OR-Notes

J E Beasley
OR-Notes are a series of introductory notes on topics that fall under the broad heading
of the field of operations research (OR). They were originally used by me in an
introductory OR course I give at Imperial College. They are now available for use by
any students and teachers interested in OR subject to the following conditions.

A full list of the topics available in OR-Notes can be found here.

Network analysis - cost/time tradeoff

One important extension to the basic network analysis technique relates to project
cost/ project time tradeoff.

In this extension to the basic method we assume that, for each activity, the completion
time can be reduced (within limits) by spending more money on the activity.
Essentially each activity now has more than one possible completion time (depending
upon how much money we are willing to spend on it).

This use of cost information is the CPM technique.

A common assumption is to say that for each activity the completion time can lie in a
range with a linear relationship holding between cost and activity completion time
within this range (as illustrated below).
Reducing an activity completion time is known as "crashing" the activity and to
illustrate this concept consider the activity on node network we had before, for which
the network diagram is reproduced below.
Introducing costs into this problem we have the package input shown below. For
activity 1, for example, the normal cost is 100 associated with a normal time of 6
weeks, and the crash cost is 240 associated with a crash time of 4 weeks.

The output from the package for this example is shown below.
The above calculation is based upon the normal times for each activity. If we were to
adopt the crash times for each and every activity we would have:
indicating that the project can take anywhere between 24 and 16 weeks depending
upon the activity completion time (which can vary between the normal time and the
crash time).

Crashing

As seen above we can have any possible project completion time between 24 and 16
weeks - but which one shall we choose? To help us answer this question let us first
consider 23 weeks, i.e. we wish to move from the normal time project duration of 24
weeks to a project duration of 23 weeks. Plainly to achieve a project completion time
of 23 weeks this we need to crash (reduce) the completion time of one (or more)
activities - but which ones?

The solution associated with 24 weeks has one critical path, namely 1-3-5-7-8-9-11.
Clearly unless we crash an activity on this critical path we can never reduce the
completion time of the entire project. Of these activities only 1, 5, 8 and 9 are capable
of being crashed:

if we were to crash activity 1 by one week we would incur an additional cost of


70
if we were to crash activity 5 by one week we would incur an additional cost of
40
if we were to crash activity 8 by one week we would incur an additional cost of
20
if we were to crash activity 9 by one week we would incur an additional cost of
40

Clearly the best choice is to crash the activity with the lowest incremental (additional)
cost - so in this case we would choose to crash activity 8 by one week at an additional
cost of 20. This will reduce the length (duration) of the critical path 1-3-5-7-8-9-11 by
one week, i.e. from 24 weeks to 23 weeks.

The new situation is:

Suppose now we wish to reduce the project by a further week, i.e. to 22 weeks.
Plainly we will adopt the same approach as before:

examine all activities in the current critical path which are capable of being
crashed
choose to crash the activity with the lowest incremental cost
This procedure works perfectly until we reach a situation in which there are two or
more critical paths. In such cases the activity with the lowest incremental cost may not
be the best choice.

For example if there are two critical paths A-E-F and B-E-F in a network and activity
A has the lowest incremental cost then crashing activity A will have no effect on the
critical path B-E-F, and hence no effect on the overall project completion time. We
would still need to crash one activity on B-E-F before we could reduce the completion
time for the entire project. In fact in this situation we would need to consider three
options:

crash both A and B by one time unit


crash E by one time unit
crash F by one time unit

to determine the best approach. Clearly once there is more than one critical path the
situation becomes more complicated. Indeed we stressed the word perfectly above.
More technically, choosing to crash the critical activity with the lowest incremental
cost is guaranteed to be an optimal approach (i.e. we crash in the best possible
way) provided we have only a single critical path. However once we encounter two
or more critical paths we cannot guarantee that we can still crash the project in an
optimal way.

