You are on page 1of 355

CHAPTER 1: Introduction

CHAPTER ONE

GENERAL INTRODUCTION

1.1. GENERAL

The stability and improvement of underground excavation and surface slopes mining

during and after the excavation is a big concern to designers as any kind of instability

may result in damage to the environment, high cost in repair work as well as time

consumption. The forms of instability and their mechanism and the factors and

conditions associated with them must be clearly understood so that a correct way to

the stabilisation and reinforcement of the structure can be undertaken. Rock

reinforcement is a specific technique with in the general category of rock

improvement methods. And rock improvement concludes all techniques which

looking for increasing the strength or decreasing the deformability characteristics of

a rock mass. Rock mass stabilisation by bolting has now been used for more than a

century all over the world (Snyder 1983). In civil and mining engineering projects

various kinds of rock bolt; mechanically, grouted, anchored, are recently considered

one of the principal support members in rock structure.

Rock bolting in various types has been used as early as the nineteenth century. An

early use of bolts in a coal mine reported in 1918 in Germany (Lang et al 1979). The

bolt was made out of wood and used preventing small pieces of rock from falling

between the face and the main support system. Palmer and et al (1976) evaluated

limiting displacement as the key parameter of the bolting action.

1
CHAPTER 1: Introduction

In the past, because of the lack of understanding on the behaviour of rock mass and

rock bolt as well as their complicate interaction, the use of rock bolt was not

developed like today. However, in the recent years, the range of using of rock bolt

systems has been extended both in mining and civil structures and has been become a

dominant measure for rock support in mining engineering. This is because of

advances made in the understanding of bolt failure as well as the improvement

attained in strata control technology. To decrease roof failure of a mine fully grouted

bolts are used more than mechanically anchored bolts, it is due to fully grouted bolts

have greater area of anchorage capacity. The majority of the 100 million roof bolts

installed each year in the United States are fully grouted resin bolt (Maleki 1992).

They can create the great reinforcement on rock walls around underground

excavation and also are very effective in closely jointed rocks and in soft rocks. Rock

reinforcement system will increase the factor of safety against crack initiation, and

will influence the orientation of critical existing crack. The idea of a resin

reinforcement system leads directly to the load transfer of the load from unstable

rock through the reinforcement system to stable rock. The reinforcement system and

load transfer concepts have been used to define three fundamental types of

reinforcement system (Windsor and Thomson 1993):

1-Continous mechanically coupled (CMC) systems,

2-Continious frictionally coupled (CFC) systems and

3-Discretly mechanically or frictionally coupled (DMFC) system.

The load transfer between the rock bolt and the borehole is dependent on some

parameters such as borehole dimeter, annulus thickness, bolt profile and so on .In a

fully grouted rock bolt, the load transfer mechanism is dependent on the shear stress

2
CHAPTER 1: Introduction

attained on the interfaces of bolt-resin and resin rock. The shear stress capability of

the interfaces and the rate of shear stress generation determine the response of the

bolts to the strata behaviour. The researches on rock bolts, gained momentum

following the introduction of new Austria tunnelling method (NATM) in the early

sixties and since its introduction more than 30 years ago, resin grouting has

significantly improved the effectiveness of roof bolting and this process is

continuing. Many researchers have worked on application of fully grouted rock bolts

both theoretically and experimentally, but a little research has become on load

transfer mechanism. Littlejohn and Bruce (1975) conducted the first systematic study

on the failure of rock bolt system and suggested three modes of failure of rock bolts

system include:

- Failure of rock mass,

- Failure of rock bolt and

- Failure of bolt-grout-rock interface.

Hollingshead (1971), Pells (1974), Farmer (1975), Xueyi (1983), Aydan et al (1985),

Serbousek and Singer, (1987), Aydan (1989), Singer (1990), Hyett et al. (1992),

Skybey (1992), Gray et al. (1998) Li and Stillborg (1999), Fabyznchic et al. (1992,

1998), Thompson and Finn (2001), Kilic and et al. (2002, 2003), Aziz (2003),

Ivanovic (2003) and Campbell and Mould (2005) carried out the theoretical and the

experimental approaches to define the bolt behaviour under axial loading conditions.

They tried to describe the bolt/grout/rock interaction under axial loading conditions.

In majorities of the above research, the bolt profile was ignored.

In case of bolt bending behaviour and the load transfer mechanism subjected to

lateral loading conditions, following researchers carried out the analytical and

3
CHAPTER 1: Introduction

experimental study. Dulascka (1972) then Bjurstrom (1974), Haas (1976,1981),

Azuar (1977), Hibino and Motojima (1981), Egger and Fernands (1983) and Ludvig

(1983), Gerard (1983), Dight (1982), Bjornfot & Stephansson (1983), Larsson

(1983), Schubert (1984), Yoshinaka et al. (1987), Spang and Egger, (1990), Stillberg

(1994), Holmberg (1992), Egger and Zabuski (1991), Ferrero (1995), Pellet and

Egger (1995), Goris et al. (1996), Grasselli (2005) and Mahoni et al (2005). All

experimental testing of grouted bolts were performed as a single shear test without

applying tensile loads on the bolt. However, in some research, only confining

pressure on the moving block was applied.

To the best of authors knowledge, no suitable literature was available at the time of

writing this thesis to report on the effect of bolt profile on bending behaviour of

perpendicular bolts to the joints and also the effect of pretensioning in this situation.

1.2. BACKGROUND FOR PRESENT RESEARCH

The present research including; laboratory tests, numerical design, field tests and

some theoretical design, by the author was carried out because of following reasons:

1- Load transfer capacity of bolt types in particular with different profiles and

ribs has not been evaluated before.

2- All previous shear tests have been carried out by single shear test, giving

difficulties in shear joint due to non-equilibrium situation and un-uniformity

distributed load on shear joint (twisting due to movement) So, new method is

designed in present research. Due to virtue of symmetry, no moment in the

moving block can be induced, while such forces undoubtedly are available in

single shear apparatus, which were used so far.

4
CHAPTER 1: Introduction

3- No shear test and failure mechanism have been reported yet on high strength

steel, which are main applicable bolts in Australia and all around the world.

4- There was lake of understanding in axial and shear behaviour and load

transfer of bolts and also some ambiguous reports in their failure mechanism.

5- New available high strength steel bolts in market have not previously

importantly tested.

6- There is lack of quality data available on the exact nature of fully grouted bolt

under shearing, subjected to pretensioning.

7- There are no reported results in case of diversity of resin thickness and

quantitative significance of shear resistance mechanism in different

surrounding rock strengths.

8- There is no reported result in load transfer mechanism subjected to axial

loading, regarding different bolt profile such as rib height and rib spacing.

9- There is no valuable numerical design in both axial and shear behaviour of

the bolts, especially in profile behaviour and bolt/grout/concrete contact

interfaces.

1.3. KEY OBJECTIVE

1- The evaluating of the shear behaviour mechanism in bolt-grout and grout-

rock interfaces both in the laboratory and field,

2- To design and develop a shear testing machine which meets and removes the

relevant problems in previous machines,

3- The study of the load transfer capacity in bolt-grout-rock interface both field

and laboratory, in different Types of bolts,

5
CHAPTER 1: Introduction

4- The effect of resin thickness on shear behaviour of bolts and load transfer

evaluation, subjected to axial and shear behaviour,

5- The effect of rock strength on bending behaviour of bolts,

6- The effect of bolt pretensioning on shear behaviour and load transfer

mechanism,

7- The effect of bolt profile and thread rebar specifications on load transfer

under various level of pretensioning and different strength surrounding

materials.

8- To better understanding the exact nature and quantitative significant of load

transfer mechanism for shear resistance,

9- The evaluation of rib height and rib spacing and resin thickness in different

bolt profile on load transfer mechanism subjected to axial loading,

10- Numerical design of bolt/ joint/ concrete and contact elements in both axial

and lateral applied loads and

11- The verification of results by numerical simulation.

1.4. RESEARCH METHODOLOGY

The laboratory tests and numerical modelling were chosen as the main methods for

this research project. DSS (Double shearing system) was used for laboratory tests

subjected to bolt bending behaviour, pull and push tests were used to define load

transfer mechanism subjected to axial loading conditions and 3D finite element

program, Ansys, was used to find the stress-strain behaviour in bolt-grout-concrete,

bolt/grout and grout/concrete interfaces and their interactions, which have not been

considered in previous researches.

6
CHAPTER 1: Introduction

1.5. SCOP OF THE THESIS

In spite of many research including theoretically and experimentally on bond

strength of fully grouted rock bolts have been done, still lack of understanding of

load transfer mechanism on fully resin grouted bolts is recognised. In other words the

lack of published results on bolt bending behaviour in different bolt profile

characteristics and surrounding materials in various pretension loads, writer of the

thesis seeking the method to evaluate the load transfer under both axial and lateral

loading conditions. This thesis consists of 10 chapters. The flowchart of the

arrangement of the thesis is shown in Figure 1.1.

7
CHAPTER 1: Introduction

CHAPTER ONE
INTRODUCTION

CHAPTER TWO
ROCKBOLT SYSTEM AND REVIEW OF BOLT BEHAVIOUR UNDER AXIAL LOADING

CHAPTER THREE
REVIEW OF SHEAR BEHAVIOUR OF BOLTS AND MECHANICAL PROPERTIES OF
THE MATERIAL USED

CHAPTER FOUR
FAILURE MECHANISM OF BOLT RESIN INTERFACE SUBJECTED TO AXIAL LOAD

CHAPTER FIVE
DOUBLE SHEARING OF BOLTS ACROSS JOINTS

CHAPTER SIX
ROLE OF BOLT ANNULUS THICKNESS ON BOLT SHEARING

CHAPTER SEVEN
NUMERICAL DESIGN IN FULLY GROUTED ROCK BOLTS

CHAPTER EIGHT
ANALYTICAL BEHAVIOUR OF FUULY GROUTED BOLT

CHAPTER NINE
FIELD INVESTIGATION

CHAPTER TEN
CONCLUSION AND RECOMMENDATION

Figure 1. 1. Structure of Chapters in the thesis

Chapter 1 presents the general purpose of the research, background of the

research in field of rock bolt and methodology of the research and key

objectives.

8
CHAPTER 1: Introduction

Chapter 2 includes the general knowledge of the rock bolt system, rock bolts

application and reinforcement mechanism in particular fully grouted rock bolt

and the advantages of this type of bolt. And also highlights the bolt theories,

rock bolt types and their descriptions. Moreover, it gives a brief view of the

bolt behaviour and load transfer mechanism subjected to axial loading

conditions in both analytical and experimental methods.

Chapter 3 deals with the brief view of the bolt bending behaviour subjected to

lateral loading conditions both theoretically and experimentally. In additions,

it evaluates the mechanical and physical properties of the material used such

as; bolt, grout and concrete.

Chapter 4 describes the load transfer mechanism when bolt axially is loaded.

And also different types of bolts in terms of different profile characteristics in

both pull and push tests are discussed.

Chapter 5 deals with shear behaviour of bolts across joints. It describes the

experimental procedure and double shearing system. Six different types of

bolts in terms of mechanical and physical characteristics and three material

strengths; 20, 40 and 100 MPa were considered to evaluate the load transfer

mechanism under various pretension loads, 0, 5, 10, 20, 50 and 80 kN.

Chapter 6 describes effect of the resin thickness on bolt shear performance.

For this reason, tests are carried out on the same type of bolt, pretension load

and the concrete strength.

Chapter 7 gives a brief view of finite element application in rock bolt. In

addition, it presents the validation of the numerical modelling results with the

laboratory results. 32 models are created to define the effect of concrete

strength, resin thickness, different pretension loads on the load built up along

9
CHAPTER 1: Introduction

the bolt, grout and concrete during the shearing process. Moreover, the stress,

strain developed along the bolt subjected to the axial behaviour are discussed

in this chapter.

Chapter 8 deals with a brief review of the analytical methods of the bolt

bending behaviour and prediction of the hinge point location in both elastic

and plastic condition. In addition, the axial load distribution along the elastic

bolt installed in elasto plastic rock mass in a circular tunnel is evaluated

numerically. A program was written for this reason. It was tried to use the

material properties of the Metropolitan colliery mine in the model.

Chapter 9 illustrates the fieldwork description. Two different bolt types,

which are considered in experimental work, selected for field investigation

practically. They were instrumented by 18 strain gauges in both sides of the

bolt along the 2.1 m bolt length. During several months the bolt monitoring

was carried out and load distribution along the bolt was recorded.

Chapter 10 summarise the results and principal conclusions of the research

work presented in this thesis and the recommendations for further research.

10
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

CHAPTER TWO
ROCK BOLT SYSTEM AND REVIEW OF BOLT
BEHAVIOUR UNDER AXIAL LOADING

2.1. INTRODUCTION

This chapter concludes two main parts; first, general description of rock bolts,

particularly fully grouted rock bolts and then followed by the review of the bolt

behaviour subjected to axial loading conditions.

Rock bolting technology has advanced rapidly during the past three decades due to

better understanding of load transfer mechanisms and advances made in bolt system

technology. Bolts are used both as temporary and permeant support systems, in

tunnelling and mining operations. In surface mining they are used for slope stability

operations and in underground working in a variety of purposes, which include

roadway development, shaft sinking and stoping operations. Rock bolts are basically

installed to prevent the movement of discontinuity planes, depending upon the

direction of installation and nature of discontinuity surface. Bolts provide a tensile

effect to transfer the load from one side to another when relative strata layer

movement takes place with separation. Basically rock bolts provide a reinforcement

zone in rock mass and the main aim of rock reinforcement is to make greater use of

inherent rock mass strength to enable the rock media to support themselves.

2.2. HISTORICAL

The application of bolts as a mean of ground control was first reported in 1918 in a

coal mine in Germany (Lang.T.A et al. 1979). In the united kingdoms the earliest

reporting came from the slate quarry located in North Wales in 1872 (Schach et al

11
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

1979). Bolstad and Hill (1983) reported the use of mechanical rock bolt in a metal

mine in the United States (1927). However, the development of rock bolting as a

practical and economical technology began with the Norwegian in the late 1940s.

To reduce the number of fatal accidents caused by roof falls, the U.S Bureau of

Mines (USBM) begun the use of roof bolting technology in 1947. The use of rock

bolt was significantly spread throughout of U.S., which by 1952; the annual roof bolt

consumption had reached 25 million. The practices of rock bolting technology for

Australian condition took place with the snowy mountain hydroelectric Scheme

(1949-1969). It was during this period that the use of grouted rock bolts for

permanent reinforcement was pioneered.

2.2.1. History of bolting Australian mines

In Australia the application of roof bolting in conjunction with normal timber support

was reported from Elrington Colliery, New South Wales in 1949. This was soon

turned into fully scale bolting operation that mine in April 1950 (Gardner 1971).

Since 1983, bolts have become the main method of support in most of the

underground openings in Australia mines. Near 5 million of different bolt type are

installed in the Australia mining industry per year.

2.3. ROOF BOLT PRACTICE AND APPLICATION

Nowadays, the application of rock bolts for ground reinforcement and stabilisation is

of worldwide scale, and the level of bolt usage has contributed to increased

variations in design and purpose. In the US coal mines, every year around 15000 km

entries are excavated and about 100 million roof bolts are installed in these entries

(Yassein et al 2004). Similarly the application of Hundreds of million of units are

12
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

installed each year in Australia, and a recent survey revealed that the worldwide

usage of rock bolts was in excess of 500,000,000 annually (Windsor, 1997). Figure

2.1 displays the usage of rock bolts in the past decades in the coal mining industry

(Junlu 1999). Rock bolts are installed as an active support system, as they are loaded

from the time of installation. This is achieved by the pretensioning process. Bolt

pretensioning can clamp individual bedding planes together and closes the small gaps

that might have occurred due to sagging after excavation. Pretensioning of the fully

grouted bolt can create much higher level of active support than the point anchored

bolts such as the mechanically anchored bolts.


Number of bolts consumed in million

120

100

80

60

40

20

0
1920 1930 1940 1950 1960 1970 1980 1990 2000

Year

Figure 2. 1. Usage of rock bolts in the world

2.4. REINFORCEMENT MECHANISM

The main aim of rock reinforcement is to make greater use of inherent rock mass

strength to enable the rock media to support themselves (Biniawski 1984). Rock

reinforcement depends upon the type of rock bolt and anchorage system. The rock-

bolt interaction is affected by the rock type, strata lithology and encapsulation

13
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

characteristics. The development of the load on the bolt or a section of its length is

affected by the strata lithology with other parameters being equal.

Rock mass in general is insufficiently strong in tension or in shear. These properties

can be strengthened by bolting. Supporting of the ground with bolts allows the

application of compression to the strata, which will aid to increase the shear and

tension resistance through effective binding of the strata layers. The increase of these

strengths can thus be achieved by the friction effect. Another mechanism of bolt

reinforcement is by beam composite action.

2.5. BOLT THEORIES

Table 2.1 lists the various theories proposed for ground support using rock bolts. As

can be seen from the Table 2.1, the selection of any prosed theory is dependent upon

the methodology of bolt application and the geological conditions. The proposed

terminology used fro each theory is influence by the geological conditions; normally

the suspension theory is dead weight transfer of the lowered and separated beds to

the upper and stronger and commitment beds. Full column grouted bolts reinforce the

bedded roof strata by resisting slip along bedding planes (Stimpson 1983).

14
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading
Table 2. 1 Bolt theories

Theory Description Shape Comments Reference


The dead weight load of the strata
transferred between the bolt head and The upper layer should
the anchor. be strong enough to Peng (1984)
Suspension anchre the bolts Stillborg
(1986)

Bolts bind the strata layers together, The tensile failure is


which prevents or greatly reduce the prevented because of Peng (1984)
movements. The frictional effect the increase in binding Panek
generated by bolt pretensioning strength and stiffness (1956) Xiu
increases the shear strength between effect However, failure (1997)
Beam b a
the layers, may still occur by Snyder
building shearing at the two (1983)
ends. Hence bolts a Stillborg
and b are most 1986)
effective in this method.
When the roof strata are highly
fractured and blocky, or planes of Confinement is
weakness intersect the immediate provided by way of
roof strata, keying effect roof support tensioned roof bolts,
Keying may be used. Roof bolting provides and then the strata Peng (1986)
effect significant frictional forces along material will be locked
fractures, cracks, and weak planes or keyed together.

The main aim of the arching theory is


to increase the value of compressive To support the
stresses in the roof so that the tensile weakened zones Wagner
stress is ignored and the shear between bolts, the use (1997)
Arching resistance increased. Arching of wire mesh and
Action provides very strong roof profile, shotcrete is
which is one of the strongest roof recommended
profiles

15
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

2.6. TYPE OF ROCK BOLTS

Rock bolts are classified into three main groups, according to their anchorage

systems Hoek and Wood, (1988) and Franklin and Dusseault (1989). Table 2.2

shows the types of rock bolts presented preliminary by Peng (1984). The first group

is the mechanically anchored rock bolts that can be anchored by a slit and wedge

mechanism or an expansion shell. The second group is the friction anchored rock

bolts, split set and swellex. The third group is the fully grouted rock bolts that can be

anchored by cement or resin. Table 2.2 and Table 2.3 show the different type of rock

bolts and their accessaries respectively.

16
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

Table 2.2. Bolt types and description


Table 2.2 Descriptions of
Types of Types of Capacity
Applicability Advantages Disadvantages Typical diagram
bolts anchor (t)
Slot and wedge Inexpensive Limited to use

Hard rock
Immediate in soft rock
Expansion shell
support condition
Point
anchored Resin grout Universal 10-16 possible Long-term
bolts High capacity stability is
(tensioned in hard rocks. affected by
Combination slippage.
Most strata
anchor[NIA1]

Cement -High corrosion -Shrinkage of


resistance cement, longer
Injection Most strata - Durable setting time
Cartridge - Consistent. -Installation is
Fully length
Resin -Increased use time critical
grouted bolt
recently -Costlier than
(untensioned)
15-25 specially for mechanical bolt.
Injection All strata weak rocks
Cartridge

Seedsman
(2005)

17
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

Table 2.2 Continued

Types of Types of Capacity


Applicability Advantages Disadvantages Typical diagram
bolts anchor (t)
Suitable at This Type of
intersection and support should be
Roof truss Expansion shell Adverse roof
high pressure used if bolt are not
area pretensioned
Flexible
Same as Special procedure
Bulb grouted bolt has to apply for
Grouted Universal Up to 50
-Capability up tensioning
Cable ton
to 15 m
Heiten

Cheap, Simple - Relatively


installation expensive
Split set Weak to - Capability of - Hole diameter is
Friction moderate strata 10-14 large critical for installation
Swellex displacement -Not very
-Reusable. corrosion resistive.

Does not Only drill bit


Threaded prevent rotary
Weak to Up to33 mucking up
Fibre Resin Anchor
moderate strata ton
glass

18
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading

Table 2.2 Continued Table 2.2 Continued

Types of Type of Applicabi


Capacity (t) Advantages Disadvantages Typical diagram
bolts anchor lity
Helical rock Fully 0.92tone/in HRB can be Needs
bolt (Giralo grouted / Weak rock implemented modification to
2005) point with any size, the bolter
anchored grade and hydrulic system
length of bar

Hilti onestep Resin Weak to >20 t Faster bolt Limitation of bolt


bolt anchor moderate installation- length-
www.Hilti.com rocks increased Higher price
working compar
safety

Cone bolt (Big Resin Rock burst Up to 20 t Easy to The preformance


Bell1999) anchor zone install- heavily dependes
Effective even on grout
in high specifications
deformation
Posimix 4 Resin Moderate Up to 12.5 t Constant -Spin torque for
(Mikula 2004) anchor strengths annulus mixing resin is
high
-Spring can catch
on mesh during
insertion

19
CHAPTER 2: Rock bolt system and review of bolt behaviour under axial loading
Table 2.3. Bolt accessories
Accessories Usage Diagram Comments

Face plate To uniformly distribute the load at bolt Used with all types of bolt.

collar. Dome shape is the most


common.

Anti friction To reduce the friction between the nut Increases the torque-tension

washer and faceplate. ratio. Common for all bolt


types.

Nuts and Common for all bolt types

spherical To prevent the bolt from pulling and

seats applying pretension load

W-strap Pulled into rock surface by the bolt to Provide a large surface

conform major irregularities. confinement to any loose rock


between bolts.

Wire mesh To prevent injury to personnel and Used right up to the face to

damage to equipment from small avoid any accident at intervals


between 1 to 1.5 m.
pieces of rock or spalled flakes.
welded Chainlink

20
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

2.7. LOAD TRANSFER IN ROCK BOLTS

The performance of any reinforcement system is limited by the efficiency of load

transfer. Basically the load transfer process begins when the movement of a block of

rock reinforced has occurred. The concept of the load transfer is composed of three

basic mechanisms; Stille (1992) and Windsor (2004).

i. Rock movement, which requires load transfer from the unstable rock to the

reinforcing element.

ii. Transfer of load via reinforcing element from the unstable zone to a stable

zone.

iii. Transfer of the reinforcing element load to the stable rock mass.

There are a wide variety of methods by which the load transfer between the rock and

reinforcing element may be achieved and many reinforcing devices have been

developed.

Fabjanczyk and Tarrant (1992) identified load transfer as a mechanism by which

force is generated and sustained by a supporting tendon as a consequence of strata

deformation Windsor (1996, 97), Windsor and Thomson (1993, 1996) refined this

concept as the transfer of load from unstable rock within the reinforcement system to

stable rock. They classified the current reinforcement devices into three groups:

-Continuous mechanically coupled (CMC),

-Continuous frictionally coupled (CFC) and,

-Discretely mechanically or frictionally coupled(DMFC).

21
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

2.7.1. Load Transfer Concept in Fully Grouted Rock Bolts

A fully grouted bolt is a passive roof support system, which is activated by the

movement of the surrounding rock. Fully grouted bolting system consists of three

components; the bolt, the grout, and the surrounding rock. The relationship between

these three is similar to continuous mechanically coupled bolt system (CMC) shown

in Figure 2.2. The efficiency of load transfer is affected by the type and the grout

properties (cementitious or resin), profile of the rock bolt (see Chapter Four), hole

and bolt diameter, anchorage length, rock material, confinement pressure, over/under

spinning and installation procedures. As Figure 2.3 shows, the fully grouted bolt

provides greater shear surface for the transmission of the load from the rock to the

bolt and visa versa (Snyder 1983). The main utility of the grout is to supply a

mechanism for the load transfer between the rock and the reinforcing element. The

redistribution of forces along the bolt is the result of movement in the rock mass,

when the movements occur, the load is transferred to the bolt via shear resistance in

the grout. This resistance could be the result of adhesion and /or mechanical

interlocking.

GGrout
Bolt

Rock
Section C-C

Figure 2. 2. Continuous mechanically coupled rock bolt

22
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Stable area Join Unstable area

Figure 2.3. Load transfer in fully grouted rock bolts

Adhesion is the actual bonding between the grout, the steel and the rock, and the

mechanical interlocking is a keying effect created when grout fills irregularities

between bolt and the rock. It is practically recommended use of 25 % to 30 % more

resin than the theoretical annulus volume (Aziz et al. 1992).

The bolt will help to prevent failure of the weak zone if there is sufficient anchorage

length and if failure does not occur in one of the component (grout or bolt) when the

load develops in the bolt. Stress concentration is induced between the hole wall

roughness and the bolt surface profile. This localized stress concentration could go

over the strength of the grout and rock, resulting in localized crushing that allows

additional deformation in the steel.

Singer (1990) demonstrated that there is no adhesion between the grout-bolt and

grout-rock interface. However, in most cases, which have been reported, there is very

little adhesion between grout/rock and grout/bolt, Aziz and Webb (2003). In general,

only resinous grouts can meet the high strength requirements for short anchorages.

The grouted bolt has an advantage which is greater load transfer compared with the

expansion shell or wedge type bolt anchorages. This may be essential in weaker rock

strata where transfer of high loads over a short length of borehole may commence

failure at the rock interface.

23
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Serbousek and Singer, (1987) found that the rate of load transfer from the bolt to the

rock exponentially is decayed. This exponentially reduction in load transfer is

dependent upon the material properties of the bar, the grout, and the rock interfaces.

Figure 2.4 shows the rate of load transfer along the bolt. Based on several pull out

tests they found the load transfer between the bolt, grout and rock is controlled by

mechanical interlocking. The significant tests, which were carried out in the current

research in both pull and push tests showed that mechanical interlocking and bolt

profile configuration play a great role on load transfer mechanism, is discussed in

Chapter Four.

14

12 Resin grout
Gypsum grout
10

8
Load (Kips)

0
0 10 20 30 40 50

Distance from bolt head

Figure 2.4 Rate of load transfer along the fully grouted rock bolts

2.8. SELECTION OF FULLY GROUTED BOLTS

Carr (1971), Parker (1973), Reed (1974), Gerdeen et al (1977), Wittaker and grant

(1980), Dight (1982), Snyder (1983), Maleki (1992), Gray and et al (1998) Siab

24
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

(2001) and Yassein et al. (2002) found that fully grouted bolts were much more

successful in supporting roof strata than mechanically anchored bolts. The reason

behind is following advantages.

1- Fully grouted bolt can create a full contact with the surrounding rock and

because of high stiffness is able to increase the rock stiffness by joining the

roof layers together and also reducing the roof sagging.

2- The fully grouted bolts are loaded as long as the surrounding rock deformation

is continuing.

3- It has capability to sustain high peak load (see Figure 2.6).

4- Fully grouted bolt can provide greater support to the rock mass than point

Anchored Bolts even with the same steel strength (Gray et al. 1998).

5- They can produce the higher degree of load transfer in comparison to the other

types of bolts (Whitaker 1998).

6- Fully grouted rock bolts can be about 5 times more effective than mechanical

bolts in reduction of roof beam deflection, when the roof is suspended from

component rock. (Gerdeen et al 1977).

7- The axial stiffness for fully grouted bolts is 10-20 times larger than for

mechanical bolts (Gerdeen et al 1977).

8- Resin grouted bolts does not fail suddenly. They undergo at least 100 mm of

movement prior to failure (Harrison 1987).

9- Fully grouted bolts are more effective than mechanical bolts in ground control

in thinly layered deposit (Snyder 1983).

10- Fully grouted bolts can be used on or close to the face for normal tunnel

blasting without any damaging effect on the functioning of the rock bolt (Stjern

and Myrvang 1998).

25
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

2.8.1. Fully Grouted Bolt Failure

Various types of axial failure can occur when using grouted bolts. Failure can take

place in one or more of the following modes. This was considered by Littlejohn

(1993) as well.

-The bolt,

-The grout,

-The rock,

-The bolt-grout interface or

-Grout rock interface.

The type of axial failure depends on the properties of individual elements. The steel

bar governs the axial behaviour of the bolt, which is much stiffer and stronger than

the grout and rock. If the bolt has sufficient length to transfer the entire bolt load to

the rock, then the bolt will fail if the ultimate strength of the bolt is less than what is

necessary to support. The maximum capacity of the steel depends upon the bolt

diameter and steel grade. It should be noted that it might be failure in the steel bolt

occurs under the shear load. The shear failure happens if a section along the bolt is

subjected to a shear load, which exceeds its shear strength. The shear stress at the

bolt-grout interface is greater than the shear stress at the grout-rock interface; it is

because of the smaller effective area. It can be understood that if the grout and rock

have similar strengths and if the required anchorage length is inadequate, then failure

could occur at the bolt-grout interface. If the surrounding rock is softer, then the

failure could happen at the grout rock interface.

26
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

2.8.2. Load Transfer Measurement

In a fully grouted rock bolts, the load transfer mechanism is dependent on the shear

stress continued on the bolt/resin and resin/rock interfaces. The peak shear stress

capability of the interfaces and the rate of shear stress generation determine the

reaction of the bolt to the strata behaviour. Load transfer is determined by

measurement of the peak shear stress capacity and system stiffness.




Rock






Grout

load

Bolt

Figure 2. 5 The mechanism of the load transfer

Fabjanczyk and Tarrant (1992) conducted several pull tests and evaluated the rate of

load transfer. They pointed out that the most important aspect of good load transfer is

the utilisation of the full load capacity of the bolt and they also indicated that the load

build up was a function of displacement.

Stillborg (1994) carried out a number of tests on different kinds of rock bolts

installed across a simulated joint using two blocks of high strength reinforced

concrete (Figure 2.6). It significantly reveals that the rate of load transfer in resin

grouted rock bolt is higher than other kinds of bolts.

27
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Resin grouted 22 mm diameter


fiberglass rod
Cement grouted 20 mm diameter
steel rebar

Resin grouted 20 mm diameter


steel rebar
Load (Ton)

EXL Swellex dowel To 150 mm

Expansion shell anchored 17.3


mm diameter steel rock bolt To 150 mm

Type SS 39 split set stabilizer

Deformation (mm)

Figure 2.6. Load deformation results in different bolts (Stillborg 1994)

2.9. EFFECT OF BOLT IN CONTINUUM MEDIUM

Not only the shear resistance parameters in jointy rock can increase by fully grouted

rock bolts but also the mechanical properties of the medium (deformation modulus,

strength, etc.) can be improved by rock bolt reinforcements. Basically the main effect

of roof bolting is in post failure properties of materials. When the bolts are installed,

the bolt behaviour depends upon the axial and shear stiffness (Brian and Chappel

28
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

1989), which is varied in different surrounding situations and reinforming bar

characteristics.

2.10. THE EFFECT OF BOLT ON DISCONTINUITY

Rock bolts are basically installed to prevent the movement of discontinuity planes.

The effectiveness of the bolt reinforcement is dependent upon the direction of

installation and the nature of discontinuity surface. Rock bolts can provide a tensile

effect to transfer the load from one side to another when movement takes place with

separation. Also, bolts contribute to shear strength because of the increasing

frictional effect thus creating high tensile resistance to the discontinuity layers.

Peng (1984) investigated the reinforcing effect of keying in underground

excavations. The orientation of the bolts installed in relation to the fracture plane is

illustrated in Figure 2.7. The following relationships were established for bolting at

(a) normal to fracture plane and (b) normal to the roofline of a rectangular

underground headings.

p (sin cos tag )


b = Incline bolt (2.5)
(cos + tag sin )tag

p (sin cos cos 2 tag ) Perpendicular bolt (2.6)


b =
tag

where;

p = Horizontal stress;

=Angle between the normal to the fracture plane and the horizontal plane;

= Friction angle of the fracture.

29
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

b
b + p cos 2
b + p cos 2
p p

p sin cos
Joint

Roof
b
a: perpendicular

b
b sin + p cos
2 2

p p
( b p ) sin cos
Joint

Roof

b
b: incline

Figure 2.7. Bolt installation to the joint a: perpendicular, b: incline (After Obert and
Duvall 1967)

Peng clearly related the relationship between the fracture and roof line with

horizontal stress and coefficient of friction in the case (a) suggesting that for

effective bolting (sp) must be very small and that > . However, the stability

conditions for (b) is obtainable when the bolt is installed perpendicular to the roof

line prescribed by Figure 2.7 b. and that (sp) is small

30
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

2.11. SUMMARY

Rock bolts by increasing frictional effects through the fractures and discontinuities

can provide high shear strength. Bolt pretensioning is one of main factor to increase

friction effect, and reducing the tensile stress within the layers below the tensile

strength of the rock. It makes all the layers more together. Primarily the shear

resistance at the bolt/grout or grout/rock interfaces provides the bearing capacity of

the fully grouted rock bolts. The efficiency of the grouted bolts depends upon the

shear strength of the bolt/grout interface and the grout/rock interface and different

bolt types in terms of profile characteristics.

The performance of any reinforcement system is limited by the efficiency of the load

transfer. Basically load transfer process initiates when the block movement of a rock

reinforced is occurred. The result of movement in the rock causes the forces to

redistribute along the bolt. Load is transferred to the bolt via shear resistance in the

grout. And this resistance could be the result of adhesion and /or mechanical

interlocking. Mechanical interlocking is a keying effect created when grout fills

irregularities between bolt and the rock. Stress concentration induces between the

hole roughness and the rolled ribs of the steel. Valuable research has been reported

that the rate of load transfer from the bolt to the rock is similar an exponential decay

curve and is dependent upon the material properties of the bar, the grout, the rock

and interfaces.

From the significant investigations which are mentioned above, it was found that

fully grouted bolts were much more successful in supporting roof strata than other

types of bolts. So for those mentioned advantages, the fully grouted bolts were only

selected bolts to evaluate the load transfer mechanism and affecting parameters on it.

31
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

2.12. REVIEW OF FAILURE MECHANISM OF BOLT RESIN


INTERFACE SUBJECTED TO THE AXIAL LOAD

Most rock masses include natural discontinuities, which may cause stability

problems, therefore most underground openings need to be stabilized to protect their

integrity during their service life.

Laboratory and field studies are the common methods used to study the bonding

strength, the bearing capacity of rock bolts and the load and hence the load transfer

characteristics of bolts. Often these tests overlook the role of the bolt profiles and

hence they are neglected from any analysis.

2.12.1. Theoretical behaviour of the bolt under axial load

The behaviour of fully grouted bolt has been investigated experimentally,

numerically and theoretically by several researches. When modelling a one

dimensional resin grouted anchor, Farmer (1975) proposed a theoretical solution to a

circular elastic anchor surrounded by an elastic grout confined by a rigid borehole.

He derived a homogeneous linear differential equation describing the distribution of

force along the anchor. His solution predicted that the axial stress of the bolt and

shear stress of the interface decreases exponentially from the point of loading to the

far end of the bolt before decoupling occurs. The shear stress in resin annulus was a

function of the grout as:

x
x = Gg When R-a < a (3.1)
( R a)

x
x = Gg When R-a > a (3.2)
R
a ln
a

32
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

where;

x = shear stress in resin annulus

x = extension in the bolt

a = radius of bolt

x = distance along the length of bolt starting at free end of grout

R = radius of the borehole

Gg = shear modulus of grout

Figure 2.8 shows a sketch of the stress situation around a bolt when the bolt is loaded

axially. An approximate indication of the shear distribution along a typical resin

anchor was given by the following equation and is shown in Figure 2.9.

x x
= 0.1 exp (0.2 ) (3.3)
0 a

where;

0 = Axial stress at the free end = 0 stress on bolt at x = 0,

To compare theoretical results, Farmer carried out a series pull tests in concrete,

limestone and chalk. The results showed good correlation for low axial loads in

concrete, but were different in weaker limestone and chalk. These discrepancies were

attributed to the lack of a model to account for the effect of slip at the bolt-grout

interface. The anchors in concrete closely simulated the assumed theoretical

conditions of the rigid rock boundary, and the stress distribution along the bolt was

variable as the maximum stress values were at the free end of the bolt as in Figure

2.9.

33
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Figure 2. 8. Stress situation in a grouted anchor (after Farmer, 1975)

x
0.2
= 0.1e a
x 0
a

Figure 2. 9. Theoretical stress distribution along a resin anchor in a rigid hole with
thin resin annulus (after Farmer 1975)

34
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Figure 2.10 shows the load displacement, strain distribution, and computed shear

stress distribution curves in concrete.

(a)

Strain ( )
Load (kN)

Distance along rod, x (mm)

Shear stress (kN/m^2)


(b) (a)

Distance along rod, x (mm)

Figure 2. 10. Load displacement, strain distribution, and computed shear stress
distribution curves in concrete, a) strain distribution at the specified anchor load, b)
theoretical shear-stress distribution curves. (After Farmer 1975)

The only limitation of the Farmers theory was the elastic behaviour assumption of

the system, which is not the case in real in-situ situation.

A more realistic analytical treatment of Farmers work was presented by Aydan et al

(1985). An idealized elastic-softening plastic behaviour was adopted for the anchor /

grout interface, and the analytical solution by the differential equation for the load-

displacement curve was found to be in closed agreement with the finite element

35
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

results obtained by Hollingshead (1971). In a further development Aydan (1989)

dropped the assumption of an elastic bolt by assuming a bi-linear elasto-plastic

behaviour for the bolt and elastic softening-residual plastic behaviour for both the

grout and the rock. Indraranta and Kaiser (1990 a,b) described an analytical

approach to model a reinforced circular tunnel in a homogeneous, isotropic medium

with fully grouted bolts. Using the theory of elasto-plasticity, the equivalent material

properties for supported ground were calculated and the effect of bolt density on the

stress and displacement field near the opening was determined.

Xueyi (1983) expressed a simple theoretical model to predict stress distribution along

the bolt based on field studies in yielding rocks. The concept of neutral point was

subsequently introduced. The shear stress distribution is characterized by the division

of the bolt into a pick-up length and an anchor length on either side of the neutral

point. Neutral point is the point where there is zero relative displacement between the

bolt and the rock, in this situation a positive frictional force, generates between rock

and bolt interface towards the rock and a negative frictional force forms from the

rock to the bolt due to the rock deformation. He derived the equation 3.4 for the

shear stress distribution. It should be noted that bolts in situ have both a pick up

length and an anchor length, which bolts in pull out test have only anchor length, and

it is expected that the axial load distribution in two cases will produce different

results.

x = k{u ( x) ( w( x) + u )} (3.4)

where;

x = Shear stress distribution along the bolt

k = Long term shear deformation modulus of rock (kg/cm^3)

36
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

w(x) = Expression for bolt displacement (cm)

u (x) = Bolt displacement due to strain (cm)

u = Neutral point displacement (cm)

Yu and Xian (1983) investigated the location of the neutral point along the bolt by the

equilibrium equation 3.5. They supposed that the model of the shear and axial stress

distribution along the bolt behaves according to Figure 2.11.

l
p= (3.5)
l
ln[1 + ( )]
a

Where;

P = Radial distance to the neutral point and

a = Tunnel radius
Depth

Depth

Anchor length
Neutral point

Pick -up
length

Shear stress Axial stress


Tunnel

P L
p=
ln(a + L) ln a

Figure 2. 11. Stress distribution model for grouted bolt (after Yu and Xian, 1983)

37
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Following Hyett and et al. (1996), Li and Stillborg (1999) developed an analytical

model for predicting the behaviour of rock bolts under three different conditions; a)

for bolts subjected to a concentrated pull load in pull out tests, b) for bolts installed in

a uniformly deformed rock massed and c) for bolts subjected to the opening of

individual rock joints.

The development of these models was based on the description of the mechanical

coupling at the interface between the bolt and the grout medium for the grouted tests

or between the bolt and the rock for frictionally coupled tests as shown in Figure

2.12. The shear stress along the bolt, at two levels of applied load, was given by

Equation (3.6).

A d b
b = . (3.6)
db dx

where;

A = Bolt cross section area

d = Bolt diameter

b = Applied stress
b = Shear stress at interface
b = Shear length

Figure 2. 12. Stress Component in a small section of a bolt (after Stillberg & Li,
1999)

Li and Stillborg suggested that for bolts in pull out tests, the shear stress of the

interface attenuates exponentially with increasing distance from the point of loading

when the deformation is compatible across the interface. Decoupling was found to

start at the loading point when the applied load was large enough, and then

38
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

propagated towards the far end of the bolt with an increase in the applied load. The

section of the bolt close to the loading point was completely decoupled with a zero

shear stress at the bolt interface. Figures 2.13 and 2.14 show the shear stress

distribution before and after decoupling respectively. The magnitude of the shear

stress on the decoupled bolt section depended on the decoupling mechanism at the

interface and the shear stress attenuated exponentially towards the far end of the bolt.

The shear stress at the decoupled interface is lower than the ultimate shear strength

of the interface. The calculated results showed that the decoupled length of the bolt

was shorter with a face plate than without a face plate, and the axial stress in the

decoupled section is larger for the bolt with a face plate than the bolt without a face

plate. This means that rock bolts with a faceplate have better reinforcement effect

than those without a faceplate. The shear stress between the bolt grout interface is

exponentially reduced from outside end of the bolt towards the inner end. However,

Li and Stillborg, did not specify the bolt decoupled length. This is the subject of

further research discussion to be reported in the thesis.


Shear stress

b (x )

Figure 2. 13. Shear stress along a fully coupled rock bolt subjected to an axial load
before decoupling

39
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

b = sp

Shear stress
b ( x)
b = sr
b = 0

Figure 2. 14. Distribution of shear stress along a fully grouted rock bolt subjected to
an axial load in coupled rock bolt

2.12.2. Experimental behaviour of the bolt under axial load

Various experimental studies have been carried out to examine various parameters

influencing the effective load transfer characteristics of bolt installations. These

studies include the works of Pells (1974), Farmer (1975), Serbousek and Singer,

(1987), Aydan (1989), Singer (1990), Fabyznchic et al. (1992, 1998), Hyett et al.

(1992), Skybey (1992), Ebisu et al (1993), `Gray et al. (1998), Thompson and Finn

(2001), Kilic and et al. (2002, 2003), Aziz (2003), Hagan (2003, 2004), Compton and

Oyler (2005) and Campbell and Mould (2005). The push and pull tests can be

informative to understand the effect of various parameters on the mechanical

behaviour of the bolt system, but they are not suitable to determine the material

behaviour for the evaluation of the mechanical performance of rock bolts under

various state of stress. The push and pull methods are considered the acceptable

methods to investigate the bolt/grout/rock interaction under axial loading. A great

40
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

deal of experimental studies was carried out in order to describe the bolt/grout/rock

interaction under axial loading conditions. A summary of the various research works

is as follows:

Serbousek and Singer, (1987) conducted a series of experimental pull tests in grouted

rock bolts and compared the results with analytical and numerical modelling, their

tests were conducted on 1.2 m (4. 2ft) and 0.3 m (1 ft) bolts in holes of 25.4 mm,

44.4 mm dimeters. In their tests the applied load was limited to the elastic response

of the system so that failures did not occur and examination of resin bond showed no

chemical adhesion of the grout. Basically, as movement takes place, the irregularities

on the surface of the bolt and the hole cause mechanical interlock and the interlock

will cause shear resistance to be transferred from one medium to another until the

maximum shear strength is reached. The experimental results showed that hole size

and grout type did not have a large influence on the elastic-load transfer rates. This

result was not in agreement with the results reported by Fabyznchic et al (1998), Aziz

(2004), and in the results reported in this

thesis discussed in Chapter 4. Serbousek and Singer also proposed an analytical

model (Equation 3.7), which had various restrictions that were unrealistic. They

considered the existence of the complete bonding between the bolt /grout and grout

/rock interfaces, rock deformation was zero and also the elastic deformation takes

place both in the bolt and in the grout. However, numerical simulation and laboratory

tests in this thesis have shown that grout being crushed in bolt elastic region and

experiences non-linear situation. Besides, in the complete bonding, bolt and grout

move equally, which is not real case.

4 py
y
= 0e = 0 e Edb l
2
(3.7)

41
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

where;

= Stress in the bolt at a distance y, psi

0 = Stress at the point of applied force, psi

= Decay coefficient 1/in which depends on the stiffness of the system

y = Distance along the bolt from the applied load, in

p = Load applied at the bolthead, lb

E = The modulus of the bolt

Db = The dimeter of the bolt

l = The deflection at the head of the bolt, in.

The schematic diagram of the bolt, grout, and rock with above variables is shown

in Figure 2.15. Serbousek and Singer proposed an additional numerical model to

evaluate the load transfer of fully grouted bolt.

Figure 2. 15. Variables used in closed-form solution (after Serbousek and Singer
1987)

42
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

The model was based on linear elastic behaviour, which is not the realistic case of

actual behaviour in particular for the grout interface, follows the non-linear

behaviour.

Kilic and et al. (2002, 2003) carried out a direct pull out test using different types of

rock bolts having different shapes of lugs. The bolts used were single, double and

triple conical lugged (Figure 2.16). They found, there was the influence of bolt shape

on the load bearing capacity and deformational behaviour of bolts. In addition, the

yield load in single and triple conical lugs was lowest and highest value respectively.

In all the cases in single and double conical, failure occurred in grout column and in

some cases in triple conical, failure occurred in the steel bolt. This meant the number

of lugs had some bearing on the load bearing capacity of rock bolts.

a) Single conical lugged bolt b) double conical lugged bolt

Figure 2. 16. Schematic illustration of different conical lugged bolts: (a) Single, (b)
Double and (c) Triple c) Triple conical lugged bolt

43
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Also, it was found that both the bolt length and diameter increased the bearing

capacity of the bolt. However, this increase is limited to the ultimate tensile strength

of the bolt materials.

2.12.3. Bolt grout-rock interface mechanism

Aydan (1989) carried out a series of push and pull out test to investigate the

anchorage mechanism of the grouted rock bolts and the effect of various parameters

such as bolt / borehole dimeter ratio and bolt/grout interface behaviour under triaxial

stress state. Two types of steel bars 13mm and 19 mm in diameter were tested.

The test results showed that the load bearing capacity of rock bolts was 25% higher

in the case of push-out tests than those in the case of pull out test. This increase in

push test values was attributed to the poison ratio effect (The radial stress is of

compressive character in the push out case while it tends to become tensile in the

case of pull out tests). His investigation showed that the increase of the bearing

capacity was attributable to the normal stress of compressive character resulting from

the geometric dilatancy of the bolt surface. Aydan suggested that shearing might

occur along one of the surface of weakness in the rock bolt system (grout-rock

interface and bolt grout interface), and classified the failure modes in push/pull test

as follows:

1. Failure along the bolt grout interface: This type of failure was observed in

all tests on steel bars with a smooth surface and in the case of deformed

bars installed in large borehole.

2. Failure along the grout rock interface: This type of failure was observed in

the case of deformed bars only installed in smaller dimeter boreholes.

3. Failure by splitting of grout and rock annulus

44
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Aydan observed that although shearing failure along one of the interfaces was the

main cause of failure, some samples were found to have failed by splitting without

confining pressure. This was attributed to geometrical dilatancy of the bolt-grout

interface during shearing which causes an internal pressure on the borehole.

