You are on page 1of 421

ICS 27.

100

F20 DL
Record No.: J902-2009

PROFESSIONAL STANDARD
OF THE PEOPLES REPUBLIC OF CHINA

P DL/T 5210.3-2009

Code for Construction Quality Acceptance


and Evaluation of Electric Power Construct
- Part 3: Turbine Generator Unit

3 :

Issued on July 22, 2009 Implemented on December 1, 2009


Issued by the National Energy Administration of the People's Republic of China
Contents
Foreword ...........................................................................................................................................1
1 Scope...........................................................................................................................................2
2 Normative references ..................................................................................................................2
3 General Provisions ......................................................................................................................2
4 Construction quality acceptance .................................................................................................3
4.1 Requirements for construction quality acceptance...........................................................3
4.2 Division of construction quality acceptance range and general tables.............................5
4.3 General parts of steam turbine generator units...............................................................90
4.4 Steam turbine main body installation...........................................................................116
4.5 Adjustment and lubricating oil system installation ......................................................146
4.6 Generator and exciter installation ................................................................................167
4.7 Assembly and installation of water-cooled condenser .................................................193
4.8 Installation of air-cooling condenser system................................................................198
4.9 Installation of deaerator (water tank) equipment installation.......................................205
4.10 Installation of high- and low-pressure heater .............................................................208
4.11 Installation of bypass system equipment....................................................................209
4.12 Installation of steam feed pump unit ..........................................................................212
4.13 Installation of electrically driven feed pump group ...................................................232
4.14 Installation of condensate pump.................................................................................240
4.15 Installation of desuperheater and decompressor ........................................................242
4.16 Installation of hoisting appliance ...............................................................................243
4.17 Installation of diesel generator ...................................................................................250
4.18 Installation of water circulating pump .......................................................................251
4.19 Rotary sieve installation.............................................................................................263
4.20 Trash remover equipment installation ........................................................................266
4.21 Installation of large-scale flat steel gate .....................................................................269
4.22 Deep water pump installation.....................................................................................270
4.23 Installation of water purifying plant...........................................................................272
4.24 Main body installation of combustion engine ............................................................275
4.25 Combustion engine auxiliary device and accessory machinery installation ..............289
4.26 Construction Identification and approval...................................................................290
5 Construction Quality Evaluation of Single Project .................................................................342
5.1 Basic requirements .......................................................................................................342
5.2 Evaluation provisions...................................................................................................344
5.3 Evaluation content........................................................................................................345
5.4 Evaluation methods......................................................................................................345
5.5 Construction quality evaluation for main body and sub-system of turbine generator..348
5.6 Evaluation on installation and construction quality of accessory machinery and
auxiliary device in main power house...................................................................................356
5.7 Evaluation on Installation and Construction Quality of Accessory Machines and
Auxiliary Equipments outside the Main Building.................................................................363
5.8 Evaluation on Pipe Installation Quality of Steam Turbine...........................................369
5.9 Evaluation on Construction Quality of Steam Turbine Main Body (Including Steam
Feed Pump), Equipment, Pipe Insulation and Paint..............................................................375
5.10 Evaluation on Installation and Construction Quality of Combustion Engine and Its
Auxiliary Equipments and Accessory Machines...................................................................385
5.11 Summarizing of Evaluation Score of Project Position (Scope) of Single Project ......392
5.12 Evaluation Report on the Quality of Single Project ...................................................393
6 Quality Evaluation of Single Unit...........................................................................................394
7 Quality Evaluation of Overall Project.....................................................................................396
Annex A (Informative) Typical Data of Flow Passage Part .......................................................401
Annex B (Informative) Grading Standard of Oil Quality ..........................................................415
Annex C (Normative) Vibration of Accessory Machines ..........................................................417
Annex D (Normative) Centre Alignment of Accessory Machines.............................................418
Foreword
The standard series DL/T 5210 "Code for Construction Quality Acceptance and
Evaluation of Electric Power Construct consists of 8 parts:
DL/T 5210.1 Part 1: civil work
DL/T 5210.2 Part 2: boiler unit
DL/T 5210.3 Part 3: steam turbine generator units
DL/T 5210.4 Part 4: thermal meter and control device
DL/T 5210.5 Part 5: Piping & System
DL/T 5210.6 Part 6: The equipment and the system with the water treatment and
hydrogen generation
DL/T 5210.7 Part 7: welding
DL/T 5210.8 Part 8: Processing preparation
This Part is the third part of DL/T 5210.
This Part is formualted by the National Development and Reform Commission according
to the requirements of the document "announcement on issuing the professional standard
project planning in 2008" (Fagaiban Gongye [2008] No. 1242).
During the darfting process, this Part referrenced "Standard for Quality Inspection and
Evaluation of Thermal Power Construction" (Section of steam turbine) (Dianzong [1998] No.
145) issued by the former Ministry of Power Industry.
Annex A and Annex B are informative.
Annex C and Annex D are normative.
This Part is proposed by the China Electricity Council.
The technical committee for standardization of thermal power construction in power
industry is under the jurisdiction of and in charge of the explanation of this Part.
Chief Drafting Organizations: Zhejiang Province thermal power construction company,
Jiangsu Province Electric power Construction No. 3 Company
Participating organization: Hebei Electrie Power Construction No. 1 Engineering
Corporation, Hunan Thermal Power Construction Company, Shandong Electrie Power
Construction No.1 Engineering Corporation, Shanxi Province Power Company Electrie
Power Construction No. 4 Company.
Chief drafting staffs: Lu Huanhao, Yu Xingmei, Wang Weimin, Fan Youlin, Cheng Xinyu,
Zhu Junmao, Yu Xiaoming, Yang Xiaoming, Xu Yunquan, Guo Zhenying, Liu Xinmin, Li
Wei and Zhang Xinmin.
Upon the issuance, "Standard for Quality Inspection and Evaluation of Thermal Power
Construction" (Section of steam turbine) (Dianzong [1998] No. 145) issued by the former
Ministry of Power Industry go invalid.
During the process of implementing this Part, the relevant opinions and advice, whenever
necessary, can be posted or passed on to the Standardization Center of the China Electricity
Council (No. 1, 2nd lane, Baiguang Road, Beijing 100761).

1
1 Scope
This Part in DL/T 5210 specifies the relevant requirements in construction quality
acceptance standard, quality evalution of single project, quality evalution of single unit, and
quality evalution of overal project of steam turbine generator units in thermal power
generation engineering.
This part is applicable to construction quality acceptance and engineering quality
assessment of new construction, extension and renovation of thermal power generation
project steam turbine generator units with unit capacity of 300MW ~ 1000MW thermal power
generation project and fuel gas - steam combined cycles machine unit. This part can be
referanced for assessment of thermal power generating unit and nuclear power station
conventional Island under 300MW and the BOP engineering.

2 Normative references
For dated reference, subsequent amendments to (excluding corrigenda), or revisions of,
any of these publications do not apply. However, all parties coming to an agreement
according to this standard are encouraged to study whether the latest edition of these
documents is applicable. For undated references, the latest edition of the normative document
is applicable to this standard.
GB/T7596 Quality criteria of turbine oils in service for power plants
GB 50205 50205-2001 Code for Acceptance of Construction Quality of Steel
Structures
GB/T 50375 GB/T 50375-2006 Evaluating standard for excellent quality of building
engineering
DL 5011 DL 5011-1992 The Code of Election and Acceptance for Power Plant
Construction - steam turbine unit part
DL/T5161.1~5161.17 Part 9: Specification for construction quality checkout and
evaluation of electric equipment installation
DL/T 5210.1 Specification for construction quality acceptance and evaluation of
electric power construct Part 1: Civil construction engineering
DL/T869 The Code of the Welding for Power Plant

3 General Provisions
3.0.1 This standard is formualted with a view to intensifying construction engineering
quality control in electric power inducstry, improving construction quality level, and unifying
the relevant requirements in construction quality acceptance standard and evaluation for
thermal power generation engineering.
3.0.2 The construction quality acceptance for thermal power generation project shall be
conducted by inspection lot, subitem project, subsection project, and unit project. the
construction quality acceptance is only applied with a quality grade "qualified"; in case of any
nonconformity, it shall comply with Article 4.1.12 in this Part.
3.0.3 The engineering quality evaluation shall be conducted for the projects with the
"high quality" engineering objective.
3.0.4 The engineering quality evaluation shall be conducted by the three phases (stage)

2
- single project, single unit and overal project.
3.0.5 The construction quality evaluation for single project shall be conducted upon
that the construction quality acceptance for all unit projects is qualified and the collection and
rearrangement of engineering technical document is completed, and the evaluation shall cover
the whole work content before 168-h trial operation with full load.
3.0.6 The quality evalution for single unit shall be con ducted after the construction
quality acceptance for all single projects and the 168-h trial operation of the unit with full
load are completed and the environmental protection projects suppoted are normally put into
operation. the synergic system shall be bought into the evaluation for the first unit.
3.0.7 The quality evalution for overal project shall be conducted after the quality
evalution for all single units, the performance tests of the units and the engineering archives
evaluation are completed.

4 Construction quality acceptance


4.1 Requirements for construction quality acceptance
4.1.1 The inspection, acceptance and acceptance confirmation and signature for steam
turbine generator units shall be conducted according to the requirements of this Part.
4.1.2 For the inspection and acceptance for the project construction quality, the
construction organization shall prepare the quality acceptance range division table on the base
of the works scope according to the requirements of Chapter 4 in this Part; thes upervision
organization shall conduct the examination and the parties of construction, supervision and
construction organization jointly sign and seal for approal after the construction organization
make a confirmation. For the engineering projects with engineering general contract or
construction project management (mode), the construction organization may, according to the
actual situation, add acceptance organizations in column "acceptance organization" in the
construction quality acceptance range division table; if the design organization and the
equipment manufacture organization in column "acceptance organization" participate in the
quality acceptance, the construction organization may make proper adjustment according to
the actual situation.
4.1.3 As for the discrepancy between inspection items and engineering inspection items
in "construction quality acceptance range division table ", matters can be added and deleted.
As for the project number in thix process, continunance and vacant are acceptable, but not the
alteration of the original number.
4.1.4 Engineering construction quality acceptance shall be carried out by the
acceptance organizationsacceptance organization stipulated in "construction quality
acceptance range division table". Acceptance of inspection lot, subentry project and
subsection project shall be carried out by the supervision organizations if they participate.
unit project acceptance shall be organized by development organiztions and participated by
coherent units; design organizations and manufacturing organizations shall participate in the
acceptance of related items in accordance with "construction quality acceptance range
division table". Quality acceptance personnel shall hold the qualification certificate consistent
with the profession which shall be within the validity period. Acceptance authority related to
unit project, subsection project, subentry project and inspection lot shall be confirmed by
the coherent units organized by development organiztion.

3
4.1.5 Apart from strictly implement provisions, the quality inspection personnel at
all-level shall be in accordance current national standard, professional
standard,contract,design document and manufacturing technology document.
4.1.6 The quality acceptance must be conducted after the construction project is
completed. the construction organization shall apply the quality acceptance ro the project
supervision and the development organization upon the construction organization has done
self-checking and prepared complete selfchecking records.
4.1.7 The construction organization shall notify the supervision organization and the
organizations concerned to conduct witness acceptance before being concealed, and complete
the inspection acceptance record and the confirmation and signature.
4.1.8 The appearance quality of unit projects shall be inspected by the quality
inspection personnel with visual observation, feeling or necessary measurement, and
confirmed and singed according to the overall condition of the inspected project .
4.1.9 The inspection and acceptance of project construction quality shall comply with
the requirements in Chapter 4 of this Part and be conducted by inspection lot, subitem project,
subsection project and unit project; where a unit project is constructed by multiple
construction organizations by sections, subunit projects may be set up. the subunit project
number is the original unit project number affixed with english letters for distinguishing.
4.1.10 The acceptance for construction quality shall be conducted only upon the
acceptance for inspection lots is qualified; the acceptance for subsection project shall be
conducted only upon the acceptance for subitem projects is qualified; the acceptance for unit
project shall be conducted only upon the acceptance for subsection projects is qualified.
4.1.11 The "qualified" construction quality acceptance for inspection lot, subitem
project, subsection project and unit project shall meet the following requirements:
1 The complete inspection is conducted for the inspection items according to the
requirements on inspection lots and subitem projects, and the inspection results meet the
quality quality criteria; the quality acceptance for this inspection lot or subitem project is
qualified.
2 The acceptance for the inspection lots cotnained in a subitem project is qualified and
the data for the subitem project is compelte; the quality acceptance for this subitem project is
qualified.
3 The acceptance for the subitem projects cotnained in a subsection project is qualified
and the data for the subsection project is compelte; the quality acceptance for this subsection
project is qualified.
4 The acceptance for the subitem projects cotnained in a subsection project is qualified
and the data for the subsection project is compelte; the quality acceptance for this subsection
project is qualified.
4.1.12 The nonconformity of construction quality, if existing, shall be registered for
record and treated according to the following requirements:
1 The inspection items for reworked ones, or replaed instrument or equipment, shall be
conducted again. .
2 The inspection items repaied, which satisfy the functional requirements of safe
handling, may be inspected according to the technology processing scheme and the negotiated
document.

4
3 As for the unaccepted project for rework or back repair, certifying agency or coherent
units shall carry out appraisal and make concessional treatment of the project not affecting the
inner quality, service life, use function and safe operation. . Secondary acceptance will not be
carried out to project after concessional treatment. However, this shall be indicated in
"acceptance conclusion". The written report thereof shall be attached to the acceptance table.
4.1.13 The construction quality of inspection lot and subitem project under one of the
following conditions shall not be inspected:
1 The inspection results of its dominant inspection items cannot meet the quality
criteria.
2 Design and manufacturer maintains data requirements for quality criteria, but there is
no measuring data in the inspection result column. .
3 Quality acceptance documents do not conform to records management regulation.
4.1.14 As for quality question problems caused by design or equipment manufacture, the
design or equipment manufacture units shall be responsible for the disposal. After the
entrusted on-site disposal by construction organization, if specific non- dominant items cannot
fully meet standard requirements, upon the written signature by development organiztion,
design organization, supervision organization and construction organization, the concessional
treatment can be made. Secondary acceptance will not be carried out to project undergone
concessional treatment. But it shall be noted in acceptance result and the written report shall
be attached after the acceptance table.
4.1.15 The quality acceptance documents for inspection lot, subitem project, subsection
project and unit project shall be of accurate data, complete document collection, and complete
signature procedure; and the material and handwriting for document preparation shall meet
the requirements of "durability" and the records management specifications.
4.2 Division of construction quality acceptance range and general tables
4.2.1 Quality acceptance shall be classified according to inspection lot, subentry project,
subsection project and unit project, which shall also be in accordance with those specified in
Table 4.2.1.
Table 4.2.1 Construction quality acceptance range division table
Construction number Acceptance organization
Number
Subite Constructi Supervisi Manufactur Developm
Unit Subsecti Propert Design of quality
m Inspecti Project name on on ing ent
proje on y organizati acceptanc
projec on lot organizati organizati organizatio organiztio
ct project on e table
t on on n n

01 Main body
installation
Domin
engineering of
ant
turbine
generators

01

Foundation
preparation
and iron
gasket (block)
5
configuration
before
installation of
turbine
generators

01 Foundation
preparation of Domin

turbine ant
generators

Foundation
check and
Domin Table 4.3.
01 geometric
ant 1
dimension
checking

Foundation
Domin Table 4.3.
02 settlement
ant 13
observation

Foundation
Table 4.3.
03 bearing area
2
roughening

Baseplate
grouting inner Table 4.3.
04
baffle 3
installation

Foundation
Table 4.3.
05 bolt
4
examination

02 Turbine
generators
foundation
iron gasket
(filling block)
preparation
installation

Iron gasket Table 4.3.


01
preparation 5

Iron gasket Domin Table 4.3.


02
installation ant 6

Concrete block Domin Table 4.3.


03
preparation ant 7

Adjustable
Domin Table 4.3.
04 fixer
ant 8
installation

05 Pedestal Table 4.3.


adjusting 9
6
screw
installation

02 Main body
Domin
installation of
ant
steam turbine

01 Pedesta check
Domin
and
ant
installation

Bearing seat
pedestal check domina Table 4.3.
01
and nt 10
installation

Low pressure
cylinder
domina Table 4.3.
02 pedestal check
nt 10
and
installation

02 Bearing seat
( box ) and

bearing bush
check

Bearing seat
domina Table 4.3.
01 ( box ) clean
nt 14
and check

Bearing bush domina Table 4.3.


02
check nt 15

Bearing bush
Table 4.3.
03 filling block
16
check

03 Installation of
bearing seat domina

(box ) and nt
bearing bush

Bearing seat
Table
01 positioning
4.4.1-1
and centering

Clearance
measurement
and domina Table
02
adjustment of nt 4.4.1-2
bearing bush
and oil catch

03 Clearance domina Table


measurement nt 4.4.1-3
7
and
adjustment of
thrust bearing

Bearing seat Table


04
covering 4.4.1-4

04 cleaning and
check of steam
cylindr and

cylinder
internal
component

Cleaning and
check of low Table
01
pressure 4.4.2-1
cylinder

Cleaning and
check of high
and Table
02
intermediate 4.4.2-2
pressure
cylinder

Cleaning and
check of high
and medium Table
03
pressure inner 4.4.2-3
cylinder steam
inlet pipe

Check of high
and medium
pressure
cylinder Table
04
nozzle box, 4.4.24
parting sheet
(suit), steam
seal (suit)

Check of low
pressure
cylinder
admission
Table
05 chamber,
4.4.2-5
parting
sheet(suit) and
steam seal
(suit)

8
High and
medium
pressure
cylinder Table 4.3.
06
component 17
spectrum and
hardness
recheck

low pressure
cylinder
component Table 4.3.
07
spectrum and 17
hardness
recheck

05 check of

turbinr rotor

High and
medium Table
01
pressure rotor 4.4.3
check

Low pressure Table


02
rotor check 4.4.3

06 Steam cylindr
combination
positioning

Low pressure
cylinder
combination, Table
01
joint surface 4.4.4-1
clearance
inspection

Clearance
inspection of
high and
Table
02 medium
4.4.4-2
pressure
cylinder joint
surface

Positioning
and centering
Table
03 of low
4.4.4-3
pressure
cylinder

04 Positioning Table

9
and centering 4.4.4-3
of high and
medium
pressure
cylinder

07 Aggregate
installation of
domina
steam cylindr
nt
internal
component

Centre
alignment of
Table
01 bearing seat,
4.4.5-1
steam cylindr
and rotor

Installation of
Table
02 low pressure
4.4.5-2
inner cylinder

Inner cylinder
installation of
Table
03 high and
4.4.5-3
medium
pressure

High pressure
Table
04 nozzle box
4.4.5-4
installation

Installation of
high and
medium
pressure
cylinder
parting sheet domina Table
05
(suit), balance nt 4.4.5-5
piston ( loop ),
steam
admission
shunt ring and
gland sleeve

06 Installation of Table
low pressure 4.4.5-6
cylinder
parting sheet
(suit), balance 10
piston ( loop ),
steam
admission
shunt ring and
gland sleeve

Low pressure
cylinder
internal Table
07
component 4.4.5-7
bore centre
align

High and
medium
pressure
cylinder Table
08
internal 4.4.5-8
component
bore centre
align

08 Steam cylindr
domina
load
nt
distribution

Steam cylindr
domina Table
01 load
nt 4.4.6
distribution

09 Flow passage
clearance domina

measurement nt
adjustment

Low pressure
cylinder flow
passage domina Table
01
clearance nt 4.4.7
measurement
adjustment

High and
medium
pressure
cylinder flow domina Table
02
passage nt 4.4.7
clearance
measurement
adjustment

10
Labyrinth domina
clearance nt
11
measurement
adjustment

Low pressure
cylinder
labyrinth domina Table
01
clearance nt 4.4.8
measurement
adjustment

High and
medium
pressure
cylinder domina Table
02
labyrinth nt 4.4.8
clearance
measurement
adjustment

11 Steam turbine domina



covering nt

Check before
domina Table
01 steam turbine
nt 4.4.9-1
covering

Steam turbine domina Table


02
covering nt 4.4.9-2

12 Shafting
domina
adjustment
nt
and connection

Coupling
centre align
domina Table
01 before steam
nt 4.4.10-1
turbine
covering

Coupling
centre align
domina Table
02 after steam
nt 4.4.10-1
turbine
covering

Coupling
centre align domina Table
03
before reaming nt 4.4.10-1
connection

Coupling
domina Table
04 reaming
nt 4.4.10-2
connection

12
13 Turbine
generators
domina
foundation
nt
secondary
pouring

Check before
foundation Table 4.3.
01
secondary 11
pouring

Foundation
secondary domina Table 4.3.
02
pouring and nt 12
maintenance

14 Sliding pin
system
clearance
measurement,
adjustment

Sliding pin
system
domina Table
01 clearance
nt 4.4.11-1
measurement,
adjustment

Center beam
installation
between Table
02
bearing seat 4.4.11-2
and steam
cylindr

Installation of
Table
03 push and pull
4.4.11-3
device

15 Turning gear
check and
installation

Turning gear Table


01
clearing check 4.4.12-1

Turning gear Table


02
assembling 4.4.12-2

16 Medium and
low pressure
communicatin
g pipe
installation

13
Medium and
low pressure
domina Table
01 communicatin
nt 4.4.13
g pipe
installation

17 Check before
steam turbine
thermal
insulation and
decorative
sheet
installation

Check before
steam turbine
thermal
Table
01 insulation and
4.4.14
decorative
sheet
installation

03 01 Adjustment
and lubricating
domina
oil system
nt
equipment
installation

Valve and
governing domina

valve nt
installation

Valve and
governing Table 4.5.
01
valve cleaning 1-1
and check

Valve and
governing domina Table 4.5.
02
valve nt 1-2
installation

02 Installation of
domina
actuating
nt
mechanism

Installation of
domina Table 4.5.
01 actuating
nt 2
mechanism

03
Installation of domina
protective nt
14
device

Emergency
domina Table 4.5.
01 governor
nt 3-1
installation

Emergency
domina Table 4.5.
02 trip throttle
nt 3-2
installation

Emergency
domina Table 4.5.
03 trip device
nt 3-3
installation

Other security
operating Table 4.5.
04
equipment 3-4
installation

04 Main oil pump



installation

Main oil pump domina Table 4.5.


01
installation nt 4

05 Fire resistant
fluid system domina

and piping nt
installation

Integrated
fire-resistant
Table 4.3.
01 oil feeding
33
device
installation

Installation of
fireresistant oil
box, oil
domina Table 4.5.
02 poump, oil
nt 5-1
cooler,oil filter
and
accumulator

Fire resistant
oil system Table 4.5.
03
piping 5-2
installation

Fire resistant
domina Table 4.5.
04 oil system
nt 5-3
cycle flushing

06
Lubricating oil domina
system nt

15
equipment and
piping
installation

Integrated oil
domina Table 4.5.
01 tank
nt 6-1
installation

Lubricating oil
Table 4.5.
02 cooler
6-2
installation

Oil filter Table 4.5.


03
installation 6-3

Oil poump Table 4.5.


04 check and 6-4 Table
installation 4.5. 6-5

Oil poump domina Table 4.5.


05
trial run nt 6-6

Table 4.3.
Installation of
30
06 smoke exhaust
Table 4.3.
fan
31

Oil ejector or
oil worm Table 4.5.
07
wheel pump 6-7
installation

Oil purifier Table 4.5.


08
installation 6-8

Jacking oil
Table 4.5.
09 piping
6-9
installation

Lubricating
Table 4.5.
10 pipe
6-9
installation

Lubricating oil
domina Table 4.5.
11 system cycle
nt 6-10
flushing

04 Generator and
domina
exciter
nt
installation

01 Pedestal

positioning

Pedestal Table 4.6.


01
positioning 1

02
Generator domina

16
rotor check nt

Generator domina Table 4.6.


01
rotor check nt 2-1

Rotor domina Table 4.6.


02
tightness test nt 2-2

03 Stator hoisting
domina
positioning
nt
check

Stator hoisting
domina Table 4.6.
01 positioning
nt 3
check

04 Stator domina

tightness test nt

Stator domina Table 4.6.


01
tightness test nt 4

05 Insertion of domina

generator rotor nt

insertion of domina Table 4.6.


01
generator rotor nt 5

06 Inlet and outlet


domina
water pedestal
nt
mounting

Inlet and outlet


Table 4.6.
01 water pedestal
6
mounting

07 Generator end
domina
cap bearing
nt
installation

Generator end
domina Table 4.6.
01 cap bearing
nt 7
installation

08 Adjustment of
air gap and domina

magnetic force nt
center

Adjustment of
air gap and domina Table 4.6.
01
magnetic force nt 8
center

09 Fan gap

adjustment

Fan gap Table 4.6.


01
adjustment 9

17
10 Sealing pad domina

installation nt

Sealing pad domina Table 4.6.


01
installation nt 10

11 Steam turbine
- generator domina

coupling nt
centre align

Steam turbine
- generator domina Table 4.6.
01
coupling nt 11
centre align

Coupling
domina Table
02 reaming
nt 4.4.10-2
connection

12 Generator oil
catch
installation

Generator oil
Table 4.6.
01 catch
12
installation

13 Installation of
seal of domina

generator end nt
cap

Installation of
seal of domina Table 4.6.
01
generator end nt 13
cap

14 Installation of
domina
hydrogen
nt
cooler

Installation of
domina Table 4.6.
01 hydrogen
nt 14
cooler

15 Exciter domina

installation nt

Stator and Table 4.6.


01
rotor check 15-1

Bearing Table 4.6.


02
installation 15-2

03 Exciter domina Table 4.6.


coupling nt 15-3

18
centre align

Pedestal dowel
pin and outer Table 4.6.
04
cover 15-4
installation

Adjustment of
air gap and domina Table 4.6.
05
magnetic force nt 15-5
center

Adjustment of
gap among Table 4.6.
06
fan, air damper 15-6
and oil catch

Air cooler Table 4.6.


07
installation 15-7

16 Carbon brush
yoke
installation

Carbon brush
Table 4.6.
01 yoke
16
installation

17 Air pressure
test of whole domina

set of nt
generator

Air pressure
test of whole domina Table 4.6.
01
set of nt 17
generator

18 Sealing oil
system device

and piping
installation

Integrated
sealing oil Table 4.3.
01
device 33
installation

Sealing oil
Table 4.5.
02 cooler
6-2
installation

03 Screw rod Table 4.6.


sealing oil 18-1
poump

19
installation

Other
Table 4.6.
04 equipments
18-2
installation

Sealing oil
Table 4.5.
05 piping
6-9
installation

Sealing oil
domina Table 4.5.
06 system
nt 6-10
washing

19 Internal
cooling water
system

equipment and
piping
installation

Integrated
internal
Table 4.3.
01 cooling water
33
device
installation

Internal
cooling water Table 4.6.
02
pump 19-1
installation

Installation of
cooling water
Table 4.6.
03 tank, cooler
19-2
and ion
exchanger

Internal
cooling water Table 4.6.
04
conduit 19-3
installation

Internal
cooling water domina Table 4.6.
05
system nt 19-4
flashing

20 Gas system
equipment and

piping
installation

01 Installing Table 4.6.

20
equipment 20-1

Gas pipeline Table 4.6.


02
installation 20-2

Gas pipeline
Table 4.6.
03 gas pressure
20-3
test

02 Turbine
generator
auxiliary
device
installation

01 Water-cooled
condenser domina

aggregate nt
installation

01 Condenser
domina
shell
nt
combination

Condenser
domina Table 4.7.
01 shell
nt 1-1
combination

02 Condenser
positioning
and centering

Condenser
Table 4.7.
01 positioning
1-2
and centering

03 Condenser
cooling tube domina

bundle nt
installation

Condenser
cooling tube domina Table 4.7.
01
bundle nt 2
installation

04 Condenser and
steam cylindr domina

connection and nt
tightness test

Condenser and
steam cylindr domina Table 4.7.
01
connection and nt 3
tightness test

21
05 Condenser
accessory
installation
and secondary
pouring

Condenser
accessory
Table 4.7.
01 installation
4
and secondary
pouring

06 Condenser
cleaning

equipment
installation

Condenser
Table 4.3.
01 scavenging
24
pump check

Condenser
Table 4.3.
02 cleaning pump
25
installation

Condenser
domina Table 4.3.
03 cleaning pump
nt 26
trial operation

Check and
installation of
Table 4.7.
04 rubber ball
5
cleaning
system

02 Air cooling
condenser

system
installation

01 Air cooling
steel structure
installation

Scribing line Table 4.8.


01
for base 1-1

Steel member Table 4.8.


02
pre-assembly 1-2

Bracing steel
domina Table 4.8.
03 structure
nt 1-3
installation

04 Bracing steel domina Table 4.8.


structure nt 1.4
22
high-strength
bolt
connection

Fan bridge
framework and
Table 4.8.
05 platform cover
1-5
plate
installation

Tube bundle
bracing Type A domina Table 4.8.
06
frame nt 1-6
installation

Air stopping Table 4.8.


07
installation 1-7

Platform,
ladder and
Table 4.3.
08 handrail
37
aggregate
installation

02 Air cooling
condenser fan
installation

Air cooling
Table 4.8.
01 condenser fan
2
installation

03 Exhaust
equipment

aggregate
installation

Exhaust
Table 4.7.
01 equipment
1-1
combination

Exhaust
equipment Table 4.7.
02
positioning 1-2
and centering

Exhaust
equipment and
Table 4.7.
03 steam cylindr
3
connection and
tightness test

04 Exhaust Table 4.7.


equipment 4
accessory
23
installation
and secondary
pouring

04 Air cooling
flushing water

pump
installation

Flushing water Table 4.3.


01
pump check 24

Installation of
Table 4.3.
02 flushing water
25
pump

Trial run of
domina Table 4.3.
03 flushing water
nt 26
pump

05 Exhaust
equipment hot
domina
well drainage
nt
pump
installation

Exhaust
equipment hot Table 4.3.
01
well drainage 24
pump check

Exhaust
equipment hot
Table 4.3.
02 well drainage
25
pump
installation

Exhaust
equipment hot domina Table 4.3.
03
well drainage nt 26
pump trial run

06 Vacuum
deaerator
installation

Installation of
Table 4.9.
01 deaerator main
1
body

Installation of
Table 4.9.
02 deaerator
2
accessory

07
Installation of domina
condenser pipe nt
24
bundle and
washing
device

Installation of
condenser pipe
domina Table 4.8.
01 bundle and
nt 3
washing
device

08 Electric hoist
check, domina

installation nt
and load test

Electric hoist
domina Table
01 check,
nt 4.16. 2-1
installation

Electric hoist domina Table


02
load test nt 4.16. 2-2

09 Aircooling
domina
system
nt
tightness test

Aircooling
domina Table 4.8.
01 system
nt 4
tightness test

03 01 Deaerator
( water tank ) domina

equipment nt
installation

Deaerator
( water tank ) domina Table 4.9.
01
main body nt 1
installation

02 Deaerator
( water tank )

accessory
installation

Deaerator
(water tank) Table 4.9.
01
accessory 2
installation

03

Installation of
deaerator
(water tank)
platform,
25
ladder and
handrail

Installation of
deaerator
(water tank) Table 4.3.
01
platform, 37
ladder and
handrail

04 High pressure
heater check domina

and nt
installation

01 High pressure

heater check

High pressure domina Table


01
heater check nt 4.10.1

02 High pressure
heater
installation

High pressure
Table 4.3.
01 heater
35
installation

05 Low pressure
heater check domina

and nt
installation

01 Low pressure

heater check

Low pressure domina Table


01
heater check nt 4.10.1

02 Low pressure
heater
installation

Low pressure
Table 4.3.
01 heater
35
installation

06 Gland heater
check and
installation

01 Gland heater

check

Gland heater Table 4.3.


01
check 34

02
Gland heater

26
installation

Gland heater Table 4.3.


01
installation 35

07 Turbine hall
drain flash

tank
installation

01 Turbine hall
drain flash

tank
installation

Turbine hall
drain flash Table 4.3.
01
tank 36
installation

08 Installation of
other heat
exchanger

01 Installation of
other heat
exchanger

Heat
Table 4.3.
01 exchanger
34
check

Heat
Table 4.3.
02 exchanger
35
installation

09 Bypass system
equipment

inspection
installation

01 High pressure
bypass system
equipment
inspection
installation

High pressure
bypass system
Table
01 equipment
4.11.1
inspection
installation

02
Low pressure
bypass system

27
equipment
inspection
installation

Low pressure
bypass system
Table
01 equipment
4.11.2
inspection
installation

03 Installation of
steam
discharge

device
accessing into
condenser

Installation of
steam
discharge Table
01
device 4.11.3
accessing into
condenser

04 Installation of
bypass oil
system

Hydraulic
pressure
bypass set oil Table 4.5.
01
system 5-1
equipment
installation

Hydraulic
pressure
bypass set oil Table 4.5.
02
system 5-2
pipeline
installation

Hydraulic
pressure
domina Table 4.5.
03 bypass set oil
nt 5-3
system
flashing

03

Turbine
generator
accessory
machinery 28
installation

01 01 Steam feed
domina
pump set
nt
installation

Foundation
preparation,
iron gasket

and stone bolt
preparation
installation

Foundation
preparation,
iron gasket Table
01
and stone bolt 4.12.1
preparation
installation

02 Pedestal
grinding and
positioning

Pedestal
Table
01 grinding and
4.12.2
positioning

03 Bearing
( seat ) and oil
catch check

Bearing (seat)
Table
01 and oil catch
4.12.3
check

04 Steam cylindr
combination,

check,
positioning

Steam cylindr
combination, Table
01
check, 4.12.4
positioning

05 Rotor
positioning
centre align

01 Rotor
Table
positioning
4.12.5
centre align

06 Diaphragm

29
gland
installation

01 Diaphragm
Table
gland
4.12.6
installation

07 Flow passage domina


part clearance nt
measurement,

adjustment
and thrust disc
orientation

01 Flow passage domina


part clearance nt
measurement, Table

adjustment 4.12.7
and thrust disc
orientation

08 Driving steam domina


turbine nt
covering

01 Driving steam domina


Table
turbine nt
4.12.8
covering

09 Bearing (seat)
covering and
rotor turning
gear
installation

01 Bearing (seat)
covering and
Table
rotor turning
4.12.9
gear
installation

10 Control and domina


protection nt
system check
and
installation

01 Control and domina


protection nt
Table
system check
4.12.10
and
installation

11 Lubricating oil

30
system
installation

01 Lubricating oil
Table
system
4.12.11
installation

12 Oil system domina



flashing nt

01 Oil system domina Table 4.5.



flashing nt 6-10

13 Driving steam domina


turbine trial nt
run

01 Driving steam domina


Table
turbine trial nt
4.12.12
run

14 Steam feed domina


pump nt
installation

01 Steam feed domina


Table
pump nt
4.12.13
installation

15 Steam feed domina


pump set nt

secondary
pouring

01 Steam feed domina


pump set nt Table 4.3.

secondary 20
pouring

16 Steam feed domina


pump set nt

centre align
and connection

01 Steam feed domina


pump set nt Table

centre align 4.12.14
and connection

17 Steam feed domina



pump trial run nt

01 Steam feed domina Table



pump trial run nt 4.12.15

02 Electrically domina
driven feed nt

31
pump group
installation

01 Electrically domina
driven feed nt
pump check

01 Electrically domina
Table
driven feed nt
4.13. 1
pump check

02 Motor check

01 Motor check Table



4.13. 2

03 Electrically domina
driven feed nt

pump group
installation

01 Electrically domina
driven feed nt Table

pump group 4.13. 3
installation

04 Electrically domina
driven feed nt
pump group
coupling
centre align

01 Electrically domina
driven feed nt
Table
pump group
4.12.14
coupling
centre align

05 Electrically domina
driven feed nt
pump group
secondary
pouring

01 Electrically domina
driven feed nt
Table 4.3.
pump group
20
secondary
pouring

06 Electrically
driven feed
pump oil
system

32
installation

01 Electrically
driven feed
Table
pump oil
4.13. 4
system
installation

07 Electrically domina
driven feed nt
pump oil
system
flashing

01 Electrically domina
driven feed nt
Table 4.5.
pump oil
6-10
system
flashing

08 Electrically domina
driven feed nt

pump group
trial run

01 Electrically domina
driven feed nt Table

pump group 4.13. 5
trial run

03 01 Feed pump domina


booster pump nt
installation

Booster pump

check

01 Booster pump Table 4.3.



check 24

02 Booster pump

installation

01 Booster pump Table 4.3.



installation 25

03 Booster pump domina



trial run nt

01 Booster pump domina Table 4.3.



trial run nt 26

04 Condensate domina
pump nt
installation

01 Condensate

33
pump check

01 Condensate Table

pump check 4.14.1

02 Condensate
pump
installation

01 Condensate
Table
pump
4.14.2
installation

03 Condensate domina

pump trial run nt

01 Condensate domina Table



pump trial run nt 4.14.3

05 Water ring
vacuum pump
installation

01 Installation of

vacuum pump

01 Installation of Table 4.3.



vacuum pump 25

02 Vacuum pump domina



trial run nt

01 Vacuum pump domina Table 4.3.



trial run nt 26

06 Gland heater
air exhauster
installation

01 Gland heater
air exhauster

check and
installation

01 Gland heater
air exhauster Table 4.3.

check and 30
installation

02 7 Gland heater domina


air exhauster nt
trial run

01 Gland heater domina


Table 4.3.
air exhauster nt
31
trial run

07 Low pressure
heater

34
drainage pump
installation

01 Low pressure
heater

drainage pump
check

01 Low pressure
heater Table 4.3.

drainage pump 24
check

02 Low pressure
heater

drainage pump
installation

01 Low pressure
heater Table 4.3.

drainage pump 25
installation

03 Low pressure domina


heater nt

drainage pump
trial run

01 Low pressure domina


heater nt Table 4.3.

drainage pump 26
trial run

04 Installation of
other
equipments

including
steam turbine
generator units

01 House service
pump
installation

01 House service

pump check

01 House service Table 4.3.



pump check 24

02 House service
pump
installation

01 House service
pump Table 4.3.
25
35
installation

03 House service domina



pump trial run nt

01 House service domina Table 4.3.



pump trial run nt 26

02 Installation of
raw water
pump

01 Raw water

pump check

01 Raw water Table 4.3.



pump check 24

02 Installation of
raw water
pump

01 Installation of
Table 4.3.
raw water
25
pump

03 Raw water domina



pump test run nt

01 Raw water domina Table 4.3.



pump test run nt 26

03 Condensate
make-up pump
installation

01 Condensate
make-up pump
check

01 Condensate
Table 4.3.
make-up pump
24
check

02 Condensate
make-up pump
installation

01 Condensate
Table 4.3.
make-up pump
25
installation

03 Condensate domina
make-up pump nt
trial run

01 Condensate domina
Table 4.3.
make-up pump nt
26
trial run

36
04 Deaerator
recirculating

pump
installation

01 Deaerator
recirculating

pump
installation

01 Deaerator
recirculating Table 4.3.

pump 24
installation

02 Deaerator
recirculating

pump
installation

01 Deaerator
recirculating Table 4.3.

pump 25
installation

03 Deaerator
domina
recirculating
nt
pump trial run

01 Deaerator
domina Table 4.3.
recirculating
nt 26
pump trial run

05 Other
equipment
installation

01 Steam turbine
oil
replenishment
tank
installation

01 Steam turbine
oil
Table 4.3.
replenishment
36
tank
installation

02 Auxiliary
steam headder
installation

01
Auxiliary Table 4.3.
steam headder 36
37
installation

03 Makeup water
tank
installation

01 Makeup water
Table 4.3.
tank
36
installation

04 Desuperheater
and

decompressor
installation

01 Desuperheater
and Table

decompressor 4.15
installation

05 Raw water
heater
installation

01 Raw water Table 4.3.



heater check 34

02 Raw water
Table 4.3.
heater
35
installation

06 Turbine hall
internal
recycling
pump
installation

01 Turbine hall
water

circulating
pump check

01 Turbine hall
water Table 4.3.

circulating 27
pump check

02 Turbine hall
water
domina
circulating
nt
pump
installation

01
Turbine hall domina Table 4.3.
water nt 28

38
circulating
pump
installation

03 Turbine hall
water
circulating

pump oil
piping
installment

01 Turbine hall
water
circulating Table

pump oil 4.18. 4
piping
installment

04 Turbine hall
water
domina
circulating
nt
pump trial
shipment

01 Turbine hall
water
domina Table 4.3.
circulating
nt 29
pump trial
shipment

07 Open
circulation
chilled wated
plant
installment

01 Open
circulation
cooling water
pump
examination

01 Open
circulation
Table 4.3.
cooling water
24
pump
examination

02

Open
circulation
cooling water
pump 39
installment

01 Open
circulation
Table 4.3.
cooling water
25
pump
installment

03 Open
circulation
domina
cooling water
nt
pump trial
shipment

01 Open
circulation
domina Table 4.3.
cooling water
nt 26
pump trial
shipment

04 Water filter

installment

01 Water filter Table 4.3.



installment 36

08 Closed cycle

cooling pump

01 Closed cycle
cooling pump
check

01 Closed cycle
Table 4.3.
cooling pump
24
check

02 Closed cycle
cooling pump
installation

01 Closed cycle
Table 4.3.
cooling pump
25
installation

03 Closed cycle
domina
cooling pump
nt
trial shipment

01 Closed cycle
domina Table 4.3.
cooling pump
nt 26
trial shipment

09

Closed
circulating
water cooler
40
adjustment

01 Closed
circulating

water cooler
examination

01 Closed
circulating Table 4.3.

water cooler 34
examination

02 Closed
circulating

water cooler
installation

02 Closed
circulating Table 4.3.

water cooler 35
installation

10 Turbine hall
dredge pump
installation

01 Turbine hall
dredge pump
check

01 Turbine hall
Table 4.3.
dredge pump
24
check

11 02 Turbine hall
dredge pump
installation

01 Turbine hall
Table 4.3.
dredge pump
25
installation

03 Turbine hall
domina
dredge pump
nt
trial run

01 Turbine hall
domina Table 4.3.
dredge pump
nt 26
trial run

12 Turbine hall
domina
crane
nt
installation

01 Bridge crane

installation

41
01 Bridge rail domina Table

check nt 4.16. 1-1

02 Bridge crane
Table
aggregate
4.16. 1-2
installation

03 Bridge crane
rotating
Table
machine check
4.16. 1-3
and
installation

04 Bridge crane domina Table



load test nt 4.16. 1-4

02 Other crane

installation

01 Crane Table

installation 4.16. 2-1

02 Cargo Table

handling test 4.16. 2-2

13 Heating
network
system
equipment
installation

01 Heating
network pump
installation

Heating
Table 4.3.
01 network pump
24
check

Heating
Table 4.3.
02 network pump
25
installation

Heating
domina Table 4.3.
03 network pump
nt 26
trial run

02 Installation of
the heaters in

heating
network

Heating
Table 4.3.
01 network heater
34
check

02 Installation of Table 4.3.

42
heater for 35
heating
network

14 Installation of
shutdown

cooling water
pump

01 Check of
shutdown

cooling water
pump

Check of
shutdown Table 4.3.
01
cooling water 24
pump

02 Shutdown
cooling water

pump
installation

Shutdown
cooling water Table 4.3.
01
pump 25
installation

03 Shutdown
domina
cooling water
nt
pump trial run

Shutdown
domina Table 4.3.
01 cooling water
nt 26
pump trial run

15 Diesel
generator
installation

01 Diesel
generator oil

tank
installation

Diesel
generator oil Table 4.3.
01
tank 36
installation

02 Diesel
generator
installation

43
Diesel
Table
01 generator
4.17. 1
installation

03 Diesel
domina
generator trial
nt
run

Diesel
domina Table
01 generator trial
nt 4.17. 2
run

16 Installation of
the platform,
ladder,

handrail and
cover plate of
turbine room

01 Installation of
the platform,
ladder,

handrail and
cover plate of
turbine room

Installation of
the platform,
ladder, Table 4.3.
01
handrail and 37
cover plate of
turbine room

05 Water
circulating
pump room
equipment
installation

01 Water
circulating

pump
installation

01 Check and
installation of
water
circulating domina

pump nt
foundation and
pump base
(body)

44
Check and
installation of
water
circulating domina Table
01
pump nt 4.18. 1
foundation and
pump base
(body)

02 Water
circulating domina

pump nt
installation

Table
Water 4.18. 2-1
circulating domina Table
01
pump nt 4.18. 2-2
installation Table
4.18. 2-3

03 Installation of
motor for
water
circulating
pump

Installation of
Table
motor for
4.18. 3-1
01 water
Table
circulating
4.18. 3-2
pump

04 Water
circulating
pump oil
system
installation

Water
Table
circulating
4.18. 4
01 pump oil
Table
system
4.18. 5
installation

05 Water
domina
circulating
nt
pump trial run

Water
domina Table
01 circulating
nt 4.18. 6
pump trial run

45
02 Rotary sieve
equipment
installation

01 Rotary sieve
check and
installation

Rotary sieve
Table
01 check and
4.19. 1
installation

02 Test run of
domina
rotary filter
nt
screen

Test run of
domina Table
01 rotary filter
nt 4.19. 2
screen

03 Trash remover

installation

01 Trash remover
check and
installation

Trash remover
Table
01 check and
4.20.1
installation

02 Trash remover domina



trial run nt

Trash remover domina Table


01
trial run nt 4.20.2

04 Large scale
flat plate steel

valve
installation

01 Large scale
flat plate steel

valve
installation

Large scale
flat plate steel Table
01
valve 4.21
installation

05 Water
circulating
pump room
crane
installation

46
01 Bridge crane
check and
installation

Table
4.16. 1-1
Bridge crane
Table
01 check and
4.16. 1-2
installation
Table
4.16. 1-3

02 Bridge crane domina



load test nt

Bridge crane domina Table


01
load test nt 4.16. 1-4

03 Electric hoist
check and
installation

Electric hoist
Table
01 check and
4.16. 2-1
installation

04 Electric hoist domina



load test nt

Electric hoist domina Table


01
load test nt 4.16. 2-2

06 Water
circulating
pump room

cooling water
pump
installation

01 Cooling water

pump check

Cooling water Table 4.3.


01
pump check 27

02 Cooling water
pump
installation

Cooling water
Table 4.3.
01 pump
28
installation

03 Cooling water domina



pump trial run nt

Cooling water domina Table 4.3.


01
pump trial run nt 29

47
07 Installation of
water
circulating
pump room
metal member,
platform,ladde
r and handrail

01 Installation of
water
circulating
pump room
metal member,
platform,ladde
r and handrail

Installation of
water
circulating
Table 4.3.
01 pump room
37
metal member,
platform,ladde
r and handrail

08 Water
circulating
pump room

flushing water
pump
installation

01 Flushing water

pump check

Flushing water Table 4.3.


01
pump check 24

02 Installation of
flushing water
pump

Installation of
Table 4.3.
01 flushing water
25
pump

03 Trial run of
domina
flushing water
nt
pump

Trial run of
domina Table 4.3.
01 flushing water
nt 26
pump

48
06 Public water
pump house
and rain pump

house
equipment
installation

01 House service
pump
installation

01 House service

pump check

House service Table 4.3.


01
pump check 24

02 House service
pump
installation

House service
Table 4.3.
01 pump
25
installation

03 House service domina



pump trial run nt

House service domina Table 4.3.


01
pump trial run nt 26

02 Fire pump

installation

01 Fire pump

check

Fire pump Table 4.3.


01
check 27

02 Fire pump

installation

Fire pump Table 4.3.


01
installation 28

03 Fire pump trial domina



run nt

Fire pump trial domina Table 4.3.


01
run nt 29

03 Rain pump

installation

01 Rain pump

check

01 Rain pump Table 4.3.



check 27

49
02 Rain pump

installation

01 Rain pump Table 4.3.



installation 28

03 Rain pump domina



trial run nt

01 Rain pump domina Table 4.3.



trial run nt 29

04 Installation of
hoisting
equipment

01 Crane check
and
installation

01 Crane check
Table
and
4.16. 2-1
installation

02 Cargo domina

handling test nt

01 Cargo domina Table



handling test nt 4.16. 2-2

05 Installation of

draining pump

01 Draining

pump check

01 Draining Table 4.3.



pump check 27

02 Installation of

draining pump

01 Installation of Table 4.3.



draining pump 28

03 Draining

pump trial run

01 Draining Table 4.3.



pump trial run 29

07 Water
catchment
pump house
equipment
installation

01 Deep water
pump
installation

50
01 Deep water

pump check

01 Deep water Table



pump check 4.22.1

02 Deep water
pump
installation

01 Deep water
Table
pump
4.22.2
installation

03 Deep water domina



pump trial run nt

01 Deep water domina Table



pump trial run nt 4.22.3

02 Pressure
boosting
(feedwater)
pump
installation

01 Pressure
boosting

(feedwater)
pump check

01 Pressure
boosting Table 4.3.

(feedwater) 24
pump check

02 Pressure
boosting
(feedwater)
pump
installation

01 Pressure
boosting
Table 4.3.
(feedwater)
25
pump
installation

03 Pressure
boosting domina

(feedwater) nt
pump trial run

01

Pressure domina Table 4.3.


boosting nt 26
(feedwater) 51
pump trial run

03 Trash remover
equipment
installation

01 Trash remover
check and
installation

01 Trash remover
Table
check and
4.20.1
installation

02 Trash remover domina



trial run nt

01 Trash remover domina Table



trial run nt 4.20.2

04 Large scale
flat plate steel

valve
installation

01 Large scale
flat plate steel

valve
installation

01 Large scale
flat plate steel Table

valve 4.21
installation

05 Installation of
hoisting
equipment

01 inspection and
installation of

overhead
traveling crane

01 Table
inspection and 4.16. 1-1
installation of Table

overhead 4.16. 1-2
traveling crane Table
4.16. 1-3

02 Load test of
domina
overhead
nt
traveling crane

01
Load test of domina Table

52
overhead nt 4.16. 1-4
traveling crane

03 Electric hoist
overhaul and
installation

01 Electric hoist
Table
overhaul and
4.16. 2-1
installation

04 Electric hoist domina



load test nt

01 Electric hoist domina Table



load test nt 4.16. 2-2

06 Water
purifying plant
installation

01 Water
purifying plant

equipment
inspection

01 Water
purifying plant Table

equipment 4.23. 1
inspection

02 Water
purifying plant domina

installation, nt
trial run

01 Water
purifying plant domina Table

installation, nt 4.23. 2
trial run

07 Sludge pump
equipment
installation

01 Sludge pump

check

01 Sludge pump Table 4.3.



check 27

02 Sludge pump

installation

01 Sludge pump Table 4.3.



installation 28

03
Sludge pump

53
trial run

01 Sludge pump Table 4.3.



trial run 29

08 Combustion
engine main domina

body nt
installation

01 Combustion
engine main domina

body nt
installation

01 Foundation

preparation

Foundation Table
01
preparation 4.24.1

02 Adjustable
fixer(iron domina

gasket)installat nt
ion

Adjustable
fixer(iron domina Table 4.3.
01
gasket)installat nt 8
ion

03 Check and
installation of domina

pedestal and nt
base plate

Check and
installation of domina Table
01
pedestal and nt 4.24.2
base plate

04 Combustion
engine main
domina
body
nt
positioning
installation

Combustion
engine main domina Table
01
body nt 4.24.3-1
positioning

Burner domina Table


02
installation nt 4.24.3-2

03 Combustion domina Table

54
engine load nt 4.24.3-3
distribution

Shafting
domina Table
04 adjustment
nt 4.24.3-4
and connection

Sliding pin
system
clearance domina Table
05
measurement nt 4.24.3-5
and
adjustment

Table
Rotor turning
4.4.12-1
06 gear
Table
installation
4.4.12-2

Automatic
synchronizing Table
07
device 4.24.3-6
installation

05 Combustion
engine inlet domina

side nt
installation

See DL/T
5210.2
Gas handling table
system steel 4.4.1~Ta
01
structure ble 4.4.6,
installation Table 4.3.
1~Table
4.3. 4

Inlet chamber
Table
02 aggregate
4.24.4-1
installation

Air cleaning
and sound
Table
03 suppression
4.24.4-2
system
installation

Inlet system domina Table


04
sealing check nt 4.24.4-3

06

Combustion domina
engine exhaust nt
part
55
installation

See DL/T
5210.2Ta
Exhaust ble
system steel 4.4.1~Ta
01
structure ble 4.4.6,
installation Table 4.3.
1-Table
4.3. 4

Exhaust frame
Table
02 and diffuser
4.24.5-1
installation

Draught flue
Table
03 aggregate
4.24.5-2
installation

Exhaust
domina Table
04 system seal
nt 4.24.5-3
check

01 07 Bypass
chimney
installation

Bypass
Table
01 chimney
4.24.6
installation

08 Foundation
baseplate
grouting

Table 4.3.
Foundation
11
01 baseplate
Table 4.3.
grouting
12

09 Housing

installation

Housing Table
01
installation 4.24.7

02 Combustion
engine main domina

body pipeline nt
installation

01 Combustion
engine main domina

body pipeline nt
installation

56
Combustion
engine main domina Table
01
body pipeline nt 4.24.8
installation

02 Oil system
domina
installation
nt
and flashing

Lubricating oil
Table 4.5.
01 system
6-9
installation

Fire resistant
Table 4.5.
02 oil system
5-2
installation

Lubricating oil
domina Table 4.5.
03 system
nt 6-10
flashing

Fire resistant
domina Table 4.5.
04 oil system
nt 5-3
flashing

09 Combustion
engine
auxiliary
device and
accessory
machinery
installation

01 Gaseous fuel
supply system

equipment
installation

01 Gaseous fuel
pressure
regulating
station module
installation

Gaseous fuel
pressure
Table 4.3.
01 regulating
33
station module
installation

02 Gaseous fuel
preposition

module
installation

57
Gaseous fuel
preposition Table 4.3.
01
module 33
installation

03 Gaseous fuel
domina
valve module
nt
installation

Gaseous fuel
domina Table 4.3.
01 valve module
nt 33
installation

04 Fuel gas
supercharger
installation

Fuel gas Table 4.3.


01 supercharger 33 Table
installation 4.3. 26

02 Fuel oil supply


system
installation

01 Fuel oil
treatment

system
installation

Fuel oil
Table 4.3.
processing
01 33 Table
module
4.3. 26
installation

02 Fuel oil
preposition

module
installation

Fuel oil
Table 4.3.
preposition
01 33 Table
module
4.3. 26
installation

02 03 Fuel oil filter


module
installation

Fuel oil filter


Table 4.3.
01 module
33
installation

04

Combustion
engine V
inhibitor 58
module
installation

Combustion
Table 4.3.
engine V
33
01 inhibitor
Table 4.3.
module
26
installation

05 Combustion
engine
atomizing air
pump
installation

Combustion
Table 4.3.
engine
33
01 atomizing air
Table 4.3.
pump
26
installation

03 Other
equipment
module
installation of
the
combustion
engine

01 Combustion
engine
auxiliary
module
installation

Combustion
Table 4.3.
engine
33
01 auxiliary
Table 4.3.
module
26
installation

02 Combustion
engine water
washing
module
installation

Combustion
Table 4.3.
engine water
33
01 washing
Table 4.3.
module
26
installation

59
03 Combustion
engine flame
failure

protection
module
installation

Combustion
engine flame
failure Table 4.3.
01
protection 33
module
installation

04 Combustion
engine air
handling
module
installation

Combustion
engine air
Table 4.3.
01 handling
33
module
installation

05 Combustion
engine
ventilation, domina

sealing nt
cooling system
installation

Combustion
engine Table 4.3.
ventilation, domina 30
01
sealing nt Table
cooling system 4.4.13
installation

06 Combustion
engine water
injection
module
installation

Combustion
Table 4.3.
engine water
33
01 injection
Table 4.3.
module
26
installation

60
(Seal) (Seal) (Seal)
Development Supervision Construction
organization organization organization

Date Date Date

The construction management condition of unit project shall be inspected during the
construction and acceptance of unit project and the inspection results shall be filled in Table
4.2.2.
Table 4.2.2 ()Engineering construction management record of inspection
________ plant unit Project number:
Development
Project name
organization

Design organization
Design organization
Leader

Supervision Unit engineering


organization Supervising engineer

Unit engineering
Development
construction
organization
Technical director

Unit construction Unit completion of


starting date works date

Construction management inspection result

SN Construction management system and delivery performance inspection item Inspection result

1 Implemented technical standards list

2 Read and edit of construction organization design abd construction scheme

3 Construction drawing examination and inspection meeting

4 Acceptance and inspection of equipments and materials

5 Implementation condition of compulsory provision

6 Quality control system and delivery performance

7 Safety management system and delivery performance

8 Energy saving and emission reduction target and system

9 Environmental protection

10 Certification condition of special type of work

11 Management of measurement tools

61
12 Subcontract unit aptitude management

13 Administrative situation of engineering materials

14 Inspection results of quality supervision and problem closed loop condition

Acceptance result:

General supervision engineer : Date

Development organization leader : Date

4.2.3 The information listed in Table 4.2.3 shall be examined for the unit project acceptance;
the examing results shall be complete and meet the requirements of records management.
Table 4.2.3 () check table of quality control documents of unit project
________ plant unit Project number:
Expected Actual
SN Document name Check condition
copies copies

Letter of notice and registration form of design


1
alteration and materials substitutes

Equipments and materials delivery test report and


2
quality certificate registration form

Equipment defect notice and equipment defect


3
handling report

Registration form of measurement tools used for this


4
unit project

5 Quality acceptance records of the inspection lot

6 Subentry project quality acceptance table

7 Subsection project quality acceptance table

8 Unit quality inspection and acceptance table

9 Concealed work approval

10 Construction record

11 Single machine trial run approval

Table of implementation performance of compulsory


12
provisions

Acceptance organization signature

Construction organization Date

Supervision organization Date

62
Development organization Date

4.2.4 The letter of notice for engineering design alteration, materials substitutes and change in
design shall be numbered and registered and attached following registration form. The
register of letter of notice for the unit project design alteration and materials substitutes shall
be in accordance with those specified in Table 4.2.4.
Table 4.2.4 Letter of notice and registration form of design alteration and materials substitutes
________ plant unit Project number:
No. of amended
Original Chart number related Implementation
SN Letter of notice name contents in letter of
number to alteration performance
notice

Construction Supervision
Date Date
organization organization

4.2.5 Delivery test report of equipments and materials and quality certificate shall be
numbered, registered and attached following the registration form. The register of factory test
report of unit project equipments and materials and the quality certificate shall be in
accordance with those specified in Table 4.2.5.
Table 4.2.5 ( ) unit engineering facilities, material routine test report and quality certificate material
registration table
________ plant unit Numbering:
Total Original number of
Equipment, material testing report and Providing organization
SN page of report and quality Remarks
quality certificate material name of report
report certificate material

63
Filled by Date

4.2.6 After the discovery of equipment defect, construction,supervision,manufacture and


Development organization shall check together and fill the equipment defect letter of notice.
The filling of equipment defect letter of notice shall meet the provisions of table 4.2.6.
Table 4.2.6 Letter of notice on equipment defect
________ plant unit Project number:
Subentry project
Unit project name
name

Inspection lot name No.

Equipment name Discovery date

64
Condition of equipment defect:

Construction organization

Date

Construction Manufacturing
organization organization

Supervision Construction
organization organization

Treatment suggestion:

Set up unit profession skill responbsilbe person:


Date

Organization Defect treatment conclusion: Signature

Construction
Date
organization

Manufacturing
Date
organization

Supervision
Date
organization

Development
Date
organization

4.2.7 The process unit report to development organization after the treatment of equipment
defect; the development organization organiza organizations concerned to carry out inspection
and acceptance abd sign acceptance opinion and signature on the equipment defect treatment
report. The filling of equipment defect treatmen report shall meet the provisions of table 4.2.7.

65
Table 4.2.7 Equipment defect treatmen report single
Plant unit Project number:
Subentry project
Unit project name
name

Inspection lot name No.

Equipment name Treatmen date

Defect treatment condition:

Technical director of defect treatment organization:


Date

Treatment condition of defect:

Supervision organization:
Date

Acceptance
Acceptance opinion Acceptance signature
organization

Construction
Date
organization

Manufacturing
Date
organization

Supervision
Date
organization:

Development
Date
organization

66
4.2.8 The measurement tools used for construction inspection must be identified for
measurement and in the validity period. The used measurement tools must be registered
accurately according to those specified in Table 4.2.8 during the construction. The supervision
engineer shall inspect and verify the measurement tools registered in table.
Table 4.2.8 () measurement tools used for unit project registration form
Plant unit Project number:
Calibration
Measuring equipment (tool) Factory Measurement Accuracy
SN Type/model Validity Remarks
name number limit rating
period

67
Construction
Date Supervision organization Date
organization

4.2.9 The construction quality of inspection lot shall be inspected and accepted according to
the quality criteria of inspection item; the construction quality acceptance table of inspection
lot shall be filled in. In accordance with Table 4.2.1, if there is no main control inProperty
column, the table means general. It shall be made in the acceptance organization signature
column which goes beyond acceptance range; inspection lot construction quality acceptance
shall meet the provisions of table 4.2.9.
Table 4.2.9 () construction quality acceptance table of inspection lot
Plant unit Project number: Property: Table X. X. X
Subentry project name

SN Inspection item Property Unit Quality criteria Inspection result Conclusion

Acceptance conclusion:

Acceptance organization signature

Construction
Date
organization

68
Supervision
Date
organization

Manufacturing
Date
organization

Design
Date
organization

Development
Date
organization

4.2.10 The construction quality of subentry project shall be accepted according to those
specified in Table 4.2.10 and the construction quality acceptance table of subentry project
shall be filled in. In accordance with table 4.2.1, slash shall be filled in the acceptance
organization signature column which is not belongs to the acceptance range.
Table 4.2.10 Subentry project quality acceptance table
________ plant unit Project number: Property:
Subsection project name

SN Inspection lot name Property Acceptance result Remarks

69
Acceptance conclusion:

Supervision organization:

Acceptance organization signature

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Design organization Date

Development
Date
organization

4.2.11 The construction quality of subsection project shall be accepted according to those
specified in Table 4.2.11 and the construction quality acceptance table of subsection project
shall be filled in. In accordance with table 4.2.1, slash shall be filled in the acceptance
organization signature column which is not belongs to the acceptance range.
Table 4.2.11 ( )subsection project quality acceptance table
________ plant unit Project number: Property:
Unit project name

SN Subentry project name Property Acceptance conclusion: Remarks

70
Acceptance conclusion:

Supervision organization:

Acceptance organization signature

Construction
Date
organization

Supervision organization Date

Manufacturing
Date
organization

Design organization Date

Development
Date
organization

4.2.12 The unit engineering quality shall be accepted according to those specified in Table
4.2.12 and the unit quality inspection and acceptance shall be filled in. In accordance with
table 4.2.1, slash shall be filled in the acceptance organization signature column which is not
belongs to the acceptance range.
Table 4.2.12 ( ) unit quality inspection and acceptance table
________ plant unit Project number:
SN Subsection project name Property Acceptance result Remarks

71
Acceptance conclusion:

Development organization :

Acceptance organization signature

Construction
Date
organization

Supervision organization Date

Manufacturing
Date
organization

Design organization Date

Development
Date
organization

4.2.13 Refer to table 4.2.13 for steam turbine generator units installation engineering quality
control point approval, record,compulsory provision delivery performance check. during the
process of implementing this standard, this can be adjusted according to actual situation.
Table 4.2.13 Steam turbine generator units engineering quality control point approval, record, compulsory
provision delivery performance and check item

72
Table of
Appearance
implementation
Unit Subsection Subitem quality Table
SN Name Approval Record performance of
engineering project project acceptanceand numbering
compulsory
approval
provisions

Main body installation


Table 4.26.
01 engineering of turbine
1-26
generators

Foundation preparation and


iron gasket ( block )
Table
configuration before
4.4.15
installation of turbine
generators

Foundation preparation of
turbine generators

Turbine generator foundation


01 1
01 inspection acceptance record

Foundation settlement
2
observational record

Turbine generators foundation


iron gasket ( filling block )
preparation installation
02
Steam turbine foundation iron
1 gasket (mortar block)
preparation records

Steam turbine main body Table


02
installation 4.4.16

Pedestal check and installation

Steam cylindr, bearing seat


1 pedestal leveing centering
records

Steam cylindr, bearing seat


2 pedestal, steam cylindr and
01
bearing seat gap records

Bearing seat, steam cylindr


3 pedestal stone bolt fastening
records

Table 4.26.
4 Pedestal contact check
1-1

Bearseat(box) and bearing


02
bush check

1 Bearing seat slippage check

2 Bearing seat oil-filling test Table 4.26.

73
1-2

Thrust pad contact and thrust


3
gap check

Bearing bush filling


4 block,bearing bush and shaft
neck contact check

Installation of bearing seat


(box ) and bearing bush

Bearing seat split horizontal


1
recording

Bearing bush installation


03 2
records

3 Thrust pad installation records

4 Oil catch gap records

Table 4.26.
5 Bearing seat covering
1-3

cleaning and check of steam


cylindr and cylinder internal
04 component

Steam cylindr appearance Table 4.26.


1
inspection 1-4

check of turbinr rotor

Turbine rotor appearance Table 4.26.


1
inspection 1-5

Axiocervical ellipticity and


2
non-cylindrical degree records
05
3 Axial bend records

Thrust disc floating


4
displacement records

Coupling floating
5
displacement records

Steam cylindr combination


positioning

Steam cylindr combination


1
06 records

Steam cylindr positioning and


2
centering records

3 Casing split gap records

Aggregate installation of
07 steam cylindr internal
component

1 Steam cylindr parting sheet

74
bore centre align records

Steam cylindr inner cylinder


2 vertical, lateral pin installation
records

Inner cylinder bracing stud


3
installation records

Inner cylinder split horizontal


4
recording

Inner cylinder split gap


5
records

Parting sheet expansion


6
clearance measuring record

High and medium pressure Table 4.26.


7
nozzle box check seal 1-6

Steam cylindr load distribution


08
1 Steam cylindr load distribution

Flow passage clearance


measurement adjustment

Flow passage clearance


1
inspection

Minimum axial flow passage


09 2
clearance inspection

Rotor location dimension


3
outer outer lead

coupling gasket thickness


4
records

Labyrinth clearance

10 measurement adjustment

1 Labyrinth clearance check

Steam turbine covering

Check before steam turbine Table 4.26.


1
covering 1-7
11
Table 4.26.
2 Steam turbine covering
1-8

3 Casing split bolt up records

Shafting adjustment and


12
connection

Turbine rotor coupling centre


1
align

Rotor bolt, nut counterweight


2
records

3 Shaking degree records after

75
coupling joint

Rotor bolt, bolt hole fit


4
clearance records

5 Coupling bolt up records

Turbine generators foundation


secondary pouring
13
Check before foundation Table 4.26.
1
baseplate grouting 1-9

Sliding pin system clearance


measurement and adjustment

Sliding pin system clearance


1
measurement records
14
Center beam installation
2 records between bearing seat
and steam cylindr

3 Side arm installation records

Turning gear check and


installation
15
Rotor turning gear gear
1
clearance measuring record

Medium and low pressure


communicating pipe
installation

Communicating pipe Table 4.26.


1
16 installation check 1-10

Communicating pipe cold


2
drawn records

Communicating pipe bolt up


3
records

Adjustment and lubricating oil Table 4.5.


03
system equipment installation 7

Valve and governing valve


installation

ValveValve and governing


Table 4.26.
1 valve tightness inspection
1-11
(after washing pipe)
01 Main throttle valve
2 positioning and centering
records

Combined intermediate valve


3 positioning and centering
records

05
Fire resistant fluid system and

76
piping installation

Check before fire resistant oil Table 4.26.


1
system flashing 1-12

Oily laboratory examination Table 4.26.


2
after fireresistant oil flashing 1-13

Fireresistant oil device


3
positioning records

Lubricating oil system


equipment and piping
installation

Table 4.26.
1 Oil cooler tightness inspection
1-14

Table 4.26.
2 Check before oil tank sealing
1-15
06
Check before lubricate Table 4.26.
3
(sealing) oil flushing 1-16

Oily inspection after lubricate Table 4.26.


4
(sealing) oil flushing 1-17

5 Oil poump installation records

6 Oil cooler installation records

7 Main tank centering records

Generator and exciter Table 4.6.


04
installation 21

Pedestal positioning

Generator pedestal and


1 embedded parts installation
01
records

Pedestal leveing and centering


2
records

Generator rotor check

Table 4.26.
02 1 Generator rotor tightness test
1-18

2 Rotor record of inspection

Stator tightness test


04 Table 4.26.
1 Stator tightness test
1-19

insertion of generator rotor


05 Table 4.26.
1 insertion of generator rotor
1-20

Generator end cap bearing


07
installation

77
Generator bearing bush
1 clearance measurement
records

Adjustment of air gap and


magnetic force center
08
Adjustment of air gap and
1
magnetic force center

Fan gap adjustment


09 Generator fan clearance
1
measurement records

Sealing pad installation

Generator sealing pad


10
1 inspection and installation
records

Steam turbine generator


coupling centre align
11
Steam turbine generator
1
coupling centre align

Generator oil catch installation


12 Generator oil catch installation
1
record

Installation of seal of
generator end cap
13
Installation of seal of Table 4.26.
1
generator end cap 1-21

Installation of hydrogen cooler


14 Table 4.26.
1 Hydrogen cooler tightness test
1-22

Exciter installation

Exciter rotor record of


1
inspection

Exciter clearance
2
measurement records

Exciter air gap and magnetic


3
force center measuring record
15
Exciter rotor and generator
4
rotor centre align records

Exciter fan,air damper and oil


5 catch clearance measurement
records

Exciter air cooled condenser Table 4.26.


6
water pressure test 1-23

78
Carbon brush yoke installation

Exciter (brush yoke) coupling


1
16 centre align

Clearance measurement
2
records of carbon brush yokes

Air pressure test of whole set


of generator
17
Air pressure test of whole set Table 4.26.
1
of generator 1-24

Sealing oil system device and


piping installation

Integrated sealing oil device


1
installation records

Sealing oil pump clearance


18 2
measurement records

Sealing oil pump coupling


3
centre align records

Sealing oil subdivision trial


4
run records

Internal cooling water system


equipment and piping
installation

Internal cooling water pump


1 clearance measurement
records

Internal cooling water pump


2
19 coupling centre align records

Internal cooling water pump


3
subdivision trial run records

Integrated internal cooling


4 water device installation
records

Generator internal cooling Table 4.26.


5
water system flashing 1-25

Turbine generators auxiliary Table 4.26.


02
device installation 2-8

Assembly and installation of Table 4.7.


01
water-cooled condenser 6

Condenser positioning and


02
centering

Condenser foundation pedestal


1
installation records

2 Condenser shell combination

79
records

Condenser positioning,
3
leveing and centering records

Condenser cooling tube


bundle installation

1 Tube plate interval records

2 Tube plate planeness records

Parting sheet concentricity


03 3
records

Tube plate elevation


4
difference records

Check before condenser Table 4.26.


5
poling 2-1

Low pressure cylinder and


condenser connection and
tightness test

Check before low pressure


04 Table 4.26.
1 cylinder and condenser
2-2
connection

Table 4.26.
2 Condenser watering test
2-3

Condenser accessory
installation
05
Table 4.26.
1 Drain flash tank shelter
24

Installation of air-cooling Table 4.8.


02
condenser system 5

Air cooling steel structure


installation
01
Bracing steel structure
1
installation records

Air cooling condenser fan


installation

Fan blade installation angle


1
records

Fan retaining cylinder


02 2
ellipticity records

Boss plate and gear case


3
levelness records

Fan blade top and fan drum


4
gap records

Aircooling system tightness


09
test

80
Aircooling system tightness Table 4.26.
1
test 2-5

Deaerator (water tank) Table 4.9.



equipment installation 3

Deaerator (water tank) main


body installation
03
Deaerator (water tank) main
01 1
body installation record

Deaerator (water tank) main Table 4.26.


2
body seal shelter 2-6

High pressure heater check Table



and installation 4.10.2

High pressure heater


04 installation
02 High pressure heater
1 positioning and centering
records

Low pressure heater check Table


and installation 4.10.2

Low pressure heater


05 installation
02 Low pressure heater
1 positioning and centering
records

Gland heater check Table



installation 4.10.2

06 Gland heater installation


02 Gland heater positioning and
1
centering records

Turbine hall drain flash tank Table



installation 4.10.2
07 Turbine hall drain flash tank
01 1 positioning and centering
records

Installation of other heat Table


exchanger 4.10.2

Installation of other heat


exchanger
08 other heat exchanger
02 1 positioning and centering
records

Heat exchanger (water side or Table 4.26.


2
steam side) water pressure test 2-7

81
Inspection and installation of Table
09 1
bypass system equipment 4.11.4

Turbine generator accessory Table 4.26.


