You are on page 1of 31

PRESUPUESTO FINAL CONSOLIDADO

PROYECTO : CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA


SECCION AUDITORIO
UBICACIN SANTA MARIA JULIO 2017

ITEM DESCRIPCIN METRADO P.U PARCIAL UND

OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y


01
SALUD.
OBRAS PROVISIONALES
01.01
CONSTRUCCIONES PROVISIONALES
01.01.01
01.01.01.01 CERCO PROVISIONAL DE OBRA C/MANTAS DE POLIPROPILENO 120.00 9.17 1,100.40 ML
01.01.01.02 CASETA PARA OFICINA, ALMACEN Y GUARDIANIA 246.12 50.34 12,389.68 M2
01.02 TRABAJOS PRELIMINARES
01.02.01 MOVILIZACIN A OBRA DE EQUIPOS Y HERRAMIENTAS 1.00 1,500.00 1,500.00 GBL
01.02.02 LIMPIEZA DE TERRENO MANUAL 1,302.95 1.19 1,550.51 M2
01.02.03 LIMPIEZA PERMANENTE EN OBRA 1,302.95 31.16 40,599.92 M2
01.02.04 TRAZO, NIVELACION Y REPLANTEO 1,302.95 2.89 3,765.53 M2
01.02.05 REPLANTEO DURANTE LA CONSTRUCCIN 1,302.95 3.09 4,026.12 M2
01.02.06 DESMOVILIZACIN DE EQUIPOS Y HERRAMIENTAS 1.00 2,000.00 2,000.00 GBL
01.02.07 DEMOLICION DE COLUMNAS EXISTENTES 4.10 224.91 922.13 M3
01.02.08 DEMOLICION DE MURO EXISTENTE 22.50 29.00 652.50 M3
01.03 SEGURIDAD Y SALUD LABORAL
01.03.01 EQUIPOS DE PROTECCIN INDIVIDUAL 10.00 65.00 650.00 UND
01.03.02 EQUIPOS DE PROTECCIN COLECTIVA 5.00 65.00 325.00 UND
01.03.03 SEALIZACION TEMPORAL DE SEGURIDAD 1.00 100.00 100.00 GBL
01.03.04 CAPACITACIN EN SEGURIDAD Y SALUD 1.00 750.00 750.00 GBL
RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN
01.03.05 1.00 80.00 80.00 GBL
SEGURIDAD Y SALUD DURANTE EL TRABAJO
02 ESTRUCTURAS
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACIN EN TERRENO NORMAL PARA ZAPATAS 105.84 34.63 3,665.07 M3
02.01.02 EXCAVACIN EN TERRENO NORMAL PARA CIMIENTOS CORRIDOS Y 82.60 31.16 2,573.82 M3
02.01.03 EXCAVACIN PARA CIMIENTO ESCALERAS 1.46 29.58 43.11 M3
02.01.04 RELLENO COMPACTADO C/ MAT. PROPIO 101.42 44.92 4,555.94 M3
02.01.05 REFINE, NIVELACIN Y COMPACTACIN DE TERRENO 132.01 3.53 466.00 M2
02.01.06 ACARREO DE MATERIAL DE EXCAVACIN 227.87 15.58 3,550.23 M3
02.01.07 ELIMINACIN DE MATERIAL EXCEDENTE CON MAQUINARIA 88.47 21.82 1,930.40 M3
02.02 CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G 36.07 189.42 6,832.76 M3
02.02.02 SOLADO PARA ZAPATAS E=4" CON MEZCLA 1:12 C:H 114.13 28.52 3,254.85 M2
02.02.03 SOBRECIMIENTOS -
02.02.03.01 CONCRETO MEZCLA 1:8 CEMENTO-HORMIGON 25% PM 6.52 340.16 2,219.29 M3
02.02.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO 43.50 44.45 1,933.35 M2
02.02.04 FALSO PISO DE 4" MEZCLA 1:8 CEMENTO-HORMIGON 507.55 28.58 14,505.86 M2
02.03 CONCRETO ARMADO -
02.03.01 ZAPATAS -
02.03.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 56.33 322.19 18,150.17 M3
02.03.01.02 ACERO GRADO 60 EN ZAPATAS 1,527.03 4.22 6,444.08 KG
02.03.02 VIGAS DE CIMENTACIN -
02.03.02.01 CONCRETO F'c=210 kg/cm2 EN VIGAS DE CIMENTACIN 7.08 329.65 2,333.92 M3
02.03.02.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACIN 47.20 54.58 2,576.18 M2
02.03.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACIN 401.13 4.30 1,724.86 KG
02.03.03 COLUMNAS -
02.03.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 41.76 436.72 18,235.79 M3
02.03.03.02 ENCOFRADO Y DESENCOFRADO COLUMNAS 230.23 59.13 13,613.65 M2
02.03.03.03 ACERO GRADO 60 EN COLUMNAS 5,522.42 4.15 22,918.05 KG
02.03.04 VIGAS -
02.03.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 12.64 349.63 4,419.55 M3
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 48.00 58.39 2,802.75 M2
02.03.04.03 ACERO GRADO 60 EN VIGAS 1,723.94 4.35 7,499.14 KG
02.03.05 LOSAS ALIGERADAS -
02.03.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 18.72 347.39 6,504.66 M3
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS 242.64 64.71 15,701.15 M2
02.03.05.03 ACERO GRADO 60 EN LOSAS ALIGERADAS 923.90 4.31 3,981.99 KG
02.03.05.04 LADRILLO HUECO/ARCILLA 15x30x30 P/TECHO ALIGERADO 1,741.97 2.65 4,616.22 UND.
02.03.06 PLACAS -
02.03.05.01 CONCRETO EN PLACAS F'C=210 KG/CM2 50.93 436.72 22,243.37 M3
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS 292.18 50.37 14,716.85 M2
02.03.05.03 ACERO GRADO 60 EN PLACAS 2,732.84 4.31 11,778.53 KG
02.03.07 ESCALERAS -
02.03.07.01 CONCRETO EN ESCALERAS F'C=210 KG/CM2 3.66 436.72 1,596.76 M3
02.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 18.90 51.70 976.97 M2
02.03.07.03 ACERO GRADO 60 EN ESCALERAS 691.08 4.30 2,971.64 KG
02.03.06 PODIUM
02.03.08.01 CONCRETO EN PODIUM F'C=210 KG/CM2 10.91 305.32 3,331.04 M3
02.03.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PODIUM 8.56 37.63 322.15 M2
02.03.08.03 ACERO GRADO 60 EN PODIUM 180.00 3.94 709.20 KG
03 ARQUITECTURA -
03.01 MUROS Y TABIQUES -
MURO DE LADRILLO K.K DE ARCILLA 18H DE SOGA MEZCLA C:A
03.01.01 417.94 71.29 29,795.09 M2
1:4x1.5cm
03.02 REVOQUES Y ENLUCIDOS -
03.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO MEZ. C:A 1:5 69.55 18.49 1,285.98 M2
TARRAJEO FROTACHADO DE MUROS INTERIORES MEZ. C:A 1:5
5,679.19
03.02.02 E=1.5cm 300.01 18.93 M2
TARRAJEO FROTACHADO DE MUROS EXTERIORES MEZ. C:A 1:5
7,530.08
03.02.03 E=1.5cm 321.94 23.39 M2
TARRAJEO FROTACHADO DE COLUMNAS MEZ. C:A 1:5 E=1.5cm
5,407.37
03.02.04 178.82 30.24 M2
03.02.05 TARRAJEO FROTACHADO DE VIGAS MEZ. C:A 1:5 E=1.5cm 69.28 39.18 2,714.23 M2
03.02.06 TARRAJEO FROTACHADO DE PLACAS MEZ. C:A 1:5 E=1.5cm 279.95 31.52 8,824.02 M2
03.02.07 VESTIDURA DE DERRAMES 58.60 14.78 866.11 ML
03.03 CIELORRASOS - ML
03.03.01 CIELORRASO CON MEZCLA C:A 1:4 E=2cm 208.05 31.51 6,555.61 ML
03.03.02 VESTIDURA DE FONDO DE ESCALERA C/MEZCLA 1:5 E=1.5cm 11.40 26.54 302.56 ML
SUB TOTAL 375,071.38
IGV(18%) 67512.85
PRESUPUESTO FINAL 442584.23
METRADO BASE DE PROVISIONALES

PROYECTO : CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA

SECCION OBRAS PROVISIONALES


UBICACIN SANTA MARIA JULIO 2017

ITEM DESCRIPCIN TOTAL UND

01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD.