The geometrical dilatancy of the surface is probably one of the most important

parameters in determining overall load bearing capacity. However, bolt profile

configurations, which affect severely the load transfer mechanism and interlocking

effect, was not substantiated by the Aydans tests. Further tests by Aydan included

the study of the least shear resistance, which was reported by the grout-smooth steel

interface followed in grout-rock interface and the largest shear resistance offered by

the grout steel interface of ribbed type corresponding to 19 mm ribbed bolt surface

(Figure 2.17).

It should be noted that the axial failure in the steel bar might occur if the axial load

exceeds the ultimate capacity of the steel bar. However, in short encapsulation tests

failure usually happens from the interfaces. In addition to this the failure mechanism

of fully grouted bolt depends on the grout-rock-bolt interface, which are affected by

various parameters including; contact interface stiffness, the nature of the bond

between interfaces, cohesion and angle of friction of interfaces and shear strength of

the interfaces. In numerical design method all of these parameters, are evaluated

which are ignored in previous works. Aydans tests were conducted under the

constant normal load condition (CNL) but in reality when shearing surface is smooth

enough or insignificant dilation then the testing under CNL condition is adequate to

evaluate the shear behaviour, for Non planar discontinuities shearing often results in

dilation as one asperity rides over another. So a realistic outcome of such study was

45
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

considered possible if the tests were conducted under constant normal stiffness

(CNS) condition (Figures 2.18).

Figure 2. 17. Shear stress versus shear displacement in bolt /grout interface at
different bolt diameter (after Aydan 1989)

46
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

= Rock and bolt stiffness


= Joint dilation

Joint plane

Bolt

Behaviour of bolted joint under constant normal stiffness

No dilation Dilation

Smooth surface Rough Surface

Figure 2. 18. Dilation behaviour of joint plane a) two smooth plane, b) bolt and resin
interface.

Singer (1990) conducted a series of field pull tests to investigate the transfer of

applied load from the bolthead to the rock. Figure 2.19 shows the pull test gear

arrangement force, which was applied to the head of the bolt by a hydraulic ram.

When the load was applied to the system, the bolthead would deflect. These

deflections were measured at the end of the pull gear by a dial gauge. Increasing the

pull load resulted in higher stiffness, indicating that the effectiveness of the

47
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

mechanical interlock among the bolt/grout and the rock mass and the primary

mechanism for transference of load.

Pull cellar
Hydraulic ram
Grouted bolt
Adjusting nut Deflection gauge

Pressure gauge
Strain gauge lead
wires
Crows foot

Pressure transducers
Hydraulic jack

Figure 2. 19. Pull test gear arrangement (after Singer 1990)

Singer also carried out a series of laboratory tests over a series of bolts and his results

indicated that 0.56 m (22 in) of bolt length was required to transfer 90% of the load

from the bolt to the rock .He used polyester resin and gypsum grout with a 19mm

bolt and 25.4 mm hole dimeter. Figure 2.20 shows a comparison of load distribution

in different methods along the length of the bolt. Results showed that the load

applied during a standard pull test is dissipated into the rock with, 0.61m of the bolt

head, however the anchorage at the end of the bolt, which is critical for proper

support was not tested, and that it is difficult to evaluate properly the capacity of the

grouted bolt by the pull test. Furthermore the results showed that if there is sufficient

length of the bolt past the yield zone, then the load will transfer from the bolt to the

48
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

rock. This means that the grouted bolt can still be an effective support past the yield

point of the steel.

Bolt load (10^3 Ib)

Distance from bolt head (in)

Figure 2.20. Comparison of load distribution along the bolt length

2.12.4. Load transfer mechanism

Yazici and Kaiser (1992) conducted studies on the bond strength of a conceptual

model for fully grouted cable bolts called bond strength model (BSM). According to

their theory, the bond strength of bolts depended upon the pressure at the bolt-grout

interface. The increased pressure at the interface was a function of the grout dilation

or radial movement, which was caused by the rough surfaces of the cable bolt. The

bolt surface was assumed to be zigzag in shape as shown in Figure 2.21. The bond

strength was expressed in terms of friction and dilation angle:

49
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading


= tag{i0 [1 ( ) ] + } (3.8)
lim

where;

i = Apparent dilation angle

= Reduction coefficient of dilation angle

lim = Limiting stress

= Friction angle between the bolt and grout

Consequently, the ultimate bond strength at the bolt-grout interface was limited by

the grout strength, for a rough bolt. The bond strength significantly increases when

the pressure on the bolt /grout interface builds up due to dilation created as the rough

edges of the bolt push the grout laterally against the confining rock. The theory of

Yazicic and Kaiser was not valid for bolts with different surface geometry. They

assumed only zigzag surface for bolt.

Figure 2. 21. Schematic diagram reflecting the geometry of a rough bolt (after Yazici
and Kaiser, 1992)

50
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Skybey (1992) evaluated the load transfer mechanism between bolt/resin/rock with

sky bolt concept. This bolt concept was point anchored with resin in large diameter

holes of 38 mm and 45 mm. He carried out pull out tests and obtained, the load

transfer mechanism values, which maximised the loading capacity of the resin from 6

kN/mm to 12 KN/mm.

Fabjanczyk and Tarrant (1992) investigated the load transfer mechanism in pull and

push out tests. They found that smooth and lower profiled bolts had minimum

stiffness (Figure 2.22). It was found that the load transfer was the function of various

parameters such as, hole geometry, resin properties and bar surface configurations. In

addition, it showed the role of confinement generated within the annulus as being

critical to the load transfer performance. However, they neglected the effect of bolt

rib spacing, which significantly affects the load transfer capacity of the bolt system.

Peng and Guo (1992) reported from the filed study that debonding occurred between

the resin annulus and wall rock.

Figure 2. 22. Load/displacement curves for rebar with various amounts of bar
deformation removed (after Fabjanczyk and et al, 1992)

51
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

It should be noted that in the field situation, if failure doesnt happen in steel bolt, it

is likely that it will occur in the resin grout and wall rock as the bolt profile creates

higher level of interlocking. This is supported by the experimental test observations,

which is discussed later in the thesis (Chapter 4).

Benmokrane et al (1996) carried out a series of laboratory short encapsulation pull

tests. They used six types of cement-based grouts and two types of rock anchors. The

following empirical equation was derived for the estimation of anchor pull out

resistance for the embedment length.

l
p = a+b (3.9)
d
where;

P = ultimate pull out load

l = anchorage length

d = dimeter of anchor and a, b = constants, depends on grout and anchor type.

Benmokrane et al stated that the bond strength from the laboratory tests was higher

than that from the field study.

From the tests it was investigated that the slip at the unload end began at near 80% of

the failure load and also they proposed an analytical model for the bond -stress -slip

relationship for the threaded bars and the standard cables.

= k .s + t (3.10)

where;

= Shear bond stress at anchor grout interface

s = Slip between anchorage and grout

k,t = Coefficients which depend on the type of anchor, grout and stages of shear.

52
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

Mark et al (2002) conducted a series of pull tests on fully grouted rock bolts. They

found that short encapsulation pull testing (SEPT)(the international consensus seems

to be that at least 0.3m of the bolt should be grouted to minimize the effect of the

zones of poor mixing at the top and the bottom of the resin) could be used to make a

simple evaluation of resin bolt anchorage. They proposed that poor anchorage could

be an issue, particularly where the roof rock is very weak. In their results they

expressed when anchorage is poor, roof movements near the top of bolt, within the

anchorage zone, can pull the bolt out of the upper portion of the hole at loads less

than the yield strength of the rod. It was supposed that the two most likely causes of

poor anchorage are weak rock and poor installation quality. They found that if short

encapsulation tests have confirmed that the anchorage is poor, the following steps

could improve it:

1. Check the quality of the installation (such as grout-hole-bolt),

2. Reduce the hole annulus, as most of the tests have found that the optimum

difference between the diameter of the bolt and the diameter of the hole is

no greater than 6.35mm, giving an anulus of about 3.17mm,

3. In very serious condition, the only way to increase the anchorage strength

would be to increase both the hole dimeter and the bar dimeter. This

enlarges the area of the grout-rock contact surface that increases the total

shear resistance.

2.12.5. Conclusion

From the numerous research studies undertaken around the world in pull and push

tests, it is concluded that the bolt interacts with the host rocks via shear stresses at the

contact interfaces between them. Accordingly, shear resistance of the interfaces have

53
Chapter 3: Rock bolt system and review of bolt behaviour under axial loading

to be strong enough to transfer the load from the bolt to the rock. This is affected by

several parameters such as resin annulus, grout strength, bolt profile characteristics,

rock roughness, rock strength and mechanical properties of the steel bolt.

There is a lack of significant research in terms of bolt profile specification, and load

transfer capacity in different profiles. This is an important parameter, which requires

further research, and therefore it forms a significant part of the research study carried

out by this study, which will be discussed in the later chapters.

54
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

CHAPTER THREE
REVIEW OF SHEAR BEHAVIOUR OF BOLTS AND
MECHANICAL PROPERTIES OF THE MATERIAL
USED

3.1. INTRODUCTION

Rock bolts are main elements of support in the modern stabilization techniques for

geotechnical engineering. Generally bolts work as an additional resistance against the

shear failure along joints and weakness planes. The steel bar within the rock bolt

system is the main element to resist to both the axial load under suspension

conditions and transverse the shear loads due to beam bending and slip on joints. The

axial force in the bolt is made of two components; the perpendicular component to

the shear joint, contributes to the frictional strength and the other component, parallel

to shear joint plane in the shear direction, which contributes to the dowel effect.

When rock bolts are used to support rock slope and underground excavations, they

are affected by both the axial and shear loadings during any movement on the blocks

(Figure 3.1). The bolt behaviour under both loads and how the load is transferred

along the bolt length is significantly important. These are discussed in this chapter.

This chapter consists of two main parts; First part explains a summary of significant

studies undertaken by various workers on shear behaviour and second part describes

the conducted laboratory tests to define the material properties used in the next

chapters.

55
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Ground surface

Joint Rock
Bolt


Tunnel axis

Figure 3.1. Stability issues in rock mass reinforced by fully grouted bolts

These studies were first initiated by Dulascka (1972), she was then followed by

Bjurstrom (1974), Haas (1976,1981), Azuar (1977,79), Hibin and Motojim (1981),

Egger and Fernands (1983) and Ludvig (1983), Gerard (1983), Dight (1983),

Bjornfot & Stephansson (1984), Larsson (1984), Schubert (1984), Lorig (1985),

Yoshinaka et al. (1987) Spang and Egger, (1990), Stillberg (1991), Holmberg

(1991), Egger and Zabuski (1991), Ferrero (1995), Pellet and Boulon (1995), Pellet

et al. (1995, 1996), Goris et al. (1996), Grasselli et al (1999), Grasselli (2005) and

Mahoni (2005) worked on the mechanical behaviour of rock bolts. All experimental

testing of grouted bolts were performed as a single shear test using single shear

apparatus, which results difficulties in the shear joint due to non-equilibrium

situation and un-uniformity distributed load on the shear joint. None of works

included applying tensile loads on the bolt. However, in several studies, only

confining pressure on the moving block was applied. Thus, new method is designed

in present research to evaluate the bolt bending behaviour in proper manner, which is

discussed later.

56
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

3.2. DESCRIPTION OF PAST RESEARCHES

Dulascka (1972) established the following expression to find the shear force carried

by bolt, based on idealised stress distribution at the bolt contact. Her theory was

based on the development of a plastic hinge at the point of maximum moment given

by;

c
T = 0 . 2 Db y [ 1 + (
2
) 1] (3.1)
0.03 y sin 2

where;

T = Shear force carried by bolt

c = Uniaxial compressive strength of rock

Db = Bolt diameter

y = Yield stress of bolt

= Angle between bolt and normal to the joint

The crushing strength of the concrete was at least four times greater than the

compressive strength of the concrete. As shown in Figure 3.2 there is no static

equilibrium condition in both sides of the shear joint, which is the limitation of the

system.

Bjurstrom (1974) direct shear test on cement-grouted bolts in granite blocks was

aimed to evaluate the influence of various factors affecting the shear strength of rock

joints. The bolts had inclinations of between 30o-90o with respect to the joint surface.

He found that, for angle <40o bolts failed in tension and for angles >40o the bolts

failed in a combination of both shear and tension.

57
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

(a) (b)

Figure 3. 2. The shear test arrangement in (a) and (b) probable load generation (after
Dulasck 1972)

Bjurstrom provided an analytical solution based on the equilibrium of the forces

acting on the system and expressed that the total shear strength of a bolt reinforced

joint was dependent on the following three parameters:

i) Shear resistance due to reinforcement effect:

Tb = p (cos + sin tag ) (3.2)

where;

Tb = The reinforcement effect in shear resistance due to bolting

p = Axial load corresponding to the yield strength due to shear displacement

= Initial angle between bolt and joint direction

= The friction angle of the joint

58
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

ii) Shear resistance due to the dowel effect:

Td = 0.67 d b ( y c ) 0.5
2
(3.3)

where;

d b = Bolt diameter

y = Bolt yield strength

c = Uniaxial compression strength of the rock

iii) Shear resistance due to friction of joint:

T f = A j n tag j (3.4)

where;

A j = Joint area

n = Normal stress on joint and

j = Joint friction angle

Figure 3. 3. Components of shear resistance offered by a bolt (after Bjurstrom, 1974)

59
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

According to Bjurstrom, the total contribution from the bolt to the shear strength of

the joint, shown in Figure 3.3, is given as:

Tt = p(cos + sin tag ) + 0.67 Db ( y c ) 0.5 + A j n tag j


2
(3.5)

Bjurstroms estimate of the contribution to the increase in strength reveals at first

glance to be acceptable. However, the mode of failure in surrounding materials was

neglected which is a limitation.

Hass (1976) carried out a series of single shear tests on chalk and limestone and

reported the splitting of the sheared block in the shearing process. The stresses on

both sides of the shear joint were suggested to be different, which is not a realistic

situation around the shear joint plane (Figure 3.4a). If the loading were truly

symmetrical there would be an equal probability of either block splitting. To better

distribute the shear load Hass applied a large bearing plate on the moving block, but

it was unsuccessful. Figure 3.4b shows the deformed bar subjected to lateral loading.

It obviously reveals that there is non-uniform situation along the joint plane. It is

clearly understood that the single shear test has difficulties in equal load distribution

in the shear joint. One method of minimising this problem was to by maintaining

high confining pressures in order to reduce the unbalance situation in the vicinity of

the shear joint plane. Non-uniform stress distribution across the shear joint plane was

also investigated by the numerical analysis (Afridi and et al, 2001), and thus

confirming the existence of non-equilibrium condition across the shear joint sides

(Figure 3.5).

60
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Hole diameter

Fracture

a b

Figure 3. 4. (a) block splitting in one side of shear joint (b) non equilibrium situation
in vicinity of shear joint

Normal load
Shear load

a b

Figure 3. 5. (a) Finite element mesh and (b) deviatoric of stress distribution across
the joint (Afridi and et al. 2001)

Azuar (1977) found that for bolt installed perpendicular to the joint, the frictional

effect is negligible. This finding is not consistent with the confining theories, which

contribute part of the strength increase to a frictional component. Azuar also found;

61
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

i. The maximum contribution of a rock bolt to the shear resistance of a joint is

influence by bolt orientation with respect to the joint surface. It ranges from

60 to 80 % of the ultimate tension load of the bolt installed perpendicularly

and 90 % for the inclined bolt.

ii. The friction characteristics of the joint do not influence the contribution of

the bolt.

iii. For a given shear displacement, the dilatancy increases the resistance of the

bolted joint.

Hibino and Motojima (1981) reported on shear tests on un-grouted 2 mm diameter

bolts installed in concrete blocks. They considered bolts placed in 2 mm and 40 mm

borehole for fully bonded and point anchored respectively and reported that:

i. For a given shear displacement the shear resistance of fully bonded bolts

was significantly higher than that of point anchored ones.

ii. The shear resistance did not increased by bolt inclination. This is in

contrast with others investigators.

iii. Pretensioning of the bolt reduced the shear displacement but did not

influence the shear resistance. This result is not consistent with the

laboratory and numerical results obtained by this author and discussed later

in the thesis.

Hass (1981) reported on the laboratory tests on limestone with artificially cut joints

reinforced by different types of bolts and different orientations (0o, +45o and -45o) to

the shear plane as shown in Figure 3.6. He suggested that bolts would act more

effectively when they are inclined at an acute angle to the shear surface than the

opposite direction, as they tend to elongate as shearing progress.

62
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

The total shear strength offered by a bolt was given by the summation of the bolt

contribution and the frictional strength along the shear surface, resulting from the

stress on the shear plane. Hass could not apply the bolt pretensioning effect, because

of incapability of the designed device. With increasing shear displacement, the bars

started to pull into the rock and consequently bolt resistance was reduced. However,

for bolts with bearing plate, the shear resistance was increased around 23%.

Figure 3. 6. Arrangement for bolt shear testing (after Hass, 1981)

Dight (1982) conducted a theoretical analysis of the grouted bolt performance. Dight

assumed that the bolt contribution to the strength of a sheared joint was the resultant

of the tensile force in the bolt and the dowel effect (Figure 3.7). The angle of dilation

was given by the following relationship:

63
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

v
Angle of Dilation = tag 1 ( )=i

Reinforcing bar

Grout

Figure 3. 7. General deformation patterns for a dowel in shear

The dowel force was determined by Eq (3.6)

d2 t
tp = 1.7 y p u (1 ( ) 2 ) (3.6)
4 ty

where;

pu = The bearing capacity of the grout or rock

t = Axial bolt load in the position of the plastic moment,

t y = Axial load corresponding to the yield strength

y = Yield stress of the steel,

64
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

d = Bolt diameter

And at the magnitude of t p , the location of plastic hinge was as follows:

y t 2
l pg = 0.58d (1 ( ) ) (3.7)
pu ty

Dight did not make any predictions on bolt behaviour in elastic conditions, if tension

behaviour prevails then the yield strength develops immediately. He considered the

Eq (3.8) for component of the axial load in shear direction and suggested the bolt

contribution would be the summation of Eqs (3.6) and (3.8).

t c = t y (sin + costag ( b + i ) (3.8)

where;

= The angle between the normal vector to the joint and the bolt, and b is the

basic joint friction angle.

Dight reported:

i. The normal stress acting on the joint plane does not influence the shear

resistance, which is against the criterion of joint confining effect and results

reported by Saeb and Amadei (1992).

ii. Joints with inclined bolts had stiffer behaviour than those perpendicular

ones. The deformed length of the bolt was related to the deformability of

the rock.

Egger and Fernandez (1983) carried out bolted samples of concrete blocks in a high

capacity press. They found:

65
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

i. The optimum angle of bolt inclination with respect to the joint varied from

30o to 60o. However, Sharma and Pande (1988) found that the best direction

of reinforcement is normal to the major joint direction.

ii. Perpendicular bolts have appeared to have the lowest shear resistance.

iii. Shear displacements at failure were minimal for bolt inclinations between

40o and 50o.

Ludvig (1983) performed tests on swellex bolts, split sets and two sizes ungrouted

bars. The bolts were performed at 45o and 90o to the shear joint. Under shear

condition the tube bolts, in general, were weaker than the solid bars. He suggested

that the swellex bolt has approximately the same shear resistance as a solid 14 mm

diameter ungrouted bar.

Schubert (1984) proposed an analytical analysis based on the equilibrium of the

forces acting on the deformed system and conducted shear tests on bolted concrete

and limestone blocks. The sketch of the shear device, which was used by Schubert, is

shown in Figure 3.8. His results lead to the following findings:

i. The deformability of the surrounding rock is important for the bolt

reaction.

ii. Bolts embedded in harder rock require smaller displacements for attaining

a given resistance those in softer rock.

iii. Soft steels improve the deformability of the bolted system in soft rock.

Yoshinaka et al. (1987) study on the direct shearing of 16 mm bolt diameter

suggested 35o 55o angles as most favourable bolt angle against the joint plane. In

addition, a perpendicular bolt showed lowest bolt contribution to shearing compared

with low angles (Figure3.9). Moreover, no pretensioning was considered.

66
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Figure 3. 8. Shear test machine used by Schubert (1984)


Shear Stress (MPa)

Shear displacement (mm)

Figure 3. 9. Relation between shear stress and shear displacement (After Yoshinaka
1987)

Spang and Egger (1990) made an extensive series of shear tests of grouted bolt

performance and used three different rock qualities, sandstone, concrete and granite.

67
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

They found the maximum bolt contribution to the shear strength of the joint was a

function of the ultimate strength of the bolt, Tu.

0.14
To = Tu [1.55 + 0.01 c sin 2 ( + i )] c (0.85 + 0.45tag )
1.07
(3.9)

where;

Tu = Ultimate strength of the bolt

c = The uniaxial compressive strength of the rock,

= Inclination between the bolt and the shear surface

i = Dilation

d = Dimeter of the bolt

= Friction angle of the joint and following Eq (3.10 ) was expressed for the

shear deformation of the bolt.

0.14 0.28 70 tag


uo = d (15.2 55.2 c + 56.2 c )[1 ( ) 0.125 ] (3.10)
c cos

But this theory was limited to:

i. Steel bolts grouted with cement,

ii. Borehole dimeter approximately twice that of the bolt diameter,

iii. A uniaxial strength of rock between 10-70 MPa,

iv. Deformation formula is not accepted for bolts perpendicular to the joint (

=90o) and,

v. Bolt not subjected to pretensioning

Egger and Zabuski (1991) carried out a single shear test on small bolt diameters of

between 2.5 mm to 5 mm. Tests were made without the normal pressure and no

pretensioning across the joint. Figure 3.10 shows the direct shear test apparatus.

68
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Bolts failed under the combination of both the shear and axial forces. Only low

strength steel was used in the test, as the technique was not suitable for high strength

steel, because of non-equilibrium and un-uniformity of the load distributed on the

shear joint.

Figure 3. 10. Direct shear test device (after Egger and Zabuski 1991)

Holmberg (1991) theoretically examined the mechanical behaviour of untensioned

grouted rock bolts in elastic and yielding conditions. His analytical model was based

on the equilibrium of the forces acting on the deformed system. He expressed three

stages and ultimate condition of bolt-grout interaction. These stages are shown in

Figure 3.11 and were distinguished as following:

i Bolt and surrounding medium are in elastic state,

ii Bolt is in elastic and surrounding medium in yielding state,

iii Bolt and surrounding medium are yielded,

iv Ultimate condition.

Holmbergs theory disregarded the influence of the grout material. The following
conclusions were drawn:

69
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

a: Elastic condition b: Elastic bolt and yielding subgrade

c: Yielding bolt and yielding subgrade

Tt

pu ly

y
y = uy
Tty

d: Ultimate condition

Figure 3. 11. Bolt grout behaviour sketch (after Holmberge 1991)

70
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

i. The bolt contribution to the shear resistance of a bolted joint from dowelling

effect and axial load can be determined as a function of the deformation for

different load conditions,

ii. The initial bolt angle with respect to the direction of deformation is of minor

importance with regard to the maximum resistance of the bolted joint,

iii. The initial bolt angle has great influence on the maximum deformation of the

bolt,

iv. A bolt inclination of 60o with respect to the direction of deformation reduces

the total deformation by 4 folds compared to a bolt perpendicular to the

direction of deformation,

v. When the steel bolt crushes into the rock mass and develops a shape similar to

a crank handle, the ability to resist larger deformations before failure is

increased significantly,

In jointed rock mass, the bolt shear resistance becomes important where the bolt

intersects the joint. When deformation occurs in the rock mass the grouted rock bolt

will be subjected to loading, which generates both the axial and lateral forces in the

bolt (Figure 3.12). Factors influencing include; bolt and hole diameter, steel quality,

bolt elongation, rock and grout strength.

The angle between the bolt and the joint is very important for the behaviour of the

bolted joint surface, especially in determining bolt failure type. If the angle is less

than 35o, the failure seems to be a tension failure, and if the angle is approximately

90o, the failure is in shear.

71
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Figure 3. 12. A grouted rock bolt subjected to lateral force

Ferrero (1995) proposed a shear strength model for reinforced rock joints based on

the numerical and laboratory studies on large size shear blocks. He suggested that the

overall strength of the reinforced joint could be attributed to the combination of both

the dowel effect and the incremental axial force due to the bar deformation. Figure

3.13 shows the shear test apparatus. The apparatus tend to suffer from unbalance-

distributed load on the shear joint plane. Ferreros analytical model was applicable to

the bolts installed perpendicular to the joint surface in stratified bedding planes. As

shown in Figure 3.14, the proposed analytical model was expressed by

F = t r cos Q sin (t r sin Q cos )tag (3.11)

where;

= Joint friction angle

t r = Load induced in the bolt

Q = Force due to dowel effect

72
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

= Angle between the joint and the dowel axis and

F = Global reinforced joint resistance.

According to his experimental and modelling evidence Ferrero suggested failure

could possible occur in one of the following ways, depending on the prevalent type

of stress:

Figure 3. 13. Ferreros shear test machine

Figure 3. 14. Resistance mechanism of a reinforced rock joint (after Ferrero 1995)

73
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

i. Failure due to the combination of the axial and shear force acting at the

bar joint intersection.

ii. Failure due to the axial force following the formation of hinge points.

The first yielding mechanism is likely to occur with stiffer and stronger rock at the

bar-joint plane intersection under a combination of the shear and normal forces.

As shown in Figure 3.15, the bolt is loaded by both the axial force the frictional

forces that develop between bolt and the surrounding grout.

The following equations were developed to describe the relationship between the bar

tension at the point of maximum moment and bolt-joint intersection respectively.

2
x0
tr = pu Db (3.12)
2 y0

2 2
x0 4y
t r = pu Db (1 + 02 )1.5 (3.13)
2 y0 x0

The second failure mechanism occurs when the maximum computed bending

moment in A exceeds the maximum yielding moment of the bar. Usually this kind of

failure occurs in weak and less stiff rocks. The yielding conditions propagate from

the plastic hinges up to the joint intersection and, consequently, the steel bar is

affected by tensile stress.

However, Ferrero stated that pretension does not influence the maximum resistance

of the system. This appeared to be in contrast with both the experimental and

numerical studies undertaken in current thesis, which is discussed later in the

Chapters 5 and 7 of this thesis.

74
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Figure 3. 15. Forces acting on the failure mechanism 1 (after Ferrero 1995)

Pellet and Egger (1995) analytical model for the contribution of bolts to the shear

strength of a rock joint, took into account the interaction between the axial and the

shear forces mobilised in the bolt and large plastic displacements of the bolt

occurring during the loading process. The description of the bolt behaviour must be

divided in two sections. The first one concerns the elastic range (from the beginning

of the loading process) and the second one deals with the plastic range (from the

yield to the failure of the bolt). The shape of the stressed bolt and the failure

envelope for both elastic and plastic deformations are shown in Figure 3.16 and

Figure 3.17 respectively. They used Tresca criterion as a failure criterion of the bolt.

75
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

a)

b)

Figure 3. 16. Force components and deformation of a bolt, a) in elastic zone, and b)
in plastic zone (after Pellet and Eager 1995)

76
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Relationship between axial and shear


forces in elastic conditions

Axial and shear forces at the yield limit

Yield limit

a)

Failure criterion

Axial and shear forces


at failure

b)

Figure 3. 17. Evolution of shear and axial forces in a bolt, a) in elastic zone, and b) in
plastic zone (after Pellet and Egger, 1995)

The shear forces at the end of both the elastic limit and plastic region are obtained

from Eq 3.14 and Eq 3.15 respectively.

Db el
Qoe = 0.5 p u Db ( N oe ) (3.14)
4

Db 2 N of
Qof = ec 1 16( )2 (3.15)
8 Db ec
2

where;

Qoe = Shear force acting at point O at the yield stress of the bolt

77
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

N oe = Axial force acting at shear plane at the yield stress of the bolt

el = Yield stress of the bolt

Db = Dimeter of the bolt

Qof = Shear force acting at shear plane at failure of the bolt

N of = Axial force acting at shear plane at failure of the bolt

ec = Failure stress of the bolt

The displacement of the bolt in elastic and plastic stages were expressed by the

following equations:

4
8192Qoe b
U oe = (3.16)
E 4 Db pu sin
4 3

Qoe sin op
U of = (3.17)
pu sin( op )

le l
Where op = arccos[ sin 2 cos 2 (1 ( e ) 2 sin 2 ) (3.18)
lf lf

where:

le = Distance between bolt extremity (point O) and the location of the maximum

bending moment (point A)

l f = The length of the part O_A at failure

Pellet and Eager evaluations showed that bolt inclination has a significant influence

on the maximum joint displacement. The greatest displacement is reached when the

bolt is normal to the joint. As the angle between the bolt and the joint decreased, the

displacement drops rapidly (Figure 3.18).

78
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Figure 3. 18. Joint displacement as a function of angle for different UCS value
(after Pellet 1994)

Pellets theory is valid for the inclined bolts less than 90o and is not acceptable for

bolts sharply perpendicular to the joints.

Robert (1995) reported shear tests on smooth bars and cone bolts by his double shear

apparatus. He found that failure only happened in one of the joint intersection. His

results showed non-symmetric situation in both side of the shear joint, which is likely

due to the generation of unbalance forces in three pieces blocks and is contradicted

with results from DSS in this research (see experimental results in Chapter 5).

Goris et al (1996) carried out a direct shear tests on 69 MPa concrete blocks with

joint surface area of 0.078 m2 (Figure 4.19). The test consisted of installing

perpendicularly a 15.24 mm diameter cable bolt (258 kN yield strength) into a 25.9

mm diameter hole. It was found that the yield occurred at 220 kN with 4 mm of

displacement which is higher than the double shear test carried out on the same type

of cable bolt. It appears that the single shear test has higher shear resistance than the

double shear test. This is due to inequilibrium load distribution on the shear joint and

79
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

concentration of the load through the blocks in front of the bolt, which pushes the

blocks together (zone A) resulting in the higher shear resistance which is not an

actual bolt contribution. Another limitation of the test setup was the maximum shear

displacement available being limited to 46 mm, which prevented the cabled from

failure.

Figure 3. 19. Shear block test assembly (After Goris and et al 1996)

3.3 PRETENSIONING EFFECT IN FULLY GROUTED BOLTS

Bolt tensioning places the rock into compressive state. Although pretension is very

effective in preventing bed separation and creating frictional forces between layers,

but this does not mean that higher bolt pretension always create better stability.

When a bolt is pretensioned, it would influence the shear strength of the joint with

forces acting both perpendicular and parallel to the sheared joint, this is created by

inducing confining pressure. A general rule for determining the maximum pretension

80
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

is that the pretension load should not exceed 60% of the bolt yield strength or 60% of

the anchorage capacity.

Nearly all the tests that were conducted by various authors related to the bolt

behaviour under the shear were accomplished in the absence of pretensioning.

However, in field studies and numerical simulations, pretensioning was applied and

it was unanimously agreed that pretensioning contributes to increase reinforcement

effect and improve stability, Lang et al. 1979, Maleki 1992, Peng and Guo 1992,

Jafari and Vutukuri 1994, 1998, Stankus and Guo 1997, Unrug and Thompson 2002,

Zhang and Peng 2002, and Hebblewhite 2005. However, Numerical studies placed

limitations on bolt / grout / rock contact interfaces. In addition, no experimental tests

have conducted to apply pretension in fully encapsulated high strength bolts. In

particular the evaluation of the effect of bolt profile on shear resistance under various

level of pretensioning is neglected. In current research care was taken into account to

remove the whole assumptions and limitations from both laboratory and numerical

design. Pretensioning was conducted in four different load, 0, 20, 50, and 80 kN in

both laboratory and numerical simulations. In numerical chapter a new design of bolt

model and contact interfaces is discussed. As it was discussed above, there are pros

and cons, in each method, which was used so far. A brief view of the methods is

shown in Table 3.1.

81
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Table 3.1. A brief comparison of the used methods in bolt shear behaviour

Author Base of the method Advantages Disadvantages

Dulascka Development of Prediction of shear Non static equilibrium


(1972) plastic hinge after force by bolt condition in shear joint
max. Moment
Bjurstrom Equilibrium forces Estimation of shear Mode of failure in
(1973) acting on the resistance: due to surrounding materials was
system dowel, reinforcement neglected
and friction effect,
Hass Single shear test Test were performed Non-uniform stress
(1976) on real rocks distribution along the shear
joint
Azuar Single shear test Different bolt angles Influence of friction effect
(1977) were considered could not properly
considered
Hibino Single shear test Pretensioning was Pretensioning and bolts
(1981) applied inclination could not
considered properly
Hass Single shear test Real rocks with Pretensioning was not
(1981) different bolt angles applied
were considered
Dight Theoretical analysis The prediction of Neglecting the bolt
(1982) dowel effect and hinge behaviour in elastic range,
point was considered poor effect of normal stress
on joint
Egger and Single shear test Different bolt angles Pretensioning was not
Fernandz was applied applied
(1983)
Ludvige Single shear test Different bolt angles No fully grouted bolt was
(1983) was applied tested
Schubert Equilibrium forces Pretensioning was not
(1984) acting on the Real rocks was tested considered
deformed system

82
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Table 3.1. Continued

Author Base of the method Advantages Disadvantages


Yashinaka Direct shear test Different bolt angles Pretensioning could not
(1987) was considered apply
Spang and Single shear test Real rocks was tested, Limited in: grout types,
Egger max bolt contribution annulus thickness, rock
(1990) and displacement was strength and
predicted pretensioning
Egger and Single shear test Prediction of bolt No joint confinement and
Zabuski failure at a combination bolt pretensioning was
(1991) of axial and shear considered
Holmberge The equilibrium of Bolt behaviour was The effect of grout was
(1991) forces acting on the analyzed in both elastic disregarded
deformed bar and plastic stages
Ferrero Single shear test The plastic stage of the In-capability of the
(1995) system was considered method to show the
effect of pretensioning
Pellet and Theoretical analysis Both elastic and plastic The effect of grout
Egger (1995) stages was analyzed material was neglected
Goris et al. Single shear test Perpendicular bolts Non-equilibrium load
(1996) was analyzed distribution on the shear
joint, Max. Displacement
was up to 46 mm
Grasselli Double shear test Symmetric situation Bolt pretensioning was
(2005) around the shear joint not considered
Mahoni, et Lengthy bolt-grout- -
Single shear test
al. (2005) concrete anchorage
Aziz et al Symmetric situation The size of the shear box
(2005) Double shear test around the shear joint, is small for large bolt
pretension effect, bolt diameters and strong
profile, any grout, bolt steel bolts
& hole diameter

83
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

3.4. SUMMARY

In can be inferred from this review that:

i. For rock /concrete samples reinforced with bolt inclined at an angle to the

normal of the joint plane, two hinges are developed on either side of the

joint plane. The great majority of the inclined bolts failed in tension near

the shear surface.

ii. For samples with a bolt forming a small angle to the normal of the joint

plane, bending of the bolts becomes predominant even when the shear force

is small, which will create two hinges above and below the joint plane.

iii. The vertical height of the bended bolt is about 2-4 times the bolt diameter

called effective height, corresponding to an effective length.

iv. Large bolt diameter reduces shear displacement required for obtaining a

given shear force.

v. The effect of dilatancy contributed to the stiffness of the bolted joint.

vi. Inclined bolts are stiffer and contributes significantly to the shear strength

of the bolted blocks than the perpendicular bolts.

vii. Bolt pretensioning reduces shear displacement, but not the shear resistance.

viii. The deformed length of the bolt is related to the deformability of the host

rock.

ix. Shear displacement at failure is minimal for inclinations between 40o and

50o.

To avoid the related problems for direct shear test and evaluating the load transfer

mechanism in stable situation, in this research, a new approach is evaluated as bolts

can experience both lateral and axial loads in equilibrium situation at both sides of

84
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

the shear joint without any moment generation through the testing machine and

surrounding materials. However, direct shear can provide the valuable information

on the strength parameters of rock joints but when is applied to evaluate the load

transfer mechanism of bolt, is inferior because of non-uniform distribution of stress

concentration on the shear joint and along the bolt in direct shear machine. Afridi and

et al. (2001) also have emphasised on this problem and pointed out that when the

applied shear load is not in the line with the shear plane (it is somewhat above) it

produces overturning moments, which produce rotation in the shear box and create a

non uniform stress profile.

The following work reported in the next chapter examines the interaction of rock /

resin / bolt and focuses on the following issues specifically to get proper knowledge

in the load transfer capacity and bolt / joint interaction in different situations:

i Evaluating of the shear behaviour mechanism in bolt-grout and grout-

rock interfaces.

ii Evaluating of different bolt profile on the load transfer of fully

grouted bolts, that is the main factor in load transfer capacity, which

was ignored in all above works.

iii Study of the load transfer and bending behaviour in bolt-grout-rock

interface in different material strength.

iv The effects of resin thickness on shear behaviour of bolts and load

transfer evaluation,

v The effects of bolt pretensioning on shear resistance and load transfer

of bolts.

So to achieve the above parameters and conditions extensive laboratory tests were

conducted and the results are presented in the next chapter.

85
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

It should be noted that in spite of extensive research which has been done in this

field- due to a huge number of involved factors affected on the bolt behaviour such

as, intact and rock mass strength, joint geometry and their characteristics, mechanical

bolt properties, bolt surface configuration, grout annulus thickness, grout strength,

pretensioning and relative orientation of joint with bolt, there is no overall theory to

evaluate thoroughly the bolting behaviour. Only each experiment and new or

modified idea extends the range of experience and knowledge in this field.

In the next section, it was tried to define the mechanical properties of the whole

material used- bolt, resin and concrete- in the experimental tests, which are described

in the next chapters.

3.5. MECHANICAL PROPERTIES OF REINFORCING


MATERIALS

In this part, the strength properties of bolts, resin and concrete are studied. All the

tests were carried out in the laboratory, and under controlled conditions. Parameters

examined include, the uniaxial compression strength, shear strength, and modulus of

deformations. Then parameters are pertinent to the overall study of load transfer

mechanism of bolts, resin, and concrete interactions.

3.5.1. Bolt Types

Seven different bolt types were tested for tensile strength. Three bolts are the popular

types that are used widely by the Australian mining industry. Figure 4.20 shows the

photographs for various bolts and Table 3.2 list the physical specification of all the

bolts. The bolts are of similar diameter core size, but of different profile heights and

86
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

spacings. Also included in the test is a seven-strand cable bolt used for double

shearing test. Figure 3.21 shows the general profile details of the bolts.

Tensile, bending and shear strengths of the steel bolt are the most important

mechanical parameters that influence its behaviour when loaded axially and in shear.

T1 T2 T3 T4 T5 T6

Figure 3. 20. Different Bolt Types used for axial and shear behaviour tests

Rib Spacing
Rib Width (mm) Rib Height

Core Outer
Diam. Diam.
(mm) (mm)

Figure 3. 21. Profiles specification

87
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

3.5.2. Bolt strength tests

Three kinds of laboratory tests were carried out on different Types of bolts (Table

3.2). They are:

Tensile strength

Bending strength

Direct shear test

Table 3.2. Physical specifications of different bolt types

Bolt Rib Core Rib


Bolt Commercial Spacing diameter height
name (mm) (mm) (mm)
T1 AX 11.5 21.7 1.0
T2 AXR 11.5 21.7 1.5
T3 JX 24.0 21.7 1.2
T4 9.7 19.6 1.3
T5 1.4 10.3 0.6
T6 N12 7.74 11.7 0.8

3.5.2.1. Tensile strength test

A 33 cm bolt length, was cut and tested for tensile strength by pull testing. A

universal Instron tensile testing machine was used to carry out the tensile test. The

tensile test, on all rebar specimens, were carried out in accordance with the

Australian Standards for tensile tests No AS 1391. A typical tensile test arrangement

is shown in Figure 3.22. The test specimen was installed between the two large grips

of the testing machine and then loaded in tension. The computer-controlled tensile

test loaded the specimen at a constant rate until failure. While the test progressed,

88
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

load and displacement values were monitored by the computer. The load

displacement curves in Figure 3.24 to 3.27 show a typical behaviour of the steel with

elastic behaviour in the beginning of the test and small displacement till yielding

point. Beyond the yield point, the bolt will deform without further increase in the

load until the bolt is strain hardened. Finally the steel bolt fails with contraction of

the cross section area, which is in the form cap and cone known as (necking). It

should be noted that the cable bolt failed by the tensile failure of the individual

strands.

Grips

Bolt

Figure 3. 22. Bolt clamped in Instron Universal testing Machine

As can be seen from the loading profile of the tested bolt (Figure 3.23) the following

features were deduced;

a) Elastic range

b) Yield point

c) Elasto-plastic range

d) Failure range

The yield strength of the steel bar is an important factor in the determination of bolt

tension, thus influences the effectiveness of the bolt performance. It should be noted

89
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

that although a roof bolt of high yield strength is desirable, however, it is use in situ

should be avoided.

The high strength bolt when fails, the bar is most likely to shoot out of the hole with

such high speed that it could severely injure anyone in its path (Peng 1986).

According, the current bolts strength used in mines are of strength 320 kN. The value

of the yield and ultimate failure loads in all types of bolt is described in Table 3.3.

Table 3.3. Bolt tensile strength

Yield Tensile Yield Ultimat


Bolt Point Strength stress e stress
(kN) (kN) (MPa) (MPa)
T1 260 328 683 862
T2 256 342 673 900
T3 210 358 552 942
T4 163 194 518 617
T5 38 44 365 423
T6 57 67 501 593

Necking/Yielding/Failure

T1 T2 T3 T4 T5 T6
Figure 3. 23. Stretching of the bolts after tensile test

90
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

T3
T6
400
. 350
300 T1
Tensile Load (kN)

T5
250 T2
200
150 T
100
50
0
0 20 40 60 80
Displacement (mm)

Figure 3.1. Load- deflection curve at Figure 3.25. Load- deflection curve at
tensile test in various bolts tensile test of Bolt Type T5 and T6

300
250
.

250
200
Tensile load (kN)

Tensile load (kN)


200
150
150
100 100

50 50

0 0
0 5 10 15 0 10 20 30 40 50 60

Displacement (mm) Displacement (mm)

Figure 3.26. Load- deflection curve at Figure 3.27. Load- deflection curve at
tensile test in cable bolt tensile test of Bolt Type T4

3.5.2.2. Three point load bending test

For better understanding of bending behavior of rock bolts used, several bending

tests were carried out in 3PLBT (three point load bending test). Figure 3.28 shows

the three-point load bending test set up. Three types of bolts, which were used for

axial and double shearing tests, were tested under pure bending load by this method.

Three types of bolts, which were tested under pure bending load condition. The

bending behaviour of Bolt Types T1, T2 and T3 is displayed in Figure 3.29. Bolt

91
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Type T1 has the lowest bending strength While Bolt Types T2 and T3 exhibited

higher bending loads

60

50

40

Load (KN)
30

20 AXR
JAB
10 AX

0
0 10 20 30 40

Displacement (mm)
Figure 3.28.Three point load bending Figure 3.29. Load- displacement
test set up behaviour of 3PLBT

3.5.2.3. Direct shear test

The direct shear tests on bolts were carried out guillotine test. The guillotine

apparatus is especially designed for rock bolt testing with replaceable bushing to

ensure proper fit and no possibilities for initial bending of the bolt being tested. The

shear forces are the resultant of the shear stresses distributed over the cross sectional

area of the bolt. These stresses act parallel to the cut surface. Figure 3.30 shows the

average shear load versus shear displacement for Bolt Type T1 and T3 respectively.

Table 3.4 shows the results of direct shear tests two types of bolts. The direct shear

test was conducted in an Instron 8033 Servo Controlled 50 tone Compression Testing

Machine.

92
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

250

.
200

Shear Load (kN)


150

100

50 T1
T3
0
0 2 4 6 8

Shear displacement (mm)

Figure 3. 30. direct shear test trend in Bolt Types T1 and T3

Table 3.4. Specification of bolts shear test

Bolt type Shear Shear strength Displacement


load (kN) (MPa) (mm)
T3 236.3 638.12 6.5
T3 237.2 641.3 6
T3 237 640.8 7.3
Average 236.83 640 6.6
T1 237 641 7.2
T1 241.5 653 7
T1 239.8 648.4 6.6
Average 239.43 647.5 6.93

3.5.3. Resin grout

Epoxy and polyester resins are the most commonly forms of chemicals used in bolt

installation in Australian Mines. The most popular type used is the resin combination

sausage capsule supplied by Minova Australia (formerly known as Fosrock Mining).

A program of strength properties tests was carried out on resin. These include, the

uniaxial compression tests, the double shear tests and modulus deformation tests.

These tests were carried out on slow setting (20 minutes) PB1 Mix and Pour resin.

93
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

The longer duration of setting time was essential to conduct the strength tests. The

diameter of the prepared samples was different for different tests carried out.

a) Uniaxial Compression Test: A uniaxial compression test is the most

common test performed on rock and other types of samples in this case, resin. The

samples prepared for this batch of tests had 50 mm diameter and the length to

diameter tests were in the order of 2.5: 1. The samples were cast in a special plastic

mould specifically fabricated for the test. The tests were accomplished by Instron

machine, 500 kN capacity. A constant displacement rate of 0.25 mm/min was used to

load the samples to failure. In reality, tested samples break similar Figure 3.31 and

sometimes the failure cracks are parallel to axial direction. Figure 3.32 shows the

compression test set up and subsequent tests undertaken. Although simple, care must

be taken when carrying out the test so that errors are minimised, and interpretations

are as accurate as possible. The procedure for conducting a UCS test was carried out

in accordance with International Rock Mechanics Standards. Samples were polished

and cut till the height to diameter ratio 2.5 3 was achieved. Table 3.5 list the details

of the samples tested and the UCS values obtained. A total of seven samples were

tested. The average UCS values were in the order of 70.8 MPa with SD of +/-

XXXX. The UCS Value obtained was in agreement with the manufacturers

specified strength of 71 MPa. Figure 3.33 shows the relationship between stress and

strain in resin. Figure 3.34 displays the load versus displacement. Some of sample

was instrumented with strain gauges to monitor, axial and lateral deformation of the

sample during loading process.

94
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Resin
Sample Fracture
Plane

Hemispherical Angle of
Seating Fracture

Figure 3.31. Typical fracture plane and fracture angle for compression test samples

Strain
gauge

Figure 3.32. Compression test set up

95
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

Table 3.5. Summary of the results obtained from UCS test

Failure load
Sample Length (mm) Ucs (MPa)
(KN)
S1 72.74 146.12 74.42
S3 79.54 142.74 72.7
S4 99 133.5 68
S5 79.5 143 72.7
S6 99 134 68
S7 97.75 136 69
S8 89.8 140 71
Average 70.8

b) Shear Strength: The shear strength tests were undertaken using Double

shear tests using a 50 tone capacity Avery testing machine as shown in Figure 3.35.

The samples were prepared by casting in specially prepared moulds of 32 mm

diameter, which fitted snuggly in the double shear barrel. A total of four tests were

carried out, with the average shear strength value in the order of 16.2 MPA +/- XXX.

Standard deviation. The resin was different with the sausage type as it had setting

time in the order of 20 minutes thus allowing a sufficient time for proper preparation

of the samples for various tests.

80

70
.

60
UCS=73 MPa,
Axial stress (MPa)

50 E= 10500 MPa
40 Poisson
ratio=0.26
30

20
axial
10 lateral
0
-0.03 -0.02 -0.01 0 0.01 0.02 0.03 0.04

strain

Figure 3.33. Stress strain curve for resin

96
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

160

.
140

Compressive load (kN)


120

100

80
60

40
20

0
0 1 2 3 4 5 6

Axial displacement (mm)

Figure 3.34 . Load versus displacement

3.5.3.1. Double shear test

32mm diameter samples of resin were cast in PVC tube to a length of 100mm. Each

sample was placed within the double shear-testing rig and then loaded by the Avery

testing machine until failure at a standard rate of 2.5kN per minute.. The double

shear test rig is outlined in Figure 3.35. There are two shear locations to accurately

determine the shear properties of the material being tested. From the dial reading on

the Avery testing machine, the peak load at failure was read.

