You are on page 1of 68

TECHNICAL

SPECIFICATION

FOR

ROAD WORKS
CHAPTER I

EARTH / MURRUM FILLING WORKS

1.0 SCOPE

1.1 This Specification covers classification of soil for earth work in excavation
and filling for site grading work. Reference Standards
Classification of soil for earth work in site grading 6-65-0016.

2.0 ORDINARY SOIL

2.1 Soft Soil/loose Soil


Generally any soil which yields to the ordinary application of pick and
showel, or to phawara, rake or other ordinary digging implements such as :
Sand, gravel, loam, clay, mud, black cotton soil.
Vegetation or organic soil, turf, peats, soft shale or loose murrum.
Mud concrete below ground level.
Any mixture of soil below ground level.

2.2 Hard / Dense Soil


Generally any soil which requires the close application of picks or Jumpers
or scarifier and rippers to loosen the same. Such as:

Stiff heavy clay, hard shale or compact murrum requiring grafting tool
and/ or pick and shovel.

Shingle and river or nallah bed boulders.

Soling or roads, paths, etc and hard core.

Macadam surface of any description(water bound, grouted tarmac ,


etc)

Lime concrete, stone masonry in lime or cement mortar below ground


level.

Soft conglomerate.

3.0 SOFT ROCK

This is fissured / disintegrated rocky strata, boulders (volume less than 0.4
Cu.M and more than 0.028 Cu.M) and also which cannot be
quarried/excavated by using above manual Tools but can be quarried
/excavated manually by using crow bars is classified as soft rock. Soft rock
shall include all kinds of stiff and stratified rock such as shales, laterite, hard
conglomerate, lime stone, sand stone, and unreinforced cement concrete
below ground level. Soft rock may be quarried or split with crow bar or picks
and can also be excavated by rippers, dozers and other mechanical
equipment but without the aid of blasting.

4.0 EXCAVATION

4.1 This specification covers in general the scope of excavation for this
tender only which is to be carried out as per drawings and as directed
by EIC.

4.2 The excavation mainly has to be carried out in soft soil / top soil i.e. to
the required line level and as directed by EIC

4.3 The site will be handed over to contractor with Vegetation/ bushes/
shrubs/ trees etc. Contractor shall visit the site to ascertain the nature
of ground prior to bidding to accept all the responsibilities. The removal
of the above is included in the scope of excavation and no additional
payment will be made on this account.

4.4 HPCL shall hand over the Bench Marks at site only . The proceeding
activities for setting out of work like plotting grid points with Brick
Pedestals on the land, fixing the center point for tanks as per drawing
with physical verification with existing structures/land marks for
distances measurement purpose, setting out the two permanent centre
lines for each tank along with RL of main B.M. on brick pedestals etc
to the satisfaction of EIC after stripping / clearing the ground complete
in all respect . All the survey equipment like theodolite etc, skilled &
qualified surveying manpower, recording & maintaining the
measurement book, tools & tackles etc completely at contractors cost
to the best satisfaction of HPCL.

4.5 The contractor shall provide at his own cost all the assistance which
EIC may require for checking the setting out of works. The contractor
shall be solely responsible for the horizontal & vertical alignment,
correctness of level, and correctness of every part of work and shall
rectify any errors or imperfection therein on instruction of EIC.

4.6 Prior to commencing the excavation, requisite block ground levels of


entire plot grid co-ordinate wise shall be taken by contractor at 5 meter
intervals in consultation & presence of EIC. The proper duly signed
record for the same shall be maintained.

4.7 Excavation shall be carried out once setting out of work by Contractor
is approved by HPCL. Contractor shall excavate the soil as per
approved drawings which enumerate the levels to be achieved. The
carting away and leveling of excavated earth shall be carried out as
per specifications and as directed by EIC with in the premises. To
minimize / avoid side sloughing and collapse sufficient side slope has
to be maintained by Contractor. The excavation for side slope to avoid
sloughing and collapse will not be entertained for payment. Royalty
payment, if any to be made towards excavation shall be made by the
Contractor as quoted rates are deemed to include the same.

4.8 Soil strata received as above shall be rolled thoroughly by 10T roller till
95% standard proctor maximum laboratory dry density is attained as
directed by EIC. Thereupon at corresponding co-ordinates at 5m
interval, level shall be taken to ascertain the excavated height as
instructed by EIC.

Contractor shall maintain adequate drainage facilities at site at all


times during the execution of work. Additional ditches, drains & such
other temporary means to achieve this, over and above what is shown
in drawings, will be provided and maintained by Contractor at his own
cost. Adequate dewatering facilities like dewatering pumps, piping etc
will also be provided by the Contractor for this work and also for
dewatering during excavation etc. at his own cost.

5.0 MATERIAL FOR EARTHWORK

Only material considered suitable by the Engineer-in-charge shall be


Employed for the construction and that considered unsuitable shall be
Disposed off , as directed by Engineer-in-charge, at his own cost
and no claim for compensation will be entertained.

The Contractor shall give the samples of earth he proposed to use


for filling along with the following characteristics of the samples to
Engineer- In-charge, prior to collection and use, for approval. The tests
for these characteristics shall be done in a laboratory/test house as
approved by Engineer-in-charge.

i. Mechanical Analysis or grain size distribution as per IS:2720 part iv


ii. Liquid Limit as per IS:2720 part v
iii. Plastic Limit as per IS:2720 part v
iv. Moisture Density relationship as per IS:2720 part vii

The material (soil) used for filling shall be free from boulders, lumps,
tree roots , rubbish or any organic deleterious material.

Material (soil ) having plasticity index less than 20 shall be used for
filling purposes.
Soil having laboratory maximum dry density of less than 1.5 gms/cc
shall not be used.

Care shall be taken to see that unsuitable waste material is disposed


off in such a manner that there is no likelihood of its getting mixed with
the material proposed to be used for filling.The work shall be so
planned and executed that the best available Material(soil) are
reserved for the Top portion of embankments.

6.0 CLEARING AND STRIPPING

The areas including depressions, where filling or cutting is to be


carried out shall be cleared and stripped completely of bushes, roots,
vegetation, plantation trees, shrubs, trees, organic and other
objectionable materials. All these shall be completely uprooted and
virgin soil exposed not merely scrapped at the surface. The roots of
trees shall be removed to a minimum depth of 1 m below existing
ground level and holes, hollows filled up with selected approved
available earth within all leads and lifts and compacted to obtain 90% of
laboratory dry density of soil and levelled as directed by Engineer-in-
charge. All soft patches must be worked out to remove soft soil and
selected approved earth must be filled back and the areas (areas
coming under filling ) compacted to obtain 90% of maximum laboratory
dry density of soil, as per IS:2720 part vii. The depth of stripping shall
be generally 50 to 150 mm as decided by Engineer-in-charge.

Material obtained from clearing shall be disposed off as directed by


Engineer-in-charge and in line with local bye laws/ statutory
requirements.

Payment

No separate payment shall be made for clearing, stripping and disposal


of materials obtained from clearing .This shall be considered as part of
cutting work in areas of cutting and filling work in areas of filling and the
rates quoted under the respective items of:

i. Earthwork in Excavation/cutting.

ii. Earthwork in filling (Both with available earth & earth obtained
from approved borrow areas ), shall be inclusive of clearing and
stripping with all operations described above in clause no.5 in
respective areas of cutting and filling.

No separate payment shall be made for cleaning, stripping and disposal


of materials obtained from clearing of borrow areas for earth as directed
by Engineer-in-charge.This shall be considered a part of filling work in
area of filling and the rate quoted under the respective items.

7.0 EARTHWORK IN EXCAVATION / CUTTING

After clearing, stripping of areas as specified above, spot levels at


intervals and pattern as decided by Engineer in charge shall be taken
jointly with the Contractor and Engineer in charge, and Excavation /
cutting shall commence only after the levels are signed by the
contractor as token of acceptance.

Excavation/ cutting for this work shall be carried out strictly as per the
instructions of Engineer in charge

If the contractor excavates / cuts beyond the required level, additional


quantity of earthwork shall not be paid for .The excavation taken
below the specified level shall be made good by filling with approved
material to the required compaction at contractors cost.

The final bed and sides of excavation must be levelled, dressed and
compacted. In case of areas under excavation for Site Grading, the
final surface shall be levelled, dressed and consolidated by means of
sheep foot/ power driven rollers to obtain maximum compaction.
However, no test control is required in such areas.

Provision for dewatering shall be governed by relevant clauses.

Payment

Payment for excavation shall be on the basis of volume of excavation


Calculated on the basis of joint level taken for initial and the final
finished grade levels, the volume being calculated by the trapezoidal
rule.

8.0 EARTH WORK IN FILLING

After clearing, stripping and consolidation of areas as specified in


clause 6, spot levels at intervals and pattern as decided by Engineer-
in-charge shall be taken jointly with the Contractor and Engineer-in-
charge and filling shall commence only after the levels are signed by
the Contractor as the token of his acceptance .Approved fill material
shall be spread in uniform layers not exceeding 30 cms in loose depth.
The contractor has to make his own approach and access roads from
the borrow area to the demarcated filling areas. While the contractor
may make use of such short cuts as may be available to him for earth
movement from borrow areas to the filling areas, the Owner does not
guarantee any pass way or the right of way for the Contractor work
other than available at site. No claim shall also be admissible to the
Contractor on the account of his having taken longer leads or routes
for earth movement, than envisaged by him, either due to any road
cuttings, non-availability of routes, or any other grounds whatsoever.
In case of total filling required in any area consists of earth both from
borrow areas and available approved excavated material from within
plant area, then joint levels, shall be taken before commencing filling
with earth from borrow area.
However earth from borrow areas required for filling can be used only
after the available earth from within demarcated area has been utilized
and clearance to this effect obtained from Engineer-in-charge.

All clods, lumps etc , shall be broken before compaction.

Successive layers of filling shall not be placed until the layer below has
been thoroughly compacted to satisfy the requirements laid down in
the specification.

Prior to rolling, the moisture content of material shall be brought to


within plus /minus 2% of the optimum moisture content as described in
IS:2720 part vii. The moisture content shall preferably be on the wet
side for potentially expansive soil.

After adjusting the moisture content as described ,the layers shall be


thoroughly compacted by either sheep foot roller or power driven roller
or vibratory roller as approved by Engineer-in-charge till the specified
maximum laboratory dry density is obtained.

Each layer shall be tested in field for density and accepted by


Engineer-in-charge subject to achieving the required density before
laying the next layer. A minimum of one test per 500m2 for each layer
shall be conducted.

If the layer fails to meet the required density, it shall be reworked or


the material shall be replaced and method of construction altered as
directed by Engineer-in-charge to obtain the required density.

The filling shall be finished in conformity with the alignment, levels,


cross section and dimensions as shown in the drawing. Earthen
embankment shall be filled 300mm on both sides, where height is
more than 1m, and this extra filling shall be dressed, after compaction ,
in conformity with alignment, level, cross section and dimensions as
shown in drawing to achieve proper compaction in the slope. No extra
payment shall be made in this regards.
All the royalty payments etc. as deemed admissible to statutory / govt.
authorities will be paid by contractor for all the earth brought for HPCL
works. It shall be the responsibility for the contractor to produce all such
payments, documents to Engineer-in-Charge during submission of
running bill. At the end of work no objection certificate from relevant
authorities will be submitted to ensure that HPCL is kept free from all
encumbrances

Extra material shall be removed and disposed off as directed by


Engineer-in-charge .

Tolerances
General site grading including cutting and filling in depressions shall be
carried out to within up down tolerance of+/- 5 cms of final lines grades
and slopes.

Payment

Payment for filling shall be made on cubic metre of volume calculated


on the basis of cross-section plotted from the levels of ground, where
filling is to be carried out and the levels reached after filling is duly
consolidated, volume being calculated by trapezoidal method.

Partial bill will be processed only after submission of duly certified


copy of proof of payment towards royalty.

Final bill will be processed only after submission of No objection


certificate from relevant statutory authorities towards payment of
royalty.

No extra payment shall be made towards testing charges.

9.0 MISCELLANEOUS & ENABLING WORKS

The Land development work shall be commenced in following sequence.

a. Taking spot levels and marking grid pillars and clearing bushes &
vegetation.
b. Identifying Borrow areas and obtaining laboratory results regarding
nature of soil, Optimum moisture content (OMC) and max dry density.
c. Submission of earth filling and excavation procedure.
d. Earthwork in excavation and filling. The filling shall be done in layers not
exceeding 300mm (loose) and compacted with 8-10T roller/ vibro roller so
as to achieve 95% dry density. The field testing shall be done for every
layer per 500sqm.
e. The borrow area earth brought from outside should also be commenced
simultaneously (only after it is ensured that the excavated earth within
premises shall be utilized in filling fully). Whenever there is a change in
source of earth, fresh laboratory test shall be carried out and submitted.
f. Proper watering should be ensured during filling and compaction
operation so that moisture content is near OMC.
g. Party should ensure that all royalty and other cess are paid before earth
is brought to site for filling operation.
h. The trees cut within premises should be uprooted up to 1m below ground
level and the branches to be chopped to small sizes and stacked at
designated place within premises.
i. Coordination with other contractors, creating front for others for execution
of job.

