You are on page 1of 18

Computers and Structures 82 (2004) 329346

www.elsevier.com/locate/compstruc

Analysis of cable-stayed bridges during construction


by cantilever methods
Pao-Hsii Wang *, Tzu-Yang Tang, Hou-Nong Zheng
Structural Mechanics Division, Department of Civil Engineering, Chung-Yuan University, Chung-Li, Taiwan, ROC
Received 24 December 2002; accepted 15 November 2003

Abstract
The aim of this study concerns with the analysis of cable-stayed bridges at dierent erection stages during con-
struction using the cantilever method. A nite element computation procedure is set up for the shape nding analysis of
such structures during erection procedures. Two computational processes are established, one is a forward process
analysis and the other is a backward process analysis. The former is performed by following the sequence of erection
stages in bridge construction and the latter is carried out in the reverse direction of erection procedures. Both processes
can be successfully applied for nding the initial shape of bridge structures during erection procedures. The structural
behavior of the bridge structure at dierent erection stages has been examined in details, such as the pretension required
in cable-stays and the corresponding structural congurations of the bridge, etc. The results of shape nding analysis at
each erection stage not only provide the necessary data for the purpose of structural analysis and design, but also can be
used for checking and controlling the erection procedure of the cable-stayed bridge during construction. The designed
shape (pretension in cables and conguration) of the bridge can then be achieved and constructed.
 2003 Elsevier Ltd. All rights reserved.

Keywords: Cable-stayed bridge; Initial shape; Forward process analysis; Backward process analysis

1. Introduction size and complicated nonlinear structural behaviors, the


analysis of cable-stayed bridges is much more compli-
Over the last half century a large number of cable- cated than that of conventional bridges, such as truss
stayed bridges has been built or are under construction and girder bridges. The sources of nonlinearity in cable-
all over the world. The rapid progress of this kind of stayed bridges mainly include the cable sag, beam-col-
bridges is mainly due to the development of computer umn and large deection eects. A lot of studies on this
technology, high strength steel cables, orthotropic steel kind of bridges have been done in the last half century
decks and construction technology [1,2,5,6]. Because of [46,9,10]. But few papers presented concerns with the
its aesthetic appeal, economic grounds and the ease of analysis of cable-stayed bridges during erection stages in
erection, the cable-stayed bridge is considered as most construction. Some papers concerning with the erection
suitable for medium to long span bridges with spans procedure of cable-stayed bridges focus only on
ranging from 200 to about 1000 m [2,5]. As a matter of improving the construction technology and technicality
fact, the longer span length is, the more exible the [6,7,11], but not the analysis. The purpose of this paper
bridge structural system behaves. Because of their huge is to present a nite element computation procedure for
the shape nding analysis of bridge structures during
construction based on the cantilever method, in which a
*
Corresponding author. Tel.: +886-3-265-4207; fax: +886-3- forward process analysis and a backward analysis by
265-4299. using both the linear computation procedure and the
E-mail address: phwang@cycu.edu.tw (P.-H. Wang). nonlinear computation procedures are set up.

0045-7949/$ - see front matter  2003 Elsevier Ltd. All rights reserved.
doi:10.1016/j.compstruc.2003.11.003
330 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

2. Finite element formulation y


u1 x
2.1. Finite element model Sag

Based on the nite element concept, a cable-stayed


bridge can be considered as an assembly of a nite q R2
number of cable and beam-column (for girder and
tower) elements. In this study some assumptions are qL2
qR 1
made as follows. The material is homogeneous and qL 1 Sag
R

isotropic and behaves linearly elastically. The external L


loads are displacement independent. All cables are xed
to the tower and to the girder at their joints of attach-
ment. Large displacements and large rotations are al- uj : Element Coordinates
lowed, but strain is small. The following geometric Y q : System Coordinates
x, y : Local Coordinate System
nonlinearities are taken into consideration in the anal- X, Y : Global Coordinate System
X
ysis of cable-stayed bridges. 0

Fig. 1. Plane cable element with sag.


2.1.1. Cable sag eect
The elastic cable is assumed to be perfectly exible
(h i
and possesses only tension stiness; it is incapable of Eeq A
for u1 > 0
KEjk KE11 l
resisting compression, shear and bending forces.
When the weight of the cable is neglected, the cable 0 for u1 < 0
element can be considered as a straight member. But
under the action of its own dead load and axial ten- where l is the chord length of cable element. The cable
sile force, a cable supported at its end will sag into a stiness vanishes and no element force exists for u1 < 0,
catenary shape. The axial stiness of a cable will change i.e., when shortening occurs. If the cable sag eect is
with changing sag. When a straight cable element for neglected, the stiness matrix for a linear cable element
a whole inclined cable stay is used in the analysis, the becomes KEjk KE EA=l, where Eeq is replaced
sag eect has to be taken into account. On the consid- by E.
eration of the sag nonlinearity in the inclined cable
stays, it is convenient to use an equivalent straight 2.1.2. Beam-column eect
cable element with an equivalent modulus of elastic- Since a high pretension force exists in inclined cable
ity, which can well describe the catenary action of the stays, the towers and part of the girders are subjected to
cable. a large compression action; this means that the beam-
The concept of the cable equivalent modulus of column eect has to be taken into consideration for
elasticity Eeq was rst introduced by Ernst in 1965 [3]. If girders and towers of the cable-stayed bridge. For the
the change in tension in a cable during a load increment beam-column element, the engineering beam theory is
is not large, the axial stiness of the cable will not employed and no shear strain is considered. In a beam-
change signicantly and the equivalent modulus of column, lateral deection and axial force are interrelated
elasticity of the cable can be considered constant during such that its bending stiness is dependent on the ele-
the load increment, and is given by ment axial forces, and the presence of bending moments
E will aect the axial stiness. The element bending sti-
Eeq 2 ness decreases for a compression axial force and in-
1 wL AE
12T 3 creases for a tension force.
The plane beam-column element shown in Fig. 2 is
in which Eeq is the equivalent cable modulus of elastic- employed in this study. The beam-column element is
ity, E the eective cable material modulus of elasticity, straight member with constant cross-section. It has three
A the cross-sectional area, w the cable weight per unit element coordinates, two for end rotations, u1 , u2 and
length, L the horizontal projected length of the cable one for the relative axial deformation u3 Dl, where Dl
and T is the tensile force in the cable. is the element axial elongation or shortening. The ele-
When the inclined cable stay is represented by a ment force corresponding to uj is denoted by Sj , in which
single equivalent straight cable element with one coor- S1 and S2 are the end moments and S3 is the axial force.
dinate (relative axial deformation) u1 Dl, as shown in When the beam-column eect has to be taken into
Fig. 1, the stiness matrix KEjk of the cable element has consideration, the beam-column element stiness matrix
the value as follows: has the following form [4,5]:
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 331

