Professional Documents
Culture Documents
100
F20 DL
Record No.: J902-2009
PROFESSIONAL STANDARD
OF THE PEOPLES REPUBLIC OF CHINA
P DL/T 5210.3-2009
3 :
1
1 Scope
This Part in DL/T 5210 specifies the relevant requirements in construction quality
acceptance standard, quality evalution of single project, quality evalution of single unit, and
quality evalution of overal project of steam turbine generator units in thermal power
generation engineering.
This part is applicable to construction quality acceptance and engineering quality
assessment of new construction, extension and renovation of thermal power generation
project steam turbine generator units with unit capacity of 300MW ~ 1000MW thermal power
generation project and fuel gas - steam combined cycles machine unit. This part can be
referanced for assessment of thermal power generating unit and nuclear power station
conventional Island under 300MW and the BOP engineering.
2 Normative references
For dated reference, subsequent amendments to (excluding corrigenda), or revisions of,
any of these publications do not apply. However, all parties coming to an agreement
according to this standard are encouraged to study whether the latest edition of these
documents is applicable. For undated references, the latest edition of the normative document
is applicable to this standard.
GB/T7596 Quality criteria of turbine oils in service for power plants
GB 50205 50205-2001 Code for Acceptance of Construction Quality of Steel
Structures
GB/T 50375 GB/T 50375-2006 Evaluating standard for excellent quality of building
engineering
DL 5011 DL 5011-1992 The Code of Election and Acceptance for Power Plant
Construction - steam turbine unit part
DL/T5161.1~5161.17 Part 9: Specification for construction quality checkout and
evaluation of electric equipment installation
DL/T 5210.1 Specification for construction quality acceptance and evaluation of
electric power construct Part 1: Civil construction engineering
DL/T869 The Code of the Welding for Power Plant
3 General Provisions
3.0.1 This standard is formualted with a view to intensifying construction engineering
quality control in electric power inducstry, improving construction quality level, and unifying
the relevant requirements in construction quality acceptance standard and evaluation for
thermal power generation engineering.
3.0.2 The construction quality acceptance for thermal power generation project shall be
conducted by inspection lot, subitem project, subsection project, and unit project. the
construction quality acceptance is only applied with a quality grade "qualified"; in case of any
nonconformity, it shall comply with Article 4.1.12 in this Part.
3.0.3 The engineering quality evaluation shall be conducted for the projects with the
"high quality" engineering objective.
3.0.4 The engineering quality evaluation shall be conducted by the three phases (stage)
2
- single project, single unit and overal project.
3.0.5 The construction quality evaluation for single project shall be conducted upon
that the construction quality acceptance for all unit projects is qualified and the collection and
rearrangement of engineering technical document is completed, and the evaluation shall cover
the whole work content before 168-h trial operation with full load.
3.0.6 The quality evalution for single unit shall be con ducted after the construction
quality acceptance for all single projects and the 168-h trial operation of the unit with full
load are completed and the environmental protection projects suppoted are normally put into
operation. the synergic system shall be bought into the evaluation for the first unit.
3.0.7 The quality evalution for overal project shall be conducted after the quality
evalution for all single units, the performance tests of the units and the engineering archives
evaluation are completed.
3
4.1.5 Apart from strictly implement provisions, the quality inspection personnel at
all-level shall be in accordance current national standard, professional
standard,contract,design document and manufacturing technology document.
4.1.6 The quality acceptance must be conducted after the construction project is
completed. the construction organization shall apply the quality acceptance ro the project
supervision and the development organization upon the construction organization has done
self-checking and prepared complete selfchecking records.
4.1.7 The construction organization shall notify the supervision organization and the
organizations concerned to conduct witness acceptance before being concealed, and complete
the inspection acceptance record and the confirmation and signature.
4.1.8 The appearance quality of unit projects shall be inspected by the quality
inspection personnel with visual observation, feeling or necessary measurement, and
confirmed and singed according to the overall condition of the inspected project .
4.1.9 The inspection and acceptance of project construction quality shall comply with
the requirements in Chapter 4 of this Part and be conducted by inspection lot, subitem project,
subsection project and unit project; where a unit project is constructed by multiple
construction organizations by sections, subunit projects may be set up. the subunit project
number is the original unit project number affixed with english letters for distinguishing.
4.1.10 The acceptance for construction quality shall be conducted only upon the
acceptance for inspection lots is qualified; the acceptance for subsection project shall be
conducted only upon the acceptance for subitem projects is qualified; the acceptance for unit
project shall be conducted only upon the acceptance for subsection projects is qualified.
4.1.11 The "qualified" construction quality acceptance for inspection lot, subitem
project, subsection project and unit project shall meet the following requirements:
1 The complete inspection is conducted for the inspection items according to the
requirements on inspection lots and subitem projects, and the inspection results meet the
quality quality criteria; the quality acceptance for this inspection lot or subitem project is
qualified.
2 The acceptance for the inspection lots cotnained in a subitem project is qualified and
the data for the subitem project is compelte; the quality acceptance for this subitem project is
qualified.
3 The acceptance for the subitem projects cotnained in a subsection project is qualified
and the data for the subsection project is compelte; the quality acceptance for this subsection
project is qualified.
4 The acceptance for the subitem projects cotnained in a subsection project is qualified
and the data for the subsection project is compelte; the quality acceptance for this subsection
project is qualified.
4.1.12 The nonconformity of construction quality, if existing, shall be registered for
record and treated according to the following requirements:
1 The inspection items for reworked ones, or replaed instrument or equipment, shall be
conducted again. .
2 The inspection items repaied, which satisfy the functional requirements of safe
handling, may be inspected according to the technology processing scheme and the negotiated
document.
4
3 As for the unaccepted project for rework or back repair, certifying agency or coherent
units shall carry out appraisal and make concessional treatment of the project not affecting the
inner quality, service life, use function and safe operation. . Secondary acceptance will not be
carried out to project after concessional treatment. However, this shall be indicated in
"acceptance conclusion". The written report thereof shall be attached to the acceptance table.
4.1.13 The construction quality of inspection lot and subitem project under one of the
following conditions shall not be inspected:
1 The inspection results of its dominant inspection items cannot meet the quality
criteria.
2 Design and manufacturer maintains data requirements for quality criteria, but there is
no measuring data in the inspection result column. .
3 Quality acceptance documents do not conform to records management regulation.
4.1.14 As for quality question problems caused by design or equipment manufacture, the
design or equipment manufacture units shall be responsible for the disposal. After the
entrusted on-site disposal by construction organization, if specific non- dominant items cannot
fully meet standard requirements, upon the written signature by development organiztion,
design organization, supervision organization and construction organization, the concessional
treatment can be made. Secondary acceptance will not be carried out to project undergone
concessional treatment. But it shall be noted in acceptance result and the written report shall
be attached after the acceptance table.
4.1.15 The quality acceptance documents for inspection lot, subitem project, subsection
project and unit project shall be of accurate data, complete document collection, and complete
signature procedure; and the material and handwriting for document preparation shall meet
the requirements of "durability" and the records management specifications.
4.2 Division of construction quality acceptance range and general tables
4.2.1 Quality acceptance shall be classified according to inspection lot, subentry project,
subsection project and unit project, which shall also be in accordance with those specified in
Table 4.2.1.
Table 4.2.1 Construction quality acceptance range division table
Construction number Acceptance organization
Number
Subite Constructi Supervisi Manufactur Developm
Unit Subsecti Propert Design of quality
m Inspecti Project name on on ing ent
proje on y organizati acceptanc
projec on lot organizati organizati organizatio organiztio
ct project on e table
t on on n n
01 Main body
installation
Domin
engineering of
ant
turbine
generators
01
Foundation
preparation
and iron
gasket (block)
5
configuration
before
installation of
turbine
generators
01 Foundation
preparation of Domin
turbine ant
generators
Foundation
check and
Domin Table 4.3.
01 geometric
ant 1
dimension
checking
Foundation
Domin Table 4.3.
02 settlement
ant 13
observation
Foundation
Table 4.3.
03 bearing area
2
roughening
Baseplate
grouting inner Table 4.3.
04
baffle 3
installation
Foundation
Table 4.3.
05 bolt
4
examination
02 Turbine
generators
foundation
iron gasket
(filling block)
preparation
installation
Adjustable
Domin Table 4.3.
04 fixer
ant 8
installation
02 Main body
Domin
installation of
ant
steam turbine
01 Pedesta check
Domin
and
ant
installation
Bearing seat
pedestal check domina Table 4.3.
01
and nt 10
installation
Low pressure
cylinder
domina Table 4.3.
02 pedestal check
nt 10
and
installation
02 Bearing seat
( box ) and
bearing bush
check
Bearing seat
domina Table 4.3.
01 ( box ) clean
nt 14
and check
Bearing bush
Table 4.3.
03 filling block
16
check
03 Installation of
bearing seat domina
(box ) and nt
bearing bush
Bearing seat
Table
01 positioning
4.4.1-1
and centering
Clearance
measurement
and domina Table
02
adjustment of nt 4.4.1-2
bearing bush
and oil catch
04 cleaning and
check of steam
cylindr and
cylinder
internal
component
Cleaning and
check of low Table
01
pressure 4.4.2-1
cylinder
Cleaning and
check of high
and Table
02
intermediate 4.4.2-2
pressure
cylinder
Cleaning and
check of high
and medium Table
03
pressure inner 4.4.2-3
cylinder steam
inlet pipe
Check of high
and medium
pressure
cylinder Table
04
nozzle box, 4.4.24
parting sheet
(suit), steam
seal (suit)
Check of low
pressure
cylinder
admission
Table
05 chamber,
4.4.2-5
parting
sheet(suit) and
steam seal
(suit)
8
High and
medium
pressure
cylinder Table 4.3.
06
component 17
spectrum and
hardness
recheck
low pressure
cylinder
component Table 4.3.
07
spectrum and 17
hardness
recheck
05 check of
turbinr rotor
High and
medium Table
01
pressure rotor 4.4.3
check
06 Steam cylindr
combination
positioning
Low pressure
cylinder
combination, Table
01
joint surface 4.4.4-1
clearance
inspection
Clearance
inspection of
high and
Table
02 medium
4.4.4-2
pressure
cylinder joint
surface
Positioning
and centering
Table
03 of low
4.4.4-3
pressure
cylinder
04 Positioning Table
9
and centering 4.4.4-3
of high and
medium
pressure
cylinder
07 Aggregate
installation of
domina
steam cylindr
nt
internal
component
Centre
alignment of
Table
01 bearing seat,
4.4.5-1
steam cylindr
and rotor
Installation of
Table
02 low pressure
4.4.5-2
inner cylinder
Inner cylinder
installation of
Table
03 high and
4.4.5-3
medium
pressure
High pressure
Table
04 nozzle box
4.4.5-4
installation
Installation of
high and
medium
pressure
cylinder
parting sheet domina Table
05
(suit), balance nt 4.4.5-5
piston ( loop ),
steam
admission
shunt ring and
gland sleeve
06 Installation of Table
low pressure 4.4.5-6
cylinder
parting sheet
(suit), balance 10
piston ( loop ),
steam
admission
shunt ring and
gland sleeve
Low pressure
cylinder
internal Table
07
component 4.4.5-7
bore centre
align
High and
medium
pressure
cylinder Table
08
internal 4.4.5-8
component
bore centre
align
08 Steam cylindr
domina
load
nt
distribution
Steam cylindr
domina Table
01 load
nt 4.4.6
distribution
09 Flow passage
clearance domina
measurement nt
adjustment
Low pressure
cylinder flow
passage domina Table
01
clearance nt 4.4.7
measurement
adjustment
High and
medium
pressure
cylinder flow domina Table
02
passage nt 4.4.7
clearance
measurement
adjustment
10
Labyrinth domina
clearance nt
11
measurement
adjustment
Low pressure
cylinder
labyrinth domina Table
01
clearance nt 4.4.8
measurement
adjustment
High and
medium
pressure
cylinder domina Table
02
labyrinth nt 4.4.8
clearance
measurement
adjustment
Check before
domina Table
01 steam turbine
nt 4.4.9-1
covering
12 Shafting
domina
adjustment
nt
and connection
Coupling
centre align
domina Table
01 before steam
nt 4.4.10-1
turbine
covering
Coupling
centre align
domina Table
02 after steam
nt 4.4.10-1
turbine
covering
Coupling
centre align domina Table
03
before reaming nt 4.4.10-1
connection
Coupling
domina Table
04 reaming
nt 4.4.10-2
connection
12
13 Turbine
generators
domina
foundation
nt
secondary
pouring
Check before
foundation Table 4.3.
01
secondary 11
pouring
Foundation
secondary domina Table 4.3.
02
pouring and nt 12
maintenance
14 Sliding pin
system
clearance
measurement,
adjustment
Sliding pin
system
domina Table
01 clearance
nt 4.4.11-1
measurement,
adjustment
Center beam
installation
between Table
02
bearing seat 4.4.11-2
and steam
cylindr
Installation of
Table
03 push and pull
4.4.11-3
device
15 Turning gear
check and
installation
16 Medium and
low pressure
communicatin
g pipe
installation
13
Medium and
low pressure
domina Table
01 communicatin
nt 4.4.13
g pipe
installation
17 Check before
steam turbine
thermal
insulation and
decorative
sheet
installation
Check before
steam turbine
thermal
Table
01 insulation and
4.4.14
decorative
sheet
installation
03 01 Adjustment
and lubricating
domina
oil system
nt
equipment
installation
Valve and
governing domina
valve nt
installation
Valve and
governing Table 4.5.
01
valve cleaning 1-1
and check
Valve and
governing domina Table 4.5.
02
valve nt 1-2
installation
02 Installation of
domina
actuating
nt
mechanism
Installation of
domina Table 4.5.
01 actuating
nt 2
mechanism
03
Installation of domina
protective nt
14
device
Emergency
domina Table 4.5.
01 governor
nt 3-1
installation
Emergency
domina Table 4.5.
02 trip throttle
nt 3-2
installation
Emergency
domina Table 4.5.
03 trip device
nt 3-3
installation
Other security
operating Table 4.5.
04
equipment 3-4
installation
05 Fire resistant
fluid system domina
and piping nt
installation
Integrated
fire-resistant
Table 4.3.
01 oil feeding
33
device
installation
Installation of
fireresistant oil
box, oil
domina Table 4.5.
02 poump, oil
nt 5-1
cooler,oil filter
and
accumulator
Fire resistant
oil system Table 4.5.
03
piping 5-2
installation
Fire resistant
domina Table 4.5.
04 oil system
nt 5-3
cycle flushing
06
Lubricating oil domina
system nt
15
equipment and
piping
installation
Integrated oil
domina Table 4.5.
01 tank
nt 6-1
installation
Lubricating oil
Table 4.5.
02 cooler
6-2
installation
Table 4.3.
Installation of
30
06 smoke exhaust
Table 4.3.
fan
31
Oil ejector or
oil worm Table 4.5.
07
wheel pump 6-7
installation
Jacking oil
Table 4.5.
09 piping
6-9
installation
Lubricating
Table 4.5.
10 pipe
6-9
installation
Lubricating oil
domina Table 4.5.
11 system cycle
nt 6-10
flushing
04 Generator and
domina
exciter
nt
installation
01 Pedestal
positioning
02
Generator domina
16
rotor check nt
03 Stator hoisting
domina
positioning
nt
check
Stator hoisting
domina Table 4.6.
01 positioning
nt 3
check
04 Stator domina
tightness test nt
05 Insertion of domina
generator rotor nt
07 Generator end
domina
cap bearing
nt
installation
Generator end
domina Table 4.6.
01 cap bearing
nt 7
installation
08 Adjustment of
air gap and domina
magnetic force nt
center
Adjustment of
air gap and domina Table 4.6.
01
magnetic force nt 8
center
09 Fan gap
adjustment
17
10 Sealing pad domina
installation nt
11 Steam turbine
- generator domina
coupling nt
centre align
Steam turbine
- generator domina Table 4.6.
01
coupling nt 11
centre align
Coupling
domina Table
02 reaming
nt 4.4.10-2
connection
12 Generator oil
catch
installation
Generator oil
Table 4.6.
01 catch
12
installation
13 Installation of
seal of domina
generator end nt
cap
Installation of
seal of domina Table 4.6.
01
generator end nt 13
cap
14 Installation of
domina
hydrogen
nt
cooler
Installation of
domina Table 4.6.
01 hydrogen
nt 14
cooler
15 Exciter domina
installation nt
18
centre align
Pedestal dowel
pin and outer Table 4.6.
04
cover 15-4
installation
Adjustment of
air gap and domina Table 4.6.
05
magnetic force nt 15-5
center
Adjustment of
gap among Table 4.6.
06
fan, air damper 15-6
and oil catch
16 Carbon brush
yoke
installation
Carbon brush
Table 4.6.
01 yoke
16
installation
17 Air pressure
test of whole domina
set of nt
generator
Air pressure
test of whole domina Table 4.6.
01
set of nt 17
generator
18 Sealing oil
system device
and piping
installation
Integrated
sealing oil Table 4.3.
01
device 33
installation
Sealing oil
Table 4.5.
02 cooler
6-2
installation
19
installation
Other
Table 4.6.
04 equipments
18-2
installation
Sealing oil
Table 4.5.
05 piping
6-9
installation
Sealing oil
domina Table 4.5.
06 system
nt 6-10
washing
19 Internal
cooling water
system
equipment and
piping
installation
Integrated
internal
Table 4.3.
01 cooling water
33
device
installation
Internal
cooling water Table 4.6.
02
pump 19-1
installation
Installation of
cooling water
Table 4.6.
03 tank, cooler
19-2
and ion
exchanger
Internal
cooling water Table 4.6.
04
conduit 19-3
installation
Internal
cooling water domina Table 4.6.
05
system nt 19-4
flashing
20 Gas system
equipment and
piping
installation
20
equipment 20-1
Gas pipeline
Table 4.6.
03 gas pressure
20-3
test
02 Turbine
generator
auxiliary
device
installation
01 Water-cooled
condenser domina
aggregate nt
installation
01 Condenser
domina
shell
nt
combination
Condenser
domina Table 4.7.
01 shell
nt 1-1
combination
02 Condenser
positioning
and centering
Condenser
Table 4.7.
01 positioning
1-2
and centering
03 Condenser
cooling tube domina
bundle nt
installation
Condenser
cooling tube domina Table 4.7.
01
bundle nt 2
installation
04 Condenser and
steam cylindr domina
connection and nt
tightness test
Condenser and
steam cylindr domina Table 4.7.
01
connection and nt 3
tightness test
21
05 Condenser
accessory
installation
and secondary
pouring
Condenser
accessory
Table 4.7.
01 installation
4
and secondary
pouring
06 Condenser
cleaning
equipment
installation
Condenser
Table 4.3.
01 scavenging
24
pump check
Condenser
Table 4.3.
02 cleaning pump
25
installation
Condenser
domina Table 4.3.
03 cleaning pump
nt 26
trial operation
Check and
installation of
Table 4.7.
04 rubber ball
5
cleaning
system
02 Air cooling
condenser
system
installation
01 Air cooling
steel structure
installation
Bracing steel
domina Table 4.8.
03 structure
nt 1-3
installation
Fan bridge
framework and
Table 4.8.
05 platform cover
1-5
plate
installation
Tube bundle
bracing Type A domina Table 4.8.
06
frame nt 1-6
installation
Platform,
ladder and
Table 4.3.
08 handrail
37
aggregate
installation
02 Air cooling
condenser fan
installation
Air cooling
Table 4.8.
01 condenser fan
2
installation
03 Exhaust
equipment
aggregate
installation
Exhaust
Table 4.7.
01 equipment
1-1
combination
Exhaust
equipment Table 4.7.
02
positioning 1-2
and centering
Exhaust
equipment and
Table 4.7.
03 steam cylindr
3
connection and
tightness test
04 Air cooling
flushing water
pump
installation
Installation of
Table 4.3.
02 flushing water
25
pump
Trial run of
domina Table 4.3.
03 flushing water
nt 26
pump
05 Exhaust
equipment hot
domina
well drainage
nt
pump
installation
Exhaust
equipment hot Table 4.3.
01
well drainage 24
pump check
Exhaust
equipment hot
Table 4.3.
02 well drainage
25
pump
installation
Exhaust
equipment hot domina Table 4.3.
03
well drainage nt 26
pump trial run
06 Vacuum
deaerator
installation
Installation of
Table 4.9.
01 deaerator main
1
body
Installation of
Table 4.9.
02 deaerator
2
accessory
07
Installation of domina
condenser pipe nt
24
bundle and
washing
device
Installation of
condenser pipe
domina Table 4.8.
01 bundle and
nt 3
washing
device
08 Electric hoist
check, domina
installation nt
and load test
Electric hoist
domina Table
01 check,
nt 4.16. 2-1
installation
09 Aircooling
domina
system
nt
tightness test
Aircooling
domina Table 4.8.
01 system
nt 4
tightness test
03 01 Deaerator
( water tank ) domina
equipment nt
installation
Deaerator
( water tank ) domina Table 4.9.
01
main body nt 1
installation
02 Deaerator
( water tank )
accessory
installation
Deaerator
(water tank) Table 4.9.
01
accessory 2
installation
03
Installation of
deaerator
(water tank)
platform,
25
ladder and
handrail
Installation of
deaerator
(water tank) Table 4.3.
01
platform, 37
ladder and
handrail
04 High pressure
heater check domina
and nt
installation
01 High pressure
heater check
02 High pressure
heater
installation
High pressure
Table 4.3.
01 heater
35
installation
05 Low pressure
heater check domina
and nt
installation
01 Low pressure
heater check
02 Low pressure
heater
installation
Low pressure
Table 4.3.
01 heater
35
installation
06 Gland heater
check and
installation
01 Gland heater
check
02
Gland heater
26
installation
07 Turbine hall
drain flash
tank
installation
01 Turbine hall
drain flash
tank
installation
Turbine hall
drain flash Table 4.3.
01
tank 36
installation
08 Installation of
other heat
exchanger
01 Installation of
other heat
exchanger
Heat
Table 4.3.
01 exchanger
34
check
Heat
Table 4.3.
02 exchanger
35
installation
09 Bypass system
equipment
inspection
installation
01 High pressure
bypass system
equipment
inspection
installation
High pressure
bypass system
Table
01 equipment
4.11.1
inspection
installation
02
Low pressure
bypass system
27
equipment
inspection
installation
Low pressure
bypass system
Table
01 equipment
4.11.2
inspection
installation
03 Installation of
steam
discharge
device
accessing into
condenser
Installation of
steam
discharge Table
01
device 4.11.3
accessing into
condenser
04 Installation of
bypass oil
system
Hydraulic
pressure
bypass set oil Table 4.5.
01
system 5-1
equipment
installation
Hydraulic
pressure
bypass set oil Table 4.5.
02
system 5-2
pipeline
installation
Hydraulic
pressure
domina Table 4.5.
03 bypass set oil
nt 5-3
system
flashing
03
Turbine
generator
accessory
machinery 28
installation
01 01 Steam feed
domina
pump set
nt
installation
Foundation
preparation,
iron gasket
and stone bolt
preparation
installation
Foundation
preparation,
iron gasket Table
01
and stone bolt 4.12.1
preparation
installation
02 Pedestal
grinding and
positioning
Pedestal
Table
01 grinding and
4.12.2
positioning
03 Bearing
( seat ) and oil
catch check
Bearing (seat)
Table
01 and oil catch
4.12.3
check
04 Steam cylindr
combination,
check,
positioning
Steam cylindr
combination, Table
01
check, 4.12.4
positioning
05 Rotor
positioning
centre align
01 Rotor
Table
positioning
4.12.5
centre align
06 Diaphragm
29
gland
installation
01 Diaphragm
Table
gland
4.12.6
installation
09 Bearing (seat)
covering and
rotor turning
gear
installation
01 Bearing (seat)
covering and
Table
rotor turning
4.12.9
gear
installation
11 Lubricating oil
30
system
installation
01 Lubricating oil
Table
system
4.12.11
installation
02 Electrically domina
driven feed nt
31
pump group
installation
01 Electrically domina
driven feed nt
pump check
01 Electrically domina
Table
driven feed nt
4.13. 1
pump check
02 Motor check
03 Electrically domina
driven feed nt
pump group
installation
01 Electrically domina
driven feed nt Table
pump group 4.13. 3
installation
04 Electrically domina
driven feed nt
pump group
coupling
centre align
01 Electrically domina
driven feed nt
Table
pump group
4.12.14
coupling
centre align
05 Electrically domina
driven feed nt
pump group
secondary
pouring
01 Electrically domina
driven feed nt
Table 4.3.
pump group
20
secondary
pouring
06 Electrically
driven feed
pump oil
system
32
installation
01 Electrically
driven feed
Table
pump oil
4.13. 4
system
installation
07 Electrically domina
driven feed nt
pump oil
system
flashing
01 Electrically domina
driven feed nt
Table 4.5.
pump oil
6-10
system
flashing
08 Electrically domina
driven feed nt
pump group
trial run
01 Electrically domina
driven feed nt Table
pump group 4.13. 5
trial run
Booster pump
check
02 Booster pump
installation
04 Condensate domina
pump nt
installation
01 Condensate
33
pump check
01 Condensate Table
pump check 4.14.1
02 Condensate
pump
installation
01 Condensate
Table
pump
4.14.2
installation
03 Condensate domina
pump trial run nt
05 Water ring
vacuum pump
installation
01 Installation of
vacuum pump
06 Gland heater
air exhauster
installation
01 Gland heater
air exhauster
check and
installation
01 Gland heater
air exhauster Table 4.3.
check and 30
installation
07 Low pressure
heater
34
drainage pump
installation
01 Low pressure
heater
drainage pump
check
01 Low pressure
heater Table 4.3.
drainage pump 24
check
02 Low pressure
heater
drainage pump
installation
01 Low pressure
heater Table 4.3.
drainage pump 25
installation
04 Installation of
other
equipments
including
steam turbine
generator units
01 House service
pump
installation
01 House service
pump check
02 House service
pump
installation
01 House service
pump Table 4.3.
25
35
installation
02 Installation of
raw water
pump
01 Raw water
pump check
02 Installation of
raw water
pump
01 Installation of
Table 4.3.
raw water
25
pump
03 Condensate
make-up pump
installation
01 Condensate
make-up pump
check
01 Condensate
Table 4.3.
make-up pump
24
check
02 Condensate
make-up pump
installation
01 Condensate
Table 4.3.
make-up pump
25
installation
03 Condensate domina
make-up pump nt
trial run
01 Condensate domina
Table 4.3.
make-up pump nt
26
trial run
36
04 Deaerator
recirculating
pump
installation
01 Deaerator
recirculating
pump
installation
01 Deaerator
recirculating Table 4.3.
pump 24
installation
02 Deaerator
recirculating
pump
installation
01 Deaerator
recirculating Table 4.3.
pump 25
installation
03 Deaerator
domina
recirculating
nt
pump trial run
01 Deaerator
domina Table 4.3.
recirculating
nt 26
pump trial run
05 Other
equipment
installation
01 Steam turbine
oil
replenishment
tank
installation
01 Steam turbine
oil
Table 4.3.
replenishment
36
tank
installation
02 Auxiliary
steam headder
installation
01
Auxiliary Table 4.3.
steam headder 36
37
installation
03 Makeup water
tank
installation
01 Makeup water
Table 4.3.
tank
36
installation
04 Desuperheater
and
decompressor
installation
01 Desuperheater
and Table
decompressor 4.15
installation
05 Raw water
heater
installation
02 Raw water
Table 4.3.
heater
35
installation
06 Turbine hall
internal
recycling
pump
installation
01 Turbine hall
water
circulating
pump check
01 Turbine hall
water Table 4.3.
circulating 27
pump check
02 Turbine hall
water
domina
circulating
nt
pump
installation
01
Turbine hall domina Table 4.3.
water nt 28
38
circulating
pump
installation
03 Turbine hall
water
circulating
pump oil
piping
installment
01 Turbine hall
water
circulating Table
pump oil 4.18. 4
piping
installment
04 Turbine hall
water
domina
circulating
nt
pump trial
shipment
01 Turbine hall
water
domina Table 4.3.
circulating
nt 29
pump trial
shipment
07 Open
circulation
chilled wated
plant
installment
01 Open
circulation
cooling water
pump
examination
01 Open
circulation
Table 4.3.
cooling water
24
pump
examination
02
Open
circulation
cooling water
pump 39
installment
01 Open
circulation
Table 4.3.
cooling water
25
pump
installment
03 Open
circulation
domina
cooling water
nt
pump trial
shipment
01 Open
circulation
domina Table 4.3.
cooling water
nt 26
pump trial
shipment
04 Water filter
installment
08 Closed cycle
cooling pump
01 Closed cycle
cooling pump
check
01 Closed cycle
Table 4.3.
cooling pump
24
check
02 Closed cycle
cooling pump
installation
01 Closed cycle
Table 4.3.
cooling pump
25
installation
03 Closed cycle
domina
cooling pump
nt
trial shipment
01 Closed cycle
domina Table 4.3.
cooling pump
nt 26
trial shipment
09
Closed
circulating
water cooler
40
adjustment
01 Closed
circulating
water cooler
examination
01 Closed
circulating Table 4.3.
water cooler 34
examination
02 Closed
circulating
water cooler
installation
02 Closed
circulating Table 4.3.
water cooler 35
installation
10 Turbine hall
dredge pump
installation
01 Turbine hall
dredge pump
check
01 Turbine hall
Table 4.3.
dredge pump
24
check
11 02 Turbine hall
dredge pump
installation
01 Turbine hall
Table 4.3.
dredge pump
25
installation
03 Turbine hall
domina
dredge pump
nt
trial run
01 Turbine hall
domina Table 4.3.
dredge pump
nt 26
trial run
12 Turbine hall
domina
crane
nt
installation
01 Bridge crane
installation
41
01 Bridge rail domina Table
check nt 4.16. 1-1
02 Bridge crane
Table
aggregate
4.16. 1-2
installation
03 Bridge crane
rotating
Table
machine check
4.16. 1-3
and
installation
02 Other crane
installation
01 Crane Table
installation 4.16. 2-1
02 Cargo Table
handling test 4.16. 2-2
13 Heating
network
system
equipment
installation
01 Heating
network pump
installation
Heating
Table 4.3.
01 network pump
24
check
Heating
Table 4.3.
02 network pump
25
installation
Heating
domina Table 4.3.
03 network pump
nt 26
trial run
02 Installation of
the heaters in
heating
network
Heating
Table 4.3.
01 network heater
34
check
42
heater for 35
heating
network
14 Installation of
shutdown
cooling water
pump
01 Check of
shutdown
cooling water
pump
Check of
shutdown Table 4.3.
01
cooling water 24
pump
02 Shutdown
cooling water
pump
installation
Shutdown
cooling water Table 4.3.
01
pump 25
installation
03 Shutdown
domina
cooling water
nt
pump trial run
Shutdown
domina Table 4.3.
01 cooling water
nt 26
pump trial run
15 Diesel
generator
installation
01 Diesel
generator oil
tank
installation
Diesel
generator oil Table 4.3.
01
tank 36
installation
02 Diesel
generator
installation
43
Diesel
Table
01 generator
4.17. 1
installation
03 Diesel
domina
generator trial
nt
run
Diesel
domina Table
01 generator trial
nt 4.17. 2
run
16 Installation of
the platform,
ladder,
handrail and
cover plate of
turbine room
01 Installation of
the platform,
ladder,
handrail and
cover plate of
turbine room
Installation of
the platform,
ladder, Table 4.3.
01
handrail and 37
cover plate of
turbine room
05 Water
circulating
pump room
equipment
installation
01 Water
circulating
pump
installation
01 Check and
installation of
water
circulating domina
pump nt
foundation and
pump base
(body)
44
Check and
installation of
water
circulating domina Table
01
pump nt 4.18. 1
foundation and
pump base
(body)
02 Water
circulating domina
pump nt
installation
Table
Water 4.18. 2-1
circulating domina Table
01
pump nt 4.18. 2-2
installation Table
4.18. 2-3
03 Installation of
motor for
water
circulating
pump
Installation of
Table
motor for
4.18. 3-1
01 water
Table
circulating
4.18. 3-2
pump
04 Water
circulating
pump oil
system
installation
Water
Table
circulating
4.18. 4
01 pump oil
Table
system
4.18. 5
installation
05 Water
domina
circulating
nt
pump trial run
Water
domina Table
01 circulating
nt 4.18. 6
pump trial run
45
02 Rotary sieve
equipment
installation
01 Rotary sieve
check and
installation
Rotary sieve
Table
01 check and
4.19. 1
installation
02 Test run of
domina
rotary filter
nt
screen
Test run of
domina Table
01 rotary filter
nt 4.19. 2
screen
03 Trash remover
installation
01 Trash remover
check and
installation
Trash remover
Table
01 check and
4.20.1
installation
04 Large scale
flat plate steel
valve
installation
01 Large scale
flat plate steel
valve
installation
Large scale
flat plate steel Table
01
valve 4.21
installation
05 Water
circulating
pump room
crane
installation
46
01 Bridge crane
check and
installation
Table
4.16. 1-1
Bridge crane
Table
01 check and
4.16. 1-2
installation
Table
4.16. 1-3
03 Electric hoist
check and
installation
Electric hoist
Table
01 check and
4.16. 2-1
installation
06 Water
circulating
pump room
cooling water
pump
installation
01 Cooling water
pump check
02 Cooling water
pump
installation
Cooling water
Table 4.3.