03
machinery installation 3-3

installation of steam feed Table


01
pump unit 4.12.16

Foundation preparation, iron


gasket and stone bolt
preparation installation
01
Steam feed pump unit
1 foundation embedded parts
and stone bolt check

Pedestal grinding and


positioning
02
Steam feed pump unit pedestal
1
installation records

Bearing (seat) and oil catch


check

Steam feed pump unit bearing


1 clearance measurement
records
03
Thrust bearing gap and contact
2
check

Bearing bush filling


3 block,bearing bush and shaft
neck contact check

Steam cylindr combination,


check, positioning

Steam cylindr positioning and


1
centering records
04
Sliding pin system clearance
2
measurement records

Lug clearance measurement


3
records

Rotor positioning centre align

Driving steam turbine rotor


05 1 and steam cylindr centre align
records

2 Rotor journal lift records

Diaphragm gland installation

1 Parting sheet bore centre align


06
Labyrinth clearance measuring
2
record

82
Flow passage part clearance
measurement, adjustment and
thrust disc orientation

Steam feed pump steam


1 turbine flow passage clearance
07
inspection

Steam feed pump driving


steam turbine rotor thrust gap,
2
axial location and outer lead
value measuring record

Driving steam turbine


covering
08
Steam feed pump driving Table 4.26.
1
steam turbine covering 3-1

Bearing (seat) covering and


rotor turning gear installation

Steam feed pump driving


09 1 steam turbine barring
installation records

Driving feed pump steam Table 4.26.


2
turbine bearing seat covering 1-3

Lubricating oil system


installation

Oil tank positioning and


1
centering
11
Table 4.26.
2 Oil cooler tightness inspection
1-14

3 Oil poump installation records

4 Oil poump trial run records

Oil system flashing

Oily inspection after driving


Table 4.26.
1 feed pump set lubricant
12 1-17
flashing

Pilot oil oily laboratory Table 4.26.


2
examination 1-13

Driving steam turbine trial run

Driving steam turbine trial run


1
13 record

Steam feed pump unit trial run


2
records

Steam feed pump installation


14

1 Foundation iron gasket

83
installation records

Steam feed pump unit


secondary pouring
15
Steam feed pump unit Table 4.26.
1
secondary pouring 1-9

Steam feed pump set centre


align and connection
16 Steam feed pump and its
1 driving steam turbine centre
align

Electrically driven feed pump Table 4.13.


02
group installation 6

Electrically driven feed pump


group installation

Electrically driven feed pump


group foundation embedded
1
parts and stone bolt record of
inspection

Electrically driven feed pump


2 group pedestal installation
records
03
Electrically driven feed pump
3 group bearing clearance
measurement records

Electrically driven feed pump


4 rotor axial drunkenness and
thrust gap measuring record

Electrically driven feed pump


5 rotor shaft lifting volume
measuring record

Electrically driven feed pump


group coupling centre align
04
Electrically driven feed pump
1
group coupling centre align

Electrically driven feed pump


group secondary pouring
05
Electrically driven feed pump Table 4.26.
1
group secondary pouring 1-9

Electrically driven feed pump


06
oil system installation

Electrically driven feed pump


Table 4.26.
1 group working oil cooler
1-14
water pressure test

84
Electrically driven feed pump
Table 4.26.
2 group lube oil cooler water
1-14
pressure test

Electrically driven feed pump


oil system flashing
07 Oily inspection after
Table 4.26.
1 electrically driven feed pump
1-17
oil system flashing

Electrically driven feed pump


group trial run

Fluid coupling no load trial


08 1
run records

Electrically driven feed pump


2
cold state trial run records

Feed pump booster pump Table 4.13.



installation 7

Booster pump check


01 Booster pump clearance
1
measurement records

Booster pump installation


03
Rotor coupling centre align
1
02 records

Motor air cooled condenser Table 4.26.


2
water pressure test 3-2

Booster pump trial run


03
1 Booster pump trial run record

Table 4.13.
Condensate pump installation
7

01 Condensate pump check


04 Condensate pump motor water Table 4.26.
1
cooler water pressure test 3-2

Condensate pump bearing Table 4.26.


2
cooler water pressure test 1-14

Table 4.3.
Installation of other
39
04 01 equipments including steam
Table 4.26.
turbine generator units
4-3
05 General tank container
1 positioning and centering
records

Table 4.26.
2 General tank container seal
2-4

85
Turbine hall installation of
hoisting equipment

01 Bridge crane installation

Bridge type cargo handling Table 4.26.


1
12 test 4-1

Other installation of hoisting


02
equipment

Table 4.26.
1 General cargo handling test
4-2

Table 4.23.
Water circulating pump room 3
05
equipment installation Table 4.26.
5

Water circulating pump


installation

Water circulating pump check


01 01 1 (include air tight test),
installation records

Water circulating pump trial


05 1
run

Rotary sieve installation

Rotary sieve installation


02 01 1
records

02 1 Rotary sieve trial run

Trash remover installation

Trash remover installation


03 01 1
record

02 1 Trash remover trial run

Large scale flat plate steel


valve installation

Large scale flat plate steel


04 01 1
valve installation record

Large scale flat plate steel


02 .1
valve test

Water circulating pump room


crane enection
05
01 1 crane enection records

02 1 Crane trial run

other installations of water


06
circulating pump room

other pump installation


01 1
records

86
02 1 Trial run of other pump

Table 4.23.
Public water pump house and
3
rain pump house equipment
Table 4.26.
installation
5

House service pump


installation

01 House service pump check,


02 1
installation record

03 1 House service pump trial run

Fire pump installation


06 02 02 1 Fire pump installationrecord

03 1 Fire pump trial run

Rain pump installation

03 02 1 Rain pump installation record

03 1 Rain pump trial run

Installation of hoisting
equipment

04 Installation of hoisting
01 1
equipment record

02 1 Crane test

Table 4.23.
Water catchment pump house 3
07
equipment installation Table 4.26.
5

Deep water pump installation

Deep water pump check and


01 02 1
installation records

03 1 Deep water pump trial run

Pressure boosting (feedwater)


pump installation

Pressure boosting (feedwater)


02 02 1
pump installation record

Pressure boosting (feedwater)


03 1
pump

Trash remover equipment


03
installation

Trash remover installation


1
01 record

2 Trash remover trial run

04
1 Large scale flat plate steel

87
valve installation record

Large scale flat plate steel


2
valve test

Installation of hoisting
1
05 equipmentrecord

2 Crane test

Water purifying plant


1
06 02 installationrecord

2 Water purifying plant trial run

other pump installation


02 1
07 records

03 1 Other pump trial run

Combustion engine main body Table 4.26.


08
installation 6-4

Combustion engine main body Table


01
installation 4.24.9

Foundation plate (pedestal)


01 1
installation

Combustion engine main body


04
positioning installation

Combustion engine module


1 -
hoisting positioning

Combustion engine load


2
distribution

Combustion engine rotor


3
impact test

Combustion engine precision


4
centering and coupling joint

Combustion engine foundation


5
acceptance record

6 Fixer installation

Combustion engine load


7
distribution

8 Key pin installation record

Draught flue centre align


9
record

10 Coupling centre align record

Coupling bolt up elongation


11
indicator

Module positioning
12
installation record

88
13 Fan installation record

Combustion engine inlet side


installation

Inlet side steel structure


1
installation record
05
Inlet side manhole door seal Table 4.26.
2
check 6-1

Table 4.26.
3 Housing transparent check
6-3

Combustion engine exhaust


part installation

Combustion engine exhaust


1 part steel structure installation
06 record

Exhaust part manhole door Table 4.26.


2
seal check 6-2

Table 4.26.
3 Housing transparent check
6-3

Combustion engine main body Table



pipeline installation 4.24.10

Systematic inspection before Table 4.26.


02 1
oil flushing 1-16

Oil quality check after oil Table 4.26.


2
flushing 1-17

Combustion engine auxiliary


Table 4.26.
device and accessory
7-2
machinery installation

Gaseous fuel supply system


01 1 Table 4.25
equipment installation

Fuel oil treatment system


02 1 Table 4.25
installation
09
Other equipment module
03 installation of the combustion Table 4.25
engine

Module positioning
1
installation record

Fire extinguishing system Table 4.26.


2
spray test 7-1

89
4.3 General parts of steam turbine generator units
Turbine generators foundation preparation application scope: foundation check
preparation work before the installation of turbine generator main body, including foundation
check and geometric dimension checking, foundation bearing area roughening, baffle
installation within the process of baseplate grouting and stone bolt check.
4.3.1 See table 4.3. 1 for foundation check and geometric dimension checking, inspection
and acceptance
Table 4.3. 1 Foundation check and geometric dimension checking
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Smooth
Appearance inspection sureface,flawless,hole,nest,pitting Observation
surface and reinforcement exposion

Verticality deviation mm/m 2<


between foundation Isosceles triangle method

longitudinal center line dominant check, steel tape


mm Total deviation value <5
and condenser transverse measurement
Foundation center line
inspection Verticality deviation mm/m <2
between foundation Isosceles triangle method

longitudinal center line dominant check, steel tape


mm Total deviation value <5
and generator foundation measurement

transverse center line

Elevation reference line as


Bearing area elevation In accordance with design drawing
mm the benchmark;level
deviation requirements,10
measurement

Appearance inspection Clean up foundation olt hole Observation

Foundation vertical and


Deviation between bolt
horizontal center line as
hole center and base dominant mm <10 or <0.1da
Foundation benchmark;use steel tape
center line
olt hole for measurement

Pulling plumb-bob line and


Bolt hole wall verticality
b
mm <L/200, and <10 testing with straight steel
deviation
ruler

Deviation between bolt Foundation vertical and


center and foundation Meet the requirements of the horizontal center line as
mm
vertical and horizontal drawing,and<2 benchmark;use steel tape
center line for measurement
Buired bolt Reference line as the
Machine unit shafting lift shall be
Bolt elevation deviation mm benchmark; level
considered usually as +5~+10
measurement

Pulling plumb-bob line and


Verticality deviation mm L/450
testing with straight steel

90
ruler

In accordance with actual installation


requirements of design and
Reserved foundation hole size recheck mm equipment; do not affect expansion Measuring with steel tape
sliding of steam cylindr or bearing
seat

Deviation between Foundation vertical and


anchorage plate center horizontal center line as
mm <3
and foundation vertical benchmark;use steel tape
Preembedded and horizontal center line for measurement
anchorage Foundation line as the
Anchorage plate
plate mm 3 benchmark;level
elevation deviation
measurement

Positioning retaining Measuring with suspension


mm/m <3
plate verticality deviation wire plumb

Foundation vertical and


horizontal center line as
Support center deviation mm <2
benchmark;use steel tape
High-medium
for measurement
pressure
Foundation line as the
combined Support (bracket)
mm 3 benchmark;level
reheat valve elevation deviation
measurement
pre-buried
Horizontal relevant
support
elevation difference of
mm 1 Level measurement
same valve support top
surface

Seismic isolation gap between


foundation,factory building and relevant Clean up Observation
operation platform

a dIs pre-buried steel sleeve internal diameter.


b LIs length of pre-buried steel sleeve or stone bolt

4.3.2 See table 4.3. 2 for foundation bearing area roughening inspection and acceptance
Table 4.3. 2 Foundation bearing area roughening
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Foundation cleaning Clean, without lacquer,and oil dirt Observation

Meet the requirements of manufacturer;


Iron gasket arrangement Refer to DL 5011 if there are no design
requirements

Foundation strength during Examine and verify relevant


>70%Design strength
roughening report

Chip away concrete layer protruded


Roughening depth Observation
surface mortar bed

91
Straight steel ruler
Chipping size mm Exceed iron gasket edge 10~30
measurement

Contact between iron gasket and Compact contact; no tilting on four


Paint observation;hand test
concrete corners

Levelling rod vertical and


Foundattion level after roughening Bubble centered
horizontal direction check

Mount and adjust small lifting jack


Flat, smooth and without drop pit Observation
or temporarily iron gasket position

4.3.3 See table 4.3. 3 for installation, inspection and acceptance of baffle within baseplate
grouting.
Table 4.3.3 Baseplate grouting inner baffle installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Ensure positioning of steam cylindr and Check actual size of


Open hole geometric dimension mm
stator equipment

Straight steel ruler


Thickness mm 3~5
measurement

Material Steel plate Observation

Flat and neat along the foundation inner


Position bore wall;do not affect expansion of Observation
steam cylindr and bearing seat

Straight steel ruler


Upper limb height mm 10~20 lower than pedestal upper plane
measurement

Closeness around;without obvious


Inner baffle installing Observation
deformation

4.3.4 See table 4.3.4 for stone bolt inspection and acceptance.
Table 4.3.4 Foundation bolt examination
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance Oil-free; without lacquer and dirt Observation

Bolt and nut coordination Flexible, block-free Hand feeling check

Bolt length;diameter Meet the requirements of the drawing

Gap between bolt and

Foundation bolt hole or gap within mm >5 Steel tape measurement

bolt bolt sleeve

After bolt tighten up piece 2~3 shall protude Observation

Fasciae smooth and not inclined;


Surface contact between fasciae and compact contact; spot welding or
Observation
foundation concrete locking shall be made to underplate
lower nut

Alloy steel stone bolt material Meet the requirements of manufacturer Spectrum check

4.3.5 See table 4.3.5 for iron gasket preparation,inspection and acceptance

92
Table 4.3.5 Iron gasket preparation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Iron gasket material Steel plate Observation

Meet the requirements of


Length and width mm manufacturer or provitions of DL
5011

Flat, smooth;burr free and


Appearance Observation
curling;45 chamfer around edge

Feather edge thickness mm >10 Straight steel ruler measurement

Inclination 1/10~1/25 Surveying calculation

Contact face process roughness Observation

4.3.6 See table 4.3. 6 for installation inspection and acceptance of iron gasket.
Table 4.3. 6 Iron gasket installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Pedestal and iron gasket dominant mm Local tucked in width, depth all <
Contact
Iron gasket and iron 1/4 of side length (local0.05 feeler Inspecting with a feeler gauge
face gap dominant mm
gasket gauge)

Taper liner iron staggered area 25%Iron gasket area Observation

Edge distance between iron gasket


mm >10 Straight steel ruler measurement
and foundation

Gross thickness of each stack of About


mm Straight steel ruler measurement
iron gasket 80

Greater than stack ratio of three


dominant <20% Statistical calculation
a, b
pieces of iron gasket

Meet the requirements of


Elevation of burried iron gasket
manufacturer

Iron gasket levelness deviation mm/m <0.1 Gradienter measurement

Deviation between burried iron


gasket position and the center of mm <3 Steel tape measurement
bolt hole

a Each stack of iron gasket is less than or equal to three; five is acceptable under special circumstances; only one pair of
inclined iron gasket is allowed; a pair of inclined iron gasket shall shall be deemed as two.
b Stack ratio computing formula :Stack ratio= *100%

4.3.7 See Table 4.3.7 for preparation, inspection and acceptance of concrete block.
Table 4.3.7 Concrete block preparation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Foundation Position Meet the requirements of the


Check with pedestal
roughening Size drawing

93
Formwork installation Firm, sealing Observation

Formwork height mm About 80 Straight steel ruler measurement

Formwork internal concrete surface Impurity-free ; without lacquer


Observation
cleaning and dirt Impurity-free,

Foundation surface soaking time h 24 Observation

Material specifications and mixture Meet the requirements of


ratio manufacturer or DL 5011

Meet the requirements of the


Test block curing strength dominant Test report
drawing

Meet the requirements of


Filling block maintenance On-site examination
manufacturer or DL 5011

Contact area of filling block and


dominant >70% Paint method check
pedestal

Local tucked in width, depth all <


Filling block and pedestal contact
dominant mm 1/4 of side length (local0.05 feeler Inspecting with a feeler gauge
check
gauge)

Filling block levelness deviation mm/m <0.1 Gradienter measurement

Flat, smooth,flawless,cellulate; air


hole volume shall be in
accordance with manufacturer
requirements; single filling block
Concrete block surface surface popouts volume shall be Observation
less than or equal to 10% of the
total area. The filling block
surface bubble maximum diameter
10mm.

4.3.8 see table 4.3.8 for Fixer Installation inspection and acceptance
Table 4.3.8 Adjustible fixer installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flat, smooth,air-hole-free,without
crack,burrs and rusty stain; size Observation,use the straight
Appearance inspection
shall meet the requirements steel ruler for measurement
of manufacturer

Adjustable fixer spherical face


Flexible sliding, block-free Observation
contact

Adjustable height of spherical face Meet the requirements of Straight steel ruler
mm
pad manufacturer measurement

Filled lubricating grease;pollution


Adjustable gasket lubricating grease Observation
free

Distance between adjustable device Meet requirements of baseplate Straight steel ruler
mm
bottom surface and foundation grouting measurement

94
surface

Meet the requirements of


Adjustable fixer positioning
manufacturer

Meet requirements of baseplate


Adjustable baseplate grouting
grouting

4.3.9 See table 4.3.9 for installation inspection and acceptance of pedestal adjusting screw.
Table 4.3. 9 Pedestal adjusting screw installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Concrete surface shall be made


Adjusting concrete surface check at smooth, closely contacted with the
Observation
filling block emplacement filling block and be without tilting
around.

Screw contact part shall be flat and


Filling block surface inspection Observation
smooth

Screw load carrying shall be even;


Screw installation anti-looseness measures shall be Observation
taken.

Distance between pedestal and Meet requirements of baseplate Straight steel ruler
mm
foundation surface after adjustment grouting and adjustment measurement

4.3.10 See table 4.3. 10 for pedestal check, installation,inspection and acceptance.
Table 4.3. 10 Pedestal check and installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flat, smooth, clean, burr free,


crack-free; fire resistant powder paint
Pedestal sliding surface appearance
dominant shall be painted on sliding surfaces or Observation
inspection
settle according to requirements of the
manufacturer.

Pedestal pouring slot,louvre and Observation, blowing and


Complete, clear and impurity-free
lubricate oil hole shall be checked sweeping

Gasket between pedestal and stone


Flat, smooth and be without distortion Observation
bolt

Distance between pedestal bottom Straight steel ruler


mm About 80
surface and foundation surface measurement

Pedestal sliding surface contact Inspecting with a feeler


dominant mm <0.05
clearance inspection gauge

Contact between pedestal bottom Inspecting with a feeler


dominant mm <0.05
surface and fixer spherical face gauge

Contact between pedestal bottom Inspecting with a feeler


<0.05
surface and iron gasket gauge

Contact between pedestal bottom Inspecting with a feeler


<0.05
surface and concrete iron gasket gauge

95
Position meets the requirements of the
drawing;elevation allowable deviation Gradienter,gradienter and
Pedestal centering dominant mm is 1; deviation value direction shall straight steel ruler
be consistent; the level shall meet the measurement
requirements of manufacturer.

4.3.11 See table 4.3.11 for inspection and acceptance before steam turbine generator units
foundation secondary pouring.
Table 4.3.11 Check before steam turbine generator units foundation secondary pouring
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Firm, without leaked welding;clean up


Iron gasket spot welding dominant Observation
electrode coating

Use hand hammer to knock


Foundation bolt All fastening
and listen to the sound

Foundation surface cleaning Clean, without lacquer,and oil dirt Observation

Foundation surface soaking time dominant h 24 Timing

Buried spare parts pouring check Clean, without lacquer,and oil dirt Observation

Equipment oil hole, drainage hole Shall not be blocked Observation

Check of steam cylindr (bearing Rubberized fabric shall be stuck


Observation
seat) and pedestal slot firmly and completely

Position of secondary pouring Do not affect pipeline expansion Check formwork position

Clean,impurity-free, without sludge


Foundation olt hole Observation
and dirt

Good contact with foundation


Installing anchor bolt Observation
concrete; without leakage

4.3.12 See table 4.3.12 for steam turbine generator units foundation secondary pouring and
maintenance inspection and acceptance
Table 4.3. 12 Steam turbine generator unit foundation secondary pouring and maintenance
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Check test block strength


Test block strength Meeting the requirements of DL 5011
test report

Pouring Inside pedestal louvre overflowing the


of mortar is tehe limit; outside height
Pouring height Observation
concrete shall refer to design and actual
demand.

Bolt hole and pedestal Compact internal filling Observation

Curing Meeting the requirements of DL 5011 Observation

Check after Without honeycomb. spongy


Concrete appearance dominant Observation
removal of surface, hole or crack

the mould Concrete strength dominant Meet the requirements of the drawing Check strength test report

4.3.13 See table 4.3.13 for foundation settlement observation, inspection and acceptance.
Table 4.3.13 Foundation settlement observation

96
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Original record data shall be Level measurement or


After the expiration of foundation
complete; measurement shall be examination and verification
curing period
accurate record

Foundation regular settlement


observation

Before turbine chamber positioning

Complete data;accurate
After turbine chamber positioning
measurement;foundation differential
Before generator stator positioning Level measurement or examine
settlement leveing steam
and verify; compared with
After generator stator positioning turbine;centering and centre align
source data
every other day measurement
Before turbine generators baseplate
without obvious changes.
grouting

Other matters shall be in accordance


with provisions of the manufacturer
for settlement observation

4.3.14 See table 4.3.14 for bearing seat (box) cleaning and check acceptance
Table 4.3. 14 Bearing seat (box) clean and check
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean,without casting sand,


crack-free, without rust,dirt and
sundries, the inner surface is not Five times ~ ten times
inodissoluble turbine oil; lacquer magnifier appearance
Cleaning and check
dissolved in turbine oil must be inspection; oil passage
removed; oil passage shall be endoscopy
cleaned; without welding beading,
burrs and double skin.

Environment temperature
above 5; kerosene height be
Oil penetration test dominant No leakage not less than up edge of the oil
return port; whitewash powder
observation maintained for 24h.

Pressure oil supply hole flange joint Complete circuit continuous contact
Color-painting test
surface without breaking mark

Vessel flange studding hole It shall not penetrate shell wall Test passage

Gap between bearing seat (box) and Tightened bolt;feeler gauge


dominant mm <0.05
bearing cover horizontal integration check

Flat, smooth, clean, burr free,


Bearing seat sliding surface dominant crack-free; fire resistant powder Observation
paint shall be painted on sliding

97
surfaces or settle according to
requirements of the manufacturer.

Louvre and oil hole of joint surface


between bearing seat (box ) and Clear passage; no blocking
pedestal

Contact face gap between bearing


dominant mm <0.05 Inspecting with a feeler gauge
seat (box) and pedestal

Meet the requirements of


Sliding pin gap dominant mm Measurement
manufacturer

Use internal and external


Sliding pin,cotterway dimensional
mm 0.03 diameter micrometer to take
deviation value
three points for measurement

4.3.15 Bearing bush check see Table 4.3.15.


Table 4.3.15 Bearing bush inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean and clear oil duct and oil hole ;


Cleaning
without scrap iron and sundries
Bearing
Opening position Correct Observation, Test passage
bush
Without slag inclusion,air hole,drop
Bearing pad
pit and crack

Length of bodiless
dominant mm 1.5% of the black bronze perimeter
General segment
Black bearing 5% of black bronze perimeter; there
Total length of
bronze bush dominant mm shall be no bodiless section within PT check
bodiless section
bodiless 90bearing area

Three oil wedge and tilting


dominant No bodiless section
pad

Upside-down bearing bush assembly Mismatch not allowed Check after steady nail

Not-tightened bolt;feeler
Bearing bush split gap mm <0.05
gauge check

Bonding Area of contact surface dominant >75%,even Color-painting test


spherical
face between
Inspecting with a feeler
bearing bush Split gap dominant mm <0.03
gauge
and bearing
seat

Compacted, uniform, complete circuit


Contact around oil inlet dominant of contact around hydraulic fluid Color-painting test
connection

Black Meet the requirements of


Contact angle Color-painting test
bronze manufacturer,usually 30~45

98
and shaft Contact face dominant >75%,even
neck
Shape of contact point Dot shape

Meet the requirements of


manufacturer,General depth
is0.20~0.40; oil bag area shall be 1.5
Apical Physical dimension dominant mm % ~ 2.5 % of the shaft neck projected Feeler gauge
axis oil area (the relatively bigger value shall
bag be applied to the relatively bigger
shaft neck )

Contact between oil bag


dominant Closeness Color-painting test
and shaft neck

Jacking oil way, oil hole dominant Right and clear Test passage

4.3.16 Bearing bush filling block check see Table 4.3.16.


Table 4.3.16 Bearing bush filling block check
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Filling Contact face dominant >70%,and even Color-painting test


block and 0.05 feeler gauge local tucked in Inspecting with a feeler
Local gap nun
bore depth 10 gauge

Filling Contact face >60%,and even Color-painting test


block and Total clearance of lateral Meet the requirements of
mm Feeler gauge measurement
tile part manufacturer

Material quality Stainless steel

Common piece 3
Quantity:
special Piece 5
Gasket Observation
Flat, smooth, burr free, curling and a
Appearance
full wafer

Relatively larger than the oil hole


Gasket pore diameter
diameter

4.3.17 Alloy component material recheck see table 4.3.17.


Table 4.3.17 Alloy component material recheck
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Alloy component material recheck Meet the requirements of manufacturer Spectrum check

High Surface shall be smooth and clean,


temperature dent-free, rift-free, rust-free, and other
Appearance inspection dominant Observation
bolt greater defects caused by other stress
than or concentration.
equal to High alloy steel bolt
M32 100%Spectrum check dominant Meet the requirements of manufacturer inspection area shall be
both ends

100%Hardness check dominant Meet the requirements of manufacturer Check the inspection

99
report

100%Nondestructive Check the inspection


dominant Meet the requirements of manufacturer
inspection report

20CrlMolVNbTiBSteel
Check the inspection
metallurgical phase spot dominant Meet the requirements of manufacturer
report
inspection

4.3.18 Inspection and acceptance of auxiliary device and accessory machinery foundation
preparation see table 4.3.18.
Table 4.3.18 Auxiliary device and accessory machineryfoundation preparation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Curing time In accordance with DL/T 5210.1 Check pouring record

Electrically driven feed pump


dominant Meet the requirements of the drawing Check inspection report
concrete compressive strength

Free from reinforcement


exposion,honeycomb,crack,cobble Observation, hand
Concrete surface inspection
extruding,defects,and cleaning up hammer beat
interior of foundation bolt hole

Vertical and horizontal center line


mm 10 Steel tape measurement
deviation

Small steam turbine foundation


mm -10~10 Measuring with level
bearing area elevation deviation

Pump foundation bearing area


mm -20~0 Measuring with level
elevation deviation

Checking in accordance
Center deviation of foundation bolt
mm 10 with figure,Steel tape
hole
measurement

Iron gasket position concrete Flat chipping, tight contact and


Observation
surface treatment without tilting in iron gasket

Correct position and no obvious Checking in accordance


Embedded ironworks
deflection with figure

4.3.19 As for inspection and acceptance of auxiliary device and accessory machinery iron
gasket and stone bolt preparation and installation, see table 4.3.19.
Table 4.3. 19 Preparation and installation of auxiliary device and accessory machinery iron gasket and
stone bolt
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Iron gasket Physical dimension mm 10~20 wider than side of base Measuring with ruler
configuration Surface process No warping and burrs Observation
and Surveying calculation of
Taper liner iron gradient 1:10
installation straight ruler

Taper liner iron feather


mm Vernier check
edge thickness

100
Usually not less than or equal to 3
pieces; 5 under special circumstances;
Quantity of each stack Observation
there shall be one pair of taper liner
iron

Thickness of each stack Straight rule


mm 50~60
of iron gasket measurement

At both sides of foundation olt hole and


Iron gasket distribution Observation
load-bearing position

Hand hammer knocking


Compacted;local gap after tightened
Installation of iron gasket mm test and check of feeler
stone bolt shall be less than0.05
gauge

There shall be less than 2 points on each


Iron gasket spot welding Observation
iron gasket

Surface state Oil-free without dirt, scale and bending Observation

Verticality deviation <1% Measurement


Foundation Screw thread out of the
Thread 2~3 Observation
bolt nut

Good contact between nut and gasket, Observing,knocking and


Fastening
gasket and base testing by hand hammer

Pre-buried method

Supporting Pre-buried position Check according to


Meet the requirements of manufacturer
plate Levelness mm/m design drawing

Elevation mm

a Iron gasket shall be applicable to large pump unit like feed pump and water circulating pump . As for the small scale
accessory machine sharing commonbase, the requirements for iron gasket can be loosen.

4.3.20 See table 4.3.20 for auxiliary device and accessory machinery secondary pouring
inspection and acceptance
Table 4.3.20 Auxiliary device and accessory machinery secondary pouring
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Tamp concrete tightly inside hole; keep


Foundation bolt Check during pouring
foundation bolt vertical

Primary tightening of Knocking and testing by


No looseness
stone bolt hand hammer

Equipment level and Check in comparison


In accordance with installation record
center reinspection twith original record
Check
There shall be less than 2 points on each
before Iron gasket spot welding Observation
iron gasket
secondary
Appearance inspection of
pouring
component in which the Clean,oil-free; without painting and rust
concrete is poured Observation

Foundation surface Dustless; free of sundries and oil; no


cleaning surface soaking in water

101
Internal part shall be higher than the
Pouring of concrete
external part; the internal base shall be
within the base
filled

Concrete height of the


Secondary No lower than the lower edge of base
external base Observation
pouring
Compacted; there shall be no gap and
Concrete tamping air hole at the bottom surface below
base

Curing Meeting the requirements of DL 5011

Concrete compressive strength of


70%
tightened stone bolt

Note 1: auxiliary device and accessory machinery secondary pouring shall meet the requirements of manufacturer; comply
with this provision if there is no regulation.
Note 2: If the small pump is with the casting iron pedestal, pedestal and stone bolt can be poured at the same time; auxiliary
device base and stone bolt can be poured at the same time.

4.3.21 See table 4.3.21 for installation inspection and acceptance of accessory machinery
bearing seat (bearing room).
Table 4.3.21 Installation of accessory machinery bearing seat (bearing housing)
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flawless; without slag inclusion, casting


sand and air hole; painting shall be
Appearance inspection Observation
cleaned up (oilproof paint may not be
cleaned)

Horizontal integration Scatheless; local gap after tightening the Inspecting with a feeler
Check of mm
surface bolt <0.05 gauge
bearing
Scatheless; right installation, no leak of
housing Oil level gauge Observation
oil

Oleophobic hole of oil


Clean, clear and without leakage Observation
pipe and water pipe

Grease chamber tightness Check after filling


dominant No leakage
test kerosene for 24h

Hand hammer knocking


Bolt up Firm or measuring force
moment
Bearing
Location pin Complete and tight Observation
installation
Measuring with 1000
Motor bearings seat
M >0.5 V insulation resistance
insulation
meter

4.3.22 Check, installation, inspection and acceptance of sliding bearing see table 4.3.22.
Table 4.3.22 Check and installation of accessory machinery sliding bearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

102
Without slag inclusion,air hole,drop pit Coal-soaked oil or
Black bronze check
and crack penetrating fluid check

Horizontal integration dominant


Scatheless Observation
surface

Bearing bore contact Compacted and without tilting Hand feeling


Bearing
Contact face between
bush >70%,0.05 deducted from the height of
bearing bush filling mm Paiting inspection
check gasket below the bottom filling block
block and bore

In the right direction; alignment with the


Bearing bush oil inlet Observation
hydraulic fluid connection

Bearing bush thrust


No mismatch if it is pined Hand feeling
surface

Observation; take the


Bearing
Contact angle () 30~45 bigger value for the lower
bush and
rotation speed
shaft neck
Contact area 75%Evenly dotted distribution Paiting inspection

Meet the requirements of


Pressure fuse
Top dominant mm manufacturer,Generally0.2 % of the axle
measurement
diameter and >=0.10

Bearing Meet the requirements of manufacturer; Feeler gauge


Oil-block edge at both
bush gap dominant mm Generally0.1 % of the axle diameter and measurement; insertion
sides
0.06 depth10mm~15mm

Oil wedge at both ends Inspecting with a feeler


Even weage
of the lower bush gauge

Tightening Pressure fuse


Socket bush dominant mm 0.03
force of measurement
bearing
Other bush dominant mm 0.03~0.05
bush

Smooth and clean,burr free,no elliptical


Oil ring and firm joint. Flexible with the rotation Observation
of the axis

0.05~0.15,Small lower end and big up Feeler gauge


Pectinate oil catch gap nm
end measurement

Use soft and compacted material to


Hair felt oil catch Observation
closely touch the axle

4.3.23 See table 4.3.23 for check, installation, inspection and acceptance
Table 4.3.23 Check and installation of accessory machinery sliding bearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance inspection Clean,rustless and scatheless Observation

Roll body and internal and external


Flexible rotation,no looseness Hand feeling
circle

103
Check of bearing coollar shrunk Good contact with roll body;parallel end Measure with vernier
ring and housing washer surface caliper

0.2(Duplex bearing can be amplified Pressure fuse


Bearing capping Fixed end mm
properly) measurement
and bearing
Calculation according to
axial clearance Expansion end With enough expansion space
axial length

Gap between Fixed end dominant nun -0.03~0.01


Pressure fuse
bearing and
Expansion end dominant mm -0.01~0.03 measurement
enclosure

Measure with vernier


Match of bearing and shaft In accordance with requirements of H7/k6
caliper

Bearing designation dominant Meet the requirements of the drawing

4.3.24 See table 4.3.24 inspection and acceptance of horizontal centrifugal pump
Table 4.3.24 General check of horizontal centrifugal pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance inspection of the Without casting sand, burrs, air hole, crack
Observation
casting and scar; smooth and clean joint surface

Gap between support leg and Inspecting with a feeler


mm <0.05
pedestal base gauge

Inspecting joint surface of pump


Flatten,burr free and pit Observation
body

In accordance with provisions of table 4.3.


Bearing seat
21
Bearing and
In accordance with provisions of table 4.3.
bearing seat Sliding bearing
22
check
In accordance with provisions of table 4.3.
Rolling bearing
23

Without casting sand, burrs, air hole, crack


Parts appearance Observation
and scar; smooth and clean joint surface
Check of
Internal and external
sealing Assemblage gap mm Meet the requirements of manufacturer
miking
device
Filter screen
Meet the requirements of manufacturer Measuring with tape
specification

4.3.25 See table 4.3.25 for installation inspection and acceptance of common horizontal
centrifugal pump
Table 4.3.25 Installation of common horizontal centrifugal pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Foundation preparation In accordance with provisions of table 4.3. 18

Preparation and installation of iron


In accordance with provisions of table 4.3. 19
gasket and stone bolt

Center line deviation mm 10 Steel tape measurement

104
Elevation deviation mm 10 Measuring with level

Levelness deviation of Measuring horizontal


longitudinal and transversal mm/m flange or discharge flange
directions with levelling rod

Iron feet shall be equipped with spacer shim


Installing motors with different
mm with 1~2 thickness (take the big value for Observation
pump pedestals
large pump )

Coupling center deviation In accordance with provisions of table 4.3. 32

Cooling water pipe,dewatering


Complete,firm, in order and nice; do not
conduit and bleeder pipe water Observation
obstruct the channel
impact funnel

Coupling protective cover Firm and nice Observation

Secondary pouring In accordance with provisions of table 4.3. 20

4.3.26 See table 4.3.26 inspection and acceptance of horizontal centrifugal pump trial run.
Table 4.3.26 Horizontal centrifugal pump trial run
Inspection method
Inspection item Property Unit Quality criteria and measuring
instrument

In accordance with provisions of DL/T


Examine electric test
No-load trial operation of motor 5161.1 ~ 5161.17; right direction of
rum record
Inspection rotation

before In accordance with provisions of table


Coupling center reinspection
trial run 4.3. 32

Rolling rotor Flexible, no friction Hand feeling

Coupling protection cover Firm, not touching the coupling Observation

Oil level Meet the requirements of

Oil designation manufacturer

Cooling water Passage clear and enough flow Observation

Pressure difference between


Check Meet the requirements of
sealing water pressure and filter Observation
before manufacturer
screen
trial run
Measurement by using
Inlet pressure (vacuum) Meet the design requirements
vacuum pressure meter

Matching test with


Exit door and pump linkage test Meet the design requirements electric, heat
engineering

Check Measure with pressure


Outlet pressure dominant Reach to rated value and keep stable
during gage
trial run Sound normal, no friction and without Monitor with audition
Operation condition
shocking pin and

Current meter
Working current of motor A Rated value
measurement

105
n1000r/min dominant mm 0.10
Measure the vertical
Bear 1000r/min<n2000r/min dominant mm 0.08
and horizontal direction
vibration
by using virometer
2000r/min<n3000r/min dominant mm 0.05

Adopt bearing temperature of Measurement by


dominant 80
lubricating grease thermometer

Bearing temperature by adopting


dominant 70
lubricant

Normal temperature, tight vacuum;


Shaft seal sealed packing set; a small amount of Observation
dripping is allowed

Continuous trial run duration h 4~8 Timing

With certain race time but no sudden


Shutdown and coasting operation Observation
broke-off of the pump

Note: small multistage centrifugal pump trial run; refer to requirements of feed pump trial run

4.3.27 See table 4.3. 27 for inspection and acceptance of commonvertical pump
Table 4.3. 27 Check of common vertical pump
Inspection method and
Inspection item Property Unit Quality criteria
instruments

Without casting sand, burrs, air hole, crack


Appearance inspection Observation
and scar; smooth and clean joint surface

Inspecting joint surface of pump


Flatten,burr free and pit Observation
body

Flawless; without deformation, burrs and


Short piece and joint surface of base Observation
trench

Local gap between planes of


Inspecting with a feeler
composition of impeller enclosure mm <0.05
gauge
and guide vane

It shall be in the right position; be


Packing ring of each section compacted; without rupture, detinning Observation
tank or local protrusion

In accordance with provisions of table 4.3.


Bearing seat
21
Bearing and
In accordance with provisions of table 4.3.
bearing seat Sliding bearing
22
check
In accordance with provisions of table 4.3.
Rolling bearing
23

4.3.28 See table 4.3.28 for installation inspection and acceptance of vertical pump. Table
4.3.28 Installation of common vertical pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Base Center line deviation mm 3 Steel tape measurement

106
(foundation
Elevation deviation mm 5 Measuring with level
plate)

Levelness of base end surface dominant mm/m 0.05 Measure with gradienter

Preparation and installation of iron In accordance with provisions of table


gasket 4.3. 19

Concrete shall be compacted and be


without gap; the base and the upper part
of the pump base shall be poured with
Base secondary pouring Observation
filling; before pouring of enclosure
foundation-platform, the enclosure dowel
Bar and coat shall be welded.

Measurement of plumb
Hub cap fixation Meet the requirements of the drawing
bob and straight steel ruler

In accordance with requirements for rotor Control group assembling


Rotor hoisting height
hoisting value record checking

Coupling gasket preparation dominant Meet the requirements of manufacturer

Use spanner for checking


Bearing lock nut fastening dominant Firm during coupling
connection

Coupling floating displacement mm 0.04 Measure with dial gauge

Coupling radial flutter mm <0.04 Measure with dial gauge

Coupling Radical deviation


In accordance with provisions of table
centre dominant mm Measure with dial gauge
End face deviation 4.3. 32
alignment

Inspecting with a feeler


Coupling joint back face gap mm <0.05
gauge

Lower guide bearing radial total Measure with vernier


dominant mm 0.16~0.24
clearance caliper

Adjusting bolt Locking Use the spanner for check

4.3.29 See table 4.3.29 for trial run, inspection and acceptance of common vertical pump.
Table 4.3.29 Common vertical pump trial run
Inspection method and
Inspection item Property Unit Quality standard
measuring instrument

Oil level gauge Oil level is normal Observation

Oil designation Meet the requirements of manufacturer


Check
Cooling water pipe Passage clear and enough flow Observation
before
trial run Flexible operation of the Coordination with the
Lubricate water pipe quantity of
electromagnetic valve which meet the heat engineering
water
requirements of the drawing debugging

Check Electric and heat engineering In accordance with requirements of


before protection trial run

107
trial run Test of linkage among pump, Coordination with
outlet check valves and butterfly Meet the requirements of the drawing theelectric, heat
valve. engineering debugging

In accordance with provisions of DL/T


5161.1 ~5161.17; right direction of
No-load trial operation of motor
rotation; without friction and
abnormal sound

Coupling reinspection In accordance with installation record

In accordance with requirements for Comparison with


Coupling connection
rotor hoisting value installation record

Rubber First start-up 10


bearing
mm Timing
preoiling Normal start-up 5
time

Linkage between start-up after


Meet the requirements of the drawing Observation
pump and outlet valve

Listening to and
Normal,zero friction; without
Operation condition monitoring the gauge
abnormal vibration and shock
needle, hand feeling
Motor trial
Pressure of delivery side of Measure with pressure
run dominant Reach to rated value and keep stable
pump gage

n<250r/min dominant mm 0.15 Vertical and horizontal


direction measurement
Bear n=250r/min~600r/min dominant mm 0.10 of motor upper spider;
vibration horizontal direction

n>600r/min dominant mm 0.08 measurement of stator


housing

A small amount of fresh water; normal


Shaft seal Observation, hand test
temperature

Bearing temperature by Measurement by


80
adopting lubricant thermometer

Bearing temperature by Measurement by


70
adopting lubricant thermometer

Blade angle adjustment test Meet the requirements of manufacturer

Continuous trial run duration h 4~8 Timing

4.3.30 See table 4.3.30 for inspection and acceptance of common fan installation
Table 4.3.30 Common fan installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Fan check Scatheless, hand disc block-free Observation

Blower Elevation deviation mm 10 Gradienter

108
installation Measuring with levelling
Levelness deviation mm/m 2
rod

Vertical distance between


drain pipe outlet and stator mm 1500 Steel tape measurement
shell bottom

Water seal height of drain 50 20 higher than the blower wind


mm Steel tape measurement
pipe exit pressure

Measurement by using
>0.5%,In opposite direction with the
Installation of exhaust pipe dominant levelling rod and straight
gas flow
steel ruler

4.3.31 See table 4.3. 31 for blower trial run, inspection and acceptance.
Table 4.3.31 Blower trial run
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of


Starting time
manufacturer

Meet the requirements of


Pickup current dominant
Blower manufacturer
trial run Zero friction,water impact and
Operation condition Observation, hand feeling
without abnormal vibration

Measurement by using
Inlet negative pressure dominant Reaching the design value
vacuum meter

Trial run timing h 4~8 Timing

4.3.32 See table 4.3.32 for accessory machinery coupling assembly and centre align
inspection and acceptance.
Table 4.3.32 Accessory machinery coupling assembly and centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Cool
Coupling and mm 0~0.02
housing Measure with vernier
shaft assembly
Hot caliper
Assembly gap mm -0.02~0
housing
and
Contact between spindle
check Even distribution of imprint Paiting inspection
nose with taper and coupling

Radial flutter mm 0.06


Measure with dial gauge
Floating displacement mm 0.06

Coupling Radial dominant mm Fixed :0.04,Unfixed :0.06 Maximum value of dial


center n3000 End gauge or feeler gauge
dominant mm Fixed :0.03,Unfixed :0.04
allowable surface measurement for
deviation separation
Radial dominant mm fixed:0.06,unfixed:0.10
3000>n1500 End
dominant mm fixed:0.04,unfixed:0.06
surface

109
Radial dominant mm fixed:0.10,unfixed:0.12
1500>w^750 End
dominant mm fixed:0.05,unfixed:0.08
surface

Radial dominant mm fixed:0.12,unfixed:0.16


750>n>500 End
dominant mm fixed:0.06,unfixed:0.10
surface

Radial dominant mm fixed:0.16,unfixed:0.24


n<500 End
dominant mm fixed:0.08,unfixed:0.15
surface

Checking according to
Fuel inlet nozzle direction Correct
drawing

Toothed sleeve movement


Gear value Meet the requirements of manufacturer
coupling
End surface distance

Enclosure tightness Closeness and no leakage Observation

Lubricant (grease) Meet the requirements of manufacturer

Elastic ring and dowel pin Measure with vernier


mm 0.20~0.40
tightening force caliper
Elastic Elastic ring external Measure with vernier
mm 0.20
rang diameter deviation caliper
dowel pin Measurement carried out
coupling Elastic ring and coupling when elastic ring is on
mm 0.5~1.0
hole unilateral space the same side of coupling
hole

4.3.33 See table 4.3.33 for installation, inspection and acceptance of integrated device
Table 4.3.33 Installation of integrated device
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Equipment appearance Clean,in good condition without scar Observation and check
inspection and with complete components with drawing

Canning equipment Clean and without welding slag,


dominant Observation
inspection welding beading and sundries

Clean,transparent and with protective


Liquidometer inspection Observation
Equipment hood

inspection Check of instrument,


In good condition and meeting
transmitter and signal Observation
manufacturer's requirements
indicator

Right position; specification meeting the Observation and


Joint check
requirements of the drawing measurement

Valve inspection Actuator and accurate actuator Observation

Elevation deviation mm 10 Measurement in

Center line deviation mm 10 accordance with

110
reference line

Level Bubble centered Iron spirit level

In accordance with provisions of table


Foundation, iron gasket, stone bolt
4.3. 18 and table 4.3. 19

Installing equipment Meet the requirements of manufacturer

In accordance with provisions of table


Secondary grouting
4.3. 20

In order, nice,flat, smooth and be in


Manufacture of platform, ladder and accordance with technological
Observation
handrail requirements; in accordance with
provisions of table 4.3. 37

4.3.34 See table 4.3.34 for inspection and acceptance of common heat exchanger.
Table 4.3.34 Check of common heat exchanger
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean,rustless,scatheless,flawless and
a
Appearance inspection without sundries, bleb and double Observation
skin

Tube bundle and overheat


Clear passage and right pathway Compressed air check
belt sealing box

Position of steam baffle;


Match drawing Observation
water chamber pathway

Water chamber and tube


Without short circuit Observation
bundle parting sheet

Flat, smooth and without drop pit and


Packing strip Observation
radial trench
Tubular
Tube bundle parting sheet
exchanger Block-free during suspension Observation
and lock assembling

Appearance of flange bolt Rustless; without crack and injury Observation

Even gap around; nut is at the same


Inspecting with a feeler
Flange bolt fastening side of flange; 2~3 threads are
gauge
protruding

Clean, flawless, enough expansion


Movable support clearance, flat, smooth surfac, burr Observation
free and without welding beading

10 minuts check for test


pressure stipulated on the
Hydraulic pressure test dominant No leakage manufacturer nameplate or
minituts check with 1.25
times of working pressure

a Cooler is divided into plate type and tubular type; whole supply without on-site disassembly. If on-site disassembly is carried
out, refer to the requirements of manufacturer; only take water pressure test and appearance inspection for baffle heater.

4.3.35 See table 4.3. 35 for installation, inspection and acceptance of common heat

111
exchanger.
Table 4.3.35 Common heat exchanger installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Center line deviation mm 10 Steel tape measurement

Elevation deviation mm 10 Measuring with level

Levelness deviation Levelling rod,plumb bob or


mm/m 2
Perpendicularity deviation straight rule measurement

In accordance with provisions of table


Installation of iron gasket
4.3. 19

Check after soaking in water


Tightness of floating pipe No leakage
for 24 H

Floating pipe operation Flexible and block-free Manual test

Full Good contact, flexible and reliable


Valve spool and valve seat dominant Paiting inspection
water operation
protective
Signal transmitter Flexible and block-free Manual test
device

carry out water pressure test


Welded joint and flange tightness test dominant No leakage at the heat exchanger steam
side in the meanwhile

Electric steam trap overhaul


Meet the requirements of manufacturer
installation

Safety gate actuating pressure dominant Meet the requirements of manufacturer Hydraulic pressure test

Complete and tighted water level


Pointer Observation
gauge

Secondary pouring In accordance with table 4.3. 20

Horizontal heater roller wheel and


Even contact and no cavity Observation
guide track

4.3.36 See table 4.3.36 for installation, inspection and acceptance of common tank container
Table 4.3.36 Installation of common tank container
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Tank container with Smooth surface,and free from flaw and


Observation
Foundation ground jack looseness
inspection Tank container with flat Levelling mortar and cladding damp
Observation
bottom proof course of asphalt

10 minuts check for test


pressure stipulated on the
Tightness
Pressure tank dominant No leakage manufacturer nameplate or
test
minituts check with 1.25
times of working pressure

112
Inspecting after 24h
No-pressure water tank No leakage
watering

Elevation deviation mm 10 Measuring with level

Center line deviation mm 10 Steel tape measurement

Perpendicularity deviation Measuring with levelling


mm/m 2
Levelness deviation rod

Check in comparison with


Interface direction Meet the requirements of the drawing
Tank drawing
container
Water level gauge Complete mounting, No leakage Observation
installation
Water level control device Flexible operation, No leakage Observation

Sampling tube Clear passage and right position Observation

Internal anticorrosive Complete and meet requirements of


Observation
coating drawing

In accordance with provisions of table


Secondary pouring
4.3. 20

4.3.37 See table 4.3.37 for manufacture, installation, inspection and acceptance of metal
member, steel platform, ladder, handrail and cover plate.
Table 4.3.37 Manufacture, installation, inspection and acceptance of metal member, steel platform, ladder,
handrail and cover plate.
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Deviation between base


and pillar support center mm 5 Steel tape measurement
line
Pillar Total height seton hammer
Perpendicularity deviation mm/m 1
measurement

Colddrawn steel, Steel tape


Tortuosity deviation mm/m 1
measurement

Platform elevation
mm 5 Measurement in accordance
deviation
with data grade and glass
Liner, binding beam
mm 5 tube gradienter
elevation deviation
Platform
Steel structure combination
supports deviation of mm/m 1.5,And total value is 15mm Steel tape measurement
diagonal line

Edge brattice mm Complete,height 100 Steel tape measurement

Handrail Levelness deviation mm/m 2,and the total height20mm Levelling rod measurement

Measuring with levelling


Support perpendicularity
mm/m 2 rod and along the total high
deviation
plumb bob

113
Burr free, without sharp edge, glib
turning, firm welding, filed and
Appearance Observation
strickled welded joints; stable
supports

Footboard interval Straight steel ruler


mm 5
deviation measurement

Footboard longitudinal
mm/m 10
Ladder levelness deviation Measuring with levelling

Footboard lateral levelness rod


mm/m <2
deviation

Edge brattice mm Complete,height shall 100 Steel tape measurement

Material of cover plate Checkered plate Observation

Weight of movable
kg/piece 30 Estimating
Cover plate covering plate
manufacture Installation of lifter and
Level with cover plate Observation
lewis hole

Discontinuity status Parallel and level, smooth and clean Observation

Upper side welded joint wearring


Metallic margin frame Observation
down
Cover plate
Expansion clearance mm 0.5~1.5 Observation
installation
No tilting at four corners; top level
Installation Observation
meet the requirements of the drawing

4.3.38 See table 4.3. 38 for inspection and acceptance of gear wheel (worm wheel) reducto
and increaser
Table 4.3.38 Check of gear wheel (worm wheel) reductor and increaser
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flawless; without slag inclusion,


casting sand and air hole; painting
appearance Observation
shall be cleaned up (oilproof paint may
not be cleaned)

Horizontal integration Scatheless; local gap after tightening Inspecting with a feeler
Case mm
surface the bolt <0.05 gauge
check
Scatheless; right installation, no leak of
Oil level gauge Observation
oil

Oil line, oleophobic hole Clean, clear and without leakage Observation

Check 24 H after oiling or


Tightness inspection dominant No leakage
pouring kerosene

Oil nozzle direction Direct at meshing position Observation

Smooth and clean tooth


Gear wheel (worm wheel) appearance surface,scatheless; without rust and Observation
crack

114
Gear Along the tooth depth 65%
wheel
Paiting inspection
contact Along the tooth depth 75%
face

Worm along the tooth height 60%


wheel
Paiting inspection
contact Along the tooth depth 65%
face

Multiple thread worm and worm


Position of ends shall be consistent Paiting inspection
wheel contact

L50 mm 0.09~0.17

L=51~80 mm 0.10~0.21

L=81~120 mm 0.13~0.26
Gear set
L=121~200 mm 0.17~0.34 Dial gauge measurement or
flank
L=201~320 mm 0.2~0.42 pressure fuse measurement
gap a
L=321~500 mm 0.26~0.53

L=501~800 mm 0.34~0.67

L=801~1250 mm 0.42~0.85

L140 mm 0.06~0.11
Worm L1=41~80 mm 0.09~0.19
wheel
L1=81~160 mm 0.13~0.26 Dial gauge measurement or
set
L1=161~320 mm 0.19~0.38 pressure fuse measurement
flank
gap b L1=321~630 mm 0.26~0.53

L1=631~1250 mm 0.38~0.75

In accordance with provisions of table


Bearing inspection
4.3. 22 and table 4.3. 23

Complete, noleak at joints, no ruption


Temperature element Observation, multimeter test
of the line

a L is cylindrical gear central distance or length of cone gear reference circle cone busbar; if the flank contact is not up to
standard, the manufacturer shall deal with it; manual rescrape is not allowed.
b L1Is worm wheel central distance

4.3.39 See table 4.3. 39 for steam turbine generator units general equipments installation
and implementation performance of compulsory provisions.
Table 4.3. 39 ( )Subsection projectTable of implementation performance of compulsory provisions
Unit engineering Installation of other equipments including steam Subsection project
name turbine generator units name

Project number Acceptance date Date

Delivery
SN Inspection item Related information
performance

Before filling water, it must thoroughly clean up internal rusty


1
scale, weld beading and foreign bodies. The internal anticorrosive

115
coating shall be paited according to design requirements or after the
study of technical section.

Before installing equipment, it must inspect equipment as required.


If there is damage or quality defect, it shall timely inform
organizations concerned of joint inspection. As for defect in
equipment manufacture, it shall contact the manufacturer for
treatment. If the installation quality fails to meet requirements due to
2
manufacturing quality, it shall be jointly negotiated among
construction organization, manufacturing organization, construction
or using organization; there shall be records as well as confirmation
and signature for construction, equipment inspection and defect
treatment after reaching installation quality standard.

When carrying out water pressure test on equipment, if it can only


observe condition of water pressure test by disassembling certain
3
parts and the permanent deformation may be caused on equipment
for this, it must carry out temporary strengthening work.

On the pressure vessel,access opening,welding pipe saddle,belt


4 adding,covering as well as using pipes as the support point for other
heavy things hoisting,which are all prohibited to carry out randomly

Acceptance
conclusion:

Construction organization:(Seal) Supervision organization:(Seal)

Project technical director: Supervising engineer :

Date Date

4.4 Steam turbine main body installation


4.4.1 Installation of bearing seat (box) and bearing bush
Application scope: steam turbine main body bearing, thrust bearing, installation of
bearing seat, including Bearing seat positioning and centering, Clearance measurement and
adjustment of bearing bush and oil catch, thrust bearing gap adjustment and earing
seat covering.
1 Inspection and acceptance of Bearing seat positioning and centering shall refer to
table 4.4.1-1.
Table 4.4.1-1 Bearing seat positioning and centering
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Deviation between bearing seat center


mm Usually1 Tape check
and Delivery base center line

Meeting the requirements on thickness


Bearing seat elevation mm specified in drawings, with deviation of Measuring with level
5

Relative position of bearing seat and With largest thermal expansion, sliding
dominant Observation
pedestal surface of bearing seat are not protruding

116
the pedestal edge but with some surplus

Bearing seat slippage dominant mm Meet the requirements of manufacturer Measure with dial gauge

Meet the requirements of


Transverse levelness mm/m Gradienter measurement:a
manufacturer,and 0.20
Bearing
After bore centre align,use
seat
Longitudinal level mm/m Shaft neck lift as benchmark gradienter for
measurement

2 See table 4.4.1-2 and figure 4.4.1 for inspection and acceptance of clearance
measurement and adjustment of bearing bush and oil catch
Table 4.4.1-2 Clearance measurement and adjustment of bearing bush and oil catch
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Axial Adjustment end a Meet the requirements of manufacturer Straight steel ruler
mm
clearance Electricity end b Meet the requirements of manufacturer measurement

Feeler gauge
Gap at both sides Meet the requirements of manufacturer
measurement

Top gap c dominant mm Meet the requirements of manufacturer Pressure fuse, outside
micrometer, Feeler gauge
Tightening force of bearing bush d Meet the requirements of manufacturer
measurement

Bearing bore contact face dominant 75%, and even Paiting inspection

Upper part T Meet the requirements of manufacturer


Oil catch Feeler gauge
Two sides L, R dominant mm Meet the requirements of manufacturer
gap e measurement
Lower part B Meet the requirements of manufacturer

Figure 4.4.1 Bearing bush and oil catch gap


3 See table 4.4.1-3 for inspection and acceptance of Clearance measurement and
adjustment of thrust bearing
Table 4.4.1-3 Clearance measurement and adjustment of thrust bearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

117
Smooth surface,burr free, without drop
Pad appearance inspection Observation
pit, scratch and mechanical damage

PT check or coal-soaked
Pad bodiless check Bodiless black bronze
oil (4h~8h)

Meet the requirements of Outside micrometer or


Pad thickness difference mm
manufacturer,usually0.02 dial gauge measurement

Smooth, burr free and without passage


Bearing area Observation
Thrust mark
pad Measure the thickness of
support all points along the
Degree difference mm 0.02
ring perimeter by using outside
micrometer

Thrust Contact face dominant >70% Paiting method inspection


pad
support
Horizontal integration 0.05,Local tuck in depth less than or Inspecting with a feeler
ring and dominant mm
surface local gap equal to 10% of spheric radius gauge
tilting
fillet

Contact between tile pad and oil inlet Contact tightly at all sides Paiting method inspection

Fuel inlet throttling orifice size Meet the requirements of manufacturer

Gradient chamfer of oil inlet and out


Meet the requirements of manufacturer
let of thrust pad

Thrust the rotor back and


forth after assembling; use
Thrust gap dominant mm Meet the requirements of manufacturer
dial gauge for
measurement

Contact area of every block of thrust


dominant 75% Paiting method inspection
segment (not including oil wedge)

Feeler gauge
Oil seal ring total clearance mm Meet the requirements of manufacturer
measurement

4 See table 4.4.1-4 for check of bearing seat covering.


Table 4.4.1-4 Bearing seat covering
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of manufacturer


Close clearance between coupling and Straight steel ruler
dominant mm And meet requirements of thermal
housing volume measurement
expansion

Cleaning and check within bearing


Complete, clean and impurity-free parts Observation
seat

Jacking oil pipe and installation of


dominant Finished installation Observation
temperature measuring equipment

Pressure fuse, Feeler


Tightening force of bearing cover Meet the requirements of manufacturer
gauge measurement

118
Bearing cover joint surface paint Painting sealing gum Observation

Joint surface bolt Fastening and well match with nut Observation

Radial clearance between oil deflector Feeler gauge


mm 1~1.5
ring outside feel and axle measurement

4.4.2 Steam cylindr cleaning and check


Application scope:steam turbine main body and rotor cleaning and check,
includingCleaning and check of low pressure cylinder,Cleaning and check of high and
intermediate pressure cylinder,Cleaning and check of inner cylinder steam inlet pipe,Check of
high and medium pressure cylinder nozzle box, parting sheet (suit), steam seal (suit),Check of
low pressure cylinder admission chamber, parting sheet(suit) and steam seal (suit).
1 Check of cleaning and check of low pressure cylinder refer to table 4.4.2-1.
Table 4.4.2-1 Cleaning and check of low pressure cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flawless and without slag inclusion, Use 5~ 10times magnifier


Steam cylindr appearance inspection dominant
double skin, welding beading and injury for observation

Steam Flat, smooth,burr free clean out


cylindr and Appearance anticorrosive coating and without Observation
pedestal mechanical damage
sliding Painting, inspecting with
Contact face mm Even contact and <0.05
surface a feeler gauge

Smooth, rustless and without dirt;


Check of horizontal and vertical joint
dominant anticorrosive coating shall all be cleaned Observation
surface
out

Complete circuit continuous contact


Pipe flange contact face on the steam
dominant without a break;there shall be certain Paiting method inspection
cylindr
width

Appearance inspection dominant Smooth screw thread,burr free,scatheless Observation

Suitable elasticity; tighten the nut by


Bolt and nut dominant Observation
hand
Bolt hole
Bolt hole, studding hole dominant No shifting Observation
studding
Lower studding shall be all within the
Studding bolt dominant steam cylindr flange; the upper studding Observation
shall below flange surface

Diaphragm and contact Flat, smooth, without paint, temporary


Observation
surface of valve seat press plate dismantled

Diaphragm compaction
Aerography Cultrated Observation
circle edge corner angle
safety gate
Material and thickness of
diaphragm type safety Meet the requirements of manufacturer
gate diaphragm

2 See table 4.4.2-2 for the check of cleaning and check of high and intermediate

119
pressure cylinder.
Table 4.4.2-2 Cleaning and check of high and intermediate pressure cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flawless and without slag inclusion, Use 5~ 10times magnifier


Steam cylindr appearance inspection dominant
double skin, welding beading and injury for observation

Smooth, rustless and without dirt;


Horizontal integration surface check dominant anticorrosive coating shall all be cleaned Observation
out

No casting sand, scrap iron and other


Inside of steam chamber dominant Endoscopy
attachment

Complete circuit continuous contact


Pipe flange contact face on the steam
dominant without a break;there shall be certain Paiting method inspection
cylindr
width

Appearance inspection dominant Smooth screw thread,burr free,scatheless Observation

Suitable elasticity; tighten the nut by


Bolt and nut dominant Observation
hand
Bolt hole
Bolt hole, studding hole dominant No shifting Observation
studding
Lower studding shall be all within the
Studding bolt dominant steam cylindr flange; the upper studding Observation
shall below flange surface

3 Check of cleaning and check of high and medium pressure inner cylinder steam inlet
pipe refer to table 4.4.2-3.
Table 4.4.2-3 Cleaning and check of high and medium pressure inner cylinder steam inlet pipe
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Steam inlet pipe and seam inside


Impurity-free and without scrap iron Observation
cleaning

Appearance of steam inlet pipe sealing Observation and hand


Flat, smooth, clean and burr free
ring tank feeling check

Total clearance between steam inlet


Internal and external
pipe sealing ring and both sides of mm Meet the requirements of manufacturer
miking
tank

Enlarge the debouchment


ElasticProperty All right to specified value; recover

Steam after unlashing

inlet pipe Put the sealing ring within


sealing Debouchment gap mm Meet the requirements of manufacturer the nozzle box casing for
ring check

Adjacent debouchment staggered for


Installation direction Observation
180

Axial clearance between upside-down Straight steel ruler


mm Meet the requirements of manufacturer
cylinder steam inlet pipe and steam measurement

120
inlet

4 Check of high and medium pressure cylinder nozzle box, parting sheet (suit), steam
seal (suit) see able 4.4.24.
Table 4.4.2-4 Check of high and medium pressure cylinder nozzle box, parting sheet (suit), steam seal
(suit)
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flawless and be without injury, painting,


Nozzle box appearance
oil stain and rust; the surface shall expose Observation
inspection
metallic luster
High and
Nozzle box horizontal Tighten bolt,Inspecting
medium dominant mm <0.05
integration gap with a feeler gauge
pressure
Upside-down nozzle box No radial mismatch; no notable axial Observation and hand
cylinder
mismatch mismatch feeling check

Total clearance between Measure with vernier


mm Meet the requirements of manufacturer
split seal key and tank caliper

No casting sand; without crack,welding


beading, painting, oil stain and rust; the
Parting sheet (suit), steam seal (suit)
surface shall expose metallic luster; the Observation
appearance inspection
steam seal tooth edge shall be flat,
smooth and without curl

Horizontal integration surface gap


Tighten bolt,Inspecting
between parting sheet (suit) and gland dominant mm <0.05
with a feeler gauge
sleeve

Loose bolt, Inspecting


Parting sheet diagonal plane gap mm Meet the requirements of manufacturer
with a feeler gauge

Parting sheet (suit), gland sleeve No radial mismatch; no notable axial Observation and hand
mismatch mismatch feeling check

Superlevation between parting sheet Use flat bevel scale for


mm Meet the requirements of manufacturer
suspension loop and casing split measurement

Meet the requirements of


Coordination among parting sheet
manufacturer,Suitable coordination Observation
(suit), gland sleeve pin and pin hole
elasticity

Smooth and clean, burr free and be Observation and hand


Parting sheet and tank joint surface
without oil stain feeling

Parting sheet steam stopping strip, Complete, no shortage andcrimping;


Observation
sealing strip sharpen edge

Lower parting sheet (suit) drainage


It shall be clear Observation, air blowing
hole check

5 Check of low pressure cylinder admission chamber, parting sheet(suit) and steam
seal (suit) see table 4.4.2-5.
Table 4.4.2-5 Check of low pressure cylinder admission chamber, parting sheet(suit) and steam seal (suit)

Inspection item Property Unit Quality criteria Inspection method and

121
measuring instrument

Do not install in a counter position; make Check in accordance with


Low Position of shunt ring
it drawing
pressure
Gap between all parts of
cylinder Meet the requirements of manufacturer Measurement check
shunt ring

No casting sand; without crack,welding


beading, painting, oil stain and rust; the
Parting sheet (suit), steam seal (suit)
surface shall expose metallic luster; the Observation
appearance inspection
steam seal tooth edge shall be flat,
smooth and without curl

Horizontal integration surface gap


Tighten bolt,Inspecting
between parting sheet (suit) and gland dominant mm <0.05
with a feeler gauge
sleeve

Do not tighten the bolt;


Parting sheet diagonal plane gap mm Meet the requirements of manufacturer inspecting with a feeler
gauge

Parting sheet (suit), gland sleeve No radial mismatch; no notable axial Observation and hand
mismatch mismatch feeling check

Superlevation between parting sheet Use flat bevel scale and


mm Meet the requirements of manufacturer
suspension loop and casing split feeler gauge measurement

Meet the requirements of


Coordination among parting sheet
manufacturer; suitable coordination Observation
(suit), gland sleeve pin and pin hole
elasticity

Smooth and clean, burr free and be Observation and hand


Parting sheet and tank joint surface
without oil stain feeling

Parting sheet steam stopping strip, Complete, no shortage andcrimping;


Observation
sealing strip sharpen edge

Lower parting sheet (suit) drainage


It shall be clear Observation, air blowing
hole check

4.4.3 Check of turbinr rotor


Check of turbinr rotorsee table 4.4.3.
Table 4.4.3 Check of turbinr rotor
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance inspection of steam seal,


Smooth, rustless, without burr, crack, Inspecting with
shaft neck, thrust disc, gear wheel, worm
painting,grease and other injury magnifier by 5~10 times
gear and coupling

Weight and locking key on wheel hub;


center hole closure plate and other Locking, no looseness Reinspection
locking parts

No Looseness (loose vane for


Blade and duplicate loop exception), no injury, flat, smooth Observation
inlay, without tilting and protrusion

122
Opening inside shall be clean and
Inspecting with a feeler
Adjacent spider creep of shrunt on disc impurity-free; the gap shall meet the
gauge and record
requirements of manufacturer

Feeler gauge
Velocity level mm Meet the requirements of manufacturer
Adjacent two double measurement
ring expansion clearance Feeler gauge
Pressure level mm Meet the requirements of manufacturer
measurement

Check of rotor axial Floating


displacement,differential displacement
dominant mm 0.02 Measure with dial gauge
expansion and shaft
Flutter
vibration

In accordance with manufacturer


Rotor tortuosity mm Measure with dial gauge
assembly record and 0.06

Ellipticity
Measurement by using
Shaft neck Non-cylindrical dominant mm 0.02
outside micrometer
degree

Flutter dominant mm 0.03 Measure with dial gauge


Thrust disc Floating
dominant mm 0.01 % of the thrust disc radius Measure with dial gauge
displacement

Coupling floating Stiffness dominant mm 0.02 Measure with dial gauge

displacement Semi-stiffness dominant mm 0.03 Measure with dial gauge

Radial flutter at journal oil block of the


dominant mm 0.10 Testing with dial gauge
belt joint long axis

Shrink-fitting shall be firm and without


Main shaft sealing strip Observation
distortion and injury

Clean inside, without welding slag,


Coupling waved tube scrap iron or other sundries, with oil Observation
catch hole

Measurement of internal
Coupling spigot coordination Meet the requirements of manufacturer diameter by using
outside micrometer

Check of spigot excircle


Coupling flange spigot radial flutter dominant mm 0.02 and inner circle by using
dial gauge

4.4.4 Steam cylindr combination positioning


Application scope: steam turbine main body low pressure cylinder and high-medium
pressure cylinder combination, joint surface clearance inspection and steam cylindr
positioning and centering, including low pressure cylinder combination, joint surface
clearance inspection, high and medium pressure cylinder combination,joint surface clearance
inspection and steam cylindr positioning and centering.
1 Check of low pressure cylinder combination, joint surface clearance inspection refer
to table 4.4.4-1.
Table 4.4.4-1 Low pressure cylinder combination, joint surface clearance inspection

123
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Casing split and bearing Communicating pipe or


dominant mm Meet the requirements of manufacturer
seat superlevation measuring with level

Gap between end plate and Inspecting with a feeler


mm Meet the requirements of manufacturer
side plate welded joints gauge
Welding
End plate and side plate
steam Meet the requirements of manufacturer Observation
weld groove type
cylindr and
Diagonal line dominant mm Meet the requirements of manufacturer Measuring with tape
patching
Steam Lateral dimension dominant mm Meet the requirements of manufacturer Measuring with tape
cylinder
cylindr Longitudinal size dominant mm Meet the requirements of manufacturer Measuring with tape
combination
patching Lug hole Measuring with inside
mm Upside-down, right and left 0.5
cylinder deviation micrometer
size Guide finger Measuring with inside
mm Upside-down, right and left 0.5
position deviation micrometer

Adjacent two stage steam Upper, lower cylinder fit together and
Check
Flange cylindr mismatch volume be in accordance with ex-work record

steam Bolt up force moment Meet the requirements of manufacturer Torque spanner
cylindr and Lock it before sealing. If one use
patching Vertical joint surface nut electric welding for locking; carry out
cylinder and steam cylindr spot dominant spot welding at nut and cylinder wall. Observation
combination welding Set seal welding position stipulated in
the requirements shall also be done.

Connection between cylindr steam


Joint shall meet the requirements of
exhaust section and condenser or short Observation
manufacturer
piece

Inspecting with a feeler gauge. At the


Inside low pressure; As for the cold tightening
Steam same cross-section of steam cylindr
vertical outer shell and one third bolt, use the
cylindr joint dominant mm flange, the tuck in length sum both from
horizontal integration feeler gauge for
surface internal and external shall not exceed
surface inspecting.
1/3 of the steam cylindr flange width.

Horizontal integration surface bolt and Inspecting with a feeler


mm 0.05
gap around bolt hole gauge

Check of depth gauge or


Sheath-type nut and bolt top clearance mm 2
straight steel ruler

Screw thread out of the nut Thread 2~3 Observation

2 See table 4.4.4-2 for high and medium pressure cylinder combination and the
clearance inspection, acceptance of joint surface.
Table 4.4.4-2 Clearance inspection of high and medium pressure cylinder combination and joint surface
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Steam
cylindr Horizontal integration dominant mm 0.03 feeler gauge cannot be tucked in As for the cold tightening
surface gap of high both from internal and external sides one third bolt, use the
124
pressure inside and outside feeler gauge for
cylinder. inspecting.
joint Inside low pressure; 0.05 feeler gauge shall not be tucked in As for the cold tightening
surface vertical outer shell and both from internal and external sides; the one third bolt, use the
dominant mm
horizontal integration certain tucked in part shall not exceed feeler gauge for
surface 1/3 of the packing strip width. inspecting.

Horizontal integration surface bolt and Inspecting with a feeler


mm 0.50
gap around bolt hole gauge

Check of depth gauge or


Sheath-type nut and bolt top clearance mm 2
straight steel ruler

Screw thread out of the nut Thread 2~3 Observation

3 See table 4.4.4-3 for positioning, centering, inspection and acceptance of steam
cylindr
Table 4.4.4-3 Positioning and centering of steam cylindr
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Deviation between steam cylinder Plumb bob, steel tape and


mm Usually 1
center and delivery base center line steel wire

Relative position of steam cylinder Meet the requirements of machine unit


Observation
and pedestal expansion

Meet the requirements of the drawing and


Casing split elevation mm Measuring with level
the deviation shall 5

Meet the requirements of manufacturer combined diagram


Steam cylinder lateral level mm/m
and0.20 gradienter measurement

After bore centre align,use


combined diagram
Steam cylinder longitudinal level mm/m Shaft neck lift as benchmark
gradienter for
measurement

Measurement by using
large leveling rule,
coincidence level,
Steam cylinder planeness mm/m 0.20
precision level, horizontal
pipe and depth
micrometer

Direction and gap of contact bolt and


Meet requirements of cylinder expansion Observation
bolt hole expansion direction

4.4.5 Aggregate installation of steam cylindr internal component


Application scope: steam turbine main body steam cylindr internal component aggregate
installation, including bearing seat,steam cylinder and rotor centre align, Installation of low
pressure inner cylinder, high and medium pressure inner cylinder installation, high pressure
nozzle box installation, high, medium and low pressure cylinder parting sheet (suit), balance
piston (loop), steam admission shunt ring, gland sleeve installation, low pressure cylinder
inside component bore centre align, high and medium pressure cylinder inside component

125
bore centre align.
1 Check and acceptance of centre alignment of bearing seat, steam cylindr and rotor refer
to table 4.4.5-1.
Table 4.4.5-1 Centre alignment of bearing seat, steam cylindr and rotor
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Deviation between Right and left )


dominant mm
front and rear (a-b)
bearing seat oil
catch center of
Bottom
high and medium dominant mm
c-[(a+b)/2]
pressure cylinder
and shaft axis.

Deviation between Right and left )


dominant mm
front and rear (a-b)
bearing seat oil
catch center of low Bottom
dominant mm
pressure cylinder c-[(a+b)/2]
and shaft axis.

