You are on page 1of 14

Construction of WIPRO IT SEZ Project, Block C, Gopanpally

ANNEXURE-III : DELAY ANALYSIS


Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

Delay in Handing Over SEZ


1 Documents

a Authority Letter All Works 22/Jul/16 24/Sep/16 64

b Form A1 All Works 22/Jul/16 27/Sep/16 67

Delay due to Incessant Abnormal


All Works - Due to Delayed
2 Rains in the month of Aug'16 & 1/Aug/16 30/Sep/16 48
Excavation Works
Sep'16

Concrete, Shuttering &


3 Demonetization Effect Reinforcement Works - 9/Nov/16 31/Dec/16 52
Due to Cash Payment to Labour

Delay in Approval of Samples,


4 Technical Data Sheets and other
Documents

a Paver Blocks Parking Area 17/Nov/16 24/Jan/17 68

ANNEXURE - I
Construction of WIPRO IT SEZ Project, Block C, Gopanpally
ANNEXURE-III : DELAY ANALYSIS
Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

b Precast Kerbs Parking Area & Road 17/Nov/16 3/Mar/17 106

c Shop Drawings of Faade Works Faade Works 22/Dec/16 3/Mar/17 71

d Hume Pipe Make Approval Network Trench 1/Dec/16 28/Dec/16 27

e Methodology of Cable Trench HT Cable Trench 30/Nov/16 2/Jan/17 33

f Milestone Completion Certificate All Works -


18/Jan/17 14/Feb/17 27
MS-5 Due to hindered Cashflow

g Shade Approval of Powder 'Z' type Louvers & ACP Cladding 13/Feb/17 21/Apr/17 67
Coating
Delivery of HT Panels,
h HT Panels - TDS Electrical Works 7/Jan/17 17/Apr/17 100

Delivery of LT Panels,
i LT Panels - TDS Electrical Works 7/Jan/17 8/Mar/17 60

Delivery of Fire Pumps,


j Fire Pumps FPS Works 23/Dec/16 7/Apr/17 105

Delivery of PHE Pumps,


k PHE Pumps PHE Works 23/Dec/16 17/Mar/17 84

SS Railing - Change from side SS Railing Change to Floor mounted


j mounted to Floor Mounted from Side Mounted 21/May/17 11/Jun/17 21

k RO & WTP - Change in Design Delivery of RO & WTP 1/May/17 5/Sep/17 127

ANNEXURE - I
Construction of WIPRO IT SEZ Project, Block C, Gopanpally
ANNEXURE-III : DELAY ANALYSIS
Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

ELECTRICAL LOW SIDE WORKS :


l Changes in Panels due to Revised Delivery of Panels 10/Aug/17 8/Sep/17 29
SLD
Delivery of Granite for Staircase &
m Granite Stone Approval Entrance 1/May/17 28/Sep/17 150

5 Delayed Drawings / Revisions

a Ground Floor Plan Finishing & MEP Works 8/Nov/16 4/Feb/17 88

b First Floor Plan Finishing & MEP Works 14/Nov/16 4/Feb/17 82

c Second Floor Plan Finishing & MEP Works 5/Dec/16 4/Feb/17 61

d Third Floor Plan Finishing & MEP Works 28/Dec/16 4/Feb/17 38

e Elevations Faade Works 16/Nov/16 4/Feb/17 80

f Glazing & Louvre Details Faade Works 16/Nov/16 4/Feb/17 80

g LMR Details Lift Machine Room 21/Nov/16 25/Feb/17 96

h Terrace Chiller & RO Plant Room Terrace Chiller & RO Plant 27/Nov/16 25/Feb/17 90

i Part Plan & Detail at Part First Finishing & MEP Works of
1/Mar/17 14/Mar/17 13
Floor Level First Floor

ANNEXURE - I
Construction of WIPRO IT SEZ Project, Block C, Gopanpally
ANNEXURE-III : DELAY ANALYSIS
Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

j Entrance Canopy Details ACP Cladding Works 16/Nov/16 23/Mar/17 127

k Pump Room Sunshade & Lintel Structural Works of Service Building 16/Nov/16 25/Mar/17 129
Details

l Parking Area Proposed storm Parking Area - Pavers 2/Jan/17 25/Mar/17 82


water drain

m Level of Storm Water drains Storm Water Drains 1/Jan/17 1/Mar/17 59

6 Variation Approvals

a Under plinth works Work executed 28/Dec/16 Awaited 316

Aerofoil Louver material recd. at site


b Aerofoil louvers and execution in progress 20/Apr/17 Awaited 203

Work executed at additional pantry


c Waterproofing areas 16/Mar/17 Awaited 238

d Reinf. mullions Work executed 17/Mar/17 Awaited 237

e SS eye bolts Work executed 21/Apr/17 Awaited 202

f Fire doors & Teak wood door Work executed 20/Apr/17 Awaited 203
frames

g Sewage Trench - STP Work under progress 11/Sep/17 Awaited 59

ANNEXURE - I
Construction of WIPRO IT SEZ Project, Block C, Gopanpally
ANNEXURE-III : DELAY ANALYSIS
Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

h Chiller Room - GI side sheeting Work executed 11/Sep/17 Awaited 59

Variation Order reqd. for processing


i RO & WTP - Change in Design Purchase Order to procure materials 23/Sep/17 Awaited 47

j Negative variation - STP Descoped Works 29/Sep/17 Awaited 41

k Rebar Anchoring & Diamond Work executed 9/Oct/17 Awaited 31


Cutting RCC Road
ELECTRICAL LOW SIDE WORKS :
l Changes in Panels due to Revised Work executed 18/Sep/17 Awaited 52
SLD

m HVAC WORKS : Valves, Air Vents, Work executed 8/Sep/17 Awaited 62


Fire & Smoke Dampers etc

INTERIOR WORKS : Substituition


n of Demountable Partitions in lieu Work executed 28/Jul/17 Awaited 104
of Drywall Partition

Coordination due to delayed NSC


7 All Finishing Dependant Activities 26/Nov/16 23/Mar/17 117
Finalisation
Change in Specifications as per Blockwork, 'Z' Type Louvres,
8 1/Feb/17 10/Apr/17 68
Engineer's Instructions Automatic Sliding Doors

9 All India Transporter Strike Blockwork & Plastering 30/Mar/17 7/Apr/17 8

ANNEXURE - I
Construction of WIPRO IT SEZ Project, Block C, Gopanpally
ANNEXURE-III : DELAY ANALYSIS
Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

Delay in Finalisation of NSC


10 Agencies
Electrical Works, Finishing & Interior
a Electrical Low Side Works Works 26/Nov/16 27/Feb/17 93

b Interior Works Finishing & Interior Works 26/Nov/16 15/Mar/17 109

c HVAC (Hi & Low Side) Works HVAC Works 26/Nov/16 23/Mar/17 117

d PAC Works PAC Works 26/Nov/16 24/May/17 179

Delay in Finalisation of Free Issue


11 Material Agencies

a Diesel Generator DG Works, Substitute Power 24/Sep/16 18/May/17 236

b UPS & Batteries UPS & Batteries 20/Sep/16 23/Feb/17 156

c Chillers Chillers, HVAC Works 28/Sep/16 23/Feb/17 148

d Elevators Elevator Works 29/Sep/16 23/Feb/17 147

Implementation of GST hindered


12 Implementation of GST procurement 1/Jul/17 15/Aug/17 45

Implication of GST on Cashflow Implementation of GST hindered


13 1/Jul/17 29/Jul/17 28
clearance request to WIPRO procurement

ANNEXURE - I
Construction of WIPRO IT SEZ Project, Block C, Gopanpally
ANNEXURE-III : DELAY ANALYSIS
Item of Works which could not be Date of Start of Date of Removal
S.No Nature Of Hindrance executed on account of this Delay in Days
Hindrance of Hindrance
Hindrance

Delay in Receipt of Free Supply


14 Materials

a Diesel Generator DG Works, Power on availability 9/Feb/17 5/Oct/17 238

b DG Sync Panel DG Works, Power on availability 9/Feb/17 Awaited 273

b UPS & Batteries UPS & Batteries 9/Mar/17 25/May/17 77

c Chillers Chillers, HVAC Works 6/Jan/17 18/Apr/17 102

d Elevators Elevator Works 20/Feb/17 24/May/17 93

ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

Procurement of Materials
was affected.
Reinforcement, Ready Mix
Concrete was unable to
procure due to non-issue of
SEZ documents incurring
VAT, Excise Duty & CST

From 21-May-17

From 21-May-17

From 21-May-17

From 21-May-17

From 21-May-17

ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

As per Schedule

As per Schedule

As per Schedule

As per Schedule

From Stipulated Completion


Date :
21-May-17

As per Schedule

Delivery of HT Panel as per


Schedule
Delivery of LT Panel as per
Schedule
Delivery of Fire Pumps as
per Schedule
Delivery of PHE Pumps as
per Schedule

As per MoM

ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

As per Schedule

As per Schedule

As per Schedule

As per Schedule

As per Schedule

As per Schedule

As per Schedule

As per Schedule

As per Schedule

ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

As per Schedule

As per Schedule

As per Schedule

As per Schedule

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

Variation Order Awaited

As per Schedule

Automatic Sliding Door

Delay due to Transporter


Strike, delay added to
Stipulated completion Date :
21.05.17
ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

Delay in Finalisation of NSC

Delay in Finalisation of NSC

Delay in Finalisation of NSC

Delay in Finalisation of NSC

Delay in Finalisation of NSC

Delay in Finalisation of NSC

Delay in Finalisation of NSC

Delay in Finalisation of NSC

ANNEXURE - I
WIPRO IT SEZ Project, Block C, Gopanpally
EXURE-III : DELAY ANALYSIS

Remarks

ANNEXURE - I

You might also like