01 pump
28
installation
47
07 Installation of
water
circulating
pump room
metal member,
platform,ladde
r and handrail
01 Installation of
water
circulating
pump room
metal member,
platform,ladde
r and handrail
Installation of
water
circulating
Table 4.3.
01 pump room
37
metal member,
platform,ladde
r and handrail
08 Water
circulating
pump room
flushing water
pump
installation
01 Flushing water
pump check
02 Installation of
flushing water
pump
Installation of
Table 4.3.
01 flushing water
25
pump
03 Trial run of
domina
flushing water
nt
pump
Trial run of
domina Table 4.3.
01 flushing water
nt 26
pump
48
06 Public water
pump house
and rain pump
house
equipment
installation
01 House service
pump
installation
01 House service
pump check
02 House service
pump
installation
House service
Table 4.3.
01 pump
25
installation
02 Fire pump
installation
01 Fire pump
check
02 Fire pump
installation
03 Rain pump
installation
01 Rain pump
check
49
02 Rain pump
installation
04 Installation of
hoisting
equipment
01 Crane check
and
installation
01 Crane check
Table
and
4.16. 2-1
installation
02 Cargo domina
handling test nt
05 Installation of
draining pump
01 Draining
pump check
02 Installation of
draining pump
03 Draining
pump trial run
07 Water
catchment
pump house
equipment
installation
01 Deep water
pump
installation
50
01 Deep water
pump check
02 Deep water
pump
installation
01 Deep water
Table
pump
4.22.2
installation
02 Pressure
boosting
(feedwater)
pump
installation
01 Pressure
boosting
(feedwater)
pump check
01 Pressure
boosting Table 4.3.
(feedwater) 24
pump check
02 Pressure
boosting
(feedwater)
pump
installation
01 Pressure
boosting
Table 4.3.
(feedwater)
25
pump
installation
03 Pressure
boosting domina
(feedwater) nt
pump trial run
01
03 Trash remover
equipment
installation
01 Trash remover
check and
installation
01 Trash remover
Table
check and
4.20.1
installation
04 Large scale
flat plate steel
valve
installation
01 Large scale
flat plate steel
valve
installation
01 Large scale
flat plate steel Table
valve 4.21
installation
05 Installation of
hoisting
equipment
01 inspection and
installation of
overhead
traveling crane
01 Table
inspection and 4.16. 1-1
installation of Table
overhead 4.16. 1-2
traveling crane Table
4.16. 1-3
02 Load test of
domina
overhead
nt
traveling crane
01
Load test of domina Table
52
overhead nt 4.16. 1-4
traveling crane
03 Electric hoist
overhaul and
installation
01 Electric hoist
Table
overhaul and
4.16. 2-1
installation
06 Water
purifying plant
installation
01 Water
purifying plant
equipment
inspection
01 Water
purifying plant Table
equipment 4.23. 1
inspection
02 Water
purifying plant domina
installation, nt
trial run
01 Water
purifying plant domina Table
installation, nt 4.23. 2
trial run
07 Sludge pump
equipment
installation
01 Sludge pump
check
02 Sludge pump
installation
03
Sludge pump
53
trial run
08 Combustion
engine main domina
body nt
installation
01 Combustion
engine main domina
body nt
installation
01 Foundation
preparation
Foundation Table
01
preparation 4.24.1
02 Adjustable
fixer(iron domina
gasket)installat nt
ion
Adjustable
fixer(iron domina Table 4.3.
01
gasket)installat nt 8
ion
03 Check and
installation of domina
pedestal and nt
base plate
Check and
installation of domina Table
01
pedestal and nt 4.24.2
base plate
04 Combustion
engine main
domina
body
nt
positioning
installation
Combustion
engine main domina Table
01
body nt 4.24.3-1
positioning
54
engine load nt 4.24.3-3
distribution
Shafting
domina Table
04 adjustment
nt 4.24.3-4
and connection
Sliding pin
system
clearance domina Table
05
measurement nt 4.24.3-5
and
adjustment
Table
Rotor turning
4.4.12-1
06 gear
Table
installation
4.4.12-2
Automatic
synchronizing Table
07
device 4.24.3-6
installation
05 Combustion
engine inlet domina
side nt
installation
See DL/T
5210.2
Gas handling table
system steel 4.4.1~Ta
01
structure ble 4.4.6,
installation Table 4.3.
1~Table
4.3. 4
Inlet chamber
Table
02 aggregate
4.24.4-1
installation
Air cleaning
and sound
Table
03 suppression
4.24.4-2
system
installation
06
Combustion domina
engine exhaust nt
part
55
installation
See DL/T
5210.2Ta
Exhaust ble
system steel 4.4.1~Ta
01
structure ble 4.4.6,
installation Table 4.3.
1-Table
4.3. 4
Exhaust frame
Table
02 and diffuser
4.24.5-1
installation
Draught flue
Table
03 aggregate
4.24.5-2
installation
Exhaust
domina Table
04 system seal
nt 4.24.5-3
check
01 07 Bypass
chimney
installation
Bypass
Table
01 chimney
4.24.6
installation
08 Foundation
baseplate
grouting
Table 4.3.
Foundation
11
01 baseplate
Table 4.3.
grouting
12
09 Housing
installation
Housing Table
01
installation 4.24.7
02 Combustion
engine main domina
body pipeline nt
installation
01 Combustion
engine main domina
body pipeline nt
installation
56
Combustion
engine main domina Table
01
body pipeline nt 4.24.8
installation
02 Oil system
domina
installation
nt
and flashing
Lubricating oil
Table 4.5.
01 system
6-9
installation
Fire resistant
Table 4.5.
02 oil system
5-2
installation
Lubricating oil
domina Table 4.5.
03 system
nt 6-10
flashing
Fire resistant
domina Table 4.5.
04 oil system
nt 5-3
flashing
09 Combustion
engine
auxiliary
device and
accessory
machinery
installation
01 Gaseous fuel
supply system
equipment
installation
01 Gaseous fuel
pressure
regulating
station module
installation
Gaseous fuel
pressure
Table 4.3.
01 regulating
33
station module
installation
02 Gaseous fuel
preposition
module
installation
57
Gaseous fuel
preposition Table 4.3.
01
module 33
installation
03 Gaseous fuel
domina
valve module
nt
installation
Gaseous fuel
domina Table 4.3.
01 valve module
nt 33
installation
04 Fuel gas
supercharger
installation
01 Fuel oil
treatment
system
installation
Fuel oil
Table 4.3.
processing
01 33 Table
module
4.3. 26
installation
02 Fuel oil
preposition
module
installation
Fuel oil
Table 4.3.
preposition
01 33 Table
module
4.3. 26
installation
04
Combustion
engine V
inhibitor 58
module
installation
Combustion
Table 4.3.
engine V
33
01 inhibitor
Table 4.3.
module
26
installation
05 Combustion
engine
atomizing air
pump
installation
Combustion
Table 4.3.
engine
33
01 atomizing air
Table 4.3.
pump
26
installation
03 Other
equipment
module
installation of
the
combustion
engine
01 Combustion
engine
auxiliary
module
installation
Combustion
Table 4.3.
engine
33
01 auxiliary
Table 4.3.
module
26
installation
02 Combustion
engine water
washing
module
installation
Combustion
Table 4.3.
engine water
33
01 washing
Table 4.3.
module
26
installation
59
03 Combustion
engine flame
failure
protection
module
installation
Combustion
engine flame
failure Table 4.3.
01
protection 33
module
installation
04 Combustion
engine air
handling
module
installation
Combustion
engine air
Table 4.3.
01 handling
33
module
installation
05 Combustion
engine
ventilation, domina
sealing nt
cooling system
installation
Combustion
engine Table 4.3.
ventilation, domina 30
01
sealing nt Table
cooling system 4.4.13
installation
06 Combustion
engine water
injection
module
installation
Combustion
Table 4.3.
engine water
33
01 injection
Table 4.3.
module
26
installation
60
(Seal) (Seal) (Seal)
Development Supervision Construction
organization organization organization
The construction management condition of unit project shall be inspected during the
construction and acceptance of unit project and the inspection results shall be filled in Table
4.2.2.
Table 4.2.2 ()Engineering construction management record of inspection
________ plant unit Project number:
Development
Project name
organization
Design organization
Design organization
Leader
Unit engineering
Development
construction
organization
Technical director
SN Construction management system and delivery performance inspection item Inspection result
9 Environmental protection
61
12 Subcontract unit aptitude management
Acceptance result:
4.2.3 The information listed in Table 4.2.3 shall be examined for the unit project acceptance;
the examing results shall be complete and meet the requirements of records management.
Table 4.2.3 () check table of quality control documents of unit project
________ plant unit Project number:
Expected Actual
SN Document name Check condition
copies copies
10 Construction record
62
Development organization Date
4.2.4 The letter of notice for engineering design alteration, materials substitutes and change in
design shall be numbered and registered and attached following registration form. The
register of letter of notice for the unit project design alteration and materials substitutes shall
be in accordance with those specified in Table 4.2.4.
Table 4.2.4 Letter of notice and registration form of design alteration and materials substitutes
________ plant unit Project number:
No. of amended
Original Chart number related Implementation
SN Letter of notice name contents in letter of
number to alteration performance
notice
Construction Supervision
Date Date
organization organization
4.2.5 Delivery test report of equipments and materials and quality certificate shall be
numbered, registered and attached following the registration form. The register of factory test
report of unit project equipments and materials and the quality certificate shall be in
accordance with those specified in Table 4.2.5.
Table 4.2.5 ( ) unit engineering facilities, material routine test report and quality certificate material
registration table
________ plant unit Numbering:
Total Original number of
Equipment, material testing report and Providing organization
SN page of report and quality Remarks
quality certificate material name of report
report certificate material
63
Filled by Date
64
Condition of equipment defect:
Construction organization
Date
Construction Manufacturing
organization organization
Supervision Construction
organization organization
Treatment suggestion:
Construction
Date
organization
Manufacturing
Date
organization
Supervision
Date
organization
Development
Date
organization
4.2.7 The process unit report to development organization after the treatment of equipment
defect; the development organization organiza organizations concerned to carry out inspection
and acceptance abd sign acceptance opinion and signature on the equipment defect treatment
report. The filling of equipment defect treatmen report shall meet the provisions of table 4.2.7.
65
Table 4.2.7 Equipment defect treatmen report single
Plant unit Project number:
Subentry project
Unit project name
name
Supervision organization:
Date
Acceptance
Acceptance opinion Acceptance signature
organization
Construction
Date
organization
Manufacturing
Date
organization
Supervision
Date
organization:
Development
Date
organization
66
4.2.8 The measurement tools used for construction inspection must be identified for
measurement and in the validity period. The used measurement tools must be registered
accurately according to those specified in Table 4.2.8 during the construction. The supervision
engineer shall inspect and verify the measurement tools registered in table.
Table 4.2.8 () measurement tools used for unit project registration form
Plant unit Project number:
Calibration
Measuring equipment (tool) Factory Measurement Accuracy
SN Type/model Validity Remarks
name number limit rating
period
67
Construction
Date Supervision organization Date
organization
4.2.9 The construction quality of inspection lot shall be inspected and accepted according to
the quality criteria of inspection item; the construction quality acceptance table of inspection
lot shall be filled in. In accordance with Table 4.2.1, if there is no main control inProperty
column, the table means general. It shall be made in the acceptance organization signature
column which goes beyond acceptance range; inspection lot construction quality acceptance
shall meet the provisions of table 4.2.9.
Table 4.2.9 () construction quality acceptance table of inspection lot
Plant unit Project number: Property: Table X. X. X
Subentry project name
Acceptance conclusion:
Construction
Date
organization
68
Supervision
Date
organization
Manufacturing
Date
organization
Design
Date
organization
Development
Date
organization
4.2.10 The construction quality of subentry project shall be accepted according to those
specified in Table 4.2.10 and the construction quality acceptance table of subentry project
shall be filled in. In accordance with table 4.2.1, slash shall be filled in the acceptance
organization signature column which is not belongs to the acceptance range.
Table 4.2.10 Subentry project quality acceptance table
________ plant unit Project number: Property:
Subsection project name
69
Acceptance conclusion:
Supervision organization:
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
4.2.11 The construction quality of subsection project shall be accepted according to those
specified in Table 4.2.11 and the construction quality acceptance table of subsection project
shall be filled in. In accordance with table 4.2.1, slash shall be filled in the acceptance
organization signature column which is not belongs to the acceptance range.
Table 4.2.11 ( )subsection project quality acceptance table
________ plant unit Project number: Property:
Unit project name
70
Acceptance conclusion:
Supervision organization:
Construction
Date
organization
Manufacturing
Date
organization
Development
Date
organization
4.2.12 The unit engineering quality shall be accepted according to those specified in Table
4.2.12 and the unit quality inspection and acceptance shall be filled in. In accordance with
table 4.2.1, slash shall be filled in the acceptance organization signature column which is not
belongs to the acceptance range.
Table 4.2.12 ( ) unit quality inspection and acceptance table
________ plant unit Project number:
SN Subsection project name Property Acceptance result Remarks
71
Acceptance conclusion:
Development organization :
Construction
Date
organization
Manufacturing
Date
organization
Development
Date
organization
4.2.13 Refer to table 4.2.13 for steam turbine generator units installation engineering quality
control point approval, record,compulsory provision delivery performance check. during the
process of implementing this standard, this can be adjusted according to actual situation.
Table 4.2.13 Steam turbine generator units engineering quality control point approval, record, compulsory
provision delivery performance and check item
72
Table of
Appearance
implementation
Unit Subsection Subitem quality Table
SN Name Approval Record performance of
engineering project project acceptanceand numbering
compulsory
approval
provisions
Foundation preparation of
turbine generators
Foundation settlement
2
observational record
Table 4.26.
4 Pedestal contact check
1-1
73
1-2
Table 4.26.
5 Bearing seat covering
1-3
Coupling floating
5
displacement records
Aggregate installation of
07 steam cylindr internal
component
74
bore centre align records
Labyrinth clearance
10 measurement adjustment
75
coupling joint
05
Fire resistant fluid system and
76
piping installation
Table 4.26.
1 Oil cooler tightness inspection
1-14
Table 4.26.
2 Check before oil tank sealing
1-15
06
Check before lubricate Table 4.26.
3
(sealing) oil flushing 1-16
Pedestal positioning
Table 4.26.
02 1 Generator rotor tightness test
1-18
77
Generator bearing bush
1 clearance measurement
records
Installation of seal of
generator end cap
13
Installation of seal of Table 4.26.
1
generator end cap 1-21
Exciter installation
Exciter clearance
2
measurement records
78
Carbon brush yoke installation
Clearance measurement
2
records of carbon brush yokes
79
records
Condenser positioning,
3
leveing and centering records
Table 4.26.
2 Condenser watering test
2-3
Condenser accessory
installation
05
Table 4.26.
1 Drain flash tank shelter
24
80
Aircooling system tightness Table 4.26.
1
test 2-5
81
Inspection and installation of Table
09 1
bypass system equipment 4.11.4
82
Flow passage part clearance
measurement, adjustment and
thrust disc orientation
83
installation records
84
Electrically driven feed pump
Table 4.26.
2 group lube oil cooler water
1-14
pressure test
Table 4.13.
Condensate pump installation
7
Table 4.3.
Installation of other
39
04 01 equipments including steam
Table 4.26.
turbine generator units
4-3
05 General tank container
1 positioning and centering
records
Table 4.26.
2 General tank container seal
2-4
85
Turbine hall installation of
hoisting equipment
Table 4.26.
1 General cargo handling test
4-2
Table 4.23.
Water circulating pump room 3
05
equipment installation Table 4.26.
5
86
02 1 Trial run of other pump
Table 4.23.
Public water pump house and
3
rain pump house equipment
Table 4.26.
installation
5
Installation of hoisting
equipment
04 Installation of hoisting
01 1
equipment record
02 1 Crane test
Table 4.23.
Water catchment pump house 3
07
equipment installation Table 4.26.
5
04
1 Large scale flat plate steel
87
valve installation record
Installation of hoisting
1
05 equipmentrecord
2 Crane test
6 Fixer installation
Module positioning
12
installation record
88
13 Fan installation record
Table 4.26.
3 Housing transparent check
6-3
Table 4.26.
3 Housing transparent check
6-3
Module positioning
1
installation record
89
4.3 General parts of steam turbine generator units
Turbine generators foundation preparation application scope: foundation check
preparation work before the installation of turbine generator main body, including foundation
check and geometric dimension checking, foundation bearing area roughening, baffle
installation within the process of baseplate grouting and stone bolt check.
4.3.1 See table 4.3. 1 for foundation check and geometric dimension checking, inspection
and acceptance
Table 4.3. 1 Foundation check and geometric dimension checking
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Smooth
Appearance inspection sureface,flawless,hole,nest,pitting Observation
surface and reinforcement exposion
90
ruler
4.3.2 See table 4.3. 2 for foundation bearing area roughening inspection and acceptance
Table 4.3. 2 Foundation bearing area roughening
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
91
Straight steel ruler
Chipping size mm Exceed iron gasket edge 10~30
measurement
4.3.3 See table 4.3. 3 for installation, inspection and acceptance of baffle within baseplate
grouting.
Table 4.3.3 Baseplate grouting inner baffle installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.3.4 See table 4.3.4 for stone bolt inspection and acceptance.
Table 4.3.4 Foundation bolt examination
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Alloy steel stone bolt material Meet the requirements of manufacturer Spectrum check
4.3.5 See table 4.3.5 for iron gasket preparation,inspection and acceptance
92
Table 4.3.5 Iron gasket preparation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.3.6 See table 4.3. 6 for installation inspection and acceptance of iron gasket.
Table 4.3. 6 Iron gasket installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Pedestal and iron gasket dominant mm Local tucked in width, depth all <
Contact
Iron gasket and iron 1/4 of side length (local0.05 feeler Inspecting with a feeler gauge
face gap dominant mm
gasket gauge)
a Each stack of iron gasket is less than or equal to three; five is acceptable under special circumstances; only one pair of
inclined iron gasket is allowed; a pair of inclined iron gasket shall shall be deemed as two.
b Stack ratio computing formula :Stack ratio= *100%
4.3.7 See Table 4.3.7 for preparation, inspection and acceptance of concrete block.
Table 4.3.7 Concrete block preparation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
93
Formwork installation Firm, sealing Observation
4.3.8 see table 4.3.8 for Fixer Installation inspection and acceptance
Table 4.3.8 Adjustible fixer installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Flat, smooth,air-hole-free,without
crack,burrs and rusty stain; size Observation,use the straight
Appearance inspection
shall meet the requirements steel ruler for measurement
of manufacturer
Adjustable height of spherical face Meet the requirements of Straight steel ruler
mm
pad manufacturer measurement
Distance between adjustable device Meet requirements of baseplate Straight steel ruler
mm
bottom surface and foundation grouting measurement
94
surface
4.3.9 See table 4.3.9 for installation inspection and acceptance of pedestal adjusting screw.
Table 4.3. 9 Pedestal adjusting screw installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Distance between pedestal and Meet requirements of baseplate Straight steel ruler
mm
foundation surface after adjustment grouting and adjustment measurement
4.3.10 See table 4.3. 10 for pedestal check, installation,inspection and acceptance.
Table 4.3. 10 Pedestal check and installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
95
Position meets the requirements of the
drawing;elevation allowable deviation Gradienter,gradienter and
Pedestal centering dominant mm is 1; deviation value direction shall straight steel ruler
be consistent; the level shall meet the measurement
requirements of manufacturer.
4.3.11 See table 4.3.11 for inspection and acceptance before steam turbine generator units
foundation secondary pouring.
Table 4.3.11 Check before steam turbine generator units foundation secondary pouring
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Buried spare parts pouring check Clean, without lacquer,and oil dirt Observation
Position of secondary pouring Do not affect pipeline expansion Check formwork position
4.3.12 See table 4.3.12 for steam turbine generator units foundation secondary pouring and
maintenance inspection and acceptance
Table 4.3. 12 Steam turbine generator unit foundation secondary pouring and maintenance
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
the mould Concrete strength dominant Meet the requirements of the drawing Check strength test report
4.3.13 See table 4.3.13 for foundation settlement observation, inspection and acceptance.
Table 4.3.13 Foundation settlement observation
96
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Complete data;accurate
After turbine chamber positioning
measurement;foundation differential
Before generator stator positioning Level measurement or examine
settlement leveing steam
and verify; compared with
After generator stator positioning turbine;centering and centre align
source data
every other day measurement
Before turbine generators baseplate
without obvious changes.
grouting
4.3.14 See table 4.3.14 for bearing seat (box) cleaning and check acceptance
Table 4.3. 14 Bearing seat (box) clean and check
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Environment temperature
above 5; kerosene height be
Oil penetration test dominant No leakage not less than up edge of the oil
return port; whitewash powder
observation maintained for 24h.
Pressure oil supply hole flange joint Complete circuit continuous contact
Color-painting test
surface without breaking mark
Vessel flange studding hole It shall not penetrate shell wall Test passage
97
surfaces or settle according to
requirements of the manufacturer.
Length of bodiless
dominant mm 1.5% of the black bronze perimeter
General segment
Black bearing 5% of black bronze perimeter; there
Total length of
bronze bush dominant mm shall be no bodiless section within PT check
bodiless section
bodiless 90bearing area
Upside-down bearing bush assembly Mismatch not allowed Check after steady nail
Not-tightened bolt;feeler
Bearing bush split gap mm <0.05
gauge check
98
and shaft Contact face dominant >75%,even
neck
Shape of contact point Dot shape
Jacking oil way, oil hole dominant Right and clear Test passage
Common piece 3
Quantity:
special Piece 5
Gasket Observation
Flat, smooth, burr free, curling and a
Appearance
full wafer
Alloy component material recheck Meet the requirements of manufacturer Spectrum check
100%Hardness check dominant Meet the requirements of manufacturer Check the inspection
99
report
20CrlMolVNbTiBSteel
Check the inspection
metallurgical phase spot dominant Meet the requirements of manufacturer
report
inspection
4.3.18 Inspection and acceptance of auxiliary device and accessory machinery foundation
preparation see table 4.3.18.
Table 4.3.18 Auxiliary device and accessory machineryfoundation preparation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Checking in accordance
Center deviation of foundation bolt
mm 10 with figure,Steel tape
hole
measurement
4.3.19 As for inspection and acceptance of auxiliary device and accessory machinery iron
gasket and stone bolt preparation and installation, see table 4.3.19.
Table 4.3. 19 Preparation and installation of auxiliary device and accessory machinery iron gasket and
stone bolt
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Iron gasket Physical dimension mm 10~20 wider than side of base Measuring with ruler
configuration Surface process No warping and burrs Observation
and Surveying calculation of
Taper liner iron gradient 1:10
installation straight ruler
100
Usually not less than or equal to 3
pieces; 5 under special circumstances;
Quantity of each stack Observation
there shall be one pair of taper liner
iron
Pre-buried method
Elevation mm
a Iron gasket shall be applicable to large pump unit like feed pump and water circulating pump . As for the small scale
accessory machine sharing commonbase, the requirements for iron gasket can be loosen.
4.3.20 See table 4.3.20 for auxiliary device and accessory machinery secondary pouring
inspection and acceptance
Table 4.3.20 Auxiliary device and accessory machinery secondary pouring
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
101
Internal part shall be higher than the
Pouring of concrete
external part; the internal base shall be
within the base
filled
Note 1: auxiliary device and accessory machinery secondary pouring shall meet the requirements of manufacturer; comply
with this provision if there is no regulation.
Note 2: If the small pump is with the casting iron pedestal, pedestal and stone bolt can be poured at the same time; auxiliary
device base and stone bolt can be poured at the same time.
4.3.21 See table 4.3.21 for installation inspection and acceptance of accessory machinery
bearing seat (bearing room).
Table 4.3.21 Installation of accessory machinery bearing seat (bearing housing)
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Horizontal integration Scatheless; local gap after tightening the Inspecting with a feeler
Check of mm
surface bolt <0.05 gauge
bearing
Scatheless; right installation, no leak of
housing Oil level gauge Observation
oil
4.3.22 Check, installation, inspection and acceptance of sliding bearing see table 4.3.22.
Table 4.3.22 Check and installation of accessory machinery sliding bearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
102
Without slag inclusion,air hole,drop pit Coal-soaked oil or
Black bronze check
and crack penetrating fluid check
4.3.23 See table 4.3.23 for check, installation, inspection and acceptance
Table 4.3.23 Check and installation of accessory machinery sliding bearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
103
Check of bearing coollar shrunk Good contact with roll body;parallel end Measure with vernier
ring and housing washer surface caliper
4.3.24 See table 4.3.24 inspection and acceptance of horizontal centrifugal pump
Table 4.3.24 General check of horizontal centrifugal pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Appearance inspection of the Without casting sand, burrs, air hole, crack
Observation
casting and scar; smooth and clean joint surface
4.3.25 See table 4.3.25 for installation inspection and acceptance of common horizontal
centrifugal pump
Table 4.3.25 Installation of common horizontal centrifugal pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
104
Elevation deviation mm 10 Measuring with level
4.3.26 See table 4.3.26 inspection and acceptance of horizontal centrifugal pump trial run.
Table 4.3.26 Horizontal centrifugal pump trial run
Inspection method
Inspection item Property Unit Quality criteria and measuring
instrument
Current meter
Working current of motor A Rated value
measurement
105
n1000r/min dominant mm 0.10
Measure the vertical
Bear 1000r/min<n2000r/min dominant mm 0.08
and horizontal direction
vibration
by using virometer
2000r/min<n3000r/min dominant mm 0.05
Note: small multistage centrifugal pump trial run; refer to requirements of feed pump trial run
4.3.27 See table 4.3. 27 for inspection and acceptance of commonvertical pump
Table 4.3. 27 Check of common vertical pump
Inspection method and
Inspection item Property Unit Quality criteria
instruments
4.3.28 See table 4.3.28 for installation inspection and acceptance of vertical pump. Table
4.3.28 Installation of common vertical pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
106
(foundation
Elevation deviation mm 5 Measuring with level
plate)
Levelness of base end surface dominant mm/m 0.05 Measure with gradienter
Measurement of plumb
Hub cap fixation Meet the requirements of the drawing
bob and straight steel ruler
4.3.29 See table 4.3.29 for trial run, inspection and acceptance of common vertical pump.
Table 4.3.29 Common vertical pump trial run
Inspection method and
Inspection item Property Unit Quality standard
measuring instrument
107
trial run Test of linkage among pump, Coordination with
outlet check valves and butterfly Meet the requirements of the drawing theelectric, heat
valve. engineering debugging
Listening to and
Normal,zero friction; without
Operation condition monitoring the gauge
abnormal vibration and shock
needle, hand feeling
Motor trial
Pressure of delivery side of Measure with pressure
run dominant Reach to rated value and keep stable
pump gage
4.3.30 See table 4.3.30 for inspection and acceptance of common fan installation
Table 4.3.30 Common fan installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
108
installation Measuring with levelling
Levelness deviation mm/m 2
rod
Measurement by using
>0.5%,In opposite direction with the
Installation of exhaust pipe dominant levelling rod and straight
gas flow
steel ruler
4.3.31 See table 4.3. 31 for blower trial run, inspection and acceptance.
Table 4.3.31 Blower trial run
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Measurement by using
Inlet negative pressure dominant Reaching the design value
vacuum meter
4.3.32 See table 4.3.32 for accessory machinery coupling assembly and centre align
inspection and acceptance.
Table 4.3.32 Accessory machinery coupling assembly and centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Cool
Coupling and mm 0~0.02
housing Measure with vernier
shaft assembly
Hot caliper
Assembly gap mm -0.02~0
housing
and
Contact between spindle
check Even distribution of imprint Paiting inspection
nose with taper and coupling
109
Radial dominant mm fixed:0.10,unfixed:0.12
1500>w^750 End
dominant mm fixed:0.05,unfixed:0.08
surface
Checking according to
Fuel inlet nozzle direction Correct
drawing
4.3.33 See table 4.3.33 for installation, inspection and acceptance of integrated device
Table 4.3.33 Installation of integrated device
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Equipment appearance Clean,in good condition without scar Observation and check
inspection and with complete components with drawing
110
reference line
4.3.34 See table 4.3.34 for inspection and acceptance of common heat exchanger.
Table 4.3.34 Check of common heat exchanger
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Clean,rustless,scatheless,flawless and
a
Appearance inspection without sundries, bleb and double Observation
skin
a Cooler is divided into plate type and tubular type; whole supply without on-site disassembly. If on-site disassembly is carried
out, refer to the requirements of manufacturer; only take water pressure test and appearance inspection for baffle heater.
4.3.35 See table 4.3. 35 for installation, inspection and acceptance of common heat
111
exchanger.
Table 4.3.35 Common heat exchanger installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Safety gate actuating pressure dominant Meet the requirements of manufacturer Hydraulic pressure test
4.3.36 See table 4.3.36 for installation, inspection and acceptance of common tank container
Table 4.3.36 Installation of common tank container
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
112
Inspecting after 24h
No-pressure water tank No leakage
watering
4.3.37 See table 4.3.37 for manufacture, installation, inspection and acceptance of metal
member, steel platform, ladder, handrail and cover plate.
Table 4.3.37 Manufacture, installation, inspection and acceptance of metal member, steel platform, ladder,
handrail and cover plate.
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Platform elevation
mm 5 Measurement in accordance
deviation
with data grade and glass
Liner, binding beam
mm 5 tube gradienter
elevation deviation
Platform
Steel structure combination
supports deviation of mm/m 1.5,And total value is 15mm Steel tape measurement
diagonal line
Handrail Levelness deviation mm/m 2,and the total height20mm Levelling rod measurement
113
Burr free, without sharp edge, glib
turning, firm welding, filed and
Appearance Observation
strickled welded joints; stable
supports
Footboard longitudinal
mm/m 10
Ladder levelness deviation Measuring with levelling
Weight of movable
kg/piece 30 Estimating
Cover plate covering plate
manufacture Installation of lifter and
Level with cover plate Observation
lewis hole
4.3.38 See table 4.3. 38 for inspection and acceptance of gear wheel (worm wheel) reducto
and increaser
Table 4.3.38 Check of gear wheel (worm wheel) reductor and increaser
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Horizontal integration Scatheless; local gap after tightening Inspecting with a feeler
Case mm
surface the bolt <0.05 gauge
check
Scatheless; right installation, no leak of
Oil level gauge Observation
oil
Oil line, oleophobic hole Clean, clear and without leakage Observation
114
Gear Along the tooth depth 65%
wheel
Paiting inspection
contact Along the tooth depth 75%
face
L50 mm 0.09~0.17
L=51~80 mm 0.10~0.21
L=81~120 mm 0.13~0.26
Gear set
L=121~200 mm 0.17~0.34 Dial gauge measurement or
flank
L=201~320 mm 0.2~0.42 pressure fuse measurement
gap a
L=321~500 mm 0.26~0.53
L=501~800 mm 0.34~0.67
L=801~1250 mm 0.42~0.85
L140 mm 0.06~0.11
Worm L1=41~80 mm 0.09~0.19
wheel
L1=81~160 mm 0.13~0.26 Dial gauge measurement or
set
L1=161~320 mm 0.19~0.38 pressure fuse measurement
flank
gap b L1=321~630 mm 0.26~0.53
L1=631~1250 mm 0.38~0.75
a L is cylindrical gear central distance or length of cone gear reference circle cone busbar; if the flank contact is not up to
standard, the manufacturer shall deal with it; manual rescrape is not allowed.
b L1Is worm wheel central distance
4.3.39 See table 4.3. 39 for steam turbine generator units general equipments installation
and implementation performance of compulsory provisions.
Table 4.3. 39 ( )Subsection projectTable of implementation performance of compulsory provisions
Unit engineering Installation of other equipments including steam Subsection project
name turbine generator units name
Delivery
SN Inspection item Related information
performance
115
coating shall be paited according to design requirements or after the
study of technical section.
Acceptance
conclusion:
Date Date
Relative position of bearing seat and With largest thermal expansion, sliding
dominant Observation
pedestal surface of bearing seat are not protruding
116
the pedestal edge but with some surplus
Bearing seat slippage dominant mm Meet the requirements of manufacturer Measure with dial gauge
2 See table 4.4.1-2 and figure 4.4.1 for inspection and acceptance of clearance
measurement and adjustment of bearing bush and oil catch
Table 4.4.1-2 Clearance measurement and adjustment of bearing bush and oil catch
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Axial Adjustment end a Meet the requirements of manufacturer Straight steel ruler
mm
clearance Electricity end b Meet the requirements of manufacturer measurement
Feeler gauge
Gap at both sides Meet the requirements of manufacturer
measurement
Top gap c dominant mm Meet the requirements of manufacturer Pressure fuse, outside
micrometer, Feeler gauge
Tightening force of bearing bush d Meet the requirements of manufacturer
measurement
Bearing bore contact face dominant 75%, and even Paiting inspection
117
Smooth surface,burr free, without drop
Pad appearance inspection Observation
pit, scratch and mechanical damage
PT check or coal-soaked
Pad bodiless check Bodiless black bronze
oil (4h~8h)
Contact between tile pad and oil inlet Contact tightly at all sides Paiting method inspection
Feeler gauge
Oil seal ring total clearance mm Meet the requirements of manufacturer
measurement
118
Bearing cover joint surface paint Painting sealing gum Observation
Joint surface bolt Fastening and well match with nut Observation
Diaphragm compaction
Aerography Cultrated Observation
circle edge corner angle
safety gate
Material and thickness of
diaphragm type safety Meet the requirements of manufacturer
gate diaphragm
2 See table 4.4.2-2 for the check of cleaning and check of high and intermediate
119
pressure cylinder.
Table 4.4.2-2 Cleaning and check of high and intermediate pressure cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
3 Check of cleaning and check of high and medium pressure inner cylinder steam inlet
pipe refer to table 4.4.2-3.
Table 4.4.2-3 Cleaning and check of high and medium pressure inner cylinder steam inlet pipe
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
120
inlet
4 Check of high and medium pressure cylinder nozzle box, parting sheet (suit), steam
seal (suit) see able 4.4.24.
Table 4.4.2-4 Check of high and medium pressure cylinder nozzle box, parting sheet (suit), steam seal
(suit)
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Parting sheet (suit), gland sleeve No radial mismatch; no notable axial Observation and hand
mismatch mismatch feeling check
5 Check of low pressure cylinder admission chamber, parting sheet(suit) and steam
seal (suit) see table 4.4.2-5.
Table 4.4.2-5 Check of low pressure cylinder admission chamber, parting sheet(suit) and steam seal (suit)
121
measuring instrument
Parting sheet (suit), gland sleeve No radial mismatch; no notable axial Observation and hand
mismatch mismatch feeling check
122
Opening inside shall be clean and
Inspecting with a feeler
Adjacent spider creep of shrunt on disc impurity-free; the gap shall meet the
gauge and record
requirements of manufacturer
Feeler gauge
Velocity level mm Meet the requirements of manufacturer
Adjacent two double measurement
ring expansion clearance Feeler gauge
Pressure level mm Meet the requirements of manufacturer
measurement
Ellipticity
Measurement by using
Shaft neck Non-cylindrical dominant mm 0.02
outside micrometer
degree
Measurement of internal
Coupling spigot coordination Meet the requirements of manufacturer diameter by using
outside micrometer
123
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Adjacent two stage steam Upper, lower cylinder fit together and
Check
Flange cylindr mismatch volume be in accordance with ex-work record
steam Bolt up force moment Meet the requirements of manufacturer Torque spanner
cylindr and Lock it before sealing. If one use
patching Vertical joint surface nut electric welding for locking; carry out
cylinder and steam cylindr spot dominant spot welding at nut and cylinder wall. Observation
combination welding Set seal welding position stipulated in
the requirements shall also be done.
2 See table 4.4.4-2 for high and medium pressure cylinder combination and the
clearance inspection, acceptance of joint surface.
Table 4.4.4-2 Clearance inspection of high and medium pressure cylinder combination and joint surface
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Steam
cylindr Horizontal integration dominant mm 0.03 feeler gauge cannot be tucked in As for the cold tightening
surface gap of high both from internal and external sides one third bolt, use the
124
pressure inside and outside feeler gauge for
cylinder. inspecting.
joint Inside low pressure; 0.05 feeler gauge shall not be tucked in As for the cold tightening
surface vertical outer shell and both from internal and external sides; the one third bolt, use the
dominant mm
horizontal integration certain tucked in part shall not exceed feeler gauge for
surface 1/3 of the packing strip width. inspecting.
3 See table 4.4.4-3 for positioning, centering, inspection and acceptance of steam
cylindr
Table 4.4.4-3 Positioning and centering of steam cylindr
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Measurement by using
large leveling rule,
coincidence level,
Steam cylinder planeness mm/m 0.20
precision level, horizontal
pipe and depth
micrometer
125
bore centre align.
1 Check and acceptance of centre alignment of bearing seat, steam cylindr and rotor refer
to table 4.4.5-1.
Table 4.4.5-1 Centre alignment of bearing seat, steam cylindr and rotor
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Note: a and b are right and left side clearance of horizontal split; c is top clearance
126
2 Check and acceptance of installation of low pressure inner cylinder refer to table
4.4.5-2.
Table 4.4.5-2 Installation of low pressure inner cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Measurement by using
Bracing stud gap at both sides of inner feeler gauge, inside and
dominant mm Meet the requirements of manufacturer
cylinder outside micrometer and
gauge
Measurement by using
Axial positioning key gap dominant mm Meet the requirements of manufacturer feeler gauge or dial
indicator
Measurement of feeler
Assemblage gap of the extraction
dominant mm Meet the requirements of manufacturer gauge and depth
point
micrometer
3 See table 4.4.5-3 for installation, inspection and acceptance of high and medium
pressure inner cylinder.
Table 4.4.5-3 Installation of high and medium pressure inner cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Measurement by using
Bracing stud gap at both sides of feeler gauge, inside and
dominant mm Meet the requirements of manufacturer
inner cylinder outside micrometer and
gauge
Measurement by using
Axial positioning key gap dominant mm Meet the requirements of manufacturer feeler gauge or dial
indicator
Assemblage gap of the extraction dominant mm Meet the requirements of manufacturer Measurement of feeler
127
point gauge and depth
micrometer
4 See table 4.4.54 for installation, inspection and acceptance of high pressure nozzle
box
Table 4.4.5-4 Installation of high pressure nozzle box
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
5 See table 4.4.5-5 for installation of high and medium pressure cylinder parting sheet(suit),
balance piston (loop), steam admission shunt ring and gland sleeve.
Table 4.4.5-5 Installation of high and medium pressure cylinder parting sheet (suit), balance piston (loop),
steam admission shunt ring and gland sleeve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
128
6 See table 4.4.5-6 for installation, inspection and acceptance of low pressure cylinder
parting sheet (suit), balance piston (loop), steam admission and gland sleeve. Table 4.4.5-6
Installation of low pressure cylinder parting sheet (suit), balance piston (loop), steam admission shunt ring
and gland sleeve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Diaphragm housing
Gap at both
ring Measuring with inside and
sides of radial mm Meet the requirements of manufacturer
Top and bottom of outside micrometer
location stud
balance piston loop
7 See table 4.4.5-7 for inspection and acceptance of low pressure cylinder inside bore
centre align.
Table 4.4.5-7 Low pressure cylinder inside component bore centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
8 See table 4.4.5-8 for inspection and acceptance of high and medium pressure
129
cylinder inside bore centre align.
Table 4.4.5-8 High and medium pressure cylinder internal component bore centre align
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.4.6 See table 4.4.6 for the inspection and acceptance of steam cylinder load distribution
Table 4.4.6 Steam cylinder load distribution
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Inspecting with a
Lug filling block bearing area and
dominant mm Good contact, the gap shall be <0.05 feeler gauge at both
sliding surface
ends
Dynamometer Front
Midair cylinder with
method load
Meet the requirements of manufacturer rotor; use dynamometer
distribution ratio Back
method for check
(cross ratio)
Lug contact bolt debouncing gap mm Meet the requirements of manufacturer Inspecting with a feeler
130
gauge
4.4.7 See table 4.4.7 for adjustment, inspection and acceptance of flow passage part
clearance measurement. See Annex A for data of manufacturer steam turbine flow passage
part.
Table 4.4.7 Flow passage part clearance measurement adjustment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Radial Block steam radial gland dominant mm Meet the requirements of manufacturer
clearance Parting sheet radial gland dominant mm Meet the requirements of manufacturer
If rotor is positioned
according to k value.
Make the measurement
Minimum axial throughflow clearance dominant mm Meet the requirements of manufacturer and push the rotor under
the conditions of half
solid cylinder and
complete solid cylinder.
4.4.8 See table 4.4.8 for measurement,adjustment, inspection and acceptance of labyrinth
clearance.
Table 4.4.8 Measurement and adjustment of labyrinth clearance
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
131
clearance manufacturer
piston
teeth
loop Steam seal tooth Meet the requirements of
dominant mm
steam radial clearance manufacturer
feeler gauge to measure axial
seal Flat Steam seal tooth Meet the requirements of clearance; use feeler gauge
dominant mm
tine radial clearance manufacturer to measure radial clearance;
Steam tooth axial Meet the requirements of stick rubberized fabric for
dominant mm
Stage clearance manufacturer check under the conditions
External teeth Steam seal tooth Meet the requirements of of complete solid cylinder.
dominant mm
gland radial clearance manufacturer
132
All shall be screwed in steam cylinder
flange; screw thread shall be lower
Screw thread part of steam cylinder than the flange surface; the verticality
dominant Observation
studding bolt of studding bolt and flange surface
shall meet the requirements of
manufacturer.
133
tape
Rolling rotor after steam turbine Uniform rotation in accordance with Rolling hand feeling,
covering actual situation; zero friction listening to the sound
2 See table 4.4.10-2 for inspection and acceptance of coupling reaming connection.
Table 4.4.10-2 Coupling reaming connection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Reaming
coupling Shaking degree change mm 0.02 Measure with dial gauge
before coupling reaming
134
and temporary connection
Corresponding coupling
Measurement of internal
bolt hole diameter dominant mm Meet the requirements of manufacturer
diameter meter
deviation after reaming
Measurement of internal
Bolt and nut coordination dominant Meet the requirements of manufacturer diameter volume by using
outside micrometer
Measuring external
Right tightening sequence, force diameter with depth
a
Bolt up dominant moment shall meet the requirements micrometer; torque
of manufacturer spanner or special tools
for hydraulic tensioning
adjusting
Gasket roughness Observation
gasket
a Generally, the bolt-up degree is measured by bolt elongation, fastening force moment or oil pressure of hydraulic tensioning
instrument
135
4.4.11 Sliding pin system clearance measurement and adjustment
Application scope: measurement and adjustment of sliding pin system clearance,
including sliding pin system gap adjustment, installation of bearing seat and steam cylinder
center beam and installation of pushing and pulling device.
1 See table 4.4.11-1 and figure 4.4.11 for the adjustment, inspection and acceptance of
Sliding pin system clearance measurement
Table 4.4.11-1 Sliding pin system clearance measurement and adjustment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Bearing seat
Platform plate
Locating plate
Platform plate
Locating plate
Low pressure cylinder end vertical pin gap Front and middle bearing seat vertical and horizontal pin gap
Bearing seat
Bearing seat
Pressure pin
Plateform seat
Platform plate
Front and middle bearing seat pressure pin gap Front and middle bearing seat connection bolt gap
136
2 See table 4.4.11-2 for the installation, inspection and acceptance of center beam
between bearing seat and steam cylinder.
Table 4.4.11-2 Installation of center beam between bearing seat and steam cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
3 See table 4.4.11-3 for the installation, inspection and acceptance of pushing and
pulling device.
Table 4.4.11-3 Installation of push and pull device
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
137
Application scope: check and installation of turning gear, including turning gear
cleaning check and the assembly of turning gear.
1 See table 4.4.12-1 for the inspection and acceptance of turning gear clearing.
Table 4.4.12-1 Turning gear clearing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Contact between
throwout and wobble
dominant Close joint Observation
wheel enclosure end
surface
2 See table 4.4.12-2 for the inspection and acceptance of turning gear assembling
Table 4.4.12-2 Turning gear assembling
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Hydraulic
Hydraulic motor and dominant Meet the requirements of manufacturer Measure with dial gauge
138
trochanterian alignment
Thrust bearing gap dominant mm Meet the requirements of manufacturer Measure with dial gauge
pressure
Pinion backlash mm Meet the requirements of manufacturer
barring
Torque spanner fastening
Bolt up force moment Meet the requirements of manufacturer
check
4.4.13 See table 4.4.13 for the installation, inspection and acceptance of middle and low
pressure cylinder communicating pipe
Table 4.4.13 Medium and low pressure communicating pipe installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Communicating pipe inside clearing Clean and rustless Observation and hand
Observation or oil
Weld bond tightness No leakage
penetration test
4.4.14 See table 4.4.14 for check of steam cylinder, main steam valve and adjustment steam
valve before thermal insulation and the check of turbine generators decorative sheet
Table 4.4.14 Check of steam cylinder, main steam valve and adjustment steam valve before thermal
insulation and the check of turbine generators decorative sheet
Inspection item. Property Unit Quality criteria Inspection method and
139
measuring instrument
4.4.15 See table 4.4.15 for the compulsory provision delivery performance check of
foundation preparation before the installation of turbine generators and iron gasket (block)
configuration
Table 4.4.15 Foundation preparation and iron gasket (block) configuration before installation of turbine
generators
_________ plant unit Project number:
Foundation preparation and
iron gasket ( block )
Unit engineering Main body installation of turbine
Subsection project name configuration before
name generator
installation of turbine
generators
Delivery Related
SN Inspection item
performance information
140
Instrument with the level 2 precision shall be used for settlement
observation. All observed data shall be recorded on the special record
book; protection shall be made to the settlement observation point
Acceptance
conclusion:
Date Date
4.4.16 See table 4.4.16 for the implementation performance of compulsory provisions for
subsection project and steam turbine main body installation
Table 4.4.16 Implementation performance implementation performance of compulsory provisions for
subsection project and steam turbine main body installation
________ engine Project number:
Unit engineering Steam turbine main body
Main body installation of turbine generator Subsection project name
name installation
Delivery Related
SN Inspection item
performance information
141
confirmation and signature for construction, equipment inspection and
defect treatment after reaching installation quality standard.
142
It shall inspect bolt and nut of steam cylinder according to the following
requirements:
(1)The screw thread in studding hole of bolt, nut and steam cylinder shall
be smooth and without rag; the matching between bolt and nut should not
be too loose or too tight. it shall be ablw to freely screw nut to the end by
hands; otherwise, it shall carry out research and treatment. There shall be
steel impression mark on bolt and nut of high pressure cylinder; they shall
be not exchanged randomly.
(2)As for contact plane of nut,steam cylinder or gasket with requirements
for hot tightening, Paiting inspection shall be applied to check the contact
is even or not.
(3)The screw thread of studding bolt for steam cylinder shall be entirely
screwed into flange of steam cylinder; the screw thread shall be lower
than the surface of flange; the verticality between studding bolt and
flange surface shall meet the requirements of manufacturer and shall be
less than or equal to0.50 in general; otherwise, it shall carry out research
7
and treatment.
(4)When the nut of bolt is tightened to the installation position in trial, the
screw thread of bolt shall be buckled where 2~3 buckles of nut are
exposed. When the shield nut is cooled and tightened to the installation
position, it shall ensure around 2mm clearance between top shield and top
bolt after properly fastening. The installation of tapered bolt for introduced
unit shall meet the requirements of manufacturer.
(5)Check the material of steam cylinder bolt and nut as required.
(6)The damaged screw thread shall be repaired and scraped; finally, it must
use triangular oil stone to polish the repaired and scraped area. If the screw
thread inside the studding hole need be repaired, it shall prepare special
screw tap.
(7)After inspecting and repairing screw thread, it shall use powder coating
with fine granularity and high temperature resistance for inunction
forcibly, or paint with lubricant required by the manufacturer; it shall
remove surplus paint and pack up bolt to avoid dust and clash.
143
Steam cylinder combination shall meet the following requirements :
(1)Before formal combination of the steam cylinder, non-paint trial
erection must be carried out. The closeness of joint surface shall meet the
requirements.
(2)If the manufacturer have no clear requirements for the steam cylinder
sealing paint, refer to the working pressure and temperature.
9
(3)As for the combined steam cylinder, the nut of vertical joint surface
shall be locked before the final sealing of steam cylinder. If electric
welding is used for locking, carry out spot welding at the nut and cylinder
wall. The position required by design requirements for sealing shall be
welded. Deformation caused by steam cylinder overheat shall be
avoided during welding.
The dimension of oil bag for oil hole on apical axis of lower bearing
shell shall meet the requirements of drawing. Generally, its depth shall be
between0.20~0.40mm; the area of oil bag shall be 1.5%~2.5% (larger
12 value for larger diameter of axle) of projected area of axle neck ; the axle
neck shall be tightly close to around oil bag. The oil pipe head of apical
axis must be firmly buried under black bronze and ensure to be clean and
smooth.
144
(6)Central position confirmation of turbine rotor at steam seal or oil catch
bore; rotor coupling centre align final measuring;
(7)Gasket thickness record of rotor final positioning among all coupling
flange rotor ;
(8)Clapboard centering;
(9)Measure the clearance of steam seal and throughflow part;
(10)Adjust and measure clearance of thrust bearing;
(11)Spectrum reinspection of demountable parts inside steam cylinder; ;
(12)Eliminate defects of spare parts inside steam cylinder;;
(13)Thoroughly clean up the inside of steam cylinder, pipe segment and
steam chamber; seal pipe orfice as well as socket and plug of
instrumentation
As for alloy steel materials and parts within the supervision scope, their
steel types shall be verified in manufacture, installation or overhaul to
14
prevent misusage. After assembling, comprehensive review shall be made
for a second time to confirmation no mistake before putting into operation
There must be quality certificate for shaft, impeller and blade of steam
turbine provided by the manufacturer; before installation, it shall refers to
relevant technical information provided by the manufacturer. If any
15
inadequate information or quality or quality problem is discovered, the
manufacturer shall be required to supplement inspection or take
corresponding treatment measures.
For high temperature bolt greater than or equal M32, the following
check shall be carried out before installation:
(1)Surface shall be smooth and clean, dent-free, rift-free, rust-free, and
other defects caused by other stress concentration.
17 (2) Carry out 100% spectrum check;High alloy steel bolt inspection area
shall be both ends;
(3)100% hardness check ;
(4)100% nondestructive inspection;
(5)20CrlMolVNbTiBSteel metallurgical phase spot inspection
Acceptance
conclusion:
145
Construction organization:(Seal) Supervision organization:(Seal)
Date Date
Observing with
Internal cleaning of Without casting sand, crack and sand hole,
Dominate magnifier with over five
enclosure and the internal surface shall show luster
times
Anti-looseness measure
for valve seat and internal Reliable and in good condition Observation
Cleaning
parts
and
Coloring method or
inspection Tightness of valve disc Continuously contact along the complete
Dominate drawing marks with
of valve and valve seat circle, and the width shall be uniform
pencil
body
Drainage holes Unimpeded Test passage
Fasteners
insurance on the
Steam
expansion Check against drawing
filter Correct, in good condition and reliable
clearance of and observe
screen
installation
position of mesh
Stroke of valve disc Dominate mm Meet the requirements of manufacturer Pushing and pulling, and
146
measuring with depth
gauge
Material
Dominate Meet the requirements of manufacturer Spectrum inspection
Valve
Hardness
cover bolt Dominate Meet the requirements of manufacturer Hardness inspection
Cold tightening moment Dominate Meet the requirements of manufacturer Torque spanner
2 See Table 4.5.1-2 for the inspection and acceptance on installation of steam port and
governing valve.
Table 4.5.1-2 Installation of Steam Port and Governing Valve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Elevation
mm 10
Measuring with steel tape
Deviation in the vertical and
mm 10
horizontal center lines
Level
The water bubble is in the middle Ordinary iron spirit level
The operating height or Dominate mm Meet the requirements of manufacturer Check against drawing
operating load of spring and measure with steel
147
tape
4.5.2 See Table 4.5.2 for the inspection and acceptance on installation of actuator.
Table 4.5.2 Installation of Actuator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Connecting rod assembly No deflection; flexible and no jam at joint Observation and actuation
Connection position of
Transmission Correct, firm and lock Observation
connecting rod
gear of
Space between piston Pushing, pulling and
connecting Dominate mm Meet the requirements of manufacturer
and bottom measuring
rod
Compression quantity of Pushing, pulling and
mm Meet the requirements of manufacturer
dish-type gasket measuring
148
Filter element Clean and intact; t he dimension meet the
Check against drawing
requirements of manufacturer
Slide valve
Unloading Flexible and block-free Trial operation
action
valve
Manual
screw rod for Block-free and the travel meet the
mm Trial operation
pressure requirements of manufacturer
regulation
Fly ball Adjusting nut In good condition and shall be locked Observation
or
Shaft neck protruded on
eccentric mm 10.2 Checking the marks
the top
strap
Trial operation
Trigger Binding of hook Intact and correct
of
Rotating gap with fly ball Measuring with a feeler
dropout Dominate mm Meet the requirements of manufacturer
or eccentric strap gauge
2 See Table 4.5.3-2 for the inspection and acceptance on installation of emergency trip
throttle.
Table 4.5.3-2 Installation of Emergency Trip Throttle
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
149
deformation
Contact between emergency trip Tightly contacted and no oil leakage after Trial operation,
sliding valve disc and valve seat closure observation
Positioning of emergency trip sliding The caulked joints of dowel pin, holding
Observation
valve devices screw and tally screw shall be compacted
Spring
Manual Tightness is proper Inspection
emergency
Hand grip
trip Dominate Hand grip is provided with shelters Observation
devices
Position of slide valve Dominate Positioning is correct Check against drawing
Actuation
Dominate Driving flexibly and without block Trial operation
150
manufacturer
3 See Table 4.5.3-3 for the inspection and acceptance on installation of emergency trip
devices.
Hand grip
Manual emergency trip Dominate Hand grip is provided with shelters Observation
devices
Position of
Dominate Positioning is correct Check against drawing
slide valve
Gap between
Measuring with feeler
shifter lever mm Meet the requirements of manufacturer
Electromagnet of gauge
and baffle ring
mechanical shutdown
Flexible and block-free; the slide valve
Actuation Dominate Trial operation
can be controlled accurately
Implementation
Block-free in the whole travel route Test inspection
pusher arm
151
Travel switch
mm Meet the requirements of manufacturer Measuring with a ruler
spacing
Indicating
Consistent with the actual position Checking
position
Indicator or travel switch Actuation Dominate Driving flexibly and without block Trial operation
4 See Table 4.5.34 for the inspection and acceptance on installation of other security
operating equipments.
Table 4.5.3-4 Installation of Other Security Operating Equipments
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Inspection for
connection tube Meet the requirements of manufacturer Spectrum inspection
Oil drive
material
intercepter
Position is correct; firm and tight; without
valve Assembling Check against drawing
leakage
152
magnetic valve
4.5.4 Inspection and acceptance on installation of main oil pump specified in Table 4.5.4.
Table 4.5.4 Installation of Main Oil Pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
153
The radial and axial total
Measuring with a vernier
clearance of sealing ring on the Dominate mm Meet the requirements of manufacturer
caliper or a feeler gauge
pump shell side
Clearance in the front and back Meet the requirements of manufacturer and
Measuring with block
sides of vane wheel and axial Dominate mm larger than the maximum expansion
gauge
clearance of pump shell difference
Vent port of pump body Unimpeded and without blocking Ventilation purging
Note: It is mainly the centrifugal main oil pump that the impeller of pump shaft and the high-voltage rotor of steam turbine
connected as a whole
4.5.5 Installation of the equipments and pipelines of fire resistant fluid system
Application scope: It is applicable to the installation of equipment and pile of fire resistant
fluid system, including installation of fire resistant oil tank, oil pump, oil cooler, oil filter and
accumulator and the cycle flushing of fire resistant oil system, piping installation and fire
resistant oil system.
1 See Table 4.5.5-1 for the inspection and acceptance on installation of fire resistant oil tank,
oil pump, oil cooler, oil filter and accumulator.
Table 4.5.5-1 Installation of Fire Resistant Oil Box, Oil Pump, Oil Cooler ,Oil Filter and Accumulator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Internal cleaning of
Clean, without welding slag or sundries Observation
oil tank
2 See Table 4.5.5-2 for the inspection and acceptance on installation of fire resistant oil
154
system pipe.
Table 4.5.5-2 Installation of Fire Resistant Oil System Pipe
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
3 See Table 4.5.5-3 for the inspection and acceptance for the cycle flushing of fire resistant
oil system.
Table 4.5.5-3 Cycle Flushing of Fire Resistant Oil System
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
155
Has been installed according to
Thermal instrumentation System inspection
requirements
Chemical examination
Flushing oil The oil is qualified and sufficient
and inspection
Cycle flushing pressure Dominate Meet the requirements of manufacturer Pressure gage
Measuring with
Cycle flushing oil temperature Dominate 54~60
thermometer
1 See Table 4.5.6-1for inspection and acceptance on installation of integrated oil tanks
Table 4.5.6-1 Installation of Integrated Oil Tanks
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Inspection Appearance of oil tank In good condition without scar and with
Observation
of and equipment complete components
integrated Check in accordance with
Oil tank opening complete and correct
oil tanks drawing
Clean the internal oil dominant Free from scales, welding slag, clean, Observation
tank paints with internal surface, which do not
dissolve in the turbine oil, are free from
156
shedding; paints dissolvable in the turbine
oil must be removed.
Oil tanks are cleaned Reboring, gas cutting and welding shall
dominant
and sealed not be carried out after sealing
Ladder footpath,
in according to Table 4.3.37 Observation
platform and handrail
2 See Table 4.5.6-158 for inspection and acceptance on installation of oil coolers.
Table 4.5.6- 157 Installation of Oil Coolers
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
157
Test water quality clean and free from foreign matters Visual observation
a Coolers are divided into panel coolers and tube coolers, all of which are integrally delivered, shall not be disassembled on-site;
if disassembly is carried out on-site, disassembly shall be implemented according to meet the requirements of manufacturer.
b Leak test shall be carried out on either the water side hydraulic pressure or the oil side air pressure according to the site
condition.
4 See Table 4.5.6-4doe check, installation, inspection and acceptance of vertical oil pumps
Table 4.5.6-4 inspection And Installation of Vertical Oil Pumps
158
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Axial direction of
Push and pull, measure
the on the dominant mm 3~4
with depth gauge
pressure side
5 See Table 4.5.6-5 for the checking, installation, inspection and acceptance of the horizontal
oil pumps.
Table 4.5.6-5 Inspection And Installation of Horizontal Oil Pumps
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
159
Pump base is horizontal and the direction
Installation of oil pumps Leveling rod
is correct
Filter screen of inlets Clean, free from damage, firmly fixed Observation
6 See Table 4.5.6-6 for inspection and acceptance of oil pump trial operation
Table 4.5.6-6 Oil Pump Trial Operation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Inlet tube flashing for It may be connected with oil pump after
Observation
plunger pumps proving qualified
Check
Start-up oil level of gear
before Meet the requirements of manufacturer Observation
oil pump
trial run
Fixed value of electric and
Check electricity, thermal test record and
heat engineering
all of them are qualified
protection
Pump set vibration dominant mm Meeting the requirements of DL 5011 Measuring with vibrometer
Current meter
Motor working current Rated value
measurement
7 See Table 4.5.6-7 for inspection and acceptance on installation of oil ejectors and worm
wheel pumps.
160
Table 4.5.6-7 Installation of Oil Ejectors And Oil Worm Wheel Pumps
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
ejectors throat
Back stop plate Flexible operation, free from jam Trial run
Measuring with plumb it shall be vertical and the direction of Measuring with plumb
bob the flange shall be correct. bob
Rubber seal
In good condition without damage
washers
Nozzle Coated with lubricating grease as
Assembling Observation
ring required by the manufacturer
Installation
Baffle and filter
of worm Clean and firmly fixed
screen
wheel
Flat, smooth and the plane shall not
pumps Subplates on the nozzle
higher than the oil drainage flange end Observation
ring
face of the pump body
161
Deviation in the vertical and
mm 10 Steel tape measurement
horizontal center lines
level of the equipment the water bubble is in the middle Ordinary iron leveling rod
Sludgeless
Coupling centre alignment mm Meeting the requirements of DL 5011
oil pump
9 See Table 4.5.6-9 for installation and inspection and acceptance of lubricating pipes and
jacking oil pipes
Table 4.5.6-9 Installation of Lubricant Pipes (Jacking Oil Pipes)
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Valve cleaning the inside is clean, without leakage Hydraulic pressure test
Installation direction of
dominant Valve stem horizontal or downward Check
valves
Gasket Oil proof, high temperature resistant, Check, Push and pull,
Material dominant
material without using plastics or rubber measure with depth gauge
of the Thickness mm Ordinary1
162
joint Internal Bigger than the flange internal diameter
mm
surface diameter 2~3
On-site pressure gage and the position and number are correct and
Checking
thermometer conform those specified in DL/T 5210.4
10 See Table 4.5.6-10 for inspection and acceptance of the lubricating oil system, sealing oil
systemic circulation.
Table 4.5.6-10 Cycle Flushing of Lubricating (Sealing) Oil System
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Cycle
flushing Systematic inspection (including The installation is inspection
emergency discharge system) finished, the
connection is correct
and meet the
163
requirements of the
drawing
Highest Measurement by
Flushing oil temperature
temperature80 thermometer
a Granularity counting and chemical examination of oil samples could be carried out according to the site condition.
4.5.7 See Table 4.5.7 for adjustment and inspection of implementation performance of
subsection project compulsory provisions for lubricating oil system equipment installation.
Table 4.5.7 adjustment and Inspection table for implementation performance of subsection
project compulsory provisions for lubricating oil system equipment installation
164
performance information
There shall be protective cover for manual emergency trip device; the
4
positioning billiards shall be able to correctly position slide valve.
165
looseness; the air port on the slide valve shall be smooth; the iron core
and slide valve shall be firmly connected.
The oil exit pipe for oil tank accident shall be connected to the accident
oil drainage well specified in design. Before unit trial operation, it shall
be formally installed and confirmed to be smooth.
The inspection and installation of oil piping valve shall be in accordance
with the following requirements:
Generally, two gate valves shall be set up for accident oil discharge
valve; the gate valve close to oil tank shall be made of steel. The
7
operation handwheel of accident oil discharge valve shall be set up at
over 5m away from oil tank and there shall be more than two passages.
The handwheel shall be set up with protecting glass.
There shall be clear marking on switch direction of valve; rising stem
valve shall be used instead of reverse valve. The valve stem of pipe shall
be laid flat or downward to prevent valve disc from falling off and
cutting off oil line during operation.
Drilling hole, gas cutting and welding shall not be carried out on the oil
8 pipe after it is cleaned up and sealed, otherwise, cleaning, inspection and
sealing must be carried out again.
Acceptance
conclusion:
166
Construction unit: (seal) Supervision unit: (seal)
Date Date
167
horizontal side length and side edge
length of the iron gasket (filling
block).
168
Observation, trial
Compound insulation
the inner part is clean and unimpeded ventilating of the clean
driving pipes
compressed air
Floating
dominant mm 0.03
displacement
Measure with dial
Flutter in the radial
gauge
Solid coupling direction of the mm 0.04
circumference
Standard measuring
Test pressure dominant MPa Meet the requirements of manufacturer
with pressure gauge
4.6.3 See Table 4.6.3 for inspection and acceptance of stator hoisting and emplacement
Table 4.6.3 Stator Hoisting Positioning
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
169
Stator air duct, ventage, ventilation Clean, free from dust, scrap and foreign
Observation
slot bodies
Flange studding hole of the stator It shall not penetrate shell wall Observation
Appearance of the joint Flat, smooth, free from burr and radial
dominant Observation
surface delve
Stator
Tighten 1/3~1/2bolts,
end cap
inspecting with a feeler
flange Joint surface gap dominant mm 0.05
gauge on the horizontal
and vertical joint surface.
Appearance of the seal packing The inwall is smooth and sections are
Observation
delves of the joint surface uniform
Glue filled pore canal Unimpeded, alien to the groove Ventilation inspection
4.6.4 See Table 4.6.4 for inspection and acceptance of stator tightness test
Table 4.6.4 Stator Tightness Test
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Winding insulation
Meet the requirements of Measuring with 1000 V
and electric dominant
manufacturer insulation resistance meter
resistance
Water Temporarily filter
Screen
pressure screen 200 Observation
mesh
Pretest specification
Winding insulation
Meet the requirements of Measuring with 1000 V
air and electric dominant
manufacturer insulation resistance meter
pressure resistance
170
air
Water accumulated
Flush out Inspection of gas injection
inside
Water
Winding insulation
pressure Meet the requirements of Measuring with 1000 V
Posttest and electric dominant
manufacturer insulation resistance meter
inspection resistance
Winding insulation
Gas Meet the requirements of Measuring with 1000 V
and electric dominant
pressure manufacturer insulation resistance meter
resistance
4.6.5 See Table 4.6.5for inspection and acceptance of insertion of generator rotors
Table 4.6.5 Insertion of Generator Rotor
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Meet requirements of
Electricity and thermal examination DL/T5161.1~5161.17 and
DL/T5210.4
4.6.6 See Table 4.6.6 for inspection and acceptance of pedestal mounting for inlet and outlet
water
Application scope: this table is applicable to the double-water internal cooling generator set.
