You are on page 1of 1

SAVEB Global investment

No.40, Bakori Road Kubwa F.C.T. Abuja


Tel:08039788582,08038403268,08058170112
Email: akinodematthew@yahoo.com

ESTIMATE FOR SWIMMING POOL

s/n Item Description Unit Qty Rate Amount


A Excavation of Bulk Area of Pool M2 94 950 150,000
Blinding
B 50mm plane in-situ blinding to bed M2 60 3500 210,000
C High yield bond reinforcement Kg 190 2000 380,000
12mm & 10mm
D 9mm Water membrane bar lm 55 2950 162,250
E Concrete Works
250mm waterproof bed M2 60 7450 447,000
200mm waterproof wall M2 60 7950 477,000
workmanship 150,000
Nitro bond SPR Liters 40 3450 138,000
F Swan from wall to all sides of the M2 192 1650 316,800
pool
Sum carried to summary 2,431,050

G Finishings
M2 50 1850 92,500
M2 55 1850 101,750
H Approved mosaic tiles laid to bed & M2 100 4960 496,000
wall with white cement & adhesive
I Approved anti slippery tiles laid to M2 40 4450 178,000
pool deck with sketting
workmanship 180,000
Swimming pool continued 1,048,250
Sum carried to summary
J Pool Equipments & Installations
24 Fiberglass sand filtration system 1 389,560
& 1HP Pump

Landscaping Specialist Sales And Servicing Of Lawn And Ridding Mower, Designs Interior Decoration, Renovation ,
Construction And Maintenance Of Swimming Pool , Interlocking Laying And Building Construction