x oaja o2 uj
u3 aja;b qc
oqb oqa oqb
y O.F.
3 D. coordinate transformation coefficients of
P3
u2
BM
second-order
u1 q R2
The nonlinear transformation coecients of the rst-
q L2 R q R1 order and the second-order, aja and aja;b , for the straight
Y q R3 cable element and the beam-column element can be
L X
found in Refs. [12,13]. With the help of the nonlinear
q L1
qL 3 transformation coecients aja and aja;b , the tangent
system stiness matrix can be built up with standard
u : Element Coordinates
nite element procedure by assembling the element
j
Y q : System Coordinates stiness matrices [8,1214].
x , y : Local Coordinates System
X
X, Y : Global Coordinates System
0 2.2. Linearized system equation
Fig. 2. 3 D.O.F. plane beam-column element.
In nonlinear statics the linearized nite element sys-
tem equation can be derived by the virtual work prin-
2 3 ciple as follows [8]:
C Ct 0
EI 4 S
KEjk KE33 Ct CS 0 5 DPan u Pan 2 Kab
n
 Dqnb ; a 1; 2; . . . . . . ; N
l
0 0 Rt A=I
for Pan 6 Pa 6 Pan1
where E is the modulus of elasticity, A the cross-sectional P P
area, I the moment of inertia of the cross-sectional area where 2 Kab n
EL KEjk aja akb EL Sjn anja;b n Kj  n bja;b
n n n
j j
and l the element length. The stability functions CS , Ct n Kb  n ba P is the tangent system stiness matrix,
n n n n
and Rt can be expressed in terms of the element axial u Pa Pa EL Sj aja the unbalanced forces at nth load

force S3 and the end moments S1 and S2 and can be step in statics, DPan Pan1 Pan the load increments,
found in Refs. [4,12]. Dqna qn1
a qna the displacement
P increments, KEjk the
If the beam-column eect is not considered, the ele- element stiness matrix, EL the summation over all

ment stiness matrix KEjk of a beam column element elements, and N is the number of degree of freedom
becomes the usual linear form as (D.O.F.). The superscript j denotes the nodal number.
2 3 The subscripts a; b; c; . . . denote the number of the sys-
4 2 0 tem coordinate and j; k; l; . . . are the number of the
EI 4
KEjk KE33 2 4 0 5 element coordinate. The index summation convention is
l
0 0 A=I used here for the superscripts and subscripts. Letters
printed in bold-face type, e.g. Kj , bja , represent vectors,
where Kj the external nodal load vectors, Wj the dis-
2.1.3. Large displacement eect placement vectors corresponding to Kj and bja oWj =
In general, cable-stayed bridges have a larger span oqa is the basis vector. The dot notation between vectors
and less weight than that of conventional steel and means scalar product. The superscript n denotes the
reinforced concrete bridges. Large deections may easily number of load step, e.g., qnb qb jPa Pan , and the number
appear in cable-stayed bridges. Hence, the large dis- 2 means iteration matrix of second-order.
placement eect has to be considered in the analysis The linearized system equation represents a set of
and the equilibrium equations have to be set up based on linear algebraic equations in small load interval. This
the deformed position [1214]. In general, the relation- linearized system equation can be solved with the
ship between element coordinates uj and the system NewtonRaphson method in which the equilibrium
coordinates qa can be expressed by uj uj qa where uj iteration is performed as follows:
may be nonlinear functions of qa when large deections
occur. By taking the dierentiation we have duj aja dqa The equilibrium position is found for load step n.
with Set up and solve the linearized system equation for
ouj load step n 1
aja qb
oqa DPan u Pan 2 Kab
n
 Dqnb
coordinate transformation coefficients
of first-order and Dqnb is found.
332 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

Set i 0, i Dqnb Dqnb , i n


qb qnb , and i1 n
qb conditions, the specied boundary conditions, and the
i n
qb i Dqnb . requirements of the architectural design should be sat-
ki Dqnb k ised. For shape nding computation, the dead load of
If ki qnb k
6 e (e is the convergence tolerance),then girders and towers is taken into account and the dead
i1
qn1
b qnb , and begin next load step, else i load of cables is neglected, but cable sag nonlinearity
i 1, and solve i n
u Pa
i2 n
Kab  i Dqnb , with i1 qnb induced by cable dead load is included. The computa-
i n
qb i Dqnb and repeat convergence tolerance check. tion for shape nding is performed by using the two-
loop iteration method, i.e., equilibrium iteration loop
2.3. Linear system equation and shape iteration loop, and can be started with an
estimated tension force in inclined cables [1214]. Based
In linear statics, the system equation has a linear on a reference conguration (the architectural designed
form as follows: form) with no deection and zero prestress in girders

