A B C D F
1 SERVER/WORKSTATIONS
1.1 SCADA Server (Application)
1.2 FEP server
1.3 ISR server
1.4 Development server
1.5 Workstation with dual TFT Monitors
1.6 Development console with one TFT
Laser based Video Projection system with 2x3 Module
1.7 configuration with each module at least 70" diagonal with
common projector (Optional)
1.8 External DAT tape drive
1.9 Racks 42U- OEM
Sub Total 1
2 SWITCHES
2.1 Layer II switch (SCADA/DMS Dual LAN) (48 ports)
Sub Total 2
3 SECURITY SYSTEM (DMZ)
3.1 Web server with load balancing
Sub Total 5
6 CABLING SYSTEMS
6.1 Cable, Jacks etc
G H=F+G I= D x H J
Form: 2 RTU
S.No Equipment Unit Quantity Per Unit Cost taxes & duties
A B C D F G
1 RTUs
H=F+G I= D x H J
Form: 3 Communication system - VPN (MLLN/ MPLS) Broadband
A B C D F G H=F+G
1 Bandwidth Charges
I= D x H J
Form: 4 Auxiliary Power supply
A B C D F
1 II For RTU / Data Concentrator / Communication Eqpts.
G H=F+G I= D x H J
Form: 5 : BCPU
A B C D F G
1 Trf. Diff. Relays
H=F+G I= D x H J
Form: 6 Training
Per Unit
S.No Equipment Unit Quantity Cost
A B C D F
A Operator's Training
1 Operator for SCADA Control Centre
B Maintenance Training
1 Computer Hardware & System Software
2 RTU
3 BCPU/Relays
4 Database & display development
5 Auxiliary Power Supply
6 Communication System
GRAND TOTAL
Total Cost FMS Cost
taxes & Total Unit (Incl. taxes for 01
duties Cost & duties) year
G H=F+G I= D x H J
Form: 7 FMS
S.No. Equipment FMS Cost
A B C
1 FMS charges for Control Center (Form 1) for 01 year
2 FMS charges for RTU (Form 2) for 01 year
3 FMS charges for Aux. Power Supply (Form 4) for 01 year
4 FMS charges for Relays (Form 5) for 01 year
Grand Total
Form: 8 Total
S.No. Equipment
A B
1 Total Cost for Control Center (Form 1)
2 Total Cost for RTU (Form 2)
3 Total Cost for Communication (Form 3)
4 Total Cost for Aux. Power Supply (Form 4)
5 Total Cost for Relays (Form 5)
6 Total Cost for Training (Form 6)
7 FMS charges for Control Center (Form 1) for 3 years
8 FMS charges for RTU (Form 2) for 3 years
9 FMS charges for Aux. Power Supply (Form 4) for 3 years
10 FMS charges for Relays (Form 5) for 3 years
11 FMS charges for Control Center (Form 1) for additonal 2 years (Optional)*
12 FMS charges for RTU (Form 2) for additonal 2 years (Optional)*
13 FMS charges for Aux. Power Supply (Form 4) for additonal 2 years (Optional)*
* - Initially the FMS will be for 3 years after 1 year warranty period, however FMS may be extended further for 2-3 y
mutual agreement between Utility & Vendor.
Note:-
The rates are invited for entering into an RC valid for one year from the date of issue of contract. Prices are to be q
mentioned above are for evaluation purposes only. Actual Quantities may vary as per site requirement and Release
be
Theplaced
quoted accordingly.
rates must be inclusive of all taxes as applicable at the time of bidding.
Bidders are to quote their rates strictly as per above format.
Total Duration for 3 Years + 2 Total Cost
years (Optional) years after for 3 years
warranty
C D
ver FMS may be extended further for 2-3 years on same terms and conditions on