High and medium Right and left )


dominant mm
pressure outer (a-b)
cylinder reference
steam seal bore Bottom
dominant mm After positioning of rotor,
and axle center c-[(a+b)/2] Meet the requirements of
the measurement of inside
deviation manufacturer,usually0.10
micrometer or dial gauge
High and medium Right and left )
dominant mm
pressure inner (a-b)
cylinder bore and
Bottom
axle center dominant mm
c-[(a+b)/2]
deviation

Center deviation Right and left )


dominant mm
between low (a-b)
pressure outer
cylinder reference Bottom
dominant mm
steam seal and axle c-[(a+b)/2]
center deviation

Center deviation Right and left )


dominant mm
between low (a-b)
pressure inner
cylinder bore and Bottom
dominant mm
axle center c-[(a+b)/2]
deviation

Note: a and b are right and left side clearance of horizontal split; c is top clearance

126
2 Check and acceptance of installation of low pressure inner cylinder refer to table
4.4.5-2.
Table 4.4.5-2 Installation of low pressure inner cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inner cylinder positioning key (Pin) Measuring with inside


dominant mm Meet the requirements of manufacturer
assemblage gap and outside micrometer

Measurement by using
Bracing stud gap at both sides of inner feeler gauge, inside and
dominant mm Meet the requirements of manufacturer
cylinder outside micrometer and
gauge

Measurement by using
Axial positioning key gap dominant mm Meet the requirements of manufacturer feeler gauge or dial
indicator

Steam cylinder joint surface dowel pin Measuring with inside


dominant mm Meet the requirements of manufacturer
assemblage gap and outside micrometer

Measuring with inside


Bottom centre pin assemblage gap dominant mm Meet the requirements of manufacturer
and outside micrometer

Gap between communicating pipe


Feeler gauge
joint and outer cylinder positioning dominant mm Meet the requirements of manufacturer
measurement
key

Inner cylinder steam inlet dowel pin Feeler gauge


dominant mm Meet the requirements of manufacturer
gap measurement

Measurement of feeler
Assemblage gap of the extraction
dominant mm Meet the requirements of manufacturer gauge and depth
point
micrometer

3 See table 4.4.5-3 for installation, inspection and acceptance of high and medium
pressure inner cylinder.
Table 4.4.5-3 Installation of high and medium pressure inner cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inner cylinder positioning key (Pin) Measuring with inside


dominant mm Meet the requirements of manufacturer
assemblage gap and outside micrometer

Measurement by using
Bracing stud gap at both sides of feeler gauge, inside and
dominant mm Meet the requirements of manufacturer
inner cylinder outside micrometer and
gauge

Measurement by using
Axial positioning key gap dominant mm Meet the requirements of manufacturer feeler gauge or dial
indicator

Steam cylinder joint surface dowel Measuring with inside


dominant mm Meet the requirements of manufacturer
pin assemblage gap and outside micrometer

Assemblage gap of the extraction dominant mm Meet the requirements of manufacturer Measurement of feeler

127
point gauge and depth
micrometer

4 See table 4.4.54 for installation, inspection and acceptance of high pressure nozzle
box
Table 4.4.5-4 Installation of high pressure nozzle box
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with provisions of table


Check of steam inlet pipe dominant
4.4.2-3

Inspecting with a feeler


Split gap dominant mm <0.03 gauge after tightening the
bolt

Total clearance at both sides of


dominant mm Meet the requirements of manufacturer
upside-down longitudinal stud

With inner cylinder


Supportting dominant mm Compact contact, gap <0.05
supporting surface
key at both Feeler gauge
Surface gap with upper
sides dominant mm Meet the requirements of manufacturer measurement
inner cylinder

Gap at axial location tank dominant mm Meet the requirements of manufacturer

5 See table 4.4.5-5 for installation of high and medium pressure cylinder parting sheet(suit),
balance piston (loop), steam admission shunt ring and gland sleeve.
Table 4.4.5-5 Installation of high and medium pressure cylinder parting sheet (suit), balance piston (loop),
steam admission shunt ring and gland sleeve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Radial clearance of steam inlet pipe Measuring with inside


mm Meet the requirements of manufacturer
sealing ring and outside micrometer

Axial clearance of steam inlet pipe Feeler gauge


mm Meet the requirements of manufacturer
sealing ring measurement

Expansion clearance at the end of Check of depth gauge or


mm Meet the requirements of manufacturer
steam inlet pipe straight steel ruler

Gap at both High and medium

sides of pressure inner cylinder


Measuring with inside
radial Diaphragm housing ring mm Meet the requirements of manufacturer
and outside micrometer
location Top and bottom of
stud balance piston loop

High and medium


Axial pressure inner cylinder
Measuring with inside
positioning mm Meet the requirements of manufacturer
Diaphragm housing ring and outside micrometer
key gap
Balance piston loop

Straight steel ruler


Size of gland sleeve axial location mm Meet the requirements of manufacturer
measurement

128
6 See table 4.4.5-6 for installation, inspection and acceptance of low pressure cylinder
parting sheet (suit), balance piston (loop), steam admission and gland sleeve. Table 4.4.5-6
Installation of low pressure cylinder parting sheet (suit), balance piston (loop), steam admission shunt ring
and gland sleeve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Radial clearance of steam inlet pipe Measuring with inside and


mm Meet the requirements of manufacturer
sealing ring outside micrometer

Axial clearance of steam inlet pipe Measuring with inside and


mm Meet the requirements of manufacturer
sealing ring outside micrometer

Expansion clearance at the end of Check of depth gauge or


mm Meet the requirements of manufacturer
steam inlet pipe straight steel ruler

Diaphragm housing
Gap at both
ring Measuring with inside and
sides of radial mm Meet the requirements of manufacturer
Top and bottom of outside micrometer
location stud
balance piston loop

Axial Diaphragm housing


Measuring with inside and
positioning key ring mm Meet the requirements of manufacturer
outside micrometer
gap Balance piston loop

Straight steel ruler


Size of gland sleeve axial location Meet the requirements of manufacturer
measurement

7 See table 4.4.5-7 for inspection and acceptance of low pressure cylinder inside bore
centre align.
Table 4.4.5-7 Low pressure cylinder inside component bore centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Right and left


Diaphragm dominant mm
(a-b) Meet the requirements of manufacturer
housing
Bottom and deviation 0.05
ring dominant nun
c-[(a+b)/2]

Center Right and left )


Steam dominant mm
deviation of (a-b) Meet the requirements of manufacturer Use manufacturer
admission
each Bottom and deviation 0.05 reference bore line of
shunt ring dominant mm
components c-[(a+b)/2] centres as reference;
within the Steam Right and left carry out miking by
dominant mm
low exhaust (a-b) Meet the requirements of manufacturer using rotor, colddrawn
pressure deflector Bottom And deviation 0.05 steel wire and laser laser.
dominant mm
cylinder ring c-[(a+b)/2]

Right and left


dominant mm
Steam seal (a-b) Meet the requirements of manufacturer
(suit) Bottom and the deviation0.05
dominant mm
c-[(a+b)/2]

8 See table 4.4.5-8 for inspection and acceptance of high and medium pressure

129
cylinder inside bore centre align.
Table 4.4.5-8 High and medium pressure cylinder internal component bore centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Right and left


dominant mm
Nozzle (a-b) Meet the requirements of manufacturer
group Bottom and deviation0.05
dominant mm
c-[(a+b)/2]

Center Parting Right and left


dominant mm
deviation of sheet (a-b)
Meet the requirements of manufacturer Use manufacturer
each (diaphragm
Bottom and the deviation 0.05 reference bore line of
components housing dominant mm
c-[(a+b)/2] centres as reference;
within the ring)
carry out miking by
high and Right and left
Balance dominant mm using rotor, colddrawn
medium (a-b) Meet the requirements of manufacturer
piston steel wire and laser laser.
pressure Bottom and the deviation0.05
(loop) dominant nun
cylinder c-[(a+b)/2]

Right and left


dominant mm
Steam seal (a-b) Meet the requirements of manufacturer
(suit) Bottom and the deviation0.05
dominant mm
c-[(a+b)/2]

4.4.6 See table 4.4.6 for the inspection and acceptance of steam cylinder load distribution
Table 4.4.6 Steam cylinder load distribution
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inspecting with a
Lug filling block bearing area and
dominant mm Good contact, the gap shall be <0.05 feeler gauge at both
sliding surface
ends

Lug droop arc method distribution


Meet the requirements of Dial gauge measurement
loading; lug right and left catenary dominant mm
manufacturer,usually it shall be0.10 take two catenary arc
arc difference

Dynamometer Front
Midair cylinder with
method load
Meet the requirements of manufacturer rotor; use dynamometer
distribution ratio Back
method for check
(cross ratio)

Loading difference of center line


5%
position of symmetry

Meet the requirements of


Transverse mm/m
manufacturer,and0.20
Steam cylinder combined diagram
Meet the requirements of
level gradienter measurement
Longitudinal mm/m manufacturer,Usually the rotor journal lift
shall be the benchmark

Lug contact bolt debouncing gap mm Meet the requirements of manufacturer Inspecting with a feeler

130
gauge

Meet the requirements of


Straight steel ruler
Lug bolt hole and bolt around gap mm manufacturer,And shall meet requirements
measurement
of thermal expansion.

4.4.7 See table 4.4.7 for adjustment, inspection and acceptance of flow passage part
clearance measurement. See Annex A for data of manufacturer steam turbine flow passage
part.
Table 4.4.7 Flow passage part clearance measurement adjustment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Blade tip clearance at steam


dominant mm Meet the requirements of manufacturer
admission side F

Blade tip clearance at outlet


dominant mm Meet the requirements of manufacturer Measure rotor flow
steam side E
passage at 0and 90. Use
Blade root gap at steam
dominant mm Meet the requirements of manufacturer feeler gauge or weage
admission side A
Axial feeler gauge to measure
Blade root gap at outlet
clearance dominant mm Meet the requirements of manufacturer axial clearanc; use feeler
steam side B
gauge for measurement
Axial clearance at steam
of radial clearance;stick
seal tooth steam admission dominant mm Meet the requirements of manufacturer
rubberized fabric for the
side
check of the complete
Axial clearance at steam
dominant mm Meet the requirements of manufacturer solid cylinder status.
seal tooth outlet steam side

Radial Block steam radial gland dominant mm Meet the requirements of manufacturer

clearance Parting sheet radial gland dominant mm Meet the requirements of manufacturer

Steam seal block circumference Depth gauge


dominant mm Meet the requirements of manufacturer
expansion clearance measurement

Use feeler gauge or


Rotor location dimension k value dominant mm Meet the requirements of manufacturer weage feeler gauge for
measurement

If rotor is positioned
according to k value.
Make the measurement
Minimum axial throughflow clearance dominant mm Meet the requirements of manufacturer and push the rotor under
the conditions of half
solid cylinder and
complete solid cylinder.

4.4.8 See table 4.4.8 for measurement,adjustment, inspection and acceptance of labyrinth
clearance.
Table 4.4.8 Measurement and adjustment of labyrinth clearance
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Balance Stage Use feeler gauge, weage


Seal tooth axial dominant mm Meet the requirements of

131
clearance manufacturer
piston
teeth
loop Steam seal tooth Meet the requirements of
dominant mm
steam radial clearance manufacturer
feeler gauge to measure axial
seal Flat Steam seal tooth Meet the requirements of clearance; use feeler gauge
dominant mm
tine radial clearance manufacturer to measure radial clearance;
Steam tooth axial Meet the requirements of stick rubberized fabric for
dominant mm
Stage clearance manufacturer check under the conditions
External teeth Steam seal tooth Meet the requirements of of complete solid cylinder.
dominant mm
gland radial clearance manufacturer

Flat Steam seal tooth Meet the requirements of


dominant mm
tine radial clearance manufacturer

Axial clearance of each gland casing


Meet the requirements of
arch section within the gland sleeve mm Measure with dial gauge
manufacturer
tank

Complete circuit expansion clearance


Meet the requirements of
of gland casing arch sectioninstalled mm Depth gauge measurement
manufacturer
in the gland sleeve tank

4.4.9 Steam turbine covering


Application scope: steam turbine covering, including check before steam turbine
covering and steam turbine covering.
1 See table 4.4.9-1 for inspection and acceptance before steam turbine covering.
Table 4.4.9-1 Check before steam turbine covering
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inside steam cylinder, inside pipeline


dominant Clean, impurity-free and hole seal
section and inside steam chamber
Observation
Pipe orfice, instrument table socket
dominant Reliable seal
and choke plug

Steam cylinder and component inside


Clean all the components; make all
cylinder (held loop, parting Observation and hand
dominant the joint surface smooth; burr free;
sheet,deflector ring, rotor and inner feeling
lock the loose components
cylinder)

Protective device and monitoring Checking completed; all installed


dominant Inspection
component within the steam cylinder before covering.

Nut needing hot tightening; the


contact plane with steam cylinder or dominant Closeness and even contact Paiting method inspection
gasket

Matching of screw bolt and nut shall


be smooth, burr free, too loose and too
Bolt, nut and studding hole of steam tight; high pressure cylinder bolt and Hand feeling and
dominant
cylinder nut shall all be with steel impression observation
mark and not be randomly
exchanged.

132
All shall be screwed in steam cylinder
flange; screw thread shall be lower
Screw thread part of steam cylinder than the flange surface; the verticality
dominant Observation
studding bolt of studding bolt and flange surface
shall meet the requirements of
manufacturer.

Bolt screw thread shall be 2-3 threads


Screw the bolt to the position of
out of the nut. When the shield nut is
installation (refer to the requirements
cooled and tightened to the installation
of manufacturer for exported machine dominant Observation
position, it shall ensure around 2mm
unit with requirements for tapered
clearance between top shield and top
bolt)
bolt after properly fastening.

2 Steam turbinecovering check see table 4.4.9-2.


Table 4.4.9-2 Steam turbine covering check
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

clean and impurity-free inside. Right


assembling position. The loose
component are finally locked. The
Full range supervision and
Steam cylindr internal component dominant loose and useless components are
air blowing
dismantled; part of hole channel are
clear; blocking and isolated parts are
partially blocked.

Protective device and monitoring All parts of covering are installed


dominant Inspection
component within the steam cylinder completely.

Painting combining position of spare


dominant Right and even painting Inspection
parts

Right painting; the thickness shall be


Paint laying at the steam cylinder in accordance with requirements by
Observation
horizontal integration surface paint manufacturer; the painting shall
be even

Total number of lug filling block shall


be less than or equal to 3; the contact
Temporarily support transformation
dominant mm shall be compacted;solid the steam Measure with dial gauge
of lug bracing the inner cylinder
cylinder center change before and
after transformation shall be 0.03.

Right tightening sequence, force


Observation and torque
Cold spring dominant moment shall meet the requirements
spanner
of manufacturer
Casing split Elongation indicator:
Right tightening sequence; bolt
bolt up measuring with special
elongation indicator or nut arc of
Hot tightening dominant measuring stick and depth
rotation length shall meet the
micrometer
requirements of manufacturer
Arc length:Measuring with

133
tape

Rolling rotor after steam turbine Uniform rotation in accordance with Rolling hand feeling,
covering actual situation; zero friction listening to the sound

Solid lug filling block bearing area


contact; area of0.05 feeler gauge
Feeler gauge both end
Upper lug bracing outer cylinder tucked in shall be less than or equal to
dominant mm check ; dial gauge
falsework transformation 10% of gross area; the steam cylinder
measurement
center change shall be 0.02 before
and after transformation.

4.4.10 Shafting adjustment and connection


Application scope: Shafting adjustment and connection, including coupling centre align
and coupling reaming connection.
1 See table 4.4.10-1 for inspection and acceptance of coupling centre align.
Table 4.4.10-1 Coupling centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with manufacturer


Coupling relative position mark; offset by floating displacement
if there is no marks

Deviation between center


actually measured
superlevation value and meet dominant mm 0.02
the requirements of Measurin with feeler gauge,
Coupling manufacturer reserve value chock or dial gauge
center
Right-left center deviation dominant mm 0.02
deviation
Deviation of measured lower
gape value and reserve value dominant mm 0.03
required by the manufacturer

Right-left gape deviation dominant mm 0.03

Meet the requirements of Checking with inside and


Rotor location dimension deviation nun
manufacturer outside micrometer

Coupling gasket thickness deviation mm 0.02 Outside micrometer check

Meet the requirements of combined diagram


Rotor journal lift mm/m
manufacturer gradienter measurement

2 See table 4.4.10-2 for inspection and acceptance of coupling reaming connection.
Table 4.4.10-2 Coupling reaming connection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Coupling center reinspection Meet the requirements of manufacturer

Reaming
coupling Shaking degree change mm 0.02 Measure with dial gauge
before coupling reaming
134
and temporary connection

Coupling reaming Right reaming order

Corresponding coupling
Measurement of internal
bolt hole diameter dominant mm Meet the requirements of manufacturer
diameter meter
deviation after reaming

Bolt hole surface roughness Observation

Bolt surface roughness Observation

Measurement of internal
Bolt and nut coordination dominant Meet the requirements of manufacturer diameter volume by using
outside micrometer

Coupling spigot gap or tightening Measuring with inside


mm Meet the requirements of manufacturer
force micrometer

Scale or electronic scale


Symmetrical bolt weight difference g/suit <10
weighing

Measuring external
Right tightening sequence, force diameter with depth
a
Bolt up dominant moment shall meet the requirements micrometer; torque
of manufacturer spanner or special tools
for hydraulic tensioning

When the rotor is in the


right axial position, the gap
Thickness deviation of
mm 0.02 between two couplings shall
gasket
be the benchmark; Measure

Axial with the block gauge

adjusting
Gasket roughness Observation
gasket

Appearance inspection of It shall be burr free and without crack


Observation
the gasket and oil stain

It shall be concentric to the coupling;


Gasket bolt hole Observation
reaming shall be carried out together

Use dial gauge for


Circumference flutter change before
dominant mm 0.02 measurement before and
and after coupling joint
after coupling connection

Assembly of coupling baffle and Correct assembling; complete; tightly


Observation
safety pin locked

Coordination between reaming Measurement of internal


coupling bolt and bolt hole is not Meet the requirements of manufacturer diameter by using outside
needed micrometer

a Generally, the bolt-up degree is measured by bolt elongation, fastening force moment or oil pressure of hydraulic tensioning
instrument

135
4.4.11 Sliding pin system clearance measurement and adjustment
Application scope: measurement and adjustment of sliding pin system clearance,
including sliding pin system gap adjustment, installation of bearing seat and steam cylinder
center beam and installation of pushing and pulling device.
1 See table 4.4.11-1 and figure 4.4.11 for the adjustment, inspection and acceptance of
Sliding pin system clearance measurement
Table 4.4.11-1 Sliding pin system clearance measurement and adjustment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Outer cylinder vertical 2a dominant mm Meet the requirements of manufacturer


See figure 4.4.11a for feeler
and horizontal king b dominant mm Meet the requirements of manufacturer
gauge and miking
pin c dominant mm Meet the requirements of manufacturer

2a dominant mm Meet the requirements of manufacturer


Bearing seat vertical, See figure 4.4.11b for feeler
b dominant mm Meet the requirements of manufacturer
lateral pin gauge and miking
c dominant mm Meet the requirements of manufacturer

a dominant mm Meet the requirements of manufacturer


Bearing seat pressure See Figure 4.4.11 c for feeler
b dominant mm Meet the requirements of manufacturer
pin gauge measurement
c dominant mm Meet the requirements of manufacturer

a dominant mm Meet the requirements of manufacturer Feeler gauge


Bearing seat contact
measurement,See figure
bolt b dominant mm Meet thermal displacement requirements
4.4.1 1d

Low pressure cylinder

Bearing seat
Platform plate
Locating plate

Low pressure cylinder

Platform plate
Locating plate

Low pressure cylinder end vertical pin gap Front and middle bearing seat vertical and horizontal pin gap

Bearing seat
Bearing seat

Pressure pin

Plateform seat

Platform plate

Front and middle bearing seat pressure pin gap Front and middle bearing seat connection bolt gap

Figure 4.4.11 Sliding pin system gap

136
2 See table 4.4.11-2 for the installation, inspection and acceptance of center beam
between bearing seat and steam cylinder.
Table 4.4.11-2 Installation of center beam between bearing seat and steam cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

The thickness is in accordance with


Configuration of center beam seat
manufacturer design without distortion Measuring and observing
sheet
and brute force installation

Center beam seat sheet joint surface Measuring connecting bolt


dominant mm <0.05
gap with feeler gauge

As for the center beam installation with


requirements for pre-offset volume, one
end shall be in accordance with
Center beam cold state installation requirements of manufacturer for
dominant mm Testing with dial gauge
pre-offset fastening; the other end shall be pre-raised
or pre-lowered in accordance with
manufacturer design value; then reregister
eccentricity of the sleeve.

Diametric clearance between dowel


dominant mm Meet the requirements of manufacturer
pin and location sleeve

Location hole interference of dowel


Measurement with
pin and steam cylinder (reel shaft dominant mm Meet the requirements of manufacturer
inside/outer micrometer
landing seat)

Location sleeve and center beam


dominant mm Meet the requirements of manufacturer
open hole diametric clearance

3 See table 4.4.11-3 for the installation, inspection and acceptance of pushing and
pulling device.
Table 4.4.11-3 Installation of push and pull device
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Thickness shall be confirmed in the cold


Measurement and
state. It shall be in accordance with
Side arm gasket configuration observation with outside
manufacturer design. There shall be no
micrometer
distortion and brute force installation.

Measuring connecting bolt


Side arm gasket joint surface gap dominant mm <0.05
with feeler gauge

Diametric clearance between dowel


dominant mm Meet the requirements of manufacturer
pin and location sleeve

Location hole interference of dowel


Measurement with
pin and steam cylinder (reel shaft dominant mm Meet the requirements of manufacturer
inside/outer micrometer
landing seat)

Location sleeve and side arm open


dominant mm Meet the requirements of manufacturer
hole diametric clearance

4.4.12 Check and installation of turning gear

137
Application scope: check and installation of turning gear, including turning gear
cleaning check and the assembly of turning gear.
1 See table 4.4.12-1 for the inspection and acceptance of turning gear clearing.
Table 4.4.12-1 Turning gear clearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Without casting sand, crack, bleb, smooth Observation and hand


Appearance inspection:
and clean component and burr feeling check

Pinion Length 75% of tooth length


Paiting method inspection
joggled joint Height 65% of tooth height

Gear case Level dominant mm 0.05


Inspecting and tightening
joint surface
Electrical Vertical dominant mm 0.05 the bolt with a feeler gauge
local gap
rolling
Internal lubrication oil
gear dominant Clean and clear Observation
line supply hole

Contact between
throwout and wobble
dominant Close joint Observation
wheel enclosure end
surface

Internal lubrication oil


Hydraulic dominant Clean and clear Observation
line supply hole
pressure
Inside hydraulic circuit
gear dominant Clean and clear Observation
oil supply hole

2 See table 4.4.12-2 for the inspection and acceptance of turning gear assembling
Table 4.4.12-2 Turning gear assembling
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Gap between Top dominant mm 1.5 Outside micrometer of


wobble gear and Both feeler gauge and pressure
dominant mm 0.08~1.20
rotor gearwheel sides fuse

Pinion backlash mm Meet the requirements of manufacturer

Distance from rotor cog


after disconnection of Enough distance shall be maintained Observation
Electrical
wobble wheel
rolling
Drive gearshaft gap mm Meet the requirements of manufacturer
gear
Cup spring pretension Measuring with inside
nun 0.20~0.50
value micrometer

Spring center column Straight steel ruler


mm 4
buffer value measurement

Inside fastenings Tightly locked


Observation
Motor sideshaft sealer Felted wool

Hydraulic
Hydraulic motor and dominant Meet the requirements of manufacturer Measure with dial gauge

138
trochanterian alignment

Thrust bearing gap dominant mm Meet the requirements of manufacturer Measure with dial gauge
pressure
Pinion backlash mm Meet the requirements of manufacturer
barring
Torque spanner fastening
Bolt up force moment Meet the requirements of manufacturer
check

4.4.13 See table 4.4.13 for the installation, inspection and acceptance of middle and low
pressure cylinder communicating pipe
Table 4.4.13 Medium and low pressure communicating pipe installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Communicating pipe inside clearing Clean and rustless Observation and hand

Flange face cleaning Smooth and burr free feeling check

In accordance with provisions of DL/T


Contra aperture gap and bevel
5210.5

Observation or oil
Weld bond tightness No leakage
penetration test

Without distortion and compulsion contra


Flange contra aperture Observation
aperture

Observation and hand


Flange bolt hole Without mismatch
feeling check

Bolt and nut coordination No seaming and no looseness

Measure with vernier


Flange gasket thickness mm Meet the requirements of manufacturer
caliper

Gasket and material Meet the requirements of manufacturer Observation

Communicating pipe set swinging Meet the requirements of manufacturer

Expansion joint and link bar Meet the requirements of manufacturer

Drain pipe It shall be clear Compressed air blowing

Gap between low pressure steam


admission stub pipe and outer mm Meet the requirements of manufacturer Feeler gauge measurement
cylinder

Gap between low pressure steam


admission stub pipe and inner mm Meet the requirements of manufacturer Feeler gauge measurement
cylinder

Cold Upside dominant mm


Straight steel ruler
drawing Meet the requirements of manufacturer
Downside dominant mm measurement
value

4.4.14 See table 4.4.14 for check of steam cylinder, main steam valve and adjustment steam
valve before thermal insulation and the check of turbine generators decorative sheet
Table 4.4.14 Check of steam cylinder, main steam valve and adjustment steam valve before thermal
insulation and the check of turbine generators decorative sheet
Inspection item. Property Unit Quality criteria Inspection method and

139
measuring instrument

Installation of cylinder body


drainage, instrument socket, joint Right, complete and no leakage Observation
and closure plate

Fastening iron of chrome


molybdenum vanadum cylinder Spot welding is not allowed Observation
body a

Rustless;without scar; smooth and clean


electroplating: straight and even
Appearance
framework and decorative sheet; complete
Observation
screw hole and right position

Straight and even; close joint; installation


Installation
in order; nice and firm

a Meet the requirements of manufacturer if they have.

4.4.15 See table 4.4.15 for the compulsory provision delivery performance check of
foundation preparation before the installation of turbine generators and iron gasket (block)
configuration
Table 4.4.15 Foundation preparation and iron gasket (block) configuration before installation of turbine
generators
_________ plant unit Project number:
Foundation preparation and
iron gasket ( block )
Unit engineering Main body installation of turbine
Subsection project name configuration before
name generator
installation of turbine
generators

Project number Acceptance date Date

Delivery Related
SN Inspection item
performance information

The construction and acceptance of steam turbine generator units must be


in accodance with approved design and the technical document provided
1
by the equipment manufacturing plant. If it need modify equipment the
above-mentioned documents, there must be certain approval process.

Those important materials used in construction shall be provided with


quality certificate and material certificate. If the quality of such materials
2
are doubted during checking and inspecition; they shall be inspected and
identied necessarily.

When settlement observation is carried out for foundation, the observation


work shall be carried out together with at least the following procedures:
(1) After curing period for foundation expires (with this measured value as
3 source data);
(2) Before and after all steam cylinder and generator stator of steam
turbine are positioned;
As for collapsible loess area, it shall properly increase measuring times.

140
Instrument with the level 2 precision shall be used for settlement
observation. All observed data shall be recorded on the special record
book; protection shall be made to the settlement observation point

Installation of steam cylinder and bearing seat shall be in accordance with


the following requirements:
(1) Vertical and horizontal center line of steam cylinder and bearing seat
shall meet the requirements of the drawings. In the same time, all the feet
4 bolt of steam turbine, generator and exciter shall be able to be threaded
into the bolt hole.
(2) Before steam cylinder positioning, pipeline and ironworks installed on
between the steam cylinder and foundation shall be installed before hand
to avoid hinderance in construction.

Acceptance
conclusion:

Construction organization:(Seal) Supervision organization:(Seal)

Project technical director: Supervising engineer :

Date Date

4.4.16 See table 4.4.16 for the implementation performance of compulsory provisions for
subsection project and steam turbine main body installation
Table 4.4.16 Implementation performance implementation performance of compulsory provisions for
subsection project and steam turbine main body installation
________ engine Project number:
Unit engineering Steam turbine main body
Main body installation of turbine generator Subsection project name
name installation

Project number: Acceptance date Date

Delivery Related
SN Inspection item
performance information

The construction and acceptance of steam turbine generator units must


be in accodance with approved design and the technical document
1 provided by the equipment manufacturing plant. If it need modify
equipment the above-mentioned documents, there must be certain approval
process.

Before installing equipment, it must inspect equipment as required. If


there is damage or quality defect, it shall timely inform organizations
concerned of joint inspection. As for defect in equipment manufacture, it
2 shall contact the manufacturer for treatment. If the installation quality fails
to meet requirements due to manufacturing quality, it shall be jointly
negotiated among construction organization, manufacturing organization,
development or using organization; there shall be records as well as

141
confirmation and signature for construction, equipment inspection and
defect treatment after reaching installation quality standard.

Those important materials used in construction shall be provided with


quality certificate and material certificate. If the quality of such materials
are doubted during checking and inspecition; they shall be inspected and
3 identied necessarily. All performances of quality steel, alloy steel,
nonferrous alloy, high-pressure-temperature welding material,
lubricating-oil (grease) fire-resistant liquid and insulation material must
meet design requirements and national standards and then used.

When settlement observation is carried out for foundation, the


observation work shall be carried out together with at least the following
procedures:
(1)After curing period for foundation expires (with this measured value as
source data);
(2)Before and after all steam cylinder and generator stator of steam turbine
are positioned;
4
(3)Before concrete is poured by steam turbine and generator for second
time;
(4)After commissioning test of the complete set.
As for collapsible loess area, it shall properly increase measuring times.
Instrument with the level 2 precision shall be used for settlement
observation. All observed data shall be recorded on the special record
book; protection shall be made to the settlement observation point

When there is obvious change on measurement for leveling, alignment


and centering every other day caused by nonuniform settlement of
5
foundation, the equipment shall be not be installed. Except strengthening
settlement observation, it shall also carry out research and treatment.

Before installing steam cylinder, it shall carry out the following


inspection on relevant manufacturing quality of equipment drawing and
shall meet the requirements; if necessary, it shall make records and shall
make research and treatment when failing to meet the requirements:
In appearance inspection of steam cylinder, it shall be free of crack, slag
6
inclusion, double skin, weld beading, pore, casting sand and damage.
All joint surface, sliding bearing area, flange, bore and processing surface
shall be smooth, clean and no rust and dirt. The anti-corrosive coating
shall be entirely cleaned out; the inside of steam chamber shall be
cleaned up thoroughly and without any attachment.

142
It shall inspect bolt and nut of steam cylinder according to the following
requirements:
(1)The screw thread in studding hole of bolt, nut and steam cylinder shall
be smooth and without rag; the matching between bolt and nut should not
be too loose or too tight. it shall be ablw to freely screw nut to the end by
hands; otherwise, it shall carry out research and treatment. There shall be
steel impression mark on bolt and nut of high pressure cylinder; they shall
be not exchanged randomly.
(2)As for contact plane of nut,steam cylinder or gasket with requirements
for hot tightening, Paiting inspection shall be applied to check the contact
is even or not.
(3)The screw thread of studding bolt for steam cylinder shall be entirely
screwed into flange of steam cylinder; the screw thread shall be lower
than the surface of flange; the verticality between studding bolt and
flange surface shall meet the requirements of manufacturer and shall be
less than or equal to0.50 in general; otherwise, it shall carry out research
7
and treatment.
(4)When the nut of bolt is tightened to the installation position in trial, the
screw thread of bolt shall be buckled where 2~3 buckles of nut are
exposed. When the shield nut is cooled and tightened to the installation
position, it shall ensure around 2mm clearance between top shield and top
bolt after properly fastening. The installation of tapered bolt for introduced
unit shall meet the requirements of manufacturer.
(5)Check the material of steam cylinder bolt and nut as required.
(6)The damaged screw thread shall be repaired and scraped; finally, it must
use triangular oil stone to polish the repaired and scraped area. If the screw
thread inside the studding hole need be repaired, it shall prepare special
screw tap.
(7)After inspecting and repairing screw thread, it shall use powder coating
with fine granularity and high temperature resistance for inunction
forcibly, or paint with lubricant required by the manufacturer; it shall
remove surplus paint and pack up bolt to avoid dust and clash.

When clearance of sliding pin is unqualified, it shall make adjustment.


As for oversized clearance, it shall allow repair welding or ion spraying on
8 the whole contact surface; but its hardness shall be greater than or equal to
that of virgin metal. restraining and squeezing shall not be used for
narrowing sliding pin gap.

143
Steam cylinder combination shall meet the following requirements :
(1)Before formal combination of the steam cylinder, non-paint trial
erection must be carried out. The closeness of joint surface shall meet the
requirements.
(2)If the manufacturer have no clear requirements for the steam cylinder
sealing paint, refer to the working pressure and temperature.
9
(3)As for the combined steam cylinder, the nut of vertical joint surface
shall be locked before the final sealing of steam cylinder. If electric
welding is used for locking, carry out spot welding at the nut and cylinder
wall. The position required by design requirements for sealing shall be
welded. Deformation caused by steam cylinder overheat shall be
avoided during welding.

Installation of steam cylinder and bearing seat shall be in accordance


with the following requirements:
Relative position of steam cylinder, bearing seat and pedestal shall meet
the requirements of thermal expansion during the operation of the unit. On
10
occasion of the largest thermal expansion, sliding surfaces of steam
cylinder or bearing seat shall not outstretch pedestal edge. Certain
allowance is needed. Fire resistant powder paint shall be painted on the
sliding surface or refer to the manufacturer's requirements.

Installation of steam cylinder expansion indicator shall be firm and


reliable; the indication range of indicator shall meet the maximum swelling
11 volume of steam cylinder. Before the marine machinery start-up and in the
cold state, check and ratify the final indication and record it. Record the
room temperature meanwhile.

The dimension of oil bag for oil hole on apical axis of lower bearing
shell shall meet the requirements of drawing. Generally, its depth shall be
between0.20~0.40mm; the area of oil bag shall be 1.5%~2.5% (larger
12 value for larger diameter of axle) of projected area of axle neck ; the axle
neck shall be tightly close to around oil bag. The oil pipe head of apical
axis must be firmly buried under black bronze and ensure to be clean and
smooth.

Before assembling steam turbine, it shall complete the following


work; it shall meet the requirements and shall have specified installation
records or confirmation and signature book:
(1)The iron gasket is completely installed and the foundation bolt firmly
fastened; ;
(2)Measure the final clearance between vertical and horizontal sliding pin
13
of platen, vertical pin of steam cylinder and horizontal pin of lug;
(3)Gap measuring of inner cylinder lug, vertical and horizontal sliding pin
and axial location pin
(4)Measure the clearance on horizontal joint surface of steam cylinder; ;
(5)Steam cylinder lift and turbine rotor shaft neck lift, including measuring
of rotor lift after connection between condenser and steam cylinder ;

144
(6)Central position confirmation of turbine rotor at steam seal or oil catch
bore; rotor coupling centre align final measuring;
(7)Gasket thickness record of rotor final positioning among all coupling
flange rotor ;
(8)Clapboard centering;
(9)Measure the clearance of steam seal and throughflow part;
(10)Adjust and measure clearance of thrust bearing;
(11)Spectrum reinspection of demountable parts inside steam cylinder; ;
(12)Eliminate defects of spare parts inside steam cylinder;;
(13)Thoroughly clean up the inside of steam cylinder, pipe segment and
steam chamber; seal pipe orfice as well as socket and plug of
instrumentation

As for alloy steel materials and parts within the supervision scope, their
steel types shall be verified in manufacture, installation or overhaul to
14
prevent misusage. After assembling, comprehensive review shall be made
for a second time to confirmation no mistake before putting into operation

There must be quality certificate for shaft, impeller and blade of steam
turbine provided by the manufacturer; before installation, it shall refers to
relevant technical information provided by the manufacturer. If any
15
inadequate information or quality or quality problem is discovered, the
manufacturer shall be required to supplement inspection or take
corresponding treatment measures.

Before installing high temperature bolt, make sure whether the


manufacturer instructions and quality guarantee are complete, including
16
material, specification of heat treatment,mechanicalProperty and
metallographic structure.

For high temperature bolt greater than or equal M32, the following
check shall be carried out before installation:
(1)Surface shall be smooth and clean, dent-free, rift-free, rust-free, and
other defects caused by other stress concentration.
17 (2) Carry out 100% spectrum check;High alloy steel bolt inspection area
shall be both ends;
(3)100% hardness check ;
(4)100% nondestructive inspection;
(5)20CrlMolVNbTiBSteel metallurgical phase spot inspection

Before installing heavy castings, such as steam cylinder, steam chamber


and main throttle valve, it shall check exfactory certification and quality
guarantee and carry out appearance inspection; there shall be no crack,
18 slag inclusion, double skin, weld beading, casting sand and damage.
When there is crack, its length, depth and distribution condition shall be
found out and treatment measures shall be carried out by the manufacturer
and other organizations concerned.

Acceptance
conclusion:

145
Construction organization:(Seal) Supervision organization:(Seal)

Project technical director: Supervising engineer :

Date Date

4.5 Adjustment and lubricating oil system installation


4.5.1 Valve and governing valve installation
Application scope; It is applicable to the inspection and installation of steam port and
governing valve, including cleaning, check and installation of steam port and governing
valve.
1 See Table 4.5.1-1 for the cleaning, check and acceptance of steam port and governing
valve.
Table 4.5.1-1 Cleaning of Steam Port and Governing Valve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flawless and without slag inclusion,


Appearance inspection Dominate double skin, welding beading, casting sand Observation
or damage

Material of alloy steel Spectrum and hardness


Dominate Meet the requirements of manufacturer
spare parts inspection

Observing with
Internal cleaning of Without casting sand, crack and sand hole,
Dominate magnifier with over five
enclosure and the internal surface shall show luster
times

Anti-looseness measure
for valve seat and internal Reliable and in good condition Observation
Cleaning
parts
and
Coloring method or
inspection Tightness of valve disc Continuously contact along the complete
Dominate drawing marks with
of valve and valve seat circle, and the width shall be uniform
pencil
body
Drainage holes Unimpeded Test passage

Fasteners
insurance on the
Steam
expansion Check against drawing
filter Correct, in good condition and reliable
clearance of and observe
screen
installation
position of mesh

Actuation of valve rod and Pushing and pulling,


Flexible, block-free
valve disc observing

Valve rod Pushing and pulling, and


Stroke of equilibrated
inspection Dominate mm Meet the requirements of manufacturer measuring with depth
valve
gauge

Stroke of valve disc Dominate mm Meet the requirements of manufacturer Pushing and pulling, and

146
measuring with depth
gauge

Smooth, clean, flat, without burr or radial


Joint surface inspection of valve
trench, continuously contact alone the Coloring method
cover and valve body
complete circle and with certain width

Joint surface gasket of valve cover Meet the requirements of manufacturer


Observation
and valve body and the gasket in good condition

Surface shall be smooth and clean, and


Appearance inspection without dent, rift, rust, burrs or other Observation
defects causing the concentration of stress.

Material
Dominate Meet the requirements of manufacturer Spectrum inspection

Valve
Hardness
cover bolt Dominate Meet the requirements of manufacturer Hardness inspection

Bolt screw thread Shall be coated with proper lubricant Observation

Cold tightening moment Dominate Meet the requirements of manufacturer Torque spanner

Rotation arc length of nut


Dominate mm Meet the requirements of manufacturer Measuring with tape
by hot tightening

2 See Table 4.5.1-2 for the inspection and acceptance on installation of steam port and
governing valve.
Table 4.5.1-2 Installation of Steam Port and Governing Valve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Elevation
mm 10
Measuring with steel tape
Deviation in the vertical and
mm 10
horizontal center lines

Level
The water bubble is in the middle Ordinary iron spirit level

Contact between frame Inspecting with a feeler


Contact tightly
and anchorage plate gauge

Fixed mode of frame Connected firmly; the direction and gap of


Check against drawing
and expansion direction dowel pin is correct
Supporting
The cold drawing is carried out after the
type of
heat treatment of welded joints' the
frame Check against drawing
pedestal bearing of steam port move
Cold drawing value Dominate mm and measure with steel
straightly and evenly; the direction and
tape
value meet the requirements of
manufacturer

Supporting Position of spring


Meeting the drawing requirements Check against drawing
type of support
spring

The operating height or Dominate mm Meet the requirements of manufacturer Check against drawing
operating load of spring and measure with steel

147
tape

Assembling of spring Measuring with a feeler


Contact solidly and fixed firmly
support gauge

Cold drawing value or


the installation deviation Dominate mm Meet the drawing requirements Measuring with steel tape
value of support

4.5.2 See Table 4.5.2 for the inspection and acceptance on installation of actuator.
Table 4.5.2 Installation of Actuator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In good condition, free of crack, rust,


Appearance inspection Dominate Observation
damage or deformation

Pipe joint Meet the requirements of manufacturer Check against drawing

Piston action Flexible, block-free Actuation inspection

Greater than travel of valve disc, with


Maximum stroke of Pushing, pulling and
mm surplus on both ends; meet the
piston measuring
Oil servomotor requirements of manufacturer

Correct and firm, the connection piece is


provided with tightly locked measure and
Assembling Dominate Observation
all the items shall meet the requirements
of manufacturer

Correct and firm meet the requirements


Displacement transmitter Check against drawing
of manufacturer

Indicator for the piston position and


Conform to both indications Checking and verifying
local stroke

Connecting rod assembly No deflection; flexible and no jam at joint Observation and actuation

Connection position of
Transmission Correct, firm and lock Observation
connecting rod
gear of
Space between piston Pushing, pulling and
connecting Dominate mm Meet the requirements of manufacturer
and bottom measuring
rod
Compression quantity of Pushing, pulling and
mm Meet the requirements of manufacturer
dish-type gasket measuring

Free of crack, rust, damage and


Spring inspection Observation
deformation; flat and smooth on end face
Spring
Correct, firm and all items shall meet the
support Spring support assembly Dominate Check against drawing
requirements of manufacturer

Preparation of dowel pin Dominate Correct and firm

The assembling is firm; the position and


Other parts Throttle pore plug hole diameter meet the requirements of Check against drawing
manufacturer

Check against quality


Gaskets Fluorine rubber gasket shall be selected
certificate

148
Filter element Clean and intact; t he dimension meet the
Check against drawing
requirements of manufacturer

Correctly positioned; sealed firmly; no oil


Electro Assembling Observation
leakage
hydraulic
Operating
converter Dominate Flexible and block-free Trial operation

Assembling Firm and sealed without oil leakage Observation

Slide valve Actuation and depth


Dominate mm Meet the requirements of manufacturer
travel vernier caliper

Slide valve
Unloading Flexible and block-free Trial operation
action
valve
Manual
screw rod for Block-free and the travel meet the
mm Trial operation
pressure requirements of manufacturer
regulation

Assembling of linear Correct and firm, meet the requirements


Check against drawing
difference transducer of manufacturer

4.5.3 Installation of protective device


Application scope: It is applicable to the installation of protective device, including
installation of emergency governor, emergency trip throttle, emergency trip devices and other
security operating equipments.
1 See Table 4.5.3-1 for the inspection and acceptance on installation of emergency governor.
Table 4.5.3-1 Installation of Emergency Governor
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Intact, without rust, crack, damage or


Appearance inspection Observation
deformation

Swaying degree in radial Measuring with dial


Dominate mm 0.05
circumference of shaft terminal gauge

Fly ball Adjusting nut In good condition and shall be locked Observation
or
Shaft neck protruded on
eccentric mm 10.2 Checking the marks
the top
strap

Trial operation
Trigger Binding of hook Intact and correct
of
Rotating gap with fly ball Measuring with a feeler
dropout Dominate mm Meet the requirements of manufacturer
or eccentric strap gauge

2 See Table 4.5.3-2 for the inspection and acceptance on installation of emergency trip
throttle.
Table 4.5.3-2 Installation of Emergency Trip Throttle
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance inspection Intact, without rust, crack, damage or Observation

149
deformation

Contact between emergency trip Tightly contacted and no oil leakage after Trial operation,
sliding valve disc and valve seat closure observation

Positioning of emergency trip sliding The caulked joints of dowel pin, holding
Observation
valve devices screw and tally screw shall be compacted

Spring
Manual Tightness is proper Inspection

emergency
Hand grip
trip Dominate Hand grip is provided with shelters Observation

devices
Position of slide valve Dominate Positioning is correct Check against drawing

Unimpeded and in the right direction;


Solenoid valve Test inspection
actuation is accurate and reliable
Resetting
Air cylinder or oil Block-free, move smoothly and no air or oil
solenoid Trial operation
cylinder piston leakage
valve and
Implementation pusher
air Block-free in the whole travel route Test inspection
arm
cylinder or
Good contact between vertical pusher arm
oil Movable panel Test inspection
and switch
cylinder
Travel switch spacing Meet the requirements of manufacturer Measuring with a ruler

Indicating position Consistent with the actual position Checking

Position is correct and aligns to the fuel


Mounted position Dominate Observation
inlet chamber of emergency governor

Space meets the requirements and the


Measuring with a feeler
Space requirements Dominate mm requirements for maximum expansion
gauge
difference of rotor

Correct and firm, no leakage and the inside


Spray bar Dominate Ventilation test
is clean
Oil spray Be able to control the emergency trip
Dropout lever and test tie
test device Dominate throttle and oil-spray slide valve accurately Trial operation
bar
and the indicate correctly

Space meet the requirements of


Assembling Dominate mm Measuring
manufacturer

Actuation
Dominate Driving flexibly and without block Trial operation

The pipe is clean and unimpeded; sealing is


Pipe Dominate Ventilation test
without leakage

Position is correct, the inside is clean,


Assembling Check against drawing
connection is firm and without leakage
Overflow
Actuation
valve Dominate Flexible and block-free in the whole stoke Trial operation

Pressure adjustment Dominate MPa Meet the requirements of manufacturer Inspection

Clean, the assembling is firm; the position


Throttle pore plug Dominate Check against drawing
and hole diameter meet the requirements of

150
manufacturer

Connection is firm, assembling is correct,


Connecting rod assembly Trial operation
operation is flexible and without block

3 See Table 4.5.3-3 for the inspection and acceptance on installation of emergency trip
devices.

Table 4.5.3-3 Installation of Emergency Trip Devices


Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Intact, without rust, crack, damage or


Appearance inspection Observation
deformation

The caulked joints of dowel pin, holding


Positioning of device Inspection
screw and tally screw shall be compacted

Spring Tightness is proper Inspection

Hand grip
Manual emergency trip Dominate Hand grip is provided with shelters Observation
devices
Position of
Dominate Positioning is correct Check against drawing
slide valve

Gap between
Measuring with feeler
shifter lever mm Meet the requirements of manufacturer
Electromagnet of gauge
and baffle ring
mechanical shutdown
Flexible and block-free; the slide valve
Actuation Dominate Trial operation
can be controlled accurately

Position is correct, the inside is clean,


Assembling Check against drawing
Emergency intercepter connection is firm and without leakage
valve Actuation
Dominate Flexible and block-free Trial operation

Position is correct, the inside is clean,


Assembling Check against drawing
Solenoid isolation valve connection is firm and without leakage

Actuation Dominate Flexible and block-free Trial operation

Position is correct, the inside is clean,


Main intercepter solenoid Assembling Check against drawing
connection is firm and without leakage
valve
Actuation Dominate Flexible and block-free Trial operation

Resetting solenoid valve Unimpeded and in the right direction;


Solenoid valve Test inspection
and air cylinder or oil actuation is accurate and reliable
cylinder Air cylinder or
Block-free, move smoothly and no air or
oil cylinder Trial operation
oil leakage
piston

Implementation
Block-free in the whole travel route Test inspection
pusher arm

Good contact between vertical pusher


Movable panel Test inspection
arm and switch

151
Travel switch
mm Meet the requirements of manufacturer Measuring with a ruler
spacing

Indicating
Consistent with the actual position Checking
position

Mounted Position is correct and aligns to the fuel


Dominate Observation
position inlet chamber of emergency governor

Space meets the requirements and the


Space Measuring with a
Oil spray test device Dominate mm requirements for maximum expansion
requirements feeler gauge
difference of rotor

Correct and firm, no leakage and the


Spray bar Dominate Ventilation test
inside is clean

Space meet the requirements of


Assembling Dominate Measuring
manufacturer

Indicator or travel switch Actuation Dominate Driving flexibly and without block Trial operation

The pipe is clean and unimpeded; sealing


Pipe Dominate Ventilation test
is without leakage

Clean, the assembling is firm; the


Throttle pore plug Dominate position and hole diameter meet the Check against drawing
requirements of manufacturer

Connection is firm; assemblage is


Connecting rod assembly correct; actuation is free flexible and Trial operation
block-free

4 See Table 4.5.34 for the inspection and acceptance on installation of other security
operating equipments.
Table 4.5.3-4 Installation of Other Security Operating Equipments
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Intact, without rust, crack, damage or


Appearance inspection Observation
deformation

The operation is flexible; tight; prepressing


Observing and trial
Air pilot valve quantity of spring meets the requirements of
operation
manufacturer

Inspection for
connection tube Meet the requirements of manufacturer Spectrum inspection
Oil drive
material
intercepter
Position is correct; firm and tight; without
valve Assembling Check against drawing
leakage

Actuation Dominate Flexible and block-free Trial operation

Emergency Position is correct; meet the requirements of


Pipe joint Check against drawing
trip control drawing
block Assembling of Position is correct, clean, connection is firm
Check against drawing
magnetic valve and without leakage

Actuation of Dominate Flexible and block-free Trial operation

152
magnetic valve

Clean, the assembling is firm; the position


Throttle pore plug Dominate and hole diameter meet the requirements of Check against drawing
manufacturer

Clean, the mounted position is correct,


Assembling Check against drawing
connection is firm and without leakage
Diaphragm
Flexible operation, block-free, actuating
valve
Actuation Dominate pressure meet the requirements of Trial operation
manufacturer

The operation is flexible; tight; prepressing


Protective device for low oil
Dominate (preloading) quantity of spring meets the Trial operation
pressure and low vacuum
requirements of manufacturer

The protective devices are installed after the


Protective device for axial
determination of thrust bearing position and
displacement and differential Dominate Trial operation
gap; the zero position meet the requirements
expansion
of manufacturer

Other electronic protective


Matching the installation of thermal;
devices (overspeed monitoring
Dominate position is correct; the test actuation number Trial operation
protection, vibration monitoring
is accurate
protection, etc.)

4.5.4 Inspection and acceptance on installation of main oil pump specified in Table 4.5.4.
Table 4.5.4 Installation of Main Oil Pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance of pump shell and Without casting sand, crack, paint or


Observation
impeller sundries

Tighten 1/3 bolt and


Gap on horizontal joint surface
mm <0.05 inspect with feeler gauge
of pump shell
along around

Measuring with inside


Oil seal bore of main oil pump mm Meet the requirements of manufacturer
micrometer

Inspect by feeler gauge or


Base flange of main oil pump Tight contact
painting

Matching of impeller and shaft


Tight and without looseness Inspection
and connecting key

Bolt and nut on rotor Anti-looseness measures shall be taken Observation

Measuring with dial


Radial flutter on shaft end Dominate mm 0.05
gauge

Radial flutter of impeller sealing Measuring with dial


Dominate mm 0.05
ring gauge

The radial and axial total


Measuring with a vernier
clearance of sealing ring on the Dominate mm Meet the requirements of manufacturer
caliper or a feeler gauge
impeller side

153
The radial and axial total
Measuring with a vernier
clearance of sealing ring on the Dominate mm Meet the requirements of manufacturer
caliper or a feeler gauge
pump shell side

Clearance in the front and back Meet the requirements of manufacturer and
Measuring with block
sides of vane wheel and axial Dominate mm larger than the maximum expansion
gauge
clearance of pump shell difference

Vent port of pump body Unimpeded and without blocking Ventilation purging

Note: It is mainly the centrifugal main oil pump that the impeller of pump shaft and the high-voltage rotor of steam turbine
connected as a whole

4.5.5 Installation of the equipments and pipelines of fire resistant fluid system
Application scope: It is applicable to the installation of equipment and pile of fire resistant
fluid system, including installation of fire resistant oil tank, oil pump, oil cooler, oil filter and
accumulator and the cycle flushing of fire resistant oil system, piping installation and fire
resistant oil system.
1 See Table 4.5.5-1 for the inspection and acceptance on installation of fire resistant oil tank,
oil pump, oil cooler, oil filter and accumulator.
Table 4.5.5-1 Installation of Fire Resistant Oil Box, Oil Pump, Oil Cooler ,Oil Filter and Accumulator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Internal cleaning of
Clean, without welding slag or sundries Observation
oil tank

Flexible and correspond with actual oil


Oil pointer Checking
level
Oil tank Bar magnet
Clean Observation

Clean and without damage, loading and


Filter element unloading is flexible, the dimension Observation
meets the requirements of manufacturer

Good appearance; correct dimension,


Oil pump inspection Observation
type, and joints; firmly fixed

Appearance Intact, correct dimension, model, and


Check against drawing
inspection joints
Oil cooler
Hydraulic test at 1.5 times work stress;
Dominate MPa Without seepage
water side inspect after 5min

Material and dimension meet the


Oil filter and Filter element
requirements of manufacturer and are Inspection
regenerative
clean
device
Assembling Firm and no leak Observation

Correct position and direction; firmly


Assembling Check against drawing
fixed
Accumulator
Nitrogen padding No leakage and the padding pressure
Dominate Inspection
inspection meets the requirements of manufacturer

2 See Table 4.5.5-2 for the inspection and acceptance on installation of fire resistant oil

154
system pipe.
Table 4.5.5-2 Installation of Fire Resistant Oil System Pipe
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

The internal and external surface is


Oil pipe inspection Dominate washed clean and without welding slag, Lighting inspection
rust stain or sundries

Observe after cold


Bending of oil pipe Without double skin or wrinkle
bending

Contact surface of locknut joint on Uniformly and continuously contacted


Color-painting test
spherical opening and without score break

Locknut gasket material on plane


Meet the requirements of manufacturer Observation
opening

The connection is without forced contra


aperture, dead head, arch in the middle or
Oil pipe installation Dominate Observation
keeping air; the heat expansion
compensation is provided with

The type meet the requirements of the Check against drawing


Installation of supports
drawing and the layout is reasonable and observe

The welding form meets the requirements


Welded junction inspection Dominate of technological documents and welding
procedure

The materials of pipe, joint and pipe


All shall be stainless steel Observation
fittings

The pipe end is smooth, clean and burr


Pipe cutting free; emery wheel pipe cutting machine or Observation
flame cutting cannot be adopted

Washing of piping and parts Clean, impurity-free and corrosion-free Observation

Check against quality


System sealing ring Fluorine rubber gasket shall be selected
certificate

3 See Table 4.5.5-3 for the inspection and acceptance for the cycle flushing of fire resistant
oil system.
Table 4.5.5-3 Cycle Flushing of Fire Resistant Oil System
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Installation finished, connection correct


System inspection Dominate and be in accordance with those specified Check against drawing
in design

Restriction orifice or pore plug Dismantled Inspection

Dismantled and provided with temporary Check against drawing


Electro hydraulic converter
flashing means and inspect

Replaced by temporary flashing filter


Filter element Observation
element

155
Has been installed according to
Thermal instrumentation System inspection
requirements

Chemical examination
Flushing oil The oil is qualified and sufficient
and inspection

Oil loading apparatus The inside is clean Observation

Cycle flushing pressure Dominate Meet the requirements of manufacturer Pressure gage

Measuring with
Cycle flushing oil temperature Dominate 54~60
thermometer

Sampling point position Meeting the design requirements Observation

Meet the requirements of manufacturer


Cleanness Sampling for chemical
Number of particles Dominate and at least reach to NAS5; refer to Annex
of examination
B
flashing
Magnetic steel bar Clean and without particles Observation

Tightness inspection of system Dominate Without leakage Observation

4.5.6 Lubricating oil system equipment and piping installation


Application scope: equipment and pipe installation of the lubricating oil system, including
installation of integrated oil tanks, installation of oil coolers, installation of fuel filters,
inspection and installation of vertical or horizontal oil pumps, trial operation of oil pumps,
installation of oil ejectors and oil worm wheel pumps, installation of oil purifiers, installation
of lubricant (jacking oil) pipes, and cycle flushing of lubricating (sealing) oil system.

1 See Table 4.5.6-1for inspection and acceptance on installation of integrated oil tanks
Table 4.5.6-1 Installation of Integrated Oil Tanks
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Inspection Appearance of oil tank In good condition without scar and with
Observation
of and equipment complete components
integrated Check in accordance with
Oil tank opening complete and correct
oil tanks drawing

Parting sheets and filter Check in accordance with


All the positions are correct
screens drawing

Filter screens are clean, free from


damage, fixing devices are installed at the
Filter screen inspection Observation
internal and external sides and loading
and discharging is flexible.

Flange studding hole It shall not penetrate box wall Observation

Soaked in kerosene for 4h


Tightness of floating
dominant No leakage and the weight does not
pipe
change

Clean the internal oil dominant Free from scales, welding slag, clean, Observation
tank paints with internal surface, which do not
dissolve in the turbine oil, are free from
156
shedding; paints dissolvable in the turbine
oil must be removed.

Adjustable inverted the full range is flexible, without jam,


Operation, observation
valve Meet the requirements of manufacturer

Oil tanks are cleaned Reboring, gas cutting and welding shall
dominant
and sealed not be carried out after sealing

Deviation in the vertical


Measuring steel tapes
and horizontal center mm 10
subject to the reference
lines
line
Elevation deviation mm 10

Foundation, iron meet those specified in table 4.3.18 and


gasket, stone bolt table 4.3.19
Integrated
In accordance with provisions of table
oil tank Secondary pouring
4.3.20
installation
Measure and carry out
Firm, vertical, mark posts of floating
Installation of oil level Trial operation with a
pipes are stable and the Indication is
gauge plumb bob along the total
accurate
height

Ladder footpath,
in according to Table 4.3.37 Observation
platform and handrail

2 See Table 4.5.6-158 for inspection and acceptance on installation of oil coolers.
Table 4.5.6- 157 Installation of Oil Coolers
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Specifications, types, joints and


positions are correct and clean, free Observation, Check in
Appearance inspectiona
from rust stains, foreign bodies, accordance with drawing
damages and deformation

Elevation deviation of the


mm 10
foundation measuring steel tapes subject

Deviation in the vertical and to the reference line


mm 10
horizontal center lines

Perpendicularity deviation of Measuring with a plumb bob


mm/m 5
installation along the total height

meet those specified in table 4.3.18 and


Foundation, iron gasket, stone bolt
table 4.3.19

In accordance with provisions of table


Secondary pouring
4.3.20

Check 0.6 MPa oil pressure


leak Oil side oil pressure (blast
dominant MPa No leakage or 0.35 MPa blast pressure
testb pressure) test
30 min later

157
Test water quality clean and free from foreign matters Visual observation

Oil coolers with expansion


Taken strengthening measures Observation
compensators

5 minutes check for test


pressure stipulated on the
water side dominant MPa Without leakage manufacturer nameplate or 5
minutes check with 1.5 times
of working pressure

Gasket materials Oil proof gasket Observation

Valve discs shall be tight, valve rods


shall be oil tight and switching Systematic trial operation
Inspection of block valves
positions shall have clear indications on and observation
the out side.

a Coolers are divided into panel coolers and tube coolers, all of which are integrally delivered, shall not be disassembled on-site;
if disassembly is carried out on-site, disassembly shall be implemented according to meet the requirements of manufacturer.
b Leak test shall be carried out on either the water side hydraulic pressure or the oil side air pressure according to the site
condition.

3 See Table 4.5.6-3for inspection and acceptance on installation of fuel filters


Table 4.5.6-3 Oil Filter Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Clean, free from rust stains, foreign


Appearance inspection Observation
bodies, damages and deformation

Elevation deviation of the


mm 10
foundation measuring steel tapes

Deviation in the vertical and subject to the reference line


mm 10
horizontal center lines

Perpendicularity deviation of Measuring with a plumb


mm/m 5
installation bob along the total height

meet those specified in table 4.3.18 and


Foundation, iron gasket, stone bolt
table 4.3.19

In accordance with provisions of table


Secondary pouring
4.3.20

Internal inspection Clean, free from short circuit Observation

Intact and eyelets meet the requirements


Guard plate of the filter screen Observation
of manufacturer

Intact, free from damage, firmly fixed and


Filter screen dominant Observation
meet the requirements of manufacturer

Valve discs are tight, valve rods are oil


Systematic trial operation
Block valves tight and switching position have clear
and observation
indications on the out side.

4 See Table 4.5.6-4doe check, installation, inspection and acceptance of vertical oil pumps
Table 4.5.6-4 inspection And Installation of Vertical Oil Pumps

158
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Free from casting sand, gas cavities,


Pump shells and vane wheels cracks, paint and the position of oil duct
hole is correct and unimpeded.

Vent ports on the pump shell Unimpeded


Observation
Flat, smooth, clean, free from burrs and
Joint surface of pump body
radial delves

Clean, free from damage, firmly


Filter screen
installed

Intact, free from rust, crack and flexible


Shaft bearing
rotation

Inspection Central section of


Rotor dominant mm 0.05
and the pump shaft
flutter in
Measure with dial gauge
installation the radial Axle neck mm 0.03
of oil direction
Impeller ring mm 0.08
pump
Unilateral radial
Push and pull, measure
direction of the dominant mm 0.12~0.20
with depth gauge
suction inlet

Axial direction of Push and pull, measure


dominant mm 34~4
the suction inlet with depth gauge
Impeller
Unilateral radial Measure internal and
clearance
direction on the dominant mm 0.12~0.20 external diameters with
pressure side vernier caliper

Axial direction of
Push and pull, measure
the on the dominant mm 3~4
with depth gauge
pressure side

5 See Table 4.5.6-5 for the checking, installation, inspection and acceptance of the horizontal
oil pumps.
Table 4.5.6-5 Inspection And Installation of Horizontal Oil Pumps
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

free from casting sand, gas cavities,


Appearance Observation
cracks and mechanical damages

Elevation deviation of the


mm 10 Steel tape measurement
foundation

Deviation in the vertical and


mm 10 Steel tape measurement
horizontal center lines

meet those specified in table 4.3.18 and


Foundation, iron gasket, stone bolt
table 4.3.19

In accordance with provisions of table


Secondary pouring
4.3.20

159
Pump base is horizontal and the direction
Installation of oil pumps Leveling rod
is correct

Reliably connected, have anti-looseness


Inspection of impellers Observation
measures

Filter screen of inlets Clean, free from damage, firmly fixed Observation

In accordance with provisions of table


Coupling centre alignment dominant mm
4.3.32

Pump unit bolt Installed with lock washers Observation

Rolling hand feeling,


Rotor of pump assembling dominant Uniform rotation, free from grating
listening to the sound

Installation of outer cover of the Firm, nice process and convenient


Observation
coupling maintenance

6 See Table 4.5.6-6 for inspection and acceptance of oil pump trial operation
Table 4.5.6-6 Oil Pump Trial Operation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Fuel level in tank mm not less than the lowest level

Inlet tube flashing for It may be connected with oil pump after
Observation
plunger pumps proving qualified
Check
Start-up oil level of gear
before Meet the requirements of manufacturer Observation
oil pump
trial run
Fixed value of electric and
Check electricity, thermal test record and
heat engineering
all of them are qualified
protection

Sound in the pump is normal, free from Hand feeling, listening to


Run of oil pump
attack the sound

Pump set vibration dominant mm Meeting the requirements of DL 5011 Measuring with vibrometer

Meet the requirements of manufacturer ,if


lubricant is used, it is 65~70, if the Measurement by
Shaft bearing temperature dominant
lubricating grease is used, it shall not thermometer
exceed 80

partially Indicating with pressure


Outlet pressure dominant Reach the rated value and keep stable
trial run gage

Shaft seal Tight without leakage

Continuous trial run


h 4~8 Timing
duration

Current meter
Motor working current Rated value
measurement

Shutdown and coasting with certain race time but no sudden


Observation
operation broke-off of the pump

7 See Table 4.5.6-7 for inspection and acceptance on installation of oil ejectors and worm
wheel pumps.

160
Table 4.5.6-7 Installation of Oil Ejectors And Oil Worm Wheel Pumps
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Free from casting sand, gas cavities and


Appearance inspection Observation
cracks

Diameter of nozzle throat dominant mm

Diameter of diverging Check against the


dominant mm
pipe throat drawing, use the vernier
Meet the requirements of manufacturer
Distance between nozzle caliper for depth

Oil exit and diverging pipe dominant mm measurement

ejectors throat

Straight steel ruler


Location of suction inlet Below lowest oil level of oil tank
measurement

Back stop plate Flexible operation, free from jam Trial run

Filter screen of inlets Clean, in good condition Observation

Connection is firm, sealed, oil tight and Trial tightening,


Connection
the bolt is locked observation

free from casting sand, gas cavities and


Appearance inspection Observation
cracks

Measuring with plumb it shall be vertical and the direction of Measuring with plumb
bob the flange shall be correct. bob

Rubber seal
In good condition without damage
washers
Nozzle Coated with lubricating grease as
Assembling Observation
ring required by the manufacturer
Installation
Baffle and filter
of worm Clean and firmly fixed
screen
wheel
Flat, smooth and the plane shall not
pumps Subplates on the nozzle
higher than the oil drainage flange end Observation
ring
face of the pump body

Reliably connected, have anti-looseness


Inspection of impellers Observation
measures

using torque spanner,


Connecting bolt Fastened, have anti-looseness measures
observation

Uniform rotation without abnormal Hand feeling, listening to


Manual rolling rotor
sound the sound

8 See Table 4.5.6-8for inspection and acceptance on installation of oil purifiers.


Table 4.5.6-8 Installation of Oil Purifiers
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Device inspection Conform to Table 4.5.6-1

Elevation deviation of the foundation mm 10 Steel tape measurement

161
Deviation in the vertical and
mm 10 Steel tape measurement
horizontal center lines

level of the equipment the water bubble is in the middle Ordinary iron leveling rod

meet those specified in table 4.3.18 and


Foundation, iron gasket, stone bolt
table 4.3.19

In accordance with provisions of table


Secondary pouring
4.3.20

In good condition without damage and


Appearance inspection Observation
Smoke deformation

exhaust hearing the sound and


rolling rotor Normal rotation without strange sound
fan hand feeling

Installation Meet the requirements of manufacturer Check the drawing

Sludgeless
Coupling centre alignment mm Meeting the requirements of DL 5011
oil pump

9 See Table 4.5.6-9 for installation and inspection and acceptance of lubricating pipes and
jacking oil pipes
Table 4.5.6-9 Installation of Lubricant Pipes (Jacking Oil Pipes)
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Valve type dominant use steel rising valves Observation

Valve cleaning the inside is clean, without leakage Hydraulic pressure test

Special valves (reducing


valves, overflow valves,
dominant Meet the requirements of manufacturer
oneway valves,
overpressure valves etc.)

Serial connect two hand wheel type gate


Valve Quantity dominant Observation
valves
installation
Easy for operation, more than 5m away
Oil outlet
Installation from the oil tank, have more than 2
dominant Observation
position passages and protecting glass shall be
set for handwheels

Valve packing PTFE bowl-shaped gaskets should adopt Observation

Installation direction of
dominant Valve stem horizontal or downward Check
valves

Internal and external sides shall all be


Flange Flat welding flange welded and the welded joint surface Painting inspection
shall be flat and smooth

Raise by one grade compared with the


Flange rating Observation
general one

Gasket Oil proof, high temperature resistant, Check, Push and pull,
Material dominant
material without using plastics or rubber measure with depth gauge
of the Thickness mm Ordinary1

162
joint Internal Bigger than the flange internal diameter
mm
surface diameter 2~3

Pipeline materials, pipe Clean inwall; no rust stain, dust and


dominant Observation
fittings foreign bodies

Welding dominant meet requirements of DL/T 869 Observation

Internal and external of oil pipes and


pipe fittings, supports are clean and
Complete suit of oil pipes Observation
installation of conduit clips and supports
shall be firm.

Connect to the emergency oil drainage


Emergency oil pipes dominant
shaft

Meet the requirements of the drawing Measuring with leveling


Scavenge pipe gradient dominant
and it generally shall be 3%~5% rod

Contra apertures of oil


Strong contra apertures are forbidden Observation
pipes, flange connection

Installation space of oil Without prejudice to steam turbines,


Observation
pipes thermal expansion of oil pipes
Oil piping Clear space between the oil
installation pipe and the Insulating Straight steel ruler
mm >150
layer surface of the steam measurement
pipe

Insulation values of oil


Measuring with 1000 V
pipes and exciter shaft dominant M 0.5
insulation resistance meter
bearings

Type, space Meet the requirements of the drawing Checking, measuring


Supporter
Installation Firm, reliable and beautiful Observation
and
hanger Isolation measures shall be taken, if
Stainless pipe Observation
dissimilar steels are contacted.

the contact is uniform and the


Spherical joint surrounding press marks have no Painting inspection
rupture

On-site pressure gage and the position and number are correct and
Checking
thermometer conform those specified in DL/T 5210.4

10 See Table 4.5.6-10 for inspection and acceptance of the lubricating oil system, sealing oil
systemic circulation.
Table 4.5.6-10 Cycle Flushing of Lubricating (Sealing) Oil System
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Cycle
flushing Systematic inspection (including The installation is inspection
emergency discharge system) finished, the
connection is correct
and meet the
163
requirements of the
drawing

Restriction orifices or pore plugs Dismantled inspection

Thermal instrumentation Installed as required Systematic inspection

the oil is qualified and


Flushing oil Chemical examination
sufficient

Screen more than 100 screen


Specification Observation
Temporarily mesh meshes
filter screen 2 times~4 times of oil
Flow area Measuring, calculating
pipe flow area

Highest Measurement by
Flushing oil temperature
temperature80 thermometer

More than 0.25mm dominant None Fuel inlet filter screens


of shaft bearings with
150 screen meshes (No.
60), full flow flashing
Number of oil for 0.5h, collect all the
particles 0.13mm~0.25mm dominant Particles 5 foreign matters on the
filter screen and carry
Oil out differential count
inspection with a
after flashing decuple-magnifier.
a
Meet the
requirements of
Choose samples from
manufacturer , It is
the oil tank and oil
generally not less
Chemical examination of oil samples dominant outlet of the oil cooler
than NAS grade 7 and
and carry out chemical
meet the oil index
examination
specified in GB/T
7596

Tightness inspection of jacking oil system dominant Without leakage Observation

a Granularity counting and chemical examination of oil samples could be carried out according to the site condition.

4.5.7 See Table 4.5.7 for adjustment and inspection of implementation performance of
subsection project compulsory provisions for lubricating oil system equipment installation.
Table 4.5.7 adjustment and Inspection table for implementation performance of subsection
project compulsory provisions for lubricating oil system equipment installation

________unit project number:


Unit project Subsection project Adjustment and lubricating oil
Main body installation of turbine generator
name name system equipment installation

Project number Acceptance time Date

SN Inspection item Implementation Related

164
performance information

The installation of oil-spray test device for emergency governor shall


be in accordance with the following requirements:
(1) The spray bar shall be clean and smooth; the oil-taking room of
emergency governor shall be alighted and it shall make close inspection
within the range of maximum expansion difference of rotor; its relative
position shall be able to meet the test requirement. The clearance
between nozzle and oil-taking room shall meet the requirements.
(2) The test tie bar shall be used to control the tripping lever and
oil-spray slide valve system. After installation and positioning
emergency governor, emergency trip throttle, tripping lever and test tie
bar, it shall try operation and meet the following requirements:
1) The test tie bar shall be able to accurately control disconnection or
1 in-put of emergency trip throttle corresponding to fly ball as well as oil
throughout or oil cutoff corresponding to oil-spray slide valve and
indicate them correctly;
2) The control pin shall be able to fix up location of test tie bar
reliably.
(3) As for the system of directly applying emergency trip test throttle
to oil-filling test, it shall be subject to trial operation and meet the
following requirements:
1) The indication on rotation direction of test slide valve and the oil
line switching shall be in accordance with the test sequence of
emergency governor;
2) When no oil-filling test is carried out, the indication pin shall be
able to prevent rotation or pulling of test slide valve reliably.

The installation of emergency trip indicator shall be in accordance with


the following requirements:
(1) The clearance between contact terminal of mechanical lever-type
indicator and transmitter as well as emergency governor of electricity
2
indication shall meet the requirements of drawing;
(2) The piston and spring indicator shall be jacked up with safety oil;
there shall be flexible operation and no jam on piston and indicator pole.
The safety oil pipe shall be tight, without leakage, clean and smooth.

Installation and adjustment of impulse elements (transmitters and oil


nozzles) used for axial displacement and differential expansion
protective devices shall be carried out the position and gap of the steam
3
turbine thrust bearings are determined and the position of the impulse
element to the turbine rotor zero position shall meet the requirements of
the manufacturer.

There shall be protective cover for manual emergency trip device; the
4
positioning billiards shall be able to correctly position slide valve.

The slide valve of magnetic-power disconnection throttle and electric


5
over speed protective device shall be flexible in operation and without

165
looseness; the air port on the slide valve shall be smooth; the iron core
and slide valve shall be firmly connected.