and towers, the equilibrium position of the cable-stayed
Pa Ta Kab  qb ; a 1; 2; . . . ; N bridges under the action of dead load is rst determined,
where the equilibrium iteration will be carried out if the
where Ta the generalized initial internal forces, Kab
P nonlinear computation procedure is used. Although this
EL KEjk aja akb the linear system stiness matrix. All the rst determined conguration satises the equilibrium
element stiness matrices KEjk and the transformation conditions and the boundary conditions, the require-
coecients aja are constant in linear statics. The element ments of architectural design are, in general, not ful-
displacements are calculated with uj aja qa . lled. Since the bridge span is large and no pretension
forces exist in inclined cables, quite large deections and
huge bending moments may appear in the girders and
3. Shape nding analysis of cable-stayed bridges towers. Another iteration has to be carried out in order
to reduce the deections and to smooth the bending
The major work of the structural analysis of the moments in the girder, and nally to nd the correct
whole cable-stayed bridge consists of the initial shape initial shape. Such an iteration procedure is named the
analysis, static deection analysis and dynamic response shape iteration. For shape iteration, the element axial
analysis, etc. Based on the determined correct initial forces determined in the previous step will be taken as
shape, a meaningful static and dynamic analysis of the initial element forces for the next iteration and the
cable-stayed bridges can then be performed. The work in equilibrium conguration under the action of dead load
this study is focused on the initial shape (shape nding) and such initial forces will be determined anew.
analysis to nd the geometric conguration and pre- During shape iteration, several control points on the
forces in members of cable-stayed bridges. The analysis girder (usually the nodes intersected by the girder and the
can be performed in two dierent ways: one is a linear cable) will be chosen for checking whether the conver-
computation procedure (linear theory) and the other is a gence tolerance is achieved or not. In each shape iteration
nonlinear computation procedure (nonlinear theory). In the ratio of the vertical displacement at control points to
the former case, all the nonlinearities of cable-stayed the main span length will be checked. To avoid deections
bridges are neglected and only the linear elastic cable and bending moments of tower to appear, the conver-
and beam-column elements and linear constant coordi- gence check can also be done in a similar way for the tower
nate transformation coecients are used in the com- deections, where several control points, e.g., tip of the
putation. In the latter case, all the nonlinearities of tower and nodes intersected by the tower and the cable,
cable-stayed bridges are taken into consideration, i.e., are chosen and the ratio of the horizontal displacement
the nonlinear cable element with sag eect and the beam- at control points to the tower height will be checked.
column element including stability function coecients The convergence tolerance for shape iterations can
as well as nonlinear coordinate transformation coe- be expressed in the following form:
cients are used in the analysis. The details of the initial
shape analysis are referred to Refs. [5,1214]. Theoreti- qa
6 es
cally, a more accurate (exact) solution can be obtained Ls
only by the nonlinear theory. And through iterative
computation a convergent solution can be obtained and where qa is the displacement at control points, Ls is the
a more smooth shape of the bridge girder can be found. reference length chosen for shape iteration. The refer-
The initial shape of a cable-stayed bridge provides ence length is set equal to the main span length for
the geometric conguration as well as the prestress dis- checking the girder deection and set equal to the tower
tribution of the bridge under the action of the dead load height for checking the tower deection.
of girders and towers and the pretension force in in- The shape iteration will be repeated until the con-
clined cable stays. The relations for the equilibrium vergence tolerance es , say 10 4 , is achieved. When the
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 333

convergence tolerance for shape iteration is reached, this paper is to set up a nite element computation
computation will be stopped and the initial shape of the procedure to compute and nd the initial shape of the
cable-stayed bridge is found. Both the shape iteration bridge structure at each erection stage systematically. In
and the equilibrium iteration are carried out in the the following the erection procedure of the cantilever
nonlinear computation procedure. In the linear com- method will be shortly explained and then the two
putation procedure, shape nding is carried out by analysis methods, the forward process analysis and the
shape iteration without considering the equilibrium backward process analysis, for the shape nding of the
iteration. bridge structures during erection procedures will be
The procedure of shape nding analysis of cable- introduced in details.
stayed bridges is briey summarized in the following:
4.1. Erection by the cantilever method
(1) Input the geometric and physical data of the bridge.
(2) Input the dead load of girders and towers. The ease of erection is one of the main reasons for the
(3) Input the reference conguration (designed shape) success of cable-stayed bridges over the last half century
of the bridge. [5,6,11]. Because of their self-anchored cable systems,
(4) Input suitably estimated initial forces in cable stays the cantilever method has been widely used for the gir-
to start the computation. der erection of cable-stayed bridges. The cantilever
(5) Find equilibrium position method is considered as the natural and logical solution
(i) Linear procedure for constructing the cable-stayed bridges of large span,
Linear cable and beam-column elements and where new girder segments are installed and then sup-
linear constant coordinate transformation ported by new cable stays in each erection stage, and the
coecients aja are used. construction process keeps going stage-by-stage until the
Set up and solve the linear system equation bridge is completed. Since no auxiliary supports are
for qa (equilibrium position). needed for constructing the bridge girder in the canti-
No equilibrium iteration is carried out. lever method, a lot of construction cost and time can be
(ii) Nonlinear procedure saved. There are two basic alternates in the cantilever
Nonlinear cable element with sag eect and method. One is named herein the single cantilever
beam-column element and nonlinear coordi- method and the other is the double cantilever method.
nate transformation coecients aja , aja;b are In the former the side span girders of the bridge are
used. erected on auxiliary piers and afterwards the stiening
Set up and solve the incremental linearized girder in main span is erected by one-sided free can-
system equation for Dqa . tilevering until the span centre or the anchor pier on the
Equilibrium iteration is performed by using far end is reached. In the latter, the bridge girder is
the NewtonRaphson method. erected from both side of the tower towards the anchor
(6) Shape iteration piers and the main span centre by double-sided free
Check if the convergence tolerance cantilevering [5,6,11]. In this study the double cantilever
method is considered. But the concept and the analysis
qa
6 es method presented here can also be applied to the single
Ls
cantilever method.
As an example, the erection procedure of a harp
is achieved or not. cable-stayed bridge performed by the double cantilever
If converged, the equilibrium conguration is the method is summarized as follows and illustrated in
desired initial shape. Otherwise, the newly ob- Fig. 3:
tained axial forces of members are taken as initial
element forces, repeat steps 5 and 6. Stage 1. The Pylons are erected.
(7) Output of the initial shape including geometric con- Stage 2. The rst pair of girder segments B1 is in-
guration and element forces. stalled.
Stage 3. The stayed cables C1 are installed and
stressed initially to elevate the girders and relieve
4. Shape nding analysis during erection procedures their bending moments.
Stage 4. The pair of girder segments B2 are installed.
For constructing the bridge and predicting the Stage 5. The stayed cables C2 are installed and
structural behaviors of the bridge during its erection stressed.
procedures, the geometric conguration and preforces in Stage 6. The girder segments B3 are installed.
members of the bridge structure at each erection stage Stage 7. The stayed cables C3 are installed and
have to be known and examined in details. The aim of stressed.
334 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

Stage 1

Ci = number of cable
Bi = number of beam segment

L (left tower) R (right tower)


Stage 2

B1 B1 B1 B1

Stage 3
C1 C1 C1 C1

B1 B1 B1 B1

Stage 4

C1 C1 C1 C1

B2 B1 B1 B2 B2 B1 B1 B2

Stage 5
C2 C2 C2 C2
C1 C1 C1 C1

B2 B1 B1 B2 B2 B1 B1 B2

Stage 6
C2 C2 C2 C2
C1 C1 C1 C1

B3 B2 B1 B1 B2 B3 B3 B2 B1 B1 B2 B3

Stage 7
C3 C3 C3 C3
C2 C2 C2 C2
C1 C1 C1 C1

B3 B2 B1 B1 B2 B3 B3 B2 B1 B1 B2 B3

Stage 8
C3 C3 C3 C3
C2 C2 C2 C2
C1 C1 C1 C1

B3 B2 B1 B1 B2 B3 B4 B4 B3 B2 B1 B1 B2 B3

L R

Fig. 3. Erection stages of harp cable-stayed bridges.

