposely "tempered." In the storage sys-
eous form in the products of combustion, as tem of pulverized-coal firing, the moisture re-
separate elements or in chemical combination moved from the coal may actually be vented
with other elements. Since with the method of directly to a stack. In the direct-fired system,
this appendix all quantities are to be those re- the moisture, although removed from the coal,
quired for or resulting from firing 1,000,000 is fired with the coal and therefore does not
Btu, F must also be calculated on that basis. If a truly alter the combustion quantities.
fuel contains no ash and if, in addition, it de- Similarly, the heat value and analysis of
posits no carbon in the furnace or on other heat- gaseous fuels are generally reported on the
ing surfaces, F is simply obtained by dividing volumetric basis; therefore, the temperature
1,000,000 by the "as-fired" heat value of the and the pressure conditions of the fuel are
fuel in Btu per lb. For the other cases where ash an essential part of the analysis. Standard con-
and/or solid combustible loss must be consid- ditions are commonly stated as 60F and 30
ered, Eq. may be used. in. Hg.
ATMOSPHERIC AIR, A
104(100 - Oh ash - %solid combustible loss)
F=
fuel heat value All combustion requires oxygen which in
commercial practice must be supplied from the
where: atmosphere. The theoretical quantity of oxygen
F = lb per million Btu fired may be calculated accurately from the fuel
Oh ash = percent by weight in fuel as fired analysis and simple reaction formulas, such as
OO
/ solid combustible loss = percent by weight in
fuel as fired
fuel heat value (HHV) = high heat value as fired,
Btullb
(1)
,.
The corresponding weight or volume of dry air
Fig. 1 is a graphical solution of Eq. 1, and required to supply this oxygen may then be cal-
applies to all fuels. culated, knowing that air contains approxi-
In the United States and many other coun- mately 23.1 percent oxygen by weight (20.9
tries of the world, the high heat value is the percent by volume).
accepted standard and is obtained by calori- Natural and manufactured fuels, however,
metric analysis of the fuel in a laboratory. contain varying proportions of several differ-
Producers often sell fuel on the basis of its heat ent combustible constituents, such as C, Hz, S,
value and users generally check it periodically. and various hydrocarbons. Some also contain
In any event, manufacturers of steam-gener- inert constituents, such as ash, Nz, H20,
C02,as
ating equipment need to know it; and, if it is not well as oxygen in varying quantities. Obvi-
furnished, they must make an independent test ously, determination of air for combustion then
or calculate it from constituents. For solid and becomes a time-consuming task for which
liquid fuels, empirical formulas must be used, shorter methods are desirable if accuracy can,
but for gaseous fuels the sum of the heat value at the same time, be maintained.
COMBMnON
CombustionCalculations by Graphic Methods

HHV, Btu/Lb As Fired


10,000 20,000 30,000
100
- 90
- 80
- 70
- 60
__-------- - 50 u
2
- 40
-- - Ash Sediment and
Solid Combustible Loss
% by Weight As Fired
i i

\
a

180 -
160 -
140 -
120 -

1000 2000 4000 6000 8000 10,000


HHV, Btu/Lb As Fired

Fig. 1. Weight of fuel in products of combustion

Throughout this appendix, the curves la- commercially feasible to burn all the available
beled "A" give the relation of air quantity to combustible material in the fuel.
percent excess air calculated for the several dif- The method used to determine the solid
ferent fuels. These curves A are based on "at- combustible loss consists of collecting flyash
mospheric air," which means that an arbitrary and refuse from various hoppers. From a dry
amount of moisture has been added to the air. sample burned in a muffle furnace, weight loss .

The American Boiler hlanufacturers Associa- due to combustion is measured. This b s s can
tion suggests basing all proposals on 60- be expressed as percent by weight of fuel as
percent relative humidity at 80F, which is fired.
equivalent to 0.013 lbs of water vapor per lb of In the combustion of a fuel having pure car-
dry air. (To neglect this would introduce an bon as the only combustible constituent, the air
error of approximately 1percent.) required may be accurately obtained by multi-
plying a Curve A reading by the factor
EFFECT OF UNBURNED COMBUSTIBLE

With a well-designed burner and furnace, it C = I - % solid combustible weight loss


100
is commercially possible to burn liquid and
(3)
gaseous fuels completely; no allowance is or-
dinarily made for loss of combustible in gas and
air weight calculations. In the combustion of because, in this case, air for combustion is
solid fuels, even in pulverized form, it is not directly proportional to carbon in the fuel. If,
.-
COXaUsnON
CombustionC.lcul8Uonsby Graphic Methods

however, all heat in the fuel does not come from gested an arbitrary value for use in preparing
carbon alone (so that the air is not strictly pro- proposals. As mentioned, this is taken as 0.013
portional to carbon burned), the factor C will lb of water per lb of dry air and is included in
not be exact. For high-carbon, low-volatile the atmospheric air, A, as read from the air-
fuels it will be nearly exact and will result in weight curve. When required as a separate item
only a small error even for fuels low in fixed for heat-balance calculations, an assumed
carbon and high in hydrogen. The error in- value from the following equation will be suffi-
volved by using Eq. 3 in all cases is quite within ciently accurate.
the limits of accuracy of all other combustion
calculations.
For a heat balance the combustible weight
loss must be converted to percent heat loss.
This can be done conveniently by dividing the
percent solid combustible weight loss by the MOISTURE FROM FUEL, W,
heat value of the fuel as fired and multiplying This is another item which is separately re-
by 14,500, which is the heat value for combus- ported both in an ASME Performance Test
tible in the refuse recommended by ASME Per- Codes heat balance and in a predicted heat bal-
formance Test Codes, PTC 4.1. ance. In the case of some fuels [such as natural
PRODUCTS OF COMBUSTION, P and refinery gases), the heat loss due to this
moisture may be the largest single item in the
Having calculated the foregoing quantities F heat balance. W,includes the combined surface
and A, the gaseous products of combustion and inherent moisture, W,, from a fuel plus the
may readily be determined by the addition of F moisture formed by the combustion of hydro-
and A, as previously corrected. Thus: gen, W,,. W,will vary from zero or a mere trace
in fuel oil to over 115 lb per million Btu fired in
the case of green wood; WI, will vary from zero
or a trace in lamp-black to 100 lb per million
where:
Btu fired in the case of some refinery gases.
P = total gaseous products of combustion, lb1106
Btu fired Special charts, or groups of curves, are used
F = fuel fired exclusive of ash or solid carbon loss, to calculate Wf for each fuel.
lb1106 Btu fired DRY GAS, P,
A = atmospheric air required, lb/106 Btu fired
C = combustible loss correction factor The need to calculate the "dry gas" or "dry
(4)
products," in addition to the.tota1 products, is
due to the ASME Performance Test Codes. Dry
gas loss is a separate item of the heat balance.
MOISTURE IN AIR, W, The dry gas may be determined by subtract-
Since the ASME Performance Test Codes re- ing the water vapor from the total products,
quires that heat loss due to moisture in air be thus
reported as a separate item in the test heat bal-
ance of a steam-generating unit, engineers cus- Pd = P - (14'" + Wf)
tomarily include it in a predicted heat balance. where:
In an actual test, the moisture in air can be de- Pd = dry gas, lb/106 Btu fired
termined from wet- and dry-bulb temperature P = total products of combustion, lb/106 Btu
readings, but for a predicted heat balance it W, = moisture in air, lbI106 Btu fired
must be assumed. It may vary from day to day Wr = moisture from fuel, lb/106 Btu fired
even in the same locality, but the American 46)
Boiler Manufacturers Association has sug-
COMBUSTION
Combustion CalculaUonsby Graphic Methods

CARBON DIOXIDE IN PRQDUCTS, C02 methods of laboratory analysis described in


Operators can use the C 0 2in the gases leav- Chapter 2, and found in the ASTM Standards
ing a furnace or boiler as a guide in adjusting referenced there.
the air supplied, so as not to use too much ex- PROXIMATE ANALYSIS 7 -
cess air and i n this way decrease the boiler effi- This quick and simple method is used to de-
ciency. Conversely, if the Copismaintained too termine the moisture, volatile matter, fixed
high, so that the excess air is too low, there will carbon, and ash of a given coal sample, by
be incomplete combustion of volatile fuel and weight. The moisture content is obtained by
a higher than normal loss in unburned fixed noting the loss of weight in the sample when it
carbon. is heated to a temperature of about 220F for an
The Orsat apparatus and all other chemical, hour. The moisture determined includes sur-
mechanical, or electrical means for analyzing face as well as inherent or hygroscopic mois-
flue gas, measure the.constituents of the gases ture. The volatile matter is the loss in weight
and not the excess air. However, it is desirable which follows additional heating of the sample
that the excess air be known, because i n many to a temperature of about 1750F for a half-
calculations the direct use of excess air rather hour, with all air excluded. The fixed carbon is
than CO, greatly simplifies the work. calculated from the further reduction in weight
of the sample which takes place when the coal
RELATION BETWEEN CO2 is completely burned in the presence of air,
AND EXCESS AIR
while the ash is the residue at the end of com-
It is, therefore, convenient to know the rela- plete combustion.
tionship between CO, and excess air. For bi- Since this laboratory method is approximate
tuminous coals, the relationship may be quite in nature, it is well to remember that combus-
accurately expressed in graphical form by tion calculations which are based on it may be
means of two curves. one for: high-volatile and considerably in error. For example, it is neces-
one for low-volatile fuel. Since in other fuels as sary to know the hydrogen in the coal to
oil and gas, there is greater variation in'the ratio evaluate the moisture loss in a heat balance.
of carbon to hydrogen, a whole family of curves Fig. 2 shows two curves, taken from DeBaufre's
may be required to cover the full range of original correlation,' which relate the percent-
analyses. As illustrated by these curves, the age of volatile matter i n the proximate
wide variation in excess air for a given CO,,
proves that it is unwise to think of C02as syn- a,
onymous with excess air except when dealing 2 7-
LL
with one particular fuel analysis for which the
C02-versus-excess-airrelationship is known.
The relationship between C02and excess air
for a fuel of known analysis can be calculated 12,000-12,500 Btu
by methods given in Chapter 4. Some engineers
prefer to make calculations on a weight basis -m 2
even for gaseous fuels, while others prefer the Sc 1
volume or mol system for all fuels.
O
;. o
I
ib 20 30 io io &,
COAL S % VM, H20-and Ash-Free

Chapter 2 and Appendix A give the proper-


Fig. 2. Determination of hydrogen, moisture and
ties of the many types of coal found throughout ash free (W. L. De Baufre, "Composition in Heating
the world. Particularly relevant to the calcula- Value of Fuels," Combustion, 2(11): 29-35, May
tion of the combustion products of coal are the 1931)
COUBrnON
Combustion C8lwlatlons by Graphic Mahods

analysis to the percentage of hydrogen in the Fig. 3. Variation of theoretical CO2


fuel. Actual values of hydrogen for certain with volatile matter (VM)
coals will differ from these average curves by as
much as 1.7 percent. This represents a varia-
v
I Solid Lines Were Used forcorrelating COz
and VM for Curves I3 on F~gure5.
tion of 12 lbs per million Btu in the water
formed by combustion of the hydrogen, which Lignites and
means that the moisture loss estimated from a Subbituminous
proximate analysis may be 1.5 percent greater Coals
O

or smaller than it should be, if such loss is


based on 500F. This discrepancy alone may,
T - .-
A I, C I I L I
then, be sufficient to absorb an entire manufac-
turer's margin and unaccounted-for loss, com- .-c s
monly 1.5 percent.
The character of the volatile matter is not the $ 17A lb ;o 3b 40 l o Bb 70
/ VM, H20- and Ash-Free
OO
same for all coals, because some contain more
carbon dioxide than others. This fact ac~ounts-
for the two distinct groups of points occurring
on Fig. 3, which is a correlation of the percent
C02in the dry products of combustion with the
I
Solid Line Was Used for Curves B on Figure 5.
I
volatile matter in the proximate analysis. Thus,
lignites and subbituminous coals form, on the
average, about 1 percent more C02 than bitu-
minous coals of the same volatile content. The
kind of hydrocarbon in the volatile also has a
direct bearing on the position of points in Fig.
3, since different hydrocarbons generate differ-
ent amounts of carbon dioxide. Plotting per-
cent Cop against the ratio of fixed carbon to in Coal, Dry or!As Fired
H2 - 0.1 0 2
volatile matter does not help to line up the
points.
Fig. 4. Variation of theoretical CO2 with
ULTIMATE ANALYSIS
burning it can be accurately calculated. Fur-
From the foregoing discussion, it is obvious
thermore, by knowing the ultimate analysis, it
that for accurate combustion calculations it is
is possible to obtain a better correlation be-
preferable to have an ultimate analysis of the
coal as discussed in Chapter 2. Sometimes, in- tween the percent C02 in the dry products of
stead of being reported as a separate item, the combustion and the ratio
moisture in the ultimate analysis is divided
into 8 parts oxygen and 1 part hydrogen and
then added to the oxygen and hydrogen of the for all coals. including lignite and subbi-
combustible in the coal. For combustion calcu- tuminous. This is shown by Fig. 4 where no
lations, this is not a good practice, because in GO2value plotted deviates from the solid line
computing a heat balance, the surface and in- used in labeling Curves B of Fig. 5 by more than
herent moisture in the fuel require different 0.30 percent. These are the principal reasons
- .treatment from the water formed when hydro- for preference of the ultimate over the proxi-
gen is burned. mate analysis.
Since an ultimate analysis includes the per- Fig. 6 shotzrs the variation of the atmospheric
cent hydrogen, the amount of water formed by air at zero excess air with volatile matter on a
;,4 i COMBUSTION
Combustion Calc(~Iatlons
by Graphic Methods

VM Is on H2O- and Ash-Free Basis.

1600

' 7*0 -10 20


O/O
30 40 50
Excess Air
60 70 0 10 20 30 40 50 60 70
% Excess Air

- 0
6 8 10 12 14 - 6 '
HHV, Btu/Lb As Fired HHV, Btu/Lb As Fired
Note: Use the Dotted Line for Lignites and Subbituminous Coals Only
If CI(H, - 0.1 0,)
Cannot Be Evaluated.

Fig. 5. Combustion characteristics of coal


--
COMDVSRON *
CombuaUonC.IwI~lionsby Graphic M.ulods

moisture and ash-free basis, while Fig. 7 indi- Thus, an analysis on the as-received or as-
cates the change in atmospheric air with the sampled basis serves to define the condition of
ratio the coal at the time it was tested. As dry, the
[H* "
+ 0.102 I
Figs. 6 and 7 reveal that the maximum devia-
fuel is reported with the moisture item omitted;
as ash free, it is without ash, and as moisture
and ash free, it has had both moisture and ash
tion in the calculated weight of air from the re- eliminated from the anlysis.
spective average curve is less than 22.5 percent. HEATING VALUE
Table I tabulates representative ultimate
analyses of various ranks from different states. It is customary to report the high heating
More extended lists are available in the bulle- value ( H W ) of coal', in Btu per pound, along
tins issued from time to time by the U.S. with the analysis, whether proximate or ulti-
Bureau of Mines. mate, and oncthe same basis as the analysis.
For purposes of reporting or correlation, it is Burning a small sample of coal in a bomb
often convenient to express proximate and ul- calorimeter immersed in water, and measuring
timate analyses on a basis other than as fired. the temperature rise of the water, accurateIy
determine the high heating value at constant
Fig. 6. Variation of theoretical air volume.
with volatile matter (VM) Various formulas have been, proposed for
I 1
evaluating the Btu per pound of coal from its
Solid Line Was Used for Correlating A proximate or ultimate analysis. All yield only

-
and VM for Curves Aon Figure 5 approximate results because they do not take
D into account the complex thermodynamic
P!
if 8 5 0 r changes occurring when coal is burned. If only
the coal rank is known, it is best to assume the
heating value from some reasonably close
analysis, such as given in Table I.
COMBUSTIBLE LOSS
3a 7*0 10 20 30 40 50 60 70 Combustible loss in coal-fired furnaces re-
Oh VM, H20- and Ash-Free sults from incomplete burning of either the
solid or the volatile combustible in the fuel.
r How much loss is determined by the character
of the coal itself, the methbd of firing it, and the
Solid Line Was Used for Curves A on Figure 5 furnace design and operation. With proper fur-
nace design and operation, the loss due to
unburned volatile, as determined by the pres-
ence of CO in the flue gas, is generally negligi-
ble. On the other hand, the loss due to solid
combustible in the ash, as measured by the re-
duction in weight which a sample of ash refuse
undergoes on being completely burned, may
3 650 10 20 30 40 50 vary from a negligible amount in burning pul-
d verized coal to 20 percent of the coal fired, or
Hz +0.1 0 2
in Coal, Dry pr As-Fired more, with certain sizes of anthracite.
If K,,KO,etc., are known or assumed con-
stants representing, respectively, the fractions
Fig. 7. Variation oftheoreticalair with
1 of the total ash in a pound of coal which is
COMBUSTION
CombustionCalculationsby Graphic MeUlods
6

deposited in the ash hopper, as flyash, etc., this moisture, when converted to pounds per
W. S. Patterson has shown2 that the total com- million Btu, the symbol W,has already been as-
bustibleloss may be expressed by Eq. 7. signed. It is the sum of the surface moisture,
which produces "wetness" in the coal, and the
% solid combustible weight loss = inherent or hygroscopic moisture, which being
intimately held by the coal is not readily
sensed. Table I reveals that, in some high-
volatile bituminous coals, the total moisture
x ash in coal as fired
J (7) may he as low as 1.4 percent, while it may in-
crease to 34.8 percent and higher in lignite. The
where CRl, CRl,etc., are the respective weights portion of Wc that is inherent moisture, like-
of combustible per pound of dry refuse from wise, varies from negligible amounts in super-
siftings, ash hopper, flyash, etc. For a given anthracites to high values in lignites. Curves D
coal burning unit, the sum of all K's is, then, of Fig. 5 offer a convenient method of obtaining
, equal to 1. . W, from the percent moisture and high heating
The results of Eq. 7 may be substituted in Eq. value of the coal as fired. .
3 to find the unburned combustible factor, C.
In addition to W,, coal will yield water from
the burning of its hydrogen content. Curves C,
FUEL IN PRODUCTS, F Fig. 5 , rnakc it possible to determine this water,
Wi,, in pounds ~ emillion
r Btu, from the percent
Knowing the high heating value of the coal,
hydrogen and high heating value of the coal as
its ash content, and its combustible loss factor
fired. If only a proximate analysis of the coal is
C, that portion of the fuel which reappears in
available, its hydrogen content must first be
the products of combustion, F, is taken directly
read fro111Fig. 2. Special attention is called to
from Fig. 1.
the fact that Curves C are based on hydrogen as
ATMOSPHERIC AIR, A fired, whilc the hydrogen from Fig. 2 is on a
moisture- and ash-free basis, and must be con-
For any value of excess air up to 100 percent, verted Lo the as fired condition before entering
the atmospheric air in pounds per million Btu on Curves C of Fig. 5.
as fired may be taken from Curves A, Fig. 5,
Wris thc sum of Wcand W,,.
after determining either the ratio

[H, + 0.10, I PERCENT COz IN PRODUCTS


The percent CO, by volume in the dry prod-
ucts of combustion may be read from Curves -
from an ultimate analysis of the coal or the
moisture- and ash-free volatile matter from a B, Fig. 5, for excess-air values up to 100 percent
proximate analysis. of theoretical requirements and for [C/(H2 - 0.1
0 2 )I ratios from 12.5 to 50. The ratio
The empirical relation between A and

[H, "
+ 0.10, I can, of course, be calculated from an ultimate
is shown by Fig. 7, while Fig. 6 indicates the
trend of A with a change in the moisture- and analysis of the coal. Fig. 6 shows the relation be-
ash-free volatile of the coal. tween percent CO, at zero excess air and

MOISTURE IN FUEL Wf

As already explained, the loss in weight which was the basis for the CO, curves on Fig. 5.
caused by drying the coal at 220F constitutes When only a proximate analysis is given, the
the total moisture reported in an analysis. To moisture- and ash-free volatile matter may be
COYBOSllON
Comburtlon C.lwlaUons by Graphic Methods

Table I.Analyses of Typical U.S. Coals, as Fired


A at Zero
-% Proximate Analysis- % Ultimate Analysis - HHV, Excess Air,
State Rank Hz0 VM FC ASH Hz0 C Itz S 0 2 Nz BWLb Lbl106Btu'

RI Ma 13.3 2.5 65.3 18.9 13.3 64.2 0.4 0.3 2.7 0.2 9.313 808
--
co A 2.5 5.7 83.8 8.0 2.5 83.9 2.9 0.7 0.7 1.3 13,720 787
NM A 2.9 5.5 82.7 8.9 2.9 82.3 2.6 0.8 1.3 1.2 13.340 786
PA
** A 5.4 3.8 77.1 13.7 5.4 76.1 1.8 0.6 1.8 0.6 11,950 791
*** A 2.3 3.1 87.7 6.9 2.3 86.7 1.9 0.5 0.9 0.8 13,540 794
**** A 4.9 3.7 82.2 9.2 4.9 81.6 1.8 0.5 1.3 0.7 12,820 788
-- --
AR Sa 2.1 9.8 78.8 9.3 2.1 80.3 3.4 1.7 1.7 1.5 13,700 770
PA Sa 3.0 8.4 78.9 9.7 3.0 80.2 3.3 0.7 2.0 1.1 13.450 777
VA Sa 3.1 10.6 66.7 19.6 3.1 70.5 3.2 0.6 2.2 0.8 11,850 782 -
-
- -
AR Lvb 3.4 16.2 71.8 8.6 3.4 79.6 3.9 1.0 1.8 1.7 13,700 774
MD Lvb 3.2 18.2 70.4 8.2 3.2 79.0 4.1 1.0 2.9 1.6 13,870 761
OK Lvb 2.6 16.5 72.2 8.7 2.6 80.1 4.0 1.0 1.9 1.7 13,800 775
WV Lvb 2.7 17.2 76.1 4.0 2.7 84.7 4.3 0.6 2.2 1.5 14,730 767
- --
PA Mvb 3.3 20.5 70.0 6.2 3.3 80.7 4.5 1.8 2.4 1.1 14.310 765
VA Mvb 3.1 21.8 67.9 7.2 3.1 80.1 4.7 1.0 2.4 1.5 14,030 778
-. -- -- .. --
AL Hvab 5.5 30.8 60.9 2.8 5.5 80.3 4.9 0.6 4.2 1.7 14,210 768
CO Hvab 1.4 32.6 54.3 11.7 1.4 73.4 5.1 0.6 6.5 1.3 13,210 763
KS Hvab 7.4 31.8 52.4 8.4 7.4 70.7 4.6 2.6 5.0 1.3 12,670 769
KY Hvab 3.1 35.0 58.9 3.0 3.1 79.2 5.4 0.6 7.2 1.5 14,290 758
MO Hvab 5.4 32.1 53.5 9.0 5.4 71.6 4.8 3.6 4.2 1.4 12,990 769
NM Hvab 2.0 33.5 50.6 13.9 2.0 70.6 4.8 1.3 6.2 1.2 12.650 766
OH Hvab 4.9 36.6 51.2 7.3 4.9 71.9 4.9 2.6 7.0 1.4 12.990 762
OK Hvab 2.1 35.0 57.0 5.9 2.1 76.7 4.9 0.5 7.9 2.0 13.630 757
PA Hvab 2.6 30.0 58.3 9.1 2.6 76.6 4.9 1.3 3.9 1.6 13,610 773
TN Hvab 1.8 35.9 56.1 6.2 1.8 77.7 5.2 1.2 6.0 1.9 13,890 767
TX Hvab 4.0 48.9 34.9 12.2 4.0 65.5 5.9 2.0 9.1 1.3 12.230 767
UT Hvab 4.3 37.2 51.8 6.7 43 72.2 5.1 1.1 9.0 1.6 12,990 758
VA Hvab 2.2 36.0 58.0 3.8 2.2 80.6 5.5 0.7 5.9 1.3 14,510 764
WA Hvab 4.3 37.7 47.1 10.9 4.3 68.9 5.4 0.5 8.5 1.5 12,610 758
WV Hvab 2.4 33.0 60.0 4.6 2.4 80.8 5.1 0.7 4.8 1.6 14,350 768
IL Hvcb 8.0 33.0 50.6 8.4 8.0 68.7 4.5 1.2 7.6 1.6 12,130 766
KY Hvcb 7.5 37.7 45.3 9.5 7.5 66.9 4.8 3.5 6.4 1.4 12,080 774
MO Hvcb 10.5 32.0 44.6 12.9 10.5 63.4 4.2 2.5 5.2 1.3 11,300 773
OH Hvcb 8.2 36.1 48.7 7.0 8.2 68.4 4.7 1.2 9.1 1.4 12,160 762
WY Hvcb 5.1 40.5 49.8 4.6 5.1 73.0 5.0 0.5 10.6 1.2 12,960 757
IL Hvbb 12.1 40.2 39.1 8.6 12.1 62.8 4.6 4.3 6.6 1.0 11,480 769
IN Hvbb 12.4 36.6 42.3 8.7 12.4 63.4 4.3 2.3 7.6 1.3 11,420 758
IA Hvbb 14.1 35.6 39.3 11.0 14.1 58.5 4.0 4.3 -7.2 0.9 10,720 754
. . COMBUSTION
CombustionCalcuIaUons by Graphic Memods

Table I. Analyses of Typical U.S. Coals, as Fired -Continued


A a t Zero
-40 Proximate Analysis- % Ultimate Analysis HHV, 4 x c e s s Air,
State Rank Hz0 VM .FC ASH Ha0 C HZ S 0 2 N2 BNLb LbllO6Btu'

MI Hvbb 12.4 35.0 47.0 5.6 12.4 65.8 4.5 2.9 7.4 1.4 11,860 762

co Sub 19.6 30.5 45.9 4.0 19.6 58.8 3.8 0.3 12.2 1.3 10,130 756
WY Sub 23.2 33.3 39.7 3.8 23.2 54.6 3.8 0.4 13.2 1.0 9,420 757

ND LigA 34.8 28.2 30.8 6.2 34.8 42.4 2.8 0.7 12.4 0.7 7,210 750
TX LigA 33.7 29.3 29.7 7.3 33.7 42.5 3.1 0.5 12.1 0.8 7,350 752
*A is the air required for combu~tionunder stoichiometric conditions [no excess air). with 0.013 Ib H1O per Ib dry air.
'*Orchard Bed. *"Mammoth Bed. ""Holmes Bed. R . W K KEY: Ma-hleta-anthracite. A-Anthracite. Sa-Semi-anthracite. Lvb-Low-Vol. Bituminous.
Mvb-Med.-Vol. Bituminous. Hvab-High-Vol. Bituminous A. Hvcb-High-Vol. Binuminous 9.Hvbb-High-Vol. Bituminous C. Sub-Subbituminous, LigA-
Lignite A --

used to obtain the CO, from Curves B of Fig. 5 bituminous and lignitic coals is unavailable.
for all but subbituminous coals and lignites.
Because, as explained before, the volatile in the COKE AND COKE BREEZE
latter ranks does not possess the characteristics
of other cdals, the dotted line on Fig. 5 should Coke is the fused solid residue left when cer-
be used when the ultimate analysis for sub- tain coals, petroleum, or tar pitch are heated in
- - - p p p

EXAMPLE
Assume that a Pennsylvania bituminous coal, with the moisture in the coal as fired, and WI, the water formed in
typical proximate analysis of line 25, Table I, is burned combustion. FromCurvesD, Fig. 5, for2.6-percent moisture
with 20-percent excess air and that the expected solid com- i n the fuel and a high heating value of 13,610 Btu per lb, read
bustible loss is 0.8 percent by weight. Then W, = 2 lb per million Btu.
1.Fuel, F. The sum of the ash plus solid combustible loss Next. convert the highheating value as fired to a moisture-
i s 9.1 + 0.8 = 9.9 percent by weight. With this sum, and a and ash-free basis, as follows:
high heating value from line PA, Table I, of 13,610 Btu per
lb, read from Fig. 1,F = 66 Ib per million Btu.
2. Atmospheric Air, A. The sum of the ash plus moisture
in the coal is 9.1 + 2.6 = 11.7 percent, and the mois-
I [ -$]
% = 15,400Btu

ture- and ash-free volatile matter =

[- 30
]
= "percent
per lb. and use it, together with the moisture-and ash-free
volatile determined for A, to read from Fig. 2,H2 = 5.4-per-
cent moisture and ash free, or reverting to the as-fired
For this value of volatile matter and %percent excess air, basis*5.4
read from Curves A Fig. 5 A = 920 Ib per million Btu.
3. Unburned Combustible Factor, C. Since the solid
1- - - ( ::)
- 4.8-percent hydrogen.
combustible loss is 0.8 percent, from Eq. 3 obtain From Curves C. Fig, 5 , for a high heating value of 13,610
1 - % solid combustible weight loss Btu per lb and H, = 4.8percent. read Wh = 32lb per million
C= 100 Btu. Wf = W, + LVh = 2 + 32 = 34 lb per million Btu.
7. Dry Gas, Pd. From Eq. 6, P d = P &V. + Wf) = 979 - -
= 11 -@I -0.992. (12 + 34) = 933 lb per million Btu.
8. Percent C0z in Products. For a moisture-and-ash-free
4. Total Products, P. From Eq.4, P = F + CA = 66 + 0.992 volatile matter of 34 percent and 20-percent excess air, read
920 = 979 Ib per million Btu. from Curves B, Fig. 5, CO, = 15.3 percent.
5. Moisture in Air, Wa. From Eq.5, W, = 0.013 x 920 = 121b (Note: Many of the foregoing figures will be somewhat
per million Btu. different if the ultimate, instead of the proximate, analysis
6. Moisture from Fuel, Wf This is the sum of W, the i n line PA, Table I, is used.)
an atmosphere excluding oxygen, so as to expel combustible in the fuel is lost as siftings with
their volatile content. The process of thus de- the flyash, etc., in the manner described in the
composing these fuels into their gaseous and section on coals. With coke, as with coal, the
solid fractions is known as destructive distilla-
tion or carbonization.
% solid combustible weight loss =
Coke breeze is very small-size coke that is
particularly well suited for firing on certain
types of stokers. As a rule, it contains a higher
percentage of ash than the rest of the coke. x ash in coke as fired
(9)
Table I1 presents analysis values of constit-
uents i n typical cokes, as fired.
HEATING VALUE where C R I , C R z , etc., are the respective weights
As with coal, the high heating value of coke, of combustible per pound of dry refuse from
in Btu per lb, can be determined-by a bomb siftings, ash hopper, etc., and K,, K2,etc., are
calorimeter. If not given with 'the ultimate constants representing fractions of the ash in a
- analysis, it may- be calculated approximately pound of coke found, respectively, in siftings,
from a formula of the Dulong type. ash hopper, etc.
FUEL IN PRODUCTS, F
HHV = 14,600C + 62,000 Knowing the high heating value of coke, its
ash content, and its combustible loss factor C,
(81
that portion of fuel, F, which reappears in the
where C, Hz,Ofand S are weight fraction; in the products of combustion, is taken from Fig. 1.
ultimate analysis. ATMOSPHERIC AIR, A
COMBUSTIBLE LOSS Analyses of coke are reported on either the
In burning coke or coke breeze in pulverized proximate or the ultimate basis. The chart, Fig.
form or on stokers, a certain amount of the 8, was prepared so that values of atmospheric

Table 11. Analyses of,TypicalCokes, as Fired


COl at
Aat Zero Zero
. -
-% Proximate Analysis--' %Ultimate Analysis HHV, Excess Air, Excess
Kind Hz0 VM FC Ash Hz0 C Hz S 0 2 Nz Ash BtWLb Lbl106Btu Air,%
High-temperature
coke 5.0 1.3 83.7 10.0 5.0 82.0 0.5 0.8 0.7 1.0 10.0 12,200 798 20.7
Low-temperature
coke 2.8 15.1 72.1 10.0 2.8 74.5 3.2 1.8 6.1 1.6 10.0 12,600 763 19.3
Beehive coke 0.5 1.8 86.0 11.7 0.5 84.4 0.7 1.0 0.5 1.2 11.7 12,527 807 20.5
B yproduct coke 0.8 1.4 87.1 10.7 0.8 85.0 0.7 1.0 0.5 1.3 10.7 12,690 802 20.5
High-temperature
coke breeze 12.0 4.2 65.8 18.0 12.0 66.8 1.2 0.6 0.5 0.9 18.0 10,200 805 20.1
Gas Works coke:
Horizontalretorts 0.8 1.4 88.0 9.8 0.8 86.8 0.6 0.7 0.2 1.1- 9.8 12,820 808 20.6
Verticalretorts 1.3 2.5 86.3 9.9 1.3 85.4 1.0 0.7 0.3 1.4 9.9 12,770 809 . 20.4
Narrow
coke ovens 0.7 2.0 85.3 12.0 0.7 84.6 0.5 0.7 0.3 1.2 12.0 12,550 802 20.6
, ., COMBUSTION
..
A-
3

Combustion ~a%dations by Graphic Methods

Note: VM Is on H20-and Ash-Free Basis.

1400 75 and UD

-
6 0 0 ~ 10 20 30 40 50 60 70
O/O Excess Air
u
loo 10 20 30 40 50 60 70
O/O ExcessAir

HHV, Btu/Lb As Fired HHV, Btu/Lb As Fired

Fig. 8. Combustion characteristicsof coke


C0YI)USI'ION
Combuttion &lculations by Graphic M o d s

air, A, in pounds per million Btu as fired may be W, which is this moisture in pounds per mil-
obtained after knowing either the moisture- lion Btu, may, therefore, be a small quantity if
and ash-free volatile matter in the coke or its the quenching is done rapidly, or may amount
CIH2ratio. to 1 2 lb or more in cases where storage condi-
Fig. 9 shows the empirical relation between tions enabled the coke to absorb moisture, read-
A and the volatile matter on a moisture- and ily because of its porous nature.
ash-free basis and Fig. 10 indicates how A var- Knowing the high heating value and the per-
ies with the ratio C/H2. It will be seen that no cent moisture in the coke as fired, W, may be
calculated point deviates from the solid, aver- read from Curves D, Fig. 8.
age lines on these figures by more than k 2 . 0 Wh,the pounds of water per million Btu fired
percent. The solid lines were used in labeling formed by combustion of the hydrogen in coke,
Curves A of Fig. - 8. mav be obtained from Curves C of Fig. 8, pro-
TOTAL PRODUCTS, P vidkd the hydrogen in the ultimate analysis is
The unburned combustible factor is obtained given. With only a proximate analysis of coke
from Eq. 3. This factor C is then used in correct- available, Wh is determined from Fig. 11, after
converting the volatile matter to a moisture-
ing F, the fuel in products, and A, the atmos-
and ash-free basis. This curve is based on the
pheric air when determining the total products
P from Eq. 4. graphical correlation shown in Fig. 1 2 , and as
such, is of limited accuracy. As in previous sec-
MOISTURE IN FUEL, Wf tions, Wfis the sum of W,and W,,.
The moisture reported in a coke analysis, just PERCENT CO2 IN PI3ODUCTS
as for coal, is the loss in its weight when dried Curves B of Fig. 8 offer a convenient way
at 220F. of determining the percent C 0 2 by volume
Any moisture present in coke results either in the dry products of combustion of coke,
from the quenching process or outdoor storage. for any value of excess air from zero to 100

EXAMPLE
Assume that a high-temperature coke breeze, having the 4. Total Products, P. From Eq. 4 , P = F CA = +
typical proximate analysis shown in Table I1 is burned with +
70 0.90 x 1065 = 1028 lb per million Btu.
35-percent excess air and that the expected combustible loss 5, ~ ~in ~ iwa.i ~ F~~~
, ~ E ~ 5,
. [IT, t = 0 . 0~1 3 ~= 0,013
~ ~
is 10 percent by weight. Then x 1065 = 14 lb per million Btu.
1. Fuel, F. The sum of the ash plus solid combustible loss is 6. ~ ~from ~ i ~wf.~ ~hi^ 1 is ,the t sum ~of w,, the ~ ~
18.0 + 10.0 = 28.0 percent by weight. With this sum, and a moisture in the coke as fired, and wh.the water formed in
high heating value from able 11 of 10.200 Btu Per lb. read combustion. FromCurres D, Fig. 8 , for 1 2 percent moisture
from Fig. 1 , F = 70 lb per million Btu. i n the fuel and a high heating value of 10,200 Btu per Ib
2. Atmospheric Air, A. The sum of the ash plus moisture read W, = 1 2 lb per million Btu.
in the coal is 1 8 . 0 + 12.0 = 30 percent, and the moisture- Next, with 6 percent moisture- and ash-free volatile de-
and ash-free volatile matter = termined for A, read from Fig: 11 \ V h = 1 0 lb per million
Btu. Then
W, = W, + Wh = 12 + 10 = 22 lb per million Btu.
= 6 percent. For this value of volatile matter and 35- 'I.DryGas,Pd. FromEq.6,Pd=P - ( ( I Z r , + W ~ ) = 1 0 2 8- ( I 4
percent excess air, read from Curves A, Fig, 8, A = 1065 Ib + 2 2 ) = 992 lb per million Btu.
per million Btu. 8. Percent COI in Products. For a moisture- and ash-free
3. Unburned Combustible Factor, C. Since the solid com- volatile matter of 6 percent and 35 percent excess air, read
bustible loss i s 1 0 percent, from Eq. 3 obtain from Curves B, Fig. 8, C 0 2 = 14.7 percent.
1- %solid combustible weight loss (Note:Many of the quantities calculatedin the
100, + _. example will be different if the ultimate, instead
of the proximate, analysis of coke breeze is
used.)
COMBUST!ON
$
Combustion Calculationsby Gnphic hlethds

Fig. 9 Variation of theoretical air Fig. 11. Predicted moisture from


with volatile matter (VM) of coke combustion of coke

- -
Solid Line Was Used for Correlating A 'D
and for Curves A on Flgure 8 2
u

i7iLL
2
.-

b 10
f9 00
\
F

2 4 6 8 10 12 14 16 18

% VM, HzO- and Ash-Free


% VM, HiO- and Ash-Free
I
Solid Line Was Used for Curve on Figure 11
Solid Line Was Used for Curves A
I
;;i
on Figure 8 u

a
.
$10
\

d C/HZin Coke, Dry or As Fired f: 0 0


2 0 2 4 6 8 10 12 14 16 18
3 % VM, H 2 0 - and Ash-Free
I I I I
Fig. 10. Variation of theoretical air with CIH2 Fig. 12. Variation of moisture from
combustion of coke with volatile matter (VM)

percent. As in drawing the lines for A, it is apparent that the latter is a more accurate
Curves B are plotted so that CO, values correlation. Accordingly, in reading Curves B,
may be obtained after calculating the ratio an ultimate analysis of coke is preferable to a
proximate analysis.
[ H,C0.1 O J WOOD AND BAGASSE
from the ultimate analysis, or after converting
the volatile matter in the proximate analysis as The origin of these two cellulose fuels is de-
fired to the moisture and ash-free basis. scribed in Chapter 2; typical analyses are
Comparing Fig. 13, which relates moisture shown in Tables I11 and IV.
and ash-free volatile matter to the percent C02 Moisture is the most variable single item in
at zero excess air, with Fig. 14, which shows the the composition of both wood and bagasse, its
variation of C 0 2with the ratio value ranging from 6 percent in a kiln-dried
wood to over 60 percent in green wood or ba-
gasse and up to 80 percent in bark. It is of im-
portance in combustion calculations because it
COXRETiON m

Corrrbusthm C.lculatlons by Graphic Methods

Solid Line Was Used for Correlating C02 Solid Line Was Used for Curves B
and VM for Curves B on Figure 8. on Figure 8
B
$6'
0
f E 21
''
Y,,
-
8
#; 0
20
19
b 4 8 12
% VM, HzO- and Ash-Free
16 20
0"
H, - 0.1 0,
in Coke, Dry or As-Fired