10.0 SPECIFICATION FOR MURRUM FILLING

1.0 This covers the specification for external borrowed earth material i.e.
MURRUM for land filling purposes..

2.0 Only Material considered suitable by HPCL shall be employed for the
construction and that consider unsuitable shall be disposed of, as
directed by Engineer-in-Charge, at contractors cost and no claim for
compensation will be entertain

3.0 The contractor shall give 4 to 5 samples minimum to cover the best
material available in around the vicinity to Engineer-in-Charge / HPCL
prior to collection and use for approval The test for following
characteristic for all the samples shall be done in a laboratory / test
house as guided by Engineer-in-Charge:

i ) Mechanical analysis are grain size distribution as per IS:2720 part IV.
ii ) Liquid limit as per IS:2720 part V
iii )Plastic limit as per IS: 2720 part V
iv) Moisture density relationship as per IS: 2720 part VII

4.0 The murrum used for filling shall be free from boulders, lumps, tree
roots, rubbish or any organic deleterious materials.

5.0 Murrum approved by HPCL shall only be used for filling purpose. Non
plastic material will not be permitted

6.0 Murrum having standard proctor laboratory maximum dry density of less
than 1.8 gms/cc shall not be used. The murrum shall have a Plasticity
Index of 7-17(medium Plastic) and not more than 20%Fines,i.e., Clay.
Particle size grading shall be 20mm and down size.

7.0 Care shall be taken to see that waste material from murrum is disposed
of in such a manner that there is no likely hood of its getting mixed with
the material proposed to be used for filling.
8.0 The contractor has to make own approach and access roads in the
borrow areas(Outside Plant Premises) and to the demarcated filling
area(Inside Plant Premises).

9.0 All the royalty payments etc. as deemed admissible to statutory / govt.
authorities will be paid by contractor for all the murrum brought for
HPCL works. It shall be the responsibility for the contractor to produce
all such payments, documents to Engineer-in-Charge during
submission of running bill. At the end of work no objection certificate
from relevant authorities will be submitted to ensure that HPCL is kept
free from all encumbrances.

10.0 Approved murrum material shall be spread in uniform layers not


exceeding 20 cm in loose thickness and watered as per OMC.

11.0 After checking the moisture through moisture tester by calcium carbide
method in field for OMC, the layers shall be thoroughly compacted by
vibratory roller as approved by Engineer-in-Charge till 95% of Standard
proctor maximum laboratory dry density is achieved. Each layer shall
be tested in field for density and accepted by HPCL subject to 95% of
Standard proctor maximum laboratory dry density being achieved. A
minimum of 1 test per 500 sq. mt. of compacted area in field shall be
conducted for dry density. Required equipments like Moisture Tester,
Oven, Electronic weighing machine, proctor apparatus shall be
supplied by Contractor.

12.0 Successive layers of filling and watering will not be permitted until the
layer below has been compacted thoroughly to satisfy the
requirements of the specifications. If the layer fails to meet the required
density, it shall be reworked till the required density is achieved.

13.0 The filling shall be finished in conformity with alignment levels, cross
section and dimension as shown in the drawing. Earthen embankment
shall be filled suitably on both sides to achieve the required
compaction and this extra filling shall be dressed after compaction, in
conformity with alignment, levels, cross section and dimensions as
shown in the drawing. No extra payment shall be made in this regard.

11.0 The excavated soil and / or unusable debris from excavation shall be
loaded, transported safely and unloaded at designated spots as
specified/ as per local bye laws. In case of disposal within the premises,
the soil/debris after unloading shall be levelled and dozed keeping a
distance of at least 5m from the Compound wall to give a uniform
appearance. No extra payment shall be made in this regard.
Payment

Payment for filling shall be made on cubic metre of volume calculated


on the basis of cross-section plotted from the levels of ground, where
filling is to be carried out and the levels reached after filling is duly
consolidated, volume being calculated by trapezoidal method.

Partial bill will be processed only after submission of duly certified


copy of proof of payment towards royalty.

Final bill will be processed only after submission of No objection


certificate from relevant statutory authorities towards payment of
royalty.

No extra payment shall be made towards testing charges.

CHAPTER - II
CONSTRUCTION OF WBM BASE/SUBBASE FOR
ROADS

WBM SUB BASE/ BASE COURSE

1. SCOPE

1.1 This work shall consist of clean crushed aggregates mechanically interlocked
by rolling and bonded together with screening, binding material where necessary
and water laid on a properly prepared sub grade/ sub base/ base or existing
pavement, as in case may be and finished in accordance with the requirements of
these specification and in close conformity with the lines, grade, cross section and
thickness as per approved plans or as directed by the engineer.

1.2 it is however, not desirable to lay WBM on an existing thin black topped
surface without providing adequate drainage facility for water that would get
accumulated at the interface of existing bituminous surface and WBM.

2. MATERIAL
2.1 Coarse aggregate
2.1.1 General requirement

Coarse aggregates shall be crushed granite/basalt trap stone of suitable quality


.The aggregates shall conform to the physical requirements set forth in table
1.0.below.The type and size range of the aggregates shall be specified in contract
or shall be specified by the Engineer.
Table 1.0

Test Test method Requirement


Los Angeles abrasion value IS:2386( PART IV) 50% Max.

Aggregates impact value IS:2386( PART IV)


Or IS 5640 40% max.
Flakiness index IS 2386 (PART- I) 15% max.

2.2 CRUSHED OR BROKEN STONE

The crushed stone shall be either granite/basalt trap stone, hard, durable and free
from excess flat, elongated, soft and disintegrated particles, dirt and other
deleterious material.

2.3 GRADING REQUIREMENT OF COARSE AGGRAGATES

The coarse aggregates shall conform to one of the grading given in tables 2.0 as
specified, provided, however, the use of grading no. 1 shall be restricted to sub
base course only.

Table 2.0 grading requirements of coarse aggregates


Grading no. Size range Sieve % by weight
designation passing
1 90 mm to 45 125mm 100
mm 90mm 90-100
63 mm 25-60
45mm 0-15
22.4mm 0-5
2 63mm to 90mm 100
45mm 63mm 90-100
53mm 25-75
45mm 0-15
22.4mm 0-5

3 53mm to 22.4 63mm 100


mm 53mm 95-100
45mm 65-90
22.4mm 0-10
11.2mm 0-5
Note :-the compacted thickness for a layer with grade I shall100 mm while for layer
with other grades i.e. 2&3, it shall be 75 mm.
2.4 SCREENINGS

Screenings to fill voids in coarse aggregates shall consists of the same materials
as coarse aggregates .However, where permitted predominantly non plastic
material such as moorum or gravel (other than rounded river bound materials) may
be used for this purpose provided liquid limit and plasticity index of such material
are below 20 and 6 respectively and fraction passing 75micro meter sieve does not
exceed 10 %.

Screening shall conform to the grading set forth in table 3.0 .the consolidated
details of quantity of screening required for various grades of stone aggregates
are given in table 4.0 .table also gives the quantity of materials(loose) required for
10 m^2 for sub base compacted thickness of 75/100 mm.

Table 3.0 Grading for screening

Grading Size of screening Sieve designation % by weight


classification passing the sieve
A 13.2 13.2mm 100
11.2mm 95-100
5.6mm 15-35
180 micron meter 0-10
B 11.2 11.2mm 100
5.6mm 90-100
180 micron mete 15-35

`TABLE 4.0Approximate quantity of coarse aggregates and screening required for


100/75 mm thickness for WBM Sub base/base course /for 10 m^2.

Classificatio Size Compacte Loose quantity screenings


n range d Grading Loose Grading Loose
thickness classificat quantity classification quantit
ion and and size y
size
Grading 1 90mm 100mm Type A 0.27 to Not uniform 0.30 to
to 13.2mm 0.30 0.32
45mm m^3 m^3
Grading 2 63 to 75mm Type A 0.12 to Do 0.22 to
45mm 13.2mm 0.15 0.24
m^3 m^3
do Do Do Type B 0.20 to Do
11.2mm 0.22m^ do
3
Grading 3 53 to 75mm do 0.18 to Do
22.4 0.21 do
mm m^3
2.5. BINDING MATERIAL

Binding material to be used for WBM as a filler material like murrum meant for
preventing raveling, shall comprise of a suitable material approved by engineer
having a plastic index value of les than 10 as determined in accordance with Is
:2720(part v )

The quantity of binding material where it is to be used will depend on the type of
screening. Generally, the quantity required for 75 mm compacted thickness of
WBM will be 0.06-0.09 m^3/ 10 m^2 and 0.08-0.10 m^3/ 10 m^2 for 100 mm
compacted thickness.

The above mentioned quantities should be taken as a guide only, for estimation of
quantities of construction, etc. application of binding materials may not be
necessary when the screenings used are of crushable type such as moorum or
gravel.

3. Construction Operation

3.1 Preparation of base

The surface of the sub grade/sub base/base to receive the WBM course shall be
prepared to the specified lines and cross fall (camber)and made free of dust and
other extraneous material. Any ruts or soft yielding places shall be corrected in an
approved manner and rolled until firm Sub base/base surface irregularities, where
predominant , shall be made good by providing appropriate type of profile
corrective course as per specification.

3.2 SPREADING COARSE AGGREGATES

The coarse aggregate shall be spread uniformly and evenly upon the prepared sub
grade /sub base/base to proper profile by using templates placed across the road
about 6 m apart, in such quantities that thickness of each compacted layer is not
more than 100mm for grading 1 and 75mm for grading 2 and 3 . Wherever
possible, approved mechanical devices shall be used to spread the aggregates
uniformly so as to minimize the needs for manual rectification onwards .aggregates
placed at location which are inaccessible to the spreading equipment, may be
spread in one or more layer by any approved means so as to achieve the specified
results.
The spreading shall be done from stockpiles along the side of the roadways or
directly from vehicles. in no case shall the aggregates be dumped in heaps directly
on the surface prepared to receive the aggregates nor shall hauling over
uncompacted or partially compacted base shall be allowed and the coarse
aggregate as spread shall be of uniform gradation with no pockets of fine material.
The surface of the aggregate spread shall be carefully checked with templates and
all high and low spots remedied by removing or adding aggregates as may be
required .the surface shall be checked frequently with a straight edge while
spreading and rolling so as to ensure a finished surface as par approved plan.
The coarse aggregate shall not normally be spread more than three days in
advance of the subsequent construction operation.

3.3 ROLLING

Immediately following the spreading of the coarse aggregate, rolling shall be


started with three wheeled power roller s of 8 to 10 tone capacity or tandem or
vibratory rollers of approved type . The type of roller to be used shall be approved
by the engineer based on trial run.

Except on super elevated portions where the rolling shall proceed from inner edge
to outer, rolling shall begin from the edge gradually progressing towards center
.first the edge/edges shall be compacted with roller running forwards and
backwards. the roller shall then move inwards parallel to the center line of road ,in
successive passes uniformly lapping preceding track by at least one half width.

Rolling shall be discontinued when the aggregate are partially compacted with
sufficient void space in them to permit application of screenings. During rolling,
slight sprinkling of water may be done, if necessary. Rolling shall not be done
when the sub grade is soft or yielding or when it causes a wave like motion in the
sub grade or sub base course.

The rolled surface shall be checked transversely and longitudinally .with templates
and any irregularity corrected by loosening the surface, adding or removing
necessary amount of aggregates and re-rolling until entire surface conforms to
desired cross fall(camber) and grade. In no case screening be permitted to
makeup depressions.

Materials which are crushed excessively during compaction or become segregated


shall be removed and replaced with suitable aggregates.

It shall be insured that shoulders are built up simultaneously along with WBM
courses.

3.4 APPLICATION OF SCREENING

After the coarse aggregates has been rolled to clause 3.3 screenings to completely
filled fill the interstices shall be applied gradually over the surface. these shall not
be damp or wet at time of application dry rolling shall be done while the screening
are being spread so that vibration of roller cause them to settle into the voids of the
coarse aggregates .the screening shall not dumped in piles but be spread
uniformly in successive thin layer either by the spreading motion of hand shovels
or by mechanical spreaders or directly from tipper with suitable grit spreading
arrangement .tipper operating for spreading the screenings shall be so driven as
not to disturb the coarse aggregates. the screening shall be applied in at a slow
and uniform rate(in three or more applications) so as to ensure filling of all voids
.this shall be accompanied by dry rolling and brooming with mechanical broom,
hand brooms or both. in no case shall the screening be applied so fast and thick
as to form cakes of ridges on the surface in such a manner as would prevent filling
of voids or prevent the direct bearing of roller on the coarse aggregates .these
operation shall continue until no more screenings can be forced into the voids of
he coarse aggregates.