Stage 8. Girder segments B4 is installed and the nodal and element numbering of the symmetric harp
bridge is closed at the main span centre. cable-stayed bridge at each erection stages are given. In
the gure, NU the number of degrees of freedom,
NE number of elements, NJ number of nodes, and
4.2. Forward process analysis (FPA) ISB semi-bandwidth of the system stiness matrix.
There are three system displacements at each node in the
The forward process analysis of cable-stayed bridges plane model of cable-stayed bridges, one rotation and
during construction is performed by following the se- two translation displacements. The computation of the
quence of erection stages in bridge construction. The forward process analysis is rst started from the single
nite element model of the harp cable-stayed bridge at pylon at stage 1 as shown in Fig. 4 and then continued at
dierent erection stages is shown in Fig. 4, in which the stages 2, 3, . . ., stage-by-stage, until stage 8, where the
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 335

5
Stage 1 NU=15
4 NE=4
NU = number of D.O.F. NJ=5
3
NE = number of elements ISB=6
2 NJ = number of nodes
1 ISB = semi-bandwidth of system
stiffness matrix
L
i = nodal number
5
i = element number Stage 2 NU=21
4 NE=6
3 NJ=7
6 7
ISB=18
2
1

5 NU=21
Stage 3
4 NE=8
NJ=7
3
ISB=18
6 2 7
1

5 Stage 4 NU=27
4 NE=10
NJ=9
3
ISB=18
8 6 2 7 9
1

5 Stage 5 NU=27
4
NE=12
NJ=9
3 ISB=18
8 6 2 7 9
1

5 NU=33
Stage 6
4 NE=14
3
NJ=11
ISB=18
10 8 6 2 7 9 11
1

5 NU=33
Stage 7
4 NE=16
3
NJ=11
ISB=21
10 8 6 2 7 9 11
1

5 14
Stage 8 NU=69
NE=34
4 17 NJ=23
3
ISB=21
20
10 8 6 2 7 9 11 12 13 16 19 22 21 18 15
1 23

L R

Fig. 4. Node and element numbering of harp cable-stayed bridges at dierent erection stages.

bridge is closed at the main span centre and the analysis bending moment in girders and to keep the bridge girder
of the bridge during girder construction is completed. In in desired correct position. The stressing force needed in
each stage the geometric conguration and internal cables and the girder elevation have to be determined at
forces of members of the bridge structure will be deter- each erection stage by the shape nding procedure de-
mined. scribed in the previous section. In the forward process
At erection stages of even number (2, 4, 6) only the analysis, shape iteration has to be done in order to keep
new girder segments are installed and the exterior stayed the stiening girder in horizontal position (a upward
cables are not yet in place. Relatively large vertical dis- precamber is allowed).
placements and bending moments of the girder may Since the cables will be stressed after new girder
appear. At erection stages of odd number (3, 5, 7) the segments and stayed cables are installed at the stage of
new exterior stayed cables are installed at the tip of odd number, an initial estimated force in cables is nee-
the new girder segments and then stressed to lift up the ded to start the shape iteration computation. The esti-
girders to certain elevation in order to relieve the mated cable force is determined in this study by setting
336 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

Fig. 5. Estimation of the initial cable force.

the tip displacement of girder segment caused by dead (3) Stage k 7


load w and weight of machine equipment Weq to be equal (i) Remodeling the analysis model
to that of the cable pretension force T0 , as shown in Fig. The cables of number , 15 16are newly installed
3wl8W
5, where T 8 sin a eq is the estimated initial cable force and will be stressed in situ. The rebuilt analysis
used to start the shape iteration, EI and l are exural model at stage k 7 has NU 33, NE 16,
rigidity and length of the girder segment respectively, NJ 11 and ISB 21, as shown in Fig. 4.
a is the inclined angle of the cable. (ii) Input the estimated initial forces of cables and
For illustration, the erection stages 57 shown in Fig. dead load of the girder and the tower.
4 are chosen for explaining the computation procedure (iii) Find the equilibrium position
of the forward process analysis which is summarized The equilibrium position is determined anew by
as follows: solving the static system equation. Equilibrium
iteration is carried out if the nonlinear theory
(1) Stage k 5 is used.
After nding the shape of the bridge structure at (iv) Shape iteration is carried out
stage k 5, the geometric conguration and the ini- Check if the elevation of girders and the deec-
tial force in members are known. tion of towers satisfy the convergence tolerance
(2) Stage k 6 of shape iteration or not.
(i) Remodeling the analysis model If not, the shape iteration has to be repeated.
Based on the determined (constructed) structural If yes, the initial shape (geometry and member pre-
shape at stage k 5, the girder element of num- forces) of the bridge structure at stage k 7 is
ber , are installed and the analysis model is
13 14 found and the computation is stopped.
rebuilt for stage k 6 as shown in Fig. 4. The (4) Computation is continued for the next stage until
number of nodes, elements and system coordi- the nal stage is reached, i.e., the bridge is com-
nates is renumbered as shown in Fig. 4. The total pletely constructed.
degree of freedom of the bridge structure be-
comes NU 33, and the total number of nodes The ow chart of the forward process analysis is
and elements are NJ 11, NE 14, respec- given in Fig. 6. The forward process analysis follows
tively. If the system coordinates are ordered by exactly the actual sequence of the erection procedure
following the numbering of nodes the semi-band of the bridge. The advantage of the forward process
width of the system stiness matrix becomes analysis is that the real-time factors of the bridge can be
ISB 18. taken into account, such as creep and shrinkage of
(ii) Find the equilibrium position concrete, and any alteration in design, etc.
The equilibrium position of the bridge structure
at stage 6 is determined anew by solving the sta- 4.3. Backward process analysis (BPA)
tic system equation. Equilibrium iteration is car-
ried out if the nonlinear theory is used. In contrast to the forward process analysis, the
(iii) No shape iteration is performed here, since the backward process analysis of cable-stayed bridges dur-
exterior cables at the tip of the girders are not ing construction is carried out by following the direction
yet installed. reversed to the sequence of erection stages in the bridge
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 337

start

input the geometric and physical data of the bridge


input the reference configuration of the bridge

k=0
DO _ LOOP k = 1,2,....., k end
k = no. of stage erection
k = k+1 k end = last stage erection

install girder segments (k = even)


install and stress cables (k = odd > 1)

rebuild the analysis model


reset NU,NE,NJ,ISB

input dead load of members


input estimated initial cable forces

set up and solve the system equation


find the equilibrium position and element forces no

equilibrium
linear no iteration
set q = 0.0 computation q
<
take the determined axial q
yes
forces of members as
initial element forces yes
no
k = odd
yes

shape
no iteration
q
<s
Ls

yes

update and output initial shape


(k k
) o k
nodal coordinates X , Y and element forces S j
end of DO _ LOOP

stop

Fig. 6. Flow chart of the forward process analysis for shape nding of the cable-stayed bridge during construction.

construction. The computation of the backward process on the far end of anchor piers. After releasing girder
analysis is started with the completed whole cable-stayed segments the bridge is then remodeled and reanalyzed
bridge (stage k 8 as shown in Fig. 4) by releasing one under the action of dead load and the internal force of
or one pair of girder segments at the main span centre or members determined in the previous stage in order to
338 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

nd the new initial shape which provides the geometric members provided by the structure at the previ-
conguration and member forces of the bridge structure ous stage k 6. Similarly, equilibrium iteration
at the new (current) stage. Stage-by-stage, the girder is carried out when the nonlinear theory is used.
segments and adjointing stayed cables are released, and (iii) No shape iteration is required.
the analysis model is rebuilt and the computation is (4) Repeatedly continue the computation for the next
continued repeatedly until the nal stage is reached. At stage until the nal stage (k 1) is reached.
the nal stage (k 1) there is only the pylons existed as
shown in Fig. 4. In the backward process analysis, the The ow chart of the backward process analysis is
initial shape (the geometric conguration and member given in Fig. 7. The advantage of the backward process
forces) of the whole cable-stayed bridge has to be found analysis is that no shape iteration is required at each
rst by using the shape nding procedure presented in erection stage. The shape at each stage determined by the
Section 3. After releasing girder segments and cable equilibrium condition is the desired correct position of the
stays, the conguration and member forces of the bridge bridge for the next erection stage, in which the girder is
structure are determined anew at each stage by solving precambered upwards. The disadvantage of this method is
the static system equation. When the nonlinear theory is that the real-time factors of the bridge during construc-
used, the linearized system equation is used and the tion, such as creep and shrinkage of concrete as well as any
equilibrium iteration with NewtonRaphson approach alteration in design, cannot be included, because the
is performed. computation is performed backwards from the completed
Similarly, here take stages k 7, 6, 5 shown in Fig. 4 bridge.
as an example for illustrating the computation proce-
dure of the backward process analysis. The computation
process is briey summarized as follows: 5. Example: the harp cable-stayed bridge

(1) Stage k 7 As an example, a three span symmetric harp cable-


After nding the shape of the bridge structure at stayed bridge as shown in Fig. 8 is taken for the shape
stage k 7, the geometric conguration and the ini- nding analysis of the bridge during the erection pro-
tial force in all members are known. cedure using the double cantilever method. The bridge
(2) Stage k 6 has two pylons of 260 ft high and 12 stayed cables ar-
(i) Remodeling the analysis model ranged in a harp form. The main span of the bridge is
Based on the determined structural shape at stage 1100 ft and the side span 450 ft. The nite element model
k 7, the exterior cables of number , are re-
15 16 of the whole bridge consists of 12 cable elements, 14
leased. The analysis model of the bridge structure beam-column elements for the stiening girder and 8
at stage k 6 is rebuilt as shown in Fig. 4, with beam-column elements for the pylons. This harp cable-
NU 33, NE 14, NJ 11, ISB 18. stayed bridge is erected by double cantilever method and
(ii) Find the equilibrium position there are 8 erection stages for constructing the girder of
The equilibrium position of the bridge structure the bridge. The length of each girder segment is 50 ft and
at stage k 6 is determined anew under the only at closing stage of the main span the girder segment
action of dead load of girders and towers, and length is 100 ft.
the internal forces in members obtained in the
previous stage k 7. The newly determined equi- 5.1. Whole bridge analysis
librium position oers the geometric congura-
tion and member forces of the bridge structure The initial shape of the whole harp cable-stayed
at the new stage k 6. Equilibrium iteration is bridge is rst determined herein by the two-loop itera-
carried out when the nonlinear theory is used. tion shape nding method, where both shape iteration
(iii) No shape iteration is required. and equilibrium iteration are performed by using the
(3) Stage k 5 linear and the nonlinear computation procedures. Three
(i) Remodeling the analysis model cycles of shape iteration are needed for nding the
Based on the determined structural shape at convergent initial shape of the whole harp cable-stayed
stage k 6, the exterior girder segments of num- bridge, as shown in Fig. 9.
ber , are then released and the analysis model
13 14

for stage k 5 is rebuilt as shown in Fig. 4. The 5.2. Forward process analysis (FPA)
model has NU 27, NE 12, NJ 9, ISB 18.
(ii) Find the equilibrium position As described in the previous section, the forward
Similarly, the shape of the bridge structure at process analysis is performed exactly by following the
stage k 5 is determined again under the ac- sequence of erection stages in construction. The com-
tion of dead load and the internal forces of putation is started from the single pylon at stage 1 and
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 339

start

 input the geometric and physical data of the bridge


 input the reference configuration of the bridge

k = kend

 shape finding of the whole cable-stayed bridge


DO LOOP k = k end , k end 1,..... 2,1
k = no. of erection stage
k = k 1 k end = last erection stage

 release girder segments (k = odd )


 release exterior cable-stays (k = even)

 rebuild the analysis model


 reset NU,NE,NJ,ISB

 input dead load of members


k 1
 input the nodal coordinates X , Y (
k 1
)
and element
o
k 1
forces S j determined in previous stage

 set up and solve the system equation


 find the equilibrium position and element forces no

equilibrium
linear no iteration
computation q
<
q
yes
yes

 update and output initial shape


( )
o
k k k
nodal coordinates X , Y and element forces S j
end of DO _ LOOP

stop

Fig. 7. Flow chart of the backward process analysis for shape nding of the cable-stayed bridge during construction.

carried out stage-by-stage until stage 8 is reached, i.e., girder at dierent erection stages during shape nding
the bridge girder is completely erected. The results of the computation are listed. The variation of cable forces at
forward process analysis are listed in Tables 1 and 2 and dierent erection stages are given in Table 2. There exists
plotted in Figs. 10 and 11. In Table 1 the variation of the small dierence between the results determined by the
vertical displacement of control points on the bridge linear and the nonlinear computation procedure. The
340 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

2532.29 Kips 2561.63 2561.63 2532.29


2399.69 2356.55 2356.55 2399.69
2052.48 2027.11 2027.11 2052.48

0.1310 ft
(DISPLACEMENT ENLARGED BY 10 TIMES)

REFERENCE POSITION
DURING SHAPE ITERATION (NSI=1,2)
INITIAL SHAPE DETERMINED (NSI=3)
= 0.1310 ft = DEFLECTION AT MID-SPAN
s = 10-4= TOLERANCE OF SHAPE ITERATION

Fig. 9. Initial shape nding of symmetric harp cable-stayed


bridge (based on nonlinear computation procedure).

