CRITICAL PIPING LOOPS FOR SITE INSPECTION BY COMMISSIONING GRO

66 66 66 66 13 62
Sr. SYS SYSTEM DESCRIPTION TEST PACK NO COMMENTS LINE
NO TE WALK
1 M
20 SEPERATION AND STABILIZATION 20.01-GPC-TP01
NO

2 20 SEPERATION AND STABILIZATION 20.01-GPC-TP02 Done


3 20 SEPERATION AND STABILIZATION 20.01-GPC-TP03 Done
4 20 SEPERATION AND STABILIZATION 20.01-GPC-TP07 Only 20" line Done
5 20 SEPERATION AND STABILIZATION 20.01-GPC-TP08 Done

6 20 SEPERATION AND STABILIZATION 20.01-GPC-TP10 UPTO LCV-2603 only Done

7 20 SEPERATION AND STABILIZATION 20.01-GPC-TP11 Done


8 20 SEPERATION AND STABILIZATION 20.01-GPC-TP15 Done
9 23 GAS COMPRESSION 23.01.01-GPC-TP01 Done
10 23 GAS COMPRESSION 23.01.01-GPC-TP03 EXCLUDE CLOSED DRAIN. Done
11 23 GAS COMPRESSION 23.01.01-GPC-TP08 Done
12 23 GAS COMPRESSION 23.01.01-GPC-TP09 Done
13 23 GAS COMPRESSION 23.01.01-GPC-TP12 UPTO COOLER Done
14 23 GAS COMPRESSION 23.01.01-GPC-TP13 Done
15 23 GAS COMPRESSION 23.01.01-GPC-TP14 Done
16 23 GAS COMPRESSION 23.01.01-GPC-TP15 UPTO LCV. EXCLUDE CLOSED DRAIN Done
17 23 GAS COMPRESSION 23.01.01-GPC-TP21 Done
18 23 GAS COMPRESSION 23.01.01-GPC-TP22 UPTO COOLER Done
19 23 GAS COMPRESSION 23.01.01-GPC-TP26 EXCLUDE CLOSED DRAIN Done
20 23 GAS COMPRESSION 23.01.01-GPC-TP31 Done
21 23 GAS COMPRESSION 23.01.01-GPC-TP32 Done
22 23 GAS COMPRESSION 23.01.01-GPC-TP33 Done
23 23 GAS COMPRESSION 23.01.01-GPC-TP34 Done

24 23 GAS COMPRESSION 23.01.01-GPC-TP38 UPTO LCV. EXCLUDE CLOSED DRAIN Done


25 23 GAS COMPRESSION 23.01.01-GPC-TP44 Done
26 23 GAS COMPRESSION 23.01.01-GPC-TP46 UPTO COOLER Done
27 23 GAS COMPRESSION 23.01.01-GPC-TP48 Done
28 23 GAS COMPRESSION 23.01.01-GPC-TP52 EXCLUDE CLOSED DRAIN Done
29 23 GAS COMPRESSION 23.01.01-GPC-TP55 Done
30 23 GAS COMPRESSION 23.01.01-GPC-TP58 Done
31 23 GAS COMPRESSION 23.01.01-GPC-TP59 Done
32 23 GAS COMPRESSION 23.01.01-GPC-TP60 UPTO COOLER Done
33 23 GAS COMPRESSION 23.01.01-GPC-TP63 Done
34 23 GAS COMPRESSION 23.01.01-GPC-TP65 UPTO LCV Done
35 23 GAS COMPRESSION 23.01.01-GPC-TP70 Done
36 23 GAS COMPRESSION 23.01.01-GPC-TP73 Done
37 23 GAS COMPRESSION 23.01.01-GPC-TP74 Done
38 24 GAS TREATMENT 24.01-GPC-TP01 Done
39 24 GAS TREATMENT 24.01-GPC-TP02 Done
40 24 GAS TREATMENT 24.01-GPC-TP03 UPTO LCV. EXCLUDE CLOSED DRAIN Done
41 24 GAS TREATMENT 24.01-GPC-TP09 Done
42 24 GAS TREATMENT 24.01-GPC-TP10
43 30 CRUDE OIL EXPORT 30.01-GPC-TP01 Done

