Concrete barge rehad Ogbotobo Classic Schedule Layout 28-Oct-17 19:16

Activity ID Activity Name Original Start Finish Predecess Total Float Oct 29 Nov 05 Nov 12 Nov 19 Nov 26 Dec 03 Dec 10
Duration SS T T F SS T T F SS T T F SS T T F S S T T F S S T T F S S T T FS

CBRWO_ABNL-1 Concrete barge


ba rehad Ogbotobo 50 28-Oct-17 16-Dec-17 0

CBRWO_ABNL-1.4 Project management


ma 50 28-Oct-17 16-Dec-17 0

A1090 Quality Control 50 28-Oct-17 16-Dec-17 0


A1100 Document Control 50 28-Oct-17 16-Dec-17 0
A1110 Site Cleaning 40 06-Nov-17* 15-Dec-17 1 S
10 30-Oct-17 08-Nov-17 38 08-Nov-17, CBRWO_ABNL-1.2 Mobilization
CBRWO_ABNL-1.2 Mobilization
Mobilizatio
A1054 Procurement of Grouting Materials 3 30-Oct-17* 01-Nov-17 45 Procurement of Grouting Materials
A1055 Procurement for scouring protection of slot area 3 30-Oct-17* 01-Nov-17 45 Procurement for scouring protection of slot area
A1056 Procure Material necessary for safe execution of the j 4 30-Oct-17* 02-Nov-17 44 Procure Material necessary for safe execution of the job
A1080 Mobilisation of personnel and equipment required for th 10 30-Oct-17* 08-Nov-17 1 Mobilisation of personnel and equipment required for the safe execution of
10 09-Nov-17 18-Nov-17 28 18-Nov-17, CBRWO_ABNL-1.1 Structural Integrity
CBRWO_ABNL-1.1 Structural Integrity
A1057 Carry Out Structural Integrity Assessment of the Berge 8 09-Nov-17 16-Nov-17 A1080 28 Carry Out Structural Integrity Assessment of the Berge incl
A1058 Submit Report 1 17-Nov-17 17-Nov-17 A1057 28 Submit Report
A1077 Review and Approval of Report 1 18-Nov-17 18-Nov-17 A1058 28 Review and Approval of Report
2 09-Nov-17 10-Nov-17 1 10-Nov-17, CBRWO_ABNL-1.8 De-Ballasting and Ballasting
CBRWO_ABNL-1.8 De-Ballast
De-Ballasting and Ballasting
A1060 De-ballasting of Concrete Barge in Present location an 2 09-Nov-17 10-Nov-17 A1080 1 De-ballasting of Concrete Barge in Present location and Anchore
10 11-Nov-17 20-Nov-17 26 20-Nov-17, CBRWO_ABNL-1.7 Survey
CBRWO_ABNL-1.7 Survey
A1063 Carry out survey of the underside of the concrete barg 6 11-Nov-17 16-Nov-17 A1060 1 Carry out survey of the underside of the concrete barge Hu
A1065 Produce Bartymetric Survey report 2 17-Nov-17 18-Nov-17 A1063 26 Produce Bartymetric Survey report
A1075 Review and Approval 2 19-Nov-17 20-Nov-17 A1065 26 Review and Approval
7 17-Nov-17 23-Nov-17 23 23-Nov-17, CBRWO_ABNL-1.5 Excavation
CBRWO_ABNL-1.5 Excavation (Dredging)
A1066 Dredge surrounding and under De-ballast barge as pe 6 17-Nov-17 22-Nov-17 A1063 24 Dredge surrounding and under De-ballast barg
A1067 Continuous monitoring of Dreding By survey team 6 17-Nov-17* 22-Nov-17 A1063 1 Continuous monitoring of Dreding By survey te
A1087 Confirm Excavated ( Dredged area is Ready for Grou 1 23-Nov-17 23-Nov-17 A1067 1 Confirm Excavated ( Dredged area is Ready
11 24-Nov-17 04-Dec-17 12 04-Dec-17, CBRWO_A
CBRWO_ABNL-1.6 Grouting
A1069 Prepare and MIx Grout cement 10 24-Nov-17 03-Dec-17 A1087 13 Prepare and MIx Grout c
A1070 Place Grout into bags 10 24-Nov-17 03-Dec-17 A1087 13 Place Grout into bags
A1071 Placement Grout bags into position as per drawing 10 24-Nov-17 03-Dec-17 A1087 1 Placement Grout bags i
A1081 Confirm Grout bag are well position by survey Team 1 04-Dec-17* 04-Dec-17 A1071 1 Confirm Grout bag are
6 05-Dec-17 10-Dec-17 1 10-Dec-17
CBRWO_ABNL-1.9 Placement of Geotextile membrane
A1000 Prepare Geotextile membrane to allow for placement 3 05-Dec-17 07-Dec-17 A1081 1 Prepare Geotex
A1010 Placement of Geotextile membrane 2 08-Dec-17 09-Dec-17 A1000 1 Placement o
A1020 Confirm Geotextile membrane has been placed as per 1 10-Dec-17 10-Dec-17 A1010 1 Confirm G
3 11-Dec-17 13-Dec-17 1 13-D
CBRWO_ABNL-1.10 Ballast Barge
Ba
A1120 Ballast barge on Geotextile membrane 2 11-Dec-17 12-Dec-17 A1020 1 Ballast
A1130 Confirm barge is well positioned by survey team 1 13-Dec-17 13-Dec-17 A1120 1 Con
CBRWO_ABNL-1.3 Demobilization
Demobiliza 3 14-Dec-17 16-Dec-17 0

A1029 Produce Close Out Report 1 14-Dec-17 14-Dec-17 A1130 2 Pr


A1030 Site Restoration 2 14-Dec-17 15-Dec-17 A1130 1 S
A1050 Demobilization from Site 1 16-Dec-17* 16-Dec-17 0