I I
Fig. 13 Variation of theoretical CO, Fig. 14. Variation of theoretical COz
with volatile matter (VM) of coke
I
directly influences the heating value of the fuel Other less reliable, but quicker, ways of
burned by increasing the proportion .of inert judging the moisture in wood consist in meas-
matter present. Furthermore, it requires some uring its electrical resistance or using a wood
of the heat released by the dry substance to hygrometer.
evaporate and superheat it. As a rule, kiln-dried woods contain from 6 to
DETERMINATION OF MOISTURE CONTENT 10 percent moisture, although softwoods will
show a much higher percentage unless prop-
An accurate determination of the moisture erly handled in the kiln. Air-dried woods have
content in wood or bagasse is, therefore, neces- had enough moisture evaporated to be in
sary. To obtain this, a weighed sample is placed equilibrium with the surrounding atmosphere.
in a steam or electric oven and heated to 212'F The actual percent present depends on both the
until no further loss of weight occurs. The dif- temperature and relative humidity of the ambi-
ference between the original weight and that of ent atmosphere. Fig. 15 shows how the moisture
the dried sample divided by the original weight in wood varies with different relative humidi-
is the moisture fraction as received. In the ties at 70E In arid climates, it may be as low as
lumber industry, it is customary to speak of
moisture in wood on an oven-dry basis,
whereby the loss of weight in the sample tested
is divided by the oven-dried weight rather than
the original weight. The percent moisture
oven-dry must then be converted to the as-
received basis before using it in combustion
calculations.
The oven-drying method of determining the
moisture content is not accurate with woods
such as southern yellow pine, which contain
oils that are easily volatilized, because these
oils will distill with the moisture. It is then
necessary to use the more elaborate distillation I % Relative H q i d i t y (-Ambient)

method, wherein the water and the oil are Fig. 15. Moisture content of wood
measured separately. at 70F ambient temperature
, * COMBUSTION
Combustion Calculationsby Graphic Methods

5 percent, w.hereas in humid regions it may go wood tissue, and still more on the presence of
up to 20 percent or more. Green wood, wood resins, gums, tannins, essential oils, or pig- -
waste, and bagasse contain from 40 to over 60 ments. Resin alone, for instance, may increase
percent moisture. the heating value of the same wood as much as
1 5 percent. Table I11 shows that the Btu per
HEATING VALUE
pound of dry softwoods is a little higher, on the
The high heating value of wood or bagasse is average, than that of hardwoods, due perhaps
determined by a bomb calorimeter, as in the to the fact that most softwoods are conifers con-
case of other solid fuels. From the close similar- taining resins and oils.
ity of the ultimate analyses of different woods, As mentioned, however, the chief factor af-
it might be reasonable to assume that equal fecting the heating value of the wood or bagasse
weights of dry wood will release the same as fired into a furnace is its moisture content. In
amount of heat, regardless of species. Actually, the case of wood refuse, the heating value may
as Table I11 indicates, this is not the case, the also be influenced by the amount of trash and
heating value of wood depending to some ex- dirt gathered in processing the wood. In har-
tent on the physical structure and form of the vesting sugar cane, a certain-amount of trash,

Table Ill. Typical Analyses of Dry Wood


C0z at
Aat Zero Zero
%byWeight HHV, Excess Air, Excess
C Hz S 0 2 Nz Ash BtdLb LbllO6Btu Air,%
Softwoodst
Cedar, white 48.80 6.37 .. . 44.46 ... 0.37 8400* 709 20.2
Cypress 54.98 6.54 .. . 38.08 . .. 0.40 9870X 711 19.5
Fir, Douglas 52.3 6.3 ... 40.5 0.1 0.8 9050 720 19.9
Hemlock, western 50.4 5.8 0.1 41.4 0.1 2.2 8620 706 20.4
Pine, pitch 59.00 7.19 ... 32.68 ... 1.13 11320* 702 18.7
white 52.55 6.08 ... 41.25 .. . 0.12 8900* 723 20.2
yellow 52.60 7.02 ... 40.07 ... 0.31 9610* 710 19.3
Redwood 53.5 5.9 ... 40.3 0.1 0.2 9040* 722 20.2

Hardwoodst
Ash, white 49.73 6.93 ... 43.04 ... 0.30 8920* 709 19.6
Beech 51.64 6.26 ... 41.45 ... 0.65 8760* 729 20.0
Birch, white 49.77 6.49 ... 43.45 .. . 0.29 8650* 712 20.0
Elm 50.35 6.57 ... 42.34 ... 0.74 8810* 715 19.8
Hickory 49.67 6.49 ... 43.11 . .. 0.73 8670* 711 20.0
Maple 50.64 6.02 ... 41.74 0.25 1.35 8580 719 20.2
Oak, black 48.78 6.09 ... 44.98 ... 0.15 8180* 714 20.5
red 49.49 6.62 ... 43.74 .. . 0.15 8690* 709 19.9
white 50.44 6.59 ... 42.73 .. . 0.24 8810" 715 19.8
Poplar 51.64 6.26 ... 41.45 ... 0.65 8920* 716 20.0
" Calculated from reported high heating value of kiln-dried wood assumed to contain 8-percent moisture.
tThe terms "hard" and "soft" wood. contrary to popular conception, have no reference to the actual hardness of the wood. According to the
Wood Hondbook, prepared by theForest Products Laboratory of the U. S. Department of Agriculture. hardwoods belong to the botanicalgroup
of trees that are broad-leaved whereas softwoods belong to the group that have needle or scalelike leaves, such as evergreens: cypress. larch.
and tamarack are exceptions

ARB
L.m
u
o
).Im
. ,,
C O ~ O t ?
Combustion c.rcJ.tlonc by Gnphlc Methods

Table IV. Typical Analyses of Bagasse, Dry


COz at
A at Zen, Zero
%by Weight HHv, Excess Air, Excess
C HZ 0 2 N1 Ash Btab Lbli06 Btu Air, %
Cuba 43.15 6.00 47.95 ... 2.90 7985
Hawaii 46.20 6.40 45.90 . .. 1.50 8160
Java 46.03 6.56 45.55 0.18 1.68 . 8681
Mexico 47.30 6.08 45.30 ... 1.32 8740
Peru 49.00 5.89 43.36 ... 1.75 8380
Puerto Rico 44.21 6.31 47.72 0.41 1.35 8386

leaves, cane. tops, and grass may be-included tent of these fuels are known, the portion, F, of
whicb would result in a lower heating value for the fuel that reappears in the products of com-
the bagasse. As a rule, larger quantities of trash bustion may be taken directly from Fig. 1.
and dirt are picked up when the cane is har- ATMOSPHERIC AIR, A
vested and loaded by mechanical means than
when this is done by hand. Curves A of Fig. 18 offer a convenient way of
Owing to their complex composition, it is not obtaining the "atmospheric air," A, in pounds
possible to make use of a Dulong-type formula per million Btu fired, for any excess-air value
to predict the heating value of either wood or up to 100 percent after calculating the ratio
bagasse. The formula appears to give values of
available hydrogen in the factor ' [Hz + O.lO1 1
(H+ ) from the ultimate analysis of wood or bagasse.
These lines are based on the correlation be-
which are too low and, as a result, the heating tween this ratio and the theoretical air required
values calculated with it are invariably low. sholvn by Fig. 16.
In sugar-mill practice, bagasse analyses are
frequently reported in terms of its fiber, su- PERCENT C02 IN PRODUCTS
crose, glucose, moisture, and ash content. If The percent CO, by volume in the dry prod-
these are given, the high heating value (HHV) ucts of combustion may be determined from
of bagasse in Btu per pound may be computed Curves B of Fig. 18 for any excess air from zero
from to 100 percent of theoretical requirements.
- -- Curves B are based on the solid line of Fig. 1 7 ,
HHV = 8550(F) + 7119(S)+ 6750(G)- 972(M) which shows the change in the ultimate CO-
where with the ratio
F = fiber, lbllb of bagasse
S = sucrose, lbllb of bagasse
G = glucose, lbllb of bagasse
[ H z - 0.102 1
The correlation of Fig. 1 7 shows that no value
M = moisture, lbllb of bagasse
(10) deviates from thesolid line by more than 20.2
percent Cop. This is the accuracy that may be
expected in reading Curves B.
FUEL IN PRODUCTS, F
MOISTURE IN FUEL, Wf
The combustible loss in burning wood or
bagasse is generally assumed to be zero. There- The total moisture in the products of com-
fore, if the high heating value and the ash con- bustion of either wood or bagasse has been de-
d
I\DB
.,(.
-lm.l
C-18

I
COMBUSTION
Combustion Cakulatlons by Graphic Methods

Iu Solid Line Was Used for C u r v e s i l


on Figure 18
Solid Line Was Used for Curves B
on Figure 18
cn'
.-? 750

3 a -0
650
0 Wood ??> 0 Wood
.
$600 a Bagasse
.-
c4 8
a Bagasse

0 18 1
0 10 20 30 40
in Wood or Bagasse,DryorAs Fired In Wood or Bagasse.DryorAs Fired
Hz + 0.102 H2 - 0.1 0 2
L I I I
Fig. 76. Moisture of theoretical air Fig. 17. Variation of theoretical CO2

noted by the symbol Wfi pounds per million When the ultimate analysis of wood or
Btu. It is the sum of W,, the moisture originally bagasse as fired is known, as well as the high
in the fuel and Wh, the water formed from the heating value, W, may be read directly from
combustion of hydrogen. Curves D and W,, from Curves C of Fig. 18.

EXAMPLE
Assume that saw-mill refuse from Western hemlock, con- 4. Total Products, P. From Eq. 4, P = F + CA = 255 + 1x
taining 55-percent moisture as fired and having the ultimate 1040 = 1295 lb per million Btu.
analysis shown in Table III,is burned with 45-percent excess 5, ~~i~~~~~in ~ iwa. ~ F~~~
, Eq. 5 , W, = 0.013A = 0.013
air. Then x 1040 = 14 lb per million Btu.
of Table 111 from the +
the ash and the high heating value
to the as-fired condition, or, ash
6. Moisture from Fuel, Wf. The total moisture in the prod-
ucts of combustion of wood, w,, is the sum of w,, the mois-
= 2.2 (x!3) = 1.0
ture in the wood as fired, and Wh, the water formed by its
100 combustion. Since the wood contains .%-percent moisture
percent as fired and as fired and its high heating value as determined for F is
3880 Btu per lb, from Curves D of Fig. 18, W, = 142 lb per
HHV = 8620 )-( = 3880 Btu per lb million Btu. Next, convert the percent hydrogen in Table
I11 from the dry to the as-fired basis, or
as fired. With these values for ash and HHV, read from Fig. 1,
F = 255 lb per million Btu.
2. Atmospheric Air, A. Calculate the ratio
Hz = 5.8 (w) = 2.6 percent

as fired, and with a high heating value of 3880 Btu read from
[ H? +'O.l, ] =
Curves C, Fig. 18 Wh = 60 lb per million Btu. Then
W, = W, + W h = 142 + 60 = 202 Ib per million Btu
7. Dry Gas, Pd. From Eq. 6, Pd = P - (LV. + Wd = 1295 -
[5.8 + ? f X 41.41 = 5'07 (14 + 202) = 1079 lb per million Btu.
and with this ratio read from Curves A, Fig. 18, for 45- Percent C02 in products. Compute the ratio
percent excess air, A = 1040 lb per million Btu.
50.4
3. Unburned Combustible Factor, C. The usual assump-
tion when burning wood in steam boiler furnaces is that the
]
[H: - E.l 0. = [5.8 - 0.1 X 11.4 ] = 30'4

combustible loss is zero; consequently C in Eqs. 3 and 1 and for 45-percent excess air read On Curves B, Fig'

may be taken as I. COZ = 14.2 percent.

diesel-engine oils, gas oils, kerosene, and gaso-


FUEL OILS line. As they all have a common source, the
The fuel oils ordinarily burned in steam- constituents of their analyses are the same, al-
generating units are derivatives of petroleum though the relative quantity of each varies. De
comprising the so-called "Bunker" grades, Baufre's representative tabulation in his article
COYBVSIION
'kombustion &lculations by Graphic Methods

- 21
1500 - 20
A
1400 - 19

1300 -
c ,-
H2 + 0.1 OP
E'
2 18
>"
.-
L
LL

0 10 20 30 40 50 60 70 0 10 20 30 40 50 60 70
Oh Excess Air % Excess Air

HHV, 1000 Btu/Lb As Fired HHV, 1000 Btu/Lb As Fired

Fig. 18; Combustion characteristicsof wood and bagasse


.. - ~&OYB1]STION
Combustion Calculations by Graphic Methods

on "Typical Solid and Liquid Fuels"3 shows


that the combustible fraction chiefly consists of
carbon and hydrogen with small amounts of wllorc,:
sulfur. Negligible percentages of nitrogen and WI, moisture from combustion of H2,
=
oxygen as well as water and sediment are also lb1106 Btu fired
frequently found. De Baufre's table is, in part, = hydrogen in fuel, % b y weight
reproduced as Table V. 1 1 1 IV = high (gross) heat value of fuel, Btullb
The calculated atmospheric air, A, in lbs per (12)
million Btu as fired and the percent CO, in the
products, both for zero excess air, are also tabu-
PERCENT CO2 IN PRODUCTS
lated for the different oils.
For commercial furnaces, Bunker C oil is fre- (:llrves B of Fig. 19 offer a convenient way of
quently specified. This term has come to be (I(rl(!l.~ninin~ the percent CO, by volume in the
applied to heavier fuel oils having a viscosity ( I v ~,rnductsof combustion of fuel oil, for any
from 100 to 300 S.S.F. (Saybolt seconds furol) villlrc, of ejtcess air from zero to 100 percent.
at 122F. Bunker C oil roughly corresponds to ( :11rvc:s B are plotted so that CO, values may be
No. 6 fuel oil in "Commercial Standard for Fuel 01b l i l i 11ed after calculating the ratio ClHp from
Oils" by the Bureau of Standards. Il\t! 11IIimate analysis of the fuel.

FUEL IN PRODUCTS, F EXAMPLE


A911111110 n fuel oil with the typical analysis given in Table
Refer to'Fig. 1,or calculate F directly from V 11111 I 11111 with 10-percent excess air. Then,
1 I I I 1 . From Fig. 1 for a high heat value of 18.500 BtU
1,000,000 I l l r f ' I I I I I I I I I O-percentash read F = 54lb per million Btu.

= HHV 2 . Altttospheric +r, A. From Curve A, Fig. 19, read


A - 11x5 II) per million Btu.
:I+I In1111rnedCombustible. Inthe combustion of fuel oils in
~1lllll11111r~ I,oilerfurnaces, it is generally assumed that there
'9 11(1( (~l~~llustibleheat 1oss.Therefore CinEq. 3 is equal to 1.
ATMOSPHERIC AIR, A 4. 'L'olrtl Products, P. From Eq. 4, P = CA + F = 1 x
"27 1 54 = 879 lb per million Btu.
The atmospheric air in pounds per million 54 M ~ i ~ t u in r e Air, Wo. From Eq. 5, W, = 0.013 (A) =
Btu as fired may be taken from Curve A of Fig. ().(I 1 :l(1125)= 11lb per million Btu.
Moln~urcfrom Fuel, W f . Since W, = 0, from Curves C,
19 for any value of excess air up to 100 percent. l ' l ~ . I'J,lor a high heat value of 18,500 Btullb and Hzof 11.5
The values obtained are averages for a wide I ) l t l c . r r l t l , rand W, = LV, = 56lb per million Btu.
range of fuel oils; no chemical analysis is ~ , I ) ~ ) ' ( ; J I S , P ~F/ 1. ~ ) m E q . 6 , P ~ = P - O i V ~ + W , ) = 8 7 9 - ( 1 1
necessary in using Curve A. "'I) - 012 Ib per million Btu. '

11, I'ct11.on1 C 0 2 in products. From Curves B, Fig. 19, for


I f )I l ~ trnt t c?xcessairanda M , r a t i o of 7.5, read CO? = 14.4
TOTAL PRODUCTS, P ll~fll ltlll,

The weight of the products of combustion in


pounds per million Btu as fired is given by
P = F + CA = F + A, where C, the combust- NATURAL GAS
ible-loss correction, is usually taken as 1.
Cll;~racteristicsof typical natural gases are
MOISTURE IN FUEL, Wt K ~ V ~ ? in
II Table VI, with the volumetric heating
v;lllrr, on a moisture-free basis.
For fuel oil use curve group C of Fig. 19, I:rom the standpoint of combustion calcula-
where W, is merely the moisture from hydro- ~ ~ O I , Hit, is important to remember that the terms
gen, and Wn is determined from Eq. 12. (fry o r wet as commonly applied to natural gas
COYWmON
Combu8Uon Calculations by Graphic Methods

700 1 I I I I I I ] - 7
0 10 20 30 40 50 60 70 0 10 20 30 40 50. 60 70
O/O Excess Air O/O Excess Air

I I I I I I I I I I
18 19 20 21 22
HHV,1000 Btu/Lb

Fig. 19. Combustion characteristics of fuel oil


, . COMBUSTION
Combustion Calculations by Graphic Methods

Tible V. Characteristics of Typical Liquid Fuels


A at Zero COz at
HHV, - .Excess Air, Zero Excess
" API %C %HZ %S % N2 %0z BtdLb -Ll1!10~Btu Air, %
Gasoline 60 85.0 14.8 ... 0.1 0.1 20,200 746
Kerosene 45 85.0 14.0 ... 0.5 0.5 19,900 742
Gas oil 30 85.0 12.8 0.8 0.7 0.7 19,300 745
Fuel oil 15 85.5 11.5 1.6 0.7 0.7 18,500 758

Table Vl. Characteristics of Typical Natural Gases at 60F and 30 In. Hg, Dry
COz at
-HHV - A a t Zero Zero
%by Volume Density, Btd Btul Excess Air, Excess
C02 N2 HIS CH4 C2H6 CJHB C4H1o CSHIZ LblCuFt CuFt** Lb Lbllo6 Btu Air, %

.I11 hydrocarbons heavier than CSH,*tvere assumed to be CJH,,for combustion calculations.


" If gas is saturated with moisture at 60Fand 30. in. Hg, reduce by 1.74%.

refer to its gasoline vapor, and not to its sume the standard 60F, when its actual
moisture content. In fact, the only time natural temperature is not reported.
gas has any moisture at its point of origin is
MOISTURE
when it is next to salt water. But this is a rela-
tively unusual occurrence. As already noted, the only time that natural
gas can have any moisture on leaving a well is
TEMPERATURE when it previously has lain in contact with salt
The temperature of natural gas as it issues water. It may then be considered saturated wi+
from the ground is dependent on the depth of moisture at its temperature in the well.
the well and may vary from 32 to 165F. The However, gas which is delivered from a
general rule among geologists is to assume an pipeline has often been "rehydrated," that is,
increase in temperature of 1F for every 50 feet saturated with water vapor by means of steam
in depth, although this rule will not always jets to lower the cost of maintaining pipe gas-
check with actual measurements taken in the kets. Since the steam is ordinarily added to the
field. gas in the high-pressure line, when the pres-
It is also apparent that gas which has flowed sure is lowered for local distribution, the rela-
through many miles of pipeline will have what- tive humidity of natural gas will also drop. Still
ever ambient air temperature prevails in the lo- another complication is introduced when a wet
cality where it is burned, most probably from displacement meter is employed to measure
40 to 80F. In combustion calculations for natu- the gas consumption. In this meter, the gas may
ral gas, it is deemed sufficiently accurate to as- be saturated with water.
COrnrnON
Combustion&IcuIations by Graphic Methods

In view of the variable and uncertain Vol. cu A Density of Weight


moisture content in natural gas, and in the ab- % by constituent constituent, lblcu A
sence of more definite determinations, it has Vol. Icu A fuel lblcu ft fuel
become practice i n industry to assume natural CO? 5.50 0.0550 X0.1170
=0.00644
gas to be dry at 60F and 30 in. Hg. Ha 7.00 0.0700 x0.09109
=0.00638
CH, 77.73 0.7773 x0.04246
=0.03300
DENSITY
C2H6 5.56 0.0556 =0.00446
X0.08029
The density of a gaseous fuel may be ob- c&, 2.40 0.0240 X0.1196=0.00287
tained by adding the weights of the constit- C4HIo 1.18 0.0118 X0.1582=0.00187
uents in the fuel. The following is an example C a 1 2 0.63 0.0063 X0.1904=0.00120
of a density calculation for the natural gas Total = Density of Dry Gas =0.05622
listed first in Table VI.
Density of the individual constituents are gaseous fuels. Saturated hydrocarbons do not
taken from Table VII, which lists the "satu- unite directly with hydrogen; i.e., they are sta-
rated" and "unsaturated" or "illurninant" hy- ble in the presence of hydrogen, while unsat-
drocarbons that are most frequently found in urated hydrocarbons readily take on more

Table VII. Combustion Constants of Dry Gases at 60F and 30 In. Hg


Density
Chemical of Dry Gas, -HHV of Dry Gas -
Gas Formula LblCu Ft BtulCu Ft* BtulLb

Oxygen 02 0.08461 ... . . ,

Nitrogen (atmospheric)
Air
Carbon dioxide
Water vapor
Hydrogen
Hydrogen sulfide
Carbowmonoxide
Saturated Hydrocarbons;
Methane CHI 0.04246
Ethane c2& 0.08029
Propane WR 0.1196 2573 21.573
Butane C ~ I O 0.1582 3392 21.141
Pentane c&12 0.1904 4200 22.058
---

Unsaturated Hydrocarbons
or Illurninants;
Ethylene c&4 0.07421 1614
Propylene c:fi, 0.1110 2383
Butylene C ~ R 0.1480 3190
Pentylene c&10 0.1852 4000
Acetylene C2H2 0.06971 1488 21.344
Benzene c&6 0.2060 3930 19,068
Toluene c7H8 0.2431 4750 19.537
If gas is saturated with moisture at 60F and 30.0 in. Hg, reduce by 1.74%.
COMBUSTION
Combustion Cakulationsby Graphic Methods

hydrogen. The latter are also called illuminants


because they burn with a bright luminous Heat
flame, as distinguished from the saturated hy- Volume Heating Evolved
%by cum- Value, by Com-
drocarbons which have a blue flame. Volume, cu ft of B tul ponents,
Extreme accuracy-in calculations of density Dry Gas cu ft Btulcu ft
and heating value of gaseous fuels is not war-
ranted; the precise values of the individual HZS 7.00 0.0700 X 647 = 45
CHI 77.73 0.7773 x 1014 = 788
constituents continue to change as more accu-
rate experimental procedures are developed, C2H, 5.56 0.0556 X 1789 = 99
presenting somewhat of a "moving target." C3H8 2.40 0.0240 x 2573 = 62
C4H,o 1.18 0.0118 x 3392 = 40
Figs. 20 and 2 1 and Eq. 13 may be used
CjHlz 0.63 0.0063 x 4200 = 26
whenever it is desired to correct for moisture
Heating Value of Dry Gas = 1060
content or for a temperature higher than 60F.
Btulcu ft

dm
temperature and moisture content, refer to Fig.
dl = - + (D, + wJ
+

2 2 and Eq. 1-4.


Y
where:
dl = density of gas at temperature, t, lblcu ft
d,, = density of dry gas at 60F,lblcu ft
X and Y = correction factors read from Fig. 21
D, = dust content of gas, lblcu ft at
t temperature. O F The Btu per cubic foot calculated by the
\v, = entrained water found only in primary foregoing method will generally be lower than
gas, lblcu ft at t temperature, O F that determined by calorimeter because of the
(13) arbitrary grouping of hydrocarbons explained
before. For the same reason, the calculated
Before going to a great deal of refinement, density will also be lower than actual. It fol-
however, remember that the calculated gas lows that the Btu per pound, with which we are
density can be no more accurate than the vol- primarily concerned, is nearer to its actual
umetric analysis from which it is derived. A value when it is figured from the calculated Btu
natural-gas analysis which groups all hydro- per cubic foot and calculated density than
carbons as CH,and CzH6,or C2H6andCBHsmay when it is the ratio of the calorimeter Btu per
indicate a lower density than the actual value. cubic foot and the calculated density of the gas.

HEATING VALUE
;0.30
Gas Pressure,ln. Hg Abs.
As with all other gaseous fuels, it is custom- CJ
X
ary to compute the high heating value of natu-
ral gas, in Btu per cu ft at 60F and 30 in. Hg, by b 0.20
.c
0
adding together the heat evolved by the com- .o
bustible components reported in the gas analy-
sis. Thus, for a gas such as the first one in Table
20.10
VI, the procedure indicated below may be em-
ployed, using the heating values in Table VII. Z
The high heating value in Btu per pound is '
6
0 80 100 120 140 160
then obtained by dividing the Btu per cubic Dew Point of Gas," F
foot by the density at 60F and 30 in. Hg. To cor-
rect the Btu per pound for the effect of higher Fig. 20. Water vapor in gas
- COmUmON
Combustion Calculations by Graphic Methods

FUEL IN PRODUCTS, F No chemical analysis of natural gas is neces-


After determining the Btu per pound (HHV), sary to obtain atmospheric air from Curve A.
F, which is that portion of the fuel that reap- TOTAL PRODUCTS,p
pears in the products of combustion, is easily
The weight of the products of combustion in
read from Fig. 1.
pounds per million Btu as fired is given by
ATMOSPHERIC AIR, A P = F + CA, where C is a factor to correct-A for
The atmospheric air in pounds per million the combustible loss due to imperfect combus-
Btu as fired may be taken from Curve A of Fig. tion of the fuel. When burning natural gas, C is
23for any value of excess air up to 70 percent. assumed to be 1 for any properly designed fur-
As previously defined, the term atmospheric nace supplied with the correct amount of
air is used to designate air which contains excess air.
0.013 pound of water vapor per pound of MOISTURE FROM FUEL, W,
dry air, an arbitrary amount equivalent to 60 For the general case of a gaseous fuel, Wf is
percent relative humidity at 80F. The atmo- the sum of W,, the water vapor required to satu-
spheric air, A, may be corrected for temper- rate the fuel; W,, the entrained moisture; and
atures higher than 60F using Eq. 15. W,,, the water formed in burning the hydrogen
compounds in the fuel.
As explained before, natural gas is usually
assumed to be dry, and since it seldom carries
Note: If t =t 60F,the equation reduces to A, = A, re- any entrained moisture, the first two terms
gardless of the moisture and dust content. generally may be taken as zero. If the gas is not

Note: If the Gas Pressure, p-in.Hg, Is Other Than


30", Y As Read from Fig. 21 Must Be
Multiplied by the Ratio (30Ip) Before Being
Used in Eqs. 13,15,and 18.

Ws, Lb/Lb of Dry Gas Ws, Lb/Lp of Dry Gas


I I

Fig. 21. Density correction for use in Eq. 13


.. "
COmosrrON
Combustion Calculations by Graphk Mathods

dry, but contains w, pound of water vapor per


pound of dry fuel, the pounds of water vapor
per million Btu as fired are given by
Noto: [I' t = 60F, the equationreduces to (Wh)i = W I ,
r~jfi;~rdless
of the moisture and dust content.
(181

PERCENT CO2 IN PRODUCTS


Curvc:s C, Fig. 23, permit the determination
where HHV is the high heating value of the gas of tllo percent CO* (by volume) in the dry prod-
in Btu per pound as fired. Fig. 24 is a conve- ~ t of scombustion for zero excess air. 'They are
nient plot of Eq. 16. a plot of the following approximate equation.
The water produced by the combustion of
natural gas is given by equation 1 7 which fol- '%I (LII zero excess air) =
I:(),
lows.
-- 100
Wh = 47,300 X
+
188 0.88(5.5HZS - 8.5COz - N z )
(Hs + 2CH4 + 3C2H6 + 4C@8 + ~ C & I O+ 6CSH12) 6.(i.l I
(:O,+CH,+~C~H,+~C@,+~~,O+~C~H~~
Btulcu ft at 60F and 30 in. Hg, dry (19)
(17)
r .

111(:11, 11y means of guidelines D, the percent


For dry patural gas at 60F and 30 in. Hg,Wh C:O:! for ilny other excess air up to 70 percent
may be conveniently read from Curves B of Fig. may IN!read. However, it is not advisable to
23. When it is desired to correct Wh for higher ust: (:urves D for natural gases with a nitrogen
temperature and for moisture content, Eq. 18 Pcr(:(:~\Ii~ge of Over 40. This is particularly true
may be used. lligll values of excess air.

0 0.10 0.20 0.30


Ws, Lb/Lb of Dry Gas Ws, Lb/Lb of Dry Gas
I I
Fig. 22. Heating value corrections for use in Eq. 14
C0YI)USTION
Combustion Calculationsby Graphic Methods

' 600
500

4000 10 20 30 40 50 60 70
O
h Excess Air

\ (8.5 C0z + Nz) - (5.5 HzS) in Fuel I_

0 100 200 300


0
10 20 30 - 40 50 60 70
50
C02 + CH4 + 2CzHs + 3CsH8 + 4C4Ht0 OO
/ Excess Air
5CsHtz in Fuel, O
h by Volume As Fired

Fig. 23. Combustion characteristics of natural gas


4,
COMBUSTION
Combustion Calculations by Graphic Methods

EXAMPLE
gas is higher than that of refinery gas, as is also
Assume a dry natural gas at 60F and 30 in. Hg to have
its carbon monoxide content.
the typical analysis listed first in Table VI and to be DENSITY
burned with 10-percent excess air. Then In the section on natural gas, a method was
1. Fuel, F. For a high heat value--of 18,880 Btu per lb,
refer to Fig. 1 and from it read F = 531b per million Btu. outlined for calculating the density of a gas-
2. Atmospheric Air, A. From Curve A, Fig. 23, for 10- eous fuel, given its analysis by volume. The
percent excess air read A = 8071b per million Btu. same method can be used to find the density of
3. Unburned Combustible. The general assumption refinery gas, or oil gas, either at 60F or at a
when burning natural gas in stationary boiler furnaces is higher temperature.
that the combustible loss is zero. Consequently, C in Eqs.
3 and 4 may be taken as 1. No correction for gas pressure other than the
4. Total Products, P. From Eq. 4, P = F + CA = 53 + 1 x standard 30 in. Hg is required in the calculation
807 = 860 lb per million Btu. of density, because invariably the fuel is
5. Moisture in Air, Wa. 'From Eq. 5. FV, = 0.013A = burned in a furnace which is at atmospheric
0.013 x 807 = 10 lb per million Btu.
6. Moisture from Fuel, Wf. Since W , ,the entrained
pressure. Table VIII indicates that the density
moisture, is zero and W,. the saturation moisture, is neg- of oil gas is considerably lower than that of re-
ligible, from Curves B, Fig. 23, for a high heating value of finery gas.
1061 Btu per cu ft and H2S + 2CH4 + X,H, + 4 C d 8 +
5CJ-IlO+ CJ-I12 = 7.0 + 135.5 + 16.7 + 9.6 + 5.9 + 3.8 = HEATING VALUE
198.5 percent by volume. read W f= Wh = 88 Ib per million
Btu. The heating value in Btu per cu ft is com-
7. Dry Gas, Pd. From Eq. 6, Pd = P - (W,, + Wf)= 860 - puted as set forth in the section on natural gas,
(10+ 88) = 762 lb per million Btu. with appropriate correction factors for temper-
8. Percent C0z in Products. For CO? + CH, + 2C&I, + ature and moisture as derived for blast-furnace
3C3HR+ 4Ca10 + 5C,@1?= 5.5 + 77.7 + 11.1 + 7.2 + 4.7 +
3.2 = 109.4 percent by volume and 8.5 CO? + N, - 5.5H2S
= 46.7 + 0 - 38.5 = 8.2 percent by volume. from Curves C,
Fig. 23, read 12.1 percent CO, at zero excess air. Follow-
ing Curves D as guidelines to 10-percent excess air, read Ws, LbILb of Dry Fuel Gas
CO, = 10.9percent.

REFINERY AND OIL GAS


The range in composition for refinery gas and
oil gas is shown in Table VIII. Refinery gas is
predominantly made up of saturated gases of
low boiling point, such as methane (CH,),
ethane (C2H6),propane (C3H,), butane (C4H10),
and pentane (C2H12) with small amounts of il-
luminants. Minor quantities of carbon dioxide
(C02),carbon monoxide (CO), and hydrogen
(Hz)may also be present with oxygen (02) and
nitrogen (N2) introduced to lower the hy-
drocarbon vapor pressure, in some cracking
processes. If the original crudes contained sul-
fur, the ensuing gases include hydrogen sul-
fide (H2S)unless the sulfur compounds have 1 2 4 681015 25
been removed by purifying operations. In Table HHV,lo3Btu/Lb As Fired
VIII, the last two analyses represent oil gas,
whereas the others are representative of refin-
ery gas. Note that the hydrogen content of oil Fig. 24. Water vapor in fuel gas
C0YI)WSTION
ComburUon CIlculationsby Graphic Methods
.-

gas. The Btu per pound is the ratio of Btu per cu through the calculated points on this figure
ft and the density. was used as the basis for spacing Curves A of
Although there is no doubt that some refin- Fig. 26.
ery gases contain little or no moisture, others The atmospheric air as taken from Fig. 26 can
are saturated with it. The values in the table are be corrected for temperatures other than 60F
given on a dry basis. and for moisture content by employing Eq. 15.
FUEL IN PRODUCTS, F TOTAL PRODUCTS, P
With the Btu Per pound (HHV) already de- Knowing A and F, the total wet products
termined, it is only necessary to refer to Fig. 1 formed by combustion of refinery or oil gas can
for the value of F which may also be calculated be easily computed, in pounds per million ~ t u
directly from: fired, by the addition P = F + CA.
F = - lo6 MOISTURE FROM FUEL, W,
HHV The total amount of moisture in the products
of combustion, W f ,which is derived from the
fuel itself, is the summation of the entrained
ATMOSPHERIC AIR, A moisture W,, the water vapor held by the gas
The air required for combustion may be con- W,, and the water produced by burning hydro-
veniently read from Curves A of Fig. 26 for gen, or hydrogen compounds making up the
amounts of excess air up to 70 percent of the fuel, Wh.
theoretical requirements. Due to the relatively Unless the refinery gas has undergone a
large percentages of carbon monoxide and hy- scrubbing or washing operation to remove ob-
drogen present in some of the oil gases, the jectionable elements from the distillate, it con-
magnitude of A in Table VIII varies from 648 to tains hardly any entrained moisture. Water
725 lb per million Btu. The correlation of A at vapor, however, may be present in the gas not
zero excess air with the term (CO + Hd is only because of the purifying treatment, but
brought out by Fig. 25. The average line drawn due to water introduced into the system with

Table VIII. Characteristics of Typical Refinery and Oil Gases


at 60F and 30 In. Hg, Dry
COl at
-.HHV - A at Zero Zero
%by Volume Density, Btul Excess Air, Excess
0 2 NI C02 CO II2 HIS CH4 c1H6 CJHB 6H10* CsH12t C3H6$ LblCu Ft CUFt**BtuILb LbllO6 Btu Air, %

* Includes both iso-C4Hloandn-C4HIo, .,


-
t Includes all saturated hydrocarbons heavier than C5H12, also both iso-C5HI2andn-C5HI,
* Includes all illurninants.
" If gas is saturated with moistura at 60'F and 30 in. Hg, reduce by 1.74%.
COMBUSTION
Combustion Calculationsby Graphic Methods

the crude oil, or because of steam employed i n


EXAMPLE
the distillation process. If the gas contains W,
Assume a refinery gas of the typical analysis given on
lb of water vapor per Ib of dry fuel, W,can be de- the first line of Table VIII to be fired at a temperature of
termined from Fig.24. 60F with 10-percent excess air. Then
The water which is formed by combustion, 1. Fuel, F. With a fuel high heat value of 21,880 Btu per
Wh,can be read from Curves B of Fig. 26, which lb, refer to Fig. 1and obtain F = 46lb per million Btu.
2. Atmospheric Air, A. On Curves A, Fig. 26, for 10-
are a plot of the expression percent excess air and (CO + HZ)= 0, read A = 793 lb per
million Btu.
3. Unburned Combustible. When burning refinery gas
in boiler furnaces, it is customary to assume that there is
no unburned combustible loss, so that in Eqs. 3 and 4
~ C ~ HfI = Oa12 + 3C&6) C = 1.
Btulcu ft at 60F and 30 in. HE. dry 4. Total Products, P. Using Eq. 4, P = F +CA = 46 + 1 x
793 = 839lb per million Btu.
5. Moisture, in Air, W,. This item is calculated from Eq.
When, for more accuracy, it is required to cor- 5. W, = 0.013A = 0.013 X 793 = 10lb per million Btu.
rect Wh for the effect of temperature and mois- 6. Moisture from Fuel, Wf. The moisture content of re-
finery gas itself is generally negligible. The dvater formed
ture content, Eq. 18 can be utilized. by its combustion is taken from Curves B, Fig. 26. For a
PERCENT CO2 IN PRODUCTS high heat value of 1898 Btu per cu ft and H2S + 2CH, +
3 C a 8 + 4C3Hs + 5C4Hlo+ 6C&II2= 2.18 + 83.24 + 62.73 +
For zero excess air, the Con in the dry prod- 78.88 + 45.25 + 39.12 = 311.40 percent by volume, W, =
ucts of combustion is found with the aid of Wh = 78 lb per million Btu.
Curves C, (Fig. 26. These curves were drawn 7. Dry Gas, Pd. From Eq. 6, Pd = P - (W, + W,) = 839 -
from the approximate equation. (10 + 78) = 751 1b per million Btu.
8. Percent COz in Products. The C 0 2at zero excess air is
determined first. From curves C of Fig. 26, for CH, +
% C 0 2(at zero excess air) = 2CzHG + 3C3H9+ 4CaHlo + 5C&112 = 41.62 + 41.82 + 59.16
100 + 36.20 + 32.60 = 211.40 percent by volume, and N2 +
I88 - 1.88(N? + E O 2 + 3CO + Gas) 4C02 + 3C0 + C a B= 0.0 obtain 13.3 percent COz. With
"64 +CO? + C O + CH, + X2H6+ 3C&, + Curves D as guidelines and 10-percent excess air, then,
read C 0 2 = 12 percent.

The guide Curves D of Fig. 26 make it possi- COKE-OVEN GAS


ble to obtain the percent of COzin the products
for an excess-air value up to 70 percent. Representative analyses of several byproduct
coke-oven gases are given in Table IX. Note that
the volumetric heating value is based on the gas
750 - being moisture free, and that a correction must
be made for moisture of saturation, if the gas
has been washed and cooled.
It is important to have the correct calorific
?; 650 - value at 60F and 30 in. Hg for a given analy-
V) I
sis, since the method employed here relates I
< all combustion calculations to the heat liber- I

550- 1 I l l I I I I ated. Unfortunately, many analyses show the


0 10 20 30 40 50 60 70 80 heavier hydrocarbons grouped together as "il-
(CO+ Hz)in Fuel,%by Volume luminants." DeBaufre4 and others have sug-
gested taking the illurninants to be propylene,
C.JIs. While this assumption is valid in cal-
Fig. 25. Variation of theoretical air with (CO + HZ)in culating the Btu per cu ft, it will not give accu-
combustion of refineryand oil gas rate values of H20formed by combustion, and I
COMBUSTION
Combustion Calculations by Graphic Methods

HHV, Btu/Cu Ft at 60F

% Excess Air HZ+ HzS+ 2CH4 + 3CzH6 + 4CsHa + 5C4Hio + 6C5Hiz + 3C3Hs
% by Volume As Fired

Na+ 4COz + 3 C 0 + CsHs in Fuel

+
COz + CO + CH4 + 2CzHs 3C3Ha O/O Excess Air
+ 4C4Hto+ 5CsHlz+3C~HsIn Fuel,
O/O by Volume As Fired .:- -

-.