Returning for the moment to our network above the solution associated with 23 weeks
has one critical path, namely 1-3-5-7-8-9-11, as before. Of these activities only 1, 5, 8
and 9 are capable of being crashed

if we were to crash activity 1 by one week we would incur an additional cost of


70
if we were to crash activity 5 by one week we would incur an additional cost of
40
if we were to crash activity 8 by one week we would incur an additional cost of
20
if we were to crash activity 9 by one week we would incur an additional cost of
40

Clearly the best choice is to crash the activity with the lowest incremental (additional)
cost - so in this case we would choose to crash activity 8 by one week at an additional
cost of 20. This will reduce the length (duration) of the critical path 1-3-5-7-8-9-11 by
one week, i.e. from 23 weeks to 22 weeks.
Hence we could continue as above, and eventually we would have crashed the
network down to its lowest possible completion time of 16 weeks.

Package crashing

Whilst you might expect that the package would crash the project in the same manner
as considered above (look at incremental costs) in fact it uses a totally different
approach. The package calculates the optimal (minimum cost) way to crash the
project using linear programming. As discussed previously we can formulate a
network problem using linear programming. This formulation can be easily modified
to deal with the problem of crashing (as will be seen later below).

The advantage of using linear programming to crash a project is that we can


automatically guarantee that, for any particular project completion time, we have
achieved that time by crashing in a minimum cost fashion. Crashing using incremental
costs may, because of the difficulty of dealing with multiple critical paths, not lead us
to a minimum cost solution for each possible project completion time.

The package output giving the cost associated with crashing the project from its
normal completion time of 24 weeks to 19 weeks (for example) is given below.
It can be seen that the minimum cost way to achieve an overall project completion
time of 19 weeks is by crashing activity 5 by one week, activity 8 by three weeks and
activity 9 by one week.

The output below shows the minimum cost way of achieving the lowest possible
overall project completion time of 16 weeks. It can be seen that this can be done for a
cost of 820. This contrasts with the cost of 870 associated with using all activities at
their crash times. The difference arises because it is not necessary to crash all
activities to their maximum extent to achieve an overall project completion time of 16
(in this case activity 2 does not need to be crashed).

By varying the number of weeks by which we crash the project we can construct the
graph shown below. In that graph we have plotted, for each possible project
completion time, the minimum cost associated with achieving that completion time.
Note here that this graph contains three distinct straight line segments (16 to 18, 18 to
21, 21 to 24). In general it is always true that the cost/time tradeoff graph contains a
number of distinct straight line segments (i.e. mathematically we would say that it is
piecewise linear). This arises because of the linear relationship that was assumed to
hold between cost and completion time for each activity.

Note there that the package merely provides information, in this case the cost of the
project for all possible completion times between 16 and 24 weeks. It does not tell you
which completion time you should choose (as you can have any completion time
between 16 and 24 weeks provided you are prepared to pay for it!). What the package
does is enable you, as the project manager, to make an informed choice about the
completion time to have.

Activity splitting

For the network considered above we have seen that the minimum possible
completion time (associated with the maximum cost) is 16 weeks. But what if we
really wanted a completion time of 15 weeks - is there any possible way of achieving
that?

The simple answer is NO, but with a caveat, not with the project as currently
represented by the network. It may be that we can change our project network,
opening up the possibility of (potentially) reducing the overall project completion
time below 16 weeks. A common approach to do this is activity splitting.

In activity splitting we (typically) examine each critical activity (since critical


activities are the determining factor in overall project completion) and see if they can
be split into two (or more) separate activities. For example, for the network
considered before we might decide that activity 1, requiring 6 weeks can be split as
below:

Here we have split this activity into 4 sub-activities 1a,1b,1c,1d (and their precedence
relationships). It can be seen that by so doing we have actually increased the time
required to complete activity 1 to 7 weeks, from the original 6 weeks. However, it
may be that this subdivision of activity 1, when considered from the cost crashing
point of view, gives us more flexibility.

For example before subdivision we could only crash activity 1 down from 6 weeks to
4 weeks. If we could now crash activity 1b by 2 weeks and activity 1c by 3 weeks
then we could crash activity 1 down from 7 weeks to 3 weeks - hence potentially
reducing the overall project duration below the 16 week barrier we previously
encountered.

Obviously the practicality of subdividing, and then crashing, critical activities depends
upon the context but the above example does illustrate that sometimes close
examination of critical activities with a view to subdivision can pay benefits.
Exploring the package

Because cost crashing can be modelled and solved via linear programming we have a
number of alternative options available, as the package illustrates. For example we
might be interested in finding the minimum time in which we can complete the project
subject to a constraint (limitation) upon the total cost. This is illustrated below using
the package for a total cost of 550.