If the protective devices of the steam turbine are installed and


submitted for acceptance, the following technology are required:
(1) Record of nut position of fixed spring tightening force of
emergency governors;
6
(2) Record of gaps between the dropout levers of emergency
governors and fly balls or eccentric straps;
(3) Records of oil nozzles of axial displacement protective hydraulic
devices and main shaft flanges

The oil exit pipe for oil tank accident shall be connected to the accident
oil drainage well specified in design. Before unit trial operation, it shall
be formally installed and confirmed to be smooth.
The inspection and installation of oil piping valve shall be in accordance
with the following requirements:
Generally, two gate valves shall be set up for accident oil discharge
valve; the gate valve close to oil tank shall be made of steel. The
7
operation handwheel of accident oil discharge valve shall be set up at
over 5m away from oil tank and there shall be more than two passages.
The handwheel shall be set up with protecting glass.
There shall be clear marking on switch direction of valve; rising stem
valve shall be used instead of reverse valve. The valve stem of pipe shall
be laid flat or downward to prevent valve disc from falling off and
cutting off oil line during operation.

Drilling hole, gas cutting and welding shall not be carried out on the oil
8 pipe after it is cleaned up and sealed, otherwise, cleaning, inspection and
sealing must be carried out again.

All pipes shall be constructed according to design drawing. If it need


9 modify design or adopt substitute material, it must apply to the design
unit and handle it according to relevant system

Anti-corrosive coating for buried steel pipe shall be painted before


installation; anti-corrosive measures shall not be taken for the weld
10 seams before they are qualified in inspection; the anticorrosive coating
shall be prevented from damage during transportation and assembling;
and those damaged anticorrosive coatings shall be repaired.

Acceptance
conclusion:

166
Construction unit: (seal) Supervision unit: (seal)

Project technical director: Supervision engineer:

Date Date

4.6 Generator and exciter installation


4.6.1 See Table 4.6.1 for emplacement, inspection and acceptance of generator pedestals.
Table 4.6.1 Emplacement of Generator Pedestals
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flat, smooth, clean, free from


damage, deformation, rags, the Inspecting with a feeler
Appearance inspection for pedestals embedded part of the secondary gauge and a leveling
penetration course is free from paint ruler
and rust stain

No crimping, rust; flat, smooth and


Appearance Observation
clean; cut opening at bolt

Material steel Observation

Adjustable Meet the requirements of Push and pull, measure


Gross thickness mm
gasket manufacturer , normally5 with depth gauge

Meet the requirements of


Layer numbers Layer Observation
manufacturer , 2~3

Meet the requirements of


Layout type Observation
manufacturer , echelon form

Measuring subject to the


Position deviation of pedestals mm 2 vertical and horizontal
longitudinal center lines

If it is fine grade, it shall


Elevation deviation of pedestals mm -5~0
be measured with level

The space between the bottom surface of


Meet the requirements of Straight steel ruler
the pedestal and the foundation concrete mm
manufacturer , normally around 80 measurement
surface

The 0.05mm feeler gauge could not


Contact between the pedestal and the Inspecting with a feeler
mm be inserted and the partial inserting
iron gasket (concrete block) gauge
width depth is all less than 25 of the

167
horizontal side length and side edge
length of the iron gasket (filling
block).

Position deviation mm 3 Steel tape measurement

Elevation deviation mm 5 measure with gradienter

Embed lifting Measuring with leveling


Levelness mm/m 2
bolt subplates rod

Local gaps from the


Feeler gauge
filling blocks of lifting mm 0.08
measurement
bolts

the contact is in good condition and


Contact between lifting bolt filling block hand feeling
free from tilting

Lower than the pedestal plane by Depth gauge or Straight


Crest height mm
Stone bolts of about 5 steel ruler measurement
counter sinks Swing (loose) Firm, reliable, welded joints are free
Observation
prevention welding from flaws

In accordance with provisions of table


Base plate grouting baffle installation
4.3.3

4.6.2 Generator rotor check


Application scope: this part is applicable to inspection of generator rotors, including
inspection of generator rotors and tightness test of rotors.
1 See Table 4.6.2-1for inspection and acceptance of generator rotors
Table 4.6.2-1 Generator Rotor Check
Inspection method
Inspection item Property Unit Quality criteria and measuring
instrument

Dry, clean, positive and


Ventilating duct hole Clean, unimpeded, free from stems negative gas injection
Hydrogen cooled
with compressed air
rotor
Ellpticity at the shaft Measurement by using
mm 0.03
seal outside micrometer

Flutter of water inlet Measure with dial


Water cooled rotor mm 0.05
stub pipes gauge

Cooling water Observation, trial


passage of the the inner part is clean and unimpeded ventilating of the clean
packing set compressed air

The Internal is clean, the return


Water diversion box passage is correct and the connection Observation
with the water pipe is reliable

Water diversion Stainless steels are usually used and


Observation
corner the joint welding shall be firm.

168
Observation, trial
Compound insulation
the inner part is clean and unimpeded ventilating of the clean
driving pipes
compressed air

Firmly fixed, locknuts have locking Re-tightening for trial


Equilibrium weight dominant
devices run

Slot wedges free from looseness hand feeling

Smooth and clean, free from rust,


Appearance of axle necks and shaft seal dominant Observation
pockmark and damage

Elasticity mm 0.03 Measurement by using


outside micrometer, use
the difference between
the maximum and the
Shaft neck Non-cylindrical
mm 0.03 minimum diameter of
degree
the longitudinal section
of the same cross
section

Floating
dominant mm 0.03
displacement
Measure with dial
Flutter in the radial
gauge
Solid coupling direction of the mm 0.04
circumference

Meet the requirements of


End face seam mm
manufacturer

2 See Table 4.6.2-2for inspection and acceptance of rotor tightness test.


Table 4.6.2-2 Rotor tightness test
Inspection method and
Inspection item Property Unit Quality criteria
instrument

As for hydrogen cooled rotor, use


oil-free, dry, clean compressed air or Check the chemical
Testing medium
nitrogen and use desalted water with examination list
rotor

Standard measuring
Test pressure dominant MPa Meet the requirements of manufacturer
with pressure gauge

Duration of test dominant h Meet the requirements of manufacturer Timing

the proportion of the pressure drop


dominant Meet the requirements of manufacturer Calculation
to the initial pressure

4.6.3 See Table 4.6.3 for inspection and acceptance of stator hoisting and emplacement
Table 4.6.3 Stator Hoisting Positioning
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

No damage on equipment; accurately


Stator hoisting and positioning dominant Observation, measuring
positioned

169
Stator air duct, ventage, ventilation Clean, free from dust, scrap and foreign
Observation
slot bodies

Insulated Distance to the end cap mm 20


water Observation
Water pipes and their Keep clear of each other, free from bent
pipes
positions and shriveled

Flat, smooth, clean, free from burr and


Contact surface of the stator support hand feeling
bulge

Use feeler gauge


measurement on the
Partial gaps of adjustable gasket mm 0.05
support, gasket and
pedestal

Flange studding hole of the stator It shall not penetrate shell wall Observation

Appearance of the joint Flat, smooth, free from burr and radial
dominant Observation
surface delve
Stator
Tighten 1/3~1/2bolts,
end cap
inspecting with a feeler
flange Joint surface gap dominant mm 0.05
gauge on the horizontal
and vertical joint surface.

Appearance of the seal packing The inwall is smooth and sections are
Observation
delves of the joint surface uniform

Glue filled pore canal Unimpeded, alien to the groove Ventilation inspection

Permanent gasket gaps of the two


mm 0.05~0.08 Feeler gauge measurement
sides of the locating plate

Gap between the anchor bolt nut


mm 0.03~0.25 Feeler gauge measurement
gasket and base

4.6.4 See Table 4.6.4 for inspection and acceptance of stator tightness test
Table 4.6.4 Stator Tightness Test
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Winding insulation
Meet the requirements of Measuring with 1000 V
and electric dominant
manufacturer insulation resistance meter
resistance
Water Temporarily filter
Screen
pressure screen 200 Observation
mesh
Pretest specification

inspection Check the chemical examination


Water quality Solidified water or desalted water
list

Winding insulation
Meet the requirements of Measuring with 1000 V
air and electric dominant
manufacturer insulation resistance meter
pressure resistance

Testing medium Nitrogen or clean dry compressed

170
air

Meet the requirements of Measuring with standard


Pressure dominant MPa
Hydraulic manufacturer pressure gauge

pressure Time h 8 Timing


test Inspection of watercourse joint,
Tightness dominant No leakage
insulating hose and end coil bar

Meet the requirements of


pressure dominant MPa Measuring with pressure gauge
manufacturer
Gas
Meet the requirements of
pressure time h Timing
manufacturer
test
Meet the requirements of
tightness dominant calculation
manufacturer

Water accumulated
Flush out Inspection of gas injection
inside
Water
Winding insulation
pressure Meet the requirements of Measuring with 1000 V
Posttest and electric dominant
manufacturer insulation resistance meter
inspection resistance

Winding insulation
Gas Meet the requirements of Measuring with 1000 V
and electric dominant
pressure manufacturer insulation resistance meter
resistance

4.6.5 See Table 4.6.5for inspection and acceptance of insertion of generator rotors
Table 4.6.5 Insertion of Generator Rotor
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Inspection of the joint The expose is good and the


surface direction is correct
Inner
Joint inspection for inner
end Shall have no staggered joints Observation
circle of the split
caps
Steady nails, tighten bolts and take
Installation of inner end caps
measures of anti-looseness

Inspection for cleaning of stators and


dominant Clean and impurity-free inside Observation
rotors

Meet requirements of
Electricity and thermal examination DL/T5161.1~5161.17 and
DL/T5210.4

Equipment have no impact and


Crossed rotors dominant Observation
damage

4.6.6 See Table 4.6.6 for inspection and acceptance of pedestal mounting for inlet and outlet
water
Application scope: this table is applicable to the double-water internal cooling generator set.
Table 4.6.6 Inlet and Outlet Water Pedestal Mounting
Inspection method and
Inspection index Unit Quality criteria
Property instrument

171
Flat, smooth, free from burr and
Support base plates contact pedestals tightly contacted with the Observation
pedestals

Free from foreign bodies, such as


Carry out appearance inspection
casting sand, crack and rust, the
with a 5loupe magnification or
inner inlet and outlet water
Inspection for cleaning a 10loupe magnification and
passage shall be clean and free
inspect the inlet and outlet water
from welding beading, rag and
with a endoscope
skin lamination.

The surrounding temperature is


above 5 and top up water and
Watering leakage test dominant Water inlets are all leakage free
keep it for 24h and carry out
observation

The axial distance between the water Meet the shafting expansion
inlet cover and the water inlet stub dominant mm requirements and normally is Straight steel ruler measurement
pipe around 35

Clean, meet the requirements of


Observe, check the document of
Filler of the water inlet cover manufacturer and shall have no
the manufacturer
metal fibers

Inspection of the water inlet support Measuring with 1000 V


dominant M 0.5
insulation insulation resistance meter

Contact with the rotor Tightly contacted and have bouncy Observation
Water 0.5, uniform on the right and left
deflector Radial clearance mm side and the crest is slightly bigger Inspecting with a feeler gauge
than the butt end

4.6.7 See Table 4.6.7 for installation and inspection of generator end cap bearings.
Application scope: this part is applicable to the inspection of generator stator emplacement,
including the installation of generator end cap bearings
Table 4.6.7 Generator End Cap Bearing Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

In accordance with provisions of


Shaft bearing bases shall be cleaned.
table 4.3.14

Meet those specified in Table


Bearing bush check
4.3.15 and Table 4.3.16

Partial gap between the shaft bearing


Tightening the bolts and
cover and the horizontal integration mm 0.05
measuring with a feeler gauge
plane of the shaft bearing cover

Shaft bearing cover contact with the The expose is uniform, free from
Painting inspection
bore lateral part looseness and jam

Inspection Inspect the layer joint surface


Layer gaps dominant mm 0.05
for after putting on the rotor.
insulation Horizontal split Parallel with the internal and Ruler inspection

172
boards external tile covers

Measuring with 1000 V


Insulation resistance of the tile cover dominant M 0.5
insulation resistance meter

The gap between the shaft neck crest Meet the requirements of Pressure fuse, measurement by
dominant mm
and the bearing bush manufacturer using outside micrometer

Left and right sides oil-block edge Meet the requirements of


dominant Feeler gauge measurement
gaps manufacturer

Measuring with feeler gauge and


Lateral part gap depth mm 15~20
ruler

Feeler gauge with dissimilar


Oil wedge shape Wedge is uniform thickness, the at different
wedging depth

Installation of dowel pins on the There are some clearance of the Push and pull, measure with
bearing bush crest periphery and the bottom depth gauge

Meet the requirements of


Spherical face gap mm Pressure fuse
manufacturer

4.6.8 See Table 4.6.8 for inspection and acceptance of adjustment of air gap and magnetic
force center
Table 4.6.8 Adjustment of Air Gap And Magnetic Force Center
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Measure with depth gauge on the


upper, lower, left and right
Deviation of measured value and
dominant mm 1 quatres of the same section of
average value of air gap
both ends of the stator, push and
pull

Corresponding points of both


Deviation of measured value and
dominant mm ends of the stator and measuring
specified value of magnetic center
with straight steel

Meet the requirements of the


The axial space between the rotor drawing, And meet the
dominant mm Straight steel ruler measurement
spindle shoulder and the tile edging requirements of largest thermal
expansion values

4.6.9 See Table 4.6.9 for inspection and acceptance of fan gap adjustment
Table 4.6.9 Fan Gap Adjustment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flanged Smooth and clean, free from free


appearance Observation
edge, of flaw and mechanical damage
tightly Mark with number, meet the
Position, angle dominant Check the drawing
locked requirements of manufacturer

Meet the requirements of


Installation of fan blades
manufacturer

173
Fan blade fastens the Meet the requirements of
dominant Torque spanner
moment manufacturer

Inspection of fan blades by The noise shall be solid and Knock fan blades of the two
dominant
listening to the sound uniform, free from mute sides with a copper rod

Gasket Observation

Match with the inner end Inner end caps fall into the seam
Observation
cap seam and compact the bottom seam

In good condition, free from


Joint surface contacting Observation
warping
Fan
Joint surface set pins and Uniformly tightened, take
guard dominant Observation
bolts anti-looseness measures

Measuring with feeler gauge on


Meet the requirements of
Fan gaps dominant nun 8 points of the blade
manufacturer
circumference

4.6.10 See Table 4.6.10 for inspection and acceptance of sealing pad installation
Table 4.6.10 Sealing Pad Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

The vertical joint surface shall be


burr free, the oil holes and oil
Appearance inspection chambers shall be clean, hand feeling and observation
unimpeded, and free from scraps
and welding slag.

Inspection for the pipe Clean, the meshing shall be in


connector for sampling good condition and compress the Trial erection inspection
Sealing
screw threads seal
pad base
The surface contact area of
dominant >75%, uniform Coloring method
the horizontal integration

Contact gap dominant mm <0.05 Tighten the bolts on the


Vertical horizontal integration of the
joint Flat, smooth and free from tilting fillet, contact the panel
Assembling dominant
surface staggered joints and inspecting with a feeler
gauge

Tighten bolts on the horizontal


Lateral contact of the sealing pad base integration plane, inspection of
dominant Even contact
core-cavity painting of sealing pads and
tilting fillets

Sealing Free from hole, slag inclusion,


Black bronze appearance Observation
pad cracks and pits
inspection Inspection of black Coal-soaked oil or penetrating
Free from bodiless
bronze bodiless fluid check

Oil hole and annular oil Clean, unimpeded, free from


Observation
chamber scale, scrap and foreign bodies

174
The first and second half tiles
shall be upended on the panel
Split contact area dominant >75%, uniform
and carry out painting inspection
of the division plane.

Tighten the split bolt, contact


Ring casing side surface
dominant mm <0.05 with the panel and inspecting
contacts the partial gap
with a feeler gauge

Measuring the thickness of the


Side surface parallel
dominant mm 0.03 circumference with the outside
misalignment
micrometer

Meet the requirements of Measuring with dial gauge and


Total radial clearance dominant mm
Sealing manufacturer feeler gauge
pad gap Meet the requirements of
Axial total clearance dominant mm
manufacturer

Calculate quatres in the vertical


Peripheral gap difference
mm 0.15 and horizontal direction of the
of the shaft neck
shaft neck

Gasket material Nitrile rubber pads checking

Insulator arrangement In good condition Observation


Installation
Tilting fillet internal state dominant Flexible and block-free Trial run
of sealing
Carry out inspection with depth
pad base Crest stop bolt
gauge and vernier caliper

All the bolts and nuts shall be


Assembling Observation
sealed.

Meet the requirements of Measuring with 1000 V


Insulation against ground dominant M
manufacturer , normally0.5 insulation resistance meter

4.6.11 See Table 4.6.11for inspection and acceptance of steam turbine - generator coupling
centre alignment
Table 4.6.11 Coupling Centre Alignment Of Steam Turbine - Generator
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

In accordance with manufacturer


Measuring with feeler gauge,
mark; offset by floating
Coupling relative position chock or dial gauge
displacement if there is no
marks.

Deviation of measured
Coupling central height difference
center value and reserve value dominant mm 0.02
deviation required by the
manufacturer

Right-left center deviation dominant mm 0.02

Deviation of measured dominant mm 0.03


lower gape value and

175
reserve value required by
the manufacturer

Right-left gape deviation dominant mm 0.03

Measurement by using outside


Coupling gasket thickness deviation mm 0.02
micrometer

4.6.12 See Table 4.6.12 for installation and inspection of generator oil catch installation
Table 4.6.12 Generator Oil Catches Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

The wedging depth of 0.05 feeler


Split contact mm gauge shall not exceed 1/4of the Inspecting with a feeler gauge
joint surface width

Unimpeded, the direction shall be


Drain hole correct and the section meets the Observation
oil discharge.

End Edge thickness of the oil Push and pull, measure with
mm 0.1~0.2
cap oil catch plate depth gauge

catch Oil catch plate margin Free from zigzag type and warp Observation

Meet the requirements of Within the range of 90 radian,


Oil catch gap mm
manufacturer measuring with a feeler gauge

Installation of the inner


Bolt on, sealed firmly
grease retainer plate

Electric resistance for the Meet the requirements of Measuring with 500 V insulation
dominant M
ground insulation manufacturer , normally>0.5 resistance meter

Partial gap of split surface


mm <0.10 Feeler gauge measurement
contact

Push and pull, measure with


Edge thickness mm 0.15~0.20
depth gauge
Support Unimpeded, the direction shall be
oil Oil drain hole correct and the section meets the
catch oil discharge.

Meet the requirements of Within the range of 90 radian,


Oil catch gap mm
manufacturer measuring with a feeler gauge

Installation of the inner


Bolt on, sealed firmly Observation
grease retainer plate

Partial gap of split surface


mm 0.10 Measuring on the bearing bush
contact
Bearing
Meet the requirements of Within the range of 90 radian,
bush Oil catch gap mm
manufacturer measuring with a feeler gauge
oil
Oil catch installation Bolt on, sealed firmly
catch
Installation of the inner
Bolt on, sealed firmly Observation
grease retainer plate

4.6.13 See Table 4.6.13 for inspection and acceptance of the installation of seal of generator

176
end cap
Table 4.6.13 Installation of Seal of Generator End Cap
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

The internal installation is


finished, meet relevant
Internal inspection dominant Observation and record
requirements, clean and free from
impurity

Meet requirements of
Electricity and thermal examination DL/T5161.1~5161.17 and Examination record
DL/T5210.4

Joint surface and seal groove shall


End cap flange joint surface Observation
be clean

The installation shall be complete,


Positioning pin Trial run
tight and free from looseness

Bolt Uniformly fastened Knocking and listening

Filling sealing gum dominant Fill compactly Placement method inspection

4.6.14 See Table 4.6.14 for inspection and acceptance of the installation of hydrogen cooler
Table 4.6.14 Installation of Hydrogen Cooler
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean, free from


Water chamber casting sand, dust
and rust stain

The pipe inside is


unimpeded, the pipe
outer wall shall be
Cooling water pipe
clean, free from
impurity and the heat
disassembly dissipation skeins are
Observation
inspection Clean, flat, smooth,
Joint surface of flange free from burr and
radial delve

Free from
deformation, clean,
Enclosure
the paint has no
shedding

The laying direction of the cooler Vertically or inclined


hydraulic pressure placed

Meet the
Hydraulic Measuring with pressure
Test pressure dominant MPa requirements of
pressure test gauge
manufacturer

time dominant min 30 Timing

177
tightness dominant No leakage Comprehensive inspection

3%Total cooling
Allowable plug pipe number Observation
tube number

Free from jam and


Cooling room assembling Assembling inspection
looseness

Connected, have
enough expansive
force and the
Installation of wind-shielding rubber Observation
concave formed by
the rubber is in the
airflow direction.

Meet the
Materials dominant requirements of
Joint surface pad manufacturer
(filling)materials Meet the
Section size dominant mm requirements of
manufacturer
Installation of Flat, smooth, in good
hydrogen condition and have
appearance
coolers adequate elastic
Compensate gasket property

Meet the
Thickness mm requirements of
manufacturer

Appearance is
beautiful, convenient
Air release and installation of water for operation,
Observation
blow-down pipes connect to the
discharge pipe by
water drain funnel

With direction steel


Installation Position of the hydrogen impression marks and
Observation
cooler shall not be
misplaced.

Application scope: it is applicable to installation of generator exciters, including inspection of


exciter stators and rotors, exciter bearing installation, coupling centre alignment of exciters,
dowel pin and outer cover installation of exciter pedestals and adjustment of the air gap and
magnetic center of exciters, adjustment of fans, air dampers, and oil catch gaps of exciters and
installation of air coolers.
1 See Table 4.6.15-1 for inspection and acceptance of stators and rotors of exciters.
Table 4.6.15-1 Inspection of Stators and Rotors of Exciters
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Inspection Drawing, crossing rotors Free from impact and damage Observation

178
of stators Stator air duct and Clean, free from dust, scrap and
Observation
and rotors ventage foreign bodies

Foundation frame
Inspecting with a feeler gauge on
contacts with the Contact tightly
the periphery.
pedestal

Adjustable gasket gross Push and pull, measure with


mm 2~3
thickness depth gauge

Smooth and clean, free from rust,


appearance Observation
pockmark and damage
Shaft Measurement by using outside
Ellipticity mm 0.03
neck micrometer

Non-cylindrical Measurement by using outside


mm 0.03
degree micrometer

Equilibrium weight of Fixed, tightly locked and take


Observation
all the parts of the rotor anti-looseness measures

Floating displacement dominant mm 0.03 Measure with dial gauge


Solid
Flutter of the
coupling dominant mm 0.04 Measure with dial gauge
circumference

2 See Table 4.6.15-2 for inspection and acceptance of the exciter shaft bearing installation
Table 4.6.15-2 Exciter Shaft Bearing Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Inspection Shaft bearing base inspection for In accordance with provisions


of shaft cleaning of table 4.3.14
bearing Shaft bearing base contact with Flat, smooth, free from burr Inspecting with a feeler gauge
installation the foundation frame and tightly contacted on the four angles

Gross Push and pull, measure with


mm 3
Steel plate washer thickness depth gauge
adjustment Layer
layer 2~3
number

Flat, smooth, free from


Inspect the appearance with a
Insulation warping, the thickness is
appearance micrometer, measuring with a
boards uniform and have good
insulation resistance meter
insulating property

Layer number Layer 2

Thickness Ordinary mm 3
of the Crossed Push and pull, measure with
single with lead mm >5 depth gauge
sheet wires

Overlapping Ladder type overlapping, lap


width >20mm, Gross thickness
of the overlapping shall be the
same with the single sheet 179
thickness

Shape of the four


Arcs of circles Observation
angles

More extrusive than the shaft


Dimension of the layer
mm bearing base or the periphery Observation
plate
of the upper gasket

Longitudinal
mm/m Next to shaft neck Levelness
level
Shaft bearing base measure with gradienter
Transverse
mm/m 0.20
levelness

Electric resistance for the ground Measuring with 1000 V


dominant M 0.5
insulation insulation resistance meter

Conform to those specified in


Shaft bearing inspection
Table 4.3.15 and Table 4.3.16

Meet the requirements of


Top dominant mm Pressure fuse
manufacturer

Measuring with a feeler gauge


Meet the requirements of
Lateral part dominant mm on four angles of the tile
Bearing gaps manufacturer
edging

Feeler gauge with dissimilar


Shape of the oil
Uniform wedged thickness, the at different
clearance
bearing wedging depth
installation There is some gap between the
Dowel pins on the bearing bush Push and pull, measure with
mm pin hole periphery and the
crest depth gauge
bottom

Tightening force of the bearing Meet the requirements of


dominant mm Pressure fuse
bush spherical face manufacturer

Shall be larger than the Straight steel ruler


Axial space between the shaft
mm maximum elongation value of measurement according to the
shoulder and the bearing bush
the thermal expansion manufacturer drawing

3 See Table 4.6.15-3for the inspection and acceptance of coupling Centre alignment of
exciters
Table 4.6.15-3 Coupling Centre Alignment of Exciters
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Meet the requirements of


Circumference deviation dominant mm
manufacturer, nornally0.04

Meet the requirements of


Solid Right-left gape deviation dominant mm Measuring with dial gauge, feeler
manufacturer, nornally0.03
coupling gauge and block gauge
The deviation between the
Meet the requirements of
upper and lower gapes and dominant mm
manufacturer, nornally0.03
the manufacturer reserve

180
values

Radial direction flutter of the rotor Meet the requirements of Measure with dial gauge after
dominant mm
end manufacturer coupling bolt on

4 See Table 4.6.15-4 for inspection and acceptance of installation of dowel pins and outer
covers to the exciter pedestals
Table 4.6.15-4 Pedestal Dowel Pin and Outer Cover Installation to the Exciter
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument

Specification of the Meet the requirements of


position and number manufacturer
Positioning
Fitness of pin and hole conical
pin Conical degree Observation
degree

Bottom hole gap mm Around 5 Depth gauge measurement

Clean, flat, smooth, galvanic


brightness, the skeleton shall be
appearance fast, screw holes shall be Observation
complete, and the position shall
Outer
be correct.
cover
The air throttles are flexible, the
air throttles and inspection holes
Installation Observation
are tightly shut down and firmly
installed.

5 See Table 4.6.15-5 for the adjustment of the exciter air gap and the inspection and
acceptance of magnetic center.
Table 4.6.15-5 Adjustment of Exciter Air Gap and Magnetic Center
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Measure with wedge gauge or


Deviation of measured value and special tools at upper, lower, left
Dominate mm 5% of the average value
average value of air gap and right positions of both ends
of rotor

Measure with straight steel ruler


Deviation of measured value and
Dominate mm 1 at the corresponding position at
specified value of magnetic center
both ends of rotor

Note: It is applicable to the installation of exciter with AC brushless excitation system and not applicable to the installation of
exciter with auto excitation type static state excitation system

6 See Table 4.6.15-6 for the adjustment of exciter fan, windshield and oil catch gap.
Table 4.6.15-6 Adjustment of Exciter Fan, Windshield and Oil Catch Gap
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Fan blade inspection Fan is intact without damage and Knocking and listening

181
the sound is normal

Deviation of measured value and


Dominate mm <10%, and the gap>1.5 Measuring with feeler gauge
average value of fan gap

Radial clearance of windshield Dominate mm 0.20~0.50 Measuring with feeler gauge

Oil Partial gap of split surface


mm <0.10 Measuring with feeler gauge
catch contact

Edge thickness mm 0.1~0.2 Measuring with vernier caliper

Meet the requirements of


Gap of oil catch Dominate mm Measuring with feeler gauge
manufacturer

7 See Table 4.6.15-7 for the inspection and acceptance on installation of air cooler.
Table 4.6.15-7 Installment of Air Cooler
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean, without casting sand or


Water chamber inspection Observation
sundries

Shall be according to the


specification of manufacturer; if
Pressure Dominate MPa there is no specification by Measuring with pressure gauge
Water
manufacturer, according to 1.25
pressure
times of working pressure
test
Time min 5 Timing

Tightness Dominate Without leakage Complete inspection

Plugging pipe number 3% of the total cooling pipe Observation

Gasket material of air duct


Hair pad Observation
joint surface
Cooler
Slope
mm/m Slope 3~5 to the drainage side Measurement along total length

Clean and dipped with thick oil


Air filter element and the surplus thick oil shall flow Observation
up

Installation solid, supporter and


hanger correct, joint surface close
Air duct installation Observation
and without leakage, and clean,
paint 2 light color paintings

Note: It is applicable to the installation of exciter with AC brushless excitation system and not applicable to the installation of
exciter with auto excitation type static state excitation system

4.6.16 See Table 4.6.16 for the inspection and acceptance on installation of carbon brush
yoke
Table 4.6.16 Installation of Carbon Brush Yoke
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance inspection Cleaned up without iron chips or Appearance inspection

182
other sundries

Measuring with straight steel


Radial clearance of slip ring Gap around is uniform
ruler

Measuring with a straight steel


Brush Radial clearance mm 2~3
ruler or a feeler gauge
box
Shall meet the expansion Measuring with straight steel
Difference of axial center
requirements ruler

Insulation resistance value against Measuring with 1000V


M 0.5
ground of conducting ring insulation resistance meter

Note: This table is applicable to the installation of exciter with auto excitation type static state excitation system

4.6.17 See Table 4.6.17 for the inspection and acceptance of air pressure test for whole set
of generator.
Table 4.6.17 Air Pressure Test for Whole Set of Generator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of


Seal oil pressure MPa Pressure gage value
Preparation manufacturer
before test Water pressure of < (0.1~0.15) test wind pressure
MPa Pressure gage difference
hydrogen cooler value of generator

Measuring with u-shaped


Meet the requirements of
Test pressure Dominate MPa mercury pressure gauge or
manufacturer
accurate pressure gauge

Continuous test duration Dominate h 24 Timing


Air Calculate after the measurement
pressure of start and end atmospheric
test pressure, gas temperature,
Meet the requirements of
Air leakage Dominate U-shaped mercury pressure
manufacturer
gauge display or after the
measurement of inclined type
differential manometer

4.6.18 Installation of sealing oil system


Application scope: It is applicable to installation of sealing oil system of generator, including
installation of screw rod type sealing oil pump and other equipments; see Table 4.3.33 for the
installation of sealing oil devices; refer to Table 4.5.6-9 and 4.5.6-10 for the installation and
flashing of sealing oil pipe.
1 See Table 4.6.18-1 for the inspection and acceptance on installation of screw rod type
sealing oil pump.
Table 4.6.18-1 Installation of Screw Rod Type Sealing Oil Pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Without casting sand or crack and


Inspection Pump inspection Observation
clean

Total radial Measuring with


Screw rod and Dominate mm Meet the requirements of

183
bushing of main manufacturer, and is generally
shaft 0.07~0.13

Meet the requirements of


Idler spindle and
Dominate mm manufacturer, and is generally
bushing
0.05~0.12
inside/outer micrometer
clearance Meet the requirements of
Shaft sleeve and and dial indicator
mm manufacturer, and is generally
thrust bush
0.03~0.08

Meet the requirements of


Screw rod and
mm manufacturer, and is generally
thrust bush
0.02~0.05

Meet the requirements of


Gap between the idler spindle and
Dominate mm manufacturer, and is generally Pressure fuse
the upper cover end face
0.3~1.9

Gasket material
Oil proof gasket

Circumference
Coupling mm 0.10 Measuring with flat bevel
deviation
centre scale slit method, feeler
End surface
Installation alignment mm 0.10 gauge or dial indicator
deviation

Esthetic for technology, firm and


Enclosing cover of coupling Observation
convenient for maintenance

Hand feeling and sound


Discal motion of pump rotor Nimble and block-free
hearing

Measuring with pressure


Outlet pressure of pump To rated value and being stable
gauge

Measuring with vibration


Vibration Dominate mm 0.05
By-part gauge
Bearing
trial Measuring with
Temperature Dominate 65
operation thermometer

Appearance inspection
Mechanical sealing Without leakage and heating
and hand feeling

Continuous test run time h 4~8 Timing

2 See Table 4.6.18-2 for the inspection and acceptance on installation of other equipments.
Table 4.6.18-2 Installation of Other Equipments
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean in the tank Clean without rust or sundries Observation

Flexible and reliable; accurate in


Oil Liquid level annunciator Test
movement
sealing
Measurement based on reference
tank Elevation deviation mm 10
line

Position installation Meet the requirements of the

184
drawing

Meet the requirements of


Installations direction Observation
manufacturer
Pressure
Trial operation
difference Piston action Flexible and block-free
valve
Meet the requirements of the
Piston weight
drawing

Meet the requirements of


Balanced Installations direction Observation
manufacturer
valve
Piston action Flexible and block-free Trial operation

Internal Clean without rust or sundries Observation

Leveling with glass tube or


Hydrogen Elevation deviation mm 10
measuring with level
isolating
Leveling the height difference at
device
Horizontal deviation mm/m 2 both ends of glass tube or
measuring with level ruler

4.6.19 Installation of the equipments and pipelines of internal cooling water system
Application scope: It is applicable to the installation of equipment and pipe of generator
internal cooling water system, including installation of internal cooling water pump, cooling
water tank, cooler, ion exchanger, internal cooling water conduit and the flashing of internal
cooling water system.
1 See Table 4.6.19-1 for the inspection and acceptance on installation of internal cooling
water pump.
Table 4.6.19-1 Installation of Internal Cooling Water Pump
Inspection method and
Inspection item Property Unit Quality criteria
instrument

Stainless steel material, smooth Observing, carry out spectrum


Flow passage part
and clean without sundries inspection if necessary

Meet the requirements of


Pump shaft
Inspection Dominate mm manufacturer, and is generally
0.05

Meet the requirements of The pump shaft is set on


Excircle of
Radial flutter mm manufacturer, and is generally v-shaped iron and measuring
shaft sleeve
0.08 with dial indicator

Meet the requirements of


Impeller
mm manufacturer, and is generally
sealing ring
0.08

Impeller in Meet the requirements of


radial Dominate mm manufacturer, and is generally Measuring with vernier caliper
Sealing ring direction 0.4~0.47
gap Impeller in
Measuring by push and pull
axial Dominate mm 3
method or with depth gauge
direction

185
Meet the requirements of
Axial clearance of bearing Measuring with depth gauge or
mm manufacturer, and is generally
at expansion end pressure fuse
0.30~0.40

Meet the requirements of


Circumference
mm manufacturer, and is generally
deviation Measuring with flat bevel scale
0.10
slit method, feeler gauge or dial
Meet the requirements of
Coupling End surface indicator
mm manufacturer, and is generally
Installation centre deviation
0.08
alignment
Meet the requirements of Measuring with straight steel
Spacing mm
manufacturer, and is generally 2 ruler

Solid and esthetic for technology,


Enclosure Observation
convenient for maintenance

Designation Meet the requirements of Check against specification of


Lubricating manufacturer lubricating oil
oil Oil level
Normal Oil scale observation

Measuring with vibration


Vibration Dominate mm 0.05
Bearing gauge

By-part Temperature Dominate 65 Measuring with thermometer

trial Appearance inspection and


Sealing device Dominate Well sealed without being heated
operation hand feeling

Stability after reaching rated


Outlet pressure Dominate MPa Measuring with pressure gauge
value

The operation of cylinder is


Operation condition smooth, sound in pump is normal Observation
and without impact

Continuous test run time h 4~8 Timing

2 See Table 4.6.19-2 for the inspection and acceptance on installation of cooling water tank,
cooler and ion exchanger.
Table 4.6.19-2 Installation of Cooling Water Tank, Cooler and Ion Exchanger
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Material quality
Stainless steel Observation

Internal cleaning Clean without rust or sundries Observation


Inspection
of cooling Watering test Dominate Without leakage 24h

water Water level gauge Clean, transparent and with shield Observation
tank
Liquid level annunciator Flexible, accurate and reliable Test check

Inflation pressure Meet the requirements of


warning indicator manufacturer

186
Material quality Stainless steel Observation

Intact, correct of specification,


Appearance inspection Inspection according to drawing
model, interface and position
Cooler
Meet the requirements of
inspection
manufacturer; if there is no
Timing and measuring with
Water pressure test Dominate MPa requirements by manufacturer,
pressure gauge
according to the 1.25 times of
work stress and maintain 5min

Material quality Stainless steel Refer to material certificate

Ion Tightness inspection Without leakage Water inspection


exchanger
Meet the requirements of
Resin inspection
manufacturer

3 See Table 4.6.19-3 for the inspection and acceptance on installation of internal cooling
water pipe.
Table 4.6.19-3 Installation of Internal Cooling Water Pipe
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Stainless steel or corrosion


Pipe fittings and parts material Dominate Observation
resistant material

Elbow selection Cold bend or hot press elbow Observation

Backing electric welding capping


Manner
of argon arc welding or argon arc Observation
Welding welding

Contra aperture According to the specification of


Observation
DL/T 5210.5

Flange gasket material Polytetrafluoroethylene gasket Observation

Material quality Stainless steel wire Observation


Screen of filter Screen
Dimension 70 Observation
mesh

Inside clean without burr or


Inspection of stop valve, check valve
sundries and the specification Disassembly inspection
and pipe fittings
meets the design requirements

In the right direction, convenient


Stop valve installation for operation and arranged in Observation
order

Position correct, firm and


Supporter and hanger installation Observation
technology esthetic

0.15% of the total height and the Measuring by suspending a


Pipe Vertical misalignment mm
maximum 7 plumb bob along total height
installation
Horizontal gradient mm/m Slope 3~5 to the drainage side Measuring and observing

187
Quantity and position is correct
Installation of pressure gage,
and meet the requirements of
thermometer and measuring orifice
DL/T 5210.4

The insulation value of water inlet lug


Measuring with 1000V
support for the pipeline and generator Dominate M 0.5
insulation resistance meter
rotor

4 See Table 4.6.19-4 for the inspection and acceptance of internal cooling water system
flashing.
Table 4.6.19-4 Internal Cooling Water System Flashing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Flushing Flush water quality Qualified desalted water Chemical examination


of
Inspection of flushing No obvious change of water Sampling chemical examination
external Dominate
results quality at the inlet and outlet of continuous flushing
pipeline

Transparent and pure without


Purity degree Observation
mechanical impurities
Flushing
Water Conductance Dominate S/cm 1.5 Chemical examination
of the
quality
whole set Hardness mol/L 2 Chemical examination

of system pH value 6.8~8.0 Chemical examination

NH3 value Slight amount Chemical examination

4.6.20 Installation of the equipments and pipelines of gas system


Application scope: It is applicable to the installation of equipments and pipe of generator gas
system, including installation of gas system equipments, gas system pipe and gas pipeline air
pressure test.
1 See Table 4.6.20-1 for the inspection and acceptance on installation of gas system
equipments.
Table 4.6.20-1 Installation of Gas System Equipment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Equipment such as pressure gage,


vacuum gauge, pressure regulator,
Equipment inspection Dominate hydrogen filter, rubber valve, Verification and inspection
safety valve and magnetic valve
shall be complete and intact
Gas
Measurement based on
control Position deviation mm 10
reference line
station
Measuring by suspending
Verticality deviation mm/m 1.5
plumb bob

Straight and even, regular and


Bottle rest and fence esthetic, moderate in height and Observation
convenient for application

188
Clean without rust or sundries and
Appearance the sight hole is smooth, clean and Disassembly inspection
transparent

Meet the requirements of


Hydrogen Material of joint surface
manufacturer
dryer
According to inspection method
Drying agent Meet the requirements of quality
of manufacturer

Measurement based on
Position deviation mm 10
reference line

2 See Table 4.6.20-2 for the inspection and acceptance on installation of gas system
pipeline.
Table 4.6.20-2 Installation of Gas System Pipeline
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of the


Tubes and pipes
drawing

Clean without rust, oil sludge or


Internal inspection of pipes Observation
sundries

Bottoming with argon arc welding


Manner Observation
and capping with electric welding
Welding
According to the specification of
Contra aperture
DL/T 5210.5

Measuring by suspending a
Vertical misalignment Dominate mm 0.15% of the total height, and 7
plumb bob along total height

Measuring with glass tube


Horizontal gradient Dominate mm/m 3~5 (to the drainage side)
gradienter

Drain pipes Installed at the lowest point Observation


Pipe
Discharge to the ventilation
installation Emptying pipe Observation
position out of the plant

Inspect by clean and dry white


Without impurity, water drop or oil filter paper at the exhaust outlet
Pipe purging
drop after the purging by clean, dry
and deoil compressed air

Meet the requirements of


Type Dominate Observation
manufacturer
Valve
Meet the requirements of
Gasket material Observation
manufacturer

Supporter and hanger installation Correct, firm and esthetic Observation

3 See Table 4.6.20-3 for the inspection and acceptance of gas pipeline gas pressure test.
Table 4.6.20-3 Gas Pressure Test for the Gas Pipeline
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Pressure test medium Dry and clean compressed air or Check

189
nitrogen

Measuring with U-shaped


Meet the requirements of
Test pressure Dominate MPa mercury pressure gauge or
manufacturer
vernier gauge

Pressure test time h 6 Timing

Calculation according to
Average pressure drop each hour Dominate MPa 0.1% initial pressure
measured data

4.6.21 See Table 4.6.21 for the inspection for implementation performance of subsection
project compulsory provisions of installation of generator and exciter.
Table 4.6.21 Inspection table for implementation performance of subsection project compulsory provisions
for installing generator and exciter
_________Unit Project number:
Main body installation engineering of Subsection project
Unit project name Installation of generator and exciter
turbine generators name

Project number Acceptance time Date

Implementation Related
SN Inspection item
performance information

All pipes shall be constructed according to design drawing. If it need


1 modify design or adopt substitute material, it must apply to the design
unit and handle it according to relevant system

It shall cut holes on the pipes according to design drawing before


2 installing pipes. After cutting holes, it must clean up the inside and
there shall be no drill cuttings or other foreign bodies

The construction and acceptance of steam turbine generator units must


be in accordance with approved design and the technical document
3 provided by the equipment manufacturing plant. If it need modify
equipment the above-mentioned documents, there must be certain
approval process

Before equipment installation, it must inspect the equipment as


required. If there is damage or quality defect, it shall timely inform
organizations concerned of joint inspection. As for defect in
equipment manufacture, it shall contact the Office for Research to
handle it. If the installation quality fails to meet requirements due to
4
manufacturing quality, it shall be jointly negotiated among
construction organization, manufacturing unit, building or using unit;
there shall be records as well as confirmation and signature for
construction, equipment inspection and defect treatment after reaching
installation quality standard.

190
When settlement observation is carried out for foundation, the
observation work shall be carried out together with at least the
following procedures:
(1) After curing period for foundation expires (with this measured
value as source data);
(2) Before and after all steam cylinder and generator stator of steam
turbine are positioned;
(3) Before concrete is poured by steam turbine and generator for
5
second time;
(4) After commissioning test of the complete set.
As for collapsible loess area, it shall properly increase measuring
times.
The settlement observation shall be carried out by instrument of Grade
2 precision. The observed data for each time shall be recorded at
special record book and the settlement observation point shall be
preserved properly.

The dimension of oil bag for oil hole on apical axis of lower bearing
shell shall meet the requirements of drawings. Generally, the depth
shall be between 0.20~ 0.40mm; the area of oil bag shall be
6 1.5%~2.5% (larger value for larger diameter of axle) of projected area
of axle neck; the axle neck shall be tightly close to around oil bag. The
oil-pipe head of apical axis must be firmly buried under black bronze
and ensure to be clean and smooth.

The insulated parts for insulating shaft current of generator and exciter
shall be smooth and clean and free of warping and defect; its thickness
shall be even and with good insulating property. After installation, all
7
of them shall be measured by 1000V insulation resistance meter. The
insulation resistance shall meet the requirements; generally, it shall be
0.5M

The hoisting and positioning of generator stator shall be in accordance


with the following requirements: Before hoisting and positioning of
stator, there must be approved technical scheme and safety measures;
When the cranes make hoisting under over load or by auxiliary
hoisting facilities, it must make careful check and calculation, carry
8
out careful inspection on all parts of hoisting facilities and carry out
necessary strength and performance test. It can't make hoisting before
the all results meet the hoisting requirements; it shall also test building
structures related to hoisting. If necessary, it shall carry out
strengthening.

The axial clearance values for bearing bush and shaft shoulder as well
as air fan and air damper of generator shall meet the requirements of
9
manufacturer to ensure there is no friction under full load condition
and rotor thermal expansion.

191
The official closing of generator end cap shall meet the following
requirements:
Before end cap closing, it shall carefully check the inside of generator,
where shall be free of foreign bodies; all parts shall be in good
condition and all fit clearance shall meet relevant requirements.
The check test of relevant electric and thermal meter shall be
completed and it shall be confirmed and signed jointly with relevant
personnel.
When rubber strip is used for gland packing of hydrogen-cooled and
water-hydrogen-cooled generator, its section size shall meet the
requirements and there shall be adequate elasticity and compression
amount.
When colloidal substance is used for gland packing, it shall be filled
according to the method required by the manufacturer and it shall pay
10 attention to the following two points: It shall be clean inside the
seal groove, which shall be fully filled with paint; then it shall tighten
the bolt between vertical and horizontal surface of end cap; When
compressing filled sealing material, it shall start from the filling
opening of the upper part; when the fillings exude from the next
adjacent hole, it shall block the previous hole with plug and continue
to pressurize and fill the next hole until filling all grooves.
As for the joint surface between end cap and platen as well as end cap
and casing of air-cooling and double-water internal cooling generator,
it shall tightly sealed without any leakage. If there is felt, pasteboard
and other gasket material, it shall be flat, smooth and free of
disconnection and fold; moreover, it shall be firmly compressed and
shall not be blown down.
The sealing pressure air duct on small end cap shall be smooth and
shall be aligned with pressure tuyere on large end cap

There must be quality certificate provided by the manufacturer for


shaft, guard ring and other parts of generator. Before installation, it
shall refer to relevant technical information provided by the
11
manufacturer. If there is inadequate information or quality problem, it
shall require the manufacturer to complement inspection or take
corresponding measures

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

192
4.7 Assembly and installation of water-cooled condenser

4.7.1 Installation of condenser (exhaust equipment).


Application scope: it is applicable to installation of condenser (exhaust equipment), including
assembly of condenser (exhaust equipment) enclosure as well as positioning and centering of
condenser (exhaust equipment).
1 See Table 4.7.1-1 for inspection and acceptance for assembly of condenser (exhaust
equipment) enclosure.
Table 4.7.1-1 Assembly of condenser (exhaust equipment) enclosure
Inspection method and
Inspection item Property Unit Quality criteria
instruments

Space between pipe plates and design Main Measuring with steel tape by
mm -30~0
value deviation control zones and multi-points

Verticality deviation between pipe


plate as well as clapboard and base mm/m 1 Measuring with plumb bob
plate

Central line Deviation value


of pipe
Main Meeting the requirements of
orifice on Relative misalignment mm Inspecting with pulling steel wire
control manufacturer
two direction
clapboards

The welding form shall meet the


requirements of technical
Weld space and groove of enclosure
conditions and welding code
required by the manufacturer

Measuring with pulling steel


Local bending of enclosure mm 3
wire

Measuring with pulling steel


Full-length total bending of enclosure mm 20
wire

Straightness deviation of throat top Measuring with pulling steel


mm 10
plate wire

Diagonal line deviation of throat Measuring with pulling steel


mm 20
upper end wire

Internal tie bar, baffle plate and Welding firmly, without welding
Checking according to drawing
auxiliaries skip

Open pore of condenser enclosure Without welding skip Checking according to drawing

Tightness of welded joints Without welding skip Oil penetration test

2 See Table 4.7.1-2 for inspection and acceptance for positioning and centering of condenser
(exhaust equipment).
Table 4.7.1-2 Positioning and centering of condenser (exhaust equipment)
Inspection method and
Inspection item Property Unit Quality criteria
instruments

193
Main
Concrete strength Meet requirements of drawing
control

Free from reinforcement


exposion, honeycomb, crack,
Concrete surface
cobble extruding, defects, and Observe
inspection
cleaning up interior of foundation
bolt hole

Deviation of transverse
mm 10 Inspecting with steel tape
Foundation central line

preparation Elevation deviation of


mm -10~0 Inspecting with level
foundation bearing area

Central deviation of
mm 10 Inspecting with steel tape
foundation bolt hole

Concrete surface treatment Flat chipping, tight contact and


Observe
for iron gasket without tilting in iron gasket

Correct position and no obvious


Embedded iron Observe
deflection

Geometric dimension mm 10~20 wider than side of base Inspecting with steel tape

Preparation and installation of iron In accordance with those


gasket specified in Table 4.3.5~4.3.7

Preliminary Center line deviation mm 10 Measuring with steel tape

centering Elevation deviation mm 10 Measuring with level

4.7.2 See Table 4.7.2 for inspection and acceptance for cooling tube bundle of condenser.
Table 4.7.2 Cooling tube bundle installation of condenser
Inspection method and
Inspection item Property Unit Quality criteria
instruments

Free of flaw, sand hole, corrosion


Observe by magnifier in
Appearance inspection of cooling tube pit, cross break, double skin and
5-fold~10-fold
rag

Ammonia cure test of Main Inspect by sampling 1/1000 of


Flawless
copper tube control the total copper tubes
Test on Eddy current test or water Main Meeting the requirements of DL Inspect by sampling 5% of the
cooling pressure test control 5011 total cooling tubes
tube Inspect by sampling 0.5/1000 of
Processing property test of Main
No crack or other damage the total cooling tubes; See
copper (titanium) tube control
DL5011 for inspection method

Tube plate Position and quantity of


Meet requirements of drawing Observe
inspection tube orifice

Space a between tube orifice Main


mm 0.20~0.50 Measuring with vernier caliper
and cooling tube control

No rust scale and rag; chamfer


Tube orifice of clapboard Observe
1*45

194
Non-axial groove, oil stain, rust
Cleaning up tube plate and
and rag inside hole; expose Observe
tube orifice
metallic luster

Smooth and clean, free of oil dirt,


oxidizing layer, dust, corrosion
Tube end surface Observe
pit and longitudinal groove,
Cooling
expose metallic luster
tube
Main Measuring and calculating with
assembling Expansion coefficient 4%~6%
control vernier caliper

Main
Depth of expanded joint mm 75%~90% of tube plate thickness Measuring with depth gauge
control

Main Measuring with straight steel


Exposed tube plate of steel tube mm 1~3
control ruler

Length of exposed titanium (stainless Meet welding requirements;


mm Measuring with depth gauge
steel) tube plate generally 0.3~0.5

Seal weld of titanium (stainless steel) Main


Flawless Inspect penetrating fluid
tube orfice control

Measure angle of flanging


Flanging angle of copper tube inlet 15
device

a The space between tube sheet hole and cooling tube shall ensure no excessive expansion of cooling tube; the specific value
shall be determined according to calculation.

4.7.3 See Table 4.7.3 for inspection and acceptance of connection between condenser
(exhaust equipment) and steam cylinder as well as tightness test.
Table 4.7.3 Connection between condenser (exhaust equipment) and steam cylinder as well as tightness test
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

The welding form shall meet the


Space between condenser requirements of technical
and steam cylinder conditions and welding code
required by the manufacturer
Welded Dimension of
connection upper-opening bent side of Measuring with straight steel
mm 20~50
condenser into exhaust ruler
steam cylinder

Deformation control of
mm 0.1 Monitoring with dial gauge
steam cylinder

Welding Welded connection


inspection between balancing pup
and joint as well as tie bar No leakage Watering or oil penetration test
tightness expansion joint and steam
test cylinder

Tightness test at steam side Main No leakage at expansion opening Observe after the irrigated water
control is 100mm higher than top

195
cooling tube

No foreign bodies in water


Closing of condenser end
chamber; complete tightening Observe
cap
bolt, washer and nut

Tightness inspection at Main No leakage at flange and manhole


Observe
water side control bolt

No foreign bodies at steam side


Main
Closing of condenser at steam side space; no trauma at top cooling Observe
control
tube

4.7.4 See Table 4.7.4 for inspection and acceptance for installation of condenser (exhaust
equipment) auxiliaries and secondary pouring
Table 4.7.4 Condenser (exhaust equipment) auxiliaries and secondary pouring
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Internal diameter of pipe connected Measuring with straight steel


mm >25
with water level gauge ruler

Height of U-shaped sealing water Measuring with straight steel


mm >150
pipe of connection pipe at water side ruler

Gradient at water level gauge side in


Measuring with straight steel
the direction of connection pipe at 4%~5%
ruler and level ruler
steam side

No leakage; complete and firm


Water level gauge of glass tube Watering test; observation
protective cover

Tamp concrete tightly inside hole;


Foundation bolt Observe
keep foundation bolt vertical

In accordance with those specified


Secondary pouring
in Table 4.3.20

Concrete strength of foundation bolt >70% Check measuring record

4.7.5 See Table 4.7.5 for inspection and acceptance of rubber ball cleaning system.
Table 4.7.5 Inspection and installation of rubber ball cleaning system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Ball Ball valve inspection Flexible rotation Feel by hands


installation Gland box and flange Inspection on water connection
No leakage
room tightness of system

Space between around


Less than width of grate opening Measuring with straight steel
grating and drum wall under mm
gap ruler
Ball ball receiving condition

screen Grating rotation No block Inspecting by moving hand grip

Inspecting according to
Joint position Correct
construction drawing

196
Inspecting according to
Various auxiliaries Complete
equipment drawing

Gland box and flange Inspection on water connection


No leakage
Secondary tightness of system
filter
screen
Filter screen eyelet No rag and blockage Observe

Butterfly valve rotation No jam Inspecting by moving hand grip

4.7.6 See Table 4.7.6 for inspection on implementation performance of compulsory


provision for assembly and installation of water-cooled condenser
Table 4.7.6 Inspection table on implementation performance of compulsory provision for assembly and
installation of water-cooled condenser
________Unit Project number:
Auxiliary device installation of turbine Subsection project Assembly and installation of
Unit project name
generators name water-cooled condenser

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

Before filling water, it must thoroughly clean up internal rusty


scale, weld beading and foreign bodies. The internal anticorrosive
1
coating shall be painted according to design requirements or the
study of technical section.

Before installing equipment, it must inspect equipment as required.


If there is damage or quality defect, it shall timely inform
organizations concerned of joint inspection. As for defect in
equipment manufacture, it shall contact the manufacturer for
treatment. If the installation quality fails to meet requirements due
2
to manufacturing quality, it shall be jointly negotiated among
construction organization, manufacturing unit, building or using
unit; there shall be records as well as confirmation and signature for
construction, equipment inspection and defect treatment after
reaching installation quality standard.

The quality acceptance of material shall be in compliance with the


following requirements:
The metallic material under supervision must meet the relevant
national standard and professional standard. The imported metallic
material must meet relevant national technical standards specified
3 in contract.
The steel, steel tube and space parts as well as auxiliaries under
supervision must be carried out with quality acceptance according
to quality certificate and quality guarantee. The quality certificate
or quality guarantee shall be indicated with steel type, chemical
composition, mechanical property as well as necessary

197
metallographic inspection result and heat treatment technique. As
for those with insufficient data, it shall make up for inspection. The
method, range and quantity of supplemented inspection shall meet
the national standard or relevant professional standard. The
imported metallic material shall not meet the requirements of not
only relevant national technical standards specified in contract, but
also commodity inspection qualification document.

Conclusion

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.8 Installation of air-cooling condenser system

4.8.1 Installation of steel structure


Application scope: It is applicable to steel structure installation of air-cooling condenser,
including foundation lineation, steel structure pre-assembly, bracing steel structure installation,
high-strength bolt installation of bracing steel structure, installation of fan supporting
structure and platform cover, installation of tube-bundle bracing Type-A frame and
air-stopping wall installation.
1 See Table 4.8.1-1 for inspection and acceptance of foundation lineation.
Table 4.8.1-1 Foundation lineation inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Distance deviation between


vertical and horizontal central Main Inspecting with theodolite
mm 20
line of foundation and control and steel tape
Foundation lineation (installation of column base plate)

benchmark of plant

Main
Space Column space 10m mm 1
control
deviation
Main
of pillars Column space>10m mm 2
control
Tensioning with spring
Difference Main
Diagonal line 20m mm 5 balance; measuring with
between control
steel tape; 10kN tension
central
diagonal Main
Diagonal line>20m mm 8
lines of control
pillar

Levelness deviation of column Main


mm/m 0.5 Measuring with level ruler
embedded plate control

198
Elevation deviation of
mm -10~0 Measuring with level
foundation plane

Deviation of foundation external


mm 0~+20 Measuring with steel tape
dimension

Central line deviation of


mm 5 Inspecting with steel tape
embedded foundation bolt

2 See Table 4.8.1-2 for inspection and acceptance of steel structure pre-assembly.
Table 4.8.1-2 Steel member pre-assembly
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Total length of pre-assembly


mm 5.0 Inspecting with steel tape
unit

Bending arc rise of Inspecting with steel tape


mm L/1500, and 10.0
pre-assembly unit and puling line

Multi-section Joint misalignment mm 2.0 Inspecting with weld gauge


column Inspecting with pulling line,
Column shaft distortion of
mm h/200, and 5.0 suspension line and steel
pre-assembly unit
tape

Distance between puller


mm 2.0 Inspecting with steel tape
surface and any bracket

Distance between open holes


at both outermost ends of
span and between outermost mm -10.0~+5.0 Inspecting with steel tape
sides of supporting surface
on both ends

Beam and Joint section malposition mm 2.0 Inspecting with weld gauge
truss Arch camber Main Inspecting with pulling line
mm L/5000
required in design control and straight steel ruler
Camber
Arch camber not Main Inspecting with pulling line
mm 0~+L/2000
required in design control and straight steel ruler

Malposition of member bar Inspecting with steel ruler


mm 4.0
axes at joint after scribing

Total length of pre-assembly Main


mm 5.0 Inspecting with steel tape
unit control

Pipe Bending arc rise of Inspecting pulling line and


mm L/1500, and 10.0
structure pre-assembly unit with steel tape

member Main
Joint misalignment mm t/10, and 3.0
control Inspecting with weld gauge

Groove space mm -1.0~2.0

Pre-assembly Column deviation mm 4.0 Tensioning with spring


of structure Distance deviation between balance; measuring with
mm 3.0
member beams steel tape

199
plane Difference between diagonal
mm L/2000, and 5.0
lines of frames

Difference between any two


mm L/2000, and 8.0
diagonal lines

3 See Table 4.8.1-3 for inspection and acceptance of bracing steel structure installation.
Table 4.8.1-3 Installation of bracing steel structure
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Distance between L24m mm -7.0~3.0


holes at both
outermost ends of Tensioning with spring

truss or between balance; measuring with


L>24m mm -10.0~5.0
outermost sides of steel tape

supporting surface
on both ends

Inspecting with pulling line


Mid-span arch camber of truss mm Meet requirements of drawing
and straight steel ruler

Main
H6m mm 1 Inspecting with steel ruler
Height (vertical) control
deviation Main
6<H12m mm 1.5 Inspecting with steel ruler
control

Main
L6m mm 2 Inspecting with steel ruler
Longitudinal control
deviation Main
6<H12m mm 3 Inspecting with steel ruler
control

Main
L6m mm 2 Inspecting with steel ruler
control
Lateral deviation
Main
6<H12m mm 3 Inspecting with steel ruler
control

4 See Table 4.8.14 for inspection and acceptance of high-strength bolt installation for bracing
steel structure.
Table 4.8.1-4 Installation of high-strength bolt for bracing steel structure
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Bolt hole 17mm mm 0.0~1.0 Inspecting with vernier caliper

tolerance >17mm mm 0.0~1.5 Inspecting with vernier caliper

Ellipticity of 17mm mm 1.0 Inspecting with vernier caliper

bolt hole >17mm mm 1.5 Inspecting with vernier caliper

No crack and bruise; the screw


thread is in good condition: no oil
Appearance of bolt and nut Observe
dirt, floating rust and other
attachments

200
Meet the requirements of
Inspection of bolt, nut and washer Observe
manufacturer

The surface treatment reaches the


requirements of equipment
technological documents; the
Joint surface for joint friction Observe
scale, oil dirt and dust are cleaned
up; no deformation, edge lifting,
bending and rag

Main Meet the requirements of


Bolt-up moment Inspecting with torque spanner
control manufacturer

5 See Table 4.8.1-5 for inspection and acceptance on installation of fan supporting structure
and platform cover plate.
Table 4.8.1-5 Installation of fan bridge framework and platform cover plate
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Checking against drawing and


Levelness deviation mm 2/1000 length
inspecting with level ruler

Elevation deviation mm 10 Inspecting with level


Installation Main
Final bolt-up moment Meet requirements of drawing Inspecting with torque spanner
of fan control
bridge Laying in the same direction;
framework Grating installation straight and even; uniform in gap Observe
joint; fixed firmly

Inspecting with straight steel


Grating planeness mm 3
ruler

In accordance with those


Fan deck, cover plate (grating), handrail Check against drawing; observe
specified in Table 4.3.37

6 See Table 4.8.1-6 for inspection and acceptance on installation of tube-bundle bracing
Type-A frame.
Table 4.8.1-6 Installation of tube-bundle bracing Type-A frame
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Main
Longitudinal deviation mm 10 Inspecting with steel ruler
control

Main
Lateral deviation mm 2 Inspecting with steel ruler
control

Main
Elevation deviation mm 2 Inspecting with level
control

Meet the requirements of drawing


Main Checking against drawing;
Bolted connection on specification, model and
control inspecting with torque spanner
fastening moment of bolt

Firmly installed and tightly


Installation of separating wallboard Observe
overlapped

201
7 See Table 4.8.1-7 for inspection and acceptance on installation of air-stopping wall.
Table 4.8.1-7 Installation of air-stopping wall
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of drawing


Main Checking against drawing;
Bolted connection on specification, model and
control inspecting with torque spanner
fastening moment of bolt

Main Inspecting with gradienter and


Reference line, elevation deviation Meet requirements of drawing
control theodolite

Installation of air-stopping wall Inspecting with gradienter and


Meet requirements of drawing
framework theodolite

Firmly installed and tightly


Installation of air-stopping wallboard Observe
overlapped

4.8.2 See Table 4.8.2 for inspection and acceptance on installation of air-cooling condenser
fan.
Table 4.8.2 Installation of air-cooling condenser fan
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Smooth, flawless and free of


Appearance inspection Observe
damage in appearance

Roundness or diameter of fan Main


mm Meet requirements of drawing Inspecting with steel ruler
drum control

Installation and fixation of


Meet requirements of drawing Checking against drawing
fan drum
Installation
Checking against drawing;
of fan Bolt type, extruded length Meet requirements of drawing
inspecting with steel ruler
drum
Main
Position deviation mm Meet requirements of drawing Inspecting with steel ruler
control

Main
Final bolt-up moment Meet requirements of drawing Inspecting with torque spanner
control

Flat, smooth, firm and no


Fan protecting wire net Observe
deficiency

Motor Appearance inspection No visual defect Observe


installation
Inspect correctness of installation
Motorgear case connecting Main and connection; meet the
Observe
device control requirements of gear case
instruction manual

Installation and fixation of


Meet requirements of drawing Observe
motorgear case

First oiling of gear case;


Main Meet the requirements of
inspecting oil type and liquid Observe
control manufacturer
level

202
Installation of hub plate and Main
Meet requirements of drawing Observe
fixed plate control

Appearance inspection No visual defect Observe

Fan blade installation and Main Meet the requirements of Observing and measuring with
()
blade angle adjustment control manufacturer angle measuring instrument
Blade
Space between blade and fan Meet the requirements of
installation mm Inspecting with steel ruler
drum manufacturer

Final bolt-up moment meets the


Fixing of gear case, hub plate Main
requirements of fan instruction Inspecting with torque spanner
and fan blade control
manual

4.8.3 See Table 4.8.3 for inspection and acceptance on installation of condensing tube bundle.
Table 4.8.3 Installation of condensing tube bundle and cleaning system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Free of flaw, sand hole, corrosion


Appearance inspection on Main Inspecting with magnifier by 5
pit, cross break, double skin and
tube bundle control times
rag
Tube
Main Inspecting with leveling
bundle Position deviation Meet requirements of drawing
control instrument and steel ruler
installation
The welding form shall meet the
Main
Welding requirements of technical
control
document and welding code

Straight and even in upside-down


Observe; inspecting with steel
Track rail; the upside-down rail space
ruler
Installation meets the requirements of drawing

of cleaning Meet the requirements of


Roadster Observe
system manufacturer

Meet the requirements of


Nozzle Observe
manufacturer, no blockage

4.8.4 See Table 4.8.4 for inspection and acceptance on tightness test of air-cooling system
Table 4.8.4 Tightness test of air-cooling system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of


Installation position of pressure gage
manufacturer

Meet the requirements of


Installation position of blanking plate
manufacturer

Fill in compressed air 30kPa;


Main The pressure drop in 24h is less
Tightness test kPa measuring relative pressure drop
control than or equal to 5
with precise pressure gage

4.8.5 See Table 4.8.5 for the implementation performance of subsection project compulsory
provisions for installation of air-cooling condenser system
Table 4.8.5 Inspection table on the implementation performance of subsection project compulsory

203
provisions for installation of air-cooling condenser system
________Unit Project number:
Unit project Assembly and installation of
Turbine generator auxiliary device installation Subsection project name
name air-cooling condenser

Project number Acceptance time Date

Implementation Related
SN Inspection item
performance information

Before filling water, it must thoroughly clean up internal rusty scale, weld
beading and foreign bodies. The internal anticorrosive coating shall be
1
painted according to design requirements or after the study of technical
section.

Before equipment installation, it must inspect the equipment as required. If


there is damage or quality defect, it shall timely inform organizations
concerned of joint inspection. As for defect in equipment manufacture, it
shall contact the manufacturer for treatment. If the installation quality fails
2 to meet requirements due to manufacturing quality, it shall be jointly
negotiated among construction organization, manufacturing unit, building
or using unit; there shall be records as well as confirmation and signature
for construction, equipment inspection and defect treatment after reaching
installation quality standard.

The quality acceptance of material shall be in compliance with the


following requirements:
The metallic material under supervision must meet the relevant national
standard and professional standard. The imported metallic material must
meet the requirements of relevant national technical standards specified in
contract.
The steel, steel tube and spate parts as well as auxiliaries under supervision
must be carried out with quality acceptance according to quality certificate
3 and quality guarantee. The quality certificate or quality guarantee shall be
indicated with steel type, chemical composition, mechanical property as
well as necessary metallographic inspection result and heat treatment
technique. As for those with insufficient data, it shall make up for
inspection. The method, range and quantity of supplemented inspection
shall meet the national standard or relevant professional standard. The
imported metallic material shall not meet the requirements of not only
relevant national technical standards specified in contract, but also
commodity inspection qualification document.

Installation organization shall refer to inspection record on manufacturing


quality (including nondestructive testing record) before installation of
structure and main pipes. When quality certificate information is
4 incomplete or quality is doubtful, installation organization shall question
manufacturing organization jointly with development organization and
require supplemented inspection or reinspection. Installation shall not be
carried out without inspection.

204
Conclusion

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.9 Installation of deaerator (water tank) equipment installation

4.9.1 See Table 4.9.1 for inspection and acceptance on installation of deaerator (water tank)
main body.
Table 4.9.1 Installation of deaerator (water tank) main body
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Free of crack, hole, oil stain and


Foundation surface cleaning Observe
foreign bodies

Inspecting by tapping with hand


Iron gasket installation Compact contact; no looseness
hammer

Contact surface of base, support and Smooth, clean and free of rag and
Observe
roller weld beading

Appearance inspection Straight, no bending


Support
Support contact Compact
roller Observe
Meeting the requirements of
inspection Position
expansion

No pit, scratch and mechanical


Equipment surface Observe
damage

Deviation of Central line mm 10 Measuring with steel tape


equipment
positioning Elevation mm 10 Measuring with level
dimension

Levelness deviation mm/m 2 Measuring with level

Clean and free of rust, weld


Internal inspection beading and foreign bodies; Observe
complete in internal auxiliaries

100 higher than water tank


Sewer pipe opening mm Measuring with steel tape
bottom

Appearance inspection on nozzle and Smooth eyelet; no processing


Observe
water spraying panel scrap and foreign bodies

Levelness deviation of water spraying


mm/m 2 Measuring with level ruler
panel

Uniform gap; smooth and clean


Spring nozzle inspection Observe
spring; block-free core

205
Clean, no foreign bodies and
Inspecting according to the
Filling installation smooth in surface; the height
drawing
meets relevant requirements

Groove The welding form shall meet the


Equipment
Gap requirements of technical
welding
Welded joint document and welding code

Main No leakage and no obvious According to the requirements of


Deaerator tightness test
control deformation on shell manufacturer

No omission in in-case work;


Main
Equipment sealing clean inside, tightly sealed in Observe
control
plug and manhole door

4.9.2 See Table 4.9.2 for inspection and acceptance on installation of deaerator auxiliaries.
Table 4.9.2 Installation of deaerator auxiliaries
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inspection on level gauge of magnetic Magnetic reverse turning bed


Observe
reverse turning bed indicates correctly; no jam in buoy

Tightness of plug cock of water level Inspecting by painting valve


No leakage
gauge spool

Three-way valve switch of water level


Correctly indicated Observe
gauge

Protective cover of water level gauge Smooth in edge; firmly fixed Observe

Sampling point distribution of


Meet requirements of drawing Check according to the drawing
sampling device

Cleaning Clean inside Observe

Safety Operating Flexible, reliable and no jam Turn the handle


gate
Inspecting by painting valve
Tightness inspection No leakage
spool or water pressure

4.9.3 See Table 4.9.3 for the implementation performance of subsection project compulsory
provisions for installation of deaerator (water tank) equipment
Table 4.9.3 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of deaerator (water tank) equipment
________Unit Project number:
Turbine generator auxiliary device Subsection project Installation of deaerator (water tank)
Unit project name
installation name equipment

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

Installation organization shall refer to inspection record on


manufacturing quality (including nondestructive testing record)
1
before installation of pressure vessel. When quality certificate
information is incomplete or quality is doubtful, installation

206
organization shall question manufacturing organization jointly
with development organization and require supplemented
inspection or reinspection. Installation shall not be carried out
without inspection.

Access opening must not be opened randomly on the pressure


vessel, pipe seat must not be welded, and repair must not be
2
carried out, as well as pipes must not be used as hanger and
support points for hoisting other heavy things.

When carrying out water pressure test on equipment, if it can


only observe condition of water pressure test by disassembling
3 certain parts and the permanent deformation may be caused on
equipment for this, it must carry out temporary strengthening
work.

Before filling water into tank, it must thoroughly clean up


internal rusty scale, weld beading and foreign bodies. The
internal anticorrosive coating shall be painted according to
4
design requirements or after the study of technical section. The
water supply tank shall not be sealed before confirmation and
signature for inspection.

As for butt welded junction of vessel drum, the distance


between its centre line and starting point of head bending shall
not be less than thickness of vessel wall plus 15mm and shall be
5 greater than or equal to 25mm. The distance between two
adjacent parallel welded joints shall be greater than three-fold
thickness of vessel wall and shall be greater than or equal to
100mm

When the partial gap of welded junction is two large, it shall


6
manage to repair it to given size; it must not add stuffing in gap.

Generally, the welded parts assembly shall ensure flush inner


wall (base); it there is staggered joint, the value of staggered
joint shall meet the following requirements:
a) The value for partial staggered joint of butt-joint single
7 welding shall not exceed 10% of wall thickness and shall be
less than or equal to 1mm.
b) The value for partial staggered joint of butt-joint double
welding shall not exceed 10% thickness of welded parts and
shall be less than or equal to 3mm.

As for hidden welded joints for inspection, it shall not continue


8 other procedures before passing the inspection

Acceptance result

207
Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.10 Installation of high- and low-pressure heater

Application scope: This part is applicable to installation of high- and low-voltage heater,
including heater inspection and heater installation (See Table 4.3.35 Installation of ordinary
heat exchanger).
4.10.1 See Table for inspection and acceptance of high- and low- pressure heater.
Table 4.10.1 Inspection on high- and low- pressure heater
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

No bruise, no defect in welded


joints, tightly sealed in pipe
Shell Observe
opening, complete in measuring
Appearance
point of instrumentation
inspection
Clean, no rust, correct diverging
Water chamber access, no short circuit in Observe
clapboard

No pit, rag, crack, nick and rust


Appearance Observe
Self-pressurized on surface

sealing Sealing surface Smooth, clean and no damage Observe


manhole door
Meet the requirements of
Gasket material Observe
manufacturer

1.25-fold operating pressure for


Main 10 minor confirmation and
Water pressure test No leakage
control signature book for inspection
and supervision

4.10.2 See Table 4.10.2 for inspection on the implementation performance of subsection
project compulsory provisions for inspection and installation of high pressure heater, low
pressure heater and gland heater as well as installation of drain flash tank in steam turbine
room and other heat exchanger.
Table 4.10.2 Inspection table on the implementation performance of subsection project compulsory
provisions for ( )
________Unit Project number:
Subsection project
Unit project name Turbine generator auxiliary device installation
name

Project number Acceptance time Date

SN Inspection item Implementation Related information

208
performance

Before filling water, it must clean up internal rusty scale, weld


1 beading and foreign bodies and shall not be sealed until
confirmation and signature for inspection.

Access opening must not be opened randomly on the pressure


vessel, pipe seat must not be welded, and repair must not be
2
carried out, as well as pipes must not be used as hanger and
support points for hoisting other heavy things.