Fig. 26. Combustion characteristicsof refinery gas and oil gas


4' COMBUSTION
CombustionCalculations by Graphic Methods

the resulting heat balance will be in error. A No moisture correction is necessary, because F
complete gas analysis, including all hy- is determined to two significant figures only.
drocarbons, is, therefore, essential. To find the ATMOSPHERIC AIR, A
high heating value in Btu per lb accurately, di- The atmospheric air required for combustion
vide the Btu per cu ft by the fuel density. will vary with the carbon monoxide and hy-
DENSITY drogen content of the gas. A correlation of
The density of the gaseous fuel, in turn, may atmospheric air, A, at zero excess air with the
be obtained by adding the weights of the con- term (CO + Hz)is shown in Fig. 27. The atmo-
stituents in the fuel. The following tabulation is spheric air in lb per million Btu may be read
an example of density calculation for the typi- from the curve family A in Fig. 28. The spacing
cal coke-oven gas listed first in Table IX, the of these curves is based on the average line
density of the individual constituents being drawn in Fig. 27.
taken from Table VII. ' TOTAL PRODUCTS, P
Volume,
The weight of the products of combustion is
YO cu f? Density of Weight, calculated from P = F + CA.
by constituent1 constituent, lblcu f? MOISTURE FROM FUEL, Wf
volume cu ff fuel lblcu ft fuel
The moisture, W,, in a fuel gas saturated at
Cop 1.8 0.018 X 0.1170 =
60F may be neglected as it amounts to less than
O2 0.2 0.002 X 0.08461 =
2 lb per million Btu as fired. W h ,the water
N2 3.4 , 0.034 X 0.07439 =
formed by the combustion of hydrogen and the
CO 6.3 0.063 X 0.07404 = hydrocarbons present in the coke-oven gas, is
He 53.0 0.530 X 0.005327 =
obtained from Curves B, Fig. 28. Since W, is
C H 4 31.6 0.316 x 0.04246 =
neglected, W,, which is the total moisture in the
C2H, 2.7 0.027 X 0.07421 =
flue gases derived from the fuel, is equal to W,.
C&, 1.0 0.010 X 0.2060 = In the simple case of hydrogen, the volumet-
Total = Density of Dry Gas = ric chemical'equation for combustion is

The saturation pressure of water vapor at Hz+ = H20


60F is 0.52 in. Hg. If the gas is saturated with (23)
moisture at 60F and 30 in. Hg, then the partial
pressure of all its dry constituents is Eq. 23 shows that one volume of hydrogen
30.0 - 0.52 = 29.48 in. Hg. A density correc- combines with one-half volume of oxygen to
tion is made as follows. produce one volume of water. Similarly, one
volume of CH4will form, on burning, two vol-
umes of H,O, etc. Since a coke-oven gas may
Add to this the density of the water contain Hz, CH4,C2H4,and C&,, with the aid of
vapor (from the steam tables) 0.00083 Table VII it is seen that the total volume of H a
Density of saturated gas 0.03008 evolved by these constituents is proportional to
(H, + 2 CH, + 2 C2H4 + 3 C a 6 ) . The follow-
It can be seen that the density correction for
ing exact relation will convert the volume of
moisture content will be 1 percent.
H,O to lb per million Btu.
FUEL, F
The portion of the fuel which reappears in (Hz+ 2 C H 4 + 2 C2H4 + 3 C ~ B )
volatile form i n the products of combustion can Wh = 4 7 ' 3 0 0 ~ ft
t at
~~ ~ ~and 30 in. Hg,dry
60F
be read from Fig. 1 when HHV (Btu per 1b of (24)
fuel) is known. If HHV is not given, it is found -
by dividing the Btu per cu ft by the fuel density. which is also plotted as Curves B, Fig. 28.
COYBUSTION
CombustionCalculations by Graphic Methods

Fig. 27. Variation of theoretical air with (CO + Hz) in the percent COBin the dry products of combus-
combustion of coke-oven gas tion for any other value of excess air than zero.

EXAMPLE
Assume a coke-oven gas with the typical analysis of the
first gas listed in Table IX and saturated with moisture at
60Fand 30in. Hg to be burned with 10-percent excess air.
1. Heating Value. The high heat value given as 596 Btu
per cu ft must first be corrected for moisture content by
deducting 1.74 percent; 596 - 10 = 586 Btu per cu ft satu-
rated fuel. This value is divided by the fuel density
(neglecting the moisture correction) to obtain the approx-
imate Btu per lb.

1
586
HHV = -- 19,700Btullb
(CO+ H2) in Fuel,O/o by Volume 0.0298
:. 2. Fuel, F. For a high heat value of 19,700 Btd per lb, read
from Fig. I , F = 51 lb per million Btu.
3. Atmospheric Air, A. From Curves A, Fig. 28 for 10-
percent excess air and (CO +HZ) = 6.3 + 53.0 = 59.3,read A =
PERCENT CO2 IN PRODUCTS 742lb per million Btu.
There are many constituents in coke-oven 4. Unburned Combustible. For stationary boiler furnaces,
the general assumption when burning coke-oven gas is that
gas which on burning will evolve GO2.A sim- there is no combustible heat loss. Therefore, C in Eqs. 3 and 4
ple equation relating exactly the C02in the dry is equal to 1.
products of combustion to these constituents 5. Total Products, P. From Eq. 4, P = F + CA = 51 + 1x 742 =
793 lb per million Btu.
cannot be written, but the follo\ving equation is
6. Moisture in Air, Wa. From Eq. 5, W, = 0.013A = 0.013 x
sufficiently accurate for analyses which do not 742 = 101b per million Btu.
contain excessive amounts of N,or 02. 7. Moisture from Fuel, Wg. Since W, = 0, from Curves B.
Fig. 28, for a high heat value of 596 Btu per cu ft and H 2 = ZCH,
+ 2 C a 4 + x&I,= 53.0 + 63.2 + 5.4 + 3.0 = 124.6percent by
% C02(at zero excess air) = volume, read W, = Wh = 991b per million Btu.
---
I nn 8. Dry Gas, Pd. From Eq. 6, Pd = P - (Wa= MIg)= 793 - (10
0.695 x Btulcu ft at 60F and 30 in.Hg, dry + 99) = 6841b per million Btu.
1+
(100 + C,H4 + 5C&I,I - IH2 + N2) 9. Percent C02 in Products. For a heating value of 596 Btu
per cu ft and (100 + C 3 , + %&I,) - (HZ+ N2) = (100 + 2.7 +
5.0) - (53.0 + 3.4) = 51.3 percent by volume, from Curves C.
Fig. 28, read 11.1 percent C 0 2 at zero excess air. Following
Curves D as guidelines to 10-percent excess air, read CO, = 10
Curves C, Fig. 28, are a plot of Eq. 25, while percent.
Curves D serve as guidelines for determining

Table IX. Characteristicsof Typical Coke-Oven Gases at 60F and 30 In. Hg, Dry
COz at
H H V A at Zero Zero
% by Volume Density, Btd Excess Air, Excess
COl 0 2 N2 CO CH4 GH4 GH6 Lb/Cu Ft CU Ft* BtdLb Lb/106Btu Air,%

2.6 0.6 3.7 6.1 47.9 33.9 5.2 ... 0.0316 603 19,070 676 11.3
3.13 ... . . . 11.93 42.16 37.14 4.76 0.88 0.0359 663 18,500 684 - - 12._7
0.1 ... 2.4 6.8 27.7 50.0 13.0 ... 0.0393 829 21,100 700 12.3
0.75 ... 12.1 6.0 53.0 28.15 ... . .. 0.0291 477 16,390 668 9.4
If gas is saturated with moisture at 60F and 30 in. Hg, reduce by 1.74%.
B'
COMBUSRON
CombustionCalculaUons by Graphic Methods

Fuel HHV
BtufCu Ft, Sat. at 60F, 30.0" Hg
400 450 500
550

600
650
700
750
800
850
900

O/O Excess Air Hz + 2CH4 + 2CzH4 + 3CeHe


O/O by Volume As Fired

' (100 + CzH4 + 5CeHs) - (Hz + Nz)


O/O by Volume

900 800 700 600 500 400 0 10 20 30 40 50 60 70


HHV, Btu/Cu Ft O
h Excess Air

Fig. 28. Combustion characteristics of coke-oven gas


--
COMBUSTION
CombustionC.kulaUons by Graphic Methods

even a final, cleaning by means of dry sepa-


BLAST-FURNACE GAS rators. Its temperature is much higher than that
of washed gas and because of this it is capable
The range in composition of steel-plant blast- of holding much more moisture, since it will
furnace gas is given in Table X. Note that the contain all the water vapor that it had on leav-
volumetric heating value is based on the gas ing the blast furnace regardless of its degree of
being moisture free, and that a correction must cleaning. Using a dew point of 140F has been
be made for moisture of saturation. recommended for calculating the moisture in
MOISTURE FROM CLEANING unwashed gas, but it is obviously preferable to
In Chapter 2 , blast-furnace gas was classified know the actual dew point of a particular gas
as raw gas, gas that had a primary cleaning, than to assume it. Fig. 20, then, offers a conve-
or gas-that has had a final cleaning. For pur- nient curve for determining W,, the saturation
poses of combustion calculations, however, it moisture, for any dew-point temperature from
is more convenient to speak of rr-ashed and un- 60 to 160F. There is, of course,' no entrained
rtashed gas, and these will be the terms most water in unwashed gas.
frequently employed in the discussion which DENSITY
follows. The density of dry blast-furnace gas at 60F
Washed gas is blast-furnace gas that has gone (d,,) is easily computed from its volumetric
through either primary or final washers. It may analysis by the method explained in the section
be considered saturated with moisture at what- on gas, which assumes that the gas is clean. The
ever temperature it leaves the washer because true density (d,) is obtained by correcting d6of0r
of the intimate contact between cooling water the actual temperature (t), moisture content,
and hot gas. If the gas has only been given a and dust according to Eq. 13.
primary wash, it will contain about 4 grains As an example, assume that the blast-furnace
b

(0.00057 lb per standard cubic foot) of en- gas in the first line of Table X is unwashed and
trained moisture in addition to the water vapor goes to a burner with 15 grains of dust, at 500F
required to saturate it. This entrained moisture with a dew point of 140F and at a pressure of
is carried along by the gas in the form of sus- 30 in. Hg. What is its actual density if there is
pended droplets which are effectively removed no entrained moisture?
by a final cleaner. For a saturation temperature of 140F and a
Unwashed gas, on the other hand, may exist pressure of 30 in. Hg, read from Fig. 20,
as raw gas or as gas that has had a primary, or w, = 0.1521b per 1b of dry gas, and from Fig. 2 1

Table X. Characteristics of Typical Blast-FurnaceGases


at 60F and 30 In. Hg, Dry
A at Zero COZat
% by Volume Density, -HHV - Excess Air, Zero Excess
NZ CO H2 CH4 LblCu Ft BtulCu Ft* BNLb Lb1iO6 Btu Air, %

90.1 1150 576


575
577
579
576
631

* If gas is saturated with moisture at 60and 30.0 in. Hg, reduce by 1.74%
COMBmRON
Combustion Calculations by Graphic Methods

Volume, Density -
the presence of dust will not influence the heat-
%by cum IWcu fl ing value of blast-furnace gas.
Volume, cu fl at 60F, Weight It should also be clear that any increase in the
Dry of Gas.. Dry2 lWcu fl
temperature of the gas above 60F will enhance
CO, 14.5 - 0.145 ' X 0.1170 = 0.01697
its heating value by an amount equal to the sen-
Nz 57.5 0.575 X 0.07439 = 0.04277
C O 25.0 0.250 X 0.07404 = 0.01851
sible heat of the gas above 60F.
H2 3.0 0.030
Furthermore, assume, as an example, that an
unwashed gas is saturated at 140F.It will then
Density of Clean Dry Gas at 60F = 0.07841
have 0.152 lb of moisture for each pound of dry
gas. As an inert vapor, this moisture will re-
duce the combustible fraction and, therefore,
obtain X = 0.0115 and Y = 2.29. Then the den-
the heating value of blast-furnace gas, at the
sity of clean gas at 500F and a dew point of
same time that it augments the heating value by
140F will be expressed as
the sensible heat due to its high temperature.
Having obtained the Btu per pound (HHV)-
d,,--+ X - 0.0784 + 0.0115-- 0.0393lblcu ft for the dry gas at 60F, figure the Btu per pou'nd
Y 2.29 (HHV),, at its true temperature, t , and moisture
15 0.0393 content using Eq. 14.
\Veight of dust in gas = -x --- 0.0011 lblcu ft '

7000 0.0784 Knowing the actual dew point of this gas, w,


-
is read from Fig. 20, and M and N from Fig. 22
for use in Eq. 14.
HEATING VALUE FUEL, F
The Btu per cubic foot of clean and dry blast-
After determining the true Btu per pound, F,
furnace gas at 60F, may be calculated from its
which is that portion of the fuel that shows up
analysis and the heating value of its combusti-
in the products of combustion, may be read
ble components as obtained from Table X. The
from Fig. 1. Any dust in unwashed gas may be
Btu per cubic foot thus determined, when di-
treated as ash in coal or sediment in oil.
vided by the density at 60F, will give the Btu
per pound (HHV)N,. ATMOSPHERIC AIR, A
However, in calculating the true heating The air required for the combustion of blast-
value (HHV), of a gas as fired, we must again furnace gas is a function of the ratio CH,/(CO +
take into account its dust content, its tempera- Hz) where CH,, CO, and H2represent the per-
ture, and its moisture content. centage fractions by volume of methane, car-
The dust in blast-furnace gas is made up bon monoxide, and hydrogen in the fuel.
chiefly of particles of iron ore, limestone, and For clean, dry, blast-furnace gas at 60F, the
coke. Since its structure is sandy or granular, atmospheric air, A, in pounds per million Btu,
there is reason to believe that iron ore is the may be read from Curves A in Fig. 29 for any
main component in this mixture, since its value of excess air up to 70 percent.
structure is sandy or granular, and is, therefore, This value must be corrected for the dust and
more easily lifted by the blast than coke or moisture content and temperature of the actual
limestone which comes in relatively large blast-furnace gas. After finding A from Fig. 29
lumps. When the dust burns, the coke in it may and the heating value and density as explained
be thought of as supplying the heat required to before, the true mass of atmospheric air per mil-
reduce both ore and limestone. In the absence lion Btu as fired is calculated using Eq. 15.
of actual tests showing the calorific value of the
dust, it may be assumed that the heat evolved TOTAL PRODUCTS, P
by the coke is just equal to that required to re- As with other fuels previously discussed, the
duce the ore and the limestone. If this is true, weight of the products of combustion is given
-
COYllDSRON
Combustion C8lculations by Graphic Methods

by P = F + CA lb per million Btu as fired. This readings from Curves B must be multiplied by
equation holds true for either washed or un- the same factor used in correcting the atmo-
washed gas, provided F and A are calculated as spheric air, to obtain the true moisture (WJf in
explained in the foregoing sections. pounds per million Btu as fired. This factor is
MOISTURE FROM FUEL, W, calculated using Eq. 18.
The next moisture source called "entrained
As defined in the first section, Wfis the total moisture" is carried along by the gas in the
amount of water vapor present in the products form of suspended globules. Designated as W,,
of combustion. it is considered only when the gas has been
In blast-furnace gas, three different moisture given a primary wash and averages 7 1b per mil-
sources eventually become part of the prod- lion Btu.
ucts. First, there is the moisture formed in The last source is in the water vapor required
burning the fuel and previously designated by to saturate the blast-furnace gas at any tempera-
Wk.Equation 26 shows that for clean gas at 60F ture from 60F up, as the case may be, and is
designated as W,. For blast-furnace gas satu-
47,300(HI+ 2CH4) rated with moisture at 60F, 8 lb per million Btu
W'l = Btulcu ft at 60F and 30 in.Hg,dry may be assumed for W, without serious error.
(26) This moisture must be considered separately
fromW,,and W,inaheatbalancesince itexistsas
Curves B of Fig. 29 are plotted from this avapor requiring no latent heat of vaporization.
equation. Of course, Mr, must be subtracted from the
If the actual gas is at a temperature higher total products, along with Wkand W,, to obtain
than 60F and contains dust and moisture, the the dry gas.

EXAMPLE

Assume a blast-furnace gas with the typical analysis of 4. Atmospheric Air, A. From Curves A, Fig. 29, for
the first gas listed in Table X and saturated with moisture CH,I(CO + Hz) = 0 and for 15-percent excess air, read
of 60F and burned with 15-percent excess air after going A = 662 lb per million Btu.
through a primary washer. 5. Unburned Combustible. The general assumption when
1. Density. The density given as 0.0779 lb per cu ft for burning blast-furnace gas in stationary boiler furnaces is that
the dry gas must first be corrected for moisture content. the combustible loss is zero. Consequently, C in Eqs. 3 and 4
The saturation moisture for a dew point of 60F is read from may be taken as 1.
Fig. 20 a s W, = 0.02 lb moisture per lb of dry gas. The val- 6. Total Products, P. From Eq. 4, P = F + CA = 878 + 1 X
ues of X and Y are read from Fig. 21 for W, = 0.02 and a 662 = 15401b per million Btu.
temperature of 60F bs X = 0.0015 and Y = 1.03. The en- 7. Moisture in Air, Wa. From Eq. 5, I\', = 0.013.4 =
trained moisture in a gas given a primary wash is assumed 0.013 x 662 = 9 lb per million Btu.
as w, = 0.00057 lb per standard cu ft.
8. Moisture from Fuel, Wf. As pointed out i n the text for a
We can now substitute into Eq. 13 gas that has passed through a primary washer, \Y, = 7 lb per
million Btu. Curves B, Fig. 29, show W h= 1 6 lb per million
Btu for a blast-furnace gas with a high heat value of 90.1 Btu
per cu ft and Hz + 2 CH, = 3 + 0 = 3 percent by volume as
(0 + 0.00057) = 0.0771 + (0.00057) = 0.0777 lblcu ft. fired. Therefore, MI, = W, + W, + Wh = 8 r 7 + 16 = 31 1b
per million Btu.
2. Heating Value. The high heat value given as 90.1 Btu per 9. Dry Gas, Pd. Fmm Eq. 6, Pd = P - (\Vo + \V,) = 1540 -
cu ft is first corrected for moisture content by deducting 1.74 (9 + 31) = 1500lb per million Btu.
percent; 90.1 - 1.6 = 88.5 Btu per cu ft saturated fuel. This 10. Percent C0z in Products. From the fuel analysis, calcu-
value is divided by the density to obtain the Btu per lb. late CO2 + CO + CH,= 14.5 + 25.0 + 0 = 39.5percent by v0l-
HHV 2 88.510.0777 = 1139Btu per lb. - +
u m e a n d H z + 2 C 0 +8CH4=3 +2 X25 + 8 X O =53percent
3. Fuel, F. For a high heat value of 1 1 3 9 ~ t uper lb and a by volume, and from Curves C, Fig. 29 read 26.4 percent COz
negligible amount of dust refer to Fig. 1and read F = 878 lb at zero excess air. Following Curves D as guidelines to 15-
per million Btu. .. percent excess air, read C02 = 24.8 percent.
1200 -
HHV,
Btu/Cu Ft of Dry Gas
80 100 120
2 1000 -

10 20 30 40 50 60 70
% Excess Air Hz f 2CH4,% by Volume As Fired

H2 + 2 C 0 + 8CH4, O/O by Volume As Fired

30 32 34 36 38 40 42 0 10 20 30 40 50 60 70
COz + CO + CH4 in Fuel, Oh Excess Air
O/O by Volume As F~red

Fig. 29. Combustion characteristics of blast-furnace gas


.-
COUBUSTXON
Combustion Calculationsby Graphic Methods

PERCENT C02 IN PRODUCTS % Con - lOO(CO? + C O + CH,)


Curves C and D of Fig. 29 offer a convenient
(at zero excess air) - 100 + 0 . 9 4 ( ~ ,+ 2 c 0 + a m , )
method to obtain the percent of C02in the dry
products of combustion resulting from the where Hz,C02,CO, and CH, are the symbols for
combustion of either washed or unwashed percent by volume of these constituents in the
blast-furnace gas, provided the dry volumetric fuel. This COz must not be confused with the
analysis of the gas is known. Curves C are plot- percent carbon dioxide in the dry products of
ted from the following equation: combustion.

REFERENCES
1 W. L. De Baufre, "Composition and eat in^ Value of 3 W. L. De Baufre, "Typical Solid and Liquid Fuels,"Com-
Fuels,'' Combustion, 2(11):29-35,May 1931. bustion, 3(2): 23-31, Aug. 1931.
W. S. Patterson, "Calculations of Air Requirements and W. L. De Baufre, "Typical Gaseous Fuels," Combustion,
Combustion Products of U.S. Coals by Simple Graphical 3(6):26-33, Dec. 1931.
Methods," Combustion, 3(8):9-17, Feb. 1932.
Appendix D. Steam Tables
The following tables are in accordance with ment of formulati.ons of the thermodynamic
those adopted by The Sixth International Con- properties of steain is presented in Appendix D,
ference on the Properties of-Steam and pub- Combustion Engineering, 1967 edition. It de-
lished in the 1967 ASME Steam Tables and the scribes the early research begun on steam prop-
1977 ASME Steam Tables in SI (Metric) Units by erties in 1741 and fully covers the proceedings of
the American Society of Mechanical En,'oineers. the Sixth International Conference on the Prop-
Combustion Engineering, Inc., has permission erties of Steam held between 1958 and 1963.
to reprint the tables in this form. For a copy of
REFERENCE STATE
Steam Tables, with a convenient Molier diagram
included, write to C-E Power Systems, Combus- The liquid phase at the triple point of water
tion Engineering, Inc., 1000 Prospect Hill Rd., substance is the state for which the specific in-
Windsor, CT 06095. ternal energy and the specific entropy are each
A thorough historical account of the develop- made exactly zero.

U.S. CUSTOMARY UNITS

Table I. Saturated Steam: Temperature Table (32 to 705.47OF)


Temp. Abs. Press. vol., - -- --
Enthalpy, Btullbm Entropy, BtullbmR Temp.
-
Deg. Lb,l Sat. Sat. Sat. Sat. Sat. Sat. Deg .
, Fahr. Sq. In. Liquid Evap. Vapor Liquid Evap. Vapor Liquid Evap. Vapor Fahr.
t P "I "I, ",, h, h,,, h., st SIC, S,, t
CO~mnON
Steam Tables

Table I.Saturated Steam: Temperature Table -Continued I

Temp. Abs. Press. Specific""!.y?l!!m . - - - ---


-- -Enthalpy, Btullbm-- Entropy, BtuIlbmR -
Temp.
Deg. Lb,l Sat. Sat. Sat. Sat. Sat. Sat. Deg.
Fahr. Sq. In. Liquid Evap. Vapor Liquid Evap. Vapor Liquid Evap. Vapor Fahr.
t P v, "fit h, h,,, h,, SI S,,, S., t
COMBUSTION
Steam Tables

Table I.Saturated Steam: Temperature Table -Continued

Temp. *bs, Presc


- Specific Voi., ft'llbm - -- Enthalpy,
- -- -- .
. -- --
-Btullbm - -- Entropy, BtullbmR- Temp.
-
Deg. Lb,l Sat. Sat. Sat. Sat. Sat. Sat. Deg .
Fahr. Sq. In. Liquid Evap. Vapor Liquid Evap. Vapor Liquid Evap. Vapor Fahr.
t P v, "1 I v, h, h,,, ha, st S,,, s,, t
COMBUSTION
Steam Tables

-- -

Table I.Saturated Steam: Temperature Table -Continued

Temp. Abs. Press. Specific Vol., A3nbm Enthalpy, Btullbm Entropy, BtullbmR Temp.
Deg. Lb,l Sat. Sat. Sat. Sat. Sat. Sat. Deg.
Fahr. Sq. In. Liquid Evap. Vapor Liquid Evap. Vapor Liquid Evap. Vapor Fahr.
t P VI. Ye vg h/ h, ha! Sr Se SP t
COMBUSTION
Steam Tables

Table I.Saturated Steam: Temperature Table -Continued


Temp. *bs. press. Specific Vol., A3/lbm Enthalpy, Btullbm Temp.
-
Deg . LbJ/ Sat. Sat. Sat. Sat. Sat. Sat. Deg.
Fahr. Sq. In. Liquid Evap. Vapor Liquid Evap. Vapor Liquid Evap. Vapor Fahr.
t P VJ Vf,l v.l hl. h,, h,! Sf Sljl Sf,
t

'The states shown are metastable


Stcum Tables

Table 11. Saturated Steam: Pressure Table


Specific Vol., ft3/lbm Enthalpy, Btullbm
Entropy
AbsPress. Temp Sat. Sat. Sat. Sat. Sat Sat. Abs Press.
LblSqIn. Fahr Liquid Evap Vapor Liquid Evap Vapor Liquid Evap Vapor LbISqIn.
P t VI VIP vo h, IS h. SI 51" SO P
COMBUSllON
Steam Tables

Table 11. Saturated Steam: Pressure Table -Continued ..

Specific Vol., ft3/lbm


- - .
Enthalpy, Btullbm - _ .-Entropy, BtullbmR
-.- -- -
AbsPress. Temp Sat. Sat. Sat. Sat. Sat. Sat. Abs Press.
LblSq In. Fahr Liquid Evap Vapor Liquid Evap Vapor Liquid Evap Vapor LblSqh.
P t VI VIS vv h~ hfi hv s, sh s. P

'Critical pressure
CO~vmON
Steam Tables

Table 111. Superheated Steam


Abs Press. Temperature - Degrees Fahrenheit
LblSq In. Sat. Sat.
(Sat.Temp) M'ater Steam 200 250 300 350 400 450 500 600 700 800 900

Sh 98.26 148.26198.26 248.26 298.26 348.26 398.26498.26 598.26 698.26798.26


1 v0.01614 333.6 392.5 422.4 452.3 482.1 511.9 541.7 571.5 631.1 690.7 750.3 809.8
(101.74)h 69.73 1105.81150.2 1172.91195.7 1218.7 1241.8 1265.1 1288.61336.1 1384.5 1433.71483.8
s 0.1326 1.97812.0509 2.0841 2.1152 2.1445 2.1722 2.1985 2.2237 2.2708 2.3144 2.35512.3934

Sh 25.56 75.56 125.56 175.56 225.56 325.56425.56525.56625.56


45 ~0.01721 9.399 9.77710.49711.201 11.892 12.577 13.932 15.276 16.614 17.950
(274.44)h 243.49 1172.1 1185.41210.4 1235.71260.2 1284.6 1333.3 1382.3 1431.91482.3
s 0.4021 1.6671 1.68491.71731.7471 1.7748 1.8010 1.8492 1.8934 1.93451.9730
Sh = degrees of superheat. OF h = enthalpy. Btullbm
v = specific volume, cu ftllbm s = entropy, BtuIlbmR
COMBUSTION
Steam Tables

- --

Table 111. Superheated Steam


- -
-Continued
Abs Press. Temperature - Degrees Fahrenheit
LblSq In. Sat. - Sat. '-

(Sat. Temp) Water Steam

Abs Press. Temperature - Degrees Fahrenheit


LblSqIn. Sat. Sat.
(Sat.Temp) Water Steam 350 400 450 500 550 600 700 800 900 1000 1100

Sh 37.96 87.96 137.96 187.96 237.96 287.96 387.96 487.96 587.96 687.96 787.96
80 ~ 0 . 0 1 7 5 7 5.471 5.801 6.218 6.622 7.018 7.408 7.794 8.560 9.319 10.075 10.82911.581
(312.04) h 282.15 1183.1 1204.0 1230.5 1256.1 1281.3 1306.2 1330.9 1380.5 1430.5 1481.1 1532.6 1584.9 . .
s 0.4534 1.6208 1.6473 1.6790 1.7080 1.7349 1.7602 1.7842 1.8289 1.8702 1.9089 1.9454 1.9800

Sh 33.74 83.74 133.74 183.74 223.74 283.74 383.74 483.74 583.74 683.74 783.74
85 v0.01762 5.167 5.445 5.840 6.223 6.397 6.966 7.330 8.052 8.768 9.480 10.19010.898
(316.26) h 286.52 1184.2 1203.0 1229.7 1255.5 1280.8 1305.8 1330.6 1380.2 1430.3 1481.0 1532.4 1584.7
s 0.4590 1.6159 1.6396 1.6716 1.7008 1.7279 1.7532 1.7772 1.8220 1.8634 1.9021 1.9386 1.9733

Sh 29.72 79.72 129.72 179.72 229.72 279.72 379.72 479.72 579.72 679.72 779.72
90 v0.01766 4.895 5.128 5.305 5.869 6.223 6.572 6.917 7.600 8.277 8.950 9.621 10.290
(320.28) h 290.69 1185.3 1202.0 1228.9 1254.9 1280.3 1305.4 1330.2 1380.0 1430.1 1480.8 1532.3 1584.6
s 0.4643 1.6113 1.6323 1.6646 1.6940 1.7212 1.7467 1.7707 1.8156 1.8570 1.8957 1.9323 1.9669

S h = degrees of superheat. OF h = enthalpy, Btullbm


v = specific volume, c u ftllbm s = entropy, BtullbmR
CO~OmON
Steam Tables

Table 111. Superheated Steam -Continued


Abs Press. Temperature -Degrees Fahrenheit
LblSa In. Sat. Sat.
(Sat. ?emp) Water Steam 350 400 450 500 550 600 700 800 900 1000 1100

Sh 22.18 72.18 122.28 172.18 222.18 272.18 372.18 472.18 572.18 672.18 772.18
100 v0.01774 4.431 4.590 4.935 5.266 5.588 5.904 6.216 6.833 7.443 8.050 8.655 9.258
(327.82) h 298.54 1187.2 1199.9 1227.4 1253.7 1279.3 1304.6 1329.6 1379.5 1429.7 1480.4 1532.0 1584.4
s 0.4743 1.6027 1.6187 1.6516 1.6814 1.7088 1.7344 1.7586 1.8036 1.8451 1.8839 1.9205 1.9552

Sh 26.92 76.92 126.92 176.92 226.92 326.92 426.92 526.92 626.92 726.92
180 V0.01827 2.5312 A 2.6474 2.8508 3.0433 3.2286 3.4093 3.7621 4.1084 4.4508 4.7907 5.1289
(373.08) h 346.19 1196.9- 1213.8 1243.4 1271.2 1297.9 1324.0 1375.3 1426.3 1477.7 1529.7 1582.4
S 0.5328 1.5543 1.5743 1.6078 1.6376 1.6647 1.6900 1.7362 1.7784 1.8176 1.8545 1.8894
Sh = degrees of superheat, OF h = enthalpy, Btullbm
v = specific volume, cu ftllbm s = entropy, BtuIlbmR
COMBUSTION
Steam Tables

Table 111. Superheated Steam -Continued


Abs Press. Temperature - Degrees Fahrenheit
LblSq In. Sat. Sat.
(Sat. Temp] Water Steam 400 450 500 550 600 700 800 900 1000 1100
--
Sh 22.47 72.47 122.47 172.47 222.47 322.47 422.47 522.47 622.47 722.47
190 v0.01833 2.4030 2.4961 2.6915 2.8756 3.0525 3.2246 3.5601 3.8889 4.2140 4.5365 4.8572
(377.53) h 350.94 1197.6 1212.0 1242.0 1270.1 1297.1 1323.3 1374.8 1425.9 1477.4 1529.4 1582.1
s 0.5384 1.5498 1.5667 1.6006 1.6307 1.6581 1.6835 1.7299 1.7722 1.8115 1.8484 1.8834

Abs Press. Temperature -Degrees Fahrenheit


LblSq In. Sat. Sat.
(Sat. Temp) Water Steam 400 450 500 550 600 700 800 900 1000 1100 1200

Sh = degrees of superheat, O F h = enthalpy, Btullbm


v = specific volume, c u ftllbm s = entmpy, BtuIlbmR
COMBUSTION
Steam T a b k

Table 111. Superheated Steam -Continued


Abs Press. Temperature -Degrees Fahrenheit
LblSqIn. Sat. Sat.
(Sat. Temp) Water Steam
Sh
290 v 0.01885 1.5948
(414.25) h 390.60 1202.6
s 0.5844 1.5135

Sh
300 v 0.01889 1.5427
(417.35) h 393.99 1202.9
s 0.5882 1.5105

Sh
310 vD.01894 1.4939
(420.36) h 397.30 1203.2
s 0.5920 1.5076

Sh
320 v 0.01899 1.4480
(423.31) h 400.53 1203.4
s 0.5956 1.5048

Sh
330 v 0.01903 1.4048
(426.18) h 403.70 1203.6
s 0.5991 1.5021

Sh
340 v 0.01908 1.3640
(428.99) h 406.80 1203.8
s 0.6026 1.4994

Abs Press. Temperature - Degrees Fahrenheit


LblSqIn. Sat. Sat.
(Sat.Temp) Water Steam 450 500 550 600 650 700 800 900 1000 1100 1200

Sh 5.40 55.40 105.40 155.40 205.40 255.40 355.40 455.40 555.40 655.40 755.40
400 v0.01934 1.1610 1.1738 1.2841 1.3836 1.4763 1.5646 1.6499 1.8151 1.9759'2.1339 2.2901 2.4450
(444.60) h 424.17 1204.6 1208.8 1245.1 1277.5 1307.4 1335.9 1363.4 1417.0 1470.1 1523.3 1576.9 1631.2
s 0.6217 1.4847 1.4894 1.5282 1.5611 1.5901 1.6163 1.6406 1.6850 1.7255 1.7632 1.7988 1.8325
Sh = degrees of superheat, "F h = enthalpy, Btullbm
v = specific volume, cu ftllbm s = entropy, BtullbmR
COMBUSTION
Steam Tables

able 111. Superheated Steam -Continued


Abs Press. Temperature - Degrees Fahrenheit
L ~ I S m.Q Sat. Sat.
( S a t . ~ e m ~ ) l V a t e r Steam 450 500 550 600 650 700 800 900 1000 1100 1200

Sh .60 50.60 100.60 150.60 200.60 250.60 350.60 450.60 550.60 650.60 750.60
420 v0.01942 1.1057 1.1071 1.2148 1.3113 1.4007 1.4856 1.5676 1.7258 1.8795 2.0304 2.1795 2.3273
(449.40) h 429.56 1204.7 1205.2 1242.4 1275.4 1305.8 1334.5 1362.3 1416.2 1469.4 1522.7 1576.4 1630.8
s 0.6276 1.4802 1 . 4 8 8 1.5206 1.5542 1.5835 1.6100 1.6345 1.6791 1.7197 1.7575 1.7932 1.8269

Sh = degrees of superheat, O F h = enthalpy, Btuilbm


v = specific volume, cu Rllbm s = entropy,BtuIlbmR
COXBmnON
Steam Tables

- -

Table 111. Superheated Steam -Continued


Abs Press. Temperature - Degrees Fahrenheit
LblSqIn. Sat. Sat.
(Sat. Temp) Water Steam 550 600 650 700 800 900 1000 1100 1200
Sh 46.92 96.92 146.92 196.92 296.92 396.92 496.92 596.92 696.92
700 v 0.02050 0.6556 0.7271 0.7928 0.8520 0.9072-1.0102 1.1078 1.2023 1.2948 1.3858
(503.08) h 491.60 1201.8 1243.4 1281.0 1314.6 1345.6 1403.7 1459.4 1514.4 1569.4 1624.8
s 0.6928 1.4304 1.4726 1.5090 1.5399 1.5673 1.6154 1.6580 1.6970 1.7335 1.7679

Sh 39.16 89.16 139.16 189.16 289.16 389.16 489.16 589.16 689.16


750 v 0.02069 0.6095 0.6676 0.7313 0.7882 0.8409 0.9386 1.0306 1.1195 1.2063 1.2916
(510.84) h 500.89 1200.7 1236.9 1276.1 1310.7 1342.5 1401.5 1457.6 1512.9 1568.2 1623.8
s 0.7022 1.4232 1.4598 1.4977 1.5296 1.5577 1.6065 1.6494 1.6886 1.7252 1.7598

Abs Press. Temperature ~ e ~ r eFahrenheit


e s
LblSqIn. Sat. Sat.
(Sat.Temp) Water Steam 550 600 650 700 750 800 850 900 1000 1100 1200

Sh 11.61 61.61 111.61 161.61 211.61 261.61 311.61 361.61 461.61 561.61 661.61
950 v 0.02141 0.4721 0.4883 0.5485 0.5993 0.6449 0.6871 0.7272 0.7656 0.8030 0.8753 0.9455 1.0142
(538.39) h 534.74 1194.7 1207.6 1255.1 1294.4 1329.3 1361.5 1392.0 1421.5 1450.3 1507.0 1563.2 1619.5
s 0.7358 1.3970 1.4098 1.4557 1.4921 1.5228 1.5500 1.5748 1.5977 1.6193 1.6595 1.6967 1.7317

Sh 39.18 89.18 139.18 189.18 239.18 289.18 339.18 439.18 539.18 639.18
1150 v 0.02214 0.3807 0.4263 0.4746 0.5162 0.5538 0.5889 0.6223 0.6544 0.7161 0.7754 0.8332
(561.82) h 564.78 1187.0 1230.9 1276.6 1315.2 1349.9 1382.2 1413.0 1442.8 1500.9 1558.1 1615.2
s 0.7647 1.3738 1.4160 1.4582 1.4923 1.5216 1.5478 1.5717 1.5941 1.6353 1.6732 1.7087
Sh = degrees of superheat, OF h = enthalpy, Btullbm
v = specific volume, cu ftllbm . s = entropy, BtuIlbmR
common
Steam Trbka

Table 111. Superheated Steam -Continued


Abs Press. Temperature - Degrees Fahrenheit
LblSq In. Sat. - Sat: -
(Sat. Temp) Water Steam 600 650 700 750 800 850 900 1000 1100 1200
Sh 32.81 82.81 132.81 182.81 232.81 282.81 332.81 432.81 532.81 632.81
1200 v 0.02232 0.3624 0.4016 0.4497 0.4905 0.5273 0.5615 0.5939 0.6250 0.6845 0.7418 0.7974
(567.19) h 571.85 1184.8 1224.2 1271.8 1311.5 1346.9 1379.7 1410.8 1440.9 1499.4 1556.9 1614.2
s 0.7714 1.3683 1.4061 1.4501 1.4851 1.5150 1.5415 1.5658 1.5883 1.6298 1.6679 1.7035

Sh 22.58 72.58 122.58 172.58 222.58 272.58 322.58 422.58 522.58 622.58
1300 v 0.02269 0.3299 0.3570 0.4052 0.4451 0.4804 0.5129 0.5436 0.5729 0.6287 0.6822 0.7341
(577.42) h 585.58 1180.2 1209.9 1261.9 1303.9 1340.8 1374.6 1406.4 1437.1 1496.3 1554.3 1612.0
s 0.7843 1.3577 1.3860 1.4340 1.4711 1.5022 1.5296 1.5544 1.5773 1.6194 1.6578 1.6937

Sh 12.93 62.93 112.93 162.93 212.93 262.93 312.93 412.93 512.93 612.93
1400 v 0.02307 0.3018 0.3176 0.3.667 0.4059 0.4400 0.4712 0.5004 0.5282 0.5809 0.6311 0.6798
(587.07) h 598.83 1175.3 1194.1 1251.4 1296.1 1334.5 1369.3 1402.0 1433.2 1493.2 1551.8 1609.9
s 0.7966 1.3474 1.3652 1.4181 1.4575 1.4900 1.5182 1.5436 1.5670 1.6096 1.6484 1.6845

Sh .55 50.55 100.55 150.55 200.55 250.55 350.55 450.55 550.55


2200 v 0.02669 0.1627 0.1636 0.2134 0.2458 0.2720 0.2950 0.3161 0.3545 0.3897 0.4231
(649.45) h 695.46 1122.2 1123.9 1218.0 1276.8 1323.1 1363.3 1400.0 1467.6 1530.9 1592.5
s 0.8828 1.2676 1.2691 1.3523 1.4020 1.4395 1.4708 1.4984 1.5463 1.5883 1.6266
Sh = degrees of superheat, O F h = enthalpy. Btullbm
v = specific volume, cu Rllbm s = entropy, BtuIlbmR
COLIBmZION
Steam Tables

Table 111. Superheated Steam -Continued


Abs Press. Temperature -Degrees Fahrenheit
LblSqIn. Sat. Sat.
(Sat. Temp) Water Steam 700 750 800 850 900 1000 1100 1200

Abs Press. Temperature - Degrees Fahrenheit


LblSq In. Sat. Sat.
(Sat.Temp)\Vater Steam 700 750 800 850 900 950 1000 1050 1100 1150 1200

Sh 44.92 94.92 144.92 194.92 244.92 294.92 344.92 394.92 444.92 494.92
3200 v 0.04472 0.0566 0.1300 0.1588 0.1804 0.1987 0.2151 0.2301 0.2442 0.2576 0.2704 0.2827
(705.08) h 875.54 931.6 1172.3 1250.9 1306.9 1353.4 1394.9 1433.1 1469.2-1503.8 1537.4 1570.3
s 1.0351 1.0832 1.2877 1.3515 1.3951 1.4300 1.4600 1.4866 1.5110 1.5335 1.5547 1.5749
Sh = degrees of superheat, O F h = enthalpy, Btullbm
v = specific volume, cu ftllbm . s = entropy, BtuIlbmR
COMBUSTION
Steam Tables

Table 111. Superheated Steam -Continued


Abs Press. Temperature - Degrees Fahrenheit
LblSq In. - .
(Sat. Temp) 750 800 850 900 950 '1000 ' 1 0 5 0 1100 1150 1200

Abs Press. Temperature - Degrees Fahrenheit


LblSq In.
(Sat. Temp) 750 800 850 900 950 1000 1050 1100 1150 1200 1250

Sh = degrees of superheat. "F h = enthalpy. Btullbrn


v = specific volume, cu ftilbrn s = entropy. BtuIlbrnR
COMBUSTION
Steam Tables

Table 111. Superheated Steam -Continued


Abs Press. Temperature - Degrees Fahrenheit
Lb/Sq In.
(Sat. Temp)

0.0262 0.0296 0.0350 0.0429 0.0522 0.0615 0.0701 0.0780 0.0853 0.0919 0.0982
792.7 871.2 959.8 1054.5 1144.0 1221.9 1288.5 1347.5.1400.2 1448.2 1492.9
0.9402 1.0037 1.0727 1.1437 1.2084 1.2627 1.3076 1.3460 1.3793 1.4087 1.4352
Sh = degrees of superheat, O F h = enthalpy, Btullbm
v = specific volume, cu ftllbm s = entropy, BtuIlbmR
COMBUSTION
Steam Tables

Table 111. Superheated Steam -Continued


Abs Press. Temperature -Degrees Fahrenheit
LblSq In.
(Sat. Temp)

14000 v 0.0233 0.0248 0.0267 0.0291 0.0320 0.0354 0.0392 0.0432 0.0474 0.0515 0.0555
h 771.3 832.6 894.3 958.0 1024.5 1092.3 1158.5 1221.4 1283.0 1340.2 1393.8
s 0.9019 0.9515 0.9996 1.0473 1.0953 1.1426 1.1872 1.2282 1.2671 1.3021 1.3339
Sh = degrees of superheat. O F h = enthalpy. Btullbm
v = specific volume. cu ftllbm s = entropy. Btu/lbmR .
Table 111. Superheated Steam -Continued
Abs Press. Temperature - Degrees Fahrenheit
LblSq In.
(Sat. Temp) 750 800 850 900 950 1000 1050 1100 1150 1200 1250

Sh = degrees of superheat. O F h = enthalpy. Btullbrn


v = specific volume, cu ftllbm s = entropy. BlullbmR
COMBUSTION
Sum Tables

SYSTEME INTERNATIONAL (SI METRIC) UNITS

Table I. Saturated Steam and Saturated Water: Temperature Table


Temp Press Volume, mJlkg Enthalpy, kJIkg Entropy, kJlkgK Temp
O C kPa Water Steam Water Evap. Steam Water Evap. Steam OC
T P v/ v,r '9 h~g h~ Sf SJY S9 T
COMBUSTION
st..m Tabla

Table I. - Continued
Temp Press Volume, m31kg Enthalpy, kJ/kg Entropy, kJ1kg.K Temp
OC kPa Water Steam Water Evap. Steam Water Evap. Steam OC
T P Vr V, hf h, he S/ Sfo S. T

Abstracted from "ASME Steam Table is SI (hletric) Units:' The American Society of Mechanical Engineer. Copyright 1977.