OBRAS PROVISIONALES
01.01
CONSTRUCCIONES PROVISIONALES
01.01.01
01.01.01.01 CERCO PROVISIONAL DE OBRA C/MANTAS DE POLIPROPILENO 120.00 ML
01.01.01.02 CASETA PARA OFICINA, ALMACEN Y GUARDIANIA 246.12 M2
01.02 TRABAJOS PRELIMINARES
01.02.01 MOVILIZACIN A OBRA DE EQUIPOS Y HERRAMIENTAS 1.00 GBL
01.02.02 LIMPIEZA DE TERRENO MANUAL 1,302.95 M2
01.02.03 LIMPIEZA PERMANENTE EN OBRA 1,302.95 M2
01.02.04 TRAZO, NIVELACION Y REPLANTEO 1,302.95 M2
01.02.05 REPLANTEO DURANTE LA CONSTRUCCIN 1,302.95 M2
01.02.06 DESMOVILIZACIN DE EQUIPOS Y HERRAMIENTAS 1.00 GBL
01.02.07 DEMOLICION DE COLUMNAS EXISTENTES 4.10 M3
01.02.08 DEMOLICION DE MURO EXISTENTE 22.50 M2
01.03 SEGURIDAD Y SALUD LABORAL
01.03.01 EQUIPOS DE PROTECCIN INDIVIDUAL 10.00 UND
01.03.02 EQUIPOS DE PROTECCIN COLECTIVA 5.00 UND
01.03.03 SEALIZACION TEMPORAL DE SEGURIDAD 1.00 GBL
01.03.04 CAPACITACIN EN SEGURIDAD Y SALUD 1.00 GBL

01.03.05 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO 1.00
GBL
METRADO BASE DE ESTRUCTURAS

PROYECT : CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-


LIMA
SECCION :ESTRUCTURAS
MODULO AUDITORIO
UBICACI SANTA MARIA FECHA: JULIO 2017

ITEM DESCRIPCION TOTAL UND.


02 ESTRUCTURAS
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACIN EN TERRENO NORMAL PARA ZAPATAS 105.84 M3
02.01.02 EXCAVACIN EN TERRENO NORMAL PARA CIMIENTOS CORRIDOS 82.60 M3
02.01.03 EXCAVACIN PARA CIMIENTO ESCALERAS 1.46 M3
02.01.04 RELLENO COMPACTADO C/ MAT. PROPIO 101.42 M3
02.01.05 REFINE, NIVELACIN Y COMPACTACIN DE TERRENO 132.01 M2
02.01.06 ACARREO DE MATERIAL DE EXCAVACIN 227.87 M3
02.01.07 ELIMINACIN DE MATERIAL EXCEDENTE CON MAQUINARIA 88.47 M3
02.02 CONCRETO SIMPLE
02.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P. 36.07 M3
02.02.02 SOLADO PARA ZAPATAS E=4" CON MEZCLA 1:12 C:H 114.13 M2
02.02.03 SOBRECIMIENTOS
02.02.03.01 CONCRETO MEZCLA 1:8 CEMENTO-HORMIGON 25% PM 6.52 M3
02.02.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO 43.50 M2
02.02.04 FALSO PISO DE 4" MEZCLA 1:8 CEMENTO-HORMIGON 507.55 M2
02.03 CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 56.33 M3
02.03.01.02 ACERO GRADO 60 EN ZAPATAS 1,527.03 KG
02.03.02 VIGAS DE CIMENTACIN
02.03.02.01 CONCRETO F'c=210 kg/cm2 EN VIGAS DE CIMENTACIN 7.08 M3
02.03.02.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACIN 47.20 M2
02.03.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACIN 401.13 KG
02.03.03 COLUMNAS
02.03.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 41.76 M3
02.03.03.02 ENCOFRADO Y DESENCOFRADO COLUMNAS 230.23 M2
02.03.03.03 ACERO GRADO 60 EN COLUMNAS 5,522.42 KG
02.03.04 VIGAS
02.03.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 12.64 M3
02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 48.00 M2
02.03.04.03 ACERO GRADO 60 EN VIGAS 1,723.94 KG
02.03.05 LOSAS ALIGERADAS
02.03.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2 18.72 M3
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS 242.64 M2
02.03.05.03 ACERO GRADO 60 EN LOSAS ALIGERADAS 923.90 KG
02.03.05.04 LADRILLO HUECO/ARCILLA 15x30x30 P/TECHO ALIGERADO 1,741.97 UND.
02.03.06 PLACAS
02.03.06.01 CONCRETO EN PLACAS F'C=210 KG/CM2 50.93 M3
02.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS 292.18 M2
02.03.06.03 ACERO GRADO 60 EN PLACAS 2,732.84 KG
02.03.07 ESCALERAS
02.03.07.01 CONCRETO EN escaleras F'C=210 KG/CM2 3.66 M3
02.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 18.90 M2
02.03.07.03 ACERO GRADO 60 EN ESCALERAS 691.08 KG
02.03.08 PODIUM
02.03.08.01 CONCRETO EN PODIUM F'C=210 KG/CM2 10.91 M3
02.03.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PODIUM 8.56 M2
02.03.08.03 ACERO GRADO 60 EN PODIUM 180.00 KG
METRADO BASE DE ESTRUCTURAS
PROYECTO : CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ARQUITECTURA
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

CODIGO N de Medidas
Descripcin Parcial Total Und.
N Veces Largo Ancho Alto
03 AUDITORIO
03.01 MUROS Y TABIQUES
03.01.01 MURO DE LADRILLO K.K DE ARCILLA 18H DE SOGA MEZCLA C:A 1:4x1.5cm 417.94 M2
PRIMER NIVEL
EJE A 1.00 5.10 2.50 12.75
Ventanas -1.00 3.10 1.60 -4.96
EJE B 1.00 4.44 2.50 11.10
EJE C,L 2.00 0.35 2.50 1.75
EJE M 1.00 4.44 2.50 11.10
Ventanas -1.00 1.31 1.60 -2.10
EJE 1.00 2.55 2.50 6.38
EJE O 1.00 4.30 2.50 10.75
EJE 5 1.00 4.18 2.50 10.45
1.00 3.75 2.50 9.38
Ventanas -1.00 2.75 1.60 -4.40
EJE 2 4.00 2.70 2.50 27.00
EJES INCLINADOS LADO IZQUIERDO Y DERECHO 2.00 9.52 2.50 47.60
Ventanas -2.00 2.95 1.60 -9.44
MUROS CIRCULARES 2.00 3.57 2.50 17.85
EN LOS SS.HH. 2.00 13.91 2.50 69.55
0.00
SEGUNDO NIVEL 0.00

EJE A 1.00 5.10 2.60 13.26


Ventanas -1.00 3.10 1.60 -4.96
EJE C,L 2.00 0.35 2.60 1.82
EJE 1.00 2.55 2.60 6.63
EJE O 1.00 4.30 2.60 11.18
EJE 5 1.00 4.18 2.60 10.87
1.00 3.75 2.60 9.75
Ventanas -1.00 2.75 1.60 -4.40
EJE 2 4.00 2.70 2.60 28.08
EJES INCLINADOS LADO IZQUIERDO Y DERECHO 2.00 9.52 2.60 49.50
Ventanas -2.00 2.95 1.60 -9.44
MUROS CIRCULARES 2.00 3.57 2.60 18.56
EN LOS SS.HH. 2.00 13.91 2.60 72.33

03.02 REVOQUES Y ENLUCIDOS


03.02.01 TARRAJEO DEL TIPO RAYADO O PRIMARIO MEZ. C:A 1:5 69.55 M2

EN LOS SS.HH. 2.00 13.91 2.50 69.55

03.02.02 TARRAJEO FROTACHADO DE MUROS INTERIORES MEZ. C:A 1:5 E=1.5cm 300.01 M2
PRIMER NIVEL
EJE A 1.00 5.10 2.50 12.75
Ventanas -1.00 3.10 1.60 -4.96
EJE B 2.00 4.44 2.50 22.20
EJE C,L 4.00 0.35 2.50 3.50
EJE M 2.00 4.44 2.50 22.20
Ventanas -1.00 1.31 1.60 -2.10
EJE 1.00 2.55 2.50 6.38
EJE O 1.00 4.30 2.50 10.75
EJE 5 1.00 4.18 2.50 10.45
1.00 3.75 2.50 9.38
Ventanas -1.00 2.75 1.60 -4.40
EJE 2 4.00 2.70 2.50 27.00
EJES INCLINADOS LADO IZQUIERDO Y DERECHO 2.00 9.52 2.50 47.60
Ventanas -2.00 2.95 1.60 -9.44
MUROS CIRCULARES 2.00 3.57 2.50 17.85

SEGUNDO NIVEL

EJE A 1.00 5.10 2.60 13.26


Ventanas -1.00 3.10 1.60 -4.96
EJE C,L 2.00 0.35 2.60 1.82
EJE 1.00 2.55 2.60 6.63
EJE O 1.00 4.30 2.60 11.18
EJE 5 1.00 4.18 2.60 10.87
1.00 3.75 2.60 9.75
Ventanas -1.00 2.75 1.60 -4.40
EJE 2 4.00 2.70 2.60 28.08
EJES INCLINADOS LADO IZQUIERDO Y DERECHO 2.00 9.52 2.60 49.50
Ventanas -2.00 2.95 1.60 -9.44
MUROS CIRCULARES 2.00 3.57 2.60 18.56
03.02.03 TARRAJEO FROTACHADO DE MUROS EXTERIORES MEZ. C:A 1:5 E=1.5cm 321.94 M2