Fig. 8. Symmetric harp cable-stayed.


due to dead load action there is a downward displace-
ment of 0.0082 ft at its top end. At stages 2, 4 and 6, only
results determined by the nonlinear computation pro- the new girder segments are installed but not the exte-
cedure will be considered as the correct result in the rior cable stays, so the equilibrium position is deter-
study. mined anew without shape iteration. But at stages 3, 5
In Fig. 10 the congurations of the bridge structure and 7, the new exterior cable stays are installed and
at each erection stage are plotted and the vertical dis- stressed. Therefore, the shape iteration is carried out at
placements of the girder tip and cable forces are also these stages to nd the new equilibrium position.
given, where NSI means the number of shape iterations Through shape iteration, the girder is kept in horizon-
(S.I.) needed for the convergent solution. As shown in tal position and certain bending moment in girders is
Fig. 10, only the pylon exists at erection stage 1 and relieved. Finally, at stage 8 the shape iteration is carried

Table 1
Vertical displacement (ft) of control points determined by FPA at dierent erection stages during shape nding
Erection NSI Linear analysis Nonlinear analysis
stages k NODE5 NODE7 NODE9 NODE11 NODE5 NODE7 NODE9 NODE11
1 1 )0.0082 )0.0082
2 1 )0.0161 )0.6825 )0.0161 )0.6825
3 1 )0.0196 )0.0256 )0.0196 )0.0255
4 1 )0.0372 )1.3248 )4.5129 )0.0372 )1.3383 )4.5466
5 1 )0.0408 )0.3698 )0.4778 )0.0408 )0.3766 )0.4986
2 )0.0011 )0.1554 0.0090 )0.0010 )0.1560 0.0057
3 )0.0003 )0.1071 0.0550 )0.0003 )0.1069 0.0548
6 1 )0.0755 )0.5662 )2.8326 )6.8255 )0.0764 )0.5785 )2.9340 )7.0327
7 1 )0.0751 )0.5879 )1.0458 )0.6125 )0.0753 )0.6230 )1.2983 )1.3049
2 )0.0018 )0.2244 )0.3438 0.1036 )0.0017 )0.1928 )0.2828 0.1117
3 )0.0006 )0.1078 )0.1931 0.0696 )0.0005 )0.0933 )0.1479 0.1103
4 )0.0003 )0.0484 )0.1167 0.0402 )0.0003 )0.0447 )0.0901 0.0764
5 )0.0002 )0.0177 )0.0745 0.0238
8 1 )0.1044 )0.5957 )1.4328 )2.3296 )0.1066 )0.9160 )2.2901 )3.7576
2 )0.0025 0.0267 )0.0125 )0.2684 )0.0038 0.0066 )0.0982 )0.5279
3 )0.0002 0.0680 0.1026 )0.0635 )0.0005 0.0710 0.1065 )0.1466
4 )0.0001 0.0640 0.1191 )0.0739
5 )0.0001 0.0560 0.1152 )0.0460
6 )0.0001 0.0516 0.1112 )0.0308
7 )0.0001 0.0496 0.1083 )0.0216
Remarks: NSInumbers of shape iteration; italicised data means convergent solution. Convergence tolerance e 10 4 , main span is
1100 ft. When iteration cycles exceed 20 times the computation is considered as not convergent and will be stopped. FPA Forward
process analysis.
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 341

Table 2
Cable forces (kips) determined by FPA at dierent erection stages during shape nding
Erection NSI Linear analysis Nonlinear analysis
stages k EL7 EL11 EL15 EL16 EL7 EL11 EL15 EL16
1 1
2 1
3 1 813.7 813.8
4 1 3092.0 3074.7
5 1 1359.6 1166.2 1362.5 1161.6
2 1636.4 1152.0 1639.8 1150.7
3 1829.1 1098.9 1831.3 1098.4
6 1 2545.2 3479.3 2566.5 3475.8
7 1 1652.0 1593.9 1394.9 1394.9 1696.9 1758.9 1270.4 1270.4
2 2045.4 1898.7 1210.2 1210.2 2032.0 2005.5 1157.9 1157.9
3 2234.7 2071.3 1091.1 1091.1 2195.1 2136.3 1065.4 1065.4
4 2319.0 2176.1 1022.9 1022.9 2273.1 2216.6 1010.6 1010.6
5 2349.3 2243.4 982.8 982.8
8 1 2277.7 2498.3 2250.1 2238.1 2287.8 2729.0 1967.8 1936.7
2 2223.0 2496.9 2419.0 2434.7 2183.6 2708.2 2264.0 2267.0
3 2175.6 2469.6 2461.2 2488.5 2099.2 2644.9 2355.7 2373.2
4 2052.9 2594.9 2404.6 2430.0
5 2032.6 2558.1 2435.7 2465.7
6 2027.7 2530.1 2456.5 2489.4
7 2031.5 2508.1 2471.0 2505.8
Remarks: NSInumbers of shape iteration; italicised data means convergent solution. Convergence tolerance e 10 4 , main span is
1100 ft. When iteration cycles exceed 20 times the computation is considered as not convergent and will be stopped. Cable element
EL7, EL11, EL15 and EL16 locates between node numbers 3 and 6, 4 and 8, 5 and 10 and 5 and 11, respectively.