Table 11. Saturated Steam and Saturated Water (Pressure)


Press Temp Volume, m3kg Enthalpy, kjlkg Entropy, k)/kg-K
kPa *C Water. Steam Water Evap. Steam Water Evap. Steam
P T v~ "8 hl h,, h, Sf8 S8

1.0 6.983 0.0010001 129.21 29.34 2485.0 2514.4 0.1060 8.8706 8.9767
1.5 13.036 0.0010006 87.98 54.71 2470.7 2525.5 0.1957 8.6332 8.8288
2.0 17.513 0.0010012 67.01 73.46 2460.2 2533.6 0.2607 8.4639 8.7246
3.0 24.100 0.0010027 45.67 101.00 2444.6 2545.6 0.3544 8.2241 8.5785
4.0 28.983 0.0010040 34.80 121.41 2433.1 2554.5 0.4225 8.0530 8.4755
5.0 32.898 0.0010052 28.19 137.77 2423.8 2561.6 0.4763 7.9197 8.3960
7.5 40.316 0.0010079 19.239 168.77 2406.2 2574.9 0.5763 7.6760 8.2523
10.0 45.833 0.0010102 14.675 191.83 2392.9 2584.8 0.6493 7.5018 8.1511
15.0 53.997 0.0010140 10.023 225.97 2373.2 2599.2 0.7549 7.2544 8.0093
20.0 60.086 0.0010172 7.650 251.45 2358.4 2609.9 0.8321 7.0774 7.9094
30.0 69.124 0.0010223 5.229 289.30 2336.1 2625.4 0.9441 6.8254 7.7695
40.0 75.886 0.0010265 3.993 317.65 2319.2 2636.9 1.0261 6.6448 7.6709
50.0 81.345 0.0010301 3.240 340.56 2305.4 2646.0 1.0912 6.5035 7.5947
75.0 91.785 0.0010375 2.2169 384.45 2278.6 2663.0 1.2131 6.2439 7.4570
100.0 99.632 0.0010434 1.6937 417.51 2257.9 2675.4 1.3027 6.0571 7.3598
150.0 111.37 0.0010530 1.1590 467.13 2226.2 2693.4 1.4336 5.7898 7.2234
200.0 120.23 0.0010608 0.8854 504.70 2201.6 2706.3 1.5301 5.5967 7.1268
COMBUSTION
Steam fables

Table 11. -Continued


Press Temp Volume, m3kg Enthalpy, kJlkg Entropy, kJIkg-K
kPa OC Water Steam Water Evap. Steam . -Water
' Evap. Steam
P T vf vg hf 4 hg Sl Sfg ss
300.0 133.54 0.0010735 0.6056 561.4 2163.2 2724.7 1.6716 5.3193 6.9909
400.0 143.62 0.0010839 0.4622 604.7 2133.0 2737.6 1.7764 5.1179 6.8943

Table 111. Superheated Steam


Pressure
kPa - v (specificvolume), matkg h (enthalpy),kJlkg s (entropy), kJ1kg.K
Temperature, O C
Table 111. -Continued
F'mssure
kPa v (specific volume), m31kg h (enthalpy), kJlkg s (entropy), kJ1kg.K
Cr,l Temperature, 'C
"C 50 100 150 200 300 -
400 -500 600 700 800

300 v 0.6338 0.7164 0.8753 1.0314 1.1865 1.3412 1.4957 1.6499


(133.5) h 2760.4 2865.4 3069.7 3275.2 3486.0 3703.2 3927.0 4157.3
s 7.0772 7.3119 7.7034 8.0338 8.3257 8.5898 8.8325 9.0577
400 v 0.4706 0.5343 0.6549 0.7725 0.8892 1.0054 1.1214 1.2372
(143.6) h 2752.0 2860.4 3067.2 3273.6 3484.9 3702.3 3926.4 4156.9
s 6.9286 7.1708 7.5675 7.8994 8.1919 8.4563 8.6992 8.9246
Appendix E. Engineering Conversion Factors

u he following table is designed to provide


accurate conversion of units between vari-
ous equivalent representational forms. To con-
vert a unit, locate the unit in the MULTIPLY
would be (2.5) acres x 4046.87 = 10,000 m2.
Where conversions involve the International
System of Units (le Systdme International
d'unitbs, abbreviated "SI"), ,we show the
column of the table, select the desired unit in proper symbols or formulas for the particular SI
the TO OBTAIN column, and then multiply the unit. There are symbols for the recommended
quantity to be converted by the appropriate fac- SI base, supplementary, and derived units, and
tor to obtain the desired units. for most of their multiples and submultiples.
For example, you have exactly 2.5 acres and Note that such "metric" units as kilogram-
you need to know how many square meters. In force, calorie, tom, centimeter of water, millime-
the table: acre x 4046.87 = square meter. There- ter of mercury, and metric horsepower are not
fore, 2.50000 acres = (2.50000) x [4046.87] = SI units. Also note that, in American Custom-
10117.18 square meters. ary Units (ACU); the unit pound is used as ei-
A note should be made regarding scientific ther a mass unit [pound-mass, or lbm) or as a
notation: 1 x lo1, 1 x lo2, 1 x lo3 are equivalent force unit (pound-force, or lbf); in ACU, pound
respectively to 10, 100, 1000. For negative is always pound avoirdupois, not troy pound.
powers, 1 x lo-', 1 x lo-', 1 x 10-"epresent the An asterisk I*) after the sixth or higher signif-
numbers 0.1, 0.01, 0.001. Therefore, the num- icant figure indicates that the conversion factor
ber 2.345 x lo3is 2345.0 and 2.345 x repre- is exact and that all subsequent digits are zero.
sents 0.002345. All other factors are rounded. Where fewer than
Accuracy is an important concern with con- six significant figures are shown, more preci-
version factors. This table presents most conver- sidn is not warranted.
sions with six significant figures; for example, As a further explanation of the use of this
4046.87 and 39.3701. The actual number of sig- table, note that: to convert from pound-force
nificant figures allowed in a conversion is equal per square inch, multiply by 6.894 76 to obtain
to the number of significant figures in the least the number of kilopascals (kPa) means
accurate of the conversion factors or the unit be- 1 lbf/in2=6.894 76 H a .
ing converted. For example, in the acre-to- Similarly, to convert from inches to rnillime-
square-meter illustration: if the number of ters, multiplying the inch value by 25.400 O* to
acres was known only to two significant fig- obtain the number of millimeters, means
ures, then the conversion to square meters 1 inch = 25.4 millimeters (exactly).

Table 1. Engineering Conversion Factors

MULTIPLY BY TO OBTAIN
A
abampere ampere (A)
abcoulomb coulomb (C)
abfarad farad (F)
abhenry henry (HI
abohm ohm (Ql
. -
COUtBmnON
EnglneehgConversbnFactors

- - -
TO OBTAIN

abvolt
acre (US. survey: 1foot =
(120013937)m) square meter (ma)
acre foot (U.S. survey) cubic meter (m3)
ampere (A) coulomb/second (CIS)
amperelcentimeter (Ncm) amperelinch
amperelinch (1959 internat'l inch) amperelmeter (Alm)
amperekilogram (Akg) amperelpound-mass
amperelmeter (Nm) ampere/inch
amperelpound-mass amperekilogram (Akg)
amperelsquare foot amperelsquare meter (A/mz)
amperelsquare inch amperelsquare meter (Alma)
amperelsquare meter (A/m2) amperelsquare inch
amperelsquare meter (A/m2) amperelsquare foot
amperelvolt (AN) siemens (S)
ampere/volt inch siemenslmeter (Slm)
are square meter
atmosphere (kilogram-force/cm2) kilopascal (kPa)
atmosphere (760 tom) kilopascal (kPa)
atmosphere (760 tom) inch mercury (32OF) ,
B
bar (lo5pascals) kilopascal (kPa)
barrel (42 U.S. gallons, liquid) cubic meter (m3)
barrellton (U.K. long or gross) cubic meterlmetric ton
barrellton (U.S. short or net) cubic meterlmetric ton
barrellday cubic decimeter/second \

barrel/hour cubic decimeterlsecond


barrellmillion std cubic feet cubic decimeters/kilomol
becquerel (Bq) (radioactivity) disintegrationlsecond
Btu (mean) kilojoule (kJ)
Btu (thermochemical) kilojoule (kJ)
Btu (3gF) . kilojoule (kJ)
Btu (60F) kilojoule (kj)
Btu (I.T.) (International Table) kilojoule (kJ)
Btu (I.T.) foot-pound (force)
Btu (I.T.)/cubic foot kilojoule/cubic meter (kJ/m3)
Btu (I.T.)/hour watt (W)
Btu (I.T.)/hour cubic foot kilowatt/cubic meter (kW/m3)
Btu (I.T.)hour cubic foot OF kilowatt/cubic meter kelvin (kW/m3-K)
Btu (I.T.)/hour square foot watt/square meter (W/mz)
Btu (I.T.)hour square foot OF watttsquare meter kelvin (W/m2.K)
Btu (I.T.)foot/hour square foot OF wattlmeter kelvin (Wlm-K)
Btu (I.T.)lminute .- kilowatt (kW)
Btu (I.T.)lpound-mole joulelmole (Jlmol)
Btu (I.T.)lpound-mole OF kilojoulekilomol kelvin (kJ1kmol.K)
COMBUSTION
Engineering Conversion Factors

h m X E LY BY M OBTAIN

Btu (I.T.)/pound-mass 0.555556 kilocalorie/kilogram


Btu (I.T.)/pound-mass 2.32600* kilojoule/kilogram (kJkg)
Btu (I.T.)/pound-mass OF 4.18680* kilojoule/kilogram kelvin (kJkg-K)
Btu (I.T.)/pound-mass OF 1.00000* kilocalorie/kilogram kelvin
Btu (I.T.)/second 1.05506 kilowatt (kW)
Btu (I.T.)/second cubic foot 37.2589 kilowatt/cubic meter (kW/m3)
Btu (I.T.)/second cubic foot OF 67.0661 kilowattlcubic meter kelvin (kW1mL.K)
Btu (I.T.)/second square foot 11.3565 kilowatttsquare meter (kW/m2)
Btu (I.T.)/second square foot OF 20.4418 kilowatttsquare meter kelvin (kW/mz-K)
Btu (I.T.)/gallon (U.K. liquid) 232.080 kilojoule/cubic meter (kJ/m3)
Btu (I.T.)/gallon (U.S. liquid) 278.716 kilojoule/cubic meter (kJ/m3)
C
calorie (I.T.) 4.18680* joule (J)
calorie (mean) 4.19002 joule (J)
calorie (thermochemical) 4.18400* joule (J)
calorie (themnochemical) 0.00396567 Btu (I.T.)
calorie (15'C) 4.18580 joule (J)
calorie (209C) 4.18190 joule (J)
calorie (kilogram, I.T.) 4186.80* joule (J)
calorie (kilogram, mean) 4190.02 joule (J)
calorie (kilogram, thermochemical) 4184.00* joule (J)
calorie (thermochem)/gram kelvin 4.18400* kilojoule/kilogramkelvin (kJ/kg.K)
calorie (thermochemical)/hour cm2 0.0116222 kilowattlsquare meter (kW/mz)
calorie (thermochemical)/milliliter 4.18400* megajoule/cubicmeter (MJ/m3)
calorie (thermochem)/pound-mass 9.22414 joule/kilogram (Jlkg)
candelalsquare meter (cd/ma) 0.291864 foot lambert
candelalsquare meter (cd/m2) 0.00031416 lambert
centimeter 0.393701 inch (1959 international)
centimeter water (4OC) 0.0980638 kilopascal (kPa)
centipoise 0.001000* pascal second (Pa-s)
centistoke 1.00000* square millimeter/second
chain (surveyor or gunter) 20.1168 meter (m)
coulomb (quantity of electricity) 1 .OOOOO* ampere-second (Ass)
coulomb/cubic foot 35.3147 coulomb/cubic meter (C/m3)
coulomb/cubic meter (C/m3) 0.0283168 coulomb/cubic foot
coulomb/foot 3.28084 coulomb/meter (Clm)
coulomb/inch - 39.3701 coulomb/meter (Clm)
coulomb/meter (Clm) 0.304800* coulomb/foot
coulomb/meter (Clm) 0.025400* coulomb/inch
coulomb/square foot 10.7639 coulomb/square meter (C/m2)
coulomb/square meter (C/mZ) 0.0929030 coulomb/square foot
cubic centimeter 0.035195 fluid ounce (U.K.)
cubic centimeter 0.038140 fluid ounce (U.S.)
cubic centimeter 0.0610237 cubic inch
cubic centimeter/cubic meter 1.00000 volume partslmillion
CO~USIION
Engkmring Conversion Factors

- - --
IblUmPLY BY TO OBTAIN

cubic decimeter (liter) 0.0353147 cubic foot


cubic decimeter (liter) 0.219969 gallon (U.K. liquid)
cubic decimeter (liter) 0.264172 gallon (U.S. liquid)
cubic decimeter (liter) 0.879877 quart (U.K. liquid)
cubic decimeter (liter) 1.05669 quart (U.S. liquid)
cubic decimeterkilogram 0.119826 gallon (U.S. 1iquid)lpound-mass
cubic decimeterkilogram 0.0160185 cubic footfpound-mass (ft3Abm)
cubic decimeterkilogram 0.099776 gallon (U.K. 1iquid)lpound-mass
cubic decimeter/second 127.133 cubic foothour
cubic decirneterlsecond 543.440 barrellday
cubic decimeterlsecond 3051.19 cubic footlday
cubic decimeterlsecond 13.1981 gallon '(u.K.1iquid)lminute
cubic decimeterlsecond 15.8503 gallon (U.S. 1iquid)lminute
cubic decirneterlsecond 2.11888- cubic footfminute
cubic decimeterlsecond 0.035315 cubic footlsecond
cubic decimeterlmetric ton 0.005706 barrellton (U.S.)
cubic decimeterlmetric ton 0.006391 barrellton (U.K.)
cubic decimeterlmetric ton 0.268411 gallon (U.S. 1iquid)lton(U.K.)
cubic decimeterlmetric ton 0.239653 gallon (U.S. 1iquid)lton(U.S.)
cubic foot (1959international) 0.0283168 cubic meter (mg)
cubic foot 28.3168 cubic decimeter (liter)
cubic foot 7.48052 gallon (U.S. liquid)
cubic footlfoot 0.0929030 cubic meterlmeter (m3/m)
cubic foothour 0.00786579 cubic decirneterlsecond
cubic footfminute 0.471947 cubic decirneterlsecond
cubic footlpound-mass 62.4280 cubic decimeter/kilograrn
cubic footfpound-mass 0.0624280 cubic meterkilogram (m3/kg)
cubic footlsecond 28.3169 cubic decirneterlsecond
cubic inch 0.0163871 cubic decimeter
cubic inch 16.3871 cubic centimeter
cubic meter (my . 1 000 ooo* cubic centimeter
cubic meter (m3) 1000.00* liter
cubic meter (m3) 61 023.7 cubic inch (1959international)
'

cubic meter (m3) 6.28976 barrel (42U.S. gallons, liquid)


cubic meter (m3) 35.3147 cubic foot
cubic meter (m3) 1.30795 cubic yard (1959international)
cubic meter (m3) 219.969 gallon (U.K. liquid)
cubic meter (m3) 264.172 gallon (US, liquid)
cubic meterkilogram (m3/kg) 16.0185 cubic footfpound-mass
cubic meterlmeter (mVm) 10.7639 cubic footlfoot
cubic meterlmeter (ma/m) 80.5196 gallon (U.S. 1iquid)lfoot
cubic meterlsecond meter (m3/s-m) 289 870 gallon (U.S. 1iquid)hour foot
cubic meterlsecond meter (mVsm) 4022.80 gallon (U.K. 1iquid)lminutefoot
cubic meterlsecond meter (m3/s-m) 4831.18 gallon (U.S. 1iquid)lminutefoot
cubic meterlmetric ton (m3/Mg) 5.70602 barrellton (U.S.)
COMBUSTION
Enginewing Conversion Factors

rvfmmPLY BY TO OBTAIN

cubic meterlmetric ton (m3/Mg) 6.39074 barrellton (U.K.)


cubic mile (1959 international) 4.16818 cubic kiloineter (km3)
cubic yard (1959 international) 0.764555 cubic meter (m3)
curie (Ci) (radiation dosimetry) 3.7000 x 10" * becquerel (Bq)

D
degree Celsius (difference) ("C, diff.) 1.80000* degree Fahrenheit (difference)
degree Celsius (difference) ("C, diff.) 1.00000* kelvin (difference)
degree Fahrenheit (difference) 0.555556 degree Celsius (difference) ("C, diff.)
degree Kelvin (difference) (K) 1.80000* degree Rankine (difference)
degree Rankine (difference) 0.555556 kelvin (difference) (K)
(for temperature, see under "T")
degree (angle) 0.017453 radian
degreelsecond (angular) 0.166667 revolutiodminute
dyne 0.000010* newton (N]
dyne 7.23301 x lo-' poundal
dyne 2.24809 x lo-" pound (force)
dyne ~.OOOoo* gram centirneterlsecond squared
dynelsquare centimeter O.~ooooo* pascal (Pa)
dyne secondlsquare centimeter O.~OOOOO* pascal second (Pass)
F
farad (electrical capacitance) l.OOOOO* coulomb/volt (CN)
faradlmeter (Flm) 0.025400* faradlinch
fathom (6 U.S. survey foot exactly) 1.82880 meter (m)
foot (1959 internationd) 0.304800* meter (m)
foot (1959 international) 304.800* millimeter
foot (U.S. survey) (1200/3937)* meter (m)
foot larnbert 3.42626* candelalsquare meter (cdlmz)
foot of water (39.ZF) 2988.98 pascal (Pa)
footldegree F 0.548640 meterkelvin (mlK)
foot/gallon (U.S. liquid) 80.5196 meterlcubic meter ( d m ?
(foot= 1959 international)
foot/cubic foot (1959 international) 10.7639 meterlcubic meter ( d m 3 )
foot/hour 0.0846667 millirneter/second (rnmls)
footfminute (1959 international foot) 0.0050800* meterlsecond (mls)
foot/second - 0.304800* meterlsecond (mls)
foot-poundal 0.0421401 joule Ul
foot-pound (force) 1.35582 joule (J)
foot-pound (force) 0.00128507 Btu (I.T.)
foot-pound (force)lgallon (U.S.) 0.358169 kilojoulelcubic meter (kJlm3)
foot-pound (force)/second 1.35582 watt (w)
foot-pound (force)/square inch 0.210152 joulelsquare centimeter
footcandle 1.00000* lumen/square foot
footcandle 10.7639 lux (lumedsquare meter) (lm/mz)
COMBUSTION #s

Enghsering Conversion Factors

-
MULTIPLY BY TO OBTAIN

G
gal (galileo) O.O~OOOO* meterlsecond squared (m/sz)
gallon (U.K. liquid) 0.00454609 cubic meter (m5)
gallon (U.K. liquid) 4.54609 cubic decimeter
gallon (U.K. 1iquid)how square foot 1.35927 x lo-' cubic meterlsecond square meter (ma/smz)
gallon (U.K. 1iquid)lminute 0.075768 cubic decimeterlsecond
gallon (U.K. liquid)/ 0.00081556 cubic meterlsecond square meter (ma/smz)
minute square foot
gallon (U.K. 1iquid)lpound-mass cubic decimeterkilogmm
gallon (U.K. liquid)/1000barrels cubic centimeterlcubic meter
gallon (U.S. liquid) cubic inch
- gallon (U.S. liquid) gallon (U.K. liquid)
gallon (U.S. liquid) cubic meter (mS)
gallon (U.S. 1iquid)lcubicfoot cubic decimeterlcubic meter
gallon (U.S. 1iquid)lfoot cubic meterlmeter (ma/m)
gallon (U.S. 1iquid)hour square foot cubic rneterlsecond square meter (m31s.mz)
gallon (U.S. 1iquid)lminute cubic decimeterlsecond
gallon (U.S. liquid)/ cubic meterlsecond square meter (m3/smz)
minute square foot
gallon (U.S. 1iquid)lpound-mass cubic decimeterkilogram .
gallon (U.S., dry) cubic meter (m3)
, gamma (mass) kilogram (kg)
gamma (magneticflux density) tesla (T)
gauss (magnetic flux density) tesla (T)
gauss1Oersted henrylmeter (Hlm)
gilbert ampere turn 1

grad radian (rad)


grain (117000 lbm avoirdupois) milligram (mg)
graidgallon (U.S. liquid) gramtcubic meter
graidcubic foot milligrandcubic decimeter
graid100 cubic feet milligram~cubicmeter
g- ounce-mass (avoirdupois) .-
gram ounce-mass (troy)
gram mole kilomole (kmol) ,

g d c u b i c meter milligrandgallon (U.S. liquid)


g d c u b i c meter graidgallon (U.S. liquid)
g d c u b i c meter pound-mass11000 barrels
gramlcubic meter pound-mass/1000 gallons (U.S. liquid)
g d c u b i c meter pound-mass11000 gallons (U.K. liquid)
gramlgallon (U.K.) kilograrn/cubic meter (kg/m3)
g d g a l l o n (U.S.) kilogramlcubic meter (kg/m3)
gray (GY) rad (radiationdose absorbed) - -
-
.
H
hectare , 10 000* square meter (m2J
COMBUSTION
Englneerlng Convenion Facton

MlJImPLY BY TO OBTAIN

hectare acre (U.S. survey)


henry (inductance) (H) maxwelYgilbert
henry (inductance) (H) weberlampere
henry (inductance) (H) linetampere
henrylmeter (Wm) gauss/Oersted
henrylmeter (Wm) linelampere inch
horsepower (electric) kilowatt (kW)
horsepower (hydraulic) kilowatt (kW)
horsepower (metric) kilowatt (kW)
horsepower (U.S.) (550 ft-lbf/s) kilowatt (kW)
horsepower (U.S.)(550ft:lbf/s) Btu (I.T.)/minute
horsepower hour (U.S.) (550 ft-lbf/s) megajoule (MJ)
horsepower hour (U.S.) (550 ft-lbf/s) Btu (I.T.)
horsepower/cubic foot (550 ft-lbf/s) kilowatttcubic meter (kW/m3)
hundred weight (U.K., long) kilogram (kg)
hundred weight (U.S., short) kilogram (kg)
I

inch (1959 international) 25.4000* millimeter (mm)


inch water (32 .2" F) 0.249082 kilopascal (kPa)
inch water (60F) 0.24884 kilopascal (kPa)
inch mercury (32F) 3.38638 kilopascal (kPa)
inch mercury (60F) 3.37685 kilopascal (kPa)
inchlminute 0.423333 ' millimeter/second (mmts)
J
/
joule (J) (energy, work, or heat) 0.737562 foot-pound (force)
joule (J) (energy, work, or heat) 23.7304 foot-poundal
joule (J) (energy, work, or heat) 1.00000* watt second (Ws) or Newton-meter (N-m)
joule (J) (energy,work, or heat) 9.47817 x Btu (International Table)
joule (J) (energy, work, or heat) 0.239126 calorie (20C)
joule (J) (energy, work, or heat) 0.238903 calorie (15OC)
joule (J) (energy,work, or heat) 0.238662 - calorie (mean)
joule (J) (energy,work, or heat) 0.238846 calorie (I.T.)
joule (J) (energy, work, or heat) 0.239006 calorie (thermochemical)
joule/kilogram (Jkg) 0.108411 calorie (thermochemical)/pound-mass
joulekilogram (Jkg) 4.29923 x lo-' Btu (I.T.)/pound-mass
joule/mole (Jlmol) 0.429923 Btu (I.T.)/pound mole
joule/square centimeter (J/cm2) - 4.75846 foot-pound (force)/squareinch
joule/square centimeter (J/cmz) 0.101972 kilogram (force)-meter/squarecentimeter
(kgf/cmz)
K
kelvin (degree), t, 1.800 oo* degree Rankin, t,
kilocalorie (Calorie) 1000.00* calorie
kilocalorie (thermochemical) 4.18400* kilojoule (kJ)
kilocalorie (thermochemica1)hour 1.16222 watt (w)
rmmPLY BY TO OBTAIN

kilocalorie (thermochemical)/ wattlsquare meter K (W/m%)


hour mzOC
kilocalorie (thennochemical)/
kilogram "C
kilogram (kg) (mass, by definition) pound-mass (lbm) (avoirdupois)
kilogram (kg) (mass) slug (mass)
kilogram-meter (kg-m) slug-foot
kilogram meterlsecond (kgmls) pound (mass)-foot/second
k i l o g d c u b i c decimeter pound-mass/gallon (U.S. liquid)
kilogramtcubic decimeter pound-mass/gallon (U.K. liquid)
kilogramtcubic meter (kg/ms) pound-masslcubic foot
kilogramtcubic meter (kg/ma) pound-masstbarrel
k i l o g d c u b i c meter (kg/ma) grams/gallon (U.S. liquid)
kilogram/cubic meter (kg/ms) gramslgallon (U.K. liquid)
kilogramtcubic meter (kg/ma) slug/cubic foot
k i l o g d m e t e r (kglm) pound-mass/foot
k i l o g d m o l e (kglmol) pound-masslmole
kilogramtsecond (kg/s) pound-masshour
k i l o g d s e c o n d (kgls) pound-masstsecond
kilogdsecond (kgls) ton-mass (U.K.)/minute ",

kilogdsecond (kgls) ton-mass (U.S.)/minute


kilogram/second (kgls) ton-mass (U.K.)hour
kilogdsecond (kgls) ton-mass (U.S.)hour
kilogram/second-meter(kg1s-m) pound-mass/second-foot
kilogdsecond-meter (kg1s.m) pound-masshour-foot
kilogram/second-squaremeter pound-mass/second-squarefoot '
(kg/smz)
kilogramlsecond-squaremeter pound-masslhour-square foot
Iks/s'm2)
kilogramlsquare meter (kg/mz) pound-masslsquare foot
kilogram-force (kg0 n&on (N)
kilogram (force)-meter(kgf-m) joule (J)
kilogram force (kg0 (not SI) newton (N)
kilojoule (kJ) Btu (I.T.)
kilojoule (kJ) Btu (39F)
kilojoule (kJ) Btu (60F)
kilojoule (kJ) Btu (mean)
kilojoule (kJ) Btu (thermochemical)
kilojoule/cubic meter (kJ/mS) Btu (I.T.)/cubicfoot
kilojoule/cubic meter (kJ/ms) Btu (I.T.)/gallon (U.K. liquid)
kilojoule/cubic meter (kJ/mS) Btu (I.T.)/gallon (U.S. liquid)
kilojoule/cubic meter (kJ/ms) - foot-pound (force)/gallon(U.S. liquid)
kilojoule/kilogram (kJkg) Btu (I.T.)/pound-mass
kilojoule/kilogram kelvin (kJkg.K) Btu (I.T.)/pound (mass) OF
kilojoule/kilogram-kelvin (kJ/kg.K) Btu (I.T.)/pound mole OF
COMBUSTION
Engineering Converpion Factors

- - -

TO OBTAIN

kilojoule/kilogramkelvin (kJkgK) calorie (thermochemical)/gramkelvin


kilojoule/ki10gram kelvin (kJkgK) calorie (thermochemical)/grammole "C
kilojoulekilogram kelvin ( k ~ / k ~ ~ ) kilocalorie (thermochemical)/kilogram OC
kilojoule/kilogmm kelvin (kJ/kg.K) kilowatt hourkilogram "C
kilojoule/mole (kJ/mol) kilocalorie (thermochemical)/grammole
kilometer foot (1959 international)
kilometer (km) mile (U.S. statute)
kilometer (km) nautical mile
kilometer/cubic decimeter mile (U.S. statute)/gallon(U.S. liquid)
kilometerhour (kndh), knot (international)
kilometerhour (kmlh) milesthour (U.S. statute)
kilomole (kmol) . gram mole
kilomole (kmol) pound-mole
kilomole (kmol) standard cubic foot [60E, 1atmosphere)
kilomole (kmol) standard cubic meter (0C 1atmosphere)
kilomole (kmol) standard cubic meter (lsC, 1atmosphere
kilomole/cubic meter pound-mole/cubic foot
kilomole/c,ubicmeter pound-mole/gallon (U.K. liquid)
kilomole/cubic meter pound-mole/gallon (U.S. liquid)
kilomole/cubic meter standard ftaharrel (60F, 1atmosphere)
kilonewton (kN) kip (1000 pound-force)
kilonewton (kN) ton-force (U.K., 2240 1bfJ
kilonewton (kN) ton-force (U.S., 2000 lbf)
kilonewton meter (kN-m) ton-force (U.S.) foot
kilopascal (kPa) 0.0101972 atmosphere (kilogram-force/
square centimeter)
kilopascal (kPa) atmosphere (760 tom)
kilopascal (kPa) bar
kilopascal (kPa) centimeter water (4C)
. kilopascal (kPa) inch water (392F)
kilopascal (kPa) inch mercury (32" F)
kilopascal (kPa) inch mercury (60 F)
kilopascal (kPa) millimeter mercury (0OC)
kilopascal (kPa) pound-forcelsquare foot
kilopascal (kPa) pound-forcelsquare inch
kilopascallmeter (kPa/m) ' pound-force/square inch-foot
kilopond force (kgf) newton
kilowatt (kw) Btu (I.T.)/minute
kilowatt (kw) Btu (I.T.)/second
kilowatt (kw) horsepower (electric)
kilowatt (kw) horsepower (550 foot poundlsecond)
kilowatt (kw) horsepower (hydraulic)
kilowatt (kw) ton of refrigeration (12 000 Btu/h)
kilowatt-hour megajoule (h4J)
kilowatt-hourkilogram OC kilojoulekilogram kelvin (kJkg-K)
.-
COMBuSnON
Engineering Conwrsion Factom

TO OBTAIN

kilowattlcubic meter (kW/ma) Btu (I.T.)lhourcubic foot


kilowattlcubic meter (kWlmJ) Btu (I.T.)lsecond cubic foot
kilowattlcubic meter horsepower/cubicfoot (U. S., 550 ft-lbfls)
kilowattlcubic meter kelvin Btu (I.T.)lhour cubic foot O F
(kW/m3-K)
kilowattlcubic meter kelvin Btu (I.T.)lsecondcubic foot O F
(kW/m3.K) .-.
kilowattlsquare meter (kWlmz) Btu (I.T.)/second square foot
kilowattlsquare meter (kW/m2) calorie (thermochemical)/hour cm2
kilowattlsquare meter kelvin Btu (I.T.)lsecond square foot O F
(kW/m2-K)
kip (1000 pound-force) kilonewton (kN)
kipisquare inch (forcelarea) megapascal (MPa)
knot (international) kilometerhour (M)
knot (international) U.S. statute milehour
knot (international) meterlsecond

lambert (luminance) candelalsquare meter


light-year meter
line maxwell
line weber (Wb)
linelampere henry (HI
linelampere inch henrytmeter (Hlm)
linelsquare inch tesla (T) ,
link meter (m)
liter (cubic decimeter) cubic centimeters
liter (cubic decimeter) cubic foot
liter (cubic decimeter) gallon (U.S. liquid)
liter (cubic decimeter) gallon (U.K. liquid)
lumen (luminous flux) candela-steradian (cd-sr)
lumedsquare meter lux (W
lumedsquare foot footcandle
lumedsquare foot lux (lx)
lumedsquare inch lux (lx)
lux (illuminance) lumedsquare meter (lm/m2)
lux (W footcandle
lux (lx) lumenlsquare foot
lux (h) lumedsquare inch
lux second (lx-s) foot candle second
M
maxwell line
maxwell weber (Wb)
maxwelllgilbert henry (HI
megagram (Mg) ton-mass (metric)or tonne
COMBUSTION
Engineering ConwrslonFactom

MUI3'IPL.Y BY M OBTAIN

mega- (Mg) ton-mass-(U.K.long or gross)


mega- (Mg) -ton-mass(U.S. short or net)
megagramlsquare meter (Mg/mz) ton-mass (U.S.)/square foot
megajoule (MJ) Btu (I.T.)
megajoule (MJ) horsepower hour (U.S.; 550 ft-lbfls)
megajoule (MJ) kilowatt hour (kW-h)
megajoule (MJ) them (European Community)
megajoulelcubic meter (MJ/m3) Btu (I.T.)/gallon (U.K. liquid)
megajoulelcubic meter (MJlm3) Btu (I.T.)/gallon (U.S. liquid)
megajoule/cubic meter (MJ/m3) calorie (themochemical)/milliliter
megapascal (MPa) kiplsquare inch
megapascal (MPa) pound-forcelsquare inch
megapascal (MPa) ton-force (U.S.)/square foot
megapascal (MPa) ton-force (U.S.)/square inch-
megawatt (MW) million Btu (I.T.)hour
meter (m) chain (U.S. survey)
meter (m) fathom (6 U.S. survey foot)
meter (m) foot (1959 international)
meter (m) ' foot (U.S. survey)
meter (m) link (U.S. survey)
meter (m) rod (U.S. survey)
meter (m) yard (1959 international)
meterlcubic meter ( d m 3 ) foot/cubic foot (1959 international foot)
meterlcubic meter ( d m 3 ) 0.0124193 foot/gallon (U.S. liquid)
(1959 international foot)
meterkelvin (mK) 1.82269 foot/"F (1959 international foot)
meterlsecond ( d s ) 3.28084 footlsecond (1959 international foot)
meterlsecond ( d s ) 196.850 foot/minute (1959 international foot)
mho 1.00000* siemens (S)
microbar or dynelsquare cm 0.100~0* pascal (Pa)
micrometer (pm) 0.0393701 mil
micrometer (pm) 1.00000* micron (abolished name, 1967)
micron [abolished name, i967) 1.00000* micrometer or 10-'meter (pm)
microsecondlfoot 3.28084 microsecondlmeter (pslm)
microsecondlmeter (pslm) 0.304800* microsecondlfoot
mil 0.001000* inch (1959 international)
mil - 25.4000* micrometer (lo-%)
mile (U.S. statute) 5280.00* foot (survey foot of year 1893)
mile (international) 1.609344" kilometer (km)
mile (U.S. statute) 1.609347 kilometer (km)
mile (U.S. and international nautical) 1852.00* meter (m)
mile (U.S. statute)hour 0.868961 knot (international)
mile (U.S. sta4xte)fU.S. gallon 0.425144 kilometerniter
milehour (international) 1.609 344 kilometerhour (kdh)
milligram (mg) 0.0154324 srain (mass)
COUDUSmON 3
.,

Enplnoerhg Conversion Factors

- -

MULTIPLY TO OBTAIN
- -

milligramlcubic decimeter graidcubic foot


milligramlcubic meter (mg/m3) grad100 cubic foot
milligram/gallon (U.S. liquid) gramlcubic meter (g/m3)
millimeter (mm) inch (1959 international)
millimeter (mm) foot
millimeter mercury (0C) pascal (Pa)
millimeter mercury (OC) kilopas.ca1 (@a)
millimeterlsecond ( d s ) foothour ,
millimeter/second ( d s ) inchlminute
millimeterlsecond (mmts) inchlsecond
million Btu (I.T.)/hour megawatt (MW)
million electron volt picojoule (pJ)
miner's inch cubic feegminute
minute (angle) radian
molelfoot molelmeter (mollm)
molekilogram (molkg) molelpound-mass
molelmeter (mourn) molelfoot
molelpound (mass) molekilogram (molkg)
mole/square foot molelsquare meter (mollmx)
molelsquare meter (mol/mz) molelsquare foot
N
nautical mile (U.S. or international) kilometer (km)
newton (N) kilogram-meterlsecond-squared (kg.m/s2)
newton (N) dyne
newton (N) pound-force, avoirdupois
newton (N) poundal
newton-meter (N-m) pound (force)-foot
newton-meter (N-m) pound (force)-inch
newton-meter (N-m) poundal-foot
newton-meterlmeter (N-mlm) pound (force)-foot/inch
newton-meterlmeter (N-dm) pound (force)-inchlinch
newtonlmeter '(Nlm) pound-forcelfoot
newtonlmeter (Nlrn) pound-forcelinch .
0
oersted ampere turnlmeter
ohm (electric resistance) volt/ampere (VIA)
ohm circular millfoot ohm square meterlmeter (nmz/m)
ohm foot ohm square meterlmeter (Qma/m)
ohm inch ohm square meterlmeter (Q mzlm)
ohm square metertmeter (n mz/m) ohm circular millfoot
ohm square meterlmeter (Q mz/m) ohm foot - -
-
ohm square metedmeter (Q m2/m) ohm inch
ounce-force (avoirdupois) newton (N)
ounce-mass (avoirdupois) g-
cornusnor
EngineeringConversion Factors