PRIMER NIVEL
EJE A 1.00 5.10 2.50 12.75
Ventanas -1.00 3.10 1.60 -4.96
EJE 1.00 2.55 2.50 6.38
EJE O 1.00 4.30 2.50 10.75
EJE 5 1.00 4.18 2.50 10.45
1.00 3.75 2.50 9.38
Ventanas -1.00 2.75 1.60 -4.40
EJE 2 4.00 2.70 2.50 27.00
EJES INCLINADOS LADO IZQUIERDO Y DERECHO 2.00 9.52 2.50 47.60
Ventanas -2.00 2.95 1.60 -9.44
MUROS CIRCULARES 2.00 3.57 2.50 17.85
EN LOS SS.HH. 2.00 13.91 2.50 69.55

SEGUNDO NIVEL

EJE A 1.00 5.10 2.60 13.26


Ventanas -1.00 3.10 1.60 -4.96
EJE 1.00 2.55 2.60 6.63
EJE O 1.00 4.30 2.60 11.18
EJE 5 1.00 4.18 2.60 10.87
1.00 3.75 2.60 9.75
Ventanas -1.00 2.75 1.60 -4.40
EJE 2 4.00 2.70 2.60 28.08
EJES INCLINADOS LADO IZQUIERDO Y DERECHO 2.00 9.52 2.60 49.50
Ventanas -2.00 2.95 1.60 -9.44
MUROS CIRCULARES 2.00 3.57 2.60 18.56

03.02.04 TARRAJEO FROTACHADO DE COLUMNAS MEZ. C:A 1:5 E=1.5cm 178.82 M2

PRIMER PISO Y SEGUNDO NIVEL


ENTRE EJE 8 - 8, C-1
Cara Interna 7.00 (*) Perim. = 0.30 6.55 13.76
Cara Externa 1.00 (*) Perim. = 0.60 6.55 3.93
ENTRE EJE 7 - 7, C-1
Cara Interna 2.00 (*) Perim. = 0.60 6.55 7.86
ENTRE EJE 5 - 5, C-1
Cara Interna 7.00 (*) Perim. = 0.30 6.55 13.76
Cara Interna 1.00 (*) Perim. = 0.60 6.55 3.93

ENTRE EJE 6 - 6, C-2


Cara Interna 2.00 (*) Perim. = 1.55 6.55 20.31
Cara Interna 2.00 (*) Perim. = 2.25 6.55 29.48

ENTRE EJE 6 - 6, C-3


Cara Interna 2.00 (*) Perim. = 2.00 6.55 26.20

ENTRE EJE 2- 2, C-2


Cara Interna 2.00 (*) Perim. = 2.25 6.55 29.48
ENTRE EJE 2- 2, C-3
Cara Interna 2.00 (*) Perim. = 2.30 6.55 30.13

03.02.05 TARRAJEO FROTACHADO DE VIGAS MEZ. C:A 1:5 E=1.5cm 69.28 M2

PRIMER NIVEL-LADO IZQUIERDO


VA-0.30X0.35
EJE A, ENTRE 5 Y 8 1.00 6.00 0.60 3.60
EJE 8, ENTRE A Y C 1.00 7.42 0.60 4.45
VB-0.30X0.45
EJE B, ENTRE 5 Y 8 1.00 4.83 0.80 3.86

SEGUNDO NIVEL-LADO IZQUIERDO


VA-0.30X0.35
EJE A, ENTRE 5 Y 8 1.00 6.00 0.60 3.60
EJE 8, ENTRE A Y C 1.00 7.42 0.60 4.45
VB-0.30X0.45
EJE B, ENTRE 5 Y 8 1.00 4.83 0.80 3.86

PRIMER NIVEL-LADO DERECHO


V8-0.30X0.35
EJE 8, ENTRE K Y O 1.00 13.05 0.60 7.83
EJE 5, ENTRE M Y O 1.00 6.04 0.60 3.62
EJE . ENTRE 5 Y 8 1.00 3.15 0.60 1.89
VN-0.30X0.50
EJE N, ENTRE 5 Y 8 1.00 6.02 0.90 5.42
VM-0.30X0.45
EJE M, ENTRE 5 Y 8 1.00 4.95 0.80 3.96

SEGUNDO NIVEL-LADO DERECHO


V8-0.30X0.35
EJE 8, ENTRE K Y O 1.00 13.05 0.60 7.83
EJE 5, ENTRE M Y O 1.00 6.04 0.60 3.62
EJE . ENTRE 5 Y 8 1.00 3.15 0.60 1.89
VN-0.30X0.50
EJE N, ENTRE 5 Y 8 1.00 6.02 0.90 5.42
VM-0.30X0.45
EJE M, ENTRE 5 Y 8 1.00 4.95 0.80 3.96

03.02.06 TARRAJEO FROTACHADO DE PLACAS MEZ. C:A 1:5 E=1.5cm 279.95 M2

PLACA PL-04 2.00 1.95 4.50 17.55


PLACA PL-06 2.00 1.50 4.50 13.50

PLACA PL-01 4.00 3.85 6.55 100.87


PLACA PL-02 4.00 3.85 6.55 100.87
PLACA PL-03 4.00 1.80 6.55 47.16

03.02.07 VESTIDURA DE DERRAMES 58.60 ML


LADO IZQUIERDO y DERECHO
Ventanas 2.00 6.80 13.60
Ventanas 2.00 5.54 11.08
EJE A 2.00 6.30 12.60
EJE M 1.00 6.22 6.22
EJE 1.00 6.40 6.40
EJE 5 1.00 8.70 8.70

03.03 CIELORRASOS
03.03.01 CIELORRASO CON MEZCLA C:A 1:4 E=2cm 208.05 M2

PRIMER NIVEL
Almacen lado izquierdo 1.00 area = 26.9162 26.92
Almacen, eq. sonido lado derecho 1.00 area = 61.4235 61.42

SEGUNDO NIVEL
Equipo de sonido lado izquierdo 1.00 area = 32.8973 32.90
Almacen, eq. sonido lado derecho 1.00 area = 58.1217 58.12

SS.HH. 1.00 area= 28.69 28.69

03.03.02 VESTIDURA DE FONDO DE ESCALERA C/MEZCLA 1:5 E=1.5cm 11.40 M2

ESCALERA N01
LOSA DE ESCALERA 1.00 1.75 4.00 7.00

ESCALERA N02
LOSA DE ESCALERA 1.00 1.10 4.00 4.40
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL
02 ESTRUCTURAS
02.01 MOVIMIENTO DE TIERRAS
02.01.01 EXCAVACIN EN TERRENO NORMAL PARA ZAPATAS 105.84 M3

Z-1 17.00 1.25 1.10 1.65 38.57


-
Z-2 2.00 2.65 1.45 1.65 12.68
-
Z-3 6.00 2.25 1.45 1.65 32.30
-
Z-4 4.00 2.20 1.55 1.65 22.51
-
Z-5 2.00 2.00 1.35 1.65 8.91
-
Z-6 2.00 2.25 3.25 1.65 24.13
Z-7 1.00 1.95 1.65 1.65 5.31
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

02.01.02 EXCAVACIN EN TERRENO NORMAL PARA CIMIENTOS CORRIDOS Y VIGAS DE CIMENTACIN 82.60 M3

EJE A ENTRE 5-8 1.00 3.20 0.60 1.30 2.50


EJE B ENTRE 5-8 1.00 3.45 0.60 1.30 2.69
EJE M ENTRE 5-8 1.00 3.40 0.60 1.30 2.65
EJE ENTRE 5-8 1.00 3.15 0.60 1.30 2.46
EJE O ENTRE 5-8 1.00 4.90 0.60 1.30 3.82
-
EJE 8 ENTRE C Y O 1.00 20.12 1.25 1.65 41.50
EJE 5 ENTRE M Y O, corte 2-2 1.00 5.40 0.60 1.30 4.21
EJE 5 ENTRE M Y O, corte 8-8 1.00 0.65 0.60 1.30 0.51
EJE 5 ENTRE A Y B 1.00 1.60 0.60 1.30 1.25
EJE 5 ENTRE A Y B 1.00 0.65 0.60 1.30 0.51
-
VIGA CIM. Lzqui y Derecha 2.00 10.95 0.60 1.45 19.05
-
02.01.03 EXCAVACIN PARA CIMIENTO ESCALERAS - 1.46 M3
ESC. LADO IZQUIERDO 1.00 1.10 0.45 1.00 0.50
ESC. LADO DERECHO 1.00 1.75 0.55 1.00 0.96

02.01.04 RELLENO COMPACTADO C/ MAT. PROPIO 101.42 M3

RELLENO PARA LAS ZAPATAS


EJES VERTICALES
EJE A /EJE 5 Y 7 10.00 AREA= 1.29 0.95 12.21
EJE B / ENTRE EJE 7 Y 5 6.00 AREA= 1.29 0.95 7.35
EJE C / EJE 1 1.00 AREA= 3.64 0.95 3.46
EJE C / EJE 2 2.00 AREA= 2.25 0.95 4.28
EJE E / EJE 2 2.00 AREA= 2.98 0.95 5.65
EJE F / EJE 2 2.00 AREA= 2.80 0.95 5.32
EJE G / EJE 1 1.00 AREA= 2.92 0.95 2.77
EJE N / EJE 5 1.00 AREA= 1.29 0.95 1.23
EJE / EJE 5 Y 7 2.00 AREA= 1.29 0.95 2.45

