TRANSLAY S FEEDER UNIT PROTECTION TEST FORM

Substation Name
Substation Number
Circuit

General Data

Current Rating (In) A dc


Auxiliary Supply Voltage Rating (Vx) V
CT Ratio
Trip Supply V dc
Auxiliary Supply V dc
End A
End B

Wiring ( or n/a)

Insulation resistance (see test form ECP 11-0301)

Inter relay and cubicle wiring checked Circuit diagram number..


to: Wiring diagram number..

Physical Inspection ( or n/a)

Relay free from mechanical damage/defects


CT shorting contacts close correctly when relay module withdrawn from case
Removal of plug shorts to N = 6
TRANSLAY S Feeder Unit Protection Test Form Document Number: ECP 11-0311c
Version: 2.0
Date: 12/12/2016

Secondary Injection

Secondary injection with relay and stability resistor set in accordance with GEC publication R-8011.

Calc. Op. Current N Calc. Op. Current


N Plug Phase Operate Plug Operate
Current End A End B Current End A End B

A-N
N3 &
Plug B-N N6
Out
C-N

Pilots

Insulation resistance to earth M


Insulation resistance between pilots M
Loop resistance
Open circuit impedance
Loop impedance

Service Settings

Stability Resistor Ks
Rpp Kt
N

Secondary injection with Pilots at Service Settings

Phase Calculated Operating Current Remote End Operated


Operating
Current End A End B End A End B

A-N
B-N
C-N

UK Power Networks 2017 All rights reserved 2 of 3


TRANSLAY S Feeder Unit Protection Test Form Document Number: ECP 11-0311c
Version: 2.0
Date: 12/12/2016

On-load Tests

End A End B End A End B

A Phase only Pilots Crossed Pilots Normal

B Phase only Pilots Crossed Pilots Normal

C Phase only Pilots Crossed Pilots Normal

A B C N

Primary currents
Relay current end A
Relay current end B
Note, relay current can only be checked where CT test links or MMLG test sockets are fitted.

Comments

Certification ()

All tests have been completed satisfactorily

Contractor Commissioning Engineer (if applicable)

Organisation Name

Date Signature

UK Power Networks Commissioning Engineer

Name Signature Date

UK Power Networks 2017 All rights reserved 3 of 3