The spreading, rolling, and brooming of screenings shall carried out in only such
length of road which could be compacted within one days operation.

3.5 SPRINKLING OF WATER AND GROUTING

After the screenings have been applied, the surface shall be copiously sprinkled
with water, swept and rolled .hand brooms shall be used to sweep the wet
screening into voids and to distribute them evenly. The sprinkling, sweeping and
rolling operation shall be continued until the coarse aggregate has been thoroughly
keyed, well bounded and firmly set in its full depth and a grout has been formed o
screenings. Care shall taken to see that the base or sub grade does not get
damaged due to the addition of excessive quantities of water during construction.

3.6 APPLICATION OF BINDING MATERIAL

After the application of screenings in accordance with clause 3.4 and 3.5 the
binding material where it is required to be used shall be applied successively in
two or more thin layers at thin and uniform rate .after each application ,the surface
shall be copiously sprinkled with water the resulting slurry swept in with hand
brooms or mechanical brooms to fill the voids properly ,and rolled during which
water, shall be applied to the wheels of the roller if necessary to wash down the
binding material sticking to them .these operations shall be continue until the
resulting slurry after filling the voids ,form a wave ahead of wheels of the moving
roller.

3.7 SETTING AND DRYING

After the final compaction of WBM course, the pavement shall be allowed to dry
over night .next morning hungry spots shall be filled with screening or binding
material as directed, lightly sprinkled with water if necessary and rolled .no traffic
shall be allowed on the road until macadam is set .the engineer shall have
discretion to stop hauling traffic from using the compacted WBM course, if in his
opinion it would cause excessive damaged to the surface.
The compacted WBM course should be allowed to completely dry and set before
the next pavement course is laid over it.
4. SURFACE FINISH AND QUALITY CONTROL OF WORK

4.1 The surface finish of construction shall be as specified with a tolerance of


10mm
4.2 The WBM work shall not be carried out when the atmospheric temperature is
less than zero degrees centigrade in the shed.

4.4 RECOSTRUCTION OF DEFECTIVE MACADAM

The finished surface of WBM shall conform to the tolerance of surface irregularity
of 10mm. However, where the surface irregularity of the course exceeds the
tolerance or where the course is other wise defective due to sub grade soil mixing
with the aggregates ,the course to its full thickness shall be sacrificed over the
affected area reshaped with added material as applicable and recompacted. in no
case shall depressions be filled up with screening or binding material.

4.5MEASUREMENT FOR PAYMENT

WBM shall be measured as finished work in position in square meter. The same
shall be payable in full for carrying out the all the required operations as described
above including full compaction, arrangement of all components of WBM including
water. The initial levels of surface of Subase is and final levels of WBM after
completion of full compaction are jointly recorded and the difference shall amount
to the thickness required as per SOR.

CHAPTER -III
CONSTRUCTION OF BITUMINOUS ROADS

1.0 TACK COAT

1.1 SCOPE
This work shall consist of application of a single coat of low viscosity liquid
bituminous material to an existing road surface preparatory to another bituminous
construction over it.
1.2 Materials :
The binder used for tack coat shall be bitumen conforming to IS: 73-2006
VG30 GRADE (erstwhile 60/70 as per IS:73-1992).
2.0 CONSTRUCTION OPERATION :
2.1 Preparation of base : The surface on which the tack coat is to be applied
shall be cleaned of dust and any extraneous material before the application of the
binder, by using a mechanical broom or any other approved equipment/method as
specified by the Engineer.
2.2 Application of binder :Binder shall be heated to the temperature appropriate
to the grade of bitumen used and approved by the Engineer and sprayed on the
base at the rate specified in Table below. The rate of spread is in terms of straight
bitumen.
Table : Rate of application of tack coat :
Type of Surface Bitumen quantity in
kg per 10 sq. mtr. area
i) Normal bituminous surfaces 5 to 5.5
ii) Dry and hungry bituminous surfaces 6.0 to 7.5
iii) Granular surfaces treated with primer 6.0 to 7.5
iv) Non bituminous surfaces
a) Granular base (not primed) 10.0
b) Cement concrete prevalent 7.5

Note: There is no need to apply a tack coat on a freshly laid bituminous course if
the subsequent bituminous course is overlaid immediately without opening it the
traffic.
The binder shall be applied alternately with the aid of either self propelled or
towed bitumen pressure sprayer with self heating arrangement and spraying
nozzle arrangement capable of spraying bitumen at specified rates and
temperature so as to provide a uniformly unbroken spread of bitumen.
The tack coat shall be applied just ahead of the oncoming bituminous
construction.
2.3 Quality Control of Work:
Control on the quality of materials and works shall be exercised by the
Engineer in accordance requirements mentioned in the specifications.
3.0 BITUMINOUS MACADAM ROADS

3.1 Scope :The work shall consist of construction in a single course, of 50 mm/75
mm thickness of compacted crushed aggregates premixed with a bituminous
binder, to serve as base/binder course, laid immediately after mixing, on a base
prepared previously in accordance with the requirement of these specifications and
in conformity with the line, grades and cross sections as directly by the Engineer.

3.2 Materials

3.2.1 Bitumen : The bitumen shall be paving bitumen of suitable penetration


grade of VG30 as per IS:73-2006 ((erstwhile 60/70 as per IS:73-1992).

3.2.2 Aggregates:
The aggregates shall consist of crushed granite/basalt stone or other stones
as approved by EIC. They shall be clean, strong, durable of fairly cubical shape
and free from disintegrated pieces, organics or other deleterious matters and
adherent coating. The aggregates shall preferably be hydrophobic and of low
porosity. If hydrophilic aggregates are to be used the bitumen shall preferably be
treated with anti stripping agents of approved quality in suitable doses. The
aggregates shall satisfy the physical requirements set forth in Table below.

Table: PHYSICAL RPQUIRIMNTS OR AGREEGATES FOR BITUMINOUS


MACADAM
Sr. Test Test Method Requirements
No.
1 Los Angeles Abrasion value IS: 2386 (Part IV) 40% Maximum
2 Aggregate Impact Value IS: 2386 (Part IV) 30% Maximum
3 Flakiness Index IS: 2386 (Part Ii) 35% Maximum
4 Stripping Value IS: 6241 25% Maximum
5 Soundness : 12%
i)Loss with Sodium Sulphate
5 cycles
ii)Loss with Magnesium 18%
Sulphate 5 cycles
6 Water absorption IS:2386(Part III) 2% Maximum

The aggregate for bituminous macadam for different thicknesses shall


conform to the Grading given in tables below.
TABLE: Aggregate Grading for 50mm compacted thickness of bituminous
macadam
Sieve Designation (IS) Percent by weight passing the aecia
26.5 mm 100
22.4 mm 75-100
11.2 mm 50-85
5.6 mm 20-40
2.8 mm 5-20
90 mm 0-5

TABLE: Aggregate Grading for 75mm compacted thickness of bituminous


macadam
Sieve Designation (IS) Percent by weight passing the aecia
45 mm 100
26.5 mm 75-100
22.4 mm 60-95
11.2 mm 30-55
5.6 mm 15-35
2.8 mm 5-20
90 um 0-5

3.3 Proportioning of materials : The bitumen content for premixing shall be 4


percent by weight of the total mix except when otherwise directed by the Engineer.
The quantities of aggregates to be used shall be sufficient to yield the specified
thickness after compaction.
3.4 Variation in proportioning on material :
The contractor shall have the responsibility for ensuring proper
proportioning of materials and producing a uniform mix. A variation in binder
content +0.3 percent by weight of total mix shall, however, be permissible for
individual specimens taken for quality control tests.

3.5 Construction Operation


3.5.1 Weather and seasonal limitations : The work of laying shall not be taken
up during rainy or foggy weather or when the base course is damp or wet, or
during dust storm or when the atmospheric temperature in shade is 150c or less.
3.5.2 Preparation of the base : The base on which bituminous macadam is to be
laid shall be prepared, shaped and conditioned to the specified lines, grades and
cross sections , and a priming coat where needed shall be applied as directed by
the Engineer.

3.5.3 Tack coat : A tack coat as described above shall be applied over the base.

3.5.4 Preparation and transport of mix : Bituminous macadam mix shall be


prepared in a hot mix plant of adequate capacity and capable to yield a mix of
proper and uniform quality with thoroughly coated aggregates . The plant may be
either a weigh batch or volumetric proportioning continuous or drum mix type. The
plant shall have coordinated set of essential units capable of producing uniform
mix within the job mix formula such as :
a) Cold aggregate feed system for providing blended aggregate in the correct
proportion (called cold bin feed arrangement).
b) Rotating cylindrical driver drum fitted with suitable burner capable of heating
the aggregate to the required temperature without any visible un burnt fuel
of carbon residue on the aggregate and to reduce the moisture content of
the aggregate to the specified minimum level.
c) The dryer units shall be fitted with approved set of thermometric instruments
at appropriate places so as to indicate or automatically record/register the
temperature of heated aggregate before adding/mixing the binder.
d) Gradation control: Except in case of drum for plant, other two types of plants
mentioned aboard shall have.
I) A screening unit for accurate sizing of hot aggregate ad feeding the same to
mixing unit by weight or volume control as per the specified job mix formula.
ii) Paddle Mixer unit shall be capable of producing a homogeneous mix with
uniform coating of all particles of the material aggregate with binder.
e) In case of Drum Mix Plant, the cold feed system shall have variable speed
belt conveyors/or other suitable devices for regulating the accurate
proportioning of aggregate into an even feed flow automatically from a
central operating/control cabin.
f) Bitumen control unit: Capable of measuring/metering and spraying
required quantity of bitumen at specified temperature with authomatic
synchronization of bitumen and aggregate feed.
g) Filler system : A time feeder system suitable to receive bagged or bulk
supply of filler material and its incorporation to the mix in the correct
quantity shall be a necessary auxiliary.
h) Dust control : A suitable built in dust control equipments for the dryer to
contain the exhaust of fine dust into atmosophere for environmental control,
wherever so specified by the Engineer.
i) Suitable Auxiliary Bitumen Boiler of adequate capacity with self heating
arrangement and temperature control device. The boiling should be fitted
with temperature indicating instruments.
The temperature of binder at the time of mixing shall be in the range of 1500 to
1650 C and that of the aggregate in the range of 1250 to 1500 C, Provided that the
difference in temperature between the binder and aggregate at no time exceeds
250 C.
Mixing shall be thorough to ensure that a homogenous mixture is obtained in
which all particles of the aggregates are coated uniformly and the discharge
temperature of mix shall be between 1300 to 1600 .
The mixture shall be transported from the mixing plant to the point of use in
suitable tipper vehicles. The vehicle employed for transport shall be clean and be
covered over in transit if so directed by the Engineer.
3.5.5 Spreading : The mix transferred from the tipper to the paver shall be
spread immediately by means of self propelled mechanical paver with suitable
screeds can pebble of spreading, tamping and finishing the mix true to the
specified lines, grades and cross section. The paver finisher shall have the
following essential features :
a) Loading hoppers and suitable distributing mechanism .
b) All drives having hydrostatic drive/control.
c) The machine shall have a hydraulically extendable screed for appropriate
width requirement.
d) The screed shall have tamping and vibrating arrangement for initial
compaction to the layer as it is spread without rutting or otherwise marring
the surface. It shall have adjustable amplitude and infinitely variable
frequency.
e) The paver shall be equipped with necessary control mechanism so as to
ensure that the finished surface is free from surface blemishes.
f) The payer shall be fitted with an electronic sensing device for automatic
leveling and profile control within the specified.
g) The screed shall have the internal heating arrangement.
However, in restricted locations and in narrow widths where the available
plant cannot be operated in the opinion of the Engineer, may per4mit manual
laying of the mix.
The temperature of the mix at the time of laying shall be in the range of 120
to 135 deg Centigrade. In multilayer construction the longitudinal joint in one
layer shall offset that in the layer below by about 150mm. However the joint at
the top most joint shall be at the center line of the pavement.
Longitudinal joint and edges shall be constructed true to the delineating line
parallel to the central line of the road, all joints shall be cut vertical to the full
thickness of the previously laid mix and the surface painted with hot bitumen
before placing fresh material.
3.5.6 Rolling : After spreading of the mix, rolling shall be done by 8 to 10 hour
power rollers or other approved equipment. Rolling should start as soon as
possible after the material has been spread. Rolling shall be done with care to
keep from unduly roughening the pavement surface.
Rolling of the longitudinal joints shall be done immediately behind the
paving operation. After this the rolling shall commence at the edges and progress
towards the centre longitudinally except that on super elevated portions it shall
progress from the lower to the upper edge parallel to the central line of the
pavement.
The initial or break down rolling shall be done, with 8 to 12 tonne three
wheel steel roller, as soon as it is possible to roll the mix without cracking the
surface or having the mix pick up on the roller wheels. The second or intermediate
rolling shall follow the break down rolling as closely as possible and be down while
the paving mix is still at a temperature that will result in maximum density. The final
rolling shall be done while material is still workable enough for removal of roller
marks with 8 to 10 tonne tandem roller. All the compaction operations i.e.
Breakdown rolling, intermediate rolling and final rolling can be accomplished by
using a vibratory roller of 8 to 10 forms static weight. During the initial or break
down rolling and final rolling, vibratory system shall be switched off. The joints and
edges shall be rolled with 8 to 10 tonne static roller.
When the roller has passed over the whole area one any high spots it
depressions which become apparent shall be corrected by removing or adding mix
material. The rolling shall then be continued till the entire surface has been rolled
to compaction, there is no crushing of aggregates and all rolled makes have been
eliminated. Each pass of the roller shall uniformly overlap not less than one third
of the track made in the proceeding pass. The roller wheel shall be kept damp if
necessary to avoid bituminous material from sticking to the wheels and being
picked up. In on case shall fuel lubricating oil be used for the purpose nor
excessive water poured on the wheels.
Rolling operations shall be completed in every respect before the
temperature of the mix falls below 800.
Roller (s) shall not stand on newly laid material while there is a risk that it
will be deformed thereby. The edges along and transverse of the bituminous
macadam laid and compacted earlier shall be cut to their full depth so as to
expose fresh surface which shall be painted with a thin surface coat of appropriate
binder before the new mix is placed against it.
3.5.7 Surface Finish and Quality Control of Work :
The surface finish of construction shall conform to the requirements of
specifications of this tender. Control on the quality of materials and works shall be
exercised by the Engineer.
The bituminous macadam shall be covered with either the next pavement
course or wearing course, as the case may be without any delay, if there is to be
any delay, the course shall be covered by a seal coat as per the technical
specifications mentioned in the tender before allowing any traffic over it.
The quoted rate for the work shall be for carrying out all the required operations
including:
a) Making arrangement for traffic except for initial treatment to verge shoulders
and construction of diversions.
b) Preparation of base except for laying of profile corrective course but
including filling of pot holes.
c) Providing all materials to be incorporated in the work including all royalties,
fees, rents where necessary and all leads and lifts.
d) All labour, tools, equipments, plants and incidental to complete the work to
the specification and all leads and lifts.
e) Carrying out the work in part widths if necessary or wherever directed.
f) Rolling operations shall be completed in every respect.

