Equipment Tag
Workpackage
Descriptions
Weight (Ton)
Project Area
Equipment
Weighting
Individual
Man hour
Progress
Progress
Overall
Item
No
10% 60% 10% 10% 10%
1 Shell & Tube Exchanger E02 A WP-M01 15.0 150 0.04 100% 100% 100% 100% 100% 100% 0.042
2 Shell & Tube Exchanger E03 A WP-M02 12.0 120 0.03 0% 0% 0% 0% 0% 0% 0.000
3 Drum D01 A WP-M03 5.0 50 0.01 100% 100% 100% 100% 100% 100% 0.014
4 Tower T10 A WP-M04 57.0 570 0.16 100% 100% 100% 100% 100% 100% 0.158
5 Shell & Tube Exchanger E05 B WP-M05 18.0 214 0.06 100% 100% 100% 100% 100% 100% 0.060
6 Drum D02 B WP-M06 7.0 83 0.02 100% 100% 100% 100% 100% 100% 0.023
7 Tower T20 B WP-M07 50.0 595 0.17 100% 100% 100% 100% 100% 100% 0.165
8 Drum D20 B WP-M08 4.0 48 0.01 100% 100% 100% 100% 100% 100% 0.013
updated using
Workpackage
Descriptions
Weight (Ton)
Project Area
Equipment
Weighting
Individual
Man hour
Progress
Progress
data from
Overall
Item
Equipment
No
1 Compressor C01 A WP-M09 20.0 205 0.06 100% 100% 100% 100% 100% 100% 100% 0.057
2 Compressor C02 A WP-M10 20.0 205 0.06 0% 0% 0% 0% 0% 0% 0% 0.000
3 Pump P01 A WP-M11 15.0 150 0.04 100% 100% 100% 100% 100% 100% 100% 0.042
4 Pump P02 A WP-M12 15.0 150 0.04 100% 100% 100% 100% 100% 100% 100% 0.042
5 Pump P03 B WP-M13 15.0 179 0.05 100% 100% 100% 100% 100% 100% 100% 0.050
6 Compressor C03 B WP-M14 18.0 214 0.06 100% 100% 100% 100% 100% 100% 100% 0.060
7 Compressor C04 B WP-M15 18.0 214 0.06 0% 0% 0% 0% 0% 0% 0% 0.000
8 Pump P04 B WP-M16 12.0 143 0.04 100% 100% 100% 100% 100% 100% 100% 0.040
9 Pump P05 B WP-M17 12.0 143 0.04 100% 100% 100% 100% 100% 100% 100% 0.040
8 Pump P06 B WP-M18 14.0 167 0.05 100% 100% 100% 100% 100% 100% 100% 0.046
Progress
Progress
(Tonage)
by Area
Project
Overall
Quantity
Area
Developed by Toolbox4Planning
Learn more at http://www.toolboxforplanning.com
Progress Updating Section (Static Equipment Group) Progress Calculation Section(Static)
Equipment Project Weight Chipping & Lifting & Alignment & Clear Chipping & Lifting & Alignment & Clear
Item Equipment Descriptions Workpackage Grouting Grouting
Tag No Area (Ton) Padding Rigging Bolting Punchlist Padding Rigging Bolting Punchlist
1 Shell & Tube Exchanger E02 A WP-M01 15 10-Jan-10 15-Jan-10 17-Jan-10 20-Jan-10 22-Jan-10 15 15 15 15 15
2 Shell & Tube Exchanger E03 A WP-M02 12
3 Drum D01 A WP-M03 5 11-Jan-10 16-Jan-10 18-Jan-10 21-Jan-10 23-Jan-10 5 5 5 5 5
4 Tower T10 A WP-M04 57 12-Jan-10 17-Jan-10 19-Jan-10 22-Jan-10 24-Jan-10 57 57 57 57 57
5 Shell & Tube Exchanger E05 B WP-M05 18 13-Jan-10 18-Jan-10 20-Jan-10 23-Jan-10 25-Jan-10 18 18 18 18 18
6 Drum D02 B WP-M06 7 14-Jan-10 19-Jan-10 21-Jan-10 24-Jan-10 26-Jan-10 7 7 7 7 7
7 Tower T20 B WP-M07 50 15-Jan-10 20-Jan-10 22-Jan-10 25-Jan-10 27-Jan-10 50 50 50 50 50
8 Drum D20 B WP-M08 4 16-Jan-10 21-Jan-10 23-Jan-10 26-Jan-10 28-Jan-10 4 4 4 4 4
Equipment Project Weight Chipping & Lifting & Levelling & Preliminary Final Clear Chipping & Lifting & Levelling & Preliminary Final Clear
Item Equipment Descriptions Workpackage
Tag No Area (Ton) Padding Rigging Grouting Alignment Alignment Punchlist Padding Rigging Grouting Alignment Alignment Punchlist
Developed by Toolbox4Planning