MurnLY BY M OBTAIN
ounce-mass (troy) 31.1035 g-
(Note: 12 troy ounces = 1troy pound-mass)
ounce (U.K. fluid), volume measure 28.4131 cubic centimeter
ounce (U.S. fluid), volume measure 29.5735 cubic centimeter

parsec 3.08374 x 10" meter (m)


pascal (Pa) (pressure, stress) 1.00000* newtodsquare meter (Nlmz)
pascal (Pa) 10.0000* microbar or dynelsquare centimeter
pascal (Pa) 0.0075064 millimeter mercury (0C) or tom
pascal (Pa) 2.95301 x lo-' inch mercury (32O F )
pascal (Pa) 1.45038 pound-forcelsquare inch
pascal second (Pa-s) ~OOO.OO* centipoise
pascal second (Pa-s) ~o.oooo* dyne-secondlsquare centimeter
pascal second (Pa's) 0.0208854 pound (force)-secondlsquarefoot
pascal second (Pa.s) 2419.09 pound-masslfoot-hour
pascal second (Paas) 0.671969 pound (mass)/foot-second
pascal second (Pa-s) 0.0208854 slug/foot-second
picojoule (pJ) 6.24146 million electron volt
pint (U.K. liquid) 0.568262 cubic decimeter
pint (U.S. liquid) 0.473177 cubic decimeter
pint (U.S. dry) 5.50611x lo-' cubic meter (m3)
pint (U.K. liquid)/1000barrels 3.57426 cubic decimeterlcubicmeter
poise (absolute viscosity) O.~OOOOO* pascal-second (Pa-s)
pound-mole 0.45359237* ,- kilomole (kmol)
pound-molelcubic foot 16.0185 kilomole/cubic meter (kmol/m3)
pound-mole/gallon (U.K. liquid) 99.7763 kilomole/cubic meter (kmollm3)
pound-mole/gallon (U.S. liquid) 119.826 kilomole/cubic meter (kmol/m3)
poundal 0.138255 newton (N)
poundal 0.0310810 pound-force
poundal-foot (1959 international foot) 0.0421401 newton-meter (N-m)
pound-force, avoirdupois (lbf) 4.44822 newton (N)
pound-force 32.1740 poundal
pound (force)-foot 1.35582 newton-meter (N-m)
pound (force)-footfinch 53.3787 newton-meterlmeter (N-ni/m)
pound (force)-inch 0.112985 newton-meter (N-m)
pound-forcelfoot 14.5939 newtodmeter (Nlm)
pound-forcelinch 175.127 newtodmeter (Nlm)
pound-forcelsquarefoot 0.0478803 kilopascal (kPa)
pound-forcelsquare inch (psi) 6.89476 kilopascal (kFa)
pound-forcelsquareinch-foot 22.6206 kilopascallmeter (kPa/m)
pound (force)-second/squarefoot 47.8803 pascal second (Pa-s)
pound-mass, avoirdupois (lbm) 0.45359237* kilogram (kg)
pound-mass, avoirdupois (lbm) 1.21528 pound (troy)
pound-mass, avoirdupois 7000.00
pound-mass, troy 5760.00* g d
.-
COA6BmnON
Engineering Conversion Factors

--

MULTIPLY BY TO OBTAIN

pound-mass, avoirdupois slug (mass)


pound-massharrel kilogram/cubic meter (kg/m3)
pound-mass/cubic foot (density) kilogram/cubic meter (kglm3)
pound-mass/foot kilogram/meter (kglm)
pound-masslfoot-hour pascal second ( b s )
pound-mass/foot second pascal second ( b s )
pound-mass/gallon (U.K. liquid) kilogram/cubic decimeter
pound-mass/gallon (U.S. liquid) kilogra&cubic, decimeter
pound-mass/1000 gallons g r d c u b i c meter
(U.K. liquid)
pound-mass/1000 gallons gradcubic meter
(U.S. liquid)
pound-masshour kilogradsecond (kgls)
pound-masslhour square foot - kilogram/second-square meter (kg/sm2)
pound-mass/minute kilogram/second (kgls)
pound-mass/mole kilogram/mole (kgtmol)
pound-mass/second kilogradsecond (kgls)
pound-mass/second-foot kilogradsecond-meter (kg1s.m)
pound-mass/second-squarefoot kilogrdsecond-square meter (kg/s.m2)
pound-mass/square foot kilogram/square meter (kg/m2) ./
pound (mass)-footfsecond kilogram-meterlsecond (kg-ds)
pound (mass)-squarefoot kilogram-squaremeter (kg-m2)
(moment of inertia)
Q
quart (U.K. dry) quart (U.S. dry)
quart (U.S. dry) quart (U.K. dry)
quart (U.K. liquid) cubic decimeter
quart (U.K. liquid) liter
quart (U.K. liquid) quart (U.S. liquid)
quart (U.S. liquid) cubic decimeter
quart (U.S. liquid) liter
quart (U.S. liquid) quart (U.S. dry)
quart (U.S. liquid) quart (U.K. liquid)

R
rad (radiation dose absorbed) gray (Gy) (joule/kilograrn)
radian (rad) second (angle)
radian (rad) minute (angle)
radian (rad) degree (angle)
radian (rad) grad
radianlsecond (radls) revolution/second
radianlsecond (radls) revolutiodminute
radiadsecond squared (radls2) revolutionlsecond squared
radiantsecond squared (rad/s2) revolutionlminute squared
revolutiodminute - radiantsecond (radls)
COMBUSTION
Englneerlng Conversion Facton

MUIXWLY BY TO OBTAIN

revolution/minute squared 0.00174533 radianlsecond squared (rad/s2)


revolutiodsecond 6.28318 radiantsecond (radls)
revolutiontsecond squared 6.28318 radiantsecond squared (rad/sz)
rod (U.S. suwey, 16.5 ft. exactly) 5.02921 meter (m)
roentgen 2.57976 x * coulomb/kilogram (C/kg)

S
second (angle) 4.84814 x lo-' radian (rad)
section (1square statute mile) 2.5898 square kilometer (kmf)
section (U.S. survey) 640 acre
siemens (S) (electrical conductance) 1.00000* amperelvolt (AN)or mho
siemenslmeter (S/m) 0.025400* amperelvolt inch
slug (mass) 32.1740 pound-mass (avoirdupois)
slug (mass) 14.5939 kilogram (kg) -
sluglcubic foot (density) 515.379 kilogram/cubic meter (kg/m3)
slug-foot (1959 international foot) 4.44822 kilogram-meter (kgsm)
slug/foot-second 47.8803 pascal second (Pa-s)
square foat (1959 international) 0.09290304* square meter (ma)
square footlhour (thekal diffusivity) 25.8064* square millirneter/second
square footlpound-mass 0.204816 square meterkilogram (mz/kg)
square footlsecond 9290.304* square millimeterlsecond
square foot pound (mass)lsec2 0.0421401 joule U)
square inch (1959 international) 645.160* square millimeter (mma)
square kilometer (km') 0.386101 section (1square statute mile)
square kilometer (kmz) 0.386102 square mile (1959 international)
square meter (ma) 10.7639 square foot (1959 international)
square meter (ma) 2.47104 x lo-' acre (U.S. survey)
square meter (ma) 1.19599 square yard (1959 international)
square meter/kilogram (mz/kg) 4.88243 square footfpound-mass
square mile (1959 international) 2.58999 square kilometer (ha)
square millimeter (mm2) 0.00155000 square inch (1959 international)
square millimeterlsecond (mmz/s) 1.07639 x lo-' square footfsecond
square millimeter/second (mm2/s) 0.0387501 square foothour
square millimeter/second (rnm'ls) 1.00000* centistoke
square yard (1959 international) 0.836127 square meter (m2)
standard cubic footmarre1 0.0075182 kilomolelcubic meter (kmol/m3)
(60F, 1atmosphere)
standard cubic foot 0.0011953 kilomole (kmol)
(60F, 1atmosphere)
standard cubic meter . 0.044616 kilomole (kmol)
(OC, 1atmosphere)
standard cubic meter 0.042293 kilomole (kmol)
(lSC, 1atmosphere)
statampere 3.33564 x lo-10 ampere (A)
statcoulomb 3.33564 x 10-lo coulomb (C)
C0IS)USTION
Engineering Conversion F8ctors

MULTIPLY BY TO OBTAIN

statfarad 1.11265 x farad (F)


stathenry 8.98755 x 10'' henry (HI
statohm 8.98755 x lo11 ohm (Q)
statvolt 299.793 volt (V)
stere 1.00000* cubic meter (ma)
stokes (kinematicviscosity) lo-' square meterlsecond (m2/s)
stokes 10.7639 x -' square foot/second
T
temperature (see "degree" for temperature interval or difference)
temperature, degree Fahrenheit, t, = 1.8tC+ 32
temperature, degree Celsius, t, = (t, - 32)/1.8 = 0.555 556 (t, - 32)
temperature, degree Kelvin, tK= Tc + 273.15 (by definition)
temperature, degree W i n e , t, = t + 459.67 (by definition)
temperature, degree Kelvin, tK= 0.555 556 t,
temperature, degree Rankine, t, = 1.8 tK
temperature, degree Fahrenheit, t, = 1.8tK- 459.67
temperature, degree Celsius, t, = 0.555 556t - 273.15
tesla (T) magnetic flux density 1.0000* weberlsquare meter (Wb/m2)
tesla (T) 10 OOO.O* gauss
telsa (T) 64 516.0* linehquare inch
therm (10' Btu, I.T., Eur. Comm.) 105.506 megajoule (hljl
t h e m (U.S., natural gas) 105.4804* , megajoule (MJ)
ton-force (U.K., 2240 lbf) 9.96402 kilonewton (IrN)
ton-force (U.S., 2000 lbf) 8,89644 kilonewton (kN)
ton (force) (U.S.)-foot 2.71164 kilonewton meter (kN-m)
ton-force (U.S.)/square foot 95.7605 kilopascal (kPaJ
ton-force (U.S.)/squareinch 13.7895 megapascal (MPa)
ton-mass (U.K. long or gross) 2240* pound-mass
ton-mass (U.K. long or gross) 1.01605 megagram (Mg)
ton-mass (U.K. long or gross) 1.01605 metric ton or tonne
ton-mass (U.K. long or gross) 1.12000 ton-mass.(U.S. short or net)
ton-mass (U.S. short or net) 2000* pound-mass
ton-mass (U.S. short or net) 0.907185 megagram (Mg)
ton-mass (U.S. short or net) 0.907185 metric ton or tonne '
ton-mass (U.S. short or net) 0.892857 ton-mass (U.K. long)
ton-metric (tonne) 2204.62* pound-mass
ton-metric (tonne) 1.00000* me~af3ram(Mg)
ton-metric (tonne) 0.984206 ton-mass (U.K. long)
ton-metric (tonne) 1.10231 ton-mass (U.S. short)
ton-mass (U.K.)/day 0.0117598 kilogradsecond (kg/s)
ton-mass (U.S.)/day 0.0104998 kilograrn/second (kg/s)
ton-mass (U.K.)/hour 0.282235 kilogradsecond (kg/s)
ton-mass (U.S.)/hour 0.251996 kilogram/second(kgls)
ton-mass (U.K.)/minute 16.9341 kilogram/second (kgls)
ton-mass [U.S.)/minute 15.1197 kilogram/second (kgls)
CO~mnOlO
Engineering Conversion Facton

M'uImPLY BY TO OBTAIN --

ton-mass (U.S.)/square foot 9.76485 megagram/square meter (Mglmz)


ton refrigeration (12000 Btuh) 3.517 - kiloktf (kW)
ton (nuclear equivalent of TNT) 4.184 x loa joule (J) (defined, not measured)
ton (ram mercury, 0C) 133.322 pascal
U
unitlfoot 3.28084 unitlmeter
unithenry 1.00000* amperelweber (AtWb)
unitlmeter 3.28084 volt/meter (Vim)
v
volt (V) electric potential) 1.00000* wattlampere (WIA)
voltlfoot 3.28084 voltlmeter (Vlm)
voltlinch 39.3701 voltlmeter (Vlm)
volttmeter (Vlm) 0.304800* voltlfoot
voltlmeter (Vlm) 0.025400* voltlinch
volume parts per million ~.oOOoO* cubic centimeterlcubic meter
W
watt (W) (power) 1.00000* joulelsecond Uls)
watt (W) 3.41214 Btu (I.T.)hour
watt (W) 44.2537 foot-pound (force)/minute
watt (W) 0.737562 foot pound (force)/second
watt (W) 0.860421 kilocalorie (thermochemical)hour
watt hour (W-h) 3.60000* kilojoule (kJ)
wattlinch (international) 39.3701 wattlmeter (Wlm)
wattlmeter (Wlm) 0.025400* wattlinch (international)
' wattlmeter kelvin (W1m.K) 0.577789 Btu (1.T.)-foot/hour square footF
wattlmeter kelvin (W1m.K) 6.93347 Btu (1.T.)-inchhour square foot O F
wattlmeter kelvin (W1m.K) 8.60421 calorie (thermochemica1)-cmlhourcm*"C
, wattlmeter kelvin (W1m.K) 0.00239006 calorie (thennochemical)-cmlsecondcmz "C
' wattlsquare meter (W/mz) 0.316998 - Btu (I.T.)/hour square foot
wattlsquare meter kelvin (Wlm2.K) 0.176110 Btu (I.T.)/hour square foot OF
, wattlsquare meter kelvin (WImz.K) 0.860421 kilocalorie (thermochemica1)hourcm*OC
watt second (W-s) 1.00000* joule 01
1 weber (Wb) (magnetic flux) 1.00000* volt-second (V-s)
weber (Wb) 1.00000x 10' line
weber (Wb) 1.00000 x 10' maxwell
' weberlampere (WbIA) - 1.00000* h e w &I)
Y
I yard (1959international) 0.914400* meter (m)
COMBUSnON
Subject Index Aat-Ana

SUBJECT INDEX
Page numbers for tables, graphs, and illustrations are in italics.

in pulverized-coal preparation, 11-17, 11-21, 14-31


regenerative (Ljungstrom), 11-17, 14-23, 14-28, 14-29
A, atmospheric air for combustion, 4-5, 4-6, Appendix C sootblowers in, 14-33
ABMA, 6-11, 12-18, 12-19, 20-44, 2045, 1 5 4 , 15-25, temperature in, 6-6, 14-23, 14-28, 14-31, 14-36, 21-3
C-3 tubular, 14-23
Abrasion, See also Erosion Air horsepower (Ahp), 14-4
from flyash. 23-21 Air leakage, in air heaters. See Air heaters, leakage in
of coal piping, 23-19 in precipitator, 6-12
of pulverizers, 11-12, 23-18 Air preheater, See olso Air heater 14-23, 19-13
Access to boilers, 10-5, 23-5 Air pollution control, See Control of power-plant
ACET (average cold-end temperature), 6-6, 14-23, 14-26, stack emissions, Chapter 15
14-36. 21-3 Air rise, definition, 14-28
Achieving high thermal efficiency in fossil power Air supply, BFB combustor, 9-15
plants, 1-13 Air supply, CFB boilers, 9-25
Acidlalkaline, corrosion, 20-22 Air systems, in pulverizers, 11-18, 14-23, 14-30
Acid cleaning, 21-15 Air temperature,
precautions, in, 21-17, 21-20 for combustion, 6-5
procedures in, 21-16, 21-19 forced draft fans, 6-5, 6-39, 14-2
solvents, 21-17 in pulverizers, 7-39, 11-5, 11-17
Acid dew point, 3-30, 14-26, 14-36 Airflow,
Acid-leaching of coal ash, 3-13 in fans, 6-35, 14-2, 14-5, 14-19
Acid sludge, 2-32 in pulverizers, 11-17
Acid smuts, 3-29 start-up, 7-39, 21-5
Acid wash, 21-13 in tangential firing, 10-8
Acoustic steam-leak detection (ASLD) system, 13-37 Airfoil centrifugal fan, 14-2, 14-6, 14-7, 14-8, 14-9
Acoustics, in fans, 14-23, 14-45, 1 4 4 9 AISC, 6-59
Activated carbon absorption, FGD, 15-35 Alekhnovich, A.N., B-17
Active alkalies, 3-12, 3-24 Alignment in pulverizers, 11-31
Acquisition of circulation design data, 7-11 Alkali, in coal, See olso Active alkalies; Inactive alkalies,
Additive utilization, 15-50 3-11, 3-14, 3-24
Adiabatic process, 4-12 corrosion indicator, 3-24
Advantages of C-E Controlled Circulation 7-22 Alkali-iron-trisulfates, 3-25
Advantages of pendant panel design, 7-6 Alkaline cleaning, 21-14
Advantages of horizontal-surface design, 7-6 Alkaline sludge, 2-33
Advantages of heat-pipe air preheater, 14-24 Alloys, Chapter 10 (Metallurgy and Materials)
Aeration of flyash, 16-4, 16-25, 1 5 2 6 , 16-27 in fans, 14-23
Aeration of raw water, 20-4, 20-6 in jet pumps, 16-11
AFBC (atmospheric fluidized-bed combustion), 9-30 in spray towers, 15-52
Agglomerating index, 2-4 in superheaters and reheaters, 6-42, 17-31
Agglomerating properties of coal, 2-3, 2-15, 11-7 Alumina, wear-resistant material. 23-20
Air, composition of, 4-2 American Boiler Manufacturers Assocktion, See ABMA
Air blockage, in reheater, 21-21 American Institute of Steel Construction, See AISC
Air density, 4-2, 6-35, 14-2, 14-5 American National Standards Institute, See ANSI
Air distributors in AFBC, 9-9 American Petroleum Institute, See API
Air and gas pressures, 6-32, 13-30, 14-5 American Society of Mechanical Engineers, See ASME
Air and gas volume calculations, 6-35. 14-6 American Society for Testing and Materials, See ASTM
Air heaters, 14-23 American Welding Society, 17-2, 18-18
BFB boilers, 9-16 Amines, in feedwater treatment, 20-16
CFB boilers, 9-28 Ammonia in outage condensate. 20-28
cleanliness of, 14-26, 14-33, 21-3 Analysis,
corrosion of, 14-23, 14-26, 14-29, 14-36 of bagasse, 2-26
design, 5-11, 6-13 of coal, 2-7,2-16, 2-18, 3-17, 22-5, Appendices A and C
fouling, 14-24, 14-26, 14-30, 14-33 of coal-tar pitch, 2-23
gas flow, 6-14, 14-3, 14-30 of cokes, 2-23
heat-pipe, 14-24 of dry wood. 2-24
leakage in, 6-6, 6-40, 14-3, 14-24, 14-26, 14-28, of fuel gas, 2-33
14-30, 14-32 of fuel oil. 2-31
in marine boilers, 10-17 of fuel properties. 4-5, 22-5
conmusnou
Subject Index An.-Aut

of furnaces, 6-16, 7-4 third party inspection, 18-2


of hog fuels, 2-25 ASME Boiler and Pressure Vessel Committee, 17-2
hydrodynamic, 5-22 ASME, Certificate of authorization, 18-2
of refuse as fuel. 2-27 ASME Furnace Performance Factors Committee, 11-3
of U.S. water supplies, 2 0 4 , 20-5 ASME Performance Test Codes, PTC, 22-1
of water, 21-12 PTC 3.2, 22-5
Analytical evaluation (of remanent life), 24-13 PTC 4.la, 22-22, 11-24
Anemometer, 15-67, 22-22 PTC 4.1, 6-8, 15-3, 22-27
Anisotropic properties of steel, 17-3 PTC 4, 22-25
Annual outage, maintenance and planning, 23-4 PTC 19.5, 22-4, 22-14, 22-22, 22-23
ANSI, ANSIIASTM, standards and specifications. PTC 27, 22-14, 22-19
See ASTM Specifications and Standards ASMEIEEI Corrosion Laboratory research program,
Anthracite coal, 2-3, 2-5, A 4 8 20-22
Anthracite coal filters, for raw water, 20-8 ASME Short Form efficiency test, 6-9, 22-27, 22-28
Anti-Friction Bearing Manufacturers Association, Assessment of remaining life of steam-generator
AFBMA, 11-32. 11-33 Components, 24-7
API scale, gravity of oil, 2-30, 2-32 ASTM grain size index, 17-9
Approximation formula, coal analysis, 2-8, 2-13 ASTM Specifications and Standards, 17-2
Archimedes number, 9-7 coal classification.
Arc-welding, tube assemblies, 18-14 D 388, 2-3, 11-7, A-3, A-48
Arrangement of upper-furnace heating surface, 7-6 coal sampling.
Ash. D 388, 2-3, 11-7, A-3, A-48
analysis, 3-2, 3-28 D 409, 2-13, 114
in cascade evaporator, 8 4 6 D 2013, 2-7, 22-4
in chemical recovery boilers, 8-59 D 2234, 2-7, 22-4
in coal, Chapter 3, Appendix B. See also Coal ash D 2492, 2-12
content, 8 4 8 , 15-2, Chapter 2, and Appendix A D 3172, 2-8
corrosion from, 3-21, 3-28 A D 3174, 2-11, 3-2, 3-3
density, 16-4 D 3175, 2-11
deposits, 3-1, 3-11, 3-15,3-16, 3-24, 7 4 , 8-16, 1 2 4 , 21-2, D 3176, 3177, 2-12
B-1, B-3, B-16 , D 3302, 2-9
design considerations, 6-15, 7-1, 7 4 , 8-3, 8-6 coal-ash sampling,
disposal, 7-6, 15-64, Chapter 16 D 1856, 1857, 2-13, 3-5, 3-11
fusibility, 2-13, 3-5, 3-7, 3-10, 7-4, 7-8, B-5 D 3174, 2-11, 3-2, 3-3
handling of, Chapter 16 gaseous fuel sampling.
heat loss from, 6-8, 6-9, 16-30 D 1070, 2-35
in fuel oil, 2-32 D 3588, 2-34
in marine furnaces, 10-10 pulverized coal sampling
properties, Chapter 3, 7-1, 7-4, Appendix B D 197, 11-11
removallcooling systems, BFB boilers, 9-16 solid-fuel heating value
removallcooling, CFB boilers, 9-28 D 2015, 2-13
resistivity, 15-12 steam sampling,
slurry, 16-12 . D 1066, 1125, 1428, 1888, 2186, 2 0 4 6
Ash-erosion test facility, Kreisinger Development Atmospheric air
Laboratory, 25-9 for combustion, 4-5, 4-6, 4-21, ~ ~ ~ e n dC i x '
Ash-fusibility temperature, 2-13, 3-5, 3-7, 3-10, 7-4, thermal NO,, 4-30
7-8, B-5 Atmospheric fluidized-bed combustion (AFBC), 9-30
Ash-handling systems, Chapter 16. Atmospheric pressure,
See Ash-removal systems NACA report 1235, 6-37
Ash-level, in bottom hoppers, 16-6, 16-7, 16-8 Atomizer test facility, Kreisinger Development Laboratory,
Ash-removal systems, Chapter 16 25-6
bottom hoppers in, 16-6, 16-9, 16-10, 16-12, 16-15 Atomizers, in marine boilers, 10-19
control systems, 16-27 Attrition mills, 11-23
in fluidized-bed boilers, 9-16, 9-28 Audibert-Arnu Dilatometer Test, coal, A 4 7
material and energy-balance considerations, 16-29 Audibert, E., 11-3
heat removal, 16-30, 16-32 Audio-visual training, of operators, 21-33
Ash-softening temperature, 2-13, 3-5, 7-4, 7-8 Austenitic steel,
ASME Boiler and Pressure Vessel Code, 6-45, 6-50, corrosion of, 3-23, 3-26, 17-23
17-2. 18-1, 24-8 in high temperature service, 17-3
creep rates, 6-56, 17-16, 24-10 sigma phase, 17-6
cycling boilers, 7-48 welding, 18-12
inspectors, 17-2 Authorized inspectors, 18-2, 23-11
material selection, 6-42, 6-45, 17-2 .Automation of control systems, 1-22, Chapter 13
shell specifications, 6-46 Automatic drain valve, sootblowers, 14-34
COMBUSTION
Subject Index Aut-Bol

Automatic fusion welding, 18-2 reduction zone, 8-50


Automatic steam temperature controls, 5-9, 5-11, 7-39 smelt and water explosions. 8-62 -
Automatic voltage controls, 15-10 start-up, 13-26
Auxiliary equipment, 1-21, 1-28, 1-29, Chapter 14 sulfur in, 8 4 6
Auxiliary fuel firing in chemical recovery boilers, 8-53 water removal .W5,8-47, 8-48
Auxiliary steam for start-up 20-30 . Blade pitch changes, axial-flow fans, 14-9
Availability factor, 24-2 Blade shapes, fans, 14-6, 14-7
~vailability,maintaining, Chapter 24 Blast-furnace gas,
Availabilitvlreliabilitv and life continuation, 24-6 cleaning of, 241, 8-26, C-36
Available static head for furnace circulation, 7-13 dust in, 241, 8-26
Average cold-end temperature, See ACET as fuel, 2-42, 8-26, C-36
Axial-flow fans, 14-2, 14-7, 14-13, 14-18, 14-22 Bleed steam, 1-5, 10-17
Blisters, repair of, 23-14
Block system, of generator additions, 1-25
Blowdown lines, 5-29
Blowdown in safety valves, 21-25
Back corona in precipitators. 15-12 Blowing cycles, in sootblowers, 14-38, 1441
Back-pressure turbine, 1-13. 1-14 Blowing media, in sootblowers, 14-38
Backward curved blade, fans, 14-6, 14-7 Blue gas, water gas, 2-39
Baffle plates in steam drum, 5-26, 8-9 Bogomolov, W., B-17
Bag filters, See Fabric filters Boiling of water, in boilers, 5-1, 5-18. See also DNB
Bag houses, See Fabric filters Boiler, See also Boilers for process uselpower production;
Bagasse, 2-26. See Biomass Combined Circulation boiler; Controlled Circulation
combustion calculations. C-15, C-18 boiler; fluidized-bed boiler; supercritical-pressure
Balanced draft, 6-31, 6-39, 13-25, 13-29, 13-32, 24-6 steam generator
Balanced thermal loading, 6-51 access to, 10-5
Ball-race mills, 11-234 auxiliary equipment, Chapter 14
Ball-tube mills, 11-222 bank, 8-2, 8-10,8-23, 8-24
Bar-and-key grate assembly, 12-16, 12-17, 12-22, 12-24 calculations, 6-28
Barge shipment of boilers, 8-42 capacity, 1-9, 1-14, 5-6, 6-3, 8-30, 8-37, 8 4 6
Bark, as fuel, 2-24, 2-25, 8-12, 12-19, 12-20 casings. 10-20
Barometric pressure, chemical cleaning of, 21-14, 21-15
in ductwork. 6-35 circulation in, 5-14,5-15, 5-16, 5-18, 5-20, 7-10, 7-13,
in stacks, 6-37 7-16, 7-25, 7-26, 7-29, 14-41
Barrett, Elliott l?, 3-6 controls, 5-11, 10-14, 21-6, 23-17, Chapter 13
Base-load mode, 7-32 design, 5 4 ,Chapter 6, 8-3, 10-1
Battersea process, FGDS, 15-28 efficiency, 1-3, 1-13, 1-26, 6-1, 6-3, 6-13, 8-2, 8-3, 8-30,
Bearings in pulverizers, 11-32, 11-33 21-2. 22-24.22-25, 22-27
Bed expansion. in BFB. 9-10. 9-13. 9-14 exit-gas temperature, 5-11, 6-6, 6-7, 8-30, 14-23, 21-2
Bed particle size, BFB combustion, 9-13 feedwater, 21-11
Bed-zone slumping, BFB combustor 9-14 field construction of, Chapter 19
Beer, J.M., 6-16 fluidized-bed, Chapter 9
Belt feeder, for coal, 11-14 for burning process or sewage sludge, 8-28
Bending stress. 6-49. 6-56 for burning shredded rubber, 8-29
Bent-tube boilers, 10-6 function of, 5-2, 5-6
Berl, E., 20-14 heat absorption, 5-8, 8-2
BES, See Bulk entrainment separators heat-transfer rates, 6-19, 6-21, 6-28
BFB boiler for industrial application, 9-17. 9-18 industrial. Chapter 8
BFB boiler for utility application, 9-17, 9-18 load patterns, 10-1,See Cycling
BFB versus CFB, 9-9 manufacture of, 8-36, Chapter 18
Bicarbonatelcarbonate ratio, 1542 marine, Chapter 10
Bi-metallic tubes. 3-23. 8-61 material selection, 6-42, 6-45, 17-2, 1 7 4
Binary cycle. See Combined gas-turbinelsieam-turbine operation of, Chapter 21
cycle radiant, 8-11
Biomass, burning of, 8-3,84, 8-7 reheat, 1-6, Chapter 7
Bisulfitelsulfite ratio, 15-42 setting height, 16-16
Bituminous coal, 2-3, 2-5, Appendices A and C shop assembly, 8-36
Black liquor. in steel-making. 8-26 '
as fuel. 845, 846. 8-50 testing of. Chapter 22
ash content, 8 4 6 waste-heat, 1-16, 8-30, 8-35, 840, 10-10
boilers, 842, 8 4 6 Boiler drums, 5-25, 7-15, 7-17, 8-9, 10-6, 17-3, 18-2
chemical recovery of, 8-45 feedwater lines, 5-29
delivery system. 8-52 internais, 5-25, 7-16, 7-18, 8-9, 18-3, 18-5
oxidizer. 8 4 7 Boiler-follow control systems, 13-19
--
Boiler simulation facility, Kreisinger Development CAD (continuous ash discharge) grate. 12-15
Laboratory, 25-7 Calcium-carbonate scale, 20-13
Boiler stress and condition analyzer (BSCA), 13-38 Calcium oxide. See Lime
Boiler turbine systems, 1-6, 1-9, 1-12, 1-14, 7-27, 7-42 Calcium sulfate scale, 20-13, 15-44, 15-56
Boiler water treatment, Chapter 20: 20-11, 2046, 20-20, Calculations,
20-26, 20-35, 20-38, 20-39, 21-11 air and gas volumes. 6-35
concentrations, 20-45 ash-fusibility temperature, B-5
Boilers for process uselpower production, Chapter 8 combustion, 4-2,4-5.4-20, 6-4, Appendix C
. Boltzmann constant, Kg, 4-12, 6-19 draft losses, 6-33
Boston Edison- Mystic Station (FGD), 15-35 draft loss in ductwork, 6-35
Bottom ash, 16-1, 16-3, 16-5 draft loss in stacks, 6-37
Bottom-ash hoppers, Gibbs function, 4-22
capacity, 16-7 graphical methods. Appendix C
temperature of water in, 16-29 heat balance, 6-3, 6-13, 16-29
types of, 16-5, 16-6, 16-15 heat transfer, 6-16, 6-21, 6-28
Bottom-ash removal systems heating surface, 6-28, 6-30
BFB boilers, 9-16 stack effect. 6-33
CFB boilers, 9-28 temperature distribution, 6-50
dry, 1 6 1 5 Calibration of instruments, 22-22
hydraulic systems, wet, 16-5, 16-11, 16-13 Campbell, M.R., 2 4
mechanical systems, 16-5 Canned motor pump, 14-42
Bnttoming cogeneration cycles, 1-13 Capacity,
Bwrdon gage, 22-12 additions. 1-23, 1-25
Bowl mills, See also Pulverizers, Chapter 11 control of fans, 14-13
Boyton, Frederick P., 6-19 factor, 1-26, 1-29, 24-2
Bradford breakers, 11-13, 11-14 fans, 14-2, 14-5
Breeching, 10-21, See also Ductwork Capital investments, 1-29, 1-32
Brinell test, hardness, 17-14
British Standard method, ash fusibility, 3-6 Carbon dioxide, 4-3
British Thermal Unit, Btu, 2-13, Appendix D excess air, 4-5, 22-6, C-5
Brittle failure, 17-14 percentage, in combustion analysis, 4-5, C-5, C-9
Brittle fracture. See also Hydrogen damage in heat removal from water, 20-4
treatment, 17-10 Carbon loss, in coal firing, 2-19, 6-9, 8-3, 8-5, 22-7
Brown coal, 2-6, A-20, A-23, A-24, A-27. A-28, A-43, Carbon monoxide, 2-41, 6-9, 8-27,22-7
A-47, A-48, A-53 Carbonization of coal and coke, 2-1, 2-20, 2-21
Btu, in fuels, See Fuels; Heating value 2-13 Carburetted water gas, 2-40
Bubbling fluidized-bed combustion, process Carnot cycle, 1-3
considerations, 9-10 Carnot, Sadi, 1-3, 11-1
Bubbling fluidized-bed combustor, 9 - 4 Carryover, 5-25, 5-29, 5-31, 2 0 4 1 , 20-43. See olso Steam
Bubbling fluidized-bed steam generator, 9-9 separation
Buckstays, 6-50, 6-59, 19-11 Cascade evaporator, 8-47.8-48
'Bulk entrainment separators, 5-27, 5-28, 15-39, 15-54 Casing-head gasoline, 2-36
Bulk electrical resistivity, 15-5 Cast iron, in economizers, 5-10
Bureau of Mines, 2-14, 11-2, A-1, A-12, A-43 Castings, steel, for boiler pressure parts, 17-4
Burl and Van Taack curve, 20-14,20-15, 20-22 Catalysts (petroleum refining), regeneration of, 2-40, 8-27
Burner aerodynamics test facility, Kreisinser Development Catalytic decomposition, 15-65
Laboratory, 25-6 CCS, Coordinated Control System, 13-20
Burner barrel, atomizers, 10-19 C-E Acoustic Steam-Leak Detection (ASLD) system, 13-37
Burner-zone heat release, 7-5 C-E Availability Task Force, 24-4
Burners, 6-12, 7 4 , 7-9, 8-6, 8-10, 8-30, 8-50, 8-53, 9-14, C-E Boiler Stress and Condition Analyzer (BSCA), 13-38
9-24, 10-19, Chapter 12 C-E Bowl Mills, 11-6, 11-23, 11-28, 21-8, 23-18. See C-E
Burning characteristics of coal, 2-14, 3-1, 6-15, 7-1, 8-3, pulverizers
9-3, 10-9, 11-1, Chapter 12 C-E Combined Circulation Boiler, 7-25, 7-26, 7-27, 7-30,
Butterworthing, 10-13 7-31 flow in, 7-27, 7-28, 7-31, 7-33
By-pass systems, start-up, 7-36, 7-44, 7-46, 20-35, 20-36
damper control, 5-12, 5-13 turbine system in, 7-26, 7-31
in once-through operation, 5-16 C-E Combusco submerged conveyor, 16-15
marine economizers, 10-16 C-E Controlled Circulation Boiler, 7-7, 7-12, 7-13, 7-16,
turbine, 7-42 - 7-18, 7-20, 7-21
By-product fuels, 1-21, 8-26, 12-15. See also specific fuels, -advantages of, 7-22, 7-24
Chapter 2 comparison with thermal circulation, 7-12, 7-24
cyclic operation, 7-37, 7-40, 7 4 1
feedwater quality, 7-23, 20-26, 20-30,20-31
furnace design, 7-18, 7-24
Caking of coal, 2 4 , A-46, A-47 pressure in, 7-13, 7-20, 7-23
COMBUSTION
Subject Index C.EC.Coa

pumps in, 7-17, 7-23, 7-25, 14-41 reliability and maintainability, 8-63
recirculation systems, 7-13, 7-17 smelt explosions, 8-62
start-up, 7-17, 7-39, 7-41, 7 4 2 , 21-4 starting burner arrangement, 8-54
steam-drum internals, 7-18 with oxidizer and cascade evaporator, 8-47
strainers and screens, 7-18 Chemical systems. Kreisinger Development Laboratory, 25-11
tube spacing in, 7-18 Chimney action, draft (stack effect), 6-33
water treatment, 7-23 Chrome refractory, 8-60
C-E Coordinated Control System (CCS), 13-20 Chromizing, 8-62
C-Eldb mass-burning grate (for refuse firing), 12-22 Cinder reinjection, spreader stoker firing. 12-19
C-E Distributed Programmable Control, 13-14, 13-16 Circulating fluidized-bed steam generators, 9-5, 9-18
C-E Drop-'kbe Furnace System (DTFS, KDL). 2-15, 6-10 Circulating fluidized bed, 9-2, 9-5, 9-9, 9-23
C-E Multi-coated Metallizing, 8-6 Circulation of fluid, 5-14, 5-18, 5-20. See C-E Controlled
C-E HP pulverizer application, 11-28 Circulation Boiler
C-E HP pulverizer, operation, 11-18 ' Circulation ratio, 5-19
C-E HPS or HPPS bowl mill (pulverizer) for use with Circulation system, combustor, CFB boiler, 9-26
exhauster, 11-30 Circulation systems, BFB boilers, 9-16
C-E Interactive water-chemistry Management System Circulation, thermal (thermosyphonic). See Thermal
(ICMS). 13-37 circulation
C-E On-Line Thermal Information System (OTIS). 13-35 Clarifier, water treatment, 20-4, 20-6
C-E OPSIZE system (coal fineness control), 13-36 Classification of cogeneration plants, 1-13
C-E Raymond Roller Mill, 11-23, 11-25 Classification, International Coal. A-43
C-E Schnabel rail car, 8 4 1 Claus sulfur recovery system, 15-35
C-E Steam generator with RC grate for burning RDF, 8-23 Closed powerlprocess cogeneration cycle, 1-14
C-E Supercritical steam generator for full sliding CLE, cyclic life expenditure, 7-42, 7-43
pressure, 7-34 Cleaning,
C-E lkaveling-grate stoker, 12-14 airheaters, 14-26, 14-33, 21-3
C-E 'kbe-Temperature Monitoring System (TTMS), 13-38 boilers, 14-37, 21-14, 21-15
C-E Type RC spreader stoker, 12-21 blast furnace gas, 2-41, 8-26, C-36
C-E Q p e SM sectional header boiler, 10-5 coal, 2-7
C-E V2M81V2M9 Vertical Superheater Boilers, 10-6, 10-7 furnace walls, 14-37
C-E VU-40 Boiler, 8-8, 8-9, 8-12 superheaterlreheater, 21-20
C-E VU-60 Boiler, 8-14, 8-15, 8-28 Cleanliness, effect on
C-EIEVT Submerged Scraper Conveyor (SSC), 16-15 air heaters. 21-3
Cellulose fuel firing on spreader stokers, 12-19 steam temperature, 10-13
Central computer facility, Kreisinger Development Clinker grinders,
Laboratory, 25-16 bottom hoppers, 16-11
Central-station steam generators, Chapter 7 single-roll grinder, lM1
Centrifugal fans, 14-2, 14-6, 14-7, 14-8, 14-9, 14-14, Clinkers (burning coal on stokers), 12-15
14-17, 14-22 Closed-circuit grinding, 11-11
Centrifugal type drum internals, 7-15, 7-16, 7-17, 7-18, 8-9 Closed-loop fluid regenerative air heater, 10-18
CETOP (C-E Total On-Line Performance) system, 13-35 Clusters, in CFB boilers, 9-19
CFB (circulating fluidized bed), 9-5, 9-9 CO, See Carbon monoxide
CFB boiler for industrial application, 9-29 COZ,See Carbon dioxide
CFB boiler for utility application, 9-29, 9-30 Coagulation of raw water, 20-4
CFB combustor pressure profile, 9-20 C.O.A.L. World Coal Study, A-1
CFB steam generator, 9-19 Coal. See Chapter 11 for pulverizers and pulverized-coal
Chakrawrty method (ash fusibility), B-6 systems
Char, 2-14, 2-17 alkalies in, 3-11, 3-14, 3-24
Characteristic curves, fans, 13-31, 14-10, 14-11, 14-12, bituminous, 2-5
14-13, 14-14, 14-16, 14-21 blending, 3-27
Characteristics of fuels, Chapter 2, Appendices A and C brown. See Fuels (coal, brown coal)
Chemical analytical services, Kreisinger Development caking in, 2-4, A-46, A 4 7
Laboratory, 25-12 characteristics of, 2-1 through 2-19, 15-4, Appendix A
Chemical cleaning, 21-14, See also Acid cleaning; Alkaline chloride content, 3-27
cleaning Classification, International, A 4 3 , A44, A-47, A 4 9
Chemical processes, fluidized-bed combustion, 9-5 cleaning, 2-7
Chemical recovery boiler, 8-42 corrosion from, 3-21, 3-25
air system, 8-51 crushers. 11-13, 11-14
auxiliary fuel firing, 8-53 deposits, worldwide, 2-18, Appendix A
decanting bottom, 8-57 fineness, for pulverized firing, 11-6
corrosion, 8-58 fineness control (C-E OPSIZE system), 13-36
design basis, 8-54 firing on spreader stokers, 12-17
using direct-contact evaporation, 8-47 fixed carbon in. 2-4, 2-11
process zones, 8-51 flammability indices, 2-15
COMBUSTION
Subject Index Coa-Cok