4.0 SEAL COAT


4. 1 Scope

This work shall consist of application of seal coat for sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall (camber).
Seal Coat shall be as specified below :
Premixed seal coat comprising of a thin application of fine aggregate
premixed with bituminous binder.

4.2 Materials
4.2.1 Binder : As per Clause 3.2.1. Shall apply.
The quantity of binder to be utilized, in terms of straight run bitumen shall be 6.8 Kg.
per 10 Square Meter Area for seal coat .
4.2.2 Aggregate for Seal Coat
The aggregate shall be grit and shall consist of clean, hard, durable, uncoated dry
particles and shall be free from dust, soft or flaky materials, organic matter or other
deleterious substances. The aggregate shall pass 2.36 mm sieve and be retained
on 180 mm sieve. The quantity used for premixing shall be 0.06 cubic meter per 10
square meter area.
4.3 Construction Operations
4.3.1 Preparation of Base
The Seal Coat shall be applied immediately after the laying of bituminous course
which is required to be sealed. Before application of seal coat materials, the surface
shall be cleaned free of any dust or other extraneous matters.

4.3.2 Construction of Seal Coat

The Engineers of approved type shall be employed for mixing the aggregates with
the bituminous binder.
The binder shall be heated in boilers of suitable design, to the temperature
appropriate to the grade of bitumen approved by the Engineer, Also the aggregates
shall be dry and suitably heated to a temperature directed by the Engineer before
the same are placed in the mixer. Mixing of binder with aggregates to the specified
proportions shall be continued till the latter are thoroughly coated with the former.
The mix shall be immediately transported from the mixing plant to the point of use
and spread uniformly on the bituminous surface to be sealed.
As soon as sufficient length has been covered with the pre-mixed material, the
surface shall be rolled with 6-9 tonne smooth wheeled power rollers. Rolling shall be
continued till the pre-mixed material completely seals the voids in the bituminous
course and a smooth uniform surface is obtained.

4.3.3. Surface Finish and Quality Control of Work

The surface finish of construction shall conform to the requirements of specifications


of this tender. Control on the quality of materials and works shall be exercised by the
Engineer

CHAPTER IV

QUALITY CONTROL IN ROAD WORKS


1.0 GENERAL

1.1. All materials to be used, all methods adopted and all works performed shall be strictly in
accordance with the requirements of these Specifications. The Contractor shall set up a field
laboratory at locations approved by the Engineer and equip the same with adequate
equipment and personnel in order to carry out all required tests and Quality Control work as
per Specifications and/or as directed by the Engineer. The list of equipment and the facilities
to be provided shall be got approved from the Engineer in advance.

1.2. The Contractor'


s laboratory should be manned by a qualified Materials Engineer/Civil
Engineer assisted by experienced technicians, and the set-up should be got approved by the
Engineer.

1.3. The Contractor shall carry out quality control tests or the materials and work to the
frequency stipulated in subsequent paragraphs. In the absence of clear indications about
method and or frequency of tests for any item, the instructions of the Engineer shall be
followed.

1.4. For satisfying himself about the quality of the materials and work, quality control tests will
also be conducted by the Engineer (by himself, by his Quality Control Units or by any other
agencies deemed fit by him), generally to the frequency set forth herein under. Additional tests
may also be conducted where, in the opinion of the Engineer, need for such test exists.

1.5.. The Contractor shall provide necessary co-operation and assistance in obtaining the
samples for tests and carrying out the field tests as required by the Engineer from time to time.
This may include provision of labour, attendants, assistance in packing and dispatching and
any other assistance considered necessary in connection with the tests.

1.6. For the work of embankment, sub grade and pavement, construction of subsequent layer
of same or other material over the finished layer shall be done after obtaining permission from
the Engineer. Similar permission from the Engineer shall be obtained in respect of all other
items of works prior to proceeding with the next stage of construction.

1.7. The Contractor shall carry out modifications in the procedure of work, if found necessary,
as directed by the Engineer during inspection. Works falling short of quality shall be rectified
/redone by the Contractor at his own cost, and defective work shall also be removed from the
site of works by the Contractor at his own cost.

1.8. The cost of laboratory including services, essential supplies like water, electricity, sanitary
services and their maintenance and cost of all equiprnent, tools, materials, labour and
incidentals to perform tests and other operations of quality control according to the
Specification requirements shall be deemed to be incidental to the work and no extra payment
shall be made for the same. Alternatively, the contractor may choose to test all the required
tests to be done on the samples, during construction and as required by EIC in an
Engg.college/University/Consultancy firm/reputed laboratory. The above shall be approved by
EIC and all the charges shall be borne byThe contractor and shall be deemed to be incidental
to the work and no extra payment shall be made for the same.
1.9. For testing of samples of soils/soil mixes, granular materials, and mixes, bituminous
materials and mixes, aggregates, cores etc., samples in the required quantity and form shall
be supplied to the Engineer by the Contractor at his own cost.

1.10. For cement, bitumen, mild steel, and similar other materials where essential tests are to
be carried out at the manufacturer'
s plants or at laboratories other than the site laboratory, the
cost of samples, sampling, testing and furnishing of test certificates shall be borne by the
Contractor. He shall also furnish the test certificates to the Engineer.

1.11. For testing of cement concrete at site during construction, arrangements for supply of
samples, sampling, testing and supply of test results shall be made by the Contractor as per
the frequency and number of tests specified in the Handbook of Quality Control for
Construction of Roads and Runways (IRO:SP: l1) and relevant IS Codes or relevant clauses of
these Specifications, the cost of which shall be borne by the Contractor.

1.12. The method of sampling and testing of materials shall be as required by the "Handbook
of Quality Control for Construction of Roads and Runways" (IRC :SP : 11), and these MOST
Specifications. Where they are contradicting, the provision in these Specifications shall be
followed. Where they are silent, sound engineering practices shall be adopted. The sampling
and testing procedure to be used shall be as approved by the Engineer and his decision shall
be final and binding on the Contractor.

1.13. The materials for embankment construction shall be got approved from the Engineer.
The responsibility for arranging and obtaining the land for borrowing or exploitation in any
other way shall rest with the Contractor who shall ensure smooth and uninterrupted supply of
materials in the required quantity during the construction period.

Similarly, the supply of aggregates for construction of road pavement shall be from
quarries approved by the Engineer. Responsibility for arranging uninterrupted supply of
materials from the source shall be that of the Contractor.
1.14. Defective Materials

All materials which the Engineer/his representative has determined as not conforming to
the requirements of the Contract shall be rejected whether in place or not; they shall be
removed immediately from the site as directed. Materials, which have been subsequently
corrected, shall not be used in the work unless approval is accorded in writing by the Engineer.
Upon failure of the Contractor to comply with any order of the Engineer/his----representative,
given under this Clause, he Engineer/his representative shall have authority to cause the
removal of rejected material and to deduct the removal cost thereof from any payments due to
the Contractor.

1.15. Imported Materials


At the time of submission of tenders, the Contractor shall furnish a list of
materials/finished products manufactured, produced or fabricated outside India which he
proposes to use in the work. The Contractor shall not be entitled to extension of time for acts
or events occurring outside'India and it shall be the Contractor'
s responsibility to make timely
delivery to the job site of all such materials obtained from outside India.

The materials imported from outside shall conform to the relevant Specifications of
the tender. In case where materials/ finished products are not covered by the Specifications in
the Contract, the details of Specifications proposed to be followed and the testing procedure
as will as laboratories/ establishments where tests are to be carried out shall be specifically
brought out and agreed to in the Contract.

The Contractor shall furnish to the Engineer a certificate of compliance of the tests
carried out. In addition, certified mill test reports clearly identified to the lot of materials shall be
furnished at the Contractor'
s cost.
2.0 CONTROL OF ALIGNMENT, LEVEL AND SURFACE REGULARITY

2.1. General

All works performed shall conform to the lines, grades, cross sections and
dimensions shown on the drawings or as directed by the Engineer, subject to the permitted
tolerances described herein-after.

2.2. Horizontal Alignment

Horizontal alignments shall be reckoned with respect to the centre line of the carriageway as .
The edges of the carriageway as constructed shall be correct within a tolerance of 10 mm
there from. The corresponding tolerance for edges of the roadway and lower layers of
pavement shall be 20 mm.
2.3. Surface Levels .

The levels of the subgrade and different pavement courses as constructed, shall not vary from
those calculated with reference to the longitudinal and cross-profile of the road as directed by
the Engineer beyond the tolerances mentioned in Table -1.

TABLE -1 TOLERANCES IN SURFACE LEVELS

1. Subgrade + 10 mm
- 15 mm

2. Sub base + 10 mm
(a) Flexible Pavement - 15 mm

3. Base Course for Flexible Pavement


(a) Bituminous Course + 6 mm
- 6 mm
(b) Other than bituminous + 10 mm
(i) Machine laid - 10 mm
+ 15 mm
(ii) Manually laid - 15 mm

4. Wearing Course for Flexible Pavement


(a) Machine laid + 6 mm
- 6 mm
(b) Manually laid + 10 mm
- 10 mm
------------------------------------------------------------------------------------------------------------

Provided, however, that the negative tolerance for wearing course shill not be
permitted in conjunction with the positive tolerance for base course, if the thickness of the
formers thereby reduced by more than 6mm for flexible pavements and 5 mm for concrete
pavements.

For checking compliance with the above requirement for sub grade, sub-base and
base courses, measurements of the surface levels shall be taken on a grid of points placed at
6.25 in longitudinally and 3.5 in transversely. For any 10 consecutive measurements taken
longitudinally or transversely, not more than one measurement shall be permitted to exceed
the tolerance as above, this one measurement being - not in excess of 5 mm above the
permitted tolerance.