Fig. 10. Congurations of harp cable-stayed bridge during erection stages (forward process analysis, double cantilever method).
342 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

tension force (10 Kips)


cable element 3-7
3 cable element 4-9

3
2

0
1 2 3 4 5 6 7 8
erection stage (k)

10
compression force (10 3 Kips)

pylon element 1-2


8 pylon element 3-4
6

0
1 2 3 4 5 6 7 8
erection stage (k)

10
compression force (10 Kips)

girder element 2-7


8 girder element 7-9
3

0
1 2 3 4 5 6 7 8
erection stage (k)

100
bending moment (103 Kips-ft)

girder element 2-7


80
girder element 7-9
60

40

20

0
1 2 3 4 5 6 7 8
erection stage (k)

Fig. 11. Variation of member forces during erection stages (forward process analysis).

out for the whole bridge once more in order to ensure procedure and decreases dramatically when the adjoin-
the designed bridge form is achieved. The nal results ting cable stays are installed and stressed at stages 3, 5
at stage 8 (the bridge is completed) are almost identi- and 7.
cal to that obtained by the whole bridge analysis. The The results in Tables 1 and 2 and Figs. 10 and 11 oer
variation curve of selected member forces at dierent the necessary data which can be used for checking
stages during erection procedure are plotted in Fig. 11, and controlling the real-time erection procedure of the
in which it can be seen that the compression force in cable-stayed bridge during construction. The designed
pylon and girder increases monotonously and ap- shape (conguration of girders and pretension in cables)
proaches to the nal values at stage 8, and the bending of cable-stayed bridge can then be ensured and con-
moment of the girder oscillates during the erection structed.
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 343

5.3. Backward process analysis (BPA) ments and adjointing cables and the shape nding
computation is continued for each stage until stage 1 is
The backward process analysis of the harp cable- reached, where only the pylon exists. Similarly, the
stayed bridges during the erection procedure is per- variation of the vertical displacement of control points
formed by following the reverse direction of the on the girder and the axial force in cables at dierent
sequence of erection stages in bridge construction. The erection stages during shape nding are given in Tables 3
computation is started from the completed whole cable- and 4. Since no shape iteration is needed, computation
stayed bridge, i.e., from the stage 8 as shown in Fig. 12. required by the backward process analysis is easier and
By removing the centre girder segments at main span faster than that of the forward process analysis.
and the roller support at anchor piers, the analysis The congurations of the bridge structure and the
model is rebuilt for the bridge structure at the next stage cable forces at dierent erection stages determined by
(k 7) and the shape of the released bridge structure is the backward process analysis using nonlinear compu-
determined anew. Then, stage-by-stage, the analysis tation procedure are plotted in Fig. 12. It can be evi-
model is rebuilt at each stage by removing girder seg- dently seen that the girder tip moves upwards after

STAGE 8 STAGE 4
2531.5 2560.9 2561.0 2531.5 kips
2400.3 2356.9 2356.8 2400.4
2053.8 2027.9 2028.0 2053.7 3683.8 3680.0 kips

+3.3002 ft
+0.1304 ft

STAGE 7 STAGE 3
1123.2 1125.5 kips
2148.7 2146.0
1396.1 1392.3 kips
2052.5 2046.5
-1.0691 ft -0.4819 ft

STAGE 6 STAGE 2
3756.8 3758.1 kips
2320.7 2314.3
+0.6412 ft
+4.3743 ft

STAGE 5 STAGE 1 -0.0978 ft


1341.4 1342.8 kips
1684.4 1677.9
-1.3194 ft

"+" represents downward displacement

Fig. 12. Congurations of harp cable-stayed bridges during erection stages (backward process analysis, double cantilever method).

Table 3
Vertical displacement (ft) at control points determined by BPA at dierent erection stages during shape nding
Erection NSI Linear analysis Nonlinear analysis
stages k NODE5 NODE7 NODE9 NODE11 NODE5 NODE7 NODE9 NODE11
8 1 0.0000 0.0115 0.0508 0.0689 )0.0010 0.0304 0.0719 )0.0274
7 1 0.0297 )0.0397 0.2029 1.0582 0.0282 0.0083 0.3078 1.0691
6 1 0.0309 )0.2157 )1.6999 )4.8236 0.0288 )0.1548 )1.4555 )4.3743
5 1 0.0641 0.2125 1.0662 0.0622 0.2726 1.3194
4 1 0.0681 )0.8238 )3.3117 0.0662 )0.8210 )3.3002
3 1 0.0856 0.4717 0.0836 0.4819
2 1 0.0921 )0.6510 0.0901 )0.6412
1 1 0.0998 0.0978
Remarks: NSI 1, since no shape iteration is required in the backward process analysis (BPA).
344 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

Table 4
Cable forces (kips) determined by BPA at dierent erection stages during shape nding
Erection NSI Linear analysis Nonlinear analysis
stages k EL7 EL11 EL15 EL16 EL7 EL11 EL15 EL16
8 1 2112.9 2186.6 2669.0 2711.9 2053.8 2400.3 2531.5 2560.9
7 1 2119.2 1957.1 1212.6 1223.0 2052.5 2148.7 1123.2 1125.5
6 1 2411.6 3690.3 2320.7 3756.8
5 1 1772.4 1281.6 1684.4 1341.4
4 1 3676.9 3683.8
3 1 1398.0 1396.1
2 1
1 1
Remarks: Cable element EL7, EL11, EL15 and EL16 locates between node numbers 3 and 6, 4 and 8, 5 and 10 and 5 and 11,
respectively. NSI 1, since no shape iteration is required in the backward process analysis (BPA).

4
tension force (10 Kips)

cable element 3-7


3 cable element 4-9
3

0
1 2 3 4 5 6 7 8
erection stage (k)
compression force (103 Kips) compression force (103 Kips)

10
pylon element 1-2
8 pylon element 3-4
6

0
1 2 3 4 5 6 7 8
erection stage (k)

10
girder element 2-7
8 girder element 7-9
6

0
1 2 3 4 5 6 7 8
erection stage (k)
bending moment (103 Kips-ft)

80
girder element 2-7
60 girder element 7-9
40

20

-20
1 2 3 4 5 6 7 8

erection stage (k)