formation of, 2-1 handling systems, 7-4. Chapter 16


free-swelling index, FSI, A-46 heat transfer through, B-3
fuel NOx, 4-32, 12-6, 12-8, 4-35, 4-36 iron in, 3-2, 3-4, 3-9, 3-10, 3-18, 3-21, B-14
furnace design, 6-15, 7-1, 7-4, 8-3, 8-6 lime in, 3-4, 3-9
fusion temperature, 2-13, 3-5, B-5, B-11 magnesia in, 3-4, 3-9, 3-10
grindability, 2-13, 11-3, 11-5, 11-6 minerals, 3-3, 3-6
handling in power plants, 21-30 potassium, 3-4, 3-11, 3-24
hard, International Classification, A-43, A-44 properties of, Chapter 3, 16-4, Appendix B
Hardgrove grindability machine, 11-4 removal. See Ash, ash handling systems
heating value, definition, 2-13 silica in, 3-4, 3-8, 3-9, 3-11
hydrogen in, 2-8,2-16, 2-18, Appendices A and C slag, 3 4 , 3-18, B-11, B-15, B-16
ignitionldevolatilization, 2-14 sulfur in, 3-4 -
impurities in. 2-6, 2-11 thermal behavior, 3-3, 3-10, 3-18, B-3, B-11
iron content, 3-4, 3-9, 3-10, 3-16, 3-18, 3-21, B-14 total alkali, 3-12 3-14, 3-24
minerals in, 3-3, 3-7, 3-13, 3-18 viscosity, B-11
moisture content, 2-8, 2-12, 8-6, 11-4, A-2, C 4 Coal classification, Chapter 2, Appendix A
nitrogen in, NOx, 2-12,Z-16,2-18,432, Appendix A, C-10 ash-free basis. 2-4, A-2
preparation for market, 3-26 comparison of international and U.S. classification
properties of, Chapter 2, 3-18, Appendices A and C systems, A-48
particulate emission control, 15-4, Chapter 15 code numbers in international system, A-43, A 4 4
pulverized-coal-burning central-station steam generator, by rank, 2-2, 2-3, 2-4, 11-7, A-2
7-2 Coal feeders, 11-14, 11-15
quality, decline in, 24-5 Coal-fired boilers. See also Marine boilers:
sampling, 2-7 burning other fuels, 7-9, 8-2, 8-6
spreader design, 12-17 carbon loss in, 2-19, 6-9, 8-3, 8-5, 22-7
stokers, 8-3, 8-6, 10-20, 12-13 control systems, 13-7, 13-16, 13-26, 13-28
sulfur in., 2-12, 15-2, 15-26 design of, Chapter 6, Chapter 7, 8-3
wlatiIe matter in, 2-10, A-2, C-6 fans in, 14-2
water in. See Coal-moisture content fuel flexibility, 8-2, 8-6
of the world, 2-18, Appendix A heat absorption, 6-20
Coal additives and blending, 3-27 industrial boilers, Chapter 1
Coallair exhauster fans, 11-35 maintenance and rkpair, Chapter 23
Coal analyses, 2-16, 2-18, 3-14, 7-3 Appendices A and C nozzles, 6-13, 12-4, 12-5
in furnace design, 6-15, 7-1, 7-4, 7-9, 8-3, 8-6 panels and platens in, 6-16, 7-4, 7-6
foreign coals, 2-18, Appendix A particulate emissions, 8-5, Chapter 15
U.S. coals, 2-16, 3-14, 7-3, A-5, A-7, A-11, A-53, C-10 performance data, 10-9
Coal analysis, 2-7,2-16,2-18, 3-17, 22-5, Appendix A, C-10 pulverized coal, Chapter 7, 8-3, 8-6, 8-10: Chapter 11,
See also ASTM Standards and Specifications 12-5, 16-7
Audibert-Arnu dilatometer test, A-47 Scotch marine boiler, 10-4
gravity fractionation, 3-17, 3-18, 3-19 sootblower system, 14-33, 14-37
Gray-King coke-type test, A-48 sulfur oxide, SOx, 8-6, 15-2, 15-27
free-swelling index, A 4 6 Coal mining, 2-6, 3-15, 3-26
moisture cgntent, 2-8, 2-12, 8-6, 11-4, A-2, C-4 Coal pulverizers, 8-3, 8-6, 11-15, 11-21, Chapter 11.
oxygen in, 2-12, 4-2, 4-5, 11-9, C-6 See also Pulverized coal; Pulverizers
Parr formulas, 2-8 Coal size, 8-3
proximate analysis, 2-4, 2-9, 2-13, 11-9, C-5 Coal spreader design, 12-17
Roga-index test, A-47 Coal tar, 2-22 '
testing methods, 2-7, 2-12, A-46, A-48 Coal tar pitch, 2-22, 2-23
ultimate analysis, 2-7, 2-12, 4-5 a Coalification, 2-1
U.S. Bureau of Mines, 2-14, 11-2, A-1, A-12, A-43 Coal yard design and management, 21-31
Coal ash, 2-11, 2-14; Chapters 3, 7, and 16; Appendix B. Coal-water fuel (CWF) pilot plant, KDL, 25-7
See olso Slag Code numbers in coal classification, A-45
baselacid ratio, 3-8 Codes and specifications. See specific codes under ASME,
chemical analysis, 3-2, 3-6 ASTM, ANSI, U.S. Bureau of Mines, American
composition of, 2-11, 3-2 Welding Society
cooling curves, coal-ash slag, B-16 Cogeneration,
density, 1 6 4 definition, 1-12
deposits from Western type ash, 3-11 in industrial boilers, 1-9, 1-14, 8-2
- - deposit removal, 3-7, 14-33, 14-34, 14-37, B-17 Cogenerative steam cycles, 1-9, 1-13, 1-15
- dolomite percentage, 3-10 Cohen, P., B-11, B-16
flow temperature (slag), B-12 Coke, 2-20, 2-23, C-11, C-12
fouling potential, 3-1, 3-11, 3-15, 7-4, 8-16 button test. See Free-swelling index
in furnace design, 3-1, 6-15, 7-1, 7-4, 8-3, 8-6 carbonization of coal, 2-1, 2-20,z-21
fusion temperature, 2-13, 3-5, 3-7, 3-10, 7-4, 7-8, B-5 destructive distillation of, 2-20
COMBUSTION
Subject Index Cok-Coo

Coke breeze, 2-20, C-11 Constant-pressure program for C-E Combined Circulation
Coke-oven gas, 2-38,240. C-31, C-34 steam generator, 7-26
Cold primary-air system, 11-20, 14-3, 14-30 Constant-volume determination (of fuel heating value), 22-5
Cold working, Construction, Chapters 18 and 19
brittle failures, 17-10.17-14 - component lifting, 19-9
grain size. 17-9 drums, 18-2
Cold-end temperature, 6-6, 14-23, 14-26, 14-36, 21-3 fans, 14-7, 14-9
Collection efficiency (particulate), field construction, 19-3
of mechanical cyclone collectors, 15-6 furnace walls, 18-9
of fabric filters, 15-23 headers, 18-6
of precipitators, 15-8, 15-11 manager, 19-1
of venturi scrubbers, 15-8 non-destructive testing of components, 18-14
of wet scrubbers, 15-7 superheaters, reheaters, economizers, 18-12
Colorgraphic Animated Schematics, 13-18 welding of erected components, 19-17
Combined circulation. See C-E Combined Circulation boiler Continuous ash discharge grate (CAD), 12-15
Combined gas-turbinelsteam turbine power cycles, 1-14 Continuous ash removal, 16-5, 16-15, 16-19, 16-25, 16-26,
Combustible loss correction factor, 4-7, C-8, C-12 16-29
Combustion and combustion process, Chapter 4 Continuous dewatering systems, 16-14
air for, 4-2, 4-5, 4-6, 4-17, 4-27, 5-11, 6-5, 14-2 - Continuous fin construction, 18-12
chamber, 12-2 Continuous ignitor, 12-10
chronology of, 2-14 Controlled circulation. See C-E Controlled Circulation Boiler
control systems, 10-14, Chapter 13 Controlled leakage pumps, 14-44
correction factors, 4-6, 4-7, 6-7, Appendix C Control system management, 21-1
efficiency, 6-4, 6-9, 22-3 Control systems, operational, Chapter 13
equations, 4-3, 4-5 ash handling, 16-27
entropy and enthalpy of, 4-25 boiler-follow, 13-19
flow patterns, 10-3, 12-2, 22-18 by-pass damper control, 5-13
fluidized-bed-combustion, Chapter 9 cathode-ray tubes (CRT), 13-1, 13-2, 13-18, 13-22
fundamentals of, 4-2 chemical recovery boilers, 13-26
products, 4-3, 4-5, 4-7, 4-20, 6-7, 6-16, Appendix C circulating fluidized-bed boilers, 13-28
reactions, 4-17, 12-1 computer systems, 13-13
residual, 4-12 coordinated-control systems, 13-19
theory. Chapter 4 desuperheating, 5-12
Combustion air, 4-2.4-5,4-6, 4-17,4-27, 5-11.6-5. Chapter 12 diagnostic systems, 13-35
Combustion analysis, 4-20, 4-22, Appendix C fans, 14-13, 14-19
Combustion calculations, Chapter 4.4-5.4-20.64, Appendix firing equipment, 13-27
C. See dso specific fuels; graphical methods (Appendix fuel. 13-19
C); million Btu method, 4-5, C-1; mole method, 4-5 fluidized-bed boilers, 13-28
Combustion Engineering, history of, furnace explosions, 13-3
Introduction furnace implosions, 13-29, 13-31
Combustion Engineering Research and Development furnace safeguard systems, 13-8, 13-11
Facilities, Chapter 25 gas flow, 15-69
Combustion process, chronology of, 2-14 gas recirculation. 5-12
Combustion rate, See also specific fuels, industrial boilers, 1-22, 13-23
in furnace design, 6-15 influence of fuel, Q-26
in industrial boilers, 8-3 maintenance, 13-29, 23-17
Combustor, marine boilers, 10-12
BFB boiler, 9-15 programmable controllers. 13-16
CFB boiler, 9-26 process control, 13-19
Comparison of alternative designs, 1-26, 1-35 run-uplrun-down circuits, 13-21
Component reliability, 1-36 safety, 13-1
Composition of air, 4-2 sensors, 13-5, 13-7
Composition of explosive charges, 13-3 steam temperature, 5-11, 10-14, 13-25
Compound tubes, bimetallic, 3-23, 8-6 Convection, 6-23, 7-8
Computer programs, furnace wall stresses, 6-51 coefficients, 6-15, 6-23, 6-24
Computer technology, control systems, 13-13 correction factors, 6-25, 6-26
Concentration of reactants in combustion, 12-2 heat transfer, 6-14, 6-22
Condenser leakage, 7-23, 20-38,20-39, 21-12 Convection-surface sootblowers. 14-37
Condensing water, 1-25, 5-4 Conversion factors, Appendix E
Condition assessment (life continuation), Chapter 24. 24-7 Conveyors, ash removal, 16-5, 16-15, 16-16, 16-17, 16-26
Conditioning gas. 15-13 Cooling curves, coal-ash slag. B-15
Conditioning water. See Water treatment. Chapter 20 Cooling systems.
Conduction, heat transfer, 6-15 ash removal, 16-29, 16-32
Constant-pressure determination (of fuel heating value), 2-33 cooling towers, 1-27
COMBUSTION
Subject Index Coo-Dep

furnace walls, 5-8, 5-14, 5-18, 6-15, 7-10 Cracking, weld, 17-11
Coordinated-control systems, 13-19 Cramer, H.E.. 15-72
Coordinated phosphate control, 20-13, 20-35 Cranes, in field construction, 19-9, 19-10, 19-11
Copperas, in coagulation. 20-5 Creep, tube failures, 17-11, 20-24, 21-15, 24-10
Copper-reverberatory gas, 8-26 Creep rate, 17-16, 17-18, 17-19
Coprecipitation of sulfate, 15-46 Crevices. See Pitting corrosion
Correction factors, Critical components, determination of, 24-12
convection heat transfer, 6-25, 6-26 Cross-drum boilers, 10-5
pulverizer capacity, 11-5, 11-6 Cross-section of drum, 5-26, 7-16, 7-18, 8-9
solid-fuel firing, 4-7, C-3 Crosseley, H.E., 3-12
Corrosion, 3-21, 3-22, 3-25, 3-28, 20-17, 20-19, 20-20, Crude oil, 2-21, 2-27
20-21, 20-25. 20-26. See also Erosion: Lay-up Crushers, coal, 11-13, 11-14
procedures; Water treatment; Oxygen damage Crystallization rate, 15-45
acid dew point, 3-29, 3-30, 14-26, 14-36 Cumulative damage index, 6-57
air heater cold-end protection, 6-6, 14-23, 14-26, 14-36, CWF (coal-water fuel). 25-7
21-3 Cyclic life expenditure, CLE, 7-42, 7 4 2
air temperature, 6-6 Cyclic stress. See Fatigue
analysis, 20-39 Cycle ratio, 6-58
from ash, 3-2, 3-28 Cycles, choice of, Chapter 1, 1-9, 1-21, 1-27, 7-37
Burl and Van Taack curve, 20-14,20-15, 20-22 Cycling, 7-37. See variable load
chemical recovery boilers, 8-58 design considerations, 1-26, 7-37, 7-48
chloride levels, 3-27 expansion stress, 7-48
damage in boilers, 20-20 heat distribution, 7-50
damage in power plants, 20-17 load, 7-37, 7-38, 7-49
from coal, 3-23 in marine vessels, 10-1
concentrating film, 20-22 pressure-part design, 7-48
high-temperature, 3-21, 3-24, 3-28 steam-generator controls, 7 4 9
hydrogen damage, 20-20, 21-16 steam temperature, 7-39, 7 4 0 , 7 4 6
indicators, 3-25, 3-26 two-shift mode, 7-38, 7-50
metal temperatures, 3-28, 8-58 turbine protection, 7-26, 7-42, 7-44, 7-45. 7-49
minimizing, 3-23, 3-26, 8-60 water treatment, 7-50
pitting, 20-15, 20-18, 20-19 weekend mode, 7-38
prevention, 20-3, 20-12, 20-17, 20-25, 20-26, 20-30, 21-11 Cycling curves, idealized, 7-48
in outages, 20-26,20-31, 20-32 Cyclone collector, high-temperature, CFB boiler, 9-26, 9-27
and pH, 20-14, 20-15, 21-12
in start-up, 20-30, 20-31, 20-32
sources, 20-25
water treatment, 7-50, 20-17, 20-22
Corrosion of, Deaeration
air heaters, 3-29, 14-23, 14-26, 14-29, 14-36 of feedwater, 21-12
austenitic steel, 3-23, 3-24 in start-up, 20-15, 20-30
chemical recovery units, 8-58 Deashing of coal, 3-2
compound tube, 8-61 Decibel (power-plant noise), 14-45
economizers, 10-15 Deflectable sector plate, 14-32
fans, 14-21 Deflector blocks, 23-18
refuse-fired boilers, 8-17, 8-20, 8-25 Degasification of steam, 20-46
spray towers, 15-52 Degrees API, See Specific gravity
steel, 3-23, 3-24, 8-17, 8-20, 8-58, 17-23, 17-24, 17-30, Delayed coke, 2-21,2-22 ,

20-15 Demineralization,
Corrosion rates, 20-15, 20-22 in boilers, 5-17, 20-30
Corrosion-resistant cladding, 3-23 of raw water, 20-10, 20-11, 20-12
Corrosive deposits, 3-24, 3-25 Density.
Corrugated-plate separators, 5-27 calculations, 6-36, 6-37, C-24, C-29, C-33, C-36
Cost comparison, of coal ash, B-3
boiler types, 1-26, 1-28, 7-28, 8-3 fan volume specifications, 6-37, 6-40, 14-5
fans. 14-18 of gases, 4-4, 6-33, 6-37, 11-18, 14-2, 14-5, C-24, C-29,
fuels, 1-21 C-33, C-36
Costs. See Economics; Power-plant economics, 1-29 Density meters, 16-28.
Cottrell. Frederick Gardner, 15-8 Deposits, 3-4
Cottrell-type precipitators, 15-8 in coal ash, 3-11, 3-15, 3-24, 1 2 4 , 21-10
Courses, drum, 18-3, 18-6 composition of, 3-15, 3-16
Crack-like corrosion, 20-16, 20-19 corrosivity. 3-24
Cracking, fatigue, 17-15 selective deposition, 3-15
Cracking, of petroleum, 2-37 slagging and fouling, 21-10
COMBUSTION
Subject Index Dep-Eff

in tube failures, 20-20, 20-23, 20-25, 20-39 Dry saturated steam, 5-2, 5-4
Deposit removal, 3-7, 14-33. 14-34. 14-37. B-17 Dry scrubbing, SO2 removal, 15-32, 15-55
Depreciation, 1-31 . Dryers, for water separation. 5-29
Design. Chapter 1. Chapter 6. See also specific item ASME Drying pulverized coal. 11-15, 11-15
Code aspects, in remaining-life analysis, 24-8 D-shape boilers, shop asjembled, 8-37, 8-39 7

empirical approach, 6-20 DTFS, C-E Drop-Tube Furnace System (KDL), 2-15, 25-2
investigations, 1-21 Ductile gouging, 20-20, 20-21
and performance, 545-11,&3,10-1.7-18,7-24, Chapter 6 Ductility, 17-11, 17-13
Determination of coal ash, 2-11,2-13. See also Ash; Coal ash Ducts. See Ductwork
Deutsch-Anderson collection efficiency, 15-11 Ductwork.
Deviation-limit system, 13-22 design, 6-35
Dewatering systems, 16-14 draft losses, 6-35, 6-36, 22-23
Dew point, acid, 3-30, 5-30, 14-26, 14-36 field erection, 19-17
Diameter, equivalent, gas flow, 6-23 friction loss, 6-38
Dielectric strength, flyash, 15-11 gas recirculation. 6-41, 6 4 2
Diesel, Rudolph, 11-1 velocity in, 6-36, 22-19, 22-23
Dilatometer test, coal analysis, A-47 volume calculations, 6-35
Diluting air (leakage), 6-6, 14-28, 14-30, 14-32 Dust. See also Flyash; Chapter 15, Particulate emission
Direct-contact evaporation, 8-47 control in blast furnace gas, 2-41, 8-26
Direct-firing of pulverized coal, 11-16, 11-19 Dust collection by mechanical means, 15-6
Directional properties of steel, 17-3 Dust collector efficiency,See Collection efficiency, particulate
Discharge electrodes, precipitators, 15-8.15-9, 15-10, 15-15 Dust resistivity,'l5-12
Discontinuity stress, 6-48 Dust scrubbing, 15-6
Discount rate, investments. 1-34 Dutta. B.K., B-6
Dispersion of emissions, 15-7 DUZY.A.F., B-13
Dispersoids. 15-4, 15-5
Disposal of as.h.7-6, 15-64. Chapter 16
Dissociation reaction, 4-20
Distillation of coal, 2-20, 2-21
Distillation of petroleum, 2-21, 2-27, 2-37 Economics,
Distribution of ash, 16-1, 16-3, 16-4, 16-8
District heating, 1-9 of additive utilization, 15-50, 15-58, 15-62
DNB,departure from nucleate boiling, 5-18: 5-19, 7-35,20-24 of availability, Chapter 24
definition of, 5-18, 5-19 construction costs. 1-31
in ruptures, 20-24 and design considerations, 1-21, 1-26, 1-34
Documentation of outages, 23-10 fuel costs, 1-21, 1-30
DOE. See U.S. Department of Energy of operation, 1-30, 21-4
Dolomite, as a coal additive, 3-27 present worth, 1-30, 1-33, 1-35
Dolomite percentage (DP), 3-10 of replacement power costs, 1-29
Double-alkali system, FGD. 15-30 of start-up fuels, 7-39
Double-cased marine boilers, 10-20 of shop-assembly, 8-40
Double superheaters, 10-6 Economic studies of alternative designs, 1-26, 1-35
Draft. 6-31 in preliminary reports, 1-19, 1-21
balanced, 6-31, 6-39, 13-25, 13-29, 13-32, 24-6 of plant size, 1-25, 1-28
net, in stacks, 6-33, 6-37, 6-39 Economic analyses, 1-29
Economizers,
static, 6-33
Draft gage, 6-31, 22-6, 22-24
.. cast iron, 5-10
Draft losses, 6-2, 6-31, 6-33, 6-35, 6-37, 8-3, 22-24 circulation in, 5-10, 5-14
Drawings and specifications, 1-22 corrosion in, 5-10, 10-15
Drift velocity, 15-11 design of, 5-10, 6-27, 10-15
Drop-Tbbe Furnace System, C-E DTFS (KDL), 2-15, 25-2 erosion in, 23-21
Drum internals, 5-25, 7-15, 8-8, 18-3, 18-6 field construction, 19-14
Drum plates, 6-46, 18-2, 18-5 leaks, in, 21-28
Drum, tubes rolled in. 23-13 manufacture of, 18-12, 18-16
Drum-type units, marine boilers. 10-15
corrosion prevention, 20-26. 20-30 pressure drop in, 6-45
shutdown, 21-6 pressure parts, maintenance. 23-76
start-up, 20-31, 20-32, 20-33, 21-4. 21-5 Edison Electric Institute, EEI, 24-1
Dry bottom-ash system, 7-6, 16-15 EDTA in boiler water. 20-17, 20-40. 21-17
Dry bottom versus wet bottom, 7-6 Effect of thermal gradients on regenerative preheater
Dry box arrangement, 5-30 structural deformation, 14-31
Dry disposal, landfill. 15-63 Effective ash level, in hoppers, 16-7
Dry gas loss, 6-7, 21-2,22-11. 22-28 Effective projected radiant surface. EPRS, 6-17
Dry products of combustion, 4-3, 4-5, 4-7, 4-20, 6-7, Efficiency,
6-16. C-4 axial flow fans, 14-7, 14-16, 14-19
COMBUSTION
Subject Index Eff.Exp

boiler, 1-3, 1-13, 1-26, 6-1, 6-3, 6-13, 8-2, 8-3, 8-30, 21.-2 evaporation, 5-2
centrifugal fans. 14-7, 14-11, 14-14, 14-19 formation, 4-10, 4-11
dust collectors, 15-6, 15-7, 15-8, 15-11, 15-23 reaction, 4-9, 4-19, 4-28
electrostatic precipitators, 15-8, 15-11 saturated liquid, 5-2
and in-plant education, 21-4 stable element, 4-10
loss with economizer bypassed, 10-16 steam. 5-3. See Steam tables, Appendix D
Efficiency calculation, 22-24 Entrained water, 5-25, 6-8
precipitators, 15-11 Entrainment separators, 5-27, 5-28, 15-39, 15-54;
steam generators, 6-3, 6-13 see olso BES
Efficiency test measurement, 22-3, 22-4, 22-10, 22-24 Entropy,
Einstein's equation (relation), 4-11 combined systems, 4-12
Electric motor drive, auxiliary equilibrium constant, 4-18
auxiliary equipment, 1-22 fundamental, 4-12
fans, 14-16 Environmental factors, in planning, 1-27, 1-36, 15-1, 16-3
Electric Power Research Institute, EPRI, 24-1 Environmental Protection Agency. EPA
Electrical conductivity measurement, 20-47 methods for measuring flow rate and sample products,
Electrical engineering services, Kreisinger Development 22-13
Laboratory, 25-16 regulations on sulfur emissions, 15-36
Electrical properties of flyash, 15-5, 15-11, 15-13 EPRI. See Electric Power Research Institute
Electromagnetic radiation spectrum, 13-6 EPRS, Effective Projected Radiant Surface, 6-17
Electromotive force, Emf. See Thermocouple Equal-area zone method, 22-14. See dso Stack sampling
Electrostatic precipitation, 15-8, 15-9, 15-11 Equilibrium coefficient, 4-16
Electrostatic precipitator, ESP, 15-8, 15-9, 15-11, 15-15, Eauilibrium com~osition.4-16. 4-17
15-61, 15-69, 15-70. See olso Precipitators ~quilibriumdiag'ram, alloys, 17-18, 17-9
Electrostatic precipitator pilot plant (KDL), 25-9 Eouilibrium moisture content. 2-9. , 11-4.. A 4 6
Elemental sulfur and sulfuric acid production, 15-29, ~ q u i p m e n availability,
t 24-1, 24-3, 24-6, 24-7
15-35, 15-36 ~ q u < ~ m e manuals,
nt 23-1
Elevation correction factor, 6-13, 6-14 Equivalent diameter, gas flow, 6-23
Elongation, ductility (stress-strain), 17-13 ~quivalentlengths, t&ing, 6-46
Emergency shutdown, 13-10, 13-11, 23-4 Equivalent sulfur, ES, 6-6
Emissions, See NO,; Particulate matter; SO, Erosion and abrasion,
Emission control methods, 4-30, 12-6, Chapter 15 fans, 14-7, 14-21, 23-16, 23-18
Emission control systems, Chapter 15. See also Fabric coal piping, 23-18
Filters; Electrostatic precipitators; Precipitators; economizers, 23-21
Dust collection by mechanical means from flyash. 23-21
flow model tests, 15-69 pulverizers, 11-12, 23-18
flue-gas desulfurization. 15-28 Error analysis in field tests, 22-2, 22-26
Emission regulations, 8-6, 15-1 ,
ES, equivalent sulfur, 6-6
Emissivity, Escalation multiplier, determining costs, 1-32
of coal ash, B-3, 8-5 Eschka's sulfur determination of coal, 2-12
of gas, 6-15, 6-16, 6-18 ESP, electrostatic precipitator. See Electrostatic precipitator
Empirical design approach, heat transfer, 6-20 Essenhigh, Robert H., 6-16
End fixity of heads, 6-48 Ethylene diamine tetracetic acid, EDTA, 20-17, 20-40, 21-17
Endurance limits, See Fatigue Eutectics, 17-7
Energy considerations in, Evaporating surfaces,
ash removal, 16-29 bottom-ash receivers, 16-32
boiler efficiency, 6-4, 1-13, 1-26, 8-2, 8-3 waterwalls, 5-8, 5-16
boiler operation, 21-2 Excess air,
emission control, 15-1 for combustion, 4-5, 4-22, 6-5, 14-2, 21-2, C-3
fans, 14-2, 14-4, 14-19 O2 and COz relationship, 22-6, 22-7, Appendix C
Energy flow in steam generator, 5-6, 5-7 Exhaust gases,
Energy in fluid flow, 5-21 dry products of combustion, 6-7
Energy of reaction, UR,4-9 gas turbine, 1-16
Energy state transitions, gas-turbine heat recovery, 8-30
adiabatic process, 4-12 utilizing wasteheat, 10-10
Engineering conversion factors, Appendix E Exit gas temperature, 5-6, 5-11, 6-6.6-13, 14-23.14-30, 14-36
Engineering judgment, Exothermic reaction, 4-9
combustion calculations, 4-8 Expansion factor, BFB combustion, 9-10
operation, 21-1 Expansion method, boiler circulation, 5-23. See olso
Engineering studies, in design, 1-19, 1-21 - Thermodynamic method
Engler degree, viscosity of oil, 2-30 Expansion stress in cycling, 7-48
Enthalpy, 1-2, 4-8, 4-11, 4-28 Expenses, See Economics; Fixed Charges; Fuel costs;
combustion, 4-9 Operation and maintenance costs
compressed water, 6-3 Experimental determination of coal-ash, 3-5, Appendix B
COmUSnON
Subject Index Exp-FIa

Explosion factor, 1 3 4 variable-speed, 14-17


Explosions, furnace, 21-1, 21-28 Fatigue, 6-57, 17-15, 17-17, 24-11
Explosions in pulverizers, 11-35, 21-9 Fatigue analysis, 6-57
Explosive mixtures, 13-3 FBAC (fluidized-bed ash cooler), 9-8
Express-type boilers, 10-6 FBC. See Fluidized-bed combustion
Extendalloy for preventing erosion, fluidized-bed boilers, 9-16 FBSS, fluidized-bed supervisory system, 13-28
Extended economizer chemical recovery boiler, 8-49 FBHE (fluidized-bed heat exchanger), 9-8, 9-19.9-20, 9-27
External-type desuperheaters, 5-12, 7-39, 7-44, 10-14, FD. See Forced-draft fans
See also Butterworthing; Heating; Evaporators Feeders, pulverized coal, 11-12, 11-14
Feedwater,
analysis, 21-12
in Controlled Circulation boilers, 7-23
deaerators, 21-13
Fabric filters, dust collection, 15-16, 15-19, 15-37, 16-20, in drum-type units, 5-10, 5-29, 7-16, 20-26,20-34,2048
18-27 EDTA in, 20-17, 2 0 4 0 , 21-17
design, 15-22 flow control, 13-25
filter materials, 15-17, 15-23 heating, 1-5, 1-6, 1-8, 1-9, 1-12, 10-18
operating problems, 15-24 in marine boilers, 10-18
performance, 15-23 oxygen control, 20-15, 21-11
pulse-jet, 15-20 pH control, 20-16, 21-12
reverse air, 15-18 total solids, in 20-38
shaker type, 15-17 treatment, 5-17, 7-23, 7-27, 7-50, Chapter 20, 21-11
shakeldeflate, 15-20 Ferrisul, in coagulation, 20-5
Failure records, forced outages, 23-10 FGD, See Flue-gas desulfurization
Fan, Fiberglass-reinforced plastic, FRP, in spray tower, 15-54
acoustics, 14-23, 14-45, 14-49 Field construction, See Chapter 19
air horsepower, Ahp, 14-4 Field investigation, carryover, 2 0 4 2 , 2 0 4 4
capacity, k - 2 , 14-5 Field tests, 6-8, 6-20, Chapter 22
characteristic curves, 14-10, 14-11, 14-19, 14-21 Ferric oxide in coal ash, 3-2, 3-4, 3-9, 3-18, B-14
construction of, 14-7, 14-9 Ferric percentage, see Ferric oxide in coal ash
control. 14-13, 14-19 Film coefficient, thermal loading, 6-51
corrosion, 14-21 Filters for raw water, 20-5, 20-7
design considerations, 6-38, 14-4, 14-5, 14-17, 14-19 Fineness, pulverized coal, 11-5, 11-6, 11'9, 11-12. 11-26
energy factors, 6-31, 6-38, 14-2, 14-4 Fins, 6-51, 6-52, 18-11, 23-14
drives, 14-16 Fire point, fuel oil, 2-31
erosion, 14-21, 23-16, 23-18 Fired steam generators supplied with gas-turbine exhaust,
gas density, 6-37, 6-40, 14-5 8-34
laws, 14-19, 14-20 Fires, 21-28
liners. 14-22 in furnace, 21-28, 21-11
maintenance, 23-4, 23-16, 23-15 in mills. 11-36, 21-9
maximum continuous rating, 14-6 Fireside Performance Test Facility (FPTF), KDL, 25-2
noise, 14-23, 14-45, 14-49 Firing equipment control. 13-27
operating conditions, 14-5, 14-19 Firing refuse in industrial boilers, 8-14
operating principles, 14-4 Firing systems, 4-28, 5-11, 6-10, 6-12, 6-15, 7-4.7-11, 8-3,
performance testing, 14-11, 23-16 10-8, 10-9, Chapter 12 .
pressure, 6-39, 6 4 0 , 6-41. 14-4 development complex, Krelsinger Development
selection, 14-17 Laboratory. 25-4
specified capability, 6-38 duct burner (HRSG], 8-34
speeds, 14-12, 14-15, 14-18 fluidized-bed, 4-30. Chapter 9
stall, 14-15, 14-20 horizontal type, 7-5, 8-15, 8-37, 8-39, 10-19, 12-2, 12-3,
tolerances, 6-39, 14-5 13-13
vibrations, 14-15, 14-21, 23-16 stoker, 4-29, 8-12, 8-14, 12-13, 12-14, 12-23, 12-25
volume calculations, air and gas, 6-35 suspension, 4-29, 7-1, 8-25
Fans, Chapter 14, tangential, 6-16, 7-2, 7-11, 8-8, 8-26, 8-28, 10-8, 10-9,
axial flow, 14-2, 14-7, 14-13, 14-18, 14-22 12-4, 13-12
centrifugal, 14-2, 14-6, 14-7, 14-8, 14-9, 14-10, 14-14, that minimize nitrogen-oxide formation, 12-6
14-17, 14-22 Fixed carbon, in coal, 2-3, 2-4, 2-7, 2-11, 2-16, 2-18,
forced-draft (FD), 6-32, 6-39, 14-2 Appendix A
and gas-cleaning equipment, 8-6 Fixed charges, 1-30, 1-31
gas recirculation, 5-13, 6-41, 14-3 Fixed tangential firing, 8-28
in implosions, 13-29 Five-hole probe (directional pitot tube). 22-21
induced-draft [ID), 6-40. 13-32. 14-3, 1 5 4 Flame characteristics, 4-31
primary air, 11-16, 11-18, 14-2 Flame collapse, 13-29
pulverizer, 11-18 Flame detectors, 13-5
COMBUSTION
Subject Index FIa-Fue