For checking the compliance with the above requirement for bituminous wearing
courses and concrete pavements, measurements of the surface levels shall betaken on a grid
of points spaced at 6.25 m along the length and at 0.5 in from the edges and at the centre of
the pavement. In any length of pavement, compliance shall be deemed to be met for the final
road surface, only if the tolerance given above is satisfied for any point on the surface

2.4. Surface Regularity of Pavement Courses


The longitudinal profile shall be checked with a 3 metre long straight edge/moving
straight-edge as desired by the Engineer at the middle of each traffic lane along a line parallel
to the centre line of the road.
The maximum permitted number of surface irregularities shall be as per Table -2.

TABLE -2 MAXIMUM PERMITTED NUMBER OF SURFACE IRREGULARITIES

Surfaces of Surfaces of lay-byes, service


carriageways areas and all bituminous base
and paved courses
shoulders

Irregularity 4 mm 7 mm 4 mm 7 mm
Length(m) 300 75 300 75 300 75 300 75

National Highways/
Expressways * 20 9 2 1 40 18 4 2

Roads of lower
category 40 18 4 2 60 27 6 13

* Category of each section of road as described in the Contract.

The maximum allowable difference between the road surface and underside of a 3 meter long
straight-edge when placed parallel with, or at right angles to the centre line of the road at
points decided by the Engineer shall be:

for pavement surface (bituminous and cement concrete) 3 mm


for bituminous base courses 6 mm
for granular sub-base/ base courses 8 mm
for sub-bases under concrete pavements 10 mm

2.5. Rectification

Where the surface regularity of subgrade and the various pavement courses fall
outside the specified tolerances, the Contractor shall be liable to rectify these in the manner
described below and to the satisfacion of the Engineer.
(i) Subgrade : Where the surface is high, it shall be trimmed and suitably compacted.
Where the same is low, the deficiency shall be corrected by scarifying the lower layer
and adding fresh material and recompacting to the required density. The degree of
compaction and the type of material to he used shall conform to the requirements .

(ii) Granular Sub-base : Same as at (i) above, except that the degree of compaction and
the type of material to be used shall conform to the requirements .

(iii) Water Bound Macadam/Wet Mix Macadam Sub-base/Base : Where the surface is
high or low, the top 75 mm shall be scarified, reshaped with added material as
necessary and recompacted to the requirements. This shall also apply to wet mix
macadam.

(iv) Bituminous Constructions : For bituminous construction other than wearing course,
where the surface is low, the deficiency shall be corrected by adding fresh material over
a suitable tack coat if needed and recompacting to specifications. Where the surface is
high, the full depth of the layer shall be removed and replaced with fresh material and
compacted to specifications.
For wearing course, where the surface is high or low, the full depth of the layer shall be
removed and replaced with fresh material and compacted to specifications. In all cases
where the removal and replacement of a bituminous layer is involved, the area treated
shall not be less than 5 m in length and not less than 3.5 m in width.

3.0 QUALITY CONTROL TESTS DURING CONSTRUCTION

3.1. General

The materials supplied and the works carried out by the Contractor shall conform
to the specifications prescribed in the preceding Clauses.

For ensuring the requisite quality of construction, the materials and works shall be
subjected to quality control tests, as described hereinafter. The testing frequencies set forth
are the desirable minimum and the Engineer shall have the full authority to carry out additional
tests as frequently as he may deem necessary, to satisfy himself that the materials and works
comply with the appropriate specifications. However, the number of tests recommended in
Tables -3 and Table-4 may be reduced at the discretion of the Engineer if it is felt that
consistency in the quality of materials can still be maintained with the reduced number of tests.

Test procedures for the various quality control tests are indicated in the respective
Sections of these Specifications or for certain tests within this Section. Where no specific
testing procedure is mentioned, the tests shall be carried out as per the prevalent accepted
engineering practise to the directions of the Engineer.

3.2. Tests on Earthwork for Embankment, Subgrade Construction and Cut


Formation

3.2.1. Borrow material : Grid the borrow area at 25 m c/c (or closer, if the variability is high) to
full depth of proposed working. These pits should be logged and plotted lot proper
identification of suitable sources of material. The following tests on representative samples
shall be carried out:

(a) Sand Content [IS: 2720 (Partt4)]: 2 tests per 3000 cubic metres of soil.
(b) Plasticity Test [IS: 2720 (Part-5)]: Each type to be tested, 2 tests per 30(X) cub. metres of
soil.
(c) Density Test [IS:2720 (Par: 8)]: Each soil type to be tested, 2 tests per 3000 cubic
metres of soil.
(d) Deleterious Content Test [IS:2720 (Part-27)] : As and when required by the Engineer.
(e) Moisture Content Test (IS :2720 (Part-2)1: One test for every 250 cubic metres of soil.
(f) CBR Test on materials to be incorporated in the suhgrade on soaked / unsoaked
samples [IS : 2720 (Part-I6)]: One CBR test for every 3000 cu. m. atleast or closer as and
when required by the Engineer.

3.2.2. Compaction Control : Control shall be exercised on each layer by taking at least one
measurement of density for each 1000 square metres of compacted area, or closer as
required to yield the minimum number of test results for evaluating a day'
s work on statistical
basis. The determination of density shall be in accordance with IS: 2720 (Part 23). Test
locations shall be chosen only through random sampling techniques. Control shall not be
based on the result of any one test but on the mean value of a set of 5-10 density
determinations. The number of tests in one set of measurements shall be 6 (if non-destructive
tests are carried out, the number of tests shall be doubled) as long as it is felt that sufficient
control over borrow material and the method of compaction is being exercised. If considerable
variations are observed between individual density results, the minimum number of tests in
one set of measurement shall be increased to 10. The acceptance criteria shall be .subject to
the condition that the mean density is not less than the specified density plus:
1.65 - 1.65 times the standard deviation.
--------------------------------
(No. of samples)0.5

However, for earthwork in shoulders (earthen) and in the subgrade, at least one
density measurement shall be taken for every 500 square metres for the compacted area
provided further that the number of tests in each set of measurements shall be atleast 10. In
other respects, the control shall be similar to that described earlier.

3.2.3. Cut formation : Tests for the density requirements of cut formation shall be carried out
in accordance with Clause 3.2.2.

3.3. Tests on Sub-bases and Bases (excluding bitumen bound bases)

The tests and their frequencies for the different types of bases and sub-bases
shall be as given in Table -3. The evaluation of density results and acceptance criteria for
compaction control shall be on lines similar to those set out in Clause 3.2.2.

3.3.1. Acceptance criteria : The acceptance criteria for tests on the strength of cement/lime
stabilised soil and distribution of stabiliser content shall be subject to the condition that the
mean value is not less than the specified value plus :
1.65 - 1.65 times the standard deviation.
--------------------------------
(No. of samples) 0.5

TABLE -3. CONTROL TESTS AND THEIR MINIMUM FREQUENCY FOR SUB-BASES AND
BASES (EXCLUDING BITUMEN (SOUND BASES)

SI. Type of Test Frequency (min.)


No. Construction

1 Granular (i) Gradation One test per 200 m3


(ii) Atterberg limits One test per 200 m3
(iii) Moisture content One test per 250m2
prior to compaction
(iv) One test per 500 m3
Density of
(v) compacted layer As required
Deleterious
(vi) constituents As required
C.B.R.

2 Water Bound (i) Aggregate Impact One test per 200 m3 of


Macadam Value, aggregate
(ii) Grading
One test per 100 m3
(iii) Flakiness Index
One test per 200 m3 of
and Elongation Index Aggregate
(iv) Atterberg limits One test per 25 m3 of
of binding material binding material
(v) Atterberg limits of portion One test per 100 cubic
of aggregate passing 425 meter of aggregate
micron sieve

3.4 Tests on Bituminous Constructions

3.4.1. The tests and their minimum frequencies for the different types of bituminous works
shall be as given in Table -4.
3.4.2. Acceptance Criteria : The acceptance criteria for tests on density and Marshall stability
shall be subject to the condition that the mean value is not less than the specified value plus :

1.65 - 1.65 times the standard deviation.


--------------------------------
(No. of samples)0.5

TABLE -4. CONTROL TESTS AND THEIR MINIMUM FREQUENCY FOR BITUMINOUS
WORKS

SI. Type of Test Frequency (min.)


No. Construction

1 Prime Coat / Tack (i) Quality of Binder Two samples per lot to be
Coat subjected to all or some
tests as directed by the
(ii) Binder temperature for Engineer
application
At regular close intervals.
(iii) Rate of spread of Two tests per day
application
2 Seal Coat / Surface (i) Quality of Binder Two samples per lot
Dressing Dressing to be subjected
to all or some tests are
directed by the Engineer
(ii) Aggregate Impact Value One test per 50 m3 of
aggregate
(iii) Flakiness Index and - do
Elongation Index
(iv) Stripping Value of Initially one set of 3
Aggregates representative specimens
for each source of supply.
Subsequently when
warranted by changes in
the quality of aggregates
(v) Water absorption of - do
aggregates
(vi) Grading of aggregates One test per 25 m3 of
aggregate
(vii) Stone polishing value As required
(viii) Temperature of binder at At regular close intervals
application
(ix) Rate of spread of One test per 500 m3 of
3 Open graded (i) materials
Quality of Binder work
Two samples per lot to be
premix Carpet / Mix subjected to all or some
Seal Surfacing tests are directed by the
Engineer
(ii) Aggregate Impact Value
One test per 50 m3 pf
(iii) Flakiness Index and aggregate
Elongation Index of - do
(iv) aggregates
Stripping Value of
Aggregates Same as mentioned
(v) Water absorption of under serial no. 2
aggregates Same as mentioned
(vi) Grading of aggregates under serial no. 2
One test per 25 m3 of
(vii) Stone polishing value aggregate
(viii) Temperature of binder at As required
application At regular close intervals
(ix) Binder Content Two tests per day
(x) Rate of spread of mixed Regular control through
material checks on materials and
layer thickness
4 Bituminous (i) Quality of Binder Two samples per lot to be
Macadam subjected to all or some
tests are directed by the
Engineer
(ii) Aggregate Impact Value One test per 50 m3 of
aggregate
(iii) Flakiness Index and - do
Elongation Index of
(iv) aggregates
Stripping Value of Same as mentioned
Aggregates under serial no. 2
(v) Grading of Aggregates Two tests per day per
plant both on the
individual constituents
and mixed aggregates
(vi) Water absorption of from the dryer
aggregates Same as in Serial No. 2
(vii) Binder content Periodic, Subject to
minimum of two tests per
day per plant

(viii) Control of temperature of At regular close intervals


binder and aggregate for
mixing and of the mix at
the time of laying and
rolling Regular control through
Rate of spread of mater.. checks of layer thickness

CHAPTER V

MISCELLANEOUS WORKS

1.0 PITCHING ON SLOPES

1.1 Description

This work shall consist of covering the slopes of guide banks, training works and
road embankment with stone, boulders or bricks over a layer of granular material
called filter.
1.2 General

The pitching shall be provided as directed and Stone subject to marked


deterioration by water or weather shall not be accepted.

The stone shall be sound, hard, durable and fairly regular in shape. The largest
stones procurable shall be supplied, and in no case shall any fragment weigh less
than 40 Kg unless otherwise permitted by the Engineer. The sizes of spalls shall be
minimum 25 mm and shall be suitable to fill the voids in the pitching.

To drain off the seepage water and to prevent erosion of the base material, one or
more layers of graded materials, commonly known as a filter medium, shall be
provided underneath the pitching. The material for the filter shall consist of sound
gravel, stone or brick ballast and coarse sand.

1.3 Requirement for filter material :

The gradation of the filter material shall satisfy the following requirements :

(i) D18 of Filter 4 to 20 provided than the filter does not


D18 of Base Material contain more than 5 per cent of material
filter than 0.075 mm.

(ii) D16 of Filter 5 or less


D16 of Base Material

(iii) D80 of Filter Material 25


D80 of Base Material

(iv) The grain size curve of the filter should be roughly parallel to that of the base
material.
Notes :-

1. Filter design may not be required if embankment consists of Sand or Soils with liquid limit
greater than 30 which are resistant to surface erosion. In this case, if a layer of materials is
used as bedding for pitching, it shall be well graded and its D80 size shall be at least twice
the maximum void size in pitching.

2. In the foregoing D18 means the size of that sieve which allows 15 per cent by weight of the
filter material to pass through it and similar is the meaning of D80 and D18.

3. If more than one filter layer is required, the same requirement as above shall be followed
for each layer. The finer filter shall be considered as base material for selection of coarser
filter.

4. Where brick bats are used as filter material, normally the grading is not possible and in
such cases, a layer of graded gravel shall be provided below the brick bats.