It can be seen above that the minimum completion time subject to a cost constraint of
550 is 21.5 weeks.

The package also allows us to balance rewards in meeting a target desired project
completion time as against penalties for missing this completion time. The example
below illustrates this where the desired project completion time is 20 weeks, each
week we are late (complete after week 20) costs us 50 and each week we are early
(complete before week 20) earns us a reward of 75.
It can be seen that the optimum (least cost) completion time in this situation is 18
weeks, leading to a total minimum cost of 530.

PERT/Cost

PERT/Cost is a way of showing the budgeted project cost based on the activity start
times. The assumption behind PERT/Cost is that cost per unit of time for an activity is
constant between its start time and its finish time. For example, let us return to the
original network we had before with the original crashing data as illustrated below.
Deciding to complete the project in 18 weeks gives the output below.

The basic assumption in PERT/Cost is that the cost of an activity is spread uniformly
over its duration. So, for example, activity 1, with a suggested time of 6 costs us 100,
i.e. 100/6 = 16.67 for each week during which activity 1 is done. Activity 2, with a
suggested time of 2 costs us 100, i.e. 100/2 = 50 for each week during which activity
2 is done.

We have stressed above the weeks during which an activity is done. Whilst any
activities which are critical must be performed at precise times in order to complete
the overall project in 18 weeks is the same true of non-critical activities?

For this project with a completion time of 18 weeks the Activity Criticality Analysis is
Activity 2, for example (which requires 2 weeks) is non-critical and has a slack of 6
weeks. It can potentially be started at any time between week 0 (its earliest start time)
and week 6 (its latest start time) without affecting the overall project completion time.
If we were to start it in week 4, for example, the cost of 50 per week associated with
activity 2 would not be incurred until week 4. This may potentially be of benefit (why
incur a cost before you need to?).

In PERT/Cost we can produce a graphic (as below) showing the cost of the project

based on each activity starting at its earliest start (ES) time


based on each activity starting at its latest start (LS) time

This is shown below for the project considered above completing in 18 weeks. In that
figure the ES line is shown in purple, and the LS line in blue.
The gap between the cumulative ES and LS lines represents flexibility - cost can be
adjusted within the ES and LS limits by artificially delaying the start of non-critical
activities.

It is important to note however that artificially delaying the start of non-critical


activities (and hence incurring activity costs later) is not free. Rather it costs us.
Simply put time lost by delaying the start of an activity cannot later be regained (if
things do not turn out as planned) given the desired fixed completion time for the
overall project.

Project progress monitoring

The package contains two facilities for monitoring the progress of the project, one
with respect to time and the other with respect to cost. To illustrate these we have
expanded the input as below to include the actual cost incurred so far on each activity
and the percentage by which it has completed.
Supposing that we are using just normal times (and costs) and that it is currently week
10. Then we can get an indication of the time progress of the project by Solve Critical
Path Using Normal Times and then using Project Completion Analysis to get the
output below.

Using Project Cost Control we can get an indication of the cost progress of the project
at the same time as below.
Crashing by linear programming

Recall that previously we formulated our network problem as a linear program. To


remind you of it we briefly repeat this formulation below.

Below we repeat the network diagram for the problem we considered before.
However note that we have now added a dummy activity (12) with a completion time
of zero to represent the end of the project. This just makes the calculations we have to
do easier to follow.
In order to analyse this network by linear programming let x i (>=0) represent the time
at which we start activity i. Then the linear programming formulation of the above
network problem is

minimise x12

subject to

x3 >= x1 + 6
x4 >= x2 + 2
x5 >= x3 + 3
x6 >= x4 + 2
x7 >= x5 + 4
x7 >= x6 + 1
x8 >= x7 + 1
x9 >= x8 + 6
x10 >= x8 + 6
x11 >= x9 + 3
x11 >= x10 + 1
x12 >= x11 + 1

xi >=0 i=1,2,...,12
and note here that the activity completion times used here correspond to the normal
times for our cost crashing example.