When carrying out water pressure test on equipment, if it can only


observe condition of water pressure test by disassembling certain
3
parts and the permanent deformation may be caused on equipment
for this, it must carry out temporary strengthening work.

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.11 Installation of bypass system equipment

Application scope: It is applicable to installation of bypass system equipment, including


inspection and installation of high-voltage bypass system equipment, inspection and
installation of low-voltage bypass system equipment as well as installation of steam discharge
device for access to condenser.
4.11.1 See Table 4.11.1 for inspection and acceptance on installation of high-voltage bypass
system equipment.
Table 4.11.1 Installation of high-voltage bypass system equipment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

High-pressure Main
Internal cleaning Clean and impurity-free Observe
bypass valve control

Filter screen
Smooth Observe
eyelet

Desuperheating
Appearance Smooth Compressed air
water nozzle
inspection
Material of alloy Main
Meet requirements of drawing Spectrum inspection
steel parts control

Dimension of
Main
joint with Conform to the design Measuring with steel tape
control
pipeline

Internal
inspection Sealing surface Main Whole-circle linear contact, no Inspecting by painting
of valve seat and control discontinuity
209
valve spool

Flange sealing Main


Complete, no radial groove Observe
surface control

Deviation of Main
mm 10 Measuring with steel tape
central line control

Elevation
mm 10 Measuring with level
deviation
Installation
Levelness
deviation
mm/m 2 Measuring with level ruler
Verticality
deviation

a The internal inspection only refers to high voltage bypass valve where temporary valve spool need be replaced for boiler
washing pipe

4.11.2 See Table 4.11.2 for acceptance on inspection and installation of low-voltage bypass
system equipment.
Table 4.11.2 Inspection and installation of low-voltage bypass system equipment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Main
Internal cleaning Clean and impurity-free Observe
control

Filter screen eyelet Smooth Observe

Desuperheating
Appearance Smooth Compressed air
water nozzle
inspection
Material of alloy Main Meet requirements of
Spectrum inspection
Low-pressure steel parts control drawing

bypass valve Dimension of joint Main


Conform to the design Measuring with steel tape
with pipeline control

Deviation of central Main


mm 10 Measuring with steel tape
line control

Installation Elevation deviation mm 10 Measuring with level

Levelness deviation
mm/m 2 Measuring with level ruler
Verticality deviation

Deviation of central Main


mm 10 Measuring with steel tape
line control

Elevation deviation mm <10 Measuring with level


Grade 3 desuperheater
Levelness deviation mm/m 2 Measuring with level ruler

Dimension of joint Main


Conform to the design Measuring with steel tape
with pipeline control

4.11.3 See Table 4.11.3 for inspection and acceptance on installation of steam discharge
device for access to condenser
Table 4.11.3 Installation of steam discharge device accessing into condenser

210
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Main Correctly positioned, firmly welded, no


Steam baffle
control crack in welded joints
Observe
Spray water pipe and eyelet Smooth and impurity-free

Internal cleaning Clean and no rust scale

Welded joints connected with


No crack, pore and other defects Oil penetration test
condenser

4.11.4 See Table 4.11.4 for inspection on the implementation performance of subsection
project compulsory provisions for inspection and installation of bypass system equipment.
Table 4.11.4 Inspection table on the implementation performance of subsection project compulsory
provisions for inspection and installation of bypass system equipment
________Unit Project number:
Subsection project Inspection and installation of bypass
Unit project name Turbine generator auxiliary device installation
name system equipment

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

Before installing equipment, it must inspect equipment as required.


If there is damage or quality defect, it shall timely inform
organizations concerned of joint inspection. As for defect in
equipment manufacture, it shall contact the manufacturer for
treatment. If the installation quality fails to meet requirements due
1
to manufacturing quality, it shall be jointly negotiated among
construction organization, manufacturing unit, building or using
unit; there shall be records as well as confirmation and signature
for construction, equipment inspection and defect treatment after
reaching installation quality standard.

The important materials used in construction shall be provided


with quality certificate and material certificate. If the quality of
such materials are doubted during checking and inspection; they
2 shall be inspected and identified necessarily. All performances of
alloy steel, high-pressure-temperature welding material and
fire-resistant oil must meet design requirements and national
standards before application.

If valves is used as the closed circuit components (for isolation),


tightness inspection must be carried out before installation to
check the tightness of the joint surfaces of the valve seat and the
3
valve spool, valve cover and packing chamber. Tightness of valves
shall be carried out with a pressure 1.25 times of the name plate
pressure.

As for disintegration valve, it shall carry out the following


4
inspection: spectrum reinspection shall be carried out on internal

211
parts of alloy steel valve (It may make no marking on parts, but
shall record the inspection result)

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.12 Installation of steam feed pump unit

Application scope: It is applicable to installation of steam feed pump unit, including


foundation preparation, pedestal grinding and positioning, inspection and installation of
bearing (block) and oil catch, assembly, inspection and positioning of cylinder, rotor
positioning, centering adjustment of gland casing and oil catch bore, fixation of steam
cylinder, installation of clapboard and gland casing, adjustment of throughflow clearance
measurement, positioning of thrust disc, covering of driving steam turbine, covering of shaft
block and installation of gear-type rolling gear, adjustment and of driving steam turbine and
inspection and installation of protection system, installation of lubricating oil system for
driving steam turbine, test run of driving steam turbine, installation of steam feed pump,
centering of coupling for feed pump group as well as test run of steam feed pump. See Table
4.5.6-10 for oil system rinsing and See General-purpose Table 4.3.20 for secondary pouring.
4.12.1 See Table 4.12.1 for inspection and acceptance on foundation preparation as well as
preparation and installation of iron gasket and foundation bolt
Table 4.12.1 Foundation preparation as well as preparation and installation of iron gasket and foundation
bolt
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Free from reinforcement


exposion, crack, defects, and
Foundation appearance Observe
cleaning up impurities inside
foundation bolt hole

Deviation of vertical and horizontal


mm 10 Measuring with steel tape
central line

Elevation deviation mm 10 Measuring with level

Center deviation of bolt hole mm 10 Measuring with steel tape

Verticality deviation of bolt-hole wall mm/m 10 Measuring with plumb bob

Center deviation of embedded bolt mm 2 Measuring with steel tape

Treatment of concrete surface under Flat chipping, tight contact with


mm Observe
iron gasket iron gasket and without tilting

Inspecting according to the


Embedded ironworks Meet requirements of drawing
drawing

212
Preparation and installation of iron In accordance with those specified
gasket in Table 4.3.5~4.3.7

In accordance with those specified


Installation of foundation bolt
in Table 4.3.4 and Table 4.3.19

Contact area of adjustable iron gasket


70% Inspecting by painting
on spherical face

4.12.2 See Table 4.12.2 for inspection and acceptance on pedestal grinding and positioning
Table 4.12.2 Pedestal grinding and positioning
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Cast-iron pedestal contact with steam


75%, and uniform Inspecting by painting
cylinder and shaft block

Gap between lamellate pedestal Inspecting with feeler gauge


(subplate) and steam cylinder mm <0.05 after positioning of steam
arm-brace cylinder

Tightening force of sliding pin and


mm 0~0.02 Measuring with vernier caliper
pedestal pin slot

Distance between pedestal bottom Measuring with straight steel


mm 50~80
and foundation bearing area ruler

Levelness deviation of base plate for Meet the requirements of


mm/m Measuring with level ruler
fast-assembing unit manufacturer

Partial gap between base plate and


mm <0.05 Inspecting with feeler gauge
subplate

4.12.3 See Table 4.12.3 for inspection and acceptance on inspection and installation of
bearing (block)and oil catch.
Table 4.12.3 Inspection and installation of bearing (block) and oil catch
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with those specified


Shaft block inspection
in Table 4.3.14

Levelness Horizontal mm/m 0.2


deviation of Measuring with gradienter
shaft block Longitudinal mm/m Consistent with lift of axle neck

In accordance with those specified


Bearing bush inspection
in Table 4.3.15

Black bronze of tilting pad contact Meet the requirements of


Observing moulage
with axle neck manufacturer

Main
Gaps Roof Mm (0.1~0.15) /100 shaft diameter Measuring pressure fuse
control
between
Measuring oil-blocking side by
elliptical Main
Both sides Mm (0.15~0.2) /100 shaft diameter feeler gauge, with 15mm ~20mm
tiles control
inserted depth

213
Main
Gap between roof of tilting pad mm (0.12~0.2) /100 shaft diameter Measuring pressure fuse
control

Upper part mm 0.20~0.25


Gap between
post-oil-catch
Both sides mm 0.10~0.20 Measuring with feeler gauge
of elliptical
tile
Lower part mm 0.05~0.10

Meet the requirements of


Gap between oil seal of tilting pad nun Measuring with feeler gauge
manufacturer

Meet the requirements of


Gap between oil catch of thrust pad mm Measuring with feeler gauge
manufacturer

Measuring with pressure fuse,


Meet the requirements of
Tightening force of bearing bush mm outside micrometer and feeler
manufacturer
gauge

4.12.4 See Table 4.12.4 for assembly, inspection and positioning of steam cylinder.
Table 4.12.4 Assembly, inspection and positioning of steam cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Free of crack, slag inclusion and


Appearance of cylinder body Observe
weld beading

Horizontal staggered joint on vertical Main Measuring with depth gauge


mm <0.05
joint surface of steam cylinder control after assembly

Staggered joint on division plane of Measuring with depth gauge


mm 0.05
front case and steam cylinder after assembly

No casting sand, scrap iron and


Internal cleaning of steam chamber Observe
other attachment

Horizontal joint surface of steam


No rust and radial groove Observe
cylinder

Tightening 1/3 bolt and


Partial gap between horizontal joint Main
mm <0.05 inspecting with feeler gauge
surface of steam cylinder control
from inside and outside

Gap
Top Mm 1.0 Measuring with depth gauge
between
sliding pin
at bottom of Main
Both sides (total gap) mm 0.04~0.08 Measuring with vernier caliper
steam control
cylinder

Horizontal Measuring with combined


Horizontal mm/m 0.2
deviation of diagram level
steam Main Consistent with lift of front axle Measuring with combined
Longitudinal mm/m
cylinder control neck diagram level

214
Meet the requirements of Measuring with feeler gauge and
Lug gap Mm
manufacturer micrometer

Main Meet the requirements of


Material of alloy steel parts Spectrum inspection
control manufacturer

4.12.5 See Table 4.12.5 for inspection and acceptance on rotor positioning, centering
adjustment of gland casing and oil catch bore as well as fixation of steam cylinder.
Table 4.12.5 Rotor positioning, centering adjustment of gland casing and oil catch bore as well as fixation of
steam cylinder.
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with those specified


Rotor appearance
in Table 4.4.3

Main
Rotor levelness mm/m The lift of rear axle neck is zero Measuring with gradienter
control

Main
Center Right-left (a-b) mm 0.06~0.1
control
deviation of
Upper Measuring with inside
steam seal
Main micrometer
and oil catch ab mm 0.06~0.1
c control
bore
part 2
Tapping with hand hammer and
Reinspection on iron gasket mm No looseness; partial space<0.05
inspecting with feeler gauge

Preliminary fastening of foundation


Firm and without looseness Tapping with hand hammer
bolt

Reinspection on space between platen


and steam cylinder as well as shaft mm <0.05 Inspecting with feeler gauge
block

Horizontal space between steam Main


mm 0.04~0.08 Inspecting with feeler gauge
cylinder and platen bolt washer control

Horizontal space between bolt washer Main


mm 0.04~0.06 Inspecting with feeler gauge
of front bearing pedestal control

Space between bolt of front bearing


Main Meet the requirements of Measuring with straight steel
pedestal and before and after bolt mm
control manufacturer ruler
hole

Fixation of flexible-strut front bearing Tightening positioning pin and Tapping with hand hammer and
pedestal and platen bolting up listening to sound

4.12.6 See Table 4.12.6 for inspection and acceptance on installation of clapboard and gland
casing.
Table 4.12.6 Installation of clapboard and gland casing

Inspection method and


Inspection item Property Unit Quality criteria
measuring instrument

Inspection on clapboard steam seal Complete, no shortage and


Observe
block crimping; sharpen edge

215
Inspecting with bolt-up feeler
Horizontal surface space of clapboard mm <0.05
gauge

Total clearance between split seal key


Main Meet the requirements of
of clapboard and both sides of key mm Measuring with vernier caliper
control manufacturer, generally 0.05~0.08
groove

Assembling and space of gland In accordance with those specified


casing in Table 4.4.5-5

Center
Measuring with pulling steel
deviation Main Meet the requirements of
Right-left (a-b) mm wire, hanging earphone or laser
of control manufacturer, generally 0~0.08
alignment method
clapboard

Center
Measuring with pulling steel
deviation ab Main Meet the requirements of
c mm wire, hanging earphone or laser
of Upper part 2 control manufacturer, generally 0~0.05
alignment method
clapboard

Space of Meet the requirements of


c
suspension pin Main manufacturer, generally 0.20~0.30
mm Measuring pressure fuse
assembly (Figure control Meet the requirements of
g
4.12.6a) manufacturer, generally 1.50

Bearing contact area of down-hanger


75% Inspecting by painting
A [ Figure 4.12.6a)]

Axial clearance a Meet the requirements of


Steel diaphragm
of end face of manufacturer, generally 0.05~0.10
Main
lapboard (sleeve) mm Measuring with dial gauge
Cast-iron control Meet the requirements of
or holding ring
clapboard manufacturer, generally 0.10~0.20
[Figure 4.12.6b]

Contact area of clapboard radial


bottom-supporting pin [Figure 50% Inspecting by painting
4.12.6c)]

Space a of clapboard nailon Main Meet the requirements of


mm Measuring pressure fuse
clapboard support [Figure 4.12.6c)] control manufacturer, generally 0.30~0.50

Space of clapboard (sleeve) or both


sides of holding-ring positioning key Main Meet the requirements of
mm Measuring with inside/outer
(a1+a2) [Figure 4.12.6d), Figure control manufacturer, generally 0.03~0.05
micrometer for pressure fuse at
4.12.6e)]
top clearance and both sides of
Positioning key space c of clapboard
Meet the requirements of clearance
(sleeve) or holding ring [Figure mm
manufacturer, generally 2.00~2.50
4.12.6d), Figure 4.12.6e)]

216
a) Clearance in suspension pin assembly b) Axial clearance of clapboard (sleeve) or ring-holding end surface c) Clearance of clapboard nail on clapboard support

Interference

d) Clearance on both sides of clapboard (sleeve) or ring-holding positioning key e) Clearance of clapboard (sleeve) or ring-holding positioning key

Figure 4.12.6 Gap between clapboards


4.12.7 See Table 4.12.7 for inspection and acceptance on measurement and adjustment of
throughflow gap as well as positioning of thrust disc
Table 4.12.7 Measurement and adjustment of throughflow gap as well as positioning of thrust disc
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Main Meet the requirements of Measuring with feeler gauge or


Axial direction mm
Labyrinth control manufacturer wedged feeler gauge
clearance at shaft Meet the requirements of
Main Inspecting by sticking adhesive
end Radial direction mm manufacturer, generally 0.25~0.50
control tape
for one side

Main Meet the requirements of Measuring with feeler gauge or


Axial direction mm
Labyrinth control manufacturer wedged feeler gauge
clearance of Meet the requirements of
Main Inspecting by sticking adhesive
clapboard Radial direction mm manufacturer, generally 0.25~0.50
control tape
for one side

All-level axial and radial throughflow Main Meet the requirements of Measuring with feeler gauge or
mm
clearance control manufacturer wedged feeler gauge

Thrust disc approaches main


No change on throughflow
Thrust disc positioning thrust pad; reinspect axial
clearance
throughflow clearance

Main Meet the requirements of


Thrust gap mm Measuring with dial gauge
control manufacturer

Thickness deviation of thrust pad


mm 0.02 Measuring with vernier caliper
locating ring

217
Contact area of thrust segment and Main 75%, Taking on spot or uniform Inspecting by wholly painting
thrust disc control distribution after assembling thrust pad

4.12.8 See Table 4.12.84.12.8 for inspection and acceptance on covering of driving steam
turbine
Table 4.12.8 Covering of driving steam turbine
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Cleaning up steam cylinder and


No dust and foreign bodies Observe
steam chamber
Inspection before covering

Drainage hole of steam cylinder No blockage Access test

Cleaning up horizontal joint


No dust, rust and oil stain Observe
surface

Cleaning up spare parts inside


No dust, oil stain and rust Observe
cylinder

Trial erection of bolt and nut Screw in freely, without looseness Test by hands

Joint surface with


Paint black lead powder
steam cylinder
Installation Observe
Location of horizontal Basically flush with horizontal
of lower
surface surface of steam cylinder
clapboard
Installation of spare parts inside cylinder

Positioning pin at Fitting in loose and tight,


Feel clapboard by hands
bottom block-free

Reinspection on throughflow Main


Conform to installation record Inspecting suspended rotor
clearance control

Horizontal joint
No staggered joint Inspecting driven-in pin
surface on sides

Installation Bolts Fasten Inspecting with spanner


of upper
Painting joint surface
clapboard Paint black lead powder Observe
with steam cylinder

Complete, no fracture at bending


Anti-loosing washer Observe
position

Thickness of paint mm 0.5 right-left, and uniform Observe

Main Able to fall freely, no jam and top


Covering Observe
control resistance
Assembling

Positioning pin Complete, hit hard Hammering and listening

Paint black lead powder, screw


Installation of steam cylinder bolt Observe
studding to bottom hole

Main Meet the requirements of


Bolt-up moment Measuring with torque spanner
control manufacturer

218
In accordance with those
Secondary grouting specified in Table 4.3.11 and
4.3.12

4.12.9 See Table 4.12.9 for inspection and acceptance on covering of shaft block and
installation of rolling gear.
Table 4.12.9 Covering of shaft block and installation of rolling gear
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Cleaning up bearing pedestal Clean and impurity-free Observe


Covering
Temperature-measuring Firmly installed, with outgoing Observing and measuring with
bearing
equipment for bearing bush line in good condition multimeter
pedestal
Tightening force of bearing Main Meet the requirements of
mm Measuring pressure fuse
bush control manufacturer

Contact surface of In accordance with those


gear specified in Table 4.3.38

Main
Clearance Top mm 1.5~2
control
Wobble with Measuring pressure fuse
Both Main
wheel gearwheel mm 0.8~1.2
sides control
type
Distance from
gearwheel after
Installation Adequate distance, firmly fixed Observe
disconnection of
of
wobble wheel
gear-type
Contact surface of In accordance with those
rolling gear
Sliding gear specified in Table 4.3.38
wheel Limit position of
Main Positioning pin is able to embed
type sliding wheel Observe
control into notch of torsion panel
withdrawal

Installation of gearwheel
Not contact gearwheel Inspecting by rolling rotor
enclosure

Injector nozzle of lubricating


Align with lubricant housings Observe
oil

Installation Inspection on impeller and Clean on surface; firmly fixed


Observe
of blade between blade and impeller
oil-impeller
Inspection on nozzle group Clean inside; smooth passage Observe
rolling gear

Main Meet the requirements of


Blade tip clearance mm Measuring with feeler gauge
control building factory; uniform around

Considering rotor expansion,


Main
Axial clearance mm meet the requirements of Measuring with feeler gauge
control
manufacturer

219
Main Observe, compressed air
Pressure oil pipe Clean inside; smooth pipeline
control inspection

Lever, connecting rod and pin Flexible operation, adequate


Trial operation
roll travel
Installation
of manual Lever support Firmly fixed Trial operation
rolling gear
Flexible operation, safe and
Ratchet wheel Trial operation
reliable elasticity

4.12.10 See Table 4.12.10 for inspection and acceptance on adjustment of driving steam
turbine as well as inspection and installation of protection system
Table 4.12.10 Adjustment of driving steam turbine as well as inspection and installation of protection system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In good condition; free of


Main
Appearance inspection crack, rust, damage and Observe
control
deformation

Meet the requirements of


Pipe joint Checking against drawing
manufacturer

Piston action Flexible, block-free Operation inspection

Greater than travel of valve


Oil servomotor

disc, with surplus on both Pushing, pulling and


Maximum stroke of piston
ends; meet the requirements of measuring
manufacturer

Correct, firm, with locking


Main mechanism at connecting part,
Connection of oil servomotor Observe
control meet the requirements of
manufacturer

Correct, firm; meet the


Displacement transmitter Checking against drawing
requirements of manufacturer

Indicator parts for piston location and local


Conform to both indications Check and verify
travel

No deflection; flexible and no


Connecting rod assembly Observe, operate
jam at joint

Transmission Connection position of


Correct, firm and lock Observe
gear of connecting rod
connecting Main Meet the requirements of Pushing, pulling and
Space between piston and bottom mm
rod control manufacturer measuring

Compression quantity of Meet the requirements of Pushing, pulling and


mm
dish-type gasket manufacturer measuring

Free of crack, rust, damage


support
Spring

Spring appearance and deformation; flat and Observe


smooth on end face

220
Main Correct, firm; meet the
Spring support assembly Checking against drawing
control requirements of manufacturer

The assembly is firmly fixed;


the position and hole diameter
Throttle pore plug Checking against drawing
meet the requirements of
manufacturer

Clean, in good condition; the


Filter cartridge specification meets the Checking against drawing
requirements of manufacturer

Correctly positioned; sealed


Assembly Observe
Electro-hydraulic firmly; no oil leakage
converter Main
Action Flexible and no jam Trial operation
control

Assembly Firmly sealed; no oil leakage Observe


Other parts

Slide valve Main Meet the requirements of Measuring with vernier


mm
travel control manufacturer caliper
Unloading valve

Slide valve Main


Flexible and no jam Trial operation
action control

Manual screw
rod for No jam; the travel meets the Trial operation; measuring
pressure requirements of manufacturer with vernier caliper
regulation

Assembly of linear differential Correct and firm; meet the


Checking against drawing
action transmitter requirements of manufacturer

Inspection on emergency Main In accordance with those


governor control specified in Table 4.5.3-1

In accordance with those


Inspection on interrupted slide Main
specified in Table 4.5.3-2 and
Inspection valve control
Table 4.5.3-3
and
Main Meet the requirements of
installation Space between fly ball and lever mm Measuring with feeler gauge
control manufacturer
of security
Slide valve Main
parts and mm
Electromagnetic clearance control Meet the requirements of Measuring with vernier
sets
intercepter valve Oil port Main manufacturer caliper and depth gauge
mm
opening control

Fire-resistant In accordance with those


Installation of adjustable oil oil specified in Table 4.5.5-2
pipe In accordance with those
Lubricating oil
specified in Table 4.5.6-9

In accordance with those


Oil flushing of fire-resistant oil system
specified in Table 4.5.5-3

221
Main Observing pressure drop after
Tightness of accumulator No leakage
control filling nitrogen

4.12.11 See Table 4.12.11 for inspection and acceptance on installation of lubricating oil
system for driving steam turbine.
Table 4.12.11 Installation of lubricating oil system for driving steam turbine
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with those


Inspection and installation of oil cooler
specified in Table 4.5.6-2

No casting sand, air hole, crack


Cleaning up enclosure
Inspection and weld beading
and Flat, smooth, no rust and radial
Joint surface of flange Observe
installation groove
of oil filter
Appearance of filter screen No damage

Eyelet of guard plate No rag and blockage


Inspection
and Valve rod of switching
Flexible rotation Test by hands
installation valve
of oil filter Valve spool of switching
Uniform in continuous contact Inspecting by painting
valve

Horizontal motor-driven oil In accordance with those


pump specified in Table 4.5.6-5
Inspection
Vertical motor-driven oil In accordance with those
and
pump specified in Table 4.5.64
installation
Clearance between Main Meet the requirements of
of oil mm Measuring with feeler gauge
Screw pump

screw rod and shell control manufacturer


pump
Pressure regulating Main Clean and impurity-free; oil line
Observe
valve control conforms to the drawing

Inspection Main Inspecting after watering for 24


Watering test on oil tank No leakage
and control h
installation Main No welding slag, foreign bodies
Cleaning up oil tank Observe
of oil tank control and dust

Inspection on filter screen No crack Observe

No leakage in pontoon; balance in


Installation of oil level
surveyor's pole; correct in Observe
gauge
indication

Diameter of nozzle Main Meet the requirements of Check according to the drawing,
mm
Installation of oil

throat control manufacturer Measuring with vernier and


ejector

Diameter of depth gauge

diverging pipe
throat

222
Distance between
nozzle exit and
diverging pipe
throat

Location of suction Measuring with straight steel


Below lowest oil level of oil tank
inlet ruler

Suction strainer Clean, in good condition Observe

Bolt installation Firmly fixed and sealed Observe

Elevation deviation of oil


mm 10 Measuring with level
tank

Deviation of vertical and


mm 10 Measuring with steel tape
horizontal central line

In accordance with those


Installation of lubricating oil pipe
specified in Table 4.5.6-9

4.12.12 See Table 4.12.12 for inspection and acceptance on test run of driving steam turbine
Table 4.12.12 Test run of driving steam turbine
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Main
Governor oil pressure MPa
control Meet the requirements of
Online monitoring
Main manufacturer
Lubricating oil pressure MPa
control

Main
Fire-resistant oil temperature 505 Measuring thermometer
control

Main
Lubricating oil temperature 405 Measuring thermometer
control
Inspection before trial operation

Travel of starting valve


Main Meet the requirements of
corresponds to travel of oil Observe
control manufacturer
servomotor

Travel of electro hydraulic


Main
converter corresponds to Observe
control
travel of oil servomotor
Meet the requirements of
Travel of wholly electricity
manufacturer
regulation and control Main
Observe
corresponds to travel of oil control
servomotor

Nitrogen-filling pressure of Main Meet the requirements of


MPa Measuring pressure gauge
accumulator control manufacturer

Main
Trip and latching test Normal operation Test by hands
control

223
Actuation test of main
Normal Manually operate, observe
throttle valve

Test on exhaust-steam
Normal switching Observe
butterfly valve switch

Manual 0 Flexible, no friction sound


Rolling Listening to and monitoring the
gear Balance operation, no strike gauge needle
Motor-driven
note

Condenser vacuum kPa 40 Measuring with vacuum gauge

Main steam pressure MPa 0.40~0.60 Measuring pressure gauge

Feeling discharging door with


Water discharging Smooth hands; the pipe is hot to the
touch

Temperature before main


300 Measuring thermometer
throttle valve

Normal temperature; no steam


Steam supply by steam seal away and air suction at steam Observe, feel by hands
sealing point

Capable of automatic stop and


Electrical rolling gear Observe
drop out

Main
Scavenge oil temperature 65 Measuring with thermometer
control

Main
Bearing bush temperature 90 Online monitoring
control

Main Listening to and monitoring the


Operation condition No friction; abnormal vibration
Inspection control gauge needle
after Main Measuring bearing with
Rated revolution vibration mm 0.04
rolling control vibration gauge

Meet the requirements of


Static characteristic test
manufacturer

Main
Emergency trip speed Rated speed of 1.1~1.12 times Online monitoring
control

Listening to and monitoring the


Shutdown and coasting Main No friction; no sudden running
gauge needle, timing by
operation control down
stopwatch

4.12.13 See Table 4.12.13 for inspection and acceptance on installation of steam feed pump.
Table 4.12.13 Installation of steam feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Feed Location dimension of Main Accurate measurement and clear


mm Measuring with depth gauge
pump spindle nose and locknut control record

224
inspection Conform to the installation
Parts number Observe
sequence

Mark Clear steel seal Observe

In accordance with those


Shaft seal inspection
specified in Table 4.3.24

In accordance with those


Sliding bearing
specified in Table 4.3.22

Black bronze of thrust Main No bodiless, crack, air hole and Inspecting with coal-soaked or
segment control slag inclusion oil penetrating fluid

Thickness deviation of Measuring with outside


mm 0.02
Bearing inspection

main thrust pad micrometer

Thickness deviation of Measuring with outside


mm 0.02
auxiliary thrust segment micrometer

Radial gap of thrust disc


mm 0.35~0.45 Measuring with feeler gauge
and oil-blocking ring

Thickness difference of Measuring dial gauge; reading


mm 0.02
thrust-pad fixed ring maximum opposite difference

Contact area of thrust Main


75% Inspecting by painting
segment control

In accordance with those


Iron gasket installation
specified in Table 4.3.19

Clearance between lug and Main Inspecting with feeler gauge(not


mm <0.05
pedestal platen control tightening bolt)
Feed
pump
installation Transverse levelness mm/m <0.20 Measuring with gradienter

appearance No rag, rusted pit, rust stain Observe


Guide key and
key groove Total Main
mm 0.05~0.08 Measuring with vernier caliper
clearance control

4.12.14 See Table 4.12.14 for inspection and acceptance on coupling centering of feed
pump group
Table 4.12.14 Coupling centering of feed pump group
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Joint surface of No radial groove and other


Gear coupling
end shield seal damage
Appearance
Tooth No damage and deformation Observe
inspection

Gaskets In good condition

225
Compensation
Main Meet the requirements of
value of reserve
control manufacturer
Coupling temperature
Measuring dial gauge; reading
centre Radial Main
mm 0.06 maximum opposite difference
alignment deviation control

End face Main


mm 0.04
deviation control

Movement value of coupling Main Measuring with straight steel


mm 5~10
toothed sleeve control ruler

Distance between coupling Meet the requirements of


mm Measuring with vernier caliper
end face manufacturer

Location and direction of


Correct, firmly installed Observe
lubricating oil nozzle

Compensation
Main Meet the requirements of
value of reserve
control manufacturer
Coupling temperature
Measuring dial gauge; reading
centre Radial Main
Lamination-type mm 0.06 maximum opposite difference
alignment deviation control
coupling
End surface Main
mm 0.04
deviation control

Distance between coupling Meet the requirements of


mm Measuring with vernier caliper
end face manufacturer

4.12.15 See Table 4.12.15 for inspection and acceptance on test run of steam feed pump
Table 4.12.15 Test run of steam feed pump
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument

Measuring with pressure gage


Main steam parameters Reach the rated value
and thermometer

In accordance with those


Inspection before trial operation
specified in Table 4.3.26

Operation condition of steam feed Listening to and monitoring the


No friction, abnormal vibration
pump unit gauge needle

Rotation speed, outlet pressure and Main Meet the requirements of


Online monitoring
center tap pressure control manufacturer

Main
Bearing bush temperature 90 Measuring with thermometer
control

Main
Bearing annealing temperature 65 Measuring with thermometer
control

Main
Bear vibration mm 0.04 Measuring with vibration gauge
control
Vibration
Main Meet the requirements of
Shaft vibration Online monitoring
control manufacturer

226
Main
Balance pipe temperature No sudden heating phenomenon Feel by hands
control

Pressure difference between for pump Main


MPa <0.05 Observing pressure gage
outlet and feed pump inlet control

Listening to and monitoring the


Main No friction; no sudden running
Operation of pump off and coasting gauge needle; timing by
control down
stopwatch

4.12.16 See Table 4.12.16 for inspection on the implementation performance of subsection
project compulsory provisions for installation of steam feed pump unit.
Table 4.12.16 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of steam feed pump unit
_________ Unit Project number:
Installation of turbine generator Subsection project
Unit project name Installation of steam feed pump unit
auxiliaries name

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

All pipes shall be constructed according to design drawing. If


it need modify design or adopt substitute material, it must
1
apply to the design unit and handle it according to relevant
system.

If valves is used as the closed circuit components (for


isolation), tightness inspection must be carried out before
installation to check the tightness of the joint surfaces of the
2
valve seat and the valve spool, valve cover and packing
chamber. Tightness of valves shall be carried out with a
pressure 1.25 times of the name plate pressure.

It shall cut holes on the pipes according to design drawing


before installing pipes. After cutting holes, it must clean up the
3
inside and there shall be no drill cuttings or other foreign
bodies.

Before equipment installation, it must inspect the equipment as


required. If there is damage or quality defect, it shall timely
inform organizations concerned of joint inspection. As for
defect in equipment manufacture, it shall contact the
manufacturer for treatment. If the installation quality fails to
4 meet requirements due to manufacturing quality, it shall be
jointly negotiated among construction organization,
manufacturing unit, building or using unit; there shall be
records as well as confirmation and signature for construction,
equipment inspection and defect treatment after reaching
installation quality standard.

227
The important materials used in construction shall be provided
with quality certificate and material certificate. If the quality of
such materials are doubted during checking and inspection;
they shall be inspected and identified necessarily. All
5
performances of alloy steel, high-pressure and
high-temperature welding material, lubricating-oil (grease) and
fire-resistant oil must meet design requirements and national
standards before application.

Before installing steam cylinder, it shall carry out the


following inspection on relevant manufacturing quality of
equipment drawing and shall meet the requirements; if
necessary, it shall make records and shall make research and
treatment when failing to meet the requirements.
In appearance inspection of steam cylinder, it shall be free of
6
crack, slag inclusion, double skin, weld beading, pore, casting
sand and damage. All joint surface, sliding bearing area,
flange, bore and processing surface shall be smooth, clean and
no rust and dirt. The anti-corrosive coating shall be entirely
cleaned out; the inside of steam chamber shall be cleaned up
thoroughly and without any attachment.

It shall inspect bolt and nut of steam cylinder according to the


following requirements:
The screw thread in studding hole of bolt, nut and steam
cylinder shall be smooth and without rag; the matching
between bolt and nut should not be too loose or too tight. it
shall be able to freely screw nut to the end by hands;
otherwise, it shall carry out research and treatment. There shall
be steel impression mark on bolt and nut of high pressure
cylinder; they shall be not exchanged randomly.
The screw thread of studding bolt for steam cylinder shall be
entirely screwed into flange of steam cylinder; the screw
thread shall be lower than the surface of flange; the verticality
7
between studding bolt and flange surface shall meet the
requirements of manufacturer and shall be less than or equal to
0.50 in general; otherwise, it shall carry out research and
treatment.
When the nut of bolt is tightened to the installation position in
trial, the screw thread of bolt shall be buckled where 2~3
buckles of nut are exposed. When the shield nut is cooled and
tightened to the installation position, it shall ensure around
2mm clearance between top shield and top bolt after properly
fastening. The installation of tapered bolt for introduced unit
shall meet the requirements of manufacturer.
The damaged screw thread shall be repaired and scraped;

228
finally, it must use triangular oil stone to polish the repaired
and scraped area. If the screw thread inside the studding hole
need be repaired, it shall prepare special screw tap.
After inspecting and repairing screw thread, it shall use powder
coating with fine granularity and high temperature resistance
for inunction forcibly, or paint with lubricant required by the
manufacturer; it shall remove surplus paint and pack up bolt to
avoid dust and clash.

When the clearance of sliding pin is unqualified, it shall male


adjustment. As for oversized clearance, it shall allow repair
welding or ion spraying on the whole contact surface; but its
8
hardness shall be greater than or equal to that of virgin metal.
It shall not narrow clearance of narrow by restraining and
squeezing method.

The dimension of oil bag for oil hole on apical axis of lower
bearing shell shall meet the requirements of drawing.
Generally, its depth shall be between 0.20~ 0.40mm; the area
of oil bag shall be 1.5%~2.5% (larger value for larger diameter
9
of axle) of projected area of axle neck; the axle neck shall be
tightly close to around oil bag. The oil-pipe head of apical axis
must be firmly buried under black bronze and ensure to be
clean and smooth.

Before assembling steam turbine, it shall complete the


following work; it shall meet the requirements and shall have
specified installation records or confirmation and signature
book:
(1) The iron gasket is completely installed and the foundation
bolt firmly fastened;
(2) Measure the final clearance between vertical and horizontal
sliding pin of platen, vertical pin of steam cylinder and
horizontal pin of lug;
(3) Measure the clearance on horizontal joint surface of steam
cylinder;
10
(4) Horizontal lift of steam cylinder and axle neck lift of
turbine rotor; (5) Determine the central position of turbine
rotor at steam seal or oil catch bore;
(6) Clapboard centering;
(7) Measure the clearance of steam seal and throughflow
part;
(8) Adjust and measure clearance of thrust bearing;
(9) Spectrum reinspection of demountable parts inside steam
cylinder;
(10) Eliminate defects of spare parts inside steam cylinder;
(11) Thoroughly clean up the inside of steam cylinder, pipe

229
segment and steam chamber; seal pipe orfice as well as socket
and plug of instrumentation

The installation of oil-spray test device for emergency


governor shall be in accordance with the following
requirements:
(1) The spray bar shall be clean and smooth; the oil-taking
room of emergency governor shall be aligned and it shall make
close inspection within the range of maximum expansion
difference of rotor; its relative position shall be able to meet
the test requirement. The clearance between nozzle and
oil-taking room shall meet the requirements.
(2) The test tie bar shall be used to control the tripping lever
and oil-spray slide valve system. After installing and
positioning emergency governor, emergency trip throttle,
tripping lever and test tie bar, it shall try operation and meet
the following requirements:
1) The test tie bar shall be able to accurately control
11
disconnection or in-put of emergency trip throttle
corresponding to fly ball as well as oil throughout or oil cutoff
corresponding to oil-spray slide valve and indicate them
correctly;
2) The control pin shall be able to fix up location of test tie bar
reliably.
(3) As for the system of directly applying emergency trip test
throttle to oil-filling test, it shall be subject to trial operation
and meet the following requirements:
1) The indication on rotation direction of test slide valve and
the oil line switching shall be in accordance with the test
sequence of emergency governor;
2) When no oil-filling test is carried out, the indication pin
shall be able to prevent rotation or pulling of test slide valve
reliably.

The installation of emergency trip indicator shall be in


accordance with the following requirements:
(1) The clearance between contact terminal of mechanical
lever-type indicator and transmitter as well as emergency
governor of electricity indication shall meet the requirements
12
of drawing;
(2) The piston and spring indicator shall be jacked up with
safety oil; there shall be flexible operation and no jam on
piston and indicator pole. The safety oil pipe shall be tight,
without leakage, clean and smooth.

230
There shall be protective cover for manual emergency trip
13 device; the positioning billiards shall be able to correctly
position slide valve.

The slide valve of magnetic-power disconnection throttle and


electric overspeed protective device shall be flexible in
14 operation and without looseness; the air port on the slide valve
shall be smooth; the iron core and slide valve shall be firmly
connected.

After installing protection device of steam turbine, it shall


15 submit records on clearance between emergency governor
tripping lever and fly ball or eccentric strap.

The oil exit pipe for oil tank accident shall be connected to the
accident oil drainage well specified in design. Before unit trial
operation, it shall be formally installed and confirmed to be
smooth.
The inspection and installation of oil piping valve shall be in
accordance with the following requirements:
Generally, two gate valves shall be set up for accident oil
discharge valve; the gate valve close to oil tank shall be made
16 of steel. The operation hand wheel of accident oil discharge
valve shall be set up at over 5m away from oil tank and there
shall be more than two passages. The hand wheel shall be set
up with protecting glass.
There shall be clear marking on switch direction of valve;
rising stem valve shall be used instead of reverse valve. The
valve stem of pipe shall be laid flat or downward to prevent
valve disc from falling off and cutting off oil line during
operation.

Drilling hole, gas cutting and welding shall not be carried out
17 on the oil pipe after it is cleaned up and sealed, otherwise,
cleaning, inspection and sealing must be carried out again.

There must be quality certificate for shaft, impeller and blade


of steam turbine provided by the manufacturer; before
installation, it shall refers to relevant technical information
18 provided by the manufacturer. If any inadequate information or
quality or quality problem is discovered, the manufacturer
shall be required to supplement inspection or take
corresponding treatment measures.

231
Before installing heavy castings, such as steam cylinder, steam
chamber and main throttle valve, it shall check exfactory
certification and quality guarantee and carry out appearance
inspection; there shall be no crack, slag inclusion, double skin,
19
weld beading, casting sand and damage. When there is crack,
its length, depth and distribution condition shall be found out
and treatment measures shall be carried out by the
manufacturer and other organizations concerned.

Except cold-drawing welded junction specified in design, the


forced contra aperture shall be prohibited for rest welded
20
junction; thermal expansion technique shall not be used for
contra aperture

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.13 Installation of electrically driven feed pump group

Application scope: installation of electrically driven feed pump group, including inspection of
electrically driven feed pump and motor, installation of electrically-driven feed pump and
electrically driven feed pump oil system as well as trial operation of electrically driven feed
pump. See Table 4.12.14 for coupling centre alignment; see Table 4.5.6-10 for oil system
rinsing; see General-purpose Table 4.3.20 for secondary pouring.
4.13.1 See Table 4.13.1 for inspection and acceptance of electrically driven feed pump
Table 4.13.1 Inspection on electrically driven feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Space between pump wheels Meet the requirements of Measuring with inside
Dominant mm
at inlet and outlet segment manufacturer micrometer at rod-through bolt

Removing sealing device and


Measuring source data

Thrust gap Dominant mm 0.25~0.45 measuring main oil pump with


dial gauge

Removing thrust pad;


Meet the requirements of
Revolving value of operation Dominant mm measuring with dial gauge for
manufacturer
0 and 180

Meet the requirements of Disassembling balance disk;


Total revolving value Dominant mm
manufacturer measuring with dial gauge

232
Meet the requirements of Measuring with dial gauge for
Shaft lifting value Dominant mm
manufacturer upper tile and upside-down tile

Location dimension of Meet the requirements of


Dominant mm Measuring with depth gauge
spindle nose and locknut manufacturer

Conform to the installation


Parts number
sequence
Observing

Marking Clear steel seal

In accordance with those specified


Shaft seal inspection
in Table 4.3.24

In accordance with those specified


Sliding bearing
in Table 4.3.22

Black bronze of thrust No bodiless, crack, pore and slag Inspecting with coal-soaked or
Dominant
segment inclusion oil penetrating fluid

Thickness deviation of main Measuring with outside


mm 0.02
Bearing inspection

thrust pad micrometer

Thickness deviation of Measuring with outside


mm 0.02
auxiliary thrust segment micrometer

Radial gap of thrust disc and


mm 0.35~0.45 Measuring with feeler gauge
oil-blocking ring

Thickness difference of Measuring with outside


mm 0.02
thrust-pad fixed ring micrometer at any two points

Contact area of thrust


Dominant 75% Inspecting by painting
segment

4.13.2 See Table 4.13.2 for inspection and acceptance of motor.


Table 4.13.2 Motor inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Measuring with outside


Ellipticity Dominant mm 0.02
Shaft micrometer
neck Non-cylindrical Measuring with outside
Dominant mm 0.02
degree micrometer
Motor
In accordance with those
inspection Bearing pedestal and
specified in Table 4.3.21 and
bearing
Table 4.3.22

Adjustable gasket for stator 2~3 floors, layout in echelon


Observing
and bearing pedestal form

Inspection
Internal pipe of air cooler Smooth and clean Compressed air purging
and
installation Inspecting after 5 minwater
of air Water side tightness Dominant No leakage pressure test with 1.25 times
cooler working pressure

233
Clean and impurity-free, tight
Air chamber and air duct Observing
joint

Deviation of central line mm 10 Measuring with steel tape

4.13.3 See Table 4.13.3 for inspection and acceptance on installation of electrically driven
feed pump.
Table 4.13.3 Installation of electrically driven feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with those


Iron gasket installation
specified in Table 4.3.19
Insta
Clearance between lug and Inspecting with feeler gauge
llati Dominant mm <0.05
pedestal platen (Not tightening bolt)
on
of Transverse levelness mm/m <0.20 Measuring with gradienter
feed
Guide
pum Appearance No rag, rusted pit, rust stain Observing
key and
p
key
Total clearance Dominant mm 0.05~0.08 Measuring with vernier caliper
groove

Appearance inspection; in good


Appearance Observing
condition; no damage
Installation of Deviation of central
mm 10 Measuring with steel tape
fluid coupling line
or speed-up
Elevation deviation mm 10 Measuring with level:
gear case

Levelness deviation mm/m <0.04 Measuring with gradienter

Transverse levelness deviation


mm/m 0.2 Measuring with gradienter
of platen

Partial clearance between


mm <0.05 Inspecting with feeler gauge
Motor installation

bearing pedestal and platen

Pedest Meet the requirements of


Material dimension Observing
al manufacturer

bearin Meet the requirements of


Material quantity Observing
g manufacturer
insulati Measuring with 1000 V
Insulation resistance M 0.5
on insulation resistance meter
Auxiliary piping installation

Cooling water pipe Reasonable layout of pipeline Observing


and valve, correct direction and

Pump suction pipe smooth flow Observing

Installation of sealing water Reasonable layout of pipeline, Observing


pipe filter screen and valve, correct

234
connection, no blockage,
reasonable and firm support

Transparent water without


Sealing water pipeline rinsing Observing
impurity

Lined neatly, firmly fixed and


Pressure gage pipe Observing
tightly connected

Balance pipe With expansion curve Observing

Correct measuring range and


Thermometer Observing
tight joint

Correct measuring range and


Pressure gage Observing
tight joint

Lead wire of temperature No disconnection and no oil Measuring with multimeter


measuring equipment leakage at joint and observing

4.13.4 See Table 4.13.4 for inspection and acceptance on installation of electrically driven
feed pump oil system.
Table 4.13.4 Installation of electrically driven feed pump oil system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inspection and installation of oil In accordance with those specified


cooler in Table 4.5.6-2

In accordance with those specified


Inspection and installation of oil tank
in Table 4.5.6-1

Inspection and installation of oil In accordance with those specified


pipeline in Table 4.5.6-9

Inspection and installation of Meet the requirements of


auxiliary oil pump manufacturer

In accordance with those specified


Oil filter installation
in Table 4.5.6-3

Tightness test on oil filter No leakage Oil access test

4.13.5 See Table 4.13.5 for inspection and acceptance on trial operation of electrically
driven feed pump.
Table 4.13.5 Trial operation of electrically driven feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Calibration on the operating value of Meet requirements of Check records on electric and
pressure and temperature drawing thermal test

No-load trial Meet the requirement of


Motor insulating value Check records on electrical test
operation of DL/T 5161.1~5161.17
motor Bearing pedestal insulating Measuring with 1000 V
M 0.5
value insulation resistance meter

235
Feeling by hands and listening to
Rolling rotor No friction and jam inside
the sound

Start-up and no-load Meet the requirements of Check records on electric


current manufacturer profession

Rotation direction Correct Observing

Scavenge oil temperature Dominant <65


Measuring with thermometer

No-load trial Bearing bush temperature Dominant <90


operation of
motor Bear vibration Dominant mm 0.05 Measuring with vibration gauge

Motor outlet Meet the requirements of


Dominant Online monitoring
air-temperature manufacturer

Meet the requirements of


Stator core temperature Dominant Online monitoring
manufacturer

In accordance with those


Trial operation of booster pump
specified in Table 4.3.26

Cam-turn-angle
No-load trial corresponds to spoon tube Draw static characteristic curve
operation of Static test Dominant travel and meets the and compare with curve provided
fluid coupling requirements of by the manufacturer
manufacturer

Meet the requirements of


Pressure MPa
Cooling manufacturer
water Meet the requirements of
Flow m3/h
manufacturer

Meet the requirements of


Lubricating oil pressure MPa
manufacturer

Meet the requirements of


Working oil pressure MPa
manufacturer

Meet the requirements of Online monitoring

Lubricating oil temperature manufacturer, generally


455

Lubrication scavenge oil


Dominant 65
temperature

Working oil temperature 55~95

Working scavenge oil


Dominant 75~105
temperature

Gear and coupling parts Meet the requirement of oil


Observing
lubrication spray quantity

Flexible, accurate and


Regulating mechanism Observing
reliable

236
n3000 Dominant mm 0.05
Bearing
Measuring with vibration gauge
vibration
n>3000 Dominant mm 0.04

Relation curve between


Meet the requirements of
spoon tube travel and
manufacturer
rotation speed

Meet requirements of
Minimum flow device
drawing

Higher than water tank


Deaerator water level Observing water level gauge
center

Rolling rotor No jam Feeling by hands

Start-up and operation No abnormal sound and


Monitoring with listening needle
condition abnormal vibration

Meet the requirements of


Lubricating oil pressure MPa
manufacturer
Cooling trial
operation of Meet the requirements of
Working oil pressure MPa
electrically manufacturer

driven feed Scavenge oil temperature Dominant <65


pump Online monitoring
Working scavenge oil
Dominant 75~105
temperature

Lubricating oil temperature 455

Working oil temperature 55~95

n3000 Dominant mm 0.05 Measuring vertical, horizontal


Bearing
and axial vibration with vibration
vibration
n>3000 Dominant mm 0.04 gauge

Cooling trial Meet the requirement of


Motor operation
operation of non-load
electrically Pressure difference between
driven feed forepump outlet and feed Dominant MPa <0.05
pump pump inlet

Sealing water pressure of 0.15~0.20 higher than Measuring pressure gauge


Dominant MPa
feed pump pump inlet pressure

Equilibrium water chamber Basically the same as pump


Dominant MPa
pressure inlet pressure

Balance pipe temperature Dominant No sudden temperature rise Feeling by hands

Fluid coupling slippage Meet the requirements of


under rated conditions manufacturer

237
Speed adjustable range of Meet the requirements of
fluid coupling manufacturer

Relation between rotation


Meet the requirements of
speed, outlet pressure and Dominant
manufacturer
tapping pressure

No friction sound in
Coasting operation of pump coasting operation, no Timing by stopwatch and
Dominant
unit sudden pump-off monitoring with listening needle
phenomenon

4.13.6 See Table 4.13.6 for inspection on the implementation performance of subsection
project compulsory provisions for installation of electrically driven feed pump group.
Table 4.13.6 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of electrically driven feed pump group
_________Unit Project number:
Installation of turbine generator Subsection project Electrically driven feed pump group
Unit project name
auxiliaries name installation

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

All pipes shall be constructed according to design drawing. If


it need modify design or adopt substitute material, it must
1
apply to the design unit and handle it according to relevant
system.

If valves is used as the closed circuit components (for


isolation), tightness inspection must be carried out before
installation to check the tightness of the joint surfaces of the
2
valve seat and the valve spool, valve cover and packing
chamber. Tightness of valves shall be carried out with a
pressure 1.25 times of the name plate pressure.

It shall cut holes on the pipes according to design drawing


before installing pipes. After cutting holes, it must clean up the
3
inside and there shall be no drill cuttings or other foreign
bodies.

Before equipment installation, it must inspect the equipment as


required. If there is damage or quality defect, it shall timely
inform organizations concerned of joint inspection. As for
defect in equipment manufacture, it shall contact the
manufacturer for treatment. If the installation quality fails to
4
meet requirements due to manufacturing quality, it shall be
jointly negotiated among construction organization,
manufacturing unit, building or using unit; there shall be
records as well as confirmation and signature for construction,
equipment inspection and defect treatment after reaching

238
installation quality standard.

The important materials used in construction shall be provided


with quality certificate and material certificate. If the quality of
such materials are doubted during checking and inspecition;
5
they shall be inspected and identified necessarily. The
performance of lubricating oil (grease) must meet the design
specifications and national standard before application.

Drilling hole, gas cutting and welding shall not be carried out
6 on the oil pipe after it is cleaned up and sealed, otherwise,
cleaning, inspection and sealing must be carried out again.

Except cold-drawing welded junction specified in design, the


forced contra aperture shall be prohibited for rest welded
7
junction; thermal expansion technique shall not be used for
contra aperture

Acceptance result

Construction organization: (seal) Supervision organization: (seal)

Project technical director: Supervision engineer:


Date Date

4.13.7 See Table 4.13.7 for inspection on the implementation performance of subsection
project compulsory provisions for installation of booster pump and condensate pump of feed
pump.
Table 4.13.7 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of ( ) pump
_________Unit Project number:
Installation of turbine generator Subsection project
Unit project name
auxiliaries name

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

Before equipment installation, it must inspect the equipment


as required. If there is damage or quality defect, it shall
timely inform organizations concerned of joint inspection.
As for defect in equipment manufacture, it shall contact the
manufacturer for treatment. If the installation quality fails to
1
meet requirements due to manufacturing quality, it shall be
jointly negotiated among construction organization,
manufacturing unit, building or using unit; there shall be
records as well as confirmation and signature for
construction, equipment inspection and defect treatment

239
after reaching installation quality standard.

The important materials used in construction shall be


provided with quality certificate and material certificate. If
the quality of such materials are doubted during checking
2 and inspection; they shall be inspected and identified
necessarily. The performance of lubricating oil (grease)
must meet the design specifications and national standard
before application.

Acceptance result

Construction organization: (seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.14 Installation of condensate pump

Application scope: installation of condensate pump, including inspection, installation and trial
operation of condensate pump.
4.14.1 See Table 4.14.1 for inspection and acceptance of condensate pump.
Table 4.14.1 Inspection on condensate pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Pump Clear marking without


Matching parts disassembly Observing
disintegration repetition
overhaul Loosening top thread at
Axial rolling measurement Dominant Accurate and clear records bottom; measuring with
depth gauge

Axial rolling after dissembling


Dominant Accurate and clear records Measuring with depth gauge
inducer

Shell
No casting sand, pore, crack
Appearance Impeller and rag; smooth and clean on Observing
joint surface
Bearing support

Water lubricated bearing Meeting the requirements of


mm Measuring with feeler gauge
clearance manufacturer

In accordance with those


Rolling bearing overhaul
specified in Table 4.3.23

Meet the requirements of


Sliding bearing overhaul Dominant
manufacturer

240
Meet the requirements of
Pump shaft flexibility Dominant mm Measuring with dial gauge
manufacturer

Radial gap between impeller and Meet the requirements of Measuring with vernier
Dominant mm
sealing ring manufacturer caliper

Pump shell bolt-up Dominant Firm and without looseness Tightening again; observing

Installation of impeller, snap ring


No looseness Tapping with hand hammer
and shaft sleeve

Axial rolling before assembling


inducer Meet the requirements of Feeling by hands, knocking
Dominant
Axial rolling after assembling manufacturer with hammer and observing

inducer

Meet the requirements of


Radial total clearance between manufacturer, generally
Dominant mm Measuring with feeler gauge
inducer and enclosure 0.1%~0.15% of inducer
diameter and uniform around
Pump
assembling Locking after being properly
Bottom jacking screw Dominant Inspecting with spanner
positioned

The clearance of inducer and


enclosure from rotor meet
the requirement of the
Rotor hoisting height Dominant Correct measuring record
distance between required
location and the bottom;
measuring with depth gauge

Radial unilateral space between Measuring with outside and


Dominant mm 0.25~0.35
balancing drum and bushing inside micrometer

In accordance with those


Shaft seal installation
specified in Table 4.3.24

4.14.2 See Table 4.14.2 for inspection and acceptance on installation of condensate pump.
Table 4.14.2 Inspection and acceptance on installation of condensate pump
Inspection method and
Inspection item Property Unit Quality criteria
instruments

In accordance with those specified


Foundation inspection
in Table 4.3.18

Preparation and installation of iron In accordance with those specified


gasket and foundation bolt in Table 4.3.19

Deviation of central line mm 3 Measuring with steel tape

Elevation deviation mm 5 Measuring with level

Measuring with gradienter for


Levelness deviation mm/m 0.05
pump base

241
Clearance between support leg and
mm <0.05 Inspecting with feeler gauge
platen

In accordance with those specified


Coupling centre alignment a
in Table 4.3.32

Meet the requirement of rotor


Coupling gasket preparation b Dominant
hoisting height

a The side coupling of vertical condensate pump sways strongly. The iron block shall be first used to stuff inner bore of filling
box of pump shaft so that the deviation between pump shaft and inner bore of filling box is less than 0.05mm.
b The requirements for preparing this coupling gasket is only applicable to vertical condensate pump with thrust bearing on
motor.

4.14.3 See Table 4.14.3 for trial operation of condensate pump.


Table 4.14.3 Trial operation of condensate pump
Inspection method and
Inspection item Property Unit Quality criteria
instruments

Condenser trial operation under In accordance with those specified


non-vacuumized condition in Table 4.3.29

Vacuum pumping valve Dominant Opened Observing and trying by hands

Sealing water pipe Dominant Smooth and abundant water Start-up observing
Trial
operation Judging according to inlet and
Inlet screen Dominant No blockage
under outlet pressure
vacuum
Condensing water level Normal Observing
state

Observing and closing pump


Outlet pressure Dominant Meet requirements of drawing urgently in case of loss of
pressure

4.15 Installation of desuperheater and decompressor

4.15 See Table 4.15 for inspection and acceptance on installation of desuperheater and
decompressor
Table 4.15 Installation of desuperheater and decompressor
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inspection Flange sealing surface Complete, no radial groove Observing

Internal cleaning Clean and impurity-free

Filter screen eyelet Smooth

No blockage; blowhole diameter


Desuperheating water nozzle
meets the requirement of design

242
Restriction orifice
Meet requirements of drawing
arrangement

Reducing valve, regulating Flexible operation, tight packing


valve set

Material of alloy steel parts Meet requirements of drawing Spectrum inspection

Flexible operation; actuating


Safety gate pressure meets requirements of Water pressure test
drawing

Deviation of central line mm 10 Measuring with steel tape

Elevation deviation mm 10 Measuring with level

Levelness deviation mm/m


2 Measuring with level ruler

Verticality deviation mm/m


Installation

Correctly positioned, firmly


Steam baffle
welded, no crack in welded joints

Steam Spray water pipe


Smooth and impurity-free Observing
discharge and eyelet
device for
Internal cleaning Clean and no rust scale
access to
condenser Welded joints
connected with No crack, pore and other defects Oil penetration test
condenser

4.16 Installation of hoisting appliance

4.16.1 Installation of overhead traveling crane


Application scope: installation of overhead traveling crane, including rail installation and
inspection, crane assembly and installation, inspection and installation of transmission gear as
well as load test on overhead traveling crane.
1 See Table 4.16.1-1 for inspection and acceptance on rail installation
Table 4.16.1-1 Rail installation and inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

No crack, honeycomb and pitted


Foundation beam appearance Observing
surface

Elevation deviation of crane beam


mm 10 Measuring with level
and design

Deviation of Measuring with steel tape with


Span<19.5m Dominant mm 3
rail space and adding 100 N tension

243
design size Measuring with steel tape with
Span 19.5m Dominant mm 5
adding 150 N tension

Straightness deviation mm 3 Measuring with pulling line


Monorail
center line Deviation of
mm 3 Measuring with pulling line
reference line

Longitudinal
mm/m <1/1500 column space Measuring with level
levelness

Transverse levelness mm/m <1/100 track width Measuring with level ruler
Track

Maximum deviation
of full-range Dominant mm 10 Measuring with level
elevation of rail top

Elevation deviation between rack


mm 10 Measuring with level
and two railheads of sections

Ordinary joint mm 1~2 Measuring with feeler gauge


Track
clearance Measuring with straight steel
Temperature joint mm 4~6
ruler

Deviation between temperature joint Measuring with straight steel


mm 1
clearance and design value ruler

Transverse staggered joint of track Measuring with flat ruler and


mm 1
joint feeler gauge

Measuring with flat ruler and


Height difference of track joint mm 1
feeler gauge

Splint and track shall close to nut


Observing, Tapping with hand
Track bolt-up with complete washer ring, and
hammer
tightening firmly

Track joint welding Meet the requirement of design

Terminal limiting device Correctly and firmly positioned Observing

Contact with press plate, iron gasket, In good condition, compact and no
Tapping with hand hammer
track and crane beam looseness

In accordance with those specified


Secondary grouting
in Table 4.3.20

2 See Table 4.16.1-2 for inspection and acceptance on crane assembly and installation.
Table 4.16.1-2 Crane assembly and installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Bolting up all parts without


Appearance inspection looseness; no missing solder and Observing
crack in welded joints

244
Measuring with steel tape
adding 100~150 N tension or
Main beam span deviation mm 5
measuring wheel center distance
with telemeter

Measuring with steel wire and


Deflection of main beam mm/m 0.9~1.3
steel tape

Allowable
Box girder mm 5 Measuring bridge framework
deviation of
with steel tape adding 100~150
bridge
Single web beam N tension or with telemeter;
framework mm 10
truss diagonal line
diagonal line

Measuring with pulling steel


Lateral curvature of box girder mm <1/2000 Span
wire and steel tape

Lateral
Span L16.5ma mm 5
bending of Measuring with pulling steel

single web and wire and steel tape


Span L>16.5m mm <L/3000
beam truss

Track Distance end mm -1~2

deviation
Span Measuring with steel tape
of box Span <19.5m mm 1~5
end (Excurvation refers to +)
girder
traveller Midspan Span 19.5m mm 1~7

Traveller track deviation of single web


mm 3 Measuring with steel tape
and beam truss

Vertical Track gauge 3.5m mm 3


deviation
Measuring with level on the
of Track gauge 4m mm 5
same cross section
traveller
tracks Track gauge >4m mm 7

Trundle span deviation mm 3 Measuring with steel tape

L/1000, and the direction of


deflection of two driving wheels Measuring with pulling steel
Skewness of big wheel end surface mm
(or following pulley) shall be wire
opposite

Location difference of two wheels on Measuring with pulling steel


mm 1
one and the same balance beam wire

Location difference of one and the


Measuring with pulling steel
same end distance from the farthest mm 3
wire
two wheels

245
Perpendicular skewness of big wheel mm L/400 Measuring with plumb bob

Flutter of each transmission shaft mm 1 Measuring with dial gauge

The specification meets


Observing and inspecting
Appearance of steel wire requirements of drawing, no
intensity certification
broken-strand

Cylinder number of steel wire on


drum where hook at the extreme Ring 2
lower position

Steel wire on drum where hook at the Drum shall be able to contain Observing
extreme lower position entirely

Correct, firm and reliable


Dampener, limit switch
installation site

a L refers to wheel chord length at measuring position

3 See Table 4.16.1-3 for check, installation, inspection and acceptance of transmission gear.
Table 4.16.1-3 Inspection and installation of transmission gear
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

In accordance with those specified


Reductor inspection
in Table 4.3.38

Coupling
Radial deviation mm
alignment of
0.08 Measuring with dial gauge
motor and End surface
mm
reductor deviation

Radial deviation of coupling center


mm 0.15 Measuring with dial gauge
of transmission shaft

Appearance of brake strap, drum,


No crack and scar Observing
pulley and hook

Gap between brake strap of long


stroke brake and unilateral brake mm 0.7~0.8, and uniform on both sides Measuring with feeler gauge
wheel

Gap between D=100mm mm 0.60.1, and uniform on both sides


brake strap of
long stroke brake D=200mm mm 0.80.1, and uniform on both sides Measuring with feeler gauge
and unilateral
brake wheel D=300mm mm 1.00.1, and uniform on both sides

Brake strap gap Consistent in full length Measuring with feeler gauge

Qualified oil, flexible operation


Brake oil pump or electromagnet Observing
and block-free

246
Grease without rust and
Wheel bearing Observing
deteriorating

a D refers to diameter of brake wheel

4 See Table 4.16.1-4 for inspection and acceptance of load test on overhead traveling crane.
Table 4.16.1-4 Load test of overhead traveling crane
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Gap between edge of big Meet requirements of drawing, and


mm Observing
and small trundle and track on the same side

Wheel and rail contact Solid and gapless Observing

Travelling of big and Flexible rotation without strange


small travellers sound

Wheel rolls on the


No jam; disalignment
track
Unload test

Test on big and small roadster

Brake Sensitive and reliable Observing

Limit switch
Correct and reliable operation
Interlock protection
device

Gear case No-impacting sound


Feeling by hands

Bearing temperature Normal

Electric bridge
Catenary Dominant mm <L/700
type
arc of
Electric
crossbeam Dominant mm <L/600 Transit survey
monospar
at running
test Manual Dominant mm <L/500

Static Deflection of Restoration to the original state


load bridge Dominant and without residual deformation
test framework and abnormal phenomena
Inspection
Rotary hook Hooking with 1.25 times rated
after 1.25 Dominant Without residual deformation
opening load for 10 min, and inspecting it
times
after unloading
running test Welded joint No crack

Steel pieces No crack


Dynamic
load test

Testing load 1.1 times rated load Weigh or calculate

247
Test continuous time min 10 Timing

Stable, without abnormal


Travelling of big and small
Dominant vibration, blocking and impacting, Observing
travellers
and wheel track shall be carded

Motor temperature Normal Feeling by hands

Meet the requirements of Measuring with infrared


Bearing temperature
manufacturer, generally 80 thermometer

Flexible rotation, with normal


Variable speed drive parts vibration, gear meshing and Observing
normal sound

Actuation Sensitive Observing


Brake
Brake strap
Normal Feeling by hands
temperature

Stable elevation and subsidence,


Big and small hook Dominant and drum steel wire shall be lined
neatly
Observing
Motor, control equipment,
Normal operation, and accurate
limit switch and interlock
and reliable operation
protection

4.16.2 Installation of other cranes


Application scope: installation of other cranes (mainly electric block), including inspection
and installation of electric block as well as load test on electric block.
1 See Table 4.16.2-1 for inspection and acceptance on installation and inspection of electric
block.
Table 4.16.2-1 Inspection and installation of electric block
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Electric
Brake ring Without damage and grease Observing
block
inspection Revolving along the axis of Measuring with straight steel
Dominant mm 1.5~3
brake wheel ruler

No damage in gear; the oil meets


Reduction box Observing
the requirements of manufacturer

Without broken wires and hard


Steel wire Observing
bending

Without flaw and other damage,


Pulley and hook Observing and trying by hands
and flexible rotation

Fix steel wire on winding Rope shall be compacted by


Inspecting with spanner
drum press plate with firm bolt

Fix steel wire on outer cover mm Pigtail length of outstretching Observing, Tapping with hand

248
from bottom of wedge box 50; hammer
wedge chock tightly

No looseness; no jam on steel


Rope guide Observing
wire

No damage in gear; the relative


Travelling reduction gear position meets the requirements Observing
of manufacturer

Scatheless surface, flexible


Transport wheel Observing
rotation

Restricting electric block not to


Installing machine of
slide out track, and not to touch Observing
blocking entering
obstacle

One side of transport wheel


Gap between lateral margin
shall close to I beam, and
of I beam lower wing and mm 2~4
measuring another side with
transport wheel margin
straight steel ruler

Steel wire
Electric reservation on
block winding drum
Dominant Ring 3 Observing
installation where hook at
the extreme
Limiting
lower position
stopper
Distance
adjustment
between pulley
and drum cheek
mm 600 Measuring with steel tape
where hook at
the extreme
higher position

2 See Table 4.16.2-2 for inspection and acceptance of load test on electric block.
Table 4.16.2-2 Load test on electric block
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Hook where no load Stable zero friction and impaction Observing; listening by ears

Brake Reliable
Suspending with 1.25 times rated
Static
Steel wire Dominant No looseness load at 100mm height; inspecting
load test
after 10min

Lifting hook No deformation

Elevation and subsidence Elevation and subsidence with


Dynamic
of hook and travelling of Dominant Stable zero friction and impaction rated load, observing after
load test
traveller travelling 15 min.

249
Gliding distance of
suspended object after Dominant mm 50
braking

4.17 Installation of diesel generator

4.17.1 See Table 4.17.1 for inspection and acceptance on installation of diesel generator.
Table 4.17.1 Installation of diesel generator
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument

In accordance with those specified


Foundation preparation in Table 4.3.18 or meet the
requirements of manufacturer

In accordance with those specified


Making and installation of sizing
in Table 4.3.19 or Meet the
block and anchor bolt
requirements of manufacturer

Deviation of central line mm 10 Measuring with steel tape

Elevation deviation mm 10 Measuring with level

Vertical and horizontal levelness


mm/m 0.05 Measuring with gradienter
deviation

Installation of oil pipe, cooling


Complete, firm, no leakage; not
water pipe, discharge flue and heat Observing
obstructing the passage
extraction duct

In accordance with those specified


Secondary pouring in Table 4.3.20 or Meet the
requirements of manufacturer

4.17.2 See Table 4.17.2 for inspection and acceptance on trial operation of diesel generator.
Table 4.17.2 Trial operation of diesel generator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inspection Meet the requirements of


Oil level in tank Observing
before manufacturer
trial Check information or laboratory
Meet the requirements of
operation Oil desingnation test report provided by the
manufacturer
manufacturer

Evacuation gas valve Normal start-up; connection


Observing
inspection for oil tank between oil tank and atmosphere

Oil entrance & return valves start


Pipeline inspection up normally; the pipeline is Observing
smooth without blockage

250
Oil filling inspection on oil Full of diesel fuel, without air Inspecting by disassembling
Dominant
inlet pipe discharged fuel intake connection

Oil filling inspection for Full of diesel fuel, without air Inspecting by disassembling
Dominant
oil inlet filter screen discharged fuel intake connection

Cooling water pipeline


Normal pressure, no leakage Observing
inspection

The diesel engine starts/stops


Operation condition normally; the sound is normal Observing
without impacting phenomenon
Trial
Continuous operation time h 2 Timing
operation

Coasting operation with


Shutdown and coasting
determinated time and without Observing
operation
sudden stop

4.18 Installation of water circulating pump

Application scope: installation of water circulating pump, including inspection and


installation of water circulating pump for foundation and pump base (body), inspection and
installation of vertical centrifuged /diagonal / axial water circulating pump, inspection and
installation of motor for large-scale vertical / horizontal water circulating pump, installation
of oil system for water circulating pump, installation of parts and sets for hydraulic regulating
system of vertical water circulating pump as well as trial operation of large-scale vertical
water circulating pump.
4.18.1 See Table 4.18.1 inspection and acceptance on installation and inspection of
foundation and pump base (body) for water circulating pump.
Table 4.18.1 Inspection and installation of water circulating pump foundation and pump base (body)
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Foundation Deviation of foundation


mm 10 Measuring with steel tape
preparation central line

Relative elevation deviation


mm 10 Measuring with level
of each-layer foundation

Central deviation of
mm 10 Measuring with steel tape
foundation bolt hole

Center deviation of
mm 2 Measuring with steel tape
embedded foundation bolt

Center deviation of
mm 5 Measuring with steel tape
each-layer plate orifice

Dimensional check of floor Meet the requirement of


Observing
slab hole water-outlet bent pipe installation

Foundation Meet the requirement of DI/T


Curing time Inspecting curing records
cleaning 5210.1

251
and check Concrete
Dominant Meet requirements of drawing Check intensity report
strength

Free from reinforcement


Concrete exposion, honeycomb, crack,
Observing, knocking by hand
surface looseness, cobble extruding,
hammer
inspection defects, and cleaning up inside of
foundation bolt hole

Short piece and joint surface Flawless; without deformation,


Observing
of base burrs and groove

Deviation of
mm 3 Measuring with steel tape
central line
Base
Elevation
mm 5 Measuring with level
deviation

Levelness of base end


Dominant mm/m 0.05 Measuring with gradienter
surface

Preparation and installation In accordance with those


of iron gasket specified in Table 4.3.19

Concrete shall be compacted and


Installation
be without gap; the base and the
of pump
upper part of the pump base shall
base
be poured with filling; before
(pump Secondary pouring of base Observing
pouring of enclosure
body)
foundation-platform, the
enclosure dowel Bar and coat
shall be welded.

Local gap between planes of


composition of impeller mm <0.05 Inspecting with feeler gauge
enclosure and guide vane

It shall be in the right position; be


Packing ring of each section compacted; without rupture, Observing
detinning tank or local protrusion

Measuring with plumb bob and


Hub cap fixation Meet requirements of drawing
straight steel ruler

4.18.2 The inspection and installation of water circulating pump is divided into inspection
and installation of vertical centrifuged water circulating pump, inspection and installation of
diagonal water circulating pump and inspection and installation of axial water circulating
pump according to different pump forms.
1 See Table 4.18.2-1 for check, installation, inspection and acceptance of vertical centrifuged
water circulating pump.
Table 4.18.2-1 Inspection and installation of vertical centrifuged water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

252
No crack on surface, no
Appearance inspection Observing
mechanical damage

Meet the requirements of


Pump shaft flexibility mm Measuring with dial gauge
manufacturer

In accordance with those specified


Rolling bearing overhaul
in Table 4.3.23

Radial gap between impeller and Meet the requirements of


Dominant mm Measuring with vernier caliper
sealing ring manufacturer

Meet the requirements of


Rotor hoisting height Dominant mm Measuring with dial gauge
manufacturer

Clearance between balance Meet the requirements of


Dominant mm Measuring with feeler gauge
reinforcement and protecting cover manufacturer

Meet the requirement of rotor Checking according to


Coupling gasket preparation Dominant
hoisting value assembling records

Bearing lock nut fastening Firm Inspecting with spanner

2 See Table 4.18.2-2 for check, installation, inspection and acceptance of vertical diagonal
water circulating pump.
Table 4.18.2-2 Inspection and installation of vertical diagonal water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Appearance inspection of impeller,


No crack on surface, no
principal axis, coupling, bearing Observing
mechanical damage
support and main shaft sleeve drum

Single-axle flexibility Dominant mm 0.03 Measuring with dial gauge

Fluctuation after pump shaft Meet the requirements of


mm Measuring with dial gauge
assembling a manufacturer

Gap of rubber bearing and shaft Meet the requirements of


mm Measuring with vernier caliper
sleeve manufacturer

Gap of seal ring on back side of Meet the requirements of


Dominant mm Measuring with feeler gauge
impeller manufacturer

Radial clearance between impeller Meet the requirements of


Dominant mm Measuring with feeler gauge
and enclosure manufacturer

Axial clearance between impeller Measuring with straight steel


and enclosure ruler

Meet the requirements of


Rotor hoisting height Dominant mm Measuring with dial gauge
manufacturer

Meet the requirement of rotor Checking according to


Coupling gasket preparation Dominant
hoisting value assembling records

a The blade rotor assembling of blade adjustable diagonal pump may refer to the requirements of axial pump assembling.