5. The filter shall be compacted to a firm condition.

6. The thickness of filter is generally of the order of 200 mm to 300 mm. Where filter is
provided in two layers, thickness of each layer shall be 150 mm.

1.3 Construction Operations

Before laying the pitching, the sides of banks shall be trimmed to the required slope and
profiles put up by means of line and pegs at intervals of 3 meters to ensure regular
straight work and an uniform slope throughout. Depressions shall be filled and thoroughly
compacted.
The filter granular material shall be laid over the prepared base and suitably compacted
to the thickness specified on the drawings.

The lowest course of pitching shall be started from the toe wall and built up in courses
upwards. The toe wall shall be in masonry or as directed by EIC conforming to
requirements. In case of dry rubble pitching and shall be in Masonry work in cement
mortar 1: 4 in case of brick pitching.

The stone pitching shall commence in a trench below the toe of the slope. Stone shall be
placed by derrick or by hand to the required length, thickness and depth conforming to
the drawings. Stones shall be set normal to the slope, and placed so that the largest
dimension is perpendicular to the face of the slope, unless such dimension is greater
than the specified thickness of pitching.

The largest stones shall be placed in the bottom courses and for use as headers for
subsequent courses.

When full depth of pitching can be formed with a single stone, the stones shall be laid
breaking joints and all interstices between adjacent stones shall be filled in with spalls
of the proper size and wedged in with hammers to ensure tight packing.

When two or more layers or stones must be laid to obtain the design thickness of
pitching, dry masonry shall be used and stones shall be well bonded.

Where bricks are to be used, the same shall be laid on the prepared base in one or
more layers as specified. When more than one layer is to be adopted, adjacent layers
shall be properly bonded by means of a sufficient number of pin headers, extending
from one layer to the other. The bond used in laying shall be as directed by the
Engineer.
2.0 TURFING WITH GRASS SODS

2.1 Scope :
This work shall consist of furnishing and laying of the live sod of perennial
turf forming grass on embankment slopes, verge (earthen shoulders) or other
locations as directed by the Engineer. Unless otherwise specified, the work shall
be taken up as soon as possible following construction of the embankment,
provided the season is favorable for establishment of the sod.

2.2 Materials :
The sod shall consist of dense, well rooted growth of permanent and
desirable grasses, indigenous to the locality where it is to be used, and shall be
practically free from weeds or other undesirable matter. At the time the sod is cut,
the grass on the sod shall have a length of approximately 50 mm and the sod shall
have been freed of debris.
Thickness of the sod shall be as uniforn as possible, with some 50-80 mm
or so of soil covering the grass roots depending on the nature of the sod, so that
practically all the dense root system of the grasses is retained in the sod strip. The
sods shall be cut in rectangular strips of uniform width, not less than about 250 mm
x 300 mm in size but not so large that it is inconvenient to handle and transport
these without damage. During wet weather, the sod shall be allowed to dry
sufficiently to prevent rearing during handling and during dry weather shall be
watered before lifting to ensure its vitality and prevent the dropping of the soil in
handling.

2.3 Construction Operations

2.3.1 Preparation of the earth bed :


The area to be sodded shall have been previously constructed to the
required slope and cross section. Soil on the area shall be loosened, freed of all
stones larger than 50 mm diameter, sticks, stumps and any undesirable foreign
matter, and brought to a reasonably fine granular texture to a depth of not less
than 25 mm for receiving the sod.
Where required, top soil shall be spread over the slopes. Prior to placing the
top soil the slopes shall be scarified to the required depth as directed. The top soil
shall be spread to a depth which after settlement will provide the required nominal
depth. Spreading shall not be done when the ground is excessively wet.
Following soil preparation and top soiling, fertilizer is incorporated in the soil
by dicing or other means to the required depths.

2.3.2.Placing the sods : The prepared sod bed shall be moistened to the
loosened depth, if not already sufficiently moist, and the sod shall be plowed
therein within approximately 24 hours after the same has been cut. Each sod strip
shall be laid edge to edge and such that the joints caused by abutting ends are
staggered. Every strip, after it is snugly placed against the strips already in position
shall be lightly tamped with suitable wooden or metal tampers so as to eliminate
are pockets and to press it into the underlying soil. On side slopes steeper than
2 to 1 the laying of sods shall be started from bottom upwards.
At the points where water may flow over a sodded area, the upper edges of
the sod strips shall be turned into the soil below the adjacent area and a layer of
earth placed over this followed by its thorough companion.

2.3.3.Staking the sods : Where the side slope is 2 to 1 or steeper and the
distance along the slope is more than meters, the sods shall be staked with pegs
or nails spaced approximately 500 to 1000 along the longitudinal axis of the sod
strips. Stakes shall be driven approximately plump through the sods to so almost
flush with them.
2.3.4 Top dressing : After the sods have been land in position, the surface
shall be cleaned of loose sod, excess sod and other foreign material. Thereafter a
thin layer of top soil shall be scattered over the surface of top dressing and the
area thoroughly moistened by sprinkling with water.
2.4 Watering and maintenance : The sods shall be watered by the contractor for
a period of at least four weeks after laying. Watering shall be so done as to avoid
erosion and prevent damage to sodded areas by wheels of water tanks.
The contractor shall erect necessary warning signs and barriers, repair or
replace sodded areas failing to show uniform growth of grass or damaged by his
operations and shall otherwise maintain the sod at his cost until final acceptance.

3.0 SUPPLYING & LAYING RCC PIPES

3.1 SCOPE

This specification covers the supply and laying of R.C.C. Hume pipes
as may be required. The entire work shall be carried out as per latest
edition of Indian Standards IS: 783 and IS: 458.

3.2 SUPPLY OF PIPES

The contractor shall supply the R.C.C. Hume pipes of various


diameters along with complete fittings required for carrying out the
work. R.C.C. Hume Pipes should conform to class NP3 of IS: 458 as
may by required and should be in good condition. The Contractor
must furnish, on being demanded by the Engineer, manufacturers
certificates and/or test certificates from recognised authorities.

3.3 ALIGNMENT, LEVELS AND GRADE

The work shall be carried out in conformance to the alignment, levels


and grades specified In the drawings. The layout and levels shall be
made by him at his own cost from one reference grid and bench mark
given by the Engineer. He shall give all help in instruments, materials
and men to the Engineer for checking the detailed layout and levels
as and when required. Making of reference layout and level pillars
along the pipeline route and maintaining them upto completion of the
work shall be the responsibility of the Contractor, at his own cost.

3.4 LAYING OF PIPES

3.4.1 General

The laying of R.C.C. Pipes shall conform to IS:783-1985.

3.4.2 Conditions for laying

The conditions for laying of pipes to suit the conditions at site and/or
as per drawings and instruction of the Engineer shall be as classified
below:

3.4.3 Culvert Condition


In this condition the pipe is laid under embankment and may project
wholly or partly above the original ground surface.

3.4.4 Trench Condition


In this conditions the pipe is laid in a trench excavated for the
purpose. The trench shall be refilled with thoroughly tamped earth
after laying and jointing of pipes in approved manner.

3.4.5 Open Condition

In this condition the pipe is laid such that it projects wholly or partly
above original ground surface, there being no super imposed
overburden on the pipe.

3.5 Bedding and Supports

3.5.1 Culvert Condition

In this condition the pipes shall be laid generally as per sector B9 to


B16 of Appendix-B, of IS:783-1985.

3.5.2 Trench Condition

In this condition the pipes shall be laid generally as per Section B1 to


B8 of Appendix - B of IS: 783-1985.

3.5.3 Concrete Cradle Bedding

If specified in the drawing or so instructed by the Engineer, the pipes


shall be laid on Concrete cradles, conforming to section B1 of
Appendix-B of IS: 783-1985 in case of trench condition and
conforming to section B5 of Appendix - B of IS:783-1985 in case of
culvert condition.

3.5.4 Open Condition

In Open conditions the pipe laid shall be supported over rigid


pedestals constructed at intervals not greater than the length of one
individual piece of pipe, as per drawings and instruction of the
Engineer. In no case shall the joint between to pieces of pipe shall lie
at the centre of span between the supports. The pedestals shall be of
reinforced concrete with a properly shaped out top to receive one
third perimeter of the pipe.
3.5.4 Jointing of Pipes

Joints shall be flexible type as per IS: 783-1985. Rubber ring, with
material conforming to type - 1A of IS: 5382-1967 shall be placed on
the spigot with special shape and the spigot is forced into the socket
previously laid. This compresses the rubber ring as it rolls into the
annular space formed between the two surfaces of the spigot and
socket.

3.6 Hydrostatic Testing of Pipes

The pipeline as laid shall be subjected to hydrostatic test as per

clause 15.5 of IS:783-1985.

4.0 PAVER BLOCKS

4.1. Scope Of Work

The scope of work includes manufacturing, supplying and laying of precast paver
blocks. The work includes:

Clearing the site by removing all obstacles such as stones, debris etc. for laying of
paver blocks.

Supplying of paver blocks at site, including handling at both ends.

Laying of paver blocks at site as per requirement in technical specification, within


shortest possible time. The site being existing operating Retail Outlets, care should
be taken to ensure that the operation is not closed. The job of laying may required
to be carried out during night also.

Testing of paver blocks through reputed Govt./Non Govt. Test house and
submission of test results as per requirements in technical specifications. HPCL
reserves the right to carryout tests at random. Cost for such tests to be borne by
party.

The contractor shall guarantee that all material and components designed,
fabricated, supplied and laid by him shall be free from any type of defect due to
faulty material and/or workmanship/erection for a period of One year from the date
of completion of work at individual sites. However, free Maintenance for two years
shall be rendered by the contractor.
4.2 Paver Block Manufacturing Facilities

The Paver Block shall be made in factory with following minimum facilities:

4.2.1 Concrete Block making Machines:


The machine should be capable of producing high quality Paver Blocks by
obtaining high level of compaction by application of hydraulic compaction and
also by high intensity vibration to the moulds. The machine should have
automatic control panel for uniformity in strength.

4.2.2 Concrete Batching & Mixing Plant:


The concrete Mix Design should be followed for each batch of materials. The
concrete ingredient should be mixed in concrete Batching & Mixing plant with
minimum capacity of 30 cum/hour. The plant should equipped with automatic
control panel for maintaining water cement ratio from batch to batch to obtain
concrete of uniform quality and strength. The plant should be equipped with
adequate mechanism for mechanised loading of raw materials into mixer and
conveyor belt for transportation of concrete from mixer to concrete blockmaking
machine to maintain quality of wet cement.

4.2.3 Curing:
The factory should have well designed curing area to ensure adequate curing
of paver blocks.

4.2.4 Laboratory
The factory should have the following:
(i) Compression testing machine of adequate capacity
(ii) Other tools and equipment for testing raw materials and paver blocks.
(iii) (1). Systematic record of test results of various paver blocks
manufactured in the factory
(2) Concrete Mix Design for various grade of concrete used for
making of paver blocks.

4.3. Pavers Block Characteristics


The concrete pavers should have perpendicularities after release from the mould
and the same should be retained until the laying.

The surface should be of anti skid and anti glare type.

The paver should have uniform chamfers to facilitate easy drainage of surface run
off.

The pavers should have uniform interlocking space of 2mm to 3mm to ensure
compacted sand filling after vibration on the paver surface.

The concrete mix design should be followed for each batch of materials separately
and automatic batching plant is to be used to achieve uniformity in strength and
quality. The pavers shall be manufactured in single layer only. Skilled labour
should be employed for laying blocks to ensure line and level of laying, desired
shape of the surface and adequate compaction of the sand in the joints.

The pavers shall be of cement grey colour without any pigment.


The pavers are to be skirted all round with kerbing using solid concrete blocks of
size 100mm X 200mm X 400mm. The kerbing should be embedded for 100mm
depth. The concrete used for kerbing shall be cured properly for 7 days minimum.

4.4 Paver Block Dimensions

Thickness 80mm or 100 mm


Shape Uniregular (Uniform Shape with no
Hollow Or Cracks)
Chamfer 4mm to 6mm along top edges
Colour Natural cement grey colour without use of
any pigment
Dimensional Tolerance (+/-) 2mm for Length & width, (+/-)3 mm
for Height (Thickness)

4.5 Testing of Paver Blocks.

SR.NO * TEST SPECIFICATION


Average Values
(Average Of Minimum Five
Samples/ Site )

1. Compressive Strength Min. 40 N/Sqmm for 80mm thick


OR
Min. 30 N/Sqmm for
60 mm thick

2. Flexural Strength Minimum 4.5 N/Sqmm

3. Abrasion Resistance Maximum 1.5

4. Water Absorption Maximum 5.80 %

5. Minimum Cement Content 380 Kg/CuM

* Sampling and Testing Procedure As Per Enclosed Specifications


4.6 Sampling and Testing procedures for Paver Blocks

4.6.1 Sample size :

INTERNAL - Average of minimum 3 samples per 5000 Blocks


EXTERNAL - Minimum 2 Blocks per 10000 blocks . Average of minimum
8 blocks per site

Sampling: Sampling of Pavours shall be done before testing.