44 30 CRUDE OIL EXPORT 30.01-GPC-TP03 Done

45 30 CRUDE OIL EXPORT 30.01-GPC-TP04 Done


46 30 CRUDE OIL EXPORT 30.01-GPC-TP06 Done
47 30 CRUDE OIL EXPORT 30.01-GPC-TP07 Done
48 45 FUEL GAS 45.01-GPC-TP01 Done
49 45 FUEL GAS 45.01-GPC-TP02 Done
50 45 FUEL GAS 45.01-GPC-TP03 Done
51 45 FUEL GAS 45.01-GPC-TP08 Done

52 45 FUEL GAS 45.01-GPC-TP09 Done

53 46 GAS COMPRESSION 46.01.05-GPC-TP01 Done


54 46 GAS COMPRESSION 46.01.05-GPC-TP02 Done
55 46 GAS COMPRESSION 46.01.05-GPC-TP03 Done
56 46 GAS COMPRESSION 46.01.05-GPC-TP04 Done
57 46 GAS COMPRESSION 46.02.05-GPC-TP05 Done
58 46 GAS COMPRESSION 46.02.05-GPC-TP06 Done
59 46 GAS COMPRESSION 46.02.05-GPC-TP07 Done
60 46 GAS COMPRESSION 46.02.05-GPC-TP08 Done
61 46 GAS COMPRESSION 46.02.05-GPC-TP09 Done
62 55 FUEL GAS 55.01-GPC-TP0 Done
63 55 FUEL GAS 55.04-GPC-TP01 Done

64 55 FUEL GAS 55.04-GPC-TP02 Done

65 55 FUEL GAS 55.07-GPC-TP01


66 55 FUEL GAS 55.07-GPC-TP02
PECTION BY COMMISSIONING GROUP
56 26 33
HYDRO REINST REMARKS
TEST ATEME
NT 3/4" #9000- 8 elbows to be procured by GPC
Proceed with testing without sampling point.
RT cleared. WF for testing.
Done Done
Done
Done valve CH2104 and CH3204 leaking. Proceed with testing without
sampling point.
Done FT2601 size is different. Material delivered. Valve testing balance.

Done Done
Done valves DB2630,DB2627 V2617 leaking
Done V2101 is NA.
Done Done
Done DB2214 valve leaking
Done
Done Pipe gap issue
Done Instrument need to be installed
Done Done
Done GB3201- valve leaking.
Done Done
Done Insulation required and pipe gap is 50mm only.
Done Done
Done V3206 (16" ball valve) passing & V4173 (check valve) Leaking
Done Done
Done SP3301 is leaking, valve testing balance.
Done Valve leaking DB3309 AND GT3304. Gap less than 100mm. Valve
testing balance.
Done Done
Done Done
Done Insulation required, pipe gap less than 50mm.
Done Done
Done Valve DB3625 -not available.
Done Done
Done
Connection with PGC flange mismatch, materail available.
Done
Done welded valves for sampling point. Valve passing/leaking
Done Done
Done Done
Done
flange change- flange delivered on 16-02-2017.
Done Done
Done V2505 is leaking.
Done Done
Done Done
3"-GL-D22-8042 -Materials suplied
Done Sampling point balance for line 6"-1039. valve CH2601 is leaking.

Done Valves CH2701, CH2702 and V2812 are leaking, DB2714- body crack

Done Done
Done Done
Done Valve leaking CH0163 and V2817.
V5309, V5329 Valves are NA.
Done E&I thermowell not suitable to install. Procured coupling flange
Done E&I thermowell not suitable to install. Procured coupling flange
Valve V4022 received RF but required is RTJ type. Flange on spool
need to be changed to RF and same is delivered
Done Valve V4022 received RF but required is RTJ type. Flange on spool
need to be changed to RF and same is delivered
Done Done
Done Done
Done Done
Done Done
Done Done
Done Done
Done Done
Done Done

Done
Done Thermowell not suitable. ABS comment on tubing testing. Expected
modification due to additional PCV.
Done Thermowell not suitable. ABS comment on tubing testing. Expected
modification due to additional PCV.
additional material delivered.
additional material delivered.