FORMULA PERHITUNGAN INDEKS KINERJA PEMBANGKIT

UNIT PEMBANGKIT TUNGGAL

AH
1 Availabillty Factor ( AF ) x100%
PH

2 Equavalent Availabillty Factor ( EAF ) AH ( EFDH EMDH EPDH ESEDH


x100%
PH

3 Service Factor ( SF ) SH
x100%
PH

4 Planneed Outage Factor ( POF ) POH


x100%
PH

5 Maintanance Shutdown Factor ( MOF ) MOH


x100%
PH

6 Reserve Shutdown (RSF ) RSH


x100%
PH

7 Unit Derating Factor ( UDF ) EPDH EUDH


x100%
PH

8 Scheduled Outage Factor ( SOF ) POH MOH


x100%
PH
FOH
9 Forced Outage Factor ( FOF ) x100%
PH
FOH
x100%
1 Forced Outage Rate ( FOR ) FOH SH Synchronoushours
0

1 Forced Outage Rate demand ( FORd ) fxFOF


1
x100%
( fxFOH SH

1 Equivalent Forced Outage Rate ( EFOR ) FOH EFDH


x100%
2 FOH SH Syinchronoushours EFDHRS
( fxFOH ) ( fpxEFDH
1 Equivalent Forced Outage Rate demand ( EFORd )**)
( fxFOH ) SH
3 Dimana:
**) Untuk pembangkit pemikul beban puncak Fp=(SH/AH)
Jika SH,FOH atau RSH = 0, maka untuk perhitungan diberi angka f = (1/r + 1/T) / ( 1/r + 1/T+1/D)
0,001. r = Durasi FO rta-rata = (FOH/Jumlah kejadian FO )
Jika jumlah kejadian FO,Start atau start Aktual = 0, maka D = Jumlah operasi rata-rata = (SH/jumlah start actual
perhitungan diberi angka 1. T=RSH rata-rata (RSH/jumlah start yang dilakukan,baik berhasil
maupun gagal )
1 Net Capacity Factor (NCF ) Pr oduksiNetto
4 x100%
PHxDMN
1 Neto Output Factor ( NOF ) Pr oduksiNetto
5 x100%
SHxDMN
1 Plant Factor ( PF ) Pr oduksiNetto
6
x100%
( AH ( EPDH EUDH )) xDMN