Table 4.6.6 Inlet and Outlet Water Pedestal Mounting
Inspection method and
Inspection index Unit Quality criteria
Property instrument
171
Flat, smooth, free from burr and
Support base plates contact pedestals tightly contacted with the Observation
pedestals
The axial distance between the water Meet the shafting expansion
inlet cover and the water inlet stub dominant mm requirements and normally is Straight steel ruler measurement
pipe around 35
Contact with the rotor Tightly contacted and have bouncy Observation
Water 0.5, uniform on the right and left
deflector Radial clearance mm side and the crest is slightly bigger Inspecting with a feeler gauge
than the butt end
4.6.7 See Table 4.6.7 for installation and inspection of generator end cap bearings.
Application scope: this part is applicable to the inspection of generator stator emplacement,
including the installation of generator end cap bearings
Table 4.6.7 Generator End Cap Bearing Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Shaft bearing cover contact with the The expose is uniform, free from
Painting inspection
bore lateral part looseness and jam
172
boards external tile covers
The gap between the shaft neck crest Meet the requirements of Pressure fuse, measurement by
dominant mm
and the bearing bush manufacturer using outside micrometer
Installation of dowel pins on the There are some clearance of the Push and pull, measure with
bearing bush crest periphery and the bottom depth gauge
4.6.8 See Table 4.6.8 for inspection and acceptance of adjustment of air gap and magnetic
force center
Table 4.6.8 Adjustment of Air Gap And Magnetic Force Center
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
4.6.9 See Table 4.6.9 for inspection and acceptance of fan gap adjustment
Table 4.6.9 Fan Gap Adjustment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
173
Fan blade fastens the Meet the requirements of
dominant Torque spanner
moment manufacturer
Inspection of fan blades by The noise shall be solid and Knock fan blades of the two
dominant
listening to the sound uniform, free from mute sides with a copper rod
Gasket Observation
Match with the inner end Inner end caps fall into the seam
Observation
cap seam and compact the bottom seam
4.6.10 See Table 4.6.10 for inspection and acceptance of sealing pad installation
Table 4.6.10 Sealing Pad Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
174
The first and second half tiles
shall be upended on the panel
Split contact area dominant >75%, uniform
and carry out painting inspection
of the division plane.
4.6.11 See Table 4.6.11for inspection and acceptance of steam turbine - generator coupling
centre alignment
Table 4.6.11 Coupling Centre Alignment Of Steam Turbine - Generator
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Deviation of measured
Coupling central height difference
center value and reserve value dominant mm 0.02
deviation required by the
manufacturer
175
reserve value required by
the manufacturer
4.6.12 See Table 4.6.12 for installation and inspection of generator oil catch installation
Table 4.6.12 Generator Oil Catches Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
End Edge thickness of the oil Push and pull, measure with
mm 0.1~0.2
cap oil catch plate depth gauge
catch Oil catch plate margin Free from zigzag type and warp Observation
Electric resistance for the Meet the requirements of Measuring with 500 V insulation
dominant M
ground insulation manufacturer , normally>0.5 resistance meter
4.6.13 See Table 4.6.13 for inspection and acceptance of the installation of seal of generator
176
end cap
Table 4.6.13 Installation of Seal of Generator End Cap
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Meet requirements of
Electricity and thermal examination DL/T5161.1~5161.17 and Examination record
DL/T5210.4
4.6.14 See Table 4.6.14 for inspection and acceptance of the installation of hydrogen cooler
Table 4.6.14 Installation of Hydrogen Cooler
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Free from
deformation, clean,
Enclosure
the paint has no
shedding
Meet the
Hydraulic Measuring with pressure
Test pressure dominant MPa requirements of
pressure test gauge
manufacturer
177
tightness dominant No leakage Comprehensive inspection
3%Total cooling
Allowable plug pipe number Observation
tube number
Connected, have
enough expansive
force and the
Installation of wind-shielding rubber Observation
concave formed by
the rubber is in the
airflow direction.
Meet the
Materials dominant requirements of
Joint surface pad manufacturer
(filling)materials Meet the
Section size dominant mm requirements of
manufacturer
Installation of Flat, smooth, in good
hydrogen condition and have
appearance
coolers adequate elastic
Compensate gasket property
Meet the
Thickness mm requirements of
manufacturer
Appearance is
beautiful, convenient
Air release and installation of water for operation,
Observation
blow-down pipes connect to the
discharge pipe by
water drain funnel
Inspection Drawing, crossing rotors Free from impact and damage Observation
178
of stators Stator air duct and Clean, free from dust, scrap and
Observation
and rotors ventage foreign bodies
Foundation frame
Inspecting with a feeler gauge on
contacts with the Contact tightly
the periphery.
pedestal
2 See Table 4.6.15-2 for inspection and acceptance of the exciter shaft bearing installation
Table 4.6.15-2 Exciter Shaft Bearing Installation
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
Thickness Ordinary mm 3
of the Crossed Push and pull, measure with
single with lead mm >5 depth gauge
sheet wires
Longitudinal
mm/m Next to shaft neck Levelness
level
Shaft bearing base measure with gradienter
Transverse
mm/m 0.20
levelness
3 See Table 4.6.15-3for the inspection and acceptance of coupling Centre alignment of
exciters
Table 4.6.15-3 Coupling Centre Alignment of Exciters
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
180
values
Radial direction flutter of the rotor Meet the requirements of Measure with dial gauge after
dominant mm
end manufacturer coupling bolt on
4 See Table 4.6.15-4 for inspection and acceptance of installation of dowel pins and outer
covers to the exciter pedestals
Table 4.6.15-4 Pedestal Dowel Pin and Outer Cover Installation to the Exciter
Inspection method and
Inspection item Unit Quality criteria
Property measuring instrument
5 See Table 4.6.15-5 for the adjustment of the exciter air gap and the inspection and
acceptance of magnetic center.
Table 4.6.15-5 Adjustment of Exciter Air Gap and Magnetic Center
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Note: It is applicable to the installation of exciter with AC brushless excitation system and not applicable to the installation of
exciter with auto excitation type static state excitation system
6 See Table 4.6.15-6 for the adjustment of exciter fan, windshield and oil catch gap.
Table 4.6.15-6 Adjustment of Exciter Fan, Windshield and Oil Catch Gap
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Fan blade inspection Fan is intact without damage and Knocking and listening
181
the sound is normal
7 See Table 4.6.15-7 for the inspection and acceptance on installation of air cooler.
Table 4.6.15-7 Installment of Air Cooler
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Note: It is applicable to the installation of exciter with AC brushless excitation system and not applicable to the installation of
exciter with auto excitation type static state excitation system
4.6.16 See Table 4.6.16 for the inspection and acceptance on installation of carbon brush
yoke
Table 4.6.16 Installation of Carbon Brush Yoke
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
182
other sundries
Note: This table is applicable to the installation of exciter with auto excitation type static state excitation system
4.6.17 See Table 4.6.17 for the inspection and acceptance of air pressure test for whole set
of generator.
Table 4.6.17 Air Pressure Test for Whole Set of Generator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
183
bushing of main manufacturer, and is generally
shaft 0.07~0.13
Gasket material
Oil proof gasket
Circumference
Coupling mm 0.10 Measuring with flat bevel
deviation
centre scale slit method, feeler
End surface
Installation alignment mm 0.10 gauge or dial indicator
deviation
Appearance inspection
Mechanical sealing Without leakage and heating
and hand feeling
2 See Table 4.6.18-2 for the inspection and acceptance on installation of other equipments.
Table 4.6.18-2 Installation of Other Equipments
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
184
drawing
4.6.19 Installation of the equipments and pipelines of internal cooling water system
Application scope: It is applicable to the installation of equipment and pipe of generator
internal cooling water system, including installation of internal cooling water pump, cooling
water tank, cooler, ion exchanger, internal cooling water conduit and the flashing of internal
cooling water system.
1 See Table 4.6.19-1 for the inspection and acceptance on installation of internal cooling
water pump.
Table 4.6.19-1 Installation of Internal Cooling Water Pump
Inspection method and
Inspection item Property Unit Quality criteria
instrument
185
Meet the requirements of
Axial clearance of bearing Measuring with depth gauge or
mm manufacturer, and is generally
at expansion end pressure fuse
0.30~0.40
2 See Table 4.6.19-2 for the inspection and acceptance on installation of cooling water tank,
cooler and ion exchanger.
Table 4.6.19-2 Installation of Cooling Water Tank, Cooler and Ion Exchanger
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Material quality
Stainless steel Observation
water Water level gauge Clean, transparent and with shield Observation
tank
Liquid level annunciator Flexible, accurate and reliable Test check
186
Material quality Stainless steel Observation
3 See Table 4.6.19-3 for the inspection and acceptance on installation of internal cooling
water pipe.
Table 4.6.19-3 Installation of Internal Cooling Water Pipe
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
187
Quantity and position is correct
Installation of pressure gage,
and meet the requirements of
thermometer and measuring orifice
DL/T 5210.4
4 See Table 4.6.19-4 for the inspection and acceptance of internal cooling water system
flashing.
Table 4.6.19-4 Internal Cooling Water System Flashing
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
188
Clean without rust or sundries and
Appearance the sight hole is smooth, clean and Disassembly inspection
transparent
Measurement based on
Position deviation mm 10
reference line
2 See Table 4.6.20-2 for the inspection and acceptance on installation of gas system
pipeline.
Table 4.6.20-2 Installation of Gas System Pipeline
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Measuring by suspending a
Vertical misalignment Dominate mm 0.15% of the total height, and 7
plumb bob along total height
3 See Table 4.6.20-3 for the inspection and acceptance of gas pipeline gas pressure test.
Table 4.6.20-3 Gas Pressure Test for the Gas Pipeline
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
189
nitrogen
Calculation according to
Average pressure drop each hour Dominate MPa 0.1% initial pressure
measured data
4.6.21 See Table 4.6.21 for the inspection for implementation performance of subsection
project compulsory provisions of installation of generator and exciter.
Table 4.6.21 Inspection table for implementation performance of subsection project compulsory provisions
for installing generator and exciter
_________Unit Project number:
Main body installation engineering of Subsection project
Unit project name Installation of generator and exciter
turbine generators name
Implementation Related
SN Inspection item
performance information
190
When settlement observation is carried out for foundation, the
observation work shall be carried out together with at least the
following procedures:
(1) After curing period for foundation expires (with this measured
value as source data);
(2) Before and after all steam cylinder and generator stator of steam
turbine are positioned;
(3) Before concrete is poured by steam turbine and generator for
5
second time;
(4) After commissioning test of the complete set.
As for collapsible loess area, it shall properly increase measuring
times.
The settlement observation shall be carried out by instrument of Grade
2 precision. The observed data for each time shall be recorded at
special record book and the settlement observation point shall be
preserved properly.
The dimension of oil bag for oil hole on apical axis of lower bearing
shell shall meet the requirements of drawings. Generally, the depth
shall be between 0.20~ 0.40mm; the area of oil bag shall be
6 1.5%~2.5% (larger value for larger diameter of axle) of projected area
of axle neck; the axle neck shall be tightly close to around oil bag. The
oil-pipe head of apical axis must be firmly buried under black bronze
and ensure to be clean and smooth.
The insulated parts for insulating shaft current of generator and exciter
shall be smooth and clean and free of warping and defect; its thickness
shall be even and with good insulating property. After installation, all
7
of them shall be measured by 1000V insulation resistance meter. The
insulation resistance shall meet the requirements; generally, it shall be
0.5M
The axial clearance values for bearing bush and shaft shoulder as well
as air fan and air damper of generator shall meet the requirements of
9
manufacturer to ensure there is no friction under full load condition
and rotor thermal expansion.
191
The official closing of generator end cap shall meet the following
requirements:
Before end cap closing, it shall carefully check the inside of generator,
where shall be free of foreign bodies; all parts shall be in good
condition and all fit clearance shall meet relevant requirements.
The check test of relevant electric and thermal meter shall be
completed and it shall be confirmed and signed jointly with relevant
personnel.
When rubber strip is used for gland packing of hydrogen-cooled and
water-hydrogen-cooled generator, its section size shall meet the
requirements and there shall be adequate elasticity and compression
amount.
When colloidal substance is used for gland packing, it shall be filled
according to the method required by the manufacturer and it shall pay
10 attention to the following two points: It shall be clean inside the
seal groove, which shall be fully filled with paint; then it shall tighten
the bolt between vertical and horizontal surface of end cap; When
compressing filled sealing material, it shall start from the filling
opening of the upper part; when the fillings exude from the next
adjacent hole, it shall block the previous hole with plug and continue
to pressurize and fill the next hole until filling all grooves.
As for the joint surface between end cap and platen as well as end cap
and casing of air-cooling and double-water internal cooling generator,
it shall tightly sealed without any leakage. If there is felt, pasteboard
and other gasket material, it shall be flat, smooth and free of
disconnection and fold; moreover, it shall be firmly compressed and
shall not be blown down.
The sealing pressure air duct on small end cap shall be smooth and
shall be aligned with pressure tuyere on large end cap
Acceptance result
Date Date
192
4.7 Assembly and installation of water-cooled condenser
Space between pipe plates and design Main Measuring with steel tape by
mm -30~0
value deviation control zones and multi-points
Internal tie bar, baffle plate and Welding firmly, without welding
Checking according to drawing
auxiliaries skip
Open pore of condenser enclosure Without welding skip Checking according to drawing
2 See Table 4.7.1-2 for inspection and acceptance for positioning and centering of condenser
(exhaust equipment).
Table 4.7.1-2 Positioning and centering of condenser (exhaust equipment)
Inspection method and
Inspection item Property Unit Quality criteria
instruments
193
Main
Concrete strength Meet requirements of drawing
control
Deviation of transverse
mm 10 Inspecting with steel tape
Foundation central line
Central deviation of
mm 10 Inspecting with steel tape
foundation bolt hole
Geometric dimension mm 10~20 wider than side of base Inspecting with steel tape
4.7.2 See Table 4.7.2 for inspection and acceptance for cooling tube bundle of condenser.
Table 4.7.2 Cooling tube bundle installation of condenser
Inspection method and
Inspection item Property Unit Quality criteria
instruments
194
Non-axial groove, oil stain, rust
Cleaning up tube plate and
and rag inside hole; expose Observe
tube orifice
metallic luster
Main
Depth of expanded joint mm 75%~90% of tube plate thickness Measuring with depth gauge
control
a The space between tube sheet hole and cooling tube shall ensure no excessive expansion of cooling tube; the specific value
shall be determined according to calculation.
4.7.3 See Table 4.7.3 for inspection and acceptance of connection between condenser
(exhaust equipment) and steam cylinder as well as tightness test.
Table 4.7.3 Connection between condenser (exhaust equipment) and steam cylinder as well as tightness test
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Deformation control of
mm 0.1 Monitoring with dial gauge
steam cylinder
Tightness test at steam side Main No leakage at expansion opening Observe after the irrigated water
control is 100mm higher than top
195
cooling tube
4.7.4 See Table 4.7.4 for inspection and acceptance for installation of condenser (exhaust
equipment) auxiliaries and secondary pouring
Table 4.7.4 Condenser (exhaust equipment) auxiliaries and secondary pouring
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.7.5 See Table 4.7.5 for inspection and acceptance of rubber ball cleaning system.
Table 4.7.5 Inspection and installation of rubber ball cleaning system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Inspecting according to
Joint position Correct
construction drawing
196
Inspecting according to
Various auxiliaries Complete
equipment drawing
Implementation
SN Inspection item Related information
performance
197
metallographic inspection result and heat treatment technique. As
for those with insufficient data, it shall make up for inspection. The
method, range and quantity of supplemented inspection shall meet
the national standard or relevant professional standard. The
imported metallic material shall not meet the requirements of not
only relevant national technical standards specified in contract, but
also commodity inspection qualification document.
Conclusion
Date Date
benchmark of plant
Main
Space Column space 10m mm 1
control
deviation
Main
of pillars Column space>10m mm 2
control
Tensioning with spring
Difference Main
Diagonal line 20m mm 5 balance; measuring with
between control
steel tape; 10kN tension
central
diagonal Main
Diagonal line>20m mm 8
lines of control
pillar
198
Elevation deviation of
mm -10~0 Measuring with level
foundation plane
2 See Table 4.8.1-2 for inspection and acceptance of steel structure pre-assembly.
Table 4.8.1-2 Steel member pre-assembly
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Beam and Joint section malposition mm 2.0 Inspecting with weld gauge
truss Arch camber Main Inspecting with pulling line
mm L/5000
required in design control and straight steel ruler
Camber
Arch camber not Main Inspecting with pulling line
mm 0~+L/2000
required in design control and straight steel ruler
member Main
Joint misalignment mm t/10, and 3.0
control Inspecting with weld gauge
199
plane Difference between diagonal
mm L/2000, and 5.0
lines of frames
3 See Table 4.8.1-3 for inspection and acceptance of bracing steel structure installation.
Table 4.8.1-3 Installation of bracing steel structure
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
supporting surface
on both ends
Main
H6m mm 1 Inspecting with steel ruler
Height (vertical) control
deviation Main
6<H12m mm 1.5 Inspecting with steel ruler
control
Main
L6m mm 2 Inspecting with steel ruler
Longitudinal control
deviation Main
6<H12m mm 3 Inspecting with steel ruler
control
Main
L6m mm 2 Inspecting with steel ruler
control
Lateral deviation
Main
6<H12m mm 3 Inspecting with steel ruler
control
4 See Table 4.8.14 for inspection and acceptance of high-strength bolt installation for bracing
steel structure.
Table 4.8.1-4 Installation of high-strength bolt for bracing steel structure
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
200
Meet the requirements of
Inspection of bolt, nut and washer Observe
manufacturer
5 See Table 4.8.1-5 for inspection and acceptance on installation of fan supporting structure
and platform cover plate.
Table 4.8.1-5 Installation of fan bridge framework and platform cover plate
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
6 See Table 4.8.1-6 for inspection and acceptance on installation of tube-bundle bracing
Type-A frame.
Table 4.8.1-6 Installation of tube-bundle bracing Type-A frame
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Longitudinal deviation mm 10 Inspecting with steel ruler
control
Main
Lateral deviation mm 2 Inspecting with steel ruler
control
Main
Elevation deviation mm 2 Inspecting with level
control
201
7 See Table 4.8.1-7 for inspection and acceptance on installation of air-stopping wall.
Table 4.8.1-7 Installation of air-stopping wall
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.8.2 See Table 4.8.2 for inspection and acceptance on installation of air-cooling condenser
fan.
Table 4.8.2 Installation of air-cooling condenser fan
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Final bolt-up moment Meet requirements of drawing Inspecting with torque spanner
control
202
Installation of hub plate and Main
Meet requirements of drawing Observe
fixed plate control
Fan blade installation and Main Meet the requirements of Observing and measuring with
()
blade angle adjustment control manufacturer angle measuring instrument
Blade
Space between blade and fan Meet the requirements of
installation mm Inspecting with steel ruler
drum manufacturer
4.8.3 See Table 4.8.3 for inspection and acceptance on installation of condensing tube bundle.
Table 4.8.3 Installation of condensing tube bundle and cleaning system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.8.4 See Table 4.8.4 for inspection and acceptance on tightness test of air-cooling system
Table 4.8.4 Tightness test of air-cooling system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.8.5 See Table 4.8.5 for the implementation performance of subsection project compulsory
provisions for installation of air-cooling condenser system
Table 4.8.5 Inspection table on the implementation performance of subsection project compulsory
203
provisions for installation of air-cooling condenser system
________Unit Project number:
Unit project Assembly and installation of
Turbine generator auxiliary device installation Subsection project name
name air-cooling condenser
Implementation Related
SN Inspection item
performance information
Before filling water, it must thoroughly clean up internal rusty scale, weld
beading and foreign bodies. The internal anticorrosive coating shall be
1
painted according to design requirements or after the study of technical
section.
204
Conclusion
Date Date
4.9.1 See Table 4.9.1 for inspection and acceptance on installation of deaerator (water tank)
main body.
Table 4.9.1 Installation of deaerator (water tank) main body
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Contact surface of base, support and Smooth, clean and free of rag and
Observe
roller weld beading
205
Clean, no foreign bodies and
Inspecting according to the
Filling installation smooth in surface; the height
drawing
meets relevant requirements
4.9.2 See Table 4.9.2 for inspection and acceptance on installation of deaerator auxiliaries.
Table 4.9.2 Installation of deaerator auxiliaries
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Protective cover of water level gauge Smooth in edge; firmly fixed Observe
4.9.3 See Table 4.9.3 for the implementation performance of subsection project compulsory
provisions for installation of deaerator (water tank) equipment
Table 4.9.3 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of deaerator (water tank) equipment
________Unit Project number:
Turbine generator auxiliary device Subsection project Installation of deaerator (water tank)
Unit project name
installation name equipment
Implementation
SN Inspection item Related information
performance
206
organization shall question manufacturing organization jointly
with development organization and require supplemented
inspection or reinspection. Installation shall not be carried out
without inspection.
Acceptance result
207
Construction organization:(seal) Supervision organization: (seal)
Date Date
Application scope: This part is applicable to installation of high- and low-voltage heater,
including heater inspection and heater installation (See Table 4.3.35 Installation of ordinary
heat exchanger).
4.10.1 See Table for inspection and acceptance of high- and low- pressure heater.
Table 4.10.1 Inspection on high- and low- pressure heater
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.10.2 See Table 4.10.2 for inspection on the implementation performance of subsection
project compulsory provisions for inspection and installation of high pressure heater, low
pressure heater and gland heater as well as installation of drain flash tank in steam turbine
room and other heat exchanger.
Table 4.10.2 Inspection table on the implementation performance of subsection project compulsory
provisions for ( )
________Unit Project number:
Subsection project
Unit project name Turbine generator auxiliary device installation
name
208
performance
Acceptance result
Date Date
High-pressure Main
Internal cleaning Clean and impurity-free Observe
bypass valve control
Filter screen
Smooth Observe
eyelet
Desuperheating
Appearance Smooth Compressed air
water nozzle
inspection
Material of alloy Main
Meet requirements of drawing Spectrum inspection
steel parts control
Dimension of
Main
joint with Conform to the design Measuring with steel tape
control
pipeline
Internal
inspection Sealing surface Main Whole-circle linear contact, no Inspecting by painting
of valve seat and control discontinuity
209
valve spool
Deviation of Main
mm 10 Measuring with steel tape
central line control
Elevation
mm 10 Measuring with level
deviation
Installation
Levelness
deviation
mm/m 2 Measuring with level ruler
Verticality
deviation
a The internal inspection only refers to high voltage bypass valve where temporary valve spool need be replaced for boiler
washing pipe
4.11.2 See Table 4.11.2 for acceptance on inspection and installation of low-voltage bypass
system equipment.
Table 4.11.2 Inspection and installation of low-voltage bypass system equipment
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Internal cleaning Clean and impurity-free Observe
control
Desuperheating
Appearance Smooth Compressed air
water nozzle
inspection
Material of alloy Main Meet requirements of
Spectrum inspection
Low-pressure steel parts control drawing
Levelness deviation
mm/m 2 Measuring with level ruler
Verticality deviation
4.11.3 See Table 4.11.3 for inspection and acceptance on installation of steam discharge
device for access to condenser
Table 4.11.3 Installation of steam discharge device accessing into condenser
210
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.11.4 See Table 4.11.4 for inspection on the implementation performance of subsection
project compulsory provisions for inspection and installation of bypass system equipment.
Table 4.11.4 Inspection table on the implementation performance of subsection project compulsory
provisions for inspection and installation of bypass system equipment
________Unit Project number:
Subsection project Inspection and installation of bypass
Unit project name Turbine generator auxiliary device installation
name system equipment
Implementation
SN Inspection item Related information
performance
211
parts of alloy steel valve (It may make no marking on parts, but
shall record the inspection result)
Acceptance result
Date Date
212
Preparation and installation of iron In accordance with those specified
gasket in Table 4.3.5~4.3.7
4.12.2 See Table 4.12.2 for inspection and acceptance on pedestal grinding and positioning
Table 4.12.2 Pedestal grinding and positioning
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.12.3 See Table 4.12.3 for inspection and acceptance on inspection and installation of
bearing (block)and oil catch.
Table 4.12.3 Inspection and installation of bearing (block) and oil catch
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Gaps Roof Mm (0.1~0.15) /100 shaft diameter Measuring pressure fuse
control
between
Measuring oil-blocking side by
elliptical Main
Both sides Mm (0.15~0.2) /100 shaft diameter feeler gauge, with 15mm ~20mm
tiles control
inserted depth
213
Main
Gap between roof of tilting pad mm (0.12~0.2) /100 shaft diameter Measuring pressure fuse
control
4.12.4 See Table 4.12.4 for assembly, inspection and positioning of steam cylinder.
Table 4.12.4 Assembly, inspection and positioning of steam cylinder
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Gap
Top Mm 1.0 Measuring with depth gauge
between
sliding pin
at bottom of Main
Both sides (total gap) mm 0.04~0.08 Measuring with vernier caliper
steam control
cylinder
214
Meet the requirements of Measuring with feeler gauge and
Lug gap Mm
manufacturer micrometer
4.12.5 See Table 4.12.5 for inspection and acceptance on rotor positioning, centering
adjustment of gland casing and oil catch bore as well as fixation of steam cylinder.
Table 4.12.5 Rotor positioning, centering adjustment of gland casing and oil catch bore as well as fixation of
steam cylinder.
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Rotor levelness mm/m The lift of rear axle neck is zero Measuring with gradienter
control
Main
Center Right-left (a-b) mm 0.06~0.1
control
deviation of
Upper Measuring with inside
steam seal
Main micrometer
and oil catch ab mm 0.06~0.1
c control
bore
part 2
Tapping with hand hammer and
Reinspection on iron gasket mm No looseness; partial space<0.05
inspecting with feeler gauge
Fixation of flexible-strut front bearing Tightening positioning pin and Tapping with hand hammer and
pedestal and platen bolting up listening to sound
4.12.6 See Table 4.12.6 for inspection and acceptance on installation of clapboard and gland
casing.
Table 4.12.6 Installation of clapboard and gland casing
215
Inspecting with bolt-up feeler
Horizontal surface space of clapboard mm <0.05
gauge
Center
Measuring with pulling steel
deviation Main Meet the requirements of
Right-left (a-b) mm wire, hanging earphone or laser
of control manufacturer, generally 0~0.08
alignment method
clapboard
Center
Measuring with pulling steel
deviation ab Main Meet the requirements of
c mm wire, hanging earphone or laser
of Upper part 2 control manufacturer, generally 0~0.05
alignment method
clapboard
216
a) Clearance in suspension pin assembly b) Axial clearance of clapboard (sleeve) or ring-holding end surface c) Clearance of clapboard nail on clapboard support
Interference
d) Clearance on both sides of clapboard (sleeve) or ring-holding positioning key e) Clearance of clapboard (sleeve) or ring-holding positioning key
All-level axial and radial throughflow Main Meet the requirements of Measuring with feeler gauge or
mm
clearance control manufacturer wedged feeler gauge
217
Contact area of thrust segment and Main 75%, Taking on spot or uniform Inspecting by wholly painting
thrust disc control distribution after assembling thrust pad
4.12.8 See Table 4.12.84.12.8 for inspection and acceptance on covering of driving steam
turbine
Table 4.12.8 Covering of driving steam turbine
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Trial erection of bolt and nut Screw in freely, without looseness Test by hands
Horizontal joint
No staggered joint Inspecting driven-in pin
surface on sides
218
In accordance with those
Secondary grouting specified in Table 4.3.11 and
4.3.12
4.12.9 See Table 4.12.9 for inspection and acceptance on covering of shaft block and
installation of rolling gear.
Table 4.12.9 Covering of shaft block and installation of rolling gear
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Clearance Top mm 1.5~2
control
Wobble with Measuring pressure fuse
Both Main
wheel gearwheel mm 0.8~1.2
sides control
type
Distance from
gearwheel after
Installation Adequate distance, firmly fixed Observe
disconnection of
of
wobble wheel
gear-type
Contact surface of In accordance with those
rolling gear
Sliding gear specified in Table 4.3.38
wheel Limit position of
Main Positioning pin is able to embed
type sliding wheel Observe
control into notch of torsion panel
withdrawal
Installation of gearwheel
Not contact gearwheel Inspecting by rolling rotor
enclosure
219
Main Observe, compressed air
Pressure oil pipe Clean inside; smooth pipeline
control inspection
4.12.10 See Table 4.12.10 for inspection and acceptance on adjustment of driving steam
turbine as well as inspection and installation of protection system
Table 4.12.10 Adjustment of driving steam turbine as well as inspection and installation of protection system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
220
Main Correct, firm; meet the
Spring support assembly Checking against drawing
control requirements of manufacturer
Manual screw
rod for No jam; the travel meets the Trial operation; measuring
pressure requirements of manufacturer with vernier caliper
regulation
221
Main Observing pressure drop after
Tightness of accumulator No leakage
control filling nitrogen
4.12.11 See Table 4.12.11 for inspection and acceptance on installation of lubricating oil
system for driving steam turbine.
Table 4.12.11 Installation of lubricating oil system for driving steam turbine
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Diameter of nozzle Main Meet the requirements of Check according to the drawing,
mm
Installation of oil
diverging pipe
throat
222
Distance between
nozzle exit and
diverging pipe
throat
4.12.12 See Table 4.12.12 for inspection and acceptance on test run of driving steam turbine
Table 4.12.12 Test run of driving steam turbine
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Main
Governor oil pressure MPa
control Meet the requirements of
Online monitoring
Main manufacturer
Lubricating oil pressure MPa
control
Main
Fire-resistant oil temperature 505 Measuring thermometer
control
Main
Lubricating oil temperature 405 Measuring thermometer
control
Inspection before trial operation
Main
Trip and latching test Normal operation Test by hands
control
223
Actuation test of main
Normal Manually operate, observe
throttle valve
Test on exhaust-steam
Normal switching Observe
butterfly valve switch
Main
Scavenge oil temperature 65 Measuring with thermometer
control
Main
Bearing bush temperature 90 Online monitoring
control
Main
Emergency trip speed Rated speed of 1.1~1.12 times Online monitoring
control
4.12.13 See Table 4.12.13 for inspection and acceptance on installation of steam feed pump.
Table 4.12.13 Installation of steam feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
224
inspection Conform to the installation
Parts number Observe
sequence
Black bronze of thrust Main No bodiless, crack, air hole and Inspecting with coal-soaked or
segment control slag inclusion oil penetrating fluid
4.12.14 See Table 4.12.14 for inspection and acceptance on coupling centering of feed
pump group
Table 4.12.14 Coupling centering of feed pump group
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
225
Compensation
Main Meet the requirements of
value of reserve
control manufacturer
Coupling temperature
Measuring dial gauge; reading
centre Radial Main
mm 0.06 maximum opposite difference
alignment deviation control
Compensation
Main Meet the requirements of
value of reserve
control manufacturer
Coupling temperature
Measuring dial gauge; reading
centre Radial Main
Lamination-type mm 0.06 maximum opposite difference
alignment deviation control
coupling
End surface Main
mm 0.04
deviation control
4.12.15 See Table 4.12.15 for inspection and acceptance on test run of steam feed pump
Table 4.12.15 Test run of steam feed pump
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument
Main
Bearing bush temperature 90 Measuring with thermometer
control
Main
Bearing annealing temperature 65 Measuring with thermometer
control
Main
Bear vibration mm 0.04 Measuring with vibration gauge
control
Vibration
Main Meet the requirements of
Shaft vibration Online monitoring
control manufacturer
226
Main
Balance pipe temperature No sudden heating phenomenon Feel by hands
control
4.12.16 See Table 4.12.16 for inspection on the implementation performance of subsection
project compulsory provisions for installation of steam feed pump unit.
Table 4.12.16 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of steam feed pump unit
_________ Unit Project number:
Installation of turbine generator Subsection project
Unit project name Installation of steam feed pump unit
auxiliaries name
Implementation
SN Inspection item Related information
performance
227
The important materials used in construction shall be provided
with quality certificate and material certificate. If the quality of
such materials are doubted during checking and inspection;
they shall be inspected and identified necessarily. All
5
performances of alloy steel, high-pressure and
high-temperature welding material, lubricating-oil (grease) and
fire-resistant oil must meet design requirements and national
standards before application.
228
finally, it must use triangular oil stone to polish the repaired
and scraped area. If the screw thread inside the studding hole
need be repaired, it shall prepare special screw tap.
After inspecting and repairing screw thread, it shall use powder
coating with fine granularity and high temperature resistance
for inunction forcibly, or paint with lubricant required by the
manufacturer; it shall remove surplus paint and pack up bolt to
avoid dust and clash.
The dimension of oil bag for oil hole on apical axis of lower
bearing shell shall meet the requirements of drawing.
Generally, its depth shall be between 0.20~ 0.40mm; the area
of oil bag shall be 1.5%~2.5% (larger value for larger diameter
9
of axle) of projected area of axle neck; the axle neck shall be
tightly close to around oil bag. The oil-pipe head of apical axis
must be firmly buried under black bronze and ensure to be
clean and smooth.
229
segment and steam chamber; seal pipe orfice as well as socket
and plug of instrumentation
230
There shall be protective cover for manual emergency trip
13 device; the positioning billiards shall be able to correctly
position slide valve.
The oil exit pipe for oil tank accident shall be connected to the
accident oil drainage well specified in design. Before unit trial
operation, it shall be formally installed and confirmed to be
smooth.
The inspection and installation of oil piping valve shall be in
accordance with the following requirements:
Generally, two gate valves shall be set up for accident oil
discharge valve; the gate valve close to oil tank shall be made
16 of steel. The operation hand wheel of accident oil discharge
valve shall be set up at over 5m away from oil tank and there
shall be more than two passages. The hand wheel shall be set
up with protecting glass.
There shall be clear marking on switch direction of valve;
rising stem valve shall be used instead of reverse valve. The
valve stem of pipe shall be laid flat or downward to prevent
valve disc from falling off and cutting off oil line during
operation.