A total of four double shear tests were conducted in order to accurately determine the

peak shear force of the resin and to ensure consistency of both testing methods and

results. Sample measurements are shown in Table 3.6.

97
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

32 mm

Location of
Shear Failure

a b

Figure 3.35. Double shear test set up a: shear box set up b: induced loads

Table 3.6. Double shear test specifications

Diameter Sample area Failure load Shear strength


Sample
(mm) (mm*2) (kN) (MPa)
S1 31.95 801.7 25 15.6
S2 31.88 798.2 26.2 16.4
S3 31.95 801.7 28.5 17.7
S4 31.9 800 24.6 15.3
Average 16.2

3.5.4. Concrete

3.5.4.1. Uniaxial compressive strength

Four nominal concrete strengths, 20, 40, 50 and 100 MPa, were used in the double

shearing tests. These strengths compare well with the range of rock strength. From

each batch, which was prepared some cylindrical samples, were cast to measure the

concrete strength. Concrete was tested in compression to ensure that the required

98
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

strength has been obtained. Figure 3.36a & b show the concrete sample during the

test and the concrete blocks after taking out from the water tank.

The modulus of elasticity was calculated from equation which was expressed from

Australia standard AS3600 (1994) and also the typical value of Poissons ratio

specified by AS3600 is 0.2.

(3. 19)
Ec = 0.043 1.5 f cm
A suitable expression, which applies for concrete excess of 50 MPa, has been

recommended by ACI Committee 363 (1992):

(3. 20)
Ec = 3320 f cm + 6900

where;

E c = Modulus of elasticity (MPa)

= Concrete density (kg / m 3 )

f cm = Mean value of the concrete compressive strength at the relevant age (MPa)

a b

Figure 3.36. Concrete sample: a) concrete under the test b) concrete after 30 days

99
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

3.5.4.2. Concrete joint surface properties

In order to estimate the strengthening effects of bolting one has to know the friction

properties of unbolted joints. For this reason, a series of direct shear tests was

performed on specimens of broken and intact concrete, and under a variety of normal

loads. All samples were tested in direct shear, using direct shear machine. By this

method some important parameters can obtain such as, peak shear strength, residual

shear strength, cohesion and angle of internal friction (See Moosavi and Bawden

2003). The specimen properly positioned and then the lower half of the sample was

potted in the shear box ring with the potting compound. After the compound

hardened the appropriate thickness of Plexiglas spacer sheets was placed on top of

the lower shear box to form the shear plane. Whereas, the specimen being tested had

a weakness plane (concrete-concrete interface) it was placed in the shear machine

such that the plane of joint was coincided with the plane of the machine. The friction

angle of joint can be estimated by performing repeated shear tests under different

normal loads. To estimate shear resistance of a joint Barton (1966) developed an

empirical model (Brady and Brown 1985). Which can be written as following.

JCS
p = n tg JRC log10 ( ) + b (3.21)
n

Where, p =peak shear stress, n = normal stress, JRC = joint roughness coefficient,

JCS = joint compressive strength, and b basic friction angle.

From the data analysis it was found that the joint surface cohesion in both concrete

20 and 40 MPa was zero and the angle of friction was 31 and 38 degree respectively

(Figure 3.37 a and b). As Figure 3.38 shows, once the peak shear strength was

overcome, there was considerable loss of shear resistance. From the analysed

100
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

laboratory results the concrete specifications were found as shown in Table 3.7.Also

it was found that the relation between shear stress and normal stress was nearly 0.9 to

1.7 normal stress in 20 and 40 MPa concrete respectively.

5 12
4.5
10

.
.

Shear stress (MPa)


3.5
Shear stress (MPa)

8
3
2.5 6
2
4
1.5
1 2
0.5
0 0
0 2 4 6 0 2 4 6
Normal stress (MPa)
Normal stress (MPa)

a b

Figure 3.37. Variation of peak shear stress versus different normal stress in shear
joint plane in a: 20 MPa and b: 40 MPa concrete

Table 3.7. Concrete joint properties


Ucs Strength Modulus of Poisson ratio Friction
(MPa) Elasticity (MPa) angle(o)
20 21000 0.2 31
40 30000 0.2 38
50 30500 0.2 -
100 40100 0.2 -

25

2.5 kN
20 7.5 kN
5 kN
Shear load (kN)

15

10

0
0 5 10 15 20 25
displacement (mm)

Figure 3.38. Shear load versus shear displacement in joint plane in 40 MPa concrete

101
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

3.5.5. Summary

There is no doubt that the load transfer mechanism in fully grouted bolts is highly

affected by mechanical properties of bolt, surrounding materials, and contact

interfaces. Tensile, bending and shear strengths of steel bolt are the most important

mechanical parameters, which play a great role on load transfer mechanism, when

bolt is axially and laterally loaded. It was concluded that the highest and lowest value

of tensile strength were recorded for bolt Types T3 and T5 respectively. From the

analysing the load- displacement curves, it was found that bolts have three stages of

behaviour in axial loading which includes, elastic, plastic and elasto-plastic.

However, in bending behaviour bolt shows elastic and elasto-plastic behaviour. This

trend continues till failure occurs in the bolt.

The choice of grout is of great importance to access high shear resistance. From the

laboratory tests it was found that the uniaxial compressive strength and shear

strength of resin are approximately 70 and 17 MPa respectively. Thus resin grout can

experience high shear resistance and interlocking effect. This type of resin with

qualified specifications which being used is the main character to transfer the load

from bolt to rock.

Concrete is used in lieu of rocks as regular sample for experimental tests, which are

carried out for bolt purposes. An understanding of mechanical behaviour of concrete

used as surrounding material is essential for the safe and sure design. Bolt bending is

highly affected by rock/concrete strength, especially at the vicinity of shear joint,

which are the critical zones. Thus to find the mechanical properties of involved

materials in experimental tests concrete has major effect on load transfer mechanism

and bending behaviour. Consequently, the concrete properties, especially, uniaxial

102
Chapter 3: Review of shear behaviour of bolts and mechanical properties of the material used

compressive strength, and shear joint parameters are the main factor, which were

accurately found before the relevant tests. The above mechanical properties were

used in the numerical modelling and analysing the experimental data accurately,

which are discussed in the two next Chapters.

103
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

CHAPTER FOUR

FAILURE MECHANISM OF BOLT RESIN


INTERFACE S DUE TO AXIAL LOAD

4.1. INTRODUCTION

In recent years, fully encapsulated rock bolt have become a key element in the design

of ground control systems especially in the Australian coal mining industry. The

main reason the acceptance of fully grouted bolts is that they offered the maximum

shear resistance to bed separation. Load transfer mechanism of a fully grouted bolt is

a function of the bolt surface condition. The surface roughness of bolt dictates the

rate of interlocking between the bolt and the resin surface. Shear stress of interfaces

rather than the grouting material is of great importance in the overall resistance of

rock bolt system. There are limitations to pull test in determining the resistance of

interfaces as stress distribution in the system is significantly affected by the geometry

of the bolt, borehole, the embedment sample and their material properties. These are

the subjects of discussion in this chapter.

4.2. LOAD TRANSFER MECHANISM

During rock movement the load is transferred from the bolt to the rock via the grout

by the mechanical interlocking acting between the surface irregularities at the

interface. When shearing is taking place due to rock movement, the load is

transferred to the bolt by shearing of the grout interface (Serbousek, 1987). The

ability to transfer the load between bolt/grout/rock depends upon several parameters

104
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

such as; resin annulus, grout strength, bolt profile characteristics, rock roughness,

rock strength and the mechanical properties of the steel bolt.

The nature of bolt failure in field test is different from laboratory test. In field test,

the failure is dependent upon the characteristics of the system, the material properties

of the individual elements and anchorage length. Slippage may occurs at either of

rock-grout or grout-bolt interfaces, which is called decoupling behaviour.

Decoupling takes place when the shear stress exceeds the interface strength. In

laboratory test, the failure usually takes place along the bolt-grout interface and if

real rock is used instead of the steel tube as outer casing element, then the failure

may happen along the rock-grout interface and depending on the rock strength. If the

rock is soft then the failure occurs along the grout rock interface, as the mechanical

interlock breaks down at low loads and the frictional resistance comes into account.

In hard rock on the other hand, the mechanical interlock would be dominant. Kilic

(1999) reported that when surface friction of a borehole decrease, slippage occurs at

the grout-rock interface. In addition, when the bolt and borehole length exceeds a

critical length for a bolt size of 21 mm in a 27 mm hole diameter, failure takes place

at the bolt. This has been demonstrated by the laboratory tests (Aziz 2004). Figure 4.1

shows the schematic representation of the influence load transfer generation at the

interface, together with bolt profile configuration. It displays that the mechanical

interlocking occurs when the irregularities move relative to each other (wedges are

created). Surface interlocking will transfer the shear forces from one element to

another. When the shear forces exceed the maximum capacity of the medium, failure

occurs and only frictional and interlocking resistance will control the load transfer

characteristics of the bolt.

105
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

0.75mm

Geometrical configuration of bolt grout interface (bolt T1)




Rock






Grout

Load

Bolt

Figure 4. 1. Sketch of real bolt profile specifications and interfaces

4.3. BOND CHARACTERISTIC

The mechanisms of effective bonding between bolt, resin and rock can be attributed

to adhesion, friction and mechanical interlock. The effectiveness of each parameter

on bond strength is variable and depends on the test conditions. Normally the

effectiveness of adhesion is almost negligible, and this was clearly demonstrated by

sawing axially a column of resin block cast on a bolt as shown in Figures 4.2 a and b.

The cut two halve sections of the resin detached clean from the bolt core surface in

the force applied. Such finding was also supported by the interpretation of the results

106
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

of bolt /resin shearing tests carried out under constant normal stiffness conditions

(Aziz 2003). The bonding strength is almost near zero when the normal stress is

reduced. It should be noted that the frictional effect is also dependent on the bolt

surface roughness as discussed later in this chapter. It is obvious that the applied

confining pressure has a major influence on the level of friction and interlocking

action at the bolt /resin interface. Kaiser et al. (1992) reported that the mining

induced stress change is one of the most important parameters controlling the bond

strength.
Resin peak shear strength
(MPa)

Resin normal confining stress (MPa)

Figure 4. 2. (a) resin/bolt load transfer under various confining pressures (b) resin
bolt separation after post encapsulation

4.4. PULL AND PUSH ENCAPSULATION TESTS

The installation and subsequent performance of bolts in-situ, results in the bolt being

placed in often in both tension and shear. There will be a general reduction in bolt

cross section as a result of bolt tensioning, causing premature bolt resin surface

contact failure and loss of the grip. The common method of evaluating the

competence of any bolt installation is to conduct pull tests on a short section of the

anchored bolt. This encapsulation length is in the order of 300 mm long. Another

method, which has gained acceptance by the industry, is short encapsulation push or

107
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

pull test of a short length of the bolt installed in short steel cylinder tube. This kind of

test is usually carried out in the laboratory, using between 50 to 75 mm steel tube.

Concerns are often raised about the validity of the short encapsulation push test as it

does not realistically reflect on the true load transfer capability of the bolt/grout

interface. The sort encapsulation push test was developed to examine the peak load

transfer performance, without due consideration given to the possible reductions in

bolt diameter, due to pushing, which would influence the load transfer mechanism.

By pushing the bolt out of the cylindrical steel tube it would contradict the realities

of bolt functioning in-situ. The shear load developed at the bolt/ grout interface

would be in compression rather than in tension. In contrast, the short encapsulation

pull testing is considered as a more acceptable method of testing as the pulled bolt is

undergoing extension and deformation, similar to in-situ bolt condition.

Accordingly, a series of short encapsulation pull and push tests were undertaken on

three common types of bolts to examine the influence of test method on load transfer

characteristics of the bolt. These bolts were known as T1, T2 and T3 Bolt Types. For

obvious reasons all three bolt types were given identification designations. The general

characteristics of the various bolts were discussed in chapter 2. The following

parameters were examined under both pull and push test conditions:

1. Bolt-grout bond strength between bolt-grout in various bolt profiles

2. Rock-resin bond strength between rock-resin interact the interface

3. Bond stiffness between grout and bolt interface

4. Bond stiffness between rock-resin interface

108
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

Bond strength and bond stiffness between bolt and grout are best determined by

laboratory tests and the bolt/grout interface is the main bond in encapsulation pull

and push tests. However, bond and stiffness strength between grout and rock can be

determined in the field.

4.4.1. Push Encapsulation Test

Figure 4.3 shows the details of the short encapsulation push test cell. The cell is 75

mm long, which is 50% greater than that reported by Fabjanczyk and Tarrant (1992),

50 mm long steel tube. The longer length cell was selected in order to permit a

sufficient number of bolt surface profiles to be encapsulated in the cell. The cell

consisted of a machined steel cylinder tube with an internal groove. The groove

provides grip for the encapsulation medium and prevents premature failure on the

cylinder / resin interface. As opposed to pull testing, push testing involves pushing of

the bolt under constant normal load conditions through the hardened resin. With the

use of a digital load cell and LVDT, a full load / displacement history could be

obtained. All the bolt samples were each cut to lengths of 120mm using a

mechanised saw. The equal lengths ensured that all the samples of the same type had

an equal number of profile ribs and that the ends of each sample were square. All

bolts were encapsulated into the push test cells using Minova PB1 Mix and Pour

resin grout. The grout and bolt properties are illustrated in Table 4.1. As can be seen

from Figure 5.4 the bolts were centrally located with uniform resin annulus

thickness. Every effort was made to ensure the bolts were set axially parallel to the

hole axis. Figure 4.5 shows post-test sheared bolt out of the steel tube. All failures

occurred along the bolt grout interface

109
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

Universal platen

Bolt

Test cell
75 mm
LVDT

Spacer ring

27 mm Load cell
48 mm

Figure 4. 3. (a) The actual push test configuration (b) the shematic of the test

Table 4.1 Grout and steel properties

Parameter Grout Steel

UCS (MPa) 71 -
Ave. Shear strength
16.2 600 (tensile test)
(MPa)
E (Gpa) 12 200
Poisson ratio 0.25 0.3

Figure 4. 4. Preparing the bolt resin samples

110
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

Figure 4. 5. Post-test sheared Bolt Type T2 out of steel cylinder in push test

4.4.2 Pull Encapsulation Test

In order to encounter the much criticism of the push test, a series of short

encapsulation pull tests were then under taken using the same 75 mm steel tubes.

Each tested bolt was cut to a 300 mm in length, and Figure 4.6 shows the general set

up of pull testing. As can be seen from Figure 4.7 a and b, the grout is clearly been

sheared off within the ribs of the bolt, which is a clear indication of the shear failure

across the grout annulus.

The pulling force and displacement were measured by pressure and displacement

gauges automatically as they were interfaced with a data logger and a PC. The load

and displacement were incrementally recorded at every 0.2 kN until the failure

occurred in bolt/grout interface.

As can bee seen from the load displacement values, there was a significant reduction

in the peak load values in comparison to failure by push test. For bolt T1 the

reduction was 11%, and for T3 it was 7%. Also the failure loads were higher in T2

bolts. There are a number of reasons for the reduction in pulling load as compared to

111
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

push test, and these are further analysed later in the chapter. Additional figures of

the tested samples are listed in Appendix A.

Figure 4. 6. Pull test arrangement

(a) Steel sleeve (b) Bolt

Figure 4. 7. Post-test sheared bolt out of steel cylinder

4.5. DISCUSSION

Table 4.2 shows the load transfer pull and push test results of all three bolts. Figures

4.8 and 4.9 show typical load-displacement graphs of both pull and push test results

112
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

respectively. Additional results of tests are listed in Appendix A. All profiles are

characterized with an initial linear load-displacement zone, the peak shear load or

failure zone and the post peak displacement or failure zone. Post peak load /

displacement profile was considered plastic stage as the bonding has failed between

the bolt and resin. It must be stressed that the load displacement relationship of

pull/push test of bolt/resin interaction cannot be considered as elasto-plastic

relationship similar to loading to failure of a steel bar. This is because the load

displacement of the bolt/resin/rock combination is merely concerned with shearing of

the bolt from resin and hence involves separating one material from another. The

general load-displacement profiles were the same for all three types of bolts tested.

Bolt Type T3 has higher shear load and lower stiffness, its post peak load-

displacement profile was, in general, higher than the other two Bolt Types T2 and T3

respectively. This is an advantage for Bolt Type T3, as it is considered to tolerate

greater displacement before reaching the peak load, and hence is considered as an

advantage in soft coal measure rock reinforcement. Each of the Bolt Types T1 and

T3 has greater stiffness than Bolt Type T3 and thus accommodates less displacement.

They are considered as an effective support system in strong and competent rocks.

Thus the bolt anchorage stiffness is important factor prior to the bolt-grout bond

failure. Figure 4.10 provides an explanation of the load displacement profile

behaviour.

113
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

Table 4.2. The load transfer laboratory results of the bolts in both pull and push tests

Measured parameters Pull Push

Bolt type Bolt type

T1 T2 T3 T1 T2 T3

Ave Profile Height (mm) 0.75 1.35 1.2 0.75 1.35 1.2

Ave Profile Spacing (mm) 11.0 12.0 23.5 11.0 12.0 23.5

Ave Max Load (kN) 114.8 131.7 160 129.2 139.2 172

Ave Max Displacement


4.10 4.55 8.2 3.3 3.86 7.4
(mm)

Ave Shear Stress Capacity


22.2 25.4 30.9 24.8 26.85 33.6
(MPa)
Maximum effective shear
23.8 26.6 35.6 25.7 30 37.8
stress capacity (MPa)*
Average System Stiffness
28.3 28.93 19.5 39.1 36.3 23.2
(kN/mm)

180

160 T1
T2
T3
140
.

120
Shear load (kN)

100
80

60

40
20

0
0 5 10 15 20 25 30

Bond displacement (mm)

Figure 4. 8. Shear load as a function of displacement in pull test

114
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

200
180
T1
160 T2
T3

.
140

Shear load (kN) 120

100
80
60
40
20
0
0 5 10 15 20 25

Bond displacement (mm)

Figure 4. 9. shear load as a function of displacement in push test

Exceeds shear
strength point
Action wedge
Interlocking and friction
effect
Axial load

Bond failure

Elastic behaviour

Axial displacement

Figure 4. 10. General trend of push and pull test view

4.5.1. Effect of bolt profile

The magnitude of the shear stress and stiffness developed along the bolt/resin/rock

interface is influenced by the bolt profile configurations. Both bolt profile spacing

and profile height are important parameters which affect the level of load build up

115
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

along the bolt /grout interface, pre and post peak load. After decoupling, different

profiled rock bolts, behave differently. This is clearly illustrated by the load

displacement graphs shown in Figures 4.8, and 4.9.

High post-peak load residual strength feature, at the resin-bolt interface, was found to

suit Bolt Type T3 in soft formations, such as coal measure rocks, as it accommodates

greater rock deformation than the other two closely spaced bolts. Bolt Type T2 had

higher profile height than Bolt Type T1. From pull and push test results it was

found that, the higher profile bolt, with same spacing had higher level of both load

transfer capacity and stiffness values. The shear stiffness caused the transfer of the

load from one layer to another. It was found that the larger the rib, the greater was

the failure load of the rock bolt. Moreover, the higher load transfer, the greater was

the load developed over a relatively short encapsulation length of the bolt.

The total bonding failure was considered to occur, when the shear stress exceeded

the shear strength. From Figures 5.8 and 5.9 it can be seen that Bolt Type T1 before

achieving peak load was slightly higher in shear stiffness. A strong interaction

between the bolt and the grout has attributed to this high level of stiffness. From the

shear load versus shear displacement in all types of bolts it is understood that in the

Bolt Type T3, the final bond has failed at about 7-8 mm of displacement which is

nearly double to that obtained from other bolts with profile spacing 50% of the Bolt

Type T3 spacing. Such level of performance was also true to shear resistance of all

bolts tested of the same type. However, shear displacement before failure was larger

for bolt type T3. The main advantage of Bolt Type T3 is that, shear load is gradually

decreased after failure, which is suitable for soft ground conditions.

The profile spacing of the bolt was found to have significant influence on load

transfer characteristics. As stated before, the increased profile spacing allowed

116
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

greater displacement at peak load and increased load transfer at post peak range as

well. Figure 4.11 shows the relationship of shear load and rib spacing. This

relationship was based on the analysis of the laboratory test results shown in Table

5.2 in Appendix A.

a
Tmax = 52.6 ln( Ds ) 5.27 0.05 < < 0.12 (4.1)
Ds

where;

Tmax = The peak shear load at bolt-grout interface (kN)

a = Height of rib

Ds = Rib spacing

250

200
.
Shear load (kN)

150

100

50

0
0 5 10 15 20 25 30 35
Rib spacing (mm)

Figure 4.11. The effect of Rib spacing on shear load

No studies are carried out to examine the effectiveness of profile spacing beyond 25

mm range as reported in this thesis. Bur all indications suggest that, at greater profile

spacing beyond 25 mm range there will be a gradual decline in the effectiveness of

the bolt load bearing characteristics with increased spacing as extrapolated in Figure

117
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

4.11. Similarly, no studies been carried out to determine the effectiveness of closer

spacings less than 12 mm. It is however sufficient to report that reduced spacing

would lead to reduced load transfer characteristics of the bolt irrespective of bolt

profile height. This statement can be supported by the loss of peak load and reduced

post peak load displacement shown in Figure 4.12. This was also reported by Aziz

and Webb (2003).

20
18
16
.

14
Shear load (kN)

12
10
8
6
4
2
0
0 1 2 3 4 5 6

Shear displacement (mm)

Figure 4. 12. The shear load versus shear displacement in smooth bolt

4.5.2. Bolt yielding/necking

In all the tests, slip and yield occurred at the bolt grout interface and there was not

physical failure of the bolt. Bolt yielding and necking was unlikely to occur in bolts

tested in 75 mm long steel sleeves as the level of load applied actually was around

40% of the maximum tensile strength of the steel, which is far less than that required

for the bolt to yield. For the bolts to undergo necking it must be gripped firmly at

both ends. However, it should be noted that by pulling the bolt, the diameter of the

118
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

bolt continues to reduce along the bolt length and results into elongation according to

Poisson effect. The elongation characteristics of the bolt would obviously affect the

load transfer capacity of the bolt. Figure 4.13 shows the process of debonding in pull

test. The excessive tapering of the bolt end drawn on the pull side is merely intended

to show the possible small reduction in bolt diameter and is not aimed to depict bolt

necking. This debonding and bolt reduction occurs after the load displacement rises

linearly in the bolt. Based on the numerical analysis discussed later in Chapter 7

there is a high level of load induced in top head of the bolt, which is reduced

exponentially along the bolt. By increasing the load, the debonded area propagates

and expands proportionally. From this time, the load decreases and hinge point in the

curve, is named the maximum bearing capacity of the bolt, is formed. After the peak

point, the shear load - shear displacement depends upon the interlocking phenomena,

which is function of bolt profile specifications, resin grout properties and resin

thickness.

During pull testing of the bolt, the embedded or encapsulated bolt section in the steel

sleeve enclosure would undergo a gradual reduction along its length, being relatively

greater at the pulled side of the bolt, gradually reducing towards the bottom and free

end. The reduction or increase in the bolt cross-section would depend on the test

type, which is whether the test was carried out in pull or push. Such difference in

diameter change would obviously affect the level of pulling or push force required to

mobilize bolt shear.

119
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

Excessive bolt tapering


drawn for clarity

Pull load

Debonding

Figure 4. 13. Debonding at pull test

4.5.3. Effective Shear Stress at the Bond Interface

Effective bond shear strength capacity ( E ) is calculated by Equation 4.1. E is

calculated by the load at each step divided by the surface area of the bolt grout

contact interface. The contact bond length reduces with increasing the load, and this,

obviously affect the shear strength value.

Load ( N )
E ( MPa ) = (4.2)
D ( L u )

where;

D= the bolt diameter,

L= the embedded length and

U = the shear displacement at each step of loading.

Based on the double shear tests on cylindrical resin samples, (see Chapter 5), and the

above results, the pure resin shear strength at the bolt grout interface is between 45 to

120
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

70 % of the maximum shear strength generated. The reason is, the bond strength is

affected by the combination of shear and compressive strength of the resin grout,

which has come to act during the interlocking process. It is known that the

compressive strength of the grout is around 70 MPa, which is approximately 5 times

of the grout shear strength. Therefore, the bond strength of the ribbed bolt is between

5 to 8 times of the smooth surface bolt depends upon the profile characteristics.

Figures 4.14 and 4.15 show the shear stress developed along the bolt/grout interface

in both push and pull tests respectively. The minimum and the maximum yield

stresses occurred at the lowest and highest rib profile Bolt Types T1 and T2

respectively. However, the maximum shear strength generated in bolt / grout contact

interface was induced in Bolt Type T3. Such high values were considered to be

attributed to the effects of both the rib height and rib spacing causing greater

interlocking effect (see details in Appendix A).

40

35
.

30
Shear stress (MPa)

25 T1
T2
T3
20

15

10

0
0 5 10 15 20 25

Bond displacement (mm)

Figure 4.14. Shear stress versus bond displacement in Push test

121
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

40

.
35 T1
T2
T3

.
30

Shear stress (MPa)


25

20

15

10

0
0 5 10 15 20 25 30

Bond displacement (mm)


Figure 4.15. Shear stress versus bond displacement in pull test

The point where the shear load tapers away at the end of the range is defined as the

yield load. The yield and failure stress, elastic and peak shear displacements are

shown in Appendix 4.1. Table 4.3 shows various strength properties laboratory

results in both pull and push test results for three bolt types.

Table 4.3. Comparison of the laboratory results in pull and push tests

Type Ave. Ave. Peak Ave. Diff Ave. Peak Ave. Peak Ave.

of bolt Peak pull push load % disp in disp in Diff

load (kN) (kN) pull (mm) push (mm) %

T2 131.7 139.2 5.4 4.55 3.86 15.16

T1 114.8 129.2 11 4.1 3.3 19.5

T3 160 172 7 8.2 7.4 9.75

122
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

The following were deduced from Tables 4.2 and 4.3 results:

1. The average shear load values in push test were greater than the pull test,

irrespective of the bolt type,

2. The average shear stress capacity of the bolt in push test was in general

greater than the pull test,

3. The displacement at peak shear load were greater in pull test,

4. The shear stiffness of resin / bolts interface is an important factor in resisting

shear along the joint planes. As a consequence, the average system stiffness

for various bolts was greater in push than in pull tests. The difference in the

average stiffness values between push and pull tests, for all three Bolt Types

T1, T2 and T3, were in the order of 27.6, 20.3, and 16 % respectively.

5. The profile spacing appears to play a significant role in load transfer

mechanism characterisation for different bolts, and this supports the earlier

study findings under constant normal stiffness conditions reported by Aziz

(2002).

6. Bolt Type T3 can resist 25 % higher shearing force than Bolt Type T2. The

maximum peak load in Bolt T3 occurred at greater displacement. In residual

behaviour almost all bolts have the same trend in load displacement.

However, the residual shear load in Bolt T3 was twice than that of Bolt T2.

7. Bolt Type T3 losses its grip much more gradually than the other two bolts.

This is an advantage particularly in softer formation. In a way, it behaves in

an elasto-plastic manner.

123
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

4.5.4. Bolt core behaviour subjected to axial loading

In order to understand the bolt core behaviour during the shearing and also to

evaluate the Poisson effect in both pull and push tests, the mathematical calculation

was used and elastic parameters were calculated. Basically, when load is applied to

the bolt, it stretches in axial direction and contracts in the lateral direction because of

Poisson effect. When contraction occurs, the bond initiates breaking at the interface.

The stretching and contractions are calculated in both pull and push tests during

loading process. Table 4.4 shows the poison effect calculations in all three types of

bolts. There are small changes in axial and lateral strain values in push and pull test

results in all types of bolt. As expected, the pull test caused a diameter reduction

while push test caused diameter increase.

Table 4.4 axial and lateral strains along the bolt in pull and push tests

Max. Axial Diameter Lateral


Bolt Type Stress strain reduction strain
(MPa) (%) (mm) (%)
T1 302 0.151 0.008 0.04
Pull T2 346 0.173 0.011 .052
T3 421 0.21 0.013 0.06
T1 340 0.17 0.011 +0.051
Push T2 366 0.18 0.011 +0.054
T3 452 0.22 0.014 +0.066

4.5.5. Effect of annulus

In an endeavor to examine the role of increased annulus encapsulation thickness on

resin anchorage strength, a comparative push test was made using two different

encapsulation thicknesses in equal length steel tubes. One tube had the internal

diameter of 27 mm while the other had 45 mm internal diameter. As can be seen in

124
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

Figure 4.16 there was a dramatic reduction in pulling force between the two-

encapsulation thicknesses (48 % reduction in load when annulus increases from 3.5

mm to 11 mm). In both cases the same profile type of bolt was used. As reported by

Campoli et al (2002) the size of the resin annulus is one of the critical variables

affecting resin bolt performance. Hagan (2003) found that there is little significant in

shear load with resin annulus size of 4 mm or less. Hagans results showed there is

26% reduction in shear load with annulus from 3 mm to 5 mm. Ulrich (1991) found

the optimum annulus thickness is 3.1mm in 25.4 mm hole diameter.

Push test, ID= 27mm v ID 45 mm in short encapsulation


push test
T2 ID 27mm
160
T2 ID 45mm
140
120
Shear Load (kN)

100
80
60
40
20
0
0 5 10 15
Displacement (mm)

Figure 4.16. Annulus thickness effect

4.6. SUMMARY

Short encapsulation pull test represent a better and a realistic method of

evaluating the load transfer mechanism of bolt in comparison with the pull test

method.

Bolt profile configuration is an important parameter in load transfer capacity

of bolt. Both profile height and profile spacing have important and distinct role

125
Chapter 4: Failure mechanism of bolt resin interfaces due to axial load

for bolt integrity. Profile spacing dictates the level of peak load displacement,

which intern accommodates a relatively greater level of strata movement. Such

characteristics of wider spaced profile bolts like Bolt Type T3 make them

suitable for strata reinforcement in soft rocks like coal measure rocks. Increased

profile spacing beyond 25 mm has not been tested experimentally but is likely to

act detrimentally to bolt performance. Like wise the reduction of bolt profile

spacing below the tested range of 12.5 mm would not be beneficial for bolt

performance.

High profiles increases load transfer capacity of the bolt.

Yielding and necking is unlikely to occur in bolts tested in 75 mm long steel

sleeves as the peak shear load was around 40% of the maximum tensile strength

of the steel. For the bolts to undergo necking it must be gripped firmly at both

ends.

The average shear stress capacity of bolt in push test was greater than the pull

test. However the shear stiffness of the bolts were generally lower with pull test

in comparison to push test.

Bolt- resin interface failure occurred by initially shearing of the grout at the

profile tip in contact with the resin. Naturally, the load failure of the resin / bolt

surface contact is dependent on the profile height as well as spacing.

Increasing resin annual thickness reduces the load transfer capability of bolt,

and is also detrimental economically. Therefore it would be beneficial to install

the bolts effectively if the annulus resin thickness is kept to minimum.

126
Chapter 5: Double shearing of bolts across joints

CHAPTER FIVE

DOUBLE SHEARING OF BOLTS ACROSS JOINTS

5.1. INTRODUCTION

Bolts installed in jointed rock undergo axial and shear loading when sheared. Figure

5.1 shows a typical bolt bending due to bedding displacement. To gain a better

understanding of the effectiveness of bolt reinforcements, a series of laboratory

based double shear tests were carried out. Using different bolt types, and different

concrete strengths, the study examined the influence of various parameters on the

load transfer characteristics of different bolts in strata reinforcement installations.

Rock Bolt

Inside failure
Shear failure
Normal load

Joint separation

Shear force
Local crushing
Segregation
Shear fracture Rotation

Pretension load

Figure 5. 1. Bolt bending behaviour (after Indraratna et al. 2000)

127
Chapter 5: Double shearing of bolts across joints

5.2. EXPERIMENTAL PROCEDURE

5.2.1. Block Casting

Double-jointed concrete blocks were cast for each double shearing test. Four

different strengths concrete blocks were cast, 20MPa and 40MPa, 50MPa and

100MPa strengths to simulate four different rocks. The solid ingredients components

of the concrete comprised mainly sand and cement, and occasionally aggregates were

also added. The concrete mix for the low strength batch consisted of ordinary

Portland cement, mixed with Nepean River sand. However, in higher strength

concrete of 50 and 100 MPa, aggregate was added to the mix.

Once mixed the concrete was poured into greased wooden moulds measuring

600mm x 150mm x 150mm,which were divided into three sections separated by two

metal plates, A length of plastic conduit 24 mm in diameter was set through the

centre of the mould lengthways to create a hole for the bolt. Figure 5.2shows the

general view giving the actual dimensions of concrete blocks used for double

shearing tests. The concrete was left for 24hrs to set and then removed from the

moulds and placed in a water bath for a period of 30 days to cure. The plastic

conduit was removed from the centre of the blocks and the hole was reamed to the

desired hole size, ready for the appropriate diameter bolt installation. The purpose of

the reaming the hole to larger diameter was to produce rifled hole surface for

effective bolt installation anchorage. Rifling was achieved by a specially machined

tip of a wing bit shown in Figure 5.3.

128
Chapter 5: Double shearing of bolts across joints

Symmetric planes
Shear joint
Shear joint

150 mm

150 mm

150mm

300mm

Figure 5. 2. Laboratory and numerical model

Figure 5.3. Hole reaming for hole rifling

129
Chapter 5: Double shearing of bolts across joints

5.2.2. Bolt Installation in Concrete Blocks

1400 mm long bolt, threaded 100 mm on both ends was then fixed in the concrete

specimen using Minova PB1 Mix and Pour resin grout. Prior to bolt installation, the

concerete blocks were clamped together with straight metal pieces place down the

sides to keep the blocks lined up and even. The blocks were placed in an upright

position and a series of rubber stoppers and steel plates, were attached to the concrete

hole-end to prevent the resin from pouring out from the bottom of the vertically

assembled block. The rubber stopper had a hole that the rock bolt could fit through,

thus allowing minimal resin escape. A funnel was placed over the top of the hole to

guide resin and reduce spillage. In addition, two thick steel rings were inserted at the

top and bottom of the hole collars to keep the bolt centrally positioned.

Care was taken to ensure the encapsulation resin fully mixed for maximum strength.

The rock bolts had their threads taped up to prevent the resin from clogging up the

thread. Initially the resin was poured in the hole and the bolt was then pushed

through the stopper plates. Further resin was applied as required while rotating the

bar to reduce the possibility of voids and filling the space between the bolt and the

sides of the hole along the entire length of the bolt through the blocks.

The instruction for resin mixing proportion was 100 grams of resin against 2 grams

of catalyst. Care was taken to install all the bolts in their respective concrete blocks

with uniform profile /flash orientation. The bolted blocks were left for at least half an

hour to allow the resin to cure before moving them for the place of storage. Most

bolted specimens were left to cure for a minimum of seven days before being

mounted on the steel frame double shear box and tested.

130
Chapter 5: Double shearing of bolts across joints

5.3. DOUBLE SHEAR BOX

Figure 5.4 shows the steel frame shear box. The three section box was made from

20 mm steel plates machined into three box, and held assembled with a total of

34 cap screws, each 300 mm thread length. The box plates were cad coated to

prevent them from corrosion. When assembled the internal dimension of the

shear box was such that the concrete specimen fitted snugly in the shear box.

One of the unique features of double shear system was that it was a symmetric

system of load application and shearing of the bolt. This symetricity was relevant

particularly when the bolt was subjected to axial loading.

Figure 5.4. An assembled bolt fitted with load cells on both ends of the bolt

5.4. TESTING

Figure 5.5a shows the sketch of the double shear box and bolt bending. Figure 5.5b

shows the assembled shear box in 5000 kN capacity Avery testing machine. A base

platform that fitted into the bottom ram of the testing machine was used to hold the

shear box between the loading plates. Steel blocks about 55mm thick were placed

beneath the two outer concrete blocks to allow for centre block vertical displacement

when sheared. The two outer ends of the shear box were then clamped tightly with

131
Chapter 5: Double shearing of bolts across joints

the base platform to avoid toppling of the blocks during shearing. A predetermined

tensile load was applied to the bolt prior to shear loading. This acted as a

compressive/confining pressure to simulate different forces on the joints within the

concrete. The predetermined tension loads were 0, 5 KN, 10 KN, 20KN, 50KN and

80KN. The maximum applied pretension load was nearly 40% of the maximum

tensile strength of the bolt. Axial tensioning of the bolt was accomplished by

tightening simultaneously the nuts on both ends of the bolt manually. Simultaneous

manual tensioning was preferred on mechanical /hydraulically operated loading so

that equal loading of the bolt can be maintained on either side of the bolt, thus

avoiding any possibility of differential loading application at any stage of the bolt

tensioning, which could influence the encapsulation integrity. The applied axial loads

were monitored by two hollow load cells mounted on the bolt on either side of the

block. During testing, load-cell readings were taken every 10 kN at 0.04 sec /minute

loading rate. The outer sections of the shear box remained fixed as the central block

was pushed down.

Double shear testing was carried out using either 500 kN capacity Intestron

Universal Testing Machine (Figure 5.6) or 5000 kN Avery Testing Machine (Figure

5.5 b). The selection of the machine type was dependent on the bolt type and extent

of bolt shearing range required.

Information gathered from the test included the applied load, bolt vertical

displacement, axial load generated on the bolt due to shearing. It must be stressed

that the axial load cell readings were manually read from GEOKON read out unit

strain indicator P-3500, made from Vishay measurements group, and then processed.

132
Chapter 5: Double shearing of bolts across joints

Tensile zone

Compression zone

a b

Figure 5.5. Schematic of post failed assembled shear box (a), and a set up of the high
strength capacity machine -Avery machine (b)

I will fix it
later G

A Load cell E
Load cell
F Shear Box G
Bolt
Figure 5.6. The set up of the Instron machine with load cell connection

133
Chapter 5: Double shearing of bolts across joints

5.5. BOLT TYPES

Six types of bolts were tested in various combinations with respect to the concrete

strength, and are shown in Figure 5.7. These bolts were of different diameters and

profile configurations as shown in Table 3.2 in chapter 3.

T1 T2 T3 T4 T5 T6

Figure 5.7. Different bolt types

The range of double shearing tests carried out in this programme of study

consisted of the following:

a) Testing of bolts in 20 MPa concrete, representing soft rocks

b) Testing of bolts in 40 MPa concrete representing medium strength rocks

c) Testing of bolts in 100 MPa concrete representing high strength rocks

d) Testing of bolts in different encapsulation annual thickness

e) Testing of bolts without resin thickness

f) Strain gauge installed along the bolt

g) Testing of bolts for complete failure

f) A comparative study of bolts of different diameters.

134
Chapter 5: Double shearing of bolts across joints

g) Bolt contribution in different bolt characteristics

All the above tests were carried out under different pretension loads as stated

previously. Tables 5.1 to 5.3 show various tests conducted in different concrete

strengths combinations and the number of tests for each bolt type in different

pretensioning. It shows a total of 72 bolts in different situations were tested.

Table 5.1. Experimental Schedule indicating the number of samples tested per bolt in
20 MPa concrete

Pretension load (kN)


Bolt Type Total Remark
0 20 50 80
T1 2 9* 2 2 15 *7 out of 9
tests on Bolt
T2 2 2 2 2 8 Type T1 were
T3 - 2 2 2 6 tested in
different resin
Total 4 13 6 6 29 thickness

Table 5.2. Experimental Schedule indicating the number of samples tested per bolts
in 40 and 100 MPa concrete

Pretension load (kN) Total Comments


Bolt Strength
Type (MPa)
0 20 50 80
40 2 2 2 2 8 With resin
T1 40 2 1 1 1 5 Without resin
100 1 1 1 1 4 With resin
T2 40 3 3 2 2 10 With resin
T3 40 2 2 2 2 8 With resin
T4 40 1 - 1 - 2 19 mm bolt
Total 12 9 11 8 40

135
Chapter 5: Double shearing of bolts across joints

Table 5.3. Experimental Schedule indicating the number of samples tested per bolts
T5 and T6 (low strength steel) in 40 MPa concrete

Pretension load (kN)


Bolt Type Total
0 5 10
T5 1 2 2 5
T6 0 0 1 1
Total 1 2 3 6

5.6. RESULTS AND DISCUSSION

5.6.1. Shear Load and Shear Displacement

5.6.1.1. Profile description

Figure 5.8 shows a general load-displacement profile of the double shearing test.

Three distinct stages of the shear profile is shown. This is similar to the profile three-

point load bending of a steel bar. These are; elastic stage, non-linear stage and

plastic stage. Generally, the profiles are of similar configurations irrespective of the

test conditions, however the level of the load build up and the resultant

displacements were found to be influenced by various factors, such as; Bolt diameter,

concrete strength, profile configuration, resin thickness and bolt axial pretension.

i) Elastic Stage

This part of the graph is associated with the elastic behaviour of the sheared system.

The sheared joint surfaces start sliding against each as the shear load applied. This

linear section of the graph is characterised with a rapid increase of the shear load at a

relatively small displacement of less than 5 mm. On most cases the highest stiffness

and the elastic recovery of the system, upon the removal of the shearing load, will

136
Chapter 5: Double shearing of bolts across joints

depend on the level of the confining pretension load initially applied on the bolt.

There will be some minor fracturing of the grout /concrete, while is not significant to

cause the loss of bonding. The displacement level at the elastic yield stage reduces as

the bolt pretension load increases

400

350

300
.
Shear load (kN)

250
3
200
2
150
100

50 1

0
0 10 20 30 40 50

shear displacement ( mm )

Figure 5.8. Typical shear displacement profile of the sheared bolt

ii) Non-linear Stage

This stage is the transitional zone between the elastic and plastic zones. It is also

called the elasto - plastic stage. There is a sharp drop in the rate of shear stiffness

post the peak elastic yield load (P). The displacement / deflection at this stage can be

the same rate or slightly greater than the linear stage section of < 6 mm and also

depends upon the strength of material, bolt profile type and axial pretension load

level. The system stiffness decreases towards the plastic range and the bolt undergoes

irreversible bending particularly post peak yield point (P). Occasionally, a small drop

in the shear load values occurs beyond the elastic peak yield load point. This is due

137
Chapter 5: Double shearing of bolts across joints

to the axial fractures developing in the concrete and along the bolt axis. The elastic

peak yield point (P) is likely to occur at reduced displacement with increased bolt

pretension.

iii) Plastic Stage

The plastic limit of the bolt is characterised by low rate of shear loading at increased

vertical displacement, in other words the low stiffness of the system. The hinge

points are clearly created in the bolt on both sides of the shear joint because of the

reduced shear stiffness. Concrete and grout are completely damaged at the

compression zones with excessive fracturing along the bolt axis in all three blocks

(Figure 5.19).

5.6.1.2. Shear loading for a limited displacement

Tables 5.4 and 5.5 show the test results of three types of bolts tested in both 20 and

40 MPa concrete in different pretension loads. Also included in the table are test

results of non-pretensioned bolts (i.e., 0 kN pretension load). The load-displacement

profiles of the tests conducted on three types of bolts T1, T2 and T3 are shown in

Figure 5.9 (a-f). Figure 5.10 (a-f) shows the comparative shear load and vertical

displacement (deflection) profiles in both 20 and 40 MPa concrete medium for the

given pretension loads as indicated. Individual comparative results between 20 and

40 MPa in different profiles bolt are presented in Appendix B. However, Bar charts

5.11 shows the comparative results in different bolt type and concrete medium.

Additional tests on Bolt Type T4 are listed in Appendix B.

138
Chapter 5: Double shearing of bolt across joints

Table 5.4. Yield point shear load values for different bolts under different environment

Concrete Pretension Shear load at yield Shear displacement at Shear stiffness Comments

Strength load (kN) point (kN) yield point (mm) (kN/mm)

(MPa) Type Type Type Type Type Type Type Type Type Type Type Type

T1 T2 T3 T1 T2 T3 T1 T2 T3 T1 T2 T3

- - - - Hole diameter 27
0 102 71 3.3 5.53 12.83
22.4 mm
20 110 160 80 4.9 7.75 6.5 20.6 12.3
20 26.3
50 150 190 140 5.69 8.2 4.8 23.2 29

80 200 218 160 4.58 5.8 2.92 43.6 37.5 54


25 Hole diameter 27
0 116 160 157 4.6 5.13 5.4 31 29
mm
52
20 173 240 240 3.3 5.84 3.65 41 65
40 49
50 205 240 300 4.2 4.86 3.86 49 77
- - 64 -
80 280 260 4.34 5.23 50

139
Chapter 5: Double shearing of bolt across joints

Table 5. 5. Yield point shear load values for bolt Type T1 under different environment
Concrete Pretension Hole Shear load at Shear load Shear Shear Shear Comments

Strength (MPa) load (kN) diameter yield point at failure displacement at displacement at stiffness

(mm) (kN) point (kN) yield point (mm) failure (mm) (kN/mm)

20 25 163 6.23 26
762 91.7
Bolt diameter
20 27 168 5.83 29
813 80.7
21.7 mm
20 20 28 177 5.37 33
821 86
36
20 198 756 4.57 75 43
25 Without Tests
0 85 7.6 11.18
- - end carried
plate out
0 25 110 7.4 14.86 without
- -
40 resin
20 25 212 12 17.6
- -
50 25 209 8.86 23.6 With
- - end
80 25 274 10.57 26 plate
-
100 Tests carried out in 0, 20, 50 and 80 kN and are discussed in related section

140
Chapter 5: Double shearing of bolts across joints

450 600
400

.
.
500
350

Shear Load (kN)


Shear load (kN)
300 400
250
300
200
150 20kn 200
100 50KN 20 kN
80KN 50 kN
0 kN 100
50 80 kN
0 0 kN
0
0 20 40 60 80 100 0 10 20 30 40 50
shear displacement ( mm ) Shear displacement ( mm )

(a) Bolt Type T1 in 20 MPa concrete (d) Bolt Type T1 in 40 MPa concrete

400 600

Shear Load (kN) .


.

350 500
Shear load (kN)

300
0kN 400
250
50kN
200 80kN 300
20 kN
150 200 20kN
100 50kN
100 80kN
50 0 kN
0 0
0 10 20 30 40 50 0 10 20 30 40 50

Shear displacement (mm) Shear displacement (mm)

(b) Bolt Type T2 in 20 MPa concrete (e) Bolt Type T2 in 40 MPa concrete

400 600
Shear Load (kN) .

Shear load (kN) .

500
300
400

200 300

200
20kN
100 80kN 20 kN
100 50 kN
50 kN 0kN
0 0
0 10 20 30 40 50 0 10 20 30 40 50

Shear displacement (mm) Shear displacement (mm)

(c) Bolt Type T3 in 20 MPa concrete (f) Bolt Type T3 in 40 MPa concrete
Figure 5.9 (a-f). All bolt shear load and vertical displacement profiles in both 20 and
40 MPa concrete medium

141
Chapter 5: Double shearing of bolts across joints

400 600

.
350

.
shear load (kN) 500
300

Shear load (kN)


250 400
200 300
150 T1-20 kN
T3- 20 kN 200
100 T2-20 kN T3-20 kN
50 T1-20 kN 100 T2-20 kN
0 0
0 10 20 30 40 50 0 10 20 30 40 50

Shear displacement (mm) Shear displacement (mm)

(a) 20 MPa concrete (d) 40 MPa concrete


400 600
.

Shear Load (kN) .


