You are on page 1of 5

WORKDONE

CONTRACT Previous Current


Item Descriptions Unit Quantities Rate (RM) Amount (RM) Quantities Amount (RM) Quantities

WIDENING OF EXISTING ROAD FOR


TEMPORARY ACCESS ROAD TO SITE

Supply of labour, machineries, equipment and small tools


for the following works:

A Laying, levelling and compacting of 200mm thick Grade m2 4,907 17.60 86,363.20 - 1,097.25
30 Concrete on prepared road-base including formwork
and treatment of joints between existing and new road
including provision of contraction, expansion,
construction, longitudinal joints and joint filler.

B Laying of one layer of mesh reinforcement BRC A9. m2 4,907 3.00 14,721.00 - 1,097.25

C Construct and complete 900mm diameter precast m 4 80.00 320.00 - -


reinforced concrete pipe culvert (RCP) Class "H" with
aggregate surround.

D Construct and complete 900mm (W) x 900mm (D) m 130 70.00 9,100.00 - -
precast reinforced concrete u-drain including 50mm thick
of lean concrete Grade 10, 100mm thick hardcore base
and all necessary excavation, backfilling and disposal of
excavated material.

E Construct and complete 2000mm (W) x 2000mm (L) x no. 1 1,355.80 1,355.80 - -
1500mm (D) reinforced concrete sump constructed of
Grade 30 concrete wall and slab, on Grade 10 concrete
blinding complete with hinged hot dipped galvanised
mild steel grating and galvanised step irons all necessary
excavation, backfilling and disposal of excavated
material.
F Workers accomodation L.S. - - inclusive inclusive

Note :-

The following machineries are to be provided by the


Main Contractor :-
(i) Excavator
(ii) Backhoe
(iii) Crane
(iv) Lorries

SUB-CONTRACT SUM (RM) 111,860.00 -


WORKDONE
Current To-Date
Amount (RM) Quantities Amount (RM)

19,311.60 1,097.25 19,311.60

3,291.75 1,097.25 3,291.75

- -

- -

- -
inclusive inclusive

22,603.35 22,603.35
Workdone Measurement

Length Width Height Factor 1 Area Remarks


(m) (m) (m) (m2)

1 Slab 192.50 5.70 1,097.25


2 BRC 192.50 5.70 1,097.25