3 See Table 4.18.2-3 for check, installation, inspection and acceptance of vertical axial water

253
circulating pump.
Table 4.18.2-3 Inspection and installation of vertical axial water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

No rust stain, rag and mechanical


Appearance inspection Observing
damage

Clearance with thrust-shaft


Dominant mm 0.10~0.15 Measuring with vernier caliper
Rocker arm

sleeve end-face

With inwall of rotor body No jam Trial operation

Pivot movement value of impeller Dominant mm 0.50 Measuring with dial gauge

Flexible rotation and without jam


Pivot
inside shaft sleeve

Transition fit with key groove;


Collared shaft Measuring with vernier caliper
fitting in loose and tight

Complete and no crack, rag and


Sealing device parts Observing
defection

Measuring with multi-purpose


Installation angle deviation Meet requirements of drawing
goniasmometer
Blade

Radial clearance between


Dominant mm 2~3 Measuring with feeler gauge
end face and enclosure

Oil servomotor piston stroke


Meet the requirements of
corresponding to blade Observing
manufacturer
corner

Rotation angle between Meet the requirements of


Observing
blades manufacturer

Blade rotation No jam Observing

Carrying out together with blade


Tightness of oil pipeline and sealing No leakage on combination plane
operation test according to the
device and bolt hole
requirement of manufacturer

Fastening and pouring lead or


Bolt of overflowing surface Observing
epoxy resin at bolt hole

No damage and rust in finishing


Appearance inspection on
processing; no chap and peeling in Observing
main shaft
Main shaft inspection

axle-neck chromium coating

Main shaft length checking Meet requirements of drawing Measuring with steel tape

Main shaft flexibility Dominant mm 0.10 Measuring with dial gauge

Radial flutter at axle neck mm 0.06

254
Coupling floating
mm 0.04
displacement

Coupling radial flutter mm 0.04

Cleaning up, the inside oil pipe be


Main shaft and internal oil added with gasket; the joint is
Observing
pipeline tight and the bolt is fastened and
locked uniformly

Partial gap on joint surface


of main shaft and pump mm <0.05 Measuring with feeler gauge
wheel

The joint surface shall be added


Final connection between
with water proofing paint Observing
main shaft and pump wheel
according to the requirements

Levelness deviation of
Dominant mm/m 0.05 Measuring with gradienter
coupling flange surface

When the blade is at maximum


Clearance deviation of blade and minimum corner, measuring
Dominant 20% of average value
Assembling of main shaft and pump wheel

and enclosure upper, middle and lower points


with feeler gauge

Unilateral space of lower 5%~15% greater than the


edge and enclosure of unilateral space of upper margin Measuring with feeler gauge
impeller and enclosure

Main shaft elevation before Design value, equal to coupling Measuring with straight steel
mm
installing motor seam depth plus 2~6 ruler

Hub cap Smooth in surface, no pit Observing

Align seal loop and water inlet;


Seal loop assembly Observing
smooth eyelet

Tight joint; the joints shall stagger


Packing set filling Observing
120~180 with each other

Thickness deviation of
mm 0.05 Measuring with vernier caliper
guiding bush

Upside-down clearance
Measuring with outside
deviation of axle and guide Dominant mm 0.05
micrometer and vernier caliper
bearing

4.18.3 The inspection and installation on motor of large-scale water circulating pump is
divided into inspection and installation on motor of large-scale vertical water circulating
pump and horizontal water circulating pump.
1 See Table 4.18.3-1 for check, installation, inspection and acceptance on motor of large-scale
vertical water circulating pump.
Table 4.18.3-1 Inspection and installation on motor of large-scale vertical water circulating pump

Inspection item Propert Unit Quality criteria Inspection method and

255
y measuring instrument

Inspection on plane of
composition of frame support Flat, smooth and no damage
leg

Oil groove tightness of Domin Inspecting after soaking


No leakage
upside-down frame ant kerosene for 24h

Water test with 1.25 times


Domin
Tightness of oil cooler No leakage operating pressure; inspecting
ant
Inspect after 5min

ion Motor coupling floating


mm 0.04 Measuring with dial gauge
before displacement

installa Meet the requirement of DL/T


Motor electric inspection
tion 5161.1~5161.17

Purging and inspecting by


Internal cooling pipe Smooth, clean
compressed air p

Water test with 1.25 times


Air Waterside tightness
No leakage operating pressure; inspecting
cooler test
after 5min

Air chamber Clean, impurity-free and tight


Observing
inspection joint

The rotor is slightly lower; With pump coupling elevation


Center deviation of rotor and Domin deviation value 0.4% of as reference, measuring
%
stator magnetic field a ant effective height of stator silicon magnetic field center after
steel sheet lower frame installation

Stator elevation error b mm 1 Measuring with level

With horizontal base center as


Installation of motor frame and stator

Domin
Frame center deviation mm 1.5 reference, measuring with
ant
straight steel ruler

Frame levelness deviation mm/m 0.10 Measuring with gradienter

Clearance Bolt fastening


mm 0.05
between position
Measuring with feeler gauge
lower frame Sum of wedged area of 0.05
Other position mm
and base feeler gauge 30% of total area

End face clearance after


mm <0.05 Measuring with feeler gauge
coupling joint

Partial gap on joint surface of


mm <0.05 Measuring with feeler gauge
stator and lower frame

Positioning pin Fit closely

Appearance inspection on thrust Domin No crack, pore, slag inclusion and Inspecting with coal-soaked or
bearing
thrust
d

bearing and guide bearing ant bodiless in black bronze oil penetrating fluid

256
Smooth, clean, flat, smooth and
Thrust disc Observing
no damage

Contact area of thrust segment Domin 70%, taking on uniform spot


Inspecting by painting
and thrust disc ant distribution

Support bolt Well-integrated with bearing bush Observing

Surface clearance between


mm <0.03 Measuring with feeler gauge
thrust block and upper frame

Motor Inspecting with feeler gauge at


Domin
installa Air gap deviation <10% of average value upside-down ends of magnetic
ant
tion pole

Upper-frame horizontal Domin


mm/m 0.10 Measuring with gradienter
deviation ant

Domin Measuring with combined


Thrust disc levelness mm/m 0.02
ant diagram level

Coordination of thrust cone and Meet the requirements of


shaft manufacturer

Measuring with outside


Thickness deviation of snap ring mm 0.02
micrometer

0.03; the length shall be less than


Clearance between snap ring
mm or equal to 20% of perimeter and Measuring with feeler gauge
and load-bearing surface
distributed uniformly

Thrust segment adjusting bolt Uniform load; tightly locked

Jacking up rotor after thrust


bearing oiling and measuring
Thrust-bearing insulation value M 0.30
with 1000V insulation
resistance meter

After oil tank oiling, measuring


Upper-guide-bearing insulation
M 0.30 with 1000V insulation
value
resistance meter

Meet the requirements of


Upper-guide-bearing and axial Domin Measuring with pressure fuse
mm manufacturer, generally
unilateral space ant method and feeler gauge
0.08~0.10

Domin
n<250r/min mm/m 0.03
Relative ant
Measuring opposite maximum
waggling n=250r/min~375r/mi Domin
mm/m reading with dial gauge at
of motor n ant
0.02 coupling section
shaft n=250r/min~600r/mi Domin
mm/m
n ant

Relative Domin Measuring opposite maximum


n<250r/min mm/m 0.05
waggling ant reading with dial gauge at
of water n=250r/min~375r/mi Domin pump guide bearing
mm/m 0.04
pump n ant

257
shaft n=250r/min~600r/mi Domin
mm/m 0.03
n ant

Absolutel Domin
n<250r/min mm 0.40
y ant
Measuring opposite maximum
waggling n=250r/min~375r/mi Domin
mm 0.30 reading with dial gauge at
of water n ant
pump guide bearing
pump n=250r/min~600r/mi Domin
mm 0.20
shaft n ant

Rad
ial
Dom
dire mm 0.12
inant
750>n500 ctio
r/min n

End
Permanent Dom
surf mm 0.06
couping inant Measuring opposite maximum
ace
center reading with dial gauge or
Rad
allowable feeler gauge
ial
deviation Dom
dire mm 0.16
inant
n<500r/mi ctio
n n

End
Coupling center deviation

Dom
surf mm 0.08
inant
ace
Motor installation

Rad
ial
Dom
dire mm 0.16
inant
750>n500 ctio
r/min n

Non-perm End
Dom
anent surf mm 0.10
inant Measuring opposite maximum
coupling ace
reading with dial gauge or
center Rad
feeler gauge
allowable ial
Dom
deviation dire mm 0.24
inant
n<500r/mi ctio
n n

End
Dom
surf mm 0.15
inant
ace

Radial total clearance of lower


mm 0.16~0.24 Measuring with vernier caliper
guide bearing

Adjusting bolt Tightly locked Inspecting with spanner

258
Positioning pin at joint surface Tightly contacted Tapping with hand hammer

aThe rotor field center is slightly lower than stator field center. bThe stator elevation error refers to the value after meeting the
previous requirements

2 See Table 4.18.3-2 for check, installation, inspection and acceptance on motor of horizontal
water circulating pump.
Table 4.18.3-2 Inspection and installation on motor of horizontal water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Inspection on plane of
composition of frame Flat, smooth and no damage Observing
support leg

Ellipticity Dominant mm 0.02


Shaft Measuring with outside
diameter Non-cylinder micrometer
Dominant mm 0.02
degree

Motor coupling floating


Inspection mm 0.04 Measuring with dial gauge
displacement
before
Bearing pedestal and In accordance with those
installation
bearing specified in Table 4.3.21~4.3.23

No rust, crack and deformation;


Appearance inspection on
the fan blades firmly installed Observing
motor fan
without looseness

Meet the requirement of DL/T


Motor electric inspection
5161.1~5161.17

Adjustable gasket for 2~3 floors, layout in echelon


Observing
stator and bearing pedestal form

Center deviation of rotor Meet the requirements of Measuring with straight steel
Dominant mm
and stator magnetic field manufacturer ruler

Stator elevation error mm 1 Measuring with level

Frame levelness deviation mm/m 0.20 Measuring with gradienter

Material
Motor dimension Meet the requirements of
Pedestal
installation Material manufacturer
bearing
quantity
insulation
Insulation Measuring with 1000V
M 0.5
resistance insulation resistance meter

Partial gap on joint surface


mm <0.05 Measuring with feeler gauge
of stator and lower frame

Positioning pin Tightly fitted

259
4.18.4 See Table 4.18.3-2 for inspection and acceptance on installation of oil system for
water circulating pump.
Table 4.18.4 Installation of oil system for water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Oil tank and equipment In good condition without scar and


Observing
appearance with complete components

Oil tank opening Complete and correct Observing

Flange studding hole It shall not penetrate box wall Observing

Internal cleaning of oil tank Dominant Clean and impurity-free Observing

Not dissolve in turbine oil; no


Paint inside oil tank Observing
falling off
Inspection and installation of high- and low-level oil tank

Inspecting after watering for


Oil-tank tightness test No leakage
24 h

Flat-bottom oil tank Leveling mortar and cladding


Observing
foundation damp proof course of asphalt

Bracket-carrying oil tank Smooth surface, and free from


Observing
foundation flaw and looseness

Deviation of vertical and


mm 10 Measuring with steel tape
horizontal central line

Elevation deviation mm 10 Measuring with gradienter

Verticality deviation mm/m 2 Measuring with level ruler

Levelness deviation mm/m 1.0

Interface direction Meet requirements of drawing

Installation of oil level


Firm and vertical Observing
gauge

Ladder footpath, platform Neat, nice, flat, smooth; meet the


Observing
and handrail technical requirements

Valve type Applying steel rising stem Observing


Oil piping installation

Valve cleaning Clean inside and no leakage Water pressure test

Pipeline material, pipe Clean inwall; no rust stain, dust


Dominant Observing
fittings and foreign bodies

Sleeve welding or argon arc


Welding Dominant Observing
welding for base coat

260
Measuring with glass tube
Scavenge pipe gradient Dominant mm/m 30~50
gradienter

Oil-pipe vertical deviation mm 1.5mm/m, and the maximum 7 Measuring with plumb bob

It shall not be transmitted to the


Oil pipe and valve loading Observing
Oil piping installation

equipment

Installation form and space Meet the requirement of drawing


Checking
of supporter and hanger design

Supporter and hanger


Firm, reliable and nice Observing
installation

On-site pressure gage and Correct position and quantity; meet


Checking
thermometer the requirement of thermal control

In accordance with those specified


Oil feed pump inspection
in Table 4.5.6-4 and Table 4.5.6-5

Deviation of vertical and


mm 10 Measuring with steel tape
horizontal central line

Elevation deviation mm 10 Measuring with gradienter

Circumference
Dominant nun 0.10
deviation Measuring with flat bevel
Coupling
End surface scale
centre Dominant mm 0.08
deviation
alignment
Coupling
mm 2~3 Measuring with steel tape
clearance
Inspection and installation of oil feed pump

Firm, nice process and convenient


Coupling outer cover Observing
maintenance

No rust, crack, damage; no groove


mark on sealing surface; no rag,
Oil filter inspection Observing
blockage and breakage in filter
screen eyelet

By-part Inlet oil pipe It may be connected with oil pump


Observing
trial rinsing after proving qualified
operation Manual rolling Uniform rotation without abnormal Listening to the sound and
rotor sound feeling by hands

Oil temperature
for trial 15~65 Measuring with thermometer
operation

Oil pump Measuring with vibration


Dominant mm 0.08
vibration gauge

Oil pump
Dominant 85 Measuring with thermometer
temperature

Oil pump Listening to the sound and


Dominant Normal, stable
operating state feeling by hands

261
Outlet oil pipe It may be connected with bearing
Observing
rinsing bush after proving qualified

4.18.5 See Table 4.18.5 for inspection and acceptance on installation of parts and sets for
hydraulic regulating system of vertical water circulating pump.
Table 4.18.5 Installation of parts and sets for hydraulic regulating system of vertical water circulating pump
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument

Levelness deviation of
flange on oil distributor mm/m 0.06 Measuring with gradienter
Inspection and installation of parts and sets

base

Radial flutter of oil


mm 0.10 Measuring with dial gauge
distributor

Concentricity deviation
of regulator and motor mm 0.60 Measuring with dial gauge
shaft

Pilot oil valve clearance


mm 0.15~0.20 Measuring with vernier caliper
of regulator

Piston stroke indication


Fit with indication of regulator
of regulator oil Observing
blade position
servomotor

4.18.6 See Table 4.18.6 for inspection and acceptance on trial operation large-scale vertical
water circulating pump.
Table 4.18.6 Trial operation of large-scale vertical water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Oil level gauge Normal oil level Observing

Meet the requirements of


Oil designation Observing
manufacturer
Inspection before trial operation

Cooling water pipe Smooth, adequate water quantity Observing

Flexible operation of the


Water quantity of
electromagnetic valve; meet Observing
lubrication water pipe
requirements of drawing

Fixed value of electric


and heat engineering Eligible
protection

Linkage test of pump and Coordination with the eelectric,


Meet requirements of drawing
outlet valve heat engineering debugging
Inspection during

No-load trial operation of


trial operation

Correct rotation direction Observing


motor

Meet the requirement of


Coupling reinspection Check installation records
installation records

262
Meet the requirement of rotor
Coupling connection Check installation records
hoisting value

Rubber First
10
bearing start-up
min Timing
pre-oiling Normal
5
time start-up

Linkage between start-up


Coordination with the eelectric,
after pump and outlet Meet requirements of drawing
heat engineering debugging
valve

Normal, zero friction; without Listening to and monitoring the


Operation condition
abnormal vibration and shock gauge needle, Feeling by hands

Reach to rated value and keep


Pump outlet pressure Measuring pressure gauge
stable

n250r/min Dominant mm 0.15


Measuring vertical and radial
Bearing 250<n<
Dominant mm 0.10 vibration at stator frame with
vibration 600r/min
vibrometer

n600r/min Dominant mm 0.08

A small amount of fresh water; Measuring with thermodetector


Shaft seal
normal temperature and observing

Adopt bearing
temperature of lubricating 80 Measuring with thermometer
grease

Bearing temperature by
70 Measuring with thermometer
adopting lubricant

Blade angle adjustment Meet the requirements of


test manufacturer

Continuous operation
h 4~8 Timing Observing
time

4.19 Rotary sieve installation

Application scope: rotary sieve installation, including inspection, installation and trial
operation of rotary sieve.
4.19.1 See Table 4.19.1 for inspection and acceptance on installation and inspection of
rotary sieve.
Table 4.19.1 Rotary sieve inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Appearance
inspection

Spare parts No damage, deformation, Observing


welded joints; no crack,
missing solder; no casting
263
sand, pore and crack in
castings

Combination (assembly) Flat, smooth; no rag and


Observing
surface groove mark

In accordance with those


Reductor inspection
specified in Table 4.3.38

In accordance with those


Bearing inspection specified in Table 4.3.22 and
Table 4.3.23

Preparation and
In accordance with those
installation of iron gasket
specified in Table 4.3.19
and foundation bolt

Meet the requirement of


Curing time Inspecting pouring records
DL/T 5210.1

Concrete Meet requirements of


Dominant Check strength test report
strength drawing
Foundation
Free from reinforcement
preparation
Concrete exposion, honeycomb, crack,
surface looseness, cobble extruding, Observing
inspection defects, and cleaning up
Seat frame installation

inside of foundation bolt hole

Height difference of
mm 5 Measuring with level
separated base coordinate

Deviation of central line mm 10 Measuring with steel tape

Elevation deviation mm 10 Measuring with level

Horizontal deviation of
Dominant mm/m 0.5 Measuring with gradienter
seat frame

Smooth joint; vertical in full


Sealing plate length; flat and smooth on Observing
sealing surface

Concrete foundation of
Contact tightly Observing
sealing plate support

Guide track Single-track bending Measuring with pulling steel


mm 3
installation deviation wire

Full-length straightness Measuring with pulling steel


mm/m 1
deviation of guide track wire

Interface malposition of
mm 1.5 Measuring with steel tape
guide track

Space deviation of guide


Dominant mm 3 Measuring with steel tape
track

264
Verticality deviation of Suspending plumb bob along
mm/m 1
guide track total height

Deviation of guide-track
mm 5 Measuring with steel tape
diagonal line

Guide-track center
elevation deviation of Dominant mm 3 Glass tube gradienter
bottom double-side curve

Horizontal deviation of
Dominant mm/m 0.5 Measuring with gradienter
loading shaft

Tightly fit with pin hole,


Guard pin of loading axis Observing
with cut-off groove on pin

Smooth oil hole; the oiling


Chain ring staff Observing
device is in good condition

Clearance
between
No looseness and jam
swivel pin
Driving motor installation

Chain and pin hole Observing and feeling by


plate Flexible and no jam in track hands
Roller
groove

Locknut and
Tightly locked
pin

Chain plate and otter Correct direction; reliably Checking according to


board assembly connected drawing

Align mutual position; no Observing and feeling by


Two chain wheel assembly
jam on chain plate hands

Otter-board diagonal line


mm 5 Measuring with steel tape
deviation

Clearance between
reductor, motor support mm 0.05 Inspecting with feeler gauge
and base

Meet requirements of Checking according to


Layout of wash waterpipe
drawing drawing

Correct position; smooth


Nozzle installation Observing
eyelet
Auxiliaries installation

Snap knife Flexible operation

Meet the requirements of


Dump tank gradient
manufacturer

Dirt blocking net In good condition; firm Observing

Transmission gear
Firm and reliable Observing
protective cover

265
In accordance with those
Metal cover plate
specified in Table 4.3.37

4.19.2 See Table 4.19.2 for inspection and acceptance on trial operation of rotary sieve.
Table 4.19.2 Trial operation of rotary sieve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Sieve rotation Dominant Flexible without jam Observing


Trial operation before access to water

Reductor No oil leakage; no crashing in gear Observing

Guard pin No deformation Observing

Bearing temperature 80 Measuring with thermometer

Meet the requirements of


Motor current
manufacturer

Trial operation time h 4~8 Timing

Motor operating current after Meet the requirements of


access to water manufacturer

4.20 Trash remover equipment installation

Application scope: trash remover equipment installation, including inspection and


installations well as trial operation of trash remover.
4.20.1 See Table 4.20.1 for acceptance on inspection and installation of trash remover
Table 4.20.1 Inspection and installation of trash remover
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

No damage, deformation, welded


joints; no crack, missing solder;
Parts Observing
Appearance inspection

no casting sand, pore and crack in


castings

Flat, smooth; no rag and groove


Joint surface Observing
mark

In accordance with those specified


Bearing inspection
in Table 4.3.23

Guide Preparation and


In accordance with those specified
track installation of iron gasket
in Table 4.3.19
installation and foundation bolt

Single-track bending Measuring with pulling steel


mm 3
deviation wire

266
Full-length straightness Measuring with pulling steel
mm/m 1
deviation of guide track wire

Interface malposition of
nun 1.5 Measuring with steel tape
guide track

Space deviation of guide


Dominant mm 3 Measuring with steel tape
track

Verticality deviation of Suspending plumb bob along


mm/m 1
guide track total height

Deviation of guide-track
mm 5 Measuring with steel tape
diagonal line

Planeness of net grating mm 3


Dirt blocking parts installation

Transit clearance at
longitudinal switching mm 3.5 Measuring with steel tape
section of net grating

Full-length verticality of Suspending plumb bob along


mm/m <1
dirt-blocking grate total height

Planeness of
mm 2
dirt-blocking grate

Horizontal deviation of
Dominant mm/m 0.5 Measuring with gradienter
loading shaft

Tightly fit with pin hole, with cut


Guard pin of loading axis Observing
-off groove on pin

Smooth oil hole; the oiling device


Chain ring staff Observing
is in good condition

Chain assembly No looseness and jam


Chain Observing and feeling by hands

Locknut and pin Tightly locked


Driving mechanism installation

The specification shall meet the


Steel wire and drum Observing and inspecting
requirement; no broken wire and
appearance intensity certification
crack

Cylinder number of steel


wire on drum with
Ring 2
scraper bucket at the
lowest position

Cylinder number of steel


Observing
wire on drum with Drum shall be able to contain
scraper bucket at the entirely
highest position

Installation of dampener Correct, firm and reliable


and limit switch installation site

Clearance between mm 0.05 Inspecting with feeler gauge

267
reductor, motor support
and base

Two chain wheel Align mutual position; no jam on


Observing and feeling by hands
assembly chain plate

Installation and layout of


Meet requirements of drawing Checking according to drawing
operating house
Accessory installation

Casing installation Firm and reliable Observing

Protective cover of
Firm and reliable Observing
driving device

In accordance with those specified


Metal cover plate
in Table 4.3.37

4.20.2 See Table 4.20.2 for inspection and acceptance on trial operation of trash remover.
Table 4.20.2 Trial operation of trash remover
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clearance between wheel Meet the requirement of drawing


mm
edge and track and on the same side

Wheel and rail contact Compact and gapless

Wheel rolls on the track No jam; disalignment


No load test

Integral traveling Flexible without strange sound Observing

Brake Sensitive and reliable

Limit switch Correct and reliable operation

Interlock protection
device

Feeling by hands and listening to


Transmission No abnormal sound
the sound
Non-load test

Scraper bucket lifting No jam Observing

Rotary brush and net


Meet requirements of drawing
grating
Trial operation of access to

Rotary brush rotation Dominant Flexible without jam Observing


water

Reduction gear No oil leakage; no crashing in gear Observing

Guard pin No deformation Observing

268
Bearing temperature 80 Measuring with thermometer

Meet the requirements of


Motor current
manufacturer

Trial operation time h 4~8 Timing

4.21 Installation of large-scale flat steel gate

4.21 See Table 4.21 for inspection and acceptance on installation and test of large-scale flat
steel gate.
Table 4.21 Installation and test of large-scale flat steel gate
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Door head appearance of


No oil leakage; no crashing in gear Observing
gate groove sill

Flat and smooth without pit; the


Observing and checking
Gate flap surface corrosion protection shall
Appearance manufacture document
meet the technical requirements
inspection
Appearance and Meet the requirement of design
Checking the drawing
dimension of parts drawing

Meet the requirement of design


Parts material Checking the drawing
drawing

Straight deviation of
Measuring with pulling steel
single-section gate mm 1/2000 of structure member length
wire
groove

Full-length straightness
Measuring with pulling steel
deviation of gate-groove mm 1
wire
working surface

Interface malposition of
Bulkhead mm 0.5 Measuring with steel tape
guide track
gate
Space deviation of guide
installation Dominant mm 8 Measuring with steel tape
track

Verticality deviation of Suspending plumb bob along


mm/m 1
guide track total height

Deviation of guide-track
mm 8 Measuring with steel tape
diagonal line

Bottom sill planeness mm/m 2 Measuring with level ruler

Secondary Inspection on gate Without missing parts and missing


Observing
pouring of groove connection solder
gate groove Inspection inside gate
Clean and impurity-free Observing
groove

269
Concrete pouring inside The concrete inside embedded parts
gate-groove embedded shall be much more parallel and Observing
parts level than that outside

Compact; thee shall be no cavity or


Concrete tamping air between concrete and embedded Observing
parts

Meet the requirement of DL/T


Curing
5210.1

Automatic hooking and


Flexible and reliable Observing
unhooking device

Gate flap at lowest


Tight waterstop Transparent inspection
Test on flat position
steel gate Full-travel on and off
Flexible, smooth and reliable Observing
test

On and off test on Check the design


Meet requirements of drawing
flowing water requirements

4.22 Deep water pump installation

Application scope: This part is applicable to deep water pump installation for water-collecting
pump house, including inspection, installation and trial operation of deep water pump.
4.22.1 See Table 4.22.1 for inspection and acceptance of deep water pump.
Table 4.22.1 Deep water pump inspection
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument

Coupling driving-shaft end face Flat and smooth; no rag, damage;


of pump shell and ascending-pipe vertical to axes; the screw thread is Observing
bracket in good condition

Fitting surface of impeller and No rust stain, rag and mechanical


Observing
tapered sleeve damage on the surface

No damage; forbidden to contact


Rubber bearing Observing
grease

Radial flutter of driving shaft Dominant mm <0.20 Measuring with dial gauge

Coordination of impeller and


Fastened without looseness Tapping with hand hammer
shaft

Clearance between sand cap and Meet the requirements of


Dominant mm Measuring with vernier caliper
sealing ring manufacturer

Clearance between balancing Meet the requirements of


Dominant mm Measuring with vernier caliper
drum and balance sleeve manufacturer

Clearance between impeller and Meet the requirements of


Dominant mm Measuring with vernier caliper
sealing ring manufacturer.

270
Axial displacement quantity of Measuring with push-and-pull
Dominant mm 6~8
impeller method

After tightening up water outlet


Elongation deviation of pump
mm 2 blade and shell, measuring with
shaft
depth gauge

4.22.2 See Table 4.22.2 for inspection and acceptance on installation of deep water pump.
Table 4.22.2 Deep water pump installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Complete gaskets; parallel flange;


Flange type overlapped adjacent pump-pipe Inspecting with pulling line
Outlet pipe
axes
connection

Pipe hoop type Fastening screw thread Observing and knocking

Joint is tightly fastened; the


Pump shaft connection chromium plating surface conform Observing
to guide bearing position

Levelness deviation of pump base mm/m 0.2 Measuring with level ruler

Connection between motor and Observing and tapping with hand


Bolt-up
pump base hammer

Meet the requirements of


Rotor hoisting height Dominant mm Measuring with depth gauge
manufacturer

Correct rotation direction; meet the


Connection between motor and Observing and measuring with
requirement of rotor hoisting
pump shaft straight steel ruler
height

Able to be taken out from shaft


Water level measuring device Observing
freely

Lubricating water pipe installation Correct joint and abundant water Observing

Insulating value for deep-well After filling condensed water for


pump motor of submersible water M 5 24h, measuring with 500V
pump motor insulation resistance meter

After being soaked under water


Insulating value for cable joint of
M >5 for 6h, measuring with 500V
submersible water pump motor
insulation resistance meter

4.22.3 See Table 4.22. for inspection and acceptance on trial operation of deep water pump.
Table 4.22.3 Trial operation of deep water pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

No-load trial operation of motor Correct rotation direction Observing

271
Rubber bearing preoiling time min 20 Timing

Motor working current <Rated value Measuring with amperemeter

Axial displacement quantity of No change before and after Stopping pump and measuring
Dominant
impeller start-up after start-up for 20min

Measuring with vibration gauge


Bearing vibration Dominant mm 0.10
at motor bearing pedestal

Bearing temperature 80 Measuring with thermometer

A small amount of fresh water;


Shaft seal Observing, Feeling by hands
normal temperature

Reach to rated value and keep


Pump outlet pressure Dominant Measuring pressure gauge
stable

Continuous trial operation time h 4~8 Timing

4.23 Installation of water purifying plant

Application scope: installation of water purifying plant for hydraulic engineering, including
inspection, installation and trial operation of water purifying plant.
4.23.1 See Table 4.23.1 for inspection and acceptance of water purifying plant.
Table 4.23.1 Inspection on water purifying plant
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Specification & model Meet requirements of drawing Checking according to drawing

Appearance The dimension shall meet the


inspection requirement of design drawing; Observing and measuring with
Visual inspection
correct joint position; the steel tape
appearance is in good condition

Internal The water chamber and enclosure


device Internal cleanliness is in good condition and Checking according to drawing
inspection impurity-free

Horizontal deviation of
mm 4
branch pipe

Vertical misalignment of
mm 3 Measuring with L-square
branch pipe and main pipe

Hole diameter and eyelet


Meet requirements of drawing Checking according to drawing
angle

Position of pipe orfices Meet requirements of drawing Checking according to drawing

272
Thickness of packing
Meet requirements of drawing Checking according to drawing
material

Enclosure material Meet requirements of drawing Checking according to drawing

The property shall meet Inspecting product qualification


Fillings Dominant
requirements of drawing certificate

4.23.2 See Table 4.23.2 for inspection and acceptance on installation and trial operation of
water purifying plant.
Table 4.23.2 Installation and trial operation of water purifying plant
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirement of DL/T


Curing time Inspecting pouring records
5210.1

Meet the requirement of


Installation Concrete surface design drawing; no Observing and checking
of water Foundation inspection reinforcement exposion, design drawing
purifying inspection honeycomb and crack
plant
Surface deviation mm 5 Measuring with level

Deviation of central
mm 5 Measuring with steel tape
line

Measuring with plumb bob


Vertical deviation mm 2.5% of the equipment height
Positioning along the total height
of water
Center displacement mm 10 Measuring with steel tape
purifying
plant
Elevation deviation mm 10 Measuring with level

Installation
Foundation surface
of water No impurity, dust and oil stain
cleaning
purifying
Concrete height of the Higher than or equal to the
plant
external base lower edge of base
Secondary
Compacted; there shall be no Observing
grouting
Concrete tamping gap at the lower bottom of
base

Meet the requirement of DL/T


curing
5210.1

Inspecting after fully filling


Test on access to water No leakage, No deformation
water for 24 h
Segmental
No water leakage and gas
trial Connecting pipeline of parts Observing
leakage
operation
Meet the requirement of
Water outlet of trial operation Dominant Checking laboratory report
design drawing

4.23.3 See Table 4.23.3 for inspection on the implementation performance of subsection

273
project compulsory provisions for engineering installation organizations in water-circulating
pump room equipment, public-water pump house equipment and water-collecting pump
house equipment.
Table 4.23.3 Inspection table on the implementation performance of subsection project compulsory
provisions for ( )
________Unit Project number:
Subsection project
Unit project name
name

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

Before filling water into tank container, it must thoroughly clean up


internal rusty scale, weld beading and foreign bodies. The internal
1
anticorrosive coating shall be painted according to design
requirements or after the study of technical section.

Before equipment installation, it must inspect the equipment as


required. If there is damage or quality defect, it shall timely inform
organizations concerned of joint inspection. As for defect in
equipment manufacture, it shall contact the manufacturer for
treatment. If the installation quality fails to meet requirements due
2
to manufacturing quality, it shall be jointly negotiated among
construction organization, manufacturing unit, building or using
unit; there shall be records as well as confirmation and signature
for construction, equipment inspection and defect treatment after
reaching installation quality standard.

When carrying out water pressure test on equipment, if it can only


observe condition of water pressure test by disassembling certain
3
parts and the permanent deformation may be caused on equipment
for this, it must carry out temporary strengthening work.

Access opening must not be opened randomly on the pressure


vessel, pipe seat must not be welded, and repair must not be carried
4
out, as well as pipes must not be used as hanger and support points
for hoisting other heavy things.

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

274
4.24 Main body installation of combustion engine

Application scope: main body installation of combustion engine, including preparation of


combustion engine foundation installation, main body positioning and installation of
combustion engine, installation of inlet system, installation of exhaust system and enclosure
installation of combustion engine.
4.24.1 See Table 4.24.1 for inspection and acceptance on preparation of combustion engine
foundation installation.
Table 4.24.1 Preparation of combustion engine foundation installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Smooth surface without crack,


Appearance inspection hole, honeycomb, pitted surface Observing
and reinforcement exposion

Foundation longitudinal
center line and combustion mm/m <2
Inspecting by isosceles triangle
engine
Dominant method; measuring with steel
Transverse verticality
tape
deviation of main-body mm Total deviation value <5
supporting leg

Verticality deviation
mm/m <2
between foundation Inspecting by isosceles triangle

longitudinal center line and Dominant method; measuring with steel

Foundation generator foundation mm Total deviation value <5 tape

inspection transverse center line

With elevation reference line as


Elevation deviation of Meet the requirement of design
mm benchmark, measuring with
bearing area drawing, 10
level

Clean, without lacquer, oil dirt


Foundation cleaning Observing
and oil dirt

Foundation strength during


>70% of design strength Strength test
roughening

Chip away surface concrete layer


Roughening depth Observing
and expose coagulation layer

Position for mounting and


adjusting small lifting jack Flat, smooth and without drop pit Observing
or temporarily iron gasket

Deviation between bolt


Embedded With foundation horizontal
center and foundation Meet requirements of drawing,
foundation mm central line as benchmark,
vertical and horizontal <2
bolt measuring with steel tape
center line

Bolt elevation deviation mm 0~3 With reference line as


benchmark, measuring with

275
level

Vertical deviation mm L/450a

Appearance Without lacquer and dirt Observing

Bolt and nut coordination mm Flexible without jam Inspecting and feeling by hands

Length and diameter of


Meet requirements of drawing Measuring with steel tape
bolt

Gap between bolt and bolt


Meet the requirements of
hole or gap within bolt mm Measuring with steel tape
manufacturer, >5
sleeve

Meet the requirements of


After tightening up bolt manufacturer, exposing 2~3 Observing
buckles

Deviation between
With vertical and horizontal
anchorage plate center and
mm <3 central lines benchmark,
foundation vertical and
Embedded measuring with steel tape
horizontal center line
anchorage
Elevation deviation of With foundation line as
plate mm 3
anchorage plate benchmark,

Verticality difference of
mm/m <3 Measuring with plumb bob
positioning retaining plate

Meet the requirement of design


Recheck on reserve hole and limes
and practical equipment Measuring with steel tape
margin is dimension
installation

Meet the requirements of Measuring with level gauge and


Embedded base plate
manufacturer communicating vessels

Meet the requirements of


Alloy steel stone bolt material Spectrum inspection
manufacturer

a L refers to the length of foundation bolt

4.24.2 See Table 4.24.2 for inspection and acceptance on installation and inspection of
combustion engine base plate and platen
Table 4.24.2 Inspection and installation of combustion engine base plate and platen
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Pedestal sliding surface and base Flat, smooth, clean and no Inspecting with leveling ruler
plate inspection damage, deformation and rag feeler gauge

No crimping, rust; flat, smooth and


Gasket inspection Observing
clean; cut opening at bolt

Base plate; Measuring with level gauge and


Elevation mm 1
platen communicating vessels

276
Meet the requirement of drawing
Measuring with combined
Horizontal mm/m provided by the manufacturer, with
diagram level
the same direction

Meet the requirement of rawing Measuring with tapeline and


Gasket geometric dimension mm
provided by the manufacturer outside micrometer

Inspection on base plate, platen and Meet the requirement of the


Dominant Inspecting by painting on site
gasket contact manufacturer

Contact between pedestal bottom


Dominant mm <0.05 Inspecting with feeler gauge
surface and fixer spherical face

Meet requirements of drawing;


Longitudinal and horizontal device Measuring with straight steel
mm deviation of platen central line in
of base plate and platen ruler
vertical and horizontal direction<1

4.24.3 Positioning and installation of combustion engine main body


Application scope: This part is applicable to positioning and installation of combustion engine
main body, including positioning inspection of combustion engine, installation of combustion
chamber, load distribution of combustion engine, adjustment and connection of shafting,
clearance measurement and adjustment of sliding pin system as well as installation of
automatic synchronizing device.
1 See Table 4.24.3-1 for inspection and acceptance of combustion engine positioning
Table 4.24.3-1 Combustion engine positioning inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

The appearance is in good


condition; no collision mark in
Appearance inspection on equipment Dominant Site inspection
transport; the transport detection
device indicates in good condition

Clean and without rag, high spot,


Combustion engine base Site inspection
rust and groove

Combustion engine hoisting and No damage on equipment;


Dominant Observing, measuring
positioning accurately positioned

Inspection on combustion engine and Meet the requirement of the Inspecting by painting on site;
Dominant
platen contact surface manufacturer inspecting with feeler gauge

Measuring with feeler gauge


Meet the requirement of the
Gasket partial clearance mm among support, gasket and
manufacturer
platen

Fastening of anchor bolt nut gasket Fastening according to the


Nm Torque spanner
and base requirement of the manufacturer

2 See Table 4.24.3-2 for inspection and acceptance on installation of burner


Table 4.24.3-2 Burner installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirements of


Material of alloy steel parts spectrum check
manufacturer

277
Cleanliness inspection inside Clean and without rust and foreign
Dominant Site inspection
combustion chamber bodies

Cleanliness inspection inside main Clean and without rust and foreign
Dominant Site inspection
body joints bodies

Inspection on joint flange face of Clean and without rag, high spot,
Site inspection
burner and main body rust and radial groove

The number is consistent with the


Installation position Dominant Site inspection
drawing

The opposite-angle fastening and


Bolt-up Dominant the moment shall meet the Inspecting with torque spanner
requirement of the manufacturer

3 See Table 4.24.3-3 for inspection and acceptance of combustion engine load distribution
Table 4.24.3-3 Combustion engine load distribution
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

No crimping, rust; flat, smooth and Observing and inspecting with


Gasket cleaning and check
clean; cut opening at bolt micrometer

Meet the requirements of Measuring with dial gauge or


Load distribution Dominant mm
manufacturer chock

Meet the requirements of


Combustion engine rotor lift Dominant mm/m Combined diagram gradienter
manufacturer

4 See Table 4.24.3-4 for inspection and acceptance of shafting adjustment and connection
Table 4.24.3-4 Shafting adjustment and connection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Spectrum inspection or
Meet the requirements of
Coupling bolt; nut material examining certification
manufacturer
provided by the manufacturer

Meet the requirements of


Coupling bolt; nut hardness Inspecting with sclerometer
manufacturer

Meet the requirements of


Material of other alloy steel parts Spectrum inspection
manufacturer

Meet the requirements of


Minimum axial throughflow clearance Dominant mm Dial gauge; special tools
manufacturer

Corresponding to the
manufacturer's mark; when there
Coupling relative position is no mark, the floating Site inspection
displacement shall be offset
mutually

Central Measuring with feeler gauge,


reinspection Deviation of measured Dominant mm Meet the requirements of chock or dial gauge

central height difference manufacturer, 0.02


value and reserve value
required by the
278
manufacturer

Meet the requirements of


Right-left center deviation Dominant mm
manufacturer, 0.02

Deviation of measured
lower gape value and Meet the requirements of
Dominant mm
reserve value required by manufacturer, 0.02
the manufacturer

Meet the requirements of


Right-left gape deviation Dominant mm
manufacturer, 0.02

Meet the requirements of


Bolt-hole surface roughness Observing
manufacturer or

Meet the requirements of


Bolt surface roughness Observing
manufacturer or

After formal coupling


Circumference flutter before and after Meet the requirements of
Dominant mm connection, measuring with dial
coupling joint manufacturer, 0.02
gauge

Safety pin, stop pin, cotter pin, nut-cap Correct assembling; complete;
Observing
cover plate, bolt assembly tightly locked

Bolt and nut Meet the requirements of


coordination manufacturer

Measuring with inside


Coupling spigot Meet the requirements of
mm micrometer calipers or dial
dimension manufacturer
gauge
Loading minor
Weight difference of
axis; coupling Meet the requirements of Weighing with scale or
symmetrical screw Dominant g/set
joint manufacturer or <10 electronic scale
bolt and nut

Measuring external diameter


Correct tightening sequence; the
with depth micrometer; torque
Bolt-up a Dominant fastening degree shall meet the
spanner or special tools for
requirements of manufacturer
hydraulic tensioning

a Generally, the bolt-up degree is measured by bolt elongation, fastening force moment or oil pressure of hydraulic tensioning
instrument

5 See Table 4.24.3-5 for inspection and acceptance on measurement and adjustment of sliding
pin system clearance.
Table 4.24.3-5 Measurement and adjustment of sliding pin system clearance
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
horizontal pin

Distance between
Vertical and
i

Meet the requirement of the


anchorage plate and mm Tapeline
ll i

manufacturer
combustion engine

279
Smooth, clean and without high
Contact surface inspection Dominant Feeling by hands
spot and rag

Meet the requirement of the Measuring with feeler gauge and


Sheet inserting clearance Dominant mm
manufacturer micrometer

Smooth and clean; complete screw


Cleaning and check Observing
thread; without scar and rag

Fit properly; tighten the nut to the


Bolt and nut inspection Observing
Push-pull rod installation

end freely

Meet the requirement of the


Installation position Site inspection
manufacturer

Meet the requirements of force


Fastening Dominant moment required by the Torque spanner
manufacturer

Correct installation; reliable


Anti-loose pin Observing
fastness

6 See Table 4.24.3-6 and Figure 4.24.3 for inspection and acceptance on installation of
automatic synchronizing device
Table 4.24.3-6 Installation of automatic synchronizing device
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

The appearance is in good


condition; no collision mark;
Equipment appearance Dominant clean; complete; complete Observing
assembly; meet the requirement of
the manufacturer

Installation position Meet requirements of drawing Observing

Reserve dimension mm Meet requirements of drawing Tapeline

Pallet upper-part
Measuring with inside
longitudinal spacing A mm Meet requirements of drawing
micrometer
during SSS clutch on-off

Pallet left-side longitudinal


Measuring with inside
spacing A during SSS clutch mm Meet requirements of drawing
Installation dimension

micrometer
on-off

Pallet right-side
Measuring with inside
longitudinal spacing A mm Meet requirements of drawing
micrometer
during SSS clutch on-off

Pallet upper-part lateral


Measuring with depth
spacing B during SSS mm Meet requirements of drawing
micrometer
clutch on-off

Pallet left-side lateral


Measuring with depth
spacing B during SSS nun Meet requirements of drawing
micrometer
clutch on-off

280
Pallet right-side lateral
Measuring with depth
spacing B during SSS mm Meet requirements of drawing
micrometer
clutch on-off

The opposite-angle fastening and


Bolt-up Dominant the moment shall meet the Inspecting with torque spanner
requirement of the manufacturer

Figure 4.24.3 Automatic synchronizing device


4.24.4 Inlet system installation
Application scope: This part is applicable to air inlet system installation of gas generating unit,
including assembly and installation of inlet chamber, air purification, sealing inspection on
sound deadening system and inlet system.
1 See Table 4.24.4-1 for inspection and acceptance on assembly and installation of inlet
chamber
Table 4.24.4-1 Assembly and installation of inlet chamber
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Tight overlapping; no damage on


Gasket installation Observing
gasket

Bolt-up Firm and without looseness Observing

Firm; guaranteed by argon arc


Nut insurance Observing
welding

Inspection and installation of


Meet requirements of drawing Observing
expansion joint

2 See Table 4.24.4-2 for inspection and acceptance of air purification sound deadening system
Table 4.24.4-2 Air purification and sound deadening system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean, no deformation, no damage


on expansion joint; ageing; meet
Equipment appearance inspection Site inspection
the requirement of the
manufacturer

Deviation of central
Alignment mm 10 Measuring with steel tape
line

281
Elevation deviation mm 10 Measuring with level

0.2% of the total height; and the


Vertical deviation mm Site inspection
maximum 10

Clearance between
Gapless after glue impregnating Site inspection
modules

Connected Staggered joint Meet the requirements of


mm Measuring with steel tape
with expansion deviation manufacturer
joint of inlet Meet the requirements of
Blocking distance mm Measuring with steel tape
chamber manufacturer and expansion

Correct position; the space


Inspecting with straight steel
Silencer installation between meets the requirement of
ruler
drawing

Correct position; no water leakage


Rain hood installation Site inspection
and nice in appearance

Tight overlapping; no damage on


Sealing washer installation Site inspection
gasket

The specification meets the design


Filter screen installation requirements; correct position; Observing
tight joint

Correct position; flexible and tight


Manhole door inspection Site inspection
switching

Platform, stairway and handrail Neat, nice, flat and smooth; meet
Observing
installation the technical requirements

3 See Table 4.24.4-3 for inspection and acceptance of inlet system sealing
Table 4.24.4-3 Sealing inspection of inlet system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Clean and without rust, weld


Internal cleaning Dominant Observing
beading and foreign bodies

Correct gasket installation; no part


Gasket inspection Dominant Observing
reaching the passage

Filter screen inspection Dominant Complete, clean and no damage Observing

Correct, complete and reliable


Inside bolt installation Dominant Site inspection
anti-loose measures

Internal transmittancy inspection Dominant No ray penetration Observing

Pass examination on internal work


Manhole door sealing Dominant Observing
omission and cleanliness

4.24.5 Exhaust system installation


Application scope: This part is applicable to exhaust system installation of gas generating unit,
including installation of exhaust frame and diffusion section, assembly and installation of

282
draught flue as well as sealing inspection of exhaust system.
1 See Table 4.24.5-1 for inspection and acceptance on installation of exhaust frame and
diffusion section
Table 4.24.5-1 Installation of exhaust frame and diffusion section
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Center deviation of Meet requirements of drawing,


Dominant mm Measuring with steel tape
Foundation embedded foundation bolt and 5
preparation Meet the requirement of the
Base plate elevation nun Gradienter
manufacturer

Clean and without rag, high spot,


Cleaning and check of frame and rust and radial groove; no Measuring with leveling ruler
diffusion section staggered joint on flanged joint and observing on site
surface

No malposition; smooth screw


thread; no rag and damage; fit
Bolt hole inspection Observing
properly; the nut may be screwed
Inspection
to the end by hands
on exhaust
Correct and complete; the force
flange face
moment meets the requirement of
Bolt-up Observing
the manufacturer; reliable
anti-loose measures

Correct, Meet the requirement of


Installation position Dominant Observing
the manufacturer

Meet the requirements of force


Diffusion Bolt-up Dominant moment required by the Torque spanner
section manufacturer
installation Flange face clearance Meet the requirement of the
Dominant mm Inspecting with feeler gauge
inspection manufacturer, <0.03

Correct, complete and reliable


Press plate installation Site inspection
anti-loose measures

2 See Table 4.24.5-2 for inspection and acceptance on assembly and installation of draught
flue
Table 4.24.5-2 Assembly and installation of draught flue
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Cleaning and Cleaning and check of Clean and without rag, high spot,
Observing
check of joint surface flange rust and radial groove
inlet and Inspection on bolt
Clean and no rust Observing
outlet flue hole cleanliness

Fastening piece Smooth and clean; complete


Observing
inspection screw thread; without scar and rag

283
Inspection on spring
thread insert inside Tightly fit with bolt hole Observing
bolt hole

No damage on gasket; correct


Gasket inspection, installation Dominant
position; no straight gape

Meet the requirements of


Flange seal weld PT inspection
manufacturer

Bolted connection Firm and without looseness Site inspection


Expansion
joint Protection block
Abundant quantity; firm
inspection inspection before Site inspection
connection
installation

Expansion joint Meet the requirements of Measuring with straight steel


dimension inspection manufacturer ruler

The force moment shall meet the


Bolt-up Torque spanner
requirements of manufacturer

Vertical and
horizontal mm 10 Tapeline
central line
Draught flue
installation Elevation mm 10 Gradienter

Meet the requirement of the


Sliding surface Dominant Site inspection
manufacturer

3 See Table 4.24.5-3 for acceptance on sealing inspection of exhaust system


Table 4.24.5-3 Sealing inspection of exhaust system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Internal cleaning Dominant Clean and impurity-free Observing

Internal thermal insulation inspection Dominant Correct installation; complete

Correct, complete and reliable


Internal bolt installation Dominant Site inspection
anti-loose measures

Correct gasket installation; no part


Gasket inspection Dominant Observing
reaching the passage

Pass examination on internal work


Manhole door sealing Dominant Observing
omission and cleanliness

4.24.6 See Table 4.24.6 for inspection and acceptance on assembly and installation of
bypass chimney
Table 4.24.6 Assembly and installation of bypass chimney
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

284
Checking according to the
Center deviation of
Dominant 10 drawing; measuring with
Foundation embedded foundation bolt
steel tape
preparation
Meet the requirement of the
Base plate elevation mm Gradienter
manufacturer

Bolt up Firm and without looseness Observing

Tight overlapping; no damage on


Gasket installation Site inspection
Chimney gasket
assembly
Welded junction inspection Meet the requirement of DL/T 869 PT test

The space between expansion


Expansion joint installation Dominant Site inspection
meets the requirement of drawing

Note: This Table is applicable to the assembly and installation of bypass chimney in case of no exhaust-heat boiler

4.24.7 See Table 4.24.7 for inspection and acceptance on installation of combustion engine
enclosure
Table 4.24.7 Installation of combustion engine enclosure
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Deviation of central line mm 10 Steel tape

Tight overlapping; no damage on


Gasket installation gasket; the joint is in dovetailed Site inspection
groove
Enclosure
assembly Bolt-up Firm and without looseness Observing

Inspection access, manhole


Flexible switch; sealing Site inspection
door inspection

Fabrication of platform, ladder and Neat, nice, flat and smooth; meet
Observing
handrail the technical requirements

Internal transmittance inspection of


Dominant No ray penetration Observing
enclosure

Spray test on fire extinguishing system Dominant Tight enclosure; no leakage point Observing

4.24.8 See Table 4.24.8 for inspection and acceptance on installation of combustion engine
main-body pipeline
Table 4.24.8 Installation of combustion engine main-body pipeline
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument

Meet the requirement of DI/T


Pipeline connection Site inspection
5210.5

285
Correct direction; flexible
Valve installation Site inspection
operation

Meet the requirement of DL/T


Supporter and hanger installation Site inspection
5210.5

The bolt-up force moment shall


Flange connection meet the requirements of Site inspection
manufacturer

Inspection and installation of


Meet requirements of drawing Site inspection
expansion joint

Gasket installation Meet requirements of drawing Site inspection

Meet the requirement of DL/T


Tightness test Dominant
5210.5

Sound system; the temporary pipe


Preparation before pipeline blow-down Site inspection
intensity meets the requirement

Pipeline blow-down and cleanliness Clean and without rust and foreign Air for instrument or nitrogen
Dominant
inspection bodies purging inspection

Prevent secondary pollution; the


Pipeline recovery Dominant bolt -up or welding meets the Site inspection
requirement of this system pipeline

4.24.9 See Table 4.24.9 for inspection on the implementation performance of subsection
project compulsory provisions for installation of combustion engine main body.
Table 4.24.9 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of combustion engine main body
________Unit Project number:
Subsection project Main body installation of combustion
Unit project name Combustion engine installation
name engine

Project number Acceptance time Date

Implementation
SN Inspection item Related information
performance

Before equipment installation, it must inspect the equipment as


required. If there is damage or quality defect, it shall timely inform
organizations concerned of joint inspection. As for defect in
equipment manufacture, it shall contact the manufacturer for
treatment. If the installation quality fails to meet requirements due
1
to manufacturing quality, it shall be jointly negotiated among
construction organization, manufacturing unit, building or using
unit; there shall be records as well as confirmation and signature
for construction, equipment inspection and defect treatment after
reaching installation quality standard.

The important materials used in construction shall be provided


2 with quality certificate and material certificate. If the quality of
such materials are doubted during checking and inspecition; they

286
shall be inspected and identified necessarily. All performances of
quality steel, alloy steel, high-pressure and high-temperature
welding material, lubricating-oil (grease) and fire-resistant oil must
meet design requirements and national standards before
application.

Settlement observation point shall be set up on foundation of


combustion gas turbine and combined cycle generating unit. When
there is obvious change on measurement for leveling, alignment
3 and centering every other day caused by non-uniform settlement of
foundation, the equipment shall be not be installed. Except
strengthening settlement observation, it shall also carry out
research and treatment.

When clearance of sliding pin is unqualified, it shall make


adjustment. As for oversized clearance, it shall allow repair
welding or ion spraying on the whole contact surface; but its
4
hardness shall be greater than or equal to that of virgin metal. It
shall not narrow clearance of narrow by restraining and squeezing
method.

The quality acceptance of material shall be in compliance with the


following requirements:
(1) The metallic material under supervision must meet the relevant
national standard and professional standard. The imported metallic
material must meet the requirements of relevant national technical
standards specified in contract.
(2) The steel, steel tube and spate parts as well as auxiliaries under
supervision must be carried out with quality acceptance according
to quality certificate and quality guarantee. The quality certificate
or quality guarantee shall be indicated with steel type, chemical
composition, mechanical property as well as necessary
metallographic inspection result and heat treatment technique. As
for those with insufficient data, it shall make up for inspection. The
5
method, range and quantity of supplemented inspection shall meet
the national standard or relevant professional standard. The
imported metallic material shall not meet the requirements of not
only relevant national technical standards specified in contract, but
also commodity inspection qualification document.
(3) The important metal parts shall not only meet the requirement
of relevant professional standards and national standards, but also
have quality guarantee for parts. As for alloy steel materials and
parts within the supervision scope, their steel types shall be
verified in manufacture, installation or overhaul to prevent
misusage. After assembling, comprehensive review shall be made
for a second time to confirmation no mistake before putting into
operation

287
Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.24.10 See Table 4.24.10 for inspection on the implementation performance of subsection
project compulsory provisions for installation of combustion engine main-body pipes
Table 4.24.10 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of combustion engine main-body pipes
________Unit Project number:
Installation of combustion engine auxiliary Installation of combustion
Unit project name Subsection project name
device engine main-body pipes

Project number Acceptance time Date

Implementation Related
SN Inspection item
performance information

Those important materials used in construction shall be provided with


quality certificate and material certificate. If the quality of such materials
1
are doubted during checking and inspecition; they shall be inspected and
identified necessarily.

Auxiliary facilities andother design requirements:


(1) Gas flow measuring device shall be set up for in-factory main gas
pipe and gas inlet pipe on each combustion gas turbine; emergency shut
( of ) valve shall be installed for in-factory main gas pipe, which shall be
set up at safe and operation-convenient position.(2) Lightning protection
facilities shall be set up for pressure regulating station; there shall be
electrostatic grounding facilities for pipeline and equipment inside the
station.
(3) Inside the plant shall be set up with inert gas replacement system
2
during outage of natural gas pipeline. The capacity of replacement gas
should be twice as much as total capacity of replaced gas.
(4) The natural gas system inside the factory shall be set up with air
lancing, sampling joint exhaust stack for gas displacement. According to
layout or safety requirements, the exhaust stack may be set up
independently or led to blowdown pipe by part concentration. The
discharge of relief gas into the atmosphere shall meet the requirement of
environmental protection and fire protection to prevent it from intaking
into ventilation system, window or adjacent buildings.

288
All pipes shall be constructed according to design drawing. If it need
3 modify design or adopt substitute material, it must apply to the design
unit and handle it according to relevant system.

Alloy-steel pipe, pipe fittings, pipe auxiliaries and valve shall be carried
4 out spectrum recheck piece by piece before using, and make marks for
material

During pressure test of pipe system, the pressure shall be maintained for
10min after reaching test pressure and then drop to design stress;
comprehensive inspection shall be carried out for all joints. There shall
5
not be water seepage or leakage mark on the overall system except partial
places obstruct of pump or valve padding and no deformation by visual
observation.

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.25 Combustion engine auxiliary device and accessory machinery installation

4.25 See Table 4.25 for inspection on the implementation performance of subsection project
compulsory provisions for gas equipment installation subsection project, fuel-fired equipment
installation subsection project as well as other equipment installation of combustion engine.
Table 4.25 Inspection table on the implementation performance of subsection project compulsory provisions
for ( )
________Unit Project number:
Combustion engine auxiliary device and Subsection project
Unit project name
accessory machinery installation name

Project number Acceptance time Date

Implementation Related
SN Inspection item
performance information

Before equipment installation, it must inspect the equipment as required.


If there is damage or quality defect, it shall timely inform organizations
concerned of joint inspection. As for defect in equipment manufacture, it
shall contact the manufacturer for treatment. When the installation
quality can't be reached due to manufacturing quality, joint negotiation
shall be made among construction organization, manufacturing
organization, development or using organization. There shall be records
as well as confirmation and signature for construction, equipment

289
inspection and defect treatment after reaching installation quality
standard.

Those important materials used in construction shall be provided with


quality certificate and material certificate. If the quality of such materials
2 are doubted during checking and inspection; they shall be inspected and
identified necessarily. The performance of lubricating oil (grease) must
meet the design specifications and national standard before application.

All pipes shall be constructed according to design drawing. If it need


3 modify design or adopt substitute material, it must apply to the design
unit and handle it according to relevant system.

Alloy-steel pipe, pipe fittings, pipe auxiliaries and valve shall be carried
4 out spectrum recheck piece by piece before using, and make marks for
material

During pressure test of pipe system, the pressure shall be maintained for
10min after reaching test pressure and then drop to design stress;
comprehensive inspection shall be carried out for all joints. There shall
5
not be water seepage or leakage mark on the overall system except
partial places obstruct of pump or valve padding and no deformation by
visual observation.

Access opening must not be opened randomly on the pressure vessel,


pipe seat must not be welded, and repair must not be carried out, as well
6
as pipes must not be used as hanger and support points for hoisting other
heavy things.

Acceptance result

Construction organization:(seal) Supervision organization: (seal)

Project technical director: Supervision engineer:

Date Date

4.26 Construction Identification and approval

4.26.1 Unit project construction Identification and approval for turbine generator main-body
installation.
1 See Table 4.26.1-1 for Identification and approval of platen contact inspection.
Table 4.26.1-1 Identification and approval table of platen contact inspection
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

290
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

The contact surface of platen and bearing pedestal sliding block as well
1
as platen and steam cylinder shall be smooth and clean without rag.

The contact surface of platen and bearing pedestal sliding block as well
2 as platen and steam cylinder shall be tight and inspected with 0.05mm
feeler gauge to prevent wedging.

The contact area of casting platen shall be inspected with red lead
powder or red stamp-pad ink; the area with contact points per sq. cm
3
shall account for over 75% of the total area and shall be distributed
uniformly.

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

2 See Table 4.26.1-2 for Identification and approval table of bearing pedestal oil-filling test
Table 4.26.1-2 Identification and approval table of bearing pedestal oil-filling test
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

291
Confirmation and signature description or sketch map: Oil-filling test shall be carried out on oil chamber of bearing pedestal; it
shall be repaired and tested again when there is leakage during oil-filling test.

SN Inspection item Inspection result

Before oil-filling test, the oil chamber and oil line of bearing pedestal
1
shall be inspected and shall be smooth and clean inside and outside.

The height of kerosene for oil-filling shall be greater than or equal to


2 upper-opening outer wall of scavenge pipe; there shall be no leakage in
oil-filling after 24h.

3 The paint dissolvable in turbine oil has been removed.

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

3 See Table 4.26.1-3 for Identification and approval of bearing pedestal covering
Table 4.26.1-3 Identification and approval table of bearing pedestal covering
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

292
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

The inside of bearing pedestal shall be clean and impurity-free; all


parts shall be completely and correctly installed; the bolt shall be
1 tightened up and locked tightly; the elements of thermal meter shall be
well installed and adjusted; all clearance shall meet the requirement of
drawing (Checking related records)

As for horizontal joint surface of bearing cover and connection area of


oil catch and bearing bush, they shall be tightly contacted; after
2
fastening blot, the joint surfaces shall not be plugged in by 0.03mm
feeler gauge; all joint surface shall be coated with oil-proof sealants.

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

4 See Table 4.26.1-4 for Identification and approval of steam cylinder appearance inspection.
Table 4.26.1-4 Identification and approval table of steam cylinder appearance inspection
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

293
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Appearance inspection on steam cylinder

2 Check of horizontal and vertical joint surface

3 Bolt hole, studding hole

4 Bolt and nut

5 Appearance inspection on bolt hole

6 Top clearance of sheath-type nut and bolt

7 Horizontal integration surface bolt and gap around bolt hole

8 Screw thread out of the nut

9 Spot welding bolt on vertical joint surface

10 Installation of atmospheric relief valve

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

5 See Table 4.26.1-5 for Identification and approval of turbine rotor appearance inspection.

294
Table 4.26.1-5 Identification and approval table of turbine rotor appearance inspection
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

Cleanliness of steam seal, shaft neck, thrust disc, gear wheel, worm gear
1
and coupling

Weight and locking key on wheel hub; center hole closure plate and other
2
locking parts

3 No looseness and damage on rotor blade and double ring

Axial displacement, differential expansion and floating displacement of


4
rotor as well as flange flutter of detection device

5 Rotor tortuosity

6 Axle neck ellipticity

7 Axle-neck non-cylindrical degree

8 Coupling floating displacement

9 Coupling spigot coordination

10 Coupling flange spigot radial flutter

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

295
Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

6 See Table 4.26.1-6 for Identification and approval on inspection and sealing of high and
medium pressure nozzle box
Table 4.26.1-6 Identification and approval table on inspection and sealing of high and medium pressure
nozzle box
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Clean and impurity-free inside

2 All parts are completely and reliably installed

3 The inspection on alloy steel parts meets the requirement of drawing

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

296
Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

7 See Table 4.26.1-7 for Identification and approval of inspection before steam turbine
covering
Table 4.26.1-7 Identification and approval table of inspection before steam turbine covering
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Compressed air purging

2 Protective device and monitoring component inside the steam cylinder

3 Paints required for covering

4 Trial erection of steam cylinder internal component

5 Foundation settlement of steam turbine generator units

High-temperature fasteners hardness; spectrum reinspection on spare parts


6
and pipeline materials of demountable alloy steel inside steam cylinder

Statistics on defects and quality problems as well as sealing conditions


7
within covering range

Construction record, Identification and approval, acceptance and


8
uncompleted items within covering range

9 Serial number and registration of instruments and tools

10 Site civilized construction and site environment

297
11 Various engineering construction schemes, systems and documents

The overhead traveling cranes in turbine house meet the hoisting


12
requirements

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

8 See Table 4.26.1-8 for Identification and approval of steam turbine covering
Table 4.26.1-8 Identification and approval table of steam turbine covering
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

The inside of equipment shall be clean and in good order and condition
1
during covering

2 Impurity-free, with instruments left inside cylinder body

3 The parts is completely and correctly installed

4 High-temperature bolt up

Paint laying at the steam cylinder horizontal joint surface and parts joint
5
surface

6 Temporarily support transformation of lug bracing the inner cylinder

7 Continuity of covering work

8 Rolling rotor after steam turbine covering

298
9 Sealing the opening in time after covering

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

9 See Table 4.26.1-9 for Identification and approval of steam turbine foundation before
secondary grouting
Table 4.26.1-9 Identification and approval table of steam turbine foundation before secondary grouting
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

The secondary grouting scheme and technical disclosure have been


1
completed and shall meet the requirement of DI /T5011

According to the requirements of DL/T 5011, the due work and


2 related record have been completed and shall meet the requirement of
drawing before checking foundation secondary grouting.

The checking of foundation grouting material shall meet the


3 requirement of drawing; the test piece passes the strength test
(providing relevant strength test report)

The rough surface between foundation concrete and secondary


4 grouting layer shall be cleaned by air lancing and free of foreign
bodies, paint and oil stain; the concrete surface shall be soaked for at

299
least 24h.

The platen grouting screw has been correctly installed; the baffle plate
of secondary grouting has been correctly installed and has no effect on
5
expansion; the surface between platen and secondary grouting shall be
cleaned up without paint and oil stain

The spot welding of foundation iron gasket has been completed; the
foundation bolt has been adjusted to the cylinder body and the central
position of stator toe-board foundation bolt hole; the inside of
6
foundation bolt hole has been cleaned up without any impurity; the
foundation bolt subplate and foundation concrete are well contacted to
ensure no motar leakage.

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

10 See Table 4.26.1-10 for Identification and approval on installation and inspection of
communicating pipe.
Table 4.26.1-10 Identification and approval table on installation and inspection of communicating pipe
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

300
1 Cold drawing value of communicating pipe

2 Internal cleanliness inspection before final sealing of communicating pipe

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

11 As for steam port and governing valve disassembling during washing pipe, it shall carry
out tightness inspection after washing pipe. See Table 4.6.1-11 for Identification and approval
on tightness inspection of steam port and governing valve.
Table 4.26.1-11 Identification and approval table (after washing pipe) on tightness inspection of steam port
and governing valve
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval record description:

SN Inspection item Inspection result

The appearance of valve disc and valve seat shall be smooth and clean
1
without scar

2 The valve rod and valve disc acts flexibly without jam

The area between valve disc and valve seat shall be inspected by painting
3 method or scribing pencil marks; the whole ring shall be contacted
continuously and uniform in width

301
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

12 See Table 4.26.1-12 for Identification and approval on inspection of fire resistant oil
system before flashing
Table 4.26.1-12 Identification and approval table on inspection of fire resistant oil system before flashing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval record description:

SN Inspection item Inspection result

The system and temporary measures have been installed and completed;
1
the connection shall be correct and meet the requirement of drawing

2 The oil tank has been sealed

3 The restriction orifice or pore plug have been removed

The electro hydraulic converter has been replaced by temporary flashing


4
block

5 The filter element has be replaced by temporary flashing filter element t

6 The thermal meter has been installed as required

7 The flushing oil meets the requirement and shall be sufficient

8 The valve condition meets the requirement of flashing

The accident oil drainage system is correctly connected; the inside of


9
accident oil drainage well is cleaned up

10 The sand box, fire extinguisher and other fire-fighting tools shall be well

302
prepared

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

13 See Table 4.26.1-13 for Identification and approval on oiliness laboratory examination of
fire-resistant oil after flashing
Table 4.26.1-13 Identification and approval on oiliness laboratory examination of fire-resistant oil after
flashing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval record description:

SN Inspection item Inspection result

Oil sample shall be taken at from filter before scavenge oil, main
1
oil-drainage header pipe or sampling point required by the manufacturer

The oil analysis granularity meets the requirement of the manufacturer or


2
the stipulated requirements

3 The magnetic steel rod shall be clean without any particle

4 The oiliness indicators of fire-resistant oil meets the requirement

303
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

14 See Table 4.26.1-14 for inspection and acceptance on tightness inspection of oil cooler
Table 4.26.1-14 Inspection and acceptance table on tightness inspection of oil cooler
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval record description:

SN Inspection item Inspection result

1 The water for test shall be clean and without any impurity

Measures have been taken to strengthen oil cooler with expansion


2
compensator

Test pressure: test pressure of the manufacturer's nameplate or 1.5 times of


3
operating pressure

4 Pressure stabilization time: 5min

5 Tightness inspection: No leakage

304
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

15 See Table 4.26.1-15 for Identification and approval on oil tank inspection before sealing
Table 4.26.1-15 Identification and approval table on oil tank inspection before sealing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval description:

SN Inspection item Inspection result

1 The internal parts are complete and correct; the fasteners are reliable

2 The opening of oil tank is complete and correct

The inside of oil tank is clean and free from scales and welding slags; the
3 inner surface is undissolvable in paints for turbine oil and without any
falling off; the paints dissolvable in turbine oil have been removed.

305
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

16 See Table 4.26.1-16 for Identification and approval of inspection before lubrication
(sealing) oil flushing
Table 4.26.1-16 Identification and approval table of inspection before lubrication (sealing) oil flushing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval record description:

SN Inspection item Inspection result

The system (including accident oil discharge system) and temporary measures
1 have been installed and completed; the connection shall be correct and meet
requirements of drawing

2 The oil tank has been sealed

3 The restriction orifice or pore plug have been removed

4 The thermal meter has been installed as required

5 The flushing oil meets the requirement and shall be sufficient

The specification of temporary filter screen and the flow area meet the
6
requirement

7 The valve condition meets the requirement of flashing

8 Trial operation of oil pump motor and smoke exhaust fan

306
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

17 See Table for Identification and approval of oiliness inspection after lubrication (sealing)
oil flushing
Table 4.26.1-17 Identification and approval table of oiliness inspection after lubrication (sealing) oil flushing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Identification and approval record description: Oiliness laboratory report shall be provided.

