Professional Documents
Culture Documents
May 2011
KAZCOPPER
Open Pit Design and Scheduling Study for Benkala
Deposit
CONTENTS
TABLES
FIGURES
1.1 Introduction
The NPV Scheduler programme comprises three components, the ultimate pit shell
generator, a push back generator and the optimising scheduler. The ultimate pit generator
is the first stage of the optimisation process and utilises a Lerchs-Grossman algorithm to
generate an economic open pit shell from the Mineral Resource block model based on the
initial input parameters.
The initial objective of this study was to obtain an optimised pit shell containing
economically viable Mineral Resources, which will form a basis for subsequent open pit mine
design. The Ore Reserve statement will be derived from the mine design applying modifying
factors. The pitshell generated through the design will then be used for the mining
scheduling.
The base case metal price used for the pit optimisation was US$6,000/t Cu. The major Key
Performance Indicators (KPI) such as mining and processing costs, and other parameters,
considered during the optimisation, have been provided by the Client and reviewed by WAI.
A summary of the optimisation parameters is shown in Table 1.1.
One of the most crucial geotechnical parameters is the overall pit slope angle. The shallower
the overall slope angle, the more waste cells that are included in the pit design. This has a
great effect on the stripping ratio and hence economic viability.
WAI was provided with a geotechnical study report produced by Stavrolit LLP. Based on
the information present in the report an overall pit slope angle of 48o was used for the
optimisation and design. It should be noted that WAI was not in a position to review the
report as well as the supporting studies.
Due to lack of metallurgical testwork on primary ores, this type of material was excluded
from optimisation and pit design.
Additional optimisation runs have been performed with Inferred resources enabled and
using a high Cu price (9,000 US$/t) in order to assess the projects exploration potential and
to use the extended pit limits as a guide for surface infrastructure location.
The results of the WAI optimisation as calculated by NPV Scheduler are presented in Table
1.2 below. The Base case optimised pit shell 3D image is shown in Figure 1.1.
Only the Measured and Indicated Mineral Resources were utilised in the optimisation as this
is the only categories of Mineral Resources which can transferred to Ore Reserves and
included into mine production schedule.
Based on the open pit optimisation, WAI has carried out a pit design for Benkala. The main
pit design parameters are given in Table 2.1 below.
A number of trial pit designs have been performed in order to optimise ore tonnages and
stripping ratio. The resulting pit design details are given in Table 2.2, a plan view is shown in
Figure 2.1, whilst a 3D view is shown in Figure 2.2 below.
After the pit has was designed, an evaluation of the pit reserve was been performed (Table
2.3), with details of the ore to waste ratio shown in Table 2.4.
WAI has generated a mining schedule for the designed open pit. The schedule is targeting
full operational capacity of the processing facilities (18,000t Cu per annum) to be met, with
appropriate ramp-up in production during the first two years 3,500t Cu in first year and
9,000t Cu in the second.
The schedule considers a requirement for stripping works at the initial stage of mining and
maintains consistent annual rock tonnages through the life of mine. The overall project
timeframe is likely to be increased considering the availability of primary ores, which
potentially could be treated at the same processing facilities. Table 3.1 below describes the
mining schedule for the designed open pit.
The designed open pit plan, long-section and cross-section are given in Figure 3.1, Figure 3.2
and Figure 3.3 below respectively. All of the pictures are colour-coded by extraction
sequence.
Note: