You are on page 1of 2

Course Certification Workshop

Period 2017-02
Career Business Engineering
Professor Diana Balboa, MBA, PMP
Type of Evaluation Group Activity N 08 Page 1 of 2

Group Information
First Name Last Name
Member N 01
Member N 02
Member N 03
Member N 04
Member N 05

Instructions
Final Grade Group Activity N 08
The Group Activity N 08 has just 1 block.
Use black or blue pen. Answers that are written in pencil won't be
corrected.
Every correct answer is worth to 10 points
The Group Activity N 08 lasts 20 minutes.
Plan Schedule Management & Define Activities

1. Which of the following is NOT part of the Schedule Management Plan?


a) Level of accuracy
b) Units of measure
c) Control thresholds
d) None of the above

2. All the following come after the Define Activities process EXCEPT:
a) Estimate Activity Durations
b) Sequence Activities
c) Plan Schedule Management
d) Develop Schedule

3. It is an important INPUT in the Define Activities process:


a) Activity attributes.
b) Work packages.
c) Milestones.
d) None of the above.

4. All the following are Tools & Techniques involved in the Define Activities process EXCEPT:
a) Rolling wave planning
b) Inspection
c) Decomposition
d) Expert judgment

5. ______ is/are a form of progressive elaboration planning where the work to be accomplished in the near term is planned
in detail and future work is planned at a higher level.
a) Iterative development
b) Rolling wave planning
c) User stories
d) Progressive planning

6. It is a helpful Tool & Technique for obtaining activities from the work packages
a) Analytical techniques
b) Decomposition
c) Inspection
d) Montecarlo Analysis
Course Certification Workshop
Period 2017-02
Career Business Engineering
Professor Diana Balboa, MBA, PMP
Type of Evaluation Group Activity N 08 Page 2 of 2

7. The Tool & Technique used in Plan Schedule Management process used for choosing strategic options to estimate
and schedule the project.
a) Decomposition
b) Analytical Techniques
c) Meetings
d) Delphi Technique

8. It is an OUTPUT from the Define Activities process where we can find all the significant points or events in a project
a) Work packages
b) Activity list
c) Activity attributes
d) Milestone List

9. You are the Project Manager and your team is going to star with the Define Activities process, they are not sure about
what to do, so you suggest to verify
a) The Project Management Plan
b) The Requirements Management Plan
c) The Schedule Management Plan
d) The Schedule

10. It is included in the Schedule Management Plan


a) Rules of performance
b) Reporting formats
c) Process description
d) All of the above