SN Inspection item Inspection result

1 Taking oil sample from sampling points of oil tank and oil cooler

The oil analysis granularity meets the requirement of the manufacturer or


2
reaches grade NAS 7

3 The oiliness indicators of turbine oil meets the requirement

Acceptance result:

Acceptance Quality acceptance opinions Acceptance signature

307
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

18 See Table 4.26.1-18 for Identification and approval of generator rotor tightness test
Table 4.26.1-18 Identification and approval table of generator rotor tightness test
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Pressure test medium

2 Test pressure

3 Test time

4 Pressure drop (air leakage)

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

308
19 See Table 4.26.1-19 for Identification and approval of generator stator tightness test
Table 4.26.1-19 Identification and approval table of generator stator tightness test
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Pressure test medium

2 Test pressure

3 Testing time

4 Tightness

5 Winding insulation resistance (before pressure test)

6 Winding insulation resistance (after pressure test)

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

20 See Table 4.26.1-20 for Identification and approval of generator crossed rotor
Table 4.26.1-20 Identification and approval table of generator crossed rotor
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

309
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Cleaning inspection of stator and rotor

Confirmation on electric, thermal test and erection work before crossing


2
rotor

3 Rotor-crossing process

4 Confirmation on temporary sealing measures after crossing rotor

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

21 See Table 4.26.1-21 for Identification and approval of generator end cap installation and
sealing
Table 4.26.1-21 Identification and approval table of generator end cap installation and sealing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

310
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Internal cleaning inspection before sealing

Confirmation on relevant electric, thermal examination and erection


2
work before sealing

3 Condition confirmation of end-cap flange joint surface

4 Filling sealing gum

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

22 See Table 4.26.1-22 for identification and approval of tightness test on generator hydrogen
cooler
Table 4.26.1-22 Identification and approval table of tightness test on generator hydrogen cooler
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

311
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Test medium inspection

2 Test pressure inspection

3 Inspection on solid compression time

4 Leakage detection

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

23 See Table 4.26.1-23 for Identification and approval table of water pressure test on exciter
air-cooled condenser
Table 4.26.1-23 Identification and approval table of water pressure test on exciter air-cooled condenser
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

312
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Test medium inspection

2 Test pressure inspection

3 Inspection on solid compression time

4 Leakage detection

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

24 See Table 4.26.1-24 for identification and approval of generator complete air pressure test
Table 4.26.1-24 Identification and approval table of generator complete air pressure test
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

313
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Test pressure

2 Continuity test time

3 Air leakage

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

25 See Table 4.26.1-25 for identification and approval table of generator internal cooling
water system flashing
Table 4.26.1-25 Identification and approval table of generator internal cooling water system flashing
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Identification and approval description or sketch map: (Water quality report shall be provided)

314
SN Inspection item Inspection result

1 Purity for rinse water quality of the whole system

2 Electrical conductivity for rinse water quality of the whole system

3 Hardness for rinse water quality of the whole system

4 PH value for rinse water quality of the whole system

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

26 See Table 4.26.1-26 for Identification and approval on appearance quality acceptance of
turbine generator main-body installation unit project.
Table 4.26.1-26 Identification and approval table on appearance quality acceptance of turbine generator
main-body installation unit project
________Unit Project number:
Main body installation of turbine Construction
Unit project name
generator organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


paint shall be uniform and the objects shall be in the natural color
and free from pollution

The mark and label shall be uniform, complete and normative

1 Overall appearance quality The thermal-insulation appearance is in good condition

The pipe below 76 is arrayed reasonably and orderly

The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment
2 No leakage point
and system

315
The material, procedure, thickness and color shall meet the
requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

The surface shall be smooth, without damage and shedding

The rendering coat shall be smooth and without cracks


Thermal-insulation The seaming of heat preservation metal shell shall meet the
5
engineering specification

The overlapping size of insulating layer enclosure in the metal shell


75mm

Matching application, firm connection and corrosion-proof

6 Bolted connection The penetration direction shall be consistent

The exposed screw thread shall be united and meet the specification

The mark shall be striking, united and normative


Equipment and system
7 The label shall be complete, united, clear, hung firmly and without
mark
pollution

Without construction residual

Production area Without water, oil or ash accumulation


8
management The articles shall be stacked regularly and fixed

The doors of cabinets (boxes) shall be closed tightly

Acceptance organization Quality acceptance opinions Signature

Construction organization Date

Supervision organization Date

Development organization Date

4.26.2 Identification and approval on unit project construction of turbine generator auxiliary
device installation
1 See Table 4.26.2-1 for Identification and approval of condenser inspection before crossing
pipe
Table 4.26.2-1 Identification and approval table of condenser inspection before crossing pipe
________Unit Project number:
Subsection project
Unit project name
name

Subitem project
Inspection lot name
name

316
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Acceptance of condenser assembly

2 Separated sealing top condenser and steam cylinder

3 Cooling pipe inspection

4 Cleanness an drag inspection of pipe (separation) plate orifice

Completion condition of opening and welding at cooling pipe


5
installation area

6 Cleanliness inside condenser

7 Cooling pipe fitting

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

2 See Table 4.26.2-2 for Identification and approval on inspection before connection of low
pressure cylinder and condenser
Table 4.26.2-2 Identification and approval table on inspection before connection of low pressure cylinder

317
and condenser
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Centering of low-pressure outer cylinder

2 Longitudinal and lateral level of steam cylinder

3 Space between condenser and steam cylinder

Dimension of upper-opening bent side of condenser into exhaust steam


4
cylinder

5 Contact surface of steam cylinder and platen

The deformation control measures have been implemented during steam


6
cylinder connection

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

318
Manufacturing
Date
organization

Development
Date
organization

3 See Table 4.26.2-3 for Identification and approval of condenser watering test inspection
Table 4.26.2-3 Identification and approval table of condenser watering test inspection
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 The watering height meets the requirement

2 The joint flange of condenser is free of leakage

3 No leakage on cooling water pipes

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction Date

319
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

4 See Table 4.26.2-4 for Identification and approval on hidden inspection of drain flash tank
Table 4.26.2-4 Identification and approval table on hidden inspection of drain flash tank
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 The internal parts (device) is clean and in good condition

2 The inside is clean and impurity -free

320
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

5 See Table 4.26.2-5 for Identification and approval on tightness test of air-cooling system
Table 4.26.2-5 Identification and approval table on tightness test of air-cooling system
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

321
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Whether there is gas leakage on all parts of system

2 Whether the pressure drop of system within 24h meets the requirement

3 There is no leakage during watering (when watering test is adopted)

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

6 See Table 4.26.2-6 for Identification and approval of deaerator (water tank) before main
body sealing
Table 4.26.2-6 Identification and approval table of deaerator (water tank) before main body sealing

322
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name. Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 No omission for working inside tank

2 Internal cleaning

3 The plug and manhole door are tightly sealed

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

323
Development
Date
organization

7 See Table 4.26.2-7 for Identification and approval on water pressure test of heat exchanger
(water side or steam side)
Table 4.26.2-7 Identification and approval table on water pressure test of heat exchanger (water side or
steam side)
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Identification and approval record description:

SN Inspection item Inspection result

1 The water for test shall be clean and without any impurity

Test pressure: test pressure of the manufacturer's nameplate or 1.5 times of


2
operating pressure

3 Specification, measuring range, precision class and number of pressure gage

4 Pressure stabilization time: 10min

5 Tightness inspection: No leakage

6 No deformation on enclosure

7 No leakage at flange connection area and welded joints

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

324
Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

8 See Table 4.26.2-8 for Identification and approval on unit project appearance quality
acceptance of turbine generator auxiliary device installation
Table 4.26.2-8 Identification and approval table for unit project appearance quality acceptance of turbine
generator auxiliary device installation
________Unit Project number:
Construction
Unit project name Turbine generator auxiliary device installation
organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


paint shall be uniform and the objects shall be in the natural color
and free from pollution

The mark and label shall be uniform, complete and normative

1 Overall appearance quality The thermal insulation appearance shall be in good condition

The pipe below 76 is arrayed reasonably and orderly

The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment
2 No leakage point
and system

The material, procedure, thickness and color shall meet the


requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

5 Thermal insulation The surface shall be smooth, without damage and shedding
engineering
The rendering coat shall be smooth and without cracks

The seaming of heat preservation metal shell shall meet the

325
specification

The overlapping size of insulating layer enclosure in the metal shell


75mm

Matching application, firm connection and corrosion-proof

Penetration direction shall be consistent


6 Bolted connection
The exposed screw thread shall be united and meet the
specification

The mark shall be striking, united and normative


Equipment and system
7 The label shall be complete, united, clear, hung firmly and without
mark
pollution

Without construction residual

Production area Without water, oil or ash accumulation


8
management The articles shall be stacked regularly and fixed

The doors of cabinets (boxes) shall be closed tightly

Acceptance organization Quality acceptance opinions Signature

Construction organization Date

Supervision organization Date

Development organization Date

4.26.3 Identification and approval on unit project construction of turbine generator


auxiliaries installation
1 See Table 4.26.3-1 for Identification and approval on driving steam turbine covering of
steam feed pump
Table 4.26.3-1 Identification and approval table on driving steam turbine covering of steam feed pump
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 Cleaning up steam cylinder and steam chamber

326
2 Drainage hole of steam cylinder

3 Cleaning up horizontal joint surface

4 Cleaning up spare parts inside cylinder

5 Trial erection of bolt and nut

6 Installation of spare parts inside cylinder

7 Covering process (carried out continuously without remnant)

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

2 See Table 4.26.3-2 for Identification and approval on water pressure test of pump motor
cooler
Table 4.26.3-2 Identification and approval table on water pressure test of pump motor cooler
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

327
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 No deformation on enclosure

2 No leakage at flange connection area and welded joints

3 Test pressure

4 Testing time

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

3 See Table 4.26.3-3 for unit project appearance quality acceptance Identification and
approval of turbine generator auxiliaries installation
Table 4.26.3-3 Identification and approval table on unit project appearance quality acceptance of turbine

328
generator auxiliaries installation
________Unit Project number:
Construction
Unit project name Installation of turbine generator auxiliaries
organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


paint shall be uniform and the objects shall be in the natural color
and free from pollution

The mark and label shall be uniform, complete and normative

1 Overall appearance quality The thermal insulation appearance shall be in good condition

The pipe below 76 is arrayed reasonably and orderly

The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment and


2 No serious leakage point
system

The material, procedure, thickness and color shall meet the


requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

The surface shall be smooth, without damage and shedding

The rendering coat shall be smooth and without cracks


Thermal insulation The seaming of heat preservation metal shell shall meet the
5
engineering specification

The overlapping size of insulating layer enclosure in the metal


shell 75mm

Matching application, firm connection and corrosion-proof

Penetration direction shall be consistent


6 Bolted connection
The exposed screw thread shall be united and meet the
specification

The mark shall be striking, united and normative


7 Equipment and system mark The label shall be complete, united, clear, hung firmly and without

pollution

329
Without construction residual

Production area Without water, oil or ash accumulation


8
management The articles shall be stacked regularly and fixed

The doors of cabinets (boxes) shall be closed tightly

Acceptance organization Quality acceptance opinions Signature

Construction organization Date

Supervision organization Date

Development organization Date

4.26.4 Unit project construction Identification and approval on other equipment installation
of steam turbine generator units
1 See Table 4.26.4-1 for Identification and approval of bridge cranes load test
Table 4.26.4-1 Identification and approval table of bridge cranes load test
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

During load test, the hook lifting as well as large and small vehicle travelling are
1
stable and free of no jam and strange sound

The brake is sensitive and reliable; the limit switch and interlock protection device
2
operates correctly and reliably

3 There is no crashing on gear case; the bearing temperature is normal

4 Catenary arc of girder during rated static load test

10min after 1.25 times rated static load test, the bridge framework deflection shall
restore to the original state and there is no residual deformation and abnormal
5
phenomena; The rotary hook gape is free of residual deformation; there is no crack on
steel pieces and welded joints

During 1.1 times rated dynamic loading test, the lifting of large and small hook is
6
stable; the steel wire of rotary drum is lined neatly

7 Brake operation inspection

330
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

2 See Table 4.26.4-2 for Identification and approval of ordinary crane load test
Table 4.26.4-2 Identification and approval table of ordinary crane load test
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

During unload test, the hook lifting as well as large and small vehicle
1
travelling are stable and free of no jam and strange sound

2 10min after 1.25 times rated load at 100mm height, the brake shall be reliable

331
in inspection; there shall be no looseness on steel wire and no deformation on
hook

The rated load rises and falls for 15min; the hook lifting and trolley traveling
3 is stable and free of no jam and strange sound; after braking, the gliding
distance of hoisting objects is less than or equal to 50mm

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

3 See Table 4.26.4-3 for Identification and approval for unit project appearance quality
acceptance on other equipment installation of steam turbine generator units
Table 4.26.4-3 Identification and approval table for unit project appearance quality acceptance on other
equipment installation of steam turbine generator units
________Unit Project number:
Other equipment installation of steam Construction
Unit project name
turbine generator units organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


1 Overall appearance quality paint shall be uniform and the objects shall be in the natural color

and free from pollution

The mark and label shall be uniform, complete and normative

The thermal insulation appearance shall be in good condition

The pipe below 76 is arrayed reasonably and orderly

332
The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment and


2 No serious leakage point
system

The material, procedure, thickness and color shall meet the


requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

The surface shall be smooth, without damage and shedding

The seaming of heat preservation metal shell shall meet the


Thermal insulation
5 specification
engineering
The overlapping size of insulating layer enclosure in the metal
shell 75mm

Matching application, firm connection and corrosion-proof

Penetration direction shall be consistent


6 Bolted connection
The exposed screw thread shall be united and meet the
specification

The mark shall be striking, united and normative


Equipment and system
7 The label shall be complete, united, clear, hung firmly and without
mark
pollution

Without construction residual


Production area
8 Without water, oil or ash accumulation
management
The articles shall be stacked regularly and fixed

Acceptance organization Quality acceptance opinions Signature

Construction organization Date

Supervision organization Date

Development organization Date

4.26.5 See Table 4.26.5 for Identification and approval for unit project appearance quality
acceptance on water-circulating pump room equipment, public-water pump house equipment
and water-collecting pump house equipment.
Table 4.26.5 Identification and approval table for unit project appearance quality acceptance on
water-circulating pump room equipment, public-water pump house equipment and water-collecting pump

333
house equipment
________Unit Project number:
Construction
Unit project name
organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


paint shall be uniform and the objects shall be in the natural color
and free from pollution

The mark and label shall be uniform, complete and normative


1 Overall appearance quality
The pipe below 76 is arrayed reasonably and orderly

The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment
2 No serious leakage point
and system

The material, procedure, thickness and color shall meet the


requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

Matching application, firm connection and corrosion-proof

Penetration direction shall be consistent


5 Bolted connection
The exposed screw thread shall be united and meet the
specification

The mark shall be striking, united and normative


Equipment and system
6 The label shall be complete, united, clear, hung firmly and without
mark
pollution

Without construction residual

Production area Without water, oil or ash accumulation


7
management The articles shall be stacked regularly and fixed

The doors of cabinets (boxes) shall be closed tightly

Acceptance organization Quality acceptance opinions Signature

334
Construction organization Date

Supervision organization Date

Development organization Date

4.26.6 Inspection table and construction Identification and approval on the implementation
performance of unit project compulsory provisions for main body installation of combustion
engine
1 See Table 4.26.6-1 for Identification and approval on manhole door sealing inspection at air
inflow area
Table 4.26.6-1 Identification and approval table on manhole door sealing inspection at air inflow area
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

The parts inside air purification and sound deadening system have been
1
well installed and in good condition

The expansion joint connected with inlet chamber has been installed and
2
meets the requirement

The inside of air purification and sound deadening system are clean and
3
free of rust, weld beading and foreign bodies

4 No ray penetrates the inside of air purification and sound deadening system

Statistic list on the quantity of bolts and nuts inside system after fine
5
filtration

6 Insurance of argon arc welding for nuts

7 Nut insurance inspection: 100% insurance has been completed

The parts (excluding fine filtration) inside air purification and sound
8
deadening system have been improved

The air purification and sound deadening system have been connected with
9
expansion joint

10 The inside shall be clean and without rust, weld beading and foreign bodies

335
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

2 See Table 4.26.6-2 for Identification and approval on manhole door sealing inspection at
exhaust area
Table 4.26.6-2 Identification and approval table on manhole door sealing inspection at exhaust area
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 The exhaust system has been well installed and in good condition

The expansion joint connected with exhaust part has been installed and
2
meets the requirement

The inside of exhaust system shall be clean and without rust, weld
3
beading and foreign bodies

336
4 The exhaust system is dark inside and no penetrated ray

The spot welding insurance of argon arc welding for nuts has been
5
completed

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

3 See Table 4.26.6-3 for Identification and approval on enclosure translucidus inspection
Table 4.26.6-3 Identification and approval table on enclosure translucidus inspection
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

337
Confirmation and signature description or sketch map:

SN Inspection item Inspection result

1 The acceptance of enclosure installation has been completed

2 No ray penetrates into the inside of enclosure

Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

4 See Table 4.26.6-4 for Identification and approval on unit project appearance quality
acceptance of combustion engine main-body installation
Table 4.26.6-4 Identification and approval table on unit project appearance quality acceptance of

338
combustion engine main-body installation
________Unit Project number:
Main body installation Construction
Unit project name
of combustion engine organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


paint shall be uniform and the objects shall be in the natural color
and free from pollution

The mark and label shall be uniform, complete and normative

1 Overall appearance quality The thermal insulation appearance shall be in good condition

The pipe below 76 is arrayed reasonably and orderly

The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment
2 No leakage point
and system

The material, procedure, thickness and color shall meet the


requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

The surface shall be smooth, without damage and shedding

The rendering coat shall be smooth and without cracks


Thermal insulation The seaming of heat preservation metal shell shall meet the
5
engineering specification

The overlapping size of insulating layer enclosure in the metal


shell 75mm

Matching application, firm connection and corrosion-proof

Penetration direction shall be consistent


6 Bolted connection
The exposed screw thread shall be united and meet the
specification

The mark shall be striking, united and normative


Equipment and system
7 The label shall be complete, united, clear, hung firmly and without
mark
pollution

8 Production area Without construction residual

339
management Without water, oil or ash accumulation

The articles shall be stacked regularly and fixed

The doors of cabinets (boxes) shall be closed tightly

Acceptance organization Quality acceptance opinions Signature

Construction organization Date

Supervision organization Date

Development organization Date

4.26.7 Unit project construction Identification and approval on installation of combustion


engine auxiliaries and accessory machines
1 See Table 4.26.7-1 for Identification and approval on spraying test of fire extinguishing
system
Table 4.26.7-1 Identification and approval table on spraying test of fire extinguishing system
________Unit Project number:
Subsection project
Unit project name
name

Subitem project name Inspection lot name

Confirmation and signature description or sketch map:

SN Inspection item Inspection result

The pipes of fire extinguishing system have been carried out with
1
strength test

Inspecting nozzle and gas container before spraying test of fire


2
extinguishing system

3 Observing the effects during spraying test of fire extinguishing system

4 Inspecting nozzle after spraying test of fire extinguishing system

340
Acceptance result:

Acceptance
Quality acceptance opinions Acceptance signature
organization

Construction
Date
organization

Supervision
Date
organization

Manufacturing
Date
organization

Development
Date
organization

2 See Table 4.26.7-2 for Identification and approval for unit project appearance quality
acceptance on installation of combustion engine auxiliaries and accessory machines
Table 4.26.7-2 Identification and approval table for unit project appearance quality acceptance on
installation of combustion engine auxiliaries and accessory machines units
________Unit Project number:
Installation of combustion engine Construction
Unit project name
auxiliaries and accessory machines organization

Acceptance result
SN Acceptance item name
Qualified Unqualified

The equipment and structural support shall be firmly installed; the


paint shall be uniform and the objects shall be in the natural color
and free from pollution

The mark and label shall be uniform, complete and normative

1 Overall appearance quality The thermal insulation appearance shall be in good condition

The pipe below 76 is arrayed reasonably and orderly

The platform, stairway and handrail shall be stable and with good
technology

The finished product has excellent protective effects

Tightness of equipment and


2 No leakage point
system

341
The material, procedure, thickness and color shall meet the
requirement of design

3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle

There shall be no bubbles, shedding, rust return and pollution

The weld quality shall meet the requirement of specification

The welded joints shall be uniform, without weld beading and


4 Welding construction residual electrode coating

The welded joints shall be free from deformation; the welded


junction shall be free from welding skip

The surface shall be smooth, without damage and shedding

The seaming of heat preservation metal shell shall meet the


Thermal insulation
5 specification
engineering
The overlapping size of insulating layer enclosure in the metal shell
75mm

Matching application, firm connection and corrosion-proof

6 Bolted connection Penetration direction shall be consistent

The exposed screw thread shall be united and meet the specification

The mark shall be striking, united and normative


Equipment and system
7 The label shall be complete, united, clear, hung firmly and without
mark
pollution

Without construction residual

Production area Without water, oil or ash accumulation


8
management The articles shall be stacked regularly and fixed

The doors of cabinets (boxes) shall be closed tightly

Acceptance organization Quality acceptance opinions Signature

Construction organization Date

Supervision organization Date

Development organization Date

5 Construction Quality Evaluation of Single Project

5.1 Basic requirements

5.1.1 Single project as the civil work, boiler unit, steam turbine generator unit, thermal
meter and its control device, pipe and pipe system, the equipment and the system with the
water treatment and hydrogen generation, welding engineering, processing preparation and
electrical device installation in thermal power generation project shall be evaluated

342
respectively.
5.1.2 Single project as boiler unit, steam turbine generator unit, thermal meter and its
control device, pipe and pipe system, the equipment and the system with the water treatment
and hydrogen generation and processing preparation in thermal power generation project shall
be assessed respectively according to this regulation.
5.1.3 Those project construction organizations engaged in creating high quality project shall
organize the participating organizations to formulate quality objective, conduct objective
management, develop quality planning, highlight corresponding responsibilities, strengthen
process control and intensify quality acceptance in each phase before the commencement of
projects.
5.1.4 Construction organizations to assess and construct single project shall inspect
themselves according to the requirements specified in this Part. Development organizations
shall be responsible for organizing supervision organizations or other assessment
organizations to assess. In addition, the supervision organizations or other assessment
organizations shall summarize and analyze the assessment results and then write assessment
report.
5.1.5 During the assessment of single project, the actual project quality and technical project
information shall be comprehensively inspected.
5.1.6 Construction quality of single project shall be evaluated after all the acceptance of unit
project is qualified.
5.1.7 The construction quality evaluation of this single project shall be carried out
respectively according to main body and sub-system installation of turbine generator,
accessory machinery and auxiliary device in the main power house, accessory machinery and
auxiliary device out of the main power house, pipeline of steam turbine, insulation and
painting of main body (include steam feed pump) equipment piping of steam turbine,
combustion engine and its auxiliary device [six project position (scope) in total].
5.1.8 Each project position (scope) shall be evaluated according to the quality guarantee in
construction site, performance testing, quality records, size deviation and actual limit
measurement, implementation performance of compulsory provision and appearance quality.
Corresponding weighing value of each evaluation project shall be given according to its work
load and importance in this project position (scope).
5.1.9 Each evaluation item shall consist of several kinds of evaluation which shall specify
the standard score according to the importance. During the evaluation of construction quality,
each evaluation is judged as Class I, Class II or Class III which are corresponding to the
standard scores of 100%, 85% and 70% respectively.
5.1.10 During project quality evaluation, attention shall be given to promote scientific
management, strengthen project quality control, improve management mechanism and persist
to improve evaluation competence.
5.1.11 Control of project quality shall highlight material receiving inspection, process
quality control and function effectiveness test so as to improve management efficiency and
operating skills.
5.1.12 During the evaluation of project quality, attention shall be given to apply the advance
of science and technology as well as environmental protection.
5.1.13 The score for the evaluated excellent construction quality of single project shall be

343
greater than or equal to 85 scores; those projects with total score being at last 92 shall be
extremely excellent projects.

5.2 Evaluation provisions

5.2.1 The evaluated weight value of position (range) contained in single project is specified
according to the comprehensiveness of importance, difficulty and work load. Evaluation of
single project position (range) shall be carried out according to those specified in Table 5.2.1.
Table 5.2.1 Distribution Table on the Weight Value of Single Project Position (Range) of Steam Turbine
Generator Units

Weight value

Gas-steam combined
Project position (scope) Conventional fossil
cycle turbine generator Air-cooling unitb
fuel steam power unit
unita

Installation of main body and sub-system of


35 25 35
turbine generator

Accessory machinery and auxiliary device in


25 20 30
main power house

Accessory machinery and auxiliary device out of


15 10 10
main power house

Steam turbine pipe 15 10 15

Steam turbine main body (include steam feed


10 10 10
pump), equipment, pipe insulation and painting

Combustion engine and its auxiliary device 25

Note : If item of project position (scope) was missing in the table, the weight value is distributed according to actual work load
but it shall be integral value.

a The weight value of gas-steam combined cycle turbine generator unit is distributed in the type of "single-axle" configuration.
b For the air-cooling unit, the air-cooling condenser is included in the project position (scope) of accessory machinery and
auxiliary device in main power house

5.2.2 The quality evaluation for each project position (scope) shall be include the quality
guarantee condition in construction site, performance inspection, quality records, size
deviation and actual limit measurement, implementation performance of compulsory
provision and appearance quality.
5.2.3 Weight value of the evaluation item shall be according to those specified in Table
5.2.3.
Table 5.2.3 Distribution Table on the Weight Value of Evaluation Item in Project Position (Scope)
Project position (scope)

Installation Accessory Accessory Steam


of main machinery machinery turbine main Combustion
Number Evaluation item body and and auxiliary and auxiliary Steam body engine and
sub-system device in device out of turbine pipe (include its auxiliary
of turbine main power main power steam feed device
generator house house pump),

344
equipment,
pipe
insulation
and painting

Quality guarantee condition of


1 (15) (15) (15) (15) (15) (15)
construction site

2 Performance inspection (30) (25) (25) (25) (20) (30)

3 Quality records (20) (20) (20) (20) (15) (20)

Size deviation and actual limit


4 (10) (10) (15) (15) (10) (10)
measurement

Implementation performance of
5 (15) (15) (10) (15) (15) (15)
compulsory provision

6 Appearance quality (10) (15) (15) (10) (25) (10)

Note: If there is nonexistent evaluation item in the table, its weight value shall be calculated according to full score.

5.3 Evaluation content

5.3.1 Construction quality of single project shall be evaluated item by item according to the
project position (scope) and evaluation item content of this Part; the construction quality shall
be statistically analyzed basing on the records of random inspection on construction site as
well as the quality acceptance records of each inspection lot, subitem project, subsection
project and unit project; in addition, the construction quality is scored according to project
position (scope) and the requirements specified in evaluation item (corresponding table).
5.3.2 Single project shall not be evaluated to be excellent where there is any of the
following conditions:
1 To use the materials and products which China forbids publically.
2 The obtained score of any project position (scope) or evaluation item is less than 85%
standard score.

5.4 Evaluation methods

5.4.1 Contents and methods to evaluate the quality guarantee condition on construction site
shall meet the following requirements:
1 If the followings can be practically achieved, the quality guarantee on construction site is
Class I and gains 100% standard score: sound quality management, liability system and
project-department organizations; effectively-operated quality management system; perfect
technologies, working management system, site acceptance system and sampling inspection
system of equipments and materials. If sound quality management and liability systems can
be basically achieved, the quality guarantee on construction site is Class II and gains 85%
standard score. And if main quality management and liability systems can be basically
achieved, the quality guarantee on construction site is Class III and gains 70% standard score.
2 The quality guarantee on construction site with standard quality inspection and acceptance
required by projects, standard construction technologies, complete working methods,

345
operation specifications and operational guide books which have strong pertinency and
operability are Class I and gain 100% standard score; the quality guarantee on construction
site with standard and complete quality inspection and acceptance, standard construction
technologies, basically complete operation specifications and operation guide books which
have relatively strong pertinency and operability are Class II and can gain 85% standard score;
and the quality guarantee on construction site with standard and complete quality inspection
and acceptance, standard major construction technologies and complete operation
specifications as well as operation guide books which have general pertinency and operability
are Class III and gain 70% standard score.
3 The quality guarantee on construction site with complete processes to develop and
approve construction management plan, construction scheme, construction measures and risk
prevention measures which have strong pertinency and operability, are seriously implemented
and achieve notable effectiveness is Class I and gains 100% standard score; the quality
guarantee on construction site with complete development and approval processes, relatively
strong pertinency and operability, being basically implemented and achieving preferable
effectiveness is Class II and gain 85% standard score; and the quality guarantee on
construction site with sound development and approval processes, being generally
implemented is Class III and gains 70% standard score.
4 The quality guarantee on construction site with specified quality objective, proper &
effective management system and notable implementation effectiveness is Class I and gains
100% standard score; the quality guarantee on construction site with preferable
implementation effectiveness is Class II and gains 85% standard score; and the quality
guarantee on construction site with general implementation effectiveness is Class III and
gains 70% standard score.
5.4.2 Content and methods to evaluate the performance inspection shall meet the following
requirements:
1 Inspection and test of construction process as well as by-part trial operation shall meet the
requirements specified in relevant standards; the performance inspection provided with
complete and standard test records and reports is Class I and gains 100% standard score;
2 Inspection and test of construction process as well as by-part trial operation shall meet the
requirements specified in relevant standards; the performance inspection provided with
complete and basically standard test records and reports is Class II and gains 85% standard
score;
3 The above test items and test conditions basically meet the requirements specified in
relevant standards; and the performance inspection provided with basically complete test
records and reports is Class III and gains 70% standard score.
4 To sample test records and reports; to measure on site, if necessary.
5.4.3 Content and methods to evaluate the quality records shall meet the following
requirements:
1 Those quality records with material & equipment quality certificates (outgoing quality
certificates), complete site acceptance record, construction record, construction test record,
data; actual and effective content, standard classification & rearrangement, perfect reviewing
and signing procedures and meeting the requirements specified in design and standards are
Class I and gain 100% standard score. Those quality records with complete information,

346
relatively complete data, actual and effective content, relatively standard rearrangement,
relatively complete reviewing and signing procedures and meeting the requirements specified
in design and standards are Class II and gain 85% standard score. Those quality records with
basically complete information, date; actual and effective content; basically standard
rearrangement, basically complete reviewing and signing procedures and basically meeting
the requirements specified in design and standards are Class III and gain 70% standard score.
2 To inspect the quantity and content of information.
5.4.4 Content and methods to evaluate the size deviation and actual limit measurement shall
meet the following requirements:
1 As for those evaluation items, if they are permissible deviation ones; the actual values
measured at each item measuring point reach the ones specified in standard and the actual
values of 80% and more measuring points are less than or equal to 0.8 times the ones
specified in standard, they are Class I and gain 100% standard score. For those evaluation
items, if the actual values of each measuring point reach the ones specified in standard and the
average actual values of greater than 50% (including 50%) but less than 80% measuring
points are less than or equal to 0.8 times the ones specified in standard; they are Class II and
gain 85% standard score. For those evaluation items, if the actual values of each measuring
point reach the ones specified in standard; they are Class III and gain 70% standard score.
2 For those evaluation items, if they are two-way limit items, the actual values measured at
each measuring point meet the ones specified in standard and the actual values of at least 50%
measuring points approximate to the medium limit value; they are Class I and gain 100%
standard score; those evaluation items all of whose actual values at each measuring point are
within the limit specified in standard are Class II and gain 85% standard score; those
evaluation items whose measuring points meet the standard specification after treatment are
Class III and gain 70% standard score.
3 For those evaluation items, if they are one-way limit items and all the actual values at
each measuring point meet the ones specified in standard, they are Class I and gain 100%
standard score; those evaluation items whose measuring points meet the standard speciation
after treatment are Class III and gain 70% standard score.
4 If both permissible deviation and limit are available, the decision value is from the lower
Class.
5 Random 10 inspection lots or subentry project or all lots if they are less than 10 are
sampled from the relevant inspection lots or subitem projects in the category for analyzing
and calculating. If necessary, random measurement on site may be carried out.
5.4.5 Content and methods to evaluate the implementation performance of compulsory
provisions shall meet the following requirements:
1 Those compulsory provisions with detailed implementation plan, comprehensive content,
strong operability, strict implementation and complete inspection records are Class I and gain
100% standard score; those ones with implementation plan, comprehensive content,
preferable operability, preferable implementation and relatively complete inspection records
are Class II and gain 85% standard score; those ones with implementation plan,
comprehensive content, operability, implementation and inspection records are Class III and
gain 70% standard score.
2 To randomly inspect the executive plan, scheme measures, operation guide book,

347
construction record confirmation and signature and inspection records of compulsory
provisions.
5.4.6 Content and methods to evaluate the appearance quality shall meet the following
requirements:
1 The inspection points of each evaluation item are evaluated according to "good",
"ordinary" and "poor". Those evaluation item whose 90% or more inspection points are
"good" and the other inspection points are "ordinary" are Class I and gain 100% standard
score; those evaluation item whose greater than 70% (including 70%) and less than 90%
inspection points are "good" and the other inspection points are "ordinary" are Class II and
gain 85% standard score; those evaluation item whose greater than 30% (including 30% ) and
less than 70% inspection points are "good" and the other inspection points are "ordinary" are
Class III and gain 70% standard score.
2 To observe (to measure, if necessary); to inspect the quality acceptance records of
subsection project and to analyze and calculate.

5.5 Construction quality evaluation for main body and subsystem of turbine

generator

5.5.1 The evaluation method of quality guarantee condition on installation and construction
site of main body and sub-system of turbine generators shall be in accordance with those
specified in 5.4.1; the evaluation contents shall be inspected according to those specified in
Table 5.5.1 and comprehensive judgment shall be carried out.
Table 5.5.1 Evaluation Table on Quality Guarantee Condition for Construction Site
Installation of main body and sub-system of Construction
Project position (scope) Before 168h trial operation in full load
turbine generator stage

Construction Evaluation
organization organization

Evaluation result Re
Numb Deserved Obtaine
Evaluation contents mar
er score 100% 85% 70% d score
ks

Organizational structure and quality


Quality
management system operation in project
management and
department.
1 product liability 30
Technology, management, working system.
system for
Systems for material, equipment site
construction site
acceptance and sampling inspection, etc.

Pertinency and workability of quality inspection and acceptance


2 standard, construction technology standard, working method, 30
operation specifications and operation instructors

Examination and approval of construction organization design,


construction scheme, construction measure, risk aversion
3 20
measure, etc. Pertinency, workability and implementation effect
of contents

348
Implementation effects of quality objective and management
4 20
system

Weight value: 15
Total deserved score:
Evalua Total obtained score:
tion Score of quality guarantee condition on installation and construction site of main body and sub-system of turbine
result generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date

5.5.2 Inspection and evaluation for the installation performance of main body and
sub-system of turbine generators.
1 The contents of inspection and evaluation for installation performance of main body and
sub-system of turbine generators shall be carried out according to Table 5.5.2 and the
comprehensive judgment shall be carried out.
Table 5.5.2 Inspection and Evaluation Table on Performance
Installation of main body and Construction
Project position (scope) Before 168h trial operation in full load
sub-system of turbine generator stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

1 Rating of steam turbine 15

Oil system oiliness of steam turbine-generator unit


2 15
(lubricating oil and EH oil)

3 Cooling water quality of generator stator (rotor) 5

Shafting vibration and bearing temperature of steam


4 20
turbine generator unit

Bear vibration and temperature of rotating equipment


5 for the steam turbine oil system and generator water 5
cooling system

Cylinder expansion, differential expansion and axial


6 10
displacement of rotor

7 Vacuum tightness of steam turbine 15

8 Air test for whole set of generator 10

9 Tightness test for main throttle valve 5

Weight value: 30
Total deserved score:
Total obtained score:
Evaluation
Score of performance inspection for installation engineering of turbine generator main body=obtained score/deserved
result
score*weight value=
Evaluator (signature):
Date

2 Evaluation methods for the installation performance inspection of main body and

349
sub-system of turbine generators are as follows:
1) Rating of steam turbine
It is Class I, if the test value of maximum continuous rating and nominal rating of steam
turbine reaches to 100% contract value; it is rated as Class II, if the test value reaches to95%
(included)~100&; and it is rated as Class III, if the test value is lower than 95%.
2) Oil system oiliness of steam turbine generator unit
It is Class II if the lubricating oil quality reaches NAS7 and the EH quality reaches to NAS5.
It is rated as rated as Class I if any of the item surpasses Class II. It is rated as rated as Class
III if any of the item inferior to Class II.
3) Cooling water quality of generator stator (rotor)
It is Class I if the electrical conductivity 1.5 s/cm during the load on trial operating period;
it is rated as Class II if the electrical conductivity is 1.5s/cm~2s/cm and it is rated as Class
III if the electrical conductivity>2S/cm.
4) Shafting vibration and bearing temperature of steam turbine generator unit
The bearing temperature shall meet the requirements of manufacturer; it is Class I if shafting
vibration 70m; it is rated as Class II if the shafting vibration is 70m~120m and it is rated
as Class III if sampling tube 120m.
5) Bear vibration and temperature of rotating equipment for the steam turbine oil system and
generator water cooling system
The bearing temperature shall meet the requirements of manufacturer; it is Class I if the
vibration (See Annex C) is excellent; it is rated as Class II if the vibration is good and it is
rated as Class III if the vibration is qualified.
6) Cylinder expansion, differential expansion and axial displacement of rotor
The cylinder expansion, differential expansion and rotor axial displacement shall meet the
requirements of drawing; it is rated as Class I if the cylinder expansion is smooth and without
any jam or jump phenomena; it is rated as Class II if the cylinder expansion is poor but can be
smooth and without jam after treatment; it is rated as Class III if the cylinder expansion is
with slightly poor and with jam.
7) Vacuum tightness of steam turbine
Water cooling unit: it is rated as Class I if the tested vacuum value of steam
turbine0.3kPa/min; it is rates as Class II if the test value is 0.3 kPa/min~0.4 kPa/min; and it
is rated as Class III if the test value>0.4kPa/min.
Air-cooling unit: it is rated as Class I if the tested vacuum value of steam turbine0.2kPa/min;
it is rates as Class II if the test value is 0.2 kPa/min~0.3 kPa/min; and it is rated as Class III if
the test value>0.3kPa/min.
8) Air test for whole set of generator
It is rated as Class I if the air leakage of generator is less than or equal to 80% of the value
specified by manufacturer; it is rated as Class II if the air leakage of generator is larger than
80% of the required value but less than required value; and it is rated as Class III if the air
leakage of generator is larger than or equal to required value.
9) Tightness test for main throttle valve
Where the rated steam pressure, normal vacuum and the no load operation of unit, it is rated
as Class I if the speed drop under 800 r/min after the shutdown of main throttle valve; it is
rated as Class II if the speed drop to 800r/min~1000r/min; and it is rated as Class III if the

350
speed drop to higher than 1000r/min.
5.5.3 The recording and evaluation method of installation quality of main body and
sub-system of turbine generators shall be in accordance with those specified in 5.4.3; the
evaluation contents shall be inspected according to those specified in Table 5.5.3 and
comprehensive judgment shall be carried out.
Table 5.5.3 Recording and Evaluation Table on Installation Quality
Installation of main body and Construction
Project position (scope) Before 168h trial operation in full load
sub-system of turbine generator stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

1 Records of material certificate and site acceptance 5

2 Records of equipment certificate and site acceptance 10

3 Monitoring records and report of metal 5

4 Installation records 20

5 Various confirmation and signature 10

Quality acceptance table of inspection lot, subitem,


6 20
subdivision and unit project

7 Trial operation records of single rotating machine 10

Notice letter and registration form of design alteration


8 5
and materials substitutes

Equipment defect notice, equipment defect handling


9 5
report and registration form

10 Registration form of measurement tools 5

Inspection records and correction records of external


11 quality supervision central station before covering steam 5
turbine and the start-up of complete set

Weight value: 20
Total deserved score:
Total obtained score:
Evaluation
Record score of installation engineering quality of main body and sub-system of turbine generators=obtained
result
score/deserved score*weight value=
Evaluator (signature):
Date

5.5.4 Evaluation for the installation dimension deviation and actual limit measurement of
main body and sub-system of turbine generators
1 The evaluation for the size deviation and actual limit measurement of main body and
sub-system of turbine generators shall be carried out according to those specified in Table
5.5.4 and comprehensive judgment shall be carried out.
Table 5.5.4 Evaluation Table on Size Deviation and Actual Limit Measurement

351
Installation of main body and Construction
Project position (scope) Before 168h trial operation in full load
sub-system of turbine generator stage
Construction Evaluation
organization organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

Coupling centre alignment and connection of


1 20
steam turbine generator unit
Flow section gap of the steam turbine (including
2 20
axial location)
3 External gland gap 10
Bearing assembly gap (including thrust pad and
4 15
sealing pad)
5 Load distribution 5

6 Sliding pin system of turbine generators 10

7 Magnetic center and air gap of generator 5

8 Coupling center of auxiliary rotating machine 10

9 Installation position of equipment (device) 5


Weight value: 10
Total deserved score:
Total obtained score:
Evaluation
Score for the size deviation and actual limit measurement of installation engineering of main body and
result
sub-system of turbine generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date
2 The evaluation method for the installation dimension deviation and actual limit
measurement of main body and sub-system of turbine generators shall be in accordance with
those specified in 5.4.4 of this Part. The counting of measuring point number for size
deviation and limit and the provisions of permissible deviation shall comply with the
following:
1) Coupling centre alignment and connection of steam turbine generator unit
The shafting center of steam turbine generator units must meet the requirements. Four points
are set on each pair of couplings and two points on circle deviation and end face opening
respectively. Each datum for the increased flutter of each pair of coupling joint and the
moment or elongation of fastening blot shall be a measuring point according to installation
records.
2) Flow section gap of the steam turbine and external gland gap
The counting of actual measuring point number and permissible deviation shall comply with
the measuring position and state specified by manufacturer.
3) Bearing assembly gap (including sealing pad), load distribution and sliding pin system of
turbine generator
It shall be counted according to measuring points established in Chapter 4 Construction

352
Quality Acceptance Standard; the permissible deviation shall be in accordance with
provisions of manufacturer.
4) Magnetic center and air gap of generator
The counting of actual measuring point number and permissible deviation shall comply with
the requirements of measuring position specified by manufacturer.
5) Coupling center of auxiliary rotating machine
The auxiliary rotating machine includes pump and smoke exhaust fan of oil system and
generator internal cooling water system; the coupling center must meet the requirements of
DL 5011; four points shall be set on each pair of couplings and two points on circle deviation
and end face opening respectively. All the pumps and blowers shall be counted together.
6) Installation position of equipment (device)
Equipments (devices) include turbine generators and hydrogen, oil and water system
equipments (devices); the installation positions include center, elevation, levelness and
verticality; the permissible deviation is determined according to 4 Construction Quality
Acceptance Standard; the measuring point number is the counted point number.
5.5.5 The evaluation method for the management and implementation performance of
installation compulsory provision of main body and sub-system of turbine generators shall be
in accordance with those specified in 5.4.5; the evaluation contents shall be inspected
according to those specified in Table 5.5.5; comprehensive judgment shall be carried out.
Table 5.5.5 Evaluation Table for Management Implementation Performance of Compulsory Provision
Installation of main body and sub-system Construction
Project position (scope) Before 168h trial operation in full load
of turbine generator stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

Compilation condition of implementation plan of


1 25
compulsory provisions

Workability of implementation plan of compulsory


2 15
provisions

Compulsory provisions of this position(system) has been


3 30
implemented entirely

Strictness degree of implementing compulsory provisions


4 15
of this position (system)

Whether records of implementing compulsory provisions


5 15
are complete and meet requirements of specification or not

Weight value: 15
Total deserved score:
Total obtained score:
Evaluation
Score of management and implementation performance of compulsory provision for the installation engineering of
result
main body and sub-system of turbine generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date

5.5.6 Appearance quality evaluation for the installation of main body and sub-system of

353
turbine generators.
1 The appearance quality of main body and sub-system of turbine generators installation
shall be inspected and evaluated according to those specified in Table 5.5.6; comprehensive
judgment shall be carried out.
Table 5.5.6 Evaluation Table on Appearance Quality
Installation of main body and sub-system Construction
Project position (scope) Before 168h trial operation in full load
of turbine generator. stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

1 Equipment appearance 20

Pipe installation technology of hydrogen, oil and water


2 15
system

3 Tightness of equipment and system 15

4 Marks of equipment and system 10

Installation technology of platform, handrail and ladder


5 10
access

6 Installation technology of enclosure and shield 10

7 Painting and insulation 10

8 Regional environment 10

Weight value: 10
Total deserved score:
Total obtained score:
Evaluation
Score of appearance quality for the installation engineering of main body and sub-system of turbine
result
generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date

2 The evaluation methods for the appearance of the installation equipments of main body
and sub-system of turbine generators as well as the evaluation methods for the appearance
quality of pipe installation technology of hydrogen, oil and water system shall comply with
those specified in 5.4.6, and the counting method for the inspection points of evaluation shall
be implemented according to the following requirements:
1) Equipment appearance: Each independent equipment and its structure support are taken as
a evaluation point. It can be evaluated to be "good" if it is installed firmly, and is regular,
reasonable, clean and has no damage or lave.
2) Pipe installation technology of hydrogen, oil and water system: Each independent system
shall be taken as one evaluate point, and the point featured of reasonable pipe arrangement,
esthetic appearance, normative and firm installation of gradient and supporters and hangers,
well installed valves that are convenient for operation, concentrated and regular arrangement
of small diameter pipes with uniform spacing and the same turn radius shall be evaluated to
be "good".

354
3) Tightness of equipments and systems: The equipments and systems which have no leakage
points and the seepage points of which are no more than 3 points are divided as Class I; the
equipments and systems which have no leakage points and seepage points of which are no
more than 8 points are divided into Class II; the equipments and systems which have no
severe leakage points are divided as Class III.
4) Marks of equipment and system: the equipment and system with correct, complete, striking,
unified and normative as well as legibility and firm hanging mark without pollution are Class
I; the equipment and system with correct, basically complete, normative as well as legibility
and firm hanging mark without pollution are Class II; the equipment and system with correct,
basically complete and firm hanging mark are Class III.
5) Installation technology of platform, handrail and ladder access: platform, handrail and
ladder access with firm installation, smooth surface, intact coating, straight and even
horizontal pole, vertical pole, uniform spacing and height meeting the requirements, firm
welding, qualified weld appearance quality, skirting board, access ladder and safety cage
meeting the requirements are Class I; the ones with firm installation, basically reaching
smooth surface, intact coating and height meeting the requirements, firm welding, qualified
weld appearance quality, skirting board, access ladder and safety cage meeting the
requirements are Class II; the ones with firm installation and height meeting the requirements,
firm welding, skirting board, access ladder and safety cage meeting the requirements are
Class III.
6) Installation technology of enclosures and shields: the closure and shield with correct
installation position and free from knocking with rotary position, not influencing expansion,
with complete bolts, straight and even framework and panel, firm without deformation, tight
joint, regular installation, esthetic appearance, rustless and without scar are Class I; the ones
with correct installation position and free from knocking with rotary position, not influencing
expansion, with complete bolts, basically straight and even framework and panel, firm
without deformation and with regular installation are Class II; the ones with correct
installation position and free from knocking with rotary position, not influencing expansion,
with complete bolts and firmly installed framework and panel are Class III.
7) Painting and insulation: provided that the thickness and color of paint meet the design and
the paint color is matched harmoniously, the color and luster are uniform without flow mark,
wrinkle, gas bubble, shedding, rust and contamination; the insulation does not affect the
expansion, the surface is smooth without damage and shedding, the rendering coat is round
and smooth without cracks, the seaming of and metal enclosure meets the requirements and
the technique is of esthetic appearance, the point shall be classified into Class I; provided that
the paint thickness and color meet the design, the color and luster are basically uniform
without flow mark, wrinkle, gas bubble, shedding and rust; and the insulation does not affect
the expansion, the surface is smooth with damage and shedding, the rendering coat is
basically round and smooth without crack, and the seaming of metal shell meets the
requirements, the point shall be classified into Class II; provided that the paint thickness and
color meet the design, the color and luster are uniform basically; and the insulation does not
affect the expansion, the surface is basically flat and smooth, the rendering coat is basically
round and smooth and the seaming of metal shell meets the requirements, the point shall be
classified into Class III.

355
8) Regional environment: The trial operation area without oil, water or ash accumulation and
the articles with regular stacking and fixed management without sanitation dead angle is Class
I; the trial operation area without oil and water as well as ash accumulation and the articles
with regular stacking without waste stacking is Class II; the trial operation area basically
without oil and water as well as ash accumulation and the articles with basically regular
stacking is Class III.

5.6 Evaluation on installation and construction quality of accessory machinery

and auxiliary device in main power house

5.6.1 The method to evaluate the quality guarantee condition on installation and
construction site of accessory machinery and auxiliary device in main power house shall be in
accordance with those specified in 5.4.1; the evaluation contents shall be inspected according
to Table 5.5.1 and the comprehensive judgment shall be carried out.
5.6.2 Inspection and evaluation on the installation performance of the accessory machinery
and auxiliary device in the main power house.
1 The inspection and evaluation for the installation performance of accessory machinery
and auxiliary device in main power house shall be carried out according to those specified in
Table 5.6.2 and comprehensive judgment shall be carried out.
Table 5.6.2 Evaluation Table on Performance Inspection
Installation of accessory machinery and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device in main power house stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

1 Pump performance and capacity 25

2 Bear vibration and temperature of rotating equipment 20

Oil system oiliness of feed pump group (lubricating oil and


3 20
fire resistant oil)

4 Vacuum value of condenser 15

5 Setting of safety valve 10

6 Ball back ration of rubber ball cleaning system 5

7 Crane performance 5

Weight value: 25
Total deserved score:
Total obtained score:
Evaluation
Inspection score for the installation performance of accessory machinery and auxiliary device in main power
result
house=obtained score/deserved score*weight value=
Evaluator (signature):
Date

2 Inspection and evaluation methods for the installation performance of accessory

356
machinery and auxiliary device in main power house are as following.
1) Pump performance and capacity:
Provided that the performance and the volume test value of all the pumps reach to 100%
requirements of unit operation and design, it is Class I; the performance and volume test value
of main pump (condensate pump, electrically driven feed pump group, steam feed pump unit
and vacuum pump) reach to 100% requirements of unit operation and design, but the
performance and volume test value of other pumps reaching to 95% requirements of unit
operation and design, it is Class II; the performance and volume test value of main pump
(condensate pump, electrically driven feed pump group, steam feed pump unit and vacuum
pump) reach to 100% requirements of unit operation and design, but the performance and
volume test value of other pumps reaching to 90% requirements of unit operation and design,
it is Class III.
2) Bear vibration and temperature of rotating equipment:
All the bearing temperatures shall meet the requirements of manufacturer; the grease
lubricated bearing is generally not exceed 80 and the oiled bearing is generally not exceed
65~70. If the vibration (See Annex C) is excellent, it is Class I; if the vibration is good, it
is Class II; if the vibration is qualified, it is Class III.
3) Oil system oiliness of feed pump group (lubricating oil and pilot oil):
If the lubricating oil quality reaches to NAS7 and the pilot oil quality reaches to NAS5, it is
Class II; if any item is surpass Class II, it is rated as Class I; and if any item inferior to Class
II, it is rated as Class III.
4) Condenser vacuum:
At the full load of unit, if the condenser vacuum value meets the design value, it is Class I; if
the design value is 3kPa lower than design value, it is Class II; if the design value is 5kPa
lower than design value, it is Class III.
5) Setting of safety valve:
If the safety valve is tight and without leakage after the setting, the popping pressure meets
the design requirements, the re-seating pressure difference is less than 5% of popping pressure
and the data are complete, it is Class I; if the re-seating pressure difference is 5%~7% of the
popping pressure, it is Class II; and if the re-seating pressure difference is 7%~10% of the
popping pressure, it is Class III.
6) Ball back ration of rubber ball cleaning system:
If the recovery rate of rubber ball is 95% or higher, it is Class I; if the recovery rate of rubber
ball is between 90%~95%, it is Class II; and if the recovery rate of rubber ball is lower than
90%, it is Class III.
7) Crane performance:
It is Class I if all the parameters and indexes of crane performance meet the design
requirements safety license of the special equipments is obtained, the usage of crane is normal
and maintenance is perfect; it is Class II if the usage of crane is normal and maintenance is
good. It is Class III if the usage of crane is basically normal and maintenance is general.
5.6.3 The recording and evaluation method for the installation quality of accessory
machinery and auxiliary device in main power house shall be in accordance with those
specified in 5.4.3 of this Part; the evaluation contents shall be inspected according to those
specified in 5.6.3 and comprehensive judgment shall be carried out.

357
Table 5.6.3 Recording and Evaluation Table on Quality
Installation of accessory machinery and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device in main power house stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

1 Material certificate and site acceptance record 5

2 Equipment certificate and site acceptance record 10

3 Monitoring records and report of metal 5

4 Installation record 15

5 Various confirmation and signature 15

Quality acceptance table of inspection lot, subitem,


6 15
subdivision and unit project

7 Trial operation records of single rotating machine 20

Notice letter and registration form of design alteration


8 5
and materials substitutes

Equipment defect notice, equipment defect handling


9 5
report and registration form

10 Registration form of measurement tools 5

Weight value: 20
Total deserved score:
Total obtained score:
Evaluation
Record score for installation quality of accessory machinery and auxiliary device in main power house=obtained
result
score/deserved score*weight value=
Evaluator (signature):
Date

5.6.4 Evaluation for the installation dimension deviation and actual limit measurement of
accessory machinery and auxiliary device in main power house
1 The evaluation for the installation dimension deviation and actual limit measurement of
accessory machinery and auxiliary device in main power house is listed as water-cooled
condenser and air-cooling unit. The evaluation for the installation dimension deviation and
actual limit measurement of water cooling accessory machinery and auxiliary device in main
power house shall be carried out according to those specified in Table 5.6.4-1, and the
comprehensive judgment shall be carried out.
Table 5.6.4-1 Evaluation Table on Dimension Deviation and Actual Limit Measurement
Installation of accessory machinery
Construction
Project position (scope) and auxiliary device in main power Before 168h trial operation in full load
stage
house

Evaluation
Construction organization
organization

Number Evaluation contents Deserved Evaluation result Obtained Remarks

358
score 100% 85% 70% score

1 Coupling center of rotating machine 25

2 Installation position of equipment (device) 20

Flow passage part gap and external gland gap of feed


3 10
pump driving steam turbine

4 Sliding pin system of feed pump driving steam turbine 10

5 Bearing assembly gap 15

6 Installation dimension of condenser 10

7 Installation dimension of overhead traveling crane 10

Weight value: 10
Total deserved score:
Evaluation Total obtained score:
result Score for the dimension deviation and actual limit measurement of installation engineering of accessory machinery
and auxiliary device in main power house=obtained score/deserved score*weight value=Evaluator (signature):
Date

2 The evaluation method for the installation dimension deviation and actual limit
measurement of water-cooled condenser accessory machinery and auxiliary device in main
power house shall be in accordance with those specified in 5.4.4. The dimension deviation,
counting number of limits and the permissible deviation provisions shall comply with
following.
1) Coupling center of rotating machine:
The rotating machine includes every kind of pump and blower in main power house; the
coupling center must meet the requirements of DL 5011; four points shall be set on each pair
of couplings and two points on circle deviation and end face opening respectively; all the
pumps and blowers shall be counted together.
2) Installation position of equipment (device):
The equipment (device) shall include all accessory machines and auxiliary devices in main
building; the installation positions shall include center, elevation, levelness and verticality; the
permissible deviation shall be determined according to Construction Quality Acceptance
Standard; the measuring point number shall be taken as the counting point.
3) Flow passage part gap and external gland gap of feed pump driving steam turbine:
The count of actual measuring point number and permissible deviation shall comply with the
measuring position and state specified by manufacturer.
4) Sliding pin system of feed pump driving steam turbine:
It shall be counted according to measuring points established in Construction Quality
Acceptance Standard; the permissible deviation shall be in accordance with provisions of
manufacturer.
5) Bearing assembly gap:
The assembly clearance of sliding bearing shall include bushing clearance and bushing
tightening force; the assembly clearance of rolling bearing shall include bearing and enclosure
clearance as well as axial clearance of bearing capping and bearing; each data shall be taken
as one measuring point according to installation records.
6) Installation dimension of condenser:

359
The installation dimension of condenser specially refer to the verticality of pipe plate and
clapboard to base plate and the relative misalignment direction of conduit orifice center line;
the four measuring points for verticality on each pipe plate (clapboard) shall be four
measuring points for dimension and the relative misalignment values of four conduit orifice
measuring center line shall be taken from each pipe plate (clapboard) as four measuring
points for dimension.
7) Installation dimension of overhead traveling crane:
Each datum as rail dimension, main beam dimension, trolley span dimension and trundle span
shall be taken as one measuring point according to installation records.
3 The evaluation for the installation dimension deviation and actual limit measurement of
machinery and auxiliary device of air-cooling condenser accessory in main power house shall
be carried out according to those specified in Table 5.6.4-2 and comprehensive judgment shall
be carried out.
Table 5.6.4-2 Evaluation Table on Dimension Deviation and Actual Limit Measurement
Installation of accessory machinery
Construction
Project position (scope) and auxiliary device in main power Before 168h trial operation in full load
stage
house

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


Number Evaluation contents Remarks
score 100% 85% 70% score

1 Coupling center of rotating machine 20

2 Installation position of equipment (device) 20

Flow passage part gap and external gland gap of feed


3 10
pump driving steam turbine

4 Sliding pin system of feed pump driving steam turbine 10

5 Bearing assembly gap of feed pump group 10

6 Installation dimension of air-cooling condenser 20

7 Installation dimension of overhead traveling crane 10

Weight value: 10
Total deserved score:
Evaluation Total obtained score:
result Score for the dimension deviation and actual limit measurement of installation engineering of accessory machinery
and auxiliary device in main power house=obtained score/deserved score*weight value=Evaluator (signature):
Date

4 The evaluation method for the installation dimension deviation and actual limit
measurement of accessory machinery and auxiliary device of air-cooling condenser in main
power house shall be in accordance with those specified in 5.4.4; refer to relevant contents in
Table 5.6.4-1 for the requirements for No. 1, 2, 3, 4, 5, 6 and 7 inspection items in Table
5.6.4-2. For the No. 6 inspection item, the evaluation method for the installation dimension
deviation and actual limit measurement of air-cooling condenser shall be in accordance with
those specified in 5.4.4. The counting of point number and permissible deviation provisions

360
shall comply with followings:
Each datum as pillar space of air-cooling condenser, center slanting stitch of pillar, height
error on one supporting area of steel platform, condensing tube bundle position, "A" shape
structure position, levelness of blower wheel hub, diameter of blower fan drum, installation
angle of fan blade, gap between fan blade and fan drum shall be a measuring point according
to installation records.
5.6.5 The evaluation method for the management and implementation performance of
compulsory provision for the installation of accessory machinery and auxiliary device in main
power house shall be in accordance with those specified in 5.4.5. The evaluation shall be
carried out according to Table 5.5.5 and comprehensive judgment shall be carried out.
5.6.6 Evaluation for the appearance quality of accessory machinery and auxiliary device in
main power house
1 The evaluation on appearance quality of accessory machines and auxiliary devices in
main power house shall be carried out according to the content specified in Table 5.6.6 and
comprehensive judgment shall be carried out.
Table 5.6.6 Evaluation Table on Appearance Quality
Installation of accessory machines and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary devices in main building stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


SN Evaluation content
score 100% 85% 70% score Remarks

1 Equipment appearance 20

2 Pipe installation technology of oil system 15

3 Equipment and system tightness 15

4 Equipment and system mark 10

Installation technology of platform, handrail and ladder


5 10
access

6 Installation technology of enclosure and shield 10

7 Painting and insulation 10

8 Regional environment 10

Weight value: 15
Total deserved score:
Total obtained score:
Evaluation
Installation appearance quality score of accessory machines and auxiliary devices in main power house=obtained
result
score/deserved score weight value =
Evaluator (signature):
Date

2 Appearance quality evaluation method for the installation equipment appearance of


the accessory machines and the auxiliary devices in the main building and the installation
process of the oil system pipes shall meet the provisions specified in 5.4.6 of this part. The
counting method for the inspection point of the evaluation shall be implemented according to

361
the following methods.
1) Equipment appearance: Each independent equipment and its structure support
shall be taken as an evaluation point, and the point which is firmly installed,
regular, reasonable and clean without damage and remains shall be evaluated as
"good".
2) Installation technology of oil system pipes: each independent system shall be
taken as one evaluation point, and the point featured of reasonable pipe
arrangement, esthetic appearance, normative and firm installation of gradient
and supporter and hangers, well installed valves that are convenient for
operation, concentrated and regular arrangement of small diameter pipes with
uniform spacing and the same turn radius shall be evaluated to be "good".
3) Tightness of equipments and systems: the equipments and systems without
leakage points and the seepage points less than 3 are Class I; the ones without
leakage points and seepage points less than 8 are Class II; the ones without
severe leakage points are Class III.
4) Equipment and system: the equipment and system with correct, complete,
striking, unified and normative as well as legibility and firm hanging mark
without pollution are Class I; the equipment and system with correct, basically
complete, normative as well as legibility and firm hanging mark without
pollution are Class II; the equipment and system with correct, basically
complete and firm hanging mark are Class III.
5) Installation technology of platform, handrail and staircase: platform, handrail
and staircase with firm installation, smooth surface, intact coating, straight and
even horizontal pole, vertical pole, uniform spacing and height meeting the
requirements, firm welding, qualified weld appearance quality, skirting board,
access ladder and safety cage meeting the requirements are Class I; the ones
with firm installation, basically reaching smooth surface, intact coating and
height meeting the requirements, firm welding, qualified weld appearance
quality, skirting board, access ladder and safety cage meeting the requirements
are Class II; the ones with firm installation and height meeting the requirements,
firm welding, skirting board, access ladder and safety cage meeting the
requirements are Class III.
6) Installation technology of enclosures and shields: the closure and shield with
correct installation position and free from knocking with rotary position, not
influencing expansion, with complete bolts, straight and even framework and
panel, firm without deformation, tight joint, regular installation, esthetic
appearance, rustless and without scar are Class I; the ones with correct
installation position and free from knocking with rotary position, not
influencing expansion, with complete bolts, basically straight and even
framework and panel, firm without deformation and with regular installation
are Class II; the ones with correct installation position and free from knocking
with rotary position, not influencing expansion, with complete bolts and firmly
installed framework and panel are Class III.
7) Painting and thermal insulation: the painting with thickness and color meeting

362
design, color matching coordination, consistent and uniform tincture without
flow mark, wrinkle, bubble, shedding, return rust and pollution; the thermal
insulation with smooth surface without damage or shedding and the seaming of
metal enclosure meeting the requirements as well as esthetic technology are
Class I; the painting with thickness and color meeting design, basically
consistent tincture, uniform, basically without flow mark, wrinkle, bubble,
shedding or return rust; the thermal insulation with smooth surface without
damage or shedding and the seaming of metal enclosure meeting the
requirements are Class II; the painting with thickness and color meeting design,
basically consistent tincture; the thermal insulation with basically smooth
surface and the seaming of metal enclosure meeting the requirements are Class
III.
8) Regional environment: the trial operation area without oil and water as well as
ash accumulation and sanitation dead angles, articles are stacked regularly with
fixed management is Class I; the trial operation area without oil and water as
well as ash accumulation, articles are stacked regularly without sanitary fill is
Class II; the trial operation area without oil and water as well as ash
accumulation and sanitation dead angles, articles are stacked basically regularly
is Class III.

5.7 Evaluation on Installation and Construction Quality of Accessory Machines and


Auxiliary Equipments outside the Main Building

5.7.1 The evaluation methods on construction site quality guarantee condition for
installation of the accessory machines and auxiliary devices outside main building shall meet
the provisions specified in 5.4.1. The evaluation contents shall be inspected referring to those
specified in Table 5.5.1 and shall be comprehensively judged.
5.7.2 Evaluation on the performance inspection for installation of the accessory machines
and auxiliary devices outside the main building.
1 The evaluation on performance inspection for installation of the accessory machines
and auxiliary devices outside the main building shall be inspected, evaluated and judged
comprehensively according to the provisions specified in Table 5.7.2
Table 5.7.2 Evaluation Table of Performance Inspection
Accessory machine and auxiliary
Construction
Project position (scope) device installation outside the main Before 168h trial operation in full load
stage
building

Evaluation
Construction organization
organization

Deserved Evaluation results Obtained


Evaluation content Remarks
score 100% 85% 70% score

1 Performance of major equipment 40

Bearing temperature and vibration of the rotating


2 25
equipment

363
3 Outlet butterfly valve and control device 10

4 Crane performance 10

5 Service performance of steel gate 10

6 Noise 5

Weight value: 25
Total deserved score:
Total obtained score:
Evaluation
Score of performance inspection for installation of accessory machines and auxiliary device outside the main
result
building =obtained score/deserved score* weight value=
Evaluator (signature):
Date

2 The evaluation methods on the performance inspection for installation of accessory


machines and auxiliary devices outside the main building are as follows:
1) Performance of the main equipments
Major equipments shall include all the series of pumps, water purifying plant,
rotary filter screen and trash remover. If the performance of all series of the
pumps and the water purifying plant meets 100% of the operation of the unit
and the design requirements, the rotary filter screen and trash remover run
normally, it is Class I; if the performance of water circulating pump, industrial
water pump, fire pump, water intaking pump and rain pump meets 100% of the
operation of the unit and the design requirements, the performance of other
pumps reaches 90% of the operation of the unit and the design requirements,
water purifying plant, rotary filter screen and the trash remover equipments run
basically normally, it is Class II; if the performance of water circulating pump
and fire pump meets 100% of the operation of the unit and the design
requirements, the performance of other pumps reaches 90% of the operation of
the unit and the design requirements, water purifying plant, rotary filter screen
and trash remover equipments run basically normally, it is Class III.
2) Bearing temperature and vibration of the rotating equipment
Bearing temperature shall meet the requirements of manufacturer: the greased
bearing temperature generally shall not exceed 80, and the oiled bearing
temperature shall not exceed 65~70. The vibration is detailed in Annex C;
the excellent vibration is Class I; the good vibration is Class II; the qualified
vibration is Class III.
3) Outlet butterfly valve and control device
It is Class I if the linkage of pump valve meets the requirements of
manufacturer with normal and flexible actions.
4) Performance of the crane
It is Class I if all the parameter indices of the crane performance meet the
design requirements; the safety license of the special equipments is obtained;
normally used and well-maintained. It is Class II if the crane is normally used
and maintained better. It is Class III if it is used normally basically and
maintained generally.

364
5)
Steel gate
The steel gate with service performance meeting the requirements of
manufacturer, normal and flexible actions as well as tight waterstop is Class I.
6) Noise
Noise meeting the design value is Class I; the one without exceeding 10% of
the design value is Class II; one beyond the design value by 10% is Class III.
5.7.3 The evaluation method for quality record of installation of accessory machines and
auxiliary devices outside main building shall be in accordance with those specified in 5.4.3;
the evaluation contents shall be inspected according to those specified in Table 5.7.3 and shall
be comprehensively judged.
Table 5.7.3 Evaluation Table of Quality Record
Installation of accessory machine and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device outside main building stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


SN Evaluation content Remarks
score 100% 85% 70% score

1 Material certificate and site acceptance record 10

2 Equipment certificate and site acceptance record 10

3 Installation record 15

4 Various confirmation and signature 10

Quality acceptance table of inspection batch, subitem,


5 20
subdivision and unit project

6 Trial operation records of single rotating machine 20

Notice letter and registration form of design alteration


7 5
and material substitutes

Equipment defect notice, equipment defect handling


8 5
report and registration form

9 Registration form of measurement tools 5

Weight value: 15
Total deserved score:
Total obtained score:
Evaluation
Quality record score for installation of accessory machines and auxiliary devices outside main building=obtained
result
score/deserved scoreweight value =
Evaluator (signature):
Date

5.7.4 Evaluation on size deviation and actual limit measurement for installation of accessory
machines and auxiliary devices outside main building.
1 The evaluation for the size deviation and actual limit measurement of installation of
accessory machines and auxiliary devices outside main building shall be inspected according
to those specified in Table 5.7.4 and shall be comprehensively judged.
Table 5.7.4 Evaluation Table of Size Deviation and Actual Limit Measurement
Project position (scope) Installation of accessory machine and Construction Before 168h trial operation in full load

365
auxiliary device outside main building stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


SN Evaluation content Remarks
score 100% 85% 70% score

1 Coupling center of rotating machine 25

2 Installation position of equipment (device) 30

3 Assembly clearance of pump bearing 15

4 Waggling of long-axis vertical pump shaft 10

5 Installation dimension of overhead traveling crane 10

Installation dimension of steel gate and guide rail of


6 10
rotary filter screen

Weight value: 15
Total obtained score:
Total obtained score:
Evaluation
score of size deviation and actual limit measurement for installation project of accessory machines and auxiliary
result
devices outside main building=obtained score /deserved scoreweight value=

Date

2 The evaluation methods for size deviation and actual limit measurement of
installation of accessory machines and auxiliary devices outside main building shall meet
those specified in 5.4.4; the point statistics and permissible deviation of size deviation and
limit shall be implemented according to the following.
1) Coupling center of rotating machine:
The rotating machine shall include every kind of pump outside main building;
the coupling center must meet the requirements of "permissible deviation value
of accessory machine centering" as detailed in Annex D; each pair of couplings
shall be installed with four points, and the surrounding deviation and end
surface opening shall be two points respectively; all pumps shall be
summarized with statistics.
2) Installation position of equipment (device):
The equipment (device) shall include all accessory machines and auxiliary
devices outside main building; the installation positions shall include center,
elevation, levelness and verticality; the permissible deviation shall be
determined according to acceptance standard of construction quality; the
measuring point number shall be taken as the statistics point.
3) Assembly clearance of pump bearing:
The assembly clearance of sliding bearing shall include bushing clearance and
bushing tightening force; the assembly clearance of rolling bearing shall
include bearing and enclosure clearance as well as axial clearance of bearing
capping and bearing; each data shall be taken as one measuring point according
to installation records.
4) Waggling of long-axis vertical pump shaft:

366
The waggling measurement of long-axis vertical pump shaft shall be carried out
according to the requirements of manufacturer and DL 5011, and each data
shall be taken as one measuring point according to installation records.
5) Installation dimension of overhead traveling crane
Each data as rail dimension, main beam dimension, trolley span dimension and
trundle span shall be taken as one measuring point according to installation
records.
6) Installation dimension of steel gate and guide rail of rotary filter screen:
Each data as installation dimension of steel gate and guide rail of rotary filter
screen shall be taken as one measuring point according to installation records.
5.7.5 The evaluation method for the management and implementation performance of
compulsory provisions for installation of accessory machines and auxiliary devices outside
main building shall be in accordance with those specified in 5.4.5; the evaluation contents
shall be inspected and evaluated according to those specified in Table 5.5.5 and shall be
comprehensively judged.
5.7.6 Evaluation on appearance quality of accessory machines and auxiliary devices outside
main building
1 The evaluation on appearance quality of accessory machines and auxiliary devices
outside main building shall be inspected and evaluated according to the content specified in
Table 5.7.6 and shall be comprehensively judged.
Table 5.7.6 Evaluation Table of Appearance Quality
Installation of accessory machine and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device outside main building stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


SN Evaluation content Remarks
score 100% 85% 70% score

1 Equipment appearance 20

2 Auxiliary pipe installation technology of equipment 10

3 Tightness of equipment and system 15

4 Marks of equipment and system 10

Installation technology of platform, handrail and


5 15
ladder access

6 Installation technology of shield 10

7 Painting and thermal insulation 10

8 Regional environment 10

Weight value: 15
Total deserved score:
Evaluation Total obtained score:
result Score of appearance quality for installation of accessory machines and auxiliary devices outside main
building=obtained score /deserved scoreweight value=
Evaluator (signature):

367
Date

2 The evaluation methods for the appearance of the installation equipments of


accessory machines and auxiliary devices outside main building as well as the appearance
quality of installation technology of auxiliary pipe of equipment shall comply with those
specified in 5.4.6, and the counting method for the inspection points of evaluation shall be
implemented according to the following requirements.
1) Equipment appearance: each independent equipment and its framework and
bracket shall be taken as one evaluation point, and the regular, reasonable and
clean point that is firmly installed without damage or remnant shall be
evaluated to be "good".
2) Installation technology of auxiliary pipe of equipment: each independent
system shall be taken as one evaluate point, and the point featured of
reasonable pipe arrangement, esthetic appearance, correct gradient, good and
firm installation of supporters and hangers, well installed valves that are
convenient for operation, concentrated and regular arrangement of small
diameter pipes with uniform interval and same turn radius shall be evaluated to
be "good".
3) Equipment and system tightness: equipment and system without leakage point
and seepage points no larger than 5 are Class I; equipment and system without
leakage point and seepage points no larger than 10 are Class II; equipment and
system without severe leakage points are Class III.
4) Equipment and system: the equipment and system with correct, complete,
striking, unified and normative as well as legibility and firm hanging mark
without pollution are Class I; the equipment and system with correct, basically
complete, normative as well as legibility and firm hanging mark without
pollution are Class II; the equipment and system with correct, basically
complete and firm hanging mark are Class III.
5) Installation technology of platform, handrail and ladder access: platform,
handrail and ladder access with firm installation, smooth surface, intact coating,
straight and even horizontal pole, vertical pole, uniform spacing and height
meeting the requirements, firm welding, qualified weld appearance quality,
skirting board, access ladder and safety cage meeting the requirements are
Class I; the ones with firm installation, basically reaching smooth surface,
intact coating and height meeting the requirements, firm welding, qualified
weld appearance quality, skirting board, access ladder and safety cage meeting
the requirements are Class II; the ones with firm installation and height meeting
the requirements, firm welding, skirting board, access ladder and safety cage
meeting the requirements are Class III.
6) Installation technology of shield: the shield with correct installation position

368
and free from knocking with rotary position, not influencing expansion, with
complete bolts, straight and even as framework and panel, firm without
deformation, tight joint, regular installation, esthetic appearance, rustless and
without scar is Class I; the one with correct installation position and free from
knocking with rotary position, not influencing expansion, with complete bolts,
basically straight and even framework and panel, firm without deformation and
with regular installation is Class II; the one with correct installation position
and free from knocking with rotary position, not influencing expansion, with
complete bolts and firmly installed framework and panel is Class III.
7) Painting and thermal insulation: the painting with thickness and color meeting
design, color matching coordination, consistent and uniform tincture without
flow mark, wrinkle, bubble, shedding, return rust and pollution; the thermal
insulation with smooth surface without damage or shedding and the seaming of
metal enclosure meeting the requirements as well as esthetic technology are
Class I; the painting with thickness and color meeting design, basically
consistent tincture, uniform, basically without flow mark, wrinkle, bubble,
shedding or return rust; the thermal insulation with smooth surface without
damage or shedding and the seaming of metal enclosure meeting the
requirements are Class II; the painting with thickness and color meeting design,
basically consistent tincture; the thermal insulation with basically smooth
surface and the seaming of metal enclosure meeting the requirements are Class
III.
8) Regional environment: the trial operation area without oil and water as well as
ash accumulation and the articles with regular stacking and fixed management
without sanitation dead angle is Class I; the trial operation area without oil and
water as well as ash accumulation and the articles with regular stacking without
waste stacking is Class II; the trial operation area basically without oil and
water as well as ash accumulation and the articles with basically regular
stacking is Class III.

