You are on page 1of 1

November 2016 December 2016 January 2017 February 2017 March 2017

Phase Level Activities/Task Responsibility START FINISH 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20


Client Proposal NOV-30-
1 Establish 2016
2 End User Define Client ALL Dec-3- Dec-7-
Requirement Requirement 2016 2016
3 Planning/Brainstorming ALL Dec-8- Dec-12-
2016 2016
4 Interview/Research about KEVIN/REX/PABLO Dec-13- Dec-17-
proposal requirements 2016 2016
5 Checklist proposal ALL Jan-4 Jan-9-
2017 2017
6 Presentation Proposal to ALL Jan-9- Jan-14
the Panelist 2017 2017
7 Submit Requirement ALL Jan-16- JAN-20-
Checklist and Approval 2017 2017
8 Plan on Programming ALL Jan-22- Jan-24-
Language to be used 2017 2017
9 Design on GUI REX Jan-25- Jan-30-
Global Design & of the System 2017 2017
10 Detail Design Submit the GUI design CURA Jan-25- Jan-30-
Implementation To the client 2017 2017
11 Create DFD level 0-2 RONNEL Jan-25- Jan-30-
2017 2017
12 Create ERD RONNEL Jan-25- Jan-30-
2017 2017
13 Create Story Board PABLO/REX Jan-25- Jan-30-
2017 2017
14 Create Use-Case View KEVIN Jan-25- Jan-30-
2017 2017
15 PHP Coding Process ALL Jan-30- March-
2017 27-2017
16 Database Implementation RONNEL/CABAYA Jan-30- March-
2017 27-2017
17 Plan of test approach KEVIN/PABLO March- March-
15-2017 27-2017
18 Testing Conduct Module Testing CURA March- March-
18-2017 27-2017
19 Conduct System CURA March- March-
Testing 18-2017 27-2017
20 Conduct Users PABLO/REX March- March-
Acceptability Test 18-2017 27-2017
21 Conduct Test for System PABLO/REX March- March-
Attributes 18-2017 27-2017
22 Deployment Installation of the System RONNEL Ongoing Ongoing
23 Training of the User PABLO Ongoing Ongoing
24 Maintenance Support Enhancement ALL Ongoing Ongoing

You might also like