350 500
Shear load (kN)

300
250 400
200 300
150 T1-50 kN
T1-50 kN 200
100 T3-50 kN T3-50 kN
50 T2-50 kN 100 T2-50 kN
0 0
0 10 20 30 40 50 0 10 20 30 40

Shear displacement (mm) Shear displacement (mm)

(b) 20 MPa concrete (e) 40 MPa concrete

500 600
.
Shear load (kN) .

500
Shear Load (kN)

400
400
300
300
200
T1-80 kN 200
T1-80 kN
100 T3-80 kN
T2-80 kN 100 T2-80 kN
0 0
0 10 20 30 40 50 0 10 20 30
Shear displacement (mm) Shear displacement (mm)

(c) 20 MPa concrete (f) 40 MPa concrete

Figure 5.10 (a-f). Comparative results of all bolts shear load and vertical
displacement profiles in both 20 and 40 MPa concrete medium

142
Chapter 5: Double shearing of bolts across joints

350

Pretension load

.
300 40 MPa-T1
20 MPa-T1
40 MPa-T2
Pretension-Yield load (kN) 20 MPa-T3
250 40 MPa-T3
20 MPa-T2

200

150

100

50

0
0 20 50 80

Pretension load (kN)

Figure 5.11. Shear yield load difference in different concrete strength and bolt types
and various pretension loads

The following can be induced from the load /displacement data and graphs:

1. The elastic peak load (P) for non-pretension bolts in Bolt Type T1 did not

change significantly with changes in the concrete strength (see Figure 5.9 a

and d), However, there was a difference in P value in Bolt Type T2. Only

one test was made at no Pretension load in Bolt Type T3, which was in 40

MPa concrete. A possible explanation for the difference can be attributed to

the profile configurations between these two bolt types.

2. For the increase in pretension load from 20 kN to 80 kN, the peak elastic

shear load P values for the three Types of bolts increased by 81% for Bolt

Type T1, 45% for Bolt Type T2 and 100% for Bolt Type T3. In 40 MPa

concrete the respective Pvalues were 55 % increase in Bolt Type T1, and 9

% in Bolt Type T2. No tests were made for Bolt Type T3 in 80 kN.

However, P value in Bolt Type T3 increased 25 % from 20 to 50 kN

143
Chapter 5: Double shearing of bolts across joints

pretension load. This means that the tensioned bolt acts as an active support

system and provided the confining pressure to the sheared joint surfaces.

3. The peak elastic shear load displacement level for the given axial pretension

load was dependent on the bolt type. This displacement was more likely to

decrease with increased pretension load.

4. The strength of the medium has influenced the shear load level but not the

trend. Shear load values for all bolts were generally less in 20 MPa concrete

medium in comparison to the shear load values of bolts tested in 40 MPa

concrete.

5. Bolt Type T2 displayed closer and consistent shear load/displacement profiles

at all three levels of bolt pretension loads (20, 50, and 80 kN) particularly in

40 MPa strength. This consistency was relatively less in 20 MPa concrete,

and remained less scattered than the other two Bolt Types T1 and T2.

6. Bolt Type T3 load - displacement profiles were inconsistent and diverse at

different pretension load, this was expected in view of the large profile

spacing configurations of this bolt.

7. As shown in Figure 5.12, shearing of the bolt without bolt pretension can lead

to an early loss of resin/bolt bonding and inward pulling and bending of the

bolt, leading to excessive gap formation. This situation became worse when

the bolt ends were not fitted with nuts and plates to hold against the concrete

block ends. The presence of end plat plays importance role in providing better

structure reinforcement (see Tadolini and Ulrich 1986).

As can be seen from Figure 5.13 the gap created as a result of bolt bending,

was different for different test environment. The gap height varied under

different concrete type, pretension load values, and bolt type. The effective

144
Chapter 5: Double shearing of bolts across joints

gap (Chen 1999) was determined from testing of each of the bolt types T5

and T6 and was in the order of 1.35 and 3 times the bent bolt diameter (Db)

respectively. The formation of the gap is shown in Figure 5.33.

9. Figures 5.9 to 5.11 show the peak elastic yield load P values in different

bolt types in both 20 and 40 MPa concrete. Obviously, no definite

conclusions can be made on different bolt behaviour without bolts being

pretensioned in 20 MPa concrete. However, P value in Bolt Type T2

showed 38 % more than Bolt Type T1 in 40 MPa concrete and almost the

same with Bolt Type T3. What is obvious is the trend, which was also

showed in Figures 5.10 (a-f), that bolt pretensioning can contribute to

increased elastic peak yield load, and that the value of the peak yield load is

dependent on the level of pretensioning and concrete strength

10. Peak elastic yield point values changed with changes in resin annulus

thickness. This is clearly evident when testing bolts installed in different

diameter holes in 20 MPa concrete shown in Table 5.5 (Details in the next

chapter).

Type T1

Figure 5.12. Bolt slippage along the bolt -grout interface in case of non-pretensioning
and non- plate

145
Chapter 5: Double shearing of bolts across joints

Figure 5.13. Axial fracture along the concrete and broking off of the grout in tensile
zone in bolt type T1 in 40 MPa concrete with 80 kN pretensioning

5.6.1.3. Shear loading of bolt to ultimate failure

Next, a series of tests were carried out to examine the effect of increased shear

displacement until the bolt was completely sheared (failed). Two approaches were

adopted:

i. Shearing of small diameter bolts. The bolts used in these tests were Bolt

Types T5 and T6, tested in 40 MPa concrete.

ii. Shearing of the 23 mm bolt in 100 MPa high concrete. Only Bolt Type T1

was used in this test.

The above tests were undertaken at different confining pressures similar to tests

carried out under limited displacement. The general descriptions of these bolts are

shown in Table 3.1.

Tables 5.6 shows the test results on Bolt Types T5 and T6. Figures 5.14 shows the

load displacement profiles of the bolts tested under different axial load conditions.

The level of maximum shear loads and displacement were different because of

146
Chapter 5: Double shearing of bolts across joints

different pretension loads, and bolt types as indicated in Figure 5.15. The relationship

between shear yield load and pretensioning in Bolt Type T5 is shown in Figure 5.16a

and failed sheared bolt Type T6 is shown in Figure 5.16 b.

Table 5.7 shows the results of the tests carried on Bolt Type T1 tested in 100 MPa

concrete. Figure 5.17 shows the load displacement profiles of the bolt Type T1 in

different pretensioning in 100 MPa concrete. The excessive bolt necking in 100 MPa

concrete is shown in Figure 5.18. Figure 5.19 shows the failed bolt across the joint

planes and the crushed zones within the vicinity of the sheared planes in Bolt Type

T1 in 100 MPa concrete. Figure 5.20 shows the sheared failure resin imprint.

147
Chapter 5: Double shearing of bolts across joints

Table 5.6. Test results at Bolt Types T5 and T6 surrounded by 40 MPa concrete

Concrete Hinge Angle of


strength Yield Displ Failure Displ at
Bolt Preload Gap distance bolt Stiffness
point at yield load failure
Type (kN) (mm) (mm) bending (kN/mm)
(kN) (mm) (kN) (mm)
(***) (0)
40 0 48.7 6.3 76.5 23.8* 16* 34 28 7.75

T5 40 5 70 4.23 100.8 18.4* 15* 37 28 16.55


40 10 83 3.96 118.9 21.1* 18* 40 30 21
T6 40 10 98 4.33 172 36** 35** 40 44 22.6

* Displacement at failure and gap in bolt Type T5 is between 1.25 to 2 times bolt diameter

** Displacement at failure and gap in bolt Type T6 is around 3 times bolt diameter

*** Hinge distance in two types of bolts is between 2.8 to 3.3 times bolt diameter

149
Chapter 5: Double shearing of bolts across joints

Table 5.7. Bolt type T1 in 100 MPa concrete

Displ. Displ. Angle


Yield Peak Bolt Hinge
Pretension- at at Max displ. of Stiffness
load load deflection distance
load (kN) yield failure (mm) rotation (kN/mm
(kN) (kN) (mm) (mm))
(mm) (mm) (o)

0 219 8.9 272 - 22 31.65 65 14 24.6

20 260 7 770 69.6 50 69.6 - - 37.15

50 300 11 500 - 22.5 34 60 - 27.3

80 329 7.25 799 53.5 48 53.5 45 45 45.4


20 kN
pretension Failure
load is was
Remarks carried occurred
out in 36 only in
mm hole 80 kN
diameter

150
CHAPTER 5: Double shearing of bolts across joints

200
180 4
160
140
. 120 3
Shear load (kN)

100
80
2
60 1
T5-0 kN
40 T5-5 kN
T5-10 kN
20 T6-10N12

0
0 10 20 30 40 50

Shear displacement (mm)

Figure 5.14. Shear load versus shear displacement in 0, 5 and 10 kN pretension load
in Bolt Types T5 and T6 in 40 MPa concrete

Failure

Curve 1 Curve 2

Failure

Curve 3 Curve 4

Figure 5.15. The bolt failure view in different pretensioning

151
CHAPTER 5: Double shearing of bolts across joints

.
160
failure load over Max. tensile load (%)
140
120

100
80
60 23o
40 12o
20

0
0 5 10
Pretensioning (kN)

Figure 5.16. (a) Relationship between failure load and maximum tensile strength of
the single shear on bolt type T5, (b) bolt failure angle

900

800

700
.

600
Shear load (kN)

500

400

300

200 0 kN
50 kN
100 80 kN

0
0 10 20 30 40 50 60

Shear displacement (mm)

Figure 5.17. Shear load versus shear displacement in 100 MPa concrete and different
pretensioning in Bolt Type T1

152
CHAPTER 5: Double shearing of bolts across joints

O 
B

Failure location 


Bolt Type T1
A

Figure 5.18. Excessive bolt necking in concrete 100 MPa in 80 kN pretension load

Confining effect on joint surface

Created gap between bolt -grout


interface

Overwhelmed grout under high


pressure

A B L AB 60
L AB mm

Figure 5.19. Bolt/ joint concrete interaction at shear joint in concrete 100 MPa and
80 kN pretension load

153
CHAPTER 5: Double shearing of bolts across joints

50kN 80kN with bolt failure

Figure 5.20. Bolt imprint on resin in concrete 100 MPa at 50 and 80 kN pretension
loads

The following were deduced from both sets of tests stated above:

A) Testing of Bolt Types T5 and T6 in 40 MPa Concrete:

i. The snapping or failure of the bolt across joint planes, were the results

of both shearing and tensile loading. This is because the failed surfaces

of the bolt were not vertical and parallel to the sheared vertical joint

planes. The failed sheared bolt surface angle was in the order of 12o

from the sheared joint plane shown in Figure 5.16b.

ii. The peak elastic yield point P in the bolt has gradually moved from

the plastic hinge point (first yield point in the bolt) towards the bolt /

joint intersection.

iii. Bolt necking initiated around the peak elastic yield point P.

Noticeable necking was evident because of the predominately tensile

load at the bolt joint intersection. When necking commences, the bolt

154
CHAPTER 5: Double shearing of bolts across joints

diameter decrease severely on the effective length, which is between the

hinge points in the vicinity of the shear joint.

iv. For the pretension load of 80 kN, the shear displacement at failure for

Bolt Type T6 was 40% higher than the corresponding shear

displacement for Bolt Type T5. As Figure 5.16a shows the relationship

between the failure load and the maximum tensile strength of the Bolt

Type T5 in different pretension, indicating that the slope of the

relationship was in the order of 18o. These results contradicted Ferreros

result (1995), which stated that the pretension does not influence the

maximum shear resistance of the system. Ferreros tests were

undertaken in a single shear test box, whereby the pretension loads were

applied to one side of the bolt.

B) Testing in 100 MPa Concrete.

As shown in Table 5.7 and Figures 5.17, the following were noted:

i. The displacement rate of the sheared bolted block in 100 MPa strength

concrete was, as expected, lower than in both 20 and 40 MPa concrete

respectively.

ii. The failure load for Bolt Type T1 with Pretension load of 80kN was in

the order of 799 kN. This was in excess of the axial tensile failure load

of the bolt at around 340 kN.

iii. The crushed zones in 100 MPa concrete were less that those obtained in

40 MPa concrete. The length of the crushed zone was in the order of 60

mm on either side of the joint plane. This clearly demonstrated that

155
CHAPTER 5: Double shearing of bolts across joints

during shearing there was significant resistance concrete and hence less

vertical displacement.

iv. No failure occurred at 50 kN pretension load, however the failure was

achieved at 80 kN. The level of concrete crashing and sheared failed

resin imprints are shown in Figure 5.20.

v. During shearing, the bolt failed at around 66 % of the maximum tensile

strength of the bolt. The bolt could not have failed at this level on

purely the axial load, and this demonstrates again that the failure was a

combination of both shear and axial loads at the bolt joint intersection

(see Figures 5.21).

1
.

0.9
Axial load / Ultimate tensile load

0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
0 10 20 30 40 50 60

Shear displacement (mm)

Figure 5.21. The ratio of axial load developed along the bolt over ultimate tensile
strength of the bolt versus shear displacement in concrete 100 MPa with 80 kN
pretension load

156
CHAPTER 5: Double shearing of bolts across joints

5.6.2. Influence of Shearing Load on Pretension Load

Figure 5.22 shows a typical shear load versus bolt pretension load developed along

the bolt installed in a 20 MPa concrete medium. Point A is known as the Limit of

Maximum Frictional Bonding Strength (LMFBS) which indicates shear load values

whereby the pretension load values, monitored by the load cells mounted on either

sides of the bolt, began to increase from the initial applied load. This level of shear

load is significantly higher than the peak elastic yield point (P) shown in Figures 5.9

and 5.10 respectively, and discussed in previous section (5.6.1). The level of shear

load increase was dependent on the initial axial tensile load on the bolt, concrete type

and bolt profile pattern. Figure 5.23 (a-f) shows different shear load and load cell

readings for various bolts. The graph profiles were different for different bolt types.

400

350

300
Shear load (kN) .

250

200
LMFBS
150
A
100

50

0
0 20 40 60 80 100 120 140

Axial load developed along the bolt(kN)

Figure 5.22. Shear load versus load cell readings on tensile load applied on a bolt
installed in a 20 MPa concrete

157
CHAPTER 5: Double shearing of bolts across joints

500 600

.
Shear load (kN) .
400 500

Shear load (kN)


400
300
B C 300
200 A
20 kN
20 kN 200
50 kN
100 50 kN 80 kN
80 kN 100
0 0
0 50 100 150 200 0 50 100 150
Axial load along the bolt (kN) Axial load along the bolt (kN)

(a) Bolt Type T1 in20 MPa concrete (d) Bolt Type T1 in 40 MPa concrete

400 600
Shear load (kN) .

350

Shear load (kN) .


500
300
C
B 400
250
200 A 300
150
20 kN 200
100 50 kN 20 kN
80 kN 50 kN
50 100 80 kN
0 0
0 20 40 60 80 100 120 140 0 50 100 150
Axial load along the bolt (kN) Axial load along the bolt (kN)

(b) Bolt Type T2 in 20 MPa concrete (e) Bolt Type T1 in 40 MPa

400 600
Shear load (kN) .

350
.

500
300
Shear load (kN)

C
250 400
200 300
B
150 20 kN 200
100 A
50 kN
80 kN 100
50
0 0
0 50 100 150 200 0 50 100 150

Axial load along the bolt (kN) Axial load along the bolt (kN)

(c) Bolt Type T3 in 20 MPa (f) Bolt Type T3 in 40 MPa


Figure 5.23 (a-f). Shear load and pretension loads (load cell readings) for various
bolts with initial pretension load of 20, 50 and 80 kN

158
CHAPTER 5: Double shearing of bolts across joints

The following can be observed from the shear load versus axial load built up

along the bolt in different pretension load and concrete strengths.

i. The level of initial confining axial load applied to bolts had profound

influence on the applied shear load at the LMFBS between the bolt and

the resin. The higher was the initial tensioning load, the greater was the

shear load at the LMFBS.

ii. The shear load values at the LMFBS were greater than P at the shear load

shear displacement curve in all levels of pretensioning and concrete

strengths.

iii. Back sloping of the load cell-shear load graph prior to the failure of the

frictional bonding strength in high pretension load (80 kN) was attributed

to the crushing of the concrete blocks as indicated in Figure 5.24. Clearly

the bolt appears to have pulled through the concrete as the shear load was

increased. This phenomenon was more common in weaker concrete such

as in 20 MPa concrete medium. Thus 20 MPa concrete was too weak for

testing 22 mm core diameter bolts.

iv. Bolt Type T2 installed in the 40 MPa concrete had comparatively greater

shear load at LMFBS point than the other two bolts.

v. The level of shear displacement at the LMFBS point was dependent on

the level of initial pretension load. As can be seen from Figure 5.25. The

shear displacement was greater in 80 kN pretension load than the other

two profiles with 20 and 50 kN pretension loads.

159
CHAPTER 5: Double shearing of bolts across joints

Compressed

Figure 5.24. End crushing of the concrete in high pretensioning load

140
Axial load along the bolt (kN) .

120

100
8.6 mm
80

60 7.7 mm

40
5.8 mm 20kN
20 50 kN
80 kN

0
0 5 10 15 20 25 30 35

Shear displacement (mm)

Figure 5.25. Axial load developed along the bolt versus shear displacement in Bolt
Type T2 in 40 MPa concrete

5.6.3. Load Transfer Level In Different Profile

Figure 5.26 shows the comparison of the peak P values as a function of pretensioning

in different bolt profiles and the concrete strength. From the graph it can be seen that

the level of P has increased with increasing the concrete strength in different bolt

160
CHAPTER 5: Double shearing of bolts across joints

profiles. Bolt Types T3 and T2 had the lowest and highest (P) levels respectively in

20 MPa concrete. The graph also show that, in 20 MPa strength, the effect of

pretensioning in lower pretension load was much more effective than the higher

pretension load. In addition, it shows that Bolt Type T2 in 40 MPa concrete has

almost constant trend. In all the laboratory tests it was noted that the yielding of the

bolt bar begins at the plastic hinge point, which is positioned between 20 and 40 mm

from the shear joint plane, was dependent on the materials properties and test

conditions.

350

300 T1, 100 MPa

250
.

T2, 40 MPa
Yield load (kN)

200
T1, 40 MPa
150 T2, 20 MPa

T1, 20 MPa
100
T3, 20 MPa
50

0
0 20 40 60 80 100

Pretensioning (kN)

Figure 5.26. Effect of pretension load, bolt profile and concrete strength on the bolt
resistance

What is also obvious is that the failed area in the concrete mass was two or three

order of magnitude greater than the cross sectional area of the bolt. Once again this is

a clear indication that the bolt has failed under the combination of both shear and

axial load conditions.

161
CHAPTER 5: Double shearing of bolts across joints

5.6.4. Double Shearing of Instrumented Bolt

To gain a clear understanding of the pattern of build up of loads and stresses along

the bolt, two tests were carried out on strain gauged instrumented bolts (Bolt Type

T2), one test was made with bolt not subjected to pretension load (zero pretension)

and the other with a pretension load of 20 kN. Figures 5.27 and 5.28 show the

location of the strain gauges in Bolt Type T2. In each designated locations 1 to 6,

strain gauges were mounted on a side of the bolt surface. However, there were only

single strain gauges at locations 7 and 8, which were situated at the lower side of the

bolt. The spots where the strain gauge located had the bolt profile ground flat and

smoothed. The 21.7 mm core diameter bolts were installed in 27 mm holes as per

previous tests. Both tests were carried out in 40 MPa concrete. Details of strain

gauges positions are clearly marked in Figure 5.27. The strain gauge measurements

revealed that both the tensile and compression stresses were generated along the bolt

length during the shearing process.

By comparing the axial strain at each location along the bolt, the axial stress could be

determined by equation 5.1:

aij = E b ( ai aj ) (5.1)

and the shear stress distribution can be given by:

aij . Ab r
ij = = Eb ( ai aj ). (5.2)
2rl 2l

where;
aij = Change in axial stress between two adjacent gauges

Eb = Bolt modulus of elasticity (MPa)

162
CHAPTER 5: Double shearing of bolts across joints

150mm 300mm 150mm

Joint

Tension Load cell


Bolt


6 5 1 2 3 4
Grout
Tension Compression

Strain gauges
gauges
a) Without pretension load

Joint Joint
Load cell
Strain gauges Tension
Bolt
6 5 1 2 3 4


8 7 Tension Compressio
grout

30 30
30 30

60 60

90

b) 20 kN pretension load and the distance measurements

Figure 5.27. Schematic diagram of the strain gauges locations in the reinforcing
element (a) without pretension load and (b) 20 kN pretension load

163
CHAPTER 5: Double shearing of bolts across joints

ai = Axial strain at gauge 1( s )

aj = Axial strain at gauge 2( s )

l = Distance between gauges (mm)

r = Bolt radius (mm)

Using the above equations in un-loaded conditions, it was found that, for a 30 kN

shear load, the maximum tensile and shear stresses, between the strain gauges 3 and

4 at the bolt / grout interface were 196 MPa and 35 MPa respectively. Beyond this

load, the stresses were reduced, indicating the bond failure between bolt and grout.

The minimum axial and shear stresses were recorded at 50 kN shear load, which are

approximately 18 and 3.25 MPa respectively. Further analyses are presented in

Appendix B. This situation is occurred at the elastic region of the shear load-shear

displacement curve, which is supported by experimental and numerical results. It

should be noted that the distribution of the shear stress prior to the yield point is in

agreement with Farmers theory (1995). Load build up registered for the rest of the

strain gauges are shown in Figure 5.28. Figure 5.29 shows a section of the bolt with

strain gauges mounted on its outer surface. Figure 5.30 shows the variation of the

strain changes along the bolt.

The following were observed:

i. Strain gauge No 3 in non-pretension case, located in the compression zone

and placed 60 mm away from the shear joint, produced 2.5 % strain at 60 kN

shear load (one half of the total shear load acting of two joint planes). This

value of strain is in the range of the plastic region (higher than 0.3 % at the

end of the elastic region). This yield situation has occurred around 20% of the

maximum tensile strength of the bolt.

164
CHAPTER 5: Double shearing of bolts across joints

ii. The formation of two plastic hinges in the bolt symmetrically opposite to

either side of the sheared joint plane was determined by strain measurements.

Beyond the hinge point and towards the bolt ends there was a gradual decline

in the rate of bolt strain. This was in line with the findings obtained from the

numerical simulation. From the strain gauges located in the vicinity of the

hinge points, it was found that very small shear loads (12 kN at strain gauge

no 5) were needed to subject the outer profiles to strain. Thus it was clearly

evident from Figure 5.28 that both the tensile and the compression zones are

initiated in the bolt during the early process of shearing.

iii. From the pretension case it was found that the hinge point is located around

30 mm from the shear joint. The location of the hinge points depends on the

strength of the concrete. In week concrete, there will be excessive crushing of

the concrete in the vicinity of the sheared joint faces leading to higher

distance between the hinge point and joint spacing. However, the hinge point

location will be closer in high strength concrete.

160

140
.

120
Shear Load (kN)

100

80
strain 3
60
strain 1
strain 4
40
strain 5 20

0
-3 -2.5 -2 -1.5 -1 -0.5 0 0.5 1

Strain %

Figure 5.28. The shear load versus strain measurements in non-pretension load

165
CHAPTER 5: Double shearing of bolts across joints

Figure 5.29. The bolt surface with strain gauges installed

Joint
0.5
Length along the bolt (cm)
0
-10 -8 -6 -4 -2 0 2 4
-0.5

Strain %
-1

-1.5

-2
Right side of the joint Left side of the joint
-2.5

-3

Figure 5.30. The strain rate along the bolt, drawn by strain measurements in non-
pretension load

Figures 5.31 and 5.32 show the relationship between the applied shear load and

strains developed along the bolt in 20 kN pretension load.

500
gauge 1
450
gauge 2
.)

400
gauge 3
350
gauge 4
Shear load (kN)

gauge 5 300
gauge 9 250
gauge 7 200
gauge 6 150
100
50
0
-2 -1.5 -1 -0.5 0 0.5 1 1.5 2

Strain %

Figure 5.31. Shear load versus strain gauge measurements along the bolt in 20 kN
pretensions.

166
CHAPTER 5: Double shearing of bolts across joints

2
Left side of the joint Right side of the joint

1.5

strain % 0.5
Bolt axis

0
-10 -5 0 5 10
-0.5

Distance from shear joint (cm)

Figure 5.32. The variation of the strain gauge measurements along the bolt at 20 kN
pretension load

It is clear from the strain gauge measurements that the higher values of the strain

occurred within the distance of 30 mm from either side of the shear joint plane. Thus

it is reasonable to assume that the location of the hinge points are likely to be in these

zones and this finding is in agreement with the numerical studies discussed later in

Chapter 7. Further analysis of the strain variations along the bolt as shown in

Appendix B.

5.6.5. Medium (Concrete and resin) Reaction

When a bolted joint is sheared, the surrounding materials (concrete and grout)

deform and induce support reaction against the shear load along the bolts length.

This reaction depends upon the mechanical properties of the rock and grout. It is

noted that at early stages of shearing, the surrounding materials behave elastically,

which ends at around 10-20% of the loading time- as determined from the numerical

analysis- discussed later in the numerical chapter 7. The severities of these changes

167
CHAPTER 5: Double shearing of bolts across joints

depend upon several parameters, such as the mechanical and physical properties of

the bolt, rock and grout strength and bolt pretension load. Yield in the surrounding

materials will begin in the vicinity of the shear joint and propagates with increasing

bolt deformation. The grout annulus yields when the shear load (lateral bolt pressure)

at the bolt/joint intersection becomes equal to the grout yield strength. Grout

separation will start from the hinge point towards the shear joint and completely

separates from the bolt in the tension zone. Due to the axial bolt load, the yield in the

grout can be determined when the actual bond stress, between bolt and grout is

equal to the grout yield strength y as:

=1 (5.3)
y

When the yield occurs in the surrounding material, the axial bond strength between

the bolt/grout will change and on the yielding length the residual bond strength is

considered to be frictional and a function of the lateral pressure. This relationship can

be written as:

res = p( x ) (5.4)

where;

= Bond shear stress (MPa)

y = Grout shear strength (MPa)

res = Residual bond strength (MPa)

= Friction coefficient between bolt-grout interface

P( x ) = Support reaction (MPa)

168
CHAPTER 5: Double shearing of bolts across joints

For bolt lateral deformation, the rock is affected by the bolt pressure and the yield

in concrete is initiated from the pressure zone, which is in the vicinity of the bolt

joint intersection. In other words, the yield appears in the concrete when the

maximum elastic deformation of the concrete is exceeded. Gradually yield is

developed and expanded through the rock with increasing the bolt deformation.

Figure 5.33 shows the concrete block being split axially along the bolt, due to the

high stresses induced along the shear direction through the concrete blocks.

These fractures originate from the compression zone (critical zone in the vicinity

of the shear joint) and propagate into the upper side of the concrete block. By

splitting the concrete, the reaction pressure reduces and then the bolt deformation

increases with increasing the shear load. It is noted that block fracturing was

observed in all of the double shear tests performed. Figure 5.34 displays the gap

created between the bolt and the grout in the plastic stage, which was around 0.8-

1.0 Db (Db= bolt diameter). It is reasonable to conclude that the contact surface

area from the shear joint plane along the bolt between bolt/grout/concrete

interfaces gradually decreases to form the gap in the vicinity of the shear joint.

Axial fracture

Figure 5.33. Axial fracture developed along the bolt through the 20 MPa concrete

169
CHAPTER 5: Double shearing of bolts across joints

Gap height

Figure 5.34. The created gap in plastic stage

5.6.6. Prediction Of The Bolt Contribution

Bolt contribution to the shear strength of the reinforced shear joint plane depends

upon the rock/ concrete strength, grout strength, bond strength between the

interfaces, mechanical and physical properties of the steel bolt, joint specification

and bolt pretension loads. Each of these parameters, as discussed in previous

chapters, plays significant role in affecting the shear resistance and the failure

mechanism. Some of the affected parameters on the bolt contribution are inherent

specification for the shear joint which were found by direct shear tests on 20 and 40

MPa concrete joint planes. Based on the laboratory studies and shown in Table 3.6,

the value of the friction angle for 20 and 40 MPa concrete were measured as 31o and

38o respectively. Thus the confining effect can be calculated as;

N c = c + n tan (5.5)

where;

N c = Confining load (kN)

170
CHAPTER 5: Double shearing of bolts across joints

c = Cohesion between block joints (kN)

n = Normal force (kN)

= Angle of friction (o)

When the bolt is subjected to shearing, the total shear resistance is a combination of

the joint without reinforcement element and bolt contribution. According to Mohr

Coulomb criterion, the shear joint contribution under the confining pressure can be

expressed as in Equation 5.6. Also the bolt contribution can be expressed as in

Equation 5.7.

Tv
Tt = N c tan (5.6)
2

Tv 2 N c tan
Tt =
2

Tt
Tb =
Fmax

Tv 2 N c tan
Tb = = f (t ) (5.7)
2 Fmax

where;

f (t ) = Bolt contribution

Tv = Shear load

171
CHAPTER 5: Double shearing of bolts across joints

Tt = Joint contribution

Fmax = Maximum tensile strength of the bolt

ub
f (u ) =
Db

f (u ) = Dimensionless factor in terms of shear displacement,

ub = Shear displacement and

Db = Bolt diameter.

Table 5.8 shows the confining force value in different concrete strength and various

level of pretensioning. By using the above equations in different rock strength and

various level of pretensioning, the bolt contribution is calculated

Table 5.8. Joint confining specification

Concrete Pretension Joint angle Confining


strength load (kN) of friction load (kN)
(MPa (o)
20 31 12
20 50 31 30
80 31 48
20 38 15.6
40 50 38 23.4
80 38 62.5

The bolt contribution in bolt Types T1, T2, T3, T4, T5 and T6 in different concrete

strength and bolt pretension loads are presented in Appendix B.

172
CHAPTER 5: Double shearing of bolts across joints

Based on the laboratory results in different concrete strength, pretension load and

steel strength, the following relationships were established among the related

parameters;

Tb = 120.5 ln( c ) + 0.014( f ty ) 2 + 0.058( f ty ) 239 (5.8)

uy (5.9)
= 1.06 ln( c ) + 4.96
Db

where;

Tb = Yield point at shear load- displacement curve

c = Uniaxial compressive strength of the rock (MPa)

f ty = Pretension load (kN)

u y = Joint movement (mm), which is usually twice bolt deflection

Db = Bolt diameter (mm)

From the equation it can be envisaged that the increase in the rate of the bolt

contribution reduces when concrete strength increases. Figure 5.35 shows the effect

of concrete strength on factor of the shear movement in both the numerical and

experimental analysis. The numerical results were conducted without pretension

load. Clearly as the concrete strength increased the shear displacement factor f(u)

tapers of exponentially reaching a constant level of around 0.5 beyond the concrete

strength of 60 MPa.

173
CHAPTER 5: Double shearing of bolts across joints

2.5

2 numeric

Lab
1.5

f (u )
1

0.5

0
0 20 40 60 80 100 120

Conrete strength (MPa)

Figure 5.35. Effect of concrete strength on the factor of movement

With the inclusion of the resin thickness and the strength properties of the steel while

maintaining the other parameters constant, the following relationship was stabled

using the statistical method SPSS V.7 software with 77 % correlation factor;

Tb Db
= 0.36( ) + 0.004(Pr) + 0.005( c ) + 0.53 (5.10)
y Dh

where;

Tb = Shear yield load (kN)

y = Maximum tensile strength of bolt (kN)

Db = Bolt diameter (mm)

Dh = Hole diameter (mm)

Pr = Pretension load (kN)

c = Uniaxial compressive strength of the rock (MPa)

174
CHAPTER 5: Double shearing of bolts across joints

Figure 5.36 shows the relationship between the expected and observed results, which

show good agreement between predicted and observed results.

Figure 5.36. Expected cumulative results versus observed cumulative results

The following were deduced from the bolt contribution in all types of bolts.

From the results in bolt Type T1, T2 and T3 it is concluded that the

maximum bolt contribution of the bolts depends upon the concrete strength

and bolt pretension load.

In 40 MPa concrete, for instance, in bolt Type T1, it was found that in case of

un-pretensioned load, there was no significant change in the level of bolt

contribution. However, the bolt contribution was increased to around 70 % in

20 MPa concrete when the bolt was pre-tensioned.

The bolt Type T3 has shown lower level of contribution in comparison with

bolt Types T1 and T2 in 20 MPa concrete.

Bolt contribution was increased around 15 % with existence of the resin grout

compared with absence of the grout at the same conditions.

175
CHAPTER 5: Double shearing of bolts across joints

Despite the lower shear load developed at the bolt- joint intersection in bolt

Type T5 compared with bolt Type T6, the overall bolt /joint contribution in

bolt Type T5 is higher than the bolt Type T6- 125% of the maximum tensile

strength of the bolt against 135%. This means that the bolt contribution

significantly depends upon the maximum tensile strength of the bolt.

The axial and shear loads are at their maximum at the bolt - joint intersection.

However, it has to be considered that for those cases in which the resistance

factor is less than 1, the shear stress is dominant. In particular for case

without pretensioning the resistance factor is around half of the maximum

tensile strength of the bolt, which bolt has likely failed in the pure shearing

condition. The reason for this is when the bolt is moving down -as there is no

axial load against axial movement, it can move easily and no axial stress

develops along the bolt. Then the bolt failure is due to the only shear stresses.

From the bolt Type T1 in 100 MPa concrete it was found that the maximum

bolt-joint contribution at failure is about 120 % of the maximum tensile

strength of the bolt.

The value of bolt contribution at yield point in concrete 20, 40 and 100 MPa

in Bolt Type T1 was about 0.24, 0.3 and 0.52 respectively.

5.7. SUMMARY

The double shearing study has demonstrated its importance in better understanding

of the role that a bolt would play in real ground reinforcements particularly in

sheared zones. The double shear system represented a better method of shearing

176
CHAPTER 5: Double shearing of bolts across joints

system as it enabled to allow a symmetric study of bolt shearing analysis, which is

not possible with available systems.

Accordingly the following were deduced from the study:

Bolt profiles plays a significant role in load transfer mechanism,

Bolt pretensioning contributes to increased level of shear resistance,

The resistance of the bolt will dependent on the concrete strength

Increasing the concrete strength reduces significantly the joint shear

displacement and contributed to increased shear stiffness.

The study demonstrated that the current size of the double shearing apparatus is

insufficient to conduct tests with larger diameter bolts. It thus recommended that the

size of the system to be doubled for effective results.

177
CHAPTER 6: Role of bolt annulus thickness on shearing

CHAPTER 6

ROLE OF BOLT ANNULUS THICKNESS ON BOLT

SHEARING

6.1. INTRODUCTION

The effect of resin thickness when bolt is axially loaded was investigated extensively

which was mentioned in Chapter 4. It was concluded that the optimum resin annular

spacing of 3-4 mm provides the safe installation and interlocking effect while bolt is

subjected to axial loading, Skybey (1992). In this method of loading, the anchorage

capacity decreases dramatically with increased annular spacing. However, there exist

no reported results in terms of resin thickness so far when bolt is subjected to lateral

loading (bending). Here, the effect of annulus on the shear resistance and shear

stiffness is considered.

6.2. TEST METHOD

To investigate the effect of resin thickness on load transfer mechanism and bending

behaviour of the fully grouted rock bolts, only bolt type T1 was selected through the

various types of bolts tested in previous section. Tests were carried out in two

concrete strengths, 20 and 100 MPa, in 25, 27, 28, and 36 mm hole diameter. All

tests were accomplished at the same pretensioned load - 20 kN. From the

investigations the following results were established.

178
CHAPTER 6: Role of bolt annulus thickness on shearing

6.3. EXPERIMENTAL RESULTS AND DISCUSSION

Tables 6.1 and 6.2 show the results of experimental tests in different resin

thicknesses. From the tables, it can be found that the yield load of the bolt-joint

reinforced system has increased 21% with an increase of annulus from 1.6 to 7.1

mm. In this situation, shear displacement has showed a 36 % reduction. Thus, the

bolt-joint stiffness has increased up to %65, which revealing the high effectiveness of

resin thickness in particular when the concrete strength is lower than resin strength.

Table 6.1. The results of bolt tested in type T1-20MPa strength with 20 kN
pretension load

Db Dh Annulus Hinge Bolt Bolt Comment


(mm) (mm) (mm) distance deflection bending
(mm) (mm) (o)

21.7 25 1.6 60 63 42
21.7 27 2.6 59 60 38
20 MPa
21.7 28 3.1 50 65 40
21.7 36 7.1 45 67 50
21.7 36 7.1 27.5 49 51 100MPa

Table 6. 2. The results of shear test in different resin thickness and concrete strength

Db Dh Annulus Yield Yield Failure Stiffness Remarks


(mm) (mm) (mm) load (kN) displacement load (kN/mm)
(mm) (kN)

21.7 25 1.6 163 6.23 762 26


21.7 27 2.6 168 5.83 813 29
21.7 28 3.1 177 5.37 821 33
21.7 36 7.1 198 4.57 756 43 *
21.7 36 7.1 259 6.53 784 40 100MPa
* This test stopped at plastic range and after dropping the load again was loading.

179
CHAPTER 6: Role of bolt annulus thickness on shearing

6.3.1. Shear load/ shear displacement

Figure 6.1 presents the comparison of shear load versus shear displacement in

different resin thickness. The shear load shear displacement for individual resin

thickness is presented in Appendix C.

Bar charts 6.2 and 6.3 show the effect of hole diameter on shear yield displacement,

yield load respectively. The shear stiffness is one of the important factors in resisting

shear along the joint surfaces.

In all the tests after the yield point, it can be seen that there is a gradual significant

increase in the shear load with high value of the shear displacement until failure

reached in the bolt at the bolt/joint intersection. In 27 mm hole diameter bolt was not

snapped. However, there was 5.6 % bolt diameter reduction at the bolt joint

intersection. Bolt yielded at 168 kN with 5.8 mm displacement.

900

800
700
Shear load (kN) .

600

500

400 25 mm

300 27mm
25mm
200 28mm
36mm
100

0
0 20 40 60 80 100
Shear displacement (mm)

Figure 6. 1. Shear load as function of shear displacement in different resin thickness

180
CHAPTER 6: Role of bolt annulus thickness on shearing

40

.
Dh
35

Hole size and yield displ.(mm)


yield displ
30

25

20

15

10

0
1 2 3 4
parameter
Parameter

Figure 6. 2. Effect of resin thickness on shear displacement


.

250
Hole size and Yield load (mm-kN) .

Dh
198
200 yield Load
177
163 168

150

100

50 36
25 27 28

0
1 2 3 4
Parameter

Figure 6.3. The effect of resin thickness on shear load shear displacement yield point

181
CHAPTER 6: Role of bolt annulus thickness on shearing

In addition, it reveals that beyond the yield load, there was significant increase in

shear load- approximately four times before failure- due to reaction pressure, the

confining effect and the bolt pretensioning.

In case of 36 mm hole diameter the hinge point distance is lower than the lower resin

thickness, about 45 mm, which is 70% of thin resin annulus. In addition, the higher

resin thickness showed the higher shear yield load, which is due to the resin annulus.

It should be noted that the resin strength was more than triple concrete strength (see

chapter 3). This makes a stronger beam around the bolt and finally a stronger system,

that shows lower overall resistance and lower shear displacement.

With increase of the resin annulus, shear yield displacement was reduced, yield load

and shear stiffness was increased. Figure 6.4 shows the shear load versus the shear

displacement in different resin thickness and concrete strength. With comparison to

20 MPa concrete in different resin thickness it was found that there is a high level of

shear load in higher resin thickness and lower overall resistance in higher resin

thickness, which is expected. In addition it revealed that higher concrete strength

appears to have lower overall resistance. Besides, this shows that lower resin

thickness in high concrete strength has lower overall resistance, because the lower

resin annulus in high strength concrete makes it stronger as resin strength is 60% of

the concrete strength. Also it shows there is a high level of the shear yield load in the

lower resin annulus compared with higher resin annulus in stronger concrete. This

means stronger and stiffer surrounding material tends to have a higher shear

resistance to be induced in the bolt and lower overall resistance in the system. It is

inferable that overall bolt contribution in lower strength concrete is slightly higher

than the high strength concrete. The reason, in soft concrete strength, the bolt can

mobilized a greater axial force due to its ability to be deformed.

182
CHAPTER 6: Role of bolt annulus thickness on shearing

900

800

700

Shear load (kN) .


600

500

400

300
80 kN-27mm-100
200 20kN-36mm-100
20kN-36mm-20
100 20kN-27mm-20

0
0 20 40 60 80

Shear displacement (mm)

Figure 6.4. Shear load and shear displacement in concrete 20 and 100 MPa and 20
kN pretension load and different resin thickness in Bolt Type T1

Figure 6.5 and 6.6 show the resin breaking and gap creation in high and thin resin

thickness at the vicinity of the bolt joint intersection in concrete 20 and 40 MPa

respectively with 20 kN pretension load. From the Figure 6.5 it can be seen that grout

is separated from the bolt in the tension zone, and is crushed by pressing in the

compression zone. In higher concrete strength in Figure 6.6, resin has broken off but

is not separated, due to harder concrete.

Easily will be
separated due to
tension cracks

Figure 6.5. Gap creation between bolt grout at high resin thickness in concrete 20
MPa with 20 kN preload (5 mm thick)

183
CHAPTER 6: Role of bolt annulus thickness on shearing

Figure 6.6. Gap creation between bolt grout at high resin thickness in concrete 40
MPa with 20 kN preload (5 mm thick)

6.3.2. Axial load built up

Figure 6.7 presents the shear load as a function of axial load build up along the bolt.

As stated in chapter 5, point A is called LMFBS.

900
800
700 3
Shear load (kN) .

600
500
2
400
300
200 A LMF
100
1
0
0 50 100 150 200 250
Axial load along the bolt (kN)

Figure 6.7. Shear load and axial load build up along the bolt in concrete 20 MPa and
20 kN pretension load and thin resin thickness in bolt Type T1 (25mm)

The trend of axial load generation can be classified into three sections. In the first

part, the increase in axial load is negligible. At the end of this part, which is LMFBS,

184
CHAPTER 6: Role of bolt annulus thickness on shearing

the axial load begins to increase and continues gradually with high shear

displacement. This means when failure occurs in the surrounding materials, grout

and rock, the bolt can penetrate through its base bottom. As it is pretensioned, the

axial load increases along the bolt.

The third section usually will start from 70% of the shear failure load, while the

increase rate of axial load is decreasing with higher shear displacement rate. This is

more likely around the bolt necking. This behaviour continues until complete failure

in the bolt at the bolt joint intersection. Figure 6.8 shows the axial load developed

along the bolt as a function of the shear displacement in different resin thickness.

Figure 6.9 shows the axial load shear displacement in 27 mm hole diameter. The

same trend was found in all resin thickness (see appendix). It shows that the smooth

behaviour at the beginning is due to the elastic behaviour of the materials and their

strength, which dont transfer much load on the bolt.

900
800
700
Shear load (kN) .

600
500
400
300 27 mm
200 25 mm
28 mm
100 36 mm

0
0 20 40 60 80 100 120 140 160 180 200 220

Axial Load along the bolt (kN)

Figure 6.8. Shear load versus axial load developed along the bolt in different resin
thickness in 20 MPa concrete

185
CHAPTER 6: Role of bolt annulus thickness on shearing

The smooth end has resulted for the bolt necking and reaches to the failure, causing

reduction in bolt resistance and higher rate of the shear displacement.

. 250

Low rate of axial load


Axial load along the bolt (kN)
Smooth trend
200 Axial load

150

100
Low rate of
axial load
Smooth trend
50

0
0 20 40 60 80 100

shear displacement (mm)

Figure 6.9. Axial load versus- shear displacement in bolt T1 and 20 kN preload in 27
mm hole diameter surrounded by 20 MPa concrete

6.3.3. Failure mechanism of reinforced element

Those bolts, which reached failure, continued very lengthy plastic behaviour and

finally failed due to the applied shear load and generated axial load. This ductile

behaviour happens in the bending region, which is located between hinge points. By

increasing shear load, the axial load is increased at the straight length of the bolt in

the bending region and then by combination of the axial and shear load at the vicinity

of the shear joint, the bolt was failed.

Figure 6.10 presents the axial stress along the bolt versus shear displacement in high

resin thickness. It shows in nearly half of the maximum deflection, the shear stress

developed five times which is due to the acceleration of the load generation along the

186
CHAPTER 6: Role of bolt annulus thickness on shearing

bolt. This occurrence happens beyond the LMBFS. From the figure it can be seen

that the maximum stress build up along the bolt is about 600 MPa, which is nearly

equal of tensile yield point of the bolt. However, the bolt failed in this test. If we

accept that the bolt should fail only by axial load, bolt should not be failed in this

stress, which is less than tensile yield point of the bolt, while bolt was failed and

snapped in this level of the stress. Thus it is inferred that bolt failure is combination

of the axial and shear loads developed in the bolt joint intersection. Figure 6.11

shows the axial resistance factor (axial load build up, over ultimate bolt tensile

strength) versus shear displacement. It depicted that after the yield point, the axial

load generation in all different resin thickness is approximately the same. However,

beyond the yield point, the higher resin thickness appeared to have higher resistance

factor, being 13% of the maximum tensile strength of the bolt compared with 9% in

lower resin thickness. In all of these tests the bolt failed during the shearing process.

However, the maximum load generation along the bolt is 67% of the maximum

tensile strength of the bolt.

900
800
Axial stress (MPa) .

700
600
500
400
300
200
100 stress

0
0 20 40 60 80

Shear displacement (mm)


Figure 6.10. Axial stress versus shear displacement in bolt Type T1 in 20 kN preload
in 36 mm hole diameter surrounded by 20 MPa concrete

187
CHAPTER 6: Role of bolt annulus thickness on shearing

0.8

0.7

Axial resistance factor .


0.6

0.5

0.4

0.3

0.2 36mm
28mm
0.1 25mm

0
0 20 40 60 80 100

Shear displacement (mm)

Figure 6.11. Comparison of the axial load induced in bolt in different resin thickness
in 20 MPa strength (axial resistance factor is equal axial load over ultimate tensile
strength of the bolt)

This means that, at least 33% of the failure load is applied by shear load. So it can be

again inferred that the bolt has failed under a combination of the axial and shear load.

Figure 6.12 shows the side profile of the failed rock bolt embedded in 36 mm hole

diameter and 20 MPa surrounding concrete in 20 kN pretensioning. Inspection of the

failed reinforcing element showed that the failed surface causes the axial and

shearing failures, which initiates with small cracks from the center. However, it is

supposed that after the yield point, the shear stress generation in the vicinity of the

shear joint through the reinforced bar is almost constant and the bolt fails with the

increase of the axial load along the bolt due to much bending with combination of

shear load developed. It shows the shear lip in the failed bolt has created an ellipsoid

shape. This was found by Mahony et al. (2005) as well.

188
CHAPTER 6: Role of bolt annulus thickness on shearing

(a) (b)

Figure 6.12. Side profile of failed bolt Type T1 surrounded by concrete 20 MPa and
36 mm hole diameter at 20 kN pretension load b) typical end profile of a failed
reinforcing element

The following can be found from shear load/shear displacement and axial load

results in different resin annulus.

At given shear load the axial load developed along the bolt in low resin

thickness is higher than the high resin thickness

As the resin strength is significantly higher than the surrounding material in

soft concrete (20 MPa) higher resin annulus makes the stronger system

Higher resin thickness showed high level of shear yield load and a low level

of maximum axial load on the bolt

Hinge point distance was reduced with increase of resin annulus surrounded

by soft concrete

Shear displacement was reduced at the shear yield load in high resin

thickness

Shear stiffness was increased with increase of resin thickness

Higher resin thickness shows higher LMFBS (Limit of maximum frictional

bonding strength).