Drilling hole, gas cutting and welding shall not be carried out
17 on the oil pipe after it is cleaned up and sealed, otherwise,
cleaning, inspection and sealing must be carried out again.
231
Before installing heavy castings, such as steam cylinder, steam
chamber and main throttle valve, it shall check exfactory
certification and quality guarantee and carry out appearance
inspection; there shall be no crack, slag inclusion, double skin,
19
weld beading, casting sand and damage. When there is crack,
its length, depth and distribution condition shall be found out
and treatment measures shall be carried out by the
manufacturer and other organizations concerned.
Acceptance result
Date Date
Application scope: installation of electrically driven feed pump group, including inspection of
electrically driven feed pump and motor, installation of electrically-driven feed pump and
electrically driven feed pump oil system as well as trial operation of electrically driven feed
pump. See Table 4.12.14 for coupling centre alignment; see Table 4.5.6-10 for oil system
rinsing; see General-purpose Table 4.3.20 for secondary pouring.
4.13.1 See Table 4.13.1 for inspection and acceptance of electrically driven feed pump
Table 4.13.1 Inspection on electrically driven feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Space between pump wheels Meet the requirements of Measuring with inside
Dominant mm
at inlet and outlet segment manufacturer micrometer at rod-through bolt
232
Meet the requirements of Measuring with dial gauge for
Shaft lifting value Dominant mm
manufacturer upper tile and upside-down tile
Black bronze of thrust No bodiless, crack, pore and slag Inspecting with coal-soaked or
Dominant
segment inclusion oil penetrating fluid
Inspection
Internal pipe of air cooler Smooth and clean Compressed air purging
and
installation Inspecting after 5 minwater
of air Water side tightness Dominant No leakage pressure test with 1.25 times
cooler working pressure
233
Clean and impurity-free, tight
Air chamber and air duct Observing
joint
4.13.3 See Table 4.13.3 for inspection and acceptance on installation of electrically driven
feed pump.
Table 4.13.3 Installation of electrically driven feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
234
connection, no blockage,
reasonable and firm support
4.13.4 See Table 4.13.4 for inspection and acceptance on installation of electrically driven
feed pump oil system.
Table 4.13.4 Installation of electrically driven feed pump oil system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4.13.5 See Table 4.13.5 for inspection and acceptance on trial operation of electrically
driven feed pump.
Table 4.13.5 Trial operation of electrically driven feed pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Calibration on the operating value of Meet requirements of Check records on electric and
pressure and temperature drawing thermal test
235
Feeling by hands and listening to
Rolling rotor No friction and jam inside
the sound
Cam-turn-angle
No-load trial corresponds to spoon tube Draw static characteristic curve
operation of Static test Dominant travel and meets the and compare with curve provided
fluid coupling requirements of by the manufacturer
manufacturer
236
n3000 Dominant mm 0.05
Bearing
Measuring with vibration gauge
vibration
n>3000 Dominant mm 0.04
Meet requirements of
Minimum flow device
drawing
237
Speed adjustable range of Meet the requirements of
fluid coupling manufacturer
No friction sound in
Coasting operation of pump coasting operation, no Timing by stopwatch and
Dominant
unit sudden pump-off monitoring with listening needle
phenomenon
4.13.6 See Table 4.13.6 for inspection on the implementation performance of subsection
project compulsory provisions for installation of electrically driven feed pump group.
Table 4.13.6 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of electrically driven feed pump group
_________Unit Project number:
Installation of turbine generator Subsection project Electrically driven feed pump group
Unit project name
auxiliaries name installation
Implementation
SN Inspection item Related information
performance
238
installation quality standard.
Drilling hole, gas cutting and welding shall not be carried out
6 on the oil pipe after it is cleaned up and sealed, otherwise,
cleaning, inspection and sealing must be carried out again.
Acceptance result
4.13.7 See Table 4.13.7 for inspection on the implementation performance of subsection
project compulsory provisions for installation of booster pump and condensate pump of feed
pump.
Table 4.13.7 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of ( ) pump
_________Unit Project number:
Installation of turbine generator Subsection project
Unit project name
auxiliaries name
Implementation
SN Inspection item Related information
performance
239
after reaching installation quality standard.
Acceptance result
Date Date
Application scope: installation of condensate pump, including inspection, installation and trial
operation of condensate pump.
4.14.1 See Table 4.14.1 for inspection and acceptance of condensate pump.
Table 4.14.1 Inspection on condensate pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Shell
No casting sand, pore, crack
Appearance Impeller and rag; smooth and clean on Observing
joint surface
Bearing support
240
Meet the requirements of
Pump shaft flexibility Dominant mm Measuring with dial gauge
manufacturer
Radial gap between impeller and Meet the requirements of Measuring with vernier
Dominant mm
sealing ring manufacturer caliper
Pump shell bolt-up Dominant Firm and without looseness Tightening again; observing
inducer
4.14.2 See Table 4.14.2 for inspection and acceptance on installation of condensate pump.
Table 4.14.2 Inspection and acceptance on installation of condensate pump
Inspection method and
Inspection item Property Unit Quality criteria
instruments
241
Clearance between support leg and
mm <0.05 Inspecting with feeler gauge
platen
a The side coupling of vertical condensate pump sways strongly. The iron block shall be first used to stuff inner bore of filling
box of pump shaft so that the deviation between pump shaft and inner bore of filling box is less than 0.05mm.
b The requirements for preparing this coupling gasket is only applicable to vertical condensate pump with thrust bearing on
motor.
Sealing water pipe Dominant Smooth and abundant water Start-up observing
Trial
operation Judging according to inlet and
Inlet screen Dominant No blockage
under outlet pressure
vacuum
Condensing water level Normal Observing
state
4.15 See Table 4.15 for inspection and acceptance on installation of desuperheater and
decompressor
Table 4.15 Installation of desuperheater and decompressor
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
242
Restriction orifice
Meet requirements of drawing
arrangement
243
design size Measuring with steel tape with
Span 19.5m Dominant mm 5
adding 150 N tension
Longitudinal
mm/m <1/1500 column space Measuring with level
levelness
Transverse levelness mm/m <1/100 track width Measuring with level ruler
Track
Maximum deviation
of full-range Dominant mm 10 Measuring with level
elevation of rail top
Contact with press plate, iron gasket, In good condition, compact and no
Tapping with hand hammer
track and crane beam looseness
2 See Table 4.16.1-2 for inspection and acceptance on crane assembly and installation.
Table 4.16.1-2 Crane assembly and installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
244
Measuring with steel tape
adding 100~150 N tension or
Main beam span deviation mm 5
measuring wheel center distance
with telemeter
Allowable
Box girder mm 5 Measuring bridge framework
deviation of
with steel tape adding 100~150
bridge
Single web beam N tension or with telemeter;
framework mm 10
truss diagonal line
diagonal line
Lateral
Span L16.5ma mm 5
bending of Measuring with pulling steel
deviation
Span Measuring with steel tape
of box Span <19.5m mm 1~5
end (Excurvation refers to +)
girder
traveller Midspan Span 19.5m mm 1~7
245
Perpendicular skewness of big wheel mm L/400 Measuring with plumb bob
Steel wire on drum where hook at the Drum shall be able to contain Observing
extreme lower position entirely
3 See Table 4.16.1-3 for check, installation, inspection and acceptance of transmission gear.
Table 4.16.1-3 Inspection and installation of transmission gear
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Coupling
Radial deviation mm
alignment of
0.08 Measuring with dial gauge
motor and End surface
mm
reductor deviation
Brake strap gap Consistent in full length Measuring with feeler gauge
246
Grease without rust and
Wheel bearing Observing
deteriorating
4 See Table 4.16.1-4 for inspection and acceptance of load test on overhead traveling crane.
Table 4.16.1-4 Load test of overhead traveling crane
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Limit switch
Correct and reliable operation
Interlock protection
device
Electric bridge
Catenary Dominant mm <L/700
type
arc of
Electric
crossbeam Dominant mm <L/600 Transit survey
monospar
at running
test Manual Dominant mm <L/500
247
Test continuous time min 10 Timing
Electric
Brake ring Without damage and grease Observing
block
inspection Revolving along the axis of Measuring with straight steel
Dominant mm 1.5~3
brake wheel ruler
Fix steel wire on outer cover mm Pigtail length of outstretching Observing, Tapping with hand
248
from bottom of wedge box 50; hammer
wedge chock tightly
Steel wire
Electric reservation on
block winding drum
Dominant Ring 3 Observing
installation where hook at
the extreme
Limiting
lower position
stopper
Distance
adjustment
between pulley
and drum cheek
mm 600 Measuring with steel tape
where hook at
the extreme
higher position
2 See Table 4.16.2-2 for inspection and acceptance of load test on electric block.
Table 4.16.2-2 Load test on electric block
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Hook where no load Stable zero friction and impaction Observing; listening by ears
Brake Reliable
Suspending with 1.25 times rated
Static
Steel wire Dominant No looseness load at 100mm height; inspecting
load test
after 10min
249
Gliding distance of
suspended object after Dominant mm 50
braking
4.17.1 See Table 4.17.1 for inspection and acceptance on installation of diesel generator.
Table 4.17.1 Installation of diesel generator
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument
4.17.2 See Table 4.17.2 for inspection and acceptance on trial operation of diesel generator.
Table 4.17.2 Trial operation of diesel generator
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
250
Oil filling inspection on oil Full of diesel fuel, without air Inspecting by disassembling
Dominant
inlet pipe discharged fuel intake connection
Oil filling inspection for Full of diesel fuel, without air Inspecting by disassembling
Dominant
oil inlet filter screen discharged fuel intake connection
Central deviation of
mm 10 Measuring with steel tape
foundation bolt hole
Center deviation of
mm 2 Measuring with steel tape
embedded foundation bolt
Center deviation of
mm 5 Measuring with steel tape
each-layer plate orifice
251
and check Concrete
Dominant Meet requirements of drawing Check intensity report
strength
Deviation of
mm 3 Measuring with steel tape
central line
Base
Elevation
mm 5 Measuring with level
deviation
4.18.2 The inspection and installation of water circulating pump is divided into inspection
and installation of vertical centrifuged water circulating pump, inspection and installation of
diagonal water circulating pump and inspection and installation of axial water circulating
pump according to different pump forms.
1 See Table 4.18.2-1 for check, installation, inspection and acceptance of vertical centrifuged
water circulating pump.
Table 4.18.2-1 Inspection and installation of vertical centrifuged water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
252
No crack on surface, no
Appearance inspection Observing
mechanical damage
2 See Table 4.18.2-2 for check, installation, inspection and acceptance of vertical diagonal
water circulating pump.
Table 4.18.2-2 Inspection and installation of vertical diagonal water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
a The blade rotor assembling of blade adjustable diagonal pump may refer to the requirements of axial pump assembling.
3 See Table 4.18.2-3 for check, installation, inspection and acceptance of vertical axial water
253
circulating pump.
Table 4.18.2-3 Inspection and installation of vertical axial water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
sleeve end-face
Pivot movement value of impeller Dominant mm 0.50 Measuring with dial gauge
Main shaft length checking Meet requirements of drawing Measuring with steel tape
254
Coupling floating
mm 0.04
displacement
Levelness deviation of
Dominant mm/m 0.05 Measuring with gradienter
coupling flange surface
Main shaft elevation before Design value, equal to coupling Measuring with straight steel
mm
installing motor seam depth plus 2~6 ruler
Thickness deviation of
mm 0.05 Measuring with vernier caliper
guiding bush
Upside-down clearance
Measuring with outside
deviation of axle and guide Dominant mm 0.05
micrometer and vernier caliper
bearing
4.18.3 The inspection and installation on motor of large-scale water circulating pump is
divided into inspection and installation on motor of large-scale vertical water circulating
pump and horizontal water circulating pump.
1 See Table 4.18.3-1 for check, installation, inspection and acceptance on motor of large-scale
vertical water circulating pump.
Table 4.18.3-1 Inspection and installation on motor of large-scale vertical water circulating pump
255
y measuring instrument
Inspection on plane of
composition of frame support Flat, smooth and no damage
leg
Domin
Frame center deviation mm 1.5 reference, measuring with
ant
straight steel ruler
Appearance inspection on thrust Domin No crack, pore, slag inclusion and Inspecting with coal-soaked or
bearing
thrust
d
bearing and guide bearing ant bodiless in black bronze oil penetrating fluid
256
Smooth, clean, flat, smooth and
Thrust disc Observing
no damage
Domin
n<250r/min mm/m 0.03
Relative ant
Measuring opposite maximum
waggling n=250r/min~375r/mi Domin
mm/m reading with dial gauge at
of motor n ant
0.02 coupling section
shaft n=250r/min~600r/mi Domin
mm/m
n ant
257
shaft n=250r/min~600r/mi Domin
mm/m 0.03
n ant
Absolutel Domin
n<250r/min mm 0.40
y ant
Measuring opposite maximum
waggling n=250r/min~375r/mi Domin
mm 0.30 reading with dial gauge at
of water n ant
pump guide bearing
pump n=250r/min~600r/mi Domin
mm 0.20
shaft n ant
Rad
ial
Dom
dire mm 0.12
inant
750>n500 ctio
r/min n
End
Permanent Dom
surf mm 0.06
couping inant Measuring opposite maximum
ace
center reading with dial gauge or
Rad
allowable feeler gauge
ial
deviation Dom
dire mm 0.16
inant
n<500r/mi ctio
n n
End
Coupling center deviation
Dom
surf mm 0.08
inant
ace
Motor installation
Rad
ial
Dom
dire mm 0.16
inant
750>n500 ctio
r/min n
Non-perm End
Dom
anent surf mm 0.10
inant Measuring opposite maximum
coupling ace
reading with dial gauge or
center Rad
feeler gauge
allowable ial
Dom
deviation dire mm 0.24
inant
n<500r/mi ctio
n n
End
Dom
surf mm 0.15
inant
ace
258
Positioning pin at joint surface Tightly contacted Tapping with hand hammer
aThe rotor field center is slightly lower than stator field center. bThe stator elevation error refers to the value after meeting the
previous requirements
2 See Table 4.18.3-2 for check, installation, inspection and acceptance on motor of horizontal
water circulating pump.
Table 4.18.3-2 Inspection and installation on motor of horizontal water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Inspection on plane of
composition of frame Flat, smooth and no damage Observing
support leg
Center deviation of rotor Meet the requirements of Measuring with straight steel
Dominant mm
and stator magnetic field manufacturer ruler
Material
Motor dimension Meet the requirements of
Pedestal
installation Material manufacturer
bearing
quantity
insulation
Insulation Measuring with 1000V
M 0.5
resistance insulation resistance meter
259
4.18.4 See Table 4.18.3-2 for inspection and acceptance on installation of oil system for
water circulating pump.
Table 4.18.4 Installation of oil system for water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
260
Measuring with glass tube
Scavenge pipe gradient Dominant mm/m 30~50
gradienter
Oil-pipe vertical deviation mm 1.5mm/m, and the maximum 7 Measuring with plumb bob
equipment
Circumference
Dominant nun 0.10
deviation Measuring with flat bevel
Coupling
End surface scale
centre Dominant mm 0.08
deviation
alignment
Coupling
mm 2~3 Measuring with steel tape
clearance
Inspection and installation of oil feed pump
Oil temperature
for trial 15~65 Measuring with thermometer
operation
Oil pump
Dominant 85 Measuring with thermometer
temperature
261
Outlet oil pipe It may be connected with bearing
Observing
rinsing bush after proving qualified
4.18.5 See Table 4.18.5 for inspection and acceptance on installation of parts and sets for
hydraulic regulating system of vertical water circulating pump.
Table 4.18.5 Installation of parts and sets for hydraulic regulating system of vertical water circulating pump
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument
Levelness deviation of
flange on oil distributor mm/m 0.06 Measuring with gradienter
Inspection and installation of parts and sets
base
Concentricity deviation
of regulator and motor mm 0.60 Measuring with dial gauge
shaft
4.18.6 See Table 4.18.6 for inspection and acceptance on trial operation large-scale vertical
water circulating pump.
Table 4.18.6 Trial operation of large-scale vertical water circulating pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
262
Meet the requirement of rotor
Coupling connection Check installation records
hoisting value
Rubber First
10
bearing start-up
min Timing
pre-oiling Normal
5
time start-up
Adopt bearing
temperature of lubricating 80 Measuring with thermometer
grease
Bearing temperature by
70 Measuring with thermometer
adopting lubricant
Continuous operation
h 4~8 Timing Observing
time
Application scope: rotary sieve installation, including inspection, installation and trial
operation of rotary sieve.
4.19.1 See Table 4.19.1 for inspection and acceptance on installation and inspection of
rotary sieve.
Table 4.19.1 Rotary sieve inspection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Appearance
inspection
Preparation and
In accordance with those
installation of iron gasket
specified in Table 4.3.19
and foundation bolt
Height difference of
mm 5 Measuring with level
separated base coordinate
Horizontal deviation of
Dominant mm/m 0.5 Measuring with gradienter
seat frame
Concrete foundation of
Contact tightly Observing
sealing plate support
Interface malposition of
mm 1.5 Measuring with steel tape
guide track
264
Verticality deviation of Suspending plumb bob along
mm/m 1
guide track total height
Deviation of guide-track
mm 5 Measuring with steel tape
diagonal line
Guide-track center
elevation deviation of Dominant mm 3 Glass tube gradienter
bottom double-side curve
Horizontal deviation of
Dominant mm/m 0.5 Measuring with gradienter
loading shaft
Clearance
between
No looseness and jam
swivel pin
Driving motor installation
Locknut and
Tightly locked
pin
Clearance between
reductor, motor support mm 0.05 Inspecting with feeler gauge
and base
Transmission gear
Firm and reliable Observing
protective cover
265
In accordance with those
Metal cover plate
specified in Table 4.3.37
4.19.2 See Table 4.19.2 for inspection and acceptance on trial operation of rotary sieve.
Table 4.19.2 Trial operation of rotary sieve
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
266
Full-length straightness Measuring with pulling steel
mm/m 1
deviation of guide track wire
Interface malposition of
nun 1.5 Measuring with steel tape
guide track
Deviation of guide-track
mm 5 Measuring with steel tape
diagonal line
Transit clearance at
longitudinal switching mm 3.5 Measuring with steel tape
section of net grating
Planeness of
mm 2
dirt-blocking grate
Horizontal deviation of
Dominant mm/m 0.5 Measuring with gradienter
loading shaft
267
reductor, motor support
and base
Protective cover of
Firm and reliable Observing
driving device
4.20.2 See Table 4.20.2 for inspection and acceptance on trial operation of trash remover.
Table 4.20.2 Trial operation of trash remover
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Interlock protection
device
268
Bearing temperature 80 Measuring with thermometer
4.21 See Table 4.21 for inspection and acceptance on installation and test of large-scale flat
steel gate.
Table 4.21 Installation and test of large-scale flat steel gate
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Straight deviation of
Measuring with pulling steel
single-section gate mm 1/2000 of structure member length
wire
groove
Full-length straightness
Measuring with pulling steel
deviation of gate-groove mm 1
wire
working surface
Interface malposition of
Bulkhead mm 0.5 Measuring with steel tape
guide track
gate
Space deviation of guide
installation Dominant mm 8 Measuring with steel tape
track
Deviation of guide-track
mm 8 Measuring with steel tape
diagonal line
269
Concrete pouring inside The concrete inside embedded parts
gate-groove embedded shall be much more parallel and Observing
parts level than that outside
Application scope: This part is applicable to deep water pump installation for water-collecting
pump house, including inspection, installation and trial operation of deep water pump.
4.22.1 See Table 4.22.1 for inspection and acceptance of deep water pump.
Table 4.22.1 Deep water pump inspection
Inspection method and measuring
Inspection item Property Unit Quality criteria
instrument
Radial flutter of driving shaft Dominant mm <0.20 Measuring with dial gauge
270
Axial displacement quantity of Measuring with push-and-pull
Dominant mm 6~8
impeller method
4.22.2 See Table 4.22.2 for inspection and acceptance on installation of deep water pump.
Table 4.22.2 Deep water pump installation
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Levelness deviation of pump base mm/m 0.2 Measuring with level ruler
Lubricating water pipe installation Correct joint and abundant water Observing
4.22.3 See Table 4.22. for inspection and acceptance on trial operation of deep water pump.
Table 4.22.3 Trial operation of deep water pump
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
271
Rubber bearing preoiling time min 20 Timing
Axial displacement quantity of No change before and after Stopping pump and measuring
Dominant
impeller start-up after start-up for 20min
Application scope: installation of water purifying plant for hydraulic engineering, including
inspection, installation and trial operation of water purifying plant.
4.23.1 See Table 4.23.1 for inspection and acceptance of water purifying plant.
Table 4.23.1 Inspection on water purifying plant
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Horizontal deviation of
mm 4
branch pipe
Vertical misalignment of
mm 3 Measuring with L-square
branch pipe and main pipe
272
Thickness of packing
Meet requirements of drawing Checking according to drawing
material
4.23.2 See Table 4.23.2 for inspection and acceptance on installation and trial operation of
water purifying plant.
Table 4.23.2 Installation and trial operation of water purifying plant
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Deviation of central
mm 5 Measuring with steel tape
line
Installation
Foundation surface
of water No impurity, dust and oil stain
cleaning
purifying
Concrete height of the Higher than or equal to the
plant
external base lower edge of base
Secondary
Compacted; there shall be no Observing
grouting
Concrete tamping gap at the lower bottom of
base
4.23.3 See Table 4.23.3 for inspection on the implementation performance of subsection
273
project compulsory provisions for engineering installation organizations in water-circulating
pump room equipment, public-water pump house equipment and water-collecting pump
house equipment.
Table 4.23.3 Inspection table on the implementation performance of subsection project compulsory
provisions for ( )
________Unit Project number:
Subsection project
Unit project name
name
Implementation
SN Inspection item Related information
performance
Acceptance result
Date Date
274
4.24 Main body installation of combustion engine
Foundation longitudinal
center line and combustion mm/m <2
Inspecting by isosceles triangle
engine
Dominant method; measuring with steel
Transverse verticality
tape
deviation of main-body mm Total deviation value <5
supporting leg
Verticality deviation
mm/m <2
between foundation Inspecting by isosceles triangle
275
level
Bolt and nut coordination mm Flexible without jam Inspecting and feeling by hands
Deviation between
With vertical and horizontal
anchorage plate center and
mm <3 central lines benchmark,
foundation vertical and
Embedded measuring with steel tape
horizontal center line
anchorage
Elevation deviation of With foundation line as
plate mm 3
anchorage plate benchmark,
Verticality difference of
mm/m <3 Measuring with plumb bob
positioning retaining plate
4.24.2 See Table 4.24.2 for inspection and acceptance on installation and inspection of
combustion engine base plate and platen
Table 4.24.2 Inspection and installation of combustion engine base plate and platen
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Pedestal sliding surface and base Flat, smooth, clean and no Inspecting with leveling ruler
plate inspection damage, deformation and rag feeler gauge
276
Meet the requirement of drawing
Measuring with combined
Horizontal mm/m provided by the manufacturer, with
diagram level
the same direction
Inspection on combustion engine and Meet the requirement of the Inspecting by painting on site;
Dominant
platen contact surface manufacturer inspecting with feeler gauge
277
Cleanliness inspection inside Clean and without rust and foreign
Dominant Site inspection
combustion chamber bodies
Cleanliness inspection inside main Clean and without rust and foreign
Dominant Site inspection
body joints bodies
Inspection on joint flange face of Clean and without rag, high spot,
Site inspection
burner and main body rust and radial groove
3 See Table 4.24.3-3 for inspection and acceptance of combustion engine load distribution
Table 4.24.3-3 Combustion engine load distribution
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
4 See Table 4.24.3-4 for inspection and acceptance of shafting adjustment and connection
Table 4.24.3-4 Shafting adjustment and connection
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Spectrum inspection or
Meet the requirements of
Coupling bolt; nut material examining certification
manufacturer
provided by the manufacturer
Corresponding to the
manufacturer's mark; when there
Coupling relative position is no mark, the floating Site inspection
displacement shall be offset
mutually
Deviation of measured
lower gape value and Meet the requirements of
Dominant mm
reserve value required by manufacturer, 0.02
the manufacturer
Safety pin, stop pin, cotter pin, nut-cap Correct assembling; complete;
Observing
cover plate, bolt assembly tightly locked
a Generally, the bolt-up degree is measured by bolt elongation, fastening force moment or oil pressure of hydraulic tensioning
instrument
5 See Table 4.24.3-5 for inspection and acceptance on measurement and adjustment of sliding
pin system clearance.
Table 4.24.3-5 Measurement and adjustment of sliding pin system clearance
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
horizontal pin
Distance between
Vertical and
i
manufacturer
combustion engine
279
Smooth, clean and without high
Contact surface inspection Dominant Feeling by hands
spot and rag
end freely
6 See Table 4.24.3-6 and Figure 4.24.3 for inspection and acceptance on installation of
automatic synchronizing device
Table 4.24.3-6 Installation of automatic synchronizing device
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Pallet upper-part
Measuring with inside
longitudinal spacing A mm Meet requirements of drawing
micrometer
during SSS clutch on-off
micrometer
on-off
Pallet right-side
Measuring with inside
longitudinal spacing A mm Meet requirements of drawing
micrometer
during SSS clutch on-off
280
Pallet right-side lateral
Measuring with depth
spacing B during SSS mm Meet requirements of drawing
micrometer
clutch on-off
2 See Table 4.24.4-2 for inspection and acceptance of air purification sound deadening system
Table 4.24.4-2 Air purification and sound deadening system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Deviation of central
Alignment mm 10 Measuring with steel tape
line
281
Elevation deviation mm 10 Measuring with level
Clearance between
Gapless after glue impregnating Site inspection
modules
Platform, stairway and handrail Neat, nice, flat and smooth; meet
Observing
installation the technical requirements
3 See Table 4.24.4-3 for inspection and acceptance of inlet system sealing
Table 4.24.4-3 Sealing inspection of inlet system
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
282
draught flue as well as sealing inspection of exhaust system.
1 See Table 4.24.5-1 for inspection and acceptance on installation of exhaust frame and
diffusion section
Table 4.24.5-1 Installation of exhaust frame and diffusion section
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
2 See Table 4.24.5-2 for inspection and acceptance on assembly and installation of draught
flue
Table 4.24.5-2 Assembly and installation of draught flue
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Cleaning and Cleaning and check of Clean and without rag, high spot,
Observing
check of joint surface flange rust and radial groove
inlet and Inspection on bolt
Clean and no rust Observing
outlet flue hole cleanliness
283
Inspection on spring
thread insert inside Tightly fit with bolt hole Observing
bolt hole
Vertical and
horizontal mm 10 Tapeline
central line
Draught flue
installation Elevation mm 10 Gradienter
4.24.6 See Table 4.24.6 for inspection and acceptance on assembly and installation of
bypass chimney
Table 4.24.6 Assembly and installation of bypass chimney
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
284
Checking according to the
Center deviation of
Dominant 10 drawing; measuring with
Foundation embedded foundation bolt
steel tape
preparation
Meet the requirement of the
Base plate elevation mm Gradienter
manufacturer
Note: This Table is applicable to the assembly and installation of bypass chimney in case of no exhaust-heat boiler
4.24.7 See Table 4.24.7 for inspection and acceptance on installation of combustion engine
enclosure
Table 4.24.7 Installation of combustion engine enclosure
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
Fabrication of platform, ladder and Neat, nice, flat and smooth; meet
Observing
handrail the technical requirements
Spray test on fire extinguishing system Dominant Tight enclosure; no leakage point Observing
4.24.8 See Table 4.24.8 for inspection and acceptance on installation of combustion engine
main-body pipeline
Table 4.24.8 Installation of combustion engine main-body pipeline
Inspection method and
Inspection item Property Unit Quality criteria
measuring instrument
285
Correct direction; flexible
Valve installation Site inspection
operation
Pipeline blow-down and cleanliness Clean and without rust and foreign Air for instrument or nitrogen
Dominant
inspection bodies purging inspection
4.24.9 See Table 4.24.9 for inspection on the implementation performance of subsection
project compulsory provisions for installation of combustion engine main body.
Table 4.24.9 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of combustion engine main body
________Unit Project number:
Subsection project Main body installation of combustion
Unit project name Combustion engine installation
name engine
Implementation
SN Inspection item Related information
performance
286
shall be inspected and identified necessarily. All performances of
quality steel, alloy steel, high-pressure and high-temperature
welding material, lubricating-oil (grease) and fire-resistant oil must
meet design requirements and national standards before
application.
287
Acceptance result
Date Date
4.24.10 See Table 4.24.10 for inspection on the implementation performance of subsection
project compulsory provisions for installation of combustion engine main-body pipes
Table 4.24.10 Inspection table on the implementation performance of subsection project compulsory
provisions for installation of combustion engine main-body pipes
________Unit Project number:
Installation of combustion engine auxiliary Installation of combustion
Unit project name Subsection project name
device engine main-body pipes
Implementation Related
SN Inspection item
performance information
288
All pipes shall be constructed according to design drawing. If it need
3 modify design or adopt substitute material, it must apply to the design
unit and handle it according to relevant system.
Alloy-steel pipe, pipe fittings, pipe auxiliaries and valve shall be carried
4 out spectrum recheck piece by piece before using, and make marks for
material
During pressure test of pipe system, the pressure shall be maintained for
10min after reaching test pressure and then drop to design stress;
comprehensive inspection shall be carried out for all joints. There shall
5
not be water seepage or leakage mark on the overall system except partial
places obstruct of pump or valve padding and no deformation by visual
observation.
Acceptance result
Date Date
4.25 See Table 4.25 for inspection on the implementation performance of subsection project
compulsory provisions for gas equipment installation subsection project, fuel-fired equipment
installation subsection project as well as other equipment installation of combustion engine.
Table 4.25 Inspection table on the implementation performance of subsection project compulsory provisions
for ( )
________Unit Project number:
Combustion engine auxiliary device and Subsection project
Unit project name
accessory machinery installation name
Implementation Related
SN Inspection item
performance information
289
inspection and defect treatment after reaching installation quality
standard.
Alloy-steel pipe, pipe fittings, pipe auxiliaries and valve shall be carried
4 out spectrum recheck piece by piece before using, and make marks for
material
During pressure test of pipe system, the pressure shall be maintained for
10min after reaching test pressure and then drop to design stress;
comprehensive inspection shall be carried out for all joints. There shall
5
not be water seepage or leakage mark on the overall system except
partial places obstruct of pump or valve padding and no deformation by
visual observation.
Acceptance result
Date Date
4.26.1 Unit project construction Identification and approval for turbine generator main-body
installation.
1 See Table 4.26.1-1 for Identification and approval of platen contact inspection.
Table 4.26.1-1 Identification and approval table of platen contact inspection
________Unit Project number:
Subsection project
Unit project name
name
290
Confirmation and signature description or sketch map:
The contact surface of platen and bearing pedestal sliding block as well
1
as platen and steam cylinder shall be smooth and clean without rag.
The contact surface of platen and bearing pedestal sliding block as well
2 as platen and steam cylinder shall be tight and inspected with 0.05mm
feeler gauge to prevent wedging.
The contact area of casting platen shall be inspected with red lead
powder or red stamp-pad ink; the area with contact points per sq. cm
3
shall account for over 75% of the total area and shall be distributed
uniformly.
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
2 See Table 4.26.1-2 for Identification and approval table of bearing pedestal oil-filling test
Table 4.26.1-2 Identification and approval table of bearing pedestal oil-filling test
________Unit Project number:
Subsection project
Unit project name
name
291
Confirmation and signature description or sketch map: Oil-filling test shall be carried out on oil chamber of bearing pedestal; it
shall be repaired and tested again when there is leakage during oil-filling test.
Before oil-filling test, the oil chamber and oil line of bearing pedestal
1
shall be inspected and shall be smooth and clean inside and outside.
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
3 See Table 4.26.1-3 for Identification and approval of bearing pedestal covering
Table 4.26.1-3 Identification and approval table of bearing pedestal covering
________Unit Project number:
Subsection project
Unit project name
name
292
Confirmation and signature description or sketch map:
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
4 See Table 4.26.1-4 for Identification and approval of steam cylinder appearance inspection.
Table 4.26.1-4 Identification and approval table of steam cylinder appearance inspection
________Unit Project number:
Subsection project
Unit project name
name
293
Confirmation and signature description or sketch map:
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
5 See Table 4.26.1-5 for Identification and approval of turbine rotor appearance inspection.
294
Table 4.26.1-5 Identification and approval table of turbine rotor appearance inspection
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
Cleanliness of steam seal, shaft neck, thrust disc, gear wheel, worm gear
1
and coupling
Weight and locking key on wheel hub; center hole closure plate and other
2
locking parts
5 Rotor tortuosity
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
295
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
6 See Table 4.26.1-6 for Identification and approval on inspection and sealing of high and
medium pressure nozzle box
Table 4.26.1-6 Identification and approval table on inspection and sealing of high and medium pressure
nozzle box
________Unit Project number:
Subsection project
Unit project name
name
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
296
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
7 See Table 4.26.1-7 for Identification and approval of inspection before steam turbine
covering
Table 4.26.1-7 Identification and approval table of inspection before steam turbine covering
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
297
11 Various engineering construction schemes, systems and documents
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
8 See Table 4.26.1-8 for Identification and approval of steam turbine covering
Table 4.26.1-8 Identification and approval table of steam turbine covering
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
The inside of equipment shall be clean and in good order and condition
1
during covering
4 High-temperature bolt up
Paint laying at the steam cylinder horizontal joint surface and parts joint
5
surface
298
9 Sealing the opening in time after covering
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
9 See Table 4.26.1-9 for Identification and approval of steam turbine foundation before
secondary grouting
Table 4.26.1-9 Identification and approval table of steam turbine foundation before secondary grouting
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
299
least 24h.