5.8 Evaluation on Pipe Installation Quality of Steam Turbine

5.8.1 The evaluation method of quality assurance condition of construction site of steam
turbine pipe shall meet those specified in 5.4.1; the evaluation content shall be inspected
referring to those specified in Table 5.5.1 and shall be comprehensively judged.
5.8.2 Evaluation on performance inspection for installation of steam turbine pipe.
1 The evaluation content of performance inspection for installation of steam turbine
pipe shall be inspected according to those specified in Table 5.8.2 and shall be
comprehensively judged.
Table 5.8.2 Scoring Table of Performance Inspection
Project position (scope) Installation of steam turbine pipe Construction stage Before 168h trial operation in full load

Construction Evaluation
organization organization

SN Evaluation content Deserved Evaluation result Obtained Remarks

369
score 100% 85% 70% score

Spectral analysis of alloy steel as pipe materials and


1 10
pipe fittings as well as hardness inspection:

2 Valve inspection 10

Inspection of creep expansion supervising section


3 5
and creep monitoring point

4 Adjustment and inspection of supporter and hanger 15

5 Welded junction inspection under supervision: 15

6 Expansion inspection of pipe system 10

7 System tightness test 10

Blowing inspection of main steam and reheating


8 10
system

9 Internal cleaning degree of system 10

10 System earthing inspection 5

Weight value: 30
Total deserved score:
Evaluation Total obtained score:
result Score of performance inspection for installation of steam turbine pipe=obtained score/deserved score weight value=
Evaluator (signature):
Date

2 The evaluation methods for performance inspection of installation of steam turbine


pipe are listed as follows.
1) Spectral analysis of alloy steel as pipe materials and pipe fittings as well as
hardness inspection:
Report inspection; spectral analysis of alloy steel as pipe materials and pipe
fittings as well as hardness inspection result meeting design or specification
requirements with intact, standard and complete records are Class I and gain
100% standard score; those ones with little inspection value not meeting the
design or specification requirements but meeting the requirements after
processing or to be applied with concession through unified agreement of the
parties and intact, standard and complete related records are Class II and gain
85% standard score; those ones with partial inspection value not meeting the
design or specification requirements but meeting the requirements after
processing or to be applied with concession through unified agreement of the
parties and basically intact, standard and complete related records are Class III
and gain 70% standard score.
2) Valve inspection:
The valves with qualified inspection and complete record, and the service
performance fully meeting the operating requirement after operation in system
and without leakage on site (including internal leakage) are Class I and gain
100% standard score; the ones with internal (external) leakage phenomenon
(only limited to drainage system valve for main pipe) for individual valve in

370
system and the service performance meeting the operating requirement after
processing are Class II and gain 85% standard score; the ones with internal
(external) leakage phenomenon (only limited to drainage system valve for main
pipe) for a small amount of valves in system and the service performance
basically meeting the operating requirement after processing are Class III and
gain 70% standard score.
3) Inspection of creep expansion supervising section and creep monitoring point:
Installation of creep supervising section and creep measurement points meeting
design and compulsory provision requirements and with intact, actual and
complete record is Class I and gains 100% standard score, the one meeting
design and compulsory provision requirements and with basically intact, actual
and complete record is Class II and gains 85% standard score; the one basically
meeting design and compulsory provision requirements and with basically
intact, actual and complete record is Class III and gains 70% standard score.
4) Adjustment and inspection of supporter and hanger:
Installation of supporter and hanger meeting design and specification
requirements with actual and complete record and the thermal running state
meeting design and specification requirements is Class I and gains 100%
standard score; the one meeting design and specification requirements with
actual and complete record and may meet design and specification
requirements after adjustment or processing under thermal state is Class II and
gains 85% standard score; the one basically meeting design and specification
requirements with basically actual and complete record and basically meeting
design and specification requirements after adjustment or processing under
running state is Class III and gains 70% standard score.
5) Welded junction inspection under supervision:
The welded junction under supervision with qualified 100% non-destructive
inspection according to specification and the first qualification rate reaching
98% and above is Class I and gains 100% standard score; the one with the first
qualification rate reaching 96% and above is Class II and gains 85% standard
score; the one with the first qualification rate reaching 95% and above is Class
III and gains 70% standard score.
6) Expansion inspection of pipe system:
Pipe system expansion meeting the design requirements with correct expansion
indication and without expansion obstructing phenomenon on site and with
complete record is Class I and gains 100% standard score; the one basically
meeting the design requirements and with complete record is Class II and gains
85% standard score; the one with deviation for individual position expansion
but basically not influencing the normal operation of system and with basically
complete record is Class III and gains 70% standard score.
7) System tightness test:
The system tightness test shall be qualified with complete confirmation and
signature, and the main pipe of system during operational process shall be free
from leakage phenomenon. If the system tightness is good without any leakage

371
point, it is Class I and gains 100% standard score; the slight leakage points
(limited to drain and blowdown system of main pipe system less than 2 and
leakage points of medium and low-pressure pipe system less than 5) and not
influencing the normal operation of unit is Class II and gains 85% standard
score; the slight leakage point (limited to drain and blowdown system of main
pipe system less than 4 and leakage points of medium and low-pressure pipe
system less than 8) and not influencing the normal operation of unit is Class III
and gains 70% standard score.
8) Blowing inspection of main steam and reheating system:
The system flushing with scientific and reasonable scheme, less flushing times
and effect reaching code and standard requirements [impact spot on last target
card 0.8mm, 0.5mm~0.8mm (including 0.8mm) spot no larger than 8 points
and 0.2mm~0.5mm spot with even distribution], complete record and
confirmation and signature and intact target card preservation is Class I and
gains 100% standard score; the system flushing with scientific and reasonable
scheme, and flushing effect reaching code and standard requirements, basically
complete record and confirmation and signature and intact target card
preservation is Class II and gains 85% standard score; the system flushing with
scientific and reasonable scheme, and flushing effect basically reaching code
and standard requirements, basically complete record and confirmation and
signature and intact target card preservation is Class III and gains 70% standard
score.
9) Internal cleaning degree of system:
The pipe system with clean internal cleaning (flushing) and complete record
and confirmation and signature as well as good systems operation is Class I and
gains 100% standard score; the pipe system with comparatively clean internal
cleaning (flushing) and complete record and confirmation and signature as well
as the slight jam or other poor phenomena existing for equipment and valves
caused by unclean system during operation, but not influencing the normal
operation of system is Class II and gains 85% standard score; the one with
basically complete record and confirmation and signature the slight jam or
other poor phenomena existing for equipment and valves caused by unclean
system during operation, but basically not influencing the normal operation of
system is Class III and gains 70% standard score.
10) Earthing inspection of fuel gas and fuel oil pipes:
The system with earthing construction meeting design and specification
requirements and qualified ground resistance test as well as complete and
standard test record and report is Class I and gains 100% standard score; the
one with system earthing construction meeting design and specification
requirements and with qualified ground resistance test as well as basically
complete and standard test record and report is Class II and gains 85% standard
score; the one with system earthing construction basically meeting design and
specification requirements and with qualified ground resistance test as well as
basically complete and standard test record and report is Class III and gains

372
70% standard score.
5.8.3 The evaluation method of quality record for installation of steam turbine pipe shall be
in accordance with those specified in 5.4.3; the evaluation contents shall be inspected
according to those specified in Table 5.8.3 and shall be comprehensively judged.
Table 5.8.3 Scoring Table of Quality Record
Construction
Project position (scope) Installation of steam turbine pipe Before 168h full load trial operation
stage

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


SN Evaluation content Remarks
score 100% 85% 70% score

Raw material Quality certificate document of raw


and material equipment and warehouse entry 10
equipment acceptance record
1 inspection
and Field spectrum, thickness and hardness
5
acceptance inspection record
record

Quality acceptance record 10

Trace record of pipe piping (installation) 10

Monitoring record of creep expansion 5

Installation record of expansion indicator 5


Construction Welded junction inspection, heat
2 10
record treatment and detection record

Design alteration and defect treatment


10
record

Confirmation and signature record of


5
concealed items

Acceptance record of tightness test 10


Construction
Acceptance record of washing pipe and
3 test 15
washing
(debugging)
Valve debugging record 5

Weight value: 20 scores


Total deserved score:
Evaluation Total obtained score:
result Score of quality record for installation of steam turbine pipe=obtained score/deserved scoreweight value=
Evaluator (signature):
Date

5.8.4 Evaluation on size deviation and actual limit measurement for installation of steam
turbine pipe.
1 The evaluation on size deviation and actual limit measurement for installation of
steam turbine pipe shall be inspected according to those specified in Table 5.8.4-1 and shall

373
be comprehensively judged.
2 The evaluation method of size deviation and actual limit measurement for installation
of steam turbine pipe shall meet those specified in 5.4.4; the specific inspection item of size
deviation and limit evaluation content shall be carried out according to those specified in
Table 5.8.4-2.
Table 5.8.4-1 Evaluation Table of Size Deviation and Actual Limit Measurement for Installation of Steam
Turbine Pipe
Before 168h full load trial
Project position (scope) Installation of steam turbine pipe Construction stage
operation

Construction Evaluation
organization organization

Deserved Evaluation result Obtained


SN Inspection item Remarks
score 100% 85% 70% score

1 Size deviation of pipe positioning 15

2 Installation deviation value of supporter and hanger 20

3 Adjustment of original position of spring 20

4 Flatness and deviation of contra aperture 15

5 Spacing of two welds 5

Distance from weld to supporter and hanger (open pore


6 5
position or bend beginning point)

7 Length of connecting bolt exposed from screw thread 10

8 Cold drawing value deviation of pipe 5

9 Gradient of flange end surface. 5

Weight value: 15 scores


Total deserved score:
Total obtained score:
Evaluation
Score of size deviation and actual limit measurement for installation of steam turbine pipe=obtained score/deserved
result
scoreweight value=
Evaluator (signature):
Date

Table 5.8.4-2 Items to Be Inspected of Size Deviation and Actual Limit Measurement for Installation of
Steam Turbine Pipe
SN Inspection item Unit Permissible variation value

Elevation deviation mm <15

Bending degree DN100 1/1000 and 20


Size deviation of
1 of the horizontal mm
pipe positioning DN>100 2/1000 and 20
pipe

Vertical pipe verticality mm 2/1000 and 15

2 Installation deviation value of supporter and hanger Meeting the requirements of the design drawing

3 Adjustment of original position of spring Meeting the requirements of the design drawing

Flatness of contra DN<100 mm 1


4
aperture DN100 mm 2

374
Spacing of two DN500 mm >external diameter of pipe, and>150
5
welds DN>500 mm >external diameter of pipe, and>500

Distance from weld Spacing between weld and bending


mm >external diameter of pipe, and>100
to supporter and point of bent pipe
6 hanger (open pore Spacing between weld and opening mm >50
position or bend Spacing between weld and edge of
mm >50
beginning point) supporter and hanger

7 Length of connecting bolt exposed from screw thread Exposing 2~3 threads

8 Cold drawing value deviation of pipe Meeting the design requirements

No larger than 1.5/1000 of the outer diameter of the


9 Gradient of flange end surface mm
flange and no larger than 2mm

5.8.5 The evaluation method of management and implementation performance of


compulsory provisions for installation of steam turbine pipe shall meet those specified in
5.4.5; the evaluation content shall be inspected referring to those specified in Table 5.5.5 and
shall be comprehensively judged.
5.8.6 Evaluation on appearance quality for installation of steam turbine pipe.
The evaluation method of appearance quality for installation of steam turbine pipe shall
meet those specified in 5.4.6; the evaluation content shall be inspected and evaluated
according to the contents specified in Table 5.8.6 and shall be comprehensively judged.
Table 5.8.6 Scoring Table of Appearance Quality
Installation of steam turbine
Project position (scope) Construction stage Before 168h full load trial operation
pipe

Construction organization Evaluation organization

Deserved Evaluation result Obtained


SN Evaluation content Remarks
score 100% 85% 70% score

1 Overall appearance quality 25

2 System tightness 10

3 Painting construction 10

4 Welding construction 5

5 Thermal insulation project 15

6 Bolted connection 5

7 System mark 5

8 Installation of supporter and hanger 15

9 Valve installation 10

Weight value: 10 scores


Total deserved score:
Evaluation Total obtained score:
result Score of appearance quality for the installation of steam turbine pipe=obtained score/deserved scoreweight value=
Evaluator (signature):
Date

5.9 Evaluation on Construction Quality of Steam Turbine Main Body (Including Steam

375
Feed Pump), Equipment, Pipe Insulation and Paint

5.9.1 Evaluation on the quality assurance conditions on the construction site.


The evaluation method of quality assurance conditions on the construction site for steam
turbine main body (including steam feed pump), equipment, pipe insulation and paint shall be
in accordance with those specified in Article 5.4.1. The evaluation content shall be inspected
and comprehensively evaluated according to those specified in Table 5.5.1.
5.9.2 Evaluation on performance inspection
1 Performance inspection and evaluation items of steam turbine main body, equipment,
pipe insulation and paint project are detailed in Table 5.9.2.
Table 5.9.2 Evaluation Table of Performance Inspection
Steam turbine main body (including steam
Construction
Project position (scope) feed pump), equipment, pipe insulation Before 168h full load trial operation
stage
and paint

Construction Evaluation
organization organization

Evaluation result Obtained Remarks


SN Evaluation content Deserved score
100% 85% 70% score

Spectrum re-inspection of alloy


steel for thermal insulation 5
member

Steam turbine Expansion joints and expansion


1 8
main body clearances of main parts

shed-free and crack-free 5

Insulating layer surface


12
temperature inspection

Qualified materials for the on-site


10
inspection

Binding and laying of insulating


10
Equipment layer
2
pipe insulation Installation quality of support
10
member

Installation quality of protective


10
layer

Equipment Adhesive strength 15


3
pipe paint Uniform in color 15

Weight value: 20 scores


Total deserved score:
Evaluation Total obtained score:
results The performance inspection score for steam turbine main body (including steam feed pump), equipment, pipe
insulation and paint projects= obtained score/deserved scoreweight value =
Evaluator ( signature):
Date

2 Inspection criteria

376
1) Steam turbine main body:
Spectrum re-inspection of insulation-member alloy steel: spectral analysis shall
be carried out for the alloy steel piece by piece; materials shall not be misused.
Materials of the alloy steel parts shall meet the requirements specified in
equipment technical documents.
Expansion joint and expansion clearance in main parts: they shall meet the
requirements specified in equipment technical documents. Expansion joints
shall be arranged to be criss-cross; through-expansion joints shall not be
available and the expansion joints directions shall be consistent with designed
ones. For the quality and clearance of expansion joints: the expansion joints
shall meet the design requirements; the size deviation of expansion clearance
meet design requirements and insulation materials are filled in compaction; it
shall be free from any lumpy shedding and large-area cracking. Inspection on
insulation layer surface temperatures: during the full load trial operation of
steam turbine generator units, the insulation layer surface of the steam turbine
main body (including steam feed pump) are inspected in thermal state; where
the environment temperature is not greater than 25, the insulation-layer
surface temperature shall not be greater than 50; where the environment
temperature is greater than 25, the insulation-layer surface temperature is not
greater than 25plus the environmental temperature.
2) Equipment and pipe insulation:
Material qualification on-site inspection: technical performance of insulation
materials meets the design criteria. There are complete quality certificates,
delivery reports and random inspection reports.
The binding and laying of insulating layer shall meet the design If the same
kind of thermal insulation product is adopted during the laying of insulating
layer, in the following conditions, the layer must be divided into sub-layer:
thickness of hard material is greater than 80mm; or the thickness of semi-hard
material or soft material is greater than 100mm. Gap joint shall not be larger
than 5mm. Joints in the same layer shall be staggered and in the adjacent
vertical layers shall be pressed; angle joint is close-over overlay one. The edge
joints shall be regular, the staggered joints shall be in good order, and the layer
surfaces shall be even. Binding of hard or semi-hard insulating layer shall be
firm and the binding spacing of hard insulating layer shall not be larger than
400 mm. Where the nominal diameter is equal to or greater than 600mm, the
pipe or equipment shall be reinforced with additional iron wire or steel strip and
the binding spacing shall not be greater than 500mm. The binding spacing of
the semi hard heat insulating layers shall not be larger than 300 mm; at least
two galvanized iron wires shall be bound on each thermal insulation product
and the spacing shall be uniform; the appearance shall be flat.
Quality of support member installation: support member is firmly installed in
the right position without looseness.
Support member spacing: for vertical pipes with nominal diameter greater than
100mm and vertical equipments, the spacing of plane-wall support members is

377
1.5~2m. Round tank and pipe: the spacing of high-temperature pipe support
members is 2m~3m; the spacing of moderate temperature pipe support member
is 3m~5 m and the spacing of low temperature pipe support members is 5
m~7m. The width of the support member shall be less than the insulation
thickness by 10mm but shall not be less than 20mm.
Installation quality of protective layer: the upper circumferential joints and
longitudinal joints of the metallic protective layer for equipment and pipe shall
overlap the lower ones in downstream direction; the overlapping shall be firm,
without looseness or falling off; the joints shall be regular; the layout of self
plugging rivet or tapping screw shall be uniform. Appearance of protective
layer is tidy and esthetic. Overlapping spacing of metallic protective layer: for
indoor equipment and pipe, it is not less than 20mm at general positions and not
less than 50mm at expansion joint positions. For outdoor equipment and pipe: it
is not less than 50mm in general position and not less than 75mm in expansion
joint position. Overlapping of metallic protective layer for upright high
temperature pipe shall be not less than 80mm. Where the rendering coat is
taken as the protective layer, the broken joint of the rendering coat for high
temperature pipe shall be kept at the same position of the expansion joint of
insulating layer. The expansion joint surface of outdoor rendering coat shall be
added with metal protective shell or provided with other waterproof measures.
The width and depth of quadrilled or annular flute expansion joints reserved by
the rendering coat of large equipment shall meet design requirements.
3) Equipment and pipe paint:
The paint color shall meet design requirements; the post-painted surface color
is uniform and consistent; there shall be no spot, falling off, flow mark or
obvious brush mark etc.
3 Inspection method: site inspection; if necessary, inspecting the construction records
to judge it comprehensively.
1) Steam turbine main body thermal insulation
Spectrum re-inspection of alloy steel: checking spectral analysis report.
Expansion joints and expansion clearances of main parts: inspecting the
construction acceptance records.
Without shedding or cracking: inspecting the acceptance license.
Insulating-layer surface temperature inspection: measuring with thermoscope
for the surface temperatures of metals or outer guard boards.
2) Equipment and pipe insulation:
Qualification of materials for on-site inspection: inspecting whether the
delivery report, quality certificate and material random inspection report of
each batch of materials are complete or not.
Binding and laying of heat insulating layer: observation and ruler-based
inspection
Installation quality of support member: observation and ruler-based inspection.
Installation quality of protective layer: observation and ruler-based inspection.
3) Equipment and pipe paint: observation

378
5.9.3 Quality record evaluation.
1 The quality record evaluation items of steam turbine main body (including steam
feed pump), equipment, pipe insulation and paint are detailed in Table 5.9.3 and shall be
comprehensively evaluated according to those specified in the table.
2 Evaluation criteria: Those quality records with material & equipment quality
certificates (outgoing quality certificates), complete site acceptance record, construction
record, construction test record, data; actual and effective content, standard classification &
rearrangement, perfect reviewing and signing procedures and meeting the requirements
specified in design and standards are Class I and gain 100% standard score. Those quality
records with complete information, relatively complete data, actual and effective content,
relatively standard rearrangement, relatively complete reviewing and signing procedures and
meeting the requirements specified in design and standards are Class II and gain 85%
standard score. Those quality records with basically complete information, date; actual and
effective content; basically standard rearrangement, basically complete reviewing and signing
procedures and basically meeting the requirements specified in design and standards are Class
III and gain 70% standard score.
3 Evaluation methods: to inspect the quantity and content of information
Table 5.9.3 Evaluation Table of Quality Records
Steam turbine main body (including
Construction
Project position (scope) steam feed pump), equipment, pipe Before 168h full load trial operation
stage
insulation and paint

Construction Evaluation
organization organization

Deserved Evaluation results Obtained


SN Evaluation content Remarks
score 100% 85% 70% score

Delivery certificates and re-inspection


7
reports of materials and equipments

Notice letter and registration form of


design alteration and materials 3
substitutes

Confirmation and signature of the


critical process records of concealed 8
Steam
project
1 turbine main
Expansion joints and expansion
body 6
clearances records of main parts

Confirmation and signature for the


inspection records of insulating-layer 8
surface temperature

Inspection report of heat insulating


material, plastering material and 8
formula

2 Equipment Delivery certificate or report of material 3


pipe Site acceptance record of material 3

379
insulation On-site inspection report of material 4

Confirmation and signature for the


measurement of insulating-layer surface 6
temperature

Confirmation and signature for the


measurement of main steam pipe 7
surface temperature

Confirmation and signature for the


measurement of reheated steam surface 6
temperature

Confirmation and signature for the


measurement of cylinder surface 6
temperature

Quality acceptance of inspection batch,


5
subitem, subdivision

Delivery certificate of material 5

Equipment Site acceptance record of material 5


3
pipe paint Quality acceptance records of
10
inspection batch, subitem, subdivision

Weight value: 15 scores


Total deserved score:
Total obtained score:
Evaluation
The quality inspection score for steam turbine main body (including steam feed pump), equipment, pipe insulation
results
and paint projects= obtained score/deserved scoreweight value =
Evaluator(signature):
Date

5.9.4 Size deviation and limit evaluation.


1 Size deviation and limit evaluation items of steam turbine main body, equipment,
pipe insulation and paint project are detailed in Table 5.9.4.
2 Inspection criteria
1) Steam turbine main body thermal insulation:
Insulating layer thickness: about -5mm~+15mm.
Expansion joint and expansion clearance sizes in main parts: they shall meet
the requirements specified in equipment technical documents.
Inspection on temperature on insulation layer surface: during the trial operation
of steam turbine generator in full load, the insulation layer surface of the steam
turbine main body (including steam feed pump) are inspected in thermal state;
where the environment temperature is not greater than 25 , the
insulation-layer surface temperature shall be not greater than 50; where the
environment temperature is greater than 25, the insulation-layer surface
temperature is not greater than 25plus environmental temperature.
2) Equipment and pipe insulation:
Insulating layer thickness: shall meet the design requirements; allowable
deviation of thermal insulating material thickness shall be -5mm ~10mm.

380
Thermal inspection on insulation layer surface of the heating power pipes, such
as equipment main steam and reheated steam, the valve and the pipe fittings:
where the environment temperature is not greater than 25 , the
insulation-layer surface temperature shall be not greater than 50; where the
environment temperature is greater than 25, the insulation-layer surface
temperature is not greater than 25 plus environmental temperature. Surface
temperature inspection of cylinder: the temperature difference between the
upper and lower cylinder shall not be higher than 50.
3) Equipment and pipe paint:
Film thickness shall meet the design requirements.
3 Inspection method: it shall be site inspection assisted by inspecting construction
records and comprehensive judgment on the size deviation and limit.
1) Steam turbine main body:
Insulating layer thickness: inspecting the confirmation and signature records.
Expansion joint and expansion clearance sizes in main parts: inspecting the
confirmation and signature records and they shall meet the requirements
specified in equipment technical documents.
Record, confirmation and signature inspection of insulating layer surface
temperature: thermal inspection on the main body surface with thermoscope.
2) Equipment and pipe insulation:
Insulating layer thickness: inspection on heat insulating layer for its thickness
by vertically inserting one straight pin with a length above that thickness into
this heat insulating layer
Inspection on insulating layer surface temperature of equipment: to inspect with
infrared thermometer and spot inspect three points every 50m2.
Inspection on surface temperatures of the heating power pipes, such as
equipment, main steam and reheated steam, the valve and the pipe fittings: to
inspect on the main steam pipe with infrared thermometer and spot inspect
three points every 50m.
The thermal insulations for the creep measurement points and the parts with
special purposes by the design and criteria shall meet the relevant requirements.
3) Equipment and pipe paint: paint thickness tester shall be applied to measure.
Table 5.9.4 Evaluation Table of Size Deviations and Limits
Steam turbine main body (including
Construction
Project position (scope) steam feed pump), equipment, pipe Before 168h full load trial operation
stage
insulation and painting

Evaluation
Construction organization
organization

Evaluation results Obtained


SN Evaluation content Deserved score Remarks
100% 85% 70% score

1 Steam turbine Insulating layer thickness 8


main body
Expansion joint and expansion
6
clearance sizes of main parts

381
Spot inspection on insulating layer
6
surface temperatures

Insulating layer thickness 10

Cylinder surface temperature test 16

Equipment insulating layer surface


15
temperature test

Test on surface temperatures of the


Equipment and
2 heating power pipes, such as main
pipe insulation 16
steam and reheated steam, the valve
and the pipe fittings

The creep measurement points and the


parts with special purposes by the
13
design and criteria shall meet the
specifications.

Equipment and
3 Film thickness 10
pipe paint

Weight value: 10 scores


Total deserved score:
Evaluation Total obtained score:
results The quality inspection score for steam turbine main body (including steam feed pump), equipment, pipe insulation
and paint projects= obtained score/deserved scoreweight value = Evaluator (signature):
Date

5.9.5 Evaluation on implementation performance of compulsory provisions


1 The evaluation items on implementation performance of compulsory provisions for
steam turbine main body (including steam feed pump), equipment and pipe insulation are
detailed in Table 5.9.5.
2 The inspection and evaluation method on implementation performance of
compulsory provisions for steam turbine main body (including steam feed pump), equipment,
pipe insulation and paint are detailed in 5.4.5.
Table 5.9.5 Evaluation Table of Compulsory Provision Implementation Performance
Project position Steam turbine main body (including steam feed Construction
Before 168h full load trial operation
(scope) pump), equipment, pipe insulation and painting stage

Construction Evaluation
organization organization

Evaluation results Obtained


SN Evaluation content Deserved score Remarks
100% 85% 70% score

Compilation condition of implementing


1 5
compulsory provision plan

Workability of implementing compulsory


2 15
provision plan

Compulsory provisions of this position (system)


3 25
have been implemented entirely

382
Strictness degree of implementing compulsory
4 25
provisions of this position (system)

Records of implementing compulsory provision


5 whether be complete and meet requirements of 30
specification or not

Weight value :15 scores


Total deserved score:
Total obtained score:
Evaluation
The quality inspection score for steam turbine main body (including steam feed pump), equipment, pipe
results
insulation and paint projects= obtained score/deserved scoreweight value =
Evaluator (signature) :
Date

5.9.6 Appearance quality evaluation:


1 The appearance quality evaluation items on steam turbine main body (including
steam feed pump), equipment, pipe insulation and paint are detailed in Table 5.9.6.
2 Inspection criteria
1) Steam turbine main body:
The appearance and process of insulating layer shall be fine: the surface
smoothness shall not be greater than 3mm/m; it shall be regular, straight and
even; the circular arc shall be smooth; free from shedding and obvious crack;
the color and luster shall be uniform and tidy without contamination.
2) Equipment and pipe insulation:
Outer casing installation process: when corrugated plate (contour plate) is
adopted as the outer casing, the upper and lower corrugation shall be vertical,
upper joints shall overlap the lower joints, downstream overlapping, the upper
and lower joints shall be in the same horizontal line, and interfaces shall be flat.
Axial and circumferential overlapping of pipe outer casing shall not be less
than 50mm; outdoor pipe and high-temperature pipe overlapping shall not be
less than 75mm. Circumferential joints of outer casing shall be consistent with
the pipe gradient direction. Axial joint shall be downward, arranged in the
15-45 position below the pipe horizontal center line, and form an extended
line, recommended to be installed in the concealed position, and moved to the
60 position above the pipe horizontal center line when there are obstacles in
the side surface or bottom. Self plugging rivet or self-tapping screw shall be
arranged uniformly in the fixed distance; the surface shall be tidy and esthetic
Construction process of plastering layer: the surface smoothness shall not be
greater than 5mm/m; the plastering layer surface shall be smooth, the corner
angle shall be square and sharp, the circular arc shall be slick without obvious
crack.
Valve bushing process: the valve bushing shall be firmly fixed without
loosening, the appearance shall be smooth and esthetic; and it shall be
convenient for installation and dismantling.
Small pipe thermal insulation process: thermal insulating belt or thermal
insulating rope winding shall be tight, firm, multi-layer pressed joints,

383
consistent in thickness. Appearance shall be flat, smooth and beautiful.
3) Equipment and pipe paint:
It shall be uniform and consistent in tone; without spot, falling off, wrinkle,
flow mark, floating film, paint particle or obvious brush mark after painting.
4) Equipment and system mark shall meet the design; be complete, standard,
uniform and striking.
3 Inspection method: it shall be observed and inspected on the site, accompanied by
actual measuring and checking the inspection acceptance records, confirmation and signature
and shall be carried out with qualitative or quantitative conclusions.
Table 5.9.6 Evaluation Table on Appearance Quality
Steam turbine main body
(including steam feed pump), Construction
Project position (scope) Before 168h full load trial operation
equipment, pipe insulation and stage
paint

Evaluation
Construction organization
organization

Evaluation
SN Deserved Obtained
Evaluation content results Remarks
Deserved score score
100% 85% 70%

Surface smoothness shall not be


4
greater than 3mm/m

Insulating layer Regular, straight and even and


4
appearance and process smooth for circular arc
1
of steam turbine main Without shedding or obvious
3
body crack

Uniform in color and tidy


4
without contamination

Construction process of
5
plastering layer

Outer guard board (including


Equipment pipe metal enclosure) installation 25
2
insulation process

Valve bushing process 15

Small pipe thermal insulation


10
process

Color meets the design 10

Uniform in color 5
3 Equipment pipe paint
Without pervious spots, wrinkle,
5
shedding or flow mark

Meeting the design 5


Equipment and system
4 Complete, standard, uniform
mark 5
and striking

Evaluation Weight value: 25 scores

384
results Total deserved score:
Total obtained score:
The quality inspection score for steam turbine main body (including steam feed pump), equipment, pipe insulation
and paint projects= obtained score/deserved scoreweight value =
Evaluator (signature) :
Date

5.10 Evaluation on Installation and Construction Quality of Combustion Engine and


Its Auxiliary Equipments and Accessory Machines

5.10.1 The evaluation methods of quality assurance conditions on installation and


construction sites for the combustion engine and its auxiliary equipments and accessory
machines shall be in accordance with those specified in Article 5.4.1. The evaluation contents
shall be inspected and comprehensively evaluated according to those specified in Table 5.5.1.
5.10.2 Evaluation on installation performance inspection of the combustion engine and its
auxiliary equipments and accessory machines.
1 The contents of evaluation on installation performance inspection of the combustion
engine and its auxiliary equipments and accessory machines shall be inspected and
comprehensively evaluated according to those specified in Table 5.10.2.
Table 5.10.2 Evaluation Table of Performance Inspection
Project position Installation of the combustion engine and its Construction
Before 168h full load trial operation
(scope) auxiliary equipments and accessory machines stage

Construction Evaluation
organization organization

Evaluation results Obtained


SN Inspection items Deserved score
100% 85% 70% score Remarks

1 Combustion engine output power 20

Bearing vibration and temperatures of the


2 20
combustion engine main body

Oil quality in the oil systems (lubricating oil


3 15
and fire-resistant oil)

Performance on auxiliary equipments and


4 15
accessory machines

Bearing vibration and temperatures of


5 10
accessory machines

Enclosure tightness of the combustion engine


6 5
main body

7 Tightness of the combustion gas system 10

8 Exhaust temperature of the combustion engine 5

385
Weight value: 30
Total deserved score:
Total obtained score:
Evaluation results Installation performance inspection score of the combustion engine and its auxiliary equipments and
accessory machines=Obtained score/Deserved scoreWeight value=
Evaluator (signature):
Date

2 Methods of evaluation on installation performance inspection of the combustion


engine and its auxiliary equipments and accessory machines are as follows.
1) Combustion engine output power:
Class I shall be evaluated if the test values of the combustion engine
maximum-continuous output and rated output reach 100% of values given in
the contract; Class II shall be evaluated if the test values reach
95%(included)~100% of values given in the contract; Class III shall be
evaluated if the test values reach 95% below of values given in the contract.
2) Bearing vibration and temperature values of the combustion engine main body:
The combustion engine bearing temperature values shall all meet the
requirements of the manufacturer. Class I shall be evaluated if the shafting
vibration is less than or equal to 70m; Class II shall be evaluated if the
shafting vibration is between 70m and 120m; Class III shall be evaluated if
the shafting vibration is greater than or equal to 120m.
3) Oil quality in the oil systems:
If the lubricating oil quality reaches to NAS7 and the fire-resistant oil quality
reaches to NAS5, the oil quality in the oil systems shall be evaluated as Class II;
if one oil quality of the two surpasses the criterion specified in Class II, the oil
quality in the oil systems shall be evaluated as Class I; and if one oil quality of
the two is inferior to the criterion specified in Class II, the oil quality in the oil
systems shall be evaluated as Class III.
4) Performance of auxiliary equipments and accessory machines:
Auxiliary equipments and accessory machines refer to the attached pumps of
the combustion engine, air blowers and fuel processing equipments. If the
performances of all these equipments reach the units operation and design
requirements, the performance shall be evaluated as Class I. If the main
equipment performances reach the units operation and design requirements and
the other equipment performances basically reach the units operation and
design requirements, the performance shall be evaluated as Class II. If
performances of all these equipments basically reach the units operation and
design requirements, the performance shall be evaluated as Class III.
5) Bearing vibration and temperature values of accessory machines:
Bearing temperature shall all meet the provisions and requirements of the
manufacturer. Lipid-lubricating bearing temperature generally shall not exceed
80, oil-lubricating bearing temperature generally shall not exceed 65~70.
Vibration of accessory machines is detailed in Appendix C. If the amplitude
reaches the high-class criterion, the vibration shall be evaluated as Class I; if

386
the amplitude reaches the good-class criterion, the vibration shall be evaluated
as Class II; if the amplitude reaches the qualified criterion, the vibration shall
be evaluated as Class III.
6) Enclosure tightness of the combustion engine main body:
If the enclosure is tight without light-leak and the spray tests of the fire
extinguishing protection system are without leakage points, the enclosure
tightness shall be evaluated as Class I; if the enclosure is tight without
light-leak and the spray tests of the fire extinguishing protection system are
without obvious leakage points, the enclosure tightness shall be evaluated as
Class II; if the enclosure is tight without obvious light-leak and spray tests of
the fire extinguishing protection system are without obvious leakage points, the
enclosure tightness shall be evaluated as Class III.
7) Tightness of the combustion gas system:
If the combustion gas system equipments and pipes are tight without leakage,
the tightness shall be evaluated as Class I.
8) Exhaust temperature of the combustion engine:
If the exhaust temperature average values of the combustion engine are not
greater than assurance values given in the contract, it shall be evaluated as
Class I.
5.10.3 Methods of evaluation on installation quality records of the combustion engine and
its auxiliary equipments and accessory machines shall meet the requirements specified in
Article 5.4.3, The evaluation contents shall be inspected and comprehensively evaluated
according to those specified in Table 5.10.3.
Table 5.10.3 Evaluation Table of Installation Quality Records
Project position Installation of the combustion engine and its Construction
Before 168h full load trial operation
(scope) auxiliary equipments and accessory machines stage

Construction Evaluation
organization organization

Evaluation result Obtained


SN Inspection items Deserved score Remarks
100% 85% 70% score

Material certificates and site acceptance


1 5
records

Equipment certificates and site acceptance


2 10
records

3 Monitoring records and reports of metal 5

4 Installation records 20

5 Various certificates 15

Quality acceptance table of inspection lot,


6 20
subitem, subsection and unit project

Trial operation records of single rotating


7 10
machine

Notice letters and registration forms of


8 5

387
design alterations and materials substitutes

Equipments defects notices, equipments


9 5
defects handling reports and registration forms

10 Registration forms of measurement tools 5

Weight value: 20
Total deserved score:
Total obtained score:
Installation construction quality records score of the combustion engine and its auxiliary equipments and
Evaluation results
accessory machines=Obtained score/Deserved scoreWeight value=
Evaluator (signature):
Date

5.10.4 Evaluation on actual measurement of installation size deviation and limit of the
combustion engine and its auxiliary equipments and accessory machines
1 Evaluation on actual measurement of installation size deviation and limit of the
combustion engine and its auxiliary equipments and accessory machines shall be inspected
and comprehensively evaluated according to those specified in Table 5.10.4.
Table 5.10.4 Evaluation Table of Actual Measurement of Installation Size Deviation and Limit
Project position Installation of the combustion engine and its Construction
Before 168h full load trial operation
(scope) auxiliary equipments and accessory machines stage

Construction Evaluation
organization organization

Evaluation result Obtained


SN Inspection items Deserved score Remarks
100% 85% 70% score

1 Equipments (devices) installation position 25

Coupling centre alignment and connection of


2 20
the combustion engine

Assembling gaps between the combustion


3 10
engine shafts and self-synchronizing couplers

4 Sliding pin system of the combustion engine 10

5 Combustion engine load distribution 10

6 Coupling centers of rotating machines 10

Assembling gaps between rotating machines


7 5
bearings

Installation position of inlet and exhaust


8 10
passage as well as bypass chimney

Weight value: 10
Total deserved score:
Evaluation Total obtained score:
results Actual measurement of installation project size deviation and limit score of the combustion engine and its
auxiliary equipments and accessory machines=Obtained score/Deserved scoreWeight value=
Evaluator (signature):

388
Date

2 Methods of evaluation on actual measurement of installation size deviation and limit


of the combustion engine and its auxiliary equipments and accessory machines shall meet
those specified in Article 5.4.4 of this part. Point counting and allowable deviation provisions
of the size deviation and limit shall be implemented as follows.
1) Equipment (device) installation position; installation position of inlet and
exhaust passage as well as bypass chimney:
Equipments (devices) include the combustion engine and auxiliary system
equipments (devices). Installation positions include center, elevation, levelness
and verticality; allowable deviation shall be determined according to Chapter 4
Construction Quality Acceptance Criteria; the measuring points are regarded as
statistic points.
2) Coupling centre alignment and connection of the combustion engine:
Coupling centre alignment of the combustion engine must meet the
requirements of the equipment manufacturing plant and DL 5011. Four points
are set up for each pair of the couplings, and two points are respectively set up
for circumference deviation and end face opening. Coupling connection
includes the connection of load short-shafts and the combustion engine rotors
and the connection of load short-shafts and the driven end rotors. Each datum
for the increased flutter of each pair of coupling after connection and the force
moment or elongation of fastening blots shall be a measuring point according to
the installation records.
3) Assembling gaps between the combustion engine shafts and self-synchronizing
couplers; sliding pin system of the combustion engine and the combustion
engine load distribution:
They shall be counted according to the measuring points determined in Chapter
4 Construction Quality Acceptance Criterion; the allowable deviation shall be
in accordance with the provisions of the manufacturers.
4) Coupling centers of rotating machines:
Coupling centers must meet the requirements of accessory machines centre
alignment allowable deviation. Four points are set up for each pair of the
couplings (see Appendix D), and two points are respectively set up for
circumference deviation and end face opening. All the data shall be
gather-counted.
5) Bearing assembly gap:
The assembling gap between sliding bearings include bearing bush gap and
bearing bush tightening force; the assembling gap between rolling bearings
includes the gap between bearings and enclosures, axial gap between bearing
capping and bearing shaft.Each datum shall be a measuring point according to

389
the installation records.
5.10.5 The evaluation methods for the management and implementation performance of the
compulsory provisions on the installation of combustion engine and its auxiliary equipments
and accessory machines shall meet the requirements of 5.4.5, the evaluation shall include the
inspection and evaluation according to the contents specified in Table 5.5.5 and the
comprehensive judgement shall be carried out finally.
5.10.6 Evaluation on installation appearance quality of the combustion engine and its
auxiliary equipments and accessory machines.
1 For the evaluation on the installation appearance quality of combustion engine and
its auxiliary equipments and accessory machines, the inspection shall be carried out according
to the requirements of Table 5.10.6 and the comprehensive judgement shall be carried out
finally.
Table 5.10.6 Evaluation Table on Appearance Quality
Installation of combustion
engine and its auxiliary Construction
Project position (scope) Before carrying out trial operation with 168h full load
equipments and accessory stage
machines

Evaluation
Construction organization
organization

Deserved Evaluation result Obtained


SN Inspection item Remarks
score 100% 85% 70% score

1 Equipment appearance 20

Pipe installation technology of gas, oil and


2 15
water systems

3 Equipment and system tightness 15

4 Equipment and system mark 10

Installation technology of platform, handrail


5 10
and ladder access

Installation technology of enclosure and


6 10
shield

7 Painting and insulation 10

8 Regional environment 10

Weight value: 1 0
Total deserved score:
Total obtained score:
Evaluation
Appearance quality score of the installation works of combustion engine and its auxiliary equipments and accessory
result
machines=obtained score/deserved score weight value =
Evaluator (signature):
Date

2 The evaluation methods for the appearance of the installation equipments of


combustion engine and its auxiliary equipments and accessory machines as well as the
evaluation methods for the appearance quality of pipe installation technology of gas, oil and
water systems shall comply with those specified in 5.5.9, and the counting method for the

390
inspection points of evaluation shall be implemented according to the following requirements:
1) Equipment appearance: Each independent equipment and its framework and
bracket shall be taken as one evaluation point, and the regular, reasonable and
clean point that is firmly installed without damage or remnant shall be
evaluated to be "good".
2) Pipe installation technology of gas, oil and water systems: Each independent
system shall be taken as one evaluate point, and the point featured of
reasonable pipe arrangement, esthetic appearance, correct gradient, good and
firm installation of supporters and hangers, well installed valves that are
convenient for operation, concentrated and regular arrangement of small
diameter pipes with uniform interval and same turn radius shall be evaluated to
be "good".
3) Tightness of equipments and systems: In this item, the equipment and systems
do not include the fuel gas system. The equipments and systems with no leak
sources and the systems with no more than 3 leak sources shall be classified
into Class I; the equipments and systems without leak sources and those with
no more than 8 leak sources shall be classified into Class II; the equipments
and systems without severe leak sources shall be classified into Class III.
4) Equipment and system mark: The equipments and systems with correct,
complete, striking, uniform, standard, legible, firmly-hung and pollution-free
marks shall be classified into Class I; the equipments and systems with correct,
basically complete, standard, legible, firmly-hung and pollution-free marks
shall be classified into Class II; and those with correct, basically complete and
firmly-hung marks shall be classified into Class III.
5) Installation technology of platform, handrail and staircase: The platform,
handrail and staircase that are firmly installed, with smooth surface, good
coating, straight and even horizontal pole, vertical pole, uniform space, height
meeting the relevant requirements, firm welding, qualified weld appearance
quality, and skirting board, access ladder and safety cage meeting the
specifications shall be classified into Class I; the platform, handrail and
staircase that are firmly installed, reach smooth surface basically and are with
good coating, height meeting the relevant requirements, firm welding, qualified
weld appearance quality, and skirting board, access ladder and safety cage
meets the specifications shall be classified into Class II; and those firmly
installed platform, handrail and staircase with height meeting the relevant
requirements, firm welding, and skirting board, access ladder and safety cage
meeting the specification shall be classified into Class III.
6) Installation technology of enclosure and shield: The enclosure and shield that
are installed at right positions, have no rubbing with rotating positions and no
influence on expansion, and are with complete bolts, straight, even,
deformation-free and tightly-welded framework and panel, regular, beautiful,
rustless and scar-free installation shall be classified into Class I; the enclosure
and shield that are installed at right positions, have no rubbing with rotating
positions and no influence on expansion, and are with complete bolts, basically

391
straight, even and tightly-welded framework and panel free from obvious
deformation as well as are with regular installation shall be classified into Class
II; and those that are installed at right positions, have no rubbing with rotating
positions and no influence on expansion, and are with complete bolts and
firmly installed framework and panel shall be classified into Class III.
7) Painting and insulation: provided that the thickness and color of paint meet the
design and the paint color is matched harmoniously, the color and lustre are
uniform without flow mark, wrinkle, gas bubble, shedding, rust and
contamination; the insulation does not affect the expansion, the surface is
smooth without damage and shedding, the rendering coat is round and smooth
without cracks, the seaming of and metal enclosure meets the requirements and
the technique is of esthetic appearance, the point shall be classified into Class I;
provided that the paint thickness and color meet the design, the color and lustre
are basically uniform without flow mark, wrinkle, gas bubble, shedding and
rust; and the insulation does not affect the expansion, the surface is smooth
with damage and shedding, the rendering coat is basically round and smooth
without crack, and the seaming of metal shell meets the requirements, the point
shall be classified into Class II; provided that the paint thickness and color
meet the design, the color and lustre are uniform basically; and the insulation
does not affect the expansion, the surface is basically flat and smooth, the
rendering coat is basically round and smooth and the seaming of metal shell
meets the requirements, the point shall be classified into Class III.
8) Regional environment: The trial operation area without oil and water as well as
ash accumulation and the articles with regular stacking and fixed management
without sanitation dead angle is Class I; the trial operation area without oil and
water as well as ash accumulation and the articles with regular stacking without
waste stacking is Class II; the trial operation area basically without oil and
water as well as ash accumulation and the articles with basically regular
stacking is Class III.
5.11 Summarizing of Evaluation Score of Project Position (Scope) of Single Project

5.11.1 The actual quality evaluation score of single project shall be summarized and
evaluated corresponding to each project position (scope) and evaluation item.
5.11.2 Quality evaluation score and evaluation rating of single project shall be implemented
in accordance with requirements specified in Table 5.11.2.
Table 5.11.2 Quality Evaluation Score Summary Table of Single Project
Name of project position (scope)

Installation of Installation of Steam turbine Installation of


Installation
accessory accessory main body combustion
of main body Installation
Evaluation machines and machines and (including engine and its In
SN and of steam Remarks
content auxiliary auxiliary steam feed auxiliary total
sub-system lead pipe of
devices in devices pump), equipments
of turbine turbine
main power outside main equipment, and accessory
generator
house power house pipe insulation machines

392
and painting

On-site quality
1 assurance
condition

2 Performance test

3 Quality record

Actual
measurement of
4 dimensional
deviation and
limit

Implementation
performance of
5
compulsion
provisions

Appearance
6
quality

Subtotal

Subtotal weight
value listed in Table
5.2.3

Total score Evaluation rating (class)

Evaluator (signature):
Evaluation organization (official seal)
Date

5.12 Evaluation Report on the Quality of Single Project

5.12.1 After quality evaluation of single project, supervision or evaluation organization


shall issue evaluation report which shall include the following contents:
1 Overview of single project.
2 Quality evaluation situation and result of project position (scope).
3 Quality evaluation situation and result of single project.
5.12.2 The report of single project quality evaluation shall meet the following requirements:
1 Single project overview: explaining primary device situation, each construction
participating organization (design, construction, debugging, supervision, etc), contracting
pattern and construction safety workload (contract amount), major projects characteristics,
quality control in the construction process.
2 Administrative situation of single project: quality characteristics (technology
lightspot, management innovation, technology innovation and "four new" application), as
well as completion conditions of safety and environmental protection targets.
3 Construction quality acceptance situation: checking condition of the acceptance
result of unit project, subsection project and subitem project.
4 Evaluation of each project position (scope): where there is the item of serious
inconformity, it shall be indicated on stress.
5 Quality evaluation score summary, evaluation grade and conclusive opinions of

393
single project.

6 Quality Evaluation of Single Unit

6.0.1 The quality evaluation for single unit shall be conducted after the construction quality
acceptance for all single projects and the 168-h trial operation of the unit with full load are
completed and the environmental protection projects supported are normally put into
operation. The public system shall be bought into the evaluation for the first unit.
6.0.2 More units of the same stage shall be evaluated according to single unit respectively,
and the support public system for units put into production subsequently shall be evaluated
synchronously with the unit.
6.0.3 168h full-load trial operation quality evaluation of the unit shall be in accordance with
those specified in Table 6.0.3.
Table 6.0.3 Quality Evaluation Table on 168h Full-load Trial Operation of the Unit
Project name Unit number

Test organization Evaluation organization

Examining Examination
SN Evaluation content Property Remarks
standard/examining value result/measured value

Conditions for entering into 168h trial


1 Dominant Meeting the requirements
operation

2 Continuous operation time Dominant 168h

Continuous steady load Meeting preselected load


3
curve

4 Continuous average load rate 90%

5 Time of continuous full load 96h

6 Thermal protection utilization rate Dominant 100%

Thermal control automatic utilization


rate (coordination investment,
7 Dominant 95%
adjustment quality reaching the
standard)

Thermal control, electrical measuring


8 99%
point/ instrument utilization rate

Accuracy rate of indication of meters


9 at thermal control and electrical 98%
measuring points

10 Electric protection utilization rate Dominant 100%

Electric automatic device utilization


11 Dominant 100%
rate

Qualification of steam and water


12 Qualified
quality

Termination of full load trial Approved by


13 Dominant
operation commander-in-chief

394
Number of days from the first pipe
blowing and lighting to the
14 90d
completion of trial operation with
168h full load

Starting frequency of 168h trial


15 3 times
operation

16 Tightness of vacuum system Dominant 0.3kPa/min

Hydrogen leakage rate of electric


17 10Nm3/d
generator

18 Shafting vibration of unit Dominant 76m

19 Load dump test of unit Meeting requirements

Evaluation score:

Evaluator (signature):
Date

Note 1: Class I: evaluation score 92 (including 92)~100; each index reaching the examination value and relevant requirements;
test conditions meeting the requirements; test report, confirmation and signature complete and normative.
Note 2: Class II: evaluation score 85 (including 85)~92; dominant indexes reaching examination value and relevant
requirements; test conditions meeting the requirements; test report, confirmation and signature being complete and normative;
85% and above general indexes reaching examination value and relevant requirements; test report, confirmation and signature
complete and normative fundamentally.
Note 3: Class III: evaluation score 70 (including 70)~85; dominant indexes reaching examination value and relevant
requirements; test conditions meeting the requirements; test report, confirmation and signature complete and normative; 70% and
above general indexes reaching assessment value and relevant requirements; test report, confirmation and signature complete and
normative fundamentally.

6.0.4 Single unit evaluation score is the sum of obtained score of all weighted single project
quality evaluation and unit 168-h full load trial operation technical index evaluation, and the
evaluation score statistics shall be in accordance with those specified in Table 6.0.4.
Table 6.0.4 Statistic Table of Single Unit Evaluation Score
Project name Unit number

Construction organization Evaluation organization

SN Quality evaluation of single project Score Weight % Obtained score

1 Civil work 15

2 Boiler unit 16

3 Steam turbine generator unit 15

4 Thermal meter and control device 9

5 Pipe and system 5

Equipment and system with the water treatment and hydrogen


6 5
generation

7 Welding work 6

8 Processing preparation 3

395
9 Installation of electrical devices 10

10 Technical indexes for 168-h full load trial operation of unit 16

Evaluation score:

Evaluator (signature):
Evaluation organization (official seal)
Date

Note 1: Evaluation of civil works shall be carried out by making reference to the requirements of GB/T 50375.
Note 2: Electrical device installation shall be evaluated according to the unit project fine rate in DL/T 5161.1~5161.17; thereinto,
Class I: fine rate is 100%; Class II: fine rate is 95%~99%; Class III: fine rate is 90%~94%.

7 Quality Evaluation of Overall Project

7.0.1 The quality evaluation for overall project shall be conducted after the quality
evaluation for all single units, net special test, the performance tests of the units and the
engineering archives management evaluation are completed.
7.0.2 Technical index evaluation of performance test of unit shall be in accordance with
those specified in Table 7.0.2.
Table 7.0.2 Evaluation Table of the Technical Indexes of Performance Test on Single Unit
Project name Unit number

Evaluation
Test organization
organization

Design Test condition Test report


Measured
SN Evaluation content Property value/guarantee (coincidence (coincidence Remarks
value
value rate) rate)

Thermal efficiency
1 Dominant
of boiler

Maximum
2 continuous rating of
boiler

3 Boiler rated load

Minimum stable
combustion rating
4
of boiler fuel (arc)
cut

Coal pulverizing
5
system rating

Unit consumption
6
of coal pulverizer

Air leakage ratio of


7
air preheater

Dust remover
8
efficiency

9 Maximum rating of Dominant

396
steam turbine
(combustion
engine)

Nominal rating of
steam turbine
10
(combustion
engine)

Heat consumption
of steam turbine
11 Dominant
(combustion
engine)

Coal consumption
12 of unit power Dominant
supply

Station service
13 power consumption Dominant
rate of unit

Shafting vibration
14 Dominant
of unit

15 Unit RB test

Pollutant emission
16 (NOx, SO2, fume Dominant
and waste water)

17 Noise

18 Heat dissipation

19 Dust

Denitration
20
efficiency

Denitration
21
efficiency

Waste water and


22 Dominant
sewage treatment

Water consumption
23 rate for power Dominant
generation

Evaluation score:

Evaluator (signature):
Date

Note 1: Class I: evaluation score 92 (including 92)~100; each index reaching design value, contract guarantee value and relevant
criteria; test conditions meeting the requirements; test reports and statistical forms complete and normative.
Note 2: Class II: evaluation score 85 (including 85)~92; dominant indexes reaching design value, contract guarantee value and
relevant criteria; test conditions meeting the requirements; 85% and above general indexes reaching design value, contract
guarantee value and relevant criteria, test reports and statistical forms complete and normative fundamentally.

397
Note 3: Class III: evaluation score 70 (including 70)~85; dominant indexes reaching design value, contract guarantee value and
relevant criteria; test conditions meeting the requirements; 70% and above general indexes reaching design value, contract
guarantee value and relevant criteria, test reports and statistical forms complete and normative fundamentally.

7.0.3 The evaluation on the engineering archives management shall be in accordance with
those specified in Table 7.0.3.
Table 7.0.3 Evaluation Table of Engineering Archives Management
Project name Project scale

Development Evaluation
organization organization

Content of
Deserved Obtained
Evaluation content unmatched Remarks
score score
item

Each item archives working system shall be improved;


management system and working procedure shall be
developed. Unified leadership, hierarchical management and
responsibility system of leader shall be adopted for project
5
archives work. Development organization shall supervise and
instruct construction participating organizations. Project
archives work shall be carried out synchronously with project
Basic
construction.
management of
Filing work shall be brought into the post responsibilities of
archives work
relevant department and personnel as well as contract 5
management, and provided with assessment measures.

Archives management shall be informationalized and


convenient for shortcut retrieve and utilization. Facilities and
equipments shall meet the requirements of archives safety, 20
protection and modernization management. Personnel shall be
on duty with certificates.

Within 45 days after put into production, all archives shall be


Time of filing 5
handed over to development organization

Filing documents shall be intact, accurate, systematic and


Scope of filling 30
effective. Retention period shall be classified accurately.

Project document collection and arrangement (classification,


volume compilation, arrangement, serial number and catalog) 20

Archives shall be normative; hand-over procedures shall be complete


quality Completion drawing compilation shall be normative and meet
5
the actual conditions

Durable carrier, legibility, complete signature and seal 10

Engineering archives management evaluation score:

Evaluation
result
Evaluator (signature):
Date

398
Note 1: Class I: evaluation score of 92 (including 92)~100.
Note 2: Class II: evaluation score of 85(including 85)~ 92.
Note 3: Class III: evaluation score of 70(including 70)~85.

7.0.4 Application of advanced technology such as advance of science and technology as


well as energy saving and emission reduction shall be paid attention to in the overall project
quality evaluation. Projects that win state, province and department (industry) level award or
certificate shall be awarded scores according to those specified in Table 7.0.4.
Table 7.0.4 Statistic Table of State, Province and Department (Industry)-level Awards
Project name Project scale

SN Awarded project Awarded project name Award department Awarded score

1 High quality project award

2 Scientific and technological achievement award

3 Patent

4 Working method

5 QC achievement

6 "Four new" application

7 New record

8 Saving

9 Environmental protection

Total score:

Evaluator (signature):
Evaluation organization (official seal)
Date

7.0.5 Overall project quality evaluation score is the sum of mean value of all single unit
evaluation scores, mean value of all unit performance test evaluation scores, obtained score of
engineering archives management evaluation and awarded scores; overall project quality shall
be evaluated according to those specified in Table 7.0.5.
Table 7.0.5 Summary Table of Overall Project Quality Evaluation
Project name Project scale

Development organization Design organization

Construction organization Debugging organization

Supervision organization Performance test organization

SN Evaluation content Weight % Obtained score

1 Mean value of all single unit evaluation scores 55

2 Mean value of all unit performance test evaluation scores 30

3 Engineering archives management evaluation 15

4 Awarded score

Overall project quality evaluation score:

Evaluator (signature):
Evaluation organization (official seal)
Date

7.0.6 Fine project: overall project quality evaluation score is 85 and above; high-quality fine
project: 92 and above.
7.0.7 Overall project quality evaluation shall be organized and coordinated by the
development organization, and carried out independently by the supervision organization or

399
other evaluation organizations. The evaluation results shall be issued with evaluation report.
7.0.8 Overall project quality evaluation shall meet the relevant current national and
professional regulations on project completion acceptance and evaluation.

400
Annex A

(Informative)

Typical Data of Flow Passage Part

A.1 Typical data of flow passage clearance of STC 300MW steam turbine (for your
information only)
A.1.1 Flow passage clearance of high- and medium-pressure cylinders
See Figure A.1 for the flow passage clearance of high- and medium-pressure cylinders.

Steam flow direction

Steam flow direction

Rotor

Grade High-pressure cylinder Grade Medium-pressure cylinder


number A B E F number A B E F

1 9.76 9.71 9.80 9.68 12 10.81 13.80 13.78 12.75

2 8.25 8.16 8.13 8.28 13 10.81 13.80 13.78 12.75

3 8.25 8.16 8.13 8.28 14 10.81 13.80 13.78 10.81

4 8.25 8.16 8.13 8.28 15 10.81 13.80 13.78 10.81

5 8.25 8.16 8.13 8.28 16 10.81 10.81

6 8.25 8.16 8.13 8.28 17 10.01 14.60 14.58 10.01

7 8.25 8.26 18 10.01 14.60 14.58 10.01

8 8.25 8.16 8.15 8.26 19 10.01 14.61 14.58 10.01

9 8.25 8.16 8.15 8.26 20 9.19 15.47 9.19

10 8.25 8.16 8.15 8.26

11 8.25 8.16 10.34

Figure A.1 Flow Passage Clearance of High- and Medium-pressure Cylinders

401
The location dimension K value of rotor is 9.80mm 0.13mm.
The design clearance values of the Grade 1~20 radial diaphragm gland and steam seal
gland of high- and medium-pressure rotors all are 0.75mm.
A.1.2 Flow passage clearance of low-pressure cylinders
1 See Figure A.2 for axial clearance.

Rotor Rotor

Grade Valve adjusting end Motor end


number A B E F A B E F

1 26.49 17.30 17.30 26.49 17.35 26.44 26.44 17.35

2 26.49 25.86 25.86 26.49 17.35 35.00 35.00 17.35

3 26.49 25.86 25.86 26.49 17.35 35.00 35.00 17.35

4 26.49 25.54 25.54 26.49 17.35 34.68 34.68 17.35

5 27.47 22.99 33.17 18.33 32.13 24.03

6 28.48 37.43 19.34 46.57

7 31.00 21.86

Figure A.2 Axial Clearance of Low-pressure Cylinders


The location dimension K value of rotor is 26.49mm 0.13mm.
2 See Table A.1 for the radial clearance.
Table A.1 Radial Clearance of Low-pressure Cylinders

Steam seal gland Diaphragm gland


Grade number
Valve adjusting end Motor end Valve adjusting end Motor end

1 1.05 1.05 0 0

2 1.15 1.35 1.00 1.00

3 1.45 1.55 1.30 1.30

4 1.85 1.55 1.40 1.30

5 1.35 1.65 1.00 1.50

6 3.38 3.38 1.54 1.54

7 6.10 6.10 1.61 1.61

A.2 Typical data of flow passage clearance of STC 600MW steam turbine (for your
information only)
See Figure A.3 for the flow passage clearance of high- and medium-pressure cylinders.

402
Rotor

Steam flow direction

High-pressure cylinder Medium-pressure cylinder


Grade Grade
number number
A B E F H A B E F

1 11.933 11.86 11.96 11.89 11

2 12

3 13

4 14

5 15

6 16

7 17

8 18

9 19

10 20

Figure A.3 Flow Passage Clearance of High- and Medium-pressure Cylinders


The location dimension K value (F value of Grade 1) of rotor is 11.96mm0.13mm.
A.3 Typical data of flow passage clearance of STC 1000MW steam turbine (for your
information only)
A.3.1 Flow passage clearance of No.1 low-pressure rotor
1 See Figure A.4 for axial clearance.

403
Valve adjusting end Motor end Rotor
location Rotor location
Grade Grade
A B E F A B E F dimension dimension K2
number number
K1

1 28.00 1 13.95 14.00

2 14.85 27.95 28.00 14.00 2 28.85 13.95 14.00 28.00

3 28.10 28.00 3 14.10 14.00


14.000.50 28.000.50
4 32.50 32.00 4 46.50 18.00

5 21.00 34.00 65.00 5 35.00 20.00 51.00

6 24.00 39.40 6 38.00 25.40

Figure A.4 Axial Clearance of No.1 Low-pressure Rotor


2 See Figure A.5 for radial clearance.

Steam gland clearance (radial gland of low-pressure Seal gland clearance (radial gland of low-pressure
Grade number
rotor blade) partition panel)

1 1.30~1.60

2 1.30~1.60 1.30~1.60
Valve
3 1.30~1.60 1.30~1.60
adjusting
4 1.50~1.80 1.40~1.70
end
5 3.40~3.70 1.30~1.60

6 1.00~1.30

1 1.30~1.60

2 1.30~1.60 1.30~1.60

Motor 3 1.30~1.60 1.30~1.60

end 4 1.50~1.80 1.40~1.70

5 3.40~3.70 1.30~1.60

6 1.00~1.30

Figure A.5 Radial Clearance of No.1 Low-pressure Rotor

404
A.3.2 Flow passage clearance of No.2 low-pressure rotor
1 See Figure A.6 for axial clearance.

Valve adjusting end Motor end Rotor


Rotor location
Grade Grade location
A B E F A B E F dimension K2
number number dimension K1

1 35.95 36.00 1 13.95 14.00

2 14.60 36.00 36.00 14.00 2 36.60 14.00 14.00 36.00

3 35.95 36.00 3 13.95 14.00


14.050.50 36.050.50
4 26.90 36.00 4 48.90 14.00

5 17.00 38.00 44.00 5 39.00 16.00 22.00

6 20.00 43.40 6 42.00 21.40

Figure A.6 Axial Clearance of No.2 Low-pressure Rotor


2 See Figure A.7 for radial clearance.

Steam gland clearance (radial gland of low-pressure Seal gland clearance (radial gland of low-pressure
Grade number
rotor blade) partition panel)

1 1.30~1.60

2 1.30~1.60 1.30~1.60
Valve
3 1.30~1.60 1.30~1.60
adjusting
4 1.50~1.80 1.40~1.70
end
5 3.40~3.70 1.30~1.60

6 1.00~1.30

Motor 1 1.30~1.60
end 2 1.30~1.60 1.30~1.60

3 1.30~1.60 1.30~1.60

4 1.50~1.80 1.40~1.70

5 3.40~3.70 1.30~1.60

405
6 1.00~1.30

Figure A.7 Radial Clearance of No.2 Low-pressure Rotor

A.4 Typical data of flow passage clearance of HTC 1000MW steam turbine (for your
information only)
A.4.1 Flow passage clearance of low-pressure rotor
1 See Figure A.8 for the axial clearance on the steam admission side at blade top and
root.

Steam flow direction

Low-pressure rotor

No.1 low-pressure cylinder No.2 low-pressure cylinder


Grade
Valve adjusting end Motor end Valve adjusting end Motor end
number
N L N L N L N L

1 21.10 21.90 10.50 11.30 34.80 35.60 10.60 11.40

2 20.90 21.90 11.20 12.00 34.50 35.60 11.30 12.10

3 20.80 21.90 11.90 12.70 34.50 35.60 12.00 12.80

4 25.20 23.80 16.90 15.50 39.00 37.40 17.00 15.60

5 23.30 23.80 15.90 16.20 37.00 37.40 16.00 16.30

6 24.00 24.00 38.00 38.00

Figure A.8 Axial Clearance on the Steam Admission Side at Blade Top and Root of Low-pressure Rotor
2 See Figure A.9 for the axial clearance of Grade 1 and Grade 2 tip glands at valve
adjusting end

Steam flow direction

Grade number Valve adjusting end H Motor end H

1 9.40 9.40

406
2 9.40 9.40

Figure A.9 Axial Clearance of Grade 1 and Grade 2 Tip Gland at Valve Adjusting End of Low-pressure
Rotor
3 See Figure A.10 for the radial clearance of Grade 2~6 diaphragm glands.

Diaphragm gland Steam flow direction

Low-pressure rotor

N
Grade number
Right side Left side Top Bottom

2 1.40 1.70 1.00 1.40

3 1.40 1.70 1.00 1.40

4 1.40 1.70 1.00 1.40

5 1.80 1.40 2.00 1.60

6 1.80 1.40 2.00 1.60

Figure A.10 Radial Clearance of Grade 2~6 Diaphragm Glands of Low-pressure Rotor
4 See Figure A.11 for the radial clearance of the tip gland at blade top.

Low-pressure rotor

Z-1
Grade number
Right side Left side Top Bottom

1 1.98 1.58 1.98 1.78

2 2.23 1.83 2.23 2.03

3 2.23 1.83 2.23 2.03

407
4 3.70 3.30 3.70 3.50

5 3.80 3.40 3.60 3.60

6 12.20 11.80 12.00 12.00

Figure A.11 Radial Clearance of Tip Gland at Blade Top of Low-pressure Rotor
A.4.2 Flow passage clearance of medium-pressure rotor
1 See Figure A.12 for the axial clearance on the steam admission side at blade top and
root.

Steam flow direction

Grade Valve adjusting end Motor end


number N L L J N L L J

1 8.00 15.00 8.80 13.00 4.90 16.00 5.70 10.00

2 8.60 13.00 9.40 5.60 10.00 6.40

3 9.10 14.00 9.90 6.10 11.00 6.90

4 6.20 11.00 7.00 7.10 11.00 7.90

5 6.20 11.00 7.50 7.10 11.00 8.60

6 6.20 11.00 7.50 7.10 11.00 8.60

7 6.20 11.00 7.00 7.10 11.00 7.90

Figure A.12 Axial Clearance on the Steam Admission Side at Blade Top and Root of Medium-pressure
Rotor
2 See Figure A.13 for the axial clearance of the tip gland at blade top.

408
Steam flow direction

Valve adjusting end Motor end


Grade number
H H' H H'

1 4.90 8.40 7.60 5.40

2 4.90 9.10 7.60 6.10

3 4.90 9.50 7.60 6.50

4 3.60 6.60 10.30 7.50

5 3.60 6.50 10.30 7.50

6 3.45 6.55 10.30 7.50

7 3.55 6.45 10.30 7.50

Figure A.13 Axial Clearance of Tip Gland at Blade Top of Medium-pressure Rotor
3 See Figure A.14 for the axial clearance of diaphragm gland.

Steam flow direction

Rotor

Valve adjusting end Motor end


Grade number
M M M M

1 6.63 10.22 9.52 7.33

2 8.03 10.82 9.52 7.33

3 8.03 10.82 9.52 7.33

4 6.15 9.14 12.47 9.17

5 6.15 9.14 12.47 9.17

409
6 4.56 7.55 12.47 9.17

7 4.56 7.55 12.47 9.17

Figure A.14 Axial Clearance of Diaphragm Gland of Medium-pressure Rotor


4 See Figure A.15 for the radial clearance of the tip gland at blade top.

Steam flow direction

O
Grade number
Right side Left side Top Bottom

1 1.27 1.27 1.57 1.57

2 1.27 1.27 1.57 1.57

3 1.27 1.27 1.57 1.57

4 1.27 1.27 1.57 1.57

5 1.27 1.27 1.57 1.57

6 1.27 1.27 1.57 1.57

Figure A.15 Radial Clearance of Tip Gland at Blade Top of Medium-pressure Rotor
5 See Figure A.16 for the radial clearance of diaphragm gland.
Steam flow direction

Rotor

N
Grade number
Right side Left side Top Bottom

1 1.50 1.50 1.50 1.50

2 0.54 0.54 0.74 0.74

3 0.54 0.54 0.74 0.74

4 0.54 0.54 0.74 0.74

5 0.54 0.54 0.74 0.74

6 0.54 0.54 0.74 0.74

Figure A.16 Radial Clearance of Diaphragm Gland of Medium-pressure Rotor

410
A.4.3 Flow passage clearance of high-pressure rotor
1 See Figure A.17 for the axial clearance on the steam admission side at blade top and
root.

Steam flow direction

Grade number N L'

1 4.50 5.30

2 5.40 6.20

3 5.70 6.30

4 6.30 7.10

5 6.90 7.70

6 7.30 8.10

7 7.30 8.10

8 8.30 9.10

9 8.30 9.10

10 8.30 9.10

Figure A.17 Axial Clearance on the Steam Admission Side at Blade Top and Root of High-pressure Rotor
2 See Figure A.18 for the axial clearance of the tip gland at blade top.

411
Steam flow direction

Grade 1

Steam flow direction

Grade 2~10

Grade number H H'

1 5.10 4.70

2 7.50 5.90

3 8.00 6.10

4 8.50 6.70

5 8.80 7.30

6 9.20 7.60

7 9.60 7.80

8 9.90 8.70

9 10.20 8.50

10 10.40 8.70

Figure A.18 Axial Clearance of Tip Gland at Blade Top of High-pressure Rotor
3 See Figure A.19 for the axial clearance of Grade 2~10 diaphragm glands.

Steam flow direction

412
Grade number M M'

2 9.53 7.32

3 9.53 7.32

4 9.53 7.32

5 10.43 8.02

6 10.43 8.02

7 12.12 9.52

8 12.12 9.52

9 12.12 9.52

10 12.12 9.52

Figure A.19 Axial Clearance of Grade 2~10 Diaphragm Glands of High-pressure Rotor
4 See Figure A.20 for the radial clearance of the tip gland at blade top.

Steam flow direction

Grade 1

Steam flow direction

Grade 2~10

O
Grade number
Right side Left side Top Bottom

1 1.27 1.27 1.27 1.27

2 1.17 1.17 1.17 1.47

3 1.17 1.17 1.17 1.47

4 1.17 1.17 1.17 1.47

5 1.17 1.17 1.17 1.47

6 1.17 1.17 1.17 1.47

7 1.17 1.17 1.17 1.47

8 1.17 1.17 1.17 1.47

9 1.17 1.17 1.17 1.47

10 1.17 1.17 1.17 1.47

Figure A.20 Radial Clearance of Tip Gland at Blade Top of High-pressure Rotor

413
5 See Figure A.21 for the radial clearance of Grade 2~10 diaphragm glands.

Steam flow direction

N
Grade number
Right side Left side Top Bottom

2 0.64 0.64 0.64 0.94

3 0.54 0.54 0.54 0.84

4 0.54 0.54 0.54 0.84

5 0.54 0.54 0.54 0.84

6 0.54 0.54 0.54 0.84

7 0.54 0.54 0.54 0.84

8 0.54 0.54 0.54 0.84

9 0.54 0.54 0.54 0.84

10 0.54 0.54 0.54 0.84

Figure A.21 Radial Clearance of Grade 2~10 Diaphragm Glands of High-pressure Rotor

414
Annex B

(Informative)

Grading Standard of Oil Quality

B.1 The Oil Quality Standards of National Aerospace Standard (NAS, 1638) was issued in
January 1984, see Table B.1.
Table B.1 NAS Grading Standards for Oil Cleanliness

Graded granularity Grain size m

100/mL
5~15 15~25 25~50 50~100 100~250 250

00 125 22 4 1 0 0

0 250 44 8 2 0 0

1 500 59 16 5 1 0

2 1000 178 32 6 1 0

3 2000 356 63 11 2 0

4 4000 712 126 22 4 0

5 8000 1435 253 45 8 0

6 16000 2350 506 90 16 0

7 32000 5700 1012 180 32 0

8 64000 11400 2025 360 64 0

9 128000 22800 4050 720 128 0

10 256000 45600 8100 1440 256 0

11 512000 91200 16200 2880 512 0

12 1024000 182400 32400 5760 1024 0

B.2 MOOG Pollution Grade Standard jointly proposed by Aircraft Industries Association of
America (ALA), American Society for Testing and Materials (ASTM) and Society of
Automotive Engineers (SAE) is detailed in Table B.2, contamination scope of different
Grades: Grade 0--very difficult to realize; Grade 1--super clean system; Grade 2--high-level
guided missile system; Grade 3 and Grade 4--common precision devices (like electric
hydraulic servoactuator); Grade 5--low-level guided missile system; Grade 6-Grade 1
industrial system.
Table B.2 MOOG Pollution Grade Standard

Graded granularity Grain size m

100/mL
5~10 10~25 25~50 50~100 >100

0 2700 670 93 16 1

1 4600 1340 210 28 3

2 9700 2680 380 56 5

3 24000 5360 780 110 11

4 32000 10700 1510 225 21

415
5 87000 21400 3130 430 41

6 128000 42000 6500 1000 92

B.3 As for the equality relation between ISO grading standards and NAS and MOOG
grading standards, the International Standardization Organization (ISO) considers s kind of
improved grading standard, the grades of quantity with the grain sizes above 5m and above
15m may be looked up from ISO Drawing, and now the equality relation between ISO
grading standards and MOOG and NAS grading standards are listed in Table B.3.
Table B.3 Equality Relation between ISO Grading Standards and NAS and MOOG Grading Standards
ISO standard NAS standard MOOG standard

26/23
25/23
12
23/20
21/18

21/18
11
20/17

20/16
10
19/16

18/15 9 6

17/14 8 5

16/13 7 4

15/12 6 3

14/11 5 2

13/10 4 1

12/9 3 0

11/8 2

10/8
1
10/7

10/6
0
9/6

8/5 00

7/5
6/3
5/2
2/0.8

416
Annex C

(Normative)

Vibration of Accessory Machines

The bearing vibration (double amplitude) criteria for accessory machines shall be made
reference to DL 5011 and are detailed in Table C.1.
Table C.1 Bearing Vibration (double amplitude) Criteria for Accessory Machines

Rotation speed n Vibration amplitude mm

r/min
High class Good Qualified

n1000 0.05 0.07 0.10


1000<n2000 0.04 0.06 0.08
2000<n3000 0.03 0.04 0.05
n>3000 0.02 0.03 0.04

417
Annex D

(Normative)

Centre Alignment of Accessory Machines

The allowable deviation value (maximum value of the reading difference between
opposite faces) for the coupling centre alignment of accessory machines shall be made
reference to DL 5011 and is detailed in Table D.1.
Table D.1 Allowable Deviation Value (maximum value of the reading difference between opposite faces)
for Centre Alignment of Coupling

Allowable deviation value mm


Rotation speed n
r/min Stationary Non-stationary

Radial direction End surface Radial direction End surface

n3000 0.04 0.03 0.06 0.04

3000>n1500 0.06 0.04 0.10 0.06

1500>n750 0.10 0.05 0.12 0.08

750>n>500 0.12 0.06 0.16 0.10

n<500 0.16 0.08 0.24 0.15

418

You might also like