Start End Duration Total Critical

Task name EST LST EFT LFT


Node Node (day) Float Path
Milestone 1 Concept Phase
A Find several suitable location for bridge 1 2 2 0 0 2 2 0 C
B Determine the client scope and requirement 2 3 14 2 2 16 16 0 C
C Community Engagement (Public Consultation) 3 4 7 16 16 23 23 0 C
D Produce Project Proposal 4 6 7 23 23 30 30 0 C
E Develop option analysis and recommendation 4 5 7 23 23 30 30 0 C
F Finalization of conceptual design 6 7 14 30 30 44 44 0 C
Milestone 2 Project Proposal
G Propose the conceptual design to stakeholders 7 8 14 44 44 58 58 0 C
H Seek for permits and approval required 8 10 30 58 58 88 88 0 C
I Tender invitation for contractor 8 9 14 58 74 72 88 16 NC
J Review of tender design and time frame 10 11 14 88 88 102 102 0 C
Milestone 3 Site Investigation
K Site Hoarding and Logistic work 11 12 30 102 102 132 132 0 C
L Levelling survey 12 13 30 132 162 162 192 30 NC
M Geotechnical Investigation and Analysis 12 14 60 132 132 192 192 0 C
N Environmental management and Risk Analysis 12 15 30 132 162 162 192 30 NC
Milestone 4 Foundation
O Landscaping (cut and fill) 14 16 30 192 192 222 222 0 C
P Setting out by surveyor 16 18 180 222 222 402 402 0 C
Q Setup Cofferdam (casing underwater) 16 17 30 222 222 252 252 0 C
R Foundation for abutment & pier 17 18 150 252 252 402 402 0 C
Milestone 5 Bridge Construction
S Setting out by surveyor 18 20 270 402 402 672 672 0 C
T Construction of tower 18 19 60 402 402 462 462 0 C
U Stay cable and deck construction 19 20 210 462 462 672 672 0 C
Milestone 6 Road Construction
V Landscaping 20 21 30 672 672 702 702 0 C
W Setting out by surveyor 21 24 180 702 702 882 882 0 C
X Foundation for elevated road 21 22 30 702 702 732 732 0 C
Y Column, column cap and concrete girder construction 22 23 90 732 732 822 822 0 C
Z Precast slab + road construction 23 24 60 822 822 882 882 0 C
Milestone 7 Finalization
AA Lighting, electrical installation and drainage system 24 25 20 882 892 902 912 10 NC
AB Steel protection coat and painting 24 27 30 882 882 912 912 0 C
AC Traffic signs & Road marking 24 26 7 882 905 889 912 23 NC
Milestone 8 Handover
AD Safety inspection & System check 27 28 14 912 912 926 926 0 C
AE Construction site cleaning 28 29 7 926 926 933 933 0 C
AF Handover to stakeholders 29 30 7 933 933 940 940 0 C