189
CHAPTER 6: Role of bolt annulus thickness on shearing

As in soft concrete, bolt bending generates extensive stress on resin /

concrete interface and failure occurs by shearing of the concrete at the resin /

concrete interface. It is assumed that bolt and resin strengths are more than

adequate to transfer the required load. Thus, to distribute the concentrated

shear stress on the rock and also to obtain larger and stronger anchorage,

increasing the hole diameter is a recommended option. However, in strong

surrounding material (rocks) increasing the resin thickness is not suitable

option as it decreases shear stiffness. Sakurai and Kawashima (1992)

reported that the stiffness of rock mass increases when rock bolts are

installed. This increase in stiffness is more dominant in hard rocks than in

soft rocks.

Consequently it can be concluded that in lower rock strength, to obtain the higher

bolt-joint stiffness/shear resistance, increasing the grout annulus is so important to

achieve this goal. It should be noticed that this is when the resin strength is higher

than the rock strength. However, in higher concrete strength and lower resin strength,

the shear stiffness reduces as resin thickness increases.

6.3.4. Effect of resin thickness on shear stiffness

Bar charts 6.13 show the effect of hole diameter on shear stiffness. The shear

stiffness is one of the important factors in resisting shear along the joint surfaces.

It shows the shear stiffness in higher resin thickness is higher than the lower resin

thickness. It has to be mentioned that the stiffness value by numerical simulation was

found to be 12 and 19 kN/mm without a pretensioning load at 27 and 36 mm hole

diameter respectively.

190
CHAPTER 6: Role of bolt annulus thickness on shearing

.
40 36

Stiffness-Hole size (kN/mm-mm)


Dh
35
stifness
30 27 28
25
25

Hole diameter
21.6
20 16.5
14.4
15 13

10
5
Stiffness
0
1 2 3 4
Parameter ( hole diameter and Stiffness)

Figure 6.13. The effect of hole diameter versus stiffness

From the experimental results it can be inferred that the effective stiffness of a fully

grouted rock bolt depends on the mechanical properties and physical configuration of

the bolt, grout and rock and annulus thickness. (Gerdeen 1997) expressed an

analytical method to find the effective stiffness of the bar, assuming a rigid rock

mass as following equation. In the case of rigid rock mass and high resin thickness,

the above equation almost can offer the acceptable prediction as compared with

experimental results. However, as the rock property, which plays the great role on

the reaction pressure and shear load level, is neglected, this equation in soft rock

predicts incorrect results.

K s = EI 3
(6.1)
K
=4
4 EI
(6.2)

Db 4
I= (6.3)
64

2Eg
K= (6.4)
( Dh Db )

191
CHAPTER 6: Role of bolt annulus thickness on shearing

where;

E = Modulus elasticity of the bar

Eg = Modulus of elasticity of the grout

Dh = Hole diameter

Db = Bolt diameter

I = Bolt moment of inertia

In 36 mm hole size when the resin is three times stronger than the concrete, it

predicts shear stiffness 21 kN/mm against 21.6 kN/mm from laboratory.

As resin thickness reduces, whereas the overall strength of the surrounding material

changes to softer material, the stiffness will change, this model cannot predict it and

again gives higher shear stiffness, which is unrealistic prediction.

The empirical method to find the reinforcement system stiffness is calculated

according to the equation below.

K s = 24.1 ln(0.137 t a + 0.068 Db ) (6.5)

Dh Db
ta = (6.6)
2

where;

Ks = Bolt stiffness (kN/mm)

ta = Resin thickness (mm)

Db = Bolt diameter (mm)

Dh = Hole diameter (mm)

192
CHAPTER 6: Role of bolt annulus thickness on shearing

By expanding the equation in a larger range of hole diameter it was concluded that

the angle of stiffness declines gradually.

6.4. NUMERICAL SIMULATION IN DIFFERENT RESIN


THICKNESS

Numerical finite element method in different resin thickness and different concrete

strength was carried out with ANSYS 9.1, which was discussed properly in

numerical chapter. In this investigation different hole diameter, namely 25, 27, 32

and 36 mm in 20 and 40 MPa concrete was simulated. Figure 6.14 and 6.15 show the

effect of hole size and concrete strength on shear displacement.

From the numerical analyses it was found that the relation between shear

displacement and concrete strength in 27 and 36 mm hole diameter (2.5 and 7 resin

annulus) is according to the following equations respectively.

U y = 310 ( c ) 0.74 (6.7)

(6.8)
U y = 160 ( c ) 0 .6

Where, U y is shear displacement (mm) and c is uniaxial compressive strength of

the concrete (MPa)

Table 7.3 displays the effect of concrete strength on shear displacement in different

resin thickness. It shows there is slightly decrease in displacement in elastic

behaviour compared with significant displacement reduction in non-linear behaviour

in different concrete strength.

193
CHAPTER 6: Role of bolt annulus thickness on shearing

40
36
33.97 Numerical Dh
35 displ (mm)

hole zise and displacement


30 27 26.38
25

(mm) 20

15

10

0
1 2
hole diameter and displacement

Figure 6.14. Effect of hole diameter and resin thickness on shear displacement in
numerical design

40
shear displacement (mm) .

30

36mm
27mm
20

10

0
0 20 40 60 80 100 120

Concrete strength (MPa)

Figure 6.15. Effect of resin thickness and concrete strength on shear displacement in
numerical design in un-pretension load

194
CHAPTER 6: Role of bolt annulus thickness on shearing

Table 6.3. Concrete strength effect on shear displacement reduction in different resin
thickness

Percent of displacement
Hole diameter Concrete strength reduction (%)
(mm) (MPa) Elastic Non-linear
behaviour behaviour
27 20 to 60 12.4 55

36 20 to 100 16 60

6.5. THE EFFECT OF RESIN ANNULUS ON INDUCED


STRESSES

The value of the generated stresses in the vicinity of the joint intersection was

evaluated in different resin thickness of 1.6, 2.6 and 5 mm, concrete and grout

modulus of elasticity and following results was established. It is noted that in these

analyses the concrete and grout were assumed to be linearly elastic, homogenous,

and isotropic. The behaviour of steel bolt was assumed non-linear hardening

behaviour discussed in numerical chapter.

6.5.1. Induced Shear Stress

Figure 6.16 shows the relationship between shear stress developed on the bolt in

vicinity of joint plane and concrete modulus of elasticity. The analyzed were carried

out in three resin thickness. As can be seen the shear stress decreased with increasing

level of concrete modulus. The rate of decrease was greater in thicker encapsulation

annulus layer. The results of medium concrete strength are presented in Appendix C.

195
CHAPTER 6: Role of bolt annulus thickness on shearing

6.5.2. Induced Tensile Stress

Tensile stress is a more critical stress than the compression stress, since the most

possibility of the failure happens because of tensile /combination of tensile and shear

which are located in vicinity of hinge point and bolt joint intersection. The effect of

grout and concrete elasticity modulus were evaluated. It was found that the induced

tensile stresses are reduced with increase of concrete modulus. Figure 6.17 displays

the induced tensile stress as a function of grout modulus. In general, there was a

gradual decline in tensile stress with increasing grout modulus in both concrete soft

and medium. In addition, small resin thickness has produced higher tensile stress

along the bolt.


.

340
Shear stress in bolt intersection (MPa)

335
330
325
320
315
310
305 27mm
300 32mm
25mm
295
290
285
0 10 20 30 40 50

Concrete Modulus (GPa)

Figure 6.16. Induced shear stress versus concrete modulus of elasticity in different
annulus size (grout modulus is considered 12 GPa)

196
CHAPTER 6: Role of bolt annulus thickness on shearing

700

Tensile stress along the bolt (MPa) .


690 32mm
27mm
25mm
680

670

660

650

640

630

620
0 5 10 15 20 25 30

Grout modulus (GPa)

Figure 6. 17. Induced tensile stress versus grout modulus of elasticity in soft concrete
(20 GPa)

6.5.3 Induced Compression Stress

Induced compression stresses are not so important for the bolt under compression, as

it cannot fail under the compression. Figure 6.18 shows the amount of compression

stresses as a function of concrete modulus of elasticity in different resin thickness.

There is no significant change in compression stress after 10 GPa modulus of

elasticity. From the simulated models it is possible to suggest that, the greater the

elastic modulus of concrete, the less the magnitude of induced stresses in/along the

bolt.

6.6. Effect Of Concrete Modulus Of Elasticity On Shear


Displacement

Figure 6.19 shows the effect of concrete modulus of elasticity on shear displacement

under different resin thickness. There is an exponential relationship between concrete

197
CHAPTER 6: Role of bolt annulus thickness on shearing

modulus of elasticity and shear displacement. The shear displacement is reduced

dramatically in range of the lower concrete modulus. The drop in shear displacement

tapers of to a near constant rate post-E value of approximately 15 GPa. Also it shows

there is no significant change between different resin thicknesses.


Compression stress along the bolt (MPa) .

1200

1000

800

600

400
32mm
27mm
200
25mm

0
0 10 20 30 40 50
Concrete modulus (GPa)
Figure 6.18. Induced compression stress versus concrete modulus of elasticity

However, in low concrete modulus of elasticity, higher thickness causes less

displacement but in higher concrete modulus of elasticity (stiff rock or hard rock)

thin resin appeared lower displacement, so it is concluded that, it is better to use in

soft rock higher resin thickness and in hard rock lower resin thickness. The reason

behind this is when debonding occurs and grout is broken, the bolt can move through

the resin on contact interface. When the resin thickness is reasonable value and low,

the interlocking effect is activated and resists against interface movement, so

displacement is reduced. From the simulated models it is possible to conclude that,

the greater the elastic modulus of concrete, the less the magnitude of shear

displacement.

198
CHAPTER 6: Role of bolt annulus thickness on shearing

14
Eg=12,32mm

Shear displacement (mm) .


12
Eg=12,27mm
10 Eg=12,25mm

0
0 10 20 30 40

Concrete modulus (GPa)

Figure 6.19. Shear displacement versus concrete modulus of elasticity in different


resin thickness, grout modulus is 12 GPa

It should be noted that in non-linear behaviour of concrete and resin, different resin

thickness definitely appears a significant difference in shear displacement.

6.7. Effect of grout modulus of elasticity on shear displacement

In this section a variety of grout modulus of elasticity was evaluated in different

concrete strength and in different annulus thicknesses. It was observed that there was

an exponential relationship between the modulus of elasticity and the shear

displacement in both concrete strengths of 20 and 40 MPa. Higher resin thickness

produced relatively lower shear displacement. As Figures 6.20 shows the shear

displacement is increased with increasing the resin thickness in both 20 and 40 MPa

concrete. However, this trend is reduced with increasing the grout modulus of

elasticity.

199
CHAPTER 6: Role of bolt annulus thickness on shearing

Ec=20,32 mm

Shear displacement (mm) .


5
Ec=20, 27 mm

4 Ec=20, 25 mm

0
0 10 20 30 40

Grout modulus (GPa)


Figure 6.20. Shear displacement versus grout modulus of elasticity in different resin
thickness, concrete modulus is 20 GPa and constant

6.8. EFFECT OF BOLT MODULUS

The variety of bolt modulus of elasticity is evaluated in different modulus of

elasticity and 12 GPa grout modulus of elasticity. Figure 6.21 shows the effect of

bolt modulus of elasticity on shear displacement. It shows that the shear

displacement is reduced with increasing bolt modulus of elasticity. This trend is

lower in high concrete strength. The effect of bolt modulus on shear displacement is

analytically discussed in analytical section, which shows acceptable agreement with

numerical results. In addition the results showed there is no significant changes in

induced stresses along the bolt in different modulus of elasticity. It is noted that this

part of the simulation is only in 2.5-resin thickness.

200
CHAPTER 6: Role of bolt annulus thickness on shearing

.
3.3

Shear displacement (mm)


3 y = 5.5495x-0.1479
R2 = 0.9203
2.7

2.4

2.1 y = 3.9086x-0.114
R2 = 0.9663
1.8
Ec=40
Ec=20
1.5 Power (Ec=40)
0 50 100 150 200 250

Bolt modulus (GPa)

Figure 6.21. Shear displacement as a function of bolt modulus variations in different


rock strength

The following can be noted from the numerical simulation:

The higher annulus thickness appears lower displacement in case when resin

strength is stronger than the surrounding material,

Low concrete modulus is more sensitive than the high concrete modulus on

shear displacement,

Shear displacement is reduced with increase of bolt, grout and concrete

modulus of elasticity,

Beyond the 15 GPa concrete modulus, there was not observed significant

changes on induced compressive stress on the bolt, and

With increasing grout modulus of elasticity, tensile and shear stress built up

along the bolt are reduced

201
CHAPTER 6: Role of bolt annulus thickness on shearing

6.9. SUMMARY

When concrete strength is significantly higher than the resin strength, the

larger annulus size shows higher shear displacement and lower shear

stiffness. This means the strength of the rock and resin -in terms of shear

stiffness and shear resistance of fully grouted bolts subjected to transversely

loading - is more effective than the resin annulus.

In soft strength materials (20 MPa) as the resin strength is significantly higher

than the surrounding material, higher resin annulus makes the stronger system

Hinge point distance was reduced with increase of resin annulus, when

surrounding material is weaker than the resin strength

Shear displacement was reduced at the shear yield load in higher resin

thickness

Shear stiffness was increased with increase of resin thickness

Higher resin thickness shows higher LMFBS (Limit of maximum frictional

bonding strength).

As in soft concrete, bolt bending generates extensive stress on resin / concrete

interface and failure occurs by shearing of the concrete at the resin / concrete

interface. It is assumed that bolt and resin strengths are more than adequate to

transfer the required load. Thus, to distribute the concentrated shear stress on the

rock and also to obtain larger and stronger anchorage, increasing the hole diameter is

a recommended option. However, in strong surrounding material (rocks) increasing

the resin thickness is not suitable option as it decreases shear stiffness.

Consequently it can be concluded that in lower rock strength, to obtain the higher

bolt-joint stiffness/shear resistance, increasing the grout annulus is so important to

202
CHAPTER 6: Role of bolt annulus thickness on shearing

achieve this goal. It should be noticed that this is when the resin strength is higher

than the rock strength. However, in higher concrete strength and lower resin strength,

the shear stiffness reduces as resin thickness increases.

203
CHAPTER 7: Numerical analyses in fully grouted rock bolts

CHAPTER 7
NUMERICAL ANALYSES IN FULLY GROUTED
ROCK BOLTS

7.1. INTRODUCTION

The current chapter consists of several parts, which are presented as follows. It is

aimed to describe a literature survey of the fundamentals of numerical modelling, the

application of numerical modelling in mining particularly in field of rock bolt,

developing of the FE model for the bolt/grout/rock and two interfaces, verification of

the model and finally analysing the stresses and strains developed in the rock bolt,

surrounding materials and related investigations.

Numerical methods represent the most versatile computational method for the

various engineering disciplines. The fundamental characteristic of numerical

methods is that a structure is discritised into small elements. Then the constitutive

equations that describe the individual elements and their interactions are constructed.

Finally these equations, which are large in number, are solved simultaneously and

interactively using computers. The results from this procedure include the stress

distribution and displacement pattern within the structure. Numerical modelling

includes several analysis techniques such as, finite elements, boundary elements,

distinct elements and other numerical approaches that depend upon the material and

the structure base numerical methods into three major models.

204
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7. 2. FE IN ANSYS

The ANSYS software is a commercial Finite element analysis program, which has

been in use for more than thirty years (Pool et al. 2003). The software is capable to

analyse the stress and strain build up in the verity of problems, specially designing

roof bolts and long wall support systems.

The original code, developed around a direct frontal solver has been expanded over

the years to include full featured pre- and post- processing capabilities, which

support a comprehensive list of analysis capabilities including linear static analysis,

multiple non-linear analyses, modal analysis, contact interface analyses and many

other analysis types. Ansys is a powerful nonlinear simulation tool, Bhashyam.G.R

(2002).

In this study only structural analysis was used. Structural analyses are available in

the ANSYS Multiphysics, ANSYS Mechanical, ANSYS Structural, and ANSYS

Professional programs only. Static analysis is used to determine displacements,

stresses, and strains under static loading conditions. (Both linear and non-linear static

analyses). Nonlinearities can include plasticity, stress stiffening, large deflection,

large strain, hyperelasticity, contact surfaces, creep. A brief description of numerical

techniques, finite element method, basic theory of finite element method, non-linear

solution in Ansys and failure criteria in Ansys are presented in Appendix D.

7.3. A REVIEW OF NUMERICAL MODELING IN ROCK BOLT

A number of computer programs have been developed for modelling civil and

geotechnical problems. Some of these programs can be used partially to design and

analyse roof-bolting systems. It is noted that to simulate the whole characters of a

205
CHAPTER 7: Numerical analyses in fully grouted rock bolts

model, such as modelling of the joints, bedding planes, contact interface and failure

criterion, the use of 3D software is necessary. Several numerical methods are used in

rock mechanics to model the response of rock masses to loading and unloading.

These methods include the finite element method (FEM), the boundary element

method (BEM), finite difference method (FDM) and the discrete element method.

A few research was carried out on bolt behaviour in FE field; such as, Coats and Yu

(1970), Hollingshead (1971), Aydan (1989), Saeb and Amadei (1990), Aydan and

Jawamoto (1992), Swoboda and Marence (1992), Moussa and Swoboda (1993),

Chen et al. (1994, 1999, 2004), Surajit (1999), and Marence and Swoboda (1995).

One of the earliest attempts to use standard finite elements to model the bolt and

grout was done by Coats and Yu (1970). The research was carried out on the stress

distribution around a cylindrical hole with the finite element model either in tension

or compression. It was found that the stress distribution was a function of the bolt

and rock moduli of elasticity. The presence of grout between the bolt and the rock

was not considered and also any allowance was not given for yielding. The analysis

was also accomplished only in linear elastic behaviour with two phase materials,

which were the limitation of the model.

Hollingshead (1971) solved the same problem using a three-phase material (bolt-

grout and rock) and allowed the penetration of a yield zone into the grout using an

elastic perfectly plastic criterion, according to the Tresca yield criterion, for the

three materials (Figure 7.1). In the model the interface behaviour was not considered.

John and Dillen (1983) developed a new one-dimensional element passing through a

cylindrical surface to which elements representing the surrounding material are

attached (Figure 7.2). They considered three important modes of failure of fully

grouted bolts. In this model, for axial behaviour a bi-linear elasto-plastic model and

206
CHAPTER 7: Numerical analyses in fully grouted rock bolts

for the bonding material an elastic-perfectly plastic-brittle-residual plastic model was

assumed. Although this model had eliminated many previous limitations and had

shown a good agreement with the experimental results, it has neglected rock stiffness

and in situ stress effects around the borehole. They claimed the critical shear stress

has occurred at the grout-rock interface, which is not always the case in the field or

in laboratory.

Bolt
Grout
Rock

Figure 7. 1. FE Simulation of bolted rock mass (After Hollingshead, 1971)

Figure 7. 2. Three-Dimensional rock bolt element (After John and Dillen, 1983)

207
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Aydan (1989) presented a finite element model of the bolt. He assumed a cylindrical

bolt and grout annulus is connected to the rock and was a three-dimensional 8-nodal

points. Two of these nodes are connected to the bolt and six nodes are connected to

the rock mass. The use of boundary element and finite element techniques to analyse

the stresses and deformations along the bolt was conducted by Peng and Guo (1988)

(Figure 7.3). The effect of the faceplate was replaced by a boundary element. The

effect of reinforcement because of the assumption of perfect bonding was

overestimated.

Shear force in
wall rock Shear force in bolt

Bearing plate

Reaction force bolt


Bolt head Tension in bolt

Figure 7. 3. Bolt-Rock interaction model (Peng and Guo, 1988)

Stankus and Guo (1996) investigated that in bedded and laminated strata, point

anchor and fully grouted bolts are very effective especially where they are installed

at high tension quickly after the excavation. They used three different lengths 3300,

2400 and 1500 mm and three different tensions; 66, 89, and 110 kN and found that:

- Bolts with higher pretension, induce a smaller deflection

- The longer the bolt, the larger the load,

208
CHAPTER 7: Numerical analyses in fully grouted rock bolts

- In bolts with the same length and high tension, there is small deflection,

- Large beam deflection was observed at long bolt, and small beam deflection

at the short bolt.

They developed a method to achieve the optimum beaming effect (OBE). However,

there were some assumptions in their methodology, such as: the problem in gap

element, which is not flexible for any kind of mesh especially when the grout

thickness is low. Many relevant parameters about contact interface cannot be defined

in gap element. The whole materials were modelled in elastic region.

Marence and Swoboda (1995) developed a special element, Bolt Crossing Joint

(BCJ) element. It connects the bolt elements on both sides of the shear joint. This

element has only two nodes, each on one side of the discontinuity. The model can not

predict the debonding length along the bolt grout interface and hinge point position.

Kharchafi et al. (1998) simulated the behaviour of bolted rock joints in a three-

dimensional method. However, they did not analyse the bolt behaviour in large

displacements. Also bolt pretensioning was not considered in their model.

It was realized and required that in order to further facilitate the data analysis and

stress, strain build up along the bolt surrounding by composite material and their

interaction, a powerful computer simulation is needed. The finite element modeling

is considered the only tool to accomplish this goal. Although, still there is lack of an

adequate global model of grouted bolt to analyze the bolt behaviour properly, in

particular contact interface behaviour.

In this study, three-dimensional formulations and non-linear deformations of rock,

grout, bolt and two interfaces are taken into account in the reinforced system. A

description of the numerical model developed is presented below.

209
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7.4. MATERIAL DESIGN MODEL

Finite element method is the most suitable computational method to evaluate the real

behavior of the bolt, grout and surrounding rock when there are composite materials

with different interfaces in the model. Three dimensional finite element model of the

reinforced structure subjected to the shear loading was used to examine the

behaviour of bolted rock joints. Three governing materials (steel, grout, and

concrete) with two interfaces (bolt/grout and grout/concrete) were considered for 3D

numerical simulation. To create the best possible mesh, symmetry rules should be

applied to the model. To reduce the computing demand and computing time (when a

fine mesh is used) the density of the mesh has been optimised during the meshing

process. The division of zones into elements was such that the smallest elements

were used in where details of stress and displacement were required. The process of

FE analysis is shown in Figure 7.4.

210
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Start

Decide and analysing the


problem

Select 3D Software

Material Geometry of Element


properties the model type

Mesh generation

Contact interface properties

Boundary condition

Dof Condition Symmetric Condition Loading

Determine load step, sub step,


time step and solution method
Analyse nodal
Convergence and Element No
No Yes
solution
Check penalty
stiffness Unacceptable
OK
Improve
No Compare with Mesh
Acceptable Increase sub step
laboratory tests

OK
END
Modify contact and
material properties

Figure 7.4. The process of FE simulation (Dof = degrees of freedom)

211
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7.4.1 Modelling of Concrete and Grout

Care was taken to develop the best model for concrete and grout that could offer an

appropriate behaviour. 3D solid elements, Solid 65 that has 8 nodes was used with

each node having three translation degrees of freedom, that tolerates irregular shapes

without significant loss in accuracy. The element is capable of plastic deformation,

cracking in three orthogonal directions, and crushing. The geometry and node

locations for this element type are shown in Figure 7.5 a. The solid element not only

is capable of plastic deformation, cracking in tension and crushing in compression,

creep nonlinearity and large deflection geometrical nonlinearity but also includes the

failure criteria of concrete; Fanning (2001), Feng et al (2002) and Ansys (2004).

Concrete can fail by cracking when the tensile stress exceeds the tensile strength or

by crushing when the compressive stress exceeds the concrete compressive strength.

A finite element mesh for concrete is shown in Figure 7.5b. Figure 7.6 shows the

finite element mesh for grout. Due to symmetry only a quarter of the model need to

be treated.

4
5 P
O
6
M
N
2
L 3
Z k

Y
X I 1

Figure 7.5. (a) 3D concrete Solid 65 (b) Concrete mesh

212
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Fine mesh at vicinity of shear


joint

Figure 7.6. Finite element mesh for grout

7.4.2 Modelling the Bolt

The steel bar is the main element within the rock bolt system to resist both axial and

shear loads during the loading process due to rock movements. So care was taken to

model the steel bar properly, in particular the type of element designed and bolt

behaviour in both linear and non-linear region. 3D solid elements, solid 95 that has

20 nodes was used to model the steel bar, with each node having three translation

degrees of freedom. The approach is adopted in this study, is to reveal that the

experimentally verified shear resistance effect of fully grouted bolt can be

investigated by numerical design. Elastic behavior of the elements was defined by

Youngs Modulus and Poissons ratio of the various materials. The stress-strain

relationship of steel is assumed as bilinear kinematics hardening model and the

modulus of elasticity of strain hardening after yielding is accounted as a hundredth of

the original one, Cha et al. (2003), Hong et al. (2003) and Abedi et al. (2003). Yield

strength of the steel was obtained from laboratory tests, 600 MPa. Figure 7.7 displays

the finite element mesh for bolt

213
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Fine mesh around


shear joint

Figure 7.7. Finite element mesh for bolt

7.4.3. Contact Interface Model

The main difficulties of numerical simulation of reinforced shear joint are the

simulation of the bolt/grout and grout/rock interfaces. An important parameter

controlling the mechanism of load transfer from the bolt to the rock through resin, is

bond behaviour between the interfaces. If these interfaces are not designed properly,

it is certainly difficult to understand the bonding behaviour and when and where

debonding occurs and how gap is created between interfaces and how the load is

transferred. Thus, care was taken to design the contact interfaces as they behave

realistically. To study the stress-strain generation through numerical modelling, it is

very important to model the interfaces accurately (Pal et al. 1999). Ostreberge (1974)

also emphasized on the bond strength influence between two adjacent mediums on

the accurate load transfer. Nietzsche and Hass (1976) proposed a model for bolt-

grout -rock and assumed a linear elastic behaviour for all materials and perfect

bonding for all contact interfaces (bolt/grout and grout/ rock). It has to be noted that

perfect bonding particularly between bolt/grout interface could not consider the right

behaviour, as there is no cohesion strong enough between them. In addition, there is

214
CHAPTER 7: Numerical analyses in fully grouted rock bolts

large stresses and strains concentration at the vicinity of the shear joints, which

restricts the perfect bonding. The interface behavior of the grout-concrete was

considered as a standard contact behaviour, where the normal pressure changes to

zero when separation occurs. As found from laboratory results the low value of

cohesion (150 kPa) was adopted for contact interface, which was determined from

the test results under constant normal condition.

3D surface-to-surface contact element (contact 174) was used to represent the contact

between 3D target surfaces (steel-grout and rock-grout). This element is applicable to

3D structural contact analysis and is located on the surfaces of 3D solid elements

with midside nodes. This contact element is used to represent contact and sliding

between 3-D "target" surfaces (Target 170) and a deformable surface, defined by this

element. The element is applicable to three-dimensional structural and coupled

thermal-structural contact analysis. This element is also located on the surfaces of 3-

D solid or shell elements with midside nodes. It has the same geometric

characteristics as the solid or shell element face with which it is connected. Contact

occurs when the element surface penetrates one of the target segment elements on a

specified target surface. The contact elements themselves overlay the solid elements

describing the boundary of a deformable body and are potentially in contact with the

target surface. This target surface is discritised by a set of target segment elements

(Target170) and is paired with its associated contact surface via a shared real

constant set.

7.4.4. Geometrical Model

The model bolt core diameter ( Db ) of 22 mm and the grouted cylinder ( Dh ) of 27

mm had the same dimensions as those used in the laboratory test. Due to the

215
CHAPTER 7: Numerical analyses in fully grouted rock bolts

symmetry of the problem, only one fourth of the system was considered here. Figure

7.8 shows the geometry of the FE model with mesh generation.

Shear joint
Shear load

Grout

T
150
C
C
mm
15 cm T

Bolt

15
150cm
mm

Concrete
150 mm
7.5cm
75mm 15 cm

Figure 7.8. Geometry of the model and mesh generation

7.5. VERIFICATION OF THE MODEL

A numerical representation model for fully grouted reinforcement bolt has been

developed. Then, validity of the developed model has been assessed with laboratory

data, which were conducted in a variety of rock strengths and pretensioning. The

comparison of experimental results with numerical simulations displayed that the

model is capable of predicting the bolt-grout-concrete interaction and interfaces

behaviour. The consistency of the experimental observation with numerical design

model is presented by typical shear load-shear displacement curves shown in Figure

216
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7.9. More comparison results are shown in Appendix D. It is clear that when the

concrete strength was doubled, there was a twice reduction in the shear displacement.

400

350

300
.

250
Shear load (kN)

200

150

100 Laboratory
Numeric
50

0
0 5 10 15 20

Shear displacement (mm)

Figure 7.9. Load-deflection in 80 kN pretension bolt load and 40 MPa concrete

7.6. MODELLING OF FULLY GROUTED ROCK BOLTS

An extensive series of laboratory tests to analyse the bending behaviour of fully

grouted bolts in different rock strength, bolt pretensioning and resin thickness were

carried out. Three governing materials (steel, grout, and rock) with two interfaces

(bolt grout and grout-rocks) were considered for 3D numerical simulation.

By this three-dimensional FEM, characteristics of elasto - plastic materials and

contact interfaces behaviour are simulated. The numerical modelling in different rock

strengths (20, 40, 50 and 80 MPa) and different pretension loads (0, 20, 50, and 80

kN) were carried out and the results were analysed in the following sections. Table

7.1 shows a total of 32 numerical models in different rock strengths, pretensioning,

and resin thicknesses.

217
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Table 7.1. Summery of created models

Concrete Pretension Bolt Hole Resin thickness Number


strength load (kN) diameter diameter (mm) of models
(MPa) (mm) (mm)
0 22 25 1.5
22 27 2.5 3
22 32 5
20 22 25 1.5
22 27 2.5 3
22 32 5
20 50 22 25 1.5
22 27 2.5 3
22 32 5
80 22 25 1.5
22 27 2.5 3
22 32 5
0 22 25 1.5
22 27 2.5 3
22 32 5
20 22 25 1.5
22 27 2.5 3
22 32 5
40 50 22 25 1.5
22 27 2.5 3
22 32 5
80 22 25 1.5
22 27 2.5 3
22 32 5
0 22 27 2.5
20 22 27 2.5 4
50 50 22 27 2.5
80 22 27 2.5
0 22 27 2.5
20 22 27 2.5 4
80 50 22 27 2.5
80 22 27 2.5

218
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7.7. RESULTS AND DISCUSSION

The numerical simulation was carried out in a variety of concrete strength and

different pretensioning. However, because of large output results, only the main

results of 0 and 80 kN pretensioning are presented here and the rest of the analyses

are shown in Appendix D.

7.7.1. Bolt Behaviour

7.7.1.1. Stress developed along the bolt

When a beam with a straight longitudinal axis is loaded laterally, its longitudinal axis

is deformed into a curve, the resulting stresses and strains are directly related to the

curvature of the deflection curve, which is affected by the surrounding materials.

Figure 7.10 shows a quarter of the model with induced loads along the shear joint.

When the beam is bent, there were both deflection and rotation at each point. The

angle of rotation is the angle between the bolt axis and the tangent to the

deflection curve, shown as point o. is measured for the bent bolts tested. The

deflection trend in 20 MPa concrete is shown in Figure 7.11. Also to find the

relationship between the bolt deflection and each point along the bolt axis, the output

raw data from the numerical simulation were classified and entered, as an input data

to Maple software (Ver. 9.1). Equation 7.3 and Figure 7.12 were established.

219
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Shear joint
Shear load

S Tensioning load
Grout
T
C
C
S Bolt T
S

S
Concrete

Confining pressure

Figure 7.10. Numerical model (s = symmetric planes, c = compression zone, T =


tension zone

dv
tan = , (7.1)
dx
dv (7.2)
= arctan
dx

dx o
dv

Shear joint location

Figure 7. 11. Bolt displacement in 20 MPa, without Pretensioning

220
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Distance from centre to end (mm)


A B

Shear displacement (mm)

Effective height

Figure 7.12. Shear displacement as a function of bolt length sections in 20 MPa


concrete

U y = 40.76 + 26 Arc tan(e ( 0.05 x 7.2 ) ) (7.3)

where;

U y = Shear displacement (mm)

X = distance from the bolt centre to the end (mm), from A to B.

The relationship between vertical displacement at the bolt - joint intersection and

hinge point is:

Uy (hinge) = (0.15-0.2) Uy (joint)

Which is consistent with laboratory results. Figure 7.13 shows the bolt deflection in

40 MPa concrete.

221
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Bolt deflection around hinge point

Shear displacement (mm)

Bolt deflection at moving side

Loading steps

Figure 7.13. Bolt deflection at the moving side and hinge point versus loading
process, in 40 MPa concrete without pretension load

Figure 7.14 shows the contours of stress developed along the bolt in 20 MPa

concrete. It shows the stresses in the top part of the bolt and towards the perimeter

are tensile and it is compressive at the centre. However, the stress conditions at the

lower half section of the bolt are reverse. In addition, the shape of the bolt between

the hinges can be considered as linear. The rate of stress changes in post failure

region is plotted in Figure 7.15. It can be seen that the induced stresses at these

zones are high and the bolt appears in yield state. At the two hinges the yield limit of

the bolt is reached quickly. However, further increase of the shear load has no

apparent influence on the stress built up at the hinge point. From this stage

afterwards, only the tensile stresses are developed and expanded between the hinge

points and may lead the bolt to fail at distance between the hinge points which are

located at the vicinity of the shear joint, as the maximum stress and strain occurre

between the hinge points.

222
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Shear joint
Tensile zone
A
Compression
zone
Compression zone
O

Tensile zone

Figure 7.14. Stress built up along the bolt axis in 20 MPa concrete without
pretensioning

Shear joint
Stress along the bolt (MPa)

Bolt axis

O A

Distance from centre to end (mm)

Figure 7.15. The trend of stress built up along the bolt axis 20 MPa concrete with 80
kN pretensioning

From analysing the results in different pretensioning it was found that there are no

significant changes in induced stresses along the bolt with increase of the pretension

load in the tension zone. However, there is a slight reduction in the compression

stresses with increasing the pretension load. Induced stresses are higher than the

223
CHAPTER 7: Numerical analyses in fully grouted rock bolts

yield point and less than the maximum tensile strength of the steel bolt in both

situations (without and with pretensioning in all concrete strengths). Moreover, in

different concrete strength it was observed that the strength of the concrete, affects

greatly shear displacement and bolt contribution. However, there was not observed

meaningful changes in induced stresses beyond the yield point along the bolt axis

with increasing the rock strength. But, the value of stresses was slightly reduced in

high level of pretensioning and high concrete strength.

The rate of stress generation and Von Mises stresses along the bolt in 40 MPa

concrete are presented in Appendix D. The Von Mises stress trend along the bolt axis

perpendicular to the shear joint in 20 MPa concrete is plotted in Figure 7.16.

Shear joint
Von Mises stress along the bolt (MPa)

O A

Distance from centre to end (mm)

Figure 7.16. Von Mises stress trend in 20 MPa concrete without pretensioning

Comparing the results in both pretensioning and non-pretensioning in 20 MPa

concrete it was found that the Von Mises stress is slightly decreased with increase of

the bolt pretension. However, this difference is not significant.

224
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Figure 7.17 shows the shear stress concentration along the bolt. The rate of shear

stress changes along the bolt axis is displayed in Figure 7.18. Figure 7.19 shows the

shear stress trend along the length of the bolt in one side of the joint surrounded with

soft concrete.

Shear joint A

O
Max Stress
concentration

Figure 7.17. Shear stress contour in the concrete 20 MPa without pretensioning

As it shows the maximum shear stress is concentrated at the vicinity of the joint

plane and according to structural analysis, bending moment in this point is zero.

These stresses slowly increase, beginning with the plastic deformation and ending

with a stable situation. The value of shear stress dramatically reduces from the shear

joint towards the bolt end. This trend likely reaches to zero at the hinge point. In the

two hinges, the yield limit of the steel is reached quickly, at about 0.3 P and 0.4 P in

concrete 20 and 40 MPa respectively, (P is the maximum given applied load).

Further increase of the shear force has no apparent influence on the stresses in the

hinges. The distance between the hinge points is reduced with increasing the strength

of the concrete.

225
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Shear joint
Shear joint

Shear stress trend along the bolt (MPa)


Bolt axis

Shear stress distribution

Distance from centre to end (mm)

Figure 7.18. The rate of shear stress along the bolt axis in concrete 20 MPa without
pretensioning

500
450
400
.

350
Shear stress (MPa)

300
y = 430.07e-0.1052x
250 R2 = 0.9399
200
150
100
50
0
0 10 20 30 40 50 60

Joint plane
Distance from joint (mm)

Figure 7.19. The rate of shear stress along the bolt axis in concrete 20 MPa without
pretensioning in one side of the joint plane

226
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Figure 7.20 shows the trend of shear stress changes in stress profile with the shear

stress tapering off to a stable state past the yield point. It displays the shear stress

trend is not exceeded during further loading after the yield point. Eventually, the

combination of this stress with induced tensile stress at the bolt-joint intersection

lead the bolt to failure. By increasing the bolt initial tensile load, the shear stress was

decreased and this was also observed in different concrete strength. However, there

was not observed significant changes with increasing shear load after the yield point.

Any reduction in shear stress causes an increase in the bolt resistance to shear. It can

be noted that the shear stress was slightly increased with increasing concrete

strength. The details results are presented in Appendix A7.I.


Shear stress (MPa)

Loading steps

Figure 7. 20. Shear stress trend in bolt joint intersection in concrete 20 MPa at post
failure region without pretension load

227
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7.8.1.2. Strain developed along the bolt

Simultaneously with increasing the shear load, strains were generated along all the

surrounding materials, in particular along the bolt axis. With increase of the bolt

deflection, plastic strain is induced in the critical locations in all three materials (bolt,

resin and concrete). Figure 7.21 shows the location of the maximum plastic

deformation along the bolt while bending. It shows there are two hinge points around

the shear plane with approximately 50 mm distance from the shear joint in 20 MPa

concrete. However, increasing pretension load has not affected significantly hinge

points distances, which are around 2.3Db. This value in the laboratory test is around

44mm that is 2 Db. The strains and the rate of strain changes along the bolt in 20

MPa concrete are shown in Figures 7.22 and 7.23. As the Figure 7.22 shows the

outer layer of the bolt material has yielded, whereas the middle part of the bolt

crosses section remains in the elastic state.

Shear load

+14.6

-11.3

-9.7

+13

Figure 7. 21. Deformed bolt shape in post failure region in 20 MPa concrete

228
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Shear joint
A
Compression strain

Tensile strain

Figure 7.22. The plastic strain contour along the bolt axis in concrete 20 MPa
without pretensioning

Shear joint

Bolt axis

Figure 7.23. Strain trend along the bolt axis in concrete 20 MPa without
pretensioning in upper fibre of the bolt

Figure 7.24 shows the beginning of plastic strain during the shearing and trend of the

strain development as a function of the time stepping. It notes that both the tensile

and the compression strain around the bolt were started approximately 27-30 % of

229
CHAPTER 7: Numerical analyses in fully grouted rock bolts

loading time and increased with increasing of the shearing load. However, the rate of

increase in the tensile zone is higher than the compression zone. As Figure 7.25

shows these strains appeared in early stage of loading and small displacement

(around 3 mm) and increased with increasing the shear deflections.


Compression & tension strain

Tensile strain trend

Compression strain

Time of loading

Figure 7. 24. The yield strain trend as a function of time stepping concrete 20 MPa in
20 kN pretension

With increase of the loading, the shear displacement was increased. It was found that

there is a significant increase in the shear displacement after 35% of the loading time.

Bending of the bolt is predominant at the low loading time. The generation of the

Von Mises strain at the hinge point as a function of the loading time is shown in

Figure 7.26. It displays the plastic strain is initiated at the hinge point around 35 % of

loading. Figures 7.27 and 7.28 show Von Misses strain and the rate of yield strain

changes along the bolt in 20 MPa concrete.

230
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Compression & tension strain

Tension strain

Compression strain

Shear displacement (mm)

Figure 7. 25. Tension and pressure strain along the bolt in 20 MPa concrete and 20
kN pretension
Plastic strain

Von Mises strain rate

Shear strain rate

Loading steps

Figure 7.26. The Von Mises strain trend along the bolt axis in concrete 40 MPa and
80 kN pretensioning

231
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Shear joint location


A

Figure 7.27. Von Mises strain along the bolt in concrete 20 MPa concrete without
pretensioning

Shear joint location


Strain along the bolt

O A

Distance from centre to end (mm)

Figure 7.28. Von Mises strain trend in concrete 20 MPa without pretensioning in
upper fibre of the bolt

With comparison of the data analysing, (pretensioning and non-pretensioning) it

shows that the intensity of the strain along the bolt axis is slightly reduced with

increase of the pretension load. However, the affected area in the tensile zone is

232
CHAPTER 7: Numerical analyses in fully grouted rock bolts

expanded towards the shear joint. In addition, it was found that the strains in both the

compression and tension zones were reduced in higher concrete strength.

7.7.2. Concrete

7.7.2.1. Stress developed in concrete

The behaviour of concrete under the shear load was analysed in different concrete

strength and different pretension loads. During the shearing process the middle part

of the concrete assembled system was moved down with increasing the shear load.

Figure 7.29 shows the concrete deflection rate after concrete failure. During the

concrete movement, the reaction forces are developed and increased in critical

locations (at the vicinity of the shear joint), which are affected by the steel bolt. So,

stresses and strains are induced and propagated in such zones.

O
A
Concrete displacement (mm)

Distance from centre to end (mm)

Figure 7.29. The concrete displacement in non-pretension condition in 20 MPa


concrete

233
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Figure 7.30 shows the high-induced stress in the vicinity of the shear joint as the

maximum reaction forces are expected in these areas. It is considered that when the

induced stress in concrete is larger than the ultimate stress of the concrete, the

concrete will be crushed. Figure 7.31 displays the rate of induced stresses in concrete

interface at the vicinity of the shear joint. It shows the induced stresses are much

higher than the compressive strength of the concrete and concrete at this location

would be severely crushed. From the figure it can be seen that the length of the high

stress distribution is propagated approximately 60 mm from the shear plane. At an

early stage of the loading, concrete was crushed and stresses propagated through the

concrete, the yielding of the concrete started around 2 mm deflection from the

intersection edge. Beyond this point stresses are increased quickly through the

concrete especially at the vicinity of the joint intersection and reaction zones. From

the pretensioning results it was found that the induced stresses in the vicinity of shear

joints were reduced slightly with increase of the bolt pretension load.

Maximum reaction stresses

Figure 7.30. Yield stress induced in 20 MPa concrete without pretensioning


condition

234
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Shear joint location

Displ. (mm)- induced stress (MPa)


Stress trend

Deflection trend

O A

Distance from centre to end (mm)

Figure 7.31. Induced stress and displacement trend in 20 MPa concrete without
pretensioning

In addition, the trend of the induced stresses and strains built up along the concrete

interface in higher concrete, 40 MPa, was the same as the soft concrete, 20MPa.

However, the value of stresses and strains were slightly reduced in higher concrete.

7.7.2.2. Strain developed in concrete

As discussed in the section above, in the vicinity of the shear joint, there was highest

level of induced stresses. Consequently it is expected that the strain would be highest

around such zones. Figure 7.32 shows the induced strain contours at the high-

pressure zone. The rate of the strain changes in the concrete interface along the bolt

axis is presented in Appendix D. Figure 7.33 shows the induced strain in terms of

loading time in grout and concrete. It reveals that the strain generation is initiated in

the concrete prior to the resin grout. This is due to the lower concrete strength, as the

concrete strength is one third of the grout strength. Figure 7.34 shows the rate of the

235
CHAPTER 7: Numerical analyses in fully grouted rock bolts

shear displacement in concrete block at the shearing side and bolt - joint intersection

in 20 and 40 MPa without pretension load. Figure 7.35 shows the rate of strain

variations along the contact interface through the concrete versus loading time in 40

MPa concrete without pretension load. It shows there is approximately exponential

relation in the strain trend with increasing the loading process. In addition, also after

20% of loading steps, the plastic strain is induced along the contact interface at the

vicinity of the shear joint. This value in soft concrete (20MPa) is at an earlier stage,

which is around 15% of loading step. In addition, it shows the strain built up along

the bolt axis is lower than the shear direction. With comparison of the induced strain

along the joint interface in both pretensioning and non-pretensioning it was found

that the value of strain in shear direction is reduced (around 15%) with increasing the

pretensioning. In both axial and shear direction the strain concentration was

generated at vicinity of the shear joint.

Figure 7.32. The produced strain contours in 20 MPa concrete without pretensioning
(in shearing direction)

236
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Strain in grout and concrete


Strain in grout-concrete

Concrete Grout

Loading steps

Figure 7.33. Induced strain in concrete 20 MPa in grout and concrete versus loading
in non-pretension load and 27 mm hole diameter
Concrete displacement (mm)
Concrete displacement (mm)

Intersection edge
Intersection edge

Moving block Shearing block

Loading steps Loading steps


(a) (b)

Figure 7.34. Concrete displacement versus loading time in concrete (a) 20 and (b) 40
MPa in non-pretension condition

237
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Strain along the bolt axis

Concrete strain
Strain in shear direction

Minimum principal strain

Loading steps

Figure 7.35. Induced strain rate along the contact interface in 40 MPa concrete and
non pretension condition

Figure 7.36 shows the deformational behaviour of both concrete medium and bolt.

The plastic deformation of the concrete occurs at nearly 15 % of the maximum shear

load, while the deformation of the bolt occurs at 33% of the loading steps.
Strain in bolt and concrete

Strain in concrete

Strain in bolt

Loading steps

Figure 7.36. Induced strain in concrete and bolt as a function of loading steps in 20
MPa concrete with 80 kN pretensioning

238
CHAPTER 7: Numerical analyses in fully grouted rock bolts

From the graphs it can be seen that in very low values of the bolt deflection and time

steps, fractures happened in the concrete, which is in elastic range of the bolt. Any

further increase in the shearing force appears not to influence the stresses at the

hinges points, however the induced stresses in the concrete blocks causes extensively

fractures propagation and eventually leading the concrete to failure.

7.7.3. Grout

7.7.3.1. Stress developed in grout

It is known that the grout bands the bolt shanks to the surrounding ground making

the bolt an integral part of the rock mass itself, and the efficiency of the grouted bolts

depends on the shear strength of the bolt-grout interface and the grout-rock interface.

Figure 7.37 shows the induced stress contours through the resin layer surrounded by

20 MPa concrete without pretensioning. It was revealed that the induced stress

exceeded the uniaxial compressive strength of the grout at the vicinity of the bolt

joint intersection causes crushing of the grout in this zone. It shows the value of

induced stress in the grout layer in vicinity of the shear joint is much higher than the

uniaxial strength of the grout and grout in this location can be crushed. Observation

of the broken assembled sample after test displayed that grout was intensively

crushed around this zone. The damaged area in upper side of the grout was

approximately 60 mm from the shear joint. Figures 7.38 and 7.39 show both the gap

formation after bending in the numerical and laboratory methods respectively. It is

noted that the induced stresses were reduced with increasing the pretensioning.

(Nearly 10 %). However, it shows they are slightly expanded).