EJES HORIZONTALES

EJE 1 / EJE B Y M 2.00 AREA= 6.92 0.95 13.15


EJE 6 / ( Z-3 ) 4.00 AREA= 2.80 0.95 10.63
EJE 6 / ( Z-4 ) 2.00 AREA= 3.09 0.95 5.86

CON CIMIENTOS CORRIDOS


EJE A ENTRE 5-8 1.00 3.20 0.60 0.50 0.96
EJE B ENTRE 5-8 1.00 3.45 0.60 0.50 1.04
EJE M ENTRE 5-8 1.00 3.40 0.60 0.50 1.02
EJE ENTRE 5-8 1.00 3.15 0.60 0.50 0.95
EJE O ENTRE 5-8 1.00 4.90 0.60 0.50 1.47
EJE 8 ENTRE C Y O 1.00 20.12 1.25 0.50 12.58
EJE 5 ENTRE M Y O, corte 2-2 1.00 5.40 0.60 0.50 1.62
EJE 5 ENTRE M Y O, corte 8-8 1.00 0.65 0.60 0.50 0.20
EJE 5 ENTRE A Y B 1.00 1.60 0.60 0.50 0.48
EJE 5 ENTRE A Y B 1.00 0.65 0.60 0.50 0.20

CON VIGAS DE CIMENTACION


VIGA CIM. Lzqui y Derecha 2.00 10.95 0.60 0.50 6.57

02.01.05 REFINE, NIVELACIN Y COMPACTACIN DE TERRENO 132.01 M2

RELLENO PARA LAS ZAPATAS


EJES VERTICALES
EJE A /EJE 5 Y 7 10.00 AREA= 1.29 12.85
EJE B / ENTRE EJE 7 Y 5 6.00 AREA= 1.29 7.74
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL
EJE C / EJE 1 1.00 AREA= 3.64 3.64
EJE C / EJE 2 2.00 AREA= 2.25 4.50
EJE E / EJE 2 2.00 AREA= 2.98 5.95
EJE F / EJE 2 2.00 AREA= 2.80 5.60
EJE G / EJE 1 1.00 AREA= 2.92 2.92
EJE N / EJE 5 1.00 AREA= 1.29 1.29
EJE / EJE 5 Y 7 2.00 AREA= 1.29 2.58

EJES HORIZONTALES

EJE 1 / EJE B Y M 2.00 AREA= 6.92 13.85


EJE 6 / ( Z-3 ) 4.00 AREA= 2.80 11.19
EJE 6 / ( Z-4 ) 2.00 AREA= 3.09 6.17

CON CIMIENTOS CORRIDOS


EJE A ENTRE 5-8 1.00 3.20 0.60 1.92
EJE B ENTRE 5-8 1.00 3.45 0.60 2.07
EJE M ENTRE 5-8 1.00 3.40 0.60 2.04
EJE ENTRE 5-8 1.00 3.15 0.60 1.89
EJE O ENTRE 5-8, corte 2-2 1.00 4.90 0.60 2.94
-
EJE 8 ENTRE C Y O 1.00 20.12 1.25 25.15
EJE 5 ENTRE M Y O, corte 2-2 1.00 5.40 0.60 3.24
EJE 5 ENTRE M Y O, corte 8-8 1.00 0.65 0.60
EJE 5 ENTRE A Y B 1.00 1.60 0.60 0.96
EJE 5 ENTRE A Y B 1.00 0.65 0.60 0.39

CON VIGAS DE CIMENTACION


VIGA CIM. Lzqui y Derecha 2.00 10.95 0.60 13.14

02.01.06 ACARREO DE MATERIAL DE EXCAVACIN 227.87 M3

EXCAVACIN EN TERRENO NORMAL PARA ZAPATAS 105.84


EXCAVACIN EN TERRENO NORMAL PARA CIMIENTOS CORRIDOS Y VIGAS DE 82.60
EXCAVACIN PARA CIMIENTO ESCALERAS 1.46

02.01.07 ELIMINACIN DE MATERIAL EXCEDENTE CON MAQUINARIA 88.47 M3

EXCAVACIN EN TERRENO NORMAL PARA ZAPATAS 105.84


EXCAVACIN EN TERRENO NORMAL PARA CIMIENTOS CORRIDOS Y VIGAS DE 82.60
EXCAVACIN PARA CIMIENTO ESCALERAS 1.46
RELLENO COMPACTADO C/ MAT. PROPIO (101.42)

02.02 CONCRETO SIMPLE


02.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G 36.07 M3

AUDITORIO-SALON
EJE A ENTRE 5-8 1.00 5.10 0.60 0.80 2.45
EJE B ENTRE 5-8 1.00 4.50 0.60 0.80 2.16
EJE M ENTRE 5-8 1.00 4.50 0.60 0.80 2.16
EJE ENTRE 5-8 1.00 5.10 0.60 0.80 2.45
EJE O ENTRE 5-8 1.00 4.95 0.60 0.80 2.38
-
EJE 5 ENTRE M Y O 1.00 5.50 0.60 0.80 2.64
EJE 5 ENTRE M Y O, corte 8-8 1.00 1.10 0.60 0.80 0.53
EJE 5 ENTRE A Y B 1.00 2.00 0.60 0.80 0.96
EJE 5 ENTRE A Y B 1.00 1.10 0.60 0.80 0.53
-
VIGA CIM. Izqui y Der. Corte 3-3 2.00 13.75 0.60 0.70 11.55
VIGA CIM. Izqui y Der. Corte 4-4 2.00 7.10 0.60 0.70 5.96
VIGA CIM. Izqui y Der. Corte 5-5 2.00 2.75 0.60 0.70 2.31
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

02.02.02 SOLADO PARA ZAPATAS E=4" CON MEZCLA 1:12 C:H 114.13 M2
EN ZAPATAS
Z-1 17.00 1.25 1.10 23.38
-
Z-2 2.00 2.65 1.45 7.69
-
Z-3 6.00 2.25 1.45 19.58
-
Z-4 4.00 2.20 1.55 13.64
-
Z-5 2.00 2.00 1.35 5.40
-
Z-6 2.00 2.25 3.25 14.63
Z-7 1.00 1.95 1.65 3.22

EJE 8 ENTRE C Y O 1.00 20.12 1.25 25.15

EN ESCALERAS
ESC. LADO IZQUIERDO 1.00 1.10 0.45 0.50
ESC. LADO DERECHO 1.00 1.75 0.55 0.96

02.02.03 SOBRECIMIENTOS
02.02.03.01 CONCRETO MEZCLA 1:8 CEMENTO-HORMIGON 25% PM 6.52 M3
EJE A ENTRE 5-8 1.00 5.10 0.15 0.70 0.54
EJE B ENTRE 5-8 1.00 4.50 0.15 0.70 0.47
EJE M ENTRE 5-8 1.00 4.50 0.15 0.70 0.47
EJE ENTRE 5-8 1.00 5.10 0.15 0.70 0.54
EJE O ENTRE 5-8 1.00 4.95 0.15 0.70 0.52
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL
EJE 5 ENTRE M Y O 1.00 5.50 0.15 0.70 0.58
EJE 5 ENTRE M Y O, corte 8-8 1.00 1.10 0.15 0.70 0.12
EJE 5 ENTRE A Y B 1.00 2.00 0.15 0.70 0.21
EJE 5 ENTRE A Y B 1.00 1.10 0.15 0.70 0.12

VIGA CIM. Izqui y Der. Corte 3-3 2.00 13.75 0.15 0.60 2.48
VIGA CIM. Izqui y Der. Corte 5-5 2.00 2.75 0.15 0.60 0.50

02.02.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO 43.50 M2

EJE A ENTRE 5-8 1.00 5.10 0.70 3.57


EJE B ENTRE 5-8 1.00 4.50 0.70 3.15
EJE M ENTRE 5-8 1.00 4.50 0.70 3.15
EJE ENTRE 5-8 1.00 5.10 0.70 3.57
EJE O ENTRE 5-8 1.00 4.95 0.70 3.47

EJE 5 ENTRE M Y O 1.00 5.50 0.70 3.85


EJE 5 ENTRE M Y O, corte 8-8 1.00 1.10 0.70 0.77
EJE 5 ENTRE A Y B 1.00 2.00 0.70 1.40
EJE 5 ENTRE A Y B 1.00 1.10 0.70 0.770

VIGA CIM. Izqui y Der. Corte 3-3 2.00 13.75 0.60 16.500
VIGA CIM. Izqui y Der. Corte 5-5 2.00 2.75 0.60 3.300
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

02.02.04 FALSO PISO DE 4" MEZCLA 1:8 CEMENTO-HORMIGON 507.55 M2


LADO IZQUIERDO
EQUIPO DE SONIDO 1.00 AREA 12.21 12.21
ALMACEN-DEPOSITO 1.00 AREA 16.55 16.55

LADO DERECHO
EQUIPO DE SONIDO 1.00 AREA 12.21 12.21
ALMACEN-DEPOSITO 1.00 AREA 45.23 45.23

SALON-AUDITORIO 1.00 AREA 421.36 421.36

02.03 CONCRETO ARMADO


02.03.01 ZAPATAS
02.03.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 56.33 M3

ZAPATAS
Z-1 17.00 1.25 1.10 0.50 11.69
-
Z-2 2.00 2.65 1.45 0.50 3.84
-
Z-3 6.00 2.25 1.45 0.50 9.79
-
Z-4 4.00 2.20 1.55 0.50 6.82
-
Z-5 2.00 2.00 1.35 0.50 2.70
-
Z-6 2.00 2.25 3.25 0.50 7.31