The platen grouting screw has been correctly installed; the baffle plate
of secondary grouting has been correctly installed and has no effect on
5
expansion; the surface between platen and secondary grouting shall be
cleaned up without paint and oil stain
The spot welding of foundation iron gasket has been completed; the
foundation bolt has been adjusted to the cylinder body and the central
position of stator toe-board foundation bolt hole; the inside of
6
foundation bolt hole has been cleaned up without any impurity; the
foundation bolt subplate and foundation concrete are well contacted to
ensure no motar leakage.
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
10 See Table 4.26.1-10 for Identification and approval on installation and inspection of
communicating pipe.
Table 4.26.1-10 Identification and approval table on installation and inspection of communicating pipe
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
300
1 Cold drawing value of communicating pipe
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
11 As for steam port and governing valve disassembling during washing pipe, it shall carry
out tightness inspection after washing pipe. See Table 4.6.1-11 for Identification and approval
on tightness inspection of steam port and governing valve.
Table 4.26.1-11 Identification and approval table (after washing pipe) on tightness inspection of steam port
and governing valve
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
The appearance of valve disc and valve seat shall be smooth and clean
1
without scar
2 The valve rod and valve disc acts flexibly without jam
The area between valve disc and valve seat shall be inspected by painting
3 method or scribing pencil marks; the whole ring shall be contacted
continuously and uniform in width
301
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
12 See Table 4.26.1-12 for Identification and approval on inspection of fire resistant oil
system before flashing
Table 4.26.1-12 Identification and approval table on inspection of fire resistant oil system before flashing
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
The system and temporary measures have been installed and completed;
1
the connection shall be correct and meet the requirement of drawing
10 The sand box, fire extinguisher and other fire-fighting tools shall be well
302
prepared
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
13 See Table 4.26.1-13 for Identification and approval on oiliness laboratory examination of
fire-resistant oil after flashing
Table 4.26.1-13 Identification and approval on oiliness laboratory examination of fire-resistant oil after
flashing
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
Oil sample shall be taken at from filter before scavenge oil, main
1
oil-drainage header pipe or sampling point required by the manufacturer
303
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
14 See Table 4.26.1-14 for inspection and acceptance on tightness inspection of oil cooler
Table 4.26.1-14 Inspection and acceptance table on tightness inspection of oil cooler
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
1 The water for test shall be clean and without any impurity
304
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
15 See Table 4.26.1-15 for Identification and approval on oil tank inspection before sealing
Table 4.26.1-15 Identification and approval table on oil tank inspection before sealing
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
1 The internal parts are complete and correct; the fasteners are reliable
The inside of oil tank is clean and free from scales and welding slags; the
3 inner surface is undissolvable in paints for turbine oil and without any
falling off; the paints dissolvable in turbine oil have been removed.
305
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
16 See Table 4.26.1-16 for Identification and approval of inspection before lubrication
(sealing) oil flushing
Table 4.26.1-16 Identification and approval table of inspection before lubrication (sealing) oil flushing
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
The system (including accident oil discharge system) and temporary measures
1 have been installed and completed; the connection shall be correct and meet
requirements of drawing
The specification of temporary filter screen and the flow area meet the
6
requirement
306
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
17 See Table for Identification and approval of oiliness inspection after lubrication (sealing)
oil flushing
Table 4.26.1-17 Identification and approval table of oiliness inspection after lubrication (sealing) oil flushing
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
Identification and approval record description: Oiliness laboratory report shall be provided.
1 Taking oil sample from sampling points of oil tank and oil cooler
Acceptance result:
307
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
18 See Table 4.26.1-18 for Identification and approval of generator rotor tightness test
Table 4.26.1-18 Identification and approval table of generator rotor tightness test
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
2 Test pressure
3 Test time
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
308
19 See Table 4.26.1-19 for Identification and approval of generator stator tightness test
Table 4.26.1-19 Identification and approval table of generator stator tightness test
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
2 Test pressure
3 Testing time
4 Tightness
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
20 See Table 4.26.1-20 for Identification and approval of generator crossed rotor
Table 4.26.1-20 Identification and approval table of generator crossed rotor
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
309
Confirmation and signature description or sketch map:
3 Rotor-crossing process
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
21 See Table 4.26.1-21 for Identification and approval of generator end cap installation and
sealing
Table 4.26.1-21 Identification and approval table of generator end cap installation and sealing
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
310
Confirmation and signature description or sketch map:
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
22 See Table 4.26.1-22 for identification and approval of tightness test on generator hydrogen
cooler
Table 4.26.1-22 Identification and approval table of tightness test on generator hydrogen cooler
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
311
Confirmation and signature description or sketch map:
4 Leakage detection
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
23 See Table 4.26.1-23 for Identification and approval table of water pressure test on exciter
air-cooled condenser
Table 4.26.1-23 Identification and approval table of water pressure test on exciter air-cooled condenser
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
312
Confirmation and signature description or sketch map:
4 Leakage detection
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
24 See Table 4.26.1-24 for identification and approval of generator complete air pressure test
Table 4.26.1-24 Identification and approval table of generator complete air pressure test
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
313
Confirmation and signature description or sketch map:
1 Test pressure
3 Air leakage
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
25 See Table 4.26.1-25 for identification and approval table of generator internal cooling
water system flashing
Table 4.26.1-25 Identification and approval table of generator internal cooling water system flashing
________Unit Project number:
Subsection project
Unit project name
name
Identification and approval description or sketch map: (Water quality report shall be provided)
314
SN Inspection item Inspection result
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
26 See Table 4.26.1-26 for Identification and approval on appearance quality acceptance of
turbine generator main-body installation unit project.
Table 4.26.1-26 Identification and approval table on appearance quality acceptance of turbine generator
main-body installation unit project
________Unit Project number:
Main body installation of turbine Construction
Unit project name
generator organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
The platform, stairway and handrail shall be stable and with good
technology
Tightness of equipment
2 No leakage point
and system
315
The material, procedure, thickness and color shall meet the
requirement of design
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
The exposed screw thread shall be united and meet the specification
4.26.2 Identification and approval on unit project construction of turbine generator auxiliary
device installation
1 See Table 4.26.2-1 for Identification and approval of condenser inspection before crossing
pipe
Table 4.26.2-1 Identification and approval table of condenser inspection before crossing pipe
________Unit Project number:
Subsection project
Unit project name
name
Subitem project
Inspection lot name
name
316
Confirmation and signature description or sketch map:
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
2 See Table 4.26.2-2 for Identification and approval on inspection before connection of low
pressure cylinder and condenser
Table 4.26.2-2 Identification and approval table on inspection before connection of low pressure cylinder
317
and condenser
________Unit Project number:
Subsection project
Unit project name
name
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
318
Manufacturing
Date
organization
Development
Date
organization
3 See Table 4.26.2-3 for Identification and approval of condenser watering test inspection
Table 4.26.2-3 Identification and approval table of condenser watering test inspection
________Unit Project number:
Subsection project
Unit project name
name
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction Date
319
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
4 See Table 4.26.2-4 for Identification and approval on hidden inspection of drain flash tank
Table 4.26.2-4 Identification and approval table on hidden inspection of drain flash tank
________Unit Project number:
Subsection project
Unit project name
name
320
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
5 See Table 4.26.2-5 for Identification and approval on tightness test of air-cooling system
Table 4.26.2-5 Identification and approval table on tightness test of air-cooling system
________Unit Project number:
Subsection project
Unit project name
name
321
Confirmation and signature description or sketch map:
2 Whether the pressure drop of system within 24h meets the requirement
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
6 See Table 4.26.2-6 for Identification and approval of deaerator (water tank) before main
body sealing
Table 4.26.2-6 Identification and approval table of deaerator (water tank) before main body sealing
322
________Unit Project number:
Subsection project
Unit project name
name
2 Internal cleaning
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
323
Development
Date
organization
7 See Table 4.26.2-7 for Identification and approval on water pressure test of heat exchanger
(water side or steam side)
Table 4.26.2-7 Identification and approval table on water pressure test of heat exchanger (water side or
steam side)
________Unit Project number:
Subsection project
Unit project name
name
1 The water for test shall be clean and without any impurity
6 No deformation on enclosure
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
324
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
8 See Table 4.26.2-8 for Identification and approval on unit project appearance quality
acceptance of turbine generator auxiliary device installation
Table 4.26.2-8 Identification and approval table for unit project appearance quality acceptance of turbine
generator auxiliary device installation
________Unit Project number:
Construction
Unit project name Turbine generator auxiliary device installation
organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
1 Overall appearance quality The thermal insulation appearance shall be in good condition
The platform, stairway and handrail shall be stable and with good
technology
Tightness of equipment
2 No leakage point
and system
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
5 Thermal insulation The surface shall be smooth, without damage and shedding
engineering
The rendering coat shall be smooth and without cracks
325
specification
326
2 Drainage hole of steam cylinder
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
2 See Table 4.26.3-2 for Identification and approval on water pressure test of pump motor
cooler
Table 4.26.3-2 Identification and approval table on water pressure test of pump motor cooler
________Unit Project number:
Subsection project
Unit project name
name
327
Confirmation and signature description or sketch map:
1 No deformation on enclosure
3 Test pressure
4 Testing time
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
3 See Table 4.26.3-3 for unit project appearance quality acceptance Identification and
approval of turbine generator auxiliaries installation
Table 4.26.3-3 Identification and approval table on unit project appearance quality acceptance of turbine
328
generator auxiliaries installation
________Unit Project number:
Construction
Unit project name Installation of turbine generator auxiliaries
organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
1 Overall appearance quality The thermal insulation appearance shall be in good condition
The platform, stairway and handrail shall be stable and with good
technology
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
pollution
329
Without construction residual
4.26.4 Unit project construction Identification and approval on other equipment installation
of steam turbine generator units
1 See Table 4.26.4-1 for Identification and approval of bridge cranes load test
Table 4.26.4-1 Identification and approval table of bridge cranes load test
________Unit Project number:
Subsection project
Unit project name
name
During load test, the hook lifting as well as large and small vehicle travelling are
1
stable and free of no jam and strange sound
The brake is sensitive and reliable; the limit switch and interlock protection device
2
operates correctly and reliably
10min after 1.25 times rated static load test, the bridge framework deflection shall
restore to the original state and there is no residual deformation and abnormal
5
phenomena; The rotary hook gape is free of residual deformation; there is no crack on
steel pieces and welded joints
During 1.1 times rated dynamic loading test, the lifting of large and small hook is
6
stable; the steel wire of rotary drum is lined neatly
330
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
2 See Table 4.26.4-2 for Identification and approval of ordinary crane load test
Table 4.26.4-2 Identification and approval table of ordinary crane load test
________Unit Project number:
Subsection project
Unit project name
name
During unload test, the hook lifting as well as large and small vehicle
1
travelling are stable and free of no jam and strange sound
2 10min after 1.25 times rated load at 100mm height, the brake shall be reliable
331
in inspection; there shall be no looseness on steel wire and no deformation on
hook
The rated load rises and falls for 15min; the hook lifting and trolley traveling
3 is stable and free of no jam and strange sound; after braking, the gliding
distance of hoisting objects is less than or equal to 50mm
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
3 See Table 4.26.4-3 for Identification and approval for unit project appearance quality
acceptance on other equipment installation of steam turbine generator units
Table 4.26.4-3 Identification and approval table for unit project appearance quality acceptance on other
equipment installation of steam turbine generator units
________Unit Project number:
Other equipment installation of steam Construction
Unit project name
turbine generator units organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
332
The platform, stairway and handrail shall be stable and with good
technology
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
4.26.5 See Table 4.26.5 for Identification and approval for unit project appearance quality
acceptance on water-circulating pump room equipment, public-water pump house equipment
and water-collecting pump house equipment.
Table 4.26.5 Identification and approval table for unit project appearance quality acceptance on
water-circulating pump room equipment, public-water pump house equipment and water-collecting pump
333
house equipment
________Unit Project number:
Construction
Unit project name
organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
The platform, stairway and handrail shall be stable and with good
technology
Tightness of equipment
2 No serious leakage point
and system
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
334
Construction organization Date
4.26.6 Inspection table and construction Identification and approval on the implementation
performance of unit project compulsory provisions for main body installation of combustion
engine
1 See Table 4.26.6-1 for Identification and approval on manhole door sealing inspection at air
inflow area
Table 4.26.6-1 Identification and approval table on manhole door sealing inspection at air inflow area
________Unit Project number:
Subsection project
Unit project name
name
The parts inside air purification and sound deadening system have been
1
well installed and in good condition
The expansion joint connected with inlet chamber has been installed and
2
meets the requirement
The inside of air purification and sound deadening system are clean and
3
free of rust, weld beading and foreign bodies
4 No ray penetrates the inside of air purification and sound deadening system
Statistic list on the quantity of bolts and nuts inside system after fine
5
filtration
The parts (excluding fine filtration) inside air purification and sound
8
deadening system have been improved
The air purification and sound deadening system have been connected with
9
expansion joint
10 The inside shall be clean and without rust, weld beading and foreign bodies
335
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
2 See Table 4.26.6-2 for Identification and approval on manhole door sealing inspection at
exhaust area
Table 4.26.6-2 Identification and approval table on manhole door sealing inspection at exhaust area
________Unit Project number:
Subsection project
Unit project name
name
1 The exhaust system has been well installed and in good condition
The expansion joint connected with exhaust part has been installed and
2
meets the requirement
The inside of exhaust system shall be clean and without rust, weld
3
beading and foreign bodies
336
4 The exhaust system is dark inside and no penetrated ray
The spot welding insurance of argon arc welding for nuts has been
5
completed
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
3 See Table 4.26.6-3 for Identification and approval on enclosure translucidus inspection
Table 4.26.6-3 Identification and approval table on enclosure translucidus inspection
________Unit Project number:
Subsection project
Unit project name
name
337
Confirmation and signature description or sketch map:
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
4 See Table 4.26.6-4 for Identification and approval on unit project appearance quality
acceptance of combustion engine main-body installation
Table 4.26.6-4 Identification and approval table on unit project appearance quality acceptance of
338
combustion engine main-body installation
________Unit Project number:
Main body installation Construction
Unit project name
of combustion engine organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
1 Overall appearance quality The thermal insulation appearance shall be in good condition
The platform, stairway and handrail shall be stable and with good
technology
Tightness of equipment
2 No leakage point
and system
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
339
management Without water, oil or ash accumulation
The pipes of fire extinguishing system have been carried out with
1
strength test
340
Acceptance result:
Acceptance
Quality acceptance opinions Acceptance signature
organization
Construction
Date
organization
Supervision
Date
organization
Manufacturing
Date
organization
Development
Date
organization
2 See Table 4.26.7-2 for Identification and approval for unit project appearance quality
acceptance on installation of combustion engine auxiliaries and accessory machines
Table 4.26.7-2 Identification and approval table for unit project appearance quality acceptance on
installation of combustion engine auxiliaries and accessory machines units
________Unit Project number:
Installation of combustion engine Construction
Unit project name
auxiliaries and accessory machines organization
Acceptance result
SN Acceptance item name
Qualified Unqualified
1 Overall appearance quality The thermal insulation appearance shall be in good condition
The platform, stairway and handrail shall be stable and with good
technology
341
The material, procedure, thickness and color shall meet the
requirement of design
3 Painting construction The color and luster shall be consistent, uniform and without flow
mark and wrinkle
The exposed screw thread shall be united and meet the specification
5.1.1 Single project as the civil work, boiler unit, steam turbine generator unit, thermal
meter and its control device, pipe and pipe system, the equipment and the system with the
water treatment and hydrogen generation, welding engineering, processing preparation and
electrical device installation in thermal power generation project shall be evaluated
342
respectively.
5.1.2 Single project as boiler unit, steam turbine generator unit, thermal meter and its
control device, pipe and pipe system, the equipment and the system with the water treatment
and hydrogen generation and processing preparation in thermal power generation project shall
be assessed respectively according to this regulation.
5.1.3 Those project construction organizations engaged in creating high quality project shall
organize the participating organizations to formulate quality objective, conduct objective
management, develop quality planning, highlight corresponding responsibilities, strengthen
process control and intensify quality acceptance in each phase before the commencement of
projects.
5.1.4 Construction organizations to assess and construct single project shall inspect
themselves according to the requirements specified in this Part. Development organizations
shall be responsible for organizing supervision organizations or other assessment
organizations to assess. In addition, the supervision organizations or other assessment
organizations shall summarize and analyze the assessment results and then write assessment
report.
5.1.5 During the assessment of single project, the actual project quality and technical project
information shall be comprehensively inspected.
5.1.6 Construction quality of single project shall be evaluated after all the acceptance of unit
project is qualified.
5.1.7 The construction quality evaluation of this single project shall be carried out
respectively according to main body and sub-system installation of turbine generator,
accessory machinery and auxiliary device in the main power house, accessory machinery and
auxiliary device out of the main power house, pipeline of steam turbine, insulation and
painting of main body (include steam feed pump) equipment piping of steam turbine,
combustion engine and its auxiliary device [six project position (scope) in total].
5.1.8 Each project position (scope) shall be evaluated according to the quality guarantee in
construction site, performance testing, quality records, size deviation and actual limit
measurement, implementation performance of compulsory provision and appearance quality.
Corresponding weighing value of each evaluation project shall be given according to its work
load and importance in this project position (scope).
5.1.9 Each evaluation item shall consist of several kinds of evaluation which shall specify
the standard score according to the importance. During the evaluation of construction quality,
each evaluation is judged as Class I, Class II or Class III which are corresponding to the
standard scores of 100%, 85% and 70% respectively.
5.1.10 During project quality evaluation, attention shall be given to promote scientific
management, strengthen project quality control, improve management mechanism and persist
to improve evaluation competence.
5.1.11 Control of project quality shall highlight material receiving inspection, process
quality control and function effectiveness test so as to improve management efficiency and
operating skills.
5.1.12 During the evaluation of project quality, attention shall be given to apply the advance
of science and technology as well as environmental protection.
5.1.13 The score for the evaluated excellent construction quality of single project shall be
343
greater than or equal to 85 scores; those projects with total score being at last 92 shall be
extremely excellent projects.
5.2.1 The evaluated weight value of position (range) contained in single project is specified
according to the comprehensiveness of importance, difficulty and work load. Evaluation of
single project position (range) shall be carried out according to those specified in Table 5.2.1.
Table 5.2.1 Distribution Table on the Weight Value of Single Project Position (Range) of Steam Turbine
Generator Units
Weight value
Gas-steam combined
Project position (scope) Conventional fossil
cycle turbine generator Air-cooling unitb
fuel steam power unit
unita
Note : If item of project position (scope) was missing in the table, the weight value is distributed according to actual work load
but it shall be integral value.
a The weight value of gas-steam combined cycle turbine generator unit is distributed in the type of "single-axle" configuration.
b For the air-cooling unit, the air-cooling condenser is included in the project position (scope) of accessory machinery and
auxiliary device in main power house
5.2.2 The quality evaluation for each project position (scope) shall be include the quality
guarantee condition in construction site, performance inspection, quality records, size
deviation and actual limit measurement, implementation performance of compulsory
provision and appearance quality.
5.2.3 Weight value of the evaluation item shall be according to those specified in Table
5.2.3.
Table 5.2.3 Distribution Table on the Weight Value of Evaluation Item in Project Position (Scope)
Project position (scope)
344
equipment,
pipe
insulation
and painting
Implementation performance of
5 (15) (15) (10) (15) (15) (15)
compulsory provision
Note: If there is nonexistent evaluation item in the table, its weight value shall be calculated according to full score.
5.3.1 Construction quality of single project shall be evaluated item by item according to the
project position (scope) and evaluation item content of this Part; the construction quality shall
be statistically analyzed basing on the records of random inspection on construction site as
well as the quality acceptance records of each inspection lot, subitem project, subsection
project and unit project; in addition, the construction quality is scored according to project
position (scope) and the requirements specified in evaluation item (corresponding table).
5.3.2 Single project shall not be evaluated to be excellent where there is any of the
following conditions:
1 To use the materials and products which China forbids publically.
2 The obtained score of any project position (scope) or evaluation item is less than 85%
standard score.
5.4.1 Contents and methods to evaluate the quality guarantee condition on construction site
shall meet the following requirements:
1 If the followings can be practically achieved, the quality guarantee on construction site is
Class I and gains 100% standard score: sound quality management, liability system and
project-department organizations; effectively-operated quality management system; perfect
technologies, working management system, site acceptance system and sampling inspection
system of equipments and materials. If sound quality management and liability systems can
be basically achieved, the quality guarantee on construction site is Class II and gains 85%
standard score. And if main quality management and liability systems can be basically
achieved, the quality guarantee on construction site is Class III and gains 70% standard score.
2 The quality guarantee on construction site with standard quality inspection and acceptance
required by projects, standard construction technologies, complete working methods,
345
operation specifications and operational guide books which have strong pertinency and
operability are Class I and gain 100% standard score; the quality guarantee on construction
site with standard and complete quality inspection and acceptance, standard construction
technologies, basically complete operation specifications and operation guide books which
have relatively strong pertinency and operability are Class II and can gain 85% standard score;
and the quality guarantee on construction site with standard and complete quality inspection
and acceptance, standard major construction technologies and complete operation
specifications as well as operation guide books which have general pertinency and operability
are Class III and gain 70% standard score.
3 The quality guarantee on construction site with complete processes to develop and
approve construction management plan, construction scheme, construction measures and risk
prevention measures which have strong pertinency and operability, are seriously implemented
and achieve notable effectiveness is Class I and gains 100% standard score; the quality
guarantee on construction site with complete development and approval processes, relatively
strong pertinency and operability, being basically implemented and achieving preferable
effectiveness is Class II and gain 85% standard score; and the quality guarantee on
construction site with sound development and approval processes, being generally
implemented is Class III and gains 70% standard score.
4 The quality guarantee on construction site with specified quality objective, proper &
effective management system and notable implementation effectiveness is Class I and gains
100% standard score; the quality guarantee on construction site with preferable
implementation effectiveness is Class II and gains 85% standard score; and the quality
guarantee on construction site with general implementation effectiveness is Class III and
gains 70% standard score.
5.4.2 Content and methods to evaluate the performance inspection shall meet the following
requirements:
1 Inspection and test of construction process as well as by-part trial operation shall meet the
requirements specified in relevant standards; the performance inspection provided with
complete and standard test records and reports is Class I and gains 100% standard score;
2 Inspection and test of construction process as well as by-part trial operation shall meet the
requirements specified in relevant standards; the performance inspection provided with
complete and basically standard test records and reports is Class II and gains 85% standard
score;
3 The above test items and test conditions basically meet the requirements specified in
relevant standards; and the performance inspection provided with basically complete test
records and reports is Class III and gains 70% standard score.
4 To sample test records and reports; to measure on site, if necessary.
5.4.3 Content and methods to evaluate the quality records shall meet the following
requirements:
1 Those quality records with material & equipment quality certificates (outgoing quality
certificates), complete site acceptance record, construction record, construction test record,
data; actual and effective content, standard classification & rearrangement, perfect reviewing
and signing procedures and meeting the requirements specified in design and standards are
Class I and gain 100% standard score. Those quality records with complete information,
346
relatively complete data, actual and effective content, relatively standard rearrangement,
relatively complete reviewing and signing procedures and meeting the requirements specified
in design and standards are Class II and gain 85% standard score. Those quality records with
basically complete information, date; actual and effective content; basically standard
rearrangement, basically complete reviewing and signing procedures and basically meeting
the requirements specified in design and standards are Class III and gain 70% standard score.
2 To inspect the quantity and content of information.
5.4.4 Content and methods to evaluate the size deviation and actual limit measurement shall
meet the following requirements:
1 As for those evaluation items, if they are permissible deviation ones; the actual values
measured at each item measuring point reach the ones specified in standard and the actual
values of 80% and more measuring points are less than or equal to 0.8 times the ones
specified in standard, they are Class I and gain 100% standard score. For those evaluation
items, if the actual values of each measuring point reach the ones specified in standard and the
average actual values of greater than 50% (including 50%) but less than 80% measuring
points are less than or equal to 0.8 times the ones specified in standard; they are Class II and
gain 85% standard score. For those evaluation items, if the actual values of each measuring
point reach the ones specified in standard; they are Class III and gain 70% standard score.
2 For those evaluation items, if they are two-way limit items, the actual values measured at
each measuring point meet the ones specified in standard and the actual values of at least 50%
measuring points approximate to the medium limit value; they are Class I and gain 100%
standard score; those evaluation items all of whose actual values at each measuring point are
within the limit specified in standard are Class II and gain 85% standard score; those
evaluation items whose measuring points meet the standard specification after treatment are
Class III and gain 70% standard score.
3 For those evaluation items, if they are one-way limit items and all the actual values at
each measuring point meet the ones specified in standard, they are Class I and gain 100%
standard score; those evaluation items whose measuring points meet the standard speciation
after treatment are Class III and gain 70% standard score.
4 If both permissible deviation and limit are available, the decision value is from the lower
Class.
5 Random 10 inspection lots or subentry project or all lots if they are less than 10 are
sampled from the relevant inspection lots or subitem projects in the category for analyzing
and calculating. If necessary, random measurement on site may be carried out.
5.4.5 Content and methods to evaluate the implementation performance of compulsory
provisions shall meet the following requirements:
1 Those compulsory provisions with detailed implementation plan, comprehensive content,
strong operability, strict implementation and complete inspection records are Class I and gain
100% standard score; those ones with implementation plan, comprehensive content,
preferable operability, preferable implementation and relatively complete inspection records
are Class II and gain 85% standard score; those ones with implementation plan,
comprehensive content, operability, implementation and inspection records are Class III and
gain 70% standard score.
2 To randomly inspect the executive plan, scheme measures, operation guide book,
347
construction record confirmation and signature and inspection records of compulsory
provisions.
5.4.6 Content and methods to evaluate the appearance quality shall meet the following
requirements:
1 The inspection points of each evaluation item are evaluated according to "good",
"ordinary" and "poor". Those evaluation item whose 90% or more inspection points are
"good" and the other inspection points are "ordinary" are Class I and gain 100% standard
score; those evaluation item whose greater than 70% (including 70%) and less than 90%
inspection points are "good" and the other inspection points are "ordinary" are Class II and
gain 85% standard score; those evaluation item whose greater than 30% (including 30% ) and
less than 70% inspection points are "good" and the other inspection points are "ordinary" are
Class III and gain 70% standard score.
2 To observe (to measure, if necessary); to inspect the quality acceptance records of
subsection project and to analyze and calculate.
5.5 Construction quality evaluation for main body and subsystem of turbine
generator
5.5.1 The evaluation method of quality guarantee condition on installation and construction
site of main body and sub-system of turbine generators shall be in accordance with those
specified in 5.4.1; the evaluation contents shall be inspected according to those specified in
Table 5.5.1 and comprehensive judgment shall be carried out.
Table 5.5.1 Evaluation Table on Quality Guarantee Condition for Construction Site
Installation of main body and sub-system of Construction
Project position (scope) Before 168h trial operation in full load
turbine generator stage
Construction Evaluation
organization organization
Evaluation result Re
Numb Deserved Obtaine
Evaluation contents mar
er score 100% 85% 70% d score
ks
348
Implementation effects of quality objective and management
4 20
system
Weight value: 15
Total deserved score:
Evalua Total obtained score:
tion Score of quality guarantee condition on installation and construction site of main body and sub-system of turbine
result generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date
5.5.2 Inspection and evaluation for the installation performance of main body and
sub-system of turbine generators.
1 The contents of inspection and evaluation for installation performance of main body and
sub-system of turbine generators shall be carried out according to Table 5.5.2 and the
comprehensive judgment shall be carried out.
Table 5.5.2 Inspection and Evaluation Table on Performance
Installation of main body and Construction
Project position (scope) Before 168h trial operation in full load
sub-system of turbine generator stage
Evaluation
Construction organization
organization
Weight value: 30
Total deserved score:
Total obtained score:
Evaluation
Score of performance inspection for installation engineering of turbine generator main body=obtained score/deserved
result
score*weight value=
Evaluator (signature):
Date
2 Evaluation methods for the installation performance inspection of main body and
349
sub-system of turbine generators are as follows:
1) Rating of steam turbine
It is Class I, if the test value of maximum continuous rating and nominal rating of steam
turbine reaches to 100% contract value; it is rated as Class II, if the test value reaches to95%
(included)~100&; and it is rated as Class III, if the test value is lower than 95%.
2) Oil system oiliness of steam turbine generator unit
It is Class II if the lubricating oil quality reaches NAS7 and the EH quality reaches to NAS5.
It is rated as rated as Class I if any of the item surpasses Class II. It is rated as rated as Class
III if any of the item inferior to Class II.
3) Cooling water quality of generator stator (rotor)
It is Class I if the electrical conductivity 1.5 s/cm during the load on trial operating period;
it is rated as Class II if the electrical conductivity is 1.5s/cm~2s/cm and it is rated as Class
III if the electrical conductivity>2S/cm.
4) Shafting vibration and bearing temperature of steam turbine generator unit
The bearing temperature shall meet the requirements of manufacturer; it is Class I if shafting
vibration 70m; it is rated as Class II if the shafting vibration is 70m~120m and it is rated
as Class III if sampling tube 120m.
5) Bear vibration and temperature of rotating equipment for the steam turbine oil system and
generator water cooling system
The bearing temperature shall meet the requirements of manufacturer; it is Class I if the
vibration (See Annex C) is excellent; it is rated as Class II if the vibration is good and it is
rated as Class III if the vibration is qualified.
6) Cylinder expansion, differential expansion and axial displacement of rotor
The cylinder expansion, differential expansion and rotor axial displacement shall meet the
requirements of drawing; it is rated as Class I if the cylinder expansion is smooth and without
any jam or jump phenomena; it is rated as Class II if the cylinder expansion is poor but can be
smooth and without jam after treatment; it is rated as Class III if the cylinder expansion is
with slightly poor and with jam.
7) Vacuum tightness of steam turbine
Water cooling unit: it is rated as Class I if the tested vacuum value of steam
turbine0.3kPa/min; it is rates as Class II if the test value is 0.3 kPa/min~0.4 kPa/min; and it
is rated as Class III if the test value>0.4kPa/min.
Air-cooling unit: it is rated as Class I if the tested vacuum value of steam turbine0.2kPa/min;
it is rates as Class II if the test value is 0.2 kPa/min~0.3 kPa/min; and it is rated as Class III if
the test value>0.3kPa/min.
8) Air test for whole set of generator
It is rated as Class I if the air leakage of generator is less than or equal to 80% of the value
specified by manufacturer; it is rated as Class II if the air leakage of generator is larger than
80% of the required value but less than required value; and it is rated as Class III if the air
leakage of generator is larger than or equal to required value.
9) Tightness test for main throttle valve
Where the rated steam pressure, normal vacuum and the no load operation of unit, it is rated
as Class I if the speed drop under 800 r/min after the shutdown of main throttle valve; it is
rated as Class II if the speed drop to 800r/min~1000r/min; and it is rated as Class III if the
350
speed drop to higher than 1000r/min.
5.5.3 The recording and evaluation method of installation quality of main body and
sub-system of turbine generators shall be in accordance with those specified in 5.4.3; the
evaluation contents shall be inspected according to those specified in Table 5.5.3 and
comprehensive judgment shall be carried out.
Table 5.5.3 Recording and Evaluation Table on Installation Quality
Installation of main body and Construction
Project position (scope) Before 168h trial operation in full load
sub-system of turbine generator stage
Evaluation
Construction organization
organization
4 Installation records 20
Weight value: 20
Total deserved score:
Total obtained score:
Evaluation
Record score of installation engineering quality of main body and sub-system of turbine generators=obtained
result
score/deserved score*weight value=
Evaluator (signature):
Date
5.5.4 Evaluation for the installation dimension deviation and actual limit measurement of
main body and sub-system of turbine generators
1 The evaluation for the size deviation and actual limit measurement of main body and
sub-system of turbine generators shall be carried out according to those specified in Table
5.5.4 and comprehensive judgment shall be carried out.
Table 5.5.4 Evaluation Table on Size Deviation and Actual Limit Measurement
351
Installation of main body and Construction
Project position (scope) Before 168h trial operation in full load
sub-system of turbine generator stage
Construction Evaluation
organization organization
352
Quality Acceptance Standard; the permissible deviation shall be in accordance with
provisions of manufacturer.
4) Magnetic center and air gap of generator
The counting of actual measuring point number and permissible deviation shall comply with
the requirements of measuring position specified by manufacturer.
5) Coupling center of auxiliary rotating machine
The auxiliary rotating machine includes pump and smoke exhaust fan of oil system and
generator internal cooling water system; the coupling center must meet the requirements of
DL 5011; four points shall be set on each pair of couplings and two points on circle deviation
and end face opening respectively. All the pumps and blowers shall be counted together.
