Daily Construction Report

Project Name: Jubail Holiday Inn Hotel Date: 15.02.2017 Weather: Heavy Rain
Developer: DUR Hospitality Report No.: 002 Day Wed Wind Speed
Client Representative: Hill International ME (Ltd) Total Project Duration Days: 720 High Temp 24deg.
Supervision Consultant: ASDO Duration Elapsed in Days 720 Low Temp: 9deg.
Contractor: Asmael General Contracting Est. Day Shift R Night Shift Work Stopped:
From: 11:00 To: 16:00

A - Manpower List

S.No Indirect Manpower Total Remarks

1 Steelmen 3

2 Mason 1

3 Unskilled Labor 1

4 Carpenter 2

10

TOTAL INDIRECT MANPOWER 7

B. Equipment and Machinery List


Total Hrs. or Contractor or Effective Total Effective
S.No Equipment Idle Hours Remarks
Site Subcontractor Working Hrs Hrs

1 Mobile Crane 4 Subcontractor 8 8 4


2 Trailer 4 Subcontractor 8 8 4
3

10

11

Page 1 of 2
C) Construction Activities
Summary of completed

Activities
1 Fence Assembly and Installation
2 All Activities were stopped due to heavy rains and strong wind.

On-going Activities

Anticipated Activities Next Day


1 Fence Assembly / Installation
2 Hauling of perimeter fence from Khalidya camp - Al Khobar to Jubail site.
3 Concrete Footing for Consultatnt/Client Temporary Portable Office.
4 Delivery of Portable Offices

Started Activities Today

Remarks

Delivered Materials and Equipment on site

Prepared By Initiated by Contractor Verified by (Engineer) Concurred by (Client)


ACC JM Project Manager

Comments: Date:

Received By :

Page 2 of 2