Now to expand this formulation to include cost crashing let ci be the number of time
units (weeks in this case) by which we choose to crash (reduce) the completion time
of activity i. Recalling the problem (as below)

we have that only activities 1,2,5,8,9 can be crashed in this example so we need only
define crash variables for those activities. These crash variables must satisfy

0 <= c1 <= 2 (activity 1 can be crashed by at most 2 time units)


0 <= c2 <= 1 (activity 2 can be crashed by at most 1 time units)
0 <= c5 <= 2 (activity 5 can be crashed by at most 2 time units)
0 <= c8 <= 3 (activity 8 can be crashed by at most 3 time units)
0 <= c9 <= 1 (activity 9 can be crashed by at most 1 time units)

The key to amending the formulation is to note that wherever a completion time for an
activity appears in the formulation above it must be changed to completion time -
crash variable. Hence the first constraint x3 >= x1 + 6 which says that the start time
for activity 3 must be at least as big as the start time for activity 1 plus 6 (the
completion time for activity 1) is now changed to x3 >= x1 + 6 - c1, since the
completion time for activity 1 has effectively changed to 6-c1. Note that the cost
associated with c1 is 70c1, since each week that we crash activity 1 costs us 70.

Continuing in this vein the complete LP formulation of the problem of determining


the minimum cost way of crashing the project to achieve a given completion time T is
given by

minimise 70c1 + 50c2 + 40c5 + 20c8 + 40c9

subject to
x12 = T

x3 >= x1 + 6 - c1
x4 >= x2 + 2 - c2
x5 >= x3 + 3
x6 >= x4 + 2
x7 >= x5 + 4 - c5
x7 >= x6 + 1
x8 >= x7 + 1
x9 >= x8 + 6 - c8
x10 >= x8 + 6 - c8
x11 >= x9 + 3 - c9
x11 >= x10 + 1
x12 >= x11 + 1

0 <= c1 <= 2
0 <= c2 <= 1
0 <= c5 <= 2
0 <= c8 <= 3
0 <= c9 <= 1

xi >= 0 i=1,2,...,12

To ease the notation below we will refer to all the constraints above (excluding the
single constraint x12 = T) as the constraint set CS.

This linear program (LP) can be solved using the package as below, for T=19. The
input (in part) needed to enter the LP is:
with the solution being

This has the same additional cost of 140 as before, but has a different structure. Here
we have decided to crash activity 5 by two weeks and activity 8 by three weeks. In the
results from the package for crashing 19 weeks before we crashed activity 5 by one
week, activity 8 by three weeks and activity 9 by one week.

In fact this original structural solution can be found by using Obtain Alternative
Optimal to get
The package also had the facility to find the minimum project completion time
satisfying a cost constraint. To achieve this we simply need the LP

minimise x12

subject to the constraint set CS we had before and

70c1 + 50c2 + 40c5 + 20c8 + 40c9 <= cost limit

The package also had the facility to find the best project completion time when there
were penalties for late completion and rewards for early completion. To formulate this
let the desired completion time be D, the penalty for late completion be P per time
unit (week in this case) late, the reward for early completion be R per time unit (week
in this case) early. Note that all these are known numbers, not variables.

Then to find the best project completion time the ONLY APPROPRIATE
APPROACH is to solve two LPs. One assuming we finish "early" and the other
assuming we finish "late". Comparing the cost of the optimal solutions to these LPs
will give us the best project completion time.

This solution of two LPs as being the only appropriate approach is stressed above.
This is because it is commonly believed that the problem of finding the best project
completion time when there were penalties for late completion and rewards for early
completion can be correctly solved using just a single LP. Indeed this is the approach
used by the package. However this is simply incorrect, as the example below
illustrates.