6) Installation position of equipment (device)
Equipments (devices) include turbine generators and hydrogen, oil and water system
equipments (devices); the installation positions include center, elevation, levelness and
verticality; the permissible deviation is determined according to 4 Construction Quality
Acceptance Standard; the measuring point number is the counted point number.
5.5.5 The evaluation method for the management and implementation performance of
installation compulsory provision of main body and sub-system of turbine generators shall be
in accordance with those specified in 5.4.5; the evaluation contents shall be inspected
according to those specified in Table 5.5.5; comprehensive judgment shall be carried out.
Table 5.5.5 Evaluation Table for Management Implementation Performance of Compulsory Provision
Installation of main body and sub-system Construction
Project position (scope) Before 168h trial operation in full load
of turbine generator stage
Evaluation
Construction organization
organization
Weight value: 15
Total deserved score:
Total obtained score:
Evaluation
Score of management and implementation performance of compulsory provision for the installation engineering of
result
main body and sub-system of turbine generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date
5.5.6 Appearance quality evaluation for the installation of main body and sub-system of
353
turbine generators.
1 The appearance quality of main body and sub-system of turbine generators installation
shall be inspected and evaluated according to those specified in Table 5.5.6; comprehensive
judgment shall be carried out.
Table 5.5.6 Evaluation Table on Appearance Quality
Installation of main body and sub-system Construction
Project position (scope) Before 168h trial operation in full load
of turbine generator. stage
Evaluation
Construction organization
organization
1 Equipment appearance 20
8 Regional environment 10
Weight value: 10
Total deserved score:
Total obtained score:
Evaluation
Score of appearance quality for the installation engineering of main body and sub-system of turbine
result
generators=obtained score/deserved score*weight value=
Evaluator (signature):
Date
2 The evaluation methods for the appearance of the installation equipments of main body
and sub-system of turbine generators as well as the evaluation methods for the appearance
quality of pipe installation technology of hydrogen, oil and water system shall comply with
those specified in 5.4.6, and the counting method for the inspection points of evaluation shall
be implemented according to the following requirements:
1) Equipment appearance: Each independent equipment and its structure support are taken as
a evaluation point. It can be evaluated to be "good" if it is installed firmly, and is regular,
reasonable, clean and has no damage or lave.
2) Pipe installation technology of hydrogen, oil and water system: Each independent system
shall be taken as one evaluate point, and the point featured of reasonable pipe arrangement,
esthetic appearance, normative and firm installation of gradient and supporters and hangers,
well installed valves that are convenient for operation, concentrated and regular arrangement
of small diameter pipes with uniform spacing and the same turn radius shall be evaluated to
be "good".
354
3) Tightness of equipments and systems: The equipments and systems which have no leakage
points and the seepage points of which are no more than 3 points are divided as Class I; the
equipments and systems which have no leakage points and seepage points of which are no
more than 8 points are divided into Class II; the equipments and systems which have no
severe leakage points are divided as Class III.
4) Marks of equipment and system: the equipment and system with correct, complete, striking,
unified and normative as well as legibility and firm hanging mark without pollution are Class
I; the equipment and system with correct, basically complete, normative as well as legibility
and firm hanging mark without pollution are Class II; the equipment and system with correct,
basically complete and firm hanging mark are Class III.
5) Installation technology of platform, handrail and ladder access: platform, handrail and
ladder access with firm installation, smooth surface, intact coating, straight and even
horizontal pole, vertical pole, uniform spacing and height meeting the requirements, firm
welding, qualified weld appearance quality, skirting board, access ladder and safety cage
meeting the requirements are Class I; the ones with firm installation, basically reaching
smooth surface, intact coating and height meeting the requirements, firm welding, qualified
weld appearance quality, skirting board, access ladder and safety cage meeting the
requirements are Class II; the ones with firm installation and height meeting the requirements,
firm welding, skirting board, access ladder and safety cage meeting the requirements are
Class III.
6) Installation technology of enclosures and shields: the closure and shield with correct
installation position and free from knocking with rotary position, not influencing expansion,
with complete bolts, straight and even framework and panel, firm without deformation, tight
joint, regular installation, esthetic appearance, rustless and without scar are Class I; the ones
with correct installation position and free from knocking with rotary position, not influencing
expansion, with complete bolts, basically straight and even framework and panel, firm
without deformation and with regular installation are Class II; the ones with correct
installation position and free from knocking with rotary position, not influencing expansion,
with complete bolts and firmly installed framework and panel are Class III.
7) Painting and insulation: provided that the thickness and color of paint meet the design and
the paint color is matched harmoniously, the color and luster are uniform without flow mark,
wrinkle, gas bubble, shedding, rust and contamination; the insulation does not affect the
expansion, the surface is smooth without damage and shedding, the rendering coat is round
and smooth without cracks, the seaming of and metal enclosure meets the requirements and
the technique is of esthetic appearance, the point shall be classified into Class I; provided that
the paint thickness and color meet the design, the color and luster are basically uniform
without flow mark, wrinkle, gas bubble, shedding and rust; and the insulation does not affect
the expansion, the surface is smooth with damage and shedding, the rendering coat is
basically round and smooth without crack, and the seaming of metal shell meets the
requirements, the point shall be classified into Class II; provided that the paint thickness and
color meet the design, the color and luster are uniform basically; and the insulation does not
affect the expansion, the surface is basically flat and smooth, the rendering coat is basically
round and smooth and the seaming of metal shell meets the requirements, the point shall be
classified into Class III.
355
8) Regional environment: The trial operation area without oil, water or ash accumulation and
the articles with regular stacking and fixed management without sanitation dead angle is Class
I; the trial operation area without oil and water as well as ash accumulation and the articles
with regular stacking without waste stacking is Class II; the trial operation area basically
without oil and water as well as ash accumulation and the articles with basically regular
stacking is Class III.
5.6.1 The method to evaluate the quality guarantee condition on installation and
construction site of accessory machinery and auxiliary device in main power house shall be in
accordance with those specified in 5.4.1; the evaluation contents shall be inspected according
to Table 5.5.1 and the comprehensive judgment shall be carried out.
5.6.2 Inspection and evaluation on the installation performance of the accessory machinery
and auxiliary device in the main power house.
1 The inspection and evaluation for the installation performance of accessory machinery
and auxiliary device in main power house shall be carried out according to those specified in
Table 5.6.2 and comprehensive judgment shall be carried out.
Table 5.6.2 Evaluation Table on Performance Inspection
Installation of accessory machinery and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device in main power house stage
Evaluation
Construction organization
organization
7 Crane performance 5
Weight value: 25
Total deserved score:
Total obtained score:
Evaluation
Inspection score for the installation performance of accessory machinery and auxiliary device in main power
result
house=obtained score/deserved score*weight value=
Evaluator (signature):
Date
356
machinery and auxiliary device in main power house are as following.
1) Pump performance and capacity:
Provided that the performance and the volume test value of all the pumps reach to 100%
requirements of unit operation and design, it is Class I; the performance and volume test value
of main pump (condensate pump, electrically driven feed pump group, steam feed pump unit
and vacuum pump) reach to 100% requirements of unit operation and design, but the
performance and volume test value of other pumps reaching to 95% requirements of unit
operation and design, it is Class II; the performance and volume test value of main pump
(condensate pump, electrically driven feed pump group, steam feed pump unit and vacuum
pump) reach to 100% requirements of unit operation and design, but the performance and
volume test value of other pumps reaching to 90% requirements of unit operation and design,
it is Class III.
2) Bear vibration and temperature of rotating equipment:
All the bearing temperatures shall meet the requirements of manufacturer; the grease
lubricated bearing is generally not exceed 80 and the oiled bearing is generally not exceed
65~70. If the vibration (See Annex C) is excellent, it is Class I; if the vibration is good, it
is Class II; if the vibration is qualified, it is Class III.
3) Oil system oiliness of feed pump group (lubricating oil and pilot oil):
If the lubricating oil quality reaches to NAS7 and the pilot oil quality reaches to NAS5, it is
Class II; if any item is surpass Class II, it is rated as Class I; and if any item inferior to Class
II, it is rated as Class III.
4) Condenser vacuum:
At the full load of unit, if the condenser vacuum value meets the design value, it is Class I; if
the design value is 3kPa lower than design value, it is Class II; if the design value is 5kPa
lower than design value, it is Class III.
5) Setting of safety valve:
If the safety valve is tight and without leakage after the setting, the popping pressure meets
the design requirements, the re-seating pressure difference is less than 5% of popping pressure
and the data are complete, it is Class I; if the re-seating pressure difference is 5%~7% of the
popping pressure, it is Class II; and if the re-seating pressure difference is 7%~10% of the
popping pressure, it is Class III.
6) Ball back ration of rubber ball cleaning system:
If the recovery rate of rubber ball is 95% or higher, it is Class I; if the recovery rate of rubber
ball is between 90%~95%, it is Class II; and if the recovery rate of rubber ball is lower than
90%, it is Class III.
7) Crane performance:
It is Class I if all the parameters and indexes of crane performance meet the design
requirements safety license of the special equipments is obtained, the usage of crane is normal
and maintenance is perfect; it is Class II if the usage of crane is normal and maintenance is
good. It is Class III if the usage of crane is basically normal and maintenance is general.
5.6.3 The recording and evaluation method for the installation quality of accessory
machinery and auxiliary device in main power house shall be in accordance with those
specified in 5.4.3 of this Part; the evaluation contents shall be inspected according to those
specified in 5.6.3 and comprehensive judgment shall be carried out.
357
Table 5.6.3 Recording and Evaluation Table on Quality
Installation of accessory machinery and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device in main power house stage
Evaluation
Construction organization
organization
4 Installation record 15
Weight value: 20
Total deserved score:
Total obtained score:
Evaluation
Record score for installation quality of accessory machinery and auxiliary device in main power house=obtained
result
score/deserved score*weight value=
Evaluator (signature):
Date
5.6.4 Evaluation for the installation dimension deviation and actual limit measurement of
accessory machinery and auxiliary device in main power house
1 The evaluation for the installation dimension deviation and actual limit measurement of
accessory machinery and auxiliary device in main power house is listed as water-cooled
condenser and air-cooling unit. The evaluation for the installation dimension deviation and
actual limit measurement of water cooling accessory machinery and auxiliary device in main
power house shall be carried out according to those specified in Table 5.6.4-1, and the
comprehensive judgment shall be carried out.
Table 5.6.4-1 Evaluation Table on Dimension Deviation and Actual Limit Measurement
Installation of accessory machinery
Construction
Project position (scope) and auxiliary device in main power Before 168h trial operation in full load
stage
house
Evaluation
Construction organization
organization
358
score 100% 85% 70% score
Weight value: 10
Total deserved score:
Evaluation Total obtained score:
result Score for the dimension deviation and actual limit measurement of installation engineering of accessory machinery
and auxiliary device in main power house=obtained score/deserved score*weight value=Evaluator (signature):
Date
2 The evaluation method for the installation dimension deviation and actual limit
measurement of water-cooled condenser accessory machinery and auxiliary device in main
power house shall be in accordance with those specified in 5.4.4. The dimension deviation,
counting number of limits and the permissible deviation provisions shall comply with
following.
1) Coupling center of rotating machine:
The rotating machine includes every kind of pump and blower in main power house; the
coupling center must meet the requirements of DL 5011; four points shall be set on each pair
of couplings and two points on circle deviation and end face opening respectively; all the
pumps and blowers shall be counted together.
2) Installation position of equipment (device):
The equipment (device) shall include all accessory machines and auxiliary devices in main
building; the installation positions shall include center, elevation, levelness and verticality; the
permissible deviation shall be determined according to Construction Quality Acceptance
Standard; the measuring point number shall be taken as the counting point.
3) Flow passage part gap and external gland gap of feed pump driving steam turbine:
The count of actual measuring point number and permissible deviation shall comply with the
measuring position and state specified by manufacturer.
4) Sliding pin system of feed pump driving steam turbine:
It shall be counted according to measuring points established in Construction Quality
Acceptance Standard; the permissible deviation shall be in accordance with provisions of
manufacturer.
5) Bearing assembly gap:
The assembly clearance of sliding bearing shall include bushing clearance and bushing
tightening force; the assembly clearance of rolling bearing shall include bearing and enclosure
clearance as well as axial clearance of bearing capping and bearing; each data shall be taken
as one measuring point according to installation records.
6) Installation dimension of condenser:
359
The installation dimension of condenser specially refer to the verticality of pipe plate and
clapboard to base plate and the relative misalignment direction of conduit orifice center line;
the four measuring points for verticality on each pipe plate (clapboard) shall be four
measuring points for dimension and the relative misalignment values of four conduit orifice
measuring center line shall be taken from each pipe plate (clapboard) as four measuring
points for dimension.
7) Installation dimension of overhead traveling crane:
Each datum as rail dimension, main beam dimension, trolley span dimension and trundle span
shall be taken as one measuring point according to installation records.
3 The evaluation for the installation dimension deviation and actual limit measurement of
machinery and auxiliary device of air-cooling condenser accessory in main power house shall
be carried out according to those specified in Table 5.6.4-2 and comprehensive judgment shall
be carried out.
Table 5.6.4-2 Evaluation Table on Dimension Deviation and Actual Limit Measurement
Installation of accessory machinery
Construction
Project position (scope) and auxiliary device in main power Before 168h trial operation in full load
stage
house
Evaluation
Construction organization
organization
Weight value: 10
Total deserved score:
Evaluation Total obtained score:
result Score for the dimension deviation and actual limit measurement of installation engineering of accessory machinery
and auxiliary device in main power house=obtained score/deserved score*weight value=Evaluator (signature):
Date
4 The evaluation method for the installation dimension deviation and actual limit
measurement of accessory machinery and auxiliary device of air-cooling condenser in main
power house shall be in accordance with those specified in 5.4.4; refer to relevant contents in
Table 5.6.4-1 for the requirements for No. 1, 2, 3, 4, 5, 6 and 7 inspection items in Table
5.6.4-2. For the No. 6 inspection item, the evaluation method for the installation dimension
deviation and actual limit measurement of air-cooling condenser shall be in accordance with
those specified in 5.4.4. The counting of point number and permissible deviation provisions
360
shall comply with followings:
Each datum as pillar space of air-cooling condenser, center slanting stitch of pillar, height
error on one supporting area of steel platform, condensing tube bundle position, "A" shape
structure position, levelness of blower wheel hub, diameter of blower fan drum, installation
angle of fan blade, gap between fan blade and fan drum shall be a measuring point according
to installation records.
5.6.5 The evaluation method for the management and implementation performance of
compulsory provision for the installation of accessory machinery and auxiliary device in main
power house shall be in accordance with those specified in 5.4.5. The evaluation shall be
carried out according to Table 5.5.5 and comprehensive judgment shall be carried out.
5.6.6 Evaluation for the appearance quality of accessory machinery and auxiliary device in
main power house
1 The evaluation on appearance quality of accessory machines and auxiliary devices in
main power house shall be carried out according to the content specified in Table 5.6.6 and
comprehensive judgment shall be carried out.
Table 5.6.6 Evaluation Table on Appearance Quality
Installation of accessory machines and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary devices in main building stage
Evaluation
Construction organization
organization
1 Equipment appearance 20
8 Regional environment 10
Weight value: 15
Total deserved score:
Total obtained score:
Evaluation
Installation appearance quality score of accessory machines and auxiliary devices in main power house=obtained
result
score/deserved score weight value =
Evaluator (signature):
Date
361
the following methods.
1) Equipment appearance: Each independent equipment and its structure support
shall be taken as an evaluation point, and the point which is firmly installed,
regular, reasonable and clean without damage and remains shall be evaluated as
"good".
2) Installation technology of oil system pipes: each independent system shall be
taken as one evaluation point, and the point featured of reasonable pipe
arrangement, esthetic appearance, normative and firm installation of gradient
and supporter and hangers, well installed valves that are convenient for
operation, concentrated and regular arrangement of small diameter pipes with
uniform spacing and the same turn radius shall be evaluated to be "good".
3) Tightness of equipments and systems: the equipments and systems without
leakage points and the seepage points less than 3 are Class I; the ones without
leakage points and seepage points less than 8 are Class II; the ones without
severe leakage points are Class III.
4) Equipment and system: the equipment and system with correct, complete,
striking, unified and normative as well as legibility and firm hanging mark
without pollution are Class I; the equipment and system with correct, basically
complete, normative as well as legibility and firm hanging mark without
pollution are Class II; the equipment and system with correct, basically
complete and firm hanging mark are Class III.
5) Installation technology of platform, handrail and staircase: platform, handrail
and staircase with firm installation, smooth surface, intact coating, straight and
even horizontal pole, vertical pole, uniform spacing and height meeting the
requirements, firm welding, qualified weld appearance quality, skirting board,
access ladder and safety cage meeting the requirements are Class I; the ones
with firm installation, basically reaching smooth surface, intact coating and
height meeting the requirements, firm welding, qualified weld appearance
quality, skirting board, access ladder and safety cage meeting the requirements
are Class II; the ones with firm installation and height meeting the requirements,
firm welding, skirting board, access ladder and safety cage meeting the
requirements are Class III.
6) Installation technology of enclosures and shields: the closure and shield with
correct installation position and free from knocking with rotary position, not
influencing expansion, with complete bolts, straight and even framework and
panel, firm without deformation, tight joint, regular installation, esthetic
appearance, rustless and without scar are Class I; the ones with correct
installation position and free from knocking with rotary position, not
influencing expansion, with complete bolts, basically straight and even
framework and panel, firm without deformation and with regular installation
are Class II; the ones with correct installation position and free from knocking
with rotary position, not influencing expansion, with complete bolts and firmly
installed framework and panel are Class III.
7) Painting and thermal insulation: the painting with thickness and color meeting
362
design, color matching coordination, consistent and uniform tincture without
flow mark, wrinkle, bubble, shedding, return rust and pollution; the thermal
insulation with smooth surface without damage or shedding and the seaming of
metal enclosure meeting the requirements as well as esthetic technology are
Class I; the painting with thickness and color meeting design, basically
consistent tincture, uniform, basically without flow mark, wrinkle, bubble,
shedding or return rust; the thermal insulation with smooth surface without
damage or shedding and the seaming of metal enclosure meeting the
requirements are Class II; the painting with thickness and color meeting design,
basically consistent tincture; the thermal insulation with basically smooth
surface and the seaming of metal enclosure meeting the requirements are Class
III.
8) Regional environment: the trial operation area without oil and water as well as
ash accumulation and sanitation dead angles, articles are stacked regularly with
fixed management is Class I; the trial operation area without oil and water as
well as ash accumulation, articles are stacked regularly without sanitary fill is
Class II; the trial operation area without oil and water as well as ash
accumulation and sanitation dead angles, articles are stacked basically regularly
is Class III.
5.7.1 The evaluation methods on construction site quality guarantee condition for
installation of the accessory machines and auxiliary devices outside main building shall meet
the provisions specified in 5.4.1. The evaluation contents shall be inspected referring to those
specified in Table 5.5.1 and shall be comprehensively judged.
5.7.2 Evaluation on the performance inspection for installation of the accessory machines
and auxiliary devices outside the main building.
1 The evaluation on performance inspection for installation of the accessory machines
and auxiliary devices outside the main building shall be inspected, evaluated and judged
comprehensively according to the provisions specified in Table 5.7.2
Table 5.7.2 Evaluation Table of Performance Inspection
Accessory machine and auxiliary
Construction
Project position (scope) device installation outside the main Before 168h trial operation in full load
stage
building
Evaluation
Construction organization
organization
363
3 Outlet butterfly valve and control device 10
4 Crane performance 10
6 Noise 5
Weight value: 25
Total deserved score:
Total obtained score:
Evaluation
Score of performance inspection for installation of accessory machines and auxiliary device outside the main
result
building =obtained score/deserved score* weight value=
Evaluator (signature):
Date
364
5)
Steel gate
The steel gate with service performance meeting the requirements of
manufacturer, normal and flexible actions as well as tight waterstop is Class I.
6) Noise
Noise meeting the design value is Class I; the one without exceeding 10% of
the design value is Class II; one beyond the design value by 10% is Class III.
5.7.3 The evaluation method for quality record of installation of accessory machines and
auxiliary devices outside main building shall be in accordance with those specified in 5.4.3;
the evaluation contents shall be inspected according to those specified in Table 5.7.3 and shall
be comprehensively judged.
Table 5.7.3 Evaluation Table of Quality Record
Installation of accessory machine and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device outside main building stage
Evaluation
Construction organization
organization
3 Installation record 15
Weight value: 15
Total deserved score:
Total obtained score:
Evaluation
Quality record score for installation of accessory machines and auxiliary devices outside main building=obtained
result
score/deserved scoreweight value =
Evaluator (signature):
Date
5.7.4 Evaluation on size deviation and actual limit measurement for installation of accessory
machines and auxiliary devices outside main building.
1 The evaluation for the size deviation and actual limit measurement of installation of
accessory machines and auxiliary devices outside main building shall be inspected according
to those specified in Table 5.7.4 and shall be comprehensively judged.
Table 5.7.4 Evaluation Table of Size Deviation and Actual Limit Measurement
Project position (scope) Installation of accessory machine and Construction Before 168h trial operation in full load
365
auxiliary device outside main building stage
Evaluation
Construction organization
organization
Weight value: 15
Total obtained score:
Total obtained score:
Evaluation
score of size deviation and actual limit measurement for installation project of accessory machines and auxiliary
result
devices outside main building=obtained score /deserved scoreweight value=
Date
2 The evaluation methods for size deviation and actual limit measurement of
installation of accessory machines and auxiliary devices outside main building shall meet
those specified in 5.4.4; the point statistics and permissible deviation of size deviation and
limit shall be implemented according to the following.
1) Coupling center of rotating machine:
The rotating machine shall include every kind of pump outside main building;
the coupling center must meet the requirements of "permissible deviation value
of accessory machine centering" as detailed in Annex D; each pair of couplings
shall be installed with four points, and the surrounding deviation and end
surface opening shall be two points respectively; all pumps shall be
summarized with statistics.
2) Installation position of equipment (device):
The equipment (device) shall include all accessory machines and auxiliary
devices outside main building; the installation positions shall include center,
elevation, levelness and verticality; the permissible deviation shall be
determined according to acceptance standard of construction quality; the
measuring point number shall be taken as the statistics point.
3) Assembly clearance of pump bearing:
The assembly clearance of sliding bearing shall include bushing clearance and
bushing tightening force; the assembly clearance of rolling bearing shall
include bearing and enclosure clearance as well as axial clearance of bearing
capping and bearing; each data shall be taken as one measuring point according
to installation records.
4) Waggling of long-axis vertical pump shaft:
366
The waggling measurement of long-axis vertical pump shaft shall be carried out
according to the requirements of manufacturer and DL 5011, and each data
shall be taken as one measuring point according to installation records.
5) Installation dimension of overhead traveling crane
Each data as rail dimension, main beam dimension, trolley span dimension and
trundle span shall be taken as one measuring point according to installation
records.
6) Installation dimension of steel gate and guide rail of rotary filter screen:
Each data as installation dimension of steel gate and guide rail of rotary filter
screen shall be taken as one measuring point according to installation records.
5.7.5 The evaluation method for the management and implementation performance of
compulsory provisions for installation of accessory machines and auxiliary devices outside
main building shall be in accordance with those specified in 5.4.5; the evaluation contents
shall be inspected and evaluated according to those specified in Table 5.5.5 and shall be
comprehensively judged.
5.7.6 Evaluation on appearance quality of accessory machines and auxiliary devices outside
main building
1 The evaluation on appearance quality of accessory machines and auxiliary devices
outside main building shall be inspected and evaluated according to the content specified in
Table 5.7.6 and shall be comprehensively judged.
Table 5.7.6 Evaluation Table of Appearance Quality
Installation of accessory machine and Construction
Project position (scope) Before 168h trial operation in full load
auxiliary device outside main building stage
Evaluation
Construction organization
organization
1 Equipment appearance 20
8 Regional environment 10
Weight value: 15
Total deserved score:
Evaluation Total obtained score:
result Score of appearance quality for installation of accessory machines and auxiliary devices outside main
building=obtained score /deserved scoreweight value=
Evaluator (signature):
367
Date
368
and free from knocking with rotary position, not influencing expansion, with
complete bolts, straight and even as framework and panel, firm without
deformation, tight joint, regular installation, esthetic appearance, rustless and
without scar is Class I; the one with correct installation position and free from
knocking with rotary position, not influencing expansion, with complete bolts,
basically straight and even framework and panel, firm without deformation and
with regular installation is Class II; the one with correct installation position
and free from knocking with rotary position, not influencing expansion, with
complete bolts and firmly installed framework and panel is Class III.
7) Painting and thermal insulation: the painting with thickness and color meeting
design, color matching coordination, consistent and uniform tincture without
flow mark, wrinkle, bubble, shedding, return rust and pollution; the thermal
insulation with smooth surface without damage or shedding and the seaming of
metal enclosure meeting the requirements as well as esthetic technology are
Class I; the painting with thickness and color meeting design, basically
consistent tincture, uniform, basically without flow mark, wrinkle, bubble,
shedding or return rust; the thermal insulation with smooth surface without
damage or shedding and the seaming of metal enclosure meeting the
requirements are Class II; the painting with thickness and color meeting design,
basically consistent tincture; the thermal insulation with basically smooth
surface and the seaming of metal enclosure meeting the requirements are Class
III.
8) Regional environment: the trial operation area without oil and water as well as
ash accumulation and the articles with regular stacking and fixed management
without sanitation dead angle is Class I; the trial operation area without oil and
water as well as ash accumulation and the articles with regular stacking without
waste stacking is Class II; the trial operation area basically without oil and
water as well as ash accumulation and the articles with basically regular
stacking is Class III.
5.8.1 The evaluation method of quality assurance condition of construction site of steam
turbine pipe shall meet those specified in 5.4.1; the evaluation content shall be inspected
referring to those specified in Table 5.5.1 and shall be comprehensively judged.
5.8.2 Evaluation on performance inspection for installation of steam turbine pipe.
1 The evaluation content of performance inspection for installation of steam turbine
pipe shall be inspected according to those specified in Table 5.8.2 and shall be
comprehensively judged.
Table 5.8.2 Scoring Table of Performance Inspection
Project position (scope) Installation of steam turbine pipe Construction stage Before 168h trial operation in full load
Construction Evaluation
organization organization
369
score 100% 85% 70% score
2 Valve inspection 10
Weight value: 30
Total deserved score:
Evaluation Total obtained score:
result Score of performance inspection for installation of steam turbine pipe=obtained score/deserved score weight value=
Evaluator (signature):
Date
370
system and the service performance meeting the operating requirement after
processing are Class II and gain 85% standard score; the ones with internal
(external) leakage phenomenon (only limited to drainage system valve for main
pipe) for a small amount of valves in system and the service performance
basically meeting the operating requirement after processing are Class III and
gain 70% standard score.
3) Inspection of creep expansion supervising section and creep monitoring point:
Installation of creep supervising section and creep measurement points meeting
design and compulsory provision requirements and with intact, actual and
complete record is Class I and gains 100% standard score, the one meeting
design and compulsory provision requirements and with basically intact, actual
and complete record is Class II and gains 85% standard score; the one basically
meeting design and compulsory provision requirements and with basically
intact, actual and complete record is Class III and gains 70% standard score.
4) Adjustment and inspection of supporter and hanger:
Installation of supporter and hanger meeting design and specification
requirements with actual and complete record and the thermal running state
meeting design and specification requirements is Class I and gains 100%
standard score; the one meeting design and specification requirements with
actual and complete record and may meet design and specification
requirements after adjustment or processing under thermal state is Class II and
gains 85% standard score; the one basically meeting design and specification
requirements with basically actual and complete record and basically meeting
design and specification requirements after adjustment or processing under
running state is Class III and gains 70% standard score.
5) Welded junction inspection under supervision:
The welded junction under supervision with qualified 100% non-destructive
inspection according to specification and the first qualification rate reaching
98% and above is Class I and gains 100% standard score; the one with the first
qualification rate reaching 96% and above is Class II and gains 85% standard
score; the one with the first qualification rate reaching 95% and above is Class
III and gains 70% standard score.
6) Expansion inspection of pipe system:
Pipe system expansion meeting the design requirements with correct expansion
indication and without expansion obstructing phenomenon on site and with
complete record is Class I and gains 100% standard score; the one basically
meeting the design requirements and with complete record is Class II and gains
85% standard score; the one with deviation for individual position expansion
but basically not influencing the normal operation of system and with basically
complete record is Class III and gains 70% standard score.
7) System tightness test:
The system tightness test shall be qualified with complete confirmation and
signature, and the main pipe of system during operational process shall be free
from leakage phenomenon. If the system tightness is good without any leakage
371
point, it is Class I and gains 100% standard score; the slight leakage points
(limited to drain and blowdown system of main pipe system less than 2 and
leakage points of medium and low-pressure pipe system less than 5) and not
influencing the normal operation of unit is Class II and gains 85% standard
score; the slight leakage point (limited to drain and blowdown system of main
pipe system less than 4 and leakage points of medium and low-pressure pipe
system less than 8) and not influencing the normal operation of unit is Class III
and gains 70% standard score.
8) Blowing inspection of main steam and reheating system:
The system flushing with scientific and reasonable scheme, less flushing times
and effect reaching code and standard requirements [impact spot on last target
card 0.8mm, 0.5mm~0.8mm (including 0.8mm) spot no larger than 8 points
and 0.2mm~0.5mm spot with even distribution], complete record and
confirmation and signature and intact target card preservation is Class I and
gains 100% standard score; the system flushing with scientific and reasonable
scheme, and flushing effect reaching code and standard requirements, basically
complete record and confirmation and signature and intact target card
preservation is Class II and gains 85% standard score; the system flushing with
scientific and reasonable scheme, and flushing effect basically reaching code
and standard requirements, basically complete record and confirmation and
signature and intact target card preservation is Class III and gains 70% standard
score.
9) Internal cleaning degree of system:
The pipe system with clean internal cleaning (flushing) and complete record
and confirmation and signature as well as good systems operation is Class I and
gains 100% standard score; the pipe system with comparatively clean internal
cleaning (flushing) and complete record and confirmation and signature as well
as the slight jam or other poor phenomena existing for equipment and valves
caused by unclean system during operation, but not influencing the normal
operation of system is Class II and gains 85% standard score; the one with
basically complete record and confirmation and signature the slight jam or
other poor phenomena existing for equipment and valves caused by unclean
system during operation, but basically not influencing the normal operation of
system is Class III and gains 70% standard score.
10) Earthing inspection of fuel gas and fuel oil pipes:
The system with earthing construction meeting design and specification
requirements and qualified ground resistance test as well as complete and
standard test record and report is Class I and gains 100% standard score; the
one with system earthing construction meeting design and specification
requirements and with qualified ground resistance test as well as basically
complete and standard test record and report is Class II and gains 85% standard
score; the one with system earthing construction basically meeting design and
specification requirements and with qualified ground resistance test as well as
basically complete and standard test record and report is Class III and gains
372
70% standard score.
5.8.3 The evaluation method of quality record for installation of steam turbine pipe shall be
in accordance with those specified in 5.4.3; the evaluation contents shall be inspected
according to those specified in Table 5.8.3 and shall be comprehensively judged.
Table 5.8.3 Scoring Table of Quality Record
Construction
Project position (scope) Installation of steam turbine pipe Before 168h full load trial operation
stage
Evaluation
Construction organization
organization
5.8.4 Evaluation on size deviation and actual limit measurement for installation of steam
turbine pipe.
1 The evaluation on size deviation and actual limit measurement for installation of
steam turbine pipe shall be inspected according to those specified in Table 5.8.4-1 and shall
373
be comprehensively judged.
2 The evaluation method of size deviation and actual limit measurement for installation
of steam turbine pipe shall meet those specified in 5.4.4; the specific inspection item of size
deviation and limit evaluation content shall be carried out according to those specified in
Table 5.8.4-2.
Table 5.8.4-1 Evaluation Table of Size Deviation and Actual Limit Measurement for Installation of Steam
Turbine Pipe
Before 168h full load trial
Project position (scope) Installation of steam turbine pipe Construction stage
operation
Construction Evaluation
organization organization
Table 5.8.4-2 Items to Be Inspected of Size Deviation and Actual Limit Measurement for Installation of
Steam Turbine Pipe
SN Inspection item Unit Permissible variation value
2 Installation deviation value of supporter and hanger Meeting the requirements of the design drawing
3 Adjustment of original position of spring Meeting the requirements of the design drawing
374
Spacing of two DN500 mm >external diameter of pipe, and>150
5
welds DN>500 mm >external diameter of pipe, and>500
7 Length of connecting bolt exposed from screw thread Exposing 2~3 threads
2 System tightness 10
3 Painting construction 10
4 Welding construction 5
6 Bolted connection 5
7 System mark 5
9 Valve installation 10
5.9 Evaluation on Construction Quality of Steam Turbine Main Body (Including Steam
375
Feed Pump), Equipment, Pipe Insulation and Paint
Construction Evaluation
organization organization
2 Inspection criteria
376
1) Steam turbine main body:
Spectrum re-inspection of insulation-member alloy steel: spectral analysis shall
be carried out for the alloy steel piece by piece; materials shall not be misused.