4.6.2. Compressive Strength


Testing for compressive strength shall be undertaken. The average
compressive strength of the blocks tested shall be 40 N/Sqmm.

4.6.3. Abrasion Resistance


Testing for abrasion shall be in accordance with IS 1237 (Specifications for
Cement Concrete Floor Tiles).

4.6.4 Flexural Strength


Testing for flexural shall be in accordance with IS 1237 (Specifications
for Cement Concrete Floor Tiles).

4.6.5. Water Absorption


Testing for water absorption shall be in accordance with IS 2185:1979 :Part 1(
Specifications for Concrete Masonry Units).

4.7 LAYING OF PAVER BLOCKS.

4.7.1 PRIMING
The contactors are required to verify the existing WBM drivway surface.

It will be the responsibility of the Paver block party to ensure that the Manholes/
Pipeline/ Cable trenches / circular drainage system etc. raised to driveway level
using the requisite materials as per instruction of Engg In Charge (EIC) of HPCL.
The areas of potholes /deep depressions at the isolated locations also have to be
filled up before laying the paver blocks. No extra payments will be made for this
purpose. The area of raised manholes shall be included in the measurement of
overall area of paver blocks for the purpose of payment.

It will be the responsibility of the contractors to ensure that undulations on the


paver blocks are eliminated after the traffic is allowed on it. Proper slope for
draining of water needs to be ensured by the contractor. All necessary materials,
tools, tackles are required to be arranged by the contractor.
4.7.2 BEDDING SAND COURSE

The bedding sand shall consist of a clean well graded sand passing through
4.75 mm sieve and suitable to concrete manufacture .The bedding should be from
either a single source or blended to achieve the following grading.
IS SIEVE SIZE % PASSING
9.52 mm 100
4.75 mm 95-100
2.36 mm 80-100
1.18 mm 50-100
600 microns 25-60
300 microns 10-30
150 microns 5-15
75 microns 0-10
____________________________________________________________
__________

Contractor shall be responsible to ensure that single-sized, gap-graded sands or


sands containing an excessive amount of fines or plastic fines are not used. The
sand particles should preferably be sharp not rounded, as sharp sand possess
higher strength and resist the migration of sand from under the block to less
frequently areas. Even though sharp sands are relatively more difficult to compact
than rounded sands, the use of sharp sands is preferred for the more heavily
trafficked driveways. The sand use for bedding shall be free of any deletorious
soluble salts or other contaminants likely to cause efflorescence.
The sand shall be of uniform moisture content and within 4%-8% when spread and
shall be protected against rain when stockpiled prior to spreading. Saturated sand
shall not be used.

The bedding sand shall be spread loose in a uniform layer as per drawing. The
compacted uniform thickness shall be of 50mm and within + 5mm .Thickness
variation shall not be used to correct irregularities in the base course surface.

The spread sand shall be carefully maintained in a loose dry condition and
protected against pre-compaction both prior to and following screening .Any pre-
compacted sand or screeded sand left overnight shall be loosened before further
laying of paving units take place.

Sand shall be slightly screeded in a loose condition to the predetermined depth


only slightly ahead of the laying of the paving unit.

Any depressions in the screeded sand exceeding 5mm shall be loosened, raked
and rescreeded before laying of paving units.
4.7.3 LAYING OF INTERLOCKING PAVING UNITS :

Paving units shall be laid in herringbone laying pattern throughout the pavement.
Once the laying pattern has been established, it shall continue without interruption
over the entire pavement surface. Cutting of blocks, the use of infill concrete or
discontinuities in laying pattern is not be permitted in other than approved
locations.

Paving units shall be placed on the uncompacted screeded sand bed to the
nominated laying pattern, care being taken to maintain the specified bond
throughout the job. The first row shall be located next to an edge restraint.
Specially manufactured edge paving units are permitted or edge units may be cut
using a power saw, a mechanical or hydraulic guillotine, bolster or other approved
cutting machine.

Paving units shall be placed to achieve gaps nominally 2 to 3mm wide between
adjacent paving joints. No joint shall be less than 1.5 mm nor more than 4mm.
Frequent use of string lines shall be used to check alignment. In this regard, the
laying face shall be checked at least every two metres as the face proceeds.
Should the face become out of alignment, it must be corrected prior to initial
compaction and before further laying job is proceeded with.

In each row, all full units shall be laid first. Closure units shall be cut and fitted
subsequently. Such closure units shall consist of not less than 25% of a full unit.

To infill spaces between 25mm and 50mm wide, a concrete having 1:2:4 cement:
sand: coarse aggregate mix and a strength of 45 N/Sqmm shall be used. Within
such mix the nominal aggregate size shall not exceed one third the smallest
dimension of the infill space. For smaller spaces dry packed mortar shall be used.

Except where it is necessary to correct any minor variations occurring in the laying
bond, the paving units shall n ot be hammered into position. Where adjustment of
position is necessary care shall be taken to avoid premature compaction of the
sand bedding.

4.7.4 INITIAL COMPACTION

After laying the paving units, they shall be compacted to achieve consolidation of
the sand bedding and brought to design levels and profiles by not less than two (2)
passes of a suitable plate compactor.

The compactor shall be a high-frequency, low amplitude mechanical flat plate


vibrator having plate area sufficient to cover a minimum of twelve paving units.

Prior to compaction all debris shall be removed from the surface.


Compaction shall proceed as closely as possible following laying and prior to any
traffic. Compaction shall not, however, be attempted within one metre of the laying
face. Compaction shall continue until lipping has been eliminated between
adjoining units. Joints shall then be filled and recompacted as per requiremnents.

All work further than one metre from the laying face shall be left fully compacted at
the completion of each days laying.

Any units that are structurally damaged prior to or during compaction shall be
immediately removed and replaced.

Sufficient plate compactors shall be maintained at the paving site for both bedding
compaction and joint filling.

4.7.5 JOINT FILLING AND FINAL COMPACTION

As soon as practical after compaction and in any case prior to the termination of
work on that day and prior to the acceptance of construction traffic, sand for joint
filling shall be spread over the pavement.

Joint sand shall pass a 2.36 mm (No 8) sieve and shall be free of soluble salts or
contaminants likely to cause efflorescence. The sane shall comply with the
following grading limits:

IS SIEVE SIZE % PASSING

2.36 mm 100
1.18 mm 90-100
600 microns 60-90
300 microns 30-60
150 microns 15-30
75 microns 10-20
__________________________________________________________________
____

The Contractor shall supply a sample of the jointing sand to be used in the contract
prior to delivering any such material to site for incorporation into the works.
Certificates of test results issued by a recognised testing laboratory confirming that
the samples conform to the requirements of this specification shall accompany the
sample.

The jointing sand shall be broomed to fill the joints. Excess sand shall then be
removed from the pavement surface and the jointing sand shall be compacted with
not less than one (1) pass the the plate vibrator and joints refilled with sand to full
depth. This procedure shall be repeated until all joints are completely filled with
sand. No traffic shall be permitted to use the pavement until all joints have been
completely filled with sand and compacted.
Both the sand and paving units shall be dry when sand is spread and broomed into
the joints to prevent premature setting of the sand.

The difference in level (lipping) between adjacent units shall not exceed 3mm with
not more than 1% in any 3m x 3m area exceeding 2mm. Pavements which is
deformed beyond above limits after final compaction, shall be taken out and
reconstructed to the satisfaction of the Engineer.

4.7.6 Edge Restraint


Edge restraints need to be sufficiently robust to withstand override by the
anticipated traffic, to withstand thermal expansion and to prevent loss of the laying
course material from beneath the surface course. The edge restraint should
present a vertical face down to the level of the underside of the laying course.

The surface course should not be vibrated until the edge restraint, together with
any bedding or concrete haunching, has gained sufficient strength. It is essential
that edge restraints are adequately secured.

4.7.7 Laying Patterns.


Details of laying pattern should be specified before commencement of laying.
Typical laying patterns are enclosed.

4.7.8 Sampling of Paver blocks.


1.Method of sampling
Before laying paver blocks, each designated section comprising not more than
50000 blocks, shall be divided into ten approximately equal groups. Three
blocks shall be drawn from each group.

2.Marking and Identification


All samples shall be clearly marked at the time of sampling in such a way that
the designated section of part thereof, and the consignment represented by the
sample, are clearly defined.
The sample shall be dispatched to the approved test laboratory taking
precaution to avoid damage to the paving in transit. Protect the paving from
damage and contamination until they have been tested. The testing shall be
carried as soon as possible, after the sample has been taken. As soon as
practicable after sampling. The samples shall be stored in water at 20
degree C 5 degree C for 24 hours prior to testing.

4.8 Procedure for Testing of Compressive Strength of Paver Blocks.

Reference : BS 6717 Part-I (1993) Specification for Paving Blocks

1 TESTING MACHINE : The testing machines shall be of suitable capacity for


the test and capable of applying the load at the rate specified. It shall
comply, as regards repeatability and accuracy with the requirements of
relevant ISI specs.

2 PROCEDURE : The sample specimens shall be tested in wet condition after


being stored for at least 24 hours, in water maintained at a temperature of 20
degrees C5 degrees C. before the specimens are submerged in water, the
necessary area shall be determined by the method described in Appendix A
.
The plates of the testing machine shall be wiped clean and any loose grit or
other material removed from the contact faces of the specimen. Plywood
nominally 4mm thick, shall be used as packing between the upper and
lower faces of the specimen and the machine plates, and these boards shall
be larger than the specimen by a margin of at least 5mm at all points. Fresh
packing shall be used for each specimen tested. The specimen shall be
placed in the machine with the wearing surface in a horizontal plane and in
such away that the axes of the specimen are aligned with those of the
machine plates. The load shall be applied without shock and increased
continuously at the rate of Approximately 15 N/sqmm per minute until no
greater load can be sustained. The maximum load applied to the specimen
shall be recorded.

CALCULATION OF CORRECTED STRENGTH : The compressive strength of


each block specimen shall be calculated by dividing the maximum load by full
cross section area and multiplying by an appropriate factors.

Thickness And Chamfer Correction Factors


For Compressive Strength
Work Size Thickness in mm Correction Factors
Plain block Chamfered block
60 1.00 1.06
80 1.12 1.18
100 1.18 1.24

COMPRESSIVE STRENGTH CALCULATION : The average corrected


compressive strength for the designated block section shall be calculated.
CHAPTER VI

SAFETY REQUIREMENT FOR CONSTRUCTION WORKS

A GENERAL

11 This specification deals with the subject matter of safety and


protection to be observed in the Civil Construction. This shall be followed
along with all related statutory requirements/obligation including
Governmental byelaws, codes, ordinance of local or central authorities
related to the construction work.

1.2. In case of complicated work like deep excavation, intricate shuttering


and formwork, excavation in loose soil and below water table, stacking of
excavated earth etc., work plan with necessary drawings and documents
have to be prepared by the Contractor and got approved by the Engineer.

1.3 Necessary reference shall be made to the following Indian Standard


Codes on safety requirements for various type of work :

2.0 INDIAN STANDARD

4130 1991 Demolition of Buildings


3764 1992 Excavation Work
4014 (P-II) 1967 Scaffolding, Steel Tubular
3696 (P-I & P-II) Scaffolds and Ladders 1987 to 1991
4138 1977 Working in Compressed Air
7293 1974 Working with Construction Machinery
8989 1978 Erection of Concrete Framed Structures

3.0 EXCAVATIONS

3.1. No excavation or earth work below the foundation level of an


adjoining building shall be taken up unless adequate steps are taken to
prevent damage to the existing structure or fall of any part.
3.2 Every accessible part of an excavation, pit or opening in the ground
into which there is a danger of persons falling shall be suitably
fenced with a barrier upto a height of one metre suitably placed from
the edge of the excavation as far as practicable.
3.3. No material or load shall be placed or stacked near the edge of the
excavation or opening in the ground. The excavated material shall
not be placed within 1.5 m of the trench or half of the depth of the
trench whichever is more.
3.4 Cutting shall be done from top to bottom. No undercutting of sides of
excavation shall be allowed.
3.5 Materials shall not be dumped against existing walls or partition to a
height that may endanger the stability of the walls.
3.6 While withdrawing piled materials like loose earth, crushed stone,
sand, etc. from the stock piles, no over hanging shall be allowed to
be formed in the existing dump.
3.7 No material on any of the sites of work shall be so stacked or placed
as to cause danger or inconvenience to any person or public or any
other agency at work.
4.0 SCAFFOLDING, LADDERS & SHUTTERING

4.1 For all work that cannot be done from the ground level or from part of
any permanent structure or from other available means of support,
soundly constructed scaffoldings of adequate strength shall be used
as a safe means of access to places of work.