Z-7 1.00 1.95 1.65 0.50 1.61


CIMIENTO CORRIDO
EJE 8 ENTRE C Y O 1.00 20.12 1.25 0.50 12.58

02.03.01.02 ACERO GRADO 60 EN ZAPATAS 1,527.03 KG


VER PLANILLA DE METRADOS ACEROS 1,527.03

02.03.02 VIGAS DE CIMENTACIN


02.03.02.01 CONCRETO F'c=210 kg/cm2 EN VIGAS DE CIMENTACIN 7.08 M3

AUDITORIO-SALON

VIGA CIM. Izqui y Der. Corte 3-3 2.00 13.75 0.30 0.50 4.13
VIGA CIM. Izqui y Der. Corte 4-4 2.00 7.10 0.30 0.50 2.13
VIGA CIM. Izqui y Der. Corte 5-5 2.00 2.75 0.30 0.50 0.83

02.03.02.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS DE CIMENTACIN 47.20 M2

AUDITORIO-SALON

VIGA CIM. Izqui y Der. Corte 3-3 2.00 13.75 1.00 27.50
VIGA CIM. Izqui y Der. Corte 4-4 2.00 7.10 1.00 14.20
VIGA CIM. Izqui y Der. Corte 5-5 2.00 2.75 1.00 5.50

02.03.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACIN 401.13 #REF!


VER PLANILLA DE METRADOS ACEROS 401.13
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

02.03.03 COLUMNAS
02.03.03.01 CONCRETO EN COLUMNAS F'C=210 KG/CM2 41.76 M3.

AUDITORIO-SALON

C 1, 0.30x0.30 26.00 0.30 0.30 6.55 15.33

C 2, forma L 3.00 1.55 0.30 6.55 9.14


3.00 1.55 0.30 6.55 9.14
C 3, forma T 2.00 1.45 0.30 6.55 5.70

C4, 0.50X0.30 2.00 0.50 0.30 6.55 1.97

C5,0.15X0.50 1.00 0.15 0.50 6.55 0.49

02.03.03.02 ENCOFRADO Y DESENCOFRADO COLUMNAS 230.23 M2

AUDITORIO-SALON

C 1, 0.30x0.30 `+20+6 1.20 6.55 7.86

C 2, forma L 3.00 3.10 6.55 60.92


3.00 3.10 6.55 60.92
C 3, forma T 3.50 3.10 6.55 71.07

C4, 0.50X0.30 2.00 1.60 6.55 20.96

C5,0.15X0.50 1.00 1.30 6.55 8.52

02.03.03.03 ACERO GRADO 60 EN COLUMNAS 5,522.42 KG


Ver Planilla de acero 5,522.42

02.03.04 VIGAS
02.03.04.01 CONCRETO EN VIGAS F'C=210 KG/CM2 - - 12.64 M3

PRIMER NIVEL-LADO IZQUIERDO


VA-0.30X0.35
EJE A, ENTRE 5 Y 8 1.00 6.00 0.30 0.35 0.63
EJE 8, ENTRE A Y C 1.00 7.42 0.30 0.35 0.78
VB-0.30X0.45
EJE B, ENTRE 5 Y 8 1.00 4.83 0.30 0.45 0.65
VCH-0.30X0.20
EJE 5, ENTRE A Y B 1.00 1.85 0.30 0.20 0.11
EJE 7, ENTRE A Y B 1.00 6.11 0.30 0.20 0.37
EJE A', ENTRE 7 Y 6 1.00 2.85 0.30 0.20 0.17
EJE C, ENTRE 7 Y 8 1.00 2.05 0.30 0.20 0.12
EJE 4, ENTRE A Y C 1.00 6.71 0.30 0.20 0.40

SEGUNDO NIVEL-LADO IZQUIERDO


EJE A, ENTRE 5 Y 8 1.00 6.00 0.30 0.35 0.63
EJE 8, ENTRE A Y C 1.00 7.42 0.30 0.35 0.78
VB-0.30X0.45
EJE B, ENTRE 5 Y 8 1.00 4.83 0.30 0.45 0.65
VCH-0.30X0.20
EJE 5, ENTRE A Y B 1.00 1.85 0.30 0.20 0.11
EJE C, ENTRE 7 Y 8 1.00 2.05 0.30 0.20 0.12
EJE 4, ENTRE A Y C 1.00 6.71 0.30 0.20 0.40

PRIMER NIVEL-LADO DERECHO


V8-0.30X0.35
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL
EJE 8, ENTRE K Y O 1.00 13.05 0.30 0.35 1.37
EJE 5, ENTRE M Y O 1.00 6.04 0.30 0.35 0.63
EJE . ENTRE 5 Y 8 1.00 3.15 0.30 0.35 0.33
VCH-0.30X0.20
INCLINADA, ENTRE K Y N 1.00 1.85 0.30 0.20 0.11
EJE 0, ENTRE 7 Y 8 1.00 6.73 0.30 0.20 0.40
EJE K, ENTRE 8 Y 7 1.00 2.05 0.30 0.20 0.12
VN-0.30X0.50
EJE N, ENTRE 5 Y 8 1.00 6.02 0.30 0.20 0.36
VM-0.30X0.45
EJE M, ENTRE 5 Y 8 1.00 4.95 0.30 0.20 0.30

SEGUNDO NIVEL-LADO DERECHO


V8-0.30X0.35
EJE 8, ENTRE K Y O 1.00 11.62 0.30 0.35 1.22
EJE 5, ENTRE M Y O 1.00 6.04 0.30 0.35 0.63
EJE . ENTRE 5 Y 8 1.00 3.15 0.30 0.35 0.33
VCH-0.30X0.20
INCLINADA, ENTRE K Y N 1.00 1.85 0.30 0.20 0.11
EJE K, ENTRE 8 Y 7 1.00 2.05 0.30 0.20 0.12
VN-0.30X0.50
EJE N, ENTRE 5 Y 8 1.00 6.02 0.30 0.20 0.36
VM-0.30X0.45
EJE M, ENTRE 5 Y 8 1.00 4.95 0.30 0.20 0.30
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

02.03.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 48.00 M2

PRIMER NIVEL-LADO IZQUIERDO


VA-0.30X0.35
EJE A, ENTRE 5 Y 8 1.00 6.00 0.30 1.80
EJE 8, ENTRE A Y C 1.00 7.42 0.30 2.23
VB-0.30X0.45
EJE B, ENTRE 5 Y 8 1.00 4.83 0.65 3.14
VCH-0.30X0.20
EJE 5, ENTRE A Y B 1.00 1.85 0.20 0.37
EJE 7, ENTRE A Y B 1.00 2.00 0.20 0.40
EJE A', ENTRE 7 Y 6 1.00 2.85 0.20 0.57

SEGUNDO NIVEL-LADO IZQUIERDO


VA-0.30X0.35
EJE A, ENTRE 5 Y 8 1.00 6.00 0.30 1.80
EJE 8, ENTRE A Y C 1.00 7.42 0.30 2.23
VB-0.30X0.45
EJE B, ENTRE 5 Y 8 1.00 4.83 0.80 3.86

PRIMER NIVEL-LADO DERECHO


V8-0.30X0.35
EJE 8, ENTRE K Y O 1.00 13.05 0.30 3.92
EJE 5, ENTRE M Y O 1.00 6.04 0.30 1.81
EJE . ENTRE 5 Y 8 1.00 3.15 0.30 0.95
VN-0.30X0.50
EJE N, ENTRE 5 Y 8 1.00 6.02 0.90 5.42
VM-0.30X0.45
EJE M, ENTRE 5 Y 8 1.00 4.95 0.75 3.71

SEGUNDO NIVEL-LADO DERECHO


V8-0.30X0.35
EJE 8, ENTRE K Y O 1.00 13.05 0.30 3.92
EJE 5, ENTRE M Y O 1.00 6.04 0.30 1.81
EJE . ENTRE 5 Y 8 1.00 3.15 0.30 0.95
VN-0.30X0.50
EJE N, ENTRE 5 Y 8 1.00 6.02 0.90 5.42
VM-0.30X0.45
EJE M, ENTRE 5 Y 8 1.00 4.95 0.75 3.71

02.03.04.03 ACERO GRADO 60 EN VIGAS 1,723.94 KG


Ver Planilla de Metrados acero 1,723.94

02.03.05 LOSAS ALIGERADAS 18.72 M3

02.03.05.01 CONCRETO EN LOSAS ALIGERADAS F'C=210 KG/CM2


PRIMER NIVEL
Almacen lado izquierdo 1.00 area = 26.9162 0.09 2.42
Almacen, eq. sonido lado derecho 1.00 area = 61.4235 0.09 5.53