Materials of the alloy steel parts shall meet the requirements specified in
equipment technical documents.
Expansion joint and expansion clearance in main parts: they shall meet the
requirements specified in equipment technical documents. Expansion joints
shall be arranged to be criss-cross; through-expansion joints shall not be
available and the expansion joints directions shall be consistent with designed
ones. For the quality and clearance of expansion joints: the expansion joints
shall meet the design requirements; the size deviation of expansion clearance
meet design requirements and insulation materials are filled in compaction; it
shall be free from any lumpy shedding and large-area cracking. Inspection on
insulation layer surface temperatures: during the full load trial operation of
steam turbine generator units, the insulation layer surface of the steam turbine
main body (including steam feed pump) are inspected in thermal state; where
the environment temperature is not greater than 25, the insulation-layer
surface temperature shall not be greater than 50; where the environment
temperature is greater than 25, the insulation-layer surface temperature is not
greater than 25plus the environmental temperature.
2) Equipment and pipe insulation:
Material qualification on-site inspection: technical performance of insulation
materials meets the design criteria. There are complete quality certificates,
delivery reports and random inspection reports.
The binding and laying of insulating layer shall meet the design If the same
kind of thermal insulation product is adopted during the laying of insulating
layer, in the following conditions, the layer must be divided into sub-layer:
thickness of hard material is greater than 80mm; or the thickness of semi-hard
material or soft material is greater than 100mm. Gap joint shall not be larger
than 5mm. Joints in the same layer shall be staggered and in the adjacent
vertical layers shall be pressed; angle joint is close-over overlay one. The edge
joints shall be regular, the staggered joints shall be in good order, and the layer
surfaces shall be even. Binding of hard or semi-hard insulating layer shall be
firm and the binding spacing of hard insulating layer shall not be larger than
400 mm. Where the nominal diameter is equal to or greater than 600mm, the
pipe or equipment shall be reinforced with additional iron wire or steel strip and
the binding spacing shall not be greater than 500mm. The binding spacing of
the semi hard heat insulating layers shall not be larger than 300 mm; at least
two galvanized iron wires shall be bound on each thermal insulation product
and the spacing shall be uniform; the appearance shall be flat.
Quality of support member installation: support member is firmly installed in
the right position without looseness.
Support member spacing: for vertical pipes with nominal diameter greater than
100mm and vertical equipments, the spacing of plane-wall support members is
377
1.5~2m. Round tank and pipe: the spacing of high-temperature pipe support
members is 2m~3m; the spacing of moderate temperature pipe support member
is 3m~5 m and the spacing of low temperature pipe support members is 5
m~7m. The width of the support member shall be less than the insulation
thickness by 10mm but shall not be less than 20mm.
Installation quality of protective layer: the upper circumferential joints and
longitudinal joints of the metallic protective layer for equipment and pipe shall
overlap the lower ones in downstream direction; the overlapping shall be firm,
without looseness or falling off; the joints shall be regular; the layout of self
plugging rivet or tapping screw shall be uniform. Appearance of protective
layer is tidy and esthetic. Overlapping spacing of metallic protective layer: for
indoor equipment and pipe, it is not less than 20mm at general positions and not
less than 50mm at expansion joint positions. For outdoor equipment and pipe: it
is not less than 50mm in general position and not less than 75mm in expansion
joint position. Overlapping of metallic protective layer for upright high
temperature pipe shall be not less than 80mm. Where the rendering coat is
taken as the protective layer, the broken joint of the rendering coat for high
temperature pipe shall be kept at the same position of the expansion joint of
insulating layer. The expansion joint surface of outdoor rendering coat shall be
added with metal protective shell or provided with other waterproof measures.
The width and depth of quadrilled or annular flute expansion joints reserved by
the rendering coat of large equipment shall meet design requirements.
3) Equipment and pipe paint:
The paint color shall meet design requirements; the post-painted surface color
is uniform and consistent; there shall be no spot, falling off, flow mark or
obvious brush mark etc.
3 Inspection method: site inspection; if necessary, inspecting the construction records
to judge it comprehensively.
1) Steam turbine main body thermal insulation
Spectrum re-inspection of alloy steel: checking spectral analysis report.
Expansion joints and expansion clearances of main parts: inspecting the
construction acceptance records.
Without shedding or cracking: inspecting the acceptance license.
Insulating-layer surface temperature inspection: measuring with thermoscope
for the surface temperatures of metals or outer guard boards.
2) Equipment and pipe insulation:
Qualification of materials for on-site inspection: inspecting whether the
delivery report, quality certificate and material random inspection report of
each batch of materials are complete or not.
Binding and laying of heat insulating layer: observation and ruler-based
inspection
Installation quality of support member: observation and ruler-based inspection.
Installation quality of protective layer: observation and ruler-based inspection.
3) Equipment and pipe paint: observation
378
5.9.3 Quality record evaluation.
1 The quality record evaluation items of steam turbine main body (including steam
feed pump), equipment, pipe insulation and paint are detailed in Table 5.9.3 and shall be
comprehensively evaluated according to those specified in the table.
2 Evaluation criteria: Those quality records with material & equipment quality
certificates (outgoing quality certificates), complete site acceptance record, construction
record, construction test record, data; actual and effective content, standard classification &
rearrangement, perfect reviewing and signing procedures and meeting the requirements
specified in design and standards are Class I and gain 100% standard score. Those quality
records with complete information, relatively complete data, actual and effective content,
relatively standard rearrangement, relatively complete reviewing and signing procedures and
meeting the requirements specified in design and standards are Class II and gain 85%
standard score. Those quality records with basically complete information, date; actual and
effective content; basically standard rearrangement, basically complete reviewing and signing
procedures and basically meeting the requirements specified in design and standards are Class
III and gain 70% standard score.
3 Evaluation methods: to inspect the quantity and content of information
Table 5.9.3 Evaluation Table of Quality Records
Steam turbine main body (including
Construction
Project position (scope) steam feed pump), equipment, pipe Before 168h full load trial operation
stage
insulation and paint
Construction Evaluation
organization organization
379
insulation On-site inspection report of material 4
380
Thermal inspection on insulation layer surface of the heating power pipes, such
as equipment main steam and reheated steam, the valve and the pipe fittings:
where the environment temperature is not greater than 25 , the
insulation-layer surface temperature shall be not greater than 50; where the
environment temperature is greater than 25, the insulation-layer surface
temperature is not greater than 25 plus environmental temperature. Surface
temperature inspection of cylinder: the temperature difference between the
upper and lower cylinder shall not be higher than 50.
3) Equipment and pipe paint:
Film thickness shall meet the design requirements.
3 Inspection method: it shall be site inspection assisted by inspecting construction
records and comprehensive judgment on the size deviation and limit.
1) Steam turbine main body:
Insulating layer thickness: inspecting the confirmation and signature records.
Expansion joint and expansion clearance sizes in main parts: inspecting the
confirmation and signature records and they shall meet the requirements
specified in equipment technical documents.
Record, confirmation and signature inspection of insulating layer surface
temperature: thermal inspection on the main body surface with thermoscope.
2) Equipment and pipe insulation:
Insulating layer thickness: inspection on heat insulating layer for its thickness
by vertically inserting one straight pin with a length above that thickness into
this heat insulating layer
Inspection on insulating layer surface temperature of equipment: to inspect with
infrared thermometer and spot inspect three points every 50m2.
Inspection on surface temperatures of the heating power pipes, such as
equipment, main steam and reheated steam, the valve and the pipe fittings: to
inspect on the main steam pipe with infrared thermometer and spot inspect
three points every 50m.
The thermal insulations for the creep measurement points and the parts with
special purposes by the design and criteria shall meet the relevant requirements.
3) Equipment and pipe paint: paint thickness tester shall be applied to measure.
Table 5.9.4 Evaluation Table of Size Deviations and Limits
Steam turbine main body (including
Construction
Project position (scope) steam feed pump), equipment, pipe Before 168h full load trial operation
stage
insulation and painting
Evaluation
Construction organization
organization
381
Spot inspection on insulating layer
6
surface temperatures
Equipment and
3 Film thickness 10
pipe paint
Construction Evaluation
organization organization
382
Strictness degree of implementing compulsory
4 25
provisions of this position (system)
383
consistent in thickness. Appearance shall be flat, smooth and beautiful.
3) Equipment and pipe paint:
It shall be uniform and consistent in tone; without spot, falling off, wrinkle,
flow mark, floating film, paint particle or obvious brush mark after painting.
4) Equipment and system mark shall meet the design; be complete, standard,
uniform and striking.
3 Inspection method: it shall be observed and inspected on the site, accompanied by
actual measuring and checking the inspection acceptance records, confirmation and signature
and shall be carried out with qualitative or quantitative conclusions.
Table 5.9.6 Evaluation Table on Appearance Quality
Steam turbine main body
(including steam feed pump), Construction
Project position (scope) Before 168h full load trial operation
equipment, pipe insulation and stage
paint
Evaluation
Construction organization
organization
Evaluation
SN Deserved Obtained
Evaluation content results Remarks
Deserved score score
100% 85% 70%
Construction process of
5
plastering layer
Uniform in color 5
3 Equipment pipe paint
Without pervious spots, wrinkle,
5
shedding or flow mark
384
results Total deserved score:
Total obtained score:
The quality inspection score for steam turbine main body (including steam feed pump), equipment, pipe insulation
and paint projects= obtained score/deserved scoreweight value =
Evaluator (signature) :
Date
Construction Evaluation
organization organization
385
Weight value: 30
Total deserved score:
Total obtained score:
Evaluation results Installation performance inspection score of the combustion engine and its auxiliary equipments and
accessory machines=Obtained score/Deserved scoreWeight value=
Evaluator (signature):
Date
386
the amplitude reaches the good-class criterion, the vibration shall be evaluated
as Class II; if the amplitude reaches the qualified criterion, the vibration shall
be evaluated as Class III.
6) Enclosure tightness of the combustion engine main body:
If the enclosure is tight without light-leak and the spray tests of the fire
extinguishing protection system are without leakage points, the enclosure
tightness shall be evaluated as Class I; if the enclosure is tight without
light-leak and the spray tests of the fire extinguishing protection system are
without obvious leakage points, the enclosure tightness shall be evaluated as
Class II; if the enclosure is tight without obvious light-leak and spray tests of
the fire extinguishing protection system are without obvious leakage points, the
enclosure tightness shall be evaluated as Class III.
7) Tightness of the combustion gas system:
If the combustion gas system equipments and pipes are tight without leakage,
the tightness shall be evaluated as Class I.
8) Exhaust temperature of the combustion engine:
If the exhaust temperature average values of the combustion engine are not
greater than assurance values given in the contract, it shall be evaluated as
Class I.
5.10.3 Methods of evaluation on installation quality records of the combustion engine and
its auxiliary equipments and accessory machines shall meet the requirements specified in
Article 5.4.3, The evaluation contents shall be inspected and comprehensively evaluated
according to those specified in Table 5.10.3.
Table 5.10.3 Evaluation Table of Installation Quality Records
Project position Installation of the combustion engine and its Construction
Before 168h full load trial operation
(scope) auxiliary equipments and accessory machines stage
Construction Evaluation
organization organization
4 Installation records 20
5 Various certificates 15
387
design alterations and materials substitutes
Weight value: 20
Total deserved score:
Total obtained score:
Installation construction quality records score of the combustion engine and its auxiliary equipments and
Evaluation results
accessory machines=Obtained score/Deserved scoreWeight value=
Evaluator (signature):
Date
5.10.4 Evaluation on actual measurement of installation size deviation and limit of the
combustion engine and its auxiliary equipments and accessory machines
1 Evaluation on actual measurement of installation size deviation and limit of the
combustion engine and its auxiliary equipments and accessory machines shall be inspected
and comprehensively evaluated according to those specified in Table 5.10.4.
Table 5.10.4 Evaluation Table of Actual Measurement of Installation Size Deviation and Limit
Project position Installation of the combustion engine and its Construction
Before 168h full load trial operation
(scope) auxiliary equipments and accessory machines stage
Construction Evaluation
organization organization
Weight value: 10
Total deserved score:
Evaluation Total obtained score:
results Actual measurement of installation project size deviation and limit score of the combustion engine and its
auxiliary equipments and accessory machines=Obtained score/Deserved scoreWeight value=
Evaluator (signature):
388
Date
389
the installation records.
5.10.5 The evaluation methods for the management and implementation performance of the
compulsory provisions on the installation of combustion engine and its auxiliary equipments
and accessory machines shall meet the requirements of 5.4.5, the evaluation shall include the
inspection and evaluation according to the contents specified in Table 5.5.5 and the
comprehensive judgement shall be carried out finally.
5.10.6 Evaluation on installation appearance quality of the combustion engine and its
auxiliary equipments and accessory machines.
1 For the evaluation on the installation appearance quality of combustion engine and
its auxiliary equipments and accessory machines, the inspection shall be carried out according
to the requirements of Table 5.10.6 and the comprehensive judgement shall be carried out
finally.
Table 5.10.6 Evaluation Table on Appearance Quality
Installation of combustion
engine and its auxiliary Construction
Project position (scope) Before carrying out trial operation with 168h full load
equipments and accessory stage
machines
Evaluation
Construction organization
organization
1 Equipment appearance 20
8 Regional environment 10
Weight value: 1 0
Total deserved score:
Total obtained score:
Evaluation
Appearance quality score of the installation works of combustion engine and its auxiliary equipments and accessory
result
machines=obtained score/deserved score weight value =
Evaluator (signature):
Date
390
inspection points of evaluation shall be implemented according to the following requirements:
1) Equipment appearance: Each independent equipment and its framework and
bracket shall be taken as one evaluation point, and the regular, reasonable and
clean point that is firmly installed without damage or remnant shall be
evaluated to be "good".
2) Pipe installation technology of gas, oil and water systems: Each independent
system shall be taken as one evaluate point, and the point featured of
reasonable pipe arrangement, esthetic appearance, correct gradient, good and
firm installation of supporters and hangers, well installed valves that are
convenient for operation, concentrated and regular arrangement of small
diameter pipes with uniform interval and same turn radius shall be evaluated to
be "good".
3) Tightness of equipments and systems: In this item, the equipment and systems
do not include the fuel gas system. The equipments and systems with no leak
sources and the systems with no more than 3 leak sources shall be classified
into Class I; the equipments and systems without leak sources and those with
no more than 8 leak sources shall be classified into Class II; the equipments
and systems without severe leak sources shall be classified into Class III.
4) Equipment and system mark: The equipments and systems with correct,
complete, striking, uniform, standard, legible, firmly-hung and pollution-free
marks shall be classified into Class I; the equipments and systems with correct,
basically complete, standard, legible, firmly-hung and pollution-free marks
shall be classified into Class II; and those with correct, basically complete and
firmly-hung marks shall be classified into Class III.
5) Installation technology of platform, handrail and staircase: The platform,
handrail and staircase that are firmly installed, with smooth surface, good
coating, straight and even horizontal pole, vertical pole, uniform space, height
meeting the relevant requirements, firm welding, qualified weld appearance
quality, and skirting board, access ladder and safety cage meeting the
specifications shall be classified into Class I; the platform, handrail and
staircase that are firmly installed, reach smooth surface basically and are with
good coating, height meeting the relevant requirements, firm welding, qualified
weld appearance quality, and skirting board, access ladder and safety cage
meets the specifications shall be classified into Class II; and those firmly
installed platform, handrail and staircase with height meeting the relevant
requirements, firm welding, and skirting board, access ladder and safety cage
meeting the specification shall be classified into Class III.
6) Installation technology of enclosure and shield: The enclosure and shield that
are installed at right positions, have no rubbing with rotating positions and no
influence on expansion, and are with complete bolts, straight, even,
deformation-free and tightly-welded framework and panel, regular, beautiful,
rustless and scar-free installation shall be classified into Class I; the enclosure
and shield that are installed at right positions, have no rubbing with rotating
positions and no influence on expansion, and are with complete bolts, basically
391
straight, even and tightly-welded framework and panel free from obvious
deformation as well as are with regular installation shall be classified into Class
II; and those that are installed at right positions, have no rubbing with rotating
positions and no influence on expansion, and are with complete bolts and
firmly installed framework and panel shall be classified into Class III.
7) Painting and insulation: provided that the thickness and color of paint meet the
design and the paint color is matched harmoniously, the color and lustre are
uniform without flow mark, wrinkle, gas bubble, shedding, rust and
contamination; the insulation does not affect the expansion, the surface is
smooth without damage and shedding, the rendering coat is round and smooth
without cracks, the seaming of and metal enclosure meets the requirements and
the technique is of esthetic appearance, the point shall be classified into Class I;
provided that the paint thickness and color meet the design, the color and lustre
are basically uniform without flow mark, wrinkle, gas bubble, shedding and
rust; and the insulation does not affect the expansion, the surface is smooth
with damage and shedding, the rendering coat is basically round and smooth
without crack, and the seaming of metal shell meets the requirements, the point
shall be classified into Class II; provided that the paint thickness and color
meet the design, the color and lustre are uniform basically; and the insulation
does not affect the expansion, the surface is basically flat and smooth, the
rendering coat is basically round and smooth and the seaming of metal shell
meets the requirements, the point shall be classified into Class III.
8) Regional environment: The trial operation area without oil and water as well as
ash accumulation and the articles with regular stacking and fixed management
without sanitation dead angle is Class I; the trial operation area without oil and
water as well as ash accumulation and the articles with regular stacking without
waste stacking is Class II; the trial operation area basically without oil and
water as well as ash accumulation and the articles with basically regular
stacking is Class III.
5.11 Summarizing of Evaluation Score of Project Position (Scope) of Single Project
5.11.1 The actual quality evaluation score of single project shall be summarized and
evaluated corresponding to each project position (scope) and evaluation item.
5.11.2 Quality evaluation score and evaluation rating of single project shall be implemented
in accordance with requirements specified in Table 5.11.2.
Table 5.11.2 Quality Evaluation Score Summary Table of Single Project
Name of project position (scope)
392
and painting
On-site quality
1 assurance
condition
2 Performance test
3 Quality record
Actual
measurement of
4 dimensional
deviation and
limit
Implementation
performance of
5
compulsion
provisions
Appearance
6
quality
Subtotal
Subtotal weight
value listed in Table
5.2.3
Evaluator (signature):
Evaluation organization (official seal)
Date
393
single project.
6.0.1 The quality evaluation for single unit shall be conducted after the construction quality
acceptance for all single projects and the 168-h trial operation of the unit with full load are
completed and the environmental protection projects supported are normally put into
operation. The public system shall be bought into the evaluation for the first unit.
6.0.2 More units of the same stage shall be evaluated according to single unit respectively,
and the support public system for units put into production subsequently shall be evaluated
synchronously with the unit.
6.0.3 168h full-load trial operation quality evaluation of the unit shall be in accordance with
those specified in Table 6.0.3.
Table 6.0.3 Quality Evaluation Table on 168h Full-load Trial Operation of the Unit
Project name Unit number
Examining Examination
SN Evaluation content Property Remarks
standard/examining value result/measured value
394
Number of days from the first pipe
blowing and lighting to the
14 90d
completion of trial operation with
168h full load
Evaluation score:
Evaluator (signature):
Date
Note 1: Class I: evaluation score 92 (including 92)~100; each index reaching the examination value and relevant requirements;
test conditions meeting the requirements; test report, confirmation and signature complete and normative.
Note 2: Class II: evaluation score 85 (including 85)~92; dominant indexes reaching examination value and relevant
requirements; test conditions meeting the requirements; test report, confirmation and signature being complete and normative;
85% and above general indexes reaching examination value and relevant requirements; test report, confirmation and signature
complete and normative fundamentally.
Note 3: Class III: evaluation score 70 (including 70)~85; dominant indexes reaching examination value and relevant
requirements; test conditions meeting the requirements; test report, confirmation and signature complete and normative; 70% and
above general indexes reaching assessment value and relevant requirements; test report, confirmation and signature complete and
normative fundamentally.
6.0.4 Single unit evaluation score is the sum of obtained score of all weighted single project
quality evaluation and unit 168-h full load trial operation technical index evaluation, and the
evaluation score statistics shall be in accordance with those specified in Table 6.0.4.
Table 6.0.4 Statistic Table of Single Unit Evaluation Score
Project name Unit number
1 Civil work 15
2 Boiler unit 16
7 Welding work 6
8 Processing preparation 3
395
9 Installation of electrical devices 10
Evaluation score:
Evaluator (signature):
Evaluation organization (official seal)
Date
Note 1: Evaluation of civil works shall be carried out by making reference to the requirements of GB/T 50375.
Note 2: Electrical device installation shall be evaluated according to the unit project fine rate in DL/T 5161.1~5161.17; thereinto,
Class I: fine rate is 100%; Class II: fine rate is 95%~99%; Class III: fine rate is 90%~94%.
7.0.1 The quality evaluation for overall project shall be conducted after the quality
evaluation for all single units, net special test, the performance tests of the units and the
engineering archives management evaluation are completed.
7.0.2 Technical index evaluation of performance test of unit shall be in accordance with
those specified in Table 7.0.2.
Table 7.0.2 Evaluation Table of the Technical Indexes of Performance Test on Single Unit
Project name Unit number
Evaluation
Test organization
organization
Thermal efficiency
1 Dominant
of boiler
Maximum
2 continuous rating of
boiler
Minimum stable
combustion rating
4
of boiler fuel (arc)
cut
Coal pulverizing
5
system rating
Unit consumption
6
of coal pulverizer
Dust remover
8
efficiency
396
steam turbine
(combustion
engine)
Nominal rating of
steam turbine
10
(combustion
engine)
Heat consumption
of steam turbine
11 Dominant
(combustion
engine)
Coal consumption
12 of unit power Dominant
supply
Station service
13 power consumption Dominant
rate of unit
Shafting vibration
14 Dominant
of unit
15 Unit RB test
Pollutant emission
16 (NOx, SO2, fume Dominant
and waste water)
17 Noise
18 Heat dissipation
19 Dust
Denitration
20
efficiency
Denitration
21
efficiency
Water consumption
23 rate for power Dominant
generation
Evaluation score:
Evaluator (signature):
Date
Note 1: Class I: evaluation score 92 (including 92)~100; each index reaching design value, contract guarantee value and relevant
criteria; test conditions meeting the requirements; test reports and statistical forms complete and normative.
Note 2: Class II: evaluation score 85 (including 85)~92; dominant indexes reaching design value, contract guarantee value and
relevant criteria; test conditions meeting the requirements; 85% and above general indexes reaching design value, contract
guarantee value and relevant criteria, test reports and statistical forms complete and normative fundamentally.
397
Note 3: Class III: evaluation score 70 (including 70)~85; dominant indexes reaching design value, contract guarantee value and
relevant criteria; test conditions meeting the requirements; 70% and above general indexes reaching design value, contract
guarantee value and relevant criteria, test reports and statistical forms complete and normative fundamentally.
7.0.3 The evaluation on the engineering archives management shall be in accordance with
those specified in Table 7.0.3.
Table 7.0.3 Evaluation Table of Engineering Archives Management
Project name Project scale
Development Evaluation
organization organization
Content of
Deserved Obtained
Evaluation content unmatched Remarks
score score
item
Evaluation
result
Evaluator (signature):
Date
398
Note 1: Class I: evaluation score of 92 (including 92)~100.
Note 2: Class II: evaluation score of 85(including 85)~ 92.
Note 3: Class III: evaluation score of 70(including 70)~85.
3 Patent
4 Working method
5 QC achievement
7 New record
8 Saving
9 Environmental protection
Total score:
Evaluator (signature):
Evaluation organization (official seal)
Date
7.0.5 Overall project quality evaluation score is the sum of mean value of all single unit
evaluation scores, mean value of all unit performance test evaluation scores, obtained score of
engineering archives management evaluation and awarded scores; overall project quality shall
be evaluated according to those specified in Table 7.0.5.
Table 7.0.5 Summary Table of Overall Project Quality Evaluation
Project name Project scale
4 Awarded score
Evaluator (signature):
Evaluation organization (official seal)
Date
7.0.6 Fine project: overall project quality evaluation score is 85 and above; high-quality fine
project: 92 and above.
7.0.7 Overall project quality evaluation shall be organized and coordinated by the
development organization, and carried out independently by the supervision organization or
399
other evaluation organizations. The evaluation results shall be issued with evaluation report.
7.0.8 Overall project quality evaluation shall meet the relevant current national and
professional regulations on project completion acceptance and evaluation.
400
Annex A
(Informative)
A.1 Typical data of flow passage clearance of STC 300MW steam turbine (for your
information only)
A.1.1 Flow passage clearance of high- and medium-pressure cylinders
See Figure A.1 for the flow passage clearance of high- and medium-pressure cylinders.
Rotor
401
The location dimension K value of rotor is 9.80mm 0.13mm.
The design clearance values of the Grade 1~20 radial diaphragm gland and steam seal
gland of high- and medium-pressure rotors all are 0.75mm.
A.1.2 Flow passage clearance of low-pressure cylinders
1 See Figure A.2 for axial clearance.
Rotor Rotor
7 31.00 21.86
1 1.05 1.05 0 0
A.2 Typical data of flow passage clearance of STC 600MW steam turbine (for your
information only)
See Figure A.3 for the flow passage clearance of high- and medium-pressure cylinders.
402
Rotor
2 12
3 13
4 14
5 15
6 16
7 17
8 18
9 19
10 20
403
Valve adjusting end Motor end Rotor
location Rotor location
Grade Grade
A B E F A B E F dimension dimension K2
number number
K1
Steam gland clearance (radial gland of low-pressure Seal gland clearance (radial gland of low-pressure
Grade number
rotor blade) partition panel)
1 1.30~1.60
2 1.30~1.60 1.30~1.60
Valve
3 1.30~1.60 1.30~1.60
adjusting
4 1.50~1.80 1.40~1.70
end
5 3.40~3.70 1.30~1.60
6 1.00~1.30
1 1.30~1.60
2 1.30~1.60 1.30~1.60
5 3.40~3.70 1.30~1.60
6 1.00~1.30
404
A.3.2 Flow passage clearance of No.2 low-pressure rotor
1 See Figure A.6 for axial clearance.
Steam gland clearance (radial gland of low-pressure Seal gland clearance (radial gland of low-pressure
Grade number
rotor blade) partition panel)
1 1.30~1.60
2 1.30~1.60 1.30~1.60
Valve
3 1.30~1.60 1.30~1.60
adjusting
4 1.50~1.80 1.40~1.70
end
5 3.40~3.70 1.30~1.60
6 1.00~1.30
Motor 1 1.30~1.60
end 2 1.30~1.60 1.30~1.60
3 1.30~1.60 1.30~1.60
4 1.50~1.80 1.40~1.70
5 3.40~3.70 1.30~1.60
405
6 1.00~1.30
A.4 Typical data of flow passage clearance of HTC 1000MW steam turbine (for your
information only)
A.4.1 Flow passage clearance of low-pressure rotor
1 See Figure A.8 for the axial clearance on the steam admission side at blade top and
root.
Low-pressure rotor
Figure A.8 Axial Clearance on the Steam Admission Side at Blade Top and Root of Low-pressure Rotor
2 See Figure A.9 for the axial clearance of Grade 1 and Grade 2 tip glands at valve
adjusting end
1 9.40 9.40
406
2 9.40 9.40
Figure A.9 Axial Clearance of Grade 1 and Grade 2 Tip Gland at Valve Adjusting End of Low-pressure
Rotor
3 See Figure A.10 for the radial clearance of Grade 2~6 diaphragm glands.
Low-pressure rotor
N
Grade number
Right side Left side Top Bottom
Figure A.10 Radial Clearance of Grade 2~6 Diaphragm Glands of Low-pressure Rotor
4 See Figure A.11 for the radial clearance of the tip gland at blade top.
Low-pressure rotor
Z-1
Grade number
Right side Left side Top Bottom
407
4 3.70 3.30 3.70 3.50
Figure A.11 Radial Clearance of Tip Gland at Blade Top of Low-pressure Rotor
A.4.2 Flow passage clearance of medium-pressure rotor
1 See Figure A.12 for the axial clearance on the steam admission side at blade top and
root.
Figure A.12 Axial Clearance on the Steam Admission Side at Blade Top and Root of Medium-pressure
Rotor
2 See Figure A.13 for the axial clearance of the tip gland at blade top.
408
Steam flow direction
Figure A.13 Axial Clearance of Tip Gland at Blade Top of Medium-pressure Rotor
3 See Figure A.14 for the axial clearance of diaphragm gland.
Rotor
409
6 4.56 7.55 12.47 9.17
O
Grade number
Right side Left side Top Bottom
Figure A.15 Radial Clearance of Tip Gland at Blade Top of Medium-pressure Rotor
5 See Figure A.16 for the radial clearance of diaphragm gland.
Steam flow direction
Rotor
N
Grade number
Right side Left side Top Bottom
410
A.4.3 Flow passage clearance of high-pressure rotor
1 See Figure A.17 for the axial clearance on the steam admission side at blade top and
root.
1 4.50 5.30
2 5.40 6.20
3 5.70 6.30
4 6.30 7.10
5 6.90 7.70
6 7.30 8.10
7 7.30 8.10
8 8.30 9.10
9 8.30 9.10
10 8.30 9.10
Figure A.17 Axial Clearance on the Steam Admission Side at Blade Top and Root of High-pressure Rotor
2 See Figure A.18 for the axial clearance of the tip gland at blade top.
411
Steam flow direction
Grade 1
Grade 2~10
1 5.10 4.70
2 7.50 5.90
3 8.00 6.10
4 8.50 6.70
5 8.80 7.30
6 9.20 7.60
7 9.60 7.80
8 9.90 8.70
9 10.20 8.50
10 10.40 8.70
Figure A.18 Axial Clearance of Tip Gland at Blade Top of High-pressure Rotor
3 See Figure A.19 for the axial clearance of Grade 2~10 diaphragm glands.
412
Grade number M M'
2 9.53 7.32
3 9.53 7.32
4 9.53 7.32
5 10.43 8.02
6 10.43 8.02
7 12.12 9.52
8 12.12 9.52
9 12.12 9.52
10 12.12 9.52
Figure A.19 Axial Clearance of Grade 2~10 Diaphragm Glands of High-pressure Rotor
4 See Figure A.20 for the radial clearance of the tip gland at blade top.
Grade 1
Grade 2~10
O
Grade number
Right side Left side Top Bottom
Figure A.20 Radial Clearance of Tip Gland at Blade Top of High-pressure Rotor
413
5 See Figure A.21 for the radial clearance of Grade 2~10 diaphragm glands.
N
Grade number
Right side Left side Top Bottom
Figure A.21 Radial Clearance of Grade 2~10 Diaphragm Glands of High-pressure Rotor
414
Annex B
(Informative)
B.1 The Oil Quality Standards of National Aerospace Standard (NAS, 1638) was issued in
January 1984, see Table B.1.
Table B.1 NAS Grading Standards for Oil Cleanliness
100/mL
5~15 15~25 25~50 50~100 100~250 250
00 125 22 4 1 0 0
0 250 44 8 2 0 0
1 500 59 16 5 1 0
2 1000 178 32 6 1 0
3 2000 356 63 11 2 0
B.2 MOOG Pollution Grade Standard jointly proposed by Aircraft Industries Association of
America (ALA), American Society for Testing and Materials (ASTM) and Society of
Automotive Engineers (SAE) is detailed in Table B.2, contamination scope of different
Grades: Grade 0--very difficult to realize; Grade 1--super clean system; Grade 2--high-level
guided missile system; Grade 3 and Grade 4--common precision devices (like electric
hydraulic servoactuator); Grade 5--low-level guided missile system; Grade 6-Grade 1
industrial system.
Table B.2 MOOG Pollution Grade Standard
100/mL
5~10 10~25 25~50 50~100 >100
0 2700 670 93 16 1
415
5 87000 21400 3130 430 41
B.3 As for the equality relation between ISO grading standards and NAS and MOOG
grading standards, the International Standardization Organization (ISO) considers s kind of
improved grading standard, the grades of quantity with the grain sizes above 5m and above
15m may be looked up from ISO Drawing, and now the equality relation between ISO
grading standards and MOOG and NAS grading standards are listed in Table B.3.
Table B.3 Equality Relation between ISO Grading Standards and NAS and MOOG Grading Standards
ISO standard NAS standard MOOG standard
26/23
25/23
12
23/20
21/18
21/18
11
20/17
20/16
10
19/16
18/15 9 6
17/14 8 5
16/13 7 4
15/12 6 3
14/11 5 2
13/10 4 1
12/9 3 0
11/8 2
10/8
1
10/7
10/6
0
9/6
8/5 00
7/5
6/3
5/2
2/0.8
416
Annex C
(Normative)
The bearing vibration (double amplitude) criteria for accessory machines shall be made
reference to DL 5011 and are detailed in Table C.1.
Table C.1 Bearing Vibration (double amplitude) Criteria for Accessory Machines
r/min
High class Good Qualified
417
Annex D
(Normative)
The allowable deviation value (maximum value of the reading difference between
opposite faces) for the coupling centre alignment of accessory machines shall be made
reference to DL 5011 and is detailed in Table D.1.
Table D.1 Allowable Deviation Value (maximum value of the reading difference between opposite faces)
for Centre Alignment of Coupling
418