239
CHAPTER 7: Numerical analyses in fully grouted rock bolts

High stress zone

Figure 7.37. Induced stress contours in grout layer in un-pretension condition and 20
MPa

Created gap between grout and bolt

Figure 7.38. Created gaps in post failure region in 20 MPa concrete in the Numerical
simulation

240
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Created gap

Figure 7.39. Created gaps in post failure region in 20 MPa concrete in the laboratory
test

Figure 7.40 shows the rate of the grout deflection versus loading time in different

grout locations: moving block, intersection and hinge point. It shows that at the hinge

points there is almost no lateral deflection as the grout layer is separated from the

bolt/grout interface (See Figure 7.39).

at hinge point
Shear displacement (mm)

at Intersection

at shearing block

Loading steps

Figure 7.40. The grout displacement in different location along the bolt axis in 40
MPa concrete

241
CHAPTER 7: Numerical analyses in fully grouted rock bolts

7.7.3.2. Strain Developed in Grout

While shearing tacking place, strains are induced through the grout particularly at the

vicinity of the shear joint and the reaction zones. The value of strain in the grout

layer was around 10 times greater than the linear region at critical zones. This means

that the grout in those areas had broken off the sides that were in tension (as was

shown in Chapter 6, Experimental Results). The rate of induced strain along the

grout layer in axial direction is displayed in Figure 7.41.

Comparison of the results of strain along the joint interface in the grout layer showed

that the value of strain was decreased around 3 % and 5 % in the compression and

tension zones with increasing pretensioning to 80 kN which is due to higher shear

resistance and low lateral displacement. Figure 7.42 shows the grout shear

displacement in moving side of the shear block and the bolt -joint intersection versus

induced plastic strain.

Tensile zone
Strain along the grout

Compression zone

Distance from centre to end (mm)

Figure 7.41. The rate of induced strain along the grout layer in non-pretension
condition in axial direction

242
CHAPTER 7: Numerical analyses in fully grouted rock bolts

It displays the grout layer at the bolt -intersection will start to crush after slightly

movement along the joint and causes the plastic strain generation in the grout layer.

40
(mm) .
displacement (mm)
35

30
displacement

Moving side
25

20
Intersection
15
shear
shear

10
Grout
grout

0
0 0.1 0.2 0.3 0.4

Plastic
Plasticstrain
strain at
at intersection
the intersection

Figure 7.42. The grout displacement as a function of plastic strain generated in bolt-
joint intersection through the grout in non-pretension condition

In high concrete strength, the value of induced stress was slightly reduced and also

pretensioning causes reduction in level of induced stresses along the bolt grout

interface. The induced stress and strain and the rate of changes along the grout layer

in different concrete strength and pretension loads are presented in Appendix D.

7.7.4. Contact Pressure

Contact pressure contours were found to increase with increasing the shear load.

However, contact pressure has slightly reduced with increase of the pretension load.

Figure 7.43 shows the rate of induced contact pressure along the grout-concrete and

bolt grout. It displays that in vicinity of the shear joint there is high level of contact

243
CHAPTER 7: Numerical analyses in fully grouted rock bolts

pressure in both interfaces. However, this value in bolt grout contact interface is

much higher than grout concrete interface.

Shear joint
Contact pressure (MPa)

Contact pressure (MPa)


Distance from centre to end (mm)
Distance from centre to end (mm)
(a) (b)

Figure 7.43. The rate of contact pressure changes between (a) grout concrete
interface (b) bolt-grout interface in 20 MPa concrete in non-pretension condition

Figures 7.44 shows the rate of contact pressure generation in the concrete-grout and

grout - bolt interfaces respectively in 20 MPa concrete in 36 mm hole diameter with

80 kN pretension load. They show there is exponential relation between contact

pressure and loading process at the bolt - grout interface, which started after around

15% of the loading process. However, the contact pressure trend in the concrete -

grout interface has formed by 2 parts, from beginning to around 15% of the loading,

there is an approximate linear relation then followed by an exponential relation till

the end of the load stepping process. Figure 7.45 depicts the shear load versus

contact pressure at the bolt - grout interface. It shows that the significant contact

pressure is initiated after 50 kN shear load.

244
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Contact pressure (MPa)


(a) (b)

Contact pressure (MPa)


Loading steps
Loading steps

Figure 7.44. Contact pressure at the (a) bolt - grout interface (b) concrete - grout
interface in 20MPa concrete in high resin thickness (36mm hole diameter) in 80kN
pretension load

400
350
300
load (kN)
(kN)

250
Shear load

200
150
Shear

100
50
0
0 50 100 150 200

Contactpressure
Contact pressure (MPa)
(MPa)
Figure 7.45. Shear load versus bolt-grout contact pressure at 36 mm hole and 20 MPa
and 80kN preload

7.8. SUMMARY

The numerical analysis of the grout/concrete/bolt interaction has demonstrated that:

There were no significant changes in induced stresses along the bolt with

increasing pretension load, particularly in the tension zone. However, there

was a small reduction in the compression stresses.

245
CHAPTER 7: Numerical analyses in fully grouted rock bolts

The yield limit of the bolt occurs first at the hinge point at about 0.3 P and 0.4

P in 20 MPa and 40 MPa concrete respectively, (P is the maximum given

applied load). Further increase in the shear force has no apparent influence on

the stresses in the hinges. The distance between the hinge points reduced with

increasing the concrete strength.

The strength of concrete, affect greatly shear displacement and bolt

contribution. However, no significant change was observed in the induced

stresses beyond the yield point along the bolt axis with increasing the

concrete strength.

The maximum shear stress was concentrated in the vicinity of the bolt-joint

intersection.

There was an exponential relationship between the value of the shear stress

and the distance from the shear joint.

The shear stress value was not exceeded during further loading after the yield

point. Eventually, the combination of this stress with induced tensile stress at

the bolt-joint intersection lead the bolt to failure.

By increasing the bolt pretension load, the shear stress was decreased and this

was also observed in different concrete strength.

The shear stress at the bolt joint intersection slightly increased with

increasing the concrete strength.

There was no observed significant change in the hinge point distances with

increase of the bolt pretension.

There was significant increase in the shear displacement beyond 35 % of the

loading step, which is likely the yield point.

246
CHAPTER 7: Numerical analyses in fully grouted rock bolts

The value of strain in shear direction along the concrete was reduced (around

15%) with increasing the pretensioning. In both axial and shear direction the

strain concentration was generated in the vicinity of the shear joint.

The induced stresses exceeded the uniaxial compressive strength of the grout

in the vicinity of the bolt joint intersection, causing grout crushing.

The damaged area in the upper side of the grout was approximately 60 mm

from the shear joint.

The induced stresses along the grout were reduced with increasing the

pretension load, nearly 10 %. However, it shows they have slightly expanded.

The value of strain was decreased by around 3 % and 5 % in both the

compression and tension zones where the bolt pretension load increased to 80

kN.

7.9. NUMERICAL MODELLING OF FAILURE MECHANISM OF


BOLT RESIN INTERFACE SUBJECTED TO AXIAL LOADING

7.9.1. Introduction

A numerical model was developed to find the contact interface behaviour during

shearing under both pull and push tests. The same 3D solid elements and surface-to-

surface contact elements were used for grout and steel simulations. The numerical

simulation of the actual bolt cross-section area and its ribs was a complicated one,

and is almost impossible with the range of software available in the market today.

However, an attempt was made to model the bolt profile configurations by taking

into account the realistic behaviour of the rock-grout and grout-bolt interfaces, based

on the laboratory observations. To achieve this task, the coordinates of all nodes for

247
CHAPTER 7: Numerical analyses in fully grouted rock bolts

all the materials were firstly defined, then all these coordinates were inter-connected

to form the elements and finally the elements were extruded, in several directions, to

obtain real shape of the bolt.

7.9.2. Results and Discussion

Figure 7.46 shows the finite element mesh. Figure 7.47 shows the Bolt Type T1

under pull test condition. Two main fractures produced as a result of shearing of the

bolt from the resin. The first one begins at the top of the rib, with an angle of about

53 degrees running almost parallel to the rib orientation, and the second one has an

angle of less than 40 degree from the bolt axis. When these fractures intersect each

other, they cause the resin to chip away from the main resin body as it is

overwhelmed by the rib surface roughness while shearing.

Grout

Bolt

Outer plate

Figure 7. 46. Finite element mesh: a quarter of the model

248
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Rock
Shear and tensile 1
fractures 2 Grout
Bolt

Pull
Bolt

Grout Outer plate

Figure 7.47. The bolt movement in pulling test

The produced internal pressure by the bolt profile irregularities causes tangential

stress inducement in the grout. The grout fractures and shears when the induced

stress exceeds the shearing strength of the grout material, thus allowing the bolt to

slide easily along the sheared and slikenside fractures in the grout interface surface.

7.9.2.1. Bolt Behaviour

Figure 7.48 shows the bolt displacement trend. The maximum bolt displacement

occurs at the top collar on the pulling side of the bolt, causing a reduction in bolt

diameter. As a result, there will be an increase in grout-bolt surface debonding as

discussed in Chapter 4. The decrease in the bolt diameter, due to the Poisson effect in

the steel, contributes to an axial elongation of about 0.084 mm at the top collar of the

249
CHAPTER 7: Numerical analyses in fully grouted rock bolts

bolt where the load is applied. This value in push test is around 0.05 mm as shown in

Figure 7.49.

Axial displacement (mm)

0.08 mm length elongation

Distance from end to top (mm)

Figure 7. 48. Rate of the bolt displacement

grout

Push load

bolt

Outer plate

Figure 7. 49. Bolt displacement contour in Bolt Type T1 in case of push test

250
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Figures 7.50 and 7.51 show the maximum induced strain, located in the vicinity of

the applied load position in both the pull and push results respectively. The strain

value is around the elastic strain range and therefore the bolt is unlikely to yield.

Movement direction

Figure 7.50. Induced strain along the bolt profiles

Concentrated stress and strain

Figure 7.51. Shear strain in bolt ribs in push test

251
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Figure 7.52 shows the stress trend along the bolt profile, which shows the maximum

stress being concentrated at the pulling end of the bolt, gradually reducing towards

its free end. Similar results were found by Karanam (2005). Also it shows the shear

and tensile stress trends along the bolt. The maximum tensile stress along the bolt is

330 MPa. This value is in the order of one half of the elastic yield point strength of

600 MPa. This means the bolt behaves elastically and is unlikely to reach the yield

and situation. The axial stress developed along the bolt is given by:

4T
t = (7.4)
D 2
and
(7.5)
D 2 * t
T =
4

Where, t is the tensile stress, T is the axial load, D is the bolt diameter and y is

the yield strength of the bolt. The bolt behaves elastically as long as the following

expression is satisfied:

t < y (7.6)

So in this situation with failure along the bolt / grout interface, bolt never experience

yield situation. The shear stress and strain contours along the bolt/grout interface in

case of push test are shown in D.

252
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Von Mises stress


Stress along the bolt (MPa)

Axial stress

Shear stress

A
O
Distance from end to top head of the bolt (mm)

Figure 7.52. Von Mises Stress and shear stress along the bolt axis

7.9.2.2. Grout Behaviour

The behaviour of interface grout anulus is assumed to be elastic-softening-residual

plastic flow type. This behaviour was developed by Aydan (1989), and is given as:

= G < max (7.7)

max
= max ( max r ) (7.8)
r max

=r (7.9)

Where;

G = Shear modulus of grout interface

= Shear strain at any point in the interface

253
CHAPTER 7: Numerical analyses in fully grouted rock bolts

r = Shear strain at residual shear strength

max = Shear strain at peak shear strength

r = Residual shear strength of the interface

max = Peak shear strength of interface

= Shear stress at any point in interface

The grout material is in elastic conditions if the following expression is satisfied;

Tt < T y (7.10)

where;

Tt = Actual bond stress in the grout

T y = Yield stress of the grout in shear

From the strain generated along the grout interface it was found that the surface of

the grout layer was disturbed by the shear stress induced at the interface and this

strain is higher than the elastic strain range that caused the grout to be damaged at the

contact surface. Figure 7.53 displays the shear stress contour at the grout interface.

The whole contact area of the grout surface was affected by the shear stress and

consequently the induced shear strain was highly dominated. The maximum bonding

stress was approximately 38% of the uniaxial compressive strength of the resin grout.

The stress produced along the grout contact interface was greater than the yield

strength of the grout of 16 MPa and beyond the yield point only a slight increase in

load increment is enough to damage the whole contact surface. Also, the shear

displacement increased as a result the bonding failure occurred. The shear stress at

254
CHAPTER 7: Numerical analyses in fully grouted rock bolts

the bolt grout interface can be calculated by Equation (7.11), which shows a close

agreement with the results from the numerical simulation.

Thus,

f D 2
= = = 23.2 MPa (7.11)
A 8rl

where;

= Shear stress in the grout bolt interface (MPa)

f = Axial force in the bolt (kN)

A = Contact interface area (mm2)

D = Bolt diameter (mm)

Using Farmer (1974) equation the shear strength was equal to 27 MPa.

(
0.2 x
) (7.12)
= 0.1e a

where;

= Shear stress along the bolt grout interface

= Axial stress

a = Bolt radius

During the shearing process, the bolts outer plate was influenced by the stresses and

strains of the resin contact surface. Also these were small amount of generated over

the contact surface. From the analyses it was found that the induced stress along the

surface of the outer plate was insignificant, at about 30% of the yield stress, which is

not sufficient to reach the outer plate to yield. In addition, the grout debonding

255
CHAPTER 7: Numerical analyses in fully grouted rock bolts

occurred around 50 to 60 kN in different applied load levels. The details results are

listed in Appendix D.

Figure 7.53. Shear stress contours along the grout interface

7.9.3. Modulus of Elasticity Effect

The Young'
s modulus is the intrinsic property of an undamaged material, which has

main effect on shearing behaviour of the elasto-plastic contact interface. To define

the influence of this main factor, numerical simulations, with different grout modulus

of elasticity, were carried out to obtain the function coefficients. In the proposed

model the behaviour of the resin grout was assumed isotropic, homogeneous and

linear. However, the behaviour of contact interface was assumed non-linear with

perfect bonding between grout and outer plate and standard bonding between the

grout and bolt including a small cohesion and friction which was calculated from the

bolt - grout interface under constant normal stiffness condition tests (Aziz 2003).

Figures 7.54 to 7.55 show the shear displacement as a function of grout modulus of

elasticity in push, pull and their combination respectively. This relationship was

256
CHAPTER 7: Numerical analyses in fully grouted rock bolts

based on the data produced by the numerical model. There is a power function

between the shear displacement and grout modulus of elasticity.

2.1

1.8
.
Shear displacement (mm)

1.5

1.2

0.9

0.6

0.3

0
0 5 10 15 20 25 30

Grout modulus of elastisity (GPa)

Figure 7.54. The effect of grout modulus of elasticity on shear displacement in push
test

3
2.7
.

2.4
Shear displacement (mm)

2.1
1.8
1.5
1.2
0.9
0.6
0.3
0
0 5 10 15 20 25 30

Grout modulus of elastisity (GPa)

Figure 7.55. The effect of grout modulus of elasticity on shear displacement in pull
test

257
CHAPTER 7: Numerical analyses in fully grouted rock bolts

Equations 7.13 and 7.14 show the shear displacement as a function of grout modulus

of elasticity for push and pull respectively.

0.68 (7.13)
U y = 1.6 E g

0.71
U y = 2. 4 E g (7.14)

By combining Equations 7.13 and 7.14, the following relationship was established.

2.4 E g 0.71 (7.15)


( dE g dU y ) 0
u > 0 1.6 E g 0.68

Where, E g is grout modulus of elasticity, de and du are changes in grout modulus of

elasticity and shear displacement in interface respectively.

3
.

2.5
Shear displacement (mm)

1.5

1
pull
push
0.5

0
0 5 10 15 20 25 30

Grout modulus of elastisity (GPa)

Figure 7.56. The shear displacement as a function of grout modulus of elasticity in


case of push and pull test

258
CHAPTER 7: Numerical analyses in fully grouted rock bolts

It was found that the value of Equation 7.15 is always positive. The energy required

to exceed the shear strength of the interface is therefore higher than in the pull test.

The reason behind is because of Poisson effect and increasing the lateral pressure.

7.10.4. Summary

Both the experimental and numerical simulation has lead to the following

conclusions:

The average shear stress capacity of a bolt in a push test was greater than

that in a pull test.

Yielding and necking is unlikely to occur in bolts tested in 75 mm long

steel sleeves as the peak shear load was around 40% of the maximum

tensile strength of the steel. For the bolts to undergo necking it must be

gripped firmly at both ends.

Bolt-resin interface failure occurred by initially shearing of the grout at

the profile tip in contact with the resin.

Numerical simulation provided an opportunity to understand better the

stresses and strains generated as a result of bolt resin interface shearing.

Such understanding supported clearly both analytically as well as by

simulation.

The experimental test findings were in agreement with the numerical

simulations and analytical results.

259
CHAPTER 8: Analytical aspect of fully grouted bolts

CHAPTER 8

ANALYTICAL ASPECT OF FULLY GROUTED BOLT

8.1. REACTION FORCES DURING THE SHEARING

Numerous investigators have proposed analytical models and tried to evaluate the

bolt behaviour subjected to shearing, which are presented in following sections.

However, according to nature of theoretical solution, accepting of the some

assumptions is inevitable. When a bolted rock joint is subjected to shearing, the bolt

is deformed with increasing joint displacement and this can mobilizes a normal and a

shear force in the bolt, Swoboda and Marence (1992). And also with applying load to

a beam, its longitudinal axis is deformed into a curve and two components are

produced. A lateral load Q and an axial load N and two critical points: one in bolt-

joint intersection with zero bending moment and another in the maximum bending

moment (hinge point) with zero shear stress. these loads produce stress resultants in

the form of bending moments M, shear force Q and axial forces N throughout the

beam. Since both the axial force N and bending moment M produce normal stresses,

we need to combine those stresses to obtain the final stress distribution. Based on the

beams theory the axial stress produces a uniform stress distribution =


N and the
A

bending moment produces a linearly varying stress = My with compression on the


I

upper part of the beam and tension on the lower part and inverse in other side of the

joint. Figure 8.1 shows the assembled concrete, grout and steel model. Figure 8.2

displays the load generation along the bolt under shearing. The final distribution of

260
CHAPTER 8: Analytical aspect of fully grouted bolts

normal stresses is obtained by superposing the stresses produced by the axial force

and the bending moment.

N My (8.1)
=
A I
d 2
A = (8.2)
4

d 4
I = (8.3)
64

Note that N is negative when it produces tension and positive bending produces

compression in the upper part of the beam.

Joint

bolt grout

N1 N1

Rock

Figure 8. 1. Assembled model (concrete, grout and steel bolt)

Shear joint
M
N1
C D E
N cf
Qcf
Q (x)

M M

N1 N1

Q (x) Q (x)

Figure 8. 2. Load generation along the bolt during the shearing

261
CHAPTER 8: Analytical aspect of fully grouted bolts

As the loading increase, the surrounding medium concrete or grout supplies a

reaction. This reaction acts on the bolt length, which progressively increases until the

bolt reaches the yield situation, this reaction pressure depends on medium strength

and medium stiffness, which is discussed later.

Q ( x) = f ( K y ,U y , Db ) (8.4)

where; k y = Medium stiffness, u y = Displacement along the joint and Db = Bolt

diameter.

8.2. STEEL BOLT BEHAVIOUR

8.2.1. Plastic Design

Steel has predictable structural behaviour in the stress range in excess of the yield

point, i.e, the plastic range. Within this range, stress is no longer proportional to

strain and permanent deformation takes place. Plastic design implies a design

procedure based upon behaviour of the structure or element stressed within the

plastic range of the material (Crawley et al 1984).

There are two principal aspects of plastic theory. The first involves the stress pattern

at a single cross section and the developed stress resultant. The second aspect

involves the element as a whole the entire length of a series of continuous beam.

8.2.2. Plastic Theory

Whereas steel is ductile material, it is able to withstand deformation under load

without fracture. Figure 8.3 shows the normal stress strain curve for structural steel.

When the yield point, Fy , is first reached, it has a corresponding strain y . Any

262
CHAPTER 8: Analytical aspect of fully grouted bolts

slight increase in stress beyond this point will cause the steel to behave plastically.

However, its ductile quality allows it to be strained or stretched 15 times its yield

point strain without a noticeable increase in stress.

400
350
.

300 Fy
Axial Load (kN)

250
200
150
100
50
0
y
0 10 20 30 40 50 60 70
Axial displacement (mm)

Figure 8. 3. Stress strain relationship for bolt type T1

This is frequently referred to as a large flow of the material at a constant stress. If

this phenomenon is applied to a member in bending, the stress patterns illustrated at

Figure 8.4 a,b,c and d,e are those resulting from successively higher bending

moments. Rock bolts act as flexible support and redistribute the bending moment on

it, Moussa and Swoboda (1995).

Fy Fy Fy

Fy Fy Fy
a b c d e

Figure 8. 4. Elastic plastic stress sequence in bending

263
CHAPTER 8: Analytical aspect of fully grouted bolts

From elastic theory, stress is proportional to distance from the neutral axis, and

triangular stress patterns are formed such as those shown in Figure 8.4-b and c, the

outermost fibre has reached the yield point, and the corresponding stress resultant or

yield bending moment would be My= Fy . (r). Any additional moment would cause

the outermost fibre to flow but at the same time maintain the yield stress.

Consequently the adjacent fibres undergo an increase in strain with corresponding

increase in stress up to a maximum of Fy . This condition is shown in Figure (8.4.d).

For still larger moments, the process continues until the entire section is stressed up

to Fy as shown in Figure 8.4 e. This is the maximum stress on the entire section. In

this stress condition, plastic hinge is formed, and the corresponding moment is

referred to as the plastic moment. Since the stress almost is constant in both the

tension and compression regions, the areas and internal forces must be equal.

8.2.3. Basic Equation For A Grouted Rock Bolt Subjected To

Lateral Deformation

According to beams theory on an elastic foundation the mechanical performance of

the grouted rock bolt is as following equation, Hetenyi (1961).

k m Db
y ( 4) + y=0 (8.5)
EI

where;
y = deflection of the bolt

E = modulus elasticity of the bolt

I = moment of inertia of the bar

264
CHAPTER 8: Analytical aspect of fully grouted bolts

K m = Stiffness of subgrade reaction, which is function of annulus thickness, rock

mass surrounding materials.

Db = bolt diameter

E m = Modulus of subgrade

It is assumed that transversely loaded bolts behave according to Figure 8.5, which

shows the reaction forces supply, shear force, a bending moment and shear

displacement diagrams. The resulting strains and stresses in the beam are directly

related to the curvature of the deflection curve. This is discussed primarily by

Crawley and Dillon (1984). The bolt bending creates a bending stress in the bolt,

Koshti (2002 a,b).

Two points M1 and M2 are identified on the deflection curve. Point M1 is selected at

an arbitrary distance x from the axis y and point M2 is located a small distance (ds)

further along the curve. From each of these points a line normal to the tangent to the

deflection curve is drawn that is normal to curve itself. These normal intersect at

point o, which is the center of curvature of deflection curve. The distance M1o from

the curve to the center of curvature is called the radius of curvature ( ). Curvature is

a measure of how sharply a beam is bent. If the load on a beam is small, the beam

will be nearly straight, the radius of curvature will be very small. If the load is

increased, the amount of bending will increase, the radius of curvature will become

smaller, and the curvature will become larger. When yield in both subgrade and bolt

has occurred the bolt angle then changes towards the directions of deformation and

an axial load will develop in the bolt.

265
CHAPTER 8: Analytical aspect of fully grouted bolts

M
N0
Bolt with reaction forces C D E
N cf
Qcf
Q (x)
M1
M2 ds
Bolt bending
Lhg
Hinge point distance o
Hinge point
Shear force diagram = y ///

Max bending
//
Bending moment diagram y

Shear displacement y

Figure 8. 5. Deformed shape, shear force, bending moment and shear displacement
diagrams

According to Egger and Spang (1990) the deformed shape of the bolt shows two

singular point: one in the bolt-joint intersection, and another one in the point of

maximum bending moment (hinge point).

The failure of the bar may happens in one of these two locations; joint-bolt

intersection (affected by contribution of normal and transversal forces at the point C)

or at the point D, occurring by the combination of the axial force and the bending

moment (hinge point), where the bending moment is maximum and shear force is

zero. The failure equations can be determined by following interaction formula,

Pellet (1994).

266
CHAPTER 8: Analytical aspect of fully grouted bolts

Failure at the bolt-joint intersection and in the maximum bending moment are

presented in Equations 8.9 and 8.10 respectively

N cf Qcf
( )2 + ( )2 = 1 (8.9)
Np Qp

MD N
+ ( D )2 = 1 (8.10)
Mp Np

where;

N cf = Normal force at yield limit

N p = Normal force at failure

Qcf = Shear force at yield limit

Q p = Shear force at failure

M D = Bending moment at yield limit

M p = Bending moment at plastic limit

N D = Axial force in hinge point

According to beam theory both the bending moment and curvature of the bolt at

point C are zero. However, the axial force and shear force in this point are maximum.

By using the above equations, pellet (1996) carried out an analytical formulation and

obtained following equations to determine the failure forces at bolt-joint intersection

and maximum bending moment. The axial force and shear force at bolt-joint

intersection are calculated by Equations 8.11 and 8.12:

267
CHAPTER 8: Analytical aspect of fully grouted bolts

Qe 2 (8.11)
N cf = Ab f 1 4( )
Ab f

Ab N cf 2
Qcf = f 1 ( ) (8.12)
2 Ab f

where;

Ab = Bolt cross section area,

f = Failure stress at bolt material and

Qe = Shear force acting at point C in elastic limit

Qcf = Shear force acting at point C at failure of the bolt material

Axial force and shear force at point maximum bending moment are calculated from

Equations 8.13 and 8.14.

2
Qcf
N Df = Ab f 1 16 3 (8.13)
Pu (1.69D f

D 3
N cf (8.14)
Q Df = Pu 1.69 f [1 ( )2 ]
16 Ab f

According to the analysing it was found that the amount of shear load at bolt joint

intersection is higher than that at hinge point, which is consistent with the numerical

design as the maximum shear stress concentration was found at bolt joint

intersection.

268
CHAPTER 8: Analytical aspect of fully grouted bolts

8.3. BOLT - JOINT CONTRIBUTION

In reality when the bolt - joint is perpendicularly oriented (near 90 degree) bolt

would fail under combination of the shear and tension as it was found from the

experimental and numerical results. Whereas in small angles bolt is affected by

stretching load, failure is occurred under the tension, this occurrence was originally

investigated by Bjurstrom (1973). In a simple analytic procedure the contribution of

the bolt is calculated as following (Figure 8.6).

Joint
fs

Tv

Bolt

ft
Tj

Figure 8. 6. Applied loads on joint intersection

T j = ft cos + f s sin (8.15)

Tv = ft sin - f s cos (8.16)

Tb = T j + T v ag (8.17)

Tb = ft cos + f s sin + ( ft sin - f s cos ) ag (8.18)

Tb = ft (cos + sin ag ) + f s (sin -cos ag ) (8.19)

where;

269
CHAPTER 8: Analytical aspect of fully grouted bolts

fs = Shear load

ft = Axial load, which could be summation of axial load due to pretensioning

along the bolt ( T1 ) and axial load developed due to shearing movements ( T2 ), so it

can be written as:

f t = (T1 + T2 ) Ty (Maximum tensile strength of bolt)

= Joint slope

= Joint friction angle

Tb = Bolt contribution

From the equation it can be seen that bolt contribution depends upon the bolt angle,

angle of friction, confining effect and axial load developed along the bolt.

In this equation if angle is great (perpendicular bolt), it can be expressed as;

Tb = ft ag + f s (8.20)

With comparison of two equations for inclined and perpendicular bolt, it is found

that the role of confining in case of perpendicular is significant.

In other words, pretensioning can increase the confining effect and consequently bolt

contribution. In reality a coefficient of the pretensioning may affect as confining,

then,

Tb = ( KN1 + T2 ) ag + f s (8.21)

N 1 = Pretensioning

K = interface load transfer factor, it can be assumed equal coefficient of friction

angle

270
CHAPTER 8: Analytical aspect of fully grouted bolts

In absence of confining pressure and pretensioning, the only resistance forces are

shear resistance between bolt-grout:

T b = f s + .2rl ag (8.22)

where;

= Shear stress between bolt-grout interface

l = embedded length

r = bolt radius

Without pretensioning or end plate bolt is pulling along the bolt with applying the

shear load, however, if there is end plate, tensile stresses are produced along the bolt

and bolt contribution will increase. As it shows when pretensioning or confining

pressure increases contribution of the bolt will increase. This occurrence was

observed by laboratory and numerical results.

8.4. REACTION FORCES

A grouted bolt subjected to lateral deformation induces a support reaction that will

develop in both the grout and the rock mass. When the bolt is laterally loaded it is

assumed that the response from the subgrade depends on the mechanical properties

of the rock mass. Because of the small width of the grout annulus, probably should

be disregarded and the influence of the grout material is insignificant. However, if

the resin thickness is high and stronger than the surrounding rock, the effect is

271
CHAPTER 8: Analytical aspect of fully grouted bolts

significant as was confirmed by laboratory results. Besides, the effect of resin

thickness was compared with the case without resin. It was found that bolt

contribution would increase. (See laboratory chapter). There is a high value of lateral

deformation and pressure reaction in vicinity of the bolt-joint intersection. Thus the

yield in the subgrade will start in locations next to the shear joint and will expand

with increasing the bolt deformation progressively.

8.4.1. Basic Equation for Rock and Subgrade Material

The reaction of lateral bolt deformation can express by following equations (in

elastic situation).

pu = k m u y (8.23)

where,

pu = Support reaction

K m = Lateral stiffness, this is function of annulus thickness, rock and resin

mechanical properties.

u y = Lateral deformation

Terzaghi (1955) found one equation for lateral stiffness in elastic material. However

he neglected the effect of grout properties:

Em
Km = (8.24)
1.35 Db

E m = Modulus of elasticity of subgrade

Db = Diameter of the bolt

272
CHAPTER 8: Analytical aspect of fully grouted bolts

Based on rock mechanics equations E m is equal (0.3-0.4) Ei or equal 400 c and

Ei = Modulus of elasticity of intact subgrade

So it is concluded that the reaction force can be measured as a function of bolt

deflection, subgrade modulus of elasticity and strength of material, which these

parameters are evaluated in numerical simulation chapter. According to the

Holmberg (1991) analysis, the support reaction of subgrade can be expressed as.

300 c u y
pu = (8.25)
Db

And according to Pellets discussion

Pu = c .Db (8.26)

8.6. ANALYTICAL APPROACH TO DEFINE THE HINGE


POINT LOCATION REGARDING AXIAL LOAD ALONG THE
BOLT

8.6.1. Elastic behaviour

When lateral force acts on the bar, then the axial force and bending moment are

induced along the bolt. Figure 8.7 displays the induced loads around the bolt during

shearing.

Bolt with reaction forces C D E No


N cf
Qcf
Pu
Lp

Figure 8. 7. Reaction forces in bolt loaded laterally

273
CHAPTER 8: Analytical aspect of fully grouted bolts

N cf MD
max = (8.37)
A S

d 2
A= (8.38)
4
d 3
S = (8.39)
32

where,

M D = bending moment,

N cf = axial force,

A = area of bar cross section

d = bolt diameter,

S = section modulus.

max = normal stress acting on the bolt

The bending moment at point D can calculated as Equation 8.41. Point D is the hinge

point, which carries zero shear stress and maximum bending moment. With assuming

the equilibrium situation in this part of the beam, it can be expressed as follows:

Fy = 0 Qcf = Pu * L p (8.40)

Pu . .L p
2 (8.41)
MD = 0 M D = Qcf * L p
2
By substituting Eq (8.40) in Eq (8.41) and simplify, it can be written:

2
M D = pu l p / 2 (8.42)

and, by substituting the Equations 8.38, 8.39, 8.42 in Equation 8.37, hinge point

distance to the shear joint can be expressed as a following equation.

274
CHAPTER 8: Analytical aspect of fully grouted bolts

Db ( yDb 4 N cf )
2
1 (8.43)
lp =
4 pu

where;

Qcf = shear force

Lcp = reaction length

Pu = reaction fore, which can be equal c .Db according to Pellets discussion

y = elastic yield stress

c = uniaxial compressive strength of rock

Figure 8.8 shows the effect of hinge point distance as a function of the axial force

along the bolt. As figure shows in the higher level of axial force, close to the tensile

yield point of the bolt, there is not significant difference in hinge point in different

rock strength. Yield tensile load is around 230 kN. According to the laboratory tests

and recording of axial load along the bolt, it was observed that there is no significant

change in value of the axial load in elastic region, so with this assumption the hinge

point length, distance from maximum bending moment to the shear joint, can be

expressed as Equation 8.44. Figure 8.9 shows the variation of the bolt diameter as a

function of hinge point location. It displays that the hinge point location is increased

with increasing bolt diameter. In addition, higher rock strength, has shown lower

hinge point distance.

1 yDb
3

lp = (8.44)
4 pu

275
CHAPTER 8: Analytical aspect of fully grouted bolts

.
250

Axial load along the bolt (kN)


20 MPa-Elastic
200 40 MPa-elastic

150

100

50

0
0 10 20 30 40 50 60

Hinge point distance (mm)

Figure 8. 8. Hinge point distance versus axial force

45

40
Bolt diameter (mm) .

35

30

25

20

15

10 20 MPa

5 40 MPa

0
0 20 40 60 80 100 120

Hinge point distance (mm)

Figure 8. 9. Bolt diameter versus hinge point distance in different rock strength

8.6.2. Plastic Behaviour

As discussed earlier the failure of the bar may happens in one of these two locations;

bolt - joint intersection or at the maximum bending moment, The failure equation in

276
CHAPTER 8: Analytical aspect of fully grouted bolts

maximum bending moment can be determined by Equation 8.45, which was

described in Eq (8.10).

MD N (8.45)
+ ( D )2 = 1
Mp Np

According to beam theory both the bending moment and curvature of the bolt at the

bolt- joint intersection are zero. With validation of Trescas failure criterion for the

bolt behaviour, the value of plastic bending moment and axial force at failure can be

expressed as follows:

1.7Db y
3

Mp = (8.46)
32

Db 2 y
Np =
4 (8.47)

By substituting Equations 8.43, 8.47 and 8.48 in Equation 8.46, it can be written as:

2
32 p u l p 4N D
+( )2 = 1 (8.48)
3.4D b . y D b 2 . y
3

After simplification, and substituting the Pu = c .Db hinge point distance can be

expressed as follows:

( 2 Db y 16 N D )
4 2 2

l p = 0.32 (8.49)
cDb 2 . y

Figure 8.10 presents the effect of axial load on hinge point distance in plastic

situation at both 20 and 40 MPa concrete. It indicates that there is no significant

influence in hinge point distance in different rock strength at high level of axial load.

However, the hinge point distance is reduced with increasing the strength of

277
CHAPTER 8: Analytical aspect of fully grouted bolts

surrounding material. This was consistent with the laboratory results (Figure 8.12)

Moreover, the hinge point distance was increased with decreasing the axial load in

the bolt with polynomial trend. Thus, it can be inferred that when axial load

increases, the hinge point distances reach closer. This means the maximum axial load

moves towards the bolt-joint intersection and eventually lead the bolt to failure with

combination of axial and shear load at this area. Figure 8.11 shows the comparison of

hinge point distance and axial load in both elastic and plastic situation.

In other words, increase of the axial load is due to the lateral load increase, which

induces higher axial deformation. So with increasing the axial deformation, yield

position will move towards the bolt joint intersection, which was observed, from

laboratory results (Bolt Type T5). After stopping the test it was observed that the rib

distance at hinge point were increased which is due to yield at this point.

250
.

20 MPa
Axial load along the bolt (kN)

200 40 MPa

150

100

50

0
0 10 20 30 40 50 60 70 80

Hinge point distance (mm)

Figure 8. 10. The relationship between axial load and hinge point distance in
different rock strength in plastic situation

278
CHAPTER 8: Analytical aspect of fully grouted bolts

250

.
20 MPa-Plastic
40 MPa-Plastic
20 MPa-Elastic

Axial load along the bolt (kN)


200 40 MPa-elastic

150

100

50

0
0 10 20 30 40 50 60 70 80

Hinge point distance (mm)

Figure 8. 11. The relationship between the axial load and hinge point distance in both
elastic and plastic situation

Higher
strength

Lower
strength

Figure 8. 12. Hinge point position in different concrete strength

However, other test after dramatic reduction in load, they were continuing till failure

occurred with bolt separation at the bolt joint intersection, this means that initially

279
CHAPTER 8: Analytical aspect of fully grouted bolts

failure will occur at yield point and then with increasing axial load and axial

deformation this yield moves towards the joint intersection and results the failure at

that point with combination of the axial and shear load.

Holmberge (1991) developed an equation to define hinge point location in case of

yielding bolt and yielding subgrade as following:

y
l h = 0.58 Db (1 ku t ) 2 (8.50)
pu

where;

K = factor depends upon the modulus of elasticity , bolt yield strength and grout

condition

According to this equation when axial displacement increases, hinge point position

moves towards the bolt joint intersection (Figure 8.13), which was discussed earlier.

16
.

14
Hinge point position (mm)

12

10

0
0 0.2 0.4 0.6 0.8 1 1.2

Axial deformation (mm)

Figure 8. 13. Relationship between hinge point position and axial deformation

280
CHAPTER 8: Analytical aspect of fully grouted bolts

8.7. ANALYTICAL APPROACH TO DEFINE THE HINGE


POINT LOCATION REGARDING SHEAR DISPLACEMENT

According to previous sections in elastic region the Equation 8.51 was found to

define the hinge point location with strength of material and axial force induced in

the bolt.

1 yDb
3

lp = (8.51)
4 pu

Based on a semi - empirical expression, which was derived regarding the subgrade

support reaction in elastic conditions, the Equation 8.51 can be written as Equation

8.53:

300 c u y (8.52)
Pu =
Db

1 y D b
4

lp = (8.53)
4 300 c u y

By simplification of Equation 8.53, the hinge point location can be expressed as

Equation 8.54. Hinge point location gets stable situation with increasing the shear

displacement along the joint. Moreover, the hinge point location is decreased in

higher rock strength. (Figure 8.14)

2 y 12
l p = 0.025 Db ( )
cu y (8.54)

From the previous sections, it is concluded that first yield point will be in hinge point

and by increasing shear load, shear displacement, axial load and axial deformation

281
CHAPTER 8: Analytical aspect of fully grouted bolts

will increase. Then due to these changes, failure position will move towards the joint.

This effect was evaluated by laboratory tests in Bolt Type T5 clearly. The hinge

point location was initially investigated by Dight (1982).

100
.

90 20 MPa
Hinge point distance (mm)

40 MPa
80 100 MPa
70
60
50
40
30
20
10
0
0 2 4 6 8 10 12

Shear displacement (mm)

Figure 8. 14. Hinge point location as a function of shear displacement in elastic


region

8.8. ANALYTICAL METHOD TO DEFINE THE SHEAR


DISPLACEMENT IN CASE OF BOLT MODULUS OF
ELASTICITY

By substituting Eq (8.39) in Eq (8.40), which were expressed in previous section and

simplifications, bending moment at hinge point can be written:

2
M D = Qcf / 2 Pu (8.55)

and, By substituting the Equations 8.38, 8.39 and 8.55 in Equation 8.37, Equation

8.56 is expressed.

282
CHAPTER 8: Analytical aspect of fully grouted bolts

d b 2 y
Qcf = 0.5[ Pu d b ( N cf )]0.5 (8.56)
4

where;

Qcf = shear fore

Lcp = reaction length

Pu = reaction force

y = elastic yield stress

In elastic limit, axial force along the bolt is negligible, this assumption was

confirmed from the laboratory results, which was discussed in previous chapter. So,

the shear force can be written as following equation:

d b 3 y * Pu
Qcf = ( ) 0.5 (8.57)
16

By substituting the Equation 8.57 in Equation 8.58, which was expressed by pellet in

elastic limit for determining the shear displacement, Equation 8.60 is developed.

Pellets theory was according to the beams theory on an elastic foundation the

mechanical performance of the grouted rock bolt:

u oe = 22 .7Q cf
4 1 4 3
E .d b p u sin (8.58)

pu = c d b (8.59)

u oe = 0.08(d b y c d b ) 2 1
3 (8.60)
E .Db ( c d b ) 3 sin
4

where;

c = Uniaxial compressive of surrounding material

283
CHAPTER 8: Analytical aspect of fully grouted bolts

E = bolt modulus of elasticity

= angle between bolt and joint

In this equation the value of axial load is reduced as it is in elastic range. in this range

as laboratory tests showed there was no axial load on the bolt, so it can be removed

from the equation.

Following Equation comes from numerical simulations:

0.14
U oe = 5.5 E b (8.61)

As the Figure 8.15 shows the small difference which is distinguished between the

analytical and numerical curves is due to some assumptions in analytical method

such as defining the same strength for surrounding materials and neglecting of

contact interfaces. However, in numerical simulation, two surrounding materials,

grout and concrete, with different strength and also contact interface properties are

defined, so this small difference is reasonable.

4.5
Shear displacement (mm) .

4 Numerical
Analytical

3.5

2.5

1.5
0 50 100 150 200 250

Bolt modulus (GPa)

Figure 8. 15. Comparison of the numerical and analytical results, concrete 20 MPa,

284
CHAPTER 8: Analytical aspect of fully grouted bolts

8.9. Analysis of a Fully Grouted Elastic Bolt in Plastic


Rock Mass

Following Farmer (1975), the equilibrium of a fully grouted rock bolt may be

written:

Ab x = Fx x (8.62)

x Fx
= (8.63)
x Ab

where;

Ab is bolt cross section area

Fx is the shear load due to bond per unit length in elastic behaviour

du x
x = Eb (8.64)
dx

Then substituting (8.64) into (8.63):

d 2u x Fx
2
= (8.65)
dx Ab Eb

In other words, the shear force due to the bolt can be assumed as a linear function
of the relative slip between the bolt and the rock, Moosavi (1997).
Then,

Fx = K (u r u x ) (8.66)

where;

K = shear stiffness of interfaces (N/mm^2)

285
CHAPTER 8: Analytical aspect of fully grouted bolts

u r = Rock displacement along the bolt (mm) which decreases with distance from the

surface of the excavation and depends of many in situ parameters.

By combining (6.66) and (6.67) the following equation, where is distribution of the

displacement along the bolt is found.

d 2u x Ku x Ku r
2
= (8.67)
dx Ab Eb Ab Eb

The above Equation was considered by Moosavi (1997) as well. However, he

considered both bolt and rock mass in elastic condition. In this model the bolt and

rock mass behaviours are considered elastic and plastic respectively.

u r can be represented by an analytical function of the geometry of the tunnel and

rock surface movement.

u ro .ro
ur = (8.68)
ro + x

where;

ro = Tunnel radius, u ro is the total deformation of the excavation wall, which

depends on the property of the rock mass, maybe, written (Stille et al. 1989):

ro B r
u ro = [2( e ) f +1 + ( f 1)] (8.69)
f + 1 ro

1 +
B= ( Po re ) (8.70)
Er

2
re = ( Po + b ) b (8.71)
1+ k

286
CHAPTER 8: Analytical aspect of fully grouted bolts

And parameters b, k and f can be found from following equations.

c
b= (8.72)
tan

k = tan 2 ( 45 + ) (8.73)
2

tan( 45 + ) (8.74)
f = 2
tan( 45 + )
2

where;

= poison ration of rock mass

Po = in situ stress

c = cohesion

= friction angle

re = the boundary between the zone of plastic and elastic

By substituting Eq (8.69) into Eq (8.68) and then Eq (8.68) into Eq (8.64) a

numerical method has been developed as following.

To solve the Equation (8.64) a numerical method is obtained in which the bolt length

was divided into small equal sections. It should be noted that the bond stiffness was

considered constant. Then the load distribution can be calculated by linking these

small sections together.

As we have,

d 2u x Ku x Ku r
2
= (8.75)
dx Ab Eb Ab Eb

To solve the equation dimensionless quantities are defined.

287
CHAPTER 8: Analytical aspect of fully grouted bolts

x ux ux
x = , u x = , u r =
ro u ro u ro

Then it can be written,

d 2 u x Kro
2 2
Kro
u x = u r (8.76)
dx 2
Ab Eb Ab Eb

2 2
Kro Kr
is a dimensionless quantity. By defining = o it can be written as,
Ab E b Ab Eb

d 2 u x
u x = u r (8.77)
dx 2

By dividing the bolt to the n equal sections (Figure 8.16) and defining

x = xi+1 xi = L and using the following expressions for derivatives of u x


(nro )

at x = xi

li 1 li +1 Nodal point


xi 1 xi xi +1

Figure 8. 16. Notation for numerical formulation

dux ux ( xi+1 ) ux ( xi1 )


= (8.78)
dx 2x

or
du x u x ( xi+1 ) u x ( xi )
= (8.79)
dx x

288
CHAPTER 8: Analytical aspect of fully grouted bolts

d 2 u x u x ( xi+1 ) 2u x ( xi ) + u x ( xi1 )
= (8.80)
dx (x ) 2

Equation (8.77) for i = 2, , n can be written as;

u x ( xi1 ) [2 + (x ) 2 ]u x ( xi ) + u x ( xi+1 ) = (x ) 2 u r ( xi )

These n 1 equation with two boundary conditions will form a tridiagonal

system of n + 1 linear algebraic equations with n + 1 unknowns, { u x ( xi ) },

which can be solved.

1
u r = (8.81)
1 + x

The solution is conducted for two cases;

Case 1: two free ends of the bolt Fx =0 at x =0 and Fx =0 at x=L, where

u ro du x
Fx = Ab Eb ( )
ro dx

Defining normalized force Fx = Fx/ (AbEb) the above boundary conditions will be

equivalent to;

u x ( x 2 ) u x ( x1 ) = 0 and u x ( x n +1 ) u x ( x n ) = 0

Case 2: Faceplate attached to one end > ux = ur0 at x = 0 and Fx = 0 at x = L,

or

u x ( x1 ) = 1 and u x ( x n +1 ) u x ( x n ) = 0

289
CHAPTER 8: Analytical aspect of fully grouted bolts

Figures 8.17 to 8.23 show the distribution of axial load developed along the bolt and

the normalised displacement, without face plate, installed in plastic surrounding

materials. The input data for surrounding materials are used according to SCT report.

The initial stress and rock modulus of elasticity are considered 25 and 15000 MPa

respectively. The effect of bolt length, rock modulus, initial stress and shear stiffness

of the interface are evaluated on the axial load built up along the bolt. Figure 8.17

shows the axial load along the bolt in different bolt length. It displays with increasing

the bolt length, axial load is increased and also the peak point of the load moves

towards the end of the bolt. In addition, the bolt load is concentrated near the

excavation surface. Figure 8.18 shows the normalised displacement as function of

bolt length. It shows with increase of the bolt length, rock displacement is reduced.

Figures 8.19 and 8.20 show the normalised displacement as function of bolt length,

for a 2.1 m bolt, in same rock strength, but different initial stress with various

interface shear stiffness. It shows there are no significant changes on the normalised

displacement at different stress. However, with increase of interface stiffness,

displacement is reduced. It should be noted that according to Equation 8.69 to 8.74,

the value of u ro in 15 and 25 MPa initial stress is 6.3 and 10 mm respectively.