SEGUNDO NIVEL
Equipo de sonido lado izquierdo 1.00 area = 32.8973 0.09 2.96
Almacen, eq. sonido lado derecho 1.00 area = 58.1217 0.09 5.23
SS.HH. 1.00 area= 28.69 0.09 2.58
PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS 242.64 M2

PRIMER NIVEL
Almacen lado izquierdo 1.00 area = 26.9162 26.92
Almacen, eq. sonido lado derecho 1.00 area = 61.4235 61.42
Frisos 1.00 58.79 0.25 14.70
SEGUNDO NIVEL
Equipo de sonido lado izquierdo 1.00 area = 32.8973 32.90
Almacen, eq. sonido lado derecho 1.00 area = 58.1217 58.12
Frisos 1.00 56.12 0.25 14.03
SS.HH. 1.00 area= 28.69 28.69
Frisos 1.00 23.45 0.25 5.86

02.03.05.03 ACERO GRADO 60 EN LOSAS ALIGERADAS 923.90 KG

Ver Planilla de Metrados acero 923.90

02.03.05.04 LADRILLO HUECO/ARCILLA 15x30x30 P/TECHO ALIGERADO 1,741.97

PRIMER NIVEL 8.33 8.33


Almacen lado izquierdo 1.00 area = 26.9162 8.33 224.30
Almacen, eq. sonido lado derecho 1.00 area = 61.4235 8.33 511.86

SEGUNDO NIVEL
Equipo de sonido lado izquierdo 1.00 area = 32.8973 8.33 274.14
Almacen, eq. sonido lado derecho 1.00 area = 58.1217 8.33 484.35
SS.HH. 1.00 area= 28.69 8.33 238.99

02.03.06 PLACAS
02.03.06.01 CONCRETO EN PLACAS F'C=210 KG/CM2 50.93 M3
PLACA PL-04 2.00 1.30 0.3 6.55 5.11
PLACA PL-05 2.00 1.32 0.15 6.55 2.59
PLACA PL-05 2.00 1.50 0.3 6.55 5.90

PLACA PL-01 2.00 3.85 0.3 6.55 15.13


PLACA PL-02 2.00 3.85 0.3 6.55 15.13
PLACA PL-03 2.00 1.80 0.3 6.55 7.07

02.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS 292.18 M2


PLACA PL-04 2.00 3.10 6.55 40.61
PLACA PL-05 2.00 2.79 6.55 36.55
PLACA PL-06 2.00 3.36 6.55 44.02

PLACA PL-01 4.00 3.85 4.50 69.30


PLACA PL-02 4.00 3.85 4.50 69.30
PLACA PL-03 4.00 1.80 4.50 32.40

02.03.06.03 ACERO GRADO 60 EN PLACAS 2732.84 KG

Ver Planilla de Metrados acero 2,732.84

02.03.07 ESCALERAS
02.03.07.01 CONCRETO EN escaleras F'C=210 KG/CM2 3.66 M3
ESCALERA N01
CIMENTACION 1.00 1.75 0.50 1.00 0.88
LOSA DE ESCALERA 1.00 1.75 4.00 0.15 1.05
PASOSY CONTRAPASOS 15.00 0.18 0.25 1.75 1.18

ESCALERA N02
CIMENTACION 1.00 1.10 0.50 1.00 0.55
LOSA DE ESCALERA 1.00 1.10 4.00 0.15 0.66
PASOSY CONTRAPASOS 14.00 0.18 0.25 1.10 0.69

02.03.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 18.90 M2


PLANILLA DE METRADOS DE ESTRUCTURAS

PROYECTO
: CONSTRUCCION DEL AUDITORIO LAS ESTRELLAS- SANTA MARIA-HUAURA-LIMA
SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

MEDIDAS CANTIDAD
ITEM DESCRIPCION N VECES UND.
LARGO ANCHO ALTO PARCIAL TOTAL

ESCALERA N01
LOSA DE ESCALERA 1.00 1.75 4.00 7.00
PASOSY CONTRAPASOS 15.00 1.75 0.18 4.73

ESCALERA N02
LOSA DE ESCALERA 1.00 1.10 4.00 4.40
PASOSY CONTRAPASOS 14.00 1.10 0.18 2.77

02.03.07.03 ACERO GRADO 60 EN ESCALERAS 691.08 KG


Ver Planilla de Metrados acero 691.08

02.03.08 PODIUM
02.03.08.01 CONCRETO EN PODIUM F'C=210 KG/CM2 10.91 M3
CONCRETO 210 1 VOLUMEN= 10.91

02.03.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PODIUM 8.56 M2


1.00 12.23 0.70 8.56

02.03.08.03 ACERO GRADO 60 EN PODIUM 180.00 KG


Acero liso de 3/8 1.00 KG= 180.00 180.00
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)
02.03 CONCRETO ARMADO
02.03.01 ZAPATAS
02.03.01.02 ACERO GRADO 60 EN ZAPATAS

AUDITORIO

Z-1 Parrilla en x 5/8" 1.10 6.00 17.00 112.20 112.20


Parrilla en y 5/8" 0.95 7.00 17.00 113.05 113.05
Z-2 Parrilla en x 5/8" 2.50 8.00 2.00 40.00 40.00
Parrilla en y 5/8" 1.30 14.00 2.00 36.40 36.40
Z-3 Parrilla en x 5/8" 2.10 8.00 6.00 100.80 100.80
Parrilla en y 5/8" 1.30 12.00 6.00 93.60 93.60
Z-4 Parrilla en x 5/8" 2.05 8.00 4.00 65.60 65.60
Parrilla en y 5/8" 1.40 10.00 4.00 56.00 56.00
Z-5 Parrilla en x 5/8" 1.85 8.00 2.00 29.60 29.60
Parrilla en y 5/8" 1.20 12.00 2.00 28.80 28.80
Z-6 Parrilla en x 5/8" 2.10 8.00 2.00 33.60 33.60
Parrilla en y 5/8" 3.10 10.00 2.00 62.00 62.00
Z-7(INFERIOR) Parrilla en x 5/8" 1.80 17.00 1.00 30.60 30.60
Parrilla en y 5/8" 1.50 10.00 1.00 15.00 15.00
Z-7(SUPERIOR) Parrilla en x 1/2" 1.80 17.00 1.00 30.60 30.60
Parrilla en y 1/2" 1.50 10.00 1.00 15.00 15.00
EJE 3 / EJE C ( Z-1 ) Parrilla en x 5/8" 19.97 7.00 1.00 139.79 139.79
Parrilla en y 5/8" 1.10 101.00 1.00 111.10 111.10
TOTAL (ML) 0.00 0.00 955.94 45.60 0.00 0.00 0.00 0.00
3.973 2.235 1.55 0.994 0.888 0.56 0.395 0.25
TOTAL (KG) 0.00 0.00 1,481.71 45.33 0.00 0.00 0.00 0.00
1,527.03 1,527.03
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

02.03.02 VIGAS DE CIMENTACIN


02.03.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACIN

AUDITORIO-SALON

VIGA CIM. Izqui y Der. Corte 3-3 ACERO LONG 5/8" 1.75 4.00 2.00 7.00 7.00
ACERO LONG 1/2" 1.75 3.00 2.00 5.25 5.25
ESTRIBOS 3/8" 1.60 16.00 2.00 25.60 25.60

VIGA CIM. Izqui y Der. Corte 3-3 ACERO LONG 5/8" 2.20 4.00 2.00 8.80 8.80
ACERO LONG 1/2" 2.20 3.00 2.00 6.60 6.60
ESTRIBOS 3/8" 1.60 19.00 2.00 30.40 30.40

VIGA CIM. Izqui y Der. Corte 3-3 ACERO LONG 5/8" 2.10 4.00 2.00 8.40 8.40
ACERO LONG 1/2" 2.10 3.00 2.00 6.30 6.30
ESTRIBOS 3/8" 1.60 18.00 2.00 28.80 28.80

VIGA CIM. Izqui y Der. Corte 3-3 ACERO LONG 5/8" 2.35 4.00 2.00 9.40 9.40
ACERO LONG 1/2" 2.35 3.00 2.00 7.05 7.05
ESTRIBOS 3/8" 1.60 20.00 2.00 32.00 32.00

VIGA CIM. Izqui y Der. Corte 3-3 ACERO LONG 5/8" 2.70 4.00 2.00 10.80 10.80
ACERO LONG 1/2" 2.70 3.00 2.00 8.10 8.10
ESTRIBOS 3/8" 1.60 23.00 2.00 36.80 36.80

VIGA CIM. Izqui y Der. Corte 3-3 ACERO LONG 5/8" 2.65 4.00 2.00 10.60 10.60
ACERO LONG 1/2" 2.65 3.00 2.00 7.95 7.95
ESTRIBOS 3/8" 1.60 23.00 2.00 36.80 36.80

VIGA CIM. Izqui y Der. Corte 4-4 ACERO LONG 5/8" 1.20 4.00 2.00 4.80 4.80
ACERO LONG 1/2" 1.20 3.00 2.00 3.60 3.60
ESTRIBOS 3/8" 1.60 12.00 2.00 19.20 19.20