Fig. 13. Variation of member forces during erection stages (backward process analysis).
P.-H. Wang et al. / Computers and Structures 82 (2004) 329346 345

removing a girder segments as shown at stages 7, 5 and 3 is presented in the study, both the FPA and BPA
in Fig. 12. The upward tip displacements can be con- methods can also be applied to bridges constructed
sidered as the necessary precamber of the girder for the by the single cantilever method.
next erection stage during construction. The precamber 4. In the FPA method, shape iteration has to be per-
is very helpful for keeping the bridge girder in original formed and the computation becomes time-con-
designed conguration and for reducing the bending suming.
moment in girders. As shown at stages 6, 4 and 2 in Fig. 5. No shape iteration is required in the BPA method
12, where the exterior cable stays are removed, but not and the computation in BPA is faster than that in
the adjointing girder segment, large downward dis- FPA.
placements at the tip of the girder will occur and the 6. The disadvantage of the BPA method is that the
bending moment in girders becomes quite large. Finally real-time factors of the bridge cannot be taken into
the variation curve of selected member forces at dierent consideration, such as creep and shrinkage of con-
stages during erection procedure are plotted in Fig. 13. crete, weight of machine equipments and design
It is also seen in Fig. 13 that the compression force in the alteration during construction, since the analysis is
pylon and the girder increases monotonously and the started from a completed whole bridge and carried
bending moment of the girder oscillates during erection out backwards stage-by-stage.
procedure. 7. The advantage of the FPA method is that the above
Similarly, the backward process analysis can also mentioned real-time factors of the bridge can be
oer the necessary data for checking and controlling the taken into account and the computation can be
real-time erection procedure of the cable-stayed bridge changed and repeated by following the actual erec-
during construction. tion procedure during real construction.
8. The solution of the BPA method is unique and of-
fers the accurate conguration and member pre-
6. Conclusion forces of the bridge structure at dierent erection
stages. The precamber of the bridge girder exists
A nite element computation procedure is set up for automatically in the solution and can keep the gird-
the shape nding analysis of cable-stayed bridges during ers in horizon and eectively reduce their bending
erection procedures. Two computational process are moments when girder segments are installed at the
established: the forward process analysis (FPA) and the next erection stage.
backward process analysis (BPA). The forward process 9. The solution of the FPA method is not unique, since
analysis of cable-stayed bridges during construction is shape iteration is carried out at erection stages. The
performed by following the sequence of erection stages numerical results depends on the estimated cable ini-
in bridge construction, while the backward process tial forces used for starting the computation of
analysis follows the reverse direction of the sequence of shape iterations. There are many possible solutions
the bridge erection procedure. At each erection stage, existed. The nal results determined by the FPA
the nite element analysis model is rebuilt, then the method at the nal erection stage, i.e., at the stage
system equation is set up and solved anew under the of girder closing at bridge mid-span or anchor piers,
action of dead load and member forces determined in may be quite dierent from that of the designed
the previous stage for nding the corresponding new shape of the bridge (the results of initial shape anal-
initial shape. Based on the numerical analysis in the ysis of the whole bridge). Therefore the shape itera-
study some conclusions are made as follows: tion has to be done once again at the end of the last
erection stage where the girder is closed, in order to
1. Both the FPA and BPA methods can be success- ensure the designed shape of the bridge is achieved.
fully and eciently used for nding the congura- 10. The initial shape analysis of the whole bridge is nec-
tions and preforces in members of the bridge essary for both the FPA and BPA methods. Its re-
structure at dierent erection stages during the gir- sults are used for starting the computation in the
der construction using the cantilever method. BPA method and used as a basis for checking the
2. Both the FPA and BPA methods can oer the nec- correctness of the results determined by the FPA
essary data which can be used for checking and method.
controlling the real erection procedures of the
cable-stayed bridge during construction, and to en- In both methods, either the linear computation pro-
sure that the designed shape (conguration of gird- cedure (linear theory) or the nonlinear computation
ers and pretension in cables) of cable-stayed bridges procedure (nonlinear theory) can be employed. Analysis
can be achieved and constructed. of cable-stayed bridges using the nonlinear theory oers
3. Although only an example of the harp cable-stayed theoretically more accurate results than that determined
bridge constructed by the double cantilever method by the linear theory. But the computation becomes more
346 P.-H. Wang et al. / Computers and Structures 82 (2004) 329346

complicated and time-consuming when the nonlinear [6] F. Leonhardt, W. Zellner, Past, present and future of
theory is utilized. From the view of engineering practice, cable- stayed bridges, in: Proceedings of The Seminar of
linear theory can be used for shape nding analysis, Cable-Stayed Bridge Recent Developments and Their
which oers acceptable results in many cases. Future, Yokohama, Japan, pp. 133, 1991.
[7] T. Nakagawa, K. Sugii, M. Nagai, H. Mochizuki, Design
sand erection of a cable trussed bridge, in: Proceedings of
the Thirteenth KKNN Symposium on Civil Engineering,
Acknowledgement Taipei, Taiwan, pp. 107112, December 2000.
[8] K.H. Schrader, Die Deformationsmethode als Grundlage
The research was sponsored by a grant under no. einer Problemorientierten Sprache, BI-Taschenbuch, *830,
NSC 89-2211-E-033-009 from the National Science Bibliographisches Institute, Mannheim, Zurich, 1969.
Council, Taiwan, Republic of China. [9] Tang MC. Analysis of cable-stayed bridges. J Struct Div,
ASCE 1971;97:148196.
[10] Tang MC. Design of cable-stayed bridges. J Struct Div
References ASCE 1972;98:1789802.
[11] M. Virlogeux, Erection of cable-stayed bridges, in: Pro-
[1] Billington D, Nazmy A. History and aesthetics of cable- ceedings of the Conference of Cable-stayed Bridges-recent
stayed bridges. J Struct Eng ASCE 1990;117(10):310134. developments and their future, held at Yokohama, Japan,
[2] Chang FK, Cohen E. Long-span bridges: state-of-the-art. pp. 77106, 1991.
J Struct Div ASCE 1981;107(ST7):114560. [12] Wang PH, Tseng TC, Yang CG. Initial shape of cable-
[3] Ernst HJ. Der E-Modul von Seilen unter Beruecksichti- stayed bridges. Int J Comput Struct 1993;46(6):1095106.
gung des Durchhanges. Der Bauingenieur 1965;40(2):525. [13] Wang PH, Yang CG. Parametric studies on cable-stayed
[4] Fleming JF. Nonlinear static analysis of cable-stayed bridges. Int J Comput Struct 1996;60(2):24360.
bridges. Int J Comput Struct 1979;10:62135. [14] Wang PH, Lin HT, Tang TY. Study on nonlinear analysis
[5] Gimsing NJ. Cable Supported Bridges Concept and De- of a highly redundant cable-stayed bridge. Int J Comput
sign. second ed. New York: John Wiley and Sons Inc.; 1997. Struct 2002;80(2):16582.

You might also like