Flame emissivity, 6-16, 6-18, 13-5 Flux welding, 18-6


Flame monitoring, tangential firing, 13-10, 13-12 Fluxing property of coal ash, 3-8
Flame spectrophotometry, water tests, 2 0 4 6 Flyash,
Flammability indices of coal, 2-15, 11-7 accumulation, 6-22
Flash and fire points of fuel oil, 2-31 conditioners, 16-27. 16-28
Float and sink separation, 3-17 disposal, 15-24, 15-62, 15-64, Chapter 16, 22-4
Flocculation. See coagulation erosion, 14-7, 14-21, 23-21
Flow increase, thermal head, 5-21, 7-19, 7-24 heat transfer, effect on, 6-22
Flow model tests, 15-69, 15-71, 25-8 hoppers, 15-15, 15-16, 15-24, 16-24
Flow patterns, 10-3, 12-2, 22-18 methods, of collection, 15-4
Flow and pressure drops, 5-22, 6-32, 6-45, 7-19, 14-5 particle size, 15-2, 15-4, 15-15
Flow temperature of slag, B-12 properties, of 15-11, 15-13, 15-72, Appendix B
Flow turbulence, 22-2 sampling, 15-6
Flue-gas, terminal velocity, 15-5, 16-1, 16-2
analysis of, 4-5 Flyash removal systems, 16-20
calculation of, 4-5, 4-20, Appendix C BFB boilers, 9-17
cleaning process development (KDL),25-8 CFB boilers, 9-29
reheaters, 15-55 continuous, 16-5, 16-15, 16-16, 16-19, 16-25, 16-29
scrubbers, Chapter 15 fluidizing-type flyash intake, 16-21
velocity of, 6-23, 6-24, 7-8 intermittent, 16-20
Flue-gas desulfurization systems, FGDS. See Chapter 15 mechanical conveyors, 16-26
Fluid coke, 2-22 pressure, 16-21, 16-22, 16-23
Fluid flow, vacuum, 16-20, 16-22
energy in, 5-21 vacuum-pressure, 16-23
friction, 5-21, 7-20 Foam carryover, 5-29, 20-42
Ohm's law analogy, 6-22 Foam formation, 20-42, 20-43
Fluid-to-fluid heat transfer rates, 6-22 Food-processing wastes, as fuel, 2-26
Fluid regenerative airheater, 10-18 Foerster, E.F., B-2
Fluid temperature, FOR, Forced outage rate, 24-2, 24-5
in Combined Circulation, 7-29, 7-31, 7-34, 7-35 Forced-draft fans, 6-32, 6-39, 14-2
in heat exchanger, 6-27 boiler infiltration, 6-40
logarithmic mean temperature difference, 6-26 entering air temperature, 6-5, 6-39, 14-2
Fluid velocity measurement, 22-19 Forced outage maintenance, 23-11
Fluidization, Forced oxidation, 15-50
description of, 9-1 Forged reinforcing rings for boiler drums, 17-3
of flyash, 16-21, 16-25, 16-27 Formation and control of NO, in steam-generators, 4-30
Fluidized-bed combustion, fluidized-bed firing, See Chapter 9 Formation of coal, 2-1
Fluidized catalytic cracking (FCC), 2-37, 2-40, 9-1 Forming headers, 18-6
Fluidized-bed ash cooler (FBAC), 9-8 Fossil fuels, Chapter 2
Fluidized-bed boiler (fluidized-bed steam generator); Bubbling Fouling,
fluidized bed (BFB); Circulating fluidized bed (CFB) alkali content, 3-11, 3-15, 3-24
bed expansion, BFB, 9-14 in air heaters, 14-24, 14-26, 14-30, 14-33
heat transfer in, 9-7, 9-8 from coal ash, 3-1, 3-11, 3-15, 3-16, 3-24. 7 4 , 8-16
installation, Great Lakes Naval Base, 9-2 deposits, 3-15, 3-24, 12-4, 14-33, 21-10, B-1, B-3, B-16
operation of, 21-26 Fractionation, coal analysis; 3-17
start-up, 21-26 Franklin Institute of Pennsylvania, 17-1
supervisory (control) system, 13-28 Frazer, Persifor, Jr., coal classification
tube rupture, 21-27 Free enthalpy. See Gibbs Free Energy
Fluidized-bed combustion, 9-7, Free gas area, 6-2, 6-23, 6-30
bed thermal inertia, 9-3 Freeboard, BFB boiler, 9-10
bed temperature, 9-3, 9-13, 9-23 Free-swelling index, A 4 6
C-E pilot plant, 9-2 Frequency analysis of noise, 14-23, 14-45, 14-49
characteristics of, 9-3, 9-5 Friction-factors, 5-21, 6-34, 6-38, 7-20
chemical processes, 9-5 Front firing. See Horizontally fired systems
development of, 9-1 Froth flotation, 2-7
efficiencies, 9-5 Frozen smelt, 8-57
fuel flexibility, 9-3 FSSS, Furnace Safeguard Supervisory System, 13-8,
in-situ capture of sulfur dioxide, 4-30, 9-4, 9-13, 9-23 13-11, 3-14, 13-26
nitrogen-oxide production, 4-30, 9-4, 9-6, 9-13, 9-23 Fuel,
- test facilities, Kreisinger Development Laboratory, 25-3 and air ratio, 13-3, 21-2
TVA 160-MW unit, 9-17, 9-18 analysis, Chapter 2, 4-5, 22-5, Appendices A and C;
Fluidized-bed firing, 4-30 see Analysis (of specific fuels)
Fluidized-bed heat exchanger (FBHE), 9-8 burning equipment, 8-10, Chapter 12
Fluidizing velocities, BFB combustion, 9-10, 9-13 choices, 1-21, 5:7, 7-1
COMBUSTION
Subject Index Fue-Fus -

combustion calculations, Chapter 4: 4-2, 4-5, 4-20, liquid waste fuels, 8-7, 8-10, 8-26
6-4, Appendix C natural gas, 2-35,2-36, 2-37, C-21, C-23
combustion constants, 2-34 petroleum coke, 2-21
combustion processes, Chapter 4 refuse, municipal and industrial, 2-27
constant-pressure calorimeter, 2-33 - - technology, Kreisinger Development Laboratory, 25-2
constant volume determination. 2-13, 22-5 wood, 2-23,2-24, 2-26, C-15, C-17
costs, 1-21, 1-30 bark, 2-24,2-25
and design considerations, 5-7, 7-1 hog fuel, 2-25
efficiency, 4-6, 6-3 Full sliding pressure supercritical design, 7-32
feed system, BFB boilers, 9-11 Full-scale burner facility (KDL). 25-4
feed system. CFB boilers, 9-24 Fundamental entropy, 4-12
fired, 6-4, 6-12 Fundamental temperature, 4-12
firing systems, Chapter 12; Firing systems Furnace,
flexibility, 7-1, 8-6 aerodynamics test facility (KDL), 25-9
flow measurement, 22-4 analysis, 6-16, 7-4, 8-3, 8-50, 8-51
heating value. Chapter 2, Appendices A and C circulation. See Circulation, thermal; C-E Controlled
hydrogen in, 2-8, 6-8, Appendices A and C Circulation combustion processes, Chapter 4
NO,, 4-30, 4-31, 4-32, 4-33, 7-4, 12-6 construction, 18-9
in products, 4-5, Appendix C design, 5-8, 6-14, 6-17, 6-20, 7-1, 7-5, 8-3, 8-4, 10-3
oil, 2-28, 2-29, Appendix C empirical design approach, 6-20
preparation system, BFB boiler, 9-14 explosions, 13-2, 13-8, 21-1, 21-28
preparation system. CFB boiler, 9-24 flame area. 6-19
properties, Chapter 2, 22-3, Appendices A and C fires, 21-11, 21-28
sampling, 2-7, 11-4, 11-11, 22-4 gas temperature, 22-10
and sorbent feed systems, BFB boilers, 9-11 implosions, 13-29, 13-31
specifications for spreader-stoker firing, 12-18 performance, 6-14
sulfur in, 2-12.2-28, 2-31, 2-32, 15-2, 15-26 radiation, 4-29, 6-15, 6-19, 6-22, 6-26, 6-28, 16-30
supply reliability, 1-36 recirculation, in walls, 5-14, 5-18, 7-13
systems development, Kreisinger Development release rate, 6-17, 7-4, 8-4
Laboratory, 2 5 4 seasoning. 21-2
Fuel burning, Chapter 4, 10-19, Chapter 12 size, 6-15, 7-1, 8-3, 8-4, 10-3
Fuel burning systems, 8-6, 11-15, Chapter 12 stresses, 6 4 9 , 6-55, 6-56
marine boilers, 10-19 temperature probes. 14-40
Fuels. testing, 6-20, 6-55
ash in, 16-2, 16-3; see Ash; Coal ash thermal loading, 6-49, 7-48, 7-49
bagasse (biomass), 2-26, 8-4, 8-7, C-15, C-18 tubes, 6-21, 6-22, 23-13
biomass, 8-4, 8-7 volume, 6-17, 7-5, 8-4
black liquor, 8-42, 8-44, 8-45, 8-46, 8-50 wall systems, design of, 7-10. See Furnace wall
coal, 2-1, 2-3, 2-4, 2-15, 2-16, Chapter 11, Appendices Furnace plan heat-release rate (NHIIPA), 6-16, 6-17, 7 4
A and C Furnace wall,
anthracite, 2-3, 2-5, Appendices A and C circulation in, 5-14, 5-18, 5-20, 6-50, 7-10, 7-12
bituminous. 2-3. 2-5. A ~ ~ e n d i c A
e sand C circulation in subcritical-pressure steam generators, 7-12
brown coal, 2-6, A-13, A-20, A-22, A-25, A-43, A - 4 7 clean up, 20-35, 20-36
lignite, 2-3.2-4, 2-5, 11-4, A-10, A-20, A-23, A-47, A-54 in Controlled Circulation, 7-13, 7-17, 7-18, 7-24
peat, 2-1, 2-4, 2-6, A-5, A-18 design considerations, 5-8, 6-49, 6-52, 7-10, 7-18
subbituminous, 2-4, 2-7, A-10, A-16, A-54 field construction, 19-10, 19-12
coal tar, 2-22 fins, 6-50, 6-52, 23-14
coal tar pitch, 2-22, 2-23 fusion panel welder, 18-10, 18-11
coke, 2-2, 2-20, 2-23, C-11, C-12, C-13 header-to-header differential, 7-19
coke breeze, 2-20. C-11 heat flow, 7-10
food processing wastes, 2-26 maintenance and repair, 23-11
fuel gas, 2-33. 2-34 manufacture, 18-9, 18-10, 18-11
blast furnace gas, 2-41, 2-42, 8-26, C-36 mechanical loading, 6-50
coke oven gas, 2-38, 2-40, C-31, C-34 metallurgy, Chapter 17
liquefied petroleum gas, 2-36, 2-38 offset bender, 18-10, 18-11
natural gas, 2-35.2-36. 2-37, C-21, C-23 performance, 5-8, 7-18
producer gas. 2-38 pressure, 5-14, 7-10, 7-13, 7-23, 7-26, 7-32, 7-46
refinery and oil gas, 2-37,2-39, 8-26, C-29 sootb:owers, 15-3
water gas, 2-39, 4-22 strainers, and screens, 7-18
fuel oil, 2-28, 2-29, 2-31, C-19, C-22 temperature, 5-19, 6-52
oil refinery refuse fuel, 2-32 two-phase flow, 5-18
petroleum. 2-27 tubes, 6-50, 7-10, 18-9, 18-13, 23-13
sludges. 2-32 Fusion-panel welding, 18-9, 18-10, 18-11
liquid fuels. 2-27. C-23. See olso fuel oil Fusion temperature of coal ash, 2-13, 3-5, 3-7, 3-10, 7-4,
COMBUSTION
Subject Index Fur-Hea

7-8. B-5, Appendix B. See also Ash fusibility: deposit Gravity fractionation of coal, 3-17
removal, 3-7. 12-4. 14-33, 14-37 Gray-King coke type test, A-48, A-51
Fusion-welded construction, 6-49, 8-8,18-9 Grindability index. 2-13, 11-3, 114, 11-6. See also
Hardgrove method
Grinders, for clinkers, 1611
Gypsum production, 15-32, 15-64
Gypsum supersaturation, wet scrubbing, 16-29
Gage pressure. 6-31
Gages, 6-32, 22-8, 22-10, 22-12. See &so, Control systems;
Instrumentation
Garbage as fuel. See Refuse
Gas conditioning, 15-13 Hammer (impact) mills, 11-22, 11-27
Gas density calculations, 4 4 , 6-35, 14-5 Hard-face welding (chemical recovery units), 8-61
Gas emissivity, 6-16 Handhole plates, 10-5
Gas flow, Hard coal, A-43
in air heaters, 6-13, 14-23, 14-24, 14-28 Hardening of steel, 17-10, 17-14
boilers, Chapter 6 Hardgrove method, 2-13, 11-3, 114
control devices, 5-13. 15-69 Hardness deposits. See Scale
eauivalent diameter. 6-23 Hardness, removing, 20-6
fahs, 14-5 Hardness testing, 17-14
and heat transfer. 6-21 HEA ignitor, 12-12
measurement. 22-13 Head on drum, 6 4 7 , 6 4 9
Gas furnace design, 6 4 6 , 7-9, 8-7 Header-to-header differential, 7-19
Gas metal arc welding (GMAW), 19-18 Heat. See also Enthalpy
Gas-to-gas absorptivity, 6-18 absorption, 5-6, 6-2, 6-15, 6-18, 6-20, 7-9, 7-17, 8-2,
Gas-to-liquid phase, 15-39, 15-41 22-3, 22-10
Gas-phase reaction, 4-23, 4-33 absorption rates, 6-3, 6-15, 6-21, 6-28, 8-2, 22-3, 22-10
Gas pressure drop. See Ductwork; Friction factors: Pressure balance, bottom-ash handling systems, 16-29
Gas calculations, 6-33, Appendix C balance calculation, 4-7, 6-3, 6-12, 6-13, 16-29, 22-24
Gas flow measurement and sampling techniques, 22-13 balance of steam-topping cogenerative cycle, 1-15
Gas quantity calculations, 4-5, 6-36. Appendix C credits, heat balance, 6-4, 6-11
Gas recirculation' systems, detectors, 13-5
as control device, 5-13, 6-41 distribution in cycling, 7 4 9
fans, 6-41, 14-3 exothermic, 4-9
Gas-side efficiency, 14-28 flow, 5-21, 6-14, 6-21, 7-10
Gas temperature, 6-6, 6-19, 6-20, 6-27, 14-5, 14-28, loss of ash from stoker or fluidized bed, 6-9
14-36, 21-3 losses, ash handling, 16-30
Gas tungsten arc welding (GTAW), 19-17 losses, boiler, 5-4, 5-7, 6-4, 6-11, 6-13, 21-3: 22-24,
Gas turbine systems, 1-12, 8-30, 8-34 22-27, 22-28
cycles in, 1-14 rates (power-plant), 1-9, 1-16, 1-26, 1-29, 7-37
heat recovery, 8-30, 8-32, 8-33 release rates, 6-16, 6-17, 7-5, 8-4
Gaseous fuels, 2-33, 6-7, 22-6. See also Blast furnace sensors, 13-5
gas; Natural gas value. See HHV, LHV
Gaseous products of combustion, 4-3, 4-20, 15-2, 15-4, Heat-duty distribution,
15-26, Appendix C BFB boiler, 9-1
Gases, combustion constants of, 2-34 CFB boiler, 9-21, 9-22
Gaussian distribution. 15-72 Heat in bottom ash cooling water, 16-30
Geiger-Mueller tube, 13-5 Heat of liquid, 5-2, 6-3
Generating reserve, 1-24 Heat of reaction, 4-9, 4-28
Generators. See Boilers; Steam Generators Heat pipe as a thermodynamic system, 14-24
Geometrical configuration of tubes and fins, 6-51 Heat-pipe air heater, 14-23
German Standard, coal fusibility, 3-6 Heat recovery equipment
Gibbs-Dalton law, 4-17 air heaters, 5-7, 5-11, 10-16, 14-23
Gibbs Free Energy, 4-12 boilers, 5-10, 6-13, 10-15
Gibbs function calculations, 4-16, 4-22 design, 8-30, 8-38
Gibbs and Helmholtz functions, 4-12 economizers, 5-7, 5-10, 6-22, 6-27, 18-12
Gibbs-Helmholtz equation, 4-15 marine boilers, 10-15
Girth seam in drum, 18-6 steam generators, HRSG, 8-30, 8-33
Goals of operator training, 21-1, 21-31 unfired, 1-16, 8-30, 10-10
Grain boundaries, i n alloys, 17-9, 17-10 Heat storage capacity, 21-27
Grain size, 17-6. See also Heat treatment Heat transfer, 6-14, 6-21, 6-28
Grain size index, 17-10 from ash, B-3
Graphical methods of combustion analysis, 4-8, Appendix C calculations, 6-16
Graphitization of steel, 17-11, 17-23 coefficients, fluidized-bed boilers. 9-7, 9-8
COMBUSTION
Subject l n d u Hoa-Ion

and corrosion test loop, KDL; 25-9 Hydrogen sulfide, H2S, removal, water treatment, 20-4
empirical design approach, 6-18, 6-20 Hydrostatic pressure, 5-22, 7-13
in fluidized-bed boilers, 9-7
logarithmic mean temperature difference, 6-26
non-luminous radiation, 6-26
rates, 6-21, 6-23, 6-25, 6-28
surfaces, 5-6, 6-14, 6-17, 6-21, 6-28, 8-58, 14-26, 22-3, ID. See Induced-draft fans
22-10 Ideal cycling curves, 7-49
Heat treatment. 17-11, 17-12. See also Phase diagrams; Ideal gases, 4-16
TTT curves IGCI, Industrial Gas Cleaning Institute, 15-4, 15-25
Heat of vaporization, 5-2 Ignitionldevolatilization of coal, 2-14
Heating loads, seasonal, 1-20 Ignition energy, 12-9, 12-10
Heating value, 2-13, 4-9. See also specific fuels Ignition systems, 12-8, 12-9, 12-11, 12-12, 12-13
Helmholtz free energy function, 4-15 Impact strength, 17-14
Hemispherical head, 6-47 Impact tube, pressure measurements, 6-33, 22-19
Hero's engine, 5-5 Impaction efficiency of scrubbers, 15-7
HHV, higher heating value, 2-13, 4-9 Implosions, furnace, 13-29, 13-31
High-acid coal ash, 3-7 Impurities,
High-alkali coal. 3-11 in coal, 2-6. 2-11. Chapter 3, Appendix B
High-energy arc ignitor, HEA, 12-10, 12-12 in water, 20-1, 20-2
High-pressure heat-transfer loop, 7-11, 25-10, 25-11 Inactive alkali, 3-12 .
High-efficiency steam plants, 1-6, 1-13, 1-26 Inconel, in tube coating, 3-23
High-temperature corrosion, 3-21, 3-24, 3-28 Incremental-load cost studies, 22-3
High-temperature properties of steel, 17-16 Induced-draft (ID) fans, 6-40, 13-32, 14-3, 1 5 4
High-temperature-water boilers, 8-42 Induction pressure-welding, 18-12
High-temperature-water installation, 1-20, 1-21 Industrial boilers, Chapter 8. See also Chapter I
High-voltage conductivity cell, 15-5 Industrial Gas Cleaning Institute, IGCI, 15-4, 15-25
Higher heating value. See HHV Industrial power plants, Chapter 1, Chapter 8
History of combustion theory, 4-1 cogeneration in, 1-9, 1-14, 8-2
Hog fuel, 2-25 definition, 1-18, 8-1
Hooke's law, 17-13 design, Chapter 1, Chapter 8
Hoop stress, 20-24 Infiltration, boiler, effect on FD fans, 6-40
Horizontally fired systems, 7-5, 8-15, 8-37, 8-39, 10-19, Influence of fuel on control systems, 13-26
12-2, 12-3, 13-3 Infrared hot-spot detection system. 14-35
Hopper ash collection, 7-6, 15-15, 15-16, 16-1, 16-3, 16-24 Infrared spectra, IR, 13-6
electrostatic precipitators, 15-15, 15-16 ' Inherent ash, 2-11
fabric filters, 15-22 Inherent moisture in coal, 2-9, 11-4, 11-17. See also
flyash hopper plugging, 15-24 Moisture; Moisture content
Hopper heating, 15-25 Injection-seal pump design, 14-44
Hot-spot detection system, infrared, 14-35 Inner casings in marine boilers, 10-20
Hottel emissivity, 6-16 In-service maintenance, 23-2
Hot-wire anemometer, 22-22 In-situ resistivity, 15-6, 15-12, 15-13
Hot-working plates, 18-5 Inspectors, 17-2, 18-2, 23-11
Howden, J, and Co., 15-29 Inspection codes, 17-2, 18-2, 23-11, 24-8
Howden limellimestone scrubbing process. 15-29 Instream (external) classifier, pulverizer, 11-22.11-24,1147
Hoy, H.R., B-11 Instrument error, 6-11, 22-1, 22-26
HP pulverizer, 11-28, Instrumentation. 1-22, 13-1, 13-2, 22-11
bowl, bowl hub, and vane-wheel assembly, 11-33 Instrumentation laboratory, Kreisinger Development
a
classifier and discharge-valve assemblies, 11-34 Laboratory, 25-16
journal assembly, 11-33 Integral classifier, pulverizer, 11-24, 11-27
lubrication system, 11-32 Integral offset-bender, 18-10
millside and liner assembly, 11-32 Interest-during-construction costs. IDC, 1-31
separator body and vane-wheel assembly, 11-33 Interest multiplier, 1-33
HRSG, heat-recovery steam generator, 8-30 Internal energy of reaction, 4-9
HRSG's for incinerator gas, 8-35 Intermittent bottom-ash equipment, 16-5, 16-7, 16-17 .
HTW. See High-temperature-water boilers Intermittent-dewatering systems, 16-14
Hydraulic-beam press. 18-4 Internals. See Drum internals
Hydraulic jack methods, 21-25 International coal classification, A-43, A44, A-47, A 4 9
Hydraulic systems, in ash removal, 16-5 International Organization for Standardization, coal
Hydrazine, in corrosion prevention, 20-15, 20-26, 21-14 classification, A-46
Hydrodynamic principles of circulation, 5-22 International Standards, ash fusibility, 3-6, B-5
~ y d r o ~ einncoal, 2-8.2-16,~-18, Appendices A and C Interstage thermal treatment, welding, 17-11
Hydrogen in fuel, 6-8. See specific fuels in Chapter 2, Investment costs. 1-28. See Power-plant Economics. 1-29
Appendices A and C Ion-exchange. See demineralization
COMBUSTION
Subject Index Ion-Mac

Ionic flame monitoring ignitor, IFM, 12-11 pH control, 15-51, 15-55


Iron in coal ash, 3-2, 3-4, 3-9, 3-10, 3-18, 3-21, B-14 utilization, in wet scrubbing, 15-51
Ironlcalcium ratio in coal ash, 3-9, 7-4 in water treatment, 20-6
Ironlcarbon phase diagram, 17-8 Lime-limestone scrubbing, FGDS, 15-29.15-30. 15-32,15-36
Ironlcarbonlchromium. phase diagram 17-8 Lime-soda softening, 20-6
Iron copper corrosion, 20-16 Limestone. See Dolomite
Ironldolomite ratio in coal ash, 3-10 in FBC combustion, 6-9, 9-3, 9-5
Iron-water reaction, 20-14 utilization in fluidized bed, 9-5, 9-6, 9-13
Limit circuits, 13-21
Liners, fans, erosion prevention, 14-22
Liquefied petroleum gas, LPG, 2-36
Liquid fuels. See Fuels
JANAF Tables, 4-23 Liquid-penetrant testing, 18-18
Jet pumps for ash transport, 16-11, 16-12 Liquid-to-gas ratio, in scrubbers, 15-29
Joint Army, Navy, Air Force Project, JANAF, 4-23 Liquid waste fuels, 8-7, 8-10, 8-26
Journal assemblies, 11-24, 11-29, 11-33, 11-34, 23-3 Ljungstrom air preheater leakage control system, 14-32
Ljungstrom trisector air heater, 10-16, 11-16, 11-17, 14-23,
14-28, 14-29
LMTD, logarithmic mean temperature difference, 6-26
LNCFS, Low NO, Concentric Firing System, 12-8
Kangaroo tower crane, 19-11 Load control, 21-7
Karagodina, N.V.. B-10 Load duration curves. 1-19. 1-20, 1-25
KDL, Kreisinger Development Laboratory, Chapter 25 Load factor, 1-23, 24-2
Kick's law of crushing, 11-3 Load requirements in cycling, 1-26, 7-37, 7-38, 24-11
Kingsbury-type pump bearings, 14-42 Load variations in marine boilers, 10-1
Kovitskii, N.V., B-10 Loading in cycling, 1-26, 7-38, 7-48, 24-11
Kraft paper making process, 8-42 Local stress, 6-55, 17-15, 24-8, 24-9
Kreisinger Development Laboratory, 6-54,655, Chapter 25 Location of,
coal sampling nozzles, 11-11
power plants, 1-26
steam sampling nozzles, 20-46
Logarithmic mean temperature difference, 6-26
Laboratory analyses and testing, 6-54,2042. 22-20, Logic, furnace safety systems, 13-8, 13-13
25-12, 25-14 Long slags, B-15
Landfill disposal, FGD, 15-29, 15-62, 15-64 Losses, heat, 6-4, 22-24,22-27, 22-28
Landfill disposal, fluidized-bed combustion, 9-17 dry gas, 6-7, 21-2
Large high-pressure furnace-wall systems, 7-10 heat credits, 6-11
Laser laboratory, Kreisinger Development Laboratory, 25-15 hydrogen in fuel, 6-8, 21-3
Law of cooling, Newton, 6-15 integral precipitator, 6-12
Law of conservation of mass, 4-11 moisture in air, 6-7, 21-3
Laws of thermodynamics, 1-2 moisture in fuel, 6-7, 21-3
Lay-up procedures, 20-26,20-27, 20-28, 20-29 radiation and convection, 640, 6-11, 21-3
Lead and tin, phase relationship 17-7 sensible heat in ash. 6-8
Leakage, unaccounted for, 6-10
air preheater, 6-6, 6-40, 14-3, 14-24, 14-26, 14-28, unburned combustible, 6-9, 21-3, 22-7
14-30, 14-32 uncertainty analysis, 22-2
control system, Ljungstrom air preheater, 14-32 Losses, pressure. See Pressure, losses
safety-valve, 21-23 Low-efficiency power plants, 1-26
superheater, reheater, economizer 21-27 Low NO, Concentric Firing System, LNCFS, 12-8
Lean-phase fluidization, CFB combustion, 9-19 Low pressure water treatment, 20-13
Levelized costs, 1-33, 1-35 Low-pH crystallization, 15-32
LHV, lower heating value, 2-13, 4-9 Low-rank coal, A-45, A-49, A-53
Life continuation, Low-temperature corrosion, 3-29, 6-6, 14-23, 14-26,
considerations, 13-38, 24-15 14-29, 14-32
need for, 24-6, 24-7 Low heating value, LHV, gas, 2-33, 4-9
Life of a unit, 1-28, 1-30, 6-57, 24-15 Lubrication, in maintenance, 21-8, 23-2
Ligament efficiency, 6-47 Lurgi, circulating fluidized-bed combustion, 9-2
Light emissions, 13-5
Light-off. See Start-up
Lignite, 2-3, 2 4 , 2-5, 114, A-10, A-20, A-23, A-47, A-54
grindability, 11-3, 114
Lime, See also Limestone Maceration of bagasse, 2-26
coal ash, effect on, 3-9, 3-27 .. McClintock, EA.. 22-2
in FGD systems, 15-29, 15-30, 15-32, 15-36 Machining of,
COMBUSTION
Subiect Index Mac-Mol

drums, 18-2, 18-3, 18-4, 18-5, 18-6 Measuring availability, 24-2


headers, 18-6 Mechanical carryover, 5-25, 2041, 20-43
McIlroy, J.B., B-13, B-14, B-15 Mechanical draft fans. See Fans, Chapter 14
Magnesia in coal, 3-9 Mechanical loading of furnace walls, 6-50, 7 4 8
Magnetic flux testing, 23-16 Mechanical removal of ash, 16-5, 16-25
Magnetic-particle testing, 17-3, 18-14, 18-18 Mechanical stress in Pressure vessels. 6-46
Magnetite, 20-14 Mechanical systems, ~ r e i s i n ~ ~e re v e l a ~ m e Laboratory,
nt
Maintenance and repair, Chapter 23. See also Annual 25-8
outage; Emergency shutdown; Forced outage; Melting temperature of coal ash (ash fusibility temperature,
In-service maintenance ash fusion temperature), 2-13, 3-5, 3-7, 3-10, 7-4,
ash handling systems, 15-25, Chapter 16 7-8, B-5
coal transport piping, 23-18 Membrane stress, 6-55
control systems, 13-34, 23-17 Metal temperature in superheater and reheater tubes,
documentation, 23-10 643,645
equipment manuals, 23-1 Metal temperatures, tolerance, 6-44
fans. 23-16 Metal-tem~eraturedetermination, 24-12
firing equipment, 23-7 ~etallurg; and materials, Chapter 17, Chapter 25
of flyash intakes, 15-25
in planning and scheduling, 23-22
-
Meteoroloeical information.
for combustion calculations, 4-2, 4-3, 6-7
pressure parts, 23-11 for fan desiw, 6-31, 6-37, 14-2
pulverizers, 23-3, 23-7, 23-21 for stack performance, 6-37
Manometers, 22-24. See also Draft gages; Pressure for structural design, 6-58
differentials Methods of
Manufacture of boiler components. Chapter 18 burning solid fuels, 4-28
shop assembly, 8-29, 18-9, 18-12 of particulate emission control, 15-4, 15-5, 15-6, 15-8
Marine boilers, Chapter 10 testing coal, A 4 6
fuels in, 10-9, 10-19, 10-20 Mill drying of coal, 114, 11-17
space limitations in, 10-2 Mill exhauster fan, 11-35, 14-3
waste-heat boiler system modules, 10-12 Mill-scale cleaning, 21-16
waste-heat designs, 10-10 Mill size and boiler capacity, 7-3, 7-4, 7-39 (pulverizers);
Marine and stationary boilers, comparison, 10-22 8 4 6 (pulp mill)
Marshak, Y.L.,B-16 Mills. See Bowl mills; Pulverizers %

Martensite, 17-9 Million-Btu method, 4-5, C-1


Martynova, M.I., B-10 Mineral matter in coal, 3-3, 3-7, 3-13, 3-18, Appendix B
Mass-burning of unprepared refuse. 8-16, 8-17, 8-18 Minimum fluidization velocity, 9-2
Mass, conservation of, 4-11 Minimum load in cycling, 7-50
Mass-energy, 4-11 Mining, of coal, 2-6, 3-26
Mass flow, 6-28, 6-30, 6-45, 14-20 Mist eliminator, FGDS, 15-54
Mass transfer. SOz absorption, 15-39 Mitsubishi, Heavy Industries, Selective Catalytic Reduction
Material selection, System, NOx. 15-65
ash-handling equipment, 16-8, 16-11, 16-12 Mixed bed water treatment, 20-11,20-12
ASME Boiler and Pressure Vessel Code, 6-42, 6-45, 17-2 Modeling theory, emission control systems, 15-69
in boiler construction, 17-2, 17-4, 17-5 Modulus of elasticity, 17-13
fabric filters, 15-23 Moisture. See also Water
reheaters, 6-42 in air, 4-2, 4-3, 4-7, 6-9, C-4
spray tower components. 15-52 air heaters. 14-33
superheaters. 6-42 in coal, 2-8, 2-12, 11-4, 11-17
Materials technology, Kreisinger Development Laboratory, flyash hoppers, 15-26, 16-20, 16-24
25-15 removal in drums, 5-25
Mathematical model of furnaces, 6-51 Moisture content. See olso Water
Maximum continuous rating, MCR, 7-8, 14-6 coal, 2-8, 2-12, 8-6, 11-4, 11-17, A-2, C-4. See also
Maximum shear theory, 6-55 specific coals
Maximum thermal circulation effect, 10-3 combustion calculations, Appendix C
Maximum tolerable oxidation, MTO, 15-47 eauilibrium moisture content. 2-9. 114. A-46
Mean bed particle size, BFB combustion, 9-10 fuh samples, 2-7, 22-5, endice ices A and C
Measurement of gaseous and liquid fuels, 6-7
nitrogen-oxide concentration, 22-17 refuse as fuel, 2-27, 7-9, 8-16, 8-21
particulate loading, 22-14 pulverized coal, 11-4, 11-6, 11-17
sulfur dioxide and sulfuric-acid concentration. 22-15 saturated steam, 5-25, 20-41
Measurement errors (efficiency calculations). 22-26 Moisture loss and boiler efficiency, 21-3
Measurement techniques, Mo~,4 4 , 4-9, 4-11
draft, 6-31, 22-6, 22-24 Mole. See Mol; Mole method; Molal volume
gas-flow, 22-13, 22-18, 22-19 Mole method of combustion analysis, 4-5, 4-17, 4-20
particulate matter, 1 5 4 , 22-13, 22-14, 22-15, 22-16 Molecular weight, 4-2, 4-3
COmmnON
S u b k t Index Md-Opt

Mol-volume relationship, 4 4 Non-luminous radiation, 6-26


Mold volume, 4-4 Non-regenerable FGD process, 15-29
Mollier diagram (Mollier chart), 5-2, D-1 Normal power in marine boilers, 10-1
Monitoring plant operation, 22-1 NO,, nitrogen oxides, 4-30.4-31, 7-4, 8-6, 12-6, 15-3
Moody and Langan, 3-16 catalyst selection. 15-66
MSW (municipal solid waste) grate. 6-19, 12-22 control, 4-32, 4-34, 15-64
Multi-coated metallizing, 8-61 in design considerations, 4-34
Multi-drum marine boilers, 10-6 firing systems that minimize formation, 12-6, 12-7
Multi-fuel capability, 8-1, 8-2, 8-4, 8-7 formation, 4-30, 12-6, 15-3,
Multiple-pass steam generator for mass-burning of fuel NO,, 4-32,4-33
municipal refuse, 8-18 h - N O , concentric firing system. 12-8, 12-9
Municipal solid waste. See Fuels, refuse, municipal and post-combustion reduction processes. 15-65, 15-68
industrial removal, 15-64, 15-66, 15-68
testing, 4-34
thermal, 4-30
Nozzle calibration, 22-10
Nozzles,
NACA Report 1235, Standard Atmosphere, air, 5-12, 12-2, 1 2 4 , 12-5, 12-7, 12-9, 12-19
lkbles and Data. 4-2, 6-37 in drum plates, 18-6
National Board of Boiler and Pressure Vessel Inspectors, fuel, 5-12, 6-13, 7-11, 12-2, 12-3, 12-4, 12-5, 12-22
17-2 in wet scrubbers, 15-33, 15-38
National Board Inspection Code, NBIC, 23-11 NPHR, net plant heat rate, 1-9.1-16, 1-26, 1-27, 1-29, 7-37
National Fire Protection Association, 11-31, 11-34, 11-35, NSPS. New Source Performance Standards, 8-6
12-9 Nucleate boiling, 5-18, 5-19, 6-52, 20-23, 20-23
NFPA 85E, 12-10 Number of operating cycles, 7-48
NFPA 85F, 11-31, 11-35 Nusselt number, 6-23, 9-7
NFPA 85G, 13-34
Natural circulation. See Thermal circulation
Natural gas, 2-35.2-36, 2-37, C-21, C-23 0
combustion of, 4-8, 6-8, C-21, C-23
furnace, 6-16, 6-18 Objectives of operation, 21-1
heating value, 2-36, 2-37, C-25 Offset-bender, 18-10, 18-11
specific heat of products of combustion, 6-29 Ohm's law, 6-22, 15-12
Natural oxidation, 1 5 4 9 Oleschuck, O.N., B-1
Naval vessels. See Marine boilers, Chapter 10 Oil as fuel, 2-27.2-28, 2-29, 2-31, C-19, C-22
Negative pressure excursion, 13-29 Oil burner, in marine boilers. 10-19
Net draft in stacks, 6-33, 6-37, 6-39 Oil-furnace design, 6-16, 7-9
Net heat inputlplan area, NHIIIPA, 6-16, 6-17, 7-4 Oil and gas furnace design, 6-16, 7-9
Net plant heat rate, NPHR, 1-9, 1-16, 1-26, 1-29, 7-37 Oil gas, 2-37, 2-39, C-29
Net radiation, 6-19 Oil guns, 10-8
Newcomen's engine, 5-5 Once-through steam generators, 5-14, 5-17, 7-25 to 7-37
Newton, law of cooling, 6-15 On-line maintenance, 23-2
Nicholls, P., B-14 Opacity of flyash, 15-73
Nickel and copper phase diagram, 17-7, 17-8 Open-hearth furnace gas, 8-26
Ni-Hard, 11-34, 23-3 Operation,
Nitrogen, air heaters, 21-3
in atmospheric air, 4-2, 4-30 C-E Controlled Circulation Systems, 7-23, 21-5.
in coal, 2-12, 2-16, 2-18, 4-32, Appendix A, C-10 See C-E Controlled Circulation Boiler
in natural gas, 2-35 C-E pulverizers, 11-35, 21-5, 21-8
Nitrogen blanketing in outages, 20-26 drum-type units, 20-30,20-31, 20-35,20-37,20-38, 21-5
Nitrogen oxides. See NO, of fluidized-bed boilers, 21-26
Noise, of power plants, Chapter 21
characteristics (signature), 14-23, 14-45, 14-46 problems in, 21-27
exposure, 14-45 of steam generators, Chapter 21
measurement of, 1 4 4 6 supercritical units, 20-31, 20-35, 20-39, 21-6, 21-7
physical level scales of, 14-45 sootblowers, 14-38, 21-2, 21-3
reduction, 14-23, 1 4 4 5 , 1 4 4 8 Operation and maintenance costs, 1-25, 1-30
sound power, 14-23 Operational control systems, Chapter 13
sound pressure, 14-45, 14-47, 24-49 Operational testing, 22-3
sources, 1 4 4 8 Operator training programs, 21-4, 21-31, 23-22
Nonidestructive testing, NDT, 18-14. See also Liquid penetrant Opposed firing, 12-3
testing; Magnetic particle testing; Radiographic testing; OPSIZE system, 13-35,2545
Ultrasonic testing Optical properties of flyash, 15-72
Non-heat absorbing equipment, 6-2 Optimization. See Prefabrication
Subject Index Orb-Pro

Orbital welding, 18-12 Perkins, Henry, C., 4-8


Orifice, Controlled Circulation boilers, 7-17,7-18,7-23.7-25 Petroleum, 2-27. See also Fuel oil
Orifice-flow measurements, 2 2 4 Petroleum coke, 2-21
Orifice pressure drop, 7-19,7-25 Petroleum cracking, 8-27. See Catalysts
Orifice probe, 22-10 PFBC, pressurized fluidized-bed combustion, 9-30
Orsat apparatus, 22-6.22-7 PFBC turbocharged cycle, 1-17,1-18, 9-30
Orsat analysis, 4-20 PFBC combined cycle, 9-30
Orthotropic plate, 6-51,6-51, 6-53 pH control, 15-31,15-57,20-13,20-16,20-18, 21-12
Outages, pH and corrosion, 20-14,20-15, 20-18,21-12
corrosion prevention. 20-26 Phase diagrams, 17-6
maintenance, 23-4,23-6, 23-8,23-11 Phase fields, in alloys, 17-8
reserves, 1-24 Phase relationships, 17-8
start-up, 7-39 Phase transformation (water to steam), 5-24
Overbed feed, BFB combustion, 9-9, 9-11,9-11,9-15 Phosphates, in water treatment, 20-8,20-13,2040
Overfeed stokers, 12-13. 12-14 Phosphate-hydroxide method, 2040
Overfire air, in mass-burning of municipal refuse, 8-19 Photoelectric emission, 13-6
Overfire air ports, OFA, 4-33,12-7,12-7 Pinch point, 8-32
Overheating failures, 20-23 Piezoelectric element, 18-17
Overshot feeder, 11-15 Pipe, definition, 17-3
Oxidation in FGDS process. 15-48 Piping elbows, deflector blocks, 23-19,23-20
Oxidizer. black liquor, 8-47 Pitting, 20-18,20-19, 20-20
Oxygen, Pitting corrosion, 20-15,20-18
carbon dioxide relationship, 22-7 Pitot tubes, 22-10,22-19,22-20,22-21
in coal. 2-12,2-16, 11-9 Pitot-static tubes, 22-18. See pitot tubes
control (in feedwater), 21-11 Plan area, net heat input, NHIIPA, 6-16,6-17,7-4
damage, 20-3, 20-15,20-18,21-12 Plant availability. Chapter 24
in feedwater, 20-3,20-38,21-11 Plastic deformation, ductility, 17-11,17-13, 17-14, 17-18
gas-phase reaction, 4-23 Plastic elongation, yield strength, 17-13
measurement, 22-7 Pneumatic controls, 13-23
removal, 20-15, 20-30,20-32 Pneumatic ash removal, 16-5,16-20,16-24
solubility in water, 20-30 Ponds, ash disposal, 16-5,16-15
Oxygen-free water, 5-10 Postweld heat treating, in field, 19-18
Potassium in coal ash, 3-11
Pound mol. See Mol, Mole
Power generation, block system, 1-25
Power plant,
Panel-processing welding machine, PPM, 18-9 additions, 1-26
Paper making, 8-40 auxiliaries, Chapter 14
Parr formulas, 2-8 diagnostic systems, 13-24
Parr, S.W., 2-4 design, Chapter 1,Chapter 6
Partial sliding-pressure supercritical design, 7-32 economics. 1-29.See also Operation and Maintenance
Particle convection Nusselt number vs. Archimedes costs
number, fluidized-bed combustion, 9-7 noise. 14-45. See Noise
Particle size, flyash, 15-2,15-4,15-15 operations, Chapter 21
Particulate emission control, 154 performance, plant. 24-1
Particulate matter, 15-1,15-4. See also Dust; Flyash testing, Chapter 22
Particulate resistivity, 15-6,15-12,15-13 Prandtl number, 6-23,9-7
Particulate sampling trains, 22-15,22-16 Pre-boiler cleaning, 7-50,20-1, 20-4,21-13
Parts per billion, ppb, 20-4 Precipitators. Chapter 15 '
Parts per million, ppm, 20-4 air leakage, 6-12
Part-load operation, BFB combustor, 9-14 ash hoppers, 15-10,15-15,16-24
Part-load operation, CFB boilers, 9-24 . design factors. 15-10
Peak loads, 1-23,1-24, 7-37 electrostatic precipitators. See electrostatic precipitator
Peak stress, 6-55, 17-15,17-16 heat loss, 6-12
Pearlite and ferrite, two-phase structure, 17-7,17-7 heating of outlet hoppers, 15-25
Peat, 2-1,2-6,A-5 hopper plugging. 15-24
Peg fins. 18-11 precipitation rate, 15-11,15-14
Percentage COz, combustion calculations, Appendix C Predictive maintenance, 22-23
Perforated centrifugal drum internals. 8-9 Prefabrication, 18-11.See also Shop assembly
Performance and design specifications, 1-23,6-1,7-9, Prefiring purge, 13-11,21-5
8-6.See Design Preheater, air. See Air heaters
Performance guarantees. 22-3 Preheating of combustion air, 5-6. 5-11,6-5. 11-17. 11-18,
Performance requirements 14-23,14-30,M-31
in industrial boilers, 8-1 Preliminary reports (power-plant studies). 1-19
COMBUSnON
Subject Index Pre-Ral

