Node Node (day) Float Path Milestone 1 Concept Phase A Find several suitable location for bridge 1 2 2 0 0 2 2 0 C B Determine the client scope and requirement 2 3 14 2 2 16 16 0 C C Community Engagement (Public Consultation) 3 4 7 16 16 23 23 0 C D Produce Project Proposal 4 6 7 23 23 30 30 0 C E Develop option analysis and recommendation 4 5 7 23 23 30 30 0 C F Finalization of conceptual design 6 7 14 30 30 44 44 0 C Milestone 2 Project Proposal G Propose the conceptual design to stakeholders 7 8 14 44 44 58 58 0 C H Seek for permits and approval required 8 10 30 58 58 88 88 0 C I Tender invitation for contractor 8 9 14 58 74 72 88 16 NC J Review of tender design and time frame 10 11 14 88 88 102 102 0 C Milestone 3 Site Investigation K Site Hoarding and Logistic work 11 12 30 102 102 132 132 0 C L Levelling survey 12 13 30 132 162 162 192 30 NC M Geotechnical Investigation and Analysis 12 14 60 132 132 192 192 0 C N Environmental management and Risk Analysis 12 15 30 132 162 162 192 30 NC Milestone 4 Foundation O Landscaping (cut and fill) 14 16 30 192 192 222 222 0 C P Setting out by surveyor 16 18 180 222 222 402 402 0 C Q Setup Cofferdam (casing underwater) 16 17 30 222 222 252 252 0 C R Foundation for abutment & pier 17 18 150 252 252 402 402 0 C Milestone 5 Bridge Construction S Setting out by surveyor 18 20 270 402 402 672 672 0 C T Construction of tower 18 19 60 402 402 462 462 0 C U Stay cable and deck construction 19 20 210 462 462 672 672 0 C Milestone 6 Road Construction V Landscaping 20 21 30 672 672 702 702 0 C W Setting out by surveyor 21 24 180 702 702 882 882 0 C X Foundation for elevated road 21 22 30 702 702 732 732 0 C Y Column, column cap and concrete girder construction 22 23 90 732 732 822 822 0 C Z Precast slab + road construction 23 24 60 822 822 882 882 0 C Milestone 7 Finalization AA Lighting, electrical installation and drainage system 24 25 20 882 892 902 912 10 NC AB Steel protection coat and painting 24 27 30 882 882 912 912 0 C AC Traffic signs & Road marking 24 26 7 882 905 889 912 23 NC Milestone 8 Handover AD Safety inspection & System check 27 28 14 912 912 926 926 0 C AE Construction site cleaning 28 29 7 926 926 933 933 0 C AF Handover to stakeholders 29 30 7 933 933 940 940 0 C