VIGA CIM. Izqui y Der. Corte 4-4 ACERO LONG 5/8" 1.35 4.00 2.00 5.40 5.40
ACERO LONG 1/2" 1.35 3.00 2.00 4.05 4.05
ESTRIBOS 3/8" 1.60 13.00 2.00 20.80 20.80

VIGA CIM. Izqui y Der. Corte 4-4 ACERO LONG 5/8" 1.95 4.00 2.00 7.80 7.80
ACERO LONG 1/2" 1.95 3.00 2.00 5.85 5.85
ESTRIBOS 3/8" 1.60 18.00 2.00 28.80 28.80

VIGA CIM. Izqui y Der. Corte 4-4 ACERO LONG 5/8" 2.60 4.00 2.00 10.40 10.40
ACERO LONG 1/2" 2.60 3.00 2.00 7.80 7.80
ESTRIBOS 3/8" 1.60 22.00 2.00 35.20 35.20

VIGA CIM. Izqui y Der. Corte 5-5 ACERO LONG 5/8" 2.75 4.00 2.00 11.00 11.00
ACERO LONG 1/2" 2.75 3.00 2.00 8.25 8.25
ESTRIBOS 3/8" 1.60 22.00 2.00 35.20 35.20

TOTAL (ML) 0.00 0.00 94.40 70.80 0.00 329.60 0.00 0.00
3.973 2.235 1.552 0.994 0.888 0.56 0.395 0.25
TOTAL (KG) 0.00 0.00 146.51 70.38 0.00 184.25 0.00 0.00
401.13 401.13
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)
02.03.03 COLUMNAS
02.03.03.03 ACERO FY=4200KG/CM2 GRADO 60 EN COLUMNAS

COLUMNA ( C-1 )

C 1, 0.30x0.30 ACERO LONG 5/8" 7.20 4.00 26.00 748.80 748.80


ACERO LONG 1/2" 7.20 4.00 26.00 748.80 748.80
ESTRIBOS 3/8" 1.15 54.00 26.00 1614.60 1,614.60
C 2, forma L ACERO LONG 5/8" 7.20 8.00 6.00 345.60 345.60
ACERO LONG 3/4" 7.20 4.00 6.00 172.80 172.80
ESTRIBOS 3/8" 1.62 54.00 6.00 524.88 524.88
ESTRIBOS 3/8" 2.60 54.00 6.00 842.40 842.40
C 3, forma T ACERO LONG 5/8" 7.20 18.00 2.00 259.20 259.20
ESTRIBOS 3/8" 2.92 54.00 2.00 315.36 315.36
ESTRIBOS 3/8" 1.62 54.00 2.00 174.96 174.96
C4, 0.50X0.30 ACERO LONG 5/8" 7.20 18.00 1.00 129.60 129.60
ESTRIBOS 3/8" 1.52 54.00 1.00 82.08 82.08
C5,0.15X0.50 ACERO LONG 1/2" 7.20 8.00 1.00 57.60 57.60
ESTRIBOS 3/8" 1.52 54.00 1.00 82.08 82.08

TOTAL (ML) 0.00 172.80 1,483.20 806.40 0.00 3,636.36 0.00 0.00
3.973 2.235 1.552 0.994 0.888 0.56 0.395 0.25

TOTAL (KG) 0.00 386.21 2,301.93 801.56 0.00 2,032.73 0.00 0.00
5,522.42 5,522.42
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

LONG. CANT. DE N DE 12
ITEM PARTIDA DESCRIPCION TIPO 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PAR. (ML) ELEM VECES mm
02.03 CONCRETO ARMADO
02.03.04 VIGAS
02.03.04.03 ACERO FY=4200KG/CM2 GRADO 60 EN VIGAS

AUDITORIO-SALON
PRIMER NIVEL-LADO IZQUIERDO
VA-0.30X0.35

6.42
EJE A, ENTRE 5 Y 8 ACERO LONG 5/8" 6.42 5 1.00 32.10 32.10
0.25

6.32
ACERO LONG 1/2" 6.32 1 1.00 6.32 6.32
0.20

0.075
0.35 ESTRIBOS 8mm 1.17 38 1.00 44.46 44.46
0.30

7.84
EJE 8 ENTRE A Y C ACERO LONG 5/8" 7.84 4 1.00 31.36 31.36
0.25

7.74
ACERO LONG 1/2" 7.74 2 1.00 15.48 15.48
0.20

0.075
0.35 ESTRIBOS 8mm 1.17 47 1.00 54.99 54.99

0.30

VB-0.30X0.45

5.27
EJE B, ENTRE 5 Y 8 ACERO LONG 5/8" 5.27 6 1.00 31.62 31.62
0.25

0.075
0.45 ESTRIBOS 8mm 1.50 34 1.00 51.00 51.00
0.30
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

VCH-0.30X0.20
2.17
EJE 5, ENTRE A Y B ACERO LONG 1/2" 2.17 6 1.00 13.02 13.02
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 14 1.00 14.00 14.00
0.30

6.43
EJE 7, ENTRE A Y B ACERO LONG 1/2" 6.43 6 1.00 38.58 38.58
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 40 1.00 40.00 40.00
0.30

3.17
EJE A', ENTRE 7 Y 6 ACERO LONG 1/2" 3.17 6 1.00 19.02 19.02
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 23 1.00 23.00 23.00
0.30

2.37
EJE C, ENTRE 7 Y 8 ACERO LONG 1/2" 2.37 6 1.00 14.22 14.22
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 18 1.00 18.00 18.00
0.30

7.03
EJE 4, ENTRE A Y C ACERO LONG 1/2" 7.03 6 1.00 42.18 42.18
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 42 1.00 42.00 42.00
0.30

PRIMER NIVEL-LADO DERECHO


V8-0.30X0.35
13.47
EJE 8, ENTRE K Y O ACERO LONG 5/8" 13.47 4 1.00 53.88 53.88
0.25
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)
13.37

0.20 ACERO LONG 1/2" 13.37 2 1.00 26.74 26.74

0.075
0.35 ESTRIBOS 8mm 1.17 81 1.00 94.77 94.77

0.30

6.46
EJE 5, ENTRE M Y O ACERO LONG 5/8" 6.46 4 1.00 25.84 25.84

0.25
6.36

0.20 ACERO LONG 1/2" 6.36 2 1.00 12.72 12.72

0.075
0.35 ESTRIBOS 8mm 1.17 39 1.00 45.63 45.63

0.30

6.46
EJE . ENTRE 5 Y 8 ACERO LONG 5/8" 3.57 4 1.00 14.28 14.28

0.25
6.36

0.20 ACERO LONG 1/2" 3.47 2 1.00 6.94 6.94

0.075
0.35 ESTRIBOS 8mm 1.17 38 1.00 44.46 44.46

0.30

VCH-0.30X0.20
2.17
INCLINADA, ENTRE K Y N ACERO LONG 1/2" 2.17 6 1.00 13.02 13.02
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 18 1.00 18.00 18.00

0.30

7.05
EJE 0, ENTRE 7 Y 8 ACERO LONG 1/2" 7.05 6 1.00 42.30 42.30
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 42 1.00 42.00 42.00

0.30
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

2.35
EJE K, ENTRE 8 Y 7 ACERO LONG 1/2" 2.35 6 1.00 14.10 14.10
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 18 1.00 18.00 18.00

0.30
VN-0.30X0.50
6.44
EJE N, ENTRE 5 Y 8 ACERO LONG 3/4" 6.44 2 1.00 12.88 12.88

0.25
6.34

0.20 ACERO LONG 5/8" 6.34 4 1.00 25.36 25.36

0.075
0.50 ESTRIBOS 8mm 1.60 39 1.00 62.40 62.40

0.30

VM-0.30X0.45

5.52
EJE M, ENTRE 5 Y 8 ACERO LONG 5/8" 5.52 6 1.00 33.12 33.12
0.25

0.075
0.45 ESTRIBOS 8mm 1.50 34 1.00 51.00 51.00

0.30

SEGUNDO NIVEL-LADO IZQUIERDO


VA-0.30X0.35

6.42
EJE A, ENTRE 5 Y 8 ACERO LONG 5/8" 6.42 5 1.00 32.10 32.10
0.25

6.32
ACERO LONG 1/2" 6.32 1 1.00 6.32 6.32
0.20

0.075
0.35 ESTRIBOS 8mm 1.17 38 1.00 44.46 44.46

0.30
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

7.84
EJE 8 ENTRE A Y C ACERO LONG 5/8" 7.84 4 1.00 31.36 31.36
0.25
7.74
ACERO LONG 1/2" 7.74 2 1.00 15.48 15.48
0.20

0.075
0.35 ESTRIBOS 8mm 1.17 47 1.00 54.99 54.99

0.30

VB-0.30X0.45

5.27
EJE B, ENTRE 5 Y 8 ACERO LONG 5/8" 5.27 6 1.00 31.62 31.62
0.25

0.075
0.45 ESTRIBOS 8mm 1.50 34 1.00 51.00 51.00

0.30

VCH-0.30X0.20
2.17
EJE 5, ENTRE A Y B ACERO LONG 1/2" 2.17 6 1.00 13.02 13.02
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 14 1.00 14.00 14.00

0.30
2.37
EJE C, ENTRE 7 Y 8 ACERO LONG 1/2" 2.37 6 1.00 14.22 14.22
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 18 1.00 18.00 18.00

