You are on page 1of 2

Progress Tracking Sheet-Equipment Erection

Chipping & Lifting & Alignment & Clear


Grouting
Padding Rigging Bolting Punchlist

Equipment Tag

Workpackage
Descriptions

Weight (Ton)
Project Area
Equipment

Weighting

Individual
Man hour

Progress

Progress
Overall
Item

No
10% 60% 10% 10% 10%

1 Shell & Tube Exchanger E02 A WP-M01 15.0 150 0.04 100% 100% 100% 100% 100% 100% 0.042
2 Shell & Tube Exchanger E03 A WP-M02 12.0 120 0.03 0% 0% 0% 0% 0% 0% 0.000
3 Drum D01 A WP-M03 5.0 50 0.01 100% 100% 100% 100% 100% 100% 0.014
4 Tower T10 A WP-M04 57.0 570 0.16 100% 100% 100% 100% 100% 100% 0.158
5 Shell & Tube Exchanger E05 B WP-M05 18.0 214 0.06 100% 100% 100% 100% 100% 100% 0.060
6 Drum D02 B WP-M06 7.0 83 0.02 100% 100% 100% 100% 100% 100% 0.023
7 Tower T20 B WP-M07 50.0 595 0.17 100% 100% 100% 100% 100% 100% 0.165
8 Drum D20 B WP-M08 4.0 48 0.01 100% 100% 100% 100% 100% 100% 0.013

Chipping & Lifting & Levelling & Preliminary Final Clear


Padding Rigging Grouting Alignment Alignment Punchlist
Progress is
Equipment Tag

updated using
Workpackage
Descriptions

Weight (Ton)
Project Area
Equipment

Weighting

Individual
Man hour

Progress

Progress
data from

Overall
Item

Equipment
No

5% 40% 15% 20% 10% 10%


Tracker Sheet

1 Compressor C01 A WP-M09 20.0 205 0.06 100% 100% 100% 100% 100% 100% 100% 0.057
2 Compressor C02 A WP-M10 20.0 205 0.06 0% 0% 0% 0% 0% 0% 0% 0.000
3 Pump P01 A WP-M11 15.0 150 0.04 100% 100% 100% 100% 100% 100% 100% 0.042
4 Pump P02 A WP-M12 15.0 150 0.04 100% 100% 100% 100% 100% 100% 100% 0.042
5 Pump P03 B WP-M13 15.0 179 0.05 100% 100% 100% 100% 100% 100% 100% 0.050
6 Compressor C03 B WP-M14 18.0 214 0.06 100% 100% 100% 100% 100% 100% 100% 0.060
7 Compressor C04 B WP-M15 18.0 214 0.06 0% 0% 0% 0% 0% 0% 0% 0.000
8 Pump P04 B WP-M16 12.0 143 0.04 100% 100% 100% 100% 100% 100% 100% 0.040
9 Pump P05 B WP-M17 12.0 143 0.04 100% 100% 100% 100% 100% 100% 100% 0.040
8 Pump P06 B WP-M18 14.0 167 0.05 100% 100% 100% 100% 100% 100% 100% 0.046

Progress Summary by Project Area-Equipment Erection


Weighting
Man hour

Progress

Progress
(Tonage)

by Area
Project

Overall
Quantity
Area

A 159 1600 0.44 80% 35.4%


B 168 2000 0.56 89% 49.6%
Total 327 3600 1.00 85.0%

Developed by Toolbox4Planning
Learn more at http://www.toolboxforplanning.com
Progress Updating Section (Static Equipment Group) Progress Calculation Section(Static)

Equipment Project Weight Chipping & Lifting & Alignment & Clear Chipping & Lifting & Alignment & Clear
Item Equipment Descriptions Workpackage Grouting Grouting
Tag No Area (Ton) Padding Rigging Bolting Punchlist Padding Rigging Bolting Punchlist

1 Shell & Tube Exchanger E02 A WP-M01 15 10-Jan-10 15-Jan-10 17-Jan-10 20-Jan-10 22-Jan-10 15 15 15 15 15
2 Shell & Tube Exchanger E03 A WP-M02 12
3 Drum D01 A WP-M03 5 11-Jan-10 16-Jan-10 18-Jan-10 21-Jan-10 23-Jan-10 5 5 5 5 5
4 Tower T10 A WP-M04 57 12-Jan-10 17-Jan-10 19-Jan-10 22-Jan-10 24-Jan-10 57 57 57 57 57
5 Shell & Tube Exchanger E05 B WP-M05 18 13-Jan-10 18-Jan-10 20-Jan-10 23-Jan-10 25-Jan-10 18 18 18 18 18
6 Drum D02 B WP-M06 7 14-Jan-10 19-Jan-10 21-Jan-10 24-Jan-10 26-Jan-10 7 7 7 7 7
7 Tower T20 B WP-M07 50 15-Jan-10 20-Jan-10 22-Jan-10 25-Jan-10 27-Jan-10 50 50 50 50 50
8 Drum D20 B WP-M08 4 16-Jan-10 21-Jan-10 23-Jan-10 26-Jan-10 28-Jan-10 4 4 4 4 4

Progress Updating Section(Rotating Equipment Group) Progress Calculation Section(Rotating)

Equipment Project Weight Chipping & Lifting & Levelling & Preliminary Final Clear Chipping & Lifting & Levelling & Preliminary Final Clear
Item Equipment Descriptions Workpackage
Tag No Area (Ton) Padding Rigging Grouting Alignment Alignment Punchlist Padding Rigging Grouting Alignment Alignment Punchlist

1 Compressor C01 A WP-M09 20 17-Jan-10 19-Jan-10 23-Jan-10 24-Jan-10 26-Jan-10 28-Jan-10 20 20 20 20 20 20


2 Compressor C02 A WP-M10 20 0
3 Pump P01 A WP-M11 15 18-Jan-10 20-Jan-10 24-Jan-10 25-Jan-10 27-Jan-10 29-Jan-10 15 15 15 15 15 15
4 Pump P02 A WP-M12 15 19-Jan-10 21-Jan-10 25-Jan-10 26-Jan-10 28-Jan-10 30-Jan-10 15 15 15 15 15 15
5 Pump P03 B WP-M13 15 20-Jan-10 22-Jan-10 26-Jan-10 27-Jan-10 29-Jan-10 31-Jan-10 15 15 15 15 15 15
6 Compressor C03 B WP-M14 18 21-Jan-10 23-Jan-10 27-Jan-10 28-Jan-10 30-Jan-10 1-Feb-10 18 18 18 18 18 18
7 Compressor C04 B WP-M15 18 0
8 Pump P04 B WP-M16 12 22-Jan-10 24-Jan-10 28-Jan-10 29-Jan-10 31-Jan-10 2-Feb-10 12 12 12 12 12 12
9 Pump P05 B WP-M17 12 23-Jan-10 25-Jan-10 29-Jan-10 30-Jan-10 1-Feb-10 3-Feb-10 12 12 12 12 12 12
10 Pump P06 B WP-M18 14 24-Jan-10 26-Jan-10 30-Jan-10 31-Jan-10 2-Feb-10 4-Feb-10 14 14 14 14 14 14

Equipment Tracker Sheet

Developed by Toolbox4Planning
Learn more at http://www.toolboxforplanning.com

You might also like