Dasar Perancangan :
V bak = Q x tr V bak = A x h
= 14 m3/hari x 0,33 hari 5,06 m3 = A x 1 m
= 4,6 m3 A = 5,06 m2
V= 4,6 m3 x 1,1 = 5,06 m3
= 280 kg
= 0,56 m3 A = 1,232 m2
= 196 kg
= 19,6 m3 A = 4,3 m2
= 2,04 m3 A = 2,24 m2
Q = 9,8 m3/hari
= 137,2 kg
Waktu tinggal = 15-30 hari; depth = 1 m; Organic loading = 0,05-0,25 kg/hari/m3
= 548,8m3
tr = 80 hari 274,4 m3 = A x 1 m
V masing-masing = 274,4 m3
= 123,48 kg
Kolam aerasi:
Depth: 1 m ; Organic loading: 25-335 kg BOD/hari/ha ; tr: 5-20 hari ; BOD Removal: 80-
85%
Q = 9,8 m3/hari
= 1,56 kg/hari
Kebutuhan lahan = (1,56 kg BOD/hari)/( 310 kg BOD/hari/ha )
= 0,005 ha
= 50 m2
= 50 m2 x 2 m A = 50 m2
V = 100 m3
OFR = 10 m3/hari/m2
Q = 9,8 m3/hari
A = Q/OFR V = Axh
A = 0,98 m2 h = 1,375 m
V = Q x tr
= 1,225 m3
V = 1,225 m3 x 1,1
V = 1,3475 m3