4.2 All scaffolding shall be securely supported or suspended and


wherever necessary be properly braced to ensure stability.

4.3 All working platform and stages from which workers are liable to fall
shall be of adequate width depending on the type of work done and
closely boarded and planked.

4.4 Every ladder shall be securely fixed at top and bottom. A ladder more
than 5 m long shall have a prop.

4.5 No portable single ladder shall be over 8 m in length.

4.6 Unfinished scaffolding which is under construction shall be


prominently marked as unsafe and any access points shall be
closed.
4.7. Shuttering

The above remarks shall be applicable for this also. Shuttering,


particularly for slabs, should be treated as a scaffold. Unfinished
shuttering should be marked as dangerous similarly the finished form
work should be adequately supported, care being taken to avoid trap
door effects.
5.0 SAFETY APPLIANCE

5.1 Those engaged in white washing and mixing or stacking of cement


bags or any materials which is injurious to the eyes, shall be
provided with protective goggles.

5.2. The Contractor shall not employ men below the age of 18 and
women on the work of painting with products containing lead in any
form. Whenever men above the age of 18 are employed on the work
of lead painting the following precautions shall be taken :

5.3. All necessary personnel safety equipment such as safety helmets,


safety boots, safety belts, leather gloves for welders, clear glass
safety goggles etc., as considered adequate by the Engineer have to
be kept available for the use of persons employed at the site of work
and maintained in condition suitable for immediate use and
Contractor shall take steps to ensure proper use of equipment by the
workers.

5.4 Sign boards 1 x 1.5 m in size with the following wording shall be
erected at the access to these areas. CONSTRUCTION AREA,
HELMET REQUIRED BEYOND THIS POINT.

5.5 Arrangement for rendering prompt and adequate first aid to the
injured persons shall be maintained at every work site under the
guidance of a medical officer-in-charge of the project. Depending
upon the magnitude of the work the availability of an ambulance at a
very short notice (a telephone call) shall be ensured.

First-aid arrangements commensurate with the degree of hazard and with


the number of workers employed shall be maintained in a readily
accessible place throughout the working hours. At least one experienced
first-air attendant with his distinguishing badge shall be available on each
shift to take care of injured persons. Arrangements shall be made for
calling the medical officer, when such a need may arise. It is
recommended that foreman/assistant foreman/supervisor/permanent
workmen who are normally present at each working phase in each shift are
given adequate training on first-aid methods to avoid employment of a
separate attendant.

6.0 MISCELLANEOUS

6.1 The Contractor shall provide necessary fencing and lights to protect
the public from accident.

6.2 To ensure effective enforcement of the rules and regulations relating


to safety precautions, the arrangements made by the Contractor
shall be open to inspection by the Engineer and Owner.

6.3. All sources of ignition shall be prohibited in areas where flammable


liquids are stored, handled and processed. Suitable warning and NO
SMOKING signs shall be posted in all such places. Receptacles
containing flammable liquids shall be stacked in such a manner as to
permit free passage of air between them.
6.4 All combustible materials shall be continuously removed from such
areas where flammable liquids are stored, handled and processed.
All spills of flammable liquids shall be cleared up immediately.
Containers of flammable liquids shall be tightly capped.

7.0 REPORTING OF ACCIDENT


7.1 All accidents, major or minor must be reported immediately. The
Contractor, will provide first aid to the injured person immediately and
the injured person shall report to the first aid station along with the
INJURED ON WORK form duly filled in quintuplicate and submit to
the Medical Officer of the First Aid Station.
7.2. Serious Injury
In case of serious injury, the following procedure shall be adopted by
the Contractor:

a) Provide First Aid at his own First Aid Station.


b) Take the injured person to the Hospital along with the INJURED
ON WORK form duly filled in.

c) Reporting the accident to the Owner/Engineer by the Contractor.

7.3 Fatal Accident

Fatal accident must be reported immediately to the Engineer/Owner


as well as to the Police.

8.0 PENALTY

Failure to observe the Safety Rules will make the Contractor liable to
penalty by way of suspension of work, fine and termination of
contract.
TYPICAL

INSPECTION & TEST PLAN

(I T P )

SAMPLE FORMAT

FOR

EARTH FILLNG/ MURRUM FILLING/ WBM


STANDARD INSPECTION & TEST PLAN (I T P ) FOR LAND DEVELOPMENT
WORKS:

1.0 GENERAL NOTES:

Inspection and Test Plan(ITP) given herein is indicative only. The


Contractor shall prepare and submit ITP for all activities The provisions
indicated herein for stage wise inspection are minimum and the Engineer-in-
Charge may decide to increase the Hold Point / Witness Point. Contractor
has to prepare ITPs for any of the activities not covered herein, submit the
same to HPCL and obtain their approval.

Contractor to prepare required reporting formats and job procedures for


each activity i.e. Setting out of work, levels at 5x5m grid co-ordinate wise
and as per technical specifications, submission of min. 5 nos. Earth/
Murrum samples meeting tender specifications along with soil lab. test
report, watering, OMC, Rolling , carting away earth etc to HPCL for approval
well in advance prior to commencement of activity. Submission of samples
of WBM components like aggregates, screening and binder meeting
technical specifications along with lab reports to HPCL well in advance to
enable approval by HPCL to commence activity. Any deviation to ITP shall
be subjected to HPCLs written approval. Contractor to carry out 100%
examination of all activities and proper records shall be maintained and
made available to HPCL Officers requirement at any time of inspection
during the contract period.

2.0 LEGEND :

2.1 HP: HOLD POINT

A point which requires inspection/verification and acceptance by HPCL


before any further processing is permitted.
The contractor shall not process the activity/item beyond the Hold Point
without written approval from Engineer-in-Charge.

2.2 W: Witness Point

An Activity which requires witness by HPCL when activity is performed.

2.3 RW : Review of Contractors Documentation

2.4 S : Surveillance Inspection by HPCL

Monitoring of observations to verify whether or not materials/items/services


confirms to specified requirement. Surveillance activities may include audit,
inspection, witness of testing, review of quality documentation & records,
personnel qualifications, etc.

2.5 WC: 100% examination by Contractor.

3.0 The Indicative Inspection and Test Plan(ITP) is as given below:

Sr. ACTIVITY CONTRACTOR HPCL


No.
1.0 EARTH FILLING

1.1 Fixing of co-ordinates with respect to WC HP


HPCL Bench Mark (B.M.) as per HPCL lay
out , Setting out of various Control point &
alignment, grid levels 5mx5m and as per
tender specifications, Co-ordinates wise
survey & recording. The readings will be
taken on same co-ordinates in subsequent
activity. Clearing of vegetation, shrubs etc
and disposal of the same outside premises
and make surface ready for further
activities.

Collection of Earth samples from various WC HP


1.2 borrow areas, soil sample lab analysis,
submission of test reports to HPCL for
approval with all requisite details.

1.3 Excavation as per approved drawings/as WC W


directed by EIC & carting away unusable
earth as per instructions of HPCL within
Plant premises.

1.4 (A) Rolling of virgin soil & testing for WC W


95% max. lab. Dry density achieved in
case of soil only.

(B) In case of soil encountered in WC HP


1.5(A) above, lab results indicating 95%
MDD to be submitted to HPCL prior to
taking up further Earth filling in 300mm
layers.

1.5 (A) EARTH FILLING :


- 300mm layer checking it with WC W
templates/tools at various co-ordinates
& recording.
- Watering the layer, checking the WC W
OMC through Moisture Tester & recording
co-ordinate wise.

(B) COMPACTION :
- Rolling the OMC watered layer
immediately once tested for OMC till 95% WC W
Standard Proctor dry density achieved.

- Testing for compaction to confirm


its 95% Standard Proctor dry density
achieved co-ordinate wise, Recording the WC W
levels co-ordinate wise . (Min. 1 no test per
500 sq. Mtr.)

- Offering Tested layer to HPCL to


inspect & witness to give clearance for
next layer. WC HP

1.6 Final profile of Earth surface to receive WC W/ HP


Murrum/WBM as per Approved
levels/coordinates and Construction
drawing to be prepared by Contractor
based on general civil detail drawing
furnished in this tender duly approved by
HPCL, to be executed as per 1.5 above,
cutting / making of edges for
embankments etc & complete as per EIC
instructions.

2.0 MURRUM FILLING

2.1 Fixing of co-ordinates with respect to WC HP


HPCL B.M. as per HPCL lay out , Setting
out of various Control point & alignment,
grid levels 5mx5m and as per tender
specifications, Co-ordinates wise survey &
recording. The readings will be taken on
same co-ordinates in subsequent activity.
Clearing of vegetation, shrubs etc and
disposal of the same outside premises and
make surface ready for further activities.
.
Collection of Murrum samples from various WC HP
2.2 borrow areas, lab analysis of samples,
submission of test reports to HPCL for
approval with all requisite details.

2.3 Excavation, if any as per approved WC W


drawings and as directed by EIC & carting
away unusable earth as per instructions of
HPCL within Plant premises.

2.4 (A) Rolling of sub grade/ sub base soil WC W


& testing for 95% max. lab. Dry density
achieved in case of soil only.

2.5 (A) MURRUM LAYING :


- 200mm layer checking it with WC W
templates/tools at various co-ordinates
& recording.
- Watering the layer, checking the WC W
OMC through Moisture Tester & recording
co-ordinate wise.

(B) COMPACTION : WC W
- Rolling the OMC watered layer
immediately once tested for OMC till 95%
Standard Proctor dry density achieved.

- Testing for compaction to confirm WC W


its 95% Standard Proctor dry density
achieved co-ordinate wise, Recording the
levels co-ordinate wise . (Min. 1 no test per
500 sq. Mtr.)

- Offering Tested layer to HPCL to WC HP


inspect & witness to give clearance for
next layer.

2.6 Final profile of Murrum surface to


receive WBM/ as per Approved
levels/coordinates and Construction WC W/ HP
drawing to be prepared by Contractor
based on general civil detail drawing
furnished in this tender duly approved by
HPCL, to be executed as per 2.5 above,
cutting / making of edges for
embankments etc & complete as per EIC
instructions.
3.0 WBM LAYING

3.1 Fixing of co-ordinates with respect to WC HP


HPCL B.M. as per HPCL lay out , Setting
out of various Control point & alignment,
grid levels 5mx5m and as per tender
specifications, Co-ordinates wise survey &
recording. The readings will be taken on
same co-ordinates in subsequent activity.
Clearing of vegetation, shrubs etc and
disposal of the same outside premises and
make surface ready for further activities

3.2 Collection of coarse aggregate, screening WC HP


and binder samples from various borrow
areas, lab analysis of samples and
submission of test reports to HPCL for
approval with all requisite details.

3.3 Rolling of sub base/ sub grade to achieve WC HP


95% of maximum dry density (MDD) and
clearance of the same by HPCL.
3.4 WBM Laying 100 mm thk WC W

- Spreading of coarse aggregate with


templates/ edge supports to the
required line and level and as per
technical specifications and
directions of Engineer In Charge
(EIC)
3.5 Rolling of spreaded aggregates to suit WC W
required profile of the surface
3.6 Applications of screening in the voids WC HP
including spreading, brooming and rolling
etc
3.7 Rolling of the WBM surface along with WC W
screening and sprinkling of water including
brooming, sweeping etc
3.8 Application of binder, brooming in as many WC HP
number of layers required to fill the voids
as per technical specifications. Rolling of
the layers to suit profile and as per
required compacted thickness of 100mm.
Rolling, setting, drying, repairing of hungry
spots, correction of surface profile, if any.
3.9 WBM Laying 75 mm thk WC W
- Spreading of coarse aggregate with
templates/ edge supports to the
required line and level and as per
technical specifications and
directions of Engineer In Charge
(EIC)

3.10 Rolling of spreaded aggregates to suit WC W


required profile of the surface
3.11 Applications of screening in the voids WC HP
including spreading, brooming and rolling
etc
3.12 Rolling of the WBM surface along with WC W
screening and sprinkling of water including
brooming, sweeping etc
3.13 Application of binder, brooming in as many WC HP
number of layers required to fill the voids
as per technical specifications. Rolling of
the layers to suit profile and as per
required compacted thickness of 75mm.
Rolling, setting, drying, repairing of hungry
spots, correction of surface profile, if any.

You might also like