35
Load along the bolt (kN) .

po=25 MPa
30
XL=5m
25 XL=10m
XL=2.1 m
20
15
10
5
0
0 2 4 6 8 10
Bolt length (m)

Figure 8. 17. Axial load along the bolt versus bolt length, in case of unplated with 25
MPa initial stress and 15 GPa modulus of surrounding rock

290
CHAPTER 8: Analytical aspect of fully grouted bolts

0.8
po=25 MPa

Normalised displacement .
0.7
0.6 XL=5m
XL=10m
0.5 XL=2.1 m
0.4
0.3
0.2
0.1
0
0 2 4 6 8 10 12
Bolt length (m)

Figure 8. 18. Normalised displacement versus bolt length in case of unplated with 25
MPa initial stress and 15 GPa modulus of surrounding rock

0.8
Po=25 MPa, E=15 GPa
Normalised displacement

0.75 k=10
k=10
k=1
0.7

0.65

0.6

0.55
0 0.5 1 1.5 2 2.5

Bolt length (m)

Figure 8. 19. Normalised displacement versus bolt length in case of unplated with 25
MPa initial stress and 15 GPa modulus of surrounding rock at different k values

0.8
Normalised displacement .

po=15 k=100
0.75 k=10
k=1
0.7

0.65

0.6

0.55
0.5
0 0.5 1 1.5 2 2.5
Bolt length (m)

Figure 8. 20. Normalised displacement versus bolt length in case of unplated with 15
MPa initial stress and 15 GPa modulus of surrounding rock at different k values

291
CHAPTER 8: Analytical aspect of fully grouted bolts

Figure 8.21 shows the distribution of axial load along the bolt length (2.1 m) in

different interface stiffness. It displays with increase of stiffness the load developed

is increased. Figure 8.22 shows load developed along the bolt increased with increase

of initial stress. This is considered at constant stiffness. Figures 8.23 and 8.24 show

load distribution along the bolt 2.1m and 10 m respectively at 25 MPa initial stress

for different values of rock modulus of elasticity. It displays softer rocks generate

higher value of load along the bolt.

80
Load along the bolt (kN) .

70 Po=25 MPa, E=15 GPa

60 k=1
50 k=10
k=100
40
30
20
10
0
0 0.5 1 1.5 2 2.5

Bolt length (m)

Figure 8. 21. Load developed along the bolt versus bolt length in case of unplated
with 15 MPa initial stress and 25 GPa modulus of surrounding rock at different k
values

16
Load along the bolt (kN) .

14 k=10 po=35 M Pa
Po=25 M Pa
12 P0=15 M Pa
10
8
6
4
2
0
0 0.5 1 1.5 2 2.5
Bolt length (m)

Figure 8. 22. Load developed along the bolt versus bolt length in case of unplated
with 15 GPa modulus of surrounding rock at different initial stresses

292
CHAPTER 8: Analytical aspect of fully grouted bolts

35
E=5GPa

Load along bolt (kN) .


Po=25 MPa
30 E=15GPa
25 E=25GPa
E=50GPa
20
15
10
5
0
0 0.5 1 1.5 2 2.5
Bole length (m)

Figure 8. 23. Load developed along the bolt versus bolt length in case of unplated
with 25 MPa initial stress and different modulus of surrounding rock at k=10
Axial load along bolt (kN) .

120
100 E=5GPa

80 E=15GPa
E=25GPa
60
40
20
0
0 2 4 6 8 10 12

Bolt length (m)

Figure 8. 24. Load developed along the bolt versus bolt length in case of unplated
with 25 MPa initial stress and different modulus of surrounding rock at k=10, L=10
m

Case 2: End plate attached to end

Using Eq 8.76 and boundary conditions in case 2(using end plate), the axial load

built up along the bolt and distribution of the bolt displacement for different bond

strength, rock mass modulus of elasticity, bolt length in various initial stress are

analyzed as follows. Figures 8.25 and 8.26 show the axial load and distribution of the

bolt displacement in two different bond stiffness respectively. It shows the bond

293
CHAPTER 8: Analytical aspect of fully grouted bolts

strength plays a major role on increasing the bolt load and reducing the bolt

displacement.

160
140

Axial load (kN) .


120 k=1
100 k=10
80
60
40
20
0
0.00 0.50 1.00 1.50 2.00 2.50

Bolt length (m)

Figure 8. 25. Load developed along the bolt versus bolt length in case of using end
plate with 25 MPa initial stress and different k, at Er = 5GPa

1.02
Normalised displacement .

1.00
0.98
0.96 k=1
0.94 k=10
0.92
0.90
0.88
0.00 0.50 1.00 1.50 2.00 2.50

Bolt length (m)

Figure 8. 26. Normalised displacement versus bolt length in case of using end plate
with 25 MPa initial stress and different k, at Er = 5GPa

Figures 8.27 and 8.28 show the distribution of axial load and bolt displacement in

different rock modulus and different bolt length. It displays that higher rock modulus

of elasticity generates lower axial load along the bolt. This trend is reduced

exponentially towards the bolt end in both bolt length. Figure 8.29 shows the axial

load distribution along the bolt in different initial stress conditions. It reveals that

294
CHAPTER 8: Analytical aspect of fully grouted bolts

surrounding rocks involved with higher initial stress induces higher axial load along

the bolt. As Figure 8.30 shows, the axial load reduces with decreasing the radius of

plastic zone around the tunnel.

400
350 E=5GPa,L=2.1m
E=15GPa,l=2.1m
.

300
E=5GPa, L=10m
Axial load (kN)

250
200 E=15GPa,l=10m
150
100
50
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00

Bolt length (m)

Figure 8. 27. Axial load versus bolt length in case of using end plate with 25 MPa
initial stress and different rock modulus and bolt length, k=10

1.20
Normalised displacement

1.00
E=15GPa,l=2.1m
0.80
E=5GPa,l=10m
0.60
0.40

0.20
0.00
0.00 2.00 4.00 6.00 8.00 10.00 12.00

Bolt length (m)

Figure 8. 28. Normalized displacement versus bolt length in case of using end plate
with 25 MPa initial stress and different rock modulus and bolt length, k=10

295
CHAPTER 8: Analytical aspect of fully grouted bolts

160
140 E=5GPa,po=25MPa
E=5GPa,po=15MPa

.
120 E=5GPa,po=5MPa

Axial load (kN)


100
80
60
40
20
0
0.00 0.50 1.00 1.50 2.00 2.50

Bolt length (m)

Figure 8. 29. Axial load versus bolt length in case of using end plate in different
initial stress with 5 GPa rock modulus, k=10

160
140
.

E=5GPa, re=4m
120
Axial load (kN)

100 E=5GPa, re=2


80
60
40
20
0
0.00 0.50 1.00 1.50 2.00 2.50

Bolt length (m)

Figure 8. 30. Axial load versus bolt length in case of using end plate in different
plastic zone radius with 5 GPa rock modulus, k=10

From the above analyses in both cases; with and without end plates, it can be inferred

that:

Higher value of k generates higher value of axial loads

Axial load increases with increasing value of initial stress

Higher value of rock modulus of elasticity induces higher value of axial

loads.

296
CHAPTER 8: Analytical aspect of fully grouted bolts

Higher bond strength and bolt length generates the distribution of bolt

displacement reduces with increasing bond strength and bolt length

Lower value of the plastic zone reduces the value of bolt load generation

along the bolt

8.10. CONCLUSION

At hinge point when the elastic limit is reached, bending moment cannot increase

further. Thus the shear force remains constant at very low level. However, maximum

shear stresses are concentrated at bolt joint intersection and numerical design showed

that after elastic limit it cannot increase significantly and remains almost constant. So

as the deflection at bolt joint intersection is higher than hinge deflection around 85%.

Thus the axial stresses at bolt joint intersection will increase and finally with

combination of axial load and shear load bolt will break at bolt joint intersection (see

the laboratory chapter).

From the axial load developed along the elastic bolt surrounded in the elasto plastic

materials in circular tunnel it can be inferred that, bond strength, rock mass modulus

and initial stress affects significantly the load distribution level.

297
CHAPTER 9: Field investigations

CHAPTER 9

FIELD INVESTIGATIONS

9.1. INTRODUCTION

To verify the experimental findings, with respect to the influence of bolt profile

characteristics on load transfer mechanism, a program of field study were undertaken

in two local coal mines Collieries in the Southern Coalfields of Sydney Basin, NSW,

Australia.

The aim of the study was to compare the load transfer capabilities of two different

profiled bolts. The comparative study was carried out by strain gauge

instrumentation of each bolt. In Metropolitan site, the instrumented bolts were

installed at the travelling road with 255 m away from the retreating longwall face at

the time of installation.

In Appin, the instrumented bolts were installed at the belt road, 700 m away from the

retreating longwall face at the time of installation. Two different types of fully

instrumented bolts were installed in each site. The methodology of their installation,

positioning, and regular monitoring is the subject of discussion in this chapter.

9.2. SITE DESCRIPTION

9.2.1. Metropolitan Colliery


Metropolitan Colliery is an underground coal mine situated in the Southern

Coalfields of Sydeny Basin, NSW, Australia, around 35 km north of Wollongong

(Figure 9.1). It is a sophisticated mine, utilising longwall method with continuous

miner development of main headings and longwall gate roads. The average seam

298
CHAPTER 9: Field investigations

thickness of the Bulli Seam in the instrumented site is around 3 m. Underground

access is performed by drift and shaft. A representative geological section and related

strength of materials close to the experimental site, illustrating the immediate roof

stratification above the Bulli seam is shown in Figure 9.2. The roof rock consists

mainly of sandstone and mudstones, and is classified as moderate to strong roof. The

detailed layout of the mine and location of the longwall panel is shown in Figure 9.3.

The maximum horizontal stress at Metropolitan Collier based on measurements in G

panel (Tarrant 2002) is between parallel to the gateroads (030/150 relative to GN) to

30o West of the gateroads (060/120 relative to GN).

Metropolitan
Colliery

a b

Figure 9. 1. Geographical location of (a) Metropolitan and (b) Appin Colliery

Metropolitan Colliery currently drives gateroads N-S and extracts longwall S-N.

From the stress measurements it was found that the vertical stress, 1 = 25 MPa,

oriented between parallel with the current heading direction and 30 west of the

heading direction. 2 = 15 MPa to 17 MPa and 3 = 12.5 MPa vertical. It should

299
CHAPTER 9: Field investigations

be noted that these measurements were conducted within sandstone of modulus 16

GPa. Six, 2.1 m long instrumented bolts were installed at the instrumented site. Three

bolts were of Bolt Type T1 and the other three were Bolt Type T3, which installed in

the longwall panel between C/T 7 and 8. Figure 9.4 shows the bolt installation at the

site.

Sandstone
Height (m)

Sandstone

Sandstone

Mudstone
Mudstone

Coal Bulli
Seam
Laboratory UCS (MPa)
Siltstone
Depth (m)

Sandstone
Sandstone
Siltstone
Sandstone

Figure 9. 2. Modelled geological section and strength profiles (SCT report 2002)

Figure 9.5 shows the details of the instrumented bolt installation pattern. The regular

pattern of bolting in the site was 6 bolts in a row with spacing between the rows 1.2

m. In addition to the instrumented bolts, three extensometer probes were installed

between the two rows of instrumented bolts. However, no extensometer monitoring

was carried, because of the readout box malfunction.

300
CHAPTER 9: Field investigations

Assumed insitu
stress direction

Maingate Concentration of
major horizontal
stress on maingate
side

C/ T 8

C/ T 7
Tailgate Relief

Figure 9.3. The detailed layout of the panel under investigation indicating
instrumentation site at Metropolitan Colliery

Figure 9.4. Photograph of the site with installed bolts

301
CHAPTER 9: Field investigations

TRT1-1 TRT3-1

TRT1-2 TRT3-2
Ordinary bolt
TRT1-3 TRT3-3 Mega bolt
Instrumented bolts
Direction of Development
Long wall retreat
C/ T 8

C/ T 7

Figure 9. 5. Detail site plane of the instrumented bolts at Metropolitan Colliery

9.2.2. Appin Colliery

9.3. INSTRUMENTATION

9.3.1. Instrumented Bolts


An instrumented rock bolt with electrical strain gauges placed at discrete points

along the 2.1 m bolt length. The first step involved in the bolt instrumentation

process was to cut two identical, diametrically opposite channels of 6 mm wide and 3

mm deep each along the bolt axis (see Signer and Rains 2001), leaving outer 100 mm

intact as shown in Figures 9.6. The intact bolt configuration without any channel in

the first 100 mm ensured the stability and integrity of the strain gauges and the

302
CHAPTER 9: Field investigations

corresponding wirings during the installation of bolt in the field. This has been the

normal practice in bolt instrumentation, Signer and Jones (1990). Figure 9.7 shows a

section of a bolt with engraved channels.

Once the channels were cut, they were smoothened with sand paper and wiped clean

with alcohol solvents. A total of 18 strain gauges were mounted on each bolt (9 in

each channel). The spacing between the strain gauges mounted on 2.1 m bolt, was

200 mm. The slots were then filled with silicon gel to cover up the strain gauges, and

allowed to harden for a week prior to installation in the field. Figure 9.8 shows a

section of an instrumented bolt with strain gauges and wirings visible through the

silicon cover.

303
CHAPTER 9: Field investigations

6
100
200

1 21.8

200

2 Cross Section
200
Slot : 6 mm x 2.5 mm
3 Slot Area : < 10 %

200
4
, Gauge Factor 2.15
All Strain Gauges are 5 mm,
120
200

200
2100

200
7

200
Strain Gauges
8

200

300

Long Section

Figure 9. 6. Strain gauge and bolt layout

Figure 9. 7. Bolt segment showing channels

304
CHAPTER 9: Field investigations

Figure 9. 8. A section of an instrumented bolt showing the strain gauge and wirings
through the silicon gel.

9.3.2. Intrinsically Safe Strain Bridge Monitor

An intrinsically safe Strain Bridge Monitor (SBM), IS2000, was used for the

underground measurement of strains developed in the instrumented bolts. The

following description of the SBM is based on an operation handbook prepared by

Strata Control Technology Operations Pty Ltd. The SBM is an electronic instrument

(readout box) that is used for:

Stress monitoring

Measuring bolt loads

Measuring shear displacements

Other strain gauge monitoring applications

The SBM is fully approved for use in Australian Coal Mines. The instrument is

portable and battery powered requiring recharging periodically. When used

underground, the SBM is connected to the instrumented bolts by electrical leads.

Measures were taken throughout the experiment to protect the SBM, leads and

connections from ingress of moisture and dust as these could seriously affect the

measured results. The SBM is set to operate with the more commonly used 120

strain gauges. By choice of appropriate bridge circuit, it was possible to measure the

strain in a single gauge, two gauges or four gauges. The quarter bridge

305
CHAPTER 9: Field investigations

configuration, used in this experiment, was restricted to 120 strain gauges only. As

the SBM had a fixed gauge factor setting of 2.00, the actual strain measurement,

indicated by the display, could be calculated as follows. A general view of the SBM,

while taking reading in underground is shown in Figure 9.9.

2Vd
E= For quarter bridge configuration (9.1)
G

Vd
E= For half bridge configuration (9.2)
G

Vd
E= For full bridge configuration (9.3)
2G

where;

E = the mean actual strain measured by an active gauge,

Vd = the change in SBM reading, and

G = the gauge factor of the strain gauge.

Figure 9. 9. A general view of the SBM, while taking readings in underground

306
CHAPTER 9: Field investigations

9.4. FIELD MONITORING AND DATA ANALYSING

9.4.1. Metropolitan Colliery

Following of the bolt installation, site monitoring was carried out at regular periods,

until the site was over run by the approaching longwall face.

When rock bolts are installed in the tunnel, the load generation initiates at the bolt /

grout / rock structure. The whole full length of the bolt can experience loading. In

reality, when adjacent rock blocks are sheared, due to joint roughness dilation occurs

and this generates tensile forces in the bolt. After decoupling rock bolts according to

their profile configurations behave differently.

Figures 9.10 and 9.11 Show the load developed on both bolt Types T1 and T3

respectively with respect to the approaching longwall positions, right, middle and left

bolts of the traveling road. The details results are presented in Appendix.

Despite the mega bolt installation at the right side of the road, there was higher shear

loading as compared to the bolts at other side of road, which is due to the direction,

and impact of the horizontal stresses. In addition, it shows that Bolt Type T3 had

higher load developed at the left and right side as compared to Bolt Type T1 (30 kN

in Bolt Type T3 against 28 kN in Bolt Type T1). However, the load transferred at the

middle of the section was almost the same in both types of bolts. It is to be noted

that, because of the increased distance between the longwall face position and the

location of the instrumented site, the load developed on each bolt was not maximum

at this stage and that the final load developed would be significantly greater than the

recorded amount.

307
CHAPTER 9: Field investigations

2500
TRT1-1
TRA6 (Installed at the right)

Roof height (mm) .


2000

1500
255.0
221.0
140.0
1000 90.0
25.0
1.0
500 -110.0
-163
-260
0
-5 0 5 10 15 20 25 30

Load on bolt (kN)

2500
TRA5 (Installed at the middle)
TRT1-2
.

2000
255
Roof height (mm)

221
1500 140
90
1000 25
1
-110
500 -163
-260
0
-10 0 10 20 30 40

Load on bolt (kN)

255.0
2500 TRA1 (Installed at the left)
TRT1-3 221.0
140.0
90.0
Roof height (mm) .

2000 25.0
1.0
-110.0
1500 -163
-260

1000

500

0
0 2 4 6 8 10 12

Load on bolt (kN)

Figure 9. 10. Load transferred on the bolt Type T1 installed at the right side of the
TR, Metropolitan Colliery.

308
CHAPTER 9: Field investigations

2500 TRJ1 (Installed at the right)


TRT3-1

.
255.0
2000

Roof height (mm)


221.0
140.0
1500 90.0
25.0
1000 1.0
-110
500 -163
-260
0
-10 0 10 20 30 40

Load on bolt (kN)

2500
TRT3-2
TRJ3 (Installed at the middle)
.

2000
Roof height (mm)

1500
255.0
221.0
1000 140.0
90.0
25.0
1.0
500 -110.0
-163
-260
0
-5 0 5 10 15 20 25

Load on bolt (kN)

2500 TRJ6
TRT3-3 255.0
.

221.0
2000 (Installed at the left) 140.0
Roof height (mm)

90.0
1500 25.0
1.0
1000 -110.0
-163
500 -260

0
-5 0 5 10 15 20 25 30

Load on bolt (kN)

Figure 9.11. Load transferred on the bolt Type T3 installed at the right side of the
TR, Metropolitan Colliery.

309
CHAPTER 9: Field investigations

Figures 9.12 and 9.13 show the corresponding shear stresses at the bolt resin

interface for both bolt Types T1 and T3 respectively. The shear stress developed at

the bolt resin interface was calculated by using the following equations:

F1 F 2
= (9.4)
dl

where;

= average shear stress at the bolt-resin interface,

F1 = axial force acting in the bolt at strain gauge position 1, calculated from

strain gauge reading,

F2 = axial force acting in the bolt at strain gauge position 2, calculated from

strain gauge reading,

d = bolt diameter, and

l = distance between strain gauge position 1 and strain gauge position 2.

From the results it was found that the shear stress sustained by the bolt/resin

interface had almost the same magnitude in Bolt Types T1 and T3 in the middle

and right side of the roadway, at approximately 1.1 MPa. However, the

magnitude of the shear stress developed in the Bolt Type T2 at the left side of the

roadway was nearly four times of the Bolt Type T1 (1.2 against 0.3). This is due

to the wider profile spacing and higher profile height, which is consistent with

the laboratory results found from pull and push results. (See chapter 4). It should

be noted that if shear stress is negative, it would indicate that the shear stress is

towards the tunnel wall, and plus would have meat that it is against the tunnel

wall (Cai et al 2004).

310
CHAPTER 9: Field investigations

2500 255.0
TRT1-1
TRA6 221.0
2000 Installed at the right 140.0

Roof height (mm) .


90.0
1500 55.0
25.0

1000 1.0
-110.0

500 -163
-266

0
-1.5 -1.0 -0.5 0.0 0.5 1.0 1.5

Shear stress (MPa)

2500 TRA5
TRT1-2
255
Installed at the middle
Roof height (mm) .

2000 221
140
1500 90
25
1000 1
-110
-163
500
-260

0
-1.0 -0.5 0.0 0.5 1.0 1.5 2.0

Shear stress (MPa)

TRA1 2500
TRT1-3 255.0
.

Installed at the left 221.0


Roof height (mm)

2000
140.0
90.0
1500
25.0

1000 1.0
-110
500 -163
-260
0
-0.8 -0.6 -0.4 -0.2 0.0 0.2 0.4

Shear stress (MPa)

Figure 9. 12. Shear stress developed at the bolt/resin interface of the Bolt Type T1, in
Metropolitan Colliery.

311
CHAPTER 9: Field investigations

2500 TRJ6
TRT3-3 255.0

.
Installed at the left 221.0
2000

Roof height (mm)


140.0
90.0
1500
25.0

1000 1.0
-110.0
500 -163
-260
0
-1.5 -1.0 -0.5 0.0 0.5 1.0 1.5

Shear stress (MPa)

TRJ3 2500 255.0


TRT3-2
Installed at the middle 221.0
.

2000
140.0
Roof height (mm)

90.0
1500
25.0
1000 1.0
-110
500 -163
-260
0
-1.0 -0.5 0.0 0.5 1.0

Shear stress (MPa)

TRJ1
TRT3-1 2500
255.0
Roof height (mm) .

Installed at the right 221.0


2000
140.0
1500 90.0
25.0
1000 1.0
-110
500 -163
-260
0
-2.0 -1.5 -1.0 -0.5 0.0 0.5 1.0 1.5

Shear stress (MPa)

Figure 9. 13. Shear stress developed at the bolt/resin interface of the Bolt Type T3, in
Metropolitan Colliery.

Appin

312
CHAPTER 10: Conclusions and recommendations

CHAPTER 10

CONCLUSIONS AND RECOMMENDATIONS

10.1. SUMMARY

The load transfer mechanism and reinforcement system behaviour has been

comprehensively investigated during the course of this research. The thesis has

presented methods and results of experimental testing in both axial and lateral

loading conditions, finite element analyses and field investigations carried out over

three years. The main them and philosophy throughout the work was: (i) The

evaluating of the shear behaviour mechanism in bolt-grout and grout-rock interfaces

in the laboratory, numeric and field in different Types of bolts, resin thickness and

different concrete strength, (ii) design and develop a shear testing machine which

meets and removes the relevant problems in previous machines, (iii) The effect of

bolt pretensioning, bolt profile and thread rebar specifications on shear behaviour

and load transfer mechanism, (iv) Numerical analyses of bolt-joint-concrete and

contact elements in both axial and lateral applied loads.

10.2. CONCLUSIONS

A number of important parameters have been identified which affect the load transfer

mechanism and bolt behaviour subjected to axial and lateral loading conditions.

Accordingly, a series of experimental studies, numerical techniques and field

investigations were undertaken. The following sections describe the main

conclusions drawn from this research.

313
CHAPTER 10: Conclusions and recommendations

10.2.1. Literature survey

In can be inferred from this review that:

For rock /concrete samples reinforced with bolt inclined at an angle to the

normal of the joint plane, bolts failed in tension near the shear surface. In

addition, inclined bolts are stiffer to the shear strength of the bolted blocks

than the perpendicular bolts. Moreover, shear displacement at failure is

minimal for inclinations between 40o and 50o.

For samples with a bolt forming a small angle to the normal of the joint

plane, bending of the bolts becomes predominant even when the shear force

is small,

The vertical height of the bended bolt is about 2-4 times the bolt diameter

called effective height, corresponding to an effective length.

Large bolt diameter reduces shear displacement required for obtaining a

given shear force.

Bolt pretensioning reduces shear displacement, but not the shear resistance.

Direct shear test produces overturning moments, which produce rotation in


the shear box and create a non uniform stress profile. Accordingly it is

inferior because of non-uniform distribution of stress concentration on the

shear joint and along the bolt in direct shear machine.

10.2.2. Experimental investigations

Bolt profile configuration is an important parameter in load transfer

capacity of bolt.

314
CHAPTER 10: Conclusions and recommendations

Profile spacing dictates the level of peak load - displacement, which intern

accommodates a relatively greater level of strata movement.

High profiles increases load transfer capacity of the bolt.

Yielding and necking is unlikely to occur in bolts tested in 75 mm long

steel sleeves as the peak shear load was around 40% of the maximum

tensile strength of the steel.

Push test showed the higher value of shear stress capacity of bolt compared

with pull test.

The load failure of the resin / bolt surface contact is dependent on the

profile height as well as spacing.

Increasing resin annual thickness reduces the load transfer capability of bolt

subjected to axial loading conditions. However, it depends upon the

surrounding material strengths subjected to lateral loading conditions.

The double shear system represented a better method of shearing system as

it enabled to allow a symmetric study of bolt shearing analysis.

The maximum bolt contribution of the bolts significantly depends upon the

concrete strength and bolt pretension load.

Bolt contribution was increased around 15 % with existence of the resin

grout compared with absence of the grout at the same conditions.

Physical and mechanical properties of the bolt types affect the bolt joint

contribution.

The axial and shear loads are at their maximum at the bolt - joint

intersection.

315
CHAPTER 10: Conclusions and recommendations

From the bolt Type T1 in 100 MPa concrete it was found that the maximum

bolt-joint contribution at failure is about 120 % of the maximum tensile

strength of the bolt.

The value of bolt contribution at yield point in concrete 20, 40 and 100

MPa in Bolt Type T1 was about 0.24, 0.3 and 0.52 respectively.

Increasing the concrete strength reduces significantly the joint shear

displacement and contributed to increased shear stiffness.

In lateral loading conditions, the effect of resin and concrete strength is

more effective than the resin thickness.

Hinge point distance was reduced with increase of the resin annulus, when

surrounding material was weaker than the resin strength

An extensive stress and strain was developed on the resin / concrete

interface in soft concrete during the bolt bending.

In all bending situations, axial fractures were created along the concrete

blocks after the yield point.

Shear stress in softer concrete was lower than the harder concrete due to the

excessive deformation. Then the tensile load develops while the dowel

component reduces.

The dowel effect in harder concrete is strong due to the higher shear

resistance. It results bolt to cut before excessive deformation. So, it prevents

the excessive axial load generation along the bolt.

316
CHAPTER 10: Conclusions and recommendations

10.2.3. Numerical analyses

The yield limit of the bolt first begins from the hinge points at both sides of

the shear joint.

Further increase in the shear force beyond the yield point has no apparent

influence on the stresses in the hinges.

The distance between the hinge points reduced with increasing the concrete

strength.

During the shearing process the tension and the compression stresses and

strains were generated in the upper and lower fibre of the bolt in the vicinity

of the shear joint.

Bolt profile in the vicinity of the bolt-joint intersection experienced the

maximum shear stress value. In addition, there was an exponential

relationship between the value of the shear stress and the distance from the

shear joint.

The shear stress value was not exceeded during further loading after the yield

point. Eventually, the combination of this stress with induced tensile stress at

the bolt-joint intersection lead the bolt to failure.

By increasing the bolt pretension load, the shear stress was decreased and this

was also observed in different concrete strength.

The value of strain along the concrete and grout was reduced with increasing

the pretensioning.

The induced stresses exceeded the uniaxial compressive strength of the grout

and concrete in the vicinity of the bolt joint intersection, causing them

crushing.

317
CHAPTER 10: Conclusions and recommendations

The average shear stress capacity of a bolt in a push test was greater than that

in a pull test.

Bolt-resin interface failure occurred by initially shearing of the grout at the

profile tip in contact with the resin.

Numerical simulation provided an opportunity to understand better the

stresses and strains generated as a result of bolt resin interface shearing.

10.2.4. Field investigations

10.3. SUGGESTIONS FOR FURTHER RESEARCH

This research provided a comprehensive understanding of some of the significant

factors that affects the load transfer mechanism, such as; bolt profile characteristics,

mechanical and physical bolt property, different surrounding concrete strength and

resin thickness, various pretension loads. However, still it needs more and further

research in this field.

Double shearing system (DSS) provides the better understanding of the

bolt/joint interaction. However, it is recommended that the size of the double

shearing apparatus system to be doubled for effective results. The design of

the new shear box is completed and the apparatus is under construction for

future research (Figure 10.1).

To better understanding of the resin thickness subjected to lateral loading

conditions, more tests needs to be undertaken in different concrete strength.

318
CHAPTER 10: Conclusions and recommendations

Further studies on hard concrete strength (more than 100 MPa) are

recommended to obtain better understanding of the load transfer in hard rock

conditions.

In very hard rock conditions, the use of real rocks instead of concrete is

recommended.

To find the actual load transfer mechanism in high profile spacing in different

bolt types, the use of longer steel sleeve is recommended.

Effect of bolt, grout and concrete modulus of elasticity in different concrete

strength and resin thickness in non-linear condition is recommended by

numerical simulations.

319
References

REFRENCES

Abedi, K., H. Afshin and A. Ferdousi (2003). Investigation into the behaviour of a
novel steel section for concrete filled tubular columns under axial and cyclic
loadings. Int. Symp. on Advances in structures, Australia.891-897.

Afridi, A. J., Kown S and Wilson J.W (2001). Investigation of rock failure in a direct
shear machine. Mining technology 110.(3): 158-162.

Ansell.A (2005). Laboratory testing of a new type of energy absorbing rock bolt.
Tunnelling and underground space technology 20.(4): 291-300.

Aydan, O. and T. Kawamoto (1992). Shear reinforcement effect of rockbolts in


discontinious rock masses. Int.Sym. of Rock support in mining and underground
construction, Canada.483-489.

Aydan.O (1989). The stabilisation of rock engineering structures by rock bolts.


Geotechnical Engineering.Thesis. Nagoya, Nagoya: 202.

Aydan.O, Ichikawa.Y and Kawamoto.T (1985). Load bearing capacity and stress
distribution in/along rockbolts with elastic behaviour of interfaces. 5th Int.Conf.
Numerical Methods in Geomechanics, Nagoya.(Cited in Moosavi 1994).

Aziz, N. I. (2004). Bolt surface profiles-an important parameter in load transfer


capacity appraisal. Int.Symp.on Ground support, Perth, Western Australia.221-231.

Aziz, N. I. and Webb.B (2003). Load transfer appraisal capacity of bolts using short
encapsulation push test. 4th Underground Coal Operators'Conference, University of
Wollongong,Australia.72-81.

Aziz, Z., D. Campbel and J. Levay (1992). Experience with resin anchored bolts in
large permanent undeground excavation. Int. Symp. of Rock Support in Mining and
Underground Construction, Canada.467-472.

320
References

Azuar.J.J (1977). Stabilisation des massif rocheux fissures par barres dacier scellees.
Rap.de Rech.LPC No.73, Lab.Central des Ponts et Chaussees.(Cited in Spang and
Egger 1990).
Barton. D.B (1967). A history of tin mining and smelting in Cornwall, Publisher:
Barton. 302p.

Benmokran, B., H. Xu and E. Bellavance (1996). Bond strength of cement grouted


glass fiber reinforced plastic (GFRP) anchor bolts. int.J.Rock mechanics and
Min.Sci. 33.(5): 455-465.

Bhashyam.G.R (2002). Ansys Mechanical-A powerful nonlinear simulation tool,


2004. Ansys,Inc. 275 Technology Drive Canonsburge,PA 15317.

Bieniawski, Z. T. (1984). Rock mechaincs design in mining and tunnelling, Balkema


publishers, 272p.

Bjornfot.F and Stephansson.O (1983). Interaction of grouted rock bolts and hard rock
masses at variable loading in a test drift of the Kiirunavaara mine,Sweden. Proc. of
Int. Symp. of Rock bolting, Sweden.86-104.

Bjurstrom, S. (1974). Shear strength of hard rock joints reinforced by grouted


untensioned bolts. Internation congress of rock mechanics.1194-1199.

Bolstad.D and Hill.J (1983). Bureau of Mines rock bolting research. Proceedings of
the International Symposium on Rock Bolting, Abisko, Sweden.313-320.

Brady.B.H.G and Brown.E.T (1985). Rock mechanics for underground mining,


Second Ed. London, George Allen and Unwin Ltd,571p.

Brian.A and B. A. Chappel (1989). Rock bolts and shear stiffness in jointed rock
masses. Journal of Geotechnical Engineering 115.(2): 179-197.

Cai, Y., T. Esaki and Y. Jiang (2004). An analytical model to predict axial load in
grouted rock bolt for soft rock tunnelling. Tunnelling and Underground Space
Technology XXX: 1-12.

321
References

Campbel. R and Mould.R.J (2005). Impacts of gloving and un-mixed resin in fully
encapsulated roof bolts on geotechnical design assumptions and strata control in coal
mines. Int. J. of Coal Geology xx: 1-10.
Campoli, A., P. S. Milis, P. Todo and K. Dever (2002). Optimizing rebar resin
annulus. Mining engineering 54.(3): 42-44.

Carr.F (1971). recent development in strata bolting in National Coal Board mines in
United Kingdom. Aus.IMM Symposium on rock bolting.11p.(Cited in Dight 1982).

Cha.E.J, Choi.S.M and Kim.Y (2003). A moment-rotation curve for CFT square
column and steel beams according to reliability analysis. Int. Conference on
Advances in Structures, Sydney-Australia.943-950.

Chappel, B. A. (1989). Rock bolts and shear stiffness in jointed rock masses.
International Journal of Rock Mechanics and Mining Science & Geomechanics
Abstracts 115.(2): 179-195.

Chappell, B. A. (1987). Predicted and measured rock mass moduli. Mining Science
and Technology 6.(1): 89-104.

Chen, S. H. and P. Egger (1999). Three dimensional elasto-viscoplastic finite


element and its application. Int. J. for Numerical and analytical methods in
geomechanics 23: 61-78.

Chen, S. H. and G. N. Pande (1994). Rheological model and finite element analysis
of jointed rock masses reinforced by passive, fully-grouted bolts. International
Journal of Rock Mechanics and Mining Science & Geomechanics Abstracts 31.(3):
273-277.

Chen, S. H., S. Qiang and S. F. Chen (2004). Composite element model of the fully
grouted rock bolt. Rock mechanics and rock engineering 37.(3): 193-212.

Coates.D.F and Yu.Y.S (1970). Three dimensional stress distribution around a


cylindrical hole and anchor. Proceeding of 2nd Int. Cong. Rock Mechanics.175-182.

322
References

Compton.C and Oyler.D (2005). Investigation of Fully Grouted Roof Bolts Installed
Under In Situ Conditions. Proceedings of the 24th International Conference on
Ground Control in Mining. Morgantown,, WV: West Virginia University;.302-312.

Crawley. S.W, Dillon R.M and C. W.O (1984). steel buildings (analysis and design),
3rd ed. New York, 673p

Crawley.S.W and Dillon.R.M (1984). Steel buildings : analysis and design. 3rd Ed.
New York, Wiley. 673p.

Dey.A (2001). Shear behaviour of fully grouted bolts under constant normal stiffness
condition. Civil, Mining and Environmental Eng.Thesis. Wollongong, Wollongong:
273.

Dight.P.M (1982). Improvements to the stability of rock walls to open pit


mines.Thesis. Melborn, Monash: 395.

Dulacska.H (1972). Dowel action of reinforcement crossing cracks in concrete.


Journal of the American Concrete Institute 69.(12): 754-757.

Ebisu.S, Aydan.O and Komura.S (1993). Mechanism of interface failure of rock


anchors. Int.Conf. of Assessment and Prevention of Failure Phenomena in Rock
Engineering.677-685.

Eddy, G. E., C. Rightmire, T. and C. W. Byrer (1982). Relationship of methane


content of coal rank and depth theoretical vs. observed. SPE/DOE Symposium on
unconventional gas recovery, Pittsburgh, Pa., USA

Egger.P and Fernandes.H (1983). A novel triaxial press-study of anchored jointed


models. 5th Congr. on rock mechanics,ISRM, Melbourn.171-175.

Egger.P and Zabuski. L (1991). behaviour of rough bolted joints in direct shear tests.
7th Int. Congress on rock mechanics, Aachen, Germany, A.A. Balkema.1285-1288.

323
References

Fabjanczyk, M. W., K. Hurt and D. Hindmarsh (1998). Optimisation of roof bolt


performance. Int. Conf. on geomechanics / ground control in mining and
underground construction, Wollongong University.413-424.

Fabjanczyk, M. W. and G. C. Tarrant (1992). Load transfer mechanisms in


reinforcing tendons. International confress on ground control in mining, Wollongong
University.212-218.

Fanning, P. (2001). Nonlinear models of reinforced and post tensioned concrete


beams. Structural engineering: 111-119.

Farmer, I. W. (1975). Stress distribution along a resin grouted rock anchor. Rock
mechanics and mining science 12: 347-351.

Feng.P, Lu.X.Z and Ye.L.P (2002). Experimental research and finite element
analysis of square concrete column confined by FRP under uniaxial compression.
17th Australian Conference on the Mechanics of Structures and Materials, Gold
Coast, Australia.60-65.

Ferrero. A.M (1995). The shear strength of reinforced rock joints. Int. J.Rock
Mech.Min.Sci.&Geomech. Abstr. 32.(6): 595-605.

Flow science Inc (2005). Implicit Versus Explicit Methods, 2005.


http://www.flow3d.com/Cfd-101/impvexp.htm.

Franklin.J.A and Dusseault.M.B (1989). Rock Engineering. McGraw-Hill,New


York,USA,600p.

Fuller, P. G. and R. H. T. Cox (1975). Mechanics of load transfer from steel tendons
to cement based grout. Proc. of 5th. Australian Conference on the mechanics of
structures and materials,, Melbourne.

fundamentals), e. E. (2005).
http://www.efunda.com/formulae/solid_mechanics/failure_criteria/failure_criteria_d
uctile.cfm( accessed in Dec 2005), 2005.

324
References

Gale, W. J. and R. L. Blackwood (1987). stress distribution and rock failure around
coal mine roadway. Int.J.rock Mech. Min. Sci. and Geomech. Abstr. 24.(3): 165-173.

Gardner, F. J. (1971). History of rock bolting. Symposioum on rock bolting, The


Australia Institute of mining and metallurgy.14p.

Gerdeen, J. C., V. W. Snyder and Viegelahn.G.L. (1997). Design criteria for roof
bolting plans using fully resin grouted nontensioned bolts to reinforce bedded mine
roof.

Gerrard.C (1983). Rock bolting in theory. Int. Symp. on rock bolting, Sweden.131-
160.

Giraldo L., Cotten S., Farrand J., Pile J. and Bessinger S. (2005). Improved pull out
strength of fully grouted roof bolts through hole geometry modification. 24th
Internation conference on ground control in mining, West Virginia.279-284.

Goris. J.M, Martin. L.A and Curtin. R (1996). Shear behaviour of Cable bolt
supports in horizontal, bedded deposits. Proceeding of 15th Int. Conference on
ground control in mining, WV. USA, Colorado School of Mines.511-521.

Grasselli, G. (2005). 3D Behaviour of bolted rock joints: experimental and numerical


study. International Journal of Rock Mechanics and Mining Sciences 42.(1): 13-24.

Grasselli, G., M. Kharachfi and P. Egger (1999). Experimental and numerical


comparison between fully grouted and frictional bolts. Proce. 9th Int. Symp. on Rock
Mechanics,ISRM, Paris.903-907.

Gray, P. A., N. Hunt and M. W. Fabjanczyk (1998). New development in ground


support with particular refrence to high capacity, High load transfer rock bolts. Int.
Conf. On geomechanics/ ground control in mining and underground construction,
Wollongong University.513-5124.

Hagan, P. C. (2003). Observation on the differences in load transfer of a fully


encapsulated rockbolt. 1st Australian ground control in mining, Australia.10-13.

325
References

Hagan. P.C (2003). The variability of some rockbolt parameters and their potential
impact on anchorage performance in coal mines.UNSW.Research center. 8 p.

Harrison.N.J (1987). The design of roof bolting systems. Colliery Guardian 235.(9):
366-372 (Cited in Jafary 1994).

Hartman.W and Hebblewhite.B (2003). Understanding the performance of rock


reinforcement elements under shear loading through laboratory testing- A 30 year
history. 1st AGCM Conference

Hartman.W and Hebblewhite.B (2003). Understanding the performance of rock


reinforcement elements under shear loading through laboratory testing-A 30 year
history. 1st ACGM Conference, Australia.7p.

Hass, C. J. (1981). Analysis of rock bolting to prevent shear movement in fractured


ground. Mining engineering 33: 698-704.

Hass.C.J (1976). Shear resistance of rock bolt. Journal of Transactions, Society of


Mining Engineers of AIME: 1-31.

Hebblewhite.B.K (2005). Status of roof bolting research at UNSW.

Hematian.J (1994). Stability of roadways and intersections. Civi and Mining


Eng.Thesis. Wollongong, Wollongong: 269.

Hetenyi.M (1961). Beams on elastic foundation. Ann Arbor: The University of


Michigan Press. Sixth printing (cited in Holmberge 1991).

Hibino.S and Motijima.M (1981). Effects of rock bolting in jointy rocks. Proceeding
of the Int. Sym. on weak rock.1057-1062.

Hoek.E and Wood.D.F (1988). Rock support. Mining Magazine 159.(4): 5p (cited in
Jafary 1994).

Hollingshead.G.W (1971). Stress distribution in rock anchors. Canadian


Geotechnical Journal 8: 588-592.

326
References

Holmberge.M (1991). The mechanical behaviour of untensioned grouted rock


bolts.Thesis. Stockholm, Royal Institute of Technology: 127p.

Holmberge.M and Stille.H (1992). The mechanical behaviour of a single grouted


bolt. Int. Sym. of Rock support in mining and underground construction,
Canada.473-481.

Hong.S.D, Choi.S.M and Kim.Y (2003). A moment-rotation curve for CFT square
columns and steel beams. Int. Conference on Advances in Structures, Sydney-
Australia.951-956.

Hyett, A. J., W. F. Bawden, G. R. Macsporran and M. Moosavi (1995). A


constitutive law for bond failure of fully-grouted cable bolts using a modified hoek
cell. International Journal of Rock Mechanics and Mining Science & Geomechanics
Abstracts 32.(1): 11-36.

Hyett, A. J., W. F. Bawden and R. D. Reichert (1992). The effect of rock mass
confinment on the bond strength of fully grouted cable bolts. Int.J.Rock mechanics
and Min.Sci.&Geomech.Abstr. 29.(5): 503-524.

Hyett. A.J, Mossavi.M and Bawden. W.F (1996). Load distribution along fully
grouted bolts, with emphasis on cable bolt reinforcement. Int.J. for Numerical and
Analytical Methods in Geomechanics 20: 517-544.

Indraratna. B and Haque.A (2000). Shear behaviour of rock joints,Rotterdam,


Netherlands : Balkema.

Indraratna.B and Kaiser. P. K (1990). Design for grouted rock bolts based on the
convergence control method. International Journal of Rock Mechanics and Mining
Science & Geomechanics Abstracts 27.(4): 269-281.

Indraratna.B and Kaiser.P.K (1990). Analytical model for the design og grouted rock
bolts. Int.J. for Numerical and Analytical Methods in Geomechanics 14: 227-251.

327
References

Ivanovic.A, Starkey.A, Neilson.R.D and Rodger.A.A (2003). The influence of load


on the frequency response of rock bolt anchorage. Journal of Advances in
engineering software 34: 697-705.

Jafari, A. and V. S. Vutukuri (1998). Numerical modelling of conventional and pre-


tensioned roof bolting methods in an underground coal mines. Int. Conf. on
geomechanics/ground control in mining and underground construction, Wollongong
University.987-996.
Jafari.A (1994). Application of high pre-tension to full-column grouted bolts in
roadway support in underground coal mines. Mining engineering.Thesis. Sydney,
New South Wales.

John.C.M and Van Dillen.D.E (1983). Rock bolts: A new numerical representation
and its application in tunnel design. Proc.24th U.S. Symp. Rock Mech., Texas A&M
University.13-25(Cited in Moosavi 1994).

Junlu.L (1999). A new rock bolt design criterion and knowledge -based expert
system for stratified roof, Virginia Polytechnic Institute and State University. Ph.D
Thesis.: 177p.

Junlu.L (1999). A new rock bolt design criterion and knowledge-based expert system
for stratified roof.

Kaiser, P. K., S. Yazici and J. Nose (1992). Effect of stress change on the bond
strength of fully grouted cables. International Journal of Rock Mechanics and Mining
Science & Geomechanics Abstracts 29.(3): 293-306.

Karanam.U.M.R and Dasyapu.S.K (2005). Experimental and numerical


investigations of stresses in a fully grouted rock bolts. Geotechnical and Geological
Engineering 23: 297-308.

Kharchafi.M, Grasselli.G and Egger.P (1998). 3D behaviour of bolted rock


joints:Experimental and numerical study, Int.Sym. of Mechanics of jointed and
faulted rock.299-304.

328
References

Kilic .A and Anil. M (1999). The effects of grout properties to the bolt capacity. 16th
Mining congress, Turkey.189-196 cited in Kilic et al (2002).

Kilic .A, Yasar. E and Celik. A.G (2002). Effect of grout properties on the pull out
load capacity of fully grouted rock bolt. Tunnelling and underground space
technology 17: 355-362.

Kilic, A., E. Yasar and C. D. Atis (2003). Effect of bar shape on the pull-out capacity
of fully-grouted rockbolts. Tunnelling and underground space technology 18.(1): 1-6.

Koshti.A (2002). Simulation of effect of bending stress on the beam. Proceeding of


SPIE
Koshti.A (2002). Simulation of ultrasonic measurment on a bolt in a shear joint.
Proceeding of SPIE.411-422.

Lang.T.A, Bischoff.J.A and Wagner.P.L (1979). A program plan for determining


optimum roof bolt tension-theory and application of rock reinforcement systems in
coal mines, USBM: 256p(Cited in jafary 1994).

Larsson.H and Olofsson.T (1983). Bolt action in jointed rock. Proc.Int.Symp.of Rock
Bolting, Sweden.179-192.

Li, C. and B. Stillborg (1999). Analytical models for rock bolts. International Journal
of Rock Mechanics and Mining Sciences 36.(8): 1013-1029.

Littlejohn.G.S and Bruce.D.A (1975). Rock anchors-state of the art,Part 1:design.


Ground Engineering.25-32 (Cited in Dey 2001).

Littlejohn.S (1993). Rock reinforcement-technology, testing, design and evaluation.


Comprehensive Rock Engineering Principals, Practice and Projects(Ed.J.A.Hudson)-
V.4, 413-451.

Lorig, L. J. (1985). A simple numerical representation of fully bonded. Journal of


Computers and Geotechnics 10: 79-87.

Ludvig. B (1983). shear tests on rock bolts. Int. Sympo. on rock bolting,
Sweden.193-203.

329
References

Mahony.L, Hagan.P, Hebblewhite.B and Hartman.W (2005). Development of a


facility for testing shear performance of installed rock reinforcement tendons. Proc.
of 24th Int. Conf. on Ground Control in Mining, WV. Morgantown.USA.357-365.
Maleki, H. (1992). significance of bolt tension in ground control. rock support in
mining and underground construction, Canada.439-443.

Marence.M and Swobodea. M (1995). Numerical model for rock bolt with
consideration of rock joint movements. Rock Mechanics & Rock Enginnering 28.(3):
145-165.

Mark.C., Compton.C, Oyler.D and Dolinar.D (2002). Anchorage pull testing for
fully grouted roof bolts. 21st International Conference on Ground Control in Mining,
Morgantown,W.V.105-113.

Mikula.P.A (2004). Changing to the Posimix4 resin bolt for Jumbo and Quick-
Chenat Mt Charlotte mine. Proc. of the Fifth Int. Symp. on Ground support,
Perth,Western Australia.211-221.

Moosavi, M. and W. F. Bawden (2003). Shear strength of Portland cement grout.


Journal of Cement and Concrete Composites 25.(7): 729-735.

Moosavi.M (1997). load distribution along fully grouted cable bolts based on
constitutive models obtained from modified Hoek cells. Mining Eng.Thesis. Ontario,
Queen: 287.

Moussa.A and Swoboda.G (1995). Interaction of rock bolts and shotcrete tunnel
lining. Int.Sym. of Numerical models in Geomechanics.443-449.

Nitzsche. R. N and Haas. C. J (1976). Installation induced stresses for grouted roof
bolts. International Journal of Rock Mechanics and Mining Science & Geomechanics
Abstracts 13.(1): 17-24.