0.30

7.03
EJE 4, ENTRE A Y C ACERO LONG 1/2" 7.03 6 1.00 42.18 42.18
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 42 1.00 42.00 42.00
0.30

SEGUNDO NIVEL-LADO DERECHO


V8-0.30X0.35
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

13.47
EJE 8, ENTRE K Y O ACERO LONG 5/8" 12.04 4 1.00 48.16 48.16

0.25
13.37

0.20 ACERO LONG 1/2" 11.94 2 1.00 23.88 23.88

0.075
0.35 ESTRIBOS 8mm 1.17 81 1.00 94.77 94.77

0.30

6.46
EJE 5, ENTRE M Y O ACERO LONG 5/8" 6.46 4 1.00 25.84 25.84

0.25
6.36

0.20 ACERO LONG 1/2" 6.36 2 1.00 12.72 12.72

0.075
0.35 ESTRIBOS 8mm 1.17 39 1.00 45.63 45.63

0.30

6.46
EJE . ENTRE 5 Y 8 ACERO LONG 5/8" 3.57 4 1.00 14.28 14.28

0.25
6.36

0.20 ACERO LONG 1/2" 3.47 2 1.00 6.94 6.94


PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

0.075
0.35 ESTRIBOS 8mm 1.17 38 1.00 44.46 44.46

0.30

VCH-0.30X0.20
2.17

INCLINADA, ENTRE K Y N ACERO LONG 1/2" 2.17 6 1.00 13.02 13.02


0.20

0.075
0.20 ESTRIBOS 8mm 1.00 18 1.00 18.00 18.00

0.30

2.35
EJE K, ENTRE 8 Y 7 ACERO LONG 1/2" 2.35 6 1.00 14.10 14.10
0.20

0.075
0.20 ESTRIBOS 8mm 1.00 18 1.00 18.00 18.00

0.30
VN-0.30X0.50
6.44
EJE N, ENTRE 5 Y 8 ACERO LONG 3/4" 6.44 2 1.00 12.88 12.88

0.25
6.34

0.20 ACERO LONG 5/8" 6.34 4 1.00 25.36 25.36

0.075
0.50 ESTRIBOS 8mm 1.60 39 1.00 62.40 62.40

0.30

VM-0.30X0.45
5.52

EJE M, ENTRE 5 Y 8 ACERO LONG 5/8" 5.52 6 1.00 33.12 33.12


0.25

0.075
0.45 ESTRIBOS 8mm 1.50 34 1.00 51.00 51.00

0.30

TOTAL (ML) 0.00 25.76 489.40 426.52 0.00 0.00 1,222.42 0.00
3.973 2.235 1.552 0.994 0.888 0.56 0.395 0.25

TOTAL (KG)
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)
TOTAL (KG) 0.00 57.57 759.55 423.96 0.00 0.00 482.86 0.00
1,723.94 1,723.94
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

LONGITUD
CANTIDAD N DE 12
PARTIDA DESCRIPCION TIPO PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
DE ELEM VECES mm
(ML)

02.03.05 LOSAS ALIGERADAS


ACERO GRADO 60 EN LOSAS ALIGERADAS
02.03.05.03

PRIMER NIVEL
Lado izquierto-almacen, sonido
BASTONES AC. NEGAT. 1/2" 2.31 6.00 1.00 14
BALANCIN AC. NEGAT. 1/2" 2.50 6.00 1.00 15
AC. POSITIVO AC. POSIT. 1/2" 7.22 6.00 1.00 43
A.T. AC. T 1/4" 2.55 46.00 1.00 117

BALANCIN AC. NEGAT. 1/2" 2.53 7.00 1.00 18


AC. POSITIVO AC. POSIT. 1/2" 2.80 7.00 1.00 20
A.T. AC. T 1/4" 2.55 12.00 1.00 31
Lado derecho-almacen, sonido
BASTONES AC. NEGAT. 1/2" 3.91 13.00 1.00 51
BALANCIN AC. NEGAT. 1/2" 4.85 13.00 1.00 63
AC. POSITIVO AC. POSIT. 1/2" 12.78 13.00 1.00 166
A.T. AC. T 1/4" 2.05 52.00 1.00 107

SEGUNDO NIVEL
Lado izquierto-almacen, sonido
BASTONES AC. NEGAT. 1/2" 2.31 13.00 1.00 30
BALANCIN AC. NEGAT. 1/2" 2.50 13.00 1.00 33
AC. POSITIVO AC. POSIT. 1/2" 7.22 13.00 1.00 94
A.T. AC. T 1/4" 2.55 46.00 1.00 117

Lado derecho-almacen, sonido


BASTONES AC. NEGAT. 1/2" 2.62 13.00 1.00 34
BALANCIN AC. NEGAT. 1/2" 4.85 13.00 1.00 63
AC. POSITIVO AC. POSIT. 1/2" 12.78 13.00 1.00 166
A.T. AC. T 1/4" 2.05 52.00 1.00 107

TOTAL (ML) 0.00 0.00 0.00 809.15 0.00 0.00 0.00 478.40
3.973 2.235 1.552 0.994 0.888 0.56 0.395 0.25

TOTAL (KG)
0.00 0.00 0.00 804.30 0.00 0.00 0.00 119.60
923.90 923.90
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)
02.03.06 PLACAS
ACERO GRADO 60 EN PLACAS
02.03.06.03

PLACA PL-04 ACERO LONG 1/2" 7.20 18.00 2.00 259.20 259.20
ESTRIBOS 3/8" 3.10 54.00 2.00 334.80 334.80
ESTRIBOS 3/8" 1.90 54.00 2.00 205.20 205.20
PLACA PL-05 ACERO LONG 1/2" 7.20 20.00 2.00 288.00 288.00
ESTRIBOS 3/8" 1.37 54.00 2.00 147.96 147.96
ESTRIBOS 3/8" 1.72 54.00 2.00 185.76 185.76
PLACA PL-06 ACERO LONG 5/8" 7.20 6.00 2.00 86.40 86.40
ACERO LONG 1/2" 7.20 16.00 2.00 230.40 230.40
ESTRIBOS 3/8" 2.48 54.00 2.00 267.84 267.84
ESTRIBOS 3/8" 1.48 54.00 2.00 159.84 159.84

PLACA PL-01 ACERO LONG 3/8" 4.17 48.00 2.00 400.32 400.32
ACERO LONG 1/2" 4.70 32.00 2.00 300.80 300.80

PLACA PL-02 ACERO LONG 3/8" 4.17 48.00 2.00 400.32 400.32
ACERO LONG 1/2" 4.70 32.00 2.00 300.80 300.80

PLACA PL-03 ACERO LONG 3/8" 2.12 48.00 2.00 203.52 203.52
ACERO LONG 1/2" 4.70 20.00 2.00 188.00 188.00

TOTAL (ML) 0.00 0.00 0.00 1,567.20 0.00 2,102.04 0.00 0.00
3.973 2.235 1.552 0.994 0.888 0.56 0.395 0.25

TOTAL (KG)
0.00 0.00 0.00 1,557.80 0.00 1,175.04 0.00 0.00
2,732.84 2,732.84
PLANILLA DE METRADOS DE ACERO

PROYECTO

SECCION :ESTRUCTURAS
MODULO ESTRUCTURAS
UBICACIN SANTA MARIA FECHA: JULIO 2017

LONGITU
CANTIDA
D N DE 12
ITEM PARTIDA DESCRIPCION TIPO D DE PARCIAL 1" 3/4" 5/8" 1/2" 3/8" 8mm 1/4" TOTAL
PARCIAL VECES mm
ELEM
(ML)

02.03.07 ESCALERAS
ACERO GRADO 60 EN ESCALERAS
02.03.07.03

ESCALERA N01
Losa superior ACERO LONG 1/2" 5.67 1.00 1.00 5.67 5.67
losa inferior ACERO LONG 1/2" 5.63 18.00 2.00 202.68 202.68
ganchos sup 1/2" 1.35 1.00 1.00 1.35 1.35
ganchos inferior 1/2" 2.05 18.00 2.00 73.80 73.80
Losa superior ACERO LONG 1/2" 1.75 23.00 1.00 40.25 40.25
losa inferior ACERO LONG 1/2" 1.75 22.00 1.00 38.50 38.50

ESCALERA N02
Losa superior ACERO LONG 1/2" 5.67 1.00 1.00 5.67 5.67
losa inferior ACERO LONG 1/2" 5.63 18.00 2.00 202.68 202.68
ganchos sup 1/2" 1.35 1.00 1.00 1.35 1.35
ganchos inferior 1/2" 2.05 18.00 2.00 73.80 73.80
Losa superior ACERO LONG 1/2" 1.10 23.00 1.00 25.30 25.30
losa inferior ACERO LONG 1/2" 1.10 22.00 1.00 24.20 24.20

TOTAL (ML) 0.00 0.00 0.00 695.25 0.00 0.00 0.00 0.00
3.973 2.235 1.552 0.994 0.888 0.56 0.395 0.25

TOTAL (KG)
0.00 0.00 0.00 691.08 0.00 0.00 0.00 0.00
691.08 691.08