More formally the LP associated with assuming that we finish "early" is

minimise 70c1 + 50c2 + 40c5 + 20c8 + 40c9 - R*(D - x12)


subject to the constraint set CS we had before and
x12 <= D (finish at or before the desired completion time)

Similarly the LP associated with assuming that we finish "late" is

minimise 70c1 + 50c2 + 40c5 + 20c8 + 40c9 + P*(x12 - D)


subject to the constraint set CS we had before and
x12 >= D (finish at or after the desired completion time)

With D=20, R=75 and P=50, which was the case dealt with by the package before
above, the LP for finishing early can be solved as below to give a solution with x 12=16
and cost 20 (after adjusting the cost of the LP for the constant term -R*D = -75*20 = -
1500 in this case)
The LP for finishing late can be solved as below to give a solution with x12=20 and
cost 100 (after adjusting the cost of the LP for the constant term -P*D = -50*20 = -
1000 in this case)
Hence using our two LP approach it is clear that:

finishing "early" - the best solution is to finish in 16 weeks at a cost of 20


finishing "late" - the best solution is to finish in 20 weeks at a cost of 100

Hence overall the best solution is to crash the project to complete in 16 weeks, at a
total crashing cost (after rewards for early completion) of 20. Note that in computing
this cost figure of 20 we have not accounted for the total ordinary Normal Cost (since
that must be incurred anyway) and so adding this in (total cost 500) we have that this
solution is of value 520.

Compare now the solution obtained by the package, which was of total cost 530
associated with a completion time of 18 weeks. This was obtained using the
(incorrect) single LP approach.

In fact we could have detected that the package solution was in error before now. We
actually crashed the project to 16 weeks and had an associated cost of 820. Now
finishing in 16 weeks incurs a reward of 4*75 = 300 giving a total cost of 820 - 300 =
520. The same cost as given by our correct two LP approach but contradicting the cost
of 530 given by the package using the single LP approach.
PARETO ANALYSIS STEP BY STEP

Pareto Analysis is a statistical technique in decision-making used


for the selection of a limited number of tasks that produce
significant overall effect. It uses the Pareto Principle (also known
as the 80/20 rule) the idea that by doing 20% of the work you can
generate 80% of the benefit of doing the entire job. Take quality
improvement, for example, a vast majority of problems (80%) are
produced by a few key causes (20%). This technique is also called
the vital few and the trivial many.

In the late 1940s Romanian-born American engineer and management


consultant, Joseph M. Juran suggested the principle and named it after
Italian economist Vilfredo Pareto, who observed that 80% of income in
Italy went to 20% of the population. Pareto later carried out surveys in
some other countries and found to his surprise that a similar distribution
applied.

We can apply the 80/20 rule to almost anything:


80% of customer complaints arise from 20% of your products and
services.
80% of delays in the schedule result from 20% of the possible
causes of the delays.
20% of your products and services account for 80% of your profit.
20% of your sales force produces 80% of your company revenues.
20% of a systems defects cause 80% of its problems.

The Pareto Principle has many applications in quality control. It is the


basis for the Pareto diagram, one of the key tools used in total quality
control and Six Sigma.

In PMBOK, Pareto ordering is used to guide corrective action and to help


the project team take steps to fix the problems that are causing the
greatest number of defects first.

Pareto Analysis
Here are eight steps to identifying the principal causes you should focus
on, using Pareto Analysis:

1. Create a vertical bar chart with causes on the x-axis and count
(number of occurrences) on the y-axis.
2. Arrange the bar chart in descending order of cause importance
that is, the cause with the highest count first.
3. Calculate the cumulative count for each cause in descending order.
4. Calculate the cumulative count percentage for each cause in
descending order. Percentage calculation: {Individual Cause Count}
/ {Total Causes Count}*100
5. Create a second y-axis with percentages descending in increments
of 10 from 100% to 0%.
6. Plot the cumulative count percentage of each cause on the x-axis.
7. Join the points to form a curve.
8. Draw a line at 80% on the y-axis running parallel to the x-axis. Then
drop the line at the point of intersection with the curve on the x-
axis. This point on the x-axis separates the important causes on the
left (vital few) from the less important causes on the right (trivial
many).

Figure 1: Pareto Analysis Diagram

Here is a simple example of a Pareto diagram, using sample data


showing the relative frequency of causes for errors on websites. It
enables you to see what 20% of cases are causing 80% of the problems
and where efforts should be focussed to achieve the greatest
improvement. In this case, we can see that broken links, spelling errors
and missing title tags should be the focus.

The value of the Pareto Principle for a project manager is that it reminds
you to focus on the 20% of things that matter. Of the things you do for
your project, only 20% are crucial. That 20% produces 80% of your
results. Identify, and focus on those things first, but don't entirely ignore
the remaining 80% of the causes.