Preparation system for spreader-stoker firing of refuse- Pulp-mill waste streams, incineration of, 8-30
derived fuel, 8-22 Pulse-jet fabric filters, 15-20
Present worth, 1-33, 1-35 Pulsing-flow waves, 22-17
Pressure, Pulse-jet collector, 15-20, 15-20
differentials, 22-11 Pulverized coal, 3-15
drop, BFB combustors, 9-13 drying, 11-5, 11-15
drop, CFB combustors, 9-23 firing, 4-29, 8-3, 8 4 , 8-5, Chapter 11 (Pulverizer and
drops and available static head, thermal circulation vs. Pulverized-Coal Systems), 12-4, 16-1, 16-4, 16-5
Controlled Circulation, 7-25 furnace design, 6-15
gages, 22-11 preparation, 11-12, 11-15 to 11-34
heat rate, supercritical pressure, 1-9, 7-37 sampling, 11-11
high-pressure test loop (KDL), 7-11, 25-10, 25-11 storage, 11-15, 11-15, 11-18
versus load for full sliding pressure supercritical unit, 7-32 unit with horizontal surface in furnace, 7-7
losses, 6-31, 6-33, 6-35, 6-37, 22-19 Pulverizers, Chapter 11. See olso Bowl mills; Mills
measurements, 6-33 air temperature, 7-39, 8-6, 8-15, 11-5, 11-17, 11-25,
profile, CFB boiler, 9-20 17-5, 19-15
sliding-pressure operation, 7-31, 7-32, 7-32, 7-44, alignment, 11-31
7-46, 7-47 coal size, 8-3
and stress, 6-49, 7-48 design, 6-12, 8-5, 11-24, 11-31
and temperature, 8-54, 17-2 explosions, 11-35, 21-9
in waterwalls vs. load, 7-26, 7-31, 7-32 fires, 11-36, 21-9
Pressure drop, 6-32, 6-45,-7-19, 13-32 foundation design, 11-31
calculations, 6-45 inerting and fire extinguishing. 11-35
versus draft loss, 6-32 maintenance of, 23-3, 23-18
Pressure specifications, operation, 11-32, 21-9
combustion reactions, 12-1 pyritic rejection from, 8-6, 15-27
fans, 6-38, 13-32, 14-5 reject system, 16-18, 16-19
marine boilers, 10-4 safety and controls, 11-35
thermal circulation svstems, 7-11 selection for variable load operation, 7-39
Pressurized exhauster, Bystem, 11-19 shell design requirements, 11-31
Pressurized fluidized-bed combustion IPFBCI., 1-18.. 9-30 turndown capacity, 8-7
Preventive maintenance, Chapter 23, 23-23 types, 11-21, 11-26
Primary air, Pump-assisted thermal circulation, 5-15. See also C-E
in preheaters, 14-30 Controlled Circulation
in pulverizers, 11-16, 14-2, 14-6 Pumps,
Primary stress, 6-54 circulation, 7-17, 14-41, 14-43
Primary temperature, 5-3 feedwater, 14-41
Priming (steam), 2 0 4 2 maintenance of, 23-15
Principles of operation, Chapter 21 recirculation, 7-12, 14-41, 14-43
Priorities in maintenance, 23-3 zero-leakage, 14-42
Problems in operation, 21-27 Pump differential pressure, 7-23
Process considerations, bubbling fluidized-bed boiler, Purge, of system, 21-54
9-10, 9-13 Pyrites, 3-4, 11-12, 15-27, 16-18
Process controls, 13-18 Pyritic sulfur, 15-26, 15-27
Process or sewage sludge, burning of, 8-28 rejection from pulverizers, 8-6, 15-27
Process parameters, CFB combustion, 9-22, 9-23
Process steam cycles. See Cogenerative steam cycles
Process zones in a chemical recovery furnace, 8-51
Processes in kraft pulping and chemical recovery, 8 4 4
Producer gas, 2-38 Q-Pipe heat-pipe air heater, 14-23
Products of combustion, 4-2, 4-3, 4-7, Appendix C
Programmable controllers, 13-14
Prompt NO,4-31
Properties of,
air, 4-2, 4-3 Radial acceleration, water separation, 5-27
coal, Chapter 2, 3-18, Appendices A and C Radial airfoil fans, 14-2. See Centrifugal fans; Fans
coal ash, Chapter 3, 16-4, Appendix B Radial heat flow, 6-22
metals, Chapter 17 Radiant beam length, 6-26
steam, 5-1, 5-3. See olso Steam tables, Appendix D Radiant heat absorption, 6-30, 6-30
Proportionality constant, 4-18 Radiation, heat transfer, 546-10.6-11, 6-15.6-22, 21-3, B-3
Proximate analysis of coal, 2-7, 2-9 Radiographic testing, 18-6, 18-14, 18-17
Public opinion and power plant design, 1-27, 1-36 Radiographical examination of welds in field, 19-18
Pulp and paper industry chemical recovery boilers, 8-42 Rai, B., B-6
Pulp-mill capacity, relation to boiler size, 8-46 Ralston, O.C., 2-4
COMBUSTION
Subject Index Ran.Sch

Rank, of coal. See Coal classification Resistance bulb. See Temperature measurements -
Rankine cycle, 14. 1-4, 1-5, 1-6, 1-13 Resistivity of particulate matter, 15-6, 15-12, 15-13
Rankine, W.J.M., 1-4 Retractable sootblowers, 7-4, 10-6, 14-33
Rapping system, precipitators, 15-8, 15-13, 15-15 Return-flow burners, 10-19
Raw refuse, 2-27, 8-14 Revenue requirements, method, 1-34 -
Raw-water treatment, 2 0 4 Reverse air fabric filter, 15-18, 15-19
Raymond Impact Mill, 11-26, 11-27 Reversing hoods, water separation. 5-27, 5-28
Raymond Roller Mill, 11-25 Reynolds number, 6-23, 6-25, 15-70, 22-21
RC (stoker) grate for burning RDF, 8-21, 8-22 Reynolds, William C., 4-8
Reactivity of char, 2-15 Rifled tubing, 7-10, 7-12, 7-35
Recirculation systems, furnace walls, 5-14, 5-15, 5-18, 7-10, Rigid frame precipitator, 15-8, 15-15
7-12, 7-16, 7-18, 7-28, 7-31 Ring roll mill, 11-23
Recycle ratio, BFB combustion, 9-11 Ringelmann number, 15-73, 15-73
Recycle system, Ring-type logic-processor architecture, 13-16
BFB boilers, 9-16 Rittinger's law of crushing, 11-3
CFB boilers, 9-27 RMS (root-mean-square]
Refinery gas. 2-37.2-39, 8-27 sound pressure, 14-45
Refractory coating, furnace walls, 8-20 value of wave form, 22-23
Refractory cooling (ash hoppers), 16-8 Roberts, A.G., B-11
Refuse as fuel, 2-27, 7-9, 8-14, 8-16, 8-17 Rockwell test. See Hardness
Refuse burning in utility boiIers, 7-9 Roll pressure adjustment, 11-28, 11-34
Refuse-derived-fuel system (for burning prepared refuse), Roga-index test, A 4 7
8-4, 8-21 Root causes (of problems), 24-5
Regeneration vs. cogeneration: the thermodynamics, 1-12 Root-mean-square sound pressure, See RMS
Regenerative air heaters, 10-16, 14-23, 14-28, 14-29 Rosin equation, 6-16
marine, 10-16, 10-17, 10-18 Rotor, in regenerative air heater, 14-28, 14-29
Regenerative Rankine cycle, 1-4, 1-5, 1-6 Rupture, 20-24. See also Stress
Regenerator waste gas, 2 4 0 , 8-27, 8-28 Russian method, coal classification, 3-6
Reheat (stress-relief) cracking, 17-11 Ryzhakov, A.V., B-16
Reheat cycles, 1-6, 1-7, 1-8, 1-30. 1-11, 1-9, 7-37
Reheat regenerative cycle,
600-MW subcritical-pressure power plant, 1-7, 1-8
800-MW supercritical-pressure power plant, 1-10, 1-11
Reheat system, desuperheating, 5-12 Safety, 1-36, 11-35, 13-1, 18-2, 21-1
Reheat steam generators, 1-6, 5-9, 6-3, 6-30, Chapter 7 considerations in chemical recovery boiler design, 8-63
Reheaters, 5-9. 6 4 2 , 21-26. See d s o Superheater control systems, 13-1, 13-11
CFB boilers. 9-22 operations, 21-1
design considerations, 1-6, 6-30, 6-42 regulations. See specific agencies and codes
flue-gas, 15-55 tags, 2 1 4
heat transfer rates, 6-25, 6-28, 6-30 valves, 21-22, 21-23, 21-24, 21-25
manufacture of, 18-12 walkdowns, 21-26, 21-29
pressure drop in, 6-45 Sage, W.L., B-13, B-15
temperature control, 5-11, 6 4 1 , 6-42, 7-40, 7-41, 21-8 Salts in boiler water, 5-31
Reid, W.T., B-11, B-14, B-16 Sample results (fineness test), 11-12
Reinforced openings, 6 4 9 Sampling,
Relationships between stokar, fluidized-bed, and pulverized coal. 2-7. 11-4, 11-11, 22-4
firing of solid fuels, 9 4 flyash, 15-6
Relative flue-gas volumes and heat absorption patterns stack emissions, 22-13, 22-15, 22-16, 22-17
(CFB), 9-21 steam, 20-43
Reliability and maintainability of chemical recovery techniques, 2-7, 11-11, 2045, 22-13
boilers, 8-63 Saturated steam, 5-2, 5-25, 7 4 2
Reliability of electric utilities, 1-25, 1-36, 24-1, 24-6, Saturated water (liquid), 5-2. See Steam tables, Appendix D
Chapter 24 Saturation temperature, 5-2, 8-54, Appendix D
Remaining-life analysis. ASME Code aspects, 24-8; Sauter mean droplet diameter, 15-40
Chapter 24 passim Savery, Thomas, 5-5
Removable planetary-gear drive (HP pulverizer), 11-31 Savings in manufacturing and erection, shop-assembled
Replacement power costs, 1-29 units, 8-41
Repair and maintenance, Chapter 23 Sawdust as fuel, 2-25
Repairable and replaceable liners (fans), 14-22 Saybolt Furol Viscosity, 2-30, 2-31
Reports. Saybolt Universal viscosity, 2-30, 2-31, 2-32
maintenance, 23-10 Scale,
power-plant studies, 1-19, 1-28 formation, 6-21, 1544, 2042, 20-39, 20-40
Reserves, 1-24, 24-4 removal. 7-22. 20-39. 21-16. 21-17
Residual combustion, 4-12 Schaefer, R.L., B-7
COMBUSTION
Subject Index Sch-Spe

Schnabel rail car, 8-4L8-41 removal tempe~ature,B-13


Scotch marine boiler, 10-4, 10-4 viscosity, B-11, 8-15
Schikorr hypothesis, pH control, 20-14 Slagging, 3-4, 3-18, 6-15, 21-10, 21-11
SCR post-combustion NOx-reduction process, 15-65 Slag-tap furnaces, 7-6
Screen dryer, 5-28, 5-29 Slagging temperature, B-17
Screen openings, 11-9, 11-10 Sliding-pressure operation, 7-23, 7-25, 13-19
Screen tubes, 10-6, 10-13 Sliding-pressure operation of C-E Combined Circulation
Screens, water separation. 5-27 steam generators, 7-32
Scrubbers, 15-6, 15-7, 15-28 to 15-64 Sliding-pressure programs for subcritical-pressure drum
Seal pot, CFB boiler. 9-27 boilers, 7-46
Seaman, H.J., 11-2 Slip-ring motor drives, 14-17
Seasonal variations in heating loads. 1-20 Sludge,
Seasoning of furnace, 21-2 dewatering, 15-64, 15-65
Secondary stress, 6-54 disposal, 15-64
Sectional-header boilers, 10-5, 10-5 as fuel, 2-32
Sector plate, deflectable, 14-32 uses for, 15-64
Seebeck and Peltier, 22-2 Sluice gates, in hoppers, 16-10
Selection of materials, 6-42. Chapter 17 Smelt-water explosions, 8-62
Selection of solvents. 21-17 Sodium aluminate, in water treatment, 20-5
Selective catalytic reduction, SCR, 15-65 Sodium and fouling rate, 3-11, 3-15, 3-24
Selective deposition. 3-15, 3-24 Sodium sulfite, feedwater control, 20-15, 20-16
Selective non-catalytic reduction. SNCR, 15-68 Sodiumlvanadium ratio, corrosion, 3-28
Semianthracite coal, 2-3, 2-4, 2-5 Softening temperature of coal ash, 3-5, B-6, B-7.
Semi-direct pulverizing system, 11-16, 11-17 See also Ash softening temperature; Ash-fusibility
Semi-ellipsoidal head, 6-48 temperature; Fusion temperature of coal ash
Sensible heat loss in ash. 6-8 Solid carbon loss, prediction of, 6-10
Sensors (detectors), 13-5, 13-7 Solid fuel firing, relationships between stoker, fluidized-bed,
Service exposure considerations (materials), 17-22 and pulverized firing, 9-4
Setting height of boiler. 16-16 Solid fuels, 2-19, 4-6, 8-2, 8-26, 22-5. See also Coal; Coke;
Settling ponds, 16-7, 16-15 Refuse; Sludge; Wood
Settling tanks, 16-14 Solid particle erosion, SPE, in steam turbines, 17-25
Sewage sludge as fuel. 8-28 Solids contents. See also Water treatment
Shaft horsepower, Shp, 10-1 in boiler water. 7-16, 20-22
Shake-deflate fabric filters. 15-20 in steam, 5-25. 7-15
Shaker-type fabric filters, 15-17 Solids, recycle in spray-dry scrubbing, 15-59, 15-60
Shell design, 6-46 Solvent-contact, scale removal, 7-22
Shielded metal arc welding, SMAW, 19-18 Solvents, selection of, 21-17
Shipment of shop-assembled boilers. 8-41 Solubility of oxygen in water, 20-30
Shop assembly of boilers. 8-36, 18-12 (optimization) Sonntag, Richard E., 4-8
Short slags. B-15 Sootblower erection, 19-11
Short-term probes, corrosion indicators, 3-26 Sootblower systems, 10-6, 14-33, 14-37, 14-37, 14-39,
SHO, superheater outlet, headers, 7 4 2 1440, 21-2
Shredded rubber, bu:ning of, 8-29 Sorbent
Shrink allowance in welds, 23-13 feed, BFB combustion, 9-15
Shutdown, 13-10, 21-6, 21-27 feed system, CFB boilers, 9-25
Siddall, R.G., 6-16 preparation, BFB combustion, 9-15
Sigma phase, 17-6 preparation, CFB boilers, 9-24
Silica, Sound paths, 14-48
in boiler water, 5-30. 5-30 Sound pressure level in power plants, 14-45, 1449
in coal ash, 3-4, 3-8, 3-9, 3-11 Space heating and power plants, 1-19
Silica/alumina ratio, 3-8. 3-9 Space limitations in marine boilers, 10-2
Silica Percentage, 3-11 Spare parts, determining need for, 23-2
Silo fluidization of flyash, 16-26 SPE, solid particle erosion (in steam turbines). 17-25
Single-nozzle sootblowers, 14-37 Specific collection area, SCA, 15-10
Single-V bottom hopper. 16-7 Specific gravity, 2-30, 2-34, 22-5
Single-extraction regenerative cycle, 1-5 Specific heat, 443, 6-12, 6-25, 6-28, 6-29, B-1, B-3
Sintering, 8-58 solid fuels, products of combustion. 6-29
Sizing of fuel and sorbent CFB combustors, 9-22,943.9-24 liquid and gaseous fuels, products of combustion. 6-29
Slack, 2-5 air, at varying moisture contents, 6-29
Slag, 34.3-10,lO-15.16-1, Appendix B. See also Bottom ash Specifications, 1-22. See o/so specific agencies and codes
accumulation, 6-19, 6-21, 6-22, 7-24, 8-3, 10-6, 10-13, for fans. 6-38
16-1 and material selections, 17-1
and furnace seasoning, 6-21, 20-2 tensile strength. 17-11
on furnace walls, 3-22. 6-21. 6-22. 16-1 Spectrum, total electromagnetic radiation. 13-6_
COMBUSTION
Subiect Index Spa-Sto

Speed variations in fans, 14-12 - air heaters, 6-5, 6-6, 10-17, 14-36
Spherical shell, thickness. 6-46 cycles [power plant), 1-3 to 1-18
Spheroidization, 20-24, 20-25 dryers, 5-2, 5-28, 5-29
Spinning reserve; 1-24 generation, Chapter 5
Spray-dryerlabsorber, SDIA, 15-33. 15-55; See Spray-dry production and chemical recovery (pulp and paper
scrubbing industry), 8-42
Spray carryover, 2041, 20-43 properties, 5-1, Appendix D
Spray-dry scrubbing, 15-32, 15-55 purity, 5-25
additive type and quality, 15-57 quality, 5-2, 5-25
approach to saturation, 15-58 sampling methods, 20-45, 22-13, 22-15, 22-26, 22-17
atomization quality, 15-60 tables, 5-2, Appendix D
chlorides, effect of, 15-60 temperature control. See Superheaters, control of steam
. drop-size reactor, 15-55 temperature; Reheaters, temperature control
inlet SO2 concentration. effect of, 15-61 temperatures. 5-3, 7-39. See Superheater; Reheaters
mass and heat transfer, 15-56 washers, 5-30
process effect in SDIA, 15-57 and water separation, 5-24, 5-26, 7-15, 7-16, 7-18, 7-36,
recycle of solids, 15-59 8-8
stoichiometric ratio. 15-58 Steam-atomizing oil guns, 10-8. 10-22
spray-down temperature, 15-59 + Steam-driven pumps, 1-22
Spray-tower, 15-38, 15-52 Steam drum, 5-25 to 5-30,746, 7-18, 8-8, 18-2,18-3, 23-7
Spreader stokers, 12-15, 12-17, 12-18, 12-19 internals, 5-25, 5-29, 8-8, 8-9
cellulose firing. 12-19 Steam generation, history of, 5-5
design considerations, 12-17 Steam generators. See Boiler; C-E Controlled Circulation
refuse burning, 8-15 boilers; C-E Combined Circulation boilers; Chemical
marine boilers, 10-20 recovery boilers; Fluidized-bed boilers
SSC, submerged scraper conveyor, 16-15 auxiliaries, 1-21, Chapter 14
Stack, for cogeneration plants, 1-14
calculations, 6 3 3 , 6-37, 6-39 efficiency, 6-3, 6-4, 6-13, 21-2, 22-24
effective height, 15-71, 15-71 fluidized-bed, Chapter 9
emissions, 22-4, 22-13 for gas-turbine heat recovery, 8-30
heat loss, 22-4 marine, Chapter 10
performance curves, 6-37 pressure parts. 5-5. 5-8. 7-6. 18-2. 23-7
sampling, 22-13 reheat, 1-6. 5-6. 5-9. Chapter 7 passim, 9-18
Stack effect, 6-33 supercritical-pressure. 5-16, 7-25 to 7-37
Staggered-tube arrangement, 6-24 testing, Chapter 22
Staging, NOx control, 4-33 waste-heat, 10-15, 8-30, 8-33
Stall. fans. 14-15. 14-20 Steam lines, 21-21
Standard reference state, 4-8 Steam-turbine drive, 1-14
Start-up, Chapter 21, Steel. Chapter 17 passim
after outages. 7-39, 741 alloys, 5-3, 6-43, 6-45, 15-52, 17-3, 17-4, 17-9, 17-10,
air temperature, 7-39 17-25
BFB combustor, 944, 21-26 boilers for steel-making service. 8-26
CFB boilers, 9-24, 21-26 castings for boiler pressure parts, 1 7 4
in Combined Circulation boilers, 7-36, 7-44, 7-46, 20-35, corrosion, 3-23, 3-24, 8-17, 8-20, 8-58, 17-23, 17-30,
20-36, 20-38 20-15. See also Hydrogen damage; Oxygen damage
in Controlled Circulation boilers, 7-17, 7-39, 741, 7 4 2 , slags in, B-2
214 properties, 17-3
and corrosion. 20-30, 20-3t 20-32 testing, 17-3
operation. 5-17, 20-30 Stefan-Boltzmann constant, 6-15, 6-19
procedures, 21-4 Step ignition, 12-10
rates, 7-40 Stoichometry, additive [FGDS), 15-50
safety controls. 13-11. 21-1 Stochiometry of combustion, 4-17
supercritical boilers. 20-34, 21-6, 21-7 Stoke's law. 15-11
systems for supercritical steam generators. 7-36 Stoker applications,
temperature matching system, 7-44 in bagasse (and biomass), 8-4, 12-19, 12-20
turbine by-pass system. 7 4 2 for coal, 8-4, 8-6, 12-13, 12-14, 12-15, 12-19
Statistics on availability of generating units, 24-4 fuel specification, 8-4, 12-18
Stauscheibe pitot tube, 22-20.22-20 industrial power plants. 8-14. 8-16, Chapter 8 passim
Static holes. 6-33 marine boilers, 10-9, 10-10
Static horsepower, 14-4 refuse firing, 8-14 to 8-26, 12-21, 12-23, 12-25
Static tube. 6-33. 22-19 versus pulverized coal. 8-3
Static pressure, 6-32, 6-40, 1 1 4 , 14-6 traveling grate. 12-13, 12-14
Steady fluid flow, 5-21 Stoker firing. 4-29
Steam. Stokers. 8-3. 8-4. 12-13
COMBUSTION
Subject Index Sto-km

Storage (indirect) system, 11-15 marine boilers, 10-13


Storage of pulverized coal, 11-15, 11-18 materials selection, 5-3, 5-9, 6-43, 6-45
Strainers, in Controlled Circulation systems. 7-18 manufacture of, 18-12, 18-16
Stress, 6 4 5 to 6-59. See also Cracking; Fatigue pressure drop in, 6 4 5
allowable limits, 6-56 shop assembly, 18-12
analysis, 642, 649, 6-54. See also Non-destructive slag accumulation, 3-1, 3-4, 7-4, 10-13
testing; Testing steam temperature control, 5-11, 5-16, 6-41, 6-42,7-39
damage, 6-57. 21-9.24-10, 24-11, 24-14 surface arrangement, 7-6, 9-12, 9-16, 9-20, 9-22, 9-27,
experimental, 6 5 4 10-13
intensity, 6-55 temperature curves, 5-13, 7-31, 7-41, 7-46, 8-34, 10-14
maximum shear theory, 6-55 Superheater outlet header, SHO,7-42
rupture 17-16. 20-24 Superimposed recirculation, 5-14, 5-17
Stresses in, Supplementary-fired steam generators, 1-16,8-30.8-33,8-35
furnace walls, 6-50 Support,
local, 6-55, 24-8, 24-9 boiler structure, 6-58, 19-3
pressure vessels. 6-46, 7-48 marine boilers, 10-21
Stress-relief cracking. See Reheat cracking, 17-11 .Surge tanks, 16-14
Structural, , Surveys of Energy Resources, A-1
deformation (in regenerative air heaters), 14-31 -Suspended solids, 20-3
design, 6 4 4 ,6 4 9 ,6-58 Suspension firing, 4-29,
materials selection, 17-5 of prepared refuse, 8-25
Subbituminous coal, 2-3, 2-6, 2-10,2-17,A-42, A-51, A-53 of cellulose fuels. 12-20
Subcritical pressure, 1-7, 5-14, 5-16 to 5-24, 7-12 to 7-24, Swing-hammer coal crushers, 11-13
20-30, 20-33 Synchronous-motor (fan drive), 14-17
Subcritical steam cycles, 1-7, 1-15, 5-17, 7-37, 7-50 Swelling index, A46. See FSI
Submerged-arc automatic welding, SAA, 18-7 Systems additions, 1-25, 1-26
Submerged scraper conveyor, SSC, 16-15 Systems approach to training programs, 21-31. 21-32
Sub-scale burner facility, Kreisinger Development System reserves, 1-24, 24-4
Laboratory, 25-5
Suction-type pulverizers, 11-19, 11-30, 11-35, 16-18 +

Sulfur,
in black liquor, 8 4 6
in coal, 2-12, 15-2, 15-26 Tangential air nozzles, 5-12, 12-4. See Nozzles. air
in coal ash, 3 4 Tangential firing systems, 5-12, 7-4, 7-11, 8-28. 10-8,
in coke, 2-22 10-9, 12-4, 12-5, 12-6, 12-7, 12-14
emissions. 15-2. 15-26. See also Sulfur oxides ash deposits, 12-5
in fuel oil, 2-3, 2-28, 2-29, 2-31 for byproduct fuels, 7-6, 8-10, 8-26
removal vs. fluidized-bed temperature, 9-6 design considerations, 7-4, 7-11, 7-35
Sulfur-oxides, SO,, firing patterns, 7-35, 10-8
control, 15-28 to 15-64 fixed (non-tilting), 8-28
emissions, 15-2. 15-26 fuels (that can be burned). 8-10
formation, 13-27 ignition systkrns, 12-10, 12-11, 12-12
in-situ capture in fluidized-bed combustion, 4-30, 9 4 , low NO,, 12-6
9-13, 9-23 wirh overfire air, 12-7
removal, 15-28 to 15-64 for refinery regenerator gas, 8-27
Sulfuric-acid corrosion, 3-29, 14-36 refuse firing, 8-11, 8-25
Sulfuric-acid-mist sampling train, 22-17 safety systems, 13-9, 13-10, 13-12, 13-16
Supercharged steam generators. 1-17, 1-18 Tangential fuel nozzles, 5-12, 7-11. See Nozzles. fuel
Supercritical-pressure cycles. 1-9, 1-10, 7-37, 7-50, 20-31, Temperature.
20-34 average cold-end. See ACET
Supercritical-pressure sliding-pressure operation. 7 4 6 in combustion reactions, 12-2
Supercritical-pressure steam generators, 5-16, 7-25 to 7-37 control, 5-11, 8-24, 10-13, 21-8
Superheated steam cycles, 14, 1-6, 5-2 curves. See Superheaters, temperature curves
Superheaters, 5-9, 18-12. See also Reheaters, decay, 13-31
circulation in, 5-14, 7-10, 7-27 in design, 1-3, 6-1, 6-18, 643, Chapter 7 (passim)
cleaning, 21-19, 21-20 distribution, 6-44, 6-51, 6-53
control of steam temperature, 5-11, 5-16, 641,6-42, fluctuation, 5-18
7-39, 10-14, 13-22, 13-23, 13-25, 21-8 flyash hoppers. 15-24
design considerations, 6-42, 6-45, 7-6, 7-8, 8-10, 8-14, furnaces. See Furnace
8-20, 8-24, 8-58 gradients (delta t), 6-22, 6-31, 6-32
double, 10-6 and heat absorption, 5-8
inverted, marine U-loop, 10-7 in heat exchangers. 6-27
leaks, 21-28 measurements, 17-16, 22-8, 22-11
maintenance. 23-7 and pressure, 4-10, 5-2, 17-2
COMBUSTION
Subject Index Tern-Tub

primary air to pulverizers, 7-39 1-21, 1-27, 7-37 .-


properties, high-temperature, 17-16 Thermodynamic method of circulation, 5-23. See Thermal,
reheaters. See Reheaters, temperature control circulation
and ruptures. 20-24 Thermodynamic-standard, 4-15
of saturation, 5-2, 6-52, Appendix D Thermodynamics, laws of; 1-2
sensors, 13-5, 13-7 Thermogravimetric burn-off of DTFS chars, 2-17
superheaters, 8-14, 8-20, 8-24, 8-58. See Superheaters, Thermometers, 22-8, 22-9, 22-11
control of steam temperature Thermosyphonic circulation. See Thermal, circulation
and tube spacing, 7-9 Thickness of spherical shell, 6-46
in two-phase flow, 5-18 Three-course drum, 18-6
Temperature curves, 10-16 Three-element controls, 13-25
Temperature matching system (turbine bypass), 7-43 Tilting tangential firing, 12-4, 12-5. See Tangential firing
Temperature-pressure-volume relationship 4-3 systems
Temperature profile of unfired HRSG, 8-34 Time-dependent costs, 1-31
Temperature-time-transformation curve. TTT, 17-9 Tolerances in fans, 6-39, 14-3, 14-6
Temperature, waste heat applications, 8-30, 8-34 Topping cogeneration cycles, 1-13
Tempering, 6-39, 17-10 Torispherical head, 6-48
Tensile properties, 17-11 Total alkalies, in coal ash, 3-11
Test loop, high pressure and temperature. KDL, 7-11. Total boiler output, 6-3
25-10, 25-11 Total carbon in coal, 2-12
Testing, Total heat, 5-2, 5-3, 5-6
boiler and power plant, Chapter 22 Total pressure, 6-33
coal, A-46. A 4 8 . See also Coal classification Total products of combustion, Appendix C
of creep and stress rupture, 17-16 Total reduced sulfur, TRS, 8-52
drum plates. 18-5 Total solids, 20-3
flow-model, 15-69, 15-71, 25-8 Total solids in boiIer water, 20-31, 20-32, 20-36, 20-37,
fuels, 2-13, 2-15, 25-3, 25-13, A-2, A 4 3 to A-55 20-38.20-38. 20-41, 2 0 4 2
liquid-penetrant, 18-15 Total suspended solids, TSS, 16-3
of long-term service exposure, 17-21 Toughness versus temperature, 17-14
magnetic-particle, 17-3, 18-6, 18-15, 18-18 Training for maintenance, 23-22
of materials, 18-4, 18-18, 24-14, 25-13 Training programs, operators, 21-4, 21-31
' non-destructive, 18-14, 18-15, 25-13 Transient limits, 7-42
performance, 14-11, 1 5 4 , 22-1 Transition-temperature properties, 17-15
radiographic, 18-14, 18-15 Transition temperature range, 17-14
temperature, 17-14 Transportation of boiler components, 18-1, 18-9
ultrasonic, 17-3, 18-4, 18-15, 18-16, 18-17, 23-7 Transportation of shop-assemblies, 18-8
Test loop, heat transfer and corrosion, KDL, 25-9 Transverse clearance guide, 7-9
Theory, Traveling-grate stoker, 12-13, 12-14
of combustion, Chapter 4 Treatment, heat, 17-11, 17-12
of elasticity. 6-46 Triple-V bottom hopper, 16-7
of (flow) modeling. 15-69 Trisector air preheater. See Air preheater
Thermal, Tri-sodium phosphate. TSP, 21-13
behavior of coal ash, 3-3, 3-10, 3-18, B-3, B-11 TRS, total reduced sulfur, 8-52
circulation, 5-14, 5-15, 5-18, 7-10, 7-12 to 7-16, 7-20, TSS, total suspended solids, 16-3
7-24, 7-25, 8-37, 10-12 Tbbe (tubing),
circulation tangentially fired steam generator, 7-14 arrangement, 6-24, 7-6
conductivity, B-I assemblies, 7-8, 18-9, 19-13
cycles, choices, 1-1, 1-9, 1-21, 7-37 coatings, 3-23
draft, 6-33, 6-37 diameter, 5-8, 6-22, 8-25, 6-50
expansion, 8-38, 21-4, 23-5 geometry, 5-8, 6-25, 6-52
gradients, effect on regenerative-preheater structural heat flow, 6-21, 6-22
deformation, 14-31 failures, 20-21, 20-23, 21-15. 24-11
head, 7-14. 7-19. 7-24, 7-25 leaks, 7-23, 21-27, 21-28
loading, 6-51 measurement, ultrasonic, 23-7
NO,, 4-30 material selection, 6-42, 6 4 5 , 17-2, 17-3, 17-4, 17-19
performance. See Furnace performance panels, 7-6, 18-13
pump-assisted circulation, 5-14, 5-15, 7-13, 7-17 repair welding, 23-12, 23-13, 23-14
stress, 6-52, 7-48, 7-49, 17-10 ruptures, 20-24, 23-6
treatment, 17-11. See also heat treatment scale and exfoliation, 17-24, 17-25, 17-26, 17-27, 20-12
Thermochemical tables (Gibbs Function Calculation), spacing, 6-2, 6-24, 6-26, 6-47, 7-18, 8-8, 8-14
4-23 to 4-26 strength, 7-9, 17-11 to 17-19
Thermochemistry, combustion analysis. 4-8 temperature monitoring system, TTMS, 13-38
Thermocouples, 22-8, 22-10, 22-11, 23-5 temperatures. 6-22, 6-43. 6-45, 6-50, 6-52, 6-53
Thermodynamic cycles and efficiency, 1-2, 1-4, 1-6, 1-9, thickness, 6 4 5 , 6-50, 24-14
COMBUSTlON
Subject Index Tub-Wat .-

in water walls, 6-50, 7-10, 7-18, 18-9 Variable inlet vanes, in fans, 14-7, 14-8, 14-13, 14-14,
'lbbular air heaters, 8-12, 8-13, 10-16, 14-23 14-15, 14-18, 14-19
lhibidity, reinoval. 20-8 Variable-pitch axial fans, 14-2, 14-9, 14-10, 14-11, 14-15,
lhrbine (steam). 7-26, 7-27, 7-31 14-16
auxiliary equipment for, 1-21 Variable loads in cycling, 7-38, 7-41, 7-49
backpressure type, 1-13, 1-14 Variable-pressure operation, 7-23, 7-25, 7-31, 7-32, 7-35,
by-pass system, 7-42 7-40, 7--44, 13-19
expansion (adiabatic). 1-2 Variable-speed fans, 14-13, 14-17, 14-18
protection in cycling, 7-39, 7 4 2 , 7-50 Velocity,
sliding-pressure operation, 7-32, 7-44, 7-45, 7-46, calculations, graphical methods. 22-19
13-19, 13-21 of circulation in U-circuit, 5-23
lhrbo-separators, 5-28, 5-28 design, BFB boilers, 9-13
lbrndown capacity, 7-39, 8-7 design, CFB combustors, 9-23
Turndown, CFB combustion, 9-22 of drift, 15-11
Two-drum bent-tube boilers (marine], 10-3, 10-6, 10-7 in ducts, 6-36, 6-38, 22-19
Two-element control, 13-25 effect on scale removal, 20-32, 21-17
Two-phase flow, 5-18 mass (velocity), 6-24, 6-24, 6-25, 6-35, 7-20
Two-shifting mode in cycling. 7-38, 7-50 measurement, 6-33, 22-19, 22-23
Two-speed fan motor, 14-17 pressure, 6-5, 6-32
Two-stage scrubbers. 15-37, 15-38 stacks, 6-39
Type-S pitot tube. See Stauscheibe pitot tube turndown. BFB combustor, 9-14
vector diagrams (of fans), 14-6
Velox cycle. 1-18
Vented air fans for pulverizers, 11-15
Venturi scrubber, 15-7, 15-28
U-tube circuit, (subcritical drum-type boiler), 5-21, 5-22 Verdinne, Henri, 11-3
U-loop superheater, 10-7 Vertical versus spiral or helical furnace walls, 7-33
Ultimate analysis of coal, 2-7. 2-12 Vertically-fired systems. 12-4, 12-6
Ultimate analysis of other fuels. See Analysis Vibrations in fans, 14-15, 14-21, 23-16
Ultrasonic testing, 17-3, 18-4, 18-15, 18-16, 18-17, 23-7 Vibrators in flyash hoppers, 16-25
Ultraviolet detection, 13-5 Victaulic couplings, 23-19, 23-21
Unaccounted-for losses (heat), 6-10 Viscosity,
Unbalanced thermal loading, 6-53 of fuel oil, 2-30. 2-31, 2-32
Unburned combustible(s), 4-6, 6-9, 22-7, C-3 and temperature relationships, 2-31, 2-32, B-11
Unburned fuel loss, 21-3 Volatile matter in coal, 2-10, A-2, C-6
Uncertainty (error)in efficiency determination, 22-25,22-26 Volatile treatment of feedwater, 20-16
Unclassified heat loss, 6-10 Volume,
Underbed feed, BFB combustion, 9-11, 9-13, 9-14, 9-15 in fans, 6-40, 6-41, 13-31, 14-2, 14-4, 14-6, 14-12,
Underfeed stokers, 12-13 14-19, 14-21
Undergrate air. mass-burning grate, 8-19 in gas-flow. 13-32
Unfired steam generators, 1-16, 8-30, 8-33, 10-10. Volume correction factor (for local negative pressure), 6-37
See also Waste heat boilers Volume correction for elevation above sea level, 6-13, 6-14
United Nations coal classification, A-43 Volumetric flue-gas analysis, 4-5, 22-6
Unprepared refuse, mass-burning of, 8-16, 8-17, 8-18 Volumetric heat release rate, 6-17, 7-5, 8 4
U.S. Bureau of Mines, 2-14, 11-2, 11-6, A-1, A-12, A 4 3 Vorticity, 22-19
U.S. coals, 2-14, 2-16, Appendix A Voskoboinikov, V.G., B-2
U.S. Department of Energy, 24-1 VP boiler, 8-38, 8-39
U.S. emission regulations, 1-20. 1-36. 15-1 VU-40 boiler, 8-8, 8-9, 8-11, 8-12
U.S. Federal Register. 15-1 VU-60 boiler, 8-14, 8-15, 8-16, 8-26, 8-28
1J.S. water supplies, 20-4, 20-5
Use of chelants for internal control, 20-17
UV (ultraviolet) flame detectors, 13-5

Walkdown, safety procedures, 21-26, 21-29


Wall-firing. See Horizontally-fired systems
Wall thickness, hemispherical head, 6-47
Vacuum systems, flyash removal, 1620.16-21, 16-22, 16-23 Wark, Kenneth, 4-8
Valves (boiler), 14-45 Washers, for steam, 5-30
Van Wylen. Gordon 1.. 4-8. 4-11 Wastage of steel. See Corrosion; Steel, corrosion
Van't Hoff equation. 4-19, 13-19 Waste fuel, 1-19, 2-26, 2-27, 8-4, 8-7, 8-10, 8-26
Vane-controlled fans. See Variable inlet vanes Waste gas (regenerator). 2 4 0
Vaporization, heat of, 5-2 Waste heat boilers, 8-30, 8-33, 10-10, 10-15. See Heat
Vaporous carryover, 5-30, 7-16, 2 0 4 3 recovery, steam generators
Vargaftik. N.B., B-1 Water,
T
COMBUSTION
Subiect Index Waf-Zer

analysis of U.S. water supplies, 20-4, 20-5 materials, 17-6


for boilers, 20-11 orbital, 18-12, 18-16
chemistry management system, ICMS, 13-37 repairs, 23-11
density, 5-26, 7-13 solid fins, 18-11
gas (blue gas), 2-39 techniques, 18-6, 18-9, 18-10, 18-11, 18-12
impurities in, 5-25, 20-1, 20-2, 20-3, 20-4 Welds,
oxygen in, 5-10, 20-3,20-30, 20-32.20-38. 21-11 field postweld heat-treating of, 19-18
separation, in boiler drum, 5-25. See Drum internals field radiographical examination of, 19-18
softening processes, 20-6 Weston, P.L., Jr., B-2
and steam mixtures, 5-2, 5-14,5-19, 5-20;5-25, 7-13, 7-19 Wet-bottom vs. dry-bottom furnaces, 7-6
supplies, 20-1, 20-30 Wet-motor pump 1441, 14-43
technology, Chapter 20 Wet natural gas, 2-36
testing, 20-39 Wet-process sludge (FGDS), 15-64
treatment, 7-23, 7-27, 7-50, 20-4, 20-6, 20-11 Wet scrubbers, 15-6, 15-7, 15-28 to 15-64
vapor in gaseous fuels, 2-41, 6-7, C-36 Wet scrubbing.
Water-cooled furnaces. See Furnace wall; Waterwalls effect of chloride, 15-43
Water gas, 2-39, 4-22 effect of magnesium, 15-42
Water-impounded hoppers, 6-9, 7-6, 16-5 Wet steam, 5-2
Water quenching, 17-10 White, David, 2-4
Water-steam cycles. 22-10 Wilkins, D.M.. B-11
Water-tube boilers, 5-5, 10-5 Wilson, Carroll, A-1
Waterwalls, 5-5, 6-50. See Furnace wall; C-E Controlled Windbox-assembly erection, 19-14, 19-15
Circulation boiler Windbox design. See Horizontally fired systems;
erection, 19-10, 19-12, 19-12 Tangential firing systems
evaporation in, 5-8, 5-16 Window welds, 23-12
flow in, 5-16, 5-18 Winkler, Fritz, 9-1
steam generation. 5-8 Wobbling of headers, 18-9
tube failures, 20-21, 20-23, 21-15, 24-11 Wohlenberg, W.J., 11-3
wastage, 3-27, 8-58, 8-59, 24-9 Wood as fuel, 2-23, 2-24, 2-26, C-15, C-16, C-17
Waterwashing, 14-33, 14-34, 14-35 Work, mechanical energy, 1-2 to 1-6, 5-21, 5-23
Watt, J.D., B-12, B-15 Work-hardening. See Fatigue
Weak-acid analysis, coal, 3-12 World Energy Conference, A-1
Wear resistance in fans, 14-3, 14-21, 14-22
Weigh tanks, 2 2 4
Weight of fuel fired, 6-12, 7-3
Weight support in marine boilers, 10-21
Weighted-wire precipitator, 15-8, 15-9, 15-15 Yield strength. 17-13
Weld-beveling. 18-5, 18-6 Young's modulus of elasticity, 17-13
Weld overlay, 8-61
Welded furnace enclosure, 6 4 9 to 6-55. See Fusion-panel
welding; Furnace wall
Welding,
boiler components, 18-2
z
drum plates, 18-6 Zeldovich mechanism (thermal NOx formation), 4-31
of erected components, 19-17 Zeolite softening. 20-9
flux, 18-6 Zerban and Nye, 1-1
hard-face, 8-61 Zero-leakage pumps, 1441, 14-42

You might also like