Norusis. M.J (1997). SPSS 7.5 guide to data analysis, Upper Saddle
River,N.J:Prentice Hall,553p., SPSS Inc.

330
References

Obert.L and Duvall.W.I (1967). Rock mechanics and the design of structures in rock.
Wiley,New York.650p.
Ostreberge. J.O and Gill. S.A (1973). load transfer mechanism for piers. Proceedings
of the 9th Canadian rock mechanics symposium, Montreal , Canada, Mines Brance,
Departement of Energey, Mines and Resources.235-262.

Pal.S and Wathugala.G.W (1999). Distribution state model for sand-geosynthetic


interfaces and application to pull out tests. Int.J. for Numerical and Analytical
Methods in Geomechanics 23: 1873-1892.

Palmer.W.T, Bailey.S.G and Fuller.P.G (1976). Experience with pre-placed supports


in timber and cut and fill stopes. Proc.AMIRA tech.Meeting, Wollongong.45-71.

Panek.L.A (1956). Theory of model testing as applied to roof bolting: U.S.Bureau of


Mines,R.I.5154.(cited in Moosavi 1994).

Parker.H, Hargraves.R.P.N, Ramsell.R and Hawkins.A (1973). Strata reinforcement


using the technique of long hole resin dowelling. The Mining Engineer,.pp.519-
532.(Cited in Dight 1982).

Pell. P.J.N (1974). The behaviour of fully bonded rock bolts. Int. Congress on rock
mechanics, Rotterdam, S.N.1212-1217.

Pellet.F (1994). Strength and deformability of jointed rock masses reinforced by rock
bolts. Civil Engineering.Thesis. Lausanne, Institute of Technology: 206.

Pellet.F and Boulon.M (1995). A constitutive model for the mechanical behaviour of
bolted rock joint. Mechanics of jointed and faulted rock.179-183.

Pellet.F and P. Egger (1996). Analytical model for the mechanical behaviour of
bolted rock joints subjected to shearing. Journal of Rock mechanic and rock
engineering 29.(2): 73-97.

Pellet.F, Egger.P and Ferrero.A.M (1995). Contribution of fully bonded rock bolts to
the shear strength of joints:Analytical and experimental evaluation. Mechanics of
Jointed and Faulted rock.873-878.

331
References

Peng, S. and S. Guo (1992). An improved numerical model of grouted bolt-roof rock
interaction in underground openings. Rock support in mining and underground
construction, Canada.67-74.

Peng. S and Chiang. H. S (1984). Longwall mining, Wiley, International


Publication,267p.

Peng.S (1986). Coal mining ground control, A Wiley-Interscience.

Pool.G, Cheng.Y and Mandel.J (2003). Advancing analysis capabilities in Ansys


through solver technology. Electronic transactions on numerical analysis 15: 106-
121.

Reed.J.J (1974). Rock reinforcement and stabilization-bolting alternatives. Mining


Congress.pp.40-45 (Cited in Dight 1982).

Robert.DP (1995). Testing of mining tunnel support elements and systems for hard
rock mines, Master of Science in Engineering to Departement of Mechanical
Engineering, University of Natal, South Africa: 206.

Saeb, S. and B. Amadei (1992). Modelling rock joints under shear and normal
loading. Int.J.Rock mechanics and mining science 29.(3): 267-278.

Saeb.S and Amadei.B (1990). Finite element implementation of a new model for
rock joints. Int. Symp. of Rock Joints.707-712.

Sakurai.S and Kawashima.I (1992). Modelling of jointed rock masses reinforced by


rock bolts. Rock support in mining and underground construction, Canada.547-550.

Schach. R, Garshol. K and Heltzen. A.M (1979). Rock bolting A practical handbook,
Wheaton &Co.Ltd.,Exeter.

Schubert.P (1984). The bearing capacity of fully grouted rock bolts at shearing
jonts.Thesis. Leoben, Montan: 176.

332
References

Schwab. P.M (1976). An elasticity and finite element study of the fully grouted resin
roofbolt under transvers loading. Eng. Department, Michigan: 87.

Serbouski, M. O. and S. P. Singer (1987). Linear load transfer mechanics of fully


grouted roof bolts: 15p.

Sharma K. G. and Pande G. N. (1988). Stability of rock masses reinforced by


passive, fully-grouted rock bolts. International Journal of Rock Mechanics and
Mining Science & Geomechanics Abstracts, 25.(5): 273-285.

Siab, L. (2001). Stability analysis of jointed rock slopes reinforced by passive, fully
grouted bolts. Computers and Geothechnic 28: 325-347.

Signer. S. P and S. D. Jones (1990). Case study on the use of grouted roof bolt
loading in a two-entry gate road. 31st US Symp. on Rock Mechanics.145-152.

Signer. S. P and Raines.R (2001). Effects of bolt spacing and bolt length and roof
span on bolt loading in a Trona mine. 20th Intl Conf on Ground Control in Mining.
Morgantown, y, WV: West Virginia Universit.302-308.

Singer, S. P. (1990). Field verification of load transfer mechanics of fully grouted


roof bolts. US Bureau of Mines.(9301).
Sinha.R.S and Schoeman.K.D (1983). Rock tunnels and rock reinforcement. Int.
Symp. of Rock bolting, Sweden.310-321.

Skybey. G (1992). A new rock bolting concept fro underground roadways. 11th
International Conference on Ground Control in Mining, Wollongong University.236-
239.
Snyder, W. V. (1983). Analysis of beam building using fully grouted roof bolts. Int.
Symp. on. Rock bolting, Sweden.246-255.

Spang, K. and P. Egger (1990). Mode of action and calculation of fully grouted rock
bolts as reinforcement in stratified or jointed rock mass. International Journal of
Rock Mechanics and Mining Science & Geomechanics Abstracts 7.(4): 181-189.
Spang, K. and P. Egger (1991). Action of fully-grouted bolts in jointed rock and
factors of influence : Spang, K; Egger, P Rock Mech Rock Engng V23, N3, July-

333
References

Sept 1990, P201-209. International Journal of Rock Mechanics and Mining Science
& Geomechanics Abstracts 28.(2-3): A173-A174.

Spang.K and Egger.P (1990). Action of fully grouted bolts in jointed rock and factors
of influence. Rock mechanic and rock engineering 23: 201-229.

Stankus.J.C and Guo.S (1996). Computer automated finite element analysis-A


powerful tool for fast mine design and ground control problem diagnosis and solving.
5th Conference on the use of computer in the coal industry, West Virginia-USA.108-
115.

Stankus.J.C and Guo.S (1997). New design criteria for roof bolt systems. Proceeding
of 16th Int. Conf. on Ground Control in Mining, WV.Morgantown.157-168.

Stillborg, B. (1986). Professional users handbook for rock bolting, Clausthal-


Zellerfeld, Germany : Trans Tech, 145 p.

Stillborg. B (1994). Professional users handbook for rock bolting. Series on rock and
soil mechanics. 2nd Ed. Atalas Copco. Sweden. 1-85pp.

Stille.H (1992). Rock support in theory and practice. Int. Symp. of Rock support in
Mining and Undeground Construction, Canada.421-437.

Stille.H, Holmberge.M and Nord.G (1989). Support of weak rock with grouted bolts
and shotcrete. Int.J.rock Mech. Min. Sci. and Geomech. Abstr. 26.(1): 99-113.

Stimpson, B. (1983). The influence of rock bolt location on the reinforcement of


horizontally bedded roofs by full column grouted bolts. Int. Conf. of Rock bolting,
Sweden.256-265.

Stjern, G. and A. Myrvang (1998). The influence of blasting on grouted rockbolts.


Tunnelling and underground space technology 13.(1): 65-70.
Surajit, P. and G. Wije Wathugala (1999). disturbed state model for sand-
geosynthetic interfaces and application to pull-out tests. Int. J. for Numerical and
analytical methods in geomechanics 23: 1873-1892.

334
References

Swoboda.G and Marence.M (1992). Numerical modelling of rock bolts in interaction


with fault system. Int.Sym. of Numerical modelling in Geomechanics.729-737.

Tadoloni.S.C and Ulrich.B.F (1986). Evaluation of beraing plates installed on full


column resin grouted bolts, Bureau of Mines: Denver. 17p.

Tarrant. G (2002). Assessment of support requirments associated longwall


reorientation, SCT, Report No:MET2431: 30 p.

Tassien.A, Zhang.Y, Han.J and Peng.S (2002). Comparison of some aspects of


bolting mechanism between fully-grouted resin and tensioned bolts in underground
mine entries. 21st Intrnational Conference on Ground Control in MIning,
Morgantown,W.V.114-125.

Thompson, A. and D. J. Finn (2001). The performance of grouted split tube rock bolt
systems. rock technology Library: 13 p.

Thompson.A.G (1992). Tensioning reinforcing cables. Proc. Int. Sym. of Rock


support in mining and underground construction, Ontario, Canada.285-291.

Ulrich.B.F, Wuest.W.J, J. and Stateham.R.M (1991). Relationships between annulus


thickness and the integrity of resin grouted roof bolts, US Bureau of Mines, RI 9253:
13p.

Unrug, K. and E. Thompson (2002). Field testing of the fully grouted thrust
tensioned bolts. 21th Int. Conf. on ground control in mining.141-144.

Wang.B and Garga.V.K (1992). A numerical model for rock bolts. Int. Symposioum
of rock support in mining and underground construction.Ontario,Canada. 57-65.
Whitaker.A (1998). Critical assessment of past research into rock bolt.
Mining.Thesis. Sydney, New South Wales: 2p.
http://www.mines.unsw.edu.au/Publications/abstracts/WhitakerA_1998.pdf.

Whitaker.B.N and Grant.A.S (1980). Time dependence,load relaxation and


performance aspects of polyester rsin grouted reinforcing bars in sedimentary rocks.

335
References

Int.Conf.on Structure.Founds.on Rocks,ISRM, Sydney.pp.77-85 (cited in Dight


1982).

Windsor, C. R. and A. Thompson (1996). Terminology in rock reinforcement practic.


NARMA96, Canada.8p.

Windsor. C.R (1996). Rock reinforcement system. EUROCK 96., Italy.30p.

Windsor.C.R and Thmpson.A.G (1993). Rock reinforcement-technology, testing,


design and evaluation. Comprehensive Rock Engineering Principals, Practice and
Projects(Ed.J.A.Hudson)-V.4, 451-484.

Winsdor CR (1997). Rock reinforcement systems. Int.J.rock Mech. Min. Sci. and
Geomech. Abstr. 34.(6): 919-951.

Winsdor. C.R (2004). Rock reinforcement practice.Report. Perth, Rock Technology.

Xinzheng.LU, Erxiang.S and Jiangjing.J (2004). Analysis on the safety margin and
damage model for the excavation support structure in a very deep pit. 4rd Int. Symp.
on Safety Science and Technology (ISSST), Shanghai,China.368-373.

Xiu.Z, Wang.X and Wang.A (1997). Strategies for the application of rockbolting
technology to longwall gateroads in Chinese coal mines. Proceedings of 16th
Conference on Ground Control in Mining, Morgantown,, WV.191-198.

Xueyi.S (1983). Grouted rock bolt used in underground engineering in soft


surrounding rock or in highly stresses regions. Int.Sym.on Rock bolting,
Sweden.266-272.

Yap, L. P. and A. A. Rodger (1984). A study of the behaviour of vertical rock


anchors using the finite element method. Rock mechanics and mining science 21.(2):
47-61.

Yassein.A, Wahab.K and Peng.S (2004). 3D FEM simulation for fully grouted bolts.
International conference on ground control in mining, West Virginia.273-277.

336
References

Yassein.A, Y. Zhang, Han.J and S. Peng (2002). Comparison of some aspects of


bolting mechanism betwenn fully-grouted resin and tensioned bolts in underground
mine entries. 21st International Conference on Ground Control in Mining,
Morgantown.W.V.114-125.

Yazici, S. and P. K. Kaiser (1992). Bond strength of grouted cable bolts.


International Journal of Rock Mechanics and Mining Science & Geomechanics
Abstracts 29.(3): 279-292.

Yoshinaka, R., S. Sakaguch, T. Shimizu, H. Arai and E. Kato (1987). Experimental


study on the rock bolt reinforcement in discontinuous rocks. Proc. of Int. Society for
rock Mechanics, Australia, NWU, Balkema and Canadian rock Mechanics
Association.1329-1332.

Zhang.Y and Peng.S (2002). Design considerations for tensioned bolts. Proc. of 21th
International Conference on ground control in Mining, West Virginia.131-140.

Zhen-Yu.T and Xian.C (1983). Behaviour of rock bolting as tunnelling support. Int.
Symp. on Rock bolting, Sweden.273-278.

337
CHAPTER ONE .....................................................................................................1
GENERAL INTRODUCTION ..............................................................................1

1.1. GENERAL.....................................................................................................1
1.2. BACKGROUND FOR PRESENT RESEARCH ...........................................4
1.3. KEY OBJECTIVE .........................................................................................5
1.4. RESEARCH METHODOLOGY....................................................................6
1.5. SCOP OF THE THESIS.................................................................................7

CHAPTER TWO ..................................................................................................11


ROCK BOLT SYSTEM AND REVIEW OF BOLT BEHAVIOUR UNDER
AXIAL LOADING ...............................................................................................11

2.1. INTRODUCTION........................................................................................11
2.2. HISTORICAL..............................................................................................11
2.2.1. History of bolting Australian mines .......................................................12
2.3. ROOF BOLT PRACTICE AND APPLICATION ........................................12
2.4. REINFORCEMENT MECHANISM............................................................13
2.5. BOLT THEORIES .......................................................................................14
2.6. TYPE OF ROCK BOLTS ............................................................................16
2.7. LOAD TRANSFER IN ROCK BOLTS .......................................................21
2.7.1. Load Transfer Concept in Fully Grouted Rock Bolts .............................22
2.8. SELECTION OF FULLY GROUTED BOLTS ............................................24
2.8.1. Fully Grouted Bolt Failure.....................................................................26
2.8.2. Load Transfer Measurement ..................................................................27
2.9. EFFECT OF BOLT IN CONTINUUM MEDIUM .......................................28
2.10. THE EFFECT OF BOLT ON DISCONTINUITY ......................................29
2.11. SUMMARY..............................................................................................31
2.12. REVIEW OF FAILURE MECHANISM OF BOLT RESIN INTERFACE
SUBJECTED TO THE AXIAL LOAD...............................................................32
2.12.1. Theoretical behaviour of the bolt under axial load................................32
2.12.2. Experimental behaviour of the bolt under axial load ............................40
2.12.3. Bolt grout-rock interface mechanism .................................................44

vii
2.12.4. Load transfer mechanism.....................................................................49
2.12.5. Conclusion ..........................................................................................53

CHAPTER THREE ..............................................................................................55


REVIEW OF SHEAR BEHAVIOUR OF BOLTS AND MECHANICAL
PROPERTIES OF THE MATERIAL USED......................................................55

3.1. INTRODUCTION........................................................................................55
3.2. DESCRIPTION OF PAST RESEARCHES..................................................57
3.3 PRETENSIONING EFFECT IN FULLY GROUTED BOLTS .....................80
3.4. SUMMARY.................................................................................................84
3.5. MECHANICAL PROPERTIES OF REINFORCING MATERIALS............86
3.5.1. Bolt Types.............................................................................................86
3.5.2. Bolt strength tests ..................................................................................88
3.5.3. Resin grout ............................................................................................93
3.5.4. Concrete ................................................................................................98
3.5.4.2. Concrete joint surface properties.......................................................100
3.5.5. Summary.............................................................................................102

CHAPTER FOUR...............................................................................................104
FAILURE MECHANISM OF BOLT RESIN INTERFACE S DUE TO AXIAL
LOAD ..................................................................................................................104

4.1. INTRODUCTION......................................................................................104
4.2. LOAD TRANSFER MECHANISM...........................................................104
4.3. BOND CHARACTERISTIC......................................................................106
4.4. PULL AND PUSH ENCAPSULATION TESTS........................................107
4.4.1.Push Encapsulation Test .......................................................................109
4.4.2. Pull Encapsulation Test .......................................................................111
4.5. DISCUSSION ............................................................................................112
4.5.1. Effect of bolt profile ............................................................................115
4.5.2. Bolt yielding/necking ..........................................................................118
4.5.3. Effective Shear Stress at the Bond Interface.........................................120

viii
4.5.4. Bolt core behaviour subjected to axial loading .....................................124
4.5.5. Effect of annulus .................................................................................124
4.6. SUMMARY...............................................................................................125

CHAPTER FIVE ................................................................................................127


DOUBLE SHEARING OF BOLTS ACROSS JOINTS ....................................127

5.1. INTRODUCTION......................................................................................127
5.2. EXPERIMENTAL PROCEDURE .............................................................128
5.2.1. Block Casting ......................................................................................128
5.2.2. Bolt Installation in Concrete Blocks.....................................................130
5.3. DOUBLE SHEAR BOX ...........................................................................131
5.4. TESTING...................................................................................................131
5.5. BOLT TYPES............................................................................................134
5.6. RESULTS AND DISCUSSION .................................................................136
5.6.1. Shear Load and Shear Displacement....................................................136
5.6.1.1. Profile description ............................................................................136
5.6.1.2. Shear loading for a limited displacement...........................................138
5.6.1.3. Shear loading of bolt to ultimate failure ............................................146
A) Testing of Bolt Types T5 and T6 in 40 MPa Concrete: .............................154
5.6.2. Influence of Shearing Load on Pretension Load...................................157
5.6.3. Load Transfer Level In Different Profile.............................................160
5.6.4. Double Shearing of Instrumented Bolt.................................................162
5.6.5. Medium (Concrete and resin) Reaction................................................167
5.6.6. Prediction Of The Bolt Contribution....................................................170
5.7. SUMMARY...............................................................................................176

CHAPTER 6 .......................................................................................................178
ROLE OF BOLT ANNULUS THICKNESS ON BOLT SHEARING .............178

6.1. INTRODUCTION.....................................................................................178
6.2. TEST METHOD ........................................................................................178
6.3. EXPERIMENTAL RESULTS AND DISCUSSION..................................179

ix
6.3.1. Shear load/ shear displacement ............................................................180
6.3.2. Axial load built up...............................................................................184
6.3.4. Effect of resin thickness on shear stiffness...........................................190
6.4. NUMERICAL SIMULATION IN DIFFERENT RESIN THICKNESS ......193
6.5. THE EFFECT OF RESIN ANNULUS ON INDUCED STRESSES ...........195
6.5.1. Induced Shear Stress............................................................................195
6.5.2. Induced Tensile Stress .........................................................................196
6.5.3 Induced Compression Stress .................................................................197
6.6. Effect Of Concrete Modulus Of Elasticity On Shear Displacement............197
6.7. Effect of grout modulus of elasticity on shear displacement.......................199
6.8. EFFECT OF BOLT MODULUS...............................................................200
6.9. SUMMARY...............................................................................................202

CHAPTER 7 .......................................................................................................204
NUMERICAL ANALYSES IN FULLY GROUTED ROCK BOLTS..............204

7.1. INTRODUCTION......................................................................................204
7. 2. FE IN ANSYS..........................................................................................205
7.3. A REVIEW OF NUMERICAL MODELING IN ROCK BOLT .................205
7.4. MATERIAL DESIGN MODEL .................................................................210
7.4.1 Modelling of Concrete and Grout .........................................................212
7.4.2 Modelling the Bolt................................................................................213
7.4.3. Contact Interface Model ......................................................................214
7.4.4. Geometrical Model..............................................................................215
7.5. VERIFICATION OF THE MODEL...........................................................216
7.6. MODELLING OF FULLY GROUTED ROCK BOLTS ............................217
7.7. RESULTS AND DISCUSSION .................................................................219
7.7.1. Bolt Behaviour ....................................................................................219
7.7.1.1. Stress developed along the bolt.........................................................219
7.8.1.2. Strain developed along the bolt.........................................................228
7.7.2. Concrete ..............................................................................................233
7.7.2.1. Stress developed in concrete .............................................................233
7.7.2.2. Strain developed in concrete .............................................................235

x
7.7.3. Grout...................................................................................................239
7.7.3.1. Stress developed in grout ..................................................................239
7.7.3.2. Strain Developed in Grout ...............................................................242
7.7.4. Contact Pressure..................................................................................243
7.8. SUMMARY...............................................................................................245
7.9. NUMERICAL MODELLING OF FAILURE MECHANISM OF BOLT
RESIN INTERFACE SUBJECTED TO AXIAL LOADING ............................247
7.9.1. Introduction.........................................................................................247
7.9.2. Results and Discussion ........................................................................248
7.9.2.1. Bolt Behaviour .................................................................................249
7.9.2.2. Grout Behaviour ...............................................................................253
7.9.3. Modulus of Elasticity Effect ................................................................256
7.10.4. Summary ...........................................................................................259

CHAPTER 8 .......................................................................................................260
ANALYTICAL ASPECT OF FULLY GROUTED BOLT...............................260

8.1. REACTION FORCES DURING THE SHEARING...................................260


8.2. STEEL BOLT BEHAVIOUR ....................................................................262
8.2.1. Plastic Design......................................................................................262
8.2.2. Plastic Theory......................................................................................262
8.2.3. Basic Equation For A Grouted Rock Bolt Subjected To Lateral
Deformation..................................................................................................264
8.3. BOLT - JOINT CONTRIBUTION.............................................................269
8.4. REACTION FORCES................................................................................271
8.4.1. Basic Equation for Rock and Subgrade Material..................................272
8.6. ANALYTICAL APPROACH TO DEFINE THE HINGE POINT
LOCATION REGARDING AXIAL LOAD ALONG THE BOLT....................273
8.6.1. Elastic behaviour .................................................................................273
8.6.2. Plastic Behaviour.................................................................................276
8.7. ANALYTICAL APPROACH TO DEFINE THE HINGE POINT
LOCATION REGARDING SHEAR DISPLACEMENT ..................................281

xi
8.8. ANALYTICAL METHOD TO DEFINE THE SHEAR DISPLACEMENT IN
CASE OF BOLT MODULUS OF ELASTICITY..............................................282
8.9. Analysis of a Fully Grouted Elastic Bolt in Plastic Rock Mass
.........................................................................................................................285
8.10. CONCLUSION........................................................................................297

CHAPTER 9 .......................................................................................................298
FIELD INVESTIGATIONS ...............................................................................298

9.1. INTRODUCTION......................................................................................298
9.2. SITE DESCRIPTION.................................................................................298
9.2.1. Metropolitan Colliery ..........................................................................298
9.2.2. Appin Colliery.....................................................................................302
9.3. INSTRUMENTATION..............................................................................302
9.3.1. Instrumented Bolts ..............................................................................302
9.3.2. Intrinsically Safe Strain Bridge Monitor ..............................................305
9.4. FIELD MONITORING AND DATA ANALYSING..................................307
9.4.1. Metropolitan Colliery ..........................................................................307

CHAPTER 10......................................................................................................313
CONCLUSIONS AND RECOMMENDATIONS .............................................313

10.1. SUMMARY.............................................................................................313
10.2. CONCLUSIONS......................................................................................313
10.2.1. Literature survey................................................................................314
10.2.2. Experimental investigations...............................................................314
10.2.3. Numerical analyses............................................................................317
10.2.4. Field investigations...........................................................................318
10.3. SUGGESTIONS FOR FURTHER RESEARCH ......................................318

xii
LIST OF FIGURES

Figure 1. 1. Structure of Chapters in the thesis ..........................................................8


Figure 2. 1. Usage of rock bolts in the world .13
Figure 2. 2. Continuous mechanically coupled rock bolt ........................................22
Figure 2.3. Load transfer in fully grouted rock bolts................................................23
Figure 2.4 Rate of load transfer along the fully grouted rock bolts........................24
Figure 2. 5 The mechanism of the load transfer.......................................................27
Figure 2.6. Load deformation results in different bolts (Stillborg 1994)...................28
Figure 2.7. Bolt installation to the joint a: perpendicular, b: incline (After Obert and
Duvall 1967) ...................................................................................................30
Figure 2. 8. Stress situation in a grouted anchor (after Farmer, 1975) ......................34
Figure 2. 9. Theoretical stress distribution along a resin anchor in a rigid hole with
thin resin annulus (after Farmer 1975).............................................................34
Figure 2. 10. Load displacement, strain distribution, and computed shear stress
distribution curves in concrete, a) strain distribution at the specified anchor load,
b) theoretical shear-stress distribution curves. (After Farmer 1975) .................35
Figure 2. 11. Stress distribution model for grouted bolt (after Yu and Xian, 1983) ..37
Figure 2. 12. Stress Component in a small section of a bolt (after Stillberg & Li,
1999)...............................................................................................................38
Figure 2. 13. Shear stress along a fully coupled rock bolt subjected to an axial load
before decoupling............................................................................................39
Figure 2. 14. Distribution of shear stress along a fully grouted rock bolt subjected to
an axial load in coupled rock bolt ....................................................................40
Figure 2. 15. Variables used in closed-form solution (after Serbousek and Singer
1987)...............................................................................................................42
Figure 2. 16. Schematic illustration of different conical lugged bolts: (a) Single, (b)
Double and (c) Triple c) Triple conical lugged bolt .............................................43
Figure 2. 17. Shear stress versus shear displacement in bolt /grout interface at
different bolt diameter (after Aydan 1989) ......................................................46
Figure 2. 18. Dilation behaviour of joint plane a) two smooth plane, b) bolt and resin
interface. .........................................................................................................47
Figure 2. 19. Pull test gear arrangement (after Singer 1990) ...................................48

xiii
Figure 2.20. Comparison of load distribution along the bolt length..........................49
Figure 2. 21. Schematic diagram reflecting the geometry of a rough bolt (after Yazici
and Kaiser, 1992) ............................................................................................50
Figure 2. 22. Load/displacement curves for rebar with various amounts of bar
deformation removed (after Fabjanczyk and et al, 1992) .................................51

Figure 3.1. Stability issues in rock mass reinforced by fully grouted bolts...............56
Figure 3. 2. The shear test arrangement in (a) and (b) probable load generation (after
Dulasck 1972) .................................................................................................58
Figure 3. 3. Components of shear resistance of bolt (after Bjurstrom, 1974)............59
Figure 3. 4. (a) block splitting in one side of shear joint (b) non equilibrium situation
in vicinity of shear joint...................................................................................61
Figure 3. 5. (a) Finite element mesh and (b) deviatoric of stress distribution across
the joint (Afridi and et al. 2001) ......................................................................61
Figure 3. 6. Arrangement for bolt shear testing (after Hass, 1981)...........................63
Figure 3. 7. General deformation patterns for a dowel in shear................................64
Figure 3. 8. Shear test machine used by Schubert (1984).........................................67
Figure 3. 9. Relation between shear stress and shear displacement (After Yoshinaka
1987)...............................................................................................................67
Figure 3. 10. Direct shear test device (after Egger and Zabuski 1991) .....................69
Figure 3. 11. Bolt grout behaviour sketch (after Holmberge 1991) ..........................70
Figure 3. 12. A grouted rock bolt subjected to lateral force .....................................72
Figure 3. 13. Ferreros shear test machine ...............................................................73
Figure 3. 14. Resistance mechanism of a reinforced rock joint (after Ferrero 1995).73
Figure 3. 15. Forces acting on the failure mechanism 1 (after Ferrero 1995)............75
Figure 3. 16. Force components and deformation of a bolt, a) in elastic zone, and b)
in plastic zone (after Pellet and Eager 1995)....................................................76
Figure 3. 17. Evolution of shear and axial forces in a bolt, a) in elastic zone, and b) in
plastic zone (after Pellet and Egger, 1995).......................................................77
Figure 3. 18. Joint displacement as a function of angle for different UCS value
(after Pellet 1994) ...........................................................................................79
Figure 3. 19. Shear block test assembly (After Goris and et al 1996).......................80
Figure 3. 20. Different Bolt Types used for axial and shear behaviour tests.............87

xiv
Figure 3. 21. Profiles specification ..........................................................................87
Figure 3. 22. Bolt clamped in Instron Universal testing Machine.............................89
Figure 3. 23. Stretching of the bolts after tensile test ...............................................90
Figure 3. 24. Load- deflection curve at tensile test in various bolts 91
Figure 3.25. Load- deflection curve at tensile test of Bolt Type T5 and T6...91
Figure 3.26. Load- deflection curve at tensile test in cable bolt 91
Figure 3.27. Load- deflection curve at tensile test of Bolt Type T4.. 91
Figure 3.28.Three point load bending test set up .. 92
Figure 3.29. Load- displacement behaviour of 3PLBT..92
Figure 3. 30. direct shear test trend in Bolt Types T1 and T3...93
Figure 3.31. Typical fracture plane and fracture angle for compression test samples95
Figure 3.32. Compression test set up..95
Figure 3.33. Stress strain curve for resin 96
Figure 3.34 . Load versus displacement.97
Figure 3.35. Double shear test set up a: shear box set up b: induced loads 98
Figure 3.36. Concrete sample: a) concrete under the test b) concrete after 30 days..99
Figure 3.37. Variation of peak shear stress versus different normal stress in shear
joint plane in a: 20 MPa and b: 40 MPa concrete....101
Figure 3.38. Shear load versus shear displacement in joint plane in 40 MPa concrete

Figure 4. 1. Sketch of real bolt profile specifications and interfaces106


Figure 4. 2. (a) resin/bolt load transfer under various confining pressures (b) resin
bolt separation after post encapsulation .........................................................107
Figure 4. 3. (a) The actual push test configuration (b) the shematic of the test .......110
Figure 4. 4. Preparing the bolt resin samples .........................................................110
Figure 4. 5. Post-test sheared Bolt Type T2 out of steel cylinder in push test.........111
Figure 4. 6. Pull test arrangement..........................................................................112
Figure 4. 7. Post-test sheared bolt out of steel cylinder ..........................................112
Figure 4. 8. Shear load as a function of displacement in pull test...........................114
Figure 4. 9. shear load as a function of displacement in push test ........................115
Figure 4. 10. General trend of push and pull test view...........................................115
Figure 4.11. The effect of Rib spacing on shear load .............................................117
Figure 4. 12. The shear load versus shear displacement in smooth bolt..................118

xv
Figure 4. 13. Debonding at pull test ......................................................................120
Figure 4.14. Shear stress versus bond displacement in Push test............................121
Figure 4.15. Shear stress versus bond displacement in pull test .............................122
Figure 4.16. Annulus thickness effect ...................................................................125

Figure 5. 1. Bolt bending behaviour (after Indraratna et al. 2000)..........................127


Figure 5. 2. Laboratory and numerical model ........................................................129
Figure 5.3. Hole reaming for hole rifling...............................................................129
Figure 5.4. An assembled bolt fitted with load cells on both ends of the bolt .........131
Figure 5.5. Schematic of post failed assembled shear box (a), and a set up of the high
strength capacity machine -Avery machine (b) ..............................................133
Figure 5.6. The set up of the Instron machine with load cell connection ................133
Figure 5.7. Different bolt types .............................................................................134
Figure 5.8. Typical shear displacement profile of the sheared bolt.........................137
Figure 5.9 (a-f). All bolt shear load and vertical displacement profiles in both 20 and
40 MPa concrete medium..............................................................................141
Figure 5.10 (a-f). Comparative results of all bolts shear load and vertical
displacement profiles in both 20 and 40 MPa concrete medium.....................142
Figure 5.11. Shear yield load difference in different concrete strength and bolt types
and various pretension loads..........................................................................143
Figure 5.12. Bolt slippage along the bolt -grout interface in case of non-pretensioning
and non- plate ...............................................................................................145
Figure 5.13. Axial fracture along the concrete and broking off of the grout in tensile
zone in bolt type T1 in 40 MPa concrete with 80 kN pretensioning ...............146
Figure 5.14. Shear load versus shear displacement in 0, 5 and 10 kN pretension load
in Bolt Types T5 and T6 in 40 MPa concrete.................................................151
Figure 5.15. The bolt failure view in different pretensioning .................................151
Figure 5.16. (a) Relationship between failure load and maximum tensile strength of
the single shear on bolt type T5, (b) bolt failure angle ...................................152
Figure 5.17. Shear load versus shear displacement in 100 MPa concrete and different
pretensioning in Bolt Type T1.......................................................................152
Figure 5.18. Excessive bolt necking in concrete 100 MPa in 80 kN pretension .....153

xvi
Figure 5.19. Bolt/ joint concrete interaction at shear joint in concrete 100 MPa and
80 kN pretension load ...................................................................................153
Figure 5.20. Bolt imprint on resin in concrete 100 MPa at 50 and 80 kN pretension
loads .............................................................................................................154
Figure 5.21. The ratio of axial load developed along the bolt over ultimate tensile
strength of the bolt versus shear displacement in concrete 100 MPa with 80 kN
pretension load..............................................................................................156
Figure 5.22. Shear load versus load cell readings on tensile load applied on a bolt
installed in a 20 MPa concrete.......................................................................157
Figure 5.23 (a-f). Shear load and pretension loads (load cell readings) for various
bolts with initial pretension load of 20, 50 and 80 kN ....................................158
Figure 5.24. End crushing of the concrete in high pretensioning load ....................160
Figure 5.25. Axial load developed along the bolt versus shear displacement in Bolt
Type T2 in 40 MPa concrete .........................................................................160
Figure 5.26. Effect of pretension load, bolt profile and concrete strength on the bolt
resistance ......................................................................................................161
Figure 5.27. Schematic diagram of the strain gauges locations in the reinforcing
element (a) without pretension load and (b) 20 kN pretension load................163
Figure 5.28. The shear load versus strain measurements in non-pretension load ....165
Figure 5.29. The bolt surface with strain gauges installed......................................166
Figure 5.30. The strain rate along the bolt, drawn by strain measurements in non-
pretension load..............................................................................................166
Figure 5.31. Shear load versus strain gauge measurements along the bolt in 20 kN
pretensions. ...................................................................................................166
Figure 5.32. The variation of the strain gauge measurements along the bolt at 20 kN
pretension load..............................................................................................167
Figure 5.33. Axial fracture developed along the bolt through the 20 MPa concrete169
Figure 5.34. The created gap in plastic stage .........................................................170
Figure 5.35. Effect of concrete strength on the factor of movement.......................174
Figure 5.36. Expected cumulative results versus observed cumulative results .......175

Figure 6. 1. Shear load as function of shear displacement in different annulus.......180


Figure 6. 2. Effect of resin thickness on shear displacement ..................................181

xvii
Figure 6.3. The effect of resin thickness on load - displacement yield point ..........181
Figure 6.4. Shear load and shear displacement in concrete 20 and 100 MPa and 20
kN pretension load and different resin thickness in Bolt Type T1 ..................183
Figure 6.5. Gap creation between bolt grout at high resin thickness in concrete 20
MPa with 20 kN preload (5 mm thick) ..........................................................183
Figure 6.6. Gap creation between bolt grout at high resin thickness in concrete 40
MPa with 20 kN preload (5 mm thick) ..........................................................184
Figure 6.7. Shear load and axial load build up along the bolt in concrete 20 MPa and
20 kN pretension load and thin resin thickness in bolt Type T1 (25mm)........184
Figure 6.8. Shear load versus axial load developed along the bolt in different resin
thickness in 20 MPa concrete ........................................................................185
Figure 6.9. Axial load versus- shear displacement in bolt T1 and 20 kN preload in 27
mm hole diameter surrounded by 20 MPa concrete .......................................186
Figure 6.10. Axial stress versus shear displacement in bolt Type T1 in 20 kN preload
in 36 mm hole diameter surrounded by 20 MPa concrete...............................187
Figure 6.11. Comparison of the axial load induced in bolt in different resin thickness
in 20 MPa strength (axial resistance factor is equal axial load over ultimate
tensile strength of the bolt) ............................................................................188
Figure 6.12. Side profile of failed bolt Type T1 surrounded by concrete 20 MPa and
36 mm hole diameter at 20 kN pretension load b) typical end profile of a failed
reinforcing element .......................................................................................189
Figure 6.13. The effect of hole diameter versus stiffness .......................................191
Figure 6.14. Effect of hole diameter and resin thickness on shear displacement in
numerical design ...........................................................................................194
Figure 6.15. Effect of resin thickness and concrete strength on shear displacement in
numerical design in un-pretension load .........................................................194
Figure 6.16. Induced shear stress versus concrete modulus of elasticity in different
annulus size (grout modulus is considered 12 GPa) .......................................196
Figure 6. 17. Induced tensile stress versus grout modulus of elasticity in soft concrete
(20 GPa) .......................................................................................................197
Figure 6.18. Induced compression stress versus concrete modulus of elasticity .....198
Figure 6.19. Shear displacement versus concrete modulus of elasticity in different
resin thickness, grout modulus is 12 GPa.......................................................199

xviii
Figure 6.20. Shear displacement versus grout modulus of elasticity in different resin
thickness, concrete modulus is 20 GPa and constant......................................200
Figure 6.21. Shear displacement as a function of bolt modulus variations in different
rock strength .................................................................................................201

Figure 7. 1. FE Simulation of bolted rock mass (After Hollingshead, 1971) ..........207


Figure 7. 2. Three-Dimensional rock bolt element (After John and Dillen, 1983) ..207
Figure 7. 3. Bolt-Rock interaction model (Peng and Guo, 1988) ...........................208
Figure 7.4. The process of FE simulation (Dof = degrees of freedom)...................211
Figure 7.5. (a) 3D concrete Solid 65 (b) Concrete mesh .................212
Figure 7.6. Finite element mesh for grout..............................................................213
Figure 7.7. Finite element mesh for bolt................................................................214
Figure 7.8. Geometry of the model and mesh generation ......................................216
Figure 7.9. Load-deflection in 80 kN pretension bolt load and 40 MPa concrete ...217
Figure 7.10. Numerical model (s = symmetric planes, c = compression zone, T =
tension zone ..................................................................................................220
Figure 7. 11. Bolt displacement in 20 MPa, without Pretensioning........................220
Figure 7.12. Shear displacement as a function of bolt length sections in 20 MPa
concrete ........................................................................................................221
Figure 7.13. Bolt deflection at the moving side and hinge point versus loading
process, in 40 MPa concrete without pretension load.....................................222
Figure 7.14. Stress built up along the bolt axis in 20 MPa concrete without
pretensioning.................................................................................................223
Figure 7.15. The trend of stress built up along the bolt axis 20 MPa concrete with 80
kN pretensioning...........................................................................................223
Figure 7.16. Von Mises stress trend in 20 MPa concrete without pretensioning.....224
Figure 7.17. Shear stress contour in the concrete 20 MPa without pretensioning ...225
Figure 7.18. The rate of shear stress along the bolt axis in concrete 20 MPa without
pretensioning.................................................................................................226
Figure 7.19. The rate of shear stress along the bolt axis in concrete 20 MPa without
pretensioning in one side of the joint plane....................................................226
Figure 7. 20. Shear stress trend in bolt joint intersection in concrete 20 MPa at post
failure region without pretension load ...........................................................227

xix
Figure 7. 21. Deformed bolt shape in post failure region in 20 MPa concrete ........228
Figure 7.22. The plastic strain contour along the bolt axis in concrete 20 MPa
without pretensioning....................................................................................229
Figure 7.23. Strain trend along the bolt axis in concrete 20 MPa without
pretensioning in upper fibre of the bolt..........................................................229
Figure 7. 24. The yield strain trend as a function of time stepping concrete 20 MPa in
20 kN pretension ...........................................................................................230
Figure 7. 25. Tension and pressure strain along the bolt in 20 MPa concrete and 20
kN pretension................................................................................................231
Figure 7.26. The Von Mises strain trend along the bolt axis in concrete 40 MPa and
80 kN pretensioning ......................................................................................231
Figure 7.27. Von Mises strain along the bolt in concrete 20 MPa concrete without
pretensioning.................................................................................................232
Figure 7.28. Von Mises strain trend in concrete 20 MPa without pretensioning in
upper fibre of the bolt....................................................................................232
Figure 7.29. The concrete displacement in non-pretension condition in 20 MPa
concrete ........................................................................................................233
Figure 7.30. Yield stress induced in 20 MPa concrete without pretensioning
condition.......................................................................................................234
Figure 7.31. Induced stress and displacement trend in 20 MPa concrete without
pretensioning.................................................................................................235
Figure 7.32. The produced strain contours in 20 MPa concrete without pretensioning
(in shearing direction) ...................................................................................236
Figure 7.33. Induced strain in concrete 20 MPa in grout and concrete versus loading
in non-pretension load and 27 mm hole diameter...........................................237
Figure 7.34. Concrete displacement versus loading time in concrete (a) 20 and (b) 40
MPa in non-pretension condition...................................................................237
Figure 7.35. Induced strain rate along the contact interface in 40 MPa concrete and
non pretension condition ...............................................................................238
Figure 7.36. Induced strain in concrete and bolt as a function of loading steps in 20
MPa concrete with 80 kN pretensioning ........................................................238
Figure 7.37. Induced stress contours in grout layer in un-pretension condition and 20
MPa ..............................................................................................................240

xx
Figure 7.38. Created gaps in post failure region in 20 MPa concrete in the Numerical
simulation .....................................................................................................240
Figure 7.39. Created gaps in post failure region in 20 MPa concrete in the laboratory
test ................................................................................................................241
Figure 7.40. The grout displacement in different location along the bolt axis in 40
MPa concrete ................................................................................................241
Figure 7.41. The rate of induced strain along the grout layer in non-pretension
condition in axial direction ............................................................................242
Figure 7.42. The grout displacement as a function of plastic strain generated in bolt-
joint intersection through the grout in non-pretension condition ....................243
Figure 7.43. The rate of contact pressure changes between (a) grout concrete
interface (b) bolt-grout interface in 20 MPa concrete in non-pretension
condition.......................................................................................................244
Figure 7.44. Contact pressure at the (a) bolt - grout interface (b) concrete - grout
interface in 20MPa concrete in high resin thickness (36mm hole diameter) in
80kN pretension load ....................................................................................245
Figure 7.45. Shear load versus bolt-grout contact pressure at 36 mm hole and 20 MPa
and 80kN preload..........................................................................................245
Figure 7. 46. Finite element mesh: a quarter of the model .....................................248
Figure 7.47. The bolt movement in pulling test .....................................................249
Figure 7. 48. Rate of the bolt displacement ...........................................................250
Figure 7. 49. Bolt displacement contour in Bolt Type T1 in case of push test ........250
Figure 7.50. Induced strain along the bolt profiles.................................................251
Figure 7.51. Shear strain in bolt ribs in push test ...................................................251
Figure 7.52. Von Mises Stress and shear stress along the bolt axis ........................253
Figure 7.53. Shear stress contours along the grout interface ..................................256
Figure 7.54. The effect of grout modulus of elasticity on shear displacement in push
test ................................................................................................................257
Figure 7.55. The effect of grout modulus of elasticity on shear displacement in pull
test ................................................................................................................257
Figure 7.56. The shear displacement as a function of grout modulus of elasticity in
case of push and pull test...............................................................................258

xxi
Figure 8. 1. Assembled model (concrete, grout and steel bolt)...............................261
Figure 8. 2. Load generation along the bolt during the shearing.............................261
Figure 8. 3. Stress strain relationship for bolt type T1 ...........................................263
Figure 8. 4. Elastic plastic stress sequence in bending ........................................263
Figure 8. 5. Deformed shape, shear force, bending moment and shear displacement
diagrams .......................................................................................................266
Figure 8. 6. Applied loads on joint intersection .....................................................269
Figure 8. 7. Reaction forces in bolt loaded laterally...............................................273
Figure 8. 8. Hinge point distance versus axial force...............................................276
Figure 8. 9. Bolt diameter versus hinge point distance in different rock strength ...276
Figure 8. 10. The relationship between axial load and hinge point distance in
different rock strength in plastic situation......................................................278
Figure 8. 11. The relationship between the axial load and hinge point distance in both
elastic and plastic situation ............................................................................279
Figure 8. 12. Hinge point position in different concrete strength ...........................279
Figure 8. 13. Relationship between hinge point position and axial deformation.....280
Figure 8. 14. Hinge point location as a function of shear displacement in elastic
region............................................................................................................282
Figure 8. 15. Comparison of the numerical and analytical results, concrete 20 MPa,
.....................................................................................................................284
Figure 8. 16. Notation for numerical formulation .................................................288
Figure 8. 17. Axial load along the bolt versus bolt length, in case of unplated with 25
MPa initial stress and 15 GPa modulus of surrounding rock ..........................290
Figure 8. 18. Normalised displacement versus bolt length in case of unplated with 25
MPa initial stress and 15 GPa modulus of surrounding rock ..........................291
Figure 8. 19. Normalised displacement versus bolt length in case of unplated with 25
MPa initial stress and 15 GPa modulus of surrounding rock at different k values
.....................................................................................................................291
Figure 8. 20. Normalised displacement versus bolt length in case of unplated with 15
MPa initial stress and 15 GPa modulus of surrounding rock at different k values
.....................................................................................................................291

xxii
Figure 8. 21. Load developed along the bolt versus bolt length in case of unplated
with 15 MPa initial stress and 25 GPa modulus of surrounding rock at different
k values.........................................................................................................292
Figure 8. 22. Load developed along the bolt versus bolt length in case of unplated
with 15 GPa modulus of surrounding rock at different initial stresses............292
Figure 8. 23. Load developed along the bolt versus bolt length in case of unplated
with 25 MPa initial stress and different modulus of surrounding rock at k=10
.....................................................................................................................293
Figure 8. 24. Load developed along the bolt versus bolt length in case of unplated
with 25 MPa initial stress and different modulus of surrounding rock at k=10,
L=10 m .........................................................................................................293
Figure 8. 25. Load developed along the bolt versus bolt length in case of using end
plate with 25 MPa initial stress and different k, at Er = 5GPa .........................294
Figure 8. 26. Normalised displacement versus bolt length in case of using end plate
with 25 MPa initial stress and different k, at Er = 5GPa..................................294
Figure 8. 27. Axial load versus bolt length in case of using end plate with 25 MPa
initial stress and different rock modulus and bolt length, k=10 ......................295
Figure 8. 28. Normalized displacement versus bolt length in case of using end plate
with 25 MPa initial stress and different rock modulus and bolt length, k=10..295
Figure 8. 29. Axial load versus bolt length in case of using end plate in different
initial stress with 5 GPa rock modulus, k=10.................................................296
Figure 8. 30. Axial load versus bolt length in case of using end plate in different
plastic zone radius with 5 GPa rock modulus, k=10.......................................296

Figure 9. 1. Geographical location of (a) Metropolitan and (b) Appin Colliery ......299
Figure 9. 2. Modelled geological section and strength profiles (SCT report 2002) .300
Figure 9.3. The detailed layout of the panel under investigation indicating
instrumentation site at Metropolitan Colliery.................................................301
Figure 9.4. Photograph of the site with installed bolts ...........................................301
Figure 9. 5. Detail site plane of the instrumented bolts at Metropolitan Colliery....302
Figure 9. 6. Strain gauge and bolt layout ...............................................................304
Figure 9. 7. Bolt segment showing channels..........................................................304

xxiii
Figure 9. 8. A section of an instrumented bolt showing the strain gauge and wirings
through the silicon gel. ..................................................................................305
Figure 9. 9. A general view of the SBM, while taking readings in underground ....306
Figure 9. 10. Load transferred on the bolt Type T1 installed at the right side of the
TR, Metropolitan Colliery. ............................................................................308
Figure 9.11. Load transferred on the bolt Type T3 installed at the right side of the
TR, Metropolitan Colliery. ............................................................................309
Figure 9. 12. Shear stress developed at the bolt/resin interface of the Bolt Type T1, in
Metropolitan Colliery....................................................................................311
Figure 9. 13. Shear stress developed at the bolt/resin interface of the Bolt Type T3, in
Metropolitan Colliery....................................................................................312

xxiv

You might also like